09-000948
Thomas L. Sheehey vs.
Michael Chbat And Department Of Environmental Protection
Status: Closed
Recommended Order on Thursday, January 14, 2010.
Recommended Order on Thursday, January 14, 2010.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8THOMAS L. SHEEHEY, )
12)
13Petitioner, )
15)
16vs. ) Case No. 09-0948
21)
22MICHAEL CHBAT AND DEPARTMENT OF )
28ENVIRONMENTAL PROTECTION, )
31)
32Respondents. )
34)
35RECOMMENDED ORDER
37This case was heard by David M. Maloney, Administrative Law
47Judge of the Division of Administrative Hearings, on
55September 14 and 15, 2009, in Shalimar, Florida.
63APPEARANCES
64For Petitioner Thomas L. Sheehey:
69David Michael Chesser, Esquire
73Chesser & Barr, P.A.
771201 Eglin Parkway
80Shalimar, Florida 32579
83For Respondent Michael Chbat:
87John L. Wharton,Esquire
91Frederick L. Aschauer, Jr., Esquire
96Rose, Sundstrom & Bentley, LLP
1012548 Blairstone Pines Drive
105Tallahassee, Florida 32301
108For Respondent Department of Environmental Protection:
114Amanda Gayle Bush, Esquire
118Department of Environmental Protection
122Office of the General Counsel
1273900 Commonwealth Boulevard, Mail Stop 35
133Tallahassee, Florida 32399-3000
136STATEMENT OF THE ISSUE
140Whether Michael Chbat's 2008 application for a Wetland
148Resource Permit (WRP) to construct a culvert extension across
157his property in Walton County, Florida, should be approved?
166PRELIMINARY STATEMENT
168This proceeding concerns a permit the Department of
176Environmental Protection (the "Department" or "DEP") denominated
184an "Amended Wetland Resource Permit", (the "Amended Permit").
193It was issued by DEP on December 19, 2008, to Michael Chabat
205("Chabat" or "Respondent Chabat").
211Eighteen days after the Amended Permit's issuance,
218Thomas L. Sheehey ("Petitioner" or "Sheehey") filed with DEP a
230Petition for Formal Administrative Hearing challenging it.
237The Department referred the petition to the Division of
246Administrative Hearings (DOAH) and asked that an administrative
254law judge be designated to conduct the proceeding. The petition
264was assigned Case No. 09-0948.
269Chbat filed a motion to dismiss that was granted. Sheehey
279filed an amended petition on May 14, 2009. The case was set for
292hearing on the amended petition in August of 2009 and re-set to
304commence on September 14, 2009.
309Five days prior to the hearing, on September 9, 2009, Chbat
320and the Department filed a motion in limine. The motion sought
331an order that would prevent Petitioner from entering evidence
340that would support a bar both to Chbat's application and the
351issuance of the Amended Permit by operation of the doctrine of
362res judicata . The motion also sought to preclude any evidence
373that DEP was required to enforce a settlement agreement entered
383in March of 2007 between Mr. Sheehey and Mr. Chbat.
393On the next day, September 10, 2009, the parties filed a
404Joint Pre-hearing Stipulation. The stipulation made reference
411to the subject of the motion in limine. Listed among the facts
423which remain to be litigated was: "Whether the Amended Wetland
433Resource Permit presents any new issues from those contested and
443settled in the original permit issued May 9, 2007, Number 66-
4540235320-001-DF." Joint Pre-hearing Stipulation , at 16. Along
461the same line, the stipulation listed among the issues of law
472which remained to be litigated: "Whether or not the Proposed
482Amended Permit is res judicata ." Id. at 17.
491The case proceeded to final hearing as scheduled on
500September 14, 2009. At the outset, DEP and Chabat's motion in
511limine was argued by the parties. A ruling was entered that res
523judicata was not applicable to the proceeding and that the
533settlement agreement entered in March of 2007 could not be
543enforced in this proceeding to require the Department to reject
553Chbat's application or deny the Amended Permit. The settlement
562agreement, however, was not excluded from the record or as
572evidence; it was allowed to be introduced as background.
581As the applicant with the burden of proof, Chbat proceeded
591first. Three witnesses testified in the case-in-chief: Michael
599Chbat, Petitioner; Mark Thomasson, P.E., accepted as an expert
608in stormwater engineering; and, Larry O'Donnell, an
615Environmental Manager in the Department's Wetland Resource
622Permitting Program.
624Chbat offered ten exhibits into evidence. Marked for
632identification as Chbat Exs. 1-10, all were admitted. Two of
642the ten exhibits, Chbat 9 and 10, were depositions of Les
653Porterfield, P.E., president and owner of Porterfield
660Engineering; and Clifford Street, P.E., the Department's
667Supervisor for Engineering Support for Submerged Lands and
675Environmental Resources Program of the Northwest District, both
683of whom testified at the final hearing.
690The Department proceeded next. It presented two witnesses:
698Mr. O'Donnell, who was re-called and accepted as an expert in
709the application of state rules and statutes in wetland resource
719permitting; and Mr. Street, accepted as an expert in stormwater
729engineering. The Department offered two exhibits, Deptartment
736Exhibits 1 and 2 which were admitted into evidence.
745Petitioner proceeded after the Department. Testimony was
752accepted from four of the witnesses Petitioner presented:
760Thomas Eugene Cummins, a resident of Lot 5 in La Grange Bayou;
772Thomas Sheehey, Petitioner and resident of Lot 8 in La Grange
783Bayou; Mr. Porterfield, accepted as an expert in stormwater
792engineering and wetland permitting; and, Todd Wilkinson, vice
800president of Environmental Services, Inc., accepted as an expert
809in the application of state rules and statutes in wetland
819permitting and also in the field of marine biology. Mr. Sheehey
830also presented the testimony of Ms. Julie Dickinson, a DEP
840environmental supervisor with the Department's Wetland Program.
847The testimony of Ms. Dickinson, however, was stricken.
855Petitioner offered 11 exhibits into evidence, marked for
863identification as Petitioner's Exhibits 1-11. All were
870admitted.
871After the conclusion of Petitioner's case, Chbat re-called
879himself as a witness and presented the live testimony of
889Mr. Street in rebuttal.
893The three-volume transcript of the hearing was filed on
902October 26, 2009. It was ordered that proposed recommended
911orders were due on November 30, 2009. A joint motion for
922extension of the time to file proposed recommended orders was
932filed on the basis of errors in the transcript. On December 7,
9442009, an order was entered giving the parties until December 11,
9552009 to file their proposed orders. The next day a corrected
966volume of the transcript was filed. The parties all timely
976filed Proposed Recommended Orders, which have been considered in
985the preparation of this Recommended Order.
991FINDINGS OF FACT
994La Grange Bayou Estates
9981. La Grange Bayou Estates is a residential subdivision in
1008Freeport, Walton County, Florida.
10122. The subdivision lies to the north of the shoreline of
1023Choctawhatchee Bay. It can be viewed as divided roughly in half
1034between bayfront lots south of an east-west road that transects
1044the subdivision and lots that are north of the road.
10543. The subdivision is platted and the plat is in the
1065public records of Walton County. Filed with the Clerk of the
1076Circuit Court in and for Walton County, Florida, on
1085September 15, 1982, the plat ("the 1982 Plat") shows 29
1097residential lots in the subdivision as of that date. See
1107Petitioner's Ex. 6.
11104. Lots 1 through 16, according to the 1982 Plat, are the
1122bayfront lots, south of a 40-foot wide road designated as a
1133private road in the plat. That road is now known as Alden Lane.
11465. Wetlands over which the Department has jurisdiction
1154("jurisdictional wetlands") comprise much of the southern
1163portion of bayfront lots and the drainage easement. Among the
1173bayfront lots are both Lot 9 which belongs to Mr. Chbat and Lot
11868 which belongs to Mr. Sheehey. A 50-foot easement lies between
1197Lot 9 and Lot 8 and is described more fully below. The presence
1210of jurisdictional wetlands on Mr. Chbat's lot over which he
1220hopes to install the culvert extension requires that he obtain a
1231WRP.
12326. To the north of Alden Lane are lots numbered by the
12441982 Plat as 17 through 29. The lots are served by Alden Lane
1257and, in what is roughly the northeast quadrant of the
1267subdivision, by two other roads. One of the roads is shown on
1279the 1982 Plat as a "40' PRIVATE ROAD." Id. A 2006 aerial
1291photograph introduced into evidence by Chbat designates the road
"1300unnamed." See Chbat Ex. 5. The other is designated as a
"1311graded county road," on the 1982 Plat. By 2006, it had come to
1324be known as Beatrice Point Road. Id.
13317. Beatrice Point Road transects a pond that runs roughly
1341340 feet (excluding about 30 feet of roadway) in a northeasterly
1352direction from Alden Lane to the southern edge of an area north
1364of the subdivision shown on the 1982 Plat to be un-platted. The
1376pond is most likely the result of a "borrow pit" dug in order to
1390obtain fill for the construction of the roads when the
1400subdivision was initially developed.
