02-003529EPP
In Re: Florida Power Corporation Hines Energy Complex, Power Block 3, Power Plant Siting Supplemental Application No. Pa92-33sa2 vs.
*
Status: Closed
Recommended Order on Tuesday, June 10, 2003.
Recommended Order on Tuesday, June 10, 2003.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: FLORIDA POWER )
13CORPORATION HINES ENERGY )
17COMPLEX, POWER BLOCK 3, POWER )
23PLANT SITING SUPPLEMENTAL ) Case No. 02 - 3529EPP
32APPLICATION NO. PA92 - 33SA2. )
38)
39RECOMMENDED ORDER
41Pursuant to notice, the Division of Administrative
48Hearings, by its duly - designated Administrative Law Judge,
57Charles A. Stampelos, held a certification hearing in the above -
68styled case on May 12, 2003, in Bartow, Florida.
77APPEARANC ES
79For Progress Energy Florida (formerly known as Florida
87Power Corporation):
89Douglas S. Roberts, Esquire
93Hopping Green & Sams, P.A.
98123 South Calhoun Street
102Post Office Box 6526
106Tallahassee, Florida 32314
109For the Department of Environmental Prote ction:
116Scott A. Goorland, Esquire
120Department of Environmental Protection
1243900 Commonwealth Boulevard
127Mail Station 35
130Tallahassee, Florida 32399 - 3000
135For the Southwest Florida Water Management District:
142Martha A. Moore, Esquire
146Southwest Florida Water
149Management District
1512379 Broad Street
154Brooksville, Florida 34604 - 6899
159For Polk County:
162Michael Duclos, Esquire
165Polk County Attorney's Office
169Post Office Box 9005
173Bartow, Florida 33831 - 9005
178STATEMENT OF THE ISSUE
182The issue to be resolved in this proceeding is whether the
193Governor and Cabinet, sitting as the Siting Board, should issue
203certification to Progress Energy Florida ("PEF"), to construct
213and operate a new 530 megawatt ("MW") natural gas - fired
226electrical power plant in Polk County, Florida. The proposed
235site for the Project is located at Progress Energy Florida's
245existing Hines Energy Complex, southwest of Bartow, Florida.
253PRELIMINARY STATEMENT
255This proceeding was conducted pursuant to the Florida
263Electrical Power Plant Siting Act ("PPSA") , Chapter 403, Part
274II, Florida Statutes, and Chapter 62 - 17, Florida Administrative
284Code, to consider PEF's application for site certification for
293the proposed Hines Power Block 3 (also referred to as the
"304Project").
306On September 4, 2002, Florida Power Co rporation ("FPC" or
"317PEF") filed its Supplemental Application for site certification
326for the Hines Power Block 3 with the Florida Department of
337Environmental Protection ("Department" or "FDEP"). (On
345January 1, 2003, Florida Power Corporation changed its c orporate
355name to Progress Energy Florida ("PEF")). The application was
366found to be complete on September 19, 2002. The application was
377found to be sufficient on February 13, 2003.
385On February 4, 2003, the Florida Public Service Commission
394issued its Fin al Order determining the need for the proposed
405electrical power plant.
408On April 11, 2003, FDEP issued its written Staff Analysis
418Report concerning the Project, as required by Section
426403.507(4), Florida Statutes, incorporating the reports from
433other state and regional agencies and proposing a comprehensive
442set of proposed Conditions of Certification.
448On May 7, 2003, a joint prehearing stipulation was
457submitted to the undersigned, which indicated that no party to
467this proceeding objected to certification o f the Project.
476On May 12, 2003, during the certification hearing, FDEP
485submitted its revised Staff Analysis Report as FDEP Exhibit 2.
495After proper public notice by both PEF and by FDEP, a
506certification hearing was held in Bartow, Florida on May 12,
5162003, as required by Section 403.508(3), Florida Statutes. The
525purpose of the certification hearing was to receive oral,
534written, and documentary evidence concerning whether, through
541available and reasonable methods, the location and operation of
550the proposed Hines Power Block 3 would produce minimal adverse
560effects on human health, the environment, the ecology of the
570land and its wildlife, and the ecology of State waters and their
582aquatic life, in an effort to balance the increase in demand for
594an electrical p ower plant location and operation with the broad
605interests of the public. See Section 403.502, Florida Statutes.
614The hearing would have also considered any petitions challenging
623the separate FDEP - issued prevention of significant deterioration
632("PSD") per mit for the Project; however, no such petition was
645filed.
646At the certification hearing, PEF presented the oral
654testimony of three witnesses and had PEF exhibits numbered 1
664through 9, 11 and 12 admitted into evidence. These exhibits
674included the prefiled written testimony of three additional
682witnesses. That testimony was filed pursuant to Rule 62 -
69217.141(3), Florida Administrative Code. The prefiled written
699testimony has been accepted based upon execution of affidavits
708attesting to the accuracy of the tes timony and accompanying
718exhibits. FDEP presented the testimony of Hamilton S. Oven, of
728the FDEP's Siting Coordination Office, and had FDEP Exhibits 1
738and 2 admitted into evidence. No member of the public appeared
749at the hearing to offer testimony or othe r evidence on the
761Project.
762Subsequent to the certification hearing, PEF, upon
769authorization granted at the hearing, submitted its late - filed
779exhibit PEF - 10, representing the Affidavit of Paul V. Crimi,
790attesting to his prefiled written testimony and exhib its.
799Following the conclusion of the May 12, 2003 hearing, a
809transcript of the hearing was filed on May 29, 2003. The Joint
821Proposed Recommended Order of PEF, FDEP, Southwest Florida Water
830Management District ("SWFWMD"), and Polk County was timely
840submit ted and has been considered in the rendition of this
851Recommended Order.
853FINDINGS OF FACT
856BACKGROUND
8571. Progress Energy Florida, previously known as Florida
865Power Corporation, is an electric utility that provides
873electricity in a 32 - county service area in Florida, extending
884from the middle of the Panhandle down through the center of the
896state, including the west coast of Florida, north of Tampa Bay.
