01-000947BID Universal Precision Industries, Inc. vs. Tampa Bay Water, A Regional Water Supply Authority
 Status: Closed
Recommended Order on Friday, May 4, 2001.


View Dockets  
Summary: Failure to supply certain documents with bid proposed wad minor irregularity that could be waived by agency.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8UNIVERSAL PRECISION )

11INDUSTRIES, INC., )

14)

15Petitioner, )

17)

18vs. ) Case No. 01- 0947BID

24)

25TAMPA BAY WATER, )

29)

30Respondent, )

32)

33and )

35)

36COMMERCE CONTROLS, INC., and )

41TAMPA ARMATURE WORKS, INC., )

46)

47Intervenors. )

49____________________________ )

51RECOMMENDED ORDER

53This matter was heard before the Division of

61Administrative Hearings by its assigned Administrative Law

68Judge, Donald R. Alexander, on April 3, 2001, in Tampa,

78Florida.

79APPEARANCES

80For Petitioner : Dominick J. Graziano, Esquire

87Bavol , Bush & Sisco , P.A.

92100 South Ashley Drive, Suite 2100

98Tampa, Florida 33602-5311

101For Respondent : Richard A. Harrison, Esquire

108Allen, Dell, Frank & Trinkle , P.A.

114Post Office Box 2111

118Tampa, Florida 33601-2111

121Barrie S. Buenaventura, Esquire

125Tampa Bay Water

1282535 Landmark Drive, Suite 211

133Clearwater, Florida 33761-3930

136For Intervenor : Stephen D. Marlowe, Esquire

143( CCI) Marlowe & McNabb , P.A.

149324 South Hyde Park Avenue, Suite 210

156Tampa, Florida 33606-4127

159For Intervenor : Michael M. MacInnes, Treasurer

166(Armature) E. Mark Tempest, Manager

171Tampa Armature Works, Inc.

175440 South 78th Street

179Tampa, Florida 33619

182STATEMENT OF THE ISSUE

186The issue is whether Tampa Bay Water's award of a

196contract to Commerce Controls, Inc. to furnish control panel

205fabrications for a regional water treatment plant under

213Contract No. 2001-22 was contrary to competition, arbitrary,

221or capricious, as alleged by Petitioner.

227PRELIMINARY STATEMENT

229This matter began on February 5, 2001, when Respondent,

238Tampa Bay Water, advised all bidders, including Petitioner,

246Universal Precision Industries, Inc., the third lowest

253responsive bidder, that it intended to award Contract No.

2622001-22 to Intervenor, Commerce Controls, Inc., to provide

270certain control panel fabrications. By a written protest

278filed on February 13, 2001, Petitioner alleged that the award

288of the contract was clearly erroneous, contrary to

296competition, arbitrary, and capricious because the apparent

303successful bidder had failed to comply with the bid

312specifications in three material respects.

317On February 21, 2001, Petitioner requested a hearing

325under Sections 120.569 and 120.57(3), Florida Statutes (2000),

333to contest the proposed action. The matter was referred by

343Respondent to the Division of Administrative Hearings on

351March 7, 2001, with a request that an Administrative Law Judge

362be assigned to conduct a hearing. By Notice of Hearing dated

373March 9, 2001, a final hearing was scheduled on April 3, 2001,

385in Tampa, Florida. On March 19, 2001, Intervenor, Commerce

394Controls, Inc., was authorized to intervene in this

402proceeding. On March 30, 2001, the case was transferred from

412Administrative Law Judge J. Lawrence Johnston, Jr. to the

421undersigned. Intervenor, Tampa Armature Works, Inc., the

428second lowest bidder, was authorized to intervene at the final

438hearing subject to the issues already raised by Petitioner.

447At the final hearing, Petitioner presented the testimony

455of John A. Sessa, its chief financial officer; Joseph Kehoe,

465instrumentation and control supervisor for Tampa Bay Water;

473and Sean Gucken, an employee of Commerce Controls, Inc. The

483parties also offered Joint Exhibits 1-19, which were received

492in evidence. Exhibits 18 and 19 are the depositions of

502Karen R. Lawson, an employee of Commerce Controls, Inc., and

512James L. Hall, a consultant with Parsons Engineering Science,

521who assisted in the preparation of the Invitation for Sealed

531Bids.

