06-004756 Beach Group Investments, Llc vs. Department Of Environmental Protection
 Status: Closed
Recommended Order on Thursday, April 19, 2007.


View Dockets  
Summary: The application for a coastal construction control line permit should be denied because the project extends seaward of the 30-year erosion projection.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8BEACH GROUP INVESTMENTS, LLC, )

13)

14Petitioner, )

16)

17vs. ) Case No. 06 - 4756

24)

25DEPARTMENT OF ENVIRONMENTAL )

29PROTECTION, )

31)

32Respondent. )

34)

35RECOMMENDED ORDER

37A duly - noticed final hearing was held in this case by

49Administrative Law Judge T. Kent Wetherell, II, on February 15 -

6016 , 200 7 , in Tallahassee , Florida.

66APPEARANCES

67For Petitioner: William L. Hyde, Esquire

73Fowler White Boggs Banker, P.A.

78Post Office B ox 11240

83Tallahassee, Florida 32302 - 3240

88For Respondent: Kelly L. Russell, Esquire

94Department of Environmental Protection

98The Douglas Building, Mail Station 35

1043900 Commonwealth Boulevard

107Tallahassee, Florida 32399 - 3000

112STATEMENT OF THE ISSUE

116The issue is whether the Department of Environmental

124Protection should approve Petitioner’s application for a coastal

132construction control line permit .

137PRELIMINARY STATEMENT

139On November 1, 2006, the Department of Environmental

147Protection (Depar tment) issued a proposed final order denying

156Petitioner’s application for a coastal construction control line

164(CCCL) permit. Petitioner timely requested an administrative

171hearing on the denial of its perm it application, and on

182November 21, 2006, the Depar tment referred the matter to the

193Division of Administrative Hearings (D OAH) for the a ssignment of

204an A dministrative L aw J udge to conduct the hearing requested by

217Petitioner.

218The final hearing was initially scheduled for April 4 - 5 ,

229200 7, in Ft. Pierce, but it was rescheduled for February 15 - 16,

2432007, in Tallahassee at the parties’ request. The parties filed

253a Joint Pre - hearing Stipulation on February 12, 2007.

263At the final hearing, Petitioner presented the testimony of

272Michael Walther and Harold Seltzer and the Department presented

281the testimony of Tony McNeal, Michael Barnett, and Emmett

290Foster. The following exhibits were received into evidence:

298Petitioner’s Exhibits (Pet. Ex.) 1, 2, 9 through 11, 15 through

30917, 19 through 27, 29 through 35, 36A through 36C, and 37

321through 39 ; and Department’s Exhibits (Dept. Ex.) 5 through 13,

33116 through 19, 21 through 23, 24A through 24N, and 25 through

34327 . Official recognition was taken of Section 161.053, Florida

353Statues (2006), 1 and Florida Administrative Code Rule Chapter

36262B - 33.

365The three - volume Transcript of the final hearing wa s filed

377on March 1 , 2007 . The parties requested 21 da ys from that date

391to file proposed recommended orders (PROs) , but t he deadline was

402subsequently extended to March 30, 2007, upon Petiti oner’s

411unopposed motion . The PROs were timely filed and have been

422given due consideration.

425FINDINGS OF FACT

428A. Stipulated Facts 2

4321. Petitioner, Beach Group Investments, LLC (Beach Group),

440is a limited liability corporation under Florida law. Its

449addre ss is 14001 63rd Way North, Clearwater , Florida 33760.

4592. On December 19, 2005, Coastal Technology Corporation

467(Coastal Tech) on behalf of Beach Group submitted to the

477Department an application for a CCCL permit pursuant to Chapter

487161, Florida Statute s, to construct 17 luxury townhome units in

498two four - story buildings, a pool, a dune walk - over, and

511ancillary parking and driveway areas (hereafter “the Project ”).

520The Department designated the application as File No. SL - 224.

5313. The property on which the Project is proposed

540(hereafter “the Property ”) is located between the Department's

549reference monument s R - 34 and R - 35, in St. Lucie County . The

565Property’s address is 222 South Ocean Drive, Fort Pierce,

574Florida.

5754. The Property is located seaward of the CCCL line

585estab lished in accordance with S ection 161.053, Florida

594Statutes , and Florida Administrative Code Rule Chapter 62B - 33.

6045. On April 21, 2006, the application was determined to be

615complete.

6166. By letter dated June 5, 2006, the Departme nt notified

627Beach Group that the Project appeared to be located seaward of

638the 30 - year erosion projection of the seasonal high water line

650(SHWL ), and that in accordance with S ection 161.053(6), Florida

661Statutes, the staff could not recommend approval of th e Project

672since major structures are seaward of the estimated erosion

681projection.

6827. By letter dated July 7, 2006, and subsequent

691submittals, Beach Group requested a waiver of the 90 - day time

703period for processing completed applications pursuant to Cha pter

712120, Florida Statutes, until October 31, 2006.

7198. On August 30, 2006, Beach Group submitted a certified

729engineering analysis of the 30 - year erosion projection of the

740SHWL for the Department's consideration pursuant to Florida

748Administrative Code R ule 62B - 33.024(1). Beach Group's analysis

758determined that the proposed major structures associated with

766the Project were located landward, not seaward, of the 30 - year

778erosion projection.

7809. The Department also performed its own 30 - year erosion

791project ion of the SHWL, and determined that the proposed major

802structures were located seaward, not landward, of the 30 - year

813erosion projection. The Department asserts that the proposed

821structures are located between 87 feet and 68 feet seaward of

832the Department 's determination of the 30 - year erosion

842projection.

84310. The Department disagreed with Beach Group's analysis

851because the analysis ap peared to be inconsistent with S ection

862161.053(6), Florida Statutes, Florida Administrative Code Rule

86962B - 33.024, and th e Department's own analysis.

87811. The Property is located just south of the Fort Pierce

889Inlet , and landward of a federally maintained beach restoration

898project that had approximately 14 years of life remaining under

908the existing Congressional authorizat ion when the permit was

917submitted to the Department.

92112. By proposed Final Order dated November 1, 2006, the

931Department provided to Beach Group notice of its intent to deny

942the permit application.

94513. The proposed Final Order was received by Beach G roup

956on November 8, 2006. Beach Group's petition for hearing was

966timely filed with the Department.

97114. Since the Department proposes to deny Beach Group's

980CCCL permit application, its substantial interests are clearly

988at issue, and it has standing to maintain this proceeding.

99815. On December 11, 2006, the Department issued an

1007environmental resource permit for the Project .

101416. The Department denied Beach Group’s permit application

1022because the Project extends seaward of the 30 - year erosion

1033projection calculated by the Department and because the

1041Project’s i mpacts to the beach - dune system had not been

1053minimized . The permit was not denied on the basis of the

1065existence, or absence , of a line of continuous construction in

1075the vicinity of the Project .

