05-002982 Michael D`ordine And Ann E. Hawkins vs. Department Of Environmental Protection And Palm Beach County Water Utilities Department
 Status: Closed
Recommended Order on Tuesday, October 18, 2005.


View Dockets  
Summary: Palm Beach County`s application for a domestic wastewater collection/transmission system to serve the Scripps Project is approved; the pipe material used met technical specifications.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8TROY AND TRACEY LEE; JOSEPH )

14ACQUAOTTA AND LISA GABLER; )

19ANTHONY AND VERONICA DALY; )

24MICHAEL D'ORDINE AND ANN E. )

30HAWKINS; LISA LANDER; and )

35INDIAN TRAIL IMPROVEMENT )

39DISTRICT, )

41)

42Petitioners, ) Case Nos. 05 - 2979

49) 05 - 2980

53vs. ) 05 - 2981

58) 05 - 2982

62PALM BEACH COUNTY and ) 05 - 2983

70DEPARTMENT OF ENVIRONMENTAL ) 05 - 2984

77PROTECTION, )

79)

80Respondents. )

82____________ ____________________)

84RECOMMENDED ORDER

86Pursuant to notice, these matters were heard before the

95Division of Administrative Hearings by its assigned

102Administrative Law Judge, Donald R. Alexander, on September

11013, 14, and 15, 2005, in West Palm Beach, Flo rida.

121APPEARANCES

122For Petitioners: Michael D'Ordine

126(Case No. 05 - 2982) Ann E. Hawkins

1344474 140th Avenue North

138Royal Palm Beach, Florida 33411 - 8464

145For Petitioner: Lisa Lander

149(Case No. 05 - 2983) 13881 40th Street North

158Royal Palm Beach, Florida 33411 - 8491

165For Petitioner: Anthony D. Lehman, Esquire

171(Case No. 05 - 2984) Hunton & Williams, LLP

180Bank of America Plaza, Suite 4100

186600 Peachtree Street, Northeast

190Atlanta, Georgia 30308 - 2216

195William D. Preston, Esquire

199William D. Preston, P.A.

2034832 - A Kerry Forrest Parkway

209Tallahassee, Florida 32308 - 2272

214For Respondent: Francine M. Ffolkes, Esquire

220(Department) Justin G. Wolfe, Esquire

225Department of Environmental Protect ion

2303900 Commonwealth Boulevard

233Mail Station 35

236Tallahassee, Florida 32399 - 3000

241For Respondent: Edward P. de la Parte, Jr., Esquire

250(County) de la Parte & Gilb ert, P.A.

258Post Office Box 2350

262Tampa, Florida 33601 - 2350

267Amy Taylor Petrick, Esquire

271Palm Beach County Attorney's Office

276301 North Oli ve Avenue, Suite 601

283West Palm Beach, Florida 33401 - 4705

290STATEMENT OF THE ISSUE

294The issue is whether Palm Beach County's application for

303a permit to construct a domestic wastewater

310collection/transmission system in Palm Beach Cou nty should be

319approved.

320PRELIMINARY STATEMENT

322On May 12, 2005, Respondent, Department of Environmental

330Protection (Department), issued its Notice of Permit Issuance

338(Notice), which proposed to issue Permit No. 0048923 - 017 - DWC

350(Permit) to Respondent, Palm B each County (County),

358authorizing the construction of a domestic wastewater

365collection/transmission system. The Permit allows the

371construction of a wastewater collection and transmission

378system to serve the Palm Beach County Research Village

387(Village), wh ich will be home of the Scripps Florida

397Biomedical Research Institution and Campus (Scripps Project)

404in an unincorporated area of the County.

411On August 15, 2005, Petitioners, Troy and Tracey Lee,

420Joseph Acquaotta and Lisa Gabler, Anthony and Veronica Dal y,

430Michael D'Ordine and Ann E. Hawkins, and Lisa Lander, who

440reside in the area where the transmission line will be

450constructed, filed with the Department five identical,

457untitled papers challenging the proposed agency action. These

465papers were treated as formal petitions and were forwarded by

475the Department to the Division of Administrative Hearings

483(DOAH) on August 18, 2005, with a request that an

493administrative law judge be assigned to conduct a hearing.

502The Petitions have been assigned DOAH Case Nos. 05 - 2979

513through 05 - 2983. On August 15, 2005, Petitioner, Indian Trail

524Improvement District (ITID), also filed with the Department a

533Petition for Formal Administrative Hearing (Petition)

539challenging the same proposed agency action. That Petition

547was forwa rded to DOAH on August 18, 2005, and has been

559assigned DOAH Case No. 05 - 2984. By Order dated August 23,

5712005, all cases were consolidated.

576On August 22, 2005, the Department filed a Motion for

586Summary Hearing Pursuant to Section 403.973(15)(b), F.S.

593(Mo tion). The Motion was later joined in by the County. That

605statute requires in part that "summary proceedings must be

614conducted within 30 days after a party files the motion for

625summary hearing, regardless of whether the parties agree to

634the summary proce eding." Because the project qualifies for an

644expedited hearing, the Motion was granted and the cases were

654scheduled for a final hearing on September 13 - 15, 2005, in

666West Palm Beach, Florida.

670At the beginning of the final hearing, the undersigned

679granted the Department's and County's ore tenus motion in

688limine to exclude the introduction of evidence regarding

696certain real estate disputes between ITID and the County on

706the ground that those disputes should be adjudicated by the

716circuit court.

718At the final hearing, the Department presented the

726testimony of Robert E. Heilman, a professional engineer,

734Pretreatment Coordinator, and accepted as an expert; Timothy

742W. Powell, a professional engineer, Wastewater Permitting

749Supervisor, and accepted as an expert; and Michael W.

758Bechtold, a professional engineer, Senior Permitter, and

765accepted as an expert. Also, it offered Department Exhibits

7741 - 3, and 7, which were received in evidence. The County

786presented the testimony of Robert Walker, a professional

794engineer, Ex ecutive Director of UniBell PVC Pipe Association,

803and accepted as an expert; Brian A. Shields, a professional

813engineer, Director of Engineering of the Water Utilities

821Department, and accepted as an expert; Leisha Pica, a

830professional engineer, Deputy Direc tor of the Water Utilities

839Department, and accepted as an expert; and Bevin A. Beaudet, a

850professional engineer, director of the Water Utilities

857Department, and accepted as an expert. Also, it offered

866County Exhibits 1 - 21, 23, 36, 39, 92, 93, 107, 122, 12 4 - 127,

882129, 142 - 145, 151A and B, 152, and 153, which were received in

896evidence.

