05-002478TL
In Re: Florida Power And Light St. Johns-Pellicer-Pringle 230 Kv Transmission Line Project Transmission Line Siting Application No. Ta05-13 vs.
*
Status: Closed
Recommended Order on Monday, March 6, 2006.
Recommended Order on Monday, March 6, 2006.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: FLORIDA POWER & LIGHT )
15ST. JOHNS - PELLICER - PRINGLE, )
22230 KV PROJECT, TRANSMISSION ) Case No. 05 - 2478TL
32LINE SITING APPLICATION NO. )
37TAO5 - 13. )
41___ ____________ ________________ )
45RECOMMENDED ORDER
47Pursuant to notice, a formal hearing was held in this case
58on January 10 , 2006 , in St. Augustine, Florida, before the
68Division of Administrative Hearings, by its assigned
75Administrative Law Judge, Donald R. Alexander .
82APPEARANCES
83For Florida Power Carolyn S. Raepple , Esquire
90& Light Company: Hopping Green & Sams, P.A.
98P ost Office Box 6526
103Tallahassee, Florida 32314 - 6526
108For Department Scott A. Goorland , Es quire
115of Environmental D epartment of Environmental Protection
122Protection: Mail Station 35
1263000 Commonwealth B oulevard
130Tallahassee, Florida 32399 - 3000
135For St. Johns Michael D. Hunt, Esq uire
143County: Deputy County Attorney
1474020 Lewis Speedway , Suite 1120
152St. Augustine, F lorida 32084 - 8637
159For St. Johns Veronika Th i e bach , Esq uire
169River Water St. Johns River Water Management District
177Management 4049 Re id Street
182District: Palatka, F lorida 32177 - 2529
189STATEMENT OF THE ISSUES
193The issues for determination are whether and the extent to
203which the properly proposed corridor (the FPL Corridor) for the
213St. Johns - Pellicer - Pringle 230 - kV transmissio n line (the SJPP
227Line) complies with the criteria in Section 403.529(4)(a) - (e),
237Florida Statutes (2005) 1 , and whether Florida Power & Light's
247(FPL 's ) application for corridor certification should be
256approved in whole, with modifications or conditions, or d enied.
266PRELIMINARY STATEMENT
268Pursuant to Section 403.537, F lorida S tatutes , FPL
277submitted a Petition to Determine Need for the SJPP Line project
288to the Public Service Commission (PSC) on March 25, 2005 . The
300PSC issued Order No. PSC - 0 5 - 0527 - FOF - EI, dated May 13, 2005 ,
318determining the need for the SJPP Line.
325On July 5, 2005, FPL filed its Application for Corridor
335Certification for the SJPP Line (Application) with the
343Department of Environmental Protection (Department) an d paid the
352appropriate application fee . The Application wa s filed under
362the Transmission L ine Siting Act (TLSA), codified in Section s
373403.52 through 403.5365, Florida Stat utes , for a new 230 - kV
385overhead transmission line and related facilities connecting the
393existing St. Johns substation near St. Augustine in St. Johns
403County to the proposed Pringle s ubstation in the C ity of Palm
416Coast in Flagler County (the Project).
422The various reviewing agencies have submitted reports on
430the Project and have proposed Co nditions of Certification. On
440D ecember 9, 2005 , the D epartment issued its Summary and
451Compilation of Agency Reports Including Proposed Conditions of
459Certification for the Project, incorporating the reports of the
468reviewing agencies and proposing a compiled set of Conditions of
478Certifica tion. During the certification hearing, a R evised
487Summary and Compilation of Agency Reports, including an updated
496version of the proposed Conditions of Certification , dated
504December 29, 2005, was a dmitted into the record as Department
515Exhibit 1 .
518The ce rtification hearing was held on January 10, 2006.
528All notices required by law were timely published in accordance
538with Section 403.527, F lorida Statutes. The final hearing was
548conducted for the purpose of receiving oral, written, and
557documentary evidence concerning whether the Project should be
565approved in whole, or with such modifications and conditions as
575the Siting Board deems appropriate, or denied under the TLSA.
585FPL presented one witness and offered composite exh ibits
594numbered FPL 1 , which includes the prefiled written testimony of
604four witnesses , Daniel Hronec, Analee Mayes , Anthony N. Arcuri,
613and Philip Simpson, and exhibits numbered as DH - 1, DH - 2, DH - 3,
629AM - 1, AM - 2, PS - 1, and TA - 1 , and FPL 2 , which contains the
648various notices of publication relat ed to this matter. A lso, on
660January 20, 2006, FPL submitted late - filed exhibit FPL 3, which
672includes the public notices from the D epartment 's website .
683Finally , official recognition of these notices has been taken.
692At the hearing, FPL presented the te stimony of Daniel
702Hronec, P.E., an expert in electrical transmission line
710engineering, who t estif ied and submitted pre - filed written
721testimony and exhibits . FPL also submitted pre - filed testimony
732and exhibits from: Analee Mayes, AICP, an expert in land us e
744planning; Anthony N. Arcuri, an expert in botany, vegetative
753mapping , and listed plant species; and Phil ip Simpson, an expert
764in wildlife ecology and transmission line impacts to t errestrial
774ecological resources. All pre - filed written testimony and
783exhi bits submitted by FPL have been received into evidence
793without objection.
795In addition to presenting the Revised Summary and
803Compilation of Agency Reports, the Department presented the
811testimony of Ann Seiler, an Environmental Specialist III who
820coordinate d the processing of the Application , and prepared the
830Revised Summary and Compilation of Agency Reports .
838A publi c hearing was held at 11 :00 a .m. on January 10 ,
8522006 , for the purpose of allowing members of the public an
863opportunity to present evidence and testimony. No member of the
873public appeared to testify.
877The Transcript of the final hearing was filed with the
887Division of Ad ministrative Hearings on January 18, 2006 . On
898February 16, 2006, FPL filed a Proposed Recommended Order which
908has been substant ially used in the preparation of this
918Recommended Order.
