06-000186 Donald G. Tuten vs. Department Of Environmental Protection
 Status: Closed
Recommended Order on Friday, August 11, 2006.


View Dockets  
Summary: Respondent proved that some but not all conditions attached to the default permit were reasonable and necessary to protect the environment.

1Case No. 06-0186

4STATE OF FLORIDA

7DIVISION OF ADMINISTRATIVE HEARINGS

11DONALD G. TUTEN, ) ) ) ) ) ) ) ) ) ) )

25Petitioner, RECOMMENDED ORDER

28vs.

29DEPARTMENT OF ENVIRONMENTAL

32PROTECTION,

33Respondent.

34On May 2-3, 2006, a final administrative hearing was held in

45this case in West Palm Beach, Florida, before J. Lawrence

55Johnston, Administrative Law Judge, Division of Administrative

62Hearings.

63APPEARANCES

64For Petitioner: Frederick M. Dahlmeier, Esquire

70Cromwell & Dahlmeier, P.L.

74760 U.S. Highway One, Suite 301

80North Palm Beach, Florida 33408

85For Respondent: Francine M. Ffolkes, Esquire

91Department of Environmental Protection

95The Douglas Building, Mail Station 35

1013900 Commonwealth Boulevard

104Tallahassee, Florida 32399-3000

107STATEMENT OF THE ISSUE

111The issue in this case is whether, and what, reasonable

121mitigative conditions are necessary to protect the interest of

130the public and the environment, prior to issuing Petitioner's

139default permit.

141PRELIMINARY STATEMENT

143On August 31, 2000, Petitioner applied for an Environmental

152Resource Permit (ERP) to dredge an extension, 50 feet wide by 300

164feet long by 5 feet deep, to an existing man-made canal normal

176(perpendicular) to the Central and South Florida Flood Control

185(now South Florida Water Management District, or SFWMD) Rim Canal

195(the L-48 Borrow Canal), which is along the northwest shore of

206Lake Okeechobee. DEP sent a Request for Additional Information

215(RAI) on December 12, 2000, and denied the application on

225January 11, 2001--after Petitioner declined to waive the 90-day

234default period under Section 120.60(1), Florida Statutes, and

242before Petitioner responded to the RAI.

248On appeal from DEP's denial of the application, the court in

259Tuten v. Dept. of Environmental Protection , 819 So. 2d 187, 189

270(Fla. 4th DCA 2002)(Tuten I ), resolved in Petitioner's favor the

281dispute between the parties as to when the 90-day default period

292began to run; held that Petitioner was entitled to a default

303permit; and remanded "to the DEP to issue a default permit after

315a hearing to determine if conditions should be imposed to insure

326the protection of the environment."

331What happened next is described in Tuten v. Dept. of

341Environmental Protection , 906 So. 2d 1202, 1203-04 (Fla. 4th DCA

3512005)(Tuten II ):

354Almost two years later, with no default

361permit or evidentiary hearing in sight, Tuten

368filed [with the court] a Motion to Show Cause

377asking why a default permit without any

384conditions should not be granted because of

391the lack of an evidentiary hearing over this

399span of time. Eleven days later, the DEP

407issued a permit with general and specific

414conditions believed necessary to protect the

420interest of the public and the environment.

427Contained within the permit was a notice of

435Tuten's rights. Pursuant to sections 120.569

441and 120.57, Florida Statutes, the default

447permit and all conditions set forth therein

454are final unless a sufficient petition for an

462administrative hearing is timely filed (21

468days). Tuten failed to petition for an

475administrative hearing, choosing instead to

480file the instant appeal more than twenty-one

487days later, bringing the case to this court

495once again.

497We reverse the DEP's issuance of the default

505permit and remand jurisdiction to the DEP to

513allow it to conduct an evidentiary hearing on

521the issue of conditions to be placed on the

530permit. Pursuant to this court's ruling in

537Tuten I , the DEP must conduct an

544administrative hearing prior to the issuance

550of the default permit. "When the mandate was

558received by the [DEP], the [DEP] should have

566carried and placed into effect the order and

574judgment of this Court. Absent permission to

581do so, the [DEP] was without authority to

589alter or evade the mandate of this Court."

597Stuart v. Hertz Corp. , 381 So. 2d 1161, 1163

606(Fla. 4th DCA 1980).

610On January 17, 2006, DEP referred its intended ERP with

620conditions to the Division of Administrative Hearings (DOAH),

628along with Tuten II and the court's August 5, 2005, Mandate "that

640such further proceedings be had in this cause as may be in

652accordance with the opinion of this Court, and with the rules of

664procedure and with the laws of the State of Florida."

674On January 19, 2006, DEP filed a Motion for More Definite

685Statement as to Petitioner's disputed issues of material fact

694(indicating that DEP essentially viewed the court's mandate as

703merely extending the time for Petitioner to request a hearing on

714DEP's proposed permit with conditions). On January 27, 2006,

723Petitioner filed a Response in opposition and Motion to Strike

733and requested a hearing. On February 1, 2006, DEP filed a Reply

745to the Response and a Response in opposition to the Motion to

757Strike. The filings essentially disputed which party had the

766burden to plead and prove the conditions to be attached to the

778default permit. Oral argument was heard during the telephonic

787pre-hearing conference held on March 6, 2006. Based on the

797written and oral arguments, it was ruled on March 13, 2006, that

809under the appellate opinions remanding the case, DEP had the

819burden to plead and prove "'the reasonable mitigative conditions

828necessary to protect the interest of the public and the

838environment, prior to issuing a default permit.' Manasota-88,

846Inc. v. Agrico Chem. Co. , 576 So. 2d 781, 783 (Fla. 2d DCA

8591991)." In addition, it was ruled that DEP's proposed default

869permit with general and specific conditions, while reversed by

878the appellate court, was deemed to constitute DEP's pleading of

888the "reasonable mitigative conditions" DEP sought to impose on

897the default permit to be issued to the Petitioner. Finally, it

908was ruled that, in the absence of an applicable rule of procedure

920for this situation, and in order to frame the issues for

931determination at the hearing being scheduled for May 2-4, 2006,

941Petitioner was required to file a paper identifying which of

951DEP's conditions were acceptable to Petitioner, if any.

959Petitioner filed such a paper on March 24, 2006. In it,

970Petitioner denied any conditions "necessary to protect 'the

978interests of the public' unless said conditions are necessary to

988'protect the environment.'" Petitioner also admitted "that any

996of DEP's general and specific conditions, which have been

1005specifically adopted by established rule, as conditions

1012applicable to 'default permits', may attach and become conditions

1021to" the default permit. Petitioner pointed out that the 19

1031general conditions attached to DEP's suggested default permit

"1039appear to be general conditions resembling those adopted by the

1049South Florida Water Management District." Petitioner took the

1057position that, instead, the 17 general conditions set out in

1067DEP's Florida Administrative Code 1 Rules 62-4.160, entitled

"1075Permit Conditions," and 62-4.070(7) (providing that "issuance of

1083a permit does not relieve any person from complying with the

1094requirements of Chapter 403, F.S., or Department rules") would

1104apply and were acceptable to Petitioner. Petitioner apparently

1112was unaware of DEP's Rules 62-330.200(4) and 62-4.001. Rule 62-

1122330.200(4) adopts by reference SFWMD's general conditions, which

1130are contained in Rule 40E-4.381 (1995) 2 , for use in issuing

1141permits like Petitioner's; and Rule 62-4.001 provides that "the

1150provisions of this Part . . . shall not apply to activities

1162regulated under Part IV of Chapter 373, Florida Statutes."

