95-001577
Robert Starr, Jim Duff, Betty Brenneman, Michele D`amour, Richard Bossey, And Jane Bossey vs.
Bocilla Utilities Company And Department Of Environmental Protection
Status: Closed
Recommended Order on Friday, August 25, 1995.
Recommended Order on Friday, August 25, 1995.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8ROBERT STARR, BETTY )
12BRENNEMAN, and JIM DUFF, )
17)
18Petitioners, )
20)
21vs. ) CASE NO. 95-1577
26)
27BOCILLA UTILITIES, INC. and )
32DEPARTMENT OF ENVIRONMENTAL )
36PROTECTION, )
38)
39Respondents. )
41______________________________)
42RECOMMENDED ORDER
44Final hearing was held in Port Charlotte, Florida, on July 31 and August 1,
581995, before Robert E. Meale, Hearing Officer of the Division of Administrative
70Hearings.
71APPEARANCES
72The parties were represented at the hearing as follows:
81For Petitioners: Robert Starr
85Post Office Box 5337
89Grove City, Florida 34224
93Betty Brenneman
95Post Office Box 67
99Placida, Florida 33946
102Jim Duff
104Post Office Box 41
108Placida, Florida 33946
111For Respondent M. Christopher Bryant
116Bocilla Oertel Hoffman
119Utilities: Post Office Box 6507
124Tallahassee, Florida 32314-6507
127For Respondent Thomas I. Mayton, Jr.
133Department of Assistant General Counsel
138Environmental Department of Environmental Protection
143Protection: 2600 Blair Stone Road
148Tallahassee, Florida 32399-2440
151STATEMENT OF THE ISSUE
155The issue in this case is whether Bocilla Utilities, Inc. is entitled to a
169public drinking water construction permit for the expansion of an existing
180reverse-osmosis water plant located on Don Pedro Island.
188PRELIMINARY STATEMENT
190By Application for a Public Drinking Water Facility Construction Permit
200filed January 26, 1995, Bocilla Utilities, Inc. requested a permit for the
212expansion of its water plant and the addition of two new water wells.
225By Intent to Issue dated February 27, 1995, the Department of Environmental
237Protection stated its intent to issue the permit.
245By Petition dated March 17, 1995, Petitioners challenged the issuance of
256the permit on several grounds.
261At the hearing, Bocilla Utilities called five witnesses and offered into
272evidence 22 exhibits. The Department of Environmental Protection called two
282witnesses and offered into evidence three exhibits. Petitioners called seven
292witnesses and offered into evidence 12 exhibits. All exhibits were admitted
303except Petitioners Exhibits 4, 5, and 7, which were proffered.
313The transcript was filed August 8, 1995. Rulings on timely filed proposed
325recommended orders are in the appendix.
331FINDINGS OF FACT
3341. Bocilla Utilities, Inc. (Applicant) was incorporated in the mid-1980s
344for the purpose of supplying water to a residential development being developed
356by some or all of the principals of the water utility. The residential
369development is on a bridgeless barrier island in Charlotte County.
3792. Applicant initially proposed locating the plant on the mainland with
390submerged pipes to the island. This proposal was approved by the Army Corps of
404Engineers and Department of Environmental Regulation, but the Trustees of the
415Internal Improvement Trust Fund denied Applicant's request for an easement
425across submerged state lands.
4293. After failing to obtain a submerged land easement, Applicant obtained
440the permits to build a reverse-osmosis (RO) water plant at its present location
453on the barrier island. Included among the permits was a permit from the
466Department of Natural Resources dated September 11, 1985, allowing Applicant to
477construct the water treatment plant, two underground concrete water storage
487tanks, and a tennis court on top of the tanks up to 100 feet seaward of the
504coastal construction control line.
5084. Applicant is a certificated utility that, since September 1994, has
519been regulated by the Public Service Commission. It was previously regulated by
531Charlotte County.
5335. By Application for a Public Drinking Water Facility Construction Permit
544filed January 26, 1995 (Application), Applicant requested a permit to expand the
556treatment capacity of its water plant from 30,000 gallons per day (gpd) to
570120,000 gpd. By installing the new treatment equipment in two stages, the plant
584would have an immediate capacity of 60,000 gpd. Applicant proposes no material
597changes to the existing water storage tanks, distribution system, or the size or
610location of the building that houses the existing and proposed water treatment
622equipment.
6236. The Application form asks Applicant to identify any well construction
634permits obtained from the water management district and to provide a map showing
647any sanitary hazards within 500 feet of each proposed well. The Application
659form requires Applicant's professional engineer to attest that the project
669complies with Chapter 62-555, Florida Administrative Code. The Engineering
678Report attached to the completed Application supplies the requested information,
688but explains that Applicant's hydrogeologist had not, as of the date of the
701report, obtained the well-construction permits from the water management
710district.
7117. By Intent to Issue dated February 27, 1995, the Department of
723Environmental Protection (DEP) gave notice of its intent to issue the requested
735permit. Noting that it has permitting jurisdiction under Section 403.861(9),
745Florida Statutes, and that the project is not exempt, DEP determined that a
758public drinking water construction permit is required for the proposed work.
769The Intent to Issue is based on DEP's
777belief that reasonable assurances have been
783provided to indicate that the proposed project
790will not adversely impact water quality and
797the proposed project will comply with the
804appropriate provisions of Florida Administrative
809Code Rules 62-4, 62-550, 62- 555 and 62-699.
8178. Petitioners timely objected to the issuance of the proposed permit.
828Petitioners reside in Applicant's certificated area on the barrier island. They
839presently obtain their water from private wells or cisterns, rather than
850Applicant. If the permit were granted so as to expand Applicant's production
862capacity, Petitioners would be more likely required to obtain water from
873Applicant due to Charlotte County's mandatory hookup ordinance.
8819. About a week before filing the Application, Applicant applied on
892January 20, 1995, to the Southwest Florida Water Management District (SWFWMD)
903for permits for the construction of the two wells included in the draft permit.
91710. SWFWMD granted these permits on February 8, 1995, about three weeks
929after receiving the applications. Consistent with its normal practice in
939granting well-construction permits, SWFWMD did not provide interested persons
948with a point of entry to challenge the permits.
95711. The SWFWMD permits provide in part:
964A. Compliance with state and local county
971health regulations as per Chapter 17-555,
977Florida Administrative Code (F.A.C.), is
982required via the Drinking Water System Permit.
989B. Compliance with Chapters 17-532 and 17- 555,
997F.A.C., on construction standards and grouting
1003procedures for Public Supply Wells shall be
1010followed.
1011* * *
1014D. This well site has been judged as satisfactory
1023based on the location and information provided to
1031[SWFWMD] at the time of the well site inspection.
1040. . .
1043* * *
10461. Public Supply Wells must meet certain setback
1054requirements from all potential sources of
1060contamination. To obtain and retain your Drinking
1067Water System Permit, please coordinate any future
1074development of the surrounding property within 200'
1081of your well site with the Charlotte County Health
1090Department.
1091* * *
109412. By letter dated February 14, 1995, from a SWFWMD representative to
1106Applicant's hydrogeological consultant, SWFWMD acknowledged that it granted
1114Applicant a setback variance of 100 feet from nearby septic systems in
1126permitting the two new wells. The letter states that the "variance is based upon
1140the known geohydrology of the area and the proposed construction of the wells,"
1153as well as an understanding that the "existing public system is working out with
1167no problems."
116913. A month later, a letter from a DEP engineer identifies various types
1182of sanitary hazards and implicitly ratifies the setback variance granted by
1193SWFWMD. By letter dated March 14, 1995, Gary Maier identified sanitary hazards
1205as septic tank systems, sewer lines, swimming pools and associated chemicals,
1216pet excretions, and residential chemicals such as pesticides, fertilizers,
1225paints, oils, and solvents. Mr. Maier's letter acknowledges that SWFWMD had
1236granted a variance from 200 feet to 100 feet "due to geologic and treatment
1250conditions," but cautions that "any further decrease in setbacks for sanitary
1261hazards would be imprudent."
126514. Applicant's water plant is located on Don Pedro Island, which is part
1278of an island chain consisting, from north to south, of Knight Island, Don Pedro
1292Island, and, usually, Little Gasparilla Island. The low-lying island chain
1302fronts the Gulf of Mexico on the west. The northern end of the island chain
1317abuts Lemon Bay on the east. Over the years, storms have opened and closed
1331passes at various points along the island chain. The island chain is vulnerable
1344to flooding, and some areas are more vulnerable than others.
135415. One of the historic passes is Bocilla Pass. The plant site area is
1368about a half mile south of this now-closed pass. The Gulf beaches on either side
1383of the point at which the Bocilla Pass emptied into the Gulf have suffered
1397considerable erosion in recent years, to the point that recently built homes
1409have been inundated by water and had to be removed or razed.
