08-002552 Daniel M. Sevick vs. Department Of Health
 Status: Closed
Recommended Order on Monday, February 16, 2009.


View Dockets  
Summary: Petitioner failed to prove that innovative on-site sewage disposal system would not be subject to flooding. The statute has flood elevation standard, not an avenue to allow for a system which purports to prevent flooding by use of air pressure.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8DANIEL M. SEVICK, )

12)

13Petitioner, )

15)

16vs. ) Case No. 08-2552

21)

22DEPARTMENT OF HEALTH, )

26)

27Respondent, )

29)

30and )

32)

33NO MOUNDS SYSTEMS OF FLORIDA, )

39INC., AND SAVE OUR SUWANNEE, )

45INC., )

47)

48Intervenors. )

50)

51RECOMMENDED ORDER

53This cause came on for formal proceeding and hearing before

63P. Michael Ruff, a duly-designated Administrative Law Judge of

72the Division of Administrative Hearings. The hearing was

80conducted in Tallahassee, Florida, on September 16 and 17, 2008.

90The appearances were as follows:

95APPEARANCES

96For Petitioner: Kenneth J. Plante, Esquire

102Tana D. Storey, Esquire

106Brewton Plante, P.A.

109225 South Adams Street, Suite 250

115Tallahassee, Florida 32301

118For Respondent: Mark Dunn, Esquire

123Lisa M. Raleigh, Esquire

127Office of the Attorney General

132The Capitol, Plaza Level 01

137Tallahassee, Florida 32399

140Lucy M. Schneider, Esquire

144Department of Health

1474052 Bald Cypress Way, Bin A02

153Tallahassee, Florida 32399

156For Intervenor: Save Our Suwannee, Inc.

162John M. Lockwood, Esquire

166Rutledge, Ecenia & Purnell, P.A.

171215 South Monroe Street, Suite 420

177Tallahassee, Florida 32301

180For Intervenor: No Mound Systems of Florida, Inc.

188Kenneth J. Plante, Esquire

192Tana D. Storey, Esquire

196Brewton Plante, P.A.

199225 South Adams Street, Suite 250

205Tallahassee, Florida 32301

208STATEMENT OF THE ISSUES :

213The issues to be resolved in this proceeding concern

222whether an application to construct and operate an on-site

231sewage treatment and disposal system (OSTDS), within the

239Suwannee River flood plain, meets the requirements of Section

248381.0065(4)(t), Florida Statutes (2007), and relevant Department

255of Health (Department) rules, and whether the department applied

264an un-adopted rule in denying the permit application.

272PRELIMINARY STATEMENT

274This cause arose concerning the denial of the Petitioner's

283application to construct an OSTDS on Lots 12 and 13 in the Log

296Landing Subdivision in Dixie County, Florida. Those lots are

305located adjacent to the Suwannee River. On July 23, 2007, a

316letter was issued by the Department denying the permit

325application based upon the following statement:

331Our engineer has reviewed your proposal.

337Based on the site elevation submitted (16.8

344feet) and the 10 year flood elevation (22

352feet) the proposal is not in compliance with

360381.0065(4)(t), Florida Statutes, and must

365be denied.

367Thereafter a timely Petition in Opposition to the denial

376was submitted by the Petitioner, seeking an administrative

384hearing. The Petition was filed August 16, 2007, and by Order

395of September 21, 2007, the Department assigned the Petitioner to

405an appointed presiding officer to conduct an informal

413administrative hearing.

415On January 4, 2008, the Petitioner filed an Amended

424Petition for Administrative Hearings, which included a challenge

432pursuant to Section 120.57(1), Florida Statutes (2007),

439concerning its position that the Department had followed and

448applied an un-adopted rule in the process of its denial of the

460permit application. On May 14, 2008, the Department entered an

470Order Granting the renewed Motion for Leave to file an Amended

481Petition and then referred the Amended Petition to the Division

491of Administrative Hearings. The matter was assigned to an

500administrative law judge and thence transferred to the

508undersigned administrative law judge, and this proceeding

515ensued.

516Prior to the hearing, Petitions to Intervene were filed by

526Save our Suwannee, Inc. (SOS), the Suwannee River Water

535Management District (the District), the Florida Department of

543Environmental Protection (DEP), and No Mounds Systems of

551Florida, Inc. (No Mound).

555Thereafter, an amended Petition to Intervene was filed by

564SOS. The Petitions to Intervene filed by SOS, DEP, and the

575District were denied based upon lack of standing. No Mound's

585Petition for Leave to Intervene was granted, based upon there

595being no objection thereto. SOS was granted leave to file a

606Second Amended Petition to Intervene to demonstrate how it and

616its members' substantial interests could be affected by the

625permit application and therefore why it and its members had

635standing.

636The Second Amended Petition to Intervene by SOS was filed

646pursuant to an Order denying the Amended Petition to Intervene

656by SOS, entered by the undersigned on the day prior to the

668hearing, because the Amended Petition was filed immediately

676prior to the hearing. This resulted in the Second Amended

686Petition to Intervene by SOS being timely filed on September 29,

6972008, after the conduct of the hearing. Because of this

707sequence of events concerning SOS's intervention, SOS was

715allowed to proffer its testimony at the hearing, as to its

726standing, and as to its position regarding the merits of the

737permit application, with the understanding by all parties that

746should the Second Amended Petition to Intervene be granted,

755(which it was) that the proffered evidence by SOS would become

766its actual evidence to be considered in support of its second

777amended intervention petition. This was done in order to avoid

787a bi-furcated hearing situation, with the inherent delay

795involved in allowing SOS to put on its case at a later time, if

809it were allowed to file a Second Amended Petition to Intervene,

820which it was. Thus the hearing, including SOS's full

829participation as an intervenor, under the above-described

836circumstances, was concluded on the above date.

843The cause came on for hearing as noticed. The Petitioner

853presented the testimony of Allen F. Hassett, Professional

861Engineer (PE), accepted as an expert in the field of Sanitary

872and Waste Water Engineering: Harry Wild; PE, who was accepted as

883an expert in onsite sewage treatment and disposal systems

892(OSTDS) design and environmental engineering; and Steven Sayko,

900Professional Geologist (PG), who was accepted as an expert in

910the field of Hydrogeology. The Petitioner's Exhibits 1 through

91916 were admitted into evidence.

924The Department presented the testimony of Gerald Briggs,

932Chief of the Bureau of Onsite Sewage Program; Samuel Averett;

942and Paul Booher, PE, of the Bureau of Onsite Sewage Programs, of

954the Department of Health. The Respondent's Exhibits 1 through

96312 and 15 through 17, as well as 20A, B, and C were admitted

977into evidence.

979The Respondent's Exhibits 1 through 10 and 15 through 17

989are maintenance reports which are routinely submitted to the

998Department on a quarterly basis and relate to various no mound

1009systems in Florida. These were objected to by the Petitioner on

1020relevancy and hearsay grounds. It was determined that they come

1030within the business records exception to the hearsay rule and

1040the hearsay objection was overruled. They were determined to be

1050relevant, subject to briefing on whether the prejudice out-

1059weighed the relevance. It is determined that these exhibits are

1069relevant and they are admitted. They will be weighed and

1079considered in terms of their remoteness in time from the design

1090and installation of the proposed system, and in terms of any

1101innovations which have been brought forward as to no mound

1111systems since the time of a particular maintenance report

1120regarding a no mound system in these exhibits. Other factors

1130such as location and elevation, which render the systems

1139addressed by some of these maintenance reports to be different

1149in character, construction and operational parameters from the

1157system proposed, are deemed to detract from the substance and

1167materiality of such reports.

1171Upon conclusion of the proceeding, the parties had the

1180evidence transcribed and elected to submit proposed recommended

1188orders. The Proposed Recommended Orders were timely submitted

1196after the Order was entered on the Second Amended Petition for

1207Intervention by SOS, which closed the record. Proposed

1215Recommended Orders were submitted by the Petitioner, the

1223Respondent, and by the Intervenors. All have been considered in

1233the rendition of this Recommended Order.

