98-002184
John Workman vs.
Chuck Emling And Department Of Environmental Protection
Status: Closed
Recommended Order on Monday, May 10, 1999.
Recommended Order on Monday, May 10, 1999.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8JOHN WORKMAN, )
11)
12Petitioner, )
14)
15vs. ) Case No. 98-2184
20)
21CHUCK EMLING and STATE OF FLORIDA, )
28DEPARTMENT OF ENVIRONMENTAL )
32PROTECTION, )
34)
35Respondents. )
37______________________________________)
38RECOMMENDED ORDER
40This cause came on for formal proceeding before P. Michael
50Ruff, Administrative Law Judge of the Division of Administrative
59Hearings. Pursuant to notice a final hearing was conducted on
69January 15, 1999, in Pensacola, Florida.
75APPEARANCES
76For Petitioner: M. J. Menge, Esquire
82Shell, Fleming, Davis & Menge, P.A.
88Seville Tower
90Post Office Box 1831
94Pensacola, Florida 32596
97For Respondent Chuck Emling:
101Alan B. Bookman, Esquire
105Emmanuel, Sheppard & Condon
109Post Office Drawer 1271
113Pensacola, Florida 32596
116For Respondent Department of Environmental Protection:
122Ricardo Muratti, Esquire
125Department of Environmental Protection
129Douglas Building, Mail Station 35
1343900 Commonwealth Boulevard
137Tallahassee, Florida 32399-3000
140STATEMENT OF THE ISSUE
144The issue to be resolved in this proceeding concern whether
154a modification of a general permit should be issued by the
165Respondent agency Department of Environmental Protection
171(Department), to the Respondent, Chuck Emling, so as to allow
181construction and operation of a stormwater discharge facility on
190Emling's property in Gulf Breeze, Florida.
196PRELIMINARY STATEMENT
198The Respondent, Chuck Emling, owns a parcel of property in
208Santa Rosa County Florida, located along the southern right-of-
217way boundary of U.S. Highway 98. He is in the process of
229constructing a recreational center or "sports complex" to be
238known as the Gulf Breeze Sports Complex ("Club Property"). The
250property is bordered on the west by Crane Cove Boulevard and on
262the east by property owned by the Petitioner, John Workman and
273members of his family. Mr. Workman operates an automotive repair
283shop on the northern portion of his property and resides in a
295home on the southern portion of it.
302On or about October 23, 1997, Mr. Emling applied for and was
314issued a general permit by the Department for the construction of
325a new stormwater discharge facility on the subject property.
334Under prevailing law, specifically Rule 62-25.801, Florida
341Administrative Code, a general permit is automatically granted,
349without notice to any other persons or entities, for stormwater
359discharge facilities, as pertinent hereto, which have drainage
367areas of less than 100 acres and which provide retention or
378detention, with filtration, of the first one-half inch of run-
388off. No notice of this application was sent to the Petitioner or
400adjoining property owners or published in the local newspaper
409because such is not legally required.
415Mr. Emling desired to modify the design of his sports
425facility and the attendant stormwater discharge or management
433portion of the facility and thus filed an application for a
444modification of his general permit on or about March 12, 1998.
455This reflected substantial changes to the stormwater management
463plan previously filed with the Department. The retention areas,
472for instance, were reduced from some 301,787 cubic feet to
483approximately 97,110 cubic feet.
488Upon receipt of the application for modification the
496Department provided the Petitioner with notice of the
504application. The Petitioner timely filed a Petition for
512Administrative Proceeding with the Department and on May 11,
5211998, the Department requested assignment of an Administrative
529Law Judge to conduct all necessary proceedings. This proceeding
538and hearing ensued.
541The Department presented the testimony of James Sherrouse,
549an engineer with the Department and presented six exhibits which
559were admitted into evidence at the hearing. The Respondent, Mr.
