05-002478TL In Re: Florida Power And Light St. Johns-Pellicer-Pringle 230 Kv Transmission Line Project Transmission Line Siting Application No. Ta05-13 vs. *
 Status: Closed
Recommended Order on Monday, March 6, 2006.


View Dockets  
Summary: Florida Power and Light demonstrated that a proposed transmission line from St. Johns County to Flagler County met all statutory requirements and should be certified.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8IN RE: FLORIDA POWER & LIGHT )

15ST. JOHNS - PELLICER - PRINGLE, )

22230 KV PROJECT, TRANSMISSION ) Case No. 05 - 2478TL

32LINE SITING APPLICATION NO. )

37TAO5 - 13. )

41___ ____________ ________________ )

45RECOMMENDED ORDER

47Pursuant to notice, a formal hearing was held in this case

58on January 10 , 2006 , in St. Augustine, Florida, before the

68Division of Administrative Hearings, by its assigned

75Administrative Law Judge, Donald R. Alexander .

82APPEARANCES

83For Florida Power Carolyn S. Raepple , Esquire

90& Light Company: Hopping Green & Sams, P.A.

98P ost Office Box 6526

103Tallahassee, Florida 32314 - 6526

108For Department Scott A. Goorland , Es quire

115of Environmental D epartment of Environmental Protection

122Protection: Mail Station 35

1263000 Commonwealth B oulevard

130Tallahassee, Florida 32399 - 3000

135For St. Johns Michael D. Hunt, Esq uire

143County: Deputy County Attorney

1474020 Lewis Speedway , Suite 1120

152St. Augustine, F lorida 32084 - 8637

159For St. Johns Veronika Th i e bach , Esq uire

169River Water St. Johns River Water Management District

177Management 4049 Re id Street

182District: Palatka, F lorida 32177 - 2529

189STATEMENT OF THE ISSUES

193The issues for determination are whether and the extent to

203which the properly proposed corridor (the FPL Corridor) for the

213St. Johns - Pellicer - Pringle 230 - kV transmissio n line (the SJPP

227Line) complies with the criteria in Section 403.529(4)(a) - (e),

237Florida Statutes (2005) 1 , and whether Florida Power & Light's

247(FPL 's ) application for corridor certification should be

256approved in whole, with modifications or conditions, or d enied.

266PRELIMINARY STATEMENT

268Pursuant to Section 403.537, F lorida S tatutes , FPL

277submitted a Petition to Determine Need for the SJPP Line project

288to the Public Service Commission (PSC) on March 25, 2005 . The

300PSC issued Order No. PSC - 0 5 - 0527 - FOF - EI, dated May 13, 2005 ,

318determining the need for the SJPP Line.

325On July 5, 2005, FPL filed its Application for Corridor

335Certification for the SJPP Line (Application) with the

343Department of Environmental Protection (Department) an d paid the

352appropriate application fee . The Application wa s filed under

362the Transmission L ine Siting Act (TLSA), codified in Section s

373403.52 through 403.5365, Florida Stat utes , for a new 230 - kV

385overhead transmission line and related facilities connecting the

393existing St. Johns substation near St. Augustine in St. Johns

403County to the proposed Pringle s ubstation in the C ity of Palm

416Coast in Flagler County (the Project).

422The various reviewing agencies have submitted reports on

430the Project and have proposed Co nditions of Certification. On

440D ecember 9, 2005 , the D epartment issued its Summary and

451Compilation of Agency Reports Including Proposed Conditions of

459Certification for the Project, incorporating the reports of the

468reviewing agencies and proposing a compiled set of Conditions of

478Certifica tion. During the certification hearing, a R evised

487Summary and Compilation of Agency Reports, including an updated

496version of the proposed Conditions of Certification , dated

504December 29, 2005, was a dmitted into the record as Department

515Exhibit 1 .

518The ce rtification hearing was held on January 10, 2006.

528All notices required by law were timely published in accordance

538with Section 403.527, F lorida Statutes. The final hearing was

548conducted for the purpose of receiving oral, written, and

557documentary evidence concerning whether the Project should be

565approved in whole, or with such modifications and conditions as

575the Siting Board deems appropriate, or denied under the TLSA.

585FPL presented one witness and offered composite exh ibits

594numbered FPL 1 , which includes the prefiled written testimony of

604four witnesses , Daniel Hronec, Analee Mayes , Anthony N. Arcuri,

613and Philip Simpson, and exhibits numbered as DH - 1, DH - 2, DH - 3,

629AM - 1, AM - 2, PS - 1, and TA - 1 , and FPL 2 , which contains the

648various notices of publication relat ed to this matter. A lso, on

660January 20, 2006, FPL submitted late - filed exhibit FPL 3, which

672includes the public notices from the D epartment 's website .

683Finally , official recognition of these notices has been taken.

692At the hearing, FPL presented the te stimony of Daniel

702Hronec, P.E., an expert in electrical transmission line

710engineering, who t estif ied and submitted pre - filed written

721testimony and exhibits . FPL also submitted pre - filed testimony

732and exhibits from: Analee Mayes, AICP, an expert in land us e

744planning; Anthony N. Arcuri, an expert in botany, vegetative

753mapping , and listed plant species; and Phil ip Simpson, an expert

764in wildlife ecology and transmission line impacts to t errestrial

774ecological resources. All pre - filed written testimony and

783exhi bits submitted by FPL have been received into evidence

793without objection.

795In addition to presenting the Revised Summary and

803Compilation of Agency Reports, the Department presented the

811testimony of Ann Seiler, an Environmental Specialist III who

820coordinate d the processing of the Application , and prepared the

830Revised Summary and Compilation of Agency Reports .

838A publi c hearing was held at 11 :00 a .m. on January 10 ,

8522006 , for the purpose of allowing members of the public an

863opportunity to present evidence and testimony. No member of the

873public appeared to testify.

877The Transcript of the final hearing was filed with the

887Division of Ad ministrative Hearings on January 18, 2006 . On

898February 16, 2006, FPL filed a Proposed Recommended Order which

908has been substant ially used in the preparation of this

918Recommended Order.

