07-004745TL
In Re: Tampa Electric Company Willow Oak-Wheeler-Davis Transmission Line Siting Application No. Ta07-15 vs.
*
Status: Closed
Recommended Order on Tuesday, May 13, 2008.
Recommended Order on Tuesday, May 13, 2008.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: TAMPA ELECTRIC )
13ST. JOHNS-PELLICER-PRINGLE, )
16COMPANY WILL0W-OAK-WHEELER- ) Case No. 07-4745TL
22DAVIS TRANSMISSION LINE SITING )
27APPLICATION NO. TA07-15 )
31_______________________________)
32RECOMMENDED ORDER
34Pursuant to notice, a formal hearing was held in this case
45on March 4 and 5, 2008, in Brandon, Florida, before the Division
57of Administrative Hearings, by its assigned Administrative Law
65Judge, Donald R. Alexander.
69APPEARANCES
70For Tampa Electric Lawrence N. Curtin, Esquire
77Company: Gigi Rollini, Esquire
81Holland & Knight, LLP
85Post Office Box 810
89Tallahassee, Florida 32302-0810
92For Department Toni L. Sturtevant, Esquire
98of Environmental Department of Environmental Protection
104Protection: Mail Station 35
1083000 Commonwealth Boulevard
111Tallahassee, Florida 32399-3000
114For Hillsborough Marva M. Taylor, Esquire
120County: Assistant County Attorney
124601 East Kennedy Boulevard
128County Center, 27th Floor
132Tampa, Florida 33602-4156
135For Polk County: Michael E. Duclos, Esquire
142Assistant County Attorney
145Post Office Box 9005
149Bartow, Florida 33831-9005
152For Intervenors: Susan Watson, pro se
1583624 Windchime Lane
161Dover, Florida 33527-4930
164STATEMENT OF THE ISSUE
168The issue for determination is whether and the extent to
178which the proposed corridor by Tampa Electric Company (TECO)
187contained in its Application for Corridor Certification
194(Application) should be approved in whole, with modifications or
203conditions, or denied.
206PRELIMINARY STATEMENT
208Pursuant to Section 403.537, Florida Statutes (2007), 1 on
217March 28, 2007, TECO submitted a petition for determination of
227need for the proposed Willow Oak-Wheeler-Davis 230 kV
235transmission line project with the Florida Public Service
243Commission (PSC). The PSC issued Order No. PSC-07-0522-FOF-EI,
251dated June 21, 2007, determining the need for the transmission
261line.
262On October 12, 2007, TECO filed its Application with the
272Department of Environmental Protection (Department) and paid
279the appropriate application fee. The Application was filed
287under the Transmission Line Siting Act (TLSA), codified in
296Sections 403.52 through 403.5365, Florida Statutes, for a new
305230 kV overhead transmission line and related facilities
313connecting the planned Willow Oak substation west of Mulberry in
323Polk County to the planned Davis substation located in Temple
333Terrace, Hillsborough County, Florida, with an intermediate
340connection to the existing Wheeler substation located along
348Wheeler Road northeast of Brandon in Hillsborough County (the
357Project).
358The various reviewing agencies have submitted reports on
366the Project and have proposed Conditions of Certification. On
375February 4, 2008, the Department issued its Transmission Line
384Site Certification Staff Analysis Report, incorporating the
391reports of the reviewing agencies and proposing a complied set
401of Conditions of Certification. During the certification
408hearing, a revised and updated version of the proposed
417Conditions of Certification was admitted into the record as
426Department Exhibit 4.
429By Notice of Hearing dated October 26, 2007, a
438certification hearing was scheduled on March 4-7 and 10-14,
4472008, in Brandon, Florida. On February 29, 2008, the case was
458transferred from Administrative Law Judge J. Lawrence Johnston
466to the undersigned.
469On February 25, 2008, Tom and Susan Watson, who own
479property in Dover, Florida, immediately adjacent to the proposed
488corridor, filed their Petition to Intervene. Intervention was
496authorized by Order dated February 26, 2008.
503On February 28, 2008, Intervenors filed a Motion for Leave
513to Allow Expert Witness to Appeal (sic) by Phone. This request
524was granted at the certification hearing and Dr. Hanoch Talmor,
534a Gainesville physician, was permitted to testify by telephone
543on behalf of Intervenors.
547The certification hearing was held on March 4 and 5, 2008,
558in Brandon, Florida. (Only two of the days reserved for hearing
569were required to complete the matter.) All notices required by
579law were timely published in accordance with Section 403.527,
588Florida Statutes. The final hearing was conducted for the
597purpose of receiving oral, written, and documentary evidence
605concerning whether the Project should be approved in whole, or
615with such modifications and conditions as the Siting Board deems
625appropriate, or denied under the TLSA.
631At the certification hearing, TECO presented the testimony
639of David M. Lukcic, Manager of Capital Projects and
648Environmental Health and Safety; Chip S. Whitworth, Manager of
657the Transmission Engineering Department and accepted as an
665expert; Philip W. Simpson, a scientist with Environmental
673Consulting & Technology, Inc. (ECT) and accepted as an expert;
683Anthony N. Arcuri, a scientist with ECT and accepted as an
694expert; Darren Stowe, a scientist with ECT and accepted as an
705expert; Jim Brooks, a professional engineer with Black & Veatch
715and accepted as an expert; and Dr. Linda S. Erdreich, a senior
727managing scientist and epidemiologist for Exponent, Inc. and
735accepted as an expert. Also, it offered TECO Exhibits 1-26,
745which were received in evidence. Although Intervenors filed a
754post-hearing written objection to Exhibit 26, that objection is
763overruled and the exhibit has been received in evidence. The
773Department presented the testimony of Ann S. Seiler, an
782Environmental Specialist III and accepted as an expert, and
791Michael P. Halpin, Administrator of its Siting Office and
800accepted as an expert. Also, it offered Department Exhibits 1
810through 4, which were received in evidence. Hillsborough and
819Polk Counties participated in the hearing but did not submit any
830evidence. Intervenors were represented by Susan Watson, a non-
839attorney, who testified on her own behalf. She presented the
849testimony of Quilla Paul Daniels, who now resides in Plant City
860but formerly owned property near the proposed corridor, and
869Dr. Hanoch Talmor, a medical doctor in Gainesville, Florida.
878Intervenors also offered Intervenors Exhibits 1 and 2, which
887were received in evidence.
891A public hearing was held at 7:00 p.m. on March 5, 2008,
903for the purpose of allowing members of the public an opportunity
914to present evidence and testimony. Thirty-five members of the
923public testified, one with a power point presentation. Public
932Exhibits 1-8 were also received in evidence.
939The Transcript (three volumes) of the final hearing was
948filed on April 2, 2008. Intervenors and TECO filed Proposed
958Recommended Orders on April 15 and 16, 2008, respectively, which
968have been considered in the preparation of this Recommended
977Order. The Department has joined in TECO's filing.
985FINDINGS OF FACT
988Based upon all of the evidence the following findings of
998fact are determined:
1001I. Parties
10031. The TLSA establishes TECO and the Department as parties
1013to this proceeding, and the following became parties upon their
1023timely filing of a notice of intent to be a party, which each
1036has done: Florida Department of Transportation (DOT),
1043Department of Community Affairs (DCA), Southwest Florida Water
1051Management District (SWRWMD), and Hillsborough County. See
1058§ 403.527(2), Fla. Stat. Although the Florida Fish and Wildlife
1068Conservation Commission (FFWCC) did not become a party, the
1077Department accepted its comments and recommended conditions in
1085the agency report. On February 21, 2008, the City of Temple
1096Terrace was accepted as a party without objection after the
1106Stat. On February 25, 2008, Tom and Susan Watson filed a
1117Petition to Intervene. Although this was after the deadline
1126established in the prehearing schedule for becoming a party,
1135TECO did not object based upon an agreement to conditions
1145relating to the presentation of witnesses by the Watsons.
1154Intervenors agreed to those conditions. Finally, Polk County
1162did not file a notice of intent to be a party, but appeared
1175without objection at the certification hearing.
1181II. The Application
1184A. Project Description
11872. Generally, an electrical transmission line's purpose is
1195to transport large amounts of electricity from a generating
1204facility to one or more substations. At the substation, the
1214electricity can be either increased or reduced in voltage
1223through transformers and other electrical equipment for further
1231safe and practical transportation, or distribution directly to
1239customers.
12403. TECO is seeking certification of a corridor between the
1250planned Willow Oak substation located at the intersection of
1259State Road 60 and Turner Road just northwest of Mulberry in Polk
1271County, the existing Wheeler substation in Valrico, and the
1280planned Davis substation in Temple Terrace, a span of
1289approximately thirty miles, within which it will ultimately
1297construct the line on a narrow right-of-way (ROW). 2 Once all
1308property interests in the ROW are acquired, the boundaries of
1318the corridor will shrink to the typical width of the 25 to 100-
1331foot ROW. In some cases, the ROW will be 300 feet wide.
