02-000573EPP
In Re: Florida Power And Light Martin Unit 8 Power Plant Siting Application No. Pa89-27a vs.
*
Status: Closed
Recommended Order on Wednesday, March 5, 2003.
Recommended Order on Wednesday, March 5, 2003.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: FLORIDA POWER & LIGHT )
15COMPANY MARTIN UNIT 8 )
20POWER PLANT SITING )
24APPLICATION NO. PA89 - 27A. ) Case No. 02 - 0573EPP
35____________________________________)
36RECOMMEND ED ORDER
39Pursuant to notice, the Division of Administrative Hearings,
47by its duly designated Administrative Law Judge, Charles A.
56Stampelos, held a certification hearing in the above - styled case
67on February 17, 2003, in Indiantown, Florida.
74APPEARANCES
75For Florida Power & Light Company:
81Peter C. Cunningham, Esquire
85Douglas S. Roberts, Esquire
89Hopping Green & Sams
93Post Office Box 6526
97Tallahassee, Florida 32314
100For the Department of Environmental Protecti on:
107Scott A. Goorland, Esquire
111Department of Environmental Protection
1153900 Commonwealth Boulevard
118The Douglas Building, Mail Station 35
124Tallahassee, Florida 32399 - 3000
129For Martin County:
132Krista Storey, Esquire
135Martin County
1372401 Southeast Monterey Road
141Stuart, Florida 34996 - 3322
146STATEMENT OF THE ISSUE
150The issue to be resolved in this proceeding is whether the
161Governor and Cabinet, sitting as the Siting Board, should issue
171certification to Flor ida Power & Light Company ("FPL"), to
183construct and operate a combined cycle generating unit, providing
192an additional 800 megawatts, at FPL's existing Martin Plant site
202in Martin County, Florida, and an associated 8.5 mile
211transmission line in accordance w ith the Florida Electrical Power
221Plant Siting Act, Section 403.501, et seq. , Florida Statutes.
230PRELIMINARY STATEMENT
232This proceeding was conducted pursuant to the Florida
240Electrical Power Plant Siting Act ("PPSA"), Chapter 403, Part II,
252Florida Statutes, and Chapter 62 - 17, Florida Administrative Code,
262to consider FPLs application for site certification for the
271proposed Martin Unit 8 Project (also referred to as the
"281Project").
283On February 1, 2002, FPL filed its application for site
293certification for the Martin Unit 8 Project with the Florida
303Department of Environmental Protection ("Department" or "FDEP").
312The application was found to be complete on February 18, 2002.
323The application was found to be sufficient on June 5, 2002.
334As required by Section 403 .508(1) and (2), Florida Statutes,
344a land use hearing on the Project was held in the community of
357Indiantown, Florida, on May 1, 2002. By Final Order, dated
367August 13, 2002, the Siting Board adopted the undersigneds
376Recommended Land Use Order, holding th at the site of the proposed
388Martin Unit 8 Project is consistent and in compliance with the
399land use plans and zoning ordinances of Martin County, Florida.
409On December 10, 2002, the Florida Public Service Commission
418("PSC") issued its Final Order determin ing the need for Martin
431Unit 8, pursuant to Section 403.519, Florida Statutes.
439On December 20, 2002, the FDEP issued its written Staff
449Analysis Report concerning the Project, as required by Section
458403.507(4), Florida Statutes. That Report contained rep orts from
467other state, regional, and local agencies and a compiled set of
478proposed Conditions of Certification for the Martin Unit 8
487Project, as proposed by FDEP and the various agencies which had
498reviewed the Project.
501On February 10, 2003, a J oint P rehear ing S tipulation was
514submitted to the undersigned, which indicated that no party to
524this proceeding objected to certification of the Project.
532On February 17, 2003, during the certification hearing, FDEP
541submitted its revised Staff Analysis Report as an exhi bit (FDEP
552Exhibit 2) to update and correct various matters in the earlier
563version of its analysis, and to revise the proposed Conditions of
574Certification.
575After proper public notice by both FPL and FDEP, a
585certification hearing was held in Indiantown, Fl orida, on
594February 17, 2003, as required by Section 403.508(3), Florida
603Statutes. The purpose of the certification hearing was to
612receive oral, written, and documentary evidence concerning
619whether, through available and reasonable methods, the location,
627c onstruction, and operation of the proposed Martin Unit 8 Project
638will produce minimal adverse effects on human health, the
647environment, the ecology of the land and its wildlife, and the
658ecology of State waters and their aquatic life, in an effort to
670fully balance the increase in demand for an electrical power
680plant location and operation with the broad interests of the
690public. See Section 403.502, Florida Statutes. The hearing
698would have also considered any petitions challenging the separate
707FDEP - issued p revention of significant deterioration ("PSD")
718permit for the Project. However, no such petition was filed.
728Prefiled written direct testimony and exhibits of seven FPL
737witnesses were filed with the Division of Administrative Hearings
746on February 12, 2003. That testimony was filed pursuant to Rule
75762 - 17.141(3), Florida Administrative Code. At the certification
766hearing, FPL presented summary testimony and exhibits of three of
776those witnesses, affirming their prefiled testimony and exhibits
784and summarizing portions of their testimony. The prefiled
792written testimony and exhibits of four witnesses have been
801accepted based upon execution of affidavits from those witnesses
810not attending the hearing, attesting to the accuracy of the
820testimony and accompanying ex hibits. FPL exhibits numbered 1
829through 8 were introduced and admitted into evidence. FDEP
838presented the testimony of Hamilton S. Oven, Jr., P.E., of the
849FDEP's Siting Coordination Office, and FDEP Exhibits 1 and 2 were
860admitted into evidence. Martin Co unty also attended the
869certification hearing. Martin County's Agency Report was
876accepted into evidence as part of the FDEP's Staff Analysis
886Report. The Florida Public Service Commission, the Florida
894Department of Community Affairs, the Florida Fish and W ildlife
904Conservation Commission, the Florida Department of
910Transportation, and the South Florida Water Management District
918(SFWMD), all of which were parties to this proceeding, did not
929enter appearances at the certification hearing. However, those
937agenci es joined in the prehearing stipulation. The agency
946reports from these five agencies and from the Treasure Coast
956Regional Planning Council were accepted into evidence as part of
966the FDEP's Staff Analysis Report. At the conclusion of the
976hearing, members of the general public were allowed to offer
986testimony on the Project.
990Following the conclusion of the February 17, 2003, hearing,
999a transcript of the hearing was filed on February 21, 2003. The
1011Joint Proposed Order of FPL, FDEP, SFWMD, and Martin County w as
1023timely submitted and has been considered in the rendition of this
1034Recommended Order.
1036FINDINGS OF FACT
1039Background
10401. Florida Power & Light Co. ("FPL") is the largest
1052electric utility in Florida, currently serving approximately
1059seven million customers i n its 34 - county service area. That
1071service area extends south from the northern Florida border along
1081the east coast of the State, and includes all of the southern
1093portion of the Florida peninsula. FPL currently operates 34
1102generating units at 14 location s in Florida, including the Martin
1113Plant. FPL has been supplying electricity in Florida since 1926.
11232. FPL's Martin Plant site is located in the western
1133portion of Martin County, Florida, approximately seven miles
1141northwest of the community of Indiantow n, Florida. The Martin
1151Plant is located in the unincorporated area of Martin County.
1161Access is by State Road 710, which runs northwest/southeast along
1171the northeast boundary of the Martin Plant site.
11793. The Martin Plant site contains approximately 11, 300
1188acres. The existing Martin Plant includes two 800 megawatt
1197(nominal) steam - electric generating units known as Units 1 and 2,
1209two 450 megawatt (nominal) combined cycle generating units known
1218as Units 3 and 4, and two 170 megawatt (nominal) simple cycle
1230combustion turbines known as Units 8A and 8B. FPL applied for
1241permits for Martin Units 1 and 2 prior to 1973. Martin Units 1
1254and 2, which use residual fuel oil and natural gas, began
1265commercial operation in 1980 and 1981, respectively. Martin
1273Units 3 a nd 4, which use natural gas and are permitted to burn
1287distillate or "light" oil, were certified under the PPSA in 1991
1298and began operation in 1994. Units 8A and 8B, which use natural
1310gas and light oil, were approved through modification of the
1320original si te certification in 2000, and began operation in 2001.