569Emling, presented the testimony of Jay Baynes, a civil engineer
579with the engineering firm providing professional engineering
586assistance for Emling's project and presented one exhibit which
595was admitted into evidence. The Petitioner presented the
603testimony of John Broxson and Charles Merritt, who had observed
613the project property and the Workman property over a long period
624of time and were familiar with the natural flow of stormwaters
635over those properties. The Petitioner also testified and adduced
644the testimony of Leland Empie, a certified land surveyor who had
655performed surveying work for the Petitioner on a the subject
665properties and in the vicinity. The Petitioner also presented
674the testimony of Charles Meister, a civil engineer retained by
684the Petitioner to review the plans and calculations submitted by
694the applicant, as well as the testimony of Mr. Sherrouse the
705Department's engineer. The Petitioner presented eight exhibits
712which were admitted into evidence.
717Upon the conclusion of the proceeding the parties requested
726that it be transcribed. They requested an opportunity to submit
736proposed recommended orders which have been timely submitted and
745considered in the rendition of this recommended order.
753FINDINGS OF FACT
7561. The Respondent Chuck Emling, intends to build a sports
766complex, herein known as the "Club Property." He obtained a
776general stormwater discharge facility permit therefor, since his
784property represents a drainage area of approximately 10 acres in
794size, well under the threshold of 100 acres or less by which a
807general permit may be granted and because he proposes to
817construct and operate the facility such as to retain the first
828one-half inch of run-off. Because his plans for the sports
838complex and attendant stormwater discharge facility changed he
846applied for a modification of that general permit, which was duly
857noticed by the Department and protested by the Petitioner herein.
867The Petitioner is concerned that overflow from the retention
876areas will be channeled onto his property and that the berm at
888the northeast corner of the project site will cause natural
898stormwater flow to be diverted onto Workman's property which
907formerly flowed across Mr. Emling's property. The Petitioner
915contends that a landowner, such as the applicant, may not
925construct a berm along the borders of his property to prevent
936surface waters that would otherwise naturally flow onto his
945property from doing so, under generally accepted principles of
954real property law. 1
9582. The Department is an agency of the State of Florida
969charged, as pertinent hereto, with authority to regulate
977stormwater discharge facility construction, design and operation,
984pursuant to the legal authority cited herein.
9913. The proposed project is approximately ten acres in size
1001and the project is expected to exceed all required standards for
1012stormwater retention. The facility, as proposed in the
1020modification application, will store approximately 18,254 cubic
1028feet of run-off water and percolate it through its retention
1038system within approximately seventy-two hours. The modified
1045facility will store between 97,000 and 110,000 cubic feet of
1057stormwater for percolation which is approximately five times
1065greater than that required by regulations contained in Chapter
107462-25, Florida Administrative Code, concerning storage of one-
1082half inch of run-off, if the drainage area served by the
1093stormwater facility is 100 acres or less. The subject project
1103site is approximately 10 acres in size.
11104. Prior to development of the Club Property, an
"1119equalization pipe" ran under Crane Cove Boulevard providing for
1128run-off of stormwater which was in excess of the amount that
1139could be retained in the low-lying area immediately to the west
1150of Crane Cove Boulevard and the Club Property. This was designed
1161to allow such excess water to flow back onto the Club Property as
1174well as to allow stormwater run-off on the Club Property to the
1186east to reach the inlet of the equalization pipe to flow westward
1198into the depressed area to the west of Crane Cove Boulevard. In
1210other words, flow was permitted in both an easterly and westerly
1221direction to equalize excess stormwater on both properties and to
1231permit continuance of the historic east-to-west flow of
1239stormwater over the land surface of the properties involved
1248herein, after the installation of the obstacle consisting of
1257Crane Cove Boulevard. Installation of the pipe and Crane Cove
1267Boulevard occurred before the installation of the berms around
1276the boundary of the applicant's property which are a part of the
1288subject project.
12905. The equalization pipe under Crane Cove Boulevard has now
1300been connected to an extended pipe running under the Club
1310Property all the way to the boundary of the Club Property which
1322joins the Workman property. Some surface waters that
1330historically and naturally flowed back onto the Club Property
1339from the depressed area to the west of Crane Cove Boulevard, if
1351that area flooded, and which are kept off the Club Property by
1363the berms, can now pass through the equalization pipe without
1373flowing onto or across the Club Property, which thus prevents the
1384stormwater facility proposed to be installed from treating off-
1393site stormwater. The pipe is supposedly sited and installed at
1403an elevation so as to allow discharge off the Club Property only
1415of stormwater in excess of the retention and treatment standard
1425sub judice , which is that the facility will retain on-site all
1436stormwater run-off resulting from less than a 100-year storm
1445event.
