06-003288
Manasota-88, Inc. And Roy R. Lewis, Iii vs.
Department Of Environmental Protection And Manatee County Port Authority
Status: Closed
Recommended Order on Tuesday, February 6, 2007.
Recommended Order on Tuesday, February 6, 2007.
1Case No. 06-3288
4STATE OF FLORIDA
7DIVISION OF ADMINISTRATIVE HEARINGS
11MANASOTA-88, INC. and ROY R. ) ) ) ) ) ) ) ) ) ) ) ) )
29LEWIS, III,
31RECOMMENDED ORDER
33Petitioners,
34vs.
35DEPARTMENT OF ENVIRONMENTAL
38PROTECTION and MANATEE COUNTY
42PORT AUTHORITY,
44Respondents.
45On October 30-31 and November 1, 2006, a final
54administrative hearing was held in this case in Bradenton,
63Florida, before J. Lawrence Johnston, Administrative Law Judge
71(ALJ), Division of Administrative Hearings (DOAH).
77APPEARANCES
78For Petitioners Manasota-88, Inc. and Roy R. Lewis, III:
87John R. Thomas, Esquire
91Thomas & Associates, P.A.
95233 Third Street North, Suite 101
101St. Petersburg, Florida 33701-3818
105For Respondent Department of Environmental Protection:
111W. Douglas Beason, Esquire
115Department of Environmental Protection
119The Douglas Building, Mail Station 35
1253900 Commonwealth Boulevard
128Tallahassee, Florida 32399-3000
131For Manatee County Port Authority:
136Kevin S. Hennessy, Esquire
140R. David Jackson, Esquire
144Lewis, Longman & Walker, P.A.
1491001 Third Avenue West, Suite 670
155Bradenton, Florida 34205-7848
158STATEMENT OF THE ISSUES
162The issues in this case are: whether the Department of
172Environmental Protection (DEP) should modify an Environmental
179Resource Permit (ERP) held by the Manatee County Port Authority
189(the Port) for expansion of its facilities at Port Manatee by
200eliminating a specific condition (SC) that prohibits the opening
209and use of those expanded facilities before DEP's "final success
219determination" concerning the Port's related seagrass mitigation
226ERP; and whether attorney's fees should be awarded.
234PRELIMINARY STATEMENT
236On February 10, 2005, the Port applied for modification of
246SC 5 of its ERP. DEP twice requested additional information
256relating to how the Port would provide reasonable assurance with
266respect to the requested permit modification, and the Port
275responded with additional information that was reviewed by DEP.
284On April 7, 2006, DEP gave notice of its intent to approve
296the requested modification and issued a draft permit modification
305that also included modifications to the related seagrass
313mitigation ERP that were not requested by the Port. After DEP
324extended the time for the Port to file a petition, DEP and the
337Port met on July 5, 2006, and DEP issued a revised Notice of
350Intent (NOI) and revised draft permit modification that granted
359the Port's application without the additional modifications.
366On July 19, 2006, Manasota-88, Inc., and Roy R. Lewis, III
377(Robin Lewis) timely petitioned for a formal administrative
385hearing challenging the NOI and revised draft permit modification
394and seeking to reinstate the NOI and draft permit modification
404issued in April. DEP dismissed the petition with leave to amend
415based on DEP's determination that the petition included
423insufficient allegations as to how Petitioners' substantial
430interests were affected by the proposed agency action. On
439August 21, 2006, Petitioners filed an Amended Petition for Formal
449Administrative Proceeding (Petition), which DEP referred to
456(DOAH).
457On September 8, 2006, the Port filed a Motion to Dismiss
468with Prejudice and a Motion to Expedite Final Hearing. On
478September 15, 2006, the final hearing was scheduled for
487October 11 and 12, 2006. On September 19, 2006, the Motion to
499Dismiss was denied, and the Motion to Expedite was granted,
509requiring discovery responses within 15 days.
515On September 26 and 27, 2006, Petitioners filed a Motion to
526Impose Expedited Deposition Transcript Costs and an Emergency
534Motion to Continue Hearing and to Compel Discovery. A telephonic
544hearing was held on September 29, 2006, and the final hearing was
556continued until October 30-31 and November 1, 2006.
564On October 27, 2006, the parties filed a Pre-Hearing
573Stipulation, and the Port filed a Motion in Limine seeking to
584exclude evidence relating to: other permits issued to the Port;
594DEP's Consent Order OGC File No. 05-2790; and seagrass mitigation
604success credit determinations made by DEP. The Port also filed a
615Motion for Attorney's Fees.
619At the onset of the final hearing, the Motion in Limine was
631argued and denied.
634During the final hearing, the Port, as applicant, called as
644witnesses: George F. Isiminger, Director of Engineering and
652Environmental Affairs for the Port Authority; Stephen G. Swingle,
661an environmental scientist; Raymond F. Dennis, III, an ecologist
670responsible for the monitoring of the sea grass mitigation at
680Port Manatee; and Thomas F. Ries, the current seagrass mitigation
690supervisor for the Port Manatee expansion project. The Port also
700designated excerpts from the deposition transcripts of
707Janet Llewellyn, Deputy Director of the DEP's Division of Water
717Resource Management, and Martin Seeling, an environmental
724administrator with the DEP, for admission as Port Exhibits 17 and
73518. The other parties added excerpts for consideration as part
745of the exhibits. The Port also offered Port Exhibits 1 through
75613, 15, 16, and 19 through 21, which were admitted in evidence
768without objection, along with Port Exhibits 17 and 18.
777Petitioners called two witnesses: Robin Lewis, who is an
786environmental consultant and the former seagrass mitigation
793supervisor for the Port Manatee expansion project; and Glenn
802Compton, Chairman of Manasota-88. Petitioners also had their
810Exhibits 3, 9, 24, 26, 34, 37, 41, 57, 64, 66, 69, 75, 88, 90,
82593, 96 through 101, 105 through 108, and 116 admitted in
836evidence. Ruling was reserved on objections to Petitioners'
844Exhibits 21 and 109, which are sustained.
851In rebuttal, the Port re-called Mr. Dennis and also called
861David Crewz of the Fish and Wildlife Research Institute.
870After presentation of evidence, the parties arranged for
878preparation of a Transcript of the final hearing; the parties
888were given ten days from the filing of the Transcript in which to
901file proposed recommended orders (PROs); and the record was
910closed. However, at that point, Petitioners inquired about the
919status of the transcripts of the depositions of Don Deis and
930Cheryl Miller, consultants for DEP on seagrass mitigation
938success, which were filed at the outset of the proceedings but
949deferred pending an assessment of the need for them to be made
961after the presentation of other evidence; and the record was re-
972opened to reflect Petitioners' request that those transcripts be
981placed in evidence and to allow the other parties to respond.
992When the Port objected, the transcripts were marked as
1001Petitioners' Exhibits 117 and 118, and the parties were given an
1012opportunity to file argument on their admissibility and to
1021designate excerpts from the transcripts to be considered, if
1030admitted. Written arguments on admissibility and all
1037designations, together with the Port's additional objections to
1045certain designations, were filed by November 13, 2006. Based on
1055the written arguments, the objections are overruled, and the
1064designated portions of Petitioners' Exhibits 117 and 118 are
1073admitted in evidence.
1076On November 13, 2006, Petitioners also filed a Request for
1086Official Recognition of the Florida Conceptual State Land
1094Management Plan and ERP No. 0129291-003-EI (with related NOI),
1103which were identified as Petitioners' Exhibit 1 and 5,
1112respectively (although Petitioners also proposed that the latter
1120be identified as Petitioners' Exhibit 119). The other parties
1129filed objections, which are overruled; and the Request for
1138Official Recognition is granted.
