08-002552
Daniel M. Sevick vs.
Department Of Health
Status: Closed
Recommended Order on Monday, February 16, 2009.
Recommended Order on Monday, February 16, 2009.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DANIEL M. SEVICK, )
12)
13Petitioner, )
15)
16vs. ) Case No. 08-2552
21)
22DEPARTMENT OF HEALTH, )
26)
27Respondent, )
29)
30and )
32)
33NO MOUNDS SYSTEMS OF FLORIDA, )
39INC., AND SAVE OUR SUWANNEE, )
45INC., )
47)
48Intervenors. )
50)
51RECOMMENDED ORDER
53This cause came on for formal proceeding and hearing before
63P. Michael Ruff, a duly-designated Administrative Law Judge of
72the Division of Administrative Hearings. The hearing was
80conducted in Tallahassee, Florida, on September 16 and 17, 2008.
90The appearances were as follows:
95APPEARANCES
96For Petitioner: Kenneth J. Plante, Esquire
102Tana D. Storey, Esquire
106Brewton Plante, P.A.
109225 South Adams Street, Suite 250
115Tallahassee, Florida 32301
118For Respondent: Mark Dunn, Esquire
123Lisa M. Raleigh, Esquire
127Office of the Attorney General
132The Capitol, Plaza Level 01
137Tallahassee, Florida 32399
140Lucy M. Schneider, Esquire
144Department of Health
1474052 Bald Cypress Way, Bin A02
153Tallahassee, Florida 32399
156For Intervenor: Save Our Suwannee, Inc.
162John M. Lockwood, Esquire
166Rutledge, Ecenia & Purnell, P.A.
171215 South Monroe Street, Suite 420
177Tallahassee, Florida 32301
180For Intervenor: No Mound Systems of Florida, Inc.
188Kenneth J. Plante, Esquire
192Tana D. Storey, Esquire
196Brewton Plante, P.A.
199225 South Adams Street, Suite 250
205Tallahassee, Florida 32301
208STATEMENT OF THE ISSUES :
213The issues to be resolved in this proceeding concern
222whether an application to construct and operate an on-site
231sewage treatment and disposal system (OSTDS), within the
239Suwannee River flood plain, meets the requirements of Section
248381.0065(4)(t), Florida Statutes (2007), and relevant Department
255of Health (Department) rules, and whether the department applied
264an un-adopted rule in denying the permit application.
272PRELIMINARY STATEMENT
274This cause arose concerning the denial of the Petitioner's
283application to construct an OSTDS on Lots 12 and 13 in the Log
296Landing Subdivision in Dixie County, Florida. Those lots are
305located adjacent to the Suwannee River. On July 23, 2007, a
316letter was issued by the Department denying the permit
325application based upon the following statement:
331Our engineer has reviewed your proposal.
337Based on the site elevation submitted (16.8
344feet) and the 10 year flood elevation (22
352feet) the proposal is not in compliance with
360381.0065(4)(t), Florida Statutes, and must
365be denied.
367Thereafter a timely Petition in Opposition to the denial
376was submitted by the Petitioner, seeking an administrative
384hearing. The Petition was filed August 16, 2007, and by Order
395of September 21, 2007, the Department assigned the Petitioner to
405an appointed presiding officer to conduct an informal
413administrative hearing.
415On January 4, 2008, the Petitioner filed an Amended
424Petition for Administrative Hearings, which included a challenge
432pursuant to Section 120.57(1), Florida Statutes (2007),
439concerning its position that the Department had followed and
448applied an un-adopted rule in the process of its denial of the
460permit application. On May 14, 2008, the Department entered an
470Order Granting the renewed Motion for Leave to file an Amended
481Petition and then referred the Amended Petition to the Division
491of Administrative Hearings. The matter was assigned to an
500administrative law judge and thence transferred to the
508undersigned administrative law judge, and this proceeding
515ensued.
516Prior to the hearing, Petitions to Intervene were filed by
526Save our Suwannee, Inc. (SOS), the Suwannee River Water
535Management District (the District), the Florida Department of
543Environmental Protection (DEP), and No Mounds Systems of
551Florida, Inc. (No Mound).
555Thereafter, an amended Petition to Intervene was filed by
564SOS. The Petitions to Intervene filed by SOS, DEP, and the
575District were denied based upon lack of standing. No Mound's
585Petition for Leave to Intervene was granted, based upon there
595being no objection thereto. SOS was granted leave to file a
606Second Amended Petition to Intervene to demonstrate how it and
616its members' substantial interests could be affected by the
625permit application and therefore why it and its members had
635standing.
636The Second Amended Petition to Intervene by SOS was filed
646pursuant to an Order denying the Amended Petition to Intervene
656by SOS, entered by the undersigned on the day prior to the
668hearing, because the Amended Petition was filed immediately
676prior to the hearing. This resulted in the Second Amended
686Petition to Intervene by SOS being timely filed on September 29,
6972008, after the conduct of the hearing. Because of this
707sequence of events concerning SOS's intervention, SOS was
715allowed to proffer its testimony at the hearing, as to its
726standing, and as to its position regarding the merits of the
737permit application, with the understanding by all parties that
746should the Second Amended Petition to Intervene be granted,
755(which it was) that the proffered evidence by SOS would become
766its actual evidence to be considered in support of its second
777amended intervention petition. This was done in order to avoid
787a bi-furcated hearing situation, with the inherent delay
795involved in allowing SOS to put on its case at a later time, if
809it were allowed to file a Second Amended Petition to Intervene,
820which it was. Thus the hearing, including SOS's full
829participation as an intervenor, under the above-described
836circumstances, was concluded on the above date.
843The cause came on for hearing as noticed. The Petitioner
853presented the testimony of Allen F. Hassett, Professional
861Engineer (PE), accepted as an expert in the field of Sanitary
872and Waste Water Engineering: Harry Wild; PE, who was accepted as
883an expert in onsite sewage treatment and disposal systems
892(OSTDS) design and environmental engineering; and Steven Sayko,
900Professional Geologist (PG), who was accepted as an expert in
910the field of Hydrogeology. The Petitioner's Exhibits 1 through
91916 were admitted into evidence.
924The Department presented the testimony of Gerald Briggs,
932Chief of the Bureau of Onsite Sewage Program; Samuel Averett;
942and Paul Booher, PE, of the Bureau of Onsite Sewage Programs, of
954the Department of Health. The Respondent's Exhibits 1 through
96312 and 15 through 17, as well as 20A, B, and C were admitted
977into evidence.
979The Respondent's Exhibits 1 through 10 and 15 through 17
989are maintenance reports which are routinely submitted to the
998Department on a quarterly basis and relate to various no mound
1009systems in Florida. These were objected to by the Petitioner on
1020relevancy and hearsay grounds. It was determined that they come
1030within the business records exception to the hearsay rule and
1040the hearsay objection was overruled. They were determined to be
1050relevant, subject to briefing on whether the prejudice out-
1059weighed the relevance. It is determined that these exhibits are
1069relevant and they are admitted. They will be weighed and
1079considered in terms of their remoteness in time from the design
1090and installation of the proposed system, and in terms of any
1101innovations which have been brought forward as to no mound
1111systems since the time of a particular maintenance report
1120regarding a no mound system in these exhibits. Other factors
1130such as location and elevation, which render the systems
1139addressed by some of these maintenance reports to be different
1149in character, construction and operational parameters from the
1157system proposed, are deemed to detract from the substance and
1167materiality of such reports.
1171Upon conclusion of the proceeding, the parties had the
1180evidence transcribed and elected to submit proposed recommended
1188orders. The Proposed Recommended Orders were timely submitted
1196after the Order was entered on the Second Amended Petition for
1207Intervention by SOS, which closed the record. Proposed
1215Recommended Orders were submitted by the Petitioner, the
1223Respondent, and by the Intervenors. All have been considered in
1233the rendition of this Recommended Order.
