99-001916
Vincent D`antoni vs.
David Boston And Department Of Environmental Protection
Status: Closed
Recommended Order on Wednesday, March 22, 2000.
Recommended Order on Wednesday, March 22, 2000.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8VINCENT R. D'ANTONI, JR., )
13)
14Petitioner, )
16)
17vs. ) Case Nos. 99-1916
22) 99-2861
24DEPARTMENT OF ENVIRONMENTAL )
28PROTECTION and DAVID BOSTON, )
33)
34Respondents. )
36________________________________)
37RECOMMENDED ORDER
39Pursuant to notice, a formal hearing was held in these cases
50on September 28, 1999, and January 27, 2000, in Jacksonville,
60Florida, and by telephone on February 21, 2000, before Donald R.
71Alexander, the assigned Administrative Law Judge of the Division
80of Administrative Hearings.
83APPEARANCES
84For Petitioner: Vincent R. D'Antoni, Jr., pro se
923824 Wayland Street
95Jacksonville, Florida 32277
98For Respondent: Francine M. Ffolkes, Esquire
104(agency) Department of Environmental Protection
1093900 Commonwealth Boulevard
112Mail Station 35
115Tallahassee, Florida 32399-3000
118For Respondent: David Boston, pro se
124(Boston) 2262 Orchard Street
128Jacksonville, Florida 32209
131STATEMENT OF THE ISSUES
135The issues are whether David Boston should be issued an
145environmental resource permit and sovereign submerged lands
152authorization allowing him to construct 96 linear feet of rip rap
163revetment; construct a private dock of less than 1,000 square
174feet; and place 3,500 square feet of fill in non-jurisdictional
185areas; and whether he qualifies for a general permit to place a
197fill pad in isolated wetlands adjacent to the St. Johns River, a
209Class III waterbody.
212PRELIMINARY STATEMENT
214This matter began on November 5, 1998, when Respondent,
223Department of Environmental Protection, issued a letter advising
231Respondent, David Boston, that he "qualified" to "use a noticed
241general permit to fill less than 4,000 square feet of an isolated
254wetland to facilitate construction of a single family home"; that
264the project was not on state owned submerged lands, and therefore
275he needed no authority from the agency to use those lands for
287private purposes; and that the project was exempt from the
297Environmental Resources Program permitting. That matter has been
305assigned Case No. 99-2861. On January 21, 1999, the agency
315issued a Notice of Permit Issuance advising interested parties
324that Respondent, David Boston, was being issued an environmental
333resource permit and submerged lands authorization to "construct a
342rip rap revetment and dock" on his property located adjacent to
353the St. Johns River in Duval County, Florida. That matter has
364been assigned Case No. 99-1916.
369By letter dated January 26, 1999, Petitioner, Vincent R.
378D'Antoni, Jr., an adjacent property owner, objected to the
387issuance of a permit in Case No. 99-1916 on the grounds that the
400proposed dock would infringe on the navigable area of his own
411dock; the fill would increase flooding on his property; and the
422project would harm an endangered fern. On June 1, 1999,
432Petitioner filed an Amended Petition for Administrative Hearing
440in Case No. 99-2861 alleging that the applicant does not qualify
451for a general permit because the filling would cause flooding on
462Petitioner's property; the stormwater storage function would be
"470eradicated"; and the use of the permit would diminish water
480quality and wildlife habitat in the river, thereby adversely
489affecting the value of his property.
495The two matters were referred by the agency to the Division
506of Administrative Hearings on April 28 and June 30, 1999,
516respectively, with a request that an Administrative Law Judge be
526assigned to conduct a formal hearing. At the request of the
537agency, both cases were consolidated by Order dated August 20,
5471999.
548By Notice of Hearing dated June 10, 1999, a final hearing
559was scheduled in Case No. 99-1916 on September 28, 1999, in
570Jacksonville, Florida. Later, however, the order of
577consolidation provided that both matters would be heard at that
587time. On September 22, 1999, the cases were transferred from
597Administrative Law Judge P. Michael Ruff to the undersigned.