1142The Transcript (745 pages in six volumes) was filed on
1152December 11, 2006. The parties filed timely PROs. In addition,
1162Petitioners filed a Motion for SLAPP Fees and Response to Port
1173Manatee Fee Motion. (The PROs filed by Petitioners and the Port
1184also addressed the Port's Motion for Attorney's Fees.) On
1193January 2, 2007, the Port filed a Response in Opposition to
1204Petitioners' Motion for SLAPP Fees. On January 3, 2007,
1213Petitioners filed an Amended PRO in compliance with the 40-page
1223limit in Florida Administrative Code Rule 28-106.215. (Unless
1231otherwise indicated, all rule references are to the current
1240Florida Administrative Code, and all statute references are to
1249the 2006 codification of the Florida Statutes.)
1256FINDINGS OF FACT
1259A. The Parties
12621. DEP is an executive agency of the State of Florida under
1274Article IV, Section 6, of the Florida Constitution. DEP
1283administers the Environmental Resource Permit Program pursuant to
1291Chapter 373, Part IV, Florida Statutes, for various activities,
1300including "dredging and filling" by Florida's seaports.
13072. The Port operates and sets policy for Port Manatee, a
1318public deepwater commercial seaport located in the northern part
1327of Manatee County on Tampa Bay.
13333. Manasota-88, Inc., is a Florida corporation not for
1342profit that has at least 25 current members residing within
1352Manatee County. Manasota-88 was formed, more than one year
1361before the Port filed its application for the permit modification
1371that is the subject of this proceeding, for the purposes of
1382protection of public health and the environment, fish and
1391wildlife resources, and air and water quality.
13984. A substantial number of the members of Manasota-88 fish,
1408swim and snorkel, watch birds, and enjoy wild life observation in
1419Tampa Bay around Port Manatee.
14245. Robin Lewis is president and principal ecologist for
1433Lewis Environmental Services, Inc., an environmental consulting
1440firm. Mr. Lewis is a wetlands scientist with extensive expertise
1450in ecology, restoration, and creation of marshes, mangrove
1458forests, and seagrass meadows.
14626. Robin Lewis had been involved in many projects relating
1472to seagrass protection and restoration in Tampa Bay and the area
1483where the Project is located. At the inception of the Port
1494Manatee expansion project, Mr. Lewis objected to the Port's
1503underestimation of the acreage of seagrass that would be impacted
1513by the expansion project. Mr. Lewis was subsequently hired by
1523the Port on a contract basis to map seagrass in the impact and
1536mitigation areas of the Port's expansion project.
15437. Mr. Lewis owns two boats that he sometimes uses for
1554fishing and shallow water recreation. The boats are equipped
1563with poles so that he can pole into motorized vessel restriction
1574zones. Mr. Lewis has fished the area around Port Manatee many
1585times over the course of most of his adult life. Mr. Lewis is
1598also a wildlife and bird watching enthusiast. The Tampa Bay area
1609around Port Manatee, including the area of project impacts and
1619the mitigation areas, provide opportunities for wildlife
1626observation and bird-watching, and Mr. Lewis has engaged in those
1636activities in the Port Manatee area many times over the years.
1647B. DEP Permits, Port Authority Application, and
1654Mitigation Credit Correspondence
16578. In August 1994, the Port began the permitting process
1667for a substantial expansion of Port Manatee by applying to DEP's
1678Bureau of Beaches and Coastal Systems for authorization for
1687dredging and filling and other activities in the coastal waters
1697and wetlands around Port Manatee.
17029. In December 1999, the Board of Trustees of the Internal
1713Improvement Trust Fund and DEP issued ERP No. 0129291-001-EC, a
"1723Conceptual Permit" for enlargement of the main access channel
1732at the entrance to Port Manatee, construction of a ship turning
1743basin, expansion of Berth 5, and construction of new Berths 4 and
175512 (Phase II) at Port Manatee (the Expansion Project).
176410. Conceptual Permit SC 5 provided that the Port would
1774have to obtain individual ERPs for the various conceptually
1783approved activities. The Conceptual Permit's "Description of
1790Activities" section on page 1 summarized that the Port proposed
1800to offset 12.7 acres of seagrass habitat impacts by transplanting
1810the existing seagrass and by creating, restoring, and enhancing
1819seagrass habitat in Tampa Bay.
182411. Conceptual Permit SC 9 specified that DEP had to deem
1835the seagrass mitigation to be successful before the Port could
1845initiate dredging.
184712. The requirement to achieve 12.7 seagrass mitigation
1855success credits was specified in ERP No. 0129291-002-EI (the
"1864Seagrass Mitigation Permit"), which was issued to the Port on
1875August 29, 2000. Procedures for documenting seagrass mitigation
1883success are included in the Seagrass Mitigation Permit and an
1893attached July 2000 Seagrass Mitigation Plan, authored principally
1901by Robin Lewis, which authorize and describe all of the seagrass
1912mitigation requirements for the Expansion Project.
191813. Pursuant to SC 9 of the Seagrass Mitigation Permit, the
1929requirements of SC 8 must be met for the mitigation to be
1941considered successful, but the Port is allowed to request a
1951determination that any portion of the mitigation is successful at
1961any time.
196314. In furtherance of the conceptually approved Expansion
1971Project, on December 17, 2002, the Port obtained ERP No. 0129291-
1982003-EI authorizing the requested construction activities.
1988Subsequently, ERP No. 0129291-003-EI was the subject of an
1997application for a major modification to authorize more dredging
2006for enlargement of the channel wideners, which resulted in
2015issuance of ERP No. 0129291-009-EM (the Construction Permit) on
2024June 10, 2004.
202715. SC 5 of the Construction Permit identified the seagrass
2037mitigation criteria and specific seagrass acreage DEP would
2045require to determine the seagrass mitigation successful for
2053purposes of authorizing dredging (referred to as "initial
2061success" or "dredging success"), and established a second
2070threshold of seagrass mitigation success necessary for
2077authorization to use the new facilities: "The final success
2086determination, showing 12.7 credits have been achieved, must be
2095documented prior to opening of Berths 4, 5, and Phase II of Berth
210812 to shipping."
211116. By letter dated February 7, 2005, the Port requested a
2122minor modification of the Seagrass Mitigation Permit to extend
2131the mitigation construction deadline five years, to August 29,
21402010, "to be on the safe side." On May 11, 2005, this minor
2153modification was granted as ERP 0129291-011-EI.
215917. On February 10, 2005, the Port filed the instant
2169application to modify the Construction Permit by eliminating the
2178last sentence of its SC 5 of so that the Port could open and
2192begin beneficial use of the new berths it had constructed before
2203DEP's "final success determination" concerning the Port's related
2211seagrass mitigation.
221318. On March 11 and April 14, 2005, DEP transmitted
2223requests for additional information (RAIs) relating to how the
2232Port would "provide reasonable assurance in a documented
2240commitment plan to full success of the seagrass mitigation
2249credits required by permits 0129291-002-EI and 0129291-003-EI, as
2257well as assurance for financial commitment to accomplish the
2266action plan."
226819. On March 14, 2005, the Port responded to the first RAI,
2280asserting that reasonable assurance was provided by the Port's
22892003/2004 seagrass mitigation monitoring report that requested
229610.44 mitigation credits. The Port further contended that the
2305mitigation was trending toward success and the necessary
2313additional credits would become available in the next year.
2322DEP's second RAI acknowledged those assertions, but in a letter
2332dated April 18, 2005, DEP also requested that the Port submit a
2344remedial action plan for the failed transplantation of Thalassia
2353testudinum (also referred to as T. testudinum and commonly called
2363turtle grass) from the impact area to Mitigation Areas 1, 2,
2374and 3.
