03-004001BID
D. J. Haycook Construction Company vs.
Volusia County School Board
Status: Closed
Recommended Order on Monday, March 8, 2004.
Recommended Order on Monday, March 8, 2004.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8D. J. HAYCOOK CONSTRUCTION )
13COMPANY, )
15)
16Petitioner, )
18)
19vs. ) Case No. 03 - 4001BID
26)
27VOLUSIA COUNTY SCHOOL BOARD, )
32)
33Respondent. )
35)
36)
37RECOMMENDED O RDER
40This cause came on for hearing pursuant to notice on
50December 11 and 12, 2003, in Deland, Florida, before P. Michael
61Ruff, duly - designated Administrated Law Judge. The appearances
70were as follows:
73APPEARANCES
74For Petitioner: S. LaRue Willia ms, Esquire
81Kinsey, Vincent, Pyle, L.C.
85150 South Palmetto Avenue, Box A
91Daytona Beach, Florida 32114
95For Respondent: Theodore R. Doran, Esquire
101Michael G. Dyer, Esquire
105Doran, Wolfe, Rost & Ansay
110444 Seabreeze Boulevard, S uite 800
116Post Office Drawer 15110
120Daytona Beach, Florida 32115
124STATEMENT OF THE ISSUES
128The issues to be resolved in this proceeding concern
137whether the Petitioner, D. J. Haycook Construction Company
145(Haycook) was the lowest responsive bidde r for an elementary
155school procurement project known as Elementary School "X," let
164by the Volusia County School Board and whether the Petitioner
174should have been awarded the contract.
180PRELIMINARY STATEMENT
182This cause arose upon the issuance of "an adverti sement for
193bid" by the Volusia County School Board (Board) seeking sealed
203bids from contractors for the construction of a new elementary
213school for Volusia County, Elementary School "X." The bids were
223to be submitted on or before 2:00 p.m., August 6, 2003 , at which
236time all bids would be publicly opened and read aloud. The
247advertisement for bid was issued on July 16, 2003, and the Board
259received eleven proposals in response to it. It opened and read
270all bids for Elementary School "X" on August 6, 2003, a nd
282determined that Haycook was the lowest bidder. Haycook's base
291bid was in the amount of $7,599,000.00. The firm of Clancy and
305Theys Construction Company, Inc. (Clancy and Theys) was the
314third lowest bidder with a base bid of $7,840,000.00. The
326second lowest bidder, Mark Construction Company, failed to
334extend its bid bond after the bid opening and during the
345pendency of this protest and therefore effectively withdrew its
354bid and is no longer in contention.
361The selected bidder would serve as a general c ontractor
371responsible for the construction of the school with an
380established project budget of $8,000,000.00. The bids were
390opened and read on August 6, 2003, and after the bids were
402opened the Board, through its project architect Philip Daimwood,
411of Daim wood, Derryberry, Pavelchak Architects, P.A. (architect
419or Daimwood), began an investigation of the low bidder, in
429accordance with the Board's interpretation of the advertisement
437and solicitation specifications wherein the Board reserved the
445right to use s ufficient time to investigate the bids and
456qualifications of the bidders. In this investigatory process
464the Board, through its architect, solicited information from the
473low bidder, Haycook, in order to ascertain that Haycook had the
484capability, based in p art upon information from its earlier jobs
495or projects, to self - perform work in four areas: earthwork,
506structural steel, masonry, and concrete. A number of letter
515exchanges and at least one meeting between representatives of
524Haycook and the Board occurred in this regard.
532Ultimately the Board took the position that Haycook's bid
541was not responsive because of failure to comply with all
551requirements of the solicitation advertisement and addenda. The
559Board thus awarded the contract to the third lowest bidd er,
570Clancy and Theys, on October 14, 2003. Haycook timely protested
580the proposed award and the cause was forwarded to the Division
591of Administrative Hearings and ultimately to the undersigned
599administrative law judge. Upon waiver of the relevant time
608per iod for setting of the hearing, the parties agreed to set the
621hearing on December 11 and 12, 2003, and the hearing proceeded
632as scheduled on those dates.
637In its formal written protest Haycook questioned the school
646Board's authority to verify Haycook's e xperience and capability
655to, in effect, serve as its own subcontractor ("self -
666performing") in the work areas of structural steel, concrete,
676masonry, and earthwork. Haycook protested on grounds that the
685school board failed to follow its own rules and the b id
697documents in determining the lowest responsive bidder, and that
706Section 120.57(3)(f), Florida Statutes, prohibits consideration
712of submissions after the bid opening which amend or supplement a
723bid or proposal. Haycook also maintains that the rejection of
733its bid was grossly arbitrary and unfair by applying evaluation
743criteria not set forth in the school board's rules or bid
754documents, and that the Board improperly delved into Haycook's
763means, methods, and procedures of self - performing its work,
773misappli ed the definition of "self - performed," and that the
784Board's inability to verify to its satisfaction prior self -
794performed work by Haycook on other past projects is not a legal
806criteria for rejection. Haycook maintains that the bid
814documents do not define " self - performance," nor do they require
825pre - qualified bidders to prove to the school board architect's
836satisfaction that the bidder has self - performed work on similar
847school projects in the past, by proving the use of only salaried
859employees on Haycook's ow n payroll. Haycook takes issue with
869the school board's definition of "self - performance" and contends
879that its means, methods, and procedures for self - performing the
890work were not prohibited by the bid documents or any rules or
902regulations of the Board tha t relate to bidding of school board
914projects.
915The school board maintains that it could not verify that
925Haycook had "self - performed" earthwork, structure steel,
933concrete, and masonry on prior school projects and that, based
943upon the Board's interpretatio n of self - performance, that
953Haycook's self - performance on its earlier projects really
962amounted to the use of "subcontractor" relationships and not
971self - performance. Because it did not list subcontractors in
981these four areas on the relevant bid document, a nd did not
993establish to the Board's architect's satisfaction that it would
1002self - perform these areas of work with its own labor,
1013supervision, and material resources, that Haycook had been non -
1023responsive as to these four areas of work on its bid.
1034Haycook ca lled four witnesses to testify at the hearing:
1044Jack Dunlap, Reed Hadley, Harold Goodemote, and Dennis Haycook.
1053Mr. Goodemote was presented as an expert witness. The parties
1063agreed that Petitioner's Exhibits 1 through 9 and the
1072Respondent's Exhibits 1 th rough 28, some of which Haycook also
1083used for its own exhibits, would be jointly offered and received
1094into evidence. The Board called witnesses Patricia Drago,
1102Philip Daimwood, Carl Gerken, Scott Stegall, Allen Green, Gary
1111Parker, Steve Eckman, and Gary E hrlich as its witnesses.
1121Witnesses Stegall, Parker, Eckman, Green, Daimwood, and Gerken
1129were presented as expert witnesses on behalf of the school
1139Board.
1140Prior to the hearing the parties filed a Joint Pre - Hearing
1152Stipulation setting forth contested and u ncontested issues of
1161fact and law. The school board also filed a Memorandum of Law
1173prior to hearing. Upon conclusion of the hearing the parties
1183ordered a transcript thereof which was submitted along with the
1193parties' timely submitted Proposed Recommended Orders. The
1200Transcript, the Proposed Recommended Orders, and the notes of
1209the undersigned have been carefully read and considered in the
1219rendition of this Recommended Order.
1224FINDINGS OF FACT
12271. On June 13, 2003, the School Board of Volusia County
1238autho rized the issuance of a request for proposal for the
1249construction of a new elementary school known as Elementary
1258School "X." The proposed new school would be located in Orange
1269City, Florida.