14048. The southern boundary of the pond lies along
1413approximately 140 feet of Alden Lane's northern edge. The pond
1423is across the street from Lots 9, 10 and 11 of the subdivision.
1436The pond is also not far northeast of the 50-foot easement (the
"1448Drainage Easement") between Lots 9 and 8.
1456The Drainage Easement
14599. The Drainage Easement is just to the west of Lot 9. It
1472is noted on the 1982 Plat as a "50' EASEMENT (PRIVATE)." Id.
1484The 50-foot wide Drainage Easement runs the length of the
1494western boundary of Lot 9 and the length of the eastern boundary
1506of Lot 8. The northeast corner of the Drainage Easement is
1517approximately 30 feet from the southwest corner of the pond
1527separated from the pond by the roadway of Alden Lane.
153710. The eastern boundary of the Drainage Easement is
1546226.37 feet in length, or if taken to the middle of Alden Lane,
1559246.3 feet. The western boundary is 206.13 feet long or if
1570taken to the middle of the road, 226.65 feet.
157911. The purpose of the Drainage Easement, as is evident
1589from its denomination in this recommended order, is drainage.
1598As Mr. Street definitively put it at hearing, it is "now and
1610always has been intended to drain stormwater to the [B]ay."
1620Tr. Vol. III at 179.
162512. Mr. Street's opinion of the function of the Drainage
1635Easement is supported by drawings submitted by Mr. Chbat as part
1646of the WRP application.
165013. The drawings show that the Drainage Easement's
1658function is facilitated by three culverts north of the Easement
1668(referred to during the hearing as "pipes") each of which is
1680intended to direct stormwater at its point of discharge toward
1690the Drainage Easement. See Chbat Ex. 1.
169714. One of the culverts ("the Drainage Ditch Culvert")
1708serves a drainage ditch that is to the north of the Easement and
1721Alden Lane. According to the drawings, the drainage ditch lies
1731on the other side of the "un-named road" from the pond, that is,
1744to the west of the pond, and is some 40-to-50 feet north of the
1758Drainage Easement.
176015. The Drainage Ditch Culvert extends from the ditch to
1770the southern half of Alden Lane from where it appears from the
1782application's drawings that stormwater would be conveyed to the
1791western side of the Drainage Easement along it's border with Lot
18028 and on toward the Bay. In fact, it is a functioning culvert
1815that "conveys water from a swale on the side of the road into
1828the [D]rainage [E]asement." Tr. 64. Once in the Drainage
1837Easement, according to the drawings, the water should flow into
1847the Bay out of a "cut," id. , that is labeled on the drawings as
1861an "existing trench." See Chbat Ex. 1. The trench, however,
1871has been filled in with sand by tidal activity or sediment
1882deposited by stormwater or both. The trench has not been
1892maintained, and it no longer exists.
189816. The other two culverts (the "Pond Culverts") lie east
1909of the Drainage Ditch Culvert. They catch overflow from the
1919pond caused by stormwater and convey it under and through Alden
1930Lane toward the Drainage Easement.
193517. The westernmost Pond Culvert (the "Western Pond
1943Culvert") appears to terminate in Alden Lane near its southern
1954edge just north of the Easement. At the time of hearing,
1965however, it was not functioning properly. "[I]t is full of sand
1976and silted up . . .", tr. Vol. I at 58; "[t]he pipe to the west
1992is clogged and it is not functioning." Tr. Vol. I at 64. It is
2006also at an elevation that would keep it from serving drainage
2017purposes in all but the most severe storm events. See Chbat
2028Ex. 9 at 22.
203218. The other Pond Culvert, (the "Eastern Pond Culvert")
2042terminates in the northwest corner of Lot 9 at the border
2053between Lot 9 and the Drainage Easement about 10 feet southeast
2064of the terminus of the Western Pond Culvert. The Eastern Pond
2075Culvert is the culvert with which the Amended Permit is
2085concerned, that is, it is the culvert to be extended by the
2097permit. Calling it a "pipe," Mr. Street offered the following
2107about the assistance the Eastern Pond Culvert offers in
2116conveying stormwater into the Drainage Easement and down to the
2126Bay:
2127There is currently a pipe that discharges
2134into that easement. There
2138. . . was an attempt to place the water from
2149the . . . pond into the easement. And the
2159natural flow of water on this entire
2166property from the road to the [B]ay is north
2175to south. At some point, at least 2004,
2183that drainage easement contained a
2188conveyance at its southern end that would
2195safely discharge stormwater to the [B]ay.
2201Tr. Vol. III at 179-80.
2206Petitioner Sheehey and Lot 8
221119. Thomas Sheehey is the owner of Lot 8, where he has a
2224residence in which he makes his home. He has lived in the
2236residence approximately five years. During that time,
2243Mr. Sheehey has fished in the Bay and enjoyed the use of his
2256kayak and his waverunner on the Bay. He also enjoys "sitting
2267down having a cup of coffee and looking at it," tr. vol. III at
2281151, as well as watching his neighbors fish. The recreational
2291uses to which he puts the Bay is the reason he chose to purchase
2305a bayfront lot in La Grange Bayou Estates.
231320. Over the period of time that he has resided on Lot 8,
2326Mr. Sheehey has observed the effects of rain events on his lot
2338and well as lots close to Lot 8. He has also taken pictures of
2352his property and the near-by lots. Among the photographs were
2362four taken after rain events or "after a wet period," tr. vol.
2374III at 88, at some point in the last four years. The four
2387photos were introduced as a composite exhibit, Petitioner's Ex.
23962, with each photograph marked as 2A, 2B, 2C or 2D. Mr. Sheehey
2409could not specify when the pictures were taken in the past four
2421years other than that if a picture had a certain dock in it,
2434then it was taken after January of 2009.
244221. Petitioner's Ex. 2A was taken from Mr. Sheehey's lot
2452looking toward the Bay. It shows an area of the lot under water
2465separated from the Bay by a ridge.
247222. Petitioner's Ex. 2B is a picture taken from Lot 13
2483looking west across Lots 12, 11, 10, 9 "down through . . . 8."
2497Tr. Vol. III at 86. Much of what is photographed is among trees
2510and vegetation emerging from water standing above the surface of
2520the soil.
252223. Petitioner's Ex. 2C is a picture taken from Alden Lane
2533looking south across Mr. Chbat's property. It shows a wide
2543swath of water that extends from the road across most of the
2555property to the Bay. The water is either in a swale or
2567constitutes overflow outside the swale.
257224. The most recent of the four is Petitioner's Ex. 2D,
2583which shows the dock referred to by Mr. Sheehey that was built
2595in early 2009. It is a picture taken from Lot number 13 toward
2608the west through Lots 12, 11, 10, 9. Like the others, it shows
2621vegetation standing in water to the north of the Bay. Taken
2632together, the four pictures in Petitioner's Exhibit 2
2640demonstrate that significant portions of the lots depicted are
2649under water following sufficient amounts of recent rain.
265725. The four photographs that comprise Petitioner's
2664Exhibit 2 are not the only photos taken by Mr. Sheehey that were
2677introduced into evidence. Three other photographs of
2684Mr. Sheehey's, Petitioner's Exhibits 7A, 7B and 7C, were
2693admitted following testimony about them from a long-time
2701observer of the flow of water from Alden Lane to the Bay.
2713A Long-time Observer
271626. Thomas Eugene Cummins had lived in La Grange Estates
"2726[t]wo months shy of 20 years," tr. vol. III at 7, at the time
2740of his testimony. His house was the fourth to be constructed in
2752the subdivision.
275427. Over the two decades of his residence, the pond
2764between Alden Lane and the property north of the subdivision has
2775been in existence. Consistent with the drawings submitted to
2784DEP as part of the application, when asked where the pond
2795overflows today, Mr. Cummins answered "it drains under Alden
2804Lane on to Mr. Chbat's lot." Tr. Vol. III at 8.
281528. Asked by Mr. Chesser at hearing, "When the water comes
2826out of the pond, is it possible to know where it spreads?" 1/
2839Mr. Cummins testified:
2842On really heavy rains, I have watched the
2850normal color of the pond change from its
2858dark blackish gray color into the reddish
2865color that the clay has washed down into it,
2874flow under Alden Lane and on to Mr. Chbat's
2883lot, and then proceed west through the
2890wetland on lots eight, seven, six, and my
2898five, and turn reddish color even in my lot.
2907Tr. Vol. III at 9-10. Mr. Cummins knew the source of the "red
2920color" of the stormwater: red clay introduced to La Grange
2930Estates by the County half a decade earlier. Mr. Cummins
2940testified:
2941Beatrice Point Road, which is the road that
2949runs over the pond, about five years ago the
2958county did some repair on the road and
2966actually put red clay in certain spots to
2974even it out.
