03-002374BID
Granite Construction Company Of California vs.
Department Of Transportation
Status: Closed
Recommended Order on Monday, August 25, 2003.
Recommended Order on Monday, August 25, 2003.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8GRANITE CONSTRUCTION COMPANY OF )
13CALIFORNIA, )
15)
16Petitioner, )
18)
19vs. ) Case No. 03 - 2374BID
26)
27DEPARTMENT OF TRANSPORTATION, )
31)
32Respondent, )
34)
35and )
37)
38GILBERT SOUTHERN CORPORATION, )
42)
43Intervenor. )
45)
46RECOMMENDED ORDER
48Pursuant to notice, a formal hearing was held in this case
59on July 28, 2003, in Tallahassee, Florida, before T. Kent
69Wetherell, II, the designated Administrative Law Judge o f the
79Division of Administrative Hearings.
83APPEARANCES
84For Petitioner: William E. Williams, Esquire
90J. Andrew Bertron, Jr., Esquire
95Huey, Guilday, Tucker, Schwartz,
99and Williams, P.A.
1021983 Centre Point Boulevard, Suite 200
108Post Office Bo x 12500
113Tallahassee, Florida 32317 - 2500
118For Respondent: Robert C. Downie, II, Esquire
125Department of Transportation
128Haydon Burns Building, Mail Station 58
134605 Suwannee Street
137Tallahassee, Florida 32399 - 0458
142For Intervenor: Christopher T. Mc Rae, Esquire
149McRae & Metcalf, P.A.
1531677 Mahan Center Boulevard
157Tallahassee, Florida 32312
160STATEMENT OF THE ISSUE
164The issue is whether the Department of Transportations
172proposed award of the contract for FIN Project Nos. 25840115201,
18225840115602, and 25841005603 to Intervenor is contrary to the
191Departments governing statutes, rules, policies, or the bid
199solicitation specifications.
201PRELIMINARY STATEMENT
203On May 22, 2003, the Department of Transportation
211(Department) posted notice of its intent to award the contract
221for a construction project known as Interstate 4 Reconstruction,
23014th Street to 50th Street, Hillsborough County, Florida, FIN
239Project Nos. 25840115201, 25840115602, and 25841005603 (the
246Project) to Intervenor. Thereafter, Petitioner ti mely filed a
255notice of protest and a formal written protest (Protest) with
265the Department challenging the proposed award. The Protest
273requested that the Department refer the matter to the Division
283of Administrative Hearings (Division) for the assignment o f an
293Administrative Law Judge to conduct a formal hearing. The
302Department referred the Protest to the Division on June 25,
3122003.
313Intervenor filed a motion to intervene with the Department,
322and that motion was referred to the Division along with the
333Prot est. The motion was granted by Order dated June 30, 2003.
345In accordance with the expedited time frame established by
354Section 120.57(3)(e), Florida Statutes, the final hearing was
362initially set for July 22 and 23, 2003. The hearing was
373subsequently resch eduled for July 28 and 29, 2003, at the
384request of the parties.
388On June 25, 2003, before the matter was referred to the
399Division, Intervenor filed a motion to dismiss the Protest on
409the theory that it is actually an untimely challenge to the bid
421specifica tions rather than a timely challenge to the proposed
431award of the contract. The Department joined Intervenor's
439motion through a filing dated June 30, 2003. The motion to
450dismiss was denied through a detailed Order dated July 11, 2003,
461and the case procee ded to final hearing on July 28, 2003.
473At the hearing, Petitioner presented the testimony of
481Jeffrey Wittmann, J.C. Miseroy, Robert Szatynski, Teresa
488Driskell, and Juanita Moore. Petitioner's Exhibits P1 - A, P1 - B,
500P1 - C, P3, P4, P7, and P8 were received in to evidence. Neither
514the Department nor Intervenor presented the testimony of any
523witnesses at the hearing. Exhibits R1, R2, and R5 through R11,
534which were jointly introduced by the Department and Intervenor,
543were received into evidence. The parties' Joint Exhibits J1
552through J27 were also received into evidence.
559The two - volume Transcript of the hearing was filed with the
571Division on August 4, 2003. The parties were given ten days
582from the date that the Transcript was filed to file their
593proposed rec ommended orders (PROs). The parties' PROs were
602timely filed and were given due consideration by the undersigned
612in preparing this Recommended Order.
617All statutory references are to the 2002 codification of
626the Florida Statutes, unless otherwise indicated.
632FINDINGS OF FACT
635Based upon the testimony and evidence received at the
644hearing and the stipulations set forth in the parties'
653Pre - Hearing Stipulation, the following findings are made:
662A. Parties
6641. The Department is the state agency responsible for
673construction and maintenance of the State highway system, which
682includes Interstate 4. The Department is the contracting agency
691for the Project at issue in this proceeding.
6992. Petitioner and Intervenor are corporations engaged in
707the business of roa d and bridge construction, and they both
718submitted bids for the Project.
7233. Intervenor was determined by the Department to be the
733lowest responsible bidder for the Project, and Petitioner was
742determined to be the next lowest responsible bidder.
7504. Peti tioner and Intervenor both have the requisite
759standing in this proceeding.
763B. Overview of the Project
7685. The Project involves the widening and "reconstruction"
776of approximately three miles of Interstate 4 in Hillsborough
785County between 14th Street and 5 0th Street.
7936. The Project is located in the Department's District
802Seven.
8037. The Department's initial cost estimate for the Project
812was $148.5 million, making this the most expensive project ever
822in District Seven.
8258. The Project is being funded pr imarily by federal funds
836from the U.S. Department of Transportation, Federal Highway
844Administration (FHWA).
8469. The high per - mile cost of the Project is a result of
860the complexity of the Project due to its location in an urban
872environment and the numerou s bridges included in the Project.
882C. Bid Documents
88510. The Department issued a Bid Solicitation Notice
893(Notice) for the Project on February 28, 2003.
90111. The Notice provided a general description of the
910Project and informed prospective bidders how the y could obtain
920the plans and specifications for the Project.
92712. The Notice also included a list of the pay items for
939the Project. That list included "approx[imate]" quantities for
947each item, and was "not for bidding purposes."
95513. The plans and specifi cations for the Project included
965a Summary of Pay Items, sheets 2 through 16D (Summary), which
976listed the pay items for the Project, as well as the estimated
988quantity for each item.
99214. More than 400 pay items were listed in the Summary,
1003including Item No. 2534 - 72 - 12, Barrier Wall Noise (the "noise
1016wall").
101815. The noise wall is an aesthetic feature. Its purpose
1028is to reduce the amount of roadway noise that can be heard on
1041adjacent property. The noise wall is free - standing and is not
1053structurally connected to the roadway or other aspects of the
1063Project.
106416. It is possible that the noise wall may be deleted from
1076the Project during construction. However, bidders were required
1084to bid on the noise wall since it is shown in the plans and is
1099listed as a pay item in the Summary and on the proposal form.
