09-001725
Goose Bayou Homeowner&Apos;S Association vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Wednesday, September 16, 2009.
Recommended Order on Wednesday, September 16, 2009.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8GOOSE BAYOU HOMEOWNER'S )
12ASSOCIATION, )
14)
15Petitioner, )
17)
18vs. ) Case No. 09-1725
23)
24DEPARTMENT OF ENVIRONMENTAL PROTECTION, )
29)
30)
31Respondent. )
33)
34RECOMMENDED ORDER
36On July 29, 2009, a final administrative hearing in this
46case was held by video teleconference in Tallahassee and Panama
56City before J. Lawrence Johnston, Administrative Law Judge (ALJ),
65Division of Administrative Hearings (DOAH).
70APPEARANCES
71For Petitioner: Bill Britton, Qualified Representative
77Goose Bayou Homeowner's Association
814002 Valencia Court
84Panama City, Florida 32405-3221
88For Respondent: Brynna J. Ross, Esquire
94Hillary Copeland, Esquire
97Department of Environmental Protection
1013900 Commonwealth Boulevard
104Mail Station 35
107Tallahassee, Florida 32399-3000
110STATEMENT OF THE ISSUE
114The issue in this case is whether the Department of
124Environmental Protection (DEP or Department) should exempt
131Petitioner's alleged maintenance-dredging from wetland resource
137permitting under Florida Administrative Code Rule 62-
144312.050(1)(e). 1
146PRELIMINARY STATEMENT
148On December 4, 2007, the Department determined that
156Petitioner's proposal was not exempt and gave notice of intent to
167deny Petitioner's application for an exemption for alleged
175maintenance dredging. On March 27, 2009, Petitioner filed a
184second amended petition for an administrative hearing. On
192April 2, 2009, DEP referred the petition to DOAH for appointment
203of an ALJ. The matter was scheduled for a final hearing on
215May 27, 2009, but the parties jointly moved for an abeyance,
226which was granted. On July 10, 2009, the parties requested a
237final hearing, which was scheduled for July 29, 2009, by video
248teleconference.
249The parties filed a Joint Pre-Hearing Stipulation on
257July 23, 2009, which was amended before the final hearing. The
268Amended Joint Pre-Hearing Stipulation was filed after the
276hearing, on July 31, 2009.
281The parties stipulated to the admission of Exhibits 1, 4,
29140, 48, 52, and 73-99. Petitioner called Michael Mathews,
300Environmental Supervisor II employed in DEP's Panama City office
309DEP. DEP called Mr. Mathews and Jim Stoutamire, a Program
319Administrator employed in DEP's Tallahassee office.
325After the presentation of evidence, DEP requested a
333Transcript of the final hearing, and the parties were given ten
344days from the filing of the Transcript in which to file proposed
356recommended orders (PROs). The Transcript was filed on
364August 11, 2009. The parties' timely PROs have been considered.
374FINDINGS OF FACT
3771. Petitioner has applied for a maintenance-dredging
384exemption from wetland resource permitting for two channels in
393Goose Bayou on the two ends of a U-shaped upland cut canal
405adjacent to Goose Bayou.
4092. Rule 62-312 provides in pertinent part:
416(1) No permit shall be required under this
424chapter for dredging or filling . . . for the
434projects listed below.
437* * *
440(e) The performance of maintenance dredging
446of existing manmade canals, channels, and
452intake and discharge structures, where the
458spoil material is to be removed and deposited
466on a self-contained, upland spoil site which
473will prevent the escape of the spoil material
481and return water from the spoil site into
489surface waters of the state, provided no more
497dredging is performed than is necessary to
504restore the canal, channels, and intake and
511discharge structures to original design
516specifications, and provided that control
521devices are used at the dredge site to
529prevent turbidity and toxic or deleterious
535substances from discharging into adjacent
540waters during maintenance dredging. This
545exemption shall apply to all canals
551constructed before April 3, 1970, and to
558those canals constructed on or after April 3,
5661970, pursuant to all necessary state
572permits. This exemption shall not apply to
579the removal of a natural or manmade barrier
587separating a canal or canal system from
594adjacent waters of the state. Where no
601previous permit has been issued by the Board
609of Trustees of the Internal Improvement Trust
616Fund or the United States Army Corps of
624Engineers for construction or maintenance
629dredging of the existing manmade canal or
636intake or discharge structure, such
641maintenance dredging shall be limited to a
648depth of no more than 5 feet below mean low
658water.