920FINDINGS OF FACT
923Based upon all of the evidence the following findings of
933fact are determined:
936I. Parties
9381. The TLSA establishes FPL and the Department as parties
948to this proceeding, and the follo wing became parties upon their
959timely filing of a notice of intent to be a party, which each
972has done: F lorida D epartment of Transportation (D OT ) ,
983D epartment of Community Affairs (D CA ) , St. Johns River Water
995Management District ( SJR WMD ) , St. Johns County, and the C ity of
1009Palm Coast . See § 403.527(4), Fla. Stat.
1017II. The Application
1020A . Project Description
10242. Generally, a n electrical transmission line ' s purpose is
1035to transport large amounts of electricity from a generating
1044facility to one or more substati ons. At the substation, the
1055electricity can be either increased or reduced in voltage
1064through transformers and other electrical equipment for further
1072safe and practical transportation , or distribution directly to
1080customers.
10813. FPL is seeking certificat ion of a corridor between the
1092existing St. Johns substation and the proposed Pringle
1100substation within which it will ultimately construct the SJPP
1109Line on a narrow right - of - way (ROW). Once all property
1122interests in the ROW are acquired, the boundaries of the
1132corridor will shrink to the typical width of the 15 to 60 - foot
1146ROW.
11474. The service area for the proposed SJPP Line (the
1157Project Service Area) is St. Johns County and Flagler County .
1168T he SJPP Line will follow Interstate 95 (I - 95) in a north - south
1184di rection and will connect to the proposed intermediate
1193Deerwood, Vermont, Anastasia , and Pellicer substations.
11995. The Project Service Area includes an area of increasing
1209load and customer base in the area south of St. Johns and north
1222of Pringle substatio ns and to the west of the existing Bunnell -
1235St. Johns 115 - kV transmission line.
12426. The three objectives of the SJPP Line project are: (1)
1253to address the need, as confirmed by the PSC , to serve FPL ' s
1267increasing load and customer base in the area south of St. Johns
1279and north of Pringle substations in a reliable manner; ( 2) to
1291provide additional transmission reinforcement to the existing
1298115 - kV transmission line between the Bunnell and St. Johns
1309substations; and (3) to efficiently and effectively integrate
1317a nd serve new distribution substations that are needed to serve
1328projected load growth within Flagler and St. Johns Counties .
1338The primary path for the SJPP transmission line bringing
1347electricity into the Project Service Area will be aligned within
1357or adjace nt to existing linear features, such as existing road,
1368transmission line and railroad ROWs. The only exception is a
1378distance of less than half a mile in length between the proposed
1390Vermont substation in the St. Augustine Industrial Park and
1399I - 95, where the corridor largely follows property lines.
14097. The primary path for the SJPP transmission line
1418bringing electricity into the Project Service Area will be
1427aligned within or adjacent to existing linear features, such as
1437existing road, transmission line, and railroad ROWs. The only
1446exception is a distance of less than half a mile in length
1458between the proposed Vermont substation in the St. Augustine
1467Industrial Park and I - 95, where the corridor largely follows the
1479property line.
1481B. Need for the SJPP Line
14878. The P SC determined a new 230 - kV transmission line
1499between the St. Johns substation and the proposed Pringle
1508substation is needed, taking into account the need for electric
1518system reliability and integrity in northeast Florida and the
1527need to provide a bundant, low - cost electrical energy to assure
1539the economic well - being of the citizens of the State,
1550particularly those in northeast Florida.
15559. The PSC noted that FPL ' s planning studies indicate this
1567additional transmission capacity will be needed by Dec ember 2008
1577to alleviate potential overloads and low voltage conditions that
1586could result from a single contingency event. Without the
1595addition of this transmission capability by 2008, the PSC found
1605that up to 8,300 electric customers could experience serv ic e
1617interruptions.
161810. The PSC recognized that the Siting Board will make the
1629final corridor selection upon consideration of the factors and
1638criteria specified in Section 403.529, Fl orida Stat utes .
1648C. Transmission Line Design
165211. The typical design for the SJPP Line will be a single -
1665circuit unguyed concrete pole structure, 90 feet above grade in
1675height, with the conductors framed in a vertical configuration.
1684Each of the three conductors is anticipated to be a 1,431
1696thousand circular mils , aluminum cond uctor, steel reinforced
1704alumoweld core. There will also be a smaller overhead ground
1714wire to provide shielding and lightning protection for the
1723conductors and provide communications capability . The maximum
1731current rating for the line will be 1,905 ampere s. In some
1744locations, electric distribution lines and communication cables
1751may also be attached to the structures bene ath the conductors .
176312. In some locations, such as along FPL ' s St. Johns - Tocoi
1777transmission line right - of - way and along Tocoi Road, a d ouble -
1792circuit configuration, with or without distribution underbuild,
1799may be used.
180213. The span length between structures will ty pically vary
1812between 250 and 75 0 feet , depending on site - specific conditions,
1824ROW widths , and other design considerations. Both pole height
1833and span length may vary to accommodate such things as locating
1844poles to coincide with property boundaries or existing
1852collocated utility facility poles, to avoid or minimize wetland
1861impacts, to cross other utility lines, and to facilitate wide
1871crossings of water bodies and roadways.
187714. Where the transmission line turns large angles or
1886crosses other major linear facilities , the structures may be
1895guyed or anchored to support the differential tension.
190315. Access roads and structure pads will be constructed
1912only where necessary to provide access for construction,
1920maintenance , and emergency restoration. Where constructed, the
1927typical road top width will be about 14 feet , with a 2 - to - 1 side
1944slope, and a minimum elevation of 6 inches over me an or seasonal
1957high water. Structur e pads will have variable sizes, depending
1967on site specific requirements, but will be of sufficient size to
1978provide access to structure locations for the large construction
1987equipment. Access roads and structur e pads wil l not be paved.
1999Culverts will be installed beneath access roads and structure
2008pads with spacing, diameter , and length to maintain
2016preconstruction flo ws.
201916. The design of the SJPP Line complies with good
2029e ngineering practices. The SJPP Line will be des igned in
2040compliance with all applicable design codes, including the
2048National Electrical Safety Code (NESC) , the D epartment's
2056regulations on electric and magnetic fields, the DOT Utility
2065Accommodation Manual, the St. Johns County and City of Palm
2075Coast nois e ordinances, and standards of the Amer ican Society of
2087Civil Engineers (ASCE) , the Institute of Electrical and
2095Electronics Engineers , Amer ican Society of Testing Materials,
2103American National Standards Institute, and American Concrete
2110Institute, as well as FPL ' s own design standards.
