04-002817EPP
In Re: Progress Energy Florida Hines Energy Center Power Block 4 Power Plant Siting Application No. Pa 92- 33sa3 vs.
*
Status: Closed
Recommended Order on Tuesday, April 5, 2005.
Recommended Order on Tuesday, April 5, 2005.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: PROGRESS ENERGY FLORIDA )
14HINES ENERGY CENTER POWER )
19BLOCK 4 POWER PLANT SITING ) Case No. 04 - 2817EPP
30APPLICATION NO. PA 92 - 33SA3. )
37)
38SITE CERTIFIC ATION RECOMMENDED ORDER
43Pursuant to due notice, the Division of Administrative
51Hearings, by its duly - designated Administrative Law Judge,
60Charles A. Stampelos, held a certification hearing in the above -
71styled case on March 23, 2005, in Bartow, Florida.
80A PPEARANCES
82For Progress Energy Florida:
86Douglas S. Roberts, Esquire
90Hopping Green & Sams, P.A.
95Post Office Box 6526
99Tallahassee, Florida 32314 - 6526
104For the Department of Environmental Protection:
110Scott A. Goorland, Esquire
114Dep artment of Environmental Protection
1193900 Commonwealth Boulevard
122Mail Station 35
125Tallahassee, Florida 32399 - 3000
130For the Southwest Florida Water Management District:
137Martha A. Moore, Esquire
141Southwest Florida Water Management Distric t
1472379 Broad Street
150Brooksville, Florida 34604 - 6899
155STATEMENT OF THE ISSUE
159The issue to be resolved in this proceeding is whether the
170Governor and Cabinet, sitting as the Siting Board, should issue
180a final order granting certification to Prog ress Energy Florida
190(PEF), to construct and operate a new 530 megawatt (MW)
200natural gas - fired electrical power plant in Polk County,
210Florida. The proposed site for the Project is located at PEFs
221existing Hines Energy Complex, southwest of Bartow, Flo rida.
230PRELIMINARY STATEMENT
232This proceeding was conducted pursuant to the Florida
240Electrical Power Plant Siting Act (PPSA), Chapter 403, Part
249II, Florida Statutes, and Florida Administrative Code Chapter
25762 - 17, to consider PEFs application for site cer tification for
269the proposed Hines Power Block 4 (also referred to as the
280Project).
281On August 5, 2004, Florida Power Corporation, doing
289business as PEF filed its Supplemental Application for site
298certification for the Hines Power Block 4 with the Florida
308Department of Environmental Protection (Department or FDEP).
315The application was found to be complete on August 20, 2004.
326The application was found to be sufficient on November 22, 2004.
337On November 23, 2004, the Florida Public Service Commission
346( FPSC) issued its Final Order determining the need for the
357proposed electrical power plant.
361On February 16, 2005, FDEP issued its written Staff
370Analysis Report concerning the Project, as required by Section
379403.507(4), Florida Statutes, incorporating the r eports from
387other state and regional agencies and proposing a comprehensive
396set of proposed Conditions of Certification.
402On February 17, 2005, a joint Prehearing Stipulation was
411submitted to the undersigned, which indicated that no party to
421this proceedin g objected to certification of the Project.
430On March 23, 2005, during the certification hearing, FDEP
439submitted its revised Staff Analysis Report as an exhibit.
448After proper public notice by both PEF and by FDEP, a
459certification hearing was held in B artow, Florida, on March 23,
4702005, as required by Section 403.508(3), Florida Statutes. The
479purpose of the certification hearing was to receive oral,
488written, and documentary evidence concerning whether, through
495available and reasonable methods, the locat ion and operation of
505the proposed Hines Power Block 4 would produce minimal adverse
515effects on human health, the environment, the ecology of the
525land and its wildlife, and the ecology of State waters and their
537aquatic life, in an effort to fully balance th e increase in
549demand for an electrical power plant location and operation with
559the broad interests of the public. See § 403.502, Fla. Stat.
570The hearing would have also considered any petitions challenging
579the separate FDEP - issued prevention of significan t deterioration
589(PSD) permit for the Project. However, no such petition was
599filed.
600At the certification hearing, PEF presented the oral
608testimony of three witnesses and had PEF Exhibits (PEF Ex.)
618numbered 1 through 10 admitted into evidence. These exh ibits
628included the pre - filed written testimony of five witnesses.
638That testimony was filed pursuant to Florida Administrative Code
647Rule 62 - 17.141(3). The pre - filed written testimony of two
659witnesses, Karl Bullock and Richard Zwolak, has been accepted,
668ba sed upon their execution of affidavits attesting to the
678accuracy of the testimony and accompanying exhibits. The other
687three witnesses adopted their pre - filed testimony during the
697hearing. FDEP presented the testimony of Steven Palmer, of the
707FDEPs Siti ng Coordination Office, and had FDEP Exhibits 1 and 2
719(FDEP Ex.) admitted into evidence. No member of the public
729appeared at the hearing to offer testimony or other evidence on
740the Project.
742Following the conclusion of the March 23, 2005, hearing, a
752one - v olume Transcript (Tr.) of the hearing was filed on
764March 29, 2005. The Joint Proposed Recommended Order of PEF,
774FDEP, and the Southwest Florida Water Management District
782(SWFWMD) was timely submitted and has been considered in the
792rendition of this Reco mmended Order.
798FINDINGS OF FACT
801Background
8021. Progress Energy Florida, previously known as Florida
810Power Corporation, is an electric utility that provides
818electricity in a 35 - county service area in Florida. This
829service area stretches from the Panhandl e through the center of
840the state and includes the western coast of Florida north of
851Tampa Bay. PEF currently serves approximately 1.5 million
859customers in this service area. PEF has been providing electric
869service in Florida for over 100 years. PEFs c urrent generating
880capacity is 9,174 megawatts. The Company currently operates 14
890different power plant facilities in the state. PEF has a
900customer growth rate of 1.7 percent per year. (Hunter, Tr. 14 -
91215; PEF Ex. 10, Slide 2).
9182. The PEF Hines Energy Complex is located in the
928southwest portion of Polk County, Florida, approximately 3.5
936miles south of the city of Bartow. The community of Homeland is
948located one mile northeast of the Hines site. County Road 555
959runs through the Project site. The Hine s site contains
969approximately 8,200 acres of reclaimed phosphate mine lands.