1239FINDINGS OF FACT

12421. Daniel Sevick is the owner of two lots, consisting of a

1254total of 1.24 acres, within the flood plain of the Suwannee

1265River. The lots are lots 12 and 13 in "Log Landing

1276Subdivision." The Petitioner applied for a construction permit

1284for the installation of an OSTDS on that property. The

1294application for the permit was submitted to the Dixie County

1304Health Department, which forwarded it to the Department of

1313Health for review, in accordance with Section 381.0065(4)(j),

1321Florida Statutes (2007). The Respondent, Department of Health,

1329(Department) is an Agency of the State of Florida charged with

1340implementing and enforcing the provisions of Chapter 381,

1348Florida Statutes, and Florida Administrative Code Chapter 64E.

1356Among its duties are the review of and issuance of permits for

1368construction of OSTDS.

13712. The permit application was reviewed by the Department

1380and was subsequently denied, based upon the following reasoning

1389contained in the denial letters:

1394Our engineer has reviewed your proposal.

1400Based on the site elevation submitted (16.8

1407feet) and the 10 year elevation (22 feet)

1415the proposal is not in compliance with

1422381.0065(4)(t), Florida Statutes, and must

1427be denied.

14293. Certain of the facts have been stipulated to by the

1440parties. The parties thus agree that the 10-year flood

1449elevation for the property is 22 feet; the site elevation of the

1461property is 16.8 feet and the two-year flood elevation for the

1472property is 16.00 feet. The bottom of the proposed drainfield

1482is at an elevation of 14.30 feet. The Petitioner thus proposes

1493to install the OSTDS system with the bottom of the drainfield

15041.70 feet below the two-year flood elevation. The proposed

1513system consists of a conventional septic tank system connected

1522to a "no mound" drainfield system.

1528No Mound System

15314. The no mound drainfield system is an innovative

1540drainfield system. No Mound was granted a permit for its design

1551as an "innovative system" by the Department, initially

1559authorizing installation of five systems in Florida, starting on

1568December 23, 1998. An "innovative system" is defined as an

"1578onsite sewage treatment and disposal system that, in whole or

1588in part, employs materials, devices, or techniques that are

1597novel or unique and that have not been successfully field tested

1608under sound scientific and engineering principles under climatic

1616and soil conditions found in this state." See §

1625381.0065(4)(2)(g), Fla. Stat (2007). Innovative systems, by

1632definition are considered to be "performance-based systems"

1639which have additional requirements placed on them depending on

1648the performance level of the effluent treatment.

16555. The design of the OSTDS system submitted with the

1665permit application included several changes intended for this

1673particular property, based upon discussions between the

1680Petitioner's representatives and the Department. The changes

1687include relocation of the OSTDS and drainfield to the highest

1697elevation of the property; addition of a solar-recharge battery

1706alternative power supply; the obtaining of additional

1713information with regard to soil borings; and the performance of

1723an evaluation to confirm the capacity of the soil anchors in

1734saturated soil. The OSTDS, including the no mound drainfield,

1743was designed by Harry Wild, PE, specifically for the

1752Petitioner's property. The proposed OSTDS is considered by the

1761Department to be an "engineer-designed" system.

17676. Over approximately the last 10 years No Mound has been

1778issued innovative permits authorizing the installation of

1785approximately 250 no mound drainfield systems.

17917. The no mound system is an innovative system which does

1802not employ a conventional drainfield. Instead, based upon

1810principles of physics and engineering, the drainfield system is

1819designed to be installed underground, with air pumped into the

1829system to depress the groundwater elevation or "water table," so

1839as to provide the required separation or distance between the

1849absorption surface of the drainfield (bottom of the drainfield)

1858and the groundwater. In Florida the separation required is 24

1868inches. The drainfield system is designed to retain air pumped

1878into it, for depression of the groundwater level, by being

1888covered with pieces of geo-fabric and a p.v.c. membrane designed

1898to retain air within the system under a certain level of

1909pressure. The air pressure is designed to depress the water

1919level of groundwater directly beneath the area of the

1928drainfield, much like the principle of a "diving bell."

19378. The drainfield system would be covered with two pieces

1947of geo-fabric on either side of a 30 mill. p.v.c. membrane, the

1959same material used as a liner for hazardous waste landfills.

1969The geo-fabric material protects the p.v.c. membrane from damage

1978or puncture during construction. Once in operation the membrane

1987is unlikely to tear under normal conditions, unless through

1996intentional puncture with an extremely sharp implement or

2004through some catastrophic event, such as a large tree falling on

2015the surface above the membrane.

20209. The membrane is held in position by a patented ballast

2031and anchor system. The ballast material consists of pre-

2040stressed concrete beams, spanning the width of the drainfield.

2049At each end of each beam is a soil anchor.

205910. The 20 pre-stressed ballast beams are held in place

2069with 40 helically shaped screw anchors, which screw into the

2079soil. Each anchor is intended to withstand 5,000 pounds of

2090upward force. The screw anchors are designed to hold the

2100concrete beams in place in saturated soil. The soil anchors are

2111threaded with a washer and nut on both the top and the bottom of

2125the concrete beam which prevents the beam from moving

2134vertically, downward or upward, so that the beam can resist any

2145uplifting force.

214711. Air is pumped into this system by a continuous air

2158pump which would be wired into the power system of the residence

2170to be on the property. There would also be an emergency power

2182supply. The air pressure inside the system would vary in

2192response to the level of water outside the system whether

2202groundwater or surface water. As the water outside the system

2212rises or subsides, the water inside and beneath the system is

2223supposed to remain lowered, as the pressure inside the system is

2234designed to increase or decrease. The Petitioner maintains that

2243the ballast system is designed to contain the pressure (air

2253pressure) which would be required to continue to suppress any

2263groundwater or flood water associated with a ten-year flood

2272event.

227312. The system has an "air bleed," which is intended to

2284maintain aerobic conditions in the drainfield. If surface

2292waters overflow the top of the drainfield system in a flood

2303event, the air bleed system is designed to continue functioning.

2313The air would enter the soil beneath the ground surface and

2324bubble up through any water above the ground surface. If both

2335the primary and backup power supplies should fail, the

2344Petitioner maintains that the air bleed would "shut off" so that

2355no air would escape from the system and thus maintain the

2366pressure within the system, much like a diving bell. This

2376characteristic is designed to maintain the separation between

2384the groundwater surface and the bottom of the drainfield in the

2395event of a power failure.

240013. The Department has interpreted the operative statute,

2408Section 381.0065(4)(t), Florida Statutes (2007), as providing

2415that the absorption surface of a drainfield for any OSTDS system

2426cannot lie below the 10-year flood elevation, if it is located

2437within the floodways of the Suwannee or Aucilla Rivers, unless

2447the system meets all the exceptions contained in Section

2456381.0065(4)(t)1.a.b. and c., Florida Statutes. One of these

2464exceptions requires that the bottom of the drainfield, the

2473absorption surface, be at least 36 inches above the two-year

2483flood elevation for the site. The two-year flood elevation at

2493the subject site is 16 feet. The proposed installation would

2503have the bottom of the drainfield or absorption surface located

25131.70 feet below that two-year flood elevation, thus not

2522complying with that exception.

252614. The applicant's system is not in compliance with the

2536portion of paragraph (c), referenced above as an exception,

2545concerning a system approved by the county health department,

2554pursuant to department rule, which is "other than" a system

2564using "alternative drainfield materials." This system would

2571apparently use so-called "alternative drainfield materials."

257715. Innovative systems are those which represent new

2585technology that has not been completely field-tested in Florida.

2594The Petitioner has applied for the permit as an innovative

2604permit application, which contains a requirement that the system

2613be replaced with an alternative system in case it fails within a

2625five-year test period.

262816. No mound systems are site specific, with each one

2638being specifically designed for a particular property with its

2647unique characteristics. There are approximately 50 no mound

2655systems approved, permitted and operating in Florida at the

2664present time. The evidence does not reflect which, if any, of

2675those systems are installed below flood elevations. The

2683drainfield portion of such a system works in the same way as a

2696conventional drainfield, that is, the soil and piping which lies

2706below the membrane. The membrane system is the unique

2715characteristic of the no mound system. Because of the membrane

2725and ballasting system designed to retain air pressure over and

2735in contact with the drainfield absorption surface, the system is

2745different and more complex than the standard drainfield system,

2754although it treats affluent in the same way.

276217. Two significant problems arose with the installation

2770of the first five innovative permit, no mound systems. The

2780testimony of Sam Averett, who is a septic system contractor,

2790described an installation of a no mound system on his own

2801property in 1999. The system was installed in accordance with

2811Mr. Hassett's specifications and recommendations, and he was

2819present during the installation. Mr. Hassett testified in

2827support of the petition in this case as an engineering expert.