237620. On September 9, 2005, DEP responded to the Port's
23862003/2004 seagrass mitigation monitoring report and seagrass
2393mitigation credit request, granting approval of only 6.1 of the
240310.44 mitigation credits requested. In addition, DEP commented
2411that "pursuant to the requirements of the mitigation plan, MCPA
2421shall prepare and submit a remedial action plan to the Department
2432for review and approval." This comment referred to the failed
2442transplantation of T. testudinum .
244721. On September 29, 2005, the Port submitted its
2456Resolution PA 05-16 reaffirming the Port's commitment to fully
2465comply with the conditions of its permits, "including, but not
2475limited to, conditions relating to seagrass mitigation."
248222. By letter dated October 25, 2005, Martin Seeling
2491explained to Petitioners why DEP staff was recommending at the
2501time that the pending application to modify the Construction be
2511granted:
2512All the originally required mitigation
2517activities have now been completed, and some
2524additional planting in Mitigation Sites 1-4
2530was completed this September. Based both on
2537the permittee's reports and the Department's
2543inspections, about half of the seagrass
2549mitigation credits have been achieved, and
2555the rest of the mitigation is clearly
2562trending toward success. We anticipate that
2568nearly all the remaining credits will be
2575achieved with the next year.
2580The purpose of the referenced permit
2586condition was to provide a strong incentive
2593for the permittee to complete the mitigation
2600in a timely manner and to provide the
2608Department with assurance that the loss of
2615seagrasses could indeed be mitigation. Both
2621of those goals appear to have been
2628accomplished. At this point, the main thing
2635needed for the mitigation success is
2641additional time.
2643Since there is no real advantage to be gained
2652by keeping the berths closed, Department
2658staff have recommended issuance of the permit
2665modification. One of our requirements for
2671the Port to complete this application was for
2679them to provide some alternate form of
2686assurance that the mitigation would be
2692completed. Our first suggestion of a surety
2699bond was not feasible, but the Port was able
2708to provide assurance by way of a . . .
2718Resolution (our second recommendation). In
2723addition to the resolution, we can also add
2731new (or revise existing) permit conditions to
2738strengthen the assurance that the Port will
2745actively pursue mitigation success until it
2751is achieved.
275323. On December 12, 2005, Martin Seeling advised the Port
2763that, according to DEP's Office of General Counsel, contrary to
2773earlier indications, the requested modification to SC 5 of the
2783Construction Permit "would require a major modification to the
2792permit"; and DEP requested the permit application fee that
2801applies to a major modification application.
280724. On February 15, 2006, the Port submitted an Annual
2817Progress and Mitigation Success Report claiming entitlement to
282513.06 seagrass mitigation success credits.
283025. On April 7, 2006, DEP issued a proposed agency action
2841that not only granted the Port's requested permit modification by
2851eliminating the last sentence of SC 5 of the Construction Permit,
2862but also combined and modified the Construction Permit Seagrass
2871Mitigation Permit Special Conditions to:
2876a. clarify the actions required and
2882mitigation ratios applied to the various
2888mitigation Sites as shown in the Seagrass
2895Mitigation Table included in proposed amended
2901SC 2;
2903b. clarify the reporting and coordination of
2910monitoring between the seagrass mitigation
2915supervisor and DEP in proposed amended SC 4e,
2923f and g;
2926c. clarify that Mitigation Site 9B would be
2934removed from the mitigation program because
2940of seagrass impacts in that Site caused by an
2949unauthorized discharge of clay during
2954construction activities in proposed amended
2959SC 5f;
2961d. clarify the use of Areas of Interest in
2970the methodology for documenting seagrass
2975mitigation success in proposed amended SC 8;
2982e. clarify that an evaluation of "overall
2989net change" within Mitigation Sites 1, 2, 3,
29978 and 9 would be required in addition to the
3007Area of Interest analysis in proposed amended
3014SC 8e;
3016f. require analysis of the propeller scar
3023recovery areas by monitoring and
3028characterizing the seagrass species and
3033density in 10 propeller scars selected by the
3041mitigation supervisor in proposed amended
3046SC 8g;
3048g. required submittal of a seagrass planting
3055plan for mitigation of impacts in the
3062flushing channels at Mitigation Site 7,
3068including "information regarding the pre-
3073impact seagrass community (density and
3078species composition) to assist the
3083Department's determination of restoration
3087success" in proposed amended SC 8; and
3094h. required submittal of a Remedial Action
3101Plan within 60 days, including planting to
3108re-establish T. testudinum to "compensate for
3114the temporal loss of approximately 3 acres of
3122T. testudinum " in proposed amended SC 14.
312926. The NOI issued with the April 7, 2006, proposed agency
3140action explained that additional assurances in the Seagrass
3148Mitigation Permit would be required and that remedial action for
3158the loss of Thalassia would also be required.
316627. The Port received a draft of the April 7, 2006,
3177proposed agency action and submitted a "White Paper" explaining
3186that it considered many of the requirements to be new
3196requirements, not included in the Seagrass Mitigation or
3204Construction Permits, that "raised the bar," making it more
3213difficult for the Port to achieve seagrass mitigation success.
3222DEP's mitigation credit consultants, Cheryl Miller and Don Deis
3231of PBS&J Corporation, responded with a memo refuting the Port's
3241contentions and defending the April 7, 2006, proposed agency
3250action. Ms. Miller, Mr. Deis and Martin Seeling, Environmental
3259Administrator for DEP's Bureau of Beaches and Coastal Systems
3268continue to support the April 7, 2006, proposed agency action and
3279do not consider it to "raise the bar." The current seagrass
3290mitigation supervisor Thomas Ries supported most the permit
3298modifications proposed by DEP and thought they were necessary.
3307However, the Port disputed the addition of minor Seagrass
3316Mitigation Permit modifications to the major Construction Permit
3324modification the Port requested. DEP gave the Port an extension
3334of time to file a petition for an administrative hearing while
3345the matter was further discussed.
335028. On April 18, 2006, DEP transmitted a draft Seagrass
3360Mitigation Credit Assignment letter dated April 21, 2006, that
3369approved 10.86 of the requested 13.06 seagrass mitigation success
3378credits.
337929. The Port met with DEP on April 28, 2006, and advocated
3391for additional credits. As a result of this meeting, DEP's
3401Deputy Director of the Division of Water Resource Management,
3410Janet Llewellyn, on behalf of DEP, decided that the Port should
3421be granted an additional .59 mitigation credits for a combined
3431Area of Interest (AOI) 8A/8B. On May 10, 2006, DEP issued a
3443credit assignment letter granting 11.45 credits, including the
3451additional credits assigned in the combined AOI 8A/8B.
345930. During the meeting on April 28, 2006, DEP and Port
3470representatives also agreed that the additional permit
3477modifications proposed by DEP in the April 7, 2006, proposed
3487agency action would be removed from the proposed major
3496modification of the Construction Permit, discussed, and
3503negotiated; and that the Port would apply for modification of the
3514Seagrass Mitigation Permit to incorporate some or all of those
3524modifications in the Seagrass Mitigation Permit, including a
3532requirement to implement a Turtle Grass Remedial Action Plan.
3541The Port subsequently continued to characterize DEP's demand for
3550a Remedial Action Plan addressing the loss of Turtle Grass as
"3561raising the bar" and opposed it.
