06-004756
Beach Group Investments, Llc vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Thursday, April 19, 2007.
Recommended Order on Thursday, April 19, 2007.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8BEACH GROUP INVESTMENTS, LLC, )
13)
14Petitioner, )
16)
17vs. ) Case No. 06 - 4756
24)
25DEPARTMENT OF ENVIRONMENTAL )
29PROTECTION, )
31)
32Respondent. )
34)
35RECOMMENDED ORDER
37A duly - noticed final hearing was held in this case by
49Administrative Law Judge T. Kent Wetherell, II, on February 15 -
6016 , 200 7 , in Tallahassee , Florida.
66APPEARANCES
67For Petitioner: William L. Hyde, Esquire
73Fowler White Boggs Banker, P.A.
78Post Office B ox 11240
83Tallahassee, Florida 32302 - 3240
88For Respondent: Kelly L. Russell, Esquire
94Department of Environmental Protection
98The Douglas Building, Mail Station 35
1043900 Commonwealth Boulevard
107Tallahassee, Florida 32399 - 3000
112STATEMENT OF THE ISSUE
116The issue is whether the Department of Environmental
124Protection should approve Petitioners application for a coastal
132construction control line permit .
137PRELIMINARY STATEMENT
139On November 1, 2006, the Department of Environmental
147Protection (Depar tment) issued a proposed final order denying
156Petitioners application for a coastal construction control line
164(CCCL) permit. Petitioner timely requested an administrative
171hearing on the denial of its perm it application, and on
182November 21, 2006, the Depar tment referred the matter to the
193Division of Administrative Hearings (D OAH) for the a ssignment of
204an A dministrative L aw J udge to conduct the hearing requested by
217Petitioner.
218The final hearing was initially scheduled for April 4 - 5 ,
229200 7, in Ft. Pierce, but it was rescheduled for February 15 - 16,
2432007, in Tallahassee at the parties request. The parties filed
253a Joint Pre - hearing Stipulation on February 12, 2007.
263At the final hearing, Petitioner presented the testimony of
272Michael Walther and Harold Seltzer and the Department presented
281the testimony of Tony McNeal, Michael Barnett, and Emmett
290Foster. The following exhibits were received into evidence:
298Petitioners Exhibits (Pet. Ex.) 1, 2, 9 through 11, 15 through
30917, 19 through 27, 29 through 35, 36A through 36C, and 37
321through 39 ; and Departments Exhibits (Dept. Ex.) 5 through 13,
33116 through 19, 21 through 23, 24A through 24N, and 25 through
34327 . Official recognition was taken of Section 161.053, Florida
353Statues (2006), 1 and Florida Administrative Code Rule Chapter
36262B - 33.
365The three - volume Transcript of the final hearing wa s filed
377on March 1 , 2007 . The parties requested 21 da ys from that date
391to file proposed recommended orders (PROs) , but t he deadline was
402subsequently extended to March 30, 2007, upon Petiti oners
411unopposed motion . The PROs were timely filed and have been
422given due consideration.
425FINDINGS OF FACT
428A. Stipulated Facts 2
4321. Petitioner, Beach Group Investments, LLC (Beach Group),
440is a limited liability corporation under Florida law. Its
449addre ss is 14001 63rd Way North, Clearwater , Florida 33760.
4592. On December 19, 2005, Coastal Technology Corporation
467(Coastal Tech) on behalf of Beach Group submitted to the
477Department an application for a CCCL permit pursuant to Chapter
487161, Florida Statute s, to construct 17 luxury townhome units in
498two four - story buildings, a pool, a dune walk - over, and
511ancillary parking and driveway areas (hereafter the Project ).
520The Department designated the application as File No. SL - 224.
5313. The property on which the Project is proposed
540(hereafter the Property ) is located between the Department's
549reference monument s R - 34 and R - 35, in St. Lucie County . The
565Propertys address is 222 South Ocean Drive, Fort Pierce,
574Florida.
5754. The Property is located seaward of the CCCL line
585estab lished in accordance with S ection 161.053, Florida
594Statutes , and Florida Administrative Code Rule Chapter 62B - 33.
6045. On April 21, 2006, the application was determined to be
615complete.
6166. By letter dated June 5, 2006, the Departme nt notified
627Beach Group that the Project appeared to be located seaward of
638the 30 - year erosion projection of the seasonal high water line
650(SHWL ), and that in accordance with S ection 161.053(6), Florida
661Statutes, the staff could not recommend approval of th e Project
672since major structures are seaward of the estimated erosion
681projection.
6827. By letter dated July 7, 2006, and subsequent
691submittals, Beach Group requested a waiver of the 90 - day time
703period for processing completed applications pursuant to Cha pter
712120, Florida Statutes, until October 31, 2006.
7198. On August 30, 2006, Beach Group submitted a certified
729engineering analysis of the 30 - year erosion projection of the
740SHWL for the Department's consideration pursuant to Florida
748Administrative Code R ule 62B - 33.024(1). Beach Group's analysis
758determined that the proposed major structures associated with
766the Project were located landward, not seaward, of the 30 - year
778erosion projection.
7809. The Department also performed its own 30 - year erosion
791project ion of the SHWL, and determined that the proposed major
802structures were located seaward, not landward, of the 30 - year
813erosion projection. The Department asserts that the proposed
821structures are located between 87 feet and 68 feet seaward of
832the Department 's determination of the 30 - year erosion
842projection.
84310. The Department disagreed with Beach Group's analysis
851because the analysis ap peared to be inconsistent with S ection
862161.053(6), Florida Statutes, Florida Administrative Code Rule
86962B - 33.024, and th e Department's own analysis.
87811. The Property is located just south of the Fort Pierce
889Inlet , and landward of a federally maintained beach restoration
898project that had approximately 14 years of life remaining under
908the existing Congressional authorizat ion when the permit was
917submitted to the Department.
92112. By proposed Final Order dated November 1, 2006, the
931Department provided to Beach Group notice of its intent to deny
942the permit application.
94513. The proposed Final Order was received by Beach G roup
956on November 8, 2006. Beach Group's petition for hearing was
966timely filed with the Department.
97114. Since the Department proposes to deny Beach Group's
980CCCL permit application, its substantial interests are clearly
988at issue, and it has standing to maintain this proceeding.
99815. On December 11, 2006, the Department issued an
1007environmental resource permit for the Project .
101416. The Department denied Beach Groups permit application
1022because the Project extends seaward of the 30 - year erosion
1033projection calculated by the Department and because the
1041Projects i mpacts to the beach - dune system had not been
1053minimized . The permit was not denied on the basis of the
1065existence, or absence , of a line of continuous construction in
1075the vicinity of the Project .