2838Within a few days or weeks the Averett system developed a

2849problem. Apparently, with a substantial rain event, the system

"2858floated" that is, the air pressure contained within the

2867membrane rose to the surface of the ground, similar to a

"2878bubble." This would have amounted to a failure to maintain the

2889air pressure necessary to ensure that a 24-inch separation

2898between the absorption surface of the drainfield and the

2907groundwater table elevation was maintained. That system was re-

2916designed and a different ballasting system or buoyancy package

2925was used, involving the use of "railroad iron" (rails), and

2935plywood spanning the drainfield in order to hold the membrane

2945beneath in place, with the whole arrangement being recovered

2954with dirt. Thereafter, on January 1, 2003, after a substantial

2964rainfall event, the system floated out of the ground once again.

2975After that second failure of the Averett system, Mr. Averett

2985installed a "hoot" system, which involves a "drip irrigation"

2994drainfield installation, with the delivery piping and the

3002drainfield being much closer to the ground surface or within six

3013inches of the surface.

301718. The system described by Jack Murray in his testimony

3027was also one of the original five systems installed in Florida

3038by No Mound, Inc. That system was designed to maintain a 30-

3050inch separation between the absorption surface of the drainfield

3059(bottom of drainfield) and the groundwater elevation or water

3068table. According to Mr. Murray it never maintained that

3077separation. He was aware of the lack of a 30-inch separation

3088being maintained because of the onsite monitors installed with

3097the system. He described the actual separation which the system

3107provided as being only .9 feet. The onsite monitors by which he

3119was able to observe the actual separation failed after about two

3130years of operation. He brought the separation issue to the

3140attention of the contractor or representative of No Mound, which

3150patented the system and oversaw the installation. According to

3159Mr. Murray, however, they never satisfactorily addressed the

3167problem. When the air pump failed, after approximately two

3176years of operation, he called the manufacturer of the air pump

3187and was informed that the air pump had been the incorrect type

3199or size for the no mound system which he had installed.

321019. Although these two referenced problems concerning the

3218Murray system and the Averett system represent two of the first

3229five innovative no mound systems installed in Florida, the

3238problems associated therewith may have been corrected since,

3246because each system installed at a given site is specifically

3256and uniquely designed by an engineer for that site and its

3267physical, hydrologic and operating circumstances. Thus, the

3274referenced problems involving buoyancy or "floating-up" of the

3282drainfield membrane system and the failure to maintain adequate

3291pressure so as to achieve the legally-mandated 24-inch

3299differential between groundwater elevation and the bottom of the

3308absorption surface, may not be construed to be direct predictors

3318of what will occur with the installation of the Sevick system.

3329The problems do point up, however, the fact that the air

3340pressure maintained at different groundwater levels in the

3348system is a critical component of the system's function and also

3359that the ballasting system and design is critical in order to

3370maintain the integrity of the membrane system or air chamber

3380overlying the drainfield surface, at different water levels and

3389conditions. This is a particular concern with regard to flood

3399conditions.

340020. It also true that the proposed air pressure to be

3411maintained in the system at issue, the Sevick system, would be

3422five pounds per square inch. Earlier systems, possibly

3430including the Murray system, maintained a pressure of two pounds

3440per square inch.

344321. However, aside from the rather conclusory testimony of

3452the Petitioner's expert witnesses, who opined generally that the

3461air pressure and the integrity of the membrane system and

3471ballast system would be adequate to maintain the legally-

3480mandated 24-inch differential of unsaturated soil below the

3488absorption surface, there was no definitive evidential showing

3496of what air pressure would actually be necessary to perform that

3507function adequately under all conditions. This is particularly

3515problematic under conditions of flooding, since the proposed

3523drainfield would be beneath both the 10-year flood elevation and

3533the two-year flood elevation. Although there was testimony

3541which indicated that the air pressures would vary, would

3550increase or decrease depending upon the water levels beneath the

3560drainfield and outside of the membrane, there was no definitive

3570showing in the evidence as to what pressures under those varying

3581water level conditions would still enable the 24-inch

3589differential to be maintained. Under the Department's

3596interpretation of its statutes and rules, a 24-inch differential

3605is deemed adequate and necessary for treatment of the sewage

3615effluent entering the drainfield.

361922. The electric power necessary for operation of the air

3629pump which pressurizes the system would be derived from

3638connection with the residence to be constructed on the lots.

3648The emergency power system would be designed to accommodate

3657situations where there is a power outage, for instance in a

3668storm situation. The alternative system would be dependent upon

3677solar-rechargeable battery power. If the air pump ceased

3685operation due to a power outage and the backup system was not

3697adequate, or adequately charged, to operate the pump

3705sufficiently or for a sufficient period of time to maintain the

3716required air pressure, then the 24-inch differential might not

3725be maintained. The evidence does not reveal a practical way to

3736monitor the air inflow or the air pressure condition inside the

3747membrane in the event of a power outage. The Petitioner's

3757witnesses maintained that if there was a power outage the air

3768bleed device would close down, thus maintaining the required air

3778pressure (akin to a diving bell circumstance). There was no

3788persuasive evidence, however, to show what air pressure would

3797thus be statically maintained and whether it would maintain the

3807required 24-inch separation.

381023. Harry Wild was the design engineer who designed the no

3821mound system for the Sevick property. Mr. Wild, however, was

3831unaware, apparently, that Dr. Jeffrey Evans, a geotechnical

3839expert and expert in the design of helical anchors for the

3850ballast system for the Sevick property, had recommended that at

3860least one boring be made for each site or each of the two lots

3874to a depth of 20 feet. This was recommended in order to verify

3887what the sub-surface conditions were, so that the conditions

3896assumed in the system design could be verified. Mr. Wild

3906testified that he only took borings to a depth of 10 feet.

3918Mr. Hassett on the other hand testified that he thought the

3929borings had only been done to six feet. In fact, the site

3941evaluations submitted to the Department demonstrated soil boring

3949had been performed to a depth of six feet below ground surface,

3961and the cross-sectional drawing indicates that the anchors,

3969designed to hold down the beams and the membrane, would only

3980begin approximately four feet below the ground surface.

398824. Thus, even though Mr. Wild was the expert designer of

3999the No mound system for the Sevick project, he was unaware of

4011whether the ballast system was a new type of system which had

4023been specifically designed for that property. He did

4031acknowledge that it was the first time he had employed that type

4043of ballast system.

404625. In spite of the higher operating pressure, five PSI

4056versus two PSI, to be maintained in the Sevick no mound system

4068over that normally maintained in previous no mound systems,

4077Mr. Wild did not perform calculations or evaluations as to the

4088beam strength and design requirements of the new ballast system.

4098He did not perform calculations or evaluations that addressed

4107the issue of membrane deflection requirements, which relates to

4116how much the membrane would move upward under various pressures.

4126This in turn could relate to how much downward pressure must be

4138exerted by the anchoring system, to counteract the buoyancy of

4148the membrane bulging upward under different pressure

4155circumstances, associated with different water levels.

416126. Mr. Hassett did not know what membrane deflection was

4171acceptable for the Sevick no mound system other than "a fair

4182amount" which he acknowledged varied "depending on the geo-

4191synthetic or the geo-grid that was specified for that particular

4201project." It is understandable that this is an innovative

4210system which requires certain revisions at times before it is

4220installed, or during the course of installation, to adapt its

4230design to the particular site. However, the evidence presented

4239at hearing, as shown by Mr. Hassett's testimony, and Mr. Wild's

4250as well, in this regard, is somewhat indefinite and does not

4261show a substantial likelihood that the membrane and concrete

4270beam and anchor ballasting system proposed will work as planned

4280from a structure and strength standpoint. As Mr. Hassett

4289testified "they will be tested before installation."

429627. As shown by Mr. Wild's testimony, the soil of the

4307Petitioner's lots is composed of fine sand at the installation

4317site. There is no evidence concerning any erosion study or

4327concerning what the erosion experience might be in a flooding

4337situation, in order to determine the effect on the helical

4347anchors and ballasting system in the event of floods of varying

4358severities, including a 10-year flood.