1081B. T he 30 - year Erosion Projection

1089(1) Background

109117. Fort Pierce Inlet (hereafter “the inlet”) was

1099constructed by the Army Corps of Engineers in the 1920’s. The

1110channel of the inlet is protected by two jetties that extend

1121several hundred feet into the Atl antic Ocean.

112918. The jetties act as a barrier to the littoral transfer

1140of sand from the north to south that would otherwise occur along

1152the beach in the vicinity of the Property. The jetties cause

1163accretion on the beach to the n orth of the inlet and eros ion of

1178the beach to the south of the inlet.

118619. The inlet channel beyond the jetties also restricts

1195the littoral transfer of sand in the area. The deepening and

1206widening of the channel in 1995 likely contributed to the

1216increased erosion observed south of the inlet in recent years.

122620. The beach to the south of the inlet, including that

1237portion on the Property , is designated as a “ critically eroded

1248beach ” by the Department. The inlet is the primary cause of the

1261erosion.

126221. Congress first authorized bea ch nouri shment s outh of

1273the inlet in 1965 . That authorization expired in 1986.

128322. Congress “reauthorized” beach nourishment south of the

1291inlet in 1996. Th at authorization expire s in 2021 , but St.

1303Lucie County has requested that the authorization be ext ended

1313for “another 50 years.”

131723. The first “major” beach nourishment south of the inlet

1327occurred in 1971. Subsequent “major” nourishments occurred in

13351 980, 1999, 2003, 2004, and 2005 . Another “major” nourishment

1346is planned for 2007.

135024. There was a “m oderate” nourishment of the beach in

13611995 , which included the placement of geotextile groins on the

1371beach just to the north of the Property . “Small” nourishment s

1383occurred in 1973, 1978, 1987, 1989, 19 90, 1992, 1994, 1997 , and

13951998.

139625. Cumulatively, the nourishment s that occurred between

1404the “major” nourishments in 1 980 and 1999 involved approximately

1414419,000 cubic yards of sand , which is more than the volume

1426in volved in several of the “major” nourishments.

143426. B each nourishment south of the inlet has b een an

1446ongoing effort since it started in 1971 . The more persuasive

1457evidence establishes that the nourishment project that is

1465authorized through 2021 is a continuation of the project started

1475in 1971 rather than a separate and distinct project.

148427. V ario us er osion control efforts have been used south

1496of the inlet in conjunction with the beach nourishment efforts.

1506For example, g eotextile groins (which are essentially massive

1515sandbags) have been installed and removed on several occasions

1524since the mid - 1990 ’s in order to “temporarily stabilize the

1536shoreline until such measures could be taken to design, permit

1546and c onstruct a long - term solution”; concrete rubble and other

1558riprap has been placed on the beach over the years (without a

1570permit from the Department ) to protect upland structures from

1580erosion; and a " spur jetty " was constructed on the south jetty

1591in an effort to reduce erosion south of the inlet.

160128. These efforts have not slowed the pace of the erosion

1612or minimized the need for beach nourishment so uth of the inlet .

1625Indeed, the need for and frequency of “major” nou rishments south

1636of the inlet have increased in recent years.

164429. Beach erosion south of the inlet will continue to be a

1656serious problem so long as the inlet exists and the jetties

1667remain in place. There is no reason to expect that the inlet or

1680the jetties will be removed in the foreseeable future and, as a

1692result, beach nourishment south of the inlet will continue to be

1703necessary.

170430. The Department has recognized the need for continuin g

1714nourishment of the beach south of the inlet, as reflected in

1725both the S trategic Beach M anagement P lan for the St. Lucie

1738Bea ches and the Ft. Pierce Inlet Management Study Implementation

1748Plan. Those plans acknowledge the long - term need for continued

1759nouri shment of the beach at a rate of at least “130,000 cubic

1773yards on an average annual basis.” The plans do not, however,

1784guarantee that future beach nourishment in the area will occur

1794at that , or any , rate.

1799(2) Rule Methodology

180231. Florida Administrative Code Rule 6 2 B - 33.024 contains

1813the methodology for determining the 30 - year erosion projection,

1823which is the projected location of the SHWL 30 years after the

1835dat e of the permit application under review.

184332. Where, as here, the beach at issue is subject to an

1855ongoing beach nourishment project, the methodology requires

1862consideration of “pre - project” conditions -- i.e. , the

1871conditions that existed before the beach nourishment efforts

1879started -- because those conditions are used to project how the

1890beach will mi grate landward in the periods over the next 30

1902years when there may not be any be ach nourishment activity .

191433. The coastal engineering experts presented by the

1922parties -- M ichael Walther for Beach Group and Emmett Foster for

1934the Department -- used essenti ally the same methodology to

1944determine the location of the 30 - year erosion projection .

1955However, the variables that they used in each step of the

1966methodology differed.

1968(a) Step 1: Locate th e Pre - Project MHWL

197834. The first step in determining the 30 - year e rosion

1990projection is to locate the pre - project MHWL .

200035. If a pre - project erosion control line (ECL) 3 has been

2013established in the area, i t is to be used as the starting - point

2028for the determination of the 30 - year erosion projection.

2038Oth erwise a pre - proj ect survey of the MHW L is to be used as the

2056starting - point.

205936. Mr. Walther used a 1997 ECL as the starting point for

2071his analysis. Mr. Foster used a March 2002 survey of the MHWL

2083as the starting point for his analysis because he did not

2094consider the 199 7 ECL to be an appropriate pre - project ECL .

210837. The March 2002 survey of the MHWL is not itself an

2120appropriate starting point for the analysis. The survey is not

2130a “pre - project” survey, no matter how the project is defined;

2142the survey occurred more than 30 years after the nourishments

2152started in 1971, and three years after the first “major”

2162nourishment pursuant to the Congressional rea uthorization of the

2171project. Moreover, as discussed below, there is a n appropriate

2181pre - project ECL in the area.

218838. Ther e are two lines that might be considered to be a

2201pre - pr oject ECL in this case -- (1) the ECL established in 1997 ,

2216and (2) the South Beach High Tide Line (SBHTL) established in

22271968.

222839. The 1997 ECL was established based upon a survey of

2239the MHWL performe d on May 5, 1997. Th e survey occurred two

2252years after a “moderate” beach nour ishment and the placement of

2263the geotextile groins on the beach. There was also a “small”

2274nourishment in 1997, but the record does not reflect whether

2284that nourishment occurred before or after the survey.

229240. The SBHTL was established based upon a survey of the

2303MHWL between 1966 and 1968 , prior to the initial nourishment of

2314the beach south of the inlet. It is approximately 65 feet

2325landward of the 1997 ECL.