1081B. T he 30 - year Erosion Projection
1089(1) Background
109117. Fort Pierce Inlet (hereafter the inlet) was
1099constructed by the Army Corps of Engineers in the 1920s. The
1110channel of the inlet is protected by two jetties that extend
1121several hundred feet into the Atl antic Ocean.
112918. The jetties act as a barrier to the littoral transfer
1140of sand from the north to south that would otherwise occur along
1152the beach in the vicinity of the Property. The jetties cause
1163accretion on the beach to the n orth of the inlet and eros ion of
1178the beach to the south of the inlet.
118619. The inlet channel beyond the jetties also restricts
1195the littoral transfer of sand in the area. The deepening and
1206widening of the channel in 1995 likely contributed to the
1216increased erosion observed south of the inlet in recent years.
122620. The beach to the south of the inlet, including that
1237portion on the Property , is designated as a critically eroded
1248beach by the Department. The inlet is the primary cause of the
1261erosion.
126221. Congress first authorized bea ch nouri shment s outh of
1273the inlet in 1965 . That authorization expired in 1986.
128322. Congress reauthorized beach nourishment south of the
1291inlet in 1996. Th at authorization expire s in 2021 , but St.
1303Lucie County has requested that the authorization be ext ended
1313for another 50 years.
131723. The first major beach nourishment south of the inlet
1327occurred in 1971. Subsequent major nourishments occurred in
13351 980, 1999, 2003, 2004, and 2005 . Another major nourishment
1346is planned for 2007.
135024. There was a m oderate nourishment of the beach in
13611995 , which included the placement of geotextile groins on the
1371beach just to the north of the Property . Small nourishment s
1383occurred in 1973, 1978, 1987, 1989, 19 90, 1992, 1994, 1997 , and
13951998.
139625. Cumulatively, the nourishment s that occurred between
1404the major nourishments in 1 980 and 1999 involved approximately
1414419,000 cubic yards of sand , which is more than the volume
1426in volved in several of the major nourishments.
143426. B each nourishment south of the inlet has b een an
1446ongoing effort since it started in 1971 . The more persuasive
1457evidence establishes that the nourishment project that is
1465authorized through 2021 is a continuation of the project started
1475in 1971 rather than a separate and distinct project.
148427. V ario us er osion control efforts have been used south
1496of the inlet in conjunction with the beach nourishment efforts.
1506For example, g eotextile groins (which are essentially massive
1515sandbags) have been installed and removed on several occasions
1524since the mid - 1990 s in order to temporarily stabilize the
1536shoreline until such measures could be taken to design, permit
1546and c onstruct a long - term solution; concrete rubble and other
1558riprap has been placed on the beach over the years (without a
1570permit from the Department ) to protect upland structures from
1580erosion; and a " spur jetty " was constructed on the south jetty
1591in an effort to reduce erosion south of the inlet.
160128. These efforts have not slowed the pace of the erosion
1612or minimized the need for beach nourishment so uth of the inlet .
1625Indeed, the need for and frequency of major nou rishments south
1636of the inlet have increased in recent years.
164429. Beach erosion south of the inlet will continue to be a
1656serious problem so long as the inlet exists and the jetties
1667remain in place. There is no reason to expect that the inlet or
1680the jetties will be removed in the foreseeable future and, as a
1692result, beach nourishment south of the inlet will continue to be
1703necessary.
170430. The Department has recognized the need for continuin g
1714nourishment of the beach south of the inlet, as reflected in
1725both the S trategic Beach M anagement P lan for the St. Lucie
1738Bea ches and the Ft. Pierce Inlet Management Study Implementation
1748Plan. Those plans acknowledge the long - term need for continued
1759nouri shment of the beach at a rate of at least 130,000 cubic
1773yards on an average annual basis. The plans do not, however,
1784guarantee that future beach nourishment in the area will occur
1794at that , or any , rate.
1799(2) Rule Methodology
180231. Florida Administrative Code Rule 6 2 B - 33.024 contains
1813the methodology for determining the 30 - year erosion projection,
1823which is the projected location of the SHWL 30 years after the
1835dat e of the permit application under review.
184332. Where, as here, the beach at issue is subject to an
1855ongoing beach nourishment project, the methodology requires
1862consideration of pre - project conditions -- i.e. , the
1871conditions that existed before the beach nourishment efforts
1879started -- because those conditions are used to project how the
1890beach will mi grate landward in the periods over the next 30
1902years when there may not be any be ach nourishment activity .
191433. The coastal engineering experts presented by the
1922parties -- M ichael Walther for Beach Group and Emmett Foster for
1934the Department -- used essenti ally the same methodology to
1944determine the location of the 30 - year erosion projection .
1955However, the variables that they used in each step of the
1966methodology differed.
1968(a) Step 1: Locate th e Pre - Project MHWL
197834. The first step in determining the 30 - year e rosion
1990projection is to locate the pre - project MHWL .
200035. If a pre - project erosion control line (ECL) 3 has been
2013established in the area, i t is to be used as the starting - point
2028for the determination of the 30 - year erosion projection.
2038Oth erwise a pre - proj ect survey of the MHW L is to be used as the
2056starting - point.
205936. Mr. Walther used a 1997 ECL as the starting point for
2071his analysis. Mr. Foster used a March 2002 survey of the MHWL
2083as the starting point for his analysis because he did not
2094consider the 199 7 ECL to be an appropriate pre - project ECL .
210837. The March 2002 survey of the MHWL is not itself an
2120appropriate starting point for the analysis. The survey is not
2130a pre - project survey, no matter how the project is defined;
2142the survey occurred more than 30 years after the nourishments
2152started in 1971, and three years after the first major
2162nourishment pursuant to the Congressional rea uthorization of the
2171project. Moreover, as discussed below, there is a n appropriate
2181pre - project ECL in the area.
218838. Ther e are two lines that might be considered to be a
2201pre - pr oject ECL in this case -- (1) the ECL established in 1997 ,
2216and (2) the South Beach High Tide Line (SBHTL) established in
22271968.
222839. The 1997 ECL was established based upon a survey of
2239the MHWL performe d on May 5, 1997. Th e survey occurred two
2252years after a moderate beach nour ishment and the placement of
2263the geotextile groins on the beach. There was also a small
2274nourishment in 1997, but the record does not reflect whether
2284that nourishment occurred before or after the survey.