532The Transcript of the hearing was filed on April 11,

5422001. Proposed Findings of Fact and Conclusions of Law were

552filed by Tampa Armature Works, Inc. on April 20, 2001, and by

564the other parties on April 23, 2001. These filings have been

575considered by the undersigned in the preparation of this

584Recommended Order.

586FINDINGS OF FACT

589Based upon all of the evidence, the following findings of

599fact are determined:

602a. Background

6041. In this bid dispute, Petitioner, Universal Precision

612Industries, Inc. (UPI), contends that Respondent, Tampa Bay

620Water, acted contrary to competition and in an arbitrary and

630capricious manner when it proposed to award a contract to

640Intervenor, Commerce Controls, Inc. ( CCI), the lowest

648responsive bidder. In its petition, UPI alleged that CCI

657failed to include in its bid documents "catalog cuts and

667information with complete model number, manufacturer's

673specifications, and dimension drawings describing the proposed

680component," as required by the specifications. As further

688clarified at hearing, UPI alleged that CCI deviated from the

698specifications in a material respect by submitting a price for

708a "customized-made panel" instead of a higher costing Hoffman

717panel ( encloser ), and by submitting prices for a mix of AC/DC

730surge protectors rather than 100 percent DC surge protectors.

739All other allegations in the petition have been abandoned.

748UPI goes on to contend that by CCI pricing out the two items

761in this manner, CCI gained a competitive advantage of around

771$36,000.00 over UPI.

7752. Tampa Bay Water is a regional water supply authority

785created and existing pursuant to Sections 163.01, 373.1962,

793and 373.1963, Florida Statutes, and an interlocal agreement

801among Pinellas, Pasco, and Hillsborough Counties and the

809Cities of Tampa, New Port Richey , and St. Petersburg known as

820the "Amended and Restated Interlocal Agreement Reorganizing

827the West Coast Regional Water Supply Authority," dated June

83610, 1998. In all, Tampa Bay Water is responsible for meeting

847the potable water needs of approximately two million

855customers.

8563. The controversy began on January 8, 2001, when Tampa

866Bay Water issued an Invitation for Sealed Bids for Contract

876No. 2001-22 for the fabrication of certain control panels and

886associated parts for a regional water treatment plant. In

895paragraph 2 of the Instructions to Bidders, Tampa Bay Water

905specifically reserved the right "to waive any and all minor

915irregularities and technicalities."

9184. A mandatory pre-bid conference was held on

926January 23, 2001. Representatives of UPI, CCI, and

934Intervenor, Tampa Armature Works, Inc. (TAW), attended the

942conference and later submitted bids. Thereafter, the sealed

950bids were opened publicly on January 30, 2001. CCI submitted

960the lowest bid ($469,481.00), TAW the second lowest bid

970($486,144.00), while UPI submitted the third lowest bid

979($495,000.00).

9815. On February 5, 2001, Respondent announced its

989intention to award the contract to CCI, who submitted the

999lowest responsive bid. After efforts to informally resolve

1007the dispute were unsuccessful, this action was filed.

1015b. The bid documents

10196. The Instructions to Bidders required that

"1026[q ] uotations for services are to be provided on the Bid

1038Schedule included herein." They further provided that

"1045[p ] roposals must be provided on the Bid Schedule included

1056with the contract documents." The Bid Schedule form in the

1066bid documents provided fourteen line items to be completed by

1076the bidders : one line each for each of the seven control

1088panels and one line each for the factory acceptance testing on

1099each panel. The Bid Schedule also provided a pre-determined

1108Owner's Allowance and then a "Total Contract Price" line for

1118the fifteen line items.

11227. The Instructions to Bidders further required that

"1130[a ] ll quotations must reflect delivered cost which includes

1140all packing, handling, shipping charges, taxes, discounts and

1148delivery to Tampa Bay Water."