142116. The plant site area includes the building housing the water treatment
1433and other equipment, two 50,000-gallon storage tanks immediately to the west of
1446the building, the existing water supply well located just east of the building,
1459and the two proposed water supply wells located a short distance east and south
1473of the building.
147617. The existing storage tanks, which mark the westernmost extent of the
1488plant site area, are about 235 feet east of a pronounced erosion line along the
1503Gulf shore and are separated from the Gulf by South Gulf Boulevard. Immediately
1516adjacent to the tanks is the building housing the water treatment equipment. The
1529two proposed wells would be located about 200 and 450 feet south of the tanks.
154418. The plant site area is much closer to water on the east. The
1558southerly proposed well is about 12 feet west of the mean high water line of
1573Bocilla Lagoon, and the northerly proposed well is about 16 feet west of the
1587mean high water line of Bocilla Lagoon. The building housing the water
1599treatment equipment is further away from the water, but still less than 50 feet.
161319. Bocilla Lagoon is a long and narrow waterway that was dredged in a
1627north-south direction parallel to the Gulf shoreline. Bocilla Lagoon is closed
1638off by land less than a quarter of a mile south of the plant site area. The
1655lagoon runs to the north to connect to what remains of Bocilla Pass, which then
1670runs easterly a short distance to a dredged extension of Lemon Bay.
168220. The building housing the water treatment equipment and the storage
1693tanks are not located in the vulnerable FEMA V[elocity] zone. However, the
1705record does not establish the location of the proposed wells relative to the V-
1719zone. Testimony concerning the location of the V-zone relative to the water
1731plant establishes only that the building, not the two proposed wells, are safely
1744outside the V-zone. Nothing in the record establishes contour lines on the
1756barrier island in the vicinity of the plant site area or the elevation of the
1771land at the site of the two proposed wells.
178021. Applicant has recently upgraded the security of the storage tanks
1791through the addition of locks to the manholes. The installation of fences is
1804impractical and unnecessary because the tanks are topped by a six-inch,
1815reinforced slab of concrete that also serves as tennis courts.
182522. The proposed wells would be well constructed. They would extend 167
1837feet into a confined artesian aquifer. The concrete pressurized grouting
1847coupled with a potentiometric surface of seven feet make it unlikely that the
1860wells would be vulnerable to contaminants. During severe-storm conditions,
1869pumping would cease, leaving the system in its naturally pressurized state, so
1881that surface water could not easily flow down into the well. Additionally, the
1894RO filtration technology is one of the most effective at eliminating
1905contaminants from drinking water.
190923. However, failing to have shown that the two proposed wells are outside
1922the V-zone, Applicant has also failed to provide reasonable assurances that the
1934two proposed wells would be protected from damage from the velocity wave action
1947associated with the V-zone.
195124. Applicant has constructed and operated the water plant in an exemplary
1963fashion. Applicant has at all times met or exceeded applicable standards for
1975water quality, safety, and operations. Original construction exceeded minimum
1984requirements and added to the durability of the fixtures. The building housing
1996the water treatment equipment and hydropneumatic tank has been issued a
2007floodproofing certificate by a registered engineer. The certificate states that,
2017with human intervention in the form of bolting predrilled plywood boards over
2029openings, the plant is waterproofed to an elevation of 14 feet NGVD, which is
2043one foot higher than the FEMA-supplied base flood elevation of 13 feet NGVD.
205625. Applicant employs an operations manager with a Class A license rather
2068than one with merely a Class C license, even though only a Class C operator is
2084required for a water plant of this size. Also, Applicant maintains a low-level
2097chlorine indicator, even though not required to do so due to the small size of
2112the utility.
211426. The relevant sewage flows from the quantity of water that would be
2127drawn by each proposed well would be greater than 2000 gpd.
213827. Near the proposed wells are single- and multi-family residences served
2149by on-site sewage disposal systems, the above- described road, a swimming pool
2161on the other side of the road, an injection well, and the treatment plant at
2176which Applicant stores anti-scaling agents, ammonia, chlorine, and acid.
2185However, Applicant has shown that none of these items is within 100 feet of the
2200proposed wells. Bocilla Lagoon is not a sanitary hazard at this time.
221228. The two deficiencies in Applicant's proof relate solely to the
2223susceptibility of the proposed wells to a significant risk of damage from
2235flooding and other disasters and the location of the proposed wells relative to
2248areas least subject to localized flooding. In all other respects, such as fire
2261flow and security, Applicant has provided reasonable assurances that the
2271applicable criteria would be satisfied or that the proposed work would have no
2284bearing on the issue raised by Petitioners.
2291CONCLUSIONS OF LAW
229429. The Division of Administrative Hearings has jurisdiction over the
2304subject matter. Section 120.57(1), Florida Statutes. (All references to
2313Sections are to Florida Statutes. All references to Rules are to the Florida
2326Administrative Code.)
232830. Applicant and DEP stipulated to Petitioners' standing. Absent the
2338stipulation, Petitioners have standing as residents of the island chain who, as
2350a result of the proposed expansion of capacity, would be more likely to be
2364required to hookup to Applicant's expanded service due to Charlotte County's
2375mandatory hookup ordinance.
237831. Rule 62-555.530(1) requires DEP to evaluate each application for a
2389public water supply permit for compliance with applicable water quality
2399standards, which are not at issue in this case, and for "[a]dequate engineering
2412design complying with acceptable engineering principles as established in Rule
242262- 555.310 through .360, F.A.C." Rule 62-555.530(2) provides that DEP "shall
2433either issue or deny a permit pursuant to Chapter 120, F.S."
244432. Rule 62-555.300 explains the purpose of Rules 62- 555.310 through .360
2456as follows:
2458The quality of drinking water when it ultimately
2466reaches the consumer depends on the construction,
2473operation, and maintenance of a public water
2480system. The following rules establish requirements
2486for construction, operation, and maintenance of a
2493public water system and cover all aspects of a
2502public water system from collection through
2508treatment, storage, and distribution.
251233. Two rules are relevant to this case. Rule 62-555.310 provides:
2523Raw water shall be obtained from the most desirable
2532source that is available, and an effort shall be
2541made to prevent or control contamination of the
2549source. The plant site area shall not be subject
2558to a significant risk from earthquakes, floods,
2565fires, or other disasters which could cause a
2573breakdown of the public water system or any
2581portion thereof.
258334. Rule 62-555.312 states:
2587The following setback distances around public
2593drinking water supply wells apply to newly
2600constructed wells. However, the 100 and 200
2607foot setback distances which have been in effect
2615since November 9, 1977 and December 13, 1983,
2623respectively remain in effect.
2627(1) Public drinking water supply wells that
2634serve water systems having total sewage flows
2641greater than 2,000 gallons per day shall be
2650placed no closer than 200 feet from on-site
2658sewage disposal systems (septic tanks) other
2664than land application of reclaimed water areas.
2671Public drinking water supply wells serving water
2678systems having total sewage flows of less than or
2687equal to 2,000 gallons per day shall be placed no
2698closer than 100 feet from on-site sewage disposal
2706systems (septic tanks) other than land application
2713of reclaimed water areas.
2717* * *
2720(4) Public drinking water supply wells shall
2727be located no closer than 100 feet from other
2736sanitary hazards as defined in Rule 62- 550.200,
2744F.A.C.
2745(5) Public drinking water supply wells shall
2752be located on ground least subject to localized
2760flooding, and as far as is practical when the
2769direction of ground water slope or movement is
2777known, wells shall be located on the upstream
2785side of sanitary hazards.
2789(6) [DEP] or appropriate water management
2795district shall decrease or increase these
2801distances when approving well construction permits,
2807if justified, by the presence or absence of
2815natural barriers such as impermeable geological
2821strata, adequate protection by treatment, or
2827proper construction practices.
283035. The remaining rules in Rules 62-555.310 through .360 are not directly
2842relevant to this case. These rules govern the location of water mains; well-
2855drilling methods (Rule 62- 555.315); water treatment, storage, and
2864distribution; fluoridation; cleaning and disinfection; post-construction
2870certification by DEP; operation and maintenance; water testing; and cross-
2880connections.
288136. The rules do not define "plant site area." Rule 62- 550.200(55)
2893defines "sanitary hazard" as a "physical condition which involves or affects any
2905part of a drinking water system or the raw water source, and that creates an
2920imminent or potentially serious risk to the health of any person who consumes
2933water from that system."
293737. Applicant and DEP raise two major contentions concerning the scope of
2949review that DEP should properly give the Application. The first argument is
2961that DEP has delegated to SWFWMD the responsibility for ensuring that the two
2974proposed wells are suitably located.
297938. The statutes and rules do not clearly divide responsibilities between
2990DEP and the water management districts in permitting public supply water wells.
3002But DEP cannot defer this decision entirely to SWFWMD for several reasons.
