07-001020
Amec Civil, Llc vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, January 18, 2008.
Recommended Order on Friday, January 18, 2008.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DEPARTMENT OF TRANSPORTATION, )
12)
13Petitioner, )
15)
16vs. ) Case No. 0 7 - 1020
24)
25AMEC CIVIL, LLC, )
29)
30Respondent. )
32)
33RECOMMENDED ORDER
35Upon due notice, a disputed - fact hearing was convened in
46this cause on September 20, 2007 , in Jacksonville , Florida,
55before Ella Jane P. Davis, a duly - assigned Administrative Law
66Judge of the Division of Administrative Hearings.
73APPEARANCES
74For Petitioner: Erik Fenniman , Esquire
79Department of Transportation
82Haydon Burns Building
85605 Suwannee Street, Mail Station 58
91Tallahassee, Florida 32399
94For Respondent: F. Alan Cummings, Esquire
100S. Elysha Luken, Esquire
104Smith, Currie & Hancock
1081004 DeSoto Park Drive
112Tallahassee, Florida 32301
115STATEMENT OF THE ISSUE
119Whether the Department of Transportation (Petitioner) may
126declare AMEC CIVIL , LLC, (Respondent) non - responsible for 90
136days and ineligible to bid on Department contracts d uring that
147period, based upon Respondent's alleged failure to timely submit
156contract documents and comply with contract requirements on
164Contract Numbers 21349 and 21350 ( Financial Project Numbers
173209600 - 1 - 52 - 01 and 213290 - 1 - 52 - 01 ) .
190PRELIMINARY STATEMENT
192O n January 17, 200 7 , the Department of Transportation (D OT )
205notified AMEC Civil, LLC, of the Departments intent to declare
215AMEC non - responsible for a period of three months based upon
227AMEC 's failure to timely comply with contract requirements on
237DOT Contra ct numbers 21349 and 21350.
244Respondent filed a Petition for Formal Administrative
251Proceedings, and on March 1, 2007, DOT referred the matter to
262the Division of Administrative Hearings.
267The hearing was initially scheduled for May 3, 2007, but
277was twice co ntinued. All interlocutory Motions and Order s
287appear in the case file.
292At the disputed - fact hearing held September 20, 2007, the
303style of this cause was orally amended , as set - out above, to
316reflect the duty to go forward . (TR - 19)
326The parties stipulated that Florida Stat ut es ( 2006 ) apply,
338in particular Sections 337.14, 337.16 , and 337.164.
345At hearing, Florida Administrative Code Rule 14 - 22. 0 141 as
357presented, was officially recognized . AMEC was granted 10 days
367from the close of hearing to object in writin g to any other
380portions of Chapter 14 - 22, as presented at hearing . (TR - 18 - 19)
396No written objection was filed, so Chapter 14 - 22 , has been
408officially recognized for purposes of this Recommended Order.
416Petitioner D OT presented the oral testimony of Terri
425To wers, its Final Estimate s Manager for District II, and B rian
438Blanchard, its Director , Office of Construction. Petitioner's
445Exhibits P - 1 through P - 10 were received in evidence. Respondent
458AMEC presented the oral testimony of Carlos Rosand, AMECs
467Project Manager, and had Exhibits R - 1 through R - 6 admitted in
481evidence .
483A Transcript was filed with the Division on October 10,
4932007. The parties had stipulated to 30 days thereafter for the
504filing of their respective Proposed Recommended Orders. Each
512partys P roposed Recommended Order has been considered in
521preparation of this Recommended Order. 1/
527FINDINGS OF FACT
5301 . Respondent AMEC Civil, LLC, is a Florida corporation
540whose principal business is road and bridge construction.
5482. DOT is the state agency respon sible for entering into
559contracts for the construction , improvements , and maintenance of
567state roads. DOTs legislative authority includes preserving
574the integrity of the public contracting process and determining
583contractors non - responsible. §§ 337.164 and 337.16, Fla. Stat.
593(2006). The point in contention herein is DOTs January 17,
6032007, L etter of I ntent to D eclare AMEC N on - responsible.
6173. This case arises from two separate contracts Respondent
626AMEC entered into with Petitioner DOT to construct the
635i nterchange at Interstate 295 and Interstate 95 in Duval County,
646which construction project stretched over five years.
6534. AMEC has filed no challenge, pursuant to Section
662120.57(3), Florida Statutes, to the specifications of either
670contract. AMEC waived any Section 120.57(1 )( e) issues with
680regard to forms utilized by DOT , but which forms had not been
692adopted as rules in their own right. (TR - 26)
7025. The interchange was comprised of two separate financial
711project numbers with two separate sets of plans, o ne using the
723metric form of computation and the other using the English form
734of computation. The two projects were bid together and were
744combined for purposes of the total construction.
7516. The contract and bid specification package incorporated
759by refer ence the 2000 Edition of DOTs Standard Specifications
769for Road and Bridge Construction, and also included supplemental
778specifications for each element. Therefore, all these items
786became part of the contracts between the parties.
7947. The construction was supposed to be completed in 1461
804days, but suffered significant delays.
8098 . DOT made periodic pay estimates to AMEC on the two
821separate contact numbers . Contract No. 21349, Financial Project
830209600 - 1 - 52 - 01, was the smaller project, in English Units, for
845w hich DOT paid AMEC $11,388,417.98. Contract No. 21350,
856Financial Project 213290 - 1 - 52 - 01 was the larger project, in
870Metric Units, for which DOT paid AMEC $98,816,947.85.
