98-004539
Robert P. Ackert vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Thursday, December 16, 1999.
Recommended Order on Thursday, December 16, 1999.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DEPARTMENT OF ENVIRONMENTAL PROTECTION
12CLOYD TONEY (Facility 0668502540);
16JAMES F. JENNINGS (Facility 128626716);
21JAMES SCELFO (Facility 018500049);
25DARREL HANEY (Facility 128503387); OGC CASE NOS. 98-1208
33LEO COHEN and MARK GROSBY (Facility) 96-2930
40498627087); LEO COHEN and JOHN H 96-3405
47ROTH (Facility 498627088); ROBERT C. 98-1974
53ACKERT (Facility 498627087); CLOYD 98-2544
58TONEY (Facility 538628774); LUELLA R 98-2440
64CEASER (Facility 068501883); JACK A. 96-3404
70HARKNESS (Facility 158506545); and 98-2050
75PETER D. KLEIST (Facility 058500923), 97-0117
8198-1774
82Petitioners, 98-2035
84and DOAH CASE NOS. 98-2021
8998-2030
90ENVIRONMENTAL CORPORATION OF 98-4535
94AMERICA, INC., 98-4536
9798-4537
98Intervenor, 98-4538
10098-4539
101vs. 98-4540
10398-4541
104DEPARTMENT OF ENVIRONMENTAL 98-4542
108PROTECTION, 98-4543
110Respondent.
111_____________________________________/
112FINAL ORDER
114An Administrative Law Judge with the Division of
122Administrative Hearings (" DOAH") submitted his Recommended Order
131to the Department of Environmental Protection ("Department") in
141these consolidated cases. The Recommended Order indicated that
149copies were served upon counsel for Petitioners, Cloyd Toney, et
159al. ("Petitioners"), and upon counsel for Intervenor,
168Environmental Corporation of America (" ECA"). A copy of the
179Recommended Order is attached as Exhibit A. Exceptions to the
189Recommended Order were filed on behalf of Petitioners, ECA and
199the Department. The Department subsequently filed its Responses
207to the Exceptions of Petitioner and ECA. The matter is now
218before the Secretary of the Department for final agency action.
228BACKGROUND
229Petitioners funded efforts to cleanup petroleum and
236petroleum product contamination at various "Joy Food Stores"
244(some, formerly "Coastal Mart") facilities involved in these
253cases. Petitioners also filed applications with the Department
261for reimbursement of the cleanup costs under an amnesty program
271created by § 376.3071, Florida Statutes. This statutory amnesty
280program applies to owners or operators who notified the
289Department that their property was contaminated by petroleum or
298petroleum products. Under the statutory reimbursement program,
305the facility owner or operator would usually hire a contractor to
316cleanup petroleum contaminated sites. The contractor would then
324perform certain petroleum contamination cleanup program tasks
331("program tasks") required by the Department, often through
341subcontractors and suppliers.
344The first program task is an Initial Remedial Action
353("IRA"). The typical IRA consists of conducting soil borings and
365taking samples of soil at the site, removal of all contaminated
376soil identified by the soil samples, and back-filling the
385excavated area with uncontaminated soil. The next program task
394is the preparation of a Contamination Assessment Report ("CAR").
405The purpose of a CAR is to determine the vertical and horizontal
417extent of groundwater contamination. The determination of
424groundwater contamination requires installation and sampling of
431groundwater wells. The third program task is a Remedial Action
441Plan ("RAP") whereby a system to remediate the. groundwater at a
454site is designed and submitted to the Department for approval.
464The final program task is the Remedial Action (" RA") implementing
476the system designed and approved in the RAP. Upon completion of
487a program task, the facility owner, operator, or their designee
497submits an application to the Department for reimbursement of the
507cleanup costs at the various sites.
513ECA entered into contracts with " funders" to finance the
522petroleum contamination cleanup costs at the sites involved in
531the consolidated cases now on review. ECA, purportedly acting on
541behalf of its "investors," also entered into a series of
551agreements with Gurr/Omega (an environmental consulting firm) for
559cleanup of petroleum contamination at the sites. Under these
568agreements, Gurr/Omega was required to provide all labor,
576equipment, and materials and to perform all work needed to
586complete the remediation of the sites selected and approved by
596ECA. Gurr/Omega was to "complete such performance in strict
605compliance with all applicable statutes rules and regulations and
614to the satisfaction of FDEP". Gurr-Omega would submit its
624invoices for the petroleum cleanup work to ECA, and ECA would pay
636Gurr/Omega with money obtained from its investors. ECA would
645then receive an assignment of Gurr/Omega's right to reimbursement
654of cleanup costs from the Department.
660Each of the Petitioners in these consolidated cases claimed
669a 15% "second-tier" markup on funds paid to ECA. The payments to
681ECA also included a 15% "first-tier" markup on sums which ECA
692indicated were paid to subcontractors for cleanup activities
700conducted at the various sites. In October of 1996 or later, the
712Department denied the portions of numerous reimbursement
719applications filed by Petitioners relating to the 15% "first-
728tier" markups paid to ECA. Petitioners then filed their
737petitions challenging the Department's denials of reimbursement
744for the "first-tier" markups, and the petitions were referred to
754DOAH for formal administrative proceedings.
759The above-captioned cases were consolidated by DOAH, and
767Administrative Law Judge J. Lawrence Johnston (" ALJ") was
777assigned to conduct a formal administrative hearing. A DOAH
786final hearing was held before the ALJ on August 17 20, 1999, in
799Tampa, Florida. Testimony of witnesses and documentary evidence
807was presented on behalf of Petitioners and the Department. The
817ALJ subsequently entered a Recommended Order ("RO") in these
828consolidated cases on December 16, 1999.