13434. The objectives of the Project are to address: (a) the
1354need, as confirmed by the PSC, to provide additional
1363transmission reinforcement to the existing 230 kV transmission
1371network north of State Road 60, west of the planned Willow Oak
1383substation, and east of the existing River substation in a
1393reliable manner consistent with the North America Electric
1401Reliability Council (NAERC) and the Florida Reliability
1408Coordinating Council (FRCC) and other applicable standards; (b)
1416the need to serve the increasing load and customer base in the
1428Project service area; and (c) the need to provide for another
1439electrical feed via a separate ROW path, thereby reducing the
1449impact of a loss of existing transmission facilities on a common
1460ROW.
1461B. Need for the Line
14665. In earlier proceedings before the PSC, it determined a
1476new 230 kV transmission line between the planned Willow Oak, the
1487existing Wheeler, and the planned Davis substations is needed,
1496taking into account the need for electric system reliability and
1506integrity and the need to provide abundant, low cost electrical
1516energy to assure the economic well-being of the citizens of the
1527State. The PSC found that the planned Willow Oak substation and
1538the planned Davis substation constitute the appropriate starting
1546and ending points for the proposed line. The PSC noted that the
1558additional transmission capacity will be needed by 2012 and
1567recognized that the Siting Board will make the final
1576determination concerning the route selection upon consideration
1583of the factors and criteria specified in Section 403.529,
1592Florida Statutes.
1594C. Transmission Line Design
15986. The typical design for the transmission line will be a
1609single-circuit unguyed concrete pole structure using concrete or
1617crushed stone back fill. The poles are proposed to range in
1628height from 80 feet above grade to 125 feet above grade, with
1640the conductors framed in a vertical configuration. Three
1648conductors will be used, and each of the three conductors is
1659anticipated to be a 1,590 aluminum conductor steel supported
1669wire, with 45 strands of annealed aluminum that lay over seven
1680steel strands. The conductor is 1.504 inches in diameter with a
1691weight of approximately 1.7 pounds per foot. There will also be
1702a smaller overhead ground wire to provide shielding and
1711lightening protection for the conductors. The maximum current
1719rating is 2,560 amperes. In some locations there could be a
173169 kV and a distribution underbuild. Additionally, the vertical
1740configuration will be adjusted to a horizontal configuration in
1749the vicinity of the South Lakeland Airport to enable the height
1760to be lowered to approximately 46 feet above grade to account
1771for the air traffic.
17757. The open span length between structures will typically
1784vary between 300 and 800 feet, depending on site-specific
1793conditions. Both pole height and span length may vary to
1803accommodate various conditions that may be encountered.
18108. Access roads and structure pads will be constructed
1819only where necessary to provide access for construction,
1827maintenance, and emergency restoration. Where constructed, the
1834typical road top width will be 14 feet, with a 2-to-1 side
1846slope, and a minimum elevation of between six inches and two
1857feet. Structure pads will have variable sizes but are typically
186775 feet by 75 feet. These are designed to support the equipment
1879needed to install and maintain the transmission line. Culverts
1888will be installed beneath access roads and structure pads with
1898the specific design reviewed by the appropriate regulatory
1906agencies. The design will be similar to previously approved
1915designs.
19169. The design of the transmission line complies with good
1926engineering practices. The transmission line will be designed
1934in compliance with all applicable design codes, including the
1943National Electrical Safety Code, the Department's regulations on
1951electric and magnetic fields, the DOT Utility Accommodation
1959Manual, the requirements of applicable regulatory agencies
1966including the Department, SWFWMD, and PSC, as well as TECO's own
1977design standards.
197910. The Project assures the citizens of Florida that
1988operation safeguards are technically sufficient for their
1995welfare and protection.
1998D. Transmission Line Construction
200211. The initial phase of construction is to clear the ROW.
2013Since much of the length of the corridor is collocated, that is,
2025grouped or placed side by side, with existing roads and utility
2036facilities, the need for clearing has been minimized. Clearing
2045will consist mainly of tree trimming and the selective removal
2055of trees. In areas owned by TECO clearing will range from a
2067width of 25 to 100 feet. In forested areas in which a new line
2081will be located, clearing will also be limited to 25 to 100 feet
2094in width. In wetlands, trees capable of exceeding 14 feet in
2105height that could come in conflict with the line will be removed
2117by hand clearing or use of very low ground pressure equipment.
2128Low growing herbaceous vegetation will not be cleared from
2137wetlands.
213812. After the ROW is cleared, any necessary access roads
2148and structure pads will be constructed. Typically, access roads
2157and pads are not required in all areas.
216513. The next phases of construction involve the physical
2174transmission line construction. Initially, the materials are
2181assembled on the jobsite. Next, holes are augered at each pole
2192location. The structures are framed with insulators and
2200hardware that may be installed prior to the setting of the
2211structure. After all appropriate operations relative to the
2219assembly and framing have been performed on the ground, the top
2230section of the structure is lifted with a crane and set on the
2243previously installed base section. The two sections are then
2252jacked together. Typically, the pole is embedded into the
2261ground approximately 25 to 35 feet deep.
226814. After the poles have been installed and the hardware
2278and equipment on the pole, including the insulators, have been
2288installed, a wire pulling operation is conducted. In this
2297phase, reels of wire, wire tensioning, and retarding equipment
2306all will be mobilized. The locations generally include the dead
2316end structures, but the length of the wire that can be placed on
2329a reel may dictate the location of some of the equipment. Each
2341structure must be equipped with hanging blocks or pulleys so the
2352conductors may be pulled through smoothly for the entire length
2362of the reel. Once the conductors are pulled in and secured at
2374the dead end structures, the wires are sagged and tensioned
2384appropriately to maintain vertical clearances. Finally, the
2391pulleys are removed from each structure and the conductor is
2401secured to the insulator attachment.
240615. The final stage of construction is the cleanup stage.
2416This involves inspection of the entire project to ensure that
2426all material has been cleaned up, removal of all silt fences,
2437hay bales, excess spoils, or dirt from the foundation
2446excavation, and ensuring that the gates and fences have been
2456properly restored or installed.
246016. Throughout construction, sedimentation management
2465techniques, such as the use of silt screens and hay bales, or
2477other best management practices, will be employed as necessary
2486to minimize potential impacts from erosion and sedimentation.
249417. While each phase of construction will typically take
2503up to two weeks in a particular location, the construction crew
2514will normally be active for two to four days at a typical
2526structure location after the necessary pads have been installed.
2535Construction for the entire project is expected to last from
2545twelve to eighteen months.
2549E. Methodology for Choosing TECO Corridor
255518. TECO established a multi-disciplinary team to identify
2563and evaluate routing alternatives within the Project Study Area.
2572This multi-disciplinary team was comprised of experts in land
2581use, engineering, and environmental disciplines. The team,
2588which included both TECO representatives and outside consultants
2596from ECT, engaged in a number of activities including data
2606collection, preparation of a regional screening map, the
2614identification of alternative route segments, the development of
2622criteria to evaluate the route segments, the actual evaluation
2631both quantitatively and qualitatively of these routes, and the
2640ultimate selection of the preferred route which was accepted by
2650TECO. Members of the public assisted in this effort throughout
2660the development of the proposed corridor.
266619. The objective of the corridor selection study was to
2676select a corridor that could be certified balancing land use,
2686socioeconomic, environmental, engineering, and cost
2691considerations. Corridor selection methodologies were designed
2697to be integrative of multidisciplinary siting criteria, regional
2705and objective in decision-making, sensitive to social and
2713environmental conditions, responsive to regulatory requirements,
2719reflective of community concerns and issues, and capable of
2728accurate documentation and verification.
273220. The selection process consisted of three tasks
2740including (a) project and study area definition; (b) resource
2749mapping and alternative route delineation; and (c) evaluation of
2758alternative routes and selection of the proposed corridor. Due
2767to the dense and urban nature of the TECO service area, it was
2780difficult to find areas with no population or development for a
2791corridor.
279221. The multidisciplinary team developed a regional
2799screening map, received in evidence as TECO Exhibit 14, which
2809was prepared by the team using generally publicly available
2818information including Geographic Information System (GIS)
2824mapping. The map data were collected from various state
2833agencies and local governments. Information was gathered from
2841the Florida Geographic Data Library (which distributes GIS
2849data), the Florida Natural Areas Inventory, and most of the
2859agencies involved in this proceeding. Various environmental and
2867land use data were mapped as were existing infrastructure, and
2877information gathered on roads, railroads, rivers, waterbodies,
2884and the like. These represented primarily siting constraints or
2893siting issues within a particular study area. The regional
2902screening map was then used to identify route segments.
291122. The licensing team used the regional screening map as
2921the first step in identifying the various route segments that
2931connected the three substation locations at Davis, Wheeler, and
2940Willow Oak.
294223. TECO's multi-disciplinary team gathered data on siting
2950opportunities and constraints within the study area and
2958identified forty-one line segments which could be assembled into
2967a total of four hundred twenty-three potential route
2975combinations. Using a predefined set of ten environmental, land
2984use, and engineering criteria, each route segment was measured
2993for those resources. Using a software program developed by ECT,
3003the data was entered and totaled for each route combination.
3013Using the weights developed by the licensing team for each
3023criterion, the weights were applied and tabulated for all
3032routes. The routes were then ranked in order from best to worst
3044based on the weighted scores.