14466. Thus, for this reason, there is little likelihood that
1456stormwater will be discharged onto the Workman property from this
1466pipe from the Club Property and the applicant's proposed
1475stormwater facility. It is also unlikely that stormwater will
1484traverse the equalization pipe and its extension to the boundary
1494of the Workman property from the west since, if the depressed
1505area lying west of Crane Cove Boulevard floods, the stormwater
1515collected there would more likely migrate westward since that is
1525the direction of natural flow.
15307. The Petitioner's case, on direct and through cross-
1539examination, establishes two problems with the application for
1547permit modification as proposed. First, the elevation of the
1556weir on the eastern boundary of the Club Property, next to the
1568Workman property, which allows water to be discharged through the
1578pipe from the Club Property onto the Workman property, above a
1589certain level, is purportedly at a lower level than the
1599calculations provided by the applicant's engineers. Their
1606calculations indicate what they believe is necessary to retain
1615stormwater up to the volume of a
1622100-year storm event before it can spill onto the Workman
1632property. The Petition contends the calculations indicate that
1640the weir would thus have to be at an elevation of 19 feet to
1654retain stormwater to that level or volume, but the applicant's
1664plans and evidence show variously that the weir would be either
1675at 18.9 feet or at
168018.3 feet.
16828. Additionally, the modification plan increases the size
1690and configuration of the earthen berm around the northern end of
1701the Club Property, moving it more toward the outer northern
1711boundary along U.S. 98. The Petitioner demonstrated two problems
1720with the size, configuration and location of the berm in this
1731area of the property, that is the northern side of the Club
1743Property in the area where it joins the northwest portion and
1754boundary of the Workman property. First, the Department of
1763Transportation (DOT) drain structure in the highway right-of-way
1771of U.S. 98, at that point, is being subjected to siltation caused
1783by unstabilized earth eroding off the berm and toward and into
1794the drainage structure. This can cause downstream siltation
1802pollution as well as actual physical blockage of all or part of
1814the drainage capability of this structure. In addition to the
1824possible pollution hazard posed by this situation it can also
1834result in water ponding on the Workman property through impedance
1844of proper drainage. Additionally, the configuration, size and
1852location of the berm on the northeast corner and portion of the
1864applicant's property may cause "backing up" or ponding of water
1874on the Workman property. The erosion to the berm must be
1885stabilized properly and the berm should be so located and
1895configured near this northeast corner of the applicant's property
1904and the northwest corner of the Workman property and other
1914necessary steps taken so as to prevent the ponding of water onto
1926the Workman property. A grant of the permit should be so
1937conditioned.
19389. The modification application proposes erosion control
1945measures, including sod and landscaping, to enhance and preserve
1954the stormwater system's integrity. During construction the
1961project and site will be protected from soil erosion and
1971sedimentation. Protective measures will include, as a minimum,
1979installing staked hay bales and silt and sediment fencing
1988downhill from any earth work activity, prior to the start of
1999construction. The project specifications require all soil
2006erosion and sedimentation to be controlled during construction
2014and retained on-site. The stormwater collection and treatment
2022system will require periodic maintenance for continued proper
2030operation, including removal of silt and debris from infiltration
2039areas and maintenance of vegetative cover. The grant of the
2049permit should be conditioned on these steps being strictly
2058followed, especially with regard to proper design and
2066configuration of any berm and sod of it, so as to prevent erosion
2079and resulting sedimentation into the DOT drainage and stormwater
2088treatment system consisting of the culverts and swales along
2097Highway 98. It is critical that those DOT structures and systems
2108be maintained in proper operating condition and not impeded by
2118construction and operation of the proposed project so as to
2128prevent the ponding of water on the adjacent property owners'
2138land.