2977Tr. Vol. III at 9. Prior to the county's work on the road
2990referred-to by Mr. Cummins, there had been no red clay in the
3002neighborhood. Alden Way, for example, has no red clay. It is a
3014road composed of shell. The only red clay in the subdivision is
3026that which is on Beatrice Point Road.
303329. The water that runs onto Mr. Cummins' lot following a
3044heavy rain rises to as much as 12 inches. 2 / The water rises as
3059high as it does because it is held back by a naturally-occurring
3071land formation between the Bay and Mr. Cummins property. This
3081geo-formation was referred-to at hearing as the ridge line or
3091the ridge.
3093The Ridge
309530. The Ridge was described by Mr. Cummins as a vegetated
3106mass of earth that most of the time, even in heavy rains, sits
3119above the water that collects on the bayfront lots of La Grange
3131Estates.
313231. The Ridge prevents a substantial amount of stormwater
3141runoff from entering the Bay from the wetlands on the southern
3152portion of the subdivision's bayfront lots. For that reason,
3161the ridge is called "our upland, 3 / " tr. vol. III at 13, according
3175to Mr. Cummins. Between Lot 9 and Lot 5, the ridge varies in
3188width "anywhere between 10 feet . . . up toward Mr. Chbat's lot,
3201down to [Mr. Cummins'] lot where its around 30 or 40 feet
3213[wide.]" Id. (It may extend, in fact, across all of the
3224bayfront lots.) The ridge meanders not far from the shoreline.
3234Id. In some places it is as narrow as five feet. The height of
3248the ridge varies as well from as low as one foot to as high as
3263two and half feet.
326732. Mr. Street also testified about the Ridge, referring
3276to it in his testimony as a "ridge line":
3286Now, there is a ridge line, and there's been
3295a lot of testimony about this ridge line,
3303that it exists across all of the lots. My
3312testimony was, essentially, related to the
3318review that I did, which was primarily
3325associated with lots eight and nine, and the
3333drainage easement between them. And from
3339what I can tell, the elevation of that ridge
3348line is give or take three. Elevation
3355three, not a height of three. An elevation
3363of three. It could be lower, and perhaps,
3371is higher. And its subject to the vagaries
3379of a number of factors, flow of stormwater,
3387wave action, tidal influence, and the like.
3394And these accretions and depositions of sand
3401over time change that ridge line. And
3408sometimes, it opens up. And sometimes it
3415may not have a natural opening, depending on
3423where you are along that entire stretch of
3431beach.
3432* * *
3435[T]o the extent there is an opening in that
3444ridge line, water will flow naturally to the
3452bay.
3453Tr. Vol. III at 180-181. An "east west flow of water," tr. vol.
3466III at 181, along the bayfront lots, that is, a flow of water
3479either in an easterly direction or a westerly one is contrary to
3491the flow from Alden Lane north of the lots to the Bay south of
3505the lots. Whether flowing east or west, the water in the
3516southern portions of the bayfront lots is "controlled by the
3526ridge line." Id. In other words, stormwater that flows from
3536north to south across the bayfront lots, including Mr. Chbat's
3546and the Drainage Easement, is going to collect and begin to flow
3558from east to west or west to east at some point north of the
3572Ridge before it drains into the Bay. The only exception to
3583east-west flow, as made clear by Mr. Street, is when and if
3595there is an opening in the Ridge that allows the water otherwise
3607held back by the Ridge to flow southward into the Bay.
361833. The east-west flow of the water along the Ridge was
3629described at hearing as "unnatural." Id. In fact, it is not
3640un-natural. The Ridge is the cause of the east-west flow and,
3651as Mr. Street testified, the Ridge is the result of natural
3662processes such as tidal influence, wave action, accretion and
3671deposition of sand. 4 /
367634. The Ridge is shown in Petitioner's Exhibit 7A, 5 /
3687another photograph taken by Mr. Sheehey. The ridge as shown in
3698the picture is well vegetated and above water to its north and
3710higher than the Bay to its south. It is quite clear that if
3723there is no opening in the ridge to the Bay, stormwater north of
3736the ridge is forced to flow in east-west directions and is
3747prevented from flowing into the Bay.
375335. Petitioners' Exhibit 7B is a photograph of the
3762southern terminus of a swale ( see paragraphs 40 - 49, below) on
3775Mr. Chbat's property. It shows the swale cut through the Ridge.
3786Water, however, does not appear to be running from the end of
3798the swale into the bay. It appears that the end of the swale is
3812a few feet from the Bay separated by a narrow sandy area on the
3826shore. Nonetheless, the photograph shows that there is
3834potential for stormwater to flow from the swale when the swale
3845has more water in it.
385036. Petitioner's Exhibit 7C is a picture of the pond 6 /
3862across the street from Mr. Chbat's Lot 9.
3870Mr. Chbat and Lot 9
387537. Michael Chbat is the owner of Lot 9. He purchased the
3887lot "[t]o build a house on it." Tr. Vol. I at 22. Because he
3901has family close by (in Fort Walton Beach), Mr. Chbat expects to
3913use a house built on the lot for weekend visits. His ultimate
3925aspiration is to live in a house on Lot 9 after he retires from
3939his position as a construction engineer with the City of
3949Tallahassee.
395038. At hearing, Mr. Chbat described Lot 9 on the day he
3962bought it: "the lot was overgrown. It drained from north to
3973south. It had water standing on it. And it had a pipe [the
3986Eastern Pond Culvert] on the northwest corner discharging."
3994Tr. Vol. I at 23.
399939. He also described the state of the lot at the time of
4012hearing. The Eastern Pond Culvert on the northwest corner was
4022still there. The lot had been cleared to some extent to rid it
4035of invasive species. Overgrown vegetation was trimmed or
4043cleared to make room for a driveway permitted by the Department
4054and "a parking pad in the front area of it, as well as an access
4069pad in the uplands." Id. A dock had also been constructed from
4081the property into the Bay. The most significant difference
4090between the lot at the time of purchase and the lot at the time
4104of hearing for purposes of this proceeding is that the lot now
4116has a swale (the Swale) that runs from the point of discharge of
4129the Eastern Pond Culvert "all of the way to the bay area." Id.
4142The Swale
414440. The Swale was put in sometime after March 20, 2007, as
4156the result of a Settlement Agreement fully executed on that date
"4167By and Between Michael Chbat and Thomas L. Sheehey."
4176Petitioner's Ex. 10.
417941. The Settlement Agreement followed events that
4186commenced in 2004 when Mr. Chbat filed an application (the "2004
4197Application") with DEP for a WRP primarily to construct a house
4209and a boardwalk leading from the house on Lot 9 to a dock in the
4224Bay. The 2004 Application also proposed the extension of the
4234Eastern Pond Culvert with a "pipe" along the western boundary of
4245Chbat's property in a manner substantially similar to the
4254culvert extension allowed by the Amended Permit that is the
4264subject of this proceeding.
426842. On October 28, 2005, DEP proposed that the 2004
4278Application be granted. The permit (the "Proposed Original
4286Permit") was assigned No. 66-0235320-001-DF. See Petitioner's
4294Ex. 10, at 2.
429843. The Proposed Original Permit was challenged by
4306Mr. Sheehey when he "filed a Petition for Administrative Hearing
4316contesting certain action authorized under the [Proposed
4323Original] Permit . . . specifically the relocation of a drainage
4334pipe . . . ." Petitioner's Ex. 10, at 2. After referral of the
4348petition to DOAH, Mr. Chbat and Mr. Sheehey wrote in the
4359Settlement Agreement that they had "determined that it is in
4369their best interests to settle this matter amicably pursuant to
4379the terms hereafter". Id.
438444. Among the terms is that Chbat would file an Amended
4395Application. See id. The agreed-to amendment to the 2004
4404Application was attached to the Settlement Agreement as Exhibit
"4413A," a drawing of a "Drainage Swale Plan," produced by Genesis
4424Group for Mr. Chbat. The drawing depicts a swale that runs from
4436the discharge point of the Eastern Pond Culvert nearly the full
4447length of the western boundary of Lot 9 to the Bay. See Exhibit
"4460A" to Petitioner's Ex. 10. The Swale was designed to take the
4472place of the 2004 Application's proposal for a "pipe" 7 / attached
4484to the point of the discharge from the Eastern Pond Culvert.
4495The Settlement Agreement received the support of DEP because the
4505Department believed that a swale would assist in improving the
4515quality of the stormwater discharged to the Bay over the
4525untreated discharge from the end of the "pipe."
453345. Pursuant to the terms of the Settlement Agreement the
45432004 Application was amended. The Department amended the
4551Proposed Original Permit accordingly and final agency action was
4560taken with the issuance of a permit to Mr. Chbat (the "Final
4572Original Permit") found in DEP Permit File No. 66-0235320-001-
4582DF.