1331Units 1 and 2, 3 and 4, 8A and 8B, and associated facilities,
1344occupy approximately 400 acres of the Martin Plant site.
13534. The Martin Plant site has long been identified for
1363additional generating ca pacity. When site certification for
1371Units 3 and 4 was issued, the Siting Board also recognized the
1383Martin Plant sites suitability for further capacity expansion
1391through its "ultimate site capacity" approval for the three - phase
1402Martin Coal Gasification/Co mbined Cycle (CG/CC) Project. That
1410Project contemplated, following construction of Units 3 and 4,
1419two additional phases involving combined cycle Units 5 and 6,
1429with supporting coal gasification facilities, and then
1436construction of a coal gasification faci lity to support Units 3
1447and 4. FPL has not as yet chosen to proceed with the latter two
1461phases of that Project. The portion of the Martin Plant site
1472certified under the PPSA comprises 2,192 acres. Neither FPL, nor
1483any other party, has invoked, or sought to invoke, the
1493jurisdiction of the PPSA with respect to Martin Units 1 and 2.
1505The Martin Plant site has continued to be identified as a
1516preferred location for additional generating capacity in each of
1525FPL's Ten Year Power Plant Site Plans for the past de cade.
1537Existing Units 1, 2, 3, and 4 will remain in operation and will
1550not be affected by the Project.
15565. The Martin Plant site contains a 6,800 acre cooling
1567pond (6,500 acres of water surface and 300 acres of embankment),
1579which provides cooling water t o the four existing steam electric
1590generating units at the site. Makeup water for the cooling pond
1601is withdrawn from the St. Lucie Canal, under a Permit Agreement
1612between FPL and SFWMD. Withdrawals from the St. Lucie Canal have
1623occurred since 1978. Make up water from the St. Lucie Canal is
1635currently withdrawn pursuant to the terms of a permit agreement
1645between the South Florida Water Management District and FPL and
1655the existing Conditions of Certification for Martin Units 3 and
16654. The existing approvals allow withdrawals of an average of
167532,000 - acre feet of water per year and a maximum of 50,000 - acre
1692feet in any 12 month period. Daily withdrawals are limited to a
1704maximum of 518.4 million gallons per day.
17116. Other existing facilities on the Martin Plan t site
1721include residual and light oil storage tanks, water and
1730wastewater treatment facilities, two onsite system substations
1737and transmission lines, warehouses, maintenance buildings, and
1744administration and ancillary facilities. The balance of the
1752Martin site is undeveloped or utilized for agricultural
1760operations. This includes the Barley Barber Swamp and a 1,200
1771acre parcel, known as the Northwest Parcel, established as a
1781wetland mitigation area associated with the Martin CG/CC Project.
17907. Land uses surrounding the Martin Plant site are
1799primarily agricultural, including cropland, pastures, groves,
1805three types of wetlands, scattered rural residences, and
1813undeveloped land. The nearest residence is approximately two
1821miles away from the proposed Martin U nit 8 Project area.
1832Project Overview
18348. The Martin Unit 8 Project will combine the two
1844existing simple cycle combustion turbines in operation at the
1853Martin Plant (Units 8A and 8B) with two new combustion turbines,
1864four new heat recovery steam generators , and a new steam turbine
1875electric generator. The resulting "four - on - one" combined cycle
1886Unit 8 will have a generating capacity of approximately 1,100
1897megawatts and will increase the total installed generating
1905capacity of the Martin Plant by approximately 800 megawatts. The
1915Project also includes an optional cooling tower and two new
1925transmission lines to integrate Unit 8 with FPL's transmission
1934system.
19359. Martin Unit 8 will be located south of existing Units
19463 and 4, with the new steam turbine and the new CTs (8C and 8D)
1961adjacent to and east of existing Units 8A and 8B. The Project
1973Area comprises approximately 110 acres. The Unit 8 power block
1983will be located in an area that has already been affected by
1995existing uses at the Martin Plant. Approximate ly 15.5 acres will
2006be occupied by the Unit 8 power block. Approximately 28.4 acres
2017will be occupied by construction facilities (laydown, parking and
2026construction trailers). The Project Area is located completely
2034within the already certified portion of th e Martin Plant Site.
2045Need for Martin Unit 8
205010. On December 10, 2002, the Florida Public Service
2059Commission ("PSC") issued its Final Order determining the need
2070for the FPL Martin Unit 8 Project (as well as FPL's proposed Unit
20833 at its Manatee Plant). The PSC determined that FPL has a need
2096for additional capacity to maintain the reliability of FPLs
2105electrical system. FPL was found to have a need for Martin Unit
21178 taking into account the need for adequate electricity at a
2128reasonable cost. The Commissi on found that FPL chose a proven
2139technology and has the necessary experience in the construction
2148and operation of combined cycle units. Further, the cost
2157estimates for Martin Unit 8 were found to be reasonable. The
2168Commission concluded there were no furt her energy conservation
2177measures available to FPL that could offset the need for Martin
2188Unit 8. FPL was found to have implemented a considerable amount
2199of cost effective energy conservation and demand side management.
2208Based upon FPLs evaluation of othe r alternatives submitted in
2218response to a request for proposals, the Commission found that
2228Martin Unit 8, along with Manatee Unit 3, are the most cost
2240effective alternatives available to meet FPL's need for
2248additional generating capacity beginning in 2005. The PSC also
2257found FPL had properly and accurately evaluated transmission
2265costs. The Commission concluded that FPL had met the statutory
2275requirements under Section 403.519, Florida Statutes, for the
2283determination of need for Martin Unit 8.
2290Project Sch edule and Construction
229511. FPL expects to begin construction of Martin Unit 8 in
2306June 2003, or upon receiving final approvals for the Project.
2316Unit 8 is expected to be completed in June 2005, in order to meet
2330FPL's customer's summer needs in that year. The simple cycle
2340portions of the two new combustion turbines associated with Unit
23508 are scheduled for completion in June 2004, to allow operation
2361in simple cycle mode while construction of the combined cycle
2371unit is ongoing. The two existing combustion tu rbines will
2381continue operating in simple cycle mode until the combined cycle
2391unit is completed.
239412. Peak construction employment for the Project will be
2403approximately 574 construction workers, management, and staff.
2410Construction employment is expected to average about 250 workers
2419during the 24 - month construction period.
242613. FPL made roadway improvements at the Martin Plant
2435entrance in connection with the construction of Units 3 and 4.
2446Construction of temporary or permanent roads that connect offsit e
2456is not proposed, as the existing plant entrance at S.R. 710 will
2468be used for Project constructionaffic resulting from Project
2476construction will not degrade traffic flow below established
2484levels of service. Major pieces of equipment will be delivere d
2495by truck over existing roadways, or by rail over a rail line that
2508already serves the Martin Plant site.
251414. The Unit 8 Project Area has been previously cleared and
2525graded, with scrubgrass cover. The Project will require minimal
2534clearing. Impacts from creating material laydown areas will be
2543minimal, temporary, and mainly associated with grubbing and
2551grading to create proper drainage.
255615. Soils will need to be excavated to provide support for
2567the Unit 8 foundation and other facilities. Foundations f or
2577heavy loads will be supported by spread foundations or pilings.
2587Subsurface excavations may require temporary dewatering by
2594localized pumping of the shallow aquifer to lower the water
2604table. The effluent from dewatering will be routed to the
2614cooling po nd. There will be no significant impacts from
2624construction dewatering on surface waters. No offsite impacts to
2633groundwater from dewatering activities are expected, and there
2641will be no impacts to underlying deeper aquifers.
264916. The entire construction area within the Unit 8 Project
2659Area is outside the 100 year flood zone. Construction activities
2669will alter runoff in parts of the site but no adverse effects are
2682expected from these activities. Construction period surface
2689water runoff will be conveyed to existing stormwater channels and
2699ponds that can provide wet retention for all runoff from these
2710areas. The stormwater management system for Unit 8 has been
2720previously designed and constructed as part of the development of
2730Units 3 and 4 and Units 8A and 8 B.
274017. No construction for the Project is proposed in surface
2750waters of the State. Impacts to offsite surface waters from
2760construction - related runoff are expected to be negligible.
2769Onsite construction activities will not cause adverse ecological
2777effe cts, as the Project Area is already highly altered, and
2788maintained as either grassy, open areas or covered with limerock.
