04-003248BID Betancourt-Castellon And Associates vs. Miami-Dade County School Board
 Status: Closed
Recommended Order on Tuesday, December 14, 2004.


View Dockets  
Summary: Respondent violated statute requiring the award to the lowest responsible bidder when Respondent rejected protester`s bid for violation of an ill-defined, previously undisclosed conflict-of-interest prohibition.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8BETANCOURT CASTELLON )

11ASSOCIATES, INC., )

14)

15Petitioner, )

17)

18vs. ) Case No. 04 - 3248BID

25)

26MIAMI - DADE COUNTY SCHOOL )

32BOARD, )

34)

35Respondent, )

37)

38and )

40)

41MAGNUM CO NSTRUCTION )

45MANAGEMENT CORPORATION, )

48)

49Intervenor. )

51______________________________)

52RECOMMENDED ORDER

54Robert E. Meale, Administrative Law Judge of the Division

63of Administrative Hearings, conducted the final hearing in

71Miami, Florida, on Octob er 13, 2004.

78APPEARANCES

79For Petitioner: Ira Libanoff

83Ferencik Libanoff Brandt

86Bustamante and Williams, P.A.

90150 South Pine Island Road, Suite 400

97Fort Lauderdale, Florida 33324

101For Respondent: Luis M. Garcia

106Miami - Dade County School Board

1121450 Northeast 2nd Avenue, Suite 400

118Miami, Florida 33132

121For Intervenor: J. Alfred o de Armas

128Alvarez, Armas & Borron, P.A.

1333211 Ponce De Leon Boulevard, Suite 302

140Coral Gables, Florida 33134

144STATEMENT OF THE ISSUE

148Pursuant to Section 120.57(3)(f), Florida Statutes, the

155issue is whether Respondent's proposed rescission of an award of

165a design - build contract to Petitioner for the construction of

176additions to two high schools was contrary to the Respondent's

186governing statutes, rules or policies or contrary to the

195specific ations of Respondent's request for qualifications.

202PRELIMINARY STATEMENT

204On March 30, 2004, Respondent issued a Request for

213Qualifications of design - build firms for the design and

223construction of additions to two high schools. Petitioner and

232Intervenor t imely submitted responses.

237On July 18, 2004, Respondent's School Board awarded the

246contract to Petitioner. Intervenor timely protested the award,

254claiming that a conflict of interest existed between

262Petitioner's design - build team and Respondent's design criteria

271professional team.

273Following receipt of Intervenor's protest, Respondent's

279legal counsel concluded that the conflict precluded the award to

289Petitioner, and he recommended that Respondent's School Board

297rescind the award, evidently implying that t he School Board

307should award the contract to Intervenor. Petitioner timely

315protested the proposed agency action of rescinding the award of

325the contract to Petitioner, and the case proceeded on the issue

336set forth above.

339At the hearing, Petitioner called three witnesses and

347offered into evidence four exhibits: Petitioner Exhibits 1 - 4.

357Respondent called no witnesses and offered into evidence seven

366exhibits: School Board Exhibits 0 - 6. Intervenor called two

376witnesses and offered into evidence four exhibit s: Intervenor

385Exhibits 1 - 4. All exhibits were admitted except School Board

396Exhibit 4, which was not admitted for the truth. Respondent

406proffered the exhibit for all purposes for which it was not

417admitted.

418The court reporter filed the transcript on Dece mber 2,

4282004. The parties filed their proposed recommended orders on

437December 13, 2004.

440FINDINGS OF FACT

4431. On March 30, 2004, Respondent issued a Request for

453Qualifications (RFQ) for design - build firms to design and

463construct additions at Southwest Miami Senior High School and

472Miami Killian Senior High School. The RFQ invites parties to

482submit proposals, if they are interested in performing the

491design and construction of three - story additions at each school

502(the subject projects).

5052. Respondent had used the design - build approach for

515school construction for the past seven to ten years. In this

526process, the contractor assumes the responsibility for most of

535the project, as well as, of course, the project construction.