233041. The SBHTL is the functional equivalent of an ECL , and

2341it roughly corresponds to the “best fit line” for the March 2002

2353survey used by Mr. Foster as the starting point for his

2364determination of the 30 - year erosion projection in this case.

237542. The Department contends that t he 1997 ECL i s not based

2388upon a “pre - project” survey of the MHWL because the applicable

2400beach restoration project south of the inlet began in the 1970’s

2411and has been ongoing since that time. Beach Group contends that

2422the applicable project is the current one that is authorized

2432through 2021, and that the 1997 sur vey preceded the start of the

2445nourishment s authorized by that project.

245143. The Department has used the 1997 ECL as the starting -

2463point for determining the 30 - year erosi on projection in several

2475prior permits in the vicinity of the P roject , 4 and i n an April 9,

24911999, memorandum discussing the 30 - year erosion projection in

2501the vicinity of monuments R - 35 and R - 36, Mr. Foster stated that

2516“the ECL represents the pre - project [MHWL] .”

252544. Mr. Foster no longe r considers the 1997 ECL to be the

2538appropriate pre - project MHWL for purposes of determining the 30 -

2550year erosion projection south of the inlet. He testified that

2560had he been aware of “the complete background” of the 1997 ECL

2572and the extent of the nourishme nts in the 1980’s and 1990’s , he

2585would have brought the issue to the Department’s attention so

2595that the Department could consider whether the 1997 ECL or “an

2606earlier prenourishment line” was the appropriate pre - project

2615MHWL.

261645. Although it is a close que stion, t he more persuasive

2628evidence presented at the final hearing establishes that the

26371997 ECL is not an appropriate pre - project MHWL because the

2649applicable “project” includes the beach nourishment efforts

2656started in 1971 that have continued through the present , even

2666though those efforts were intermittent at times .

267446. Thus, the a ppropriate starting point for determining

2683the location of the 30 - year erosion projection is the SBHTL , not

2696the 1997 ECL used by Mr. Walther or the March 2002 MHWL survey

2709u sed by Mr. Foster .

2715(b) Step 2: Locate the Pre - Project SHWL

272447. The second step in determining the 30 - year erosion

2735projection is to determine the location of the pre - project SHWL.

274748. Mr. Walther located the pre - project SHWL 26.4 feet

2758landward of the 1997 E CL. That is the surveyed distance between

2770the MHWL and SHWL in June 2005.

277749. Mr. Foster located the pre - project SHWL at the most

2789landward location that the SHWL w as surveyed i n March 2002. Th e

2803line is between 50 and 75 feet 5 landward of the “best fine” line

2817used by Mr. Foster as the pre - project MHWL, and it is as much as

283325 feet landward of the surveyed location of the SHWL in some

2845areas.

284650. Mr. Foster used “an average [of] 50 feet” as the MHWL -

2859to - SHWL distance in his analysis of several prior permit s in the

2873vicinity of the Project . 6

287951. Mr. Foster te stified that the distance betwe en the

2890MHWL and SHWL in this area varies “from the 20s in the immediate

2903post - nourishment situation s . . . all the way up to 70 - some

2919feet” and that the “the averages gravi tate towards 40 feet.”

293052. Consistent with that testimony, the distance between

2938the surveyed locations of the MHWL and SHWL depicted on

2948Department Exhibit 6 is approximately 40 feet, on average.

295753. The MHWL - to - SHWL distance calculated by Mr. Walther is

2970not a reasonable projection of the pre - project distance because

2981it was based upon survey data taken immediately after a “major”

2992beach nourishment when the shoreline was unnaturally steep and ,

3001hence, not representative of “pre - project” conditions.

300954. The SHWL located by Mr. Foster is also not a

3020reasonable projection of the pre - project SHWL because it was

3031based upon a March 2002 survey (which is clearly not " pre -

3043project " ); because it used the most landward surveyed location

3053of the SHWL rather than a “best fit” line or an average of the

3067distances between the surveyed MHWL and SHWL ; and because it

3077runs across areas of well - established dune vegetation.

308655. In sum, t he MHWL - to - SHWL distance calculated by Mr.

3100Walther (26.4 feet) is too low, whereas the distance resulting

3110from Mr. Foster's siting of the SHWL based on the March 2002

3122survey (50 to 75 feet) is too high. Those distances are

3133essentially endpoints of the range observed in this area , as

3143described by Mr. Foster.

314756. A more reasonable estimate of the pre - project MHWL - to -

3161SHWL distance is approximately 40 feet . See Findings 51 and 52.

317357. Thus, th e pre - project SHWL is located 40 feet landward

3186of and parallel to the SB HTL . That line is not depicted on any

3201of the exhibits, but on Petitioner’s Exhibit 37 , it roughly

3211corresponds to a straight line between the points where the red -

3223dashed line intersects the Property’s north and south

3231boundaries.

3232(c) Step 3: Calculate the Erosion Rate

323958. The third step in determining the 30 - year erosion

3250projection is to calculate an erosion rate.

325759. The erosion rate used by Mr. Foster was - 7 feet per

3270year (ft/yr) . T hat rate was calculated based upon an average of

3283the shoreline change data for monument R - 35 for the period from

32961949 to 1967. The rate would have been h ig her had Mr. Foster

3310averaged the rate s for the nearby monuments. 7

331960. The erosion rate used by Mr. Walther was - 4.9 f t/yr .

3333That rate was calculated based upon an average of the shoreline

3344change data for monuments R - 34 to R - 39 over the period of 1930

3360to 19 68.

336361. An erosion rate of - 7 ft/ yr south of the inlet was

3377referenced in permit application s submitted by Mr. Walter’s

3386firm , Coastal Tech, for several shore protection structures

3394south of the inlet ; was used by Mr. Foster in his review of

3407several prior CC CL permit applications south of the inlet ; and

3418was included in reports on the inlet prepared by the Army Corps

3430of Engineers over the years .

343662. An erosion rate of - 3.3 ft/yr was used and accepted by

3449the Department in its review of another permit applicati on in

3460the general vicinity of the project. 8 That erosion rate was

3471based upon data from the period of 1972 to 1994, which is after

3484the beach nourishment sta r ted south of the inlet.

349463. It is not entirely clear why Mr. Foster chose to use a

3507data set starti ng in 1949, particularly since his report stated

3518that the “1928 - 30 survey already shows significant erosion

3528occurring south of the inlet.” His testimony did not adequately

3538explain the choice of that data set.

354564. The use of a longer data set is typically more

3556appropriate when calculating a historical rate. In this case,

3565however, the use of the shorter period of 1949 - 68 is reasonable

3578because the 1930 - 49 erosion r ate was considerably lower than the

35911949 - 68 rate, 9 which has the effect of skewing the erosion rate

3605calculated for the longer period of 1930 - 68.