1239FINDINGS OF FACT
12421. Daniel Sevick is the owner of two lots, consisting of a
1254total of 1.24 acres, within the flood plain of the Suwannee
1265River. The lots are lots 12 and 13 in "Log Landing
1276Subdivision." The Petitioner applied for a construction permit
1284for the installation of an OSTDS on that property. The
1294application for the permit was submitted to the Dixie County
1304Health Department, which forwarded it to the Department of
1313Health for review, in accordance with Section 381.0065(4)(j),
1321Florida Statutes (2007). The Respondent, Department of Health,
1329(Department) is an Agency of the State of Florida charged with
1340implementing and enforcing the provisions of Chapter 381,
1348Florida Statutes, and Florida Administrative Code Chapter 64E.
1356Among its duties are the review of and issuance of permits for
1368construction of OSTDS.
13712. The permit application was reviewed by the Department
1380and was subsequently denied, based upon the following reasoning
1389contained in the denial letters:
1394Our engineer has reviewed your proposal.
1400Based on the site elevation submitted (16.8
1407feet) and the 10 year elevation (22 feet)
1415the proposal is not in compliance with
1422381.0065(4)(t), Florida Statutes, and must
1427be denied.
14293. Certain of the facts have been stipulated to by the
1440parties. The parties thus agree that the 10-year flood
1449elevation for the property is 22 feet; the site elevation of the
1461property is 16.8 feet and the two-year flood elevation for the
1472property is 16.00 feet. The bottom of the proposed drainfield
1482is at an elevation of 14.30 feet. The Petitioner thus proposes
1493to install the OSTDS system with the bottom of the drainfield
15041.70 feet below the two-year flood elevation. The proposed
1513system consists of a conventional septic tank system connected
1522to a "no mound" drainfield system.
1528No Mound System
15314. The no mound drainfield system is an innovative
1540drainfield system. No Mound was granted a permit for its design
1551as an "innovative system" by the Department, initially
1559authorizing installation of five systems in Florida, starting on
1568December 23, 1998. An "innovative system" is defined as an
"1578onsite sewage treatment and disposal system that, in whole or
1588in part, employs materials, devices, or techniques that are
1597novel or unique and that have not been successfully field tested
1608under sound scientific and engineering principles under climatic
1616and soil conditions found in this state." See §
1625381.0065(4)(2)(g), Fla. Stat (2007). Innovative systems, by
1632definition are considered to be "performance-based systems"
1639which have additional requirements placed on them depending on
1648the performance level of the effluent treatment.
16555. The design of the OSTDS system submitted with the
1665permit application included several changes intended for this
1673particular property, based upon discussions between the
1680Petitioner's representatives and the Department. The changes
1687include relocation of the OSTDS and drainfield to the highest
1697elevation of the property; addition of a solar-recharge battery
1706alternative power supply; the obtaining of additional
1713information with regard to soil borings; and the performance of
1723an evaluation to confirm the capacity of the soil anchors in
1734saturated soil. The OSTDS, including the no mound drainfield,
1743was designed by Harry Wild, PE, specifically for the
1752Petitioner's property. The proposed OSTDS is considered by the
1761Department to be an "engineer-designed" system.
17676. Over approximately the last 10 years No Mound has been
1778issued innovative permits authorizing the installation of
1785approximately 250 no mound drainfield systems.
17917. The no mound system is an innovative system which does
1802not employ a conventional drainfield. Instead, based upon
1810principles of physics and engineering, the drainfield system is
1819designed to be installed underground, with air pumped into the
1829system to depress the groundwater elevation or "water table," so
1839as to provide the required separation or distance between the
1849absorption surface of the drainfield (bottom of the drainfield)
1858and the groundwater. In Florida the separation required is 24
1868inches. The drainfield system is designed to retain air pumped
1878into it, for depression of the groundwater level, by being
1888covered with pieces of geo-fabric and a p.v.c. membrane designed
1898to retain air within the system under a certain level of
1909pressure. The air pressure is designed to depress the water
1919level of groundwater directly beneath the area of the
1928drainfield, much like the principle of a "diving bell."
19378. The drainfield system would be covered with two pieces
1947of geo-fabric on either side of a 30 mill. p.v.c. membrane, the
1959same material used as a liner for hazardous waste landfills.
1969The geo-fabric material protects the p.v.c. membrane from damage
1978or puncture during construction. Once in operation the membrane
1987is unlikely to tear under normal conditions, unless through
1996intentional puncture with an extremely sharp implement or
2004through some catastrophic event, such as a large tree falling on
2015the surface above the membrane.
20209. The membrane is held in position by a patented ballast
2031and anchor system. The ballast material consists of pre-
2040stressed concrete beams, spanning the width of the drainfield.
2049At each end of each beam is a soil anchor.
205910. The 20 pre-stressed ballast beams are held in place
2069with 40 helically shaped screw anchors, which screw into the
2079soil. Each anchor is intended to withstand 5,000 pounds of
2090upward force. The screw anchors are designed to hold the
2100concrete beams in place in saturated soil. The soil anchors are
2111threaded with a washer and nut on both the top and the bottom of
2125the concrete beam which prevents the beam from moving
2134vertically, downward or upward, so that the beam can resist any
2145uplifting force.
214711. Air is pumped into this system by a continuous air
2158pump which would be wired into the power system of the residence
2170to be on the property. There would also be an emergency power
2182supply. The air pressure inside the system would vary in
2192response to the level of water outside the system whether
2202groundwater or surface water. As the water outside the system
2212rises or subsides, the water inside and beneath the system is
2223supposed to remain lowered, as the pressure inside the system is
2234designed to increase or decrease. The Petitioner maintains that
2243the ballast system is designed to contain the pressure (air
2253pressure) which would be required to continue to suppress any
2263groundwater or flood water associated with a ten-year flood
2272event.
227312. The system has an "air bleed," which is intended to
2284maintain aerobic conditions in the drainfield. If surface
2292waters overflow the top of the drainfield system in a flood
2303event, the air bleed system is designed to continue functioning.
2313The air would enter the soil beneath the ground surface and
2324bubble up through any water above the ground surface. If both
2335the primary and backup power supplies should fail, the
2344Petitioner maintains that the air bleed would "shut off" so that
2355no air would escape from the system and thus maintain the
2366pressure within the system, much like a diving bell. This
2376characteristic is designed to maintain the separation between
2384the groundwater surface and the bottom of the drainfield in the
2395event of a power failure.
240013. The Department has interpreted the operative statute,
2408Section 381.0065(4)(t), Florida Statutes (2007), as providing
2415that the absorption surface of a drainfield for any OSTDS system
2426cannot lie below the 10-year flood elevation, if it is located
2437within the floodways of the Suwannee or Aucilla Rivers, unless
2447the system meets all the exceptions contained in Section
2456381.0065(4)(t)1.a.b. and c., Florida Statutes. One of these
2464exceptions requires that the bottom of the drainfield, the
2473absorption surface, be at least 36 inches above the two-year
2483flood elevation for the site. The two-year flood elevation at
2493the subject site is 16 feet. The proposed installation would
2503have the bottom of the drainfield or absorption surface located
25131.70 feet below that two-year flood elevation, thus not
2522complying with that exception.
252614. The applicant's system is not in compliance with the
2536portion of paragraph (c), referenced above as an exception,
2545concerning a system approved by the county health department,
2554pursuant to department rule, which is "other than" a system
2564using "alternative drainfield materials." This system would
2571apparently use so-called "alternative drainfield materials."
257715. Innovative systems are those which represent new
2585technology that has not been completely field-tested in Florida.