356731. On July 5, 2006, DEP issued a Revised NOI regarding the
3579requested permit major modification and a revised permit
3587modification that granted the Port's request to be allowed to
3597open and begin using the expanded berth facilities and included
3607only limited other edits and clarifications. Specifically, the
3615language at issue in SC 5 was changed to read:
3625The final success determination, showing that
363112.7 credits have been achieved, must be
3638documented and approved by the Department
3644prior to the original-expiration date of this
3651permit (December 17, 2007).
3655The Revised NOI explained that Port Resolution PA-05-16 and the
36652005 annual monitoring report documenting 11.45 credits provided
3673reasonable assurance of seagrass mitigation success without the
3681additional modifications proposed in the April 7, 2006, proposed
3690agency action.
369232. Petitioners supported issuance of the April 7, 2006,
3701proposed agency action or denial of the major modification. When
3711the revised NOI was issued, Petitioners requested an
3719administrative hearing to oppose the major modification of the
3728Construction Permit unless the minor Seagrass Mitigation Permit
3736modifications were added back in.
374133. The Port had not yet submitted an application for the
3752modifications of the Seagrass Mitigation Permit. The Port
3760continued to characterize the requirement to implement a Remedial
3769Action Plan addressing the temporal loss of Turtle Grass as
"3779raising the bar" and has not yet committed to remedial actions
3790by the end of the final hearing in this case.
3800C. Significance of Turtle Grass Transplant Failure
380734. The Expansion Project is between two aquatic preserves,
3816Cockroach Bay Aquatic Preserve to the north and Terra Ceia
3826Aquatic Preserve to the south, waterward of the Cockroach Bay
3836State Buffer Preserve, and includes several types of seagrass as
3846well as a relatively productive benthic community, supporting a
3855wide array of corals, worms, crabs, fish, invertebrates, and
3864dolphins.
386535. Seagrass beds expand and contract, move with the
3874sediment around them, may be buried and unburied in sediments,
3884and have been observed to appear to "come and go" over areas as
3897large as 50 acres in Tampa Bay. These changes may occur
3908seasonally and over time depending on climate, water quality and
3918other factors. Three types of seagrass were identified in the
3928Impact Areas, Thalassia testudinum , Halidule wrightii , and
3935Syringodium filiforme --commonly called Turtle Grass, Shoal Grass,
3943and Manatee Grass. Approximately 3 acres of Turtle Grass and
39532.33 acres of Shoal Grass were transplanted from the Impact
3963Areas.
396436. Shoal Grass is a diminutive type of seagrass with roots
3975that occupy only the first few inches of sediment. Shoal Grass
3986has less bio-mass, less weight, less leaf structure and less
3996rhizome structure that Turtle Grass. Shoal Grass grows and
4005colonizes rapidly in shallow shoals and commonly proliferates in
4014the summer when waters are warm and loses leaves and dies back in
4027the winter when the water cools. Through persistence of buried
4037rhizomes, Shoal Grass can survive being exposed during very low
4047tides. Rain can adversely affect Shoal Grass by rapidly changing
4057salinity and nutrient loads carried by stormwater. Shoal Grass
4066is an early successional species that is adapted to being
4076uprooted and moved by currents and re-anchoring and re-rooting.
408537. Turtle Grass is a much more robust species, typically
4095five to ten times the bio-mass of shoal grass, including larger
4106leaves, rhizomes, and roots. Turtle Grass grows more slowly and
4116is more resistant to being dislodged because its roots and
4126rhizomes are larger and grow 6 to 8 inches deep in the sediment.
4139Turtle Grass is a climax species in terms of succession in Tampa
4151Bay. Turtle Grass plants must be handled carefully because of
4161their unique growing pattern that relies on a number of leaves to
4173provide food to a buried rhizome that then feeds a growing tip or
4186meristem that grows horizontally.
419038. Turtle Grass has broader leaves that extend upward
4199together and move in the water, providing greater protection for
4209certain species that other seagrasses provide. Turtle Grass
4217provides a much more distinct fish nursery and shrimp nursery
4227function. Because Turtle Grass grows in deeper water, it
4236provides more refuge for fish. Turtle Grass provides habitat for
4246species like scallops and larger shrimp. Turtle Grass rhizomes
4255store a great deal of energy which enables Turtle Grass to
4266withstand adverse conditions to a greater degree than other sea
4276grasses.
427739. The loss of approximately 3 acres of Turtle Grass
4287represented a substantial loss of habitat. This loss of habitat
4297had a substantial adverse effect on fish and wildlife utilization
4307in the Port Manatee Expansion Project area. The reduced fish and
4318wildlife utilization associated with the loss of turtle grass
4327substantially affected recreational fishing, birding, and
4333wildlife observation opportunities in the Port Manatee Expansion
4341Project area.
434340. The NOI issued in conjunction with the Seagrass
4352Mitigation Permit includes a lengthy summary at page 5 describing
4362the Port's proposed seagrass mitigation activities, including
4369specifically that Turtle Grass from the impact area would be
4379transplanted to Mitigation Sites 1, 2, and 3.
438741. The Seagrass Mitigation Plan requires the Port to map
4397the specific types of seagrasses found in the Impact Areas and
4408describes the details for the seagrass mitigation effort,
4416including on page 11 that "All turtlegrass in areas A and B to be
4430dredged will be transplanted to mitigation Sites 1, 2, and 3."
444142. The "Monitoring Required" section on page 16 of the
4451Seagrass Mitigation Permit states DEP may require remedial
4459actions if the mitigation is not successful pursuant to the
4469permit conditions.
447143. The Seagrass Mitigation Plan describes the remedial
4479actions required for transplantation failure, requiring remedial
4486planting if seagrass transplanted to Sites 1, 2, and 3 was not
4498successful due to bioturbation or excessive currents.
450544. The Seagrass Mitigation Plan includes a Success
4513Assessment Methodology Summary that explains in relevant part:
4521If the mitigation is not successful, remedial
4528action will be taken to ensure success.
4535Reasonable assurance of success is provided
4541by advanced transplanting, the mitigation
4546ratios, over-design of mitigation
4550opportunities, and a remedial action plan.
455645. The Expansion Project was time-sensitive due to
4564financing opportunities, resulting in the need to use unproved
4573techniques to timely accomplish the transplantation. The
4580Seagrass Mitigation Plan describes a process for selecting a
4589contractor and the contractor's proposed method. The Plan
4597describes "proven" and "alternative" methods for transplanting
4604seagrasses at a high rate by maximizing the size of sod units.
461646. The Port began its seagrass mitigation program in early
46262000 with the "Early Start Program" involving small-scale
4634transplanting experiments. The Seagrass Mitigation Plan
4640documents that the planting of seagrass began on April 3, 2000,
4651and that the transplanting of Turtle Grass from the impact areas
4662into mitigation site 1, 2, and 3 was scheduled to begin as soon
4675as possible after DEP issued the Permit.
468247. The Port retained a firm known as ASISI, owned by Jim
4694Anderson, to provide seagrass transplantation services, including
4701the large-scale or "mega-unit" transplants needed to expedite the
4710project, and ASISI developed a system for transplanting Shoal
4719Grass units and a system for transplanting 4-foot by 5-foot sods
4730of Turtle Grass from the Impact Areas to Mitigation Sites 1, 2,
4742and 3. The sod transplanting machine developed by ASISI used a
4753process referred to in the Seagrass Mitigation Plan as one of the
"4765alternative methods," the "modified tree spade" method.
477248. In July 2001, Robin Lewis reported to the Port
4782regarding Mr. Lewis' seagrass transplantation monitoring.
4788Mr. Lewis cautioned the Port that ASISI's test planting of
4798several Turtle Grass sod units had been too rough on the Turtle
4810Grass sod units and that they were not likely to survive and
4822persist.