834RECOMMENDED ORDER
836Based on his retrospective application of Ch. 99-379, § 4,
846Laws of Florida (1999), the ALJ concluded that the Department's
8561998 amendments to Rules 62-773.200(9) and 62-773.350(9)-(10),
863F.A.C., were not applicable to Petitioners' applications for
871reimbursement of the petroleum contamination cleanup costs at the
880sites involved in these cases. The ALJ also concluded that
890Petitioners had established that ECA's activities were integral
898and essential to site rehabilitation under the applicable rule
907provisions in effect at the time Petitioners' subject
915applications for reimbursements of petroleum cleanup costs were
923filed with the Department. However, the ALJ did conclude that
"933interest" payments made by ECA to Petitioners, together with
942ECA's 15% markups thereon and Petitioners' 15% markups on ECA's
952markups, were not allowable under Rules 62-773.200(12), 62-
960773.350(4)(e), and 62-773.650(1), F.A.C. (1993).
965The ALJ ultimately recommended that the Department enter a
974final order granting specified claims of Petitioners as set forth
984on page 62 of the RO for reimbursement of ECA's 15% "first tier"
997markups, together with Petitioners' 15% markups thereon. The ALJ
1006also recommended that the final order in these cases direct
1016Petitioners to repay to the Department overpayments made to them
1026of interest paid by ECA, together with ECA's 15% markups on the
1038interest and Petitioners' markups thereon, as specified on page
104763 of the RO.
1051RULINGS ON PETITIONERS' EXCEPTIONS
1055Exception 1
1057Petitioners' first Exception takes issue with Findings of
1065Fact 41 of the RO wherein the ALJ found that the subject
1077reimbursement applications submitted to the Department contained
1084no evidence that Petitioners were seeking reimbursement of
"1092interest" payments being made to Petitioners by ECA. In his
1102related Finding of Fact 42, the ALJ also found that the
1113Department first obtained evidence that the reimbursement
1120applications contained interest payments from ECA to Petitioners
1128during the course of prehearing discovery in these consolidated
1137cases. The ALJ further found that, upon such discovery, the
1147Department sought to recover those interest payments, together
1155with any markups thereon. The challenged factual findings of the
1165ALJ in paragraph 41 of the RO are affirmed in this Final Order.
1178An agency reviewing a DOAH recommended order may not reject
1188or modify the findings of fact of an administrative law judge
1199(formerly "hearing officer") unless the agency first determines
1208from a review of the entire record, and states with particularity
1219in the order, that the findings of fact were not based on
1231competent substantial evidence. See subsection 120.57(1)(1),
1237Florida Statutes. Accord Dunham v. Highlands County School
1245Board, 652 So.2d 894 (Fla. 2d DCA 1995); Dietz v. Florida
1256Unemployment Appeals Commission, 634 So.2d 272 (Fla. 4th DCA
12651994); Florida Dept. of Corrections v. Bradley , 510 So.2d 1122
1275(Fla. 1st DCA 1987). I conclude that the ALJ's Finding of Facts
128741 and 42 are based on competent substantial evidence of record.
1298This competent substantial evidence includes the expert testimony
1306at the DOAH final hearing of Charles Williams, an environmental
1316administrator in the Department's Bureau of Petroleum Storage
1324Systems. (Tr. Vol. IV, pages 112-215)
1330In addition, the case law of Florida holds that it is the
1342ALJ's responsibility to weigh the evidence presented in these
1351DOAH proceedings, resolve conflicts therein, judge the
1358credibility of witnesses, and draw permissible inferences from
1366the evidence. Heifetz v. Dept. of Business Regulation , 475 So.2d
13761277 (Fla. 1st DCA 1985). Thus, a reviewing agency may not
1387reweigh the evidence presented at a DOAH formal hearing, attempt
1397to resolve conflicts therein, or judge the credibility of
1406witnesses. Belleau v Dept. of Environmental Protection , 695
1414So.2d 1305,1307 (Fla. 1st DCA 1997); Mavnard v. Unemployment
1424Appeals Commission , 609 So.2d 143, 145 (Fla. 4th DCA 1992).
1434I decline to substitute my judgment for that of the ALJ on
1446this evidentiary challenge raised by Petitioners. Accordingly,
1453Petitioners' Exception 1 is denied.
1458Exception 2a
1460Petitioner's second Exception does not take exception to
1468any factual findings or legal conclusions in the RO on review.
1479Instead, this exception challenges the ALJ's prehearing ruling
1487denying Petitioners' Motion In Limine requesting that evidence
1495bearing on the Department's claims for recovery of alleged
"1504interest" overpayments to Petitioners be excluded at the DOAH
1513final hearing.
1515Petitioners first argue that the ALJ lacked jurisdiction to
1524hear the Department's claims for recovery of alleged overpayments
1533of interest to Petitioners based on information obtained during
1542the discovery phase of these proceedings. Petitioners
1549essentially conclude that the scope of these proceedings is
1558limited to matters set forth in their reimbursement applications
1567and in the Department's related Orders of Determinations. This
1576argument of Petitioners overlooks a basic tenet of administrative
1585law that a DOAH formal proceeding wherein an agency action is
1596contested is not merely an administrative review of prior
1605preliminary agency action, but is a de novo proceeding intended
1615to formulate final agency action. See , e.g., Hamilton County
1624Commissioners v. State Dept. of Environmental Regulation , 587 So.
