00-002010
Save Our Bays And Canals Association vs.
Tampa Bay Water And Department Of Environmental Protection
Status: Closed
Recommended Order on Monday, July 24, 2000.
Recommended Order on Monday, July 24, 2000.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8SAVE OUR BAYS AND CANALS, )
14INC., )
16)
17Petitioner, )
19)
20vs. )
22)
23TAMPA BAY WATER and )
28DEPARTMENT OF ENVIRONMENTAL )
32PROTECTION, )
34) Case No. 00-2010
38Respondents, )
40)
41and )
43)
44SOUTHWEST FLORIDA WATER )
48MANAGEMENT DISTRICT, )
51)
52Intervenor. )
54______________________________)
55RECOMMENDED ORDER
57Robert E. Meale, Administrative Law Judge of the Division of
67Administrative Hearings, conducted the final hearing in Tampa,
75Florida, on July 7 and 10-12, 2000.
82APPEARANCES
83For Petitioner: Ralf G. Brookes, Attorney
891217 East Cape Coral Parkway
94Suite 107
96Cape Coral, Florida 33904
100For Respondent Tampa Bay Water:
105Donald D. Conn, General Counsel
110Tampa Ba y Water
1142535 Landmark Drive, Suite 211
119Clearwater, Florida 33761
122J. Frazier Carraway
125Salem, Saxon & Nielson, P.A.
130101 East Kennedy Boulevard
134Suite 3200
136Tampa, Florida 33601
139For Respondent Department of Environmental Protection:
145Cynthia K. Christen
148Senior Assistant General Counsel
152Department of Environmental Protection
1563900 Commonwealth Boulevard
159Mail Station 35
162Tallahassee, Flori da 32399-3000
166For Intervenor Southwest Florida Water Management District
173William S. Bilenky
176General Counsel
178Jack R. Pepper, Jr.
182Associate General Counsel
185Southwest Florida Water
188Management District
1902379 Broad Street
193Brooksvill e, Florida 34609-6899
197STATEMENT OF THE ISSUE
201The issue is whether Respondent Department of Environmental
209Protection may issue to Respondent Tampa Bay Water a variance
219from the requirements, in Rules 62-555.520(4)(c) and (d), Florida
228Administrative Code, that an application for a permit to
237construct and operate a drinking water system contain drawings of
247the project with sufficient detail to describe clearly the work
257to be undertaken and complete specifications of the project to
267supplement the drawings.
270PRELIMINARY STATEMENT
272By Final Order Granting Petition for Variance From Rule
28162 -555.520(4)(c) and (d), F.A.C., Respondent Department of
289Environmental Protection issued Respondent Tampa Bay Water a
297variance from the cited rule's requirements for the contents of
307an application for a public drinking water facility construction
316permit.
317By petition dated May 1, 2000, Petitioner challenged the
326issuance of the variance on various grounds. By Request for
336Assignment of Administrative Law Judge and Notice of Preservation
345of Record filed May 11, 2000, Respondent Department of
354Environmental Protection requested that an Administrative Law
361Judge of the Division of Administrative Hearings conduct the
370final hearing and issue a recommended order. In response to the
381Initial Order requesting available dates for the final hearing,
390the parties filed a response on June 5, 2000, offering, as their
402first available dates, July 7 and 10-13, 2000. By Notice of
413Hearing entered June 12, 2000, the Administrative Law Judge set
423the hearing for July 7 and 10-13, 2000.
431By Order entered June 12, 2000, the Administrative Law Judge
441denied a Motion to Consolidate or Hold in Abeyance filed by
452Petitioner on June 8, 2000, and a Motion to Dismiss filed by
464Respondent Tampa Bay Water on May 22, 2000.
472On June 1, 2000, Intervenor filed a Petition for Leave to
483Intervene in Formal Administrative Proceeding. By Order entered
491July 3, 2000, the Administrative Law Judge granted the petition.
501On June 29, 2000, Petitioner filed an amended petition
510challenging the issuance of the variance. By order entered July
5203, 2000, the Administrative Law Judge granted leave to Petitioner
530to file the amended petition that had been filed on June 29,
5422000. At the commencement of the hearing, the Administrative Law
552Judge granted the request of Petitioner to file an amended
562verified petition, which was identical to the amended petition,
571except that it was verified by the president of Petitioner.
581At the hearing, Petitioner called nine witnesses and offered
590into evidence Petitioner Exhibits 1-9 and 11-14. Respondent
598Tampa Bay Water called six witnesses. Respondent Department of
607Environmental Protection called four witnesses. Intervenor
613called one witness. One member of the public testified. The
623parties jointly offered into evidence Joint Exhibits 1-12, 14-16,
63220, and 22-37. All exhibits were admitted except Petitioner
641Exhibits 9 and 11; as for Petitioner Exhibit 12, only the blue,
653checked circled items were admitted. Petitioner proffered the
661exhibits and portion of Exhibit 12 that were not admitted.
671At the end of the hearing, the Administrative Law Judge gave
682the parties nine days, or until Friday, July 21, 2000, within
693which to file proposed recommended orders, so that the
702Administrative Law Judge could issue his recommended order by the
712following Monday, July 24, 2000.
717The court reporter filed the Transcript on July 14, 2000.
727The parties filed their proposed recommended orders on July 21,
7372000. Respondents and Intervenor filed a joint proposed
745recommended order.
747Respondent Tampa Bay Water also filed on July 21, 2000, a
758Motion for the Award of Attorney's Fees and Costs and Memorandum
769of Law.
771FINDINGS OF FACT
774I. Inception of Tampa Bay Water, Consolidated Permit,
782and Other Documentation for the Production of Drinking Water
7911. Respondent Tampa Bay Water (TBW) is a wholesale public
801water supply utility. TBW is governed by a nine-member board of
812directors with one member each from the municipalities of Tampa,
822St. Petersburg, and New Port Richey and two members each from the
834counties of Hillsborough, Pinellas, and Pasco. The purpose of
843TBW is to use group resources to find regional solutions to the
855problems of water supply in the region. Over two million persons
866in the three-county area rely on TBW for their drinking water.
8772. The predecessor of TBW was the West Coast Regional Water
888Supply Authority (WCRWSA), which was created in 1974. The West
898Coast Regional Water Supply Authority was also a wholesale public
908water supply authority. However, the authority operated as a
917cooperative entity, and TBW operates as a regulatory entity.
9263. In 1996, WCRWSA sought to renew its permit from
936Intervenor Southwest Florida Water Management District (SWFWMD)
943to allow continued withdrawals from four of its eleven major
953wellfields. Concerned with the environmental impacts, such as
961drawdowns of the water levels of wetlands, streams, and lakes,
971from the environmental, if not regulatory, overpumping of the
980wellfields, SWFWMD denied the application for the quantities
988requested.
9894. An Administrative Law Judge at the Division of
998Administrative Hearings conducted a hearing and issued a
1006recommended order finding adverse environmental effects from
1013overpumping, but recommending that SWFWMD issue the requested
1021permits subject to certain conditions. Subsequent negotiations
1028resulted in the parties' entering into a series of agreements
1038covering withdrawals from the four wellfields that had been the
1048subject of the administrative hearing and seven more wellfields
1057that were approaching repermitting (11 Wellfields), as well as a
1067series of other matters.
10715. On May 20, 1998, WCRWSA, the three member counties, the
1082three member municipalities, and SWFWMD entered into the Northern
1091Tampa Bay New Water Supply and Ground Water Withdrawal Reduction
1101Agreement (Partnership Agreement).
11046. The Partnership Agreement requires WCRWSA to bring one
1113or more projects online, by December 31, 2002, to produce at
1124least 38 million gallons per day (MGD) and, by December 31, 2007,
1136to produce at least 85 MGD of new water supply. The Partnership
1148Agreement requires SWFWMD to provide WCRWSA with $183 million
1157toward eligible water supply projects.
11627. The Partnership Agreement notes that the then-current
1170Master Water Plan of WCRWSA recognizes that "an aggressive
1179conservation and demand management program is an integral
1187component of a sustainable water supply." (Joint Exhibit 3, p.