8809 . AMECs two contracts are still open and will be closed
892only when all claims are resolved.
89810 . DOTs contracts provide a mechanism at the end of
909construction projects for a final settling up between the
918parties, recognizing that the periodic payments were only
926estim ates of quantities installed. This mechanism , handled by
935DOTs Fi nal Estimates Office, affords the contractor and the
945Agency an opportunity to make a final identification of the full
956particulars of any payment issues within 90 days of final
966acceptance. This contractual ACCEPTANCE AND FINAL PAYMENT
973process, found at S ection 9 - 9 of the Supplemental Specifications
985of the instant contracts, states, in pertinent part:
993* * *
996. . . The Department will pay the estimate,
1005less any sums that the Department may have
1013deducted or retained under the provisions of
1020the Contract, as soon as practicable after
1027final acceptance of the work , provided the
1034Contractor has met the requirements of (a)
1041through (g) below.
1044If the Contractor fails to furnish all
1051required Contract Documents within 90 days
1057of the Departments offer of final payment
1064or request for refund of overpayment, the
1071Department may suspend the Contractors
1076Certificate of Qualification under the
1081provision of Florida Administrative Code,
108614 - 22.
1089(a) The Contractor has agreed in writing
1096to accept the balance due or refund the
1104o verpayment, as determined by the
1110Department, as full settlement of his
1116account u nder the Contract and of all cla ims
1126in connection therewith, or the Contractor,
1132has through the use of the Qualified
1139Acceptance Letter, accepted the balance due
1145or refunded the overpayment, as determined
1151by the Department, with the stipulation that
1158his acceptance of such payment or the making
1166of such refund does not constitute any bar,
1174admission, or estoppel, or have any effect
1181as to those payments in dispute or the
1189subject of a pending claim between the
1196Contractor and the Department. To receive
1202payment based on a Qualified Acceptance
1208Letter, define in writing the dispute or
1215pending claim with full particular of all
1222items of all issues in dispute, including
1229itemized amounts clai med for all particulars
1236of all items, and submit it as part of the
1246Qualified Acceptance Letter. The Contractor
1251further agrees, by submitting a Qualified
1257Acceptance Letter that any pending or future
1264arbitration claim or suit is limited to
1271those particulars , including the itemi zed
1277amounts, defined in the orig inal Qualified
1284Acceptance Letter, and that he will commence
1291with any arbitration claim or suit within
1298820 calendar days from and after the time of
1307final acceptance of the work and that his
1315failure to fil e a formal claim within this
1324period constitutes his full acceptance of
1330the Engineers final estimate and payment.
1336The overpayment refund check from the
1342Contractor, if required, will be considered
1348a part of any Acceptance Letter executed.
1355* * *
1358(d) The surety on the Contract bond
1365consents, by completion of their portion of
1372the affidavit and surety release subsequent
1378to the Contractors completion of his
1384portion, to final payment to the Contractor
1391and agreed that the making of such payment
1399doe s not relieve the surety of any of its
1409obligations under the bond.
1413* * *
1416(g) The Contractor has submitted the Form
1423FHWA - 47 (formerly known as PR - 47) Record of
1434Materials and Labor on Federal - a id Projects,
1443to the Engineer for transmittal to the FHWA.
1451. . . (Emphasis supplied)
145611 . Section 5 - 12 .2 of the contracts provides , in pertinent
1469part :
14715 - 12.2 Notice of Claim .
14785 - 12.2.1 Claims For Extra Work : . . .
1489On projects with an original Contract amount
1496greater than $3,000,000 within 180 calendar
1504days after final acceptance of the project
1511in accordance with 5 - 11, the Contractor
1519shall submit full and complete documentation
1525as described in 5 - 12.3 . . . .
153512 . By contract, a contractors claim is a pre - requisite
1547to filing a circuit court action, and there is a Claims Office
1559and a complete claims resolution procedure within DOT, including
1568utilization of a three - member Dispute Resolution Board.
157713. Contrary to Contract Specification 9 - 9, AMEC filed
1587suit against DOT prior to final acceptance of the projects.
1597Tha t lawsuit became Duval County Circuit Court Case 03 - CA -
1610005462. Exactly when that lawsuit was instituted is not clear
1620on this record, but the prefix 03 , suggest s it was filed in
16342003, even before AMEC made its first formal claim . (See
1645Finding of Fact 14 .) DOTs Director of the Office of
1656Construction, Brian Blanchard, was not aware of any prior
1665instance of a contractor suing DOT before the issuance of a
1676Qualified Acceptance Letter.
16791 4 . On May 5, 2006, AMEC submitted to DOTs Claims Office,
1692a claim docu ment , addressing both project numbers , allegedly
1701pursuant to the contracts Section 5 - 12 , in relation to the
1713issue of night work . Apparently, AMEC felt DOT had forbidden,
1725or put significant impediments on, AMECs doing night work on
1735the projects in or der to speed up construction by spending more
1747on labor , so th is claim involved the equivalent of time delays
1759as well as overtime costs.
