08-004272BID
Mid-State Paving Co., Inc. vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, January 9, 2009.
Recommended Order on Friday, January 9, 2009.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8MID-STATE PAVING CO., INC., )
13)
14Petitioner, )
16)
17vs. ) Case No. 08-4272BID
22)
23DEPARTMENT OF TRANSPORTATION, )
27)
28Respondent, )
30)
31and )
33)
34KAMMINGA & ROODVOETS, INC., )
39)
40Intervenor. )
42)
43RECOMMENDED ORDER
45Pursuant to notice, a formal hearing was held in this case
56on October 14, 2008, in Bartow, Florida, before Lawrence P.
66Stevenson, a duly-designated Administrative Law Judge of the
74Division of Administrative Hearings.
78APPEARANCES
79For Petitioner: James M. McCrae, Esquire
85Law Office of Jim McCrae
90Lake Mary Professional Campus
941349 International Parkway South
98Suite 2421
100Lake Mary, Florida 32746
104For Respondent: C. Denise Johnson, Esquire
110Department of Transportation
113Haydon Burns Building, Mail Station 58
119605 Suwannee Street
122Tallahassee, Florida 32399-0450
125For Intervenor: George E. Spofford, Esquire
131Glenn Rasmussen Fogarty and Hooker, P.A.
137100 South Ashley Drive, Suite 1300
143Tampa, Florida 33602
146STATEMENT OF THE ISSUE
150Whether Respondent acted contrary to the agency's governing
158statutes, rules or policies, or the bid specifications in its
168proposed decision to award Contract No. T1285 to Intervenor
177Kamminga & Roodvoets, Inc. ("K & R").
186PRELIMINARY STATEMENT
188On July 10, 2008, Respondent Department of Transportation
196("Department") posted its intended award of Project No. 197593-
2071-52-01, Proposal No. T1285 ("Contract T1285") for the
217construction of the one-way pair on State Road 600 through Lake
228Alfred. The notice of intent to award reflected that the
238winning contractor was K & R. Mid-State Paving Co., Inc.
248("Mid-State"), submitted the second-low bid. Mid-State filed a
258notice of protest on July 14, 2008, and filed a formal written
270protest on July 24, 2008. The case was forwarded to the
281Division of Administrative Hearings ("DOAH") on August 28, 2008,
292for assignment of an administrative law judge and the conduct of
303a formal hearing. The hearing was initially scheduled to be
313held on September 25 and 26, 2008.
320On September 9, 2008, K & R filed a motion to intervene,
332which was granted by order dated September 17, 2008. Also on
343September 9, 2008, K & R filed an unopposed motion for
354continuance. That motion was granted and the hearing was
363rescheduled for October 14 and 15, 2008. The hearing convened
373on October 14, 2008, and concluded on that date.
382At the final hearing, Mid-State presented the testimony of
391Alvin Mulford, its vice president. The Department presented the
400testimony of Philip Davis, its state estimates engineer, and
409Richard D. Riles, a general engineering consultant. The
417Department's Exhibits 1 through 4 were admitted into evidence.
426The Department's Exhibit 1 was the deposition testimony of
435David A. Sadler, the director of the Department's office of
445construction, and the exhibits attached to the deposition.
453K & R presented the testimony of Marcus B. Tidey, Jr., the vice
466president in charge of its Florida division. K & R's Exhibits
4771 through 5 were admitted into evidence. In addition, Joint
487Exhibits 1 and 2 were admitted by stipulation of all the
498parties. Joint Exhibit 1 consisted of Mid-State's formal
506written protest and 23 tabs of supporting documentation. Joint
515Exhibit 2 contained the details of the Department's bid
524tabulation.
525A Transcript of the proceeding was filed at DOAH on
535October 29, 2008, meaning that Proposed Recommended Orders would
544be due on November 10, 2008. The Department timely filed its
555Proposed Recommended Order on November 10, 2008. Also on
564November 10, 2008, Mid-State filed a motion to extend the time
575for filing proposed recommended orders until November 14, 2008,
584due to "unexpected urgent matters" that required the attention
593of Mid-State's counsel. Mid-State's motion contended that no
601party would be prejudiced by the extension because as of the
612time of the motion's filing, no proposed recommended orders had
622been filed. In fact, the Department's Proposed Recommended
630Order was filed roughly two hours before Mid-State's motion, but
640the undersigned credited Mid-State's counsel with having been
648unaware of that filing.