12712. The school board issued an advertisement for the
1280constructi on of Elementary School "X" and had it published. The
1291project architect for the Board prepared the solicitation
1299documents constituting a "Phase III specifications" manual and
1307three addenda.
13093. The advertisement stated that "the school board
1317expressly re serves the right to reject any and all bids and to
1330waive informalities therein, and to use sufficient time to
1339investigate the bids and the qualifications of the bidders."
13484. Section 00430 of the solicitation required that all
1357bidders list the name of the subcontractor for each type of the
136912 areas of construction work for Elementary School "X" as
1379follows:
1380'For each type of work' below, list the name
1389of the subcontractor. List only one name on
1397each line and only one subcontractor for
1404each type of work. V arious 'type of work'
1413sub - contracts may have more than one
1421subcontractor (re: roofing; metal roofing
1426and membrane roofing), list each
1431subcontractor accordingly. Use additional
1435sheets, if required.
1438Additionally, Section 00430 provided:
1442The term subcontrac tor as used herein shall
1450be defined in 2001, Florida Statute
1456713.01(27) - subcontractor means a person
1462other than a materialman or laborer who
1469enters into a contract with a contractor for
1477the performance of any part of such
1484contractor's contract.
1486The dead line for submission of proposals in response to the
1497solicitation was August 6, 2003. On August 6, 2003, Haycook's
1507bid proposal and that of the second and third lowest bidders
1518were opened and read by the members of the school board's staff.
1530Haycook listed itself as performing or "self - performing" in
1540areas of earthwork, masonry, concrete, and structural steel on
1549the required list of subcontractors form pursuant to section
155800430 of the solicitation.
15625. Subsequently, the project architect began to
1569investi gate the bids for the project. This was done through
1580correspondence and direct contact between Haycook, the project
1588architect, Mr. Daimwood, and the school board staff. This
1597process began on August 8, 2003. As part of the evaluation
1608process the architec t verbally requested documentation from
1616Haycook to verify its past and present abilities to self - perform
1628in the four areas of earthwork, concrete, masonry, and
1637structural steel, as well as by letters dated August 12, August
164815, and August 25, 2003. Haycoo k responded to these information
1659requests by letters of August 11, 13, and 28, 2003.
16696. The bid documents for the school project included the
1679bidding and contractual conditions, general conditions,
1685technical specifications, and the drawings listed on pag es 10D - 1
1697to 10D - 2. In order to have a responsive bid a bidder was
1711required to comply with the bid documents when submitting its
1721bid. The relevant bid documents at issue in this dispute are
1732Section 0020, "invitation to bid," Section 00100, "instruction
1740to bidders," Section 00300, "bid form," and Section 00430, "list
1750of subcontractors."
17527. The bid documents also required each bidder to deliver
1762a bid bond in the amount of five percent of its bid to accompany
1776the proposal. After acceptance of the lowest re sponsive bid,
1786and issuance of the contract award, a bidder was required to
1797deliver a payment and performance bond in the amount of 100
1808percent of the contract price. There is no dispute that Haycook
1819has a bonding capacity of 18 million dollars for a singl e
1831project and 35 million dollars for aggregate projects and the
1841bonding capacity is not in dispute.
18478. The invitation to bid documents require that bidders be
1857required to hold a current Certificate of Pre - Qualification
1867issued by the school board at the t ime of bid opening. Haycook
1880at all material times hereto held a Certificate of Pre -
1891Qualification and was licensed to perform all work called for by
1902the bid documents including, among others, self - performance of
1912earthwork, concrete work, masonry, and struc tural steel.
19209. The three bids received were in the amounts as follows:
1931(1) D. J. Haycook Construction Company: a base bid of
1941$7,599,000.00; Alternate One, $189,000.00; Alternate Two,
1950$48,800.00; Alternate Three, $21,000.00; (2) Mark Construction
1959Comp any of Longwood, Florida: base bid of $7,657,000.00,
1970Alternate One, $221,000.00; Alternate Two, $50,000.00; Alternate
1979Three, $20,000.00; (3) Clancy and Theys Construction Company of
1989Orlando, Florida: base bid of $7,840,000.00; Alternate One,
1999$230,000.00; A lternate Two, $50,000.00; Alternate Three,
2008$21,000.00.
201010. Section 00430 required each bidder to furnish a list
2020of subcontractors defined as quoted above in the bid form.
2030Section 00430 of the bid form also permitted a bidder to list
2042itself as a subcontr actor. The form provides: "A contractor may
2053not list himself as performing a type of work unless he is self -
2067performing and is a Florida licensed contractor for that type of
2078work". Haycook was properly licensed at the time of bidding,
2089and at all relevant times, to self - perform in the four areas of
2103earthwork, structural steel, masonry, and concrete at issue in
2112this case.
211411. After the bids were opened and examined, Mr. Daimwood,
2124the architect evaluating bids for the school board, requested
2133that Haycook fu rnish a list of past projects where it had self -
2147performed earthwork, structural steel, masonry, and concrete
2154work. Haycook provided a list of examples of prior projects for
2165which it had self - performed work in those areas on August 11,
21782003. The list incl uded five projects for earthwork, four
2188projects for structural steel, seven projects for masonry, and
2197seven projects for concrete. Thereafter, on August 12, 2003,
2206the architect requested additional information regarding self -
2214performance of work in the fou r areas at issue.
222412. Haycook provided the architect with the requested
2232additional information on August 13, 2003, including a list of
2242each project, the total cost of each project, the completion
2252dates, as well as contact persons with their telephone num bers
2263and including copies of qualifications of the subcontractors
2271listed on Haycook's subcontractor list.
227613. On August 25, 2003, the architect requested Haycook
2285payroll records and workers compensation information for two of
2294the listed projects of tho se Haycook had provided, that for
2305Goldsboro Elementary School and Eustis Elementary School.
231214. On August 28, 2003, Haycook sent a letter to the
2323architect explaining that on the Goldsboro job the earthwork was
2333self - performed by a combination of supervisi ng and directing the
2345work with salaried employees, with leasing of labor from an
2355employment service, and hiring of labor by the cubic yard with a
2367cap on the activity. Haycook also explained that structural
2376steel work on the projects was self - performed by a combination
2388of supervising and directing the work with salaried employees,
2397leasing of labor from an employment service, hiring of labor
2407paid by the foot to erect specific components of the job, as
2419well as using salaried employees for the performance of s pecific
2430activities, and including purchasing of fabricated materials and
2438then hiring crew labor and equipment on an hourly basis to erect
2450them.
245115. In the August 28, 2003, letter Haycook also explained,
2461with respect to the self - performed masonry work o n both the
2474Eustis and Goldsboro jobs, that those areas of work were self -
2486performed by purchasing fabricated material, supervising and
2493directing the work with salaried employees, hiring labor by the
2503unit price (for instance by the block) to lay the block, a nd
2516hiring labor from an employee leasing service for specific
2525activities as to those jobs.
253016. Haycook also explained in the August 28, 2003, letter
2540that a combination of the methods and means of performing
2550delineated above and in that letter would be us ed for the
2562activities listed on the subcontractor list on the relevant bid
2572form for Elementary School "X". Haycook explained that it had
2583priced and used its own costs for the activities listed on the
2595bid form to arrive at the bid price for Elementary Scho ol "X".
