05-000007BID
Compass Environmental, Inc., And Shaw Environmental, Inc. vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Monday, March 21, 2005.
Recommended Order on Monday, March 21, 2005.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8COMPASS ENVIRONMENTAL, INC., )
12and SHAW ENVIRONMENTAL, INC., )
17)
18Petitioners, )
20)
21vs. )
23) Case Nos. 05 - 0007BID
29DEPARTMENT OF ENVIRONMENTAL ) 05 - 0008BID
36PROTECTION, )
38)
39Respondent, )
41)
42and )
44)
45CDM CONSTRUCTORS, INC., )
49)
50Intervenor. )
52_____________________________ )
54RECOMMENDED ORDER
56This matter was heard before the Division of
64Administrative Hearings by its assigned Administrative Law
71Judge, Donald R. Alexander, on February 2, 3, 4, and 7, 2005, in
84Tallahassee, Florida.
86APPEARANCES
87For Petitioner: J. Andrew Bertron, Jr., Esquire
94(Compass) Amy W. Schrader, Esquire
99H uey, Guilday, Tucker, Schwartz
104& Williams, P.A.
107Post Office Box 12500
111Tallahassee, Florida 32317 - 2500
116For Petitioner: Seann M. Frazier, Esquire
122(Shaw) John K. Lond ot, Esquire
128Greenberg Traurig, P.A.
131Post Office Box 1838
135Tallahassee, Florida 32302 - 1838
140Dorn C. McGrath, III, Esquire
145Greenberg Traurig, P.A.
1481750 Tysons Boulevard, Suite 1200
153McLean, Virginia 22102 - 4208
158For Respondent: Thomas M. Beason, Esquire
164Marshall G. Wiseheart, Esquire
168Francine M. Ffolkes, Esquire
172Brian J. Cross, Esquire
176Department of Environmental Protection
1803900 Commonwealth Boulevard
183Mail Station 35
186Tallahassee, Florida 32399 - 3000
191For Intervenor: A. Kenneth Levine, Esquire
197Chistopher J. Karo, Esquire
201Tew Cardenas, LLP
204215 South Monroe Street, Suite 702
210Tallahassee, Florida 3 2301 - 1839
216STATEMENT OF THE ISSUE
220The issue is whether the Department of Environmental
228Protection's (Department's) proposed award of a contract to
236Intervenor, CDM Constructors, Inc. (CDM), is contrary to the
245Department's governing statutes, rules or polic ies, or the
254solicitation's specifications.
256PRELIMINARY STATEMENT
258This matter began on December 7, 2004, when the Department
268advised all vendors who had filed proposals that it intended to
279award a contract for Solicitation Number 2005002C to CDM. The
289contr act calls for CDM to assist the Department in the
300management and closure of the Piney Point Phosphates
308Phosphogypsum Stack System (Piney Point) in Manatee County,
316Florida.
317On December 9, 2004, Petitioners, Compass Environmental,
324Inc. (Compass) and Shaw E nvironmental, Inc. (Shaw), who had also
335participated in the solicitation process, gave timely notice
343that they intended to file a formal written protest to the
354proposed award. Formal written protests were filed by both
363Petitioners on December 20, 2004. I n its protest, Compass
373contended that the negotiation process was flawed because a
382member of the Department's evaluation committee (Dr. Fuliehan)
390had an actual or apparent conflict of interest because one of
401his consulting firm's clients was a subcontracto r listed in
411CDM's proposal. In its protest, Shaw raised the same conflict
421of interest issue, and further contended that the proposals of
431CDM and Compass were non - responsive, that the evaluations were
442not conducted in the "sunshine," as required by Florida law, and
453that the scoring of the responses was arbitrary, capricious, and
463contrary to competition.
466The matter was referred by the Department to the Division
476of Administrative Hearings on January 3, 2005, with a request
486that an Administrative Law Judge b e assigned to conduct a
497hearing. Compass's protest was assigned Case No. 05 - 0007BID,
507while Shaw's protest was assigned Case No. 05 - 0008BID. On
518January 14, 2005, CDM's Petition to Intervene was granted.
527By Notice of Hearing dated January 6, 2005, a fi nal hearing
539was scheduled on February 2 and 3, 2005, in Tallahassee,
549Florida. Continued hearings were held on February 4 and 7,
5592005.
560On January 28, 2005, Shaw filed a Petition for Review of
571Non - Final Agency Action and Motion to Stay with the First
583Distr ict Court of Appeal seeking to stay the Department's
593decision to continue contract negotiations with CDM until this
602protest is resolved. The Motion to Stay was denied on March 2,
6142005; a decision on the merits of the case remains pending. See
626Shaw Enviro nmental, Inc. v. State, Department of Environmental
635Protection et al. , Case No. 1D05 - 407.
643On January 28, 2005, the Department's Motion for Protective
652Order was denied in part and Petitioners were allowed to depose
663Theresa L. Mussetto, a Department attorn ey serving as the
673Department's Ethics Officer, regarding certain ethical issues.
680At the outset of the final hearing, the Department's Motion in
691Limine and to Strike Portions of Petitioners' Petitions for
700Hearing was denied. A ruling on a similar Motion b y CDM filed
713the morning of the final hearing was reserved. The Motion is
724hereby denied.
726On January 31, 2005, the parties consented to the entry of
737an Agreed Confidentiality Order, which allowed the parties to
746review, under specified conditions, certain d ocuments and other
755information that Ardaman & Associates, Inc. (Ardaman), an
763outside consulting firm used by the Department, asserted were
772confidential and constituted trade secrets. That information is
780found in Shaw Exhibit 64 and has been sealed to prot ect its
793confidentiality. In addition, during the course of the hearing,
802certain confidential information was discussed, and that portion
810of the record has been transcribed in a separate volume of the
822Transcript and sealed to protect its confidentiality.
829A t the final hearing, Compass presented the testimony of
839Tom McSweeney, its vice - president; and Charles E. Icenogle, a
850consultant. Also, it offered Compass Exhibits 12, 21, 24, 32,
86056, and 61, which were received in evidence. Exhibit 56 is the
872deposition testimony of William Perpich, an employee of U.S.
881Filter, which operates a reverse osmosis system at Piney Point.
891Shaw presented the testimony of Gwenn D. Godfrey, Department
900Procurement Administrator; Phil Coram, Chief of the Department's
908Bureau of Mine Reclamation; Dr. Nadim F. Fuleihan, a consultant;
918Earl Black, an attorney at the Department of Revenue; Ivan
928Nance, a Project Manager at the Piney Point facility; Bruce
938Scott, a Project Manager at the Piney Point facility; James E.
949Fendley, Vice - President of Commercial Construction; and Barbara
958F. Phillips, a Procurement Analyst at the Department of Revenue.
968Also, it offered Shaw Exhibits 21, 54, 61, and 64, which were
980received in evidence. Exhibit 54 is the deposition of Theresa
990L. Mussetto, a Department attorney. The Department presented
998the testimony of Phil Coram, Chief of the Department's Bureau of
1009Mine Reclamation; Dr. Nadim F. Fuleihan, a consultant and
1018accepted as an expert; Robert H. Brown, a Senior Environmental
1028Administrator with Manatee County ; Gwenn D. Godfrey, Department
1036Procurement Administrator and accepted as an expert; Sam Zamani,
1045Department Administrator of the Phosphate Management Program;
1052John Wright, a Department professional engineer; Earl Black, a
1061Department of Revenue attorney; Bar bara F. Phillips, a
1070Procurement Analyst at the Department of Revenue; and Jon Alden,
1080a Department attorney. Also it offered Department Exhibits 1,
10892, 4 - 6, 8, 9, 14, 16, 17, 23, 27, and 43. Exhibits 16 and 17
1106were not admitted while a ruling was reserved on Exhibit 43.
1117All other exhibits were received. Exhibit 43 is also received
1127in evidence. CDM presented the testimony of Michael Edgar, a
1137Client Officer; Dr. Vaughn Astley, a consultant and accepted as
1147an expert; and Craig A. Kovach, a consultant and ac cepted as an
1160expert. Also, it offered CDM Exhibit 1, which was received in
1171evidence. Finally, the parties offered Joint Exhibits 1, 4 - 11,
118213, 16, 22, 23, 26 - 28, 34 - 36, 38, 39, and 41, which were
1198received in evidence.
1201The Transcript of the hearing (eight volumes) was filed on
1211February 16, 2005. Proposed Findings of Fact and Conclusions of
1221Law were filed by the parties on February 28, 2005, and they
1233have been considered by the undersigned in the preparation of
1243this Recommended Order.
1246FINDINGS OF FACT
1249Bas ed on all of the evidence, the following findings of
1260fact are made:
1263a. Background
12651. Piney Point is an abandoned fertilizer manufacturing
1273plant adjacent to Port Manatee in Manatee County. In the
1283fertilizer manufacturing process, phosphate rock is conver ted
1291into soluble phosphorus by adding sulfuric acid to the phosphate
1301rock to produce phosphoric acid. A by - product of this activity
1313is phosphogypsum. For every ton of phosphoric acid produced,
1322approximately five tons of phosphogypsum are produced. The
1330p hosphogypsum is stored in stacks like the ones at Piney Point.