213910. The pre-development stormwater discharge rate for the
2147project site, as shown in Appendix D to DEP Exhibit 3, was 6.55
2160cubic feet per second. The proposed project will retain all
2170stormwater on-site with up to 100 percent of the volume caused by
2182a "100-year storm." This means that the proposed 24-foot weir
2192will be set at a minimum elevation of 18.3 feet, so that no
2205stormwater will be discharged from the site until it reaches at
2216least an elevation of 18.3 feet. It will discharge less than the
2228predevelopment amount of stormwater after that point or once the
2238surface water elevation in the retention system exceeds 18.3
2247feet. Thus the Club Property stormwater design will lessen the
2257impact on all properties to the east of the development, and to
2269the west as well, because all stormwater will be retained unless
2280it exceeds the volume of 100 percent of a 100-year storm falling
2292on the site area. Thus the pre-development discharge of 6.55
2302cubic feet per second will be entirely eliminated unless such a
2313storm intensity and volume is reached. Even if the pond were to
2325reach its maximum elevation, a discharge to the east towards
2335Workman's property would only be 6.44 cubic feet per second or
2346slightly under the pre-development discharge rate.
235211. When the project is completed a "junction box" will be
2363placed at the end of the mitered end section of the 18-inch pipe
2376on the Club Property. The side discharge slot on that junction
2387box will be set at an elevation of 18.3 feet. Therefore, no
2399discharge from the Club site can flow toward Crane Cove Boulevard
2410to the west unless a storm event in excess of a 100-year storm
2423occurs, because only such an event would cause water to exceed
2434that elevation. Thus, by not otherwise discharging from the site
2444through the pipe the project will result in a lessening of any
2456previous impacts on properties both west and east of the subject
2467site from stormwater discharge.
247112. The testimony of Mr. Leland Empie, a surveyor,
2480testifying for the Petitioner, contains discussion of a purported
2489wetlands area lying just west of the Club Property, across Crane
2500Cove Boulevard and south of Highway 98. That wetlands area, if
2511indeed it is a jurisdictional wetlands area, which was not
2521definitively established, is only approximately one and one-half
2529acres in size. Mr. Empie also postulated that there may be a
2541wetlands area on the Club Property but that could not be
2552definitively determined, as he admitted himself. He testified
2560that he saw no definitive indication of jurisdictional wetlands
2569on the project site and the area in question has been "cut and
2582filled" so it is difficult to determine the fact of existence of
2594any wetlands area on the Club Property. In any event, there has
2606been no showing that the subject project will discharge
2615stormwater to any wetland except possibly the wetland west of
2625Crane Cove Boulevard, assuming that it qualifies as a
2634jurisdictional wetland, which has not been proven. If that were
2644the case, the discharge would only occur at a volume and level in
2657the stormwater system which exceeds that of a 100-year storm. If
2668such a discharge occurs it will still be, as found above, at a
2681volume-per-day less than the historic run-off volume from the
2690subject property in its predevelopment stage.
269613. In summary, no preponderant definitive evidence was
2704offered to prove that jurisdictional wetlands exist on the
2713project site. The Petitioner's surveyor witness, Mr. Empie,
2721relied on overlays of data from federal map sources to determine
2732the purported location of wetlands on a map but could not verify
2744the accuracy of the maps nor explain the difference in the manner
2756in which jurisdictional wetlands are determined by the Northwest
2765region of the Department versus the method used by the federal
2776agencies referenced in his testimony.
2781CONCLUSIONS OF LAW
278414. The Division of Administrative Hearings has
2791jurisdiction of the subject matter of and the parties to this
2802proceeding. See Sections 120.569 and 120.57(1), Florida Statutes
2810(1997).
281115. If a development has the potential to discharge
2820stormwater it is subject to regulation by the Department in
2830accordance with Sections 403.061, and 403.814, Florida Statutes,
2838as well as Chapter 62-25, of the Florida Administrative Code.
2848Permitting jurisdiction over stormwater discharge facilities
2854derives from Sections 403.161, and 403.814, Florida Statutes, and
2863Rules 62-25.001, 62-25.801, and 62-4.530, Florida Administrative
2870Code.
287116. The applicant has the burden of proving that it is
2882entitled to the modification of the general permit at issue in
2893this proceeding. See Department of Transportation vs. J.W.C.
2901Company, Inc. , 396 So. 2d 778 (Fla. 1st DCA 1981). The
2912Respondent, Mr. Emling, has offered a preponderance of evidence,
2921regarding the stormwater facility concerning its nature and scope
2930so as to support the proposed modification. The Respondent has
2940established that the project will meet all applicable stormwater
2949discharge criteria.