920FINDINGS OF FACT

923Based upon all of the evidence the following findings of

933fact are determined:

936I. Parties

9381. The TLSA establishes FPL and the Department as parties

948to this proceeding, and the follo wing became parties upon their

959timely filing of a notice of intent to be a party, which each

972has done: F lorida D epartment of Transportation (D OT ) ,

983D epartment of Community Affairs (D CA ) , St. Johns River Water

995Management District ( SJR WMD ) , St. Johns County, and the C ity of

1009Palm Coast . See § 403.527(4), Fla. Stat.

1017II. The Application

1020A . Project Description

10242. Generally, a n electrical transmission line ' s purpose is

1035to transport large amounts of electricity from a generating

1044facility to one or more substati ons. At the substation, the

1055electricity can be either increased or reduced in voltage

1064through transformers and other electrical equipment for further

1072safe and practical transportation , or distribution directly to

1080customers.

10813. FPL is seeking certificat ion of a corridor between the

1092existing St. Johns substation and the proposed Pringle

1100substation within which it will ultimately construct the SJPP

1109Line on a narrow right - of - way (ROW). Once all property

1122interests in the ROW are acquired, the boundaries of the

1132corridor will shrink to the typical width of the 15 to 60 - foot

1146ROW.

11474. The service area for the proposed SJPP Line (the

1157Project Service Area) is St. Johns County and Flagler County .

1168T he SJPP Line will follow Interstate 95 (I - 95) in a north - south

1184di rection and will connect to the proposed intermediate

1193Deerwood, Vermont, Anastasia , and Pellicer substations.

11995. The Project Service Area includes an area of increasing

1209load and customer base in the area south of St. Johns and north

1222of Pringle substatio ns and to the west of the existing Bunnell -

1235St. Johns 115 - kV transmission line.

12426. The three objectives of the SJPP Line project are: (1)

1253to address the need, as confirmed by the PSC , to serve FPL ' s

1267increasing load and customer base in the area south of St. Johns

1279and north of Pringle substations in a reliable manner; ( 2) to

1291provide additional transmission reinforcement to the existing

1298115 - kV transmission line between the Bunnell and St. Johns

1309substations; and (3) to efficiently and effectively integrate

1317a nd serve new distribution substations that are needed to serve

1328projected load growth within Flagler and St. Johns Counties .

1338The primary path for the SJPP transmission line bringing

1347electricity into the Project Service Area will be aligned within

1357or adjace nt to existing linear features, such as existing road,

1368transmission line and railroad ROWs. The only exception is a

1378distance of less than half a mile in length between the proposed

1390Vermont substation in the St. Augustine Industrial Park and

1399I - 95, where the corridor largely follows property lines.

14097. The primary path for the SJPP transmission line

1418bringing electricity into the Project Service Area will be

1427aligned within or adjacent to existing linear features, such as

1437existing road, transmission line, and railroad ROWs. The only

1446exception is a distance of less than half a mile in length

1458between the proposed Vermont substation in the St. Augustine

1467Industrial Park and I - 95, where the corridor largely follows the

1479property line.

1481B. Need for the SJPP Line

14878. The P SC determined a new 230 - kV transmission line

1499between the St. Johns substation and the proposed Pringle

1508substation is needed, taking into account the need for electric

1518system reliability and integrity in northeast Florida and the

1527need to provide a bundant, low - cost electrical energy to assure

1539the economic well - being of the citizens of the State,

1550particularly those in northeast Florida.

15559. The PSC noted that FPL ' s planning studies indicate this

1567additional transmission capacity will be needed by Dec ember 2008

1577to alleviate potential overloads and low voltage conditions that

1586could result from a single contingency event. Without the

1595addition of this transmission capability by 2008, the PSC found

1605that up to 8,300 electric customers could experience serv ic e

1617interruptions.

161810. The PSC recognized that the Siting Board will make the

1629final corridor selection upon consideration of the factors and

1638criteria specified in Section 403.529, Fl orida Stat utes .

1648C. Transmission Line Design

165211. The typical design for the SJPP Line will be a single -

1665circuit unguyed concrete pole structure, 90 feet above grade in

1675height, with the conductors framed in a vertical configuration.

1684Each of the three conductors is anticipated to be a 1,431

1696thousand circular mils , aluminum cond uctor, steel reinforced

1704alumoweld core. There will also be a smaller overhead ground

1714wire to provide shielding and lightning protection for the

1723conductors and provide communications capability . The maximum

1731current rating for the line will be 1,905 ampere s. In some

1744locations, electric distribution lines and communication cables

1751may also be attached to the structures bene ath the conductors .

176312. In some locations, such as along FPL ' s St. Johns - Tocoi

1777transmission line right - of - way and along Tocoi Road, a d ouble -

1792circuit configuration, with or without distribution underbuild,

1799may be used.

180213. The span length between structures will ty pically vary

1812between 250 and 75 0 feet , depending on site - specific conditions,

1824ROW widths , and other design considerations. Both pole height

1833and span length may vary to accommodate such things as locating

1844poles to coincide with property boundaries or existing

1852collocated utility facility poles, to avoid or minimize wetland

1861impacts, to cross other utility lines, and to facilitate wide

1871crossings of water bodies and roadways.

187714. Where the transmission line turns large angles or

1886crosses other major linear facilities , the structures may be

1895guyed or anchored to support the differential tension.

190315. Access roads and structure pads will be constructed

1912only where necessary to provide access for construction,

1920maintenance , and emergency restoration. Where constructed, the

1927typical road top width will be about 14 feet , with a 2 - to - 1 side

1944slope, and a minimum elevation of 6 inches over me an or seasonal

1957high water. Structur e pads will have variable sizes, depending

1967on site specific requirements, but will be of sufficient size to

1978provide access to structure locations for the large construction

1987equipment. Access roads and structur e pads wil l not be paved.

1999Culverts will be installed beneath access roads and structure

2008pads with spacing, diameter , and length to maintain

2016preconstruction flo ws.

201916. The design of the SJPP Line complies with good

2029e ngineering practices. The SJPP Line will be des igned in

2040compliance with all applicable design codes, including the

2048National Electrical Safety Code (NESC) , the D epartment's

2056regulations on electric and magnetic fields, the DOT Utility

2065Accommodation Manual, the St. Johns County and City of Palm

2075Coast nois e ordinances, and standards of the Amer ican Society of

2087Civil Engineers (ASCE) , the Institute of Electrical and

2095Electronics Engineers , Amer ican Society of Testing Materials,

2103American National Standards Institute, and American Concrete

2110Institute, as well as FPL ' s own design standards.