1171Petitioner's application was for an activity regulated under Part

1180IV of Chapter 373, Florida Statutes. 3

1187The case was noticed for hearing in West Palm Beach on

1198May 2-4, 2006, and an Order of Pre-Hearing Instructions was

1208entered, which required the parties to file a pre-hearing

1217stipulation, or unilateral statements if they could not

1225stipulate.

1226In the two weeks leading up to the final hearing, Petitioner

1237filed a Motion for Continuance, a Unilateral Pre-Hearing

1245Stipulation, a Motion in Limine, and a Motion for View, and DEP

1257filed a Motion for Protective Order, a Motion for Official

1267Recognition, a Unilateral Pre-Hearing Statement, and responses in

1275opposition to Petitioner's Motion in Limine and Motion for View.

1285The Motion for Continuance was heard by telephone and denied. At

1296the outset of the final hearing, the Motion in Limine and Motion

1308for View were denied; the Motion for Protective Order was granted

1319(if not moot); and the Motion for Official Recognition was

1329granted. Petitioner also made an ore tenus motion for attorney's

1339fees under Section 120.595, Florida Statutes, and ruling was

1348reserved.

1349In its case-in-chief, DEP called: Lucy Blair, an expert in

1359the areas of biology, ecology, water quality impacts of dredging

1369and filling on water resources, and the ERP permitting rules and

1380statutes; and Calvin Alvarez, an expert in the areas of water

1391quality, biology, impacts of dredging and filling on water

1400resources, and the ERP permitting rules and statutes. DEP also

1410had DEP Exhibits 1, 2, and 7 admitted into evidence. Petitioner

1421called Gerald Ward, an expert in environmental permitting,

1429including water resources, soils, wetlands, hydrographics,

1435environmental agency process, excavation/dredging methods and

1441related engineering. Petitioner also had Petitioner’s Exhibits

14481, 2, 3, 4, 5, 6, 8, 12, 13, 14, 15, 16, 18, 19, and 21 admitted

1465into evidence. Ruling was reserved on DEP's relevance objection

1474to Petitioner's Exhibit 7, which is now overruled.

1482After presentation of evidence, DEP requested a transcript

1490of the final hearing, and Petitioner requested 15 days from the

1501filing of the transcript in which to file proposed recommended

1511orders (PROs), which was granted without objection. The

1519Transcript was filed (in two volumes) on June 7, 2006, making

1530PROs due to be filed June 22, 2006. However, the parties jointly

1542requested an extension until June 30, 2006, which was granted.

1552DEP timely filed its PRO, and Petitioner filed his PRO on July 3,

15652006, which included his request for attorney's fees under

1574Section 120.595, Florida Statutes. Both PROs have been

1582considered in the preparation of this Recommended Order.

1590FINDINGS OF FACT

1593A. Application and Default

15971. Petitioner's application is to dredge an extension, 50

1606feet wide by 300 feet long by 5 feet deep, to an existing 650

1620foot-long man-made canal of the same width and depth, normal

1630(perpendicular) to old Central and South Florida Flood Control

1639(now SFWMD) Rim Canal (the L-48 Borrow Canal), which is along the

1651northwest shore of Lake Okeechobee.

16562. Petitioner's initial, incomplete application filed in

1663DEP's Port St. Lucie office on August 31, 2000, included: the

1674proposed project's location by County, section, township, and

1682range; its legal description; a sketch of its general location

1692and surrounding landmarks; a SFWMD letter verifying conformity

1700with the requirements of a "No Notice General Permit for

1710Activities in Uplands" of a drawing for a proposed pond expansion

1721(to a size less than half an acre), "which will provide borrow

1733material necessary for a house pad and access drive"; a

1743description of water control Structure 127, together with its

1752purpose, operation, and flood discharge characteristics, which

1759were said to describe water levels in Buckhead Ridge, the name of

1771the subdivision where the project was proposed; two virtually

1780identical copies of a boundary survey for Petitioner's property

1789(one with legal description circled) showing the existing canal,

1798with boat basin off the canal on Petitioner's property near the

1809L-48 Rim Canal, at a scale of one inch equals 200 feet; two more

1823virtually identical copies of the boundary survey at the same

1833scale showing the existing canal, with boat basin off the canal

1844on Petitioner's property near the L-48 Rim Canal, and the

1854proposed canal extension and house locations; and a copy of a

18651996 aerial photograph of Petitioner's property and existing

1873canal, and vicinity. The application did not describe a proposed

1883method or any other details of construction, include any water

1893quality information, or include a water quality monitoring plan.

19023. On September 15, 2000, Petitioner filed an additional

1911page of the application form with DEP's Punta Gorda office. The

1922page added the information: "Digging to be done with trac-hoe."

1932No other specifics of the proposed construction method were

1941included.

19424. What happened after the filing of the application is

1952described in Tuten I and Tuten II , which are the law of the case.

1966However, those opinions do not explain the delay between Tuten I

1977and the issuance of DEP's proposed ERP with conditions

1986approximately two years later. The evidence presented at the

1995final hearing explained only that counsel of record for DEP

2005promptly asked district staff to draft a proposed default ERP

2015with conditions that "would probably track the RAI that had been

2026sent out prior to the default." DEP's district staff promptly

2036complied and forwarded the draft to DEP's Office of General

2046Counsel in Tallahassee, which did not provide any legal advice as

2057to the draft ERP for almost two years. There was no further

2069explanation for the delay.

20735. As reflected in Tuten II and in the Preliminary

2083Statement, it was DEP's position that the proper procedure to

2093follow after its default was to issue a proposed ERP with

2104conditions and that it would be Petitioner's burden to request an

2115administrative hearing to contest any conditions and to prove

2124Petitioner's entitlement to a default ERP with conditions other

2133than those in DEP's proposed ERP.

2139B. DEP's Proposed General Conditions

21446. The conditions DEP wants attached to Petitioner's

2152default permit include general conditions taken from SFWMD's Rule

216140E-4.381, which are appropriate, as indicated in the Preliminary

2170Statement and Conclusions of Law, and as conceded by Petitioner's

2180expert.

21817. While the Rule 40E-4.381 general conditions are

2189appropriate, Petitioner takes the position (and his expert

2197testified) that some of the general permit conditions contained

2206in Rule 62-4.160, as well as Rule 62-4.070(7) (providing that

"2216issuance of a permit does not relieve any person from complying

2227with the requirements of Chapter 403, F.S., or Department

2236rules"), are more appropriate general conditions to attach to

2246Petitioner's default ERP, even if technically inapplicable,

2253because the Chapter 62 Rules govern the operation of a permitted

2264project (whereas the former govern the construction of a

2273permitted project) and are "more protective of the environment."

2282Actually, all of the rules contain general conditions that govern

2292both construction and operation phases of an ERP, and all are

"2303protective of the environment." There is no reason to add

2313general conditions taken from Rules 62-4.160 and 62-4.070(7) to

2322the applicable general conditions contained in Rule 40E-4.381.

2330C. DEP's Proposed Specific Conditions

2335(i) In General

23388. The conditions DEP wants attached to Petitioner's

2346default permit also include specific conditions which essentially

2354require that Petitioner provide the information in the RAI sent

2364in December 2000, together with additional specific conditions

2372thought necessary to protect the environment in light of the lack

2383of detail in the application without the answers to the RAI.

