99-000694 Sarah E. Berger vs. Southern Hy Power Corporation And Department Of Environmental Protection
 Status: Closed
Recommended Order on Thursday, March 2, 2000.


View Dockets  
Summary: Applicant presented reasonable assurances that the proposed project complies with statutes and rules.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8BERNARD M. CAMPBELL and )

13BESSIE H. CAMPBELL, )

17)

18Petitioners, )

20)

21vs. ) Case No. 99-0307

26) OGC No. 98-3033

30SOUTHERN HY POWER CORPORATION )

35and STATE OF FLORIDA, DEPARTMENT )

41OF ENVIRONMENTAL PROTECTION, )

45)

46Respondents. )

48_________________________________)

49SARAH E. BERGER, )

53)

54Petitioner, )

56)

57vs. ) Case No. 99-0308

62) OGC No. 98-3022

66SOUTHERN HY POWER CORPORATION )

71and STATE OF FLORIDA, DEPARTMENT )

77OF ENVIRONMENTAL PROTECTION, )

81)

82Respondents. )

84_________________________________)

85SARAH E. BERGER, )

89)

90Petitioner, )

92)

93vs. ) Case No. 99-0694

98) OGC No. 99-0244

102SOUTHERN HY POWER CORPORATION )

107and STATE OF FLORIDA, DEPARTMENT )

113OF ENVIRONMENTAL PROTECTION, )

117)

118Respondents. )

120_________________________________)

121BERNARD and BESSIE CAMPBELL, )

126)

127Petitioners, )

129)

130vs. ) Case No. 99-0696

135) OGC No. 99-0247

139SOUTHERN HY POWER CORPORATION )

144and STATE OF FLORIDA, DEPARTMENT )

150OF ENVIRONMENTAL PROTECTION, )

154)

155Respondents. )

157_________________________________)

158RECOMMENDED ORDER

160A hearing was held pursuant to notice, on September 22

170through 24, 1999, in Inglis, Levy County, Florida, and on

180November 1 and 2, 1999, in Tallahassee, Florida, by Stephen F.

191Dean, assigned Administrative Law Judge of the Division of

200Administrative Hearings.

202APPEARANCES

203For Petitioners: John S. Clardy III, Esquire

210Post Office Box 2410

214Crystal River, Florida 34426-2410

218For Respondent Southern Hy Power Corporation:

224Daniel H. Thompson, Esquire

228Berger, Davis & Singerman

232215 South Monroe Street, Suite 705

238Tallahassee, Florida 32301

241For Respondent Department of Environmental Protection:

247Andrew Zodrow, Esquire

250Department of Environmental Protection

2543900 Commonwealth Boulevard

257Mail Station 35

260Tallahassee, Florida 32399-3000

263STATEMENT OF THE ISSUE

267Whether Southern Hy Power Corporation (Hy Power) has

275provided reasonable assurance, based on plans, test results, or

284other information, that its proposed h y droelectric facility will

294comply with the Management and Storage of Surface Water (MSSW)

304statutes and rules of Southwest Florida Water Management District

313(SWFWMD) and the Wetland Resource Management permit (WRM)/water

321quality certification statutes and rules of the Florida

329Department of Environmental Protection (DEP).

334PRELIMINARY STATEMENT

336Hy Power applied to DEP on August 31, 1993, for a WRM

348pe r mit/water quality certification to construct a hydroelectric

357f a cility on the Inglis By-Pass Channel immediately to the south

369of the spillway located on the Inglis Bypass Channel within the

380Town of Inglis, Levy County, Florida. On January 5, 1998, DEP

391issued a Notice of Denial of the Environmental Resource Permit.

401The re a sons for the denial included a finding that the

413application was incomplete and that the applicant failed to

422provide reasonable assu r ances that the proposed project would

432comply with the MSSW prov i sions of Part IV of Chapter 373,

445Florida Statutes, and the rules adopted thereu n der.

454In response to the notice of denial, Hy Power filed on

465Jan u ary 20, 1998, a motion for extension of time to file a

479petition for administrative proceeding to challenge the denial.

487In add i tion, on August 4, 1998, Hy Power filed with DEP an

501application for a MSSW permit. On November 6, 1998, DEP issued a

513Notice of Intent to Issue MSSW permit application number 38-

5230129249-002 to Hy Power to construct and operate its proposed

533hydroelectric f a cility. On December 21, 1998, DEP issued a

544Notice of Intent to issue WRM permit application number 38-

5542370696-3.001 for the pr o posed facility.

561On November 21, 1998, Ms. Berger filed a petition for formal

572administrative proceedings objecting to DEP’s intent to issue the

581MSSW permit to Hy Power. On November 23, 1998, the Campbells

592filed a petition also challenging DEP’s intent to issue the MSSW

603permit. On February 2, 1999, the Cam p bells filed a petition

615challenging that intent. DEP r e ferred the petitions to DOAH. On

627February 8, 1999, Ms. Berger also filed a petition for formal

638administrative pr o ceedings objecting to DEP’s intent to issue the

649WRM permit to Hy Power to construct the facility. On March 18,

6611999, an order was entered consolidating the four petitions.

670WITNESSES

671Hy Power called the following witnesses: Richard Volkin,

679who was accepted as an expert in the areas of engineering and

691dra w ing, construction and operation of hydroelectric facilities,

700i n cluding analysis of environmental impacts associated with such

710facilities; and Douglas Smith, who was accepted as an e x pert in

723the area of environmental engineering with special expe r tise in

734geology and hydrogeology.

737DEP called the following witnesses: Ken Huntington, who was

746accepted as an expert in the areas of Environmental Resource

756Pe r mitting criteria, and environmental impacts of dredge and fill

767projects and activities; Randy Cooper, who was accepted as an

777expert in the areas of civil engineering, surface water h y drology

789and MSSW permitting criteria; Mercily Toledo, who was accepted

798as an expert in the areas of enviro n mental impacts of dredge and

812fill activities and wetland resource management permitting

819criteria; Eric Shaw, who was a c cepted as an expert in Outstanding

832Florida Water (OFW) water body classifications; Joe May, who was

842accepted as an expert in the areas of geology and hydrogeology;

853Mary Duncan, who was accepted as an e x pert in the areas of

867permitting issues with respect to impacts on the West Indian

877Manatee and the activities regulated by DEP; and Louie

886Wainwright, who is the administrator of field operations for the

896DEP Office of Greenways and Trails.

902Petitioners called the following witnesses: Linda Sloan,

909who was accepted as an expert on the requirements of the

920Comprehe n sive Plan of Inglis and Levy County; Stephen Wilson, who

932was accepted as an expert in the field of land surveying; James

944C. Bitter, who was accepted as an expert in occup a tional safety

957and technology; Bill Edwards, who was a c cepted as an expert in

970the areas of coffer dams and construction of concrete structures

980in aquatic and semi-aquatic environments; Stephen Boyes, who was

989accepted as an expert in g e ology and hydrogeology; Gary Maidhof,

1001who was accepted as an expert in the Citrus County Manatee

1012Protection Plan; David Gammon, who is Manager of Purchase Power

1022Resources for Florida Power Corporation; Kenton Lambert, who is a

1032mai n tenance and construction specialist for the DEP office of

1043Gree n ways and Trails; Bessie Campbell, one of the Petitio n ers;

1056and Sarah E. Berger, one of Petitioners.

1063EXHIBITS

1064The parties entered 12 joint stipulated exhibits into

1072ev i dence. Hy Power entered 12 e x hibits at hearing and one late-

1087filed exhibit after the hearing had adjourned. DEP entered eight

1097exhibits into evidence. Petitioners entered 15 exhibits into

1105evidence, and proffered one exhibit, a Land Surveyor’s Drawing,

1114which was not accepted into evidence.

1120PREHEARING STIPULATION

1122The parties filed a Joint Prehearing Stipulation on or about

1132September 22, 1999, which stipulated certain issues of law and

1142fact that described the parties to this proceeding and the

1152pro j ect that is at issue. These stipulations are included or

1164inco r porated by reference as findings of fact and conclusions of

1176law in this Recommended Order.

1181STIPULATED ISSUES OF LAW

1185The parties stipulated that pre-Environmental/Resource

1190Permitting statutes and rules (ERP) are applicable to these WRM

1200and MSSW permit proceedings. The following pre-ERP statutes and

1209rules are being utilized, relevant portions of which are set

1219forth below in Section 403.918, Florida Statutes (1991); and

1228Chapter 40D-4, Florida Administrative Code (in effect prior to

1237October 3, 1995) along with Basis of Review incorporated therein.

1247The parties also stipulated to the following:

1254Jurisdiction

1255The Di vision of Administrative Hearings has

1262juri s diction over the parties to and the subject matter

1273of this proceeding pursuant to Chapter 120, Florida

1281Statutes.

1282MSSW and WRM Permitting Criteria Generally

1288Since Hy Power filed its WRM permit application on

1297August 31, 1993, the statutes and rules applicable to

1306this proceeding are those which were in effect prior to

1316the promulgation of Environmental Resource Permitting

1322Rules by DEP on October 3, 1995, as described more

1332fully below. See Section 373.414(9), Florida Statutes.

1339MSSW Permitting Criteria

1342The criteria for review for the MSSW permit is

1351contained in Rule 40D-4.301, F.A.C., as it existed on

1360or before October 3, 1995, which stated as follows:

136940D -4.301 Conditions for Issuance of

1375Permits.

