02-003790BID
Paul J. Sierra Construction, Inc. vs.
Southwest Florida Water Management District
Status: Closed
Recommended Order on Wednesday, December 4, 2002.
Recommended Order on Wednesday, December 4, 2002.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8PAUL J. SIERRA CONSTRUCTION, )
13INC., )
15)
16Petitioner, )
18)
19vs. ) Case No . 02 - 3790BID
27)
28SOUTHWEST FLORIDA WATER )
32MANAGEMENT DISTRICT, )
35)
36Respondent. )
38______________________________)
39RECOMMENDED ORDER
41This matter was heard before t he Division of
50Administrative Hearings by its assigned Administrative Law
57Judge, Donald R. Alexander, on October 22, 2002, in Tampa,
67Florida.
68APPEARANCES
69For Petitioner: Stephen H. Kurvin, Esquire
757 South Lime Avenue
79Sarasota, Florida 34237 - 6105
84For Respondent: Stephen O. Rushing, Esquire
90Mark F. Lapp, Esquire
942379 Broad Street
97Brooksville, Florida 34604 - 6899
102STATEMENT O F THE ISSUE
107The issue is whether Respondent's decision to reject all
116proposals on RFP No. 008 - 02 to design and build an ancillary
129building at the Tampa Service Office was arbitrary, as alleged
139by Petitioner.
141PRELIMINARY STATEMENT
143This matter began on Sep tember 3, 2002, when Respondent,
153Southwest Florida Water Management District, advised all
160proposers, including Petitioner, Paul J. Sierra Construction,
167Inc., that it intended to (1) reject all proposals on RFP No.
179008 - 02 to construct an ancillary building at its Tampa Service
191Center and (2) revise the scope of the project by combining
202the construction of the ancillary building with all other
211construction to be taken at the Tampa Service Center. On
221September 5, 2002, Petitioner filed a timely Notice of Prot est
232to the decision alleging that Respondent's action was
240arbitrary. A timely Formal Written Protest was then filed on
250September 12, 2002.
253After efforts by the parties to resolve the matter were
263unsuccessful, the matter was referred by Respondent to the
272Division of Administrative Hearings on September 27, 2002,
280with a request that an Administrative Law Judge be assigned to
291conduct a hearing. By Notice of Hearing dated October 1,
3012002, a final hearing was scheduled on October 22, 2002, in
312Tampa, Florida.
314At the final hearing, Petitioner presented the testimony
322of Robert Pellegrino, its division manager; Ricky M. Lawson,
331its assistant division manager; Steven M. Long, Mark Leytze,
340and Nicholas Spirakis, all employees of Respondent; and
348Enrique A. Woodruf f, the project architect. Also, it offered
358Petitioner's Exhibits 1 - 9. All were received in evidence
368except Exhibit 3. Respondent presented the testimony of Mark
377Leytze, a state certified contractor and manager of
385Respondent's construction projects, and Thomas G. Dabney, II,
393vice - chairman of the Governing Board. Also, it offered
403Respondent's Exhibits 2 - 8, 10, 11, and 13, which were received
415in evidence. Exhibit 2 is the video deposition of Ronnie E.
426Duncan, chairman of the Governing Board, and Exhibit 3 is the
437transcription of that deposition.
441The Transcript of the hearing was filed on November 10,
4512002. Proposed Findings of Fact and Conclusions of Law were
461filed by Respondent and Petitioner on November 20 and 27,
4712002, respectively, and they have been considered by the
480undersigned in the preparation of this Recommended Order.
488FINDINGS OF FACT
491Based upon all of the evidence, the following findings of
501fact are determined:
5041. On May 21, 2002, Respondent, Southwest Florida Water
513Management District (D istrict), through its contracts manager,
521issued an Invitation to Proposal inviting interested persons
529to submit competitive sealed proposals on Request for Proposal
538No. 008 - 02 (RFP No. 008), which called for the design and
551construction of an ancillary buil ding at its District Service
561Office (Tampa Service Center) located at 7601 Highway 301
570North, Tampa, Florida. The proposed facility is an
578approximately 5,000 square foot metal building which will
587house the District's field staff. The last paragraph of th e
598document provided that "[t]he District shall reserve the right
607to reject any or all bids/proposals received with or without
617cause."
6182. On May 24, 2002, the District placed an advertisement
628of its Invitation to Proposal in three local newspapers in
638Hil lsborough County. The last paragraph of each advertisement
647also provided that the District reserved the right to reject
657all bids with or without cause.
6633. A mandatory pre - proposal conference was held on
673June 6, 2002, which was attended by various inter ested
683persons, including Petitioner, Paul J. Sierra Construction,
690Inc. (Sierra), a large construction firm located in Tampa,
699Florida. Although Sierra engages in general construction, it
707also has a division which specializes in projects using Butler
717buildi ng systems. A Butler building utilizes a combination of
727a metal roof with a pre - engineered structural system.
