05-004454BID
Merkury Corporation, D/B/A Merkury Development vs.
Department Of Management Services
Status: Closed
Recommended Order on Monday, July 10, 2006.
Recommended Order on Monday, July 10, 2006.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8MERKURY CORPORATION, d/b/a )
12MERKURY DEVELOPMENT, )
15)
16Petitioner, )
18)
19vs. ) Case No. 05 - 4454BID
26)
27DEPARTMENT OF MANAGEMENT )
31SERVICES, )
33)
34Respondent, )
36)
37and )
39)
40E.L.C.I. CONSTRUCTION GROUP, )
44INC., )
46)
47Intervenor. )
49)
50RECOMMENDED ORDER
52This case came before Administrative Law Judge John G.
61Van Laningham for final hearing on April 27, 2006, in Miami,
72Florida.
73APPEARANCES
74For Petitioner: Jose ph K. Hall, Esquire
81Law Office of Joseph K. Hall,
87Esquire, P.A.
895721 Southeast 17th Street
93Plantation, Florida 33301
96For Respondent: Clifford A. Taylor, Esquire
102Department of Management Services
1064050 Esplanade Way, Suite 160D
111Talla hassee, Florida 32399 - 0950
117For Intervenor: Joel M. Aresty, Esquire
123Joel M. Aresty, P.A.
12711077 Biscayne Boulevard
130Penthouse
131Miami, Florida 33161
134STATEMENT OF THE ISSUES
138The issues in this bid protest are whether Intervenor's bid
148materi ally deviated from the project specifications and, if so,
158whether Respondent's preliminary decision to award Intervenor
165the construction contract at issue was clearly erroneous,
173arbitrary or capricious, or contrary to competition.
180PRELIMINARY STATEMENT
182R espondent Department of Management Services issued an
190Invitation to Bid for the purpose of soliciting proposals from
200contractors interest ed in building classrooms for the ICARE
209Baypoint School, a Department of Juvenile J ustice facility. Six
219bids were rece ived and opened on September 22, 2005. On
230October 17, 2005, Respondent announced its intent to award the
240construction contract to Intervenor E.L.C.I. Construction Group,
247Inc.
248Petitioner Merkury Corporation filed a formal written
255protest of the intended award on October 20, 2005. The case was
267referred to the Division of Administrative Hearings, where the
276protest petition was filed on December 8, 2005.
284At a scheduling conference on December 16, 2005, the
293parties agreed that the case could probably be deci ded without
304an evidentiary hearing, and it was decided with the parties'
315input and consent that the undersigned would defer setting a
326final hearing until after the parties had filed a joint
336stipulation of facts, which would be due no later than
346January 6, 2006. 1 That date was nearly a month after the
358undersigned's receipt of the protest petition; by agreeing to
367it, as they did, the parties waived their right to an expedited
379hearing. 2
381On December 29, 2006, Respondent filed a Motion to
390Relinquish Jurisdic tion. That particular motion gave rise to a
400briefing schedule that extended into February 2006. The
408parties, who had input into this schedule, consistently told the
418undersigned that they continued to believe the case probably
427could be resolved without a formal hearing.
434On February 1, 2006, while Respondent's Motion to
442Relinquish Jurisdiction was pending, Petitioner moved for leave
450to amend its formal protest and, on February 21, 2006, was
461granted permission to do so. Petitioner's Amended Bid Protest
470r aised new protest grounds, giving rise to genuine disputes of
481material fact. Consequently, Respondent's Motion to Relinquish
488Jurisdiction was denied and the final hearing scheduled.
496On March 16, 2006, Intervenor filed a Petition in
505Intervention, which th e undersigned granted on March 27, 2006.
515The final hearing took place on April 27, 2006, as
525scheduled, with all parties present. In its case, Petitioner
534elicited testimony from its corporate president, Paul A. Tolles,
543as well as from Moises Bichachi, t he vice president of
554Intervenor. In addition, Petitioner's Exhibits 1 and 2 were
563received in evidence.
566Respondent offered the testimony of its Project Manager,
574Jere Lahey. Respondent also offered 347 Bates - numbered pages of
585exhibits, which were admitted into evidence without objection.
593The final hearing transcript was filed on May 26, 2006,
603making the proposed recommended orders due on June 1, 2006,
613pursuant to the schedule established at the conclusion of the
623final hearing. Respondent timely filed a Pro posed Recommended
632Order. Petitioner's late - filed Proposed Recommended Order was
641accepted out - of - time, as was Intervenor's. All of the parties'
654post - hearing submissions were carefully considered during the
663preparation of this Recommended Order.
668Unless o therwise indicated, citations to the Florida
676Statutes refer to the 2005 Florida Statutes.
683FINDINGS OF FACT
6861. Pursuant to an Invitation to Bid (the "ITB"),
696Respondent Department of Management Services ("DMS") solicited
705bids on a project known as the ICAR E Baypoint School Classroom
717Addition (the "Project"). 3 Bids were due on September 22, 2005.
7292. As a condition of submitting a bid, interested
738contractors needed first to be "prequalified" by DMS. DMS
747prequalified Petitioner Merkury Corporation ("Merku ry") and
756Intervenor E.L.C.I. Construction Group, Inc., ("ELCI"), among
765several others.