304924. Once the rankings were performed, the top ranked
3058routes were subjected to further evaluation. These routes were
3067high in scoring but somewhat different in the path that they
3078took between the three substation locations. They were then
3087evaluated using predetermined qualitative criteria, which
3093included such things as homes in proximity to the route. The
3104analysis included an examination of where the homes were located
3114along the route, whether they are scattered and easily avoided
3124with the placement of a corridor, or whether they are clustered
3135together in a fashion making it difficult to avoid them in
3146placement of the corridor. Numerous driving surveys of the
3155various routes were performed during this phase where the routes
3165were publicly accessible, and a helicopter flyover was also
3174completed.
317525. At the completion of the evaluation, a recommendation
3184was made for a proposed route, which was accepted by TECO. Once
3196the proposed corridor location was selected, the team examined
3205various siting issues within and along the route and developed
3215corridor boundaries of varying widths. In some areas a much
3225wider width was needed to provide flexibility for siting, while
3235a more narrow width was needed in areas where siting issues were
3247less and where there was a reasonable certainty concerning where
3257the ROW could be located.
326226. TECO also engaged in an extensive public outreach
3271program. The public participation program included open houses,
3279mass mailings, surveys, a toll-free telephone number, newsprint
3287advertisements, a website, and meetings with regulatory agencies
3295and local elected officials.
329927. There were three direct mailings as a part of the
3310public outreach program. The first mailing was a notification
3319of four open houses that were to be held. One open house was
3332conducted in Polk County, while three (Seffner, Plant City, and
3342Temple Terrace) were conducted in Hillsborough County.
3349Following the completion of the open house process, a second
3359mailing was sent providing a summary of the survey results. The
3370third mailing notified recipients that the Application was filed
3379on October 12, 2007. Approximately 4,500 recipients were
3388identified for these mailings. The names of the recipients were
3398obtained by identifying the properties located within 500 feet
3407in both directions from the centerline of the routes. The
3417Hillsborough and Polk County Property Appraisers' offices were a
3426source for this information as well as the TECO customer
3436database. The Hillsborough County Office of Neighborhood
3443Relations was consulted for a list of registered homeowners'
3452associations. For the homeowners' associations, which numbered
3459around two hundred, those that were within one mile in both
3470directions from the centerline of the route were notified. The
3480recipients of the notifications included property owners and
3488tenants or lessees. The Hillsborough County Large Facilities
3496Ordinance was used as a guide to identify the area of the
3508notifications, although that Ordinance mandates a 250-foot
3515notification distance from the centerline of the routes, and
3524TECO actually used 500 feet on both sides of the centerline.
353528. The same distances were not used for recipients of
3545each of the mailings. The distances described in Finding of
3555Fact 27 were used for the first two mailings. For the third
3567mailing, the proposed corridor had been selected. As a result,
3577the distance was measured not from the centerline of the route,
3588but from the edge of the corridor. This was done because in
3600some areas the corridor was extended beyond the 500-foot limit
3610and potential recipients would have been missed had the area of
3621inclusion not been extended. Additional mailings are planned if
3630the corridor is certified. Additional informational open houses
3638will also be held, and the transmission structures and potential
3648locations will be identified at that time so the public can be
3660informed.
366129. As part of the public outreach, TECO also ran a series
3673of four advertisements in local newspapers. The first newspaper
3682advertisement was run on February 20, 2007, in The Tampa
3692Tribune , Lakeland Ledger , Mulberry Press , Temple Terrace News ,
3700and Brandon News . Two more advertisements were run on
3710February 28 and March 1, 2007, in The Tampa Tribune and Lakeland
3722Ledger . These advertisements were in addition to the required
3732public notices of the application being filed, the certification
3741hearing being scheduled, and the public hearing being scheduled
3750that were run on October 30 and December 27, 2007, and
3761February 18, 2008. The required advertisements were run in The
3771Tampa Tribune , Lakeland Ledger , and The Winter Haven News Chief .
3782The February 18 notice of public hearing was also run in The
3794Polk County Press .
379830. Copies of the Application were maintained for public
3807inspection during the certification process at the TECO offices
3816in Tampa and Winter Haven. In addition, a copy of the
3827Application was provided to the John Germany Public Library in
3837downtown Tampa, the Polk County Library in Bartow, and the
3847Temple Terrace Library in Temple Terrace. All of the
3856applications available for public inspection were updated as
3864additional information was submitted to the Department.
387131. The public participation program provided substantive
3878input to the route evaluation study in terms of study area
3889boundary, siting opportunities, and constraints in the area,
3897identification of route segments to be evaluated, and weights to
3907be assigned to the route evaluation criteria. The cumulative
3916responses of the public's ranking of the weights to apply to
3927TECO's siting criteria were very comparable to the team's
3936weighting indicating little significant difference in route
3943ranking.
394432. Once the proposed alignment was identified, the multi-
3953disciplinary team delineated the boundaries or width of the
3962corridor to provide flexibility for locating the eventual ROW
3971within that corridor.
397433. State, regional, and local agencies with regulatory
3982authority of the Project reviewed the Application and submitted
3991to the Department a report concerning the impact of the Project
4002on matters within their respective jurisdictions, as required by
4011Section 403.526(2), Florida Statutes. The Department compiled
4018the reports and made a recommendation that the Project be
4028granted approval subject to appropriate conditions. See
4035Department Exhibit 2.
403834. The Department, SWFWMD, and DOT stipulated as to the
4048certification of the Project subject to conditions of
4056certification proposed by the Department. On April 16, 2008,
4065the City of Temple Terrace and TECO entered into a separate
4076stipulation for certification. None of the agencies involved in
4085the review process recommended that the proposed corridor be
4094denied or modified. No alternate corridors were filed for
4103consideration by any of the parties. Further, no additional
4112conditions of certification were proposed by any party at the
4122certification hearing.
4124III. Detailed Description of the TECO Corridor
413135. The proposed corridor provides significant
4137opportunities for collocation with other linear facilities such
4145as roads and transmission lines which provide the opportunity to
4155reduce the amount of new access road construction, impacts to
4165wildlife habitat, and other impacts. The width of the proposed
4175corridor varies along the route to provide flexibility within
4184the corridor to avoid impacts to such areas as existing
4194developments, large wetland areas, and a bald eagle's nest.
4203A. From the Planned Davis Substation to the Existing
4212Wheeler Substation
421436. The western end of the corridor begins at the planned
4225Davis substation site in Temple Terrace which is a large parcel
4236owned by TECO. There is an existing substation there called the
4247River substation and the planned Davis substation will be
4256located in proximity to that existing substation. Land use is
4266generally open land. This portion of the corridor is bordered
4276on the west by the Hillsborough River and has a large area of
4289pasture land on the east side with mixed hardwood swamp and
4300cypress swamp on the western portion.
430637. Leaving the TECO substation property, the corridor
4314travels east across Interstate 75 (I-75) and the width of the
4325corridor in this area narrows to approximately 300 feet. This
4335is also TECO property. As the corridor passes I-75 it
4345approaches the Tampa Bypass Canal, which is owned by the SWFWMD.
4356The corridor is expanded in this area to minimize the impacts on
4368the SWFWMD operations along the Bypass Canal and on the
4378recreational facilities located in the southwestern portion of
4386the parcel used by Temple Terrace. Land is low density
4396residential with a cemetery and a recreational facility. The
4405property has pine/oak woods along the northwestern corner and a
4415mixed hardwood swamp on the northeastern corner. The property
4424is bisected north and south by the Tampa Bypass Canal.
443438. Once the SWFWMD property is exited the corridor turns
4444due east for approximately 5.4 miles until south of Lake
4454Thonotosassa, where it turns south. This portion is owned by
4464TECO. The corridor is 300 feet wide. The western portion is
4475primarily developing and developed lands surrounding the
4482corridor and, as it proceeds east, it crosses more rural lands,
4493pasture, strawberry fields, row crops, various agricultural
4500operations, cattle grazing, and some citrus groves. A portion
4509of the corridor contains a natural gas pipeline within TECO's
4519property. In addition to the agricultural vegetation, there is
4528a pine/oak area, some marsh, and some emergent aquatic
4537vegetation, along with some ponds. The corridor crosses Baker
4546Creek, a tributary to Lake Thonotosassa, which is north of the
4557corridor. A mixed hardwood swamp and a cypress swamp are found
4568here.
456939. The proposed corridor then turns south and approaches
4578areas of developing or developed lands. TECO's fee ownership
4587extends to the south. The corridor crosses Interstate 4 and, at
4598the beginning of its intersection with U.S. Highway 92, the
4608corridor has been expanded from approximately 3,100 feet up to
46195,100 feet in width to avoid a bald eagle's nest and the
4632scattered residences in the area. The widened corridor proceeds
4641south to State Road 574 or Martin Luther King Boulevard. Land
4652use is agricultural, low density residential, and undeveloped
4660property. This area of the corridor contains some pine/oak
4669woods, large areas of marsh, some crop land, some mixed hardwood
4680swamp, and scattered residential development.
468540. Once the corridor crosses State Road 574 it narrows
4695again to approximately 300 feet in width and is located on TECO
4707property. The corridor then proceeds south to the existing
4716Wheeler substation located off of Wheeler Road in Valrico.
4725There is a large amount of development to the west of the
4737corridor and developing lands to the east of the corridor.