361465. The higher erosion rate calculated by Mr. Foster also

3624better takes into account the i ncreased frequency of the

3634nourishments in recent years as well as the continued need for

3645shore stabilization in the area.

365066. In sum, the higher erosion rate of - 7 f t/yr calculated

3663by Mr. Foster using the 1949 - 68 data set better reflects the

3676historical post - inlet, pre - nourishment erosion rate than does

3687the lower erosion rate calculated by Mr. Walther.

3695(d) Step 4: De termine the Remaining Project Life

370467. The f ourth step in determining the 30 - year erosion

3716projection is to determine the “remaining project life” of the

3726“ exist ing ” beach nourishment project .

373468. It was stipulated that there are 14 ye ars remaining

3745until t he currently authorized federal beach rest oration project

3755expires .

375769. It is reasonable to expect that beach nourishment

3766south of the inlet will continue well beyond th e expiration of

3778the current federal project , but there were no other funded and

3789permitt ed projects in place a t the time Beach Group’s permit

3801application was filed.

380470. Potential future beach nourishment projects are not

3812considered “existing” under the rule methodology in Florida

3820Administrative Code Rule 62B - 33.024 unless they are funded and

3831permitted at the time the application at issue is filed.

384171. Mr. Walther used the 14 - year remaining life of the

3853existing federal project in his calculation of the 30 - year

3864erosion projection, as did Mr. Foster.

387072. The “remaining project life” applicable to this case

3879is 14 years, notwithstanding the likelihood of continued beach

3888nourishment in the area beyond the expiration of the existing

3898project.

3899(e) Step 5: Calculate the 30 - year Erosion Projection

390973. The final step in determining the location of th e 30 -

3922year erosion projection is a calculation using the variables

3931determined in the previous steps.

393674. The calculation is as follows: first, the re maining

3946project life determined in step four is subtracted from 30;

3956then, that result is multiplied by the erosion rate determined

3966in step three to get a distance; and, finally, the SHWL is moved

3979t hat distance landward of its pre - project location determined in

3991step two.

399375. Subtracting the remaining project of 14 years from 30

4003equals 16 years.

400676. Multiplyin g 16 years by the erosion rate of - 7 f t/yr

4020equals 112 feet, which means that the 30 - year erosion line is

4033located 112 feet landward of the pre - project SHWL (or 152 feet

4046landward of the SBHTL) .

405177. That line is not depicted on any of the exhibits, but

4063it ro ughly corresponds to a straight line than runs across the

4075Property parallel to the SBHTL just landward of the “conc. pad”

4086and “existing conc. Pile caps (typ)” shown on Petitioner’s

4095Exhibit 37. The line is 25 to 30 feet seaward of Mr. Foster’s

410830 - year eros ion projection depicted on that exhibit.

4118(3) Ultimate Finding Regarding the Location of

4125the Proposed Structures in Relation to

4131the 30 - year Erosion Projection

413778. The Project includes major structures seaward of th e

414730 - year erosion projection, as deter mined above.

4156C. Impacts of the Pr oject on the Beach - Dune System

416879. The Project includes 17 luxury town home units in t wo

4180four - story buildings, a pool and spa, landscaping, and a n

4192elevated dune walkover. The units will range from 2,700 to

42034,400 square f eet of living space and are projected to be

4216offered for sale in the $1.5 to $2.5 million range .

422780. B e ach Group’s principal , Harold Seltzer, testified

4236that the Project is sited as far landward as possible to allow

4248for the development of all 17 units while still complying with

4259the local setback and height restrictions; that the Project ’s

4269financial viability depends upon it being developed as proposed;

4278and that the Project cannot be redesigned and remain financially

4288viable.

428981. The CCCL permit application i ncluded a letter from the

4300City of Ft. Pierce confirming that the Project is consistent

4310with the applicable local development codes . Mr. Seltzer

4319testified that the Project’s local development approvals expired

4327in September 2006 because the CCCL permit had not been issued,

4338and that Beach Group is having to go back through the local

4350permitting process .

435382. The seaward extent of the Project is the 1978 CCCL,

4364which is approximately 250 fee t seaward of the current CCCL.

437583. The buildings on the adjacent proper ties are also

4385located on the 1978 CCCL. The Project does not extend further

4396seawar d than the nearby development, including the structures

4405authorized by the Department in File Nos. SL - 162 and SL - 173. 10

442084 . The seaward boundary of the Property is the SBHTL .

4432That line is approximately 295 feet landward of the MHWL

4442established in June 2005, and as noted above, it is

4452approximately 65 feet landward of the ECL established in 1997.

446285 . The adjacent propert ies are developed with multi - s tory

4475residential buildings. There is a densely vegetated dune

4483feature in front of the building to the south of the Property .

4496There is some vegetation, but no discernable dune in front of

4507the building to the north of the Property .

451686 . The Property as a whole is sparsely vegetated , but

4527there are areas of “prolific vegetation” on the P roperty .

453887 . The seaward extent of the vegetation on the Property

4549roughly corresponds t o the location of the 1978 CCCL. There are

4561several mature sea grape cluste rs in the vicinity of that line .

457488 . The beach in front of the Property is devoid of

4586vegetation. It has a steep slope immediately landward of the

4596water line; a wide (approximately 270 feet) expanse of

4605relatively flat beach; and a gently sloping dune feature that

4615starts just landward of the P roperty ’s seaward boundary, crests

4626approximately 30 feet fa rther landward, and then gradually

4635slopes downward across the Property all of the way to State Road

4647A1A .

464989 . The dune feature on the Property is the frontal dun e.

4662It is the first mound s a nd locat ed landward of the beach that

4677has sufficient vegetation, height, continuity, and configura tion

4685to offer protective value.

468990 . The crest of the frontal dune is seaward of the

4701vegetation line on the Property , and ranges in height from .7

4712to .2 feet NAV D. 11 The seaward toe of the dune is shown on

4727the topographic survey for the Property at elevations ranging

4736fr om .27 to .85 feet NAVD. Similar elevations occur on the

4748landward side of the dune crest, just landward of the 1978 CCCL .

476191 . The vegetation on the Property extends landward of the

47721978 CCCL and landward of the line shown on the topographic

4783survey of the Property as the “approximate location of sparse

4793grass and ground cover.” The landward extent of the vegetation

4803does not in and of itself defi ne the landward extent of the

4816dune; changes in the slope of the ground must also be

4827considered.

482892 . The more persuasive evidence establishes that the

4837landward toe of the frontal dune is landward of the 1978 CCCL,

4849but not as f ar landward as suggested by D epartment witness Tony

4862McNeal . 12 The landward toe of the dune on the P roperty is best

4877defined by the elevations landward of the dune crest similar to

4888the elevations shown for the seaward toe of the dune.

