05-004308
Kevin Burkett vs.
Osceola County, Habitat Restoration, Inc.; And South Florida Water Management District
Status: Closed
Recommended Order on Wednesday, August 9, 2006.
Recommended Order on Wednesday, August 9, 2006.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8KEVIN BURKETT , )
11)
12Petitioner , )
14)
15vs. ) Case No. 05 - 4308
22)
23OSCEOLA COUNTY ; HABITAT )
27RESTORATION, INC. ; AND SOUTH )
32FLORIDA WATER MANAGEMENT )
36DISTRICT , )
38)
39Respondent s. )
42)
43RECOMMENDED ORDER
45A formal administrative hearing in this case was held on
55March 14 and 15, 2006, in Orlando, Florida, before Bram D. E.
67Canter, an Administrative Law Judge of the Division of
76Administrative Hearings (DOAH).
79APP EARANCES
81For Petitioner: Eric T. Olsen, Esquire
87Hopping Green & Sams, P.A.
92Post Office Box 6526
96Tallahassee, Florida 32314 - 6526
101For Respondent Osceola County:
105Timot hy Smith, Esquire
109Silvia Morell Alderman, Esquire 1
114Akerman Senterfitt
116106 East College Avenue, Suite 1200
122Tallahassee, Florida 32301
125Olga Sanchez de Fuentes, Esquire
130Office of the County Attorney
1351 Courthouse Square, Suite 4200
140Kissimmee, Florida 34741 - 5440
145For Respondent South Florida Water Management District:
152Pete r Cocotos, Esquire
156South Florida Water Management District
1613301 Gun Club Road, M ail S top C ode 1410
172West Palm Beach, Florida 33406
177STATEMENT OF THE ISSUE S
182The issues in this case are whether Peti tioner has standing
193to initiate this proceeding and whether Respondents Osceola
201County and Habitat Restoration, Inc., demonstrated their
208entitlement to the permit modification they are requesting.
216PRELIMINARY STATEMENT
218On November 2, 2005, South Florida Wa ter Management
227District ("the District") gave notice of its intent to issue a
240Modification to Environmental Resource Permit No. 49 - 00121 - S - 02
253("the ERP Modification") to Respondents Osceola County ("the
264County") and Habitat Restoration, Inc. (HRI) , for a p roject
275known as Poinciana Boulevard, Phase II. Petitioner timely filed
284a petition challenging the proposed agency action , and the
293District referred the matter to DOAH to conduct a formal
303evidentiary hearing.
305At the hearing, the County presented the testi mony of Rod
316Schultz, Stuart Bradow , and John Atkins. The County's Exhibits
325C - 1 through C - 5, C - 7 through C - 9, C - 11 through C - 16, C - 18
349through C - 25, and C - 27 were admitted into evidence. Joint
362Exhibits 1, 1 - A, J - 1(c), J - 1(d), J - 1(f), J - 1(g), J - 1(i), J - 1(j) ,
3852, 2 - A, and J - 9 (including Exhibit 5 to Joint Exhibit J - 9) were
403also admitted into evidence at the request of the County. 2 The
415District presented the testimony of Susan Elfers and Jennifer
424Stout. Joint Exhibit J - 1(h) was admitted at the request of the
437District. Petitioner presented the testimony of Kevin Burkett
445and Tom Odom. Petitioner's Exhibits P - 1, P - 6 through P - 8, and
461P - 14 through P - 17 were admitted into evidence. Petitioner's
473Exhibit P - 20 was not admitted into evidence, but at the request
486of Pe titioner, a proffer of the exhibit was allowed.
496Official recognition was taken of Florida Administrative
503Code Chapters 40E - 4 and 62 - 345, as well as the District's Basis
518of Review for Environmental Resource Applications (Basis of
526Review).
527Th e four - volume T r anscript of the hearing was filed with
541DOAH on May 10, 2006. The parties jointly moved for an
552extension of the date for filing their post - hearing submittals,
563and the parties were given a new deadline of June 19, 2006.
575Each party timely filed a Proposed R ecommended Order that was
586carefully considered in the preparation of this Recommended
594Order .
596FINDINGS OF FACT
599Background
6001. Petitioner resides in Orlando and is a recreational
609hunter.
6102. T he District is a multi - purpose water management
621district, operati ng pursuant to Chapter 373, Florida Statutes,
630and Florida Administrative Code Chapter 40E. Its principal
638office is in West Palm Beach, Florida.
6453. The County has been an applicant/permittee at all times
655material to this proceeding.
6594. HRI is co - permitte e and operates a regional mitigation
671area near the town of Holopaw.
6775. On October 13, 2004, the District issued Environmental
686Resource Permit No. 49 - 00121 - S - 02 ("the Original ERP") to the
703County, authorizing construction and operation of a surface
711water m anagement system in conjunction with the widening of
721Poinciana Boulevard ("the Road Project"). The Road Project is
732expected to adversely impact 6.61 acres of wetlands.
7406. I n the Original ERP, mitigation for the wetland impacts
751was to be provided through the purchase of mitigation credits in
762the 1600 - acre Florida Mitigation Bank (FMB).
7707. The Road Project and the wetlands that it would impact
781are located within the Shingle Creek Drainage Basin.