260917. Enclosed with the August 28, 2003, letter from Haycook
2619were copies of its purchase orders and cost journals for the
2630Goldsboro School, concerning earthwork, masonry, and structural
2637steel activities and its vendor purchase orders and cost
2646journ als for the Eustis Elementary School's masonry work done by
2657Haycook. The enclosures with the August 28, 2003, letter showed
2667that Haycook had purchased the materials, performed the work
2676with its own employees, and performed work using additional
2685outside la bor in the areas of structural metals, prefabricated
2695structures, earthwork, cast - in - place concrete, structural steel
2705erection, and masonry work. Haycook also provided its proposals
2714used on the Goldsboro project which consisted of concrete labor
2724and struct ural steel labor.
272918. The architect interpreted the term "self - performance"
2738to mean labor with the contractor's own employees only. Based
2748upon that restrictive interpretation, he concluded that he had
2757not found adequate information demonstrating Hayco ok's having
"2765self - performed" these types of work previously. Additionally,
2774the architect opined that Haycook's intended self - performance on
2784Elementary School "X" project at issue, in the four work areas
2795in dispute, "is in our opinion, a subcontractor form at."
280519. Uncontroverted evidence adduced at hearing established
2812that Haycook has extensive public school construction
2819experience. The Petitioner's President, Dennis Haycook, has
2826built more than 35 public schools and Haycook's project manager,
2836Reed Hadl ey, who is assigned to the Elementary School "X"
2847project, has built over 25 school projects. Dennis Haycook was
2857also a principal of Mark Arnold Construction Company in the
2867past, which was one of the largest public school contractors in
2878Florida. In the pa st 10 years, with his own company, the
2890Petitioner, Haycook, has built numerous school projects
2897including the Goldsboro school which was a $7,000,000.00
2907project. The Goldsboro, Eustis, and other Haycook - built schools
2917referenced during the hearing and in th e evidence were all
2928projects that were built within the authorized budget, were
2937timely, and were of quality construction.
294320. The Board ultimately rejected Haycook's bid on
2951Elementary School "X" because of the architect's interpretation
2959concerning "self - performance," i.e. that all work must be
2969performed by employees on Haycook's payroll. The bid documents
2978did not define "self - performance," nor do the bid documents
2989require that labor used must be on the contractor's payroll in
3000order for his performance to constitute "self - performance."
300921. Haycook's witnesses were consistent in their testimony
3017as to the definition of "self - performance": "self - performance,"
3029as customarily used in the construction industry, includes the
3038contractor's purchasing of materials , performing part of the
3046work with its own labor force, providing other labor not on the
3058contractor's payroll, and directly supervising the work with the
3067contractor's supervisory personnel. The term "subcontractor" is
3074defined in the custom and usage of th e construction industry,
3085however, to mean someone or an entity that provides all labor,
3096material, and equipment necessary to do the complete operation,
3105as well as all supervision. It is more of a "total turn key
3118operation." A subcontractor provides every thing necessary to
3126finish the work, including supervision, and then merely answers
3135to the general contractor in terms of responsibility for the
3145quality of the job and its timeliness.
315222. The school board's witnesses, expert and otherwise,
3160gave interpre tations of the concept of self - performance which
3171were somewhat conflicting. Mr. Daimwood, the architect, opined
3179that self - performance requires the contractors to use employees
3189on its own payroll and make direct payment of workers'
3199compensation for such em ployees. His opinion was that anything
3209else would be a subcontractor relationship and not self -
3219performance. He later testified, however, that paying labor not
3228actually on Haycook's payroll could still constitute self -
3237performance. Patricia Drago, of the school board staff,
3245testified that if a contractor uses 10 employees on his payroll
3256and uses 10 non - employees, this would be self - performance. If
3269such a contractor has 10 employees and uses 11 non - employees,
3281she was not sure whether this would constitute self - performance.
3292Allen Green testified that self - performance of an area of work
3304requires the majority of that work to be performed by the
3315contractor's own employees, while other work could be performed
3324by contract labor. He later changed his definition to require a
3335contractor to have all employees on the payroll in order to
3346self - perform. In other testimony, however, Mr. Green opined
3356that if a contractor supplemented his labor with a couple of
3367additional masons and paid them by the piece, then he would n o
3380longer be self - performing. At still another point in his
3391testimony he added that it would be dependent upon the stage of
3403the project as to whether the contractor's use of contract labor
3414is self - performing or subcontracting. He felt that if the
3425contract or adds some additional masons near the end of a job, as
3438opposed to the beginning, then he could still be self -
3449performing.
345023. Gary Parker is the Director of Facilities for the Lake
3461County School Board. He testified that from his perspective,
3470self - perf ormance required the use of employees on the
3481contractor's payroll. This definition, however, was not
3488consistent with Lake County's course of conduct with the job
3498that Haycook performed. Mr. Parker acknowledged that there had
3507been no complaints by the arc hitect or anyone else associated
3518with the Eustis school project where Haycook listed itself as
3528self - performing for masonry work, even though Haycook had
3538retained a different entity to perform masonry labor (although
3547not supply materials or supervision).
355224. Scott Stegall, the Director of Capital Outlay for the
3562Seminole County School Board, testified that self - performance
3571would require a contractor to perform all work without the use
3582of outside contractors, including labor. Yet Mr. Stegall
3590acknowledged t hat Haycook listed itself as self - performing
3600masonry work on the Goldsboro school project and used a firm or
3612entity known as Webber and Tucker to perform some masonry work,
3623and that the Seminole County School Board had no dispute with
3634this approach. Mr. S tegall's evaluation form for Haycook had
3644stated that Haycook did not improperly substitute any
3652subcontractors from the submitted list in that project. He
3661later changed his definition of self - performance to acknowledge
3671that a contractor could bring in labo rers individually to
3681perform without a "formal contract"; these informal labor
3689contracts would not take it out of the self - performance category
3701according to Mr. Stegall.
370525. The evidence concerning the Lake County District's and
3714Seminole County District 's experience as to the Eustis school
3724project and the Goldsboro school project with Haycook's
3732performance, including Haycook's approach to self - performance,
3740was satisfactory in terms of pricing and the quality and
3750timeliness of the work performed. The per ceived fear by the
3761Respondent that Haycook's performance might be substandard or
3769that it might "bid shop" amongst potential subcontractors, after
3778the bid opening, if Haycook did not list all subcontractors on
3789the bid response, and self - performed in the man ner Haycook
3801described in its evidence, has not been shown to have occurred
3812with regard to any of Haycook's past projects. There has been
3823no demonstration by preponderant evidence that the use of only
3833subcontractors listed or named in the bid response has resulted,
3843in itself, in a lower price or better performance for the public
3855by a contractor situated as Haycook.
386126. The architect testified that one method of defining
"3870self - performance" is to determine whether the entity performing
3880work was a subcont ractor as defined by the bid documents. If
3892the work is not being performed by a subcontractor, then it is
3904being performed by the general contractor or self - performance.
3914As the term is used in the construction industry, a
3924subcontractor generally furnishes materials, installs the work,
3931and supervises its own work.
393627. The bid documents define subcontractor as follows:
"3944subcontractor means a person other than a materialman or
3953laborer who enters into a contract with a contractor for the
3964performance of any p art of such contractor's contract."
397328. Preponderant, credible, and substantial evidence was
3980presented by Haycook to show that Haycook's use of the term
"3991subcontractor" was an entity that furnishes the materials,
3999provides the labor, and the supervision, and undertakes the
4008entire responsibility for that type or phase of the work. When
4019a general contractor hires contract labor only, this excludes
4028what is occurring from the definition of subcontractor, since
4037the definition of subcontractor prevailing in thi s proceeding
4046based upon the bid documents, takes out of that subcontractor
4056definition "a materialman or laborer." The preponderant
4063credible evidence shows that when Haycook purchases materials
4071and provides the labor, whether or not the labor is on Haycook 's
4084payroll, which Haycook then directly supervises , this, by
4092definition, is not a subcontractor situation under the
4100definition of that concept in the bid documents themselves.