229240. The SBHTL was established based upon a survey of the
2303MHWL between 1966 and 1968 , prior to the initial nourishment of
2314the beach south of the inlet. It is approximately 65 feet
2325landward of the 1997 ECL.
233041. The SBHTL is the functional equivalent of an ECL , and
2341it roughly corresponds to the best fit line for the March 2002
2353survey used by Mr. Foster as the starting point for his
2364determination of the 30 - year erosion projection in this case.
237542. The Department contends that t he 1997 ECL i s not based
2388upon a pre - project survey of the MHWL because the applicable
2400beach restoration project south of the inlet began in the 1970s
2411and has been ongoing since that time. Beach Group contends that
2422the applicable project is the current one that is authorized
2432through 2021, and that the 1997 sur vey preceded the start of the
2445nourishment s authorized by that project.
245143. The Department has used the 1997 ECL as the starting -
2463point for determining the 30 - year erosi on projection in several
2475prior permits in the vicinity of the P roject , 4 and i n an April 9,
24911999, memorandum discussing the 30 - year erosion projection in
2501the vicinity of monuments R - 35 and R - 36, Mr. Foster stated that
2516the ECL represents the pre - project [MHWL] .
252544. Mr. Foster no longe r considers the 1997 ECL to be the
2538appropriate pre - project MHWL for purposes of determining the 30 -
2550year erosion projection south of the inlet. He testified that
2560had he been aware of the complete background of the 1997 ECL
2572and the extent of the nourishme nts in the 1980s and 1990s , he
2585would have brought the issue to the Departments attention so
2595that the Department could consider whether the 1997 ECL or an
2606earlier prenourishment line was the appropriate pre - project
2615MHWL.
261645. Although it is a close que stion, t he more persuasive
2628evidence presented at the final hearing establishes that the
26371997 ECL is not an appropriate pre - project MHWL because the
2649applicable project includes the beach nourishment efforts
2656started in 1971 that have continued through the present , even
2666though those efforts were intermittent at times .
267446. Thus, the a ppropriate starting point for determining
2683the location of the 30 - year erosion projection is the SBHTL , not
2696the 1997 ECL used by Mr. Walther or the March 2002 MHWL survey
2709u sed by Mr. Foster .
2715(b) Step 2: Locate the Pre - Project SHWL
272447. The second step in determining the 30 - year erosion
2735projection is to determine the location of the pre - project SHWL.
274748. Mr. Walther located the pre - project SHWL 26.4 feet
2758landward of the 1997 E CL. That is the surveyed distance between
2770the MHWL and SHWL in June 2005.
277749. Mr. Foster located the pre - project SHWL at the most
2789landward location that the SHWL w as surveyed i n March 2002. Th e
2803line is between 50 and 75 feet 5 landward of the best fine line
2817used by Mr. Foster as the pre - project MHWL, and it is as much as
283325 feet landward of the surveyed location of the SHWL in some
2845areas.
284650. Mr. Foster used an average [of] 50 feet as the MHWL -
2859to - SHWL distance in his analysis of several prior permit s in the
2873vicinity of the Project . 6
287951. Mr. Foster te stified that the distance betwe en the
2890MHWL and SHWL in this area varies from the 20s in the immediate
2903post - nourishment situation s . . . all the way up to 70 - some
2919feet and that the the averages gravi tate towards 40 feet.
293052. Consistent with that testimony, the distance between
2938the surveyed locations of the MHWL and SHWL depicted on
2948Department Exhibit 6 is approximately 40 feet, on average.
295753. The MHWL - to - SHWL distance calculated by Mr. Walther is
2970not a reasonable projection of the pre - project distance because
2981it was based upon survey data taken immediately after a major
2992beach nourishment when the shoreline was unnaturally steep and ,
3001hence, not representative of pre - project conditions.
300954. The SHWL located by Mr. Foster is also not a
3020reasonable projection of the pre - project SHWL because it was
3031based upon a March 2002 survey (which is clearly not " pre -
3043project " ); because it used the most landward surveyed location
3053of the SHWL rather than a best fit line or an average of the
3067distances between the surveyed MHWL and SHWL ; and because it
3077runs across areas of well - established dune vegetation.
308655. In sum, t he MHWL - to - SHWL distance calculated by Mr.
3100Walther (26.4 feet) is too low, whereas the distance resulting
3110from Mr. Foster's siting of the SHWL based on the March 2002
3122survey (50 to 75 feet) is too high. Those distances are
3133essentially endpoints of the range observed in this area , as
3143described by Mr. Foster.
314756. A more reasonable estimate of the pre - project MHWL - to -
3161SHWL distance is approximately 40 feet . See Findings 51 and 52.
317357. Thus, th e pre - project SHWL is located 40 feet landward
3186of and parallel to the SB HTL . That line is not depicted on any
3201of the exhibits, but on Petitioners Exhibit 37 , it roughly
3211corresponds to a straight line between the points where the red -
3223dashed line intersects the Propertys north and south
3231boundaries.
3232(c) Step 3: Calculate the Erosion Rate
323958. The third step in determining the 30 - year erosion
3250projection is to calculate an erosion rate.
325759. The erosion rate used by Mr. Foster was - 7 feet per
3270year (ft/yr) . T hat rate was calculated based upon an average of
3283the shoreline change data for monument R - 35 for the period from
32961949 to 1967. The rate would have been h ig her had Mr. Foster
3310averaged the rate s for the nearby monuments. 7
331960. The erosion rate used by Mr. Walther was - 4.9 f t/yr .
3333That rate was calculated based upon an average of the shoreline
3344change data for monuments R - 34 to R - 39 over the period of 1930
3360to 19 68.
336361. An erosion rate of - 7 ft/ yr south of the inlet was
3377referenced in permit application s submitted by Mr. Walters
3386firm , Coastal Tech, for several shore protection structures
3394south of the inlet ; was used by Mr. Foster in his review of
3407several prior CC CL permit applications south of the inlet ; and
3418was included in reports on the inlet prepared by the Army Corps
3430of Engineers over the years .
343662. An erosion rate of - 3.3 ft/yr was used and accepted by
3449the Department in its review of another permit applicati on in
3460the general vicinity of the project. 8 That erosion rate was
3471based upon data from the period of 1972 to 1994, which is after
3484the beach nourishment sta r ted south of the inlet.
349463. It is not entirely clear why Mr. Foster chose to use a
3507data set starti ng in 1949, particularly since his report stated
3518that the 1928 - 30 survey already shows significant erosion
3528occurring south of the inlet. His testimony did not adequately
3538explain the choice of that data set.