13422. Federal and state regulations require that the
1350phosphogypsum be managed in stack systems. (Stack systems are
1359large impoundments containing contaminated water that has come
1367into contact w ith the phosphogypsum.) This is accomplished by
1377using process water to "slurry" the phosphogypsum to the stacks
1387where the phosphogypsum settles out.
13923. The process water becomes extremely polluted as a
1401result of the manufacturing activities and is typ ically very
1411acidic. It contains heavy metals, such as arsenic, cadmium,
1420chromium, and fluoride, in addition to high levels of nutrients,
1430nitrogen, and total dissolved solids. It is also slightly
1439radioactive. The process water is stored in impoundments
1447s urrounded by the phosphogypsum stacks, in cooling ponds, and in
1458the seepage ditches around the stacks.
14644. The Piney Point site is located south of Tampa,
1474approximately one mile inland from Bishops Harbor, which is a
1484portion of Tampa Bay. The site encom passes a total of
1495approximately six hundred acres. There are two phosphogypsum
1503stacks located at Piney Point; each of these is divided into two
1515compartments or ponds. Today, the old gypsum stack rises to a
1526height of eighty feet. The site previously held around 1.4
1536billion gallons of process water with 800 million gallons stored
1546in the various ponds and 600 million gallons stored in the pores
1558of the gypsum stacks as pore water. The site is currently
1569estimated to have 500 to 550 million gallons of process water of
1581which about 350 million gallons is pore water. All of this
1592water must be treated and removed in order to close and
1603remediate the site.
16065. To close one of these phosphogypsum stack systems, all
1616of the water must be removed from the ponds. The surface is
1628allowed to dry and is then graded. A polyethylene liner is
1639placed over the surface and than a soil cover is placed on top
1652of the liner. The liner prevents any additional rainfall from
1662infiltrating into the gypsum stack and creating additional
1670process water. The pore water underneath the liner is then
1680allowed to drain from the stack and is collected in seepage
1691ditches, where the water will ultimately be treated. A thick
1701layer of grass is grown on the steep slopes of the gypsum stacks
1714to help prevent infiltration of rainwater back into the stacks.
1724The ultimate goal is to convert this site into a freshwater
1735reservoir for the residents of Manatee County.
17426. Until early 2001, Piney Point Phosphates, Inc., which
1751was a subsidiary of Mulberry Pho sphate Company (Mulberry), owned
1761and operated a fertilizer manufacturing complex at Piney Point.
1770(Mulberry also operated another fertilizer manufacturing complex
1777in Mulberry, Florida). In February 2001, Mulberry filed a
1786petition for protection from credi tors in the United States
1796Bankruptcy Court in Tampa, Florida. At the same time, Mulberry
1806notified the Department that it did not have the resources to
1817maintain the site. (The Department was also advised by Mulberry
1827that it did not have the resources to m aintain the stack system
1840at the Mulberry site.)
18447. Because there existed the potential for release of the
1854contaminated waters from Piney Point into Tampa Bay, the
1863Department immediately assumed financial responsibility for
1869Piney Point and in May 2001, a state court appointed a Receiver
1881for Piney Point to take "all reasonable steps and action to
1892preserve the Property's environmental integrity and its
1899compliance with environmental regulations." To execute these
1906duties, the Receiver entered into a contract with the
1915Department. Pursuant to that contract, it retained the services
1924of Ardaman, an international engineering consulting firm in
1932Orlando, Florida, as its engineer of record to design a plan to
1944close Piney Point and to ensure that the plan was properly
1955implemented. At about the same time, the Receiver contracted
1964with IT Corporation, the predecessor to Shaw, to begin some of
1975the site closure work on an emergency basis. Since that time,
1986the Department has spent $63 million at Piney Point, with Shaw
1997rece iving a majority of that amount.
20048. Based on the Departments experience at the Mulberry
2013site, it believed that it could realize a significant savings to
2024the State through the Invitation to Negotiate (ITN) process and
2034the use of a lump sum contract, rathe r than continuing to
2046contract out the work for Piney Point on a time and materials
2058basis. Further, the Department's Inspector General had
2065recommended a lump sum contract as an incentive to the
2075contractor selected to conduct the closure work.
2082b. The ITN
20859. Under Section 403.4154(3)(a), Florida Statutes (2004), 1
"2093[t]he department may take action to abate or substantially
2102reduce any imminent hazard caused by the physical condition,
2111maintenance, operation, or closure of a phosphogypsum stack
2119system." Pursu ant to this provision, on July 16, 2004, the
2130Department issued ITN No. 2005002C (the ITN) entitled "Closure
2139of the Piney Point Phosphogypsum Stack System." The contract
2148called for a contractor to provide services at the Piney Point
2159site in three primary a reas: continued operation and
2168maintenance of the site; water consumption; and closure of the
2178phosphogypsum stack system. Water consumption consists of
2185treating the process water and pore water and removing it from
2196the site by evaporation, irrigation, dis charge, or other
2205methods. Closure of the stacks includes draining water from the
2215stacks, grading the banks, and installing liners, clean soil,
2224and sod. The contract is estimated to be worth approximately
2234$51.2 million to the successful vendor. The contr act was
2244intended to replace the Receiver's existing contract with Shaw,
2253although Shaw was free to compete for the new contract.
226310. A number of individuals were involved with developing
2272the ITN. First, Gwenn D. Godfrey, who is the Department's
2282Procuremen t Administrator, assisted with the original ITN.
2290Also, Phil Coram, who is the Department's Chief of the Bureau of
2302Mine Reclamation, was heavily involved with the ITN and assumed
2312a major role on technical issues such as operation and
2322maintenance as well as water management planning. Although the
2331Department does not normally use private consultants in the
2340procurement process, due to the complex technical issues
2348involved, it retained Ardaman to assist with the procurement
2357process. Ardaman, who was then serv ing as engineer of record on
2369the project, does approximately 90 to 95 percent of all work
2380performed in Florida in the area of phosphogypsum stack systems
2390and has special expertise in that area. (As noted above,
2400Ardaman designed the complex closure plan fo r the facility.)
2410One of its employees, Dr. Nadim Fuleihan, a senior vice
2420president and principal engineer, has served as the chief
2429engineer for the Piney Point project since 2001 and has worked
2440closely with Mr. Coram, who has been the Department's
2449coordin ator on the project since 2002. According to Mr. Coram,
2460Dr. Fuleihan "knew more about that site, especially the closure
2470aspects, . . . than anyone." This observation was undisputed.
2480For that reason, Dr. Fuleihan was requested to assist in the
2491procuremen t process.
249411. Mr. Coram was asked by Department management to
2503identify individuals to serve as evaluators for the ITN process.
2513Besides Dr. Fuleihan, management wanted the evaluators to
2521consist of Department employees within the Bureau of Mine
2530Reclamatio n, the Division of Waste Management, the Office of
2540General Counsel, and representatives from other agencies that
2548had been involved with Piney Point.
255412. The seven ITN evaluators consisted of Mr. Coram;
2563Dr. Fuleihan; Sam Zamani, Administrator for the Department's
2571Phosphate Management Program; John Wright, a professional
2578engineer in the Department's Division of Waste Management; Jon
2587Alden, a Department attorney who has represented the Department
2596in the Mulberry bankruptcy case; Robert Brown, a Senior
2605En vironmental Administrator for Manatee County; and Richard
2613Eckenrod, Executive Director of the Tampa Bay Estuary Program
2622(TBEP).
262313. Before the evaluation process began, the Department
2631required all members of the evaluation team to sign a
2641certification t hat if "at any time during [their] participation
2651on the contractor selection committee, that a potential conflict
2660of interest exists," they agreed to notify the Department's
2669Procurement Section of the circumstances surrounding the
2676potential conflict of int erest. By doing so, the Department
2686complied with Section 287.057(20), Florida Statutes, which
2693requires that if the procurement costs more than $25,000.00,
"2703the individuals taking part in the development or selection of
2713criteria for evaluation, the evaluat ion process, and the award
2723process shall attest in writing that they are independent of,
2733and have no conflict of interest in, the entities evaluated and
2744selected." A requirement that the certification form be
2752executed by each team member is also found in the solicitation
2763instructions. Significantly, the certification form imposed a
2770continuing obligation on the evaluators to notify the Department
2779should any "potential conflict of interest arise."
278614. Prior to submitting responses, three potential
2793vendors, Shaw, Compass, and CDM, contacted Dr. Fuleihan and
2802asked him to participate on their respective teams in the ITN
2813process. Dr. Fuleihan declined to work with any of them on an
2825exclusive basis. Tetra Tech, Inc., which is Ardaman's parent
2834company, also con sidered preparing a response to the ITN but
2845Dr. Fuleihan advised it not to do so since Ardaman's status as
2857engineer of record could raise a conflict of interest.