897Petitioners in Case Nos. 05 - 2979 and 05 - 2981 did not

910appear at the final hearing. One of the Petitioners in Case

921No. 05 - 2980, Joseph Acquaotta (but not Lisa Gabler, who also

933signed the Petition), appeared as a witness on the final day

944of the hearing. Petitioners in Case No. 05 - 2982, Michael

955D'Ordine and Ann E. Hawkins, testified on their own behalf.

965Petitioner in Case No. 05 - 2983, Lisa Lander, testified on her

977own behalf an d presented the testimony of Alexandria Larson,

987who resides in the area. Also, she offered Lander Exhibits 1,

9982, 3A - W, and 4 - 6, which were received in evidence.

1011ITID presented the testimony of Christopher Karch, a

1019professional engineer and vice - presiden t of its Board of

1030Supervisors; and David L. Farabee, a professional engineer and

1039accepted as an expert. Also, it offered ITID Exhibits 1 and

10502, which were received in evidence.

1056Finally, official recognition has been taken of the

1064following matters: a co py of an Order denying ITID's Renewed

1075Motion for Temporary Injunction in Case No.

1082502005CA000965XXXXMB, Indian Trail Improvement District v.

1088Palm Beach County (Cir. Ct., 15th Jud. Cir.); the Recommended

1098and Final Orders issued in DOAH Case No. 04 - 4492GM; t he

1111Recommended Order issued in DOAH Case Nos. 04 - 4336GM, 04 -

11234337GM, and 04 - 4650GM; and the Recommended Standards for

1133Wastewater Facilities (1997 Edition), more commonly referred

1140to as the Ten State Standards.

1146The Transcript of the hearing (five volumes) was filed on

1156September 19, 2005. By agreement of the parties, proposed

1165findings of fact and conclusions of law were due on September

117629, 2005. Filings were timely made by Lander and D'Ordine

1186(jointly), ITID, the County, and the Department, and they have

1196been considered by the undersigned in the preparation of this

1206Recommended Order.

1208FINDINGS OF FACT

1211Based upon all of the evidence, the following findings of

1221fact are determined:

1224A. Parties

12261. The County is a political subdivision of the State of

1237Flori da and is the permittee in this matter. The County Water

1249Utilities Department currently serves approximately 425,000

1256persons, making it the largest utility provider in Palm Beach

1266County and the third largest in the State of Florida.

12762. ITID is an indep endent water control special district

1286created by special act of the legislature in 1957 and whose

1297boundaries lie within the County. Portions of the

1305transmission line to be constructed by the County will cross

1315easements and roads, and pass under canals, ow ned by ITID.

13263. Petitioners Joseph Acqualotta, Michael D'Ordine, Ann

1333E. Hawkins, and Lisa Lander all live in areas in close

1344proximity to the proposed transmission line. Lander lives

1352adjacent to the proposed route of the line along 40th Street

1363North, whil e Acqualotta, D'Ordine, and Hawkins live adjacent

1372to the proposed route along 140th Avenue North. Acqualotta,

1381Hawkins (but not D'Ordine, who resides with Hawkins), and

1390Lander own the property where they reside. Petitioners Troy

1399and Tracey Lee (Case No. 0 5 - 2979), Lisa Gabler (Case No. 05 -

14142980), and Anthony and Veronica Daly (Case No. 05 - 2982) did

1426not appear at the final hearing.

14324. The Department is an agency of the State of Florida

1443authorized to administer the provisions of Part I of Chapter

1453403, Florida Statutes, and is the state agency charged with

1463the responsibility of issuing domestic wastewater collection/

1470transmission permits under Section 403.087, Florida Statutes

1477(2004) . 1

1480B. Background

14825. On December 15, 2004, the County filed its

1491application wi th the Department for an individual permit to

1501construct a domestic wastewater collection/transmission system

1507(Transmission Line). The Transmission Line is one element of

1516the County's Northern Region Utilities Improvement Project

1523(Project) and will be appr oximately 41,050 feet long and

1534comprised of approximately 32,350 linear feet of 20 - inch force

1546main and 18,700 linear feet of 30 - inch force main (or nearly

1560ten miles in length).

15646. A primary purpose of the Project is to provide water

1575and wastewater servi ce to the Village, a 1,900 acre parcel

1587located in the unincorporated part of the County several miles

1597west of the Florida Turnpike, south of State Road 710, and

1608north of the Villages of Wellington and Royal Palm Beach. The

1619Village will be the home of the Scripps Project and Campus.

1630The Transmission Line will run from the southeastern corner of

1640the Village south to Northlake Boulevard, then east to 140th

1650Avenue North, then south along that roadway to 40th Street

1660North, where it turns east until it intercon nects with

1670existing facilities.

16727. The wastewater will be collected in a regional pump

1682station on the Scripps Project site, where it will be pumped

1693through the Transmission Line to the East Central Plant, which

1703will be the primary treatment facility. The East Central

1712Plant is owned and operated by the City of West Palm Beach

1724(City), but the County owns between forty and forty - five

1735percent of the treatment capacity. Because the wastewater

1743system is interconnected, the wastewater could also be treated

1752at t he County's Southern Regional Plant. Ultimately, the flow

1762from the Scripps Project will be one or two million gallons

1773per day.

17758. The Transmission Line is the only way that wastewater

1785can be handled at the Scripps Project. A preliminary analysis

1795by th e Department and the South Florida Water Management

1805District determined that on - site treatment was not feasible

1815because of the environmentally sensitive nature of the area.

18249. The Scripps Project will include residential units,

1832commercial entities, and institutional uses, such as medical

1840clinics. Besides serving these customers, the Transmission

1847Line will also serve other customers in the area. The County

1858has already signed agreements with the Beeline Community

1866Development District (which lies a few mi les northwest of the

1877Village) and the Village of Royal Palm Beach (which lies

1887several miles south - southeast of the Village). At the time of

1899the hearing, the County anticipated that it would also sign an

1910agreement with Seacoast Utility Authority (whose ser vice area

1919is located just southeast of the Village) to transport

1928wastewater through the Transmission Line.

