03-001581BID E - Builder vs. Miami-Dade County School Board
 Status: Closed
Recommended Order on Friday, October 10, 2003.


View Dockets  
Summary: Petitioner failed to establish that Respondent`s preliminary decision to award a public contract was contrary to a governing statute, rule, policy, or project specification. Recommended that bid protest be rejected.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8E - BUILDER, )

12)

13Petitioner, )

15)

16vs. ) Case No. 03 - 1581BID

23)

24MIAMI - DADE COUNTY SCHOOL BOARD, )

31)

32Respondent, )

34)

35and )

37)

38EMERGING SOLUTIONS d/b/a )

42CONSTRUCTWARE, INC., )

45)

46Intervenor. )

48)

49RECOMMENDED ORDER

51This case came before Administrative Law Judge John G.

60Van Laningham for final hearing on June 17 and 18, 2003, in

72Miami, Florida.

74APPEARANCES

75For Petitioner: Aaron R. Resnick, Esquir e

82Gunster, Yoakley & Stewart, P.A.

87One Biscayne Tower, Suite 3400

922 South Biscayne Boulevard

96Miami, Florida 33131

99For Respondent: Luis M. Garcia, Esquire

105Miami - Dade County School Board

1111450 Northeast 2nd Avenue, Suite 400

117Miami, Florida 33132

120For Intervenor: Mitchell A. Bierman, Esquire

126Weiss, Serota, Helfman, Pastoriza

130& Guedes, P.A.

1332665 South Bayshore Drive, Suite 420

139Miami, Florida 33133

142STATEMENT OF THE ISSUES

146The issues in this bid protest are whether, in making a

157preliminary decision to award a public contract, Respondent

165acted contrary to a governing statute, rule, policy, or project

175specification; and, if so, for each such instance, whether th e

186misstep was clearly erroneous, arbitrary or capricious, or

194contrary to competition.

197PRELIMINARY STATEMENT

199Petitioner E - Builder, Inc. (“E - Builder”) has challenged a

210selection committee’s recommendation to Respondent Miami - Dade

218County School Board (the “B oard”) that a contract be awarded to

230Intervenor Emerging Solutions d/b/a Constructware, Inc.

236(“Constructware”). The subject contract is for internet - based

245collaborative construction and claims reduction support

251services, which will facilitate the administ ration of the

260ongoing capital construction program in the Miami - Dade County

270Public School District (the “District”).

275Six vendors submitted proposals in response to Request for

284Proposals No. 026 - CC10, which had been issued in the autumn of

2972002. A selection committee reviewed the proposals and, in

306December 2002, voted to recommend that the contract be awarded

316to Constructware. E - Builder protested, the Board referred the

326matter to the Division of Administrative Hearings (“DOAH”),

334Constructware was allowed to intervene, and the undersigned

342scheduled a final hearing, which took place on June 17 and 18,

3542003.

355At the final hearing, E - Builder presented Jonathan Antevy,

365one of its principals, together with four witnesses who were, at

376the time, employ ees of the District, namely Rose Barefield Cox,

387John Pennington, Barbara Jones, and Laurence White. E - Builder

397also offered 15 exhibits (Petitioner’s Exhibits 4, 25 - 27, 30,

40840, 49, 55, 56, 132, 133, and 143 - 46), which were received into

422evidence.

423By agre ement of the parties, the Board and Constructware

433conducted direct examinations, as desired, of the witnesses

441called during E - Builder’s case. As well, exhibits numbered 2 - 12

454were admitted as Respondent’s Exhibits, and official recognition

462was taken of Sch ool Board Rule 6Gx13 - 8C - 1.064 , which was marked

477for identification as Respondent’s Exhibit 1.

483T he final hearing transcript was filed with DOAH on

493September 8, 2003, and the parties timely filed their respective

503Proposed Recommended Orders before the e stablished deadline,

511which was September 26, 2003.

516Unless otherwise indicated, citations to the Florida

523Statutes refer to the 2003 Florida Statutes.

530FINDINGS OF FACT

533I. The Request for Proposals

5381. In the fall of 2002, the Board issued Request for

549Pro posals No. 026 - CC10 (the “RFP”) to solicit offers on a

562contract for internet - based collaborative construction and

570claims reduction support services.

5742. As stated in Section II at page 1, the purpose of the

587RFP was

589[t]o commission one or more firms to provide

597the Board with internet - based collaborative

604construction and claims reduction support

609services. It is intended that this

615technology be gradually phased into the

621construction program as new projects from

627the District’s Capital Construction Five -

633ye ar Work Plan come online. Miami - Dade

642County Public Schools is the fourth largest

649public school system in the nation and has a

658large - scale on - going capital construction

666program.

667The deadline for submission of proposals in response to the RFP

678was Novembe r 26, 2002.

6833. Section V of the RFP, which was titled “Required

693Information to be Submitted by Proposers,” prefaced a list of

704ten specific items with the instruction that “[a]ll proposals

713shall contain the following information and shall be presented

722i n the following format[.]” There is no dispute that material

733compliance with Section V was mandatory and that proposals could

743be —— and in fact were —— disqualified from consideration for

754failure to include all of the required information.

7624. Section VI of the RFP set forth the scope of work. It

775provided, in pertinent part:

779The proposer(s) shall provide Internet

784collaborative construction and claims

788reduction support services for use in

794connection with the [Board]’s capital

799construction program which should include

804but not be limited to, the following:

811A. The proposer should provide an off -

819the - shelf application product and

825application service provider services on a

831purely web - based system. Users will access

839and interface with the application via the

846inter net using Internet Explorer TM browser

853software running on computer workstations

858under typical Windows TM operating system.

864Users should not have to purchase or have

872installed on their workstations any other

878applications in order to use the application

885serv ice provider's application. The

890application service provider should host all

896applications and data and own and/or own the

904lease to their facility as well as all

912hardware and software. The application

917should include but not limited to the

924following:

925* * *

9289. Custom web site documents folders

934and subfolders creation and organization and

940the ability to submit multiple documents or

947files (select, drag and drop) to the project

955web site electronically from authorized

960computer workstations. Project folders

964should be capable of storing, including but

971not limited to, all plans, drawings,

977specifications, contracts, general

980conditions, surveys, geo - technical

985photographs, reports and other documents

990typically encountered in a multiple - large -

998project const ruction program.

1002* * *

100511. Ability to submit documents to

1011specific web site documents folders or

1017attach them to specific forms using

1023facsimile machines to allow non - computer

1030users to interface with the system. Ability

1037to electronically print documents directly

1042to web site documents folders from other

1049Windows TM applications. Ability to download

1055documents from the project site and to

1062resubmit them as new versions with all

1069original maintained and accessible.

1073* * *

1076C. Furnish and insta ll a zoom/tilt/pan

1083web - camera and connect to a high speed

1092Internet connection at each construction

1097site. Proposers should provide web camera

1103server equipment and ISP services necessary

1109to support web camera functions such as

1116automatic multiple daily view picture

1121taking, picture archival and retrieval and

1127time lapse playback of pictures.