4583Installation of the Swale
458746. The Swale was installed, but it did not work as
4598intended. The result of the Swale's installation was more water
4608on the lot rather than less.
461447. Mr. Chbat described the after-effects of the Swale:
"4623it started bringing more water to the lot . . .". Vol. I
4637at 31. The increased amount of water is the result of several
4649factors, one of which is tidal influence: the tide from the Bay
4661pushes water into the Swale. "[A]bout halfway on the swale
4671. . . that water from the bay was meeting the water from the
4685pipe . . .". Id. The water from the Bay tide and the
4699stormwater conveyed by the Swale would meet at "about the middle
4710of the span of the swale." Id. The result was "a lot more
4723water," id. , on the lot.
472848. Mr. Thomason confirmed Mr. Chbat's assessment that the
4737reason the Swale did not function as effectively as necessary is
4748tidal flow onto Lot 9 from the Bay particularly from high winds.
4760But tidal flow onto Lot 9 and the interruption in the discharge
4772of stormwater through the Swale are not the only problems.
4782There is also a maintenance factor that accompanies tidal flow:
4792sand deposition.
479449. Mr. Thomason elaborated: "[D]uring storm events or
4802[just normal] wave action in the bay, sand is brought back up on
4815to . . . the sandy area at the end of [Lot 9] next to the
4831[Bay.]" 8 / Tr. Vol. I at 62. The influx of sand onto Lot 9 is
4847not just a problem for adequate functioning of the Swale. The
4858Drainage Easement has "the same problem." Id. Both the Swale
4868and the Drainage Easement are plagued by deposition of sand
4878pushed landward by normal tidal influences and storm events.
4887Maintenance of the Swale and the Drainage Easement, therefore,
4896would assist the drainage of stormwater into the Bay.
490550. The tidal influence and maintenance issues that
4913Mr. Chbat encountered with the Swale led him to apply for a
4925different and new permit. That application was filed in 2008.
4935The 2008 Application
493851. Mr. Chbat filed a "Joint Application for Works in the
4949Waters of Florida" with DEP on August 1, 2008 (the "2008
4960Application"). See Chbat Exhibit 1.
496652. The work to be approved was similar to the work
4977originally proposed in the 2004 Application in that both
4986applications proposed installation of a "pipe" to be fixed to
4996the discharge point of the Eastern Pond Culvert that would run
5007along the western boundary of Lot 9 toward the Bay.
501753. A description of the work is contained in Section 10
5028of the 2008 Application: "Extension of an existing stormwater
5037pipe within a private lot approximately 150 feet. The slope for
5048the proposed pipe extension will be at minimum so that
5058stormwater will be treated further, and minimizing erosion."
5066Chbat Ex. 1 at 3.
507154. After the filing of the 2008 Application, Mr. Chbat
5081learned that Mr. Sheehey objected to the newest Chbat proposal
5091because he believed 150 feet is not lengthy enough to clear the
5103Ridge. See Chbat Exhibit 2. In order to cure the objection,
5114Mr. Chbat proposed a modification to the 2008 Application. He
5124attached a "sealed and signed drawing," id. , to a letter dated
5135September 18, 2008, that he submitted to DEP. The drawing shows
5146the extension to be 177 feet, 27 feet more than initially
5157proposed by the 2008 Application. The additional 27 feet was
5167intended to ensure that the discharge would be directly into the
5178Bay in order to "eliminate any possible run-off impact to
5188adjacent properties." Id.
519155. The modification was accepted by DEP." See exhibit
5200number 1 9 / attached to the Amended Permit, Chbat Exhibit 4.
521256. There was conflicting evidence in the proceeding on
5221whether the outfall from a culvert extension of 177 feet will be
5233bayward of the Ridge. The issue was put to rest by Mr. Streets
5246testimony in rebuttal at the hearing. See Tr. Vol. III at 194
5258and 203-4. His testimony establishes that the point of
5267discharge at the end of the culvert extension will clear the
5278Ridge so that the discharge will be directly into the Bay.
5289The Mound
529157. The culvert extension is designed at an elevation and
5301with cover (presumably sod). The extension runs through
5309jurisdictional wetlands and segments them. It does not,
5317however, isolate any portion of the wetlands. The wetlands on
5327Mr. Chbat's property and those to the immediate east and west of
5339it, therefore, will retain their status as jurisdictional
5347wetlands should the extension be installed.
535358. With its sod cover, the culvert extension will be a
5364mini-berm (or a "mound" as Mr. Street called it) at an elevation
5376of 17 to 18 inches above grade. Water that pools to its west
5389will no longer be able to flow eastward of the mound (except
5401rarely under the most extreme weather events.) Conversely,
5409water that collects to its east will no longer be able to flow
5422westward of the extension.
542659. It would have to be a severe storm event for water to
5439rise above the mound. Mr. Chbat has never seen water rise to 18
5452inches above grade and Mr. Cummins testified the highest water
5462ever gets on his property is roughly 12 inches.
547160. The Department approved the 2008 Application as
5479modified to lengthen the extension to 177 feet and issued the
5490Amended Permit. But an incorrect and critical assumption was
5499made during review of the application that related to the mound.
5510Review of the 2008 Application
551561. During his review of the application, Mr. Street, as
5525DEP's stormwater engineer, assumed from the drawings that the
5534Drainage Easement is functional. 1 0/ The assumption was expressed
5544in Mr. Street's testimony in the Department's case-in-chief:
5552Q [D]id you determine whether the pipe, as
5560it would be mounded . . . [the culvert
5569extension covered in sod] . . . would create
5578problems for storm water flow?
5583A I looked at that. There were two
5591conclusions that I drew. One was that the
5599mound would create a higher water elevation
5606on the Chbat property east of the mound, but
5615would not create standing water west of the
5623mound extending into the [Drainage E]asment
5629. . . . Which on the drawings that I
5639reviewed showed an existing trench at the
5646south end of that easement. And it was my
5655opinion that any water that fell west of the
5664mound would exit through the easement.
5670Tr. Vol. II at 92 (emphasis added.)
567762. Mr. Street's assumption that water would not pool to
5687the west of the mound in the Drainage Easement and toward Mr.
5699Sheehey's property was contradicted by Mr. Sheehey's stormwater
5707engineer, Mr. Porterfield.
5710THe Porterfield Testimony and Support for It at Hearing
571963. The testimony at hearing of Mr. Porterfield, who
5728conducted a site visit, established the opposite of what
5737Mr. Street assumed. The volume of stormwater runoff that pools
5747east of the mound, that is, water on Lot 9, will not be as great
5762as the volume as the water that pools west of the mound.
577464. Water that would have flowed onto Lot 9 from the
5785Eastern Pond Culvert will flow directly to the Bay via the
5796culvert extension. The extension will also protect the
5804Drainage Easement and Lot 8 from water that would have flowed
5815from the Eastern Pond Culvert onto that property. But there is
5826a significant difference between stormwater to the west of the
5836extension and to the east. To the extension's west, the
5846Drainage Easement and Lot 8 will have to contend with stormwater
5857from the Drainage Ditch Culvert, the culvert north of Alden Lane
5868that does not convey stormwater from the pond but that like the
5880Pond Culverts has a discharge point directed at the Drainage
5890Easement.
589165. How often and to what extent pooling of stormwater
5901will occur west of the mound due to its presence is difficult to
5914determine on the state of this record. 11/ No studies or analyses
5926of the likelihood and severity of storm events and the volumes
5937of stormwater runoff that would be produced by them were
5947conducted by any of the stormwater engineers in the case nor
5958were any such analyses done with regard to pooling caused by the
5970presence of the covered culvert extension. The testimony of
5979Mr. Porterfield, however, and other evidence, demonstrates that
5987that additional collection of water west of the mound caused by
5998the mound will occur following heavy rain.
600566. Mr. Street was present in the hearing room throughout
6015the entire hearing, including during the presentation of
6023Mr. Sheehey's case. As Mr. Street candidly testified on
6032rebuttal after he had heard all the evidence:
6040I would also maintain that the drainage
6047easement which has signs of a historical
6054usage as a drainage easement with a trench,
6062in fact, that conveys water safely to the
6070bay, that should be re-established and
6076maintained . Thats what its there for.
6083Tr. Vol III at 181 (emphasis added.)
609067. Thus, it became clear to Mr. Street after listening to
6101all the evidence in the case that the Drainage Easement has not
6113been properly maintained. The trench that was expected to carry
6123stormwater toward the Bay no longer exists.
613068. In short, the testimony of Mr. Street, for all his
6141many strengths as a witness, falls short of supporting the
6151position of the Department and Mr. Chbat. Having never visited
6161the site, 1 2/ he approved the project on the basis of drawings
6174that do not conform to the on-site physical reality. When
6184presented with the evidence at hearing that the Drainage
6193Easement is not functioning, he championed re-establishment and
6201maintenance of the Drainage Easement.
