98-002184 John Workman vs. Chuck Emling And Department Of Environmental Protection
 Status: Closed
Recommended Order on Monday, May 10, 1999.


View Dockets  
Summary: Respondent showed reasonable assurance that standards of Chapter 62-25, Florida Administrative Code, regarding storewater management and treatment would be met because of compliance with the on-site containment criteria for general permits.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8JOHN WORKMAN, )

11)

12Petitioner, )

14)

15vs. ) Case No. 98-2184

20)

21CHUCK EMLING and STATE OF FLORIDA, )

28DEPARTMENT OF ENVIRONMENTAL )

32PROTECTION, )

34)

35Respondents. )

37______________________________________)

38RECOMMENDED ORDER

40This cause came on for formal proceeding before P. Michael

50Ruff, Administrative Law Judge of the Division of Administrative

59Hearings. Pursuant to notice a final hearing was conducted on

69January 15, 1999, in Pensacola, Florida.

75APPEARANCES

76For Petitioner: M. J. Menge, Esquire

82Shell, Fleming, Davis & Menge, P.A.

88Seville Tower

90Post Office Box 1831

94Pensacola, Florida 32596

97For Respondent Chuck Emling:

101Alan B. Bookman, Esquire

105Emmanuel, Sheppard & Condon

109Post Office Drawer 1271

113Pensacola, Florida 32596

116For Respondent Department of Environmental Protection:

122Ricardo Muratti, Esquire

125Department of Environmental Protection

129Douglas Building, Mail Station 35

1343900 Commonwealth Boulevard

137Tallahassee, Florida 32399-3000

140STATEMENT OF THE ISSUE

144The issue to be resolved in this proceeding concern whether

154a modification of a general permit should be issued by the

165Respondent agency Department of Environmental Protection

171(Department), to the Respondent, Chuck Emling, so as to allow

181construction and operation of a stormwater discharge facility on

190Emling's property in Gulf Breeze, Florida.

196PRELIMINARY STATEMENT

198The Respondent, Chuck Emling, owns a parcel of property in

208Santa Rosa County Florida, located along the southern right-of-

217way boundary of U.S. Highway 98. He is in the process of

229constructing a recreational center or "sports complex" to be

238known as the Gulf Breeze Sports Complex ("Club Property"). The

250property is bordered on the west by Crane Cove Boulevard and on

262the east by property owned by the Petitioner, John Workman and

273members of his family. Mr. Workman operates an automotive repair

283shop on the northern portion of his property and resides in a

295home on the southern portion of it.

302On or about October 23, 1997, Mr. Emling applied for and was

314issued a general permit by the Department for the construction of

325a new stormwater discharge facility on the subject property.

334Under prevailing law, specifically Rule 62-25.801, Florida

341Administrative Code, a general permit is automatically granted,

349without notice to any other persons or entities, for stormwater

359discharge facilities, as pertinent hereto, which have drainage

367areas of less than 100 acres and which provide retention or

378detention, with filtration, of the first one-half inch of run-

388off. No notice of this application was sent to the Petitioner or

400adjoining property owners or published in the local newspaper

409because such is not legally required.

415Mr. Emling desired to modify the design of his sports

425facility and the attendant stormwater discharge or management

433portion of the facility and thus filed an application for a

444modification of his general permit on or about March 12, 1998.

455This reflected substantial changes to the stormwater management

463plan previously filed with the Department. The retention areas,

472for instance, were reduced from some 301,787 cubic feet to

483approximately 97,110 cubic feet.

488Upon receipt of the application for modification the

496Department provided the Petitioner with notice of the

504application. The Petitioner timely filed a Petition for

512Administrative Proceeding with the Department and on May 11,

5211998, the Department requested assignment of an Administrative

529Law Judge to conduct all necessary proceedings. This proceeding

538and hearing ensued.

541The Department presented the testimony of James Sherrouse,

549an engineer with the Department and presented six exhibits which

559were admitted into evidence at the hearing. The Respondent, Mr.