354564. The use of a longer data set is typically more
3556appropriate when calculating a historical rate. In this case,
3565however, the use of the shorter period of 1949 - 68 is reasonable
3578because the 1930 - 49 erosion r ate was considerably lower than the
35911949 - 68 rate, 9 which has the effect of skewing the erosion rate
3605calculated for the longer period of 1930 - 68.
361465. The higher erosion rate calculated by Mr. Foster also
3624better takes into account the i ncreased frequency of the
3634nourishments in recent years as well as the continued need for
3645shore stabilization in the area.
365066. In sum, the higher erosion rate of - 7 f t/yr calculated
3663by Mr. Foster using the 1949 - 68 data set better reflects the
3676historical post - inlet, pre - nourishment erosion rate than does
3687the lower erosion rate calculated by Mr. Walther.
3695(d) Step 4: De termine the Remaining Project Life
370467. The f ourth step in determining the 30 - year erosion
3716projection is to determine the remaining project life of the
3726 exist ing beach nourishment project .
373468. It was stipulated that there are 14 ye ars remaining
3745until t he currently authorized federal beach rest oration project
3755expires .
375769. It is reasonable to expect that beach nourishment
3766south of the inlet will continue well beyond th e expiration of
3778the current federal project , but there were no other funded and
3789permitt ed projects in place a t the time Beach Groups permit
3801application was filed.
380470. Potential future beach nourishment projects are not
3812considered existing under the rule methodology in Florida
3820Administrative Code Rule 62B - 33.024 unless they are funded and
3831permitted at the time the application at issue is filed.
384171. Mr. Walther used the 14 - year remaining life of the
3853existing federal project in his calculation of the 30 - year
3864erosion projection, as did Mr. Foster.
387072. The remaining project life applicable to this case
3879is 14 years, notwithstanding the likelihood of continued beach
3888nourishment in the area beyond the expiration of the existing
3898project.
3899(e) Step 5: Calculate the 30 - year Erosion Projection
390973. The final step in determining the location of th e 30 -
3922year erosion projection is a calculation using the variables
3931determined in the previous steps.
393674. The calculation is as follows: first, the re maining
3946project life determined in step four is subtracted from 30;
3956then, that result is multiplied by the erosion rate determined
3966in step three to get a distance; and, finally, the SHWL is moved
3979t hat distance landward of its pre - project location determined in
3991step two.
399375. Subtracting the remaining project of 14 years from 30
4003equals 16 years.
400676. Multiplyin g 16 years by the erosion rate of - 7 f t/yr
4020equals 112 feet, which means that the 30 - year erosion line is
4033located 112 feet landward of the pre - project SHWL (or 152 feet
4046landward of the SBHTL) .
405177. That line is not depicted on any of the exhibits, but
4063it ro ughly corresponds to a straight line than runs across the
4075Property parallel to the SBHTL just landward of the conc. pad
4086and existing conc. Pile caps (typ) shown on Petitioners
4095Exhibit 37. The line is 25 to 30 feet seaward of Mr. Fosters
410830 - year eros ion projection depicted on that exhibit.
4118(3) Ultimate Finding Regarding the Location of
4125the Proposed Structures in Relation to
4131the 30 - year Erosion Projection
413778. The Project includes major structures seaward of th e
414730 - year erosion projection, as deter mined above.
4156C. Impacts of the Pr oject on the Beach - Dune System
416879. The Project includes 17 luxury town home units in t wo
4180four - story buildings, a pool and spa, landscaping, and a n
4192elevated dune walkover. The units will range from 2,700 to
42034,400 square f eet of living space and are projected to be
4216offered for sale in the $1.5 to $2.5 million range .
422780. B e ach Groups principal , Harold Seltzer, testified
4236that the Project is sited as far landward as possible to allow
4248for the development of all 17 units while still complying with
4259the local setback and height restrictions; that the Project s
4269financial viability depends upon it being developed as proposed;
4278and that the Project cannot be redesigned and remain financially
4288viable.
428981. The CCCL permit application i ncluded a letter from the
4300City of Ft. Pierce confirming that the Project is consistent
4310with the applicable local development codes . Mr. Seltzer
4319testified that the Projects local development approvals expired
4327in September 2006 because the CCCL permit had not been issued,
4338and that Beach Group is having to go back through the local
4350permitting process .
435382. The seaward extent of the Project is the 1978 CCCL,
4364which is approximately 250 fee t seaward of the current CCCL.
437583. The buildings on the adjacent proper ties are also
4385located on the 1978 CCCL. The Project does not extend further
4396seawar d than the nearby development, including the structures
4405authorized by the Department in File Nos. SL - 162 and SL - 173. 10
442084 . The seaward boundary of the Property is the SBHTL .
4432That line is approximately 295 feet landward of the MHWL
4442established in June 2005, and as noted above, it is
4452approximately 65 feet landward of the ECL established in 1997.
446285 . The adjacent propert ies are developed with multi - s tory
4475residential buildings. There is a densely vegetated dune
4483feature in front of the building to the south of the Property .
4496There is some vegetation, but no discernable dune in front of
4507the building to the north of the Property .
451686 . The Property as a whole is sparsely vegetated , but
4527there are areas of prolific vegetation on the P roperty .
453887 . The seaward extent of the vegetation on the Property
4549roughly corresponds t o the location of the 1978 CCCL. There are
4561several mature sea grape cluste rs in the vicinity of that line .
457488 . The beach in front of the Property is devoid of
4586vegetation. It has a steep slope immediately landward of the
4596water line; a wide (approximately 270 feet) expanse of
4605relatively flat beach; and a gently sloping dune feature that
4615starts just landward of the P roperty s seaward boundary, crests
4626approximately 30 feet fa rther landward, and then gradually
4635slopes downward across the Property all of the way to State Road
4647A1A .
464989 . The dune feature on the Property is the frontal dun e.
4662It is the first mound s a nd locat ed landward of the beach that
4677has sufficient vegetation, height, continuity, and configura tion
4685to offer protective value.
468990 . The crest of the frontal dune is seaward of the
4701vegetation line on the Property , and ranges in height from .7
4712to .2 feet NAV D. 11 The seaward toe of the dune is shown on
4727the topographic survey for the Property at elevations ranging
4736fr om .27 to .85 feet NAVD. Similar elevations occur on the
4748landward side of the dune crest, just landward of the 1978 CCCL .
476191 . The vegetation on the Property extends landward of the
47721978 CCCL and landward of the line shown on the topographic
4783survey of the Property as the approximate location of sparse
4793grass and ground cover. The landward extent of the vegetation
4803does not in and of itself defi ne the landward extent of the
4816dune; changes in the slope of the ground must also be
4827considered.