11538. In a section of the "Conditions of the Contract," the

1164following requirements were imposed:

1168The proposal shall include the following:

1174Catalog cuts and information with complete

1180model number, manufacturer's

1183specifications, and dimension drawings

1187describing the proposed components.

1191Total cost to Owner of all components

1198including a separately itemized freight

1203cost to the project site.

1208Per diem costs, expenses included, for

1214supplying an experienced representative to

1219the project site to assist with startup and

1227operator training.

1229Delivery time of all panels following

1235receipt of purchase order.

12399. In the same section of the bid documents, under a

1250heading entitled "Qualifications of Bidders," there is found a

1259requirement that "[t ]he Unit Control Panels shall be bid in

1270detail, depicting a base unit price per device, utilizing an

1280Excel spreadsheet supplied to the bidder."

128610. Finally, the bid documents contained seven

1293spreadsheets, one for each of the panels, which set forth by

1304line item a description of each component, its function, the

1314manufacturer's name and model number, and the quantity

1322required. The last column of each spreadsheet was blank and

1332was titled "Costs."

133511. The purpose of a bidder submitting spreadsheets was

1344to ensure that Tampa Bay Water was getting the specific

1354components identified in those spreadsheets. Therefore, Tampa

1361Bay Water wanted to ensure that the bidder was furnishing the

1372parts specified, but it was not concerned with the manner in

1383which a bidder may have priced any particular components.

139212. The specifications also called for a number of surge

1402protectors for each of the seven panels. However, they did

1412not specify whether the protectors would be AC or DC, or the

1424number of each. Because there is a significant difference in

1434price between the two, a few days before the bids were to be

1447submitted, a UPI employee, Frank Dressel, made a telephonic

1456inquiry with James L. Hall, an outside consultant who assisted

1466in the preparation of the specifications, seeking

1473clarification. Hall advised Dressel that he should price out

1482his proposal using all DC surge protectors, even though the

1492specifications were not clear on that point, and he was unsure

1503of the exact number of DC surge devices that would ultimately

1514be used. Hall later conveyed this same advice to all bidders

1525before the bids were submitted.

1530c. CCI's bid proposal

153413. CCI's bid proposal did not include the catalog cut

1544sheets (product specification sheets) or the spreadsheets in

1552its proposal. However, CCI provided a cover letter with its

1562proposal which stated that

1566The bid requirements asked for several

1572items, for which there was no line on the

1581bid form. This proposal addition serves to

1588provide the additional information

1592required.

15931. The equipment we are providing is the

1601exact model as specified by Tampa Bay

1608Water, therefore, we have not included the

1615catalog cut sheets or major equipment

1621listing with our bid. We can, if

1628necessary, provide the information.

16322. Per diem expenses for an electrician

1639for wiring field terminations to the

1645control panels $336.00, based on an 8 hour

1653day.

16543. Per diem expenses for a CCI start-up

1662technician would be $900.00, based upon a

166940 hour work week.

16734. Freight expenses are $7,000.00.

167914. After reading the letter, a Tampa Bay Water

1688representative, Joseph Kehoe, "felt comfortable" with that

1695statement and treated it as a representation by CCI that it

1706would supply the exact parts specified by Tampa Bay Water. In

1717an abundance of caution, however, Kehoe sought guidance from

1726his General Counsel regarding the apparent irregularities in

1734the CCI bid, as well as apparent irregularities in the second

1745lowest bid submitted by TAW. The General Counsel advised that

1755the irregularities appeared to be minor and could be waived,

1765but that further clarification could be sought from the

1774bidders with respect to any of the omitted information.

178315. Kehoe then sought clarification from CCI regarding

1791the freight charges and delivery schedule. He also requested

1800the spreadsheets and catalog cut sheets previously offered by

1809CCI in its response. By letters dated February 2 and 5, and

1821March 1, 2001, and a "Supplemental Information" submittal

1829containing the spreadsheets and catalog sheets, CCI provided

1837the necessary clarification. That information confirmed the

1844accuracy of the representations in CCI's January 30, 2001,

1853letter, which indicated that CCI would supply all of the

1863required equipment at the price stated in its bid.