620669. Mr. Chbat placed part of the Swale's functionality
6215problem on the tide pushing stormwater northward but his case
6225also recognized the maintenance problem caused by deposition of
6234sand that besets the Swale. Mr. Thomason, moreover, recognized
6243that the Drainage Easement has the same maintenance issue.
6252Mr. Chbat's stormwater engineer testified
6257During storm events or just normal wave
6264action in the bay, sand is brought back up
6273on to. . . the sandy area at the end of
6284[Chbat's] lot next to the water. And so
6292that . . . tends to inhibit the natural flow
6302down the swale . . . we have the same
6312problem on the drainage easement . . . where
6321sand builds up in that discharge .
6328Tr. Vol. I at 62 (emphasis added).
633570. From this record, it is clear that neither the Swale
6346nor the Drainage Easement functions properly. Their functional
6354status, moreover, is due in significant part to lack of
6364maintenance. It may be that maintenance ultimately will not
6373solve the problem; maintenance efforts to keep the Swale and
6383Drainage Easement clear of the sand deposited by tidal activity
6393may require too much effort for them to be reasonably required.
6404But that evidence was not produced. Indeed, the record was
6414silent as to any maintenance efforts with regard to the Swale by
6426Mr. Chbat or with regard to the Drainage Easement by the owner
6438of the easement.
644171. The record is also silent as to whether DEP voiced any
6453concern about the maintenance issues that beset the Swale. It
6463is clear that concern was not raised by the Department in regard
6475to the Drainage Easement until the rebuttal phase of the
6485hearing, since the assumption was made that the easement was
6495properly maintained.
649772. Whatever communication may have occurred with regard
6505to maintenance issues among the parties, the Department issued
6514the Amended Permit. 1 3/
651973. The Permit/Authorization Number for the Amended Permit
6527is 66-235320-002-DF. 1 4/ Issued December 19, 2008, the Amended
6537Permit has an expiration date of December 19, 2013. The
6547expiration date coincides with the construction phase of five
6556years on the face of the Amended Permit. See Chbat Ex. 4.
6568Mr. Sheehey Challenges the Amended Permit
657474. On January 6, 2009, Mr. Sheehey, pro se , filed with
6585DEP a petition (the "Petition") seeking a formal administrative
6595hearing with regard to "Amended Wetland Resource Permit 66-
660400235320-002-DF."
660575. Although the Petition makes reference to the Amended
6614Permit, it seeks in the first instance enforcement of the
6624Settlement Agreement that relates to the Final Original Permit.
6633The Petition states: "Petitioner believes that the Florida
6641Department of Environmental Protection has jurisdiction over
6648this matter and should enforce the March 20, 2007 Settlement
6658Agreement which requires that Permittee act in conformance with
6667Exhibit 'A' of the Agreement [the drawing of the Swale]."
667776. In the event that DEP declined to enforce the
6687Settlement Agreement, the Petition sets out disputed issues of
6696material fact that relate to issuance of the Amended Permit.
670677. The Petition was referred to DOAH on February 19,
67162009. One week before the final hearing, the Department filed
6726the motion in limine that is discussed in the Preliminary
6736Statement of this Recommended Order. The motion was granted to
6746the extent that it sought to preclude Sheehey from introducing
6756evidence that supported enforcement of the Settlement Agreement
6764since the 2008 Application, which, while bearing similarity to
6773the 2004 Application, is nonetheless an independent application
6781that should be approved or denied on its own merits without
6792regard to the 2004 Application, the Proposed Original Permit,
6801the Settlement Agreement or the Final Original Permit.
680978. The case proceeded to hearing on the remaining issues
6819raised by the Petition: 1) whether Sheehey has standing to
6829contest approval of the 2008 Application; 2) whether Chbat gave
6839the notice required by Section 373.413, Florida Statutes, and
68483) whether Chbat's application meets the criteria in statutes
6857and rules for issuance of the Amended Permit.
6865Standing
686679. The findings of fact relevant to Mr. Sheehey's
6875standing are found in paragraph 9, above.
6882Notice
688380. Notice of the 2008 Application was published in The
6893Defuniak Springs Herald-Breeze, a newspaper published in
6900Defuniak Springs, Walton County, Florida. The notice was
6908published on October 23, 2008.
691381. The evidence presented by Mr. Sheehey concerning lack
6922of legal notice consisted of testimony by Mr. Sheehey at hearing
6933in response to questions from his counsel. See Tr. Vol. III at
6945134.
694682. The testimony does not establish that Mr. Sheehey was
6956a person who had filed a written request for notification of any
6968pending application affecting his particular area. The
6975testimony of Mr. Sheehey, moreover, establishes that he was
6984given oral notice of the application by Mr. O'Donnell within
6994four days of its filing.
6999WRP Permitting Criteria
700283. To obtain a WRP, an applicant must satisfy the
7012criteria in Florida Administrative Code Chapter 62-312 and
7020Section 373.414, Florida Statutes. These criteria govern a
7028range of topics including water quality.
7034Water Quality 1 5/
703884. Florida Administrative Code Rule 62-312.080 provides
7045that no permit shall be issued unless the Department has been
7056supplied with reasonable assurances that the proposed work will
7065not violate water quality standards.
707085. Water that enters the pond spends some amount of time
7081in the pond (residence time) before flowing out. During
7090residence time, solids drop out of the water so that the quality
7102of the stormwater that flows out of the pond is reasonably
7113expected to be better than the quality of the stormwater runoff
7124when it entered the pond. Vegetation surrounding the pond,
7133furthermore, enhances the quality of the water in the pond,
7143whether the waters source is runoff or rain falling directly
7153into the pond.
715686. The water that flows out of the pond north of Alden
7168Lane is existing discharge.\. Vol. I at 65. It generally
7178made its way to the Bay prior to the Swale. Some of it makes
7192its way to the Bay via the Swale now; some of it outside the
7206Swale as overflow. The culvert extension will convey that
7215discharge to the Bay if the extension is installed. The quality
7226of the water is not significantly less when it discharges to the
7238Bay via the Swale or otherwise from the Chbat property than when
7250it would enter the culvert extension should it be installed.
726087. It is true that the Swale would have provided
7270filtration and additional treatment to the discharge from the
7279Eastern Pond Culvert as does the Chbat property in general. But
7290that does not mean that the quality of the culverts discharge
7301is a concern. The Swale may have been an option preferable to
7313the extension of the culvert as far as water quality goes but
7325all parties agree that the Swale has failed as a conveyance
7336(albeit Mr. Sheehey maintains that the Swale would work with
7346proper maintenance.) That there is a discharge method that
7355improves the quality of the discharge, such as a swale, does not
7367mean that the discharge to the Bay via the culvert extension is
7379of insufficient quality.
738288. None of the parties tested the quality of the
7392discharge from the Eastern Pond Culvert. The Department,
7400nonetheless, offered evidence with regard to its quality.
740889. The Department concluded that the quality of the pond
7418and its discharge were not of concern. Had the pond been
7429contaminated to an extent that would have given rise to
7439concerns, moreover, the Swale or the culvert extension as a
7449means of conveying the discharge to the Bay would not have made
7461a discernible difference.\. Vol. II at 80.
746890. The Department provided evidence of assumptions made
7476with regard to the quality of the water that led the Department
7488to conclude that testing of the discharge was unnecessary.
7497Mr. ODonnell, the Departments expert in the application of
7506state rules and statutes in wetland resource permitting,
7514detailed the assumptions at hearing:
7519My assumption was that that pond was dug
7527some time in the past as a way to provide
7537fill for roads. That it was never any part
7546of . . . [a] stormwater treatment system.
7554And that it conveyed upstream water through
7561the pond and then on down into
7568Choctawhatchee Bay. It was strictly a
7574[borrow pit and a conveyance pond.] It was
7582never permitted as a treatment system in any
7590way that I was aware of in my diligence [in
7600determining whether the extension should be
7606permitted.]
7607Tr. Vol. II at 79. Once Mr. ODonnells testimony entered the
7618record at the behest of Mr. Chbat, the burden shifted to
7629Mr. Sheehey to prove that the applicant had not provided
7639reasonable assurance of water quality. Mr. Sheehey did not
7648offer evidence of any testing of the discharge. Nor did he
7659offer testimony that rebutted Mr. ODonnells opinion. In fact,
7668the testimony of Mr. Wilkinson (Mr.Sheehey's witness) supported
7676Mr. O'Donnell's opinion with regard to water quality. See Tr.
7686Vol. III at 112 .
769191. In sum, the Department made assumptions that are found
7701to be reasonable based on Mr. ODonnells expertise and
7710experience. Those assumptions were not shown to be unreasonable
7719by Mr. Sheehey. The Departments conclusions about water
7727quality flow directly from Mr. ODonnells reasonable
7734assumptions.