652On November 12, 2008, K & R filed an objection to the
664motion to extend, arguing that Mid-State waited until the
673proposed recommended orders of the Department and K & R had been
685served before filing its motion, thus obtaining the benefit of
695reading the oppositions' proposed orders before filing its own.
704However, regardless of whether its proposed order was served on
714Mid-State on November 10, 2008, K & R had yet to file its
727proposed recommended order at DOAH as of the morning of
737November 12, 2008. Thus, only the Department had timely filed a
748Proposed Recommended Order.
751By order dated November 12, 2008, the undersigned granted
760Mid-State's motion to extend the time for filing proposed
769recommended orders until November 14, 2008, with the proviso
778that the Department would be given until November 21, 2008, to
789file a supplemental proposed recommended order 1 if it felt the
800need to address any new arguments raised in Mid-State's proposed
810recommended order.
812K & R filed its Proposed Recommended Order on
821November 12, 2008. Mid-State filed its Proposed Recommended
829Order on November 14, 2008. By letter filed at DOAH on
840November 18, 2008, the Department and K & R informed the
851undersigned that they would not file supplements to their
860proposed recommended orders. The parties' submissions have been
868considered in the preparation of this Recommended Order.
876All references to the Florida Statutes are to the 2008
886edition, unless otherwise noted.
890FINDINGS OF FACT
893Based on the oral and documentary evidence presented at the
903final hearing and on the entire record of the proceeding, the
914following findings of fact are made:
9201. On May 14, 2008, the Department released its bid
930solicitation for Contract T1285. The proposed contract was for
939the construction of a one-way pair through Lake Alfred,
948including new construction, reconstruction, milling and
954resurfacing, widening, drainage improvements, lighting,
959signalization, signing and pavement marking and landscaping on
967State Road 600 (U.S. 17/92). Polk County, the location of the
978project, lies in the Department's District 1.
9852. Qualified contractors, including Mid-State and K & R,
994received an electronic disk containing the solicitation, bid
1002blank, plans and specifications for Contract T1285.
10093. The letting date for this project was June 18, 2008.
1020Bids were to be submitted on or before that date via Bid
1032Express, the electronic bidding system used by the Department.
10414. No party submitted a protest of the terms, conditions,
1051and specifications contained in the solicitation pursuant to
1059Subsection 120.57(3)(b), Florida Statutes.
10635. The work to be performed on Contract T1285 included the
1074installation of limerock road base to be paid for in accordance
1085with line item 0175, Optional Base Group 09 ("Base Group 09").
10986. The bid documents included a set of "Supplemental
1107Specifications." Section 6 of the Supplemental Specification
1114was titled "Control of Materials." Subsection 6-3.3, titled
"1122Construction Aggregates," provided as follows: "Aggregates used
1129on Department projects must be in accordance with Florida
1138Administrative Code Rule 14-103." 2
11437. Under the heading "Developmental Specifications" is a
1151February 15, 2008, revision to the Construction Aggregates
1159subsection that provides:
1162Subarticle 6-3.3 (Page 54) is expanded by the following:
11716-3.3.1 Department Directed Source for
1176Aggregates: For this Contract, obtain aggregates
1182for use in limerock base from the following
1190vendor: Vulcan Construction Materials LP. Upon
1196award of the Contract, provide the vendor and the
1205Department a schedule of project aggregate needs.
1212Once a schedule has been provided to both the
1221Department and vendor, the Engineer will issue
1228written authorization, with a copy to the vendor,
1236for the purchase of aggregates from the vendor.
1244This authorization is required before aggregates
1250will be released by the vendor. Pick up the
1259required aggregate such that the project schedule
1266will be maintained. Payment to the vendor by the
1275Contractor will be due upon receipt of the
1283materials pursuant to the Department's Vendor
1289Contract No. BDH50. This rate is the unit price
1298agreed upon by the Department and the vendor and
1307will be made available to bid proposal holders at
1316the time of bid at
1321http://www.dot.state.fl.us/construction/aggregate
1322/aggregate.htm.
1323The Department will make payment to the
1330Contractor for the aggregates on progress
1336estimates as a part of the bid unit price for the
1347appropriate pay items. The rate is subject to
1355change and adjustments for such changes will be
1363made to the bid unit price of the appropriate pay
1373items.
1374Disputes with the vendor concerning
1379aggregate supply will not be cause for Contract
1387time adjustments, time suspensions or monetary
1393adjustments to the Contract amount. The
1399Contractor will be solely responsible for
1405providing the necessary advance notice to the
1412vendor and other coordination to obtain timely
1419aggregate supply for the project.