1376(1) In o rder to obtain an individual

1384construction and operation permit under this

1390chapter, an applicant must give reasonable

1396assurances that the surface water management

1402system:

1403(a) provide adequate flood protection

1408and drainage,

1410(b) will not cause adverse wat er quality

1418and quantity impacts on receiving waters and

1425adjacent lands regulated pursuant to Chapter

1431373, Florida Statutes,

1434(c) will not cause discharges which

1440r e sult in any violation, in surface waters of

1450the state, of the applicable standards and

1457crit e ria of Chapter17-3, and Rule 17-4.242,

1465(d) will not cause adverse impacts on

1472surface and groun d water levels and flows,

1480(e) will not diminish the capability of

1487a lake or other impoundment to fluctuate

1494through the full range established for it in

1502Chapter 40D-8.

1504(f) will not cause adverse environmental

1510impacts, or adverse impacts to wetlands, fish

1517and wildlife, or other natural r e sources,

1525(g)can be effectively operated and

1530mai n tained,

1533(h) will not adversely affect public

1539health and safety,

1542(i) is consistent with the requirements

1548of other public age n cies,

1554(j) will not otherwise be harmful to

1561w a ter resources within the District,

1568(k) will not interfere with the legal

1575rights of others as defined in Rule 17-40.07,

1583and

1584(l) is not against pub lic policy.

1591(2) The standards and criteria contained

1597in the Basis of Review adopted by reference

1605in Rule 40D-4.091(1) apply to the design and

1613performance of surface water management

1618sy s tems to provide the reasonable assurances

1626r e quired under Rule 40D-4.301(1). Other

1633met h ods of meeting overall objectives may be

1642pr o posed and may be considered in determining

1651whether the applicant has provided the

1657re a sonable assurances required by Rule 40D-

16654.301(1).

1666DEP AUTHORITY

1668DEP has the authority to administer the SWFWMD

1676MSSW permitting rules pursuant to an interagency

1683agre e ment with SWFWMD and §373.026, Florida Statutes.

1692WRM PERMITTING CRITERIA

1695The criteria for the WRM permit application

1702a s pects of this case are governed by Chapter 403, Part

1714VIII, the "Warren S. Henderson Wetland Protection Act

1722of 1984," including Section 403.918, Florida Statutes.

1729(1991), which states in relevant part as follows:

1737(1) A permit may not be issued under

1745ss. 403.91-403.929 unless the applicant

1750pr o vides the department with reasonable

1757assu r ance that water quality standards will

1765not be violated. . . .

1771(2) A permit may not be issued under

1779ss. 403.91-403.929 unless the applicant

1784pr o vides the department with reasonable

1791assu r ance that the project is not contrary to

1801the public interest. However, for a project

1808which significantly degrades or is within an

1815Outstanding Florida Water, as provided by

1821d e partment rule, the applicant must provide

1829reasonable assurance that the project will be

1836clearly in the public interest.

1841(a) In determining whether a project is

1848not contrary to the public interest, or is

1856clearly in the public interest, the

1862depar t ment shall consider and balance the

1870following criteria:

18721. Whether the project will adversely

1878affect the public health, safety, or welfare

1885or the property of others;

18902. Whether the project will adversely

1896affect the conservation of fish and wildlife,

1903including endangered or threatened species,

1908or their habitats;

19113. Whether the project will adversely

1917affect navigation or the flow of water or

1925cause harmful erosion or shoaling;

19304. Whether the project will adversely

1936affect the fishing or recreational values or

1943marine productivity in the vicinity of the

1950project;

19515. Whether the project will be of a

1959temporary or pe r manent nature;

19656. Whether the project will adversely

1971affect or will enhance significant historical

1977and archaeological resources under the

1982prov i sions of s. 267.061; and

19897. The current condition and relative

1995value of functions being performed by areas

2002affected by the proposed activity.

2007(b) If the applicant is unable to

2014ot h erwise meet the criteria set forth in this

2024subsection, the department, in deciding to

2030grant or deny a permit, shall consider

2037mea s ures proposed by or acceptable to the

2046appl i cant to mitigate adverse effects which

2054may be caused by the project. . . .

2063The WRM permitting criteria are also governed by

2071Rule Chapters 62-4 (Permits), 62-302 (Surface Water

2078Quality Standards), 62-312 (Dredge and Fill Activities)

2085and 62-521 (Wellhead Protection), Florida

2090Administrative Code.

2092The u se of the property to generate hydroelectric

2101power is compatible with Section 253.7829(2), Florida

2108Statutes, which states:

2111The development of hydroelectric power is a

2118compatible use of greenway land and may be

2126considered by the Board of Trustees of the

2134Internal Improvement Trust Fund as an

2140allo w able use within the greenways of Lake

2149Rou s seau and the lower Withlacoochee River,

2157pr o vided that such hydroelectric power

2164complies with all requisite state and federal

2171enviro n mental and water management standards.

2178POST-HEARING

2179An original Transcript has been filed with the Division of

2189Administrative Hearings. Both sides filed proposed findings in

2197the form of Proposed Recommended Orders which were read

2206considered. Counsel for Petitioners, John S. Clardy, withdrew as

2215counsel, and an order was entered striking certain of

2224Petitioners' pleadings as an improper and untimely effort to

2233adduce additional evidence relating to the credibility of

2241witnesses.

2242FINDINGS OF FACT

2245STIPULATED FINDINGS OF FACT

22491. By Joint Prehearing Stipulation the parties agreed to

2258the following description of the pa r ties and the project:

2269PARTIES:

22702. The Department of Environmental Protection (the

2277Department) is a government agency in the State of Florida

2287existing by virtue of Section 20.255, Florida Statutes, and

2296operating pursuant to Chapters 253, 373, 376, and 403, Florida

2306Statutes, and T i tle 62, Florida Administrative Code. Under an

2317interagency agreement with SWFWMD, the Department also implements

2325Title 40D, Florida Administrative Code. The Department is

2333located in Tallahassee, Florida, and it has a district office in

2344Tampa, Florida, which district includes Levy County.

23513. Southern Hy Power Corporation is a Florida Corporation

2360whose principal offices are located at 7008 Southwest 30th Way in

2371Gainesville, Florida.

23734. Betty Berger is an interested party with a mailing

2383a d dress of Post Office Box 83, Inglis, Florida.

23935. The Campbells are an interested party with a mailing

2403a d dress of 245 Palm Street, Inglis, Florida.

24126. Hy Power applied on A ugust 31, 1993, to the Department

2424for a WRM permit/water quality certification to construct a

2433h y droelectric facility on the Inglis By-Pass Channel. The

2443pro j ect is located in Section 12, Township 17 South, Range 16

2456East, within the town of Inglis in Levy County. The facility

2467consists of a powerhouse located on the south side of the channel

2479measu r ing about 28 feet wide by 115 feet long, drawing water from

2493the Inglis By-Pass Channel, passing it through a single-pit type

2503tu r bine and discharging downstream of the Inglis By-Pass Spillway

2514Dam.

25157. Hy Power applied on August 4, 1998, to the Department

2526for a MSSW permit for the same proposed hydroelectric facility on

2537the Inglis By-Pass Channel.

2541DESCRIPTION OF PROPOSED PROJECT

25458. The project involves the construction of an intake

2554structure, powerhouse, and tailrace on a 0.61-acre area located

2563on the south side of the existing Inglis By-Pass Spillway. The

2574facility will take advantage of the existing hydrostatic head

2583that exists on either side of the Spillway Dam, to generate

2594ele c tricity.

25979. The powerhouse will be constructed below grade and will

2607contain a single megawatt turbine and generating unit. The

2616i n take structure will divert flows from the upstream side of the

2629Spillway Dam through the powerhouse and back into the By-Pass

2639Channel. A small one-story control building and low profile

2648su b station will be constructed above grade within the boundaries

2659of the project area.

266310. The hydroelectric project is considered to be a "Run of

2674the River" type of facility because it can only use that water

2686which flows down the existing channel. The geometry of the

2696cha n nel restricts flow to a certain amount, therefore the project

2708cannot create or use flows above those that the By-Pass Channel

2719can provide. The overall authority for control of water levels

2729in Lake Rousseau and flow to the lower Withlacoochee River will

2740remain with the DEP.

274411. Lake Rousseau was created in 1909 when the Inglis Dam

2755was constructed across the Withlachoochee River for the purposes

2764of hydroelectric generation. The dam impounds over 11 miles of

2774the Withlachoochee River and forms a lake approximately 3,000 to

27854,000 acres in size. Prior to construction of the Barge Canal,

2797water released from the Inglis Dam would flow down the lower

2808po r tion of the Withlachoochee River about 10 miles before

2819entering into the Gulf of Mexico.

282512. In the mid to late 1960's the Army Corps of Engineers

2837(ACOE) built a portion of the Cross Florida Barge Canal between

2848the Gulf of Mexico and Lake Rousseau. The canal severed the

2859Withlachoochee River dow n stream of the Inglis Dam causing its

2870flow to be diverted into the Barge Canal and then into the Gulf.

2883In order to maintain the flow of freshwater from Lake Rousseau to

2895the lower segment of the River, the 8,900-foot long Inglis By-

2907Pass Channel and Spil l way were constructed. The resulting

2917downstream flow ensures navigation in the lower portion of the

2927River and sustains its freshwater and estuarine environment.

293513. The water level in Lake Rousseau is generally

2944mai n tained at an elevation of 27.5 feet above mean sea level

2957(msl) by a combination of the Inglis Dam, the Inglis Lock, which

2969is located in the Barge Canal, and the By-Pass Channel Spillway.

