06-000186
Donald G. Tuten vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Friday, August 11, 2006.
Recommended Order on Friday, August 11, 2006.
1Case No. 06-0186
4STATE OF FLORIDA
7DIVISION OF ADMINISTRATIVE HEARINGS
11DONALD G. TUTEN, ) ) ) ) ) ) ) ) ) ) )
25Petitioner, RECOMMENDED ORDER
28vs.
29DEPARTMENT OF ENVIRONMENTAL
32PROTECTION,
33Respondent.
34On May 2-3, 2006, a final administrative hearing was held in
45this case in West Palm Beach, Florida, before J. Lawrence
55Johnston, Administrative Law Judge, Division of Administrative
62Hearings.
63APPEARANCES
64For Petitioner: Frederick M. Dahlmeier, Esquire
70Cromwell & Dahlmeier, P.L.
74760 U.S. Highway One, Suite 301
80North Palm Beach, Florida 33408
85For Respondent: Francine M. Ffolkes, Esquire
91Department of Environmental Protection
95The Douglas Building, Mail Station 35
1013900 Commonwealth Boulevard
104Tallahassee, Florida 32399-3000
107STATEMENT OF THE ISSUE
111The issue in this case is whether, and what, reasonable
121mitigative conditions are necessary to protect the interest of
130the public and the environment, prior to issuing Petitioner's
139default permit.
141PRELIMINARY STATEMENT
143On August 31, 2000, Petitioner applied for an Environmental
152Resource Permit (ERP) to dredge an extension, 50 feet wide by 300
164feet long by 5 feet deep, to an existing man-made canal normal
176(perpendicular) to the Central and South Florida Flood Control
185(now South Florida Water Management District, or SFWMD) Rim Canal
195(the L-48 Borrow Canal), which is along the northwest shore of
206Lake Okeechobee. DEP sent a Request for Additional Information
215(RAI) on December 12, 2000, and denied the application on
225January 11, 2001--after Petitioner declined to waive the 90-day
234default period under Section 120.60(1), Florida Statutes, and
242before Petitioner responded to the RAI.
248On appeal from DEP's denial of the application, the court in
259Tuten v. Dept. of Environmental Protection , 819 So. 2d 187, 189
270(Fla. 4th DCA 2002)(Tuten I ), resolved in Petitioner's favor the
281dispute between the parties as to when the 90-day default period
292began to run; held that Petitioner was entitled to a default
303permit; and remanded "to the DEP to issue a default permit after
315a hearing to determine if conditions should be imposed to insure
326the protection of the environment."
331What happened next is described in Tuten v. Dept. of
341Environmental Protection , 906 So. 2d 1202, 1203-04 (Fla. 4th DCA
3512005)(Tuten II ):
354Almost two years later, with no default
361permit or evidentiary hearing in sight, Tuten
368filed [with the court] a Motion to Show Cause
377asking why a default permit without any
384conditions should not be granted because of
391the lack of an evidentiary hearing over this
399span of time. Eleven days later, the DEP
407issued a permit with general and specific
414conditions believed necessary to protect the
420interest of the public and the environment.
427Contained within the permit was a notice of
435Tuten's rights. Pursuant to sections 120.569
441and 120.57, Florida Statutes, the default
447permit and all conditions set forth therein
454are final unless a sufficient petition for an
462administrative hearing is timely filed (21
468days). Tuten failed to petition for an
475administrative hearing, choosing instead to
480file the instant appeal more than twenty-one
487days later, bringing the case to this court
495once again.
497We reverse the DEP's issuance of the default
505permit and remand jurisdiction to the DEP to
513allow it to conduct an evidentiary hearing on
521the issue of conditions to be placed on the
530permit. Pursuant to this court's ruling in
537Tuten I , the DEP must conduct an
544administrative hearing prior to the issuance
550of the default permit. "When the mandate was
558received by the [DEP], the [DEP] should have
566carried and placed into effect the order and
574judgment of this Court. Absent permission to
581do so, the [DEP] was without authority to
589alter or evade the mandate of this Court."
597Stuart v. Hertz Corp. , 381 So. 2d 1161, 1163
606(Fla. 4th DCA 1980).
610On January 17, 2006, DEP referred its intended ERP with
620conditions to the Division of Administrative Hearings (DOAH),
628along with Tuten II and the court's August 5, 2005, Mandate "that
640such further proceedings be had in this cause as may be in
652accordance with the opinion of this Court, and with the rules of
664procedure and with the laws of the State of Florida."
674On January 19, 2006, DEP filed a Motion for More Definite
685Statement as to Petitioner's disputed issues of material fact
694(indicating that DEP essentially viewed the court's mandate as
703merely extending the time for Petitioner to request a hearing on
714DEP's proposed permit with conditions). On January 27, 2006,
723Petitioner filed a Response in opposition and Motion to Strike
733and requested a hearing. On February 1, 2006, DEP filed a Reply
745to the Response and a Response in opposition to the Motion to
757Strike. The filings essentially disputed which party had the
766burden to plead and prove the conditions to be attached to the
778default permit. Oral argument was heard during the telephonic
787pre-hearing conference held on March 6, 2006. Based on the
797written and oral arguments, it was ruled on March 13, 2006, that
809under the appellate opinions remanding the case, DEP had the
819burden to plead and prove "'the reasonable mitigative conditions
828necessary to protect the interest of the public and the
838environment, prior to issuing a default permit.' Manasota-88,
846Inc. v. Agrico Chem. Co. , 576 So. 2d 781, 783 (Fla. 2d DCA
8591991)." In addition, it was ruled that DEP's proposed default
869permit with general and specific conditions, while reversed by
878the appellate court, was deemed to constitute DEP's pleading of
888the "reasonable mitigative conditions" DEP sought to impose on
897the default permit to be issued to the Petitioner. Finally, it
908was ruled that, in the absence of an applicable rule of procedure
920for this situation, and in order to frame the issues for
931determination at the hearing being scheduled for May 2-4, 2006,
941Petitioner was required to file a paper identifying which of
951DEP's conditions were acceptable to Petitioner, if any.
959Petitioner filed such a paper on March 24, 2006. In it,
970Petitioner denied any conditions "necessary to protect 'the
978interests of the public' unless said conditions are necessary to
988'protect the environment.'" Petitioner also admitted "that any
996of DEP's general and specific conditions, which have been
1005specifically adopted by established rule, as conditions
1012applicable to 'default permits', may attach and become conditions
1021to" the default permit. Petitioner pointed out that the 19
1031general conditions attached to DEP's suggested default permit
"1039appear to be general conditions resembling those adopted by the
1049South Florida Water Management District." Petitioner took the
1057position that, instead, the 17 general conditions set out in
1067DEP's Florida Administrative Code 1 Rules 62-4.160, entitled
"1075Permit Conditions," and 62-4.070(7) (providing that "issuance of
1083a permit does not relieve any person from complying with the
1094requirements of Chapter 403, F.S., or Department rules") would
1104apply and were acceptable to Petitioner. Petitioner apparently
1112was unaware of DEP's Rules 62-330.200(4) and 62-4.001. Rule 62-
1122330.200(4) adopts by reference SFWMD's general conditions, which
1130are contained in Rule 40E-4.381 (1995) 2 , for use in issuing
1141permits like Petitioner's; and Rule 62-4.001 provides that "the
1150provisions of this Part . . . shall not apply to activities
1162regulated under Part IV of Chapter 373, Florida Statutes."