606At the final hearing on September 28, 1999, the Department
616of Environmental Protection made an ore tenus request for a
626continuance on the ground that it needed to depose Petitioner's
636expert witness. The unopposed request was granted, and the
645matters were later rescheduled to January 27, 2000, in
654Jacksonville, Florida. A continued hearing was held by telephone
663on February 21, 2000, for the limited purpose of allowing
673Petitioner's engineering expert to present rebuttal testimony.
680At the final hearing, Petitioner testified on his own behalf
690and presented the testimony of his wife, Nancy N. D'Antoni, and
701Ronnie D. Perron, a professional engineer. Also, he offered
710Petitioner's Exhibit Nos. 1-6, which were received in evidence.
719Petitioner's Exhibit No. 1 is the deposition testimony of Ronnie
729D. Perron. Respondent, Department of Environmental Protection,
736presented the testimony of Michael Eaton, manager of
744environmental resource permitting and accepted as an expert in
753permitting and environmental impact of projects on wetlands and
762surface waters; Robert M. Dunne, an environmental specialist II;
771David P. Apple, a professional engineer and accepted as an expert
782in stormwater engineering and design; and Respondent, David
790Boston. Also, it offered Respondent's Exhibit Nos. 1-14. All
799exhibits were received in evidence.
804The Transcript of the hearing (two volumes) was filed on
814February 25, 2000. Proposed Findings of Fact and Conclusions of
824Law were filed by the Department of Environmental Protection on
834March 10, 2000, and they have been considered by the undersigned
845in the preparation of this Recommended Order. None were filed by
856the other parties.
859FINDINGS OF FACT
862Based upon all of the evidence, the following findings of
872fact are determined:
8751. In this permitting dispute between neighbors,
882Petitioner, Vincent R. D'Antoni, Jr., contends generally that
890Respondent, David Boston (Boston), will cause flooding to
898Petitioner's property by reason of placing too much fill on an
909isolated wetland, which lies in the center of Boston's property.
919The filling is in conjunction with Boston's efforts to construct
929a single-family residence and private dock on his property,
938purchased in June 1998, which lies adjacent to the St. Johns
949River, a Class III waterbody, in Duval County, Florida.
9582. In preliminary decisions made on November 5, 1998, and
968January 21, 1999, Respondent, Department of Environmental
975Protection ( DEP), "acknowledge[d] receipt" of Boston's intent to
984use a noticed general permit "to fill less than 4,000 square feet
997of an isolated wetland to facilitate construction of a single
1007family home" on his lot (Case No. 99-2861), and gave notice of
1019its intent to issue Boston an environmental resource permit and
1029sovereign submerged lands authorization allowing him to construct
1037a rip rap revetment and a dock and to place 3,500 square feet of
1052fill in mainly non-jurisdictional areas (Case No. 99-1916).
10603. Although a number of objections were raised by
1069Petitioner in his original filings, as clarified at the final
1079hearing, Petitioner now contends that Boston placed excessive
1087fill on his lot, including an isolated wetland, and that the fill
1099has resulted in flooding, saturated soil, or standing water on
1109Petitioner's property. He also contends that the location of
1118Boston's proposed dock will affect the ability to use his own
1129dock. Because no evidence was presented on the docking issue,
1139and through admissions Petitioner acknowledged that there will be
1148no adverse environmental impacts, no consideration will be given
1157to those objections. Finally, Petitioner does not object to the
1167placement of the rip rap revetment on the shoreline.
1176Accordingly, the request for an environmental resource permit and
1185consent to use sovereign submerged lands in Case No. 99-1916
1195should be approved.