212017. The Project assures the citizens of Florida that
2129operation safeguards are technically sufficient for their
2136welfare and protection.
2139D. Transmission Line Construction
214318. Surveying the ROW to facilitate acquisition of th e
2153necessary property interests is a first step towards
2161construction. After property rights for the ROW have been
2170acquired, the initial phase of construction is to clear the ROW.
2181Since nearly the entire length of the FPL Corridor is collocated
2192with existi ng roads and utility facilities, the need for
2202acquisition of private property and the need for clearing ha ve
2213been minimized. Clearing will consist mainly of tree trimming
2222and the removal of trees that exceed or are capable of exceeding
223414 feet in height. In wetlands, trees capable of exceeding 14
2245feet in height that could come in conflict with the line will be
2258removed by hand - clearing or use of very low ground pressure
2270equipment. Low - growing herbaceous vegetation will not be
2279cleared from wetlands.
228219. After the ROW is cleared, any necessary access roads
2292and structure pads will be constructed. Typically, access road s
2302and pads are only required in wet and low areas. This enables
2314all subsequent construction activity in those wet areas to
2323remain on the ne wly constructed access road and pad.
233320. The next phases of construction involve the physical
2342transmission line construction. Initially, materials are
2348brought to the jobsite. Next, holes are augered at each pole
2359location and the poles are then erected using cranes or other
2370heavy equipment. The hole is then backfilled with suitable
2379fill. Typically, the pole is embedded into the ground
2388approximately 16 to 20 feet .
239421. After the poles are set, the poles are framed , that
2405is, the insulators and hardware a re installed on the pole. Then
2417through a wire pulling operation the conductors and overhead
2426groun d wires are installed. The conductors are then properly
2436sagged and tensioned to provide the proper vertical clearances.
2445Next, the conductors are " lipped in " to the insulator
2454assemblies. The final stage of constru ction is ROW clean - up.
246622. During all stages of construction, FPL will maintain
2475traffic on any adjacent county, state , or federal roadways in
2485compliance with applicable DOT and St. Johns County regu lations .
249623. Throughout construction, sedimentation management
2501techniques, such as the use of silt screens and hay bales, will
2513be employed as necessary to minimize potential impacts from
2522e rosion and sedimentation.
252624. While each phase of construction w ill typically take
2536only 1 to 7 days in an area, the entire SJPP Line construction
2549process will last approximately 13 months.
2555E . Methodology for Choosing FPL Corridor
256225. On project initiation, FPL management instructed its
2570multi - disciplinary corridor se lection team to identify, if it
2581could, a corridor for the SJPP Line that connects the St. Johns
2593and Pringle substations and allows connections to the proposed
2602intermediate substations.
2604a. Corridor Selection and Public Involvement
261026. FPL established a m ulti - disciplinary team to identify
2621and evaluate routing alternatives within the Project Study Area.
2630This multi - disciplinary team was comprised of a transmission
2640line engineer, a land use planner, and an ecologist.
264927. FPL ' s multi - disciplinary team gathere d data on siting
2662opportunities and constraints within the study area and
2670identified 45 line segments which could be assembled into
2679approximately 630 alternate routes for the SJPP Line.
268728. FPL also engaged in an extensive public participation
2696program to gather input for its route evaluation study. This
2706public participation program included an open house, mass
2714mailings, a community surve y, a toll - free telephone number and
2726an e - mail address, a website, and meetings with regulatory
2737agencies, community assoc iations, homeowner groups, and
2744individual homeowners and property owners.
274929. The public participation program provided substantive
2756input to the route evaluation study in terms of study area
2767boundary, siting opportunities and constraints in the area,
2775ide ntification of route segments to be evaluated, and weights to
2786be assigned to the route evaluat ion criteria.
279430. FPL ' s multi - d isciplinary team evaluated the 630 routes
2807quantitatively, using 11 weighted factors , and then evaluated in
2816more detail, using bot h quantitative and qualitative criteria, a
2826few distinct routes identified from among the highest - ranking
2836routes .
283831. Through this process, FPL ' s multi - disciplinary team
2849was able to identif y a route o f the FPL Corridor that , on
2863balance , is the most approp riate considering environmental, land
2872use, engineering, and cost considerations.
287732. Once the preferred alignment was identified, the
2885multi - disciplinary team delineated the boundaries or width of
2895the FPL Corridor to provide flexibility for l ocating the
2905e ventual ROW within that corridor.
2911b . Agencies ' Review of FPL ' s Application and Resulting
2923Determinations
292433. S tate, regional , and local agenc ies with regulatory
2934authority over the project reviewed FPL ' s Application and
2944submitted to the Department a repo rt as to the impact of the
2957proposed SJPP Line on matters within the agency ' s jurisdiction,
2968as required by Section 403.526(2), Fl orida Statutes. The
2977Department then compiled these reports and made a recommendation
2986that the SJPP Line be granted approval sub ject to appropriate
2997conditions.
2998III. Stipulations Entered Into by Parties
300434. All agency parties filed stipulations with FPL in
3013which these parties and FPL agreed to the Conditions of
3023Certification for the SJPP line and the entry into the record of
3035the pre - file d written testimony and exhibits of FPL ' s witnesses .
3050IV. D etailed Description of the FPL Corridor
305835. Almost the entire length of the FPL Corridor is
3068collocated with existing linear features, such as roa ds and
3078transmission lines. This collocatio n will minimize impacts of
3087the new SJPP Line. The width of the FPL Corridor varies along
3099the route to provide flexibility within the corridor to minimize
3109or avoid impacts to such areas as existing developments and
3119large wetland areas.
3122A. F rom the St. Johns Substation to the Deerwood
3132Substation
313336. The SJPP line will exit the existing St. Johns
3143substation at SR 207 near Lightsey Boulevard and utilize the
3153existing 110 - f oo t - wide St. Johns - Tocoi 230 - kV ROW. The FPL
3171Corridor will be collocated within this exis ting ROW north and
3182west until the intersection with I - 95. Along the existing ROW
3194and in the vicinity of the St. Johns substation, the land use is
3207residential or vacant.