119731.) The Partnership Agreement notes that the then-current
1205Master Water Plan states that the conservation program was
1214expected to reduce use by 10 MGD per day by 2000 and 17 MGD by
12292005.
12308. From the effective date of the agreement through
1239December 31, 2002, the Partnership Agreement requires a reduction
1248in pumping of the 11 Wellfields to 158 MGD, based on a rolling
126136-month average. For the next five years, the Partnership
1270Agreement requires a reduction in pumping of the 11 Wellfields to
1281121 MGD, based on an annual average. After that, effective
1291December 31, 2007, the Partnership Agreement requires a reduction
1300in pumping of the 11 Wellfields to 90 MGD, also based on an
1313annual average.
13159. Three weeks after the execution of the Partnership
1324Agreement, WCRWSA was reorganized into TBW in June 1998 through
1334the execution of two documents: an Amended and Restated
1343Interlocal Agreement dated June 10, 1998 (Interlocal Agreement),
1351and a Master Water Supply Contract dated June 10, 1998. TBW
1362assumed WCRWSA's rights and responsibilities under the
1369Partnership Agreement.
137110. The Interlocal Agreement empowers TBW to produce and
1380supply drinking water "in such manner as will give priority to
1391reducing adverse environmental effects of excessive or improper
1399withdrawals of Water from concentrated areas." (Joint Exhibit 1,
1408pp. 20-21.)
141011. The Interlocal Agreement incorporates the phased-in
1417reductions in withdrawals from the 11 Wellfields that are set
1427forth in the Partnership Agreement. The Interlocal Agreement
1435notes that, if the Partnership Agreement provides for extensions
1444of the deadlines, the deadlines contained in the Interlocal
1453Agreement shall likewise be subject to extension.
146012. Applying to the 11 Wellfields, SWFWMD issued TBW a
1470Consolidated Permit, which was issued on December 15, 1998, and
1480became effective on January 1, 1999. Complementing the
1488Partnership Agreement, which reflects SWFWMD's resource-
1494development role, is the Consolidated Permit, which reflects
1502SWFWMD's regulatory role.
150513. The Consolidated Permit incorporates the phased-in
1512reductions of withdrawals, as set forth above, for the 11
1522Wellfields. Although the deadlines for phased-in reductions are
1530conditioned on the funding to be provided by SWFWMD, pursuant to
1541the Partnership Agreement, these deadlines are otherwise
1548unconditional and firm. The Consolidated Permit expressly
1555provides for extensions of deadlines, except the deadlines set
1564for the phased-in reductions of withdrawals from the 11
1573Wellfields.
157414. The Consolidated Permit imposes upon TBW extensive
1582responsibilities regarding environmental monitoring, reporting,
1587and mitigation. These responsibilities extend to groundwater,
1594wetlands, and surface waters, as TBW must, among other things,
1604monitor and report levels in the surficial and Floridan aquifers
1614and potentiometric surfaces in the Floridan aquifer in the
1623vicinity of the 11 Wellfields, as well as in the vicinity of
1635selected wetlands and surface waters. The Consolidated Permit
1643sets specific "regulatory levels" for these resources.
1650II. Present and Future Tampa Bay Water Facilities,
1658Including the Surface Water Treatment Plant
166415. A majority of TBW's production facilit ies consists of
1674the 11 Wellfields. In an effort to supplement these production
1684sources so as to comply with the phased-in reduction deadlines
1694set forth in the Consolidated Permit and other documents, TBW
1704annually adopts a New Water Plan, which describes capital
1713planning for drinking water production facilities.
171916. The June 2000 New Water Plan summarizes the
1728requirements of the Partnership Agreement. The June 2000 New
1737Water Plan notes that TBW reaffirmed its Master Water Plan and
1748New Water Plan projects in April 2000. These projects include
1758the Enhanced Surface Water System, which includes the Tampa Bay
1768Regional Surface Water Treatment Plant (SWTP), Tampa Bay
1776Reservoir Project (Reservoir), and projects obtaining water from
1784the Alafia River, Hillsborough River, and Tampa Bypass Canal.
1793Other projects, besides the Enhanced Surface Water System,
1801include Seawater Desalination (Desal Plant).
180617. The June 2000 New Water Plan states that the Enhanced
1817Surface Water System is eligible for a maximum of $120 million
1828from SWFWMD, pursuant to its funding obligation under the
1837Partnership Agreement.
183918. This case involves the means by which the SWTP will be
1851permitted, and, in consideration of the manner of permitting,
1860this case involves the means by which the SWTP will be designed
1872and constructed. The June 2000 New Water Plan notes that TBW and
1884USFilter Operating Services, Inc. (USFilter) have entered into a
1893contract for the latter to design, build, and operate (DBO) the
1904SWTP (DBO Contract). The June 2000 New Water Plan reports that
1915USFilter is currently constructing an access road to the site.
192519. Among current issues, the June 2000 New Water Plan
1935describes this case, noting that TBW obtained a variance from
1945Respondent Department of Environmental Protection (DEP) allowing
1952a design, build (DB) approach to permitting the SWTP. The June
19632000 Water Plan states that the present challenge "has the
1973potential to delay the completion of the [SWTP] by an estimated
19848 months, subsequently delaying delivery of the initial 22 mgd
1994(dry weather conditions) of new surface water to the regional
2004system until May 2003 and more likely final acceptance of the
2015[SWTP] to September 2003." (Joint Exhibit 5, p. 4.) (The
2025accuracy of this statement is open to debate because SWFWMD
2035granted an environmental resource permit for the SWTP project
2044only on June 27, 2000--before which no significant alteration of
2054the land could have taken place.)
206020. In the meantime, the June 2000 New Water Plan predicts
2071a water supply shortfall of 100,000 to 2 million gallons per day
2084in the South-Central service area of Hillsborough County.
209221. Addressing the SWTP, the June 2000 New Water Plan
2102states that TBW purchased the site in October 1999 and released a
2114Request for Proposals on July 19, 1999. Four pre-qualified DBO
2124teams responded on October 18, 1999.
213022. The June 2000 New Water Plan erroneously states that
2140TBW applied for a public drinking water facility construction
2149permit (Water Treatment Permit) in October 1999. Actually, in
2158September or October, TBW prefiled with the Hillsborough County
2167Health Department (Health Department) its application for a Water
2176Treatment Permit and paid the $7500 filing fee. The purpose of
2187this courtesy filing or prefiling was to allow Health Department
2197representatives to examine the application, including drawings
2204and specifications for the SWTP, and perhaps expedite the
2213approval process, once TBW filed a formal application.
222123. The June 2000 New Water Plan reports that the SWTP will
2233have a peak day, surface water treatment capacity of 60 MGD and
2245will be located on a 433-acre site near U.S. Route 301 and
2257Broadway Avenue in central Hillsborough County. The June 2000
2266New Water Plan states that the SWTP project schedule calls for
2277completion of construction by March 2003 with plant startup and
2287testing in May 2003 and final acceptance testing in September
22972003. The June 2000 New Water Plan estimates that detailed
2307design, site permitting, and construction of the SWTP will cost
2317$84.3 million, and the annual operation and maintenance expenses
2326will be $7.9 million.
233024. As for the Desal Plant, the June 2000 New Water Plan
2342reports that TBW will pursue a design, build, own, operate, and
2353transfer (DBOOT) approach to acquire a plant to produce,
2362initially, 25 MGD and capable of expansion by an additional 10
2373MGD. The June 2000 New Water Plan states that this plant will
2385cost a total of about $96 million in capital expenses and about
2397$19 million annually to operate.
2402III. Procurement of the Surface Water Treatment Plant
2410A. Design, Build, Operate Contract and Basis of Design
241925. TBW issued a Request for Proposals (RFP) that invited
2429base and alternative proposals for the SWTP. TBW hired Parsons
2439Engineering Sciences to prepare a preliminary design of the SWTP,
2449so as to assist in the preparation of the proposals; although
2460offerors could use alternative designs to the Parsons base
2469design, all proposals had to meet the performance standards
2478specified in the RFP.