301439. Even if DEP delegates to the water management districts the authority
3026over the location of public water supply wells, DEP does not necessarily deprive
3039itself of authority over the location of public supply wells. Section
3050373.308(1) authorizes DEP to delegate to the water management districts the
3061authority for issuing permits for the "location [and] construction" of water
3072wells. But Section 373.308(4) adds that this delegation is not necessarily
3083absolute:
3084Notwithstanding the provision in this section
3090for delegation of authority to a water management
3098district, [DEP] may prescribe minimum standards
3104for the location [and] construction of water
3111wells throughout all or parts of the state, as
3120may be determined by [DEP].
312540. Sections 403.852(12)(d)2, 403.853(1)(a), and 403.861(7) and (9)
3133require DEP to adopt rules concerning public drinking water supplies.
3143Exercising this authority, DEP adopted Rules 62- 555.310 through 62-555.360 and
315462-555.530.
315541. DEP's rules acknowledge the role of the water management districts in
3167issuing permits to construct public water supply wells. Rule 62-555.510(2)
3177requires:
3178Before construction of a public water supply well,
3186the licensed water well contractor shall obtain an
3194application form from and apply to the appropriate
3202water management district for a permit to construct
3210the well in accordance with Rule 62-555.315 and
3218Chapter 62-532, F.A.C., and Chapter 373, Part III,
3226F.S.
322742. The reference to Rule 62-555.315, which is a detailed rule governing
3239well-drilling methods, arguably stresses the role of the water management
3249districts in reviewing technical well- construction specifications. But the
3258omission of a similar express reference to the location of wells undermines the
3271absolute-delegation argument of Applicant and DEP on this point.
328043. In any event, nothing in the rules implies that DEP must defer
3293absolutely to a water management district in applying the locational criteria
3304governing water wells, as set forth in Rule 62-555.312. DEP's rules contemplate
3316that the construction of a public water supply well will require a permit from
3330the water management district and a permit from DEP.
333944. Rule 62-555.520 requires the applicant, prior to "commencing
3348construction or alteration," to use the same form on which the Application was
3361made in this case to apply "to [DEP]" for a construction permit. The
3374application form suggests that DEP anticipates an applicant will obtain a well-
3386construction permit from a water management district, but that DEP will also
3398undertake its own review of this information, at least as to the location of the
3413well.
341445. For instance, DEP's application form requests a map showing sanitary
3425hazards within 500 feet of the proposed well. If the water management district
3438permit resolved all siting questions of the proximity of the water well to
3451sanitary hazards, DEP would not require this information on its application
3462form.
346346. The only textual support for the argument of Applicant and DEP is Rule
347762-555.312(6), which states that DEP "or" the water management district may
3488change setbacks for good cause. This language does not necessarily preclude DEP
3500from exercising jurisdiction over the location of public water supply wells. In
3512any event, setbacks are only part of the locational criteria, and the
3524disjunctive reference to the water management district or DEP is too slim a
3537basis on which to conclude that, in issuing public water supply construction
3549permits, DEP is prohibited from considering the locational criteria in Rule 62-
3561555.312.
356247. The argument of Applicant and DEP that DEP cannot consider locational
3574criteria fails for another reason. If the responsibility for applying the
3585locational criteria fell exclusively to the water management district,
3594substantially affected persons such as Petitioners would lose their right, under
3605Chapter 120, Florida Statutes, to a formal hearing on these issues prior to the
3619issuance of the public water supply construction permit. Without regard to
3630whether these rights are extended by constitutional, statutory, or decisional
3640law, DEP's Rule 62-555.530(2) expressly guarantees that the issuance and denial
3651of permits will be governed by Chapter 120, Florida Statutes.
366148. Thus, regardless whether SWFWMD applied the locational criteria of
3671Rules 62-555.310 through 62-555.360 in issuing the two well-construction
3680permits, DEP must also apply these criteria in deciding whether to issue the
3693public water supply construction permit sought in this case.
370249. The setback for sanitary hazards is 100 feet except that it is, in
3716this case, 200 feet for septic tanks. DEP properly approved SWFWMD's reduction
3728of setbacks from sanitary hazards from 200 feet to 100 feet based on the depth
3743of the proposed wells; the proposed method of construction; the use of a
3756confined, well pressurized artesian aquifer, and the effectiveness of the
3766proposed RO treatment method. However, no reduction below 100 feet is
3777permissible.
377850. Applicant has provided reasonable assurances that the two proposed
3788wells satisfy the setback requirements of Rule 62- 555.312(1), (4), and (6).
3800There are no sanitary hazards within 100 feet of either proposed well. The only
3814potential sanitary hazard within 100 feet of either well is Bocilla Lagoon, but
3827the record does not suggest that water quality of the lagoon constitutes a
3840sanitary hazard.
384251. However, Applicant has failed to provide reasonable assurances that
3852the location of the proposed wells satisfies the requirements of Rule 62-
3864555.312(5), which is the only part of Rule 62-555.312 not addressing setbacks
3876from sanitary hazards.
387952. Rule 62-555.312(5) contains two requirements. First, public drinking
3888water supply wells must be located on "ground least subject to localized
3900flooding." Second, "as far as practical when the direction of ground water
3912slope of movement is known," wells must be located on the upstream side of
3926sanitary hazards.
392853. The second part of subsection (5) is not applicable. This part of the
3942rule is qualified by the clause, "as far as is practical when the direction of
3957ground water slope or movement is known." There is no indication that the
3970direction of ground water slope is known, so the second part of the rule has no
3986bearing on this case. In any event, the second part of the rule is not only
4002conditioned by knowledge of the direction of groundwater slope or movement, but
4014also by the qualification that the location is governed by the rule requirement
4027only "as far as is practical."
403354. By contrast, the first part of subsection (5) is not conditioned upon
4046any knowledge of local conditions or the qualification of practicality. The
4057first part of the rule says that public drinking water supply wells shall be
4071located on "ground least subject to localized flooding."
407955. The first part of Rule 62-555.312(5) thus requires a determination
4090that, if the local area is flooded, then the proposed wells must be on ground
4105that is the last site within the local area to flood. The first part of
4120subsection (5) ignores widespread flooding, but not localized flooding.
412956. Absolutely nothing in the record indicates that the proposed wells are
4141on ground least subject to localized flooding. DEP has not disclosed its
4153interpretation of the phrases, "least subject" and "localized flooding." The
4163close proximity of the proposed wells to the mean high water line of Bocilla
4177Lagoon demands that Applicant and DEP address the location of the proposed wells
4190with respect to the extent to which they would be subject to localized flooding.
4204Applicant has not provided reasonable assurances as to this requirement of Rule
421662- 555.312(5).
421857. The proposed wells would be well constructed and, due to their
4230potentiometric surfaces, relatively unsusceptible to contamination. But Rule
423862-555.312(5) focuses on susceptibility to localized flooding and makes no
4248exceptions for quality constructed wells, pressurized aquifers, or effective
4257filtration systems. Subsection (5) addresses the safety of public water supply
4268wells by ensuring that they are placed in areas least subject to localized
4281flooding, rather than relying entirely on quality well construction, positively
4291pressurized aquifers, and RO filtration systems.
429758. Rule 62-555.310 also supplies locational criteria for the "plant site
4308area," which includes the building and its contents, including the proposed new
4320water treatment equipment. Applicant and DEP argue that the locational criteria
4331of Rule 62- 555.310 are inapplicable to the proposed expansion involving the
4343water treatment equipment. They point out that Applicant is seeking a permit
4355for the expansion--not initial construction--of a water treatment plant.
436459. The Application is for a permit to quadruple capacity to 120,000 gpd
4378through the replacement of RO filters and the addition of two new supply wells.
4392Rule 62-555.310 states that the "plant site area shall not be subject to a
4406significant risk from . . . floods, fires, or other disasters which could cause
4420a breakdown of the public water system or any portion thereof."
443160. Mr. Maier conceded that a vast plant expansion would require review of
4444the plant site area. His reasoning was that such an expansion would involve the
4458removal and addition of considerable equipment and would represent a fundamental
4469change in the plant. But he contended that the present expansion was not so
4483extensive as to trigger such review.
448961. Obviously, there are alterations to water plants that do not add to
4502capacityeatment systems may be changed or updated, and storage tanks and
4513distribution systems may be replaced. Earlier permits for the plant site area
4525entitled the permittee to construct and operate a plant of the permitted
4537capacity at a specific area. Thus, reviewing later requests for permits to
4549alter treatment systems, storage tanks, and distribution systems, without
4558increasing capacity, should not normally trigger reconsideration of the original
4568approval of the location of the plant site area. Request for permits to alter
4582without any increase in capacity means that service remains the same in terms of
4596the extent of public reliance on specific quantities of water, and the risk
4609remains the same in terms of the extent of public harm in the event of the
4625interruption of such service.