23949. Some DEP's proposed specific conditions are designed to

2403ascertain whether the application would provide reasonable

2410assurance that permitting criteria would be met. (They make the

2420requested information subject to DEP "approval" based on whether

2429reasonable assurance is provided.) In general, those specific

2437conditions no longer are appropriate since DEP is required to

2447issue a default permit. (Looked at another way, inclusion of

2457those specific conditions effectively would un-do the default, in

2466direct contradiction of the court's opinion Tuten I and Tuten

2476II .) See Conclusion of Law 52, infra .

248510. On the other hand, some of the RAI information was

2496designed to ascertain the proposed method and other details of

2506construction. Pending the "answers" to those "RAI conditions,"

2514DEP also wants broad specific conditions, including a baseline

2523water quality investigation and a water quality monitoring plan,

2532designed to be adequate for a "worst case scenario" that could

2543result from the project.

254711. Petitioner opposes DEP's proposed broad specific

2554conditions. He takes the position that it was incumbent on DEP

2565in this proceeding to use discovery procedures to ascertain

2574Petitioner's intended method of construction and tailor specific

2582conditions to the method of construction revealed through

2590discovery. At the same time, Petitioner opposes DEP's proposed

2599specific conditions requiring RAI-type information, including the

2606details of his proposed construction method.

261212. Notwithstanding the positions Petitioner has taken in

2620this case, his expert testified that Petitioner intends to use a

2631steel wall inserted between the water and upland at the end of

2643the existing canal, phased excavation from the upland side, and

2653removal of the steel wall in the final phase of construction.

2664Assuming that method of construction, Petitioner takes the

2672position (and his expert testified) that the statutes, rules, and

2682permit conditions acceptable to Petitioner, and which generally

2690prohibit pollution of the environment, are adequate.

269713. Even if the statutes, rules, and permit conditions

2706acceptable to Petitioner would be adequate for the method of

2716construction Petitioner now says he will use, Petitioner's

2724application does not in fact commit to a method of construction.

2735All Petitioner's application says is that he intends to dig with

2746a trac-hoe. Without a binding commitment to a method of

2756construction, it was appropriate for DEP to take the position

2766that specific conditions were necessary to ascertain the method

2775of construction Petitioner would use and, pending the "answers"

2784to those "RAI conditions," and to impose broad specific

2793conditions, including a baseline water quality investigation and

2801a water quality monitoring plan, designed to be adequate for a

"2812worst case scenario" that could result from the project.

282114. In his PRO, Petitioner committed to use the

2830construction method described by his expert during the hearing,

2839as follows:

2841A. Excavation of any spoil shall be

2848done by means of a mechanical trac-hoe;

2855B. Prior to the excavation of any soil,

2863Petitioner shall first install an isolating

2869wall, such as interlocking sheet pile,

2875between the existing man-made canal, and the

2882proposed canal extension;

2885C. The mechanical excavation shall be

2891done in such a manner such that the excavated

2900soil is not deposited in wetlands or in areas

2909where it might be reasonably contemplated to

2916re-enter the waters of the State of Florida;

2924D. After the proposed canal extension

2930is excavated to its project limits in the

2938foregoing manner, the side slopes of the

2945canal extension shall be allowed to

2951revegetate prior to removal of the isolating

2958wall.

295915. With a condition imposing this method of construction,

2968fewer and narrower specific conditions will be necessary.

2976ii. Seriatim Discussion

297916. DEP's proposed Specific Condition 1 requires a

2987perpetual conservation easement prohibiting docking and mooring

2994of water craft on all portions of Petitioner's property within

3004the canal extension in order to "address cumulative impacts."

3013But DEP did not prove that the proposed conservation easement was

3024reasonably necessary to protect the interest of the public and

3034the environment. First, DEP did not prove that there would be

3045any cumulative impacts, much less unacceptable cumulative

3052impacts, from Petitioner's project. See § 373.414(8), Fla.

3060Stat.; Rule 40E-4.302(1)(b); and BOR § 4.2.8. Second, even if

3070unacceptable cumulative impacts were proven, those could be

3078addressed in other permit cases (assuming no DEP default in those

3089proceedings), since the concept of cumulative impacts essentially

3097requires an applicant to share acceptable cumulative impacts with

3106other similar permittees, applicants, and foreseeable future

3113applicants. See Broward County v. Weiss, et al. , DOAH Case No.

312401-3373, 2002 Fla. ENV LEXIS 298, at ¶¶54-58 (DOAH Aug. 27,

31352002).

313617. As Petitioner points out, the easement further

3144described in Specific Condition 1 appears to be overly broad for

3155its stated purpose in that it would cover "the legal description

3166of the entire property affected by this permit and shown on the

3178attached project drawings," which could be interpreted to include

3187not just the canal extension but the entire extended canal, or

3198even the entirety of Petitioner's 6.6 acres of property. Indeed,

3208the latter might have been the actual intention, since DEP's

3218witness testified that Specific Condition 1 also was intended to

3228address impacts from fertilizer runoff and septic tank leaching

3237from new homes built along the canal. Although some of those

3248impacts (as well as future construction of additional homes and

3258docks) actually are secondary impacts, not cumulative impacts, it

3267is possible that they can be addressed in DEP or SFWMD

3278proceedings on future applications, as well as in Department of

3288Health proceedings on septic tank installations.

329418. DEP's proposed Specific Condition 2 requires that:

3302spoil material from the dredging to be "used for the sole purpose

3314of constructing a single-family fill pad" on Petitioner's

3322property under a pending permit; spoil "be placed in a manner so

3334as not to affect wetlands or other surface waters"; and the

"3345spoil disposal location shall be shown in the drawings required

3355by Specific Condition #4 below."

336019. DEP did not prove that the first requirement was

3370reasonably necessary to protect the interest of the public and

3380the environment. First, it is unreasonable since Petitioner

3388already has built the referenced single-family fill pad and a

3398home on top of it. Second, the reason DEP's witness gave for

3410this requirement was that, under an operating agreement with

3419SFWMD (which was officially recognized), DEP only has

3427jurisdiction to take action on single-family uses (which he

3436defined to include duplexes, triplexes, and quadriplexes) but not

3445on larger multi-family and certain other projects. However, the

3454operating agreement on jurisdiction is not a reason to place

3464Specific Condition 1 on the use of spoil material on Petitioner's

3475default permit. SFWMD can regulate, in permitting proceedings

3483under its jurisdiction, the placement of fill material for multi-

3493family construction or other projects not under DEP jurisdiction.

3502In addition, under the operating agreement, jurisdiction can be

"3511swapped" by written agreement in cases where deviation from the

3521operating agreement would result in more efficient and effective

3530regulation.

353120. The second two requirements under Specific Condition 2

3540are reasonable and necessary to protect the interest of the

3550public and the environment.

355421. DEP's proposed Specific Condition 3 requires disclosure

3562of all pending and issued permits for the property from SFWMD,

3573Glades County, or the U.S. Army Corps of Engineers (USCOE). DEP

3584did not prove that this is reasonable or reasonably necessary to

3595protect the interest of the public and the environment. DEP

3605probably has all such permits and can easily obtain any it does

3617not have.

