03-004001BID D. J. Haycook Construction Company vs. Volusia County School Board
 Status: Closed
Recommended Order on Monday, March 8, 2004.


View Dockets  
Summary: Petitioner showed method of evaluation of bids amounted to Respondent departing from specifications in an arbitrary way, which was erroneous as a matter of law and fact. Petitioner demonstrated that it was the lowest, best, and responsive bid.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8D. J. HAYCOOK CONSTRUCTION )

13COMPANY, )

15)

16Petitioner, )

18)

19vs. ) Case No. 03 - 4001BID

26)

27VOLUSIA COUNTY SCHOOL BOARD, )

32)

33Respondent. )

35)

36)

37RECOMMENDED O RDER

40This cause came on for hearing pursuant to notice on

50December 11 and 12, 2003, in Deland, Florida, before P. Michael

61Ruff, duly - designated Administrated Law Judge. The appearances

70were as follows:

73APPEARANCES

74For Petitioner: S. LaRue Willia ms, Esquire

81Kinsey, Vincent, Pyle, L.C.

85150 South Palmetto Avenue, Box A

91Daytona Beach, Florida 32114

95For Respondent: Theodore R. Doran, Esquire

101Michael G. Dyer, Esquire

105Doran, Wolfe, Rost & Ansay

110444 Seabreeze Boulevard, S uite 800

116Post Office Drawer 15110

120Daytona Beach, Florida 32115

124STATEMENT OF THE ISSUES

128The issues to be resolved in this proceeding concern

137whether the Petitioner, D. J. Haycook Construction Company

145(Haycook) was the lowest responsive bidde r for an elementary

155school procurement project known as Elementary School "X," let

164by the Volusia County School Board and whether the Petitioner

174should have been awarded the contract.

180PRELIMINARY STATEMENT

182This cause arose upon the issuance of "an adverti sement for

193bid" by the Volusia County School Board (Board) seeking sealed

203bids from contractors for the construction of a new elementary

213school for Volusia County, Elementary School "X." The bids were

223to be submitted on or before 2:00 p.m., August 6, 2003 , at which

236time all bids would be publicly opened and read aloud. The

247advertisement for bid was issued on July 16, 2003, and the Board

259received eleven proposals in response to it. It opened and read

270all bids for Elementary School "X" on August 6, 2003, a nd

282determined that Haycook was the lowest bidder. Haycook's base

291bid was in the amount of $7,599,000.00. The firm of Clancy and

305Theys Construction Company, Inc. (Clancy and Theys) was the

314third lowest bidder with a base bid of $7,840,000.00. The

326second lowest bidder, Mark Construction Company, failed to

334extend its bid bond after the bid opening and during the

345pendency of this protest and therefore effectively withdrew its

354bid and is no longer in contention.

361The selected bidder would serve as a general c ontractor

371responsible for the construction of the school with an

380established project budget of $8,000,000.00. The bids were

390opened and read on August 6, 2003, and after the bids were

402opened the Board, through its project architect Philip Daimwood,

411of Daim wood, Derryberry, Pavelchak Architects, P.A. (architect

419or Daimwood), began an investigation of the low bidder, in

429accordance with the Board's interpretation of the advertisement

437and solicitation specifications wherein the Board reserved the

445right to use s ufficient time to investigate the bids and

456qualifications of the bidders. In this investigatory process

464the Board, through its architect, solicited information from the

473low bidder, Haycook, in order to ascertain that Haycook had the

484capability, based in p art upon information from its earlier jobs

495or projects, to self - perform work in four areas: earthwork,

506structural steel, masonry, and concrete. A number of letter

515exchanges and at least one meeting between representatives of

524Haycook and the Board occurred in this regard.

532Ultimately the Board took the position that Haycook's bid

541was not responsive because of failure to comply with all

551requirements of the solicitation advertisement and addenda. The

559Board thus awarded the contract to the third lowest bidd er,

570Clancy and Theys, on October 14, 2003. Haycook timely protested

580the proposed award and the cause was forwarded to the Division

591of Administrative Hearings and ultimately to the undersigned

599administrative law judge. Upon waiver of the relevant time

608per iod for setting of the hearing, the parties agreed to set the

621hearing on December 11 and 12, 2003, and the hearing proceeded

632as scheduled on those dates.

637In its formal written protest Haycook questioned the school

646Board's authority to verify Haycook's e xperience and capability

655to, in effect, serve as its own subcontractor ("self -

666performing") in the work areas of structural steel, concrete,

676masonry, and earthwork. Haycook protested on grounds that the

685school board failed to follow its own rules and the b id

697documents in determining the lowest responsive bidder, and that

706Section 120.57(3)(f), Florida Statutes, prohibits consideration

712of submissions after the bid opening which amend or supplement a

723bid or proposal. Haycook also maintains that the rejection of

733its bid was grossly arbitrary and unfair by applying evaluation

743criteria not set forth in the school board's rules or bid

754documents, and that the Board improperly delved into Haycook's

763means, methods, and procedures of self - performing its work,

773misappli ed the definition of "self - performed," and that the

784Board's inability to verify to its satisfaction prior self -

794performed work by Haycook on other past projects is not a legal

806criteria for rejection. Haycook maintains that the bid

814documents do not define " self - performance," nor do they require

825pre - qualified bidders to prove to the school board architect's

836satisfaction that the bidder has self - performed work on similar

847school projects in the past, by proving the use of only salaried

859employees on Haycook's ow n payroll. Haycook takes issue with

869the school board's definition of "self - performance" and contends

879that its means, methods, and procedures for self - performing the

890work were not prohibited by the bid documents or any rules or

902regulations of the Board tha t relate to bidding of school board

914projects.

915The school board maintains that it could not verify that

925Haycook had "self - performed" earthwork, structure steel,

933concrete, and masonry on prior school projects and that, based

943upon the Board's interpretatio n of self - performance, that

953Haycook's self - performance on its earlier projects really

962amounted to the use of "subcontractor" relationships and not

971self - performance. Because it did not list subcontractors in

981these four areas on the relevant bid document, a nd did not

993establish to the Board's architect's satisfaction that it would

1002self - perform these areas of work with its own labor,

1013supervision, and material resources, that Haycook had been non -

1023responsive as to these four areas of work on its bid.

1034Haycook ca lled four witnesses to testify at the hearing:

1044Jack Dunlap, Reed Hadley, Harold Goodemote, and Dennis Haycook.

1053Mr. Goodemote was presented as an expert witness. The parties

1063agreed that Petitioner's Exhibits 1 through 9 and the

1072Respondent's Exhibits 1 th rough 28, some of which Haycook also

1083used for its own exhibits, would be jointly offered and received

1094into evidence. The Board called witnesses Patricia Drago,

1102Philip Daimwood, Carl Gerken, Scott Stegall, Allen Green, Gary

1111Parker, Steve Eckman, and Gary E hrlich as its witnesses.

1121Witnesses Stegall, Parker, Eckman, Green, Daimwood, and Gerken

1129were presented as expert witnesses on behalf of the school

1139Board.

1140Prior to the hearing the parties filed a Joint Pre - Hearing

1152Stipulation setting forth contested and u ncontested issues of

1161fact and law. The school board also filed a Memorandum of Law

1173prior to hearing. Upon conclusion of the hearing the parties

1183ordered a transcript thereof which was submitted along with the

1193parties' timely submitted Proposed Recommended Orders. The

1200Transcript, the Proposed Recommended Orders, and the notes of

1209the undersigned have been carefully read and considered in the

1219rendition of this Recommended Order.

1224FINDINGS OF FACT

12271. On June 13, 2003, the School Board of Volusia County

1238autho rized the issuance of a request for proposal for the

1249construction of a new elementary school known as Elementary

1258School "X." The proposed new school would be located in Orange

1269City, Florida.

