02-003790BID Paul J. Sierra Construction, Inc. vs. Southwest Florida Water Management District
 Status: Closed
Recommended Order on Wednesday, December 4, 2002.


View Dockets  
Summary: Challenger failed to show that agency`s action in rejecting all proposals to achieve cost savings on project was arbitrary.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8PAUL J. SIERRA CONSTRUCTION, )

13INC., )

15)

16Petitioner, )

18)

19vs. ) Case No . 02 - 3790BID

27)

28SOUTHWEST FLORIDA WATER )

32MANAGEMENT DISTRICT, )

35)

36Respondent. )

38______________________________)

39RECOMMENDED ORDER

41This matter was heard before t he Division of

50Administrative Hearings by its assigned Administrative Law

57Judge, Donald R. Alexander, on October 22, 2002, in Tampa,

67Florida.

68APPEARANCES

69For Petitioner: Stephen H. Kurvin, Esquire

757 South Lime Avenue

79Sarasota, Florida 34237 - 6105

84For Respondent: Stephen O. Rushing, Esquire

90Mark F. Lapp, Esquire

942379 Broad Street

97Brooksville, Florida 34604 - 6899

102STATEMENT O F THE ISSUE

107The issue is whether Respondent's decision to reject all

116proposals on RFP No. 008 - 02 to design and build an ancillary

129building at the Tampa Service Office was arbitrary, as alleged

139by Petitioner.

141PRELIMINARY STATEMENT

143This matter began on Sep tember 3, 2002, when Respondent,

153Southwest Florida Water Management District, advised all

160proposers, including Petitioner, Paul J. Sierra Construction,

167Inc., that it intended to (1) reject all proposals on RFP No.

179008 - 02 to construct an ancillary building at its Tampa Service

191Center and (2) revise the scope of the project by combining

202the construction of the ancillary building with all other

211construction to be taken at the Tampa Service Center. On

221September 5, 2002, Petitioner filed a timely Notice of Prot est

232to the decision alleging that Respondent's action was

240arbitrary. A timely Formal Written Protest was then filed on

250September 12, 2002.

253After efforts by the parties to resolve the matter were

263unsuccessful, the matter was referred by Respondent to the

272Division of Administrative Hearings on September 27, 2002,

280with a request that an Administrative Law Judge be assigned to

291conduct a hearing. By Notice of Hearing dated October 1,

3012002, a final hearing was scheduled on October 22, 2002, in

312Tampa, Florida.

314At the final hearing, Petitioner presented the testimony

322of Robert Pellegrino, its division manager; Ricky M. Lawson,

331its assistant division manager; Steven M. Long, Mark Leytze,

340and Nicholas Spirakis, all employees of Respondent; and

348Enrique A. Woodruf f, the project architect. Also, it offered

358Petitioner's Exhibits 1 - 9. All were received in evidence

368except Exhibit 3. Respondent presented the testimony of Mark

377Leytze, a state certified contractor and manager of

385Respondent's construction projects, and Thomas G. Dabney, II,

393vice - chairman of the Governing Board. Also, it offered

403Respondent's Exhibits 2 - 8, 10, 11, and 13, which were received

415in evidence. Exhibit 2 is the video deposition of Ronnie E.

426Duncan, chairman of the Governing Board, and Exhibit 3 is the

437transcription of that deposition.

441The Transcript of the hearing was filed on November 10,

4512002. Proposed Findings of Fact and Conclusions of Law were

461filed by Respondent and Petitioner on November 20 and 27,

4712002, respectively, and they have been considered by the

480undersigned in the preparation of this Recommended Order.

488FINDINGS OF FACT

491Based upon all of the evidence, the following findings of

501fact are determined:

5041. On May 21, 2002, Respondent, Southwest Florida Water

513Management District (D istrict), through its contracts manager,

521issued an Invitation to Proposal inviting interested persons

529to submit competitive sealed proposals on Request for Proposal

538No. 008 - 02 (RFP No. 008), which called for the design and

551construction of an ancillary buil ding at its District Service

561Office (Tampa Service Center) located at 7601 Highway 301

570North, Tampa, Florida. The proposed facility is an

578approximately 5,000 square foot metal building which will

587house the District's field staff. The last paragraph of th e

598document provided that "[t]he District shall reserve the right

607to reject any or all bids/proposals received with or without

617cause."