462962. In this case, Applicant seeks a permit to alter a system by increasing
4643its capacity by four times. This means that the public reliance on Applicant's
4656water is increased four times, and the public harm in the event of the
4670interruption of service is increased four times. The assessment of risk, by
4682rule, addresses the consequence of the breakdown in the public water system and
4695necessarily the extent of public harm done by such a breakdown. When
4707Applicant's water plant was originally permitted, an interruption in service
4717harmed one-quarter of the public that would come to rely on the expanded
4730capacity for which Applicant now seeks approval.
473763. Thus, Rule 62-555.310 applies to the Application and the plant site
4749area subject to alteration.
475364. Applicant has provided reasonable assurances that the new water
4763treatment equipment is not subject to a significant risk from floods, fires, or
4776other disasters that could cause a breakdown of the public water system or any
4790portion thereof. The risk to the building and its contents from flooding is
4803adequately attenuated by the location of the building outside of the more
4815dangerous V-zone and its compliance with FEMA floodproofing standards.
4824Notwithstanding some evidence concerning inadequate fire flows, there is no real
4835reason to doubt that the plant site area suffers a significant risk of damage
4849from fire. As Applicant pointed out, seawater to fight fires is plentiful on
4862the island.
486465. Rule 62-555.310 also applies to the two proposed wells, which, in this
4877case, are part of the "plant site area." The rule does not refer only to the
"4893plant" itself, but rather extends to the entire "plant site area." The purpose
4906of the rule is to prevent breakdowns in the public water supply system, of which
4921a crucial part is the water supply well. In this case, the inclusion of the
4936proposed wells in the plant site area is reinforced by their close proximity to
4950the water treatment equipment, storage tanks, and pumps.
495866. Applicant has failed to provide reasonable assurances that the
4968proposed wells are not subject to significant risk of damage from flooding or
4981other disasters, including wave action. Quality well construction, a pressurized
4991aquifer, and an RO treatment system tend to reduce the susceptibility of the
5004wells to damage from flooding and possibly wave action. But Applicant has not
5017provided reasonable assurances that the remaining risk satisfies the criteria of
5028Rule 62-555.310 in terms of the extent of risk and resulting damage.
504067. Applicant's request for attorneys' fees and costs is denied.
5050RECOMMENDATION
5051It is
5053RECOMMENDED that the Department of Professional Regulation enter a final
5063order denying the application of Bocilla Utilities, Inc. for a public water
5075supply construction permit.
5078ENTERED on August 25, 1995, in Tallahassee, Florida.
5086___________________________________
5087ROBERT E. MEALE
5090Hearing Officer
5092Division of Administrative Hearings
5096The DeSoto Building
50991230 Apalachee Parkway
5102Tallahassee, Florida 32399-1550
5105(904) 488-9675
5107Filed with the Clerk of the
5113Division of Administrative Hearings
5117on August 25, 1995.
5121APPENDIX
5122Rulings on Respondents' Proposed Findings
51271-4: adopted or adopted in substance.
51335: rejected as irrelevant and repetitious.
51396-7 (except last sentence): adopted or adopted in substance.
51487 (last sentence): rejected as unsupported by the appropriate weight of
5159the evidence and legal argument.
51648 (except last sentence): rejected as subordinate, recitation of
5173testimony, and irrelevant.
51768 (last sentence): adopted or adopted in substance.
51849: rejected as irrelevant.
518810: adopted or adopted in substance, except to extent of legal argument as
5201to effect of action of SWFWMD in granting variance.
521011-12: rejected as irrelevant.
521413 (except last sentence): adopted or adopted in substance.
522313 (last sentence): rejected as irrelevant.
522914-17 (except last sentence): adopted or adopted in substance.
523817 (last sentence): rejected as legal argument.
524518-21: adopted or adopted in substance.
525122: rejected as unnecessary.
525523: adopted or adopted in substance as to protection from only sanitary
5267hazards.
526824-26: adopted or adopted in substance as to description of aquifer,
5279proposed well construction, and efficiency of RO filtration process, but not as
5291reasons in support of Paragraph 23.
529727 (first sentence): adopted or adopted in substance.
530527 (remainder): rejected as unnecessary.
531028: adopted or adopted in substance.
531629: rejected as unnecessary.
532030-31: adopted or adopted in substance.
532632: rejected as irrelevant.
533033-40: rejected as unsupported by the appropriate weight of the evidence.
5341COPIES FURNISHED:
5343Virginia B. Wetherell, Secretary
5347Department of Environmental Protection
5351Twin Towers Office Building
53552600 Blair Stone Road
5359Tallahassee, FL 32399-2400
5362Kenneth Plante, General Counsel
5366Department of Environmental Protection
5370Twin Towers Office Building
53742600 Blair Stone Road
5378Tallahassee, FL 32399-2400
5381Robert Starr
5383P.O. Box 5337
5386Grove City, FL 34224
5390Betty Brenneman
5392P.O. Box 67
5395Placida, FL 33946
5398Jim Duff
5400P.O. Box 41
5403Placida, FL 33946
5406M. Christopher Bryant
5409Oertel Hoffman
5411P.O. Box 6507
5414Tallahassee, FL 32314-6507
5417Thomas I. Mayton, Jr.
5421Assistant General Counsel
5424Department of Environmental Protection
54282600 Blair Stone Road
5432Tallahassee, FL 32399-2440
5435NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5441All parties have the right to submit written exceptions to this Recommended
5453Order. All agencies allow each party at least 10 days in which to submit
5467written exceptions. Some agencies allow a larger period within which to submit
5479written exceptions. You should contact the agency that will issue the final
5491order in this case concerning agency rules on the deadline for filing exceptions
5504to this Recommended Order. Any exceptions to this Recommended Order should be
5516filed with the agency that will issue the final order in this case.
5529=================================================================
5530AGENCY FINAL ORDER
5533=================================================================
5534STATE OF FLORIDA
5537DEPARTMENT OF ENVIRONMENTAL PROTECTION
5541ROBERT STARR, BETTY BRENNEMAN,
5545and JIM DUFF,
5548Petitioners,
5549vs. OGC Case No. 95-0665
5554DOAH Case No. 95-1577
5558BOCILLA UTILITIES, INC. and
5562DEPARTMENT OF ENVIRONMENTAL
5565PROTECTION,
5566Respondents.
5567_______________________________/
5568FINAL ORDER
5570On August 25, 1995, a Hearing Officer with the Division of Administrative
5582Hearings (hereafter "DOAH"), submitted his Recommended Order to the Respondent,
5593Department of Environmental Protection (hereafter "Department") 1/ Copies of
5603the Recommended Order were served upon the Petitioners, Robert Starr, Betty
5614Brenneman, and Jim Duff (hereafter "Petitioners"), and upon the Respondent,
5625Bocilla Utilities, Inc. (hereafter "Utility"). A copy of the Recommended Order
5637is attached hereto as Exhibit A.
5643On September 11, the Respondents 2/ timely filed joint Exceptions to
5654Recommended Order and a joint Request for Official Recognition. The Utility
5665also simultaneously filed a Request for Oral Argument. No exceptions or
5676responses were filed by the pro se Petitioners. The matter is now before the
5690Secretary of the Department for final agency action.
5698BACKGROUND
5699The Utility is a private utility owning and operating an existing public
5711drinking water plant located on Don Pedro Island. 3/ Don Pedro Island is a
5725bridgeless barrier island in the Gulf of Mexico and is located within the
5738geographical boundaries of Charlotte County, Florida. The Utility is currently
5748regulated by the Public Service Commission and provides water to customers of a
5761residential development on the island. Petitioners live on Don Pedro Island and
5773have residences within the Utility's certificated area, but are not present
5784customers of the Utility. Petitioners presently obtain their water from private
5795wells or cisterns, but may be required to obtain water from the Utility in the
5810future due to Charlotte County's mandatory hookup ordinance.
5818The Utility filed an Application for a Public Drinking Water Facility
5829Construction Permit (hereafter "Application") with the Department on January 26,
58401995. (Utility Ex. 1) The Application requested a permit to expand the
5852treatment capacity of its water plant from 30,000 gallons per day (gpd) to
5866120,000 gpd. By installing the new treatment equipment in two stages, the plane
5880would have an immediate capacity of 60,000 gpd. The Application proposed no
5893material changes to the existing water storage tanks, distribution system, or
5904the size or location of the building that houses the existing and proposed water
5918treatment equipment.