111217. The estimated quantity for the noise wall provided in
1122the Summary is 1,453 meters squared (m 2 ), which is the same as
1137the "approx[imate]" quantity that was shown in the Notice.
114618. That same figure -- 1,453 m 2 -- is provided for the noise
1161wall on the proposal form. The proposal form is commonly
1171referred to as the "bid blank."
117719. The bid blank was provided to the prospective bidders
1187in electronic format. It lists each pay item for the Project,
1198and for each ite m, it specifies the item number, item
1209description, and estimated quantity.
121320. The bidders were required to insert their bid or unit
1224price for each pay item directly into the electronic bid blank
1235form. The bidders could not change the estimated quantitie s
1245shown on the bid blank. If a bidder attempted to do so, its bid
1259would have been rejected as nonresponsive.
126521. Once the bid/unit prices are inserted into the
1274electronic bid blank form, the bid amount is automatically
1283calculated for each pay item by mul tiplying the estimated
1293quantity shown on the form by the bidder's bid/unit price. The
1304bidder's total bid is then automatically calculated by adding up
1314the bid amounts for each pay item.
132122. The bid documents 1 incorporated by reference the 2000
1331edition of the Department's Standard Specifications for Road and
1340Bridge Construction (Standard Specifications).
134423. Section 2 - 3 of the Standard Specifications, entitled
"1354Interpretation of Estimated Quantities," explains the purpose
1361and significance of the estimate d quantities set forth in the
1372bid documents. That provision states:
1377For those items constructed within
1382authorized plan limits or dimensions, use
1388the quantities shown in the plans and in the
1397proposal form as the basis of the bid. The
1406Department will als o use these quantities
1413for final payment as limited by the
1420provisions for the individual items. For
1426those items having variable final pay
1432quantities that are dependent upon actual
1438field conditions, use and measurement, the
1444quantities shown in the plans an d in the
1453proposal form are approximate and provide
1459only a basis for calculating the bid upon
1467which the Department will award the
1473Contract. . . .
1477The Department may increase, decrease, or
1483omit the estimated quantities of work to be
1491done or to be furnishe d.
149724. The estimated quantities shown in the bid documents
1506are not necessarily the actual quantities that will be built on
1517the Project. It is important, however, that the estimated
1526quantities be as accurate as possible so that the Department can
1537develop a reasonably accurate cost estimate for budgeting
1545purposes and so that contractors can have a good idea of the
1557resources that they will need to devote to construction when
1567they are formulating their bids.
157225. Section 3 - 1 of the Standard Specifications, en titled
"1583Consideration of Bids," informed bidders how the Department
1591would determine the lowest bid for the Project. That provision
1601states that:
1603[F]or purposes of award, after opening and
1610reading the proposals, the Department will
1616consider as the bid the c orrect summation of
1625each unit bid price multiplied by the
1632estimated quantities shown in the proposal
1638form.
163926. The "proposal form" referenced in Section 3 - 1 of the
1651Standard Specifications is the official form on which the
1660Department requires formal bids to be prepared and submitted.
1669It is the same as the "bid blank" described above.
1679D. Pre - bid Phase
168427. Petitioner ordered the plans and specifications for
1692the Project on March 3, 2003. The Department sent the plans and
1704specifications to Petitioner on Mar ch 4, 2003.
171228. Petitioner received the plans and specifications
1719approximately two weeks prior to the mandatory bidders'
1727meeting/"pre - bid conference" held on March 31, 2003.
173729. The pre - bid conference was attended by two of
1748Petitioner's employees. Neither of those employees asked
1755questions regarding the estimated quantity for the noise wall,
1764although they each asked questions regarding other elements of
1773the Project.
177530. The Transcript of the pre - bid conference reflects that
1786no other bidder asked about the estimated quantity for the noise
1797wall either, even though the noise wall was mentioned on several
1808occasions at the conference, and a question was asked about the
1819quantity shown for another item listed in the specifications.
182831. At some point after the pr e - bid conference,
1839Petitioner's senior estimator, Jeffrey Wittmann, calculated
"1845take - offs" for all of the walls in the Project, including the
1858noise wall. This is a standard practice done in the course of
1870putting together a bid.
187432. The purpose of a take - o ff is to verify the accuracy of
1889the estimated quantities in the bid documents and to calculate
1899the work and materials that will be required to perform the
1910contract. A take - off converts the graphical information shown
1920in the plans for an item to a numerica l amount for that item,
1934and is done by using the plans and specifications for the
1945Project and the Department's standard computation manual.
195233. The take - off calculated by Mr. Wittmann for the noise
1964wall was 3,809 m 2 , which is more than two - and - a - half time s the
1984estimated quantity of 1,453 m 2 shown in the bid documents.
199634. The Department's contact person for the Project was
2005Teresa Driskell.
200735. Ms. Driskell began receiving questions about the
2015accuracy of the estimated quantity for the noise wall in late
2026Ma rch or early April. The first question regarding that issue
2037came from Intervenor.
204036. Intervenor questioned the estimated quantity shown for
2048the noise wall in the Summary and the bid blank because its
2060take - off showed the estimated quantity to be significa ntly more
2072than 1,453 m 2 .
207837. Ms. Driskell referred Intervenor's question to Robert
2086Szatynski, the Department's outside consultant and engineer of
2094record for the Project, and asked him to formulate a response.
210538. Mr. Szatynski directed a member of his s taff to review
2117the computations and spreadsheets from which the estimated
2125quantity for the noise wall was originally computed. Based upon
2135the results of his staff's review, Mr. Szatynski responded to
2145Ms. Driskell that the 1,453 m 2 figure was correct.
215639. Ms. Driskell forwarded that response to Intervenor,
2164but not to other prospective bidders. Ms. Driskell followed a
2174similar pattern with respect to other inquiries; she provided
2183the response only to the prospective bidder who made the
2193inquiry.
219440. Ms. Dri skell continued to get questions from other
2204prospective bidders, including Petitioner through Mr. Wittmann,
2211regarding the accuracy of the estimated quantity for the noise
2221wall.
222241. On Friday, April 18, 2003, Ms. Driskell asked Richard
2232Frank, the Departmen t's in - house construction manager for the
2243Project, to take a look at the questions being raised by the
2255prospective bidders regarding the estimated quantity for the
2263noise wall.
226542. Mr. Frank calculated his own take - off for the noise
2277wall, which only took h im about an hour. Mr. Frank's take - off
2291calculated an estimated quantity for the noise wall of 3,853 m 2 ,
2304which is very similar to Mr. Wittmann's calculation.
231243. Based upon his take - off, Mr. Frank sent an e - mail to
2327Ms. Driskell which stated that he "agree[ d] with the concerns
2338that have been raised that the quantity [for the noise wall] is
2350in error" and that Ms. Driskell could "let the contractors know
2361that they are correct."
236544. Mr. Frank's e - mail was sent to Ms. Driskell at
2377approximately 4:30 p.m. on April 18, 2003. A copy of the e - mail
2391was sent to Mr. Szatynski at the same time.