2798These areas do not contain unique wildlife species and are not
2809considered important wildlife habitats because of their disturbed
2817natu re. Wetlands within the Project Area are limited primarily
2827to man - made ditches and stormwater basins. A small depressional
2838wetland area is located within the pine flatwoods parcel to the
2849east of the power block, but will not be impacted by the
2861constructi on of Unit 8. The site certification for the Martin
2872CG/CC Project addressed wetland impacts for the entire certified
2881site, and mitigation for those potential future impacts has
2890already been provided in the Northwest Parcel.
289718. Noise during construction of the Project will comply
2906with the Martin County Noise Control Ordinance. Construction
2914noise will not affect wildlife in the vicinity of the site. The
2926Martin Plant site already has noise associated with operation of
2936the existing facility and wildlife i n the area is acclimated to
2948such activities.
295019. Control measures will be implemented during Project
2958construction to minimize fugitive air emissions and its potential
2967impacts. Clearing will be kept to a minimum, thereby reducing
2977air emissions from expo sed surfaces. Watering will be used to
2988control fugitive dust on highly traveled areas.
299520. During Project construction, portable chemical toilets
3002and bottled water will be utilized. Solid and hazardous wastes
3012generated during construction will be handl ed and disposed
3021offsite by contractors.
3024Project Description
302621. The Martin Unit 8 Project will utilize the two existing
3037simple cycle combustion turbines ("CTs") presently operating at
3047the Site (Units 8A and 8B) in combination with two new CTs, four
3060new H RSGs, and a new steam turbine/electric generator. Each of
3071the existing CTs, and each of the new CTs, has a nominal
3083generating capacity of approximately 170 MWs. The CTs operate
3092much like a jet engine, in which air and fuel are combined in the
3106CT and then combusted. The heated gases then rotate a shaft that
3118drives an electrical generator. The exhaust gases from the
3127combustion turbines produce steam in the HRSGs, which is used in
3138turn to drive a separate steam turbine generator. By utilizing
3148the waste he at from the CTs, the resulting combined cycle Unit 8
3161will be more efficient than the simple cycle CTs and traditional
3172steam - electrical units. Martin Unit 8, with generating capacity
3182of approximately 1100 megawatts, will be among the most efficient
3192electri c generators in Florida. The Project will add
3201approximately 800 megawatts of generating capacity to the Martin
3210Plant site.
321222. Duct burners are proposed for each HRSG and are fired
3223during peak demand periods to achieve the total nominal
3232generating capac ity of Unit 8. The four CTs will be equipped
3244with inlet air evaporative cooling which creates a cooler, more
3254moisture - laden air stream in the CT, allowing additional power to
3266be produced more efficiently. The CTs will also be capable of
3277power augmentatio n, in which steam from the HRSG is injected into
3289the CT during periods of peak electrical demand to increase
3299electrical output. Each CT will be capable of operation in
"3309peak" mode in which the firing temperature of the combustion
3319turbine is increased, res ulting in increased power.
332723. Exhaust gases from Unit 8 will be emitted from a stack
3339associated with each HRSG unit. Each combustion turbine will
3348also be capable of operating in simple cycle mode in which
3359exhaust gases will be emitted either from a b ypass stack
3370associated with each CT or from the HRSG stack. Natural gas
3381heaters will be used if the CTs are operated in simple cycle
3393mode. The height of the four HRSG stacks will be a maximum of
3406150 feet.
340824. Cooling water for Martin Unit 8 will be pr ovided by
3420either the existing cooling pond or by a new closed - cycle, wet
3433mechanical draft cooling tower. Wastewaters and stormwater from
3441the power block will be treated onsite and recycled to the
3452cooling pond. Other onsite facilities to be constructed as part
3462of the Project will include interconnections with the existing
3471onsite transmission facilities, a gas metering and regulation
3479yard, along with storage facilities for light oil and ammonia.
3489The new Unit 8 will also utilize many of the existing facilit ies
3502and infrastructure components already present at the Martin Plant
3511site.
351225. The primary fuel for the CTs, and the sole fuel for
3524the HRSG duct burners and the fuel heaters, will be natural gas
3536delivered to the Martin Plant by pipeline. The Martin P lant site
3548is presently served by an existing natural gas lateral that may
3559supply gas to Unit 8. Natural gas will not be stored onsite.
3571Light oil with a maximum sulfur content of 0.05 percent by weight
3583will be used as an alternate fuel for the CTs for an equivalent
3596of 500 hours per year per CT. The light oil will be delivered by
3610truck and will be stored in an existing two million gallon tank
3622or in a previously approved, but still to be constructed, two
3633million gallon tank.
363626. Martin Unit 8 will gene rate only small quantities of
3647solid wastes. These will be limited to municipal solid wastes
3657and infrequent replacement of inlet air filters. The catalyst in
3667the selective catalytic reduction (SCR) system will be replaced
3676periodically and disposed of in a ccordance with applicable
3685requirements. Hazardous wastes will be produced in limited
3693quantities. These will be collected and disposed of offsite by a
3704licensed hazardous waste contractor.
370827. Martin Unit 8 will connect to the existing onsite
3718electrical system substation via a new tie line. Additional bays
3728will be added to the existing substation to accommodate the
3738interconnection to FPL's existing electric transmission system.
3745A new 230 kilovolt ('kV') transmission line will be constructed
3755between the onsite Martin Plant System Substation and the
3764existing FPL Indiantown Substation. The new single pole line
3773will be constructed across the Martin Plant site for 1.5 miles
3784and then will follow an existing FPL transmission line right - of -
3797way and existing pub lic roadways to the Indiantown substation.
3807The entire length of that line is approximately 13 miles. An 8.5
3819mile segment of this line is to be constructed in a new right - of -
3835way and this segment is included as part of the Project.
3846Air Emissions
384828. Air emissions from Martin Unit 8 will result from both
3859the combustion process and impurities in the fuel. Nitrogen
3868oxides are formed through the oxidation of a portion of the
3879nitrogen that is naturally found in natural gas. Additional
3888nitrogen oxides are fo rmed through the oxidation of the nitrogen
3899contained in the combustion air. Carbon monoxide and volatile
3908organic compounds are formed by incomplete combustion of fuel.
3917Sulfur dioxide and particulate matter emission rates are dictated
3926by the amount of sul fur in the fuel. Operation of the Unit 8
3940cooling tower will result in emissions of particulate matter,
3949made up of minerals, created by evaporation of the cooling water.
3960These emissions are referred to as cooling tower "drift".
397029. All major new or mod ified sources of regulated air
3981pollutants that are located in areas attaining compliance with
3990ambient air quality standards must be reviewed under state and
4000federal Prevention of Significant Deterioration ("PSD") review
4009requirements. Martin Unit 8 is cons idered a major modification
4019to the existing Martin Plant site because the Project's emissions
4029will exceed the PSD significant emission increase thresholds for
4038several regulated air pollutants. Based on expected emissions
4046from Unit 8, PSD review was requir ed for: particulate matter
4057("PM"), sulfur dioxide ("SO 2 "), nitrogen oxides ("NO x "), carbon
4073monoxide ("CO"), volatile organic compounds ("VOC") and sulfuric
4085acid mist. PSD review is used to ensure that significant air
4096quality deterioration will not result from new facilities like
4105Unit 8. These analyses include a review of the proposed
4115emissions control technology, a source impact analysis, an air
4124quality impact analysis, source information, and additional air
4132quality impact analyses.
4135Air Emissions Contr ol Technology
414030. Air emissions from Martin Unit 8 will be minimized
4150through the inherent efficiency of the combined cycle design, and
4160the use of: natural gas as the primary fuel; advanced combustion
4171control technology; and post - combustion control techno logy.
4180Natural gas, the cleanest of fossil fuels, and light oil have
4191very low levels of impurities and can be burned very efficiently.
4202When firing natural gas, the use of dry low NO x ("DLN") combustion
4217design in the CTs, and low NO x burners ("LNB") in the duct
4232burners, will also minimize air emissions by inhibiting formation
4241of thermal NO x by premixing of fuel and air prior to combustion
4254(in the DLN), and by reducing flame temperatures (in the DLN and
4266LNB). Water injection will be used for NO x control whe n the CTs
4280fire light oil. Selective Catalytic Reduction (SCR) will provide
4289additional control of emissions of NO x from Unit 8 when operating
4301in combined cycle mode. In the SCR system, located in the HRSGs,
4313ammonia is injected into the CT exhaust where NO x in the gas
4326stream reacts with the ammonia in the presence of a catalyst to
4338form nitrogen and water.