248226. After publishing the RFP in papers and technical
2491journals and on the Internet, TBW was able to prequalify five
2502teams of offerors. Four of the five prequalified offerors
2511submitted proposals. TBW received a total of nine proposals
2520because each offeror submitted a base proposal and one
2529alternative proposal, and one offeror submitted a second
2537alternative proposal.
253927. At its January board meeting, TBW selected the USFilter
2549proposal. No party filed a bid protest to the specifications of
2560the RFP or the selection of USFilter and its team. After the
2572selection of USFilter, TBW entered into negotiations with
2580USFilter. During this process, USFilter agreed, at its expense,
2589to add sand to the granulated activated carbon filters to remove
2600fine particles more efficiently, even though it cannot recover
2609the resulting cost of $1.5 million before or after the
2619commencement of operations.
262228. TBW and USFilter entered into the DBO Contract on April
263310, 2000 (DBO Contract). The DBO Contract identifies "Design
2642Requirements" that "are intended to include the basic design
2651principles, concepts and requirements for the [c]onstruction . .
2660but do not include the detailed design or indicate or describe
2671each and every item required for full performance of the physical
2682[c]onstruction . . .." (Joint Exhibit 23, Section 1.2.6.)
269129. The "Design Requirement s" are Schedule 6 to the DBO
2702Contract. Schedule 6 contains all of the individual, technical
2711specifications for the SWTP. Schedule 6 occupies two of the four
2722volumes of large, three-ringed binders forming the DBO Contract.
273130. The DBO Contract identifie s USFilter, Clark, and Camp
2741Dresser & McKee, Inc. (Camp Dresser) as the DBO team for the SWTP
2754project. Camp Dresser is providing design services, Clark is
2763performing the construction, and USFilter is providing the
2771operation and maintenance services for at least 15 years, as well
2782as the financial guarantee, through its corporate parent.
279031. The DBO Contract provides TBW with a fixed construction
2800cost, fixed operating costs, and guaranteed finished water
2808quality. Schedule 8 assures that finished water quality will
2817meet all applicable state and federal drinking water quality
2826standards. Two witnesses at the hearing testified that TBW
2835exacted from USFilter assurances of water quality that, as to
2845certain parameters, will exceed applicable state and federal
2853drinking water quality standards.
285732. The DBO Contract provides TBW with a firm completion
2867date, subject to design modifications requested by TBW and
2876uncontrollable circumstances, such as acts of God, raw water
2885whose quality exceeds the maximum limits, or the delay caused by
2896this case.
289833. A key document in this case is the Basis of Design
2910Report (Basis of Design), which was prepared by the DBO team in
2922April 2000. Acknowledging the phased-in withdrawal limitations
2929and potential for fines for not meeting the deadlines set forth
2940in the Consolidated Permit, the Basis of Design describes the
2950purpose of the DBO process as follows:
2957By utilizing the [DBO] approach for the
2964[SWTP], [TBW] expects to secure substantial
2970benefits . . .[,] includ[ing] costs savings,
2978innovative design, reduced risk of schedule
2984and cost excesses, long-term contracted
2989facility operations, and maintenance
2993efficiencies and guaranties.
2996(Joint Exhibit 8, pp. 1-2.)
300134. The Basis of Design reports that the SWTP will be
3012located on a 100-acre parcel within a 435-acre tract that will
3023also accommodate facilities for groundwater treatment and storage
3031of the treated groundwater, treated surface water from the SWTP,
3041and treated saline water from the Desal Plant.
304935. The Basis of Design identifies t he sources of raw water
3061for the SWTF as the Tampa Bypass Canal, Hillsborough River, and
3072Alafia River. Once online, the reservoir will help normalize
3081quantities of available raw water throughout the dry season.
309036. The Basis of Design describes the main treatment
3099process as pretreatment, including pH adjustment with sulfuric
3107acid or caustic soda, powdered activated car feed, and ferric
3117sulfate coagulant addition; coagulation, flocculation, and
3123sedimentation using a high-rate ballasted sedimentation process
3130known by its tradename as ACTIFLO; ozonoation for primary
3139disinfection, taste and odor control, and partial conversion of
3148dissolved organic carbon to an assimilable or biodegradable form;
3157biologically active filtration for turbidity reduction, taste and
3165odor control; reduction of biodegradable organic carbon; and
3173post-treatment, including secondary disinfection using
3178chloramines. The finished water will then be pumped into tanks
3188for storage and blending before release into the distribution
3197facilities.
31983 7. Distinguishing the DB process from the typical design,
3208bid, build (DBB) process, the Basis of Design states:
3217a very significant amount of process studies
3224and pre-engineering was performed by the
3230Project Team in support of its [DBO
3237p]roposal. This work included a set of
3244drawings covering all disciplines and
3249developed to the 25 to 30 percent completion
3257stage at a minimum with some drawings
3264developed to a greater degree. This stage of
3272drawing development is significantly beyond
3277the sketches and diagrams usually provided in
3284Basis of Design or Preliminary Design
3290Reports. For this [Basis of Design,] the
3298referenced drawings are attached and should
3304be examined when reviewing this [Basis of
3311Design]. As such, a relatively small number
3318of figures are contained within this [Basis
3325of Design].
3327(Joint Exhibit 8, pp. 1-4.)
333238. The Basis of Design notes that the Project Team
3342conducted "pilot-scale" studies of the chosen treatment processes
3350using Lake Manatee raw water. The purpose of these studies was
3361to validate the selected treatment processes, provide water
3369quality data, and establish appropriate operating criteria, such
3377as coagulant dosages.
338039. The Basis of Design addresses raw water quality issues.
3390One table sets out values for 30 different water quality
3400parameters for each of the three raw water sources. The Basis of
3412Design discloses expected water quality data for 11 water quality
3422parameters.
342340. Of particular interest are total nitrogen and total
3432phosphorus because, as noted in the Basis of Design, the algal
3443life-cycle increases dissolved organic carbon and nutrient
3450concentrations in reservoir water, and the "severity of this
3459problem is impossible to predict." (Joint Exhibit 8, pp. 2-4.)
3469The expected water quality values for total nitrogen and total
3479phosphorus, respectively, are, on average, 0.8 and 0.55 mg/L and,
3489at maximum, 1.6 and 2.1 mg/L.
349541. Each of the three surface waters approaches the average
3505values, but none approaches the maximum values, for total
3514nitrogen. The same is true for total phosphorus for the Tampa
3525Bypass Canal and Hillsborough River. However, for the Alafia
3534River, total phosphorus is 2.09 mg/L, so the raw water from the
3546Alafia River may present a substantial treatment challenge, as it
3556exceeds even the maximum expected value for total phosphorus.
356542. An error in Table 2-4 in reporting the maximum and
3576average values of manganese (either the maximum value should be
35860.02 mg/L or the average value should be 0.001 mg/L) and the
3598omission of a turbidity parameter expressed in NTUs precludes
3607analysis of these water quality parameters. However, the other
3616expected parameters appear to reflect the actual water quality of
3626these three surface waters.
363043. Section 4 of the Basis of Design describes the
3640facilities and design criteria for the SWTP. This section begins
3650with site grading, roadways, yardpiping, and stormwater
3657management and extends to detailed discussions of the
3665pretreatment and treatment processes, including the ACTIFLO,
3672ozone contactor, and biologically active filtration.
3678B . Urgency of New Means of Producing Drinking Water
368844. The SWTP is the hub of a network of production,
3699storage, transmission, and distribution facilities that TBW plans
3707to bring online in order to meet the requirements and deadlines
3718set forth in the Consolidated Permit and other documents. The
3728urgency for bringing this component of these new facilities
3737online as soon as possible is due to environmental reasons, as
3748well as the financial and legal reasons set forth above.
375845. Overpumping of existing wellfields has drawn down water
3767levels in surface waters and wetlands, to the detriment of the
3778overall level of biodiversity supported by these natural
3786resources. Some lakes have been down 10 years, and a few have
3798been down 40 or 50 years. During the recent drought, the City of
3811Tampa, which obtains water from the Hillsborough River, lacked
3820adequate volumes of surface water from which to produce
3829sufficient finished water to meet the demand of its customers.