361922. DEP's proposed Specific Condition 4 requires fully

3627dimensional plan view and cross-sectional drawings of the

3635property and area to be dredged, before and after dredging,

3645including a north arrow and the water depths in and adjacent to

3657the dredge area. DEP's witness stated that the primary purpose

3667of this part of the condition is to provide hydrographic

3677information normally provided in an application (or required in

3686an RAI) so that DEP's hydrographic engineer can ascertain

3695flushing characteristics, which are pertinent primarily to the

3703dissolved oxygen water quality parameter and to heavy metals from

3713boat use. As previously indicated, requests for information

3721relating to reasonable assurance and the public interest test

3730generally no longer are appropriate since DEP is required to

3740issue a default permit. See Finding 9, supra . However,

3750information regarding flushing characteristics, combined with

3756other specific conditions, is reasonable and necessary to protect

3765the interest of the public and the environment. See Finding 27,

3776infra . 23. In addition, the plan view and cross-sectional drawings

3787required by Specific Condition 4 are to include the location of

3798navigational obstructions in the immediate area, any roads,

3806ditches, or utility lines that abut the property; any

3815encumbrances, and any associated structures. DEP's witness

3822stated that the primary purpose of this information is to

3832determine whether Petitioner has provided reasonable assurance

3839that the "public interest" test under Rule 40E-4.302 is met, and

3850make sure that management, placement, and disposal of spoil

3859material do not infringe on property rights or block culverts and

3870cause flooding. As previously indicated, requests for

3877information relating to reasonable assurance and the public

3885interest test generally no longer are appropriate. See Finding

38949, supra . However, information regarding the location of

3903culverts to assure that management of spoil does not cause

3913flooding is reasonable and necessary to protect the interest of

3923the public and the environment.

392824. In addition to objecting to having to provide RAI

3938information as a "default permittee," Petitioner's expert

3945asserted that the information requested in Specific Condition 4

3954would be provided as part of the "as-built" drawings required by

3965General Condition 6. But General Condition 6 does not require

"3975as-built" drawings. Rather, it requires an "as-built"

3982certification that can be based on "as-built" drawings or on-site

3992observation. Besides, the purpose of the "as-built"

3999certification is to determine "if the work was completed in

4009compliance with permitted plans and specifications." Without the

4017information requested in Specific Condition 4, there would only

4026be vague and general permitted plans and specifications and

4035hydrographic information.

403725. Finally as to Specific Condition 4, Petitioner objects

4046to the requirement that the drawings be sealed by a registered

4057professional engineer. However, Petitioner cites to General

4064Condition 6, which requires that the "as-built" certification be

4073given by a "registered professional" and cites Rule Form 62-

4083343.900(5), which makes it clear that "registered professional"

4091in that context means a registered professional engineer.

409926. DEP's proposed Specific Condition 5 requires Petitioner

4107to submit for DEP approval, within 180 days of permit issuance

4118and before any construction, reasonable assurance that the canal

4127extension will not violate water quality standards due to depth

4137or configuration; that it will not cause a violation of water

4148quality standards in receiving water bodies; and that it will be

4159configured to prevent creation of debris traps or stagnant areas

4169that could result in water quality violations. The reasonable

4178assurance is to include hydrographic information or studies to

4187document flushing time and an evaluation of the maximum desirable

4197flushing time, taking several pertinent factors into

4204consideration.

420527. As previously indicated, requests for information

4212relating to reasonable assurance and the public interest test

4221generally no longer are appropriate. See Finding 9, supra . In

4232addition, Petitioner's expert testified without dispute that the

4240information requested could take more than 180 days and cost

4250approximately $20,000. However, it is reasonable and necessary

4259to protect the interest of the public and the environment to

4270include a specific condition that Petitioner's canal extension be

4279configured so as have the best practicable flushing

4287characteristics.

428828. DEP's proposed Specific Condition 6 requires Petitioner

4296to submit for DEP approval, within 180 days of permit issuance

4307and before any construction, reasonable assurance that

4314construction of the canal extension will meet all permit criteria

4324set out in Rules 40E-4.301 and 40E-4.302 and in BOR § 4.1.1. As

4337previously indicated, requests for information relating to

4344reasonable assurance and the public interest test generally no

4353longer are appropriate. See Finding 9, supra .

436129. DEP's proposed Specific Condition 7 requires Petitioner

4369to submit existing water quality information for DEP approval

4378within 180 days of permit issuance and before any construction.

4388In this instance, DEP's approval would not be a determination on

4399the provision of reasonable assurance but a determination as to

4409the reliability of the water quality information, which is

4418necessary to establish a baseline for assessing and monitoring

4427the impact of the project. For that reason, the information is

4438reasonable and necessary to protect the interest of the public

4448and the environment.

445130. Petitioner's expert testified that the information

4458could cost $2,000-$3,000 to produce (and more, if DEP rejects the

4471information submitted, and more information is required). He

4479also testified that water quality information already is

4487available, including over 25 years worth of at least monthly

4497information on all pertinent parameters except biological oxygen

4505demand and fecal coliform, at a SFWMD monitoring station in the

4516Rim Canal at Structure 127 (a lock and pump station at the Hoover

4529Levee on Lake Okeechobee) approximately 8,000 feet away from

4539Petitioner's canal. DEP did not prove that the SFWMD information

4549would not serve the purpose of establishing baseline water

4558quality for Petitioner's canal for all but the missing

4567parameters. For that reason, only water quality information for

4576the missing parameters is reasonable and necessary to protect the

4586interest of the public and the environment in this case.

459631. DEP's proposed Specific Condition 8 requires that, if

4605the water quality information required by Specific Condition 7

4614shows any violations of state ambient water quality standards,

4623Petitioner must submit for DEP approval, within 180 days of

4633permit issuance and before any construction, a plan to achieve

4643net improvement for any parameters shown to be in violation, as

4654required by Section 373.414, Florida Statutes. See also BOR §

46644.2.4.1 and 4.2.4.2. Normally, if applicable, this information

4672would be expected in an application or RAI response.

4681Petitioner's expert testified that this condition would require

4689Petitioner to help "fix Buckhead Ridge" (unfairly) and that it

4699would cost lots of money. But Petitioner did not dispute that

4710the law requires a plan for a "net improvement," which does not

4722necessarily require a complete "fix" of water quality violations,

4731if any. As previously indicated, requests for information

4739relating to reasonable assurance and the public interest test

4748generally no longer are appropriate, and Petitioner's ability to

4757construct the canal extension should not be dependent on DEP's

4767approval of a net improvement plan. See Finding 9, supra . But a

4780specific condition that Petitioner implement a plan to achieve

4789net water quality improvement in the event of any water quality

4800violations would be reasonable and necessary to protect the

4809interest of the public and the environment.

481632. DEP's proposed Specific Condition 9 requires Petitioner

4824to submit for DEP's approval, at least 60 days before

4834construction, detailed information on how Petitioner intends to

4842prevent sediments and contaminants from being released into

4850jurisdictional waters. DEP asserts that this specific condition

4858asks for a detailed description of how the applicant will comply

4869with various subsections of BOR § 4.2.4.1 that address short-term

4879water quality to aid in providing reasonable assurance that water

4889quality standards will not be violated, as required by Section

4899373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e). As

4906previously indicated, requests for information relating to

4913reasonable assurance and the public interest test generally no

4922longer are appropriate, and Petitioner's ability to construct the

4931canal extension should not be dependent on DEP's approval of

4941information submitted. See Finding 9, supra . But it is

4951reasonable and necessary to protect the interest of the public

4961and the environment to include a specific condition that

4970Petitioner's canal extension be constructed using adequate

4977turbidity barriers; stabilize newly created slopes or surfaces in

4986or adjacent to wetlands and other surface waters to prevent

4996erosion and turbidity; avoid propeller dredging and rutting from

5005vehicular traffic; maintain construction equipment to ensure that

5013oils, greases, gasoline, or other pollutants are not released

5022into wetlands and other surface waters; and prevent any other

5032discharges during construction that will cause water quality

5040violations.