1872d. UPI's concerns

187516. According to UPI's chief financial officer, John

1883Sessa, CCI "did not provide pricing or part numbers to

1893indicate that they were supplying" some of the items required

1903by the specifications. More specifically, three of the seven

1912panels required Hoffman enclosures. In reviewing the CCI

1920proposal, Sessa could find no price quote for a Hoffman

1930enclosure, but he did find a manufacturer's quote for a

1940similar enclosure by another manufacturer, Thermal Designs and

1948Manufacturing ( TDM). Also, Sessa was unable to determine

1957whether CCI's bid was based on all DC surge protectors.

1967Therefore, Sessa concluded that CCI was not supplying the

1976Hoffman enclosures or the required number of DC surge

1985protectors. By CCI using lower costing parts in pricing out

1995its bid, Sessa contended that CCI had obtained a competitive

2005advantage over UPI.

200817. The prices used for CCI's bid were prepared by

2018Karen R. Lawson, a sales engineer in CCI's Plymouth, Michigan

2028office. Lawson gathered her estimates from catalogs and

2036vendors and then submitted them to her supervisor, Jerry

2045Zitterman, who in turn forwarded them to a CCI employee in

2056St. Petersburg, Florida.

205918. Because she either gave the vendor an incorrect part

2069number for a Hoffman panel, or there was a substantial lead

2080time in obtaining such a unit, Lawson used a price for a

2092customized panel made by TDM, and not the price for a Hoffman

2104panel. That price, however, was later adjusted upward by more

2114than 25 percent in the bid proposal, presumably to take into

2125account the labor component. In pricing out the surge

2134protectors, Lawson used an average unit price, which was

2143derived by taking "both prices and [using] an average of those

2154numbers."

215519. Notwithstanding the manner in which it had priced

2164out the panel and surge protectors, CCI unequivocally agreed

2173that it was obligated to supply all equipment specified by

2183Tampa Bay Water by manufacturer and part number, and that was

2194the intent of its January 30, 2001, letter included in its bid

2206proposal. At the same time, Tampa Bay Water understood that

2216CCI was supplying all of the items specified in the

2226spreadsheets and that CCI would be held to its bid price as to

2239all of the specified components.

224420. CCI's failure to supply the spreadsheets and catalog

2253cut sheets at the time the bid proposal was submitted, and its

2265manner of pricing out the required panels and surge

2274protectors, were minor deviations from the specifications, did

2282not give CCI a substantial advantage over other bidders, and

2292did not adversely affect the interests of Tampa Bay Water.

2302This is especially true here since CCI's bid proposal included

2312a letter which indicated that CCI would provide all required

2322equipment at the stated price. Under the terms of the

2332Invitation for Sealed Bids, Tampa Bay Water properly waived

2341the minor irregularities in order to achieve the purpose of

2351securing the lowest responsible bid.

2356e. UPI's bid proposal

236021. There were a number of irregularities in UPI's bid

2370as well. For example, certain items in the spreadsheets had a

2381dash instead of a price in the "Costs" column. UPI's bid

2392proposal also failed to provide any information as to the per

2403diem costs from an experienced representative to assist with

2412start up and operator training. In addition, UPI changed the

2422indicated quantities for each component in the spreadsheets

2430from whatever Tampa Bay Water had specified to a quantity of

2441one. Finally, as to two of the three different size fuses

2452required for each of its panels, UPI's spreadsheet failed to

2462list a price and showed a quantity of zero.

247122. A representative of Tampa Bay Water established that

2480had UPI been the lowest bidder, the agency would have sought

2491clarification from the bidder as to the above items in the

2502same manner that it sought clarification from CCI.

2510f. TAW's bid proposal

251423. TAW's bid also omitted the catalog cut sheets and

2524the spreadsheets, and it failed to provide any information as

2534to freight charges, per diem start up expenses, or delivery

2544schedule. Clarification regarding these items would also have

2552been required, had TAW submitted the lowest bid.