383946. Not surprisingly, these supply problems are ac companied
3848by record withdrawals from the 11 Wellfields. Withdrawals in May
3858and June of this year were the highest monthly withdrawals on
3869record--208 MGD and 175 MGD, respectively. If the drought
3878continues and TBW continues to meet the demands of its customers,
3889TBW's withdrawals from the 11 Wellfields will exceed the
3898permitted 158 MGD, on a rolling 36-month average, by April 2001.
390947. Wellfield overpumping has stressed the groundwaters.
3916Although surface waters respond to substantial rains in as little
3926as a day or two, groundwater takes significantly longer to
3936respond. The surficial water table is as much as 20 feet below
3948ground level, and the Floridan Aquifer is even deeper. The
3958surficial aquifer does not begin to respond to substantial rains
3968for one week, and the Floridan Aquifer begins to respond in two
3980to four weeks.
398348. The condition of the surficial and Floridan aquifers
3992affects the Hillsborough River and Tampa Bypass Canal, which are
4002significantly recharged by the surficial and, sometimes, the
4010Floridan Aquifer. The Floridan Aquifer is especially important
4018to the Tampa Bypass Canal, whose rock bed has been breached.
4029During dry periods, the two aquifers are the primary sources of
4040recharge for these two surface waters. The Alafia River is more
4051confined, but gets water from the Floridan Aquifer through two
4061springs at the head of the river.
406849. TBW has already made substantial gains through
4076conservation and has met the goal of nearly 10 MGD for 2000.
4088Over the next 20 years, maximum potential gains are expected to
4099be no more than 74-94 MGD. Conservation will continue to play an
4111important role in securing adequate drinking water supplies in
4120the Tampa Bay area, but conservation, even in conjunction with
4130reclaimed water, will not suffice, especially when future
4138population growth in the area is considered.
414550. TBW also manages wellfield production efficiently.
4152Under its Optimized Regulatory Operations Plan, TBW collects and
4161analyzes wellfield data to determine which wellfield to tap,
4170notwithstanding specific limits set by wellfield, in order to
4179minimize environmental damage. The consumptive use permits
4186issued to TBW for the surface waters that will provide raw water
4198to the SWTP restrict the amounts and timing of the removals.
4209Additionally, a hydrobiological monitoring program requires the
4216collection and analysis of data to safeguard against adverse
4225effects in the rivers and, downstream, in the estuary.
423451. The contractual deadline for delivery of the SWTP is
4244September 30, 2002. The timeframe for bringing online the SWTP
4254necessarily relies on acceptance testing in the wet season,
4263during which 60-65 percent of the annual rain occurs. The wet
4274season extends from mid June to the end of September. Acceptance
4285testing of the SWTP is imperative toward the end of this period
4297because this is when the water quality of the surface waters
4308bears the highest levels of the contaminants. Thus, if delays
4318postpone beyond the wet season the point at which acceptance
4328testing can take place, the postponement will effectively be
4337until the next wet season and, possibly, the end of the next wet
4350season.
4351IV. Permitting the Design, Build Process
4357for the Surface Water Treatment Plant
4363A. General
436552. The DB process envisioned by TBW would essentially
4374break into phases the process by which TBW would obtain the
4385necessary Public Drinking Water Treatment Construction Permit
4392(Permit). The Permit initially would be based on "30 percent
4402plans," which reflect about a 30 percent level of effort toward
4413the overall design work or 30 percent completion of all of the
4425design work (30 Percent Plans).
443053. Generally, 30 Percent Plans mark the end of the
4440preliminary design phase. Plans reflecting 30, 60 and 90 percent
4450levels of effort are customary in DBB processes, as these are the
4462stages at which owners typically review design work. In 30
4472Percent Plans, some items are designed to 100 percent and other
4483items are not designed at all. However, 30 Percent Plans provide
4494reasonable assurance that the designed system is constructable.
450254. In essence, the Permit initially would be a conceptual
4512permit for the entire SWTP coupled with a construction permit for
4523those components for which the design is already complete on the
453430 Percent Plans. Construction of each remaining component of
4543the SWTP would await subsequent permit modifications authorizing
4551construction of that component. As noted above, the May 18,
45612000, cover letter anticipates another interim permit, or permit
4570modification, covering specific components, and then the final
4578permit, or permit modification, covering the entire SWTP.
458655. The DEP district office in Orlando has substantial
4595experience with permitting DB water treatment projects. From
46031996-98, the DEP Orlando office has permitted four such projects
4613for the Orlando Utilities Commission and one such project for the
4624City of Kissimmee. One of the Orlando Utilities Commission
4633projects was to construct a completely new water treatment plant.
464356. Based on the experience of the DEP Orlando office, DB
4654permitting, when based initially on 30 Percent Plans, shortens
4663and simplifies the permitting process. DB permitting eliminates,
4671or at least postpones, the presentation of elements, such as
4681electrical and HVAC, that are irrelevant to the permitting
4690process; the elimination of elements irrelevant to permitting
4698from the initial designs helps the regulator find the elements
4708that are relevant to the permitting process. Also, the
4717experience of the DEP Orlando office is that the DB process
4728results in no more permit modifications for change orders than
4738are typical of a conventional DBB process.
474557. The DB-approval process used by the DEP Orlando office
4755is modeled after the DEP-permitting process for wastewater
4763treatment plants. DEP rules allow DB permitting of these plants,
4773which are similar in construction to water treatment plants. In
4783fact, DEP is preparing to adopt rules to allow DB permitting of
4795water treatment plants.
479858. Because the DEP Orlando office did not issue variances
4808from the rules that arguably preclude DB construction of water
4818treatment plants, there is no precedent for the issuance of the
4829variance sought in this case. However, the experience of the DEP
4840Orlando office is that applicants do not present basic design
4850changes after the initial submission, and DB permitting does not
4860mean that regulatory objectives are sacrificed to the expediency
4869sought by the applicant.
4873B. The Present Case
487759. On April 11, 2000, Camp Dresser, on behalf of TBW,
4888filed with the Health Department an Application for a Public
4898Drinking Water Facility Construction Permit. The April 2000
4906drawings that accompanied the April 11, 2000, application are
4915described above. The cover letter to the Health Department notes
4925that, "upon conceptual approval of the project, individual
4933components will be permitted through permit modifications based
4941on submittals of complete drawings and specifications for each
4950component."
495160. In this case, the availability of the Basis of Design
4962meant that the 30 Percent Plans reflected more than a 30 percent
4974level of effort or completion of the five-stage process of
4984pretreatment, pH adjustment, ozone contactors, filtration, and
4991storage in tanks. The engineer had already sized the facilities
5001and defined all of the processes and elements of the SWTP. The
5013April 2000 drawings, as supplemented by the Basis of Design,
5023therefore presented a relatively detailed description of the
5031scope, elements, and processes of the project.
503861. On May 18, 2000, Camp Dresser submitted to the Health
5049Department more advanced drawings, which are dated May 18, 2000.
5059The cover letter explains that the drawings are a complete set of
5071Phase I drawings and specifications. The letter states that Camp
5081Dresser intends to file complete drawings and specifications in
5090three phases. Phase I, which is completed with the May 2000
5101drawings, consists of sitework, high rate flocculation and
5109sedimentation, and ozone contact tanks. Phase II consists of
5118biologically active granulated active carbon filters, clearwell,
5125and gravity thickeners. Phase III consists of the remainder of
5135the project.
513762. As of July 3, 2000, prior to the final hearing, the
5149design for the SWTP had reached the 60 percent level of effort or
5162completion.
516363. Although the SWTP described in the DBO Contract, Basis
5173of Design, and May drawings is a relatively large, complex
5183facility, it does not employ unproven technology. The
5191standardization of design and regulatory review is facilitated by
5200the use of the so-called Ten States' Standards, which are
5210standards commonly used by the permitting authorities of numerous
5219states, including Florida, to determine the capabilities of
5227specified treatment processes in achieving specific water quality
5235levels.
