04-003209EPP In Re: New Hope Power Partnership Okeelanta Cogeneration Facilities Power Plant Siting Application No. Pa 04-46 vs. *
 Status: Closed
Recommended Order on Thursday, March 31, 2005.


View Dockets  
Summary: The uncontroverted evidence admitted during the local public certification hearing on New Hope Power`s power plant expansion project supported the approval of the project.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: NEW HOPE POWER )

14PARTNERSHIP OKEELANTA )

17COGENERATION FACILITIES POWER ) Case No. 04 - 3209EPP

26PLANT SITING APPLICATION NO. PA )

3204 - 46. )

36_______________________________ )

38RECOMMENDED O RDER OF CERTIFICATION

43Pursuant to notice, the Division of Administrative

50Hearings, by its duly - designated Administrative Law Judge,

59Charles A. Stampelos, held a certification hearing in the above -

70styled case on March 21, 2005, in Palm Beach County, Florid a.

82APPEARANCES

83For Petitioner New Hope Power Partnership (”New Hope”):

91David S. Dee, Esquire

95Landers & Parsons

98310 West College Avenue

102Tallahassee, Florida 32301

105For the Florida Department of Environmental Protection:

112Scott A. Go orland, Esquire

117Department of Environmental Protection

1213900 Commonwealth Boulevard

124Mail Station 35

127Tallahassee, Florida 32399

130STATEMENT OF THE ISSUE

134The issue to be determined in this case is whether the

145Governor and Cabinet, sitting as the Siting Board, should grant

155certification to New Hope for the expansion of the Okeelanta

165cogeneration facility to a total net steam electrical generating

174capacity of 140 megawatts (”MW”).

179PRELIMINARY STATEMENT

181On September 3, 2004, New Hope filed an a pplication

191(”Application”) with the Florida Department of Environmental

198Protection (”Department” or ”DEP”) for authorization to

205construct and operate a 65 MW expansion (the ”Expansion Project”

215or ”Project”) of the Okeelanta cogeneration facility in Palm

224Be ach County, Florida. The Okeelanta cogeneration facility

232(”Facility”) is an existing electrical power plant that burns

241biomass ( e.g. , bagasse and wood) to generate 74.9 MW of

252electricity. New Hope’s application is subject to the

260requirements of the Flori da Electrical Power Plant Siting Act

270(”PPSA”), Sections 403.501 - .518, Florida Statutes. (All

278statutory references are to the 2004 codification of the Florida

288Statutes.) The Department transmitted New Hope’s Application to

296the Division of Administrative H earings for appropriate

304proceedings under the PPSA. In compliance with Section

312403.508(3), Florida Statutes, the certification hearing (the

319”Certification Hearing”) in this case was scheduled for

327March 21, 2005.

330On March 9, 2005, a ”Prehearing Stipulatio n for Land Use

341and Certification Hearings” (”Prehearing Stipulation”) was filed

348by New Hope, DEP, the Florida Department of Community Affairs

358(”DCA”), the Florida Department of Transportation (”DOT”), the

366Florida Public Service Commission (”PSC”), the Flor ida Fish and

376Wildlife Conservation Commission (”FFWCC”), the South Florida

383Water Management District (”SFWMD”), the Treasure Coast Regional

391Planning Council (”TCRPC”), and Palm Beach County (the

399”County”). In the Prehearing Stipulation, all of the

407signato ries either recommended certification of the Project, or

416did not dispute, or took no position concerning the

425certification of the Project, provided that the Project is

434constructed and operated in compliance with the Conditions of

443Certification. Prehearing Stipulation at 10 - 17.

450On March 21, 2005, a Certification Hearing was conducted in

460compliance with Section 403.508(3), Florida Statutes. At the

468Certification Hearing, New Hope called one witness, Kennard

476Kosky (accepted as an expert concerning the permit ting of

486electrical power plants and air pollution control). New Hope

495introduced Exhibits 1 - 39 (Ex.) into evidence without objection.

505New Hope’s Amended Exhibit List was also admitted into evidence

515as New Hope Power Exhibit A, and New Hope was permitted t o

528supplement the record with the transcript of the land use

538hearing in this case.

542By Order dated March 3, 2005, the Administrative Law Judge

552granted New Hope’s request to take official recognition of the

562”Amended Final Order Granting Determination of Ne ed” (dated

571November 18, 2004) of the PSC. This document was included with

582the exhibits introduced into evidence at the Certification

590Hearing. Ex. 22.

593The Department called one witness, Hamilton S. Oven

601(accepted as an expert concerning power plant site certification

610in the State of Florida). The Department introduced three

619exhibits (DEP Exhibits 1 - 3) into evidence, without objection.