489893 . The Project extends into the frontal dune on th e

4910P roperty , and it will requires minor excavation of the frontal

4921dune, primarily in the area of the proposed pool.

493094 . All aspects of the project, except for the proposed

4941dune walkover, will be landward of the crest of the frontal dune

4953and t he mature sea grape clusters located on th e dune.

496595 . There will be no net excavation on the Property as a

4978result of the Project . The sand excavated for the pool will be

4991placed on - site , and additional beach - compatible sand will be

5003used as fill for the site. Overall, the Project will result in

5015the net placement of approximately 66 cubic yards of sand on the

5027Property .

502996 . The proposed structures will be elevated on piles,

5039which will allow the beach - dune system to fluctuate under the

5051structure s during storm events. The finished floor elevation of

5061the proposed structures is approximately feet NAVD, which is

5070slightly higher than the elevations associated with the toes of

5080the frontal dune.

508397 . The Project will not destabilize the frontal dune,

5093even though it will encr oach into the dune.

510298 . The impacts of the Project on the beach - dune system

5115will be mitigated by the placement of additional sand into the

5126beach - dune system, as described above.

513399 . The Project’s impacts will be further mitigated by the

5144enhancements to the frontal dune described in the permit

5153application .

5155100 . Mr. Walt her testified that the frontal dune on the

5167Property could “very easily” be enhanced to be of comparable

5177height and magnitude of the dun es on the adjacent properties .

5189101 . T he permit a p plication proposes enhancements to the

5201frontal dune as part of the Site Landscaping Plan for the

5212Project. The proposed enhancements include increasing the crest

5220of the dune to a height of feet NAVD , and extensive planting

5232of the dune with sea grapes, beach morning glories, and sea

5243oats. The plantings would extend from the 1978 CCCL to the

5254seaward toe of the existing frontal dune.

5261102 . The dune enhancements proposed in the permit

5270application should be included as a specific condition of the

5280CCCL permi t for the Project, if it is approved.

5290CONCLUSIONS OF LAW

5293103 . DOAH has jurisdiction over the parties to and subject

5304matter of this proceeding pursuant to Sections 120.569 and

5313120.57(1), Florida Statutes .

5317104 . Beach Group has the burden to prove by a

5328pre ponderance of the evidence that its permit application should

5338be approved. See Dept. of Transportation v. J.W.C. Co., Inc. ,

5348396 So. 2d 778, 788 - 89 (Fla. 1st DCA 1981).

5359105 . The Department’s interpretation of the statutes and

5368rules governing the issuance of CCCL permits is entitled to

5378deference . See , e.g. , Dept. of Environmental Reg. v. Goldring ,

5388477 So. 2d 532, 534 (Fla. 1985) (“Courts should accord great

5399deference to administrative interpretations of statutes which

5406the administrative agency is required to enforce.”) .

5414106 . Generally, a ll construction seaward of the CCCL

5424requires a permit from the Department , unless an exemption

5433applies . See § 161.053 , Fla . Stat. ; Atlantis at Perdido Ass’n

5445v. Warner , 932 So. 2d 1206 (Fla. 1st DCA 2006). No exemption

5457ap pl ies in this case.

5463107 . T he Department may not issue a CCCL permit for major

5476structures seaward of the 30 - year erosion projection , except in

5487limited circumstances not applicable in this case . See

5496§ 163.053(6)(b), Fla. Stat .

5501108 . Florida Administrative Code Rule 62B - 33.024

5510establishes the procedure for determining the location of the

55193 0 - year erosion projection . The rule provides in pertinent

5531part :

5533(1) A 30 - year erosion projection is the

5542projection of long - term shoreline recession

5549occurring over a peri od of 30 years based on

5559shoreline change information obtained from

5564historical measurements. A 30 - year erosion

5571projection of the seasonal high water line

5578(SHWL) shall be made by the Department on a

5587site specific basis upon receipt of an

5594application with th e required topographic

5600survey . . . for any activity affected by

5609the requirements of Section 161.053(6), F.S.

5615An applicant may submit a proposed 30 - year

5624erosion projection for a property, certified

5630by a professional engineer licensed in the

5637state of Flori da, to the Department for

5645consideration.

5646(2) A 30 - year erosion projection shall be

5655determined using one or more of the

5662following procedures:

5664(a) An average annual shoreline change

5670rate in the location of the mean high water

5679line (MHWL) at a Departm ent reference survey

5687monument shall be determined and multiplied

5693by 30 years. The resulting distance shall

5700be added landward of the SHWL located on the

5709application survey. The rate shall be

5715determined as follows:

57181. The shoreline change rate shall be

5725derived from historical shoreline data

5730obtained from coastal topographic surveys

5735and maps, controlled aerial photography, and

5741similar sources approved by the Department.

5747Data from periods of time that clearly do

5755not represent current prevailing coastal

5760p rocesses acting on or likely to act on the

5770site shall not be used.

57752. The shoreline change rate shall

5781include the zone spanned by three adjacent

5788Department reference monuments on each side

5794of the site. A lesser or greater number of

5803reference monuments can be used as necessary

5810to obtain a rate representative of the site,

5818and a rationale for such use shall be

5826provided.

58273. In areas that the Department

5833determines to be either stable or accreting,

5840a minus one - foot per year shoreline change

5849rate shall be applied as a conservative

5856estimate.

5857* * *

5860(d) Beach nourishment or restoration

5865projects shall be considered as follows:

58711. Future beach nourishment or

5876restoration projects shall be considered as

5882existing if all funding arrangements have

5888been made and all permits have been issued

5896at the time the application is submitted.

59032. Existing beach nourishment or

5908restoration projects shall be considered to

5914be either a one - time beach construction

5922event or a long - term series of related sand

5932placement e vents along a given length of

5940shoreline. The Department shall make a

5946determination of remaining project life

5951based on the project history, the likelihood

5958of continuing nourishments, the funding

5963arrangements, and consistency with the

5968Strategic Beach Manage ment Plan adopted by

5975the Department for managing the state’s

5981critically eroded shoreline and the related

5987coastal system.

59893. The MHWL to SHWL distance landward of

5997the erosion control line (ECL) shall be

6004determined. If the ECL is not based on a

6013pre - proje ct survey MHWL, then a pre - project

6024survey MHWL shall be used instead of the

6032ECL. The pre - project SHWL shall be located

6041by adding the MHWL to the SHWL distance

6049landward of the pre - project MHWL (usually

6057the ECL). The remaining project life, which

6064is the nu mber of years the restored beach

6073MHWL is expected to be seaward of the ECL,

6082shall be subtracted from the 30 years as a

6091credit for the nourishment project. The

6097non - credited remaining years times the pre -

6106project shoreline change rate for the site

6113yields the 30 - year projection distance

6120landward of the pre - project SHWL.