1171Petitioner's application was for an activity regulated under Part
1180IV of Chapter 373, Florida Statutes. 3
1187The case was noticed for hearing in West Palm Beach on
1198May 2-4, 2006, and an Order of Pre-Hearing Instructions was
1208entered, which required the parties to file a pre-hearing
1217stipulation, or unilateral statements if they could not
1225stipulate.
1226In the two weeks leading up to the final hearing, Petitioner
1237filed a Motion for Continuance, a Unilateral Pre-Hearing
1245Stipulation, a Motion in Limine, and a Motion for View, and DEP
1257filed a Motion for Protective Order, a Motion for Official
1267Recognition, a Unilateral Pre-Hearing Statement, and responses in
1275opposition to Petitioner's Motion in Limine and Motion for View.
1285The Motion for Continuance was heard by telephone and denied. At
1296the outset of the final hearing, the Motion in Limine and Motion
1308for View were denied; the Motion for Protective Order was granted
1319(if not moot); and the Motion for Official Recognition was
1329granted. Petitioner also made an ore tenus motion for attorney's
1339fees under Section 120.595, Florida Statutes, and ruling was
1348reserved.
1349In its case-in-chief, DEP called: Lucy Blair, an expert in
1359the areas of biology, ecology, water quality impacts of dredging
1369and filling on water resources, and the ERP permitting rules and
1380statutes; and Calvin Alvarez, an expert in the areas of water
1391quality, biology, impacts of dredging and filling on water
1400resources, and the ERP permitting rules and statutes. DEP also
1410had DEP Exhibits 1, 2, and 7 admitted into evidence. Petitioner
1421called Gerald Ward, an expert in environmental permitting,
1429including water resources, soils, wetlands, hydrographics,
1435environmental agency process, excavation/dredging methods and
1441related engineering. Petitioner also had Petitioners Exhibits
14481, 2, 3, 4, 5, 6, 8, 12, 13, 14, 15, 16, 18, 19, and 21 admitted
1465into evidence. Ruling was reserved on DEP's relevance objection
1474to Petitioner's Exhibit 7, which is now overruled.
1482After presentation of evidence, DEP requested a transcript
1490of the final hearing, and Petitioner requested 15 days from the
1501filing of the transcript in which to file proposed recommended
1511orders (PROs), which was granted without objection. The
1519Transcript was filed (in two volumes) on June 7, 2006, making
1530PROs due to be filed June 22, 2006. However, the parties jointly
1542requested an extension until June 30, 2006, which was granted.
1552DEP timely filed its PRO, and Petitioner filed his PRO on July 3,
15652006, which included his request for attorney's fees under
1574Section 120.595, Florida Statutes. Both PROs have been
1582considered in the preparation of this Recommended Order.
1590FINDINGS OF FACT
1593A. Application and Default
15971. Petitioner's application is to dredge an extension, 50
1606feet wide by 300 feet long by 5 feet deep, to an existing 650
1620foot-long man-made canal of the same width and depth, normal
1630(perpendicular) to old Central and South Florida Flood Control
1639(now SFWMD) Rim Canal (the L-48 Borrow Canal), which is along the
1651northwest shore of Lake Okeechobee.
16562. Petitioner's initial, incomplete application filed in
1663DEP's Port St. Lucie office on August 31, 2000, included: the
1674proposed project's location by County, section, township, and
1682range; its legal description; a sketch of its general location
1692and surrounding landmarks; a SFWMD letter verifying conformity
1700with the requirements of a "No Notice General Permit for
1710Activities in Uplands" of a drawing for a proposed pond expansion
1721(to a size less than half an acre), "which will provide borrow
1733material necessary for a house pad and access drive"; a
1743description of water control Structure 127, together with its
1752purpose, operation, and flood discharge characteristics, which
1759were said to describe water levels in Buckhead Ridge, the name of
1771the subdivision where the project was proposed; two virtually
1780identical copies of a boundary survey for Petitioner's property
1789(one with legal description circled) showing the existing canal,
1798with boat basin off the canal on Petitioner's property near the
1809L-48 Rim Canal, at a scale of one inch equals 200 feet; two more
1823virtually identical copies of the boundary survey at the same
1833scale showing the existing canal, with boat basin off the canal
1844on Petitioner's property near the L-48 Rim Canal, and the
1854proposed canal extension and house locations; and a copy of a
18651996 aerial photograph of Petitioner's property and existing
1873canal, and vicinity. The application did not describe a proposed
1883method or any other details of construction, include any water
1893quality information, or include a water quality monitoring plan.
19023. On September 15, 2000, Petitioner filed an additional
1911page of the application form with DEP's Punta Gorda office. The
1922page added the information: "Digging to be done with trac-hoe."
1932No other specifics of the proposed construction method were
1941included.
19424. What happened after the filing of the application is
1952described in Tuten I and Tuten II , which are the law of the case.
1966However, those opinions do not explain the delay between Tuten I
1977and the issuance of DEP's proposed ERP with conditions
1986approximately two years later. The evidence presented at the
1995final hearing explained only that counsel of record for DEP
2005promptly asked district staff to draft a proposed default ERP
2015with conditions that "would probably track the RAI that had been
2026sent out prior to the default." DEP's district staff promptly
2036complied and forwarded the draft to DEP's Office of General
2046Counsel in Tallahassee, which did not provide any legal advice as
2057to the draft ERP for almost two years. There was no further
2069explanation for the delay.
20735. As reflected in Tuten II and in the Preliminary
2083Statement, it was DEP's position that the proper procedure to
2093follow after its default was to issue a proposed ERP with
2104conditions and that it would be Petitioner's burden to request an
2115administrative hearing to contest any conditions and to prove
2124Petitioner's entitlement to a default ERP with conditions other
2133than those in DEP's proposed ERP.
2139B. DEP's Proposed General Conditions
21446. The conditions DEP wants attached to Petitioner's
2152default permit include general conditions taken from SFWMD's Rule
216140E-4.381, which are appropriate, as indicated in the Preliminary
2170Statement and Conclusions of Law, and as conceded by Petitioner's
2180expert.
21817. While the Rule 40E-4.381 general conditions are
2189appropriate, Petitioner takes the position (and his expert
2197testified) that some of the general permit conditions contained
2206in Rule 62-4.160, as well as Rule 62-4.070(7) (providing that
"2216issuance of a permit does not relieve any person from complying
2227with the requirements of Chapter 403, F.S., or Department
2236rules"), are more appropriate general conditions to attach to
2246Petitioner's default ERP, even if technically inapplicable,
2253because the Chapter 62 Rules govern the operation of a permitted
2264project (whereas the former govern the construction of a
2273permitted project) and are "more protective of the environment."
