02-000573EPP In Re: Florida Power And Light Martin Unit 8 Power Plant Siting Application No. Pa89-27a vs. *
 Status: Closed
Recommended Order on Wednesday, March 5, 2003.


View Dockets  
Summary: Florida Power & Light showed compliance with existing land use plan and zoning ordinances pursuant to Section 403.508(2), Florida Statutes. Certification justified pursuant to Section 403.501 et. seq., F.S. under the Electrical Power Plant Siting Act.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: FLORIDA POWER & LIGHT )

15COMPANY MARTIN UNIT 8 )

20POWER PLANT SITING )

24APPLICATION NO. PA89 - 27A. ) Case No. 02 - 0573EPP

35____________________________________)

36RECOMMEND ED ORDER

39Pursuant to notice, the Division of Administrative Hearings,

47by its duly designated Administrative Law Judge, Charles A.

56Stampelos, held a certification hearing in the above - styled case

67on February 17, 2003, in Indiantown, Florida.

74APPEARANCES

75For Florida Power & Light Company:

81Peter C. Cunningham, Esquire

85Douglas S. Roberts, Esquire

89Hopping Green & Sams

93Post Office Box 6526

97Tallahassee, Florida 32314

100For the Department of Environmental Protecti on:

107Scott A. Goorland, Esquire

111Department of Environmental Protection

1153900 Commonwealth Boulevard

118The Douglas Building, Mail Station 35

124Tallahassee, Florida 32399 - 3000

129For Martin County:

132Krista Storey, Esquire

135Martin County

1372401 Southeast Monterey Road

141Stuart, Florida 34996 - 3322

146STATEMENT OF THE ISSUE

150The issue to be resolved in this proceeding is whether the

161Governor and Cabinet, sitting as the Siting Board, should issue

171certification to Flor ida Power & Light Company ("FPL"), to

183construct and operate a combined cycle generating unit, providing

192an additional 800 megawatts, at FPL's existing Martin Plant site

202in Martin County, Florida, and an associated 8.5 mile

211transmission line in accordance w ith the Florida Electrical Power

221Plant Siting Act, Section 403.501, et seq. , Florida Statutes.

230PRELIMINARY STATEMENT

232This proceeding was conducted pursuant to the Florida

240Electrical Power Plant Siting Act ("PPSA"), Chapter 403, Part II,

252Florida Statutes, and Chapter 62 - 17, Florida Administrative Code,

262to consider FPL’s application for site certification for the

271proposed Martin Unit 8 Project (also referred to as the

"281Project").

283On February 1, 2002, FPL filed its application for site

293certification for the Martin Unit 8 Project with the Florida

303Department of Environmental Protection ("Department" or "FDEP").

312The application was found to be complete on February 18, 2002.

323The application was found to be sufficient on June 5, 2002.

334As required by Section 403 .508(1) and (2), Florida Statutes,

344a land use hearing on the Project was held in the community of

357Indiantown, Florida, on May 1, 2002. By Final Order, dated

367August 13, 2002, the Siting Board adopted the undersigned’s

376Recommended Land Use Order, holding th at the site of the proposed

388Martin Unit 8 Project is consistent and in compliance with the

399land use plans and zoning ordinances of Martin County, Florida.

409On December 10, 2002, the Florida Public Service Commission

418("PSC") issued its Final Order determin ing the need for Martin

431Unit 8, pursuant to Section 403.519, Florida Statutes.

439On December 20, 2002, the FDEP issued its written Staff

449Analysis Report concerning the Project, as required by Section

458403.507(4), Florida Statutes. That Report contained rep orts from

467other state, regional, and local agencies and a compiled set of

478proposed Conditions of Certification for the Martin Unit 8

487Project, as proposed by FDEP and the various agencies which had

498reviewed the Project.

501On February 10, 2003, a J oint P rehear ing S tipulation was

514submitted to the undersigned, which indicated that no party to

524this proceeding objected to certification of the Project.

532On February 17, 2003, during the certification hearing, FDEP

541submitted its revised Staff Analysis Report as an exhi bit (FDEP

552Exhibit 2) to update and correct various matters in the earlier

563version of its analysis, and to revise the proposed Conditions of

574Certification.

575After proper public notice by both FPL and FDEP, a

585certification hearing was held in Indiantown, Fl orida, on

594February 17, 2003, as required by Section 403.508(3), Florida

603Statutes. The purpose of the certification hearing was to

612receive oral, written, and documentary evidence concerning

619whether, through available and reasonable methods, the location,

627c onstruction, and operation of the proposed Martin Unit 8 Project

638will produce minimal adverse effects on human health, the

647environment, the ecology of the land and its wildlife, and the

658ecology of State waters and their aquatic life, in an effort to

670fully balance the increase in demand for an electrical power

680plant location and operation with the broad interests of the

690public. See Section 403.502, Florida Statutes. The hearing

698would have also considered any petitions challenging the separate

707FDEP - issued p revention of significant deterioration ("PSD")

718permit for the Project. However, no such petition was filed.

728Prefiled written direct testimony and exhibits of seven FPL

737witnesses were filed with the Division of Administrative Hearings

746on February 12, 2003. That testimony was filed pursuant to Rule

75762 - 17.141(3), Florida Administrative Code. At the certification

766hearing, FPL presented summary testimony and exhibits of three of

776those witnesses, affirming their prefiled testimony and exhibits

784and summarizing portions of their testimony. The prefiled

792written testimony and exhibits of four witnesses have been

801accepted based upon execution of affidavits from those witnesses

810not attending the hearing, attesting to the accuracy of the

820testimony and accompanying ex hibits. FPL exhibits numbered 1

829through 8 were introduced and admitted into evidence. FDEP

838presented the testimony of Hamilton S. Oven, Jr., P.E., of the

849FDEP's Siting Coordination Office, and FDEP Exhibits 1 and 2 were

860admitted into evidence. Martin Co unty also attended the

869certification hearing. Martin County's Agency Report was

876accepted into evidence as part of the FDEP's Staff Analysis

886Report. The Florida Public Service Commission, the Florida

894Department of Community Affairs, the Florida Fish and W ildlife

904Conservation Commission, the Florida Department of

910Transportation, and the South Florida Water Management District

918(SFWMD), all of which were parties to this proceeding, did not

929enter appearances at the certification hearing. However, those

937agenci es joined in the prehearing stipulation. The agency

946reports from these five agencies and from the Treasure Coast

956Regional Planning Council were accepted into evidence as part of

966the FDEP's Staff Analysis Report. At the conclusion of the

976hearing, members of the general public were allowed to offer

986testimony on the Project.

990Following the conclusion of the February 17, 2003, hearing,

999a transcript of the hearing was filed on February 21, 2003. The

1011Joint Proposed Order of FPL, FDEP, SFWMD, and Martin County w as

1023timely submitted and has been considered in the rendition of this

1034Recommended Order.

1036FINDINGS OF FACT

1039Background

10401. Florida Power & Light Co. ("FPL") is the largest

1052electric utility in Florida, currently serving approximately

1059seven million customers i n its 34 - county service area. That

1071service area extends south from the northern Florida border along

1081the east coast of the State, and includes all of the southern

1093portion of the Florida peninsula. FPL currently operates 34

1102generating units at 14 location s in Florida, including the Martin

1113Plant. FPL has been supplying electricity in Florida since 1926.

11232. FPL's Martin Plant site is located in the western

1133portion of Martin County, Florida, approximately seven miles

1141northwest of the community of Indiantow n, Florida. The Martin

1151Plant is located in the unincorporated area of Martin County.

1161Access is by State Road 710, which runs northwest/southeast along

1171the northeast boundary of the Martin Plant site.

11793. The Martin Plant site contains approximately 11, 300

1188acres. The existing Martin Plant includes two 800 megawatt

1197(nominal) steam - electric generating units known as Units 1 and 2,

1209two 450 megawatt (nominal) combined cycle generating units known

1218as Units 3 and 4, and two 170 megawatt (nominal) simple cycle

1230combustion turbines known as Units 8A and 8B. FPL applied for

1241permits for Martin Units 1 and 2 prior to 1973. Martin Units 1

1254and 2, which use residual fuel oil and natural gas, began

1265commercial operation in 1980 and 1981, respectively. Martin

1273Units 3 a nd 4, which use natural gas and are permitted to burn

1287distillate or "light" oil, were certified under the PPSA in 1991

1298and began operation in 1994. Units 8A and 8B, which use natural

1310gas and light oil, were approved through modification of the

1320original si te certification in 2000, and began operation in 2001.

1331Units 1 and 2, 3 and 4, 8A and 8B, and associated facilities,

1344occupy approximately 400 acres of the Martin Plant site.