907PEF currently serves approximately 1.5 million customers in this
916service area. PEF has been providing elec tric service for over
927100 years, beginning in 1899 when it began business as the St.
939Petersburg Electric Light & Power Company. The Company's
947generating capacity has grown from an initial generation of 50
957kilowatts up to its total generating capacity toda y of
967approximately 8,586 megawatts. PEF has a customer growth rate
977of approximately two percent per year. The Company currently
986operates 14 different power plant facilities using a mix of
996natural gas, oil, coal, and nuclear power.
10032. The PEF Hines Ener gy Complex is located in the
1014southwest portion of Polk County, Florida, approximately 3.5
1022miles south of the city of Bartow. The unincorporated community
1032of Homeland lies about one mile to the northeast of the site
1044boundary. County Road 555 runs through the Project site. The
1054Hines site contains approximately 8,200 acres of reclaimed
1063phosphate mine lands. The site is located in a region of the
1075state dominated by phosphate mining operations, including mines,
1083settling ponds, sand tailings, gypsum stacks an d chemical
1092beneficiation plants. The adjacent land uses consist almost
1100entirely of active phosphate mining or reclaimed mine lands.
11093. The Hines Energy Complex was identified and purchased
1118by then Florida Power Corporation in the mid - 1990s. The site
1130was selected following a comprehensive process of locating a
1139suitable site for a large new generating facility. A systematic
1149site selection approach was undertaken to identify sites
1157suitable for multiple units which could accommodate potential
1165clean coal technology, be technology and fuel flexible, be cost
1175effective, be fully compatible with PEF's commitment to
1183environmental protection, be in compliance with applicable
1190government regulations, and be consistent with state and local
1199land use policies. At th at time, Florida Power Corporation
1209solicited the help of a team of community, educational and
1219environmental leaders to evaluate over 50 potential sites in
1228Florida and south Georgia. That two - year process culminated in
12391991 with the selection of the Hines site.
12474. In January 1994, the Siting Board certified the Hines
1257Energy Complex for an ultimate site capacity of 3,000 megawatts
1268of electrical generating capacity and also granted certification
1276for the construction and operation of an initial 470 MW combi ned
1288cycle unit known as Power Block 1. In 2001, the Siting Board
1300also granted certification for the construction and operation of
1309Hines Power Block 2, a 530 MW combined cycle unit, which is
1321currently under construction.
13245. The Hines Energy Complex con tains a number of existing
1335facilities and is divided into several major areas. The plant
1345island is the location for the existing and future power
1355generation facilities. It is approximately 704 acres. A 722 -
1365acre cooling pond has been constructed on the s ite, along with a
1378311 - acre brine pond. A buffer area has been created along the
1391eastern portion of the site containing approximately 2,128
1400acres. These areas serve as a wildlife corridor as well.
1410Approximately 4,000 acres of the site are designated for water
1421crop areas to supply captured rainfall for use in the power
1432plant.
14336. The Hines Energy Complex is served by an existing dual
1444circuit 230 kV transmission line that enters the Hines site from
1455the northwest. A second dual circuit 230 kV transmissio n line
1466departs the site heading due south. The existing transmission
1475lines are adequate to serve the new Power Block 3. Natural gas
1487is delivered to the Hines Energy Complex by two existing natural
1498gas pipelines, which will serve Power Blocks 1, 2 and 3. Fuel
1510oil is also burned in the existing units and is delivered by
1522truck and stored in an on - site storage tank. That tank is
1535adequate to serve the requirements of Power Block 3.
1544PROJECT OVERVIEW
15467. The Hines Power Block 3 is a 530 MW combined - cycle
1559pow er plant to be fueled primarily with natural gas. Fuel oil
1571will be used as a backup fuel. The proposed Power Block 3 will
1584be located entirely within the existing Hines Energy Complex
1593site. The unit will be located west of Power Blocks 1 and 2.
1606All cons truction activities for Power Block 3 will occur within
1617an approximately 5 - acre portion of the plant island.
1627NEED FOR POWER BLOCK 3
16328. On February 4, 2003, the Florida Public Service
1641Commission issued a Final Order determining the need for the
1651Progress Energy Florida's Hines Power Block 3 Project. The
1660Public Service Commission determined that the Hines Power
1668Block 3 will be needed by December 2005, to maintain electric
1679system reliability and integrity for PEF. This was based upon
1689an evaluation of PEF's load forecast and maintenance of its
1699required reserve margin of generating capacity above the firm
1708demand of PEF's customers. The Public Service Commission also
1717found that the Hines Power Block 3 will contribute to the
1728provision of adequate electricity at reasonable cost. The
1736Project was found to consist of a proven technology at
1746reasonable estimated cost. Construction at the Hines site also
1755allows PEF to take advantage of existing infrastructure at the
1765Hines Energy Complex, thereby saving PEF site devel opment costs.
1775The Public Service Commission also concluded that PEF, in
1784proposing the Hines Power Block 3, had identified the least cost
1795alternative compared to other options, including outside
1802proposals from third parties. There are no cost effective
1811co nservation measures available that might mitigate PEF's need
1820for Hines Power Block 3. In conclusion, the Florida Public
1830Service Commission determined that PEF met the statutory
1838requirements under Section 403.519, Florida Statutes, for the
1846Commission to gr ant the determination of need for Hines Power
1857Block 3.
1859PROJECT SCHEDULE AND CONSTRUCTION
18639. The proposed Power Block 3 is very similar both to the
1875existing Hines Power Block 1 and to Power Block 2, which is
1887currently under construction at the Hines site. The proposed
1896combustion turbines for the new unit are from the same
1906manufacturer, Siemens Westinghouse. Due to normal upgrades in
1914those combustion turbines, they will be able to produce slightly
1924more electrical energy. Engineering of the units will com mence
1934in August 2003, and on - site construction will begin no later
1946than the first quarter of 2004. The new unit is proposed to be
1959in service by December 1, 2005.
196510. Construction activities will be initiated by the
1973preparation of the five - acre site for construction. This will
1984include mobilization of contractors and subcontractors along
1991with plant construction personnel. Existing construction lay
1998down and parking areas will be utilized for Power Block 3. On -
2011site construction will begin with the instal lation of the
2021circulating water piping and pilings for structural foundations.