2560CONCLUSIONS OF LAW

256324 . The Division of Administrative Hearings has

2571jurisdiction over the subject matter and the parties hereto

2580pursuant to Sections 120.569 and 120.57(3), Florida Statutes

2588(2000).

258925. Tampa Bay Water is a regional water supply authority

2599established pursuant to Sections 373.1961 and 373.1962,

2606Florida Statutes (2000). Thus, it is not a state agency and

2617subject to the competitive bidding requirements found in

2625Section 287.057, Florida Statutes (2000).

263026. There are no provisions in Sections 373.1961 and

2639373.1962, Florida Statutes (2000), pertaining to burden of

2647proof, grounds for overturning a regional water supply

2655authority's preliminary decision, or the standard of proof.

2663In the absence of specific statutory requirements, public

2671entities such as Tampa Bay Water have the obligation to engage

2682in contracting procedures in a manner which is not arbitrary

2692and capricious. See , e.g. , Volume Services Div. of Interstate

2701United Corp. v. Canteen Corp. , 369 So. 2d 391, 394 (Fla. 2d

2713DCA 1979); Eagle Tire & Service Center v. Escambia County

2723Utilities Authority , DOAH Case No. 00- 0661BID ( Escam. Cty .

2734Util. Auth ., July 14, 2000).

274027. However, by Rule 49B-3.002, Florida Administrative

2747Code, Tampa Bay Water has submitted to, and adopted, the

2757procedures and substantive requirements of Section 120.57(3),

2764Florida Statutes (2000), for purposes of resolving contract

2772bid disputes. Therefore, that statute controls this

2779proceeding. Paragraph (3)(f) provides in relevant part as

2787follows:

2788(f ) In a competitive-procurement protest,

2794no submissions made after the bid or

2801proposal opening shall be considered.

2806Unless otherwise provided by statute, the

2812burden of proof shall rest upon the party

2820protesting the proposed agency action. In a

2827competitive-procurement protest, other than

2831a rejection of all bids, the administrative

2838law judge shall conduct a de novo proceeding

2846to determine whether the agency’s proposed

2852action is contrary to the agency’s governing

2859statutes, the agency’s rules or policies, or

2866the bid or proposal specifications. The

2872standard of proof for such proceedings shall

2879be whether the proposed agency action was

2886clearly erroneous, contrary to competition,

2891arbitrary, or capricious.

289428. Under the foregoing statute, the undersigned is

2902first obliged to determine, in a de novo setting, whether

2912Respondent's action is contrary to governing statutes, rules,

2920policies, or bid specifications. Within that factual

2927framework, it must then be determined if the Board’s action is

2938clearly erroneous, contrary to competition, arbitrary, or

2945capricious. In its Proposed Recommended Order, UPI contends

2953that Tampa Bay Water's decision to award the contract to CCI

2964was arbitrary, capricious, and contrary to competition. The

2972contention that the decision was clearly erroneous has

2980apparently been abandoned.

298329. Under long-standing principles, an arbitrary

2989decision is one not supported by fact or logic while a

3000decision is capricious if it is taken without thought or

3010reason. The inquiry to be made in determining whether an

3020agency has acted arbitrarily or capricious is whether the

3029agency has (1) considered all relevant factors; (2) given

3038actual, good faith consideration to those factors; and (3)

3047used reason rather than whim to progress from consideration of

3057those factors to its final decision. Adam Smith Enterprises,

3066Inc. v. State Dep't of Envir. Reg. , 553 So. 2d 1260, 1273

3078(Fla. 1st DCA 1989). At the same time, if a decision is

3090justifiable under any analysis that a reasonable person would

3099use to reach a decision of similar importance, the decision is

3110neither arbitrary or capricious. Dravco Basic Materials Co.,

3118Inc. v. State, Dep't of Trans. , 602 So. 2d 632, 634, fn. 3

3131(Fla. 2d DCA 1992).

313530. An act is contrary to competition when it offends or

3146subverts the fundamental policies underlying competitive

3152procurement. Enpower, Inc. et al. v. Tampa Bay Water et al. ,

3163DOAH Case No. 99- 3398BID (Tampa Bay Water, Nov. 15, 1999).