523664. Although the ACTIFLO technology is relatively new, it
5245has been in use for at least five years. A pretreatment
5256sedimentation barrier that reduces treatment time and thus
5264tankage volume requirements, ACTIFLO is in use in a water
5274treatment plant with a capacity of 60 MGD in Canada, which TBW's
5286selection team members visited. ACTIFLO presently is being
5294incorporated into a surface water treatment plant in Melbourne,
5303Florida, where it must treat the nutrient-rich water of Lake
5313Washington and the St. Johns River. The City of Tampa is adding
5325ACTIFLO basins to its facilities. Also significant is the fact
5335that ACTIFLO easily passed the pilot test on Lake Manatee. At
5346present, 25 facilities using ACTIFLO are under design or
5355construction in North America.
535965. As is consistent with the theory, the DBO process for
5370designing, building, and operating the SWTP has demanded greater
5379cooperation among the three entities that operate relatively
5387independently in the DBB process. Pursuant to their obligations
5396under the DBO Contract, Camp Dresser, Clark, and USFilter have
5406coordinated, and likely will continue to coordinate, their
5414efforts closely from design and construction, up to operation, to
5424save time and money from the traditional DBB process, in which
5435the design phase, construction phase, and operation phase are
5444relatively independent of each other.
5449C. The Variance
545266. In general, DEP has the authority to issue public
5462drinking water treatment construction permits. The successful
5469applicant obtains one permit--for construction and operation.
5476There are no conceptual permits or separate operating permits.
548567. In Hillsborough County, as well as 10 other counties,
5495DEP has delegated its responsibilities for issuing public
5503drinking water treatment construction permits. In Hillsborough
5510County, DEP has delegated this responsibility by an interagency
5519agreement to the Health Department. Applying DEP rules to
5528determine whether to issue a public drinking water construction
5537permit, the Health Department defers to DEP for the issuance of
5548variances from DEP rules.
555268. In typical permitting cases, the Health Department u ses
5562its own staff in processing the application and reaching a
5572permitting decision. In a large case, such as this, the Health
5583Department's lone professional engineer, who was hired in
5591September 1999, can obtain considerable assistance from
5598professional engineers within the Tampa Bay area and professional
5607engineers employed by DEP.
561169. Perceiving a possible incompatibility between the DB
5619process and the rules from which the variance is sought in this
5631case, TBW initially filed a request for a variance with the
5642Health Department. However, the Health Department declined to
5650issue a variance to DEP rules and informed TBW that it had to
5663file its request with DEP. Thus, on January 10, 2000, TBW filed
5675a petition for a variance with DEP.
568270. On March 28, 2000, DEP issued a final order, pursuant
5693to Section 120.542, Florida Statutes, granting the requested
5701variance from Rule 62-555.520(4)(c) and (d), Florida
5708Administrative Code (Variance). The Variance finds that the
5716purpose of the underlying statutes would be met "because no
5726component of the project would be permitted or constructed
5735without review by the permitting authority of the complete plans
5745and specifications for that portion of the project." The
5754Variance finds that the DB approach will protect the public
5764health, safety, and welfare in providing safe drinking water
5773without exacerbating possible negative environmental impacts from
5780the overuse of groundwater.
578471. The Variance relieves TBW of the necessity of complying
5794with two subsections of the rule governing the contents of
5804applications for a public drinking water construction permit.
5812Rule 62-555.520(4)(c) and (d), Florida Administrative Code,
5819provides:
5820The permit application form sets forth the
5827minimum information which is to be supplied
5834to the Department or the Approved County
5841Health Department. Additional information
5845may be required by the Department to clarify
5853information submitted in the permit
5858application or to demonstrate that the
5864proposed level of treatment will effectively
5870treat the contaminants present in the raw
5877water. The information required by the
5883application is as follows:
5887* * *
5890(c) Prints of drawings of the work project
5898which contain sufficient detail to clearly
5904apprise the Department of the work to be
5912undertaken. All prints shall be minimum of
591918 x 24 inches and a maximum size of 36 x 42
5931inches. The scale of details contained shall
5938be satisfactory for microfilm reproduction.
5943(Reduced size photographic reproduction of
5948drawings for submission may be authorized.)
5954(d) Complete specifications of the project
5960necessary to supplement the prints submitted.
596672. The issuance of the Variance by DEP has met with
5977approval, albeit cautious approval, by the Health Department.
5985One Health Department witness was an Engineer III, who is 19-year
5996employee of the Health Department and supervisor of four
6005Environmental Specialists charged with reviewing construction
6011plans for drinking water plants. He testified that he agreed
6021with DEP's final order granting the Variance. The Engineer III
6031and the other Health Department witness, its professional
6039engineer, testified that the issuance of the initial permit would
6049not influence the Health Department in deciding whether to issue
6059permit modifications, except to ensure compatibility.
606573. Allo wing TBW not to comply with Rule 62 -555.520(4)(c)
6076and (d), Florida Administrative Code, the Variance provides that
6085the initial permit shall not authorize the construction of any
6095component of the SWTP; each component may be constructed only
6105after the submission of complete plans and specifications for
6114that component and the issuance of a permit modification based on
6125those complete plans and specifications. The Variance also
6133provides that the permitting authority shall publish a notice of
6143intent to issue a permit modification "if the permitting
6152authority believes that the modifications are of a controversial
6161nature, or that there is heightened public awareness of the
6171project."
6172V. Save Our Bays and Canals, Inc.
6179A. The Verified Amended Petition
618474. On May 1, 2000, Petitioner filed a petition challenging
6194the Variance. On June 29, 2000, Petitioner filed an amended
6204petition challenging the Variance, and the Administrative Law
6212Judge granted Petitioner leave to file an amended petition on
6222July 3, 2000. At the start of the hearing, on July 7, 2000,
6235Petitioner filed a verified amended petition, which was identical
6244to the amended petition, except that, on July 6, 2000,
6254Petitioner's president had verified the pleading "to the best of
6264[his] knowledge, information and belief."
626975. The verified amended petition states that Petitioner
6277has over 400 members. The verified amended petition alleges that
6287a substantial number of Petitioner's members will consume the
6296finished water produced by the SWTP and will use the surface
6307waters supplying the SWTP for recreation.
631376. The verified amended petition states that the purpose
6322of Petitioner is to save the bays, canals, and waterways of the
6334Tampa Bay area and to ensure safe drinking water for its members
6346and residents of the Tampa Bay area.
635377. The verified amended petition states that the Variance
6362affects Petitioner because it would allow the issuance of the
6372Permit and construction of initial phases of the SWTP prior to
6383submittal, review, and approval of complete plans for the next
6393and subsequent phases. The verified amended petition alleges
6401that Petitioner incorporated to pool its resources to review
6410applications, so as to ensure safe drinking water. The verified
6420amended petition states that submittal and review of a complete
6430set of drawings and specifications is necessary prior to
6439construction of the SWTP to ensure the ability of the facility to
6451comply with state drinking water standards. The verified amended
6460petition states that review of all individual components of the
6470SWTP is necessary to assure the protection of the public health,
6481safety, and welfare and the compliance with all applicable state
6491and federal laws.
649478. Addressing specifically the 30 Percent Plans, the
6502verified amended petition objects to the absence of a list of
6513items to be included in the 30 Percent Plans. The verified
6524amended petition alleges that this piecemeal approach to
6532permitting will require Petitioner to request administrative
6539hearings on each phase of permitting. The verified amended
6548petition states that the Variance may have adverse environmental
6557and safety impacts that cannot be evaluated fully without a
6567submittal and review of the complete drawings and specifications.
657679. The verified amended petition states that the DBO
6585approach is "self-created." The verified amended petition
6592objects to the failure of TBW to obtain the Variance before
6603issuing the RFP and instead using the DBO Contract as a basis for
6616claiming hardship so as to qualify for the Variance.
662580. The verified amended petiti on states that the number of
6636variances issued for similar 30 Percent Plans threatens to create
6646a situation in which the variance subsumes the rule requiring
6656complete drawings and specifications. The verified amended
6663petition objects to this form of unwritten policy that has not
6674been published as a rule.
667981. The verified amended petition states that the phased
6688permitting of the SWTP may create permitting momentum that
6697discourages a rigorous application of the rules at a later stage.