7673. Each bidder was required to submit a "Base Bid" ( i.e.
779the total price for all work, including labor and materials,
789specified in the ITB), together with a price fo r each of six
802numbered "Alternates." 4 The contract would be awarded to the
812responsive bidder offering the lowest bid, the latter being
821defined as, generally speaking, the bid proposing the lowest
830aggregate price on the Base Bid plus the cost(s) of any
841Alt ernate(s) chosen by DMS. 5
8474. Of interest in this case is Alternate No. 1, which, in
859the ITB as originally issued, appeared as follows:
867Alternate No. 1 Allowance for Owner [=DMS]
875contribution for buried feeder conduit to
881the electrical transformer (O wner will
887provide number).
889Alternate No. 1 referred to the work described in the
900Electrical Site Plan (which was part of the ITB) that would be
913necessary to bring electricity to the Project (hereafter, the
"922electric service connection"). In brief, esta blishing the
931electric service connection entailed installing the wiring
938between the electrical panel in the new building and the nearest
949transformer, which latter belonged to the local electric
957company, Florida Power & Light ("FP&L").
9655. DMS knew that the Project would need power. Thus,
975Alternate No. 1 was not optional, as the nomenclature might
985suggest. But the cost of establishing the electric service
994connection would be largely dependent on factors exclusively
1002within FP&L's control. And as of the time the ITB was issued,
1014DMS had been unable to obtain from FP&L sufficient information
1024to allow bidders accurately to estimate the cost of this
1034particular item. The purpose of Alternate No. 1, therefore, was
1044to make the electric service connection a non - competitive item.
1055This would be accomplished by DMS's providing prospective
1063bidders with a cost estimate based on information to be obtained
1074from FP&L. DMS expected that each competing contractor would
1083bid the same amount on Alternate No. 1, namely, the amount that
1095DMS had provided.
10986. As initially defined, however, Alternate No. 1 was
1107somewhat confusing, and at the pre - bid meeting in early
1118September 2005, an issue was raised about DMS's intent regarding
1128this item. As a result, Addendum No. 1 to the I TB, which was
1142issued on September 8, 2005, to address questions raised at the
1153pre - bid meeting, included the following:
1160ADDENDUM NO. 1 ITEM NO. 5: An allowance
1169shall be carried for the cost of new service
1178connection from new transformer to nearest
1184FP & L point of service. Owner will provide
1193budget number to be carried for this
1200allowance.
1201This addendum amended the description of Alternate No. 1, making
1211clearer (it was believed) DMS's intent that the electric service
1221connection not be a point of competi tion between the bidders, as
1233each would carry, as an allowance, the Owner - provided budget
1244number for this item.
12487. Unfortunately for everyone concerned, DMS never
1255provided the interested contractors the budget number reflecting
1263the estimated cost of esta blishing the electric service
1272connection. 6 Consequently, none of the bidders proposed a dollar
1282figure for Alternate No. 1. Instead, each responded to
1291Alternate No. 1 by stating, in effect, that the requested
1301allowance could not be provided according to t he specifications
1311(which unambiguously instructed that DMS would provide the
1319number to be carried for this allowance).
13268. To be sure, the bidders' respective responses to
1335Alternate No. 1 were not identical. Merkury, for example, wrote
"1345N/A," which is co mmonly understood to mean "not applicable."
1355ELCI's bid proposal, on the other hand, stated, "By Owner."
1365Merkury argues that the phrase "By Owner" means that DMS, rather
1376than ELCI, should be responsible for establishing at DMS's
1386expense the electric ser vice connection. The undersigned
1395rejects this interpretation of ELCI's bid as unpersuasive and
1404unsupported by the greater weight of the evidence. In the
1414instant context, the phrase "By Owner" is most readily and
1424reasonably understood, objectively, as bei ng functionally the
1432equivalent of "N/A." ELCI was simply expressing the idea that
1442the budget number (not the work) would be provided by DMS a
1455reasonable response, given the language of Alternate No. 1. In
1465sum, despite some differences in wording, every one of the
1475responses to Alternate No. 1, including ELCI's, was the product
1485of the bidder's inability, in the absence of the Owner - provided
1497budget number, to carry as an allowance the Owner - provided
1508budget number.
15109. Of the five contractors who timely sub mitted a bid
1521proposal, Merkury's Base Bid of $2,874,597 was the lowest,
1532followed closely by ELCI's Base Bid of $2,877,000. DMS decided
1544to take all six Alternates, however, and after the additional
1554costs were added, ELCI was deemed the lowest responsive bi dder,
1565Merkury the second lowest. Accordingly, on October 17, 2005,
1574DMS announced its intent to accept ELCI's bid in toto and award
1586ELCI the contract for the Project.
159210. Protesting the intended award, Merkury takes the
1600position that DMS's failure to pr ovide the budget number for
1611Alternate No. 1 effectively rendered this item a nullity,
1620compelling the bidders to include in their respective Base Bids
1630the cost of the electric service connection, which work remained
1640a part of the Project, by virtue of the b id specifications,
1652notwithstanding the loss of Alternate No. 1. Consistent with
1661this understanding of the effect of DMS's silence regarding the
1671budget figure, Merkury took into account the anticipated cost of
1681establishing the electric service connection w hen working up its
1691Base Bid, ultimately adding $33,388 to the bottom line as a
1703result. ELCI, in contrast, assuming that DMS eventually would
1712provide the figure for the allowance, did not factor into its
1723Base Bid calculation the cost of the electric servic e
1733connection.