17641 5 . On July 19, 2006, DOT issued to AMEC a single Offer
1778of Final Payment authored by Terri Towers, District II Fina l
1789Estimates Manager, for each of the two financial project s . This
1801letter essentially ask ed what balance AMEC w ould accept to close
1813the contract s . In this letter, DOT acknowledged May 5, 2006, as
1826the da te of final acceptance of work . The effect of DOT s
1841designation of May 5, 2006, as the date of final acceptance was
1853that AMEC then had 180 days from May 5, 2006 (until November 5,
18662006) , to submit any and all claims , pursuant to Specification
18765 - 12 , to DOTs Claims Office, while having 90 days from DOTs
1889O ffer of Final Payment to submit all documents required by the
1901contract and to state a balance AMEC would accept for each
1912project , with all the particulars , pursuant to Supplemental
1920Specification 9 - 9. Under that contract specification, AMEC's
1929f ailure to ti mely challenge the amount(s) offered by DOT would
1941cut AMEC off from claiming more than was offered and constituted
1952AMECs a greement to take the amount DOTs Final Estimates Office
1963had offered on each project . C hallenging the amount offered
1974through timely filing a qualified acceptance with full
1982particulars would not have preclude d payment of any additional
1992amounts AMEC claimed . However, within 90 days of DOTs offer,
2003AMEC was required either to submit a signed regular acceptance
2013of the amount offered for e ach project or to submit a signed
2026qualified acceptance of the amount offered for each project .
2036Whichever type of acceptance AMEC elected to file, the contract
2046required, and DOTs July 19, 2006, Offer of Final Payment letter
2057instructed, that AMECs accepta nce, the surety release, and the
2067FHWA - 47 form must be filed within 90 days of the Offer of Final
2082Payment. It is un - refuted that either a regular acceptance or a
2095qualified acceptance is a contract document .
21031 6 . Ms. Towers acknowledged that the July 19, 2006 , Offer
2115of Final Payment letter incorrectly referred to Article 9 - 9 of
2127the Standard Specifications, when it stated, "P lease be advised
2138that this letter constitutes an offer of final payment and is
2149being made pursuant to an d subject to all requirement s and
2161conditions set out in Article 9 - 9 of the S tandard
2173S pecifications . " However, there is no material difference, for
2183purposes of this case, between that item and Supplemental
2192Specification 9 - 9, ( See DOT Exhibit 10, showing revision dates
2204and contents ) . Moreover, subsequent correspondence clarified
2212which specification was involved, and n o one testified that AMEC
2223was misled or confused as to which contract specification was
2233being invoked by DOT's July 19, 2006 , letter or which
2243specification is applicable to this case.
22491 7 . Ms. Towers testified that the Offer of Final Payment
2261is the last estimate of the total job and is the summary of
2274DOTs whole estimate for each financial project.
22811 8 . DOTs Offer of Final Payment dated July 19, 2006,
2293stated, i n sum, We think that we owe AMEC nothing on No.
2306209600 - 1 - 52 - 01 and that we owe AMEC $752.63 on No. 213290 - 1 - 52 -
232701. DOTs accompanying pay estimates included categories for
2335item descriptions, item numbers, quantities, unit price and the
2344total payment amount to date for each financial project number.
2354The letter , which referenced both project numbers, requested
2362that AMEC , Please sign and return the enclosed Letters of
2372Acceptance to this office (one for each financial project
2381number ) . A form for AMEC to fill out on each project number
2395was attached.
23971 9 . The DOT form s AMEC was requested to sign (one form for
2412each financial project number) were entitled Acceptance on
2420Offer of Final Payment. They permitted AMEC to either accept
2430the final balance payment offered by D OT or to disagree with the
2443amount offered, stating the alternative balance AMEC believed to
2452be due from DOT; stating the additional amount separately , with
2462a breakdown of project number, pay item, and dollar amount; to
2473acknowledge that by accepting payment , AMEC was not subject to
2483any bar or estoppel, or to any effect as to those payments in
2496dispute or which w ere the subject of a pending claim. The form
2509also stated in all capital letters, NOTE: FULL PARTICULARS OF
2519THE ABOVE DISPUTE OR PENDING CLAIM MUST B E SUBMITTED WITH THIS
2531ACCEPTANCE LETTER. ANY OUTSTANDING CONTRACT DOCUMENTS,
2537INCLUDING THE 21 - A, MUST BE RECEIVED BEFORE THIS PAYMENT CAN BE
2550ALLOWED.
255120 . Blank Acceptance on Offer of Final Payment forms , with
2562the respective project number on each of the m , were attached to
2574the Offer of Final Payment letter . Ms . Towers acknowledged that
2586neither the Offer of Final Payment letter , no r the attached
2597forms upon which AMEC was expected to itemize the amounts still
2608in dispute, bore the specific words qualified a cceptance
2617letter , a term used in Supplemental Specification 9 - 9 ( s ee
2631Finding of Fact 10 ) or the term qualified letter of
2642acceptance.
26432 1 . Behind the Acceptance on Offer of Final Payment form
2655for the English project/contract, which the July 19, 2006, O ffer
2666of Final Payment letter requested that AMEC fill - out, were DOTs
2678final audit, or accounting of, the amounts the Final Estimates
2688Office believed were owed by DOT to AMEC for the English
2699project/contract number s . Behind the Acceptance on Offer of
2709Final Payment forms for the Metric project/contract, which the
2718July 19, 2006, Offer of Final Payment letter requested that AMEC
2729fill - out, were DOTs final audit, or accounting of, the amounts
2741the Final Estimates Office believed were owed by DOT to AMEC for
2753the Metric project/contract numbers.