11984. The property in issue lies just south of the
1208Jacksonville University Country Club and a few blocks west of
1218University Boulevard North on Wayland Street, which fronts the
1227eastern side of the St. Johns River in a tract of land known as
1241University Park. Except for the Boston lot, all other waterfront
1251lots are now developed. When facing the river from Wayland
1261Street, Petitioner's lot lies to the right of Boston's lot, while
1272another lot owned by Robert Henderson (Henderson) lies to the
1282left of Boston's lot. The lots are up to 500 feet deep; Boston's
1295lot is around 96 feet wide, while Petitioner's lot has a similar
1307width but narrows to only 20 feet or so near the river.
13195. At the river end of the D'Antoni, Boston, and Henderson
1330lots is an area of contiguous wetlands. Until 1995, DEP
1340regulated those wetland areas and this prevented D'Antoni and
1349Henderson from placing any fill in those areas. Under DEP's
1359current wetland delineation rule, however, such areas are non-
1368jurisdictional, and any placement of fill at the river end is
1379outside the purview of DEP's jurisdiction.
13856. Before Boston's lot was cleared and filled, it was about
1396a foot lower in elevation than the D'Antoni lot; this was true
1408even though Petitioner has never changed the natural grade of his
1419property since it was purchased and developed. Therefore, water
1428tended to flow naturally from an upland area north or east of the
1441D'Antoni lot, through the D'Antoni lot to Boston's lot, and then
1452through the lower part of the Henderson lot populated by "very
1463mature cypress trees," and eventually into the St. Johns River.
14737. According to a 1977 aerial photograph, the Boston lot
1483contained what appears to be a tidal connection from an uplands
1494area through the wetlands on his property to the river. However,
1505construction on property adjacent to the Henderson lot sometime
1514after 1977 severed this connection, and a tidal connection
1523(direct hydrologic connection) to the river no longer exists.
15328. Under Rule 62-341.475(1)(f), Florida Administrative
1538Code, "a single family residence" is exempt from the
1547Environmental Resource Program permitting and a general permit
1555will be granted "as long as it is not part of a larger plan of
1570common development," and "the total area of dredging or filling
1580in isolated wetlands for the residence and associated residential
1589improvement shall not exceed 4000 square feet." Since there is
1599no longer a direct hydrologic connection between the wetlands on
1609Boston's property and the St. Johns River, the wetlands are
1619isolated within the meaning of this rule.
16269. Availing himself of the foregoing provision, on
1634October 19, 1998, Boston gave notice to DEP "of [his] intent to
1646use a noticed general permit to fill less than 4,000 square feet
1659of an isolated wetland" on his property. He also provided
1669certain drawings and other information (prepared by his surveyor)
1678to show that he qualified for the permit. DEP does not "issue" a
1691noticed general permit; rather, it only determines whether the
1700applicant qualifies for a permit and then "acknowledges" this
1709fact. Accordingly, on November 5, 1998, DEP "acknowledge[d]
1717receipt" of Boston's notice.
172110. Although DEP encourages the user of such a permit to
1732notify affected or adjoining property owners, there was no legal
1742requirement that Boston do so, and he proceeded to clear the lot
1754and then fill a part of the wetland area with two or three feet
1768of dirt without giving notice to Petitioner or Henderson, his two
1779neighbors. The filling raised the elevation of the Boston
1788property at least two feet above the D'Antoni and Henderson lots
1799and impeded the prior natural flow of water. At the same time,
1811Boston constructed a three to four-foot timber wall (consisting
1820of railroad ties) on the Henderson property line to retain the
1831fill and a similar two-foot wall on Petitioner's line. These
1841changes had the effect of impounding the water which had
1851previously flowed naturally in a north-south direction through
1859the wetlands from the D'Antoni lot to the Boston lot to the
1871Henderson lot. It also generated runoff from the Boston lot to
1882the D'Antoni lot, which had not previously occurred.