173411. ELCI guessed correctly, for in choosing Alternate
1742No. 1, DMS decided that it would provide the successful bidder
1753with the budget number when such became available and thereafter
1763pay the cost of establishing the electric service connect ion via
1774a change order. Merkury maintains that DMS should have rejected
1784ELCI's bid as materially non - responsive (because the costs that
1795were used in preparing ELCI's Base Bid did not include the cost
1807of establishing the electric service connection) and aw arded the
1817contract to Merkury as the lowest responsive bidder.
182512. In light of Merkury's argument, it is relevant to note
1836that the ITB called for the Base Bid to be given as a lump sum,
1851without breaking out individual costs; that is, in fact, how
1861each of the six responding contractors presented their
1869respective Base Bids. Thus, there was no way for DMS to know,
1881upon opening the bids, that Merkury's Base Bid included a cost
1892component relating to the electric service connections, while
1900ELCI's did not.
1903CONCLUSIONS OF LAW
190613. DOAH has personal and subject matter jurisdiction in
1915this proceeding pursuant to Sections 120.569, 120.57(1), and
1923120.57(3), Florida Statutes, and the parties have standing.
193114. Pursuant to Section 120.57(3)(f), Florida Statutes,
1938the burden of proof rests with the party opposing the proposed
1949agency action, here Merkury. See State Contracting and
1957Engineering Corp. v. Department of Transp. , 709 So. 2d 607, 609
1968(Fla. 1st DCA 1998). Merkury must sustain its burden of proof
1979by a prep onderance of the evidence. Florida Dept. of Transp. v.
1991J.W.C. Co., Inc ., 396 So. 2d 778, 787 (Fla. 1st DCA 1981).
200415. Section 120.57(3)(f), Florida Statutes, spells out the
2012rules of decision applicable in bid protests. In pertinent
2021part, the statute pr ovides:
2026In a competitive - procurement protest, other
2033than a rejection of all bids, the
2040administrative law judge shall conduct a de
2047novo proceeding to determine whether the
2053agency's proposed action is contrary to the
2060agency's governing statutes, the agency's
2065rules or policies, or the bid or proposal
2073specifications. The standard of proof for
2079such proceedings shall be whether the
2085proposed agency action was clearly
2090erroneous, contrary to competition,
2094arbitrary, or capricious.
209716. The First District Court of Appeal has construed the
2107term "de novo proceeding," as used in Section 120.57(3)(f),
2116Florida Statutes, to "describe a form of intra - agency review.
2127The judge may receive evidence, as with any formal hearing under
2138section 120.57(1), but the object of the pr oceeding is to
2149evaluate the action taken by the agency." State Contracting ,
2158709 So. 2d at 609. In deciding State Contracting , the court
2169followed Intercontinental Properties, Inc. v. State Dept. of
2177Health and Rehabilitative Services , 606 So. 2d 380, 386 ( Fla.
21881st DCA 1992), an earlier decision it actually predates the
2199present version of the bid protest statute in which the court
2211had reasoned:
2213Although the hearing before the hearing
2219officer was a de novo proceeding, that
2226simply means that there was an evi dentiary
2234hearing during which each party had a full
2242and fair opportunity to develop an
2248evidentiary record for administrative review
2253purposes. It does not mean, as the hearing
2261officer apparently thought, that the hearing
2267officer sits as a substitute for th e
2275Department and makes a determination whether
2281to award the bid de novo. Instead, the
2289hearing officer sits in a review capacity,
2296and must determine whether the bid review
2303criteria . . . have been satisfied.
231017. In framing the ultimate issue to be decide d in this de
2323novo proceeding as being "whether the agency's proposed action
2332is contrary to the agency's governing statutes, the agency's
2341rules or policies, or the bid or proposal specifications," the
2351statute effectively establishes a standard of conduct fo r the
2361agency, which is that, in soliciting and accepting bids or
2371proposals, the agency must obey its governing statutes, rules,
2380and the project specifications. If the agency breaches this
2389standard of conduct, its proposed action is subject to
2398(recommended ) reversal by the administrative law judge in a
2408protest proceeding.
241018. Consequently, the party protesting the intended award
2418must identify and prove, by the greater weight of the evidence,
2429a specific instance or instances where the agency's conduct in
2439t aking its proposed action was either: (a) contrary to the
2450agency's governing statutes; (b) contrary to the agency's rules
2459or policies; or (c) contrary to the bid or proposal
2469specifications.
247019. It is not sufficient, however, for the protester to
2480prove m erely that the agency violated the general standard of
2491conduct. By virtue of the applicable standards of "proof,"
2500which are best understood as standards of review, 7 the protester
2511additionally must establish that the agency's misstep was: (a)
2520clearly erro neous; (b) contrary to competition; or (c) an abuse
2531of discretion.
253320. The three review standards mentioned in the preceding
2542paragraph are markedly different from one another. The abuse of
2552discretion standard, for example, is more deferential (or
2560narrow er) than the clearly erroneous standard. The bid protest
2570review process thus necessarily entails a decision or decisions
2579regarding which of the several standards of review to use in
2590evaluating a particular action. To do this requires that the
2600meaning and applicability of each standard be carefully
2608considered.