14248. The import of Developmental Specification 6-3.3.1 was
1432that all bidders would be required to obtain the limerock needed
1443for Base Group 09 from a single vendor, Vulcan Construction
1453Materials LP ("Vulcan"). The winning bidder would agree to pay
1465Vulcan in accordance with a separate contract negotiated between
1474Vulcan and the Department.
14789. The hyperlink provided in Developmental Specification
14856-3.3.1 3 led to a document called "Aggregate Guidance" produced
1495by the Department's State Construction Office. The front page
1504of the Aggregate Guidance document contained "Bidder
1511Information" consisting of a spreadsheet setting forth the
1519Vulcan price per ton for limerock base and limestone coarse
1529aggregate, with the price varying depending on the date and port
1540of delivery. Between January and June 2008, the Vulcan price
1550per ton for limerock base from both the Port of Tampa and Port
1563Canaveral was $16.93.
156610. The Aggregate Guidance page contained additional
1573hyperlinks with the following titles: "Aggregate Vendor Contract
1581Usage," "Aggregate Vendor Contract," "Aggregate Vendor Projects
1588List," "Aggregate Vendor Authorization Letter," "Aggregate
1594Vendor Contract Frequently Asked Questions," and "Aggregate
1601Price Adjustment Sheet."
160411. Alvin Mulford is the vice-president of Mid-State who,
1613along with his estimator, put together his company's bid for
1623Contract T1285. Mr. Mulford testified that his company has been
1633bidding on Department work, and that he has never before seen a
1645provision similar to Developmental Specification 6-3.3.1.
1651Mr. Mulford directed his estimator to obtain clarification from
1660the Department, to be sure that the bidders were required to
1671purchase the limerock base from Vulcan.
167712. One reason for Mr. Mulford's concern was the
"1686exorbitant" rate charged by Vulcan in comparison to other
1695vendors. The restriction to a single supplier was so abnormal,
1705and that supplier's rate was so out of line with the market,
1717that Mr. Mulford decided to seek guidance from the Department
1727through the question and response internet bulletin board
1735provided by the Department for its projects.
174213. The question posed by Mid-State was as follows:
1751Does the contractor have to use Vulcan
1758materials for the limerock base at a rate of
1767$16.93 per ton as stated in the
1774Developmental Specifications 6-3.3.1? If so
1779from which location is the material to be
1787picked up? Is it also true that payment to
1796the vendor (Vulcan Materials) will be due
1803immediately upon receipt of the materials?
1809I wanted to clarify this issue as it is
1818unusual for the contractor to be limited to
1826the use of only one vendor.
183214. The Department's response was as follows:
1839The unit rate for the Material can be found
1848at the following website:
1852http://www.dot.state.fl.us/construction/
1853Aggregate/Aggregate.htm
1854Pickup locations for the Material can be
1861found at the following website:
1866http://www.dot.state.fl.us/construction/
1867Aggregate/Aggregate.htm
1868Payment should be issued by the Contractor
1875to the Vendor (Vulcan Construction
1880Materials LP) upon receipt of the materials
1887as defined in Developmental Specification
18926-3.3.1.
189315. Because the Department's response did no more than
1902redirect him to the Department's website, Mr. Mulford decided to
1912look at the website in more detail. He investigated the
1922hyperlinks, including the Vulcan contract with the Department.
1930When he clicked on the hyperlink titled "Aggregate Vendor
1939Contract Usage," he found a document that provided as follows,
1949in relevant part:
1952Aggregate Vendor Contract Usage by Districts
1958With the execution of the contract with
1965Vulcan Construction Materials LP, contract
1970number BDH50, Vulcan has committed to
1976provide aggregate in the types and
1982quantities defined in the contract
1987(attached).
1988The process for this contract in Districts
19951, 5, and 7, is as follows:
20021. Include in the projects identified in
2009the attached spreadsheet the appropriate
2014special provision beginning with the July
20202007 lettings. The District Specifications
2025Engineer and District Construction Office
2030will need to coordinate this effort.
20362. There are two special provisions for the
2044purpose of notifying construction contract
2049bidders of the Department's intention toward
2055the aggregate. The first special provision
2061is the mandatory version that will direct
2068the bidder to obtain aggregates for the
2075specified work from Vulcan. The second
2081special provision provides the bidder an
2087option to obtain its aggregates from Vulcan.