482892 . The more persuasive evidence establishes that the
4837landward toe of the frontal dune is landward of the 1978 CCCL,
4849but not as f ar landward as suggested by D epartment witness Tony
4862McNeal . 12 The landward toe of the dune on the P roperty is best
4877defined by the elevations landward of the dune crest similar to
4888the elevations shown for the seaward toe of the dune.
489893 . The Project extends into the frontal dune on th e
4910P roperty , and it will requires minor excavation of the frontal
4921dune, primarily in the area of the proposed pool.
493094 . All aspects of the project, except for the proposed
4941dune walkover, will be landward of the crest of the frontal dune
4953and t he mature sea grape clusters located on th e dune.
496595 . There will be no net excavation on the Property as a
4978result of the Project . The sand excavated for the pool will be
4991placed on - site , and additional beach - compatible sand will be
5003used as fill for the site. Overall, the Project will result in
5015the net placement of approximately 66 cubic yards of sand on the
5027Property .
502996 . The proposed structures will be elevated on piles,
5039which will allow the beach - dune system to fluctuate under the
5051structure s during storm events. The finished floor elevation of
5061the proposed structures is approximately feet NAVD, which is
5070slightly higher than the elevations associated with the toes of
5080the frontal dune.
508397 . The Project will not destabilize the frontal dune,
5093even though it will encr oach into the dune.
510298 . The impacts of the Project on the beach - dune system
5115will be mitigated by the placement of additional sand into the
5126beach - dune system, as described above.
513399 . The Projects impacts will be further mitigated by the
5144enhancements to the frontal dune described in the permit
5153application .
5155100 . Mr. Walt her testified that the frontal dune on the
5167Property could very easily be enhanced to be of comparable
5177height and magnitude of the dun es on the adjacent properties .
5189101 . T he permit a p plication proposes enhancements to the
5201frontal dune as part of the Site Landscaping Plan for the
5212Project. The proposed enhancements include increasing the crest
5220of the dune to a height of feet NAVD , and extensive planting
5232of the dune with sea grapes, beach morning glories, and sea
5243oats. The plantings would extend from the 1978 CCCL to the
5254seaward toe of the existing frontal dune.
5261102 . The dune enhancements proposed in the permit
5270application should be included as a specific condition of the
5280CCCL permi t for the Project, if it is approved.
5290CONCLUSIONS OF LAW
5293103 . DOAH has jurisdiction over the parties to and subject
5304matter of this proceeding pursuant to Sections 120.569 and
5313120.57(1), Florida Statutes .
5317104 . Beach Group has the burden to prove by a
5328pre ponderance of the evidence that its permit application should
5338be approved. See Dept. of Transportation v. J.W.C. Co., Inc. ,
5348396 So. 2d 778, 788 - 89 (Fla. 1st DCA 1981).
5359105 . The Departments interpretation of the statutes and
5368rules governing the issuance of CCCL permits is entitled to
5378deference . See , e.g. , Dept. of Environmental Reg. v. Goldring ,
5388477 So. 2d 532, 534 (Fla. 1985) (Courts should accord great
5399deference to administrative interpretations of statutes which
5406the administrative agency is required to enforce.) .
5414106 . Generally, a ll construction seaward of the CCCL
5424requires a permit from the Department , unless an exemption
5433applies . See § 161.053 , Fla . Stat. ; Atlantis at Perdido Assn
5445v. Warner , 932 So. 2d 1206 (Fla. 1st DCA 2006). No exemption
5457ap pl ies in this case.
5463107 . T he Department may not issue a CCCL permit for major
5476structures seaward of the 30 - year erosion projection , except in
5487limited circumstances not applicable in this case . See
5496§ 163.053(6)(b), Fla. Stat .
5501108 . Florida Administrative Code Rule 62B - 33.024
5510establishes the procedure for determining the location of the
55193 0 - year erosion projection . The rule provides in pertinent
5531part :
5533(1) A 30 - year erosion projection is the
5542projection of long - term shoreline recession
5549occurring over a peri od of 30 years based on
5559shoreline change information obtained from
5564historical measurements. A 30 - year erosion
5571projection of the seasonal high water line
5578(SHWL) shall be made by the Department on a
5587site specific basis upon receipt of an
5594application with th e required topographic
5600survey . . . for any activity affected by
5609the requirements of Section 161.053(6), F.S.
5615An applicant may submit a proposed 30 - year
5624erosion projection for a property, certified
5630by a professional engineer licensed in the
5637state of Flori da, to the Department for
5645consideration.
5646(2) A 30 - year erosion projection shall be
5655determined using one or more of the
5662following procedures:
5664(a) An average annual shoreline change
5670rate in the location of the mean high water
5679line (MHWL) at a Departm ent reference survey
5687monument shall be determined and multiplied
5693by 30 years. The resulting distance shall
5700be added landward of the SHWL located on the
5709application survey. The rate shall be
5715determined as follows:
57181. The shoreline change rate shall be
5725derived from historical shoreline data
5730obtained from coastal topographic surveys
5735and maps, controlled aerial photography, and
5741similar sources approved by the Department.
5747Data from periods of time that clearly do
5755not represent current prevailing coastal
5760p rocesses acting on or likely to act on the
5770site shall not be used.
57752. The shoreline change rate shall
5781include the zone spanned by three adjacent
5788Department reference monuments on each side
5794of the site. A lesser or greater number of
5803reference monuments can be used as necessary
5810to obtain a rate representative of the site,
5818and a rationale for such use shall be
5826provided.
58273. In areas that the Department
5833determines to be either stable or accreting,
5840a minus one - foot per year shoreline change
5849rate shall be applied as a conservative
5856estimate.
5857* * *
5860(d) Beach nourishment or restoration
5865projects shall be considered as follows:
58711. Future beach nourishment or
5876restoration projects shall be considered as
5882existing if all funding arrangements have
5888been made and all permits have been issued
5896at the time the application is submitted.
59032. Existing beach nourishment or
5908restoration projects shall be considered to
5914be either a one - time beach construction
5922event or a long - term series of related sand
5932placement e vents along a given length of
5940shoreline. The Department shall make a
5946determination of remaining project life
5951based on the project history, the likelihood
5958of continuing nourishments, the funding
5963arrangements, and consistency with the
5968Strategic Beach Manage ment Plan adopted by
5975the Department for managing the states
5981critically eroded shoreline and the related
5987coastal system.