61274. If the Department is unable to

6134scientifically determine a pre - project

6140erosion rate due to a lack of pre - project

6150data, the Department shall set the 30 - year

6159erosion projection along an exi sting,

6165reasonably continuous, and uniform line of

6171construction that has been shown to be not

6179unduly affected by erosion.

6183109 . Beach Group argues in its PRO (at paragraph 58.d)

6194that , for purposes of applying this rule methodology, the

6203“remaining project l ife” applicable to this case

6211is likely to exceed 30 years, given the

6219history of beach renourishment in this area

6226since 1971, the likelihood of continuing

6232renourishments, including a request by St.

6238Lucie County to extend the life of the

6246nourishment project (and the unlikelihood

6251that state, federal and local governments

6257will allow this and other similarly situated

6264structures to simply fall into the Atlantic

6271Ocean), funding arrangements, and

6275nourishment project’s undisputed consistency

6279with the Strategic Beach Management Plan and

6286the Fort Pierce Inlet Management Plan.

6292110 . There is some appeal to this argument , particularly

6302since it is reasonable to expect that beach nourishment south of

6313the inlet will continue for the foreseeable future. However,

6322t he potent ial for continued nourishments beyond the term of the

6334“ existing” project is not appropriate for consideration under

6343Florida Administrative Code Rule 62B - 33.024. See also

6352§ 161.053(6)(d), Fla. Stat.

6356111 . The “existing” project includes future nourishment

6364project s only if “all funding arrangements have been made and

6375all permits have been issued at the time the application is

6386submitted.” F la. Admin. Code R. 62B - 33.024(2)(d)1. Potential

6396(or even likely) future nourishment projects other than one

6405authorized by Congress through 202 1 do not meet that standard. 13

6417112 . The factors listed in Florida Administrative Code

6426Rule 62B - 33.024(2)(d)2 . relating to the Department’s

6435determination of remaining project life necessarily relate to

6443“ existing ” project s, as defined in Subparagraph (2)(d)1 . of the

6456rule. Indeed, it would be illogical -- and , arguably, contrary

6466to Section 161.053(6)(d), Florida Statutes -- to construe

6474Subparagraph (2)(d)2 . of the rule to allow for consideration of

6485projects that would not be considered to be “existing” under

6495Subparagraph (2)(d)1 . of the rule.

6501113 . The more persuasive evidence establishes that the

6510Project extends seaward of the 30 - year erosion projection . See

6522Findings of Fact, Part B. Therefore, the Department may not

6532issue a CCCL perm it for the Project . See § 161.053(6)(b), Fla.

6545Stat.

6546114 . In light of th is co nc lusion, it is not necessary to

6561determine whether the Project otherwise satisfies the applicable

6569CCCL permit ting requirements . H owever, th e issue will be

6581addressed below in an abundance of caution in the event that t he

6594Department or an appellate court rejects the conclusion that the

6604Project is located seaward of the 30 - year erosion projection .

6616115 . The Department is authorized to issue permits for

6626construction seaward of the CC CL if the permit is “clearly

6637justified” based upon the consideration of facts and

6645circumstances, including the potential impacts of the proposed

6653construction on the beach - dune system . See § 161.053(5)(a)3.

6664Fla. Stat.

6666116 . The general criteria governing a pproval of a CCCL

6677permit are set forth in Florida Admin istrative Code 62B - 33.005.

6689The rule requires the applicant to “ provide the Department with

6700sufficient information pertaining to the proposed project to

6708show that any impacts associated with the constr uction have been

6719minimized and that the construction will not result in a

6729significant adverse impact.” Fla. Admin. Code R. 62B - 33.005(2).

6739117 . It is undisputed that the Project will not result in

6751a “ significant adverse impact , ” which is defined as an adv erse

6764impact of such magnitude that it may alter the coastal system by

6776measurably affecting the existing shoreline change rate;

6783significantly interfering with its ability to recover from a

6792coastal storm; or disturbing topography or vegetation such that

6801the dune system becomes unstable or suffers catastrophic failure

6810or the protective value of the dune system is significantly

6820lowered. See Fla. Admin. Code R. 62B - 33.002(31)(b).

6829118 . At issue is whether the Project will cause “adverse

6840impacts” to the beach - du ne system and, if so, whet h er those

6855impacts have been minimized. Adverse impacts are impacts to the

6865coastal system that may cause a measurable interference with he

6875natural func t ioning of the system. See F la. Admin. Code R. 62B -

689033.002(31)(a ).

6892119 . Florid a Administrative Code Rule 62B - 33.005(3)(b)

6902requires “siting and design criteria that minimize adverse and

6911other impacts and . . . mitigation of adverse impacts . ” The

6924Deparment contends that the Project fails to meet the

6933requirements of th is rule because the Project w ill be located on

6946the frontal dune, no t landward of the dune.

6955120 . For the same reason, the Department contends that the

6966Project fails to meet the requirements of Florida Administrative

6975Code Rule 62B - 33.005(8), which requires major structures to be

6986“located a sufficient distance landward of the beach and frontal

6996dune to permit natural shoreline fluctuations, to preserve and

7005protect beach and dune system stability, and to allow natural

7015recovery to occur following storm - induced erosion.”

7023121 . I t is undisputed that the Project satisfies the

7034permitting criteria in Florida Admi nistrative Code Rule 62B -

704433.005, except for those in paragraph (3)(b) and subsection (8).

7054122 . The frontal dune is “the first natural or manmade

7065mound or bluff of sand which is located landward of the beach

7077and which has sufficient vegetation, height, continuity, and

7085configuration to offer protective value.” § 161.053(6)(a)1.,

7092Fla. Stat. It is undisputed that the Project encroaches i nto

7103frontal dune, but that it is behind t he crest of the dune.

7116123 . The only express statutory or rule prohibition

7125against construction on a frontal dune is in the limited

7135circumstance where construction of a single - family dwelling is

7145permitted seaward of the 30 - year erosion projection. See

7155§ 1 61.053(6)(c)3. - 4., Fla. Stat. (requiring the dwelling to be

7167located “landward of the frontal dune structure” and “as far

7177landward . . . as practicable without being located seaward of

7188or on the frontal dune”).

7193124 . There is no express statutory prohibiti on against

7203construction on a frontal dune landward of the 30 - year erosion

7215projection, so long as the proposed construction does not

7224destabilize the frontal dune or otherwise adversely impact the

7233beach - dune system. See , e.g. , Young v. Dept. of Environmenta l

7245Protection , 2005 Fla. ENV LEXIS 155 , at ¶¶ 83, 111 (DOAH Aug.

725715, 2005 ), adopted in toto , 2005 Fla. ENV LEXIS 154 ( DEP Sep.

727126, 2005), aff’d per curiam , 937 So. 2d 133 (Fl a. 2nd DCA 2006)

7285(table) .