5920On February 27, 1995, the Department executed a Notice of Intent to Issue
5933the requested permit to the Utility. (Utility Ex. 8) The Notice of Intent to
5947Issue observed that the Department has permitting jurisdiction under Section
5957403.861(9), Florida Statutes, and that the project was not exempt. The Notice
5969of Intent to Issue also contained a Department determination that a public
5981drinking water construction permit is required for the proposed work. The
5992Intent to Issue the permit was based on the Department's stated "belief that
6005reasonable assurances have been provided to indicate that the proposed project
6016will not adversely impact water quality and the proposed project will comply
6028with the appropriate provisions of Florida Administrative Code Rules 62-4, 62-
6039550, 62-555 and 62-669." Petitioners subsequently filed a timely petition
6049challenging the issuance of the proposed permit and requesting a formal hearing.
6061About a week before filing the Application with the Department, the Utility
6073also applied to the Southwest Florida Water Management District (hereafter
"6083Water District") for permits to construct two new water wells referred to in
6097the Application filed with the Department. The Water District granted these
6108well permits on February 8, 1995. The Water District apparently did not provide
6121the Petitioners with a point of entry to challenge the water well permits.
6134The Utility plant site area includes the building housing the water
6145treatment and other equipment, two 50,000-gallon storage tanks immediately to
6156the west of the building, the existing water supply well located just east of
6170the building, and the two proposed water supply wells located a short distance
6183east and south of the building. The existing storage tanks, which mark the
6196westernmost extent of the plant site area, are about 235 feet east of a
6210pronounced erosion line along the Gulf shore and are separated from the Gulf by
6224South Gulf Boulevard. Immediately adjacent to the tanks is the building housing
6236the water treatment equipment. The two proposed wells would be located about
6248200 and 450 feet south of the tanks. Near the proposed wells are single and
6263multi-family residences served by on-site sewage disposal systems.
6271A formal administrative hearing was held on July 31 and August 1, 1995,
6284before DOAH Hearing Officer Robert E. Meale (hereafter "Hearing Officer"). Each
6296of the parties presented the testimony of witnesses and had various exhibits
6308admitted into evidence. Proposed Recommended Order were filed by the parties
6319after the hearing and the Hearing Officer subsequently entered his Recommended
6330Order on August 25, 1995.
6335The Hearing Officer found that the Utility had failed to establish that the
6348two proposed wells (1) would not be susceptible to a significant risk of damage
6362from flooding and other disasters and (2) were to be located on ground least
6376subject to localized flooding. In view of these critical findings, the Hearing
6388Officer concluded that the Utility had failed to provide reasonable assurances
6399that its proposed water treatment expansion project would not violate the
6410provisions of Rules 62-555.310 and 62-555.312(5), Florida Administrative Code.
6419The Hearing Officer also made a related critical ruling of law that the
6432Department had not totally delegated to the Water District all responsibility
6443and authority to consider questions related to the adequacy of proposed water
6455wells identified in the wager treatment system-expansion application before the
6465Department for review. The Hearing Officer ultimately recommended that the
6475Department enter a Final Order denying the Utility's application for a permit to
6488expand the water treatment capacity of its existing water treatment plant on Don
6501Pedro Island.
6503RULING ON UTILITY'S REQUEST FOR ORAL ARGUMENT
6510The Utility filed a Request for Oral Argument before the Secretary in
6522connection with the agency review of its exceptions to the Hearing Officer's
6534Recommended Order. The provisions of Rule 62-103.200(3), Florida Administrative
6543Code, state that the Secretary of the Department, in her discretion, may grant
6556oral argument in support of a party's exceptions to a Recommended Order
6568submitted by a DOAH hearing officer. The matters before the Secretary for
6580consideration in this case are adequately set forth in the thorough joint
6592written Exceptions to Recommended Order filed by the Utility and the Department,
6604and oral argument is not necessary to clarify the issues. Accordingly, the
6616Utility's Request for Oral Argument is denied.
6623RULING ON RESPONDENTS' REQUEST FOR OFFICIAL RECOGNITION
6630The joint request filed by the Utility and the Department asks the
6642Secretary to take official recognition of a delegation order filed on July 12,
66551984, by the Secretary of the former Department of Environmental Regulation.
6666Section 120.61, Florida Statutes, and Rule 60Q-2.020, Florida Administrative
6675Code, do provide for official recognition by hearing officers in formal
6686administrative proceedings of any matters that may be judicially noticed by the
6698courts of this state. This delegation order, however, was not submitted to the
6711Hearing Officer for official recognition in the DOAH formal proceedings.
6721In the process of considering exceptions to a recommended order of a DOAH
6734hearing officer, the Secretary performs a review function comparable to an
6745appellate court. Pursuant to Section 120.57(1)(b)10, Florida Statutes, the
6754Secretary may not reject or modify the findings of fact of the Hearing Officer,
6768unless she "first determines from a review of the complete record . . . that the
6784findings of fact were not based on competent substantial evidence" or that the
6797DOAH proceedings "did not comply with essential requirements of law." (emphasis
6808supplied) Thus, it would be improper for the Secretary to modify or reject any
6822of the findings of fact of the Hearing Officer in this case based on the
6837contents of a 1984 delegation order of the Secretary of DER which was not before
6852the Hearing Officer for consideration and is not a part of the record of the
6867DOAH proceedings on agency review. See Thornber v. City of Fort Walton Beach,
6880534 So.2d 754 (Fla. 1st DCA 1988); Rosenberg v. Rosenberg, 511 So.2d 593, 595
6894(Fla. 3d DCA 1987), footnote 3.
6900Respondents' Request for Official Recognition is denied.
6907RULINGS ON RESPONDENTS' EXCEPTIONS TO RECOMMENDED ORDER Exception I.
6916This exception take issue with a portion of the last sentence of Finding of
6930Fact 14 wherein the Hearing Officer found that the island chain is vulnerable to
6944flooding, "and some areas are more vulnerable [to flooding] than others." The
6956Respondents concede in their exceptions that the evidence before the Hearing
6967Officer established that that there have been occasions when waters from the
6979Gulf of Mexico have flowed over the low-lying Don Pedro Island Into Bocilla
6992Lagoon, a dredged canal located in the interior of the Island. Respondents
7004contend that there was no evidence that some portions of the Island are more
7018vulnerable to flooding than others.
7023The record does contain some evidence which would appear to support a
7035permissible inference by the Hearing Officer that some areas of Don Pedro Island
7048are more vulnerable to flooding than others. Petitioners' Composite Exhibit 11
7059(containing a collection of beachfront and aerial photographs) and and the
7070related testimony of Petitioners Betty Brenneman and Jim Duff seem to fairly
7082support a finding that the beach-front areas of Don Pedro Island immediately
7094adjacent to the waters of the Gulf of Mexico would appear to be more vulnerable
7109to flooding than more interior Island areas to the east, which may receive some
7123protection from a "high berm" along the Gulf side of the Island. (Tr. Vol. III,
713816-42; 61-62)
7140Under Section 120.57(1)(b)10, Florida Statutes, the findings of fact of a
7151hearing officer may not be rejected or modified by a reviewing agency, unless
7164the agency first determines from a review of the complete record that such
7177findings were not based on competent substantial evidence or that the
7188proceedings on which the findings were based do not comply with the essential
7201requirements of law. Also, a reviewing agency is not free to modify or reject a
7216hearing officer's findings of fact to fit a conclusion desired by it or by a
7231party by interpreting the evidence or drawing inferences therefrom in a manner
7243different from permissible interpretations made and inferences drawn by a
7253hearing officer. Heifetz v. Dept. of Business Regulation, 475 So.2d 1277, 1281-
72651282 (Fla. 1st DCA 1985)
7270Consequently, Respondents' Exception I. is denied. Exceptions II. and III.
7280In these exceptions, the Utility and the Department challenge the
7290correctness of the Hearing Officer's findings in the second and third sentences
7302of Finding of Fact 20 and in Finding of Fact 28. These findings of the Hearing
7318Officer relate to the purported failure of the Utility to establish that the
7331proposed location of the two new wells would be "safely outside" the Federal
7344Emergency Management Agency ("FEMA") velocity zone ("V-zone"), 4/ and the
7358failure to "provide reasonable assurances that the two proposed wells would be
7370protected from damage from the velocity wave action associated with the V-zone."
7382The Respondents contend in their exceptions that (1) there is no evidence of
7395record that any portion of Don Pedro Island is located in a FEMA V-zone, and (2)
7411there are no provisions in the rules of the Department or the Water District
7425applicable to construction of public water wells prohibiting the location of
7436drinking water wells within a FEMA V-zone.
7443The record reflects that the issue of the location of the two new proposed-
7457wells in relation to a FEMA V-zone was not interjected in this case by the
7472Petitioners or Respondents, but was first raised on direct questioning by the
7484Hearing Officer of the Utility's witness John Bosserman. (Tr. Vol. II., 79-80)
7496The Respondents' exceptions suggest that the Hearing Officer's questions
7505concerning the FEMA V-zone did not arise out of the record in this case, but
7520were the result of the Hearing Officer's personal knowledge acquired in another
7532unrelated administrative hearing not involving the parties in this proceeding.