16332d 1378,1387 (Fla. 1st DCA 1991); Florida Dept. of Transportation
1644v. J.W.C. Company. Inc. , 396 So 2d 778, 785 (Fla. 1st DCA 1981);
1657and McDonald v. Dept. of Banking and Finance, 346 So. 2d 569, 584
1670(Fla. 1st DCA 1977).
1674In such de novo formal hearings, neither the Department nor
1684the parties challenging the agency actions are restricted to the
1694matters set forth in the application documents or in the
1704Department's written notices of intent to issue or deny the
1714requested permits or reimbursements. See , e.g. , Hamilton County
1722Commissioners , supra, at 1387-1388; DeCarion v. Dept. of
1730Environmental Regulation, 445 So. 2d 619, 621 (Fla. 1st DCA
17401984). Therefore, it was not beyond the ALJ's jurisdiction to
1750have considered evidence in these proceedings of alleged
1758overpayments of interest by the Department to Petitioners, even
1767though the interest overpayment issue was not apparent in the
"1777four corners" of the reimbursement applications or the
1785Department's related Orders of Determinations. Hamilton County
1792Commissioners, supra , at 1387 1388; McDonald , supra , at 584.
1801Petitioners further contend that the ALJ erred, as a matter
1811of law, by ruling that the Department's interest overpayment
1820claims were "analogous to compulsory counterclaims which should
1828be determined in these proceedings". Petitioners suggest that
1837the Department should be required to commence separate audit
1846proceedings to recover the alleged interest overpayments. I
1854conclude, however, that the challenged prehearing ruling of the
1863ALJ refusing to limit the scope of the DOAH final hearing as
1875requested by Petitioners does not appear to be a matter over
1886which the Department has "substantive jurisdiction" under §
1894120.57(1)(1), Florida Statutes (1999).
1898The Florida courts have indicated that, subsequent to the
19071996 amendments to the Administrative Procedure Act, an agency
1916reviewing a DOAH recommended order is precluded from overruling
1925procedural or evidentiary rulings by an administrative law judge,
1934except "in the most extreme cases" where the proceedings "did not
1945comply with the essential requirements of law". See Florida
1955Power & Light Company v. State of Florida Siting Board , 693 So.2d
19671025,1028 (Fla. 1st DCA 1997) (Benson, J., concurring). Based on
1978my review of the record, l am unable to conclude that the cases
1991now on review are among those "extreme cases" where procedural or
2002evidentiary rulings of administrative law judges are so egregious
2011as to violate the essential requirements of law.
2019Consequently, Petitioners' Exception 2a is denied.
2025Exception 2b
2027This Exception takes issue with Conclusion of Law 94 of the
2038RO wherein the ALJ rejects Petitioners' attempt to distinguish
2047the seemingly adverse rulings of the Court in Environmental Trust
2057v. Dept. of Environmental Protection , 714 So.2d 493 (Fla. 1st DCA
20681998). In Environmental Trust , the court upheld the Department's
2077final order denying reimbursements of sums representing
"2084factoring discounts" for providing funding for the cleanup costs
2093of petroleum contamination at various sites.
2099The Environmental Trust court upheld the Department's
2106position that the cost of the factoring discounts amounted-to
2115interest on the face amount of the invoices and observed that
"2126[ i] nterest is not transformed into a reimbursable item merely
2137because the claimant elects to characterize it as a discount."
2147Id. at 497-498. At page 497 of the Environmental Trust opinion,
2158the court ruled that the "cost represented by the series of
2169discounts for providing capital is not an actual cost of the site
2181rehabilitation work" under § 376.3071 (12)(d), Florida Statutes.
2189At page 500 of the Environmental Trust opinion, the court also
2200ruled that the existing provisions of Rule 62-773 prohibited
2209reimbursement for "interest or carrying charges of any kind",
2218except for certain interest payments designated in the
2226Department's rules which were not applicable to the reimbursement
2235applications in that case. See Rule 62-773.350(4)(e), F.A.C.
2243In the challenged Conclusion of Law 94, the ALJ concluded
2253in these proceedings that Petitioners' attempt "to distinguish
2261interest payments made nearly simultaneously with receipt of
2269invoice payments from discounts is to elevate form over
2278substance. The two [payments] are equivalent." I concur with
2287these conclusions of the ALJ and conclude that the interest
2297payments at issue here are not distinguishable in substance to
2307the "factoring discounts" ruled to be nonreimbursable in the
2316Environmental Trust decision. I also concur with the ALJ's
2325related conclusions in paragraph 96 of the RO that the subject
2336interest payments made by ECA to Petitioners (and the markups
2346thereon) are not included within those permissible interest
2354payments designated in Rule 62-773.650(1), F.A.C., and are thus
2363not "interest costs incurred" under Rule 62 773.200(12), F.A.C.
2372In view of the above, Petitioners' Exception 2b is denied.
2382Request for Oral Presentation
2386Petitioners' Exception ends with a Request for Oral
2394Presentation to the Secretary. This request of Petitioners has
2403been previously denied in a separate "Order Denying Request for
2413Oral Argument" entered on January 10, 2000. This Order Denying
2423Request for Oral Argument is affirmed and incorporated by
2432reference herein. Accordingly, the portion of Petitioners'
2439Exceptions requesting permission to make an oral presentation to
2448the Secretary in these proceedings is denied for the reasons set
2459forth in the prior Order Denying Request for Oral Argument.
