06-003288 Manasota-88, Inc. And Roy R. Lewis, Iii vs. Department Of Environmental Protection And Manatee County Port Authority
 Status: Closed
Recommended Order on Tuesday, February 6, 2007.


View Dockets  
Summary: Port Manatee did not provide reasonable assurance that removing an economic incentive would not delay timely completion of seagrass mitigation. Recommend that the Environmental Resource Permit modification be granted w/condition of remedial action.

1Case No. 06-3288

4STATE OF FLORIDA

7DIVISION OF ADMINISTRATIVE HEARINGS

11MANASOTA-88, INC. and ROY R. ) ) ) ) ) ) ) ) ) ) ) ) )

29LEWIS, III,

31RECOMMENDED ORDER

33Petitioners,

34vs.

35DEPARTMENT OF ENVIRONMENTAL

38PROTECTION and MANATEE COUNTY

42PORT AUTHORITY,

44Respondents.

45On October 30-31 and November 1, 2006, a final

54administrative hearing was held in this case in Bradenton,

63Florida, before J. Lawrence Johnston, Administrative Law Judge

71(ALJ), Division of Administrative Hearings (DOAH).

77APPEARANCES

78For Petitioners Manasota-88, Inc. and Roy R. Lewis, III:

87John R. Thomas, Esquire

91Thomas & Associates, P.A.

95233 Third Street North, Suite 101

101St. Petersburg, Florida 33701-3818

105For Respondent Department of Environmental Protection:

111W. Douglas Beason, Esquire

115Department of Environmental Protection

119The Douglas Building, Mail Station 35

1253900 Commonwealth Boulevard

128Tallahassee, Florida 32399-3000

131For Manatee County Port Authority:

136Kevin S. Hennessy, Esquire

140R. David Jackson, Esquire

144Lewis, Longman & Walker, P.A.

1491001 Third Avenue West, Suite 670

155Bradenton, Florida 34205-7848

158STATEMENT OF THE ISSUES

162The issues in this case are: whether the Department of

172Environmental Protection (DEP) should modify an Environmental

179Resource Permit (ERP) held by the Manatee County Port Authority

189(the Port) for expansion of its facilities at Port Manatee by

200eliminating a specific condition (SC) that prohibits the opening

209and use of those expanded facilities before DEP's "final success

219determination" concerning the Port's related seagrass mitigation

226ERP; and whether attorney's fees should be awarded.

234PRELIMINARY STATEMENT

236On February 10, 2005, the Port applied for modification of

246SC 5 of its ERP. DEP twice requested additional information

256relating to how the Port would provide reasonable assurance with

266respect to the requested permit modification, and the Port

275responded with additional information that was reviewed by DEP.

284On April 7, 2006, DEP gave notice of its intent to approve

296the requested modification and issued a draft permit modification

305that also included modifications to the related seagrass

313mitigation ERP that were not requested by the Port. After DEP

324extended the time for the Port to file a petition, DEP and the

337Port met on July 5, 2006, and DEP issued a revised Notice of

350Intent (NOI) and revised draft permit modification that granted

359the Port's application without the additional modifications.

366On July 19, 2006, Manasota-88, Inc., and Roy R. Lewis, III

377(Robin Lewis) timely petitioned for a formal administrative

385hearing challenging the NOI and revised draft permit modification

394and seeking to reinstate the NOI and draft permit modification

404issued in April. DEP dismissed the petition with leave to amend

415based on DEP's determination that the petition included

423insufficient allegations as to how Petitioners' substantial

430interests were affected by the proposed agency action. On

439August 21, 2006, Petitioners filed an Amended Petition for Formal

449Administrative Proceeding (Petition), which DEP referred to

456(DOAH).

457On September 8, 2006, the Port filed a Motion to Dismiss

468with Prejudice and a Motion to Expedite Final Hearing. On

478September 15, 2006, the final hearing was scheduled for

487October 11 and 12, 2006. On September 19, 2006, the Motion to

499Dismiss was denied, and the Motion to Expedite was granted,

509requiring discovery responses within 15 days.

515On September 26 and 27, 2006, Petitioners filed a Motion to

526Impose Expedited Deposition Transcript Costs and an Emergency

534Motion to Continue Hearing and to Compel Discovery. A telephonic

544hearing was held on September 29, 2006, and the final hearing was

556continued until October 30-31 and November 1, 2006.

564On October 27, 2006, the parties filed a Pre-Hearing

573Stipulation, and the Port filed a Motion in Limine seeking to

584exclude evidence relating to: other permits issued to the Port;

594DEP's Consent Order OGC File No. 05-2790; and seagrass mitigation

604success credit determinations made by DEP. The Port also filed a

615Motion for Attorney's Fees.

619At the onset of the final hearing, the Motion in Limine was

631argued and denied.

634During the final hearing, the Port, as applicant, called as

644witnesses: George F. Isiminger, Director of Engineering and

652Environmental Affairs for the Port Authority; Stephen G. Swingle,

661an environmental scientist; Raymond F. Dennis, III, an ecologist

670responsible for the monitoring of the sea grass mitigation at

680Port Manatee; and Thomas F. Ries, the current seagrass mitigation

690supervisor for the Port Manatee expansion project. The Port also

700designated excerpts from the deposition transcripts of

707Janet Llewellyn, Deputy Director of the DEP's Division of Water

717Resource Management, and Martin Seeling, an environmental

724administrator with the DEP, for admission as Port Exhibits 17 and

73518. The other parties added excerpts for consideration as part

745of the exhibits. The Port also offered Port Exhibits 1 through

75613, 15, 16, and 19 through 21, which were admitted in evidence

768without objection, along with Port Exhibits 17 and 18.

777Petitioners called two witnesses: Robin Lewis, who is an

786environmental consultant and the former seagrass mitigation

793supervisor for the Port Manatee expansion project; and Glenn

802Compton, Chairman of Manasota-88. Petitioners also had their

810Exhibits 3, 9, 24, 26, 34, 37, 41, 57, 64, 66, 69, 75, 88, 90,

82593, 96 through 101, 105 through 108, and 116 admitted in

836evidence. Ruling was reserved on objections to Petitioners'

844Exhibits 21 and 109, which are sustained.

851In rebuttal, the Port re-called Mr. Dennis and also called

861David Crewz of the Fish and Wildlife Research Institute.

870After presentation of evidence, the parties arranged for

878preparation of a Transcript of the final hearing; the parties

888were given ten days from the filing of the Transcript in which to

901file proposed recommended orders (PROs); and the record was

910closed. However, at that point, Petitioners inquired about the

919status of the transcripts of the depositions of Don Deis and

930Cheryl Miller, consultants for DEP on seagrass mitigation

938success, which were filed at the outset of the proceedings but

949deferred pending an assessment of the need for them to be made

961after the presentation of other evidence; and the record was re-

972opened to reflect Petitioners' request that those transcripts be

981placed in evidence and to allow the other parties to respond.

992When the Port objected, the transcripts were marked as

1001Petitioners' Exhibits 117 and 118, and the parties were given an

1012opportunity to file argument on their admissibility and to

1021designate excerpts from the transcripts to be considered, if

1030admitted. Written arguments on admissibility and all

1037designations, together with the Port's additional objections to

1045certain designations, were filed by November 13, 2006. Based on

1055the written arguments, the objections are overruled, and the

1064designated portions of Petitioners' Exhibits 117 and 118 are

1073admitted in evidence.

1076On November 13, 2006, Petitioners also filed a Request for

1086Official Recognition of the Florida Conceptual State Land

1094Management Plan and ERP No. 0129291-003-EI (with related NOI),

1103which were identified as Petitioners' Exhibit 1 and 5,

1112respectively (although Petitioners also proposed that the latter

1120be identified as Petitioners' Exhibit 119). The other parties

1129filed objections, which are overruled; and the Request for

1138Official Recognition is granted.

