04-002817EPP In Re: Progress Energy Florida Hines Energy Center Power Block 4 Power Plant Siting Application No. Pa 92- 33sa3 vs. *
 Status: Closed
Recommended Order on Tuesday, April 5, 2005.


View Dockets  
Summary: The uncontroverted evidence admitted during the local public certification hearing on Progress Energy of Florida`s project to construct and operate a new 530 MW natural gas-fired electrical power plant in Polk County, FL, supported project approval.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: PROGRESS ENERGY FLORIDA )

14HINES ENERGY CENTER POWER )

19BLOCK 4 POWER PLANT SITING ) Case No. 04 - 2817EPP

30APPLICATION NO. PA 92 - 33SA3. )

37)

38SITE CERTIFIC ATION RECOMMENDED ORDER

43Pursuant to due notice, the Division of Administrative

51Hearings, by its duly - designated Administrative Law Judge,

60Charles A. Stampelos, held a certification hearing in the above -

71styled case on March 23, 2005, in Bartow, Florida.

80A PPEARANCES

82For Progress Energy Florida:

86Douglas S. Roberts, Esquire

90Hopping Green & Sams, P.A.

95Post Office Box 6526

99Tallahassee, Florida 32314 - 6526

104For the Department of Environmental Protection:

110Scott A. Goorland, Esquire

114Dep artment of Environmental Protection

1193900 Commonwealth Boulevard

122Mail Station 35

125Tallahassee, Florida 32399 - 3000

130For the Southwest Florida Water Management District:

137Martha A. Moore, Esquire

141Southwest Florida Water Management Distric t

1472379 Broad Street

150Brooksville, Florida 34604 - 6899

155STATEMENT OF THE ISSUE

159The issue to be resolved in this proceeding is whether the

170Governor and Cabinet, sitting as the Siting Board, should issue

180a final order granting certification to Prog ress Energy Florida

190(“PEF”), to construct and operate a new 530 megawatt (“MW”)

200natural gas - fired electrical power plant in Polk County,

210Florida. The proposed site for the Project is located at PEF’s

221existing Hines Energy Complex, southwest of Bartow, Flo rida.

230PRELIMINARY STATEMENT

232This proceeding was conducted pursuant to the Florida

240Electrical Power Plant Siting Act (“PPSA”), Chapter 403, Part

249II, Florida Statutes, and Florida Administrative Code Chapter

25762 - 17, to consider PEF’s application for site cer tification for

269the proposed Hines Power Block 4 (also referred to as the

280“Project”).

281On August 5, 2004, Florida Power Corporation, doing

289business as PEF filed its Supplemental Application for site

298certification for the Hines Power Block 4 with the Florida

308Department of Environmental Protection (“Department” or “FDEP”).

315The application was found to be complete on August 20, 2004.

326The application was found to be sufficient on November 22, 2004.

337On November 23, 2004, the Florida Public Service Commission

346( FPSC) issued its Final Order determining the need for the

357proposed electrical power plant.

361On February 16, 2005, FDEP issued its written Staff

370Analysis Report concerning the Project, as required by Section

379403.507(4), Florida Statutes, incorporating the r eports from

387other state and regional agencies and proposing a comprehensive

396set of proposed Conditions of Certification.

402On February 17, 2005, a joint Prehearing Stipulation was

411submitted to the undersigned, which indicated that no party to

421this proceedin g objected to certification of the Project.

430On March 23, 2005, during the certification hearing, FDEP

439submitted its revised Staff Analysis Report as an exhibit.

448After proper public notice by both PEF and by FDEP, a

459certification hearing was held in B artow, Florida, on March 23,

4702005, as required by Section 403.508(3), Florida Statutes. The

479purpose of the certification hearing was to receive oral,

488written, and documentary evidence concerning whether, through

495available and reasonable methods, the locat ion and operation of

505the proposed Hines Power Block 4 would produce minimal adverse

515effects on human health, the environment, the ecology of the

525land and its wildlife, and the ecology of State waters and their

537aquatic life, in an effort to fully balance th e increase in

549demand for an electrical power plant location and operation with

559the broad interests of the public. See § 403.502, Fla. Stat.

570The hearing would have also considered any petitions challenging

579the separate FDEP - issued prevention of significan t deterioration

589(“PSD”) permit for the Project. However, no such petition was

599filed.

600At the certification hearing, PEF presented the oral

608testimony of three witnesses and had PEF Exhibits (PEF Ex.)

618numbered 1 through 10 admitted into evidence. These exh ibits

628included the pre - filed written testimony of five witnesses.

638That testimony was filed pursuant to Florida Administrative Code

647Rule 62 - 17.141(3). The pre - filed written testimony of two

659witnesses, Karl Bullock and Richard Zwolak, has been accepted,

668ba sed upon their execution of affidavits attesting to the

678accuracy of the testimony and accompanying exhibits. The other

687three witnesses adopted their pre - filed testimony during the

697hearing. FDEP presented the testimony of Steven Palmer, of the

707FDEP’s Siti ng Coordination Office, and had FDEP Exhibits 1 and 2

719(FDEP Ex.) admitted into evidence. No member of the public

729appeared at the hearing to offer testimony or other evidence on

740the Project.

742Following the conclusion of the March 23, 2005, hearing, a

752one - v olume Transcript (Tr.) of the hearing was filed on

764March 29, 2005. The Joint Proposed Recommended Order of PEF,

774FDEP, and the Southwest Florida Water Management District

782(“SWFWMD”) was timely submitted and has been considered in the

792rendition of this Reco mmended Order.

798FINDINGS OF FACT

801Background

8021. Progress Energy Florida, previously known as Florida

810Power Corporation, is an electric utility that provides

818electricity in a 35 - county service area in Florida. This

829service area stretches from the Panhandl e through the center of

840the state and includes the western coast of Florida north of

851Tampa Bay. PEF currently serves approximately 1.5 million

859customers in this service area. PEF has been providing electric

869service in Florida for over 100 years. PEF’s c urrent generating

880capacity is 9,174 megawatts. The Company currently operates 14

890different power plant facilities in the state. PEF has a

900customer growth rate of 1.7 percent per year. (Hunter, Tr. 14 -

91215; PEF Ex. 10, Slide 2).

9182. The PEF Hines Energy Complex is located in the

928southwest portion of Polk County, Florida, approximately 3.5

936miles south of the city of Bartow. The community of Homeland is

948located one mile northeast of the Hines site. County Road 555

959runs through the Project site. The Hine s site contains

969approximately 8,200 acres of reclaimed phosphate mine lands.