2282Actually, all of the rules contain general conditions that govern
2292both construction and operation phases of an ERP, and all are
"2303protective of the environment." There is no reason to add
2313general conditions taken from Rules 62-4.160 and 62-4.070(7) to
2322the applicable general conditions contained in Rule 40E-4.381.
2330C. DEP's Proposed Specific Conditions
2335(i) In General
23388. The conditions DEP wants attached to Petitioner's
2346default permit also include specific conditions which essentially
2354require that Petitioner provide the information in the RAI sent
2364in December 2000, together with additional specific conditions
2372thought necessary to protect the environment in light of the lack
2383of detail in the application without the answers to the RAI.
23949. Some DEP's proposed specific conditions are designed to
2403ascertain whether the application would provide reasonable
2410assurance that permitting criteria would be met. (They make the
2420requested information subject to DEP "approval" based on whether
2429reasonable assurance is provided.) In general, those specific
2437conditions no longer are appropriate since DEP is required to
2447issue a default permit. (Looked at another way, inclusion of
2457those specific conditions effectively would un-do the default, in
2466direct contradiction of the court's opinion Tuten I and Tuten
2476II .) See Conclusion of Law 52, infra .
248510. On the other hand, some of the RAI information was
2496designed to ascertain the proposed method and other details of
2506construction. Pending the "answers" to those "RAI conditions,"
2514DEP also wants broad specific conditions, including a baseline
2523water quality investigation and a water quality monitoring plan,
2532designed to be adequate for a "worst case scenario" that could
2543result from the project.
254711. Petitioner opposes DEP's proposed broad specific
2554conditions. He takes the position that it was incumbent on DEP
2565in this proceeding to use discovery procedures to ascertain
2574Petitioner's intended method of construction and tailor specific
2582conditions to the method of construction revealed through
2590discovery. At the same time, Petitioner opposes DEP's proposed
2599specific conditions requiring RAI-type information, including the
2606details of his proposed construction method.
261212. Notwithstanding the positions Petitioner has taken in
2620this case, his expert testified that Petitioner intends to use a
2631steel wall inserted between the water and upland at the end of
2643the existing canal, phased excavation from the upland side, and
2653removal of the steel wall in the final phase of construction.
2664Assuming that method of construction, Petitioner takes the
2672position (and his expert testified) that the statutes, rules, and
2682permit conditions acceptable to Petitioner, and which generally
2690prohibit pollution of the environment, are adequate.
269713. Even if the statutes, rules, and permit conditions
2706acceptable to Petitioner would be adequate for the method of
2716construction Petitioner now says he will use, Petitioner's
2724application does not in fact commit to a method of construction.
2735All Petitioner's application says is that he intends to dig with
2746a trac-hoe. Without a binding commitment to a method of
2756construction, it was appropriate for DEP to take the position
2766that specific conditions were necessary to ascertain the method
2775of construction Petitioner would use and, pending the "answers"
2784to those "RAI conditions," and to impose broad specific
2793conditions, including a baseline water quality investigation and
2801a water quality monitoring plan, designed to be adequate for a
"2812worst case scenario" that could result from the project.
282114. In his PRO, Petitioner committed to use the
2830construction method described by his expert during the hearing,
2839as follows:
2841A. Excavation of any spoil shall be
2848done by means of a mechanical trac-hoe;
2855B. Prior to the excavation of any soil,
2863Petitioner shall first install an isolating
2869wall, such as interlocking sheet pile,
2875between the existing man-made canal, and the
2882proposed canal extension;
2885C. The mechanical excavation shall be
2891done in such a manner such that the excavated
2900soil is not deposited in wetlands or in areas
2909where it might be reasonably contemplated to
2916re-enter the waters of the State of Florida;
2924D. After the proposed canal extension
2930is excavated to its project limits in the
2938foregoing manner, the side slopes of the
2945canal extension shall be allowed to
2951revegetate prior to removal of the isolating
2958wall.
295915. With a condition imposing this method of construction,
2968fewer and narrower specific conditions will be necessary.
2976ii. Seriatim Discussion
297916. DEP's proposed Specific Condition 1 requires a
2987perpetual conservation easement prohibiting docking and mooring
2994of water craft on all portions of Petitioner's property within
3004the canal extension in order to "address cumulative impacts."
3013But DEP did not prove that the proposed conservation easement was
3024reasonably necessary to protect the interest of the public and
3034the environment. First, DEP did not prove that there would be
3045any cumulative impacts, much less unacceptable cumulative
3052impacts, from Petitioner's project. See § 373.414(8), Fla.
3060Stat.; Rule 40E-4.302(1)(b); and BOR § 4.2.8. Second, even if
3070unacceptable cumulative impacts were proven, those could be
3078addressed in other permit cases (assuming no DEP default in those
3089proceedings), since the concept of cumulative impacts essentially
3097requires an applicant to share acceptable cumulative impacts with
3106other similar permittees, applicants, and foreseeable future
3113applicants. See Broward County v. Weiss, et al. , DOAH Case No.
312401-3373, 2002 Fla. ENV LEXIS 298, at ¶¶54-58 (DOAH Aug. 27,
31352002).
313617. As Petitioner points out, the easement further
3144described in Specific Condition 1 appears to be overly broad for
3155its stated purpose in that it would cover "the legal description
3166of the entire property affected by this permit and shown on the
3178attached project drawings," which could be interpreted to include
3187not just the canal extension but the entire extended canal, or
3198even the entirety of Petitioner's 6.6 acres of property. Indeed,
3208the latter might have been the actual intention, since DEP's
3218witness testified that Specific Condition 1 also was intended to
3228address impacts from fertilizer runoff and septic tank leaching
3237from new homes built along the canal. Although some of those
3248impacts (as well as future construction of additional homes and
3258docks) actually are secondary impacts, not cumulative impacts, it
3267is possible that they can be addressed in DEP or SFWMD
3278proceedings on future applications, as well as in Department of
3288Health proceedings on septic tank installations.
329418. DEP's proposed Specific Condition 2 requires that:
3302spoil material from the dredging to be "used for the sole purpose
3314of constructing a single-family fill pad" on Petitioner's
3322property under a pending permit; spoil "be placed in a manner so
3334as not to affect wetlands or other surface waters"; and the
"3345spoil disposal location shall be shown in the drawings required
3355by Specific Condition #4 below."
