07-004745TL In Re: Tampa Electric Company Willow Oak-Wheeler-Davis Transmission Line Siting Application No. Ta07-15 vs. *
 Status: Closed
Recommended Order on Tuesday, May 13, 2008.


View Dockets  
Summary: The application for a proposed corridor in which to place a transmission line between western Polk County and Brandon is approved; electric and magnetic fields would not affect the health of adjacent property owners.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: TAMPA ELECTRIC )

13ST. JOHNS-PELLICER-PRINGLE, )

16COMPANY WILL0W-OAK-WHEELER- ) Case No. 07-4745TL

22DAVIS TRANSMISSION LINE SITING )

27APPLICATION NO. TA07-15 )

31_______________________________)

32RECOMMENDED ORDER

34Pursuant to notice, a formal hearing was held in this case

45on March 4 and 5, 2008, in Brandon, Florida, before the Division

57of Administrative Hearings, by its assigned Administrative Law

65Judge, Donald R. Alexander.

69APPEARANCES

70For Tampa Electric Lawrence N. Curtin, Esquire

77Company: Gigi Rollini, Esquire

81Holland & Knight, LLP

85Post Office Box 810

89Tallahassee, Florida 32302-0810

92For Department Toni L. Sturtevant, Esquire

98of Environmental Department of Environmental Protection

104Protection: Mail Station 35

1083000 Commonwealth Boulevard

111Tallahassee, Florida 32399-3000

114For Hillsborough Marva M. Taylor, Esquire

120County: Assistant County Attorney

124601 East Kennedy Boulevard

128County Center, 27th Floor

132Tampa, Florida 33602-4156

135For Polk County: Michael E. Duclos, Esquire

142Assistant County Attorney

145Post Office Box 9005

149Bartow, Florida 33831-9005

152For Intervenors: Susan Watson, pro se

1583624 Windchime Lane

161Dover, Florida 33527-4930

164STATEMENT OF THE ISSUE

168The issue for determination is whether and the extent to

178which the proposed corridor by Tampa Electric Company (TECO)

187contained in its Application for Corridor Certification

194(Application) should be approved in whole, with modifications or

203conditions, or denied.

206PRELIMINARY STATEMENT

208Pursuant to Section 403.537, Florida Statutes (2007), 1 on

217March 28, 2007, TECO submitted a petition for determination of

227need for the proposed Willow Oak-Wheeler-Davis 230 kV

235transmission line project with the Florida Public Service

243Commission (PSC). The PSC issued Order No. PSC-07-0522-FOF-EI,

251dated June 21, 2007, determining the need for the transmission

261line.

262On October 12, 2007, TECO filed its Application with the

272Department of Environmental Protection (Department) and paid

279the appropriate application fee. The Application was filed

287under the Transmission Line Siting Act (TLSA), codified in

296Sections 403.52 through 403.5365, Florida Statutes, for a new

305230 kV overhead transmission line and related facilities

313connecting the planned Willow Oak substation west of Mulberry in

323Polk County to the planned Davis substation located in Temple

333Terrace, Hillsborough County, Florida, with an intermediate

340connection to the existing Wheeler substation located along

348Wheeler Road northeast of Brandon in Hillsborough County (the

357Project).

358The various reviewing agencies have submitted reports on

366the Project and have proposed Conditions of Certification. On

375February 4, 2008, the Department issued its Transmission Line

384Site Certification Staff Analysis Report, incorporating the

391reports of the reviewing agencies and proposing a complied set

401of Conditions of Certification. During the certification

408hearing, a revised and updated version of the proposed

417Conditions of Certification was admitted into the record as

426Department Exhibit 4.

429By Notice of Hearing dated October 26, 2007, a

438certification hearing was scheduled on March 4-7 and 10-14,

4472008, in Brandon, Florida. On February 29, 2008, the case was

458transferred from Administrative Law Judge J. Lawrence Johnston

466to the undersigned.

469On February 25, 2008, Tom and Susan Watson, who own

479property in Dover, Florida, immediately adjacent to the proposed

488corridor, filed their Petition to Intervene. Intervention was

496authorized by Order dated February 26, 2008.

503On February 28, 2008, Intervenors filed a Motion for Leave

513to Allow Expert Witness to Appeal (sic) by Phone. This request

524was granted at the certification hearing and Dr. Hanoch Talmor,

534a Gainesville physician, was permitted to testify by telephone

543on behalf of Intervenors.

547The certification hearing was held on March 4 and 5, 2008,

558in Brandon, Florida. (Only two of the days reserved for hearing

569were required to complete the matter.) All notices required by

579law were timely published in accordance with Section 403.527,

588Florida Statutes. The final hearing was conducted for the

597purpose of receiving oral, written, and documentary evidence

605concerning whether the Project should be approved in whole, or

615with such modifications and conditions as the Siting Board deems

625appropriate, or denied under the TLSA.

631At the certification hearing, TECO presented the testimony

639of David M. Lukcic, Manager of Capital Projects and

648Environmental Health and Safety; Chip S. Whitworth, Manager of

657the Transmission Engineering Department and accepted as an

665expert; Philip W. Simpson, a scientist with Environmental

673Consulting & Technology, Inc. (ECT) and accepted as an expert;

683Anthony N. Arcuri, a scientist with ECT and accepted as an

694expert; Darren Stowe, a scientist with ECT and accepted as an

705expert; Jim Brooks, a professional engineer with Black & Veatch

715and accepted as an expert; and Dr. Linda S. Erdreich, a senior

727managing scientist and epidemiologist for Exponent, Inc. and

735accepted as an expert. Also, it offered TECO Exhibits 1-26,

745which were received in evidence. Although Intervenors filed a

754post-hearing written objection to Exhibit 26, that objection is

763overruled and the exhibit has been received in evidence. The

773Department presented the testimony of Ann S. Seiler, an

782Environmental Specialist III and accepted as an expert, and

791Michael P. Halpin, Administrator of its Siting Office and

800accepted as an expert. Also, it offered Department Exhibits 1

810through 4, which were received in evidence. Hillsborough and

819Polk Counties participated in the hearing but did not submit any

830evidence. Intervenors were represented by Susan Watson, a non-

839attorney, who testified on her own behalf. She presented the

849testimony of Quilla Paul Daniels, who now resides in Plant City

860but formerly owned property near the proposed corridor, and

869Dr. Hanoch Talmor, a medical doctor in Gainesville, Florida.

878Intervenors also offered Intervenors Exhibits 1 and 2, which

887were received in evidence.

891A public hearing was held at 7:00 p.m. on March 5, 2008,

903for the purpose of allowing members of the public an opportunity

914to present evidence and testimony. Thirty-five members of the

923public testified, one with a power point presentation. Public

932Exhibits 1-8 were also received in evidence.

939The Transcript (three volumes) of the final hearing was

948filed on April 2, 2008. Intervenors and TECO filed Proposed

958Recommended Orders on April 15 and 16, 2008, respectively, which

968have been considered in the preparation of this Recommended

977Order. The Department has joined in TECO's filing.

985FINDINGS OF FACT

988Based upon all of the evidence the following findings of

998fact are determined:

1001I. Parties

10031. The TLSA establishes TECO and the Department as parties

1013to this proceeding, and the following became parties upon their

1023timely filing of a notice of intent to be a party, which each

1036has done: Florida Department of Transportation (DOT),

1043Department of Community Affairs (DCA), Southwest Florida Water

1051Management District (SWRWMD), and Hillsborough County. See

1058§ 403.527(2), Fla. Stat. Although the Florida Fish and Wildlife

1068Conservation Commission (FFWCC) did not become a party, the

1077Department accepted its comments and recommended conditions in

1085the agency report. On February 21, 2008, the City of Temple

1096Terrace was accepted as a party without objection after the

1106Stat. On February 25, 2008, Tom and Susan Watson filed a

1117Petition to Intervene. Although this was after the deadline

1126established in the prehearing schedule for becoming a party,

1135TECO did not object based upon an agreement to conditions

1145relating to the presentation of witnesses by the Watsons.

1154Intervenors agreed to those conditions. Finally, Polk County

1162did not file a notice of intent to be a party, but appeared

1175without objection at the certification hearing.

1181II. The Application

1184A. Project Description

11872. Generally, an electrical transmission line's purpose is

1195to transport large amounts of electricity from a generating

1204facility to one or more substations. At the substation, the

1214electricity can be either increased or reduced in voltage

1223through transformers and other electrical equipment for further

1231safe and practical transportation, or distribution directly to

1239customers.

12403. TECO is seeking certification of a corridor between the

1250planned Willow Oak substation located at the intersection of

1259State Road 60 and Turner Road just northwest of Mulberry in Polk

1271County, the existing Wheeler substation in Valrico, and the

1280planned Davis substation in Temple Terrace, a span of

1289approximately thirty miles, within which it will ultimately

1297construct the line on a narrow right-of-way (ROW). 2 Once all

1308property interests in the ROW are acquired, the boundaries of

1318the corridor will shrink to the typical width of the 25 to 100-

1331foot ROW. In some cases, the ROW will be 300 feet wide.