434231. State and federal PSD regulations require that Martin
4351Unit 8 meet all applicable emission limiting standards and that
4361Best Available Control Techno logy ("BACT") be applied in order to
4374control emissions. BACT is defined in Rule 62 - 210.200(38),
4384Florida Administrative Code, as:
4388An emission limitation, including a visible
4394emissions standard, based on the maximum
4400degree of reduction of each pollutant emi tted
4408which the Department [of Environmental
4413Protection], on a case by case basis, taking
4421into account energy, environmental and
4426economic impacts, and other costs, determines
4432is achievable through application of
4437production processes and available methods,
4442s ystems and techniques (including fuel
4448cleaning or treatment or innovative fuel
4454combustion techniques) for control of each
4460such pollutant.
4462The BACT requirements are intended to ensure that the air
4472emission control systems for Unit 8 reflect the latest in control
4483technologies used in the electric utility industry and take into
4493consideration existing and future air quality in the vicinity of
4503the Project. BACT review includes a cost - benefit analysis of
4514alternative control technologies capable of achieving a higher
4522degree of emission reduction than the proposed technology.
453032. In its PSD review, the Department preliminarily
4538determined that the air emissions control technologies proposed
4546for Martin Unit 8 are consistent with BACT as required under
4557federal an d state PSD regulations. The use of natural gas as the
4570primary fuel, with light oil as an alternate fuel for the CTs,
4582combined with advanced combustion control technology, will
4589provide the maximum degree of emission reduction for sulfur
4598dioxide, particula te matter, volatile organic compounds, carbon
4606monoxide, and sulfuric acid mist. The dry low NO x control
4617technology for the CTs and the duct burners, and water injection
4628when the CTs fire light oil, along with SCR in combined cycle
4640mode, reflect the latest available control technologies for
4648reducing NO x emissions from combined cycle systems. Combustion
4657controls also limit the formation of carbon monoxide and volatile
4667organic compounds. Cooling tower drift will be minimized through
4676use of high - efficiency d rift eliminators.
468433. The emission limits for Martin Unit 8 in the
4694Department's recommended Conditions of Certification are
4700identical to the emission limits proposed as BACT by the
4710Department. The recommended NO x emission limit of 2.5 parts per
4721million for combined cycle operation during natural gas - firing is
4732equal to or lower than BACT determinations for other combined
4742cycle units in the State of Florida.
4749Air Quality Impact Analysis
475334. Ambient air quality standards have been established by
4762the U.S. EPA and FDEP to protect public health and welfare. Air
4774quality in the vicinity of the Martin Plant currently meets all
4785federal and State ambient air quality standards. Martin County
4794is classified as an attainment area for all criteria pollutants,
4804and no area of Florida is currently designated as "nonattainment"
4814for any air pollutant.
481835. In its PSD review, the Department preliminarily
4826determined that air quality modeling demonstrates that Martin
4834Unit 8 will comply with all State and federal ambient ai r quality
4847standards, as well as PSD Class I and II increments. The air
4859quality modeling conducted for the Project followed EPA and FDEP
4869modeling guidelines. Two air quality models were utilized to
4878assess air quality impacts in the area surrounding the Ma rtin
4889Plant site. The modeling also assessed impacts in the nearest
4899PSD Class I area, which is the Everglades National Park, located
4910approximately 90 miles south of the Project site. Local
4919meteorological data from the National Weather Service was used in
4929the modeling. The modeling incorporated maximum air emissions
4937from the Unit 8 in both combined and simple cycle modes, using
4949light oil and natural gas, and at various operating modes, loads,
4960and ambient air temperatures which may affect the emission rates
4970and dispersion from the Unit. In its PSD review, the Department
4981preliminarily determined that the air quality modeling results
4989indicated that the maximum air impacts from the Project will
4999comply with all ambient air quality standards and PSD Class I and
5011II increments. While these analyses assumed a stack height of
5021125 feet, a stack height of up to 150 feet would generally result
5034in lower impacts, and would not change the conclusions as to the
5046Project's compliance with all air quality standards.
505336. EP A has established "Significant Impact Levels" for the
5063various pollutants that are subject to PSD review, and the
5073Department has adopted these Significant Impact Levels at Rule
508262 - 204.200(29), Florida Administrative Code. The comparison of a
5092projects air quality impacts with the Significant Impact Levels
5101represents an initial screening analysis to determine which
5109pollutants require a more detailed modeling analysis. In its PSD
5119review, the Department preliminarily determined that the
5126predicted impacts of t he emissions of all air pollutants from
5137Unit 8 are below the PSD Class I and Class II Significant Impact
5150Levels, except for SO 2 for the 24 - hour averaging period with the
5164CTs firing light oil. Accordingly, air quality impacts from Unit
51748 are considered ins ignificant based upon this screening analysis
5184for all pollutants except for SO 2 over the 24 - hour averaging
5197period.
519837. More refined, multi - source modeling was conducted to
5208assess the impacts of Unit 8's SO 2 emissions over the 24 - hour
5222averaging period. In its PSD review, the Department
5230preliminarily determined that this modeling demonstrated that SO 2
5239emissions from Unit 8, when considered along with other existing
5249and PSD sources, would be well below each of the relevant air
5261quality standards.
526338. Nit rogen oxides and volatile organic compounds are
5272precursors to the formation of ozone in the atmosphere.
5281Emissions of these air pollutants from Martin Unit 8 are
5291extremely small compared to regional emissions of NO x and VOCs.
5302In its PSD review, the Depart ment preliminarily determined that
5312the emissions from Unit 8 will not cause or contribute to any
5324violation of the ambient air quality standards for ozone.
533339. There are expected to be no air quality impacts from
5344associated industrial, commercial, or res idential growth due to
5353the Project or its location. In its PSD review, the Department
5364preliminarily determined that there should also be no adverse
5373impacts to the "Air Quality Related Values," including
5381visibility, soils, vegetation, or wildlife, in the c losest PSD
5391Class I area at the Everglades National Park. Unit 8's potential
5402impacts on regional haze in this Class I area were below the
5414screening level.
541640. In its PSD review, the Department preliminarily
5424determined that impacts from the proposed Unit 8 cooling tower
5434will be minimal. Potential cooling tower impacts on visibility
5443(fogging) and from deposition of drift emissions were evaluated
5452using accepted computerized modeling methodology and conservative
5459assumptions based on relevant design paramete rs for the proposed
5469cooling tower. Results of the evaluations demonstrated that
5477there would be only a very few hours per year in which fogging
5490induced by cooling tower operation will occur. When fogging does
5500occur, the impacts will remain on the Martin P lant site property.
5512Deposition from cooling tower drift will be minimized through the
5522use of high - efficiency drift eliminators. Impacts of cooling
5532tower deposition will be minimal inside the Project Area, and
5542will only occur within the Martin Plant site.
5550Water Uses and Sources
555441. Water uses for the Martin Unit 8 will include condenser
5565cooling, general plant service water, fire protection water, and
5574demineralized water. The largest water use for Unit 8 will be to
5586replace net evaporation from either the cooling pond or the
5596cooling tower due to cooling of the new Unit. Process water uses
5608will include demineralized water to be used in the combustion
5618turbine inlet foggers, for combustion turbine power augmentation,
5626for NO x control in the combustion turbines during light oil
5637firing, and for steam cycle makeup.
564342. Water for Unit 8 will be taken from the existing Martin
5655Plant cooling pond. Makeup to that pond is withdrawn from the
5666St. Lucie Canal, which ultimately connects to Lake Okeechobee.
5675Makeup water w ill be pumped into the cooling pond at an existing
5688intake structure at the southern end of the cooling pond. Water
5699will then be withdrawn from the pond for uses in the Martin Unit
57128.
571343. New cooling water system structures for Unit 8 will be
5724constructe d in the cooling pond. There will be no other
5735construction in surface waters at or near the Project Area.