978The area around the larger Hines site has been dominated by

989phosphate mining operations, including mines, settling ponds,

996sand tailings, gypsum stacks, and chemical beneficiation plants.

1004The adjacent land uses consist almost entirely of active

1013phosphate mining or mined and reclaimed lands. (PEF Ex. 6,

1023Zwolak at 5 - 6; PEF Ex. RZ - 2; PEF Ex. 1 at 2 - 1).

10403. In the late 1980’s, PEF began planning to meet the

1051needs of future growth in customer demand for electricity and

1061decided to identify a site that allowed for a wide variety of

1073possible generation technologies, while at the same time meeting

1082the ecological and regulatory requirements for building new

1090generation. PEF solicited th e help of a team of local

1101community, educational, and environmental leaders to evaluate

1108over 50 potential sites in Florida and South Georgia. This two -

1120year process culminated in 1991 with the selection of the Hines

1131site, then known as the Polk County site . (PEF Ex. 6, Hunter at

11454).

11464. In January 1994, the Governor and Cabinet, acting as

1156the Siting Board, certified the Hines Energy Complex for an

1166ultimate site capacity of 3,000 megawatts (MW) of generating

1176capacity fueled by either natural gas, coal ga s or fuel oil, and

1189also granted certification for the construction and operation of

1198an initial 470 MW combined cycle unit known as Power Block 1.

1210Power Block 1 began operation in 1999. In 2001, the Siting

1221Board also granted certification for the construc tion and

1230operation of Hines Power Block 2, a 530 MW combined cycle unit.

1242Power Block 2 began operation in 2003. In 2003, certification

1252was granted by the Siting Board for Power Block 3, which is

1264currently under construction, and expected to be in service by

1274late 2005. (PEF Ex. 6, Hunter at 5; PEF Ex. 1, Preface at 1 - 2;

1290FDEP Ex. 2 at 1).

12955. The original certification proceeding that culminated

1302in the 1994 certification included extensive evaluations of the

1311worst case capacity constraints and potential environmental

1318effects of the operation of the expected 3,000 MW of capacity.

1330Those evaluations included assessments of air quality impacts,

1338water quality and wildlife impacts, water use, noise impacts,

1347socioeconomic impacts and benefits, traffic impacts of

1354construction and operation, and other impacts of the entire

1363planned capacity of 3,000 MW. This original evaluation

1372significantly reduces the time and expense for processing the

1381Supplemental Site Certification Application and allows PEF to

1389respond more quickly to the growth in demand for electrical

1399generating facilities. The ultimate site capacity determination

1406assures PEF that the Hines Energy Complex site has adequate air,

1417water, and land resources to accommodate additional electrical

1425generating facil ities. The 1994 certification also established

1433that the full 3,000 MW of generating capacity and the Hines site

1446are consistent with the local land use plans and zoning

1456regulations of Polk County. (PEF Ex. 1, Pre - 1 to Pre - 2 at 2.4

1472to 2.5).

14746. The Hine s Energy Complex contains a number of existing

1485facilities and is divided into several major areas. The plant

1495island is the location for the existing and future power

1505generation facilities. It is approximately 704 acres. A 722 -

1515acre cooling pond, that is being expanded to approximately 1200

1525acres, has been constructed on the site, along with a 311 - acre

1538brine pond. A buffer and mitigation area has been created along

1549the eastern portion of the Hines site containing approximately

15582,498 acres. These areas se rve as a wildlife corridor as well.

1571Approximately 3500 acres of the site are designated for water

1581crop areas to supply captured rainfall for use in the power

1592plant. (PEF Ex. 6, Hunter at 3; PEF Ex. JJH - 4; PEF Ex. 1 at 2 -

16101).

16117. The Hines Energy Comple x is interconnected to the

1621electrical grid through multiple existing electrical

1627transmission lines. A new 20 mile long 230 kV transmission line

1638to connect the Hines Site to the existing PEF West Lake Wales

1650Substation is being permitted separately. Natura l gas is

1659delivered to the Hines Energy Complex by two existing natural

1669gas pipelines, which will serve Power Blocks 1, 2, 3, and 4.

1681Fuel oil is also burned in the existing units and is delivered

1693by truck and stored in an onsite storage tank. A new fuel o il

1707unloading station and a new fuel and storage tank will be added

1719to serve Power Block 4. (PEF Ex. 6, Hunter at 6, 8; PEF Ex. 1

1734at 3 - 1; Tr. 17).

1740Project Overview

17428. The Hines Power Block 4 is a 530 MW combined - cycle

1755power plant to be fueled primarily with natural gas. Fuel oil

1766will be used as a backup fuel. The proposed Power Block 4 will

1779be located entirely within the existing Hines Energy Complex

1788site. The unit will be located west of Power Blocks 1, 2 and 3.

1802All construction activities for Power Block 4 will occur within

1812an approximately 5 - acre portion of the plant island. (PEF Ex.

18241, at 3 - 2, 4 - 1; PEF Ex. 6, Robinson at 5; Exs. JMR 4 and 5).

1843Need for Power Block 4

18489. On November 23, 2004, the FPSC issued a Final Order

1859determining the need for the PEF’s Hines Power Block 4 Project.

1870The FPSC determined that the Hines Power Block 4 will be needed

1882by 2007 to maintain electric system reliability and integrity

1891for PEF. This was based upon an evaluation of PEF’s load

1902forecast and maintenance of its required 20 percent reserve

1911margin of generating capacity above the firm demand of PEF’s

1921customers. Power Block 4 adds to the diversity of PEF’s

1931generating assets in terms of technology, fuel, age, and

1940functionality. Operational flexibility is provided by Power

1947Block 4’s dual fuel capability. The FPSC also found that the

1958Hines Power Block 4 will contribute to the provision of adequate

1969electricity at reasonable cost. The FPSC concluded that PEF, in

1979proposing the Hines Power Block 4, had identified the l east cost

1991alternative compared to other options, including outside

1998proposals from third parties. There are no cost - effective

2008conservation measures available that might mitigate PEF’s need

2016for Hines Power Block 4. In conclusion, the FPSC determined

2026that P EF met the statutory requirements under Section 403.519,

2036Florida Statutes, for the Commission to grant the determination

2045of need for Hines Power Block 4. (PEF Ex. 3).

2055Project Schedule and Construction

205910. The proposed Power Block 4 is similar to the exi sting

2071Hines Power Blocks 1, 2, and 3, which exist or are currently

2083under construction at the Hines site. The proposed combustion

2092turbines for the new unit are two advanced General Electric 7FA

2103combustion turbines, designed for dual fuel operation.