260921. The clearly erroneous standard is generally applied in
2618reviewing a lower tribunal's findings of fact. In Anderson v.
2628City of Bessemer City, N.C. , 470 U.S. 564, 573 - 74 (1985), the
2641United States Supreme Court expounded on the meaning of the
2651phrase "clearly erroneous," explaining:
2655Although the meaning of the phrase "clearly
2662erroneous" is not immediately apparent,
2667certain general principles governing the
2672exercise of the appellate court's power to
2679o verturn findings of a [trial] court may be
2688derived from our cases. The foremost of
2695these principles . . . is that "[a] finding
2704is 'clearly erroneous' when although there
2710is evidence to support it, the reviewing
2717court on the entire evidence is left with
2725th e definite and firm conviction that a
2733mistake has been committed ." . . . . This
2743standard plainly does not entitle a
2749reviewing court to reverse the finding of
2756the trier of fact simply because it is
2764convinced that it would have decided the
2771case differently . The reviewing court
2777oversteps the bounds of its duty . . . if it
2788undertakes to duplicate the role of the
2795lower court. "In applying the clearly
2801erroneous standard to the findings of a
2808[trial] court sitting without a jury,
2814appellate courts must constantl y have in
2821mind that their function is not to decide
2829factual issues de novo. " . . . . If the
2839[trial] court's account of the evidence is
2846plausible in light of the record viewed in
2854its entirety, the court of appeals may not
2862reverse it even though convinced that had it
2870been sitting as the trier of fact, it would
2879have weighed the evidence differently.
2884Where there are two permissible views of the
2892evidence, the factfinder's choice between
2897them cannot be clearly erroneous. . . . .
2906(Citations omitted)(emphas is added).
291022. The Florida Supreme Court has used somewhat different
2919language to give this standard essentially the same meaning:
2928A finding of fact by the trial court in a
2938non - jury case will not be set aside on
2948review unless there is no substantial
2954evid ence to sustain it, unless it is clearly
2963against the weight of the evidence, or
2970unless it was induced by an erroneous view
2978of the law. A finding which rests on
2986conclusions drawn from undisputed evidence,
2991rather than on conflicts in the testimony,
2998does not carry with it the same
3005conclusiveness as a finding resting on
3011probative disputed facts, but is rather in
3018the nature of a legal conclusion. . . . .
3028When the appellate court is convinced that
3035an express or inferential finding of the
3042trial court is without support of any
3049substantial evidence, is clearly against the
3055weight of the evidence or that the trial
3063court has misapplied the law to the
3070established facts, then the decision is
3076'clearly erroneous' and the appellate court
3082will reverse because the trial cou rt has
3090'failed to give legal effect to the
3097evidence' in its entirety.
3101Holland v. Gross , 89 So. 2d 255, 258 (Fla. 1956)(citation
3111omitted).
311223. Because administrative law judges are the triers of
3121fact charged with resolving disputed issues of material f act
3131based upon the evidence presented at hearing, and because bid
3141protests are fundamentally de novo proceedings, the undersigned
3149is not required to defer to the letting authority in regard to
3161any findings of objective historical fact that might have been
3171made in the run - up to preliminary agency action. It is
3183exclusively the administrative law judge's job, as the trier of
3193fact, to ascertain from the competent, substantial evidence in
3202the record what actually happened in the past or what reality
3213presently e xists, as if no findings previously had been made.
322424. If, however, the challenged agency action involves an
3233ultimate factual determination for example, an agency's
3241conclusion that a proposal's departure from the project
3249specifications was a minor irre gularity as opposed to a material
3260deviation then some deference is in order, according to the
3271clearly erroneous standard of review. 8 To prevail on an
3281objection to an ultimate finding, therefore, the protester must
3290substantially undermine the factual pred icate for the agencys
3299conclusion or convince the judge that a defect in the agency's
3310logic led it unequivocally to commit a mistake.
331825. There is another species of agency action that also is
3329entitled to review under the clearly erroneous standard:
3337inte rpretations of statutes for whose administration the agency
3346is responsible, and interpretations of the agency's own rules.
3355See State Contracting and Engineering Corp. v. Department of
3364Transp. , 709 So. 2d 607, 610 (Fla. 1st DCA 1998). In deference
3376to the agency's expertise, such interpretations will not be
3385overturned unless clearly erroneous. Id. 9
339126. This means that if the protester objects to the
3401proposed agency action on the ground that it violates either a
3412governing statute within the agency's subst antive jurisdiction
3420or the agency's own rule, and if, further, the validity of the
3432objection turns on the meaning, which is in dispute, of the
3443subject statute or rule, then the agency's interpretation should
3452be accorded deference; the challenged action sho uld stand unless
3462the agency's interpretation is clearly erroneous (assuming the
3470agency acted in accordance therewith). 10
347627. The statute requires that agency action (in violation
3485of the applicable standard of conduct) which is "arbitrary, or
3495capricious" be set aside. Earlier, the phrase "arbitrary, or
3504capricious" was equated with the abuse of discretion standard,
3513see endnote 7 , supra , because the concepts are practically
3522indistinguishable and because use of the term "discretion"
3531serves as a useful reminde r regarding the kind of agency action
3543reviewable under this highly deferential standard.