193310. All of the treatment facilities have sufficient

1941existing capacity to treat the estimated amount of domestic

1950wastewater that will be generated by the Scripps Project and

1960the other users that will discharge to the Line.

196911. The County commenced construction of the

1976Transmission Line in May 2005 when the Department issued the

1986Permit. On August 2, 2005, the County published the

1995Department's Notice to issue the Permit, and once the

2004Petitions were filed, the County stopped construction pending

2012the outcome of this hearing. Approximately seventy percent of

2021the Transmission Line is now completed. The Permit does not

2031allow the Transmission Line to be u sed until it is pressure

2043tested and certified complete. Upon completion, the County

2051must receive an Approval to Place a Domestic Wastewater

2060Collection/Transmission System into Operation from the

2066Department. Such approval is given only after the County ha s

2077given reasonable assurance that adequate transmission,

2083treatment, and disposal is available in accordance with

2091Department standards. See Fla. Admin. Code R. 62 - 604.700.

210112. On August 15, 2005, Petitions challenging the

2109issuance of the Permit were fil ed by ITID and the individual

2121Petitioners. ITID contends that the Transmission Line will

2129convey not only domestic wastewater, but also industrial

2137waste; that the County did not comply with all applicable

2147technical standards and criteria required under the

2154Department's rules; that the Project will be located on ITID's

2164right - of - way, on which the County has no right to occupy; that

2179the Project will be located within seventy - five feet from

2190private drinking wells and does not provide an equivalent

2199level of reli ability and public health protection; and that

2209the pipe material and pressure design is inappropriate for the

2219Transmission Line's requirements. The individual Petitioners

2225(who filed identical Petitions) are mainly concerned about the

2234location of the Trans mission Line in relation to their private

2245drinking wells and property, the possibility of the pipe

2254bursting or leaking once it becomes operational, and the

2263restoration of their property to its original condition after

2272construction is completed.

227513. As to the property claims by all Petitioners, the

2285County plans to place the Transmission Line in property that

2295it either owns or has an easement, in property that it is in

2308the process of condemning, or in a public right of way. While

2320the County acknowledges th at it has already placed, and

2330intends to place other portions of, the Transmission Line in

2340easements that ITID says it has the exclusive right to use and

2352for which a permit from ITID is required, the County alleges

2363that it also has the right to use those e asements without an

2376ITID permit. The dispute between the County and ITID is the

2387subject of a circuit court proceeding in Palm Beach County,

2397and neither the Department nor DOAH has the authority to

2407decide property interests.

2410C. Petitioners' Objections

2413a . Domestic wastewater and pretreatment

241914. The wastewater that will be generated by the Scripps

2429Project is considered domestic wastewater; it will not include

2438industrial wastewater. Waste that is industrial or non -

2447domestic must be pretreated to protect the wastewater plant,

2456collection system, and the health of system workers and the

2466general public.

246815. The Department administers a pretreatment program

2475through which it requires a public wastewater utility to

2484police the entities that discharge to their wastewater plants.

2493A central part of the pretreatment program is the local

2503ordinance that gives legal authority to the utility to permit,

2513inspect, and take enforcement action against industrial users

2521who are part of the pretreatment program. The utility files

2531an annual report with an industrial user survey, and the

2541Department periodically inspects and audits local pretreatment

2548programs to ensure they are being operated as intended. The

2558system is not failsafe but is designed to ensure that

2568potentially har mful wastes are rendered harmless before

2576discharge. For example, the utility has the authority to

2585immediately shut water off if a harmful discharge is

2594occurring.

259516. Both the County and the City have pretreatment

2604programs approved by the Department. T he City has an

2614ordinance that allows it to enforce the pretreatment standards

2623for all entities that discharge to its wastewater system. The

2633County Water Utilities Department has a written pretreatment

2641manual, and the County has zoning restrictions on the

2650discharge of harmful material to the wastewater system. It

2659has also entered into an interlocal agreement under which it

2669agrees to enforce the City ordinance. The County provides

2678wastewater treatment to industrial, educational, and medical

2685facilities, and it has never experienced a discharge from any

2695of these facilities that has caused adverse health or

2704environmental impacts. The County pretreatment program for

2711the Southern Regional Facility was approved in 1997. The City

2721pretreatment program for the Eas t Central Regional Facility

2730was approved in 1980.

273417. The Scripps Project must apply for a permit from the

2745County and provide a baseline monitoring report, data on its

2755flow, and information on the flow frequency and raw materials.

2765Medical waste from the Scripps Project will be pretreated to

2775render it safe before it is discharged into the Transmission

2785Line.

2786b. Transmission Line Design

279018. The Transmission Line was designed in accordance

2798with the technical standards and criteria for wastewater

2806transmis sion lines in Florida Administrative Code Rule 62 -

2816604.300(5). That rule incorporates by reference a set of

2825standards commonly known as the Ten State Standards, which

2834contain several of the standards used in the design of this

2845project. These standards are recommended, but are not

2853mandatory, and a professional engineer should exercise his or

2862her professional judgment in applying them in any particular

2871case.

287219. The Transmission Line also meets the design

2880standards promulgated by the America Water Works As sociation

2889(AWWA). Specifically, the County used the AWWA C - 905 design

2900standard for sizing the polyvinyl chloride, or PVC, pipe used

2910in the project. The County has received written certification

2919from the manufacturer that the PVC pipe meets the standards in

2930AWWA C - 905.

293420. The Transmission Line is designed with stub - outs,

2944which will allow for future connections without an

2952interruption of service, and inline isolation valves, which

2960allow the line to be shut down for maintenance.

2969c. The Use of PVC Pipe

297521. There is no standard regulating the selection of PVC

2985pipe material in the Department's rules. Instead, the

2993Department relies on the certification of the applicant and

3002the engineer's seal that the force main will be constructed to

3013accepted engineering standards. The only specification

3019applicable to the Transmission Line is the Ten State Standard,

3029adopted and incorporated by reference in Florida

3036Administrative Code Rule 62 - 604.300(5)(g). That document

3044contains a general requirement that the material se lected have

3054a pressure rating sufficient to handle anticipated pressures

3062in wastewater transmission lines.