3174Those policies have been described as protecting the public

3183against collusive contracts; securing fair competition on

3190equal terms for all bidders or proposers ; removing not only

3200collusion, but the temptation for collusion and the

3208opportunity for private gain at public expense; closing all

3217avenues to favoritism and fraud in whatever form; securing the

3227best value for the public at the lowest possible expense; and

3238affording an equal advantage to all persons desiring to do

3248business with the government. Wester v. Belote et al. , 138

3258So. 721, 723-24 (Fla. 1931).

326331. Finally, Tampa Bay Water has specifically reserved

3271the right "to waive any and all minor irregularities and

3281technicalities." In doing so, it cannot accept a bid that is

3292materially at variance with the specifications. But not every

3301deviation from the bid specifications is material. A

3309deviation is only material if it gives a proposer a

3319substantial advantage over the other proposers and thereby

3327restricts or stifles competition. Tropabest Foods, Inc. v.

3335Dep't of Gen. Svcs. , 493 So. 2d 50 (Fla. 1st DCA 1986). If a

3349deviation does not provide a proposer with such a palpable

3359competitive advantage, it constitutes a minor irregularity

3366that should be waived. Robinson Electrical Co., Inc. v. Dade

3376Co. , 417 So. 2d 1032, 1034 (Fla. 3d DCA 1982). See also

3388Intercontinental Properties, Inc. v. Dep't of Health and

3396Rehab. Svcs. , 606 So. 2d 380, 387 (Fla. 3d DCA 1992)(there is

3408a "strong public policy against disqualifying the low bidder

3417for technical deficiencies which do not confer an economic

3426advantage on one bidder over another").

343332. UPI contends that Tampa Bay Water acted arbitrarily

3442and capriciously and in a manner which is contrary to

3452competition by accepting a letter from CCI as an assurance

3462that the required parts would be supplied, and as a substitute

3473for the spreadsheets and catalog cut sheets required by the

3483specifications.

348433. Tampa Bay Water's actions were not shown to be

3494contrary to any statute, rule, or policy. Neither did they

3504sanction a material variance from the bid specifications. In

3513the Invitation for Sealed Bids, Tampa Bay Water reserved the

3523right "to waive any and all minor irregularities and

3532technicalities." The irregularities in CCI's bid did not give

3541it a substantial advantage over the other bidders, restrict

3550competition, affect the price of the bid, or adversely impact

3560the interests of the agency. Under these circumstances, the

3569irregularities were clearly minor, and Tampa Bay Water could

3578waive them in order to secure the lowest responsible bid.

358834. The evidence further shows that Tampa Bay Water's

3597bid reviewer ( Kehoe) acted reasonably under the circumstances

3606by immediately recognizing the apparent deficiencies in CCI's

3614bid, seeking guidance from his General Counsel, and requesting

3623clarification from CCI as to certain items in its bid. Based

3634on its evaluation of the information, Tampa Bay Water

3643confirmed the accuracy of CCI's representation in its proposal

3652that it would supply all of the requested equipment at the

3663stated price. Therefore, the agency did not act arbitrarily

3672or capriciously, as alleged by UPI.

367835. Finally, the award of the contract to CCI was not

3689shown to be contrary to competition. More specifically, there

3698was no evidence of collusion, unfair competition by the

3707bidders, favoritism, or one bidder having an unequal advantage

3716over the others. Indeed, in awarding the contract to CCI,

3726Tampa Bay Water merely secured the best value for the public

3737at the lowest possible expense.

3742RECOMMENDATION

3743Based on the foregoing Findings of Fact and Conclusions

3752of Law, it is

3756RECOMMENDED that the Tampa Bay Authority enter a final

3765order awarding the contract to CCI, the lowest responsive

3774bidder.

3775DONE AND ENTERED this 4th day of May, 2001, in

3785Tallahassee, Leon County, Florida.

