04-003248BID
Betancourt-Castellon And Associates vs.
Miami-Dade County School Board
Status: Closed
Recommended Order on Tuesday, December 14, 2004.
Recommended Order on Tuesday, December 14, 2004.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8BETANCOURT CASTELLON )
11ASSOCIATES, INC., )
14)
15Petitioner, )
17)
18vs. ) Case No. 04 - 3248BID
25)
26MIAMI - DADE COUNTY SCHOOL )
32BOARD, )
34)
35Respondent, )
37)
38and )
40)
41MAGNUM CO NSTRUCTION )
45MANAGEMENT CORPORATION, )
48)
49Intervenor. )
51______________________________)
52RECOMMENDED ORDER
54Robert E. Meale, Administrative Law Judge of the Division
63of Administrative Hearings, conducted the final hearing in
71Miami, Florida, on Octob er 13, 2004.
78APPEARANCES
79For Petitioner: Ira Libanoff
83Ferencik Libanoff Brandt
86Bustamante and Williams, P.A.
90150 South Pine Island Road, Suite 400
97Fort Lauderdale, Florida 33324
101For Respondent: Luis M. Garcia
106Miami - Dade County School Board
1121450 Northeast 2nd Avenue, Suite 400
118Miami, Florida 33132
121For Intervenor: J. Alfred o de Armas
128Alvarez, Armas & Borron, P.A.
1333211 Ponce De Leon Boulevard, Suite 302
140Coral Gables, Florida 33134
144STATEMENT OF THE ISSUE
148Pursuant to Section 120.57(3)(f), Florida Statutes, the
155issue is whether Respondent's proposed rescission of an award of
165a design - build contract to Petitioner for the construction of
176additions to two high schools was contrary to the Respondent's
186governing statutes, rules or policies or contrary to the
195specific ations of Respondent's request for qualifications.
202PRELIMINARY STATEMENT
204On March 30, 2004, Respondent issued a Request for
213Qualifications of design - build firms for the design and
223construction of additions to two high schools. Petitioner and
232Intervenor t imely submitted responses.
237On July 18, 2004, Respondent's School Board awarded the
246contract to Petitioner. Intervenor timely protested the award,
254claiming that a conflict of interest existed between
262Petitioner's design - build team and Respondent's design criteria
271professional team.
273Following receipt of Intervenor's protest, Respondent's
279legal counsel concluded that the conflict precluded the award to
289Petitioner, and he recommended that Respondent's School Board
297rescind the award, evidently implying that t he School Board
307should award the contract to Intervenor. Petitioner timely
315protested the proposed agency action of rescinding the award of
325the contract to Petitioner, and the case proceeded on the issue
336set forth above.
339At the hearing, Petitioner called three witnesses and
347offered into evidence four exhibits: Petitioner Exhibits 1 - 4.
357Respondent called no witnesses and offered into evidence seven
366exhibits: School Board Exhibits 0 - 6. Intervenor called two
376witnesses and offered into evidence four exhibit s: Intervenor
385Exhibits 1 - 4. All exhibits were admitted except School Board
396Exhibit 4, which was not admitted for the truth. Respondent
406proffered the exhibit for all purposes for which it was not
417admitted.
418The court reporter filed the transcript on Dece mber 2,
4282004. The parties filed their proposed recommended orders on
437December 13, 2004.
440FINDINGS OF FACT
4431. On March 30, 2004, Respondent issued a Request for
453Qualifications (RFQ) for design - build firms to design and
463construct additions at Southwest Miami Senior High School and
472Miami Killian Senior High School. The RFQ invites parties to
482submit proposals, if they are interested in performing the
491design and construction of three - story additions at each school
502(the subject projects).
5052. Respondent had used the design - build approach for
515school construction for the past seven to ten years. In this
526process, the contractor assumes the responsibility for most of
535the project, as well as, of course, the project construction.
5453. For the subject projects, Respondent entered into a
554contract with a Design Criteria Professional (DCP) to represent
563Respondent, as the owner, in certain aspects of the construction
573project. The DCP for these projects is Santos/Raimundez
581Architects, P.A.
5834. The contract between Respondent an d the DCP states that
594Respondent has selected the DCP based, in part, on its
604designation of specialists, including Fraga Engineers for the
612mechanical and electrical work. The contract provides that any
621such specialists that are subconsultants to, rather t han
630employees of, the DCP will enter into subcontracts with the DCP,
641but not Respondent.