5453. For the subject projects, Respondent entered into a

554contract with a Design Criteria Professional (DCP) to represent

563Respondent, as the owner, in certain aspects of the construction

573project. The DCP for these projects is Santos/Raimundez

581Architects, P.A.

5834. The contract between Respondent an d the DCP states that

594Respondent has selected the DCP based, in part, on its

604designation of specialists, including Fraga Engineers for the

612mechanical and electrical work. The contract provides that any

621such specialists that are subconsultants to, rather t han

630employees of, the DCP will enter into subcontracts with the DCP,

641but not Respondent.

6445. The DCP and its designated specialists form the DCP

654Team, which performs various tasks in connection with each

663project. These tasks include site investigations to determine

671project feasibility, the production of project - specific Phase I

681or schematic drawings from the master specifications that

689Respondent maintains for school construction, and the issuance

697of a building permit for the schematic design.

7056. Once the contractor commences construction, the DCP

713Team visits the site to protect Respondent, as the owner, from

724deviations from the approved design. The DCP Team also approves

734draws based on the percentage of work completed and change

744orders, as appropriate.

7477. The DCP Team performs about 10 - 15 percent of the

759overall design for a project. For the subject projects, the DCP

770Team spent seven months in performing its responsibilities prior

779to Respondent's selection of a contractor.

7858. The only involvement of Fraga En gineers with the

795subject projects is for the mechanical and electrical work noted

805above, as well as plumbing and fire - suppression work of a

817similar nature for which the DCP also contracted.

8259. For the subject projects, Petitioner retained Silva

833Architects as its architect and primary team member, and Silva

843Architects entered into a subcontract with Louis Aguirre for the

853mechanical, electrical, plumbing, and fire - suppression design

861and construction.

86310. The principal of Silva Architects and the principal of

873Fra ga Engineers are, respectively, husband and wife. There is

883no indication in this record of any improper communications

892between Mr. Silva and Ms. Fraga concerning the contents of the

903RFQ or the Phase I drawings, as prepared by Respondent, or the

915contents o f the proposal, as prepared by Petitioner. However,

925at the time of this solicitation, Fraga Engineers was serving as

936the engineering firm on at least two of Petitioner's projects,

946although her firm probably was under contract with Silva

955Architects, not Pe titioner.

95911. Except for the following provision, the RFQ does not

969address potential conflicts between an offeror and Respondent.

977RFQ Paragraph I.H provides:

981Any proposer desiring to participate in this

988process must not have as part of its team an

998A/E [archit ectural/engineering] firm

1002presently under contract with the Board for

1009a specific project for which the proposer,

1016or any member thereof, is performing as the

1024general contractor. The Board considers

1029this a conflict of interest and such

1036proposals will not be eligible for award

1043under this RFQ.

104612. Petitioner and Intervenor submitted timely proposals

1053to Respondent. Among several offerors submitting proposals,

1060Petitioner submitted the lowest bid, at $17,536,000, followed

1070closely by Intervenor's second - lowest bid, at $17,556,000.

108113. Finding Petitioner's proposal acceptable in all

1088respects, Respondent's School Board awarded the contract to

1096Petitioner at its meeting of June 16, 2004. On the same day,

1108Intervenor filed a notice of protest, followed by a timely

1118formal wr itten protest.

112214. The formal written protest, which is in the form of an

1134undated letter from Intervenor's counsel to Respondent and

1142Respondent's counsel, states that Intervenor was not allowed to

1151bid on projects where its architect/engineer was on Respondent' s

1161DCP Team for another project. The formal written protest argues

1171that Ms. Fraga, or her company, is part of Petitioner's team on

1183other pending projects while she, or her company, is part of

1194Respondent's DCP Team.

119715. Respondent conducted an informal confer ence with

1205Intervenor and later with Petitioner in an attempt to resolve

1215the matter. Failing in that effort, Respondent's counsel issued

1224a letter, dated August 25, 2004, in which he recommended that

1235Respondent's School Board rescind the proposed award to

1243P etitioner. In his letter, Respondent's counsel reasoned that

1252the spousal relationship between Petitioner's architect and the

1260engineering firm under contract with Respondent's architect

"1267would create a continuing and unavoidable conflict of interest

1276that w ill inure to the benefit of either of these parties in

1289violation of the General Requirements of the Bid, or at a

1300minimum, could create a perceived or potential conflict of

1309interest."