7542I will not consider this suggestion of the Hearing Officer improperly taking
7554notice of facts outside the record because my review of the Recommended Order is
7568based entirely on the record as it has been presented to me in connection with
7583the Respondents' exceptions. See City of Miami v. St. Joe Paper Co., 347 So.2d
7597622, 624 (Fla. 3d DCA 1977)
7603In any event, I concur with the Respondents' argument that that the rules
7616of the Water District and the Department setting forth the criteria for location
7629of public water wells do not contain any provisions prohibiting the location of
7642drinking water wells in a FEMA V-zone. See Rules 40D-3.505 and 62-555.312,
7654Florida Administrative Code. Furthermore, I conclude in subsequent rulings in
7664this Final Order that the location of the two proposed wells as previously
7677permitted by the Water District, is not at issue in this proceeding. Thus, the
7691location of the two proposed wells relative to an alleged FEMA V-zone does not
7705appear to be relevant to the critical issue on this case of whether the Utility
7720has provided reasonable assurances that its proposed expansion of the treatment
7731capacity of its existing water plant will not violate applicable water quality
7743standards.
7744Even assuming, arguendo, that the existence of a FEMA V-zone was relevant
7756to the Utility's application at issue here, the record reflects that the
7768Respondents are correct in their conclusion that the uncontroverted evidence in
7779this case establishes that the Utility's existing water plant facility is not
7791located in a FEMA V-zone. This is acknowledged by the Hearing Officer in
7804Finding of Fact 20. In fact, the uncontroverted evidence shows that the
7816existing water plant structures are Located in a "A-17" zone, which is less
7829vulnerable to Gulf storm surge than a "V-zone". (Tr. Vol. II., 80; Utility Ex.
784421) I also agree with the Respondents' observation that the record evidence
7856would not seem to support a permissible inference that the location of the two
7870proposed wells would be in a FEMA V-Zone due to the potential of a storm surge
7886from the Gulf, since it is undisputed that the proposed well locations are
7899eastward of and farther away from the Gulf than the existing water plant.
7912(Utility Ex. 16)
7915In view of the above, I conclude that the location of the proposed new
7929wells by the Utility relative to a FEMA V-zone is not a factor within the
7944purview of the applicable permitting rules for location of public water wells
7956and that the location of the wells is not at issue in this case. I also
7972determine that there is no competent substantial evidence of record to support a
7985finding by the Hearing Officer that the location of the two proposed wells would
7999be in a FEMA V-zone, even if this FEMA criteria was applicable to the subject
8014permit proceeding.
8016Accordingly, Respondents' Exceptions II. and III. are granted. Exception
8025IV.
8026This exception of Respondents objects to the findings in the first sentence
8038of Finding of Fact 28 wherein the Hearing Officer asserts that:
8049The two deficiencies in Applicant's proof
8055relate solely to the susceptibility of the
8062proposed wells to a significant risk of damage
8070from flooding and other disasters and the
8077location of the proposed wells relative to
8084areas least subject to localized flooding.
8090The Respondents argue that these findings are improper due to:
8100(1) The delegation from the Department to the Water District of the
8112permitting of construction of public water wells.
8119(2) Lack of competent substantial evidence of risk of damage to the wells.
8132(3) Improper shifting of burden of proof.
8139The issue of delegation to the Water District of the duty and authority for
8153the permitting of construction of public water wells is disposed of in the
8166succeeding consolidated rulings on Respondents' exceptions V. through XII. I am
8177of the view that grounds (2) and (3) above are meritorious for the following
8191reasons.
8192The Hearing Officer's unchallenged findings establish that the Utility's
8201existing water plant on Don Pedro Island is well-constructed, exceeds minimum
8212construction and operating requirements, and has been operated since the 1980's
8223in "an exemplary fashion". (Findings of Fact 3, 21, 22, 24, and 25) The
8238Hearing Officer's findings also acknowledge that the reverse osmosis filtration
8248technology currently utilized at the water plant and proposed to be expanded in
8261capacity in this permit proceeding "is one of the most effective at eliminating
8274contaminants from drinking water." (Finding of Fact 22) The Hearing Officer
8285further finds that the subject Application "proposes no material changes to the
8297existing water storage tanks, distribution system, or the size or location of
8309the building that houses the existing and proposed water treatment equipment."
8320(Finding of Fact 5)
8324A review of the transcript of testimony reflects that the Utility presented
8336the testimony of Pedro Mora, the licensed professional engineer who prepared the
8348subject Application for the Utility. Mr. Mora testified that the Application
8359complied with the Department rules and standards for the issuance of the permit
8372to expand the treatment capacity of the existing water plant. (Tr. Vol. I, 89-
838690) Mr. Mora's testimony was corroborated by the expert testimony of two
8398Department permit review specialists who were involved in the review of the
8410Utility's Application. 5/ James Oni and Gary Maier both testified that, in
8422their opinion, the Utility's proposed project complied with all Department rules
8433and standards applicable to expansion of the drinking water system at the plant
8446on Don Pedro Island. (Tr. Vol. I, 137-138; 191-193)
8455Petitioners did not come forward with any expert witnesses at the DOAH
8467hearing to controvert the prior expert testimony presented in favor of the
8479Utility's permit request. 6/ Furthermore, the record reflects that Petitioners
8489failed to present any expert or lay testimony of prior contamination of the
8502water treated at the Utility's water plant due to flooding conditions since
8514commencement of operation in the 1980's. Thus, I conclude that the challenged
8526findings of the Hearing Officer in the first sentence of Finding Of Fact 28 are
8541based on an erroneous interpretation of the Department rules and are not based
8554on competent substantial evidence of record.
8560In view of the above and the conclusions in the following ruling,
8572Respondents' Exception IV. is granted
8577Exceptions V. through XII.
8581These exceptions of the Respondents take issue with various legal
8591conclusions and rule interpretations of the Hearing Officer in Conclusions of
8602Law 38, 39, 43, 44, 47, 48, 51, 55, 56, and 66. The Respondents also take
8618exception to the Hearing Officer's ultimate recommendation that the Department
8628enter a Final Order denying the Utility's application for expansion of the
8640capacity of its existing water treatment plant. The challenged legal
8650conclusions, rule interpretations, and recommendation of the Hearing Officer all
8660deal essentially with the same basic issue of the extent of the Department's
8673delegation to the Water District of responsibility for the permitting of public
8685water wells.
8687The Utility and the Department have consistently maintained the position
8697before the Hearing Officer and in these exceptions that the Department has
8709delegated to the Water District final authority and total responsibility to
8720issue permits for the location, construction, repair, and abandonment of public
8731water wells. It is undisputed that the Water District issued the two water well
8745permits to the Utility on February 8, 1995. Thus, these water well permits were
8759issued by the Water District prior to the commencement of this administrative
8771proceeding and even prior to the time that the Department issued its notice of
8785intent to issue the subject water treatment system expansion permit.
8795In the challenged Conclusions of Law identified above, the Hearing Officer
8806goes through a process of construing, in para materia, various rules of the
8819Department to support his interpretations and legal conclusions that the
8829Department has at least retained concurrent jurisdiction over the permitting of
8840public water wells. The Respondents contend in their exceptions that these rule
8852interpretations and resulting legal conclusions of the Hearing officer arc
8862erroneous and should be rejected. I concur with these exceptions of the
8874Respondents for the following reasons:
88791. The controlling provisions of Section 373.308, Florida Statutes, impose
8889a mandatory duty on the Department to delegate to the various water management
8902districts the authority to implement programs for the issuance of permits for
8914the location, construction, repair, and abandonment of water wells. Respondents
8924correctly observe in their exceptions that prior to the year 1983, the statutory
8937language in this delegation statute was permissive rather than mandatory. See
8948Section 373.308, Florida Statutes (1981). The 1983 statutory change inserting
8958the critical term "shall" for the prior permissive term "may" seems to evidence
8971the clear intent of the Legislature to ensure that the permitting of public
8984water wells would thereafter be handled on a regional basis by the five water
8998management districts. This statutory mandate to delegate the permitting of
9008public water wells to the water management districts was carried out by the
9021Department through the adoption of implementing agency rules. See, e.g., Rule
903262-555.510, Florida Administrative Code. 7/
90372. The Department's public water treatment specialists James Oni and Gary
9048Maier both testified at the DOAH formal hearing that the Department does not
9061currently have anything to do with the issuance of water well permits and that
9075such permits are issued by the water management districts. (Tr. Vol. 1, 140,
9088198-199; Vol. III, 93). Both Mr. Oni and Mr. Maier were accepted by the Hearing
9103Officer in this case as experts in applying Department rules to drinking water
9116treatment plants. (Tr. Vol. 1, 133-135, 191). A review of the record does not
9130indicate the presence of any other competent substantial evidence to the
9141contrary.