7374. At the pre - proposal meeting, Sierra requested a copy
748of RFP No. 008 - 02, which contained the general conditions for
760the project, nature of the services required, insurance
768requirements, and evaluation procedures. Section 1.13 of that
776document provided in relevant part that "the District reserves
785the right to reject all proposals and not grant any award from
797the issuance of this RFP."
8025. Five proposals, including Sierra's, were received and
810opened on June 26, 2002. All proposals were reviewed and
820independently scored by a three - person selection committee
829composed of District staffers. Although Sierra's proposal of
837$374,038.00 was not the low est dollar amount submitted, it
848received the highest numerical score of 279, edging out two
858other proposers who both received scores of 277. The lowest
868dollar proposal submitted was $337,000.00.
8746. Under the process in place, the selection committee
883th en referred the results of its evaluation to a three - person
896Facilities Ad Hoc Committee (Committee), comprised of the
904Governing Board's chairman, Mr. Ronnie E. Duncan, the
912Governing Board's vice - chairman, Mr. Thomas D. Dabney, II, and
923the treasurer of the Governing Board, Watson L. Haynes, II.
933The Committee was delegated the authority to reject any
942proposal without further action by the District's Governing
950Board; however, approval of a proposal had to be confirmed by
961the Governing Board.
9647. Committee mem bers Duncan and Dabney are developers
973with extensive experience in construction while Mr. Haynes has
982a background in accounting. The Committee was formed in late
9922001 for the purpose of achieving more efficiencies in the
1002construction process, particularly in light of a newspaper's
1010criticism of the money spent by the District while renovating
1020Building 2 at its Brooksville office. The Committee was not
1030obligated to accept the selection committee scoring. Rather,
1038the Committee had a duty to make the ultimat e decision as to
1051how taxpayer dollars are best spent.
10578. The Committee met on July 30, 2002, to consider the
1068results of the evaluation. Mr. Haynes was not present. The
1078two other members voiced concerns regarding the cost of
1087Sierra's proposal, which wa s more than $74.00 per square foot.
1098For that reason, the Committee continued the decision on
1107awarding the contract to its next meeting on August 28, 2002.
1118It also requested the staff to determine how costs on the
1129project could be reduced.
11339. On July 31, 2002, Sierra contacted the District's
1142contract manager, Steven M. Long, by telephone and was told
1152that Sierra had received the highest ranking from the
1161selection committee, but that the Committee had postponed a
1170decision until its next meeting because of concerns over the
1180cost of the project.
118410. On August 28, 2002, the Committee reconvened. Due
1193to a personal conflict, Mr. Haynes was not present. By a 2 - 0
1207vote, the Committee determined that because of the cost
1216concerns, all proposals should be rejected, and that the 5,000
1227square foot ancillary building should be combined with two
1236other projects being undertaken at the Tampa Service Center
1245under a single construction manager to reduce costs and
1254realize other benefits. This decision was conveyed by
1262teleph one to Sierra on September 1, 2002.
127011. On September 3, 2002, formal Notice of Rejection
1279letters were sent to all five proposers. On September 5,
12892002, Sierra filed its Notice of Protest. This was followed
1299by a Formal Written Protest filed on September 12, 2002, in
1310which Sierra contended that the Committee's decision was
1318arbitrary.
131912. The Tampa Service Center is a branch office of the
1330District and includes office, technical, maintenance, and
1337garage facilities with accompanying parking and roadways.
1344Existing Building 1 is outdated, crowded, and inadequate and
1353must be replaced. It will be demolished once the new Building
13641 is constructed. Although the District initially decided
1372that the new building would need 30,000 square feet, it later
1384determined that the approximately 5,000 square feet needed to
1394house District field staff could be separated out as an
1404ancillary building from Building 1 and built as a metal
1414building. A preengineered metal building was selected since
1422it would be cheaper and faster to build, and some of the field
1435staff could be moved out of the crowded existing Building 1 to
1447the ancillary building while new Building 1 was being
1456constructed.
145713. In addition to the construction of the new Building
14671 and the ancillary building, the D istrict intends to re - roof
1480existing Building 2, demolish Building 1, re - route traffic
1490flow, install security gates, improve parking, improve the
1498stormwater system, and install new landscaping.
150414. As a general rule, as a project gets larger, there
1515are eco nomies of scale that result in cost reductions because
1526the cost per unit becomes less as a greater quantity is
1537purchased. In deciding to reject all proposals, and combine
1546all of the work at the Tampa Service Center, the Committee
1557considered the following advantages to having a construction
1565manager supervise the entire project:
1570a. It would reduce potential confusion by better
1578coordinating the number of contractors and subcontractors on
1586the job and create a more efficient work flow.