4747B. From the Existing Wheeler Substation to the Planned
4756Willow Oak Substation
475941. From the existing Wheeler substation near Wheeler Road
4768the corridor proceeds south slightly more than one mile and then
4779turns east for approximately one mile before turning south to
4789State Road 60. In this portion of the corridor the width is
4801approximately 300 feet and it is located on TECO property.
4811There are residential properties in the vicinity of the
4820corridor, including the Diamond Hills and Sommerset
4827subdivisions. The land use is generally medium density
4835residential surrounding the corridor and also some agricultural
4843lands. Land uses in this area include pasture land, pine/oak
4853woods, crop land, marsh, open land, ponds, mixed hardwood
4862conifer swamp, and pine flat woods.
486842. The corridor proceeds east along State Road 60, which
4878is a major transportation corridor. The corridor is expanded to
4888approximately 2,000 to 3,000 feet in this area to allow
4900opportunities to follow other linear facilities that are located
4909south of State Road 60, such as other transmission lines or
4920roads. There are scattered residential properties with
4927agricultural uses, strawberry fields, pastures, and some citrus
4935in the area. Phosphate lands are located to the south of this
4947segment of the corridor. The corridor proceeds along to the
4957east. The majority of this area is reclaimed phosphate mining
4967lands.
496843. The final segment of the proposed corridor has again
4978been expanded to approximately 4,000 feet wide as it continues
4989along both sides of State Road 60 and both sides of Old Hopewell
5002Road. As the roads converge, the corridor is narrowed to
5012approximately 500 feet. From there it proceeds to the planned
5022Willow Oak substation in western Polk County. In this area
5032there is existing development surrounding the substation site
5040and proposed development along State Road 60. The South
5049Lakeland Airport is in this area. Along State Road 60 there is
5061a mix of commercial, residential, and some industrial
5069properties. The Willow Oak substation site is located within
5078open land.
5080IV. Compliance With Section 403.529(4) Criteria
5086A. Ensure Electric Power System Reliability and Integrity
509444. The PSC found that there are regional transmission
5103system limitations in northeast Hillsborough County. By 2012,
5111the existing 230 kV transmission network will not have
5120sufficient capability to provide reliable electric service to
5128the existing and proposed substations. The PSC also found that
5138some of the projected load to be served by the planned future
5150distribution substations will be located further east and north
5159of the existing 230 kV transmission network. The PSC determined
5169that the proposed transmission line is needed by March 2012 to
5180(a) provide additional transmission reinforcement to the
5187existing 230 kV transmission network north of State Road 60,
5197west of Willow Oak substation, and to the east of the existing
5209River substation in a reliable manner consistent with the NERC,
5219FRCC, and other applicable standards; (b) serve the increasing
5228load and customer base in the projected service areas; and (c)
5239provide for another electrical feed via a separate ROW path,
5249thereby reducing the impact of a loss of the existing
5259transmission facilities on a common ROW. The PSC concluded that
5269the Project is needed to preserve electric system reliability
5278and integrity.
5280B. Meet the Electrical Energy Needs of the State in an
5291Orderly and Timely Fashion
529545. The PSC recognized that TECO's planning studies
5303indicate that the proposed line is needed by March 2012 to
5314provide sufficient capability to provide reliable service to
5322existing and proposed substations.
532646. The location of the proposed transmission line on the
5336proposed corridor would meet the electrical energy needs of the
5346state in a timely fashion.
5351C. Comply with the Nonprocedural Requirements of Agencies
535947. Construction, operation, and maintenance of the
5366proposed corridor will comply with applicable nonprocedural
5373requirements of agencies.
537648. The Department has concluded that the Project as
5385proposed will comply with all applicable Department statutes,
5393rules, policies, and procedures.
5397D. Be Consistent with Applicable Local Government
5404Comprehensive Plans
540649. The Polk County Comprehensive Plan identified electric
5414transmission and distribution facilities as a permitted use in
5423all land use categories. In the Future Land Use Element of the
5435Hillsborough County Comprehensive Plan, there are an objective
5443and several policies that address bulk transmission lines. The
5452policies address the locational criteria and public input. The
5461policies will be met by the proposed transmission line. The
5471City of Temple Terrace's Comprehensive Plan does not address
5480bulk transmission lines.
548350. After certification of this project, TECO will acquire
5492the necessary property interests in a ROW within the certified
5502corridor for placement of the line. Construction of
5510transmission lines on such established ROWs is excepted from the
5520definition of "development" in Section 163.3164(5), Florida
5527Statutes. Accordingly, the provisions of the local
5534comprehensive plans related to "development" that have been
5542adopted by the local governments crossed by the line are not
5553applicable to this project.
555751. No variances or exemptions from applicable state or
5566local standards or ordinances are needed for the project.
5575E. Implementation of Legislative Intent in Section 403.521
5583a. The Need for the Line as a Means of Providing
5594Abundant Low-Cost Electrical Energy
559852. The PSC determined that the proposed line is needed
5608taking into account the factors set forth in Section 403.537,
5618Florida Statutes.
562053. The PSC found that TECO evaluated three alternatives
5629to the Project. All three were transmission modifications to
5638the proposed ROW that used a portion of, or the entire existing,
5650common ROW. The PSC accepted TECO's rejection of the
5659alternatives primarily because of economics and reliability
5666concerns. The PSC found that the proposed line will assure the
5677economic well-being of the citizens of the state by serving
5687projected new electric load in the region and improving the
5697region's electric reliability by minimizing the region's
5704exposure to single contingency events.
5709b. Impact Upon the Public
571454. The proposed line is appropriate from a land use
5724perspective. The Project takes advantage of the opportunity to
5733be collocated with other transmission lines, roadways, and ROWs.
5742By following these existing linear features, the corridor
5750conforms to existing and future development patterns and
5758minimizes intrusion into residential areas. As a result, the
5767proposed line is in proximity to relatively few residences.
577655. The line as proposed will comply with all applicable
5786nonprocedural agency standards, including the Department
5792standards in Florida Administrative Code Rule Chapter 62-814
5800limiting the electric and magnetic fields associated with new
5809transmission lines.
581156. TECO proposes to use five different configurations for
5820the transmission line, depending upon the location. The options
5829include a 230 kV single circuit roadside, a 230 kV single
5840circuit roadside with a 69 kV underbuild, a 230 kV single
5851circuit roadside with 69 kV and 13 kV distribution underbuild, a
5862230 kV single circuit for the South Lakeland Airport, and a
5873230 kV single circuit for use in the 300-foot existing TECO ROW.
5885For each of these configurations the Department's rule requires
5894that the electric and magnetic fields (or energy forces) be
5904calculated to ensure compliance. The electric field is what is
5914created underneath and outside of a transmission line as a
5924result of placing voltage on the conductor. It is a byproduct
5935of placing voltage on the conductor. The magnetic field is
5945created as a result of the current traveling along the
5955conductor. It is generally a magnetic flux field that surrounds
5965the conductors and the transmission lines.
597157. Those portions of Florida Administrative Code Rule
5979Chapter 62-814 that are applicable to this Project establish
5988maximum values for electric and magnetic fields. The electric
5997field is expressed as a kilovolt meter (kV/m) and compliance is
6008required both within the ROW and at the edge of the right-of-way
6020for the transmission line. The magnetic field is expressed as
6030milliGauss (mG) and compliance is determined at the edge of the
6041ROW.
604258. Compliance with the electric and magnetic field
6050requirements was calculated for each of the configurations that
6059may be utilized for the Project. The results were then compared
6070to the requirements of Florida Administrative Code Rule 62-
6079814.450(3). See TECO Exhibit 21. The maximum expected values
6088from all configurations for the electric fields within the ROW
6098and at the edge of the ROW and for the magnetic fields at the
6112edge of the ROW are all below the values set forth in the rule.
612659. The maximum voltage and current that is ever
6135anticipated for the line during its life are used in making the
6147calculations. However, it is highly unlikely that this
6155condition would occur. It is anticipated that the maximum
6164condition would occur less than five percent of the time while
6175the transmission line is operating. In order to operate at the
6186maximum level the conductor must be operating at its maximum
6196temperature and the conductor would be at its lowest point in
6207the span to create that condition. There would also need to be
6219some type of system disturbance that would cause a maximum
6229condition to occur. This would be a worst case scenario.
6239Levels for electric fields will be less at the normal operating
6250levels and magnetic fields about fifty percent less.
625860. Intervenors own property and live within the area of
6268the expanded corridor between U.S. Highway 92 and State Road 574
6279in Dover. In this area TECO owns a 300-foot ROW originally
6290considered for the corridor, which contains an eagle's nest.
6299While this area is near the Intervenors' property, the proposed
6309corridor is the entire area up to 5,100 feet in width, and the
6323actual ROW location for the line has not yet been determined.
6334Intervenors are primarily concerned about the potential health
6342effects to their son caused by exposure to electric and magnetic
6353fields from the transmission line in the vicinity of their
6363property. In support of these concerns, they presented the
6372prefiled, written testimony of Dr. Hanoch Talmor, a medical
6381doctor in Gainesville, Florida, who has treated their son for
6391over fifteen years. Doctor Talmor is a board-certified
6399pediatrician who now specializes in the area of general holistic
6409medicine.