11325. Section VII of the RFP, which prescribed various

1141“submittal requirements,” stated in relevant part:

1148Proposers shall indicate in their submittal,

1154the capabilities of t heir system regarding

1161the above scope of work, as well as the

1170following:

1171A. Initial set - up process, list Licenses

1179requirements, state the software and

1184hardware requirements for M - DCPS in order to

1193use the web - based system (i.e. browser plug -

1203ins, operating systems, etc).

1207* * *

1210E. Describe the training program to train

1217M - DCPS in use of the web - based system, on

1229site, number of classes, number of students

1236and hours of training proposed.

1241* * *

1244G. Describe travel distance from technical

1250sup port to M - DCPS. Provide technical

1258support in person at M - DCPS when required.

1267II. The Evaluation

12706. On December 9, 2002, a group of individuals who had

1281been appointed to serve on a committee (the “Evaluation

1290Committee”) whose task was to make a recomme ndation to the Board

1302as to whom should be awarded the contract met to review the six

1315proposals that were timely submitted in response to the RFP.

1325The Evaluation Committee unanimously agreed that the proposals

1333submitted by E - Builder, Constructware, and ano ther vendor were

1344responsive to the requirements of Sections V, VI, and VII; the

1355other proposers were eliminated from further consideration. The

1363Evaluation Committee decided to invite the three remaining

1371contenders to make presentations to the Evaluation C ommittee at

1381a later date.

13847. The Evaluation Committee met again on December 16,

13932002. At that time, the three proposers still in the

1403competition were allowed one hour apiece to demonstrate,

1411explain, and answer questions about their respective solutions.

1419After the presentations, the Evaluation Committee voted for the

1428proposal which best met the needs of the District. When the

1439votes were tallied, Constructware was the winner, with E - Builder

1450in second place. Accordingly, the Evaluation Committee agreed

1458t o recommend that the contract be awarded to Constructware.

1468III. Relevant Details About Constructware’s Proposal

14748. Because the instant protest is based largely on E -

1485Builder’s contention that Constructware’s proposal was

1491materially nonresponsive to severa l provisions in Sections VI

1500and VII of the RFP, the following is a brief look at the

1513relevant aspects of Constructware’s response to the RFP.

15219. In its proposal, Constructware addressed the items

1529contained in Section VI by interlining specific responses within

1538the relevant language of the RFP, which language was reproduced

1548in its entirety. For present purposes, given the reasons for

1558the recommended disposition that follows, it is not necessary to

1568quote Constructware’s responses to Section VI, which are

1576i ncluded in the evidentiary record in any event. Suffice it to

1588say that Constructware’s proposal was complete in the sense that

1598for each item listed in Section VI, Constructware provided a

1608response, offered a solution, or explained what it could do if

1619awar ded the contract.

162310. Turning to Section VII, Constructware’s proposal

1630stated in pertinent part as follows:

1636[With reference to Section VII.A.,]

1642Constructware is a true [Application Service

1648Provider] requiring only a web - browser and a

1657connection to the Internet. The System can

1664function on a 56K connection, but faster

1671bandwidth is recommended for maximum

1676performance.

1677* * *

1680[With reference to Section VII.E.,]

1686Constructware has established a team of

1692individuals specifically geared to train and

1698implement the application to M - DCPS’ unique

1706needs. The Solution Group is made up of

1714professional Implementation Managers and

1718Certified Constructware Trainers. In most

1723cases, the Implementation Manager will meet

1729with your executive team to understand the

1736scope of the program / project(s) and the

1744desired goal of using the application. With

1751this information and direct feedback from

1757your team, the Implementation Manager will

1763develop a scope document to help guide the

1771team through this rollout. This informat ion

1778will be shared with the Certified

1784Constructware Trainers to develop a custom

1790training plan to meet your goals.

1796Throughout the rollout, the Implementation

1801Managers will stay in contact with your

1808executive team to provide status and update

1815the rollout p lan as the project progresses.

1823The following is a list of the standard

1831training and implementation options

1835available:

18361) Private Training – ½ day to 5 day

1845per student depending on the amount of the

1853product utilized and the type of user

1860trained. Class s izes for private training

1867are limited to 12 students.

18722) Train the Trainer – 5 day course

1880designed to train in - house individuals to

1888act as your personal certified trainer.

18943) Public Training – 3 - day course in

1903our Atlanta Headquarters covering the

1908ma jority of the modules available.

19144) Implementation Services

19175) Orientation – Offered as part of

1924the initial database setup, this orientation

1930would assist your Constructware Supervisor

1935on how to get started with the system. This

1944orientation is done r emotely utilizing Webex

1951technology.

1952* * *

1955[With reference to Section VII.G.,]

1961[b]ecause Constructware is an Internet - based

1968application, technical support staffs have

1973not been required to travel to a client’s

1981site to resolve issues. Constructwa re

1987utilizes the Webex technology to review user

1994browser settings in the event a user has any

2003problems accessing the product. Clients

2008wanting a true web - based system should

2016exercise caution dealing with vendors

2021offering on site technical support. This is

2028a prime indicator of workstation setups and

2035additional software loads not required on

2041true web - based solutions.

2046Constructware’s Solutions Group offers

2050consultant visits to ensure proper

2055connectivity and browser settings in the

2061event clients lack the tec hnical staff that

2069would normally handle these procedures.

2074Constructware is headquartered near Atlanta,

2079Georgia. All support staff and consultants

2085are based in this office, but are accustom

2093[ sic ] to traveling to client sites

2101throughout the nation when req uired.

2107IV. E - Builder’s Protest

211211. By letter dated December 18, 2002, E - Builder was told

2124that it would not be awarded the contract. The letter, however,

2135did not notify E - Builder, as it should have pursuant to Section

2148120.57(3)(a), Florida Statutes, that failure to file a formal

2157protest within the time prescribed in Section 120.57(3) would

2166constitute a waiver of proceedings under the Administrative

2174Procedure Act (“APA”).

217712. To better understand what happened next, it is useful

2187to know that the RFP, at page iii, set up an informal protest

2200procedure as a nonexlusive alternative to formal administrative

2208proceedings under the APA. According to this informal

2216procedure,

2217[p]roposers may file letters of protest no

2224later than 48 hours prior to the Board

2232Mee ting for which the award is scheduled to

2241be made. These letters of protest will be

2249reviewed by Staff. Staff will offer the

2256protesting proposer the opportunity for a

2262meeting to discuss the protest. If the

2269proposer is not satisfied with the response

2276to th e protest, he/she may request to

2284address the School Board.

2288On January 13, 2003, E - Builder submitted an “Official Letter of

2300Protest” that was timely under the above quoted provisions

2309because the Board was scheduled to make the award at its meeting

2321on Janua ry 15, 2003. As a result of E - Builder’s informal

2334protest, the item relating to the contract in question was

2344removed from the Board’s agenda for January 15.