2094* * *
20975. After these projects have been awarded,
2104the contractor is required to notify FDOT
2111and Vulcan a schedule of its aggregate needs
2119for the project. After receiving this
2125schedule, FDOT's Resident Engineer will
2130issue written authorization to the
2135contractor, with copy to Vulcan. This
2141authorization is required before Vulcan will
2147release aggregate to the contractor.
21526. Payment to Vulcan will be from the
2160contractor. FDOT will pay cost of aggregate
2167on progress estimates as part of the
2174contractor's bid price for the work.
2180The contractor is required to include in its
2188bid price for the work the cost of the
2197aggregate at the Vulcan rate. The Vulcan
2204rate will be posted on the FDOT State
2212Construction Website showing the rate. When
2218adjustments are made to the Vulcan rate,
2225FDOT will make adjustments in the
2231construction contract unit price. . . .
2238(Emphasis added.)
224016. Mr. Mulford testified that he understood the
2248underscored language in the hyperlinked document to be a
2257directive to the bidders and therefore a mandatory requirement
2266of the bid specifications. He did not ask the Department for
2277further clarification because he believed the requirement was
2285clearly stated in the hyperlinked document.
229117. David Sadler, the director of the Department's office
2300of construction, testified that the hyperlinked document was
2308developed by his office to offer guidance to the districts as to
2320the concept behind and use of the aggregate vendor contract.
2330The document was not a part of the bid solicitation document.
234118. Mid-State's bid price was $7,429,398.44. Mid-State's
2350price for Base Group 09 was $619,645.80, or $19.30 per square
2362yard. This price reflected the Vulcan rate for limerock base of
2373$16.92 plus tax and Mid-State's costs for the work associated
2383with Base Group 09.
238719. K & R's bid price was $7,370,505.24, or $58,893.20
2400lower than the bid price of Mid-State. K & R's price for Base
2413Group 09 was $256,848.00, based on a stated unit price of $8.00
2426per square yard for limerock base. K & R's price for Base
2438Group 09 was $362,797.80 lower than that of Mid-State,
2448accounting for more than the differential between the overall
2457bids of Mid-State and K & R.
246420. Marcus Tidey, Jr., K & R's vice president in charge of
2476its Florida division, testified that K & R was well aware that
2488the Vulcan price for limerock base was $16.93, and that K & R
2501understands its obligation to pay that price to Vulcan should
2511K & R be awarded Contract T1285. Mr. Tidey testified that at
2523the time of bid submission, he cut K & R's bid price to $8.00
2537per square yard as a competitive strategy to win the contract.
2548Mr. Tidey made a conscious decision that K & R would absorb the
2561difference between $8.00 bid price and the Vulcan price of
2571$16.93.
257221. Mr. Tidey testified that K & R needed to win this job
2585in order not to have its crews and equipment sit idle during the
2598economic downturn, and therefore decided to take all of its
2608markup, roughly $250,000, out of the bid. He could have made
2620the $250,000 cut on any item or items in the bid, but decided on
2635Base Group 09 because the limerock base was a big item and
2647therefore easy to cut by a large amount.
265522. Mr. Tidey also testified that the contract provides a
2665$400,000 incentive payment for early completion of the job,
2675meaning that K & R will be able to work "faster and smarter" and
2689make up for the price reduction at the end of the job.
270123. Mr. Tidey testified that he obtained the Vulcan prices
2711from the Department's website as instructed by Developmental
2719Specification 6-3.3.1. He did not click on the hyperlinks,
2728which appeared to reference the contract between the Department
2737and Vulcan and therefore was of no concern to him.
274724. The Department and K & R dispute Mid-State's assertion
2757that the underscored language of the hyperlink set forth in
2767Finding of Fact 15 was a requirement of the bid specifications,
2778based on Mr. Sadler's direct testimony and the underlying
2787illogic and unfairness of requiring bidders to seek out hidden
2797specifications. The Department and K & R concede that if the
2808bid specifications did in fact require the bidders to include in
2819Base Group 09 the full costs associated with obtaining the
2829limerock base from Vulcan, then K & R's bid is nonresponsive.
284025. Developmental Specification 6-3.3.1 directed bidders
2846to the Department's webpage for the purpose of obtaining the
2856current Vulcan rate quote. It did not instruct the bidders to
2867investigate the hyperlinks or to assume that the information
2876contained therein was mandatory. Absent an instruction to
2884bidders to review the information contained in the hyperlinks,
2893the Department could not make such information mandatory without
2902placing less curious bidders at a competitive disadvantage. The
2911Department had no intent to play hide-and-seek with the bid
2921specifications in the manner suggested by Mid-State.