2980These water control features are known collectively as the Inglis

2990Project Works. The water levels in the lower Withlachoochee

2999River immediately to the west of the By-Pass spillway are close

3010to sea level. The resulting head provides the potential energy

3020needed to drive the proposed generator turbine. Under normal

3029conditions the majority of water released from Lake Rousseau

3038flows over the Spillway Dam into the lower segment of the River.

3050According to the DEP Office of Greenways and Trails (OGT), the

3061maximum capacity of the existing By-Pass Channel Spillway is

30701,540 cubic feet per second. The hydroelectric project will

3080divert whatever flow is allowed around the existing spillway

3089through the turbine and back into the channel.

309714. When the Cross Florida Barge Canal project was

3106cancelled in the 1990's, the ACOE transferred owne r ship of the

3118property to the State of Florida Board of Trustees, who in turn

3130has leased the property to the DEP for use as the Cross Florida

3143Greenbelt State Recreation and Conservation Area. Management of

3151this property, the control of river flow and lake levels, and

3162operation of the Inglis Project Works are exercised by the DEP's

3173OGT. The OGT utilizes a document entitled "Water Control Plan

3183for Inglis Project Works," dated September 1994, as a guide to

3194operating the structures. The Water Control Plan is incorporated

3203as part of the MSSW intent to issue.

321115. On or about April 25, 1995, the Governor and Cabinet,

3222sitting as the Board of Trustees of the Internal Improvement

3232Trust Fund ("Trustees"), approved a request from Hy Power to

3244su b lease 0.61 acres of Greenway property at the project site for

3257the purpose of providing electric power. The request was

3266challenged by Berger and the Campbells, and resulted in an

3276administrative hearing held on November 3, 1995.

328316. As a result of the hearing, Administrative Law Judge

3293Larry Sartin entered a Recommended Order on July 12, 1996, that

3304the Board enter an order approving execution by the DEP of the

3316proposed sublease and dismissing the petition of Berger and the

3326Campbells. The Recommended Order was approved by the Trustees in

3336its entirety in a Final Order dated April 12, 1996 ("Final

3348O r der"). Berger v. Southern Hy Power Corporation et al. , Case

3361No. 95-3589.

336317. A copy of the Final Order is listed as an exhibit to

3376this Stipulation, and the Findings of Fact and Conclusions of Law

3387co n tained therein are adopted herein. As previously ruled by the

3399undersigned, the previous Final Order is res judicata as to

3409Petitioners in this case, who are collaterally estopped from

3418challenging any of the findings of fact or conclusions of law

3429contained in the previous Final O r der. Petitioners reserve the

3440right to litigate issues of fact and law not addressed in the

3452Findings of Fact or Conclusions of Law contained in that Final

3463Order with regard to the permittabi l ity of this project under the

3476WRM and MSSW permitting proposals, and to raise objections as to

3487relevance to this proceedings of any of the Findings of Fact or

3499Conclusions of Law in the Final Order.

350618. On February 21, 1995, Hy Power filed application with

3516the Federal Energy Regulatory Commission (FERC) for a conduit

3525exemption from the licensing requirements of Part I of the

3535Fe d eral Powers Act (FPA) for the proposed project. Petitioners

3546and various other persons filed protests with FERC in opposition

3556to the project.

355919. On April 21, 1997, FERC issued an Order Granting

3569Co n duit Exemption, a copy of which is listed as an exhibit to

3583this Stipulation. Petitioners in this case are collaterally

3591estopped from challenging any of the findings or conclusions

3600contained in that Order Granting Conduit Exemption. Petitioners

3608reserve the right to litigate issues of fact and law not

3619addressed in the Findings of Fact or Conclusions of Law contained

3630in that Order Granting Conduit Exemption with regard to the

3640permittability of this project under the WRM and MSSW permitting

3650proposals, and to raise objections as to relevance to this

3660proceedings of any of the findings or co n clusions in the Order

3673Granting Conduit Exemption.

3676FACTS ADDUCED AT HEARING

3680OUTLINE OF PROJECT

368320. The proposed project calls for the construction of a

3693water retention structure along the existing By-Pass spillway,

3701the excavation of a large hole in which the powerhouse and

3712turbine would be constructed "in-the-dry" south of the existing

3721dam, and a millrace below the proposed project to return the

3732water back into the existing water course.

373921. Conflicting testimony was received regarding the facts

3747surrounding the construction of the project. These included:

3755whether the proposed project will touch the existing wing walls

3765of the existing dam; whether the water retention structure is a

3776coffer dam; whether the proposed water retention structure will

3785safely retain the water; whether the powerhouse and turbine have

3795sufficient negative buoyancy to stay in the ground; whether the

3805proposed excavation will weaken the existing dam; and whether the

3815de-watering of the excavation site will adversely impact ground

3824and surface water.

3827PROJECT DESIGN AND ENGINEERING

383122. Engineering for the project was directed by witness

3840Richard A. Volkin, a professional engineer and president and CEO

3850of Engineering Company, Inc., based in Canton, Massachusetts.

3858Mr. Volkin has extensive national and international e x perience in

3869the design, management, and operation of hydroelectric

3876facilities.

387723. Other engineers in Mr. Volkin’s firm worked on the

3887pr o ject under Mr. Volkin’s direct supervision, including John

3897May, who became registered as a professional engineer in Florida

3907in order to sign and seal the engineering drawings for the

3918project, which he initially did around 1994. Mr. May became ill

3929and r e tired in 1998.

393524. Because of the length of time the application process

3945has taken and the fact that Mr. May retired, there was a time

3958while the application was pending, when Hy Power's design team

3968was without a registered Florida engineer. When this was brought

3978to the attention of Hy Power, Hy Power substituted Steven

3988Crockett for Mr. May as the Florida-registered professional

3996engineer of record for the project. DEP routinely accepts an

4006applicant’s changing its e n gineer of record during the course of

4018permit application or co n struction.

402425. Mr. Crockett is a civil and structural engineer who has

4035considerable experience in preparing dam structural designs.

4042Mr. Crockett independently reviewed and evaluated the engineering

4050drawings for the project. Mr. Crockett resealed the dra w ings by

4062using his drawn seal and signing the plans because his embossed

4073seal was not readily available and time was of the essence.

4084Mr. Crockett has advised DEP that he is now engine er of record

4097for the project, using the appropriate DEP forms.

410526. Mr. Volkin’s firm performed all of the studies required

4115by the various agencies, including a geotechnical study of the

4125area, a 50-year analysis of water flow in and out of the Lake

4138Rousseau regime, and water quality evaluations of water in the

4148By-Pass Channel.

415027. The ACOE performed deep hole borings of the soils

4160(a p proximately 36-40 feet below sea level) in the area of the

4173pro j ect site to determine soil stabilization conditions at the

4184site when they were constructing the Inglis Project Works. The

4194soil conditions found can reasonably be expected to be similar

4204today.

420528. Mr. Volkin’s company also took its own eight-foot deep

4215surface core samples. The purpose of those samples was to verify

4226the ACOE data. The new core samples verified the original core

4237samples.

423829. Mr. Volkin also reviewed the ACOE’s engineering

4246dra w ings developed from construction of the Spillway Dam. These

4257show that the dam is founded on limestone bedding that has been

4269stabilized with concrete. The hydroelectric facility will be

4277constructed adjacent to and south of the dam structure and

4287adjacent to and north of the barge canal. The same type of

4299limestone bedrock is found in the area of the proposed

4309construction.

431030. The facility design includes an intake channel on the

4320upstream channel and a tailrace downstream. Those are the only

4330structures that will be constructed next to the By-Pass Channel.

434031. The construction of the facility itself will be "in the

4351dry." Hy Power will use coffer dams to seal off the construction

4363site from the By-Pass Channel, so that there will not be water

4375leakage from the Channel into the construction site. Water from

4385the By-Pass Channel will enter the power plant when the coffer

4396dams are lifted and the water is a l lowed to flow into the

4410facility.

441132. The Petitioners presented the testimony of Bill

4419Edwards, an individual with considerable experience in the

4427construction of bridges, cofferdams, and similar concrete

4434structures in aquatic and semi-aquatic conditions. Mr. Edwards

4442is a former hard-hat diver who worked all over the world and

4454worked in Florida for many years prior to his retirement. Based

4465upon his experience and expertise in construction related to

4474projects of this type, his testimony is credible and worthy of

4485consideration.

448633. Mr. Edwards pointed out that if the proposed water

4496retention structure did not touch the wing wall of the existing

4507dam, it could not keep the water out and would not have the

4520strength that it needed to retain the water.

452834. Hy Power’s witnesses explained that the retention

4536structure would be set close enough to the existing wing wall

4547that waterproofing materials could be placed between the two

4556structures to keep the water out. Further, that the existing

4566plans did not show interior bracing which would be included for

4577structural strength and integrity. In sum, the retention

4585structure will be in contact with existing dam’s wing wall, but

4596will be free standing and not dependent upon the strength of the

4608wing wall for its strength.

461335. Mr. Edwards pointed out that a cofferdam by definition

4623has walls on all sides of the structure. The structure proposed

4634by Hy Power did not have walls all the way around the proposed

4647excavation. In rebuttal, Hy Power presented evidence that its

4656plans were conceptual, design drawing and not construction plans.

4665Hy Power represented that in actuality it would put as many walls

4677as were necessary to keep the water out of the hole it intended

4690to excavate.

4692a sh racks will be constructed at the intake

4701stru c tures to protect aquatic life and make sure that trash and

4714veg e tation do not enter the intake structure or go down river.

4727The trash rack bars will be two inches on center, which the U.S.

4740Fish and Wildlife Service has determined as the appropriate size

4750for the protection of fish.