2594The Petitioner has applied for the permit as an innovative
2604permit application, which contains a requirement that the system
2613be replaced with an alternative system in case it fails within a
2625five-year test period.
262816. No mound systems are site specific, with each one
2638being specifically designed for a particular property with its
2647unique characteristics. There are approximately 50 no mound
2655systems approved, permitted and operating in Florida at the
2664present time. The evidence does not reflect which, if any, of
2675those systems are installed below flood elevations. The
2683drainfield portion of such a system works in the same way as a
2696conventional drainfield, that is, the soil and piping which lies
2706below the membrane. The membrane system is the unique
2715characteristic of the no mound system. Because of the membrane
2725and ballasting system designed to retain air pressure over and
2735in contact with the drainfield absorption surface, the system is
2745different and more complex than the standard drainfield system,
2754although it treats affluent in the same way.
276217. Two significant problems arose with the installation
2770of the first five innovative permit, no mound systems. The
2780testimony of Sam Averett, who is a septic system contractor,
2790described an installation of a no mound system on his own
2801property in 1999. The system was installed in accordance with
2811Mr. Hassett's specifications and recommendations, and he was
2819present during the installation. Mr. Hassett testified in
2827support of the petition in this case as an engineering expert.
2838Within a few days or weeks the Averett system developed a
2849problem. Apparently, with a substantial rain event, the system
"2858floated" that is, the air pressure contained within the
2867membrane rose to the surface of the ground, similar to a
"2878bubble." This would have amounted to a failure to maintain the
2889air pressure necessary to ensure that a 24-inch separation
2898between the absorption surface of the drainfield and the
2907groundwater table elevation was maintained. That system was re-
2916designed and a different ballasting system or buoyancy package
2925was used, involving the use of "railroad iron" (rails), and
2935plywood spanning the drainfield in order to hold the membrane
2945beneath in place, with the whole arrangement being recovered
2954with dirt. Thereafter, on January 1, 2003, after a substantial
2964rainfall event, the system floated out of the ground once again.
2975After that second failure of the Averett system, Mr. Averett
2985installed a "hoot" system, which involves a "drip irrigation"
2994drainfield installation, with the delivery piping and the
3002drainfield being much closer to the ground surface or within six
3013inches of the surface.
301718. The system described by Jack Murray in his testimony
3027was also one of the original five systems installed in Florida
3038by No Mound, Inc. That system was designed to maintain a 30-
3050inch separation between the absorption surface of the drainfield
3059(bottom of drainfield) and the groundwater elevation or water
3068table. According to Mr. Murray it never maintained that
3077separation. He was aware of the lack of a 30-inch separation
3088being maintained because of the onsite monitors installed with
3097the system. He described the actual separation which the system
3107provided as being only .9 feet. The onsite monitors by which he
3119was able to observe the actual separation failed after about two
3130years of operation. He brought the separation issue to the
3140attention of the contractor or representative of No Mound, which
3150patented the system and oversaw the installation. According to
3159Mr. Murray, however, they never satisfactorily addressed the
3167problem. When the air pump failed, after approximately two
3176years of operation, he called the manufacturer of the air pump
3187and was informed that the air pump had been the incorrect type
3199or size for the no mound system which he had installed.
321019. Although these two referenced problems concerning the
3218Murray system and the Averett system represent two of the first
3229five innovative no mound systems installed in Florida, the
3238problems associated therewith may have been corrected since,
3246because each system installed at a given site is specifically
3256and uniquely designed by an engineer for that site and its
3267physical, hydrologic and operating circumstances. Thus, the
3274referenced problems involving buoyancy or "floating-up" of the
3282drainfield membrane system and the failure to maintain adequate
3291pressure so as to achieve the legally-mandated 24-inch
3299differential between groundwater elevation and the bottom of the
3308absorption surface, may not be construed to be direct predictors
3318of what will occur with the installation of the Sevick system.
3329The problems do point up, however, the fact that the air
3340pressure maintained at different groundwater levels in the
3348system is a critical component of the system's function and also
3359that the ballasting system and design is critical in order to
3370maintain the integrity of the membrane system or air chamber
3380overlying the drainfield surface, at different water levels and
3389conditions. This is a particular concern with regard to flood
3399conditions.
340020. It also true that the proposed air pressure to be
3411maintained in the system at issue, the Sevick system, would be
3422five pounds per square inch. Earlier systems, possibly
3430including the Murray system, maintained a pressure of two pounds
3440per square inch.
344321. However, aside from the rather conclusory testimony of
3452the Petitioner's expert witnesses, who opined generally that the
3461air pressure and the integrity of the membrane system and
3471ballast system would be adequate to maintain the legally-
3480mandated 24-inch differential of unsaturated soil below the
3488absorption surface, there was no definitive evidential showing
3496of what air pressure would actually be necessary to perform that
3507function adequately under all conditions. This is particularly
3515problematic under conditions of flooding, since the proposed
3523drainfield would be beneath both the 10-year flood elevation and
3533the two-year flood elevation. Although there was testimony
3541which indicated that the air pressures would vary, would
3550increase or decrease depending upon the water levels beneath the
3560drainfield and outside of the membrane, there was no definitive
3570showing in the evidence as to what pressures under those varying
3581water level conditions would still enable the 24-inch
3589differential to be maintained. Under the Department's
3596interpretation of its statutes and rules, a 24-inch differential
3605is deemed adequate and necessary for treatment of the sewage
3615effluent entering the drainfield.
361922. The electric power necessary for operation of the air
3629pump which pressurizes the system would be derived from
3638connection with the residence to be constructed on the lots.
3648The emergency power system would be designed to accommodate
3657situations where there is a power outage, for instance in a
3668storm situation. The alternative system would be dependent upon
3677solar-rechargeable battery power. If the air pump ceased
3685operation due to a power outage and the backup system was not
3697adequate, or adequately charged, to operate the pump
3705sufficiently or for a sufficient period of time to maintain the
3716required air pressure, then the 24-inch differential might not
3725be maintained. The evidence does not reveal a practical way to
3736monitor the air inflow or the air pressure condition inside the
3747membrane in the event of a power outage. The Petitioner's
3757witnesses maintained that if there was a power outage the air
3768bleed device would close down, thus maintaining the required air
3778pressure (akin to a diving bell circumstance). There was no
3788persuasive evidence, however, to show what air pressure would
3797thus be statically maintained and whether it would maintain the
3807required 24-inch separation.
381023. Harry Wild was the design engineer who designed the no
3821mound system for the Sevick property. Mr. Wild, however, was
3831unaware, apparently, that Dr. Jeffrey Evans, a geotechnical
3839expert and expert in the design of helical anchors for the
3850ballast system for the Sevick property, had recommended that at
3860least one boring be made for each site or each of the two lots
3874to a depth of 20 feet. This was recommended in order to verify
3887what the sub-surface conditions were, so that the conditions
3896assumed in the system design could be verified. Mr. Wild
3906testified that he only took borings to a depth of 10 feet.
3918Mr. Hassett on the other hand testified that he thought the
3929borings had only been done to six feet. In fact, the site
3941evaluations submitted to the Department demonstrated soil boring
3949had been performed to a depth of six feet below ground surface,
3961and the cross-sectional drawing indicates that the anchors,
3969designed to hold down the beams and the membrane, would only
3980begin approximately four feet below the ground surface.
398824. Thus, even though Mr. Wild was the expert designer of
3999the No mound system for the Sevick project, he was unaware of
4011whether the ballast system was a new type of system which had
4023been specifically designed for that property. He did
4031acknowledge that it was the first time he had employed that type
4043of ballast system.
404625. In spite of the higher operating pressure, five PSI
4056versus two PSI, to be maintained in the Sevick no mound system
4068over that normally maintained in previous no mound systems,
4077Mr. Wild did not perform calculations or evaluations as to the
4088beam strength and design requirements of the new ballast system.