504133. DEP's proposed Specific Condition 10 requires

5048Petitioner to submit, at least 60 days before construction,

5057detailed information regarding Petitioner's plans for handling

5064spoil from dredging, including "discharge details, locations

5071retention plans, volumes, and data used to size the disposal

5081cell(s)." It allows this information to be combined with the

5091Specific Condition 2 submittal. It also requires spoil to be

5101properly contained to prevent return of spoil to waters of the

5112State and to be deposited in a self-contained upland site that

5123prevents return of any water or material into waters of the

5134State.

513534. DEP asserts that this specific condition (like Specific

5144Condition 9) is necessary to comply with BOR § 4.2.4.1 by

5155addressing short-term water quality to aid in providing

5163reasonable assurance that water quality standards will not be

5172violated, as required by Section 373.414(1), Florida Statutes,

5180and Rule 40E-4.301(1)(e). As previously indicated, requests for

5188information relating to reasonable assurance and the public

5196interest test generally no longer are appropriate, and

5204Petitioner's ability to construct the canal extension should not

5213be dependent on DEP's approval of information submitted. See

5222Finding 9, supra . But it is reasonable and necessary to protect

5234the interest of the public and the environment to include a

5245specific condition requiring spoil to be properly contained to

5254prevent return of spoil to waters of the State and to be

5266deposited in a self-contained upland site that prevents return of

5276any water or material into waters of the State.

528535. DEP's proposed Specific Condition 11 requires

5292Petitioner to submit "as-built" drawings to DEP's Punta Gorda

5301office with 30 days after completion of construction, "as

5310required by General Condition #6." Petitioner's expert testified

5318that this condition was unreasonable only because it duplicates

5327General Condition 6 and two statutes. But General Condition 6

5337actually does not require "as-built" drawings, see Finding 9,

5346supra , and it is not clear what statutes Petitioner's expert was

5357referring to. For these reasons, and because it provides a

5367filing location, Specific Condition 11 is reasonable and

5375reasonably necessary to protect the interest of the public and

5385the environment.

538736. DEP's proposed Specific Condition 12 requires

5394Petitioner to "maintain the permitted canal free of all rafted

5404debris by removal and property upland disposal." DEP asserts

5413that this specific condition is necessary to comply with BOR §

54244.2.4.2 by addressing long-term water quality to aid in providing

5434reasonable assurance that water quality standards will not be

5443violated, as required by Section 373.414(1), Florida Statutes,

5451and Rule 40E-4.301(1)(e). Rafted debris, which may be of an

5461organic or inorganic nature, can accumulate at the end of canals

5472due to wind, waves, boats, or other forces. Such organic rafted

5483debris may rot and, by creating a high biological oxygen demand,

5494rob the water of dissolved oxygen. Petitioner's only expressed

5503opposition to this condition is that the conservation easement in

5513Specific Condition 3 might prevent compliance. While it is

5522unclear how the easement would prevent compliance, the issue is

5532eliminated if no conservation easement is required.

553937. DEP's proposed Specific Condition 13 requires

5546Petitioner to use turbidity screens during construction for

5554compliance with BOR § 4.2.4.1 by addressing short-term water

5563quality to aid in providing reasonable assurance that water

5572quality standards will not be violated, as required by Section

5582373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e). The

5589turbidity screen requirements detailed in this specific condition

5597are typical best management practices that contractors use and

5606are a standard condition placed in permits of this nature by DEP.

5618Petitioner contends that turbidity screens are unnecessary given

5626his intended construction method and that other conditions are

5635sufficient to cover DEP's concerns. However, as indicated, the

5644application does not commit to a method of construction. With

5654the application in its current state, Specific Condition 13 is

5664appropriate subject to a demonstration by Petitioner that

5672turbidity screens are not needed for the construction method

5681committed to in Petitioner's PRO.

568638. DEP's proposed Specific Condition 14 requires

5693Petitioner to "ensure that any discharge or release of pollutants

5703during construction or alteration are not released into wetlands

5712or other surface waters that will cause water quality standards

5722to be violated." Again, this condition is intended to ensure

5732compliance with BOR § 4.2.4.1 by addressing short-term water

5741quality to aid in providing reasonable assurance that water

5750quality standards will not be violated, as required by Section

5760373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e). While

5767this specific condition seems general and perhaps duplicates

5775other conditions (which was Petitioner's only point of

5783contention), DEP added it in an attempt to make sure the possible

5795and not uncommon release of pollutants from construction

5803equipment was addressed. As such, the condition is appropriate.

581239. DEP's proposed Specific Condition 15 provides details

5820on the use of turbidity screens. Petitioner's primary points of

5830contention are that turbidity screens are not needed for his

5840intended construction method and that other conditions are

5848sufficient without this condition. As such, the relevant issues

5857already have been addressed in connection with Specific Condition

586613. With the application in its current state, Specific

5875Condition 15 is appropriate subject to a demonstration by

5884Petitioner that turbidity screens are not needed for the

5893construction method committed to in Petitioner's PRO.

590040. DEP's proposed Specific Condition 16 requires

5907Petitioner to used staked filter cloth to contain any turbid run-

5918off and erosion from created slopes of the canal extension. This

5929is the most common best management practice and is a standard

5940condition for ERP permits dealing with side slopes that may

5950affect water quality. Unstable slopes can result in chronic

5959turbidity, which is detrimental to wildlife. Unstable slopes

5967also can lead to upland runoff being deposited into the water

5978along with debris and sediment. Such runoff can bring

5987deleterious substances such as heavy metals and nutrient-loaded

5995substances that might impact dissolved oxygen levels in the

6004water.

600541. Petitioner's primary points of contention on Specific

6013Condition 16 are that, like turbidity screens, staked filter

6022cloth is not needed for Petitioner's intended construction method

6031and that other conditions are sufficient without this condition.

6040(Petitioner also questions why the condition gives Petitioner up

6049to 72 hours from "attaining final grade" to stabilize side

6059slopes, but the condition also requires side slope stabilization

"6068as soon as possible," and the 72-hour outside limit seems

6078reasonable.) As such, the relevant issues already have been

6087addressed in connection with Specific Condition 13 and 15. With

6097the application in its current state, Specific Condition 16 is

6107appropriate subject to a demonstration by Petitioner that staked

6116filter cloth is not needed if he uses the construction method

6127committed to in Petitioner's PRO.

613242. DEP's proposed Specific Condition 17, 18, 19, and 20:

6142details required long-term water quality monitoring and reporting

6150[#17]; establishes sampling intervals and requires Petitioner to

6158submit a "plan to remediate" if monitoring shows water quality

6168violations or "a trend toward future violations of water quality

6178standards directly related to the permitted canal" [#18]; allows

"6187additional water quality treatment methods" to be required if

6196water quality monitoring shows it to be necessary [#19]; and

6206allows water quality monitoring requirements to be modified

6214(which "may include reduction in frequency and parameters . . .