354928. It has been observed that an arbitrary decision is one
3560that is not supported by facts or logic, or is despotic. Agrico
3572Chemical Co. v. State Dept. of Environme ntal Regulation , 365 So.
35832d 759, 763 (Fla. 1st DCA 1978), cert. denied , 376 So. 2d 74
3596(Fla. 1979). Thus, under the arbitrary or capricious standard,
"3605an agency is to be subjected only to the most rudimentary
3616command of rationality. The reviewing court is not authorized
3625to examine whether the agency's empirical conclusions have
3633support in substantial evidence." Adam Smith Enterprises, Inc.
3641v. State Dept. of Environmental Regulation , 553 So. 2d 1260,
36511273 (Fla. 1st DCA 1989). Nevertheless,
3657the reviewing court must consider whether
3663the agency: (1) has considered all relevant
3670factors; (2) has given actual, good faith
3677consideration to those factors; and (3) has
3684used reason rather than whim to progress
3691from consideration of each of these factors
3698to its final decision.
3702Id.
370329. The second district framed the "arbitrary or
3711capricious" review standard in these terms: "If an
3719administrative decision is justifiable under any analysis that a
3728reasonable person would use to reach a decision of similar
3738importance, it would seem that the decision is neither arbitrary
3748nor capricious." Dravo Basic Materials Co., Inc. v. State Dept.
3758of Transp. , 602 So. 2d 632, 634 n.3 (Fla. 2d DCA 1992). As the
3772court observed, this "is usually a fact - intensive
3781determination." Id. at 6 34.
378630. Compare the foregoing "arbitrary or capricious"
3793analysis with the test for reviewing discretionary decisions:
"3801Discretion, in this sense, is abused when
3808the judicial action is arbitrary, fanciful,
3814or unreasonable, which is another way of
3821saying that discretion is abused only where
3828no reasonable man would take the view
3835adopted by the trial court. If reasonable
3842men could differ as to the propriety of the
3851action taken by the trial court, then it
3859cannot be said that the trial court abused
3867its discre tion."
3870Canakaris v. Canakaris , 382 So. 2d 1197, 1203 (Fla. 1980),
3880quoting Delno v. Market St. Ry. Co. , 124 F.2d 965, 967 (9th Cir.
38931942). Further,
3895[t]he trial court's discretionary power is
3901subject only to the test of reasonableness,
3908but that test requi res a determination of
3916whether there is logic and justification for
3923the result. The trial courts' discretionary
3929power was never intended to be exercised in
3937accordance with whim or caprice of the judge
3945nor in an inconsistent manner. Judges
3951dealing with ca ses essentially alike should
3958reach the same result. Different results
3964reached from substantially the same facts
3970comport with neither logic nor
3975reasonableness.
3976Canakaris , 382 So. 2d at 1203
398231. Whether the standard is called "arbitrary or
3990capricious" or "abuse of discretion," the scope of review, which
4000demands maximum deference, is the same. Clearly, then, the
4009narrow "arbitrary or capricious" standard of review cannot
4017properly be applied in evaluating all agency actions that might
4027be challenged in a bid protest; rather, this highly deferential
4037standard appropriately applies only to those decisions which are
4046committed to the agency's discretion.
405132. Therefore, where the protester objects to agency
4059action that entails the exercise of discretion, but onl y in such
4071instances, the objection cannot be sustained unless the agency
4080abused its discretion, i.e. acted arbitrarily or capriciously.
408833. The third standard of review articulated in Section
4097120.57(3)(f) is unique to bid protests. The "contrary to
4106com petition" test is a catch - all which applies to agency actions
4119that do not turn on the interpretation of a statue or rule, do
4132not involve the exercise of discretion, and do not depend upon
4143(or amount to) a determination of ultimate fact.
415134. Although the c ontrary to competition standard, being
4160unique to bid protests, is less well defined than the other
4171review standards, the undersigned concludes that the set of
4180proscribed actions should include, at a minimum, those which:
4189(a) create the appearance of and o pportunity for favoritism; (b)
4200erode public confidence that contracts are awarded equitably and
4209economically; (c) cause the procurement process to be genuinely
4218unfair or unreasonably exclusive; or (d) are unethical,
4226dishonest, illegal, or fraudulent. See , e.g. , R. N. Expertise,
4235Inc. v. Miami - Dade County School Bd., et al. , Case No. 01 -
42492663BID, 2002 WL 185217, *21 - *22 (Fla.Div.Admin.Hrgs. Feb. 4,
42592002 ); see also E - Builder v. Miami - Dade County School Bd. et
4274al. , Case No. 03 - 1581BID, 2003 WL 22347989, *10
4284(Fl a.Div.Admin.Hrgs. Oct. 10, 2003)
428935. Turning to the merits of this case, Merkury's argument
4299that ELCI's bid was materially non - responsive proceeds from the
4310premise that, notwithstanding DMS's failure to provide the
4318budget number as promised in the descri ption of Alternate No. 1,
4330the successful bidder is obligated under the bid specifications
4339to perform all work necessary to complete the electric service
4349connection. Building on this proposition, Merkury reasons that
4357because installation of the electric se rvice connection was an
4367essential aspect of the Project, bidders were bound to estimate
4377the cost of this work in computing their respective Base Bids
4389and to include such cost in their bids . ELCI's failure to
4401include the cost of the electric service conne ction in its Base
4413Bid, Merkury concludes, constituted a material deviation from
4421the bid specifications, for which its bid should have been
4431rejected as non - responsive.