475537. The turbine blades are "double regulated," and ope r ate

4766generally between 60 and 90 revolutions per minute. The d e sign

4778enables the turbine to operate at a constant speed to gene r ate a

4792consistent flow of electricity, notwithstanding the fact that the

4801flow of the water may vary. The blade speed is not very fast,

4814and the 2.5-meter blades pr o vide a two to three-foot opening.

4826This design acts to prevent fish mortality.

483338. Ther e are four ways to shut off the flow of water

4846through the proposed structure: close the pitch of the blades,

4856close the wicket gates, allow the counter balance to the wicket

4867gates to kick in and automatically close the gates, and close off

4879the main gates. This is a fail safe system ("four level

4891r e dundancy") designed to work upon any failure.

490139. Once water goes through the generator, its velocity is

4911reduced to no greater than its intake rate which is a maximum of

4924three feet per second. This prevents the water being di s charged

4936from the tailrace from causing erosion. If the head of water in

4948the dam produces a flow exceeding three feet per second, it can

4960be diverted over the other dams which will be functional.

497040. The power plant will be encased in con crete, except for

4982a small access way that enables a person to go down a set of

4996stairs to the plant. It will be a sealed, waterproof structure,

5007as required by FERC and the ACOE. This will prevent penetration

5018of groundwater, or flood waters in the event a ma s sive flood

5031overtops the plant. The only water entering the powerhouse will

5041be through the turbine tunnel for power ge n eration purposes.

505241. Mr. Edwards pointed out that the powerhouse was a

5062closed structure and as such would have positive buoyancy, that

5072is, it would float. Mr. Edwards pointed out that the proposed

5083site is between the barge canal and By-Pass spillway and there is

5095a great deal of groundwater and potentiometric pressure in the

5105existing water table. In sum, there is a unlimited supply of

5116groundwater at the site, and powerhouse could float out of the

5127ground just like an empty swimming pool. Hy Power presented

5137rebuttal evidence that the weight of the building, the turbine,

5147and the water flowing through the turbine would be close to

5158negative buoyancy, and they would add additional weight to the

5168structure as necessary to keep it in place.

517642. The project is designed to generate three megawatts of

5186electric power which is enough electricity to serve between 300

5196and 3000 homes, depending on usage.

520243. The project is designed to be unmanned. This is common

5213for facilities such as this. The plant can be operated by remote

5225control, unlike the existing controls at the By-Pass Dam, which

5235are operated manually. DEP can access, monitor, and control

5244remotely the generator's operation to include shutting the

5252facility down at any time.

525744. There will be remote sensors to monitor water

5266elev a tions. Flood protection will improve because of the ability

5277of DEP to manage water flow from a remote location. If there is

5290any major disruption, the plant will shut itself down.

529945. The project is classified as "green power." In other

5309words, it generates natural energy without any disruption to the

5319environment.

532046. The project will have minimal to no impact on the

5331env i ronment. There will be no significant changes in water

5342quality compared to existing conditions as a r e sult of either

5354construction or operation of the facility.

5360WRM Permit Criteria

536347. Hy Power has provided reasonable assurances that the

5372proposed project will not cause a violation of state water

5382qua l ity standards of Section 403.918(a), Florida Statutes (1991).

5392The parties stipulated that turbidity and dissolved oxygen were

5401the two surface water quality issues of concern in this

5411procee d ing.

541448. The receiving water body is the Inglis By-Pass Channel.

5424The Inglis By-Pass Channel is a Class III surface water. The

5435project is not l o cated in a OFW. While the lower Withlacoochee

5448River is an OFW, the OFW designation runs up the natural river

5460itself, and does not include the Spillway Dam, tailrace, or the

5471remainder of the By-Pass Channel. There would be no degradation

5481of water quality at the point of contact with the Withlacoochee

5492River OFW.

549449. The DEP and FERC looked specifically at potential for

5504tu r bidity and dissolved oxygen in determining whether the project

5515would violate state water quality standards. The standards for

5524turbidity and dissolved oxygen will not be violated.

553250. Because the By-Pass Dam is an under flow structure, a

5543minimum of oxygenation currently occurs as water flows through

5552the existing dam. The proposed project runs the water

5561underground through the generator; however, Hy Power will measure

5570the dissolved oxygen below the dam in the Lower Withlacoochee

5580River. In the event there is any lowering of dissolved oxygen,

5591Hy Power can install a "sparge ring" to reoxygenate the water

5602going through the turbine so that dissolved oxygen remains at

5612current levels.

561451. No turbidity will be added to the receiving water as a

5626result of the project, because water velocity is low and the

5637structure is encased in concrete and rip-rap.

564452. The only other potential for turbidity would occur when

5654the coffer dams are removed after construction is co m plete. The

5666coffer dams can be removed with the generator closed to permit

5677any turbidity to settle. The amount of siltation that might

5687occur when the generator is opened would be insignificant.

569653. Where a project is not in a OFW, an applicant must

5708pr o vide reasonable assurance that the project will not be

5719contrary to public interest. See Section 403.918(2), Florida

5727Statutes (1991). Hy Power has provided such assurances.

573554. The project will not directly affect public health,

5744safety or welfare, or the property of others. See Section

5754403.918 (2)(a)1., Florida Statutes. There are concerns relating

5762to the structural integrity of the proposed facility and adjacent

5772structures which are discussed extensively below.

577855. The project will have no adverse impact upon the

5788co n servation of fish and wildlife, including threatened and

5798enda n gered species and their habitat. See Section 403.918

5808(2)(a)2., Florida Statutes.

581156. While manatees are not likely to be found at the

5822pro j ect site, the installation of the trash racks will eliminate

5834any potential adverse impact on manatees. In fact, the racks

5844will be an improv e ment over the current unprotected Spillway Dam.

5856DEP procedures require a specific manatee control plan be

5865implemented to deal with site specific concerns.

587257. The project will not adversely affect navigation or the

5882flow of the water or cause harmful erosion or shoaling. See

5893Section 403.918(2)(a)3., Florida Statutes.

589758. The project will not adversely affect fishing or

5906re c reation values or marine productivity in the vicinity of the

5918pr o ject. See Section 403.918(2)(a)4., Florida Statutes.

592659. The perm a nent project and its construction will cause

5937no significant environmental impacts. See Section

5943403.918(2)(a)5., Florida Statutes.

594660. There will be no adverse impacts to significant

5955hi s torical and archeological resources. Section 403.918(2)(a)6.,

5963Florida Statutes.

596561. With regard to the impact on current conditions and

5975relative value of functions being performed by the areas affected

5985by the proposed activity, there will be no negative impacts. See

5996Section 403.918(2)(a)7., Florida Statutes. Improvement will

6002result from better control of water flow at the project site,

6013installation of trash racks and implementation of green power.

6022THE FORESEEABLE ADVERSE SECONDARY OR CUMULATIVE IMPACTS

602962. Potential adverse secondary impacts related to power

6037transmission are addressed through the fact that there is an

6047existing power line corridor that can be used to transmit the

6058electricity. Any need to change the corridor could be addressed

6068by subsequent DEP permi t ting. Cumulative impacts are not at

6079issue.

608063. Mr. Gammon, with Florida Power, acknowledged that the

6089current electric company, presumably Florida Power, would be

6097r e quired by FERC to transport the electricity generated by Hy

6109Power over its existing corridor and poles.

611664. No final decision has been made regarding how to acces s

6128the site with equipment during construction. Several feasible

6136construction options exist, and there are se v eral ways of

6147accessing the site with heavy equipment vehicles and without

6156impacting wetlands. Any final dec i sion would be subject to DEP

6168approval.

616965. Since the project meets the public interest criteria of

6179Section 403.918(2)(a), Florida Statutes, and wetland impacts are

6187minimal, the project is permittable without the need for

6196mitigation. See Section 403.918(2)(b), Florida Statutes.

620266. The ACOE has issued a permit for the facility. The

6213permit varies slightly from the DEP intent to issue in the use of

6226reinforced concrete rather than rip-rap on the bottom half of the

6237intake channel. This is to comply with ACOE prefe r ence, but the

6250variation has only an environmental benefit.

625667. Counsel for Petitioners sought to elicit testimony from

6265Linda Sloan, Executive Director of the Withlacoochee Regional

6273Planning Council, with regard to compliance of the proposed

6282pro j ect with the Town of Inglis Comprehensive Plan and Land

6294Develo p ment Code. Such compliance is not relevant to this

6305proceeding. At any rate, Ms. Sloan conceded that any prohibition

6315that might apply in the Land Development Code to construction of

6326the pr o posed facility could potentially be alleviated by

6336exemption or variance provisions in the Code.

6343MSSW PERMIT CRITERIA

634668. The project will provide adequate flood protection and

6355drainage in the conventional sense. See Rule 40D-4.301(1)(a),

6363Florida Administrative Code. Because the amount of impervious

6371area is minimal, runoff from the project will not in any way

6383contribute to increased flooding or adversely impact drainage

6391pa t terns.

639469. The total amount of impervious area of the facility is

6405less than that of a single-family residence. SWFWMD rules do not

6416even require MSSW permits for single-family res i dences because

6426the impact is not significant. The only purpose for requiring a

6437MSSW permit for the project is to review the project’s potential

6448downstream impacts to the watershed, not stormwater runoff from

6457the facility itself.

646070. The project will not cause adverse water quality or

6470w a ter quantity impacts on adjacent lands in violation of Chapter

6482373, Florida Statutes, or cause a discharge that violates state

6492water quality standards. See Rule 40 D-4.301(1)(b), Florida

6500Administrative Code.