569Emling, presented the testimony of Jay Baynes, a civil engineer

579with the engineering firm providing professional engineering

586assistance for Emling's project and presented one exhibit which

595was admitted into evidence. The Petitioner presented the

603testimony of John Broxson and Charles Merritt, who had observed

613the project property and the Workman property over a long period

624of time and were familiar with the natural flow of stormwaters

635over those properties. The Petitioner also testified and adduced

644the testimony of Leland Empie, a certified land surveyor who had

655performed surveying work for the Petitioner on a the subject

665properties and in the vicinity. The Petitioner also presented

674the testimony of Charles Meister, a civil engineer retained by

684the Petitioner to review the plans and calculations submitted by

694the applicant, as well as the testimony of Mr. Sherrouse the

705Department's engineer. The Petitioner presented eight exhibits

712which were admitted into evidence.

717Upon the conclusion of the proceeding the parties requested

726that it be transcribed. They requested an opportunity to submit

736proposed recommended orders which have been timely submitted and

745considered in the rendition of this recommended order.

753FINDINGS OF FACT

7561. The Respondent Chuck Emling, intends to build a sports

766complex, herein known as the "Club Property." He obtained a

776general stormwater discharge facility permit therefor, since his

784property represents a drainage area of approximately 10 acres in

794size, well under the threshold of 100 acres or less by which a

807general permit may be granted and because he proposes to

817construct and operate the facility such as to retain the first

828one-half inch of run-off. Because his plans for the sports

838complex and attendant stormwater discharge facility changed he

846applied for a modification of that general permit, which was duly

857noticed by the Department and protested by the Petitioner herein.

867The Petitioner is concerned that overflow from the retention

876areas will be channeled onto his property and that the berm at

888the northeast corner of the project site will cause natural

898stormwater flow to be diverted onto Workman's property which

907formerly flowed across Mr. Emling's property. The Petitioner

915contends that a landowner, such as the applicant, may not

925construct a berm along the borders of his property to prevent

936surface waters that would otherwise naturally flow onto his

945property from doing so, under generally accepted principles of

954real property law. 1

9582. The Department is an agency of the State of Florida

969charged, as pertinent hereto, with authority to regulate

977stormwater discharge facility construction, design and operation,

984pursuant to the legal authority cited herein.

9913. The proposed project is approximately ten acres in size

1001and the project is expected to exceed all required standards for

1012stormwater retention. The facility, as proposed in the

1020modification application, will store approximately 18,254 cubic

1028feet of run-off water and percolate it through its retention

1038system within approximately seventy-two hours. The modified

1045facility will store between 97,000 and 110,000 cubic feet of

1057stormwater for percolation which is approximately five times

1065greater than that required by regulations contained in Chapter

107462-25, Florida Administrative Code, concerning storage of one-

1082half inch of run-off, if the drainage area served by the

1093stormwater facility is 100 acres or less. The subject project

1103site is approximately 10 acres in size.

11104. Prior to development of the Club Property, an

"1119equalization pipe" ran under Crane Cove Boulevard providing for

1128run-off of stormwater which was in excess of the amount that

1139could be retained in the low-lying area immediately to the west

1150of Crane Cove Boulevard and the Club Property. This was designed

1161to allow such excess water to flow back onto the Club Property as

1174well as to allow stormwater run-off on the Club Property to the

1186east to reach the inlet of the equalization pipe to flow westward

1198into the depressed area to the west of Crane Cove Boulevard. In

1210other words, flow was permitted in both an easterly and westerly

1221direction to equalize excess stormwater on both properties and to

1231permit continuance of the historic east-to-west flow of

1239stormwater over the land surface of the properties involved

1248herein, after the installation of the obstacle consisting of

1257Crane Cove Boulevard. Installation of the pipe and Crane Cove

1267Boulevard occurred before the installation of the berms around

1276the boundary of the applicant's property which are a part of the

1288subject project.

12905. The equalization pipe under Crane Cove Boulevard has now

1300been connected to an extended pipe running under the Club

1310Property all the way to the boundary of the Club Property which

1322joins the Workman property. Some surface waters that

1330historically and naturally flowed back onto the Club Property

1339from the depressed area to the west of Crane Cove Boulevard, if

1351that area flooded, and which are kept off the Club Property by

1363the berms, can now pass through the equalization pipe without

1373flowing onto or across the Club Property, which thus prevents the

1384stormwater facility proposed to be installed from treating off-

1393site stormwater. The pipe is supposedly sited and installed at

1403an elevation so as to allow discharge off the Club Property only

1415of stormwater in excess of the retention and treatment standard

1425sub judice , which is that the facility will retain on-site all

1436stormwater run-off resulting from less than a 100-year storm

1445event.