286615. On September 10, 2004, CDM, Compass, Shaw, and Coburn
2876Construction (Coburn) submitted re plies to the ITN. The
2885Department subsequently deemed the reply by Coburn to be non -
2896responsive for its failure to comply with the requirements of
2906the ITN. Coburn did not challenge this determination. The
2915other proposals were independently reviewed, score d, and ranked.
2924The results were given to Mr. Coram, who computed an average
2935rank for each of the firms. The final average rankings were
2946very close with Shaw being ranked first, followed by Compass and
2957CDM, who were tied.
296116. After the initial replies we re filed, Mr. Eckenrod
2971became concerned that he had a potential conflict of interest
2981with Craig A. Kovach, President of QuietEarth Consultants, Inc.,
2990which was identified as a CDM subcontractor and team member.
3000Mr. Kovach's wife served on the TBEP Board o f Directors and had
3013hiring and firing authority over Mr. Eckenrod. Accordingly,
3021Mr. Eckenrod emailed the Department's Office of General Counsel
3030for a determination of whether a conflict existed.
303817. Under the Department's Code of Ethics, which is also
3048known as Administrative Directive DEP 202 (DEP 202),
"3056[e]mployees should avoid any conduct . . . which might
3066undermine the public trust, whether that conduct is unethical or
3076may give the appearance of ethical impropriety." See Compass
3085Exhibit 32, DEP 202 , paragraph 7.a. In addition, another
3094document known as DEP 315 establishes Department policy for the
3104purchase of contractual and professional services. See Compass
3112Exhibit 61. Paragraph 26 of DEP 315 adopts the standards of
3123conduct for public officers and employees which are codified in
3133Section 112.313(3) and (7)(a), Florida Statutes. While not
3141specifically applicable to Mr. Eckenrod's situation, among other
3149things, that paragraph prohibits Department employees from
3156having an "employment or contractual relationship with any
3164business entity . . . which is . . . doing business with" the
3178Department.
317918. Teresa L. Mussetto, a Department attorney who then
3188served as a Department Ethics Officer on behalf of the General
3199Counsel, issued an opinion on September 29, 2004, stating in
3209part that even though Mr. and Mrs. Kovach had never sought to
3221influence Mr. Eckenrod, his professional association with a
3229member of the CDM team "may be perceived as a conflict of
3241interest," and that if the contract were ultimately awa rded
3251to CDM, the transaction might "reasonably give rise to the
3261'appearance of impropriety.'" See Shaw Exhibit 21. Ms.
3269Mussetto also determined that even though Mr. Eckenrod was not a
3280Department employee, he acted as an integral part of the
3290procuremen t team and that DEP 202 was applicable to him. (It
3302follows that DEP 315 would likewise apply.) Because DEP 202
3312requires that every aspect of the procurement process be
3321conducted in a manner which would not undermine the public trust
3332or lead a reasonable person to question its fairness and
3342impartiality, Mr. Eckenrod's potential conflict with CDM's
3349subcontractor was a sufficient basis for his removal from the
3359evaluation team, and he did not participate further in the
3369process.
337019. On October 12, 2004, the D epartment gave notice of its
3382rankings of the vendors and informed them that it intended to
3393exercise its right to conduct oral discussions with all three
3403vendors. The firms would then be asked to submit Best and Final
3415Offers (BAFOs) which would be scored a new. This was consistent
3426with the ITN, which provided that the Department "reserves the
3436right to short list respondents deemed to be in the competitive
3447range to conduct oral discussions prior to the final
3456determination of contract award." The decision to conduct oral
3465discussions was made by senior management in the Department at
3475the time scores were posted for the replies to the ITN. The
3487Secretary of the Department, along with other senior management,
3496determined oral discussions would be conducted with a ll three
3506vendors to assist in formulating the BAFO Instructions
3514(Instructions) and then the Department would proceed to score
3523the BAFOs. No one has challenged this process.
3531c. Development of the BAFO Instructions
353720. Before drafting the Instructions, th e Secretary of the
3547Department met with Earl Black, a Department of Revenue
3556attorney, and Barbara F. Phillips, a Purchasing Analyst with the
3566same agency. Both individuals had substantial experience with
3574procurements and were asked to participate in the BAF O process.
3585They agreed and were added to the evaluation team. As finally
3596formed, the team consisted of two attorneys, four engineers, and
3606two persons with significant procurement experience. Six of the
3615eight had considerable prior knowledge of the Piney Point site.
362521. In an effort to refine the Instructions, CDM, Compass,
3635and Shaw each made oral presentations to the Department's
3644evaluators and other Department staff on November 3, 2004. All
3654of the evaluators, including Mr. Black and Ms. Phillips,
3663atte nded the oral presentation. As part of this process, the
3674vendors were able to ask questions of the evaluators, and the
3685evaluators were able to ask questions of the vendors.
369422. Following the oral discussions, another round of
3702discussions was held with each vendor. These discussions were
3711referred to as "negotiation sessions." The purpose of these
3720discussions was to better understand the cost elements and facts
3730of each vendors initial proposal in order to develop the
3740Instructions. Mr. Alden, Dr. Fulei han, Mr. Black, and
3749Ms. Phillips conducted these discussions with each vendor.
375723. The Instructions were drafted by a group of
3766individuals including Dr. Fuleihan, Mr. Black, Ms. Phillips,
3774Ms. Godfrey, Mr. Alden, and Mr. Coram. Dr. Fuleihan gave input
3785on the sections relating to technical issues primarily in the
3795scope of work, which included the process water consumption
3804section. He was also involved in revising the pricing summary
3814and developing the evaluation criteria. Neither Shaw nor
3822Compas s challenged any part of the Instructions.
383024. After the Instructions were completed, but before the
3839BAFOs were submitted by the three vendors, the Department again
3849required each evaluator to complete a second conflict of
3858interest certification. The form was similar to the earlier
3867certification in the procurement process and required that the
3876members certify that they had "no conflict of interest" with
3886the "entities being considered for the contract award." Like
3895the earlier form, it imposed a continuing obligation on the
3905evaluators to notify the Department should any potential
3913conflict of interest arise. The form listed CDM, Compass,
3922and Shaw as the relevant entities. Each member, including
3931Dr. Fuleihan, executed the certification. At that time,
3939Dr. Fuleihan was not aware of any projects that Ardaman was
3950doing for Shaw or Compass, and he did not believe that Ardaman
3962was doing any work for CDM because of a past disagreement with
3974one of the CDM entities that resulted in no work between the
3986com panies for many years.
399125. Section 1.19 of the Instructions provides that the
4000Department reserves the right to waive minor informalities or
4009irregularities in the offers received where such are merely a
4019matter of form and not substance and the correction of which are
4031not prejudicial to other vendors.
4036d. Evaluation of the BAFOs
404126. On November 15, 2004, the Department issued the
4050Instructions, which required that responses be filed by the
4059three vendors no later than Wednesday, December 1, 2004. The
4069Ins tructions also informed the vendors that negotiations with
4078the top - ranked vendor would begin immediately after the posting
4089of the scoring results. CDM, Compass, and Shaw timely submitted
4099their BAFOs on December 1, 2004. CDM's response indicated that
4109it p roposed to use a specific water treatment process relying on
4121The Mosaic Company (Mosaic) as its subcontractor. This company
4130was formed when the phosphate operations of the Cargill
4139Companies and IMC Global, Inc. were combined in October 2004, or
4150shortly be fore the BAFOs were filed.
415727. The evaluators located in Tallahassee were
4164individually given the responses submitted by CDM, Compass, and
4173Shaw on Thursday, December 2, 2004. For those evaluators
4182located outside of Tallahassee, the responses were given on
4191Friday, December 3, 2004. Pursuant to a specific set of
4201instructions provided by the Department, each evaluator, acting
4209independently, then individually ranked the BAFO responses.
421628. In order to determine the responsiveness of the BAFOs,
4226Ms. Godfrey used a checklist to review the individual submittals
4236and found that all three were complete. Also, Dr. Fuleihan, who
4247served as the subject matter expert, reviewed each proposal to
4257ensure that the qualifications of the persons identified in the
4267responses m et the minimum qualifications listed in the
4276Instructions. He determined that all three vendors met the
4285minimum qualifications. Therefore, the Department considered
4291all three vendors responsive to the Instructions and qualified
4300to perform the work. (If a n evaluator considered a particular
4311item in the response to be incomplete or defective, the
4321evaluator could reflect that by assigning a lower score to that
4332response.)
4333e. The BAFO Scoring Process
433829. For scoring purposes, each BAFO response was divided
4347in to approximately fifteen identified subcategories. A one - to -
4358five scale (with five being the highest score) was used to
4369evaluate each subcategory of the vendors response. The raw
4378scores for a given subcategory would be multiplied by a weight
4389factor that corresponded to that subcategory to arrive at a
4399weighted score for each subcategory. To obtain a total score
4409for each vendor, the weighted scores for each subcategory would
4419then be added together. The total weighted scores could range
4429between 0 and 220. Each vendor was then assigned a ranking
4440based on its weighted total score. The vendor with the highest
4451score received a rank of one, the second highest score received
4462a rank of two, and the third highest score received a rank of
4475three. If two or more ve ndors had identical weighted total
4486scores the ranks were added together and divided by two. (For
4497example, if Vendor A received a 175 and Vendors B and C each
4510received a 170, the vendors would be ranked as follows: Vendor
4521A - 1.0, Vendor B - 2.5, and Vend or C - 2.5.)