336019. DEP did not prove that the first requirement was
3370reasonably necessary to protect the interest of the public and
3380the environment. First, it is unreasonable since Petitioner
3388already has built the referenced single-family fill pad and a
3398home on top of it. Second, the reason DEP's witness gave for
3410this requirement was that, under an operating agreement with
3419SFWMD (which was officially recognized), DEP only has
3427jurisdiction to take action on single-family uses (which he
3436defined to include duplexes, triplexes, and quadriplexes) but not
3445on larger multi-family and certain other projects. However, the
3454operating agreement on jurisdiction is not a reason to place
3464Specific Condition 1 on the use of spoil material on Petitioner's
3475default permit. SFWMD can regulate, in permitting proceedings
3483under its jurisdiction, the placement of fill material for multi-
3493family construction or other projects not under DEP jurisdiction.
3502In addition, under the operating agreement, jurisdiction can be
"3511swapped" by written agreement in cases where deviation from the
3521operating agreement would result in more efficient and effective
3530regulation.
353120. The second two requirements under Specific Condition 2
3540are reasonable and necessary to protect the interest of the
3550public and the environment.
355421. DEP's proposed Specific Condition 3 requires disclosure
3562of all pending and issued permits for the property from SFWMD,
3573Glades County, or the U.S. Army Corps of Engineers (USCOE). DEP
3584did not prove that this is reasonable or reasonably necessary to
3595protect the interest of the public and the environment. DEP
3605probably has all such permits and can easily obtain any it does
3617not have.
361922. DEP's proposed Specific Condition 4 requires fully
3627dimensional plan view and cross-sectional drawings of the
3635property and area to be dredged, before and after dredging,
3645including a north arrow and the water depths in and adjacent to
3657the dredge area. DEP's witness stated that the primary purpose
3667of this part of the condition is to provide hydrographic
3677information normally provided in an application (or required in
3686an RAI) so that DEP's hydrographic engineer can ascertain
3695flushing characteristics, which are pertinent primarily to the
3703dissolved oxygen water quality parameter and to heavy metals from
3713boat use. As previously indicated, requests for information
3721relating to reasonable assurance and the public interest test
3730generally no longer are appropriate since DEP is required to
3740issue a default permit. See Finding 9, supra . However,
3750information regarding flushing characteristics, combined with
3756other specific conditions, is reasonable and necessary to protect
3765the interest of the public and the environment. See Finding 27,
3776infra . 23. In addition, the plan view and cross-sectional drawings
3787required by Specific Condition 4 are to include the location of
3798navigational obstructions in the immediate area, any roads,
3806ditches, or utility lines that abut the property; any
3815encumbrances, and any associated structures. DEP's witness
3822stated that the primary purpose of this information is to
3832determine whether Petitioner has provided reasonable assurance
3839that the "public interest" test under Rule 40E-4.302 is met, and
3850make sure that management, placement, and disposal of spoil
3859material do not infringe on property rights or block culverts and
3870cause flooding. As previously indicated, requests for
3877information relating to reasonable assurance and the public
3885interest test generally no longer are appropriate. See Finding
38949, supra . However, information regarding the location of
3903culverts to assure that management of spoil does not cause
3913flooding is reasonable and necessary to protect the interest of
3923the public and the environment.
392824. In addition to objecting to having to provide RAI
3938information as a "default permittee," Petitioner's expert
3945asserted that the information requested in Specific Condition 4
3954would be provided as part of the "as-built" drawings required by
3965General Condition 6. But General Condition 6 does not require
"3975as-built" drawings. Rather, it requires an "as-built"
3982certification that can be based on "as-built" drawings or on-site
3992observation. Besides, the purpose of the "as-built"
3999certification is to determine "if the work was completed in
4009compliance with permitted plans and specifications." Without the
4017information requested in Specific Condition 4, there would only
4026be vague and general permitted plans and specifications and
4035hydrographic information.
403725. Finally as to Specific Condition 4, Petitioner objects
4046to the requirement that the drawings be sealed by a registered
4057professional engineer. However, Petitioner cites to General
4064Condition 6, which requires that the "as-built" certification be
4073given by a "registered professional" and cites Rule Form 62-
4083343.900(5), which makes it clear that "registered professional"
4091in that context means a registered professional engineer.
409926. DEP's proposed Specific Condition 5 requires Petitioner
4107to submit for DEP approval, within 180 days of permit issuance
4118and before any construction, reasonable assurance that the canal
4127extension will not violate water quality standards due to depth
4137or configuration; that it will not cause a violation of water
4148quality standards in receiving water bodies; and that it will be
4159configured to prevent creation of debris traps or stagnant areas
4169that could result in water quality violations. The reasonable
4178assurance is to include hydrographic information or studies to
4187document flushing time and an evaluation of the maximum desirable
4197flushing time, taking several pertinent factors into
4204consideration.
420527. As previously indicated, requests for information
4212relating to reasonable assurance and the public interest test
4221generally no longer are appropriate. See Finding 9, supra . In
4232addition, Petitioner's expert testified without dispute that the
4240information requested could take more than 180 days and cost
4250approximately $20,000. However, it is reasonable and necessary
4259to protect the interest of the public and the environment to
4270include a specific condition that Petitioner's canal extension be
4279configured so as have the best practicable flushing
4287characteristics.
428828. DEP's proposed Specific Condition 6 requires Petitioner
4296to submit for DEP approval, within 180 days of permit issuance
4307and before any construction, reasonable assurance that
4314construction of the canal extension will meet all permit criteria
4324set out in Rules 40E-4.301 and 40E-4.302 and in BOR § 4.1.1. As
4337previously indicated, requests for information relating to
4344reasonable assurance and the public interest test generally no
4353longer are appropriate. See Finding 9, supra .
436129. DEP's proposed Specific Condition 7 requires Petitioner
4369to submit existing water quality information for DEP approval
4378within 180 days of permit issuance and before any construction.
4388In this instance, DEP's approval would not be a determination on
4399the provision of reasonable assurance but a determination as to
4409the reliability of the water quality information, which is
4418necessary to establish a baseline for assessing and monitoring
4427the impact of the project. For that reason, the information is
4438reasonable and necessary to protect the interest of the public
4448and the environment.
445130. Petitioner's expert testified that the information
4458could cost $2,000-$3,000 to produce (and more, if DEP rejects the
4471information submitted, and more information is required). He
4479also testified that water quality information already is
4487available, including over 25 years worth of at least monthly
4497information on all pertinent parameters except biological oxygen
4505demand and fecal coliform, at a SFWMD monitoring station in the
4516Rim Canal at Structure 127 (a lock and pump station at the Hoover
4529Levee on Lake Okeechobee) approximately 8,000 feet away from
4539Petitioner's canal. DEP did not prove that the SFWMD information
4549would not serve the purpose of establishing baseline water
4558quality for Petitioner's canal for all but the missing
4567parameters. For that reason, only water quality information for
4576the missing parameters is reasonable and necessary to protect the
4586interest of the public and the environment in this case.
459631. DEP's proposed Specific Condition 8 requires that, if
4605the water quality information required by Specific Condition 7
4614shows any violations of state ambient water quality standards,
4623Petitioner must submit for DEP approval, within 180 days of
4633permit issuance and before any construction, a plan to achieve
4643net improvement for any parameters shown to be in violation, as
4654required by Section 373.414, Florida Statutes. See also BOR §
46644.2.4.1 and 4.2.4.2. Normally, if applicable, this information
4672would be expected in an application or RAI response.