410929. The bid documents provide no definition for self -
4119performance, but simply c ontain the following requirements: "a
4128contractor may not list himself as performing a type of work
4139unless he is self - performing and is a Florida licensed
4150contractor for that type of work." Therefore, if a contractor
4160meets these two requirements, he is res ponsive to this
4170specification concerning when subcontractors should be listed or
4178need not be listed in the bid response.
418630. Haycook meets both of the two requirements for self -
4197performing. Haycook's definition of self - performing work is
4206consistent with and does not conflict with the definition of
"4216subcontractor," which excludes materialmen and laborers.
422231. Haycook's expert witness, Mr. Harold Goodemote, is a
4231general contractor with 20 years experience, including 8 years
4240as a project engineer and chief estimator for Foley and
4250Associates Construction Company for many public school projects
4258in the Orlando, Melbourne, and Daytona Beach area.
4266Mr. Goodemote is also Vice - President of "Coleman - Goodemote"
4277which has been in existence for approximately 10 years and has
4288built projects worth multi - millions of dollars for Daytona
4298Speedway related entities.
430132. It was established through Mr. Goodemote's testimony
4309that it is customary in the construction industry to self -
4320perform work by the contractor's purchasing o f materials and
4330using the contractor's own employees, along with "third party
4339labor," to complete work under the direct supervision and
4348control of the general contractor. The testimony of Mr. Reed
4358Hadley and Mr. Haycook likewise establishes that it is com mon
4369practice in the construction industry to self - perform work in
4380the manner in which Haycook has performed it in the past. For
4392example, both the Lake County and Seminole County School Boards
4402allowed Haycook to list itself as self - performing where Haycook
4413purchased masonry materials and used contract labor to install
4422the masonry materials and components.
442733. "Bid shopping" is a practice whereby a contractor
4436submits a bid for a project and, after winning the bid, goes to
4449its subcontractors or even to new subcontractors, not considered
4458in the bid process, and attempts to get lower prices from them,
4470versus the prices the contractor had when it submitted its bid.
4481This allows more profit to be built into the job for the
4493contractor or, if the contractor artifi cially bid low in order
4504to get the job, tends to allow the contractor to restore profit
4516to the job for itself. The school board's rationale for
4526requiring pre - bid opening listing of subcontractors is to
4536prevent bid shopping after the bid is awarded in orde r to
4548protect the competitive integrity of the bidding process. The
4557listing of subcontractors is a practice of the Volusia County
4567School Board and some other school boards in Florida.
457634. Ms. Drago, in her testimony, acknowledged that a
4585substantial num ber of school boards in Florida do not require a
4597list of subcontractors to be provided with bid proposals, and
4607she acknowledged that this does not mean that those school
4617boards' bid processes lack credibility and competitive
4624integrity. She was unaware of any examples in the Volusia
4634County School Board's experience where a contractor listed
4642itself as self - performing and then shopped subcontractors after
4652the bid opening to obtain a better price.
466035. The preponderant evidence of record does not establish
4669t hat this has been the case with Haycook or other contractors on
4682past Volusia County School Board jobs. This is in accord with
4693Mr. Haycook's testimony, who described the detrimental effects
4701such a practice could have on future relationships between a
4711contr actors and subcontractors in terms of having them available
4721for later jobs, if a contactor became known for "beating down"
4732subcontractors' prices. If a contractor had a reputation for
4741engaging in that practice, in the future subcontractors' bids to
4751that g eneral contractor would likely be higher, if he could get
4763their bids, and this might result in that contractor having
4773difficulty rendering bid proposals that were low enough to have
4783a chance of being successful.
478836. The bid documents give the school boar d the right to
4800determine if each subcontractor listed by the bidders is
4809qualified to perform the work and if not, to reject that
4820subcontractor and require a replacement subcontractor. It is
4828noteworthy that neither the architect nor the school board
4837reject ed Haycook as being unqualified to perform the work in any
4849of the areas in which Haycook, in effect, listed itself as the
4861subcontractor.
486237. The bid documents do not provide that the school board
4873may reject "sub - subcontractors" engaged by a subcontract or, nor
4884does the school board examine the history and capabilities of
4894sub - subcontractors that a subcontractor intends to use. Once a
4905subcontractor is acceptable to the Board, there is no further
4915review to determine what means, methods, and procedures the
4924subcontractor uses to perform the work. The subcontractor can
4933contract out all of the work to sub - subcontractors who are
4945actually performing the work, and the Board might not even be
4956aware of it. Therefore, its method or rationale of listing
4966subcontracto rs and then investigating the subcontractors is no
4975guarantee of ensuring quality of work. In fact, the more areas
4986of work that the general contractor does itself, the more direct
4997control over performance the school board would have.
500538. The school board apparently uses a different approach
5014in the instance where a general contractor lists itself as a
5025subcontractor for one or more types of work, i.e. is self -
5037performing. The Board's practice in that situation requires the
5046general contractor to list each co ntractor who may perform parts
5057of the work. Therefore, the general contractor must list each
5067contractor who will perform the work in each area while this
5078standard is not applied to listed subcontractors.
508539. The bid documents do not disclose to bidders the
5095school board's unwritten definition and interpretation of "self -
5104performance." They do not reveal that under the Board's
5113interpretation a contractor must self - perform only with
5122employees on its payroll; that a pre - qualified contractor
5132licensed to perf orm work in a given area must prove that it has
5146self - performed such work in the past with its own employees
5158only; that general contractors will be treated differently from
5167subcontractors on the subcontractors list, as to the listing of
5177contract labor, and that even though the term "subcontractor" in
5187the bid documents excludes "materialmen" and "laborers," the
5195school board still considers contract labor as a subcontractor
5204or subcontracting, that must be listed for self - performance
5214work.
521540. Haycook has sub stantial experience in bidding and
5224performing work on public school projects, as does Mr. Haycook
5234himself, with both Haycook and a prior company with which he was
5246associated. Haycook had prepared a bid three or four months
5256earlier on a prototype school pr oject similar to Elementary
5266School "X" and had extensive cost information obtained from its
5276work on that project and from subcontractors, including those
"5285bidding" Elementary School "X." Haycook maintains a large
5293database of subcontractors and suppliers e xperienced in
5301performing work and portions of the work necessary for the
5311Elementary School "X" project, including cost information. It
5319has a database of over 3,000 names useful in obtaining and
5331providing labor for use on parts and subparts of any self -
5343per formed work. Prior to the bid, Haycook received the plans
5354and specifications enabling it to determine the quantities of
5363materials needed and the costs per unit for installing the
5373materials and performing the necessary work.
537941. Haycook had received subc ontractor bids in each of the
5390four areas that it later determined it would self - perform
5401(earthwork, structural steel, concrete, and masonry). Because
5408Haycook's "takeoffs," historical pricing information and recent
5415bid information from another Volusia Coun ty prototype school
5424indicated that it could self - perform the work at less cost than
5437using the bids of subcontractors in those four work areas,
5447Haycook elected to self - perform the work and listed itself as
5459the subcontractor in those four work areas. This w as not a case
5472where Haycook simply ran out of time to get subcontractors' bids
5483in those four work areas and therefore simply listed itself as
5494performing in the four work areas at issue due to time
5505expediency. It was also not because Haycook intended listi ng
5515itself as performing in the four subject work areas so that it
5527would create an opportunity to get lower bids from unknown
5537subcontractors after bid opening, in order to enhance its
5546profitability and support a low bid, in terms of putting enough
5557money in the job for itself.