13434. The objectives of the Project are to address: (a) the

1354need, as confirmed by the PSC, to provide additional

1363transmission reinforcement to the existing 230 kV transmission

1371network north of State Road 60, west of the planned Willow Oak

1383substation, and east of the existing River substation in a

1393reliable manner consistent with the North America Electric

1401Reliability Council (NAERC) and the Florida Reliability

1408Coordinating Council (FRCC) and other applicable standards; (b)

1416the need to serve the increasing load and customer base in the

1428Project service area; and (c) the need to provide for another

1439electrical feed via a separate ROW path, thereby reducing the

1449impact of a loss of existing transmission facilities on a common

1460ROW.

1461B. Need for the Line

14665. In earlier proceedings before the PSC, it determined a

1476new 230 kV transmission line between the planned Willow Oak, the

1487existing Wheeler, and the planned Davis substations is needed,

1496taking into account the need for electric system reliability and

1506integrity and the need to provide abundant, low cost electrical

1516energy to assure the economic well-being of the citizens of the

1527State. The PSC found that the planned Willow Oak substation and

1538the planned Davis substation constitute the appropriate starting

1546and ending points for the proposed line. The PSC noted that the

1558additional transmission capacity will be needed by 2012 and

1567recognized that the Siting Board will make the final

1576determination concerning the route selection upon consideration

1583of the factors and criteria specified in Section 403.529,

1592Florida Statutes.

1594C. Transmission Line Design

15986. The typical design for the transmission line will be a

1609single-circuit unguyed concrete pole structure using concrete or

1617crushed stone back fill. The poles are proposed to range in

1628height from 80 feet above grade to 125 feet above grade, with

1640the conductors framed in a vertical configuration. Three

1648conductors will be used, and each of the three conductors is

1659anticipated to be a 1,590 aluminum conductor steel supported

1669wire, with 45 strands of annealed aluminum that lay over seven

1680steel strands. The conductor is 1.504 inches in diameter with a

1691weight of approximately 1.7 pounds per foot. There will also be

1702a smaller overhead ground wire to provide shielding and

1711lightening protection for the conductors. The maximum current

1719rating is 2,560 amperes. In some locations there could be a

173169 kV and a distribution underbuild. Additionally, the vertical

1740configuration will be adjusted to a horizontal configuration in

1749the vicinity of the South Lakeland Airport to enable the height

1760to be lowered to approximately 46 feet above grade to account

1771for the air traffic.

17757. The open span length between structures will typically

1784vary between 300 and 800 feet, depending on site-specific

1793conditions. Both pole height and span length may vary to

1803accommodate various conditions that may be encountered.

18108. Access roads and structure pads will be constructed

1819only where necessary to provide access for construction,

1827maintenance, and emergency restoration. Where constructed, the

1834typical road top width will be 14 feet, with a 2-to-1 side

1846slope, and a minimum elevation of between six inches and two

1857feet. Structure pads will have variable sizes but are typically

186775 feet by 75 feet. These are designed to support the equipment

1879needed to install and maintain the transmission line. Culverts

1888will be installed beneath access roads and structure pads with

1898the specific design reviewed by the appropriate regulatory

1906agencies. The design will be similar to previously approved

1915designs.

19169. The design of the transmission line complies with good

1926engineering practices. The transmission line will be designed

1934in compliance with all applicable design codes, including the

1943National Electrical Safety Code, the Department's regulations on

1951electric and magnetic fields, the DOT Utility Accommodation

1959Manual, the requirements of applicable regulatory agencies

1966including the Department, SWFWMD, and PSC, as well as TECO's own

1977design standards.

197910. The Project assures the citizens of Florida that

1988operation safeguards are technically sufficient for their

1995welfare and protection.

1998D. Transmission Line Construction

200211. The initial phase of construction is to clear the ROW.

2013Since much of the length of the corridor is collocated, that is,

2025grouped or placed side by side, with existing roads and utility

2036facilities, the need for clearing has been minimized. Clearing

2045will consist mainly of tree trimming and the selective removal

2055of trees. In areas owned by TECO clearing will range from a

2067width of 25 to 100 feet. In forested areas in which a new line

2081will be located, clearing will also be limited to 25 to 100 feet

2094in width. In wetlands, trees capable of exceeding 14 feet in

2105height that could come in conflict with the line will be removed

2117by hand clearing or use of very low ground pressure equipment.

2128Low growing herbaceous vegetation will not be cleared from

2137wetlands.

213812. After the ROW is cleared, any necessary access roads

2148and structure pads will be constructed. Typically, access roads

2157and pads are not required in all areas.

216513. The next phases of construction involve the physical

2174transmission line construction. Initially, the materials are

2181assembled on the jobsite. Next, holes are augered at each pole

2192location. The structures are framed with insulators and

2200hardware that may be installed prior to the setting of the

2211structure. After all appropriate operations relative to the

2219assembly and framing have been performed on the ground, the top

2230section of the structure is lifted with a crane and set on the

2243previously installed base section. The two sections are then

2252jacked together. Typically, the pole is embedded into the

2261ground approximately 25 to 35 feet deep.

226814. After the poles have been installed and the hardware

2278and equipment on the pole, including the insulators, have been

2288installed, a wire pulling operation is conducted. In this

2297phase, reels of wire, wire tensioning, and retarding equipment

2306all will be mobilized. The locations generally include the dead

2316end structures, but the length of the wire that can be placed on

2329a reel may dictate the location of some of the equipment. Each

2341structure must be equipped with hanging blocks or pulleys so the

2352conductors may be pulled through smoothly for the entire length

2362of the reel. Once the conductors are pulled in and secured at

2374the dead end structures, the wires are sagged and tensioned

2384appropriately to maintain vertical clearances. Finally, the

2391pulleys are removed from each structure and the conductor is

2401secured to the insulator attachment.

240615. The final stage of construction is the cleanup stage.

2416This involves inspection of the entire project to ensure that

2426all material has been cleaned up, removal of all silt fences,

2437hay bales, excess spoils, or dirt from the foundation

2446excavation, and ensuring that the gates and fences have been

2456properly restored or installed.

246016. Throughout construction, sedimentation management

2465techniques, such as the use of silt screens and hay bales, or

2477other best management practices, will be employed as necessary

2486to minimize potential impacts from erosion and sedimentation.

249417. While each phase of construction will typically take

2503up to two weeks in a particular location, the construction crew

2514will normally be active for two to four days at a typical

2526structure location after the necessary pads have been installed.

2535Construction for the entire project is expected to last from

2545twelve to eighteen months.

2549E. Methodology for Choosing TECO Corridor

255518. TECO established a multi-disciplinary team to identify

2563and evaluate routing alternatives within the Project Study Area.

2572This multi-disciplinary team was comprised of experts in land

2581use, engineering, and environmental disciplines. The team,

2588which included both TECO representatives and outside consultants

2596from ECT, engaged in a number of activities including data

2606collection, preparation of a regional screening map, the

2614identification of alternative route segments, the development of

2622criteria to evaluate the route segments, the actual evaluation

2631both quantitatively and qualitatively of these routes, and the

2640ultimate selection of the preferred route which was accepted by

2650TECO. Members of the public assisted in this effort throughout

2660the development of the proposed corridor.

266619. The objective of the corridor selection study was to

2676select a corridor that could be certified balancing land use,

2686socioeconomic, environmental, engineering, and cost

2691considerations. Corridor selection methodologies were designed

2697to be integrative of multidisciplinary siting criteria, regional

2705and objective in decision-making, sensitive to social and

2713environmental conditions, responsive to regulatory requirements,

2719reflective of community concerns and issues, and capable of

2728accurate documentation and verification.

273220. The selection process consisted of three tasks

2740including (a) project and study area definition; (b) resource

2749mapping and alternative route delineation; and (c) evaluation of

2758alternative routes and selection of the proposed corridor. Due

2767to the dense and urban nature of the TECO service area, it was

2780difficult to find areas with no population or development for a

2791corridor.

279221. The multidisciplinary team developed a regional

2799screening map, received in evidence as TECO Exhibit 14, which

2809was prepared by the team using generally publicly available

2818information including Geographic Information System (GIS)

2824mapping. The map data were collected from various state

2833agencies and local governments. Information was gathered from

2841the Florida Geographic Data Library (which distributes GIS

2849data), the Florida Natural Areas Inventory, and most of the

2859agencies involved in this proceeding. Various environmental and

2867land use data were mapped as were existing infrastructure, and

2877information gathered on roads, railroads, rivers, waterbodies,

2884and the like. These represented primarily siting constraints or

2893siting issues within a particular study area. The regional

2902screening map was then used to identify route segments.

291122. The licensing team used the regional screening map as

2921the first step in identifying the various route segments that

2931connected the three substation locations at Davis, Wheeler, and

2940Willow Oak.

294223. TECO's multi-disciplinary team gathered data on siting

2950opportunities and constraints within the study area and

2958identified forty-one line segments which could be assembled into

2967a total of four hundred twenty-three potential route

2975combinations. Using a predefined set of ten environmental, land

2984use, and engineering criteria, each route segment was measured

2993for those resources. Using a software program developed by ECT,

3003the data was entered and totaled for each route combination.

3013Using the weights developed by the licensing team for each

3023criterion, the weights were applied and tabulated for all

3032routes. The routes were then ranked in order from best to worst

3044based on the weighted scores.