59893. The MHWL to SHWL distance landward of
5997the erosion control line (ECL) shall be
6004determined. If the ECL is not based on a
6013pre - proje ct survey MHWL, then a pre - project
6024survey MHWL shall be used instead of the
6032ECL. The pre - project SHWL shall be located
6041by adding the MHWL to the SHWL distance
6049landward of the pre - project MHWL (usually
6057the ECL). The remaining project life, which
6064is the nu mber of years the restored beach
6073MHWL is expected to be seaward of the ECL,
6082shall be subtracted from the 30 years as a
6091credit for the nourishment project. The
6097non - credited remaining years times the pre -
6106project shoreline change rate for the site
6113yields the 30 - year projection distance
6120landward of the pre - project SHWL.
61274. If the Department is unable to
6134scientifically determine a pre - project
6140erosion rate due to a lack of pre - project
6150data, the Department shall set the 30 - year
6159erosion projection along an exi sting,
6165reasonably continuous, and uniform line of
6171construction that has been shown to be not
6179unduly affected by erosion.
6183109 . Beach Group argues in its PRO (at paragraph 58.d)
6194that , for purposes of applying this rule methodology, the
6203remaining project l ife applicable to this case
6211is likely to exceed 30 years, given the
6219history of beach renourishment in this area
6226since 1971, the likelihood of continuing
6232renourishments, including a request by St.
6238Lucie County to extend the life of the
6246nourishment project (and the unlikelihood
6251that state, federal and local governments
6257will allow this and other similarly situated
6264structures to simply fall into the Atlantic
6271Ocean), funding arrangements, and
6275nourishment projects undisputed consistency
6279with the Strategic Beach Management Plan and
6286the Fort Pierce Inlet Management Plan.
6292110 . There is some appeal to this argument , particularly
6302since it is reasonable to expect that beach nourishment south of
6313the inlet will continue for the foreseeable future. However,
6322t he potent ial for continued nourishments beyond the term of the
6334 existing project is not appropriate for consideration under
6343Florida Administrative Code Rule 62B - 33.024. See also
6352§ 161.053(6)(d), Fla. Stat.
6356111 . The existing project includes future nourishment
6364project s only if all funding arrangements have been made and
6375all permits have been issued at the time the application is
6386submitted. F la. Admin. Code R. 62B - 33.024(2)(d)1. Potential
6396(or even likely) future nourishment projects other than one
6405authorized by Congress through 202 1 do not meet that standard. 13
6417112 . The factors listed in Florida Administrative Code
6426Rule 62B - 33.024(2)(d)2 . relating to the Departments
6435determination of remaining project life necessarily relate to
6443 existing project s, as defined in Subparagraph (2)(d)1 . of the
6456rule. Indeed, it would be illogical -- and , arguably, contrary
6466to Section 161.053(6)(d), Florida Statutes -- to construe
6474Subparagraph (2)(d)2 . of the rule to allow for consideration of
6485projects that would not be considered to be existing under
6495Subparagraph (2)(d)1 . of the rule.
6501113 . The more persuasive evidence establishes that the
6510Project extends seaward of the 30 - year erosion projection . See
6522Findings of Fact, Part B. Therefore, the Department may not
6532issue a CCCL perm it for the Project . See § 161.053(6)(b), Fla.
6545Stat.
6546114 . In light of th is co nc lusion, it is not necessary to
6561determine whether the Project otherwise satisfies the applicable
6569CCCL permit ting requirements . H owever, th e issue will be
6581addressed below in an abundance of caution in the event that t he
6594Department or an appellate court rejects the conclusion that the
6604Project is located seaward of the 30 - year erosion projection .
6616115 . The Department is authorized to issue permits for
6626construction seaward of the CC CL if the permit is clearly
6637justified based upon the consideration of facts and
6645circumstances, including the potential impacts of the proposed
6653construction on the beach - dune system . See § 161.053(5)(a)3.
6664Fla. Stat.
6666116 . The general criteria governing a pproval of a CCCL
6677permit are set forth in Florida Admin istrative Code 62B - 33.005.
6689The rule requires the applicant to provide the Department with
6700sufficient information pertaining to the proposed project to
6708show that any impacts associated with the constr uction have been
6719minimized and that the construction will not result in a
6729significant adverse impact. Fla. Admin. Code R. 62B - 33.005(2).
6739117 . It is undisputed that the Project will not result in
6751a significant adverse impact , which is defined as an adv erse
6764impact of such magnitude that it may alter the coastal system by
6776measurably affecting the existing shoreline change rate;
6783significantly interfering with its ability to recover from a
6792coastal storm; or disturbing topography or vegetation such that
6801the dune system becomes unstable or suffers catastrophic failure
6810or the protective value of the dune system is significantly
6820lowered. See Fla. Admin. Code R. 62B - 33.002(31)(b).
6829118 . At issue is whether the Project will cause adverse
6840impacts to the beach - du ne system and, if so, whet h er those
6855impacts have been minimized. Adverse impacts are impacts to the
6865coastal system that may cause a measurable interference with he
6875natural func t ioning of the system. See F la. Admin. Code R. 62B -
689033.002(31)(a ).
6892119 . Florid a Administrative Code Rule 62B - 33.005(3)(b)
6902requires siting and design criteria that minimize adverse and
6911other impacts and . . . mitigation of adverse impacts . The
6924Deparment contends that the Project fails to meet the
6933requirements of th is rule because the Project w ill be located on
6946the frontal dune, no t landward of the dune.
6955120 . For the same reason, the Department contends that the
6966Project fails to meet the requirements of Florida Administrative
6975Code Rule 62B - 33.005(8), which requires major structures to be
6986located a sufficient distance landward of the beach and frontal
6996dune to permit natural shoreline fluctuations, to preserve and
7005protect beach and dune system stability, and to allow natural
7015recovery to occur following storm - induced erosion.
7023121 . I t is undisputed that the Project satisfies the
7034permitting criteria in Florida Admi nistrative Code Rule 62B -
704433.005, except for those in paragraph (3)(b) and subsection (8).
7054122 . The frontal dune is the first natural or manmade
7065mound or bluff of sand which is located landward of the beach
7077and which has sufficient vegetation, height, continuity, and
7085configuration to offer protective value. § 161.053(6)(a)1.,
7092Fla. Stat. It is undisputed that the Project encroaches i nto
7103frontal dune, but that it is behind t he crest of the dune.
7116123 . The only express statutory or rule prohibition
7125against construction on a frontal dune is in the limited
7135circumstance where construction of a single - family dwelling is
7145permitted seaward of the 30 - year erosion projection. See
7155§ 1 61.053(6)(c)3. - 4., Fla. Stat. (requiring the dwelling to be
7167located landward of the frontal dune structure and as far
7177landward . . . as practicable without being located seaward of
7188or on the frontal dune).