773592. Reasonable assurances have been provided that the
7743project will not violate water quality standards.
7750Public Interest Test
775393. Choctawhatchee Bay is not designated as an
7761outstanding Florida water. The test that Mr. Chbat must meet
7771therefore is whether the activity proposed by the permit
7780application is not contrary to the public interest.
7788§ 373.414, Fla. Stat.
779294. In making that determination, the Department is
7800directed by the statute to consider and balance seven criteria.
7810See § 373.414(a) 1-7, Fla. Stat. Of the seven, three are at
7822issue once water quality is determined to be of no concern.
783395. Two of the three, [w]hether the activity will be of a
7845Statutes, and [t]he current condition and relative value of
7854functions being performed by areas affected by the proposed
7863activity, Section 373.414(1)(a)7., Florida Statutes, do not
7871require in-depth consideration.
787496. With regard to the nature of the project time-wise,
7884the evidence establishes that the culvert extension is intended
7893to be permanent.
789697. With regard to current condition, the area affected by
7906the proposed activity is a residential lot, a substantial
7915portion of which is under water following heavy rain. To
7925facilitate the conveyance of stormwater, the lot is served by
7935the Swale. The Swale is not functioning optimally because of
7945lack of maintenance and because of the Ridge. With regard to
7956relative value from the standpoint of water quality, the
7965function being performed by the lot and the Swale is little, at
7977least as established by this record. While it is certainly true
7988that the lot with or without the Swale will filtrate and
7999otherwise treat stormwater runoff from the pond, the difference
8008in the quality of the stormwater conveyed by the culvert
8018extension from that which would enter the Bay without the
8028extension is not significant. See the discussion above of
8037Mr. ODonnells accepted opinions.
804198. Of the seven statutory criteria to be weighed and
8051balanced by the Department, the one that is central to this case
8063is found in subparagraph 1., of subsection (1)(a): [w]hether
8072the [culvert extension] will adversely affect . . . the property
8083of others. The property of others in this case is the
8094property of Mr. Sheehey.
8098The Projects Effect on the Property of Mr. Sheehey .
810899. For the reasons discussed in paragraphs 63-70, above,
8117Mr. Chbat has failed to provide reasonable assurances that the
8127project will not have a detrimental effect on the property of
8138Mr. Sheehey.
8140100. The extent of the detrimental effect to Mr. Sheehey's
8150property is difficult to determine from this record but it is
8161highly likely based on all the evidence of record that there
8172will be a detrimental effect: additional flooding in heavy rain
8182events.
8183CONCLUSIONS OF LAW
8186101. The Division of Administrative Hearings has
8193jurisdiction over the subject matter of and the parties to this
8204proceeding. §§ 120.569 and 120.57(1), Fla. Stat.
8211Standing
8212102. Mr. Sheehey has standing to contest the issuance of
8222the Amended Permit.
8225Notice
8226103. The notice requirement in Section 373.413, Florida
8234Statutes, is not applicable in this case.
8241104. Mr. Sheehey presented no evidence that he was a
8251person who had filed a written request for notification of any
8262application in his area pending with DEP. There is no question
8273that he actively sought notice from DEP about applications with
8283regard to Lot 9, but it was done by telephone and visits to the
8297DEP office.
8299105. During one of those visits, the Department gave
8308Mr. Sheehey notice of the 2008 Application. Furthermore, notice
8317was published in a local newspaper. Such notice was not shown
8328by Mr. Sheehey to be untimely.
8334Burden of Proof as to the WRP
8341106. As the applicant for the WRP, Mr. Chbat has the
8352burden of showing affirmative entitlement to its issuance.
8360Dep't of Transp. v. J.W.C. Co. , 396 So. 2d 778, 789 (Fla. 1st
8373DCA 1981). In the context of this case, Chbat must provide
8384reasonable assurances that applicable statutory and rule
8391conditions support the issuance of the WRP.
8398107. If Mr. Chbat makes a prima facie case, the burden
8409shifts to Mr. Sheehey to present evidence of equivalent quality
8419that reasonable assurances have not been made. See J.W.C. , 396
8429So. 2d at 789. Mere speculation about what might occur, does
8440not satisfy Mr. Sheehey's burden of presenting evidence contrary
8449to Chbat's prima facie case. See , e.g. , Chipola Basin
8458Protective Group, Inc. v. Dep't of Envtl. Reg. , Case No. 88-3355
8469(DER Dec. 30, 1988).
8473108. "Reasonable assurances" means "a substantial
8479likelihood that the project will be successfully implemented."
8487See Metro. Dade County v. Coscan Fla., Inc. , 609 So. 2d 644, 648
8500(Fla. 3d DCA 1992).
8504109. An applicant must provide reasonable assurances that
8512take into account contingencies that might reasonably be
8520expected. But an applicant is not required to eliminate all
8530contrary possibilities, however remote, or to address impacts
8538that are only theoretical and not reasonably likely. Hoffert v.
8548St. Joe Paper Co. , Case Nos. 89-5053 and 89-6381, (DOAH Oct. 26,
85602990; DER Dec. 6, 1990); Alafia River Basin Stewardship Council,
8570Inc. v. S.W. Fla. Water Mgmt. Dist. , Case No. 98-4925 (DOAH July
85822, 1999; SWFWMD July 27, 1999).
8588110. Competent, substantial evidence based on detailed
8595site plans and engineering studies, coupled with credible expert
8604engineering testimony, is a sufficient basis for a finding of
8614reasonable assurances. See Hamilton County Board of County
8622Commissioners v. Dep't of Envtl. Prot. , 587 So. 2d 1378 (Fla.
86331st DCA 1991). But such evidence is subject to rebuttal by
8644expert engineering testimony based on material differences
8651between site plans and personally-observed physical reality.
8658Deference to Agency Interpretation
8662111. The interpretation of an agency of its own rules and
8673of statutes the agency is required to implement is entitled to
8684deference. Such interpretations are not to be disregarded
8692unless clearly erroneous. Sullivan v. Fla. Dep't of Envtl.
8701Prot. , 890 So. 2d 417 (Fla. 1st DCA 2004); Bd. Of Podiatric Med.
8714v. Fla. Med. Ass'n. , 779 So. 2d 658, (Fla. 1st DCA 2001).
8726Wetland Resource Permit
8729112. Pursuant to Section 373.414, Florida Statutes, an
8737applicant for a WRP is required to demonstrate that the proposed
8748activities will not be harmful to water resources and will
8758comply with applicable rules. This statutory section is
8766implemented in DEP's Northwest District through Florida
8773Administrative Code Chapter 62-312 and, in particular, through
8781Florida Administrative Code Rule 62-312.080.
8786113. Chbat and the Department presented competent,
8793substantial evidence 1 6/ demonstrating reasonable assurance that
8801the proposed project will comply with the provisions of Florida
8811Administrative Code Rule 62-312.080(1), that is, that the
8819project will not violate state water quality standards.
8827114. Pursuant to Florida Administrative Code Rule 62-
8835312.080(2) and Section 373.414(1), Florida Statutes, Mr. Chbat
8843is required to demonstrate reasonable assurances that the
8851proposed project is not contrary to the public interest based on
8862a balancing of the seven factors listed in Section
8871373.414(1)(a), Florida Statutes.
8874115. Mr. Chbat has failed to show the project is not
8885contrary to the public interest because of the effect the
8895project is likely to have on Mr. Sheehey's property.
8904116. Mr. Sheehey demonstrated through Mr. Porterfield's
8911testimony that in heavy rains Lot 8 is likely to suffer greater
8923flooding because of Mr. Chbat's project.
8929117. Mr. Porterfield's testimony was countered by
8936Mr. Thomason's testimony. In a case like this, it would not be
8948unusual to look to the testimony of DEP's storm water engineer
8959to "break the tie" between testimony given by the stormwater
8969engineer of the applicant and the stormwater engineer of the
8979applicant's opponent.
8981118. In testifying for DEP, Mr. Street was accepted as an
8992expert in storm water engineering. The credentials that
9000entitled him to that expertise were beyond challenge both from
9010the standpoint of his education and his experience. His
9019demeanor on the stand was forthright. From the substance of his
9030testimony and his demeanor, he is found to be an expert whose
9042testimony is credible and whose opinions are entitled to great
9052weight. But there was a shift in Mr. Street's position between
9063when he testified in the case-in-chief for the Department, based
9073on his review of the drawings submitted by Mr. Chbat, and when
9085he testified on rebuttal after he had heard all of the evidence
9097in the case. Mr. Street moved from a position of "the Drainage
9109Easement will protect Mr. Sheehey's property," to "the trench in
9119the Drainage Easement needs to be re-established and the
9128easement maintained" in order to protect Mr. Sheehey's property.