1142The Transcript (745 pages in six volumes) was filed on

1152December 11, 2006. The parties filed timely PROs. In addition,

1162Petitioners filed a Motion for SLAPP Fees and Response to Port

1173Manatee Fee Motion. (The PROs filed by Petitioners and the Port

1184also addressed the Port's Motion for Attorney's Fees.) On

1193January 2, 2007, the Port filed a Response in Opposition to

1204Petitioners' Motion for SLAPP Fees. On January 3, 2007,

1213Petitioners filed an Amended PRO in compliance with the 40-page

1223limit in Florida Administrative Code Rule 28-106.215. (Unless

1231otherwise indicated, all rule references are to the current

1240Florida Administrative Code, and all statute references are to

1249the 2006 codification of the Florida Statutes.)

1256FINDINGS OF FACT

1259A. The Parties

12621. DEP is an executive agency of the State of Florida under

1274Article IV, Section 6, of the Florida Constitution. DEP

1283administers the Environmental Resource Permit Program pursuant to

1291Chapter 373, Part IV, Florida Statutes, for various activities,

1300including "dredging and filling" by Florida's seaports.

13072. The Port operates and sets policy for Port Manatee, a

1318public deepwater commercial seaport located in the northern part

1327of Manatee County on Tampa Bay.

13333. Manasota-88, Inc., is a Florida corporation not for

1342profit that has at least 25 current members residing within

1352Manatee County. Manasota-88 was formed, more than one year

1361before the Port filed its application for the permit modification

1371that is the subject of this proceeding, for the purposes of

1382protection of public health and the environment, fish and

1391wildlife resources, and air and water quality.

13984. A substantial number of the members of Manasota-88 fish,

1408swim and snorkel, watch birds, and enjoy wild life observation in

1419Tampa Bay around Port Manatee.

14245. Robin Lewis is president and principal ecologist for

1433Lewis Environmental Services, Inc., an environmental consulting

1440firm. Mr. Lewis is a wetlands scientist with extensive expertise

1450in ecology, restoration, and creation of marshes, mangrove

1458forests, and seagrass meadows.

14626. Robin Lewis had been involved in many projects relating

1472to seagrass protection and restoration in Tampa Bay and the area

1483where the Project is located. At the inception of the Port

1494Manatee expansion project, Mr. Lewis objected to the Port's

1503underestimation of the acreage of seagrass that would be impacted

1513by the expansion project. Mr. Lewis was subsequently hired by

1523the Port on a contract basis to map seagrass in the impact and

1536mitigation areas of the Port's expansion project.

15437. Mr. Lewis owns two boats that he sometimes uses for

1554fishing and shallow water recreation. The boats are equipped

1563with poles so that he can pole into motorized vessel restriction

1574zones. Mr. Lewis has fished the area around Port Manatee many

1585times over the course of most of his adult life. Mr. Lewis is

1598also a wildlife and bird watching enthusiast. The Tampa Bay area

1609around Port Manatee, including the area of project impacts and

1619the mitigation areas, provide opportunities for wildlife

1626observation and bird-watching, and Mr. Lewis has engaged in those

1636activities in the Port Manatee area many times over the years.

1647B. DEP Permits, Port Authority Application, and

1654Mitigation Credit Correspondence

16578. In August 1994, the Port began the permitting process

1667for a substantial expansion of Port Manatee by applying to DEP's

1678Bureau of Beaches and Coastal Systems for authorization for

1687dredging and filling and other activities in the coastal waters

1697and wetlands around Port Manatee.

17029. In December 1999, the Board of Trustees of the Internal

1713Improvement Trust Fund and DEP issued ERP No. 0129291-001-EC, a

"1723Conceptual Permit" for enlargement of the main access channel

1732at the entrance to Port Manatee, construction of a ship turning

1743basin, expansion of Berth 5, and construction of new Berths 4 and

175512 (Phase II) at Port Manatee (the Expansion Project).

176410. Conceptual Permit SC 5 provided that the Port would

1774have to obtain individual ERPs for the various conceptually

1783approved activities. The Conceptual Permit's "Description of

1790Activities" section on page 1 summarized that the Port proposed

1800to offset 12.7 acres of seagrass habitat impacts by transplanting

1810the existing seagrass and by creating, restoring, and enhancing

1819seagrass habitat in Tampa Bay.

182411. Conceptual Permit SC 9 specified that DEP had to deem

1835the seagrass mitigation to be successful before the Port could

1845initiate dredging.

184712. The requirement to achieve 12.7 seagrass mitigation

1855success credits was specified in ERP No. 0129291-002-EI (the

"1864Seagrass Mitigation Permit"), which was issued to the Port on

1875August 29, 2000. Procedures for documenting seagrass mitigation

1883success are included in the Seagrass Mitigation Permit and an

1893attached July 2000 Seagrass Mitigation Plan, authored principally

1901by Robin Lewis, which authorize and describe all of the seagrass

1912mitigation requirements for the Expansion Project.

191813. Pursuant to SC 9 of the Seagrass Mitigation Permit, the

1929requirements of SC 8 must be met for the mitigation to be

1941considered successful, but the Port is allowed to request a

1951determination that any portion of the mitigation is successful at

1961any time.

196314. In furtherance of the conceptually approved Expansion

1971Project, on December 17, 2002, the Port obtained ERP No. 0129291-

1982003-EI authorizing the requested construction activities.

1988Subsequently, ERP No. 0129291-003-EI was the subject of an

1997application for a major modification to authorize more dredging

2006for enlargement of the channel wideners, which resulted in

2015issuance of ERP No. 0129291-009-EM (the Construction Permit) on

2024June 10, 2004.

202715. SC 5 of the Construction Permit identified the seagrass

2037mitigation criteria and specific seagrass acreage DEP would

2045require to determine the seagrass mitigation successful for

2053purposes of authorizing dredging (referred to as "initial

2061success" or "dredging success"), and established a second

2070threshold of seagrass mitigation success necessary for

2077authorization to use the new facilities: "The final success

2086determination, showing 12.7 credits have been achieved, must be

2095documented prior to opening of Berths 4, 5, and Phase II of Berth

210812 to shipping."

211116. By letter dated February 7, 2005, the Port requested a

2122minor modification of the Seagrass Mitigation Permit to extend

2131the mitigation construction deadline five years, to August 29,

21402010, "to be on the safe side." On May 11, 2005, this minor

2153modification was granted as ERP 0129291-011-EI.

215917. On February 10, 2005, the Port filed the instant

2169application to modify the Construction Permit by eliminating the

2178last sentence of its SC 5 of so that the Port could open and

2192begin beneficial use of the new berths it had constructed before

2203DEP's "final success determination" concerning the Port's related

2211seagrass mitigation.

221318. On March 11 and April 14, 2005, DEP transmitted

2223requests for additional information (RAIs) relating to how the

2232Port would "provide reasonable assurance in a documented

2240commitment plan to full success of the seagrass mitigation

2249credits required by permits 0129291-002-EI and 0129291-003-EI, as

2257well as assurance for financial commitment to accomplish the

2266action plan."

226819. On March 14, 2005, the Port responded to the first RAI,

2280asserting that reasonable assurance was provided by the Port's

22892003/2004 seagrass mitigation monitoring report that requested

229610.44 mitigation credits. The Port further contended that the

2305mitigation was trending toward success and the necessary

2313additional credits would become available in the next year.

2322DEP's second RAI acknowledged those assertions, but in a letter

2332dated April 18, 2005, DEP also requested that the Port submit a

2344remedial action plan for the failed transplantation of Thalassia

2353testudinum (also referred to as T. testudinum and commonly called

2363turtle grass) from the impact area to Mitigation Areas 1, 2,

2374and 3.

237620. On September 9, 2005, DEP responded to the Port's

23862003/2004 seagrass mitigation monitoring report and seagrass

2393mitigation credit request, granting approval of only 6.1 of the

240310.44 mitigation credits requested. In addition, DEP commented

2411that "pursuant to the requirements of the mitigation plan, MCPA

2421shall prepare and submit a remedial action plan to the Department

2432for review and approval." This comment referred to the failed

2442transplantation of T. testudinum .

