00-002010 Save Our Bays And Canals Association vs. Tampa Bay Water And Department Of Environmental Protection
 Status: Closed
Recommended Order on Monday, July 24, 2000.


View Dockets  
Summary: Tampa Bay Water is entitled to Variance; construction of surface water treatment plant responds to urgent environmental, financial, and legal factors. Protestor did not file for improper purpose.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8SAVE OUR BAYS AND CANALS, )

14INC., )

16)

17Petitioner, )

19)

20vs. )

22)

23TAMPA BAY WATER and )

28DEPARTMENT OF ENVIRONMENTAL )

32PROTECTION, )

34) Case No. 00-2010

38Respondents, )

40)

41and )

43)

44SOUTHWEST FLORIDA WATER )

48MANAGEMENT DISTRICT, )

51)

52Intervenor. )

54______________________________)

55RECOMMENDED ORDER

57Robert E. Meale, Administrative Law Judge of the Division of

67Administrative Hearings, conducted the final hearing in Tampa,

75Florida, on July 7 and 10-12, 2000.

82APPEARANCES

83For Petitioner: Ralf G. Brookes, Attorney

891217 East Cape Coral Parkway

94Suite 107

96Cape Coral, Florida 33904

100For Respondent Tampa Bay Water:

105Donald D. Conn, General Counsel

110Tampa Ba y Water

1142535 Landmark Drive, Suite 211

119Clearwater, Florida 33761

122J. Frazier Carraway

125Salem, Saxon & Nielson, P.A.

130101 East Kennedy Boulevard

134Suite 3200

136Tampa, Florida 33601

139For Respondent Department of Environmental Protection:

145Cynthia K. Christen

148Senior Assistant General Counsel

152Department of Environmental Protection

1563900 Commonwealth Boulevard

159Mail Station 35

162Tallahassee, Flori da 32399-3000

166For Intervenor Southwest Florida Water Management District

173William S. Bilenky

176General Counsel

178Jack R. Pepper, Jr.

182Associate General Counsel

185Southwest Florida Water

188Management District

1902379 Broad Street

193Brooksvill e, Florida 34609-6899

197STATEMENT OF THE ISSUE

201The issue is whether Respondent Department of Environmental

209Protection may issue to Respondent Tampa Bay Water a variance

219from the requirements, in Rules 62-555.520(4)(c) and (d), Florida

228Administrative Code, that an application for a permit to

237construct and operate a drinking water system contain drawings of

247the project with sufficient detail to describe clearly the work

257to be undertaken and complete specifications of the project to

267supplement the drawings.

270PRELIMINARY STATEMENT

272By Final Order Granting Petition for Variance From Rule

28162 -555.520(4)(c) and (d), F.A.C., Respondent Department of

289Environmental Protection issued Respondent Tampa Bay Water a

297variance from the cited rule's requirements for the contents of

307an application for a public drinking water facility construction

316permit.

317By petition dated May 1, 2000, Petitioner challenged the

326issuance of the variance on various grounds. By Request for

336Assignment of Administrative Law Judge and Notice of Preservation

345of Record filed May 11, 2000, Respondent Department of

354Environmental Protection requested that an Administrative Law

361Judge of the Division of Administrative Hearings conduct the

370final hearing and issue a recommended order. In response to the

381Initial Order requesting available dates for the final hearing,

390the parties filed a response on June 5, 2000, offering, as their

402first available dates, July 7 and 10-13, 2000. By Notice of

413Hearing entered June 12, 2000, the Administrative Law Judge set

423the hearing for July 7 and 10-13, 2000.

431By Order entered June 12, 2000, the Administrative Law Judge

441denied a Motion to Consolidate or Hold in Abeyance filed by

452Petitioner on June 8, 2000, and a Motion to Dismiss filed by

464Respondent Tampa Bay Water on May 22, 2000.

472On June 1, 2000, Intervenor filed a Petition for Leave to

483Intervene in Formal Administrative Proceeding. By Order entered

491July 3, 2000, the Administrative Law Judge granted the petition.

501On June 29, 2000, Petitioner filed an amended petition

510challenging the issuance of the variance. By order entered July

5203, 2000, the Administrative Law Judge granted leave to Petitioner

530to file the amended petition that had been filed on June 29,

5422000. At the commencement of the hearing, the Administrative Law

552Judge granted the request of Petitioner to file an amended

562verified petition, which was identical to the amended petition,

571except that it was verified by the president of Petitioner.

581At the hearing, Petitioner called nine witnesses and offered

590into evidence Petitioner Exhibits 1-9 and 11-14. Respondent

598Tampa Bay Water called six witnesses. Respondent Department of

607Environmental Protection called four witnesses. Intervenor

613called one witness. One member of the public testified. The

623parties jointly offered into evidence Joint Exhibits 1-12, 14-16,

63220, and 22-37. All exhibits were admitted except Petitioner

641Exhibits 9 and 11; as for Petitioner Exhibit 12, only the blue,

653checked circled items were admitted. Petitioner proffered the

661exhibits and portion of Exhibit 12 that were not admitted.

671At the end of the hearing, the Administrative Law Judge gave

682the parties nine days, or until Friday, July 21, 2000, within

693which to file proposed recommended orders, so that the

702Administrative Law Judge could issue his recommended order by the

712following Monday, July 24, 2000.

717The court reporter filed the Transcript on July 14, 2000.

727The parties filed their proposed recommended orders on July 21,

7372000. Respondents and Intervenor filed a joint proposed

745recommended order.

747Respondent Tampa Bay Water also filed on July 21, 2000, a

758Motion for the Award of Attorney's Fees and Costs and Memorandum

769of Law.

771FINDINGS OF FACT

774I. Inception of Tampa Bay Water, Consolidated Permit,

782and Other Documentation for the Production of Drinking Water

7911. Respondent Tampa Bay Water (TBW) is a wholesale public

801water supply utility. TBW is governed by a nine-member board of

812directors with one member each from the municipalities of Tampa,

822St. Petersburg, and New Port Richey and two members each from the

834counties of Hillsborough, Pinellas, and Pasco. The purpose of

843TBW is to use group resources to find regional solutions to the

855problems of water supply in the region. Over two million persons

866in the three-county area rely on TBW for their drinking water.

8772. The predecessor of TBW was the West Coast Regional Water

888Supply Authority (WCRWSA), which was created in 1974. The West

898Coast Regional Water Supply Authority was also a wholesale public

908water supply authority. However, the authority operated as a

917cooperative entity, and TBW operates as a regulatory entity.

9263. In 1996, WCRWSA sought to renew its permit from

936Intervenor Southwest Florida Water Management District (SWFWMD)

943to allow continued withdrawals from four of its eleven major

953wellfields. Concerned with the environmental impacts, such as

961drawdowns of the water levels of wetlands, streams, and lakes,

971from the environmental, if not regulatory, overpumping of the

980wellfields, SWFWMD denied the application for the quantities

988requested.

9894. An Administrative Law Judge at the Division of

998Administrative Hearings conducted a hearing and issued a

1006recommended order finding adverse environmental effects from

1013overpumping, but recommending that SWFWMD issue the requested

1021permits subject to certain conditions. Subsequent negotiations

1028resulted in the parties' entering into a series of agreements

1038covering withdrawals from the four wellfields that had been the

1048subject of the administrative hearing and seven more wellfields

1057that were approaching repermitting (11 Wellfields), as well as a

1067series of other matters.

10715. On May 20, 1998, WCRWSA, the three member counties, the

1082three member municipalities, and SWFWMD entered into the Northern

1091Tampa Bay New Water Supply and Ground Water Withdrawal Reduction

1101Agreement (Partnership Agreement).

11046. The Partnership Agreement requires WCRWSA to bring one

1113or more projects online, by December 31, 2002, to produce at

1124least 38 million gallons per day (MGD) and, by December 31, 2007,

1136to produce at least 85 MGD of new water supply. The Partnership

1148Agreement requires SWFWMD to provide WCRWSA with $183 million

1157toward eligible water supply projects.

11627. The Partnership Agreement notes that the then-current

1170Master Water Plan of WCRWSA recognizes that "an aggressive

1179conservation and demand management program is an integral

1187component of a sustainable water supply." (Joint Exhibit 3, p.