641061. In his written statement Dr. Talmor states that
6419Intervenors' son is at present nonambulatory and nonverbal. He
6428also testified that he displays severe chemical sensitivities
6436and is listed on the state chemically sensitive lists. Although
6446he is not a neurologist, Dr. Talmor opined that because of the
6458son's neurological involvement and his extensive medical
6465history, he would be adversely affected by high voltage power
6475lines near his home. He further testified that the son has
6486seizures which can be affected by smells, sounds, visual
6495stimuli, sleep patterns, and allergic reactions.
650162. During cross-examination, Dr. Talmor acknowledged that
6508he is not familiar with the levels of electric and magnetic
6519fields expected to result from this transmission line in the
6529vicinity of Intervenors' property. Even so, he opined that the
6539only safe levels of electric and magnetic fields with regard to
6550human exposure would be at levels of zero. He admitted,
6560however, that electric devices typically found in the household
6569such as clocks, ovens, refrigerators, televisions, electric
6576blankets, and the like, as well as electric wiring in the house,
6588would be expected to produce electric and magnetic fields to
6598which a person living in the house would be exposed. At the
6610certification hearing, Dr. Talmor also discussed various
6617research articles concerning this subject. In formulating his
6625opinions, however, Dr. Talmor had reviewed only summaries and
6634excerpts of the studies, rather than the complete studies.
664363. TECO presented the testimony of Dr. Laura S. Erdreich,
6653an epidemiologist, who is familiar with the configuration for
6662the transmission ROW that is proposed to be used in the vicinity
6674of Intervenors' residence. Doctor Erdreich testified that she
6682is familiar with the levels expected to be produced from the
6693transmission line at the edge of the ROW. With regard to
6704electric fields, Dr. Erdreich testified that the lowest level
6713that has ever been proposed as being necessary for the
6723protection of human health is 4.2 kV/m. This was by an
6734organization called the International Commission for Non-
6741Ionizing Radiation Protection (ICNIRP). The organization is
6748based in Europe and is sponsored by the World Health
6758Organization. The level that organization recommended is more
6766than twice the maximum level of 2.0 kV/m found in Florida
6777Administrative Code Rule 62-814.450(3)(a). The maximum expected
6784electric fields at the edge of the ROW for the Project in the
6797vicinity of Intervenors' residence is 0.1 kV/m.
680464. For magnetic fields, Dr. Erdreich testified that the
6813ICNIRP proposed a level of 833 mG as being protective of human
6825health based on exposure. This is the lowest level that has
6836been proposed by any regulatory authority or similar body based
6846on potential health effects. In contrast, Florida
6853Administrative Code Rule 62-814.450(3)(d) provides in relevant
6860part that the "maximum magnetic field at the edge of a 230 kV or
6874smaller transmission ROW . . . shall not exceed 150 mG." This
6886value is much greater than the 13.6 mG maximum level expected at
6898the edge of the TECO ROW and in the vicinity of Intervenors'
6910home. Under typical operational conditions, the expected
6917magnetic field would be approximately 7 mG, which is less than
6928one percent of the health-based exposure limit recommended by
6937the ICNIRP.
693965. Doctor Erdreich also testified that she is familiar
6948with the research that has been conducted concerning health
6957effects from environmental exposure to electric and magnetic
6965fields. The research includes epidemiological studies of humans
6973in the natural environment, laboratory studies which typically
6981expose all animals to high levels often for nearly their entire
6992lifetime, and studies of cells and tissues in laboratories to
7002try to isolate the mechanism that may affect humans. The amount
7013of research being performed has been reduced over the last few
7024years because, despite considerable research, an adverse effect
7032from exposure to humans at environmental levels has not been
7042substantiated. Additionally, causal associations between
7047exposure and health effects have not been found when the data
7058and research have been reviewed by committees of scientists of
7068various disciplines. Doctor Erdreich testified that she is
7076aware of the studies that were referred to by Dr. Talmor as well
7089as other studies on the subject. Although the subject of
7099exposure to low levels, even on a long-term basis, such as
7110levels less than 10 mG, has been studied extensively, she noted
7121that the findings have been that magnetic fields have no known
7132effect on the human body until exposure to levels well above
71431,000 mG.
714666. The United States Government does not regulate
7154electric and magnetic exposure except in occupational settings.
7162There are no requirements for regulation of transmission lines
7171in these areas. The State of Florida is one of only a few
7184states that have such requirements. There is no existing body
7194of research demonstrating that adverse health consequences
7201result from exposure to electric and magnetic fields at the
7211levels expected to result from the 300-foot ROW single pole
7221configuration that is proposed for the vicinity of Intervenors'
7230property. Doctor Erdreich opined that these levels do not pose
7240a threat of adverse health effects to the population near the
7251edge of the ROW. She further opined that in the unlikely
7262circumstance that the edge of the ROW for the transmission line
7273would be placed at the edge of the residence of the property,
7285the levels of electric and magnetic fields from the transmission
7295line would still not create a health concern. She also stated
7306that her opinion would be the same if one of the residents were
7319shown to have an illness that resulted in a chemical
7329sensitivity. She based her opinions on the fact that there is
7340no evidence demonstrating any correlation between this exposure
7348and adverse health effects. Finally, Dr. Erdreich testified
7356that no group has ever suggested that there is a need for lower
7369levels near hospitals or convalescent facilities or other places
7378where physical therapy occurs.
738267. The levels of electric and magnetic fields from the
7392transmission line will decrease as one moves further from the
7402edge of the ROW. The levels expected from the transmission
7412line, which are already well below the State requirements and a
7423small fraction of the lowest levels that have ever been
7433suggested as being required for the protection of human health,
7443are similar to the levels that would be expected to result from
7455common household appliances.
745868. Mrs. Watson testified that her residence has
7466electricity and electric household appliances such as air-
7474conditioning, television, refrigerator, and a vacuum cleaner.
7481All of these devices produce electric and magnetic fields at
7491levels in the range of what would be expected from the TECO
7503transmission line. Additionally, there is natural exposure to
7511magnetic fields and electric and magnetic fields from electrical
7520devices that are encountered in everyday life.
7527ansmission lines can generate audible noise as a
7535result of irregularities that collect on the conductor. During
7544periods of fair weather dust can collect on the conductor and
7555that may cause low levels of audible noise. When rain is
7566experienced, the dust is washed off but replaced with water
7576droplets on the conductor that create a condition that results
7586in slightly higher levels of audible noise. The noise levels
7596experienced during rainfall events are temporary, and the noise
7605is reduced as soon as the water droplets evaporate from the
7616conductor.
761770. The expected levels of noise are generally calculated
7626using a program called the Bonneville Power Administration Field
7635Effects Program. The information utilized to make the
7643calculations includes the conductor size, the configuration of
7651the transmission line, and the voltage expected.
765871. The calculations performed for the transmission line
7666show that the audible noise levels at the edge of the ROW during
7679fair weather would range from 16.1 dBA, which is decibels of
7690noise in a range that can be heard, to a high of 22.5 dBA.
7704During periods of rainfall the expected audible noise at the
7714edge of the ROW ranges from a low of 41.1 dBA to a high of
772947.5 dBA. For the ROW configuration that is proposed for the
7740area including the Watson property, the expected levels during
7749fair weather are a maximum of 16.1 dBA and during foul weather a
7762maximum of 41.1 dBA at the edge of the ROW. The noise levels
7775will decrease as one moves away from the edge of the ROW. Also,
7788during rainfall events, when the maximum noise levels are
7797expected, the rain will tend to mask the sound from the
7808transmission line.
781072. Studies that have been prepared on this issue indicate
7820that complaints concerning noise are primarily related to
7828interference with sleep. The studies indicate that to minimize
7837the potential of interference with sleep, the noise level
7846outside of the home should not exceed 50 dBA. The maximum
7857expected noise level from the Project will not exceed 50 dBA.
7868Mr. Brooks, TECO's expert who testified on this issue, stated
7878that he had never had an occasion to deal with a noise level
7891complaint during his thirty-seven years of experience with
7899transmission lines.
790173. TECO Exhibit 22 contains a summary of the audible
7911noise expected from the transmission line for the various
7920configurations. It also contains a chart with the noise levels
7930expected from common activities for comparative purposes. The
7938maximum fair weather audible noise from any of the five
7948configurations would be comparable to the levels that one would
7958encounter in a bedroom at night. The maximum levels for the
7969same configurations during foul weather would be comparable to
7978what one might experience in a quiet office or a living room.
7990The levels for the configuration to be utilized in the area of
8002the Watson property are below the maximums for the Project and
8013significantly less than levels expected at a quiet office or
8023bedroom at night.
802674. At the public portion of the certification hearing,
8035thirty-five members of the public uniformly testified in
8043opposition to the Project, as proposed. A number of those
8053testifying expressed concern about the impact of the Project on
8063property values, the possible effects of the electric and
8072magnetic fields expected from the transmission line once the ROW
8082has been selected and the line constructed, and the desire to
8093have TECO seek another route. Although these concerns are
8102genuine, impacts on property values is not a subject for
8112consideration at this hearing. As discussed above in greater
8121detail, the evidence demonstrates that adverse impacts from the
8130low levels of electric and magnetic fields projected from the
8140Project are not expected. No alternate corridors have been
8149proposed for consideration by any party to this proceeding.