482349. During the summer of 2001, ASISI began to mechanically
4833transplant about three acres of Turtle Grass from the Impact
4843Areas to Mitigation Sites 2 and 3. This up-front seagrass
4853transplantation was intended to provide immediate partial
4860mitigation for the seagrass impacts.
486550. In August 2001, Mr. Lewis warned the Port that ASISI's
4876mega-unit transplant efforts using the modified tree spade method
4885were failing. Mr. Lewis asserted that the sod units were not
4896being handled gently enough and were not being installed
4905carefully into excavated holes with their surfaces flush with or
4915below grade, as required by the Seagrass Mitigation Plan.
4924Pursuant to the Seagrass Mitigation Plan, Mr. Lewis urged the
4934Port to consider changing the methods employed to transplant
4943seagrass. Mr. Lewis recommended to the Port that it at least
4954immediately retain divers to follow ASISI's sod transplanting
4962machine to manually re-install Turtle Grass plants that were
4971damaged or improperly planted by the mechanical system. The Port
4981approved this "diver mop-up" program in November 2001, and diver
4991mop-up efforts were incorporated into the transplantation
4998process. These efforts proved to be successful only to a limited
5009extent because they were too late after most of the transplanting
5020had already taken place and most of the sod had washed away.
503251. In 2001, while ASISI was mechanically transplanting
5040Turtle Grass from the Impact Areas to Sites 2 and 3, Mr. Lewis'
5053company was staking, preparing final designs, and implementing
5061the Piney Point mitigation projects in Mitigation Sites 4A and
50716A, involving scrape-down of deposited sediments and Shoal Grass
5080planting. The Port's engineer testified to his concern that
5089Mr. Lewis was not around to supervise and assist ASISI's mega-
5100unit Turtle Grass transplantation, but the Port had advised
5109Mr. Lewis that he was not to monitor ASISI's transplanting
5119efforts because ASISI's principal, Jim Anderson, did not want him
5129to do so.
513252. During 2002, Mr. Lewis informally monitored ASISI's
5140mega-unit transplants and found that just over 100 units had
5150survived out of a total of 12,000 units transplanted. Subsequent
5161monitoring found that virtually none of the Turtle Grass units
5171survived and persisted. Turtle Grass is slow-growing, and only
5180less than an acre has grown throughout the mitigation area.
5190D. Disputed Credit Determinations
519453. Mr. Lewis' 2002 annual monitoring of all of the
5204mitigation sites established a sufficient acreage of new seagrass
5213to allow the Port to initiate dredging for part of the Expansion
5225Project. Nonetheless, the Port rejected Mr. Lewis' analysis of
5234the seagrass mitigation acreage and expressed disappointment
5241Mr. Lewis would not include additional seagrass acreage the Port
5251wished to claim as mitigation that Mr. Lewis considered pre-
5261existing seagrass.
526354. In late 2002, the Port determined that it would not
5274renew its contract with Lewis Environmental Services for 2003.
5283After some disagreement about Mr. Lewis' remaining
5290responsibilities under the existing contract, Mr. Lewis agreed to
5299prepare the annual monitoring report for 2002 but refused to
5309prepare or certify the November 2002 credit report submitted by
5319the Port. In a December 31, 2002, letter to the Port's George
5331Isiminger, Robin Lewis submitted his resignation as the
5339Mitigation Supervisor of record "on the basis of personal and
5349professional ethics."
535155. In early 2003, DEP accepted that the Port's November
53612002 seagrass mitigation success report documented at least 5.66
5370acres of new seagrass in the mitigation sites and authorized the
5381Port to begin dredging for the Expansion Project.
538956. The Port subsequently retained Thomas Ries as the
5398successor mitigation supervisor and continued to monitor the
5406seagrass mitigation and submit annual progress reports and credit
5415requests.
541657. Robin Lewis maintained an interest in the seagrass
5425mitigation project and requested copies of the Port's submittals
5434and submitted comments and concerns regarding the Port's credit
5443requests and documentation. Mr. Lewis' submittals were
5450considered by DEP in determining how much credit to approve. In
5461some cases, Mr. Lewis and DEP found that the Port requested more
5473credits than it was entitled to and employed analyses that were
5484not completely correct. Subsequent discussions revealed
5490disagreements regarding the meaning of permit conditions and how
5499to document seagrass mitigation success. As result of these
5508discussions, DEP corrected some errors and did not award all of
5519the requested credit.
552258. Due to extensive discussion of disagreements concerning
5530the Port's credit request for 2003, DEP recommended that a
5540combined credit request for 2003 and 2004 be submitted in 2005.
5551The combined credit request for 2003/2004 was submitted on
5560March 4, 2005. It requested a cumulative total of 10.44 credits.
5571After discussion, an RAI, and a DEP inspection, DEP granted
5581approval of a cumulative total of 6.1 credits by letter dated
5592September 9, 2005.
559559. The Port's next credit request was submitted in
5604February 2005 and was for a cumulative total of 13.06 credits.
5615After discussion, DEP granted 11.45 credits in April 2006.
562460. The Port proved that it was entitled to at least 10.86
5636credits under the Seagrass Mitigation Permit through 2005. The
5645only real remaining credit determination issue is whether the
5654Port is entitled to 10.86 or 11.45 credits. (Since the Port did
5666not challenge the credit determination, it waived the right to
5676credit in excess of 11.45 credits.) This determination depends
5685on the use of combined AOI 8A/8B.
569261. The use of AOI was a concern to DEP and a point of
5706contention because it is possible for the selection of AOIs to
5717introduce bias in the monitoring. In the case of combined AOI
57288A/8B, an AOI where mitigation credit was to be earned by
5739increasing seagrass coverage by excluding motorized boats and
5747allowing seagrass to recover in prop scars, there was no aerial
5758photography for the baseline year 1999 for use in determining
5768increased coverage in 8B. However, the Port interpreted the
5777language of the Seagrass Mitigation Permit to allow the Port to
5788assume complete coverage in the baseline year for 8B (and no
5799increased coverage there), measure increased coverage in 8A, and
5808calculate credits based on the increases in 8A, multiplied by a
5819mitigation ratio that applied to the acreage of the combined AOI
58308A/8B, since the increased seagrass coverage in Site 8A was great
5841enough mathematically to meet the percentage increase required
5849for credit for both Area 8A and 8B. This interpretation and
5860calculation resulted in a request for .59 credits for the
5870combined AOI 8A/8B.
587362. Because this interpretation assumed complete coverage
5880in Site 8A in baseline year 1999, the Port argued that it was a
"5894conservative" approach. After the meeting on April 28, 2006,
5903Ms. Lewellyn agreed.
590663. Petitioners contended that this "conservative" approach
5913in effect would award mitigation credit for Site 8B even if
5924seagrasses contracted or even were eliminated in Site 8B after
5934the baseline year 1999. Although such a result probably was not
5945intended, the approach taken with respect to AOI 8A/8B was not
5956inconsistent with the literal language of the Seagrass Mitigation
5965Permit.
596664. In addition, on more than one occasion, DEP could have
5977advised the Port that it would not approve credits for the
5988combined AOI 8A/8B because aerial photography for the baseline
5997year 1999 was not available, mitigation success in Site 8B could
6008not be verified, and credit could not be awarded for Site 8B.
6020Ms. Llewellyn thought that, after letting those opportunities
6028pass, it would be unfair for DEP to now deny the credits
6040requested by the Port for the combined AOI 8A/8B through 2005.
6051Based on the totality of the evidence, it is found that the Port
6064is entitled to 11.45 credits at this time.