6225or the release of the monitoring process"), "based on long term

6237trends indicate that the permitted canal is not a source to

6248create water quality violations [#20]." These conditions are

6256intended to ensure compliance with BOR § 4.2.4.2 by addressing

6266long-term water quality to aid in providing reasonable assurance

6275that water quality standards will not be violated, as required by

6286Section 373.414(1), Florida Statutes, and Rule 40E-4.301(1)(e).

629343. The evidence was that these specific conditions are

6302standard for ERP permits where a constructed system may lead to

6313water quality violations in the long term. Contrary to

6322Petitioner's contentions, conditions of this kind are not

6330dependent on a post-construction finding of water quality

6338standard violations (even though DEP defaulted on Petitioner's

6346application). Besides contending that monitoring requirements in

6353Specific Conditions 17 and 18 are unnecessary, Petitioner also

6362contends that they are too extensive and not tailored to

6372Petitioner's intended construction, but DEP proved their

6379necessity, even assuming the construction method committed to in

6388Petitioner's PRO. Petitioner complains that Specific Condition

639519 is vague and that Petitioner's ERP does not provide for "water

6407quality treatment." But the present absence of post-construction

6415water quality treatment should not preclude the possible future

6424imposition of some kind of water quality treatment if monitoring

6434shows it to be necessary. For this kind of condition, the

6445absence of detail regarding the kind of treatment to be imposed

6456is natural since it would depend on future events.

646544. DEP's proposed Specific Condition 21 merely requires

6473that Petitioner's project comply with State water quality

6481standards in Florida Administrative Code Rules 62-302.500 and 62-

6490302.530. Petitioner contends that this is duplicative and

6498unnecessary. But it certainly is not unreasonable to be specific

6508in this regard.

6511D. No Improper Purpose

651545. As part of his request for attorney's fees under

6525Section 120.595, Florida Statutes, Petitioner necessarily

6531contends that DEP participated in this proceeding "for an

6540improper purpose"--i.e. , "primarily to harass or to cause

6549unnecessary delay or for frivolous purpose or to needlessly

6558increase the cost of litigation, licensing, or securing the

6567approval of an activity." Even assuming that DEP should be

6577considered a "nonprevailing adverse party," Petitioner's evidence

6584did not prove that DEP's participation was for an "improper

6594purpose." To the contrary, DEP "participated" initially because

6602Petitioner filed an application. DEP's denial of Petitioner's

6610application was not proven to be "for an improper purpose" but

6621rather for the purpose of attempting to protect the environment.

6631The propriety of the denial was litigated in Tuten I , which made

6643no finding that the denial was "for an improper purpose" and

6654which ordered DEP to participate in a hearing for purposes of

6665determining "reasonable mitigative conditions." The two-year

6671delay between Tuten I and Tuten II was not fully explained, but

6683Tuten II also made no finding that the denial, or the delay, or

6696DEP's proposed ERP with conditions were "for an improper purpose"

6706and again ordered DEP to participate in a hearing for purposes of

6718determining "reasonable mitigative conditions." While DEP's

6724views on the nature of the hearing to be conducted for purposes

6736of determining "reasonable mitigative conditions" was rejected,

6743it was not proven that DEP argued its views "for an improper

6755purpose" or that its participation, once its views were rejected,

6765was "for an improper purpose," as defined by statute. To the

6776contrary, the evidence was that DEP participated in this

6785proceeding in an attempt to place conditions on Petitioner's

6794permit which DEP thought were necessary to protect the

6803environment, many (although not all) of which are accepted in

6813this Recommended Order.

681646. As Petitioner accepts and points out, it remains

6825necessary for Petitioner to construct and operate his project in

6835a manner that does not violate environmental statutes and rules.

6845But without any water quality information or monitoring, DEP's

6854enforcement of those laws and rules will be hamstrung.

6863CONCLUSIONS OF LAW

686647. Tuten I and Tuten II are the law of the case. Under

6879those decisions, the issue for determination in this case is

6889whether, and what, reasonable mitigative conditions are necessary

6897to protect the interest of the public and the environment, prior

6908to issuing Petitioner's default permit.

691348. As reflected in the Preliminary Statement, it is

6922concluded that DEP has the burden to plead and prove "'the

6933reasonable mitigative conditions necessary to protect the

6940interest of the public and the environment, prior to issuing a

6951default permit.' Manasota-88, Inc. v. Agrico Chem. Co. , 576

6960So. 2d 781, 783 (Fla. 2d DCA 1991)." DEP's proposed default

6971permit with general and specific conditions, while reversed by

6980the appellate court in Tuten II , was deemed to constitute DEP's

6991pleading of the "reasonable mitigative conditions" DEP seeks to

7000impose on the default permit to be issued to the Petitioner.

701149. DEP's proposed General Conditions 1-19 are taken from

7020Rule 40E-4.381, which DEP adopted by reference under Rule 62-

7030330.200(4). These conditions apply to and are binding on all ERP

7041permits located within the geographic jurisdiction of the SFWMD,

7050unless waived or modified upon a determination that the

7059conditions are inapplicable to the activity authorized by the

7068permit. In the absence of such a determination, these General

7078Conditions are “standard conditions,” and they are “substantive

7087requirements of [the applicable permitting statute].” See

7094generally Op. Att’y Gen. Fla. 78-169 (1978). Ultimately,

7102Petitioner agreed to General Conditions 1-19.

710850. DEP's Rule 62-4.001 states that “the provisions of this

7118Part . . . shall not apply to activities regulated under Part IV

7131of Chapter 373, F.S.” Tuten’s proposed canal extension is an

7141activity regulated under Part IV of Chapter 373, Florida

7150Statutes. Therefore, contrary to Petitioner's contention, the

7157provisions of Rule Chapter 62-4, Part I, including the permit

7167conditions contained in Rules 62-4.070(7) and 62-4.160, do not

7176apply in this case.

718051. Rule 40E-4.381(2) provides:

7184In addition to those general conditions set

7191forth in subsection (1), the Governing Board

7198shall impose on any permit granted under this

7206chapter and chapter 40E-40 F.A.C., such

7212reasonable project-specific special

7215conditions as are necessary to assure that

7222the permitted system will not be inconsistent

7229with the overall objectives of the District

7236or will not be harmful to the water resources

7245of the District, as set forth in District

7253rules.

725452. DEP contends that Rule 40E-4.381(2), along with

7262Attorney General Opinion 78-169, authorizes the imposition of

7270requirements that Petitioner provide RAI responses and reasonable

7278assurance of compliance with permitting criteria under Rules 40E-

72874.301, entitled "Conditions for Issuance of Permits," and 40E-

72964.302, entitled "Additional Conditions for Issuance of Permits."

7304But it is concluded that those permitting criteria do not apply

7315to default permits and are not the kind of "standard conditions"

7326referred to in Attorney General Opinion 78-169, which answered

7335the specific question:

7338May an agency place as conditions in a

7346default license issued pursuant to

7351s.120.60(2), F.S., standard conditions such

7356as the reporting of water quality violations,

7363periodic operating reports, and monitoring

7368requirements which are routinely placed in

7374agency licenses which do not call for project

7382design changes, or impose other such

7388substantive requirements of Ch. 403, F.S., or

7395rules duly adopted thereunder?