304924. Once the rankings were performed, the top ranked

3058routes were subjected to further evaluation. These routes were

3067high in scoring but somewhat different in the path that they

3078took between the three substation locations. They were then

3087evaluated using predetermined qualitative criteria, which

3093included such things as homes in proximity to the route. The

3104analysis included an examination of where the homes were located

3114along the route, whether they are scattered and easily avoided

3124with the placement of a corridor, or whether they are clustered

3135together in a fashion making it difficult to avoid them in

3146placement of the corridor. Numerous driving surveys of the

3155various routes were performed during this phase where the routes

3165were publicly accessible, and a helicopter flyover was also

3174completed.

317525. At the completion of the evaluation, a recommendation

3184was made for a proposed route, which was accepted by TECO. Once

3196the proposed corridor location was selected, the team examined

3205various siting issues within and along the route and developed

3215corridor boundaries of varying widths. In some areas a much

3225wider width was needed to provide flexibility for siting, while

3235a more narrow width was needed in areas where siting issues were

3247less and where there was a reasonable certainty concerning where

3257the ROW could be located.

326226. TECO also engaged in an extensive public outreach

3271program. The public participation program included open houses,

3279mass mailings, surveys, a toll-free telephone number, newsprint

3287advertisements, a website, and meetings with regulatory agencies

3295and local elected officials.

329927. There were three direct mailings as a part of the

3310public outreach program. The first mailing was a notification

3319of four open houses that were to be held. One open house was

3332conducted in Polk County, while three (Seffner, Plant City, and

3342Temple Terrace) were conducted in Hillsborough County.

3349Following the completion of the open house process, a second

3359mailing was sent providing a summary of the survey results. The

3370third mailing notified recipients that the Application was filed

3379on October 12, 2007. Approximately 4,500 recipients were

3388identified for these mailings. The names of the recipients were

3398obtained by identifying the properties located within 500 feet

3407in both directions from the centerline of the routes. The

3417Hillsborough and Polk County Property Appraisers' offices were a

3426source for this information as well as the TECO customer

3436database. The Hillsborough County Office of Neighborhood

3443Relations was consulted for a list of registered homeowners'

3452associations. For the homeowners' associations, which numbered

3459around two hundred, those that were within one mile in both

3470directions from the centerline of the route were notified. The

3480recipients of the notifications included property owners and

3488tenants or lessees. The Hillsborough County Large Facilities

3496Ordinance was used as a guide to identify the area of the

3508notifications, although that Ordinance mandates a 250-foot

3515notification distance from the centerline of the routes, and

3524TECO actually used 500 feet on both sides of the centerline.

353528. The same distances were not used for recipients of

3545each of the mailings. The distances described in Finding of

3555Fact 27 were used for the first two mailings. For the third

3567mailing, the proposed corridor had been selected. As a result,

3577the distance was measured not from the centerline of the route,

3588but from the edge of the corridor. This was done because in

3600some areas the corridor was extended beyond the 500-foot limit

3610and potential recipients would have been missed had the area of

3621inclusion not been extended. Additional mailings are planned if

3630the corridor is certified. Additional informational open houses

3638will also be held, and the transmission structures and potential

3648locations will be identified at that time so the public can be

3660informed.

366129. As part of the public outreach, TECO also ran a series

3673of four advertisements in local newspapers. The first newspaper

3682advertisement was run on February 20, 2007, in The Tampa

3692Tribune , Lakeland Ledger , Mulberry Press , Temple Terrace News ,

3700and Brandon News . Two more advertisements were run on

3710February 28 and March 1, 2007, in The Tampa Tribune and Lakeland

3722Ledger . These advertisements were in addition to the required

3732public notices of the application being filed, the certification

3741hearing being scheduled, and the public hearing being scheduled

3750that were run on October 30 and December 27, 2007, and

3761February 18, 2008. The required advertisements were run in The

3771Tampa Tribune , Lakeland Ledger , and The Winter Haven News Chief .

3782The February 18 notice of public hearing was also run in The

3794Polk County Press .

379830. Copies of the Application were maintained for public

3807inspection during the certification process at the TECO offices

3816in Tampa and Winter Haven. In addition, a copy of the

3827Application was provided to the John Germany Public Library in

3837downtown Tampa, the Polk County Library in Bartow, and the

3847Temple Terrace Library in Temple Terrace. All of the

3856applications available for public inspection were updated as

3864additional information was submitted to the Department.

387131. The public participation program provided substantive

3878input to the route evaluation study in terms of study area

3889boundary, siting opportunities, and constraints in the area,

3897identification of route segments to be evaluated, and weights to

3907be assigned to the route evaluation criteria. The cumulative

3916responses of the public's ranking of the weights to apply to

3927TECO's siting criteria were very comparable to the team's

3936weighting indicating little significant difference in route

3943ranking.

394432. Once the proposed alignment was identified, the multi-

3953disciplinary team delineated the boundaries or width of the

3962corridor to provide flexibility for locating the eventual ROW

3971within that corridor.

397433. State, regional, and local agencies with regulatory

3982authority of the Project reviewed the Application and submitted

3991to the Department a report concerning the impact of the Project

4002on matters within their respective jurisdictions, as required by

4011Section 403.526(2), Florida Statutes. The Department compiled

4018the reports and made a recommendation that the Project be

4028granted approval subject to appropriate conditions. See

4035Department Exhibit 2.

403834. The Department, SWFWMD, and DOT stipulated as to the

4048certification of the Project subject to conditions of

4056certification proposed by the Department. On April 16, 2008,

4065the City of Temple Terrace and TECO entered into a separate

4076stipulation for certification. None of the agencies involved in

4085the review process recommended that the proposed corridor be

4094denied or modified. No alternate corridors were filed for

4103consideration by any of the parties. Further, no additional

4112conditions of certification were proposed by any party at the

4122certification hearing.

4124III. Detailed Description of the TECO Corridor

413135. The proposed corridor provides significant

4137opportunities for collocation with other linear facilities such

4145as roads and transmission lines which provide the opportunity to

4155reduce the amount of new access road construction, impacts to

4165wildlife habitat, and other impacts. The width of the proposed

4175corridor varies along the route to provide flexibility within

4184the corridor to avoid impacts to such areas as existing

4194developments, large wetland areas, and a bald eagle's nest.

4203A. From the Planned Davis Substation to the Existing

4212Wheeler Substation

421436. The western end of the corridor begins at the planned

4225Davis substation site in Temple Terrace which is a large parcel

4236owned by TECO. There is an existing substation there called the

4247River substation and the planned Davis substation will be

4256located in proximity to that existing substation. Land use is

4266generally open land. This portion of the corridor is bordered

4276on the west by the Hillsborough River and has a large area of

4289pasture land on the east side with mixed hardwood swamp and

4300cypress swamp on the western portion.

430637. Leaving the TECO substation property, the corridor

4314travels east across Interstate 75 (I-75) and the width of the

4325corridor in this area narrows to approximately 300 feet. This

4335is also TECO property. As the corridor passes I-75 it

4345approaches the Tampa Bypass Canal, which is owned by the SWFWMD.

4356The corridor is expanded in this area to minimize the impacts on

4368the SWFWMD operations along the Bypass Canal and on the

4378recreational facilities located in the southwestern portion of

4386the parcel used by Temple Terrace. Land is low density

4396residential with a cemetery and a recreational facility. The

4405property has pine/oak woods along the northwestern corner and a

4415mixed hardwood swamp on the northeastern corner. The property

4424is bisected north and south by the Tampa Bypass Canal.

443438. Once the SWFWMD property is exited the corridor turns

4444due east for approximately 5.4 miles until south of Lake

4454Thonotosassa, where it turns south. This portion is owned by

4464TECO. The corridor is 300 feet wide. The western portion is

4475primarily developing and developed lands surrounding the

4482corridor and, as it proceeds east, it crosses more rural lands,

4493pasture, strawberry fields, row crops, various agricultural

4500operations, cattle grazing, and some citrus groves. A portion

4509of the corridor contains a natural gas pipeline within TECO's

4519property. In addition to the agricultural vegetation, there is

4528a pine/oak area, some marsh, and some emergent aquatic

4537vegetation, along with some ponds. The corridor crosses Baker

4546Creek, a tributary to Lake Thonotosassa, which is north of the

4557corridor. A mixed hardwood swamp and a cypress swamp are found

4568here.

456939. The proposed corridor then turns south and approaches

4578areas of developing or developed lands. TECO's fee ownership

4587extends to the south. The corridor crosses Interstate 4 and, at

4598the beginning of its intersection with U.S. Highway 92, the

4608corridor has been expanded from approximately 3,100 feet up to

46195,100 feet in width to avoid a bald eagle's nest and the

4632scattered residences in the area. The widened corridor proceeds

4641south to State Road 574 or Martin Luther King Boulevard. Land

4652use is agricultural, low density residential, and undeveloped

4660property. This area of the corridor contains some pine/oak

4669woods, large areas of marsh, some crop land, some mixed hardwood

4680swamp, and scattered residential development.

468540. Once the corridor crosses State Road 574 it narrows

4695again to approximately 300 feet in width and is located on TECO

4707property. The corridor then proceeds south to the existing

4716Wheeler substation located off of Wheeler Road in Valrico.

4725There is a large amount of development to the west of the

4737corridor and developing lands to the east of the corridor.