8158Finally, some members of the public complained that they were
8168unaware that a new transmission line corridor was being proposed
8178until just before the hearing. However, the evidence shows that
8188long before the certification hearing, information concerning
8195this process was widely disseminated through advertisements,
8202open houses, mass mailings, surveys, and meeting with regulatory
8211agencies and local elected officials.
8216c. Impact Upon the Environment
822175. The Project as proposed will have minimal
8229environmental impact.
823176. Construction of the line within the proposed corridor
8240will not adversely affect the conservation of fish and wildlife,
8250including endangered or threatened species, or their habitats.
8258The proposed corridor avoids or minimizes intrusion into the
8267undisturbed wildlife habitats due to its collocation with
8275existing linear facilities for almost its entire length. The
8284current condition and relative value of function of the habitat
8294in the proposed corridor is generally minimal from a wildlife
8304ecology and protected species perspective. There are some areas
8313with higher quality habitat. One is in the area south of Lake
8325Thonotosassa. In that location, there is a natural gas pipeline
8335corridor that already disturbs the area in the proposed
8344corridor. In the area of the bald eagle's nest, clearing in the
8356ROW would be limited to 25 to 100 feet in width. Also, the
8369Conditions of Certification require extensive surveys and plans
8377for wildlife protection. The area has experienced clearing and
8386tree removal to accommodate development. Care was taken in
8395routing the proposed corridor to avoid or minimize proximity of
8405the corridor to known listed species locations, including
8413routing inputs from wildlife agencies such as the FFWCC and the
8424U.S. Fish and Wildlife Service (USFWS). Clearing of additional
8433natural habitats and potential wetland impacts will be
8441minimized.
844277. During the regional screening route selection process
8450the known locations of bald eagle nests were identified and
8460mapped. Members of the public pointed out at the open houses
8471that there existed a previously unreported bald eagle nest in
8481the area north of Jess Baldwin Road. This was subsequently
8491verified and identified as a correct location of an eagle nest
8502that had been previously unknown to the FFWCC and USFWS. When
8513the nest was identified and located, the corridor was expanded
8523up to 5,100 feet in this area to give TECO maximum flexibility
8536in avoiding potential impacts to the nest as well as to existing
8548homes in the area. TECO has begun a long-term monitoring
8558program for this particular nest and this will be continued
8568until such time as the applicant and the agencies deem it
8579sufficient. The program is designed to monitor the activity of
8589the eagles in the area with respect to successful breeding,
8599successful rearing of the young, and the habitat usage and
8609flight patterns from that nest. This information will be
8618utilized in the selection of the ultimate ROW in this area to
8630avoid any impacts to the nesting area.
863778. The USFWS and FFWCC establish buffers for limiting
8646activity in proximity to an eagle's nest. The buffers are
8656either 330 feet or 660 feet in diameter, depending on the level
8668of construction activity that is to be carried out. In cases in
8680which a more minimal level of construction is to be performed, a
8692660-foot buffer must be maintained if there is not visual buffer
8703between the nest and the construction activity. A 330-foot
8712buffer must be maintained at all times. If a visual buffer can
8724be maintained in the area of this eagle's nest, the buffer size
8736could be reduced below 660 feet, providing additional
8744flexibility for the location of the ROW. This determination
8753will be made by the USFWS and FFWCC.
876179. Construction of the line within the proposed corridor
8770will not cause a significant adverse impact to the current
8780condition and relative value of functions of the vegetative
8789communities within the corridor. Much of the length of the
8799corridor allows placement of the transmission line within or
8808adjacent to existing linear features to take advantage of
8817previous disturbances to vegetation. TECO will also minimize
8825impacts to forested wetland vegetation through the use of
8834restrictive clearing practices during both construction and
8841maintenance. In the forested wetland portions of the ROW, trees
8851and shrubs that have an expected mature height greater than
8861fourteen feet and "danger trees," which are trees that could
8871fall into the conductors and cause an outage, will be removed.
8882Other vegetation will generally not be disturbed. In these
8891areas, vegetation will be removed by hand, usually with chain
8901saws or with low-ground-pressure equipment to reduce soil
8909compaction and damage to ground cover. The removal of
8918vegetation in forested wetlands will not significantly affect
8926the vegetative root mat or soil surface conditions. The non-
8936forested wetlands should not require any clearing.
894380. There will be some filling in wetlands associated with
8953the placement of pole pads and access roads. However, TECO will
8964minimize these impacts through a careful alignment of the ROW
8974and the varying of span distances between poles. TECO will also
8985install an appropriate number and size of culverts to properly
8995maintain existing wetland hydroperiods along areas of fill in
9004wetlands. Also, any unavoidable wetland impacts associated with
9012the project will be mitigated in accordance with the Conditions
9022of Certification.
902481. TECO has utilized information from the Hillsborough
9032and Polk County Comprehensive Plans and the Department of State,
9042Division of Historical Resources (DHR), to identify potential
9050archeological and historical resources within the proposed
9057corridor. A number of locations were identified as a result of
9068the information and the Conditions of Certification require that
9077a survey be performed when the actual ROW is located. If any
9089artifacts are found the information will be submitted to the DHR
9100for analysis and decisions will be made as to how to proceed.
9112The proposed corridor contains the least potential impacts to
9121known sites and the corridor allows ample opportunity for siting
9131the ROW to avoid potential historic and archeological sites.
914082. In addition to comments from the public described in
9150Finding of Fact 74, a number of members of the public expressed
9162concern over the environmental impacts from the construction and
9171maintenance of the transmission line. Some of those expressing
9180concerns have residences or property in the area of the expanded
9191corridor surrounding the eagle's nest. Although some of these
9200individuals are within the corridor, it is not clear at this
9211point that they will be near or adjacent to the ROW which is
9224ultimately selected. The ROW is proposed to be within the
9234expanded corridor in this area. The eagle's nest presents a
9244constraint with a 330 or 660-foot buffer. Evaluations will be
9254performed considering impacts to the community and homes,
9262impacts to the environment, and costs. If the buffer is reduced
9273to 330 feet this will assist in the routing of the ROW. As
9286detailed above, TECO engaged in extensive public outreach, made
9295efforts to avoid populated areas with the corridor location, and
9305the Conditions of Certification require extensive measures to
9313eliminate or minimize the potential impacts on wildlife and
9322habitat. TECO will minimize any necessary cutting of trees in
9332areas that do not already have an established ROW. The area of
9344clearing will be limited to from 25 to 100 feet in width.
935683. The Project will comply with all applicable state,
9365regional, and local nonprocedural regulations, including the
9372wetland regulatory standards applicable to such projects.
9379d. Balance of Need versus Impacts
938584. The Project effects a reasonable balance between the
9394need for a transmission line as a means for providing abundant
9405low cost energy and the impact upon the public and the
9416environment resulting from the location of the transmission line
9425corridor and the construction and maintenance of the
9433transmission line.
9435V. Conditions of Certification
943985. The design, construction, and operation of the line in
9449the proposed corridor will comply with the Conditions of
9458Certification set forth in Department Exhibit 4.
946586. The Conditions of Certification establish a post-
9473certification review process through which the final ROW, access
9482road, and structure locations will be reviewed by agencies with
9492regulatory authority over the project for the purpose of
9501monitoring for compliance with the Conditions of Certification.
950987. While the proposed corridor has few homes in close
9519proximity to it and very limited wetland crossings, TECO has
9529agreed to conditions of certification that further minimize land
9538use and environmental impacts. For example, TECO has agreed
9547that to the extent practicable it will locate its ROW to avoid
9559the taking of homes, to collocate the ROW within or adjacent to
9571existing ROWs, and to vary the length of the span between poles
9583as appropriate to eliminate or reduce wetland impacts.
9591CONCLUSIONS OF LAW
959488. The Division of Administrative Hearings has
9601jurisdiction over the parties and the subject matter of this
9611proceeding. §§ 120.569 and 403.527(1), Fla. Stat.
961889. This certification proceeding was held pursuant to the
9627Transmission Line Siting Act, Sections 403.52 through 403.5365,
9635Florida Statutes, and Florida Administrative Code Rule Chapter
964362-17, Part II. The intent of this certification process is:
9653to fully balance the need for the
9660transmission lines with the broad interests
9666of the public in order to effect a
9674reasonable balance between the need for the
9681facility as a means of providing abundant
9688low-cost electrical energy and the impact on
9695the public and the environment resulting
9701from the location of the transmission line
9708corridor and the construction and
9713maintenance of the transmission lines.
9718§ 403.521, Fla. Stat. To implement this intent, the Legislature
9728has set forth specific requirements for the PSC to determine the
9739need for the proposed transmission line and address other
9748matters within its jurisdiction, for other various agencies to
9757prepare reports and studies regarding matters within their
9765jurisdiction, for publication of notice of the application and
9774certification proceeding, for third parties to have an
9782opportunity to offer alternate corridor routes for
9789consideration, and for criteria to be considered in determining
9798whether an application should be approved in whole, approved
9807with modification or conditions, or denied. See §§ 403.526,
9816403.527, 403.5271, 403.529, and 403.537, Fla. Stat.