131016. In his letter, Respondent's counsel stated that "we

1319disagree" with the recommended order entered in SBR Joint

1328Venture v. Miami - Dade County School Board , DOAH Case No.

133903 - 1102BID (August 1, 2003), in which the Administrative Law

1350Judge concluded, among other things, that a bidding contractor's

1359team did not include subcontracto rs under contract with the

1369contractor's architect, rather than directly with the

1376contractor. Unless the pronoun refers to the legal counsel's

1385office or a committee formed to resolve the bid dispute, the

"1396we" in the letter of Respondent's counsel is unclea r because

1407Respondent's School Board entered a final order on August 20,

14172003 -- one year and five days before the letter of Respondent's

1429counsel -- adopting the recommended order.

143517. Another confusing part of counsel's letter is an

1444explanatory footnote, in whic h Respondent's counsel

1451unsuccessfully distinguishes the present case, in which Silva

1459Architects is directly under contract with Petitioner, from SBR

1468Joint Venture , in which the third - tier subcontractor was under

1479contract with the general contractor's archi tect, not the

1488general contractor. (In SBR Joint Venture , as in the present

1498case, the so - called "third tier" subcontractor has a contract

1509with the "second tier" architect, but not the "first tier"

1519contractor.) The question in this case is not whether the

1529second - tier Silva Architects is part of Petitioner's team --

1540clearly, it is. A major question in this case is whether Fraga

1552Engineers is part of Petitioner's team -- clearly, it is not,

1563unless Ms. Fraga and Mr. Silva are interchangeable due to their

1574marriage or her company's third - tier participation in other

1584projects of Petitioner is attributed to the subject projects.

159318. In any event, before Respondent's School Board could

1602take up its counsel's recommendation, Petitioner protested the

1610recommendation, and this ca se ensued.

1616CONCLUSIONS OF LAW

161919. The Division of Administrative Hearings has

1626jurisdiction over the subject matter. §§ 120.569 and

1634120.57(3)(e), Fla. Stat. (2004).

163820. Section 120.57(3)(f) provides:

1642In a competitive - procurement protest, other

1649than a rejection of all bids, proposals, or

1657replies, the administrative law judge shall

1663conduct a de novo proceeding to determine

1670whether the agency's proposed action is

1676contrary to the agency's governing statutes,

1682the agency's rules or policies, or the

1689solicitation specific ations.

169221. Pursuant to Section 120.57(3)(f), Florida Statutes,

1699the burden of proof is on "the party protesting the proposed

1710agency action," and the standard of proof is: "whether the

1720proposed agency action was clearly erroneous, contrary to

1728competition, a rbitrary, or capricious."

173322. Section 1013.46(1)(a), Florida Statutes, requires

1739Respondent to award the contract to the "lowest responsible

1748bidder." Section 1013.45(1)(b), Florida Statutes, provides that

1755Respondent may use the design - build procedure, as desc ribed in

1767Section 287.055, Florida Statutes, for the construction of new

1776facilities or major additions to existing facilities.

178323. This case is unusual because of the existence of two

1794proposed agency actions opposing each other (or, in the

1803alternative, the abse nce of the proposed agency action on which

1814this case is purportedly based). Initially, the agency

1822tentatively awarded the contract to Petitioner, as the lowest

1831offeror. Intervenor protested this action. Subsequently, the

1838agency's counsel agreed with Int ervenor's contention that

1846Petitioner should be disqualified due to a conflict of interest,

1856and he recommended the rescission of the agency's earlier

1865action. Petitioner protested this action.

187024. Although Respondent's School Board has never taken up

1879its counse l's recommendation, the parties agree that this case

1889is ripe and presents for determination the sustainability of the

1899recommendation of Respondent's counsel, rather than the

1906sustainability of the proposed agency action of Respondent's

1914School Board.