670882. The verified ame nded petition states that the request
6718for a variance is improper because it is for a variance from
6730statutes, not rules. The verified amended petition states that
6739Section 403.861(10), Florida Statutes, requires DEP or Health
6747Department approval of "complete plans and specifications prior
6755to the installation, operation, alteration, or extension of any
6764public water system." The verified amended petition states that
"6773installation" means construction.
677683. The verified amended petition states that Section
6784403.861(5), Florida Statutes, prohibits the issuance of a public
6793drinking water treatment construction permit "until the water
6801system has been determined to have the required capabilities
6810. . .." The verified amended petition states that the assurances
6821of USFilter are insufficient to satisfy this requirement.
682984. The verified amended petition states that Section
6837120.542, Florida Statutes, which authorizes the variance
6844procedure used in this case, does not authorize variances for
6854compliance with federal law. The verified amended petition
6862states that TBW must obtain a federal variance in order to obtain
6874the Variance.
687685. The verified amended petition states that the 30
6885Percent Plans omit information required for permitting, such as
6894the listing of a certified operator, monitoring and recordkeeping
6903programs, and various financial elements, such as the posting of
6913a bond and creation of reserves to demonstrate financial
6922soundness.
692386. The verified amended petition states that TBW's
6931substantial hardship is based on contract deadlines that are
6940entirely self-created and, thus, insufficient to warrant a
6948variance. The verified amended petition notes that the
6956environmental damage cited as a basis for granting the Variance
"6966was caused by years of overpumping by . . . TBW . . .." Also,
6981the verified amended petition states that member governments of
6990TBW continue to approve new development, which increases the
6999demand for drinking water, because TBW and its member governments
7009have failed to exploit fully the potential for conservation and
7019reclaimed water. Similarly, the verified amended petition states
7027that SWFWMD helped create the hardship by renewing the permits
7037for additional withdrawals from the 11 Wellfields.
704487. The verified amended petition states that the DBO
7053process will not necessarily save time and money and is not a
7065recognized exception to the general requirement that an applicant
7074must submit complete drawings and specifications prior to
7082permitting. The verified amended petition states that 30 Percent
7091Plans do not provide sufficient detail to know what the
7101contractor is promising to build, and it would be faster to
7112correct any mistakes prior to the start of construction, rather
7122than after the start of construction.
7128B. Standing
713088. Petitioner was an unin corporated association from its
7139formation in early October 1999 through February 3, 2000, when it
7150was incorporated as a Florida not-for-profit corporation.
7157Originally named Save Our Bays and Canals Association, the
7166unincorporated association was formed by members of the Apollo
7175Beach Civic Association who were concerned about the
7183environmental impact upon their bays and canals of intensive
7192utility and industrial land uses in close proximity to their
7202homes. Apollo Beach is an unincorporated area along the
7211southeast shore of Tampa Bay, just south of the mouth of the
7223Alafia River.
722589. The land uses with which the unincorporated association
7234has been concerned in its brief existence include a sulfur plant,
7245the TECO Big Bend plant, a proposed National Gypsum plant, a
7256proposed concrete plant, the proposed Desal Plant, and, now the
7266proposed SWTP. The Apollo Beach area is very close to the
7277proposed site of the Desal Plant, but is about 17 miles south
7289southeast from the proposed site of the SWTP.
729790. Petitioner a nd its members are primarily concerned with
7307the Desal Plant, not the SWTP. However, Petitioner and its
7317members express concern with the SWTP. The concerns are that DB
7328permitting of the SWTP will jeopardize the production of safe
7338drinking water and will result in greater costs to TBW customers,
7349who will eventually bear the financial burden of costly reworking
7359of a hastily designed and constructed project.
736691. Standing analysis is simplified by the elimination of
7375the issue of whether the verification of the amended petition
7385confers standing. The claims of Petitioner in this case do not
7396rise to the level of an attempt to prevent an activity, conduct,
7408or product to be permitted from impairing, polluting, or
7417otherwise injuring the air, water, or other natural resources of
7427the State.
742992. First, finished drinking water is not a natural
7438resource of the State. Although a resource, finished drinking
7447water is not natural. Although of lower water quality, raw water
7458is a natural resource. The potable water leaving the SWTP is a
7470manufactured resource.
747293. Second, even if finished drinking water were a natural
7482resource, the issuance of the Variance does not have the effect
7493of impairing, polluting, or otherwise injuring a natural
7501resource. The Variance excuses compliance with two rules
7509requiring complete drawings and specifications. Even assuming
7516that the SWTP would impair, pollute, or otherwise injure natural
7526resources, the Variance would not have such an effect because the
7537act of granting the Variance is distinct from the act of granting
7549the Permit itself.
755294. Thus, facts regarding the circumstances under which
7560Petitioner's president verified the amended petition are
7567irrelevant for the purpose of determining standing.
757495. Petitioner's standing is a function of the
7582characteristics of the corporation and its members.
758996. At the corporate level, the articles of incorporation
7598state that the "specific and primary purposes for which this
7608corporation is formed are to operate for the public education and
7619advancement of the water quality of Tampa Bay, its tributaries,
7629its estuaries and its canals and for other charitable purposes,
7639by the distribution of its funds for such purposes."
764897. There is some indication in the record of an attempt,
7659after filing the petition commencing this proceeding, to amend
7668the articles of incorporation to state, among Petitioner's
7676purposes, the protection of drinking water. The record does not
7686contain the written articles of incorporation, as amended, or
7695amended articles of incorporation after February 3, 2000.
7703However, for the purpose of this recommended order, the
7712Administrative Law Judge shall assume that such an amendment was
7722made at some point after the filing of the petition and before
7734the final hearing.
773798. At the membership le vel, the water to be produced by
7749the SWTP will be distributed primarily to customers in Pasco and
7760Pinellas counties, St. Petersburg, and the Northwest Service Area
7769of Hillsborough County, not to Apollo Beach, which is in southern
7780Hillsborough County. Nearly all of Petitioner's members reside
7788in Apollo Beach or other nearby communities, which also will not
7799be served by the SWTP.
780499. Although an insubstantial number of Petitioner's
7811members will consume finished water from the SWTP in their homes,
7822a substantial number will consume finished water from the SWTP at
7833their places of work or schools and where they shop or dine out.
7846Drinking water is ubiquitous, and the mixture of functional land
7856uses in Apollo Beach is not, so it is highly probable that
7868members of Petitioner will travel the three-county area in
7877connection with their employment, education, and recreation.
7884100. Close analysis of the characteristics of Petitioner
7892and its members reveals no basis for finding standing to
7902challenge the Variance.
7905101. Nothing in the record suggests that Petitioner or any
7915of its members have devoted themselves to the arcane task of
7926resisting a perceived trend of state and local agencies to issue
7937series of permits in response to DB proposals--or, more
7946colorfully, to engage in "piecemeal permitting."
7952102. About the only interest that Petitioner can
7960legitimately claim in DB permitting is that multiple points of
7970entry, at each permit and permit modification, will result in
7980additional expense. If Petitioner has standing to contest even
7989the permitting of the SWTP, Petitioner must petition each time
7999for an administrative hearing, conduct discovery, and participate
8007in the final hearing. However, this seems, at most, like a
8018tenuous interest, which suffers also from the speculation that
8027later stages of the DB permitting process will continue to
8037present new issues not raised in the challenge of the Permit
8048initially approved.
8050103. Turning to the members themselves, their consumption
8058of drinking water produced by the SWTP is no basis for standing
8070either because the attenuated relationship between the Variance,
8078which excuses compliance with two rules concerning the contents
8087of applications, and the safety of drinking water or the
8097additional costs that could arise from hasty designing,
8105constructing, or permitting. Although it is conceivable that a
8114record could have been made that the DB permitting proposed in
8125this case would likely result in incomplete, incompetent
8133permitting review, so as to jeopardize the public health if the
8144permit were to issue, the record in this case does not support
8156such a contention. To the contrary, the record establishes that
8166the DB permitting is at least as likely as DBB permitting to
8178provide the regulatory oversight necessary to assure the design
8187and construction of a successful public drinking water treatment
8196plant
8197104. Lacking a substantial nexus in the record between the
8207DB permitting authorized by the Variance and the quality of the
8218drinking water that, if the Health Department issues the Permit,
8228would likely be produced by the SWTP and likelihood of success of
8240the overall construction project, the members of Petitioner
8248likewise lack standing to challenge the Variance.