119731.) The Partnership Agreement notes that the then-current

1205Master Water Plan states that the conservation program was

1214expected to reduce use by 10 MGD per day by 2000 and 17 MGD by

12292005.

12308. From the effective date of the agreement through

1239December 31, 2002, the Partnership Agreement requires a reduction

1248in pumping of the 11 Wellfields to 158 MGD, based on a rolling

126136-month average. For the next five years, the Partnership

1270Agreement requires a reduction in pumping of the 11 Wellfields to

1281121 MGD, based on an annual average. After that, effective

1291December 31, 2007, the Partnership Agreement requires a reduction

1300in pumping of the 11 Wellfields to 90 MGD, also based on an

1313annual average.

13159. Three weeks after the execution of the Partnership

1324Agreement, WCRWSA was reorganized into TBW in June 1998 through

1334the execution of two documents: an Amended and Restated

1343Interlocal Agreement dated June 10, 1998 (Interlocal Agreement),

1351and a Master Water Supply Contract dated June 10, 1998. TBW

1362assumed WCRWSA's rights and responsibilities under the

1369Partnership Agreement.

137110. The Interlocal Agreement empowers TBW to produce and

1380supply drinking water "in such manner as will give priority to

1391reducing adverse environmental effects of excessive or improper

1399withdrawals of Water from concentrated areas." (Joint Exhibit 1,

1408pp. 20-21.)

141011. The Interlocal Agreement incorporates the phased-in

1417reductions in withdrawals from the 11 Wellfields that are set

1427forth in the Partnership Agreement. The Interlocal Agreement

1435notes that, if the Partnership Agreement provides for extensions

1444of the deadlines, the deadlines contained in the Interlocal

1453Agreement shall likewise be subject to extension.

146012. Applying to the 11 Wellfields, SWFWMD issued TBW a

1470Consolidated Permit, which was issued on December 15, 1998, and

1480became effective on January 1, 1999. Complementing the

1488Partnership Agreement, which reflects SWFWMD's resource-

1494development role, is the Consolidated Permit, which reflects

1502SWFWMD's regulatory role.

150513. The Consolidated Permit incorporates the phased-in

1512reductions of withdrawals, as set forth above, for the 11

1522Wellfields. Although the deadlines for phased-in reductions are

1530conditioned on the funding to be provided by SWFWMD, pursuant to

1541the Partnership Agreement, these deadlines are otherwise

1548unconditional and firm. The Consolidated Permit expressly

1555provides for extensions of deadlines, except the deadlines set

1564for the phased-in reductions of withdrawals from the 11

1573Wellfields.

157414. The Consolidated Permit imposes upon TBW extensive

1582responsibilities regarding environmental monitoring, reporting,

1587and mitigation. These responsibilities extend to groundwater,

1594wetlands, and surface waters, as TBW must, among other things,

1604monitor and report levels in the surficial and Floridan aquifers

1614and potentiometric surfaces in the Floridan aquifer in the

1623vicinity of the 11 Wellfields, as well as in the vicinity of

1635selected wetlands and surface waters. The Consolidated Permit

1643sets specific "regulatory levels" for these resources.

1650II. Present and Future Tampa Bay Water Facilities,

1658Including the Surface Water Treatment Plant

166415. A majority of TBW's production facilit ies consists of

1674the 11 Wellfields. In an effort to supplement these production

1684sources so as to comply with the phased-in reduction deadlines

1694set forth in the Consolidated Permit and other documents, TBW

1704annually adopts a New Water Plan, which describes capital

1713planning for drinking water production facilities.

171916. The June 2000 New Water Plan summarizes the

1728requirements of the Partnership Agreement. The June 2000 New

1737Water Plan notes that TBW reaffirmed its Master Water Plan and

1748New Water Plan projects in April 2000. These projects include

1758the Enhanced Surface Water System, which includes the Tampa Bay

1768Regional Surface Water Treatment Plant (SWTP), Tampa Bay

1776Reservoir Project (Reservoir), and projects obtaining water from

1784the Alafia River, Hillsborough River, and Tampa Bypass Canal.

1793Other projects, besides the Enhanced Surface Water System,

1801include Seawater Desalination (Desal Plant).

180617. The June 2000 New Water Plan states that the Enhanced

1817Surface Water System is eligible for a maximum of $120 million

1828from SWFWMD, pursuant to its funding obligation under the

1837Partnership Agreement.

183918. This case involves the means by which the SWTP will be

1851permitted, and, in consideration of the manner of permitting,

1860this case involves the means by which the SWTP will be designed

1872and constructed. The June 2000 New Water Plan notes that TBW and

1884USFilter Operating Services, Inc. (USFilter) have entered into a

1893contract for the latter to design, build, and operate (DBO) the

1904SWTP (DBO Contract). The June 2000 New Water Plan reports that

1915USFilter is currently constructing an access road to the site.

192519. Among current issues, the June 2000 New Water Plan

1935describes this case, noting that TBW obtained a variance from

1945Respondent Department of Environmental Protection (DEP) allowing

1952a design, build (DB) approach to permitting the SWTP. The June

19632000 Water Plan states that the present challenge "has the

1973potential to delay the completion of the [SWTP] by an estimated

19848 months, subsequently delaying delivery of the initial 22 mgd

1994(dry weather conditions) of new surface water to the regional

2004system until May 2003 and more likely final acceptance of the

2015[SWTP] to September 2003." (Joint Exhibit 5, p. 4.) (The

2025accuracy of this statement is open to debate because SWFWMD

2035granted an environmental resource permit for the SWTP project

2044only on June 27, 2000--before which no significant alteration of

2054the land could have taken place.)

206020. In the meantime, the June 2000 New Water Plan predicts

2071a water supply shortfall of 100,000 to 2 million gallons per day

2084in the South-Central service area of Hillsborough County.

209221. Addressing the SWTP, the June 2000 New Water Plan

2102states that TBW purchased the site in October 1999 and released a

2114Request for Proposals on July 19, 1999. Four pre-qualified DBO

2124teams responded on October 18, 1999.

213022. The June 2000 New Water Plan erroneously states that

2140TBW applied for a public drinking water facility construction

2149permit (Water Treatment Permit) in October 1999. Actually, in

2158September or October, TBW prefiled with the Hillsborough County

2167Health Department (Health Department) its application for a Water

2176Treatment Permit and paid the $7500 filing fee. The purpose of

2187this courtesy filing or prefiling was to allow Health Department

2197representatives to examine the application, including drawings

2204and specifications for the SWTP, and perhaps expedite the

2213approval process, once TBW filed a formal application.

222123. The June 2000 New Water Plan reports that the SWTP will

2233have a peak day, surface water treatment capacity of 60 MGD and

2245will be located on a 433-acre site near U.S. Route 301 and

2257Broadway Avenue in central Hillsborough County. The June 2000

2266New Water Plan states that the SWTP project schedule calls for

2277completion of construction by March 2003 with plant startup and

2287testing in May 2003 and final acceptance testing in September

22972003. The June 2000 New Water Plan estimates that detailed

2307design, site permitting, and construction of the SWTP will cost

2317$84.3 million, and the annual operation and maintenance expenses

2326will be $7.9 million.

233024. As for the Desal Plant, the June 2000 New Water Plan

2342reports that TBW will pursue a design, build, own, operate, and

2353transfer (DBOOT) approach to acquire a plant to produce,

2362initially, 25 MGD and capable of expansion by an additional 10

2373MGD. The June 2000 New Water Plan states that this plant will

2385cost a total of about $96 million in capital expenses and about

2397$19 million annually to operate.

2402III. Procurement of the Surface Water Treatment Plant

2410A. Design, Build, Operate Contract and Basis of Design

241925. TBW issued a Request for Proposals (RFP) that invited

2429base and alternative proposals for the SWTP. TBW hired Parsons

2439Engineering Sciences to prepare a preliminary design of the SWTP,

2449so as to assist in the preparation of the proposals; although

2460offerors could use alternative designs to the Parsons base

2469design, all proposals had to meet the performance standards

2478specified in the RFP.

248226. After publishing the RFP in papers and technical

2491journals and on the Internet, TBW was able to prequalify five

2502teams of offerors. Four of the five prequalified offerors

2511submitted proposals. TBW received a total of nine proposals

2520because each offeror submitted a base proposal and one

2529alternative proposal, and one offeror submitted a second

2537alternative proposal.