2110Engine ering of the units will commence in December 2005 and on -

2123site construction will begin no later than the first quarter of

21342006. The new unit is proposed to be in service by December 1,

21472007. (PEF Ex. 6, Robinson at 4, 13 - 14).

215711. Construction activitie s will be initiated by the

2166preparation of the five - acre site for construction. This will

2177include mobilization of contractors and subcontractors along

2184with plant construction project management personnel. Existing

2191construction laydown and parking areas wi ll be utilized for

2201Power Block 4. On - site construction will begin with the

2212installation of the circulating water piping and pilings for

2221structural foundations. Power Block 4 will be mechanically

2229complete by June 2007. (PEF Ex. 6, Robinson at 14).

223912. The construction workforce for Power Block 4 is

2248expected to average about 145 employees over the two - year

2259construction period. Peak construction employment is estimated

2266at 350 employees. The construction payroll is expected to be

2276$15 million annually. Based upon prior experience during

2284construction of Power Blocks 1, 2, and 3, it is expected that

2296most construction workers will be drawn from the Polk County and

2307Central Florida areas. Construction employees are expected to

2315commute daily to the job site. Traffic improvements have

2324already been made in the vicinity of the Hines Energy Complex.

2335Traffic impacts related to construction of Power Block 4 will

2345not require additional road improvements. (PEF Ex. 1 at 4 - 16 to

23584 - 17).

236113. No new roads will be req uired to support construction

2372of Power Block 4 as the existing plant access road will be used

2385during construction. Major project components will be delivered

2393to the Hines site by rail or by truck. No off - site upgrade of

2408rail or road facilities is expecte d to be necessary. All

2419oversized deliveries will receive necessary Florida Department

2426of Transportation (“DOT”) approvals. (PEF Ex. 1 at 3 - 20, 4 - 3;

2440PEF Ex. 6, Robinson at 14 - 15).

244814. Most major earthwork activities for construction for

2456the Power Block 4 construction area were performed during

2465initial site development activities that were completed in 1996.

2474There are no expected impacts to land in the Project area except

2486for minor grading, installation of foundation systems and

2494infrastructure piping, t he new control/administration building,

2501and the new fuel oil tank. (PEF Ex. 1 at 4 - 1).

251415. Heavily loaded and structural foundation loads such as

2523the heat recovery steam generators, combustion turbines, steam

2531turbines, and step - up transformers will be supported by deep

2542foundations. These foundations will include deep foundations

2549such as pilings similar to those used for Power Blocks 1, 2, and

25623. Lightly loaded foundations will use spread foundations.

2570Construction dewatering will occur primarily at ex cavations for

2579the circulating water intake structure and the discharge head

2588wall in the cooling pond. Other additional limited dewatering

2597may occur, depending upon the amount of rainfall and the depth

2608of other excavations onsite. Dewatering would be perf ormed

2617using well points or open pit sump pumps, which have a very

2629localized impact area. Dewatering effluent will be routed to

2638the existing on - site stormwater collection ditches for return to

2649the existing cooling pond. (PEF Ex. 6, Robinson at 12 - 13; PEF

2662E x. 1 at 4 - 7).

266916. The entire Project area is outside the 100 - year flood

2681zone. There will be no construction impacts to either on - site

2693or off - site water bodies or wetlands as a result of construction

2706activities. (PEF Ex. 1 at 2 - 2, 4 - 5).

271717. On - site construction activities will not have any

2727measureable adverse ecological impacts. The five - acre Project

2736area has already been cleared and graded in anticipation of

2746construction of Power Block 4 and other future units. The Power

2757Block 4 area is primarily bare soil, with very sparse weedy

2768vegetation of low - ecological functional value. This habitat is

2778suitable for few animals and exhibits low plant species

2787diversity. It will not support populations of threatened and

2796endangered species or species of special concern. There are no

2806jurisdictional or non - jurisdictional wetlands that would be

2815impacted by the development of Power Block 4 and the on - site

2828portion of the new transmission line. Mitigation for wetland

2837impacts on the Hines Energy Complex occurred as p art of the

2849original permitting process for the Hines Energy Complex. (PEF

2858Ex. 6, Bullock at 5 - 6; PEF Ex. 1 at 4 - 10 to 4 - 12).

287618. Construction noise impacts from construction of all

2884phases up to the 3,000 MWs of ultimate site capacity were

2896analyzed as pa rt of the 1992 certification application. It was

2907shown at that time that the applicable noise criteria would be

2918complied with during construction of each future phase. An

2927updated analysis of construction noise from Power Block 4

2936reaffirmed the earlier an alysis and demonstrated no adverse

2945impacts from construction noise. The nearest residences are

2953approximately 2.9 miles from the plant site. The Project

2962construction noise levels will be less than the existing noise

2972levels measured near these residences. Construction noise will

2980have an insignificant effect on noise levels. (PEF Ex. 6,

2990Osbourn at 15 - 16; PEF Ex 1 at 4 - 17 to 4 - 19).

300619. During construction, the most prevalent construction

3013air emissions will be fugitive dust, generated by site grading,

3023exc avation, vehicular traffic, and other construction

3030activities. Dust control measures will be used and will

3039typically require moisture conditioning of construction areas

3046and roadways. Disturbed areas will also be stabilized by

3055mulching or seeding as soon as practical. Crushed rock may also

3066be used in high traffic areas. It is not expected that these

3078air emissions from construction will present any significant air

3087quality problems during the construction period. (PEF Ex. 1 at

30974 - 14 to 4 - 16).

3104Project Des cription

310720. Power Block 4 will be similar to the existing Power

3118Blocks 1, 2, and 3 at the Hines site. Power Block 4 is a new

3133combined cycle unit of approximately 530 MWs. It will consist

3143of two advanced GE 7 FA combustion turbines (“CT”) designed for

3154d ual fuel operation, using primarily natural gas and low sulfur

3165fuel oil as a backup fuel. Each CT will connect to an

3177electrical generator, capable of generating approximately 170

3184MWs of electricity. Each CT in Power Block 4 will be paired

3196with a heat rec overy steam generator (“HRSG”) which will extract

3207heat energy from the CT’s exhaust gas. The HRSG is essentially

3218a boiler that turns heat in the CT’s exhaust, which would be

3230otherwise wasted, into steam. The steam produced in both HRSGs

3240is used to drive a single steam turbine, which will produce an

3252additional 190 MWs of electricity. (PEF Ex. 6, Robinson at 4 to

32645; PEF Ex. JMR - 2; FDEP Ex. 2 at 1 - 10).

