02-003529EPP In Re: Florida Power Corporation Hines Energy Complex, Power Block 3, Power Plant Siting Supplemental Application No. Pa92-33sa2 vs. *
 Status: Closed
Recommended Order on Tuesday, June 10, 2003.


View Dockets  
Summary: Progress Energy Florida provided sufficient evidence for granting certification to construct and operate a new 530 megawatt natural gas-fueled electrical power plant in Polk County.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: FLORIDA POWER )

13CORPORATION HINES ENERGY )

17COMPLEX, POWER BLOCK 3, POWER )

23PLANT SITING SUPPLEMENTAL ) Case No. 02 - 3529EPP

32APPLICATION NO. PA92 - 33SA2. )

38)

39RECOMMENDED ORDER

41Pursuant to notice, the Division of Administrative

48Hearings, by its duly - designated Administrative Law Judge,

57Charles A. Stampelos, held a certification hearing in the above -

68styled case on May 12, 2003, in Bartow, Florida.

77APPEARANC ES

79For Progress Energy Florida (formerly known as Florida

87Power Corporation):

89Douglas S. Roberts, Esquire

93Hopping Green & Sams, P.A.

98123 South Calhoun Street

102Post Office Box 6526

106Tallahassee, Florida 32314

109For the Department of Environmental Prote ction:

116Scott A. Goorland, Esquire

120Department of Environmental Protection

1243900 Commonwealth Boulevard

127Mail Station 35

130Tallahassee, Florida 32399 - 3000

135For the Southwest Florida Water Management District:

142Martha A. Moore, Esquire

146Southwest Florida Water

149Management District

1512379 Broad Street

154Brooksville, Florida 34604 - 6899

159For Polk County:

162Michael Duclos, Esquire

165Polk County Attorney's Office

169Post Office Box 9005

173Bartow, Florida 33831 - 9005

178STATEMENT OF THE ISSUE

182The issue to be resolved in this proceeding is whether the

193Governor and Cabinet, sitting as the Siting Board, should issue

203certification to Progress Energy Florida ("PEF"), to construct

213and operate a new 530 megawatt ("MW") natural gas - fired

226electrical power plant in Polk County, Florida. The proposed

235site for the Project is located at Progress Energy Florida's

245existing Hines Energy Complex, southwest of Bartow, Florida.

253PRELIMINARY STATEMENT

255This proceeding was conducted pursuant to the Florida

263Electrical Power Plant Siting Act ("PPSA") , Chapter 403, Part

274II, Florida Statutes, and Chapter 62 - 17, Florida Administrative

284Code, to consider PEF's application for site certification for

293the proposed Hines Power Block 3 (also referred to as the

"304Project").

306On September 4, 2002, Florida Power Co rporation ("FPC" or

"317PEF") filed its Supplemental Application for site certification

326for the Hines Power Block 3 with the Florida Department of

337Environmental Protection ("Department" or "FDEP"). (On

345January 1, 2003, Florida Power Corporation changed its c orporate

355name to Progress Energy Florida ("PEF")). The application was

366found to be complete on September 19, 2002. The application was

377found to be sufficient on February 13, 2003.

385On February 4, 2003, the Florida Public Service Commission

394issued its Fin al Order determining the need for the proposed

405electrical power plant.

408On April 11, 2003, FDEP issued its written Staff Analysis

418Report concerning the Project, as required by Section

426403.507(4), Florida Statutes, incorporating the reports from

433other state and regional agencies and proposing a comprehensive

442set of proposed Conditions of Certification.

448On May 7, 2003, a joint prehearing stipulation was

457submitted to the undersigned, which indicated that no party to

467this proceeding objected to certification o f the Project.

476On May 12, 2003, during the certification hearing, FDEP

485submitted its revised Staff Analysis Report as FDEP Exhibit 2.

495After proper public notice by both PEF and by FDEP, a

506certification hearing was held in Bartow, Florida on May 12,

5162003, as required by Section 403.508(3), Florida Statutes. The

525purpose of the certification hearing was to receive oral,

534written, and documentary evidence concerning whether, through

541available and reasonable methods, the location and operation of

550the proposed Hines Power Block 3 would produce minimal adverse

560effects on human health, the environment, the ecology of the

570land and its wildlife, and the ecology of State waters and their

582aquatic life, in an effort to balance the increase in demand for

594an electrical p ower plant location and operation with the broad

605interests of the public. See Section 403.502, Florida Statutes.

614The hearing would have also considered any petitions challenging

623the separate FDEP - issued prevention of significant deterioration

632("PSD") per mit for the Project; however, no such petition was

645filed.

646At the certification hearing, PEF presented the oral

654testimony of three witnesses and had PEF exhibits numbered 1

664through 9, 11 and 12 admitted into evidence. These exhibits

674included the prefiled written testimony of three additional

682witnesses. That testimony was filed pursuant to Rule 62 -

69217.141(3), Florida Administrative Code. The prefiled written

699testimony has been accepted based upon execution of affidavits

708attesting to the accuracy of the tes timony and accompanying

718exhibits. FDEP presented the testimony of Hamilton S. Oven, of

728the FDEP's Siting Coordination Office, and had FDEP Exhibits 1

738and 2 admitted into evidence. No member of the public appeared

749at the hearing to offer testimony or othe r evidence on the

761Project.

762Subsequent to the certification hearing, PEF, upon

769authorization granted at the hearing, submitted its late - filed

779exhibit PEF - 10, representing the Affidavit of Paul V. Crimi,

790attesting to his prefiled written testimony and exhib its.

799Following the conclusion of the May 12, 2003 hearing, a

809transcript of the hearing was filed on May 29, 2003. The Joint

821Proposed Recommended Order of PEF, FDEP, Southwest Florida Water

830Management District ("SWFWMD"), and Polk County was timely

840submit ted and has been considered in the rendition of this

851Recommended Order.

853FINDINGS OF FACT

856BACKGROUND

8571. Progress Energy Florida, previously known as Florida

865Power Corporation, is an electric utility that provides

873electricity in a 32 - county service area in Florida, extending

884from the middle of the Panhandle down through the center of the

896state, including the west coast of Florida, north of Tampa Bay.