253927. At its January board meeting, TBW selected the USFilter

2549proposal. No party filed a bid protest to the specifications of

2560the RFP or the selection of USFilter and its team. After the

2572selection of USFilter, TBW entered into negotiations with

2580USFilter. During this process, USFilter agreed, at its expense,

2589to add sand to the granulated activated carbon filters to remove

2600fine particles more efficiently, even though it cannot recover

2609the resulting cost of $1.5 million before or after the

2619commencement of operations.

262228. TBW and USFilter entered into the DBO Contract on April

263310, 2000 (DBO Contract). The DBO Contract identifies "Design

2642Requirements" that "are intended to include the basic design

2651principles, concepts and requirements for the [c]onstruction . .

2660but do not include the detailed design or indicate or describe

2671each and every item required for full performance of the physical

2682[c]onstruction . . .." (Joint Exhibit 23, Section 1.2.6.)

269129. The "Design Requirement s" are Schedule 6 to the DBO

2702Contract. Schedule 6 contains all of the individual, technical

2711specifications for the SWTP. Schedule 6 occupies two of the four

2722volumes of large, three-ringed binders forming the DBO Contract.

273130. The DBO Contract identifie s USFilter, Clark, and Camp

2741Dresser & McKee, Inc. (Camp Dresser) as the DBO team for the SWTP

2754project. Camp Dresser is providing design services, Clark is

2763performing the construction, and USFilter is providing the

2771operation and maintenance services for at least 15 years, as well

2782as the financial guarantee, through its corporate parent.

279031. The DBO Contract provides TBW with a fixed construction

2800cost, fixed operating costs, and guaranteed finished water

2808quality. Schedule 8 assures that finished water quality will

2817meet all applicable state and federal drinking water quality

2826standards. Two witnesses at the hearing testified that TBW

2835exacted from USFilter assurances of water quality that, as to

2845certain parameters, will exceed applicable state and federal

2853drinking water quality standards.

285732. The DBO Contract provides TBW with a firm completion

2867date, subject to design modifications requested by TBW and

2876uncontrollable circumstances, such as acts of God, raw water

2885whose quality exceeds the maximum limits, or the delay caused by

2896this case.

289833. A key document in this case is the Basis of Design

2910Report (Basis of Design), which was prepared by the DBO team in

2922April 2000. Acknowledging the phased-in withdrawal limitations

2929and potential for fines for not meeting the deadlines set forth

2940in the Consolidated Permit, the Basis of Design describes the

2950purpose of the DBO process as follows:

2957By utilizing the [DBO] approach for the

2964[SWTP], [TBW] expects to secure substantial

2970benefits . . .[,] includ[ing] costs savings,

2978innovative design, reduced risk of schedule

2984and cost excesses, long-term contracted

2989facility operations, and maintenance

2993efficiencies and guaranties.

2996(Joint Exhibit 8, pp. 1-2.)

300134. The Basis of Design reports that the SWTP will be

3012located on a 100-acre parcel within a 435-acre tract that will

3023also accommodate facilities for groundwater treatment and storage

3031of the treated groundwater, treated surface water from the SWTP,

3041and treated saline water from the Desal Plant.

304935. The Basis of Design identifies t he sources of raw water

3061for the SWTF as the Tampa Bypass Canal, Hillsborough River, and

3072Alafia River. Once online, the reservoir will help normalize

3081quantities of available raw water throughout the dry season.

309036. The Basis of Design describes the main treatment

3099process as pretreatment, including pH adjustment with sulfuric

3107acid or caustic soda, powdered activated car feed, and ferric

3117sulfate coagulant addition; coagulation, flocculation, and

3123sedimentation using a high-rate ballasted sedimentation process

3130known by its tradename as ACTIFLO; ozonoation for primary

3139disinfection, taste and odor control, and partial conversion of

3148dissolved organic carbon to an assimilable or biodegradable form;

3157biologically active filtration for turbidity reduction, taste and

3165odor control; reduction of biodegradable organic carbon; and

3173post-treatment, including secondary disinfection using

3178chloramines. The finished water will then be pumped into tanks

3188for storage and blending before release into the distribution

3197facilities.

31983 7. Distinguishing the DB process from the typical design,

3208bid, build (DBB) process, the Basis of Design states:

3217a very significant amount of process studies

3224and pre-engineering was performed by the

3230Project Team in support of its [DBO

3237p]roposal. This work included a set of

3244drawings covering all disciplines and

3249developed to the 25 to 30 percent completion

3257stage at a minimum with some drawings

3264developed to a greater degree. This stage of

3272drawing development is significantly beyond

3277the sketches and diagrams usually provided in

3284Basis of Design or Preliminary Design

3290Reports. For this [Basis of Design,] the

3298referenced drawings are attached and should

3304be examined when reviewing this [Basis of

3311Design]. As such, a relatively small number

3318of figures are contained within this [Basis

3325of Design].

3327(Joint Exhibit 8, pp. 1-4.)

333238. The Basis of Design notes that the Project Team

3342conducted "pilot-scale" studies of the chosen treatment processes

3350using Lake Manatee raw water. The purpose of these studies was

3361to validate the selected treatment processes, provide water

3369quality data, and establish appropriate operating criteria, such

3377as coagulant dosages.

338039. The Basis of Design addresses raw water quality issues.

3390One table sets out values for 30 different water quality

3400parameters for each of the three raw water sources. The Basis of

3412Design discloses expected water quality data for 11 water quality

3422parameters.

342340. Of particular interest are total nitrogen and total

3432phosphorus because, as noted in the Basis of Design, the algal

3443life-cycle increases dissolved organic carbon and nutrient

3450concentrations in reservoir water, and the "severity of this

3459problem is impossible to predict." (Joint Exhibit 8, pp. 2-4.)

3469The expected water quality values for total nitrogen and total

3479phosphorus, respectively, are, on average, 0.8 and 0.55 mg/L and,

3489at maximum, 1.6 and 2.1 mg/L.

349541. Each of the three surface waters approaches the average

3505values, but none approaches the maximum values, for total

3514nitrogen. The same is true for total phosphorus for the Tampa

3525Bypass Canal and Hillsborough River. However, for the Alafia

3534River, total phosphorus is 2.09 mg/L, so the raw water from the

3546Alafia River may present a substantial treatment challenge, as it

3556exceeds even the maximum expected value for total phosphorus.

356542. An error in Table 2-4 in reporting the maximum and

3576average values of manganese (either the maximum value should be

35860.02 mg/L or the average value should be 0.001 mg/L) and the

3598omission of a turbidity parameter expressed in NTUs precludes

3607analysis of these water quality parameters. However, the other

3616expected parameters appear to reflect the actual water quality of

3626these three surface waters.

363043. Section 4 of the Basis of Design describes the

3640facilities and design criteria for the SWTP. This section begins

3650with site grading, roadways, yardpiping, and stormwater

3657management and extends to detailed discussions of the

3665pretreatment and treatment processes, including the ACTIFLO,

3672ozone contactor, and biologically active filtration.

3678B . Urgency of New Means of Producing Drinking Water

368844. The SWTP is the hub of a network of production,

3699storage, transmission, and distribution facilities that TBW plans

3707to bring online in order to meet the requirements and deadlines

3718set forth in the Consolidated Permit and other documents. The

3728urgency for bringing this component of these new facilities

3737online as soon as possible is due to environmental reasons, as

3748well as the financial and legal reasons set forth above.

375845. Overpumping of existing wellfields has drawn down water

3767levels in surface waters and wetlands, to the detriment of the

3778overall level of biodiversity supported by these natural

3786resources. Some lakes have been down 10 years, and a few have

3798been down 40 or 50 years. During the recent drought, the City of

3811Tampa, which obtains water from the Hillsborough River, lacked

3820adequate volumes of surface water from which to produce

3829sufficient finished water to meet the demand of its customers.

383946. Not surprisingly, these supply problems are ac companied

3848by record withdrawals from the 11 Wellfields. Withdrawals in May

3858and June of this year were the highest monthly withdrawals on

3869record--208 MGD and 175 MGD, respectively. If the drought

3878continues and TBW continues to meet the demands of its customers,

3889TBW's withdrawals from the 11 Wellfields will exceed the

3898permitted 158 MGD, on a rolling 36-month average, by April 2001.