240045. On the morning of Monday, April 21, 2003,
2409Mr. Szatynski sent an e - mail to Ms. Driskell concurring in
2421Mr. Frank's assessment. That e - mail stated that:
2430[W]e agree with [Mr. Fr ank] that the
2438original quantity shown in the plans is
2445inaccurate. The final quantity for [the
2451noise wall] should be 3893.9 m2. We will
2459send the updated quantity calculation sheet
2465for your use.
246846. Later that same day, Mr. Szatynski sent Ms. Driskell a
2479revised area computation sheet for the noise wall. The sheet
2489specified a new quantity for the wall of 3,894 m 2 .
250247. The spreadsheet used by Mr. Szatynski's staff to
2511calculate the original estimated quantity for the noise wall had
2521a mathematical error in i t. The heights and lengths for the
2533noise wall in the spreadsheet that were derived from a take - off
2546of the plans were correct, but the formula underlying the
2556spreadsheet failed to multiply those dimensions by the number of
2566panels needed for the noise wall. The error in the spreadsheet
2577was not known to or found by Mr. Szatynski or his staff when
2590they reviewed the noise wall quantity estimate in response to
2600Ms. Driskell's first request described above.
260648. In recalculating the area of the noise wall,
2615Mr. S zatynski did not change any of the wall's dimensions in the
2628plans or any of the figures in his original take - off. He simply
2642corrected the formula underlying in the spreadsheet to include
2651the number of panels needed in the calculation.
265949. Even though the Department knew that the estimated
2668quantity for the noise wall in the bid documents was
"2678inaccurate" and "in error," and even though it had been given
2689the corrected "final quantity" from Mr. Szatynski on April 21,
26992003, the Department did not issue an add endum to change the
2711estimated quantity.
271350. Addenda are issued by the Department's Tallahassee
2721office upon the request of the District office. The
"2730turn - around time" for an addenda varies based on nature and
2742extent of the change.
274651. No changes to the plans were necessary to correct the
2757erroneous estimated quantity for the noise wall, and
2765Mr. Szatynski had already provided a corrected area computation
2774sheet. The only other thing that would have been necessary to
2785correct the noise wall quantity was a re vised electronic bid
2796blank and revised Summary page.
280152. According to Juanita Moore, the Department's contract
2809administrator in Tallahassee for the Project, it would have only
2819taken "a few hours" to do an addendum to change the estimated
2831quantity for the n oise wall under such circumstances.
284053. The decision not to issue an addendum to correct the
2851estimated quantity for the noise wall was made by Ms. Driskell
2862alone. She based her decision on a number of factors, including
2873the fact that the noise wall was a stand - alone item that was not
2888structurally related to the remainder of the Project and that it
2899might be deleted from the Project; the fact that the noise wall
2911was not a "major item of work;" 2 her estimate that the projected
2924cost overrun would be less than $1,000,000, which is less than
2937one percent of the total contract price; and her concern that
2948the plans would need to be revised or that it would take too
2961long to get an addendum approved.
296754. In hindsight, Ms. Driskell clearly made the wrong
2976decision by not changing the estimated quantity for the noise
2986wall because her concerns about the time it would take for an
2998addendum and need for revisions to the plans were unfounded, she
3009underestimated cost overrun that the error would cause by
3018approximately $500,00 0, and it turned out that the ultimate
3029award of the contract hinges on that pay item. Nevertheless,
3039Ms. Driskell's decision not to seek an addendum to correct the
3050estimated quantity for the noise wall was not arbitrary or
3060illogical at the time that it was made.
306855. The Department issued five formal addenda to the
3077Project specifications. The addenda were issued on March 17,
30862003 (Addendum No. 1); April 7, 2003 (Addendum No. 2); April 17,
30982003 (Addendum No. 3); April 22, 2003 (Addendum No. 4); and
3109April 29 , 2003 (Addendum No. 5).
311556. The addenda were sent by overnight delivery to the
3125prospective bidders, and they contained instructions on how to
3134download the updated electronic bid blank form from the
3143Internet.
314457. Addenda Nos. 4 and 5 were issued after Ap ril 21, 2003,
3157which is the date that the Department received confirmation from
3167Mr. Szatynski that the noise wall quantity estimate in the bid
3178documents was "inaccurate" and that the correct "final quantity"
3187was 3,894 m 2 . However, Addendum No. 4 was in the review process
3202prior to that date.
320658. Addendum No. 4 changed the estimated quantities for
3215several pay items, including an eight - foot traffic railing
3225barrier wall (Item No. 2521 - 7 - 1), which Mr. Wittmann had
3238discussed with Ms. Driskell in connection with their discussions
3247regarding the noise wall. The change added approximately 1,100
3257meters to that pay item.
326259. Using the unit prices bid for that item by Petitioner
3273and Intervenor, the financial impact of the change in the
3283quantity for the barrier wall ite m was between $500,000 and
3295$790,000. That amount is less than the financial impact of the
"3307error" in the estimated quantity for the noise wall.
331660. On the afternoon of Friday, April 25, 2003,
3325Mr. Wittmann e - mailed Ms. Driskell and asked "[w]hy [there was ]
3338no change to the [noise wall] in addendum 4 as previously
3349discussed." Ms. Driskell did not respond to Mr. Wittmann's
3358e - mail, although as discussed below, she answered his question
3369in a telephone conversation on Monday, April 28, 2003.
337861. Addendum N o. 5 was issued the day before the bid
3390submittal deadline. It changed the estimated quantity for Item
3399No. 2102 - 911 - 2 to correct an obvious scrivener's error.
341162. At some point during the pre - bid phase, a bidder other
3424than Petitioner or Intervenor made a public records request for
3434all of the Department's responses to the questions asked by
3444prospective bidders. Ms. Driskell's supervisor directed her to
3452provide the information responsive to the public records request
3461to all of the prospective bidders.
346763 . That information was not provided to the prospective
3477bidders in the form of an addendum; it was just "made available
3489to them" at the District Seven office on April 29, 2003.
3500Included in that information were Mr. Frank's e - mail stating
3511that the estimated quantity for the noise wall was "in error"
3522and Mr. Szatynski's e - mail concurring in that assessment and
3533providing a "final quantity" of 3,894 m 2 .
354364. Ms. Driskell called each of the prospective bidders on
3553April 28, 2003, to inform them that the package o f information
3565could be picked up on April 29, 2003. During her conversation
3576with Mr. Wittmann, Ms. Driskell was again asked why the
3586estimated quantity for the noise wall had not been changed. She
3597told Mr. Wittmann that it was "too close to the letting" a nd
3610that "it would not be changed."
361665. Ms. Driskell's response to Mr. Wittmann is somewhat
3625disingenuous because she had the necessary information since
3633April 21, 2003, to make a change in the noise wall quantity
3645through an addendum, and it would have taken only "a few hours"
3657to do so. Indeed, on April 21, 2003, Ms. Driskell's supervisor,
3668Brian McKishnie, told Ms. Driskell that she "need[ed] to tell
3678them [the bidders] to 'bid it [the noise wall] as you see it' or
3692get the corrected quantity to all bidders."