2029Power Block 3 will be mechanically complete by August 2005.
203911. The construction workforce for Power Block 3 is
2048expected to average about 145 employees over the two - year
2059con struction period. Peak construction employment is estimated
2067at 350 employees. The construction payroll is expected to be
2077$15 million annually. Based upon prior experience during
2085construction of Power Blocks 1 and 2, it is expected that most
2097construction workers will be drawn from the Polk County and the
2108central Florida area. Construction employees are expected to
2116commute daily to the job site. Approximately 10 - 15 percent of
2128total material and equipment purchases are expected to be made
2138in the central F lorida area, including Polk County.
214712. No new roads will be required to support construction
2157of Power Block 3 as the existing plant access road will be used
2170during construction. Major Project components will be delivered
2178to the Hines site by rail or b y truck. No off - site upgrade of
2194rail or road facilities is expected to be necessary. All
2204oversized deliveries will receive necessary Florida Department
2211of Transportation ("DOT") approvals.
221713. Most major earthwork activities for construction for
2225the P ower Block 3 construction area were performed during
2235initial site development activities that were completed in 1996.
2244There are no expected impacts to land in the Project area except
2256for minor grading.
225914. Heavily loaded and structural foundation loads such as
2268the heat recovery steam generators, combustion turbines, steam
2276turbines, and step up transformers will be supported by deep
2286foundations. These foundations would include deep foundations
2293such as pilings similar to that used for Power Blocks 1 and 2.
2306Lightly loaded foundations will use spread foundations.
2313Construction dewatering will occur primarily at excavations for
2321the circulating water intake structure and the discharge
2329structure in the cooling pond. Other additional limited
2337dewatering may oc cur depending upon the amount of rainfall and
2348the depth of other excavations on - site. Dewatering would be
2359performed using well points or open pit sump pumps, which have a
2371very localized impact area. Any dewatering would all be within
2381the existing plant i sland area. Dewatering effluent will be
2391routed to the existing on - site stormwater collection ditches for
2402return to the existing cooling pond.
240815. The entire Project area is outside the 100 - year flood
2420zone. There will be no construction impacts to either on - site
2432or off - site water bodies or wetlands as a result of construction
2445activities.
244616. On - site construction activities will not cause
2455measurable adverse ecological effects. The five - acre Project
2464area has already been cleared and graded in anticipati on of
2475construction of Power Block 3 and other future units.
2484Vegetation coverage in these areas consists of maintained
2492grasslands of low ecological functional value. This habitat is
2501suitable for few animals and exhibits low plant species
2510diversity. It wi ll not support populations of threatened and
2520endangered species or species of special concern. There are no
2530state or federal jurisdictional wetlands that would be impacted
2539by the development of Power Block 3. Mitigation for wetland
2549impacts occurred as pa rt of the original permitting process for
2560the Hines Energy Complex.
256417. Construction noise impacts from construction of all
2572phases up to the 3000 MWs of ultimate site capacity were
2583analyzed as part of the 1992 certification application. It was
2593shown at that time that all of the applicable noise criteria
2604would be complied with during construction. An updated analysis
2613of construction noise reaffirmed the earlier analysis and
2621demonstrated no adverse impacts from construction noise. The
2629nearest residence i s approximately 2.5 miles from the plant
2639site. The Project construction noise levels will be less than
2649the existing noise levels measured near these residences.
2657Construction noise will have an insignificant effect on noise
2666levels.
266718. During construct ion, the most prevalent construction
2675air emissions will be fugitive dust, generated by site grading,
2685excavation, vehicular traffic, and other construction
2691activities. Dust control measures will be used and will
2700typically require moisture conditioning of c onstruction areas
2708and roadways. Disturbed areas will also be stabilized by
2717mulching or seeding as soon as practical. Crushed rock may also
2728be used in high traffic areas. It is not expected that these
2740air emissions from construction will present any sign ificant air
2750quality problems during the construction period.
2756PROJECT DESCRIPTION
275819. Power Block 3 will be similar to the existing Power
2769Blocks 1 and 2 at the Hines site. Power Block 3 is a new
2783combined cycle unit of approximately 530 MWs. It will consi st
2794of two advanced Siemens Westinghouse combustion turbines ("CT")
2804designed for dual fuel operation. Each CT will connect to an
2815electrical generator, capable of generating approximately 170
2822MWs of electricity. Each CT in Power Block 3 will be paired
2834with a heat recovery steam generator ("HRSG") which will extract
2846heat energy from the CT's exhaust gas. The HRSG is essentially
2857a boiler that turns heat in the CT's exhaust, which would be
2869otherwise wasted, into steam. The steam produced in both HRSGs
2879is use d to drive a single steam turbine, which will produce an
2892additional 190 MWs of electricity.
289720. The normal operating mode for Power Block 3 will be
2908for both CTs to be in operation providing steam from their
2919respective HRSGs to the single steam turbine. However, Power
2928Block 3 can be operated in other ways, depending on the need for
2941electricity. One CT can be operated at full load producing
2951steam from its HRSG that would power the steam turbine at half
2963load while the other CT and HRSG are idle. The unit will be
2976operated between 30 percent load and full load in the combined
2987cycle mode while meeting its air emission permit requirements.
2996The modern combined cycle power plant is one of the most
3007efficient power cycles available today.
301221. Natural gas will be the primary fuel used in Power
3023Block 3. Gas will be delivered by the existing gas pipelines
3034that serve the Hines Energy Complex. Fuel oil will be delivered
3045by truck to the existing fuel unloading facilities and stored in
3056the existing on - site fuel sto rage tanks.
306522. The existing on - site electrical switchyard will be
3075expanded to provide electrical transmission interconnection for
3082Power Block 3. No new off - site transmission lines will be
3094required for Power Block 3.