244721. On September 29, 2005, the Port submitted its

2456Resolution PA 05-16 reaffirming the Port's commitment to fully

2465comply with the conditions of its permits, "including, but not

2475limited to, conditions relating to seagrass mitigation."

248222. By letter dated October 25, 2005, Martin Seeling

2491explained to Petitioners why DEP staff was recommending at the

2501time that the pending application to modify the Construction be

2511granted:

2512All the originally required mitigation

2517activities have now been completed, and some

2524additional planting in Mitigation Sites 1-4

2530was completed this September. Based both on

2537the permittee's reports and the Department's

2543inspections, about half of the seagrass

2549mitigation credits have been achieved, and

2555the rest of the mitigation is clearly

2562trending toward success. We anticipate that

2568nearly all the remaining credits will be

2575achieved with the next year.

2580The purpose of the referenced permit

2586condition was to provide a strong incentive

2593for the permittee to complete the mitigation

2600in a timely manner and to provide the

2608Department with assurance that the loss of

2615seagrasses could indeed be mitigation. Both

2621of those goals appear to have been

2628accomplished. At this point, the main thing

2635needed for the mitigation success is

2641additional time.

2643Since there is no real advantage to be gained

2652by keeping the berths closed, Department

2658staff have recommended issuance of the permit

2665modification. One of our requirements for

2671the Port to complete this application was for

2679them to provide some alternate form of

2686assurance that the mitigation would be

2692completed. Our first suggestion of a surety

2699bond was not feasible, but the Port was able

2708to provide assurance by way of a . . .

2718Resolution (our second recommendation). In

2723addition to the resolution, we can also add

2731new (or revise existing) permit conditions to

2738strengthen the assurance that the Port will

2745actively pursue mitigation success until it

2751is achieved.

275323. On December 12, 2005, Martin Seeling advised the Port

2763that, according to DEP's Office of General Counsel, contrary to

2773earlier indications, the requested modification to SC 5 of the

2783Construction Permit "would require a major modification to the

2792permit"; and DEP requested the permit application fee that

2801applies to a major modification application.

280724. On February 15, 2006, the Port submitted an Annual

2817Progress and Mitigation Success Report claiming entitlement to

282513.06 seagrass mitigation success credits.

283025. On April 7, 2006, DEP issued a proposed agency action

2841that not only granted the Port's requested permit modification by

2851eliminating the last sentence of SC 5 of the Construction Permit,

2862but also combined and modified the Construction Permit Seagrass

2871Mitigation Permit Special Conditions to:

2876a. clarify the actions required and

2882mitigation ratios applied to the various

2888mitigation Sites as shown in the Seagrass

2895Mitigation Table included in proposed amended

2901SC 2;

2903b. clarify the reporting and coordination of

2910monitoring between the seagrass mitigation

2915supervisor and DEP in proposed amended SC 4e,

2923f and g;

2926c. clarify that Mitigation Site 9B would be

2934removed from the mitigation program because

2940of seagrass impacts in that Site caused by an

2949unauthorized discharge of clay during

2954construction activities in proposed amended

2959SC 5f;

2961d. clarify the use of Areas of Interest in

2970the methodology for documenting seagrass

2975mitigation success in proposed amended SC 8;

2982e. clarify that an evaluation of "overall

2989net change" within Mitigation Sites 1, 2, 3,

29978 and 9 would be required in addition to the

3007Area of Interest analysis in proposed amended

3014SC 8e;

3016f. require analysis of the propeller scar

3023recovery areas by monitoring and

3028characterizing the seagrass species and

3033density in 10 propeller scars selected by the

3041mitigation supervisor in proposed amended

3046SC 8g;

3048g. required submittal of a seagrass planting

3055plan for mitigation of impacts in the

3062flushing channels at Mitigation Site 7,

3068including "information regarding the pre-

3073impact seagrass community (density and

3078species composition) to assist the

3083Department's determination of restoration

3087success" in proposed amended SC 8; and

3094h. required submittal of a Remedial Action

3101Plan within 60 days, including planting to

3108re-establish T. testudinum to "compensate for

3114the temporal loss of approximately 3 acres of

3122T. testudinum " in proposed amended SC 14.

312926. The NOI issued with the April 7, 2006, proposed agency

3140action explained that additional assurances in the Seagrass

3148Mitigation Permit would be required and that remedial action for

3158the loss of Thalassia would also be required.

316627. The Port received a draft of the April 7, 2006,

3177proposed agency action and submitted a "White Paper" explaining

3186that it considered many of the requirements to be new

3196requirements, not included in the Seagrass Mitigation or

3204Construction Permits, that "raised the bar," making it more

3213difficult for the Port to achieve seagrass mitigation success.

3222DEP's mitigation credit consultants, Cheryl Miller and Don Deis

3231of PBS&J Corporation, responded with a memo refuting the Port's

3241contentions and defending the April 7, 2006, proposed agency

3250action. Ms. Miller, Mr. Deis and Martin Seeling, Environmental

3259Administrator for DEP's Bureau of Beaches and Coastal Systems

3268continue to support the April 7, 2006, proposed agency action and

3279do not consider it to "raise the bar." The current seagrass

3290mitigation supervisor Thomas Ries supported most the permit

3298modifications proposed by DEP and thought they were necessary.

3307However, the Port disputed the addition of minor Seagrass

3316Mitigation Permit modifications to the major Construction Permit

3324modification the Port requested. DEP gave the Port an extension

3334of time to file a petition for an administrative hearing while

3345the matter was further discussed.

335028. On April 18, 2006, DEP transmitted a draft Seagrass

3360Mitigation Credit Assignment letter dated April 21, 2006, that

3369approved 10.86 of the requested 13.06 seagrass mitigation success

3378credits.

337929. The Port met with DEP on April 28, 2006, and advocated

3391for additional credits. As a result of this meeting, DEP's

3401Deputy Director of the Division of Water Resource Management,

3410Janet Llewellyn, on behalf of DEP, decided that the Port should

3421be granted an additional .59 mitigation credits for a combined

3431Area of Interest (AOI) 8A/8B. On May 10, 2006, DEP issued a

3443credit assignment letter granting 11.45 credits, including the

3451additional credits assigned in the combined AOI 8A/8B.

345930. During the meeting on April 28, 2006, DEP and Port

3470representatives also agreed that the additional permit

3477modifications proposed by DEP in the April 7, 2006, proposed

3487agency action would be removed from the proposed major

3496modification of the Construction Permit, discussed, and

3503negotiated; and that the Port would apply for modification of the

3514Seagrass Mitigation Permit to incorporate some or all of those

3524modifications in the Seagrass Mitigation Permit, including a

3532requirement to implement a Turtle Grass Remedial Action Plan.

3541The Port subsequently continued to characterize DEP's demand for

3550a Remedial Action Plan addressing the loss of Turtle Grass as

"3561raising the bar" and opposed it.

356731. On July 5, 2006, DEP issued a Revised NOI regarding the

3579requested permit major modification and a revised permit

3587modification that granted the Port's request to be allowed to

3597open and begin using the expanded berth facilities and included

3607only limited other edits and clarifications. Specifically, the

3615language at issue in SC 5 was changed to read:

3625The final success determination, showing that

363112.7 credits have been achieved, must be

3638documented and approved by the Department

3644prior to the original-expiration date of this

3651permit (December 17, 2007).

3655The Revised NOI explained that Port Resolution PA-05-16 and the

36652005 annual monitoring report documenting 11.45 credits provided

3673reasonable assurance of seagrass mitigation success without the

3681additional modifications proposed in the April 7, 2006, proposed

3690agency action.

369232. Petitioners supported issuance of the April 7, 2006,

3701proposed agency action or denial of the major modification. When

3711the revised NOI was issued, Petitioners requested an

3719administrative hearing to oppose the major modification of the

3728Construction Permit unless the minor Seagrass Mitigation Permit

3736modifications were added back in.

