03-002220BID Royal Concrete Concepts, Inc. vs. Broward County School Board
 Status: Closed
Recommended Order on Thursday, November 20, 2003.


View Dockets  
Summary: Respondent`s decision to reject all bids was not contrived or arbitrary, but based upon sound reasons discovered and fully exposed by an initial bid protest.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8ROYAL CONCRETE CONCEPTS, )

12INC., )

14)

15Petitioner, )

17) Case No. 03 - 2220BID

23vs. )

25)

26BROWARD COUNTY SCHOOL BOARD, )

31)

32Respondent, )

34)

35and )

37)

38JAMES B. PIRTLE CONS TRUCTION )

44COMPANY, INC., )

47)

48I ntervenor. )

51)

52PAD ULA & WADSWORTH )

57CONSTRUCTION COMPANY , )

60)

61P etitioner, )

64) Case No. 03 - 2221BID

70vs . )

73)

74BROWARD COUNTY SCHOO L BOARD, )

80)

81R espondent , )

84)

85and )

87)

88J AMES B. PIRTLE CONST RUCTION )

95COMPANY, INC., )

98)

99Intervenor. )

101____________________ _________

103RECOMMENDED ORDER

105Pursuant to notice a formal hearing was held in these

115cases on August 20 - 21, 2003, in Fort Lauderdale, Florida,

126before J. D. Parrish, a designated Administrative Law Judge of

136the Division of Administrative Hearings.

141APPEARANCES

142For Petitioner, Royal Concrete Concepts, Inc.:

148Steven L. Schwartberg, Esquire

152Schwarzberg & Associates

155Esperante, Suite 210

158222 Lakeview Avenue

161West Palm Beach, Florida 33401

166For Petitioner, Padula & Wadsworth Construction Inc.:

173Thomas Shahady, Esquire

176Adorno & Yoss, P.A.

180350 East Las Olas Boulevard

185Suite 1700

187Fort Lauderdale, Florida 33301

191For Respondent, School Board of Broward County, Florida:

199Robert Paul Vignola, Esquire

203Broward County School Board

207Kathleen C. Wright Administrative Building

212600 Southeast Third Avenue, 11th Floor

218Fort Lauderdale, Florida 33301

222For Intervenor, James B. Pirtle Construction Company,

229Inc.:

230Usher L. Brown, Esquire

234Brown, Salzman, Weiss & Garganese, P.A.

240Two Landmark Center, Suite 660

245225 East Robinson Street

249Orlando, Florida 32801

252STATEMENT OF THE ISSUE

256Whether the Respondent, School Board of Broward County,

264Florida (Respondent or Board), may reject all bids as proposed

274for Bid No. 2002 - 02 - FC, Group A1, or whether such action is

289illegal, arbitrary, dishonest, or fraudulent.

294PRELIMINARY STATEMENT

296These ca ses came to the Division of Administrative

305Hearings by way of an underlying matter (also a bid challenge)

316during which case the Respondent determined it would reject

325all bids submitted for the bid. The Petitioners, Royal

334Concrete Concepts, Inc. (Royal), and Padula & Wadsworth

342Construction, Inc. (Padula), timely filed protests to the

350second decision; thereafter, the cases were scheduled for

358hearing. The findings of fact that follow more completely

367track the procedural course of this cause. The instant cas es

378dealt solely with the Board's decision to reject all bids.

388At the hearing the parties offered joint exhibits and

397individual exhibits, all of which the transcript more fully

406identifies. Similarly, all parties presented testimony of

413witnesses. Those individuals are also identified and noted in

422the transcript of this proceeding. At the conclusion of the

432hearing, the parties stipulated that they would file proposed

441recommended orders within 30 days of the filing of the

451transcript. All parties substantial ly complied with that

459stipulation and the P roposed R ecommended O rders have been

470fully considered in the preparation of this R ecommended O rder.

481FINDINGS OF FACT

4841. The Respondent is the entity charged with the

493responsibility of governing the public schools within the

501Broward County School District. As such, the acquisition of

510school properties and attendant improvements fall within the

518Board's legal authority. These cases involve the procurement

526of relocatable buildings suitable for classroom purposes.