978The area around the larger Hines site has been dominated by
989phosphate mining operations, including mines, settling ponds,
996sand tailings, gypsum stacks, and chemical beneficiation plants.
1004The adjacent land uses consist almost entirely of active
1013phosphate mining or mined and reclaimed lands. (PEF Ex. 6,
1023Zwolak at 5 - 6; PEF Ex. RZ - 2; PEF Ex. 1 at 2 - 1).
10403. In the late 1980s, PEF began planning to meet the
1051needs of future growth in customer demand for electricity and
1061decided to identify a site that allowed for a wide variety of
1073possible generation technologies, while at the same time meeting
1082the ecological and regulatory requirements for building new
1090generation. PEF solicited th e help of a team of local
1101community, educational, and environmental leaders to evaluate
1108over 50 potential sites in Florida and South Georgia. This two -
1120year process culminated in 1991 with the selection of the Hines
1131site, then known as the Polk County site . (PEF Ex. 6, Hunter at
11454).
11464. In January 1994, the Governor and Cabinet, acting as
1156the Siting Board, certified the Hines Energy Complex for an
1166ultimate site capacity of 3,000 megawatts (MW) of generating
1176capacity fueled by either natural gas, coal ga s or fuel oil, and
1189also granted certification for the construction and operation of
1198an initial 470 MW combined cycle unit known as Power Block 1.
1210Power Block 1 began operation in 1999. In 2001, the Siting
1221Board also granted certification for the construc tion and
1230operation of Hines Power Block 2, a 530 MW combined cycle unit.
1242Power Block 2 began operation in 2003. In 2003, certification
1252was granted by the Siting Board for Power Block 3, which is
1264currently under construction, and expected to be in service by
1274late 2005. (PEF Ex. 6, Hunter at 5; PEF Ex. 1, Preface at 1 - 2;
1290FDEP Ex. 2 at 1).
12955. The original certification proceeding that culminated
1302in the 1994 certification included extensive evaluations of the
1311worst case capacity constraints and potential environmental
1318effects of the operation of the expected 3,000 MW of capacity.
1330Those evaluations included assessments of air quality impacts,
1338water quality and wildlife impacts, water use, noise impacts,
1347socioeconomic impacts and benefits, traffic impacts of
1354construction and operation, and other impacts of the entire
1363planned capacity of 3,000 MW. This original evaluation
1372significantly reduces the time and expense for processing the
1381Supplemental Site Certification Application and allows PEF to
1389respond more quickly to the growth in demand for electrical
1399generating facilities. The ultimate site capacity determination
1406assures PEF that the Hines Energy Complex site has adequate air,
1417water, and land resources to accommodate additional electrical
1425generating facil ities. The 1994 certification also established
1433that the full 3,000 MW of generating capacity and the Hines site
1446are consistent with the local land use plans and zoning
1456regulations of Polk County. (PEF Ex. 1, Pre - 1 to Pre - 2 at 2.4
1472to 2.5).
14746. The Hine s Energy Complex contains a number of existing
1485facilities and is divided into several major areas. The plant
1495island is the location for the existing and future power
1505generation facilities. It is approximately 704 acres. A 722 -
1515acre cooling pond, that is being expanded to approximately 1200
1525acres, has been constructed on the site, along with a 311 - acre
1538brine pond. A buffer and mitigation area has been created along
1549the eastern portion of the Hines site containing approximately
15582,498 acres. These areas se rve as a wildlife corridor as well.
1571Approximately 3500 acres of the site are designated for water
1581crop areas to supply captured rainfall for use in the power
1592plant. (PEF Ex. 6, Hunter at 3; PEF Ex. JJH - 4; PEF Ex. 1 at 2 -
16101).
16117. The Hines Energy Comple x is interconnected to the
1621electrical grid through multiple existing electrical
1627transmission lines. A new 20 mile long 230 kV transmission line
1638to connect the Hines Site to the existing PEF West Lake Wales
1650Substation is being permitted separately. Natura l gas is
1659delivered to the Hines Energy Complex by two existing natural
1669gas pipelines, which will serve Power Blocks 1, 2, 3, and 4.
1681Fuel oil is also burned in the existing units and is delivered
1693by truck and stored in an onsite storage tank. A new fuel o il
1707unloading station and a new fuel and storage tank will be added
1719to serve Power Block 4. (PEF Ex. 6, Hunter at 6, 8; PEF Ex. 1
1734at 3 - 1; Tr. 17).
1740Project Overview
17428. The Hines Power Block 4 is a 530 MW combined - cycle
1755power plant to be fueled primarily with natural gas. Fuel oil
1766will be used as a backup fuel. The proposed Power Block 4 will
1779be located entirely within the existing Hines Energy Complex
1788site. The unit will be located west of Power Blocks 1, 2 and 3.
1802All construction activities for Power Block 4 will occur within
1812an approximately 5 - acre portion of the plant island. (PEF Ex.
18241, at 3 - 2, 4 - 1; PEF Ex. 6, Robinson at 5; Exs. JMR 4 and 5).
1843Need for Power Block 4
18489. On November 23, 2004, the FPSC issued a Final Order
1859determining the need for the PEFs Hines Power Block 4 Project.
1870The FPSC determined that the Hines Power Block 4 will be needed
1882by 2007 to maintain electric system reliability and integrity
1891for PEF. This was based upon an evaluation of PEFs load
1902forecast and maintenance of its required 20 percent reserve
1911margin of generating capacity above the firm demand of PEFs
1921customers. Power Block 4 adds to the diversity of PEFs
1931generating assets in terms of technology, fuel, age, and
1940functionality. Operational flexibility is provided by Power
1947Block 4s dual fuel capability. The FPSC also found that the
1958Hines Power Block 4 will contribute to the provision of adequate
1969electricity at reasonable cost. The FPSC concluded that PEF, in
1979proposing the Hines Power Block 4, had identified the l east cost
1991alternative compared to other options, including outside
1998proposals from third parties. There are no cost - effective
2008conservation measures available that might mitigate PEFs need
2016for Hines Power Block 4. In conclusion, the FPSC determined
2026that P EF met the statutory requirements under Section 403.519,
2036Florida Statutes, for the Commission to grant the determination
2045of need for Hines Power Block 4. (PEF Ex. 3).
2055Project Schedule and Construction
205910. The proposed Power Block 4 is similar to the exi sting
2071Hines Power Blocks 1, 2, and 3, which exist or are currently
2083under construction at the Hines site. The proposed combustion
2092turbines for the new unit are two advanced General Electric 7FA
2103combustion turbines, designed for dual fuel operation.