212017. The Project assures the citizens of Florida that

2129operation safeguards are technically sufficient for their

2136welfare and protection.

2139D. Transmission Line Construction

214318. Surveying the ROW to facilitate acquisition of th e

2153necessary property interests is a first step towards

2161construction. After property rights for the ROW have been

2170acquired, the initial phase of construction is to clear the ROW.

2181Since nearly the entire length of the FPL Corridor is collocated

2192with existi ng roads and utility facilities, the need for

2202acquisition of private property and the need for clearing ha ve

2213been minimized. Clearing will consist mainly of tree trimming

2222and the removal of trees that exceed or are capable of exceeding

223414 feet in height. In wetlands, trees capable of exceeding 14

2245feet in height that could come in conflict with the line will be

2258removed by hand - clearing or use of very low ground pressure

2270equipment. Low - growing herbaceous vegetation will not be

2279cleared from wetlands.

228219. After the ROW is cleared, any necessary access roads

2292and structure pads will be constructed. Typically, access road s

2302and pads are only required in wet and low areas. This enables

2314all subsequent construction activity in those wet areas to

2323remain on the ne wly constructed access road and pad.

233320. The next phases of construction involve the physical

2342transmission line construction. Initially, materials are

2348brought to the jobsite. Next, holes are augered at each pole

2359location and the poles are then erected using cranes or other

2370heavy equipment. The hole is then backfilled with suitable

2379fill. Typically, the pole is embedded into the ground

2388approximately 16 to 20 feet .

239421. After the poles are set, the poles are framed , that

2405is, the insulators and hardware a re installed on the pole. Then

2417through a wire pulling operation the conductors and overhead

2426groun d wires are installed. The conductors are then properly

2436sagged and tensioned to provide the proper vertical clearances.

2445Next, the conductors are " lipped in " to the insulator

2454assemblies. The final stage of constru ction is ROW clean - up.

246622. During all stages of construction, FPL will maintain

2475traffic on any adjacent county, state , or federal roadways in

2485compliance with applicable DOT and St. Johns County regu lations .

249623. Throughout construction, sedimentation management

2501techniques, such as the use of silt screens and hay bales, will

2513be employed as necessary to minimize potential impacts from

2522e rosion and sedimentation.

252624. While each phase of construction w ill typically take

2536only 1 to 7 days in an area, the entire SJPP Line construction

2549process will last approximately 13 months.

2555E . Methodology for Choosing FPL Corridor

256225. On project initiation, FPL management instructed its

2570multi - disciplinary corridor se lection team to identify, if it

2581could, a corridor for the SJPP Line that connects the St. Johns

2593and Pringle substations and allows connections to the proposed

2602intermediate substations.

2604a. Corridor Selection and Public Involvement

261026. FPL established a m ulti - disciplinary team to identify

2621and evaluate routing alternatives within the Project Study Area.

2630This multi - disciplinary team was comprised of a transmission

2640line engineer, a land use planner, and an ecologist.

264927. FPL ' s multi - disciplinary team gathere d data on siting

2662opportunities and constraints within the study area and

2670identified 45 line segments which could be assembled into

2679approximately 630 alternate routes for the SJPP Line.

268728. FPL also engaged in an extensive public participation

2696program to gather input for its route evaluation study. This

2706public participation program included an open house, mass

2714mailings, a community surve y, a toll - free telephone number and

2726an e - mail address, a website, and meetings with regulatory

2737agencies, community assoc iations, homeowner groups, and

2744individual homeowners and property owners.

274929. The public participation program provided substantive

2756input to the route evaluation study in terms of study area

2767boundary, siting opportunities and constraints in the area,

2775ide ntification of route segments to be evaluated, and weights to

2786be assigned to the route evaluat ion criteria.

279430. FPL ' s multi - d isciplinary team evaluated the 630 routes

2807quantitatively, using 11 weighted factors , and then evaluated in

2816more detail, using bot h quantitative and qualitative criteria, a

2826few distinct routes identified from among the highest - ranking

2836routes .

283831. Through this process, FPL ' s multi - disciplinary team

2849was able to identif y a route o f the FPL Corridor that , on

2863balance , is the most approp riate considering environmental, land

2872use, engineering, and cost considerations.

287732. Once the preferred alignment was identified, the

2885multi - disciplinary team delineated the boundaries or width of

2895the FPL Corridor to provide flexibility for l ocating the

2905e ventual ROW within that corridor.

2911b . Agencies ' Review of FPL ' s Application and Resulting

2923Determinations

292433. S tate, regional , and local agenc ies with regulatory

2934authority over the project reviewed FPL ' s Application and

2944submitted to the Department a repo rt as to the impact of the

2957proposed SJPP Line on matters within the agency ' s jurisdiction,

2968as required by Section 403.526(2), Fl orida Statutes. The

2977Department then compiled these reports and made a recommendation

2986that the SJPP Line be granted approval sub ject to appropriate

2997conditions.

2998III. Stipulations Entered Into by Parties

300434. All agency parties filed stipulations with FPL in

3013which these parties and FPL agreed to the Conditions of

3023Certification for the SJPP line and the entry into the record of

3035the pre - file d written testimony and exhibits of FPL ' s witnesses .

3050IV. D etailed Description of the FPL Corridor

305835. Almost the entire length of the FPL Corridor is

3068collocated with existing linear features, such as roa ds and

3078transmission lines. This collocatio n will minimize impacts of

3087the new SJPP Line. The width of the FPL Corridor varies along

3099the route to provide flexibility within the corridor to minimize

3109or avoid impacts to such areas as existing developments and

3119large wetland areas.

3122A. F rom the St. Johns Substation to the Deerwood

3132Substation

313336. The SJPP line will exit the existing St. Johns

3143substation at SR 207 near Lightsey Boulevard and utilize the

3153existing 110 - f oo t - wide St. Johns - Tocoi 230 - kV ROW. The FPL

3171Corridor will be collocated within this exis ting ROW north and

3182west until the intersection with I - 95. Along the existing ROW

3194and in the vicinity of the St. Johns substation, the land use is

3207residential or vacant.

321037. At I - 95, the preferred corridor will follow the

3221eastern ROW line of the highway south to the intersection with

3232Tocoi Road. The corridor in this stretch is 500 f ee t wide.