907PEF currently serves approximately 1.5 million customers in this

916service area. PEF has been providing elec tric service for over

927100 years, beginning in 1899 when it began business as the St.

939Petersburg Electric Light & Power Company. The Company's

947generating capacity has grown from an initial generation of 50

957kilowatts up to its total generating capacity toda y of

967approximately 8,586 megawatts. PEF has a customer growth rate

977of approximately two percent per year. The Company currently

986operates 14 different power plant facilities using a mix of

996natural gas, oil, coal, and nuclear power.

10032. The PEF Hines Ener gy Complex is located in the

1014southwest portion of Polk County, Florida, approximately 3.5

1022miles south of the city of Bartow. The unincorporated community

1032of Homeland lies about one mile to the northeast of the site

1044boundary. County Road 555 runs through the Project site. The

1054Hines site contains approximately 8,200 acres of reclaimed

1063phosphate mine lands. The site is located in a region of the

1075state dominated by phosphate mining operations, including mines,

1083settling ponds, sand tailings, gypsum stacks an d chemical

1092beneficiation plants. The adjacent land uses consist almost

1100entirely of active phosphate mining or reclaimed mine lands.

11093. The Hines Energy Complex was identified and purchased

1118by then Florida Power Corporation in the mid - 1990s. The site

1130was selected following a comprehensive process of locating a

1139suitable site for a large new generating facility. A systematic

1149site selection approach was undertaken to identify sites

1157suitable for multiple units which could accommodate potential

1165clean coal technology, be technology and fuel flexible, be cost

1175effective, be fully compatible with PEF's commitment to

1183environmental protection, be in compliance with applicable

1190government regulations, and be consistent with state and local

1199land use policies. At th at time, Florida Power Corporation

1209solicited the help of a team of community, educational and

1219environmental leaders to evaluate over 50 potential sites in

1228Florida and south Georgia. That two - year process culminated in

12391991 with the selection of the Hines site.

12474. In January 1994, the Siting Board certified the Hines

1257Energy Complex for an ultimate site capacity of 3,000 megawatts

1268of electrical generating capacity and also granted certification

1276for the construction and operation of an initial 470 MW combi ned

1288cycle unit known as Power Block 1. In 2001, the Siting Board

1300also granted certification for the construction and operation of

1309Hines Power Block 2, a 530 MW combined cycle unit, which is

1321currently under construction.

13245. The Hines Energy Complex con tains a number of existing

1335facilities and is divided into several major areas. The plant

1345island is the location for the existing and future power

1355generation facilities. It is approximately 704 acres. A 722 -

1365acre cooling pond has been constructed on the s ite, along with a

1378311 - acre brine pond. A buffer area has been created along the

1391eastern portion of the site containing approximately 2,128

1400acres. These areas serve as a wildlife corridor as well.

1410Approximately 4,000 acres of the site are designated for water

1421crop areas to supply captured rainfall for use in the power

1432plant.

14336. The Hines Energy Complex is served by an existing dual

1444circuit 230 kV transmission line that enters the Hines site from

1455the northwest. A second dual circuit 230 kV transmissio n line

1466departs the site heading due south. The existing transmission

1475lines are adequate to serve the new Power Block 3. Natural gas

1487is delivered to the Hines Energy Complex by two existing natural

1498gas pipelines, which will serve Power Blocks 1, 2 and 3. Fuel

1510oil is also burned in the existing units and is delivered by

1522truck and stored in an on - site storage tank. That tank is

1535adequate to serve the requirements of Power Block 3.

1544PROJECT OVERVIEW

15467. The Hines Power Block 3 is a 530 MW combined - cycle

1559pow er plant to be fueled primarily with natural gas. Fuel oil

1571will be used as a backup fuel. The proposed Power Block 3 will

1584be located entirely within the existing Hines Energy Complex

1593site. The unit will be located west of Power Blocks 1 and 2.

1606All cons truction activities for Power Block 3 will occur within

1617an approximately 5 - acre portion of the plant island.

1627NEED FOR POWER BLOCK 3

16328. On February 4, 2003, the Florida Public Service

1641Commission issued a Final Order determining the need for the

1651Progress Energy Florida's Hines Power Block 3 Project. The

1660Public Service Commission determined that the Hines Power

1668Block 3 will be needed by December 2005, to maintain electric

1679system reliability and integrity for PEF. This was based upon

1689an evaluation of PEF's load forecast and maintenance of its

1699required reserve margin of generating capacity above the firm

1708demand of PEF's customers. The Public Service Commission also

1717found that the Hines Power Block 3 will contribute to the

1728provision of adequate electricity at reasonable cost. The

1736Project was found to consist of a proven technology at

1746reasonable estimated cost. Construction at the Hines site also

1755allows PEF to take advantage of existing infrastructure at the

1765Hines Energy Complex, thereby saving PEF site devel opment costs.

1775The Public Service Commission also concluded that PEF, in

1784proposing the Hines Power Block 3, had identified the least cost

1795alternative compared to other options, including outside

1802proposals from third parties. There are no cost effective

1811co nservation measures available that might mitigate PEF's need

1820for Hines Power Block 3. In conclusion, the Florida Public

1830Service Commission determined that PEF met the statutory

1838requirements under Section 403.519, Florida Statutes, for the

1846Commission to gr ant the determination of need for Hines Power

1857Block 3.

1859PROJECT SCHEDULE AND CONSTRUCTION

18639. The proposed Power Block 3 is very similar both to the

1875existing Hines Power Block 1 and to Power Block 2, which is

1887currently under construction at the Hines site. The proposed

1896combustion turbines for the new unit are from the same

1906manufacturer, Siemens Westinghouse. Due to normal upgrades in

1914those combustion turbines, they will be able to produce slightly

1924more electrical energy. Engineering of the units will com mence

1934in August 2003, and on - site construction will begin no later

1946than the first quarter of 2004. The new unit is proposed to be

1959in service by December 1, 2005.

196510. Construction activities will be initiated by the

1973preparation of the five - acre site for construction. This will

1984include mobilization of contractors and subcontractors along

1991with plant construction personnel. Existing construction lay

1998down and parking areas will be utilized for Power Block 3. On -

2011site construction will begin with the instal lation of the

2021circulating water piping and pilings for structural foundations.

2029Power Block 3 will be mechanically complete by August 2005.