4098He did not perform calculations or evaluations that addressed
4107the issue of membrane deflection requirements, which relates to
4116how much the membrane would move upward under various pressures.
4126This in turn could relate to how much downward pressure must be
4138exerted by the anchoring system, to counteract the buoyancy of
4148the membrane bulging upward under different pressure
4155circumstances, associated with different water levels.
416126. Mr. Hassett did not know what membrane deflection was
4171acceptable for the Sevick no mound system other than "a fair
4182amount" which he acknowledged varied "depending on the geo-
4191synthetic or the geo-grid that was specified for that particular
4201project." It is understandable that this is an innovative
4210system which requires certain revisions at times before it is
4220installed, or during the course of installation, to adapt its
4230design to the particular site. However, the evidence presented
4239at hearing, as shown by Mr. Hassett's testimony, and Mr. Wild's
4250as well, in this regard, is somewhat indefinite and does not
4261show a substantial likelihood that the membrane and concrete
4270beam and anchor ballasting system proposed will work as planned
4280from a structure and strength standpoint. As Mr. Hassett
4289testified "they will be tested before installation."
429627. As shown by Mr. Wild's testimony, the soil of the
4307Petitioner's lots is composed of fine sand at the installation
4317site. There is no evidence concerning any erosion study or
4327concerning what the erosion experience might be in a flooding
4337situation, in order to determine the effect on the helical
4347anchors and ballasting system in the event of floods of varying
4358severities, including a 10-year flood.
436328. Dr. Evans established in his deposition testimony that
4372the helical anchors get their resistance to upward force from
4382the sheer strength of the soil, which is a frictional value
4393combined with the effective stress on the soil. If a certain
4404amount of soil is eroded away, then the holding capacity of the
4416anchors is correspondingly reduced. Dr. Evans, however, assumed
4424that the applied load per anchor was 5,000 pounds, with the
4436anchor handling 5,000 pounds of upward force if it was 10 feet
4449underground. Therefore, the designers of the system would need
4458to assure that the anchors are 10 feet underground and that the
4470applied load is 5,000 pounds, according to Dr. Evan's testimony.
4481He opined that if erosion of varying amounts occurred that could
4492affect the anchors' holding capacity.
449729. In fact, the evidence shows that the anchors or the
4508top of the anchors may only be proposed to be installed four
4520feet below the surface. Therefore, the evidence does not
4529clearly establish that the beam/anchor system is adequate to
4538maintain the stability of the drainfield membrane system in the
4548event of a flooding situation.
455330. Gerald Briggs testified on behalf of the Department.
4562He described the growing concern that nitrogen levels in the
4572effluent of OSTDS systems represent, in terms of potential
4581environmental degradation of ground or surface waters, which the
4590Department is charged with addressing by the statutory authority
4599cited below. The no mound system, like any conventional OSTDS
4609system, has no specific provision that would treat or reduce
4619nitrogen levels in the effluent from the system. The 24-inch
4629separation between the absorption surface of the drainfield and
4638the groundwater elevation is designed to be unsaturated soil,
4647which provides treatment of only a primary nature for
4656essentially the public health/pathogenic components of the OSTDS
4664system effluent (i.e. sanitary treatment).
466931. Although there is not such a monitoring requirement,
4678the Department has requested data from the Petitioner regarding
4687the quality of the effluent that would leave the system. If the
4699system were ever installed, it should be done with the condition
4710that effluent sampling and testing of the effluent should be
4720performed, in order to ascertain that the system operates
4729properly, in terms of public health and environmental
4737degradation, on an ongoing basis.
474232. The Petitioner's witnesses, Mr. Wild and Mr. Sayko,
4751acknowledged that the system proposed is not infallible and
4760there are certain risks posed by the installation. For
4769instance, if a pump was broken then the water level would start
4781to rise inside the no mound system, according to Mr. Sayko's
4792testimony.
479333. Moreover, the absorption surface in the drainfield as
4802proposed, would likely be "subject to flooding" in a situation
4812of power outages and erosion during a flood event. It must be
4824remembered that the ground surface is some five feet below the
483510-year flood elevation at the installation site and the
4844absorption surface or bottom of the drainfield is over seven
4854feet below the 10-year flood elevation. Thus, in the
4863circumstance of power outages or flood-caused erosion, the
4871absorption surface of the proposed drainfield could be "subject
4880to flooding."
488234. The Department denied the subject permit application
4890because the site elevation is 16.8 feet and the 10-year flood
4901elevation at the site is 22 feet. Thus, the proposal was to
4913install the absorption surface below the 10-year flood elevation
4922(more than seven feet below it). In denying the requested
4932permit the Department denied it based upon its interpretation of
4942the subject statute, Section 381.0065(4)(t)(1), Florida Statutes
4949(2007). It did not actually employ an un-adopted rule or
"4959agency statement of general applicability" in making this
4967interpretation. Rather, it interpreted the statute, applying it
4975to the particular facts of the permit application and the
4985situation prevailing at the proposed installation site. It was
4994not applying an interpretation or policy statement of general
5003applicability enforced throughout its jurisdiction, or
5009throughout the flood plain area of the Suwannee and Aucilla
5019Rivers, but rather was applying the statutory language and its
5029interpretation of it to the particular site and circumstances of
5039the proposed system and its contemplated operation.
504635. A variance from the above-referenced statutory
5053requirements and related rules is not at issue in this case
5064because the Petitioner has not sought a variance. Although
5073variances have been granted in the Suwannee River flood plain
5083area, in accordance with Section 381.0065(4)(h), Florida
5090Statutes (2007), the grant of such variances has usually carried
5100the concomitant requirement of more advanced treatment of the
5109effluent in the system to be installed, as allowed by the
5120granted variance. Thus, an aerobic treatment unit (ATU) or
5129performance-based septic treatment system, such as an advanced
5137secondary treatment system (AST), as well as the use of drip
5148drainfields, such as the hoot system, have been required in
5158accordance with the statute.
516236. An ATU introduces air into the treatment unit in order
5173to enhance the treatment and generally employ filters as well,
5183according to witness Briggs. An AST type system reduces the
5193biochemical oxygen demand (BOD), total suspended solids, as well
5202as treating the nitrogen and phosphorus contents of the
5211effluent. Historically, the Department has only approved
5218variances in the Suwannee or Aucilla River flood plains for
5228vacant lots with the use of ATU or AST type systems.
523937. A drip drainfield reduces the required height of the
5249drainfield by some 12 inches because it is only buried six
5260inches into the soil. This is done because it is designed to be
5273buried in the shallow root zone of trees and plants which allow
5285trees and plants to uptake the nutrients in the effluent water
5296and thus prevent them from being deposited in the ground or
5307surface waters. In the Suwannee River basin area, most of the
5318variances granted by the Department have required such drip
5327drainfield systems.
532938. One of the statutory considerations for granting of a
5339variance is that the Petitioner for a variance should not have
5350created the hardship involved, resulting in the need for the
5360variance. The Department maintains that the Petitioner,
5367Mr. Sevick, has created the hardship in this case by purchasing
5378the lot knowing of the restrictions on OSTDS systems that were
5389legally prevailing. The evidence, however, does not really
5397establish that the Petitioner intentionally created the hardship
5405by purchasing a lot knowing of all the restrictions that were in
5417place and their effects. One can infer, for instance, that he
5428was aware of advertisements by No Mounds, that lots in the
5439Suwannee River basin or flood plain area could be developed by
5450using its OSTDS system without even necessitating the use of
5460fill. The Department's evidence simply does not establish that
5469the Petitioner, Mr. Sevick, intended creating the hardship, on
5478his own volition, by purchasing the lot with knowledge that the
5489specific restrictions were in place, from a legal standpoint.