13534. The Martin Plant site has long been identified for

1363additional generating ca pacity. When site certification for

1371Units 3 and 4 was issued, the Siting Board also recognized the

1383Martin Plant site’s suitability for further capacity expansion

1391through its "ultimate site capacity" approval for the three - phase

1402Martin Coal Gasification/Co mbined Cycle (CG/CC) Project. That

1410Project contemplated, following construction of Units 3 and 4,

1419two additional phases involving combined cycle Units 5 and 6,

1429with supporting coal gasification facilities, and then

1436construction of a coal gasification faci lity to support Units 3

1447and 4. FPL has not as yet chosen to proceed with the latter two

1461phases of that Project. The portion of the Martin Plant site

1472certified under the PPSA comprises 2,192 acres. Neither FPL, nor

1483any other party, has invoked, or sought to invoke, the

1493jurisdiction of the PPSA with respect to Martin Units 1 and 2.

1505The Martin Plant site has continued to be identified as a

1516preferred location for additional generating capacity in each of

1525FPL's Ten Year Power Plant Site Plans for the past de cade.

1537Existing Units 1, 2, 3, and 4 will remain in operation and will

1550not be affected by the Project.

15565. The Martin Plant site contains a 6,800 acre cooling

1567pond (6,500 acres of water surface and 300 acres of embankment),

1579which provides cooling water t o the four existing steam electric

1590generating units at the site. Makeup water for the cooling pond

1601is withdrawn from the St. Lucie Canal, under a Permit Agreement

1612between FPL and SFWMD. Withdrawals from the St. Lucie Canal have

1623occurred since 1978. Make up water from the St. Lucie Canal is

1635currently withdrawn pursuant to the terms of a permit agreement

1645between the South Florida Water Management District and FPL and

1655the existing Conditions of Certification for Martin Units 3 and

16654. The existing approvals allow withdrawals of an average of

167532,000 - acre feet of water per year and a maximum of 50,000 - acre

1692feet in any 12 month period. Daily withdrawals are limited to a

1704maximum of 518.4 million gallons per day.

17116. Other existing facilities on the Martin Plan t site

1721include residual and light oil storage tanks, water and

1730wastewater treatment facilities, two onsite system substations

1737and transmission lines, warehouses, maintenance buildings, and

1744administration and ancillary facilities. The balance of the

1752Martin site is undeveloped or utilized for agricultural

1760operations. This includes the Barley Barber Swamp and a 1,200

1771acre parcel, known as the Northwest Parcel, established as a

1781wetland mitigation area associated with the Martin CG/CC Project.

17907. Land uses surrounding the Martin Plant site are

1799primarily agricultural, including cropland, pastures, groves,

1805three types of wetlands, scattered rural residences, and

1813undeveloped land. The nearest residence is approximately two

1821miles away from the proposed Martin U nit 8 Project area.

1832Project Overview

18348. The Martin Unit 8 Project will combine the two

1844existing simple cycle combustion turbines in operation at the

1853Martin Plant (Units 8A and 8B) with two new combustion turbines,

1864four new heat recovery steam generators , and a new steam turbine

1875electric generator. The resulting "four - on - one" combined cycle

1886Unit 8 will have a generating capacity of approximately 1,100

1897megawatts and will increase the total installed generating

1905capacity of the Martin Plant by approximately 800 megawatts. The

1915Project also includes an optional cooling tower and two new

1925transmission lines to integrate Unit 8 with FPL's transmission

1934system.

19359. Martin Unit 8 will be located south of existing Units

19463 and 4, with the new steam turbine and the new CTs (8C and 8D)

1961adjacent to and east of existing Units 8A and 8B. The Project

1973Area comprises approximately 110 acres. The Unit 8 power block

1983will be located in an area that has already been affected by

1995existing uses at the Martin Plant. Approximate ly 15.5 acres will

2006be occupied by the Unit 8 power block. Approximately 28.4 acres

2017will be occupied by construction facilities (laydown, parking and

2026construction trailers). The Project Area is located completely

2034within the already certified portion of th e Martin Plant Site.

2045Need for Martin Unit 8

205010. On December 10, 2002, the Florida Public Service

2059Commission ("PSC") issued its Final Order determining the need

2070for the FPL Martin Unit 8 Project (as well as FPL's proposed Unit

20833 at its Manatee Plant). The PSC determined that FPL has a need

2096for additional capacity to maintain the reliability of FPL’s

2105electrical system. FPL was found to have a need for Martin Unit

21178 taking into account the need for adequate electricity at a

2128reasonable cost. The Commissi on found that FPL chose a proven

2139technology and has the necessary experience in the construction

2148and operation of combined cycle units. Further, the cost

2157estimates for Martin Unit 8 were found to be reasonable. The

2168Commission concluded there were no furt her energy conservation

2177measures available to FPL that could offset the need for Martin

2188Unit 8. FPL was found to have implemented a considerable amount

2199of cost effective energy conservation and demand side management.

2208Based upon FPL’s evaluation of othe r alternatives submitted in

2218response to a request for proposals, the Commission found that

2228Martin Unit 8, along with Manatee Unit 3, are the most cost

2240effective alternatives available to meet FPL's need for

2248additional generating capacity beginning in 2005. The PSC also

2257found FPL had properly and accurately evaluated transmission

2265costs. The Commission concluded that FPL had met the statutory

2275requirements under Section 403.519, Florida Statutes, for the

2283determination of need for Martin Unit 8.

2290Project Sch edule and Construction

229511. FPL expects to begin construction of Martin Unit 8 in

2306June 2003, or upon receiving final approvals for the Project.

2316Unit 8 is expected to be completed in June 2005, in order to meet

2330FPL's customer's summer needs in that year. The simple cycle

2340portions of the two new combustion turbines associated with Unit

23508 are scheduled for completion in June 2004, to allow operation

2361in simple cycle mode while construction of the combined cycle

2371unit is ongoing. The two existing combustion tu rbines will

2381continue operating in simple cycle mode until the combined cycle

2391unit is completed.

239412. Peak construction employment for the Project will be

2403approximately 574 construction workers, management, and staff.

2410Construction employment is expected to average about 250 workers

2419during the 24 - month construction period.

242613. FPL made roadway improvements at the Martin Plant

2435entrance in connection with the construction of Units 3 and 4.

2446Construction of temporary or permanent roads that connect offsit e

2456is not proposed, as the existing plant entrance at S.R. 710 will

2468be used for Project constructionaffic resulting from Project

2476construction will not degrade traffic flow below established

2484levels of service. Major pieces of equipment will be delivere d

2495by truck over existing roadways, or by rail over a rail line that

2508already serves the Martin Plant site.

251414. The Unit 8 Project Area has been previously cleared and

2525graded, with scrubgrass cover. The Project will require minimal

2534clearing. Impacts from creating material laydown areas will be

2543minimal, temporary, and mainly associated with grubbing and

2551grading to create proper drainage.

255615. Soils will need to be excavated to provide support for

2567the Unit 8 foundation and other facilities. Foundations f or

2577heavy loads will be supported by spread foundations or pilings.

2587Subsurface excavations may require temporary dewatering by

2594localized pumping of the shallow aquifer to lower the water

2604table. The effluent from dewatering will be routed to the

2614cooling po nd. There will be no significant impacts from

2624construction dewatering on surface waters. No offsite impacts to

2633groundwater from dewatering activities are expected, and there

2641will be no impacts to underlying deeper aquifers.

264916. The entire construction area within the Unit 8 Project

2659Area is outside the 100 year flood zone. Construction activities

2669will alter runoff in parts of the site but no adverse effects are

2682expected from these activities. Construction period surface

2689water runoff will be conveyed to existing stormwater channels and

2699ponds that can provide wet retention for all runoff from these

2710areas. The stormwater management system for Unit 8 has been

2720previously designed and constructed as part of the development of

2730Units 3 and 4 and Units 8A and 8 B.

274017. No construction for the Project is proposed in surface

2750waters of the State. Impacts to offsite surface waters from

2760construction - related runoff are expected to be negligible.

2769Onsite construction activities will not cause adverse ecological

2777effe cts, as the Project Area is already highly altered, and

2788maintained as either grassy, open areas or covered with limerock.

2798These areas do not contain unique wildlife species and are not

2809considered important wildlife habitats because of their disturbed

2817natu re. Wetlands within the Project Area are limited primarily

2827to man - made ditches and stormwater basins. A small depressional

2838wetland area is located within the pine flatwoods parcel to the

2849east of the power block, but will not be impacted by the

2861constructi on of Unit 8. The site certification for the Martin

2872CG/CC Project addressed wetland impacts for the entire certified

2881site, and mitigation for those potential future impacts has

2890already been provided in the Northwest Parcel.