27572 2 . A 21 - A is a surety release form. An FHWA - 47 is a
2779form required by the Federal Highway A dministration for release
2789of funds on a federally - funded project , such as the two projects
2802in the instant case. It is un - refu ted that each of these forms
2817qualifies as a contract document. A blank DOT - approved 21 - A
2830f orm and a blank FHWA - 47 f orm were supposed to be attached to ,
2846and transmitted to AMEC, with DOT's July 19, 2006, Final Offer
2857of Payment letter, but these forms wer e not attached.
28672 3 . On A ugust 16 , 2006, AMEC acknowledged receiving DOTs
2879Offer of Final Payment letter on August 9, 2006 .
28892 4 . On August 31, 2006, DOT responded that , due to mailing
2902problems, the timetable for AMEC to submit the re q uired contract
2914docume nts was adjusted to 90 days from August 7, 2006. This
2926response date for AMEC would have been November 7 , 2006. DOT 's
2938August 31, 2006, letter re - stated that the FHWA - 47 form and the
2953Surety Release (Form 21 - A) also must be submitted with the
2965response.
296625. Having received nothing from AMEC in response to the
2976July 19, 2006 , Offer of Final Payment, the Final Estimates
2986Office, on October 11, 2006, sent AMEC a Notice of Missing or
2998Incomplete Contract Documents, advising that 60 days had elapsed
3007since DOTs Offe r of Final Payment. DOT routinely sends this
3018type of letter to alert contractors that the 90 days from the
3030Offer of Final Payment in which to submit their regular
3040acceptance or qualified acceptance and required contract
3047documents is running out. The lett er to AMEC also specifically
3058named the 21 - A and FHWA - 47 forms. If the time provided by
3073S pecification 9 - 9 runs out without a challenge to the amount
3086offered by DOT, then the contractor loses the opportunity to
3096contest the amount offered. Therefore, when c ontractors receive
3105DOTs Notice of Missing or Incomplete Documents letter, they
3114usually communicate with DOTs Final Estimates Office or
3122otherwise coordinate the submittal of the appropriate missing
3130documents within the remaining 30 days allowed. DOTs
3138Oc tober 11, 2006, letter contained boilerplate language warning
3147AMEC that its certificate of qualification to bid could be
3157suspended for failure to submit the necessary documents.
31652 6 . On October 30, 2006, AMEC submitted to DOTs Claims
3177Office a second claim , again addressing both project numbers,
3186and allegedly pursuant to Contract Sectio n 5 - 12, on all
3198remaining issues besides the night work issue which had been
3208raised on May 5, 2006. (See Finding of Fact 14.)
32182 7 . The supporting documents for AMEC's two c laims
3229constitute 10 large notebooks , observed at final hearing but not
3239admitted in evidence . AMECs Project Engineer testified that
3248t here were also five or more boxes of paper related to impact
3261delay . It is not clear whether these boxes were or were not
3274sent to DOT s Claims Office with the two claims.
328428 . O n November 1, 2006, AMEC sent DOT a letter headed
3297Qualified Acceptance , stating:
3300This will acknowledge receipt of your
3306letter dated August 7, 2006, and a copy of
3315the Departments Offer of Final Payme nt. We
3323agree to accept $752.63 payment as the
3330amount due to us under said contract with
3338the understanding that acceptance of such
3344payment shall not constitute any bar,
3350estoppels, or have any effect as to those
3358payments in dispute or those matters which
3365ar e the subject of a pending claim or
3374lawsuit.
3375The matters which are the subject of
3382pending claims and lawsuits are hereby
3388adopted by referenc e. The lawsuit is styled
3396AMEC C ivil, LLC v. State of Florida,
3404Department of Transportation, Duval County
3409Circuit C ourt, Case No: 03 - CA - 005462. The
3420Department is in possession of the complaint
3427and other pleadings, as well as matters
3434obtained through discovery. The documents
3439are extremely voluminous and too burdensome
3445to attach to this letter. All pending
3452claims have been certified and submitted to
3459the Department. Many of these claims have
3466already gone through the DRB process. The
3473Department is aware of all of AMECs
3480lawsuits and pending claims, in regard to
3487which AMEC reserves all of its rights.
349429 . DRB stands for Dispute Resolution Board . AMEC had
3506provided a copy of the voluminous documentation supporting its
3515two claims (see Finding of Fact 2 7 ) to each of the three members
3530of the DRB as well as to DOTs Claims Office.
354030 . Terri Towers testified that AMECs November 1, 2006,
3550letter to the Final Estimates Office was not sufficient to
3560constitute a Qualified Acceptance Letter, because it incorrectly
3568incorporated a lawsuit and the lawsuits pleadings and
3576referenced DOTs possession of a circuit court complaint, a nd
3586because it did not give a separate dollar amount for each of the
3599two respective financial project number s . Brian Blanchard ,
3608Director of Construction, also testified that AMECs letter was
3617unacceptable for compliance with Supplemental Specification 9 - 9,
3626because the letter did not give the Department a high - level view
3639of the itemized amounts in dollars and time. Both DOT witnesses
3650were concerned because AMEC had provided no breakdown of the
3660dollar amount AMEC was still requesting for each respective
3669proj ect/ contract. The purpose of S pecification 9 - 9, is to cut
3683off any additional requests for payment , claims, amendments to
3692claims, or law s uits that could raise the dollar amount specified
3704in the qualified offer of acceptance . The statement of
3714particulars w ould limit how claims might move money demands
3724around. In short, a qualified acceptance letter is designed to
3734work as a final cut - off of demands , and AMECs submittal was
3747unclear and missing two respective bottom line s .