203911. The construction workforce for Power Block 3 is

2048expected to average about 145 employees over the two - year

2059con struction period. Peak construction employment is estimated

2067at 350 employees. The construction payroll is expected to be

2077$15 million annually. Based upon prior experience during

2085construction of Power Blocks 1 and 2, it is expected that most

2097construction workers will be drawn from the Polk County and the

2108central Florida area. Construction employees are expected to

2116commute daily to the job site. Approximately 10 - 15 percent of

2128total material and equipment purchases are expected to be made

2138in the central F lorida area, including Polk County.

214712. No new roads will be required to support construction

2157of Power Block 3 as the existing plant access road will be used

2170during construction. Major Project components will be delivered

2178to the Hines site by rail or b y truck. No off - site upgrade of

2194rail or road facilities is expected to be necessary. All

2204oversized deliveries will receive necessary Florida Department

2211of Transportation ("DOT") approvals.

221713. Most major earthwork activities for construction for

2225the P ower Block 3 construction area were performed during

2235initial site development activities that were completed in 1996.

2244There are no expected impacts to land in the Project area except

2256for minor grading.

225914. Heavily loaded and structural foundation loads such as

2268the heat recovery steam generators, combustion turbines, steam

2276turbines, and step up transformers will be supported by deep

2286foundations. These foundations would include deep foundations

2293such as pilings similar to that used for Power Blocks 1 and 2.

2306Lightly loaded foundations will use spread foundations.

2313Construction dewatering will occur primarily at excavations for

2321the circulating water intake structure and the discharge

2329structure in the cooling pond. Other additional limited

2337dewatering may oc cur depending upon the amount of rainfall and

2348the depth of other excavations on - site. Dewatering would be

2359performed using well points or open pit sump pumps, which have a

2371very localized impact area. Any dewatering would all be within

2381the existing plant i sland area. Dewatering effluent will be

2391routed to the existing on - site stormwater collection ditches for

2402return to the existing cooling pond.

240815. The entire Project area is outside the 100 - year flood

2420zone. There will be no construction impacts to either on - site

2432or off - site water bodies or wetlands as a result of construction

2445activities.

244616. On - site construction activities will not cause

2455measurable adverse ecological effects. The five - acre Project

2464area has already been cleared and graded in anticipati on of

2475construction of Power Block 3 and other future units.

2484Vegetation coverage in these areas consists of maintained

2492grasslands of low ecological functional value. This habitat is

2501suitable for few animals and exhibits low plant species

2510diversity. It wi ll not support populations of threatened and

2520endangered species or species of special concern. There are no

2530state or federal jurisdictional wetlands that would be impacted

2539by the development of Power Block 3. Mitigation for wetland

2549impacts occurred as pa rt of the original permitting process for

2560the Hines Energy Complex.

256417. Construction noise impacts from construction of all

2572phases up to the 3000 MWs of ultimate site capacity were

2583analyzed as part of the 1992 certification application. It was

2593shown at that time that all of the applicable noise criteria

2604would be complied with during construction. An updated analysis

2613of construction noise reaffirmed the earlier analysis and

2621demonstrated no adverse impacts from construction noise. The

2629nearest residence i s approximately 2.5 miles from the plant

2639site. The Project construction noise levels will be less than

2649the existing noise levels measured near these residences.

2657Construction noise will have an insignificant effect on noise

2666levels.

266718. During construct ion, the most prevalent construction

2675air emissions will be fugitive dust, generated by site grading,

2685excavation, vehicular traffic, and other construction

2691activities. Dust control measures will be used and will

2700typically require moisture conditioning of c onstruction areas

2708and roadways. Disturbed areas will also be stabilized by

2717mulching or seeding as soon as practical. Crushed rock may also

2728be used in high traffic areas. It is not expected that these

2740air emissions from construction will present any sign ificant air

2750quality problems during the construction period.

2756PROJECT DESCRIPTION

275819. Power Block 3 will be similar to the existing Power

2769Blocks 1 and 2 at the Hines site. Power Block 3 is a new

2783combined cycle unit of approximately 530 MWs. It will consi st

2794of two advanced Siemens Westinghouse combustion turbines ("CT")

2804designed for dual fuel operation. Each CT will connect to an

2815electrical generator, capable of generating approximately 170

2822MWs of electricity. Each CT in Power Block 3 will be paired

2834with a heat recovery steam generator ("HRSG") which will extract

2846heat energy from the CT's exhaust gas. The HRSG is essentially

2857a boiler that turns heat in the CT's exhaust, which would be

2869otherwise wasted, into steam. The steam produced in both HRSGs

2879is use d to drive a single steam turbine, which will produce an

2892additional 190 MWs of electricity.

289720. The normal operating mode for Power Block 3 will be

2908for both CTs to be in operation providing steam from their

2919respective HRSGs to the single steam turbine. However, Power

2928Block 3 can be operated in other ways, depending on the need for

2941electricity. One CT can be operated at full load producing

2951steam from its HRSG that would power the steam turbine at half

2963load while the other CT and HRSG are idle. The unit will be

2976operated between 30 percent load and full load in the combined

2987cycle mode while meeting its air emission permit requirements.

2996The modern combined cycle power plant is one of the most

3007efficient power cycles available today.

301221. Natural gas will be the primary fuel used in Power

3023Block 3. Gas will be delivered by the existing gas pipelines

3034that serve the Hines Energy Complex. Fuel oil will be delivered

3045by truck to the existing fuel unloading facilities and stored in

3056the existing on - site fuel sto rage tanks.

306522. The existing on - site electrical switchyard will be

3075expanded to provide electrical transmission interconnection for

3082Power Block 3. No new off - site transmission lines will be

3094required for Power Block 3.

309923. Pursuant to the authorization under the 1994 site

3108certification, a 10,000 gallon per day domestic wastewater

3117treatment plant will treat any additional on - site domestic and

3128sanitary wastewaters from on - site showers, lavatories, toilets,

3137and drinking fountains. The treated effluent is directed to the

3147on - site cooling pond. Potable water is provided from an

3158existing on - site approved potable water system which is adequate

3169to support Power Blocks 1, 2 and 3. Potable water is supplied

3181from well water and is treated and chlorinated for on - s ite uses

3195such as drinking, washing, showers, and other uses.