5498Thus it was not proven that the Petitioner is unable to
5509establish a hardship for purposes of seeking a variance pursuant
5519to Section 381.0065(4)(h), Florida Statutes (2007), on the basis
5528that the Petitioner created the hardship.
553439. As established by witness Briggs, nitrogen and
5542phosphorus elements of OSTDS effluents are of growing concern
5551for ground and surface waters in Florida. Nitrogen and
5560phosphorus enhance algae growth in surface waters, which can
5569lead to reduced dissolved oxygen content and other factors
5578harmful to fish and wildlife. There is thus a deleterious
5588environmental impact from nitrogen and phosphorus levels in
5596surface waters or groundwaters, in addition to the pathogens
5605which can characterize effluent from OSTDS systems, related to
5614human waste.
561640. Advanced septic systems such as ATUs or ASTs have been
5627required in the grant of variance-based septic system permits in
5637flood plains of the rivers because of the potential of their
5648being flooded and because of the locations of the systems. The
5659Department, in consideration of its statutory charge, has sought
5668to seek as much treatment as possible for the effluent, in such
5680situations, in order to prevent significant degradation of
5688ground or surface water. A no mound system is a drainfield
5699dispersal system, so it itself poses no additional treatment
5708capability than does a conventional OSTDS system, as established
5717by both witnesses Wild and Briggs.
5723CONCLUSIONS OF LAW
572641. The Division of Administrative Hearings has
5733jurisdiction of the subject matter of and the parties to this
5744proceeding. §§ 120.569 and 120.57(1), Fla. Stat. (2008).
575242. The Department has the authority to issue permits
5761governing installation and operation of OSTDS systems. The
5769intent of the Legislature to that effect is set out in Section
5781381.0065(1), Florida Statutes (2007), concerning permitting.
5787Therein it is provided:
57911. LEGISLATIVE INTENT.-It is the intent of
5798the legislature that where a publicly owned
5805or investor-owned sewerage system is not
5811available, the department shall issue
5816permits for the construction, installation,
5821modification, abandonment, or repair for
5826onsite sewage treatment and disposal systems
5832under conditions as described in this
5838section and rules adopted under this
5844section. It is further the intent of the
5852legislature that the installation and use of
5859onsite sewage treatment and disposal systems
5865not adversely affect the public health or
5872significantly degrade the groundwater or
5877surface water.
5879The following requirements are imposed by Section
5886381.0065(4)(t), Florida Statutes (2007), for installation of
5893OSTDS in the floodways of the Suwannee and Aucilla Rivers:
5903(t) Notwithstanding the provisions of sub-
5909paragraph (g)1., onsite sewage treatment and
5915disposal systems located in floodways of the
5922Suwannee and Aucilla Rivers must adhere to
5929the following requirements:
5932(1) The absorption surface of the
5938drainfield shall not be subject to flooding
5945based on 10-year flood elevations.
5950Provided, however, for lots or parcels
5956created by the subdivision of land in
5963accordance with applicable local government
5968regulations prior to January 17, 1990, if an
5976applicant cannot construct a drainfield
5981system with the absorption surface of the
5988drainfield at an elevation equal to or above
599610-year flood elevation , the department
6001shall issue a permit for an onsite sewage
6009treatment and disposal system within the 10-
6016year flood plain of rivers, streams, and
6023other bodies of flowing water if all of the
6032following criteria are met:
6036a. The lot is at least one-half acre in
6045size;
6046b. The bottom of drainfield is at least 36
6055inches above the 2-year flood elevation; and
6062c. The applicant installs either:
6067A waterless, incinerating, or organic
6072waste composting toilet and a gray water
6079system and drainfield in accordance with
6085department rules; an aerobic treatment unit
6091and drainfield in accordance with department
6097rules; a system approved by the state health
6105office that is capable of reducing effluent
6112nitrate by at least 50 percent; or a system
6121approved by the county health department
6127pursuant to department rule other than a
6134system using alternative drainfield
6138materials. . . . (Emphasis supplied).
614443. The purpose of Subsection (4)(t) is to provide
6153additional requirements for OSTDS located in the floodways of
6162the Suwannee and Aucilla Rivers. These provisions show a
6171particular legislative concern for these environmentally
6177important areas, hence the legislatively-imposed unique
6183requirements for these regions.
618744. The stated legislative intent provides that when
6195attempting to place OSTDS in these floodways, "[T]he absorption
6204surface of the drainfield shall not be subject to flooding based
6215on 10-year flood elevations ." If one reads the entire text of
6227Section 381.0065(4)(t)1., a consistency through the entire text
6235of that paragraph is revealed which shows a legislative intent
6245centered on the actual placement of the bottom of a drainfield
6256system in relation to the 10-year flood elevation. It is not a
6268subjective concern that the absorption surface of such a
6277drainfield not be "subject to flooding," depending upon the type
6287of innovative, engineered system which might be capable of being
6297installed, which would, if operating correctly, isolate the
6305absorption surface itself from flood waters.
631145. It is true that the first sentence of that
6321subparagraph, cited last-above, states that the absorption
6328surface "shall not be subject to flooding based on 10-year flood
6339elevations," rather than openly stating that the 10-year flood
6348elevation is a mandatory minimum elevation. However, when the
6357paragraph is read in its entirety, it can be seen that the
6369second sentence of (4)(t)1., provides a legislative explanation
6377of what "subject to flooding" actually means. In other words,
6387if one wishes to install a OSTDS in the flood zone of either
6400river, the drainfield must not be "subject to flooding," but if
6411one owns a lot which meets the exception language beginning in
6422the second sentence of that paragraph and the "applicant cannot
6432construct a drainfield system with the absorption surface of the
6442drainfield at an elevation equal to or above the 10-year flood
6453elevation," the exceptions beginning in that second sentence can
6462be applicable to that particular situation. The point is, if
6472one reads Section 381.0065(4)(t)1., Florida Statutes (2007), in
6480its entirety and in complete context, it is clear that the
6491legislature meant that "subject to flooding" meant that one does
6501not place the bottom of the drainfield below the 10-year flood
6512elevation in the Suwannee and Aucilla River flood plains (unless
6522the exceptions are met). The system proposed by the Petitioner
6532is a closed drainfield system designed to withstand the flood
6542waters by isolation of the drainfield surface through the use of
6553a maintained positive air pressure. The Petitioner thus
6561contends that the above-referenced requirement regarding the
6568absorption surface not being subject to flooding is met by the
6579particular devices installed, with regard to the drainfield,
6587referenced in the Findings of Fact.
659346. The Petitioner contends that Section 381.0065, Florida
6601Statutes (2007), contemplates the use and installation of
6609innovative systems, such as the No mound system and, because it
6620is a closed system, and is designed to withstand the pressure of
6632flood waters, that the absorption surface will not be subject to
6643flood waters as contemplated by the statute. However, the
6652purpose of the above-cited subsection, in relation to the
6661remainder of Section 381.0065, Florida Statutes, which provides
6669the framework for OSTDS regulation, simply provides additional
6677requirements for OSTDS systems to be located within the 10-year
6687flood elevation of the Suwannee and Aucilla River basins,
6696without regard to the type of system proposed.
670447. Section 381.0065 addresses permitting, siting,
6710construction, installation, inspection, operation, maintenance,
6715modification, repair and abandonment of onsite systems. It also
6724provides for variances, special consideration for sensitive
6731areas such as the Suwannee and Aucilla River flood zones,
6741Department evaluation of onsite system additives, and the
6749development and permitting of alternative treatment units and
6757innovative system designs.
676048. While that section contemplates innovation, design
6767provisions for engineer-designed, performance-based systems, are
6773found in Section 381.0065(4)(j), and innovative systems in
6781Section 381.0065(3)(e), not in Section 381.0065(4)(t).