91423. The case law of Florida holds that great deference should be accorded
9155to administrative interpretations of statutes and rules that the agency is
9166required to enforce, and such administrative interpretations should not be
9176overturned unless clearly erroneous. See, e.g., Falk v. Beard, 614 So.2d 1086,
91881089 (Fla. 1993); Dept. of Env. Regulation v. Goldring, 477 So.2d 532, 534 (Fla.
92021985); Harloff v. City of Sarasota, 575 So.2d 1324, 1327 (Fla. 2d DCA 1991);
9216Reedy Creek Improvement Dist. v. Dept. of Env. Regulation, 486 So.2d 642, 648
9229(Fla. 1st DCA 1986). I conclude that this interpretations by Mr. Oni and Mr.
9243Maier of no current Department responsibility for the issuance of public water
9255well permits are not clearly erroneous. Rather, these interpretations appear to
9266be entirely consistent with the controlling provisions of Section 373.308,
9276Florida Statutes, and the Department's related rules dealing with delegation of
9287water well permitting to the water management districts.
92954. The only apparent source for the proposition that the Department has
9307retained concurrent jurisdiction with the water management district for
9316permitting public water wells is the Hearing Officer's personal interpretations
9326of the statutory and rule provisions quoted from his Recommended Order. 8/ At
9339the administrative review level the agency head is free to exercise his or her
9353judgment and reject erroneous conclusions of law or rule interpretations of a
9365hearing officer. See, e.g., Section 120.57(1)(b)10, Florida Statutes;
9373MacPherson v. School Board of Monroe County, 505 So.2d 682 (Fla. 3d DCA 1987);
9387Siess v. Dept. of Health and Rehabilitative Services, 468 So.2d 478 (Fla. 2d DCA
94011985); Alles v. Dept. of Professional Regulation, 423 So.2d 624 (Fla. 5th DCA
94141982). I conclude that these challenged rule interpretations and related
9424conclusions of law of the Hearing Officer are erroneous and must be rejected.
9437Based on the above, Respondents' Exceptions V., VI., VII., VIII., IX., X.,
9449XI., and XII. are granted.
9454Conclusion
9455I share the Hearing Officer's concern with the fact that the Petitioners
9467apparently did not receive actual notice of the Utility's pending water well
9479applications prior to the permits being issued by the Water District in February
9492of 1995. I would note that the record does not contain any testimony or other
9507evidence that any of the Petitioners in this case actually filed a written
9520request with the Water District to receive a copy of any pending applications
9533affecting Don Pedro Island as seemingly authorized by the Water District's
9544rules. See, Rule 40D-1.603(4), Florida Administrative Code. In any event, I am
9556not aware of any precedent for the Department having the legal authority to deny
9570a water treatment system modification permit to an applicant because a permit
9582challenger did not have actual knowledge of a related water well permit
9594application having been filed with a water management district prior to its
9606issuance of the permit. I am also not aware of any legal authority for the
9621Department to reverse or modify the actions of a water management district in
9634issuing water well permits eight months prior, particularly in a formal
9645administrative proceeding in which the water management district is not even a
9657party.
9658It is therefore ORDERED:
9662A. The findings in paragraph 20 of the Recommended Order are modified by
9675deleting therefrom the second sentence.
9680B. The findings in paragraph 23 of the Recommended Order are rejected in
9693their entirety.
9695C. The findings in paragraph 28 of the Recommended Order are modified by
9708deleting therefrom the first sentence.
9713D. Conclusions of Law 38, 39, and 43 of the Recommended Order are rejected
9727their its entirety.
9730E. Conclusion of Law 44 of the Recommended Order is modified by deleting
9743therefrom the last sentence.
9747F. Conclusion of Law 47 of the Recommended Order is modified by deleting
9760therefrom the first sentence.
9764G. Conclusions of Law 48, 51, 55, 56, and 65 of the Recommended Order are
9779rejected in their entirety.
9783H. Conclusion of Law 66 of the Recommended Order is modified by deleting
9796therefrom the first sentence.
9800I. The Recommendation of the Hearing Officer on pages 22-23 of the
9812Recommended Order is rejected in its entirety.
9819J. All of the Hearing Officer's remaining findings of fact and conclusions
9831of law not expressly modified or rejected in paragraphs A through I above are
9845adopted and incorporated herein by reference.
9851K. The Department's South District Office is directed to ISSUE to the
9863applicant Bocilla Utilities, Inc., permit number 5084079 for expansion of its
9874existing water treatment plant on Don Pedro Island, subject to the conditions
9886set forth in the Notice of Intent to Issue.
9895Any party to this Order has the right to seek judicial review of the Order
9910pursuant to Section 120.68, Florida Statutes, by the filing of a Notice of
9923Appeal pursuant to Rule 9.110, Florida Rules of Appellate Procedure, with the
9935clerk of the Department in the Office of General Counsel, 3900 Commonwealth
9947Boulevard, Tallahassee, Florida 32399-3000; and by filing a copy of the Notice
9959of Appeal accompanied by the applicable filing fees with the appropriate
9970District Court of Appeal. The Notice of Appeal must be filed within 30 days
9984from the date this Order is filed with the clerk of the Department.
9997DONE AND ORDERED this 9th day of October, 1995, in Tallahassee, Florida.
10009STATE OF FLORIDA DEPARTMENT
10013OF ENVIRONMENTAL PROTECTION
10016_________________________________
10017VIRGINIA B. WETHERELL
10020Secretary
10021Marjory Stoneman Douglas Building
100253900 Commonwealth Boulevard
10028Tallahassee, Florida 32399-3000
10031FILING AND ACKNOWLEDGMENT
10034FILED, ON THIS DATE PURSUANT TO S. 120.52
10042FLORIDA STATUES WITH THE DESIGNATED
10047DEPARTMENT CLERK, RECEIPT OF WHICH
10052IS HEREBY ACKNOWLEDGED.
10055_______________________________
10056B. Reader. 10/09/95
10059DEPUTY CLERK DATE
10062ENDNOTES
100631/ The term "Department" in this Final Order will include the former Department
10076of Environmental Regulation, a predecessor agency of the present Department of
10087Environmental Protection.
100892/ The Utility and the Department will sometimes be referred to collectively as
10102the "Respondents".
101053/ The Utility initially proposed locating the plant on the mainland and
10117conveying water through submerged pipes to Don Pedro Island. This proposal was
10129approved by the Army Corps of Engineers and the former Department of
10141Environmental Regulation, but the Trustees of the Internal Improvement Trust
10151Fund denied the Utility's request for an easement across sovereign submerged
10162lands. After failing to obtain a sovereign submerged land easement, the Utility
10174obtained permits to build a reverse-osmosis (RO) water plant at its present
10186location on the barrier island. Included among the permits was a permit from
10199the Department of Natural Resources dated September 11, 1985, allowing the
10210Utility to construct the water treatment plant and two underground concrete
10221water storage tanks up to 100 feet seaward of the coastal construction control
10234line.
102354/ A "FEMA V-zone" is a term whose source is derived from the provisions of the
10251National Flood Insurance Program. In 44 CFR 59.1, a "FEMA V-zone" is indirectly
10264defined as a coastal "area of specific flood hazard extending from offshore to
10277the inland limit of a primary frontal dune along an open coast and any other
10292area subject to high velocity wave action from storms or seismic sources."
103045/ James Oni is a licensed professional engineer in this state who holds the
10318title of Professional Engineer II with the Department. (Tr. Vol. 1. 132) Mr.
10331Oni's supervisor Gary Maier is also a Florida licensed professional engineer who
10343holds the title of Professional Engineer III with the Department. (Tr. Vol. 1,
10356190). Both Mr. Oni and Mr. Maier were accepted by the Hearing Officer as
10370experts in the operation of drinking water treatment plants and in applying
10382Department rules relating to drinking water treatment plants. (Tr. Vol. 1, 133-
10394135, 191)
103966/ In the landmark case of Florida Dept. of Transportation v. J.W.C. Co., Inc.,
10410396 So.2d 778 (Fla. 1st DCA 1981), the court wrote a seminal opinion dealing
10424with the respective evidentiary burdens of the permit applicant and permit
10435challenger in a formal administrative hearing. The court concluded that once
10446the permit applicant has presented its evidence and has made a preliminary
10458showing of "reasonable assurances" that applicable Department standards will not
10468be violated, then the burden shifts to the permit challenger to go forward with
10482evidence to prove that the applicant is not entitled to the permit. Id. 789.
10496The court also observed that the permit challenger must present "contrary
10507evidence of equivalent quality" to that presented by the permit applicant. Id.
10519789. It is evident that the Petitioners in this case failed to go forward with
10534the presentation of controverting evidence of equivalent quality to that
10544presented by the Respondents' experts in favor of the permit.