556342. As general contractor for the entire project, Haycook
5572intended to provide general supervision of the entire project
5581including subcontractors. With respect to self - performed work,
5590Haycook intended to supply materials and component s and to
5600directly supervise and control the means, methods, and
5608procedures of the self - performed work with contract labor.
561843. Haycook's definition of "self - performance" for
5626earthwork involved Haycook's renting equipment, retaining
5632contract laborers to c lear the site, place the fill (paid by the
5645hour or by the yard), compact the fill, and grade the site.
5657Haycook directly supervises self - performed work and schedules
5666and manages it with Haycook's project manager and on - site
5677superintendent.
567844. The testim ony of Reed Hadley and Dennis Haycook on
5689behalf of Haycook established that Haycook had self - performed
5699earthwork on other projects in the same manner as described
5709above, satisfactorily for the owners. Specific project names
5717and other project information s howing earthwork self - performance
5727by Haycook was provided to the architect as referenced above.
5737Mr. Haycook established that Haycook had "self - performed"
5746earthwork on 50 to 60 percent of its projects in the past.
575845. Haycook's definition of self - perform ance of structural
5768steel included engaging a licensed fabricator, as required by
5777the bid specifications in this instance, hiring experienced
5785labor erection crews, purchasing the materials and component
5793parts, and directly supervising and managing the work, including
5802scheduling of the labor crews. Haycook had performed structural
5811steel on 10 to 15 percent of its past projects. Four examples
5823of projects, self - performed in structural steel, were provided
5833to the architect along with related detailed informati on.
584246. Haycook's self - performance of concrete work included
5851its purchasing of materials, hiring contract labor for footings,
5860paid by the lineal foot, and concrete slabs paid by the square
5872foot, and directly supervising, coordinating, and scheduling the
5880concrete work activities with Haycook's own project managers and
5889superintendent. Haycook has self - performed concrete work on
5898approximately 80 percent of its past projects. The architect
5907was provided a project listing of self - performed concrete work
5918and d etailed information showing Haycook's experience in this
5927area. Concrete work is the area of work most commonly self -
5939performed by general contractors in the construction market area
5948in and around Volusia County.
595347. Haycook's self - performance of masonr y includes
5962Haycook's purchasing of concrete blocks, and reinforcing steel
5970placed within the block, hiring labor on a unit price basis to
5982install it (as, for instance, paid by the block laid), directly
5993supervising the work, and coordinating and scheduling t he
6002masonry work activities with Haycook's project manager and
6010superintendent. Haycook has self - performed masonry on
6018approximately 70 percent of its past projects. The architect
6027was provided examples of projects listing self - performed masonry
6037work by Hayc ook, as well as detailed information depicting
6047Haycook's experience in this work area.
605348. Mr. Goodemote, as referenced above, is a local general
6063contractor with school board project experience and is Haycook's
6072expert witness. He established that it is common practice in
6082the construction industry in the Volusia County area for
6091contractors to self - perform work in the manner that Haycook had
6103self - performed it in the past and proposes to do on Elementary
6116School "X." He established with reference to the Boa rd's
6126definition of "subcontractor," which excludes "materialmen" and
"6133laborers," that a contractor's purchase of materials and the
6142hiring of contract labor to install the materials does not come
6153within the definition of "subcontractor" or "subcontracting."
6160He established that a subcontractor is the one who provides all
6171labor, material, equipment, and supervision necessary to
6178complete a work operation. "It's a total turnkey operation.
6187They provide everything to finish the work." Mr. Goodemote's
6196opinion e stablishes that "self - performance" of the subject work
6207includes a general contractor hiring contract labor to perform a
6217part of the work, because many times there are multiple vendors
6228associated with a portion of the work, and the contractor is
6239still direc ting and supervising the work and assuming all the
6250risks associated with the work. Mr. Goodemote himself has self -
6261performed as a general contractor and observed other contractors
6270self - perform earthwork, masonry, concrete work, and structural
6279steel work. He demonstrated that if a general contractor uses
6289contract labor to perform a portion of the work, it still
6300remains a "self - performance" by the general contractor, and that
6311the laborers do not have to be on the contractor's payroll in
6323order for the work to constitute self - performance, according to
6334the general practice and usage in the construction industry.
634349. When requested by the architect to provide examples of
6353past projects that it had self - performed in the four subject
6365work areas, Haycook listed fiv e projects as to earthwork; four
6376projects in structural steel; seven projects as to masonry; and
6386seven projects as to concrete. In consideration of his
6395restrictive view of what self - performance means (i.e. that self -
6407performance can only mean performance o f work by salaried
6417employees on the general contractor's own payroll), the
6425architect (evaluator) requested payroll records and workers'
6432compensation information on two projects only, the Goldsboro
6440Elementary School and Eustis Elementary School.
644650. The b id documents do not provide unbridled discretion
6456in the architect/evaluator, or in the school board, to define
6466self - performance in a manner not provided for or inconsistent
6477with the bid documents or to define "subcontractor," to include
6487contract labor and thus require the labor to be listed as a
6499subcontractor on the bid response. There was no notice to any
6510of the bidders that such a restrictive definition would be
6520employed, nor that a contractor listing itself as self -
6530performing, and therefore standing in same position as other
6539subcontractors as to the areas of work it would self - perform,
6551would be treated differently from other subcontractors by, in
6560effect, having to list such persons or entities as those
6570providing contract labor as "sub - subcontractors." T here was no
6581evidence that the architect was provided sole discretion to
6590verify self - performance experience as to the two projects only
6601and ignore verification information of self - performance as to
6611the other listed projects provided by Haycook.
661851. Althou gh the architect and the Board contended that
6628Haycook's listing of itself as self - performing in the four work
6640areas at issue might allow Haycook to "buy out" subcontractors
6650or to "bid shop," there was no evidence offered to substantiate
6661that this was Hayco ok's intent or that Haycook or any other
6673identified contractor in Volusia County or the surrounding area
6682had ever attempted to "buy out" subcontractors on Volusia County
6692school projects. Contrarily, Mr. Haycook testified that he does
6701not engage in a pract ice of "buying out" subcontractors after he
6713has obtained contracts with a winning bid. He explained, as
6723referenced above, that subcontractors and the business
6730relationships that he has with them are crucial to the success
6741of his business. If Haycook made a practice of engaging in such
6753inappropriate operational and pricing conduct when bidding for
6761projects, or entering into related contracts, then
6768subcontractors would either elect not give bids to Haycook at
6778all when Haycook was, in the future, attempting to formulate bid
6789responses, or would not give Haycook their lowest or best price
6800because of their knowledge of such a practice, if Haycook
6810engaged in it. This would obviously have an adverse effect on
6821Haycook's ability in the future to be successful in co mpetitive
6832bid procurements or projects.
683652. Haycook has self - performed in the manner intended as
6847to Elementary School "X" for years, as have his competitors.
6857Although the Board apparently feared that Haycook's listing
6865itself as self - performing in the areas of work in question gave
6878it a competitive advantage over other bidders, the evidence does
6888not bear out that fear. The competing bidders had the same
6899opportunity to look at their past cost knowledge and experience,
6909their knowledge of materialmen and suppliers in the area, their
6919knowledge of the labor market and available labor and other data
6930by which they might arrive at an independent evaluation of what
6941a particular area of the work should cost, as well as the
6953methods and means necessary to perform i t. They had the same
6965opportunity to evaluate any such knowledge base they have and
6975elect to self - perform one or more areas of the work, as did
6989Haycook. Since they had the same opportunity to do so, the
7000evidence does not show there is any competitive adva ntage gained
7011by Haycook in this situation which was not available to other
7022bidders as well.