4681Petitioner's expert testified that this condition would require
4689Petitioner to help "fix Buckhead Ridge" (unfairly) and that it
4699would cost lots of money. But Petitioner did not dispute that
4710the law requires a plan for a "net improvement," which does not
4722necessarily require a complete "fix" of water quality violations,
4731if any. As previously indicated, requests for information
4739relating to reasonable assurance and the public interest test
4748generally no longer are appropriate, and Petitioner's ability to
4757construct the canal extension should not be dependent on DEP's
4767approval of a net improvement plan. See Finding 9, supra . But a
4780specific condition that Petitioner implement a plan to achieve
4789net water quality improvement in the event of any water quality
4800violations would be reasonable and necessary to protect the
4809interest of the public and the environment.
481632. DEP's proposed Specific Condition 9 requires Petitioner
4824to submit for DEP's approval, at least 60 days before
4834construction, detailed information on how Petitioner intends to
4842prevent sediments and contaminants from being released into
4850jurisdictional waters. DEP asserts that this specific condition
4858asks for a detailed description of how the applicant will comply
4869with various subsections of BOR § 4.2.4.1 that address short-term
4879water quality to aid in providing reasonable assurance that water
4889quality standards will not be violated, as required by Section
4899373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e). As
4906previously indicated, requests for information relating to
4913reasonable assurance and the public interest test generally no
4922longer are appropriate, and Petitioner's ability to construct the
4931canal extension should not be dependent on DEP's approval of
4941information submitted. See Finding 9, supra . But it is
4951reasonable and necessary to protect the interest of the public
4961and the environment to include a specific condition that
4970Petitioner's canal extension be constructed using adequate
4977turbidity barriers; stabilize newly created slopes or surfaces in
4986or adjacent to wetlands and other surface waters to prevent
4996erosion and turbidity; avoid propeller dredging and rutting from
5005vehicular traffic; maintain construction equipment to ensure that
5013oils, greases, gasoline, or other pollutants are not released
5022into wetlands and other surface waters; and prevent any other
5032discharges during construction that will cause water quality
5040violations.
504133. DEP's proposed Specific Condition 10 requires
5048Petitioner to submit, at least 60 days before construction,
5057detailed information regarding Petitioner's plans for handling
5064spoil from dredging, including "discharge details, locations
5071retention plans, volumes, and data used to size the disposal
5081cell(s)." It allows this information to be combined with the
5091Specific Condition 2 submittal. It also requires spoil to be
5101properly contained to prevent return of spoil to waters of the
5112State and to be deposited in a self-contained upland site that
5123prevents return of any water or material into waters of the
5134State.
513534. DEP asserts that this specific condition (like Specific
5144Condition 9) is necessary to comply with BOR § 4.2.4.1 by
5155addressing short-term water quality to aid in providing
5163reasonable assurance that water quality standards will not be
5172violated, as required by Section 373.414(1), Florida Statutes,
5180and Rule 40E-4.301(1)(e). As previously indicated, requests for
5188information relating to reasonable assurance and the public
5196interest test generally no longer are appropriate, and
5204Petitioner's ability to construct the canal extension should not
5213be dependent on DEP's approval of information submitted. See
5222Finding 9, supra . But it is reasonable and necessary to protect
5234the interest of the public and the environment to include a
5245specific condition requiring spoil to be properly contained to
5254prevent return of spoil to waters of the State and to be
5266deposited in a self-contained upland site that prevents return of
5276any water or material into waters of the State.
528535. DEP's proposed Specific Condition 11 requires
5292Petitioner to submit "as-built" drawings to DEP's Punta Gorda
5301office with 30 days after completion of construction, "as
5310required by General Condition #6." Petitioner's expert testified
5318that this condition was unreasonable only because it duplicates
5327General Condition 6 and two statutes. But General Condition 6
5337actually does not require "as-built" drawings, see Finding 9,
5346supra , and it is not clear what statutes Petitioner's expert was
5357referring to. For these reasons, and because it provides a
5367filing location, Specific Condition 11 is reasonable and
5375reasonably necessary to protect the interest of the public and
5385the environment.
538736. DEP's proposed Specific Condition 12 requires
5394Petitioner to "maintain the permitted canal free of all rafted
5404debris by removal and property upland disposal." DEP asserts
5413that this specific condition is necessary to comply with BOR §
54244.2.4.2 by addressing long-term water quality to aid in providing
5434reasonable assurance that water quality standards will not be
5443violated, as required by Section 373.414(1), Florida Statutes,
5451and Rule 40E-4.301(1)(e). Rafted debris, which may be of an
5461organic or inorganic nature, can accumulate at the end of canals
5472due to wind, waves, boats, or other forces. Such organic rafted
5483debris may rot and, by creating a high biological oxygen demand,
5494rob the water of dissolved oxygen. Petitioner's only expressed
5503opposition to this condition is that the conservation easement in
5513Specific Condition 3 might prevent compliance. While it is
5522unclear how the easement would prevent compliance, the issue is
5532eliminated if no conservation easement is required.
553937. DEP's proposed Specific Condition 13 requires
5546Petitioner to use turbidity screens during construction for
5554compliance with BOR § 4.2.4.1 by addressing short-term water
5563quality to aid in providing reasonable assurance that water
5572quality standards will not be violated, as required by Section
5582373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e). The
5589turbidity screen requirements detailed in this specific condition
5597are typical best management practices that contractors use and
5606are a standard condition placed in permits of this nature by DEP.
5618Petitioner contends that turbidity screens are unnecessary given
5626his intended construction method and that other conditions are
5635sufficient to cover DEP's concerns. However, as indicated, the
5644application does not commit to a method of construction. With
5654the application in its current state, Specific Condition 13 is
5664appropriate subject to a demonstration by Petitioner that
5672turbidity screens are not needed for the construction method
5681committed to in Petitioner's PRO.
568638. DEP's proposed Specific Condition 14 requires
5693Petitioner to "ensure that any discharge or release of pollutants
5703during construction or alteration are not released into wetlands
5712or other surface waters that will cause water quality standards
5722to be violated." Again, this condition is intended to ensure
5732compliance with BOR § 4.2.4.1 by addressing short-term water
5741quality to aid in providing reasonable assurance that water
5750quality standards will not be violated, as required by Section
5760373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e). While
5767this specific condition seems general and perhaps duplicates
5775other conditions (which was Petitioner's only point of
5783contention), DEP added it in an attempt to make sure the possible
5795and not uncommon release of pollutants from construction
5803equipment was addressed. As such, the condition is appropriate.