309923. Pursuant to the authorization under the 1994 site
3108certification, a 10,000 gallon per day domestic wastewater
3117treatment plant will treat any additional on - site domestic and
3128sanitary wastewaters from on - site showers, lavatories, toilets,
3137and drinking fountains. The treated effluent is directed to the
3147on - site cooling pond. Potable water is provided from an
3158existing on - site approved potable water system which is adequate
3169to support Power Blocks 1, 2 and 3. Potable water is supplied
3181from well water and is treated and chlorinated for on - s ite uses
3195such as drinking, washing, showers, and other uses.
320324. Solid wastes that may be generated by Power Block 3
3214include circulating water system screenings, sanitary waste
3221solids, water treatment filter backwash solids, office solid
3229wastes, and sol id wastes produced in the course of operating and
3241maintaining the unit. Office wastes are expected to be the
3251biggest component of these wastes. These wastes will be
3260disposed of in differing ways. Circulating water system
3268screenings will be recycled on - s ite to the extent possible. All
3281other solid wastes will be disposed of off - site in appropriate
3293facilities. PEF has a corporate commitment to waste
3301minimization. This includes extensive recycling of waste
3308products, reduction at the source, and eliminatio n of most
3318hazardous waste storage. This corporate commitment will be
3326implemented on a continuing basis at the Hines Energy Complex.
3336WATER USE AND SUPPLY
334025. The steam in the steam turbine is cooled to the liquid
3352state in a steam condenser. The rejecte d heat from the steam is
3365transferred to water pumped from the existing cooling pond into
3375the circulating water system and then returned to the cooling
3385pond. The heat rejected from the power plant results in forced
3396evaporation above and beyond the natural evaporation that occurs
3405in the cooling pond. The circulating water system equipment for
3415Power Block 3 will include two new circulating water pumps
3425capable of pumping 60,000 gallons per minute. An additional
3435intake structure will be constructed at the coo ling pond to
3446support these pumps. A new discharge structure will also be
3456constructed in the cooling pond. There will be no need to
3467expand the size of the cooling pond to accommodate Power
3477Block 3.
347926. The existing 722 - acre cooling pond will supply cooli ng
3491water and other water needs for Power Block 3. All process
3502water needs for Power Block 3 will be supplied from the existing
3514cooling pond. Water is pumped from the pond to the existing
3525water treatment area east of Power Block 1. The water is
3536processed for use either as service water or as demineralized
3546water. Service water is used for washdown of equipment and
3556other uses. The higher quality demineralized water is used for
3566makeup to the steam - condensate - feedwater cycle in the HRSGs to
3579replace steam cy cle losses. Demineralized water is also used
3589when firing low sulfur fuel oil in the CTs to control nitrogen
3601oxide (NO x ) emissions.
360627. The reverse osmosis equipment in the demineralized
3614water system produces a brine reject that will be pumped to the
3626ex isting on - site brine pond. The other wastewater streams from
3638Power Block 3 will come from the boiler blowdown and from floor
3650drains located throughout the facility. Boiler blowdown results
3658from removal of a portion of the water cycling in the HRSG to
3671con trol the buildup of solids in that water. Boiler blowdown is
3683collected and pumped back to the cooling pond without further
3693treatment. Areas that contain lubricating oil equipment or
3701where fuel lines run above ground will have containment curbs or
3712walls. Wastewater streams from these areas that may contain oil
3722will be routed to the existing oil water separator to remove oil
3734contamination prior to being pumped to the cooling pond. Any
3744collected oil will be properly disposed. All wastewaters will
3753be colle cted and processed as appropriate and pumped back to the
3765cooling pond. The cooling pond has no discharge to area surface
3776waters.
377728. The cooling pond at the Hines Energy Complex
3786experiences both natural and forced evaporation. The forced
3794evaporation is that additional evaporation above and beyond
3802natural evaporation and is caused by the heat rejected from the
3813power plant. The total annual average evaporation rate from the
3823cooling pond from natural evaporation and from heat rejected by
3833Power Blocks 1, 2 and the proposed Power Block 3 is
3844approximately 9.3 million gallons per day. This includes an
3853increase in evaporation of 2.2 million gallons per day for Power
3864Block 3. This loss of water needs to be replenished to keep the
3877cooling pond operating and keep the plant continuing in
3886operation.
388729. It has been determined that, over the long term, Power
3898Block 3 will require an average annual daily water supply of 2.6
3910million gallons per day, and a peak monthly water supply need of
39224.4 million gallons per day. This is needed to replace
3932evaporation from the pond and to supply the process water needs
3943for the new unit. The existing Conditions of Certification for
3953the Hines Energy Complex authorize the use of at least 5 million
3965gallons per day of groundwater begi nning with the third
3975generating unit at the Hines Energy Complex. The existing Units
39851 and 2 utilize a mix of treated wastewater from on - site and
3999off - site sources and captured rainfall to supply cooling and
4010process water needs for Power Blocks 1 and 2. T he water needs
4023for Power Block 3 will be supplied from these previously
4033approved quantities of groundwater. The water will be pumped
4042from the Upper Floridan Aquifer from two new on - site wells
4054located south of the cooling pond. They will be spaced to
4065mini mize interference during simultaneous pumping operations.
4072The wells will have a diameter of 20 inches and the casing will
4085be set to a depth of 360 feet below land surface. The total
4098depth of these two production wells will be 880 feet below land
4110surface.
411130. Under the proposed Conditions of Certification, no
4119groundwater will be withdrawn to supplement the cooling pond
4128until the operating level in the cooling pond falls to 160 feet
4140and the water that is stored in the on - site water cropping areas
4154have be en depleted. The normal pond operating level is proposed
4165to range between 159 and 163 feet above National Geodetic
4175Vertical Datum ("NGVD"). The proposed on - site withdrawals were
4187previously evaluated as part of the initial certification
4195proceeding in 1994 , and were found to have no adverse impacts.
4206The proposed on - site withdrawals for Power Block 3 will not have
4219any adverse impacts on existing legal users of water in the
4230vicinity of the Project. PEF has investigated other reasonably
4239obtainable sources of water in the region and found none that
4250could meet the needs for Power Block 3 beginning in November
42612005, when the unit is to begin operation.