292826. In addition, K & R points to three line items of the
2941bid specifications in which the Department eliminates
2948competition, instructing the bidders not to bid and inserting a
2958fixed unit price and bid amount for all bidders as to those
2970items. K & R reasonably asserts that the Department was fully
2981capable of treating Base Group 09 in the same fashion, had it
2993intended to require the bidders to pass through to the
3003Department all the costs associated with obtaining the limerock
3012base from Vulcan. However, the Department supplied the bid
3021quantity (31,106 square yards) and left it to the bidders to
3033determine the price per unit they would bid.
304127. K & R's bid was responsive. Nothing in the bid
3052specifications prevented K & R from absorbing part of the cost
3063of the Vulcan limerock base and passing the savings on to the
3075Department, or required bidders to pass on to the Department the
3086full costs of complying with the bid specifications regarding
3095Base Group 09.
309828. The sole remaining issue is whether K & R's bid,
3109though facially responsive, was materially unbalanced. The
3116Department routinely conducts reviews of bid line items that
3125appear "unbalanced," i.e., for which there appear to be
3134significant differences between the price bid and the
3142Department's cost estimate, in order to determine whether the
3151price difference is due to a quantity error by the bidder. The
3163Department's review confirms that the bid quantity specified on
3172the bid blank is accurate.
317729. If a quantity error is found, the bids are
3187recalculated using the bidders' unit prices and the correct
3196quantities to determine whether the bid rankings would change.
3205A bid for which there is a discrepancy between the bid and the
3218Department's estimate is termed "mathematically unbalanced." A
3225mathematically unbalanced bid that affects the ranking of the
3234low bid is "materially unbalanced." A mathematically unbalanced
3242bid is acceptable, but a materially unbalanced bid affords the
3252bidder an unfair competitive advantage and must be rejected.
326130. The Department followed its usual procedure in
3269analyzing the K & R bid to determine whether it was unbalanced.
3281Philip Gregory Davis, the Department's state estimates engineer,
3289testified that there were some unbalanced items in the K & R
3301bid, but no quantity errors that would have changed the ranking
3312of the bids.
331531. Richard Ryals, the project designer who conducted the
3324unbalanced bid review, testified that the quantities were
3332correct for Base Group 09. As noted above, K & R's low bid for
3346Base Group 09 was an intentional strategy, not the result of a
3358quantity error.
336032. K & R's current bonded capacity qualification with the
3370Department is $258 million in contracts at any one time. K & R
3383posted a bid bond, and has more than enough capacity to
3394comfortably perform this contract. There is no economic danger
3403to the Department in accepting K & R's low bid.
3413CONCLUSIONS OF LAW
341633. The Division of Administrative Hearings has
3423jurisdiction over the parties to and subject matter of this
3433cause, pursuant to Section 120.569 and Subsection 120.57(3),
3441Florida Statutes.
344334. Subsection 120.57(3)(f), Florida Statutes, provides in
3450pertinent part:
3452. . . . Unless otherwise provided by
3460statute, the burden of proof shall rest with
3468the party protesting the proposed agency
3474action. In a competitive-procurement
3478protest, other than a rejection of all bids,
3486proposals, or replies, the administrative
3491law judge shall conduct a de novo proceeding
3499to determine whether the agency's proposed
3505action is contrary to the agency's governing
3512statutes, the agency's rules or policies, or
3519the solicitation specifications. The
3523standard of proof for such proceedings shall
3530be whether the proposed agency action was
3537clearly erroneous, contrary to competition,
3542arbitrary, or capricious. . . .
354835. Pursuant to Subsection 120.57(3)(f), Florida Statutes,
3555the burden of proof rests with Mid-State as the party opposing
3566the proposed agency action to prove "a ground for invalidating
3576the award." See State Contracting and Engineering Corp. v.
3585Department of Transportation , 709 So. 2d 607, 609 (Fla. 1st DCA
35961998). Mid-State must prove by a preponderance of the evidence
3606that the Department's proposed award of the contract to K & R is
3619arbitrary, capricious, or beyond the scope of the Department's
3628discretion as a state agency. Department of Transportation v.
3637Groves-Watkins Constructors , 530 So. 2d 912, 913-914 (Fla.
36451988); Department of Transportation v. J.W.C. Co., Inc. , 396
3654So. 2d 778, 787 (Fla. 1st DCA 1981). See also § 120.57(1)(j),
3666Fla. Stat.