321037. At I - 95, the preferred corridor will follow the
3221eastern ROW line of the highway south to the intersection with
3232Tocoi Road. The corridor in this stretch is 500 f ee t wide.
3245Within the corridor in this stretch, the land use is vacant.
3256There is some residential development outside the corridor to
3265the east.
326738. At the I - 95/Tocoi Road i ntersection, the FPL Corridor
3279is expanded in all four quadrants following property lines to
3289allow FPL flexibility in traversing the short distance to
3298Deerwood substation and crossing I - 95 to proceed south f rom
3310Deerwood.
331139. The FPL Corridor follows Tocoi Road to enter and exit
3322the proposed Deerwood substation, encompassing 100 f ee t or less
3333in width on both the north and south sides of the road. The
3346line will be built either on the south or north side of the
3359road. A FPL distribution line currently exists on the south
3369side of Tocoi Road .
3374B. F rom the Deerwood Substation to the Vermont Substation
338440. The FPL Corridor will leave the Tocoi Road alignment
3394at the I - 95 intersection. The FPL Corridor then follows the
3406western ROW edge of I - 95 south to the FEC Railr oad, where the
3421corridor turns to the southwest for a short distance. In this
3432section, the corrid or is 500 f ee t wide.
344241. At the north end of the St. Augustine Industrial Park,
3453the corridor follows property lines to the access road (Deerpark
3463Boulevard) i nto the industrial park. The corridor is 200 f ee t
3476wide in this section. From the north end of the access road,
3488the FPL Corridor follows the east edge of the road south to the
3501Vermont substation site , is 100 f ee t wide in this section , and
3514includes an exis ting FPL distribu tion line.
3522C. From the Vermo nt Substation to the Anastasia
3531Substation
353242. The FPL Corridor exits the Vermont substation heading
3541northeast toward I - 95. In this area, the corridor will be of
3554variable width and will include both sides of S tate Road 207 (SR
3567207) . An existing 115 - kV FPL transmission line already occupies
3579the north side of the SR 207, and a distribution line is located
3592on the south side. An existing FPL distribution line traverse s
3603north - south in this area and is also include d in the corridor.
3617In the area between the Vermont substation and I - 95 , the
3629corridor is north and east of existing residential subdivisions.
363843. The corridor between the Vermont substation and I - 95
3649is widened to allow flexibility in accommodating a num ber of
3660land use and engineering considerations. These considerations
3667include the crossing of SR 207, the existing transmission line
3677and distribution lines, existing residential development south
3684of SR 207, existing commercial development north of SR 207, and
3695a large borrow pond west of I - 95.
370444. The corridor will reach I - 95 south of SR 207, at which
3718point it will then follow I - 95 ' s western boundary southward.
3731The corridor is 500 f ee t wide in this area where it parallels
3745I - 95 south to SR 206.
375245. The predominant land use in the area between the
3762Vermont and Anastasia substations is silviculture.
3768D. From the Anastasia Substation to the Pellicer
3776Substation
377746. At the intersection of SR 206 and I - 95, the corridor
3790is again widened variably to include the p roperties on the
3801northwest and southwest quadrants of the interchange to provide
3810flexibility in finalizing the Anastasia substation plans and
3818providing ingress and egress to that substation.
382547. The FPL Corridor will exit the Anastasia substation
3834and fo llow the western boundary of I - 95 southward. The corridor
3847is 500 f ee t wide in this stretch with the exception of the
3861location of a rest area on the west side of I - 95 , approximately
38752.5 miles south of Anastasia substation . The corridor is of
3886variable widt h around the rest area, but generally 1,000 f ee t
3900wide to allow flexibility in traversing either the front or rear
3911of the rest area. In this area, the predominant land use is
3923silviculture.
392448. Where I - 95 intersects the FEC Railroad north of C ounty
3937Road 2 04 (CR 204) , the FPL Corridor turns and follows the
3949railroad southward. The corridor is located along the east side
3959of the railroad and is 500 f ee t wide. North of CR 204, the
3974corridor is expanded along the road to allow ingress to the
3985Pellicer substation site located south of CR 204 and east of the
3997railroad. Land uses in this area are primarily silviculture.
4006E. From the Pellicer Substation to the Pringle Substation
401549. The FPL Corridor includes the entire Pellicer site,
4024which is already owned by FPL, alo ng the east side of the FEC
4038Railroad south to Pellicer Creek. The corridor in this area
4048crosses lands owned or proposed to be purchased by the SJRWMD
4059for conservation purposes for approximately one mile.
406650. From Pellicer Creek south to the Pringle subs tation,
4076the corridor will follow the east side of the railroad bed and
4088will be variable in width, generally 150 to 300 f ee t wide.
410151. At the Pringle substation site, which is already owned
4111by FPL, the corridor includes the entire substation site. The
4121FP L Corridor for the stretch sout h of Pellicer Creek falls in a
4135currently undeveloped portion of the Palm Coast Park D evelopment
4145of Regional Impact (D RI ) within the City of Palm Coast ' s
4159jurisdict ion. The development order for the Palm Coast Park DRI
4170provide s for an easement for the SJPP transmission line within
4181the FPL C orridor .
4186V. C ompliance With Section 403.529(4) C riteria
4194A . Ensure Electric Power System Reliability and Integrity
420352. The PSC found that there are regional transmission
4212system limitations in St. Johns and Flagler Counties. By 2008,
4222the existing 115kV transmission network between the Bunnell
4230substation in Flagler County and the St. Johns s ubstation in
4241St. Johns County will not have sufficient capacity to provide
4251reliable electric service to the existing and proposed
4259substations in the area. The SJPP Line would be built to
4270alleviate potential overloads and low voltage conditions from a
4279single contingency event, which occurs when a single element
4288such as a generator, transmission circuit or transformer is
4297eliminated from the system. If the SJPP Line is not built,
4308service interruptions affecting up to 8,300 customers could
4317occur.