6182. On May 24, 2002, the District placed an advertisement

628of its Invitation to Proposal in three local newspapers in

638Hil lsborough County. The last paragraph of each advertisement

647also provided that the District reserved the right to reject

657all bids with or without cause.

6633. A mandatory pre - proposal conference was held on

673June 6, 2002, which was attended by various inter ested

683persons, including Petitioner, Paul J. Sierra Construction,

690Inc. (Sierra), a large construction firm located in Tampa,

699Florida. Although Sierra engages in general construction, it

707also has a division which specializes in projects using Butler

717buildi ng systems. A Butler building utilizes a combination of

727a metal roof with a pre - engineered structural system.

7374. At the pre - proposal meeting, Sierra requested a copy

748of RFP No. 008 - 02, which contained the general conditions for

760the project, nature of the services required, insurance

768requirements, and evaluation procedures. Section 1.13 of that

776document provided in relevant part that "the District reserves

785the right to reject all proposals and not grant any award from

797the issuance of this RFP."

8025. Five proposals, including Sierra's, were received and

810opened on June 26, 2002. All proposals were reviewed and

820independently scored by a three - person selection committee

829composed of District staffers. Although Sierra's proposal of

837$374,038.00 was not the low est dollar amount submitted, it

848received the highest numerical score of 279, edging out two

858other proposers who both received scores of 277. The lowest

868dollar proposal submitted was $337,000.00.

8746. Under the process in place, the selection committee

883th en referred the results of its evaluation to a three - person

896Facilities Ad Hoc Committee (Committee), comprised of the

904Governing Board's chairman, Mr. Ronnie E. Duncan, the

912Governing Board's vice - chairman, Mr. Thomas D. Dabney, II, and

923the treasurer of the Governing Board, Watson L. Haynes, II.

933The Committee was delegated the authority to reject any

942proposal without further action by the District's Governing

950Board; however, approval of a proposal had to be confirmed by

961the Governing Board.

9647. Committee mem bers Duncan and Dabney are developers

973with extensive experience in construction while Mr. Haynes has

982a background in accounting. The Committee was formed in late

9922001 for the purpose of achieving more efficiencies in the

1002construction process, particularly in light of a newspaper's

1010criticism of the money spent by the District while renovating

1020Building 2 at its Brooksville office. The Committee was not

1030obligated to accept the selection committee scoring. Rather,

1038the Committee had a duty to make the ultimat e decision as to

1051how taxpayer dollars are best spent.

10578. The Committee met on July 30, 2002, to consider the

1068results of the evaluation. Mr. Haynes was not present. The

1078two other members voiced concerns regarding the cost of

1087Sierra's proposal, which wa s more than $74.00 per square foot.

1098For that reason, the Committee continued the decision on

1107awarding the contract to its next meeting on August 28, 2002.

1118It also requested the staff to determine how costs on the

1129project could be reduced.

11339. On July 31, 2002, Sierra contacted the District's

1142contract manager, Steven M. Long, by telephone and was told

1152that Sierra had received the highest ranking from the

1161selection committee, but that the Committee had postponed a

1170decision until its next meeting because of concerns over the

1180cost of the project.

118410. On August 28, 2002, the Committee reconvened. Due

1193to a personal conflict, Mr. Haynes was not present. By a 2 - 0

1207vote, the Committee determined that because of the cost

1216concerns, all proposals should be rejected, and that the 5,000

1227square foot ancillary building should be combined with two

1236other projects being undertaken at the Tampa Service Center

1245under a single construction manager to reduce costs and

1254realize other benefits. This decision was conveyed by

1262teleph one to Sierra on September 1, 2002.

127011. On September 3, 2002, formal Notice of Rejection

1279letters were sent to all five proposers. On September 5,

12892002, Sierra filed its Notice of Protest. This was followed

1299by a Formal Written Protest filed on September 12, 2002, in

1310which Sierra contended that the Committee's decision was

1318arbitrary.

131912. The Tampa Service Center is a branch office of the

1330District and includes office, technical, maintenance, and

1337garage facilities with accompanying parking and roadways.