3245Within the corridor in this stretch, the land use is vacant.

3256There is some residential development outside the corridor to

3265the east.

326738. At the I - 95/Tocoi Road i ntersection, the FPL Corridor

3279is expanded in all four quadrants following property lines to

3289allow FPL flexibility in traversing the short distance to

3298Deerwood substation and crossing I - 95 to proceed south f rom

3310Deerwood.

331139. The FPL Corridor follows Tocoi Road to enter and exit

3322the proposed Deerwood substation, encompassing 100 f ee t or less

3333in width on both the north and south sides of the road. The

3346line will be built either on the south or north side of the

3359road. A FPL distribution line currently exists on the south

3369side of Tocoi Road .

3374B. F rom the Deerwood Substation to the Vermont Substation

338440. The FPL Corridor will leave the Tocoi Road alignment

3394at the I - 95 intersection. The FPL Corridor then follows the

3406western ROW edge of I - 95 south to the FEC Railr oad, where the

3421corridor turns to the southwest for a short distance. In this

3432section, the corrid or is 500 f ee t wide.

344241. At the north end of the St. Augustine Industrial Park,

3453the corridor follows property lines to the access road (Deerpark

3463Boulevard) i nto the industrial park. The corridor is 200 f ee t

3476wide in this section. From the north end of the access road,

3488the FPL Corridor follows the east edge of the road south to the

3501Vermont substation site , is 100 f ee t wide in this section , and

3514includes an exis ting FPL distribu tion line.

3522C. From the Vermo nt Substation to the Anastasia

3531Substation

353242. The FPL Corridor exits the Vermont substation heading

3541northeast toward I - 95. In this area, the corridor will be of

3554variable width and will include both sides of S tate Road 207 (SR

3567207) . An existing 115 - kV FPL transmission line already occupies

3579the north side of the SR 207, and a distribution line is located

3592on the south side. An existing FPL distribution line traverse s

3603north - south in this area and is also include d in the corridor.

3617In the area between the Vermont substation and I - 95 , the

3629corridor is north and east of existing residential subdivisions.

363843. The corridor between the Vermont substation and I - 95

3649is widened to allow flexibility in accommodating a num ber of

3660land use and engineering considerations. These considerations

3667include the crossing of SR 207, the existing transmission line

3677and distribution lines, existing residential development south

3684of SR 207, existing commercial development north of SR 207, and

3695a large borrow pond west of I - 95.

370444. The corridor will reach I - 95 south of SR 207, at which

3718point it will then follow I - 95 ' s western boundary southward.

3731The corridor is 500 f ee t wide in this area where it parallels

3745I - 95 south to SR 206.

375245. The predominant land use in the area between the

3762Vermont and Anastasia substations is silviculture.

3768D. From the Anastasia Substation to the Pellicer

3776Substation

377746. At the intersection of SR 206 and I - 95, the corridor

3790is again widened variably to include the p roperties on the

3801northwest and southwest quadrants of the interchange to provide

3810flexibility in finalizing the Anastasia substation plans and

3818providing ingress and egress to that substation.

382547. The FPL Corridor will exit the Anastasia substation

3834and fo llow the western boundary of I - 95 southward. The corridor

3847is 500 f ee t wide in this stretch with the exception of the

3861location of a rest area on the west side of I - 95 , approximately

38752.5 miles south of Anastasia substation . The corridor is of

3886variable widt h around the rest area, but generally 1,000 f ee t

3900wide to allow flexibility in traversing either the front or rear

3911of the rest area. In this area, the predominant land use is

3923silviculture.

392448. Where I - 95 intersects the FEC Railroad north of C ounty

3937Road 2 04 (CR 204) , the FPL Corridor turns and follows the

3949railroad southward. The corridor is located along the east side

3959of the railroad and is 500 f ee t wide. North of CR 204, the

3974corridor is expanded along the road to allow ingress to the

3985Pellicer substation site located south of CR 204 and east of the

3997railroad. Land uses in this area are primarily silviculture.

4006E. From the Pellicer Substation to the Pringle Substation

401549. The FPL Corridor includes the entire Pellicer site,

4024which is already owned by FPL, alo ng the east side of the FEC

4038Railroad south to Pellicer Creek. The corridor in this area

4048crosses lands owned or proposed to be purchased by the SJRWMD

4059for conservation purposes for approximately one mile.

406650. From Pellicer Creek south to the Pringle subs tation,

4076the corridor will follow the east side of the railroad bed and

4088will be variable in width, generally 150 to 300 f ee t wide.

410151. At the Pringle substation site, which is already owned

4111by FPL, the corridor includes the entire substation site. The

4121FP L Corridor for the stretch sout h of Pellicer Creek falls in a

4135currently undeveloped portion of the Palm Coast Park D evelopment

4145of Regional Impact (D RI ) within the City of Palm Coast ' s

4159jurisdict ion. The development order for the Palm Coast Park DRI

4170provide s for an easement for the SJPP transmission line within

4181the FPL C orridor .

4186V. C ompliance With Section 403.529(4) C riteria

4194A . Ensure Electric Power System Reliability and Integrity

420352. The PSC found that there are regional transmission

4212system limitations in St. Johns and Flagler Counties. By 2008,

4222the existing 115kV transmission network between the Bunnell

4230substation in Flagler County and the St. Johns s ubstation in

4241St. Johns County will not have sufficient capacity to provide

4251reliable electric service to the existing and proposed

4259substations in the area. The SJPP Line would be built to

4270alleviate potential overloads and low voltage conditions from a

4279single contingency event, which occurs when a single element

4288such as a generator, transmission circuit or transformer is

4297eliminated from the system. If the SJPP Line is not built,

4308service interruptions affecting up to 8,300 customers could

4317occur.

431853. In addition, the PSC found that the FPL North Region

4329(extending from Indian River County to Nassau County) has grown

4339by a compound annual average growth rate of 3.7 percent over the

4351past five years. The SJPP Line is also needed to serve the

4363increasing load and customer base in the area.

437154. O peration of the SJPP Line would be consistent with

4382the North Amer ican Electric Reliability Council and Florida

4391Reliability Coordinating Council transmission system standards.

439755. FPL has a responsibility to provide safe and reliable

4407service to its customers. S ee § 366.03, Fla. Stat. The

4418provision of reliable electri c service is impor tant to FPL and

4430its customers. In the past, FPL has demonstrated the ability to

4441plan a reliable electric system consistent with the NESC and

4451ASCE standards.