443636. Merkury's initial premise is based on an
4444interpretation of the bid specificati ons that, while contrary to
4454DMS's, is at least plausible and perhaps reasonable. It is not
4465necessary to determine whether DMS's interpretation is clearly
4473erroneous, however, because the next step in Merkury's
4481reasoning the assertion that bidders were bou nd to include in
4493their Base Bids the cost of performance associated with the
4503electric service connection is a non sequitur. That the
4513successful bidder will be contractually obligated to perform a
4522particular piece of work does not logically compel the
4531con clusion that, to be responsive, a bidder must include the
4542cost of such work in its bid. To the contrary, where an "out
4555the door" bid price is solicited, as here, practically any bid
4566that proposes a lump - sum total cost within reason must be
4578considered resp onsive, regardless of how the bidder computed its
4588bid, or what expenses were included (or not included) therein. 11
459937. Thus, even if Merkury were correct about the meaning
4609of the bid specifications vis - à - vis the electric service
4621connection, the upshot wou ld be that ELCI underbid on the
4632Project by mistakenly omitting a material cost from its bid
4642computation but its bid would be responsive nonetheless . The
4653downside for ELCI in that event would be possibly having to
4664install the electric service connection a t a loss, because as a
4676general rule, bidders on public contracts must bear the
4685consequences of their bid computation errors. Department of
4693Transp. v. Ronlee, Inc. , 518 So. 2d 1326, 1328 (3rd DCA 1987) ,
4705rev. denied , 528 So. 2d 1183 (Fla. 1988) ; Graham v. C lyde , 61
4718So. 2d 656, 658 (Fla. 1952)("After the bid is accepted, the
4730bidder is bound by his error and is expected to bear the
4742consequence of it.") .
474738. In sum, DMS did not err in deeming ELCI's bid
4758responsive. Indeed, because DMS had no way of knowing, at the
4769time the bids were opened, what costs ELCI or the other bidders
4781had included in (or omitted from) their Base Bids, it was not
4793possible for DMS to reject ELCI's bid on the basis of the
4805alleged deviation about which Merkury has complained. That
4813being the case , accepting ELCI's bid was not contrary to any
4824governing statute, rule, or bid specification, and it is
4833concluded that DMS did not violate the applicable standard of
4843conduct in the manner that Merkury has urged. 12
485239. There having been no cogni zable violation of the
4862standard of conduct, it is concluded that the intended award
4872should stand.
4874RECOMMENDATION
4875Based on the foregoing Findings of Fact and Conclusions of
4885Law, it is RECOMMENDED that a Final Order be entered directing
4896that the proposed awa rd to ELCI be implemented in accordance
4907with DMS's intentions.
4910DONE AND ENTERED this 10th day of July, 2006, in
4920Tallahassee, Leon County, Florida.
4924S
4925___________________________________
4926JOHN G. VAN LANINGHAM
4930Administrative Law Judge
4933Division of Admini strative Hearings
4938Division of Administrative Hearings
4942The DeSoto Building
49451230 Apalachee Parkway
4948Tallahassee, Florida 32399 - 3060
4953(850) 488 - 9675 SUNCOM 278 - 9675
4961Fax Filing (850) 921 - 6847
4967www.doah.state.fl.us
4968Filed with the Clerk of the
4974Division of Admin istrative Hearings
4979this 10th day of July, 2006.
4985ENDNOTES
49861 / The parties ultimately filed a Joint Stipula tion on January
499823, 2006. The stipulated facts, being thus memorialized in the
5008record, were taken as established without need of further proof.
50182 / Section 120.57(3)(e), Florida Statutes, requires that bid
5027protests be heard within 30 days after the admin istrative law
5038judge's receipt of the formal written protest, unless the
5047parties waive the right to a prompt hearing.
50553 / The Project entails the construction of additional classrooms
5065at a facility operated by the Department of Juvenile Justice.
50754 / The c ost of an Alternate can be either positive (an increase
5089in the Base Bid) or negative (a deduction from the Base Bid).
5101In this instance, each Alternate was expected to add an
5111additional cost to the Base Bid, if accepted.
51195 / The ITB permitted DMS to selec t any, all, or none of the six
5135Alternates. If, however, DMS chose fewer than all six, then the
5146lowest bid would belong to the bidder offering the lowest price
5157for the Base Bid plus each Alternate (if any) taken in numerical
5169order . For example, if DMS wer e to select Alternate Nos. 1, 2,
5183and 4, then the relevant respective bid prices, for the purpose
5194of determining the lowest bid, would be each bidder's Base Bid
5205plus its proposed costs for Alternate Nos. 1 and 2, Alternate
5216No. 4 having been taken out of ord er.