7898. As shown in Petitioner's Exhibit P - 6, only a very small
802p ortion of the FMB is located within the Shingle Creek Drainage
814Basin. Almost all of the FMB is within the Reedy Creek Drainage
826Basin, which is west of the Shingle Creek Drainage Basin.
8369. The County applied for a modification of the original
846permit , and the District issued the ERP Modification to the
856County and HRI. The ERP Modification changes only the
865mitigation plan for offsetting the wetland impacts of the Road
875Project.
87610. The ERP Modification calls for mitigation of the
885wetland impacts of the Road Project through the restoration of
895wetlands within the regional mitigation area operated by HRI.
904The proposed HRI mitigation site is within Osceola County, but
914outside the Shingle Creek Drainage Basin.
920Standing
92111. For the past six or seven years , Petiti oner has been
933hunting within a small area of the FMB, along its eastern
944boundary, as shown on Petitioner's Exhibit 15. Petitioner hunts
953there approximately 20 times each year. He hunts for deer,
963turkey , and hogs. He also enjoys observing nature while he is
974hunting.
97512. The FMB is not open to the general public for hunting.
987Petitioner hunts in the FMB with the verbal permission of the
998owner. Petitioner expects the permission he has been given to
1008hunt in the FMB will continue into the future.
101713. A fen ce surrounds the FMB, but deer and turkey can get
1030over a fence and hogs can get under a fence.
104014. At the hearing, there was some dispute about the exact
1051location of the boundary that divides the Shingle Creek Drainage
1061Basin from the Reedy Creek Drainage Basin , and in which of the
1073two basins Petitioner hunts. The dispute was caused by the fact
1084that the area where Petitioner hunts is close to the boundary
1095and the official maps of the b asin s are at such a small scale
1110that the line which depicts the boundary covers a large area.
1121No evidence was presented about the precise location of the
1131topography that divides the basins. The more persuasive
1139evidence in the record is that a small area of the FMB (the
1152acreage was never established) is within the Shingle Cre ek
1162Drainage Basin and includes the area where Petitioner hunts.
117115. Petitioner's primary objection to the ERP Modification
1179is the proposal to mitigate for the loss of 6.61 acres of
1191wetlands by restoring wetlands that are outside the Shingle
1200Creek Drainage Basin. He contends that the ERP Modification
1209will serve as a precedent for future mitigation outside the
1219Shingle Creek Drainage Basin. 3 Petitioner's standing argument is
1228that th e future mitigation outside the B asin will reduce
1239populations of the wildlif e within the FMB where he hunts.
125016. Undermining this premise for Petitioner's standing is
1258the fact that drainage basin boundaries are hydrologic
1266boundaries based on patterns of water movement; they are not
1276boundaries associated with wildlife movement. T he animals that
1285Petitioner hunts move freely across drainage basin boundaries.
129317. Therefore, drainage basin boundaries are not the
1301proper focus for determining whether Petitioner is substantially
1309affected by the proposed ERP Modification. Whether Petiti oner
1318is substantially affected depends on the effect the ERP
1327Modification would have on environmental factors (including the
1335quality and extent of wetlands) that determine the populations
1344of wildlife Petitioner enjoys hunting and observing, no matter
1353where those environmental factors are located.
135918. Petitioner assumes that all future mitigation outside
1367the Shingle Creek Drainage Basin will be detrimental to his
1377interests. However, Stuart Bradow explained that whether future
1385wetlands impacts and future mi tigation would affect Petitioner's
1394interests depends on the proximity of the future impacted
1403wetlands and associated mitigation to the area where Petitioner
1412hunts, without regard to wh ich drainage basin the wetlands and
1423mitigation are located within .
142819. Some wetland impacts in the Shingle Creek Drainage
1437Basin would be too distant to adversely affect Petitioner's
1446interests. Some out - of - basin mitigation could be close enough
1458to positively affect Petitioner's interests. Because much of
1466the Shingle Creek Dr ainage Basin is more distant from
1476Petitioner's hunting area than areas of the Reedy Creek Drainage
1486Basin, it can be reasonably inferred that there could be future
1497mitigation in the Reedy Creek Drainage Basin to offset wetland
1507impacts in the Shingle Creek D rainage Basin that would benefit
1518Petitioner's interests.
152020. Petitioner's precedent argument, that all future out -
1529of - basin mitigation will per se be adverse to his interests, is
1542contradicted by the more credible and persuasive evidence in the
1552record.
155321. The ERP Modification does not call for any
1562construction or other activities within the area where
1570Petitioner hunts or in any other part of the FMB.
158022. The ERP Modification will not physically impact the
1589area within the FMB where Petitioner hunts.
159623. T he ERP Modification does not reduce the number of
1607acres within the FMB.
161124. The ERP Modification will not affect Petitioner's
1619access to the FMB for hunting.
162525. The direct and indirect impacts associated with the
1634loss off 6.61 acres of wetlands caused by the Road Project would
1646not adversely affect Petitioner's hunting or nature observation
1654within the FMB.
165726. Petitioner's evidence regarding the biological
1663processes that link the alleged future wetland losses within the
1673Shingle Creek Drainage Basin to pop ulations of deer, turkey , and
1684hogs in the FMB was inadequate. There was no evidence
1694presented, for example, about the variability in such game
1703populations, the causes of the variability, and how wetland
1712acreage affects population variability.