7399Otherwise, the default statute would be rendered meaningless, and

7408instruction of Tuten I and Tuten II to determine the "reasonable

7419mitigative conditions [that] are necessary to protect the

7427interest of the public and the environment" would be ignored.

743753. On the other hand, as found, other specific conditions

7447proposed by DEP are "reasonable mitigative conditions [that] are

7456necessary to protect the interest of the public and the

7466environment." Specifically, Specific Conditions 4, 5, and 11-21

7474are reasonable as proposed. Specific Conditions 2 and 5-10, as

7484modified by the Findings of Fact, are appropriate.

749254. Attorney's fees under Section 120.595(1), Florida

7499Statutes, may be awarded only upon a finding that the

"7509nonprevailing adverse party" participated in the proceeding "for

7517an improper purpose," defined as "primarily to harass or to cause

7528unnecessary delay or for frivolous purpose or to needlessly

7537increase the cost of litigation, licensing, or securing the

7546approval of an activity." Based on the findings, Petitioner's

7555request for such an award from DEP should be denied in this case.

7568RECOMMENDATION

7569Based upon the foregoing Findings of Fact and Conclusions of

7579Law, it is

7582RECOMMENDED that DEP enter a final order issuing Petitioner

7591a default ERP, to expire five years from issuance, to dredge an

7603extension, 50 feet wide by 300 feet long by 5 feet deep, to an

7617existing man-made canal, as applied for, subject to: DEP's

7626proposed General Conditions 1-19; DEP's proposed Specific

7633Conditions 4 and 11-21; DEP's proposed Specific Conditions 2, 5,

7643and 7-10, as modified by the Findings of Fact; and the

7654construction method committed to in Petitioner's PRO (see Finding

766314, supra .

7666DONE AND ENTERED this 11th day of August, 2006, in

7676Tallahassee, Leon County, Florida.

7680S

7681J. LAWRENCE JOHNSTON

7684Administrative Law Judge

7687Division of Administrative Hearings

7691The DeSoto Building

76941230 Apalachee Parkway

7697Tallahassee, Florida 32399-3060

7700(850) 488-9675 SUNCOM 278-9675

7704Fax Filing (850) 921-6847

7708www.doah.state.fl.us

7709Filed with the Clerk of the

7715Division of Administrative Hearings

7719this 11th day of August, 2006.

7725ENDNOTES

77261 / Except for Rule Chapter 40E-4, or unless otherwise stated,

7737all Rule references are to the current version of the Florida

7748Administrative Code.

77502 / All references to Rule Chapter 40E-4 are to the 1995 version

7763of the Rule, which is the version adopted by Rule 62-330.200(4).

77743 / Unless otherwise stated, all statutory references are to the

77852005 codification of the Florida Statutes.

7791COPIES FURNISHED :

7794Lea Crandall, Agency Clerk

7798Department of Environmental Protection

7802The Douglas Building, Mail Station 35

78083900 Commonwealth Boulevard

7811Tallahassee, Florida 32399-3000

7814Greg Munson, General Counsel

7818Department of Environmental Protection

7822The Douglas Building, Mail Station 35

78283900 Commonwealth Boulevard

7831Tallahassee, Florida 32399-3000

7834Colleen M. Castille, Secretary

7838Department of Environmental Protection

7842The Douglas Building

78453900 Commonwealth Boulevard

7848Tallahassee, Florida 32399-3000

7851Francine M. Ffolkes, Esquire

7855Department of Environmental Protection

7859The Douglas Building, Mail Station 35

78653900 Commonwealth Boulevard

7868Tallahassee, Florida 32399-3000

7871Frederick M. Dahlmeier, Esquire

7875Cromwell & Dahlmeier, P.L.