191625. The A dministrative Law Judge has accepted the parties'

1926agreement on the procedural posture of this case, but

1935respectfully points out shortcomings of the procedure in which a

1945bid protest concerns the recommendation of legal counsel or a

1955committee formed to resol ve bid protests informally, rather than

1965the proposed action of the contract - awarding entity -- here, the

1977School Board. The parties have effectively denied the School

1986Board the opportunity to consider counsel's recommendation prior

1994to an administrative heari ng. The School Board might have

2004rejected counsel's recommendation, perhaps on grounds including

2011those set forth in this recommended order. The School Board

2021might have accepted counsel's recommendation, perhaps awarding

2028the contract to Intervenor -- an acti on, at best, implied by

2040counsel's letter, but necessary to Intervenor's standing -- or

2049rebidding the subject projects, with more explicit conflict - of -

2060interest provisions addressing the tiers of participants and the

2069effect of marriage between two principals o f any of the

2080participants, at whatever tier. The incompleteness of counsel's

2088recommendation in selecting one of these two options, if

2097Petitioner's proposal were rejected, would have been even more

2106problematic in this case, if Intervenor had prevailed.

211426. How ever, accepting the parties' understanding of the

2123posture of this case, Petitioner bears the burden of proving

2133that the rescission of the award to it, and implicit award to

2145Intervenor, would be contrary to statutes, rules, or policies or

2155the RFQ.

215727. The mater ial facts of this case are not in dispute.

2169Petitioner submitted the lowest bid and would have received the

2179award, but for the issue raised by Intervenor concerning a

2189conflict of interest involving Fraga Engineers.

219528. Fraga Engineers works indirectly with Res pondent on

2204the subject projects and works with Petitioner on other

2213projects, but does not work even indirectly with Petitioner on

2223the subject projects, unless Ms. Fraga and Mr. Silva are

2233interchangeable due to their marriage. For these projects,

2241Fraga Eng ineers is a second - tier consultant to Respondent's DCP.

2253Although Fraga Engineers is on Respondent's DCP Team for the

2263subject projects and Respondent retains the right not to allow

2273its DCP to remove Fraga Engineers, the DCP, not Fraga Engineers,

2284is under c ontract with Respondent for these projects.

2293Contractually, Fraga Engineers' only relationship with these

2300projects is under a subcontract with the DCP.

230829. Fraga Engineers serves as a third - tier consultant to

2319Silva Architects on projects for which Petitioner is the first -

2330tier contractor. However, as noted above, for the subject

2339projects, Fraga Engineers' only relationship with Petitioner's

2346team is that Ms. Fraga -- claimed by Intervenor to be better known

2359as Mrs. Silva -- is married to Mr. Silva.

236830. None of these r elationships among Petitioner,

2376Respondent, Silva Architects, and Fraga Engineers violates any

2384applicable statutes, rules, or policies or any specifications of

2393the RFQ, with respect to the creation of a conflict of interest

2405that would necessitate or justify the disqualification of

2413Petitioner or the rejection of its proposal.

242031. The only conflict - of - interest provision in the RFQ is

2433Paragraph I.H. This conflict - of - interest provision requires two

2444conditions for a determination of the ineligibility of the

2453offeror or rejection of its proposal. In this case, neither of

2464these conditions is met.

246832. First, Fraga Engineers is not part of Petitioner's

2477team for these projects. For these projects, the little -

2487mentioned Mr. Aguirre, not Fraga Engineers, serves as the

2496mechani cal, electrical, plumbing, and fire - suppression engineer.

2505RFQ Paragraph I.H covers the current members of Petitioner's

2514team for the two high - school additions that are the subject of

2527this RFQ. Nothing in the RFQ or Respondent's rules or policies

2538extends t he disqualification from the members of the offeror's

2548team on the subject projects to members of its team on past

2560projects or other ongoing projects. Nor do the RFQ or

2570Respondent's rules and policies require or permit Respondent to

2579treat Silva Architects as though it were Fraga Engineers due to

2590the marriage of the principals of the two entities. The RFQ and

2602Respondent's rules and policies contain no attribution rules,

2610under which Ms. Fraga would be treated as the principal of Silva

2622Architects due to her m arriage with Mr. Silva.