171627. Petitio ner's expert, Tom Odom, acknowledged that
1724drainage basin boundaries do not limit wildlife movement, yet
1733offered an opinion that seemed to assume the opposite. For
1743example, his opinion that Petitioner's enjoyment of deer hunting
1752in the FMB might diminish a s a result of the ERP Modification
1765was based on his belief that deer populations would be
1775restricted to "a certain area" and prevented from intermixing.
178428. Mr. Odom's opinion was also based on the assumption
1794that HRI's mitigation proposal at its site nea r Holopaw would
1805not be successful. That opinion contradicts Petitioner's basic
1813contention that the HRI mitigation site is too far away to
1824offset the wetland impacts caused by the Road Project.
1833According to Petitioner, the HRI site is too far away to offs et
1846those wetland impacts but close enough to adversely affect
1855Petitioner's hunting in the FMB if the mitigation site fails to
1866function as proposed.
186929. Mr. Odom also opined that the elimination of small
1879wetland areas can be detrimental to wildlife and are not
1889mitigated by increasing the size of a large wetland area.
1899However, in this regard there is no difference between the
1909Original ERP and the ERP Modification. Both permits would allow
1919the loss of the small wetland s caused by the Road Project and
1932would mitigate the losses by adding to or enhancing larger,
1942regionally significant wetland areas. Petitioner did not
1949challenge the Original ERP. He cannot collaterally attack in
1958this proceeding the District's previous determination to allow
1966the loss of the sma ll wetlands caused by the Road Project.
197830. Petitioner failed to demonstrate that the ERP
1986Modification would reduce populations of deer, turkey , and hogs
1995in the FMB to the extent that Petitioner's enjoyment of hunting
2006would be diminished. Petitioner fail ed to demonstrate that he
2016will be substantially affected by the District's approval of the
2026ERP Modification.
202831. At the hearing, the parties presented evidence on all
2038factual disputes related to the ERP Modification. Therefore,
2046despite the foregoing find ing that Petitioner did not
2055demonstrate his standing, findings related to the other factual
2064disputes are set forth below.
2069Cumulative Impact Analysis
207232. Pursuant to Subsection 373.414(8)(a), Florida
2078Statutes (2005) , the District is required to consider the
2087cumulative impacts upon wetlands and other surface waters within
2096the same drainage basin as the proposed activity. The
2105cumulative impact analysis is supposed to consider existing
2113projects, projects under construction, projects for which
2120permits have b een sought, developments of regional impact, and
2130other activities regulated under Chapter 373, Florida Statutes,
2138or which may reasonably be expected based upon local government
2148comprehensive plans. Although Petitioner claimed otherwise, the
2155record shows t he District considered these projects and
2164activities in the cumulative impact analysis it conducted for
2173the ERP Modification.
217633. Section 4.2.8 of the Basis of Review provides that ,
2186when adverse impacts to wetlands are not fully offset within the
2197same dra inage basin as the impacts, the applicant must provide
2208reasonable assurance that the proposed activity will not result
2217in unacceptable cumulative impacts to the functions of wetlands
2226within the drainage basin where the impacts would occur.
223534. In conducti ng its cumulative impacts analysis, the
2244District considered future projects within the Shingle Creek
2252Drainage B asin which the District determined would likely have
2262similar impacts. It determined that similar impacts would be
2271caused by future road - widening projects.
227835. Petitioner complained that the County did not perform
2287a cumulative impact assessment of the Orange County portion of
2297the Shingle Creek Drainage Basin, but the testimony revealed
2306that was because the District already had this data. The
2316Dist rict reviewer who conducted the cumulative impact analysis,
2325Susan Elfers, is also the reviewer for all road projects in the
2337Orlando area. The Florida Department of Transportation
2344routinely provides the District projections of future road
2352projects. Becaus e Ms. Elfers had considerable information
2360regarding Orange County transportation projects, the District
2367did not require the County to provide that information.
237636. In performing the cumulative impact analysis, the
2384District is directed by Section 4.2.8 of the Basis of Review to
2396consider the functions of wetlands and other surface waters in
2406the basin "as a whole."
241137. Approximately 20,000 acres of the Shingle Creek
2420Drainage Basin lies within Osceola County. Of this total, 4,631
2431acres are wetlands. More th an a quarter of the wetlands are in
2444some form of conservation status. According to the County,
2453there are 3 , 113 more acres of wetlands proposed for conservation
2464in the Shingle Creek Drainage Basin. Altogether, 94 percent of
2474the wetlands in the Shingle Cre ek Drainage Basin in Osceola
2485County are either in conservation or proposed for conservation.
249438. More than half of the Shingle Creek Drainage Basin
2504lies in Orange County, north of Osceola County. Tom Odom
2514determined that the entire Shingle Creek Drainage Basin was
2523comprised of over 22,000 acres of wetlands , of which 88 percent
2535are protected.
253739. Considering the wetland functions of the Shingle Creek
2546Drainage Basin "as a whole," the projected cumulative loss of
2556wet lands associated with road projects repre sents a very minor
2567impact on the total wetland functions in the Shingle Creek
2577Drainage Basin and a very small fraction of the wetland
2587functions already under protection.
259140. A s discussed in detail below, the proposed HRI
2601mitigation site will provide subst antial environmental benefits
2609to the region.