426931. PEF has undertaken several efforts to minimize the use
4279of groundwater through the use of water conservat ion practices,
4289as required by the Conditions of Certification in the 1994 site
4300certification. These measures include the use of combined cycle
4309combustion turbine design that uses water conserving electric
4317generation technologies, retention of any dewateri ng effluents
4325on - site, on - site rainwater and stormwater capture and reuse in
4338the cooling pond, return of internal wastewater streams to the
4348cooling pond for reuse, and reuse of treated wastewater from
4358sewage treatment facilities.
436132. Power Blocks 1 and 2 are supplied water from the on -
4374site water cropping system, and on - site and off - site treated
4387wastewaters. The capture and reuse of rainfall is an integrated
4397part of PEF's efforts to reduce dependence on the Upper Floridan
4408Aquifer as a source of water. In the water cropping system,
4419precipitation that falls within the dams in the water cropping
4429areas of the Hines Energy Complex will be captured, temporarily
4439stored and routed to the cooling pond as needed. This captured
4450rainfall is used to make up for evapo rative losses. In
4461addition, recycled plant wastewaters and treated wastewater from
4469the City of Bartow are the other primary sources of water for
4481Hines Power Blocks 1 and 2. The City of Bartow currently
4492provides approximately 1.7 million gallons per day o f treated
4502wastewater for use at the Hines Energy Complex.
451033. PEF is also pursuing other activities for the
4519potential development of water resources at the Hines Energy
4528Complex. This involves preparing an integrated water supply
4536plan for the site. The plan will be incorporated into the site
4548certification through separate modification requests. One
4554component of this plan is an aquifer recharge and recovery
4564project ("ARRP"). This Project will take stormwater and
4574reclaimed effluent and provide additiona l on - site treatment to
4585comply with FDEP's groundwater standards. The treatment will
4593take place in on - site treatment wetlands and sand filters. Once
4605treated, the water would be injected into the Floridan Aquifer
4615through an on - site recharge well for later use at the Hines
4628Energy Complex and for aquifer enhancement. Under this
4636proposal, PEF would withdraw 85 percent of the total water
4646injected into the aquifer; the remaining 15 percent will not be
4657withdrawn in order to provide water resource enhancement to the
4667aquifer. PEF will also continue to investigate and report to
4677the Southwest Florida Water Management District on evaluation of
4686alternative sources of reclaimed water and of the feasibility of
4696using brackish groundwater resources to minimize the use of
4705fresh groundwater resources.
4708AIR EMISSIONS
471034. The primary air pollutants emitted from Hines Power
4719Block 3 will include nitrogen oxides ("NO x "), carbon monoxide
4731("CO"), volatile organic compounds ("VOC"), particulate matter
4742("PM"), and sulfur oxides suc h as sulfur dioxide. The primary
4755cause of the air emissions from the new unit will be the
4767combustion of natural gas and distillate or light oil in the
4778CTs. Emissions of NO x , CO, and VOC will result from the
4790combustion process. Emissions of PM and sulfur dioxide result
4799from trace impurities in the fuel itself.
480635. Air emissions from Power Block 3 will be minimized
4816through the inherent efficiency of the combined cycle
4824technology, as well as the use of natural gas and light oil, use
4837of combustion control s, and use of post - combustion control
4848technology for nitrogen oxide emissions. Natural gas is the
4857cleanest of fossil fuels and contains minimal amounts of
4866impurities. Light oil is also very low in impurities and its
4877use will be limited to up to 720 hours per year per combustion
4890turbine. Natural gas and light oil burn very efficiently, thus
4900minimizing the formation of air pollutants. Emissions are also
4909minimized through the use of advanced combustion control
4917technology in the combustion turbine, specific ally dry, low NO x
4928combustion controls for firing natural gas, and use of water
4938injection when firing light oil. A post - combustion control
4948technology, selective catalytic reduction ("SCR") will be used
4958to further reduce NO x emissions from Power Block 3.
496836. The Hines Power Block 3 is required to meet federal
4979and state new source performance standards ("NSPS") and best
4990available control technology ("BACT") requirements, both of
4999which limit air pollution emission rates. The Project m ust also
5010comply with ambient air quality standards ("AAQS") and
5020prevention of significant deterioration ("PSD") increment
5028standards, which establish levels of air quality which must be
5038met.
503937. Hines Power Block 3 is required to undergo PSD review
5050because it is a new source of air pollution that will emit some
5063air pollutants above the threshold amounts established under the
5072PSD program. PSD review was required for air emissions of PM,
5083sulfur dioxide, NO x , CO, VOC, and sulfuric acid mist because
5094these emis sions are greater than the established PSD thresholds.
5104FDEP has independently prepared a draft PSD review for Power
5114Block 3 that will be addressed in FDEP's separately - issued PSD
5126permit for the Project.
513038. The BACT analysis for Hines Power Block 3 is part of
5142the evaluation of air emissions control technology under the PSD
5152regulations and is applicable to all pollutants for which PSD
5162review is required. BACT is a pollutant - specific emission
5172standard that provides the maximum degree of emission reductio n,
5182after taking into account the energy, environmental, and
5190economic impacts and other costs. A BACT analysis is performed
5200first by identifying available and technically feasible emission
5208control alternatives and then evaluating their degree of
5216emission r eduction, costs and adverse impacts. The BACT limit
5226arrived at for each pollutant is the most stringent degree of
5237emission control that is not rejected on the basis of economic,
5248energy, environmental or other technical grounds.
525439. For NO x , in its sep arate draft PSD analysis, FDEP has
5267preliminarily determined for this facility a BACT emission limit
5276of 2.5 parts per million when firing natural gas, and 10 parts
5288per million when firing low sulfur fuel oil. These emission
5298levels will be achieved by the u se of dry low NO x combustion
5312technology when firing natural gas, use of water injection when
5322firing fuel oil, and use of SCR technology. These limits are
5333equivalent to emission limits established on other similar units
5342in Florida.
534440. For emissions of carbon monoxide, in its PSD analysis,
5354FDEP preliminarily has determined for this facility, a BACT
5363limit of 10 parts per million during natural gas firing and 20
5375parts per million during oil firing, which will be achieved
5385using good combustion techniques.