4747B. From the Existing Wheeler Substation to the Planned

4756Willow Oak Substation

475941. From the existing Wheeler substation near Wheeler Road

4768the corridor proceeds south slightly more than one mile and then

4779turns east for approximately one mile before turning south to

4789State Road 60. In this portion of the corridor the width is

4801approximately 300 feet and it is located on TECO property.

4811There are residential properties in the vicinity of the

4820corridor, including the Diamond Hills and Sommerset

4827subdivisions. The land use is generally medium density

4835residential surrounding the corridor and also some agricultural

4843lands. Land uses in this area include pasture land, pine/oak

4853woods, crop land, marsh, open land, ponds, mixed hardwood

4862conifer swamp, and pine flat woods.

486842. The corridor proceeds east along State Road 60, which

4878is a major transportation corridor. The corridor is expanded to

4888approximately 2,000 to 3,000 feet in this area to allow

4900opportunities to follow other linear facilities that are located

4909south of State Road 60, such as other transmission lines or

4920roads. There are scattered residential properties with

4927agricultural uses, strawberry fields, pastures, and some citrus

4935in the area. Phosphate lands are located to the south of this

4947segment of the corridor. The corridor proceeds along to the

4957east. The majority of this area is reclaimed phosphate mining

4967lands.

496843. The final segment of the proposed corridor has again

4978been expanded to approximately 4,000 feet wide as it continues

4989along both sides of State Road 60 and both sides of Old Hopewell

5002Road. As the roads converge, the corridor is narrowed to

5012approximately 500 feet. From there it proceeds to the planned

5022Willow Oak substation in western Polk County. In this area

5032there is existing development surrounding the substation site

5040and proposed development along State Road 60. The South

5049Lakeland Airport is in this area. Along State Road 60 there is

5061a mix of commercial, residential, and some industrial

5069properties. The Willow Oak substation site is located within

5078open land.

5080IV. Compliance With Section 403.529(4) Criteria

5086A. Ensure Electric Power System Reliability and Integrity

509444. The PSC found that there are regional transmission

5103system limitations in northeast Hillsborough County. By 2012,

5111the existing 230 kV transmission network will not have

5120sufficient capability to provide reliable electric service to

5128the existing and proposed substations. The PSC also found that

5138some of the projected load to be served by the planned future

5150distribution substations will be located further east and north

5159of the existing 230 kV transmission network. The PSC determined

5169that the proposed transmission line is needed by March 2012 to

5180(a) provide additional transmission reinforcement to the

5187existing 230 kV transmission network north of State Road 60,

5197west of Willow Oak substation, and to the east of the existing

5209River substation in a reliable manner consistent with the NERC,

5219FRCC, and other applicable standards; (b) serve the increasing

5228load and customer base in the projected service areas; and (c)

5239provide for another electrical feed via a separate ROW path,

5249thereby reducing the impact of a loss of the existing

5259transmission facilities on a common ROW. The PSC concluded that

5269the Project is needed to preserve electric system reliability

5278and integrity.

5280B. Meet the Electrical Energy Needs of the State in an

5291Orderly and Timely Fashion

529545. The PSC recognized that TECO's planning studies

5303indicate that the proposed line is needed by March 2012 to

5314provide sufficient capability to provide reliable service to

5322existing and proposed substations.

532646. The location of the proposed transmission line on the

5336proposed corridor would meet the electrical energy needs of the

5346state in a timely fashion.

5351C. Comply with the Nonprocedural Requirements of Agencies

535947. Construction, operation, and maintenance of the

5366proposed corridor will comply with applicable nonprocedural

5373requirements of agencies.

537648. The Department has concluded that the Project as

5385proposed will comply with all applicable Department statutes,

5393rules, policies, and procedures.

5397D. Be Consistent with Applicable Local Government

5404Comprehensive Plans

540649. The Polk County Comprehensive Plan identified electric

5414transmission and distribution facilities as a permitted use in

5423all land use categories. In the Future Land Use Element of the

5435Hillsborough County Comprehensive Plan, there are an objective

5443and several policies that address bulk transmission lines. The

5452policies address the locational criteria and public input. The

5461policies will be met by the proposed transmission line. The

5471City of Temple Terrace's Comprehensive Plan does not address

5480bulk transmission lines.

548350. After certification of this project, TECO will acquire

5492the necessary property interests in a ROW within the certified

5502corridor for placement of the line. Construction of

5510transmission lines on such established ROWs is excepted from the

5520definition of "development" in Section 163.3164(5), Florida

5527Statutes. Accordingly, the provisions of the local

5534comprehensive plans related to "development" that have been

5542adopted by the local governments crossed by the line are not

5553applicable to this project.

555751. No variances or exemptions from applicable state or

5566local standards or ordinances are needed for the project.

5575E. Implementation of Legislative Intent in Section 403.521

5583a. The Need for the Line as a Means of Providing

5594Abundant Low-Cost Electrical Energy

559852. The PSC determined that the proposed line is needed

5608taking into account the factors set forth in Section 403.537,

5618Florida Statutes.

562053. The PSC found that TECO evaluated three alternatives

5629to the Project. All three were transmission modifications to

5638the proposed ROW that used a portion of, or the entire existing,

5650common ROW. The PSC accepted TECO's rejection of the

5659alternatives primarily because of economics and reliability

5666concerns. The PSC found that the proposed line will assure the

5677economic well-being of the citizens of the state by serving

5687projected new electric load in the region and improving the

5697region's electric reliability by minimizing the region's

5704exposure to single contingency events.

5709b. Impact Upon the Public

571454. The proposed line is appropriate from a land use

5724perspective. The Project takes advantage of the opportunity to

5733be collocated with other transmission lines, roadways, and ROWs.

5742By following these existing linear features, the corridor

5750conforms to existing and future development patterns and

5758minimizes intrusion into residential areas. As a result, the

5767proposed line is in proximity to relatively few residences.

577655. The line as proposed will comply with all applicable

5786nonprocedural agency standards, including the Department

5792standards in Florida Administrative Code Rule Chapter 62-814

5800limiting the electric and magnetic fields associated with new

5809transmission lines.

581156. TECO proposes to use five different configurations for

5820the transmission line, depending upon the location. The options

5829include a 230 kV single circuit roadside, a 230 kV single

5840circuit roadside with a 69 kV underbuild, a 230 kV single

5851circuit roadside with 69 kV and 13 kV distribution underbuild, a

5862230 kV single circuit for the South Lakeland Airport, and a

5873230 kV single circuit for use in the 300-foot existing TECO ROW.

5885For each of these configurations the Department's rule requires

5894that the electric and magnetic fields (or energy forces) be

5904calculated to ensure compliance. The electric field is what is

5914created underneath and outside of a transmission line as a

5924result of placing voltage on the conductor. It is a byproduct

5935of placing voltage on the conductor. The magnetic field is

5945created as a result of the current traveling along the

5955conductor. It is generally a magnetic flux field that surrounds

5965the conductors and the transmission lines.

597157. Those portions of Florida Administrative Code Rule

5979Chapter 62-814 that are applicable to this Project establish

5988maximum values for electric and magnetic fields. The electric

5997field is expressed as a kilovolt meter (kV/m) and compliance is

6008required both within the ROW and at the edge of the right-of-way

6020for the transmission line. The magnetic field is expressed as

6030milliGauss (mG) and compliance is determined at the edge of the

6041ROW.

604258. Compliance with the electric and magnetic field

6050requirements was calculated for each of the configurations that

6059may be utilized for the Project. The results were then compared

6070to the requirements of Florida Administrative Code Rule 62-

6079814.450(3). See TECO Exhibit 21. The maximum expected values

6088from all configurations for the electric fields within the ROW

6098and at the edge of the ROW and for the magnetic fields at the

6112edge of the ROW are all below the values set forth in the rule.

612659. The maximum voltage and current that is ever

6135anticipated for the line during its life are used in making the

6147calculations. However, it is highly unlikely that this

6155condition would occur. It is anticipated that the maximum

6164condition would occur less than five percent of the time while

6175the transmission line is operating. In order to operate at the

6186maximum level the conductor must be operating at its maximum

6196temperature and the conductor would be at its lowest point in

6207the span to create that condition. There would also need to be

6219some type of system disturbance that would cause a maximum

6229condition to occur. This would be a worst case scenario.

6239Levels for electric fields will be less at the normal operating

6250levels and magnetic fields about fifty percent less.

625860. Intervenors own property and live within the area of

6268the expanded corridor between U.S. Highway 92 and State Road 574

6279in Dover. In this area TECO owns a 300-foot ROW originally

6290considered for the corridor, which contains an eagle's nest.

6299While this area is near the Intervenors' property, the proposed

6309corridor is the entire area up to 5,100 feet in width, and the

6323actual ROW location for the line has not yet been determined.

6334Intervenors are primarily concerned about the potential health

6342effects to their son caused by exposure to electric and magnetic

6353fields from the transmission line in the vicinity of their

6363property. In support of these concerns, they presented the

6372prefiled, written testimony of Dr. Hanoch Talmor, a medical

6381doctor in Gainesville, Florida, who has treated their son for

6391over fifteen years. Doctor Talmor is a board-certified

6399pediatrician who now specializes in the area of general holistic

6409medicine.