574544. Cooling water from the pond will be circulated through
5755the Unit 8 condensers and auxiliary heat exchangers to remove
5765waste heat. This waste h eat is dissipated by the cooling pond,
5777primarily by evaporation, radiation and conduction to the
5785atmosphere. The cooled water is then recirculated through the
5794pond back to the units. The proposed Unit 8 will either utilize
5806the cooling pond in the same ma nner as the existing units or will
5820utilize a mechanical draft cooling tower instead. If a cooling
5830tower is constructed, it will dissipate the heat primarily by
5840evaporation and conduction to the atmosphere. Makeup water for
5849the cooling tower would be with drawn from the cooling pond and
5861blowdown from the new cooling tower will then be returned to the
5873cooling pond
587545. The cooling pond is approximately 6,800 acres, with
58856,500 acres being water surface and the balance in the
5896embankments. The existing Martin Plant cooling pond has been
5905sized, constructed, and previously approved to handle the thermal
5914load associated with additional generating capacity.
5920Mathematical modeling of the thermal performance of the cooling
5929pond was previously performed based on a wid e range of potential
5941heat loadings to the pond. Based upon that modeling, with the
5952expected operation of all of the generating units, including Unit
59628, there is adequate water available under the permitted amounts
5972to operate the existing units as well as Martin Unit 8. The
5984Project will not require an increase in the currently - authorized
5995withdrawal rates of water from the St. Lucie Canal or from
6006groundwater sources with or without the cooling tower. With the
6016addition of Martin Unit 8, the Plant will conti nue to be operated
6029within the thermal limits and constraints that were previously
6038reviewed and permitted.
604146. Potable water will be provided by the existing
6050permitted system and the potable water uses for Unit 8 will not
6062exceed the existing permitted qu antities. Domestic wastewater
6070generated by Unit 8 will be handled by the existing system.
608147. Water for process water needs will be withdrawn from
6091the cooling pond and pretreated and used as service water. The
6102service water system will also feed the existing reverse
6111osmosis/mixed bed demineralizer system which may be upgraded for
6120Unit 8 within the existing area occupied by that equipment.
6130Waste streams from the RO treatment system will be treated by
6141existing plant systems and recycled to the cooling pond.
615048. The design and operation of Martin Unit 8 will
6160incorporate a number of water conserving features. All of the
6170power block area contact stormwater will be recycled back to the
6181cooling pond, minimizing makeup requirements for cooling water.
6189All wastewaters will be treated and recycled to the cooling pond.
6200Use of the dry low NO x burners in the combustion turbines will
6213minimize water use when natural gas is fired. These features,
6223when combined with the existing water management features,
6231includi ng the toe drain recovery system and limited cooling pond
6242discharges, help minimize the use of both groundwater and surface
6252waters.
6253Wastewaters and Surface Water Discharges
625849. Unit 8 will utilize the existing Martin Plant's
6267wastewater treatment system. The only new wastewater generated
6275by Unit 8 will be HRSG blowdown and equipment area stormwater and
6287wash waters. HRSG blowdown will be quenched with service water
6297and recycled to the cooling pond. Equipment area stormwater and
6307wash waters will be passe d through an oil/water separator and
6318then recycled to the cooling pond.
632450. The cooling system for Martin Unit 8 requires either
6334chlorination or use of biocides to prevent biofouling of the heat
6345rejection system. A chlorine solution will be fed into th e
6356intake structure for the Unit 8 heat rejection system as
6366appropriate. If the cooling tower is installed, a scale
6375inhibitor will be fed into the circulating water system to
6385control the formation of calcium carbonate scales, which can
6394adhere to the heat t ransfer surfaces and impair cooling
6404performance. Sulfuric acid and a polymer will also be added as
6415necessary to the water treatment.
642051. Chemical treatment will also be required in the HRSG to
6431prevent corrosion and scaling of the condensate piping. Th e HRSG
6442boiler and piping will be chemically cleaned initially during
6451commissioning, and periodically during the life of the Unit.
6460These chemicals will not be permanently stored onsite but will be
6471delivered by a licensed contractor at the time of the sched uled
6483cleanings. Wastewaters from this cleaning will consist of the
6492cleaning solutions and the materials removed. Chemical
6499wastewaters can also result from draining of chemical storage
6508tanks or from cleaning and maintenance operations. These wastes
6517will be contained and treated locally or routed to the existing
6528neutralization system for treatment. These flows will be
6536intermittent and will not contribute to the overall wastewater
6545flows.
654652. Minimum and maximum water levels within the cooling
6555pond will remain within previously approved levels. Surface
6563water discharges from the pond will occur only during annual gate
6574tests and following extreme rainfalls. The spillway is
6582controlled by four sluice gates which allow water to discharge
6592automatically to pro tect the embankment from overtopping during
6601large rainfall events. The current operating scenario for the
6610cooling pond provides for approximately 6.33 feet of freeboard,
6619allowing the pond enough freeboard between the water level and
6629the top of the embankm ent to hold more than eight 100 - year
6643storms.
664453. Based upon previous modeling of the Martin cooling pond
6654and predicted makeup water volumes to the pond, the estimated
6664concentrations of dissolved constituents within the cooling pond
6672were calculated. Thi s modeling indicated that there would be no
6683exceedances of Class III surface water quality standards in the
6693cooling pond water. The water quality in the St. Lucie Canal,
6704which would receive any discharge from the cooling pond, will not
6715be affected by gate testing because there is an existing mixing
6726zone within the intake/discharge canal between the spillway and
6735the St. Lucie Canal. In order to limit the impact of a
6747discharge, the intake pumps for the cooling pond can be run
6758during gate tests to return spi llway releases to the cooling
6769pond. Prior to annual gate tests, the cooling pond water is
6780analyzed in accordance with the existing industrial wastewater
6788facility permits. If the test results indicate any constituent
6797in the pond would exceed 90 percent of the Class III surface
6809water criteria, FPL operates the makeup pumps to prevent any
6819exceedance of a water quality standard in the St. Lucie Canal by
6831pumping the discharge water back into the pond. Gate tests will
6842be performed in the same manner after addi tion of Unit 8.
685454. The St. Lucie Canal is a manmade canal excavated in the
68661910s and 1920s to regulate the water level of Lake Okeechobee.
6877The Canal extends approximately 30 miles from Lake Okeechobee to
6887the St. Lucie Inlet near Stuart. It has a dept h of approximately
6900eight feet and an average flow of 748 cubic feet per second. It
6913is controlled at both ends by locks, which regulate the discharge
6924from Lake Okeechobee and into the Atlantic Ocean. Vegetation
6933along and in the canal is dominated by emerg ent grasses and
6945exotic species, as well as saw palmetto, pine, cabbage palm, and
6956planted citrus. The canal is considered only marginal breeding
6965and spawning habitat for fish. The planned withdrawals to supply
6975Unit 8 will not contribute to the existing ef fects from
6986sedimentation, nutrient loading, and salinity fluctuations in the
6994canal.
6995Surface Water Management System
699955. The stormwater facilities to handle runoff from the
7008Martin Unit 8 Project area were designed and constructed with
7018Units 3 and 4. Th e surface water management system for the
7030Project has been designed to meet the requirements of the South
7041Florida Water Management District. The peak post - construction
7050runoff flow rate resulting from the design storm will not exceed
7061the pre - development pe ak flow rate. The Project drainage system
7073of catch basins, pipes, channels, and culverts will convey runoff
7083to the existing site drainage system of channels and ponds. Non -
7095contact surface runoff from the area disturbed for Project
7104construction and operat ion of Unit 8 will be collected and routed
7116to two existing permanent ponds. Existing drainage patterns will
7125be maintained, ensuring proper function of the stormwater system.
7134An existing, temporary construction stormwater pond will be
7142utilized during cons truction to prevent sediment transmission
7150offsite until construction of Unit 8 is complete. Prior to
7160beginning any earth disturbing activities, a silt fence will be
7170installed along the perimeter of the Project where runoff to
7180offsite areas is expected. T emporary erosion and sedimentation
7189control measures will be designed to prevent sediment from being
7199displaced and carried offsite by construction runoff. All
7207temporary sediment and erosion control measures will be removed
7216at the end of construction.
7221Gro undwater Impacts
722456. The only groundwater withdrawals associated with the
7232operation of Martin Unit 8 will be the withdrawal of groundwater
7243for the potable water system. The withdrawal will be within the
7254existing permitted allocations of groundwater. The only known
7262potable water wells within one mile of the Site are those
7273operated by FPL.