431853. In addition, the PSC found that the FPL North Region
4329(extending from Indian River County to Nassau County) has grown
4339by a compound annual average growth rate of 3.7 percent over the
4351past five years. The SJPP Line is also needed to serve the
4363increasing load and customer base in the area.
437154. O peration of the SJPP Line would be consistent with
4382the North Amer ican Electric Reliability Council and Florida
4391Reliability Coordinating Council transmission system standards.
439755. FPL has a responsibility to provide safe and reliable
4407service to its customers. S ee § 366.03, Fla. Stat. The
4418provision of reliable electri c service is impor tant to FPL and
4430its customers. In the past, FPL has demonstrated the ability to
4441plan a reliable electric system consistent with the NESC and
4451ASCE standards.
4453B. Meet the Electrical Energy Needs of the State in an
4464Orderly and Timely Fa shion
446956. The PSC recognized that FPL ' s planning studies
4479indicate that the SJPP Line is needed by December 200 8 to
4491alleviate potential overloads and low voltage conditions from a
4500single cont ingency event.
450457. Location of the SJPP Line on the FPL Corrid or would
4516meet the electrical energy needs of the state in a timely
4527fashion .
4529C. Comply with the Nonprocedural Requirements of Agencies
453758. Construction, operation , and maintenance of the SJPP
4545Line in the FPL Corridor will comply with applicable non -
4556proce dural requirements of agencies.
456159. The D epartment has concluded that the project as
4571proposed will comply with all applicable D epartment statutes,
4580rules, policies, and procedures.
4584D. Be Consistent with Applicable Local Government
4591Comprehensive Plans
459360. The D epartment has concluded that the SJPP Line as
4604proposed would produce a minimal adverse impact on the
4613environment and public health, safety , and welfare without
4621unduly conflicting with local statute s and local comprehensive
4630plans.
463161. After certific ation of this project, FPL will acquire
4641the necessary property interest s in a ROW within the certified
4652corridor for placement of the SJPP Line. Construction of
4661transmission lines on such established ROWs is excepted from the
4671definition of " development " in Section 163.3164(5), Fl orida
4679Statutes. Accordingly, the provisions of the local
4686c omprehensive p lans related to " development " that have been
4696adopted by the local governments crossed by the SJPP Line are
4707not applicable to this project .
471362. To the extent the c omprehensive p lans of the local
4725governments crossed by the SJPP Line include provisions
4733applicable to non - development activities , the proposed
4741transmission line in the FPL Corridor wo uld be consistent with
4752them.
475363. The City of Palm Coast Comprehens ive Plan is
4763essentially silent on transmission lines as a land use, which is
4774consistent with such lines being excepted from the definition of
" 4784development " regulated by the Plan.
478964. Policy A.1.8.3 of the St. Johns County Comprehensive
4798Plan provides that " future utility facilities shall be located
4807to promote the efficient provision of services , minimize the
4816cost of construction and maintenance, and minimize the impact on
4826the natural environment. " Because of the thoroughness of the
4835corridor selection proc ess and criteria, and the appropriateness
4844of the corridor from a land use perspective, the proposed SJPP
4855L ine is consistent with that policy.
486265. No variances or exemptions from applicable state or
4871local standards or ordinances are needed for the project .
4881E. Implementation of Legislative Intent in Section 40 3.521
4890a . The Need for the SJPP Line as a Means of Providing
4903Abundant Low - Cost Electrical Energy
490966. The PSC determined that the SJPP Line is needed taking
4920into account the factors set forth i n Section 403.537, Florida
4931Statutes.
493267. In the need proceeding, the PSC considered two
4941alternatives, including transmission modifications to the
4947existing 115 - kV system. The PSC accepted FPL ' s rejection of the
4961two alternatives " due to economics and conc erns with the ability
4972to serve additional future customers west of the I - 95/US - 1
4985corridor. " The PSC found that the proposed transmission line
4994would " assure the economic well - being of the citizens of the
5006state by serving projected new electric load in the region, and
5017improving the region ' s electric reliability by minimizing the
5027region ' s exposure to single contingency events. "
503568. The PSC has determined that the estimated cost of the
5046Project is reasonable, and that the SJPP Line will assure the
5057economic we ll - being of the citizens of the state by serving
5070projected new electric load in the region and improving the
5080region ' s electric reliability by minimizing the region ' s
5091exposure to single contingency events.
5096b. Impact Upon the Public
510169. The SJPP Line is appropriate from a land use
5111perspective because this type of transmission line currently
5119exists in all types of land uses in Florida, including
5129residential, commercial, industrial, agricultural, and vacant
5135land. The SJPP Line takes advantage of the opport unity to be
5147collocated with other transmission lines, roadways, and railroad
5155ROWs for almost the entire distance. By following these
5164existing linear features, the FPL Corridor conforms to existing
5173and future development patterns, and minimizes intrusion i nto
5182residential areas and conservation lands. As a result, the
5191proposed SJPP Line is in proximity to relatively few residences
5201and only one crossing of lands either purchased or proposed for
5212purchase under federal, state , or local land acquisition
5220program s. Further, by collocating with other public and utility
5230ROWs, the amount of land that will be required for the SJPP line
5243is less than if it were not collocated.
525170. The FPL Corridor minimizes impacts to existing homes
5260by following a route where there i s very little residential
5271development and where planned residential development is very
5279low density.
52817 1. T he SJPP Line as proposed will comply with all
5293applicable non - procedural standards, including the noise
5301ordinances of St. Johns County and the C ity of Palm Coast, and
5314the standards adopted by the Department limiting the electric
5323and magnetic fields associated with transmission lines .
5331c. Impact Upon the Environment
533672. The SJPP Line Project as proposed will have minimal
5346environmental impact.
534873. Co nstruction of the SJPP Line within t he FPL Corridor
5360will not adversely affect the conservation of fish and wildlife,
5370including endangered or threatened species, or their habitats.