2469RULINGS ON DEPARTMENT'S EXCEPTIONS
2473Exception 1
2475The Department's first Exception takes issue with paragraph
248389 of the RO containing the ALJ's legal conclusion that Chapter
249499-379, § 4, Laws of Florida (1999), should be given
2504retrospective application to the Department's 1998 amendments to
2512Chapter 62-773, F.A.C. I conclude that this Exception of the
2522Department is well taken for the following reasons:
25301. Section 4 of Chapter 99-379 amended § 120.54(1)(f),
2539Florida Statutes ( Supp. 1998), by adding a sentence thereto that:
2550An agency may not adopt retroactive rules,
2557including retroactive rules intended to
2562clarify existing law, unless that power is
2569expressly authorized by statute.
2573This 1999 amendment to § 120.54(1)(f) was enacted by the
2583Legislature effective June 18,1999. It is undisputed that there
2593is no language in Chapter 99-379 expressing the intent of the
2604Legislature that the provisions of section 4 thereof should be
2614given retrospective application to agency rules adopted prior to
2623the effective date of this act.
26292. Absent a clear legislative intent to the contrary, a
2639substantive statute is presumed to act prospectively and to apply
2649only to conduct occurring after the effective date of the
2659statute. See State v. Lavazzoli , 434 So. 2d 321, 323 (Fla.
26701983); Fleeman v. Case , 342 So.2d 815 (Fla. 1976); Life Care
2681Centers v. Sawqrass Care Center 683 So.2d 609, 613 (Fla. 1st DCA
26931996). A "substantive" statute is one which "creates or imposes
2703a new obligation or duty". See , e.g . L, Gupton v. Villane Key
2717and Saw Shop. Inc. , 656 So.2d 475, 477 (Fla. 1995); Young v.
2729Altenhaus , 472 So.2d 1152, 1154 (Fla. 1985). The subject
2738provisions of Section 4 of Ch. 99-379 impose a new obligation or
2750duty on state agencies to not adopt retroactive rules.
2759Therefore, the 1999 amendment to § 120.54(1)(f), F.S., is a
2769substantive statutory provisions which should be applied
2776prospectively only to agency rules adopted after June 18,1999.
2786It is undisputed that the amendments to the petroleum cleanup
2796reimbursement provisions of Rule 62-773, F.A.C., at issue in
2805these proceedings were adopted on August 11, 1998.
28133. In addition, section 8 of Chapter 99-379 expresses the
2823clear intent of the Legislature that "[t]his act shall take
2833effect upon becoming a law." It is also undisputed that all
2844sections of Chapter 99-379 became law effective June 18,1999,
2854when the act was approved by the Governor. The Florida Supreme
2865Court has ruled that the Legislature's inclusion of an effective
2875date of a law " effectively rebuts any argument that retroactive
2885application of the law was intended ". Dept. of Revenue v.
2896Zuckerman Vernon Corp. , 354 So. 2d 353, 358 (Fla. 1977 (emphasis
2907supplied). Accord Foreman v. Russo , 624 So.2d 333, 336 (Fla. 4th
2918DCA 1993); Middlebrooks v. Dept. of State, 565 So.2d 727, 728
2929(Fla. 1st DCA 1990).
29334. Finally, l would note that the ALJ's legal conclusions
2943in paragraph 89 of the RO are inconsistent. The ALJ first cited
2955cases approving the general rule of law that administrative rules
2965are presumed to operate prospectively, in the absence of express
2975language to the contrary. However, the ALJ then concluded in the
2986last sentence of his Conclusion of Law 89 that: "[u] nder these
2998circumstances, Section 4 of Chapter 99-379 is not considered to
3008have truly retroactive effect and may be applied retroactively to
3018control these cases." If Section 4 of Chapter 99-379 "is not
3029considered to have truly retroactive effect" as the ALJ correctly
3039concluded, then it is inconsistent for the ALJ to also conclude
3050in the same sentence that these provisions "may be applied
3060retroactively to control these cases" dealing with Department
3068rule amendments adopted in 1998.
3073Based on the above rulings, the Department's Exception 1 is
3083granted. Accordingly, the ALJ's legal conclusions in paragraphs
309189 and 90 of the RO that the provisions of Section 4 of Chapter
310599-379 should be given retroactive application to the
3113Department's 1998 amendments to Rule 62-773 are rejected.
3121Exception 2
3123The Department's second and final Exception takes exception
3131to the ALJ's Conclusion of Law 92. In paragraph 92 of the RO,
3144the ALJ concludes that ECA acted in the role of a project
3156coordinator similar to a general contractor in connection with
3165the remediation of the petroleum contamination at the various
3174sites designated in these proceedings. The ALJ further concludes
3183that ECA's contributions were "integral to" and "essential to
3192completion of" site rehabilitation under the pertinent Department
3200rules. The ALJ ultimately concludes in this paragraph that ECA's
3210contributions "were enough to justify ECA's markups under these
3219rules and under Section 376.3071 (4)(c), Florida Statutes".
3228These legal conclusions of the ALJ, based on his
3237interpretations of statutory and rules provisions which the
3245Department has the duty to implement and enforce, are rejected on
3256the following grounds
32591. These statutory and rule interpretations in Conclusion
3267of Law 92 are expressly based on the ALJ's erroneous conclusion
3278that ECA's contributions or actions were "not limited by [the
32881998 amendments to] Rule 62-773.350(9)-(11)". In the preceding
3297ruling, I rejected the ALJ's retrospective application of the
3306provisions of Section 4 of Chapter 99-379 to preclude the
3316Department from applying the 1998 amendments to Rule 62-773 to
3326Petitioners' pending reimbursement applications. I thus conclude
3333that the decision in Environmental Trust , supra , is controlling
3342precedent as to these proceedings.