289718. Noise during construction of the Project will comply

2906with the Martin County Noise Control Ordinance. Construction

2914noise will not affect wildlife in the vicinity of the site. The

2926Martin Plant site already has noise associated with operation of

2936the existing facility and wildlife i n the area is acclimated to

2948such activities.

295019. Control measures will be implemented during Project

2958construction to minimize fugitive air emissions and its potential

2967impacts. Clearing will be kept to a minimum, thereby reducing

2977air emissions from expo sed surfaces. Watering will be used to

2988control fugitive dust on highly traveled areas.

299520. During Project construction, portable chemical toilets

3002and bottled water will be utilized. Solid and hazardous wastes

3012generated during construction will be handl ed and disposed

3021offsite by contractors.

3024Project Description

302621. The Martin Unit 8 Project will utilize the two existing

3037simple cycle combustion turbines ("CTs") presently operating at

3047the Site (Units 8A and 8B) in combination with two new CTs, four

3060new H RSGs, and a new steam turbine/electric generator. Each of

3071the existing CTs, and each of the new CTs, has a nominal

3083generating capacity of approximately 170 MWs. The CTs operate

3092much like a jet engine, in which air and fuel are combined in the

3106CT and then combusted. The heated gases then rotate a shaft that

3118drives an electrical generator. The exhaust gases from the

3127combustion turbines produce steam in the HRSGs, which is used in

3138turn to drive a separate steam turbine generator. By utilizing

3148the waste he at from the CTs, the resulting combined cycle Unit 8

3161will be more efficient than the simple cycle CTs and traditional

3172steam - electrical units. Martin Unit 8, with generating capacity

3182of approximately 1100 megawatts, will be among the most efficient

3192electri c generators in Florida. The Project will add

3201approximately 800 megawatts of generating capacity to the Martin

3210Plant site.

321222. Duct burners are proposed for each HRSG and are fired

3223during peak demand periods to achieve the total nominal

3232generating capac ity of Unit 8. The four CTs will be equipped

3244with inlet air evaporative cooling which creates a cooler, more

3254moisture - laden air stream in the CT, allowing additional power to

3266be produced more efficiently. The CTs will also be capable of

3277power augmentatio n, in which steam from the HRSG is injected into

3289the CT during periods of peak electrical demand to increase

3299electrical output. Each CT will be capable of operation in

"3309peak" mode in which the firing temperature of the combustion

3319turbine is increased, res ulting in increased power.

332723. Exhaust gases from Unit 8 will be emitted from a stack

3339associated with each HRSG unit. Each combustion turbine will

3348also be capable of operating in simple cycle mode in which

3359exhaust gases will be emitted either from a b ypass stack

3370associated with each CT or from the HRSG stack. Natural gas

3381heaters will be used if the CTs are operated in simple cycle

3393mode. The height of the four HRSG stacks will be a maximum of

3406150 feet.

340824. Cooling water for Martin Unit 8 will be pr ovided by

3420either the existing cooling pond or by a new closed - cycle, wet

3433mechanical draft cooling tower. Wastewaters and stormwater from

3441the power block will be treated onsite and recycled to the

3452cooling pond. Other onsite facilities to be constructed as part

3462of the Project will include interconnections with the existing

3471onsite transmission facilities, a gas metering and regulation

3479yard, along with storage facilities for light oil and ammonia.

3489The new Unit 8 will also utilize many of the existing facilit ies

3502and infrastructure components already present at the Martin Plant

3511site.

351225. The primary fuel for the CTs, and the sole fuel for

3524the HRSG duct burners and the fuel heaters, will be natural gas

3536delivered to the Martin Plant by pipeline. The Martin P lant site

3548is presently served by an existing natural gas lateral that may

3559supply gas to Unit 8. Natural gas will not be stored onsite.

3571Light oil with a maximum sulfur content of 0.05 percent by weight

3583will be used as an alternate fuel for the CTs for an equivalent

3596of 500 hours per year per CT. The light oil will be delivered by

3610truck and will be stored in an existing two million gallon tank

3622or in a previously approved, but still to be constructed, two

3633million gallon tank.

363626. Martin Unit 8 will gene rate only small quantities of

3647solid wastes. These will be limited to municipal solid wastes

3657and infrequent replacement of inlet air filters. The catalyst in

3667the selective catalytic reduction (SCR) system will be replaced

3676periodically and disposed of in a ccordance with applicable

3685requirements. Hazardous wastes will be produced in limited

3693quantities. These will be collected and disposed of offsite by a

3704licensed hazardous waste contractor.

370827. Martin Unit 8 will connect to the existing onsite

3718electrical system substation via a new tie line. Additional bays

3728will be added to the existing substation to accommodate the

3738interconnection to FPL's existing electric transmission system.

3745A new 230 kilovolt ('kV') transmission line will be constructed

3755between the onsite Martin Plant System Substation and the

3764existing FPL Indiantown Substation. The new single pole line

3773will be constructed across the Martin Plant site for 1.5 miles

3784and then will follow an existing FPL transmission line right - of -

3797way and existing pub lic roadways to the Indiantown substation.

3807The entire length of that line is approximately 13 miles. An 8.5

3819mile segment of this line is to be constructed in a new right - of -

3835way and this segment is included as part of the Project.

3846Air Emissions

384828. Air emissions from Martin Unit 8 will result from both

3859the combustion process and impurities in the fuel. Nitrogen

3868oxides are formed through the oxidation of a portion of the

3879nitrogen that is naturally found in natural gas. Additional

3888nitrogen oxides are fo rmed through the oxidation of the nitrogen

3899contained in the combustion air. Carbon monoxide and volatile

3908organic compounds are formed by incomplete combustion of fuel.

3917Sulfur dioxide and particulate matter emission rates are dictated

3926by the amount of sul fur in the fuel. Operation of the Unit 8

3940cooling tower will result in emissions of particulate matter,

3949made up of minerals, created by evaporation of the cooling water.

3960These emissions are referred to as cooling tower "drift".

397029. All major new or mod ified sources of regulated air

3981pollutants that are located in areas attaining compliance with

3990ambient air quality standards must be reviewed under state and

4000federal Prevention of Significant Deterioration ("PSD") review

4009requirements. Martin Unit 8 is cons idered a major modification

4019to the existing Martin Plant site because the Project's emissions

4029will exceed the PSD significant emission increase thresholds for

4038several regulated air pollutants. Based on expected emissions

4046from Unit 8, PSD review was requir ed for: particulate matter

4057("PM"), sulfur dioxide ("SO 2 "), nitrogen oxides ("NO x "), carbon

4073monoxide ("CO"), volatile organic compounds ("VOC") and sulfuric

4085acid mist. PSD review is used to ensure that significant air

4096quality deterioration will not result from new facilities like

4105Unit 8. These analyses include a review of the proposed

4115emissions control technology, a source impact analysis, an air

4124quality impact analysis, source information, and additional air

4132quality impact analyses.

4135Air Emissions Contr ol Technology

414030. Air emissions from Martin Unit 8 will be minimized

4150through the inherent efficiency of the combined cycle design, and

4160the use of: natural gas as the primary fuel; advanced combustion

4171control technology; and post - combustion control techno logy.

4180Natural gas, the cleanest of fossil fuels, and light oil have

4191very low levels of impurities and can be burned very efficiently.

4202When firing natural gas, the use of dry low NO x ("DLN") combustion

4217design in the CTs, and low NO x burners ("LNB") in the duct

4232burners, will also minimize air emissions by inhibiting formation

4241of thermal NO x by premixing of fuel and air prior to combustion

4254(in the DLN), and by reducing flame temperatures (in the DLN and

4266LNB). Water injection will be used for NO x control whe n the CTs

4280fire light oil. Selective Catalytic Reduction (SCR) will provide

4289additional control of emissions of NO x from Unit 8 when operating

4301in combined cycle mode. In the SCR system, located in the HRSGs,

4313ammonia is injected into the CT exhaust where NO x in the gas

4326stream reacts with the ammonia in the presence of a catalyst to

4338form nitrogen and water.

434231. State and federal PSD regulations require that Martin

4351Unit 8 meet all applicable emission limiting standards and that

4361Best Available Control Techno logy ("BACT") be applied in order to

4374control emissions. BACT is defined in Rule 62 - 210.200(38),

4384Florida Administrative Code, as:

4388An emission limitation, including a visible

4394emissions standard, based on the maximum

4400degree of reduction of each pollutant emi tted

4408which the Department [of Environmental

4413Protection], on a case by case basis, taking

4421into account energy, environmental and

4426economic impacts, and other costs, determines

4432is achievable through application of

4437production processes and available methods,

4442s ystems and techniques (including fuel

4448cleaning or treatment or innovative fuel

4454combustion techniques) for control of each

4460such pollutant.