390947. Wellfield overpumping has stressed the groundwaters.

3916Although surface waters respond to substantial rains in as little

3926as a day or two, groundwater takes significantly longer to

3936respond. The surficial water table is as much as 20 feet below

3948ground level, and the Floridan Aquifer is even deeper. The

3958surficial aquifer does not begin to respond to substantial rains

3968for one week, and the Floridan Aquifer begins to respond in two

3980to four weeks.

398348. The condition of the surficial and Floridan aquifers

3992affects the Hillsborough River and Tampa Bypass Canal, which are

4002significantly recharged by the surficial and, sometimes, the

4010Floridan Aquifer. The Floridan Aquifer is especially important

4018to the Tampa Bypass Canal, whose rock bed has been breached.

4029During dry periods, the two aquifers are the primary sources of

4040recharge for these two surface waters. The Alafia River is more

4051confined, but gets water from the Floridan Aquifer through two

4061springs at the head of the river.

406849. TBW has already made substantial gains through

4076conservation and has met the goal of nearly 10 MGD for 2000.

4088Over the next 20 years, maximum potential gains are expected to

4099be no more than 74-94 MGD. Conservation will continue to play an

4111important role in securing adequate drinking water supplies in

4120the Tampa Bay area, but conservation, even in conjunction with

4130reclaimed water, will not suffice, especially when future

4138population growth in the area is considered.

414550. TBW also manages wellfield production efficiently.

4152Under its Optimized Regulatory Operations Plan, TBW collects and

4161analyzes wellfield data to determine which wellfield to tap,

4170notwithstanding specific limits set by wellfield, in order to

4179minimize environmental damage. The consumptive use permits

4186issued to TBW for the surface waters that will provide raw water

4198to the SWTP restrict the amounts and timing of the removals.

4209Additionally, a hydrobiological monitoring program requires the

4216collection and analysis of data to safeguard against adverse

4225effects in the rivers and, downstream, in the estuary.

423451. The contractual deadline for delivery of the SWTP is

4244September 30, 2002. The timeframe for bringing online the SWTP

4254necessarily relies on acceptance testing in the wet season,

4263during which 60-65 percent of the annual rain occurs. The wet

4274season extends from mid June to the end of September. Acceptance

4285testing of the SWTP is imperative toward the end of this period

4297because this is when the water quality of the surface waters

4308bears the highest levels of the contaminants. Thus, if delays

4318postpone beyond the wet season the point at which acceptance

4328testing can take place, the postponement will effectively be

4337until the next wet season and, possibly, the end of the next wet

4350season.

4351IV. Permitting the Design, Build Process

4357for the Surface Water Treatment Plant

4363A. General

436552. The DB process envisioned by TBW would essentially

4374break into phases the process by which TBW would obtain the

4385necessary Public Drinking Water Treatment Construction Permit

4392(Permit). The Permit initially would be based on "30 percent

4402plans," which reflect about a 30 percent level of effort toward

4413the overall design work or 30 percent completion of all of the

4425design work (30 Percent Plans).

443053. Generally, 30 Percent Plans mark the end of the

4440preliminary design phase. Plans reflecting 30, 60 and 90 percent

4450levels of effort are customary in DBB processes, as these are the

4462stages at which owners typically review design work. In 30

4472Percent Plans, some items are designed to 100 percent and other

4483items are not designed at all. However, 30 Percent Plans provide

4494reasonable assurance that the designed system is constructable.

450254. In essence, the Permit initially would be a conceptual

4512permit for the entire SWTP coupled with a construction permit for

4523those components for which the design is already complete on the

453430 Percent Plans. Construction of each remaining component of

4543the SWTP would await subsequent permit modifications authorizing

4551construction of that component. As noted above, the May 18,

45612000, cover letter anticipates another interim permit, or permit

4570modification, covering specific components, and then the final

4578permit, or permit modification, covering the entire SWTP.

458655. The DEP district office in Orlando has substantial

4595experience with permitting DB water treatment projects. From

46031996-98, the DEP Orlando office has permitted four such projects

4613for the Orlando Utilities Commission and one such project for the

4624City of Kissimmee. One of the Orlando Utilities Commission

4633projects was to construct a completely new water treatment plant.

464356. Based on the experience of the DEP Orlando office, DB

4654permitting, when based initially on 30 Percent Plans, shortens

4663and simplifies the permitting process. DB permitting eliminates,

4671or at least postpones, the presentation of elements, such as

4681electrical and HVAC, that are irrelevant to the permitting

4690process; the elimination of elements irrelevant to permitting

4698from the initial designs helps the regulator find the elements

4708that are relevant to the permitting process. Also, the

4717experience of the DEP Orlando office is that the DB process

4728results in no more permit modifications for change orders than

4738are typical of a conventional DBB process.

474557. The DB-approval process used by the DEP Orlando office

4755is modeled after the DEP-permitting process for wastewater

4763treatment plants. DEP rules allow DB permitting of these plants,

4773which are similar in construction to water treatment plants. In

4783fact, DEP is preparing to adopt rules to allow DB permitting of

4795water treatment plants.

479858. Because the DEP Orlando office did not issue variances

4808from the rules that arguably preclude DB construction of water

4818treatment plants, there is no precedent for the issuance of the

4829variance sought in this case. However, the experience of the DEP

4840Orlando office is that applicants do not present basic design

4850changes after the initial submission, and DB permitting does not

4860mean that regulatory objectives are sacrificed to the expediency

4869sought by the applicant.

4873B. The Present Case

487759. On April 11, 2000, Camp Dresser, on behalf of TBW,

4888filed with the Health Department an Application for a Public

4898Drinking Water Facility Construction Permit. The April 2000

4906drawings that accompanied the April 11, 2000, application are

4915described above. The cover letter to the Health Department notes

4925that, "upon conceptual approval of the project, individual

4933components will be permitted through permit modifications based

4941on submittals of complete drawings and specifications for each

4950component."

495160. In this case, the availability of the Basis of Design

4962meant that the 30 Percent Plans reflected more than a 30 percent

4974level of effort or completion of the five-stage process of

4984pretreatment, pH adjustment, ozone contactors, filtration, and

4991storage in tanks. The engineer had already sized the facilities

5001and defined all of the processes and elements of the SWTP. The

5013April 2000 drawings, as supplemented by the Basis of Design,

5023therefore presented a relatively detailed description of the

5031scope, elements, and processes of the project.

503861. On May 18, 2000, Camp Dresser submitted to the Health

5049Department more advanced drawings, which are dated May 18, 2000.

5059The cover letter explains that the drawings are a complete set of

5071Phase I drawings and specifications. The letter states that Camp

5081Dresser intends to file complete drawings and specifications in

5090three phases. Phase I, which is completed with the May 2000

5101drawings, consists of sitework, high rate flocculation and

5109sedimentation, and ozone contact tanks. Phase II consists of

5118biologically active granulated active carbon filters, clearwell,

5125and gravity thickeners. Phase III consists of the remainder of

5135the project.

513762. As of July 3, 2000, prior to the final hearing, the

5149design for the SWTP had reached the 60 percent level of effort or

5162completion.

516363. Although the SWTP described in the DBO Contract, Basis

5173of Design, and May drawings is a relatively large, complex

5183facility, it does not employ unproven technology. The

5191standardization of design and regulatory review is facilitated by

5200the use of the so-called Ten States' Standards, which are

5210standards commonly used by the permitting authorities of numerous

5219states, including Florida, to determine the capabilities of

5227specified treatment processes in achieving specific water quality

5235levels.

523664. Although the ACTIFLO technology is relatively new, it

5245has been in use for at least five years. A pretreatment

5256sedimentation barrier that reduces treatment time and thus

5264tankage volume requirements, ACTIFLO is in use in a water

5274treatment plant with a capacity of 60 MGD in Canada, which TBW's

5286selection team members visited. ACTIFLO presently is being

5294incorporated into a surface water treatment plant in Melbourne,

5303Florida, where it must treat the nutrient-rich water of Lake

5313Washington and the St. Johns River. The City of Tampa is adding

5325ACTIFLO basins to its facilities. Also significant is the fact

5335that ACTIFLO easily passed the pilot test on Lake Manatee. At

5346present, 25 facilities using ACTIFLO are under design or

5355construction in North America.