650271. As indicated by the WRM water quality findings above,

6512the project will not generally violate state surface water

6521quality sta n dards. See Rule 40 D-4.301(1)( c), Florida

6531Administrative Code.

653372. The project will not generally cause adverse impact on

6543surface or groundwater levels or flows. See Rule 40 D-

65534.301(1)(d), Florida Administrative Code.

655773. Since the project is a run-of-the-river, it will not

6567diminish the capability of a lake or other impoundment to

6577fluct u ate through the full range established for it under Chapter

658940D-8, Florida Administrative Code.

659374. The project will not cause adverse environmental

6601i m pacts, or adverse impacts to wetlands, fish, and wildlife or

6613other natural resources.

661675. The project can be effectively operated and maintained.

6625See Rule 40D-4.301(1)(g), Florida Administrative Code. The

6632project is a slow speed, low maintenance facility. The design

6642concept is well established and has been successfully used for

6652many years.

665476. Possible adverse affects to public safety are discussed

6663below.

666477. The project is consis tent with the requirements of

6674other public agencies. See Rule 40D-4.301(1)(i), Florida

6681Administrative Code.

668378. Potential harm to water r e sources within the SWFWMD are

6695discussed below. See Rule 40D-4.301(1)(j), Florida

6701Administrative Code.

670379. Th e proposed project generally will not interfere with

6713the legal rights of others. See Rule 40D-4.301(1)(k), Florida

6722Administrative Code.

672480. The proposed project is not against public policy. See

6734Rule 40D-4.301(1)(l), Florida Administrative Code.

673981. The project complies with the requirements contained in

6748the Basis of Review. See Rule 40D-4.301(2), Florida

6756Administrative Code.

675882. There is a dispute as to whether the project was within

6770or at the edge of the 100-year flood plain. This dispute is

6782related to how one interprets the rule as it relates to the

6794millrace and the location of the facility which is under ground.

6805In the conventional sense, the project is not in the flood plain.

6817Further, the project is designed in such a way, that it is

6829waterproof if it were topped with water.

683683. While in the past SWFWMD may have had concerns that the

6848project might cause downstream flooding, SWFWMD currently has no

6857such concerns, given the run-of-the-river status of the proposed

6866project. The operation of the project will not cause downstream

6876flooding.

687784. The DEP included in its intent to issue, conditions

6887co n tained in the sublease between Hy Power and the DEP in order

6901to ensure that the facility would remain run-of-the-river, would

6910comply with the water control plan, and would otherwise comply

6920with the terms of the sublease. The DEP has final control over

6932water flow and can revoke the permit or othe r wise take

6944enforcement action against Hy Power if Hy Power fails to comply

6955with the water control plan.

6960GROUNDWATER IMPACTS

696285. Operation of the project will not cause groundwater

6971contamination or otherwise have adverse groun d water impacts.

6980Some concerns about groundwater during excavation of the

6988construction site were raised. The conflicting evidence received

6996regarding them is discussed below.

700186. An area of concern was the de-watering plan for the

7012project. Everyone agrees there will be some water seepage into

7022the construction site that will have to be pumped out. The

7033parties disagree regarding the amount of water that will have to

7044be removed. Their estimates of amount of water to be removed

7055vary because their estimates of size and over-all depth of the

7066site vary.

706887. Petitioners presented credible evidence that a

7075potential exists for the construction site to have a large

7085quantity of water because of its location between two sources of

7096surface water (the By-Pass Channel and Barge Canal), because of

7106the makeup of the subsurface, and because of the depth of the

7118construction.

711988. Hy Power credibly represents that if excessive

7127groundwater is found, it can address the adverse impacts through

7137its de-watering plan that would have to be filed with FERC and

7149DEP. The technology exists to address the de-watering of the

7159project. Such plans are routinely considered by DEP after a

7169construction permit is issued and before de-watering occurs.

717789. There is very little evidence of sinkhole activity in

7187the project area, and the construction activities are not

7196e x pected to cause any sinkhole activity.

7204NOISE POLLUTION

720690. Mr. Bitter expressed concerns that FERC would require

7215the facility to install a very loud siren that would result in

7227sudden noise adverse to the well-being of neighbors. Mr. Bitter

7237is unfamiliar with FERC siren requirements at run-of the-river

7246hydroelectric facilities.

724891. In contrast, Mr. Volkin, who has substantial exper i ence

7259in this area, testified that the only alarm device that would be

7271required would be for the protection of the workers du r ing

7283construction.

728492. The purpose of the alarm is to warn persons below a dam

7297spillway of a change in the volume of water being let out of the

7311impoundment. In the case of a run-of-the-river facility, the

7320volume is near constant, changing only gradually.

732793. Therefore, even if a warning siren had to be installed

7338its use would be limited to significant changes in flow or

7349testing. This would not constitute a nuisance.

735694. Further, the facility is located in the vicinity of the

7367Crystal River Nuclear Power Plant which has its own warning

7377sirens. It would be prudent to make any warning devices required

7388for this structure significantly different from those at the

7397nuclear plant and to limit their use.

7404DAM SAFETY AND FERC REVIEW

740995. In reviewing whether Hy Power’s applications complied

7417with the relevant permitting criteria, the DEP took into

7426consi d eration the review of the facility already performed by

7437FERC. FERC will also be responsible for reviewing the project as

7448it is being co n structed.

745496. Mr. Edwards also raised concerns about the structural

7463stability of the By-Pass Dam itself. This has been a subject of

7475concern by those responsible for the dam, and a survey of the

7487structure was conducted in 1993, referred to as the Greiner

7497Report.

749897. The Greiner Report identified specific maintenance

7505problems that have been and are being addressed by the DEP.

7516However, DEP’s maintenance plan does not address specifically the

7525possibility that the weight of the dam over time has caused some

7537shifting in the dam.

754198. Hy Power has only a few core borings and only one at

7554the location of the generator. Hy Power is using the ACOE’s

7565original borings, as confirmed by several new ones, to develop

7575its preliminary plans.

757899. The DEP considered FERC and the ACOE as responsible

7588agencies for determining the structural integrity of the dam.

7597DEP has taken FERC’s review of this facility into consi d eration

7609as part of DEP’s own permitting review. It is normal for DEP to

7622rely on outside sources and agencies for assistance in

7631determining compliance with DEP pe r mitting criteria such as

7641public health and safety, and it is reasonable for DEP to do so

7654in this instance. Most states do not have the full capability to

7666evaluate dam safety, and so they rely on FERC and ACOE.

7677100. On April 21, 1997, the pro ject received a conduit

7688e x emption from FERC. The application process is illu s trated in

7701Hy Power Exhibit 11.

7705101. Hy Power su b mitted to DEP detailed information about

7716the dam, the associated stru c tures and the proposed project which

7728had been reviewed by FERC and the ACOE, the two agencies in the

7741United States who are responsible for dam stru c ture design,

7752control, and administration. Included in the package was the

7761Greiner Report and Hy Power’s review of it.

7769102. FERC evaluated the project, the In glis By-Pass Dam

7779structure, and the proximity of the project to the Dam in

7790relation to structural impact, upstream and downstream impacts,

7798water quality, and environmental issues.

7803103. Mr. Edwards raised concerns regarding the ability of

7812the limestone bedrock to sustain additional construction in the

7821area of proposed construction. This is a material issue in the

7832controversy which impacts several aspects of the proposed

7840construction.

7841104. Mr. Edwards pointed out that the barge canal channel

7851was constructed with the use of explosives that caused a

7861fracturing of limestone bedrock. He pointed out that the steel

7871panels, which Hy Power proposes to drive into the bedrock to

7882construct the water retention structure necessary to excavate the

7891hole into which the turbine and powerhouse would be placed, will

7902further fracture this bedrock. This creates two potential

7910dangers. It could permit water to move under and around the

7921bottoms of the panels, potentially scouring the loosened material

7930from the base of the panels and making them unstable and subject

7942to failure. It could weaken the entire southern wing of the

7953existing spillway dam. Mr. Edwards opined that this could result

7963in catastrophic failure of the dam or the coffer dam.

7973105. Such a failure would cause major destruction and loss

7983of life to those persons living and working in and along the

7995lower Withlacoochee River.

7998106. Hy Power presented rebuttal evidence that it could and

8008would, if necessary, inject concrete into the limestone to

8017stabilize it and avoid the concerns raised by Mr. Edwards.

8027107. FERC specifically evaluated concerns raised by project

8035opponents over the poor physical condition of the By-Pass Channel

8045Spillway structures, relying particularly on the 1993 Greiner

8053Report. FERC noted that the DEP had entered into a contract to

8065correct any deficiencies listed in the Greiner Report, which "did

8075not conclude that the deficiencies at the By-Pass Spillway

8084threaten downstream life and property."

8089108. The FERC review concluded that the dam was safe. To

8100ensure safety, FERC is requi r ing that Hy Power do a complete

8113stability analysis of the dam prior to any construction.

8122Articles 301 and 302 of the FERC exemption ensure that all final

8134drawings and specifications be submitted to FERC prior to

8143construction, along with a suppor t ing design report consistent

8153with FERC’s Engineering Guidelines; that FERC can require changes

8162to assure a safe and adequate pro j ect; and that Hy Power must

8176also submit approved coffer dam co n struction drawings and

8186specifications at least 30 days prior to starting co n struction.