6072E. Unauthorized Discharges of Sediment and Other
6079Violations of DEP rules; O.G.C. File No. 05-2790
608765. During the summer of 2004, there was an inadvertent
6097release of dredged material from a disposal area into Mitigation
6107Site 9B in conjunction with the Port's implementation of the
6117Expansion Project under the Construction Permit. This violated
6125SC 14, 17, and 18 of the Construction Permit, and SC 5 of the
6139Seagrass Mitigation Permit, and killed about 2.52 acres of mixed
6149seagrass beds consisting of Turtle Grass and Shoal Grass growing
6159in Mitigation Site 9B. The Port promptly notified DEP and
6169initiated corrective action. The matter was resolved by issuance
6178of a Consent Order, which was not challenged. As of July 2006,
6190the Port had removed the sediment, but destruction of these 2.52
6201acres of Turtle Grass and Shoal Grass remained un-mitigated as of
6212the time of the hearing.
621766. Clearly, the additional loss of approximately 2.52
6225acres of Turtle Grass and Shoal Grass in Mitigation Site 9B
6236represents an additional substantial loss of habitat and the
6245functions performed by the habitat. This additional habitat loss
6254will have a substantial affect on fish and wildlife utilization
6264in the Port Manatee area. However, Petitioners' attempt to
6273characterize these as part of the "cumulative impacts" of the
6283Expansion Project is not well-founded. Rather, they are an
6292inadvertent permit violation that has been resolved by consent
6301order. As such, those matters do not bear on whether the pending
6313permit modification request should be granted.
6319F. Consideration of the Relevant Factors
632567. Reasonable assurance of successful mitigation for the
6333impacts of the Expansion Project was predicated on four factors
6343identified in the Seagrass Mitigation Plan: the upfront
6351transplantation of seagrass; the mitigation ratios; the credits
6359available in the program; and the remedial action requirements.
636868. As found, the purpose of the last sentence of
6378Construction Permit SC 5--making the opening and use of the new
6389facilities contingent on documentation of the "final success
6397determination, showing 12.7 credits have been achieved"--was to
6406provide DEP reasonable assurance that the loss of seagrasses
6415would be successfully mitigated in a timely manner by
6424establishing a strong incentive for the permittee to complete the
6434mitigation promptly.
643669. As found, the Port is entitled to 11.45 credits for its
6448seagrass mitigation efforts to date. The mitigation project is
6457trending towards continued success in terms of credits, and it is
6468not unreasonable to expect 12.7 credits to be achieved in the
6479near future due to natural processes alone. For these reasons,
6489it is found that the permit modification requested by the Port
6500and now also proposed by DEP would not delay achievement of 12.7
6512credits.
651370. It is less clear whether the permit modification
6522requested by the Port and now also proposed by DEP would delay
6534the "final success determination," including remediation of the
6542Turtle Grass component of the upfront transplantation, which
6550could include planting Turtle Grass. Through the final hearing,
6559the Port and DEP had not come to an agreement on what such
6572remediation should include. (While not clear from the evidence,
6581it seems possible that the Port even may take the position that
6593the "final success determination" will occur when 12.7 credits
6602are documented regardless of the failure of the Turtle Grass
6612transplantation.) It is Petitioners' position that SC 5 of the
6622Construction Permit is an important incentive for the Port to
6632timely remediate the failure of the Turtle Grass transplantation
6641and that it should not be modified without clarification at least
6652as to the remediation required for the failure of the Turtle
6663Grass transplantation. Under the totality of the circumstances
6671of this case, Petitioners' position has merit.
6678G. Improper Purpose
668171. Even if Petitioners ultimately prevail do not prevail,
6690the evidence did not establish that they participated in this
6700proceeding primarily to harass or to cause unnecessary delay, or
6710for frivolous or improper purpose or to needlessly increase the
6720Port's cost to obtain the approval. Rather, their purpose has
6730been to protect the natural resources of Tampa Bay, in particular
6741its seagrass habitat.
6744CONCLUSIONS OF LAW
6747H. Standing
674972. Section 403.412(5), Florida Statutes, gives Manasota-88
6756standing to petition to challenge proposed agency action.
676473. Petitioners have a substantial interest in mitigation
6772of the seagrass habitat impacts of the Expansion Project which is
6783cognizable under the permitting criteria applicable to the
6791subject permit applications. As a result, Petitioners have
6799substantial interests that will be affected by the proposed
6808agency action. As such, Petitioners have standing pursuant to
6817Sections 120.52(12)(b) and 120.569(1), Florida Statutes. See
6824also § 403.412(5)-(6), Fla. Stat.
682974. The Petitioners have established an immediate injury-
6837in-fact sufficient to allow them to participate as parties, and
6847they have standing to challenge the proposed agency action.
6856J. Burden of Proof
686075. As the applicant, the Port has the burden of showing by
6872preponderance of the credible and credited evidence that it is
6882entitled to the approval at issue here. Department of
6891Transportation v. J.W.C. Co. , 396 So. 2d 778, 789 (Fla. 1st DCA
69031981).
690476. If the Port makes a prima facie showing of reasonable
6915assurances, the burden shifts to Petitioners to present evidence
6924of equivalent quality. J.W.C. Co. , 396 So. 2d at 789.
6934I. Permit Criteria
693777. ERP conditions of approval are set forth in Chapter
6947373, Florida Statutes, and in Rule Chapter 62-330, which
6956incorporates certain Southwest Florida Water Management District
6963(SWFWMD) rules in effect in 2005, including Rules 40D-4.301 and
697340D-4.302, and the 2005 SWFWMD Basis of Review. To demonstrate
6983entitlement to the major modification, the Port is required to
6993provide reasonable assurance to DEP that it will meet these
7003conditions of approval.
700678. "Reasonable assurance" means "a substantial likelihood
7013that the project will be successfully implemented." Metropolitan
7021Dade County v. Coscan Florida, Inc. , 609 So. 2d 644, 648 (Fla. 3d
7034DCA 1992); Save Anna Maria, Inc. v. Department of Transportation ,
7044700 So. 2d 113, 117 (Fla. 2d DCA 1997). Reasonable assurances
7055must take into account contingencies that might reasonably be
7064expected, but an applicant is not required to eliminate all
7074contrary possibilities, however remote, or to address impacts
7082which are only theoretical and not reasonably likely.
709079. The test in this case is not whether DEP properly
7101evaluated the original application, but whether the Port provided
7110reasonable assurance that the applicable conditions for issuance
7118of the major modification have been satisfied. When a permittee
7128seeks to modify an existing permit, regulatory review includes
7137only that portion of the existing permit that is proposed to be
7149modified. See Friends of the Everglades, Inc. v. Dept. of
7159Environmental Reg. , 496 So. 2d 181, 183 (Fla. 1st DCA 1986);
7170Behrens v. Boran , ORDER NO. SWF 02-052, 2 ER FALR 257 (SWFWMD
7182Aug. 27, 2002), DOAH Case No. 02-0282, 2002 Fla. ENV LEXIS 192
7194(DOAH July 29, 2002); Kunnen v. Southwest Fla. Water Mgmt. Dist. ,
7205ORDER NO.: SWF 02-003, DOAH Case No. 01-2571, 2002 Fla. ENV LEXIS
72174 (SWFWMD Jan. 29, 2002; DOAH Dec. 17, 2001). The "reasonable
7228assurance" requirement applies to the activities for which
7236permitting is presently sought and does not burden the applicant
7246with "providing 'reasonable assurances' anew with respect to the
7255original project already constructed in accordance with a valid
7264permit." Friends of the Everglades , supra at 183. Therefore, a
7274determination of whether the Port has provided reasonable
7282assurances to the DEP is limited to a review of those portions of
7295the proposed permit modification that are different from the
7304Construction Permit it is modifying.