33472. In the Environmental Trust opinion, the court observed
3356that reviewing courts "must give great weight to the intent
3366expressed by the agency in determining whether a revised rule
3376imposes new requirements or merely clarifies existing
3383requirements". Id. at 714 So.2d 501. The court then upheld the
3395Department's position that the "revised version" of Rule 62-773
3404did not establish any new requirements, but only clarified the
3414existing rules relied upon by the Department in reviewing
3423reimbursement applications for petroleum contamination cleanup 1
3430costs. The court held in Environmental Trust that "the revised
3440version of Rule 62-773 can be applied retroactively because it
3450merely restates the Department's settled interpretation of the
3458existing rule." Id. at 501.
34633. The court ruled in Environmental Trust that "[n] othing
3473in section 376.3071, Florida Statutes (1995), creates an
3481entitlement to recover these expenses." Id. at 501. The court
3491also approved the rule of statutory construction that statutes
3500establishing economic grants or entitlements are strictly
3507construed in favor of the government and against the grantee.
3517Id. at 501. Accord 3 Sutherland Statutory Construction , § 63.02
3527(5th Ed. 1992). Therefore, any doubts as to whether a particular
3538claim for reimbursement in these proceedings represents an
3546activity integral or essential to the rehabilitation of the
3555subject contaminated sites should be resolved against
3562Petitioners.
35634. It is an established rule of administrative law in this
3574state that considerable deference should be accorded to an
3583agency's interpretation of its own rules which it is required to
3594enforce, and that such rule interpretations should not be
3603overturned unless clearly erroneous. See , e.g., Falk v. Beard ,
3612614 So.2d 1086, 1089 (Fla. 1993); State Contracting v. Dept. of
3623Transportation , 709 So 2d 607, 610 (Fla. 1st DCA 1998).
3633Furthermore, an agency's interpretation of its own administrative
3641rules does not have to be the only reasonable interpretation; it
3652is enough if the agency interpretation is a permissible one.
3662Suddath Van Lines, inc. v. Dept. of Environmental Protection, 668
3672So.2d 209,212 (Fla. 1st DCA 1996); Golfcrest Nursing Home v.
3683State, Aqencv for Health Care Administration, 662 So.2d 1330,1333
3693(Fla. 1st DCA 1995).
36975. Charles Williams, an Environmental Administrator in the
3705Department's Bureau of Petroleum Storage Systems, interpreted the
3713provisions of Rule 62-773, as amended in 1998, at the DOAH final
3725hearing. Mr. Williams testified that ECA must act in the
3735capacity of a general contractor responsible for the project
3744planning and the supervision of subcontractors and vendors while
3753the cleanup activities were being performed in order to be
3763entitled to the markups claimed in these proceedings. (Tr. Vol.
3773IV, pages 123-127) This rule interpretation is supported by the
3783plain language of current Rule 62 2 773.350(9)(e), as amended in
37941998. Mr. Williams was of the opinion that, under the
3804Department's rules, ECA was essentially acting in the role of a
" 3815funder arranger" rather than a "general contractor". (Tr. Vol.
3825IV, page 125) Mr. Williams also testified that it was Gurr/Omega,
3836not ECA, who acted in the role of general contractor in the 3
3849cleanup of the subject contaminated sites. (Tr. Vol. IV, page
3859127) The fact that Gurr/Omega, not ECA, was the "full service
3870contractor" ultimately responsible for employing and supervising
3877the subcontractors and vendors at the subject contaminated sites
3886is clearly evidenced in the ALJ's unchallenged Findings of Fact
389643-48.
3897Based on the above, the Department's Exception 2 is granted.
3907CONCLUSION
3908An agency has the principal responsibility of interpreting
3916statutes and rules within its regulatory jurisdiction and
3924expertise. Public Employees Relations Commission v. Dade County
3932Police Benevolent Association , 467 So.2d 987, 989 (Fla. 1985);
3941Florida Public Employee Council, 79 v. Daniels , 646 So.2d 813,
3951816 (Fla. 1st DCA 1994). The Department is the state agency
3962charged by the Legislature with the duty of enforcing the
3972provisions of § 376.3071, Florida Statutes, and of adopting rules
3982implementing this statutory section. Consequently, the
3988interpretation of the provisions of § 376.3071 and Rule 62-773
3998are the primary responsibility of the Department.
4005I conclude that the Department's statutory and rule
4013interpretations challenged in these cases are not "clearly
4021erroneous". To the contrary, these statutory and rule
4030interpretations viewed in light of the Environmental Trust
4038decision and the "strict construction" requirement are
4045permissible interpretations which should not be overturned. It
4053is therefore ORDERED:
4056A. The portion of the last sentence of Conclusion of Law
406789 concluding that Section 4 of Chapter 99-379 "may be applied
4078retroactively to control these cases" is rejected, and all of 4
4089Conclusions of Law 90, 92, and 93 of the RO are rejected.
4101B. As modified above, the RO is adopted and incorporated
4111herein by reference.
4114C. Petitioners' claims for reimbursements of ECA's 15%
4122markups, together with Petitioners' 15% markups thereon, as
4130specified on page 62 of the RO are DENIED.