538941. In its preliminary PSD analysis, FDEP has determined
5398for this facility that sulfur dioxide emissions, including
5406sulfuric acid mist, will be controlled through the use of clean
5417fuels. In its draft PSD analysis, FDEP has also determined for
5428this fac ility that BACT limits for particulate matter for Power
5439Block 3 will be achieved through the use of clean fuels, natural
5451gas and low sulfur fuel oil.
545742. Fuel oil firing will be limited to a maximum of about
5469720 hours per year. For VOC, emissions will be controlled using
5480good combustion, and in its PSD analysis, FDEP has determined
5490preliminarily for this facility that BACT limits will be 2 parts
5501per million during gas firing and 10 parts per million when
5512firing low sulfur fuel oil.
551743. The air emissi ons from Power Block 3 cannot be
5528permitted at a level that would cause or contribute to a
5539violation of federal and state AAQS for the six criteria air
5550pollutants or PSD increments for sulfur dioxide, NO x and PM. The
5562PSD increments refer to the amount of i ncremental air quality
5573deterioration allowed from a new air pollution source. Polk
5582County is classified as a Class II area for PSD purposes. The
5594nearest Class I PSD area within which limited increases in air
5605pollutant concentrations are allowed is the Ch assahowitzka
5613National Wilderness Area.
561644. Air emissions from Power Block 3 were principally
5625analyzed for emissions from fuel oil firing as representing the
5635maximum air quality impact. The air quality impact analysis was
5645performed using approved air qu ality models and indicated that
5655Power Block 3 will not cause any violations of federal or state
5667AAQS and will comply with applicable PSD Class II and Class I
5679increments. The maximum impact of the Project was estimated to
5689be well below the applicable PSD C lass II increments. Maximum
5700ambient air impacts were also estimated to be well below the
5711applicable ambient air quality standards. Using worst case air
5720emissions during oil firing, it was shown that the Project
5730impacts would be less than the PSD Class I increments, as well
5742as less than the Class I significant impact levels, and
5752therefore were concluded to not be significant in the PSD Class
5763I area.
576545. Air emissions from Power Block 3 are not expected to
5776have any impact on vegetation or to cause any gr owth - related air
5790quality impacts. The results of the visibility impact analysis
5799of the Project's emissions in the nearest Class I area
5809demonstrated no adverse impact on visibility at that location
5818due to Power Block 3.
5823NOISE
582446. Noise impacts during c onstruction and operation of
5833Power Block 3 were shown not to be significant, and the expected
5845increase in noise will be below levels noticeable by human
5855hearing. Noise monitoring was originally conducted at various
5863locations around the Hines Energy Comple x site prior to
5873construction and operation of Power Block 1. Additional noise
5882monitoring was conducted at these locations in 2000 during the
5892permitting of Power Block 2, to determine any changes since the
5903original permitting. There are only a few isolate d rural
5913residences in the land area surrounding the site. The nearest
5923residence is about 2.5 miles from the proposed Power Block.
5933Mining activities in the surrounding area result in considerable
5942traffic on nearby roads, causing noise levels to exceed the EPA
5953guideline of 55 decibels ("dBa"). Without the area traffic,
5964noise levels meet the EPA guidelines. Using a conservative
5973approach which tends to overstate the Project impacts, noise
5982impacts due to Power Block 3 would increase by less than 1 dBa
5995at the nearest receptor and will not be significant. Similar
6005noise level increases were predicted for plant construction.
6013Therefore, the Project will meet applicable noise criteria and
6022no significant noise impacts will occur as a result of the
6033Project.
6034LAND U SE AND SOCIOECONOMIC IMPACTS
604047. The Plant Island, where Power Block 1 is in operation
6051and where Power Block 3 will be constructed, is located near the
6063southern end of the site.
606848. The northern boundary of the Plant Island is about two
6079miles south of CR 640. The western limit of the City of Fort
6092Meade is about 3.5 miles east of the Plant Island, and the
6104unincorporated community of Homeland is more than 2.5 miles
6113northeast of the Plant Island. The nearest residential use is
6123three homes located more th an 2.5 miles from the southern
6134boundary of the Plant Island. Otherwise, the entire area
6143surrounding the proposed power plant site consists of phosphate
6152mines.
615349. The site is buffered from surrounding populations at
6162Homeland and Fort Meade by an extens ive buffer area on the
6174eastern perimeter of the site.
617950. There has been almost no change in land use and very
6191little change in the landscape in the area of the Hines Energy
6203Complex since the original site certification.
620951. There have not been any cha nges in the area
6220surrounding the Hines Energy Complex that would change the land
6230use and socioeconomic conclusions reached in the Final Order of
6240Certification issued for the site by the Siting Board on
6250January 27, 1994.
625352. No land use or socioeconomic impacts will be
6262associated with construction of Power Block 3 that were not
6272previously addressed in the Final Order of Certification for the
6282Hines Energy Complex in 1994.
628753. The number of indirect jobs in Polk County resulting
6297from construction of Power Block 3 will be approximately 113.
6307These jobs will generate earnings of about $11 million. They
6317will primarily be in manufacturing of fabricated metal products,
6326retail trade, real estate, business services, and health
6334services sectors of the local econom y.
634154. The land use impacts from development of Power Block 2
6352will be quite minimal, and the economic benefits will be
6362substantial. Current operating employment at the Hines Energy
6370Complex is 29. The staffing level at the plant is expected to
6382increase by six employees with the addition of Power Block 3.
6393Annual payroll was $2.7 million in 2002. The annual payroll
6403will increase by about $500,000 (2002 dollars) when Power
6413Block 3 becomes operational in 2005.
641955. The estimated number of new indirect job s from the
6430operation of Power Block 3 is 10, generating earnings of
6440$458,000 per year. These jobs will primarily be in
6450construction, retail trade, real estate, business services and
6458health services sectors of the local economy.
646556. The estimated incre ase in property taxes for Power
6475Block 3 is $3.4 million. Over one - half of this revenue goes to
6489support the Polk County school system. Since Polk County is
6499required to provide very few services to the Hines Energy
6509Complex, the net benefit of these revenue s to the County and the
6522local school system is substantial.