369966. Although there is conflicting evidence regarding what
3707Ms. Driskell told Mr. Wittmann on and around April 21, 2003,
3718regarding the discrepancy in the estimated quantity for the
3727noise wall and the Department's intent to issue an addenda to
3738change the qua ntity, it is ultimately immaterial what
3747Mr. Wittmann was told at that time because on April 28, 2003,
3759Ms. Driskell clearly and unequivocally told Mr. Wittmann that no
3769change was going to be made to the noise wall.
377967. Thus, on April 28, 2003, Petitioner w as on notice that
3791the estimated quantity for the noise wall was going to remain
38021,453 m 2 , and Petitioner prepared its bid based upon that figure.
381568. Petitioner did not file a specification protest within
382472 hours after Ms. Driskell informed Mr. Wittmann that the
3834estimated quantity for the noise wall was not going to be
3845changed.
384669. Petitioner did not pick up the package of information
3856which included the e - mails from Mr. Frank and Mr. Szatynski
3868related to the corrected noise wall quantity until May 12, 2 003,
3880which is nearly two weeks after it had submitted its bid. Thus,
3892Petitioner could not have relied on the information in those
3902e - mails in preparing its bid.
390970. On April 30, 2003, Petitioner, Intervenor, and several
3918other bidders timely submitted the ir bids for the Project.
392871. Neither Petitioner, nor any other prospective bidder,
3936filed a solicitation protest within 72 hours after the Notice
3946was issued.
394872. Neither Petitioner, nor any other prospective bidder,
3956filed a solicitation protest within 72 hours after they received
3966the plans and specifications for the Project.
397373. Neither Petitioner, nor any other prospective bidder,
3981filed a specification protest based upon the matters included in
3991(or omitted from) any of the addenda within 72 hours after th eir
4004issuance.
4005E. Department's Review of the Bids
401174. The bids submitted by Petitioner and Intervenor were
4020both determined to be responsive.
402575. Intervenor's bid of $149,898,506.15 was the lowest
4035bid.
403676. Petitioner's bid of $149,959,420.22 was the next
4046lowest bid. It was approximately $61,000 (or 0.041 percent)
4056more than Intervenor's bid.
406077. The Department has a policy -- Section 3.3 of Policy No.
4072600 - 010 - 001 - d (effective February 14, 2001) -- which requires that
4087before an award can be made based upon th e apparent low bid, the
4101bid must be reviewed to ensure that it is not "materially
4112unbalanced." FHWA policy is in accord.
411878. The primary purpose of this review is to determine
4128whether there is a quantity error in the bid documents that the
4140apparent low b idder is exploiting to the State's detriment or to
4152the detriment of the competitive bidding process.
415979. There are two types of unbalanced bids, a
4168mathematically unbalanced bid and a materially unbalanced bid.
4176As described by the FHWA policy, which is in accord with the
4188Department's policy and the testimony of the Department
4196witnesses at the hearing,
4200[a] mathematically unbalanced bid is
4205structured on the basis of a nominal price
4213submitted for some work and inflated prices
4220for other work. There is no p rohibition
4228against a contractor submitting a
4233mathematically unbalanced bid.
4236A material unbalanced bid, however, exists
4242if there is a reasonable doubt that the
4250award to the bidder submitting the
4256mathematically unbalanced bid will result in
4262the lowest ult imate cost to the Government
4270or have a detrimental effect on the
4277competitive bid process. A materially
4282unbalanced bid is unacceptable.
428680. The Department's unbalanced bid review is a two - step
4297process. The first step is to determine whether the bid is
4308m athematically unbalanced. The second step is to determine
4317whether a mathematically unbalanced bid is materially
4324unbalanced.
432581. The Department utilizes a computer program in the
4334first step of the process to determine whether a bid is
4345mathematically unbala nced. The computer compares the unit cost
4354bid for each item to a pre - determined estimated price for that
4367item. The computer "flags" any items for which the bid price is
4379materially different from the estimated price. If any items are
4389flagged, the bid is considered to be mathematically unbalanced.
439882. Then, in the second step of the process, a Department
4409estimator compares the quantity for the flagged unit item(s) in
4419the bid documents with the "correct" quantity for the item(s)
4429based upon a take - off from the plans. Based upon that
4441comparison, the estimator determines whether the mathematical
4448unbalance will result in a material cost overrun, a change in
4459the low bidder, or otherwise be contrary to competition. If so,
4470the bid is deemed to be materially unb alanced; otherwise, the
4481bid is accepted.
448483. This process is more formally described in Department
4493Policy No. 600 - 010 - 001 - d as follows:
45043.3 Post - letting Procedures
4509* * *
4512(d) [A]s soon as the Bid verses Estimate
4520(SAS) Report has been generated, a list of
4528mathematically unbalanced bid items is sent
4534to the District Design Project Manager
4540(Central Office only). They review the
4546computation book and check the quantities of
4553items for possible overruns and/or
4558underruns. If the quantity is found to be
4566i n error, the Project Manager calculates the
4574correct quantity and faxes the list back to
4582the estimator. The estimator then
4587calculates the effects of the
4592overrun/underruns by multiplying each
4596contractor's unit bid by the overrun amount.
4603The overrun amount is added back to each
4611contractor's total bid. If there is an
4618underrun, the amount is subtracted from each
4625contractor's total bid. If this adjustment
4631causes the low bidder's total to become
4638larger than another contractor's total, a
4644switch in low bidders h ave [sic] occurred,
4652which is a materially unbalanced bid. The
4659project must not be awarded to the original
4667low bidder. The lowest adjusted bid will
4674then be considered the low bidder and award
4682will be made accordingly.
4686(e) As soon as the bids have been loaded
4695into the system by the Contracts
4701Administration Offices, the low bid verses
4707estimate (SAS) report can then be generated
4714(Central Office only). This is followed by
4721the Unbalanced Bid Item report. The
4727Unbalanced Bid Item program utilizes a bell
4734cur ve distribution that develops a
4740statistical average unit price (Average 2).
4746The program then establishes a range of
4753acceptable prices to which the contractor's
4759prices are compared. If this comparison is
4766above or below a defined window (range), it
4774is flag ged by the program. This flag
4782basically means to check the quantity on the
4790mathematical unbalanced bid items for
4795possible quantity overruns and/or underruns.
4800The flag could also indicate the pay item
4808was not needed when a contractor bids a
4816small unit pri ce on an item. . . .
4826(Emphasis in original.)
482984. The computer program flagged four items which were
4838mathematically unbalanced in Intervenor's bid. After review,
4845none of those items resulted in Intervenor's bid being declared
4855materially unbalanced.