374133. The Port had not yet submitted an application for the

3752modifications of the Seagrass Mitigation Permit. The Port

3760continued to characterize the requirement to implement a Remedial

3769Action Plan addressing the temporal loss of Turtle Grass as

"3779raising the bar" and has not yet committed to remedial actions

3790by the end of the final hearing in this case.

3800C. Significance of Turtle Grass Transplant Failure

380734. The Expansion Project is between two aquatic preserves,

3816Cockroach Bay Aquatic Preserve to the north and Terra Ceia

3826Aquatic Preserve to the south, waterward of the Cockroach Bay

3836State Buffer Preserve, and includes several types of seagrass as

3846well as a relatively productive benthic community, supporting a

3855wide array of corals, worms, crabs, fish, invertebrates, and

3864dolphins.

386535. Seagrass beds expand and contract, move with the

3874sediment around them, may be buried and unburied in sediments,

3884and have been observed to appear to "come and go" over areas as

3897large as 50 acres in Tampa Bay. These changes may occur

3908seasonally and over time depending on climate, water quality and

3918other factors. Three types of seagrass were identified in the

3928Impact Areas, Thalassia testudinum , Halidule wrightii , and

3935Syringodium filiforme --commonly called Turtle Grass, Shoal Grass,

3943and Manatee Grass. Approximately 3 acres of Turtle Grass and

39532.33 acres of Shoal Grass were transplanted from the Impact

3963Areas.

396436. Shoal Grass is a diminutive type of seagrass with roots

3975that occupy only the first few inches of sediment. Shoal Grass

3986has less bio-mass, less weight, less leaf structure and less

3996rhizome structure that Turtle Grass. Shoal Grass grows and

4005colonizes rapidly in shallow shoals and commonly proliferates in

4014the summer when waters are warm and loses leaves and dies back in

4027the winter when the water cools. Through persistence of buried

4037rhizomes, Shoal Grass can survive being exposed during very low

4047tides. Rain can adversely affect Shoal Grass by rapidly changing

4057salinity and nutrient loads carried by stormwater. Shoal Grass

4066is an early successional species that is adapted to being

4076uprooted and moved by currents and re-anchoring and re-rooting.

408537. Turtle Grass is a much more robust species, typically

4095five to ten times the bio-mass of shoal grass, including larger

4106leaves, rhizomes, and roots. Turtle Grass grows more slowly and

4116is more resistant to being dislodged because its roots and

4126rhizomes are larger and grow 6 to 8 inches deep in the sediment.

4139Turtle Grass is a climax species in terms of succession in Tampa

4151Bay. Turtle Grass plants must be handled carefully because of

4161their unique growing pattern that relies on a number of leaves to

4173provide food to a buried rhizome that then feeds a growing tip or

4186meristem that grows horizontally.

419038. Turtle Grass has broader leaves that extend upward

4199together and move in the water, providing greater protection for

4209certain species that other seagrasses provide. Turtle Grass

4217provides a much more distinct fish nursery and shrimp nursery

4227function. Because Turtle Grass grows in deeper water, it

4236provides more refuge for fish. Turtle Grass provides habitat for

4246species like scallops and larger shrimp. Turtle Grass rhizomes

4255store a great deal of energy which enables Turtle Grass to

4266withstand adverse conditions to a greater degree than other sea

4276grasses.

427739. The loss of approximately 3 acres of Turtle Grass

4287represented a substantial loss of habitat. This loss of habitat

4297had a substantial adverse effect on fish and wildlife utilization

4307in the Port Manatee Expansion Project area. The reduced fish and

4318wildlife utilization associated with the loss of turtle grass

4327substantially affected recreational fishing, birding, and

4333wildlife observation opportunities in the Port Manatee Expansion

4341Project area.

434340. The NOI issued in conjunction with the Seagrass

4352Mitigation Permit includes a lengthy summary at page 5 describing

4362the Port's proposed seagrass mitigation activities, including

4369specifically that Turtle Grass from the impact area would be

4379transplanted to Mitigation Sites 1, 2, and 3.

438741. The Seagrass Mitigation Plan requires the Port to map

4397the specific types of seagrasses found in the Impact Areas and

4408describes the details for the seagrass mitigation effort,

4416including on page 11 that "All turtlegrass in areas A and B to be

4430dredged will be transplanted to mitigation Sites 1, 2, and 3."

444142. The "Monitoring Required" section on page 16 of the

4451Seagrass Mitigation Permit states DEP may require remedial

4459actions if the mitigation is not successful pursuant to the

4469permit conditions.

447143. The Seagrass Mitigation Plan describes the remedial

4479actions required for transplantation failure, requiring remedial

4486planting if seagrass transplanted to Sites 1, 2, and 3 was not

4498successful due to bioturbation or excessive currents.

450544. The Seagrass Mitigation Plan includes a Success

4513Assessment Methodology Summary that explains in relevant part:

4521If the mitigation is not successful, remedial

4528action will be taken to ensure success.

4535Reasonable assurance of success is provided

4541by advanced transplanting, the mitigation

4546ratios, over-design of mitigation

4550opportunities, and a remedial action plan.

455645. The Expansion Project was time-sensitive due to

4564financing opportunities, resulting in the need to use unproved

4573techniques to timely accomplish the transplantation. The

4580Seagrass Mitigation Plan describes a process for selecting a

4589contractor and the contractor's proposed method. The Plan

4597describes "proven" and "alternative" methods for transplanting

4604seagrasses at a high rate by maximizing the size of sod units.

461646. The Port began its seagrass mitigation program in early

46262000 with the "Early Start Program" involving small-scale

4634transplanting experiments. The Seagrass Mitigation Plan

4640documents that the planting of seagrass began on April 3, 2000,

4651and that the transplanting of Turtle Grass from the impact areas

4662into mitigation site 1, 2, and 3 was scheduled to begin as soon

4675as possible after DEP issued the Permit.

468247. The Port retained a firm known as ASISI, owned by Jim

4694Anderson, to provide seagrass transplantation services, including

4701the large-scale or "mega-unit" transplants needed to expedite the

4710project, and ASISI developed a system for transplanting Shoal

4719Grass units and a system for transplanting 4-foot by 5-foot sods

4730of Turtle Grass from the Impact Areas to Mitigation Sites 1, 2,

4742and 3. The sod transplanting machine developed by ASISI used a

4753process referred to in the Seagrass Mitigation Plan as one of the

"4765alternative methods," the "modified tree spade" method.

477248. In July 2001, Robin Lewis reported to the Port

4782regarding Mr. Lewis' seagrass transplantation monitoring.

4788Mr. Lewis cautioned the Port that ASISI's test planting of

4798several Turtle Grass sod units had been too rough on the Turtle

4810Grass sod units and that they were not likely to survive and

4822persist.

482349. During the summer of 2001, ASISI began to mechanically

4833transplant about three acres of Turtle Grass from the Impact

4843Areas to Mitigation Sites 2 and 3. This up-front seagrass

4853transplantation was intended to provide immediate partial

4860mitigation for the seagrass impacts.

486550. In August 2001, Mr. Lewis warned the Port that ASISI's

4876mega-unit transplant efforts using the modified tree spade method

4885were failing. Mr. Lewis asserted that the sod units were not

4896being handled gently enough and were not being installed

4905carefully into excavated holes with their surfaces flush with or

4915below grade, as required by the Seagrass Mitigation Plan.

4924Pursuant to the Seagrass Mitigation Plan, Mr. Lewis urged the

4934Port to consider changing the methods employed to transplant

4943seagrass. Mr. Lewis recommended to the Port that it at least

4954immediately retain divers to follow ASISI's sod transplanting

4962machine to manually re-install Turtle Grass plants that were

4971damaged or improperly planted by the mechanical system. The Port

4981approved this "diver mop-up" program in November 2001, and diver

4991mop-up efforts were incorporated into the transplantation

4998process. These efforts proved to be successful only to a limited

5009extent because they were too late after most of the transplanting

5020had already taken place and most of the sod had washed away.