535965. As is consistent with the theory, the DBO process for

5370designing, building, and operating the SWTP has demanded greater

5379cooperation among the three entities that operate relatively

5387independently in the DBB process. Pursuant to their obligations

5396under the DBO Contract, Camp Dresser, Clark, and USFilter have

5406coordinated, and likely will continue to coordinate, their

5414efforts closely from design and construction, up to operation, to

5424save time and money from the traditional DBB process, in which

5435the design phase, construction phase, and operation phase are

5444relatively independent of each other.

5449C. The Variance

545266. In general, DEP has the authority to issue public

5462drinking water treatment construction permits. The successful

5469applicant obtains one permit--for construction and operation.

5476There are no conceptual permits or separate operating permits.

548567. In Hillsborough County, as well as 10 other counties,

5495DEP has delegated its responsibilities for issuing public

5503drinking water treatment construction permits. In Hillsborough

5510County, DEP has delegated this responsibility by an interagency

5519agreement to the Health Department. Applying DEP rules to

5528determine whether to issue a public drinking water construction

5537permit, the Health Department defers to DEP for the issuance of

5548variances from DEP rules.

555268. In typical permitting cases, the Health Department u ses

5562its own staff in processing the application and reaching a

5572permitting decision. In a large case, such as this, the Health

5583Department's lone professional engineer, who was hired in

5591September 1999, can obtain considerable assistance from

5598professional engineers within the Tampa Bay area and professional

5607engineers employed by DEP.

561169. Perceiving a possible incompatibility between the DB

5619process and the rules from which the variance is sought in this

5631case, TBW initially filed a request for a variance with the

5642Health Department. However, the Health Department declined to

5650issue a variance to DEP rules and informed TBW that it had to

5663file its request with DEP. Thus, on January 10, 2000, TBW filed

5675a petition for a variance with DEP.

568270. On March 28, 2000, DEP issued a final order, pursuant

5693to Section 120.542, Florida Statutes, granting the requested

5701variance from Rule 62-555.520(4)(c) and (d), Florida

5708Administrative Code (Variance). The Variance finds that the

5716purpose of the underlying statutes would be met "because no

5726component of the project would be permitted or constructed

5735without review by the permitting authority of the complete plans

5745and specifications for that portion of the project." The

5754Variance finds that the DB approach will protect the public

5764health, safety, and welfare in providing safe drinking water

5773without exacerbating possible negative environmental impacts from

5780the overuse of groundwater.

578471. The Variance relieves TBW of the necessity of complying

5794with two subsections of the rule governing the contents of

5804applications for a public drinking water construction permit.

5812Rule 62-555.520(4)(c) and (d), Florida Administrative Code,

5819provides:

5820The permit application form sets forth the

5827minimum information which is to be supplied

5834to the Department or the Approved County

5841Health Department. Additional information

5845may be required by the Department to clarify

5853information submitted in the permit

5858application or to demonstrate that the

5864proposed level of treatment will effectively

5870treat the contaminants present in the raw

5877water. The information required by the

5883application is as follows:

5887* * *

5890(c) Prints of drawings of the work project

5898which contain sufficient detail to clearly

5904apprise the Department of the work to be

5912undertaken. All prints shall be minimum of

591918 x 24 inches and a maximum size of 36 x 42

5931inches. The scale of details contained shall

5938be satisfactory for microfilm reproduction.

5943(Reduced size photographic reproduction of

5948drawings for submission may be authorized.)

5954(d) Complete specifications of the project

5960necessary to supplement the prints submitted.

596672. The issuance of the Variance by DEP has met with

5977approval, albeit cautious approval, by the Health Department.

5985One Health Department witness was an Engineer III, who is 19-year

5996employee of the Health Department and supervisor of four

6005Environmental Specialists charged with reviewing construction

6011plans for drinking water plants. He testified that he agreed

6021with DEP's final order granting the Variance. The Engineer III

6031and the other Health Department witness, its professional

6039engineer, testified that the issuance of the initial permit would

6049not influence the Health Department in deciding whether to issue

6059permit modifications, except to ensure compatibility.

606573. Allo wing TBW not to comply with Rule 62 -555.520(4)(c)

6076and (d), Florida Administrative Code, the Variance provides that

6085the initial permit shall not authorize the construction of any

6095component of the SWTP; each component may be constructed only

6105after the submission of complete plans and specifications for

6114that component and the issuance of a permit modification based on

6125those complete plans and specifications. The Variance also

6133provides that the permitting authority shall publish a notice of

6143intent to issue a permit modification "if the permitting

6152authority believes that the modifications are of a controversial

6161nature, or that there is heightened public awareness of the

6171project."

6172V. Save Our Bays and Canals, Inc.

6179A. The Verified Amended Petition

618474. On May 1, 2000, Petitioner filed a petition challenging

6194the Variance. On June 29, 2000, Petitioner filed an amended

6204petition challenging the Variance, and the Administrative Law

6212Judge granted Petitioner leave to file an amended petition on

6222July 3, 2000. At the start of the hearing, on July 7, 2000,

6235Petitioner filed a verified amended petition, which was identical

6244to the amended petition, except that, on July 6, 2000,

6254Petitioner's president had verified the pleading "to the best of

6264[his] knowledge, information and belief."

626975. The verified amended petition states that Petitioner

6277has over 400 members. The verified amended petition alleges that

6287a substantial number of Petitioner's members will consume the

6296finished water produced by the SWTP and will use the surface

6307waters supplying the SWTP for recreation.

631376. The verified amended petition states that the purpose

6322of Petitioner is to save the bays, canals, and waterways of the

6334Tampa Bay area and to ensure safe drinking water for its members

6346and residents of the Tampa Bay area.

635377. The verified amended petition states that the Variance

6362affects Petitioner because it would allow the issuance of the

6372Permit and construction of initial phases of the SWTP prior to

6383submittal, review, and approval of complete plans for the next

6393and subsequent phases. The verified amended petition alleges

6401that Petitioner incorporated to pool its resources to review

6410applications, so as to ensure safe drinking water. The verified

6420amended petition states that submittal and review of a complete

6430set of drawings and specifications is necessary prior to

6439construction of the SWTP to ensure the ability of the facility to

6451comply with state drinking water standards. The verified amended

6460petition states that review of all individual components of the

6470SWTP is necessary to assure the protection of the public health,

6481safety, and welfare and the compliance with all applicable state

6491and federal laws.

649478. Addressing specifically the 30 Percent Plans, the

6502verified amended petition objects to the absence of a list of

6513items to be included in the 30 Percent Plans. The verified

6524amended petition alleges that this piecemeal approach to

6532permitting will require Petitioner to request administrative

6539hearings on each phase of permitting. The verified amended

6548petition states that the Variance may have adverse environmental

6557and safety impacts that cannot be evaluated fully without a

6567submittal and review of the complete drawings and specifications.

657679. The verified amended petition states that the DBO

6585approach is "self-created." The verified amended petition

6592objects to the failure of TBW to obtain the Variance before

6603issuing the RFP and instead using the DBO Contract as a basis for

6616claiming hardship so as to qualify for the Variance.

662580. The verified amended petiti on states that the number of

6636variances issued for similar 30 Percent Plans threatens to create

6646a situation in which the variance subsumes the rule requiring

6656complete drawings and specifications. The verified amended

6663petition objects to this form of unwritten policy that has not

6674been published as a rule.

667981. The verified amended petition states that the phased

6688permitting of the SWTP may create permitting momentum that

6697discourages a rigorous application of the rules at a later stage.

670882. The verified ame nded petition states that the request

6718for a variance is improper because it is for a variance from

6730statutes, not rules. The verified amended petition states that

6739Section 403.861(10), Florida Statutes, requires DEP or Health

6747Department approval of "complete plans and specifications prior

6755to the installation, operation, alteration, or extension of any

6764public water system." The verified amended petition states that

"6773installation" means construction.

677683. The verified amended petition states that Section

6784403.861(5), Florida Statutes, prohibits the issuance of a public

6793drinking water treatment construction permit "until the water

6801system has been determined to have the required capabilities

6810. . .." The verified amended petition states that the assurances

6821of USFilter are insufficient to satisfy this requirement.