261241. The County and HRI proved by a preponderance of the
2623evidence that the ERP Modification will not result in
2632unacceptable cumulative impacts within the Shingle Creek
2639Drainage Basin.
2641Secondary Impacts
264342. In a ddition to addressing the direct impacts of a
2654project, the Districts Basis of Review requires that a
2663projects secondary impacts be offset. Petitioner contends that
2671the secondary impacts associated with the ERP Modification were
2680not addressed. However, the record evidence indicates a
2688qualitative analysis of secondary impacts was made by the
2697District to determine whether the HRI mitigation site would
2706offset the secondary impacts of the Road Project.
271443. The District determined that the excess value of th e
2725proposed HRI mitigation over the lost value of the impacted
2735wetlands was sufficient to offset the relatively minor secondary
2744impacts expected from the Road Project. That determination was
2753reasonable.
2754The Proposed Mitigation Site
275844. HRI owns a regional mitigation area of over 2,000
2769acres. This area includes extensive wetland areas that were
2778significantly degraded by the cattle and agricultural operations
2786of previous owners. Portions of the 2,000 - acre tract continue
2798to suffer from over - drainage and wid espread exotic nuisance
2809species, including the area which HRI proposes to restore as
2819mitigation for the wetland impacts of the Road Project.
282845. The 2,000 - acre mitigation area already contains
283823 previously approved wetland mitigation projects. Wildlife
2845use of the area has been steadily increasing as each mitigation
2856project has been implemented. The area now supports a high
2866diversity of wildlife, including an impressive array of
2874endangered and threatened animal species.
287946. The HRI mitigation site for the ERP Modification
2888consists of 26.1 acres in four separate areas with separate
2898mitigation activities proposed for each area. There would be
2907high level enhancement of 6.8 acres of a forested wetland area,
2918moderate level enhancement of 13.9 acres of mixe d forested
2928wetland, four acres of upland buffer enhancement and
2936preservation, and 1.4 acres of herbaceous wetland enhancement.
294447. The proposed mitigation will include filling in part
2953of a drainage canal, removing exotic plant species, and planting
2963cypres s trees. The mitigation site will be managed for wildlife
2974and protected by a conservation easement.
298048. The mitigation proposal for the ERP Modification
2988involves activities that are similar to those that HRI has
2998successfully completed as part of several other mitigation
3006projects in HRI's regional mitigation area. HRI's success with
3015similar mitigation projects provides part of the reasonable
3023assurances that the mitigation authorized by the ERP
3031Modification will also succeed in creating wetlands of high
3040fu nctional value.
304349. The proposed offsite mitigation area represents
3050substantially greater wildlife habitat benefits than were
3057provided by the 6.61 acres of wetlands impacted by the Road
3068Project.
306950. Petitioner claims that the County and HRI failed to
3079dem onstrate that the proposed mitigation site was engineered to
3089allow water movement as needed to create and maintain
3098appropriate hydrologic conditions for the restored wetlands.
3105Petitioner did not claim that the proposed mitigation project
3114was not properly engineered, but only that the District was not
3125provided the kind of engineering analysis usually required for
3134such projects.
313651. At the hearing, the District witness, Ms. Elfers,
3145explained that the District's determination that the proposed
3153mitigation pro ject was properly engineered was based in part on
3164information exchanged during meetings with the applicant.
3171Moreover, the County presented an expert engineering witness,
3179John Atkins , who testified about the engineering aspects of the
3189project site related to hydrology and offered his opinion that
3199the project is properly engineered. 4 The more persuasive
3208evidence in the record is that the proposed mitigation project
3218is engineered so that the hydrologic aspects of the project will
3229allow for the successful res toration and maintenance of the
3239wetlands involved.
3241Uniform Mitigation Assessment Method
324552. The Uniform Mitigation Assessment Method (UMAM),
3252codified in Florida Administrative Code Chapter 62 - 345, is used
3263to determine the amount of wetland mitigation requ ired. The
3273UMAM methodology provides a standardized procedure for assessing
3281the function provided by wetlands. By examining a number of
3291environmental factors, such as its community structure and its
3300water environment, the UMAM can assess the value of the function
3311being provided by a wetland. UMAM allows for the functional
3321value of a wetland to be quantified and compared t o the
3333functional value of other wetlands .
333953. A UMAM analysis was performed on both the wetlands
3349that would be impacted by the Road Pro ject and the wetlands that
3362HRI proposes to restore. Under UMAM, the functional gain score
3372for the restored wetlands must at least equal to the functional
3383loss score for the impacted wetlands.
338954. The UMAM score determined for the wetlands impacted by
3399the Road Project was 4.47 functional units. The UMAM score
3409determined for the HRI mitigation site was 5.4 7 functional
3419units. These scores mean that the wetland functional value gain
3429for the proposed HRI mitigation site was determined to more than
3440offset the functional loss that would be caused by the wetland
3451impacts of the Road Project.
345655. The four restoration areas within the HRI mitigation
3465site were separately scored using the UMAM methodology. Among
3474the factors considered were time lag and risk. Time lag means
3485the period of time between when the functions are lost at an
3497impact site and when those functions are replaced by the
3507mitigation. Fla. Admin. Code R. 62 - 345.600(1)(a). Mitigation
3516risk refers to the degree of uncertainty in achieving the
3526mitig ation objectives. Fla. Admin. Cod R. 62 - 345.600(2) .