503251. In 2001, while ASISI was mechanically transplanting

5040Turtle Grass from the Impact Areas to Sites 2 and 3, Mr. Lewis'

5053company was staking, preparing final designs, and implementing

5061the Piney Point mitigation projects in Mitigation Sites 4A and

50716A, involving scrape-down of deposited sediments and Shoal Grass

5080planting. The Port's engineer testified to his concern that

5089Mr. Lewis was not around to supervise and assist ASISI's mega-

5100unit Turtle Grass transplantation, but the Port had advised

5109Mr. Lewis that he was not to monitor ASISI's transplanting

5119efforts because ASISI's principal, Jim Anderson, did not want him

5129to do so.

513252. During 2002, Mr. Lewis informally monitored ASISI's

5140mega-unit transplants and found that just over 100 units had

5150survived out of a total of 12,000 units transplanted. Subsequent

5161monitoring found that virtually none of the Turtle Grass units

5171survived and persisted. Turtle Grass is slow-growing, and only

5180less than an acre has grown throughout the mitigation area.

5190D. Disputed Credit Determinations

519453. Mr. Lewis' 2002 annual monitoring of all of the

5204mitigation sites established a sufficient acreage of new seagrass

5213to allow the Port to initiate dredging for part of the Expansion

5225Project. Nonetheless, the Port rejected Mr. Lewis' analysis of

5234the seagrass mitigation acreage and expressed disappointment

5241Mr. Lewis would not include additional seagrass acreage the Port

5251wished to claim as mitigation that Mr. Lewis considered pre-

5261existing seagrass.

526354. In late 2002, the Port determined that it would not

5274renew its contract with Lewis Environmental Services for 2003.

5283After some disagreement about Mr. Lewis' remaining

5290responsibilities under the existing contract, Mr. Lewis agreed to

5299prepare the annual monitoring report for 2002 but refused to

5309prepare or certify the November 2002 credit report submitted by

5319the Port. In a December 31, 2002, letter to the Port's George

5331Isiminger, Robin Lewis submitted his resignation as the

5339Mitigation Supervisor of record "on the basis of personal and

5349professional ethics."

535155. In early 2003, DEP accepted that the Port's November

53612002 seagrass mitigation success report documented at least 5.66

5370acres of new seagrass in the mitigation sites and authorized the

5381Port to begin dredging for the Expansion Project.

538956. The Port subsequently retained Thomas Ries as the

5398successor mitigation supervisor and continued to monitor the

5406seagrass mitigation and submit annual progress reports and credit

5415requests.

541657. Robin Lewis maintained an interest in the seagrass

5425mitigation project and requested copies of the Port's submittals

5434and submitted comments and concerns regarding the Port's credit

5443requests and documentation. Mr. Lewis' submittals were

5450considered by DEP in determining how much credit to approve. In

5461some cases, Mr. Lewis and DEP found that the Port requested more

5473credits than it was entitled to and employed analyses that were

5484not completely correct. Subsequent discussions revealed

5490disagreements regarding the meaning of permit conditions and how

5499to document seagrass mitigation success. As result of these

5508discussions, DEP corrected some errors and did not award all of

5519the requested credit.

552258. Due to extensive discussion of disagreements concerning

5530the Port's credit request for 2003, DEP recommended that a

5540combined credit request for 2003 and 2004 be submitted in 2005.

5551The combined credit request for 2003/2004 was submitted on

5560March 4, 2005. It requested a cumulative total of 10.44 credits.

5571After discussion, an RAI, and a DEP inspection, DEP granted

5581approval of a cumulative total of 6.1 credits by letter dated

5592September 9, 2005.

559559. The Port's next credit request was submitted in

5604February 2005 and was for a cumulative total of 13.06 credits.

5615After discussion, DEP granted 11.45 credits in April 2006.

562460. The Port proved that it was entitled to at least 10.86

5636credits under the Seagrass Mitigation Permit through 2005. The

5645only real remaining credit determination issue is whether the

5654Port is entitled to 10.86 or 11.45 credits. (Since the Port did

5666not challenge the credit determination, it waived the right to

5676credit in excess of 11.45 credits.) This determination depends

5685on the use of combined AOI 8A/8B.

569261. The use of AOI was a concern to DEP and a point of

5706contention because it is possible for the selection of AOIs to

5717introduce bias in the monitoring. In the case of combined AOI

57288A/8B, an AOI where mitigation credit was to be earned by

5739increasing seagrass coverage by excluding motorized boats and

5747allowing seagrass to recover in prop scars, there was no aerial

5758photography for the baseline year 1999 for use in determining

5768increased coverage in 8B. However, the Port interpreted the

5777language of the Seagrass Mitigation Permit to allow the Port to

5788assume complete coverage in the baseline year for 8B (and no

5799increased coverage there), measure increased coverage in 8A, and

5808calculate credits based on the increases in 8A, multiplied by a

5819mitigation ratio that applied to the acreage of the combined AOI

58308A/8B, since the increased seagrass coverage in Site 8A was great

5841enough mathematically to meet the percentage increase required

5849for credit for both Area 8A and 8B. This interpretation and

5860calculation resulted in a request for .59 credits for the

5870combined AOI 8A/8B.

587362. Because this interpretation assumed complete coverage

5880in Site 8A in baseline year 1999, the Port argued that it was a

"5894conservative" approach. After the meeting on April 28, 2006,

5903Ms. Lewellyn agreed.

590663. Petitioners contended that this "conservative" approach

5913in effect would award mitigation credit for Site 8B even if

5924seagrasses contracted or even were eliminated in Site 8B after

5934the baseline year 1999. Although such a result probably was not

5945intended, the approach taken with respect to AOI 8A/8B was not

5956inconsistent with the literal language of the Seagrass Mitigation

5965Permit.

596664. In addition, on more than one occasion, DEP could have

5977advised the Port that it would not approve credits for the

5988combined AOI 8A/8B because aerial photography for the baseline

5997year 1999 was not available, mitigation success in Site 8B could

6008not be verified, and credit could not be awarded for Site 8B.

6020Ms. Llewellyn thought that, after letting those opportunities

6028pass, it would be unfair for DEP to now deny the credits

6040requested by the Port for the combined AOI 8A/8B through 2005.

6051Based on the totality of the evidence, it is found that the Port

6064is entitled to 11.45 credits at this time.

6072E. Unauthorized Discharges of Sediment and Other

6079Violations of DEP rules; O.G.C. File No. 05-2790

608765. During the summer of 2004, there was an inadvertent

6097release of dredged material from a disposal area into Mitigation

6107Site 9B in conjunction with the Port's implementation of the

6117Expansion Project under the Construction Permit. This violated

6125SC 14, 17, and 18 of the Construction Permit, and SC 5 of the

6139Seagrass Mitigation Permit, and killed about 2.52 acres of mixed

6149seagrass beds consisting of Turtle Grass and Shoal Grass growing

6159in Mitigation Site 9B. The Port promptly notified DEP and

6169initiated corrective action. The matter was resolved by issuance

6178of a Consent Order, which was not challenged. As of July 2006,

6190the Port had removed the sediment, but destruction of these 2.52

6201acres of Turtle Grass and Shoal Grass remained un-mitigated as of

6212the time of the hearing.

621766. Clearly, the additional loss of approximately 2.52

6225acres of Turtle Grass and Shoal Grass in Mitigation Site 9B

6236represents an additional substantial loss of habitat and the

6245functions performed by the habitat. This additional habitat loss

6254will have a substantial affect on fish and wildlife utilization

6264in the Port Manatee area. However, Petitioners' attempt to

6273characterize these as part of the "cumulative impacts" of the

6283Expansion Project is not well-founded. Rather, they are an

6292inadvertent permit violation that has been resolved by consent

6301order. As such, those matters do not bear on whether the pending

6313permit modification request should be granted.