12712. The school board issued an advertisement for the

1280constructi on of Elementary School "X" and had it published. The

1291project architect for the Board prepared the solicitation

1299documents constituting a "Phase III specifications" manual and

1307three addenda.

13093. The advertisement stated that "the school board

1317expressly re serves the right to reject any and all bids and to

1330waive informalities therein, and to use sufficient time to

1339investigate the bids and the qualifications of the bidders."

13484. Section 00430 of the solicitation required that all

1357bidders list the name of the subcontractor for each type of the

136912 areas of construction work for Elementary School "X" as

1379follows:

1380'For each type of work' below, list the name

1389of the subcontractor. List only one name on

1397each line and only one subcontractor for

1404each type of work. V arious 'type of work'

1413sub - contracts may have more than one

1421subcontractor (re: roofing; metal roofing

1426and membrane roofing), list each

1431subcontractor accordingly. Use additional

1435sheets, if required.

1438Additionally, Section 00430 provided:

1442The term subcontrac tor as used herein shall

1450be defined in 2001, Florida Statute

1456713.01(27) - subcontractor means a person

1462other than a materialman or laborer who

1469enters into a contract with a contractor for

1477the performance of any part of such

1484contractor's contract.

1486The dead line for submission of proposals in response to the

1497solicitation was August 6, 2003. On August 6, 2003, Haycook's

1507bid proposal and that of the second and third lowest bidders

1518were opened and read by the members of the school board's staff.

1530Haycook listed itself as performing or "self - performing" in

1540areas of earthwork, masonry, concrete, and structural steel on

1549the required list of subcontractors form pursuant to section

155800430 of the solicitation.

15625. Subsequently, the project architect began to

1569investi gate the bids for the project. This was done through

1580correspondence and direct contact between Haycook, the project

1588architect, Mr. Daimwood, and the school board staff. This

1597process began on August 8, 2003. As part of the evaluation

1608process the architec t verbally requested documentation from

1616Haycook to verify its past and present abilities to self - perform

1628in the four areas of earthwork, concrete, masonry, and

1637structural steel, as well as by letters dated August 12, August

164815, and August 25, 2003. Haycoo k responded to these information

1659requests by letters of August 11, 13, and 28, 2003.

16696. The bid documents for the school project included the

1679bidding and contractual conditions, general conditions,

1685technical specifications, and the drawings listed on pag es 10D - 1

1697to 10D - 2. In order to have a responsive bid a bidder was

1711required to comply with the bid documents when submitting its

1721bid. The relevant bid documents at issue in this dispute are

1732Section 0020, "invitation to bid," Section 00100, "instruction

1740to bidders," Section 00300, "bid form," and Section 00430, "list

1750of subcontractors."

17527. The bid documents also required each bidder to deliver

1762a bid bond in the amount of five percent of its bid to accompany

1776the proposal. After acceptance of the lowest re sponsive bid,

1786and issuance of the contract award, a bidder was required to

1797deliver a payment and performance bond in the amount of 100

1808percent of the contract price. There is no dispute that Haycook

1819has a bonding capacity of 18 million dollars for a singl e

1831project and 35 million dollars for aggregate projects and the

1841bonding capacity is not in dispute.

18478. The invitation to bid documents require that bidders be

1857required to hold a current Certificate of Pre - Qualification

1867issued by the school board at the t ime of bid opening. Haycook

1880at all material times hereto held a Certificate of Pre -

1891Qualification and was licensed to perform all work called for by

1902the bid documents including, among others, self - performance of

1912earthwork, concrete work, masonry, and struc tural steel.

19209. The three bids received were in the amounts as follows:

1931(1) D. J. Haycook Construction Company: a base bid of

1941$7,599,000.00; Alternate One, $189,000.00; Alternate Two,

1950$48,800.00; Alternate Three, $21,000.00; (2) Mark Construction

1959Comp any of Longwood, Florida: base bid of $7,657,000.00,

1970Alternate One, $221,000.00; Alternate Two, $50,000.00; Alternate

1979Three, $20,000.00; (3) Clancy and Theys Construction Company of

1989Orlando, Florida: base bid of $7,840,000.00; Alternate One,

1999$230,000.00; A lternate Two, $50,000.00; Alternate Three,

2008$21,000.00.

201010. Section 00430 required each bidder to furnish a list

2020of subcontractors defined as quoted above in the bid form.

2030Section 00430 of the bid form also permitted a bidder to list

2042itself as a subcontr actor. The form provides: "A contractor may

2053not list himself as performing a type of work unless he is self -

2067performing and is a Florida licensed contractor for that type of

2078work". Haycook was properly licensed at the time of bidding,

2089and at all relevant times, to self - perform in the four areas of

2103earthwork, structural steel, masonry, and concrete at issue in

2112this case.

211411. After the bids were opened and examined, Mr. Daimwood,

2124the architect evaluating bids for the school board, requested

2133that Haycook fu rnish a list of past projects where it had self -

2147performed earthwork, structural steel, masonry, and concrete

2154work. Haycook provided a list of examples of prior projects for

2165which it had self - performed work in those areas on August 11,

21782003. The list incl uded five projects for earthwork, four

2188projects for structural steel, seven projects for masonry, and

2197seven projects for concrete. Thereafter, on August 12, 2003,

2206the architect requested additional information regarding self -

2214performance of work in the fou r areas at issue.

222412. Haycook provided the architect with the requested

2232additional information on August 13, 2003, including a list of

2242each project, the total cost of each project, the completion

2252dates, as well as contact persons with their telephone num bers

2263and including copies of qualifications of the subcontractors

2271listed on Haycook's subcontractor list.

227613. On August 25, 2003, the architect requested Haycook

2285payroll records and workers compensation information for two of

2294the listed projects of tho se Haycook had provided, that for

2305Goldsboro Elementary School and Eustis Elementary School.

231214. On August 28, 2003, Haycook sent a letter to the

2323architect explaining that on the Goldsboro job the earthwork was

2333self - performed by a combination of supervisi ng and directing the

2345work with salaried employees, with leasing of labor from an

2355employment service, and hiring of labor by the cubic yard with a

2367cap on the activity. Haycook also explained that structural

2376steel work on the projects was self - performed by a combination

2388of supervising and directing the work with salaried employees,

2397leasing of labor from an employment service, hiring of labor

2407paid by the foot to erect specific components of the job, as

2419well as using salaried employees for the performance of s pecific

2430activities, and including purchasing of fabricated materials and

2438then hiring crew labor and equipment on an hourly basis to erect

2450them.

245115. In the August 28, 2003, letter Haycook also explained,

2461with respect to the self - performed masonry work o n both the

2474Eustis and Goldsboro jobs, that those areas of work were self -

2486performed by purchasing fabricated material, supervising and

2493directing the work with salaried employees, hiring labor by the

2503unit price (for instance by the block) to lay the block, a nd

2516hiring labor from an employee leasing service for specific

2525activities as to those jobs.

253016. Haycook also explained in the August 28, 2003, letter

2540that a combination of the methods and means of performing

2550delineated above and in that letter would be us ed for the

2562activities listed on the subcontractor list on the relevant bid

2572form for Elementary School "X". Haycook explained that it had

2583priced and used its own costs for the activities listed on the

2595bid form to arrive at the bid price for Elementary Scho ol "X".

260917. Enclosed with the August 28, 2003, letter from Haycook

2619were copies of its purchase orders and cost journals for the

2630Goldsboro School, concerning earthwork, masonry, and structural

2637steel activities and its vendor purchase orders and cost

2646journ als for the Eustis Elementary School's masonry work done by

2657Haycook. The enclosures with the August 28, 2003, letter showed

2667that Haycook had purchased the materials, performed the work

2676with its own employees, and performed work using additional

2685outside la bor in the areas of structural metals, prefabricated

2695structures, earthwork, cast - in - place concrete, structural steel

2705erection, and masonry work. Haycook also provided its proposals

2714used on the Goldsboro project which consisted of concrete labor

2724and struct ural steel labor.