436328. Dr. Evans established in his deposition testimony that

4372the helical anchors get their resistance to upward force from

4382the sheer strength of the soil, which is a frictional value

4393combined with the effective stress on the soil. If a certain

4404amount of soil is eroded away, then the holding capacity of the

4416anchors is correspondingly reduced. Dr. Evans, however, assumed

4424that the applied load per anchor was 5,000 pounds, with the

4436anchor handling 5,000 pounds of upward force if it was 10 feet

4449underground. Therefore, the designers of the system would need

4458to assure that the anchors are 10 feet underground and that the

4470applied load is 5,000 pounds, according to Dr. Evan's testimony.

4481He opined that if erosion of varying amounts occurred that could

4492affect the anchors' holding capacity.

449729. In fact, the evidence shows that the anchors or the

4508top of the anchors may only be proposed to be installed four

4520feet below the surface. Therefore, the evidence does not

4529clearly establish that the beam/anchor system is adequate to

4538maintain the stability of the drainfield membrane system in the

4548event of a flooding situation.

455330. Gerald Briggs testified on behalf of the Department.

4562He described the growing concern that nitrogen levels in the

4572effluent of OSTDS systems represent, in terms of potential

4581environmental degradation of ground or surface waters, which the

4590Department is charged with addressing by the statutory authority

4599cited below. The no mound system, like any conventional OSTDS

4609system, has no specific provision that would treat or reduce

4619nitrogen levels in the effluent from the system. The 24-inch

4629separation between the absorption surface of the drainfield and

4638the groundwater elevation is designed to be unsaturated soil,

4647which provides treatment of only a primary nature for

4656essentially the public health/pathogenic components of the OSTDS

4664system effluent (i.e. sanitary treatment).

466931. Although there is not such a monitoring requirement,

4678the Department has requested data from the Petitioner regarding

4687the quality of the effluent that would leave the system. If the

4699system were ever installed, it should be done with the condition

4710that effluent sampling and testing of the effluent should be

4720performed, in order to ascertain that the system operates

4729properly, in terms of public health and environmental

4737degradation, on an ongoing basis.

474232. The Petitioner's witnesses, Mr. Wild and Mr. Sayko,

4751acknowledged that the system proposed is not infallible and

4760there are certain risks posed by the installation. For

4769instance, if a pump was broken then the water level would start

4781to rise inside the no mound system, according to Mr. Sayko's

4792testimony.

479333. Moreover, the absorption surface in the drainfield as

4802proposed, would likely be "subject to flooding" in a situation

4812of power outages and erosion during a flood event. It must be

4824remembered that the ground surface is some five feet below the

483510-year flood elevation at the installation site and the

4844absorption surface or bottom of the drainfield is over seven

4854feet below the 10-year flood elevation. Thus, in the

4863circumstance of power outages or flood-caused erosion, the

4871absorption surface of the proposed drainfield could be "subject

4880to flooding."

488234. The Department denied the subject permit application

4890because the site elevation is 16.8 feet and the 10-year flood

4901elevation at the site is 22 feet. Thus, the proposal was to

4913install the absorption surface below the 10-year flood elevation

4922(more than seven feet below it). In denying the requested

4932permit the Department denied it based upon its interpretation of

4942the subject statute, Section 381.0065(4)(t)(1), Florida Statutes

4949(2007). It did not actually employ an un-adopted rule or

"4959agency statement of general applicability" in making this

4967interpretation. Rather, it interpreted the statute, applying it

4975to the particular facts of the permit application and the

4985situation prevailing at the proposed installation site. It was

4994not applying an interpretation or policy statement of general

5003applicability enforced throughout its jurisdiction, or

5009throughout the flood plain area of the Suwannee and Aucilla

5019Rivers, but rather was applying the statutory language and its

5029interpretation of it to the particular site and circumstances of

5039the proposed system and its contemplated operation.

504635. A variance from the above-referenced statutory

5053requirements and related rules is not at issue in this case

5064because the Petitioner has not sought a variance. Although

5073variances have been granted in the Suwannee River flood plain

5083area, in accordance with Section 381.0065(4)(h), Florida

5090Statutes (2007), the grant of such variances has usually carried

5100the concomitant requirement of more advanced treatment of the

5109effluent in the system to be installed, as allowed by the

5120granted variance. Thus, an aerobic treatment unit (ATU) or

5129performance-based septic treatment system, such as an advanced

5137secondary treatment system (AST), as well as the use of drip

5148drainfields, such as the hoot system, have been required in

5158accordance with the statute.

516236. An ATU introduces air into the treatment unit in order

5173to enhance the treatment and generally employ filters as well,

5183according to witness Briggs. An AST type system reduces the

5193biochemical oxygen demand (BOD), total suspended solids, as well

5202as treating the nitrogen and phosphorus contents of the

5211effluent. Historically, the Department has only approved

5218variances in the Suwannee or Aucilla River flood plains for

5228vacant lots with the use of ATU or AST type systems.

523937. A drip drainfield reduces the required height of the

5249drainfield by some 12 inches because it is only buried six

5260inches into the soil. This is done because it is designed to be

5273buried in the shallow root zone of trees and plants which allow

5285trees and plants to uptake the nutrients in the effluent water

5296and thus prevent them from being deposited in the ground or

5307surface waters. In the Suwannee River basin area, most of the

5318variances granted by the Department have required such drip

5327drainfield systems.

532938. One of the statutory considerations for granting of a

5339variance is that the Petitioner for a variance should not have

5350created the hardship involved, resulting in the need for the

5360variance. The Department maintains that the Petitioner,

5367Mr. Sevick, has created the hardship in this case by purchasing

5378the lot knowing of the restrictions on OSTDS systems that were

5389legally prevailing. The evidence, however, does not really

5397establish that the Petitioner intentionally created the hardship

5405by purchasing a lot knowing of all the restrictions that were in

5417place and their effects. One can infer, for instance, that he

5428was aware of advertisements by No Mounds, that lots in the

5439Suwannee River basin or flood plain area could be developed by

5450using its OSTDS system without even necessitating the use of

5460fill. The Department's evidence simply does not establish that

5469the Petitioner, Mr. Sevick, intended creating the hardship, on

5478his own volition, by purchasing the lot with knowledge that the

5489specific restrictions were in place, from a legal standpoint.

5498Thus it was not proven that the Petitioner is unable to

5509establish a hardship for purposes of seeking a variance pursuant

5519to Section 381.0065(4)(h), Florida Statutes (2007), on the basis

5528that the Petitioner created the hardship.

553439. As established by witness Briggs, nitrogen and

5542phosphorus elements of OSTDS effluents are of growing concern

5551for ground and surface waters in Florida. Nitrogen and

5560phosphorus enhance algae growth in surface waters, which can

5569lead to reduced dissolved oxygen content and other factors

5578harmful to fish and wildlife. There is thus a deleterious

5588environmental impact from nitrogen and phosphorus levels in

5596surface waters or groundwaters, in addition to the pathogens

5605which can characterize effluent from OSTDS systems, related to

5614human waste.

561640. Advanced septic systems such as ATUs or ASTs have been

5627required in the grant of variance-based septic system permits in

5637flood plains of the rivers because of the potential of their

5648being flooded and because of the locations of the systems. The

5659Department, in consideration of its statutory charge, has sought

5668to seek as much treatment as possible for the effluent, in such

5680situations, in order to prevent significant degradation of

5688ground or surface water. A no mound system is a drainfield

5699dispersal system, so it itself poses no additional treatment

5708capability than does a conventional OSTDS system, as established

5717by both witnesses Wild and Briggs.

5723CONCLUSIONS OF LAW

572641. The Division of Administrative Hearings has

5733jurisdiction of the subject matter of and the parties to this

5744proceeding. §§ 120.569 and 120.57(1), Fla. Stat. (2008).

575242. The Department has the authority to issue permits

5761governing installation and operation of OSTDS systems. The

5769intent of the Legislature to that effect is set out in Section

5781381.0065(1), Florida Statutes (2007), concerning permitting.

5787Therein it is provided:

57911. LEGISLATIVE INTENT.-It is the intent of

5798the legislature that where a publicly owned

5805or investor-owned sewerage system is not

5811available, the department shall issue

5816permits for the construction, installation,

5821modification, abandonment, or repair for

5826onsite sewage treatment and disposal systems

5832under conditions as described in this

5838section and rules adopted under this

5844section. It is further the intent of the

5852legislature that the installation and use of

5859onsite sewage treatment and disposal systems

5865not adversely affect the public health or

5872significantly degrade the groundwater or

5877surface water.