7287125 . Florida Administrative Code Rule 62B - 33.005(8) does

7297not expressly prohibit construction that encroaches into a

7305frontal dune; it only requires that major structures be located

7315a “sufficient distance landward of the . . . frontal dune to

7327permit natur al shoreline fluctations, to preserve and protect

7336beach and dune system stability, and to allow natural recovery

7346to occur following storm - induced erosion . ” Where, as here, the

7359more persuasive evidence establishes that the location of the

7368proposed structures on the landward side of the crest of the

7379frontal dune wi ll not destabilize the dune or otherwise

7389adversely affect the beach - dune system, the purpose of the rule

7401is satisfied . See Young , supra .

7408126 . The stability of the beach - dune system in the

7420vicinity of the Property is dependent upon the continuing

7429renour ish ment efforts ; the contribution of the frontal dune on

7440the P roperty to the stability of the beach - dune system or the

7454protection of upland properties is relatively minor in

7462comparison. As a result, t he slight encroachment of the Project

7473into the landward side of the frontal dune will not have a

7485material impact on t he na tural functioning of the beach - dune

7498system or the ability of the system to recover following storm -

7510induced erosion.

7512127 . The impacts to the frontal dune will be limited to

7524minor excavation s and the removal of existing dune vegetation in

7535areas behind the crest of the dune . Those impacts will not

7547destabilize the frontal dune or materially affect the ability of

7557th e dune or the beach - dune system to recover from storm events ,

7571and the impacts ha ve been adequately mitigated through the

7581plac e ment of additional sand in the beach - dune system and the

7595proposed enhancements to the frontal dune.

7601128 . In sum, if it is determined contrary to the

7612conclusion above that the Project is landward of the 30 - yea r

7625erosion projection, the permit should be approved because the

7634more persuasive evidence establishes that the Project satisfies

7642the applicable criteria in Florida Administrative Code Rule 62B -

765233.005.

7653RECOMMENDATION

7654Based upon the foregoing findings of fac t and conclusions

7664of law, it is

7668RECOMMENDED that the Department issue a final order denying

7677Beach Group’s application for a CCCL permit.

7684DONE AND ENTERED this 19th day of April, 200 7 , in

7695Tallahassee, Leon County, Florida.

7699S

7700T. KENT WETHERELL, II

7704Administrative Law Judge

7707Division of Administrative Hearings

7711The DeSoto Building

77141230 Apalachee Parkway

7717Tallahassee, Florida 32399 - 3060

7722(850) 488 - 9675 SUNCOM 278 - 9675

7730Fax Filing (850) 921 - 6847

7736www.doah.state.fl.us

7737Filed with the Clerk of the

7743Division of Administrative Hearings

7747this 19th day of April , 2007 .

7754ENDNOTES

77551 / All statutory references in this Recommended Order are to the

77672006 version of the Florida Statutes.

77732 / Finding s 1 throug h 14 are based upon the stipulations in the

7788Joint Pre - hearing Stipulation . Finding s 15 and 16 are based

7801upon stipulations at the final hearing. See Tr. 102 - 03, 191 - 97.

78153 / The ECL represents the boundary between the sovereignty lands

7826of the state and th e adjacent upland properties. See §

7837161.151(3), Fla. Stat. An ECL is to be established prior to a

7849beach restoration project in order to define the ownership of

7859the beach created by the project. See § 161.141, Fla. Stat.

7870The new beach created seaward of the ECL is state property ; any

7882new beach created landward of the ECL is private property

7892subject to a public easement across the property. See §§

7902161.141, 161.191, Fla. Stat. But cf. Save Our Beaches, Inc. v.

7913Dept. of Environmental Protection , 31 Fla. L . Weekly D1173 (Fla.

79241st DCA Apr. 28, 2006) (holding that the establishment of an ECL

7936as part of a beach renourishment project results in an

7946unconstitutional taking of the upland property owners’ riparian

7954rights), question certified , 31 Fla. L. Weekly D181 1 (Fla. 1st

7965DCA July 3, 2006), rev. granted , 937 So. 2d 1099 (Fla. 2006).

79774 / See , e.g. , Pet. Ex. 24 (File Nos. SL - 162 and SL - 173); Pet.

7994Ex. 25 (File No. SL - 200).

80015 These distances are based upon the scale shown on Department

8012Exhibit 6, which is more acc urate that Mr. Foster’s testimony

8023that the distances between MHWL and SHWL, as surveyed in March

80342002, was “ about 40 to 60 feet.\. 290 (emphasis supplied) .

80466 / See Pet. Ex. 24 (memo dated April 9, 1999, attached to the

8060analyses for File Nos. SL - 162 an d SL - 173). See also Tr. 68

8076(referencing Mr. Foster’s use of “a distance of some 42 feet

8087based on historical averages” in his review of File No. SL - 222).

81007 / See , e.g. , Pet. Ex. 16 (Table 1), which shows an average

8113erosion rate of - 7.5 ft/yr for monuments R - 34 to R - 39 over the

8130period of 1949 - 68. Accord Tr. 291 - 92.

81408 / See Pet. Ex. 25 (File No. SL - 200).

81519 / See Pet. Ex. 16 (Table 1), which reflects that the erosion

8164rates for monuments R - 34 and R - 35 were - 0.1 and - 0.5 ft/yr,

8181respectively, for the period o f 1930 - 49, as compared to - 10.3

8195and - 6.7 ft/yr, respectively, for the period of 1949 - 68.

820710 / See , e.g. , Pet. Ex. 24; Dept. Ex. 6. Beach Group points out

8221that the structures authorized in File Nos. SL - 162 and SL - 173

8235were found to be landward of the 30 - ye ar erosion projection

8248calculated by the Department. However, the “remaining project

8256life” was longer when those permit applications were filed -- in

82671999 and 2000, respectively -- and, as a result, the historical

8278erosion rate was applied to a smaller numb er of years in

8290calculating the landward migration of the SHWL in those cases.

8300Indeed, as Mr. Foster pointed out in his review of those

8311applications, the 30 - year erosion projection is “time sensitive”

8321and “must be adjusted in the future for diminishing cre dit for

8333the renourishment project.” Pet. Ex. 24 (memorandum dated April

83429, 1999, attached to analyses for File Nos. SL - 162 and SL - 173).

835711 / NAVD is the North American Vertical Datum of 1988. See Fla.

8370Admin. Code R. 61B - 33.002(37). Elevations shown on t he

8381topographic survey for the Property are reflected in relation to

8391the NAVD. See Pet. Ex. 19 ( n ote 11).

840112 / Mr. McNeal opined that the landward toe of the frontal dune

8414was located 20 feet or more landward of the 1978 CCCL. See Tr.