5378The FPL Corridor avoids or minimizes intrusion into the
5387undisturbed wildlif e habitats due to its collocation with
5396existing linear facilities for almost its entire length. The
5405current condition and relative value of function of the habitat
5415in the FPL Corridor is minimal from a wildlife ecology and
5426protected species perspective. Great care was taken in routing
5435the FPL Corridor to avoid or minimize proximity of the corridor
5446to known listed species locations, including routing inputs from
5455wildlife agencies such as the F lorida Fish and Wildlife
5465Conservation Commission (F F WCC ) and the U.S. Fish and Wildlife
5477Service. Further, due to the presence of existing linear
5486features along much of the route, clearing of additional natural
5496habitats and potential wetland impacts will be minimized.
550474. Construction of the SJPP Line within t he FPL Corridor
5515will not cause a significant adverse impact to the current
5525condition and relative value of functions of the vegetative
5534communities within the FPL Corridor. First, nearly the entire
5543length of the FPL Corridor allows placement of the transmission
5553l ine within or adjacent to existing linear features to take
5564advantage of previous disturbances to vegetation . FPL will also
5574minimize impacts to forested wetland vegetation through the use
5583of restrictive clearing practices during both construction and
5591maint enance. In the forested wetland portions of the ROW , FPL
5602will only take out trees and shrubs that have an expected mature
5614height greater than 14 feet and " danger trees, " which are trees
5625that could fall into the conductors and cause an outage. In
5636these ar eas, vegetation will be removed by hand, usually with
5647chain saws, or with low - ground - pressure shear or rotary machines
5660to reduce soil compaction and damage to ground cover. The
5670removal of vegetation in forested wetlands will not affect the
5680vegetative root mat or soil surface conditions. The non -
5690forested wetlands should not require any clearing.
569775. There will be some filling in wetlands associated with
5707the placement of pole pads and access roads. However, FPL will
5718minimiz e impacts on wetlands vegetatio n through a careful
5728alignment of the ROW and the varying of span distances between
5739poles. FPL will also install an appropriate number and size of
5750culverts to properly maintain existing wetland hydroperiods
5757along areas of fill in wetlands. Also, any unavo idable wetland
5768impacts associated with the project will be mitigated in
5777accordance with the Conditions of Certification.
578376. FPL has agreed to avoid the removal of listed plant
5794species on public lands and waters, wherever practicable. When
5803removal is ne cessary on public lands/waters, FPL will consult
5813with the Department , F F WCC, and the Department of Agriculture
5824and Consumer Services to determine the appropriate steps to
5833minimize, mitigate , or otherwise appropriately address potential
5840project related impa cts to listed plant species. FPL ' s
5851commitment to avoid, minimize and/or mitigate potential impacts
5859to listed plant species within public lands and waters will
5869promote the conservation of endangered and threatened plant
5877species populations and their habita ts.
588377. The SJPP Line Project will comply with all applicable
5893state, regional , and local non - procedural regulations, including
5902the wetland regulatory standards applicable to such projects.
5910d . Balance of Need versus Impacts
591778. The SJPP Line would effe ct a reasonable balance
5927between the need for a transmission line as a means for
5938providing abundant low cost energy and the impact upon the
5948public and the environment resulting from the location of the
5958transmission line corridor and the construction and mai ntenance
5967of the transmission line.
5971VI. C onditions of Certification
597679. The design, construction , and operation of the SJPP
5985L ine as proposed in the FPL Corridor will comply with the
5997conditions of certification set forth in Department Exhibit 1.
600680. T he conditions of certification establish a post -
6016certification review process through which the final right - of -
6027way, access road , and structure locations will be reviewed by
6037agencies with regulatory authority over the project for the
6046purpose of monitoring fo r compliance with the conditions of
6056certification .
605881. While the FPL Corridor has few homes in close
6068proximity to it and very limited wetland crossings, FPL has
6078agreed to conditions of certification that further minimize land
6087use and environmental impact s. For example, FPL has agreed that
6098to the extent practicable it will locate its ROW to avoid the
6110taking of homes, to collocate the ROW within or adjacent to
6121existing ROWs, and to vary the length of the span between poles
6133as appropriate to eliminate or re duce wetland impacts.
6142CONCLUSIONS OF LAW
614582. The Division of Administrative Hearings has
6152jurisdiction over the parties to, and the subject matter of,
6162this proceeding. § § 120.569 and 403.527(2), Fla. Stat.
617183. This certification proceeding was held pur suant to the
6181Transmission Line Siting Act, Sections 403.52 through 403.5365,
6189Florida Statutes, and Florida Administrative Code Chapter 62 - 17,
6199Part II. The intent of this licensing process is:
6208to fully balance the need for the
6215transmission lines with the b road interests
6222of the public in order to effect a
6230reasonable balance between the need for the
6237facility as a means of providing abundant
6244low - cost electrical energy and the impact on
6253the public and the environment resulting
6259from the location of the transmiss ion line
6267corridor and the construction and
6272maintenance of the transmission lines.
6277§ 403.521, Fla. Stat. To implement this intent, the Legislature
6287has set forth specific requirements for the PSC to determine the
6298need for the proposed transmission line and address other
6307matters within its jurisdiction, for other various agencies to
6316prepare reports and studies regarding matters within their
6324jurisdiction, for publication of notice of the application and
6333certification proceeding, for third parties to have an
6341o pportunity to offer alternate corridor routes for
6349consideration, and for criteria to be considered in determining
6358whether an application should be approved in whole, approved
6367with modification or conditions, or denied. See §§ 403.526,
6376403.527, 403.5271, a nd 403.529, Fla. Stat.
638384. All parties identified in Finding of Fact No. 1 have
6394standing in this proceeding.
639885. FPL has the burden of proving that , under the criteria
6409of Section 403.529(4), Florida Statutes, the FPL Corridor for
6418the SJPP Line should be certified as proposed based upon a
6429preponderance of the evidence presented at the certification
6437hearing. See , e.g. , F la. Dept. of Transp. v . J.W.C Co., Inc. ,
6450396 So. 2d 778, 788 (Fla. 1 st DCA 1981).
646086. The evidence in the record of this proceeding
6469d emonstrates compliance with the procedural requirements of the
6478TLSA, including the notice requirements for the certification
6486and public hearings.