375631 . Ms. Towers testified that DO T would have accepted from
3768AMEC the filled - in Acceptance on Offer of Final Payment forms
3780she had enclosed with her July 19, 2006, Offer of Final Payment
3792letter (see Finding s of Fact 19 - 21 ); would have accepted a
3806summary of the 10 three ring binders submitt ed with the two
3819claims; probably would have accepted the equivalent information
3827in another format; and would even have accepted AMECs
3836November 1, 2006, Q ualified Acceptance Letter, provided AMEC had
3846submitted the final separate totals (balances) it claime d on
3856each project and the supporting particulars for each amount by
3866project .
386832. Mr. Blanchard understood the concept AMEC was
3876attempting to use in its November 1, 2006, letter of
3886incorporat ion by reference , but stated that the goal of an
3898acceptance o r qualified acceptance letter to the Final Estimates
3908O ffice , as required by 9 - 9, was to avoid overlaps and redundancy
3922and to limit amounts claimed , and accordingly, AMECs vague
3931November 1, 2006, incorporation by reference was unacceptable .
394033 . AMECs Nov ember 1, 2006 , letter referred to lawsuits
3951and claims in the plural . It left Ms. Towers unsure about
3963wh e ther the final amount AMEC was seeking was included in the
3976lawsuit named and further unsure about how the two claims were
3987related to that lawsuit o r possible other lawsuits. Ms. Towers
3998did not consult DOTs l egal staff about the status of any
4010lawsuits, but t here is no certainty that even if she had
4022con sulted DOTs Legal Section conc er n ing the lawsuit
4033specifically named in AMECs November 1, 2006, le tter , she would
4044have gotten a current bottom line dollar amount request ed for
4055final payment on each project .
406134. Ms. Towers knew AMEC had filed claims on May 5, 2006,
4073and October 3 0 , 2006, but she did not take it upon herself to go
4088to DOTs Claims Off ice in the same building and try to analyze
4101all AMECs claim documents, either as they had existed when they
4112had been submitted or as they may have been modified over time.
4124She thought that at least one payment of about $50,000 , was
4136about to be made by DO T upon negotiations that had occurred
4148since May 5, 2006, ( ultimately, $50,000 was actually paid to
4160AMEC in mid - 2007 ) , but how on - going negotiations might have
4174affect ed the balance AMEC was willing accept for the respective
4185projects 90 days past August 7, 2 006 ( November 7, 2006 ) , was not
4200up to Ms. Towers to ferret out. AMEC was required t o clarify
4213th ese amount s in writing and sign - off on them .
422635 . At hearing, AMECs P roject E ngineer testified that
4237each of AMECs two claims constituted all particulars. H e
4247also stated that both claims were covered in the single -
4258referenced lawsuit. He further testified that AMECs May 5,
42672006 , claim clearly demand ed a balance of $18,164,105.00 . This
4280amount is supported by the exhibit related thereto. However,
4289the October 3 0 , 2006, claim was divided into at least four
4301sections , and although each section was totaled, the reader
4310would have to add together the several sections bottom lines to
4321get the total $51,534,615.00 claim amount . Therefore, it
4332appears that only with su ch addition would even the DOT Claims
4344Office be able to discern the fiscal extent of AMECs second
4355claim. Moreover, the two claims AMEC had attempted to
4364incorporate by reference in its November 1, 2006, letter
4373contained at least one cross - over or redundan cy. AMEC
4384calculated a bonus amount into its May 5, 2006, claim and listed
4396the same bonus in the October 3 0 , 2006, claim with a caveat to
4410the effect of DOT, dont pay us a second time if you paid us
4424under the first claim. This bonus redundancy constitut ed a
4434potential five - million dollar overlap of the two claims . AMEC's
4446P roject E ngineer did not know if there were any other
4458duplications within AMECs two claims. Finally, the two claims
4467each combined material concerning both project /contract numbers.
44753 6 . Mr. Blanchard had looked at the two claims only in
4488preparation for hearing , but he had noted a lot of duplication,
4499over - accounting, overlap, and redundancy, and testified that
4509Supplemental Specification 9 - 9 was designed to weed out such
4520problems by req uiring that the contractor list a tot al balance
4532claimed for each project.
45363 7 . Ms. Towers testified that AMEC did not provide the
4548three required contract documents ( a sufficient qualified
4556acceptance lette r, Form 21 - A, and Form FHWA - 47) within 90 days
4571of Au gust 7, 2006 (November 7, 2006).
45793 8 . On November 16, 2006, Ms. Towers notified AMEC that
4591AMECs November 1, 2006 , letter was materially unacceptable,
4599stating that the letter failed to comply with Supplemental
4608Specification 9 - 9 (a) - (g) and :
4617The Qualified Acceptance Letter
4621submitted by AMEC materially failed to meet
4628the express requirements set f orth in
4635Supplemental Specificati on 9 - 9, of the
4643Contract as previously stated. Specifically
4648AMEC requested to have matters which are
4655the subject of pending claims and lawsuits
4662adopt ed by reference. AMEC cited C ase No.