14466. Thus, for this reason, there is little likelihood that

1456stormwater will be discharged onto the Workman property from this

1466pipe from the Club Property and the applicant's proposed

1475stormwater facility. It is also unlikely that stormwater will

1484traverse the equalization pipe and its extension to the boundary

1494of the Workman property from the west since, if the depressed

1505area lying west of Crane Cove Boulevard floods, the stormwater

1515collected there would more likely migrate westward since that is

1525the direction of natural flow.

15307. The Petitioner's case, on direct and through cross-

1539examination, establishes two problems with the application for

1547permit modification as proposed. First, the elevation of the

1556weir on the eastern boundary of the Club Property, next to the

1568Workman property, which allows water to be discharged through the

1578pipe from the Club Property onto the Workman property, above a

1589certain level, is purportedly at a lower level than the

1599calculations provided by the applicant's engineers. Their

1606calculations indicate what they believe is necessary to retain

1615stormwater up to the volume of a

1622100-year storm event before it can spill onto the Workman

1632property. The Petition contends the calculations indicate that

1640the weir would thus have to be at an elevation of 19 feet to

1654retain stormwater to that level or volume, but the applicant's

1664plans and evidence show variously that the weir would be either

1675at 18.9 feet or at

168018.3 feet.

16828. Additionally, the modification plan increases the size

1690and configuration of the earthen berm around the northern end of

1701the Club Property, moving it more toward the outer northern

1711boundary along U.S. 98. The Petitioner demonstrated two problems

1720with the size, configuration and location of the berm in this

1731area of the property, that is the northern side of the Club

1743Property in the area where it joins the northwest portion and

1754boundary of the Workman property. First, the Department of

1763Transportation (DOT) drain structure in the highway right-of-way

1771of U.S. 98, at that point, is being subjected to siltation caused

1783by unstabilized earth eroding off the berm and toward and into

1794the drainage structure. This can cause downstream siltation

1802pollution as well as actual physical blockage of all or part of

1814the drainage capability of this structure. In addition to the

1824possible pollution hazard posed by this situation it can also

1834result in water ponding on the Workman property through impedance

1844of proper drainage. Additionally, the configuration, size and

1852location of the berm on the northeast corner and portion of the

1864applicant's property may cause "backing up" or ponding of water

1874on the Workman property. The erosion to the berm must be

1885stabilized properly and the berm should be so located and

1895configured near this northeast corner of the applicant's property

1904and the northwest corner of the Workman property and other

1914necessary steps taken so as to prevent the ponding of water onto

1926the Workman property. A grant of the permit should be so

1937conditioned.

19389. The modification application proposes erosion control

1945measures, including sod and landscaping, to enhance and preserve

1954the stormwater system's integrity. During construction the

1961project and site will be protected from soil erosion and

1971sedimentation. Protective measures will include, as a minimum,

1979installing staked hay bales and silt and sediment fencing

1988downhill from any earth work activity, prior to the start of

1999construction. The project specifications require all soil

2006erosion and sedimentation to be controlled during construction

2014and retained on-site. The stormwater collection and treatment

2022system will require periodic maintenance for continued proper

2030operation, including removal of silt and debris from infiltration

2039areas and maintenance of vegetative cover. The grant of the

2049permit should be conditioned on these steps being strictly

2058followed, especially with regard to proper design and

2066configuration of any berm and sod of it, so as to prevent erosion

2079and resulting sedimentation into the DOT drainage and stormwater

2088treatment system consisting of the culverts and swales along

2097Highway 98. It is critical that those DOT structures and systems

2108be maintained in proper operating condition and not impeded by

2118construction and operation of the proposed project so as to

2128prevent the ponding of water on the adjacent property owners'

2138land.