2110Engine ering of the units will commence in December 2005 and on -
2123site construction will begin no later than the first quarter of
21342006. The new unit is proposed to be in service by December 1,
21472007. (PEF Ex. 6, Robinson at 4, 13 - 14).
215711. Construction activitie s will be initiated by the
2166preparation of the five - acre site for construction. This will
2177include mobilization of contractors and subcontractors along
2184with plant construction project management personnel. Existing
2191construction laydown and parking areas wi ll be utilized for
2201Power Block 4. On - site construction will begin with the
2212installation of the circulating water piping and pilings for
2221structural foundations. Power Block 4 will be mechanically
2229complete by June 2007. (PEF Ex. 6, Robinson at 14).
223912. The construction workforce for Power Block 4 is
2248expected to average about 145 employees over the two - year
2259construction period. Peak construction employment is estimated
2266at 350 employees. The construction payroll is expected to be
2276$15 million annually. Based upon prior experience during
2284construction of Power Blocks 1, 2, and 3, it is expected that
2296most construction workers will be drawn from the Polk County and
2307Central Florida areas. Construction employees are expected to
2315commute daily to the job site. Traffic improvements have
2324already been made in the vicinity of the Hines Energy Complex.
2335Traffic impacts related to construction of Power Block 4 will
2345not require additional road improvements. (PEF Ex. 1 at 4 - 16 to
23584 - 17).
236113. No new roads will be req uired to support construction
2372of Power Block 4 as the existing plant access road will be used
2385during construction. Major project components will be delivered
2393to the Hines site by rail or by truck. No off - site upgrade of
2408rail or road facilities is expecte d to be necessary. All
2419oversized deliveries will receive necessary Florida Department
2426of Transportation (DOT) approvals. (PEF Ex. 1 at 3 - 20, 4 - 3;
2440PEF Ex. 6, Robinson at 14 - 15).
244814. Most major earthwork activities for construction for
2456the Power Block 4 construction area were performed during
2465initial site development activities that were completed in 1996.
2474There are no expected impacts to land in the Project area except
2486for minor grading, installation of foundation systems and
2494infrastructure piping, t he new control/administration building,
2501and the new fuel oil tank. (PEF Ex. 1 at 4 - 1).
251415. Heavily loaded and structural foundation loads such as
2523the heat recovery steam generators, combustion turbines, steam
2531turbines, and step - up transformers will be supported by deep
2542foundations. These foundations will include deep foundations
2549such as pilings similar to those used for Power Blocks 1, 2, and
25623. Lightly loaded foundations will use spread foundations.
2570Construction dewatering will occur primarily at ex cavations for
2579the circulating water intake structure and the discharge head
2588wall in the cooling pond. Other additional limited dewatering
2597may occur, depending upon the amount of rainfall and the depth
2608of other excavations onsite. Dewatering would be perf ormed
2617using well points or open pit sump pumps, which have a very
2629localized impact area. Dewatering effluent will be routed to
2638the existing on - site stormwater collection ditches for return to
2649the existing cooling pond. (PEF Ex. 6, Robinson at 12 - 13; PEF
2662E x. 1 at 4 - 7).
266916. The entire Project area is outside the 100 - year flood
2681zone. There will be no construction impacts to either on - site
2693or off - site water bodies or wetlands as a result of construction
2706activities. (PEF Ex. 1 at 2 - 2, 4 - 5).
271717. On - site construction activities will not have any
2727measureable adverse ecological impacts. The five - acre Project
2736area has already been cleared and graded in anticipation of
2746construction of Power Block 4 and other future units. The Power
2757Block 4 area is primarily bare soil, with very sparse weedy
2768vegetation of low - ecological functional value. This habitat is
2778suitable for few animals and exhibits low plant species
2787diversity. It will not support populations of threatened and
2796endangered species or species of special concern. There are no
2806jurisdictional or non - jurisdictional wetlands that would be
2815impacted by the development of Power Block 4 and the on - site
2828portion of the new transmission line. Mitigation for wetland
2837impacts on the Hines Energy Complex occurred as p art of the
2849original permitting process for the Hines Energy Complex. (PEF
2858Ex. 6, Bullock at 5 - 6; PEF Ex. 1 at 4 - 10 to 4 - 12).
287618. Construction noise impacts from construction of all
2884phases up to the 3,000 MWs of ultimate site capacity were
2896analyzed as pa rt of the 1992 certification application. It was
2907shown at that time that the applicable noise criteria would be
2918complied with during construction of each future phase. An
2927updated analysis of construction noise from Power Block 4
2936reaffirmed the earlier an alysis and demonstrated no adverse
2945impacts from construction noise. The nearest residences are
2953approximately 2.9 miles from the plant site. The Project
2962construction noise levels will be less than the existing noise
2972levels measured near these residences. Construction noise will
2980have an insignificant effect on noise levels. (PEF Ex. 6,
2990Osbourn at 15 - 16; PEF Ex 1 at 4 - 17 to 4 - 19).
300619. During construction, the most prevalent construction
3013air emissions will be fugitive dust, generated by site grading,
3023exc avation, vehicular traffic, and other construction
3030activities. Dust control measures will be used and will
3039typically require moisture conditioning of construction areas
3046and roadways. Disturbed areas will also be stabilized by
3055mulching or seeding as soon as practical. Crushed rock may also
3066be used in high traffic areas. It is not expected that these
3078air emissions from construction will present any significant air
3087quality problems during the construction period. (PEF Ex. 1 at
30974 - 14 to 4 - 16).
3104Project Des cription
310720. Power Block 4 will be similar to the existing Power
3118Blocks 1, 2, and 3 at the Hines site. Power Block 4 is a new
3133combined cycle unit of approximately 530 MWs. It will consist
3143of two advanced GE 7 FA combustion turbines (CT) designed for
3154d ual fuel operation, using primarily natural gas and low sulfur
3165fuel oil as a backup fuel. Each CT will connect to an
3177electrical generator, capable of generating approximately 170
3184MWs of electricity. Each CT in Power Block 4 will be paired
3196with a heat rec overy steam generator (HRSG) which will extract
3207heat energy from the CTs exhaust gas. The HRSG is essentially
3218a boiler that turns heat in the CTs exhaust, which would be
3230otherwise wasted, into steam. The steam produced in both HRSGs
3240is used to drive a single steam turbine, which will produce an
3252additional 190 MWs of electricity. (PEF Ex. 6, Robinson at 4 to
32645; PEF Ex. JMR - 2; FDEP Ex. 2 at 1 - 10).