4453B. Meet the Electrical Energy Needs of the State in an

4464Orderly and Timely Fa shion

446956. The PSC recognized that FPL ' s planning studies

4479indicate that the SJPP Line is needed by December 200 8 to

4491alleviate potential overloads and low voltage conditions from a

4500single cont ingency event.

450457. Location of the SJPP Line on the FPL Corrid or would

4516meet the electrical energy needs of the state in a timely

4527fashion .

4529C. Comply with the Nonprocedural Requirements of Agencies

453758. Construction, operation , and maintenance of the SJPP

4545Line in the FPL Corridor will comply with applicable non -

4556proce dural requirements of agencies.

456159. The D epartment has concluded that the project as

4571proposed will comply with all applicable D epartment statutes,

4580rules, policies, and procedures.

4584D. Be Consistent with Applicable Local Government

4591Comprehensive Plans

459360. The D epartment has concluded that the SJPP Line as

4604proposed would produce a minimal adverse impact on the

4613environment and public health, safety , and welfare without

4621unduly conflicting with local statute s and local comprehensive

4630plans.

463161. After certific ation of this project, FPL will acquire

4641the necessary property interest s in a ROW within the certified

4652corridor for placement of the SJPP Line. Construction of

4661transmission lines on such established ROWs is excepted from the

4671definition of " development " in Section 163.3164(5), Fl orida

4679Statutes. Accordingly, the provisions of the local

4686c omprehensive p lans related to " development " that have been

4696adopted by the local governments crossed by the SJPP Line are

4707not applicable to this project .

471362. To the extent the c omprehensive p lans of the local

4725governments crossed by the SJPP Line include provisions

4733applicable to non - development activities , the proposed

4741transmission line in the FPL Corridor wo uld be consistent with

4752them.

475363. The City of Palm Coast Comprehens ive Plan is

4763essentially silent on transmission lines as a land use, which is

4774consistent with such lines being excepted from the definition of

" 4784development " regulated by the Plan.

478964. Policy A.1.8.3 of the St. Johns County Comprehensive

4798Plan provides that " future utility facilities shall be located

4807to promote the efficient provision of services , minimize the

4816cost of construction and maintenance, and minimize the impact on

4826the natural environment. " Because of the thoroughness of the

4835corridor selection proc ess and criteria, and the appropriateness

4844of the corridor from a land use perspective, the proposed SJPP

4855L ine is consistent with that policy.

486265. No variances or exemptions from applicable state or

4871local standards or ordinances are needed for the project .

4881E. Implementation of Legislative Intent in Section 40 3.521

4890a . The Need for the SJPP Line as a Means of Providing

4903Abundant Low - Cost Electrical Energy

490966. The PSC determined that the SJPP Line is needed taking

4920into account the factors set forth i n Section 403.537, Florida

4931Statutes.

493267. In the need proceeding, the PSC considered two

4941alternatives, including transmission modifications to the

4947existing 115 - kV system. The PSC accepted FPL ' s rejection of the

4961two alternatives " due to economics and conc erns with the ability

4972to serve additional future customers west of the I - 95/US - 1

4985corridor. " The PSC found that the proposed transmission line

4994would " assure the economic well - being of the citizens of the

5006state by serving projected new electric load in the region, and

5017improving the region ' s electric reliability by minimizing the

5027region ' s exposure to single contingency events. "

503568. The PSC has determined that the estimated cost of the

5046Project is reasonable, and that the SJPP Line will assure the

5057economic we ll - being of the citizens of the state by serving

5070projected new electric load in the region and improving the

5080region ' s electric reliability by minimizing the region ' s

5091exposure to single contingency events.

5096b. Impact Upon the Public

510169. The SJPP Line is appropriate from a land use

5111perspective because this type of transmission line currently

5119exists in all types of land uses in Florida, including

5129residential, commercial, industrial, agricultural, and vacant

5135land. The SJPP Line takes advantage of the opport unity to be

5147collocated with other transmission lines, roadways, and railroad

5155ROWs for almost the entire distance. By following these

5164existing linear features, the FPL Corridor conforms to existing

5173and future development patterns, and minimizes intrusion i nto

5182residential areas and conservation lands. As a result, the

5191proposed SJPP Line is in proximity to relatively few residences

5201and only one crossing of lands either purchased or proposed for

5212purchase under federal, state , or local land acquisition

5220program s. Further, by collocating with other public and utility

5230ROWs, the amount of land that will be required for the SJPP line

5243is less than if it were not collocated.

525170. The FPL Corridor minimizes impacts to existing homes

5260by following a route where there i s very little residential

5271development and where planned residential development is very

5279low density.

52817 1. T he SJPP Line as proposed will comply with all

5293applicable non - procedural standards, including the noise

5301ordinances of St. Johns County and the C ity of Palm Coast, and

5314the standards adopted by the Department limiting the electric

5323and magnetic fields associated with transmission lines .

5331c. Impact Upon the Environment

533672. The SJPP Line Project as proposed will have minimal

5346environmental impact.

534873. Co nstruction of the SJPP Line within t he FPL Corridor

5360will not adversely affect the conservation of fish and wildlife,

5370including endangered or threatened species, or their habitats.

5378The FPL Corridor avoids or minimizes intrusion into the

5387undisturbed wildlif e habitats due to its collocation with

5396existing linear facilities for almost its entire length. The

5405current condition and relative value of function of the habitat

5415in the FPL Corridor is minimal from a wildlife ecology and

5426protected species perspective. Great care was taken in routing

5435the FPL Corridor to avoid or minimize proximity of the corridor

5446to known listed species locations, including routing inputs from

5455wildlife agencies such as the F lorida Fish and Wildlife

5465Conservation Commission (F F WCC ) and the U.S. Fish and Wildlife

5477Service. Further, due to the presence of existing linear

5486features along much of the route, clearing of additional natural

5496habitats and potential wetland impacts will be minimized.