982390. All parties identified in Finding of Fact No. 1 have
9834standing in this proceeding.
983891. TECO has the burden of proving that, under the
9848criteria of Section 403.529(4)(a)-(e), Florida Statutes, the
9855proposed corridor for the Willow Oak-Wheeler-Davis transmission
9862line should be certified as proposed based upon a preponderance
9872of the evidence presented at the certification hearing. See,
9881e.g. , Fla. Dept. of Transp. v. J.W.C Co., Inc. , 396 So. 2d 778,
9894788 (Fla. 1st DCA 1981).
989992. The evidence in the record of this proceeding
9908demonstrates compliance with the procedural requirements of the
9916TLSA, including the notice requirements for the certification
9924and public hearings. It is noted that TECO voluntarily engaged
9934in an extensive public outreach program that included additional
9943newspaper notices and extensive mailings.
994893. In deciding whether TECO's Application should be
9956approved, approved with conditions, or denied, the Siting Board
9965must determine whether, and the extent to which, the location of
9976the corridor and the construction and maintenance of the
9985transmission line in the corridor will:
9991(a) Ensure electric power system
9996reliability and integrity;
9999(b) Meet the electrical energy needs of the
10007state in an orderly and timely fashion;
10014(c) Comply with nonprocedural requirements
10019of agencies;
10021(d) Be consistent with applicable local
10027government comprehensive plans; and
10031(e) Effect a reasonable balance between the
10038need for the transmission line as a means of
10047providing abundant low-cost electrical
10051energy and the impact upon the public and
10059the environment resulting from the location
10065of the transmission line corridor and the
10072maintenance of the transmission lines.
10077§ 403.529(4), Fla. Stat.
1008194. Compliance with Section 403.529(4)(a), Florida
10087Statutes . The PSC determined the need for a new 230 kV
10099transmission line between the planned Willow Oak and Wheeler
10108substations with an intermediate connection to the existing
10116Wheeler substation in Order No. PSC-07-0522-FOF-EI issued on
10124June 21, 2007. Among other things, the PSC found that the
10135existing 230 kV transmission network will not have sufficient
10144capability to provide reliable service to the existing and
10153proposed substations by the year 2012. The PSC also found that
10164some of the projected load to be served by the proposed
10175distribution substations will be located further east and north
10184of the existing 230 kV transmission network. It further found
10194that the proposed transmission line is needed by March 2012 to
10205(a) provide additional transmission reinforcement to the
10212existing 230 kV transmission network north of State Road 60,
10222west of Willow Oak substation and to the east of the existing
10234River substation in a reliable manner consistent with other
10243applicable standards; (b) serve the increasing load and customer
10252base in the projected service area; and (c) provide for another
10263electrical feed via a separate ROW path, thereby reducing the
10273impact of the loss of the existing transmission facilities on a
10284common ROW. The PSC's determination of need for the project is
10295binding on all parties to the certification proceeding. See
10304§ 403.537(1)(d), Fla. Stat. Based upon the PSC Order
10313determining need, a prima facie showing that the proposed
10322transmission line would enhance electric system reliability,
10329integrity, and restoration of service has been made. Finally,
10338the PSC found that the corridor meets the criteria of
10348Section 403.529(4)(a), Florida Statutes.
1035295. Compliance with Section 403.529(4)(b), Florida
10358Statutes . The PSC acknowledged in its Order Determining Need
10368for the proposed line that TECO demonstrated the need for the
10379line by March 2012. Evidence regarding the design of the
10389transmission line, the construction phases for the transmission
10397line, including the projected 12 to 18-month construction
10405schedule, and the proposed location of the line, demonstrates
10414that the Project will meet the electrical needs of the State in
10426an orderly and timely fashion within the timeframes established
10435by the PSC.
1043896. Compliance with Section 403.529(4)(c), Florida
10444Statutes . The evidence supports a conclusion that the location
10454of the transmission line in the proposed corridor and the
10464construction and maintenance of that line in conformance with
10473the recommended Conditions of Certification contained in
10480Department Exhibit 4 will comply with the non-procedural
10488requirements of all agencies.
1049297. Compliance with Section 403.529(4)(d), Florida
10498Statutes . The evidence supports a conclusion that there are no
10509inconsistencies between the proposed transmission line and the
10517comprehensive plans adopted by local governments whose
10524jurisdictions are crossed by the proposed line.
1053198. Compliance with Section 403.529(4)(e), Florida
10537Statutes . The location of the proposed corridor and the
10547construction, operation, and maintenance of the transmission
10554line in that corridor provide a reasonable balance between the
10564need for the transmission line and the impact of the
10574transmission line upon the public and the environment. The
10583impact upon the public and the environment will be minimized by
10594the collocation with existing linear facilities where feasible,
10602the practices that TECO will utilize concerning clearing
10610activities and construction and operation activities to minimize
10618unnecessary clearing, the avoidance of wetland areas where
10626feasible, the avoidance of taking homes where feasible, and
10635compliance with the extensive Conditions of Certification that
10643have been imposed by the Department and other agencies.
10652Measures have been and will be taken to minimize the impact to
10664the previously undocumented bald eagle's next and a buffer of at
10675least 330 feet will be established in accordance with applicable
10685guidelines to protect the nest. The corridor has been widened
10695in appropriate locations to provide TECO with flexibility in
10704locating the ROW, and the Conditions of Certification have
10713requirements to which TECO has agreed concerning the
10721establishment of the ROW and impacts to the environment and
10731residents. The electric and magnetic field levels expected from
10740the transmission line have been shown to be significantly below
10750the maximum limits in effect in Florida and a small fraction of
10762the lowest levels that have ever been even proposed based upon
10773potential effects to human health. The evidence does not
10782demonstrate that the location of the ROW in reasonable proximity
10792to Intervenors' residence will increase the potential exposure
10800to electric and magnetic fields of the residents beyond that
10810which is already occurring as a result of everyday living.
10820Research has not demonstrated that levels in the range expected
10830from the Project produce any adverse health effects. The
10839overall impacts of the Project have been shown to be minimal,
10850particularly when balanced with the significant electrical
10857energy requirements that will be satisfied by construction and
10866operation of the transmission line within the proposed corridor.
1087599. While the concerns of Intervenors and the members of
10885the public who offered comments on the proposal are genuine and
10896well-intended, they do not constitute a basis under the TLSA or
10907applicable Department rules for modifying, or providing further
10915conditions to, the corridor, or denying the Application. 3
10924100. Based upon a preponderance of the evidence presented
10933at the certification hearing, TECO has met its burden of proving
10944that the transmission line and related facilities should be
10953certified as proposed, subject to the Conditions of
10961Certification included in Department Exhibit 4.
10967RECOMMENDATION
10968Based upon the foregoing Findings of Fact and Conclusions
10977of Law, it is
10981RECOMMENDED that the Siting Board enter a Final Order
10990approving Tampa Electric Company's Willow Oak-Wheeler-Davis 230
10997kV Transmission Line Application for Certification subject to
11005the Conditions of Certification set forth in Department Exhibit
110144.
11015DONE AND ENTERED this 13th day of May, 2008, in
11025Tallahassee, Leon County, Florida.
11029S
11030DONALD R. ALEXANDER
11033Administrative Law Judge
11036Division of Administrative Hearings
11040The DeSoto Building
110431230 Apalachee Parkway
11046Tallahassee, Florida 32399-3060
11049(850) 488-9675 SUNCOM 278-9675
11053Fax Filing (850) 921-6847
11057www.doah.state.fl.us
11058Filed with the Clerk of the
11064Division of Administrative Hearings
11068this 13th day of May, 2008.
11074ENDNOTES
110751/ All subsequent references are to the 2007 version of the
11086Florida Statutes.
110882/ The estimated capital cost of the transmission line is $72.2
11099million, excluding right-of-way costs. See TECO Exhibit 1,
11107Appendix A.
111093/ For obvious reasons, it can be said with almost certainty
11120that no owner, tenant, or lessee desires to have a transmission
11131line, with large concrete poles, related equipment, and wires,
11140placed near or adjacent to his or her property.