8255VI. Ultimate Findings of Fact
8260105. Petitioner and its members lack standing to challenge
8269the Variance.
8271106. TBW faces a substantial hardship if not given the
8281Variance. The legal and financial consequences of a failure to
8291meet the phased-in withdrawal reductions are real and
8299substantial. The environmental damage caused by overpumping the
830711 Wellfields underscores the urgency of developing alternative
8315sources of raw water for production into finished drinking water.
8325107. The rule from which TBW seeks the Variance is derived
8336from the statute discussed in the Conclusions of Law. The
8346underlying purpose of this statute is the protection of the
8356public health, safety, and welfare. The Variance serves the
8365underlying purposes in two respects. First, the 30 Percent Plans
8375contain sufficient detail to allow permitting to proceed without
8384jeopardizing the objective of the rules to ensure that the
8394USFilter team designs and constructs a water treatment plant that
8404is in full compliance with all federal and state law. Second,
8415the Variance provides that the USFilter team shall construct no
8425component of the SWTP until it has been permitted, either
8435initially or by a permit modification.
8441VII. Petitioner's Liability for Attorneys' Fees and Costs
8449108. Petitioner has a Technical Committee on which
8457Petitioner relies for examination of technical aspects of matters
8466that are of general concern to Petitioner. This committee
8475obtained a copy of the Variance and, after examination and
8485discussion, developed a position in opposition to DEP's stated
8494intent to grant the Variance.
8499109. The Chair of Petitioner 's Technical Committee, who has
8509a bachelor of science degree in chemistry and is an industrial
8520hygienist, drafted a letter reflecting the opinion of the
8529committee in opposition to the Variance. Petitioner's attorney
8537then converted this letter into the petition that commenced this
8547proceeding.
8548110. At all times, the Board of Directors of Petitioner
8558approved the actions of the Technical Committee and Petitioner's
8567attorney, including the filing of the petition.
8574111. When Petitioner's president verified the amended
8581petition, he reasonably relied on the advice of counsel
8590concerning the substance of the assertions, and the advice of
8600counsel was based on the work of the Technical Committee.
8610Petitioner's president also reasonably relied on the work of the
8620Technical Committee when he verified the amended petition.
8628112. Although DB permitting has been available for the
8637design and construction of wastewater treatment plants for an
8646undetermined period of time, DB permitting for the design and
8656construction of public drinking water plants is a new concept.
8666The concept is so new that the DEP Orlando office mistakenly
8677issued at least 2 DB permits for public drinking water plants
8688without requiring the applicant to obtain a variance from the two
8699rules that prevent DB permitting for such facilities. The
8708concept is so new that the key Health Department employees have
8719expressed concern over personnel demands from this new means of
8729permitting, although they have also expressed at least lukewarm
8738support for the Variance.
874211 3. The record portrays the employees of the Health
8752Department as hard-working and competent, but over-burdened. The
8760DB permitting obviously places significant responsibilities upon
8767the Health Department, especially as it familiarizes itself with
8776DP permitting. Although the availability of professional support
8784from other sources, including DEP, ultimately resolves this
8792issue, the situation of the Health Department also is relevant in
8803assessing Petitioner's liability for attorneys' fees and costs.
8811114. T wo or three aspects of the drawings were deficient,
8822according to Petitioner's professional engineer, whose testimony
8829has been admitted despite the unreasonably restricted opportunity
8837presented for cross-examination by his contractually driven
8844refusal to identify past clients or jobs. Although none of these
8855items seems likely to jeopardize a successful construction
8863project, these were design points on which well-informed
8871professionals could reasonably differ.
8875115. Although the issue of "improper purpose" presents a
8884closer question than the substantive issues discussed above,
8892there is inadequate subjective or objective evidence in the
8901record supporting TBW's claim for attorneys' fees and costs on
8911this ground. Ultimately, the novelty of DB permitting of
8920drinking water treatment plants precludes a finding of improper
8929purpose. All available facts drive this determination, and, at
8938this point in time, the relative uniqueness of DB permitting of
8949drinking water treatment plants to DEP, the Health Department,
8958and Petitioner and its members provides the necessary margin to
8968preclude a finding of improper purpose.
8974CONCLUSIONS OF LAW
8977116. The Division of Administrative Hearings has
8984jurisdiction over the subject matter. Section 120.57(1), Florida
8992Statutes. (All references to Sections are to Florida Statutes.
9001All references to Rules are to the Florida Administrative Code.)
9011117. Seeking the Variance, the burden of proof is on TBW.
9022Department of Transportation v. J. W. C. Company, Inc. , 396 So.
90332d 778 (Fla. 1st DCA 1981). See also Section 120.542(2).
9043118. Section 120.542(1) recognizes that "[s]trict
9049application of uniformly applicable rule requirements can lead to
9058unreasonable, unfair, and unintended results in particular
9065instances." Consequently, Section 120.542(2) provides that
9071variances and waiver shall be granted when the applicant
"9080demonstrates that the purpose of the underlying statute will be
9090or has been achieved by other means by the person and when
9102application of a rule would create a substantial hardship or
9112would violate principles of fairness."
9117119. TBW chose not to proceed under the fairness prong.
9127Section 120.542(2) defines a "substantial hardship" as a
"9135demonstrated economic, technological, legal, or other type of
9143hardship to the person requesting the variance or waiver."
9152120. As noted above, TBW proved the substantial hardship.
9161The need for the SWTP is urgent--environmentally, legally, and
9170financially.
9171121. Petitioner did not rely on Section 403.810(5) in its
9181proposed recommended order. (An examination of that subsection
9189suggests that it may have been miscited.) The statute underlying
9199Rule 62 -555.520(4)(c) and (d) is Section 403.861(10), which
9208empowers DEP to:
9211Require department or county health
9216department review and approval of complete
9222plans and specifications prior to the
9228installation, operation, alteration, or
9232extension of any public water system.
9238122. "Installation" is construction. The Variance does not
9246permit construction of any component of the SWTP prior to its
9257permitting.
9258123. In general, the purpose of Section 403.861 is to
9268assure the public health, safety, and welfare. As noted above,
9278the Variance serves the underlying purpose of the statute.
9287124. Section 403.412(5) addresses "any administrative,
9293licensing, or other proceedings authorized by law for the
9302protection of the air, water, or other natural resources of the
9313state from pollution, impairment, or destruction . . .." In such
9324proceedings, Section 403.412(5) provides that a citizen of
9332Florida "shall have standing to intervene as a party on the
9343filing of a verified pleading asserting that the activity,
9352conduct, or product to be licensed or permitted has or will have
9364the effect of impairing, polluting, or otherwise injuring the
9373air, water, or other natural resources of the state."
9382125. As noted above, Petitioner may not obtain standing
9391under Section 403.412(5).
9394126. Also as noted above, Petitioner and its members are
9404not otherwise persons whose substantial interests are affected by
9413the issuance of the Variance. Petitioner lacks standing.
9421127. In Agrico Chemical Company v. Department of
9429Environmental Regulation , 406 So. 2d 478, 482 (Fla. 2d DCA 1981),
9440rev. denied , 415 So. 2d 1359 (Fla. 1982), the court stated:
"9451before one can be considered to have a substantial interest in
9462the outcome of the proceeding he must show 1) that he will suffer
9475injury in fact which is of sufficient immediacy to entitle him to
9487a section 120.57 hearing, and 2) that his substantial injury is
9498of a type or nature which the proceeding is designed to protect."
9510128. As noted above, neither Petitioner nor its members
9519have made the required showing under either of the two prongs set
9531forth in Agrico .
9535129. Section 120.569(2)(e) provides that the signing of all
9544pleadings constitutes a "certification that the person has read
9553the pleading, motion, or other paper and that, based upon
9563reasonably inquiry, it is not interposed for any improper
9572purpose, such as to harass or to cause unnecessary delay, or for
9584frivolous purpose or needless increase in the cost of
9593litigation." A violation of these requirement requires the
9601imposition of attorneys' fees and costs.