641061. In his written statement Dr. Talmor states that

6419Intervenors' son is at present nonambulatory and nonverbal. He

6428also testified that he displays severe chemical sensitivities

6436and is listed on the state chemically sensitive lists. Although

6446he is not a neurologist, Dr. Talmor opined that because of the

6458son's neurological involvement and his extensive medical

6465history, he would be adversely affected by high voltage power

6475lines near his home. He further testified that the son has

6486seizures which can be affected by smells, sounds, visual

6495stimuli, sleep patterns, and allergic reactions.

650162. During cross-examination, Dr. Talmor acknowledged that

6508he is not familiar with the levels of electric and magnetic

6519fields expected to result from this transmission line in the

6529vicinity of Intervenors' property. Even so, he opined that the

6539only safe levels of electric and magnetic fields with regard to

6550human exposure would be at levels of zero. He admitted,

6560however, that electric devices typically found in the household

6569such as clocks, ovens, refrigerators, televisions, electric

6576blankets, and the like, as well as electric wiring in the house,

6588would be expected to produce electric and magnetic fields to

6598which a person living in the house would be exposed. At the

6610certification hearing, Dr. Talmor also discussed various

6617research articles concerning this subject. In formulating his

6625opinions, however, Dr. Talmor had reviewed only summaries and

6634excerpts of the studies, rather than the complete studies.

664363. TECO presented the testimony of Dr. Laura S. Erdreich,

6653an epidemiologist, who is familiar with the configuration for

6662the transmission ROW that is proposed to be used in the vicinity

6674of Intervenors' residence. Doctor Erdreich testified that she

6682is familiar with the levels expected to be produced from the

6693transmission line at the edge of the ROW. With regard to

6704electric fields, Dr. Erdreich testified that the lowest level

6713that has ever been proposed as being necessary for the

6723protection of human health is 4.2 kV/m. This was by an

6734organization called the International Commission for Non-

6741Ionizing Radiation Protection (ICNIRP). The organization is

6748based in Europe and is sponsored by the World Health

6758Organization. The level that organization recommended is more

6766than twice the maximum level of 2.0 kV/m found in Florida

6777Administrative Code Rule 62-814.450(3)(a). The maximum expected

6784electric fields at the edge of the ROW for the Project in the

6797vicinity of Intervenors' residence is 0.1 kV/m.

680464. For magnetic fields, Dr. Erdreich testified that the

6813ICNIRP proposed a level of 833 mG as being protective of human

6825health based on exposure. This is the lowest level that has

6836been proposed by any regulatory authority or similar body based

6846on potential health effects. In contrast, Florida

6853Administrative Code Rule 62-814.450(3)(d) provides in relevant

6860part that the "maximum magnetic field at the edge of a 230 kV or

6874smaller transmission ROW . . . shall not exceed 150 mG." This

6886value is much greater than the 13.6 mG maximum level expected at

6898the edge of the TECO ROW and in the vicinity of Intervenors'

6910home. Under typical operational conditions, the expected

6917magnetic field would be approximately 7 mG, which is less than

6928one percent of the health-based exposure limit recommended by

6937the ICNIRP.

693965. Doctor Erdreich also testified that she is familiar

6948with the research that has been conducted concerning health

6957effects from environmental exposure to electric and magnetic

6965fields. The research includes epidemiological studies of humans

6973in the natural environment, laboratory studies which typically

6981expose all animals to high levels often for nearly their entire

6992lifetime, and studies of cells and tissues in laboratories to

7002try to isolate the mechanism that may affect humans. The amount

7013of research being performed has been reduced over the last few

7024years because, despite considerable research, an adverse effect

7032from exposure to humans at environmental levels has not been

7042substantiated. Additionally, causal associations between

7047exposure and health effects have not been found when the data

7058and research have been reviewed by committees of scientists of

7068various disciplines. Doctor Erdreich testified that she is

7076aware of the studies that were referred to by Dr. Talmor as well

7089as other studies on the subject. Although the subject of

7099exposure to low levels, even on a long-term basis, such as

7110levels less than 10 mG, has been studied extensively, she noted

7121that the findings have been that magnetic fields have no known

7132effect on the human body until exposure to levels well above

71431,000 mG.

714666. The United States Government does not regulate

7154electric and magnetic exposure except in occupational settings.

7162There are no requirements for regulation of transmission lines

7171in these areas. The State of Florida is one of only a few

7184states that have such requirements. There is no existing body

7194of research demonstrating that adverse health consequences

7201result from exposure to electric and magnetic fields at the

7211levels expected to result from the 300-foot ROW single pole

7221configuration that is proposed for the vicinity of Intervenors'

7230property. Doctor Erdreich opined that these levels do not pose

7240a threat of adverse health effects to the population near the

7251edge of the ROW. She further opined that in the unlikely

7262circumstance that the edge of the ROW for the transmission line

7273would be placed at the edge of the residence of the property,

7285the levels of electric and magnetic fields from the transmission

7295line would still not create a health concern. She also stated

7306that her opinion would be the same if one of the residents were

7319shown to have an illness that resulted in a chemical

7329sensitivity. She based her opinions on the fact that there is

7340no evidence demonstrating any correlation between this exposure

7348and adverse health effects. Finally, Dr. Erdreich testified

7356that no group has ever suggested that there is a need for lower

7369levels near hospitals or convalescent facilities or other places

7378where physical therapy occurs.

738267. The levels of electric and magnetic fields from the

7392transmission line will decrease as one moves further from the

7402edge of the ROW. The levels expected from the transmission

7412line, which are already well below the State requirements and a

7423small fraction of the lowest levels that have ever been

7433suggested as being required for the protection of human health,

7443are similar to the levels that would be expected to result from

7455common household appliances.

745868. Mrs. Watson testified that her residence has

7466electricity and electric household appliances such as air-

7474conditioning, television, refrigerator, and a vacuum cleaner.

7481All of these devices produce electric and magnetic fields at

7491levels in the range of what would be expected from the TECO

7503transmission line. Additionally, there is natural exposure to

7511magnetic fields and electric and magnetic fields from electrical

7520devices that are encountered in everyday life.

7527ansmission lines can generate audible noise as a

7535result of irregularities that collect on the conductor. During

7544periods of fair weather dust can collect on the conductor and

7555that may cause low levels of audible noise. When rain is

7566experienced, the dust is washed off but replaced with water

7576droplets on the conductor that create a condition that results

7586in slightly higher levels of audible noise. The noise levels

7596experienced during rainfall events are temporary, and the noise

7605is reduced as soon as the water droplets evaporate from the

7616conductor.

761770. The expected levels of noise are generally calculated

7626using a program called the Bonneville Power Administration Field

7635Effects Program. The information utilized to make the

7643calculations includes the conductor size, the configuration of

7651the transmission line, and the voltage expected.

765871. The calculations performed for the transmission line

7666show that the audible noise levels at the edge of the ROW during

7679fair weather would range from 16.1 dBA, which is decibels of

7690noise in a range that can be heard, to a high of 22.5 dBA.

7704During periods of rainfall the expected audible noise at the

7714edge of the ROW ranges from a low of 41.1 dBA to a high of

772947.5 dBA. For the ROW configuration that is proposed for the

7740area including the Watson property, the expected levels during

7749fair weather are a maximum of 16.1 dBA and during foul weather a

7762maximum of 41.1 dBA at the edge of the ROW. The noise levels

7775will decrease as one moves away from the edge of the ROW. Also,

7788during rainfall events, when the maximum noise levels are

7797expected, the rain will tend to mask the sound from the

7808transmission line.

781072. Studies that have been prepared on this issue indicate

7820that complaints concerning noise are primarily related to

7828interference with sleep. The studies indicate that to minimize

7837the potential of interference with sleep, the noise level

7846outside of the home should not exceed 50 dBA. The maximum

7857expected noise level from the Project will not exceed 50 dBA.

7868Mr. Brooks, TECO's expert who testified on this issue, stated

7878that he had never had an occasion to deal with a noise level

7891complaint during his thirty-seven years of experience with

7899transmission lines.

790173. TECO Exhibit 22 contains a summary of the audible

7911noise expected from the transmission line for the various

7920configurations. It also contains a chart with the noise levels

7930expected from common activities for comparative purposes. The

7938maximum fair weather audible noise from any of the five

7948configurations would be comparable to the levels that one would

7958encounter in a bedroom at night. The maximum levels for the

7969same configurations during foul weather would be comparable to

7978what one might experience in a quiet office or a living room.

7990The levels for the configuration to be utilized in the area of

8002the Watson property are below the maximums for the Project and

8013significantly less than levels expected at a quiet office or

8023bedroom at night.

802674. At the public portion of the certification hearing,

8035thirty-five members of the public uniformly testified in

8043opposition to the Project, as proposed. A number of those

8053testifying expressed concern about the impact of the Project on

8063property values, the possible effects of the electric and

8072magnetic fields expected from the transmission line once the ROW

8082has been selected and the line constructed, and the desire to

8093have TECO seek another route. Although these concerns are

8102genuine, impacts on property values is not a subject for

8112consideration at this hearing. As discussed above in greater

8121detail, the evidence demonstrates that adverse impacts from the

8130low levels of electric and magnetic fields projected from the

8140Project are not expected. No alternate corridors have been

8149proposed for consideration by any party to this proceeding.

8158Finally, some members of the public complained that they were

8168unaware that a new transmission line corridor was being proposed

8178until just before the hearing. However, the evidence shows that

8188long before the certification hearing, information concerning

8195this process was widely disseminated through advertisements,

8202open houses, mass mailings, surveys, and meeting with regulatory

8211agencies and local elected officials.