3789___________________________________

3790DONALD R. ALEXANDER

3793Administrative Law Judge

3796Division of Administrative Hearings

3800The DeSoto Building

38031230 Apalachee Parkway

3806Tallahassee, Florida 32399-3060

3809(850) 488- 9675 SUNCOM 278-9675

3814Fax Filing (850) 921-6847

3818www.doah.state.fl.us

3819Filed with the Clerk of the

3825Division of Administrative He arings

3830this 4th day of May, 2001.

3836COPIES FURNISHED:

3838Donald D. Conn, General Counsel

3843Tampa Bay Water

38462535 Landmark Drive, Suite 211

3851Clearwater, Florida 33761-3930

3854Barrie S. Buenaventura, Esquire

3858Tampa Bay Water

38612535 Landmark Drive, Suite 211

3866Clearwater, Florida 33761-3930

3869Dominick J. Graziano, Esquire

3873Bavol , Bush & Sisco , P.A.

3878100 South Ashley Street, Suite 2100

3884Tampa, Florida 33602-5311

3887Richard A. Harrison, Esquire

3891Allen, Dell, Frank & Trinkle , P.A.

3897Post Office Box 2111

3901Tampa, Florida 33601-2111

3904Steven D. Marlowe, Esquire

3908Marlowe & McNabb , P.A.

3912324 South Hyde Park Avenue, Suite 210

3919Tampa, Florida 33606-4127

3922Michael M. MacInnis, Treasurer

3926Tampa Armature Works, Inc.