5879The following requirements are imposed by Section

5886381.0065(4)(t), Florida Statutes (2007), for installation of

5893OSTDS in the floodways of the Suwannee and Aucilla Rivers:

5903(t) Notwithstanding the provisions of sub-

5909paragraph (g)1., onsite sewage treatment and

5915disposal systems located in floodways of the

5922Suwannee and Aucilla Rivers must adhere to

5929the following requirements:

5932(1) The absorption surface of the

5938drainfield shall not be subject to flooding

5945based on 10-year flood elevations.

5950Provided, however, for lots or parcels

5956created by the subdivision of land in

5963accordance with applicable local government

5968regulations prior to January 17, 1990, if an

5976applicant cannot construct a drainfield

5981system with the absorption surface of the

5988drainfield at an elevation equal to or above

599610-year flood elevation , the department

6001shall issue a permit for an onsite sewage

6009treatment and disposal system within the 10-

6016year flood plain of rivers, streams, and

6023other bodies of flowing water if all of the

6032following criteria are met:

6036a. The lot is at least one-half acre in

6045size;

6046b. The bottom of drainfield is at least 36

6055inches above the 2-year flood elevation; and

6062c. The applicant installs either:

6067A waterless, incinerating, or organic

6072waste composting toilet and a gray water

6079system and drainfield in accordance with

6085department rules; an aerobic treatment unit

6091and drainfield in accordance with department

6097rules; a system approved by the state health

6105office that is capable of reducing effluent

6112nitrate by at least 50 percent; or a system

6121approved by the county health department

6127pursuant to department rule other than a

6134system using alternative drainfield

6138materials. . . . (Emphasis supplied).

614443. The purpose of Subsection (4)(t) is to provide

6153additional requirements for OSTDS located in the floodways of

6162the Suwannee and Aucilla Rivers. These provisions show a

6171particular legislative concern for these environmentally

6177important areas, hence the legislatively-imposed unique

6183requirements for these regions.

618744. The stated legislative intent provides that when

6195attempting to place OSTDS in these floodways, "[T]he absorption

6204surface of the drainfield shall not be subject to flooding based

6215on 10-year flood elevations ." If one reads the entire text of

6227Section 381.0065(4)(t)1., a consistency through the entire text

6235of that paragraph is revealed which shows a legislative intent

6245centered on the actual placement of the bottom of a drainfield

6256system in relation to the 10-year flood elevation. It is not a

6268subjective concern that the absorption surface of such a

6277drainfield not be "subject to flooding," depending upon the type

6287of innovative, engineered system which might be capable of being

6297installed, which would, if operating correctly, isolate the

6305absorption surface itself from flood waters.

631145. It is true that the first sentence of that

6321subparagraph, cited last-above, states that the absorption

6328surface "shall not be subject to flooding based on 10-year flood

6339elevations," rather than openly stating that the 10-year flood

6348elevation is a mandatory minimum elevation. However, when the

6357paragraph is read in its entirety, it can be seen that the

6369second sentence of (4)(t)1., provides a legislative explanation

6377of what "subject to flooding" actually means. In other words,

6387if one wishes to install a OSTDS in the flood zone of either

6400river, the drainfield must not be "subject to flooding," but if

6411one owns a lot which meets the exception language beginning in

6422the second sentence of that paragraph and the "applicant cannot

6432construct a drainfield system with the absorption surface of the

6442drainfield at an elevation equal to or above the 10-year flood

6453elevation," the exceptions beginning in that second sentence can

6462be applicable to that particular situation. The point is, if

6472one reads Section 381.0065(4)(t)1., Florida Statutes (2007), in

6480its entirety and in complete context, it is clear that the

6491legislature meant that "subject to flooding" meant that one does

6501not place the bottom of the drainfield below the 10-year flood

6512elevation in the Suwannee and Aucilla River flood plains (unless

6522the exceptions are met). The system proposed by the Petitioner

6532is a closed drainfield system designed to withstand the flood

6542waters by isolation of the drainfield surface through the use of

6553a maintained positive air pressure. The Petitioner thus

6561contends that the above-referenced requirement regarding the

6568absorption surface not being subject to flooding is met by the

6579particular devices installed, with regard to the drainfield,

6587referenced in the Findings of Fact.

659346. The Petitioner contends that Section 381.0065, Florida

6601Statutes (2007), contemplates the use and installation of

6609innovative systems, such as the No mound system and, because it

6620is a closed system, and is designed to withstand the pressure of

6632flood waters, that the absorption surface will not be subject to

6643flood waters as contemplated by the statute. However, the

6652purpose of the above-cited subsection, in relation to the

6661remainder of Section 381.0065, Florida Statutes, which provides

6669the framework for OSTDS regulation, simply provides additional

6677requirements for OSTDS systems to be located within the 10-year

6687flood elevation of the Suwannee and Aucilla River basins,

6696without regard to the type of system proposed.

670447. Section 381.0065 addresses permitting, siting,

6710construction, installation, inspection, operation, maintenance,

6715modification, repair and abandonment of onsite systems. It also

6724provides for variances, special consideration for sensitive

6731areas such as the Suwannee and Aucilla River flood zones,

6741Department evaluation of onsite system additives, and the

6749development and permitting of alternative treatment units and

6757innovative system designs.

676048. While that section contemplates innovation, design

6767provisions for engineer-designed, performance-based systems, are

6773found in Section 381.0065(4)(j), and innovative systems in

6781Section 381.0065(3)(e), not in Section 381.0065(4)(t).

678749. The No Mound Corporation has already been issued an

6797innovative permit, to install 250 systems in Florida. When

6806installing an OSTDS, No Mound must still meet all remaining

6816requirements of Section 381.0065. If the absorption surface of

6825a drainfield for any OSTDS, without regard to the type of

6836system, is at an elevation less than the 10-year flood

6846elevation, pursuant to Section 381.0065(4)(t)1., a. through c.,

6854all three of the statutorily-enumerated exceptions must be met,

6863and engineering design is not one of them. If all of the

6875exceptions are not met, then no OSTDS system, including the no

6886mound system, is allowed to be constructed in the floodway of

6897the Suwannee River.

690050. In enacting the Section 381.0065(4)(t), Florida

6907Statutes (2007), the legislature was not concerned with whether

6916the engineering design or innovative devices for a particular

6925type of drainfield system would render it flood proof. Rather,

6935it was concerned with the location of the drainfield, deeming

6945it, in effect, to be "subject to flooding" if it was located

6957beneath the 10-year flood elevation.

696251. It is well-settled that legislative intent is the

6971principal concept regarding statutory construction. Reynolds v.

6978State of Florida , 842 So. 2d 46, 49 (Fla. 2003); McGhee v.

6990State , 847 So. 2d 498, 501 (Fla. 4th DCA 2003). Legislative

7001intent derives primarily from statutory language itself, which

7009is the most reliable and authoritative expression of such

7018intent. Reynolds , 842 So. 2d at 49; McGhee , 847 So. 2d at 501.

703152. The statutory language must be read and considered in

7041its entirety when making an interpretation. Jones v. ETS of New

7052Orleans, Inc. , 793 So. 2d 912, 915 (Fla. 2001) (". . .

7065[S]tatutory phrases are not to be read in isolation, but rather

7076within the context of the entire section." Acosta v. Richter ,

7086671 So. 2d 149, 154 (Fla. 1996)). Once legislative intent is

7097ascertained, all parts of the statute must be read conjunctively

7107to arrive at a consistent complete context. Statutory phrases

7116should be considered with a view to the entire context of the

7128section from which they come. Borden v. Est-European Insurance

7137Company , 921 So. 2d 587, 595 (Fla. 2006); Parker v. State , 874

7149So. 2d 683, 684 (Fla. 4th DCA 2004). It is clear, when reading

7162and considering Section 381.0065(4)(t)1., Florida Statutes, in

7169its entire context, that the legislature was really concerned

7178with avoiding placement of the bottom of a drainfield below the

718910-year flood elevation.

719253. The Department is the state agency charged with

7201administering the provisions of Section 381.0065, Florida

7208Statutes (2007). The construction or interpretation of a

7216statute by an agency which it is given power to administer it

7228will generally not be overturned unless clearly erroneous.

7236Laborer's International Union of North America, Local 478 v.