11149COPIES FURNISHED:
11151Lea Crandall, Agency Clerk
11155Department of Environmental Protection
111593900 Commonwealth Boulevard
11162Mail Station 35
11165Tallahassee, Florida 32399-3000
11168Gregory M. Munson, General Counsel
11173Department of Environmental Protection
111773900 Commonwealth Boulevard
11180Mail Station 35
11183Tallahassee, Florida 32399-3000
11186Lawrence N. Curtin, Esquire
11190Holland & Knight LLP
11194Post Office Box 810
11198Tallahassee, Florida 32302-0810
11201Toni L. Sturtevant, Esquire
11205Department of Environmental Protection
112093900 Commonwealth Boulevard
11212Mail Station 35
11215Tallahassee, Florida 32399-3000
11218Kelly A. Martinson, Esquire
11222Department of Community Affairs
112262555 Shumard Oak Boulevard
11230Tallahassee, Florida 32399-2100
11233Marva M. Taylor, Esquire
11237Assistant County Attorney
11240601 East Kennedy Boulevard
11244County Center, 27th Floor
11248Tampa, Florida 33602-4156
11251Michael E. Duclos, Esquire
11255Assistant County Attorney
11258Post Office Box 9005
11262Bartow, Florida 33831-9005
11265Martha A. Moore, Esquire
11269Southwest Florida Water Management District
112742379 Broad Street
11277Brooksville, Florida 34604-6899
11280Susan Watson
112823624 Windchime Lane
11285Dover, Florida 33527-4930
11288Seauching Yu, Esquire
11291Department of Transportation
11294605 Suwannee Street
11297Mail Station 58
11300Tallahassee, Florida 32399-0458
11303James V. Antista, General Counsel
11308Florida Fish and Wildlife
11312Conservation Commission
11314620 South Meridian Street
11318Tallahassee, Florida 32399-1600
11321Manny L. Pumariega, Executive Director
11326Tampa Bay Regional Planning Council
113314000 Gateway Centre Boulevard, Suite 100
11337Pinellas Park, Florida 33782-6138
11341Patricia M. Steed, Executive Director
11346Central Florida Regional
11349Planning Council
11351555 East Church Street
11355Bartow, Florida 33830-3931
11358Samantha M. Cibula, Esquire
11362Florida Public Service Commission
113662540 Shumard Oak Boulevard
11370Tallahassee, Florida 32399-0850
11373Shaw P. Stiller, General Counsel
11378Department of Community Affairs
113822470 Centerview Drive
11385Tallahassee, Florida 32399-2100
11388NOTICE OF RIGHT TO FILE EXCEPTIONS
11394All parties have the right to submit written exceptions within
1140415 days of the date of this Recommended Order. Any exceptions
11415to this Recommended Order should be filed with the agency that
11426will render a final order in this matter.
![](/images/view_pdf.png)
- Date
- Proceedings
-
PDF:
- Date: 06/05/2008
- Proceedings: Department of Transportation`s Notice of Substitution of Counsel filed.
-
PDF:
- Date: 05/14/2008
- Proceedings: Letter to Lea Crandall from Judge Alexander regarding corrected page 1 to the Recommended Order filed.
-
PDF:
- Date: 05/13/2008
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
-
PDF:
- Date: 05/13/2008
- Proceedings: Recommended Order (hearing held March 4 and 5, 2008). CASE CLOSED.
-
PDF:
- Date: 04/16/2008
- Proceedings: Stipulation between Tampa Electric Company and the City of Temple Terrace filed.
-
PDF:
- Date: 04/15/2008
- Proceedings: Petitioner Susan Watson`s Proposed Recommended Order (completed) filed.
-
PDF:
- Date: 04/11/2008
- Proceedings: Petitioner Susan Watson`s Proposed Recommended Order (incomplete) filed.
-
PDF:
- Date: 04/03/2008
- Proceedings: Reply to Intervenor Watson`s Response to Applicant`s Opposition to Motion to Strike filed.
- Date: 04/02/2008
- Proceedings: Transcript (Volumes 1-3) filed.
-
PDF:
- Date: 03/27/2008
- Proceedings: Intervenor Susan Watson`s Response to Applicant`s Opposition to her Motion to Strike Late Filed Exhibit filed.
-
PDF:
- Date: 03/24/2008
- Proceedings: Applicant`s Response in Opposition to Intervenor`s Motion to Strike Late Filed Exhibit and Notice of Filing Late Filed Exhibit filed.
-
PDF:
- Date: 03/17/2008
- Proceedings: Intervenor Susan Watson`s Motion to Strike Tampa Electric Company`s Late File Exhibit and Notice of Filing Late Filed Exhibit filed.
-
PDF:
- Date: 03/12/2008
- Proceedings: Notice of Filing Late filed Exhibits (exhibits not available for viewing) filed.
- Date: 03/04/2008
- Proceedings: CASE STATUS: Hearing Held.
-
PDF:
- Date: 03/03/2008
- Proceedings: Letter to (Whom it may concern) from H. Talmor enclosing written testimony regarding T. Watson filed.
-
PDF:
- Date: 02/29/2008
- Proceedings: Response to Motion for Leave to Allow Expert Witness to Appear by Telephone filed.
-
PDF:
- Date: 02/28/2008
- Proceedings: Motion for Leave to Allow Expert Witness to Appeal by Phone filed.
-
PDF:
- Date: 02/26/2008
- Proceedings: Tampa Electric Company`s Notice of Filing Prehearing Stipulation filed.
-
PDF:
- Date: 02/14/2008
- Proceedings: Tampa Electric Company`s Response to City of Temple Terrace`s Unopposed Motion to Participate in Certification Proceedings filed.
-
PDF:
- Date: 02/13/2008
- Proceedings: City of Temple Terrace`s Unopposed Motion to Participate in the Certification Proceedings filed.
-
PDF:
- Date: 02/13/2008
- Proceedings: City of Temple Terrace`s Tardy Notice of Intent to Become a Party to the Certification Proceedings filed.
-
PDF:
- Date: 02/05/2008
- Proceedings: Letter to Judge Johnston from S. Watson regarding interested party in certification hearing filed.
-
PDF:
- Date: 02/04/2008
- Proceedings: Transmission Line Site Certification Staff Analysis Report filed.
-
PDF:
- Date: 02/04/2008
- Proceedings: Hillsborough County`s Notice of Intent to Become a Party to the Certification Proceedings filed.
-
PDF:
- Date: 01/31/2008
- Proceedings: City of Temple Terrace`s Proposed Revisions to the Department of Environmental Protection`s Draft Conditions of Certification filed.
-
PDF:
- Date: 01/18/2008
- Proceedings: Notice of Public Hearing (hearing will be held March 5, 2008; 7:00 p.m.; Brandon, FL)
-
PDF:
- Date: 01/16/2008
- Proceedings: Hillsborough County`s Request for Public Hearing Supplementing the Certification Hearing filed.
-
PDF:
- Date: 01/07/2008
- Proceedings: Amended Notice of Hearing (hearing set for March 4 through 7 and 10 through 14, 2008; 9:00 a.m.; Brandon, FL; amended as to location).
-
PDF:
- Date: 12/26/2007
- Proceedings: Department of Environmental Protection`s Determination of Completeness filed.
-
PDF:
- Date: 12/21/2007
- Proceedings: City of Temple Terrace`s Notice of Consent to Findings of Completeness filed.
-
PDF:
- Date: 12/20/2007
- Proceedings: Notice of Filing City of Temple Terrace`s Second Set of Completeness Questions filed.
-
PDF:
- Date: 12/20/2007
- Proceedings: City of Temple Terrace`s Second Set of Completeness Questions filed.
-
PDF:
- Date: 12/19/2007
- Proceedings: Notice of Filing City of Temple Terrace`s Second Set of Completeness Questions filed.
-
PDF:
- Date: 12/19/2007
- Proceedings: City of Temple Terrace`s Second Set of Completeness Questions filed.
-
PDF:
- Date: 12/03/2007
- Proceedings: Tampa Electric Company`s Notice of Filing Completeness Response filed.
-
PDF:
- Date: 11/14/2007
- Proceedings: Southwest Florida Water Management District`s Notice of Filing filed.
-
PDF:
- Date: 11/14/2007
- Proceedings: Southwest Florida Water Management District`s Notice of Intent to be a Party filed.
-
PDF:
- Date: 11/14/2007
- Proceedings: City of Temple Terrace`s Recommendations and First Set of Completeness Questions filed.
-
PDF:
- Date: 11/13/2007
- Proceedings: Department of Community Affairs` Notice of Intent to be a Party filed.
-
PDF:
- Date: 11/09/2007
- Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
-
PDF:
- Date: 10/26/2007
- Proceedings: Notice of Hearing (hearing set for March 4 through 7 and 10 through 14, 2008; 9:00 a.m.; Tampa, FL).
-
PDF:
- Date: 10/25/2007
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
-
PDF:
- Date: 10/25/2007
- Proceedings: Department of Environmental Pretection`s Notice of Filing of Transmission Line Siting Application (exhibits not available for viewing) filed.
-
PDF:
- Date: 10/19/2007
- Proceedings: Department of Environmental Protection`s Notice of Filing of Transmission Line Siting Application filed.
-
PDF:
- Date: 10/19/2007
- Proceedings: Tampa Electric Company`s Notice of Distribution of Additional Copies of Corridor Certification Application filed.
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 10/15/2007
- Date Assignment:
- 02/29/2008
- Last Docket Entry:
- 08/12/2008
- Location:
- Brandon, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- TL
Counsels
-
James V. Antista, Esquire
Address of Record -
Samantha M. Cibula, Esquire
Address of Record -
Lawrence N. Curtin, Esquire
Address of Record -
Michael E Duclos, Esquire
Address of Record -
Kelly M. Fernandez, Esquire
Address of Record -
Martha A. Moore, Esquire
Address of Record -
Manny L. Pumariega
Address of Record -
Patricia M. Steed
Address of Record -
Toni L. Sturtevant, Esquire
Address of Record -
Marva M. Taylor, Esquire
Address of Record -
Susan Watson
Address of Record -
Alexis M. Yarbrough
Address of Record -
Sheauching Yu, Esquire
Address of Record -
Samantha Cibula, Esquire
Address of Record