4462The BACT requirements are intended to ensure that the air

4472emission control systems for Unit 8 reflect the latest in control

4483technologies used in the electric utility industry and take into

4493consideration existing and future air quality in the vicinity of

4503the Project. BACT review includes a cost - benefit analysis of

4514alternative control technologies capable of achieving a higher

4522degree of emission reduction than the proposed technology.

453032. In its PSD review, the Department preliminarily

4538determined that the air emissions control technologies proposed

4546for Martin Unit 8 are consistent with BACT as required under

4557federal an d state PSD regulations. The use of natural gas as the

4570primary fuel, with light oil as an alternate fuel for the CTs,

4582combined with advanced combustion control technology, will

4589provide the maximum degree of emission reduction for sulfur

4598dioxide, particula te matter, volatile organic compounds, carbon

4606monoxide, and sulfuric acid mist. The dry low NO x control

4617technology for the CTs and the duct burners, and water injection

4628when the CTs fire light oil, along with SCR in combined cycle

4640mode, reflect the latest available control technologies for

4648reducing NO x emissions from combined cycle systems. Combustion

4657controls also limit the formation of carbon monoxide and volatile

4667organic compounds. Cooling tower drift will be minimized through

4676use of high - efficiency d rift eliminators.

468433. The emission limits for Martin Unit 8 in the

4694Department's recommended Conditions of Certification are

4700identical to the emission limits proposed as BACT by the

4710Department. The recommended NO x emission limit of 2.5 parts per

4721million for combined cycle operation during natural gas - firing is

4732equal to or lower than BACT determinations for other combined

4742cycle units in the State of Florida.

4749Air Quality Impact Analysis

475334. Ambient air quality standards have been established by

4762the U.S. EPA and FDEP to protect public health and welfare. Air

4774quality in the vicinity of the Martin Plant currently meets all

4785federal and State ambient air quality standards. Martin County

4794is classified as an attainment area for all criteria pollutants,

4804and no area of Florida is currently designated as "nonattainment"

4814for any air pollutant.

481835. In its PSD review, the Department preliminarily

4826determined that air quality modeling demonstrates that Martin

4834Unit 8 will comply with all State and federal ambient ai r quality

4847standards, as well as PSD Class I and II increments. The air

4859quality modeling conducted for the Project followed EPA and FDEP

4869modeling guidelines. Two air quality models were utilized to

4878assess air quality impacts in the area surrounding the Ma rtin

4889Plant site. The modeling also assessed impacts in the nearest

4899PSD Class I area, which is the Everglades National Park, located

4910approximately 90 miles south of the Project site. Local

4919meteorological data from the National Weather Service was used in

4929the modeling. The modeling incorporated maximum air emissions

4937from the Unit 8 in both combined and simple cycle modes, using

4949light oil and natural gas, and at various operating modes, loads,

4960and ambient air temperatures which may affect the emission rates

4970and dispersion from the Unit. In its PSD review, the Department

4981preliminarily determined that the air quality modeling results

4989indicated that the maximum air impacts from the Project will

4999comply with all ambient air quality standards and PSD Class I and

5011II increments. While these analyses assumed a stack height of

5021125 feet, a stack height of up to 150 feet would generally result

5034in lower impacts, and would not change the conclusions as to the

5046Project's compliance with all air quality standards.

505336. EP A has established "Significant Impact Levels" for the

5063various pollutants that are subject to PSD review, and the

5073Department has adopted these Significant Impact Levels at Rule

508262 - 204.200(29), Florida Administrative Code. The comparison of a

5092project’s air quality impacts with the Significant Impact Levels

5101represents an initial screening analysis to determine which

5109pollutants require a more detailed modeling analysis. In its PSD

5119review, the Department preliminarily determined that the

5126predicted impacts of t he emissions of all air pollutants from

5137Unit 8 are below the PSD Class I and Class II Significant Impact

5150Levels, except for SO 2 for the 24 - hour averaging period with the

5164CTs firing light oil. Accordingly, air quality impacts from Unit

51748 are considered ins ignificant based upon this screening analysis

5184for all pollutants except for SO 2 over the 24 - hour averaging

5197period.

519837. More refined, multi - source modeling was conducted to

5208assess the impacts of Unit 8's SO 2 emissions over the 24 - hour

5222averaging period. In its PSD review, the Department

5230preliminarily determined that this modeling demonstrated that SO 2

5239emissions from Unit 8, when considered along with other existing

5249and PSD sources, would be well below each of the relevant air

5261quality standards.

526338. Nit rogen oxides and volatile organic compounds are

5272precursors to the formation of ozone in the atmosphere.

5281Emissions of these air pollutants from Martin Unit 8 are

5291extremely small compared to regional emissions of NO x and VOCs.

5302In its PSD review, the Depart ment preliminarily determined that

5312the emissions from Unit 8 will not cause or contribute to any

5324violation of the ambient air quality standards for ozone.

533339. There are expected to be no air quality impacts from

5344associated industrial, commercial, or res idential growth due to

5353the Project or its location. In its PSD review, the Department

5364preliminarily determined that there should also be no adverse

5373impacts to the "Air Quality Related Values," including

5381visibility, soils, vegetation, or wildlife, in the c losest PSD

5391Class I area at the Everglades National Park. Unit 8's potential

5402impacts on regional haze in this Class I area were below the

5414screening level.

541640. In its PSD review, the Department preliminarily

5424determined that impacts from the proposed Unit 8 cooling tower

5434will be minimal. Potential cooling tower impacts on visibility

5443(fogging) and from deposition of drift emissions were evaluated

5452using accepted computerized modeling methodology and conservative

5459assumptions based on relevant design paramete rs for the proposed

5469cooling tower. Results of the evaluations demonstrated that

5477there would be only a very few hours per year in which fogging

5490induced by cooling tower operation will occur. When fogging does

5500occur, the impacts will remain on the Martin P lant site property.

5512Deposition from cooling tower drift will be minimized through the

5522use of high - efficiency drift eliminators. Impacts of cooling

5532tower deposition will be minimal inside the Project Area, and

5542will only occur within the Martin Plant site.

5550Water Uses and Sources

555441. Water uses for the Martin Unit 8 will include condenser

5565cooling, general plant service water, fire protection water, and

5574demineralized water. The largest water use for Unit 8 will be to

5586replace net evaporation from either the cooling pond or the

5596cooling tower due to cooling of the new Unit. Process water uses

5608will include demineralized water to be used in the combustion

5618turbine inlet foggers, for combustion turbine power augmentation,

5626for NO x control in the combustion turbines during light oil

5637firing, and for steam cycle makeup.

564342. Water for Unit 8 will be taken from the existing Martin

5655Plant cooling pond. Makeup to that pond is withdrawn from the

5666St. Lucie Canal, which ultimately connects to Lake Okeechobee.

5675Makeup water w ill be pumped into the cooling pond at an existing

5688intake structure at the southern end of the cooling pond. Water

5699will then be withdrawn from the pond for uses in the Martin Unit

57128.

571343. New cooling water system structures for Unit 8 will be

5724constructe d in the cooling pond. There will be no other

5735construction in surface waters at or near the Project Area.

574544. Cooling water from the pond will be circulated through

5755the Unit 8 condensers and auxiliary heat exchangers to remove

5765waste heat. This waste h eat is dissipated by the cooling pond,

5777primarily by evaporation, radiation and conduction to the

5785atmosphere. The cooled water is then recirculated through the

5794pond back to the units. The proposed Unit 8 will either utilize

5806the cooling pond in the same ma nner as the existing units or will

5820utilize a mechanical draft cooling tower instead. If a cooling

5830tower is constructed, it will dissipate the heat primarily by

5840evaporation and conduction to the atmosphere. Makeup water for

5849the cooling tower would be with drawn from the cooling pond and

5861blowdown from the new cooling tower will then be returned to the

5873cooling pond

587545. The cooling pond is approximately 6,800 acres, with

58856,500 acres being water surface and the balance in the

5896embankments. The existing Martin Plant cooling pond has been

5905sized, constructed, and previously approved to handle the thermal

5914load associated with additional generating capacity.

5920Mathematical modeling of the thermal performance of the cooling

5929pond was previously performed based on a wid e range of potential

5941heat loadings to the pond. Based upon that modeling, with the

5952expected operation of all of the generating units, including Unit

59628, there is adequate water available under the permitted amounts

5972to operate the existing units as well as Martin Unit 8. The

5984Project will not require an increase in the currently - authorized

5995withdrawal rates of water from the St. Lucie Canal or from

6006groundwater sources with or without the cooling tower. With the

6016addition of Martin Unit 8, the Plant will conti nue to be operated

6029within the thermal limits and constraints that were previously

6038reviewed and permitted.