1595b. Task coordination is essential for safety since
1603District employees and members of the public will have
1612continuing access to the Tampa Service Center while all
1621components of the project are under construction.
1628c. There will be considerable underground construction
1635work for the installation of electrical lines, telephone
1643lines, computer cabling, water lines, fire protection water
1651service lines, sewer lines, irrigation lines, and stormwater
1659lines. Improved coordination reduces duplication and the
1666possibility of putting recen tly completed work at risk for
1676damage.
1677d. By working with the architect and the construction
1686manager, the District could use value engineering to reduce
1695costs. Value engineering would allow the District to look at
1705creative ways to reduce costs by subst ituting similar, less
1715expensive items for more expensive items.
1721e. Because the District is exempt from paying state
1730sales tax, the District would save the 7 percent sales tax
1741since the construction manager sets up accounts with vendors
1750directly for the District. The District would also save the
1760contractor's percentage markup that typically encompasses the
17677 percent sales tax when it has to be paid.
1777f. The construction manager system produces a better
1785selection process and cost savings since the const ruction
1794manager can be required to obtain at least three proposals for
1805each of the sixteen divisions of labor.
1812g. There will be benefits of accountability and
1820uniformity from having only one person or entity responsible
1829for any problems encountered.
183315 . In addition, the following savings could be realized
1843through economies of scale by including the ancillary building
1852in the larger project and under a construction manager:
1861mobilization; demobilization; site work; excavation for
1867foundation; concrete for foundation; rough - in electrical work;
1876rough - in plumbing; fire protection service line; electrical
1885lines; water lines; computer cabling lines; plumbing;
1892electrical; insulation; drywall; floor tile; ceiling grid;
1899ceiling tiles; doors; air conditioning syste m; painting;
1907landscaping; irrigation sprinkler system; paving work;
1913stormwater system; and one project manager.
191916. At the same time, when the earlier decision was made
1930to separate the construction of the ancillary building out
1939from the rest of the Tampa Service Center project to save time
1951and money, the Committee believed that the ancillary building
1960would obtain its utility and communication services from an
1969existing, adjacent building. After later learning that this
1977was not the case, and that the scope of the work for the
1990ancillary building had expanded to require considerable
1997underground site work for its new utility and communication
2006services, the Committee realized that the cost and other
2015benefits originally intended had been lost.
202117. Finally, new B uilding 1 is only sixty feet from the
2033ancillary building and will require considerable underground
2040site work for its new utility and communication services.
2049Therefore, the Committee concluded that it made more sense to
2059combine the construction of the new Building 1 and the
2069ancillary building to achieve cost savings and efficiencies in
2078the installation of utility and communication services and to
2087reduce other overlapping aspects of the Tampa Service Center
2096project.
209718. Given the foregoing considerations, t he Committee's
2105decision to reject all proposals was not arbitrary in any
2115sense. While it is true that the precise amount of savings to
2127be realized cannot be quantified, the greater weight of
2136evidence shows that some savings can be achieved, and that the
2147C ommittee's decision was based on facts, sound reasoning, and
2157logic.
2158CONCLUSIONS OF LAW
216119 . The Division of Administrative Hearings has
2169jurisdiction over the subject matter and the parties hereto
2178pursuant to Sections 120.569 and 120.57(3), Florida Statut es.
218720. Section 120.57(3)(f), Florida Statutes (2002),
2193governs this dispute and provides in relevant part as follows:
2203(f) In any bid - protest proceeding
2210contesting an intended agency action to
2216reject all bids, proposals, or replies, the
2223standard of revie w by an administrative law
2231judge shall be whether the agency's intended
2238action is illegal, arbitary, dishonest, or
2244fraudulent.
224521. Therefore, the District's decision to reject all
2253proposals, as it did here, will only be overturned if it is
2265arbitrary, i llegal, dishonest, or fraudulent. In this case,
2274Petitioner contends that the District's action was arbitrary.
228222. An arbitrary decision is one not supported by fact
2292or logic. Agrico Chemical Co. v. State Dep't of Envir. Reg. ,
2303365 So. 2d 759, 763 (Fla. 1 st DCA 1978). The inquiry to be
2317made in determining whether an agency has acted arbitrarily is
2327whether the agency has (1) considered all relevant factors;
2336(2) given actual, good faith consideration to those factors;
2345and (3) used reason rather than whim to progress from
2355consideration of those factors to its final decision. Adam
2364Smith Enterprises, Inc. v. State Dep't of Envir. Reg. , 553 So.
23752d 1260, 1273 (Fla. 1st DCA 1989). At the same time, if a
2388decision is justifiable under any analysis that a reasonabl e
2398person would use to reach a decision of similar importance,
2408the decision is not arbitrary. Dravco Basic Materials Co.,
2417Inc. v. State, Dep't of Trans. , 602 So. 2d 632, 634, fn. 3
2430(Fla. 2d DCA 1992).
243423. Finally, in reviewing an agency's intended decis ion
2443to reject all bids, the administrative law judge must give
2453substantial deference to the agency's determination, owing to
2461its wide discretion in procurement matters. See , e.g. , BT
2470Builders, Inc. v. Broward County School Board , DOAH Case No.
248001 - 0317BI D (Broward Cty. School Bd., Aug. 7, 2001).
249124. Applying the foregoing principles to the facts of
2500this case, it is concluded that the evidence is insufficient
2510to show that the District's action was arbitrary. Rather, the
2520evidence clearly shows that the Committee's decision was an
2529honest exercise of its wide discretion in the bidding process.
2539This being so, the decision to reject all bids should be
2550reconfirmed.
2551RECOMMENDATION
2552Based on the foregoing Findings of Fact and Conclusions
2561of Law, it is
2565RECOMME NDED that the Southwest Florida Water Management
2573District enter a final order rejecting all proposals on
2582RRP 008 - 02.
2586DONE AND ENTERED this 4th day of December, 2002, in
2596Tallahassee, Leon County, Florida.
2600___________________________________
2601DONALD R. ALEXANDER
2604Administrative Law Judge
2607Division of Administrative Hearings
2611The DeSoto Building
26141230 Apalachee Parkway
2617Tallahassee, Florida 32399 - 3060
2622(850) 488 - 9675 SUNCOM 278 - 9675
2630Fax Filing (850) 921 - 6847
2636www.doah.state.fl.us
2637Filed with the Clerk of the
2643Division of Administrative Hearings
2647this 4th day of December, 2002.
2653COPIES FURNISHED:
2655E. D. "Sonny" Vergara, Executive Director
2661Southwest Florida Water Management Dis trict
26672379 Broad Street
2670Brooksville, Florida 34604 - 6899
2675Stephen H. Kurvin, Esquire
26797 South Lime Street
2683Sarasota, Florida 34237 - 6105
2688Stephen O. Rushing, Esquire
2692Southwest Florida Water Management District
26972379 Broad Street
2700Brooksville, Florida 34604 - 68 99
2706NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2712All parties have the right to submit written exceptions within
272210 days from the date of this Recommended Order. Any
2732exceptions to this Recommended Order should be filed with the
2742agency that will render a final or der in this matter.
- Date
- Proceedings
- PDF:
- Date: 12/04/2002
- Proceedings: Recommended Order issued (hearing held October 22, 2002) CASE CLOSED.
- PDF:
- Date: 12/04/2002
- Proceedings: Recommended Order cover letter identifying hearing record referred to the Agency sent out.
- PDF:
- Date: 11/22/2002
- Proceedings: Respondent Southwest Florida Water Management District`s Memorandum of Law and Closing Argument filed.
- Date: 11/12/2002
- Proceedings: Transcript filed.
- Date: 10/22/2002
- Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
- PDF:
- Date: 10/17/2002
- Proceedings: Joint Prehearing Stipulation (filed by Petitioner via facsimile).
- PDF:
- Date: 10/15/2002
- Proceedings: Supplemental Response to Request for Production of Documents (filed by Respondent via facsimile).
- PDF:
- Date: 10/15/2002
- Proceedings: Joint Stipulation for Use of Video Deposition as Final Hearing Testimony (R. Duncan) filed via facsimile.
- PDF:
- Date: 10/11/2002
- Proceedings: Response to Request for Production of Documents (filed by Respondent via facsimile).
- PDF:
- Date: 10/10/2002
- Proceedings: Notice of Taking Deposition (R. Lawson and B. Pellegrino) filed via facsimile.
- PDF:
- Date: 10/09/2002
- Proceedings: Respondent`s Notice of Taking Video Deposition to Perpetuate Testimony (R. Duncan) filed via facsimile.
- PDF:
- Date: 10/07/2002
- Proceedings: Letter to C. Johnson from S. Rushing enclosing copy of petition protesting the rejection of all bids in regard to above RFP filed.
- PDF:
- Date: 10/07/2002
- Proceedings: Letter to R. Bandes from S. Rushing enclosing copy of petiion protesting the rejection of all bids in regard to above RFP filed.
- PDF:
- Date: 10/07/2002
- Proceedings: Letter to T. Grosz from S. Rushing enclosing copy of petition protesting the rejection of all bids in regard to above RFP filed.
- PDF:
- Date: 10/07/2002
- Proceedings: Letter to R. Greene from S. Rushing enclosing copy of petition protesting the rejection of all bids in regard to above RFP filed.
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 09/27/2002
- Date Assignment:
- 09/30/2002
- Last Docket Entry:
- 01/06/2003
- Location:
- Tampa, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Stephen Henry Kurvin, Esquire
Address of Record -
Steve Rushing, Esquire
Address of Record