320324. Solid wastes that may be generated by Power Block 3

3214include circulating water system screenings, sanitary waste

3221solids, water treatment filter backwash solids, office solid

3229wastes, and sol id wastes produced in the course of operating and

3241maintaining the unit. Office wastes are expected to be the

3251biggest component of these wastes. These wastes will be

3260disposed of in differing ways. Circulating water system

3268screenings will be recycled on - s ite to the extent possible. All

3281other solid wastes will be disposed of off - site in appropriate

3293facilities. PEF has a corporate commitment to waste

3301minimization. This includes extensive recycling of waste

3308products, reduction at the source, and eliminatio n of most

3318hazardous waste storage. This corporate commitment will be

3326implemented on a continuing basis at the Hines Energy Complex.

3336WATER USE AND SUPPLY

334025. The steam in the steam turbine is cooled to the liquid

3352state in a steam condenser. The rejecte d heat from the steam is

3365transferred to water pumped from the existing cooling pond into

3375the circulating water system and then returned to the cooling

3385pond. The heat rejected from the power plant results in forced

3396evaporation above and beyond the natural evaporation that occurs

3405in the cooling pond. The circulating water system equipment for

3415Power Block 3 will include two new circulating water pumps

3425capable of pumping 60,000 gallons per minute. An additional

3435intake structure will be constructed at the coo ling pond to

3446support these pumps. A new discharge structure will also be

3456constructed in the cooling pond. There will be no need to

3467expand the size of the cooling pond to accommodate Power

3477Block 3.

347926. The existing 722 - acre cooling pond will supply cooli ng

3491water and other water needs for Power Block 3. All process

3502water needs for Power Block 3 will be supplied from the existing

3514cooling pond. Water is pumped from the pond to the existing

3525water treatment area east of Power Block 1. The water is

3536processed for use either as service water or as demineralized

3546water. Service water is used for washdown of equipment and

3556other uses. The higher quality demineralized water is used for

3566makeup to the steam - condensate - feedwater cycle in the HRSGs to

3579replace steam cy cle losses. Demineralized water is also used

3589when firing low sulfur fuel oil in the CTs to control nitrogen

3601oxide (NO x ) emissions.

360627. The reverse osmosis equipment in the demineralized

3614water system produces a brine reject that will be pumped to the

3626ex isting on - site brine pond. The other wastewater streams from

3638Power Block 3 will come from the boiler blowdown and from floor

3650drains located throughout the facility. Boiler blowdown results

3658from removal of a portion of the water cycling in the HRSG to

3671con trol the buildup of solids in that water. Boiler blowdown is

3683collected and pumped back to the cooling pond without further

3693treatment. Areas that contain lubricating oil equipment or

3701where fuel lines run above ground will have containment curbs or

3712walls. Wastewater streams from these areas that may contain oil

3722will be routed to the existing oil water separator to remove oil

3734contamination prior to being pumped to the cooling pond. Any

3744collected oil will be properly disposed. All wastewaters will

3753be colle cted and processed as appropriate and pumped back to the

3765cooling pond. The cooling pond has no discharge to area surface

3776waters.

377728. The cooling pond at the Hines Energy Complex

3786experiences both natural and forced evaporation. The forced

3794evaporation is that additional evaporation above and beyond

3802natural evaporation and is caused by the heat rejected from the

3813power plant. The total annual average evaporation rate from the

3823cooling pond from natural evaporation and from heat rejected by

3833Power Blocks 1, 2 and the proposed Power Block 3 is

3844approximately 9.3 million gallons per day. This includes an

3853increase in evaporation of 2.2 million gallons per day for Power

3864Block 3. This loss of water needs to be replenished to keep the

3877cooling pond operating and keep the plant continuing in

3886operation.

388729. It has been determined that, over the long term, Power

3898Block 3 will require an average annual daily water supply of 2.6

3910million gallons per day, and a peak monthly water supply need of

39224.4 million gallons per day. This is needed to replace

3932evaporation from the pond and to supply the process water needs

3943for the new unit. The existing Conditions of Certification for

3953the Hines Energy Complex authorize the use of at least 5 million

3965gallons per day of groundwater begi nning with the third

3975generating unit at the Hines Energy Complex. The existing Units

39851 and 2 utilize a mix of treated wastewater from on - site and

3999off - site sources and captured rainfall to supply cooling and

4010process water needs for Power Blocks 1 and 2. T he water needs

4023for Power Block 3 will be supplied from these previously

4033approved quantities of groundwater. The water will be pumped

4042from the Upper Floridan Aquifer from two new on - site wells

4054located south of the cooling pond. They will be spaced to

4065mini mize interference during simultaneous pumping operations.

4072The wells will have a diameter of 20 inches and the casing will

4085be set to a depth of 360 feet below land surface. The total

4098depth of these two production wells will be 880 feet below land

4110surface.

411130. Under the proposed Conditions of Certification, no

4119groundwater will be withdrawn to supplement the cooling pond

4128until the operating level in the cooling pond falls to 160 feet

4140and the water that is stored in the on - site water cropping areas

4154have be en depleted. The normal pond operating level is proposed

4165to range between 159 and 163 feet above National Geodetic

4175Vertical Datum ("NGVD"). The proposed on - site withdrawals were

4187previously evaluated as part of the initial certification

4195proceeding in 1994 , and were found to have no adverse impacts.

4206The proposed on - site withdrawals for Power Block 3 will not have

4219any adverse impacts on existing legal users of water in the

4230vicinity of the Project. PEF has investigated other reasonably

4239obtainable sources of water in the region and found none that

4250could meet the needs for Power Block 3 beginning in November

42612005, when the unit is to begin operation.

426931. PEF has undertaken several efforts to minimize the use

4279of groundwater through the use of water conservat ion practices,

4289as required by the Conditions of Certification in the 1994 site

4300certification. These measures include the use of combined cycle

4309combustion turbine design that uses water conserving electric

4317generation technologies, retention of any dewateri ng effluents

4325on - site, on - site rainwater and stormwater capture and reuse in

4338the cooling pond, return of internal wastewater streams to the

4348cooling pond for reuse, and reuse of treated wastewater from

4358sewage treatment facilities.