6445. The DCP and its designated specialists form the DCP
654Team, which performs various tasks in connection with each
663project. These tasks include site investigations to determine
671project feasibility, the production of project - specific Phase I
681or schematic drawings from the master specifications that
689Respondent maintains for school construction, and the issuance
697of a building permit for the schematic design.
7056. Once the contractor commences construction, the DCP
713Team visits the site to protect Respondent, as the owner, from
724deviations from the approved design. The DCP Team also approves
734draws based on the percentage of work completed and change
744orders, as appropriate.
7477. The DCP Team performs about 10 - 15 percent of the
759overall design for a project. For the subject projects, the DCP
770Team spent seven months in performing its responsibilities prior
779to Respondent's selection of a contractor.
7858. The only involvement of Fraga En gineers with the
795subject projects is for the mechanical and electrical work noted
805above, as well as plumbing and fire - suppression work of a
817similar nature for which the DCP also contracted.
8259. For the subject projects, Petitioner retained Silva
833Architects as its architect and primary team member, and Silva
843Architects entered into a subcontract with Louis Aguirre for the
853mechanical, electrical, plumbing, and fire - suppression design
861and construction.
86310. The principal of Silva Architects and the principal of
873Fra ga Engineers are, respectively, husband and wife. There is
883no indication in this record of any improper communications
892between Mr. Silva and Ms. Fraga concerning the contents of the
903RFQ or the Phase I drawings, as prepared by Respondent, or the
915contents o f the proposal, as prepared by Petitioner. However,
925at the time of this solicitation, Fraga Engineers was serving as
936the engineering firm on at least two of Petitioner's projects,
946although her firm probably was under contract with Silva
955Architects, not Pe titioner.
95911. Except for the following provision, the RFQ does not
969address potential conflicts between an offeror and Respondent.
977RFQ Paragraph I.H provides:
981Any proposer desiring to participate in this
988process must not have as part of its team an
998A/E [archit ectural/engineering] firm
1002presently under contract with the Board for
1009a specific project for which the proposer,
1016or any member thereof, is performing as the
1024general contractor. The Board considers
1029this a conflict of interest and such
1036proposals will not be eligible for award
1043under this RFQ.
104612. Petitioner and Intervenor submitted timely proposals
1053to Respondent. Among several offerors submitting proposals,
1060Petitioner submitted the lowest bid, at $17,536,000, followed
1070closely by Intervenor's second - lowest bid, at $17,556,000.
108113. Finding Petitioner's proposal acceptable in all
1088respects, Respondent's School Board awarded the contract to
1096Petitioner at its meeting of June 16, 2004. On the same day,
1108Intervenor filed a notice of protest, followed by a timely
1118formal wr itten protest.
112214. The formal written protest, which is in the form of an
1134undated letter from Intervenor's counsel to Respondent and
1142Respondent's counsel, states that Intervenor was not allowed to
1151bid on projects where its architect/engineer was on Respondent' s
1161DCP Team for another project. The formal written protest argues
1171that Ms. Fraga, or her company, is part of Petitioner's team on
1183other pending projects while she, or her company, is part of
1194Respondent's DCP Team.
119715. Respondent conducted an informal confer ence with
1205Intervenor and later with Petitioner in an attempt to resolve
1215the matter. Failing in that effort, Respondent's counsel issued
1224a letter, dated August 25, 2004, in which he recommended that
1235Respondent's School Board rescind the proposed award to
1243P etitioner. In his letter, Respondent's counsel reasoned that
1252the spousal relationship between Petitioner's architect and the
1260engineering firm under contract with Respondent's architect
"1267would create a continuing and unavoidable conflict of interest
1276that w ill inure to the benefit of either of these parties in
1289violation of the General Requirements of the Bid, or at a
1300minimum, could create a perceived or potential conflict of
1309interest."
131016. In his letter, Respondent's counsel stated that "we
1319disagree" with the recommended order entered in SBR Joint
1328Venture v. Miami - Dade County School Board , DOAH Case No.
133903 - 1102BID (August 1, 2003), in which the Administrative Law
1350Judge concluded, among other things, that a bidding contractor's
1359team did not include subcontracto rs under contract with the
1369contractor's architect, rather than directly with the
1376contractor. Unless the pronoun refers to the legal counsel's
1385office or a committee formed to resolve the bid dispute, the
"1396we" in the letter of Respondent's counsel is unclea r because
1407Respondent's School Board entered a final order on August 20,
14172003 -- one year and five days before the letter of Respondent's
1429counsel -- adopting the recommended order.
143517. Another confusing part of counsel's letter is an
1444explanatory footnote, in whic h Respondent's counsel
1451unsuccessfully distinguishes the present case, in which Silva
1459Architects is directly under contract with Petitioner, from SBR
1468Joint Venture , in which the third - tier subcontractor was under
1479contract with the general contractor's archi tect, not the
1488general contractor. (In SBR Joint Venture , as in the present
1498case, the so - called "third tier" subcontractor has a contract
1509with the "second tier" architect, but not the "first tier"
1519contractor.) The question in this case is not whether the
1529second - tier Silva Architects is part of Petitioner's team --
1540clearly, it is. A major question in this case is whether Fraga
1552Engineers is part of Petitioner's team -- clearly, it is not,
1563unless Ms. Fraga and Mr. Silva are interchangeable due to their
1574marriage or her company's third - tier participation in other
1584projects of Petitioner is attributed to the subject projects.
159318. In any event, before Respondent's School Board could
1602take up its counsel's recommendation, Petitioner protested the
1610recommendation, and this ca se ensued.
1616CONCLUSIONS OF LAW
161919. The Division of Administrative Hearings has
1626jurisdiction over the subject matter. §§ 120.569 and
1634120.57(3)(e), Fla. Stat. (2004).
163820. Section 120.57(3)(f) provides:
1642In a competitive - procurement protest, other
1649than a rejection of all bids, proposals, or
1657replies, the administrative law judge shall
1663conduct a de novo proceeding to determine
1670whether the agency's proposed action is
1676contrary to the agency's governing statutes,
1682the agency's rules or policies, or the
1689solicitation specific ations.
169221. Pursuant to Section 120.57(3)(f), Florida Statutes,
1699the burden of proof is on "the party protesting the proposed
1710agency action," and the standard of proof is: "whether the
1720proposed agency action was clearly erroneous, contrary to
1728competition, a rbitrary, or capricious."
173322. Section 1013.46(1)(a), Florida Statutes, requires
1739Respondent to award the contract to the "lowest responsible
1748bidder." Section 1013.45(1)(b), Florida Statutes, provides that
1755Respondent may use the design - build procedure, as desc ribed in
1767Section 287.055, Florida Statutes, for the construction of new
1776facilities or major additions to existing facilities.
178323. This case is unusual because of the existence of two
1794proposed agency actions opposing each other (or, in the
1803alternative, the abse nce of the proposed agency action on which
1814this case is purportedly based). Initially, the agency
1822tentatively awarded the contract to Petitioner, as the lowest
1831offeror. Intervenor protested this action. Subsequently, the
1838agency's counsel agreed with Int ervenor's contention that
1846Petitioner should be disqualified due to a conflict of interest,
1856and he recommended the rescission of the agency's earlier
1865action. Petitioner protested this action.
187024. Although Respondent's School Board has never taken up
1879its counse l's recommendation, the parties agree that this case
1889is ripe and presents for determination the sustainability of the
1899recommendation of Respondent's counsel, rather than the
1906sustainability of the proposed agency action of Respondent's
1914School Board.
191625. The A dministrative Law Judge has accepted the parties'
1926agreement on the procedural posture of this case, but
1935respectfully points out shortcomings of the procedure in which a
1945bid protest concerns the recommendation of legal counsel or a
1955committee formed to resol ve bid protests informally, rather than
1965the proposed action of the contract - awarding entity -- here, the
1977School Board. The parties have effectively denied the School
1986Board the opportunity to consider counsel's recommendation prior
1994to an administrative heari ng. The School Board might have
2004rejected counsel's recommendation, perhaps on grounds including
2011those set forth in this recommended order. The School Board
2021might have accepted counsel's recommendation, perhaps awarding
2028the contract to Intervenor -- an acti on, at best, implied by
2040counsel's letter, but necessary to Intervenor's standing -- or
2049rebidding the subject projects, with more explicit conflict - of -
2060interest provisions addressing the tiers of participants and the
2069effect of marriage between two principals o f any of the
2080participants, at whatever tier. The incompleteness of counsel's
2088recommendation in selecting one of these two options, if
2097Petitioner's proposal were rejected, would have been even more
2106problematic in this case, if Intervenor had prevailed.
211426. How ever, accepting the parties' understanding of the
2123posture of this case, Petitioner bears the burden of proving
2133that the rescission of the award to it, and implicit award to
2145Intervenor, would be contrary to statutes, rules, or policies or
2155the RFQ.
215727. The mater ial facts of this case are not in dispute.
2169Petitioner submitted the lowest bid and would have received the
2179award, but for the issue raised by Intervenor concerning a
2189conflict of interest involving Fraga Engineers.
219528. Fraga Engineers works indirectly with Res pondent on
2204the subject projects and works with Petitioner on other
2213projects, but does not work even indirectly with Petitioner on
2223the subject projects, unless Ms. Fraga and Mr. Silva are
2233interchangeable due to their marriage. For these projects,
2241Fraga Eng ineers is a second - tier consultant to Respondent's DCP.
2253Although Fraga Engineers is on Respondent's DCP Team for the
2263subject projects and Respondent retains the right not to allow
2273its DCP to remove Fraga Engineers, the DCP, not Fraga Engineers,
2284is under c ontract with Respondent for these projects.
2293Contractually, Fraga Engineers' only relationship with these
2300projects is under a subcontract with the DCP.
230829. Fraga Engineers serves as a third - tier consultant to
2319Silva Architects on projects for which Petitioner is the first -
2330tier contractor. However, as noted above, for the subject
2339projects, Fraga Engineers' only relationship with Petitioner's
2346team is that Ms. Fraga -- claimed by Intervenor to be better known
2359as Mrs. Silva -- is married to Mr. Silva.
236830. None of these r elationships among Petitioner,
2376Respondent, Silva Architects, and Fraga Engineers violates any
2384applicable statutes, rules, or policies or any specifications of
2393the RFQ, with respect to the creation of a conflict of interest
2405that would necessitate or justify the disqualification of
2413Petitioner or the rejection of its proposal.
242031. The only conflict - of - interest provision in the RFQ is
2433Paragraph I.H. This conflict - of - interest provision requires two
2444conditions for a determination of the ineligibility of the
2453offeror or rejection of its proposal. In this case, neither of
2464these conditions is met.
246832. First, Fraga Engineers is not part of Petitioner's
2477team for these projects. For these projects, the little -
2487mentioned Mr. Aguirre, not Fraga Engineers, serves as the
2496mechani cal, electrical, plumbing, and fire - suppression engineer.
2505RFQ Paragraph I.H covers the current members of Petitioner's
2514team for the two high - school additions that are the subject of
2527this RFQ. Nothing in the RFQ or Respondent's rules or policies
2538extends t he disqualification from the members of the offeror's
2548team on the subject projects to members of its team on past
2560projects or other ongoing projects. Nor do the RFQ or
2570Respondent's rules and policies require or permit Respondent to
2579treat Silva Architects as though it were Fraga Engineers due to
2590the marriage of the principals of the two entities. The RFQ and
2602Respondent's rules and policies contain no attribution rules,
2610under which Ms. Fraga would be treated as the principal of Silva
2622Architects due to her m arriage with Mr. Silva.
263133. Second, Fraga Engineers is not presently under
2639contract with Respondent for any project, including the subject
2648projects, for which Petitioner is the general contractor. The
2657participation of Fraga Engineers on the DCP Team for the se
2668projects is irrelevant under RFQ Paragraph I.H, which limits its
2678scope to entities under contract with Respondent. Fraga
2686Engineers is not under contract with Respondent, so its
2695involvement fails to trigger the RFQ's conflict - of - interest
2706provision.
270734. Th e parties stipulated at the start of the hearing
2718that Respondent had no rule or policy that would define a
2729conflict of interest based on a spousal relationship, except for
2739such a relationship with an employee of Respondent. So, the
2749sole remaining source o f authority for disqualifying Petitioner
2758or rejecting its proposal, on the basis of a conflict of
2769interest, would be a state statute or rule.
277735. The only applicable conflict - of - interest provision in
2788the statutes is Section 287.055(9)(b), Florida Statutes, whi ch
2797Section 1013.45(1)(b), Florida Statutes, applies to design - build
2806contracts for School Board building construction. Section
2813287.055(9)(b), Florida Statutes, states: "A design criteria
2820professional who has been selected to prepare the design
2829criteria pa ckage is not eligible to render services under a
2840design - build contract executed pursuant to the design criteria
2850package." Respondent's Rule 6Gx13 - 7B - 1.021(III)(A) states the
2860same prohibition.
286236. The present arrangement does not violate Section
2870287.055(9)(b), Florida Statutes. The statute speaks of the DCP,
2879not a member of the DCP Team. This statute merely prohibits the
2891DCP, Santos/Raimundez Architects, P.A., from rendering design -
2899build services for the subject projects.
290537. As Intervenor noted in its formal w ritten protest,
2915Florida Administrative Code Rule 60D - 5.0071(9) provides that "an
2925agency" may reserve the right to reject a bid when it determines
2937that a "conflict of interest exists." In RFQ Paragraph I.H,
2947Respondent reserved the right to reject a bid if a conflict
2958existed, and, as noted above, no such conflict exists.
296738. More importantly, though, Florida Administrative Code
2974Rule 60D - 5.0071(9) is inapplicable to this case. This rule is
2986promulgated by the Florida Department of Management Services,
2994pursuant to Section 255.29, Florida Statutes, which applies to
3003the construction of state buildings, not School Board buildings.
3012Chapter 1013, Florida Statutes, authorizes the Florida
3019Department of Education to exercise certain supervisory
3026responsibilities over the construction of School Board
3033buildings. The Florida Department of Education rule applicable
3041to such construction is at Florida Administrative Code Rule
30506 - 2.001, and it does not address conflicts of interest.
306139. Lacking any authority for rejecting Petitione r's
3069proposal on the basis of a conflict of interest set forth in any
3082statute, rule, School Board policy, or the RFQ, Respondent's
3091counsel necessarily based his rescission recommendation on a
3099perceived or potential conflict of interest not stated in the
3109sta tutes, rules, policies, or RFQ. However, this conflict of
3119interest lacks any definition, even after the hearing in this
3129case, and emerged only after the opening of the proposals.
313940. In the abstract, conflicts of interest find little
3148support due to the obvi ous potential for misdealing between the
3159persons with the conflict. Respondent's counsel was trying to
3168bolster the competitive - bidding process by adding this ill -
3179defined conflict - of - interest provision after the proposals had
3190been opened. Unfortunately, t he effect of counsel's action is
3200the opposite. Allowing agencies to add new, vague conflict - of -
3212interest requirements to a procurement after the bids or
3221proposals are opened invites manipulation of the bidding process
3230and subverts competitive bidding when, as here, the agency
3239selects a higher bid over the lowest bid of an offeror that
3251failed to comply with this new, vague requirement. As must
3261bidders, so must agencies abide by the specifications of their
3271bid packages and may not select a bidder that has co nformed to
3284an undisclosed, poorly defined bid specification, to which a
3293lower bidder failed to conform.
329841. Petitioner has proved that no conflict - of - interest
3309provision requires or permits the disqualification of Petitioner
3317or rejection of its proposal and tha t Respondent's proposed
3327disqualification of Petitioner and rejection of Petitioner's
3334proposal subverts the competitive bidding process. Petitioner
3341has thus proved that the proposed agency action adverse to
3351Petitioner is contrary to Section 1013.46(1)(a), Florida
3358Statutes, which requires Respondent to award the contract to the
"3368lowest responsible bidder."
3371RECOMMENDATION
3372It is
3374RECOMMENDED that Respondent enter a final order awarding
3382the contract to Petitioner.
3386DONE AND ENTERED this 14th day of December, 2004, in
3396Tallahassee, Leon County, Florida.
3400S
3401___________________________________
3402ROBERT E. MEALE
3405Administrative Law Judge
3408Division of Administrative Hearings
3412The DeSoto Building
34151230 Apalachee Parkway
3418Tallahassee, Florida 32399 - 3060
3423(850) 488 - 9675 SUNCOM 278 - 9675
3431Fax Filing (850) 921 - 6847
3437www.doah.state.fl.us
3438Filed with the Clerk of the
3444Division of Administrative Hearings
3448this 14th day of December, 2004.
3454COPIES FURNISHED:
3456Dr. Rudolph F. Crew, Superintendent
3461Miami - Dade County School Board
34671450 Northeast Second Avenue
3471Miami, Florida 33132 - 1394
3476Daniel J. Woodring, General Counsel
3481Department of Education
3484325 West Gaines Street, Roo m 1244
3491Tallahassee, Florida 32399 - 0400
3496Ira Libanoff
3498Ferencik Libanoff Brandt
3501Bustamante and Williams, P.A.
3505150 South Pine Island Road, Suite 400
3512Fort Lauderdale, Florida 33324
3516Luis M. Garcia
3519Miami - Dade County School Board
35251450 Northeast 2nd Avenue, Sui te 400
3532Miami, Florida 33132
3535J. Alfredo de Armas
3539Alvarez, Armas & Borron, P.A.
35443211 Ponce De Leon Boulevard, Suite 302
3551Coral Gables, Florida 33134
3555NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
3561All parties have the right to submit written exceptions within
357110 days from the date of this recommended order. Any exceptions
3582to this recommended order must be filed with the agency that
3593will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 12/14/2004
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 12/13/2004
- Proceedings: Notice of Filing MCM`s Proposed Findings of Fact and Conclusions of Law (filed via facsimile).
- PDF:
- Date: 12/13/2004
- Proceedings: MCM`s Proposed Findings of Fact and Conclusions of Law (filed via facsimile).
- PDF:
- Date: 10/18/2004
- Proceedings: Letter to Judge Meale from L. Garcia enclosing Respondent`s exhibit O filed.
- Date: 10/13/2004
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 10/12/2004
- Proceedings: BCA`s Response and Objection to MCM`s Notice to Produce at Trial (filed via facsimile).
- PDF:
- Date: 10/12/2004
- Proceedings: MCM`s Notice to Produce at Trial (Final Hearing) filed via facsimile.
- PDF:
- Date: 10/12/2004
- Proceedings: MCM`s Notice of Filing Pretrial Stipulation (filed via facsimile).
- PDF:
- Date: 10/08/2004
- Proceedings: Magnum Construction Management Corporation`s Witness and Exhibits List (filed via facsimile).
- PDF:
- Date: 10/07/2004
- Proceedings: Letter to J. De Armas from I. Libanoff regarding taking the deposition of I. Farga (filed via facsimile).
- PDF:
- Date: 10/07/2004
- Proceedings: Letter to J. DeArmas from I. Libanoff regarding Ms. Fraga`s withdrawal (filed via facsimile).
- PDF:
- Date: 10/07/2004
- Proceedings: Petitioner`s Response to Intervenor`s Motion for Sanctions (filed via facsimile).
- PDF:
- Date: 10/07/2004
- Proceedings: Petitioner`s Notice of No Objection and Supplement to Motion to Continue and/or Stay (filed via facsimile).
- PDF:
- Date: 10/06/2004
- Proceedings: Petitioner`s Motion to Continue and/or to Stay (filed via facsimile).
- PDF:
- Date: 10/05/2004
- Proceedings: Magnum Construction Management Corporation (Hereinafter "MCM") Notice of Taking Deposition of Party (Representative of Betancourt-Castellon and Associates) filed via facsimile.
- PDF:
- Date: 09/29/2004
- Proceedings: Notice of Administrative Hearing to Interested or Affected Parties (filed by L. Garcia via facsimile).
- PDF:
- Date: 09/27/2004
- Proceedings: Order Granting Intervention. (Magnum Construction Management Corporation)
- PDF:
- Date: 09/24/2004
- Proceedings: Magnum Construction Management Corporation (Hereinafter "MCM") Petition to Intervene as Interested Party filed by via facsimile.
- PDF:
- Date: 09/17/2004
- Proceedings: Notice of Hearing (hearing set for October 13, 2004; 9:00 a.m.; Miami, FL).
- PDF:
- Date: 09/17/2004
- Proceedings: Letter to Mr. Garcia from I. Libanoff, Esquire regarding Project A-0854 SW Miami Sr. High; A-0855 Miami Killian Sr. High (filed via facsimile).
Case Information
- Judge:
- ROBERT E. MEALE
- Date Filed:
- 09/17/2004
- Date Assignment:
- 09/17/2004
- Last Docket Entry:
- 02/04/2005
- Location:
- Mango, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
J. Alfredo De Armas, Esquire
Address of Record -
Luis M. Garcia, Esquire
Address of Record -
Alexander J Williams, Jr., Esquire
Address of Record