1344Existing Building 1 is outdated, crowded, and inadequate and

1353must be replaced. It will be demolished once the new Building

13641 is constructed. Although the District initially decided

1372that the new building would need 30,000 square feet, it later

1384determined that the approximately 5,000 square feet needed to

1394house District field staff could be separated out as an

1404ancillary building from Building 1 and built as a metal

1414building. A preengineered metal building was selected since

1422it would be cheaper and faster to build, and some of the field

1435staff could be moved out of the crowded existing Building 1 to

1447the ancillary building while new Building 1 was being

1456constructed.

145713. In addition to the construction of the new Building

14671 and the ancillary building, the D istrict intends to re - roof

1480existing Building 2, demolish Building 1, re - route traffic

1490flow, install security gates, improve parking, improve the

1498stormwater system, and install new landscaping.

150414. As a general rule, as a project gets larger, there

1515are eco nomies of scale that result in cost reductions because

1526the cost per unit becomes less as a greater quantity is

1537purchased. In deciding to reject all proposals, and combine

1546all of the work at the Tampa Service Center, the Committee

1557considered the following advantages to having a construction

1565manager supervise the entire project:

1570a. It would reduce potential confusion by better

1578coordinating the number of contractors and subcontractors on

1586the job and create a more efficient work flow.

1595b. Task coordination is essential for safety since

1603District employees and members of the public will have

1612continuing access to the Tampa Service Center while all

1621components of the project are under construction.

1628c. There will be considerable underground construction

1635work for the installation of electrical lines, telephone

1643lines, computer cabling, water lines, fire protection water

1651service lines, sewer lines, irrigation lines, and stormwater

1659lines. Improved coordination reduces duplication and the

1666possibility of putting recen tly completed work at risk for

1676damage.

1677d. By working with the architect and the construction

1686manager, the District could use value engineering to reduce

1695costs. Value engineering would allow the District to look at

1705creative ways to reduce costs by subst ituting similar, less

1715expensive items for more expensive items.

1721e. Because the District is exempt from paying state

1730sales tax, the District would save the 7 percent sales tax

1741since the construction manager sets up accounts with vendors

1750directly for the District. The District would also save the

1760contractor's percentage markup that typically encompasses the

17677 percent sales tax when it has to be paid.

1777f. The construction manager system produces a better

1785selection process and cost savings since the const ruction

1794manager can be required to obtain at least three proposals for

1805each of the sixteen divisions of labor.

1812g. There will be benefits of accountability and

1820uniformity from having only one person or entity responsible

1829for any problems encountered.

183315 . In addition, the following savings could be realized

1843through economies of scale by including the ancillary building

1852in the larger project and under a construction manager:

1861mobilization; demobilization; site work; excavation for

1867foundation; concrete for foundation; rough - in electrical work;

1876rough - in plumbing; fire protection service line; electrical

1885lines; water lines; computer cabling lines; plumbing;

1892electrical; insulation; drywall; floor tile; ceiling grid;

1899ceiling tiles; doors; air conditioning syste m; painting;

1907landscaping; irrigation sprinkler system; paving work;

1913stormwater system; and one project manager.

191916. At the same time, when the earlier decision was made

1930to separate the construction of the ancillary building out

1939from the rest of the Tampa Service Center project to save time

1951and money, the Committee believed that the ancillary building

1960would obtain its utility and communication services from an

1969existing, adjacent building. After later learning that this

1977was not the case, and that the scope of the work for the

1990ancillary building had expanded to require considerable

1997underground site work for its new utility and communication

2006services, the Committee realized that the cost and other

2015benefits originally intended had been lost.

202117. Finally, new B uilding 1 is only sixty feet from the

2033ancillary building and will require considerable underground

2040site work for its new utility and communication services.

2049Therefore, the Committee concluded that it made more sense to

2059combine the construction of the new Building 1 and the

2069ancillary building to achieve cost savings and efficiencies in

2078the installation of utility and communication services and to

2087reduce other overlapping aspects of the Tampa Service Center

2096project.

209718. Given the foregoing considerations, t he Committee's

2105decision to reject all proposals was not arbitrary in any

2115sense. While it is true that the precise amount of savings to

2127be realized cannot be quantified, the greater weight of

2136evidence shows that some savings can be achieved, and that the

2147C ommittee's decision was based on facts, sound reasoning, and

2157logic.