550474. Construction of the SJPP Line within t he FPL Corridor

5515will not cause a significant adverse impact to the current

5525condition and relative value of functions of the vegetative

5534communities within the FPL Corridor. First, nearly the entire

5543length of the FPL Corridor allows placement of the transmission

5553l ine within or adjacent to existing linear features to take

5564advantage of previous disturbances to vegetation . FPL will also

5574minimize impacts to forested wetland vegetation through the use

5583of restrictive clearing practices during both construction and

5591maint enance. In the forested wetland portions of the ROW , FPL

5602will only take out trees and shrubs that have an expected mature

5614height greater than 14 feet and " danger trees, " which are trees

5625that could fall into the conductors and cause an outage. In

5636these ar eas, vegetation will be removed by hand, usually with

5647chain saws, or with low - ground - pressure shear or rotary machines

5660to reduce soil compaction and damage to ground cover. The

5670removal of vegetation in forested wetlands will not affect the

5680vegetative root mat or soil surface conditions. The non -

5690forested wetlands should not require any clearing.

569775. There will be some filling in wetlands associated with

5707the placement of pole pads and access roads. However, FPL will

5718minimiz e impacts on wetlands vegetatio n through a careful

5728alignment of the ROW and the varying of span distances between

5739poles. FPL will also install an appropriate number and size of

5750culverts to properly maintain existing wetland hydroperiods

5757along areas of fill in wetlands. Also, any unavo idable wetland

5768impacts associated with the project will be mitigated in

5777accordance with the Conditions of Certification.

578376. FPL has agreed to avoid the removal of listed plant

5794species on public lands and waters, wherever practicable. When

5803removal is ne cessary on public lands/waters, FPL will consult

5813with the Department , F F WCC, and the Department of Agriculture

5824and Consumer Services to determine the appropriate steps to

5833minimize, mitigate , or otherwise appropriately address potential

5840project related impa cts to listed plant species. FPL ' s

5851commitment to avoid, minimize and/or mitigate potential impacts

5859to listed plant species within public lands and waters will

5869promote the conservation of endangered and threatened plant

5877species populations and their habita ts.

588377. The SJPP Line Project will comply with all applicable

5893state, regional , and local non - procedural regulations, including

5902the wetland regulatory standards applicable to such projects.

5910d . Balance of Need versus Impacts

591778. The SJPP Line would effe ct a reasonable balance

5927between the need for a transmission line as a means for

5938providing abundant low cost energy and the impact upon the

5948public and the environment resulting from the location of the

5958transmission line corridor and the construction and mai ntenance

5967of the transmission line.

5971VI. C onditions of Certification

597679. The design, construction , and operation of the SJPP

5985L ine as proposed in the FPL Corridor will comply with the

5997conditions of certification set forth in Department Exhibit 1.

600680. T he conditions of certification establish a post -

6016certification review process through which the final right - of -

6027way, access road , and structure locations will be reviewed by

6037agencies with regulatory authority over the project for the

6046purpose of monitoring fo r compliance with the conditions of

6056certification .

605881. While the FPL Corridor has few homes in close

6068proximity to it and very limited wetland crossings, FPL has

6078agreed to conditions of certification that further minimize land

6087use and environmental impact s. For example, FPL has agreed that

6098to the extent practicable it will locate its ROW to avoid the

6110taking of homes, to collocate the ROW within or adjacent to

6121existing ROWs, and to vary the length of the span between poles

6133as appropriate to eliminate or re duce wetland impacts.

6142CONCLUSIONS OF LAW

614582. The Division of Administrative Hearings has

6152jurisdiction over the parties to, and the subject matter of,

6162this proceeding. § § 120.569 and 403.527(2), Fla. Stat.

617183. This certification proceeding was held pur suant to the

6181Transmission Line Siting Act, Sections 403.52 through 403.5365,

6189Florida Statutes, and Florida Administrative Code Chapter 62 - 17,

6199Part II. The intent of this licensing process is:

6208to fully balance the need for the

6215transmission lines with the b road interests

6222of the public in order to effect a

6230reasonable balance between the need for the

6237facility as a means of providing abundant

6244low - cost electrical energy and the impact on

6253the public and the environment resulting

6259from the location of the transmiss ion line

6267corridor and the construction and

6272maintenance of the transmission lines.

6277§ 403.521, Fla. Stat. To implement this intent, the Legislature

6287has set forth specific requirements for the PSC to determine the

6298need for the proposed transmission line and address other

6307matters within its jurisdiction, for other various agencies to

6316prepare reports and studies regarding matters within their

6324jurisdiction, for publication of notice of the application and

6333certification proceeding, for third parties to have an

6341o pportunity to offer alternate corridor routes for

6349consideration, and for criteria to be considered in determining

6358whether an application should be approved in whole, approved

6367with modification or conditions, or denied. See §§ 403.526,

6376403.527, 403.5271, a nd 403.529, Fla. Stat.

638384. All parties identified in Finding of Fact No. 1 have

6394standing in this proceeding.

639885. FPL has the burden of proving that , under the criteria

6409of Section 403.529(4), Florida Statutes, the FPL Corridor for

6418the SJPP Line should be certified as proposed based upon a

6429preponderance of the evidence presented at the certification

6437hearing. See , e.g. , F la. Dept. of Transp. v . J.W.C Co., Inc. ,

6450396 So. 2d 778, 788 (Fla. 1 st DCA 1981).

646086. The evidence in the record of this proceeding

6469d emonstrates compliance with the procedural requirements of the

6478TLSA, including the notice requirements for the certification

6486and public hearings.

648987. In deciding whether FPL ' s Application for Corridor

6499Certification should be approved, approved with condi tions, or

6508denied, the Siting Board must determine whether, and the extent

6518to which, the location of the corridor and the construction and

6529maintenance of the transmission line in the corridor will:

6538(a) Ensure electric power system

6543reliability and integrity ;

6546(b) Meet the electrical energy needs

6552of the state in an orderly and timely

6560fashion;

6561(c) Comply with nonprocedural

6565requirements of agencies;

6568(d) Be consistent with applicable

6573local government comprehensive plans; and

6578(e) Effect a reasonable balanc e

6584between the need for the transmission line

6591as a means of providing abundant low - cost

6600electrical energy and the impact upon the

6607public and the environment resulting from

6613the location of the transmission line

6619corridor and the maintenance of the

6625transmissio n lines.

6628§ 403.529(4), Fla. Stat.