467103 - CA - 005462 and stated that the
4680Department is in possession of the complaint
4687and other pleadings. Are the pending
4693claims referenced by AMEC included in the
4700cited Case No. 03 - CA - 005462? AMEC mu st
4711clearly provide the particulars, regarding
4716dollar amount, all issues and time being
4723requested in order to have the Qualified
4730Acceptance Letter properly processed. In
4735addition, as requested in the Offer of Final
4743Payment letter, AMEC must provide the
4749pro perly executed Form 21 - A (Affidavit as
4758noted in (c) and (d) above) and Form FHWA - 47
4769(as noted in (g) above). (Emphasis supplied)
47763 9 . The emphasized language explicitly stated DOTs
4785problem with reconciling AMECs multiple claims with a single
4794lawsuit as described within AMECs November 1, 2006, Qualified
4803Acceptance letter . The rest of DOTs November 16, 2006 , letter
4814also clearly enumerated the remainder of what was required under
4824Supplemental Specification 9 - 9 (a) through (g), and again listed
4835the missin g 21 - A and FHWA - 47 form s .
484840 . DOT's November 16, 2006 , letter also stated that
4858AMECs failure to comply with 9 - 9, within the 90 days provided
4871in 9 - 9, was sufficient for DOT to invoke Rule 14 - 22.012, to
4886suspend the contractors certificate of qualification , and if
4894the certificate of qualification were already suspended, DOT
4902would invoke Florida Administrative Code Rule 14 - 22.0141(a) and
4912Section 337.16(2)( c ), Florida Statutes, to declare the
4921contractor non - responsible. The language concerning non -
4930responsibi lity was apparently suggested by DOTs Legal Section.
49394 1 . DOT's November 16, 2006, letter closed with the
4950language, As 90 days have already passed , please provide the
4961documentation as requested in the Offer of Final Payment within
497114 days from receipt of this letter so we may process the
4983pending payment . " (Emphasis supplied)
49884 2 . On November 16, 2006, DOT was still seeking 21 - A and
5003FHWA - 47 forms, even though DOT now viewed the balances DOT had
5016offered on July 19, 2006, as uncontested , due to AMEC s fai lure
5029to timely submit a qualified acceptance letter with sufficient
5038particulars.
50394 3 . AMEC did not return the executed 21 - A and FHWA - 47
5055forms within 14 days of DOTs November 16, 2006, letter, so on
5067January 17, 2007, DOT issued its Notice of Intent to D ec lare
5080Non - Responsible, which is the subject of th e instant case. DOT
5093sought to declare AMEC non - responsible for only 90 days , since
5105theirs was a first offense.
51104 4 . DOT's January 17, 2007, letter cited AMECs failure to
5122submit an Acceptance Letter, Form 21 - A, and FHWA - 47 , within 90
5136days of August 7, 2006.
51414 5 . DOTs January 17, 2007, letter stated that the
5152determination of non - responsibility would become "conclusive"
5160if, within 21 days, AMEC did not either submit the required
5171contract documents or reque st an administrative hearing.
51794 6 . The decision to cite AMEC as non - responsible was made
5193by Brian Blanchard, Director of Construction , after consultation
5201with employees of the Office of Construction , D istrict II
5211personnel, the Chief Engineer , and DOT legal staff, but the
5221January 17, 2007 , letter was signed by DOTs Chief Engineer.
52314 7 . O n February 14, 2007, DOT receive d a l etter dated
5246February 13, 2007, from AMEC , entitled O ffer of Final Payment.
5257AMECs February 13, 2007, letter incorporated by referen ce
5266AMECs November 1, 2006, letter as its Qualified Acceptance
5275Letter . Th e letter dated February 13, 2007, attempted to
5286incorporate both claims into the only named lawsuit, but it also
5297refer red to actions both prior to , and since , each of AMECs
5309claims h ad been filed. The letter again stated that As the
5321Department is fully aware, the documentation requested by the
5330Department in the lawsuit is already within the Departments
5339possession, and constitutes several hundred boxes . The Claims
5348themselves, also within the possession of the Department,
5356comprise over ten three - inch ring binders, which included
5366detailed itemization and documentation. (Emphasis added.)
5372This language only further complicated and undermined any
5380attempt to incorporate other materials by reference.
538748 . Attached to AMECs February 13, 2006, letter was a
5398completed FHWA - 47 Form and a completed Form 21 - A. February 1 4 ,
54132006, when the letter was received by DOTs Final Estimates
5423Office, was 1 91 days after the Offer of Final Payment (see
5435Fi nding of Fact 24 , counting from August 7, 2006 ) ; 90 days after
5449DOT s Nov ember 16, 2006 , letter requesting tha t the executed
5461forms be filed within 14 days ; and 2 8 days after DOTs
5473January 17, 2007 , letter gave AMEC another 21 days to submit the
5485forms.
548649 . On February 21, 2007, one of Ms. Towers subordinates
5498sent AMEC a letter acknowledging the February 14, 2007, receipt
5508of AMECs letter . This DOT letter re ferenc ed both contract
5520numbers and both project numbers and request ed that AMEC fill
5531out and submit a n attached two - page Acceptance on Offer of Final
5545Payment form (see Finding s of Fact 19 - 20 ) on Project 213290 - 1 -
556252 - 01. Only the second page of the two - page Acceptance on Offer
5577of Final Payment form for Project 209600 - 1 - 52 - 01 was attached .
5593The letter als o stated that Form 21 - A, which had been received
5607with AMECs February 14, 2007 , letter, was unacceptable because
5616the accompanying power of attorney did not grant the proper
5626authority to execute consents.
563050 . No testimony was presented at hearing concern ing the
5641sufficiency vel non of the 21 - A form submitted by AMEC on
5654February 14, 2006.