604146. Potable water will be provided by the existing

6050permitted system and the potable water uses for Unit 8 will not

6062exceed the existing permitted qu antities. Domestic wastewater

6070generated by Unit 8 will be handled by the existing system.

608147. Water for process water needs will be withdrawn from

6091the cooling pond and pretreated and used as service water. The

6102service water system will also feed the existing reverse

6111osmosis/mixed bed demineralizer system which may be upgraded for

6120Unit 8 within the existing area occupied by that equipment.

6130Waste streams from the RO treatment system will be treated by

6141existing plant systems and recycled to the cooling pond.

615048. The design and operation of Martin Unit 8 will

6160incorporate a number of water conserving features. All of the

6170power block area contact stormwater will be recycled back to the

6181cooling pond, minimizing makeup requirements for cooling water.

6189All wastewaters will be treated and recycled to the cooling pond.

6200Use of the dry low NO x burners in the combustion turbines will

6213minimize water use when natural gas is fired. These features,

6223when combined with the existing water management features,

6231includi ng the toe drain recovery system and limited cooling pond

6242discharges, help minimize the use of both groundwater and surface

6252waters.

6253Wastewaters and Surface Water Discharges

625849. Unit 8 will utilize the existing Martin Plant's

6267wastewater treatment system. The only new wastewater generated

6275by Unit 8 will be HRSG blowdown and equipment area stormwater and

6287wash waters. HRSG blowdown will be quenched with service water

6297and recycled to the cooling pond. Equipment area stormwater and

6307wash waters will be passe d through an oil/water separator and

6318then recycled to the cooling pond.

632450. The cooling system for Martin Unit 8 requires either

6334chlorination or use of biocides to prevent biofouling of the heat

6345rejection system. A chlorine solution will be fed into th e

6356intake structure for the Unit 8 heat rejection system as

6366appropriate. If the cooling tower is installed, a scale

6375inhibitor will be fed into the circulating water system to

6385control the formation of calcium carbonate scales, which can

6394adhere to the heat t ransfer surfaces and impair cooling

6404performance. Sulfuric acid and a polymer will also be added as

6415necessary to the water treatment.

642051. Chemical treatment will also be required in the HRSG to

6431prevent corrosion and scaling of the condensate piping. Th e HRSG

6442boiler and piping will be chemically cleaned initially during

6451commissioning, and periodically during the life of the Unit.

6460These chemicals will not be permanently stored onsite but will be

6471delivered by a licensed contractor at the time of the sched uled

6483cleanings. Wastewaters from this cleaning will consist of the

6492cleaning solutions and the materials removed. Chemical

6499wastewaters can also result from draining of chemical storage

6508tanks or from cleaning and maintenance operations. These wastes

6517will be contained and treated locally or routed to the existing

6528neutralization system for treatment. These flows will be

6536intermittent and will not contribute to the overall wastewater

6545flows.

654652. Minimum and maximum water levels within the cooling

6555pond will remain within previously approved levels. Surface

6563water discharges from the pond will occur only during annual gate

6574tests and following extreme rainfalls. The spillway is

6582controlled by four sluice gates which allow water to discharge

6592automatically to pro tect the embankment from overtopping during

6601large rainfall events. The current operating scenario for the

6610cooling pond provides for approximately 6.33 feet of freeboard,

6619allowing the pond enough freeboard between the water level and

6629the top of the embankm ent to hold more than eight 100 - year

6643storms.

664453. Based upon previous modeling of the Martin cooling pond

6654and predicted makeup water volumes to the pond, the estimated

6664concentrations of dissolved constituents within the cooling pond

6672were calculated. Thi s modeling indicated that there would be no

6683exceedances of Class III surface water quality standards in the

6693cooling pond water. The water quality in the St. Lucie Canal,

6704which would receive any discharge from the cooling pond, will not

6715be affected by gate testing because there is an existing mixing

6726zone within the intake/discharge canal between the spillway and

6735the St. Lucie Canal. In order to limit the impact of a

6747discharge, the intake pumps for the cooling pond can be run

6758during gate tests to return spi llway releases to the cooling

6769pond. Prior to annual gate tests, the cooling pond water is

6780analyzed in accordance with the existing industrial wastewater

6788facility permits. If the test results indicate any constituent

6797in the pond would exceed 90 percent of the Class III surface

6809water criteria, FPL operates the makeup pumps to prevent any

6819exceedance of a water quality standard in the St. Lucie Canal by

6831pumping the discharge water back into the pond. Gate tests will

6842be performed in the same manner after addi tion of Unit 8.

685454. The St. Lucie Canal is a manmade canal excavated in the

68661910s and 1920s to regulate the water level of Lake Okeechobee.

6877The Canal extends approximately 30 miles from Lake Okeechobee to

6887the St. Lucie Inlet near Stuart. It has a dept h of approximately

6900eight feet and an average flow of 748 cubic feet per second. It

6913is controlled at both ends by locks, which regulate the discharge

6924from Lake Okeechobee and into the Atlantic Ocean. Vegetation

6933along and in the canal is dominated by emerg ent grasses and

6945exotic species, as well as saw palmetto, pine, cabbage palm, and

6956planted citrus. The canal is considered only marginal breeding

6965and spawning habitat for fish. The planned withdrawals to supply

6975Unit 8 will not contribute to the existing ef fects from

6986sedimentation, nutrient loading, and salinity fluctuations in the

6994canal.

6995Surface Water Management System

699955. The stormwater facilities to handle runoff from the

7008Martin Unit 8 Project area were designed and constructed with

7018Units 3 and 4. Th e surface water management system for the

7030Project has been designed to meet the requirements of the South

7041Florida Water Management District. The peak post - construction

7050runoff flow rate resulting from the design storm will not exceed

7061the pre - development pe ak flow rate. The Project drainage system

7073of catch basins, pipes, channels, and culverts will convey runoff

7083to the existing site drainage system of channels and ponds. Non -

7095contact surface runoff from the area disturbed for Project

7104construction and operat ion of Unit 8 will be collected and routed

7116to two existing permanent ponds. Existing drainage patterns will

7125be maintained, ensuring proper function of the stormwater system.

7134An existing, temporary construction stormwater pond will be

7142utilized during cons truction to prevent sediment transmission

7150offsite until construction of Unit 8 is complete. Prior to

7160beginning any earth disturbing activities, a silt fence will be

7170installed along the perimeter of the Project where runoff to

7180offsite areas is expected. T emporary erosion and sedimentation

7189control measures will be designed to prevent sediment from being

7199displaced and carried offsite by construction runoff. All

7207temporary sediment and erosion control measures will be removed

7216at the end of construction.

7221Gro undwater Impacts

722456. The only groundwater withdrawals associated with the

7232operation of Martin Unit 8 will be the withdrawal of groundwater

7243for the potable water system. The withdrawal will be within the

7254existing permitted allocations of groundwater. The only known

7262potable water wells within one mile of the Site are those

7273operated by FPL.

727657. The existing Martin Plant cooling pond is the principal

7286source of potential impacts to groundwater at the Plant. Seepage

7296leaves the pond beneath the western and southern edges of the

7307cooling pond and moves toward the surrounding canals where it

7317reenters the surface water regime. A significant majority of the

7327seepage will be intercepted by the toe drains and returned to the

7339cooling pond, and no significant impacts to groundwater quality

7348are expected. The Project is expected to meet applicable

7357groundwater standards. Pursuant to FDEP Rule 62 - 520.520(8),

7366Florida Administrative Code, the Martin Plant cooling pond is

7375exempt from secondary groundwater standards. Furth er, there is

7384an existing zone of discharge for groundwater that extends to

7394FPL’s property line. Monitoring of constituents in the cooling

7403pond which have groundwater standards is included in the existing

7413conditions of certification for the Martin certifie d site in

7423order to meet the requirements for groundwater monitoring for

7432this exemption.

7434Noise Impacts of Construction and Operation

744058. A noise impact assessment was conducted for

7448construction and operation of Martin Unit 8. Background noise

7457levels wer e determined from a noise monitoring program performed

7467at several locations in the vicinity of the Project. These

7477background levels were then combined with noise levels expected

7486from construction and operation of Martin Unit 8. The modeling

7496assumed that all construction equipment would be operating

7504simultaneously and consistently, and therefore the impact

7511assessment is conservative. When the construction noise impacts

7519are combined with the background noise levels, the predicted

7528noise impacts are all less than the noise levels set in the

7540Martin County Noise Control Ordinance. The actual or measured

7549noise levels due to construction are expected to be lower than

7560the predicted levels. A similar analysis was performed to

7569predict maximum noise levels produced by operation of the new

7579unit, along with background noise levels. Predicted noise levels

7588during operation at the nearest residential receptors to the

7597Project are well below the maximum permissible noise levels under

7607the Martin County Noise Ordinance.