682984. The verified amended petition states that Section

6837120.542, Florida Statutes, which authorizes the variance

6844procedure used in this case, does not authorize variances for

6854compliance with federal law. The verified amended petition

6862states that TBW must obtain a federal variance in order to obtain

6874the Variance.

687685. The verified amended petition states that the 30

6885Percent Plans omit information required for permitting, such as

6894the listing of a certified operator, monitoring and recordkeeping

6903programs, and various financial elements, such as the posting of

6913a bond and creation of reserves to demonstrate financial

6922soundness.

692386. The verified amended petition states that TBW's

6931substantial hardship is based on contract deadlines that are

6940entirely self-created and, thus, insufficient to warrant a

6948variance. The verified amended petition notes that the

6956environmental damage cited as a basis for granting the Variance

"6966was caused by years of overpumping by . . . TBW . . .." Also,

6981the verified amended petition states that member governments of

6990TBW continue to approve new development, which increases the

6999demand for drinking water, because TBW and its member governments

7009have failed to exploit fully the potential for conservation and

7019reclaimed water. Similarly, the verified amended petition states

7027that SWFWMD helped create the hardship by renewing the permits

7037for additional withdrawals from the 11 Wellfields.

704487. The verified amended petition states that the DBO

7053process will not necessarily save time and money and is not a

7065recognized exception to the general requirement that an applicant

7074must submit complete drawings and specifications prior to

7082permitting. The verified amended petition states that 30 Percent

7091Plans do not provide sufficient detail to know what the

7101contractor is promising to build, and it would be faster to

7112correct any mistakes prior to the start of construction, rather

7122than after the start of construction.

7128B. Standing

713088. Petitioner was an unin corporated association from its

7139formation in early October 1999 through February 3, 2000, when it

7150was incorporated as a Florida not-for-profit corporation.

7157Originally named Save Our Bays and Canals Association, the

7166unincorporated association was formed by members of the Apollo

7175Beach Civic Association who were concerned about the

7183environmental impact upon their bays and canals of intensive

7192utility and industrial land uses in close proximity to their

7202homes. Apollo Beach is an unincorporated area along the

7211southeast shore of Tampa Bay, just south of the mouth of the

7223Alafia River.

722589. The land uses with which the unincorporated association

7234has been concerned in its brief existence include a sulfur plant,

7245the TECO Big Bend plant, a proposed National Gypsum plant, a

7256proposed concrete plant, the proposed Desal Plant, and, now the

7266proposed SWTP. The Apollo Beach area is very close to the

7277proposed site of the Desal Plant, but is about 17 miles south

7289southeast from the proposed site of the SWTP.

729790. Petitioner a nd its members are primarily concerned with

7307the Desal Plant, not the SWTP. However, Petitioner and its

7317members express concern with the SWTP. The concerns are that DB

7328permitting of the SWTP will jeopardize the production of safe

7338drinking water and will result in greater costs to TBW customers,

7349who will eventually bear the financial burden of costly reworking

7359of a hastily designed and constructed project.

736691. Standing analysis is simplified by the elimination of

7375the issue of whether the verification of the amended petition

7385confers standing. The claims of Petitioner in this case do not

7396rise to the level of an attempt to prevent an activity, conduct,

7408or product to be permitted from impairing, polluting, or

7417otherwise injuring the air, water, or other natural resources of

7427the State.

742992. First, finished drinking water is not a natural

7438resource of the State. Although a resource, finished drinking

7447water is not natural. Although of lower water quality, raw water

7458is a natural resource. The potable water leaving the SWTP is a

7470manufactured resource.

747293. Second, even if finished drinking water were a natural

7482resource, the issuance of the Variance does not have the effect

7493of impairing, polluting, or otherwise injuring a natural

7501resource. The Variance excuses compliance with two rules

7509requiring complete drawings and specifications. Even assuming

7516that the SWTP would impair, pollute, or otherwise injure natural

7526resources, the Variance would not have such an effect because the

7537act of granting the Variance is distinct from the act of granting

7549the Permit itself.

755294. Thus, facts regarding the circumstances under which

7560Petitioner's president verified the amended petition are

7567irrelevant for the purpose of determining standing.

757495. Petitioner's standing is a function of the

7582characteristics of the corporation and its members.

758996. At the corporate level, the articles of incorporation

7598state that the "specific and primary purposes for which this

7608corporation is formed are to operate for the public education and

7619advancement of the water quality of Tampa Bay, its tributaries,

7629its estuaries and its canals and for other charitable purposes,

7639by the distribution of its funds for such purposes."

764897. There is some indication in the record of an attempt,

7659after filing the petition commencing this proceeding, to amend

7668the articles of incorporation to state, among Petitioner's

7676purposes, the protection of drinking water. The record does not

7686contain the written articles of incorporation, as amended, or

7695amended articles of incorporation after February 3, 2000.

7703However, for the purpose of this recommended order, the

7712Administrative Law Judge shall assume that such an amendment was

7722made at some point after the filing of the petition and before

7734the final hearing.

773798. At the membership le vel, the water to be produced by

7749the SWTP will be distributed primarily to customers in Pasco and

7760Pinellas counties, St. Petersburg, and the Northwest Service Area

7769of Hillsborough County, not to Apollo Beach, which is in southern

7780Hillsborough County. Nearly all of Petitioner's members reside

7788in Apollo Beach or other nearby communities, which also will not

7799be served by the SWTP.

780499. Although an insubstantial number of Petitioner's

7811members will consume finished water from the SWTP in their homes,

7822a substantial number will consume finished water from the SWTP at

7833their places of work or schools and where they shop or dine out.

7846Drinking water is ubiquitous, and the mixture of functional land

7856uses in Apollo Beach is not, so it is highly probable that

7868members of Petitioner will travel the three-county area in

7877connection with their employment, education, and recreation.

7884100. Close analysis of the characteristics of Petitioner

7892and its members reveals no basis for finding standing to

7902challenge the Variance.

7905101. Nothing in the record suggests that Petitioner or any

7915of its members have devoted themselves to the arcane task of

7926resisting a perceived trend of state and local agencies to issue

7937series of permits in response to DB proposals--or, more

7946colorfully, to engage in "piecemeal permitting."

7952102. About the only interest that Petitioner can

7960legitimately claim in DB permitting is that multiple points of

7970entry, at each permit and permit modification, will result in

7980additional expense. If Petitioner has standing to contest even

7989the permitting of the SWTP, Petitioner must petition each time

7999for an administrative hearing, conduct discovery, and participate

8007in the final hearing. However, this seems, at most, like a

8018tenuous interest, which suffers also from the speculation that

8027later stages of the DB permitting process will continue to

8037present new issues not raised in the challenge of the Permit

8048initially approved.

8050103. Turning to the members themselves, their consumption

8058of drinking water produced by the SWTP is no basis for standing

8070either because the attenuated relationship between the Variance,

8078which excuses compliance with two rules concerning the contents

8087of applications, and the safety of drinking water or the

8097additional costs that could arise from hasty designing,

8105constructing, or permitting. Although it is conceivable that a

8114record could have been made that the DB permitting proposed in

8125this case would likely result in incomplete, incompetent

8133permitting review, so as to jeopardize the public health if the

8144permit were to issue, the record in this case does not support

8156such a contention. To the contrary, the record establishes that

8166the DB permitting is at least as likely as DBB permitting to

8178provide the regulatory oversight necessary to assure the design

8187and construction of a successful public drinking water treatment

8196plant

8197104. Lacking a substantial nexus in the record between the

8207DB permitting authorized by the Variance and the quality of the

8218drinking water that, if the Health Department issues the Permit,

8228would likely be produced by the SWTP and likelihood of success of

8240the overall construction project, the members of Petitioner

8248likewise lack standing to challenge the Variance.

8255VI. Ultimate Findings of Fact

8260105. Petitioner and its members lack standing to challenge

8269the Variance.

8271106. TBW faces a substantial hardship if not given the

8281Variance. The legal and financial consequences of a failure to

8291meet the phased-in withdrawal reductions are real and

8299substantial. The environmental damage caused by overpumping the

830711 Wellfields underscores the urgency of developing alternative

8315sources of raw water for production into finished drinking water.