105547/ The Department retained jurisdiction to establish minimum standards for the
10565location, construction, repair, and abandonment of water wells throughout the
10575state as authorized by Section 373.308(4), Florida Statutes. These Department
10585minimum standards for water wells are currently set forth in Chapters 62-524,
1059762-531, 62-532 and 62-555, F.A.C. The Water District has expressly incorporated
10608these Department minimum water well standards into its own rules. See Rule 40D-
106213.037(1), F.A.C.
106238/ The Hearing Officer suggests in Conclusion of Law 65 that the location of
10637the two proposed water wells is at issue in this case because they are part of
10653the "plant site" as referred to in Department Rule 62-555.310, F.A.C. This
10665conclusion of the Hearing Officer is not compelling. The Hearing Officer's
10676unchallenged Finding of Fact 17 establishes that the proposed locations of the
10688two wells would be 200 and 450 feet respectively from the water treatment tanks.
10702The remoteness of the proposed water wells from the existing water plant
10714structure does not seem to support the Hearing Officer's conclusion. Also, the
10726viability of this conclusion is further undermined by the fact the Department
10738standards for location of the "plant site" and for location of public drinking
10751water wells are set forth in two separate rules. See, Rule 62-555.310 and 62-
1076555-312, F.A.C.
10767CERTIFICATE OF SERVICE
10770I HEREBY CERTIFY that a copy of the foregoing Final Order has been sent by
10785U.S. Mail to:
10788Robert Starr
10790Post Office Box 5337
10794Grove City, Florida 34224
10798Betty Brenneman
10800Post Office Box 67
10804Placida, Florida 33946
10807M. Christopher Bruant
10810OERTEL HOFFMAN
10812Post Office Box 6507
10816Tallahassee, Florida 32314-6507
10819and by hand delivery to:
10824Thomas I. Mayton, Jr.
10828Assistant General Counsel
10831Department of Environmental Protection
108353900 Commonwealth Blvd., M.S. 35
10840Tallahassee, Florida 32399-3000
10843Ann Cole, Clerk
10846and
10847Robert E. Meale, Hearing Officer
10852DIVISION OF ADMINISTRATIVE HEARINGS
10856The DeSoto Building
108591230 Apalachee Parkway
10862Tallahassee, Florida 32300-1550
10865Jim Duff
10867Post Office Box 41
10871Placida, Florida 33946
10874this 10th day of October, 1995.
10880STATE OF FLORIDA DEPARTMENT
10884OF ENVIRONMENTAL PROTECTION
10887________________________________
10888J. TERRELL WILLIAMS
10891Assistant General Counsel
108943900 Commonwealth Blvd., MS 35
10899Tallahassee, Florida 32399-3000
10902Telephone: 904/488-9314
- Date
- Proceedings
- Date: 01/17/1996
- Proceedings: AGENCY APPEAL, ONCE THE RETENTION SCHEDULE OF -KEEP ONE YEAR AFTER CLOSURE- IS MET, CASE FILE IS RETURNED TO AGENCY GENERAL COUNSEL. -ac
- Date: 11/09/1995
- Proceedings: Final Order filed.
- Date: 11/08/1995
- Proceedings: AGENCY APPEAL, ONCE THE RETENTION SCHEDULE OF -KEEP ONE YEAR AFTER CLOSURE- IS MET, CASE FILE IS RETURNED TO AGENCY GENERAL COUNSEL. -ac
- Date: 10/10/1995
- Proceedings: Final Order filed.
- PDF:
- Date: 08/25/1995
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 07/31/95 & 08/01/95.
- Date: 08/18/1995
- Proceedings: Bocilla Utilities` Notice of Filing Bocilla Utilities` First Set of Interrogatories to Petitioners; Respondent Bocilla Utilities, Inc.`s First Set of Interrogatories to Petitioner Robert Starr filed.
- Date: 08/18/1995
- Proceedings: Joint Proposed Recommended Order of Respondents Bocilla Utilitites, Inc., and Department of Environmental Protection filed.
- Date: 08/10/1995
- Proceedings: Letter to hearing officer from Robert Starr & Betty Brenneman Re: Response to Motion by Respondent for attorney fees and costs filed.
- Date: 08/08/1995
- Proceedings: Transcript of Proceedings ; Notice of Filing Volume II of the Original Transcript of Final Hearing filed.
- Date: 08/07/1995
- Proceedings: Transcript of Proceedings Volume I and Volume III ; Notice of Filing Original Transcript of Final Hearing; Letter to M. Christopher Bryant from Maryanne Wagner Re: Transcripts filed.
- Date: 07/31/1995
- Proceedings: Petitioners Robert Starr-Betty Brenneman-Jim Duff Motion In Limine; Respondent Bocilla Utilities Response to Petitioners Request for Admissions; Supplemental Petitioners Notice of Witness Expected to Give Testimony; Bocilla Utilities Motion
- Date: 07/31/1995
- Proceedings: CASE STATUS: Hearing Held.
- Date: 07/28/1995
- Proceedings: Bocilla Utilities Motion for Attorney`s Fees and Costs filed.
- Date: 07/26/1995
- Proceedings: (Petitioners`) Notice of Filing Answers to Request for Admissions; Respondent Bocilla Utilities Response to Petitioners` Request for Admissions; Petitioners` Notice of Witness Expected to Give Testimony filed.
- Date: 07/26/1995
- Proceedings: (M. Christopher Bryant) Bocilla Utilities Motion in Limine filed.
- Date: 07/21/1995
- Proceedings: (Petitioners) (2) Notice of Filing Answers to Interrogatories; Petitioners` First Set of Interrogatories to Respondent Bocilla Utilities, Inc.; Petitioners` First Set of Interrogatories to Respondent State of Florida Department of Environmental Protection
- Date: 07/17/1995
- Proceedings: Respondent Bocilla Utilities Response to Petitioners` Request for Admissions filed.
- Date: 07/12/1995
- Proceedings: Bocilla Utilities` Notice of Service of Answers to Petitioners` First Set of Interrogatories filed.
- Date: 07/10/1995
- Proceedings: DEP`s Notice of Service of Answers to Interrogatories filed.
- Date: 06/30/1995
- Proceedings: (Respondent) Notice of Filing Answers to Interrogatories filed.
- Date: 06/19/1995
- Proceedings: (Michele d`Amour) Petition for Withdrawal from Administrative Procedure, DOAH Case No. 95-1577 and DEP/OGC Case No. 95-665 filed.
- Date: 06/19/1995
- Proceedings: Petitioner's Request for Admission from Respondent Bocilla Utilities Inc.; Notice of Service of Request for Admissions; Petition by Richardand Jane Bossey for Withdrawal from the Petition for Administrative Proceeding; Letter to M r and Mrs. Richard Bosse
- Date: 06/14/1995
- Proceedings: Order Granting Motion sent out.
- Date: 06/12/1995
- Proceedings: (Joint) (2) Notice of Service of Interrogatories; Petitioners` First Set of Interrogatories to Respondent State of Florida Department of Environmental Protection; Petitioners` First Set of Interrogatories to Respondent Bocilla utilities, Inc. filed.
- Date: 06/01/1995
- Proceedings: Respondent Bocilla Utilities, Inc.`s Motion to Dismiss and to Strike Petitioners` More Definite Statement filed.
- Date: 05/30/1995
- Proceedings: Petitioner`s Response to Request for More Definite Statement filed.
- Date: 05/17/1995
- Proceedings: (Respondent) Notice of Service of Interrogatories filed.
- Date: 05/10/1995
- Proceedings: Order on Motions to Dismiss and Strike sent out. (ruling on motions)
- Date: 05/09/1995
- Proceedings: Notice of Hearing sent out. (hearing set for 7/31/95; 12:00 noon; Port Charlotte)
- Date: 04/21/1995
- Proceedings: Department of Environmental Protection`s Supplemental Response to Initial Order filed.
- Date: 04/18/1995
- Proceedings: Petitioners` Opposition to Respondent Bocilla Utilities, Inc.,s Motion to Dismiss and Motion to Strike Petition for Administrative Proceedings filed.
- Date: 04/12/1995
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
- Date: 04/07/1995
- Proceedings: Bocillia Utilities, Inc.`s, Request for Oral Argument on its Motion to Dismiss and Strike Petition for Formal Administrative Proceedings; Bocillia Utilities, Inc.`s, Motion to Dismiss and Motion to Strike Petition for Administrative Proceedings filed.
- Date: 04/04/1995
- Proceedings: (Respondent) Notice of Appearance as Counsel filed.
- Date: 04/04/1995
- Proceedings: (DEP) Intent to Use; Notice of Intent to Issue Permit filed.
- Date: 04/04/1995
- Proceedings: Initial Order issued.
- Date: 03/31/1995
- Proceedings: Request for Assignment of Hearing Officer and Notice of Preservation of Record; Petition for Administrative Proceeding; Requirements For Service Connection filed.