7245Burroughs , 541 So. 2d 1160, 1162 (Fla. 1989); Pan American World

7256Airways v. Florida Public Service Commission , 427 So. 2d 716,

7266719 (Fla. 1983); Wallace Corporation v. City of Miami Beach , 793

7277So. 2d 1134, 1140 (Fla. 1st DCA 2001). See also Cenac v. State

7290Board of Accountancy , 399 So. 2d 1013 (Fla. 1st DCA 1981) (an

7302agency's construction of statutes within its regulatory

7309jurisdiction is generally given deference because of the

7317agency's familiarity with the statutory scheme and its expertise

7326in administering the field being regulated); Roberts v. Ayers ,

7335380 So. 2d 1057 (Fla. 1st DCA 1979). The agency's construction

7346of a statute need not be the only possible interpretation or

7357even the most desirable one, but must only be within the range

7369of possible statutory construction. Orange Park Kennel Club,

7377Inc., v. Department of Business and Professional Regulation , 644

7386So. 2d 574, 576 (Fla. 1st DCA 1994); Florida League of Cities v.

7399Department of Environmental Regulation , 603 So. 2d 1363, 1369

7408(Fla. 1st DCA 1992).

741254. If one considers Section 381.0065(4)(t), Florida

7419Statutes (2007), in its entirety, along with the remainder of

7429that statutory section, it becomes apparent that the legislature

7438was concerned with creating special consideration for the area

7447of the floodways of the Suwannee and Aucilla Rivers. It

7457intended to ensure that drainfields not be subject to flooding,

7467by requiring construction of them with an absorption surface at

7477an elevation equal to or above the 10-year flood elevation.

7487Design standards are established elsewhere in Section 381.0065,

7495Florida Statutes (2007). Once a permit is granted for an

7505innovative design system such as the no mound system, that

7515system must still meet all other requirements of Section

7524381.0065, including the provisions of paragraph (4)(t).

753155. In summary, the Department is the agency with the

7541authority as well as expertise to administer Section 381.0065,

7550Florida Statutes. Its interpretation of Section 381.0065(4)(t),

7557Florida Statutes, is the more reasonable interpretation of those

7566proposed and it is not clearly erroneous. Its interpretation

7575reflects the most likely rationale and context of the

7584legislature's intent in the enactment of the subject provision.

7593Its interpretation is deemed correct.

759856. Even if that were not the case, the above Findings of

7610Fact reveal a number of problems or potential problems with the

7621no mound system. There are several unanswered questions as to

7631the installation and operation of the no mound system to be

7642placed on the Sevick property. The primary concern is the

7652question of how effective the anchoring system would be, given

7662that some expert testimony and evidence seemed to rely on the

7673anchors being at a 10-foot depth below the ground surface, while

7684the design and apparent installation plans would indicate that

7693they would actually begin four feet below the ground surface.

7703The unanswered questions also include what might happen if

7712flood-caused erosion removed soil relied upon to exert a

7721sufficient downward force on the anchoring system to hold the

7731membrane in place. Thus, there is the potential that, through

7741flood-caused erosion, the membrane, and the air pressure that it

7751is supposed to maintain, might be displaced, rendering the

7760drainfield absorption surface subject to flooding in such an

7769event.

777057. Moreover, the evidence supportive of the above

7778Findings of Fact does not clearly establish that, in the event

7789of a power failure, even taking into account the back-up battery

7800power system, a sufficient air pressure could be maintained

7809beneath the membrane of the drainfield system so as to exclude

7820flood waters and to maintain the required 24-inch separation

7829between the bottom of the drainfield system and the groundwater

7839elevation. Thus, even if the Petitioner's interpretation of the

7848referenced statute regarding the meaning of "subject to

7856flooding" is correct, the preponderant evidence, supportive of

7864the above Findings of Fact, shows that the drainfield's

7873absorptive surface could be subject to flooding, in a flood

7883event.

7884Un-adopted Rule Issue

788758. The Petitioner contends that the Department applied an

7896un-adopted rule in its review of the permit application. The

7906Petitioner maintains that the Department expanded the definition

7914of the term "flooding" contained in Florida Administrative Code

7923Rule 64E-6.002(25) so as to include a location and elevation

7933requirement. The permit was denied, however, based upon the

7942Department's interpretation of the statute involved, Section

7949381.0065(4)(t)1., Florida Statutes (2007). Even had the rule

7957definition of flooding been considered during the review of the

7967application there is no evidence to show that the Department

7977expanded the term "flooding" and employed an un-adopted rule.

798659. A rule is defined in Section 120.52(15), Florida

7995Statutes (2008), as an agency statement of "general

8003applicability." The statement of general applicability

8009regarding definition of the term "flooding" is codified in

8018Florida Administrative Code Rule 64E-6.002(25) and defines it as

"8027a covering of the soil surface by water from any source. . . ."

804160. The definition of flooding in the Department's rule is

8051used within the context of Section 381.0065(4)(t)1., which

8059statute is concerned with elevation requirements regarding the

8067flood zones of the Suwannee River. The statute thus states that

8078the absorption surface of the drainfield shall not be subject to

8089flooding, based on 10-year flood elevations, and also states

8098that if the three exceptions are all met that an applicant who

8110cannot construct a drainfield system with the absorption surface

8119equal to or above the 10-year flood elevation may still be

8130issued a permit based upon the three exceptions, quoted above.

814061. In the case of Environmental Trust v. Department of

8150Environmental Protection , 714 So. 2d 493, 498 (Fla. 1st DCA

81601998), the First District Court of Appeal considered the

8169question of the use of an agency's rule of general applicability

8180within the context, or applicable to, a particular set of facts.

8191The court opined:

8194An agency statement that is the equivalent

8201of a rule must be adopted in the rulemaking

8210process. . . .

8214This requirement, carried forward in Section

8220120.54(1), Florida Statutes (supp. 1996),

8225prevents an administrative agency from

8230relying on general policies that are not

8237tested in the rulemaking process, but it

8244does not apply to every kind of statement an

8253agency may make. Rulemaking is required

8259only for an agency statement that is the

8267equivalent of a rule, which is defined in

8275Section 120.52(15), Florida Statutes (1996),

8280as a statement of "general applicability."

8286An agency statement explaining how an

8292existing rule of general applicability will

8298be applied in a particular set of facts is

8307not itself a rule. If that were true, the

8316agency would be forced to adopt a rule for

8325every possible variation on a theme, and

8332private entities could continually attack

8337the government for its failure to have a

8345rule that precisely addresses the facts at

8352issue. (Citations omitted)

835562. In this case had the Department considered the rule

8365term "flooding" during the course of its review of the OSTDS

8376application, it would have done so within the context of the

8387statute which specifically addresses the issue of locating such

8396systems in the Suwannee and Aucilla River floodways and which

8406is also concerned with the placement of drainfield absorption

8415surfaces in relation to the 10-year and two-year flood

8424elevations. The use of the existing rule of general

8433applicability (the flooding rule), applied to the particular set

8442of facts, which includes a statute which contemplates location

8451and elevation, does not mean that the definition of the term

"8462flooding" found in Florida Administrative Code Rule 64E-

84706.002(25) has been expanded to include a location and elevation

8480requirement. The statute itself contained that definition.

848763. A plain reading and consideration of that rule

8496demonstrates that the 10-year flood elevation is indeed

8504contemplated within that rule where it states as follows:

8513Flooding - A covering of soil surface by

8521water from any source, such as streams

8528overflowing their banks, runoff from

8533adjacent or surrounding slopes, elevation of

8539the groundwater table exceeding that of the

8546soil surface, or combination of these.

8552Terms also associated with flooding and used

8559elsewhere in this chapter are:

8564(a) Frequent-flooding which occurs more

8569than once every two years on the average;

8577(b) Ten year flood elevation -that flood

8584elevation which has a 10 in 100 probability

8592of being equaled or exceeded in any calendar

8600year.

860164. Moreover, regarding the Petitioner's interpretation of

8608the "subject to flooding" standards, it must be remembered that

8618the absorption surface of the drainfield is defined as "the

8628total surface area of soil at the bottom of the drainfield."

8639Fla. Admin. Code Rule 64E-6.002(1). If flooding is a covering

8649of soil surface as defined in the above-cited rule, and the

8660absorption surface is at the bottom of the drainfield, which is

8671obviously located beneath the soil surface, clearly when the

8680soil surface is covered or submerged by water, anything beneath

8690that surface is subject to flooding, including the absorption

8699surface of the drainfield, given the rule's definition.