272918. The architect interpreted the term "self - performance"

2738to mean labor with the contractor's own employees only. Based

2748upon that restrictive interpretation, he concluded that he had

2757not found adequate information demonstrating Hayco ok's having

"2765self - performed" these types of work previously. Additionally,

2774the architect opined that Haycook's intended self - performance on

2784Elementary School "X" project at issue, in the four work areas

2795in dispute, "is in our opinion, a subcontractor form at."

280519. Uncontroverted evidence adduced at hearing established

2812that Haycook has extensive public school construction

2819experience. The Petitioner's President, Dennis Haycook, has

2826built more than 35 public schools and Haycook's project manager,

2836Reed Hadl ey, who is assigned to the Elementary School "X"

2847project, has built over 25 school projects. Dennis Haycook was

2857also a principal of Mark Arnold Construction Company in the

2867past, which was one of the largest public school contractors in

2878Florida. In the pa st 10 years, with his own company, the

2890Petitioner, Haycook, has built numerous school projects

2897including the Goldsboro school which was a $7,000,000.00

2907project. The Goldsboro, Eustis, and other Haycook - built schools

2917referenced during the hearing and in th e evidence were all

2928projects that were built within the authorized budget, were

2937timely, and were of quality construction.

294320. The Board ultimately rejected Haycook's bid on

2951Elementary School "X" because of the architect's interpretation

2959concerning "self - performance," i.e. that all work must be

2969performed by employees on Haycook's payroll. The bid documents

2978did not define "self - performance," nor do the bid documents

2989require that labor used must be on the contractor's payroll in

3000order for his performance to constitute "self - performance."

300921. Haycook's witnesses were consistent in their testimony

3017as to the definition of "self - performance": "self - performance,"

3029as customarily used in the construction industry, includes the

3038contractor's purchasing of materials , performing part of the

3046work with its own labor force, providing other labor not on the

3058contractor's payroll, and directly supervising the work with the

3067contractor's supervisory personnel. The term "subcontractor" is

3074defined in the custom and usage of th e construction industry,

3085however, to mean someone or an entity that provides all labor,

3096material, and equipment necessary to do the complete operation,

3105as well as all supervision. It is more of a "total turn key

3118operation." A subcontractor provides every thing necessary to

3126finish the work, including supervision, and then merely answers

3135to the general contractor in terms of responsibility for the

3145quality of the job and its timeliness.

315222. The school board's witnesses, expert and otherwise,

3160gave interpre tations of the concept of self - performance which

3171were somewhat conflicting. Mr. Daimwood, the architect, opined

3179that self - performance requires the contractors to use employees

3189on its own payroll and make direct payment of workers'

3199compensation for such em ployees. His opinion was that anything

3209else would be a subcontractor relationship and not self -

3219performance. He later testified, however, that paying labor not

3228actually on Haycook's payroll could still constitute self -

3237performance. Patricia Drago, of the school board staff,

3245testified that if a contractor uses 10 employees on his payroll

3256and uses 10 non - employees, this would be self - performance. If

3269such a contractor has 10 employees and uses 11 non - employees,

3281she was not sure whether this would constitute self - performance.

3292Allen Green testified that self - performance of an area of work

3304requires the majority of that work to be performed by the

3315contractor's own employees, while other work could be performed

3324by contract labor. He later changed his definition to require a

3335contractor to have all employees on the payroll in order to

3346self - perform. In other testimony, however, Mr. Green opined

3356that if a contractor supplemented his labor with a couple of

3367additional masons and paid them by the piece, then he would n o

3380longer be self - performing. At still another point in his

3391testimony he added that it would be dependent upon the stage of

3403the project as to whether the contractor's use of contract labor

3414is self - performing or subcontracting. He felt that if the

3425contract or adds some additional masons near the end of a job, as

3438opposed to the beginning, then he could still be self -

3449performing.

345023. Gary Parker is the Director of Facilities for the Lake

3461County School Board. He testified that from his perspective,

3470self - perf ormance required the use of employees on the

3481contractor's payroll. This definition, however, was not

3488consistent with Lake County's course of conduct with the job

3498that Haycook performed. Mr. Parker acknowledged that there had

3507been no complaints by the arc hitect or anyone else associated

3518with the Eustis school project where Haycook listed itself as

3528self - performing for masonry work, even though Haycook had

3538retained a different entity to perform masonry labor (although

3547not supply materials or supervision).

355224. Scott Stegall, the Director of Capital Outlay for the

3562Seminole County School Board, testified that self - performance

3571would require a contractor to perform all work without the use

3582of outside contractors, including labor. Yet Mr. Stegall

3590acknowledged t hat Haycook listed itself as self - performing

3600masonry work on the Goldsboro school project and used a firm or

3612entity known as Webber and Tucker to perform some masonry work,

3623and that the Seminole County School Board had no dispute with

3634this approach. Mr. S tegall's evaluation form for Haycook had

3644stated that Haycook did not improperly substitute any

3652subcontractors from the submitted list in that project. He

3661later changed his definition of self - performance to acknowledge

3671that a contractor could bring in labo rers individually to

3681perform without a "formal contract"; these informal labor

3689contracts would not take it out of the self - performance category

3701according to Mr. Stegall.

370525. The evidence concerning the Lake County District's and

3714Seminole County District 's experience as to the Eustis school

3724project and the Goldsboro school project with Haycook's

3732performance, including Haycook's approach to self - performance,

3740was satisfactory in terms of pricing and the quality and

3750timeliness of the work performed. The per ceived fear by the

3761Respondent that Haycook's performance might be substandard or

3769that it might "bid shop" amongst potential subcontractors, after

3778the bid opening, if Haycook did not list all subcontractors on

3789the bid response, and self - performed in the man ner Haycook

3801described in its evidence, has not been shown to have occurred

3812with regard to any of Haycook's past projects. There has been

3823no demonstration by preponderant evidence that the use of only

3833subcontractors listed or named in the bid response has resulted,

3843in itself, in a lower price or better performance for the public

3855by a contractor situated as Haycook.

386126. The architect testified that one method of defining

"3870self - performance" is to determine whether the entity performing

3880work was a subcont ractor as defined by the bid documents. If

3892the work is not being performed by a subcontractor, then it is

3904being performed by the general contractor or self - performance.

3914As the term is used in the construction industry, a

3924subcontractor generally furnishes materials, installs the work,

3931and supervises its own work.

393627. The bid documents define subcontractor as follows:

"3944subcontractor means a person other than a materialman or

3953laborer who enters into a contract with a contractor for the

3964performance of any p art of such contractor's contract."

397328. Preponderant, credible, and substantial evidence was

3980presented by Haycook to show that Haycook's use of the term

"3991subcontractor" was an entity that furnishes the materials,

3999provides the labor, and the supervision, and undertakes the

4008entire responsibility for that type or phase of the work. When

4019a general contractor hires contract labor only, this excludes

4028what is occurring from the definition of subcontractor, since

4037the definition of subcontractor prevailing in thi s proceeding

4046based upon the bid documents, takes out of that subcontractor

4056definition "a materialman or laborer." The preponderant

4063credible evidence shows that when Haycook purchases materials

4071and provides the labor, whether or not the labor is on Haycook 's

4084payroll, which Haycook then directly supervises , this, by

4092definition, is not a subcontractor situation under the

4100definition of that concept in the bid documents themselves.

410929. The bid documents provide no definition for self -

4119performance, but simply c ontain the following requirements: "a

4128contractor may not list himself as performing a type of work

4139unless he is self - performing and is a Florida licensed

4150contractor for that type of work." Therefore, if a contractor

4160meets these two requirements, he is res ponsive to this

4170specification concerning when subcontractors should be listed or

4178need not be listed in the bid response.