727657. The existing Martin Plant cooling pond is the principal
7286source of potential impacts to groundwater at the Plant. Seepage
7296leaves the pond beneath the western and southern edges of the
7307cooling pond and moves toward the surrounding canals where it
7317reenters the surface water regime. A significant majority of the
7327seepage will be intercepted by the toe drains and returned to the
7339cooling pond, and no significant impacts to groundwater quality
7348are expected. The Project is expected to meet applicable
7357groundwater standards. Pursuant to FDEP Rule 62 - 520.520(8),
7366Florida Administrative Code, the Martin Plant cooling pond is
7375exempt from secondary groundwater standards. Furth er, there is
7384an existing zone of discharge for groundwater that extends to
7394FPLs property line. Monitoring of constituents in the cooling
7403pond which have groundwater standards is included in the existing
7413conditions of certification for the Martin certifie d site in
7423order to meet the requirements for groundwater monitoring for
7432this exemption.
7434Noise Impacts of Construction and Operation
744058. A noise impact assessment was conducted for
7448construction and operation of Martin Unit 8. Background noise
7457levels wer e determined from a noise monitoring program performed
7467at several locations in the vicinity of the Project. These
7477background levels were then combined with noise levels expected
7486from construction and operation of Martin Unit 8. The modeling
7496assumed that all construction equipment would be operating
7504simultaneously and consistently, and therefore the impact
7511assessment is conservative. When the construction noise impacts
7519are combined with the background noise levels, the predicted
7528noise impacts are all less than the noise levels set in the
7540Martin County Noise Control Ordinance. The actual or measured
7549noise levels due to construction are expected to be lower than
7560the predicted levels. A similar analysis was performed to
7569predict maximum noise levels produced by operation of the new
7579unit, along with background noise levels. Predicted noise levels
7588during operation at the nearest residential receptors to the
7597Project are well below the maximum permissible noise levels under
7607the Martin County Noise Ordinance.
7612T ransmission Line
761559. The Martin Unit 8 Project will connect to the existing
7626FPL transmission network at the FPL Martin system substation
7635within the previously certified site. Two new transmission lines
7644will be constructed to integrate the new generation into the
7654transmission network in order to meet the single contingency
7663planning criteria adopted by the National Electric Reliability
7671Council. A new 230 kilovolt ("kV") transmission line will be
7683constructed between the Martin Plant and the existing FPL
7692Ind iantown Substation located east of Indiantown. This new line
7702will be located partly in existing transmission line right - of - way
7715and partly in new transmission line right - of - way. A second 230
7729kV line will be constructed between the existing FPL Indiantown
7739Substation and the existing FPL Bridge Substation further to the
7749east, to be located entirely within an existing FPL transmission
7759line right - of - way. FPL is proposing certification only for the
7772portion of the transmission line from the Martin Plant to the
7783Indiantown Substation that will be constructed on entirely new
7792transmission line right - of - way. The other portions of the
7804transmission lines will be permitted separately.
781060. The proposed transmission line route was selected after
7819evaluation of a number of alternative routes. Other routes,
7828including other existing transmission line rights - of - way, that
7839were evaluated were found to be infeasible or undesirable because
7849of a lack either of access to, or of additional land within
7861existing right - of - ways, addi tional crossings of more land
7873parcels, or increased clearing and potential wetlands impacts
7881when compared to the selected route. The selected route also
7891allows extensive use of existing transmission line rights - of - way
7903and, within the new transmission line corridor, co - location of
7914the new line with existing roads and with existing overhead
7924utilities along a primarily undeveloped strip.
793061. The new transmission line corridor proposed for
7938certification is approximately 8.5 miles long. It will parallel
7947S.R . 76 and C.R. 726, which are adjacent to the St. Lucie Canal.
7961The width of the corridor along S.R. 76 and C.R. 726 will vary.
7974The final average right - of - way to be selected in that corridor
7988will be less than 25 feet wide. The new transmission line
7999struct ures will be single pole concrete structures, with post
8009insulators in a vertical configuration. The typical pole will be
8019about 90 to 100 feet above grade, and higher where necessary for
8031longer spans and for crossing over elevated roads, other overhead
8041uti lities, and waterways. Where the transmission line parallels
8050existing FPL electrical distribution lines, the distribution
8057lines will be co - located on the transmission structures where
8068transmission structures are able to replace the distribution
8076poles. Sp an lengths for the new line will range from 250 to 700
8090feet with a typical span of 500 feet. The span lengths vary to
8103allow avoidance of wetlands and other environmentally sensitive
8111features, or to coincide with property lines or existing
8120distribution pol es. Access is expected to be provided using
8130existing public roads that parallel much of the new transmission
8140line right - of - way. However, small sections of the line may
8153require construction of access roads for construction and
8161maintenance purposes. Acces s roads will be unpaved and can be
8172constructed above natural grade, using clean, compacted fill.
818062. The certified segment of the transmission line will
8189cross lands that are used for agricultural uses; isolated parcels
8199of cabbage palm, Brazilian pepper, live oak, and pine; and
8209infrequent residential properties. Land uses in this area are
8218primarily citrus groves, pastures, undeveloped land, scattered
8225residences, and commercial buildings along the highway.
823263. The only significant surface water body to be crossed
8242by the certified transmission line is the St. Lucie Canal, which
8253will be crossed once within the certified segment of the right -
8265of - way. No significant environmental features are located within
8275the proposed corridor to be certified. Only one p rotected
8285species, the American alligator (a species of special concern),
8294was observed along the 8.5 mile segment of the proposed
8304transmission line corridor. This occurred in a drainage ditch
8313outside of the proposed corridor itself. The new structures are
8323designed and located to minimize impacts to wetlands and the use
8334of a single pole will reduce the fill required for pole pads.
8346The transmission line corridor does not contain critical habitat
8355for any flora or fauna of the region. There are no known scen ic,
8369archaeological, or historic sites within the proposed
8376transmission line corridor
837964. Construction of the new certified segment of the
8388transmission line will initially involve surveying and locating
8396property lines to stake out the limits of the right - o f - way, the
8412location of new roads, and the pole placement sites. The right -
8424of - way is then prepared through removal of all vegetation that
8436will conflict with construction and operation of the transmission
8445line alongside roadways. This will mostly entail tr imming trees
8455and removing conflict trees that could fall into the line itself.
8466Access roads will also be constructed where needed and culverts
8476will be included to maintain existing flow conditions. Wetlands
8485impacts will be minimized through pole placemen t and clearing
8495practices. Unavoidable wetlands impacts will be addressed
8502through a post - certification process. The next step involves
8512erection of the structures which are directly embedded into the
8522ground. Insulators, hardware, and overhead wires are th en
8531installed. The final step involves final cleanup of the right -
8542of - way after construction is complete. Construction and
8551operation of the transmission line will be in compliance with
8561applicable agency standards, including the National Electrical
8568Safety C ode, the Florida Department of Transportation Utility
8577Accommodation Guide, the Martin County Noise Ordinance, and the
8586FDEP's rules setting limits for electric and magnetic fields.
8595Socioeconomic Impacts and Benefits
859965. The Martin Unit 8 Project Area is an appropriate site
8610for the proposed new Unit 8. The Project consists of the
8621installation of a new combined cycle unit at an existing power
8632plant site that has been in use for that purpose since 1980. The
8645Project area is significantly buffered from the p erimeter of the
8656FPL - owned property and nearby residential uses. The vast
8666majority of land use in the vicinity is in agricultural use or
8678undeveloped land. The nearest residence is located just less
8687than two miles south - southeast of the Project Area. Over all, the
8700Project is located in a rural area.
870766. The Martin Unit 8 Project will benefit the economy of
8718Martin County and surrounding communities. Direct benefits from
8726the Project include employment opportunities created by
8733construction and operation. The Projects direct effects on
8741socioeconomic conditions will be substantially positive.
8747Construction employment will average 250 new jobs during the two
8757year construction period. It is expected that these jobs will
8767result in direct wages of approximatel y $75 million over the two
8779year period. Due to the proximity of the Martin Plant site to
8791large labor markets in the south Florida area, the labor demand
8802for both construction and operation is expected to be met by
8813workers in these areas. Population and h ousing impacts will
8823therefore be minimal because little migration into the area is
8833anticipated as a result of the Project. Direct economic benefits
8843of construction of the Project will also result from purchases of
8854materials and equipment, estimated to be $15 to $20 million
8864within the State. It is expected that the majority of the
8875construction wages will be spent within Martin County and the
8885surrounding regions, which will create additional demands for
8893goods and services. This will create a multiplier eff ect
8903generating additional jobs and earnings.