581239. DEP's proposed Specific Condition 15 provides details
5820on the use of turbidity screens. Petitioner's primary points of
5830contention are that turbidity screens are not needed for his
5840intended construction method and that other conditions are
5848sufficient without this condition. As such, the relevant issues
5857already have been addressed in connection with Specific Condition
586613. With the application in its current state, Specific
5875Condition 15 is appropriate subject to a demonstration by
5884Petitioner that turbidity screens are not needed for the
5893construction method committed to in Petitioner's PRO.
590040. DEP's proposed Specific Condition 16 requires
5907Petitioner to used staked filter cloth to contain any turbid run-
5918off and erosion from created slopes of the canal extension. This
5929is the most common best management practice and is a standard
5940condition for ERP permits dealing with side slopes that may
5950affect water quality. Unstable slopes can result in chronic
5959turbidity, which is detrimental to wildlife. Unstable slopes
5967also can lead to upland runoff being deposited into the water
5978along with debris and sediment. Such runoff can bring
5987deleterious substances such as heavy metals and nutrient-loaded
5995substances that might impact dissolved oxygen levels in the
6004water.
600541. Petitioner's primary points of contention on Specific
6013Condition 16 are that, like turbidity screens, staked filter
6022cloth is not needed for Petitioner's intended construction method
6031and that other conditions are sufficient without this condition.
6040(Petitioner also questions why the condition gives Petitioner up
6049to 72 hours from "attaining final grade" to stabilize side
6059slopes, but the condition also requires side slope stabilization
"6068as soon as possible," and the 72-hour outside limit seems
6078reasonable.) As such, the relevant issues already have been
6087addressed in connection with Specific Condition 13 and 15. With
6097the application in its current state, Specific Condition 16 is
6107appropriate subject to a demonstration by Petitioner that staked
6116filter cloth is not needed if he uses the construction method
6127committed to in Petitioner's PRO.
613242. DEP's proposed Specific Condition 17, 18, 19, and 20:
6142details required long-term water quality monitoring and reporting
6150[#17]; establishes sampling intervals and requires Petitioner to
6158submit a "plan to remediate" if monitoring shows water quality
6168violations or "a trend toward future violations of water quality
6178standards directly related to the permitted canal" [#18]; allows
"6187additional water quality treatment methods" to be required if
6196water quality monitoring shows it to be necessary [#19]; and
6206allows water quality monitoring requirements to be modified
6214(which "may include reduction in frequency and parameters . . .
6225or the release of the monitoring process"), "based on long term
6237trends indicate that the permitted canal is not a source to
6248create water quality violations [#20]." These conditions are
6256intended to ensure compliance with BOR § 4.2.4.2 by addressing
6266long-term water quality to aid in providing reasonable assurance
6275that water quality standards will not be violated, as required by
6286Section 373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e).
629343. The evidence was that these specific conditions are
6302standard for ERP permits where a constructed system may lead to
6313water quality violations in the long term. Contrary to
6322Petitioner's contentions, conditions of this kind are not
6330dependent on a post-construction finding of water quality
6338standard violations (even though DEP defaulted on Petitioner's
6346application). Besides contending that monitoring requirements in
6353Specific Conditions 17 and 18 are unnecessary, Petitioner also
6362contends that they are too extensive and not tailored to
6372Petitioner's intended construction, but DEP proved their
6379necessity, even assuming the construction method committed to in
6388Petitioner's PRO. Petitioner complains that Specific Condition
639519 is vague and that Petitioner's ERP does not provide for "water
6407quality treatment." But the present absence of post-construction
6415water quality treatment should not preclude the possible future
6424imposition of some kind of water quality treatment if monitoring
6434shows it to be necessary. For this kind of condition, the
6445absence of detail regarding the kind of treatment to be imposed
6456is natural since it would depend on future events.
646544. DEP's proposed Specific Condition 21 merely requires
6473that Petitioner's project comply with State water quality
6481standards in Florida Administrative Code Rules 62-302.500 and 62-
6490302.530. Petitioner contends that this is duplicative and
6498unnecessary. But it certainly is not unreasonable to be specific
6508in this regard.
6511D. No Improper Purpose
651545. As part of his request for attorney's fees under
6525Section 120.595, Florida Statutes, Petitioner necessarily
6531contends that DEP participated in this proceeding "for an
6540improper purpose"--i.e. , "primarily to harass or to cause
6549unnecessary delay or for frivolous purpose or to needlessly
6558increase the cost of litigation, licensing, or securing the
6567approval of an activity." Even assuming that DEP should be
6577considered a "nonprevailing adverse party," Petitioner's evidence
6584did not prove that DEP's participation was for an "improper
6594purpose." To the contrary, DEP "participated" initially because
6602Petitioner filed an application. DEP's denial of Petitioner's
6610application was not proven to be "for an improper purpose" but
6621rather for the purpose of attempting to protect the environment.
6631The propriety of the denial was litigated in Tuten I , which made
6643no finding that the denial was "for an improper purpose" and
6654which ordered DEP to participate in a hearing for purposes of
6665determining "reasonable mitigative conditions." The two-year
6671delay between Tuten I and Tuten II was not fully explained, but
6683Tuten II also made no finding that the denial, or the delay, or
6696DEP's proposed ERP with conditions were "for an improper purpose"
6706and again ordered DEP to participate in a hearing for purposes of
6718determining "reasonable mitigative conditions." While DEP's
6724views on the nature of the hearing to be conducted for purposes
6736of determining "reasonable mitigative conditions" was rejected,
6743it was not proven that DEP argued its views "for an improper
6755purpose" or that its participation, once its views were rejected,
6765was "for an improper purpose," as defined by statute. To the
6776contrary, the evidence was that DEP participated in this
6785proceeding in an attempt to place conditions on Petitioner's
6794permit which DEP thought were necessary to protect the
6803environment, many (although not all) of which are accepted in
6813this Recommended Order.
681646. As Petitioner accepts and points out, it remains
6825necessary for Petitioner to construct and operate his project in
6835a manner that does not violate environmental statutes and rules.
6845But without any water quality information or monitoring, DEP's
6854enforcement of those laws and rules will be hamstrung.
6863CONCLUSIONS OF LAW
686647. Tuten I and Tuten II are the law of the case. Under
6879those decisions, the issue for determination in this case is
6889whether, and what, reasonable mitigative conditions are necessary
6897to protect the interest of the public and the environment, prior
6908to issuing Petitioner's default permit.
691348. As reflected in the Preliminary Statement, it is
6922concluded that DEP has the burden to plead and prove "'the
6933reasonable mitigative conditions necessary to protect the
6940interest of the public and the environment, prior to issuing a
6951default permit.' Manasota-88, Inc. v. Agrico Chem. Co. , 576
6960So. 2d 781, 783 (Fla. 2d DCA 1991)." DEP's proposed default
6971permit with general and specific conditions, while reversed by
6980the appellate court in Tuten II , was deemed to constitute DEP's
6991pleading of the "reasonable mitigative conditions" DEP seeks to
7000impose on the default permit to be issued to the Petitioner.