7612T ransmission Line

761559. The Martin Unit 8 Project will connect to the existing

7626FPL transmission network at the FPL Martin system substation

7635within the previously certified site. Two new transmission lines

7644will be constructed to integrate the new generation into the

7654transmission network in order to meet the single contingency

7663planning criteria adopted by the National Electric Reliability

7671Council. A new 230 kilovolt ("kV") transmission line will be

7683constructed between the Martin Plant and the existing FPL

7692Ind iantown Substation located east of Indiantown. This new line

7702will be located partly in existing transmission line right - of - way

7715and partly in new transmission line right - of - way. A second 230

7729kV line will be constructed between the existing FPL Indiantown

7739Substation and the existing FPL Bridge Substation further to the

7749east, to be located entirely within an existing FPL transmission

7759line right - of - way. FPL is proposing certification only for the

7772portion of the transmission line from the Martin Plant to the

7783Indiantown Substation that will be constructed on entirely new

7792transmission line right - of - way. The other portions of the

7804transmission lines will be permitted separately.

781060. The proposed transmission line route was selected after

7819evaluation of a number of alternative routes. Other routes,

7828including other existing transmission line rights - of - way, that

7839were evaluated were found to be infeasible or undesirable because

7849of a lack either of access to, or of additional land within

7861existing right - of - ways, addi tional crossings of more land

7873parcels, or increased clearing and potential wetlands impacts

7881when compared to the selected route. The selected route also

7891allows extensive use of existing transmission line rights - of - way

7903and, within the new transmission line corridor, co - location of

7914the new line with existing roads and with existing overhead

7924utilities along a primarily undeveloped strip.

793061. The new transmission line corridor proposed for

7938certification is approximately 8.5 miles long. It will parallel

7947S.R . 76 and C.R. 726, which are adjacent to the St. Lucie Canal.

7961The width of the corridor along S.R. 76 and C.R. 726 will vary.

7974The final average right - of - way to be selected in that corridor

7988will be less than 25 feet wide. The new transmission line

7999struct ures will be single pole concrete structures, with post

8009insulators in a vertical configuration. The typical pole will be

8019about 90 to 100 feet above grade, and higher where necessary for

8031longer spans and for crossing over elevated roads, other overhead

8041uti lities, and waterways. Where the transmission line parallels

8050existing FPL electrical distribution lines, the distribution

8057lines will be co - located on the transmission structures where

8068transmission structures are able to replace the distribution

8076poles. Sp an lengths for the new line will range from 250 to 700

8090feet with a typical span of 500 feet. The span lengths vary to

8103allow avoidance of wetlands and other environmentally sensitive

8111features, or to coincide with property lines or existing

8120distribution pol es. Access is expected to be provided using

8130existing public roads that parallel much of the new transmission

8140line right - of - way. However, small sections of the line may

8153require construction of access roads for construction and

8161maintenance purposes. Acces s roads will be unpaved and can be

8172constructed above natural grade, using clean, compacted fill.

818062. The certified segment of the transmission line will

8189cross lands that are used for agricultural uses; isolated parcels

8199of cabbage palm, Brazilian pepper, live oak, and pine; and

8209infrequent residential properties. Land uses in this area are

8218primarily citrus groves, pastures, undeveloped land, scattered

8225residences, and commercial buildings along the highway.

823263. The only significant surface water body to be crossed

8242by the certified transmission line is the St. Lucie Canal, which

8253will be crossed once within the certified segment of the right -

8265of - way. No significant environmental features are located within

8275the proposed corridor to be certified. Only one p rotected

8285species, the American alligator (a species of special concern),

8294was observed along the 8.5 mile segment of the proposed

8304transmission line corridor. This occurred in a drainage ditch

8313outside of the proposed corridor itself. The new structures are

8323designed and located to minimize impacts to wetlands and the use

8334of a single pole will reduce the fill required for pole pads.

8346The transmission line corridor does not contain critical habitat

8355for any flora or fauna of the region. There are no known scen ic,

8369archaeological, or historic sites within the proposed

8376transmission line corridor

837964. Construction of the new certified segment of the

8388transmission line will initially involve surveying and locating

8396property lines to stake out the limits of the right - o f - way, the

8412location of new roads, and the pole placement sites. The right -

8424of - way is then prepared through removal of all vegetation that

8436will conflict with construction and operation of the transmission

8445line alongside roadways. This will mostly entail tr imming trees

8455and removing conflict trees that could fall into the line itself.

8466Access roads will also be constructed where needed and culverts

8476will be included to maintain existing flow conditions. Wetlands

8485impacts will be minimized through pole placemen t and clearing

8495practices. Unavoidable wetlands impacts will be addressed

8502through a post - certification process. The next step involves

8512erection of the structures which are directly embedded into the

8522ground. Insulators, hardware, and overhead wires are th en

8531installed. The final step involves final cleanup of the right -

8542of - way after construction is complete. Construction and

8551operation of the transmission line will be in compliance with

8561applicable agency standards, including the National Electrical

8568Safety C ode, the Florida Department of Transportation Utility

8577Accommodation Guide, the Martin County Noise Ordinance, and the

8586FDEP's rules setting limits for electric and magnetic fields.

8595Socioeconomic Impacts and Benefits

859965. The Martin Unit 8 Project Area is an appropriate site

8610for the proposed new Unit 8. The Project consists of the

8621installation of a new combined cycle unit at an existing power

8632plant site that has been in use for that purpose since 1980. The

8645Project area is significantly buffered from the p erimeter of the

8656FPL - owned property and nearby residential uses. The vast

8666majority of land use in the vicinity is in agricultural use or

8678undeveloped land. The nearest residence is located just less

8687than two miles south - southeast of the Project Area. Over all, the

8700Project is located in a rural area.

870766. The Martin Unit 8 Project will benefit the economy of

8718Martin County and surrounding communities. Direct benefits from

8726the Project include employment opportunities created by

8733construction and operation. The Project’s direct effects on

8741socioeconomic conditions will be substantially positive.

8747Construction employment will average 250 new jobs during the two

8757year construction period. It is expected that these jobs will

8767result in direct wages of approximatel y $75 million over the two

8779year period. Due to the proximity of the Martin Plant site to

8791large labor markets in the south Florida area, the labor demand

8802for both construction and operation is expected to be met by

8813workers in these areas. Population and h ousing impacts will

8823therefore be minimal because little migration into the area is

8833anticipated as a result of the Project. Direct economic benefits

8843of construction of the Project will also result from purchases of

8854materials and equipment, estimated to be $15 to $20 million

8864within the State. It is expected that the majority of the

8875construction wages will be spent within Martin County and the

8885surrounding regions, which will create additional demands for

8893goods and services. This will create a multiplier eff ect

8903generating additional jobs and earnings.

890867. The operation of Martin Unit 8 will add approximately

891812 new full - time employees at the FPL Martin Site. The

8930additional annual payroll for these employees is estimated to be

8940$600,000. This payroll amoun t is expected to generate an

8951additional $500,000 in wages and benefits to other businesses in

8962the region. Other fixed annual operational costs for Unit 8 will

8973be expended in the region at an estimated amount of $2 million

8985per year.

898768. Property tax pay ments to Martin County resulting from

8997Martin Unit 8 during operation are estimated to be $6.7 million

9008in 2006. Based on the first five years of operation, estimated

9019local tax payments are expected to be $31.4 million for general

9030government and public scho ols in Martin County, and $900,000 in

9042sales tax paid to the State of Florida. The Project’s external

9053cost impacts are expected to be minimal and localized. The

9063Project is not expected to result in any significant impact to

9074local government services.

907769 . The entire Martin Project Area, which includes the Unit

90888 Project Area, was previously determined to be consistent with

9098the State, regional, and local comprehensive plans.

9105Additionally, the Martin Unit 8 Project, including its associated

9114transmission line, is consistent with the Martin County

9122Comprehensive Plan, the State Comprehensive Plan, and the

9130Strategic Regional Policy Plan of the Treasure Coast Regional

9139Planning Council. The Project will also comply with the

9148applicable development standards in the Martin County Land

9156Development Regulations.

915870. Construction and operation of Martin Unit 8 will not

9168adversely affect any nearby landmarks, sensitive areas,

9175recreational areas, archaeological sites, or historical sites.