418630. Haycook meets both of the two requirements for self -

4197performing. Haycook's definition of self - performing work is

4206consistent with and does not conflict with the definition of

"4216subcontractor," which excludes materialmen and laborers.

422231. Haycook's expert witness, Mr. Harold Goodemote, is a

4231general contractor with 20 years experience, including 8 years

4240as a project engineer and chief estimator for Foley and

4250Associates Construction Company for many public school projects

4258in the Orlando, Melbourne, and Daytona Beach area.

4266Mr. Goodemote is also Vice - President of "Coleman - Goodemote"

4277which has been in existence for approximately 10 years and has

4288built projects worth multi - millions of dollars for Daytona

4298Speedway related entities.

430132. It was established through Mr. Goodemote's testimony

4309that it is customary in the construction industry to self -

4320perform work by the contractor's purchasing o f materials and

4330using the contractor's own employees, along with "third party

4339labor," to complete work under the direct supervision and

4348control of the general contractor. The testimony of Mr. Reed

4358Hadley and Mr. Haycook likewise establishes that it is com mon

4369practice in the construction industry to self - perform work in

4380the manner in which Haycook has performed it in the past. For

4392example, both the Lake County and Seminole County School Boards

4402allowed Haycook to list itself as self - performing where Haycook

4413purchased masonry materials and used contract labor to install

4422the masonry materials and components.

442733. "Bid shopping" is a practice whereby a contractor

4436submits a bid for a project and, after winning the bid, goes to

4449its subcontractors or even to new subcontractors, not considered

4458in the bid process, and attempts to get lower prices from them,

4470versus the prices the contractor had when it submitted its bid.

4481This allows more profit to be built into the job for the

4493contractor or, if the contractor artifi cially bid low in order

4504to get the job, tends to allow the contractor to restore profit

4516to the job for itself. The school board's rationale for

4526requiring pre - bid opening listing of subcontractors is to

4536prevent bid shopping after the bid is awarded in orde r to

4548protect the competitive integrity of the bidding process. The

4557listing of subcontractors is a practice of the Volusia County

4567School Board and some other school boards in Florida.

457634. Ms. Drago, in her testimony, acknowledged that a

4585substantial num ber of school boards in Florida do not require a

4597list of subcontractors to be provided with bid proposals, and

4607she acknowledged that this does not mean that those school

4617boards' bid processes lack credibility and competitive

4624integrity. She was unaware of any examples in the Volusia

4634County School Board's experience where a contractor listed

4642itself as self - performing and then shopped subcontractors after

4652the bid opening to obtain a better price.

466035. The preponderant evidence of record does not establish

4669t hat this has been the case with Haycook or other contractors on

4682past Volusia County School Board jobs. This is in accord with

4693Mr. Haycook's testimony, who described the detrimental effects

4701such a practice could have on future relationships between a

4711contr actors and subcontractors in terms of having them available

4721for later jobs, if a contactor became known for "beating down"

4732subcontractors' prices. If a contractor had a reputation for

4741engaging in that practice, in the future subcontractors' bids to

4751that g eneral contractor would likely be higher, if he could get

4763their bids, and this might result in that contractor having

4773difficulty rendering bid proposals that were low enough to have

4783a chance of being successful.

478836. The bid documents give the school boar d the right to

4800determine if each subcontractor listed by the bidders is

4809qualified to perform the work and if not, to reject that

4820subcontractor and require a replacement subcontractor. It is

4828noteworthy that neither the architect nor the school board

4837reject ed Haycook as being unqualified to perform the work in any

4849of the areas in which Haycook, in effect, listed itself as the

4861subcontractor.

486237. The bid documents do not provide that the school board

4873may reject "sub - subcontractors" engaged by a subcontract or, nor

4884does the school board examine the history and capabilities of

4894sub - subcontractors that a subcontractor intends to use. Once a

4905subcontractor is acceptable to the Board, there is no further

4915review to determine what means, methods, and procedures the

4924subcontractor uses to perform the work. The subcontractor can

4933contract out all of the work to sub - subcontractors who are

4945actually performing the work, and the Board might not even be

4956aware of it. Therefore, its method or rationale of listing

4966subcontracto rs and then investigating the subcontractors is no

4975guarantee of ensuring quality of work. In fact, the more areas

4986of work that the general contractor does itself, the more direct

4997control over performance the school board would have.

500538. The school board apparently uses a different approach

5014in the instance where a general contractor lists itself as a

5025subcontractor for one or more types of work, i.e. is self -

5037performing. The Board's practice in that situation requires the

5046general contractor to list each co ntractor who may perform parts

5057of the work. Therefore, the general contractor must list each

5067contractor who will perform the work in each area while this

5078standard is not applied to listed subcontractors.

508539. The bid documents do not disclose to bidders the

5095school board's unwritten definition and interpretation of "self -

5104performance." They do not reveal that under the Board's

5113interpretation a contractor must self - perform only with

5122employees on its payroll; that a pre - qualified contractor

5132licensed to perf orm work in a given area must prove that it has

5146self - performed such work in the past with its own employees

5158only; that general contractors will be treated differently from

5167subcontractors on the subcontractors list, as to the listing of

5177contract labor, and that even though the term "subcontractor" in

5187the bid documents excludes "materialmen" and "laborers," the

5195school board still considers contract labor as a subcontractor

5204or subcontracting, that must be listed for self - performance

5214work.

521540. Haycook has sub stantial experience in bidding and

5224performing work on public school projects, as does Mr. Haycook

5234himself, with both Haycook and a prior company with which he was

5246associated. Haycook had prepared a bid three or four months

5256earlier on a prototype school pr oject similar to Elementary

5266School "X" and had extensive cost information obtained from its

5276work on that project and from subcontractors, including those

"5285bidding" Elementary School "X." Haycook maintains a large

5293database of subcontractors and suppliers e xperienced in

5301performing work and portions of the work necessary for the

5311Elementary School "X" project, including cost information. It

5319has a database of over 3,000 names useful in obtaining and

5331providing labor for use on parts and subparts of any self -

5343per formed work. Prior to the bid, Haycook received the plans

5354and specifications enabling it to determine the quantities of

5363materials needed and the costs per unit for installing the

5373materials and performing the necessary work.

537941. Haycook had received subc ontractor bids in each of the

5390four areas that it later determined it would self - perform

5401(earthwork, structural steel, concrete, and masonry). Because

5408Haycook's "takeoffs," historical pricing information and recent

5415bid information from another Volusia Coun ty prototype school

5424indicated that it could self - perform the work at less cost than

5437using the bids of subcontractors in those four work areas,

5447Haycook elected to self - perform the work and listed itself as

5459the subcontractor in those four work areas. This w as not a case

5472where Haycook simply ran out of time to get subcontractors' bids

5483in those four work areas and therefore simply listed itself as

5494performing in the four work areas at issue due to time

5505expediency. It was also not because Haycook intended listi ng

5515itself as performing in the four subject work areas so that it

5527would create an opportunity to get lower bids from unknown

5537subcontractors after bid opening, in order to enhance its

5546profitability and support a low bid, in terms of putting enough

5557money in the job for itself.

556342. As general contractor for the entire project, Haycook

5572intended to provide general supervision of the entire project

5581including subcontractors. With respect to self - performed work,

5590Haycook intended to supply materials and component s and to

5600directly supervise and control the means, methods, and

5608procedures of the self - performed work with contract labor.

561843. Haycook's definition of "self - performance" for

5626earthwork involved Haycook's renting equipment, retaining

5632contract laborers to c lear the site, place the fill (paid by the

5645hour or by the yard), compact the fill, and grade the site.

5657Haycook directly supervises self - performed work and schedules

5666and manages it with Haycook's project manager and on - site

5677superintendent.

567844. The testim ony of Reed Hadley and Dennis Haycook on

5689behalf of Haycook established that Haycook had self - performed

5699earthwork on other projects in the same manner as described

5709above, satisfactorily for the owners. Specific project names

5717and other project information s howing earthwork self - performance

5727by Haycook was provided to the architect as referenced above.

5737Mr. Haycook established that Haycook had "self - performed"

5746earthwork on 50 to 60 percent of its projects in the past.

575845. Haycook's definition of self - perform ance of structural

5768steel included engaging a licensed fabricator, as required by

5777the bid specifications in this instance, hiring experienced

5785labor erection crews, purchasing the materials and component

5793parts, and directly supervising and managing the work, including

5802scheduling of the labor crews. Haycook had performed structural

5811steel on 10 to 15 percent of its past projects. Four examples

5823of projects, self - performed in structural steel, were provided

5833to the architect along with related detailed informati on.

584246. Haycook's self - performance of concrete work included

5851its purchasing of materials, hiring contract labor for footings,

5860paid by the lineal foot, and concrete slabs paid by the square

5872foot, and directly supervising, coordinating, and scheduling the

5880concrete work activities with Haycook's own project managers and

5889superintendent. Haycook has self - performed concrete work on

5898approximately 80 percent of its past projects. The architect

5907was provided a project listing of self - performed concrete work

5918and d etailed information showing Haycook's experience in this

5927area. Concrete work is the area of work most commonly self -

5939performed by general contractors in the construction market area

5948in and around Volusia County.

595347. Haycook's self - performance of masonr y includes

5962Haycook's purchasing of concrete blocks, and reinforcing steel

5970placed within the block, hiring labor on a unit price basis to

5982install it (as, for instance, paid by the block laid), directly

5993supervising the work, and coordinating and scheduling t he

6002masonry work activities with Haycook's project manager and

6010superintendent. Haycook has self - performed masonry on

6018approximately 70 percent of its past projects. The architect

6027was provided examples of projects listing self - performed masonry

6037work by Hayc ook, as well as detailed information depicting

6047Haycook's experience in this work area.

605348. Mr. Goodemote, as referenced above, is a local general

6063contractor with school board project experience and is Haycook's

6072expert witness. He established that it is common practice in

6082the construction industry in the Volusia County area for

6091contractors to self - perform work in the manner that Haycook had

6103self - performed it in the past and proposes to do on Elementary

6116School "X." He established with reference to the Boa rd's

6126definition of "subcontractor," which excludes "materialmen" and

"6133laborers," that a contractor's purchase of materials and the

6142hiring of contract labor to install the materials does not come

6153within the definition of "subcontractor" or "subcontracting."

6160He established that a subcontractor is the one who provides all

6171labor, material, equipment, and supervision necessary to

6178complete a work operation. "It's a total turnkey operation.

6187They provide everything to finish the work." Mr. Goodemote's

6196opinion e stablishes that "self - performance" of the subject work

6207includes a general contractor hiring contract labor to perform a

6217part of the work, because many times there are multiple vendors

6228associated with a portion of the work, and the contractor is

6239still direc ting and supervising the work and assuming all the

6250risks associated with the work. Mr. Goodemote himself has self -

6261performed as a general contractor and observed other contractors

6270self - perform earthwork, masonry, concrete work, and structural

6279steel work. He demonstrated that if a general contractor uses

6289contract labor to perform a portion of the work, it still

6300remains a "self - performance" by the general contractor, and that

6311the laborers do not have to be on the contractor's payroll in

6323order for the work to constitute self - performance, according to

6334the general practice and usage in the construction industry.

634349. When requested by the architect to provide examples of

6353past projects that it had self - performed in the four subject

6365work areas, Haycook listed fiv e projects as to earthwork; four

6376projects in structural steel; seven projects as to masonry; and

6386seven projects as to concrete. In consideration of his

6395restrictive view of what self - performance means (i.e. that self -

6407performance can only mean performance o f work by salaried

6417employees on the general contractor's own payroll), the

6425architect (evaluator) requested payroll records and workers'

6432compensation information on two projects only, the Goldsboro

6440Elementary School and Eustis Elementary School.

644650. The b id documents do not provide unbridled discretion

6456in the architect/evaluator, or in the school board, to define

6466self - performance in a manner not provided for or inconsistent

6477with the bid documents or to define "subcontractor," to include

6487contract labor and thus require the labor to be listed as a

6499subcontractor on the bid response. There was no notice to any

6510of the bidders that such a restrictive definition would be

6520employed, nor that a contractor listing itself as self -

6530performing, and therefore standing in same position as other

6539subcontractors as to the areas of work it would self - perform,

6551would be treated differently from other subcontractors by, in

6560effect, having to list such persons or entities as those

6570providing contract labor as "sub - subcontractors." T here was no

6581evidence that the architect was provided sole discretion to

6590verify self - performance experience as to the two projects only

6601and ignore verification information of self - performance as to

6611the other listed projects provided by Haycook.

661851. Althou gh the architect and the Board contended that

6628Haycook's listing of itself as self - performing in the four work

6640areas at issue might allow Haycook to "buy out" subcontractors

6650or to "bid shop," there was no evidence offered to substantiate

6661that this was Hayco ok's intent or that Haycook or any other

6673identified contractor in Volusia County or the surrounding area

6682had ever attempted to "buy out" subcontractors on Volusia County

6692school projects. Contrarily, Mr. Haycook testified that he does

6701not engage in a pract ice of "buying out" subcontractors after he

6713has obtained contracts with a winning bid. He explained, as

6723referenced above, that subcontractors and the business

6730relationships that he has with them are crucial to the success

6741of his business. If Haycook made a practice of engaging in such

6753inappropriate operational and pricing conduct when bidding for

6761projects, or entering into related contracts, then

6768subcontractors would either elect not give bids to Haycook at

6778all when Haycook was, in the future, attempting to formulate bid

6789responses, or would not give Haycook their lowest or best price

6800because of their knowledge of such a practice, if Haycook

6810engaged in it. This would obviously have an adverse effect on

6821Haycook's ability in the future to be successful in co mpetitive

6832bid procurements or projects.

683652. Haycook has self - performed in the manner intended as

6847to Elementary School "X" for years, as have his competitors.

6857Although the Board apparently feared that Haycook's listing

6865itself as self - performing in the areas of work in question gave

6878it a competitive advantage over other bidders, the evidence does

6888not bear out that fear. The competing bidders had the same

6899opportunity to look at their past cost knowledge and experience,

6909their knowledge of materialmen and suppliers in the area, their

6919knowledge of the labor market and available labor and other data

6930by which they might arrive at an independent evaluation of what

6941a particular area of the work should cost, as well as the

6953methods and means necessary to perform i t. They had the same

6965opportunity to evaluate any such knowledge base they have and

6975elect to self - perform one or more areas of the work, as did

6989Haycook. Since they had the same opportunity to do so, the

7000evidence does not show there is any competitive adva ntage gained

7011by Haycook in this situation which was not available to other

7022bidders as well.

702553. As addressed above, the architect's recommendation to

7033reject the Haycook bid was based upon his interpretation that

"7043self - performance" required all work to be accomplished by

7053employees on Haycook's payroll. Using that restrictive

7060definition, the architect concluded that Haycook did not

7068demonstrate, as to the Goldsboro and Eustis projects only, that

7078Haycook had self - performed work with its own employees in the

7090past and therefore that Haycook would self - perform with its own

7102employees on the project at issue. The architect concluded that

7112Haycook's subsequent engagement of contract labor in lieu of

7121using his own payroll employees "could potentially give D. J.

7131Hayc ook Construction Company an unfair advantage over the other

7141bidders." Neither the architect's testimony nor the Board's

7149other evidence explained, however, how that would give the

7158Petitioner an unfair advantage over other bidders who, as found

7168above, were free to engage in the same proposed self - performance

7180as Haycook. The evidence did not establish how it would harm

7191the public's strong interest in getting the best possible price

7201for a quality construction effort that was completed on time,

7211within the auth orized budget, and in accordance with all the

7222contractual terms. The architect's and Board's conclusion in

7230this regard is based upon incorrect and unreasonable

7238interpretations of what is meant by "subcontractor" and the

7247concept of "self - performance." The rationale for finding that

7257Haycook's putative self - performance would give Haycook an unfair

7267advantage, vis a vis, other bidders or would promote bid

7277shopping or buy - out of subcontractors has been shown by the

7289evidence to be based upon speculation and conj ecture.

729854. Haycook's bid response has been shown to be responsive

7308to the specifications as they were stated, published and

7317furnished to the bidders, including Haycook, in the bid

7326documents at issue. The definition of self - performance employed

7336by the a rchitect and the Board is not supported by the language

7349of the bid documents and has been shown by the preponderant,

7360most credible evidence of record to be an unreasonable

7369definition and manner of evaluating the bids and particularly

7378Haycook's bid. Haycoo k has been shown to be responsive to the

7390specifications and the relevant portions of the bidding

7398documents and to have the lowest bid by a significant amount,

7409some $241,000.00 dollars as to the base bids of Haycook versus

7421that of Clancy and Theys.

7426CONCLUSI ONS OF LAW

743055. The Division of Administrative Hearings has

7437jurisdiction of the subject matter of and the parties to this

7448proceeding. §§ 120.569, 120.57(1), Fla. Stat. (2003).

745556. Section 120.57(3)(f), Florida Statutes, provides

7461pertinently as follows:

7464. . . Unless otherwise provided by statute,

7472the burden of proof shall rest with the

7480party protesting the proposed agency action.

7486In a competitive - procurement protest, other

7493than a rejection of all bids, proposals, or

7501replies, the administrative law judge shall

7507conduct a de novo proceeding to determine

7514whether the agency proposed action is

7520contrary to the agency's governing statutes,

7526the agency's rules or policies, or the

7533solicitation specifications. The standard

7537of proof for such proceeding shall be

7544whet her the proposed agency action was

7551clearly erroneous, contrary to competition,

7556arbitrary, or capricious. . . .

7562Thus the Petitioner protestant must sustain its burden of proof

7572by preponderant evidence. Department of Transportation v.

7579J.W.C. Company, Inc. , 396 So. 2d 778, 787 (Fla. 1st DCA 1981);

7591State Contracting and Engineering Corp. v. Department of

7599Transportation , 709 So. 2d 607, 609, (Fla. 1998).

760757. The Petitioner must thus demonstrate that the agency's

7616proposed action is contrary to governing stat utes, the agency's

7626rules or polices, or the bid or proposal specifications. Put

7636another way, it must be determined whether the agency was in

7647error in applying a governing principle, as for instance, its

7657interpretation or application of bid specifications. In making

7665a determination on the above issue objective facts, historical

7674or present reality must be found. Objective facts are those

7684which would depict, for example, how a bidder has operated in

7695the past with regard to past projects and how it proposes to

7707operate and perform with regard to the specifications its bid

7717and the construction at issue. The determination of such

7726objective facts, which lead to a determination of whether the

7736bidder has complied with the relevant specifications, and, if

7745not, whet her its deviation is material or non - material, involves

7757a weighing of probative testimony and other evidence which is

7767conflicting to some degree and maybe hotly contested. This

7776factual determination is the province of the Administrative Law

7785Judge; to weig h and make determinations concerning the candor,

7795credibility, and creditability of the testimony and documentary

7803evidence, the relative competency of the witnesses, in terms of

7813their experience with the subject matter at issue, their

7822relative opportunity t o observe as to contested factual matters,

7832the internal logical consistency of their testimony and its

7841relative level of consistency with that of other witnesses as to

7852contested factual matters. Judgments must thus be made as to

7862credibility and the relati ve weight to be ascribed to the

7873testimony and evidence offered by each party as to the contested

7884factual matters. Such objective facts are thus susceptible to

7893proof by ordinary and conventional methods.

7899Because a bid protest is fundamentally a de

7907novo proceeding, it is concluded that the

7914agency is entitled to no deference in

7921connection with the resolution of disputes

7927involving objective facts. It is

7932exclusively the judge's job, as the trier of

7940fact, to ascertain from the competent

7946substantial evidence in the record what

7952actually happened in the past or what

7959reality presently exits, as if no decision

7966previously had been made.

7970See R.N. Expertise Inc., v. Miami - Dade County School Board and

7982Preventive Medical Testing Center, Inc., d/b/a Global MRO,

7990Inter venor , 2002 WL 185217 (Florida Division of Administrative

7999Hearings Case No. 01 - 2663BID, 2002).

800658. The purpose of competitive bidding is to secure the

8016lowest responsible offer. Minor irregularities in bids, vis a

8025vis, specifications can be waived, ef fectuating that purpose.

8034See Air Support Services International Inc., v. Metropolitan

8042Dade County , 614 So. 2d 583, 584 (Fla. 3rd DCA 1993); Tropabest

8054Foods, Inc., v. State of Florida, Department of General

8063Services , 493 So. 2d 50, 52 (Fla. 1st DCA 1986). Although a bid

8076containing a material variance from the specifications is not

8085acceptable, Glatstein v. City of Miami , 399 So. 2d 1005 (Fla.

80963rd DCA 1981), rev. denied , 407 So. 2d 1102 (Fla. 1981), not

8108every deviation from the invitation is material.

811559. The court in Robinson Electrical, Inc., v. Dade

8124County , infra ., stated:

8128In determining whether a specific non -

8135compliance constitutes a substantial and

8140hence a non - waivable irregularity, the

8147courts' have applied two criteria - first,

8154whether the effect of a waiver would be to

8163deprive the municipality of its assurance

8169that the contract will be entered into,

8176performed and guaranteed according to its

8182specified requirements, and second, whether

8187it is of such a nature that its waiver would

8197adversely affect compet itive bidding by

8203placing a bidder in a position of advantage

8211over other bidders or by otherwise

8217undermining the necessary common standard of

8223competition.

8224In application of the general principles

8230above discussed, sometimes it is said that a

8238bid may be re jected or disregarded if there

8247is a material variance between the bid and

8255the advertisement. A minor variance,

8260however, will not invalidate the bid. In

8267this context a variance is material if it

8275gives the bidder a substantial advantage

8281over the other bidd ers, and thereby

8288restricts or stifles competition.

8292See Robinson Electrical Company v. Dade County , 417 So. 2d 1032

8303(Fla. 3rd DCA 1982).

830760. In the case at hand the Respondent Board, in essence,

8318contends that the Petitioner's bid was not responsive t o the

8329specification. Although the specification at issue permits the

8337bidder, Haycook, to list itself as self - performing in lieu of

8349listing subcontractors for the areas of work in question, which

8359Haycook did, the Respondent contends that Haycook did not

8368es tablish to the satisfaction of the architect/evaluator and the

8378Board that it had self - performed on past projects or would do so

8392on this one, Elementary School "X." Therefore, the Board

8401believes that the Petitioner will actually use subcontractors

8409whose bi ds will be obtained after bid opening, supportive of its

8421lower bid price and thereby to obtain a competitive advantage

8431over other bidders; contending, in essence, that its claiming of

8441self - performance is a subterfuge.

844761. The architect/evaluator interp reted the self -

8455performance concept to mean that the bidder should do so only

8466with its own resources, meaning employees on its own payroll,

8476largely using as a measure whether Haycook had paid workers'

8486compensation coverage for those employees. The evaluato r

8494focused on only two past projects, the Goldsboro School job and

8505the Eustis Elementary School job out of all the information

8515purportedly probative of past self - performance furnished him by

8525Haycook in the information gathering - bid evaluations process, in

8535d eciding that Haycook did not have a record of self - performance.

8548Notably, however, the Board's witness concerning the Eustis

8556School project, Gary Parker, who is employed by the Lake County

8567School District, was not employed by the Lake County District

8577durin g that project and had no role in its development or

8589oversight. He testified that he had seen an entry in the

8600minutes of a meeting concerning that project in which the

8610architect had referenced Haycook's "masonry subcontractor." His

8617overall testimony on d irect and cross - examination shows,

8627however, that he had no direct personal knowledge of that

8637masonry work arrangement, the context in which the note was made

8648by the architect (who did not testify), and Parker could not

8659state definitively whether a masonry subcontractor relationship

8666existed with Haycook on that project or not.

867462. In any event, the preponderant weight of the credible,

8684most logical testimony and evidence shows, as found above, that

8694self - performance can include the use of contract labor, as was

8706done in part on those jobs. Moreover, there is no clear reason

8718or rationale for the architect/evaluator to essentially only

8726consider two of the Petitioner's past projects in arriving at

8736his conclusion that the Petitioner had not self - performed in the

8748past; extrapolating from that determination the decision that

8756Haycook would not really self - perform as to the subject project

8768and that therefore his bid in this regard was not responsive,

8779responsible, or bona fide, and instead was a subterfuge for

8789post - tab ulation "bid shopping."

879563. The architect/evaluator's decision (and therefore the

8802Board's) was based on his view that self - performance can only be

8815done with the contractor's own employees, salaried on its own

8825payroll, and for whom the contractor is payin g workers'

8835compensation coverage costs. That narrow interpretation is not

8843based upon or supported by statute, rule, or any persuasive

8853decisional law of which the undersigned has been made aware.

8863Moreover, it represents a departure from the bid specificat ion,

8873which does not contain it and does not even define self -

8885performance. Thus that interpretation of the term, as carried

8894out herein in determining that Haycook, in the Board's view, is

8905unresponsive and not a responsible bidder, in effect, given the

8915prep onderant evidence culminating in the above germane Findings

8924of Fact, does not accord with facts, logic, and reason and is

8936therefore arbitrary. See Agrico Chemical Company v. Department

8944of Environmental Regulation , 356 So. 2d 759, 763 (Fla. 1st DCA

89551978).

895664. This is especially so given the preponderant evidence,

8965supportive of the above related Findings of Fact, which shows

8975that, even if Haycook had not self - performed on past projects,

8987it is thoroughly capable from an operational, staff,

8995experiential, an d financial standpoint to do so on the present

9006project. There is no preponderant, persuasive evidence to show

9015that Haycook intends to do otherwise. The testimony as to the

9026Board's fear that anti - competitive activity such as bid shopping

9037or "buyout" of su bcontractors will occur does not rise above

9048speculation and conjecture.

905165. Moreover, the Board has a policy and practice, and is

9062authorized by the terms of the bid documents, to investigate

9072subcontractors listed by bidders to determine if they are

9081reput able and will likely do quality work. The Board can

9092require substitution of a subcontractor it believes is not

9101reliable. Once the inquiry is over, the Board does not look

9112further at how the subcontractor performs, leaving that to the

9122supervision of the g eneral contractor. The subcontractor is

9131free to "sub - subcontract" out parts of its work, as is commonly

9144done, without objection or inquiry under the Board's practice.

9153The general contractor, however, when listing itself, in effect,

9162as a subcontractor on its bid, because, as here, it is self -

9175performing, would be precluded from "sub - subbing" out part of

9186the work to a sub - subcontractor. This is because of the Board's

9199interpretation of the concept of self - performance to mean that

9210it can only be done by salar ied employees actually on the

9222general contractor's payroll. The Board does not require that

9231stricture of others who are in the posture of subcontractors and

9242are not the general contractor. Thus, in effect, the Board

9252would require the listing as a subcont ractor of each entity

9263providing any portion of the work to the general contractor who

9274is not such a salaried employee of the general contractor, while

9285not applying this standard to listed subcontractors. This

9293unequal application of the Board's interpretat ion of self -

9303performance is, in itself, also not supported by the terms of

9314the specification nor the above found facts. It is illogical

9324under the circumstances and therefore arbitrary.

933066. The preponderant, credible testimony and evidence

9337shows that se lf - performance by a contractor may be accomplished

9349by the purchase of materials and employing, directing, and

9358supervising labor in performing the work. Self - performance does

9368not mean that a bidder or contractor must only perform with

9379persons or employees on its own payroll, so long as the bidder

9391controls the means of performance, as well as the results. This

9402is the manner of self - performance proposed by Haycook. It would

9414still supervise and direct even contract labor (not employing

9423supervision by some in tervening subcontractor).

942967. Employees can be such without actually being on the

9439contractor's salaried payroll. Webster's Dictionary defines

"9445employee" as a person who works for another in exchange for

9456financial compensation. Thus compensation can be accomplished

9463by paying by the hour, by the lineal foot, the square foot, or

9476by the piece. Black's Law Dictionary defines employee as:

9485A person in the service of another under any

9494contract for hire, express or implied, oral

9501or written, where the employe r has the power

9510or right to control or direct the employee

9518in the material details of how the work is

9527to be performed. . . .

9533Generally, when a person for whom services

9540are performed has the right to control and

9548direct individual who performs services not

9554only as to result to be accomplished by work

9563but also as to details and means by which

9572result is accomplished, individual subject

9577to direction is an 'employee.'

958268. In summary, the Petitioner was shown by the

9591preponderant evidence and above found facts to have complied

9600with the bid specifications which allow it to propose self -

9611performance of the work areas in question. The facts found show

9622that it intends to and will self - perform in a manner responsive

9635to the bid specification and that its operational capability,

9644experience, and past record of performing similar projects with

9653quality work, within budget and on time, will conform to the

9664Board's and public's interest in having such performance at the

9674lowest possible price. It has thus established its bid to be

9685responsive.

968669. Even assuming, arguendo , that Haycook was less than

9695fully responsive to the specification, in terms of how it

9705proposed to self - perform, the preponderant, direct, and

9714circumstantial evidence and the above facts do not show any

9724de viation to be material. The courts do not favor the

9735disqualification of a low bidder for non - responsiveness where a

9746bid irregularity does not impart an unfair competitive advantage

9755to the low bidder. In the case of Intercontinental Properties

9765v. DHRS , 60 6 So. 2d 380 (Fla. 3rd DCA 1992) the court, in

9779reversing a hearing officer's finding of unresponsiveness on the

9788part of a bidder, discussed at length the well - known case of

9801Liberty County v. Baxter's Asphalt and Concrete Inc. , 421 So. 2d

9812505 (Fla. 1982) co ncerning principles applicable to competitive

9821bidding. The Intercontinental court enunciated the principle

9828from the Baxter's opinion that:

9833A minor irregularity is a variation from the

9841bid invitation or proposal terms and

9847conditions which does not affect t he price

9855of the bid, or give the bidder an advantage

9864or benefit not enjoyed by other bidders, or

9872does not adversely impact the interest of

9879the department. . . .

9884There is a very strong public interest in

9892favor of saving tax dollars in awarding

9899public contr acts. There is no public

9906interest, much less a substantial public

9912interest, in disqualifying low bidders for

9918technical deficiencies in form, where the

9924low bidder did not derive any unfair

9931competitive advantage by reason of the

9937technical omission. . . .

9942I n either event, there is a strong public

9951policy in favor of awarding contracts to the

9959low bidder, and an equal strong public

9966policy against disqualifying the low bidder

9972for technical deficiencies which do not

9978confer an economic advantage on one bidder

9985over another. Id. at 387. (Emphasis

9991supplied).

9992See also ESP Security and Satellite Engineering, Inc., v.

10001University of Florida, Physical Plant Division,

10007Architecture/Engineering Department , (Case No. 94 - 2035BID,

10014Division of Administrative Hearings, April 12 , 1995).

1002170. In the case at hand the Petitioner was the low bidder

10033by the substantial amount of approximately $241,000.00 on the

10043base bid. Its preponderant evidence shows it has in the past

10054and will on this school project intend to and perform in a way

10067that will result in quality work, accomplished on time and

10077within budget. Such has been its record in the projects in the

10089past, evidence of which is in the record of this proceeding.

10100The Board will be able to enforce the price and terms of the

10113Petitioner 's bid through the terms of the resulting contract.

10123Therefore there is no irregularity in responsiveness which would

10132adversely impact the interest of the Board and the taxpayers.

10142The Petitioner did not derive any unfair competitive advantage

10151over the oth er two original and higher bidders, because, under

10162the specifications they were all free to consider their

10171experience on similar projects, any data base of costs,

10180suppliers, and labor identity information and to also propose

10189self - performance in the subject work areas or in others, if they

10202so chose.

1020471. Accordingly, in consideration of the preponderant,

10211credible evidence underlying the above - found facts, and in view

10222of the above discussion and conclusions, it is determined that

10232Haycook's bid is responsiv e, responsible, and the lowest bid.

10242It has been demonstrated that the Respondent's bid evaluation

10251and intended award is factually and legally flawed. Therefore,

10260under the circumstances found and concluded above, the failure

10269to award the subject contract to Haycook would be arbitrary,

10279contrary to competition, and clearly erroneous. § 120.57(3)(f),

10287Fla. Stat. (2003).

1029072. Finally, the Petitioner asserts that if an agency

10299action determines the substantial interest of a party based upon

10309an un - adopted rule, then the agency action shall not be presumed

10322valid or invalid, but the agency must prove that the un - adopted

10335rule meets the standards enunciated in Section 120.57(1)(e),

10343Florida Statutes. The Petitioner asserts that the definition of

"10352self - performance" is not contained in the bid documents or any

10364written rules of the school board. The Petitioner asserts that

10374Ms. Drago testified that the interpretation at issue is based on

10385the Board's practice, which is not in writing. It asserts then

10396that this interpreta tion by the Board's staff architect and the

10407Board itself is an un - adopted rule which the Board must "prove -

10421up" in the manner envisioned in the above statute. The evidence

10432in this case however, does not clearly demonstrate that the

10442interpretation of the sp ecification as to "self - performance,"

10452clearly meets the definition of a rule embodied in Section

10462120.52, Florida Statutes, (2003). Moreover, to the extent that

10471the challenge to the interpretation of the specification as an

10481unpromulgated rule might be deem ed to be an attack on the

10493specifications in the bid documents, clearly the 72 hour period,

10503during which an attack on the specifications in an invitation to

10514bid or request for proposals can be mounted, long since elapsed

10525before the bids or offers were submi tted and thus is not timely.

10538§120.57(3)(b), Fla. Stat.

10541RECOMMENDATION

10542Having considered the foregoing Findings of Fact,

10549Conclusions of Law, the evidence of record, the candor and

10559demeanor of the witnesses, and the pleadings and arguments of

10569the parties, it is, therefore,

10574RECOMMENDED that a final order be entered by the School

10584Board of Volusia County awarding the contract for Elementary

10593School "X" to the Petitioner, D. J. Haycook Construction

10602Company, Inc.

10604DONE AND ENTERED this 8th day of March, 20 04, in

10615Tallahassee, Leon County, Florida.

10619S

10620___________________________________

10621P. MICHAEL RUFF

10624Administrative Law Judge

10627Division of Administrative Hearings

10631The DeSoto Building

106341230 Apalachee Parkway

10637Tallahassee, Florida 3 2399 - 3060

10643(850) 488 - 9675 SUNCOM 278 - 9675

10651Fax Filing (850) 921 - 6847

10657www.doah.state.fl.us

10658Filed with Clerk of the

10663Division of Administrative Hearings

10667this 8th day of March, 2004.

10673COPIES FURNISHED :

10676S. LaRue Williams, Esq uire

10681Kinsey, Vincent, Pyle, L.C.

10685150 South Palmetto Avenue, Box A

10691Daytona Beach, Florida 32114

10695Theodore R. Doran, Esquire

10699Michael G. Dyer, Esquire

10703Doran, Wolfe, Rost & Ansay

10708444 Seabreeze Boulevard, Suite 800

10713Post Office Drawer 15110

10717Daytona Beach, Flor ida 32115

10722William E. Hall

10725Superintendent

10726Volusia County School Board

10730Post Office Box 2118

10734Deland, Florida 32721 - 2118

10739NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

10745All parties have the right to submit written exceptions within

1075510 days from the date of thi s Recommended Order. Any exceptions

10767to this Recommended Order should be filed with the agency that

10778will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 04/08/2004
Proceedings: Final Order filed.
PDF:
Date: 04/06/2004
Proceedings: Agency Final Order
PDF:
Date: 03/22/2004
Proceedings: Respondent`s Exceptions to Recommended Order filed.
PDF:
Date: 03/08/2004
Proceedings: Recommended Order
PDF:
Date: 03/08/2004
Proceedings: Recommended Order (hearing held December 11-12, 2003). CASE CLOSED.
PDF:
Date: 03/08/2004
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 01/02/2004
Proceedings: Letter to Judge Ruff from T. Doran enclosing a disk in word format with the Proposed Recommended Order filed.
PDF:
Date: 12/31/2003
Proceedings: (Proposed) Recommended Order filed by Respondent.
PDF:
Date: 12/29/2003
Proceedings: (Proposed) Recommended Order (filed by Petitioner via facsimile).
PDF:
Date: 12/26/2003
Proceedings: Respondent`s Exhibits filed.
PDF:
Date: 12/26/2003
Proceedings: Petitioner`s Exhibits filed.
Date: 12/26/2003
Proceedings: Transcript of Proceedings (4 Volumes) filed.
PDF:
Date: 12/26/2003
Proceedings: Notice of Filing Transcript of Proceedings Hearing before the Honorable P. Michael Ruff Taken December 11, 2003 filed.
Date: 12/11/2003
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 12/10/2003
Proceedings: Petitioner`s Motion to Strike Expert Witness (filed via facsimile).
PDF:
Date: 12/10/2003
Proceedings: Notice of Hearing (filed by Petitioner via facsimile).
PDF:
Date: 12/09/2003
Proceedings: Joint Pre-Hearing Statement filed.
PDF:
Date: 12/08/2003
Proceedings: Joint Pre-hearing Statement (filed via facsimile).
Date: 12/08/2003
Proceedings: Transcript filed.
PDF:
Date: 12/08/2003
Proceedings: Notice of Filing Transcript of Portion of Meeting of the School Board of Volusia County, Florida Held October 14, 2003 filed by Respondent.
PDF:
Date: 12/08/2003
Proceedings: School Board`s Memorandum of Law in Support of Proposed Award Contract filed.
PDF:
Date: 11/04/2003
Proceedings: Notice of Hearing (hearing set for December 11 and 12, 2003; 10:00 a.m.; Deland, FL).
PDF:
Date: 10/28/2003
Proceedings: Bid Tabulation filed.
PDF:
Date: 10/28/2003
Proceedings: Formal Written Protest filed.
PDF:
Date: 10/28/2003
Proceedings: Referral Letter filed.

Case Information

Judge:
P. MICHAEL RUFF
Date Filed:
10/28/2003
Date Assignment:
10/28/2003
Last Docket Entry:
04/08/2004
Location:
Deland, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (4):