295117. Pursuant to Rule 62-25.801(1)(b), Florida
2957Administrative Code, a general permit is granted to any person
2967for the construction and operation of a stormwater discharge
2976facility in a drainage area of less than 100 acres, which
2987provides retention of the run-off from the first one-half inch of
2998run-off. See also Rule 62-4.530(6), Florida Administrative Code.
3006It is established that retention of the first one-half inch of
3017run-off within 72 hours following the storm event in accordance
3027with Rule 62-25.025, Florida Administrative Code, will occur.
303518. Section 62-25.801, Florida Administrative Code,
3041provides that a general permit is granted to any person for
3052construction and operation of a new stormwater discharge facility
3061which, in pertinent part, has a drainage area of less than 100
3073acres and provides retention, or detention with filtration of the
3083first one-half inch of run-off. There is no question that this
3094facility meets that standard. Consequently, it was entitled to
3103the general permit, which it received upon a showing that such
3114standard would be met, without having to comply with the other
3125notice and permit requirements of Chapter 62-25, Florida
3133Administrative Code. The Department deemed the filing of the
3142modification application a substantial enough modification, that
3149it required notice in accordance with prevailing law and an
3159opportunity for a point-of-entry for persons situated as the
3168Petitioner.
316919. The Petitioner cites Rule 62-25.040, Florida
3176Administrative Code, containing the construction permit
3182requirements for stormwater discharge facilities, referencing the
"3189public interest" to be served by the discharge as one standard
3200applicable to this case and the other standard concerning whether
"3210best management practices" are proposed to be followed. The
3219preponderant evidence of the record shows that best management
3228engineering and other practices will be followed in the
3237construction and operation of the project, provided that the
3246above-referenced condition concerning siltation and erosion of
3253the bermed areas is monitored and attended to promptly and on a
3265regular basis. Siltation of DOT's storage and drainage
3273structures can cause Mr. Workman's fear of back-up of stormwaters
3283onto his property to be realized. Such an eventuality would also
3294violate the "public interest standard" in the above-cited rule.
3303The preponderant evidence shows at this point, however, that the
3313overall operation of the project, as now designed and proven at
3324hearing, will result in a net public interest benefit, because
3334less stormwater will be discharged on adjoining properties than
3343was formerly the case in the pre-development stage from the
3353subject project site. In fact, even if a 100-year storm event
3364occurs and the weir begins to discharge water off-site, an
3374unlikely event, the discharge will still be less than the normal
3385expected discharge volume from the Club Property in its former
3395pre-development stage. Thus, overall, the preponderant proof in
3403this case shows that the public interest will be positively
3413served by installation of the subject project provided it is
3423monitored in its construction phase and in its operation phase on
3434a regular basis to ensure that sedimentation, siltation,
3442vegetation cover and berm location and configuration are properly
3451maintained, controlled and executed as the case may be.
346021. Moreover, and aside from the permitting standards in
3469that rule, it is provided in Rule 62-25.030, Florida
3478Administrative Code, "Exemptions," that new stormwater discharge
3485facilities are exempt from the notice and permit requirements of
3495Chapter 62-25, Florida Administrative Code, if they provide
3503retention or detention with filtration of the run-off from the
3513first one-half inch of stormwater if their drainage areas are
3523less than 100 acres. This circumstance describes the subject
3532project and therefore, in accordance with Rule 62-25.030(2)(b),
3540Florida Administrative Code, this project would appear to be
3549exempt from the construction permit requirements, aside from the
3558fact that under Rule 62-25.801, Florida Administrative Code, it
3567clearly qualifies for the underlying general permit, which is not
3577subjected to the notice requirements either. Thus it would
3586appear that, from a strictly legal standpoint, the public
3595interest standard and the best management practices standard, and
3604any of the other construction permitting standards do not apply
3614to this project.
361722. Thus, the Respondent has established entitlement to the
3626permit modification requested.
3629RECOMMENDATION
3630Having considered the foregoing Findings of Fact,
3637Conclusions of Law, the evidence of record, the candor and
3647demeanor of the witnesses and the pleadings and arguments of the
3658parties, it is
3661RECOMMENDED:
3662That a final order be issued by the Department of
3672Environmental Protection approving the requested modification of
3679the Respondent-Applicant's stormwater discharge general permit in
3686the manner recommended and conditioned herein.