648987. In deciding whether FPL ' s Application for Corridor
6499Certification should be approved, approved with condi tions, or
6508denied, the Siting Board must determine whether, and the extent
6518to which, the location of the corridor and the construction and
6529maintenance of the transmission line in the corridor will:
6538(a) Ensure electric power system
6543reliability and integrity ;
6546(b) Meet the electrical energy needs
6552of the state in an orderly and timely
6560fashion;
6561(c) Comply with nonprocedural
6565requirements of agencies;
6568(d) Be consistent with applicable
6573local government comprehensive plans; and
6578(e) Effect a reasonable balanc e
6584between the need for the transmission line
6591as a means of providing abundant low - cost
6600electrical energy and the impact upon the
6607public and the environment resulting from
6613the location of the transmission line
6619corridor and the maintenance of the
6625transmissio n lines.
6628§ 403.529(4), Fla. Stat.
663288. Compliance with Section 403.529(4)(a), Florida
6638Statutes . The PSC determined the need for a new 230 - kV
6651transmission line between the St. Johns River and Pringle
6660substations in Order No. PSC - 05 - 0527 - FOF - EI, issued on May 13,
66772005 . Among other things, t he PSC found that construction of
6689the proposed SJPP L ine would " improve the region ' s electric
6701reliability by minimizing the region ' s exposur e to single
6712contingency events." The PSC also found that if FPL does not
6723add th is new transmission capability by 2008, up to 8,300
6735electric customers could be subject to service interruptions.
6743Th e s e finding s of the PSC address the extent to which the
6758reliability, integrity , and service restoration of the electric
6766system will be enh a nced. Th e PSC ' s determination of need for
6781the SJPP Line Project is binding upon all parties to the
6792certification proceeding. § 403.537(1)(c), Fla. Stat. By
6799submitting the PSC Order Determining Need into the record, FPL
6809made a prima facie showing that th e FPL C orridor would enhance
6822electric system reliability, integrity , and restoration of
6829service. The PSC found that the FPL Corridor meets the
6839criterion of Section 403.529(a), Florida Statutes .
684689. Compliance with Section 403.529(4)(b), Florida
6852Statutes . The PSC acknowledged in its O rder D etermining N eed
6865for the SJPP Line that FPL ' s planning studies indicate the
6877proposed transmission line needs t o be in service by December
68882008 to alleviate potential overloads and low voltage conditions
6897from a single co ntingency event. Evidence regarding the design
6907of the transmission line, the construction phases for the
6916transmission line, including the projected 13 - month construction
6925schedule, and the proposed location of the SJPP Line
6934demonstrates that the SJPP Line will meet the electrical needs
6944of the state in an orderly and timely fashion within the time
6956frames established by the PSC.
696190. Compliance with Section 403.529(4)(c), Florida
6967Statutes . The location of the SJPP Line in the FPL Corridor and
6980the construct ion and maintenance of that SJPP Line in
6990conformance with the recommended Conditions of Certification
6997contained in Department Exhibit 1 will comply appropriately with
7006the non - procedural requirements of all agencies.
701491. Compliance with Section 403.529(4 )(d), Florida
7021Statutes . There are no inconsistencies between the proposed
7030SJPP Line project and the local government comprehensive plans
7039adopted by local governments whose jurisdictions are crossed by
7048the SJPP Line .
705292. Compliance with Section 403.529( 4)(e), Florida
7059Statutes . The location of the FPL Corridor and the
7069construction , operation , and maintenance of the SJPP Line in
7078that corridor provide a reasonable balance between the need for
7088the transmission line and the impact of the transmission line
7098up on the public and the environment. The impact upon the public
7110and the environment will be minimized by the SJPP Line ' s
7122collocation with existing linear facilities for nearly its
7130entire length. Furthermore, the impact from clearing activities
7138and any othe r construction and operation activities associated
7147with the SJPP Line will be minimal, particularly when balanced
7157with the significant electrical energy requirements that will be
7166satisfied by the construction and operation of the SJPP
7175transmission line in the FPL Corridor.
718193. Based upon a preponderance of the evidence presented
7190at the certification hearing, FPL has met its burden of proving
7201that the SJPP Line and related facilities should be certified as
7212proposed , subject to the Conditions of Certificati on included in
7222Department Exhibit 1.
7225RECOMMENDATION
7226Based upon the foregoing Findings of Fact and Conclusions
7235of Law, it is
7239RECOMMENDED that the Siting Board enter a Final Order
7248approving FPL ' s St. Johns - Pellicer - Pringle 230 - kV Transmission
7262Line Applicat ion for Certification subject to the Conditions of
7272Certification set forth in Department Exhibit 1.
7279DONE AND ENTERED this 6th day of March, 2006, in
7289Tallahassee, Leon County, Florida.
7293S
7294DONALD R. ALEXANDER
7297Administrativ e Law Judge
7301Division of Administrative Hearings
7305The DeSoto Building
73081230 Apalachee Parkway
7311Tallahassee, Florida 32399 - 3060
7316(850) 488 - 9675 SUNCOM 278 - 9675
7324Fax Filing (850) 921 - 6847
7330www.doah.state.fl.us
7331Filed with the Clerk of the
7337Division of Administrat ive Hearings
7342this 6th day of March, 2006.
7348END NOTE
73501/ All subsequent references are to the 2005 version of the
7361Florida Statutes.
7363COPIES FURNISHED:
7365Lea Crand a ll, Agency Clerk
7371Department of Environmental Protection
73753900 Commonwea l th Boulevard
7380Mail St ation 35
7384Tallahassee, Florida 32399 - 3000
7389Gregory M. Munson, General Counsel
7394Department of Environmental Protection
73983900 Commonwealth Boulevard
7401Mail Station 35
7404Tallahassee, Florida 32399 - 3000
7409Carolyn S. Raepple, Esquire
7413Hopping Green & Sams, P.A.