890867. The operation of Martin Unit 8 will add approximately
891812 new full - time employees at the FPL Martin Site. The
8930additional annual payroll for these employees is estimated to be
8940$600,000. This payroll amoun t is expected to generate an
8951additional $500,000 in wages and benefits to other businesses in
8962the region. Other fixed annual operational costs for Unit 8 will
8973be expended in the region at an estimated amount of $2 million
8985per year.
898768. Property tax pay ments to Martin County resulting from
8997Martin Unit 8 during operation are estimated to be $6.7 million
9008in 2006. Based on the first five years of operation, estimated
9019local tax payments are expected to be $31.4 million for general
9030government and public scho ols in Martin County, and $900,000 in
9042sales tax paid to the State of Florida. The Projects external
9053cost impacts are expected to be minimal and localized. The
9063Project is not expected to result in any significant impact to
9074local government services.
907769 . The entire Martin Project Area, which includes the Unit
90888 Project Area, was previously determined to be consistent with
9098the State, regional, and local comprehensive plans.
9105Additionally, the Martin Unit 8 Project, including its associated
9114transmission line, is consistent with the Martin County
9122Comprehensive Plan, the State Comprehensive Plan, and the
9130Strategic Regional Policy Plan of the Treasure Coast Regional
9139Planning Council. The Project will also comply with the
9148applicable development standards in the Martin County Land
9156Development Regulations.
915870. Construction and operation of Martin Unit 8 will not
9168adversely affect any nearby landmarks, sensitive areas,
9175recreational areas, archaeological sites, or historical sites.
9182The nearest recreational fac ility is approximately six miles
9191southeast of the Project. The nearest environmentally protected
9199land is the Barley Barber Swamp located on the west side of the
9212cooling pond, which is maintained under FPLs stewardship as a
9222nature preserve. If archaeolog ical materials are discovered
9230during Project construction or operation, activities would cease.
9238State review of the find would be required before the Project
9249could proceed in the affected area.
925571. Temporary external costs resulting from the Project
9263duri ng construction include the generation of construction
9271traffic. A transportation analysis of the Project indicated that
9280traffic resulting from construction of the Project would not
9289degrade traffic flow on State Road 710 below established levels
9299of service . FPL has already implemented roadway improvements at
9309the Martin Plant entrance and State Road 710, including an
9319extended left - hand turn lane and a south - bound acceleration lane.
9332Thus, no additional roadway improvements are required for
9340construction traf fic. Operation of Martin Unit 8 will add only
935112 new employees at the Martin Plant Site. The Project will also
9363generate truck traffic for delivery of materials for operation
9372and maintenance of the Unit. However, the traffic resulting from
9382operation of U nit 8 will not degrade traffic volumes below
9393established levels of service.
9397Public Comment
939972. Three members of the public provided testimony during
9408the certification hearing. They generally expressed their
9415appreciation for the manner in which FPL has interacted with the
9426community and supported various community activities. No one
9434spoke in opposition to the Project. One member of the public
9445questioned the need for another transmission line.
9452Agency Positions and Stipulations
945673. The FDEP, the Florida Department of Community Affairs,
9465the Florida Department of Transportation, the Florida Fish and
9474Wildlife Conservation Commission, the South Florida Water
9481Management District, the Treasure Coast Regional Planning
9488Council, and Martin Co unty each prepared written reports on the
9499Project. Each of these agencies either recommended approval of
9508Martin Unit 8 or otherwise did not object to certification of the
9520proposed power plant. FDEP has proposed a series of Conditions
9530of Certification for the Project that incorporate the
9538recommendations of the various reviewing agencies. FPL states
9546that it is prepared to accept and can comply with these
9557Conditions of Certification in the design, construction, and
9565operation of Martin Unit 8. The Florida D epartment of Community
9576Affairs stipulated that the Project would not conflict with the
9586State Comprehensive Plan. The Treasure Coast Regional Planning
9594Council stated in its agency report that the Project would not
9605conflict with its Strategic Regional Polic y Plan. Martin County
9615reported that the Project would be consistent with the Countys
9625comprehensive plan and land development code. No state,
9633regional, or local agency has recommended denial of certification
9642of the Project or has otherwise objected to ce rtification of the
9654Project.
9655CONCLUSIONS OF LAW
965874. The Division of Administrative Hearings has
9665jurisdiction over the parties to, and the subject matter of, this
9676proceeding. This proceeding has been conducted in accordance
9684with the Florida Electrical Powe r Plant Siting Act, Chapter 403,
9695Part II, Florida Statutes, and Chapter 62 - 17, Part I, Florida
9707Administrative Code, which set out the procedures for power plant
9717siting reviews.
971975. In accordance with Chapters 120 and 403, Florida
9728Statutes, and Chapter 6 2 - 17, Florida Administrative Code, proper
9739notice was accorded to all persons, entities, and parties
9748entitled to such notice, and appropriate notice was provided to
9758the general public by both the Department and FPL. All necessary
9769and required governmental agencies participated, and the general
9777public had the opportunity to fully participate, in the
9786certification process. Reports and studies were issued by FDEP,
9795the Department of Community Affairs, the Florida Department of
9804Transportation, the Florida Fish and Wildlife Conservation
9811Commission, the South Florida Water Management District, the
9819Treasure Coast Regional Planning Council, and Martin County in
9828accordance with their various statutory duties under the PPSA.
983776. The Florida Public Service Commissio n has issued its
9847determination that a need exists for the electrical generating
9856facility and the electricity it will produce, in accord with
9866Section 403.519, Florida Statutes.
987077. By its own terms, the PPSA "shall not apply" to
9881electrical power plants for which applications for permits were
9890made prior to 1973. Section 403.506(1), Florida Statutes;
9898Chapter 73 - 33, Laws of Florida. FPL applied for permits for
9910Martin Units 1 and 2 prior to 1973, and thus the PPSA does not
9924apply to those existing units. FPL has not in this proceeding
9935sought to invoke the jurisdiction of the PPSA with respect to
9946existing Martin Units 1 and 2, nor has FPL elected to apply for
9959certification of Units 1 and 2 under the optional PPSA provision
9970for certification of existing electric al power plants codified at
9980Section 403.5175, Florida Statutes.
998478. Competent, substantial evidence and testimony produced
9991at the certification hearing demonstrates that FPL has met its
10001burden of proof to demonstrate that the Martin Unit 8 Project,
10012includ ing the proposed transmission line corridor, meets the
10021criteria for certification under the PPSA. Unrebutted testimony
10029and other evidence produced at the hearing demonstrates that the
10039safeguards for construction and operation of the Martin Unit 8
10049Project are technically sufficient to protect the public welfare
10058of the citizens of Florida and are otherwise reasonable and
10068available methods to achieve that protection of the public. The
10078Martin Unit 8 Project will result in minimal adverse effects on
10089human heal th, the environment, the ecology of the land and its
10101wildlife, and the ecology of state waters and their aquatic life.
10112In addition, the Project will not conflict with the state
10122comprehensive plan or the local comprehensive plan for Martin
10131County, Florida. If operated and maintained in accordance with
10140this Recommended Order and the FDEP's proposed Conditions of
10149Certification, the Martin Unit 8 Project will comply with the
10159applicable nonprocedural requirements of all agencies.
10165Furthermore, certification of the Project, including the
10172associated transmission line facility, will fully balance the
10180increasing demand for electrical power plant location and
10188operation in this State with the broad interests of the public
10199that are protected by the PPSA.
10205RECOMMENDATIO N
10207Based upon the foregoing Findings of Fact and Conclusions of
10217Law, it is
10220RECOMMENDED that the Siting Board grant full and final
10229certification to Florida Power & Light Company, under Section
10238403, Part II, Florida Statutes, for the location, construction,
10247a nd operation of the Martin Unit 8 Project, representing a 1100
10259MW combined cycle unit, and including an associated transmission
10268line as described in the Site Certification Application and the
10278evidence presented at the certification hearing, and subject to
10287the Conditions of Certification contained in FDEP Exhibit 2 and
10297incorporated herein by reference.
10301DONE AND ENTERED this 5th day of March, 2003, in
10311Tallahassee, Leon County, Florida.
10315___________________________________
10316CHARLES A. STAMPELOS
10319Administrative Law Judge
10322Division of Administrative Hearings
10326The DeSoto Building
103291230 Apalachee Parkway
10332Tallahassee, Flo rida 32399 - 3060
10338(850) 488 - 9675 SUNCOM 278 - 9675
10346Fax Filing (850) 921 - 6847
10352www.doah.state.fl.us
10353Filed with the Clerk of the
10359Division of Administrative Hearings
10363this 5th day of March, 2003.