702553. As addressed above, the architect's recommendation to
7033reject the Haycook bid was based upon his interpretation that
"7043self - performance" required all work to be accomplished by
7053employees on Haycook's payroll. Using that restrictive
7060definition, the architect concluded that Haycook did not
7068demonstrate, as to the Goldsboro and Eustis projects only, that
7078Haycook had self - performed work with its own employees in the
7090past and therefore that Haycook would self - perform with its own
7102employees on the project at issue. The architect concluded that
7112Haycook's subsequent engagement of contract labor in lieu of
7121using his own payroll employees "could potentially give D. J.
7131Hayc ook Construction Company an unfair advantage over the other
7141bidders." Neither the architect's testimony nor the Board's
7149other evidence explained, however, how that would give the
7158Petitioner an unfair advantage over other bidders who, as found
7168above, were free to engage in the same proposed self - performance
7180as Haycook. The evidence did not establish how it would harm
7191the public's strong interest in getting the best possible price
7201for a quality construction effort that was completed on time,
7211within the auth orized budget, and in accordance with all the
7222contractual terms. The architect's and Board's conclusion in
7230this regard is based upon incorrect and unreasonable
7238interpretations of what is meant by "subcontractor" and the
7247concept of "self - performance." The rationale for finding that
7257Haycook's putative self - performance would give Haycook an unfair
7267advantage, vis a vis, other bidders or would promote bid
7277shopping or buy - out of subcontractors has been shown by the
7289evidence to be based upon speculation and conj ecture.
729854. Haycook's bid response has been shown to be responsive
7308to the specifications as they were stated, published and
7317furnished to the bidders, including Haycook, in the bid
7326documents at issue. The definition of self - performance employed
7336by the a rchitect and the Board is not supported by the language
7349of the bid documents and has been shown by the preponderant,
7360most credible evidence of record to be an unreasonable
7369definition and manner of evaluating the bids and particularly
7378Haycook's bid. Haycoo k has been shown to be responsive to the
7390specifications and the relevant portions of the bidding
7398documents and to have the lowest bid by a significant amount,
7409some $241,000.00 dollars as to the base bids of Haycook versus
7421that of Clancy and Theys.
7426CONCLUSI ONS OF LAW
743055. The Division of Administrative Hearings has
7437jurisdiction of the subject matter of and the parties to this
7448proceeding. §§ 120.569, 120.57(1), Fla. Stat. (2003).
745556. Section 120.57(3)(f), Florida Statutes, provides
7461pertinently as follows:
7464. . . Unless otherwise provided by statute,
7472the burden of proof shall rest with the
7480party protesting the proposed agency action.
7486In a competitive - procurement protest, other
7493than a rejection of all bids, proposals, or
7501replies, the administrative law judge shall
7507conduct a de novo proceeding to determine
7514whether the agency proposed action is
7520contrary to the agency's governing statutes,
7526the agency's rules or policies, or the
7533solicitation specifications. The standard
7537of proof for such proceeding shall be
7544whet her the proposed agency action was
7551clearly erroneous, contrary to competition,
7556arbitrary, or capricious. . . .
7562Thus the Petitioner protestant must sustain its burden of proof
7572by preponderant evidence. Department of Transportation v.
7579J.W.C. Company, Inc. , 396 So. 2d 778, 787 (Fla. 1st DCA 1981);
7591State Contracting and Engineering Corp. v. Department of
7599Transportation , 709 So. 2d 607, 609, (Fla. 1998).
760757. The Petitioner must thus demonstrate that the agency's
7616proposed action is contrary to governing stat utes, the agency's
7626rules or polices, or the bid or proposal specifications. Put
7636another way, it must be determined whether the agency was in
7647error in applying a governing principle, as for instance, its
7657interpretation or application of bid specifications. In making
7665a determination on the above issue objective facts, historical
7674or present reality must be found. Objective facts are those
7684which would depict, for example, how a bidder has operated in
7695the past with regard to past projects and how it proposes to
7707operate and perform with regard to the specifications its bid
7717and the construction at issue. The determination of such
7726objective facts, which lead to a determination of whether the
7736bidder has complied with the relevant specifications, and, if
7745not, whet her its deviation is material or non - material, involves
7757a weighing of probative testimony and other evidence which is
7767conflicting to some degree and maybe hotly contested. This
7776factual determination is the province of the Administrative Law
7785Judge; to weig h and make determinations concerning the candor,
7795credibility, and creditability of the testimony and documentary
7803evidence, the relative competency of the witnesses, in terms of
7813their experience with the subject matter at issue, their
7822relative opportunity t o observe as to contested factual matters,
7832the internal logical consistency of their testimony and its
7841relative level of consistency with that of other witnesses as to
7852contested factual matters. Judgments must thus be made as to
7862credibility and the relati ve weight to be ascribed to the
7873testimony and evidence offered by each party as to the contested
7884factual matters. Such objective facts are thus susceptible to
7893proof by ordinary and conventional methods.
7899Because a bid protest is fundamentally a de
7907novo proceeding, it is concluded that the
7914agency is entitled to no deference in
7921connection with the resolution of disputes
7927involving objective facts. It is
7932exclusively the judge's job, as the trier of
7940fact, to ascertain from the competent
7946substantial evidence in the record what
7952actually happened in the past or what
7959reality presently exits, as if no decision
7966previously had been made.
7970See R.N. Expertise Inc., v. Miami - Dade County School Board and
7982Preventive Medical Testing Center, Inc., d/b/a Global MRO,
7990Inter venor , 2002 WL 185217 (Florida Division of Administrative
7999Hearings Case No. 01 - 2663BID, 2002).
800658. The purpose of competitive bidding is to secure the
8016lowest responsible offer. Minor irregularities in bids, vis a
8025vis, specifications can be waived, ef fectuating that purpose.
8034See Air Support Services International Inc., v. Metropolitan
8042Dade County , 614 So. 2d 583, 584 (Fla. 3rd DCA 1993); Tropabest
8054Foods, Inc., v. State of Florida, Department of General
8063Services , 493 So. 2d 50, 52 (Fla. 1st DCA 1986). Although a bid
8076containing a material variance from the specifications is not
8085acceptable, Glatstein v. City of Miami , 399 So. 2d 1005 (Fla.
80963rd DCA 1981), rev. denied , 407 So. 2d 1102 (Fla. 1981), not
8108every deviation from the invitation is material.
811559. The court in Robinson Electrical, Inc., v. Dade
8124County , infra ., stated:
8128In determining whether a specific non -
8135compliance constitutes a substantial and
8140hence a non - waivable irregularity, the
8147courts' have applied two criteria - first,
8154whether the effect of a waiver would be to
8163deprive the municipality of its assurance
8169that the contract will be entered into,
8176performed and guaranteed according to its
8182specified requirements, and second, whether
8187it is of such a nature that its waiver would
8197adversely affect compet itive bidding by
8203placing a bidder in a position of advantage
8211over other bidders or by otherwise
8217undermining the necessary common standard of
8223competition.
8224In application of the general principles
8230above discussed, sometimes it is said that a
8238bid may be re jected or disregarded if there
8247is a material variance between the bid and
8255the advertisement. A minor variance,
8260however, will not invalidate the bid. In
8267this context a variance is material if it
8275gives the bidder a substantial advantage
8281over the other bidd ers, and thereby
8288restricts or stifles competition.
8292See Robinson Electrical Company v. Dade County , 417 So. 2d 1032
8303(Fla. 3rd DCA 1982).