2158CONCLUSIONS OF LAW

216119 . The Division of Administrative Hearings has

2169jurisdiction over the subject matter and the parties hereto

2178pursuant to Sections 120.569 and 120.57(3), Florida Statut es.

218720. Section 120.57(3)(f), Florida Statutes (2002),

2193governs this dispute and provides in relevant part as follows:

2203(f) In any bid - protest proceeding

2210contesting an intended agency action to

2216reject all bids, proposals, or replies, the

2223standard of revie w by an administrative law

2231judge shall be whether the agency's intended

2238action is illegal, arbitary, dishonest, or

2244fraudulent.

224521. Therefore, the District's decision to reject all

2253proposals, as it did here, will only be overturned if it is

2265arbitrary, i llegal, dishonest, or fraudulent. In this case,

2274Petitioner contends that the District's action was arbitrary.

228222. An arbitrary decision is one not supported by fact

2292or logic. Agrico Chemical Co. v. State Dep't of Envir. Reg. ,

2303365 So. 2d 759, 763 (Fla. 1 st DCA 1978). The inquiry to be

2317made in determining whether an agency has acted arbitrarily is

2327whether the agency has (1) considered all relevant factors;

2336(2) given actual, good faith consideration to those factors;

2345and (3) used reason rather than whim to progress from

2355consideration of those factors to its final decision. Adam

2364Smith Enterprises, Inc. v. State Dep't of Envir. Reg. , 553 So.

23752d 1260, 1273 (Fla. 1st DCA 1989). At the same time, if a

2388decision is justifiable under any analysis that a reasonabl e

2398person would use to reach a decision of similar importance,

2408the decision is not arbitrary. Dravco Basic Materials Co.,

2417Inc. v. State, Dep't of Trans. , 602 So. 2d 632, 634, fn. 3

2430(Fla. 2d DCA 1992).

243423. Finally, in reviewing an agency's intended decis ion

2443to reject all bids, the administrative law judge must give

2453substantial deference to the agency's determination, owing to

2461its wide discretion in procurement matters. See , e.g. , BT

2470Builders, Inc. v. Broward County School Board , DOAH Case No.

248001 - 0317BI D (Broward Cty. School Bd., Aug. 7, 2001).

249124. Applying the foregoing principles to the facts of

2500this case, it is concluded that the evidence is insufficient

2510to show that the District's action was arbitrary. Rather, the

2520evidence clearly shows that the Committee's decision was an

2529honest exercise of its wide discretion in the bidding process.

2539This being so, the decision to reject all bids should be

2550reconfirmed.

2551RECOMMENDATION

2552Based on the foregoing Findings of Fact and Conclusions

2561of Law, it is

2565RECOMME NDED that the Southwest Florida Water Management

2573District enter a final order rejecting all proposals on

2582RRP 008 - 02.

2586DONE AND ENTERED this 4th day of December, 2002, in

2596Tallahassee, Leon County, Florida.

2600___________________________________

2601DONALD R. ALEXANDER

2604Administrative Law Judge

2607Division of Administrative Hearings

2611The DeSoto Building

26141230 Apalachee Parkway

2617Tallahassee, Florida 32399 - 3060

2622(850) 488 - 9675 SUNCOM 278 - 9675

2630Fax Filing (850) 921 - 6847

2636www.doah.state.fl.us

2637Filed with the Clerk of the

2643Division of Administrative Hearings

2647this 4th day of December, 2002.

2653COPIES FURNISHED:

2655E. D. "Sonny" Vergara, Executive Director

2661Southwest Florida Water Management Dis trict

26672379 Broad Street

2670Brooksville, Florida 34604 - 6899

2675Stephen H. Kurvin, Esquire

26797 South Lime Street

2683Sarasota, Florida 34237 - 6105

2688Stephen O. Rushing, Esquire

2692Southwest Florida Water Management District

26972379 Broad Street

2700Brooksville, Florida 34604 - 68 99

2706NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

2712All parties have the right to submit written exceptions within

272210 days from the date of this Recommended Order. Any

2732exceptions to this Recommended Order should be filed with the

2742agency that will render a final or der in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 01/06/2003
Proceedings: Final Order filed.
PDF:
Date: 01/02/2003
Proceedings: Agency Final Order
PDF:
Date: 12/13/2002
Proceedings: Exceptions to Recommended Order filed by Petitioner.
PDF:
Date: 12/04/2002
Proceedings: Recommended Order
PDF:
Date: 12/04/2002
Proceedings: Recommended Order issued (hearing held October 22, 2002) CASE CLOSED.
PDF:
Date: 12/04/2002
Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
PDF:
Date: 11/27/2002
Proceedings: (Proposed) Recommended Order filed by Petitioner.
PDF:
Date: 11/27/2002
Proceedings: Notice of Filing Proposed Recommended Order of Petitioner filed.
PDF:
Date: 11/22/2002
Proceedings: Proposed Recommended Order of the Respondent filed.
PDF:
Date: 11/22/2002
Proceedings: Notice of Filing Proposed Recommended Order of Respondent filed.
PDF:
Date: 11/22/2002
Proceedings: Respondent Southwest Florida Water Management District`s Memorandum of Law and Closing Argument filed.
Date: 11/12/2002
Proceedings: Transcript filed.
PDF:
Date: 11/12/2002
Proceedings: Notice of Filing Final Hearing Transcript filed.
PDF:
Date: 10/24/2002
Proceedings: Videotaped Deposition of: Ronnie Duncan filed.
Date: 10/22/2002
Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
PDF:
Date: 10/18/2002
Proceedings: Notice filed by Petitioner.
PDF:
Date: 10/18/2002
Proceedings: Exhibit List filed by Petitioner.
PDF:
Date: 10/17/2002
Proceedings: Joint Prehearing Stipulation (filed by Petitioner via facsimile).
PDF:
Date: 10/15/2002
Proceedings: Request for Production of Documents filed by Petitioner.
PDF:
Date: 10/15/2002
Proceedings: Witness List filed by Petitioner.
PDF:
Date: 10/15/2002
Proceedings: Notice of Taking Deposition (T. Dabney, II and M. Leytze) filed.
PDF:
Date: 10/15/2002
Proceedings: Supplemental Response to Request for Production of Documents (filed by Respondent via facsimile).
PDF:
Date: 10/15/2002
Proceedings: Joint Stipulation for Use of Video Deposition as Final Hearing Testimony (R. Duncan) filed via facsimile.
PDF:
Date: 10/11/2002
Proceedings: Response to Request for Production of Documents (filed by Respondent via facsimile).
PDF:
Date: 10/10/2002
Proceedings: Notice of Taking Deposition (R. Lawson and B. Pellegrino) filed via facsimile.
PDF:
Date: 10/09/2002
Proceedings: Respondent`s Notice of Taking Video Deposition to Perpetuate Testimony (R. Duncan) filed via facsimile.
PDF:
Date: 10/07/2002
Proceedings: Letter to C. Johnson from S. Rushing enclosing copy of petition protesting the rejection of all bids in regard to above RFP filed.
PDF:
Date: 10/07/2002
Proceedings: Letter to R. Bandes from S. Rushing enclosing copy of petiion protesting the rejection of all bids in regard to above RFP filed.
PDF:
Date: 10/07/2002
Proceedings: Letter to T. Grosz from S. Rushing enclosing copy of petition protesting the rejection of all bids in regard to above RFP filed.
PDF:
Date: 10/07/2002
Proceedings: Letter to R. Greene from S. Rushing enclosing copy of petition protesting the rejection of all bids in regard to above RFP filed.
PDF:
Date: 10/01/2002
Proceedings: Notice of Hearing issued (hearing set for October 22, 2002; 9:00 a.m.; Tampa, FL).
PDF:
Date: 10/01/2002
Proceedings: Order of Pre-hearing Instructions issued.
PDF:
Date: 09/27/2002
Proceedings: Bid Protest Bond filed.
PDF:
Date: 09/27/2002
Proceedings: Petition filed.
PDF:
Date: 09/27/2002
Proceedings: Agency referral filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
09/27/2002
Date Assignment:
09/30/2002
Last Docket Entry:
01/06/2003
Location:
Tampa, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (2):