10369COPIES FURNISHED:
10371Peter C. Cunningham, Esquire
10375Douglas S. Roberts, Esquire
10379Hopping Green & Sams, P.A.
10384Post Office Box 6526
10388Tallahassee, Florida 32314
10391Scott A. Goorland, Esquire
10395Senior Assistant General Couns el
10400Department of Environmental Protection
104043900 Commonwealth Blvd., Mail Station 35
10410Tallahassee, Florida 32399 - 3000
10415Krista Storey, Esquire
10418Tyson Waters, Esquire
10421Martin County Attorney's Office
104252401 Southeast Monterey Road
10429Stuart, Florida 34996
10432Ross Staf ford Burnaman, Esquire
10437Fish and Wildlife Conservation Commission
10442620 South Meridian Street
10446Tallahassee, Florida 32399 - 1600
10451Sheauching Yu, Esquire
10454Department of Transportation
10457Haydon Burns Building
10460605 Suwannee Street, Mail Station 58
10466Tallahassee, Florida 32399 - 0450
10471Colin Roopnarine, Esquire
10474Assistant General Counsel
10477Department of Community Affairs
104812555 Shumard Oak Boulevard
10485Tallahassee, Florida 32399 - 2100
10490Robert V. Elias, Esquire
10494Florida Public Service Commission
10498Gerald Gunter Building
105012450 Shumard O ak Boulevard
10506Tallahassee, Florida 32399 - 0850
10511Roger Saberson, Esquire
10514Treasure Coast Regional Planning Council
1051970 Southeast Fourth Avenue
10523Delray Beach, Florida 33483 - 4514
10529Susan Roeder Martin, Esquire
10533Assistant General Counsel
10536South Florida Water Managem ent District
10542Post Office Box 24680
10546West Palm Beach, Florida 33416
10551David B. Struhs, Secretary
10555Department of Environmental Protection
105593900 Commonwealth Boulevard
10562Tallahassee, Florida 32399 - 3000
10567Teri L. Donaldson, General Counsel
10572Department of Environment al Protection
105773900 Commonwealth Boulevard, Mail Station 35
10583Tallahassee, Florida 32399 - 3000
10588Kathy C. Carter, Agency Clerk
10593Office of the General Counsel
10598Department of Environmental Protection
106023900 Commonwealth Boulevard, Mail Station 35
10608Tallahassee, Florid a 32399 - 3000
10614NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
10620All parties have the right to submit written exceptions within 15
10631days from the date of this Recommended Order. Any exceptions to
10642this Recommended Order should be filed with the agency that will
10653issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/19/2004
- Proceedings: Letter to H. Oven from B. Linkiewicz regarding FDEP intent to modify conditions of certification for its Martin Power Plant filed.
- PDF:
- Date: 03/10/2003
- Proceedings: Waiver of Time Frames for Filing Exceptions (filed by S. Martin via facsimile).
- PDF:
- Date: 03/05/2003
- Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
- PDF:
- Date: 03/05/2003
- Proceedings: Recommended Order issued (hearing held February 17, 2003) CASE CLOSED.
- PDF:
- Date: 03/03/2003
- Proceedings: Letter to Judge Stampelos from P. Cunningham submitting the record of the certification hearing for the FPL Maritn project filed.
- PDF:
- Date: 02/28/2003
- Proceedings: Notice of Filing Late Signature Page to Joint Proposed Recommended Order filed by D. Roberts.
- Date: 02/21/2003
- Proceedings: Transcript of Proceedings filed.
- PDF:
- Date: 02/12/2003
- Proceedings: Notice of Filing Prepared Direct Testimony and Exhibits filed by D. Roberts.
- PDF:
- Date: 01/31/2003
- Proceedings: Notice of Filing Certified Proof of Publication for Notices of Certification Hearing for a Power Plant Siting Application ot be Located in Martin County, Florida filed by P. Cummingham.
- PDF:
- Date: 01/10/2003
- Proceedings: List of Witnesses for Certification Hearing (filed by S. Goorland via facsimile).
- PDF:
- Date: 01/03/2003
- Proceedings: Corrected Department of Transportation`s Witness List (filed via facsimile).
- Date: 12/20/2002
- Proceedings: DEP`s Power Plant Site Certification Review for Florida Power & Light Martin Expansion Project Unit 8 filed.
- PDF:
- Date: 08/19/2002
- Proceedings: Notice of Hearing issued (hearing set for February 17 through 21, 2003; 1:00 p.m.; Indiantown, FL).
- PDF:
- Date: 07/29/2002
- Proceedings: Order issued. (certification hearing scheduled for November 18-22, 2002, is cancelled and will be re-set for February 17-21, 2003, at a site to be announced)
- PDF:
- Date: 07/16/2002
- Proceedings: Stipulation and Joint Motion for Alteration of Time Limits filed.
- PDF:
- Date: 06/10/2002
- Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
- PDF:
- Date: 06/03/2002
- Proceedings: Notice of Filing Joint Proposed Recommended Order on Land Use Hearing filed.
- PDF:
- Date: 06/03/2002
- Proceedings: Letter to Judge Stampelos enclosing a disk of the joint PRO filed.
- PDF:
- Date: 05/22/2002
- Proceedings: Florida Power & Light Co. and Department of Enviromental Protection`s Joint Notice of Filing Late Exhibit filed.
- PDF:
- Date: 05/06/2002
- Proceedings: Florida Power & Light Co.`s Notice of Filing Responses to Notice of Insufficiency of the Department of Enviromental Protection filed.
- Date: 05/01/2002
- Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
- PDF:
- Date: 04/29/2002
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing Application for Site Certification for a Power Plant to be Located in Martin County, Florida filed.
- PDF:
- Date: 04/29/2002
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Land Use Hearing for a Power Plant Siting Application to be Located in Martin County, Florida filed.
- PDF:
- Date: 04/16/2002
- Proceedings: Florida Power & Light Co`s Response to Florida Department of Environmental Protection`s Notice of Insufficiency filed.
- PDF:
- Date: 03/20/2002
- Proceedings: Notice of Substitution of Counsel (filed by S. Martin via facsimile).
- PDF:
- Date: 03/18/2002
- Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
- PDF:
- Date: 03/12/2002
- Proceedings: Joint Stipulation and Motion for Alteration of Time Limit (filed via facsimile).
- PDF:
- Date: 03/11/2002
- Proceedings: Notice of Hearing sent out. (November 18-22, 2002, 9:00 a.m., Indiantown, Florida).
- PDF:
- Date: 03/11/2002
- Proceedings: Notice of Hearing issued (hearing set for May 1, 2002; 9:00 a.m.; Indiantown, FL).
- PDF:
- Date: 03/08/2002
- Proceedings: Letter to Judge Johnston from D. Roberts regarding venue of hearing filed.
- PDF:
- Date: 02/28/2002
- Proceedings: Notice of Intent to be a Party (filed by R. Burnaman via facsimile).
- PDF:
- Date: 02/25/2002
- Proceedings: Department of Environmental Protection`s Correction to Proposed Site Certification Application Schedule (filed via facsimile).
- PDF:
- Date: 02/25/2002
- Proceedings: Department of Environmental Protection`s Proposed Site Certification Applications Schedule (filed via facsimile).
Case Information
- Judge:
- CHARLES A. STAMPELOS
- Date Filed:
- 02/08/2002
- Date Assignment:
- 04/24/2002
- Last Docket Entry:
- 07/27/2004
- Location:
- Indiantown, Florida
- District:
- Southern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- EPP
Counsels
-
Ross Stafford Burnaman, Esquire
Address of Record -
Peter C Cunningham, Esquire
Address of Record -
Robert V Elias, Esquire
Address of Record -
Scott A Goorland, Esquire
Address of Record -
Susan Roeder Martin, Esquire
Address of Record -
Hamilton S Oven
Address of Record -
Colin M. Roopnarine, Esquire
Address of Record -
Roger G Saberson, Esquire
Address of Record -
Tyson Waters, Esquire
Address of Record -
Sheauching Yu, Esquire
Address of Record -
Scott A. Goorland, Esquire
Address of Record -
Roger G. Saberson, Esquire
Address of Record