663288. Compliance with Section 403.529(4)(a), Florida

6638Statutes . The PSC determined the need for a new 230 - kV

6651transmission line between the St. Johns River and Pringle

6660substations in Order No. PSC - 05 - 0527 - FOF - EI, issued on May 13,

66772005 . Among other things, t he PSC found that construction of

6689the proposed SJPP L ine would " improve the region ' s electric

6701reliability by minimizing the region ' s exposur e to single

6712contingency events." The PSC also found that if FPL does not

6723add th is new transmission capability by 2008, up to 8,300

6735electric customers could be subject to service interruptions.

6743Th e s e finding s of the PSC address the extent to which the

6758reliability, integrity , and service restoration of the electric

6766system will be enh a nced. Th e PSC ' s determination of need for

6781the SJPP Line Project is binding upon all parties to the

6792certification proceeding. § 403.537(1)(c), Fla. Stat. By

6799submitting the PSC Order Determining Need into the record, FPL

6809made a prima facie showing that th e FPL C orridor would enhance

6822electric system reliability, integrity , and restoration of

6829service. The PSC found that the FPL Corridor meets the

6839criterion of Section 403.529(a), Florida Statutes .

684689. Compliance with Section 403.529(4)(b), Florida

6852Statutes . The PSC acknowledged in its O rder D etermining N eed

6865for the SJPP Line that FPL ' s planning studies indicate the

6877proposed transmission line needs t o be in service by December

68882008 to alleviate potential overloads and low voltage conditions

6897from a single co ntingency event. Evidence regarding the design

6907of the transmission line, the construction phases for the

6916transmission line, including the projected 13 - month construction

6925schedule, and the proposed location of the SJPP Line

6934demonstrates that the SJPP Line will meet the electrical needs

6944of the state in an orderly and timely fashion within the time

6956frames established by the PSC.

696190. Compliance with Section 403.529(4)(c), Florida

6967Statutes . The location of the SJPP Line in the FPL Corridor and

6980the construct ion and maintenance of that SJPP Line in

6990conformance with the recommended Conditions of Certification

6997contained in Department Exhibit 1 will comply appropriately with

7006the non - procedural requirements of all agencies.

701491. Compliance with Section 403.529(4 )(d), Florida

7021Statutes . There are no inconsistencies between the proposed

7030SJPP Line project and the local government comprehensive plans

7039adopted by local governments whose jurisdictions are crossed by

7048the SJPP Line .

705292. Compliance with Section 403.529( 4)(e), Florida

7059Statutes . The location of the FPL Corridor and the

7069construction , operation , and maintenance of the SJPP Line in

7078that corridor provide a reasonable balance between the need for

7088the transmission line and the impact of the transmission line

7098up on the public and the environment. The impact upon the public

7110and the environment will be minimized by the SJPP Line ' s

7122collocation with existing linear facilities for nearly its

7130entire length. Furthermore, the impact from clearing activities

7138and any othe r construction and operation activities associated

7147with the SJPP Line will be minimal, particularly when balanced

7157with the significant electrical energy requirements that will be

7166satisfied by the construction and operation of the SJPP

7175transmission line in the FPL Corridor.

718193. Based upon a preponderance of the evidence presented

7190at the certification hearing, FPL has met its burden of proving

7201that the SJPP Line and related facilities should be certified as

7212proposed , subject to the Conditions of Certificati on included in

7222Department Exhibit 1.

7225RECOMMENDATION

7226Based upon the foregoing Findings of Fact and Conclusions

7235of Law, it is

7239RECOMMENDED that the Siting Board enter a Final Order

7248approving FPL ' s St. Johns - Pellicer - Pringle 230 - kV Transmission

7262Line Applicat ion for Certification subject to the Conditions of

7272Certification set forth in Department Exhibit 1.

7279DONE AND ENTERED this 6th day of March, 2006, in

7289Tallahassee, Leon County, Florida.

7293S

7294DONALD R. ALEXANDER

7297Administrativ e Law Judge

7301Division of Administrative Hearings

7305The DeSoto Building

73081230 Apalachee Parkway

7311Tallahassee, Florida 32399 - 3060

7316(850) 488 - 9675 SUNCOM 278 - 9675

7324Fax Filing (850) 921 - 6847

7330www.doah.state.fl.us

7331Filed with the Clerk of the

7337Division of Administrat ive Hearings

7342this 6th day of March, 2006.

7348END NOTE

73501/ All subsequent references are to the 2005 version of the

7361Florida Statutes.

7363COPIES FURNISHED:

7365Lea Crand a ll, Agency Clerk

7371Department of Environmental Protection

73753900 Commonwea l th Boulevard

7380Mail St ation 35

7384Tallahassee, Florida 32399 - 3000

7389Gregory M. Munson, General Counsel

7394Department of Environmental Protection

73983900 Commonwealth Boulevard

7401Mail Station 35

7404Tallahassee, Florida 32399 - 3000

7409Carolyn S. Raepple, Esquire

7413Hopping Green & Sams, P.A.