353756. Petitioner disagreed with the risk factor used to
3546score the HRI mitigation site because, according to Petitioner,
3555no engineering modeling or information was provided for the
3564hydrologic changes that would be required to achieve success.
3573The adequacy of the engineering analysis for the HRI mitigation
3583site was addressed above. The risk factor used in scoring this
3594particular area was reasonable.
359857. Petitioner also objected to the time lag values used
3608to obtain the score for the HRI mitigation site areas designated
3619Eastern Forested WL Enhancement (High Level) and the Western
3628Forested WL Enhancement (Moderate). The time values used for
3637these areas equate to an expectation that the functions lost
3647becaus e of the wetland impacts of the Road Project will be
3659replaced within five years. Petitioner contends that
3666expectation is unreasonable because the impacted wetlands
3673contain mature wetland trees which cannot be replaced in five
3683years.
368458. The time lag valu e used, however, does not reflect an
3696assumption that in five years all the trees planted in the
3707mitigation site will be as mature as a particular tree or trees
3719found in the impacted wetlands. The time lag value reflects the
3730time needed for the mitigation site to gain functional values
3740equivalent to the functional values lost. Furthermore, there
3748are already trees in the mitigation site. The more persuasive
3758evidence of record indicates that the time lag value used was
3769reasonable.
377059. Petitioner argues tha t the use of the same time lag
3782factor for the different types of wetland systems in the HRI
3793mitigation site contradicts the "express direction" of Florida
3801Administrative Code Rule 62 - 345.600(1)(a). That rule, however,
3810merely contains a qualitative stateme nt of the general
3819comparison of time lags for different wetland systems. It does
3829not require that time lags used for different systems must be
3840different.
384160. Wetlands are classified into different community types
3849by the Florida Land Use Cover and Classif ication System
3859(FLUCCS). Petitioner complains that none of the FLUCCS codes
3868for the ecological communities at the HRI mitigation site match
3878the FLUCCS codes of the wetlands proposed to be impacted by Road
3890Project. Petitioner admits , however, that two of the HRI
3899mitigation areas have similar FLUCCS codes. The two areas with
3909dissimilar wetland types are the upland buffer and existing
3918canal that will be restored to a deep water marsh. However, i t
3931was never suggest ed that these two areas were similar to the
3943impacted wetlands. They are simply areas within the HRI
3952mitigation site that are being restored in conjunction with
3961adjacent forested wetlands to enhance the overall diversity and
3970quality of the resulting ecosystem.
397561. The more persuasive and competent evidence in the
3984record indicates that the UMAM scores for the impacted wetlands
3994and the mitigation site were reasonable and that they fairly
4004characterized the proposed HRI mitigation as exceeding in
4012functional value what would be lost as a result of the w etland
4025impacts caused by the Road Project.
4031CONCLUSIONS OF LAW
403462. DOAH has jurisdiction over the parties to and subject
4044matter of this proceeding pursuant to Section s 150.569 and
4054120.57, Florida Statutes (2005) . 5
406063. The District is the agency with respo nsibility and
4070authority to review and act upon the ERP Permit Modification at
4081issue, pursuant to Chapter 373, Part IV, Florida Statutes, and
4091the "Operating Agreement Concerning Regulation Under Part IV,
4099Chapter 373, F.S." between the District and the Depar tment of
4110Environmental Protection, adopted by reference in Florida
4117Administrative Code Rule 40E - 4.091(1)(c).
412364. Under S ubs ection 120.569(1), Florida Statutes, formal
4132administrative proceedings are limited to persons whose
4139substantial interests are determ ined by an agency.
414765. In Agrico Chemical Company v. Department of
4155Environmental Regulation , 406 So. 2d 478, 482 (Fla. 2nd DCA
41651981), a two - pronged test was articulated to establish a party's
4177substantial interest. A party must demonstrate (1) the propose d
4187agency action will result in injury - in - fact of sufficient
4199immediacy to justify a Section 120.57 hearing, and (2) the
4209injury is of the type or nature the proceeding is designed to
4221protect. The first prong involves the degree of the injury and
4232the second concerns the nature of the injury at stake. Menorah
4243Manor v. AHCA , 908 So. 2d 1100, 1104 (Fla. 1st DCA 2005).
425566. Petitioner failed to meet the first prong of the
4265Agrico test because h is claim that he will suffer injury as a
4278result of the ERP Modificatio n is speculative. His allegation
4288of injury depend s on several independent, future actions or
4298effects which might never occur: (1) the ERP Modification will
4308serve as a precedent for future wetland impacts in the Shingle
4319Creek Drainage Basin that are mitiga ted outside the B asin;
4330(2) the future out - of - basin mitigation will cause a net loss of
4345wetlands in the Shingle Creek Drainage Basin; (3) the net loss
4356of wetlands in the B asin will occur in locations and will be of
4370such an extent as to cause a reduction in the populations of
4382deer, turkey , and hogs within the FMB; (4) Petitioner will
4392continue to have permission to hunt in the FMB; and
4402(5) Petitioner's enjoyment of hunting in the FMB will be
4412diminished.