730980. The proposed permit modification does not authorize any
7318additional construction activities or any additional impacts, it
7326merely provides for utilization of already constructed facilities
7334prior to a final determination of complete seagrass mitigation
7343success. The question is whether the Port will continue to
7353provide reasonable assurance without the last sentence of SC 5 of
7364the Construction Permit.
736781. Section 373.413, Florida Statutes, and Rule 40D-4.301
7375relate to the construction, alteration, operation, maintenance,
7382removal, or abandonment of a storm water management system. The
7392Construction Permit does not authorize any upland activities
7400requiring the development of a stormwater management system since
7409the authorized construction is dredging in the waters of Tampa
7419Bay.
742082. Pursuant to Section 373.414(1), Florida Statutes, an
7428ERP applicant must provide reasonable assurance that the proposed
7437activity "is not contrary to the public interest" based upon a
7448balancing of the factors listed in Section 373.414(1)(a), and
7457taking into account measures proposed by the applicant to
7466mitigate adverse effects as contemplated by Section
7473373.414(1)(b), Florida Statutes.
747683. Section 373.414(1)(b), Florida Statutes, provides in
7483relevant part that:
7486It shall be the responsibility of the
7493applicant to choose the form of mitigation.
7500The mitigation must offset the adverse
7506effects caused by the regulated activity.
7512In this case, the regulated activity is dredging and filling in
7523Tampa Bay, including dredging in the Impact Areas where
7532approximately 5.33 acres of seagrass existed. To offset these
7541seagrass impacts, the Port proposed and agreed to the mitigation
7551required by the Seagrass Mitigation Permit and the Construction
7560Permit, including the requirement the Port seeks to modify in
7570this proceeding.
757284. Rule 40D-4.302(2) requires DEP to take into
7580consideration the rule violations that resulted from the
7588inadvertent release of dredged material, as well as the efforts
7598taken by the Port to resolve the violations, when determining
7608whether the Port has provided reasonable assurance that
7616permitting standards will be met. The Port's rule violations
7625addressed in the Consent Order are substantial and significantly
7634adversely affect the existing Turtle Grass and other habitats in
7644the Port Manatee area. However, the Port has cooperated to the
7655extent of entering into the Consent Order and agreeing to
7665mitigate for the impacts. The adverse impacts to Turtle Grass
7675and Shoal Grass in the Expansion Project area have not yet been
7687fully mitigated, but progress is being made in that direction.
7697Since the violations were inadvertent, and have been resolved by
7707the Consent Order, they are not valid reasons to deny the permit
7719modification requested by the Port and now also proposed by DEP.
773085. Pursuant to Section 373.414(8)(a), Florida Statutes,
7737DEP is required to "consider the cumulative impacts upon surface
7747water and wetlands" of certain types of activities. But the loss
7758of seagrasses by the inadvertent, unauthorized discharge of
7766sediment in 2004 should not be considered cumulative impacts for
7776purposes of this major modification application, and they have
7785been addressed in the Consent Order.
779186. Opening the new berths is in the public interest if it
7803will not delay implementing the seagrass mitigation program.
7811Among other things, SC 14 of the agency action proposed on
7822April 7, 2006, would clarify that a Remedial Action Plan for the
7834temporal loss of Turtle Grass is required by the Seagrass
7844Mitigation Permit and must be performed. As found, if the
7854requested modification to SC 5 of the Construction Permit is to
7865be granted, the Port should be required to submit a Remedial
7876Action Plan within 60 days in accordance with and as set forth in
7889amended SC 14 proposed by DEP on April 7, 2006.
789987. Attorney's fees are awardable to the prevailing party
7908under Section 120.595(1), Florida Statutes. If this Recommended
7916Order is adopted, the Port would not be considered the prevailing
7927party for purposes of that statute. Even if the Port were the
7939prevailing party, attorney's fees are not awardable under the
7948statute because, as found, it was not proven that Petitioners
7958participated in this proceeding primarily to harass or to cause
7968unnecessary delay, or for frivolous or improper purpose or to
7978needlessly increase the Port's cost to obtain the approval.
7987RECOMMENDATION
7988Based upon the foregoing Findings of Fact and Conclusions of
7998Law, it is
8001RECOMMENDED that DEP grant the requested modification to SC
80105 of the Construction Permit with a condition that the Port
8021submit a Remedial Action Plan within 60 days in accordance with
8032and as set forth in amended SC 14 proposed by DEP on April 7,
80462006.
8047DONE AND ENTERED this 6th day of February, 2007, in
8057Tallahassee, Leon County, Florida.
8061S
8062J. LAWRENCE JOHNSTON
8065Administrative Law Judge
8068Division of Administrative Hearings
8072The DeSoto Building
80751230 Apalachee Parkway
8078Tallahassee, Florida 32399-3060
8081(850) 488-9675 SUNCOM 278-9675
8085Fax Filing (850) 921-6847
8089www.doah.state.fl.us
8090Filed with the Clerk of the
8096Division of Administrative Hearings
8100this 6th day of February, 2007.
8106COPIES FURNISHED :
8109Lea Crandall, Agency Clerk
8113Department of Environmental Protection
8117The Douglas Building, Mail Station 35
81233900 Commonwealth Boulevard
8126Tallahassee, Florida 32399-3000
8129Tom Beason, Acting General Counsel
8134Department of Environmental Protection
8138The Douglas Building, Mail Station 35
81443900 Commonwealth Boulevard
8147Tallahassee, Florida 32399-3000
8150Michael W. Sole, Secretary
8154Department of Environmental Protection
8158The Douglas Building, Mail Station 35
81643900 Commonwealth Boulevard
8167Tallahassee, Florida 32399-3000
8170W. Douglas Beason, Esquire
8174Department of Environmental Protection
8178The Douglas Building, Mail Station 35
81843900 Commonwealth Boulevard
8187Tallahassee, Florida 32399-3000
8190John R. Thomas, Esquire
8194Thomas & Associates, P.A.
8198233 Third Street North, Suite 101
8204St. Petersburg, Florida 33701-3818
8208Kevin S. Hennessy, Esquire
8212R. David Jackson, Esquire
8216Lewis, Longman & Walker, P. A.
82221001 Third Avenue West, Suite 670
8228Bradenton, Florida 34205-7848
8231NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
8237All parties have the right to submit written exceptions within 15
8248days from the date of this Recommended Order. Any exceptions to
8259this Recommended Order should be filed with the agency that will
8270issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 03/23/2007
- Proceedings: Department of Environmental Protection`s Responses to the Manatee County Port Authority`s Exceptions to the Recommended Order filed.
- PDF:
- Date: 03/23/2007
- Proceedings: Respondent Manatee County Port Authority`s Exceptions to Recommended Order filed.
- PDF:
- Date: 02/06/2007
- Proceedings: Recommended Order (hearing held October 30-31 and November 1, 2006). CASE CLOSED.
- PDF:
- Date: 02/06/2007
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 01/03/2007
- Proceedings: Petitioners` Notice of Filing Amended Proposed Recommended Order filed.
- PDF:
- Date: 01/02/2007
- Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to Petitioners` Motion for SLAPP Fees filed.
- PDF:
- Date: 12/26/2006
- Proceedings: Proposed Recommended Order of Respondent Manatee County Port Authority filed.
- PDF:
- Date: 12/21/2006
- Proceedings: Petitioners` Motion for Slapp Fees and Response to Port Manatee Fee Motion filed.
- PDF:
- Date: 12/21/2006
- Proceedings: Department of Environmental Protection`s Proposed Recommended Order filed.
- PDF:
- Date: 12/21/2006
- Proceedings: Proposed Recommended Order of Respondent Manatee County Port Authority filed.