453430. After all the scores had been submitted, the ranks of
4545each vendor were averaged to determine the best proposal for the
4556State. Average ranks were used in order to normalize the
4566evaluations so that an especially generous or especially ha rd
4576grader would not skew the outcome.
458231. Each of the eight evaluators conducted an individual,
4591objective, and impartial review of the three responses to the
4601Instructions. They all spent four to five days, including a
4611weekend, reviewing each of the res ponses. (There is some
4621confusion regarding the actual amount of time that Mr. Zamani
4631spent reviewing the BAFOs. Documents offered by Shaw reflect
4640that he received the BAFOs on December 3 and returned his
4651rankings the following day, December 4. Testimony offered by
4660the Department reflects that he spent several days reviewing the
4670filings. Even if Shaw's time frame is correct, there is no
4681evidence that Mr. Zamani evaluated the BAFOs in an improper or
4692arbitrary manner.) The evaluators did not have any disc ussions
4702during the evaluation process about their evaluations. Outside
4710one phone call from Mr. Brown to Mr. Coram to clarify what the
4723vendors had received with the Instructions, the evaluators had
4732no contact with one another.
473732. Mr. Alden ranked CDM f irst with a score of 177,
4749Compass second with a score of 174, and Shaw third with a score
4762of 172. Mr. Black ranked CDM first with a score of 140, Compass
4775second with a score of 137 and Shaw third with a score of 106.
4789Mr. Brown ranked CDM first with a sco re of 205, Compass second
4802with a score of 183 and Shaw third with a score of 182. Mr.
4816Coram ranked Compass first with a score of 180, Shaw second with
4828a score of 175 and CDM third with a score of 170. Dr. Fuleihan
4842ranked CDM first with a score of 192, wh ile Compass and Shaw
4855tied with scores of 189. Ms. Phillips originally submitted her
4865evaluations with Compass ranked first with a score of 144, and
4876Shaw and CDM tied with a score of 141. Due to an error when she
4891transposed her scores from her notes to her score sheet, she
4902corrected her evaluations at the hearing. With the corrected
4911scores Compass was still ranked first with a score of 144, but
4923CDM was now second with a score of 143, and Shaw third with a
4937score of 139. However, this correction did not cha nge the final
4949results of the evaluation process. Mr. Wright ranked Shaw first
4959with a score of 183, Compass second with a score of 181, and CDM
4973third with a score of 166. Mr. Zamani ranked CDM first with a
4986score of 218, Compass second with a score of 210, and Shaw third
4999with a score of 191.
500433. After the evaluators submitted their score sheets, the
5013ranks were added up and averaged to obtain a final ranking for
5025each vendor. The final ranking was as follows: CDM was ranked
5036first with an average rank of 1.688, Compass second with an
5047average rank of 1.813, and Shaw third with an average rank of
50592.500. (If Dr. Fuleihan's scores were removed from the final
5069tabulation, as requested by Compass, then Compass would be the
5079highest ranked vendor.) On December 7, 2004, the Department
5088electronically posted a recommended award to CDM as the best -
5099ranked vendor. As predetermined in the Instructions, the
5107announcement also stated that negotiations would immediately
5114begin with CDM, and if those negotiations failed, it w ould then
5126negotiate with Compass, the second ranked vendor, and if those
5136failed, with Shaw, who was ranked last.
514334. Compass and Shaw timely filed their Notices of Protest
5153on December 9, 2004. On December 20, 2004, they timely filed
5164their Formal Written Protests. Both Petitioners have contended
5172that the process was flawed because Mosaic (a listed
5181subcontractor on CDM's proposal) was a client of Ardaman; that
5191Dr. Fuleihan had a conflict of interest which should have been
5202disclosed; and he should have recu sed himself from the process.
5213Shaw also contends (for the first time in its Proposed
5223Recommended Order) that at least two of the evaluators
5232(Mr. Black and Ms. Phillips) had little, if any, knowledge or
5243experience concerning the scientific and techni cal requirements
5251sought in the ITN and Instructions and were not qualified to
5262evaluate the responses. It also alleged that a Sunshine Law
5272violation may have occurred; that Mr. Zamani did not have a
5283sufficient amount of time to evaluate the proposals; 2 and that
5294the proposals of CDM and Compass were non - responsive in various
5306respects. The other contentions raised in Shaw's formal protest
5315and the Pre - Hearing Stipulation have not been addressed in its
5327Proposed Recommended Order and are deemed to have been
5336aba ndoned. The remaining contentions are discussed below.
5344f. Sunshine Law Violation
534835. There is no evidence that the evaluators met in closed
5359meetings. Rather than scoring as a group, each of the
5369evaluators scored the BAFOs separately and independently.
5376Therefore, there was no meeting of the evaluators that was
5386required to be conducted in the sunshine.
539336. No vendor attended the oral discussion meetings
5401between another vendor and the evaluation team. However, there
5410is no evidence that any of the vend ors asked to attend those
5423meetings or that the Department denied the vendors the ability
5433to attend.
5435g. Q ualifications of the Evaluators
544137. There was no allegation in the Pre - Hearing Stipulation
5452that any of the evaluators were unqualified. Although Shaw
5461elicited testimony on that issue at hearing, especially
5469regarding the qualifications of Mr. Black and Ms. Phillips, the
5479issue was not timely raised. Even if it was, the evidence does
5491not show that those two individuals, or any other member of the
5503team, w ere not qualified. Mr. Black and Ms. Phillips were
5514chosen for the team because of their extensive experience in
5524state procurement, and not for their technical or scientific
5533background. Mr. Black, who has been an attorney for thirty - two
5545years, is an Assis tant General Counsel and Section Chief for the
5557Department of Revenue (DOR). In this position, he has handled
5567numerous procurement cases for that agency. His duties include
5576handling procurement matters, leasing matters and administrative
5583functions for DOR . Prior to assuming his position at DOR, he
5595worked for fourteen years for the Department of Management
5604Services (DMS) as its primary attorney responsible for contracts
5613dealing with environmental issues.
561738. Ms. Phillips is a Purchasing Analyst for DOR with over
562828 years of procurement experience with the vast majority
5637involving solicitation evaluations. Her responsibilities
5642involve ensuring proper administration of complex contracts and
5650specifications, Invitations to Bid (ITB), Requests for Proposals
5658( RFP), ITNs, and advertisements. She develops guidelines and
5667procedures to facilitate the ITB/RFP/ITN process and has
5675evaluated procurement policies and procedures for DOR.
5682h. Conflict of Interest Issue
568739. In its response to the ITN, CDM identified IMC Global,
5698Inc., as a subcontractor for water treatment. After CDM's
5707initial reply was submitted, IMC Global, Inc. and a subsidiary
5717of Cargill merged to form a new company known as The Mosaic
5729Company. To conform its BAFO with this corporate merger, CDM
5739cha nged its response to reflect the new company as a
5750subcontractor for water treatment and consumption. Because
5757Ardaman had a contractual relationship with Mosaic at the time
5767the BAFOs were submitted, Petitioners have contended that
5775Dr. Fuleihan had a co nflict of interest, that he should have
5787disclosed this fact, and that he should have withdrawn from the
5798ITN process. They also contend that the Department dismissed
5807another non - employee evaluator, Richard Eckenrod, when it
5816learned that he had a potential conflict of interest and that
5827Dr. Fuleihan's circumstances are no different.
583340. When Mr. Coram suggested that Dr. Fuleihan participate
5842as an evaluator, he knew that it would be likely that Ardaman
5854would have contractual relationships with most or all o f the
5865phosphate companies over time. He expected Ardaman to continue
5874to have such contractual relationships in the future simply
5883because Ardaman does excellent work. However, he did not
5892hesitate to recommend Dr. Fuleihan because he had worked with
5902him on a daily basis for over the past three years and had known
5916him for at least ten years. Mr. Coram testified that he always
5928found Dr. Fuleihan's actions to be ethical and in the best
5939interests of the State.
594341. Dr. Ardaman is a Senior Vice President of A rdaman, a
5955member of its management team, and head of the firm's corporate
5966engineering group. He receives a salary, bonus, and stock
5975options; the bonus and stock options are tied to performance and
5986profitability of Ardaman and its parent company, Tetra Tec h,
5996Inc.
599742. IMC, The Cargill Companies, and Mosaic have been
6006clients of Ardaman. This is not surprising, however, because
6015Ardaman's clients include "the whole phosphate industry."