213910. The pre-development stormwater discharge rate for the

2147project site, as shown in Appendix D to DEP Exhibit 3, was 6.55

2160cubic feet per second. The proposed project will retain all

2170stormwater on-site with up to 100 percent of the volume caused by

2182a "100-year storm." This means that the proposed 24-foot weir

2192will be set at a minimum elevation of 18.3 feet, so that no

2205stormwater will be discharged from the site until it reaches at

2216least an elevation of 18.3 feet. It will discharge less than the

2228predevelopment amount of stormwater after that point or once the

2238surface water elevation in the retention system exceeds 18.3

2247feet. Thus the Club Property stormwater design will lessen the

2257impact on all properties to the east of the development, and to

2269the west as well, because all stormwater will be retained unless

2280it exceeds the volume of 100 percent of a 100-year storm falling

2292on the site area. Thus the pre-development discharge of 6.55

2302cubic feet per second will be entirely eliminated unless such a

2313storm intensity and volume is reached. Even if the pond were to

2325reach its maximum elevation, a discharge to the east towards

2335Workman's property would only be 6.44 cubic feet per second or

2346slightly under the pre-development discharge rate.

235211. When the project is completed a "junction box" will be

2363placed at the end of the mitered end section of the 18-inch pipe

2376on the Club Property. The side discharge slot on that junction

2387box will be set at an elevation of 18.3 feet. Therefore, no

2399discharge from the Club site can flow toward Crane Cove Boulevard

2410to the west unless a storm event in excess of a 100-year storm

2423occurs, because only such an event would cause water to exceed

2434that elevation. Thus, by not otherwise discharging from the site

2444through the pipe the project will result in a lessening of any

2456previous impacts on properties both west and east of the subject

2467site from stormwater discharge.

247112. The testimony of Mr. Leland Empie, a surveyor,

2480testifying for the Petitioner, contains discussion of a purported

2489wetlands area lying just west of the Club Property, across Crane

2500Cove Boulevard and south of Highway 98. That wetlands area, if

2511indeed it is a jurisdictional wetlands area, which was not

2521definitively established, is only approximately one and one-half

2529acres in size. Mr. Empie also postulated that there may be a

2541wetlands area on the Club Property but that could not be

2552definitively determined, as he admitted himself. He testified

2560that he saw no definitive indication of jurisdictional wetlands

2569on the project site and the area in question has been "cut and

2582filled" so it is difficult to determine the fact of existence of

2594any wetlands area on the Club Property. In any event, there has

2606been no showing that the subject project will discharge

2615stormwater to any wetland except possibly the wetland west of

2625Crane Cove Boulevard, assuming that it qualifies as a

2634jurisdictional wetland, which has not been proven. If that were

2644the case, the discharge would only occur at a volume and level in

2657the stormwater system which exceeds that of a 100-year storm. If

2668such a discharge occurs it will still be, as found above, at a

2681volume-per-day less than the historic run-off volume from the

2690subject property in its predevelopment stage.

269613. In summary, no preponderant definitive evidence was

2704offered to prove that jurisdictional wetlands exist on the

2713project site. The Petitioner's surveyor witness, Mr. Empie,

2721relied on overlays of data from federal map sources to determine

2732the purported location of wetlands on a map but could not verify

2744the accuracy of the maps nor explain the difference in the manner

2756in which jurisdictional wetlands are determined by the Northwest

2765region of the Department versus the method used by the federal

2776agencies referenced in his testimony.

2781CONCLUSIONS OF LAW

278414. The Division of Administrative Hearings has

2791jurisdiction of the subject matter of and the parties to this

2802proceeding. See Sections 120.569 and 120.57(1), Florida Statutes

2810(1997).

281115. If a development has the potential to discharge

2820stormwater it is subject to regulation by the Department in

2830accordance with Sections 403.061, and 403.814, Florida Statutes,

2838as well as Chapter 62-25, of the Florida Administrative Code.

2848Permitting jurisdiction over stormwater discharge facilities

2854derives from Sections 403.161, and 403.814, Florida Statutes, and

2863Rules 62-25.001, 62-25.801, and 62-4.530, Florida Administrative

2870Code.

287116. The applicant has the burden of proving that it is

2882entitled to the modification of the general permit at issue in

2893this proceeding. See Department of Transportation vs. J.W.C.

2901Company, Inc. , 396 So. 2d 778 (Fla. 1st DCA 1981). The

2912Respondent, Mr. Emling, has offered a preponderance of evidence,

2921regarding the stormwater facility concerning its nature and scope

2930so as to support the proposed modification. The Respondent has

2940established that the project will meet all applicable stormwater

2949discharge criteria.