263133. Second, Fraga Engineers is not presently under

2639contract with Respondent for any project, including the subject

2648projects, for which Petitioner is the general contractor. The

2657participation of Fraga Engineers on the DCP Team for the se

2668projects is irrelevant under RFQ Paragraph I.H, which limits its

2678scope to entities under contract with Respondent. Fraga

2686Engineers is not under contract with Respondent, so its

2695involvement fails to trigger the RFQ's conflict - of - interest

2706provision.

270734. Th e parties stipulated at the start of the hearing

2718that Respondent had no rule or policy that would define a

2729conflict of interest based on a spousal relationship, except for

2739such a relationship with an employee of Respondent. So, the

2749sole remaining source o f authority for disqualifying Petitioner

2758or rejecting its proposal, on the basis of a conflict of

2769interest, would be a state statute or rule.

277735. The only applicable conflict - of - interest provision in

2788the statutes is Section 287.055(9)(b), Florida Statutes, whi ch

2797Section 1013.45(1)(b), Florida Statutes, applies to design - build

2806contracts for School Board building construction. Section

2813287.055(9)(b), Florida Statutes, states: "A design criteria

2820professional who has been selected to prepare the design

2829criteria pa ckage is not eligible to render services under a

2840design - build contract executed pursuant to the design criteria

2850package." Respondent's Rule 6Gx13 - 7B - 1.021(III)(A) states the

2860same prohibition.

286236. The present arrangement does not violate Section

2870287.055(9)(b), Florida Statutes. The statute speaks of the DCP,

2879not a member of the DCP Team. This statute merely prohibits the

2891DCP, Santos/Raimundez Architects, P.A., from rendering design -

2899build services for the subject projects.

290537. As Intervenor noted in its formal w ritten protest,

2915Florida Administrative Code Rule 60D - 5.0071(9) provides that "an

2925agency" may reserve the right to reject a bid when it determines

2937that a "conflict of interest exists." In RFQ Paragraph I.H,

2947Respondent reserved the right to reject a bid if a conflict

2958existed, and, as noted above, no such conflict exists.

296738. More importantly, though, Florida Administrative Code

2974Rule 60D - 5.0071(9) is inapplicable to this case. This rule is

2986promulgated by the Florida Department of Management Services,

2994pursuant to Section 255.29, Florida Statutes, which applies to

3003the construction of state buildings, not School Board buildings.

3012Chapter 1013, Florida Statutes, authorizes the Florida

3019Department of Education to exercise certain supervisory

3026responsibilities over the construction of School Board

3033buildings. The Florida Department of Education rule applicable

3041to such construction is at Florida Administrative Code Rule

30506 - 2.001, and it does not address conflicts of interest.

306139. Lacking any authority for rejecting Petitione r's

3069proposal on the basis of a conflict of interest set forth in any

3082statute, rule, School Board policy, or the RFQ, Respondent's

3091counsel necessarily based his rescission recommendation on a

3099perceived or potential conflict of interest not stated in the

3109sta tutes, rules, policies, or RFQ. However, this conflict of

3119interest lacks any definition, even after the hearing in this

3129case, and emerged only after the opening of the proposals.

313940. In the abstract, conflicts of interest find little

3148support due to the obvi ous potential for misdealing between the

3159persons with the conflict. Respondent's counsel was trying to

3168bolster the competitive - bidding process by adding this ill -

3179defined conflict - of - interest provision after the proposals had

3190been opened. Unfortunately, t he effect of counsel's action is

3200the opposite. Allowing agencies to add new, vague conflict - of -

3212interest requirements to a procurement after the bids or

3221proposals are opened invites manipulation of the bidding process

3230and subverts competitive bidding when, as here, the agency

3239selects a higher bid over the lowest bid of an offeror that

3251failed to comply with this new, vague requirement. As must

3261bidders, so must agencies abide by the specifications of their

3271bid packages and may not select a bidder that has co nformed to

3284an undisclosed, poorly defined bid specification, to which a

3293lower bidder failed to conform.