6022Indeed, Ardaman does approximately 90 to 95 percent of the
6032engineering wo rk performed in Florida involving phosphogypsum
6040stack systems, a fact well known by virtually all of the players
6052in the phosphate industry, including Petitioners. Over the last
6061five years, Ardaman has represented such clients as Agrico
6070Chemical Company, C F Industries, Inc., the United States Army
6080Corps of Engineers, the Florida Department of Community Affairs,
6089PCS Phosphate, Comanco Environmental Corporation, Moretrench
6095Environmental Services, Inc., Shaw Environmental, Inc. (and its
6103predecessor, IT Corpora tion), PENN PRO, Inc., and the Florida
6113Department of Transportation. The Department itself is among
6121Ardaman's most significant clients.
612543. When the ITN was first posted it was well known that
6137Dr. Fuleihan knew all of the principals of CDM, Compass, and
6148Shaw, including those who testified at the final hearing. In
6158fact, Dr. Fuleihan has worked on numerous occasions with most,
6168if not all, of the subcontractors and the consultants listed by
6179all three vendors in their BAFOs. All three vendors also knew
6190that Dr. Fuleihan had assisted with the ITN and BAFO processes
6201and was serving as an evaluator for the BAFOs. Prior to the
6213issuance of the Instructions, Dr. Fuleihan was present during
6222the oral discussions along with the other evaluators. He also
6232led the "ne gotiation sessions" where the Department was
6241gathering information to develop the Instructions. Only after
6249the Department proposed to award the contract to CDM on
6259December 7, 2004, did Petitioners challenge Dr. Fuleihan's
6267participation in the solicitatio n process and express a fear
6277that the process might be tainted.
628344. Mosaic is considered an important client for Ardaman.
6292However, there was no evidence that Ardaman would stand to gain
6303anything from Mosaic by it serving as a subcontractor. Under
6313the terms of the ITN, Ardaman will continue working for the
6324Department at Piney Point as the engineer of record regardless
6334of which vendor ultimately contracts with the Department.
6342Ardaman did not receive any additional work from IMC Global,
6352Inc., when it was conducting work at Piney Point in 2003, and
6364Ardaman does not expect to receive any additional work if Mosaic
6375returns to the site to assist with the operation of water
6386treatment equipment.
638845. Although it is characterized as an important team
6397member, Mo saic at most will have a limited role on CDM's team
6410and would receive very little financial benefit from this work.
6420Specifically, Mosaic will receive a nominal fee for allowing CDM
6430to use the patents on its reverse osmosis equipment and roughly
6441$50,000.00 for technical support in years three through five of
6452the project, or a total of less than one - tenth of one percent of
6467the estimated $52 million contract. (There is no guarantee that
6477Mosaic will even be used by CDM since the vendor has the right
6490to substi tute subcontractors during the post - award negotiation
6500process. In fact, CDM approached Mosaic because, at that time,
6510Dr. Vaughn Astley worked for Mosaic, and CDM wanted his
6520expertise and experience as part of CDM's team. Dr. Astley
6530subsequently retired f rom Mosaic, as planned.)
653746. There is no evidence that, as a result of Mosaic being
6549retained as a subcontractor for CDM, Ardaman or Dr. Fuleihan
6559would be given extra business over and above what they already
6570provide. There is also no evidence that as a result of CDM's
6582being awarded the contract that Dr. Fuleihan would have his
6592salary increased, obtain some sort of bonus, increase his stock
6602options, or be enriched in any way.
660947. There is no evidence that Dr. Fuleihan attempted to
6619influence the BAFO pro cess to the advantage of any particular
6630vendor. There is no evidence that he favored one vendor over
6641another when he assisted in the preparation of the Instructions,
6651determined whether the responses to the Instructions satisfied
6659the minimum qualifications , and reviewed the BAFOs. To the
6668contrary, the evidence supports a finding that Dr. Fuleihan
6677scored and ranked the individual BAFOs in a fair and objective
6688manner.
668948. Notwithstanding the lack of any evidence to show that
6699Dr. Fuliehan exhibited bias or f avoritism during the
6708solicitation process, the facts surrounding the removal of
6716Mr. Eckenrod are essentially the same as those of Dr. Fuleihan.
6727In the case of Mr. Eckenrod, a non - employee, he alerted the
6740Department that he feared that there might be an appearance of
6751impropriety due to the fact that one of the individuals listed
6762in CDM's proposal and his wife held positions on boards of the
6774organization where he worked. Because the boards had the
6783ability to hire or fire him, and determine the program's budget,
6794Mr. Eckenrod was under the impression that this relationship
6803might be perceived as potentially influencing his evaluation of
6812the proposals. Given this impression, it was determined that a
6822reasonable person might come to the same conclusion and
6831the refore Mr. Eckenrod was excused from service.
683949. In the case of Dr. Fuleihan, also a non - employee, he
6852had a professional relationship with a subcontractor (Mosaic),
6860which relationship might reasonably give rise to an appearance
6869of ethical impropriety i n the event the contract was ultimately
6880awarded to CDM. Therefore, even though there is no evidence
6890that Dr. Fuleihan acted improperly in evaluating the proposals,
6899a reasonable person might question his perceived impartiality.
6907Under the precedent establi shed in Mr. Eckenrod's case, DEP 202
6918and DEP 315 apply to Dr. Fuleihan's conduct, and he is obligated
"6930to avoid any conduct . . . which might undermine the public
6942trust . . . or give the appearance of ethical impropriety," and
6954to not have a "contractual re lationship with any business entity
6965. . . doing business with" the Department. Given these
6975standards, at a minimum, disclosure of this conflict was
6984necessary as soon as the BAFOs were filed. By failing to make
6996such a disclosure, the requirements in Sect ion 287.057(20),
7005Florida Statutes, the corresponding Instructions, and DEP 202
7013and 315 were contravened. The Department's contention that DEP
7022202 and DEP 315 do not apply to non - employees has been rejected,
7036especially since the Department applied the same provisions to
7045Mr. Eckenrod.
704750. During the course of discovery in this case (and after
7058the solicitation process was over), Dr. Fuleihan learned that
7067Ardaman does have one small contract (valued at $57,000) with
7078CDM's parent company, Camp, Dresser & McKee (located in St.
7088Louis, Missouri), that was entered into in April 2004. That
7098contract calls for Ardaman to serve as a specialty consultant/
7108subcontractor to Monsanto Company (Monsanto) in providing waste
7116disposal services for Monsanto's elemental phosphor us plant
7124located in Idaho. When Dr. Fuleihan reviewed the BAFOs, he was
7135unaware of this contract. He acknowledged, however, that had he
7145known, he would have disclosed this fact to the Department.
7155Even so, it is fair to infer that a reasonable search of
7167Ardaman's records prior to the commencement of the process would
7177have revealed this conflict, and the Department's Ethics Officer
7186could have then made a determination as to whether Dr. Fuleihan
7197could serve as a team member.
720351. Dr. Fuleihan signed two c onflict of interest forms
7213certifying that he had no conflict. He did not disclose any
7224conflict with Mosaic because he did not believe that the form
7235applied to subcontractors (as opposed to prime contractors), and
7244because his firm's relationship with a pot ential subcontractor
7253would not impede his ability to carry out his responsibilities
7263in evaluating the proposals. (If Mosaic had been a prime
7273contractor, Dr. Fuleihan acknowledged that he would have recused
7282himself from the process.) Other Department witn esses (Godfrey
7291and Coram) conceded, however, that the conflict of interest form
7301applies to subcontractors as well as the prime contractor, and
7311that if a conflict with a subcontractor arose, it should be
7322disclosed to the Department.
732652. In summary, while there is no evidence that Ardaman's
7336professional relationship with both a prime contractor and a
7345subcontractor caused the evaluator to exhibit bias or favoritism
7354towards any particular vendor, the relationships give rise to an
7364appearance of ethical improp riety so that a reasonable person
7374might question the impartiality of Dr. Fuleihan. By not having
7384those relationships disclosed, the Department's governing
7390statutes, policies, and Instructions were contravened.
7396g. Were the CDM and Compass Proposals Resp onsive?
740553. Shaw also contends that there were "many areas" in
7415which the proposals made by CDM and Compass did not materially
7426comply with the Instructions, and that they should be considered
7436non - responsive. Although Shaw's Formal Written Protest
7444identifi ed a wide range of purported deficiencies, only those
7454items which are discussed in Shaw's Proposed Recommended Order
7463are addressed here.
746654. Shaw first contends that even though the vendors were
7476required by the Instructions to demonstrate the reliability of
7485their chosen methods of water treatment, Compass elected to
7494treat half of all water it would treat through an unproven
7505technology that was not demonstrated to be reliable.
751355. Compass proposed a water treatment and consumption
7521method consisting of doub le - liming and air stripping or
7532aeration, followed by reverse osmosis. (Double - liming is a
7542chemical treatment process involving the addition of lime to
7551process water, while reverse osmosis is a physical treatment
7560where process water is forced through a sem i - permeable membrane
7572at high pressure to separate the clean and contaminated water.)
7582This was consistent with the Instructions, which specifically
7590allowed a vendor to use double - lime, air - stripping, and reverse
7603osmosis for water treatment. See Joint Exhi bit 4, Attachment 3
7614at pages 20 - 21. There is no requirement in Attachment 3 that
7627vendors use "proven technology" or demonstrate the reliability
7635and viability of their proposed water treatment methods.