6527AGENCY POSITIONS AND STIPULATIONS
653157. The FDEP, the Florida Department of Community Affairs
6540("DCA"), the FDOT, the Florida Fish and Wildlife Conservation
6551Commission, and the Southwest Florida Water Management District
6559each prepared written reports on the Project. Each of these
6569agencies either recommended approval of Hines Power Block 3 or
6579otherwise did not object to certification of the proposed power
6589plant. FDEP has proposed a series of Cond itions of
6599Certification for the Project that incorporate the
6606recommendations of the various reviewing agencies. PEF states
6614that it can comply with these Conditions of Certification in the
6625design, construction, and operation of the Hines Power Block 3.
6635No state, regional, or local agency has recommended denial of
6645certification of the Project or has otherwise objected to
6654certification of the Project.
6658CONCLUSIONS OF LAW
666158. The Division of Administrative Hearings has
6668jurisdiction over the parties to and the subject matter of this
6679proceeding. Section 403.508(3), Florida Statutes (2002)
668559. This proceeding was conducted to implement the purpose
6694and intent of the Florida Electrical Power Plant Site
6703Certification process. The purpose s of that process are to
6713assure the citizens of Florida that the construction and
6722operation safeguards of the PEF Hines Power Block 3 Project are
6733technically sufficient to protect their health and welfare and
6742to effect a reasonable balance between the need for the Project
6753and the environmental impacts on air and water quality, fish and
6764wildlife, and the water resources and other resources of the
6774State resulting from the Project's construction and operation.
6782Section 403.502(1) - (2), Florida Statutes
678860. In accordance with Chapters 120 and 403, Florida
6797Statutes, and Chapter 62 - 17, Florida Administrative Code, proper
6807public notice was accorded all persons, entities and parties
6816entitled thereto. All the necessary and required governmental
6824agencies were part ies to this proceeding or were otherwise
6834afforded adequate opportunity to participate in this proceeding.
6842All required reports by State, regional and local agencies were
6852completed and presented.
685561. The Florida Public Service Commission, in an order
6864d ated February 4, 2003, has determined a need exists for the 530
6877MW (nominal) of electrical generating capacity to be supplied by
6887the Project, pursuant to the requirements of Section 403.519,
6896Florida Statutes.
689862. The Governor and Cabinet of the State of Florida,
6908sitting as the Siting Board, determined in an order dated
6918January 26, 1993, that the Hines Energy Complex site is
6928consistent with the existing land use plans and zoning
6937ordinances of Polk County, pursuant to the procedures set out in
6948Section 403.5 08(1) and (2), Florida Statutes. Further
6956consideration of consistency with local land use plans and
6965zoning ordinances is not required for this Supplemental Site
6974Certification Application, pursuant to Section 403.517(3),
6980Florida Statutes.
698263. The Florida Department of Environmental Protection and
6990the other participating agencies have all recommended
6997certification of the Hines Power Block 3 for construction and
7007operation, subject to this Recommended Order and to the
7016conditions of certification recommended by FDEP. Progress
7023Energy Florida, the applicant, has indicated its acceptance of
7032these proposed conditions of certification. As a result, none
7041of the parties to this proceeding oppose certification of the
7051Hines Power Block 3.
705564. Based upon a preponder ance of the evidence presented
7065at the certification hearing held on May 12, 2003, Progress
7075Energy Florida has met its burden of proving that the Hines
7086Power Block 3 Project should be certified as proposed.
7095Competent substantial evidence presented at the h earing
7103demonstrates that the construction and operational safeguards
7110for the Hines Power Block 3 Project are technically sufficient
7120to protect the health and welfare of the citizens of Florida and
7132are reasonable and available methods to achieve that protec tion.
7142If constructed, maintained, and operated in accordance with this
7151Recommended Order and the FDEP's proposed Conditions of
7159Certification, incorporated herein by reference, the proposed
7166Project will produce minimal adverse effects on human health,
7175the environment, the ecology of the land and its wildlife, and
7186ecology of state waters and their aquatic life. Certification
7195of the Project is consistent with the statutory goal of the
7206Florida Electrical Power Plant Siting Act of providing abundant,
7215low cost electrical energy, and certification will effect a
7224reasonable balance between the environmental and other impacts
7232which might occur and the need for the Project as separately
7243determined by the Public Service Commission.
7249RECOMMENDATION
7250Based upon the foreg oing Findings of Fact and Conclusions
7260of Law, it is
7264RECOMMENDED that the Siting Board grant full and final
7273certification to Progress Energy Florida to construct and
7281operate a new 530 MW natural gas - fired electrical power plant in
7294Polk County, Florida, su bject to the conditions of certification
7304contained in FDEP Exhibit 2 and incorporated herein by
7313reference.
7314DONE AND ENTERED this 10th day of June, 2003, in
7324Tallahassee, Leon County, Florida.
7328___________________________________
7329CHARLES A. STAMPELOS
7332Adminis trative Law Judge
7336Division of Administrative Hearings
7340The DeSoto Building
73431230 Apalachee Parkway
7346Tallahassee, Florida 32399 - 3060
7351(850) 488 - 9675 SUNCOM 278 - 9675
7359Fax Filing (850) 921 - 6847
7365www.doah.state.fl.us
7366Filed with the Clerk of the
7372Division of Admin istrative Hearings
7377this 10th day of June, 2003.
7383COPIES FURNISHED :
7386Ross Stafford Burnaman, Esquire
7390Florida Fish and Wildlife
7394Conservation Commission
7396Bryant Building
7398620 South Meridian Street
7402Tallahassee, Florida 32399 - 1600
7407Michael Duclos, Esquire
7410Pol k County Attorney's Office
7415Post Office Box 9005
7419Bartow, Florida 33831 - 9005
7424Scott A. Goorland, Esquire
7428Department of Environmental Protection
74323900 Commonwealth Boulevard
7435Mail Station 35
7438Tallahassee, Florida 32399 - 3000
7443James McGee, Esquire
7446Florida Power Corporation
7449Post Office Box 14042
7453St. Petersburg, Florida 33733
7457Harold Mclean, General Counsel
7461Florida Public Service Commission
74652540 Shumard Oak Boulevard
7469Tallahassee, Florida 32399 - 0850
7474Martha A. Moore, Esquire
7478Southwest Florida Water Management Dist rict
74842379 Broad Street
7487Brooksville, Florida 34604 - 6899
7492Douglas S. Roberts, Esquire
7496Hopping Green & Sams, P.A.