436132. Power Blocks 1 and 2 are supplied water from the on -

4374site water cropping system, and on - site and off - site treated

4387wastewaters. The capture and reuse of rainfall is an integrated

4397part of PEF's efforts to reduce dependence on the Upper Floridan

4408Aquifer as a source of water. In the water cropping system,

4419precipitation that falls within the dams in the water cropping

4429areas of the Hines Energy Complex will be captured, temporarily

4439stored and routed to the cooling pond as needed. This captured

4450rainfall is used to make up for evapo rative losses. In

4461addition, recycled plant wastewaters and treated wastewater from

4469the City of Bartow are the other primary sources of water for

4481Hines Power Blocks 1 and 2. The City of Bartow currently

4492provides approximately 1.7 million gallons per day o f treated

4502wastewater for use at the Hines Energy Complex.

451033. PEF is also pursuing other activities for the

4519potential development of water resources at the Hines Energy

4528Complex. This involves preparing an integrated water supply

4536plan for the site. The plan will be incorporated into the site

4548certification through separate modification requests. One

4554component of this plan is an aquifer recharge and recovery

4564project ("ARRP"). This Project will take stormwater and

4574reclaimed effluent and provide additiona l on - site treatment to

4585comply with FDEP's groundwater standards. The treatment will

4593take place in on - site treatment wetlands and sand filters. Once

4605treated, the water would be injected into the Floridan Aquifer

4615through an on - site recharge well for later use at the Hines

4628Energy Complex and for aquifer enhancement. Under this

4636proposal, PEF would withdraw 85 percent of the total water

4646injected into the aquifer; the remaining 15 percent will not be

4657withdrawn in order to provide water resource enhancement to the

4667aquifer. PEF will also continue to investigate and report to

4677the Southwest Florida Water Management District on evaluation of

4686alternative sources of reclaimed water and of the feasibility of

4696using brackish groundwater resources to minimize the use of

4705fresh groundwater resources.

4708AIR EMISSIONS

471034. The primary air pollutants emitted from Hines Power

4719Block 3 will include nitrogen oxides ("NO x "), carbon monoxide

4731("CO"), volatile organic compounds ("VOC"), particulate matter

4742("PM"), and sulfur oxides suc h as sulfur dioxide. The primary

4755cause of the air emissions from the new unit will be the

4767combustion of natural gas and distillate or light oil in the

4778CTs. Emissions of NO x , CO, and VOC will result from the

4790combustion process. Emissions of PM and sulfur dioxide result

4799from trace impurities in the fuel itself.

480635. Air emissions from Power Block 3 will be minimized

4816through the inherent efficiency of the combined cycle

4824technology, as well as the use of natural gas and light oil, use

4837of combustion control s, and use of post - combustion control

4848technology for nitrogen oxide emissions. Natural gas is the

4857cleanest of fossil fuels and contains minimal amounts of

4866impurities. Light oil is also very low in impurities and its

4877use will be limited to up to 720 hours per year per combustion

4890turbine. Natural gas and light oil burn very efficiently, thus

4900minimizing the formation of air pollutants. Emissions are also

4909minimized through the use of advanced combustion control

4917technology in the combustion turbine, specific ally dry, low NO x

4928combustion controls for firing natural gas, and use of water

4938injection when firing light oil. A post - combustion control

4948technology, selective catalytic reduction ("SCR") will be used

4958to further reduce NO x emissions from Power Block 3.

496836. The Hines Power Block 3 is required to meet federal

4979and state new source performance standards ("NSPS") and best

4990available control technology ("BACT") requirements, both of

4999which limit air pollution emission rates. The Project m ust also

5010comply with ambient air quality standards ("AAQS") and

5020prevention of significant deterioration ("PSD") increment

5028standards, which establish levels of air quality which must be

5038met.

503937. Hines Power Block 3 is required to undergo PSD review

5050because it is a new source of air pollution that will emit some

5063air pollutants above the threshold amounts established under the

5072PSD program. PSD review was required for air emissions of PM,

5083sulfur dioxide, NO x , CO, VOC, and sulfuric acid mist because

5094these emis sions are greater than the established PSD thresholds.

5104FDEP has independently prepared a draft PSD review for Power

5114Block 3 that will be addressed in FDEP's separately - issued PSD

5126permit for the Project.

513038. The BACT analysis for Hines Power Block 3 is part of

5142the evaluation of air emissions control technology under the PSD

5152regulations and is applicable to all pollutants for which PSD

5162review is required. BACT is a pollutant - specific emission

5172standard that provides the maximum degree of emission reductio n,

5182after taking into account the energy, environmental, and

5190economic impacts and other costs. A BACT analysis is performed

5200first by identifying available and technically feasible emission

5208control alternatives and then evaluating their degree of

5216emission r eduction, costs and adverse impacts. The BACT limit

5226arrived at for each pollutant is the most stringent degree of

5237emission control that is not rejected on the basis of economic,

5248energy, environmental or other technical grounds.

525439. For NO x , in its sep arate draft PSD analysis, FDEP has

5267preliminarily determined for this facility a BACT emission limit

5276of 2.5 parts per million when firing natural gas, and 10 parts

5288per million when firing low sulfur fuel oil. These emission

5298levels will be achieved by the u se of dry low NO x combustion

5312technology when firing natural gas, use of water injection when

5322firing fuel oil, and use of SCR technology. These limits are

5333equivalent to emission limits established on other similar units

5342in Florida.

534440. For emissions of carbon monoxide, in its PSD analysis,

5354FDEP preliminarily has determined for this facility, a BACT

5363limit of 10 parts per million during natural gas firing and 20

5375parts per million during oil firing, which will be achieved

5385using good combustion techniques.

538941. In its preliminary PSD analysis, FDEP has determined

5398for this facility that sulfur dioxide emissions, including

5406sulfuric acid mist, will be controlled through the use of clean

5417fuels. In its draft PSD analysis, FDEP has also determined for

5428this fac ility that BACT limits for particulate matter for Power

5439Block 3 will be achieved through the use of clean fuels, natural

5451gas and low sulfur fuel oil.

545742. Fuel oil firing will be limited to a maximum of about

5469720 hours per year. For VOC, emissions will be controlled using

5480good combustion, and in its PSD analysis, FDEP has determined

5490preliminarily for this facility that BACT limits will be 2 parts

5501per million during gas firing and 10 parts per million when

5512firing low sulfur fuel oil.