306622. The Transmission Line will be constructed with PVC

3075piping with a thickness of Dimension Ratio (DR) 32.5, which is

3086the ratio of the outside dia meter of the pipe to its

3098thickness. Higher ratios mean thinner - walled pipes. This is

3108not the first time the County has used 32.5 PVC piping for one

3121of its projects, and other local governments in the State have

3132used 32.5 or thinner pipe. The County is t ypically

3142conservative in requiring thicker - walled pipe, because most

3151transmission lines are built by developers, and the County is

3161unable to design the entire line or control or inspect its

3172installation. The specifications for wastewater transmission

3178line s built in the County call for the use of DR 25 pipe. On

3193this project, however, the County determined that thicker -

3202walled pipe would have been an over - design of the system

3214because the County controls the pump stations and oversees the

3224installation; theref ore, the Director of the Water Utilities

3233Department has waived that requirement.

323823. The County considers the use of DR 32.5 PVC to be

3250conservative. Although this pipe will be thinner than what is

3260typically used in the County, it satisfies the Departmen t's

3270requirements. The Department has permitted many miles of

3278similar PVC force mains in South Florida, and none have

3288failed.

328924. PVC has benefits over other transmission line

3297material, such as ductile iron. For example, PVC is more

3307corrosion resistant. Wastewater generates hydrogen sulfide as

3314it decomposes, which can form highly corrosive sulfuric acid.

3323Some of the older transmission lines in the County that were

3334made of ductile iron have corroded. PVC also has a superior

3345ability to absorb surges, su ch as cyclical surges, than

3355ductile iron. It is easier to install, and its interior flow

3366characteristics are smoother than ductile iron or pre - stressed

3376concrete pipe.

337825. Mr. Farabee, a professional engineer who testified

3386on behalf of ITID, recommended a DR 14 pipe, which is thicker -

3399walled than the DR 32.5 pipe used by the County. While he

3411opined that the DR 32.5 pipe was too thin for the project, he

3424could not definitively state that it would not pass the 150

3435per square inch (psi) pressure test. He als o opined that the

3447pipe is undersized because it will be unable to withstand the

3458surge pressures during cleaning. The witness further

3465testified that the pipe would be subject to much higher

3475pressures than 150 psi, and therefore it was impossible to

3485know wh ether the pipe would fail. In his opinion, this means

3497the Department did not have reasonable assurance for the

3506project.

350726. The County consulted with the Unibell PVC Pipe

3516Association (Unibell) in the planning of this project.

3524Unibell is a trade associa tion that provides technical support

3534for PVC pipe manufacturers. Robert Walker, a registered

3542professional engineer and Unibell's executive director who

3549testified on behalf of the County, disagreed with Mr.

3558Farabee's conclusions concerning the adequacy of the PVC pipe

3567in this project. The AWWA C - 905 standard uses a safety factor

3580of two, which means the pipes are tested at pressures that are

3592at least twice their stated design strength.

359927. Mr. Walker explained the different standards that

3607apply to PVC pi pe. DR 32.5 pipe, which is used in this

3620project, has a minimum interior pressure rating of 125 pounds

3630per square psi. Each pipe section is tested before it is

3641shipped at 250 psi, and the minimum burst pressure for the

3652material is in excess of 400 psi. T he pipe also meets a 1000 -

3667hour test at 270 psi. In light of these standards and

3678testing, the pipe will pass the two - hour 150 psi test required

3691by the Department.

369428. Mr. Farabee expressed some concern that the PVC pipe

3704would be more prone to breakage t han ductile iron or thicker

3716PVC. However, the PVC pipe standards provide that the pipe

3726can be flattened at sixty percent without splitting, cracking,

3735or breaking. At shallow depths on dirt roads, ovalation,

3744which occurs when PVC is flattened through pres sure, will

3754initially occur, but over time the soil around the pipe will

3765become compacted and result in re - rounding of the pipe. The

3777joints are three times stiffer than the body of the pipe,

3788which will protect the joint from excessive ovalation and

3797leaking , and the use of mechanical restrained joints will

3806further strengthen the joints. There has been no joint

3815leakage in Florida due to deflection of the joints. Finally,

3825there have been no failures of PVC pipe caused by three - feet

3838of fill, which is the dept h to which the Transmission Line

3850pipe will be buried.

385429. To further protect the pipe, the County optimized

3863its pumping system to avoid cyclical surges by using variable

3873frequency drive pumps that gradually increase and decrease

3881speed rather than just tu rning on or off. In addition, the

3893pump stations are fed by two power lines that come from

3904different directions and emergency generators, which should

3911lessen the chances of harmful surging.

3917d. Testing the Installation

392130. The anticipated pressures in t he Transmission Line

3930will likely be about 50 psi. After installation, the Line

3940will be pressure tested at 150 psi for two hours, which is

3952sufficient to provide the Department with reasonable assurance

3960that the Line will hold pressure and will not leak. A lso, the

3973County contract inspectors are on the construction site daily.

3982If problems with the installation arise later, the County has

3992committed to promptly fix the problem, even if it means

4002digging up the line.

400631. During the hearing, ITID asserted tha t the Uniform

4016Policies and Procedure Manual standards, which the County has

4025adopted for use by developers when constructing wastewater

4033transmission lines, should be applied to the County as well.

4043This standard, which requires pressure testing to 200 psi f or

4054PVC pipes larger than 24 inches, has not been adopted by the

4066Department and is not an applicable Department permitting

4074standard. Even if it did apply, the Transmission Line would

4084meet this criterion because it is designed to withstand 270

4094psi for at le ast 1,000 hours.

410232. Mr. Farabee believed that the entire Transmission

4110Line would be pressure tested after the construction was

4119complete, which would require digging up sections of the pipe

4129to install bulkheads. However, this assessment of the

4137County's te sting program is incorrect.

414333. Leisha Pica, Deputy Director of the Water Utilities

4152Department, developed the schedule for the project, helped

4160develop the phasing of the work and budget, and oversaw the

4171technical aspects. She stated that the County has

4179successfully tested approximately fifty percent of the line

4187that was already installed at 150 psi for two hours and not a

4200single section of the line failed the test.