- Date: 12/11/2006
- Proceedings: Transcript of Proceedings (Volumes I-A through III-B) filed.
- PDF:
- Date: 11/22/2006
- Proceedings: Department of Environmental Protection`s Response in Opposition to the Petitioners` Request for Official Recognition filed.
- PDF:
- Date: 11/13/2006
- Proceedings: Respondent Manatee County Port Authority`s Objections to Certain Excerpts Designated by Petitioners from Depositions of Marty Seeling and Janet Llewellyn filed.
- PDF:
- Date: 11/13/2006
- Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to Petitioners` Request for Official Recognition filed.
- PDF:
- Date: 11/13/2006
- Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to the Admission of the Depositions of Don Deis and Cheryl Miller and, in the Alternative, Objections to Petitioners` Designated Excerpts from the Depositions of Don Deis and Cheryl Miller and Respondent`s Submittal of Designation of Excerpts to the Depositions of Don Deis and Cheryl Miller filed.
- PDF:
- Date: 11/09/2006
- Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Cheryl Miller filed.
- PDF:
- Date: 11/09/2006
- Proceedings: Department of Environmental Protection`s Revised Notice of Designation of Excerpts to the Deposition of Martin Seeling filed.
- PDF:
- Date: 11/09/2006
- Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Janet Lllewellyn filed.
- PDF:
- Date: 11/09/2006
- Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Martin Seeling filed.
- PDF:
- Date: 11/09/2006
- Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Donald Deis filed.
- PDF:
- Date: 11/07/2006
- Proceedings: Letter to Judge Johnston from J. Thomas enclosing a substitute for Petitioners` Exhibit 3, December 10, 1999 Environmental Resource Permit Number 0129291-001-EC and Notice of Intent.
- PDF:
- Date: 11/07/2006
- Proceedings: Memorandum in Support of Admission of Depositions of Don Deis and Cheyrl Miller filed.
- PDF:
- Date: 11/07/2006
- Proceedings: Notice of Filing Depositions of Don Deis and Cheyrl Miller and Designation of Petitioners` Excerpts filed.
- PDF:
- Date: 11/06/2006
- Proceedings: Memorandum in Support of Admission of Depositions of Don Deis and Cheryl Miller filed.
- PDF:
- Date: 11/06/2006
- Proceedings: Notice of Filing Depositions of Don Deis and Cheryl Miller and Designation of Petitioners` Excerpts.
- PDF:
- Date: 11/06/2006
- Proceedings: Letter to Judge Johnston from R. Jackson enclosing copies of the slide pictures from the Hearing filed.
- PDF:
- Date: 11/06/2006
- Proceedings: Notice of Petitioners` Excerpts of Depositions filed by Port Authority.
- PDF:
- Date: 11/03/2006
- Proceedings: Notice of Filing Depositions and Requested Excerpts by Manatee County Port Authority filed with the Judge at Hearing.
- PDF:
- Date: 11/03/2006
- Proceedings: Letter to Judge Johnston from J. Thomas enclosing Petitioner`s Proposed Hearing Exhibits filed (exhibits not available for viewing).
- PDF:
- Date: 11/03/2006
- Proceedings: Letter to Parties of Record from J. Thomas regarding the deposition exhibits filed.
- PDF:
- Date: 11/02/2006
- Proceedings: Notice of Filing Depositions and Requested Excerpts by Manatee County Port Authority.
- PDF:
- Date: 11/02/2006
- Proceedings: Letter to Judge Johnston from R. Jackson enclosing Proposed Hearing Exhibits filed (exhibits not available for viewing).
- PDF:
- Date: 11/02/2006
- Proceedings: Letter to R. Jackson from J. Thomas regarding the transmittal of Exhibits to Judge Johnston filed.
- Date: 10/30/2006
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 10/27/2006
- Proceedings: Respondent Manatee County Port Authority`s Motion for Attorney`s Fees filed.
- PDF:
- Date: 10/27/2006
- Proceedings: Respondent Manatee County Port Authority`s Motion in Limine filed.
- PDF:
- Date: 10/10/2006
- Proceedings: Letter to Judge Johnston from J. Thomas regarding the October 4, 2006 Order Granting Continuance and Re-scheduling Hearing filed.
- PDF:
- Date: 10/04/2006
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for October 30 through November 1, 2006; 9:00 a.m.; Bradenton, FL).
- PDF:
- Date: 10/03/2006
- Proceedings: Letter to Judge Johnston from J. Thomas regarding dates available for hearing filed.
- PDF:
- Date: 10/02/2006
- Proceedings: Respondent Manatee County Port Authority`s Notice of Filing Witness List filed.
- PDF:
- Date: 09/28/2006
- Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to Petitioners` Emergency Motion to Continue Hearing and to Compel Discovery and Petitioners` Motion to Impose Expedited Deposition Transcript Costs filed.
- PDF:
- Date: 09/27/2006
- Proceedings: Amended Notice of Hearing (hearing set for October 11 and 12, 2006; 9:00 a.m.; Bradenton, FL; amended as to location).
- PDF:
- Date: 09/27/2006
- Proceedings: Petitioners` Emergency Motion to Continue Hearing and to Compel Discovery filed.
- PDF:
- Date: 09/27/2006
- Proceedings: Department of Environmental Protection`s Responses and Objections to Petitioners` Request for Production filed.
- PDF:
- Date: 09/26/2006
- Proceedings: Department of Environmental Protection`s Notice of Service of Answers to Petitioners` First Set of Interrogatories filed.
- PDF:
- Date: 09/26/2006
- Proceedings: Respondent Manatee County Port Authority`s Responses to Petitioners` Request for Production filed.
- PDF:
- Date: 09/26/2006
- Proceedings: Respondent Manatee County Port Authority`s Notice of Service of Answers & Objections to Petitioners` First Set of Interrogatories filed.
- PDF:
- Date: 09/19/2006
- Proceedings: Order Granting Motion to Expedite (time for discovery responses is shortened to 15 days from service of discovery requests).
- PDF:
- Date: 09/15/2006
- Proceedings: Notice of Hearing (hearing set for October 11 and 12, 2006; 9:00 a.m.; Bradenton, FL).
- PDF:
- Date: 09/13/2006
- Proceedings: Notice of Serving Respondent Manatee County Port Authoritys` First Set of Interrogatories to Petitioner Roy R. Lewis, III filed.
- PDF:
- Date: 09/13/2006
- Proceedings: Notice of Serving Respondent Manatee County Port Authoritys` First Set of Interrogatories to Petitioner Manasota-88, Inc. filed.
- PDF:
- Date: 09/11/2006
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
- PDF:
- Date: 09/08/2006
- Proceedings: Respondent Manatee County Port Authority`s Response to Initial Order filed.
- PDF:
- Date: 09/08/2006
- Proceedings: Respondent Manatee County Port Authority`s Motion to Dismiss with Prejudice Petitioners` Amended Petition for Formal Administrative Hearing filed.
- PDF:
- Date: 09/08/2006
- Proceedings: Respondent Manatee County Port Authority`s Motion to Expedite Final Hearing filed.
Case Information
- Judge:
- J. LAWRENCE JOHNSTON
- Date Filed:
- 08/31/2006
- Date Assignment:
- 09/01/2006
- Last Docket Entry:
- 03/26/2007
- Location:
- Bradenton, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
Counsels
-
W. Douglas Beason, Esquire
Address of Record -
Kevin S. Hennessy, Esquire
Address of Record -
R. David Jackson, Esquire
Address of Record -
John R. Thomas, Esquire
Address of Record -
John R Thomas, Esquire
Address of Record