327721. The normal operating mode for Power Block 4 will be

3288for both CTs to be in operation providing steam from their

3299respective HRSGs to the single steam turbine. However, Power

3308Block 4 can be operated in other ways, depending on the need for

3321electricity. One CT can be operated at full load, producing

3331steam from its HRSG that would power the steam turbine a t half

3344load while the other CT and HRSG are idle. The unit will be

3357operated between 30 percent load and full load in the combined

3368cycle mode while meeting its air emission permit requirements.

3377(PEF Ex. 6, Robinson at 4 - 5).

338522. Natural gas will be the principal fuel used in Power

3396Block 4. Gas will be delivered by two existing gas pipelines

3407that serve the Hines Energy Complex. A new on - site gas pipeline

3420will be constructed to supply natural gas to the new Power Block

34324 from the two on - site natural gas meter regulation stations.

3444Fuel oil will be delivered by truck to a new fuel unloading

3456facilities and stored in a new on - site fuel storage tank

3468adjacent to Power Block 4. (PEF Ex. 1 at 3 - 4; Tr. 27).

348223. The existing on - site electrical switchyard will be

3492expanded to provide electrical transmission interconnection for

3499Power Block 4. The on - site segment of a new 230 kV transmission

3513line between the Hines Site and the PEF West Lake Wales

3524electrical substation is included in the project for

3532certification. (PEF Ex. 6, Robinson at 6; Tr. 17).

354124. Pursuant to the authorization under the 1994 site

3550certification, a 10,000 gallon per day domestic wastewater

3559treatment plant will treat additional on - site domestic and

3569sanitary wastewaters from on - site showers, lavatories, toilets,

3578and drinking fountains for Power Block 4. The treated effluent

3588is directed to the on - site cooling pond as makeup water.

3600Potable water is provided from an existing on - site approved

3611potable water system which is adequate to support Pow er Blocks

36221, 2, 3, and 4. Potable water is supplied from well water and

3635is treated and chlorinated for on - site uses such as drinking,

3647washing, showers, and other uses. A new on - site water

3658distribution line will be installed to support Power Block 4 and

3669t he new control and administration building. (PEF Ex. 6,

3679Robinson at 12; PEF Ex. 1 at 3 - 11 to 3 - 12).

369325. Solid wastes that may be generated by Power Block 4

3704include circulating water systems screenings, sanitary waste

3711solids, water treatment filter back wash solids, and solid wastes

3721produced in the course of operating and maintaining the unit.

3731Office wastes are expected to be the biggest component of these

3742wastes. These wastes will be disposed of in differing ways.

3752Circulating water systems screenings and water filter backwash

3760will be recycled on - site to the extent possible. All other

3772solid wastes will be disposed of off - site in appropriate

3783facilities. PEF has a corporate commitment to waste

3791minimization. This includes extensive recycling of waste

3798pr oducts, reduction at the source, and elimination of most

3808hazardous waste storage. This corporate commitment will be

3816implemented on a continuing basis at the Hines Energy Complex.

3826(PEF Ex. 6, Robinson at 12; PEF Ex. 1 at 3 - 18).

3839Water Use and Supply

384326. The existing cooling pond will supply cooling water

3852and other water needs for Power Block 4. Makeup water to the

3864cooling pond is obtained from direct precipitation, reclaimed

3872treated municipal effluent, on - site stormwater runoff, recycled

3881plant blowdown and wastewaters, water cropping, and groundwater.

3889(PEF Ex. 1 at 3 - 7 to 3 - 9).

390027. The process steam in the steam turbine is cooled to

3911the liquid state in a steam condenser. The rejected heat from

3922the steam is transferred to water pumped from the existi ng

3933cooling pond into the circulating water system and then returned

3943to the cooling pond. The heat rejected from the power plant

3954results in forced evaporation above and beyond the natural

3963evaporation that occurs in the cooling pond. The circulating

3972water system equipment for Power Block 4 will include two new

3983circulating water pumps capable of pumping 60,000 gallons per

3993minute. An additional intake structure will be constructed at

4002the cooling pond to support these pumps. (PEF Ex. 6, Robinson

4013at 7 - 8; PEF Ex. 1 at 3 - 9 to 3 - 10).

402828. All process water needs for Power Block 4 will be

4039supplied from the existing cooling pond. Water is pumped from

4049the pond to the water treatment area located east of the

4060existing power blocks. The water is processed for use e ither as

4072service water or as demineralized water. Service water is used

4082for washdown of equipment and other uses. The higher quality

4092demineralized water is used for makeup to the steam - condensate -

4104feedwater cycle in the HRSGs to replace steam cycle losses .

4115Demineralized water is also used when firing low sulfur fuel oil

4126in the CTs to control NO x emissions. (PEF Ex. 6, Robinson at 8 -

41419, Osbourn at 7; PEF Ex. 1 at 3 - 12 to 3 - 13).

415629. The reverse osmosis equipment in the demineralized

4164water system produces a brine reject that will be pumped to the

4176existing on - site brine pond for evaporation. The only other

4187wastewater streams from Power Block 4 will come from the boiler

4198blowdown and from floor drains located throughout the facility.

4207Boiler blowdown results from removal of a portion of the water

4218cycling in the HRSG to control the buildup of solids in that

4230water. Boiler blowdown is collected and pumped back to the

4240cooling pond without further treatment. Areas that contain

4248lubricating oil equipment or where fuel lines run above ground

4258will have containment curbs or walls. Wastewater streams from

4267these areas that may contain oil will be routed to the existing

4279oil water separator to remove oil contamination prior to being

4289pumped to the cooling pond. Any colle cted oil is properly

4300disposed. All wastewaters are collected and processed as

4308appropriate and pumped back to the cooling pond. The cooling

4318pond has no discharge to area surface waters. (PEF Ex. 6,

4329Robinson at 9 - 10; PEF Ex. 1 at 3 - 12 to 3 - 16; FDEP Ex. 2 at 13).

435030. The cooling pond at the Hines Energy Complex

4359experiences both natural and forced evaporation. The forced

4367evaporation is that additional evaporation above and beyond

4375natural evaporation and is caused by the heat rejected from the

4386power plant . The total annual average evaporation rate from the

4397cooling pond from natural evaporation and from heat rejected by

4407Power Blocks 1, 2, 3 and the proposed Power Block 4 is

4419approximately 10 million gallons per day. This is an increase

4429in evaporation of 2. 2 million gallons per day for Power Block 4.

4442This loss of water needs to be replenished to keep the cooling

4454pond operating and keep the plant continuing in operation. (PEF

4464Ex. 6, Robinson at 7 - 8; PEF Ex. 1 at 3 - 9).

447831. It has been determined that, ove r the long term, Power

4490Block 4 will require an average annual daily water supply of 2.4

4502million gallons per day. This is needed to replace evaporation

4512from the pond and to supply the process water needs for the new

4525unit. (PEF Ex. 1 at 3 - 8). The existing Conditions of

4537Certification for the Hines Energy Complex authorize the use of

4547up to 17.5 million gallons per day of groundwater beginning with

4558the third generating unit at the Hines Energy Complex. The

4568water needs for Power Block 4 will be supplied from these

4579previously approved quantities of groundwater. The existing

4586Units 1 and 2 utilize a mix of treated wastewater from on - site

4600and off - site sources and captured rainfall to supply cooling and

4612process water needs for Power Blocks 1 and 2. (PEF Ex. 1 at 3 - 7

4628to 3 - 9; PEF Ex. 6, Hunter at 7; FDEP Ex. 2, Appendix IV, SWFWMD

4644Agency Report at 7).

464832. Under the Conditions of Certification, no groundwater

4656will be withdrawn to supplement the cooling pond until the

4666operating level in the cooling pond falls to 16 0 feet. The

4678proposed on - site withdrawals were previously evaluated as part

4688of the initial certification proceeding in 1994 and were found

4698to have no adverse impacts. The proposed on - site withdrawals of

4710groundwater for Power Block 4 will not have any adve rse impacts

4722on existing legal users of water in the vicinity of the Project,

4734on - and off - site wetlands, or to off - site land uses. PEF has

4750investigated other reasonably obtainable sources of water in the

4759region and found none that could meet the needs for Power Block

47714. (PEF Ex. 1, Vol. 2, Appendix 10.6; FDEP Ex. 2, App. IV,

4784SWFWMD Agency Report at 8 - 9).

479133. PEF has undertaken several efforts to minimize the use

4801of groundwater through the use of water conservation practices,

4810as required by the Condition s of Certification in the 1994 site

4822certification. These measures include the use of water

4830conserving electric generation technologies, recycling of all

4837wastewater streams, and the design of the power plant as a “zero

4849discharge” facility. PEF is also con tinuing to investigate

4858other sources of water supply for the Hines site. (FDEP Ex. 2,

4870App. IV, SWFWMD Agency Report at 8).

487734. Power Blocks 1 and 2 are supplied water from the on -

4890site water cropping system and on - site and off - site treated

4903wastewaters. The capture and reuse of rainfall is an integrated

4913part of PEF’s efforts to reduce dependence on the Upper Floridan

4924aquifer as a source of water. In addition, recycled plant

4934wastewaters, treated wastewater from the City of Bartow, and

4943nearby industrial a nd power plants are the other primary sources

4954of water for Hines Power Blocks 1 and 2. The City of Bartow

4967currently provides approximately 2.0 million gallons per day of

4976treated wastewater for use at the Hines Energy Complex. (PEF

4986Ex. 1, Hunter at 7; FDE P Ex. 2, App. IV, SWFWMD Agency Report at

50016 - 8).

5004Air Emissions

500635. The primary air pollutants emitted from Hines Power

5015Block 4 will include nitrogen oxides (“NO x ”), carbon monoxide

5026(“CO”), particulate matter (“PM”), and sulfur oxides such as

5035sulfur dioxi de. The primary cause of the air emissions from the

5047new unit will be the combustion of natural gas and distillate

5058oil in the CTs. Emissions of NO x and CO will result from the

5072combustion process. Emissions of PM and sulfur dioxide result

5081from trace impur ities in the fuel itself. (PEF Ex. 6, Osbourn

5093at 4 - 5; Tr. 35 - 37).

510136. Air emissions from Power Block 4 will be minimized

5111through the inherent efficiency of the combined cycle

5119technology, as well as the use of natural gas and light oil, use

5132of combustio n controls, and use of post - combustion control

5143technology for nitrogen oxide emissions. Natural gas is the

5152cleanest of fossil fuels and contains minimal amounts of

5161impurities. Light oil is also very low in impurities and its

5172use will be limited to up to 1,000 hours per year per combustion

5186turbine. Natural gas and light oil burn very efficiently, thus

5196minimizing the formation of air pollutants. Emissions are also

5205minimized through the use of advanced combustion control

5213technology in the combustion turbin e, specifically dry, low NO x

5224combustion controls for firing natural gas, and use of water

5234injection when firing light oil. A post - combustion control

5244technology, selective catalytic reduction (“SCR”) will be used

5252to further reduce NO x emissions from Power Block 4. (PEF Ex. 6,

5265Osbourn at 5 - 6; Tr. 35).

527237. The Hines Power Block 4 is required to meet best

5283available control technology (“BACT”) requirements, which limits

5290air pollution emission rates. The Project must also comply with

5300a mbient air quality standards (“AAQS”) and prevention of

5309significant deterioration (“PSD”) increment standards, which

5315establish levels of air quality which must be met. (PEF Ex. 6,

5327Osbourn at 6 - 7; PEF Ex. 1 at 3.5 to 3 - 6; FDEP Ex. 2 at 6, 17).

534738. Hines Power Block 4 is required to undergo PSD review

5358because it is a new source of air pollution that will emit some

5371air pollutants above the threshold amounts established under the

5380PSD program. PSD review was required for air emissions of PM,

5391sulfur dioxide, NO x , CO, and sulfuric acid mist because these

5402emissions are greater than the established PSD thresholds. (PEF

5411Ex. 6, Osbourn at 7).

541639. The BACT analysis for Hines Power Block 4 is part of

5428the evaluation of air emissions control technology under the P SD

5439regulations and is applicable to all pollutants for which PSD

5449review is required. BACT is a pollutant - specific emission

5459standard that provides the maximum degree of emission reduction,

5468after taking into account the energy, environmental, and

5476economic i mpacts and other costs. (PEF Ex. 6, Osbourn at 6 - 7;

5490FDEP Ex. 2 at 6).

549540. For NO x , FDEP has preliminarily determined for this

5505facility a BACT emission limit of 2.5 parts per million when

5516firing natural gas, and 10 parts per million when firing low

5527su lfur fuel oil. These emission levels will be achieved by the

5539use of dry low NO x combustion technology when firing natural gas,

5551use of water injection when firing fuel oil, and use of SCR

5563technology. (PEF Ex. 6, Osbourn at 8; FDEP Ex. 2 at 9, 21,

5576Table 4) .

557941. Emissions of carbon monoxide will be controlled using

5588good combustion techniques. Sulfur dioxide emissions, including

5595sulfuric acid mist, will be controlled through the use of clean

5606fuels. Particulate matter emissions will be controlled through

5614the use of clean fuels, natural gas, and low sulfur fuel oil.

5626Fuel oil firing will be limited to a maximum of about 1,000

5639hours per year. (PEF Ex. 6, Osbourn at 7 - 9; PEF Ex. 10, Slide

565415; Tr. 36 - 37).

565942. The air emissions from Power Block 4 cannot be

5669permitted at a level that would cause or contribute to a

5680violation of federal and state AAQS for the six criteria air

5691pollutants or PSD increments for sulfur dioxide, NO x, and PM.

5702The PSD increments refer to the amount of incremental air

5712quality deterior ation allowed from a new air pollution source.

5722Polk County is classified as a Class II area for PSD purposes.

5734The nearest Class I PSD area within which limited increases in

5745air pollutant concentrations are allowed is the Chassahowitzka

5753National Wildernes s Area. (PEF Ex. 6, Osbourn at 9 - 11; FDEP Ex.

57672 at 6 - 8, 16 - 17).

577543. Air emissions from Power Block 4 were principally

5784analyzed for emissions from fuel oil firing as representing the

5794maximum air quality impact. The air quality impact analysis was

5804perfo rmed using approved air quality models and five years of

5815historical hourly meteorological data. This analysis indicated

5822that Power Block 4 will not cause any violations of federal or

5834state AAQS and will comply with applicable PSD Class II and

5845Class I incr ements. The maximum impact of the Project was

5856estimated to be well below the applicable PSD Class II

5866increments. Maximum ambient air impacts were also estimated to

5875be well below the applicable AAQS. Using worst case air

5885emissions during oil firing, it w as shown that the Project

5896impacts would be less than the PSD Class I increments, as well

5908as less than the Class I significant impact levels, and

5918therefore were concluded not to be significant in the PSD Class

5929I area. (PEF Ex. 6, Osbourn at 8 - 14, Exs. SO - 3 and SO - 4; FDEP

5948Ex. 2 at 7 - 8, 16 - 17).

595744. Air emissions from Power Block 4 are not expected to

5968have any impact on vegetation or to cause any growth - related air

5981quality impacts. The results of the visibility impact analysis

5990of the Project’s emissions in t he nearest PSD Class I area

6002demonstrated no adverse impact on visibility at that location

6011due to Power Block 4. (PEF Ex. 6, Osbourn at 14 - 15; FDEP Ex. 2

6027at 6 - 7, 17).

6032Noise

603345. Noise impacts during operation of Power Block 4 were

6043shown not to be signifi cant. Noise monitoring was originally

6053conducted at various locations around the Hines Energy Complex

6062site prior to construction and operation of Power Block 1.

6072Additional noise monitoring was conducted at these locations in

60812000 and 2004 during the permi tting of Power Blocks 2 and 4, to

6095determine any changes since the original permitting. There are

6104only a few isolated rural residences in the land area

6114surrounding the site. The nearest residence is about 2.5 miles

6124from the proposed Power Block 4. Indust rial activities in the

6135surrounding area result in considerable traffic on nearby roads,

6144causing noise levels to exceed the EPA guideline of 55 dBA.

6155Without the area traffic, ambient noise levels meet the EPA

6165guidelines. (PEF Ex. 1 at 2 - 65 to 2 - 72). Usin g a conservative

6181approach which tends to overstate the Project impacts, noise

6190impacts due to operation of Power Block 4 would increase by less

6202than 2 dBA at the nearest receptor and will not be significant.

6214Therefore, the Project will meet applicable nois e criteria and

6224no significant noise impacts will occur as a result of the

6235Project. (PEF Ex. 6, Osbourn at 15 - 16; PEF Ex. 10, Slide 23;

6249PEF Ex. 1 at 5 - 9 to 5 - 12).

6260Land Use and Socioeconomic Impacts

626546. The Plant Island, where Power Block 1 is in operatio n

6277and where Power Block 4 will be constructed, is located near the

6289southern end of the site. The northern boundary of the Plant

6300Island is about two miles south of CR 640. The western limit of

6313the City of Fort Meade is about 3.9 miles east of the Plant

6326Is land, and the unincorporated community of Homeland is more

6336than 3.5 miles northeast of the Plant Island. The nearest

6346residential use is three homes located approximately 2.5 miles

6355from the southern boundary of the Plant Island. Otherwise, the

6365entire area surrounding the proposed power plant site consists

6374of existing or former phosphate mines. The site is buffered

6384from surrounding populations at Homeland and Fort Meade by an

6394extensive buffer area on the eastern perimeter of the site.

6404There has been almo st no change in land use and very little

6417change in the landscape in the area of the Hines Energy Complex

6429since the original site certification. (PEF Ex. 6, Zwolak at 5 -

64416).

644247. There have not been any changes in the area

6452surrounding the Hines Energy Com plex that would change the land

6463use and socio - economic conclusions reached in the Final Order of

6475Certification issued for the site by the Siting Board on

6485January 27, 1994. The most significant change has been the

6495completion of another nearby power plant a pproximately three

6504miles southeast of the Hines site. (PEF Ex. 6, Zwolak at 6).

651648. No land use or socio - economic impacts will be

6527associated with construction of Power Block 4 that were not

6537previously addressed in the Final Order of Certification for the

6547Hines Energy Complex in 1994. (PEF Ex. 6, Zwolak at 6 - 8).

656049. The land use impacts from development and construction

6569of Power Block 4 will be quite minimal, and the economic

6580benefits will be substantial. Current operating employment at

6588the Hines Energ y Complex is 29. The staffing level at the plant

6601is expected to increase by six employees with the addition of

6612Power Block 4. Annual payroll was $2.7 million in 2002. The

6623annual payroll will increase by about $493,000 when Power Block

66344 becomes operatio nal in 2007. (PEF Ex. 6, Zwolak at 8).

664650. The estimated increase in property taxes for Power

6655Block 4 is $5.0 million. Over one - half of this revenue goes to

6669support the Polk County school system. (PEF Ex. 6, Zwolak at 8;

6681PEF Ex. 1 at 7 - 1).

6688Agency Posi tions and Stipulations

669351. The FDEP, the Florida Department of Community Affairs,

6702the FDOT, and the SWFWMD each prepared written reports on the

6713Project. (FDEP Ex. 2). Each of these agencies either

6722recommended approval of Hines Power Block 4 or otherwis e did not

6734object to certification of the proposed power plant. The FDEP

6744has proposed a series of Conditions of Certification for the

6754Project that incorporate the recommendations of the various

6762reviewing agencies. At hearing, the FDEP added one additional

6771condition related to air emissions monitoring. (Tr. 54 - 55).

6781PEF states that it can comply with these Conditions of

6791Certification in the design, construction, and operation of the

6800Hines Power Block 4. (Tr. 21, 56). No state, regional, or

6811local agency h as recommended denial of certification of the

6821Project or has otherwise objected to certification of the

6830Project. (PEF Ex. 4).

683452. Subject to compliance with the proposed conditions of

6843certification, the proposed design of Hines Power Block 4 offers

6853re asonable assurance that the standards of the FDEP and other

6864affected regulatory agencies will be met and that the operation

6874safeguards are technically sufficient for the protection of the

6883citizens of the state. The Hines Power Block 4, as proposed,

6894minimi zes through reasonable and available methods the adverse

6903effects on human health, the environment, the ecology of the

6913land and its wildlife, and the ecology of state waters and their

6925aquatic life. (FDEP Ex. 1 at 28; Tr. 57 - 59).

6936CONCLUSIONS OF LAW

693953. The Division of Administrative Hearings has

6946jurisdiction over the parties to and the subject matter of this

6957proceeding. §§ 120.569, and 120.57(1), 403.508(3), Fla. Stat.

696554. This proceeding was conducted to implement the

6973purposes a nd intent of the Florida Electrical Power Plant Site

6984Certification process. The purposes of that process are to

6993assure the citizens of Florida that the construction and

7002operation safeguards of the PEF Hines Power Block 4 Project are

7013technically sufficient to protect their health and welfare and

7022to effect a reasonable balance between the need for the Project

7033and the environmental impacts on air and water quality, fish and

7044wildlife, and the water resources and other resources of the

7054State resulting from the Project’s construction and operation.

7062§ 403.502(1) - (2), Fla. Stat.

706855. In accordance with Chapters 120 and 403, Florida

7077Statutes, and Florida Administrative Code Chapter 62 - 17, proper

7087public notice was accorded all persons, entities, and parties

7096entit led thereto. All the necessary and required governmental

7105agencies were parties to this proceeding or were otherwise

7114afforded adequate opportunity to participate in this proceeding.

7122All required reports by State, regional, and local agencies were

7132complete d and presented.

713656. The FPSC, in an Order dated November 23, 2004, has

7147determined a need exists for the 530 MW (nominal) of electrical

7158generating capacity to be supplied by the Project, pursuant to

7168the requirements of Section 403.519, Florida Statutes .

717657. The Governor and Cabinet of the State of Florida,

7186sitting as the Siting Board, determined in an order dated

7196January 26, 1993, that the Hines Energy Complex site is

7206consistent with the existing land use plans and zoning

7215ordinances of Polk County, pursuant to the procedures set out in

7226Section 403.508(1) and (2), Florida Statutes. The addition of

7235Power Block 4 will not expand the existing boundaries of the

7246Hines Energy Center or introduce a new fuel not previously

7256certified for the Hines Energy Comp lex. Further consideration

7265of consistency with local land use plans and zoning ordinances

7275is not required for this Supplemental Site Certification

7283Application, pursuant to Section 403.517(3), Florida Statutes.

729058. The FDEP and the other participating ag encies have all

7301recommended or otherwise do not object to certification of the

7311Hines Power Block 4 for construction and operation, subject to

7321this Recommended Order and to the Conditions of Certification

7330recommended by FDEP. (FDEP Ex. 2). PEF has indicat ed its

7341acceptance of these proposed conditions of certification. As a

7350result, none of the parties to this proceeding oppose

7359certification of the Hines Power Block 4.

736659. Based upon a preponderance of the evidence presented

7375at the certification hearing h eld on March 23, 2005, PEF has met

7388its burden of proving that the Hines Power Block 4 Project

7399should be certified as proposed. Competent, substantial

7406evidence presented at the hearing demonstrates that the

7414construction and operational safeguards for the H ines Power

7423Block 4 Project are technically sufficient to protect the health

7433and welfare of the citizens of Florida and are reasonable and

7444available methods to achieve that protection. If constructed,

7452maintained, and operated in accordance with this Recomm ended

7461Order and the FDEP’s proposed Conditions of Certification, the

7470proposed Project will produce minimal adverse effects on human

7479health, the environment, the ecology of the land and its

7489wildlife, and ecology of state waters and their aquatic life.

7499Cert ification of the Project is consistent with the statutory

7509goal of the Florida Electrical Power Plant Siting Act of

7519providing abundant, low cost electrical energy, and

7526certification will affect a reasonable balance between the

7534environmental and other impact s which might occur and the need

7545for the Project as separately determined by the FPSC.

7554RECOMMENDATION

7555Based on the foregoing Findings of Fact and Conclusions of

7565Law, it is RECOMMENDED that the Governor and Cabinet, sitting as

7576the Siting Board, enter a Fin al Order granting certification to

7587PEF to construct and operate a new 530 MW natural gas - fired

7600electrical power plant (Hines Power Block 4 Project) in Polk

7610County, Florida, in accordance with the Conditions of

7618Certification, FDEP Exhibit 2.

7622DONE AND ENT ERED this 5th day of April, 2005, in

7633Tallahassee, Leon County, Florida.

7637S

7638CHARLES A. STAMPELOS

7641Administrative Law Judge

7644Division of Administrative Hearings

7648The DeSoto Building

76511230 Apalachee Parkway

7654Tallahassee, Florida 32399 - 3060

7659(850) 488 - 9675 SUNCOM 278 - 9675

7667Fax Filing (850) 921 - 6847

7673www.doah.state.fl.us

7674Filed with the Clerk of the

7680Division of Administrative Hearings

7684this 5th day of April, 2005.

7690COPIES FURNISHED:

7692Douglas S. Roberts, Esquire

7696Hopping Green & Sam s, P.A.

7702Post Office Box 6526

7706Tallahassee, Florida 32314 - 6526

7711Scott A. Goorland, Esquire

7715Department of Environmental Protection

77193900 Commonwealth Boulevard

7722Mail Station 35

7725Tallahassee, Florida 32399 - 3000

7730Martha A. Moore, Esquire

7734Southwest Florida Water Management District

77392379 Broad Street

7742Brooksville, Florida 34604 - 6899

7747Michael Duclos, Esquire

7750Polk County Attorney’s Office

7754Post Office Box 9005

7758Bartow, Florida 33831 - 9005

7763James V. Antista, Esquire

7767Fish and Wildlife Conservation Commission

7772620 South Mer idian Street

7777Tallahassee, Florida 32399 - 1600

7782Sheauching Yu, Esquire

7785Department of Transportation

7788Haydon Burns Building

7791605 Suwannee Street, Mail Station 58

7797Tallahassee, Florida 32399 - 0450

7802Craig Varn, Esquire

7805Department of Community Affairs

78092555 Shuma rd Oak Boulevard

7814Tallahassee, Florida 32399 - 2100

7819Wm. Cochran Keating IV, Esquire

7824Florida Public Service Commission

78282450 Shumard Oak Boulevard

7832Tallahassee, Florida 32399 - 0850

7837Norman White, Esquire

7840Central Florida Regional Planning Council

7845555 East Chur ch Street

7850Bartow, Florida 33830

7853Steven Palmer

7855Siting Coordination Office

7858Department of Environmental Protection

78622600 Blair Stone Road

7866Tallahassee, Florida 32399

7869Raquel A. Rodriguez, General Counsel

7874Office of the Governor

7878The Capitol, Suite 209

7882Tall ahassee, Florida 32399 - 1001

7888Kathy C. Carter, Agency Clerk

7893Department of Environmental Protection

7897Office of General Counsel

7901Mail Station 35

79043900 Commonwealth Boulevard

7907Tallahassee, Florida 32399 - 3000

7912NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

7918All parties ha ve the right to submit written exceptions within

792915 days from the date of this Recommended Order. Any exceptions

7940to this Recommended Order should be filed with the agency that

7951will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 06/09/2005
Proceedings: Final Order of Certification filed.
PDF:
Date: 06/07/2005
Proceedings: Agency Final Order
PDF:
Date: 04/05/2005
Proceedings: Recommended Order
PDF:
Date: 04/05/2005
Proceedings: Site Certification Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 04/05/2005
Proceedings: Site Certification Recommended Order (hearing held March 23, 2005). CASE CLOSED.
PDF:
Date: 03/29/2005
Proceedings: (Proposed) Recommended Order filed.
PDF:
Date: 03/29/2005
Proceedings: Notice of Filing Joint Proposed Recommended Order filed.
Date: 03/29/2005
Proceedings: Transcript filed.
Date: 03/23/2005
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 03/17/2005
Proceedings: Notice of Service of Written Direct Testimony and Exhibits (filed by D. Roberts).
PDF:
Date: 03/17/2005
Proceedings: (Joint) Pre-hearing Stipulation filed.
PDF:
Date: 02/18/2005
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Certification Hearing on Progress Energy Florida Hines Energy Complex Application to Construct and Operate an Electrical Power Plant Located in Polk County, Florida filed.
PDF:
Date: 02/16/2005
Proceedings: Department of Environmental Protection`s Notice of Filing of Written Analysis filed.
PDF:
Date: 02/03/2005
Proceedings: Progress Energy Florida`s Notice of Amendment of Site Certification Application filed.
PDF:
Date: 12/23/2004
Proceedings: Notice of Filing Certified Proof of Publication for Notice of Filing of Application for Electrical Power Plant Site Certification for Construction and Operation of Site addition to Electrical Power Plant Facility Located Near Bartow, Florida filed.
PDF:
Date: 12/23/2004
Proceedings: Notice of Appearance (filed by D. Roberts, Esquire).
PDF:
Date: 12/15/2004
Proceedings: Southwest Florida Water Management District`s Notice of Filing Agency Report filed.
PDF:
Date: 11/22/2004
Proceedings: Notice of Insufficiency filed.
PDF:
Date: 10/22/2004
Proceedings: Notice of Insufficiency filed.
PDF:
Date: 10/22/2004
Proceedings: Progress Energy Florida`s Notice of Filing Responses to Notice of Insufficiency of the Florida Department of Environmental Protection filed.
PDF:
Date: 10/12/2004
Proceedings: Notice of Appearance (filed by M. Duclos, Esquire).
PDF:
Date: 10/11/2004
Proceedings: Southwest Florida Water Management District`s Preliminary Statement of Issues (filed via facsimile).
PDF:
Date: 10/06/2004
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 10/06/2004
Proceedings: Notice of Hearing (hearing set for March 23 and 24, 2005; 1:00 p.m.; Bartow, FL).
PDF:
Date: 10/05/2004
Proceedings: Order Altering Times. (time frames are altered as set forth in the Proposed Schedule for Review of Site Certification, subject to the ruling on any objection filed within five days from this date)
PDF:
Date: 10/04/2004
Proceedings: Polk County, Florida, a Political Subdivision of the State of Florida Notice of Intent to be a Party filed.
PDF:
Date: 10/01/2004
Proceedings: Joint Response to Initial Order, Filing of Scedule, and Motion and Stipulation for Alteration of Time Frames (filed via facsimile).
PDF:
Date: 09/24/2004
Proceedings: Notice of Insufficiency (filed by S. Goorland via facsimile).
PDF:
Date: 09/23/2004
Proceedings: Southwest Florida Water Management District`s Notice of Intent to be a Party (filed via facsimile).
PDF:
Date: 09/20/2004
Proceedings: Department of Transportation`s Notice of Intent to be a Party (filed via facsimile).
Date: 09/17/2004
Proceedings: Supplemental Site Certification Application (two volumes) filed.
PDF:
Date: 09/17/2004
Proceedings: Notice of Filing of Site Certification Application filed by S. Goorland.
PDF:
Date: 08/26/2004
Proceedings: Notice of Distribution of Supplemental Site Certification Application to PA 92-33 filed.
PDF:
Date: 08/20/2004
Proceedings: Statement of Completeness (filed by S. Goorland via facsimile).
PDF:
Date: 08/12/2004
Proceedings: Initial Order.
PDF:
Date: 08/12/2004
Proceedings: Notice of Filing of List of Affected Agencies (filed via facsimile).
PDF:
Date: 08/12/2004
Proceedings: Notice of Receipt of Power Plant Siting Application and Request for Assignment of Administrative Law Judge (filed via facsimile).

Case Information

Judge:
CHARLES A. STAMPELOS
Date Filed:
08/12/2004
Date Assignment:
03/07/2005
Last Docket Entry:
06/09/2005
Location:
Bartow, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
EPP
 

Counsels

Related Florida Statute(s) (7):