551743. The air emissi ons from Power Block 3 cannot be

5528permitted at a level that would cause or contribute to a

5539violation of federal and state AAQS for the six criteria air

5550pollutants or PSD increments for sulfur dioxide, NO x and PM. The

5562PSD increments refer to the amount of i ncremental air quality

5573deterioration allowed from a new air pollution source. Polk

5582County is classified as a Class II area for PSD purposes. The

5594nearest Class I PSD area within which limited increases in air

5605pollutant concentrations are allowed is the Ch assahowitzka

5613National Wilderness Area.

561644. Air emissions from Power Block 3 were principally

5625analyzed for emissions from fuel oil firing as representing the

5635maximum air quality impact. The air quality impact analysis was

5645performed using approved air qu ality models and indicated that

5655Power Block 3 will not cause any violations of federal or state

5667AAQS and will comply with applicable PSD Class II and Class I

5679increments. The maximum impact of the Project was estimated to

5689be well below the applicable PSD C lass II increments. Maximum

5700ambient air impacts were also estimated to be well below the

5711applicable ambient air quality standards. Using worst case air

5720emissions during oil firing, it was shown that the Project

5730impacts would be less than the PSD Class I increments, as well

5742as less than the Class I significant impact levels, and

5752therefore were concluded to not be significant in the PSD Class

5763I area.

576545. Air emissions from Power Block 3 are not expected to

5776have any impact on vegetation or to cause any gr owth - related air

5790quality impacts. The results of the visibility impact analysis

5799of the Project's emissions in the nearest Class I area

5809demonstrated no adverse impact on visibility at that location

5818due to Power Block 3.

5823NOISE

582446. Noise impacts during c onstruction and operation of

5833Power Block 3 were shown not to be significant, and the expected

5845increase in noise will be below levels noticeable by human

5855hearing. Noise monitoring was originally conducted at various

5863locations around the Hines Energy Comple x site prior to

5873construction and operation of Power Block 1. Additional noise

5882monitoring was conducted at these locations in 2000 during the

5892permitting of Power Block 2, to determine any changes since the

5903original permitting. There are only a few isolate d rural

5913residences in the land area surrounding the site. The nearest

5923residence is about 2.5 miles from the proposed Power Block.

5933Mining activities in the surrounding area result in considerable

5942traffic on nearby roads, causing noise levels to exceed the EPA

5953guideline of 55 decibels ("dBa"). Without the area traffic,

5964noise levels meet the EPA guidelines. Using a conservative

5973approach which tends to overstate the Project impacts, noise

5982impacts due to Power Block 3 would increase by less than 1 dBa

5995at the nearest receptor and will not be significant. Similar

6005noise level increases were predicted for plant construction.

6013Therefore, the Project will meet applicable noise criteria and

6022no significant noise impacts will occur as a result of the

6033Project.

6034LAND U SE AND SOCIOECONOMIC IMPACTS

604047. The Plant Island, where Power Block 1 is in operation

6051and where Power Block 3 will be constructed, is located near the

6063southern end of the site.

606848. The northern boundary of the Plant Island is about two

6079miles south of CR 640. The western limit of the City of Fort

6092Meade is about 3.5 miles east of the Plant Island, and the

6104unincorporated community of Homeland is more than 2.5 miles

6113northeast of the Plant Island. The nearest residential use is

6123three homes located more th an 2.5 miles from the southern

6134boundary of the Plant Island. Otherwise, the entire area

6143surrounding the proposed power plant site consists of phosphate

6152mines.

615349. The site is buffered from surrounding populations at

6162Homeland and Fort Meade by an extens ive buffer area on the

6174eastern perimeter of the site.

617950. There has been almost no change in land use and very

6191little change in the landscape in the area of the Hines Energy

6203Complex since the original site certification.

620951. There have not been any cha nges in the area

6220surrounding the Hines Energy Complex that would change the land

6230use and socioeconomic conclusions reached in the Final Order of

6240Certification issued for the site by the Siting Board on

6250January 27, 1994.

625352. No land use or socioeconomic impacts will be

6262associated with construction of Power Block 3 that were not

6272previously addressed in the Final Order of Certification for the

6282Hines Energy Complex in 1994.

628753. The number of indirect jobs in Polk County resulting

6297from construction of Power Block 3 will be approximately 113.

6307These jobs will generate earnings of about $11 million. They

6317will primarily be in manufacturing of fabricated metal products,

6326retail trade, real estate, business services, and health

6334services sectors of the local econom y.

634154. The land use impacts from development of Power Block 2

6352will be quite minimal, and the economic benefits will be

6362substantial. Current operating employment at the Hines Energy

6370Complex is 29. The staffing level at the plant is expected to

6382increase by six employees with the addition of Power Block 3.

6393Annual payroll was $2.7 million in 2002. The annual payroll

6403will increase by about $500,000 (2002 dollars) when Power

6413Block 3 becomes operational in 2005.

641955. The estimated number of new indirect job s from the

6430operation of Power Block 3 is 10, generating earnings of

6440$458,000 per year. These jobs will primarily be in

6450construction, retail trade, real estate, business services and

6458health services sectors of the local economy.

646556. The estimated incre ase in property taxes for Power

6475Block 3 is $3.4 million. Over one - half of this revenue goes to

6489support the Polk County school system. Since Polk County is

6499required to provide very few services to the Hines Energy

6509Complex, the net benefit of these revenue s to the County and the

6522local school system is substantial.

6527AGENCY POSITIONS AND STIPULATIONS

653157. The FDEP, the Florida Department of Community Affairs

6540("DCA"), the FDOT, the Florida Fish and Wildlife Conservation

6551Commission, and the Southwest Florida Water Management District

6559each prepared written reports on the Project. Each of these

6569agencies either recommended approval of Hines Power Block 3 or

6579otherwise did not object to certification of the proposed power

6589plant. FDEP has proposed a series of Cond itions of

6599Certification for the Project that incorporate the

6606recommendations of the various reviewing agencies. PEF states

6614that it can comply with these Conditions of Certification in the

6625design, construction, and operation of the Hines Power Block 3.

