03-001253DDC
Cpw Enterprises, Inc., D/B/A Cherokee Construction Company vs.
Department Of Transportation
Status: Closed
Recommended Order on Thursday, September 18, 2003.
Recommended Order on Thursday, September 18, 2003.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8CPW ENTERPRISES, INC., d/b/a )
13CHEROKEE CONSTRUCTION COMPANY, )
17)
18Petitioner, )
20)
21vs. ) Case No. 03 - 1253
28)
29DEPARTMENT OF TRANSPORTATION, )
33)
34Respondent. )
36)
37RECOMMENDED ORDER
39Pursuant to notice, a formal hearing was held in this case
50on July 11, 2003, by video teleconference between sites in
60Orlando and Tallahassee, Florida, before T. Kent Wetherell, II,
69the designated Administrative Law Judge of t he Division of
79Administrative Hearings.
81APPEARANCES
82For Petitioner: Brant Hargrove, Esquire
87Law Office of Brant Hargrove
922984 Wellington Circle, West
96Tallahassee, Florida 32308
99For Respondent: Robert M. Burdick, Esquire
105Depar tment of Transportation
109Haydon Burns Building, Mail Station 58
115605 Suwannee Street
118Tallahassee, Florida 32399 - 0458
123STATEMENT OF THE ISSUES
127The issues are whether the Department of Transportation may
136declare Petitioner non - responsible and ineli gible to bid on
147Department contracts based upon Petitioner's alleged
153unsatisfactory performance and default on Department contract
160number E - 5G08; and if so, for what period of time should
173Petitioner be declared non - responsible.
179PRELIMINARY STATEMENT
181By le tter dated February 12, 2003, the Department of
191Transportation (Department) notified Petitioner of its intent to
199declare Petitioner non - responsible for a period of two years
210based upon Petitioner's unsatisfactory performance and default
217on Department contr act number E - 5G08. On March 4, 2003,
229Petitioner timely requested a formal hearing on the Department's
238proposed action. On April 7, 2003, the Department referred the
248matter to the Division of Administrative Hearings (Division) for
257the assignment of an Adm inistrative Law Judge to conduct the
268hearing requested by Petitioner.
272The hearing was initially scheduled for June 24, 2003, but
282was subsequently continued based upon Petitioner's unopposed
289motion. The hearing was rescheduled for and held on July 11,
300200 3.
302At the hearing, Petitioner presented the testimony of
310Charles Welch and Elizabeth Gornick. Petitioner's Exhibits A
318and B were received into evidence. The Department presented the
328testimony of Judson Pankey, Stephen Bass, and Calvin Landers.
337The Depar tment's Exhibits 1 through 3, 4A, 4B, 5 through 20,
349and 22 through 24 were received into evidence. Upon the
359Department's request, official recognition was taken of
366Rule 14 - 22.0141, Florida Administrative Code.
373Petitioner was permitted to submit the depos ition testimony
382of Michael Huggins after the hearing. Mr. Huggins' deposition
391was taken on July 22, 2003, and the Transcript of the deposition
403was filed with the Division on August 22, 2003, and is hereby
415received as Petitioner's Exhibit C .
421The one - volum e Transcript of the hearing was filed with the
434Division on August 13, 2003. The parties requested and were
444given 20 days from the date that the hearing Transcript was
455filed to file their proposed recommended orders (PROs). The
464parties' PROs were timely f iled on September 2, 2003, and they
476were given due consideration by the undersigned in preparing
485this Recommended Order.
488All statutory references in this Recommended Order are to
497the 2002 codification of the Florida Statutes unless otherwise
506indicated, and all references to Rules are to the current
516version of the Florida Administrative Code.
522FINDINGS OF FACT
525Based upon the testimony and evidence received at the
534hearing and the parties' stipulations, the following findings
542are made:
544A. Parties
5461. Petiti oner is a Florida corporation whose principal
555business is road and bridge maintenance. Petitioner also does
564some landscape installation work.
5682. Petitioner's president is Charles Welch.
5743. Petitioner has received between ten and 20 contracts
583from the Department since 1993. However, the contract at issue
593in this proceeding is the first landscape installation project
602that Petitioner has done for the Department.
6094. The Department is the state agency responsible for
618maintaining and regulating the use of the right - of - way along the
632state highway system. That responsibility includes overseeing
639the installation and maintenance of landscaping within the
647right - of - way.
652B. Department Contract No. E - 5G08
6595. In November 2001, the Department awarded Petitioner a
668contract to install landscaping around six interchanges in the
677central Florida area.
6806. The interchanges were identified and prioritized in the
689bid specifications as follows: (1) I - 95/US 192 interchange;
699(2) I - 4/Lake Mary Boulevard interchange; (3) SR 25/SR 200
710interchange; (4) SR 482/SR 435 interchange; (5) I - 95/SR 518
721interchange; and (6) US 441/SR 46 interchange. The SR 482/SR
731435 interchange was subsequently deleted from the project, and
740the I - 4/Lake Mary Boulevard interchange was subsequently
749pri oritized ahead of the I - 95/US 192 interchange.
7597. The Department's contract identification number for the
767project was E - 5G08.
7728. The contract required Petitioner to prepare and mulch
78166,667 square yards of beds for the landscaping and then to
793install a t otal of 63,667 plumbago shrubs and 927 sabal palm
806trees. The plumbagos were required to be ten to 18 inches in
818height, and the palm trees were required to be nine to 20 feet
831in height.
8339. Petitioner did not challenge the specifications for the
842project.
8431 0. Petitioner bid $745,160.90 for the contract, and the
854Department accepted the bid at that amount.
86111. Petitioner's bid amount was calculated by multiplying
869a unit price for each plant type by the number of plants
881required under the contract, plus a unit price for the
891mulching/bed preparation multiplied by the total number of
899square yards in the beds. No separate amount was bid by
910Petitioner for "maintenance," and the bid form did not include a
921separate line for that item.
92612. The contract generally descr ibed the work to be
936performed by Petitioner as "furnish[ing] and install[ing] palms,
944plants and associated landscape materials at various locations."
95213. A similar description of the project was provided on
962the first page of the bid specification package.
97014. The contract and the bid specification package
978incorporated by reference the 2000 edition of the Department's
987Standard Specifications for Road and Bridge Construction
994(Standard Specifications).
99615. Mr. Welch was generally familiar with the Standard
1005Spe cifications as a result of the prior contract work that he
1017and Petitioner had done for the Department. He understood that
1027the Standard Specifications were part of each Department
1035construction and maintenance contract.
103916. Section 580 - 10 of the Standard S pecifications,
1049entitled "Contractor's Responsibility for Condition of the
1056Plantings," requires the contractor to:
1061[e]nsure that the plants are kept watered,
1068that the staking and guying is adjusted as
1076necessary, that all planting areas and beds
1083are kept fre e of weeds and undesirable plant
1092growth and that the plants are maintained so
1100that they are healthy, vigorous, and
1106undamaged at the time of acceptance.
111217. Section 580 - 11 of the Standard Specifications,
1121entitled "Plant Establishment Period and Contractor 's Warranty,"
1129requires the contractor to:
1133[a]ssume responsibility for the proper
1138maintenance, survival and condition of all
1144landscape items for a period of one year
1152after the final acceptance of all work under
1160the Contract in accordance with [Section]
11665 - 1 1. [The contractor shall also] [p]rovide
1175a Warranty/Maintenance Bond to the
1180Department in the amount of the total sums
1188bid for all landscape items as evidence of
1196warranty during this plant establishment
1201period. The costs of the bond will not be
1210paid sepa rately, but will be included in the
1219costs of other bid items.
1224* * *
1227[The contractor shall] [t]ake responsibility
1232to apply water as necessary during this
1239period and include the cost in the various
1247landscape items. No separate measurement of
1253payment w ill be made for water during the
1262plant establishment period.
126518. Pursuant to Sections 5 - 10 and 5 - 11 of the Standard
1279Specifications, "acceptance" of a project does not occur until
1288the Department determines that the contractor has satisfactorily
1296completed a ll work on the project and informs the contractor in
1308writing that the project is accepted.
131419. Sections 5 - 10.2 and 5 - 10.3 of the Standard
1326Specifications allow for acceptance of portions of the project,
1335called "partial acceptance." Those provisions do not, however,
1343require the Department to accept projects on a piecemeal basis.
135320. At the pre - construction conference held on
1362November 19, 2001, Mr. Welch asked, "if a single location
1372[would] be accepted as it is completed." The Department's
1381project manager, S tephen Bass, replied that he would "check to
1392see if this is possible," and he told Mr. Welch that "[i]n the
1405meantime, as you complete a site, advise me in writing and I
1417will respond . . . ."
142321. Based upon the subsequent correspondence between the
1431partie s, it can be inferred that the Department decided against
1442accepting the project on a site - by - site basis. No partial or
1456final acceptance was ever given for the project or any of the
1468individual sites.
147022. The first page of the specification package provided
1479that the contract period was "270 days for installation," and
"1489365 addtl [sic] days after acceptance for establishment."
149723. The 365 - day, post - acceptance establishment period
1507referred to in the specification package is the same as the one -
1520year period refe rred to in Section 580 - 11 of the Standard
1533Specifications.
153424. Petitioner's obligations during the establishment
1540period were specifically discussed at the pre - construction
1549conference. At that time, Mr. Bass made it clear to Mr. Welch
1561that the contract incl uded the one - year establishment period, in
1573addition to the 270 - day installation period.
158125. The installation period began on December 3, 2001, and
1591ended on September 8, 2002. The latter date takes into account
1602the ten "[bad] weather days" added to the ins tallation period
1613under the terms of the contract.
161926. Mr. Welch understood the project to be an
1628installation - only contract. That understanding was based upon
1637the reference to a 270 - day installation period in the
1648specifications, and the fact that the bid form did not have a
1660separate line - item for maintenance.
166627. Mr. Welch did not read the specifications word - for -
1678word prior to bidding on the project, nor did he take into
1690account Section 580 - 11 of the Standard Specifications or the
1701language on the first pag e of the specification package which
1712clearly referenced the 365 - day, post - acceptance establishment
1722period.
172328. Mr. Welch did not understand the contract to require
1733Petitioner to weed or otherwise maintain the beds after the
1743plants were installed. He under stood the contract to only
1753require Petitioner to install the plants and then water them
1763through the end of the 270 - day installation period. In reaching
1775this conclusion, Mr. Welch did not take into account
1784Section 580 - 10 of the Standard Specifications, whi ch clearly
1795requires pre - acceptance weeding and which makes the contractor
1805the absolute insurer of the plants until acceptance by the
1815Department.
181629. The Department did not in any way contribute to
1826Mr. Welch's misunderstanding of the scope of the contract. The
1836contract documents were clear and unambiguous on the issue and
1846the Department made it clear from the outset that the contract
1857included a one - year establishment period.
1864C. Petitioner's Performance Under the Contract
187030. Petitioner performed its work u nder the contract in a
1881series of steps.
188431. Petitioner first sprayed the areas at each site where
1894the landscaping would be installed with a herbacide to kill any
1905existing vegetation. Two herbacide treatments were done at each
1914site.
191532. Petitioner then "mu lched" the planting areas at each
1925site by mowing the dead vegetation and marked the locations at
1936each site where the palm trees were to be installed.
194633. Petitioner then planted the palm trees at each site.
195634. Next, Petitioner installed "weed fabric" at the
1964I - 4/Lake Mary Boulevard interchange (hereafter "the Lake Mary
1974site").
197635. The weed fabric has two purposes: it blocks the light
1987that reaches the ground thereby reducing or eliminating weeds,
1996and it also helps prevent erosion.
200236. After install ing the weed fabric, Petitioner began
2011planting the plumbago shrubs at the Lake Mary site. To do so,
2023Petitioner cut and folded back the weed fabric where each
2033plumbago was to be located and then dug the hole within which
2045the plant was placed. After the plant was placed in the hole,
2057the weed fabric was then re - folded around the base of the plant.
207137. After the plumbagos were planted, Petitioner completed
2079its work at the Lake Mary site by spreading pine straw mulch in
2092the landscaped beds. The contract req uired a four - inch layer of
2105mulch.
210638. After completing its work at the Lake Mary site,
2116Petitioner moved to another site and installed the weed fabric,
2126planted the plumbagos, and spread the pine straw mulch at that
2137site. Petitioner continued working on a s ite - by - site basis in
2151this manner until all of the sites had been completed.
216139. In June 2002, the Department expressed concern to
2170Petitioner that it had fallen behind its installation schedule.
2179In response, Petitioner put more people on the job and was ab le
2192to get back on schedule. Petitioner completed the installation
2201of the plants within the 270 days allotted for installation.
221140. Petitioner periodically watered each of the sites as
2220the plants were being installed. Petitioner had two water
2229trucks that it used for watering. The truck used at the Lake
2241Mary site sprayed a stream of water out of a hose at a
2254relatively high flow rate.
225841. Because large portions of the landscaped beds at the
2268Lake Mary site were on steep slopes around the interchange, the
2279st ream of water from the water truck caused some of the pine
2292straw to wash down the slope. Heavy rains also caused the pine
2304straw to wash down the slope and, in some areas, to wash away
2317completely. As a result, some of the landscaped areas were not
2328covered with the four inches of mulch required by the
2338specifications.
233942. Mr. Welch acknowledged the loss of mulch in some
2349areas, and he attributed it to the weed fabric being too "slick"
2361to hold the mulch. Nevertheless, because Mr. Welch considered
2370the replacem ent of the mulch to be maintenance, which he did not
2383consider to be part of the contract, Petitioner never replaced
2393the pine straw.
239643. Petitioner did not consider using a "drip line" or
2406other watering system which would have applied the water at
2416ground le vel or at a lower rate of flow than the stream of water
2431being sprayed from the water truck. Such an alternative system
2441may have minimized the amount of mulch that washed down the
2452slope from watering, but it may not have affected the mulch that
2464washed away due to heavy rains. Such a system may have also
2476gotten more water to the plants' roots.
248344. Despite the watering done by Petitioner, plumbagos and
2492palm trees died at the Lake Mary site, as well as at the other
2506sites. Mr. Welch acknowledged the "loss" of a number of trees
2517and plants, although he testified that fewer plants had died
2527than he had projected at the outset of the project. The precise
2539number of trees and plants which died before Petitioner was
2549declared in default on the contract and told to sto p work on the
2563project is not clearly reflected in the record.
257145. The loss of the plumbagos at the Lake Mary site may be
2584partially attributable to the weed fabric selected by Petitioner
2593not being permeable enough to allow the water to reach the plant
2605roots , but Petitioner's failure to utilize an alternative
2613watering system to compensate for the "problems" it encountered
2622with the weed fabric also contributed to the loss of the
2633plumbagos.
263446. On August 12, 2002, the Department and Petitioner
"2643agreed that subs tantial completion has been achieved" on each
2653of the sites. That means that all or substantially all of the
2665plants had been installed by that date; it does not mean that
2677the Department had accepted the work, either partially or
2686conditionally.
268747. By lette r dated August 13, 2002, the Department
2697informed Petitioner that maintenance of the completed sites was
2706necessary. Specifically, the letter informed Petitioner that
2713there were dead palm trees and plumbagos at all of the sites
2725which needed to be replaced, that the pine straw mulch needed to
2737be replaced at most of the sites, and that weeding needed to be
2750done.
275148. Petitioner did not perform the weeding or other
2760maintenance directed by the Department. Indeed, the only work
2769that Petitioner did on the project after August 13, 2002, was on
2781August 20, 2002, when it watered two of the sites.
279149. By letter dated August 15, 2002, Petitioner responded
2800to the Department's direction that maintenance be commenced at
2809the completed sites. In that letter, Petitioner char acterized
2818the maintenance as "extra work" and requested additional
2826compensation for the maintenance work.
283150. The Department denied Petitioner's request for
2838additional compensation by letter dated August 15, 2002. That
2847letter informed Petitioner that "a D eficiency Letter would be
2857forthcoming if weed removal operation does not begin
2865immediately." Petitioner did not respond to the letter.
287351. By letter dated August 21, 2002, the Department issued
2883a "performance deficiency" based upon Petitioner's failure to
2891maintain the planted areas as required by the contract and as
2902directed by the Department in the letters dated August 13
2912and 15, 2002. Petitioner did not contest the deficiency within
2922the ten - day period prescribed by the letter.
293152. By letter dated August 22, 2002, the Department
2940requested that Petitioner submit the Warranty/Maintenance Bond
2947required by the contract since "substantial completion has been
2956achieved on the . . . project." The letter further advised
2967Petitioner that the one - year establishment period would not
2977commence until the bond was received by the Department.
2986Petitioner did not respond to the letter.
299353. By letter dated August 27, 2002, the Department
3002provided Petitioner with a "punch list" of items that required
3012correction before the pro ject could be accepted. The list
3022included the replacement of dead palm trees and dead or under -
3034sized plumbago shrubs at all of the sites; missing pine straw
3045mulch at all of the sites; weeding and general clean - up of all
3059of the sites; and submittal of the Warranty/Maintenance Bond.
306854. At the time of the Department's August 27, 2002,
3078letter, 12 days still remained in the installation period.
3087Petitioner did not respond to the letter and it made no effort
3099to complete the punch list items identified by the Department.
310955. The Department never accepted the work performed by
3118Petitioner under the contract because of the deficiencies
3126identified above. As a result, the 365 - day post - acceptance
3138establishment period never commenced.
314256. Petitioner never provided th e Department the
3150Warranty/Maintenance Bond required by Section 580 - 11 of the
3160Standard Specifications, which was incorporated by reference
3167into the contract.
317057. The Lake Mary site is highly visible because the
3180adjacent roads are very heavily traveled.
318658. The Department received complaints regarding the
3193appearance of the Lake Mary site. The complaints came from
3203Seminole County officials and members of the public.
3211D. Alternative Weed Fabric Proposed by Petitioner
321859. The specifications package for the con tract provided
3227general requirements for the weed fabric to be used on the
3238project. It did not, however, specify a specific brand of
3248fabric which must be used.
325360. The specifications package provided that "[t]he fabric
3261shall conform to the physical require ments on Roadway and
3271Traffic Design Standards, Index No. 199 according to its
3280application."
328161. Index No. 199 refers to the weed fabric as an "erosion
3293mat," and requires it to have an ultra violet (UV) rating of
33052,000 hours. Index No. 199 does not prescri be criteria for
3317water permeability for the weed fabric.
332362. Petitioner provided the information in the
3330specifications package relating to the weed fabric to its
3339material supplier, who then provided Petitioner a fabric that
3348met the specifications. The Dep artment was not involved in
3358those discussions.
336063. As required by the specifications package, Petitioner
3368provided the Department a copy of the product data sheet for the
3380selected fabric so that the Department could confirm that the
3390fabric met the require ments of Index No. 199.
339964. The weed fabric which Petitioner selected was called
"3408gold line." It had a UV rating of 2,500 hours, which met the
3422requirements of Index No. 199. It had a water permeability
3432rating of 15 gallons per minute per square foot (gal /min/SF).
344365. After encountering the problems described above at the
3452Lake Mary site, Petitioner began looking for an alternative weed
3462fabric which would be more permeable to water.
347066. The alternative fabric identified by Petitioner was
"3478Style 125EX" from Linq Industrial Fabrics, Inc. The water
3487permeability rating for that fabric was 150 gal/min/SF, but its
3497UV rating was only 500 hours.
350367. Mr. Welch provided the data sheet for the Style 125EX
3514fabric to Mr. Bass and requested that Petitioner be allowed to
3525substitute that fabric for the fabric that it had used at the
3537Lake Mary site. The Style 125EX fabric would have been used on
3549the remaining sites, because the Lake Mary site had been
3559completed with the original weed fabric by that time.
356868. That request wa s denied by the Department because the
3579UV rating for the Style 125EX fabric did not meet the
3590requirements of Index No. 199. The lower UV rating meant that
3601the fabric would not hold up as long and, therefore, could
3612create maintenance problems in the future .
361969. After the request to substitute the Style 125EX fabric
3629was denied, Petitioner did not attempt to locate an alternative
3639material which met the UV rating specified in Index No. 199, but
3651was more permeable to water than the gold line fabric.
3661E. Petitio ner's Default and Unsatisfactory
3667Performance Rating
366970. Section 8 - 9.1 of the contract provides that:
3679The following acts or omissions constitute
3685acts of default and . . . the Department
3694will give notice, in writing, to the
3701Contractor and his surety for any delay,
3708neglect or default, if the Contractor:
3714* * *
3717(c) performs the work unsuitably, or
3723neglects or refuses to remove materials or
3730to perform anew such work that the Engineer
3738rejects as unacceptable and unsuitable;
3743(d) discontinues prosec ution of the work,
3750or fails to resume discontinued work within
3757a reasonable time after the Engineer
3763notifies the Contractor to do so;
3769* * *
3772(j) for any other cause whatsoever, fails
3779to carry on the work in an acceptable
3787manner, . . . .
3792For a no tice based upon reasons stated in
3801subparagraphs (a) through (h) and (j): if
3808the Contractor, within a period of ten
3815calendar days after receiving the notice
3821described above, fails to correct the
3827conditions of which complaint is made, the
3834Department will . . . have full power and
3843authority, without violating the Contract,
3848to take the prosecution of the work out of
3857the hands of the Contractor and to declare
3865the contractor in default.
386971. On September 16, 2002, the Department notified
3877Petitioner that it inten ded to "default" Petitioner under the
3887contract based upon its failure to maintain the planted areas,
3897its failure to replace the dead plumbagos and palms, and its
3908failure to provide the required Maintenance/Warranty Bond. As
3916required by the contract, the l etter gave Petitioner 10 days to
3928cure the deficiencies in its performance.
393472. Petitioner did not respond to the Department's default
3943letter, nor did it take any action to cure the deficiencies
3954identified by the Department. As a result, on September 30,
39642 002, the Department formally declared Petitioner in default on
3974the contract and directed Petitioner not to perform any
3983additional work on the project.
398873. By letter dated October 22, 2002, the Department
3997advised Petitioner of its "preliminary" field perfor mance rating
4006for the contract. Petitioner received a raw score of 53 (out of
401890), which is a scaled score of 59. That is an unsatisfactory
4030rating.
403174. Petitioner did not contest its rating within the time
4041allowed by the Department's October 22, 2002, let ter. As a
4052result, the preliminary rating became final.
405875. Petitioner was not scored in the area of "maintenance
4068of traffic operations." The Department had not received any
4077complaints from the public on that issue, which is the primary
4088consideration upo n which that score is based.
409676. Had Petitioner received a "satisfactory" grade in that
4105category, Petitioner's total score would have been 60. If
4114Petitioner received a higher grade in that category, its total
4124score could have been as high as 63. In eithe r event, those
4137scores still result in an unsatisfactory rating.
414477. By letter dated February 12, 2003, the Department
4153advised Petitioner that it intended to declare Petitioner
4161non - responsible for a period of two years based upon its default
4174and unsatisf actory performance on Department contract number
4182E - 5G08. Petitioner timely requested a formal hearing, and this
4193proceeding followed. The Department stipulated at the hearing
4201that its decision to declare Petitioner non - responsible was not
4212based on Petit ioner's numerical performance rating (whether it
4221is 59, 60, or 63), but rather on the actual unsatisfactory
4232performance that is described above.
4237F. Subsequent Department Contract With Vila & Sons
424578. After Petitioner's default, the Department contracted
4252with another entity "in order to salvage the Department's
4261investment in this landscaping project, i.e. , ensure that the
4270plantings become established, . . . ."
427779. That contract, entered into in May 2003 between the
4287Department and Vila & Sons Landscaping C orporation, is
4296identified as contract number E - 5H09 (Vila & Sons Contract).
4307The contract amount was $112,461.36.
431380. The Vila & Sons Contract was for "one - time
4324maintenance" of three of the sites that Petitioner was
4333responsible for under its contract with the Department. The
4342sites were the I - 4/Lake Mary Boulevard interchange, the SR 25/SR
4354200 interchange, and the US 441/SR 46 interchange.
436281. The Vila & Sons Contract was only for a 60 - day period
4376and consisted of the following landscape maintenance functi ons:
43851) weeding [which includes pruning of
4391existing live shrubs], 2) removal and
4397replacement of dead shrubs, 3) fertilizing
4403[which includes "watering in"], 4)
4409remulching as necessary, 5) watering for
4415plant establishment and/or maintenance.
4419(Brackets in o riginal).
442382. The Vila & Sons Contract called for the installation
4433of 3,700 plumbago shrubs. It does not make reference to the
4445removal of dead palm trees, the re - erection of fallen palm
4457trees, or the installation of new palm trees.
446583. The bid form for the Vila & Sons Contract included
4476separate line - items for water, mulch pine bark, plumbago shrubs,
4487slow - release fertilizer, and "landscape maintenance (weed
4495removal, manual)."
449784. The record does not establish whether the Vila & Sons
4508Contract was satisf actorily performed or whether it was
4517successful in "salvaging" the installation work which had been
4526done by Petitioner.
452985. Between the time that Petitioner was declared in
4538default in September 2002 and May 2003 when the Vila & Sons
4550Contract was entered i nto, the Central Florida area had periods
4561of cold weather. The cold temperatures during those periods may
4571have killed some of the plumbagos and palm trees installed by
4582Petitioner, but the record does not establish how many plants,
4592if any, were killed by t he cold weather as compared to the
4605plants that were already dead at the time of Petitioner's
4615default.
4616CONCLUSIONS OF LAW
4619A. Jurisdiction and Burden of Proof
462586. The Division has jurisdiction over the parties to and
4635subject matter of this proceeding purs uant to Sections 120.569
4645and 120.57(1).
464787. The Department has the burden of proof in this
4657proceeding because it is the party seeking to change the status
4668quo and because it is asserting the affirmative on the issue of
4680Petitioner's non - responsibility. Se e, e.g., Dept. of
4689Transportation v. J.W.C. Co., Inc. , 396 So. 2d 778, 788 (Fla.
47001st DCA 1981) (burden of proof is on party asserting the
4711affirmative of an issue unless a statute provides otherwise);
4720Amico v. Division of Retirement , 352 So. 2d 556 (Fla. 1st DCA
47321977) (agency had the burden of proof in case involving change
4743in person's retirement status); Balino v. Dept. of Health and
4753Rehabilitative Servs. , 348 So. 2d 349 (Fla. 1st DCA 1977)
4763(agency had the burden to establish that persons receiving
4772Medicaid benefits were no longer eligible). And cf.
4780Rule 14 - 22.0141(1) (creating presumption that bidders for
4789certain projects are responsible "unless the Department
4796determines that good cause exists to declare the contractor
4805non - responsible.")
480988. The partie s disagree as to the appropriate standard of
4820proof. The Department contends that the preponderance of the
4829evidence standard applies, see Department's PRO at 9; Petitioner
4838contends that the clear and convincing evidence standard
4846applies. See Petitioner's PRO at Paragraph 35.
485389. In Capeletti Brothers, Inc. v. Department of
4861Transportation , 362 So. 2d 346, 347 (Fla. 1st DCA 1978), the
4872court characterized a proceeding involving the suspension of a
4881contractor's certificate of qualification as "in effect [a]
4889li cense revocation proceeding[.]" The relief being sought by
4898the Department in this proceeding is substantially the same as
4908that in Capeletti Bothers . This proceeding is also penal in
4919nature because it will result in Petitioner's losing income that
4929it mig ht have received as the successful bidder on Department
4940contracts over the next two years. Accordingly, the clear and
4950convincing evidence standard of proof applies. See Dept. of
4959Banking & Finance v. Osborne, Stern & Co. , 670 So. 2d 932 (Fla.
49721996) (clear and convincing evidence standard applies in
4980disciplinary proceedings and proceedings to impose
4986administrative fines); Section 120.57(1)(j) (preponderance of
4992the evidence standard does not apply in "penal or license
5002disciplinary proceedings").
5005B. May the Department Declare Petitioner Non - responsible?
501490. Section 337.16(2) provides in pertinent part that:
5022[T]he department, for good cause, may
5028determine any contractor not having a
5034certificate of qualification nonresponsible
5038for a specified period of time or may deny,
5047suspend, or revoke any certificate of
5053qualification. Good cause includes, but is
5059not limited to, circumstances in which a
5066contractor or the contractor's official
5071representative:
5072* * *
5075(c) Fails to comply with contract
5081requirements, i n terms of payment or
5088performance record, or to timely furnish
5094contract documents as required by the
5100contract or by any state or federal statute
5108or regulation;
511091. Rule 14 - 22.0141, which implements this statute,
5119provides in pertinent part:
5123(1) Contract ors who wish to bid for the
5132performance of construction contracts less
5137than or equal to $250,000, or any
5145maintenance contracts, are presumed to be
5151responsible bidders unless the Department
5156determines that good cause exists to declare
5163the contractor non - res ponsible, which shall
5171include the following:
5174(a) One of the circumstances specified in
5181Section 337.16(2), Florida Statutes, occurs;
5186(b) The contractor or its affiliate
5192defaulted on any contract, or the contract
5199surety assumed control of or financia l
5206responsibility for, any contract of the
5212contractor;
5213* * *
5216(e) The contractor failed to comply with
5223contract requirements, or failed to follow
5229Department direction in the execution of the
5236contract;
5237* * *
5240(i) The contractor has demonstrat ed
5246instances of poor or unsatisfactory
5251performance, deficient management resulting
5255in project delay, poor quality workmanship,
5261a history of payment of liquidated damages,
5268untimely completion of projects where
5273liquidated damages were not paid,
5278uncooperative attitude, contract litigation,
5282claims, or defaults.
5285(j) When the department determines that
5291any other circumstance constituting "good
5296cause" under Section 337.16(2), Florida
5301Statutes, exists.
530392. The Department met its burden to prove that Petitioner
5313defaulted on contract number E - 5G08 by failing to weed and
5325maintain the beds during the installation period as required by
5335Section 580 - 10 of the Standard Specifications and as repeatedly
5346directed in the Department's August 2002 letters; by failing to
5356ensu re that the plants were "healthy, vigorous, and undamaged at
5367the time of acceptance" as required by Section 580 - 10 of the
5380Standard Specifications; and by failing to provide the
5388Warranty/Maintenance Bond required under the contract.
539493. The Department als o met its burden to prove that
5405Petitioner's performance on the contract was unsatisfactory as a
5414result of its failure to weed and maintain the beds and its
5426failure to replace the plants and trees that died during the
5437installation period.
543994. As a result, g ood cause exists to declare Petitioner
5450non - responsible under Section 337.16(2)(c) and Rule
545814 - 22.0141(1)(a), (b), (e), (i), and/or (j).
546695. Petitioner's misunderstanding of the scope of the
5474project is no excuse for its default and unsatisfact ory
5484performance since the specifications and the contract were
5492unambiguous. Specifically, the first page of the specification
5500package clearly stated that the contract included both a 270 - day
5512installation period and an additional 365 - day establishment
5521peri od, and the Standard Specifications clearly described the
5530contractor's obligations to keep the landscaped areas "free of
5539weeds and undesirable plant growth" prior to acceptance (Section
5548580 - 10); to maintain the plants and ensure their survival
5559through acce ptance ( Id. ) and for a one - year period after
5573acceptance (Section 580 - 11); and to provide a
5582Warranty/Maintenance Bond to the Department. Id.
558896. Contrary to Petitioner's argument and despite the fact
5597that Petitioner completed the installation of the plants within
5606the time prescribed by the contract, the evidence fails to
5616establish that Petitioner substantially performed all of its
5624obligations under the contract. Indeed, the evidence clearly
5632and conclusively establishes that Petitioner refused to perform
5640th e pre - acceptance weeding and maintenance of the beds required
5652under the contract and that it failed to submit the
5662Maintenance/Warranty Bond required under the contract or to
5670otherwise accept its responsibilities during the post - acceptance
5679maintenance perio d.
568297. Even if, as Petitioner argues, the Department's
5690refusal to allow the use of an alternative weed fabric can be
5702raised in this proceeding as a defense to its default under the
5714contract, the evidence does not support Petitioner's claims that
5723such refus al was unreasonable or that it created an
5733insurmountable obstacle to Petitioner's performance under the
5740contract. Indeed, the evidence establishes that the
5747Department's rejection of the single alternative weed fabric
5755proposed by Petitioner was based upon legitimate concerns
5763regarding the fabric's durability and that Petitioner did not
5772avail itself of other alternatives (such as watering at a lower
5783flow rate or using a drip line) that may have gotten more water
5796to the plants' roots.
5800C. For What Period Shou ld Petitioner
5807be Declared Non - responsible?
581298. The determination as to the length of time that
5822Petitioner should be declared non - responsible is governed by
5832Rule 14 - 22.0141(2), which provides:
5838Determination of Contractor Non -
5843Responsibility. The Contra ctor will be
5849determined to be non - responsible and
5856ineligible to bid on Department contracts
5862for a period of time, based on the
5870seriousness of the deficiency.
5874(a) Examples of factors affecting the
5880seriousness of a deficiency are:
58851. Impacts on proje ct schedule, cost, or
5893quality of work;
58962. Unsafe conditions allowed to exist;
59023. Complaints from the public;
59074. Delay or interference with the bidding
5914process;
59155. The potential for repetition;
59206. Integrity of the public construction
5926pr ocess; and
59297. The effect on the health, safety, and
5937welfare of the public.
594199. There is no evidence that Petitioner's performance
5949under the contract created an unsafe condition or adversely
5958affected the public safety. Nor is there any evidence of a
5969d elay or interference with the bidding process or the project
5980schedule.
5981100. Petitioner's performance did generate complaints from
5988the public because of the poor appearance of the Lake Mary site,
6000although the record does not reflect how many complaints wer e
6011received or whether any complaints were received about the other
6021sites.
6022101. Petitioner's poor performance and ultimate default
6029significantly impacted the cost of the project since it
6038ultimately required the Department to contract with another
6046company a t a cost of more than $112,000.00, "in order to salvage
6060the Department's investment in this landscaping project."
6067102. Petitioner's apparent ignorance of or blatant
6074disregard for its contractual obligations, as shown by its
6083refusal to provide pre - acceptan ce maintenance of the landscaped
6094areas and its refusal to recognize its obligations during the
6104establishment period, undermines the competitive bidding process
6111through which Petitioner obtained this contract. Moreover, in
6119light of Mr. Welch's continued mi sinterpretation of the relevant
6129provisions of the Standard Specifications, Petitioner's
6135unsatisfactory performance on this project is capable of
6143repetition on future projects if not addressed here.
6151103. These factors, taken together, support the
6158Departmen t's preliminary determination that Petitioner should be
6166declared non - responsible for a period of two years. And cf.
6178Rule 14 - 22.012(1)(a)4.(contractor's certificate of qualification
6185should be suspended for "at least one year" when it is
6196determined tha t contractor defaulted on a contract).
6204104. The record does not establish whether Petitioner has
6213bid on any Department projects since it was declared in default
6224in September 2002, or since February 2003, when the Department
6234gave notice of its intent to de clare Petitioner non - responsible.
6246Nevertheless, based upon Capeletti Brothers , supra , the period
6254of Petitioner's non - responsibility should commence on the date
6264that the Department enters its final order in this proceeding,
6274not an earlier date on which Pet itioner may have voluntarily
6285stopped bidding on Department projects.
6290RECOMMENDATION
6291Based upon the foregoing Findings of Fact and Conclusions
6300of Law, it is
6304RECOMMENDED that the Department of Transportation issue a
6312final order which declares Petitioner no n - responsible and
6322ineligible to bid on Department contracts for a period of two
6333(2) years, commencing on the date of the final order.
6343DONE AND ENTERED this 18th day of September, 2003, in
6353Tallahassee, Leon County, Florida.
6357S
6358T. KENT WETHERELL, II
6362Administrative Law Judge
6365Division of Administrative Hearings
6369The DeSoto Building
63721230 Apalachee Parkway
6375Tallahassee, Florida 32399 - 3060
6380(850) 488 - 9675 SUNCOM 278 - 9675
6388Fax Filing (850) 921 - 6847
6394www.doah.state.fl.us
6395Filed wi th the Clerk of the
6402Division of Administrative Hearings
6406this 18th day of September, 2003.
6412COPIES FURNISHED :
6415Robert M. Burdick, Esquire
6419Department of Transportation
6422Haydon Burns Building, Mail Station 58
6428605 Suwannee Street
6431Tallahassee, Florida 32399 - 04 58
6437Brant Hargrove, Esquire
6440Law Office of Brant Hargrove
64452984 Wellington Circle, West
6449Tallahassee, Florida 32308
6452James C. Myers, Clerk of Agency Proceedings
6459Department of Transportation
6462Haydon Burns Building, Mail Station 58
6468605 Suwannee Street
6471Tallahass ee, Florida 32399 - 0450
6477Pamela Leslie, General Counsel
6481Department of Transportation
6484Haydon Burns Building, Mail Station 58
6490605 Suwannee Street
6493Tallahassee, Florida 32399 - 0450
6498NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6504All parties have the right to submit wri tten exceptions within
651515 days from the date of this Recommended Order. Any exceptions
6526to this Recommended Order should be filed with the agency that
6537will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 12/23/2003
- Proceedings: Notice Directing the Clerk of Agency Proceedings to Prepare and Transmit the Record for Appeal filed.
- PDF:
- Date: 09/18/2003
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- Date: 08/13/2003
- Proceedings: Transcript filed.
- Date: 07/11/2003
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 07/02/2003
- Proceedings: Amended Notice of Taking Depositions Duces Tecum, J. Pankee filed.
- PDF:
- Date: 06/30/2003
- Proceedings: Notice of Taking Depositions Duces Tecum, C. Landers, J. Pankee filed.
- PDF:
- Date: 06/19/2003
- Proceedings: Order Granting Continuance and Re-scheduling Video Teleconference (video hearing set for July 11, 2003; 9:00 a.m.; Orlando and Tallahassee, FL).
- PDF:
- Date: 05/27/2003
- Proceedings: Notice of Taking Deposition Duces Tecum, CPW Enterprises, Inc., d/b/a Cherokee Construction Co. filed.
Case Information
- Judge:
- T. KENT WETHERELL, II
- Date Filed:
- 04/03/2003
- Date Assignment:
- 04/07/2003
- Last Docket Entry:
- 12/23/2003
- Location:
- Orlando, Florida
- District:
- Middle
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- DDC
Counsels
-
Robert M. Burdick, Esquire
Address of Record -
Brant Hargrove, Esquire
Address of Record