830760. In the case at hand the Respondent Board, in essence,
8318contends that the Petitioner's bid was not responsive t o the
8329specification. Although the specification at issue permits the
8337bidder, Haycook, to list itself as self - performing in lieu of
8349listing subcontractors for the areas of work in question, which
8359Haycook did, the Respondent contends that Haycook did not
8368es tablish to the satisfaction of the architect/evaluator and the
8378Board that it had self - performed on past projects or would do so
8392on this one, Elementary School "X." Therefore, the Board
8401believes that the Petitioner will actually use subcontractors
8409whose bi ds will be obtained after bid opening, supportive of its
8421lower bid price and thereby to obtain a competitive advantage
8431over other bidders; contending, in essence, that its claiming of
8441self - performance is a subterfuge.
844761. The architect/evaluator interp reted the self -
8455performance concept to mean that the bidder should do so only
8466with its own resources, meaning employees on its own payroll,
8476largely using as a measure whether Haycook had paid workers'
8486compensation coverage for those employees. The evaluato r
8494focused on only two past projects, the Goldsboro School job and
8505the Eustis Elementary School job out of all the information
8515purportedly probative of past self - performance furnished him by
8525Haycook in the information gathering - bid evaluations process, in
8535d eciding that Haycook did not have a record of self - performance.
8548Notably, however, the Board's witness concerning the Eustis
8556School project, Gary Parker, who is employed by the Lake County
8567School District, was not employed by the Lake County District
8577durin g that project and had no role in its development or
8589oversight. He testified that he had seen an entry in the
8600minutes of a meeting concerning that project in which the
8610architect had referenced Haycook's "masonry subcontractor." His
8617overall testimony on d irect and cross - examination shows,
8627however, that he had no direct personal knowledge of that
8637masonry work arrangement, the context in which the note was made
8648by the architect (who did not testify), and Parker could not
8659state definitively whether a masonry subcontractor relationship
8666existed with Haycook on that project or not.
867462. In any event, the preponderant weight of the credible,
8684most logical testimony and evidence shows, as found above, that
8694self - performance can include the use of contract labor, as was
8706done in part on those jobs. Moreover, there is no clear reason
8718or rationale for the architect/evaluator to essentially only
8726consider two of the Petitioner's past projects in arriving at
8736his conclusion that the Petitioner had not self - performed in the
8748past; extrapolating from that determination the decision that
8756Haycook would not really self - perform as to the subject project
8768and that therefore his bid in this regard was not responsive,
8779responsible, or bona fide, and instead was a subterfuge for
8789post - tab ulation "bid shopping."
879563. The architect/evaluator's decision (and therefore the
8802Board's) was based on his view that self - performance can only be
8815done with the contractor's own employees, salaried on its own
8825payroll, and for whom the contractor is payin g workers'
8835compensation coverage costs. That narrow interpretation is not
8843based upon or supported by statute, rule, or any persuasive
8853decisional law of which the undersigned has been made aware.
8863Moreover, it represents a departure from the bid specificat ion,
8873which does not contain it and does not even define self -
8885performance. Thus that interpretation of the term, as carried
8894out herein in determining that Haycook, in the Board's view, is
8905unresponsive and not a responsible bidder, in effect, given the
8915prep onderant evidence culminating in the above germane Findings
8924of Fact, does not accord with facts, logic, and reason and is
8936therefore arbitrary. See Agrico Chemical Company v. Department
8944of Environmental Regulation , 356 So. 2d 759, 763 (Fla. 1st DCA
89551978).
895664. This is especially so given the preponderant evidence,
8965supportive of the above related Findings of Fact, which shows
8975that, even if Haycook had not self - performed on past projects,
8987it is thoroughly capable from an operational, staff,
8995experiential, an d financial standpoint to do so on the present
9006project. There is no preponderant, persuasive evidence to show
9015that Haycook intends to do otherwise. The testimony as to the
9026Board's fear that anti - competitive activity such as bid shopping
9037or "buyout" of su bcontractors will occur does not rise above
9048speculation and conjecture.
905165. Moreover, the Board has a policy and practice, and is
9062authorized by the terms of the bid documents, to investigate
9072subcontractors listed by bidders to determine if they are
9081reput able and will likely do quality work. The Board can
9092require substitution of a subcontractor it believes is not
9101reliable. Once the inquiry is over, the Board does not look
9112further at how the subcontractor performs, leaving that to the
9122supervision of the g eneral contractor. The subcontractor is
9131free to "sub - subcontract" out parts of its work, as is commonly
9144done, without objection or inquiry under the Board's practice.
9153The general contractor, however, when listing itself, in effect,
9162as a subcontractor on its bid, because, as here, it is self -
9175performing, would be precluded from "sub - subbing" out part of
9186the work to a sub - subcontractor. This is because of the Board's
9199interpretation of the concept of self - performance to mean that
9210it can only be done by salar ied employees actually on the
9222general contractor's payroll. The Board does not require that
9231stricture of others who are in the posture of subcontractors and
9242are not the general contractor. Thus, in effect, the Board
9252would require the listing as a subcont ractor of each entity
9263providing any portion of the work to the general contractor who
9274is not such a salaried employee of the general contractor, while
9285not applying this standard to listed subcontractors. This
9293unequal application of the Board's interpretat ion of self -
9303performance is, in itself, also not supported by the terms of
9314the specification nor the above found facts. It is illogical
9324under the circumstances and therefore arbitrary.
933066. The preponderant, credible testimony and evidence
9337shows that se lf - performance by a contractor may be accomplished
9349by the purchase of materials and employing, directing, and
9358supervising labor in performing the work. Self - performance does
9368not mean that a bidder or contractor must only perform with
9379persons or employees on its own payroll, so long as the bidder
9391controls the means of performance, as well as the results. This
9402is the manner of self - performance proposed by Haycook. It would
9414still supervise and direct even contract labor (not employing
9423supervision by some in tervening subcontractor).
942967. Employees can be such without actually being on the
9439contractor's salaried payroll. Webster's Dictionary defines
"9445employee" as a person who works for another in exchange for
9456financial compensation. Thus compensation can be accomplished
9463by paying by the hour, by the lineal foot, the square foot, or
9476by the piece. Black's Law Dictionary defines employee as:
9485A person in the service of another under any
9494contract for hire, express or implied, oral
9501or written, where the employe r has the power
9510or right to control or direct the employee
9518in the material details of how the work is
9527to be performed. . . .
9533Generally, when a person for whom services
9540are performed has the right to control and
9548direct individual who performs services not
9554only as to result to be accomplished by work
9563but also as to details and means by which
9572result is accomplished, individual subject
9577to direction is an 'employee.'
958268. In summary, the Petitioner was shown by the
9591preponderant evidence and above found facts to have complied
9600with the bid specifications which allow it to propose self -
9611performance of the work areas in question. The facts found show
9622that it intends to and will self - perform in a manner responsive
9635to the bid specification and that its operational capability,
9644experience, and past record of performing similar projects with
9653quality work, within budget and on time, will conform to the
9664Board's and public's interest in having such performance at the
9674lowest possible price. It has thus established its bid to be
9685responsive.
968669. Even assuming, arguendo , that Haycook was less than
9695fully responsive to the specification, in terms of how it
9705proposed to self - perform, the preponderant, direct, and
9714circumstantial evidence and the above facts do not show any
9724de viation to be material. The courts do not favor the
9735disqualification of a low bidder for non - responsiveness where a
9746bid irregularity does not impart an unfair competitive advantage
9755to the low bidder. In the case of Intercontinental Properties
9765v. DHRS , 60 6 So. 2d 380 (Fla. 3rd DCA 1992) the court, in
9779reversing a hearing officer's finding of unresponsiveness on the
9788part of a bidder, discussed at length the well - known case of
9801Liberty County v. Baxter's Asphalt and Concrete Inc. , 421 So. 2d
9812505 (Fla. 1982) co ncerning principles applicable to competitive
9821bidding. The Intercontinental court enunciated the principle
9828from the Baxter's opinion that:
9833A minor irregularity is a variation from the
9841bid invitation or proposal terms and
9847conditions which does not affect t he price
9855of the bid, or give the bidder an advantage
9864or benefit not enjoyed by other bidders, or
9872does not adversely impact the interest of
9879the department. . . .