4139D. The Department's claims for recovery from Petitioners
4147of interest overpayments made as specified on pages 62-63 of the
4158RO are GRANTED.
4161Any party to this proceeding has the right to seek judicial
4172review of the Final Order pursuant to Section 120.68, Florida
4182Statutes, by the filing of a Notice of Appeal pursuant to Rule
41949.110, Florida Rules of Appellate Procedure, with the clerk of
4204the Department in the Office of General Counsel, 3900
4213Commonwealth Boulevard, M.S. 35, Tallahassee, Florida 32399-3000;
4220and by filing a copy of the Notice of Appeal accompanied by the
4233applicable filing fees with the appropriate District Court of
4242Appeal. The Notice of Appeal must be filed within 30 days from
4254the date this Final Order is filed with the clerk of the
4266Department.
4267DONE AND ORDERED this 13th day of March, 2000, in
4277Tallahassee, Florida.
4279STATE OF FLORIDA DEPARTMENT
4283OF ENVIRONMENTAL PROTECTION
4286_________________________________
4287DAVID B. STRUMS, Secretary
4291Marjory Stoneman Douglas Building
42953900 Commonwealth Boulevard
4298Tallahassee, Florida 32399-3000
4301ENDNOTES
43021/ The "revised version" of Rule 62-773 construed by the court
4313in the Environmental Trust decision is the same version now found
4324in Rule 62-773, F.A.C., as amended effective August 11, 1998.
4334Thus, the revised version of Rule 62-773 at issue in the
4345Environmental Trust case is the same version of Rule 62 773 at
4357issue in these proceedings.
43612/ Rule 62-773.350(9)(e), as amended in 1998, reads as follows:
4371(e) No markup shall be applied by any entity, other than
4382an unrelated third party designated as the person responsible for
4392conducting site rehabilitation, that did not provide a necessary
4401and documented service that is integral to site rehabilitation by
4411actively managing and overseeing the activities of the
4419subcontractors and vendors while the site rehabilitation work was
4428being performed. Necessary services integral to site
4435rehabilitation include: negotiation of contracts with
4441subcontrators and vendors; development of specifications and
4448solicitation of quotes for equipment and supplies; scheduling and
4457coordination of subcontrator activities; and on-site supervision
4464of activities performed by subcontrators.
44693/ Mr. Williams further testified that the Department's review
4478of the reimbursement documentation provided by Petitioners
4485revealed that ECA did virtually nothing related to the site
4495cleanups, "other than a cover letter or invoice". (Tr. Vol. IV,
4507page 172)
45094/ These legal conclusions of the ALJ are rejected for the
4520reasons set forth in detail in the above rulings granting the
4531Department's Exceptions. I find that my substituted legal
4539conclusions are as reasonable or more reasonable than those legal
4549conclusions of the ALJ that were rejected in this Final Order.
4560CERTIFICATE OF SERVICE
4563I HEREBY CERTIFY that a copy of the foregoing Final Order
4574has been sent by United States Postal Service to:
4583Bradford C. Vassey, Esquire
4587Environmental Corporation of America
4591205 South Hoover Street, Suite 101
4597Tampa, FL 33609
4600Carter B. McCain, Esquire
4604MacFarlane, Ferguson & McMullen
4608400 North Tampa Street, Suite 2300
4614Tampa, FL 33601
4617Ann Cole, Clerk and
4621J. Lawrence Johnston, Administrative Law Judge
4627Division of Administrative Hearings
4631The DeSoto Building
46341230 Apalachee Parkway
4637Tallahassee, FL 32399-1550
4640and by hand delivery to:
4645J. A. Spejenkowski, Esquire
4649Department of Environmental Protection
46533900 Commonwealth Blvd., M.S. 35
4658Tallahassee, FL 32399-3000
4661this 14th day of March, 2000.
4667STATE OF FLORIDA DEPARTMENT
4671OF ENVIRONMENTAL PROTECTION
4674________________________________
4675TERRELL WILLIAMS
4677Assistant General Counsel
46803900 Commonwealth Blvd., M.S. 35
4685Tallahassee, FL 32399-3000
4688Telephone 850/488-9314
- Date
- Proceedings
- Date: 03/15/2000
- Proceedings: Final Order filed.
- Date: 12/27/1999
- Proceedings: Petitioners and Environmental Corporation of America, Inc. Exceptions to Recommended Order filed.
- Date: 12/16/1999
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held August 17-20, 1999.
- Date: 10/05/1999
- Proceedings: Order Denying Enlargement of Proposed Recommended Order sent out.
- Date: 10/04/1999
- Proceedings: (Respondent) Proposed Recommended Final Order filed.
- Date: 09/30/1999
- Proceedings: (B. Vassey) Amended Response to Motion to Exceed Limitations of Rule 28-106.215, Florida Administrative Code (filed via facsimile).
- Date: 09/29/1999
- Proceedings: Petitioner`s Response to Motion to Exceed Limitations of Rule 28-106.215, Florida Administrative Code (filed via facsimile).
- Date: 09/27/1999
- Proceedings: (Respondent) Motion to Exceed Limitations of Rule 28-106.215, Florida Administrative Code filed.
- Date: 09/27/1999
- Proceedings: Petitioner`s Recommended Final Order filed.
- Date: 09/15/1999
- Proceedings: August 17, 1999 (Day 1) Transcript ; August 18, 1999 (Day 2) ; August 19, 1999 (Day 3) ; filed.