295117. Pursuant to Rule 62-25.801(1)(b), Florida

2957Administrative Code, a general permit is granted to any person

2967for the construction and operation of a stormwater discharge

2976facility in a drainage area of less than 100 acres, which

2987provides retention of the run-off from the first one-half inch of

2998run-off. See also Rule 62-4.530(6), Florida Administrative Code.

3006It is established that retention of the first one-half inch of

3017run-off within 72 hours following the storm event in accordance

3027with Rule 62-25.025, Florida Administrative Code, will occur.

303518. Section 62-25.801, Florida Administrative Code,

3041provides that a general permit is granted to any person for

3052construction and operation of a new stormwater discharge facility

3061which, in pertinent part, has a drainage area of less than 100

3073acres and provides retention, or detention with filtration of the

3083first one-half inch of run-off. There is no question that this

3094facility meets that standard. Consequently, it was entitled to

3103the general permit, which it received upon a showing that such

3114standard would be met, without having to comply with the other

3125notice and permit requirements of Chapter 62-25, Florida

3133Administrative Code. The Department deemed the filing of the

3142modification application a substantial enough modification, that

3149it required notice in accordance with prevailing law and an

3159opportunity for a point-of-entry for persons situated as the

3168Petitioner.

316919. The Petitioner cites Rule 62-25.040, Florida

3176Administrative Code, containing the construction permit

3182requirements for stormwater discharge facilities, referencing the

"3189public interest" to be served by the discharge as one standard

3200applicable to this case and the other standard concerning whether

"3210best management practices" are proposed to be followed. The

3219preponderant evidence of the record shows that best management

3228engineering and other practices will be followed in the

3237construction and operation of the project, provided that the

3246above-referenced condition concerning siltation and erosion of

3253the bermed areas is monitored and attended to promptly and on a

3265regular basis. Siltation of DOT's storage and drainage

3273structures can cause Mr. Workman's fear of back-up of stormwaters

3283onto his property to be realized. Such an eventuality would also

3294violate the "public interest standard" in the above-cited rule.

3303The preponderant evidence shows at this point, however, that the

3313overall operation of the project, as now designed and proven at

3324hearing, will result in a net public interest benefit, because

3334less stormwater will be discharged on adjoining properties than

3343was formerly the case in the pre-development stage from the

3353subject project site. In fact, even if a 100-year storm event

3364occurs and the weir begins to discharge water off-site, an

3374unlikely event, the discharge will still be less than the normal

3385expected discharge volume from the Club Property in its former

3395pre-development stage. Thus, overall, the preponderant proof in

3403this case shows that the public interest will be positively

3413served by installation of the subject project provided it is

3423monitored in its construction phase and in its operation phase on

3434a regular basis to ensure that sedimentation, siltation,

3442vegetation cover and berm location and configuration are properly

3451maintained, controlled and executed as the case may be.

346021. Moreover, and aside from the permitting standards in

3469that rule, it is provided in Rule 62-25.030, Florida

3478Administrative Code, "Exemptions," that new stormwater discharge

3485facilities are exempt from the notice and permit requirements of

3495Chapter 62-25, Florida Administrative Code, if they provide

3503retention or detention with filtration of the run-off from the

3513first one-half inch of stormwater if their drainage areas are

3523less than 100 acres. This circumstance describes the subject

3532project and therefore, in accordance with Rule 62-25.030(2)(b),

3540Florida Administrative Code, this project would appear to be

3549exempt from the construction permit requirements, aside from the

3558fact that under Rule 62-25.801, Florida Administrative Code, it

3567clearly qualifies for the underlying general permit, which is not

3577subjected to the notice requirements either. Thus it would

3586appear that, from a strictly legal standpoint, the public

3595interest standard and the best management practices standard, and

3604any of the other construction permitting standards do not apply

3614to this project.

361722. Thus, the Respondent has established entitlement to the

3626permit modification requested.

3629RECOMMENDATION

3630Having considered the foregoing Findings of Fact,

3637Conclusions of Law, the evidence of record, the candor and

3647demeanor of the witnesses and the pleadings and arguments of the

3658parties, it is

3661RECOMMENDED:

3662That a final order be issued by the Department of

3672Environmental Protection approving the requested modification of

3679the Respondent-Applicant's stormwater discharge general permit in

3686the manner recommended and conditioned herein.