9884There is a very strong public interest in
9892favor of saving tax dollars in awarding
9899public contr acts. There is no public
9906interest, much less a substantial public
9912interest, in disqualifying low bidders for
9918technical deficiencies in form, where the
9924low bidder did not derive any unfair
9931competitive advantage by reason of the
9937technical omission. . . .
9942I n either event, there is a strong public
9951policy in favor of awarding contracts to the
9959low bidder, and an equal strong public
9966policy against disqualifying the low bidder
9972for technical deficiencies which do not
9978confer an economic advantage on one bidder
9985over another. Id. at 387. (Emphasis
9991supplied).
9992See also ESP Security and Satellite Engineering, Inc., v.
10001University of Florida, Physical Plant Division,
10007Architecture/Engineering Department , (Case No. 94 - 2035BID,
10014Division of Administrative Hearings, April 12 , 1995).
1002170. In the case at hand the Petitioner was the low bidder
10033by the substantial amount of approximately $241,000.00 on the
10043base bid. Its preponderant evidence shows it has in the past
10054and will on this school project intend to and perform in a way
10067that will result in quality work, accomplished on time and
10077within budget. Such has been its record in the projects in the
10089past, evidence of which is in the record of this proceeding.
10100The Board will be able to enforce the price and terms of the
10113Petitioner 's bid through the terms of the resulting contract.
10123Therefore there is no irregularity in responsiveness which would
10132adversely impact the interest of the Board and the taxpayers.
10142The Petitioner did not derive any unfair competitive advantage
10151over the oth er two original and higher bidders, because, under
10162the specifications they were all free to consider their
10171experience on similar projects, any data base of costs,
10180suppliers, and labor identity information and to also propose
10189self - performance in the subject work areas or in others, if they
10202so chose.
1020471. Accordingly, in consideration of the preponderant,
10211credible evidence underlying the above - found facts, and in view
10222of the above discussion and conclusions, it is determined that
10232Haycook's bid is responsiv e, responsible, and the lowest bid.
10242It has been demonstrated that the Respondent's bid evaluation
10251and intended award is factually and legally flawed. Therefore,
10260under the circumstances found and concluded above, the failure
10269to award the subject contract to Haycook would be arbitrary,
10279contrary to competition, and clearly erroneous. § 120.57(3)(f),
10287Fla. Stat. (2003).
1029072. Finally, the Petitioner asserts that if an agency
10299action determines the substantial interest of a party based upon
10309an un - adopted rule, then the agency action shall not be presumed
10322valid or invalid, but the agency must prove that the un - adopted
10335rule meets the standards enunciated in Section 120.57(1)(e),
10343Florida Statutes. The Petitioner asserts that the definition of
"10352self - performance" is not contained in the bid documents or any
10364written rules of the school board. The Petitioner asserts that
10374Ms. Drago testified that the interpretation at issue is based on
10385the Board's practice, which is not in writing. It asserts then
10396that this interpreta tion by the Board's staff architect and the
10407Board itself is an un - adopted rule which the Board must "prove -
10421up" in the manner envisioned in the above statute. The evidence
10432in this case however, does not clearly demonstrate that the
10442interpretation of the sp ecification as to "self - performance,"
10452clearly meets the definition of a rule embodied in Section
10462120.52, Florida Statutes, (2003). Moreover, to the extent that
10471the challenge to the interpretation of the specification as an
10481unpromulgated rule might be deem ed to be an attack on the
10493specifications in the bid documents, clearly the 72 hour period,
10503during which an attack on the specifications in an invitation to
10514bid or request for proposals can be mounted, long since elapsed
10525before the bids or offers were submi tted and thus is not timely.
10538§120.57(3)(b), Fla. Stat.
10541RECOMMENDATION
10542Having considered the foregoing Findings of Fact,
10549Conclusions of Law, the evidence of record, the candor and
10559demeanor of the witnesses, and the pleadings and arguments of
10569the parties, it is, therefore,
10574RECOMMENDED that a final order be entered by the School
10584Board of Volusia County awarding the contract for Elementary
10593School "X" to the Petitioner, D. J. Haycook Construction
10602Company, Inc.
10604DONE AND ENTERED this 8th day of March, 20 04, in
10615Tallahassee, Leon County, Florida.
10619S
10620___________________________________
10621P. MICHAEL RUFF
10624Administrative Law Judge
10627Division of Administrative Hearings
10631The DeSoto Building
106341230 Apalachee Parkway
10637Tallahassee, Florida 3 2399 - 3060
10643(850) 488 - 9675 SUNCOM 278 - 9675
10651Fax Filing (850) 921 - 6847
10657www.doah.state.fl.us
10658Filed with Clerk of the
10663Division of Administrative Hearings
10667this 8th day of March, 2004.
10673COPIES FURNISHED :
10676S. LaRue Williams, Esq uire
10681Kinsey, Vincent, Pyle, L.C.
10685150 South Palmetto Avenue, Box A
10691Daytona Beach, Florida 32114
10695Theodore R. Doran, Esquire
10699Michael G. Dyer, Esquire
10703Doran, Wolfe, Rost & Ansay
10708444 Seabreeze Boulevard, Suite 800
10713Post Office Drawer 15110
10717Daytona Beach, Flor ida 32115
10722William E. Hall
10725Superintendent
10726Volusia County School Board
10730Post Office Box 2118
10734Deland, Florida 32721 - 2118
10739NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
10745All parties have the right to submit written exceptions within
1075510 days from the date of thi s Recommended Order. Any exceptions
10767to this Recommended Order should be filed with the agency that
10778will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 03/08/2004
- Proceedings: Recommended Order (hearing held December 11-12, 2003). CASE CLOSED.
- PDF:
- Date: 03/08/2004
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 01/02/2004
- Proceedings: Letter to Judge Ruff from T. Doran enclosing a disk in word format with the Proposed Recommended Order filed.
- PDF:
- Date: 12/29/2003
- Proceedings: (Proposed) Recommended Order (filed by Petitioner via facsimile).
- Date: 12/26/2003
- Proceedings: Transcript of Proceedings (4 Volumes) filed.
- PDF:
- Date: 12/26/2003
- Proceedings: Notice of Filing Transcript of Proceedings Hearing before the Honorable P. Michael Ruff Taken December 11, 2003 filed.
- Date: 12/11/2003
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 12/10/2003
- Proceedings: Petitioner`s Motion to Strike Expert Witness (filed via facsimile).
- Date: 12/08/2003
- Proceedings: Transcript filed.
- PDF:
- Date: 12/08/2003
- Proceedings: Notice of Filing Transcript of Portion of Meeting of the School Board of Volusia County, Florida Held October 14, 2003 filed by Respondent.
- PDF:
- Date: 12/08/2003
- Proceedings: School Board`s Memorandum of Law in Support of Proposed Award Contract filed.
Case Information
- Judge:
- P. MICHAEL RUFF
- Date Filed:
- 10/28/2003
- Date Assignment:
- 10/28/2003
- Last Docket Entry:
- 04/08/2004
- Location:
- Deland, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Theodore R. Doran, Esquire
Address of Record -
S. LaRue Williams, Esquire
Address of Record