5332. Pursuant to its authority, on or about December 27,

5432002, the Respondent issued a bid that is the subject matter

554of the instant challenge. The bid, identified in this record

564as Bid 2002 - 02 - FC, sought proposals for the procurement of

577district - wide

580relocatable buildings. In a prior time these buildings were

589known as "portable classrooms" or "portables."

5953. In the post - Hurricane Andrew world, these structures

605are now pre - engineered and constructed of concrete or steel

616(or a hybrid of both) and must be, b y design, capable of being

630relocated to various sites. The Petitioners, Royal and Padula

639jointly, and the Intervenor, James B. Pirtle Construction

647Company, Inc. (Pirtle or Intervenor), design, construct, and

655install such structures.

6584. In these cases the bid sought several distinct

667proposals. First, the project sought vendors who would

675provide and deliver concrete relocatable buildings (Group A1).

683Group A2 (not at issue in this proceeding) sought steel

693relocatable buildings. Group B (also not at issue in the

703instant case) sought site adaptation prices for landscaping,

711lighted covered walkways, steps, ramps, and other engineering

719incidental to the installation of the buildings.

7265. The advertisement for the bid carried the same

735generic information as to all groups. The bid documents also

745contained many terms that were applicable to all groups.

7546. Pertinent to the issues of these cases are the

764following excerpts from the bid document (Joint Exhibit 2).

773The order of

776the excerpts should not suggest any significance. The

784excerpts are listed in this manner solely for convenience

793sake:

794BASIS OF AWARD

797In order to meet the needs of the school

806system . . . each Award will be . . . up to

819three responsive and responsible bidders

824meeting specifications, terms and

828conditions. Individual projects will be

833issued . . . based upon lowest cost among

842one or more bidders per project as

849determined by the project manager.

854Therefore, it is necessary to bid on every

862item in the group, and all items in the

871group must m eet specifications in order to

879have the bid considered for award. Unit

886prices must be stated in the space provided

894on Document 00410 Bid Form. SBBC [the

901Respondent] reserves the right to procure

907goods from the second and third lowest

914bidders if: a) the lowest bidder cannot

921comply with delivery requirements or

926specifications; b) the lowest bidder is not

933in compliance with delivery requirements or

939specifications on current or previous

944orders; c) in cases of emergency; d) work

952may be issued to multiple contr actors if in

961the opinion of The School Board of Broward

969County, Florida or its staff the work

976cannot be completed by a single contractor

983in the specified time such as a Summer,

991Winter or Spring Break or if it is in the

1001best interest of SBBC to do so regardless

1009of reason.

1011ARTICLE 4 BIDDING PROCEDURES

10154.01 FORM AND STYLE OF BIDS

1021A. Bids shall be submitted on forms

1028identical to Document 00410, Bid Form, and

1035other standard forms included with the

1041Bidding Documents. The following documents

1046are required to be submitted with the Bid:

1054* * *

10576. SIGNED SEALED ARCHITECTURAL AND

1062ENGINEERING DESIGN DRAWINGS OF THE

1067STRUCTURES TO BE PROVIDED (FOR RELOCATABLE

1073BUILDINGS BID ONLY)

10765.03 REJECTION OF BIDS AND IRREGULAR

1082PROPOSALS

1083* * *

1086C. The Owner shall have the right to

1094reject any or all Bids, reject a Bid not

1103accompanied by a required bid security,

1109good faith deposit, or by other data

1116required by the Bid Documents, or reject a

1124Bid which is in any way incomplete,

1131irregular or otherwise not Responsive. Th e

1138Owner may waive any formality in the bid

1146requirements and award or not award the

1153contract in the best interests of The

1160School Board of Broward County, Florida.

1166(Emphasis in original not shown)

11717. In addition to the foregoing, the bid documents

1180contained detailed and specific design criteria that set forth

1189information such as the slope of roofs, the roof spans, the

1200mechanical systems, ventilation, plumbing, windows, and

1206stoops. These design criteria covered hundreds of topics and

1215encompassed virtually e very facet of the structures. To

1224review each bid proposal as to whether each design

1233specification was met would require countless man - hours.

12428. The issue of how to review the bid proposals was not

1254adequately anticipated by the Respondent. From the outset the

1263bid document evolved from unusual circumstances. Whether the

1271bid document was intended to be a request for proposals (RFP)

1282or an invitation to bid (ITB) was a primary confusion among

1293the Board's staff. If the proposals were to be deemed

1303responsive or not and then ranked solely on price (thus making

1314the bid process more like an ITB) how could staff effectively

1325determine the threshold question of responsiveness? If the

1333proposals were to be ranked based upon a point or qualitative

1344approach (more like an RFP) where were the criteria by which

1355to score the proposals? In fact, there were no objective

1365criteria disclosed in the bid document by which a proposal

1375could be evaluated.

13789. More curious is that no bidder brought this lack of

1389evaluation criteria to the Board's attention during the

1397mandatory bidder's conference. Moreover, no one challenged

1404the bid specifications. Presumably, the bidders believed it

1412was an "all or nothing" award. That is, if they were the

1424lowest responsive bidder, they would receive the award. The

1433question of who would be responsive and how that decision

1443would be resolved did not come to light until after the bids

1455had been opened.

145810. At the mandatory bidders' conference conducted on

1466January 14, 2003, the bidders posed questions i n the form of

1478requests for information. In response, the Respondent issued

1486six addenda intended to cover the questions posed. None of

1496the responses addressed how the bid proposals would be

1505evaluated.

150611. If anything, Addendum No. 3 added to confusion

1515related to what documents must be submitted with the bid

1525proposal. More specifically, Addendum No. 3 provided, in

1533pertinent part:

1535[Addendum 3, question and response to

1541inquiry]

15429. Can schematics be submitted with the

1549bid instead of the signed and sealed

1556architectural and engineering design

1560drawings of the structures that are

1566requested in Document Article 4.01.A.6?

1571Response: Signed and Sealed

1575Architectural/Structural Drawings are

1578required to be submitted with the Bid. The

1586Requirement for Mechanical and Electrical

1591signed and sealed drawing is waived,

1597however all engineering associated with the

1603Relocatable Buildings will require engineer

1608of record signed and sealed drawings and

1615calculations prior to issuance of building

1621permit DRC review.

162412. Nevertheles s, when the bid proposals were opened on

1634March 4, 2003, the Petitioners and the Intervenor were found

1644to be the three lowest bidders. If responsive, the Intervenor

1654would be considered the lowest bidder with the Petitioners

1663being considered alternate vendors for the procurement.

167013. Unsatisfied with the preliminary determination that

1677the Intervenor was the lowest bidder, the Petitioners timely

1686challenged the bid award. The Petitioners maintained that the

1695Intervenor had not timely provided sealed design dr awings as

1705required by the bid document. Petitioners argued that the

1714Intervenor had attempted to impermissibly amend their proposal

1722by late - filing a set of structural drawings for the bid.

173414. Thus the initial bid protest sought to determine

1743what design drawings were required by the bid and whether the

1754Intervenor had timely supplied such drawings. The Petitioners

1762contended that the Intervenor's submittal should be rejected

1770as non - responsive to the bid. Whether they had complied with

1782the full dictates o f the bid requirements was potentially at

1793issue as well.

179615. While the initial bid protest was referred to the

1806Division of Administrative Hearings and scheduled for formal

1814hearing, the parties continued to attempt to resolve the

1823issues. It was apparent that the bidders had not submitted

1833identical proposals. How the proposed products had been

1841compared and evaluated was difficult to determine.

184816. From the Respondent's committee members came the

1856disclosure that the decision of determining whether the

1864bid ders had complied with the bid ultimately came from three

1875fashioned questions. If the structure proposed was pre -

1884engineered, relocatable to various sites, and suitable for

1892educational purposes, the entry was deemed responsive. Based

1900upon this assessment the Petitioners and the Intervenor were

1909deemed responsive and their bids ranked based upon price.

191817. This approach did nothing to discern if the designs

1928were comparable in quality, if they met the bid design

1938criteria, or if the drawings were even suffi cient to comply

1949with the dictates of the bid.

195518. The first posting of the bid award for Group A1 was

1967entered March 18, 2003.

197119. On March 21, 2003, the Petitioners timely filed

1980their notices of intent to protest the award of Group A1 to

1992the Intervenor. Thereafter they timely filed the petitions to

2001protest the award and the initial protest was forwarded to the

2012Division of Administrative Hearings. The protests did not

2020encompass Group A2 or Group B.

202620. No bidder protested the proposed awards for Gro up A2

2037or Group B. In fact, the Respondent went forward on those

2048procurements and awarded contracts for those groups on April

20571, 2003. The Respondent did not award the contract award for

2068the Group at issue in this proceeding.

207521. It must be noted that the instant procurement is not

2086the Board's first experience with the procurement of concrete

2095relocatable classrooms. In fact, the Board has purchased

2103similar structures through a procurement contract that the

2111Palm Beach County School Board holds with its v endors. One of

2123the Respondent's concerns when the instant bids were reviewed

2132was why the cost per unit for the bids in this case was higher

2146than the Palm Beach County amount. As it turned out, the

2157installation economy of multiple units at one site directly

2166impacts the cost of the relocatable structures. Royal

2174confirmed this information after the bids had been opened.

218322. When the Respondent's staff met with its counsel in

2193preparation for the initial bid dispute (before the Board

2202elected to reject all bi ds) the cost of the bid, the lack of

2216full evaluation of the bidders' proposals, and the issues of

2226the first protest were openly discussed. By that time any

2236irregularities with the bid documents could not be repaired as

2246to the contracts

2249already awarded, but as to the instant matter the Respondent

2259could revisit the circumstances and determine its best course.

226823. As a result of that reassessment, the Respondent

2277elected to reject all bids regarding this group and attempt to

2288re - bid the procurement with more certain terms. To that end

2300on May 9, 2003, the Respondent issued a revised bid decision

2311that provided in pertinent part:

2316The Facilities and Construction Management

2321Division intends to recommend that The

2327School Board of Broward County, Florida, at

2334the School Board meeting on June 3, 2003,

2342reject all bids received for Group A1 and

2350authorize revising the bidding documents

2355and re - bidding. The rejection of all bids

2364received for Group A1 is made due to

2372serious flaws and ambiguities contained in

2378Document 00200 4.01.A - 6 as modified by

2386Addendum No. 3. The Division intends to

2393revise the bidding documents to delete the

2400requirements that bidders submit plans with

2406the bids; include ranges of unit quantities

2413within the bid form; include one or more

2421additional types of construction of the

2427classroom buildings including a composite

2432concrete/steel structure; and incorporate

2436within the new Invitation to Bid all

2443revised terms and conditions that were

2449released through addenda in this

2454procurement.

245524. The Petitioners timely filed protests regarding this

2463new decision by the Board and the instant action ensued.

247325. By issuing the revised decision to reject all bids

2483the Respondent intended to resolve all issues and to cure the

2494perceived problem with the lack of consistent evaluation of

2503the bidders' proposals. More specifically, the Respondent

2510would be able to assure that the project design could comport

2521with the specifications sought; specify whether architectural

2528or engineering drawings were required and when (it was hoped

2538th at the confusion over "architect" vs. "engineer" could be

2548eliminated); and obtain a substantial discount based upon

2556economies from multi - unit purchases for a single site. None

2567of the objectives sought were pre - textual or contrived.

2577Additionally, by avoiding any process that would require a

2586detailed reviewed of the bidders' proposals, countless man -

2595hours could be saved.

2599CONCLUSIONS OF LAW

260226. The Division of Administrative Hearings has

2609jurisdiction over the parties to and the subject matter of

2619these proc eedings. § § 120.569 and 120.57(3), Fla. Stat.

2629(2003).

263027. All parties have standing in this matter. The

2639Petitioners and the Intervenor have demonstrated their

2646interests will be materially affected by the decision of the

2656Board in connection with this bid. This conclusion is reached

2666based upon the determination that the Intervenor was

2674designated the primary vendor on the initial bid tabulation

2683and the Petitioners were each considered to be responsive

2692vendors that could conceivably receive orders under th e award.

270228. The standard of review in this matter is set forth

2713by statute. Section 120.57(3)(f), Florida Statutes, provides

2720in pertinent part:

2723. . . Unless otherwise provided by statute,

2731the burden of proof shall rest with the

2739party protesting the proposed agency

2744action. . . . In any bid - protest

2753proceeding contesting an intended agency

2758action to reject all bids, proposals, or

2765replies, the standard of review by an

2772administrative law judge shall be

2777whether the agency's intended action is

2783illegal, arbitra ry, dishonest, or

2788fraudulent.

278929. The Petitioners must therefore establish that the

2797Board action to reject all bids is illegal, arbitrary,

2806dishonest, or fraudulent. In contrast, if the decision is

2815supported by rational, legal, honest, and unambiguous

2822reasoning such decision should stand. This conclusion is

2830based upon the premise that the Board has wide discretion in

2841this matter that should not be overturned even if reasonable

2851persons might disagree. See Scientific Games, Inc. v. Dittler

2860Brothers, Inc. , 586 So. 2d 1128 (Fla. 1st DCA 1991).

287030. Essentially, these cases turn on the issue of

2879whether or not the Board's decision to reject all bids is

2890arbitrary. The Petitioners argue that the Board's decision to

2899reject all bids was contrived after it realized the initial

2909bid protest was meritorious as to the Intervenor's failure to

2919submit required documen ts. If the Board's decision wa s

2929contrived to meet the factual circumstances of these cases,

2938the decision may not stand.

294331. If the bid process was seriou sly flawed as claimed

2954by the Board, despite the Petitioners' protest to the

2963contrary, the rejection of all bids should be upheld. In

2973Caber Systems, Inc. v. Department of General Services , 530 So.

29832d. 325 (Fla. 1st DCA 1988) the court was faced with a similar

2996dilemma. The Caber decision proves instructive in this

3004matter.

300532. In Caber the court found that when the agency in its

3017process to review a bid protest discovered valid grounds for

3027rejecting all bids (for reasons that were neither arbitrary or

3037cap ricious) it was authorized to do so. Similarly, when

3047preparing for the hearing in the underlying or initial protest

3057in these cases, the Respondent discovered all of the

3066underlying facts that gave rise to its decision to reject all

3077bids. Those underlying facts were neither contrived nor

3085arbitrarily determined.

308733. In fact, as the history and circumstances of this

3097bid process became more studied, the basis for determining who

3107should prevail and how the Board's employees should fairly

3116review the proposals became more mired in the uncertainty of

3126the tainted process. If price were to be the sole determining

3137factor, the remainder of the specifications would prove

3145meaningless and, more significantly to the Board's concerns,

3153perhaps unenforceable. If the engineering and qualitative

3160specifications were to bear weight, how were the proposals to

3170be fairly reviewed? There were no performance standards by

3179which a committee might assign points or ratings.

318734. The three criteria by which all applicants were

3196initi ally reviewed did not address specific items listed among

3206the design requirements. Moreover, none of the bidders knew

3215or could have known that the design criteria would be waived

3226in whole or part. Clearly a proposal that did not include the

3238waived item could receive a financial advantage over a

3247competitor who included the item. Arguably, the price of any

3257proposal that included the waived item would be higher. For

3267example, if the bid design called for a covered doorway into

3278the unit and a bidder failed t o include that item, the cost

3291basis for the uncovered entry would arguably be less than the

3302unit that offered the covered doorway.

330835. But in truth, the Board did nothing to attempt to

3319resolve the issues of whether the designs submitted by the

3329parties fairly or fully met the design items requested by the

3340bid. Instead, faced with hours of evaluation, the committee

3349members "contrived" three questions to determine if the

3357proposal could be deemed responsive. The initial protest

3365exposed the inadequacy of th is approach. When called on the

3376matter and when forced to evaluate the proposals from the

3386dictates limited by the four corners of the bid document, it

3397was apparent that the only fair resolution was to reject all

3408bids. That is exactly what the Board attempted to do.

341836. In order to cure the problems discovered through the

3428review of this bid process the Board elected to take the

3439matter back to the drawing board and to begin the process

3450anew. This decision will hopefully result in clear

3458specifications an d review criteria. If the Board wants a

"3468concrete reinforced structure" it can define specifically

3475what that term means. If the Board is willing to accept a

3487steel structure with an applied concrete coating, it can do

3497so. If hybrid buildings are acceptable all parties will know

3507what is acceptable. More important, the Board will be able to

3518determine and disclose if price alone will drive the award of

3529the bid. If the Board wants the flexibility to award design

3540points for choosing a higher standard (and th ereby assume a

3551higher cost) all parties will be aware of the potential to

3562build that flexibility to their proposal. Currently, there is

3571no way to determine if the parties were submitting the same

3582quality product. No assessment was or could be made to yield

3593that determination. Accordingly, the Board's decision to

3600reject all proposals must be upheld.

3606RECOMMENDATION

3607Based on the foregoing Findings of Fact and Conclusions

3616of Law, it is RECOMMENDED that the School Board of Broward

3627County enter a Final Order a ffirming the decision to reject

3638all bids in this matter.

3643DONE AND ENTERED this 20th day of November 2003 in

3653Tallahassee, Leon County, Florida.

3657S

3658___________________________________

3659J. D. PARRISH

3662Administrative Law Judge

3665Division of Administrative Hearings

3669The DeSoto Building

36721230 Apalachee Parkway

3675Tallahassee, Florida 32399 - 3060

3680(850) 488 - 9675 SUNCOM 278 - 9675

3688Fax Filing (850) 921 - 6847

3694www.doah.state.fl.us

3695Filed with the Clerk of the

3701Division of Administrative Hearings

3705this 20th day of November 2003.

3711COPIES FURNISHED:

3713Dr. Franklin L. Till, Jr.

3718Superintendent

3719Broward County School Board

3723600 S outheast Third Avenue

3728Fort Lauderdale, Florida 33301 - 3125

3734Daniel J. Woodring, General Counsel

3739Department of Education

3742325 West Gaines Street

37461244 Turlington Building

3749Tallahassee, Florida 32399 - 0400

3754Usher Larry Brown, Esquire

3758Brown, Salzman, Weiss & Garganese, P.A.

3764225 East Robinson Street, Suite 660

3770Orlando, Florida 32801

3773Steven L. Schwarzberg, Esquire

3777Schwarzberg & Associates

3780Esperante, Suite 210

3783222 Lakeview Avenue

3786West Palm Beach, Florida 33401

3791Thomas R. Shahady, Esquire

3795Adorno & Yoss, P.A.

3799350 East Las Olas Boulevard, Suite 1700

3806Fort Lauderdale, Florida 33301

3810Robert Paul Vignola, Esquire

3814Broward County School Board

3818K. C. Wright Administrative Building

3823600 Southeast Third Avenue, 11th Floor

3829Fort Lauderdale, Florida 33301

3833NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

3839All parties have the right to submit written exceptions within

384910 days from the date of this Recommended Order. Any

3859exceptions to this Recommended Order should be filed with the

3869agency that will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 12/19/2003
Proceedings: Notice of Unavailability (filed by Respondent via facsimile).
PDF:
Date: 12/18/2003
Proceedings: Final Order filed.
PDF:
Date: 12/16/2003
Proceedings: Agency Final Order
PDF:
Date: 11/20/2003
Proceedings: Recommended Order
PDF:
Date: 11/20/2003
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 11/20/2003
Proceedings: Recommended Order (hearing held August 20-21, 2003). CASE CLOSED.
PDF:
Date: 10/17/2003
Proceedings: Letter to J. Lambert from S. Schwarzberg enclosing disk of Petitioner`s proposed recommended order filed.
PDF:
Date: 10/16/2003
Proceedings: Letter to Judge Parrish from U. Brown enclosing James B. Pirtle Construction Company, Inc.`s proposed recommended order on a disk filed.
PDF:
Date: 10/16/2003
Proceedings: Petitioner Royal Concrete Concepts, Inc`s Proposed Recommended Order with Findings of Fact and Conclusions of Law (filed via facsimile).
PDF:
Date: 10/15/2003
Proceedings: Petitioner Padula & Wadsworth Inc.`s Proposed Recommended Order (filed via facsimile).
PDF:
Date: 10/15/2003
Proceedings: Respondent School Board`s Proposed Recommended Order filed.
PDF:
Date: 10/15/2003
Proceedings: Intervenor Pirtle`s Proposed Recommended Order filed.
Date: 09/12/2003
Proceedings: Transcript (Volume 1 and 2) filed.
PDF:
Date: 08/26/2003
Proceedings: Notice of Filing Affidavit of Denis Herrman filed by Respondent.
Date: 08/25/2003
Proceedings: Joint Hearing Exhibits (1 box) filed.
Date: 08/20/2003
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 08/19/2003
Proceedings: Joint Pre-hearing Stipulation (filed via facsimile).
PDF:
Date: 08/14/2003
Proceedings: Notice of Taking Deposition (A. Kwan) filed via facsimile.
PDF:
Date: 08/12/2003
Proceedings: Order Granting Petition to Intervene (by James B. Pirtle Construction Company, Inc.).
PDF:
Date: 08/12/2003
Proceedings: Respondent School Board`s Response to Request to Produce from Petitioner Royal Concrete (filed via facsimile).
PDF:
Date: 08/12/2003
Proceedings: Respondent School Board`s Answers and Objections to First Set of Interrogatories from Petitioner Royal Concrete (filed via facsimile).
PDF:
Date: 08/12/2003
Proceedings: Petitioner, Royal Concrete Concepts, Inc.`s First Request for Production to Respondent, Broward County School Board (filed via facsimile).
PDF:
Date: 08/12/2003
Proceedings: Petitioner, Royal Concrete Concepts, Inc.`s First Set of Interrogatories to Respondent, Broward County School Board (filed via facsimile).
PDF:
Date: 08/07/2003
Proceedings: Notice of Filing Petitoiner, Padula & Wadsworth Construction, Inc.`s, Response to Respondent, School Board`s First Request to Produce (filed via facsimile).
PDF:
Date: 08/07/2003
Proceedings: Notice of Filing Petitioner, Padula & Wadsworth Construction, Inc`s Sworn Answers and Objections to Respondents First Set of Interrogatories (filed via facsimile).
PDF:
Date: 08/04/2003
Proceedings: James B. Pirtle Construction Company, Inc.`s Petition for Leave to Intervene (filed via facsimile).
PDF:
Date: 08/01/2003
Proceedings: Respondent School Board`s Second Request to Produce to Petitioner Padula & Wadsworth (filed via facsimile).
PDF:
Date: 08/01/2003
Proceedings: Notice of Taking Depositions (2), (of the unidentified "replacement" architect as referenced in Royal Concrete`s Answers to Interrogatories, S. Ford, W. Sanger, and unidentified expert witness for Padula & Wadsworth, W. Wadsworth) filed via facsimile.
PDF:
Date: 07/31/2003
Proceedings: Notice of Filing Petitioner, Royal Concrete Concepts, Inc.`s Sworn Answers and Objections to Respondent`s First Set of Interrogatories (filed via facsimile).
PDF:
Date: 07/31/2003
Proceedings: Respondent School Board`s Second Request to Produce to Petitioner Royal Concrete (filed via facsimile).
PDF:
Date: 07/31/2003
Proceedings: Notice of Filing Petitioner, Royal Concrete Concepts, Inc.`s, Response to Respondent, School Board`s First Request to Produce (filed via facsimile).
PDF:
Date: 07/31/2003
Proceedings: Notice of Filing Petitioner, Royal Concrete Concepts, Inc.`s Unsworn Answers to Respondent`s First Set of Interrogatories (filed via facsimile).
PDF:
Date: 07/25/2003
Proceedings: Re-Notice of Taking Deposition Duces Tecum (2), (M. Geary, and The Person with Most Knowledge Regarding: the procurement of the bid by James B. Pirtle Construction, Inc., submitted on March 4, 2003) filed via facsimile.
PDF:
Date: 07/18/2003
Proceedings: Notice of Taking Depositions (H. Padula, D. Locke, and Petitioners` Expert Witnesses) filed via facsimile.
PDF:
Date: 07/16/2003
Proceedings: Subpoena Duces Tecum (2), (M. Geary and The Person with Knowledge Regarding: (a) The Procurement of the Bid by James B. Pirtle Construction, Inc.,) filed via facsimile.
PDF:
Date: 07/16/2003
Proceedings: Notice of Taking Deposition Duces Tecum (2), (The Person with Knowledge Regarding: (a) The Procurement of the Bid by James B. Pirtle Construction, Inc., and M. Geary) filed via facsimile.
PDF:
Date: 07/11/2003
Proceedings: Amended Notice of Hearing (hearing set for August 20 and 21, 2003; 9:00 a.m.; Fort Lauderdale, FL, amended as to Location of Hearing).
PDF:
Date: 07/09/2003
Proceedings: Joint Motion to Change Location of Final Hearing (filed by R. Vignola via facsimile).
PDF:
Date: 07/09/2003
Proceedings: Respondent School Board`s First Set of Interrogatories to Petitioner Padula & Wadsworth (filed via facsimile).
PDF:
Date: 07/09/2003
Proceedings: Respondent School Board`s First Request to Produce to Petitioner Padula & Wadsworth (filed via facsimile).
PDF:
Date: 07/09/2003
Proceedings: Respondent School Board`s First Request to Produce to Petitioner Royal Concrete (filed via facsimile).
PDF:
Date: 07/09/2003
Proceedings: Respondent School Board`s First Set of Interrogatories to Petitioner Royal Concrete (filed via facsimile).
PDF:
Date: 07/08/2003
Proceedings: Notice of Unavailability (filed R. Vignola via facsimile).
PDF:
Date: 07/07/2003
Proceedings: Notice of Unavailability (filed by S. Schwarzberg via facsimile).
PDF:
Date: 07/01/2003
Proceedings: Amended Joint Motion for Consolidation and Continuance (filed by Respondent via facsimile).
PDF:
Date: 07/01/2003
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 07/01/2003
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for August 20 and 21, 2003; 9:00 a.m.; Fort Lauderdale, FL).
PDF:
Date: 07/01/2003
Proceedings: Order Granting Motion for Consolidation issued. (consolidated cases are: 03-002220BID, 03-002221BID)
PDF:
Date: 06/30/2003
Proceedings: Joint Motion for Consolidation and Continuance (of case no(s): 03-2221BID, 03-2220BID) filed via facsimile.
PDF:
Date: 06/26/2003
Proceedings: Joint Request for Telephone Status Conference (filed by Respondent via facsimile).
PDF:
Date: 06/23/2003
Proceedings: Notice of Hearing (hearing set for July 7 and 8, 2003; 9:00 a.m.; Fort Lauderdale, FL).
PDF:
Date: 06/17/2003
Proceedings: Letter to Judge Smith from S. Schwarzberg requesting new bid cases be assigned to Judge J. Parrish (filed via facsimile).
PDF:
Date: 06/13/2003
Proceedings: Formal Bid Protest filed.
PDF:
Date: 06/13/2003
Proceedings: Advertisement for Bids filed.
PDF:
Date: 06/13/2003
Proceedings: Formal Written Protest filed.
PDF:
Date: 06/13/2003
Proceedings: Request for Formal DOAH Hearing filed.
PDF:
Date: 06/13/2003
Proceedings: Agency referral filed.

Case Information

Judge:
J. D. PARRISH
Date Filed:
06/13/2003
Date Assignment:
06/13/2003
Last Docket Entry:
12/19/2003
Location:
Fort Lauderdale, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (2):