4208e. Compaction

421034. The County has stringent backfilling and compaction

4218requirements, w hich are sufficient to ensure the pipe will be

4229properly installed and that there will be adequate compaction

4238of the fill material. The County plans and specifications

4247provide that compaction must be to ninety - five percent of the

4259American Association of St ate Highway and Transportation

4267Officials (AASHTO) standards for non - paved surfaces and one

4277hundred percent of AASHTO standards for paved surfaces. Even

4286ITID's expert agreed that the compaction specifications are

4294sufficient.

429535. Mr. Farabee contended, h owever, that even though the

4305standards are stringent, the County cannot properly test the

4314installation for compliance with the standards. Mr. Farabee

4322believed that testing of the backfill would be done after all

4333of the construction was complete. In that case, he did not

4344see how the testing could be done without digging many holes

4355to check for the density of the backfill. These assumptions,

4365however, are incorrect.

436836. The evidence shows that a total of two hundred

4378sixty - four compaction tests have already been done on the

4389portion of the Transmission Line that was completed. No part

4399of the installation failed the tests. The County has an

4409inspector who observes the installation and pressure tests.

4417The compaction was tested at every driveway and major roadw ay,

4428as well as every five hundred feet along the route. While

4439Lander and D'Ordine pointed out at hearing that no compaction

4449tests have been performed on the dirt roads which run adjacent

4460to their property and on which construction has taken place,

4470the Dep artment requires that, before the work is certified as

4481complete, non - paved roads must be compacted in accordance with

4492AASHTO standards in order to assure that there is adequate

4502compaction of the fill material.

4507f. The Sufficiency of the Application

451337. Whe n an application for an individual transmission/

4522collection line permit is filed with the Department, the

4531applicant certifies that the design of the pipeline complies

4540with the Department's standards. However, not all of the

4549details of the construction wil l be included in the permit

4560application. The Department relies on the design engineer to

4569certify that the materials used are appropriate. The

4577application form is also signed and sealed by a professional

4587engineer registered in the State of Florida.

459438. All plans submitted by the County, including the

4603original, modifications, and final version, were certified by

4611professional engineers registered in the State of Florida.

4619After receiving the application, the Department requested

4626additional information bef ore issuing the permit, and the

4635County provided all requested information. The original

4642construction plans that were submitted with the application

4650were changed in response to the Department's requests for

4659additional information. The Permit issued by the Department

4667indicates the Transmission Line would be constructed with

4675ductile iron pipe, but this was a typographical error.

468439. ITID maintains that all of the technical

4692specifications for the project must be included in the

4701application, and because no s eparate engineering report was

4710prepared by the County with the application, the County did

4720not meet that standard. While the County did not submit an

4731engineering report, it did submit sufficient data to provide

4740reasonable assurance that the project will c omply will all

4750applicable rules of the Department. As a part of its

4760application package, the County submitted construction plans,

4767which contain the specifications required by the Department.

4775Also, the general notes included in the construction drawings

4784s pecify the use of restrained joints where appropriate, the

4794selection of pipe material, the pressure testing of the

4803Transmission Line, and other engineering requirements. In

4810addition, the plans contain numerous other conditions, which

4818are also specificatio ns sufficient to fulfill the Department's

4827requirements. Finally, further explanation and clarification

4833of the technical aspects of the application was given by the

4844County at the final hearing.

484940. At the same time, the Department engineer who

4858oversaw the permitting of this project, testified that a

4867detailed engineering report was not necessary. This engineer

4875has extensive experience in permitting transmission lines for

4883the Department and has worked on over five hundred permits for

4894wastewater transmission and collection systems. The

4900undersigned has accepted his testimony that in a relatively

4909straightforward permit such as this, the application and

4917attachments themselves can function as a sufficient

4924engineering evaluation. This is especially true here sinc e

4933the County is seeking only approval of a pipeline project,

4943which would not authorize the receipt of wastewater flow

4952unless other wastewater facilities are permitted.

4958g. Impacts on Public and Private Drinking Water Wells

496741. As part of the design of the Transmission Line, the

4978County located public and private drinking water wells in the

4988area of the line. County personnel walked the route of the

4999Transmission Line and looked for private wells and researched

5008the site plans for all of the properties along th e route. No

5021public wells were found within one - hundred feet of the

5032Transmission Line route, but they did find seventeen private

5041wells that are within seventy - five feet of the line. None of

5054the Petitioners have private wells that are within seventy -

5064five f eet of the line. While Petitioners D'Ordine and Hawkins

5075initially contended that the well on Hawkins' property was

5084within seventy - five feet of the Transmission Line, at hearing

5095Mr. D'Ordine admitted that he "misread the plans and referred

5105to the wrong pro perty."

511042. In order to protect the private drinking water

5119wells, Florida Administrative Code Rule 62 - 604.400(1)(b)

5127requires that the County provide an extra level of protection

5137for the wells that are within seventy - five feet of the

5149Transmission Line. The County will provide that extra level

5158of protection by installing restrained joints that will

5166restrain the joints between the pipe sections. The restrained

5175joints are epoxy - coated mechanical devices that reduce the

5185tendency for the pipes to separate under pressure. The County

5195has used these restrained joints on its potable water and

5205wastewater lines in other areas of the County and has never

5216experienced problems with the devices. The restrained joints

5224will provide reliable protection of the private wells within

5233seventy - five feet of the Transmission Line. The Department is

5244unaware of any instances where restrained joints have failed

5253in South Florida. If more wells are discovered that are

5263within seventy - five feet of the Transmission Line, then the

5274County will excavate the Line and install restrained joints.

5283h. Minimum Separation Distances

528743. The County has complied with all applicable pipe

5296separation requirements in the installation of the

5303Transmission Line. More specifically, it is not closer than

5312si x feet horizontally from any water main and does not

5323intersect or cross any reclaimed water lines. See Fla. Admin.

5333Code R. 62 - 555.314(1)(a). It will be at least twelve inches

5345below any water main or culvert that it crosses. See Fla.

5356Admin. Code R. 62 - 55 5.314(2)(a). Finally, it will be a

5368minimum of twelve inches below any culverts that it crosses.