8216c. Impact Upon the Environment

822175. The Project as proposed will have minimal

8229environmental impact.

823176. Construction of the line within the proposed corridor

8240will not adversely affect the conservation of fish and wildlife,

8250including endangered or threatened species, or their habitats.

8258The proposed corridor avoids or minimizes intrusion into the

8267undisturbed wildlife habitats due to its collocation with

8275existing linear facilities for almost its entire length. The

8284current condition and relative value of function of the habitat

8294in the proposed corridor is generally minimal from a wildlife

8304ecology and protected species perspective. There are some areas

8313with higher quality habitat. One is in the area south of Lake

8325Thonotosassa. In that location, there is a natural gas pipeline

8335corridor that already disturbs the area in the proposed

8344corridor. In the area of the bald eagle's nest, clearing in the

8356ROW would be limited to 25 to 100 feet in width. Also, the

8369Conditions of Certification require extensive surveys and plans

8377for wildlife protection. The area has experienced clearing and

8386tree removal to accommodate development. Care was taken in

8395routing the proposed corridor to avoid or minimize proximity of

8405the corridor to known listed species locations, including

8413routing inputs from wildlife agencies such as the FFWCC and the

8424U.S. Fish and Wildlife Service (USFWS). Clearing of additional

8433natural habitats and potential wetland impacts will be

8441minimized.

844277. During the regional screening route selection process

8450the known locations of bald eagle nests were identified and

8460mapped. Members of the public pointed out at the open houses

8471that there existed a previously unreported bald eagle nest in

8481the area north of Jess Baldwin Road. This was subsequently

8491verified and identified as a correct location of an eagle nest

8502that had been previously unknown to the FFWCC and USFWS. When

8513the nest was identified and located, the corridor was expanded

8523up to 5,100 feet in this area to give TECO maximum flexibility

8536in avoiding potential impacts to the nest as well as to existing

8548homes in the area. TECO has begun a long-term monitoring

8558program for this particular nest and this will be continued

8568until such time as the applicant and the agencies deem it

8579sufficient. The program is designed to monitor the activity of

8589the eagles in the area with respect to successful breeding,

8599successful rearing of the young, and the habitat usage and

8609flight patterns from that nest. This information will be

8618utilized in the selection of the ultimate ROW in this area to

8630avoid any impacts to the nesting area.

863778. The USFWS and FFWCC establish buffers for limiting

8646activity in proximity to an eagle's nest. The buffers are

8656either 330 feet or 660 feet in diameter, depending on the level

8668of construction activity that is to be carried out. In cases in

8680which a more minimal level of construction is to be performed, a

8692660-foot buffer must be maintained if there is not visual buffer

8703between the nest and the construction activity. A 330-foot

8712buffer must be maintained at all times. If a visual buffer can

8724be maintained in the area of this eagle's nest, the buffer size

8736could be reduced below 660 feet, providing additional

8744flexibility for the location of the ROW. This determination

8753will be made by the USFWS and FFWCC.

876179. Construction of the line within the proposed corridor

8770will not cause a significant adverse impact to the current

8780condition and relative value of functions of the vegetative

8789communities within the corridor. Much of the length of the

8799corridor allows placement of the transmission line within or

8808adjacent to existing linear features to take advantage of

8817previous disturbances to vegetation. TECO will also minimize

8825impacts to forested wetland vegetation through the use of

8834restrictive clearing practices during both construction and

8841maintenance. In the forested wetland portions of the ROW, trees

8851and shrubs that have an expected mature height greater than

8861fourteen feet and "danger trees," which are trees that could

8871fall into the conductors and cause an outage, will be removed.

8882Other vegetation will generally not be disturbed. In these

8891areas, vegetation will be removed by hand, usually with chain

8901saws or with low-ground-pressure equipment to reduce soil

8909compaction and damage to ground cover. The removal of

8918vegetation in forested wetlands will not significantly affect

8926the vegetative root mat or soil surface conditions. The non-

8936forested wetlands should not require any clearing.

894380. There will be some filling in wetlands associated with

8953the placement of pole pads and access roads. However, TECO will

8964minimize these impacts through a careful alignment of the ROW

8974and the varying of span distances between poles. TECO will also

8985install an appropriate number and size of culverts to properly

8995maintain existing wetland hydroperiods along areas of fill in

9004wetlands. Also, any unavoidable wetland impacts associated with

9012the project will be mitigated in accordance with the Conditions

9022of Certification.

902481. TECO has utilized information from the Hillsborough

9032and Polk County Comprehensive Plans and the Department of State,

9042Division of Historical Resources (DHR), to identify potential

9050archeological and historical resources within the proposed

9057corridor. A number of locations were identified as a result of

9068the information and the Conditions of Certification require that

9077a survey be performed when the actual ROW is located. If any

9089artifacts are found the information will be submitted to the DHR

9100for analysis and decisions will be made as to how to proceed.

9112The proposed corridor contains the least potential impacts to

9121known sites and the corridor allows ample opportunity for siting

9131the ROW to avoid potential historic and archeological sites.

914082. In addition to comments from the public described in

9150Finding of Fact 74, a number of members of the public expressed

9162concern over the environmental impacts from the construction and

9171maintenance of the transmission line. Some of those expressing

9180concerns have residences or property in the area of the expanded

9191corridor surrounding the eagle's nest. Although some of these

9200individuals are within the corridor, it is not clear at this

9211point that they will be near or adjacent to the ROW which is

9224ultimately selected. The ROW is proposed to be within the

9234expanded corridor in this area. The eagle's nest presents a

9244constraint with a 330 or 660-foot buffer. Evaluations will be

9254performed considering impacts to the community and homes,

9262impacts to the environment, and costs. If the buffer is reduced

9273to 330 feet this will assist in the routing of the ROW. As

9286detailed above, TECO engaged in extensive public outreach, made

9295efforts to avoid populated areas with the corridor location, and

9305the Conditions of Certification require extensive measures to

9313eliminate or minimize the potential impacts on wildlife and

9322habitat. TECO will minimize any necessary cutting of trees in

9332areas that do not already have an established ROW. The area of

9344clearing will be limited to from 25 to 100 feet in width.

935683. The Project will comply with all applicable state,

9365regional, and local nonprocedural regulations, including the

9372wetland regulatory standards applicable to such projects.

9379d. Balance of Need versus Impacts

938584. The Project effects a reasonable balance between the

9394need for a transmission line as a means for providing abundant

9405low cost energy and the impact upon the public and the

9416environment resulting from the location of the transmission line

9425corridor and the construction and maintenance of the

9433transmission line.

9435V. Conditions of Certification

943985. The design, construction, and operation of the line in

9449the proposed corridor will comply with the Conditions of

9458Certification set forth in Department Exhibit 4.

946586. The Conditions of Certification establish a post-

9473certification review process through which the final ROW, access

9482road, and structure locations will be reviewed by agencies with

9492regulatory authority over the project for the purpose of

9501monitoring for compliance with the Conditions of Certification.

950987. While the proposed corridor has few homes in close

9519proximity to it and very limited wetland crossings, TECO has

9529agreed to conditions of certification that further minimize land

9538use and environmental impacts. For example, TECO has agreed

9547that to the extent practicable it will locate its ROW to avoid

9559the taking of homes, to collocate the ROW within or adjacent to

9571existing ROWs, and to vary the length of the span between poles

9583as appropriate to eliminate or reduce wetland impacts.

9591CONCLUSIONS OF LAW

959488. The Division of Administrative Hearings has

9601jurisdiction over the parties and the subject matter of this

9611proceeding. §§ 120.569 and 403.527(1), Fla. Stat.

961889. This certification proceeding was held pursuant to the

9627Transmission Line Siting Act, Sections 403.52 through 403.5365,

9635Florida Statutes, and Florida Administrative Code Rule Chapter

964362-17, Part II. The intent of this certification process is:

9653to fully balance the need for the

9660transmission lines with the broad interests

9666of the public in order to effect a

9674reasonable balance between the need for the

9681facility as a means of providing abundant

9688low-cost electrical energy and the impact on

9695the public and the environment resulting

9701from the location of the transmission line

9708corridor and the construction and

9713maintenance of the transmission lines.

9718§ 403.521, Fla. Stat. To implement this intent, the Legislature

9728has set forth specific requirements for the PSC to determine the

9739need for the proposed transmission line and address other

9748matters within its jurisdiction, for other various agencies to

9757prepare reports and studies regarding matters within their

9765jurisdiction, for publication of notice of the application and

9774certification proceeding, for third parties to have an

9782opportunity to offer alternate corridor routes for

9789consideration, and for criteria to be considered in determining

9798whether an application should be approved in whole, approved

9807with modification or conditions, or denied. See §§ 403.526,

9816403.527, 403.5271, 403.529, and 403.537, Fla. Stat.

982390. All parties identified in Finding of Fact No. 1 have

9834standing in this proceeding.

983891. TECO has the burden of proving that, under the

9848criteria of Section 403.529(4)(a)-(e), Florida Statutes, the

9855proposed corridor for the Willow Oak-Wheeler-Davis transmission

9862line should be certified as proposed based upon a preponderance

9872of the evidence presented at the certification hearing. See,

9881e.g. , Fla. Dept. of Transp. v. J.W.C Co., Inc. , 396 So. 2d 778,

9894788 (Fla. 1st DCA 1981).