- Date: 09/07/1999
- Proceedings: Petitioners` Response to Respondent`s Analysis of Chapter 99-379, C.S.H.B. No. 107 (filed via facsimile).
- Date: 09/01/1999
- Proceedings: 2 Boxes filed.
- Date: 08/30/1999
- Proceedings: Respondent`s Response to Petitioner`s Request for Official Recognition filed.
- Date: 08/17/1999
- Proceedings: CASE STATUS: Hearing Held.
- Date: 08/12/1999
- Proceedings: (Petitioner) Request for Official Recognition (filed via facsimile).
- Date: 08/10/1999
- Proceedings: (Petitioner) Amended Pre-Hearing Stipulation (filed via facsimile).
- Date: 08/06/1999
- Proceedings: (Petitioner) Response to Respondent`s Motion in Limine: Petitioner`s Proposed Hearing Exhibits and Testimony filed.
- Date: 08/06/1999
- Proceedings: Petitioner`s Response to Respondent`s Response to Petitioner`s Motion to Intervene and Add Environmental Corporation of America as a Party and in the Alternative Motion to Strike and Request for a Formal Hearing filed.
- Date: 08/05/1999
- Proceedings: Order on Motion to Intervene and Amend Petitions sent out. (Environmental Corporation of America is granted party status to the extent that leave is granted to ECA to Intervene and participate as a party to these proceedings)
- Date: 08/02/1999
- Proceedings: Respondent`s Pre-Trial Stipulation; Motion in Limine: Petitioners Proposed Hearing Exhibits and Testimony filed.
- Date: 08/02/1999
- Proceedings: Letter to J. Spejenkowski from B. Vassey Re: Prehearing Stipulation filed.
- Date: 07/27/1999
- Proceedings: Respondent`s Response to Petitioner`s "Motion to Intervene and Add Environmental Corporation of America as a Party" and in the Alternative Motion to Strike and Request for Formal Hearing filed.
- Date: 07/26/1999
- Proceedings: (Respondent) Notice of Intent to Pursue Attorney Fees and Costs filed.
- Date: 07/22/1999
- Proceedings: (B. Vassey) Response to Respondents Request for Admissions (Set 1) filed.
- Date: 07/21/1999
- Proceedings: (ECA) Motion to Intervene and to Amend Petitions to Add Environmental Corporation of America as a Party filed.
- Date: 06/22/1999
- Proceedings: (Respondent) Request for Admissions (Set 1); Clarification of Change in Agency Position Based on Actual Data filed.
- Date: 06/07/1999
- Proceedings: Respondent`s Withdrawal of Motion to Compel Production of Documents and Motion for Sanctions and Attorney Fees (filed via facsimile).
- Date: 06/02/1999
- Proceedings: (B. Vassey) Response to Motion to Compel Production of Documents and Motion for Sanctions and Attorney`s Fees filed.
- Date: 06/01/1999
- Proceedings: (B. Vassey) Response to Motion to Compel Production of Documents and Motion for Sanctions and Attorney`s Fees (filed via facsimile).
- Date: 05/28/1999
- Proceedings: (Respondent) Notice of Hearing (6/8/99; 10:00 a.m.) filed.
- Date: 05/28/1999
- Proceedings: Respondent`s Motion to Compel Production of Documents and Motion for Sanctions and Attorney Fees filed.
- Date: 05/24/1999
- Proceedings: Department of Environmental Protection`s Notice of Service of Answers to Petitioner`s Second Set of Interrogatories filed.
- Date: 05/24/1999
- Proceedings: Order Continuing Final Hearing sent out. (hearing set for August 17 through 20, 1999; 9:00am; Tampa) 8/17/99)
- Date: 05/21/1999
- Proceedings: (Petitioner) Amended Motion for Continuance (filed via facsimile).
- Date: 05/20/1999
- Proceedings: (Petitioner) Motion to Continue (filed via facsimile).
- Date: 05/20/1999
- Proceedings: Joint Stipulation of the Parties filed.
- Date: 05/20/1999
- Proceedings: (B. Vassey) Notice of Intent to Request Official Recognition of the Certain Statutes, Rule and Official Documents filed.
- Date: 05/20/1999
- Proceedings: (B. Vassey) List of Exhibits; List of Witnesses (filed via facsimile).
- Date: 05/19/1999
- Proceedings: (B. Vassey) List of Exhibits; List of Witnesses (filed via facsimile).
- Date: 05/18/1999
- Proceedings: Respondent`s Request for Official Recognition filed.
- Date: 05/18/1999
- Proceedings: Reconsideration of Order on Motion in Limine and Motion to Compel sent out.
- Date: 05/18/1999
- Proceedings: (B. Vassey) Motion to Withdraw Petition for Administrative Hearing (for case no. 98-4536) filed.
- Date: 05/17/1999
- Proceedings: (Respondent) Memorandum; Clarification of Agency`s Change of Position filed.
- Date: 05/17/1999
- Proceedings: (Respondent) Notice of Filing Transcript; Hearing on Pending Motions (Judge has original and copy of Transcript) filed.
- Date: 05/17/1999
- Proceedings: (B. Vassey) (3) Motion to Withdraw Petition for Administrative Hearing (for DOAH case nos. 98-2030, 98-4539, 98-4542) filed.
- Date: 05/17/1999
- Proceedings: (B. Vassey) Memorandum of Law motion to Clarify Hearing filed.
- Date: 05/13/1999
- Proceedings: Memorandum of Law Motion to Clarify Hearing (filed via facsimile).