5378(However, the Department has no separation requirement for

5386culverts crossed by the Transmission Line.)

5392h. The M - Canal Crossing

539844. The Transmission Line must cross the M - canal, which

5409runs in an east - west direction approximately midway between

541940th Street North and Northlake Boulevard. The original

5427design called for the Transmission Line to cross above the

5437water, but the City and the Department suggested that it be

5448located below the canal to eliminate the chance that the pipe

5459could leak wastewater into the canal. In response to that

5469suggestion, the County redesigned the crossing so that a 24 -

5480inch high density polyethylene pipe in a 48 - inch casing will

5492be insta lled fifteen feet below the design bottom of the

5503canal. The polyethylene is fusion - welded, which eliminates

5512joints, and is isolated with a valve on either side of the

5524canal. Appropriate warning signs will be installed. See Fla.

5533Admin. Code R. 62 - 604.400 (2)(k)2. - 5. The depth of the

5546subaqueous line and the use of the slip line, or casing,

5557exceeds the Department's minimum standards. See Fla. Admin.

5565Code R. 62 - 604.400(2)(k)1.

5570i. Flushing Protocol

557345. Section 48.1 of the Ten State Standard recommends

5582that wastewater transmission lines maintain a velocity of two

5591feet per second. When the Transmission Line becomes

5599operational, it will not have sufficient flow to flush (or

5609clean) accumulated solids from the lines at the recommended

5618two feet per second velocit ies. (Sufficient flow will not

5628occur until other customers connect to the Transmission Line

5637during the first one to three years of operation.)

5646Accumulated solids produce gases and odors that could create a

5656problem at the treatment plant and might leak ou t of the

5668manhole covers. To address this potential problem, Specific

5676Condition 9 of the Permit requires the County to flush the

5687lines periodically. Pursuant to that Condition, the County

5695plans to flush the Transmission Line with additional water

5704which wi ll raise the velocity to three or four feet per

5716second, so that the accumulated solids will be flushed. The

5726water will be supplied by large portable tanks that will be

5737temporarily set up at several locations along the Line.

5746During the purging of the Line , sewage will collect in the

5757pump stations until the purge is finished. There is

5766sufficient capacity in the pump stations to contain the

5775wastewater. In addition, the County will use a cleansing tool

5785known as a pig, which is like a foam bullet that scrape s the

5799sides of the pipe as it is pushed through the line. This

5811protocol will be sufficient to keep the Line clean.

582046. ITID asserts that the County's plan for flushing is

5830inadequate, because it does not provide enough water for long

5840enough to flush both the 20 - inch and 30 - inch lines. Mr.

5854Farabee calculated that the County would need almost twice the

5864proposed volume, or almost six million gallons, to adequately

5873flush the lines.

587647. ITID's analysis of the flushing protocol is flawed,

5885however, because it assumes a constant flow in all segments of

5896the pipe, which is not practical. In order to maintain the

5907flushing velocity of three feet per second, the County will

5917introduce water into the Transmission Line at three separate

5926locations, resulting in a more constant flow velocity

5934throughout the Transmission Line. In this way, it can

5943maintain the proper velocity as the lines transition from a

595320 - inch to 30 - inch to 36 - inch pipe. The County has flushed

5969other lines in the past using this protocol and has had no

5981problems. This flushing protocol would only be in effect from

5991one to three years. The County estimates that the necessary

6001volumes to maintain a two - feet - per - second velocity in the 20 -

6017inch line would be reached in about one year. The 30 - inch

6030line should have sufficient flows sometime in 2008. These

6039estimates are based on the signed agreements the County has

6049with other utilities in the area to take their flows into the

6061Transmission Line. Because of these safeguards, the

6068Transmission Line will not accumu late solids that will cause

6078undesirable impacts while flow is less than two feet per

6088second.

6089D. Other Requirements

609248. The construction and operation of the Transmission

6100Line will not result in the release or disposal of sewage or

6112residuals without provid ing proper treatment. It will not

6121violate the odor prohibition in Florida Administrative Code

6129Rule 62 - 600.400(2)(a). It will not result in a cross -

6141connection as defined in Florida Administrative Code Rule 62 -

6151550.200. The construction or operation of the Transmission

6159Line will not result in the introduction of stormwater into

6169the Line, and its operation will not result in the acceptance

6180of non - domestic wastewater that has not been properly

6190pretreated. If constructed and permitted, the Transmission

6197Line w ill be operated so as to provide uninterrupted service

6208and will be maintained so as to function as intended. The

6219record drawings will be available at the Department's district

6228office and to the County operation and maintenance personnel.

623749. Finally, c oncerns by the individual Petitioners that

6246the County may not restore their property to its original

6256condition after construction is completed are beyond the scope

6265of this proceeding. At the hearing, however, the Deputy

6274Director of the Water Utilities Dep artment represented that

6283the County would cooperate with the individual property owners

6292to assure that these concerns are fully addressed.

6300E. Reasonable Assurance

630350. The County has provided the Department with

6311reasonable assurance, based on plans, test r esults,

6319installation of equipment, and other information that the

6327construction and installation of the Transmission Line will

6335not discharge, emit, or cause pollution in contravention of

6344the Department's standards.

6347CONCLUSIONS OF LAW

635051. The Division of Administrative Hearings has

6357jurisdiction over the subject matter and the parties pursuant

6366to Sections 120.569 and 120.57(1), Florida Statutes.

637352. Because Troy and Tracey Lee (Case No. 05 - 2979), Lisa

6385Gabler (Case No. 05 - 2980), and Anthony and Veronica D aly (Case

6398No. 05 - 2983) did not appear at the final hearing and did not

6412submit any proof in support of the allegations in their

6422respective Petitions, their Petitions should be dismissed for

6430lack of standing. See , e.g. , Agrico Chemical Co. v. Dept. of

6441Envir . Reg. et al. , 406 So. 2d 478, 482 (Fla. 2nd DCA 1981);

6455§ 120.57(1), Fla. Stat. All parties agree that the remaining

6465Petitioners have standing to bring this action.

647253. As the applicant, the County has the ultimate burden

6482of showing entitlement to th e Permit. To do so, it must

6494provide the Department with reasonable assurance that the

6502proposed activity will not "discharge, emit, or cause

6510pollution in contravention of Department standards or rules."