989992. The evidence in the record of this proceeding

9908demonstrates compliance with the procedural requirements of the

9916TLSA, including the notice requirements for the certification

9924and public hearings. It is noted that TECO voluntarily engaged

9934in an extensive public outreach program that included additional

9943newspaper notices and extensive mailings.

994893. In deciding whether TECO's Application should be

9956approved, approved with conditions, or denied, the Siting Board

9965must determine whether, and the extent to which, the location of

9976the corridor and the construction and maintenance of the

9985transmission line in the corridor will:

9991(a) Ensure electric power system

9996reliability and integrity;

9999(b) Meet the electrical energy needs of the

10007state in an orderly and timely fashion;

10014(c) Comply with nonprocedural requirements

10019of agencies;

10021(d) Be consistent with applicable local

10027government comprehensive plans; and

10031(e) Effect a reasonable balance between the

10038need for the transmission line as a means of

10047providing abundant low-cost electrical

10051energy and the impact upon the public and

10059the environment resulting from the location

10065of the transmission line corridor and the

10072maintenance of the transmission lines.

10077§ 403.529(4), Fla. Stat.

1008194. Compliance with Section 403.529(4)(a), Florida

10087Statutes . The PSC determined the need for a new 230 kV

10099transmission line between the planned Willow Oak and Wheeler

10108substations with an intermediate connection to the existing

10116Wheeler substation in Order No. PSC-07-0522-FOF-EI issued on

10124June 21, 2007. Among other things, the PSC found that the

10135existing 230 kV transmission network will not have sufficient

10144capability to provide reliable service to the existing and

10153proposed substations by the year 2012. The PSC also found that

10164some of the projected load to be served by the proposed

10175distribution substations will be located further east and north

10184of the existing 230 kV transmission network. It further found

10194that the proposed transmission line is needed by March 2012 to

10205(a) provide additional transmission reinforcement to the

10212existing 230 kV transmission network north of State Road 60,

10222west of Willow Oak substation and to the east of the existing

10234River substation in a reliable manner consistent with other

10243applicable standards; (b) serve the increasing load and customer

10252base in the projected service area; and (c) provide for another

10263electrical feed via a separate ROW path, thereby reducing the

10273impact of the loss of the existing transmission facilities on a

10284common ROW. The PSC's determination of need for the project is

10295binding on all parties to the certification proceeding. See

10304§ 403.537(1)(d), Fla. Stat. Based upon the PSC Order

10313determining need, a prima facie showing that the proposed

10322transmission line would enhance electric system reliability,

10329integrity, and restoration of service has been made. Finally,

10338the PSC found that the corridor meets the criteria of

10348Section 403.529(4)(a), Florida Statutes.

1035295. Compliance with Section 403.529(4)(b), Florida

10358Statutes . The PSC acknowledged in its Order Determining Need

10368for the proposed line that TECO demonstrated the need for the

10379line by March 2012. Evidence regarding the design of the

10389transmission line, the construction phases for the transmission

10397line, including the projected 12 to 18-month construction

10405schedule, and the proposed location of the line, demonstrates

10414that the Project will meet the electrical needs of the State in

10426an orderly and timely fashion within the timeframes established

10435by the PSC.

1043896. Compliance with Section 403.529(4)(c), Florida

10444Statutes . The evidence supports a conclusion that the location

10454of the transmission line in the proposed corridor and the

10464construction and maintenance of that line in conformance with

10473the recommended Conditions of Certification contained in

10480Department Exhibit 4 will comply with the non-procedural

10488requirements of all agencies.

1049297. Compliance with Section 403.529(4)(d), Florida

10498Statutes . The evidence supports a conclusion that there are no

10509inconsistencies between the proposed transmission line and the

10517comprehensive plans adopted by local governments whose

10524jurisdictions are crossed by the proposed line.

1053198. Compliance with Section 403.529(4)(e), Florida

10537Statutes . The location of the proposed corridor and the

10547construction, operation, and maintenance of the transmission

10554line in that corridor provide a reasonable balance between the

10564need for the transmission line and the impact of the

10574transmission line upon the public and the environment. The

10583impact upon the public and the environment will be minimized by

10594the collocation with existing linear facilities where feasible,

10602the practices that TECO will utilize concerning clearing

10610activities and construction and operation activities to minimize

10618unnecessary clearing, the avoidance of wetland areas where

10626feasible, the avoidance of taking homes where feasible, and

10635compliance with the extensive Conditions of Certification that

10643have been imposed by the Department and other agencies.

10652Measures have been and will be taken to minimize the impact to

10664the previously undocumented bald eagle's next and a buffer of at

10675least 330 feet will be established in accordance with applicable

10685guidelines to protect the nest. The corridor has been widened

10695in appropriate locations to provide TECO with flexibility in

10704locating the ROW, and the Conditions of Certification have

10713requirements to which TECO has agreed concerning the

10721establishment of the ROW and impacts to the environment and

10731residents. The electric and magnetic field levels expected from

10740the transmission line have been shown to be significantly below

10750the maximum limits in effect in Florida and a small fraction of

10762the lowest levels that have ever been even proposed based upon

10773potential effects to human health. The evidence does not

10782demonstrate that the location of the ROW in reasonable proximity

10792to Intervenors' residence will increase the potential exposure

10800to electric and magnetic fields of the residents beyond that

10810which is already occurring as a result of everyday living.

10820Research has not demonstrated that levels in the range expected

10830from the Project produce any adverse health effects. The

10839overall impacts of the Project have been shown to be minimal,

10850particularly when balanced with the significant electrical

10857energy requirements that will be satisfied by construction and

10866operation of the transmission line within the proposed corridor.

1087599. While the concerns of Intervenors and the members of

10885the public who offered comments on the proposal are genuine and

10896well-intended, they do not constitute a basis under the TLSA or

10907applicable Department rules for modifying, or providing further

10915conditions to, the corridor, or denying the Application. 3

10924100. Based upon a preponderance of the evidence presented

10933at the certification hearing, TECO has met its burden of proving

10944that the transmission line and related facilities should be

10953certified as proposed, subject to the Conditions of

10961Certification included in Department Exhibit 4.

10967RECOMMENDATION

10968Based upon the foregoing Findings of Fact and Conclusions

10977of Law, it is

10981RECOMMENDED that the Siting Board enter a Final Order

10990approving Tampa Electric Company's Willow Oak-Wheeler-Davis 230

10997kV Transmission Line Application for Certification subject to

11005the Conditions of Certification set forth in Department Exhibit

110144.

11015DONE AND ENTERED this 13th day of May, 2008, in

11025Tallahassee, Leon County, Florida.

11029S

11030DONALD R. ALEXANDER

11033Administrative Law Judge

11036Division of Administrative Hearings

11040The DeSoto Building

110431230 Apalachee Parkway

11046Tallahassee, Florida 32399-3060

11049(850) 488-9675 SUNCOM 278-9675

11053Fax Filing (850) 921-6847

11057www.doah.state.fl.us

11058Filed with the Clerk of the

11064Division of Administrative Hearings

11068this 13th day of May, 2008.

11074ENDNOTES

110751/ All subsequent references are to the 2007 version of the

11086Florida Statutes.

110882/ The estimated capital cost of the transmission line is $72.2

11099million, excluding right-of-way costs. See TECO Exhibit 1,

11107Appendix A.

111093/ For obvious reasons, it can be said with almost certainty

11120that no owner, tenant, or lessee desires to have a transmission

11131line, with large concrete poles, related equipment, and wires,

11140placed near or adjacent to his or her property.

11149COPIES FURNISHED:

11151Lea Crandall, Agency Clerk

11155Department of Environmental Protection

111593900 Commonwealth Boulevard

11162Mail Station 35

11165Tallahassee, Florida 32399-3000

11168Gregory M. Munson, General Counsel

11173Department of Environmental Protection

111773900 Commonwealth Boulevard

11180Mail Station 35

11183Tallahassee, Florida 32399-3000

11186Lawrence N. Curtin, Esquire

11190Holland & Knight LLP

11194Post Office Box 810

11198Tallahassee, Florida 32302-0810

11201Toni L. Sturtevant, Esquire

11205Department of Environmental Protection

112093900 Commonwealth Boulevard

11212Mail Station 35

11215Tallahassee, Florida 32399-3000

11218Kelly A. Martinson, Esquire

11222Department of Community Affairs

112262555 Shumard Oak Boulevard

11230Tallahassee, Florida 32399-2100

11233Marva M. Taylor, Esquire

11237Assistant County Attorney

11240601 East Kennedy Boulevard

11244County Center, 27th Floor

11248Tampa, Florida 33602-4156

11251Michael E. Duclos, Esquire

11255Assistant County Attorney

11258Post Office Box 9005

11262Bartow, Florida 33831-9005

11265Martha A. Moore, Esquire

11269Southwest Florida Water Management District

112742379 Broad Street

11277Brooksville, Florida 34604-6899

11280Susan Watson

112823624 Windchime Lane

11285Dover, Florida 33527-4930

11288Seauching Yu, Esquire

11291Department of Transportation

11294605 Suwannee Street

11297Mail Station 58

11300Tallahassee, Florida 32399-0458

11303James V. Antista, General Counsel

11308Florida Fish and Wildlife

11312Conservation Commission

11314620 South Meridian Street

11318Tallahassee, Florida 32399-1600

11321Manny L. Pumariega, Executive Director

11326Tampa Bay Regional Planning Council

113314000 Gateway Centre Boulevard, Suite 100

11337Pinellas Park, Florida 33782-6138

11341Patricia M. Steed, Executive Director

11346Central Florida Regional

11349Planning Council

11351555 East Church Street

11355Bartow, Florida 33830-3931

11358Samantha M. Cibula, Esquire

11362Florida Public Service Commission

113662540 Shumard Oak Boulevard

11370Tallahassee, Florida 32399-0850

11373Shaw P. Stiller, General Counsel

11378Department of Community Affairs

113822470 Centerview Drive

11385Tallahassee, Florida 32399-2100

11388NOTICE OF RIGHT TO FILE EXCEPTIONS

11394All parties have the right to submit written exceptions within

1140415 days of the date of this Recommended Order. Any exceptions

11415to this Recommended Order should be filed with the agency that

11426will render a final order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 08/12/2008
Proceedings: Final Order filed.
PDF:
Date: 08/07/2008
Proceedings: Agency Final Order
PDF:
Date: 06/05/2008
Proceedings: Department of Transportation`s Notice of Substitution of Counsel filed.
PDF:
Date: 05/14/2008
Proceedings: Letter to Lea Crandall from Judge Alexander regarding corrected page 1 to the Recommended Order filed.
PDF:
Date: 05/13/2008
Proceedings: Recommended Order
PDF:
Date: 05/13/2008
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 05/13/2008
Proceedings: Recommended Order (hearing held March 4 and 5, 2008). CASE CLOSED.
PDF:
Date: 04/16/2008
Proceedings: Proposed Recommended Order filed.
PDF:
Date: 04/16/2008
Proceedings: Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 04/16/2008
Proceedings: Stipulation between Tampa Electric Company and the City of Temple Terrace filed.
PDF:
Date: 04/16/2008
Proceedings: Notice of Filing of Stipulation filed.
PDF:
Date: 04/15/2008
Proceedings: Petitioner Susan Watson`s Proposed Recommended Order (completed) filed.
PDF:
Date: 04/11/2008
Proceedings: Petitioner Susan Watson`s Proposed Recommended Order (incomplete) filed.
PDF:
Date: 04/03/2008
Proceedings: Reply to Intervenor Watson`s Response to Applicant`s Opposition to Motion to Strike filed.
Date: 04/02/2008
Proceedings: Transcript (Volumes 1-3) filed.
PDF:
Date: 03/27/2008
Proceedings: Intervenor Susan Watson`s Response to Applicant`s Opposition to her Motion to Strike Late Filed Exhibit filed.
PDF:
Date: 03/24/2008
Proceedings: Applicant`s Response in Opposition to Intervenor`s Motion to Strike Late Filed Exhibit and Notice of Filing Late Filed Exhibit filed.
PDF:
Date: 03/17/2008
Proceedings: Intervenor Susan Watson`s Motion to Strike Tampa Electric Company`s Late File Exhibit and Notice of Filing Late Filed Exhibit filed.
PDF:
Date: 03/12/2008
Proceedings: Notice of Filing Late filed Exhibits (exhibits not available for viewing) filed.
Date: 03/04/2008
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 03/03/2008
Proceedings: Letter to (Whom it may concern) from H. Talmor enclosing written testimony regarding T. Watson filed.
PDF:
Date: 02/29/2008
Proceedings: Response to Motion for Leave to Allow Expert Witness to Appear by Telephone filed.
PDF:
Date: 02/28/2008
Proceedings: Motion for Leave to Allow Expert Witness to Appeal by Phone filed.
PDF:
Date: 02/28/2008
Proceedings: Witness List filed.
PDF:
Date: 02/27/2008
Proceedings: Response to Petition to Intervene filed.
PDF:
Date: 02/26/2008
Proceedings: Order Granting Leave to Intervene (Tom and Susan Watson).
PDF:
Date: 02/26/2008
Proceedings: Prehearing Stipulation filed.
PDF:
Date: 02/26/2008
Proceedings: Tampa Electric Company`s Notice of Filing Prehearing Stipulation filed.
PDF:
Date: 02/25/2008
Proceedings: Petition to Intervene (Tom and Susan Watson) filed.
PDF:
Date: 02/21/2008
Proceedings: Order Granting Leave to Participate.
PDF:
Date: 02/14/2008
Proceedings: Tampa Electric Company`s Response to City of Temple Terrace`s Unopposed Motion to Participate in Certification Proceedings filed.
PDF:
Date: 02/13/2008
Proceedings: City of Temple Terrace`s Unopposed Motion to Participate in the Certification Proceedings filed.
PDF:
Date: 02/13/2008
Proceedings: City of Temple Terrace`s Tardy Notice of Intent to Become a Party to the Certification Proceedings filed.
PDF:
Date: 02/08/2008
Proceedings: Notice and Order on Possible Ex-Parte Communication.
PDF:
Date: 02/05/2008
Proceedings: Letter to Judge Johnston from S. Watson regarding interested party in certification hearing filed.
PDF:
Date: 02/04/2008
Proceedings: Transmission Line Site Certification Staff Analysis Report filed.
PDF:
Date: 02/04/2008
Proceedings: Notice of Filing Project Analysis filed.
PDF:
Date: 02/04/2008
Proceedings: Hillsborough County`s Notice of Intent to Become a Party to the Certification Proceedings filed.
PDF:
Date: 01/31/2008
Proceedings: City of Temple Terrace`s Proposed Revisions to the Department of Environmental Protection`s Draft Conditions of Certification filed.
PDF:
Date: 01/18/2008
Proceedings: Notice of Public Hearing (hearing will be held March 5, 2008; 7:00 p.m.; Brandon, FL)
PDF:
Date: 01/16/2008
Proceedings: Hillsborough County`s Request for Public Hearing Supplementing the Certification Hearing filed.
PDF:
Date: 01/10/2008
Proceedings: City of Temple Terrace`s Transmission Line Impact Report filed.
PDF:
Date: 01/07/2008
Proceedings: Amended Notice of Hearing (hearing set for March 4 through 7 and 10 through 14, 2008; 9:00 a.m.; Brandon, FL; amended as to location).
PDF:
Date: 12/26/2007
Proceedings: Department of Environmental Protection`s Determination of Completeness filed.
PDF:
Date: 12/21/2007
Proceedings: City of Temple Terrace`s Notice of Consent to Findings of Completeness filed.
PDF:
Date: 12/20/2007
Proceedings: Notice of Filing City of Temple Terrace`s Second Set of Completeness Questions filed.
PDF:
Date: 12/20/2007
Proceedings: City of Temple Terrace`s Second Set of Completeness Questions filed.
PDF:
Date: 12/19/2007
Proceedings: Notice of Filing City of Temple Terrace`s Second Set of Completeness Questions filed.
PDF:
Date: 12/19/2007
Proceedings: City of Temple Terrace`s Second Set of Completeness Questions filed.
PDF:
Date: 12/03/2007
Proceedings: Tampa Electric Company`s Notice of Filing Completeness Response filed.
PDF:
Date: 11/20/2007
Proceedings: Notice of Incompleteness filed.
PDF:
Date: 11/14/2007
Proceedings: Southwest Florida Water Management District`s Notice of Filing filed.
PDF:
Date: 11/14/2007
Proceedings: Southwest Florida Water Management District`s Notice of Intent to be a Party filed.
PDF:
Date: 11/14/2007
Proceedings: City of Temple Terrace`s Recommendations and First Set of Completeness Questions filed.
PDF:
Date: 11/13/2007
Proceedings: Department of Community Affairs` Notice of Intent to be a Party filed.
PDF:
Date: 11/09/2007
Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
PDF:
Date: 10/26/2007
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 10/26/2007
Proceedings: Notice of Hearing (hearing set for March 4 through 7 and 10 through 14, 2008; 9:00 a.m.; Tampa, FL).
PDF:
Date: 10/25/2007
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
PDF:
Date: 10/25/2007
Proceedings: Department of Environmental Pretection`s Notice of Filing of Transmission Line Siting Application (exhibits not available for viewing) filed.
PDF:
Date: 10/19/2007
Proceedings: Department of Environmental Protection`s Notice of Filing of Transmission Line Siting Application filed.
PDF:
Date: 10/19/2007
Proceedings: Tampa Electric Company`s Notice of Distribution of Additional Copies of Corridor Certification Application filed.
PDF:
Date: 10/17/2007
Proceedings: Department of Environmental Protection`s Proposed Transmission Line Site Certification Schedule filed.
PDF:
Date: 10/17/2007
Proceedings: Statement of Agencies Entitled to Copies filed.
PDF:
Date: 10/17/2007
Proceedings: Amended Initial Order.
PDF:
Date: 10/16/2007
Proceedings: Initial Order.
PDF:
Date: 10/15/2007
Proceedings: Department of Environmental Protection`s Request for Assignment of Administrative Law Judge filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
10/15/2007
Date Assignment:
02/29/2008
Last Docket Entry:
08/12/2008
Location:
Brandon, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
TL
 

Counsels

Related DOAH Cases(s) (1):

Related Florida Statute(s) (10):

Related Florida Rule(s) (1):