441367. The second prong of the Agrico test requires a
4423de monstration of a n injury of the type that the applicable
4435statute is designed to protect. The County argues that
4444Petitioner does not meet th is test because he has no legally
4456enforceable entitlement to hunt and enjoy wildlife in the future
4466on the FMB proper ty. Petitioner , on the other hand, cites
4477S ubs ection 403.412(5), Florida Statutes, for the proposition
4486that he only needs to show the proposed activity affects his use
4498or enjoyment of natural resources.
450368. There is no decisional law on the precise questi on of
4515whether a petitioner's use of natural resources on lands which
4525he has access to by verbal permission of the owner is sufficient
4537for standing. The undersigned is inclined to the view that the
4548undisputed present right of Petitioner to hunt in the FMB is
4559sufficient to confer standing on him to object to activities
4569that affect his use and enjoyment of the natural resources of
4580the FMB; no contract or other "formal" right of access is
4591required. However, a legal conclusion on this particular
4599question is un necessary because Petitioner did not demonstrate
4608that the ERP Modification will affect his use and enjoyment of
4619the natural resources within the FMB.
462569. The County and HRI, as the applicants for the ERP
4636Modification, have the ultimate burden of proving t he ir
4646entitl ement to the permit. Department Of Transportation v.
4655J.W.C. Company, Inc. , 396 So. 2d 778 (Fla. 1st DCA 1981).
466670. In order to prove their entitlement to the ERP
4676Modification, the County and HRI must provide reasonable
4684assurances that the prop osed mitigation is not contrary to the
4695public interest, based on seven criteria enumerated in
4703S ubs ection 373.414(1)(a), Florida Statutes. Relevant here are
4712the following criteria:
47152. Whether the activity will adversely
4721affect the conservation of fish and
4727wildlife, including endangered or threatened
4732species, or their habitats;
4736* * *
47394. Whether the activity will adversely
4745affect the fishing or recreational values or
4752marine productivity in the vicinity of the
4759activity;
4760* * *
47637. The curr ent condition and relative value
4771of functions being performed by areas
4777affected by the proposed activity.
478271. An applicant must provide reasonable assurances, not
4790absolute guarantees. Reasonable assurance contemplates a
4796substantial likelihood that the project will be successfully
4804implemented. Metropolitan Dade County v. Coscan Florida, Inc. ,
4812609 So. 2d 644, 648 (Fla. 3d DCA 1992).
482172. Subsection 373.414(1)(b), Florida Statutes, provides in
4828relevant part:
4830If the applicant is unable to otherwise meet
4838the criteria set forth in this subsection,
4845the governing board or the department, in
4852deciding to grant or deny a permit, shall
4860consider measures proposed by or acceptable
4866to the applicant to mitigate adverse effects
4873that may be caused by the regulated
4880acti vity. Such measures may include, but
4887are not limited to, onsite mitigation,
4893offsite mitigation, offsite regional
4897mitigation, and the purchase of mitigation
4903credits from mitigation banks permitted
4908under s. 373.4136 . It shall be the
4916responsibility of the a pplicant to choose
4923the form of mitigation. The mitigation must
4930offset the adverse effects caused by the
4937regulated activity.
493973. Mitigation is further addressed in Section 373.4135,
4947Florida Statutes, which provides in relevant part as follows:
4956(1) The L egislature finds that the adverse
4964impacts of activities regulated under this
4970part may be offset by the creation,
4977maintenance, and use of mitigation banks and
4984offsite regional mitigation. Mitigation
4988banks and offsite regional mitigation can
4994enhance the cer tainty of mitigation and
5001provide ecological value due to the improved
5008likelihood of environmental success
5012associated with their proper construction,
5017maintenance, and management. Therefore, the
5022department and the water management
5027districts are directed to participate in and
5034encourage the establishment of private and
5040public mitigation banks and offsite regional
5046mitigation. Mitigation banks and offsite
5051regional mitigation should emphasize the
5056restoration and enhancement of degraded
5061ecosystems and the preserv ation of uplands
5068and wetlands as intact ecosystems rather
5074than alteration of landscapes to create
5080wetlands. This is best accomplished through
5086restoration of ecological communities that
5091were historically present.
5094* * *
5097( b) It is the further inte nt of the
5107Legislature that mitigation banks and
5112offsite regional mitigation be considered
5117appropriate and a permittable mitigation
5122option under the conditions specified by the
5129rules of the department and water management
5136districts.
5137(c) Offsite mitigation , including offsite
5142regional mitigation, may be located outside
5148the regional watershed in which the adverse
5155impacts of an activity regulated under this
5162part are located, if such adverse impacts
5169are offset by the offsite mitigation.
517574. A lthough Petitione r frequently referred to the adverse
5185precedent that would be created by the ERP Modification because
5195it allows for mitigation outside the Shingle Creek Drainage
5204Basin, Section 373.4135, Florida Statutes, expressly authorizes
5211out - of - basin mitigation. The a ppropriate i nquiry, therefore, is
5224not whether the mitigation proposed in the ERP Modification is a
5235precedent, but whether it meets the applicable criteria for
5244approval.