6319F. Consideration of the Relevant Factors

632567. Reasonable assurance of successful mitigation for the

6333impacts of the Expansion Project was predicated on four factors

6343identified in the Seagrass Mitigation Plan: the upfront

6351transplantation of seagrass; the mitigation ratios; the credits

6359available in the program; and the remedial action requirements.

636868. As found, the purpose of the last sentence of

6378Construction Permit SC 5--making the opening and use of the new

6389facilities contingent on documentation of the "final success

6397determination, showing 12.7 credits have been achieved"--was to

6406provide DEP reasonable assurance that the loss of seagrasses

6415would be successfully mitigated in a timely manner by

6424establishing a strong incentive for the permittee to complete the

6434mitigation promptly.

643669. As found, the Port is entitled to 11.45 credits for its

6448seagrass mitigation efforts to date. The mitigation project is

6457trending towards continued success in terms of credits, and it is

6468not unreasonable to expect 12.7 credits to be achieved in the

6479near future due to natural processes alone. For these reasons,

6489it is found that the permit modification requested by the Port

6500and now also proposed by DEP would not delay achievement of 12.7

6512credits.

651370. It is less clear whether the permit modification

6522requested by the Port and now also proposed by DEP would delay

6534the "final success determination," including remediation of the

6542Turtle Grass component of the upfront transplantation, which

6550could include planting Turtle Grass. Through the final hearing,

6559the Port and DEP had not come to an agreement on what such

6572remediation should include. (While not clear from the evidence,

6581it seems possible that the Port even may take the position that

6593the "final success determination" will occur when 12.7 credits

6602are documented regardless of the failure of the Turtle Grass

6612transplantation.) It is Petitioners' position that SC 5 of the

6622Construction Permit is an important incentive for the Port to

6632timely remediate the failure of the Turtle Grass transplantation

6641and that it should not be modified without clarification at least

6652as to the remediation required for the failure of the Turtle

6663Grass transplantation. Under the totality of the circumstances

6671of this case, Petitioners' position has merit.

6678G. Improper Purpose

668171. Even if Petitioners ultimately prevail do not prevail,

6690the evidence did not establish that they participated in this

6700proceeding primarily to harass or to cause unnecessary delay, or

6710for frivolous or improper purpose or to needlessly increase the

6720Port's cost to obtain the approval. Rather, their purpose has

6730been to protect the natural resources of Tampa Bay, in particular

6741its seagrass habitat.

6744CONCLUSIONS OF LAW

6747H. Standing

674972. Section 403.412(5), Florida Statutes, gives Manasota-88

6756standing to petition to challenge proposed agency action.

676473. Petitioners have a substantial interest in mitigation

6772of the seagrass habitat impacts of the Expansion Project which is

6783cognizable under the permitting criteria applicable to the

6791subject permit applications. As a result, Petitioners have

6799substantial interests that will be affected by the proposed

6808agency action. As such, Petitioners have standing pursuant to

6817Sections 120.52(12)(b) and 120.569(1), Florida Statutes. See

6824also § 403.412(5)-(6), Fla. Stat.

682974. The Petitioners have established an immediate injury-

6837in-fact sufficient to allow them to participate as parties, and

6847they have standing to challenge the proposed agency action.

6856J. Burden of Proof

686075. As the applicant, the Port has the burden of showing by

6872preponderance of the credible and credited evidence that it is

6882entitled to the approval at issue here. Department of

6891Transportation v. J.W.C. Co. , 396 So. 2d 778, 789 (Fla. 1st DCA

69031981).

690476. If the Port makes a prima facie showing of reasonable

6915assurances, the burden shifts to Petitioners to present evidence

6924of equivalent quality. J.W.C. Co. , 396 So. 2d at 789.

6934I. Permit Criteria

693777. ERP conditions of approval are set forth in Chapter

6947373, Florida Statutes, and in Rule Chapter 62-330, which

6956incorporates certain Southwest Florida Water Management District

6963(SWFWMD) rules in effect in 2005, including Rules 40D-4.301 and

697340D-4.302, and the 2005 SWFWMD Basis of Review. To demonstrate

6983entitlement to the major modification, the Port is required to

6993provide reasonable assurance to DEP that it will meet these

7003conditions of approval.

700678. "Reasonable assurance" means "a substantial likelihood

7013that the project will be successfully implemented." Metropolitan

7021Dade County v. Coscan Florida, Inc. , 609 So. 2d 644, 648 (Fla. 3d

7034DCA 1992); Save Anna Maria, Inc. v. Department of Transportation ,

7044700 So. 2d 113, 117 (Fla. 2d DCA 1997). Reasonable assurances

7055must take into account contingencies that might reasonably be

7064expected, but an applicant is not required to eliminate all

7074contrary possibilities, however remote, or to address impacts

7082which are only theoretical and not reasonably likely.

709079. The test in this case is not whether DEP properly

7101evaluated the original application, but whether the Port provided

7110reasonable assurance that the applicable conditions for issuance

7118of the major modification have been satisfied. When a permittee

7128seeks to modify an existing permit, regulatory review includes

7137only that portion of the existing permit that is proposed to be

7149modified. See Friends of the Everglades, Inc. v. Dept. of

7159Environmental Reg. , 496 So. 2d 181, 183 (Fla. 1st DCA 1986);

7170Behrens v. Boran , ORDER NO. SWF 02-052, 2 ER FALR 257 (SWFWMD

7182Aug. 27, 2002), DOAH Case No. 02-0282, 2002 Fla. ENV LEXIS 192

7194(DOAH July 29, 2002); Kunnen v. Southwest Fla. Water Mgmt. Dist. ,

7205ORDER NO.: SWF 02-003, DOAH Case No. 01-2571, 2002 Fla. ENV LEXIS

72174 (SWFWMD Jan. 29, 2002; DOAH Dec. 17, 2001). The "reasonable

7228assurance" requirement applies to the activities for which

7236permitting is presently sought and does not burden the applicant

7246with "providing 'reasonable assurances' anew with respect to the

7255original project already constructed in accordance with a valid

7264permit." Friends of the Everglades , supra at 183. Therefore, a

7274determination of whether the Port has provided reasonable

7282assurances to the DEP is limited to a review of those portions of

7295the proposed permit modification that are different from the

7304Construction Permit it is modifying.

730980. The proposed permit modification does not authorize any

7318additional construction activities or any additional impacts, it

7326merely provides for utilization of already constructed facilities

7334prior to a final determination of complete seagrass mitigation

7343success. The question is whether the Port will continue to

7353provide reasonable assurance without the last sentence of SC 5 of

7364the Construction Permit.

736781. Section 373.413, Florida Statutes, and Rule 40D-4.301

7375relate to the construction, alteration, operation, maintenance,

7382removal, or abandonment of a storm water management system. The

7392Construction Permit does not authorize any upland activities

7400requiring the development of a stormwater management system since

7409the authorized construction is dredging in the waters of Tampa

7419Bay.

742082. Pursuant to Section 373.414(1), Florida Statutes, an

7428ERP applicant must provide reasonable assurance that the proposed

7437activity "is not contrary to the public interest" based upon a

7448balancing of the factors listed in Section 373.414(1)(a), and

7457taking into account measures proposed by the applicant to

7466mitigate adverse effects as contemplated by Section

7473373.414(1)(b), Florida Statutes.

747683. Section 373.414(1)(b), Florida Statutes, provides in

7483relevant part that:

7486It shall be the responsibility of the

7493applicant to choose the form of mitigation.

7500The mitigation must offset the adverse

7506effects caused by the regulated activity.

7512In this case, the regulated activity is dredging and filling in

7523Tampa Bay, including dredging in the Impact Areas where

7532approximately 5.33 acres of seagrass existed. To offset these

7541seagrass impacts, the Port proposed and agreed to the mitigation

7551required by the Seagrass Mitigation Permit and the Construction

7560Permit, including the requirement the Port seeks to modify in

7570this proceeding.