7418Post O ffice Box 6526

7423Tallahassee, Florida 32314 - 6526

7428Scott A. Goorland, Esquire

7432Department of Environmental Protection

74363900 Commonwealth Boulevard

7439Mail Station 35

7442Tallahassee, Florida 32399 - 3000

7447Kelly A. Martinson, Esquire

7451Department of Community Affairs

7455255 5 Shumard Oak Boulevard

7460Tallahassee, Florida 32399 - 2100

7465Michael D. Hunt, Esquire

7469Deputy County Attorney

74724020 Lewis Speedway, Suite 1120

7477St. Augustine, Florida 32084 - 8637

7483Veronika Thiebach, Esquire

7486St. Johns River Water Management District

74924049 Reid Str eet

7496Palatka, Florida 32177 - 2529

7501Lonnie N. Groot, Esquire

7505Stenstrom, McIntosh, Colbert

7508200 West First Street, Suite 22

7514Sanford, Florida 32771 - 1268

7519Seauching Yu, Esquire

7522Department of Transportation

7525605 Suwannee Street

7528Mail Station 58

7531Tallahassee, Flori da 32399 - 0458

7537James V. Antista, General Counsel

7542Florida Fish and Wildlife

7546Conservation Commission

7548620 South Meridian Street

7552Tallahassee, Florida 32399 - 1600

7557Brian D. Teeple, Executive Director

7562Northeast Florida Regional Planning Council

75676850 Belfort Oaks Place

7571Jacksonville, Florida 32216 - 6241

7576Carl E. Kern, III, Esquire

7581Flagler County Attorney

75841200 East Moody Boulevard, Suite 11

7590Bunnell, Florida 32110 - 5919

7595Martha Carter Brown, Esquire

7599Office of the General Counsel

7604Florida Public Service Commission

76082540 Shumard Oak Boulevard

7612Tallahassee, Florida 32399 - 0850

7617Heidi M. Hughes, General Counsel

7622D epartment of Community Affairs

76272470 Centerview Drive

7630Tallahassee, Florida 32399 - 2100

7635NOTICE OF RIGHT TO FILE EXCEPTIONS

7641All parties have the right to submit written exceptions within

765115 days of the date of this Recommended Order. Any exceptions

7662to this Recommended Order should be filed with the agency that

7673will render a final order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 05/01/2006
Proceedings: Letter to FP&L from S. Goorland enclosing Conditions of Certification that were incorporated by reference in the Final Order Approving Certification of Transmission Line for FP&L St. Johns-Pellicer-Pringer, 230KV Project filed.
PDF:
Date: 04/28/2006
Proceedings: Final Order Approving Certification of Transmission Line filed.
PDF:
Date: 04/27/2006
Proceedings: Agency Final Order
PDF:
Date: 03/06/2006
Proceedings: Recommended Order
PDF:
Date: 03/06/2006
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 03/06/2006
Proceedings: Recommended Order (hearing held January 10, 2006). CASE CLOSED.
PDF:
Date: 02/16/2006
Proceedings: Proposed Recommended Order filed.
PDF:
Date: 02/16/2006
Proceedings: Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 01/20/2006
Proceedings: Notice of Filing of Late-filed FPL Exhibit 3.
Date: 01/18/2006
Proceedings: Transcript of Proceedings filed.
PDF:
Date: 01/18/2006
Proceedings: Notice of Filing Transcript of Certification Hearing filed.
Date: 01/10/2006
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 01/05/2006
Proceedings: Notice of Filing Corrected Second Page to Stipulation between Florida Power and Light Company and Department of Environmental Regulation filed.
PDF:
Date: 01/04/2006
Proceedings: Joint Stipulation of FPL and St. Johns River Water Management District Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
PDF:
Date: 01/03/2006
Proceedings: Joint Stipulation of FPL and City of Palm Coast Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
PDF:
Date: 12/29/2005
Proceedings: Department of Environmental Protection`s Notice of Filing of Revised Written Analysis filed.
PDF:
Date: 12/29/2005
Proceedings: Joint Stipulation of FPL and Department of Environmental Protection Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
PDF:
Date: 12/22/2005
Proceedings: Joint Stipulation of FPL and Department of Community Affairs Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
PDF:
Date: 12/20/2005
Proceedings: Joint Stipulation of FPL and Department of Transportation Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
PDF:
Date: 12/19/2005
Proceedings: Joint Stipulation of FPL and St. Johns County Regarding Recommended Conditions of Certification and Admission into Evidence of Written Testimony and Exhibits of FPL Witnesses filed.
PDF:
Date: 12/19/2005
Proceedings: Amended Order Amending Schedule of Procceedings (deadline for the filing of written direct testimony of witnesses and exhibits shall be no later than fifteen days before the scheduled final hearing, or by Tuesday, December 27, 2005)..
PDF:
Date: 12/16/2005
Proceedings: Order Amending Schedule of Proceedings (deadline for the filing of written direct testimony of witnesses and exhibits shall be no later than fifteen days before the scheduled final hearing, or by Tuesday, December 27, 2005) .
PDF:
Date: 12/16/2005
Proceedings: Notice of Filing Written Direct Testimony and Exhibits filed.
PDF:
Date: 12/13/2005
Proceedings: Motion to Amend Schedule of Proceedings filed.
PDF:
Date: 12/09/2005
Proceedings: Summary and Compilation of Agency Reports including Proposed Conditions of Certification for Florida Power and Light Company`s St. Johns-Pellicer-Pringle 230 KV Transmission Line Project filed.
PDF:
Date: 12/09/2005
Proceedings: Department of Environmental Protection`s Notice of Filing of Written Analysis filed.
PDF:
Date: 10/11/2005
Proceedings: St. Johns River Water Management District`s Notice of Intent to be a Party filed.
PDF:
Date: 09/12/2005
Proceedings: Determination of Sufficiency filed.
PDF:
Date: 08/18/2005
Proceedings: Department of Transportation`s Notice of Intent to be a Party filed.
PDF:
Date: 08/11/2005
Proceedings: Notice of The City of Palm Coast`s Notice of Intent to be a Party filed.
PDF:
Date: 08/05/2005
Proceedings: Notice of St. Johns County`s Notice of Intent to be a Party filed.
PDF:
Date: 07/29/2005
Proceedings: Notice of Hearing (hearing set for January 10 through 13, 2006; 9:00 a.m.; St. Augustine, FL).
PDF:
Date: 07/28/2005
Proceedings: Department of Community Affairs` Notice of Intent to be a Party filed.
PDF:
Date: 07/27/2005
Proceedings: Undeliverable envelope returned from the Post Office.
PDF:
Date: 07/22/2005
Proceedings: Department of Environmental Protection`s Proposed Schedule of Significant Dates and Stipulation for Alteration of Time Frames filed.
PDF:
Date: 07/20/2005
Proceedings: Motion for Alteration of Caption filed.
PDF:
Date: 07/20/2005
Proceedings: Determination of Completeness filed.
PDF:
Date: 07/19/2005
Proceedings: Response to the Initial Order filed.
PDF:
Date: 07/18/2005
Proceedings: St. Johns-Pellicer-Pringle Transmission Line Project Application filed.
PDF:
Date: 07/18/2005
Proceedings: Filing of Transmission Line Certification Application filed.
PDF:
Date: 07/15/2005
Proceedings: Notice of Appearance (filed by C. Raepple).
PDF:
Date: 07/12/2005
Proceedings: Filing of List of Affected Agencies filed.
PDF:
Date: 07/12/2005
Proceedings: Notice of Receipt of Transmission Line Siting Application and Request for Assignment of Administrative Law Judge filed.
PDF:
Date: 07/12/2005
Proceedings: Initial Order.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
07/12/2005
Last Docket Entry:
05/01/2006
Location:
St. Augustine, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
TL
 

Counsels

Related Florida Statute(s) (11):