3692DONE AND ENTERED this 10th day of May, 1999, in Tallahassee,

3703Leon County, Florida.

3706P. MICHAEL RUFF

3709Administrative Law Judge

3712Division of Administrative Hearings

3716The DeSoto Building

37191230 Apalachee Parkway

3722Tallahassee, Florida 32399-3060

3725(850) 488-9675 SUNCOM 278-9675

3729Fax Filing (850) 921-6847

3733Filed with the Clerk of the

3739Division of Administrative Hearings

3743this 10th day of May, 1999.

3749ENDNOTE

37501 / This proceeding may only encompass issues concerning whether

3760the statutes and agency rules governing stormwater facility

3768permitting, construction and operation are complied with. Aside

3776from matters involving the concept of the "Public Interest,"

3785dealt with in the Conclusions of Law below, it is the opinion of

3798the undersigned that any issues concerning "nuisance" or other

3807theory regarding such interference with the enjoyment of the

3816Petitioner's property rights are properly raised in the Circuit

3825Court.

3826COPIES FURNISHED:

3828M. J. Menge, Esquire

3832Shell, Fleming, Davis & Menge, P.A.

3838Seville Tower

3840Post Office Box 1831

3844Pensacola, Florida 32596

3847Alan Bookman, Esquire

3850Emmanuel, Shepard & Condon

3854Post Office Drawer 1271

3858Pensacola, Florida 32596

3861Ricardo Muratti, Esquire

3864Department of Environmental

3867Protection

3868Douglas Building, Mail Station 35

38733900 Commonwealth Boulevard

3876Tallahassee, Florida 32399-3000

3879Kathy Carter, Agency Clerk

3883Office of General Counsel

3887Douglas Building, Mail Station 35

38923900 Commonwealth Boulevard

3895Tallahassee, Florida 32399-3000

3898F. Perry Odom, General Counsel

3903Office of General Counsel

3907Douglas Building, Mail Station 35

39123900 Commonwealth Boulevard

3915Tallahassee, Florida 32399-3000

3918NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

3924All parties have the right to submit written exceptions within 15

3935days from the date of this recommended order. Any exceptions to

3946this recommended order should be filed with the agency that will

3957issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 06/25/1999
Proceedings: Final Order filed.
PDF:
Date: 06/23/1999
Proceedings: Agency Final Order
PDF:
Date: 05/10/1999
Proceedings: Recommended Order
PDF:
Date: 05/10/1999
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 01/15/99.
Date: 02/22/1999
Proceedings: Petitioner`s Exhibit 7 rec`d
Date: 02/17/1999
Proceedings: Petitioner`s Proposed Recommended Order filed.
Date: 02/16/1999
Proceedings: Respondents` Joint Proposed Recommended Order filed.
Date: 02/01/1999
Proceedings: (2 Volumes) Transcript filed.
Date: 01/15/1999
Proceedings: CASE STATUS: Hearing Held.
Date: 01/13/1999
Proceedings: Order Substituting Attorneys sent out. (M. Menge substituted for W. Whibbs, Jr.)
Date: 01/12/1999
Proceedings: Joint Motion for Substitution of Attorneys (filed via facsimile).
Date: 10/29/1998
Proceedings: Re-Notice of Hearing sent out. (hearing set for 1/15/99; 9:30am; Pensacola)
Date: 09/22/1998
Proceedings: Joint Response to Order filed.
Date: 09/15/1998
Proceedings: Order sent out. (hearing cancelled; parties to provide suggested hearing information within 7 days)
Date: 09/11/1998
Proceedings: (Petitioner) Request Continuance of Hearing filed.
Date: 07/14/1998
Proceedings: Re-Notice of Hearing sent out. (hearing set for 9/24/98; 9:30am; Pensacola)
Date: 05/27/1998
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
Date: 05/15/1998
Proceedings: Initial Order issued.
Date: 05/12/1998
Proceedings: Petition For Administrative Hearing; Agency Action Letter w/attach; Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
P. MICHAEL RUFF
Date Filed:
05/12/1998
Date Assignment:
05/15/1998
Last Docket Entry:
06/25/1999
Location:
Pensacola, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (5):

Related Florida Rule(s) (6):