524575. The applicable rule criteria for an Environmental
5253Resource Permit in the District are set forth in Florida
5263Administrative Code Rules 40E - 4.301 (1) and 40E - 4.302 , and in the
5277Basis of Review which is incorporated by reference in Florida
5287Administrative Code Rule 40E - 4.091 . Florida Administrative Code
5297Rule 40E - 4.301(3) provides that the sta ndards and criteria ,
5308including mitigation provisions, in the Basis of Review shall
5317determine whether reasonable assurances required by Florida
5324Administrative Code Rule s 40E - 4.301(1) and 40E - 4.302 have been
5337provided.
533876. Section 4.2.8 of the Basis of Revie w requires an
5349applicant to provide reasonable assurances that the proposed
5357activity will not cause unacceptable cumulative impacts upon
5365wetlands and other surface waters within the same drainage basin
5375as the regulated activity for which a permit is sought.
538577. Section 4.2.8.1 of the Basis of Review explains that the
5396cumulative impacts analysis focuses on whether there will be a
5406violation of state water quality standards or significant adverse
5415impacts to functions of wetlands or other surface waters within
5425the same drainage basin when considering the basin " as a whole . "
543778. The County and HRI provided reasonable assurances that
5446that the ERP Modification will not result in unacceptable
5455cumulative impacts in the Shingle Creek Drainage Basin.
546379. The County a nd HRI provided reasonable assurances that
5473the ERP Modification is not contrary to the public interest,
5483taking into account the seven criteria set forth in Subsection
5493373.414(1), Florida Statutes.
549680. The County and HRI provided reasonable assurances that
5505the HRI mitigation site will offset the wetland impacts that
5515will be caused by the Road Project. In fact, reasonable
5525assurance s w ere provided that a net ecological benefit to the
5537region will be achieved as a result of the proposed mitigation.
5548RECOMMENDAT ION
5550Based on the foregoing findings of fact and conclusions of
5560law, it is
5563RECOMMENDED that the Governing Board of the South Florida
5572Water Management District enter a f inal o rder issuing
5582Modification to Environmental Resource Permit No. 49 - 00121 - S - 02
5595to O sceola County and Habitat Restoration, Inc., subject to the
5606general and special conditions set forth in the District's Staff
5616Review Summary.
5618DONE AND ENTERED this 9 th day of August , 2006 , in
5629Tallahassee, Leon County, Florida.
5633S
5634BRAM D. E. CANTER
5638Administrative Law Judge
5641Division of Administrative Hearings
5645The DeSoto Building
56481230 Apalachee Parkway
5651Tallahassee, Florida 32399 - 3060
5656(850) 488 - 9675 SUNCOM 278 - 9675
5664Fax Filing (850) 921 - 6847
5670www.doah.state.fl.us
5671Filed with th e Clerk of the
5678Division of Administrative Hearings
5682this 9 th day of August , 2006 .
5690ENDNOTES
56911/ Ms. Alderman did not participate in the final hearing but
5702was substituted as counsel for Mr. Smith, who left the firm of
5714Akerman Senterfitt after the conclusion of the final hearing.
57232/ Although the parties pre - marked a number of exhibits as
"5735Joint Exhibits," the parties reserved the right to object to
5745the admission of these exhibits. Therefore, the joint exhibits
5754were only admitted if requested by a party and after any
5765objections thereto were overruled.
57693/ The parties' pre - hearing stipulations include a stipulation
5779that the wetland mitigation authorized in the Original ERP was
5789within the Shingle Creek Drainage Basin. However, there is
5798evidence in the record contradicting that stipulation. The
5806County's witness, Stuart Bradow, expressed the opinion that the
5815assignment of mitigation credit under the Original ERP to the
5825small portion of the FMB located in the Shingle Creek Drainage
5836Basin was arbitrary because i t did not equate to actual
5847environmental benefits occurring there. His opinion was based
5855largely on the small size of the FMB area within the Basin and
5868the number of mitigation credits previously purchased from the
5877FMB and assigned to that Basin.
58834/ Pet itioner argues that Mr. Atkins ' opinion that the proposed
5895mitigation project is engineered properly does not provide
5903reasonable assurances because all of the data and analysis that
5913support his opinion were not presented at the hearing in this
5924case. Howeve r, Petitioner did not object at the hearing to
5935Mr. Atkins' opinion for lack of foundation, and an expert
5945opinion is not insufficient to support a finding merely because
5955the data upon which the opinion is based is not all described by
5968the witness or contai ned in exhibits admitted into the record.
5979It is the obligation of the cross - examining party to enquire
5991into the factual basis of an expert opinion and to demonstrate
6002that the factual basis is insufficient to support the opinion.
6012See § 90.705, Fla. Stat. (2005). Petitioner's cross - examination
6022of Mr. Atkins and Ms. Elfers on this subject did not reveal
6034evidence that the project would not function properly.
6042Petitioner also objected to Mr. Atkins' testimony as being
6051beyond the scope of rebuttal and more pro perly part of the
6063County's prima facie case. However, the objection was raised
6072after the testimony was given. Furthermore, Petitioner
6079misapprehends the nature of a permit applicant's prima facie
6088case. A permit applicant is not required to prove all the facts
6100associated with a proposed project (which can number in the tens
6111of thousands) as part of his prima facie case. It is the
6123responsibility of the challenger to present factual issues in
6132dispute, at which point the applicant may offer new evidence in
6143r ebuttal. Department of Transportation v. J.W.C. Company , Inc. ,
6152396 So. 2d 778 (Fla. 1st DCA 1981). Mr. Atkins' testimony was
6164proper rebuttal to the testimony of Mr. Odom that there was
6175insufficient engineering data to determine that the mitigation
6183site w ould function as proposed.