870765. Section 381.0065(1), Florida Statutes, provides a

8714statement of the legislature's intent in enacting the OSTDS

8723regulatory program, including public health and environmental

8730concerns, where it is stated:

8735It is further the intent of the legislature

8743that the installation and use of onsite

8750sewage treatment and disposal systems not

8756adversely affect the public health or

8762significantly degrade the groundwater or

8767surface water.

876966. If effluent from OSTDS systems is not properly treated

8779and disposed of, it can pose a public health hazard involving

8790pathogenic constituency and potential environmental degradation

8796in the form of excessive nutrients, principally nitrogen and

8805phosphorous in the groundwater or surface waters. These are the

8815public health and environmental degradation-type concerns the

8822legislature was treating in enacting the regulatory program

8830involved.

883167. The evidence adduced at hearing shows that there have

8841been some operational problems with no mound systems in the

8851past, as described in the above Findings of Fact. More

8861pointedly, however, it has not been demonstrated persuasively

8869that the no mound system proposed to be placed on the Sevick

8881property has been adequately tested and found to safely address

8891the proper disposal and treatment of effluent through the

8900subject drainfield. The evidence is not persuasive in terms of

8910demonstrating that sufficient air pressure can be maintained in

8919order to sustain the required 24-inch differential of

8927unsaturated soil below the absorption surface. The air pressure

8936necessary to perform that function, especially under varying

8944ground and surface water levels, including varying flood

8952conditions, were not definitively established. This is

8959especially problematic under conditions of pump failure due to

8968inadequacy of the solar-charged battery system, if primary power

8977is interrupted, or if failure occurs due to maintenance issues.

898768. Moreover, there is a significant potential for

8995erosion, due to flood waters compromising the integrity of the

9005soil anchoring system and the membrane, and therefore the air

9015pressure within the drainfield system. The evidence shows that

9024the anchors, rather than being 10 feet beneath the soil surface

9035may only be as little as four feet below the surface (top of the

9049anchors). It has not been demonstrated by preponderant,

9057persuasive evidence that they could maintain sufficient downward

9065force so as to stabilize the anti-buoyancy beams, cover and

9075membrane system, and therefore preserve the integrity of the

9084membrane in a flood and erosion situation, particularly a 10-

9094year flood event.

909769. Thus, it has not been clearly established, aside from

9107the findings and discussions regarding the legal effect on the

9117permit application of the 10-year flood elevation standards,

9125that the system will definitely work adequately as designed and

9135installed. On balance, it must be determined that the permit

9145should therefore be denied, subject to the applicant's statutory

9154opportunity to apply for a variance, which may result in his

9165ability to install an OSTDS system of some type, similar to

9176those described above, which may provide adequate treatment,

9184even if below the 10-year flood elevation.

919170. In this connection, the preponderant evidence of

9199record does not establish that the Petitioner purchased the lots

9209in question with the intent to create a hardship situation with

9220regard to variance requirements and standards, nor does it

9229establish that he was aware, upon purchase of the lots, that the

9241subject legal interpretation might be made and that the

9250resultant legal difficulty in installing such a system below the

926010-year flood elevation might ensue. The evidence adduced does

9269not establish that he was even aware of the 10-year flood

9280elevation when he purchased the property.

9286RECOMMENDATION

9287Having considered the foregoing Findings of Fact,

9294Conclusions of Law, the evidence of record, the candor and

9304demeanor of the witnesses and pleadings and arguments of the

9314parties, it is, therefore,

9318RECOMMENDED that the Amended Petition be denied.

9325DONE AND ENTERED this 16th day of February, 2009, in

9335Tallahassee, Leon County, Florida.

9339S

9340P. MICHAEL RUFF

9343Administrative Law Judge

9346Division of Administrative Hearings

9350The DeSoto Building

93531230 Apalachee Parkway

9356Tallahassee, Florida 32399-3060

9359(850) 488-9675 SUNCOM 278-9675

9363Fax Filing (850) 921-6847

9367www.doah.state.fl.us

9368Filed with the Clerk of the

9374Division of Administrative Hearings

9378this 16th day of February, 2009.

9384COPIES FURNISHED :

9387Kenneth J. Plante, Esquire

9391Tana D. Storey, Esquire

9395Brewton Plante, P.A.

9398225 South Adams Street, Suite 250

9404Tallahassee, Florida 32301

9407Mark Dunn, Esquire

9410Lisa M. Raleigh, Esquire

9414Office of the Attorney General

9419The Capitol, Plaza Level 01

9424Tallahassee, Florida 32399

9427Lucy M. Schneider, Esquire

9431Department of Health

94344052 Bald Cypress Way, Bin A02

9440Tallahassee, Florida 32399

9443John M. Lockwood, Esquire

9447Rutledge, Ecenia & Purnell, P.A.