6593. There was no evidence of any dredging or application for
670dredging in the vicinity of the proposed alleged "maintenance-
679dredging" prior to 1971. There was evidence and a stipulation
689that Heritage Homes of Fort Walton, Inc. (Heritage Homes),
698applied to the State of Florida in or around 1971 to dredge two
711navigation channels in Goose Bayou for a project known as
721Venetian Villas and to remove two plugs separating a land-locked
731U-shaped canal from Goose Bayou. The navigation channels were to
741be 50 feet wide by five feet deep. The southern channel was to
754be 640 feet long, while the northern channel was to be 450 feet
767long. This proposal did not receive any governmental
775authorization.
7764. There was evidence and the parties stipulated that in
7861973, based on the proposed project modifications, the State of
796Florida Department of Pollution Control (DPC), a predecessor of
805DEP, issued water quality certification, and the State of Florida
815Board of Trustees of the Internal Improvement Trust Fund (BOT)
825issued a permit for the project, as modified.
8335. It appears that the issuance of the water qualify
843certification and BOT permit was part of some kind of settlement
854reached between Heritage Homes and the State of Florida for
864dredge-and-fill violations. It appears that the settlement also
872involved the conveyance of ten acres of land to the State of
884Florida in lieu of payment for the spoil used in filling the
896marsh lands between Goose Bayou and the U-shaped canal.
9056. There was evidence and the parties stipulated that, at
915some point in time, the DPC certification and a BOT permit were
927transferred from Heritage Homes to West Florida Construction
935Company (West Florida).
9387. There was evidence and the parties stipulated that, as
948of July 13, 1973, neither Heritage Homes nor West Florida had
959applied to the United States Army Corps of Engineers (Corps) for
970a permit.
9728. There was evidence and the parties stipulated that, over
982time and after receiving comments from various governmental
990agencies, West Florida's proposed project changed to involve a
999yacht basin/marina, a proposed southern channel, elimination of
1007the proposal for a northern channel, and plugging the U-shaped
1017canal to keep it separate from Goose Bayou. The location of the
1029single, southern channel under this proposal was different from
1038the proposed location of the southern channel under the Heritage
1048Homes proposal, which was to start at the southernmost arm of the
1060U-shaped canal. Instead, under West Florida's proposal, the
1068single, southern channel was to be located directly north of the
1079southernmost arm of the U-shaped canal.
10859. There was evidence and the parties stipulated that, by
1095August 21, 1974, West Florida applied to the Corps for a permit
1107to dredge the single, southern channel (50 feet wide, 565 feet
1118long, and four feet deep), to keep the northern canal plugged,
1129and to construct a yacht basin/marina.
113510. There was evidence and the parties stipulated that, the
1145United States Department of the Interior Fish and Wildlife
1154Service (FWS) and the United States Environmental Protection
1162Agency (EPA) recommended several changes to the project before
1171they could recommend that the Corps issue a permit for the 1974
1183application; however, it does not appear that the recommended
1192changes were ever made or that the Corps ever took any action on
1205the 1974 application or issued any permit for the proposed
1215project.
121611. At some point in time after 1974, the two plugs were
1228removed, which connected the U-shaped canal to Goose Bayou.
1237There is now a wide, shallow channel from the waterward ends of
1249the U-shaped canal into Goose Bayou. The evidence did not prove
1260that these channels, which Petitioner now seeks to maintenance-
1269dredge, were ever dredged by man. Their width and shallow depth
1280are more consistent with natural scouring from surface water
1289runoff leaving the canal system at low and extreme low tides than
1301with dredging. There was no evidence of soil borings, which
1311could have verified whether the channels had been dredged by man.
132212. Even if originally dredged, there was no evidence that
1332a dredged channel had been maintained over the years.
1341Mr. Stoutamire testified that DEP does not consider maintenance-
1350dredging to include the restoration or rebuilding of a channel
1360that has not been maintained and no longer exists. This
1370interpretation of the maintenance-dredging exemption is
1376reasonable.
137713. Mr. Stoutamire also testified that DEP interprets the
1386last sentence of Rule 62-312.050(1)(e), limiting maintenance-
1393dredging to no more than five feet below mean low water where no
1406previous permit has been issued, to refer to canals constructed
1416before April 3, 1970, since maintenance-dredging of canals
1424constructed after that date would not be exempt if not previously
1435permitted. This interpretation is reasonable. 2
144114. Petitioner's application did not state that control
1449devices would be used to prevent turbidity and toxic or
1459deleterious substances from discharging into adjacent waters
1466during dredging.
1468CONCLUSIONS OF LAW
147115. As applicant, Petitioner had the burden of proving
1480entitlement to the maintenance-dredging exemption. See Hough v.
1488Menses , 95 So. 2d 410, 412 (Fla. 1957); Key vattman , 959
1499So. 2d 339, 345 (Fla. 1st DCA 2007).