3930440 South 78th Street

3934Tampa, Florida 33619

3937NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

3943All parties have the right to submit written exceptions within

395315 days from the date of this Recommended Order. Any

3963exceptions to this Recommended Order should be filed with the

3973agency that will render a final order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 05/24/2001
Proceedings: Final Order filed.
PDF:
Date: 05/21/2001
Proceedings: Agency Final Order
PDF:
Date: 05/04/2001
Proceedings: Recommended Order
PDF:
Date: 05/04/2001
Proceedings: Recommended Order issued (hearing held April 3, 2001) CASE CLOSED.
PDF:
Date: 05/04/2001
Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
PDF:
Date: 04/24/2001
Proceedings: Universal Precision Industries, Inc. Notice of Filed Proposed Recommended Order (filed via facsimile).
PDF:
Date: 04/24/2001
Proceedings: Letter to Judge Alexnder from R. Harrison (disk of Joint Proposed Order) filed.
PDF:
Date: 04/23/2001
Proceedings: (Proposed) Recommended Order (filed via facsimile).
PDF:
Date: 04/23/2001
Proceedings: Universal Precision Industries, Inc. Proposed Recommended Order (filed via facsimile).
PDF:
Date: 04/23/2001
Proceedings: Notice of Filing Joint Proposed Recommended Order (filed via facsimile).
PDF:
Date: 04/20/2001
Proceedings: Recommended Order filed by Intervenor.
Date: 04/11/2001
Proceedings: Exhibits filed.
Date: 04/11/2001
Proceedings: Deposition Transcripts filed.
Date: 04/11/2001
Proceedings: Transcript of Hearing filed.
Date: 04/03/2001
Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
PDF:
Date: 04/02/2001
Proceedings: Pre-Hearing Stipulation (filed via facsimile).
PDF:
Date: 04/02/2001
Proceedings: Petitioner`s Supplemental Exhibit List (filed via facsimile).
Date: 03/30/2001
Proceedings: Pre-Hearing Stipulation (filed by Petitioner via facsimile).
PDF:
Date: 03/30/2001
Proceedings: Opposition to Motion to Intervene of Tampa Armature Works, Inc. (filed via facsimile).
PDF:
Date: 03/29/2001
Proceedings: Tampa Bay Water`s Response to Petitioner`s First Request for Production of Documents (filed via facsimile).
PDF:
Date: 03/28/2001
Proceedings: Petitioner`s Second Amended Notice of Taking Deposition Duces Tecum of Intervenor`s Party Designes and Notice of Taking Deposition of Witness (filed via facsimile).
PDF:
Date: 03/28/2001
Proceedings: Petition to Intervene as Party (filed by Tampa Armature Works, Inc ("TAW").
PDF:
Date: 03/28/2001
Proceedings: Tampa Bay Water`s Motion in Limine (filed via facsimile).
PDF:
Date: 03/26/2001
Proceedings: Petition to Intervene as Party (filed by M. MacInnes via facsimile).
PDF:
Date: 03/26/2001
Proceedings: Notice of Filing Petitioner`s Answers to Interrogatories; Petitioner`s Answers to Interrogatories (filed via facsimile).
PDF:
Date: 03/26/2001
Proceedings: Petitioner`s Amended Notice of Taking Deposition Duces Tecum of Intervenor`s, Commerce Controls, Inc., Party Designees Amended as to Time (filed via facsimile).
PDF:
Date: 03/22/2001
Proceedings: Notice of Taking Deposition (of Frank Dressler) filed via facsimile.
PDF:
Date: 03/22/2001
Proceedings: Petitioner`s First Request for Production to Respondent (filed via facsimile).
PDF:
Date: 03/22/2001
Proceedings: Petitioner`s First Interrogatories to Respondent (filed via facsimile).
PDF:
Date: 03/22/2001
Proceedings: Petitioner`s Notice of Serving First Interrogatories to Respondent (filed via facsimile).
PDF:
Date: 03/22/2001
Proceedings: Petitioner`s Notice of Taking Depositon Duces Tecum of Intervenor`s, Commerce Controls, Inc., Party Designee (filed via facsimile).
PDF:
Date: 03/20/2001
Proceedings: Notice of Taking Deposition Duces Tecum, John Sessa (filed via facsimile).
PDF:
Date: 03/20/2001
Proceedings: Petitioner`s Supplemental Notice of Taking Deposition Duces Tecum of Joseph Kehoe (filed via facsimile).
PDF:
Date: 03/20/2001
Proceedings: Petitioner`s Response to Tampa Bay Water`s First Request for Production (filed via facsimile).
PDF:
Date: 03/20/2001
Proceedings: Petitioner`s Notice of Serving Answers to Interrogatories (filed via facsimile).
PDF:
Date: 03/19/2001
Proceedings: Order Granting Leve to Intervene issued (Commerce Controls, Inc.).
PDF:
Date: 03/19/2001
Proceedings: Tampa Bay Water`s Consent to Petition to Intervene (filed by Richard Harrison via facsimile).
PDF:
Date: 03/16/2001
Proceedings: Petitioner`s Notice of Taking Deposition Duces Tecum (filed via facsimile).
PDF:
Date: 03/16/2001
Proceedings: Petition to Intervene as Party (filed via facsimile).
PDF:
Date: 03/12/2001
Proceedings: Notice of Appearance as Co-Counsel (filed by Richard Harrison via facsimile).
Date: 03/12/2001
Proceedings: Tampa Bay Water`s First Request for Production to Petitioner (filed via facsimile).
Date: 03/12/2001
Proceedings: Notice of Serving Tampa Bay Water`s First Set of Interrogatories to Petitioner (filed via facsimile).
PDF:
Date: 03/12/2001
Proceedings: Tampa Bay Water`s Motion to Strike Petitioner`s Claim for Attorney`s Fees (filed via facsimile).
PDF:
Date: 03/09/2001
Proceedings: Notice of Hearing issued (hearing set for April 3, 2001; 9:00 a.m.; Tampa, FL).
PDF:
Date: 03/09/2001
Proceedings: Order of Pre-hearing Instructions issued.
PDF:
Date: 03/07/2001
Proceedings: Petition for Formal Administrative Hearing filed.
PDF:
Date: 03/07/2001
Proceedings: Notice of Protest filed.
PDF:
Date: 03/07/2001
Proceedings: Letter to Mr. Harper from J. Keasling re: Notice of Intent filed.
PDF:
Date: 03/07/2001
Proceedings: Agency referral filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
03/07/2001
Date Assignment:
03/28/2001
Last Docket Entry:
05/24/2001
Location:
Tampa, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (4):

Related Florida Rule(s) (1):