701149. DEP's proposed General Conditions 1-19 are taken from
7020Rule 40E-4.381, which DEP adopted by reference under Rule 62-
7030330.200(4). These conditions apply to and are binding on all ERP
7041permits located within the geographic jurisdiction of the SFWMD,
7050unless waived or modified upon a determination that the
7059conditions are inapplicable to the activity authorized by the
7068permit. In the absence of such a determination, these General
7078Conditions are standard conditions, and they are substantive
7087requirements of [the applicable permitting statute]. See
7094generally Op. Atty Gen. Fla. 78-169 (1978). Ultimately,
7102Petitioner agreed to General Conditions 1-19.
710850. DEP's Rule 62-4.001 states that the provisions of this
7118Part . . . shall not apply to activities regulated under Part IV
7131of Chapter 373, F.S. Tutens proposed canal extension is an
7141activity regulated under Part IV of Chapter 373, Florida
7150Statutes. Therefore, contrary to Petitioner's contention, the
7157provisions of Rule Chapter 62-4, Part I, including the permit
7167conditions contained in Rules 62-4.070(7) and 62-4.160, do not
7176apply in this case.
718051. Rule 40E-4.381(2) provides:
7184In addition to those general conditions set
7191forth in subsection (1), the Governing Board
7198shall impose on any permit granted under this
7206chapter and chapter 40E-40 F.A.C., such
7212reasonable project-specific special
7215conditions as are necessary to assure that
7222the permitted system will not be inconsistent
7229with the overall objectives of the District
7236or will not be harmful to the water resources
7245of the District, as set forth in District
7253rules.
725452. DEP contends that Rule 40E-4.381(2), along with
7262Attorney General Opinion 78-169, authorizes the imposition of
7270requirements that Petitioner provide RAI responses and reasonable
7278assurance of compliance with permitting criteria under Rules 40E-
72874.301, entitled "Conditions for Issuance of Permits," and 40E-
72964.302, entitled "Additional Conditions for Issuance of Permits."
7304But it is concluded that those permitting criteria do not apply
7315to default permits and are not the kind of "standard conditions"
7326referred to in Attorney General Opinion 78-169, which answered
7335the specific question:
7338May an agency place as conditions in a
7346default license issued pursuant to
7351s.120.60(2), F.S., standard conditions such
7356as the reporting of water quality violations,
7363periodic operating reports, and monitoring
7368requirements which are routinely placed in
7374agency licenses which do not call for project
7382design changes, or impose other such
7388substantive requirements of Ch. 403, F.S., or
7395rules duly adopted thereunder?
7399Otherwise, the default statute would be rendered meaningless, and
7408instruction of Tuten I and Tuten II to determine the "reasonable
7419mitigative conditions [that] are necessary to protect the
7427interest of the public and the environment" would be ignored.
743753. On the other hand, as found, other specific conditions
7447proposed by DEP are "reasonable mitigative conditions [that] are
7456necessary to protect the interest of the public and the
7466environment." Specifically, Specific Conditions 4, 5, and 11-21
7474are reasonable as proposed. Specific Conditions 2 and 5-10, as
7484modified by the Findings of Fact, are appropriate.
749254. Attorney's fees under Section 120.595(1), Florida
7499Statutes, may be awarded only upon a finding that the
"7509nonprevailing adverse party" participated in the proceeding "for
7517an improper purpose," defined as "primarily to harass or to cause
7528unnecessary delay or for frivolous purpose or to needlessly
7537increase the cost of litigation, licensing, or securing the
7546approval of an activity." Based on the findings, Petitioner's
7555request for such an award from DEP should be denied in this case.
7568RECOMMENDATION
7569Based upon the foregoing Findings of Fact and Conclusions of
7579Law, it is
7582RECOMMENDED that DEP enter a final order issuing Petitioner
7591a default ERP, to expire five years from issuance, to dredge an
7603extension, 50 feet wide by 300 feet long by 5 feet deep, to an
7617existing man-made canal, as applied for, subject to: DEP's
7626proposed General Conditions 1-19; DEP's proposed Specific
7633Conditions 4 and 11-21; DEP's proposed Specific Conditions 2, 5,
7643and 7-10, as modified by the Findings of Fact; and the
7654construction method committed to in Petitioner's PRO (see Finding
766314, supra .
7666DONE AND ENTERED this 11th day of August, 2006, in
7676Tallahassee, Leon County, Florida.
7680S
7681J. LAWRENCE JOHNSTON
7684Administrative Law Judge
7687Division of Administrative Hearings
7691The DeSoto Building
76941230 Apalachee Parkway
7697Tallahassee, Florida 32399-3060
7700(850) 488-9675 SUNCOM 278-9675
7704Fax Filing (850) 921-6847
7708www.doah.state.fl.us
7709Filed with the Clerk of the
7715Division of Administrative Hearings
7719this 11th day of August, 2006.
7725ENDNOTES
77261 / Except for Rule Chapter 40E-4, or unless otherwise stated,
7737all Rule references are to the current version of the Florida
7748Administrative Code.
77502 / All references to Rule Chapter 40E-4 are to the 1995 version
7763of the Rule, which is the version adopted by Rule 62-330.200(4).
77743 / Unless otherwise stated, all statutory references are to the
77852005 codification of the Florida Statutes.
7791COPIES FURNISHED :
7794Lea Crandall, Agency Clerk
7798Department of Environmental Protection
7802The Douglas Building, Mail Station 35
78083900 Commonwealth Boulevard
7811Tallahassee, Florida 32399-3000
7814Greg Munson, General Counsel
7818Department of Environmental Protection
7822The Douglas Building, Mail Station 35
78283900 Commonwealth Boulevard
7831Tallahassee, Florida 32399-3000
7834Colleen M. Castille, Secretary
7838Department of Environmental Protection
7842The Douglas Building
78453900 Commonwealth Boulevard
7848Tallahassee, Florida 32399-3000
7851Francine M. Ffolkes, Esquire
7855Department of Environmental Protection
7859The Douglas Building, Mail Station 35
78653900 Commonwealth Boulevard
7868Tallahassee, Florida 32399-3000
7871Frederick M. Dahlmeier, Esquire
7875Cromwell & Dahlmeier, P.L.
7879760 U.S. Highway One, Suite 301
7885North Palm Beach, Florida 33408
7890NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
7896All parties have the right to submit written exceptions within 15
7907days from the date of this Recommended Order. Any exceptions to
7918this Recommended Order should be filed with the agency that will
7929issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/07/2008
- Proceedings: BY ORDER OF THE COURT: Appellant`s motion filed June 9, 2008, for rehearing is hereby denied filed.
- PDF:
- Date: 05/30/2008
- Proceedings: BY ORDER OF THE COURT: Appellant`s motion filed February 14, 2008, for attorney`s fees and costs is hereby denied filed.
- PDF:
- Date: 02/19/2008
- Proceedings: BY ORDER OF THE COURT: Appellant`s third motion for extension of tme is granted.