56575 1 . T he most common procedure DOT employs when a
5669contractor fails to comply with 9 - 9 or other DOT requirements in
5682the execution of a contract is one in which a pre - qualif ied
5696contractor is declared not qualified, or de - certified. That
5707procedure , technically called a suspension of qualification,
5715renders the previously pre - qualified contractor ineligible to
5724bid on DOT projects.
57285 2 . However, p ursuant to Florida Admini strative Code Rule
574014 - 22.0141, a contractor who wishes to bid for the performance
5752of construction contracts less than $250,000, or to work on any
5764DOT maintenance project is presumed to be a responsible bidder
5774unless DOT determines good cause exists to decl are the
5784contractor non - responsible.
57885 3 . There was credible testimony herein that, in order to
5800prevent a de - certified contractor from subbing or supplying
5810on a DOT contract while disqualified, DOT uniformly follows - up
5821its de - certification to bid with a determination that the de -
5834certified contractor is also non - responsible.
58415 4 . The credible testimony herein also shows that DOT has
5853de - certified at least two contractors who failed to timely
5864submit Letters of Qualified Acceptance after a job was
5873complet ed. Whether or not these particular contractors also
5882were declared non - responsible is not in this record.
589255 . When DOT entered its intent to declare Respondent AMEC
5903non - responsible o n January 17, 2007, AMEC had not been pre -
5917qualified with DOT since May 2 004, and AMEC has not applied for
5930pre - qualification/certification with DOT since May 2004. A
5939settlement agreement regarding resolution of AMECs pre -
5947qualification application from 2004, indicates that DOT agreed
5955that [n]o further action will be taken by the Department in
5966relation to the May 26, 2004, Application for Qualification.
597556 . Since 2004, AMEC also has not attempted to obtain any
5987DOT bid documents for construction projects of less than
5996$250,000 , for which a contractor need not be pre - qualified, and
6009has not attempted to sub or to do maintenance work on any DOT
6022project. AMECs Project E ngineer testified that AMEC has no
6032current intent to apply for jobs with such a low financial
6043return .
604557 . However, absent a de - certification or declaration of
6056AM EC as non - responsible, AMEC remains eligible at any time to
6069apply for certification or to apply for the low financial return
6080work that does not require pre - certification.
608858 . DOTs Construction Director, Brian Blanchard , manages
6096the States 2.5 billion do llar work program, and testified that
6107the integrity of the bidding process depend s upon treating all
6118contractors alike , and therefore , AMEC should be declared non -
6128responsible because it did not meet the contract requirements
6137that all other contractors had to meet, such as the timely
6148filing of its final acceptace figures and the appropriate forms
6158in compliance with a contract specification.
616459 . On or about March 1, 2007, AMEC filed its petition for
6177formal hearing herein, and the case was referred to the Div ision
6189of Administrative Hearings. DOT has not challenged the
6197timeliness of the petition .
6202CONCLUS IONS OF LAW
620660 . The Division of Administrative Hearings has
6214jurisdiction over the parties and subject matter of this
6223proceeding, pursuant to Section 120.569 and Subsection
6230120.57(1), Florida Statutes (200 7 ) .
623761 . The duty to go forward and burden of proof is upon
6250DOT , which seeks to change the status quo . See Department of
6262Transportation v. J.W.C. Co., Inc. , 396 So. 2d 778 (Fla. 1 st DCA
62751981). Pursuant to Section 337.167 (1), de - certification is not
6286equivalent to revocation of a license, and it is concluded here
6297that a declaration of non - responsibility also is not equivalent
6308to revocation of a license. Therefore, the standard of proof
6318herein is by a prep onderance of the evidence .
633062 . Supplemental Specification 9 - 9, quoted in Finding of
6341Fact 10 , is adopted by reference here. Although that
6350specification only provides for de - certification, the statutes
6359and rules permit a declaration of non - responsibility.
636863 . Section 337.16(2), Flor ida Statutes, provides, in
6377pertinent part :
6380[T]he department, for good cause, may
6386determine any contractor not having a
6392certificate of qu alification nonresponsible
6397for a specified period of time or may deny,
6406suspend, or revoke a ny certificate of
6413qualification. Good cause includes, but is
6419not limited to, circumstances in which a
6426contractor or the contractors official
6431representative:
6432* * *
6435(c) Fails to comply with contract
6441requirements, in terms of payment or
6447performance record, or to timely furnish
6453contract documents as required by the
6459contract or by any state o r f ederal statute
6469or regulation ; (E mphasis supplied)
64746 4 . Florida Administrative Code Rule 14 - 22.0141, which
6485implements this statute , provides in pertinent part:
6492(1) Contractors who wish to bid for
6499the performance of construction contracts
6504less than or equal to $250,000, or any
6513maintenance contracts, are presumed to be
6519responsible bidders unless the Department
6524determines that good cause exists to declare
6531the contractor non - responsible, which shall
6538include the following:
6541(a) One of the circumstances specified
6547in Section 337.16(2), Florida Statu t es,
6554occurs ;
6555* * *
6558(e) The contractor failed to comply
6564with contract requirements, or failed to
6570follow Department direction in the execution
6576of the contract ;
6579* * *
6582(j) When the Department determines
6587that any other circumstance constituting
6592good cause under Section 337.16 (2), F.S.,
6599exists.
6600* * *
6603(2) Determination o f Contractor Non -
6610Responsibility . The Contractor will be
6616determined to be non - responsible and
6623ineligible to bid on Department Contracts
6629for a period of time, based on the
6637seriousness of the deficiency.
6641(a) Examples of factors affecting th e
6648seriousness of the deficiency.