189011. When Petitioner observed the adjacent lot being cleared
1899and filled, and the resulting erosion of fill onto his property,
1910pooling of water, and damage to his chain link fence after a
1922heavy rain in January 1999, he filed a complaint with DEP. An
1934inspection was made by DEP, and Boston was told to stop work
1946until corrective changes were made to ensure that such flooding
1956would not occur. After a series of changes were made which
1967satisfied DEP's concerns, the stop work order was lifted. Boston
1977also signed a consent order and paid a $100.00 fine. However,
1988pending the outcome of these cases, no further construction work
1998has occurred.
200012. Petitioner has contended that Boston has placed more
2009than 7,200 square feet of fill on his property in violation of
2022the rule, which limits the amount of fill to less than 4,000
2035square feet. While this amount of filling has in fact occurred,
2046approximately 3,500 square feet of fill was placed in non-
2057jurisdictional areas between the shoreline and the isolated
2065wetlands, and the rule only requires that Boston limit his fill
2076to less than 4,000 square feet on the isolated wetland. Thus,
2088contrary to a suggestion by Petitioner's engineer, the
2096jurisdictional and non-jurisdictional filling are not totaled
2103together to determine whether the threshold within the rule has
2113been exceeded.
211513. Through photographs received in evidence and testimony
2123by Petitioner and his wife, it was established that flooding or
2134standing water has occurred on Petitioner's property during heavy
2143rainfalls since the filling occurred, even as recently as
2152January 2000. The evidence further shows that Petitioner's chain
2161link fence has been damaged through the weight of the fill
2172pressing against the fence. In addition, Petitioner has suffered
2181the loss of "a couple of trees" because of "mucky" and
" 2192oversaturated" soil caused by excessive water. Also, a dog
2201house on a raised platform in the back yard which was previously
2213dry now "stays in water." These affected areas lie immediately
2223adjacent to the filled area of the isolated wetland on Boston's
2234property. Finally, there is an erosion problem beyond the
2243isolated wetland consisting of sand and silt flowing from
2252Boston's lot onto Petitioner's lot during heavy rainfalls.
2260Despite these problems, Petitioner does not object to the
2269development of the lot; he only asks that Boston do so in a
2282manner which prevents these conditions from recurring in the
2291future.
229214. Petitioner's engineering expert, Ronnie D. Perron
2299( Perron), a professional engineer who visited the site in August
23101999, ran a computer model (Interconnected Channel and Pond
2319Routing, Version 2.11) showing runoff both before and after the
2329fill was placed on Boston's lot. He concluded that "there was
2340over one and a half feet of flooding in that wetlands due to
2353filling Mr. Boston's lot" during a "mean annual storm event,"
2363which assumes five inches of rain during a 24-hour period. Even
2374when he used more conservative estimates, Perron still arrived at
2384water accumulations ranging from 0.6 feet to 1.5 feet. This
2394excessive runoff is caused by the retaining wall and fill, which
"2405blocks off" the water and causes it to "spread out in
2416[Petitioner's] whole back yard."
242015. In response to Perron's model, a DEP professional
2429engineer, David P. Apple (Apple), ran another computer model
2438(PONDS, Version 2.25) received in evidence as Respondent's
2446Exhibit No. 14. That model shows that during a three-year, one-
2457hour storm event, the small depressed area on Boston's property
2467(including the isolated wetland) had sufficient storage capacity
2475to absorb up to six inches of runoff from off-site areas and not
2488overflow back onto Petitioner's property. This size of storm
2497event (which produces two and one-half inches of rain in an hour)
2509is typically used by the Department in calculations for single-
2519family residential property when the impervious area site is less
2529than fifty percent. In this case, Apple didn't "feel that the
2540impervious area out there was greater than [fifty] percent."
2549Therefore, Apple concluded that the storm event used by Perron
2559was too large, and that the smaller event used in his model was
2572more appropriate. He also concluded that the Boston property
2581could retain all water in a normal storm event without
2591discharging any stormwater onto the D'Antoni lot. He did not,
2601however, address the issue of the fill and retaining wall on the
2613Boston lot impounding the water on his neighbor's lot.