235213. By letter dated February 10, 2003, E - Builder was

2363informed that the Board’s staff had decided that the informal

2373protest was without merit and that E - Builder had “failed to

2385demonstrate violation of any established procedures or

2392misconduct on the part of the evaluation committee.” E - Builder

2403was further notified that it could “request to address the

2413school board [at its next meeting on February 12, 2003, when the

2425award was expected to be made], or invoke the provisions of §

2437120.569 Florida Statutes.”

244014. On February 12, 2003, within 72 hours after receiving

2450the letter just discussed, E - Builder del ivered to the Board a

2463letter styled “Supplement to Official Letter of Protest.” In

2472this supplemental protest letter, E - Builder reiterated its

2481desire to protest the intended award and expressed its intent to

2492address the Board later that day. While there i s room for

2504debate, the undersigned finds and concludes that E - Builder’s

2514correspondence of February 12, 2003, constituted a “notice of

2523protest” which was effective to commence the formal bid protest

2533process pursuant to Section 120.57(3)(b), Florida Statutes .

254115. At its meeting on February 12, 2003, the Board heard

2552from E - Builder concerning the pending protest, and following

2562that the recommendation to award Constructware the contract was

2571tabled. (As of the date of the final hearing, the Board had

2583taken no further action toward awarding the contract.)

259116. On February 20, 2003, E - Builder filed with the Board a

2604“Petition of Committee Recommendation Regarding Request for

2611Proposal No.: 026 - CC10 and for Formal Administrative Hearing.”

2621The undersigned finds and concludes that this petition

2629constituted a timely filed “formal written protest” as that term

2639is used in Section 120.57(3)(b), Florida Statutes; as such, the

2649February 20, 2003, petition is the operative pleading in this

2659case.

266017. As bases for relief, E - Builder asserted in its

2671petition, among other things, that Constructware’s proposal was

2679materially nonresponsive for failure to comply with several of

2688the RFP’s allegedly mandatory requirements. E - Builder also

2697alleged that the Evaluation Committee had fai led to take into

2708account total annual cost when weighing the merits of the

2718respective proposals. 1

2721CONCLUSIONS OF LAW

2724V. Jurisdiction

272618. The Division of Administrative Hearings has personal

2734and subject matter jurisdiction in this proceeding pursuant to

2743S ections 120.569 and 120.57(1), Florida Statutes, and the

2752parties have standing.

2755VI. The Burden of Proof

276019. Pursuant to Section 120.57(3)(f), Florida Statutes,

2767the burden of proof rests with the party opposing the proposed

2778agency action, here E - Builder. See State Contracting and

2788Engineering Corp. v. Department of Transp. , 709 So. 2d 607, 609

2799(Fla. 1st DCA 1998). E - Builder must sustain its burden of proof

2812by a preponderance of the evidence. Florida Dept. of Transp. v.

2823J.W.C. Co., Inc ., 396 So. 2d 778, 7 87 (Fla. 1st DCA 1981).

2837VII. The Rules of Decision in Bid Protests

2845A. The Standard of Conduct

285020. Section 120.57(3)(f), Florida Statutes, spells out the

2858rules of decision applicable in bid protests. In pertinent

2867part, the statute provides:

2871In a compet itive - procurement protest, other

2879than a rejection of all bids, the

2886administrative law judge shall conduct a de

2893novo proceeding to determine whether the

2899agency's proposed action is contrary to the

2906agency's governing statutes, the agency's

2911rules or policies, or the bid or proposal

2919specifications. The standard of proof for

2925such proceedings shall be whether the

2931proposed agency action was clearly

2936erroneous, contrary to competition,

2940arbitrary, or capricious.

294321. The First District Court of Appeal has construe d the

2954term “de novo proceeding,” as used in Section 120.57(3)(f),

2964Florida Statutes, to “describe a form of intra - agency review.[ 2 ]

2977The judge may receive evidence, as with any formal hearing under

2988section 120.57(1), but the object of the proceeding is to

2998e valuate the action taken by the agency.” State Contracting and

3009Engineering Corp. v. Department of Transp. , 709 So. 2d 607, 609

3020(Fla. 1st DCA 1998). In this, the court followed its earlier

3031Intercontinental Properties, Inc. v. State Dept. of Health and

3040Reh abilitative Services , 606 So. 2d 380, 386 (Fla. 1st DCA

30511992), a decision which predates the present version of the bid

3062protest statute, wherein the court had reasoned:

3069Although the hearing before the hearing

3075officer was a de novo proceeding, that

3082simply m eans that there was an evidentiary

3090hearing during which each party had a full

3098and fair opportunity to develop an

3104evidentiary record for administrative review

3109purposes. It does not mean, as the hearing

3117officer apparently thought, that the hearing

3123officer s its as a substitute for the

3131Department and makes a determination whether

3137to award the bid de novo. Instead, the

3145hearing officer sits in a review capacity,

3152and must determine whether the bid review

3159criteria set . . . have been satisfied.

316722. In framing t he ultimate issue to be decided in this de

3180novo proceeding as being “whether the agency’s proposed action

3189is contrary to the agency’s governing statutes, the agency’s

3198rules or policies, or the bid or proposal specifications,” the

3209statute effectively establ ishes a standard of conduct for the

3219agency, which is that, in soliciting and accepting bids or

3229proposals, the agency must obey its governing statutes, rules,

3238and the project specifications. If the agency breaches this

3247standard of conduct, its proposed act ion is subject to

3257(recommended) reversal by the administrative law judge in a

3266protest proceeding.

326823. Consequently, the party protesting the intended award

3276must identify and prove, by the greater weight of the evidence,

3287a specific instance or instances w here the agency’s conduct in

3298taking its proposed action was either:

3304(a) contrary to the agency’s governing statutes;

3311(b) contrary to the agency’s rules or policies; or

3320(c) contrary to the bid or proposal specifications.

332824. It is not sufficient, however, for the protester to

3338prove merely that the agency violated the general standard of

3348conduct. By virtue of the applicable standards of “proof,”

3358which are best understood as standards of review, 3 the protester

3369additionally must establish that the ag ency’s misstep was:

3378(a) clearly erroneous;

3381(b) contrary to competition; or

3386(c) an abuse of discretion.

339125. The three review standards mentioned in the preceding

3400paragraph are markedly different from one another. The abuse of

3410discretion standard, for example, is more deferential (or

3418narrower) than the clearly erroneous standard. The bid protest

3427review process thus necessarily entails a decision or decisions

3436regarding which of the several standards of review to use in

3447evaluating a particular action . To do this requires that the

3458meaning and applicability of each standard be carefully

3466considered.

3467B. The Standards of Review

34721. The Clearly Erroneous Standard

347726. The clearly erroneous standard is generally applied in

3486reviewing a lower tribunal’s f indings of fact. In Anderson v.