150716. Petitioner failed to meet its burden of proof of
1517entitlement to a maintenance-dredging exemption under Rule 62-
1525312.050(1)(e). The evidence did not prove that the channels
1534sought to be maintenance-dredged were previously dredged and
1542maintained, or that previous dredging was "pursuant to all
1551necessary state permits." Fla. Admin. Code R. 62-312.050(1)(e).
155917. Because Petitioner did not prove entitlement to exempt
1568maintenance-dredging, it is not necessary to determine whether an
1577exemption would include--as a matter of law, and despite not
1587being included in Petitioner's application--the use of "control
1595devices . . . at the dredge site to prevent turbidity and toxic
1608or deleterious substances from discharging into adjacent waters
1616during maintenance dredging." Id.
1620RECOMMENDATION
1621Based upon the foregoing Findings of Fact and Conclusions of
1631Law, it is
1634RECOMMENDED that the Department enter a final order denying
1643Petitioner a maintenance-dredging exemption under Rule 62-
1650312.050(1)(e).
1651DONE AND ENTERED this 16th day of September, 2009, in
1661Tallahassee, Leon County, Florida.
1665S
1666J. LAWRENCE JOHNSTON
1669Administrative Law Judge
1672Division of Administrative Hearings
1676The DeSoto Building
16791230 Apalachee Parkway
1682Tallahassee, Florida 32399-3060
1685(850) 488-9675
1687Fax Filing (850) 921-6847
1691www.doah.state.fl.us
1692Filed with the Clerk of the
1698Division of Administrative Hearings
1702this 16th day of September, 2009.
1708ENDNOTES
17091/ All rule references are to the version of the Florida
1720Administrative Code in effect at the time of the final hearing.
17312/ Mr. Stoutamire also testified that, in the rare case of a
1743dredging permit issued before April 3, 1970, maintenance-dredging
1751would be limited to the design specifications of the permit, but
1762that interpretation is not germane to this case.
1770COPIES FURNISHED :
1773Brynna J. Ross, Esquire
1777Department of Environmental Protection
17813900 Commonwealth Boulevard, Mail Station 35
1787Tallahassee, Florida 32399-3000
1790Bill Britton
1792Goose Bayou Homeowner's Association
17964002 Valencia Court
1799Panama City, Florida 32405-3221
1803Michael W. Sole, Secretary
1807Department of Environmental Protection
18113900 Commonwealth Boulevard, Mail Station 35
1817Tallahassee, Florida 32399-3000
1820Tom Beason, General Counsel
1824Department of Environmental Protection
18283900 Commonwealth Boulevard, Mail Station 35
1834Tallahassee, Florida 32399-3000
1837Lea Crandall, Agency Clerk
1841Department of Environmental Protection
18453900 Commonwealth Boulevard, Mail Station 35
1851Tallahassee, Florida 32399-3000
1854NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
1860All parties have the right to submit written exceptions within 15
1871days from the date of this Recommended Order. Any exceptions to
1882this Recommended Order should be filed with the agency that will
1893issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 09/16/2009
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 08/20/2009
- Proceedings: Department of Environmental Protection's Proposed Recommended Order filed.
- Date: 08/11/2009
- Proceedings: Transcript filed.
- Date: 07/29/2009
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 07/17/2009
- Proceedings: Notice of Hearing by Video Teleconference (hearing set for July 29, 2009; 9:00 a.m., Central Time; Panama City and Tallahassee, FL).
- PDF:
- Date: 07/10/2009
- Proceedings: Third Joint Status Report and Motion to Take Case Out of Abeyance filed.
- PDF:
- Date: 06/22/2009
- Proceedings: Order Continuing Case in Abeyance (parties to advise status by July 10, 2009).
- PDF:
- Date: 06/17/2009
- Proceedings: Request Documents and Pictures be Filed Into Docket of Case# 09-1725 filed.
- PDF:
- Date: 06/05/2009
- Proceedings: Order Continuing Case in Abeyance (parties to advise status by June 19, 2009).
- PDF:
- Date: 04/22/2009
- Proceedings: Order Granting Continuance and Placing Case in Abeyance (parties to advise status by June 5, 2009).
- PDF:
- Date: 04/21/2009
- Proceedings: Order on Motion to Determine Qualifications (enclosing rules regarding qualified representatives).
- PDF:
- Date: 04/21/2009
- Proceedings: Notice of Hearing (hearing set for May 27, 2009; 10:00 a.m., Central Time; Panama City, FL).
- PDF:
- Date: 04/08/2009
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
Case Information
- Judge:
- J. LAWRENCE JOHNSTON
- Date Filed:
- 04/01/2009
- Date Assignment:
- 04/02/2009
- Last Docket Entry:
- 11/17/2009
- Location:
- Panama City, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
Counsels
-
Bill Britton
Address of Record -
Brynna J. Ross, Esquire
Address of Record