8197109. FERC has its own engineering staff who will go to the

8209site and do their own analysis, along with the ACOE, of the dam

8222and structures, prior to any construction commencing. This is a

8232detailed design review evaluation so that the latest information

8241on the dam will be made known immediately prior to co n struction,

8254and will prevent any catastrophic event from happe n ing. Under

8265FERC procedures, FERC requires the applicant to obtain the DEP

8275permits prior to requiring applicant to submit more detailed

8284constru c tion designs for FERC's consideration. These more

8293detailed designs in turn will be su b ject to further review by DEP

8307and FERC.

8309110. It is assumed that Hy Power will comply with the post-

8321permitting procedures and requirements, and will present

8328complete, detailed construction drawings for FREC and DEP

8336approval. Hy Power’s failure to complete the process would

8345result in denial of a construction permit.

8352CONCLUSIONS OF LAW

8355111. The Division of Administrative Hearings has

8362jurisdi c tion over the parties to and the subject matter of this

8375procee d ing pursuant to Section 120.57(1), Florida Statutes.

8384The applicant has the burden of providing reasonable assurance

8393that the proposed project will not violate DEP Rules. Rule 62-

84044.070(1), Florida Administrative Code; Florida Department of

8411Transportation v. J.W.C. Company , 396 So. 2d 778 (Fla. 1st DCA

84221981).

8423112. The applicant's burden is "one of reasonable

8431assu r ances, not absolute guarantees." Manasota-88, Inc., v.

8440Agrico Chemical , 12 FALR 1319, 1325 (DER 1990). In assessing the

8451risk to resources, DEP is not required to assume a "worst case

8463scenario" unless such a scenario is "reasonably foreseeable."

8471Rudloe v. Gulf Specimen Co., Inc. v. Dickerson Bayshore, Inc. and

8482DER , 10 FALR 3426 (DER 1988). Reasonable assurances must deal

8492with reasonably foreseeable contingencies. The necessary

8498reaso n able assurance in a particular case that a proposed project

8510will comply with applicable air or water quality standards is a

8521mixed question of fact and law that must be made, in the final

8534anal y sis, by DEP. See, e.g., Sierra Club, et al. v. Department

8547of Env. Protection, et al ., 18 F.A.L.R. 2257, 2260 (Fla. DEP

85591996); Save Our Suwannee, Inc. vs. Piechocki and Dept. of Env.

8570Protection , 18 F.A.L.R. 1467, 1471 (Fla. DEP 1996); VQH

8579Development, Inc. v. Dept. of Environmental Protection, et al .,

858915 F.A.L.R. 3407, 3438 (Fla. DEP 1993); Barringer, et al v. E.

8601Speer and Associates, Inc., and Department of Environmental

8609Regulation , 14 F.A.L.R. 3660, 3667 n. 8 (Fla. DER 1992).

8619113. Simply raising "concerns" or speculation about what

"8627might occur" is not enough to carry a petitioner's burden. See

8638Chipola Basin Protective Group, Inc. v. Florida Department of

8647E n vironmental Protection , 11 F.A.L.R. 467, 480-81 (DER 1988).

8657Once the applicant has presented its evidence and made a

8667preliminary showing of reasonable assurances, the challenger must

8675present "contrary evidence of equivalent quality" to that

8683presented by the permit applicant. J.W.C. supra , 396 So. 2d at

8694789.

8695114. Thus, a permit applicant is not required by Florida

8705law to provide an "absolute guarantee" that a proposed project

8715will comply with all applicable air or water quality standards.

8725Piechocki , supra , 18 F.A.L.R. at 1472 (Fla. DEP 1996); Powell v.

8736U.S. Navy and Dept. of Env. Protection , 15 F.A.L.R. 3386, 3394

8747(Fla. DEP 1993).

8750115. No third party, merely by filing petition seeking

8759a d ministrative hearing, should be permitted to require an

8769applicant to completely prove anew all items in application "down

8779to [the] last detail." J.W.C. , supra , 396 So. 2d at 789. "The

8791Petitioner must identify the areas of controversy and allege a

8801factual basis for contention that the facts relied upon by the

8812applicant fall short of carrying the 'reasonable assurances'

8820burden cast upon the applicant." Id.

8826116. Under the system of regulation applicable to projects

8835of this type, the applicant obtains several permits from more

8845than one regulatory entity and from the same regulatory entity as

8856the project progresses. At the level this controversy is joined,

8866the applicant has not been able to address specifically each

8876concern raised by Petitioners; however, the applicant has

8884indicated that it must, in order to obtain added permits from

8895FERC and from DEP, present plans which do specifically address

8905these concerns. At this level of review, this constitutes

8914reasonable assurance under the regulatory scheme.

8920117. Rule 40D-4.301, Florida Administrative Code, requires

8927that in order to o b tain a permit "an applicant [for a MSSW

8941permit] must give re a sonable assurances" that the specific

8951permitting criteria will be met. As discussed in the Findings of

8962Fact section of this Recommended Order, Hy Power has provided

8972reasonable assurance that the proposed project will comply with

8981the MSSW permit r e quirements contained in Rule Chapter 40D-4,

8992Florida Administrative Code (in effect prior to October 3, 1995),

9002along with the Basis of Review inco r porated therein.

9012118. Under the permit criteria contained in Section

9020403.918, Florida Statutes (1991), and rules promulgated

9027thereunder, an applicant must first demonstrate that DEP water

9036quality standards will not be violated. Section 403.918(1),

9044Florida Statutes (1991). Hy Power has met that burden in this

9055proceeding.

9056119. Rule 62-4.242, Florida Administrative Code, applies

9063OFW standards to any proposed activity or discharge that is

9073within an OFW or signif i cantly degrades an OFW. Since discharge

9085from the project takes place outside of the Lower Withlacoochee

9095River OFW and will not significantly degrade the OFW, the OFW

9106permitting criteria do not apply, and DEP must determine whether

9116the project is not contrary to the public interest, based upon a

9128consideration and balancing of the seven fact tests set forth in

9139Section 403.918 (2)(a), Florida Statutes (1991).

9145120. Hy Power has provided reasonable assurance that the

9154proposed project is not co n trary to the public interest under

9166Section 403.918(2)(a), Florida Statutes (1991). This is

9173demonstrated both by the factual findings that there will be no

9184adverse impacts associated with the seven public interest

9192criteria, as well as the legislative findings in Section

9201253.7829(2), Florida Statutes, that development of hydroelectric

9208power is a compatible use of the project area.

9217121. The permitting agency cannot consider non-

9224environmental factors to reject a project under the "public

9233health, safety, or welfare or property of others" prong of the

9244public interest test. See Miller v. Department of Environmental

9253Regulation , 504 So. 2d 1325 (Fla. 1st DCA 1987); Taylor v. Cedar

9265Key Sewage Di s trict , 590 So. 2d 481 (Fla. 1st DCA 1991); Grove

9279Island, Ltd. v. Department of Environmental Regulation , 454 So.

92882d 571 (Fla. 1st DCA 1984); Counsel of the Lower Keys v. Charlie

9301Toppino and Sons, Inc. , 429 So. 2d 67 (Fla. 3rd DCA 1983). The

9314public interest test is limited in scope only to environmental

9324impacts associated with the seven factors set forth in Section

9334403.918(2)(a), Florida Statutes (1991), and that list of seven

9343factors is exclusive and exhaustive. Vo n Wagoner v. Department of

9354Transportation , 18 FALR 2277, 2285 (DEP 1996), aff’d sub nom ,

9364Save Anna Maria, Inc., v. Department of Transportation , 700

9373So. 2d 113, 116 (Fla. 1st DCA 1997).

9381122. In particular, DEP cannot consider whether a project

9390complies or does not comply with a local government’s

9399comprehe n sive plan. Taylor , supra .; Charlie Toppino , supra .

9410Cf ., Florida Bay Initiative, Inc., et al. v. Fla. Dept. of

9422Transportation, et al ., 19 FALR 3712, 3719 (SFWMD 1997). The

9433issue of the proposed project’s compliance with the Inglis

9442comprehensive plan and land development regulations is therefore

9450irrelevant to this procee d ing.

9456123. Petitioners have argued that the engineering diagrams

9464prepared on behalf of Hy Power should be stricken for two

9475reasons: first, they were not properly dated as required by

9485Section 471.025, Florida Statutes; and secondly, Mr. John May,

9494the original project engineer, no longer has a Florida P.E.

9504license.

9505124. DEP rules do not require that engineering drawings be

9515dated, only that they be signed and sealed. See Rule 62-

95264.050(3), Florida Administrative Code. The original drawings

9533were validly signed and sealed by Mr. May. The subsequent

9543drawings were signed and sealed by Mr. May, but he was no longer

9556registered in Florida. Furthermore, failure of an engineer to

9565date his drawings does not render them inadmissible. As stated

9575in Cape Development v. City of Cocoa Beach , 192 So. 2d 766, 769

9588(Fla. 1966), the law sets forth the procedure a professional

9598engineer may take to authenticate his drawings; it does not

9608purport to prescribe any requirements to make a drawing

9617admissible in ev i dence. Since the parties have stipulated that

9628authentication is not necessary for admissibility of documents

9636authentication is not at issue.

9641125. To the extent there was any technical d e ficiency in

9653the engineering drawings, they were cured by their being resealed

9663by Mr. Crockett, who also resealed the MSSW appl i cation so that

9676he would be designated as engineer of record. The Board of

9687Professional Engineers authorizes a successor profe s sional

9695engineer to adopt as his own the work of another engineer. See

9707Rule 61G15-27.001, Florida Administrative Code. In addition, DEP

9715rules authorize pe r mit modifications, see Rule 62-4.080(2),

9724Florida Administrative Code, and it is common for DEP to allow

9735engineering changes during the course of a pe r mit processing. To

9747require otherwise would be irrational and u n reasonable.