8325107. The rule from which TBW seeks the Variance is derived

8336from the statute discussed in the Conclusions of Law. The

8346underlying purpose of this statute is the protection of the

8356public health, safety, and welfare. The Variance serves the

8365underlying purposes in two respects. First, the 30 Percent Plans

8375contain sufficient detail to allow permitting to proceed without

8384jeopardizing the objective of the rules to ensure that the

8394USFilter team designs and constructs a water treatment plant that

8404is in full compliance with all federal and state law. Second,

8415the Variance provides that the USFilter team shall construct no

8425component of the SWTP until it has been permitted, either

8435initially or by a permit modification.

8441VII. Petitioner's Liability for Attorneys' Fees and Costs

8449108. Petitioner has a Technical Committee on which

8457Petitioner relies for examination of technical aspects of matters

8466that are of general concern to Petitioner. This committee

8475obtained a copy of the Variance and, after examination and

8485discussion, developed a position in opposition to DEP's stated

8494intent to grant the Variance.

8499109. The Chair of Petitioner 's Technical Committee, who has

8509a bachelor of science degree in chemistry and is an industrial

8520hygienist, drafted a letter reflecting the opinion of the

8529committee in opposition to the Variance. Petitioner's attorney

8537then converted this letter into the petition that commenced this

8547proceeding.

8548110. At all times, the Board of Directors of Petitioner

8558approved the actions of the Technical Committee and Petitioner's

8567attorney, including the filing of the petition.

8574111. When Petitioner's president verified the amended

8581petition, he reasonably relied on the advice of counsel

8590concerning the substance of the assertions, and the advice of

8600counsel was based on the work of the Technical Committee.

8610Petitioner's president also reasonably relied on the work of the

8620Technical Committee when he verified the amended petition.

8628112. Although DB permitting has been available for the

8637design and construction of wastewater treatment plants for an

8646undetermined period of time, DB permitting for the design and

8656construction of public drinking water plants is a new concept.

8666The concept is so new that the DEP Orlando office mistakenly

8677issued at least 2 DB permits for public drinking water plants

8688without requiring the applicant to obtain a variance from the two

8699rules that prevent DB permitting for such facilities. The

8708concept is so new that the key Health Department employees have

8719expressed concern over personnel demands from this new means of

8729permitting, although they have also expressed at least lukewarm

8738support for the Variance.

874211 3. The record portrays the employees of the Health

8752Department as hard-working and competent, but over-burdened. The

8760DB permitting obviously places significant responsibilities upon

8767the Health Department, especially as it familiarizes itself with

8776DP permitting. Although the availability of professional support

8784from other sources, including DEP, ultimately resolves this

8792issue, the situation of the Health Department also is relevant in

8803assessing Petitioner's liability for attorneys' fees and costs.

8811114. T wo or three aspects of the drawings were deficient,

8822according to Petitioner's professional engineer, whose testimony

8829has been admitted despite the unreasonably restricted opportunity

8837presented for cross-examination by his contractually driven

8844refusal to identify past clients or jobs. Although none of these

8855items seems likely to jeopardize a successful construction

8863project, these were design points on which well-informed

8871professionals could reasonably differ.

8875115. Although the issue of "improper purpose" presents a

8884closer question than the substantive issues discussed above,

8892there is inadequate subjective or objective evidence in the

8901record supporting TBW's claim for attorneys' fees and costs on

8911this ground. Ultimately, the novelty of DB permitting of

8920drinking water treatment plants precludes a finding of improper

8929purpose. All available facts drive this determination, and, at

8938this point in time, the relative uniqueness of DB permitting of

8949drinking water treatment plants to DEP, the Health Department,

8958and Petitioner and its members provides the necessary margin to

8968preclude a finding of improper purpose.

8974CONCLUSIONS OF LAW

8977116. The Division of Administrative Hearings has

8984jurisdiction over the subject matter. Section 120.57(1), Florida

8992Statutes. (All references to Sections are to Florida Statutes.

9001All references to Rules are to the Florida Administrative Code.)

9011117. Seeking the Variance, the burden of proof is on TBW.

9022Department of Transportation v. J. W. C. Company, Inc. , 396 So.

90332d 778 (Fla. 1st DCA 1981). See also Section 120.542(2).

9043118. Section 120.542(1) recognizes that "[s]trict

9049application of uniformly applicable rule requirements can lead to

9058unreasonable, unfair, and unintended results in particular

9065instances." Consequently, Section 120.542(2) provides that

9071variances and waiver shall be granted when the applicant

"9080demonstrates that the purpose of the underlying statute will be

9090or has been achieved by other means by the person and when

9102application of a rule would create a substantial hardship or

9112would violate principles of fairness."

9117119. TBW chose not to proceed under the fairness prong.

9127Section 120.542(2) defines a "substantial hardship" as a

"9135demonstrated economic, technological, legal, or other type of

9143hardship to the person requesting the variance or waiver."

9152120. As noted above, TBW proved the substantial hardship.

9161The need for the SWTP is urgent--environmentally, legally, and

9170financially.

9171121. Petitioner did not rely on Section 403.810(5) in its

9181proposed recommended order. (An examination of that subsection

9189suggests that it may have been miscited.) The statute underlying

9199Rule 62 -555.520(4)(c) and (d) is Section 403.861(10), which

9208empowers DEP to:

9211Require department or county health

9216department review and approval of complete

9222plans and specifications prior to the

9228installation, operation, alteration, or

9232extension of any public water system.

9238122. "Installation" is construction. The Variance does not

9246permit construction of any component of the SWTP prior to its

9257permitting.

9258123. In general, the purpose of Section 403.861 is to

9268assure the public health, safety, and welfare. As noted above,

9278the Variance serves the underlying purpose of the statute.

9287124. Section 403.412(5) addresses "any administrative,

9293licensing, or other proceedings authorized by law for the

9302protection of the air, water, or other natural resources of the

9313state from pollution, impairment, or destruction . . .." In such

9324proceedings, Section 403.412(5) provides that a citizen of

9332Florida "shall have standing to intervene as a party on the

9343filing of a verified pleading asserting that the activity,

9352conduct, or product to be licensed or permitted has or will have

9364the effect of impairing, polluting, or otherwise injuring the

9373air, water, or other natural resources of the state."

9382125. As noted above, Petitioner may not obtain standing

9391under Section 403.412(5).

9394126. Also as noted above, Petitioner and its members are

9404not otherwise persons whose substantial interests are affected by

9413the issuance of the Variance. Petitioner lacks standing.

9421127. In Agrico Chemical Company v. Department of

9429Environmental Regulation , 406 So. 2d 478, 482 (Fla. 2d DCA 1981),

9440rev. denied , 415 So. 2d 1359 (Fla. 1982), the court stated:

"9451before one can be considered to have a substantial interest in

9462the outcome of the proceeding he must show 1) that he will suffer

9475injury in fact which is of sufficient immediacy to entitle him to

9487a section 120.57 hearing, and 2) that his substantial injury is

9498of a type or nature which the proceeding is designed to protect."

9510128. As noted above, neither Petitioner nor its members

9519have made the required showing under either of the two prongs set

9531forth in Agrico .

9535129. Section 120.569(2)(e) provides that the signing of all

9544pleadings constitutes a "certification that the person has read

9553the pleading, motion, or other paper and that, based upon

9563reasonably inquiry, it is not interposed for any improper

9572purpose, such as to harass or to cause unnecessary delay, or for

9584frivolous purpose or needless increase in the cost of

9593litigation." A violation of these requirement requires the

9601imposition of attorneys' fees and costs.

9607130. Section 120.595(1)(c) requires the Administrative Law

9614Judge to

9616determine whether any party participated in

9622the proceeding for an improper purpose as

9629defined by this subsection and

9634s.120.569(2)(e). In making such

9638determination, the administrative law judge

9643shall consider whether the nonprevailing

9648adverse party has participated in two or more

9656other such proceedings involving the same

9662prevailing party and the same project as an

9670adverse party and in which such two or more

9679proceedings the nonprevailing adverse party

9684did not establish either the factual or legal

9692merits of its position, and shall consider

9699whether the factual or legal position

9705asserted in the instant proceeding would have

9712been cognizable in the previous proceedings.