262216. In developing the input perameters for his model, Apple
2632assumed that water falling at the front (Wayward Street) side of
2643the D'Antoni property drained to the front roadway; in fact, much
2654of that water drains to the rear of the lot into the wetland
2667area. A similar incorrect assumption was made regarding runoff
2676on the Boston lot. If modifications were made to account for the
2688proper drainage patterns, the Apple model would show larger
2697amounts of water staging on the Boston property during rainfall
2707events, which would increase the possibility of runoff onto the
2717D'Antoni lot.
271917. Apple questioned the accuracy of the Perron model given
2729the fact that Perron had used a larger storm event than he
2741(Apple) believed was appropriate. However, even if Perron had
2750used a three-year, one-hour storm event on his computer model, as
2761advocated by Apple, he established that it would have resulted in
2772flood staging on Petitioner's property between 0.97 and 1.64 feet
2782during a smaller storm event.
278718. DEP proposed no solutions to the water problems on the
2798D'Antoni lot, presumably because it concluded that the rule was
2808satisfied; that by filling the Boston lot, it was no longer the
" 2820stormwater pond for the neighborhood runoff"; and that DEP had
2830no other regulatory authority to solve this peculiar situation.
2839The record shows clearly, however, that if no changes are made,
2850water will continue to back up on Petitioner's property by virtue
2861of the higher elevation on the Boston lot, and the possibility of
2873runoff from Boston's lot exists during certain storm events.
2882Neither condition existed before the fill was added.
289019. To correct the foregoing conditions, Perron proposes
2898two corrective measures. First, Boston should install a yard
2907drain (underground culvert) beginning in the wetlands area of his
2917property and outfalling to the cypress trees on the adjacent
2927Henderson lot. Besides providing an outfall for the excess
2936water, this would also help recharge the mature cypress trees on
2947the Henderson lot. Second, D'Antoni should install a series of
"2957yard drains" using high-density polyethylene pipes to convey the
2966standing water on his lot directly into the St. Johns River. The
2978expert opined that neither activity would require a permit from
2988DEP. These modifications are reasonable and appropriate and
2996should be used by the factioning parties. Accordingly, the
3005installation of a yard drain should be a condition for Boston to
3017use his noticed general permit.
3022CONCLUSIONS OF LAW
302520. The Division of Administrative Hearings has
3032jurisdiction over the subject matter and the parties hereto
3041pursuant to Sections 120.569 and 120.57(1), Florida Statutes.
304921. As the party filing an application, Boston bears the
3059burden of proving by a preponderance of the evidence that he is
3071entitled to an environmental resource permit and sovereign
3079submerged lands authorization and that he is qualified to use the
3090noticed general permit. See , e.g. , Cordes v. State, Dep't of
3100Envir. Reg. , 582 So. 2d 652, 654 (Fla. 1st DCA 1991)(permit
3111generally); Castoro et al. v. Palmer and Dep't of Envir. Prot. ,
3122Case Nos. 95-5879 and 96-0736 ( Dep't of Envir. Prot., October 16,
31341998) (noticed general permit).
313822. Because Petitioner either withdrew his objections,
3145admitted through requests for admission, or failed to present any
3155proof regarding the issues involved in Case No. 99-1916, Boston's
3165application for an environmental resource permit and consent to
3174sovereign submerged lands should be approved. This will allow
3183him to construct 96 linear feet of rip rap revetment at the mean
3196high water mark of the St. Johns River, construct a private dock
3208of less than 1,000 square feet, and place 3,500 square feet of
3222fill on non-jurisdictional areas of his property.
322923. Rule 62-341.475, Florida Administrative Code, governs
3236the use of noticed general permits for minor activities, a type
3247of permit for which Boston seeks qualification to use in Case
3258No. 99-2861. Pertinent to this controversy are the disputed
3267criteria found in Sections (1) and (2) of the rule.