757284. Rule 40D-4.302(2) requires DEP to take into

7580consideration the rule violations that resulted from the

7588inadvertent release of dredged material, as well as the efforts

7598taken by the Port to resolve the violations, when determining

7608whether the Port has provided reasonable assurance that

7616permitting standards will be met. The Port's rule violations

7625addressed in the Consent Order are substantial and significantly

7634adversely affect the existing Turtle Grass and other habitats in

7644the Port Manatee area. However, the Port has cooperated to the

7655extent of entering into the Consent Order and agreeing to

7665mitigate for the impacts. The adverse impacts to Turtle Grass

7675and Shoal Grass in the Expansion Project area have not yet been

7687fully mitigated, but progress is being made in that direction.

7697Since the violations were inadvertent, and have been resolved by

7707the Consent Order, they are not valid reasons to deny the permit

7719modification requested by the Port and now also proposed by DEP.

773085. Pursuant to Section 373.414(8)(a), Florida Statutes,

7737DEP is required to "consider the cumulative impacts upon surface

7747water and wetlands" of certain types of activities. But the loss

7758of seagrasses by the inadvertent, unauthorized discharge of

7766sediment in 2004 should not be considered cumulative impacts for

7776purposes of this major modification application, and they have

7785been addressed in the Consent Order.

779186. Opening the new berths is in the public interest if it

7803will not delay implementing the seagrass mitigation program.

7811Among other things, SC 14 of the agency action proposed on

7822April 7, 2006, would clarify that a Remedial Action Plan for the

7834temporal loss of Turtle Grass is required by the Seagrass

7844Mitigation Permit and must be performed. As found, if the

7854requested modification to SC 5 of the Construction Permit is to

7865be granted, the Port should be required to submit a Remedial

7876Action Plan within 60 days in accordance with and as set forth in

7889amended SC 14 proposed by DEP on April 7, 2006.

789987. Attorney's fees are awardable to the prevailing party

7908under Section 120.595(1), Florida Statutes. If this Recommended

7916Order is adopted, the Port would not be considered the prevailing

7927party for purposes of that statute. Even if the Port were the

7939prevailing party, attorney's fees are not awardable under the

7948statute because, as found, it was not proven that Petitioners

7958participated in this proceeding primarily to harass or to cause

7968unnecessary delay, or for frivolous or improper purpose or to

7978needlessly increase the Port's cost to obtain the approval.

7987RECOMMENDATION

7988Based upon the foregoing Findings of Fact and Conclusions of

7998Law, it is

8001RECOMMENDED that DEP grant the requested modification to SC

80105 of the Construction Permit with a condition that the Port

8021submit a Remedial Action Plan within 60 days in accordance with

8032and as set forth in amended SC 14 proposed by DEP on April 7,

80462006.

8047DONE AND ENTERED this 6th day of February, 2007, in

8057Tallahassee, Leon County, Florida.

8061S

8062J. LAWRENCE JOHNSTON

8065Administrative Law Judge

8068Division of Administrative Hearings

8072The DeSoto Building

80751230 Apalachee Parkway

8078Tallahassee, Florida 32399-3060

8081(850) 488-9675 SUNCOM 278-9675

8085Fax Filing (850) 921-6847

8089www.doah.state.fl.us

8090Filed with the Clerk of the

8096Division of Administrative Hearings

8100this 6th day of February, 2007.

8106COPIES FURNISHED :

8109Lea Crandall, Agency Clerk

8113Department of Environmental Protection

8117The Douglas Building, Mail Station 35

81233900 Commonwealth Boulevard

8126Tallahassee, Florida 32399-3000

8129Tom Beason, Acting General Counsel

8134Department of Environmental Protection

8138The Douglas Building, Mail Station 35

81443900 Commonwealth Boulevard

8147Tallahassee, Florida 32399-3000

8150Michael W. Sole, Secretary

8154Department of Environmental Protection

8158The Douglas Building, Mail Station 35

81643900 Commonwealth Boulevard

8167Tallahassee, Florida 32399-3000

8170W. Douglas Beason, Esquire

8174Department of Environmental Protection

8178The Douglas Building, Mail Station 35

81843900 Commonwealth Boulevard

8187Tallahassee, Florida 32399-3000

8190John R. Thomas, Esquire

8194Thomas & Associates, P.A.

8198233 Third Street North, Suite 101

8204St. Petersburg, Florida 33701-3818

8208Kevin S. Hennessy, Esquire

8212R. David Jackson, Esquire

8216Lewis, Longman & Walker, P. A.