7193124 . There is no express statutory prohibiti on against
7203construction on a frontal dune landward of the 30 - year erosion
7215projection, so long as the proposed construction does not
7224destabilize the frontal dune or otherwise adversely impact the
7233beach - dune system. See , e.g. , Young v. Dept. of Environmenta l
7245Protection , 2005 Fla. ENV LEXIS 155 , at ¶¶ 83, 111 (DOAH Aug.
725715, 2005 ), adopted in toto , 2005 Fla. ENV LEXIS 154 ( DEP Sep.
727126, 2005), affd per curiam , 937 So. 2d 133 (Fl a. 2nd DCA 2006)
7285(table) .
7287125 . Florida Administrative Code Rule 62B - 33.005(8) does
7297not expressly prohibit construction that encroaches into a
7305frontal dune; it only requires that major structures be located
7315a sufficient distance landward of the . . . frontal dune to
7327permit natur al shoreline fluctations, to preserve and protect
7336beach and dune system stability, and to allow natural recovery
7346to occur following storm - induced erosion . Where, as here, the
7359more persuasive evidence establishes that the location of the
7368proposed structures on the landward side of the crest of the
7379frontal dune wi ll not destabilize the dune or otherwise
7389adversely affect the beach - dune system, the purpose of the rule
7401is satisfied . See Young , supra .
7408126 . The stability of the beach - dune system in the
7420vicinity of the Property is dependent upon the continuing
7429renour ish ment efforts ; the contribution of the frontal dune on
7440the P roperty to the stability of the beach - dune system or the
7454protection of upland properties is relatively minor in
7462comparison. As a result, t he slight encroachment of the Project
7473into the landward side of the frontal dune will not have a
7485material impact on t he na tural functioning of the beach - dune
7498system or the ability of the system to recover following storm -
7510induced erosion.
7512127 . The impacts to the frontal dune will be limited to
7524minor excavation s and the removal of existing dune vegetation in
7535areas behind the crest of the dune . Those impacts will not
7547destabilize the frontal dune or materially affect the ability of
7557th e dune or the beach - dune system to recover from storm events ,
7571and the impacts ha ve been adequately mitigated through the
7581plac e ment of additional sand in the beach - dune system and the
7595proposed enhancements to the frontal dune.
7601128 . In sum, if it is determined contrary to the
7612conclusion above that the Project is landward of the 30 - yea r
7625erosion projection, the permit should be approved because the
7634more persuasive evidence establishes that the Project satisfies
7642the applicable criteria in Florida Administrative Code Rule 62B -
765233.005.
7653RECOMMENDATION
7654Based upon the foregoing findings of fac t and conclusions
7664of law, it is
7668RECOMMENDED that the Department issue a final order denying
7677Beach Groups application for a CCCL permit.
7684DONE AND ENTERED this 19th day of April, 200 7 , in
7695Tallahassee, Leon County, Florida.
7699S
7700T. KENT WETHERELL, II
7704Administrative Law Judge
7707Division of Administrative Hearings
7711The DeSoto Building
77141230 Apalachee Parkway
7717Tallahassee, Florida 32399 - 3060
7722(850) 488 - 9675 SUNCOM 278 - 9675
7730Fax Filing (850) 921 - 6847
7736www.doah.state.fl.us
7737Filed with the Clerk of the
7743Division of Administrative Hearings
7747this 19th day of April , 2007 .
7754ENDNOTES
77551 / All statutory references in this Recommended Order are to the
77672006 version of the Florida Statutes.
77732 / Finding s 1 throug h 14 are based upon the stipulations in the
7788Joint Pre - hearing Stipulation . Finding s 15 and 16 are based
7801upon stipulations at the final hearing. See Tr. 102 - 03, 191 - 97.
78153 / The ECL represents the boundary between the sovereignty lands
7826of the state and th e adjacent upland properties. See §
7837161.151(3), Fla. Stat. An ECL is to be established prior to a
7849beach restoration project in order to define the ownership of
7859the beach created by the project. See § 161.141, Fla. Stat.
7870The new beach created seaward of the ECL is state property ; any
7882new beach created landward of the ECL is private property
7892subject to a public easement across the property. See §§
7902161.141, 161.191, Fla. Stat. But cf. Save Our Beaches, Inc. v.
7913Dept. of Environmental Protection , 31 Fla. L . Weekly D1173 (Fla.
79241st DCA Apr. 28, 2006) (holding that the establishment of an ECL
7936as part of a beach renourishment project results in an
7946unconstitutional taking of the upland property owners riparian
7954rights), question certified , 31 Fla. L. Weekly D181 1 (Fla. 1st
7965DCA July 3, 2006), rev. granted , 937 So. 2d 1099 (Fla. 2006).
79774 / See , e.g. , Pet. Ex. 24 (File Nos. SL - 162 and SL - 173); Pet.
7994Ex. 25 (File No. SL - 200).
80015 These distances are based upon the scale shown on Department
8012Exhibit 6, which is more acc urate that Mr. Fosters testimony
8023that the distances between MHWL and SHWL, as surveyed in March
80342002, was about 40 to 60 feet.\. 290 (emphasis supplied) .
80466 / See Pet. Ex. 24 (memo dated April 9, 1999, attached to the
8060analyses for File Nos. SL - 162 an d SL - 173). See also Tr. 68
8076(referencing Mr. Fosters use of a distance of some 42 feet
8087based on historical averages in his review of File No. SL - 222).
81007 / See , e.g. , Pet. Ex. 16 (Table 1), which shows an average
8113erosion rate of - 7.5 ft/yr for monuments R - 34 to R - 39 over the
8130period of 1949 - 68. Accord Tr. 291 - 92.
81408 / See Pet. Ex. 25 (File No. SL - 200).
81519 / See Pet. Ex. 16 (Table 1), which reflects that the erosion
8164rates for monuments R - 34 and R - 35 were - 0.1 and - 0.5 ft/yr,
8181respectively, for the period o f 1930 - 49, as compared to - 10.3
8195and - 6.7 ft/yr, respectively, for the period of 1949 - 68.
820710 / See , e.g. , Pet. Ex. 24; Dept. Ex. 6. Beach Group points out
8221that the structures authorized in File Nos. SL - 162 and SL - 173
8235were found to be landward of the 30 - ye ar erosion projection
8248calculated by the Department. However, the remaining project
8256life was longer when those permit applications were filed -- in
82671999 and 2000, respectively -- and, as a result, the historical
8278erosion rate was applied to a smaller numb er of years in
8290calculating the landward migration of the SHWL in those cases.