764356. There is no credible evidence in the record that the
7654water treatment method proposed by Compass would not work.
766357. Shaw also alleged that Compass failed to adequately
7672bid utility services, because on line A2 of its BAFO, Compass
7683bid only $36,200.00 for all five years of electric utility
7694services.
76955 8. In its proposal, Compass also included an assumed
7705prevailing rate for power of $100,922.00 per month. Although
7715only $36,200.00 is shown on line A2, Compass spread the rest of
7728the utility costs (approximately $2.3 million) throughout the
7736lines in Secti on B of Attachment 4. While this amount was lower
7749than the other vendors, the Department believed that Compass'
7758overall operation and maintenance expenses were reasonable, and
7766if any mistake had been made by Compass by understating the
7777power cost, it was to Compass' detriment and would not adversely
7788affect the interests of the State.
779459. Shaw also argues that Compass submitted a drawing that
7804included reinforced geotextile but omitted the cost for that
7813item in that portion of its BAFO entitled "clarificati ons."
7823(Geotextiles allow for drainage of fluids and provide a basis
7833for bridging over soft, unstable materials).
783960. Compass indicated in the clarifications section of its
7848BAFO that "reinforced geotextile would be (as needed). The cost
7858for this reinfo rced geotextile is not included." Under the
7868terms of the Instructions, there was no requirement that a
7878vendor estimate quantities that are not listed on the Pricing
7888Summary Sheet, so long as it submits a fixed price bid. Here,
7900the Pricing Summary Sheet i n the Instructions does not have a
7912line for the "as needed" geotextiles, and Compass submitted a
7922fixed price bid. Therefore, the omission of the cost for that
7933item did not render the BAFO non - responsive.
794261. Finally, Shaw has alleged that in its BAFO, Co mpass
7953limited its exposure for the cost of normal repairs and
7963replacements of pumps and piping and was therefore non -
7973responsive. This argument is based on the fact that Compass
7983included $1.1 million in its cost estimate for normal repairs
7993and replacement of pumps and piping. Shaw asserts, however,
8002that because the plant is very old, the contractor will have to
8014take responsibility for failing equipment in order to keep the
8024plant running, and Compass has essentially capped its
8032replacement costs for transfor mers, switch gears, and other
8041necessary equipment.
804362. Shaw did not present evidence that Compass had
8052actually capped its pump maintenance costs or that the amount
8062shown was inadequate. In fact, Shaw's estimated pump
8070maintenance was between $660,000.00 and $900,000.00, or less
8080than the amount proposed by Compass. Even if the amount shown
8091was underestimated, the Department has made it clear that it
8101wanted a lump sum contract and would hold the vendors to the
8113price stated in the BAFOs. (Like the other ve ndors, Compass
8124submitted a fixed price bid.)
812963. Shaw next contends that CDM's proposal was non -
8139responsive in the areas of spray evaporation, the closure
8148construction schedule, water balance, and spray irrigation.
8155These items will be discussed separately below.
816264. Shaw first asserts that CDM overestimated the amount
8171of process water it can treat with spray equipment during the
8182first two years of the contract since the spray equipment CDM
8193proposes to use will not be available until the fifth month of
8205t he first year of the contract.
821265. During the first two years of the contract, CDM
8222proposes to dispose of 175 million gallons of process water
8232through spray evaporation, which involves spraying water into
8240the air to form a mist of small droplets and enha ncing the
8253natural evaporation through various techniques. In doing so,
8261CDM intends to use a new spray system developed by CF
8272Industries, which has achieved a rate of 200 million gallons per
8283year, or twice as much as the amount CDM proposes over a two
8296year period. Therefore, even if the equipment can only be used
8307for twenty months during the first two years, it is reasonable
8318to assume that CDM can evaporate 175 million gallons of process
8329water during the first two years, as projected in its BAFO.
834066. Shaw also points out that the Instructions require
8349each vendor to supply a closure schedule including eight
"8358milestones" that must be completed within certain time frames.
8367The eighth milestone is the closure and placement of grass on
8378all lined reservoir slope s at least one year prior to the end of
8392the contract. See Joint Exhibit 4, Attachment 3, page 4, § IV.
8404While it concedes that CDM included a closure schedule for the
8415site, Shaw asserts that CDM failed to indicate when, if ever, it
8427would place grass - prote cted soil cover on all lined reservoir
8439slopes.
844067. While the Department acknowledged that CDM's BAFO was
8449not as detailed as those of the other two vendors, it points out
8462there is "a lot of flexibility in the BAFO," and that "the
8474covers were not critical f or the closure schedule." Because CDM
8485clearly intends to place the soil cover on the lined areas in
8497conformance with the closure schedule, the omission was not
8506material and does not render the BAFO non - responsive.
851668. Shaw next contends that even though the Instructions
8525require that a vendor prepare an independent water balance, it
8535is not apparent in the BAFO whether CDM prepared one. See Joint
8547Exhibit 4, page 14, § B. (A water balance is a professional
8559estimate of the volume of water on site, coupled with a
8570projection of how it will fluctuate over time considering
8579rainfall and groundwater inputs, surface and spray system
8587evaporation, groundwater seepage, and other factors.)
859369. The Instructions required that CDM independently
8600estimate the water balanc e for the five - year contract period.
8612Nothing in the Instructions, though, requires that the actual
8621calculation or spreadsheets that support the estimated water
8629balance be shown.
863270. With the assistance of its consultants, CDM estimated
8641the total quantity of process water as slightly in excess of one
8653billion gallons, which it rounded off to one billion. This
8663amount was responsive to the Instructions and was similar to the
8674amounts estimated by Shaw and Compass. Accordingly, the
8682estimate by CDM was respons ive to the Instructions.
869171. Finally, Shaw argues that while "CDM also mentioned
8700the use of spray irrigation," CDM "did not estimate any volume
8711of water to be treated with this method." The contention has
8722been considered and found to be without merit.
87307 2. In summary, the BAFOs submitted by CDM and Compass
8741conformed in all material respects to the solicitation. To the
8751extent that there were any minor deviations, they did not give
8762Compass or CDM an advantage or benefit not enjoyed by Shaw, and
8774under Sect ion 1.19 of the Instructions they could be waived by
8786the Department.
8788CONCLUSIONS OF LAW
879173. The Division of Administrative Hearings has
8798jurisdiction over the subject matter and the parties thereto
8807pursuant to Sections 120.569 and 120.57(3), Florida Statut es.
881674. Section 120.57(3)(f), Florida Statutes, provides in
8823relevant part as follows:
8827Unless otherwise provided by statute, the
8833burden of proof shall rest with the party
8841protesting the proposed agency action. In a
8848competitive - procurement protest, . . . t he
8857administrative law judge shall conduct a de
8864novo proceeding to determine whether the
8870agency's proposed action is contrary to the
8877agency's governing statutes, the agency's
8882rules or policies, or the solicitation
8888specifications. The standard of proof for
8894such proceedings shall be whether the
8900proposed agency action was clearly
8905erroneous, contrary to competition,
8909arbitrary, or capricious.
891275. By including the standard of proof language in the
8922last sentence, the statute is confusing and awkwardly worded.
8931I t is clear, however, that Petitioners have the burden of
8942proving by a preponderance of the evidence that the Department's
8952proposed award of the contract to CDM is contrary to the
8963Department's governing statutes, rules, policies, or the
8970Instructions. Presu mably, the standard of proof language
8978requires that Petitioners prove that the Department was clearly
8987erroneous or acted in a manner that was arbitrary, capricious,
8997or contrary to competition when it interpreted, applied, or
9006otherwise considered the govern ing statutes, rules, policies, or
9015Instructions.
901676. Shaw contends that by selecting Dr. Fuleihan, and
9025having him participate in every phase of the process even though
9036he had a conflict of interest which was never disclosed, the
9047Department violated Section s 287.001 and 287.057(20), Florida
9055Statutes, DEP 202 and DEP 315, and the conflict attestation form
9066included in the Instructions. (Section 287.001, Florida
9073Statutes, establishes "fair and open competition" as a basic
9082tenet of the procurement process, whic h is designed to reduce
"9093the appearance and opportunity for favoritism." Assuming that
9101an agency's action can contravene an aspirational statute that
9110merely expresses legislative intent, the argument has been
9118considered.) Shaw also contends that the Depa rtment violated
9127Section 286.011, Florida Statutes (also known as the Sunshine
9136Law), because the evaluation team and the Department's
9144management met privately on several occasions to discuss the
9153proposals. Finally, and presumably for the purpose of
9161establi shing standing, it contends that the BAFOs filed by
9171Compass and CDM were contrary to the Instructions in several
9181material respects and were therefore non - responsive. A
9190contention that at least two of the evaluators were not
9200qualified was not timely raised and need not be considered.
9210Nonetheless, in the findings of fact, this contention has been
9220rejected. In its Formal Written Protest, Compass has raised a
9230single issue, that being Dr. Fuleihan's conflict of interest.