6635No state, regional, or local agency has recommended denial of

6645certification of the Project or has otherwise objected to

6654certification of the Project.

6658CONCLUSIONS OF LAW

666158. The Division of Administrative Hearings has

6668jurisdiction over the parties to and the subject matter of this

6679proceeding. Section 403.508(3), Florida Statutes (2002)

668559. This proceeding was conducted to implement the purpose

6694and intent of the Florida Electrical Power Plant Site

6703Certification process. The purpose s of that process are to

6713assure the citizens of Florida that the construction and

6722operation safeguards of the PEF Hines Power Block 3 Project are

6733technically sufficient to protect their health and welfare and

6742to effect a reasonable balance between the need for the Project

6753and the environmental impacts on air and water quality, fish and

6764wildlife, and the water resources and other resources of the

6774State resulting from the Project's construction and operation.

6782Section 403.502(1) - (2), Florida Statutes

678860. In accordance with Chapters 120 and 403, Florida

6797Statutes, and Chapter 62 - 17, Florida Administrative Code, proper

6807public notice was accorded all persons, entities and parties

6816entitled thereto. All the necessary and required governmental

6824agencies were part ies to this proceeding or were otherwise

6834afforded adequate opportunity to participate in this proceeding.

6842All required reports by State, regional and local agencies were

6852completed and presented.

685561. The Florida Public Service Commission, in an order

6864d ated February 4, 2003, has determined a need exists for the 530

6877MW (nominal) of electrical generating capacity to be supplied by

6887the Project, pursuant to the requirements of Section 403.519,

6896Florida Statutes.

689862. The Governor and Cabinet of the State of Florida,

6908sitting as the Siting Board, determined in an order dated

6918January 26, 1993, that the Hines Energy Complex site is

6928consistent with the existing land use plans and zoning

6937ordinances of Polk County, pursuant to the procedures set out in

6948Section 403.5 08(1) and (2), Florida Statutes. Further

6956consideration of consistency with local land use plans and

6965zoning ordinances is not required for this Supplemental Site

6974Certification Application, pursuant to Section 403.517(3),

6980Florida Statutes.

698263. The Florida Department of Environmental Protection and

6990the other participating agencies have all recommended

6997certification of the Hines Power Block 3 for construction and

7007operation, subject to this Recommended Order and to the

7016conditions of certification recommended by FDEP. Progress

7023Energy Florida, the applicant, has indicated its acceptance of

7032these proposed conditions of certification. As a result, none

7041of the parties to this proceeding oppose certification of the

7051Hines Power Block 3.

705564. Based upon a preponder ance of the evidence presented

7065at the certification hearing held on May 12, 2003, Progress

7075Energy Florida has met its burden of proving that the Hines

7086Power Block 3 Project should be certified as proposed.

7095Competent substantial evidence presented at the h earing

7103demonstrates that the construction and operational safeguards

7110for the Hines Power Block 3 Project are technically sufficient

7120to protect the health and welfare of the citizens of Florida and

7132are reasonable and available methods to achieve that protec tion.

7142If constructed, maintained, and operated in accordance with this

7151Recommended Order and the FDEP's proposed Conditions of

7159Certification, incorporated herein by reference, the proposed

7166Project will produce minimal adverse effects on human health,

7175the environment, the ecology of the land and its wildlife, and

7186ecology of state waters and their aquatic life. Certification

7195of the Project is consistent with the statutory goal of the

7206Florida Electrical Power Plant Siting Act of providing abundant,

7215low cost electrical energy, and certification will effect a

7224reasonable balance between the environmental and other impacts

7232which might occur and the need for the Project as separately

7243determined by the Public Service Commission.

7249RECOMMENDATION

7250Based upon the foreg oing Findings of Fact and Conclusions

7260of Law, it is

7264RECOMMENDED that the Siting Board grant full and final

7273certification to Progress Energy Florida to construct and

7281operate a new 530 MW natural gas - fired electrical power plant in

7294Polk County, Florida, su bject to the conditions of certification

7304contained in FDEP Exhibit 2 and incorporated herein by

7313reference.

7314DONE AND ENTERED this 10th day of June, 2003, in

7324Tallahassee, Leon County, Florida.

7328___________________________________

7329CHARLES A. STAMPELOS

7332Adminis trative Law Judge

7336Division of Administrative Hearings

7340The DeSoto Building

73431230 Apalachee Parkway

7346Tallahassee, Florida 32399 - 3060

7351(850) 488 - 9675 SUNCOM 278 - 9675

7359Fax Filing (850) 921 - 6847

7365www.doah.state.fl.us

7366Filed with the Clerk of the

7372Division of Admin istrative Hearings

7377this 10th day of June, 2003.

7383COPIES FURNISHED :

7386Ross Stafford Burnaman, Esquire

7390Florida Fish and Wildlife

7394Conservation Commission

7396Bryant Building

7398620 South Meridian Street

7402Tallahassee, Florida 32399 - 1600

7407Michael Duclos, Esquire

7410Pol k County Attorney's Office

7415Post Office Box 9005

7419Bartow, Florida 33831 - 9005

7424Scott A. Goorland, Esquire

7428Department of Environmental Protection

74323900 Commonwealth Boulevard

7435Mail Station 35

7438Tallahassee, Florida 32399 - 3000

7443James McGee, Esquire

7446Florida Power Corporation

7449Post Office Box 14042

7453St. Petersburg, Florida 33733

7457Harold Mclean, General Counsel

7461Florida Public Service Commission

74652540 Shumard Oak Boulevard

7469Tallahassee, Florida 32399 - 0850

7474Martha A. Moore, Esquire

7478Southwest Florida Water Management Dist rict

74842379 Broad Street

7487Brooksville, Florida 34604 - 6899

7492Douglas S. Roberts, Esquire

7496Hopping Green & Sams, P.A.