9718In such event, it shall be rebuttably

9725presumed that the nonprevailing adverse party

9731participated in the pending proceeding for an

9738improper purpose.

9740131. The determination of a violation of Section

9748120.595(1)(c) requires that the recommended order determine the

9756amount of attorneys' fees and costs.

9762132. The inquiry concerning improper purpose is objective,

9770not subjective. In other words, "if reasonably clear legal

9779justification can be shown for the filing of the paper in

9790question, improper purpose cannot be found and sanctions are

9799inappropriate." Friends of Nassau County, Inc. v. Nassau County ,

9808752 So. 2d 42, 50 (Fla. 1st DCA 2000)(construing predecessor to

9819Section 120.569(2)(e)).

9821133. For the reasons noted above, TBW has failed to prove

9832any improper purpose by Petitioner associated with the filing of

9842any pleading or participation in this case.

9849RECOMMENDATION

9850It is

9852RECOMMENDED that the Department of Environmental Protect ion

9860enter a final order granting the Variance and denying the request

9871of Tampa Bay Water for attorneys' fees and costs.

9880DONE AND ENTERED this 24th day of July, 2000, in

9890Tallahassee, Leon County, Florida.

9894___________________________________

9895ROBERT E. MEALE

9898Administrative Law Judge

9901Division of Administrative Hearings

9905The DeSoto Building

99081230 Apalachee Parkway

9911Tallahassee, Florida 32399-3060

9914(850) 488-9675 SUNCOM 278-9675

9918Fax Filing (850) 921-6847

9922www.doah.state.fl.us

9923Filed with the Clerk of the

9929Division of Administrative Hearings

9933this 24th day of July, 2000.

9939COPIES FURNISHED:

9941Kathy C. Carter, Agency Clerk

9946Office of General Counsel

9950Department of Environmental

9953Protection

99543900 Commonwealth Boulevard

9957Mail Station 35

9960Tallahassee, Florida 32399-3000

9963Teri L. Donaldson, General Counsel

9968Department of Environmental

9971Protection

99723900 Commonwealth Boulevard

9975Mail Station 35

9978Tallahassee, Florida 32399-3000

9981Ralf G. Brookes, Attorney

99851217 East Cape Coral Parkway

9990Suite 107

9992Cape Coral, Florida 33904

9996Donald D. Conn, General Counsel

10001Tampa Bay Water

100042535 Landmark Drive, Suite 211

10009Clearwater, Florida 33761

10012J. Frazier Carraway

10015Thomas A. Lash

10018Salem, Saxon & Nielson, P.A.

10023101 East Kennedy Boulevard

10027Suite 3200

10029Tampa, Florida 33601

10032Cynthia K. Christen

10035Senior Assistant General Counsel

10039Department of Environmental

10042Protection

100433900 Commonwealth Boulevard

10046Mail Station 35

10049Tallahassee, Florida 32399-3000

10052William S. Bilenky

10055General Counsel

10057Jack R. Pepper, Jr.

10061Associate General Counsel

10064Southwest Florida Water

10067Management District

100692379 Broad Street

10072Brooksville, Florida 34609-6899

10075NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

10081All parties have the right to submit written exceptions within 15

10092days from the date of this recommended order. Any exceptions to

10103this recommended order must be filed with the agency that will

10114issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 08/18/2000
Proceedings: Agency Final Order
PDF:
Date: 08/18/2000
Proceedings: Final Order filed.
PDF:
Date: 07/24/2000
Proceedings: Recommended Order
PDF:
Date: 07/24/2000
Proceedings: Recommended Order issued. CASE CLOSED. Hearing held July 7 and 10-12, 2000.
PDF:
Date: 07/21/2000
Proceedings: Tampa Bay Water`s Motion for the Award of Attorney`s Fees and Costs and Memorandum of Law filed.
PDF:
Date: 07/21/2000
Proceedings: Joint Proposed Recommended Order of Tampa Bay Water, Department of Environmental Protection and Southwest Florida Management District filed.
PDF:
Date: 07/21/2000
Proceedings: Petitioner`s Proposed Recommended Order filed.
Date: 07/19/2000
Proceedings: Transcript (Volume 1 through 9 Condensed Version) filed.
Date: 07/14/2000
Proceedings: Transcript (Volumes 1 through 9) filed.
Date: 07/07/2000
Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
PDF:
Date: 07/07/2000
Proceedings: Petitioners Unilateral Pre-Hearing Stipulation (filed via facsimile)
PDF:
Date: 07/06/2000
Proceedings: Verified Amended Petition for Formal Administrative Hearing Under Florida Statute 120.57 (filed via facsimile)
PDF:
Date: 07/06/2000
Proceedings: Motion to Verify Amended Petition for Standing Under F.S. 403.41295) (filed via facsimile)
PDF:
Date: 07/05/2000
Proceedings: Pre-hearing Stipulation (Joint) filed.
PDF:
Date: 07/05/2000
Proceedings: Ltr. to C. Wentworth from T. Lash In re: Judge`s ruling (filed via facsimile)
PDF:
Date: 07/03/2000
Proceedings: Order Granting Petition for Leave to Intervene, Denying Motion to Strike, and Denying Request for Sanctions sent out. (Southwest Florida Water Management District petition to intervene is granted)
PDF:
Date: 06/30/2000
Proceedings: Corrected Certificate of Serviced (Petitioner) (filed via facsimile)
PDF:
Date: 06/30/2000
Proceedings: Motion to Amend Petition and Response to Sanctions (Petitioner) (filed via facsimile)
PDF:
Date: 06/29/2000
Proceedings: Amended Petition for Formal Administrative Hearing Under Florida Statute 120.57 (Petitioner) filed.
PDF:
Date: 06/29/2000
Proceedings: Tampa Bay Water`s Motion to Strike Amended Petition and to Impose Sanctions (filed via facsimile)
PDF:
Date: 06/23/2000
Proceedings: Notice of Continuation of Taking Deposition Duces Tecum-R. Brookes (filed via facsimile).
PDF:
Date: 06/22/2000
Proceedings: Notice of Continuation of Taking Deposition Duces Tecum (filed via facsimile).
PDF:
Date: 06/12/2000
Proceedings: Order sent out. (respondent, Tampa bay water motion to dismiss is denied; the renewed motion for expedited scheduling of prehearing conference is denied; the motion to consolidate or hold in abeyance is denied)
PDF:
Date: 06/12/2000
Proceedings: Order of Pre-hearing Instructions sent out.
PDF:
Date: 06/12/2000
Proceedings: Notice of Hearing sent out. (hearing set for July 7, July 7 and 10 through 13, 2000; 8:00 a.m.; Tampa, FL)
PDF:
Date: 06/09/2000
Proceedings: Joint Response in Opposition to Petitioner`s Motion to Consolidate or Hold in Abeyance (J. Carraway filed via facsimile) filed.
PDF:
Date: 06/09/2000
Proceedings: Notice of Taking Deposition Duces Tecum (filed via facsimile).
PDF:
Date: 06/08/2000
Proceedings: Motion to Consolidate or Hold in Abeyance (Petitioner) filed.
PDF:
Date: 06/05/2000
Proceedings: (Respondent) Response to Initial Order filed.
PDF:
Date: 06/02/2000
Proceedings: Renewed Motion for Expedited Scheduling of Prehearing Conference (D. Conn filed via facsimile) filed.
PDF:
Date: 06/01/2000
Proceedings: Petition for Leave to Intervene in Formal Administrative Proceeding (filed via facsimile).
Date: 05/22/2000
Proceedings: Petition for Formal Administrative Hearing under Florida Statutes 120.57 filed.
PDF:
Date: 05/22/2000
Proceedings: Motion to Dismiss filed.
PDF:
Date: 05/22/2000
Proceedings: (Respondent) Motion to Expedited Consideration w/Exhibits (filed via facsimile).
Date: 05/17/2000
Proceedings: Initial Order issued.
PDF:
Date: 05/11/2000
Proceedings: Final Order Granting Petition for Variance from Rule 62-555.520 filed.
PDF:
Date: 05/11/2000
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
ROBERT E. MEALE
Date Filed:
05/11/2000
Date Assignment:
05/17/2000
Last Docket Entry:
08/18/2000
Location:
Tampa, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (6):

Related Florida Rule(s) (2):