9137119. In the final analysis, Mr. Street's testimony on
9146rebuttal supports the position of Mr. Sheehey that the mounded
9156culvert extension will cause build up and impoundment of water
9166on Lot 8 that would ordinarily move off the lot.
9176RECOMMENDATION
9177Based on the foregoing, it is recommended that the
9186Department of Environmental Protection deny 1 7/ the Amended Permit
9196for the failure of Mr. Chbat to provide reasonable assurances
9206that the project will not adversely affect Mr. Sheehey's
9215property.
9216DONE AND ENTERED this 14th day of January, 2010, in
9226Tallahassee, Leon County, Florida.
9230S
9231DAVID M. MALONEY
9234Administrative Law Judge
9237Division of Administrative Hearings
9241The DeSoto Building
92441230 Apalachee Parkway
9247Tallahassee, Florida 32399-3060
9250(850) 488-9675
9252Fax Filing (850) 921-6847
9256www.doah.state.fl.us
9257Filed with the Clerk of the
9263Division of Administrative Hearings
9267this 14th day of January, 2010.
9273ENDNOTES
92741 / Mr. Cummins was not tendered as an expert of any kind. As
9288would be expected, Mr. Wharton, Chbat's counsel, objected to the
9298question about water overflow from the pond: "I think that
9308calls for an opinion. Is it possible to know where the water
9320spreads. It's not even a question of his personal observation."
9330Tr. Vol. III at 8. The objection was over-ruled with the
9341statement from the administrative law judge, "you can ask if the
9352witness has observed the water and to describe it." Id. The
9363witness' testimony was based on long-time personal observation.
9371It is, moreover, of a quality that clears the threshold for the
9383admission of evidence in an administrative proceeding in which
9392the substantial interests of a party are determined by an
9402agency: "Irrelevant, immaterial, or unduly repetitious evidence
9409shall be excluded, but all other evidence of a type commonly
9420relied upon by reasonably prudent persons in the conduct of
9430their affairs shall be admissible, whether or not such evidence
9440would be admissible in a trial in the courts of Florida ."
9452§ 120.569(1)(g), Fla. Stat. (emphasis added.) The testimony
9460from Mr. Cummins demonstrates that his observations and the
9469inferences he drew from those observations are of a type allowed
9480to be of record by the Administrative Procedure Act.
9489Furthermore, the conduct of the witness and his demeanor during
9499the hearing were such that his testimony was not only accepted
9510as truthful as far as what the witness had observed, but
9521supported by experience with regard to the conclusion reached.
9530That conclusion is that at times of sufficient rain or during
"9541wet periods," water from the pond flows past or under Alden
9552Lane onto Mr. Chbat's property toward the bay and then across
9563Lot 9, the Easement, and Lot's 8, 7, and 6 and in the wettest
9577time onto Lot 5, the lot owned by Mr. Cummins.
95872 / The morning of the second day of hearing, after considerable
9599rainfall over Walton County experienced by all participants the
9608day before, the water on Mr. Cummins' lot was at eight inches
9620above the soil.
96233 / Although referred to colloquially by residents as "our
9633upland," the evidence-of-record establishes that the Ridge is
9641within DEP's jurisidictional wetlands.
96454 / Mr. Street's use of the word "unnatural" to describe the
9657east-west flow is taken to mean that it is contrary to the
9669otherwise natural north-to-south flow of water across the
9677surface of Lot 9, the Easement and Lot 8.
96865 / Petitioner's Ex. 7A with 7B and 7C comprise a composite
9698exhibit: Petitioner's Ex. 7.
97026 / The photograph of the pond does little to add to the Findings
9716of Fact in this order.
97217 / The pipe originally proposed by the 2004 Application is
9732substantially similar to what is referred to in this proceeding
9742as the extension of the culvert.
97488 / Mr. Thomason's testimony with regard to the deposition of
9759sand at the end of the Swale close to the Bay, see tr. vol. I at
977574, e.g., where he refers to it as "deposition of sediment" is
9787similar to Mr. Street's testimony that one of the natural causes
9798of the Ridge is deposition of sand. The Swale, moreover,
9808receives sediment carried by stormwater as well as sand
9817deposited through tidal influences.
98219 / Exhibit Number 1 to the Amended Permit is to be distinguished
9834from Exhibit Number 2 to the Amended Permit. Exhibit Number 1
9845is entitled "PIPE EXTENSION PLAN." Exhibit Number 2 is entitled
"9855MITIGATION PLAN; it continues to show a length of 150 feet.
9866When the 2008 Application was amended to lengthen the pipe
9876extension to a 177 feet only a "single revised page was
9887submitted." Tr. Vol. I at 57. The MITIGATION PLAN was not
9898revised to show the additional 27 feet because the mitigation
9908proposed remained the same.
991210 / The assumption is at odds with the Department's acceptance
9923that the Swale did not function as planned. A large part of the
9936Swale's lack of functionality is due to deposition of sediment
9946which could be overcome by maintenance. One would expect that
9956deposition of sand in the Drainage Easement would occur for the
9967same reasons as it occurs in the Swale, which is borne out by
9980the evidence in this case.
998511/ Mr. Street elaborated on some of the factors that would have
9997to be considered to conduct such an analysis. See Tr. Vol. II
10009at 115.
1001112 / Department personnel did visit the site at some point after
10023the 2004 Application was filed.
1002813 / It is not clear from the record why the permit issued in
10042response to the 2008 Application is denominated as "amended."
10051Perhaps, an amended permit was issued because of the revision to
10062the Pipe Extension Plan drawing now attached to the Amended
10072Permit as Exhibit 1 that added an additional 27 feet to the
10084extension of the culvert. Or perhaps the permit is denominated
"10094amended" to communicate that it is an amendment to the permit
10105issued following the 2004 Application. If so, it is a misnomer.
10116The 2008 Application drawings of the work, while similar to the
10127what was permitted by the Proposed Original Permit, is a new
10138application independent of the 2004 Application, the Proposed
10146Original Permit and the Final Original Permit.
1015314 / The permit/authorization Number for the Amended Permit is
10163one digit different from number assigned to the Original Permit
10173file.
1017415 / Water quality, however, is not a real issue to any party in
10188the case. There have been no water quality violations raised
10198by the Department with regard to the quality of the pond or its
10211discharge. The record is devoid of any attempt made by any
10222resident of La Grange Estates, including Mr. Sheehey, to improve
10232the quality of the discharge from the pond even after residents
10243noticed the red tinge of the discharge following the countys
10253use of red clay to improve the roads in the subdivision. The
10265project was not designed by Mr. Chbats stormwater engineer to
10275address water quality issues. Mr. Sheeheys real issue is one
10285of water quantity: whether the volume of water on his property
10296will be increased by the installation of the culvert extension.
1030616 / The evidence which consisted of the testimony of
10316Mr. Thomason and Mr O'Donnell was competent but thin. It is
10327regarded as substantial enough, however, to shift the burden to
10337Mr. Sheehey to show the project's violation of state water
10347quality standards. Mr. Sheehey failed to carry that burden.
1035617 / Although the recommendation in this order is to deny the
10368Amended Permit, the record of this proceeding reveals ways of
10378reaching an outcome satisfactory to all parties. The
10386aspirations of the parties in this case are not in conflict.
10397Mr. Chbat wants to be able to build a residence on his lot and
10411have the lot be habitable from the stand-point of water on the
10423lot. Mr. Sheehey does not oppose Mr. Chbat's interest in
10433building a home on Lot 9. He wants simply to protect his lot
10446from additional flooding beyond what it experiences now as the
10456result of the overflow of stormwater from a borrow pit that
10467should drain to the Bay via the Drainage Easement but does not.
10479The Department is willing to issue permits sought by Mr. Chbat
10490so long as the wetlands and the Bay are protected. Likewise,
10501the Department has no intent to exacerbate the flooding on Mr.
10512Sheehey's property.
10514A potential solution is modification of the Amended Permit
10523following a site visit by DEP's stormwater engineer. During
10532such a visit, Mr. Street should double-check his determination
10541that a culvert extension of 177 feet in length will allow
10552outfall bayward of the Ridge. He should determine whether the
"10562trench" in the Drainage Easement can be re-established. The
10571Department should consider whether and to what to what extent
10581the Drainage Easement can be maintained. (Presumably an
10589association of which both Mr. Chbat and Mr. Sheehey are members
10600is the owner of the Drainage Easement.) Furthermore, the
10609Department should consider allowing cuts in the Ridge at
10618appropriate places to facilitate drainage from Lots 8 and 9 and
10629the Drainage Easement so long as drainage through the cuts will
10640not damage jurisdictional wetlands or the Bay.
10647COPIES FURNISHED :
10650Frederick L. Aschauer, Jr., Esquire
10655Rose, Sundstrom & Bentley, LLP
106602548 Blairstone Pines Drive
10664Tallahassee, Florida 32301
10667Amanda Gayle Bush, Esquire
10671Department of Environmental Protection
10675Office of the General Counsel
106803900 Commonwealth Boulevard, Mail Stop 35
10686Tallahassee, Florida 32399-3000
10689David Michael Chesser, Esquire
10693Chesser & Barr, P.A.