678749. The No Mound Corporation has already been issued an
6797innovative permit, to install 250 systems in Florida. When
6806installing an OSTDS, No Mound must still meet all remaining
6816requirements of Section 381.0065. If the absorption surface of
6825a drainfield for any OSTDS, without regard to the type of
6836system, is at an elevation less than the 10-year flood
6846elevation, pursuant to Section 381.0065(4)(t)1., a. through c.,
6854all three of the statutorily-enumerated exceptions must be met,
6863and engineering design is not one of them. If all of the
6875exceptions are not met, then no OSTDS system, including the no
6886mound system, is allowed to be constructed in the floodway of
6897the Suwannee River.
690050. In enacting the Section 381.0065(4)(t), Florida
6907Statutes (2007), the legislature was not concerned with whether
6916the engineering design or innovative devices for a particular
6925type of drainfield system would render it flood proof. Rather,
6935it was concerned with the location of the drainfield, deeming
6945it, in effect, to be "subject to flooding" if it was located
6957beneath the 10-year flood elevation.
696251. It is well-settled that legislative intent is the
6971principal concept regarding statutory construction. Reynolds v.
6978State of Florida , 842 So. 2d 46, 49 (Fla. 2003); McGhee v.
6990State , 847 So. 2d 498, 501 (Fla. 4th DCA 2003). Legislative
7001intent derives primarily from statutory language itself, which
7009is the most reliable and authoritative expression of such
7018intent. Reynolds , 842 So. 2d at 49; McGhee , 847 So. 2d at 501.
703152. The statutory language must be read and considered in
7041its entirety when making an interpretation. Jones v. ETS of New
7052Orleans, Inc. , 793 So. 2d 912, 915 (Fla. 2001) (". . .
7065[S]tatutory phrases are not to be read in isolation, but rather
7076within the context of the entire section." Acosta v. Richter ,
7086671 So. 2d 149, 154 (Fla. 1996)). Once legislative intent is
7097ascertained, all parts of the statute must be read conjunctively
7107to arrive at a consistent complete context. Statutory phrases
7116should be considered with a view to the entire context of the
7128section from which they come. Borden v. Est-European Insurance
7137Company , 921 So. 2d 587, 595 (Fla. 2006); Parker v. State , 874
7149So. 2d 683, 684 (Fla. 4th DCA 2004). It is clear, when reading
7162and considering Section 381.0065(4)(t)1., Florida Statutes, in
7169its entire context, that the legislature was really concerned
7178with avoiding placement of the bottom of a drainfield below the
718910-year flood elevation.
719253. The Department is the state agency charged with
7201administering the provisions of Section 381.0065, Florida
7208Statutes (2007). The construction or interpretation of a
7216statute by an agency which it is given power to administer it
7228will generally not be overturned unless clearly erroneous.
7236Laborer's International Union of North America, Local 478 v.
7245Burroughs , 541 So. 2d 1160, 1162 (Fla. 1989); Pan American World
7256Airways v. Florida Public Service Commission , 427 So. 2d 716,
7266719 (Fla. 1983); Wallace Corporation v. City of Miami Beach , 793
7277So. 2d 1134, 1140 (Fla. 1st DCA 2001). See also Cenac v. State
7290Board of Accountancy , 399 So. 2d 1013 (Fla. 1st DCA 1981) (an
7302agency's construction of statutes within its regulatory
7309jurisdiction is generally given deference because of the
7317agency's familiarity with the statutory scheme and its expertise
7326in administering the field being regulated); Roberts v. Ayers ,
7335380 So. 2d 1057 (Fla. 1st DCA 1979). The agency's construction
7346of a statute need not be the only possible interpretation or
7357even the most desirable one, but must only be within the range
7369of possible statutory construction. Orange Park Kennel Club,
7377Inc., v. Department of Business and Professional Regulation , 644
7386So. 2d 574, 576 (Fla. 1st DCA 1994); Florida League of Cities v.
7399Department of Environmental Regulation , 603 So. 2d 1363, 1369
7408(Fla. 1st DCA 1992).
741254. If one considers Section 381.0065(4)(t), Florida
7419Statutes (2007), in its entirety, along with the remainder of
7429that statutory section, it becomes apparent that the legislature
7438was concerned with creating special consideration for the area
7447of the floodways of the Suwannee and Aucilla Rivers. It
7457intended to ensure that drainfields not be subject to flooding,
7467by requiring construction of them with an absorption surface at
7477an elevation equal to or above the 10-year flood elevation.
7487Design standards are established elsewhere in Section 381.0065,
7495Florida Statutes (2007). Once a permit is granted for an
7505innovative design system such as the no mound system, that
7515system must still meet all other requirements of Section
7524381.0065, including the provisions of paragraph (4)(t).
753155. In summary, the Department is the agency with the
7541authority as well as expertise to administer Section 381.0065,
7550Florida Statutes. Its interpretation of Section 381.0065(4)(t),
7557Florida Statutes, is the more reasonable interpretation of those
7566proposed and it is not clearly erroneous. Its interpretation
7575reflects the most likely rationale and context of the
7584legislature's intent in the enactment of the subject provision.
7593Its interpretation is deemed correct.
759856. Even if that were not the case, the above Findings of
7610Fact reveal a number of problems or potential problems with the
7621no mound system. There are several unanswered questions as to
7631the installation and operation of the no mound system to be
7642placed on the Sevick property. The primary concern is the
7652question of how effective the anchoring system would be, given
7662that some expert testimony and evidence seemed to rely on the
7673anchors being at a 10-foot depth below the ground surface, while
7684the design and apparent installation plans would indicate that
7693they would actually begin four feet below the ground surface.
7703The unanswered questions also include what might happen if
7712flood-caused erosion removed soil relied upon to exert a
7721sufficient downward force on the anchoring system to hold the
7731membrane in place. Thus, there is the potential that, through
7741flood-caused erosion, the membrane, and the air pressure that it
7751is supposed to maintain, might be displaced, rendering the
7760drainfield absorption surface subject to flooding in such an
7769event.
777057. Moreover, the evidence supportive of the above
7778Findings of Fact does not clearly establish that, in the event
7789of a power failure, even taking into account the back-up battery
7800power system, a sufficient air pressure could be maintained
7809beneath the membrane of the drainfield system so as to exclude
7820flood waters and to maintain the required 24-inch separation
7829between the bottom of the drainfield system and the groundwater
7839elevation. Thus, even if the Petitioner's interpretation of the
7848referenced statute regarding the meaning of "subject to
7856flooding" is correct, the preponderant evidence, supportive of
7864the above Findings of Fact, shows that the drainfield's
7873absorptive surface could be subject to flooding, in a flood
7883event.
7884Un-adopted Rule Issue
788758. The Petitioner contends that the Department applied an
7896un-adopted rule in its review of the permit application. The
7906Petitioner maintains that the Department expanded the definition
7914of the term "flooding" contained in Florida Administrative Code
7923Rule 64E-6.002(25) so as to include a location and elevation
7933requirement. The permit was denied, however, based upon the
7942Department's interpretation of the statute involved, Section
7949381.0065(4)(t)1., Florida Statutes (2007). Even had the rule
7957definition of flooding been considered during the review of the
7967application there is no evidence to show that the Department
7977expanded the term "flooding" and employed an un-adopted rule.
798659. A rule is defined in Section 120.52(15), Florida
7995Statutes (2008), as an agency statement of "general
8003applicability." The statement of general applicability
8009regarding definition of the term "flooding" is codified in
8018Florida Administrative Code Rule 64E-6.002(25) and defines it as
"8027a covering of the soil surface by water from any source. . . ."