629No one contested the evidence presented by New Hope and DEP

640at the Certification Hearing. None of the signatories to the

650Prehearing Stipulation participated at the Certification

656Hearing, except New Hope and DEP. Except for New Hope and DEP,

668the parties to this proceeding did not call any witnesses or

679proffer any exhibits.

682The public was given an opportunity to provi de oral and

693written comments at the Certification Hearing. However, no

701members of the public appeared or testified at the Certification

711Hearing. No one testified or proffered any exhibits in

720opposition to the Project at the Certification Hearing.

728The on e - volume Transcript (T) of the Certification Hearing

739was filed with the Division of Administrative Hearings on

748March 25, 2005, and the parties were allowed until March 28,

7592005, to submit proposed recommended orders. New Hope and DEP

769timely filed a joint proposed recommended order on March 28,

7792005. No other party filed a proposed recommended order.

788FINDINGS OF FACT

791The Applicant

7931. The Applicant, New Hope Power Partnership, is a Florida

803partnership that owns the existing Okeelanta cogeneration

810Facility . Ex. 1 at 1 - 1, 3 - 1. New Hope will also own the

827Project. See id.

830The Site

8322. The Facility is located in an unincorporated area in

842western Palm Beach County, Florida. Ex. 1 at 2 - 1; Ex. 4 at 6; T

85817. It is approximately six miles south of South Bay and two

870miles west of U.S. Highway 27. Id. The Facility is located on

882a site (the ”Site”) that is approximately 82.1 acres in size.

893Ex. 1 at 2 - 1; Ex. 4 at 8; T 19. The Site is adjacent to

910Okeelanta Corporation’s existing sugar mill, sugar refinery, and

918su garcane fields. Ex. 1 at 2 - 1; Ex. 4 at 6; T 17, 20.

934The Surrounding Area

9373. There are large buffer areas around the Site. See Ex.

9481 at 2 - 1, 2 - 2, 2 - 4; Ex. 4 at 6; T 17 - 18. Almost all of the land

972within five miles of the Site is used for agricultural pu rposes

984(sugarcane farming). Id.

9874. The community nearest the Site is South Bay. Ex. 1 at

9992 - 2; Ex. 4 at 6; T 17. The nearest home is more than 3.5 miles

1016northeast of the Site. Ex. 1 at 2 - 4; Ex. 5 at 9; T 17 - 18.

10345. The Facility is adjacent to an exis ting electrical

1044substation (Florida Power & Light Company’s Okeelanta

1051Substation). See Ex. 1 at 1 - 2. An existing electrical

1062transmission line connects the Facility to the substation.

1070Ex. 1 at 3 - 1.

1076The Existing Facility

10796. The Facility uses biomass fu els ( e.g. , bagasse from the

1091sugar mill; clean wood waste) to generate steam and up to 74.9

1103MW of electricity (net). Ex. 1 at 1 - 1, 3 - 1; Ex. 4 at 6 - 7; T 18.

1124The Facility supplies steam to the sugar mill during the

1134sugarcane harvest (October through March) and it supplies steam

1143to the refinery throughout the year. Ex. 1 at 1 - 2, 3 - 1; Ex. 4

1160at 7; see T 18. Excess steam from the Facility is used to

1173generate electricity, which is sold to utility companies,

1181including Florida Power & Light Company. Ex. 1 - 3; E x. 4 at 7;

1196See T 50 - 51.

12017. The existing Facility includes three steam boilers, one

1210steam turbine/electrical generator, a cooling tower, an

1217electrical switchyard, materials handling and storage facilities

1224for biomass fuels, and ancillary equipment. Ex. 1 at 2 - 1, 3 - 1;

1239Ex. 4 at 7; T 20 - 21.

1247The Expansion Project

12508. The Expansion Project will increase the Facility’s

1258electrical generating capacity by 65 MW (net), creating a total

1268generating capacity of 140 MW (net). Ex. 1 at 1 - 1, 1 - 3, 2 - 1;

1286Ex. 4 at 7; T 18 . The Expansion Project will involve the

1299installation of a new turbine/electrical generator, a cooling

1307tower, and related equipment at the Site. Ex. 1 at 1 - 3, 2 - 1;

1323Ex. 4 at 8; T 19.