3497City of Bessemer City, N.C. , 470 U.S. 564, 573 - 74 (1985), the

3510United States Supreme Court expounded on the meaning of the

3520phrase “clearly erroneous,” explaining:

3525Although the meaning of the phrase "clearly

3532erroneous" is not immediately apparent,

3537certain general principles governing the

3542exercise of the appellate court's power to

3549overturn findings of a [trial] court may be

3557derived from our cases. The foremost of

3564these principles . . . is that "[a] finding

3573is 'clearly erroneou s' when although there

3580is evidence to support it, the reviewing

3587court on the entire evidence is left with

3595the definite and firm conviction that a

3602mistake has been committed ." . . . . This

3612standard plainly does not entitle a

3618reviewing court to reverse the finding of

3625the trier of fact simply because it is

3633convinced that it would have decided the

3640case differently. The reviewing court

3645oversteps the bounds of its duty . . . if it

3656undertakes to duplicate the role of the

3663lower court. "In applying the clearly

3669e rroneous standard to the findings of a

3677[trial] court sitting without a jury,

3683appellate courts must constantly have in

3689mind that their function is not to decide

3697factual issues de novo. " . . . . If the

3707[trial] court's account of the evidence is

3714plausible in light of the record viewed in

3722its entirety, the court of appeals may not

3730reverse it even though convinced that had it

3738been sitting as the trier of fact, it would

3747have weighed the evidence differently. Where

3753there are two permissible views of the

3760evidenc e, the factfinder's choice between

3766them cannot be clearly erroneous. . . . .

3775(Citations omitted)(emphasis added).

377827. The Florida Supreme Court has used somewhat different

3787language to give this standard essentially the same meaning:

3796A finding of fac t by the trial court in a

3807non - jury case will not be set aside on

3817review unless there is no substantial

3823evidence to sustain it, unless it is clearly

3831against the weight of the evidence, or

3838unless it was induced by an erroneous view

3846of the law. A finding whi ch rests on

3855conclusions drawn from undisputed evidence,

3860rather than on conflicts in the testimony,

3867does not carry with it the same

3874conclusiveness as a finding resting on

3880probative disputed facts, but is rather in

3887the nature of a legal conclusion. . . . .

3897When the appellate court is convinced that

3904an express or inferential finding of the

3911trial court is without support of any

3918substantial evidence, is clearly against the

3924weight of the evidence or that the trial

3932court has misapplied the law to the

3939established facts, then the decision is

3945'clearly erroneous' and the appellate court

3951will reverse because the trial court has

3958'failed to give legal effect to the

3965evidence' in its entirety.

3969Holland v. Gross , 89 So. 2d 255, 258 (Fla. 1956)(citation

3979omitted).

398028. Be cause administrative law judges are the triers of

3990fact charged with resolving disputed issues of material fact

3999based upon the evidence presented at hearing, and because bid

4009protests are fundamentally de novo proceedings, the undersigned

4017is not required to defer to the letting authority in regard to

4029any findings of objective historical fact that might have been

4039made in the run - up to preliminary agency action. It is

4051exclusively the administrative law judge’s job, as the trier of

4061fact, to ascertain from the c ompetent, substantial evidence in

4071the record what actually happened in the past or what reality

4082presently exists, as if no findings previously had been made.

409229. If, however, the challenged agency action involves an

4101ultimate factual determination —— for e xample, an agency’s

4110conclusion that a proposal’s departure from the project

4118specifications was a minor irregularity as opposed to a material

4128deviation —— then some deference is in order, according to the

4139clearly erroneous standard of review. 4 To prevail on an

4149objection to an ultimate finding, therefore, the protester must

4158substantially undermine the factual predicate for the agency’s

4166conclusion or convince the judge that a defect in the agency’s

4177logic led it unequivocally to commit a mistake.

418530. There is a nother species of agency action that also is

4197entitled to review under the clearly erroneous standard:

4205interpretations of statutes for whose administration the agency

4213is responsible, and interpretations of the agency’s own rules.

4222See State Contracting and Engineering Corp. v. Department of

4231Transp. , 709 So. 2d 607, 610 (Fla. 1st DCA 1998). In deference

4243to the agency’s expertise, such interpretations will not be

4252overturned unless clearly erroneous. Id. 5

425831. This means that if the protester objects to the

4268proposed agency action on the ground that it violates either a

4279governing statute within the agency’s substantive jurisdiction

4286or the agency’s own rule, and if, further, the validity of the

4298objection turns on the meaning, which is in dispute, of the

4309subjec t statute or rule, then the agency’s interpretation should

4319be accorded deference; the challenged action should stand unless

4328the agency’s interpretation is clearly erroneous (assuming the

4336agency acted in accordance therewith). 6

43422. The Abuse of Discretion S tandard

434932. The statute requires that agency action (in violation

4358of the applicable standard of conduct) which is “arbitrary, or

4368capricious” be set aside. Earlier, the phrase “arbitrary, or

4377capricious” was equated with the abuse of discretion standard,

4386s ee endnote 3, supra , because the concepts are practically

4396indistinguishable —— and because use of the term “discretion”

4405serves as a useful reminder regarding the kind of agency action

4416reviewable under this highly deferential standard.

442233. It has been obse rved that an arbitrary decision is one

4434that is not supported by facts or logic, or is despotic. Agrico

4446Chemical Co. v. State Dept. of Environmental Regulation , 365 So.

44562d 759, 763 (Fla. 1st DCA 1978), cert. denied , 376 So. 2d 74

4469(Fla. 1979). Thus, under the arbitrary or capricious standard,

4478“an agency is to be subjected only to the most rudimentary

4489command of rationality. The reviewing court is not authorized

4498to examine whether the agency’s empirical conclusions have

4506support in substantial evidence.” Ad am Smith Enterprises, Inc.

4515v. State Dept. of Environmental Regulation , 553 So. 2d 1260,

45251273 (Fla. 1st DCA 1989). Nevertheless,

4531the reviewing court must consider whether

4537the agency: (1) has considered all relevant

4544factors; (2) has given actual, good fai th

4552consideration to those factors; and (3) has

4559used reason rather than whim to progress

4566from consideration of each of these factors

4573to its final decision.

4577Id.

457834. The second district framed the “arbitrary or

4586capricious” review standard in these terms: “If an

4594administrative decision is justifiable under any analysis that a

4603reasonable person would use to reach a decision of similar

4613importance, it would seem that the decision is neither arbitrary

4623nor capricious.” Dravo Basic Materials Co., Inc. v. State Dept.

4633of Transp. , 602 So. 2d 632, 634 n.3 (Fla. 2d DCA 1992). As the

4647court observed, this “is usually a fact - intensive

4656determination.” Id. at 634.

466035. Compare the foregoing “arbitrary or capricious”

4667analysis with the test for reviewing discretionary d ecisions:

"4676Discretion, in this sense, is abused when

4683the judicial action is arbitrary, fanciful,

4689or unreasonable, which is another way of

4696saying that discretion is abused only where

4703no reasonable man would take the view

4710adopted by the trial court. If re asonable

4718men could differ as to the propriety of the

4727action taken by the trial court, then it

4735cannot be said that the trial court abused

4743its discretion."

4745Canakaris v. Canakaris , 382 So. 2d 1197, 1203 (Fla. 1980),

4755quoting Delno v. Market St. Ry. Co. , 124 F .2d 965, 967 (9th Cir.

47691942). Further,

4771[t]he trial court's discretionary power is

4777subject only to the test of reasonableness,

4784but that test requires a determination of

4791whether there is logic and justification for

4798the result. The trial courts' discretion ary

4805power was never intended to be exercised in

4813accordance with whim or caprice of the judge

4821nor in an inconsistent manner. Judges

4827dealing with cases essentially alike should

4833reach the same result. Different results

4839reached from substantially the same fa cts

4846comport with neither logic nor

4851reasonableness.

4852Canakaris , 382 So. 2d at 1203

485836. Whether the standard is called “arbitrary or

4866capricious” or “abuse of discretion,” the scope of review, which

4877demands maximum deference, is the same. Clearly, then, th e

4887narrow “arbitrary or capricious” standard of review cannot

4895properly be applied in evaluating all agency actions that might

4905be challenged in a bid protest; rather, this highly deferential

4915standard appropriately applies only to those decisions which are

4924co mmitted to the agency’s discretion.

493037. Therefore, where the protester objects to agency

4938action that entails the exercise of discretion, but only in such

4949instances, the objection cannot be sustained unless the agency

4958abused its discretion, i.e. acted ar bitrarily or capriciously.

49673. The Contrary to Competition Standard

497338. The third standard of review articulated in Section

4982120.57(3)(f) is unique to bid protests. The “contrary to

4991competition” test is a catch - all which applies to agency actions

5003that d o not turn on the interpretation of a statue or rule, do

5017not involve the exercise of discretion, and do not depend upon

5028(or amount to) a determination of ultimate fact.

503639. Although the contrary to competition standard, being

5044unique to bid protests, is le ss well defined than the other

5056review standards, the undersigned concludes that the set of

5065proscribed actions should include, at a minimum, those which:

5074(a) create the appearance of and opportunity for favoritism; (b)

5084erode public confidence that contract s are awarded equitably and

5094economically; (c) cause the procurement process to be genuinely

5103unfair or unreasonably exclusive; or (d) are unethical,

5111dishonest, illegal, or fraudulent.

5115VIII. The Responsiveness of Constructware’s Proposal

512140. As its prim ary protest grounds, E - Builder contends

5132that Constructware’s response deviated materially in at least

5140six respects from the project specifications as set forth in the

5151RFP, and that, therefore, the Board breached the applicable

5160standard of conduct by evalua ting, rather than rejecting,

5169Constructware’s allegedly nonconforming proposal. Four of the

5176seven specific protest grounds are based on Constructware’s

5184alleged failure to comply strictly with the scope of work

5194requirements set forth in Section VI of the RF P. E - Builder

5207further alleges that Constructware’s proposal deviated in two

5215material instances from the provisions of Section VII of the

5225RFP, which specifies the submittal requirements. These alleged

5233irregularities will be addressed below.

5238A. Scope of Wo rk

524341. E - Builder’s contentions regarding Constructware’s

5250alleged noncompliance with various parts of Section VI are all

5260premised on the idea that the specifications contained therein

5269were mandatory requirements. If instead the provisions of

5277Section VI w ere merely precatory or directory, however, then E -

5289Builder’s position would be untenable, as its counsel all but

5299conceded at final hearing. To prevail on its protest grounds

5309relating to the scope of work, E - Builder must demonstrate that

5321Section VI unambig uously imposed mandatory requirements, which

5329is a question of law. 7 See Travelers Indem. Co. of Illinois v.

5342Hutson , 847 So. 2d 1113, 1114 (Fla. 1st DCA 2003)(“Whether

5352ambiguity exists in a contract is . . . a question of law.”);

5365accord Specialty Restauran ts Corp. v. City of Miami , 501 So. 2d

5377101, 103 (Fla. 3d DCA 1987).

538342. E - Builder argues that the word “shall” in the sentence

5395that introduces the scope of work specifications is

5403determinative. The introductory sentence reads:

5408The proposer(s) shall provid e [the type of]

5416services [sought under this RFP] which

5422should include but not be limited to, the

5430following [particular services, products,

5434and benefits, as described below].

5439(Emphasis added). E - Builder interprets this sentence to mean,

5449effectively, that the proposer(s) shall provide services

5456including but not limited to the services specifically mentioned

5465in Section VI. 8 E - Builder thus plays down the distinction, which

5478this sentence draws, between (a) the relevant category of

5487services and (b) the constit uent services —— that is, the many

5499discrete services, products, and benefits that might constitute

5507categorical services, where the relevant category of services is

5516defined as “Internet[ - based] collaborative construction and

5524claims reduction support services for use in connection with the

5534[Board]’s capital construction program.”

553843. The undersigned, however, considers the distinction

5545just mentioned to be crucial to the meaning of the sentence in

5557question. It is clear to the undersigned that the drafters o f

5569the RFP intended, first , to reiterate (perhaps redundantly) that

5578the successful proposer should provide 9 a category of services

5588labeled “Internet[ - based] collaborative construction and claims

5596reductions support services” and, next , to describe specific

5604s ervices putatively falling within that category that the Board

5614believed —— but was not necessarily convinced —— would meet its

5625needs.

562644. To explain further, as the undersigned reads the

5635sentence, the mandate of “shall” stops at the relative clause

5645beginnin g with “which” —— and hence embraces only the category of

5657services sought. In the relative clause, which modifies the

5666referenced category of services by introducing a nonexclusive

5674list of particular services that the Board perceived as being

5684within such cat egory, the word “should” was intended, through

5694its unmistakable contrast with “shall,” to soften the latter’s

5704mandatory connotation and convey instead advisability or

5711suitability. 10 Put simply, the relative clause is directory

5720rather than mandatory; it con notes strong desire, not decisive

5730command. 11

573245. Accordingly, it is concluded, contrary to E - Builder’s

5742argument, that Section VI did not unambiguously mandate the

5751inclusion of all the listed items. Rather, Section VI

5760unambiguously advised prospectiv e proposers that including the

5768enumerated items would be prudent —— while letting them know that

5779alternative solutions had not been ruled out.

578646. Moreover, the undersigned concludes that even if the

5795above interpretation (which accords with the Board’s) we re not

5805the only reasonable one, it is at least a reasonable

5815interpretation, and therefore, in any event, the first sentence

5824of Section VI is ambiguous. Thus, the Board’s interpretation,

5833if not correct, at a minimum is not clearly erroneous and hence

5845shoul d be upheld in this proceeding.

585247. Finally, because Constructware’s proposal addressed

5858all of the items listed in Section VI, though arguably without

5869strictly conforming to each and every one, 12 the undersigned

5879concludes that the Board’s decision to ev aluate Constructware’s

5888proposal rather than rejecting it as nonresponsive, which

5896decision was taken in accordance with a permissible

5904interpretation of Section VI, was not clearly erroneous and will

5914not be disturbed. 13

5918B. Submittal Requirements

592148. E - Buil der charges that Constructware’s proposal failed

5931to comply with Subsections A, E, and F of Section VII of the

5944RFP. These provisions —— together with Constructware’s particular

5952responses —— are set forth above in the Findings of Fact.

596349. The parties have not advanced competing

5970interpretations of the relevant language of Section VII. The

5979undersigned concludes that the provisions in question are

5987reasonably clear and unambiguous, making parsing unnecessary.

5994The dispositive question, therefore, is whether th e Evaluation

6003Committee’s ultimate factual determination that Constructware’s

6009proposal materially conformed to Section VII of the RFP is

6019clearly erroneous.

602150. In comparing Constructware’s proposal to the RFP

6029provisions at issue, the undersigned is not le ft with a definite

6041and firm conviction that the Evaluation Committee made a mistake

6051when it deemed Constructware’s proposal to be in material

6060compliance with Section VII. Thus, the undersigned cannot

6068conclude that the Evaluation Committee’s decision, when measured

6076against the applicable standard of review, is clearly erroneous.

6085C. Other Factors

608851. E - Builder alleges that the Board violated a governing

6099statute, namely Section 287.057(2)(a), because, first, the RFP

6107did not require the proposers to state “ the price for each year

6120the contract may be renewed” and, second, the Evaluation

6129Committee failed to consider “the total cost for each year as

6140submitted by the vendor[s].” See § 287.057(2)(a), F LA . S TAT .

615352. E - Builder’s argument must be rejected because Section

6163287.057(2)(a), which is located in Part I of Chapter 287,

6173Florida Statutes, does not apply to constitutional entities such

6182as school boards. See Dunbar Elec. Supply, Inc. v. School Bd.

6193of Dade County , 690 So. 2d 1339, 1340 (Fla. 3d DCA 1997). Thi s

6207limitation on the chapter’s reach stems from the definition of

6217the term “agency” as set forth in Section 287.012(1), 14 which

6228operates to draw into Chapter 287, Part I, only the executive

6239branch of state government. Id. 15

624553. Because Section 287.057(2)( a) is not a statute that

6255governs the Board, the Board was not required to comply with it

6267in order to meet the standard of conduct prescribed in Section

6278120.57(3)(f). 16 No further analysis is necessary to conclude

6287that these protest grounds are without meri t.

6295RECOMMENDATION

6296Based on the foregoing Findings of Fact and Conclusions of

6306Law, it is RECOMMENDED that the Board enter a Final Order

6317declaring E - Builder’s protest to be without substantial merit

6327and authorizing the award of the subject contract to

6336Const ructware.

6338DONE AND ENTERED this 10th day of October , 2003 , in

6348Tallahassee, Leon County, Florida.

6352S

6353___________________________________

6354JOHN G. VAN LANINGHAM

6358Administrative Law Judge

6361Division of Administrative Hearings

6365The DeSoto Building

63681230 Apalachee Parkway

6371Tallahassee, Florida 32399 - 3060

6376(850) 488 - 9675 SUNCOM 278 - 9675

6384Fax Filing (850) 921 - 6847

6390www.doah.state.fl.us

6391Filed with the Clerk of the

6397Division of Administrative Hearings

6401this 10th day of October , 2003 .

6408ENDNOTES

64091 / Allegations that were not raised at the final hearing or

6421argued in E - Builder’ s Proposed Recommended Order have been

6432rejected as unpersuasive and will not be discussed herein.

64412 / Because DOAH is always independent of the letting authority,

6452see § 120.65(1), Florida Statutes, it might be preferable to

6462label bid protests before DOAH a form of inter - agency review or,

6475alternatively, intra - branch review; however, because the letting

6484authority itself ultimately renders the final order, the first

6493district’s nomenclature is not incorrect.

64983 / The term “standard of proof” as used in § 120.5 7(3)(f)

6511reasonably may be interpreted to reference standards of review .

6521This is because, while the “standard of proof” sentence fails to

6532mention any common standards of proof, it does articulate two

6542accepted standards of review: (1) the “clearly erroneou s”

6551standard and (2) the abuse of discretion (= “arbitrary, or

6561capricious”) standard. (The “contrary to competition”

6567standard —— whether it be a standard of proof or standard of

6579review —— is unique to bid protests.)

65864 / An ultimate factual determination is a conclusion derived by

6597reasoning from objective facts; it frequently involves the

6605application of a legal principle or rule to historical facts:

6615e.g. the driver failed to use reasonable care under the

6625circumstances and therefore was negligent; and it may be infused

6635with policy considerations. Reaching an ultimate factual

6642finding requires that judgment calls be made which are unlike

6652those that attend the pure fact finding functions of weighing

6662evidence and choosing between conflicting but permissible view s

6671of reality.

66735 / From the general principle of deference follows the more

6684specific rule that an agency’s interpretation need not be the

6694sole possible interpretation or even the most desirable one; it

6704need only be within the range of permissible interpret ations.

6714State Bd. of Optometry v. Florida Soc. of Ophthalmology , 538 So.

67252d 878, 885 (Fla. 1st DCA 1988); see also Suddath Van Lines,

6737Inc. v. State Dept. of Environmental Protection , 668 So. 2d 209,

6748212 (Fla. 1st DCA 1996). However, “[t]he deference grant ed an

6759agency’s interpretation is not absolute.” Department of Natural

6767Resources v. Wingfield Development Co. , 581 So. 2d 193, 197

6777(Fla. 1st DCA 1991). Obviously, an agency cannot implement any

6787conceivable construction of a statute or rule no matter how

6797s trained, stilted, or fanciful it might be. Id. Rather, "only

6808a permissible construction” will be upheld by the courts.

6817Florida Soc. of Ophthalmology , 538 So. 2d at 885. Accordingly,

6827“[w]hen the agency's construction clearly contradicts the

6834unambiguous language of the rule, the construction is clearly

6843erroneous and cannot stand.” Woodley v. Department of Health

6852and Rehabilitative Services , 505 So. 2d 676, 678 (Fla. 1st DCA

68631987); see also Legal Environmental Assistance Foundation v.

6871Board of County Com’ rs of Brevard County , 642 So. 2d 1081, 1083 -

688584 (Fla. 1994)(“unreasonable interpretation” will not be

6892sustained).

68936 / The same standard of review also applies, in a protest

6905following the announcement of an intended award, with regard to

6915preliminary agency action taken upon the agency’s interpretation

6923of the project specifications —— but perhaps for a reason other

6934than deference to agency expertise. Section 120.57(3)(b),

6941Florida Statutes, provides a remedy for badly - written or

6951ambiguous specifications: they may be protested within 72 hours

6960after the posting of the specifications. The failure to avail

6970oneself of this remedy effects a waiver of the right to complain

6982about the specifications per se. Consequently, if the dispute

6991in a protest challenging a propo sed award turns on the

7002interpretation of an ambiguous, vague, or unreasonable

7009specification, which could have been corrected or clarified

7017prior to acceptance of the bids or proposals had a timely

7028specifications protest been brought, and if the agency has a cted

7039thereafter in accordance with a permissible interpretation of

7047the specification ( i.e. one that is not clearly erroneous), then

7058the agency’s intended action should be upheld —— not necessarily

7068out of deference to agency expertise, but as a result of the

7080protester’s waiver of the right to seek relief based on a faulty

7092specification. If, however, the agency has acted contrary to

7101the plain language of a lawful specification, then its action

7111should probably be corrected, for in that event the preliminary

7121age ncy action likely would be clearly erroneous or contrary to

7132competition; in that situation, there should be no waiver,

7141because a reasonable person would not protest an unambiguous

7150specification that facially conforms to Florida procurement law.

71587 / If Sec tion VI were found to be ambiguous as a matter of law,

7174then the Board’s preliminary action would be upheld, provided

7183the Board acted in accordance with a permissible interpretation

7192of the specifications at issue. See endnote 6, supra , and

7202accompanying tex t.

72058 / If “should” were intended to mean “shall” in the subject

7217sentence, as E - Builder urges, then Section VI would contain both

7229a mandate to provide the listed services and a prohibitory

7239command not to provide only those services. Under E - Builder’s

7250cons truction, in other words, the successful proposer would be

7260required to provide the enumerated services —— and then some.

72709 / Here, the word “should” is used in its capacity as the past

7284tense of “shall.” Note, in contrast, that “should” was not used

7295as the past tense of “shall” in the first sentence of Section

7307VI.

730810 / Because the word “should,” like many words in the English

7321language, can have different shades of meaning depending on the

7331context, judicial interpretations of the term “should” as used

7340in othe r situations are of relatively limited value. Indeed,

7350although the parties have found some cases in which “should” was

7361given a mandatory connotation, and others wherein “should” was

7370deemed directory or permissive, none is on point. Compare

7379United States v. Anderson , 798 F.2d 919, 923 - 24 (7th Cir.

73911986)(holding that, where the relevant ethical canon provides

7399that a judge “should not” engage in ex parte communications,

7409jury properly may be instructed that the Code of Judicial

7419Conduct requires the presence o f both sides in judicial

7429proceedings because the word “should” is commonly interpreted to

7438mean “shall”), with State of Florida v. Thomas , 528 So. 2d 1274,

74501275 - 76 (Fla. 3d DCA 1988)(procedural rule specifying that

7460“statutory maximum sentence should be impo sed” in a particular

7470situation left room for exercise of judicial discretion because,

7479read in context, the term “should” was directory rather than

7489mandatory). In this case, in arriving at what is considered to

7500be the plain and natural meaning of Section V I, the undersigned

7512has relied less on previous appellate decisions than on common

7522sense and a practical understanding of modern usage.

753011 / The undersigned views the relative clause, in this context,

7541as being somewhat stronger than precatory; the word “sho uld”

7551here, it seems, is not so much expressing a wish as forcefully

7563instructing would - be proposers that the enumerated items had

7573better be included —— or equivalent or superior services offered

7583in their stead. Thus, while the relative clause was not meant

7594t o be mandatory, the Evaluation Committee nevertheless was

7603justified in rejecting one of the proposals as inadequate for

7613failing to include a sufficient number of the enumerated items

7623without offering acceptable alternative solutions.

762812 / As used in the ac companying text, the words “arguably” and

7641“strictly” should be emphasized, for the undersigned is not

7650persuaded that Constructware’s proposal was materially deficient

7657even if Section VI were construed to impose mandatory

7666requirements. Although it is not n ecessary to explore this

7676subject in detail, the undersigned believes that Constructware’s

7684proposal is in substantial compliance, at least, with Section

7693VI, and he would be hard - pressed to declare that any of the

7707alleged deviations were material deviations. In this regard,

7715the undersigned is mindful that while “a bid containing a

7725material variance is unacceptable, not every deviation from the

7734invitation to bid is material. [A deviation] is material if it

7745gives the bidder a substantial advantage over the ot her bidders

7756and thereby restricts or stifles competition.” Tropabest Foods,

7764Inc. v. State Dept. of General Services , 493 So. 2d 50, 52 (Fla.

77771st DCA 1986). “The test for measuring whether a deviation in a

7789bid is sufficiently material to destroy its compe titive

7798character is whether the variation affects the amount of the bid

7809by giving the bidder an advantage or benefit not enjoyed by

7820other bidders.” Harry Pepper & Associates, Inc. v. City of Cape

7831Coral , 352 So. 2d 1190, 1193 (Fla. 2d DCA 1977).

784113 / The B oard’s decision that Constructware’s proposal

7850materially complied with Section VI was an ultimate factual

7859determination and therefore is entitled to some deference in

7868this proceeding. See endnote 4, supra , and accompanying text.

787714 / § 287.012(1) provides that:

7883“Agency" means any of the various state

7890officers, departments, boards, commissions,

7894divisions, bureaus, and councils and any

7900other unit of organization, however

7905designated, of the executive branch of state

7912government. “Agency” does not include the

7918university and college boards of trustees or

7925the state universities and colleges.

793015 / As the court noted in Dunbar , there is one exception to this

7944general statement regarding the chapter’s scope. The

7951Consultants’ Competitive Negotiation Act, which is c odified in §

7961287.055, employs a special definition of “agency” that

7969specifically includes school boards. See §

7975287.055(2)(b)(“‘Agency’ means the state, a state agency, a

7983municipality, a political subdivision, a school district, or a

7992school board.”). As a result, school boards must comply with §

8003287.055 when they purchase “professional services” as defined in

8012§ 287.055(2)(a). In this case, however, the Board is not

8022seeking to acquire “professional services” within the meaning of

8031§ 287.055(2)(a). Thus, th e Consultants’ Competitive Negotiation

8039Act is not presently relevant.

804416 / In R. N. Expertise, Inc. v. Miami - Dade County School Board,

8058et al. , DOAH Case No. 01 - 2663BID, 2002 WL 185217

8069(Fla.Div.Admin.Hrgs. 2002), the undersigned entered a

8075Recommended Order, which the Board later adopted in toto,

8084wherein it was urged that the Board’s preliminary decision to

8094award a contract for drug screening services be rescinded —— in

8105part because the award would have been contrary to Section

8115287.057(2) and other provisions o f Chapter 287, Part I. In that

8127case, however, the Board did not timely bring the Dunbar

8137decision to the undersigned’s attention, or otherwise suggest

8145that the provisions of Chapter 287 not be applied as governing

8156statutes, as was done here. (Moreover, as it happened, any

8166error in the application of Chapter 287 in R. N. Expertise was

8178harmless, because the outcome would have been the same

8187regardless.) To the limited extent that R. N. Expertise is in

8198conflict with Dunbar , the undersigned must recede from th e

8208former in favor of the latter.

8214COPIES FURNISHED :

8217Aaron R. Resnick, Esquire

8221Gunster, Yoakley & Stewart, P.A.

8226One Biscayne Tower, Suite 3400

82312 South Biscayne Boulevard

8235Miami, Florida 33131

8238Luis M. Garcia, Esquire

8242Miami - Dade County Schoo l Board

82491450 Northeast 2nd Avenue, Suite 400

8255Miami, Florida 33132

8258Mitchell A. Bierman, Esquire

8262Weiss, Serota, Helfman, Pastoriza

8266& Guedes, P.A.

82692665 South Bayshore Drive, Suite 420

8275Miami, Florida 33133

8278Merrett R. Stierheim

8281Interim Superintenden t

8284Miami - Dade County School Board

82901450 Northeast Second Avenue, No. 912

8296Miami, Florida 33132 - 1394

8301Honorable Jim Horne

8304Commissioner of Education

8307Turlington Building, Suite 1514

8311325 West Gaines Street

8315Tallahassee, Florida 32399 - 0400

8320Daniel J. Woodring, Ge neral Counsel

8326Department of Education

8329Turlington Building, Suite 1244

8333325 West Gaines Street

8337Tallahassee, Florida 32399 - 0400

8342NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

8348All parties have the right to submit written exceptions within

835815 days from the date of th is Recommended Order. Any exceptions

8370to this Recommended Order should be filed with the agency that

8381will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 11/26/2003
Proceedings: (Corrected) Final Order (filed via facsimile).
PDF:
Date: 11/25/2003
Proceedings: Agency Final Order
PDF:
Date: 11/24/2003
Proceedings: Final Order of the School Board of Miami-Dade County, Florida (filed via facsimile).
PDF:
Date: 11/19/2003
Proceedings: Agency Final Order
PDF:
Date: 10/10/2003
Proceedings: Recommended Order
PDF:
Date: 10/10/2003
Proceedings: Notice of Correction.
PDF:
Date: 10/10/2003
Proceedings: Order Denying Motion to Strike.
PDF:
Date: 10/10/2003
Proceedings: Recommended Order (hearing held June 17-18, 2003). CASE CLOSED.
PDF:
Date: 10/10/2003
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 10/10/2003
Proceedings: Respondent School Board`s Memorandum in Opposition to Petitioner`s "Emergency Motion to Strike Testimony of Dr. John Pennington, or, in the Alternative to Re-Open the Administrative Hearing" (filed via facsimile).
PDF:
Date: 10/09/2003
Proceedings: Supplement to Emergency Motion to Strike Testimony of Dr. John Penninigton, or, in the Alternative to Re-Open the Administrative Hearing (filed by Petitioner via facsimile).
PDF:
Date: 10/08/2003
Proceedings: Constructware`s Response in Opposition to E-Builder`s "Emergency Motion to Strike the Testimony of John Pennington, or in the Alternative, to Reopen the Administrative Hearing" (filed via facsimile).
PDF:
Date: 10/03/2003
Proceedings: Emergency Motion to Strike Testimony of Dr. John Pennington, or, in the Alternative to Re-Open the Administrative Hearing (filed by Petitioner via facsimile).
PDF:
Date: 09/26/2003
Proceedings: Order Granting Enlargement of Time. (the parties shall serve and file their respective proposed recommended orders on or before September 26, 2003)
PDF:
Date: 09/26/2003
Proceedings: Respondent`s Proposed Recommended Order (filed via facsimile).
PDF:
Date: 09/26/2003
Proceedings: Intervenor`s Notice of Adoption of Proposed Recommended Order (filed via facsimile).
PDF:
Date: 09/26/2003
Proceedings: Proposed Recommended Order filed by Petitioner.
PDF:
Date: 09/23/2003
Proceedings: Respondent`s Unopposed Motion for an Enlargement of Time to File Proposed Recommended Orders (filed via facsimile).
PDF:
Date: 09/09/2003
Proceedings: Order Regarding Proposed Recommended Orders. (the parties` respective proposed recommended orders shall be filed on or before September 23, 2003)
Date: 09/08/2003
Proceedings: Transcript (3 Volumes) filed.
PDF:
Date: 08/28/2003
Proceedings: Letter to Judge Van Laningham from M. Bierman stating haven`t received the transcript as of August 26, 2003 filed.
PDF:
Date: 07/14/2003
Proceedings: (Joint) Pre-hearing Stipulation filed.
Date: 06/17/2003
Proceedings: CASE STATUS: Hearing Held; see case file for applicable time frames.
PDF:
Date: 06/16/2003
Proceedings: Respondent`s Corrected Notice of Filing Answers to Petitioner`s Interrogatories to Respondent (filed via facsimile).
PDF:
Date: 06/16/2003
Proceedings: Respondent`s Notice of Filing Answers to Petitioner`s Interrogatories to Respondent (filed via facsimile).
PDF:
Date: 06/11/2003
Proceedings: E-Builder`s Response to Respondent`s Interrogatories filed.
PDF:
Date: 06/11/2003
Proceedings: E-Builder, Inc.`s Notice of Serving Answers to Respondent`s Interrogatories filed.
PDF:
Date: 06/10/2003
Proceedings: Constructware`s Answers to Interrogatories (filed via facsimile).
PDF:
Date: 06/10/2003
Proceedings: Constructware`s Answers to Expert Interrogatories (filed via facsimile).
PDF:
Date: 06/10/2003
Proceedings: Constructware`s Response to Petitioner`s Request for Production of Documents to Intervenor (filed via facsimile).
Date: 06/10/2003
Proceedings: Petitioner`s Request for Production of Documents to Intervenor filed.
PDF:
Date: 06/04/2003
Proceedings: Order Denying Motion to Dismiss issued.
PDF:
Date: 06/03/2003
Proceedings: Respondent`s First Set of Interrogatories to Petitioner (filed via facsimile).
PDF:
Date: 06/03/2003
Proceedings: Respondent`s Request for Production of Documents (filed via facsimile).
PDF:
Date: 06/03/2003
Proceedings: Response in Opposition to Motion to Dismiss filed by Petitioner.
PDF:
Date: 06/02/2003
Proceedings: Miami-Dade School Board and Emerging Solutions d/b/a Constructiveware, Inc.`s Motion to Dismiss BID Protest Petition of E-Builder, Inc. filed.
PDF:
Date: 05/30/2003
Proceedings: Notice of Administrative Hearing to Interested or Affected Parties filed by Respondent.
PDF:
Date: 05/23/2003
Proceedings: Order Granting Continuance and Re-scheduling Hearing issued (hearing set for June 17 and 18, 2003; 9:00 a.m.; Miami, FL).
PDF:
Date: 05/22/2003
Proceedings: Respondent School Board`s Unopposed Motion for Continuance of Hearing (filed via facsimile).
PDF:
Date: 05/12/2003
Proceedings: Order Granting Intervention issued. (Intervenor, Emerging Solutions d/b/a Constructware, Inc.,)
PDF:
Date: 05/09/2003
Proceedings: Emerging Solutions d/b/a Constructware, Inc. Petition for Leave to Intervene as an Additional Party Respondent filed.
PDF:
Date: 05/07/2003
Proceedings: Order of Pre-hearing Instructions issued.
PDF:
Date: 05/07/2003
Proceedings: Notice of Hearing issued (hearing set for May 27, 2003; 9:00 a.m.; Miami, FL).
PDF:
Date: 05/07/2003
Proceedings: Letter to Judge Van Laningham from A. Resnick regarding scheduling telephone conference (filed via facsimile).
PDF:
Date: 05/01/2003
Proceedings: Letter of Protest filed.
PDF:
Date: 05/01/2003
Proceedings: Agency referral filed.

Case Information

Judge:
JOHN G. VAN LANINGHAM
Date Filed:
05/01/2003
Date Assignment:
05/02/2003
Last Docket Entry:
11/26/2003
Location:
Miami, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (6):