485785. The computer program did not flag the noise wall item
4868as being mathematically unbalanced. That means that the $600
4877per m 2 bid by Intervenor for the noise wall was not materially
4890different from the estimated cost for that item.
489886. Because the noise wall item was not flagged, the
4908Department was not required (or allowed) under the policy quoted
4918above to proceed to the next step to determine whether there was
4930any material unbalance on that item.
493687. Had the noise wall item been flagged as being
4946mathematic ally unbalanced, the Department would have used the
"4955final quantity" from Mr. Szatynski's April 21, 2003, e - mail in
4967evaluating whether Intervenor's bid was materially unbalanced.
4974That evaluation would have resulted in Intervenor's bid no
4983longer being the lowest bid, and under Section 3.3(d) of
4993Department Policy No. 600 - 010 - 001 - d (and the FHWA policy), the
5008contract for the Project would not have been awarded to
5018Intervenor. Instead, the contract would have been awarded to
5027Petitioner if its bid "passed" the unbalanced review.
503588. If the Department used the 3,894 m 2 estimated quantity
5047for the noise wall instead of the 1,453 m 2 , Petitioner's bid
5060amount would be $151,301,970.22 and Intervenor's bid amount
5070would be $151,363,106.15. 3 As a result, Petitioner woul d become
5083the lowest bidder by approximately $61,000.
509089. Petitioner informed the Department of these figures on
5099May 20, 2003. Thus, at the time that the Department issued the
5111notice of intent to award the contract to Intervenor, it was not
5123only aware of the "correct" estimated quantity for the noise
5133wall, but it was also aware that Intervenor would not be the
5145lowest bidder if the "correct" quantity were used.
515390. The Project has a built - in cost overrun of
5164approximately $1.5 million ( i.e. , the differenc e between
5173Intervenor's bid based upon the 1,453 m 2 estimate and its
"5185corrected" bid based upon the 3,894 m 2 estimate) because under
5197Section 2 - 3 of the Standard Specifications, payment for the
5208noise wall will be based upon the size of the wall that is
5221actua lly built and because the 3,894 m 2 more accurately reflects
5234the size of the wall than does the original 1,453 m 2 estimate.
5248F. Proposed Award to Intervenor
5253and Petitioner's Protest
525691. On May 22, 2003, the Department posted notice of its
5267intent to award the contract for the Project to Intervenor.
527792. Petitioner's Protest was timely filed in relation to
5286that notice.
5288CONCLUSIONS OF LAW
5291A. Jurisdiction
529393. The Division has jurisdiction over the parties to and
5303subject matter of this proceeding pursuant t o Sections 120.569,
5313120.57(1), and 120.57(3).
5316B. Is This Actually a Specification Protest?
532394. The Department and Intervenor argue that the Protest
5332must be dismissed in its entirety because it is actually an
5343untimely protest to the specifications in t he bid documents.
535395. The statutory language relevant to this argument is in
5363Section 120.57(3)(b), which provides in pertinent part:
5370With respect to a protest of the terms,
5378conditions, and specifications contained in
5383a solicitation, including any provision s
5389governing the methods for ranking bids,
5395proposals, or replies, awarding contracts,
5400reserving rights of further negotiation, or
5406modifying or amending any contract, the
5412notice of protest shall be filed in writing
5420within 72 hours after the posting of the
5428so licitation. The formal written protest
5434shall be filed within 10 days after the date
5443the notice of protest is filed. Failure to
5451file a notice of protest or failure to file
5460a formal written protest shall constitute a
5467waiver of proceedings under this chapte r.
547496. It is undisputed that neither Petitioner, nor any
5483other prospective bidder, filed a specification protest at any
5492point during the pre - bid phase. Therefore, if Petitioner's
5502Protest is actually a specification protest, it is untimely and
5512must be dis missed. See Section 120.57(3)(b); Capeletti
5520Brothers, Inc. v. Department of Transportation , 499 So. 2d 855,
5530857 (Fla. 1st DCA 1986) ("A failure to file a timely protest [of
5544the plans and specifications for the project] constitutes a
5553waiver of chapter 120 proceedings.").
555997. The crux of the Department's and Intervenor's argument
5568on this issue is that the estimated quantity for the noise wall
5580of 1,453 m 2 in the bid documents never changed and, because
5593Petitioner did not challenge that quantity through a
5601spec ification protest, it is barred from doing so now. This
5612argument is correct as far as it goes.
562098. The evidence establishes that the estimated quantity
5628for the noise wall in the bid documents, although clearly
5638incorrect, was not changed prior to the Depar tment's receipt of
5649bids. Moreover, the evidence establishes that Petitioner was
5657expressly told by the Department prior to the bid submittal
5667deadline that the quantity was not going to be changed. Despite
5678such notice, Petitioner did not file a specificati on protest.
568899. Petitioner argues that it was not required to file a
5699specification protest because "the only purpose to be served by
5709a bid specification challenge, bringing a specification error to
5718the agency's attention and affording it an opportunity to
5727correct that error, was accomplished throughout the necessity of
5736a formal administrative challenge." Petitioner's PRO at 16.
5744Contrary to Petitioner's argument, the purpose of a bid
5753solicitation protest is not just to afford the agency an
5763opportunity to c orrect the error, it is to get the error
5775corrected. See Capeletti Brothers , 499 So. 2d at 857 ("[T]he
5786purpose of a bid solicitation protest provision is . . . to
5798correct or clarify plans and specifications prior to accepting
5807bids."). Petitioner was clear ly on notice after Ms. Driskell
5818spoke with Mr. Wittmann on April 28, 2003, that no change was
5830going to be made to the estimated quantity for the noise wall
5842despite the Department's prior acknowledgement that there was an
5851error. At that point (if not befor e), Petitioner could have
5862brought a bid solicitation protest to force the Department to
5872correct the error, but it failed to do so. 4
5882100. Petitioner's argument that the Department should
5889nevertheless change the noise wall quantity estimate post - bid
5899and awa rd the contract based upon the "correct" noise wall
5910quantity of 3,894 m 2 is jurisdictionally foreclosed. See
5920Capeletti Brothers , 499 So. 2d at 857; Vila & Son Landscaping
5931Corporation v. Department of Transportation , Case
5937No. 93 - 4556BID, 1993 WL 94 4007, at *5 (DOAH October 22, 1993);
5951State Paving Corporation v. Department of Transportation , Case
5959No. 87 - 3848, 1987 WL 488156, at *4 (DOAH October 1, 1987).
5972101. This determination does not warrant dismissal of the
5981Protest in its entirety because the Pr otest alternatively argues
5991that the proposed contract award to Intervenor is contrary to
6001the Department's governing statutes, policies, and the proposal
6009specifications. Even though those arguments also implicate the
6017erroneous noise wall quantity estimate, those arguments are not
6026jurisdictionally foreclosed and are addressed below.
6032C. Does Petitioner's Protest to the
6038Department's Proposed Award Have Merit?