9756126. Petitioners have argued that the engineering drawings

9764do not have sufficient specificity to warrant a finding of

9774re a sonable assurance. Engineering drawings alone, however, are

9783not the only criteria for determining reasonable assurance.

9791Compare , for example, Hamilton County Commissioners v. TSI

9799Southeast , 12 FALR 3774, 3800 (DER 1990), aff’d sub nom , Hamilton

9810Co. v. State Dept. of Env. Reg. , 587 So. 2d 1378 (1st DCA 1991),

9824in which the Depar t ment concluded:

9831Although reasonable assurances can be shown

9837in part by having specific engineering

9843dra w ings and other design details in evidence

9852in support of an application, their absence

9859is not fatal to a showing of reasonable

9867assu r ances. Here, testimony by the

9874manufacturer, himself, who had extensive

9879experience with the installation, operation

9884and manufacture of such facilities as that

9891proposed . . . is, in the absence of evidence

9901to refute it, an adequate showing of

9908reasonable assurance that all emission

9913standards and the ambient air policy of DER .

9922. . will be met. Reasonable assurances can

9930be demonstrated by designs and plans stamped

9937appropriately by professional engineers

9941licensed in Florida, in part, and can also be

9950shown by competent expert test i mony, as was

9959done here.

9961Accord , Haile Community Association v. Fla. Rock Industries , 96

9970ER FALR 133 (DEP 1996).

9975127. Any additional information necessary to provide

9982reaso n able assurance that the proposed facility would comply with

9993the applicable permit standards can properly be provided at the

10003hea r ing. See McDonald v. Department of Banking and Finance , 346

10015So. 2d 569, 584 (Fla. 1st DCA 1977) (a petition for a formal

10028120.57 hearing commences a de novo proceeding , and because the

10038procee d ing is intended to formulate final agency action and not

10050to r e view action taken earlier and preliminarily, the hearing

10061officer may consider changes or other circumstances external to

10070the a p plication). See also Hamilton County Commissioners , supra ,

10080587 So. 2d at 1387; JWC , supra , 396 So. 2d at 787-788.

10092128. Petitioners have also objected to the DEP’s reliance

10101on FERC in determining reasonable assurance. It is entirely

10110appr o priate, however, for the DEP to rely on the regulatory

10122decisions of other agencies in making its reasonable assurance

10131determin a tions Save Anna, supra , 700 So. 2d at 117. While the

10144cited district court opinion referred to DEP’s reliance on a

10154permitting decision of SWFWMD, the underlying Final Order makes

10163clear that reliance on the public safety decision of another

10173agency, acting within the scope of its specific jurisdiction and

10183expertise, is also a p propriate:

10189[W]hen the Department weighs and balances

10195safety considerations in determining whether

10200proposed dredging and filling as part of a

10208DOT road project satisfies the [public safety

10215component of the] public interest balancing

10221test of former paragraph 403.918(2)(a) . . .,

10229DOT’s opinion of the safety of the design

10237should be given great weight and acceptance

10244by the Department absent compelling evidence

10250of error or omission. Vonwagoner , supra , 18

10257FALR at 2288-2289. (Emphasis added.)

10262There was no compelling evidence of error or omission in this

10273case that would justify any disregard of FERC’s determination

10282that the proposed project could be safely constructed.

10290129. No party has objected to the general and specific

10300co n ditions associated with the proposed permit. There is

10310sufficient basis in both fact and law to impose the requirements

10321as set forth in the general and specific conditions. Prudence

10331dictates that DEP require as part of the permitting and design

10342process, additional core borings in the area of intended

10351construction. This would be a source of needed information about

10361the stability of the limestone bedrock in that area and surface

10372water.

10373130. Because of the significant issues raised by

10381Petitioners and because of the catastrophic consequences of a dam

10391or coffer dam failure, special attention should be given to

10401review of the additional permits and to each of the concerns

10412raised by the Petitioners.

10416131. The sought permit, along with the incorporated ge n eral

10427conditions and specific conditions, to include those recommended

10435above, should be issued.

10439RECOMMENDATION

10440Based upon the foregoing Findings of Fact and Conclusions of

10450Law set forth herein, it is

10456RECOMMENDED:

10457That the DEP enter a Final Order that i s sues the two permits

10471challenged in this proceedings, WRM Permit No. 38-237096-3.001

10479and MSSW Permit No. 38-0129249-002, subject to the conditions

10488contained in the Intents to Issue in the r e spective WRM and MSSW

10502Permits and as described in the Recommended Order.

10510DONE AND ENTERED this 2nd day of March, 2000, in

10520Tallahassee, Leon County, Florida.

10524STEPHEN F. DEAN

10527Administrative Law Judge

10530Division of Administrative Hearings

10534The DeSoto Building

105371230 Apalachee Parkway

10540T allahassee, Florida 32399-3060

10544(850) 488-9675 SUNCOM 278-9675

10548Fax Filing (850) 921-6847

10552www.doah.state.fl.us

10553Filed with the Clerk of the

10559Division of Administrative Hearings

10563this 2nd day of Marc h, 2000.

10570COPIES FURNISHED:

10572Daniel H. Thompson, Esquire

10576Berger Davis & Singerman

10580215 South Monroe Street, Suite 705

10586Tallahassee, Florida 32301

10589Andrew Zodrow, Esquire

10592Department of Environmental Protection

105963900 Commonwealth Boulevard

10599Mail Station 35

10602Tallahassee, Florida 32399-3000

10605John S. Clardy, III, Esquire

10610Crider Law Firm

10613Plantation Point

10615521 West Fort Island Trail, Suite A

10622Crystal River, Florida 34429

10626Teri Donaldson, General Counsel

10630Department of Environmental Protection

106343900 Commonwealth Boulevard

10637Mail Station 35

10640Tallahassee, Florida 32399-3000

10643Kathy Carter, Agency Clerk

10647Department of Environmental Protection

106513900 Commonwealth Boulevard

10654Mail Station 35

10657Tallahassee, Florida 32399-3000

10660Bernard M. Campbell

10663Bessie H. Campbell

10666245 Palm Street

10669Post Office Box 159

10673Inglis, Florida 34449

10676Sarah E. Berger

10679Post Office Box 83

10683Inglis, Florida 34449

10686NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

10692All parties have the right to submit written exceptions within 15

10703days from the date of this recommended order. Any exceptions to

10714this recommended order should be filed with the agency that will

10725issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 05/17/2000
Proceedings: Notice of Agency Appeal filed. (filed by: Petitioners)
Date: 04/24/2000
Proceedings: Final Order filed.
PDF:
Date: 04/21/2000
Proceedings: Agency Final Order
Date: 03/14/2000
Proceedings: Letter to Judge Smith from R. Spetz Re: Reasons for recinding the Hydro Plant on the Withlacoochee River filed.
Date: 03/13/2000
Proceedings: Letter to Judge Dean from R. Spetz Re: Hydro Plant filed.
PDF:
Date: 03/02/2000
Proceedings: Recommended Order
PDF:
Date: 03/02/2000
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 09/22-24/99 and 11/1-2/99.
Date: 02/25/2000
Proceedings: (F. Ffolkes) Notice of Substitution of Counsel for Department of Environmental Protection filed.
Date: 01/24/2000
Proceedings: (B. & B.Campbell) Motion to Accept Post-Hearing Submittals filed.
Date: 01/21/2000
Proceedings: Order Granting Motion to Strike sent out.
Date: 01/21/2000
Proceedings: (D. Thompson) Motion to Strike and for Sanctions (filed via facsimile).
Date: 01/19/2000
Proceedings: (S. Berger) Motion filed.
Date: 01/10/2000
Proceedings: (D. Thompson) Response to Motion to Strike and Motion to Strike and for Sanctions (filed via facsimile).
Date: 01/05/2000
Proceedings: (Petitioner) Motion to Strike w/exhibits filed.
Date: 01/05/2000
Proceedings: (S. Berger, B. & B. Campbell) Public Comment Appendix w/exhibits filed.
Date: 12/28/1999
Proceedings: (D. Thompson) Motion to Strike Motion Not to Strike (filed via facsimile).
Date: 12/27/1999
Proceedings: (Petitioner) Motion Not to Strike filed.
Date: 12/16/1999
Proceedings: Motion to Strike (filed via facsimile).
Date: 12/10/1999
Proceedings: Letter to S. Berger from W. Schmidt Re: Investigation of the professional conduct of D. Smith (filed via facsimile).
Date: 12/02/1999
Proceedings: (J. Clardy) Notice of Withdrawal of Counsel; Petitioners` Proposed Recommended Order; Disk filed.
Date: 11/30/1999
Proceedings: Disk (Hy Power-DEP Joint PRO) filed.
Date: 11/29/1999
Proceedings: Joint Proposed Recommended Order of Southern Hy Power Corporation and Florida Department of Environmental Protection filed.
Date: 11/29/1999
Proceedings: Notice of Filing Joint Proposed Recommended Order of Southern Hy Power Corporation and Florida Department of Environmental Protection filed.
Date: 11/18/1999
Proceedings: Notice of Filing; (Volumes 6-9 of 9) DOAH Court Reporter Final Hearing Transcript filed.
Date: 11/12/1999
Proceedings: (D. Thompson) Exhibits filed.
Date: 11/01/1999
Proceedings: CASE STATUS: Hearing Held.
Date: 10/29/1999
Proceedings: Motion to Strike (Respondent) filed.
Date: 10/28/1999
Proceedings: Letter to Judge Dean from Vicki Phillips (Re: opposition to any project which has the possibility of degrading the gorundwaters of Citrus County) filed.
Date: 10/27/1999
Proceedings: Petitioner`s Exhibits filed.
Date: 10/08/1999
Proceedings: Order Designating Hearing Location sent out.
Date: 09/22/1999
Proceedings: CASE STATUS: Hearing Partially Held, continued to 11/1/99; 9:30am; Tallahassee)
Date: 09/10/1999
Proceedings: Respondent Department of Environmental Protection`s Response to Petitioners` Second Request for Production of Documents (filed via facsimile).
Date: 08/16/1999
Proceedings: (J. Ckardy) Cettificate of Service on New Witnesses and furter information on the case filed.
Date: 08/16/1999
Proceedings: (Petitioners) Notice and Certificate of Service of Petitioner`s Second Request for Production of Documents filed.
Date: 07/16/1999
Proceedings: (J. Clardy) Unopposed Motion for Continuance filed.
Date: 07/09/1999
Proceedings: Letter to Judge Dean from unsigned Re: Requesting subpoenas filed.
Date: 06/23/1999
Proceedings: (DEP) Notice and Certificate of Service of Answers to Interrogatories; Respondent Department of Environmental Protection`s Response to Petitioner Sarah E. Berger`s First Request for Production of Documents filed.
Date: 06/18/1999
Proceedings: Petitioners` Response to the Insufficiency of Respondent Southern HY Power`s Production of Documents and Motion to Compel Respondent Southern HY Power to Produce Documents filed.
Date: 06/16/1999
Proceedings: Petitioners` Response to the Insufficiency of Respondent Southern HY Power`s Production of Documents and Motion to Compel Respondent Southern HY Power to Produce Documents (filed via facsimile).
Date: 06/08/1999
Proceedings: Petitioner Sara E. Berger`s First Response to Request for Production of Documents filed.
Date: 06/03/1999
Proceedings: Order Granting Continuance and Re-scheduling Hearing sent out. (hearing set for September 22-24, 1999; 10:00 am; Inglis, 9/22/99)
Date: 05/28/1999
Proceedings: (Southern) Unopposed Motion for Continuance (filed via facsimile).
Date: 05/26/1999
Proceedings: (J. Clardy) Notice of Appearance; Petitioners` Response to Motion in Limine and Memorandum (filed via facsimile).
Date: 05/25/1999
Proceedings: (J. Clardy) Notice of Appearance (filed via facsimile).
Date: 05/25/1999
Proceedings: Petitioner Sarah E. berger response to Respondents Southern HY Power Corporation and Florida State of Deparment of Environmental Protection request for manatee information filed.
Date: 05/24/1999
Proceedings: Letter to Judge Dean from S. Berger Re: Responding to Daniel H. Thompson request to compel production of documents by Bernard & Bessie Campbell filed.
Date: 05/24/1999
Proceedings: Petitioner Sarah E. Berger gives notice to Respondents Southern HY Power and State of Florida Department of Protection that the issues in the MSSW Intent to Permit and the Wetland Resource Intent to Permit can be under five categories (untitled) filed.
Date: 05/24/1999
Proceedings: Petitioner Sarah E. Berger`s Responseto Respondent Department of Environmental Protection` Interrogatories; Motion to Only Have a Phone Conference filed.
Date: 05/24/1999
Proceedings: Petitioner Sarah E. Berger`s Response to Respondent Department of Environmental Protection Request for Production of Documents filed.
Date: 05/24/1999
Proceedings: Petitioner Sarah E. Berger`s Response to Respondent Department of Environmental Protection Request for Production of Documents filed.
Date: 05/24/1999
Proceedings: Petitioner Sarah E. Berger Objects to Respondent Southern HY Power Corporation Objections to Her First Set of Interrogatories filed.
Date: 05/24/1999
Proceedings: (B. Campbell) Interrogatories Dated 4/23/99 DEP-Documents to be Produced" filed.
Date: 05/20/1999
Proceedings: (D. Thompson) Motion for Prehearing Conference; Motion in Limine and Memorandum filed.
Date: 05/20/1999
Proceedings: Respondent Southern HY Power Corporation`s Objections to Petitioner Sarah E. (Betty) Berger`s First Set of Interrogatories filed.
Date: 05/17/1999
Proceedings: Letter to Judge Dean from B. Campbell, S. Berger Re: Responding to D. Thompson request to compel rpdocution of documents (filed via facsimile).
Date: 05/17/1999
Proceedings: (S. Berger) Notice and Certificate of Service to Respondents Southern HY Power Corporation and State of Florida Department of Environmental Protection filed.
Date: 05/17/1999
Proceedings: (S. Berger) Notice and Certificate of Request for Produion of Documents to Respondent State of Florida Department of Environmental Protection filed.
Date: 05/17/1999
Proceedings: (S. Berger) Notice and Certificate of of First Request for Production of Documents to Respondent Southern HY Power Corporation filed.
Date: 05/17/1999
Proceedings: Respondent Southern HY Power Corporation`s Amended Motion to Compel Answers to Interrogatories From Petitioners Bernard M.Campbell and Bessie H. Campbell (filed via facsimile).
Date: 05/17/1999
Proceedings: Respondent Southern HY Power`s Amended Motion to Compel Petitioners Bernard M. Campbell and Bessie H. Cambpell to Produce Documents (filed via facsimile).
Date: 05/14/1999
Proceedings: Respondent Southern HY Power`s Amended Motion to Compel Petitioners Bernard M.Campbell and Bessie H. Campbell to Produce Documents (filed via facsimile).
Date: 05/12/1999
Proceedings: Letter to Mr.Thompson from B. & B. Campbell Re: Requesting legal status of Southern Hy Power and Hy Power Corporations (filed via facsimile).
Date: 05/06/1999
Proceedings: (S. Berger) Notice and Certificate of Service of Interrogatories to Respondent State of Florida Department of Environmental Protection filed.
Date: 05/06/1999
Proceedings: (S. Berger) Notice and Certificate of Seravice of Interrogatories to Respondent Southern HY Power Corporation filed.
Date: 04/28/1999
Proceedings: Respondent Southern HY Power Corporation`s Second Request for Production of Documents to Petitioner Sarah E. (Betty Berger filed.
Date: 04/28/1999
Proceedings: Respondent Southern HY Power Corporation`s Second Request for Production of Documents to Bernard M. Campbell and Bessie H. Campbell filed.
Date: 04/27/1999
Proceedings: Respondent Southern Hy Power`s Motion to Compel Petitioners Bernard M. Campbell and Bessie H. Campbell to Answer Interrogatories (filed via facsimile).
Date: 04/27/1999
Proceedings: Respondent Southern Hy Power`s Motion to Compel Petitioners Bernard M. Campbell and Bessie H. Campbell to Produce Documents (filed via facsimile).
Date: 04/27/1999
Proceedings: Respondent Southern Hy Powser`s Motion to Compel Petitioner Sarah E. Berger to Produce Documents (filed via facsimile).
Date: 04/27/1999
Proceedings: Respondent Southern Hy Power`s Motion to Compel Petitioner Sarah E. Berger to Answer Interrogatories (filed via facsimile).
Date: 04/27/1999
Proceedings: Letter to Judge Dean from B. Campbell (Re: request for subpoenas) (filed via facsimile).
Date: 04/23/1999
Proceedings: (DEP) Notice and Certificate of Service of Interrogatories to Petitioners, Bernard M. Campbell and Bessie H. Campbell filed.
Date: 04/23/1999
Proceedings: (DEP) Notice and Certificate of Service of Interrogatories to Petitioner, Sarah E. Berger filed.
Date: 04/23/1999
Proceedings: Respondent Department of Environmental Protection`s First Request for Production of Documents to Petitioner`s, Bernard M. Campbell and Bessie H. Campbell filed.
Date: 04/23/1999
Proceedings: Respondent Department of Environmental Protection`s First Request for Production of Documents to Petitioner, Sarah E. Berger filed.
Date: 04/19/1999
Proceedings: First Set of Interrogatories of Respondent Southern HY Power Corporation to Petitioners Bernard M. Campbell and Bessie H. Campbell filed.
Date: 04/12/1999
Proceedings: Letter to Judge Dean from S. Berger Re: Intent to permit by DEP filed.
Date: 03/18/1999
Proceedings: (D. Thompson) Notice of Propounding First Set of Interrogatories on Petitioner Sarah E. (Betty) Berger; Notice of Propounding First Set of Interrogatories on Petitioners Bernard M. Campbell and Bessie H. Campbell filed.
Date: 03/18/1999
Proceedings: Order of Consolidation andNotice of Hearing sent out. (Consolidated cases are: 99-000307, 99-000308, 99-000694, 99-000696; hearing set for June 9-11, 1999; Inglis)
Date: 03/16/1999
Proceedings: (D. Thompson) Notice of Propounding First Set of Interrogatories on Petitioner Sarah E. (Betty) Berger (filed via facsimile).
Date: 02/25/1999
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
Date: 02/24/1999
Proceedings: (DEP) Motion to Consolidate (Cases requested to be consolidated: 99-307, 99-308, 99-694, 99-696) filed.
Date: 02/19/1999
Proceedings: Initial Order issued.
Date: 02/16/1999
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Petition for Administrative Hearing; Notice of Intent to Issue (letter) rec`d

Case Information

Judge:
STEPHEN F. DEAN
Date Filed:
02/16/1999
Date Assignment:
02/19/1999
Last Docket Entry:
05/17/2000
Location:
Inglis, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (5):

Related Florida Statute(s) (6):

Related Florida Rule(s) (6):