6518Fla. Admin. Code R. 62 - 4.070(1). Reasonable assuran ce

6528contemplates only a "substantial likelihood" that the project

6536will be successfully implemented, Metropolitan Dade County v.

6544Coscan Florida, Inc. et al. , 609 So. 2d 644, 649 (Fla. 3d DCA

65571992), and not an absolute guarantee. McCormick et al. v.

6567City of Jacksonville et al. , DOAH Case No. 88 - 2283, 1989 WL

6580224961 *8 (DOAH Oct. 16, 1989, DER Jan. 22, 1989).

659054. The minimum design and operation and maintenance

6598standards for domestic wastewater collection/transmission

6603systems are found in Florida Administra tive Code Chapter 62 -

6614604. The specific technical standards that apply to the

6623Project are found in Florida Administrative Code Rule 62 -

6633604.300, while the design and performance considerations are

6641found in Florida Administrative Code Rule 62 - 604.400.

665055. By a preponderance of the evidence, the County has

6660established that it meets all relevant criteria for issuance

6669of the Permit. More specifically, and in the context of the

6680objections raised by Petitioners, it is concluded that the

6689County has given reason able assurance that the Transmission

6698Line is designed in accordance with Florida Administrative

6706Code Rule 62 - 604.300, which contains the general technical

6716guidance for projects such as this; that it will be

6726constructed in accordance with the Department's r ules and the

6736Permit Conditions; that the subaqueous crossing of the M - canal

6747will meet the Department's criteria; that the Transmission

6755Line will be at least one hundred feet from all public

6766drinking wells; that in those instances where the Transmission

6775Lin e is within seventy - five feet of private drinking wells the

6788County will provide an equivalent level of reliability and

6797public health protection through the use of mechanical

6805restrained joints; that the County's plan for flushing the

6814Transmission Line is ad equate; that the required separation

6823distances have been maintained; that the application and

6831supporting data, as further clarified and explained at final

6840hearing, are sufficient to show that there is a substantial

6850likelihood that the Project will be succe ssfully implemented;

6859and that the Transmission Line will be located within rights -

6870of - way,

6873property owned by the County, or easements, as contemplated by

6883Florida Administrative Code Rule 62 - 604.400(1)(b).

689056. As to the property issues that have arisen b etween

6901ITID and the County, including the issue of whether the County

6912may place the Transmission Line in easements owned by ITID

6922without an ITID permit, neither the Department nor the

6931undersigned have jurisdiction to adjudicate those claims.

6938See , e.g. , Mi ller v. Dept. of Envir. Reg. , 504 So. 2d 1325,

69511327 (Fla. 1st DCA 1987); Safe Harbor Enterprises, Inc. v.

6961Robbie's Safe Harbor Marine Enterprises, Inc. et al. , DOAH

6970Case No. 98 - 3695, 1999 WL 33116615 *3 (DOAH Jan. 29, 1999, DEP

6984March 12, 1999); Hageman et al. v. Dept. of Envir. Prot. et

6996al. , DOAH Case No. 94 - 6794, 1995 WL 812077 *6 (DOAH July 7,

70101995, DEP Aug. 21, 1995).

701557. Because reasonable assurance has been given by the

7024County that Department standards and rules will not be

7033contravened, and there is a substantial likelihood that the

7042project will be successfully implemented, the Permit should be

7051issued.

7052RECOMMENDATION

7053Based on the foregoing Findings of Fact and Conclusions

7062of Law, it is

7066RECOMMENDED that the Department of Environmental

7072Protection enter a final order denying all Petitions and

7081issuing Permit No. 0048923 - 017 - DWC.

7089DONE AND ENTERED this 18th day of October, 2005, in

7099Tallahassee, Leon County, Florida.

7103S

7104DONALD R. ALEXANDER

7107Administrative Law Judge

7110Division o f Administrative Hearings

7115The DeSoto Building

71181230 Apalachee Parkway

7121Tallahassee, Florida 32399 - 3060

7126(850) 488 - 9675 SUNCOM 278 - 9675

7134Fax Filing (850) 921 - 6847

7140www.doah.state.fl.us

7141Filed with the Clerk of the

7147Division of Administrative Hearings

7151this 18th day of October, 2005.

7157ENDNOTE

71581/ All references are to Florida Statutes (2004).

7166COPIES FURNISHED:

7168Lea Crandall, Agency Clerk

7172Department of Environmental Protection

71763000 Commonwealth Boulevard

7179Mail Station 35

7182Tallahassee, Florida 32399 - 3000

7187Lisa Lander

718913881 40th Street North

7193Royal Palm Beach, Florida 33411 - 8491

7200Troy and Tracy Lee

720413881 40th Lane North

7208Royal Palm Beach, Florida 33411 - 8404

7215Joseph Acquaotta and Lisa Gabler

722013882 60th Street North

7224Royal Palm Beach, Florida 33411 - 8379

7231Anthon y and Veronica Daly

72364796 140th Avenue North

7240Royal Palm Beach, Florida 33411 - 8118

7247Michael D'Ordine and Ann E. Hawkins

72534474 140th Avenue North

7257Royal Palm Beach, Florida 33411 - 8464

7264Anthony D. Lehman, Esquire

7268Hunton & Williams, LLP

7272Bank of America Plaza, S uite 4100

7279600 Peachtree Street, Northeast

7283Atlanta, Georgia 30308 - 2216

7288William D. Preston, Esquire

7292William D. Preston, P.A.

72964832 - A Kerry Forrest Parkway

7302Tallahassee, Florida 32308 - 2272

7307Francine M. Ffolkes, Esquire

7311Department of Environmental Protection

73153000 Commonwealth Boulevard

7318Mail Station 35

7321Tallahassee, Florida 32399 - 3000

7326Amy Taylor Petrick, Esquire

7330Palm Beach County Attorney's Office

7335301 North Olive Avenue, Suite 601

7341West Palm Beach, Florida 33401 - 4705

7348Edward de la Parte, Jr., Esquire

7354De la Par te & Gilbert, P.A.