366836. The First District Court of Appeal has interpreted the
3678process set forth in Subsection 120.57(3)(f), Florida Statutes,
3686as follows:
3688A bid protest before a state agency is
3696governed by the Administrative Procedure
3701Act. Section 120.57(3), Florida Statutes
3706(Supp. 1996) [4] provides that if a bid
3714protest involves a disputed issue of
3720material fact, the agency shall refer the
3727matter to the Division of Administrative
3733Hearings. The administrative law judge must
3739then conduct a de novo hearing on the
3747protest. See § 120.57(3)(f), Fla. Stat.
3753(Supp. 1996). In this context, the phrase
" 3760de novo hearing" is used to describe a form
3769of intra-agency review. The judge may
3775receive evidence, as with any formal hearing
3782under section 120.57(1), but the object of
3789the proceeding is to evaluate the action
3796taken by the agency. See Intercontinental
3802Properties, Inc. v. Department of Health and
3809Rehabilitative Services , 606 So. 2d 380
3815(Fla. 3d DCA 1992) (interpreting the phrase
" 3822de novo hearing" as it was used in bid
3831protest proceedings before the 1996 revision
3837of the Administrative Procedure Act).
3842State Contracting and Engineering Corp. , 709 So. 2d at 609.
385237. As outlined in Subsection 120.57(3)(f), Florida
3859Statutes, the ultimate issue in this proceeding is "whether the
3869agency's proposed action is contrary to the agency's governing
3878statutes, the agency's rules or policies, or the bid or proposal
3889specifications." In addition to proving that the Department
3897breached this statutory standard of conduct, Mid-State also must
3906establish that the Department's violation was either clearly
3914erroneous, contrary to competition, arbitrary, or capricious.
3921§ 120.57(3)(f), Fla. Stat.
392538. The First District Court of Appeal has described the
"3935clearly erroneous" standard as meaning that an agency's
3943interpretation of law will be upheld "if the agency's
3952construction falls within the permissible range of
3959interpretations. If, however, the agency's interpretation
3965conflicts with the plain and ordinary intent of the law,
3975judicial deference need not be given to it." Colbert v.
3985Department of Health , 890 So. 2d 1165, 1166 (Fla. 1st DCA 2004)
3997(Citations omitted).
399939. An agency decision is "contrary to competition" when
4008it unreasonably interferes with the objectives of competitive
4016bidding. Those objectives have been stated to be:
4024[T]o protect the public against collusive
4030contracts; to secure fair competition upon
4036equal terms to all bidders; to remove not
4044only collusion but temptation for collusion
4050and opportunity for gain at public expense;
4057to close all avenues to favoritism and fraud
4065in various forms; to secure the best values
4073for the [public] at the lowest possible
4080expense; and to afford an equal advantage to
4088all desiring to do business with the
4095[government], by affording an opportunity
4100for an exact comparison of bids.
4106Harry Pepper & Associates, Inc. v. City of Cape Coral , 352
4117So. 2d 1190, 1192 (Fla. 2d DCA 1977), quoting Wester v. Belote ,
4129138 So. 2d 721, 723-724 (Fla. 1931).
413640. An agency action is capricious if the agency takes the
4147action without thought or reason or irrationally. An agency
4156action is arbitrary if is not supported by facts or logic. See
4168Agrico Chemical Co. v. Department of Environmental Regulation ,
4176365 So. 2d 759, 763 (Fla. 1st DCA 1978).
418541. To determine whether an agency acted in an arbitrary
4195or capricious manner, it must be determined "whether the agency:
4205(1) has considered all relevant factors; (2) has given actual,
4215good faith consideration to those factors; and (3) has used
4225reason rather than whim to progress from consideration of these
4235factors to its final decision." Adam Smith Enterprises v.
4244Department of Environmental Regulation , 553 So. 2d 1260, 1273
4253(Fla. 1st DCA 1989).
425742. However, if a decision is justifiable under any
4266analysis that a reasonable person would use to reach a decision
4277of similar importance, the decision is neither arbitrary nor
4286capricious. Dravco Basic Materials Co., Inc. v. Department of
4295Transportation , 602 So. 2d 632, 634, n. 3 (Fla. 2d DCA 1992).
430743. Mid-State failed to meet its burden of proof. The
4317evidence presented at the hearing did not establish that the
4327Department's proposed award of Contract T1285 to K & R is
4338contrary to the bid solicitation, contrary to the Department's
4347governing statutes, rules or policies, or that the proposed
4356award is clearly erroneous, contrary to competition, arbitrary
4364or capricious. The preponderance of the evidence established
4372that K & R's proposal was responsive to the requirements of the
4384bid solicitation and that the Department acted well within its
4394governing statutes, rules and policies.