- PDF:
- Date: 01/07/2008
- Proceedings: BY ORDER OF THE COURT: Appellant`s motion for extension of time is granted.
- PDF:
- Date: 11/26/2007
- Proceedings: BY ORDER OF THE COURT: appellant`s first motion for extension of time is granted filed.
- PDF:
- Date: 10/09/2007
- Proceedings: BY ORDER OF THE COURT: Appellee`s unopposed motion filed September 28, 2007 for fourth extension of time is granted.
- PDF:
- Date: 09/04/2007
- Proceedings: BY ORDER OF THE COURT: Appellee`s motion for third extension of time is granted.
- PDF:
- Date: 07/23/2007
- Proceedings: BY ORDER OF THE COURT: Appellee`s motion for extension of time is granted.
- PDF:
- Date: 06/28/2007
- Proceedings: BY ORDER OF THE COURT: Appellee`s unopposed motion filed June 20, 2007, for extension of time is granted.
- PDF:
- Date: 05/09/2007
- Proceedings: BY ORDER OF THE COURT: Appellant`s motion for extension of time is granted.
- PDF:
- Date: 04/04/2007
- Proceedings: BY ORDER OF THE COURT: Appellant`s third motion for extension of time is granted.
- PDF:
- Date: 03/02/2007
- Proceedings: BY ORDER OF THE COURT: Appellant`s second motion for extension of time is granted.
- PDF:
- Date: 01/29/2007
- Proceedings: BY ORDER OF THE COURT: Appellant`s motion for extension of time is granted.
- PDF:
- Date: 10/17/2006
- Proceedings: Order Denying Petitioner`s Motion to Remand and Request for Hearing filed with the Department of Environmental Protection.
- PDF:
- Date: 10/17/2006
- Proceedings: Order Granting Second Request for Extension of Time to File Exceptions to Recommended Order and Extending Time for Entry of Agency Final Order filed with the Department of Environmental Protection.
- PDF:
- Date: 10/17/2006
- Proceedings: Order Extending Time for Filing Exceptions to Recommended Order and Extending Time for Entry of Agency Final Order filed with the Department of Environmental Protection.
- PDF:
- Date: 09/26/2006
- Proceedings: DEP`s Response to Petitioner`s Exceptions to Recommended Order filed.
- PDF:
- Date: 09/25/2006
- Proceedings: DEP`s Response in Opposition to Tuten`s Request for Hearing filed.
- PDF:
- Date: 09/11/2006
- Proceedings: Petitioner`s Request for Extension of Time to File Exceptions to Recommended Order filed by Petitioner.
- PDF:
- Date: 09/01/2006
- Proceedings: Petitioner`s Request for Extension of Time to File Exceptions to Recommended Order filed.
- PDF:
- Date: 08/25/2006
- Proceedings: Petitioner`s Request for Extension of Time to File Exceptions to Recommended Order filed.
- PDF:
- Date: 08/11/2006
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 07/03/2006
- Proceedings: Corrected Pages 15 and 16 of Petitioner`s Proposed Recommended Order filed.
- PDF:
- Date: 06/30/2006
- Proceedings: Proposed Recommended Order of State of Florida Department of Environmental Protection filed.
- PDF:
- Date: 06/23/2006
- Proceedings: Order Granting Extension of Time (proposed recommended orders to be filed by June 30, 2006).
- PDF:
- Date: 06/23/2006
- Proceedings: Joint Motion for Extension of Time to file Proposed Recommended Orders filed.
- Date: 06/07/2006
- Proceedings: Transcript (May 2 and 3, 2006) filed.
- Date: 05/02/2006
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 04/25/2006
- Proceedings: Notice and Certificate of Service of Respondent DEP`s Answers to Donald G. Tuten`s First Set of Interrogatories filed.
- PDF:
- Date: 04/25/2006
- Proceedings: DEP`s Response to Tuten`s First Request for Production of Documents filed.
- PDF:
- Date: 04/19/2006
- Proceedings: Respondent Department of Protection`s Notice of Taking Deposition Duces Tecum filed.
- PDF:
- Date: 04/19/2006
- Proceedings: Respondent Department of Environmental Protection`s Notice of Taking Deposition Duces Tecum filed.
- PDF:
- Date: 04/19/2006
- Proceedings: Petitioner`s Response to Respondent`s First Request for Production of Documents filed.
- PDF:
- Date: 04/11/2006
- Proceedings: Donald G. Tuten`s Motion for Extension of Time to Respond to First Request for Production and First Set of Interrogatories filed.
- PDF:
- Date: 03/27/2006
- Proceedings: Notice of Corrected Certificate of Service of Petitioner`s Response to DEP`s Pleading of Reasonable Mitigative Conditions filed.
- PDF:
- Date: 03/27/2006
- Proceedings: Donald G. Tuten`s First Request for Production of Documents to Department of Environmental Protection filed.
- PDF:
- Date: 03/27/2006
- Proceedings: Donald G. Tuten`s First Set of Interrogatories to Department of Environmental Protection filed.
- PDF:
- Date: 03/24/2006
- Proceedings: Petitioner`s Response to DEP`s Pleading of Reasonable Mitigative Conditions filed.
- PDF:
- Date: 03/13/2006
- Proceedings: Notice of Hearing (hearing set for May 2 through 4, 2006; 9:00 a.m.; West Palm Beach, FL).
- PDF:
- Date: 03/13/2006
- Proceedings: Order on Pending Motions (Petitioner shall file a paper within ten days identifying which of DEP`s conditions are acceptable to the Petitioner, if any).
- PDF:
- Date: 03/10/2006
- Proceedings: Respondent Department of Environmental Protection`s First Request for Production of Documents to Petitioner, Donald G. Tuten filed.
- PDF:
- Date: 03/10/2006
- Proceedings: Notice and Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Donald G. Tuten filed.
- PDF:
- Date: 02/21/2006
- Proceedings: Notice of Telephonic Pre-hearing Conference (set for March 6, 2006; 10:00 a.m.).
- PDF:
- Date: 02/01/2006
- Proceedings: DEP`s Response to Petitioner Tuten`s Motion to Strike, and Reply to Petitioner Tuten`s Response to DEP`s Motion filed.
- PDF:
- Date: 01/30/2006
- Proceedings: Notice of Telephonic Pre-hearing Conference (set for February 2, 2006; 2:00 p.m.).
- PDF:
- Date: 01/27/2006
- Proceedings: Motion to Strike DEP`s Motion for More Definite Statement and Request for Hearing filed.
Case Information
- Judge:
- J. LAWRENCE JOHNSTON
- Date Filed:
- 01/17/2006
- Date Assignment:
- 01/18/2006
- Last Docket Entry:
- 07/28/2008
- Location:
- West Palm Beach, Florida
- District:
- Southern
Counsels
-
Frederick M. Dahlmeier, Esquire
Address of Record -
Francine M. Ffolkes, Esquire
Address of Record