7501123 South Calhoun Street

7505Post Office Box 6526

7509Tallahassee, Florida 32314

7512Norman White, Esquire

7515Central Florida Regional Planning Council

7520555 E ast Church Street

7525Bartow, Florida 33930

7528Sheauching Yu, Esquire

7531Department of Transportation

7534605 Suwannee Street

7537Haydon Burns Building, Mail Station 58

7543Tallahassee, Florida 32399 - 0458

7548David B. Struhs, Secretary

7552Department of Environmental Protection

7556390 0 Commonwealth Boulevard

7560Tallahassee, Florida 32399 - 3000

7565Teri L. Donaldson, General Counsel

7570Department of Environmental Protection

75743900 Commonwealth Boulevard

7577Mail Station 35

7580Tallahassee, Florida 32399 - 3000

7585Kathy C. Carter, Agency Clerk

7590Department of Environmental Protection

7594Office of the General Counsel

75993900 Commonwealth Boulevard

7602Mail Station 35

7605Tallahassee, Florida 32399 - 3000

7610NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

7616All parties have the right to submit written exceptions within

762615 days from the date of this Recommended Order. Any exceptions

7637to this Recommended Order should be filed with the agency that

7648will issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 09/15/2003
Proceedings: Final Order of Certification filed.
PDF:
Date: 09/12/2003
Proceedings: Agency Final Order
PDF:
Date: 06/10/2003
Proceedings: Recommended Order
PDF:
Date: 06/10/2003
Proceedings: Recommended Order (hearing held May 12, 2003). CASE CLOSED.
PDF:
Date: 06/10/2003
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 06/06/2003
Proceedings: Joint Proposed Recommended Order filed.
PDF:
Date: 06/06/2003
Proceedings: Notice of Filing Joint Proposed Recommended Order filed by D. Roberts.
Date: 05/29/2003
Proceedings: Transcript filed.
PDF:
Date: 05/29/2003
Proceedings: Notice of Filing Transcript of Certification Hearing filed by D. Roberts.
PDF:
Date: 05/15/2003
Proceedings: Affidavit Adopting Written Testimony filed by P. Crimi.
PDF:
Date: 05/15/2003
Proceedings: Notice of Filing Late Filed Exhibit filed by D. Roberts.
Date: 05/12/2003
Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
PDF:
Date: 05/07/2003
Proceedings: Notice of Filing Prepared Direct Testimony and Exhibits filed by D. Roberts.
PDF:
Date: 05/07/2003
Proceedings: (Joint) Pre-hearing Stipulation filed.
PDF:
Date: 05/05/2003
Proceedings: Stipulation Between Progress Energy Florida and the Department of Community Affairs filed by D. Roberts.
PDF:
Date: 04/29/2003
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Certification Hearing on Florida Power Corporation Hines Unit 3 Application to Construct and Operate an Electrical Power Plant filed by D. Roberts.
PDF:
Date: 04/11/2003
Proceedings: Electric Power Plant Site Certification Staff Analysis Report filed.
PDF:
Date: 04/11/2003
Proceedings: Department of Environmental Protection`s Notice of Filing of Written Analysis filed.
PDF:
Date: 03/19/2003
Proceedings: Notice of Hearing issued (hearing set for May 12 and 13, 2003; 10:00 a.m.; Bartow, FL).
PDF:
Date: 03/14/2003
Proceedings: Letter to Judge Alexander from D. Roberts regarding dates for site certification hearing (filed via facsimile).
PDF:
Date: 02/13/2003
Proceedings: Notice of Sufficiency of Power Plant Siting Supplemental Application (filed by S. Goorland via facsimile).
PDF:
Date: 01/27/2003
Proceedings: Order issued (the unnopposed Stipulation and Joint Motion for Alteration of Time Limits is granted, and the Revised Schedule of Significant Dates is approved).
PDF:
Date: 01/14/2003
Proceedings: Stipulation and Joint Motion for Alteration of Time Limits filed by D. Roberts.
PDF:
Date: 01/07/2003
Proceedings: Order issued. (the Southwest Florida Water Management District`s unopposed motion for extension of time to file Agency report is granted, and it shall have until February 28, 2003)
PDF:
Date: 01/03/2003
Proceedings: Southwest Florida Water Management District`s Motion for Extension of Time to File Agency Report (filed via facsimile).
PDF:
Date: 12/19/2002
Proceedings: Florida Power Corporation`s Notice of Filing Responses to Notice of Insufficiency of the Florida Department of Environmental Protection filed.
PDF:
Date: 11/22/2002
Proceedings: Florida Power Corporation`s Response to Florida Department of Environmental Protection`s Notice of Insufficiency filed.
PDF:
Date: 11/08/2002
Proceedings: Notice of Insufficiency (filed by S. Goorland via facsimile).
PDF:
Date: 11/01/2002
Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
PDF:
Date: 10/15/2002
Proceedings: Notice of Intent to be a Party (filed by SFWMD via facsimile).
PDF:
Date: 10/10/2002
Proceedings: Notice of Distribution of Supplemental Site Certification Application to PA 92-33 filed by D. Roberts.
PDF:
Date: 10/10/2002
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing Site Certification Application to PA 92-33 filed by D. Roberts.
PDF:
Date: 09/26/2002
Proceedings: Order issued. (motion granted)
PDF:
Date: 09/26/2002
Proceedings: Order issued. (motion for alteration of time limits, and stipulation for alteration of time limits is granted
PDF:
Date: 09/23/2002
Proceedings: Response to Initial Order (filed by S. Goorland via facsimile).
PDF:
Date: 09/19/2002
Proceedings: Schedule of Significant Dates, Motion for Alteration of Time Limits, and Stipulation for Alteration of Time Limits (filed by S. Goorland via facsimile).
PDF:
Date: 09/19/2002
Proceedings: Notice of Completeness of Power Plant Siting Supplemental Application (filed by S. Goorland via facsimile).
PDF:
Date: 09/17/2002
Proceedings: Notice of Filing of Site Certification Supplemental Application filed by S. Goorland.
PDF:
Date: 09/13/2002
Proceedings: Initial Order issued.
PDF:
Date: 09/10/2002
Proceedings: Notice of Filing of List of Affected Agencies (filed via facsimile).
PDF:
Date: 09/10/2002
Proceedings: Notice of Receipt of Power Plant Sitting Supplemental Application and Request for Assignment of Administrative Law Judge (filed via facsimile).

Case Information

Judge:
CHARLES A. STAMPELOS
Date Filed:
09/10/2002
Date Assignment:
05/06/2003
Last Docket Entry:
09/15/2003
Location:
Bartow, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
EPP
 

Counsels

Related Florida Statute(s) (5):