439944. The evidence at hearing established that the
4407Department has in place routine procedures for the review of bid
4418items that appear mathematically imbalanced, and that the
4426Department followed these procedures in determining that K & R's
4436bid was not materially imbalanced.
444145. The evidence established that Developmental
4447Specification 6-3.3.1 required bidders to purchase aggregates
4454for use in the limerock base from Vulcan, and that K & R
4467complied with this requirement.
447146. The evidence established that Mid-State misinterpreted
4478an informational hyperlink on the Department's website to be a
4488mandatory bid specification. The bid specifications did not
4496require the bidders to include in Base Group 09 the full costs
4508associated with obtaining the limerock base from Vulcan. K & R
4519was not prohibited from bidding a discounted rate for Base
4529Group 09.
4531RECOMMENDATION
4532Based upon the foregoing Findings of Fact and Conclusions
4541of Law set forth herein, it is
4548RECOMMENDED that the Department of Transportation enter a
4556final order dismissing Mid-State's formal written protest and
4564awarding Contract T1265 to K & R.
4571DONE AND ENTERED this 9th day of January, 2009, in
4581Tallahassee, Leon County, Florida.
4585S
4586LAWRENCE P. STEVENSON
4589Administrative Law Judge
4592Division of Administrative Hearings
4596The DeSoto Building
45991230 Apalachee Parkway
4602Tallahassee, Florida 32399-3060
4605(850) 488-9675 SUNCOM 278-9675
4609Fax Filing (850) 921-6847
4613www.doah.state.fl.us
4614Filed with the Clerk of the
4620Division of Administrative Hearings
4624this 9th day of January, 2009.
4630ENDNOTES
46311/ A typographical error in the order referenced the
4640Department's filing as a "proposed final order."
46472/ Florida Administrative Code Rule 14-103.001 provides the
4655scope of the referenced Chapter 14-103:
4661This rule chapter provides the requirements
4667and procedures for obtaining and maintaining
4673Department approval of developed and
4678operational construction aggregate sources
4682(mines and redistribution terminals) and
4687their individual construction aggregate
4691products which are intended for use on
4698Department projects. Department approval is
4703based upon the existence of suitable raw
4710materials; processing facilities capable of
4715producing specified aggregate meeting
4719Department specification requirements; and
4723an effective Quality Control Program
4728assuring the continuing quality and
4733uniformity of that production.
4737Florida Administrative Code Rule 14-103.002(1) sets forth
4744the purpose of Chapter 14-103:
4749This rule chapter sets out a standardized
4756method for producers of construction
4761aggregates to apply for, receive, and
4767maintain Department approval of construction
4772aggregate sources for use on Department
4778projects. Source and product approval, and
4784maintenance of an on-going effective Quality
4790Control Program, as monitored by the
4796Departments Quality Assurance procedures,
4800comprise the Departments primary methods of
4806determining acceptability of aggregate on
4811Department projects.
48133/ The hyperlink provided in the specification is either
4822outdated or contained a typographical error at the time the
4832specifications were published. The correct hyperlink is:
4839http://www.dot.state.fl.us/construction/Aggregate/Aggregate.shtm
48404/ The meaning of the operative language has remained the same
4851since its adoption in 1996:
4856In a competitive-procurement protest, no
4861submissions made after the bid or proposal
4868opening amending or supplementing the bid or
4875proposal shall be considered. Unless
4880otherwise provided by statute, the burden of
4887proof shall rest with the party protesting
4894the proposed agency action. In a
4900competitive-procurement protest, other than
4904a rejection of all bids, the administrative
4911law judge shall conduct a de novo proceeding
4919to determine whether the agency's proposed
4925action is contrary to the agency's governing
4932statutes, the agency's rules or policies, or
4939the bid or proposal specifications. The
4945standard of proof for such proceedings shall
4952be whether the proposed agency action was
4959clearly erroneous, contrary to competition,
4964arbitrary, or capricious. . . .
4970§ 120.57(3)(f), Fla. Stat. (1997).