329841. Petitioner has proved that no conflict - of - interest

3309provision requires or permits the disqualification of Petitioner

3317or rejection of its proposal and tha t Respondent's proposed

3327disqualification of Petitioner and rejection of Petitioner's

3334proposal subverts the competitive bidding process. Petitioner

3341has thus proved that the proposed agency action adverse to

3351Petitioner is contrary to Section 1013.46(1)(a), Florida

3358Statutes, which requires Respondent to award the contract to the

"3368lowest responsible bidder."

3371RECOMMENDATION

3372It is

3374RECOMMENDED that Respondent enter a final order awarding

3382the contract to Petitioner.

3386DONE AND ENTERED this 14th day of December, 2004, in

3396Tallahassee, Leon County, Florida.

3400S

3401___________________________________

3402ROBERT E. MEALE

3405Administrative Law Judge

3408Division of Administrative Hearings

3412The DeSoto Building

34151230 Apalachee Parkway

3418Tallahassee, Florida 32399 - 3060

3423(850) 488 - 9675 SUNCOM 278 - 9675

3431Fax Filing (850) 921 - 6847

3437www.doah.state.fl.us

3438Filed with the Clerk of the

3444Division of Administrative Hearings

3448this 14th day of December, 2004.

3454COPIES FURNISHED:

3456Dr. Rudolph F. Crew, Superintendent

3461Miami - Dade County School Board

34671450 Northeast Second Avenue

3471Miami, Florida 33132 - 1394

3476Daniel J. Woodring, General Counsel

3481Department of Education

3484325 West Gaines Street, Roo m 1244

3491Tallahassee, Florida 32399 - 0400

3496Ira Libanoff

3498Ferencik Libanoff Brandt

3501Bustamante and Williams, P.A.

3505150 South Pine Island Road, Suite 400

3512Fort Lauderdale, Florida 33324

3516Luis M. Garcia

3519Miami - Dade County School Board

35251450 Northeast 2nd Avenue, Sui te 400

3532Miami, Florida 33132

3535J. Alfredo de Armas

3539Alvarez, Armas & Borron, P.A.