3692DONE AND ENTERED this 10th day of May, 1999, in Tallahassee,
3703Leon County, Florida.
3706P. MICHAEL RUFF
3709Administrative Law Judge
3712Division of Administrative Hearings
3716The DeSoto Building
37191230 Apalachee Parkway
3722Tallahassee, Florida 32399-3060
3725(850) 488-9675 SUNCOM 278-9675
3729Fax Filing (850) 921-6847
3733Filed with the Clerk of the
3739Division of Administrative Hearings
3743this 10th day of May, 1999.
3749ENDNOTE
37501 / This proceeding may only encompass issues concerning whether
3760the statutes and agency rules governing stormwater facility
3768permitting, construction and operation are complied with. Aside
3776from matters involving the concept of the "Public Interest,"
3785dealt with in the Conclusions of Law below, it is the opinion of
3798the undersigned that any issues concerning "nuisance" or other
3807theory regarding such interference with the enjoyment of the
3816Petitioner's property rights are properly raised in the Circuit
3825Court.
3826COPIES FURNISHED:
3828M. J. Menge, Esquire
3832Shell, Fleming, Davis & Menge, P.A.
3838Seville Tower
3840Post Office Box 1831
3844Pensacola, Florida 32596
3847Alan Bookman, Esquire
3850Emmanuel, Shepard & Condon
3854Post Office Drawer 1271
3858Pensacola, Florida 32596
3861Ricardo Muratti, Esquire
3864Department of Environmental
3867Protection
3868Douglas Building, Mail Station 35
38733900 Commonwealth Boulevard
3876Tallahassee, Florida 32399-3000
3879Kathy Carter, Agency Clerk
3883Office of General Counsel
3887Douglas Building, Mail Station 35
38923900 Commonwealth Boulevard
3895Tallahassee, Florida 32399-3000
3898F. Perry Odom, General Counsel
3903Office of General Counsel
3907Douglas Building, Mail Station 35
39123900 Commonwealth Boulevard
3915Tallahassee, Florida 32399-3000
3918NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
3924All parties have the right to submit written exceptions within 15
3935days from the date of this recommended order. Any exceptions to
3946this recommended order should be filed with the agency that will
3957issue the final order in this case.
- Date
- Proceedings
- Date: 06/25/1999
- Proceedings: Final Order filed.
- Date: 02/22/1999
- Proceedings: Petitioner`s Exhibit 7 rec`d
- Date: 02/17/1999
- Proceedings: Petitioner`s Proposed Recommended Order filed.
- Date: 02/16/1999
- Proceedings: Respondents` Joint Proposed Recommended Order filed.
- Date: 02/01/1999
- Proceedings: (2 Volumes) Transcript filed.
- Date: 01/15/1999
- Proceedings: CASE STATUS: Hearing Held.
- Date: 01/13/1999
- Proceedings: Order Substituting Attorneys sent out. (M. Menge substituted for W. Whibbs, Jr.)
- Date: 01/12/1999
- Proceedings: Joint Motion for Substitution of Attorneys (filed via facsimile).
- Date: 10/29/1998
- Proceedings: Re-Notice of Hearing sent out. (hearing set for 1/15/99; 9:30am; Pensacola)
- Date: 09/22/1998
- Proceedings: Joint Response to Order filed.
- Date: 09/15/1998
- Proceedings: Order sent out. (hearing cancelled; parties to provide suggested hearing information within 7 days)
- Date: 09/11/1998
- Proceedings: (Petitioner) Request Continuance of Hearing filed.
- Date: 07/14/1998
- Proceedings: Re-Notice of Hearing sent out. (hearing set for 9/24/98; 9:30am; Pensacola)
- Date: 05/27/1998
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
- Date: 05/15/1998
- Proceedings: Initial Order issued.
- Date: 05/12/1998
- Proceedings: Petition For Administrative Hearing; Agency Action Letter w/attach; Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.
Case Information
- Judge:
- P. MICHAEL RUFF
- Date Filed:
- 05/12/1998
- Date Assignment:
- 05/15/1998
- Last Docket Entry:
- 06/25/1999
- Location:
- Pensacola, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED