03-002220BID
Royal Concrete Concepts, Inc. vs.
Broward County School Board
Status: Closed
Recommended Order on Thursday, November 20, 2003.
Recommended Order on Thursday, November 20, 2003.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8ROYAL CONCRETE CONCEPTS, )
12INC., )
14)
15Petitioner, )
17) Case No. 03 - 2220BID
23vs. )
25)
26BROWARD COUNTY SCHOOL BOARD, )
31)
32Respondent, )
34)
35and )
37)
38JAMES B. PIRTLE CONS TRUCTION )
44COMPANY, INC., )
47)
48I ntervenor. )
51)
52PAD ULA & WADSWORTH )
57CONSTRUCTION COMPANY , )
60)
61P etitioner, )
64) Case No. 03 - 2221BID
70vs . )
73)
74BROWARD COUNTY SCHOO L BOARD, )
80)
81R espondent , )
84)
85and )
87)
88J AMES B. PIRTLE CONST RUCTION )
95COMPANY, INC., )
98)
99Intervenor. )
101____________________ _________
103RECOMMENDED ORDER
105Pursuant to notice a formal hearing was held in these
115cases on August 20 - 21, 2003, in Fort Lauderdale, Florida,
126before J. D. Parrish, a designated Administrative Law Judge of
136the Division of Administrative Hearings.
141APPEARANCES
142For Petitioner, Royal Concrete Concepts, Inc.:
148Steven L. Schwartberg, Esquire
152Schwarzberg & Associates
155Esperante, Suite 210
158222 Lakeview Avenue
161West Palm Beach, Florida 33401
166For Petitioner, Padula & Wadsworth Construction Inc.:
173Thomas Shahady, Esquire
176Adorno & Yoss, P.A.
180350 East Las Olas Boulevard
185Suite 1700
187Fort Lauderdale, Florida 33301
191For Respondent, School Board of Broward County, Florida:
199Robert Paul Vignola, Esquire
203Broward County School Board
207Kathleen C. Wright Administrative Building
212600 Southeast Third Avenue, 11th Floor
218Fort Lauderdale, Florida 33301
222For Intervenor, James B. Pirtle Construction Company,
229Inc.:
230Usher L. Brown, Esquire
234Brown, Salzman, Weiss & Garganese, P.A.
240Two Landmark Center, Suite 660
245225 East Robinson Street
249Orlando, Florida 32801
252STATEMENT OF THE ISSUE
256Whether the Respondent, School Board of Broward County,
264Florida (Respondent or Board), may reject all bids as proposed
274for Bid No. 2002 - 02 - FC, Group A1, or whether such action is
289illegal, arbitrary, dishonest, or fraudulent.
294PRELIMINARY STATEMENT
296These ca ses came to the Division of Administrative
305Hearings by way of an underlying matter (also a bid challenge)
316during which case the Respondent determined it would reject
325all bids submitted for the bid. The Petitioners, Royal
334Concrete Concepts, Inc. (Royal), and Padula & Wadsworth
342Construction, Inc. (Padula), timely filed protests to the
350second decision; thereafter, the cases were scheduled for
358hearing. The findings of fact that follow more completely
367track the procedural course of this cause. The instant cas es
378dealt solely with the Board's decision to reject all bids.
388At the hearing the parties offered joint exhibits and
397individual exhibits, all of which the transcript more fully
406identifies. Similarly, all parties presented testimony of
413witnesses. Those individuals are also identified and noted in
422the transcript of this proceeding. At the conclusion of the
432hearing, the parties stipulated that they would file proposed
441recommended orders within 30 days of the filing of the
451transcript. All parties substantial ly complied with that
459stipulation and the P roposed R ecommended O rders have been
470fully considered in the preparation of this R ecommended O rder.
481FINDINGS OF FACT
4841. The Respondent is the entity charged with the
493responsibility of governing the public schools within the
501Broward County School District. As such, the acquisition of
510school properties and attendant improvements fall within the
518Board's legal authority. These cases involve the procurement
526of relocatable buildings suitable for classroom purposes.
5332. Pursuant to its authority, on or about December 27,
5432002, the Respondent issued a bid that is the subject matter
554of the instant challenge. The bid, identified in this record
564as Bid 2002 - 02 - FC, sought proposals for the procurement of
577district - wide
580relocatable buildings. In a prior time these buildings were
589known as "portable classrooms" or "portables."
5953. In the post - Hurricane Andrew world, these structures
605are now pre - engineered and constructed of concrete or steel
616(or a hybrid of both) and must be, b y design, capable of being
630relocated to various sites. The Petitioners, Royal and Padula
639jointly, and the Intervenor, James B. Pirtle Construction
647Company, Inc. (Pirtle or Intervenor), design, construct, and
655install such structures.
6584. In these cases the bid sought several distinct
667proposals. First, the project sought vendors who would
675provide and deliver concrete relocatable buildings (Group A1).
683Group A2 (not at issue in this proceeding) sought steel
693relocatable buildings. Group B (also not at issue in the
703instant case) sought site adaptation prices for landscaping,
711lighted covered walkways, steps, ramps, and other engineering
719incidental to the installation of the buildings.
7265. The advertisement for the bid carried the same
735generic information as to all groups. The bid documents also
745contained many terms that were applicable to all groups.
7546. Pertinent to the issues of these cases are the
764following excerpts from the bid document (Joint Exhibit 2).
773The order of
776the excerpts should not suggest any significance. The
784excerpts are listed in this manner solely for convenience
793sake:
794BASIS OF AWARD
797In order to meet the needs of the school
806system . . . each Award will be . . . up to
819three responsive and responsible bidders
824meeting specifications, terms and
828conditions. Individual projects will be
833issued . . . based upon lowest cost among
842one or more bidders per project as
849determined by the project manager.
854Therefore, it is necessary to bid on every
862item in the group, and all items in the
871group must m eet specifications in order to
879have the bid considered for award. Unit
886prices must be stated in the space provided
894on Document 00410 Bid Form. SBBC [the
901Respondent] reserves the right to procure
907goods from the second and third lowest
914bidders if: a) the lowest bidder cannot
921comply with delivery requirements or
926specifications; b) the lowest bidder is not
933in compliance with delivery requirements or
939specifications on current or previous
944orders; c) in cases of emergency; d) work
952may be issued to multiple contr actors if in
961the opinion of The School Board of Broward
969County, Florida or its staff the work
976cannot be completed by a single contractor
983in the specified time such as a Summer,
991Winter or Spring Break or if it is in the
1001best interest of SBBC to do so regardless
1009of reason.
1011ARTICLE 4 BIDDING PROCEDURES
10154.01 FORM AND STYLE OF BIDS
1021A. Bids shall be submitted on forms
1028identical to Document 00410, Bid Form, and
1035other standard forms included with the
1041Bidding Documents. The following documents
1046are required to be submitted with the Bid:
1054* * *
10576. SIGNED SEALED ARCHITECTURAL AND
1062ENGINEERING DESIGN DRAWINGS OF THE
1067STRUCTURES TO BE PROVIDED (FOR RELOCATABLE
1073BUILDINGS BID ONLY)
10765.03 REJECTION OF BIDS AND IRREGULAR
1082PROPOSALS
1083* * *
1086C. The Owner shall have the right to
1094reject any or all Bids, reject a Bid not
1103accompanied by a required bid security,
1109good faith deposit, or by other data
1116required by the Bid Documents, or reject a
1124Bid which is in any way incomplete,
1131irregular or otherwise not Responsive. Th e
1138Owner may waive any formality in the bid
1146requirements and award or not award the
1153contract in the best interests of The
1160School Board of Broward County, Florida.
1166(Emphasis in original not shown)
11717. In addition to the foregoing, the bid documents
1180contained detailed and specific design criteria that set forth
1189information such as the slope of roofs, the roof spans, the
1200mechanical systems, ventilation, plumbing, windows, and
1206stoops. These design criteria covered hundreds of topics and
1215encompassed virtually e very facet of the structures. To
1224review each bid proposal as to whether each design
1233specification was met would require countless man - hours.
12428. The issue of how to review the bid proposals was not
1254adequately anticipated by the Respondent. From the outset the
1263bid document evolved from unusual circumstances. Whether the
1271bid document was intended to be a request for proposals (RFP)
1282or an invitation to bid (ITB) was a primary confusion among
1293the Board's staff. If the proposals were to be deemed
1303responsive or not and then ranked solely on price (thus making
1314the bid process more like an ITB) how could staff effectively
1325determine the threshold question of responsiveness? If the
1333proposals were to be ranked based upon a point or qualitative
1344approach (more like an RFP) where were the criteria by which
1355to score the proposals? In fact, there were no objective
1365criteria disclosed in the bid document by which a proposal
1375could be evaluated.
13789. More curious is that no bidder brought this lack of
1389evaluation criteria to the Board's attention during the
1397mandatory bidder's conference. Moreover, no one challenged
1404the bid specifications. Presumably, the bidders believed it
1412was an "all or nothing" award. That is, if they were the
1424lowest responsive bidder, they would receive the award. The
1433question of who would be responsive and how that decision
1443would be resolved did not come to light until after the bids
1455had been opened.
145810. At the mandatory bidders' conference conducted on
1466January 14, 2003, the bidders posed questions i n the form of
1478requests for information. In response, the Respondent issued
1486six addenda intended to cover the questions posed. None of
1496the responses addressed how the bid proposals would be
1505evaluated.
150611. If anything, Addendum No. 3 added to confusion
1515related to what documents must be submitted with the bid
1525proposal. More specifically, Addendum No. 3 provided, in
1533pertinent part:
1535[Addendum 3, question and response to
1541inquiry]
15429. Can schematics be submitted with the
1549bid instead of the signed and sealed
1556architectural and engineering design
1560drawings of the structures that are
1566requested in Document Article 4.01.A.6?
1571Response: Signed and Sealed
1575Architectural/Structural Drawings are
1578required to be submitted with the Bid. The
1586Requirement for Mechanical and Electrical
1591signed and sealed drawing is waived,
1597however all engineering associated with the
1603Relocatable Buildings will require engineer
1608of record signed and sealed drawings and
1615calculations prior to issuance of building
1621permit DRC review.
162412. Nevertheles s, when the bid proposals were opened on
1634March 4, 2003, the Petitioners and the Intervenor were found
1644to be the three lowest bidders. If responsive, the Intervenor
1654would be considered the lowest bidder with the Petitioners
1663being considered alternate vendors for the procurement.
167013. Unsatisfied with the preliminary determination that
1677the Intervenor was the lowest bidder, the Petitioners timely
1686challenged the bid award. The Petitioners maintained that the
1695Intervenor had not timely provided sealed design dr awings as
1705required by the bid document. Petitioners argued that the
1714Intervenor had attempted to impermissibly amend their proposal
1722by late - filing a set of structural drawings for the bid.
173414. Thus the initial bid protest sought to determine
1743what design drawings were required by the bid and whether the
1754Intervenor had timely supplied such drawings. The Petitioners
1762contended that the Intervenor's submittal should be rejected
1770as non - responsive to the bid. Whether they had complied with
1782the full dictates o f the bid requirements was potentially at
1793issue as well.
179615. While the initial bid protest was referred to the
1806Division of Administrative Hearings and scheduled for formal
1814hearing, the parties continued to attempt to resolve the
1823issues. It was apparent that the bidders had not submitted
1833identical proposals. How the proposed products had been
1841compared and evaluated was difficult to determine.
184816. From the Respondent's committee members came the
1856disclosure that the decision of determining whether the
1864bid ders had complied with the bid ultimately came from three
1875fashioned questions. If the structure proposed was pre -
1884engineered, relocatable to various sites, and suitable for
1892educational purposes, the entry was deemed responsive. Based
1900upon this assessment the Petitioners and the Intervenor were
1909deemed responsive and their bids ranked based upon price.
191817. This approach did nothing to discern if the designs
1928were comparable in quality, if they met the bid design
1938criteria, or if the drawings were even suffi cient to comply
1949with the dictates of the bid.
195518. The first posting of the bid award for Group A1 was
1967entered March 18, 2003.
197119. On March 21, 2003, the Petitioners timely filed
1980their notices of intent to protest the award of Group A1 to
1992the Intervenor. Thereafter they timely filed the petitions to
2001protest the award and the initial protest was forwarded to the
2012Division of Administrative Hearings. The protests did not
2020encompass Group A2 or Group B.
202620. No bidder protested the proposed awards for Gro up A2
2037or Group B. In fact, the Respondent went forward on those
2048procurements and awarded contracts for those groups on April
20571, 2003. The Respondent did not award the contract award for
2068the Group at issue in this proceeding.
207521. It must be noted that the instant procurement is not
2086the Board's first experience with the procurement of concrete
2095relocatable classrooms. In fact, the Board has purchased
2103similar structures through a procurement contract that the
2111Palm Beach County School Board holds with its v endors. One of
2123the Respondent's concerns when the instant bids were reviewed
2132was why the cost per unit for the bids in this case was higher
2146than the Palm Beach County amount. As it turned out, the
2157installation economy of multiple units at one site directly
2166impacts the cost of the relocatable structures. Royal
2174confirmed this information after the bids had been opened.
218322. When the Respondent's staff met with its counsel in
2193preparation for the initial bid dispute (before the Board
2202elected to reject all bi ds) the cost of the bid, the lack of
2216full evaluation of the bidders' proposals, and the issues of
2226the first protest were openly discussed. By that time any
2236irregularities with the bid documents could not be repaired as
2246to the contracts
2249already awarded, but as to the instant matter the Respondent
2259could revisit the circumstances and determine its best course.
226823. As a result of that reassessment, the Respondent
2277elected to reject all bids regarding this group and attempt to
2288re - bid the procurement with more certain terms. To that end
2300on May 9, 2003, the Respondent issued a revised bid decision
2311that provided in pertinent part:
2316The Facilities and Construction Management
2321Division intends to recommend that The
2327School Board of Broward County, Florida, at
2334the School Board meeting on June 3, 2003,
2342reject all bids received for Group A1 and
2350authorize revising the bidding documents
2355and re - bidding. The rejection of all bids
2364received for Group A1 is made due to
2372serious flaws and ambiguities contained in
2378Document 00200 4.01.A - 6 as modified by
2386Addendum No. 3. The Division intends to
2393revise the bidding documents to delete the
2400requirements that bidders submit plans with
2406the bids; include ranges of unit quantities
2413within the bid form; include one or more
2421additional types of construction of the
2427classroom buildings including a composite
2432concrete/steel structure; and incorporate
2436within the new Invitation to Bid all
2443revised terms and conditions that were
2449released through addenda in this
2454procurement.
245524. The Petitioners timely filed protests regarding this
2463new decision by the Board and the instant action ensued.
247325. By issuing the revised decision to reject all bids
2483the Respondent intended to resolve all issues and to cure the
2494perceived problem with the lack of consistent evaluation of
2503the bidders' proposals. More specifically, the Respondent
2510would be able to assure that the project design could comport
2521with the specifications sought; specify whether architectural
2528or engineering drawings were required and when (it was hoped
2538th at the confusion over "architect" vs. "engineer" could be
2548eliminated); and obtain a substantial discount based upon
2556economies from multi - unit purchases for a single site. None
2567of the objectives sought were pre - textual or contrived.
2577Additionally, by avoiding any process that would require a
2586detailed reviewed of the bidders' proposals, countless man -
2595hours could be saved.
2599CONCLUSIONS OF LAW
260226. The Division of Administrative Hearings has
2609jurisdiction over the parties to and the subject matter of
2619these proc eedings. § § 120.569 and 120.57(3), Fla. Stat.
2629(2003).
263027. All parties have standing in this matter. The
2639Petitioners and the Intervenor have demonstrated their
2646interests will be materially affected by the decision of the
2656Board in connection with this bid. This conclusion is reached
2666based upon the determination that the Intervenor was
2674designated the primary vendor on the initial bid tabulation
2683and the Petitioners were each considered to be responsive
2692vendors that could conceivably receive orders under th e award.
270228. The standard of review in this matter is set forth
2713by statute. Section 120.57(3)(f), Florida Statutes, provides
2720in pertinent part:
2723. . . Unless otherwise provided by statute,
2731the burden of proof shall rest with the
2739party protesting the proposed agency
2744action. . . . In any bid - protest
2753proceeding contesting an intended agency
2758action to reject all bids, proposals, or
2765replies, the standard of review by an
2772administrative law judge shall be
2777whether the agency's intended action is
2783illegal, arbitra ry, dishonest, or
2788fraudulent.
278929. The Petitioners must therefore establish that the
2797Board action to reject all bids is illegal, arbitrary,
2806dishonest, or fraudulent. In contrast, if the decision is
2815supported by rational, legal, honest, and unambiguous
2822reasoning such decision should stand. This conclusion is
2830based upon the premise that the Board has wide discretion in
2841this matter that should not be overturned even if reasonable
2851persons might disagree. See Scientific Games, Inc. v. Dittler
2860Brothers, Inc. , 586 So. 2d 1128 (Fla. 1st DCA 1991).
287030. Essentially, these cases turn on the issue of
2879whether or not the Board's decision to reject all bids is
2890arbitrary. The Petitioners argue that the Board's decision to
2899reject all bids was contrived after it realized the initial
2909bid protest was meritorious as to the Intervenor's failure to
2919submit required documen ts. If the Board's decision wa s
2929contrived to meet the factual circumstances of these cases,
2938the decision may not stand.
294331. If the bid process was seriou sly flawed as claimed
2954by the Board, despite the Petitioners' protest to the
2963contrary, the rejection of all bids should be upheld. In
2973Caber Systems, Inc. v. Department of General Services , 530 So.
29832d. 325 (Fla. 1st DCA 1988) the court was faced with a similar
2996dilemma. The Caber decision proves instructive in this
3004matter.
300532. In Caber the court found that when the agency in its
3017process to review a bid protest discovered valid grounds for
3027rejecting all bids (for reasons that were neither arbitrary or
3037cap ricious) it was authorized to do so. Similarly, when
3047preparing for the hearing in the underlying or initial protest
3057in these cases, the Respondent discovered all of the
3066underlying facts that gave rise to its decision to reject all
3077bids. Those underlying facts were neither contrived nor
3085arbitrarily determined.
308733. In fact, as the history and circumstances of this
3097bid process became more studied, the basis for determining who
3107should prevail and how the Board's employees should fairly
3116review the proposals became more mired in the uncertainty of
3126the tainted process. If price were to be the sole determining
3137factor, the remainder of the specifications would prove
3145meaningless and, more significantly to the Board's concerns,
3153perhaps unenforceable. If the engineering and qualitative
3160specifications were to bear weight, how were the proposals to
3170be fairly reviewed? There were no performance standards by
3179which a committee might assign points or ratings.
318734. The three criteria by which all applicants were
3196initi ally reviewed did not address specific items listed among
3206the design requirements. Moreover, none of the bidders knew
3215or could have known that the design criteria would be waived
3226in whole or part. Clearly a proposal that did not include the
3238waived item could receive a financial advantage over a
3247competitor who included the item. Arguably, the price of any
3257proposal that included the waived item would be higher. For
3267example, if the bid design called for a covered doorway into
3278the unit and a bidder failed t o include that item, the cost
3291basis for the uncovered entry would arguably be less than the
3302unit that offered the covered doorway.
330835. But in truth, the Board did nothing to attempt to
3319resolve the issues of whether the designs submitted by the
3329parties fairly or fully met the design items requested by the
3340bid. Instead, faced with hours of evaluation, the committee
3349members "contrived" three questions to determine if the
3357proposal could be deemed responsive. The initial protest
3365exposed the inadequacy of th is approach. When called on the
3376matter and when forced to evaluate the proposals from the
3386dictates limited by the four corners of the bid document, it
3397was apparent that the only fair resolution was to reject all
3408bids. That is exactly what the Board attempted to do.
341836. In order to cure the problems discovered through the
3428review of this bid process the Board elected to take the
3439matter back to the drawing board and to begin the process
3450anew. This decision will hopefully result in clear
3458specifications an d review criteria. If the Board wants a
"3468concrete reinforced structure" it can define specifically
3475what that term means. If the Board is willing to accept a
3487steel structure with an applied concrete coating, it can do
3497so. If hybrid buildings are acceptable all parties will know
3507what is acceptable. More important, the Board will be able to
3518determine and disclose if price alone will drive the award of
3529the bid. If the Board wants the flexibility to award design
3540points for choosing a higher standard (and th ereby assume a
3551higher cost) all parties will be aware of the potential to
3562build that flexibility to their proposal. Currently, there is
3571no way to determine if the parties were submitting the same
3582quality product. No assessment was or could be made to yield
3593that determination. Accordingly, the Board's decision to
3600reject all proposals must be upheld.
3606RECOMMENDATION
3607Based on the foregoing Findings of Fact and Conclusions
3616of Law, it is RECOMMENDED that the School Board of Broward
3627County enter a Final Order a ffirming the decision to reject
3638all bids in this matter.
3643DONE AND ENTERED this 20th day of November 2003 in
3653Tallahassee, Leon County, Florida.
3657S
3658___________________________________
3659J. D. PARRISH
3662Administrative Law Judge
3665Division of Administrative Hearings
3669The DeSoto Building
36721230 Apalachee Parkway
3675Tallahassee, Florida 32399 - 3060
3680(850) 488 - 9675 SUNCOM 278 - 9675
3688Fax Filing (850) 921 - 6847
3694www.doah.state.fl.us
3695Filed with the Clerk of the
3701Division of Administrative Hearings
3705this 20th day of November 2003.
3711COPIES FURNISHED:
3713Dr. Franklin L. Till, Jr.
3718Superintendent
3719Broward County School Board
3723600 S outheast Third Avenue
3728Fort Lauderdale, Florida 33301 - 3125
3734Daniel J. Woodring, General Counsel
3739Department of Education
3742325 West Gaines Street
37461244 Turlington Building
3749Tallahassee, Florida 32399 - 0400
3754Usher Larry Brown, Esquire
3758Brown, Salzman, Weiss & Garganese, P.A.
3764225 East Robinson Street, Suite 660
3770Orlando, Florida 32801
3773Steven L. Schwarzberg, Esquire
3777Schwarzberg & Associates
3780Esperante, Suite 210
3783222 Lakeview Avenue
3786West Palm Beach, Florida 33401
3791Thomas R. Shahady, Esquire
3795Adorno & Yoss, P.A.
3799350 East Las Olas Boulevard, Suite 1700
3806Fort Lauderdale, Florida 33301
3810Robert Paul Vignola, Esquire
3814Broward County School Board
3818K. C. Wright Administrative Building
3823600 Southeast Third Avenue, 11th Floor
3829Fort Lauderdale, Florida 33301
3833NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
3839All parties have the right to submit written exceptions within
384910 days from the date of this Recommended Order. Any
3859exceptions to this Recommended Order should be filed with the
3869agency that will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 11/20/2003
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 11/20/2003
- Proceedings: Recommended Order (hearing held August 20-21, 2003). CASE CLOSED.
- PDF:
- Date: 10/17/2003
- Proceedings: Letter to J. Lambert from S. Schwarzberg enclosing disk of Petitioner`s proposed recommended order filed.
- PDF:
- Date: 10/16/2003
- Proceedings: Letter to Judge Parrish from U. Brown enclosing James B. Pirtle Construction Company, Inc.`s proposed recommended order on a disk filed.
- PDF:
- Date: 10/16/2003
- Proceedings: Petitioner Royal Concrete Concepts, Inc`s Proposed Recommended Order with Findings of Fact and Conclusions of Law (filed via facsimile).
- PDF:
- Date: 10/15/2003
- Proceedings: Petitioner Padula & Wadsworth Inc.`s Proposed Recommended Order (filed via facsimile).
- Date: 09/12/2003
- Proceedings: Transcript (Volume 1 and 2) filed.
- Date: 08/25/2003
- Proceedings: Joint Hearing Exhibits (1 box) filed.
- Date: 08/20/2003
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 08/12/2003
- Proceedings: Order Granting Petition to Intervene (by James B. Pirtle Construction Company, Inc.).
- PDF:
- Date: 08/12/2003
- Proceedings: Respondent School Board`s Response to Request to Produce from Petitioner Royal Concrete (filed via facsimile).
- PDF:
- Date: 08/12/2003
- Proceedings: Respondent School Board`s Answers and Objections to First Set of Interrogatories from Petitioner Royal Concrete (filed via facsimile).
- PDF:
- Date: 08/12/2003
- Proceedings: Petitioner, Royal Concrete Concepts, Inc.`s First Request for Production to Respondent, Broward County School Board (filed via facsimile).
- PDF:
- Date: 08/12/2003
- Proceedings: Petitioner, Royal Concrete Concepts, Inc.`s First Set of Interrogatories to Respondent, Broward County School Board (filed via facsimile).
- PDF:
- Date: 08/07/2003
- Proceedings: Notice of Filing Petitoiner, Padula & Wadsworth Construction, Inc.`s, Response to Respondent, School Board`s First Request to Produce (filed via facsimile).
- PDF:
- Date: 08/07/2003
- Proceedings: Notice of Filing Petitioner, Padula & Wadsworth Construction, Inc`s Sworn Answers and Objections to Respondents First Set of Interrogatories (filed via facsimile).
- PDF:
- Date: 08/04/2003
- Proceedings: James B. Pirtle Construction Company, Inc.`s Petition for Leave to Intervene (filed via facsimile).
- PDF:
- Date: 08/01/2003
- Proceedings: Respondent School Board`s Second Request to Produce to Petitioner Padula & Wadsworth (filed via facsimile).
- PDF:
- Date: 08/01/2003
- Proceedings: Notice of Taking Depositions (2), (of the unidentified "replacement" architect as referenced in Royal Concrete`s Answers to Interrogatories, S. Ford, W. Sanger, and unidentified expert witness for Padula & Wadsworth, W. Wadsworth) filed via facsimile.
- PDF:
- Date: 07/31/2003
- Proceedings: Notice of Filing Petitioner, Royal Concrete Concepts, Inc.`s Sworn Answers and Objections to Respondent`s First Set of Interrogatories (filed via facsimile).
- PDF:
- Date: 07/31/2003
- Proceedings: Respondent School Board`s Second Request to Produce to Petitioner Royal Concrete (filed via facsimile).
- PDF:
- Date: 07/31/2003
- Proceedings: Notice of Filing Petitioner, Royal Concrete Concepts, Inc.`s, Response to Respondent, School Board`s First Request to Produce (filed via facsimile).
- PDF:
- Date: 07/31/2003
- Proceedings: Notice of Filing Petitioner, Royal Concrete Concepts, Inc.`s Unsworn Answers to Respondent`s First Set of Interrogatories (filed via facsimile).
- PDF:
- Date: 07/25/2003
- Proceedings: Re-Notice of Taking Deposition Duces Tecum (2), (M. Geary, and The Person with Most Knowledge Regarding: the procurement of the bid by James B. Pirtle Construction, Inc., submitted on March 4, 2003) filed via facsimile.
- PDF:
- Date: 07/18/2003
- Proceedings: Notice of Taking Depositions (H. Padula, D. Locke, and Petitioners` Expert Witnesses) filed via facsimile.
- PDF:
- Date: 07/16/2003
- Proceedings: Subpoena Duces Tecum (2), (M. Geary and The Person with Knowledge Regarding: (a) The Procurement of the Bid by James B. Pirtle Construction, Inc.,) filed via facsimile.
- PDF:
- Date: 07/16/2003
- Proceedings: Notice of Taking Deposition Duces Tecum (2), (The Person with Knowledge Regarding: (a) The Procurement of the Bid by James B. Pirtle Construction, Inc., and M. Geary) filed via facsimile.
- PDF:
- Date: 07/11/2003
- Proceedings: Amended Notice of Hearing (hearing set for August 20 and 21, 2003; 9:00 a.m.; Fort Lauderdale, FL, amended as to Location of Hearing).
- PDF:
- Date: 07/09/2003
- Proceedings: Joint Motion to Change Location of Final Hearing (filed by R. Vignola via facsimile).
- PDF:
- Date: 07/09/2003
- Proceedings: Respondent School Board`s First Set of Interrogatories to Petitioner Padula & Wadsworth (filed via facsimile).
- PDF:
- Date: 07/09/2003
- Proceedings: Respondent School Board`s First Request to Produce to Petitioner Padula & Wadsworth (filed via facsimile).
- PDF:
- Date: 07/09/2003
- Proceedings: Respondent School Board`s First Request to Produce to Petitioner Royal Concrete (filed via facsimile).
- PDF:
- Date: 07/09/2003
- Proceedings: Respondent School Board`s First Set of Interrogatories to Petitioner Royal Concrete (filed via facsimile).
- PDF:
- Date: 07/07/2003
- Proceedings: Notice of Unavailability (filed by S. Schwarzberg via facsimile).
- PDF:
- Date: 07/01/2003
- Proceedings: Amended Joint Motion for Consolidation and Continuance (filed by Respondent via facsimile).
- PDF:
- Date: 07/01/2003
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for August 20 and 21, 2003; 9:00 a.m.; Fort Lauderdale, FL).
- PDF:
- Date: 07/01/2003
- Proceedings: Order Granting Motion for Consolidation issued. (consolidated cases are: 03-002220BID, 03-002221BID)
- PDF:
- Date: 06/30/2003
- Proceedings: Joint Motion for Consolidation and Continuance (of case no(s): 03-2221BID, 03-2220BID) filed via facsimile.
- PDF:
- Date: 06/26/2003
- Proceedings: Joint Request for Telephone Status Conference (filed by Respondent via facsimile).
- PDF:
- Date: 06/23/2003
- Proceedings: Notice of Hearing (hearing set for July 7 and 8, 2003; 9:00 a.m.; Fort Lauderdale, FL).
Case Information
- Judge:
- J. D. PARRISH
- Date Filed:
- 06/13/2003
- Date Assignment:
- 06/13/2003
- Last Docket Entry:
- 12/19/2003
- Location:
- Fort Lauderdale, Florida
- District:
- Southern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Usher L. Brown, Esquire
Address of Record -
Steven L Schwarzberg, Esquire
Address of Record -
Robert Paul Vignola, Esquire
Address of Record -
Steven L. Schwarzberg, Esquire
Address of Record