35443211 Ponce De Leon Boulevard, Suite 302

3551Coral Gables, Florida 33134

3555NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

3561All parties have the right to submit written exceptions within

357110 days from the date of this recommended order. Any exceptions

3582to this recommended order must be filed with the agency that

3593will issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 02/04/2005
Proceedings: Agency Final Order filed.
PDF:
Date: 01/19/2005
Proceedings: Agency Final Order
PDF:
Date: 12/14/2004
Proceedings: Recommended Order
PDF:
Date: 12/14/2004
Proceedings: Recommended Order (hearing held October 13, 2004). CASE CLOSED.
PDF:
Date: 12/14/2004
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 12/13/2004
Proceedings: Petitioner`s Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 12/13/2004
Proceedings: Notice of Filing MCM`s Proposed Findings of Fact and Conclusions of Law (filed via facsimile).
PDF:
Date: 12/13/2004
Proceedings: Proposed Recommended Order (filed by Respondent via facsimile).
PDF:
Date: 12/13/2004
Proceedings: MCM`s Proposed Findings of Fact and Conclusions of Law (filed via facsimile).
PDF:
Date: 12/02/2004
Proceedings: Transcript filed.
PDF:
Date: 10/18/2004
Proceedings: Letter to Judge Meale from L. Garcia enclosing Respondent`s exhibit O filed.
PDF:
Date: 10/13/2004
Proceedings: Unilateral Pre-hearing Stipulation filed.
Date: 10/13/2004
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 10/12/2004
Proceedings: BCA`s Response and Objection to MCM`s Notice to Produce at Trial (filed via facsimile).
PDF:
Date: 10/12/2004
Proceedings: MCM`s Notice to Produce at Trial (Final Hearing) filed via facsimile.
PDF:
Date: 10/12/2004
Proceedings: Petitioner`s Motion to Continue and/or Stay filed.
PDF:
Date: 10/12/2004
Proceedings: MCM`s Notice of Filing Pretrial Stipulation (filed via facsimile).
PDF:
Date: 10/12/2004
Proceedings: Petitioner`s Exhibit List (filed via facsimile).
PDF:
Date: 10/12/2004
Proceedings: Petitioner`s Witness List (filed via facsimile).
PDF:
Date: 10/12/2004
Proceedings: (Joint) Pre-hearing Stipulation (filed via facsimile).
PDF:
Date: 10/08/2004
Proceedings: Order Denying Petitioner`s Motion to Continue and/or to Stay.
PDF:
Date: 10/08/2004
Proceedings: Magnum Construction Management Corporation`s Witness and Exhibits List (filed via facsimile).
PDF:
Date: 10/07/2004
Proceedings: MCM`s Objections to Continuance (filed via facsimile).
PDF:
Date: 10/07/2004
Proceedings: Letter to J. De Armas from I. Libanoff regarding taking the deposition of I. Farga (filed via facsimile).
PDF:
Date: 10/07/2004
Proceedings: Letter to J. DeArmas from I. Libanoff regarding Ms. Fraga`s withdrawal (filed via facsimile).
PDF:
Date: 10/07/2004
Proceedings: Petitioner`s Response to Intervenor`s Motion for Sanctions (filed via facsimile).
PDF:
Date: 10/07/2004
Proceedings: Petitioner`s Notice of No Objection and Supplement to Motion to Continue and/or Stay (filed via facsimile).
PDF:
Date: 10/06/2004
Proceedings: Petitioner`s Motion to Continue and/or to Stay (filed via facsimile).
PDF:
Date: 10/05/2004
Proceedings: Magnum Construction Management Corporation (Hereinafter "MCM") Notice of Taking Deposition of Party (Representative of Betancourt-Castellon and Associates) filed via facsimile.
PDF:
Date: 10/05/2004
Proceedings: MCM`s First Request for Production (filed via facsimile).
PDF:
Date: 10/05/2004
Proceedings: (Joint) Pre-hearing Stipulation (filed via facsimile).
PDF:
Date: 10/05/2004
Proceedings: MCM`s Motion for Sanctions (filed via facsimile).
PDF:
Date: 09/29/2004
Proceedings: Notice of Administrative Hearing to Interested or Affected Parties (filed by L. Garcia via facsimile).
PDF:
Date: 09/27/2004
Proceedings: Order Granting Intervention. (Magnum Construction Management Corporation)
PDF:
Date: 09/27/2004
Proceedings: MCM`s First Request for Production (filed via facsimile).
PDF:
Date: 09/24/2004
Proceedings: Magnum Construction Management Corporation (Hereinafter "MCM") Petition to Intervene as Interested Party filed by via facsimile.
PDF:
Date: 09/17/2004
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 09/17/2004
Proceedings: Notice of Hearing (hearing set for October 13, 2004; 9:00 a.m.; Miami, FL).
PDF:
Date: 09/17/2004
Proceedings: Letter to Mr. Garcia from I. Libanoff, Esquire regarding Project A-0854 SW Miami Sr. High; A-0855 Miami Killian Sr. High (filed via facsimile).
PDF:
Date: 09/17/2004
Proceedings: Bid Protest (filed via facsimile).
PDF:
Date: 09/17/2004
Proceedings: Formal Bid Protest on MDCPS Project Nos. A0854 (Addition to Southwest Senior High School) and A0855 (Addition to Miami Killian Senior High School) filed via facsimile.
PDF:
Date: 09/17/2004
Proceedings: Agency referral (filed via facsimile).

Case Information

Judge:
ROBERT E. MEALE
Date Filed:
09/17/2004
Date Assignment:
09/17/2004
Last Docket Entry:
02/04/2005
Location:
Mango, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (6):