5225In its original protest, Merkury alleged that DMS had
5234chosen Alternates out of order, effectively starting with
5242Alternate No. 2. Because Merkury (as will be seen) had
5252submitted the lowest Base Bid, Merkury alleged that DMS should
5262have designated Merkury the lowest bidder, according the ITB's
5271instructions for determining the lowest bid. Later, however,
5279Merkury moved for, and was granted, leave to file an amended
5290protest petition. The gravamen of Merkury's amended petition
5298was not, as before, DMS' s alleged miscalculation of the lowest
5309bid, but rather DMS's alleged failure to reject ELCI's bid as
5320non - responsive.
5323At hearing and in its Proposed Recommended Order, Merkury
5332focused exclusively on the alleged non - responsiveness of ELCI's
5342bid. The und ersigned has determined, therefore, that Merkury
5351abandoned its original protest ground, and accordingly that
5359issue will not be discussed further herein.
53666 / DMS blames its failure to furnish the figure on FP&L, on whom
5380DMS was still waiting, as of the dat e the bids were due, to
5394provide information believed necessary for developing a
5401reasonable cost estimate.
54047 / The term "standard of proof" as used in § 120.57(3)(f)
5416reasonably may be interpreted to reference standards of review .
5426This is because, while th e "standard of proof" sentence fails to
5438mention any common standards of proof, it does articulate two
5448accepted standards of review: (1) the "clearly erroneous"
5456standard and (2) the abuse of discretion (="arbitrary, or
5466capricious") standard. (The "contrar y to competition"
5474standard whether it be a standard of proof or standard of
5486review is unique to bid protests.)
54938 / An ultimate factual determination is a conclusion derived by
5504reasoning from objective facts; it frequently involves the
5512application of a legal principle or rule to historical facts:
5522e.g. the driver failed to use reasonable care under the
5532circumstances and therefore was negligent; and it may be infused
5542with policy considerations. Reaching an ultimate factual
5549finding requires that judgmen t calls be made which are unlike
5560those that attend the pure fact finding functions of weighing
5570evidence and choosing between conflicting but permissible views
5578of reality.
55809 / From the general principle of deference follows the more
5591specific rule that an a gency's interpretation need not be the
5602sole possible interpretation or even the most desirable one; it
5612need only be within the range of permissible interpretations.
5621State Bd. of Optometry v. Florida Soc. of Ophthalmology , 538 So.
56322d 878, 885 (Fla. 1st DCA 1988); see also Suddath Van Lines,
5644Inc. v. State Dept. of Environmental Protection , 668 So. 2d 209,
5655212 (Fla. 1st DCA 1996). However, "[t]he deference granted an
5665agency's interpretation is not absolute." Department of Natural
5673Resources v. Wingfield Devel opment Co. , 581 So. 2d 193, 197
5684(Fla. 1st DCA 1991). Obviously, an agency cannot implement any
5694conceivable construction of a statute or rule no matter how
5704strained, stilted, or fanciful it might be. Id. Rather, "only
5714a permissible construction" will be upheld by the courts.
5723Florida Soc. of Ophthalmology , 538 So. 2d at 885. Accordingly,
"5733[w]hen the agency's construction clearly contradicts the
5740unambiguous language of the rule, the construction is clearly
5749erroneous and cannot stand." Woodley v. Departme nt of Health
5759and Rehabilitative Services , 505 So. 2d 676, 678 (Fla. 1st DCA
57701987); see also Legal Environmental Assistance Foundation v.
5778Board of County Com'rs of Brevard County , 642 So. 2d 1081, 1083 -
579184 (Fla. 1994)("unreasonable interpretation" will not b e
5800sustained).
580110 / The same standard of review also applies, in a protest
5813following the announcement of an intended award, with regard to
5823preliminary agency action taken upon the agency's interpretation
5831of the project specifications but perhaps for a reas on other
5843than deference to agency expertise. Section 120.57(3)(b),
5850Florida Statutes, provides a remedy for badly written or
5859ambiguous specifications: they may be protested within 72 hours
5868after the posting of the specifications. The failure to avail
5878one self of this remedy effects a waiver of the right to complain
5891about the specifications per se. Consequently, if the dispute
5900in a protest challenging a proposed award turns on the
5910interpretation of an ambiguous, vague, or unreasonable
5917specification, which could have been corrected or clarified
5925prior to acceptance of the bids or proposals had a timely
5936specifications protest been brought, and if the agency has acted
5946thereafter in accordance with a permissible interpretation of
5954the specification ( i.e. one that is not clearly erroneous), then
5965the agency's intended action should be upheld not necessarily
5975out of deference to agency expertise, but as a result of the
5987protester's waiver of the right to seek relief based on a faulty
5999specification. If, however, the a gency has acted contrary to
6009the plain language of a lawful specification, then its action
6019should probably be corrected, for in that event the preliminary
6029agency action likely would be clearly erroneous or contrary to
6039competition; in that situation, there s hould be no waiver,
6049because a reasonable person would not protest an unambiguous
6058specification that facially conforms to Florida procurement law.
606611 / A bid conceivably might be so far below the range of
6079reasonable bids as to be deemed non - responsive, or t o cause the
6093bidder to be rejected as not responsible, but such a situation
6104would be unusual, and in any event would be readily
6114distinguishable from the present case, where none of the bids
6124was patently ridiculous.
612712 / DMS's failure to provide the budget n umber as promised in
6140connection with Alternate No. 1, which seems clearly to have
6150been contrary to the bid specifications, is another matter. It
6160is unnecessary, however, and would be inappropriate to boot, to
6170decide whether that misstep constitutes revers ible error under
6179the applicable standard of review, for Merkury did not raise the
6190matter as a protest ground.