3277Subparagraphs (1)(f)3. and 4. require that the filling be limited
3287to "isolated wetlands," and that it "not exceed 4000 square
3297feet," while Paragraph (2)(c) requires that the filling "not
3306impede the conveyance of a stream, river[,] or other watercourse
3317in a manner that would increase off-site flooding."
332524. The evidence is undisputed that the jurisdictional
3333filling on Boston's property will be limited to less than 4,000
3345square feet in an isolated wetland. In addition, the evidence
3355shows that there is no stream, river, or other watercourse within
3366the meaning of DEP rules or statutes on the isolated wetland.
3377Therefore, because no watercourse exists on the property, the
3386filling cannot increase the type of off-site flooding envisioned
3395by the regulation. Assuming this analysis to be correct, then
3405the computer modeling by both experts was an academic exercise
3415since any off-site flooding which might be increased because of
3425the filling would not affect Boston's qualifications to use this
3435type of permit.
343825. Even so, it is clear that the filling impedes the
3449natural flow of water that occurred before the changes were made.
3460As noted in the Findings of Fact, during heavy rains which have
3472occurred as recently as January 2000, the D'Antoni lot has
3482suffered standing water and saturated soil, erosion of sand and
3492silt from the Boston lot, and damage to a chain link fence. If
3505this forum can provide no relief, then D'Antoni can only hope
3516that the drought conditions prevelant in northeast Florida will
3525continue for an indefinite period of time, or he can raise the
3537elevation of his lot by adding at least two feet of fill. For
3550obvious reasons, neither alternative is practical.
355626. Given these considerations, the solution offered by
3564Witness Perron is both reasonable and appropriate and should be
3574incorporated into the use of any noticed general permit. This
3584will result in both parties bearing the cost of making
3594improvements to their respective lots and should alleviate the
3603conditions now experienced by Petitioner.
3608RECOMMENDATION
3609Based on the foregoing Findings of Fact and Conclusions of
3619Law, it is
3622RECOMMENDED that the Department of Environmental Protection
3629enter a final order granting the application for a permit and
3640consent in Case No. 99-1916 and confirming that David Boston
3650qualifies for use of a noticed general permit in Case No. 99-2861
3662provided, however, that such use be conditioned on Boston
3671constructing an underground culvert with a yard drain from the
3681wetland area on his lot to the St. Johns River.
3691DONE AND ENTERED this 22nd day of March, 2000, in
3701Tallahassee, Leon County, Florida.
3705___________________________________
3706DONALD R. ALEXANDER
3709Administrative Law Judge
3712Division of Administrative Hearings
3716The DeSoto Building
37191230 Apalachee Parkway
3722Tallahassee, Florida 32399-3060
3725(850) 488-9675 SUNCOM 278-9675
3729Fax Filing (850) 921-6847
3733www.doah.state.fl.us
3734Filed with the Clerk of the
3740Division of Administrative Hearings
3744this 22nd day of March, 2000.
3750COPIES FURNISHED:
3752Kathy Carter, Agency Clerk
3756Department of Environmental Protection
37603900 Commonwealth Boulevard
3763Mail Station 35
3766Tallahassee, Florida 32399-3000
3769Vincent R. D'Antoni, Jr.
37733824 Wayland Street
3776Jacksonville, Florida 32277
3779David Boston
37812262 Orchard Street
3784Jacksonville, Florida 32209
3787Francine M. Ffolkes, Esquire
3791Department of Environmental Protection
37953900 Commonwealth Boulevard
3798Mail Station 35
3801Tallahassee, Florida 32399-3000
3804Teri Donaldson, General Counsel
3808Department of Environmental Protection
38123900 Commonwealth Boulevard
3815Mail Station 35
3818Tallahassee, Florida 32399-3000
3821NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
3827All parties have the right to submit written exceptions within 15
3838days from the date of this Recommended Order. Any exceptions to
3849this Recommended Order should be filed with the agency that will
3860enter a final order in this case.