804160. The definition of flooding in the Department's rule is
8051used within the context of Section 381.0065(4)(t)1., which
8059statute is concerned with elevation requirements regarding the
8067flood zones of the Suwannee River. The statute thus states that
8078the absorption surface of the drainfield shall not be subject to
8089flooding, based on 10-year flood elevations, and also states
8098that if the three exceptions are all met that an applicant who
8110cannot construct a drainfield system with the absorption surface
8119equal to or above the 10-year flood elevation may still be
8130issued a permit based upon the three exceptions, quoted above.
814061. In the case of Environmental Trust v. Department of
8150Environmental Protection , 714 So. 2d 493, 498 (Fla. 1st DCA
81601998), the First District Court of Appeal considered the
8169question of the use of an agency's rule of general applicability
8180within the context, or applicable to, a particular set of facts.
8191The court opined:
8194An agency statement that is the equivalent
8201of a rule must be adopted in the rulemaking
8210process. . . .
8214This requirement, carried forward in Section
8220120.54(1), Florida Statutes (supp. 1996),
8225prevents an administrative agency from
8230relying on general policies that are not
8237tested in the rulemaking process, but it
8244does not apply to every kind of statement an
8253agency may make. Rulemaking is required
8259only for an agency statement that is the
8267equivalent of a rule, which is defined in
8275Section 120.52(15), Florida Statutes (1996),
8280as a statement of "general applicability."
8286An agency statement explaining how an
8292existing rule of general applicability will
8298be applied in a particular set of facts is
8307not itself a rule. If that were true, the
8316agency would be forced to adopt a rule for
8325every possible variation on a theme, and
8332private entities could continually attack
8337the government for its failure to have a
8345rule that precisely addresses the facts at
8352issue. (Citations omitted)
835562. In this case had the Department considered the rule
8365term "flooding" during the course of its review of the OSTDS
8376application, it would have done so within the context of the
8387statute which specifically addresses the issue of locating such
8396systems in the Suwannee and Aucilla River floodways and which
8406is also concerned with the placement of drainfield absorption
8415surfaces in relation to the 10-year and two-year flood
8424elevations. The use of the existing rule of general
8433applicability (the flooding rule), applied to the particular set
8442of facts, which includes a statute which contemplates location
8451and elevation, does not mean that the definition of the term
"8462flooding" found in Florida Administrative Code Rule 64E-
84706.002(25) has been expanded to include a location and elevation
8480requirement. The statute itself contained that definition.
848763. A plain reading and consideration of that rule
8496demonstrates that the 10-year flood elevation is indeed
8504contemplated within that rule where it states as follows:
8513Flooding - A covering of soil surface by
8521water from any source, such as streams
8528overflowing their banks, runoff from
8533adjacent or surrounding slopes, elevation of
8539the groundwater table exceeding that of the
8546soil surface, or combination of these.
8552Terms also associated with flooding and used
8559elsewhere in this chapter are:
8564(a) Frequent-flooding which occurs more
8569than once every two years on the average;
8577(b) Ten year flood elevation -that flood
8584elevation which has a 10 in 100 probability
8592of being equaled or exceeded in any calendar
8600year.
860164. Moreover, regarding the Petitioner's interpretation of
8608the "subject to flooding" standards, it must be remembered that
8618the absorption surface of the drainfield is defined as "the
8628total surface area of soil at the bottom of the drainfield."
8639Fla. Admin. Code Rule 64E-6.002(1). If flooding is a covering
8649of soil surface as defined in the above-cited rule, and the
8660absorption surface is at the bottom of the drainfield, which is
8671obviously located beneath the soil surface, clearly when the
8680soil surface is covered or submerged by water, anything beneath
8690that surface is subject to flooding, including the absorption
8699surface of the drainfield, given the rule's definition.
870765. Section 381.0065(1), Florida Statutes, provides a
8714statement of the legislature's intent in enacting the OSTDS
8723regulatory program, including public health and environmental
8730concerns, where it is stated:
8735It is further the intent of the legislature
8743that the installation and use of onsite
8750sewage treatment and disposal systems not
8756adversely affect the public health or
8762significantly degrade the groundwater or
8767surface water.
876966. If effluent from OSTDS systems is not properly treated
8779and disposed of, it can pose a public health hazard involving
8790pathogenic constituency and potential environmental degradation
8796in the form of excessive nutrients, principally nitrogen and
8805phosphorous in the groundwater or surface waters. These are the
8815public health and environmental degradation-type concerns the
8822legislature was treating in enacting the regulatory program
8830involved.
883167. The evidence adduced at hearing shows that there have
8841been some operational problems with no mound systems in the
8851past, as described in the above Findings of Fact. More
8861pointedly, however, it has not been demonstrated persuasively
8869that the no mound system proposed to be placed on the Sevick
8881property has been adequately tested and found to safely address
8891the proper disposal and treatment of effluent through the
8900subject drainfield. The evidence is not persuasive in terms of
8910demonstrating that sufficient air pressure can be maintained in
8919order to sustain the required 24-inch differential of
8927unsaturated soil below the absorption surface. The air pressure
8936necessary to perform that function, especially under varying
8944ground and surface water levels, including varying flood
8952conditions, were not definitively established. This is
8959especially problematic under conditions of pump failure due to
8968inadequacy of the solar-charged battery system, if primary power
8977is interrupted, or if failure occurs due to maintenance issues.
898768. Moreover, there is a significant potential for
8995erosion, due to flood waters compromising the integrity of the
9005soil anchoring system and the membrane, and therefore the air
9015pressure within the drainfield system. The evidence shows that
9024the anchors, rather than being 10 feet beneath the soil surface
9035may only be as little as four feet below the surface (top of the
9049anchors). It has not been demonstrated by preponderant,
9057persuasive evidence that they could maintain sufficient downward
9065force so as to stabilize the anti-buoyancy beams, cover and
9075membrane system, and therefore preserve the integrity of the
9084membrane in a flood and erosion situation, particularly a 10-
9094year flood event.
909769. Thus, it has not been clearly established, aside from
9107the findings and discussions regarding the legal effect on the
9117permit application of the 10-year flood elevation standards,
9125that the system will definitely work adequately as designed and
9135installed. On balance, it must be determined that the permit
9145should therefore be denied, subject to the applicant's statutory
9154opportunity to apply for a variance, which may result in his
9165ability to install an OSTDS system of some type, similar to
9176those described above, which may provide adequate treatment,
9184even if below the 10-year flood elevation.
919170. In this connection, the preponderant evidence of
9199record does not establish that the Petitioner purchased the lots
9209in question with the intent to create a hardship situation with
9220regard to variance requirements and standards, nor does it
9229establish that he was aware, upon purchase of the lots, that the
9241subject legal interpretation might be made and that the
9250resultant legal difficulty in installing such a system below the
926010-year flood elevation might ensue. The evidence adduced does
9269not establish that he was even aware of the 10-year flood
9280elevation when he purchased the property.
9286RECOMMENDATION
9287Having considered the foregoing Findings of Fact,
9294Conclusions of Law, the evidence of record, the candor and
9304demeanor of the witnesses and pleadings and arguments of the
9314parties, it is, therefore,
9318RECOMMENDED that the Amended Petition be denied.
9325DONE AND ENTERED this 16th day of February, 2009, in
9335Tallahassee, Leon County, Florida.
9339S
9340P. MICHAEL RUFF
9343Administrative Law Judge
9346Division of Administrative Hearings
9350The DeSoto Building
93531230 Apalachee Parkway
9356Tallahassee, Florida 32399-3060
9359(850) 488-9675 SUNCOM 278-9675
9363Fax Filing (850) 921-6847
9367www.doah.state.fl.us
9368Filed with the Clerk of the
9374Division of Administrative Hearings
9378this 16th day of February, 2009.