923977. By a preponderance of the evide nce, Petitioners have
9249established that Ardaman (and Dr. Fuleihan) had a professional
9258relationship with the top - ranked vendor (CDM) and one of its
9270subcontractors (Mosaic) during the solicitation process; that
9277Dr. Fuleihan failed to disclose these conflicts on the
9286certification forms or to the Department; and that this omission
9296contravened the requirements of Sections 287.001 and
9303287.057(20), Florida Statutes, DEP 202 and DEP 315, and the
9313attestation form in the Instructions. Therefore, "the
9320[Department's] p roposed action is contrary to the [Department's]
9329governing statutes, the [Department's] rules or policies, or the
9338solicitation specifications." § 120.57(3)(f), Fla. Stat. 3 It is
9347inappropriate, then, to award a contract to CDM using an
9357evaluation team tha t includes Dr. Fuleihan.
936478. For the reasons given in the findings of fact, the
9375evidence does not support a conclusion that the Sunshine Laws
9385were violated. Likewise, the evidence does not support a
9394conclusion that the BAFOs submitted by Compass and CDM were non -
9406responsive. To the extent that the BAFOs deviated from the
9416Instructions, such deviations were immaterial and could be
9424waived by the Department under Section 1.19 of the Instructions.
943479. All other arguments presented by Shaw not specifically
9443add ressed by this Recommended Order have been considered and
9453rejected.
945480. In summary, because the proposed award of the contract
9464to CDM contravenes the Department's governing statutes,
9471policies, and the Instructions, the proposed award cannot be
9480sustained .
9482RECOMMENDATION
9483Based on the foregoing Findings of Fact and Conclusions of
9493Law, it is
9496RECOMMENDED that the Department of Environmental Protection
9503enter a final order determining that its proposed award of the
9514contract to CDM Constructors, Inc., which was based upon a
9524review, grading, and ranking of the vendors by an evaluation
9534team that included Dr. Fuleihan, is contrary to its governing
9544statutes, policies, and specifications.
9548DONE AND ENTERED this 21st day of March, 2005, in
9558Tallahassee, Leon County, F lorida.
9563S
9564DONALD R. ALEXANDER
9567Administrative Law Judge
9570Division of Administrative Hearings
9574The DeSoto Building
95771230 Apalachee Parkway
9580Tallahassee, Florida 32399 - 3060
9585(850) 488 - 9675 SUNCOM 278 - 9675
9593Fax Filing (850) 921 - 6847
9599www.doah.state.fl.us
9600Filed with the Clerk of the
9606Division of Administrative Hearings
9610this 21st day of March, 2005.
9616ENDNOTES
96171/ All future references are to Florida Statutes (2004).
96262/ This contention has been rejected in Finding of Fact 31.
96373/ In reaching this conclusion, the undersigned has considered a
9647contention by the Department and CDM (grounded on the two cases
9658cited below) that unless Petitioners can present "hard facts,"
9667and not mere suspicion or innuendo, that some impropriety
9676occurre d during the procurement process, the Department's action
9685must be sustained. See Gibbons & Company, Inc. v. State of Fla.,
9697Fla. Board of Regents et al. , DOAH Case No. 99 - 0697BID, 1999 WL
97111486501 *70 - 71 (allegation that a member of evaluation team, in
9723coll usion with highest ranked vendor, designed the RFP so that
9734the vendor would receive contract rejected where no evidence to
9744support that allegation); Enpower, Inc. et al. v. Tampa Bay Water
9755et al. , DOAH Case No. 99 - 3398BID, 1999 WL 1486695 *38 (allegation
9768t hat "various individuals manipulated the procurement process to
9777the point of corruption" rejected where no facts to support that
9788charge). In the instant case, however, there is evidence that an
9799evaluator had a professional relationship with the highest ra nked
9809vendor and one of its subcontractors; and that he participated in
9820reviewing, ranking, and grading those two entities. Given these
9829circumstances, an appearance of ethical impropriety arises, and a
9838reasonable person might question the evaluator's impar tiality.
9846Because governing statutes, the Code of Ethics, and the
9855Instructions require that individuals disclose and avoid this
9863type of conflict, there is no need to show any "hard facts" that
9876favoritism and bias actually occurred.
9881COPIES FURNISHED:
9883K athy C. Carter, Agency Clerk
9889Department of Environmental Protection
98933900 Commonwealth Boulevard
9896Mail Station 35
9899Tallahassee, Florida 32399 - 3000
9904Thomas M. Beason, Esquire
9908Department of Environmental Protection
99123900 Commonwealth Boulevard
9915Mail Station 35
9918Tallahassee, Florida 32399 - 3000
9923Jere Earlywine, Esquire
9926Tew Cardenas LLP
9929215 South Monroe Street, Suite 702
9935Tallahassee, Florida 32301 - 1839
9940J. Andrew Bertron, Jr., Esquire
9945Huey, Guilday, Tucker, Schwartz
9949& Williams, P.A.
9952Post Office Box 12500
9956Tallaha ssee, Florida 32317 - 2500
9962Seann M. Frazier, Esquire
9966Greenberg Traurig, P.A.
9969Post Office Drawer 1838
9973Tallahassee, Florida 32302 - 1838
9978Dorn C. McGrath, III, Esquire
9983Greenberg Traurig, P.A.
99861750 Tysons Boulevard, Suite 1200
9991McLean, Virginia 22102 - 4208
9996Gre gory M. Munson, General Counsel
10002Department of Environmental Protection
100063900 Commonwealth Boulevard
10009Mail Station 35
10012Tallahassee, Florida 32399 - 3000
10017NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
10023All parties have the right to submit written exceptions within 10
10034da ys from the date of this Recommended Order. Any exceptions to
10046this Recommended Order should be filed with the agency that will
10057render a final order in this matter.
- Date
- Proceedings
- PDF:
- Date: 04/11/2005
- Proceedings: CDM Constructors Inc.`s Response to Petitioners` Exceptions filed.
- PDF:
- Date: 03/21/2005
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 03/21/2005
- Proceedings: Recommended Order (hearing held February 2, 3, 4, and 7, 2005). CASE CLOSED.
- PDF:
- Date: 02/28/2005
- Proceedings: Notice of Appearance on Behalf of CDM Constructors (filed by J. Earlywine, Esquire).
- PDF:
- Date: 02/28/2005
- Proceedings: Respondent Department of Environmental Protection`s Proposed Recommended Order filed.
- PDF:
- Date: 02/28/2005
- Proceedings: Notice of Filing CDM Constructors INC.`s Proposed Recommended Order filed.
- PDF:
- Date: 02/28/2005
- Proceedings: Petitioner Compass Environmental, Inc.`s Proposed Recommended Order filed.
- Date: 02/16/2005
- Proceedings: Transcripts (8 Volumes) filed.
- Date: 02/02/2005
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 02/02/2005
- Proceedings: Intervenor CDM Constructors` Motion in Limine and to Strike filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Response to CDM Constructor Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Notice of Service of Answers to CDM Constructor Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Response to CDM Constructor Inc.`s First Request for Production filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Response to CDM Constructor Inc.`s First Request for Admissions filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Response to Department of Environmental Protection`s First Request for Production filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Answers to the Department of Environmental Protection`s First Set of Interrogatories filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Shaw Environmental, Inc.`s Notice of Service of Answers to Department of Environmental Protection`s First Set of Interrogatories filed.
- PDF:
- Date: 02/01/2005
- Proceedings: Respondent DEP`s Motion in Limine and to Strike Portions of Petitioners` Petitions for Hearing filed.
- Date: 02/01/2005
- Proceedings: CDM Constructor, Inc.`s Certificate of Serving Answers to Compass Environmental, Inc.`s Second Set of Interrogatories filed.
- PDF:
- Date: 01/28/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s, Certificate of Serving Answers to Intervenor, CDM Constructor`s Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 01/28/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s, Certificate of Serving Answers to Respondent, Department of Environmental Protection`s First Set of Interrogatories filed.
- PDF:
- Date: 01/27/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s, Response to First Request for Production of Documents from Intervenor, CDM Constructors Inc. filed.
- PDF:
- Date: 01/27/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s, Response to Intervenor, CDM Constructors, Inc.`s First Request for Admissions filed.
- PDF:
- Date: 01/27/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s, Response to First Request for Production of Documents from Respondent, Department of Environmental Protection filed.
- PDF:
- Date: 01/27/2005
- Proceedings: Amended Notice of Taking Deposition (amended as to date only) filed.
- PDF:
- Date: 01/27/2005
- Proceedings: Respondent DEP`s Reply to Petitioner, Shaw Environmental, Inc.`s Response to Motion for Protective Order filed.
- PDF:
- Date: 01/25/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s Response to Department of Environmental Protection`s Motion for Protective Order filed.
- PDF:
- Date: 01/25/2005
- Proceedings: Notice of Hearing (motion hearing set for January 27, 2005; at 11:00 a.m.) filed.