9452215 South Monroe Street, Suite 420

9458Tallahassee, Florida 32301

9461R. S. Power, Agency Clerk

9466Department of Health

94694052 Bald Cypress Way, Bin A02

9475Tallahassee, Florida 32399-1701

9478Dr. Ana M. Viamonte Ros, Secretary

9484Department of Health

94874052 Bald Cypress Way, Bin A00

9493Tallahassee, Florida 32399-1701

9496Josefina M. Tamayo, General Counsel

9501Department of Health

95044052 Bald Cypress Way, Bin A02

9510Tallahassee, Florida 32399-1701

9513NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

9519All parties have the right to submit written exceptions within

952915 days from the date of this Recommended Order. Any exceptions

9540to this Recommended Order should be filed with the agency that

9551will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 04/08/2009
Proceedings: Final Order filed.
PDF:
Date: 04/02/2009
Proceedings: Agency Final Order
PDF:
Date: 02/16/2009
Proceedings: Recommended Order
PDF:
Date: 02/16/2009
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 02/16/2009
Proceedings: Recommended Order (hearing held September 16-17, 2008). CASE CLOSED.
PDF:
Date: 12/01/2008
Proceedings: Department`s Evidentiary Briefing for Recommended Proposed Order filed.
PDF:
Date: 12/01/2008
Proceedings: Proposed Recommended Order filed.
PDF:
Date: 12/01/2008
Proceedings: Save Our Suwannee`s Proposed Recommended Order filed.
PDF:
Date: 12/01/2008
Proceedings: Intervenor, Nomound Systems of Florida, Inc.`s Proposed Recommended Order filed.
PDF:
Date: 12/01/2008
Proceedings: Petitioner`s Proposed Recommended Order filed.
PDF:
Date: 11/19/2008
Proceedings: Order.
PDF:
Date: 11/18/2008
Proceedings: Joint Motion to Supplement Record filed.
PDF:
Date: 11/18/2008
Proceedings: Amended Joint Pre-hearing Stipulation filed.
PDF:
Date: 11/07/2008
Proceedings: Order (recommended orders shall be due 20 days from the date of this order).
PDF:
Date: 10/29/2008
Proceedings: Letter to Judge Ruff from M. Dunn regarding filing of parties` Proposed Recommended Orders filed.
Date: 10/03/2008
Proceedings: Transcript of Final Hearing (Volumes I-III) filed.
PDF:
Date: 10/03/2008
Proceedings: Petitioner`s Response in Opposition to Save Suwannee, Inc.`s Second Amended Petition to Intervene filed.
PDF:
Date: 09/30/2008
Proceedings: Second Amended Petition to Intervene (Save Our Suwannee, Inc.) filed.
PDF:
Date: 09/29/2008
Proceedings: Undeliverable envelope returned from the Post Office.
PDF:
Date: 09/29/2008
Proceedings: Undeliverable envelope returned from the Post Office.
PDF:
Date: 09/19/2008
Proceedings: Order (Petition to Intervene filed by Save Our Suwannee, Inc. is denied).
PDF:
Date: 09/18/2008
Proceedings: Deposition of Jack E. Murray filed.
PDF:
Date: 09/18/2008
Proceedings: Order on the Suwannee River Water Management District`s Petition to Intervene.
PDF:
Date: 09/18/2008
Proceedings: Notice of Filing Deposition filed.
PDF:
Date: 09/16/2008
Proceedings: Order on Department of Environmental Protections Petition for Leave to Intervene.
Date: 09/16/2008
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 09/15/2008
Proceedings: Petitioner`s Motion for Official Recognition filed.
PDF:
Date: 09/12/2008
Proceedings: Subpoena Duces Tecum (J. Murray) filed.
PDF:
Date: 09/12/2008
Proceedings: Second Notice of Taking Telephonic Deposition Duces Tecum (J. Murray) filed.
PDF:
Date: 09/10/2008
Proceedings: Joint Motion for Official Recognition filed.
PDF:
Date: 09/09/2008
Proceedings: Joint Pre-hearing Stipulation filed.
PDF:
Date: 09/08/2008
Proceedings: Notice Cancellation of Deposition (J. McRae) filed.
PDF:
Date: 09/08/2008
Proceedings: Notice of Cancellation of Deposition (C. Luther) filed.
PDF:
Date: 09/08/2008
Proceedings: Second Amended Notice of Taking Deposition Duces Tecum (G. Briggs) filed.
PDF:
Date: 09/08/2008
Proceedings: Seconf Amended Notice of Taking Depositon Duces Tecum (P. Booher) filed.
PDF:
Date: 09/04/2008
Proceedings: Second Amended Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 09/03/2008
Proceedings: Amended Notice of Taking Deposition Duces Tecum (H. Wild) filed.
PDF:
Date: 09/03/2008
Proceedings: Second Amended Notice of Taking Deposition Duces Tecum (G. Briggs) filed.
PDF:
Date: 09/03/2008
Proceedings: Amended Notice of Taking Deposition Duces Tecum (C. Luther) filed.
PDF:
Date: 09/03/2008
Proceedings: Notice of Cancellation of Deposition filed.
PDF:
Date: 09/03/2008
Proceedings: Amended Notice of Taking Deposition Duces Tecum (J. McRae) filed.
PDF:
Date: 09/03/2008
Proceedings: Response to Petitioner`s Second Request for Production of Documents filed.
PDF:
Date: 09/02/2008
Proceedings: Amended Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 09/02/2008
Proceedings: Amended Notice of Taking Telephonic Deposition Duces Tecum filed.
PDF:
Date: 09/02/2008
Proceedings: Amended Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 09/02/2008
Proceedings: Petitioner`s Response in Opposition to the Department of Environmental Protection`s Petition for Leave to Intervene filed.
PDF:
Date: 08/29/2008
Proceedings: Notice of Taking Deposition Duces Tecum (G. Briggs) filed.
PDF:
Date: 08/29/2008
Proceedings: Notice of Taking Deposition Duces Tecum (5) filed.
PDF:
Date: 08/27/2008
Proceedings: Petitioner`s Response in Opposition to the Suwannee River Water Management District`s Petition to Intervene filed.
PDF:
Date: 08/27/2008
Proceedings: Amended Notice of Taking Video Deposition Duces Tecum (S. Sayko) filed.
PDF:
Date: 08/26/2008
Proceedings: Petitioner`s Response in Opposition to Save Our Suwannee, Inc.`s Amended Petition to Intervene filed.
PDF:
Date: 08/26/2008
Proceedings: Amended Notice of Taking Video Deposition Duces Tecum filed.
PDF:
Date: 08/26/2008
Proceedings: Notice of Taking Video Deposition Duces Tecum filed.
PDF:
Date: 08/25/2008
Proceedings: Notice of Appearance (filed by W. Beason).
PDF:
Date: 08/25/2008
Proceedings: Petition to Intervene (Nomound Systems of Florida) filed.
PDF:
Date: 08/25/2008
Proceedings: Notice of Taking Video Deposition Duces Tecum (S. Sayko) filed.
PDF:
Date: 08/25/2008
Proceedings: Notice of Taking Video Deposition Duces Tecum (A. Hassett) filed.
PDF:
Date: 08/25/2008
Proceedings: Notice of Taking Video Deposition Duces Tecum (H. Wild) filed.
PDF:
Date: 08/25/2008
Proceedings: Notice of Taking Video Deposition Duces Tecum filed.
PDF:
Date: 08/25/2008
Proceedings: Department of Environmental Protection`s Petition for Leave to Intervene filed.
PDF:
Date: 08/21/2008
Proceedings: Petition to Intervene (Suwannee River Water Management District) filed.
PDF:
Date: 08/20/2008
Proceedings: Amended Petition to Intervene (Save our Suwannee) filed.
PDF:
Date: 08/20/2008
Proceedings: Motion to Strike Petition to Intervene filed.
PDF:
Date: 08/18/2008
Proceedings: Petition to Intervene (Save our Suwannee) filed.
PDF:
Date: 08/11/2008
Proceedings: Order Denying Continuance of Final Hearing.
PDF:
Date: 08/11/2008
Proceedings: Petitioner`s Second Request for Production of Documents filed.
PDF:
Date: 08/07/2008
Proceedings: Notice of Serving Amended Answers to Petitioner`s First Set of Interrogatories filed.
PDF:
Date: 08/06/2008
Proceedings: Response to Motion to Continue filed.
PDF:
Date: 08/05/2008
Proceedings: Response to Petitioner`s First Request for Production of Documents filed.
PDF:
Date: 08/05/2008
Proceedings: Notice of Serving Answers to Petitioner`s First Set of Interrogatories filed.
PDF:
Date: 08/01/2008
Proceedings: Order (Respondent`s Motion for Summary Recommended Order is denied; Petitioner`s request for attorney`s fees is denied).
PDF:
Date: 08/01/2008
Proceedings: Notice of Unavailability filed.
PDF:
Date: 07/31/2008
Proceedings: Response to Motion to Abate Discovery Pending Resolution of Respondent`s Motion for Summary Recommended Order filed.
PDF:
Date: 07/29/2008
Proceedings: Motion to Continue filed.
PDF:
Date: 07/29/2008
Proceedings: Response to Respondent`s Motion for Summary Recommended Order filed.
PDF:
Date: 07/22/2008
Proceedings: Notice of Serving Answers to Respondent`s First Set of Interrogatories filed.
PDF:
Date: 07/21/2008
Proceedings: Motion to Abate Discovery Pending Resolution of Respondent`s Motion for Summary Recommended Order filed.
PDF:
Date: 07/21/2008
Proceedings: Notice of Unavailability filed.
PDF:
Date: 07/16/2008
Proceedings: Motion for Summary Recommended Order filed.
PDF:
Date: 07/08/2008
Proceedings: Notice of Appearance (filed by Lisa Raleigh).
PDF:
Date: 06/30/2008
Proceedings: Notice of Serving First Set of Interrogatories to Respondent filed.
PDF:
Date: 06/30/2008
Proceedings: Petitioner`s First Request for Production of Documents to Respondent filed.
PDF:
Date: 06/30/2008
Proceedings: Notice of Serving First Set of Interrogatories to Respondent filed.
PDF:
Date: 06/18/2008
Proceedings: Notice of Serving First Set of Interrogatories to Petitioner filed.
PDF:
Date: 06/12/2008
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 06/12/2008
Proceedings: Notice of Hearing (hearing set for September 16 and 17, 2008; 9:30 a.m.; Tallahassee, FL).
PDF:
Date: 06/11/2008
Proceedings: Joint Amendment to Response to Initial Order filed.
PDF:
Date: 06/06/2008
Proceedings: Joint Response to Initial Order filed.
PDF:
Date: 05/30/2008
Proceedings: Joint Motion for Extension of Time filed.
PDF:
Date: 05/23/2008
Proceedings: Initial Order.
PDF:
Date: 05/23/2008
Proceedings: Petition for Administrative Hearing filed.
PDF:
Date: 05/23/2008
Proceedings: Notice of Appointment of a Presiding Officer filed.
PDF:
Date: 05/23/2008
Proceedings: Motion to Forward Petition for Administrative Hearing to the Division of Administrative Hearings filed.
PDF:
Date: 05/23/2008
Proceedings: Amended Petition for Administrative Hearing filed.
PDF:
Date: 05/23/2008
Proceedings: Renewed Motion for Leave to File Amended Petition for Administrative Hearing filed.
PDF:
Date: 05/23/2008
Proceedings: Order on Petitioner`s Renewed Motion for Leave to File Amended Petition filed.
PDF:
Date: 05/23/2008
Proceedings: Notice (of Agency referral) filed.

Case Information

Judge:
P. MICHAEL RUFF
Date Filed:
05/23/2008
Date Assignment:
08/19/2008
Last Docket Entry:
04/08/2009
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Counsels

Related DOAH Cases(s) (1):

Related Florida Statute(s) (5):

Related Florida Rule(s) (1):