82221001 Third Avenue West, Suite 670

8228Bradenton, Florida 34205-7848

8231NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

8237All parties have the right to submit written exceptions within 15

8248days from the date of this Recommended Order. Any exceptions to

8259this Recommended Order should be filed with the agency that will

8270issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 03/26/2007
Proceedings: Final Order filed.
PDF:
Date: 03/23/2007
Proceedings: Petitioners` Response to Port Authority`s Exceptions filed.
PDF:
Date: 03/23/2007
Proceedings: Department of Environmental Protection`s Responses to the Manatee County Port Authority`s Exceptions to the Recommended Order filed.
PDF:
Date: 03/23/2007
Proceedings: Respondent Manatee County Port Authority`s Exceptions to Recommended Order filed.
PDF:
Date: 03/22/2007
Proceedings: Agency Final Order
PDF:
Date: 02/06/2007
Proceedings: Recommended Order
PDF:
Date: 02/06/2007
Proceedings: Recommended Order (hearing held October 30-31 and November 1, 2006). CASE CLOSED.
PDF:
Date: 02/06/2007
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 02/06/2007
Proceedings: Order Denying Attorney`s Fees.
PDF:
Date: 01/03/2007
Proceedings: Petitioner`s Amended Proposed Recommended Order filed.
PDF:
Date: 01/03/2007
Proceedings: Petitioners` Notice of Filing Amended Proposed Recommended Order filed.
PDF:
Date: 01/02/2007
Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to Petitioners` Motion for SLAPP Fees filed.
PDF:
Date: 12/26/2006
Proceedings: Proposed Recommended Order of Respondent Manatee County Port Authority filed.
PDF:
Date: 12/21/2006
Proceedings: Petitioners` Proposed Recommended Order filed.
PDF:
Date: 12/21/2006
Proceedings: Petitioners` Notice of Filing Proposed Recommended Order.
PDF:
Date: 12/21/2006
Proceedings: Petitioners` Motion for Slapp Fees and Response to Port Manatee Fee Motion filed.
PDF:
Date: 12/21/2006
Proceedings: Department of Environmental Protection`s Proposed Recommended Order filed.
PDF:
Date: 12/21/2006
Proceedings: Proposed Recommended Order of Respondent Manatee County Port Authority filed.
Date: 12/11/2006
Proceedings: Transcript of Proceedings (Volumes I-A through III-B) filed.
PDF:
Date: 11/22/2006
Proceedings: Department of Environmental Protection`s Response in Opposition to the Petitioners` Request for Official Recognition filed.
PDF:
Date: 11/13/2006
Proceedings: Respondent Manatee County Port Authority`s Objections to Certain Excerpts Designated by Petitioners from Depositions of Marty Seeling and Janet Llewellyn filed.
PDF:
Date: 11/13/2006
Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to Petitioners` Request for Official Recognition filed.
PDF:
Date: 11/13/2006
Proceedings: Petitioners` Request for Official Recognition filed.
PDF:
Date: 11/13/2006
Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to the Admission of the Depositions of Don Deis and Cheryl Miller and, in the Alternative, Objections to Petitioners` Designated Excerpts from the Depositions of Don Deis and Cheryl Miller and Respondent`s Submittal of Designation of Excerpts to the Depositions of Don Deis and Cheryl Miller filed.
PDF:
Date: 11/09/2006
Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Cheryl Miller filed.
PDF:
Date: 11/09/2006
Proceedings: Department of Environmental Protection`s Revised Notice of Designation of Excerpts to the Deposition of Martin Seeling filed.
PDF:
Date: 11/09/2006
Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Janet Lllewellyn filed.
PDF:
Date: 11/09/2006
Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Martin Seeling filed.
PDF:
Date: 11/09/2006
Proceedings: Department of Environmental Protection`s Notice of Designation of Excerpts to the Deposition of Donald Deis filed.
PDF:
Date: 11/07/2006
Proceedings: Letter to Judge Johnston from J. Thomas enclosing a substitute for Petitioners` Exhibit 3, December 10, 1999 Environmental Resource Permit Number 0129291-001-EC and Notice of Intent.
PDF:
Date: 11/07/2006
Proceedings: Memorandum in Support of Admission of Depositions of Don Deis and Cheyrl Miller filed.
PDF:
Date: 11/07/2006
Proceedings: Notice of Filing Depositions of Don Deis and Cheyrl Miller and Designation of Petitioners` Excerpts filed.
PDF:
Date: 11/07/2006
Proceedings: Return of Service filed.
PDF:
Date: 11/06/2006
Proceedings: Memorandum in Support of Admission of Depositions of Don Deis and Cheryl Miller filed.
PDF:
Date: 11/06/2006
Proceedings: Notice of Filing Depositions of Don Deis and Cheryl Miller and Designation of Petitioners` Excerpts.
PDF:
Date: 11/06/2006
Proceedings: Letter to Judge Johnston from R. Jackson enclosing copies of the slide pictures from the Hearing filed.
PDF:
Date: 11/06/2006
Proceedings: Notice of Petitioners` Excerpts of Depositions filed by Port Authority.
PDF:
Date: 11/03/2006
Proceedings: Notice of Filing Depositions and Requested Excerpts by Manatee County Port Authority filed with the Judge at Hearing.
PDF:
Date: 11/03/2006
Proceedings: Notice of Filing Depositions filed with the Judge at Hearing.
PDF:
Date: 11/03/2006
Proceedings: Letter to Judge Johnston from J. Thomas enclosing Petitioner`s Proposed Hearing Exhibits filed (exhibits not available for viewing).
PDF:
Date: 11/03/2006
Proceedings: Letter to Parties of Record from J. Thomas regarding the deposition exhibits filed.
PDF:
Date: 11/02/2006
Proceedings: Notice of Filing Depositions and Requested Excerpts by Manatee County Port Authority.
PDF:
Date: 11/02/2006
Proceedings: Letter to Judge Johnston from R. Jackson enclosing Proposed Hearing Exhibits filed (exhibits not available for viewing).
PDF:
Date: 11/02/2006
Proceedings: Letter to R. Jackson from J. Thomas regarding the transmittal of Exhibits to Judge Johnston filed.
Date: 10/30/2006
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 10/27/2006
Proceedings: Respondent Manatee County Port Authority`s Motion for Attorney`s Fees filed.
PDF:
Date: 10/27/2006
Proceedings: Respondent Manatee County Port Authority`s Motion in Limine filed.
PDF:
Date: 10/27/2006
Proceedings: Pre-hearing Stipulation filed.
PDF:
Date: 10/17/2006
Proceedings: Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 10/13/2006
Proceedings: Notice of Continuance of Taking Deposition Duces Tecum filed.
PDF:
Date: 10/12/2006
Proceedings: Notice of Taking Deposition Duces Tecum (signed) filed.
PDF:
Date: 10/11/2006
Proceedings: Department of Environmental Protection`s Witness List filed.
PDF:
Date: 10/10/2006
Proceedings: Petitioner`s Witness List filed.
PDF:
Date: 10/10/2006
Proceedings: Letter to Judge Johnston from J. Thomas regarding the October 4, 2006 Order Granting Continuance and Re-scheduling Hearing filed.
PDF:
Date: 10/06/2006
Proceedings: Notice of Taking Deposition Duces Tecum (unsigned) filed.
PDF:
Date: 10/04/2006
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for October 30 through November 1, 2006; 9:00 a.m.; Bradenton, FL).
PDF:
Date: 10/03/2006
Proceedings: Letter to Judge Johnston from J. Thomas regarding dates available for hearing filed.
PDF:
Date: 10/02/2006
Proceedings: Respondent Manatee County Port Authority`s Notice of Filing Witness List filed.
PDF:
Date: 09/28/2006
Proceedings: Respondent Manatee County Port Authority`s Response in Opposition to Petitioners` Emergency Motion to Continue Hearing and to Compel Discovery and Petitioners` Motion to Impose Expedited Deposition Transcript Costs filed.
PDF:
Date: 09/27/2006
Proceedings: Amended Notice of Hearing (hearing set for October 11 and 12, 2006; 9:00 a.m.; Bradenton, FL; amended as to location).
PDF:
Date: 09/27/2006
Proceedings: Petitioners` Emergency Motion to Continue Hearing and to Compel Discovery filed.
PDF:
Date: 09/27/2006
Proceedings: Motion to Impose Expedited Deposition Transcript Costs filed.
PDF:
Date: 09/27/2006
Proceedings: Department of Environmental Protection`s Responses and Objections to Petitioners` Request for Production filed.
PDF:
Date: 09/26/2006
Proceedings: Department of Environmental Protection`s Notice of Service of Answers to Petitioners` First Set of Interrogatories filed.
PDF:
Date: 09/26/2006
Proceedings: Respondent Manatee County Port Authority`s Responses to Petitioners` Request for Production filed.
PDF:
Date: 09/26/2006
Proceedings: Respondent Manatee County Port Authority`s Notice of Service of Answers & Objections to Petitioners` First Set of Interrogatories filed.
PDF:
Date: 09/22/2006
Proceedings: Notice of Taking Deposition (2) filed.
PDF:
Date: 09/19/2006
Proceedings: Order Denying Motion to Dismiss.
PDF:
Date: 09/19/2006
Proceedings: Order Granting Motion to Expedite (time for discovery responses is shortened to 15 days from service of discovery requests).
PDF:
Date: 09/15/2006
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 09/15/2006
Proceedings: Notice of Hearing (hearing set for October 11 and 12, 2006; 9:00 a.m.; Bradenton, FL).
PDF:
Date: 09/13/2006
Proceedings: Notice of Serving Respondent Manatee County Port Authoritys` First Set of Interrogatories to Petitioner Roy R. Lewis, III filed.
PDF:
Date: 09/13/2006
Proceedings: Notice of Serving Respondent Manatee County Port Authoritys` First Set of Interrogatories to Petitioner Manasota-88, Inc. filed.
PDF:
Date: 09/11/2006
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
PDF:
Date: 09/08/2006
Proceedings: Respondent Manatee County Port Authority`s Response to Initial Order filed.
PDF:
Date: 09/08/2006
Proceedings: Respondent Manatee County Port Authority`s Motion to Dismiss with Prejudice Petitioners` Amended Petition for Formal Administrative Hearing filed.
PDF:
Date: 09/08/2006
Proceedings: Respondent Manatee County Port Authority`s Motion to Expedite Final Hearing filed.
PDF:
Date: 09/08/2006
Proceedings: Notice of Appearance (filed by R. Jackson).
PDF:
Date: 09/08/2006
Proceedings: Petitioners` Response to Initial Order filed.
PDF:
Date: 09/01/2006
Proceedings: Initial Order.
PDF:
Date: 08/31/2006
Proceedings: Revised Notice of Intent filed.
PDF:
Date: 08/31/2006
Proceedings: Revised Notice of Intent to Issue a Major Modification of Consolidated Environmental Resource Permit and Sovereign Submerged Lands Authorization filed.
PDF:
Date: 08/31/2006
Proceedings: Amended Petition for Formal Administrative Proceeding filed.
PDF:
Date: 08/31/2006
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
J. LAWRENCE JOHNSTON
Date Filed:
08/31/2006
Date Assignment:
09/01/2006
Last Docket Entry:
03/26/2007
Location:
Bradenton, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
 

Counsels

Related DOAH Cases(s) (3):

Related Florida Statute(s) (7):

Related Florida Rule(s) (3):