6043102. The nature and scope of a protest to the proposed
6054contract award is prescribed by Section 12 0.57(3)(f), which
6063provides in pertinent part:
6067In a competitive - procurement protest, other
6074than a rejection of all bids, the
6081administrative law judge shall conduct a de
6088novo proceeding to determine whether the
6094agency's proposed action is contrary to the
6101age ncy's governing statutes, the agency's
6107rules or policies, or the bid or proposal
6115specifications. The standard of proof for
6121such proceedings shall be whether the
6127proposed agency action was clearly
6132erroneous, contrary to competition,
6136arbitrary, or capriciou s.
6140103. This statutory language was parsed and critically
6148analyzed by Administrative Law Judge John G. Van Laningham in
6158his Recommended Order in Syslogic Technology Services,
6165Inc. v. South Florida Water Management District , Case
6173No. 01 - 4385BID, 2002 WL 76312 (DOAH January 18, 2002). The
6185pertinent portions of that analysis, with which the undersigned
6194agrees, provide:
619645. As the statute says, the ultimate
6203issue is "whether the agency's proposed
6209action is contrary to the agency's governing
6216statutes, the agency's rules or policies, or
6223the bid or proposal specifications." This
6229could be construed as a standard of review,
6237which might be distilled into: whether the
6244agency erred in applying a governing
6250principle. Such a review would be akin to
6258an appella te court's evaluation of a lower
6266tribunal's legal conclusions. Ordinarily,
6270of course, legal conclusions are decided
6276independently (or de novo) by the reviewing
6283court, with little deference paid to the
6290trial judge. [citations omitted]
629446. The next sen tence, however, which
6301describes the "standard of proof," renders
6307the foregoing interpretation untenable, for
6312reasons that will become clear. But first:
6319it is an impediment to applying the statute
6327that of the several standards ushered in by
6335words "standar d of proof," none is a known
"6344standard of proof."
634747. As commonly used in legal discourse,
6354the term "standard of proof" signifies the
6361nature, quality, and quantity of evidence
6367with which the proponent of an allegation
6374(or the one who bears the burden o f proof)
6384must come forward in order to establish that
6392allegation. The widely - recognized standards
6398of proof are: preponderance (or greater
6404weight) of the evidence, clear and
6410convincing evidence, and proof beyond a
6416reasonable doubt. [citations omitted]. It
6421is highly unlikely that the legislature
6427intended to change the standard of proof in
6435bid protests, from "preponderance of the
6441evidence," see Section 120.57(1)(j), Florida
6446Statutes, to a new and unfamiliar standard.
645348. Instead, a reasonable interpret ation
6459of "standard of proof" as used in Section
6467120.57(3)(f) is that the term means standard
6474of review . This is because, while the
"6482standard of proof" sentence fails to
6488mention a single common standard of proof,
6495it does articulate two accepted standards o f
6503review: the "clearly erroneous" and abuse
6509of discretion (= "arbitrary, or capricious")
6516standards. (The "contrary to competition"
6521standard whether it be a standard of proof
6530or standard of review is unique to bid
6539protests.) Construing "standard of pro of"
6545to mean "standard of review" makes the
6552sentence make sense. 8
6556[Endnote 8. The legislature's use
6561of the term "standard of review"
6567in the very next sentence of the
6574statute, which deals with protests
6579contesting a rejection of bids,
6584has not been overlooke d. While
6590ordinarily it would be presumed
6595that the legislature, having
6599chosen to use different terms in
6605the same statute, must have
6610intended that each separate term
6615convey a distinct meaning, the
6620ordinary presumption simply does
6624not work here. The legisla ture
6630could not reasonably have intended
6635that a protester establish its
6640case by "clearly erroneous"
6644evidence, or by proof that is
"6650contrary to competition."]
665449. It also sheds light on the "de novo
6663proceeding" sentence. If the "standard of
6669proof" sente nce describes the standard of
6676review (as reasonably it must), then
6682logically the "de novo proceeding" sentence
6688must not prescribe the standard of review,
6695because the legislature presumably would not
6701have done so twice, differently. Moreover,
6707the "standard of proof" sentence plainly
6713manifests an intent that the agency's
6719proposed action be accorded a measure of
6726deference that is inconsistent with a de
6733novo review for error, which would seem to
6741be the standard of review if the "de novo
6750proceeding" sentence we re construed to
6756articulate one. By framing the ultimate
6762issue as being "whether the agency's
6768proposed action is contrary to the agency's
6775governing statutes, the agency's rules or
6781policies, or the bid or proposal
6787specifications," it is probable that the
6793le gislature, rather than describing a
6799standard of review, intended to establish a
6806standard of conduct for the agency. The
6813standard is: In soliciting and accepting
6819bids or proposals, the agency must obey its
6827governing statutes, rules, and the project
6833specif ications. If the agency breaches this
6840standard of conduct, its proposed action is
6847subject to (recommended) reversal by the
6853administrative law judge in a protest
6859proceeding.
686050. Applying the above interpretations,
6865it is concluded that the party protest ing
6873the intended award must identify and prove,
6880by the greater weight of evidence, a
6887specific instance or instances where the
6893agency's conduct in taking its proposed
6899action was either:
6902(a) contrary to the agency's governing
6908statutes;
6909(b) contrary to the agency's rules or
6916policies; or
6918(c) contrary to the bid or proposal
6925specifications.
6926It is not sufficient, however, for the
6933protester to prove merely that the agency
6940violated the general standard of conduct.
6946By virtue of the applicable standard s of
6954review, the protester must in addition
6960establish that the agency's misstep was:
6966(a) clearly erroneous;
6969(b) contrary to competition; or
6974(c) an abuse of discretion.
6979Id. , 2002 WL 76312 at **8 - 10 (Emphasis in original). See also
6992State Contract ing & Engineering Corporation v. Department of
7001Transportation , 709 So. 2d 607, 609 (Fla. 1st DCA 1998) (noting
7012that the object of a bid protest proceeding is to " evaluate the
7024action taken by the agency" in accordance with the standards set
7035forth in Secti on 120.57(3)(f)) .
7041104. Petitioner first argues that the Department's
7048proposed award of the contract to Intervenor is contrary to
7058Section 337.11(2). That statute requires the Department to
"7066ensure that all project descriptions, including design plans,
7074ar e complete, accurate, and up to date prior to the
7085advertisement for bids on such projects." (Emphasis supplied.)
7093105. Although Section 337.11(2) might have provided a
7101basis for a solicitation protest directed at the erroneous
7110estimated quantity for the noise wall once it became apparent
7120that the Department did not intend to correct that error through
7131an addendum, the statute does not impose a continuing obligation
7141on the Department to unilaterally correct errors in the bid
7151documents after the Project ha s been advertised. Accordingly,
7160Section 337.11(2) does not provide a basis upon which to
7170challenge the Department's intended award of a contract made
7179pursuant to the bid documents, even if an item in those
7190documents is shown to be inaccurate, as it was he re.