- Date
- Proceedings
- PDF:
- Date: 03/22/2000
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 09/28/99 & 01/27/2000.
- Date: 03/10/2000
- Proceedings: DEP`s Proposed Recommended Order (for Judge Signature) filed.
- Date: 03/09/2000
- Proceedings: Department`s Exhibit 14 w/cover letter filed.
- Date: 02/25/2000
- Proceedings: Transcript filed.
- Date: 02/21/2000
- Proceedings: CASE STATUS: Hearing Held.
- Date: 02/21/2000
- Proceedings: Letter to Judge Alexander from R. Perron Re: Summary (filed via facsimile).
- Date: 02/21/2000
- Proceedings: Letter to Judge Alexander from R. Perron Re: Summary (filed via facsimile).
- Date: 02/10/2000
- Proceedings: Transcript filed.
- Date: 02/02/2000
- Proceedings: Order sent out. (Petitioner shall have until 2/10/00, to notify the undersigned whether he intends to offer testimony in response to Respondent`s Exhibit 14)
- Date: 01/27/2000
- Proceedings: CASE STATUS: Hearing Held.
- Date: 01/18/2000
- Proceedings: Amended Notice of Hearing sent out. (hearing set for January 27, 2000; 9:00 a.m.; Jacksonville, Florida, amended as to TIME and LOCATION)
- Date: 12/02/1999
- Proceedings: Amended Notice of Hearing sent out. (hearing set for January 27, 2000; 10:30 a.m.; Jacksonville, Florida)
- Date: 11/23/1999
- Proceedings: Memorandum to Judge Alexander & Judge Ruff from V. D`Antoni Re: Date not available (filed via facsimile).
- Date: 11/08/1999
- Proceedings: Order Scheduling Hearing sent out. (hearing set for 12/22/99; 10:30am; Jacksonville)
- Date: 10/26/1999
- Proceedings: DEP`s Response to Order (filed via facsimile).
- Date: 10/21/1999
- Proceedings: Memorandum to Judge Alexander from V. D`Antoni Re: Dates not available (filed via facsimile).
- Date: 10/11/1999
- Proceedings: Order sent out. (parties shall respond within 15 days from the date of this order)
- Date: 09/28/1999
- Proceedings: Hearing Partially Held, continued to date not certain.
- Date: 09/24/1999
- Proceedings: (Respondent) Notice (filed via facsimile).
- Date: 09/24/1999
- Proceedings: Letter to Judge Alexander from V. D`Antoni Re: Late arrival of interrogatories; Interrogatories; Exhibits filed.
- Date: 09/23/1999
- Proceedings: DEP`s Prehearing Statement filed.
- Date: 09/22/1999
- Proceedings: Order sent out. (changing location of hearing)
- Date: 09/22/1999
- Proceedings: DEP`s Witness and Exhibit List; DEP`s Motion to Compel and for Admissions filed.
- Date: 08/20/1999
- Proceedings: Order of Consolidation sent out. (Consolidated cases are: 99-001916, 99-002861)
- Date: 08/11/1999
- Proceedings: (DEP) Notice and Certificate of Service of Interrogatories filed.
- Date: 08/11/1999
- Proceedings: Department of Environmental Protection`s First Request for Admissions With Interrogatories filed.
- Date: 06/30/1999
- Proceedings: (DEP) Motion to Consolidate (Cases requested to be consolidated: 99-1916, 99-2861) filed.
- Date: 06/10/1999
- Proceedings: Notice of Hearing sent out. (hearing set for 10:30am; Jacksonville; 9/28/99)
- Date: 05/17/1999
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
- Date: 04/29/1999
- Proceedings: Initial Order issued.
- Date: 04/28/1999
- Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Notice of Permit Issuance filed.