1329Construction of the Expansion Project

13349. Approximately 0.5 acres of t he Site will be occupied by

1346the new equipment that will be installed for the Expansion

1356Project. Ex. 1 at 2 - 1; Ex. 4 at 8; T 19. The construction of

1372the Project will occur in disturbed upland areas that already

1382are used for industrial operations. Ex. 1 a t 3 - 2, 4 - 1; Ex. 4 at

14009; T 20. No construction will take place in any wetland,

1411wildlife habitat, environmentally sensitive area, or 100 - year

1420flood plain. Ex. 1 at 2 - 2, 2 - 18, 4 - 1; Ex. 4 at 9; T 20.

144010. No new electrical transmission lines will need to be

1450built to accommodate the additional electrical power generated

1458by the Expansion Project. See Ex. 1 at 3 - 1, 6 - 1.

147211. During construction, there will be a temporary

1480increase in sound levels due to the heavy equipment associated

1490with the construction pr ocess. Ex. 1 at 4 - 9 through 4 - 10; Ex. 5

1507at 9; T 42 - 43. Given the remote location of the Site, the

1521sounds generated by the construction of the Expansion Project

1530will not interfere with human activities or otherwise cause a

1540nuisance at any residential loca tions. Id.

154712. The construction of the Expansion Project will result

1556in a temporary increase in traffic on some roads near the Site,

1568but these roads will continue to operate at acceptable traffic

1578levels. Ex. 1 at 4 - 8 through 4 - 9; Ex. 5 at 9; T 42.

1595Oper ation of the Expansion Project

160113. The Facility currently operates at its full capacity

1610during the sugarcane harvest. See Ex. 30, Technical Evaluation

1619at 2. The Expansion Project will enable the Facility to operate

1630at its full capacity year - round. See Ex. 1 at 3 - 1 through 3 - 2;

1648Ex. 30, Technical Evaluation at 2. Although the Facility will

1658generate more electricity after the Expansion Project is

1666completed, the basic operation of the Facility will not change.

1676Ex. 4 at 10; Ex. 5 at 6; T 22.

168614. The Faci lity has a water use permit issued by the

1698South Florida Water Management District, which authorizes the

1706Facility to use water from the Miami/North New River Canal

1716System, the surficial aquifer, and the Floridan aquifer. Ex. 1

1726at 3 - 11; Ex. 5 at 7; T 40 - 41. The Okeelanta Corporation also

1742may provide water to the Facility, in accordance with the SFWMD

1753water use permit for the Okeelanta Corporation’s sugar mill.

1762Ex. 5 at 7; T 41. After the Expansion Project is completed, the

1775amount of water used by the Faci lity will increase, commensurate

1786with the increased use of the Facility. Ex. 5 at 7; DEP Ex. 2,

1800Staff Analysis Report at 3; T 41. The additional water will be

1812obtained from the cooling pond/rock pit located at the adjacent

1822sugar mill. Id. In March 2005, the SFWMD issued a water use

1834permit that allows the Okeelanta Corporation to increase the

1843amount of water provided to the Facility from 0.4 mgd to 2.0

1855mgd. Ex. 37; see T 41.

186115. The Facility’s stormwater and process water are routed

1870to a 600 - acre area that is divided into four percolation basins.

1883Ex. 1 at 3 - 16; Ex. 5 at 8; T 41. Each basin is used on a

1901rotating basis -- i.e. , the basin is used for percolation for one

1913year and then it is used for growing sugarcane for three years.

1925Ex. 5 at 8; T 41. Eac h percolation basin is designed to hold

1939all of the Facility’s process water, plus all of the contact and

1951non - contact stormwater runoff from a 100 - year, three - day storm

1965event. Id. The Facility does not discharge any stormwater or

1975process water to any surf ace water. Ex. 1 at 5 - 9; Ex. 5 at 8; T

199341 - 42. The Facility’s use of the percolation ponds has not

2005caused and is not expected to cause any violations of any ground

2017water quality standards. Ex. 5 at 8.

202416. The Facility generates fly ash and bottom ash from the

2035combustion of biomass fuels. Ex. 1 at 3 - 16, 5 - 10; Ex. 5 at 9;

2052T 42. These materials are taken to a landfill for disposal. Id.

206417. The operation of the Expansion Project will not have

2074any significant impacts on traffic. Ex. 1 at 5 - 17; Ex. 5 a t 9;

2090T 42. The local roads will continue to operate at an acceptable

2102level of service. Id.