8427203, 207 - 10, 229 - 33. See also Dept. Ex. 24N (highlighted

8440line s ). The opinion that the encroachment was more than 20 feet

8453was in the form of a proffer because it was a new opinion not

8467disclosed by the Department prior to the final hearing. See Tr.

8478205 - 06. The exclusion of M r. McNeal’s opinion regarding the

8490landward extent of the frontal dune (and the resulting larger

8500encroachment of the project into the dune) is immaterial to Mr.

8511McNeal’s ultimate opinion that the project fails to meet the

8521applicable regulatory requirements because he understands the

8528Department’s rules to prohibit development that encroaches into

8536the frontal dune at all . See Tr. 223.

854513 / The likelihood of continued beach nourishment south of the

8556inlet for the foreseeable future might be appropriate for

8565cons ideration in the context of a request for a variance or

8577waiver under Section 120.542, Florida Statutes. See Pet. Ex. 21

8587(identifying a variance as a possible means for the Project to

8598be approved as it is currently proposed). A variance or waiver

8609must be pursued through a separate proceeding.

8616COPIES FURNISHED :

8619Lea Crandall, Agency Clerk

8623Department of Environmental Protection

8627The Douglas Building, Mail Station 35

86333900 Commonwealth Boulevard

8636Tallahassee, Florida 32399 - 3000

8641Tom Beason, General Counsel

8645Department of Environmental Protection

8649The Douglas Building, Mail Station 35

86553900 Commonwealth Boulevard

8658Tallahassee, Florida 32399 - 3000

8663Michael W. Sole, Secretary

8667Department of Environmental Protection

8671The Douglas Building, Mail Station 35

86773900 Commonwe alth Boulevard

8681Tallahassee, Florida 32399 - 3000

8686William L. Hyde, Esquire

8690Fowler White Boggs Banker, P.A.

8695Post Office box 11240

8699Tallahassee, Florida 32302 - 3240

8704Kelly L. Russell, Esquire

8708Department of Environmental Protection

8712The Douglas Building, Mail S tation 35

87193900 Commonwealth Boulevard

8722Tallahassee, Florida 32399 - 3000

8727NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

8733All parties have the right to submit written exceptions within

874315 days from the date of this Recommended Order. Any exceptions

8754to this Recommend ed Order should be filed with the agency that

8766will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 07/12/2007
Proceedings: Final Order filed.
PDF:
Date: 07/12/2007
Proceedings: Department of Environmental Protection`s Response to Petitioners` Exceptions to Recommended Order filed.
PDF:
Date: 07/12/2007
Proceedings: Response of Beach Group Investments, LLC to Exceptions filed by Department of Environmental Protection filed.
PDF:
Date: 07/12/2007
Proceedings: Department of Environmental Protection`s Exceptions to the Recommended Order filed.
PDF:
Date: 07/12/2007
Proceedings: Exceptions to Recommended Order by Petitioner Beach Group Investments, LLC filed.
PDF:
Date: 07/11/2007
Proceedings: Agency Final Order
PDF:
Date: 04/19/2007
Proceedings: Recommended Order
PDF:
Date: 04/19/2007
Proceedings: Recommended Order (hearing held February 15-16, 2007). CASE CLOSED.
PDF:
Date: 04/19/2007
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 03/30/2007
Proceedings: Department of Environmental Protection`s PRO filed.
PDF:
Date: 03/30/2007
Proceedings: Proposed Recommended Order of Petitioner Beach Group Investments, LLC filed.
PDF:
Date: 03/21/2007
Proceedings: Order Granting Extension of Time (proposed recommended orders to be filed by March 30, 2007).
PDF:
Date: 03/19/2007
Proceedings: Agreed Motion for Extension of Time to File Porposed Recommended Orders filed.
Date: 03/01/2007
Proceedings: Transcript (Volumes 1, 2, 3) filed.
Date: 02/15/2007
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 02/14/2007
Proceedings: Letter to DOAH from W. Hyde enclosing exhibits to Joint Pretrial Stipulation filed on February 12, 2007 filed.
PDF:
Date: 02/12/2007
Proceedings: Joint Prehearing Stipulation filed.
PDF:
Date: 02/12/2007
Proceedings: Order Granting Extension of Time (the pre-hearing stipulation to be filed by February 12, 2007).
PDF:
Date: 02/12/2007
Proceedings: Notice of Transfer.
PDF:
Date: 02/09/2007
Proceedings: Motion for Extension of Time to File Pre-Hearing Stipulation filed.
PDF:
Date: 02/06/2007
Proceedings: Order (Stipulated Motion for Telephonic Deposition is granted).
PDF:
Date: 02/01/2007
Proceedings: Notice of Taking Telephonic Deposition (H. Seltzer) filed.
PDF:
Date: 01/31/2007
Proceedings: Stipulated Motion for Telephonic Deposition filed.
PDF:
Date: 01/30/2007
Proceedings: Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 01/30/2007
Proceedings: Amended Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 01/29/2007
Proceedings: Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 01/18/2007
Proceedings: Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 01/10/2007
Proceedings: Notice of Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Beach Group Investments, LLC filed.
PDF:
Date: 01/09/2007
Proceedings: Notice and Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Beach Group Investments, LLC filed.
PDF:
Date: 01/03/2007
Proceedings: Amended Notice of Hearing (hearing set for February 15 and 16, 2007; 9:00 a.m.; Tallahassee, FL; amended as to Dates and Location of Hearing).
PDF:
Date: 12/28/2006
Proceedings: Motion to Switch Final Hearing Dates filed.
PDF:
Date: 12/19/2006
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 12/19/2006
Proceedings: Notice of Hearing (hearing set for April 4 and 5, 2007; 10:30 a.m.; Fort Pierce, FL).
PDF:
Date: 11/30/2006
Proceedings: Letter to Judge Canter from W. Hyde regarding failure to renumber the ultimate facts alleged in paragraph 26.
PDF:
Date: 11/29/2006
Proceedings: First Amended Petition for Formal Administrative Hearing filed.
PDF:
Date: 11/29/2006
Proceedings: Department of Environmental Protection`s Amended Response to Initial Order filed.
PDF:
Date: 11/28/2006
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
PDF:
Date: 11/28/2006
Proceedings: Notice of Appearance and Substitution of Counsel for the Florida Department of Environmental Protection (filed by K. Russell).
PDF:
Date: 11/21/2006
Proceedings: Denial of Application filed.
PDF:
Date: 11/21/2006
Proceedings: Petition for Formal Administrative Hearing filed.
PDF:
Date: 11/21/2006
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.
PDF:
Date: 11/21/2006
Proceedings: Initial Order.

Case Information

Judge:
T. KENT WETHERELL, II
Date Filed:
11/21/2006
Date Assignment:
02/09/2007
Last Docket Entry:
07/12/2007
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
 

Counsels

Related Florida Statute(s) (6):