9384COPIES FURNISHED :
9387Kenneth J. Plante, Esquire
9391Tana D. Storey, Esquire
9395Brewton Plante, P.A.
9398225 South Adams Street, Suite 250
9404Tallahassee, Florida 32301
9407Mark Dunn, Esquire
9410Lisa M. Raleigh, Esquire
9414Office of the Attorney General
9419The Capitol, Plaza Level 01
9424Tallahassee, Florida 32399
9427Lucy M. Schneider, Esquire
9431Department of Health
94344052 Bald Cypress Way, Bin A02
9440Tallahassee, Florida 32399
9443John M. Lockwood, Esquire
9447Rutledge, Ecenia & Purnell, P.A.
9452215 South Monroe Street, Suite 420
9458Tallahassee, Florida 32301
9461R. S. Power, Agency Clerk
9466Department of Health
94694052 Bald Cypress Way, Bin A02
9475Tallahassee, Florida 32399-1701
9478Dr. Ana M. Viamonte Ros, Secretary
9484Department of Health
94874052 Bald Cypress Way, Bin A00
9493Tallahassee, Florida 32399-1701
9496Josefina M. Tamayo, General Counsel
9501Department of Health
95044052 Bald Cypress Way, Bin A02
9510Tallahassee, Florida 32399-1701
9513NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
9519All parties have the right to submit written exceptions within
952915 days from the date of this Recommended Order. Any exceptions
9540to this Recommended Order should be filed with the agency that
9551will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 02/16/2009
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 02/16/2009
- Proceedings: Recommended Order (hearing held September 16-17, 2008). CASE CLOSED.
- PDF:
- Date: 12/01/2008
- Proceedings: Department`s Evidentiary Briefing for Recommended Proposed Order filed.
- PDF:
- Date: 12/01/2008
- Proceedings: Intervenor, Nomound Systems of Florida, Inc.`s Proposed Recommended Order filed.
- PDF:
- Date: 11/07/2008
- Proceedings: Order (recommended orders shall be due 20 days from the date of this order).
- PDF:
- Date: 10/29/2008
- Proceedings: Letter to Judge Ruff from M. Dunn regarding filing of parties` Proposed Recommended Orders filed.
- Date: 10/03/2008
- Proceedings: Transcript of Final Hearing (Volumes I-III) filed.
- PDF:
- Date: 10/03/2008
- Proceedings: Petitioner`s Response in Opposition to Save Suwannee, Inc.`s Second Amended Petition to Intervene filed.
- PDF:
- Date: 09/30/2008
- Proceedings: Second Amended Petition to Intervene (Save Our Suwannee, Inc.) filed.
- PDF:
- Date: 09/19/2008
- Proceedings: Order (Petition to Intervene filed by Save Our Suwannee, Inc. is denied).
- PDF:
- Date: 09/18/2008
- Proceedings: Order on the Suwannee River Water Management District`s Petition to Intervene.
- PDF:
- Date: 09/16/2008
- Proceedings: Order on Department of Environmental Protections Petition for Leave to Intervene.
- Date: 09/16/2008
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 09/12/2008
- Proceedings: Second Notice of Taking Telephonic Deposition Duces Tecum (J. Murray) filed.
- PDF:
- Date: 09/08/2008
- Proceedings: Second Amended Notice of Taking Deposition Duces Tecum (G. Briggs) filed.
- PDF:
- Date: 09/08/2008
- Proceedings: Seconf Amended Notice of Taking Depositon Duces Tecum (P. Booher) filed.
- PDF:
- Date: 09/03/2008
- Proceedings: Second Amended Notice of Taking Deposition Duces Tecum (G. Briggs) filed.
- PDF:
- Date: 09/03/2008
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (C. Luther) filed.
- PDF:
- Date: 09/03/2008
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (J. McRae) filed.
- PDF:
- Date: 09/03/2008
- Proceedings: Response to Petitioner`s Second Request for Production of Documents filed.
- PDF:
- Date: 09/02/2008
- Proceedings: Amended Notice of Taking Telephonic Deposition Duces Tecum filed.
- PDF:
- Date: 09/02/2008
- Proceedings: Petitioner`s Response in Opposition to the Department of Environmental Protection`s Petition for Leave to Intervene filed.
- PDF:
- Date: 08/27/2008
- Proceedings: Petitioner`s Response in Opposition to the Suwannee River Water Management District`s Petition to Intervene filed.
- PDF:
- Date: 08/27/2008
- Proceedings: Amended Notice of Taking Video Deposition Duces Tecum (S. Sayko) filed.
- PDF:
- Date: 08/26/2008
- Proceedings: Petitioner`s Response in Opposition to Save Our Suwannee, Inc.`s Amended Petition to Intervene filed.
- PDF:
- Date: 08/25/2008
- Proceedings: Notice of Taking Video Deposition Duces Tecum (A. Hassett) filed.
- PDF:
- Date: 08/25/2008
- Proceedings: Department of Environmental Protection`s Petition for Leave to Intervene filed.
- PDF:
- Date: 08/21/2008
- Proceedings: Petition to Intervene (Suwannee River Water Management District) filed.
- PDF:
- Date: 08/07/2008
- Proceedings: Notice of Serving Amended Answers to Petitioner`s First Set of Interrogatories filed.
- PDF:
- Date: 08/05/2008
- Proceedings: Response to Petitioner`s First Request for Production of Documents filed.
- PDF:
- Date: 08/05/2008
- Proceedings: Notice of Serving Answers to Petitioner`s First Set of Interrogatories filed.
- PDF:
- Date: 08/01/2008
- Proceedings: Order (Respondent`s Motion for Summary Recommended Order is denied; Petitioner`s request for attorney`s fees is denied).
- PDF:
- Date: 07/31/2008
- Proceedings: Response to Motion to Abate Discovery Pending Resolution of Respondent`s Motion for Summary Recommended Order filed.
- PDF:
- Date: 07/29/2008
- Proceedings: Response to Respondent`s Motion for Summary Recommended Order filed.
- PDF:
- Date: 07/22/2008
- Proceedings: Notice of Serving Answers to Respondent`s First Set of Interrogatories filed.
- PDF:
- Date: 07/21/2008
- Proceedings: Motion to Abate Discovery Pending Resolution of Respondent`s Motion for Summary Recommended Order filed.
- PDF:
- Date: 06/30/2008
- Proceedings: Notice of Serving First Set of Interrogatories to Respondent filed.
- PDF:
- Date: 06/30/2008
- Proceedings: Petitioner`s First Request for Production of Documents to Respondent filed.
- PDF:
- Date: 06/30/2008
- Proceedings: Notice of Serving First Set of Interrogatories to Respondent filed.
- PDF:
- Date: 06/18/2008
- Proceedings: Notice of Serving First Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 06/12/2008
- Proceedings: Notice of Hearing (hearing set for September 16 and 17, 2008; 9:30 a.m.; Tallahassee, FL).
- PDF:
- Date: 05/23/2008
- Proceedings: Motion to Forward Petition for Administrative Hearing to the Division of Administrative Hearings filed.
- PDF:
- Date: 05/23/2008
- Proceedings: Renewed Motion for Leave to File Amended Petition for Administrative Hearing filed.
Case Information
- Judge:
- P. MICHAEL RUFF
- Date Filed:
- 05/23/2008
- Date Assignment:
- 08/19/2008
- Last Docket Entry:
- 04/08/2009
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
Counsels
-
W. Douglas Beason, Esquire
Address of Record -
Mark S Dunn, Esquire
Address of Record -
John M. Lockwood, Esquire
Address of Record -
Kenneth J. Plante, Esquire
Address of Record -
Lisa Marie Raleigh, Esquire
Address of Record -
Lucy Schneider, Esquire
Address of Record