4975COPIES FURNISHED :
4978James C. Myers,
4981Clerk of Agency Proceedings
4985Department of Transportation
4988Haydon Burns Building
4991605 Suwannee Street, Mail Station 58
4997Tallahassee, Florida 32399-0450
5000Alexis M. Yarbrough, General Counsel
5005Department of Transportation
5008Haydon Burns Building
5011605 Suwannee Street, Mail Station 58
5017Tallahassee, Florida 32399-0450
5020Stephanie Kopelousos, Secretary
5023Department of Transportation
5026Haydon Burns Building
5029605 Suwannee Street, Mail Station 57
5035Tallahassee, Florida 32399-0450
5038C. Denise Johnson, Esquire
5042Department of Transportation
5045Haydon Burns Building, Mail Station 58
5051605 Suwannee Street
5054Tallahassee, Florida 32399-0450
5057Alvin Mulford
5059Mid-State Paving Co., Inc.
5063347 Bolender Road
5066Auburndale, Florida 33823
5069George E. Spofford, IV, Esquire
5074Glenn, Rasmussen, Fogarty & Hooker, P.A.
5080Post Office Box 3333
5084Tampa, Florida 33601-3333
5087James M. McCrae, Esquire
5091Law Office of Jim McCrae
5096Lake Mary Professional Campus
51001349 International Parkway South
5104Suite 2421
5106Lake Mary, Florida 32746
5110NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5116All parties have the right to submit written exceptions within
512610 days from the date of this Recommended Order. Any exceptions
5137to this Recommended Order should be filed with the agency that
5148will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 01/09/2009
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 11/18/2008
- Proceedings: Letter to Judge Stevenson from G. Spofford regarding receipt of Judge`s Order dated November 14, 2008 filed.
- PDF:
- Date: 11/12/2008
- Proceedings: Letter to Judge Stevenson from George Spofford regarding filing of proposed recommended orders filed.
- PDF:
- Date: 11/12/2008
- Proceedings: Kamminga & Roodvoets, Inc.`s Proposed Findings of Facts and Conclusions of Law filed.
- PDF:
- Date: 11/12/2008
- Proceedings: Order (Petitioner shall file its proposed recommended order by November 14, 2008).
- PDF:
- Date: 11/12/2008
- Proceedings: Objection to Mid-state Paving Co., Inc.`s Motion for Extension of Time and Motion to Strike Mid-state`s Proposed Order filed.
- PDF:
- Date: 11/10/2008
- Proceedings: Motion for Extension of Time to File Proposed Recommended Order filed.
- PDF:
- Date: 11/07/2008
- Proceedings: Notice of Filing Exhibits A, B, C and Tidey Exhibit 5 to the October 10, 2008 Deposition of David A. Sadler filed.
- PDF:
- Date: 10/29/2008
- Proceedings: Mid-state Paving Co., Inc. Formal Bid Protest and Exhibits (exhibits not available for viewing) filed.
- Date: 10/29/2008
- Proceedings: Transcript of Hearing filed.
- Date: 10/14/2008
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 10/14/2008
- Proceedings: Notice of Filing (Department of Transportation`s Ansers to Mid-State Paving Cor., Inc.`s First Set of Interrogatories).
- PDF:
- Date: 10/13/2008
- Proceedings: Pre-hearing Statement Jointly Between Department of Transportation and Kamminga & Roodvoets filed.
- PDF:
- Date: 10/10/2008
- Proceedings: Notice of Filing (Department of Transportation`s Answers to Mid-State Paving Co., Inc.`s First Set of Interrogatories) filed.
- PDF:
- Date: 10/07/2008
- Proceedings: Amended Notice of Hearing (hearing set for October 14 and 15, 2008; 9:30 a.m.; Bartow, FL; amended as to Room).
- PDF:
- Date: 09/24/2008
- Proceedings: Notice of Service of Answers to Petitioner`s First Set of Interrogatories filed.
- PDF:
- Date: 09/24/2008
- Proceedings: Kamminga & Roodvoets, Inc.`s Response to Petitioner`s Request for Production of Documents filed.
- PDF:
- Date: 09/10/2008
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for October 14 and 15, 2008; 9:00 a.m.; Bartow, FL).
- PDF:
- Date: 09/10/2008
- Proceedings: Notice of Serving Respondent, Department of Transportation`s, First Set of Interrogatories to Petitioner filed.
Case Information
- Judge:
- LAWRENCE P. STEVENSON
- Date Filed:
- 08/28/2008
- Date Assignment:
- 08/29/2008
- Last Docket Entry:
- 01/29/2009
- Location:
- Bartow, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
C. Denise Johnson, Esquire
Address of Record -
Alvin Mulford
Address of Record -
George E Spofford, IV, Esquire
Address of Record -
C. Denise Johnson, Assistant General Counsel
Address of Record