7201106. This construction of Section 337.11(2) is consistent
7209with Capeletti Brothers and its progeny which hold that
7218challenges to the specifications must be timely raised during
7227the pre - bid phase or they are waived. This construction of the
7240statute a lso preserves the integrity of the competitive bidding
7250process by prohibiting after - the - fact challenges to the
7261specifications in the bid documents.
7266107. Petitioner next argues that the Department's proposed
7274award of the contract to Intervenor is contrary to the
7284Department's policy of rejecting materially unbalanced bids.
7291Petitioner failed to meet its burden of proof on this issue
7302because the evidence establishes that the Department followed
7310its policy governing the review of bids for unbalancing in this
7321case. 5 In this regard, because Intervenor's bid was not
7331determined to be mathematically unbalanced with respect to the
7340noise wall item, the policy did not require (or even allow) the
7352Department to determine whether Intervenor's bid was materially
7360unbalanc ed on that item. Cf. Vila & Son , supra (discussing the
7372Department's unbalanced bid review process and post - bid changes
7382made in circumstance involving mathematically unbalanced bid
7389items). Indeed, had the Department deviated from the procedures
7398set forth in the unbalanced bid policy and declared Intervenor's
7408bid materially unbalanced by using the "correct" quantity for
7417the noise wall item, even though that item was not "flagged" by
7429the computer, its action would have been subject to challenge by
7440Intervenor as being contrary to the Department's written policy.
7449108. Finally, Petitioner argues that the Department's
7456intended award of the contract to Intervenor is contrary to the
7467bid specifications. Petitioner failed to meet its burden of
7476proof on this issue. The evidence establishes that the
7485estimated quantity for the noise wall was never changed from
74951,453 m 2 and that, consistent with Sections 2 - 3 and 3 - 1 of the
7513Standard Specifications, the Department's proposed award to
7520Intervenor was based upon that figur e. The evidence further
7530establishes that Petitioner's representative was expressly told
7537prior to the bid submittal deadline that the noise wall quantity
7548estimate was not going to be changed and Petitioner subsequently
7558submitted its bid based upon the nois e wall quantity estimate of
75701,453 m 2 . And cf. Capeletti Brothers v. Department of General
7583Services , 432 So. 2d 1359 (Fla. 1st DCA 1983)(affirming contract
7593award to lowest bidder even though bid specifications contained
7602a known and acknowledged error regar ding the ownership of the
7613access road to the construction site).
7619109. Because Petitioner failed to prove that the
7627Department's intended award of the contract to Intervenor is
7636contrary to statute, Department policy, or the bid
7644specifications, it is unnece ssary to determine whether any such
"7654misstep" was clearly erroneous, contrary to competition, or an
7663abuse of discretion. See Syslogic Technology Services , 2002 WL
767276312 at *10 (second paragraph in Paragraph 50).
7680RECOMMENDATION
7681Based upon the foregoing Findings of Fact and Conclusions
7690of Law, it is
7694RECOMMENDED that the Department of Transportation issue a
7702final order which denies the formal written protest filed by
7712Petitioner and awards the contract for the Project to
7721Intervenor.
7722DONE AND ENTERED this 25 th day of August, 2003, in
7733Tallahassee, Leon County, Florida.
7737S
7738T. KENT WETHERELL, II
7742Administrative Law Judge
7745Division of Administrative Hearings
7749The DeSoto Building
77521230 Apalachee Parkway
7755Tallahassee, Florida 32399 - 306 0
7761(850) 488 - 9675 SUNCOM 278 - 9675
7769Fax Filing (850) 921 - 6847
7775www.doah.state.fl.us
7776Filed with the Clerk of the
7782Division of Administrative Hearings
7786this 25th day of August, 2003.
7792ENDNOTES
77931/ Unless the context indicates otherwise, all references in
7802this Recommended Order to "bid documents" includes the Notice,
7811the plans and specifications for the Project, the proposal
7820form/bid blank, and the five addenda issued by the Department.
78302/ Section 1 - 3 of the Standard Specifications defines "major
7841item of work" as an item of work whose value is more than five
7855percent of the contract price. Here, the five percent threshold
7865is approximately $7.5 million.
78693/ These amounts are computed as follows:
7876Petitioner Intervenor
7878Original Bid $149,959,420.22 $1 49,898,506.15
7887Less: Noise Wall
7890@ 1,453 m 2 ( 799,150.00) ( 871,800.00)
7901Plus: Noise Wall
7904@ 3,894 m 2 2,141,700.00 2,336,400.00
"7915Corrected" Bid $151,301,970.22 $151,363,106.15
7923For Petitioner, the noise wall figures were computed by
7932mu ltiplying 1,453 m 2 and 3,894 m 2 by the $550 per m 2 bid by
7951Petitioner, and for Intervenor, the noise wall figures were
7960computed by multiplying 1,453 m 2 and 3,894 m 2 by the $600 per m 2
7978bid by Intervenor.
79814/ The undersigned is mindful that Section 120.57(3) (b)
7990requires a solicitation protest to be filed within 72 hours
8000after "posting of the solicitation" which, in this case,
8009occurred on February 28, 2003, when the Notice was issued.
8019However, under the circumstances of this case, the 72 - hour
8030period to file a specification protest (or at least a protest
8041directed to the error in the noise wall quantity) could not have
8053commenced on that date because the bidders did not yet have the
8065plans for the Project which provided the graphical information
8074from which the err or could be determined through a take - off
8087calculation. Moreover, under the circumstances of this case,
8095the Department would have been hard - pressed not to consider a
8107specification protest had one been filed by Petitioner within
811672 hours after Ms. Driskell finally informed Mr. Wittmann on
8126April 28, 2003, that despite their earlier conversations, the
8135Department did not intend to change the estimated quantity for
8145the noise wall. Ultimately, however, this is simply an academic
8155exercise since Petitioner did not file a specification protest
8164at any point in the process.
81705/ There is some merit to Petitioner's argument that the
8180Department's policy makes no sense under the circumstances of
8189this case since the primary purpose of an unbalanced bid review
8200is to determ ine whether there is a quantity error in the bid
8213documents that the bidder is exploiting to the State's detriment
8223or to the detriment of the competitive bidding process. Here,
8233the Department was aware at the time the bids were received of
8245the error in the estimated quantity for the noise wall, as well
8257as the cost overrun that the error would cause, and it was
8269informed prior to noticing its proposed award of the contract to
8280Intervenor that use of the "correct" estimated quantity would
8289result in a change in low bidders. Nevertheless, the scope of
8300review in this proceeding is limited to determining whether the
8310Department followed its policy, as written , in awarding the
8319contract, which it did.
8323COPIES FURNISHED :
8326Robert C. Downie, II, Esquire
8331Department of Tr ansportation
8335Haydon Burns Building, Mail Station 58
8341605 Suwannee Street
8344Tallahassee, Florida 32399 - 0458
8349Christopher T. McRae, Esquire
8353McRae & Metcalf, P.A.