2106Air Quality Regulations

210918. The Facility must comply with New Source Performance

2118Standards (”NSPS”) and Best Available Control Technology

2125(”BACT”) requirements, b oth of which impose strict limits on the

2136Facility’s airborne emissions. See Ex. 1 at 3 - 5; Ex. 30,

2148Technical Evaluation at 3. The Facility also must comply with

2158Ambient Air Quality Standards (”AAQS”) and Prevention of

2166Significant Deterioration (”PSD”) sta ndards, which establish

2173criteria for the protection of ambient air quality. Id. The

2183Facility previously was reviewed and approved under the PSD

2192program. Ex. 1 at 3 - 5; Ex. 5 at 6; Ex. 30, Technical Evaluation

2207at 2; T 39 - 40.

221319. The DEP has determined t hat the Expansion Project is

2224not subject to PSD pre - construction review. Ex. 5 at 6; Ex. 30,

2238Technical Evaluation at 5; T 38. The cooling towers will be the

2250only new source of air pollution associated with the Expansion

2260Project. Ex. 1 at 3 - 5; Ex. 5 at 6 ; T 38. The water droplets

2276leaving the cooling tower will evaporate, causing small amounts

2285of particulate matter to enter the atmosphere near the Site.

2295Ex. 5 at 6; T 38. However, the emissions from the cooling tower

2308are so small that the cooling tower i s exempt from the

2320permitting requirements established by the DEP. Id.

2327Best Available Control Technology

233120. A BACT determination is required for each pollutant

2340for which PSD review is required. Ex. 1 at 3 - 5; Ex. 5 at 7; DEP

2357Ex. 2, Staff Analysis Report at 15. BACT is a pollutant -

2369specific emission limit that provides the maximum degree of

2378emission reduction, after taking into account the energy,

2386environmental, and economic impacts and other costs. Ex. 1 at

23963 - 5; Fla. Admin. Code R. 62 - 210.200(38).

240621. As part of its BACT analyses for the Facility, DEP

2417determined that mechanical cyclone dust collectors and an

2425electrostatic precipitator (”ESP”) will control the Facility’s

2432emissions of particulate matter, a selective non - catalytic

2441reduction system (”SNCR” ) will control oxides of nitrogen

2450(”NOx”), use of low - sulfur fuels will control sulfur dioxide

2461emissions, and proper facility design and operating methods will

2470control other pollutants. Ex. 1 at 3 - 6 through 3 - 8; Ex. 30,

2485Draft Permit at D - 1; T 40. Accordi ngly, these air pollution

2498control systems and techniques are utilized at the Facility.

2507Id.

250822. The Facility also uses an array of continuous

2517emissions monitors to ensure that the Facility is continuously

2526in compliance with the BACT emission limits. Ex. 1 at 5 - 14;

2539Ex. 30, Draft Permit at E - 1 through E - 2.

2551Protection of Ambient Air Quality

255623. The EPA has adopted ”primary” and ”secondary” National

2565Ambient Air Quality Standards (”NAAQS”). See Ex. 1 at 2 - 21.

2577The primary NAAQS were promulgated to protec t the health of the

2589general public with an adequate margin of safety. See Ex. 1 at

26012 - 21; see also 42 U.S.C.A. § 7409(b) (1997). The secondary

2613NAAQS were promulgated to protect the public welfare, including

2622vegetation, soils, visibility and other factors, from any known

2631or anticipated adverse effects associated with the presence of

2640pollutants in the ambient air. Id. Florida has adopted EPA’s

2650primary and secondary NAAQS, and has adopted some Florida AAQS

2660(”FAAQS”) that are more stringent than EPA’s NAAQS. See id.

267024. The Facility’s potential impacts on ambient air

2678quality were evaluated by DEP, based on the continuous operation

2688of the Facility at full load, following completion of the

2698Project. Ex. 30, Technical Evaluation at 4. DEP concluded that

2708the maximum impacts from the Facility will not cause or

2718contribute to any violations of AAQS. Ex. 1 at 5 - 10 through 5 -

273314; Ex. 5 at 6 - 7; Ex. 30, Technical Evaluation at 4; Ex. 5 at 6;

2750T 39.

2752Other PSD Analyses

275525. The PSD program provides protection for those areas

2764that have good air quality. See Ex. 1 at 2 - 22; Ex. 30,

2778Technical Evaluation at 3 - 4. Different areas of Florida have

2789been designated as PSD ”Class I” or ”Class II” areas, depending

2800upon the level of protection that is to be provided under the

2812PSD p rogram. Id. In this case, the Project is located in a PSD

2826Class II area. Id. The nearest PSD Class I area is the

2838Everglades National Park (”Everglades”), which is approximately

284592 kilometers (”km”) south of the Site. Ex. 1 at 2 - 22.

285826. The DEP’s ana lyses demonstrate that the Facility’s

2867impacts on ambient air quality will not violate any applicable

2877PSD requirement for the Class I and Class II areas. Ex. 1 at 5 -

289214; Ex. 5 at 6; Ex. 30, Technical Evaluation at 4; DEP Ex. 2,

2906Staff Analysis Report at 16 - 17; T 39.

2915Compliance With Air Standards

291927. New Hope has provided reasonable assurance that the

2928Expansion Project and the Facility will comply with all of the

2939applicable air quality standards and requirements. Ex. 5 at 7;

2949Ex. 30; DEP Ex. 2, Staff Analys is Report at 17; T 38 - 40.

2964Environmental Benefits of the Project

296928. The Expansion Project will provide environmental

2976benefits. Ex. 1 at 7 - 3 through 7 - 4; Ex. 5 at 10; T 43 - 44. For

2996example, the Project will be capable of producing approximately

300565 MW ( net) of electricity in Southeast Florida, which needs new

3017electrical generating capacity. Ex. 1 at 7 - 3 through 7 - 4; Ex. 5

3032at 10; T 43 - 44. The Expansion Project will also enhance fuel

3045diversity by using renewable biomass fuels to generate

3053electricity. Id . Over 20 years, the Project may displace the

3064use of approximately 5,600,000 barrels of oil worth nearly

3075$170,000,000 (assuming oil prices of $30 per barrel). Id. In

3087addition, the Expansion Project will beneficially reuse clean

3095wood waste, which otherwi se would likely be placed in a landfill

3107for disposal. Ex. 1 at 7 - 4; Ex. 5 at 10; T 44. The Facility

3123receives wood waste and biomass materials from Miami - Dade

3133County, the Palm Beach County Solid Waste Authority, and

3142approximately 25 private recycling comp anies, thus assisting

3150them with their solid waste management programs. Ex. 5 at 10;

3161T 44. The Facility also burns melaleuca trees that have been

3172removed pursuant to land clearing programs for the eradication

3181of this nuisance species. Ex. 5 at 10.

3189Socioe conomic Benefits of the Project

319529. The Expansion Project will provide jobs for an average

3205of 70 construction workers during the 12 - month construction

3215phase of the Project. Ex. 1 at 7 - 1 through 7 - 2; Ex. 5 at 10;

3233T 43. Approximately $3.5 million will be paid in wages for

3244construction employees working on the Expansion Project. Id.

3252Consistency with Land Use Plans and Zoning Ordinances

326030. The proposed use of the Site is consistent and in

3271compliance with Palm Beach County’s comprehensive land use plan

3280a nd zoning ordinances. Ex. 1 at 2 - 2 through 2 - 4; Ex. 4 at 16;

3298Ex. 23; Ex. 24; Ex. 38; Ex. 39; T 28 - 29. The Facility and

3313Project have both been reviewed and approved by the Palm Beach

3324County Board of County Commissioners. Ex. 4 at 11 - 12; Ex. 23;

3337Ex. 24; T 23 - 25.

3343Compliance with Environmental Standards

334731. New Hope has provided reasonable assurance that the

3356Facility and Project will comply with all of the nonprocedural

3366land use and environmental statutes, rules, policies, and

3374requirements that apply to th e Project, including but not

3384limited to those requirements governing the Project’s impacts on

3393air quality, water consumption, stormwater, and wetlands.

3400Prehearing Stipulation at 24, paragraph 5.B.3.; Ex. 5 at 11; DEP

3411Ex. 2, Staff Analysis Report at 22; T 44 - 45, 60. The location,

3425construction and operation of the Facility and Project will have

3435minimal adverse effects on human health, the environment, the

3444ecology of the State’s lands and wildlife, and the ecology of

3455the State’s waters and aquatic life. Ex . 5 at 12; DEP Ex. 2,

3469Staff Analysis Report at 20; T 45 - 46, 61 - 62. The Facility and

3484Project will not unduly conflict with any of the goals or other

3496provisions of any applicable local, regional or state

3504comprehensive plan. Ex. 4 at 16; Ex. 23; Ex. 24; Ex. 38; Ex.

351739; T 28 - 29. The Conditions of Certification establish

3527operational safeguards for the Facility and Project that are

3536technically sufficient for the protection of the public health

3545and welfare. Ex. 5 at 13; T 46 - 47, 61.

3556Agency Positions and Condit ions of Certification

356332. On November 18, 2004, the PSC issued an Order (No.

3574PSC - 04 - 1105A - FOF - EI) granting New Hope’s petition for

3588determination of need for the Expansion Project. Ex. 22; DEP

3598Ex. 2, Staff Analysis Report at 4 - 6, 12 - 13. The PSC determin ed,

3614consistent with the criteria of Section 403.519, Florida

3622Statutes, that the Expansion Project is needed. Id.

363033. The DEP, DOT, DCA, and SFWMD all recommend

3639certification of the Expansion Project, subject to the

3647Conditions of Certification. Preheari ng Stipulation at 10 - 11,

365713 - 16. New Hope has accepted, and has provided reasonable

3668assurance that it will comply with, the Conditions of

3677Certification. Prehearing Stipulation at 24 - 25, paragraph

3685V.B.4; Ex. 5 at 11 - 12; T 45, 61 - 62.

3697Public Notice of the Ce rtification Use Hearing

370534. On September 29, 2004, New Hope published a ”Notice of

3716Filing of Application for Electrical Power Plant Site

3724Certification” in the Palm Beach Post , which is a newspaper of

3735general circulation published in Palm Beach County, Fl orida.

3744Ex. 31; see also Ex. 5 at 16; T 49.

375435. On October 1, 2004, the Department published ”Notice

3763of Receipt of Application for Power Plant Certification” in the

3773Florida Administrative Weekly . Ex. 35; see also Ex. 5 at 16;

3785T 49.

378736. On February 2, 2 005, New Hope published notice of the

3799Certification Hearing in the Palm Beach Post . Ex. 33; see also

3811Ex. 5 at 16; T 49.

381737. On February 4 and 11, 2005, the Department published

3827notice of the Certification Hearing in the Florida

3835Administrative Weekly . Ex. 36; see also Ex. 5 at 16; T 49.

384838. The public notices for the Certification Hearing

3856satisfy the informational and other requirements set forth in

3865Section 403.5115, Florida Statutes, and Florida Administrative

3872Code Rules 62 - 17.280 and 62 - 17.281(4). Prehearing Stipulation

3883at 24, paragraph V.B.2,3; Ex. 5 at 17; T 49, 63 - 64.

3897CONCLUSIONS OF LAW

390039. The Division of Administrative Hearings has

3907jurisdiction over the parties to and subject matter of this

3917proceeding pursuant to Sections 120.569, 120.57( 1), and 403.508,

3926Florida Statutes.

392840. New Hope and DEP provided timely public notices

3937concerning the Expansion Project and the Certification Hearing,

3945which satisfied the notice requirements contained in the PPSA,

3954Chapter 120, Florida Statutes, and Flori da Administrative Code

3963Chapter 62 - 17. Prehearing Stipulation at 26, paragraph VI.B.3.;

3973Ex. 5 at 16 - 17; Ex. 31; Ex. 33; Ex. 35; Ex. 36; T 49, 63 - 64.

3992All necessary and required governmental agencies participated in

4000the certification process, and the requir ed reports and studies

4010were issued by the DEP and the other agencies in accordance with

4022their statutory duties. DEP Ex. 2, Staff Analysis Report at 12 -

403414, 21 - 22; T 56, 62.

404141. The PSC determined there is a need for the electrical

4052generating capacity to be supplied by the Expansion Project, as

4062required by Sections 403.508(3) and 403.519, Florida Statutes.

4070Ex. 22; DEP Ex. 2, Staff Analysis Report at 4 - 6, 12 - 13.

408542. The issue for determination in this case is whether

4095certification should be granted to New Hope to construct and

4105operate the Expansion Project on the Site. Under Section

4114403.502, Florida Statutes, the Legislature provides in part:

4122It is the policy of this state that, while

4131recognizing the pressing need for increased

4137power generation faci lities, the state shall

4144ensure through available and reasonable

4149methods that the location and operation of

4156electrical power plants will produce minimal

4162adverse effects on human health, the

4168environment, the ecology of the land and its

4176wildlife, and the ecol ogy of state waters

4184and their aquatic life and will not unduly

4192conflict with the goals established by the

4199applicable local comprehensive plans. It is

4205the intent to seek courses of action that

4213will fully balance the increasing demands

4219for electrical power plant location and

4225operation with the broad interests of the

4232public. Such action will be based on these

4240premises:

4241(1) To assure the citizens of Florida that

4249operation safeguards are technically

4253sufficient for their welfare and protection.

4259(2) To ef fect a reasonable balance between

4267the need for the facility and the

4274environmental impact resulting from

4278construction and operation of the facility,

4284including air and water quality, fish and

4291wildlife, and the water resources and other

4298natural resources of t he state.

4304(3) To meet the need for electrical energy

4312as established pursuant to s. 403.519.

431843. The competent, substantial, and uncontested evidence

4325presented by New Hope and DEP at the Certification Hearing

4335demonstrates that the Expansion Project ha s met all of the

4346criteria required to obtain certification under the PPSA. New

4355Hope has provided reasonable assurance that the Project, if

4364constructed and operated in accordance with the Conditions of

4373Certification, will comply with all of the non - procedu ral

4384requirements that are applicable to the Project. Certification

4392of the Project will serve and protect the interests of the

4403public, and the benefits of the Project will outweigh the

4413negative impacts. New Hope has accepted, and demonstrated that

4422it will be able to comply with, the Conditions of Certification.

443344. In the PPSA review process and the Conditions of

4443Certification for the Project, the State of Florida has ensured

4453through available and reasonable methods that the location,

4461construction and o peration of the Expansion Project will produce

4471minimal adverse effects on human health, the environment, the

4480ecology of the land and its wildlife, and the ecology of State

4492waters and their aquatic life. If the Project is built and

4503operated in accordance w ith the Conditions of Certification, the

4513Project will not unduly conflict with the goals in any

4523applicable local, regional or state comprehensive plan. The

4531Conditions of Certification establish safeguards that are

4538technically sufficient for the protection and welfare of

4546Florida’s citizens, and the Conditions of Certification ensure

4554that the potential adverse effects of the Project will be

4564minimized.

456545. Certification of the Expansion Project is consistent

4573with the legislative intent to balance the incr easing demands

4583for electrical power plant location and operation with the

4592interests of the public. Certification of the Project

4600reasonably balances the need for the Project, as determined by

4610the PSC, with the environmental and other impacts resulting from

4620the construction and operation of the Project.

4627RECOMMENDATION

4628Based on the foregoing Findings of Facts and Conclusions of

4638Law, it is RECOMMENDED that the Governor and Cabinet, sitting as

4649the Siting Board, enter a Final Order granting certification for

4659th e expansion of the Okeelanta Cogeneration Facility to a total

4670capacity of 140 MW (net), in accordance with the Conditions of

4681Certification, DEP Exhibit 3.

4685DONE AND ENTERED this 31st day of March, 2005, in

4695Tallahassee, Leon County, Florida.

4699S

4700CHARLES A. STAMPELOS

4703Administrative Law Judge

4706Division of Administrative Hearings

4710The DeSoto Building

47131230 Apalachee Parkway

4716Tallahassee, Florida 32399 - 3060

4721(850) 488 - 9675 SUNCOM 278 - 9675

4729Fax Filing (850) 921 - 6847

4735www.doah.state.f l.us

4737Filed with the Clerk of the

4743Division of Administrative Hearings

4747this 31st day of March, 2005.

4753COPIES FURNISHED :

4756David S. Dee, Esquire

4760Landers & Parsons

4763310 West College Avenue

4767Tallahassee, Florida 32301

4770Scott Goorland, Esquire

4773Office of Genera l Counsel

4778Department of Environmental Protection

47823900 Commonwealth Boulevard

4785Mail Station 35

4788Tallahassee, Florida 32399 - 3000

4793James V. Antista, General Counsel

4798Florida Fish and Wildlife Conservation

4803Commission

4804620 South Meridian Street

4808Tallahassee, Flor ida 32399 - 1600

4814Roger Saberson, General Counsel

4818Treasure Coast Regional Planning

4822Council

482370 Southeast 4th Avenue

4827Delray Beach, Florida 33483

4831Jennifer Brubaker, Esquire

4834Public Service Commission

4837Division of Legal Services

48412540 Shumard Oak Boulevard

4845Tal lahassee, Florida 32399 - 0863

4851Leslie Bryson, Esquire

4854Department of Community Affairs

48582555 Shumard Oak Boulevard

4862Tallahassee, Florida 32399

4865Sheauching Yu, Esquire

4868Department of Transportation

4871605 Suwannee Street

4874Mail Station 58

4877Tallahassee, Florida 3239 9 - 0458

4883Sarah Nall, Esquire

48869341 Southeast Mystic Cove Terrace

4891Hobe Sound, Florida 33455

4895Denise M. Nieman, Esquire

4899Palm Beach County Attorney's Office

4904302 North Olive Avenue, Suite 601

4910West Palm Beach, Florida 33401 - 4705

4917Raquel A. Rodriguez, General Co unsel

4923Office of the Governor

4927The Capitol, Suite 209

4931Tallahassee, Florida 32399 - 1001

4936Kathy C. Carter, Agency Clerk

4941Department of Environmental Protection

4945Office of General Counsel

4949Mail Station 35

49523900 Commonwealth Boulevard

4955Tallahassee, Florida 32399 - 300 0

4961NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

4967All parties have the right to submit written exceptions within

497715 days from the date of this Recommended Order. Any exceptions

4988to this Recommended Order should be filed with the agency that

4999will issue the Final O rder in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 05/31/2005
Proceedings: Final Order of Certification filed.
PDF:
Date: 05/31/2005
Proceedings: Land Use Order filed.
PDF:
Date: 05/17/2005
Proceedings: Agency Final Order
PDF:
Date: 05/17/2005
Proceedings: Agency Final Order
PDF:
Date: 03/31/2005
Proceedings: Recommended Order
PDF:
Date: 03/31/2005
Proceedings: Recommended Order
PDF:
Date: 03/31/2005
Proceedings: Land Use and Recommended Order of Certification cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 03/31/2005
Proceedings: Recommended Order of Certification (hearing held March 21, 2005). CASE CLOSED.
PDF:
Date: 03/31/2005
Proceedings: Land Use Recommended Order (hearing held March 21, 2005). CASE CLOSED.
PDF:
Date: 03/28/2005
Proceedings: (Proposed) Land Use Recommended Order (filed by D. Dee and S. Goorland).
PDF:
Date: 03/28/2005
Proceedings: Joint Notice of Filing Proposed Recommended Order for Land Use Hearing by New Hope and the Department of Environmental Protection filed.
PDF:
Date: 03/28/2005
Proceedings: (Proposed) Recommended Order for Certification (filed by D. Dee and S. Goorland).
PDF:
Date: 03/28/2005
Proceedings: Joint Notice of Filing Proposed Recommended Order for Certification Hearing by New Hope and the Department of Environmental Protection filed.
Date: 03/25/2005
Proceedings: Transcript filed.
PDF:
Date: 03/25/2005
Proceedings: Notice of Filing Transcript filed.
Date: 03/21/2005
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 03/16/2005
Proceedings: New Hope`s Exhibit List for Land Use and Certification Hearings filed.
PDF:
Date: 03/16/2005
Proceedings: New Hope`s Notice of Filing Exhibit List filed.
PDF:
Date: 03/09/2005
Proceedings: Prehearing Stipulation for Land Use and Certification Hearings filed.
PDF:
Date: 03/07/2005
Proceedings: Letter to H. Oven from D. Dee advising of directions to hearing location filed.
PDF:
Date: 03/03/2005
Proceedings: Order Granting Official Recognition.
PDF:
Date: 02/17/2005
Proceedings: New Hopes`s Request for Official Recognition filed.
PDF:
Date: 02/04/2005
Proceedings: Department of Environmental Protection`s Notice of Filing Written Analysis filed.
PDF:
Date: 10/22/2004
Proceedings: Notice of Insufficiency (filed by S. Goorland via facsimile).
PDF:
Date: 10/20/2004
Proceedings: Notice of Appearance (filed by S. Nall, Esquire, via facsimile).
PDF:
Date: 10/18/2004
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 10/18/2004
Proceedings: Notice of Hearing (hearing set for March 21 and 22, 2005; 1:00 p.m.; South Bay, FL).
PDF:
Date: 10/05/2004
Proceedings: Order Altering Times.
PDF:
Date: 10/04/2004
Proceedings: Amended Motion and Stipulation for Alteration of Time Frames (filed by S. Goorland via facsimile).
PDF:
Date: 09/24/2004
Proceedings: Joint Response to DOAH`s Initial Order, Filing of Schedule, and Motion and Stipulation for Alteration of Time Frames (filed by S. Goorland via facsimile).
PDF:
Date: 09/17/2004
Proceedings: Department of Transportation`s Notice of Intent to be a Party (filed via facsimile).
PDF:
Date: 09/15/2004
Proceedings: Notice of Filing of Site Certification Application filed by S. Goorland.
PDF:
Date: 09/15/2004
Proceedings: Statement of Completeness filed by S. Goorland.
PDF:
Date: 09/14/2004
Proceedings: Initial Order.
PDF:
Date: 09/10/2004
Proceedings: Notice of Filing of List of Affected Agencies (filed via facsimile).
PDF:
Date: 09/10/2004
Proceedings: Notice of Receipt of Power Plant Siting Application and Request for Assignment of Administrative Law Judge (filed via facsimile).

Case Information

Judge:
CHARLES A. STAMPELOS
Date Filed:
09/10/2004
Date Assignment:
03/07/2005
Last Docket Entry:
05/31/2005
Location:
South Bay, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
Suffix:
EPP
 

Counsels

Related Florida Statute(s) (6):