7418Post O ffice Box 6526
7423Tallahassee, Florida 32314 - 6526
7428Scott A. Goorland, Esquire
7432Department of Environmental Protection
74363900 Commonwealth Boulevard
7439Mail Station 35
7442Tallahassee, Florida 32399 - 3000
7447Kelly A. Martinson, Esquire
7451Department of Community Affairs
7455255 5 Shumard Oak Boulevard
7460Tallahassee, Florida 32399 - 2100
7465Michael D. Hunt, Esquire
7469Deputy County Attorney
74724020 Lewis Speedway, Suite 1120
7477St. Augustine, Florida 32084 - 8637
7483Veronika Thiebach, Esquire
7486St. Johns River Water Management District
74924049 Reid Str eet
7496Palatka, Florida 32177 - 2529
7501Lonnie N. Groot, Esquire
7505Stenstrom, McIntosh, Colbert
7508200 West First Street, Suite 22
7514Sanford, Florida 32771 - 1268
7519Seauching Yu, Esquire
7522Department of Transportation
7525605 Suwannee Street
7528Mail Station 58
7531Tallahassee, Flori da 32399 - 0458
7537James V. Antista, General Counsel
7542Florida Fish and Wildlife
7546Conservation Commission
7548620 South Meridian Street
7552Tallahassee, Florida 32399 - 1600
7557Brian D. Teeple, Executive Director
7562Northeast Florida Regional Planning Council
75676850 Belfort Oaks Place
7571Jacksonville, Florida 32216 - 6241
7576Carl E. Kern, III, Esquire
7581Flagler County Attorney
75841200 East Moody Boulevard, Suite 11
7590Bunnell, Florida 32110 - 5919
7595Martha Carter Brown, Esquire
7599Office of the General Counsel
7604Florida Public Service Commission
76082540 Shumard Oak Boulevard
7612Tallahassee, Florida 32399 - 0850
7617Heidi M. Hughes, General Counsel
7622D epartment of Community Affairs
76272470 Centerview Drive
7630Tallahassee, Florida 32399 - 2100
7635NOTICE OF RIGHT TO FILE EXCEPTIONS
7641All parties have the right to submit written exceptions within
765115 days of the date of this Recommended Order. Any exceptions
7662to this Recommended Order should be filed with the agency that
7673will render a final order in this matter.
- Date
- Proceedings
- PDF:
- Date: 05/01/2006
- Proceedings: Letter to FP&L from S. Goorland enclosing Conditions of Certification that were incorporated by reference in the Final Order Approving Certification of Transmission Line for FP&L St. Johns-Pellicer-Pringer, 230KV Project filed.
- PDF:
- Date: 03/06/2006
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- Date: 01/18/2006
- Proceedings: Transcript of Proceedings filed.
- Date: 01/10/2006
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 01/05/2006
- Proceedings: Notice of Filing Corrected Second Page to Stipulation between Florida Power and Light Company and Department of Environmental Regulation filed.
- PDF:
- Date: 01/04/2006
- Proceedings: Joint Stipulation of FPL and St. Johns River Water Management District Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
- PDF:
- Date: 01/03/2006
- Proceedings: Joint Stipulation of FPL and City of Palm Coast Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
- PDF:
- Date: 12/29/2005
- Proceedings: Department of Environmental Protection`s Notice of Filing of Revised Written Analysis filed.
- PDF:
- Date: 12/29/2005
- Proceedings: Joint Stipulation of FPL and Department of Environmental Protection Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
- PDF:
- Date: 12/22/2005
- Proceedings: Joint Stipulation of FPL and Department of Community Affairs Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
- PDF:
- Date: 12/20/2005
- Proceedings: Joint Stipulation of FPL and Department of Transportation Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
- PDF:
- Date: 12/19/2005
- Proceedings: Joint Stipulation of FPL and St. Johns County Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
- PDF:
- Date: 12/19/2005
- Proceedings: Amended Order Amending Schedule of Procceedings (deadline for the filing of written direct testimony of witnesses and exhibits shall be no later than fifteen days before the scheduled final hearing, or by Tuesday, December 27, 2005)..
- PDF:
- Date: 12/16/2005
- Proceedings: Order Amending Schedule of Proceedings (deadline for the filing of written direct testimony of witnesses and exhibits shall be no later than fifteen days before the scheduled final hearing, or by Tuesday, December 27, 2005) .
- PDF:
- Date: 12/09/2005
- Proceedings: Summary and Compilation of Agency Reports including Proposed Conditions of Certification for Florida Power and Light Company`s St. Johns-Pellicer-Pringle 230 KV Transmission Line Project filed.
- PDF:
- Date: 12/09/2005
- Proceedings: Department of Environmental Protection`s Notice of Filing of Written Analysis filed.
- PDF:
- Date: 10/11/2005
- Proceedings: St. Johns River Water Management District`s Notice of Intent to be a Party filed.
- PDF:
- Date: 08/18/2005
- Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
- PDF:
- Date: 08/11/2005
- Proceedings: Notice of The City of Palm Coast`s Notice of Intent to be a Party filed.
- PDF:
- Date: 08/05/2005
- Proceedings: Notice of St. Johns County`s Notice of Intent to be a Party filed.
- PDF:
- Date: 07/29/2005
- Proceedings: Notice of Hearing (hearing set for January 10 through 13, 2006; 9:00 a.m.; St. Augustine, FL).
- PDF:
- Date: 07/28/2005
- Proceedings: Department of Community Affairs` Notice of Intent to be a Party filed.
- PDF:
- Date: 07/22/2005
- Proceedings: Department of Environmental Protection`s Proposed Schedule of Significant Dates and Stipulation for Alteration of Time Frames filed.
- PDF:
- Date: 07/18/2005
- Proceedings: St. Johns-Pellicer-Pringle Transmission Line Project Application filed.
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 07/12/2005
- Last Docket Entry:
- 05/01/2006
- Location:
- St. Augustine, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- TL
Counsels
-
James V. Antista, Esquire
Address of Record -
Martha Carter Brown, Esquire
Address of Record -
Kelly M. Fernandez, Esquire
Address of Record -
Scott A Goorland, Esquire
Address of Record -
Lonnie Neil Groot, Esquire
Address of Record -
Michael Hunt, Esquire
Address of Record -
Carl E Kern, Esquire
Address of Record -
Carolyn S. Raepple, Esquire
Address of Record -
Brian D Teeple
Address of Record -
Veronika Thiebach, Esquire
Address of Record -
Sheauching Yu, Esquire
Address of Record -
Scott A. Goorland, Esquire
Address of Record -
Brian D. Teeple
Address of Record