327721. The normal operating mode for Power Block 4 will be
3288for both CTs to be in operation providing steam from their
3299respective HRSGs to the single steam turbine. However, Power
3308Block 4 can be operated in other ways, depending on the need for
3321electricity. One CT can be operated at full load, producing
3331steam from its HRSG that would power the steam turbine a t half
3344load while the other CT and HRSG are idle. The unit will be
3357operated between 30 percent load and full load in the combined
3368cycle mode while meeting its air emission permit requirements.
3377(PEF Ex. 6, Robinson at 4 - 5).
338522. Natural gas will be the principal fuel used in Power
3396Block 4. Gas will be delivered by two existing gas pipelines
3407that serve the Hines Energy Complex. A new on - site gas pipeline
3420will be constructed to supply natural gas to the new Power Block
34324 from the two on - site natural gas meter regulation stations.
3444Fuel oil will be delivered by truck to a new fuel unloading
3456facilities and stored in a new on - site fuel storage tank
3468adjacent to Power Block 4. (PEF Ex. 1 at 3 - 4; Tr. 27).
348223. The existing on - site electrical switchyard will be
3492expanded to provide electrical transmission interconnection for
3499Power Block 4. The on - site segment of a new 230 kV transmission
3513line between the Hines Site and the PEF West Lake Wales
3524electrical substation is included in the project for
3532certification. (PEF Ex. 6, Robinson at 6; Tr. 17).
354124. Pursuant to the authorization under the 1994 site
3550certification, a 10,000 gallon per day domestic wastewater
3559treatment plant will treat additional on - site domestic and
3569sanitary wastewaters from on - site showers, lavatories, toilets,
3578and drinking fountains for Power Block 4. The treated effluent
3588is directed to the on - site cooling pond as makeup water.
3600Potable water is provided from an existing on - site approved
3611potable water system which is adequate to support Pow er Blocks
36221, 2, 3, and 4. Potable water is supplied from well water and
3635is treated and chlorinated for on - site uses such as drinking,
3647washing, showers, and other uses. A new on - site water
3658distribution line will be installed to support Power Block 4 and
3669t he new control and administration building. (PEF Ex. 6,
3679Robinson at 12; PEF Ex. 1 at 3 - 11 to 3 - 12).
369325. Solid wastes that may be generated by Power Block 4
3704include circulating water systems screenings, sanitary waste
3711solids, water treatment filter back wash solids, and solid wastes
3721produced in the course of operating and maintaining the unit.
3731Office wastes are expected to be the biggest component of these
3742wastes. These wastes will be disposed of in differing ways.
3752Circulating water systems screenings and water filter backwash
3760will be recycled on - site to the extent possible. All other
3772solid wastes will be disposed of off - site in appropriate
3783facilities. PEF has a corporate commitment to waste
3791minimization. This includes extensive recycling of waste
3798pr oducts, reduction at the source, and elimination of most
3808hazardous waste storage. This corporate commitment will be
3816implemented on a continuing basis at the Hines Energy Complex.
3826(PEF Ex. 6, Robinson at 12; PEF Ex. 1 at 3 - 18).
3839Water Use and Supply
384326. The existing cooling pond will supply cooling water
3852and other water needs for Power Block 4. Makeup water to the
3864cooling pond is obtained from direct precipitation, reclaimed
3872treated municipal effluent, on - site stormwater runoff, recycled
3881plant blowdown and wastewaters, water cropping, and groundwater.
3889(PEF Ex. 1 at 3 - 7 to 3 - 9).
390027. The process steam in the steam turbine is cooled to
3911the liquid state in a steam condenser. The rejected heat from
3922the steam is transferred to water pumped from the existi ng
3933cooling pond into the circulating water system and then returned
3943to the cooling pond. The heat rejected from the power plant
3954results in forced evaporation above and beyond the natural
3963evaporation that occurs in the cooling pond. The circulating
3972water system equipment for Power Block 4 will include two new
3983circulating water pumps capable of pumping 60,000 gallons per
3993minute. An additional intake structure will be constructed at
4002the cooling pond to support these pumps. (PEF Ex. 6, Robinson
4013at 7 - 8; PEF Ex. 1 at 3 - 9 to 3 - 10).
402828. All process water needs for Power Block 4 will be
4039supplied from the existing cooling pond. Water is pumped from
4049the pond to the water treatment area located east of the
4060existing power blocks. The water is processed for use e ither as
4072service water or as demineralized water. Service water is used
4082for washdown of equipment and other uses. The higher quality
4092demineralized water is used for makeup to the steam - condensate -
4104feedwater cycle in the HRSGs to replace steam cycle losses .
4115Demineralized water is also used when firing low sulfur fuel oil
4126in the CTs to control NO x emissions. (PEF Ex. 6, Robinson at 8 -
41419, Osbourn at 7; PEF Ex. 1 at 3 - 12 to 3 - 13).
415629. The reverse osmosis equipment in the demineralized
4164water system produces a brine reject that will be pumped to the
4176existing on - site brine pond for evaporation. The only other
4187wastewater streams from Power Block 4 will come from the boiler
4198blowdown and from floor drains located throughout the facility.
4207Boiler blowdown results from removal of a portion of the water
4218cycling in the HRSG to control the buildup of solids in that
4230water. Boiler blowdown is collected and pumped back to the
4240cooling pond without further treatment. Areas that contain
4248lubricating oil equipment or where fuel lines run above ground
4258will have containment curbs or walls. Wastewater streams from
4267these areas that may contain oil will be routed to the existing
4279oil water separator to remove oil contamination prior to being
4289pumped to the cooling pond. Any colle cted oil is properly
4300disposed. All wastewaters are collected and processed as
4308appropriate and pumped back to the cooling pond. The cooling
4318pond has no discharge to area surface waters. (PEF Ex. 6,
4329Robinson at 9 - 10; PEF Ex. 1 at 3 - 12 to 3 - 16; FDEP Ex. 2 at 13).
435030. The cooling pond at the Hines Energy Complex
4359experiences both natural and forced evaporation. The forced
4367evaporation is that additional evaporation above and beyond
4375natural evaporation and is caused by the heat rejected from the
4386power plant . The total annual average evaporation rate from the
4397cooling pond from natural evaporation and from heat rejected by
4407Power Blocks 1, 2, 3 and the proposed Power Block 4 is
4419approximately 10 million gallons per day. This is an increase
4429in evaporation of 2. 2 million gallons per day for Power Block 4.
4442This loss of water needs to be replenished to keep the cooling
4454pond operating and keep the plant continuing in operation. (PEF
4464Ex. 6, Robinson at 7 - 8; PEF Ex. 1 at 3 - 9).
447831. It has been determined that, ove r the long term, Power
4490Block 4 will require an average annual daily water supply of 2.4
4502million gallons per day. This is needed to replace evaporation
4512from the pond and to supply the process water needs for the new
4525unit. (PEF Ex. 1 at 3 - 8). The existing Conditions of
4537Certification for the Hines Energy Complex authorize the use of
4547up to 17.5 million gallons per day of groundwater beginning with
4558the third generating unit at the Hines Energy Complex. The
4568water needs for Power Block 4 will be supplied from these
4579previously approved quantities of groundwater. The existing
4586Units 1 and 2 utilize a mix of treated wastewater from on - site
4600and off - site sources and captured rainfall to supply cooling and
4612process water needs for Power Blocks 1 and 2. (PEF Ex. 1 at 3 - 7
4628to 3 - 9; PEF Ex. 6, Hunter at 7; FDEP Ex. 2, Appendix IV, SWFWMD
4644Agency Report at 7).
464832. Under the Conditions of Certification, no groundwater
4656will be withdrawn to supplement the cooling pond until the
4666operating level in the cooling pond falls to 16 0 feet. The
4678proposed on - site withdrawals were previously evaluated as part
4688of the initial certification proceeding in 1994 and were found
4698to have no adverse impacts. The proposed on - site withdrawals of
4710groundwater for Power Block 4 will not have any adve rse impacts
4722on existing legal users of water in the vicinity of the Project,
4734on - and off - site wetlands, or to off - site land uses. PEF has
4750investigated other reasonably obtainable sources of water in the
4759region and found none that could meet the needs for Power Block
47714. (PEF Ex. 1, Vol. 2, Appendix 10.6; FDEP Ex. 2, App. IV,
4784SWFWMD Agency Report at 8 - 9).
479133. PEF has undertaken several efforts to minimize the use
4801of groundwater through the use of water conservation practices,
4810as required by the Condition s of Certification in the 1994 site
4822certification. These measures include the use of water
4830conserving electric generation technologies, recycling of all
4837wastewater streams, and the design of the power plant as a zero
4849discharge facility. PEF is also con tinuing to investigate
4858other sources of water supply for the Hines site. (FDEP Ex. 2,
4870App. IV, SWFWMD Agency Report at 8).
487734. Power Blocks 1 and 2 are supplied water from the on -
4890site water cropping system and on - site and off - site treated
4903wastewaters. The capture and reuse of rainfall is an integrated
4913part of PEFs efforts to reduce dependence on the Upper Floridan
4924aquifer as a source of water. In addition, recycled plant
4934wastewaters, treated wastewater from the City of Bartow, and
4943nearby industrial a nd power plants are the other primary sources
4954of water for Hines Power Blocks 1 and 2. The City of Bartow
4967currently provides approximately 2.0 million gallons per day of
4976treated wastewater for use at the Hines Energy Complex. (PEF
4986Ex. 1, Hunter at 7; FDE P Ex. 2, App. IV, SWFWMD Agency Report at
50016 - 8).
5004Air Emissions
500635. The primary air pollutants emitted from Hines Power
5015Block 4 will include nitrogen oxides (NO x ), carbon monoxide
5026(CO), particulate matter (PM), and sulfur oxides such as
5035sulfur dioxi de. The primary cause of the air emissions from the
5047new unit will be the combustion of natural gas and distillate
5058oil in the CTs. Emissions of NO x and CO will result from the
5072combustion process. Emissions of PM and sulfur dioxide result
5081from trace impur ities in the fuel itself. (PEF Ex. 6, Osbourn
5093at 4 - 5; Tr. 35 - 37).
510136. Air emissions from Power Block 4 will be minimized
5111through the inherent efficiency of the combined cycle
5119technology, as well as the use of natural gas and light oil, use
5132of combustio n controls, and use of post - combustion control
5143technology for nitrogen oxide emissions. Natural gas is the
5152cleanest of fossil fuels and contains minimal amounts of
5161impurities. Light oil is also very low in impurities and its
5172use will be limited to up to 1,000 hours per year per combustion
5186turbine. Natural gas and light oil burn very efficiently, thus
5196minimizing the formation of air pollutants. Emissions are also
5205minimized through the use of advanced combustion control
5213technology in the combustion turbin e, specifically dry, low NO x
5224combustion controls for firing natural gas, and use of water
5234injection when firing light oil. A post - combustion control
5244technology, selective catalytic reduction (SCR) will be used
5252to further reduce NO x emissions from Power Block 4. (PEF Ex. 6,
5265Osbourn at 5 - 6; Tr. 35).
527237. The Hines Power Block 4 is required to meet best
5283available control technology (BACT) requirements, which limits
5290air pollution emission rates. The Project must also comply with
5300a mbient air quality standards (AAQS) and prevention of
5309significant deterioration (PSD) increment standards, which
5315establish levels of air quality which must be met. (PEF Ex. 6,
5327Osbourn at 6 - 7; PEF Ex. 1 at 3.5 to 3 - 6; FDEP Ex. 2 at 6, 17).
534738. Hines Power Block 4 is required to undergo PSD review
5358because it is a new source of air pollution that will emit some
5371air pollutants above the threshold amounts established under the
5380PSD program. PSD review was required for air emissions of PM,
5391sulfur dioxide, NO x , CO, and sulfuric acid mist because these
5402emissions are greater than the established PSD thresholds. (PEF
5411Ex. 6, Osbourn at 7).
541639. The BACT analysis for Hines Power Block 4 is part of
5428the evaluation of air emissions control technology under the P SD
5439regulations and is applicable to all pollutants for which PSD
5449review is required. BACT is a pollutant - specific emission
5459standard that provides the maximum degree of emission reduction,
5468after taking into account the energy, environmental, and
5476economic i mpacts and other costs. (PEF Ex. 6, Osbourn at 6 - 7;
5490FDEP Ex. 2 at 6).
549540. For NO x , FDEP has preliminarily determined for this
5505facility a BACT emission limit of 2.5 parts per million when
5516firing natural gas, and 10 parts per million when firing low
5527su lfur fuel oil. These emission levels will be achieved by the
5539use of dry low NO x combustion technology when firing natural gas,
5551use of water injection when firing fuel oil, and use of SCR
5563technology. (PEF Ex. 6, Osbourn at 8; FDEP Ex. 2 at 9, 21,
5576Table 4) .
557941. Emissions of carbon monoxide will be controlled using
5588good combustion techniques. Sulfur dioxide emissions, including
5595sulfuric acid mist, will be controlled through the use of clean
5606fuels. Particulate matter emissions will be controlled through
5614the use of clean fuels, natural gas, and low sulfur fuel oil.
5626Fuel oil firing will be limited to a maximum of about 1,000
5639hours per year. (PEF Ex. 6, Osbourn at 7 - 9; PEF Ex. 10, Slide
565415; Tr. 36 - 37).
565942. The air emissions from Power Block 4 cannot be
5669permitted at a level that would cause or contribute to a
5680violation of federal and state AAQS for the six criteria air
5691pollutants or PSD increments for sulfur dioxide, NO x, and PM.
5702The PSD increments refer to the amount of incremental air
5712quality deterior ation allowed from a new air pollution source.
5722Polk County is classified as a Class II area for PSD purposes.
5734The nearest Class I PSD area within which limited increases in
5745air pollutant concentrations are allowed is the Chassahowitzka
5753National Wildernes s Area. (PEF Ex. 6, Osbourn at 9 - 11; FDEP Ex.
57672 at 6 - 8, 16 - 17).
577543. Air emissions from Power Block 4 were principally
5784analyzed for emissions from fuel oil firing as representing the
5794maximum air quality impact. The air quality impact analysis was
5804perfo rmed using approved air quality models and five years of
5815historical hourly meteorological data. This analysis indicated
5822that Power Block 4 will not cause any violations of federal or
5834state AAQS and will comply with applicable PSD Class II and
5845Class I incr ements. The maximum impact of the Project was
5856estimated to be well below the applicable PSD Class II
5866increments. Maximum ambient air impacts were also estimated to
5875be well below the applicable AAQS. Using worst case air
5885emissions during oil firing, it w as shown that the Project
5896impacts would be less than the PSD Class I increments, as well
5908as less than the Class I significant impact levels, and
5918therefore were concluded not to be significant in the PSD Class
5929I area. (PEF Ex. 6, Osbourn at 8 - 14, Exs. SO - 3 and SO - 4; FDEP
5948Ex. 2 at 7 - 8, 16 - 17).
595744. Air emissions from Power Block 4 are not expected to
5968have any impact on vegetation or to cause any growth - related air
5981quality impacts. The results of the visibility impact analysis
5990of the Projects emissions in t he nearest PSD Class I area
6002demonstrated no adverse impact on visibility at that location
6011due to Power Block 4. (PEF Ex. 6, Osbourn at 14 - 15; FDEP Ex. 2
6027at 6 - 7, 17).
6032Noise
603345. Noise impacts during operation of Power Block 4 were
6043shown not to be signifi cant. Noise monitoring was originally
6053conducted at various locations around the Hines Energy Complex
6062site prior to construction and operation of Power Block 1.
6072Additional noise monitoring was conducted at these locations in
60812000 and 2004 during the permi tting of Power Blocks 2 and 4, to
6095determine any changes since the original permitting. There are
6104only a few isolated rural residences in the land area
6114surrounding the site. The nearest residence is about 2.5 miles
6124from the proposed Power Block 4. Indust rial activities in the
6135surrounding area result in considerable traffic on nearby roads,
6144causing noise levels to exceed the EPA guideline of 55 dBA.
6155Without the area traffic, ambient noise levels meet the EPA
6165guidelines. (PEF Ex. 1 at 2 - 65 to 2 - 72). Usin g a conservative
6181approach which tends to overstate the Project impacts, noise
6190impacts due to operation of Power Block 4 would increase by less
6202than 2 dBA at the nearest receptor and will not be significant.
6214Therefore, the Project will meet applicable nois e criteria and
6224no significant noise impacts will occur as a result of the
6235Project. (PEF Ex. 6, Osbourn at 15 - 16; PEF Ex. 10, Slide 23;
6249PEF Ex. 1 at 5 - 9 to 5 - 12).
6260Land Use and Socioeconomic Impacts
626546. The Plant Island, where Power Block 1 is in operatio n
6277and where Power Block 4 will be constructed, is located near the
6289southern end of the site. The northern boundary of the Plant
6300Island is about two miles south of CR 640. The western limit of
6313the City of Fort Meade is about 3.9 miles east of the Plant
6326Is land, and the unincorporated community of Homeland is more
6336than 3.5 miles northeast of the Plant Island. The nearest
6346residential use is three homes located approximately 2.5 miles
6355from the southern boundary of the Plant Island. Otherwise, the
6365entire area surrounding the proposed power plant site consists
6374of existing or former phosphate mines. The site is buffered
6384from surrounding populations at Homeland and Fort Meade by an
6394extensive buffer area on the eastern perimeter of the site.
6404There has been almo st no change in land use and very little
6417change in the landscape in the area of the Hines Energy Complex
6429since the original site certification. (PEF Ex. 6, Zwolak at 5 -
64416).
644247. There have not been any changes in the area
6452surrounding the Hines Energy Com plex that would change the land
6463use and socio - economic conclusions reached in the Final Order of
6475Certification issued for the site by the Siting Board on
6485January 27, 1994. The most significant change has been the
6495completion of another nearby power plant a pproximately three
6504miles southeast of the Hines site. (PEF Ex. 6, Zwolak at 6).
651648. No land use or socio - economic impacts will be
6527associated with construction of Power Block 4 that were not
6537previously addressed in the Final Order of Certification for the
6547Hines Energy Complex in 1994. (PEF Ex. 6, Zwolak at 6 - 8).
656049. The land use impacts from development and construction
6569of Power Block 4 will be quite minimal, and the economic
6580benefits will be substantial. Current operating employment at
6588the Hines Energ y Complex is 29. The staffing level at the plant
6601is expected to increase by six employees with the addition of
6612Power Block 4. Annual payroll was $2.7 million in 2002. The
6623annual payroll will increase by about $493,000 when Power Block
66344 becomes operatio nal in 2007. (PEF Ex. 6, Zwolak at 8).
664650. The estimated increase in property taxes for Power
6655Block 4 is $5.0 million. Over one - half of this revenue goes to
6669support the Polk County school system. (PEF Ex. 6, Zwolak at 8;
6681PEF Ex. 1 at 7 - 1).
6688Agency Posi tions and Stipulations
669351. The FDEP, the Florida Department of Community Affairs,
6702the FDOT, and the SWFWMD each prepared written reports on the
6713Project. (FDEP Ex. 2). Each of these agencies either
6722recommended approval of Hines Power Block 4 or otherwis e did not
6734object to certification of the proposed power plant. The FDEP
6744has proposed a series of Conditions of Certification for the
6754Project that incorporate the recommendations of the various
6762reviewing agencies. At hearing, the FDEP added one additional
6771condition related to air emissions monitoring. (Tr. 54 - 55).
6781PEF states that it can comply with these Conditions of
6791Certification in the design, construction, and operation of the
6800Hines Power Block 4. (Tr. 21, 56). No state, regional, or
6811local agency h as recommended denial of certification of the
6821Project or has otherwise objected to certification of the
6830Project. (PEF Ex. 4).
683452. Subject to compliance with the proposed conditions of
6843certification, the proposed design of Hines Power Block 4 offers
6853re asonable assurance that the standards of the FDEP and other
6864affected regulatory agencies will be met and that the operation
6874safeguards are technically sufficient for the protection of the
6883citizens of the state. The Hines Power Block 4, as proposed,
6894minimi zes through reasonable and available methods the adverse
6903effects on human health, the environment, the ecology of the
6913land and its wildlife, and the ecology of state waters and their
6925aquatic life. (FDEP Ex. 1 at 28; Tr. 57 - 59).
6936CONCLUSIONS OF LAW
693953. The Division of Administrative Hearings has
6946jurisdiction over the parties to and the subject matter of this
6957proceeding. §§ 120.569, and 120.57(1), 403.508(3), Fla. Stat.
696554. This proceeding was conducted to implement the
6973purposes a nd intent of the Florida Electrical Power Plant Site
6984Certification process. The purposes of that process are to
6993assure the citizens of Florida that the construction and
7002operation safeguards of the PEF Hines Power Block 4 Project are
7013technically sufficient to protect their health and welfare and
7022to effect a reasonable balance between the need for the Project
7033and the environmental impacts on air and water quality, fish and
7044wildlife, and the water resources and other resources of the
7054State resulting from the Projects construction and operation.
7062§ 403.502(1) - (2), Fla. Stat.
706855. In accordance with Chapters 120 and 403, Florida
7077Statutes, and Florida Administrative Code Chapter 62 - 17, proper
7087public notice was accorded all persons, entities, and parties
7096entit led thereto. All the necessary and required governmental
7105agencies were parties to this proceeding or were otherwise
7114afforded adequate opportunity to participate in this proceeding.
7122All required reports by State, regional, and local agencies were
7132complete d and presented.
713656. The FPSC, in an Order dated November 23, 2004, has
7147determined a need exists for the 530 MW (nominal) of electrical
7158generating capacity to be supplied by the Project, pursuant to
7168the requirements of Section 403.519, Florida Statutes .
717657. The Governor and Cabinet of the State of Florida,
7186sitting as the Siting Board, determined in an order dated
7196January 26, 1993, that the Hines Energy Complex site is
7206consistent with the existing land use plans and zoning
7215ordinances of Polk County, pursuant to the procedures set out in
7226Section 403.508(1) and (2), Florida Statutes. The addition of
7235Power Block 4 will not expand the existing boundaries of the
7246Hines Energy Center or introduce a new fuel not previously
7256certified for the Hines Energy Comp lex. Further consideration
7265of consistency with local land use plans and zoning ordinances
7275is not required for this Supplemental Site Certification
7283Application, pursuant to Section 403.517(3), Florida Statutes.
729058. The FDEP and the other participating ag encies have all
7301recommended or otherwise do not object to certification of the
7311Hines Power Block 4 for construction and operation, subject to
7321this Recommended Order and to the Conditions of Certification
7330recommended by FDEP. (FDEP Ex. 2). PEF has indicat ed its
7341acceptance of these proposed conditions of certification. As a
7350result, none of the parties to this proceeding oppose
7359certification of the Hines Power Block 4.
736659. Based upon a preponderance of the evidence presented
7375at the certification hearing h eld on March 23, 2005, PEF has met
7388its burden of proving that the Hines Power Block 4 Project
7399should be certified as proposed. Competent, substantial
7406evidence presented at the hearing demonstrates that the
7414construction and operational safeguards for the H ines Power
7423Block 4 Project are technically sufficient to protect the health
7433and welfare of the citizens of Florida and are reasonable and
7444available methods to achieve that protection. If constructed,
7452maintained, and operated in accordance with this Recomm ended
7461Order and the FDEPs proposed Conditions of Certification, the
7470proposed Project will produce minimal adverse effects on human
7479health, the environment, the ecology of the land and its
7489wildlife, and ecology of state waters and their aquatic life.
7499Cert ification of the Project is consistent with the statutory
7509goal of the Florida Electrical Power Plant Siting Act of
7519providing abundant, low cost electrical energy, and
7526certification will affect a reasonable balance between the
7534environmental and other impact s which might occur and the need
7545for the Project as separately determined by the FPSC.
7554RECOMMENDATION
7555Based on the foregoing Findings of Fact and Conclusions of
7565Law, it is RECOMMENDED that the Governor and Cabinet, sitting as
7576the Siting Board, enter a Fin al Order granting certification to
7587PEF to construct and operate a new 530 MW natural gas - fired
7600electrical power plant (Hines Power Block 4 Project) in Polk
7610County, Florida, in accordance with the Conditions of
7618Certification, FDEP Exhibit 2.
7622DONE AND ENT ERED this 5th day of April, 2005, in
7633Tallahassee, Leon County, Florida.
7637S
7638CHARLES A. STAMPELOS
7641Administrative Law Judge
7644Division of Administrative Hearings
7648The DeSoto Building
76511230 Apalachee Parkway
7654Tallahassee, Florida 32399 - 3060
7659(850) 488 - 9675 SUNCOM 278 - 9675
7667Fax Filing (850) 921 - 6847
7673www.doah.state.fl.us
7674Filed with the Clerk of the
7680Division of Administrative Hearings
7684this 5th day of April, 2005.
7690COPIES FURNISHED:
7692Douglas S. Roberts, Esquire
7696Hopping Green & Sam s, P.A.
7702Post Office Box 6526
7706Tallahassee, Florida 32314 - 6526
7711Scott A. Goorland, Esquire
7715Department of Environmental Protection
77193900 Commonwealth Boulevard
7722Mail Station 35
7725Tallahassee, Florida 32399 - 3000
7730Martha A. Moore, Esquire
7734Southwest Florida Water Management District
77392379 Broad Street
7742Brooksville, Florida 34604 - 6899
7747Michael Duclos, Esquire
7750Polk County Attorneys Office
7754Post Office Box 9005
7758Bartow, Florida 33831 - 9005
7763James V. Antista, Esquire
7767Fish and Wildlife Conservation Commission
7772620 South Mer idian Street
7777Tallahassee, Florida 32399 - 1600
7782Sheauching Yu, Esquire
7785Department of Transportation
7788Haydon Burns Building
7791605 Suwannee Street, Mail Station 58
7797Tallahassee, Florida 32399 - 0450
7802Craig Varn, Esquire
7805Department of Community Affairs
78092555 Shuma rd Oak Boulevard
7814Tallahassee, Florida 32399 - 2100
7819Wm. Cochran Keating IV, Esquire
7824Florida Public Service Commission
78282450 Shumard Oak Boulevard
7832Tallahassee, Florida 32399 - 0850
7837Norman White, Esquire
7840Central Florida Regional Planning Council
7845555 East Chur ch Street
7850Bartow, Florida 33830
7853Steven Palmer
7855Siting Coordination Office
7858Department of Environmental Protection
78622600 Blair Stone Road
7866Tallahassee, Florida 32399
7869Raquel A. Rodriguez, General Counsel
7874Office of the Governor
7878The Capitol, Suite 209
7882Tall ahassee, Florida 32399 - 1001
7888Kathy C. Carter, Agency Clerk
7893Department of Environmental Protection
7897Office of General Counsel
7901Mail Station 35
79043900 Commonwealth Boulevard
7907Tallahassee, Florida 32399 - 3000
7912NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
7918All parties ha ve the right to submit written exceptions within
792915 days from the date of this Recommended Order. Any exceptions
7940to this Recommended Order should be filed with the agency that
7951will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 04/05/2005
- Proceedings: Site Certification Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 04/05/2005
- Proceedings: Site Certification Recommended Order (hearing held March 23, 2005). CASE CLOSED.
- Date: 03/29/2005
- Proceedings: Transcript filed.
- Date: 03/23/2005
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 03/17/2005
- Proceedings: Notice of Service of Written Direct Testimony and Exhibits (filed by D. Roberts).
- PDF:
- Date: 02/18/2005
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Certification Hearing on Progress Energy Florida Hines Energy Complex Application to Construct and Operate an Electrical Power Plant Located in Polk County, Florida filed.
- PDF:
- Date: 02/16/2005
- Proceedings: Department of Environmental Protection`s Notice of Filing of Written Analysis filed.
- PDF:
- Date: 02/03/2005
- Proceedings: Progress Energy Florida`s Notice of Amendment of Site Certification Application filed.
- PDF:
- Date: 12/23/2004
- Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing of Application for Electrical Power Plant Site Certification for Construction and Operation of Site addition to Electrical Power Plant Facility Located Near Bartow, Florida filed.
- PDF:
- Date: 12/15/2004
- Proceedings: Southwest Florida Water Management District`s Notice of Filing Agency Report filed.
- PDF:
- Date: 10/22/2004
- Proceedings: Progress Energy Florida`s Notice of Filing Responses to Notice of Insufficiency of the Florida Department of Environmental Protection filed.
- PDF:
- Date: 10/11/2004
- Proceedings: Southwest Florida Water Management District`s Preliminary Statement of Issues (filed via facsimile).
- PDF:
- Date: 10/06/2004
- Proceedings: Notice of Hearing (hearing set for March 23 and 24, 2005; 1:00 p.m.; Bartow, FL).
- PDF:
- Date: 10/05/2004
- Proceedings: Order Altering Times. (time frames are altered as set forth in the Proposed Schedule for Review of Site Certification, subject to the ruling on any objection filed within five days from this date)
- PDF:
- Date: 10/04/2004
- Proceedings: Polk County, Florida, a Political Subdivision of the State of Florida Notice of Intent to be a Party filed.
- PDF:
- Date: 10/01/2004
- Proceedings: Joint Response to Initial Order, Filing of Scedule, and Motion and Stipulation for Alteration of Time Frames (filed via facsimile).
- PDF:
- Date: 09/23/2004
- Proceedings: Southwest Florida Water Management District`s Notice of Intent to be a Party (filed via facsimile).
- PDF:
- Date: 09/20/2004
- Proceedings: Department of Transportation`s Notice of Intent to be a Party (filed via facsimile).
- Date: 09/17/2004
- Proceedings: Supplemental Site Certification Application (two volumes) filed.
- PDF:
- Date: 09/17/2004
- Proceedings: Notice of Filing of Site Certification Application filed by S. Goorland.
- PDF:
- Date: 08/26/2004
- Proceedings: Notice of Distribution of Supplemental Site Certification Application to PA 92-33 filed.
Case Information
- Judge:
- CHARLES A. STAMPELOS
- Date Filed:
- 08/12/2004
- Date Assignment:
- 03/07/2005
- Last Docket Entry:
- 06/09/2005
- Location:
- Bartow, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- EPP
Counsels
-
James V. Antista, Esquire
Address of Record -
Michael E Duclos, Esquire
Address of Record -
Scott A Goorland, Esquire
Address of Record -
Mary Anne Helton, Esquire
Address of Record -
Martha A. Moore, Esquire
Address of Record -
Carolyn S. Raepple, Esquire
Address of Record -
Douglas S. Roberts, Esquire
Address of Record -
Craig D. Varn, Esquire
Address of Record -
Norman White, Esquire
Address of Record -
Sheauching Yu, Esquire
Address of Record -
Scott A. Goorland, Esquire
Address of Record -
Doug S. Roberts, Esquire
Address of Record -
Craig D Varn, Esquire
Address of Record