9182The nearest recreational fac ility is approximately six miles

9191southeast of the Project. The nearest environmentally protected

9199land is the Barley Barber Swamp located on the west side of the

9212cooling pond, which is maintained under FPL’s stewardship as a

9222nature preserve. If archaeolog ical materials are discovered

9230during Project construction or operation, activities would cease.

9238State review of the find would be required before the Project

9249could proceed in the affected area.

925571. Temporary external costs resulting from the Project

9263duri ng construction include the generation of construction

9271traffic. A transportation analysis of the Project indicated that

9280traffic resulting from construction of the Project would not

9289degrade traffic flow on State Road 710 below established levels

9299of service . FPL has already implemented roadway improvements at

9309the Martin Plant entrance and State Road 710, including an

9319extended left - hand turn lane and a south - bound acceleration lane.

9332Thus, no additional roadway improvements are required for

9340construction traf fic. Operation of Martin Unit 8 will add only

935112 new employees at the Martin Plant Site. The Project will also

9363generate truck traffic for delivery of materials for operation

9372and maintenance of the Unit. However, the traffic resulting from

9382operation of U nit 8 will not degrade traffic volumes below

9393established levels of service.

9397Public Comment

939972. Three members of the public provided testimony during

9408the certification hearing. They generally expressed their

9415appreciation for the manner in which FPL has interacted with the

9426community and supported various community activities. No one

9434spoke in opposition to the Project. One member of the public

9445questioned the need for another transmission line.

9452Agency Positions and Stipulations

945673. The FDEP, the Florida Department of Community Affairs,

9465the Florida Department of Transportation, the Florida Fish and

9474Wildlife Conservation Commission, the South Florida Water

9481Management District, the Treasure Coast Regional Planning

9488Council, and Martin Co unty each prepared written reports on the

9499Project. Each of these agencies either recommended approval of

9508Martin Unit 8 or otherwise did not object to certification of the

9520proposed power plant. FDEP has proposed a series of Conditions

9530of Certification for the Project that incorporate the

9538recommendations of the various reviewing agencies. FPL states

9546that it is prepared to accept and can comply with these

9557Conditions of Certification in the design, construction, and

9565operation of Martin Unit 8. The Florida D epartment of Community

9576Affairs stipulated that the Project would not conflict with the

9586State Comprehensive Plan. The Treasure Coast Regional Planning

9594Council stated in its agency report that the Project would not

9605conflict with its Strategic Regional Polic y Plan. Martin County

9615reported that the Project would be consistent with the County’s

9625comprehensive plan and land development code. No state,

9633regional, or local agency has recommended denial of certification

9642of the Project or has otherwise objected to ce rtification of the

9654Project.

9655CONCLUSIONS OF LAW

965874. The Division of Administrative Hearings has

9665jurisdiction over the parties to, and the subject matter of, this

9676proceeding. This proceeding has been conducted in accordance

9684with the Florida Electrical Powe r Plant Siting Act, Chapter 403,

9695Part II, Florida Statutes, and Chapter 62 - 17, Part I, Florida

9707Administrative Code, which set out the procedures for power plant

9717siting reviews.

971975. In accordance with Chapters 120 and 403, Florida

9728Statutes, and Chapter 6 2 - 17, Florida Administrative Code, proper

9739notice was accorded to all persons, entities, and parties

9748entitled to such notice, and appropriate notice was provided to

9758the general public by both the Department and FPL. All necessary

9769and required governmental agencies participated, and the general

9777public had the opportunity to fully participate, in the

9786certification process. Reports and studies were issued by FDEP,

9795the Department of Community Affairs, the Florida Department of

9804Transportation, the Florida Fish and Wildlife Conservation

9811Commission, the South Florida Water Management District, the

9819Treasure Coast Regional Planning Council, and Martin County in

9828accordance with their various statutory duties under the PPSA.

983776. The Florida Public Service Commissio n has issued its

9847determination that a need exists for the electrical generating

9856facility and the electricity it will produce, in accord with

9866Section 403.519, Florida Statutes.

987077. By its own terms, the PPSA "shall not apply" to

9881electrical power plants for which applications for permits were

9890made prior to 1973. Section 403.506(1), Florida Statutes;

9898Chapter 73 - 33, Laws of Florida. FPL applied for permits for

9910Martin Units 1 and 2 prior to 1973, and thus the PPSA does not

9924apply to those existing units. FPL has not in this proceeding

9935sought to invoke the jurisdiction of the PPSA with respect to

9946existing Martin Units 1 and 2, nor has FPL elected to apply for

9959certification of Units 1 and 2 under the optional PPSA provision

9970for certification of existing electric al power plants codified at

9980Section 403.5175, Florida Statutes.

998478. Competent, substantial evidence and testimony produced

9991at the certification hearing demonstrates that FPL has met its

10001burden of proof to demonstrate that the Martin Unit 8 Project,

10012includ ing the proposed transmission line corridor, meets the

10021criteria for certification under the PPSA. Unrebutted testimony

10029and other evidence produced at the hearing demonstrates that the

10039safeguards for construction and operation of the Martin Unit 8

10049Project are technically sufficient to protect the public welfare

10058of the citizens of Florida and are otherwise reasonable and

10068available methods to achieve that protection of the public. The

10078Martin Unit 8 Project will result in minimal adverse effects on

10089human heal th, the environment, the ecology of the land and its

10101wildlife, and the ecology of state waters and their aquatic life.

10112In addition, the Project will not conflict with the state

10122comprehensive plan or the local comprehensive plan for Martin

10131County, Florida. If operated and maintained in accordance with

10140this Recommended Order and the FDEP's proposed Conditions of

10149Certification, the Martin Unit 8 Project will comply with the

10159applicable nonprocedural requirements of all agencies.

10165Furthermore, certification of the Project, including the

10172associated transmission line facility, will fully balance the

10180increasing demand for electrical power plant location and

10188operation in this State with the broad interests of the public

10199that are protected by the PPSA.

10205RECOMMENDATIO N

10207Based upon the foregoing Findings of Fact and Conclusions of

10217Law, it is

10220RECOMMENDED that the Siting Board grant full and final

10229certification to Florida Power & Light Company, under Section

10238403, Part II, Florida Statutes, for the location, construction,

10247a nd operation of the Martin Unit 8 Project, representing a 1100

10259MW combined cycle unit, and including an associated transmission

10268line as described in the Site Certification Application and the

10278evidence presented at the certification hearing, and subject to

10287the Conditions of Certification contained in FDEP Exhibit 2 and

10297incorporated herein by reference.

10301DONE AND ENTERED this 5th day of March, 2003, in

10311Tallahassee, Leon County, Florida.

10315___________________________________

10316CHARLES A. STAMPELOS

10319Administrative Law Judge

10322Division of Administrative Hearings

10326The DeSoto Building

103291230 Apalachee Parkway

10332Tallahassee, Flo rida 32399 - 3060

10338(850) 488 - 9675 SUNCOM 278 - 9675

10346Fax Filing (850) 921 - 6847

10352www.doah.state.fl.us

10353Filed with the Clerk of the

10359Division of Administrative Hearings

10363this 5th day of March, 2003.

10369COPIES FURNISHED:

10371Peter C. Cunningham, Esquire

10375Douglas S. Roberts, Esquire

10379Hopping Green & Sams, P.A.