7361Post Office Box 2350

7365Tampa, Florida 33601 - 2350

7370Gregory M. Munson, General Counsel

7375Department of Environmental Protection

73793000 Commonwealth Boulevard, Mail Station 35

7385Tallahassee, Florida 32399 - 3000

7390NOTICE OF RIGHT TO SUBMIT EXCEPTIO NS

7397All parties have the right to submit written exceptions within

7407two calendar days of the date of this Recommended Order and

7418written responses to exceptions within two calendar days from

7427the filing of exceptions. Any exceptions to this Recommended

7436Order should be filed with the agency that will render a final

7448order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 11/02/2005
Proceedings: (Agency) Final Order filed.
PDF:
Date: 11/01/2005
Proceedings: Agency Final Order
PDF:
Date: 10/18/2005
Proceedings: Recommended Order
PDF:
Date: 10/18/2005
Proceedings: Recommended Order (hearing held September 13, 14, and 15, 2005). CASE CLOSED.
PDF:
Date: 10/18/2005
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 09/29/2005
Proceedings: Pro Se Petitioners Recommended Order filed.
PDF:
Date: 09/29/2005
Proceedings: Respondent, Department of Environmental Protection`s, Proposed Recommended Order filed.
PDF:
Date: 09/29/2005
Proceedings: Palm Beach County`s Proposed Recommended Order filed.
PDF:
Date: 09/29/2005
Proceedings: Indian Trail Improvement District`s Proposed Recommended Order filed.
PDF:
Date: 09/29/2005
Proceedings: Palm Beach County`s Proposed Recommended Order filed.
PDF:
Date: 09/21/2005
Proceedings: Letter to Judge Alexander from L. Foy enclosing exhibits as instructed at hearing filed (exhibits not available for viewing).
Date: 09/19/2005
Proceedings: Hearing before Administrative Law Judge Donald R. Alexander (transcript) filed.
Date: 09/13/2005
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 09/12/2005
Proceedings: Indian Trail Improvement District`s Request for Official Recognition filed.
PDF:
Date: 09/12/2005
Proceedings: Indian Trail Improvement District`s List of Potential Witnesses filed.
PDF:
Date: 09/12/2005
Proceedings: Notice of Appearance of Co-counsel for Department of Environmental Protection (filed by J. Wolfe).
PDF:
Date: 09/12/2005
Proceedings: Palm Beach County`s Exhibit List filed.
PDF:
Date: 09/12/2005
Proceedings: Palm Beach County`s Final Witness List filed.
PDF:
Date: 09/12/2005
Proceedings: Palm Beach County`s Notice of Filing Exhibit List filed.
PDF:
Date: 09/12/2005
Proceedings: Palm Beach County`s Notice of Filing Final Witness List filed.
PDF:
Date: 09/12/2005
Proceedings: Palm Beach County`s Notice of Filing Exhibit List filed.
PDF:
Date: 09/12/2005
Proceedings: Palm Beach County`s Notice of Filing Final Witness List filed.
PDF:
Date: 09/09/2005
Proceedings: Indian Trail Improvement District`s Request for Official Recognition filed.
PDF:
Date: 09/09/2005
Proceedings: Respondent DEP`s Witness List filed.
PDF:
Date: 09/09/2005
Proceedings: Respondent DEP`s Exhibit List filed.
PDF:
Date: 09/09/2005
Proceedings: Palm Beach County`s and Department of Environmental Protection`s Joint Pre-hearing Statement filed.
Date: 09/09/2005
Proceedings: Exhibits filed. (exhibits not available for viewing)
PDF:
Date: 09/09/2005
Proceedings: Palm Beach County`s and Department of Environmental Protection`s Joint Pre-hearing Statement filed.
PDF:
Date: 08/29/2005
Proceedings: Order (Department of Environmental Protection`s Motion for Summary Hearing granted).
PDF:
Date: 08/29/2005
Proceedings: Order (Verified Motion for Admission Pro Hac Vice filed on behalf of A. Lehman granted).
PDF:
Date: 08/25/2005
Proceedings: (Proposed) Order Granting Motion for Admission Pro Hac Vice filed.
PDF:
Date: 08/25/2005
Proceedings: Verified Motion for Admission Pro Hac Vice filed.
PDF:
Date: 08/24/2005
Proceedings: Notice of Hearing (hearing set for September 13 through 15, 2005; 9:00 a.m.; West Palm Beach, FL).
PDF:
Date: 08/23/2005
Proceedings: Order (consolidated cases are: 05-2979, 05-2980, 05-2981, 05-2982, 05-2983, and 05-2984).
PDF:
Date: 08/23/2005
Proceedings: Palm Beach County Joinder in Department of Environmental Protection`s Motion for Summary Hearing filed.
PDF:
Date: 08/23/2005
Proceedings: Palm Beach County Joinder in Department of Environmental Protection`s Motion for Summary Hearing filed.
PDF:
Date: 08/22/2005
Proceedings: Motion for Summary Hearing Pursuant to Section 403.973(15)(b), F.S. filed.
PDF:
Date: 08/19/2005
Proceedings: Palm Beach County Joinder in Department of Environmental Protection`s Motion for Consolidation filed.
PDF:
Date: 08/19/2005
Proceedings: Notice of Appearance as Co-Counsel filed.
PDF:
Date: 08/19/2005
Proceedings: Initial Order.
PDF:
Date: 08/19/2005
Proceedings: Palm Beach County Joinder in Department of Environmental Protection`s Motion for Consolidation filed.
PDF:
Date: 08/18/2005
Proceedings: Notice of Related Cases and Motion to Consolidate by Respondent Department of Environmental Protection (cases 05-2979, 05-2980, 05-2981, 05-2982, 05-2983, 05-2984) filed.
PDF:
Date: 08/18/2005
Proceedings: Domestic Wastewater Collection/Transmission Individual Permit filed.
PDF:
Date: 08/18/2005
Proceedings: Notice of Permit Issuance filed.
PDF:
Date: 08/18/2005
Proceedings: Request for Administrative Hearing filed.
PDF:
Date: 08/18/2005
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
08/18/2005
Date Assignment:
08/19/2005
Last Docket Entry:
11/02/2005
Location:
West Palm Beach, Florida
District:
Southern
Agency:
ADOPTED IN PART OR MODIFIED
 

Counsels

Related Florida Statute(s) (4):