61895/ Unless otherwise indicated, all references to Florida
6197Statutes are to the 2005 codification.
6203COPIES FURNISHED :
6206Peter Cocotos, Esquire
6209South Florida Water Management District
62143301 Gun Club Road, M ail S top C ode - 1410
6226West Pa lm Beach, Florida 33406
6232Eric T. Olsen, Esquire
6236Hopping Green & Sams, P.A.
6241Post Office Box 6526
6245Tallahassee, Florida 32314 - 6526
6250Ol g a Sanchez de Fuentes , Esquire
6257Office of the County Attorney
62621 Courthouse Square, Suite 4200
6267Kissimmee, Florida 34741 - 5440
6272Stuart N. Bradow
6275Habitat Restoration, Inc.
6278484 North Causeway
6281New Smyrna Beach, Florida 32169
6286Timothy A. Smith, Esquire
6290Silvia Morell Alderman, Esquire
6294Akerman Senterfitt
6296106 East College Avenue, Suite 1200
6302Tallahassee, Florida 32301
6305Carol Ann Wehle, Executive Director
6310South Florida Water Management District
63153301 Gun Club Road
6319West Palm Beach, Florida 33416 - 4680
6326NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6332All parties have the right to submit written exceptions within
634215 days from the date of this Recommen ded Order. Any exceptions
6354to this Recommended Order should be filed with the agency that
6365will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 08/10/2006
- Proceedings: Transmittal letter from Ann Cole forwarding Oscela County`s Exhibit No. 8 to the Agency.
- PDF:
- Date: 08/09/2006
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 08/09/2006
- Proceedings: Letter to Judge Canter from S. Alderman enclosing a copy of County Exhibit 8 filed (exhibit not available for viewing).
- PDF:
- Date: 08/09/2006
- Proceedings: Recommended Order (hearing held March 14 and 15, 2006). CASE CLOSED.
- PDF:
- Date: 06/19/2006
- Proceedings: Respondent, South Florida Water Management District`s Proposed Recommended Order filed.
- PDF:
- Date: 05/17/2006
- Proceedings: Order Granting Extension of Time (proposed recommended orders to be filed by June 19, 2006).
- PDF:
- Date: 05/12/2006
- Proceedings: Stipulation and Joint Motion to Extend Time Period for Filing Proposed Recommended Orders filed.
- Date: 05/10/2006
- Proceedings: Transcript of Proceedings (Volumes 1-4) filed.
- PDF:
- Date: 04/12/2006
- Proceedings: Letter to Judge Canter from S. Alderman regarding the transcript of the final hearing filed.
- Date: 03/14/2006
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 03/13/2006
- Proceedings: Amendment to Prehearing Stipulation to List Additional Exhibits filed.
- PDF:
- Date: 03/08/2006
- Proceedings: Notice of Service of Respondent Osceola County`s Answers to Interrogatories filed.
- PDF:
- Date: 02/27/2006
- Proceedings: Prehearing Stipulation of Habitat Restoration Inc., South Florida Water Management District and Kevin Burkett filed.
- PDF:
- Date: 02/27/2006
- Proceedings: Notice of Unavailability of Petitioner`s Counsel, Eric T. Olsen for Dates February 28, 2006 until March 6, 2006 filed.
- PDF:
- Date: 02/09/2006
- Proceedings: Notice of Service of Kevin Burkett`s Response to Respondent`s First Set of Interrogatories filed.
- PDF:
- Date: 01/19/2006
- Proceedings: Respondent, South Florida Water Management District`s Notice of Service of Answers to Petitioner`s First Set of Interrogatories filed.
- PDF:
- Date: 01/18/2006
- Proceedings: Respondent, South Florida Water Management District`s Notice of Serving First Set of Interrogatories to Petitioner, Kevin Burkett filed.
- PDF:
- Date: 01/10/2006
- Proceedings: Notice of Service of Petitioner Kevin Burkett`s First Interrogatories to Respondent Osceola County filed.
- PDF:
- Date: 12/29/2005
- Proceedings: Notice of Service of Petitioner Kevin Burkett`s First Interrogatories to Respondent South Florida Water Management District filed.
- PDF:
- Date: 12/20/2005
- Proceedings: Notice of Hearing (hearing set for March 14 and 15, 2006; 9:00 a.m.; Orlando, FL).
- PDF:
- Date: 11/23/2005
- Proceedings: South Florida Water Management District`s Staff Report Covering Permit Application filed.
Case Information
- Judge:
- BRAM D. E. CANTER
- Date Filed:
- 11/23/2005
- Date Assignment:
- 11/30/2005
- Last Docket Entry:
- 01/06/2016
- Location:
- Orlando, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
Counsels
-
Silvia Morell Alderman, Esquire
Address of Record -
Stuart N. Bradow
Address of Record -
Peter Cocotos, Esquire
Address of Record -
Eric T. Olsen, Esquire
Address of Record -
Timothy A. Smith, Esquire
Address of Record -
Jo O Thacker, Esquire
Address of Record -
Eric T Olsen, Esquire
Address of Record