10384Post Office Box 6526

10388Tallahassee, Florida 32314

10391Scott A. Goorland, Esquire

10395Senior Assistant General Couns el

10400Department of Environmental Protection

104043900 Commonwealth Blvd., Mail Station 35

10410Tallahassee, Florida 32399 - 3000

10415Krista Storey, Esquire

10418Tyson Waters, Esquire

10421Martin County Attorney's Office

104252401 Southeast Monterey Road

10429Stuart, Florida 34996

10432Ross Staf ford Burnaman, Esquire

10437Fish and Wildlife Conservation Commission

10442620 South Meridian Street

10446Tallahassee, Florida 32399 - 1600

10451Sheauching Yu, Esquire

10454Department of Transportation

10457Haydon Burns Building

10460605 Suwannee Street, Mail Station 58

10466Tallahassee, Florida 32399 - 0450

10471Colin Roopnarine, Esquire

10474Assistant General Counsel

10477Department of Community Affairs

104812555 Shumard Oak Boulevard

10485Tallahassee, Florida 32399 - 2100

10490Robert V. Elias, Esquire

10494Florida Public Service Commission

10498Gerald Gunter Building

105012450 Shumard O ak Boulevard

10506Tallahassee, Florida 32399 - 0850

10511Roger Saberson, Esquire

10514Treasure Coast Regional Planning Council

1051970 Southeast Fourth Avenue

10523Delray Beach, Florida 33483 - 4514

10529Susan Roeder Martin, Esquire

10533Assistant General Counsel

10536South Florida Water Managem ent District

10542Post Office Box 24680

10546West Palm Beach, Florida 33416

10551David B. Struhs, Secretary

10555Department of Environmental Protection

105593900 Commonwealth Boulevard

10562Tallahassee, Florida 32399 - 3000

10567Teri L. Donaldson, General Counsel

10572Department of Environment al Protection

105773900 Commonwealth Boulevard, Mail Station 35

10583Tallahassee, Florida 32399 - 3000

10588Kathy C. Carter, Agency Clerk

10593Office of the General Counsel

10598Department of Environmental Protection

106023900 Commonwealth Boulevard, Mail Station 35

10608Tallahassee, Florid a 32399 - 3000

10614NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

10620All parties have the right to submit written exceptions within 15

10631days from the date of this Recommended Order. Any exceptions to

10642this Recommended Order should be filed with the agency that will

10653issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 07/27/2004
Proceedings: Intent to Modify Conditions of Certification filed.
PDF:
Date: 07/19/2004
Proceedings: Letter to H. Oven from B. Linkiewicz regarding FDEP intent to modify conditions of certification for its Martin Power Plant filed.
PDF:
Date: 06/07/2004
Proceedings: Intent to Modify Conditions of Certification filed by DEP.
PDF:
Date: 04/15/2003
Proceedings: Final Order on Certification filed.
PDF:
Date: 04/11/2003
Proceedings: Agency Final Order
PDF:
Date: 03/10/2003
Proceedings: Waiver of Time Frames for Filing Exceptions (filed by S. Martin via facsimile).
PDF:
Date: 03/05/2003
Proceedings: Recommended Order
PDF:
Date: 03/05/2003
Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
PDF:
Date: 03/05/2003
Proceedings: Recommended Order issued (hearing held February 17, 2003) CASE CLOSED.
PDF:
Date: 03/03/2003
Proceedings: Letter to Judge Stampelos from P. Cunningham submitting the record of the certification hearing for the FPL Maritn project filed.
PDF:
Date: 02/28/2003
Proceedings: Notice of Filing Late Signature Page to Joint Proposed Recommended Order filed by D. Roberts.
PDF:
Date: 02/26/2003
Proceedings: Joint Proposed Recommended Order filed.
PDF:
Date: 02/26/2003
Proceedings: Notice of Filing Joint Proposed Recommended Order filed.
Date: 02/21/2003
Proceedings: Transcript of Proceedings filed.
PDF:
Date: 02/12/2003
Proceedings: Notice of Filing Prepared Direct Testimony and Exhibits filed by D. Roberts.
PDF:
Date: 02/10/2003
Proceedings: (Joint) Pre-hearing Stipulation filed.
PDF:
Date: 01/31/2003
Proceedings: Notice of Filing Certified Proof of Publication for Notices of Certification Hearing for a Power Plant Siting Application ot be Located in Martin County, Florida filed by P. Cummingham.
PDF:
Date: 01/10/2003
Proceedings: Notice of FPL`s Initial Witness List filed.
PDF:
Date: 01/10/2003
Proceedings: List of Witnesses for Certification Hearing (filed by S. Goorland via facsimile).
PDF:
Date: 01/03/2003
Proceedings: Corrected Department of Transportation`s Witness List (filed via facsimile).
PDF:
Date: 12/24/2002
Proceedings: Order of Pre-hearing Instructions issued.
PDF:
Date: 12/20/2002
Proceedings: Motion to Establish Prehearing Schedule filed by D. Roberts.
Date: 12/20/2002
Proceedings: DEP`s Power Plant Site Certification Review for Florida Power & Light Martin Expansion Project Unit 8 filed.
PDF:
Date: 08/29/2002
Proceedings: Land Use Order filed.
PDF:
Date: 08/19/2002
Proceedings: Notice of Hearing issued (hearing set for February 17 through 21, 2003; 1:00 p.m.; Indiantown, FL).
PDF:
Date: 07/29/2002
Proceedings: Order issued. (certification hearing scheduled for November 18-22, 2002, is cancelled and will be re-set for February 17-21, 2003, at a site to be announced)
PDF:
Date: 07/16/2002
Proceedings: Stipulation and Joint Motion for Alteration of Time Limits filed.
PDF:
Date: 06/10/2002
Proceedings: Recommended Order
PDF:
Date: 06/10/2002
Proceedings: Land Use Recommended Order issued.
PDF:
Date: 06/10/2002
Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
PDF:
Date: 06/05/2002
Proceedings: Notice of Sufficiency (filed by S. Goorland via facsimile).
PDF:
Date: 06/03/2002
Proceedings: Notice of Filing Joint Proposed Recommended Order on Land Use Hearing filed.
PDF:
Date: 06/03/2002
Proceedings: Letter to Judge Stampelos enclosing a disk of the joint PRO filed.
PDF:
Date: 05/22/2002
Proceedings: Florida Power & Light Co. and Department of Enviromental Protection`s Joint Notice of Filing Late Exhibit filed.
PDF:
Date: 05/17/2002
Proceedings: Transcripts of Proceedings filed.
PDF:
Date: 05/06/2002
Proceedings: Florida Power & Light Co.`s Notice of Filing Responses to Notice of Insufficiency of the Department of Enviromental Protection filed.
Date: 05/01/2002
Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
PDF:
Date: 04/29/2002
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing Application for Site Certification for a Power Plant to be Located in Martin County, Florida filed.
PDF:
Date: 04/29/2002
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Land Use Hearing for a Power Plant Siting Application to be Located in Martin County, Florida filed.
PDF:
Date: 04/23/2002
Proceedings: (Joint) Land Use Hearing Prehearing Stipulation filed.
PDF:
Date: 04/16/2002
Proceedings: Florida Power & Light Co`s Response to Florida Department of Environmental Protection`s Notice of Insufficiency filed.
PDF:
Date: 04/04/2002
Proceedings: Notice of Insufficiency filed by Department.
PDF:
Date: 03/26/2002
Proceedings: Order Altering Time Limit issued.
PDF:
Date: 03/20/2002
Proceedings: Notice of Participation (filed by S. Martin via facsimile).
PDF:
Date: 03/20/2002
Proceedings: Notice of Substitution of Counsel (filed by S. Martin via facsimile).
PDF:
Date: 03/20/2002
Proceedings: Notice of Appearance (filed by P. Cunningham).
PDF:
Date: 03/18/2002
Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
PDF:
Date: 03/12/2002
Proceedings: Joint Stipulation and Motion for Alteration of Time Limit (filed via facsimile).
PDF:
Date: 03/11/2002
Proceedings: Notice of Hearing sent out. (November 18-22, 2002, 9:00 a.m., Indiantown, Florida).
PDF:
Date: 03/11/2002
Proceedings: Order of Pre-hearing Instructions issued.
PDF:
Date: 03/11/2002
Proceedings: Notice of Hearing issued (hearing set for May 1, 2002; 9:00 a.m.; Indiantown, FL).
PDF:
Date: 03/08/2002
Proceedings: Letter to Judge Johnston from D. Roberts regarding venue of hearing filed.
PDF:
Date: 03/07/2002
Proceedings: Notice of Participation (filed by Martin County via facsimile).
PDF:
Date: 03/01/2002
Proceedings: Response to Initial Order (filed by DEP via facsimile).
PDF:
Date: 02/28/2002
Proceedings: Notice of Intent to be a Party (filed by R. Burnaman via facsimile).
PDF:
Date: 02/25/2002
Proceedings: Department of Environmental Protection`s Correction to Proposed Site Certification Application Schedule (filed via facsimile).
PDF:
Date: 02/25/2002
Proceedings: Department of Environmental Protection`s Proposed Site Certification Applications Schedule (filed via facsimile).
PDF:
Date: 02/22/2002
Proceedings: Notice of Filing of Site Certification Application filed by DEP.
PDF:
Date: 02/19/2002
Proceedings: Initial Order issued.
PDF:
Date: 02/18/2002
Proceedings: Statement of Completeness (filed by S. Goorland via facsimile).
PDF:
Date: 02/08/2002
Proceedings: Notice of Filing of List of Affected Agencies (filed via facsimile).
PDF:
Date: 02/08/2002
Proceedings: Notice of Receipt of Power Pant Siting Application and Request for Assignment of Administrative Law Judge (filed via facsimile).

Case Information

Judge:
CHARLES A. STAMPELOS
Date Filed:
02/08/2002
Date Assignment:
04/24/2002
Last Docket Entry:
07/27/2004
Location:
Indiantown, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
Suffix:
EPP
 

Counsels

Related Florida Statute(s) (8):