106971201 Eglin Parkway
10700Shalimar, Florida 32579
10703Thomas L. Sheehey
1070687 Alden Lane
10709Freeport, Florida 32439
10712Michael W. Sole, Secretary
10716Department of Environmental Protection
10720Douglas Building
107223900 Commonwealth Boulevard
10725Tallahassee, Florida 32399-3000
10728Tom Beason, General Counsel
10732Department of Environmental Protection
10736Douglas Building, Mail Station 35
107413900 Commonwealth Boulevard
10744Tallahassee, Florida 32399-3000
10747Lea Crandall, Agency Clerk
10751Department of Environmental Protection
10755Douglas Building, Mail Station 35
107603900 Commonwealth Boulevard
10763Tallahassee, Florida 32399-3000
10766NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
10772All parties have the right to submit written exceptions within
1078215 days from the date of this Recommended Order. Any exceptions
10793to this Recommended Order should be filed with the agency that
10804will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 04/14/2010
- Proceedings: Respondent Michael Chbat`s Exceptions to the January 14, 2010 Recommended Order Issued by Administrative Law Judge David M. Maloney filed.
- PDF:
- Date: 01/14/2010
- Proceedings: Recommended Order (hearing held September 14 and 15, 2009). CASE CLOSED.
- PDF:
- Date: 01/14/2010
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 12/11/2009
- Proceedings: Department of Environmental Protection's Proposed Recommended Order filed.
- Date: 12/08/2009
- Proceedings: Transcript of Proceedings (Volume III, corrected) filed.
- PDF:
- Date: 12/07/2009
- Proceedings: Order (Respondent Chbat's request is granted, proposed recommended orders are due on December 11, 2009).
- PDF:
- Date: 11/25/2009
- Proceedings: Order Granting Extension of Time (Proposed Recommended Orders to be filed by December 4, 2009).
- PDF:
- Date: 11/24/2009
- Proceedings: Joint Motion for Extension of Time to File Proposed Recommended Orders filed.
- PDF:
- Date: 10/30/2009
- Proceedings: Order (proposed recommended orders shall be filed by November 30, 2009).
- PDF:
- Date: 10/30/2009
- Proceedings: Letter to Judge Maloney from J. Wharton regarding date agreed upon for Parties to file Proposed Recommended Orders filed.
- Date: 10/26/2009
- Proceedings: Transcript of Proceedings (Volumes I through III) filed.
- PDF:
- Date: 09/30/2009
- Proceedings: Letter to Judge Maloney from J. Wharton regarding agreed upon date to file Proposed Recommended Orders filed.
- Date: 09/14/2009
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 09/11/2009
- Proceedings: Order (Emergency Motion for Permission to Enter Respondent's Chbat's Property is denied).
- PDF:
- Date: 09/10/2009
- Proceedings: Respondent, Michael Chbat's, Expedited Response to Emergency Motion or, in the Alternative, Suggestion of Mootness as to Emergency Motion filed.
- PDF:
- Date: 09/10/2009
- Proceedings: Emergency Motion for Permission to Enter Respondent's Chbat's Property filed.
- PDF:
- Date: 09/09/2009
- Proceedings: Respondents', Michael Chbat and the Florida Department of Environmental Protection, Motion in Limine filed.
- PDF:
- Date: 09/08/2009
- Proceedings: Notice of Service of Petitioner's Response to Respondent's Third Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 09/04/2009
- Proceedings: Cross Notice of Taking Deposition (Cliff Street, Julie Dickinson, and Larry O'Donnell) filed.
- PDF:
- Date: 09/04/2009
- Proceedings: Department of Environmental Protection's Response to Petitioner's First Request for Production of Documents filed.
- PDF:
- Date: 08/21/2009
- Proceedings: Notice of Taking Deposition Duces Tecum (of A. Kizlauskas) filed.
- PDF:
- Date: 08/21/2009
- Proceedings: Notice of Taking Deposition Duces Tecum (of L. Porterfield) filed.
- PDF:
- Date: 08/18/2009
- Proceedings: Notice of Service of Petitioner's Amended Response to Respondent's Second Set of Interrogatories to Petitoner(sic) filed.
- PDF:
- Date: 08/11/2009
- Proceedings: Petitioner's First Request for Production to Respondent Department of Environmental Protection filed.
- PDF:
- Date: 08/06/2009
- Proceedings: Respondent's Certificate of Service of Third Set of Interrogatories to Thomas L. Sheehey filed.
- PDF:
- Date: 08/06/2009
- Proceedings: Amended Notice of Hearing (hearing set for September 14 and 15, 2009; 10:00 a.m., Central Time; Shalimar, FL; amended as to Date of Hearing).
- PDF:
- Date: 07/24/2009
- Proceedings: Amended Notice of Hearing (hearing set for August 19 and 20, 2009; 10:00 a.m., Central Time; Shalimar, FL; amended as to Date of Hearing).
- PDF:
- Date: 07/17/2009
- Proceedings: Notice of Withdrawal of Date From Consideration for Final Hearing Pursuant to That Joint Response Filed June 4, 2009 filed.
- PDF:
- Date: 07/15/2009
- Proceedings: Notice of Withdrawal of Two (2) Dates From Consideration for Final Hearing Pursuant to That Joint Response Filed June 4, 2009 filed.
- PDF:
- Date: 06/29/2009
- Proceedings: Notice of Service of Petitioner's Response to Respondent's Second Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 06/29/2009
- Proceedings: Response to Respondent's, Michael Chbat, Second Request for Production of Documents filed.
- PDF:
- Date: 06/11/2009
- Proceedings: Response in Opposition to Motion to Stay or Abate Proceedings filed.
- PDF:
- Date: 06/02/2009
- Proceedings: Respondent's, Michael Chbat, Second Request for Production of Documents filed.
- PDF:
- Date: 06/02/2009
- Proceedings: Respondent's Certificate of Service of Second Set of Interrogatories to Thomas L. Sheehey filed.
- PDF:
- Date: 05/21/2009
- Proceedings: (Petitioner's) Certificate of No Objection to Extension of Time filed.
- PDF:
- Date: 05/08/2009
- Proceedings: Amended Notice of Telephonic Pre-hearing Conference (set for May 18, 2009; 9:30 a.m., Eastern Time; 8:30 a.m., Central Time).
- PDF:
- Date: 05/07/2009
- Proceedings: Notice of Telephonic Pre-hearing Conference (set for May 18, 2009; 9:30 a.m., Eastern Time; 8:30 a.m., Central Time).
- PDF:
- Date: 05/06/2009
- Proceedings: Order Canceling Hearing (parties to advise status by May 18, 2009).
- PDF:
- Date: 04/24/2009
- Proceedings: Notice of Cancellation of Deposition of Petitioner, Thomas Sheehey filed.
- PDF:
- Date: 04/23/2009
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of T. Sheehey) filed.
- PDF:
- Date: 04/09/2009
- Proceedings: Notice of Service of Petitioner`s Response to Respondent`s First Interrogatories to Thomas L. Sheehey filed.
- PDF:
- Date: 04/09/2009
- Proceedings: Response to Respondent`s, Michael Chbat, First Request for Production of Documents filed.
- PDF:
- Date: 04/02/2009
- Proceedings: Order (Motion is granted and the Petitioner shall have until April 8, 2009, to respond to the Motion to Dismiss).
- PDF:
- Date: 04/02/2009
- Proceedings: Notice of Hearing (hearing set for May 14, 2009; 10:00 a.m., Central Time; Shalimar, FL).
- PDF:
- Date: 03/31/2009
- Proceedings: Respondent`s, Michael Chbat`s, Response to Petitioner`s Motion for Extension of Time to Respond to Motion to Dismiss filed.
- PDF:
- Date: 03/25/2009
- Proceedings: Petitioner`s Motion for Extension of Time to Respond to Motion to Dismiss filed.
- PDF:
- Date: 03/24/2009
- Proceedings: Letter to Judge Ruff from F. Aschuaer regarding Motion to Dismiss filed by Respondent filed.
- PDF:
- Date: 03/10/2009
- Proceedings: Respondent`s, Michael Chbat, First Request for Production of Documents filed.
Case Information
- Judge:
- DAVID M. MALONEY
- Date Filed:
- 02/18/2009
- Date Assignment:
- 09/11/2009
- Last Docket Entry:
- 04/14/2010
- Location:
- Shalimar, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
Counsels
-
Frederick L. Aschauer, Esquire
Address of Record -
Amanda G. Bush, Esquire
Address of Record -
David Michael Chesser, Esquire
Address of Record -
Thomas L Sheehey
Address of Record -
Thomas L. Sheehey
Address of Record