7501123 South Calhoun Street
7505Post Office Box 6526
7509Tallahassee, Florida 32314
7512Norman White, Esquire
7515Central Florida Regional Planning Council
7520555 E ast Church Street
7525Bartow, Florida 33930
7528Sheauching Yu, Esquire
7531Department of Transportation
7534605 Suwannee Street
7537Haydon Burns Building, Mail Station 58
7543Tallahassee, Florida 32399 - 0458
7548David B. Struhs, Secretary
7552Department of Environmental Protection
7556390 0 Commonwealth Boulevard
7560Tallahassee, Florida 32399 - 3000
7565Teri L. Donaldson, General Counsel
7570Department of Environmental Protection
75743900 Commonwealth Boulevard
7577Mail Station 35
7580Tallahassee, Florida 32399 - 3000
7585Kathy C. Carter, Agency Clerk
7590Department of Environmental Protection
7594Office of the General Counsel
75993900 Commonwealth Boulevard
7602Mail Station 35
7605Tallahassee, Florida 32399 - 3000
7610NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
7616All parties have the right to submit written exceptions within
762615 days from the date of this Recommended Order. Any exceptions
7637to this Recommended Order should be filed with the agency that
7648will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 06/10/2003
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 06/06/2003
- Proceedings: Notice of Filing Joint Proposed Recommended Order filed by D. Roberts.
- Date: 05/29/2003
- Proceedings: Transcript filed.
- PDF:
- Date: 05/29/2003
- Proceedings: Notice of Filing Transcript of Certification Hearing filed by D. Roberts.
- Date: 05/12/2003
- Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
- PDF:
- Date: 05/07/2003
- Proceedings: Notice of Filing Prepared Direct Testimony and Exhibits filed by D. Roberts.
- PDF:
- Date: 05/05/2003
- Proceedings: Stipulation Between Progress Energy Florida and the Department of Community Affairs filed by D. Roberts.
- PDF:
- Date: 04/29/2003
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Certification Hearing on Florida Power Corporation Hines Unit 3 Application to Construct and Operate an Electrical Power Plant filed by D. Roberts.
- PDF:
- Date: 04/11/2003
- Proceedings: Electric Power Plant Site Certification Staff Analysis Report filed.
- PDF:
- Date: 04/11/2003
- Proceedings: Department of Environmental Protection`s Notice of Filing of Written Analysis filed.
- PDF:
- Date: 03/19/2003
- Proceedings: Notice of Hearing issued (hearing set for May 12 and 13, 2003; 10:00 a.m.; Bartow, FL).
- PDF:
- Date: 03/14/2003
- Proceedings: Letter to Judge Alexander from D. Roberts regarding dates for site certification hearing (filed via facsimile).
- PDF:
- Date: 02/13/2003
- Proceedings: Notice of Sufficiency of Power Plant Siting Supplemental Application (filed by S. Goorland via facsimile).
- PDF:
- Date: 01/27/2003
- Proceedings: Order issued (the unnopposed Stipulation and Joint Motion for Alteration of Time Limits is granted, and the Revised Schedule of Significant Dates is approved).
- PDF:
- Date: 01/14/2003
- Proceedings: Stipulation and Joint Motion for Alteration of Time Limits filed by D. Roberts.
- PDF:
- Date: 01/07/2003
- Proceedings: Order issued. (the Southwest Florida Water Management District`s unopposed motion for extension of time to file Agency report is granted, and it shall have until February 28, 2003)
- PDF:
- Date: 01/03/2003
- Proceedings: Southwest Florida Water Management District`s Motion for Extension of Time to File Agency Report (filed via facsimile).
- PDF:
- Date: 12/19/2002
- Proceedings: Florida Power Corporation`s Notice of Filing Responses to Notice of Insufficiency of the Florida Department of Environmental Protection filed.
- PDF:
- Date: 11/22/2002
- Proceedings: Florida Power Corporation`s Response to Florida Department of Environmental Protection`s Notice of Insufficiency filed.
- PDF:
- Date: 11/01/2002
- Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
- PDF:
- Date: 10/10/2002
- Proceedings: Notice of Distribution of Supplemental Site Certification Application to PA 92-33 filed by D. Roberts.
- PDF:
- Date: 10/10/2002
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing Site Certification Application to PA 92-33 filed by D. Roberts.
- PDF:
- Date: 09/26/2002
- Proceedings: Order issued. (motion for alteration of time limits, and stipulation for alteration of time limits is granted
- PDF:
- Date: 09/19/2002
- Proceedings: Schedule of Significant Dates, Motion for Alteration of Time Limits, and Stipulation for Alteration of Time Limits (filed by S. Goorland via facsimile).
- PDF:
- Date: 09/19/2002
- Proceedings: Notice of Completeness of Power Plant Siting Supplemental Application (filed by S. Goorland via facsimile).
- PDF:
- Date: 09/17/2002
- Proceedings: Notice of Filing of Site Certification Supplemental Application filed by S. Goorland.
Case Information
- Judge:
- CHARLES A. STAMPELOS
- Date Filed:
- 09/10/2002
- Date Assignment:
- 05/06/2003
- Last Docket Entry:
- 09/15/2003
- Location:
- Bartow, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- EPP
Counsels
-
Ross Stafford Burnaman, Esquire
Address of Record -
Mark Carpanini, Esquire
Address of Record -
Scott A Goorland, Esquire
Address of Record -
James McGee, Esquire
Address of Record -
Harold McLean, Esquire
Address of Record -
Martha A. Moore, Esquire
Address of Record -
Carolyn S. Raepple, Esquire
Address of Record -
Colin M. Roopnarine, Esquire
Address of Record -
Norman White, Esquire
Address of Record -
Sheauching Yu, Esquire
Address of Record -
Scott A. Goorland, Esquire
Address of Record