8300Indeed, as Mr. Foster pointed out in his review of those
8311applications, the 30 - year erosion projection is time sensitive
8321and must be adjusted in the future for diminishing cre dit for
8333the renourishment project. Pet. Ex. 24 (memorandum dated April
83429, 1999, attached to analyses for File Nos. SL - 162 and SL - 173).
835711 / NAVD is the North American Vertical Datum of 1988. See Fla.
8370Admin. Code R. 61B - 33.002(37). Elevations shown on t he
8381topographic survey for the Property are reflected in relation to
8391the NAVD. See Pet. Ex. 19 ( n ote 11).
840112 / Mr. McNeal opined that the landward toe of the frontal dune
8414was located 20 feet or more landward of the 1978 CCCL. See Tr.
8427203, 207 - 10, 229 - 33. See also Dept. Ex. 24N (highlighted
8440line s ). The opinion that the encroachment was more than 20 feet
8453was in the form of a proffer because it was a new opinion not
8467disclosed by the Department prior to the final hearing. See Tr.
8478205 - 06. The exclusion of M r. McNeals opinion regarding the
8490landward extent of the frontal dune (and the resulting larger
8500encroachment of the project into the dune) is immaterial to Mr.
8511McNeals ultimate opinion that the project fails to meet the
8521applicable regulatory requirements because he understands the
8528Departments rules to prohibit development that encroaches into
8536the frontal dune at all . See Tr. 223.
854513 / The likelihood of continued beach nourishment south of the
8556inlet for the foreseeable future might be appropriate for
8565cons ideration in the context of a request for a variance or
8577waiver under Section 120.542, Florida Statutes. See Pet. Ex. 21
8587(identifying a variance as a possible means for the Project to
8598be approved as it is currently proposed). A variance or waiver
8609must be pursued through a separate proceeding.
8616COPIES FURNISHED :
8619Lea Crandall, Agency Clerk
8623Department of Environmental Protection
8627The Douglas Building, Mail Station 35
86333900 Commonwealth Boulevard
8636Tallahassee, Florida 32399 - 3000
8641Tom Beason, General Counsel
8645Department of Environmental Protection
8649The Douglas Building, Mail Station 35
86553900 Commonwealth Boulevard
8658Tallahassee, Florida 32399 - 3000
8663Michael W. Sole, Secretary
8667Department of Environmental Protection
8671The Douglas Building, Mail Station 35
86773900 Commonwe alth Boulevard
8681Tallahassee, Florida 32399 - 3000
8686William L. Hyde, Esquire
8690Fowler White Boggs Banker, P.A.
8695Post Office box 11240
8699Tallahassee, Florida 32302 - 3240
8704Kelly L. Russell, Esquire
8708Department of Environmental Protection
8712The Douglas Building, Mail S tation 35
87193900 Commonwealth Boulevard
8722Tallahassee, Florida 32399 - 3000
8727NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
8733All parties have the right to submit written exceptions within
874315 days from the date of this Recommended Order. Any exceptions
8754to this Recommend ed Order should be filed with the agency that
8766will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/12/2007
- Proceedings: Department of Environmental Protection`s Response to Petitioners` Exceptions to Recommended Order filed.
- PDF:
- Date: 07/12/2007
- Proceedings: Response of Beach Group Investments, LLC to Exceptions filed by Department of Environmental Protection filed.
- PDF:
- Date: 07/12/2007
- Proceedings: Department of Environmental Protection`s Exceptions to the Recommended Order filed.
- PDF:
- Date: 07/12/2007
- Proceedings: Exceptions to Recommended Order by Petitioner Beach Group Investments, LLC filed.
- PDF:
- Date: 04/19/2007
- Proceedings: Recommended Order (hearing held February 15-16, 2007). CASE CLOSED.
- PDF:
- Date: 04/19/2007
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 03/30/2007
- Proceedings: Proposed Recommended Order of Petitioner Beach Group Investments, LLC filed.
- PDF:
- Date: 03/21/2007
- Proceedings: Order Granting Extension of Time (proposed recommended orders to be filed by March 30, 2007).
- PDF:
- Date: 03/19/2007
- Proceedings: Agreed Motion for Extension of Time to File Porposed Recommended Orders filed.
- Date: 03/01/2007
- Proceedings: Transcript (Volumes 1, 2, 3) filed.
- Date: 02/15/2007
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 02/14/2007
- Proceedings: Letter to DOAH from W. Hyde enclosing exhibits to Joint Pretrial Stipulation filed on February 12, 2007 filed.
- PDF:
- Date: 02/12/2007
- Proceedings: Order Granting Extension of Time (the pre-hearing stipulation to be filed by February 12, 2007).
- PDF:
- Date: 02/09/2007
- Proceedings: Motion for Extension of Time to File Pre-Hearing Stipulation filed.
- PDF:
- Date: 01/10/2007
- Proceedings: Notice of Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Beach Group Investments, LLC filed.
- PDF:
- Date: 01/09/2007
- Proceedings: Notice and Certificate of Service of Respondent DEP`s First Set of Interrogatories to Petitioner Beach Group Investments, LLC filed.
- PDF:
- Date: 01/03/2007
- Proceedings: Amended Notice of Hearing (hearing set for February 15 and 16, 2007; 9:00 a.m.; Tallahassee, FL; amended as to Dates and Location of Hearing).
- PDF:
- Date: 12/19/2006
- Proceedings: Notice of Hearing (hearing set for April 4 and 5, 2007; 10:30 a.m.; Fort Pierce, FL).
- PDF:
- Date: 11/30/2006
- Proceedings: Letter to Judge Canter from W. Hyde regarding failure to renumber the ultimate facts alleged in paragraph 26.
- PDF:
- Date: 11/29/2006
- Proceedings: Department of Environmental Protection`s Amended Response to Initial Order filed.
- PDF:
- Date: 11/28/2006
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
- PDF:
- Date: 11/28/2006
- Proceedings: Notice of Appearance and Substitution of Counsel for the Florida Department of Environmental Protection (filed by K. Russell).
Case Information
- Judge:
- T. KENT WETHERELL, II
- Date Filed:
- 11/21/2006
- Date Assignment:
- 02/09/2007
- Last Docket Entry:
- 07/12/2007
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
Counsels
-
William L. Hyde, Esquire
Address of Record -
Kelly L. Russell, Esquire
Address of Record