7879760 U.S. Highway One, Suite 301

7885North Palm Beach, Florida 33408

7890NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

7896All parties have the right to submit written exceptions within 15

7907days from the date of this Recommended Order. Any exceptions to

7918this Recommended Order should be filed with the agency that will

7929issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 07/28/2008
Proceedings: Mandate filed.
PDF:
Date: 07/25/2008
Proceedings: Mandate
PDF:
Date: 07/25/2008
Proceedings: Mandate
PDF:
Date: 07/07/2008
Proceedings: BY ORDER OF THE COURT: Appellant`s motion filed June 9, 2008, for rehearing is hereby denied filed.
PDF:
Date: 05/30/2008
Proceedings: BY ORDER OF THE COURT: Appellant`s motion filed February 14, 2008, for attorney`s fees and costs is hereby denied filed.
PDF:
Date: 05/30/2008
Proceedings: Per Curiam Affirmed (Fourth DCA) filed.
PDF:
Date: 02/19/2008
Proceedings: BY ORDER OF THE COURT: Appellant`s third motion for extension of tme is granted.
PDF:
Date: 01/07/2008
Proceedings: BY ORDER OF THE COURT: Appellant`s motion for extension of time is granted.
PDF:
Date: 11/26/2007
Proceedings: BY ORDER OF THE COURT: appellant`s first motion for extension of time is granted filed.
PDF:
Date: 10/09/2007
Proceedings: BY ORDER OF THE COURT: Appellee`s unopposed motion filed September 28, 2007 for fourth extension of time is granted.
PDF:
Date: 09/04/2007
Proceedings: BY ORDER OF THE COURT: Appellee`s motion for third extension of time is granted.
PDF:
Date: 07/23/2007
Proceedings: BY ORDER OF THE COURT: Appellee`s motion for extension of time is granted.
PDF:
Date: 06/28/2007
Proceedings: BY ORDER OF THE COURT: Appellee`s unopposed motion filed June 20, 2007, for extension of time is granted.
PDF:
Date: 05/09/2007
Proceedings: BY ORDER OF THE COURT: Appellant`s motion for extension of time is granted.
PDF:
Date: 04/04/2007
Proceedings: BY ORDER OF THE COURT: Appellant`s third motion for extension of time is granted.
PDF:
Date: 03/02/2007
Proceedings: BY ORDER OF THE COURT: Appellant`s second motion for extension of time is granted.
PDF:
Date: 01/29/2007
Proceedings: BY ORDER OF THE COURT: Appellant`s motion for extension of time is granted.
PDF:
Date: 11/20/2006
Proceedings: Acknowledgment of New Case, DCA Case No. 4D6-4424.
PDF:
Date: 10/17/2006
Proceedings: Order Denying Petitioner`s Motion to Remand and Request for Hearing filed with the Department of Environmental Protection.
PDF:
Date: 10/17/2006
Proceedings: Order Granting Second Request for Extension of Time to File Exceptions to Recommended Order and Extending Time for Entry of Agency Final Order filed with the Department of Environmental Protection.
PDF:
Date: 10/17/2006
Proceedings: Order Extending Time for Filing Exceptions to Recommended Order and Extending Time for Entry of Agency Final Order filed with the Department of Environmental Protection.
PDF:
Date: 10/16/2006
Proceedings: Final Order filed.
PDF:
Date: 10/12/2006
Proceedings: Agency Final Order
PDF:
Date: 09/26/2006
Proceedings: DEP`s Response to Petitioner`s Exceptions to Recommended Order filed.
PDF:
Date: 09/25/2006
Proceedings: DEP`s Response in Opposition to Tuten`s Motion to Remand filed.
PDF:
Date: 09/25/2006
Proceedings: DEP`s Response in Opposition to Tuten`s Request for Hearing filed.
PDF:
Date: 09/14/2006
Proceedings: Motion to Remand Action to Administrative Law Judge filed.
PDF:
Date: 09/14/2006
Proceedings: Petitioner`s Request for Hearing filed.
PDF:
Date: 09/14/2006
Proceedings: Petitioner`s Exceptions to Recommended Order filed.
PDF:
Date: 09/11/2006
Proceedings: Petitioner`s Request for Extension of Time to File Exceptions to Recommended Order filed by Petitioner.
PDF:
Date: 09/01/2006
Proceedings: Petitioner`s Request for Extension of Time to File Exceptions to Recommended Order filed.
PDF:
Date: 08/25/2006
Proceedings: Petitioner`s Request for Extension of Time to File Exceptions to Recommended Order filed.
PDF:
Date: 08/11/2006
Proceedings: Recommended Order
PDF:
Date: 08/11/2006
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 08/11/2006
Proceedings: Recommended Order (hearing held May 2-3, 2006). CASE CLOSED.
PDF:
Date: 07/03/2006
Proceedings: Notice of Unavailability filed.
PDF:
Date: 07/03/2006
Proceedings: Corrected Pages 15 and 16 of Petitioner`s Proposed Recommended Order filed.
PDF:
Date: 07/03/2006
Proceedings: Petitioner, Donald G. Tuten`s Proposed Recommended Order filed.
PDF:
Date: 06/30/2006
Proceedings: Proposed Recommended Order of State of Florida Department of Environmental Protection filed.
PDF:
Date: 06/23/2006
Proceedings: Order Granting Extension of Time (proposed recommended orders to be filed by June 30, 2006).
PDF:
Date: 06/23/2006
Proceedings: Joint Motion for Extension of Time to file Proposed Recommended Orders filed.
PDF:
Date: 06/22/2006
Proceedings: Joint Motion to File Proposed Recommended Orders filed.
Date: 06/07/2006
Proceedings: Transcript (May 2 and 3, 2006) filed.
Date: 05/02/2006
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 05/01/2006
Proceedings: Motion for View filed.
PDF:
Date: 05/01/2006
Proceedings: Motion in Limine filed.
PDF:
Date: 05/01/2006
Proceedings: Tuten`s Unilateral Pre-hearing Stipulation filed.
PDF:
Date: 05/01/2006
Proceedings: DEP`s Response to Motion for View filed.
PDF:
Date: 05/01/2006
Proceedings: DEP`s Response to Tuten`s Motion in Limine filed.
PDF:
Date: 04/28/2006
Proceedings: DEP`s Unilateral Pre-hearing Statement filed.
PDF:
Date: 04/28/2006
Proceedings: Motion for Continuance filed.
PDF:
Date: 04/28/2006
Proceedings: DEP`s Motion for Official Recognition filed.
PDF:
Date: 04/25/2006
Proceedings: Notice and Certificate of Service of Respondent DEP`s Answers to Donald G. Tuten`s First Set of Interrogatories filed.
PDF:
Date: 04/25/2006
Proceedings: DEP`s Response to Tuten`s First Request for Production of Documents filed.
PDF:
Date: 04/20/2006
Proceedings: Motion for Protective Order filed.
PDF:
Date: 04/19/2006
Proceedings: Respondent Department of Protection`s Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 04/19/2006
Proceedings: Respondent Department of Environmental Protection`s Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 04/19/2006
Proceedings: Notice of Taking Deposition Duces Tecum (3) filed.
PDF:
Date: 04/19/2006
Proceedings: Petitioner`s Response to Respondent`s First Request for Production of Documents filed.
PDF:
Date: 04/19/2006
Proceedings: Petitioner`s Answers to Respondent`s Interrogatories filed.
PDF:
Date: 04/11/2006
Proceedings: Donald G. Tuten`s Motion for Extension of Time to Respond to First Request for Production and First Set of Interrogatories filed.
PDF:
Date: 04/07/2006
Proceedings: Donald G. Tuten`s Preliminary Witness List filed.
PDF:
Date: 04/07/2006
Proceedings: DEP`s Preliminary Witness List filed.
PDF:
Date: 04/05/2006
Proceedings: Amended Order of Pre-hearing Instructions.
PDF:
Date: 03/27/2006
Proceedings: Notice of Corrected Certificate of Service of Petitioner`s Response to DEP`s Pleading of Reasonable Mitigative Conditions filed.
PDF:
Date: 03/27/2006
Proceedings: Motion for Order Setting Pre-hearing Discovery Deadlines filed.
PDF:
Date: 03/27/2006
Proceedings: Donald G. Tuten`s First Request for Production of Documents to Department of Environmental Protection filed.
PDF:
Date: 03/27/2006
Proceedings: Donald G. Tuten`s First Set of Interrogatories to Department of Environmental Protection filed.
PDF:
Date: 03/24/2006
Proceedings: Petitioner`s Response to DEP`s Pleading of Reasonable Mitigative Conditions filed.
PDF:
Date: 03/13/2006
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 03/13/2006
Proceedings: Notice of Hearing (hearing set for May 2 through 4, 2006; 9:00 a.m.; West Palm Beach, FL).
PDF:
Date: 03/13/2006
Proceedings: Order on Pending Motions (Petitioner shall file a paper within ten days identifying which of DEP`s conditions are acceptable to the Petitioner, if any).
PDF:
Date: 03/10/2006
Proceedings: Respondent Department of Environmental Protection`s First Request for Production of Documents to Petitioner, Donald G. Tuten filed.
PDF:
Date: 03/10/2006
Proceedings: Notice and Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Donald G. Tuten filed.
PDF:
Date: 02/21/2006
Proceedings: Notice of Telephonic Pre-hearing Conference (set for March 6, 2006; 10:00 a.m.).
PDF:
Date: 02/01/2006
Proceedings: DEP`s Response to Petitioner Tuten`s Motion to Strike, and Reply to Petitioner Tuten`s Response to DEP`s Motion filed.
PDF:
Date: 01/30/2006
Proceedings: Notice of Telephonic Pre-hearing Conference (set for February 2, 2006; 2:00 p.m.).
PDF:
Date: 01/27/2006
Proceedings: Motion to Strike DEP`s Motion for More Definite Statement and Request for Hearing filed.
PDF:
Date: 01/27/2006
Proceedings: Donald G. Tuten`s Responseto DEP`s Motion for More Definite Statement and Request for Hearing filed.
PDF:
Date: 01/25/2006
Proceedings: Unilateral Response to Initial Order filed.
PDF:
Date: 01/25/2006
Proceedings: Donald G. Tuten`s Response to Initial Order filed.
PDF:
Date: 01/19/2006
Proceedings: Motion for More Definite Statement filed.
PDF:
Date: 01/18/2006
Proceedings: Initial Order.
PDF:
Date: 01/17/2006
Proceedings: Mandate filed.
PDF:
Date: 01/17/2006
Proceedings: Environmental Resource Permit filed.
PDF:
Date: 01/17/2006
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
J. LAWRENCE JOHNSTON
Date Filed:
01/17/2006
Date Assignment:
01/18/2006
Last Docket Entry:
07/28/2008
Location:
West Palm Beach, Florida
District:
Southern
 

Counsels

Related DOAH Cases(s) (2):

Related Florida Statute(s) (5):

Related Florida Rule(s) (8):