- Date: 05/11/1999
- Proceedings: (Respondent) Notice of Change of Agency Position filed.
- Date: 05/10/1999
- Proceedings: Order on Motion in Limine and Motion to Compel sent out.
- Date: 05/06/1999
- Proceedings: (Respondent) Notice of Hearing (5/7/99; 10:00 a.m.) (filed via facsimile).
- Date: 05/06/1999
- Proceedings: Respondent`s Response to Petitioners` Motion in Limine filed.
- Date: 05/05/1999
- Proceedings: Respondent`s Response to Petitioners` Motion in Limine filed.
- Date: 05/05/1999
- Proceedings: (Petitioner) Motion in Limine (filed via facsimile).
- Date: 04/29/1999
- Proceedings: Department of Environmental Protection`s Notice of Filing Depositions Duces Tecum; Deposition of: Jack Ceccarelli ; Continued Deposition of Jack Ceccarelli (Judge has original and copy of Deposition) filed.
- Date: 04/29/1999
- Proceedings: Respondent`s Notice of Authority w/exhibits filed.
- Date: 04/27/1999
- Proceedings: Respondent`s Motion to Compel Production of Documents filed.
- Date: 04/22/1999
- Proceedings: (Petitioner) Notice and Certificate of Service of Interrogatories; Plaintiff`s Second Set of Interrogatories filed.
- Date: 03/31/1999
- Proceedings: (2) Department of Environmental Protection`s Amended Notice of Taking Depositions filed.
- Date: 03/25/1999
- Proceedings: Notice of Final Hearing (Dates and Location) sent out. (hearing set for May 25-28, 1999, starting at 9:00am on 5/25/99; Tampa)
- Date: 03/23/1999
- Proceedings: (2) Department of Environmental Protection`s Notice of Taking Depositions; Subpoena Duces Tecum (J. Spejenkowski) filed.
- Date: 03/19/1999
- Proceedings: (Respondent) Notice of Provisions Pursuant to Rule 1.351(b) Florida Rules of Civil Procedure filed.
- Date: 02/26/1999
- Proceedings: Order Continuing Final Hearing sent out. (3/9/99 hearing cancelled)
- Date: 02/25/1999
- Proceedings: Department of Environmental Protection`s Notice of Taking Depositions filed.
- Date: 02/25/1999
- Proceedings: (Petitioner) Response to Respondent`s Motion for Continuance of Final Hearing (filed via facsimile).
- Date: 02/22/1999
- Proceedings: (C. McCain) Notice of Appearance filed.
- Date: 02/19/1999
- Proceedings: Respondent`s Motion for Continuance of Final Hearing filed.
- Date: 02/18/1999
- Proceedings: (B. Vassey) Motion to Withdraw; Order (for Judge Signature) rec`d
- Date: 02/10/1999
- Proceedings: (B. Vassey) Motion for Protective Order rec`d
- Date: 01/11/1999
- Proceedings: (4) Subpoena ad Testificandum (J. Spejenkowski); (2) Subpoena Duces Tecum; (6) Return of Service filed.
- Date: 01/11/1999
- Proceedings: Response of Respondent, Department of Environmental Protection, to Petitioner`s Request for Production of Documents (Set 1) filed.
- Date: 01/08/1999
- Proceedings: Response of Respondent, Department of Environmental Protection, to Petitioner`s Request for Production of Documents (Set I) filed.
- Date: 01/08/1999
- Proceedings: Response of Respondent, Department of Environmental Protection, to Petitioner`s Request for Production of Documents (Set 1) filed.
- Date: 01/08/1999
- Proceedings: (6) Receipt of Service filed.
- Date: 12/31/1998
- Proceedings: Department of Environmental Protection`s Notice of Taking Depositions filed.
- Date: 12/23/1998
- Proceedings: Notice of Final Hearing sent out. (hearing set for March 9-12, 1999; 9:00am; Tampa)
- Date: 12/23/1998
- Proceedings: Prehearing Order sent out.
- Date: 12/23/1998
- Proceedings: Order Consolidating Cases sent out. (Consolidated cases are: 98-2021, 98-2030, 98-4535, 98-4536, 98-4537, 98-4538, 98-4539, 98-4540, 98-4541, 98-4542 & 98-4543)
- Date: 12/04/1998
- Proceedings: Department of Environmental Protection`s Notice of Service of Answers to Petitioner`s First Set of Interrogatories filed.
- Date: 11/18/1998
- Proceedings: (Respondent) Request for Production of Documents filed.
- Date: 11/18/1998
- Proceedings: Notice of Hearing and Initial Prehearing Order sent out. (hearing set for 2/3/99; 9:00am; Orlando)
- Date: 11/09/1998
- Proceedings: Answers to Interrogatories to Petitioner (set 1) filed.
- Date: 10/29/1998
- Proceedings: Plaintiff`s First Set of Interrogatories filed.
- Date: 10/29/1998
- Proceedings: (Petitioner) Notice and Certificate of Service of Interrogatories filed.
- Date: 10/28/1998
- Proceedings: (Petitioner) Motion for Venue in Tampa, Florida filed.
- Date: 10/20/1998
- Proceedings: (Respondent) Notice and Certificate of Service of Interrogatories filed.
- Date: 10/19/1998
- Proceedings: Initial Order issued.
- Date: 10/16/1998
- Proceedings: Agency Action Letter filed.
- Date: 10/13/1998
- Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; First Amended Petition for Administrative Hearing Pursuant to Section 120.57, Florida Statutes filed.