- PDF:
- Date: 01/25/2005
- Proceedings: Compass Environmental, Inc.`s Certificate of Serving Second Set of Interrogatories to Intervenor, CDM Constructors, Inc. filed.
- PDF:
- Date: 01/25/2005
- Proceedings: Respondent Department of Environmental Protection`s Motion for Protective Order filed.
- PDF:
- Date: 01/24/2005
- Proceedings: Intervenor CDM Constructor Inc.`s First Request for Admissions to Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/24/2005
- Proceedings: Intervenor CDM Constructor Inc.`s First Request for Admissions to Compass Environmental, Inc. filed.
- PDF:
- Date: 01/24/2005
- Proceedings: Amended Cross Notice of Taking Depositions Duces Tecum of Invan Nance and Bruce Scott filed.
- PDF:
- Date: 01/24/2005
- Proceedings: Intervenor CDM Constructor`s Inc.`s Certificate of Serving First Set of Interrogatories to Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/24/2005
- Proceedings: Intervenor CDM Constructor`s Inc.`s Certificate of Serving First Set of Interrogatories to Compass Environmental, Inc. filed.
- PDF:
- Date: 01/21/2005
- Proceedings: Notice and Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Shaw Environmental, Inc. filed.
- Date: 01/21/2005
- Proceedings: Respondent, Department of Environmental Protection`s First Request for Production of Documents to Petitioner, Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/21/2005
- Proceedings: Respondent, Department of Environmental Protection`s First Request for Production of Documents to Petitioner, Compass Environmental, Inc. filed.
- PDF:
- Date: 01/21/2005
- Proceedings: Notice and Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Compass Environmental, Inc. filed.
- PDF:
- Date: 01/20/2005
- Proceedings: CDM Constructor Inc.`s Certificate of Serving Answers to Compass Environmental, Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 01/20/2005
- Proceedings: CDM Constructor Inc.`s Certificate of Serving Answers to Shaw Environmental, Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 01/20/2005
- Proceedings: Cross Notice of Taking Deposition Duces Tecum of Invan Nance and Bruce Scott filed.
- PDF:
- Date: 01/20/2005
- Proceedings: Amended Cross Notice of Taking Deposition Duces Tecum of Nadim F. Fuleihan, P.E. filed.
- PDF:
- Date: 01/20/2005
- Proceedings: Respondent, Department of Environmental Protection`s Response to Petitioner, Compass Environmentl, Inc.`s, Second Request for Production of Documents filed.
- PDF:
- Date: 01/20/2005
- Proceedings: Department`s Notice of Filing Answers to Compass Environmental, Inc.`s, Second Set of Interrogatories filed.
- PDF:
- Date: 01/20/2005
- Proceedings: Letter to Judge Alexander from A. Levine requesting an extension of the hearing length by one day filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Ardaman & Associates, Inc.`s Motion for Protective Order (Deposition of Corporate Representative by Compass) filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Ardaman & Associates, Inc.`s Motion for Protective Order (Deposition of Nadim F. Fuleihan, P.E. by Compass) filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Ardaman & Associates, Inc.`s Motion for Protective Order (Deposition of Corporate Representative by Shaw) filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Ardaman & Associates, Inc.`s Motion for Protective Order (Deposition of Nadim F. Fuleihan, P.E. by Shaw) filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Ardaman & Associates, Inc.`s Motion for Protective Order (Deposition of Nadim F. Fuleihan, P.E. by CDM) filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Department`s Notice of Filing Answers to Compass Environmental, Inc.`s, First Set of Interrogatories filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Department`s Notice of Filing Answers to Shaw Environmental, Inc.`s, First Set of Interrogatories filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Respondent, Department of Environmental Protection`s Response to Petitioner, Shaw Environmental, Inc.`s, First Request for Admissions filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Respondent, Department of Environmental Protection`s Response to Petitioner, Compass Environmental, Inc.`s, First Request for Production of Documents of Documents filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Respondent, Department of Environmental Protection`s Response to Petitioner, Shaw Environmental, Inc.`s, First Request for Production of Documents filed.
- PDF:
- Date: 01/19/2005
- Proceedings: Cross Notice of Taking Deposition Duces Tecum of Nadim F. Fuleihan, P.E. (filed by Intervenor).
- Date: 01/14/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s Notice of Service of First Set of Interrogatories to Petitioner, Compass Environmental, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s Response to Petititioner, Shaw Environmental, Inc.`s First Request for Admissions filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Compass Environmetnal, Inc.`s Certificate of Serving Answers to Petitioner, Shaw Environmental, Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Compass Environmental, Inc.`s First Request for Production to Intervenor, CDM Constructors, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Compass Environmental, Inc.`s First Request for Admissions from CDM Constructors, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Compass Environmental, Inc.`s Certificate of Serving First Set of Interrogatories to Intervenor, CDM Constructors, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Notice of Taking Deposition Duces Tecum of Nadim F. Fuleihan, P.E. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Notice of Taking Deposition Duces Tecum of Corporate Representative of Ardaman & Associates, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Amended Notice of Taking Deposition Duces Tecum of Corporate Representative of Ardaman & Associates, Inc. (amended as to location only) filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Amended Notice of Taking Deposition Duces Tecum of Nadim F. Fuleihan, P.E. (amended as to location only) filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Notice of Taking Deposition of Corporate Representative of the Florida Department of Environmental Protection filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner`s Certificate of Serving Second Set of Interrogatories to Respondent, State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Compass Environmental, Inc.`s Second Request for Production to State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Cross-Notice of Taking Deposition Duces Tecum of Nadim F. Fuleihan, P.E. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Cross-Notice of Taking Deposition Duces Tecum of Corporate Representative of Ardaman & Associates, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Cross-Notice of Taking Deposition of Corporate Representative of the Florida Department of Environmental Protection filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Request for Production of Documents to CDM Constructors, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s First Set of Interrogatories to CDM Constructors, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s Notice of Service of First Set of Interrogatories to CDM Constructors, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Shaw Environmental, Inc.`s Answers to Compass Environmental, Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Shaw Environmental, Inc.`s Notice of Service of Answers to Compass Environmental, Inc`s First Set of Interrogatories filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Shaw Environmental, Inc.`s Response to Compass Environmental, Inc.`s First Request for Production filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Shaw Environmental, Inc.`s Response to First Request for Admissions from Compass Environmental, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner`s Compass Environmental`s Response to First Request for Production of Documents from Petitioner, Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Compass Environmental, Inc.`s Response to Petititioner, Shaw Environmental, Inc.`s First Request for Admissions filed.
- PDF:
- Date: 01/14/2005
- Proceedings: Petitioner, Compass Environmetnal, Inc.`s Certificate of Serving Answers to Petitioner, Shaw Environmental, Inc.`s First Set of Interrogatories filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Request for Admissions to Respondent, State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Request for Production of Documents to Respondent, State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, Notice of Service of First Set of Interrogatories to Respondent, State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Set of Interrogatories to Respondent, State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Request for Admissions to Petitioner, Compass Environmental, Inc. filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Request for Production of Documents to Petitioner, Compass Environmental, Inc. filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s, First Set of Interrogatories to Petitioner, Compass Environmental, Inc. filed.
- PDF:
- Date: 01/07/2005
- Proceedings: Petitioner, Shaw Environmental, Inc.`s Notice of Service of First Set of Interrogatories to Petitioner, Compass Environmental, Inc. filed.
- PDF:
- Date: 01/06/2005
- Proceedings: Notice of Hearing (hearing set for February 2 (and 3), 2005; 9:00 a.m.; Tallahassee, FL).
- PDF:
- Date: 01/06/2005
- Proceedings: Order. (DOAH Cases Nos. 05-0007BID and 05-0008BID are consolidated).
- PDF:
- Date: 01/04/2005
- Proceedings: Compass Environmental Inc.`s First Request for Production to Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/04/2005
- Proceedings: Petitioner`s Certificate of Serving First Set of Interrogatories to Respondent, Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/04/2005
- Proceedings: Compass Environmental, Inc.`s First Request for Admissions from Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/04/2005
- Proceedings: Petitioner`s Certificate of Serving First Set of Interrogatories to Respondent, Shaw Environmental, Inc. filed.
- PDF:
- Date: 01/04/2005
- Proceedings: Compass Environmental, Inc.`s First Request for Production to State of Florida, Department of Environmental Protection filed.
- PDF:
- Date: 01/04/2005
- Proceedings: Petitioner`s Certificate of Serving First Set of Interrogatories to Respondent, State of Florida, Department of Environmental Protection filed.
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 01/03/2005
- Date Assignment:
- 01/06/2005
- Last Docket Entry:
- 04/21/2005
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
J. Andrew Bertron, Esquire
Address of Record -
Jere L. Earlywine, Esquire
Address of Record -
Seann M. Frazier, Esquire
Address of Record -
Dorn C Mcgrath, Esquire
Address of Record -
Marshall G. Wiseheart, Esquire
Address of Record -
Donald F Wright, Esquire
Address of Record -
Jere Earlywine, Esquire
Address of Record