9607130. Section 120.595(1)(c) requires the Administrative Law
9614Judge to
9616determine whether any party participated in
9622the proceeding for an improper purpose as
9629defined by this subsection and
9634s.120.569(2)(e). In making such
9638determination, the administrative law judge
9643shall consider whether the nonprevailing
9648adverse party has participated in two or more
9656other such proceedings involving the same
9662prevailing party and the same project as an
9670adverse party and in which such two or more
9679proceedings the nonprevailing adverse party
9684did not establish either the factual or legal
9692merits of its position, and shall consider
9699whether the factual or legal position
9705asserted in the instant proceeding would have
9712been cognizable in the previous proceedings.
9718In such event, it shall be rebuttably
9725presumed that the nonprevailing adverse party
9731participated in the pending proceeding for an
9738improper purpose.
9740131. The determination of a violation of Section
9748120.595(1)(c) requires that the recommended order determine the
9756amount of attorneys' fees and costs.
9762132. The inquiry concerning improper purpose is objective,
9770not subjective. In other words, "if reasonably clear legal
9779justification can be shown for the filing of the paper in
9790question, improper purpose cannot be found and sanctions are
9799inappropriate." Friends of Nassau County, Inc. v. Nassau County ,
9808752 So. 2d 42, 50 (Fla. 1st DCA 2000)(construing predecessor to
9819Section 120.569(2)(e)).
9821133. For the reasons noted above, TBW has failed to prove
9832any improper purpose by Petitioner associated with the filing of
9842any pleading or participation in this case.
9849RECOMMENDATION
9850It is
9852RECOMMENDED that the Department of Environmental Protect ion
9860enter a final order granting the Variance and denying the request
9871of Tampa Bay Water for attorneys' fees and costs.
9880DONE AND ENTERED this 24th day of July, 2000, in
9890Tallahassee, Leon County, Florida.
9894___________________________________
9895ROBERT E. MEALE
9898Administrative Law Judge
9901Division of Administrative Hearings
9905The DeSoto Building
99081230 Apalachee Parkway
9911Tallahassee, Florida 32399-3060
9914(850) 488-9675 SUNCOM 278-9675
9918Fax Filing (850) 921-6847
9922www.doah.state.fl.us
9923Filed with the Clerk of the
9929Division of Administrative Hearings
9933this 24th day of July, 2000.
9939COPIES FURNISHED:
9941Kathy C. Carter, Agency Clerk
9946Office of General Counsel
9950Department of Environmental
9953Protection
99543900 Commonwealth Boulevard
9957Mail Station 35
9960Tallahassee, Florida 32399-3000
9963Teri L. Donaldson, General Counsel
9968Department of Environmental
9971Protection
99723900 Commonwealth Boulevard
9975Mail Station 35
9978Tallahassee, Florida 32399-3000
9981Ralf G. Brookes, Attorney
99851217 East Cape Coral Parkway
9990Suite 107
9992Cape Coral, Florida 33904
9996Donald D. Conn, General Counsel
10001Tampa Bay Water
100042535 Landmark Drive, Suite 211
10009Clearwater, Florida 33761
10012J. Frazier Carraway
10015Thomas A. Lash
10018Salem, Saxon & Nielson, P.A.
10023101 East Kennedy Boulevard
10027Suite 3200
10029Tampa, Florida 33601
10032Cynthia K. Christen
10035Senior Assistant General Counsel
10039Department of Environmental
10042Protection
100433900 Commonwealth Boulevard
10046Mail Station 35
10049Tallahassee, Florida 32399-3000
10052William S. Bilenky
10055General Counsel
10057Jack R. Pepper, Jr.
10061Associate General Counsel
10064Southwest Florida Water
10067Management District
100692379 Broad Street
10072Brooksville, Florida 34609-6899
10075NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
10081All parties have the right to submit written exceptions within 15
10092days from the date of this recommended order. Any exceptions to
10103this recommended order must be filed with the agency that will
10114issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/24/2000
- Proceedings: Recommended Order issued. CASE CLOSED. Hearing held July 7 and 10-12, 2000.
- PDF:
- Date: 07/21/2000
- Proceedings: Tampa Bay Water`s Motion for the Award of Attorney`s Fees and Costs and Memorandum of Law filed.
- PDF:
- Date: 07/21/2000
- Proceedings: Joint Proposed Recommended Order of Tampa Bay Water, Department of Environmental Protection and Southwest Florida Management District filed.
- Date: 07/19/2000
- Proceedings: Transcript (Volume 1 through 9 Condensed Version) filed.
- Date: 07/14/2000
- Proceedings: Transcript (Volumes 1 through 9) filed.
- Date: 07/07/2000
- Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
- PDF:
- Date: 07/07/2000
- Proceedings: Petitioners Unilateral Pre-Hearing Stipulation (filed via facsimile)
- PDF:
- Date: 07/06/2000
- Proceedings: Verified Amended Petition for Formal Administrative Hearing Under Florida Statute 120.57 (filed via facsimile)
- PDF:
- Date: 07/06/2000
- Proceedings: Motion to Verify Amended Petition for Standing Under F.S. 403.41295) (filed via facsimile)
- PDF:
- Date: 07/05/2000
- Proceedings: Ltr. to C. Wentworth from T. Lash In re: Judge`s ruling (filed via facsimile)
- PDF:
- Date: 07/03/2000
- Proceedings: Order Granting Petition for Leave to Intervene, Denying Motion to Strike, and Denying Request for Sanctions sent out. (Southwest Florida Water Management District petition to intervene is granted)
- PDF:
- Date: 06/30/2000
- Proceedings: Corrected Certificate of Serviced (Petitioner) (filed via facsimile)
- PDF:
- Date: 06/30/2000
- Proceedings: Motion to Amend Petition and Response to Sanctions (Petitioner) (filed via facsimile)
- PDF:
- Date: 06/29/2000
- Proceedings: Amended Petition for Formal Administrative Hearing Under Florida Statute 120.57 (Petitioner) filed.
- PDF:
- Date: 06/29/2000
- Proceedings: Tampa Bay Water`s Motion to Strike Amended Petition and to Impose Sanctions (filed via facsimile)
- PDF:
- Date: 06/23/2000
- Proceedings: Notice of Continuation of Taking Deposition Duces Tecum-R. Brookes (filed via facsimile).
- PDF:
- Date: 06/22/2000
- Proceedings: Notice of Continuation of Taking Deposition Duces Tecum (filed via facsimile).
- PDF:
- Date: 06/12/2000
- Proceedings: Order sent out. (respondent, Tampa bay water motion to dismiss is denied; the renewed motion for expedited scheduling of prehearing conference is denied; the motion to consolidate or hold in abeyance is denied)
- PDF:
- Date: 06/12/2000
- Proceedings: Notice of Hearing sent out. (hearing set for July 7, July 7 and 10 through 13, 2000; 8:00 a.m.; Tampa, FL)
- PDF:
- Date: 06/09/2000
- Proceedings: Joint Response in Opposition to Petitioner`s Motion to Consolidate or Hold in Abeyance (J. Carraway filed via facsimile) filed.
- PDF:
- Date: 06/02/2000
- Proceedings: Renewed Motion for Expedited Scheduling of Prehearing Conference (D. Conn filed via facsimile) filed.
- PDF:
- Date: 06/01/2000
- Proceedings: Petition for Leave to Intervene in Formal Administrative Proceeding (filed via facsimile).
- Date: 05/22/2000
- Proceedings: Petition for Formal Administrative Hearing under Florida Statutes 120.57 filed.
- PDF:
- Date: 05/22/2000
- Proceedings: (Respondent) Motion to Expedited Consideration w/Exhibits (filed via facsimile).
- Date: 05/17/2000
- Proceedings: Initial Order issued.
Case Information
- Judge:
- ROBERT E. MEALE
- Date Filed:
- 05/11/2000
- Date Assignment:
- 05/17/2000
- Last Docket Entry:
- 08/18/2000
- Location:
- Tampa, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
Related Florida Statute(s) (6):
Related Florida Rule(s) (2):
- 62 -555.520
- 62-555.520