6195COPIES FURNISHED :
6198Joseph K. Hall, Esquire
6202Law Office of Joseph K. Hall, Esquire, P.A.
62105721 Southeast 17th Street
6214Plantation, Florida 33301
6217Joel M. Aresty, Esquire
6221Joel M. Aresty, P.A.
622511077 Bi scayne Boulevard
6229Penthouse
6230Miami, Florida 33161
6233Clifford A. Taylor, Esquire
6237Department of Management Services
62414050 Esplanade Way, Suite 160D
6246Tallahassee, Florida 32399 - 0950
6251Tom Lewis, Jr., Secretary
6255Department of Management Services
62594050 Esplanade Way
6262Tallahassee, Florida 32399 - 0950
6267Steven S. Ferst, General Counsel
6272Department of Management Services
6276Post Office Box 9000
6280Tallahassee, Florida 32399 - 9000
6285NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6291All parties have the right to submit written exceptions with in
630210 days from the date of this Recommended Order. Any exceptions
6313to this Recommended Order should be filed with the agency that
6324will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/10/2006
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 06/22/2006
- Proceedings: Reply to Petitioner`s Belatedly Filed Proposed Recommended Order filed.
- PDF:
- Date: 06/19/2006
- Proceedings: Order Denying Motion to Strike (Department shall have until June 30, 2006, to file a reply to Merkury`s proposed recommended order).
- PDF:
- Date: 06/15/2006
- Proceedings: Response to Respondent`s Motion to Strike Petitioner`s Proposed Recommended Order filed.
- PDF:
- Date: 06/14/2006
- Proceedings: (Proposed) Order Allowing Withdrawal of Attorney of Record and Allowing Substitution of Attorney of Record filed.
- PDF:
- Date: 06/14/2006
- Proceedings: Letter to Judge Van Laningham from J. Hall enclosing original exhibits from the Final Hearing filed (Hearing exhibits not available for viewing).
- Date: 06/06/2006
- Proceedings: Transcript filed.
- PDF:
- Date: 06/05/2006
- Proceedings: Order Regarding the Transcript and Proposed Recommended Orders (Motion to Enlarge is granted; Merkury shall file a proposed recommended order no later than June 8, 2006; Department shall have until June 15, 2006, to file a reply to Merkury`s proposed recommended order).
- PDF:
- Date: 05/24/2006
- Proceedings: Motion to Direct Court Reporter to Correct Court Transcript filed.
- PDF:
- Date: 05/23/2006
- Proceedings: Order Regarding Proposed Recommended Orders (proposed recommended orders due by June 1, 2006).
- Date: 05/22/2006
- Proceedings: Transcript filed.
- Date: 04/27/2006
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 04/26/2006
- Proceedings: Response in Opposition to Motion to Allow Rebuttal Witness to Appear by Telephone filed.
- PDF:
- Date: 04/25/2006
- Proceedings: Amended Motion for Rebuttal Witnesses to Appear by Telephone filed.
- PDF:
- Date: 04/13/2006
- Proceedings: Amended Notice of Taking Depositions of Paul Tolles and Ruben Alen filed.
- PDF:
- Date: 03/14/2006
- Proceedings: Motion to Set Earlier Trial Date, Consistent with the Expedited Timeframes Specified in Section 120.57(3)(e), Florida Statutes for BID Protests filed.
- PDF:
- Date: 03/07/2006
- Proceedings: Notice of Hearing (hearing set for April 27, 2006; 9:00 a.m.; Miami, FL).
- PDF:
- Date: 02/21/2006
- Proceedings: Order on Pending Motions (parties shall confer and notify the undersigned in writing, no later than March 3, 2006, of several mutually agreeable dates for the final hearing).
- PDF:
- Date: 02/03/2006
- Proceedings: Order Enlarging Time (Respondent`s Motion is granted, deadline for replying in support of Respondent`s Motion to Relinquish Jurisdiction is enlarged to February 10, 2006).
- PDF:
- Date: 02/01/2006
- Proceedings: Petitioner`s Response in Opposition to Respondent`s Motion to Relinquish Jurisdiction filed.
- PDF:
- Date: 01/31/2006
- Proceedings: Order Enlarging Time (Petitioner`s Motion is granted, deadline for responding to Respondent`s Motion to Relinquish Jurisdiction is enlarged to January 31, 2006).
- PDF:
- Date: 01/18/2006
- Proceedings: Order Scheduling Responses to Motion to Relinquish (no later than January 20, 2006, parties shall file a Joint Stipulation of Material Facts, no later than January 27, 2006, Merkury shall file a response to the Motion, no later than February 3, 2006, DMS shall file a reply in support of its Motion) .
Case Information
- Judge:
- JOHN G. VAN LANINGHAM
- Date Filed:
- 12/08/2005
- Date Assignment:
- 12/08/2005
- Last Docket Entry:
- 07/24/2006
- Location:
- Miami, Florida
- District:
- Southern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
Joel M. Aresty, Esquire
Address of Record -
Joseph K Hall, Esquire
Address of Record -
Clifford A. Taylor, Esquire
Address of Record