83571677 Mahan Center Boulevard
8361Tallahassee, Florida 32312
8364William E. Williams, Esquire
8368J. Andrew Be rtron, Jr., Esquire
8374Huey, Guilday, Tucker, Schwartz
8378and Williams, P.A.
83811983 Centre Point Boulevard, Suite 200
8387Post Office 12500
8390Tallahassee, Florida 32317 - 2500
8395James C. Myers, Clerk of Agency Proceedings
8402Department of Transportation
8405Haydon Burns Buildi ng, Mail Station 58
8412605 Suwannee Street
8415Tallahassee, Florida 32399 - 0450
8420Pamela Leslie, General Counsel
8424Department of Transportation
8427Haydon Burns Building, Mail Station 58
8433605 Suwannee Street
8436Tallahassee, Florida 32399 - 0450
8441NOTICE OF RIGHT TO SUBM IT EXCEPTIONS
8448All parties have the right to submit written exceptions within
845810 days from the date of this Recommended Order. Any exceptions
8469to this Recommended Order should be filed with the agency that
8480will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 09/04/2003
- Proceedings: Department and Intervenor`s Exceptions to Recommended Order filed.
- PDF:
- Date: 08/25/2003
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 08/15/2003
- Proceedings: Joint Closing Argument and Request for Relief (filed by J. Holloway via facsimile).
- PDF:
- Date: 08/14/2003
- Proceedings: Respondent and Intervenor`s Proposed Recommended Order (filed via facsimile).
- Date: 08/04/2003
- Proceedings: Transcript (2 Volumes) filed.
- Date: 07/28/2003
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 07/23/2003
- Proceedings: Gilbert Southern`s Responses to Granite`s First Request to Produce filed.
- PDF:
- Date: 07/23/2003
- Proceedings: Gilbert Southern`s Responses to Granite`s First Set of Interrogatories filed.
- PDF:
- Date: 07/17/2003
- Proceedings: Amended Notice of Taking Deposition Duces Tecum of Agency Representative filed.
- PDF:
- Date: 07/17/2003
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (R. Frank and B. McKishnie) filed.
- PDF:
- Date: 07/17/2003
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for July 28 and 29, 2003; 9:00 a.m.; Tallahassee, FL).
- PDF:
- Date: 07/17/2003
- Proceedings: Letter to Judge Wetherell from C. McRae enclosing agreed dates to continue for the final hearing (filed via facsimile).
- PDF:
- Date: 07/15/2003
- Proceedings: Petitioner`s Certificate of Serving First Set of Interrogatories to Intervenor filed.
- PDF:
- Date: 07/15/2003
- Proceedings: Petitioner`s First Request for Production of Documents from Intervenor Gilbert Southern Corporation filed.
- PDF:
- Date: 07/15/2003
- Proceedings: Petitioner`s Response to Intervenor`s First Request for Admissions filed.
- PDF:
- Date: 07/15/2003
- Proceedings: Amended Notice of Hearing (hearing set for July 23 and 24, 2003; 9:00 a.m.; Tallahassee, FL, amended as to date).
- PDF:
- Date: 07/15/2003
- Proceedings: Notice of Taking Deposition Duces Tecum (G. Davis, B. McKishnie and R. Frank) filed.
- PDF:
- Date: 07/14/2003
- Proceedings: Letter to Judge Wetherell from W. Willams enclosing agreed dates available for hearing (filed via facsimile).
- PDF:
- Date: 07/14/2003
- Proceedings: Respondent, Department of Transportation`s, Response to Request for Production (filed via facsimile).
- PDF:
- Date: 07/14/2003
- Proceedings: Department Notice of Answering Granite`s First Set of Interrogatories (filed via facsimile).
- PDF:
- Date: 07/11/2003
- Proceedings: Notice of Service Petitioner`s Answers to Respondent`s Second Set of Interrogatories filed.
- PDF:
- Date: 07/11/2003
- Proceedings: Petitioner`s Response to Respondent`s First Request for Production of Documents filed.
- PDF:
- Date: 07/11/2003
- Proceedings: Petitioner`s Response to Respondent`s First Request for Admissions filed.
- PDF:
- Date: 07/11/2003
- Proceedings: Notice of Service of Petitioner`s Answers to Respondent`s First Set of Interrogatories filed.
- PDF:
- Date: 07/10/2003
- Proceedings: Joint Reply to Petitioner`s Opposition to Motion to Dismiss (filed by C. McRae via facsimile).
- PDF:
- Date: 07/09/2003
- Proceedings: Notice of Taking Deposition Duces Tecum of Agency Representative filed.
- PDF:
- Date: 07/09/2003
- Proceedings: Notice of Taking Deposition Duces Tecum (R. Szatynski and T. Driskel) filed.
- PDF:
- Date: 07/08/2003
- Proceedings: Petitioner`s Response in Opposition to Respondent and Intervenor`s Motion to Dismiss or, in the Alternative Request for Informal Hearing filed.
- PDF:
- Date: 07/03/2003
- Proceedings: Notice of Serving Department`s Second Set of Interrogatories (filed via facsimile).
- PDF:
- Date: 07/02/2003
- Proceedings: Respondent`s First Request for Admissions to Petitioner (filed via facsimile).
- PDF:
- Date: 07/02/2003
- Proceedings: Department`s First Request for Production of Documents (filed via facsimile).
- PDF:
- Date: 07/02/2003
- Proceedings: Notice of Serving Department`s First Set of Interrogatories (filed via facsimile).
- PDF:
- Date: 07/01/2003
- Proceedings: Petitioner`s First Request for Production of Documents from Respondent filed.
- PDF:
- Date: 07/01/2003
- Proceedings: Petitioner`s Certificate of Serving First Set of Interrogatories to Respondent filed.
- PDF:
- Date: 06/30/2003
- Proceedings: Order Granting Petition to Intervene. (Intervenor, Gilbert Southern Corporation)
- PDF:
- Date: 06/30/2003
- Proceedings: Notice of Hearing (hearing set for July 22 and 23, 2003; 9:00 a.m.; Tallahassee, FL).
- PDF:
- Date: 06/30/2003
- Proceedings: Motion to Dismiss, or in the Alternative, Motion to Relinquish Jurisdiction (filed by Respondent via facsimile).
- PDF:
- Date: 06/25/2003
- Proceedings: Motion to Dismiss or, in the Alternative, Request for Informal Hearing filed.
- PDF:
- Date: 06/25/2003
- Proceedings: Petition to Intervene (Intervenor, Gilbert Southern Corp.) filed.
- PDF:
- Date: 06/25/2003
- Proceedings: Notice of Appearance/Notice of Intent to Protest Procurement filed.
Case Information
- Judge:
- T. KENT WETHERELL, II
- Date Filed:
- 06/25/2003
- Date Assignment:
- 06/26/2003
- Last Docket Entry:
- 09/24/2003
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
Robert C Downie, II, Esquire
Address of Record -
Christopher T. McRae, Esquire
Address of Record -
William E. Williams, Esquire
Address of Record