66521. Impacts on project schedule,
6657cost, or quality of work;
66622. Unsafe conditions are allowed
6667to exist;
66693. Complaints from the public;
66744. Delay or interference with the
6680bidding process ;
66825. The potential for repetition;
66876. Integrity of the public
6692construction process; and
66957. The effect on the health,
6701safety, and welfare of the
6706public. (Emphasis supplied)
67096 5 . Florida Administrative Code Rule 14 - 22. 012 addresses
6721only de - certifications, but DOT submits that rule is
6731instructional for this non - responsibility case , because the
6740situations and actions are analogous . Therein, s ub - paragraph
6751(b)(1) states that a suspension of 90 days shall occur for pre -
6764qual ified contractors who fail to timely provide contract
6773documents.
67746 6 . Section 337.164, Florida Statutes, states:
6782Recognizing that the preservation of
6787the integrity of the public contracting
6793process of the department is vital to the
6801development of a balance d and efficient
6808transportation system and is a matter of
6815interest to all the people of the state, the
6824Legislature determines and declares that :
6830(1) The procedures of the department
6836for bidding and qualification of bidders on
6843department contracts exist to secure the
6849public benefits of free and open competition
6856and to secure the quality of public works.
6864(2) The opportunity to bid on
6870department contracts or to supply goods or
6877services to the department is a privilege,
6884not a right.
6887* * *
6890To this end, it is the intent of the
6899Legislature to provide sufficiently broad
6904authority to the department to ensure the
6911integrity of its public contacting process.
69176 7 . AMEC submits the following propositions: (1) That
6927AMEC does not meet the definition of contractor under Section
6937337.165, because AMEC has neither bid or applied to bid;
6947(2) That because Rule 14 - 22.0141 addresses only contractors who
6958wish to bid and AMEC does not wish to bid, that rule does not
6972apply to AMEC; (3) That contract S pecif ication 9 - 9 lists only
6986the penalty of de - certification, and accordingly DOT cannot
6996declare AMEC non - responsible; (4) That, in the present
7006situation, the appropriate and required information was timely
7014provided by AMEC, but the information just was not pu t on the
7027appropriate Acceptance on Offer of Final Payment form, provided
7036with DOTs July 19, 2006, Offer of Final Payment (see Findings
7047of Fact 18 and 21) , and that AMECs incorporation by reference,
7058of voluminous documents associated with AMECs two pendi ng
7067claims plus the circuit court case citation, in a separate
7077November 1, 2006, letter labeled Qualified Acceptance, was
7086sufficient to comply with Specification 9 - 9, which uses the term
7098qualified acceptance letter, and which does not use the term
7109acce ptance on offer of final payme nt" or total; and (5) t hat
7123DOTs January 17, 2007 , n otice of intent to declare non -
7135r esponsible was selective enforcement , used by DOT as leverage
7145in the parties circuit court case, because th e portion s of the
7158November 16, 2 006 , and January 17, 2007, letters concerning the
7169non - responsible declaration were drafted by DOTs legal staff,
7179without any precedent .
718368 . AMECs first three argument s ( not a contractor , not
7198a contractor wishing to bid , and exclusivity of contrac t
7210specification penalty ) are without merit. AMEC admits it is
7221the contractor pursuant to the existing interchange contracts
7229between the parties . DOT can not be expected to get inside the
7242head of every corporate contractor to determine if that
7251contrac tor will ever , in the future , wish to bid. Just as a
7265statute must be construed in a reasonable manner so as to avoid
7277absurd results ( see State v. Webb , 398 So. 2d 820 (Fla. 1981) ) ,
7291so must rules. Finally, just because Supplemental Specification
72999 - 9 onl y threatened de - certification as a penalty, DOT is not
7314required to ignore applicable statutes and rules and restrict
7323itself to the contract specifications when it administers State
7332contract s and addresses the contractors it employs. Herein, the
7342quoted sta tute s , rules, and contract terms all apply to AMEC.
735469 . There are two branches to AMECs fourth argument .
7365B oth are related to DOTs a nswers to AMECs interrogatories.
7376Interrogatory No. 1 requested a detailed statement of DOTs
7385basis for its January 17, 2007, declaration of non -
7395responsibility . A s part of a much longer answer, DOT responded
7407 . . . AMEC had not submitted the proper forms or itemized the
7421total amount claimed in a Qualified Acceptance Letter. In
7430response to AMECs Interrogatory No. 4, DOT responded, in
7439sum mary , that it agreed it could not require AMEC to use its
7452Acceptance on Offer of Final Payment " forms ( see Findings of
7463Fact 19 - 21 ), but it did require the substance of the form.
747770. First, there is no significant difference between
7485thes e interrogatory answers and the DOT witnesses testimony at
7495hearing , nor are these interrogatory answers and the testimony
7504contrary to contract specifications or any of the correspondence
7513between the parties. While AMEC is entirely correct that the
7523word total does not appear in Specification 9 - 9, the overall
7536thrust of that specification and of all DOTs correspondence was
7546that AMEC was expected to provide itemized amounts for each
7556project number . These amounts had to be stated so that DOTs
7568Final Esti mates Office could rely upon them as being truly final
7580claim s for each project, much as an insurance company sets up
7592reserves against outstanding accident claims, and so that the
7601final finite amount requested by the contractor could be
7610analyzed by DOT for payment and/or negotiation, ultimately
7618leading to a close - out of the contract file(s). Likewise, even
7630th e truncated portion of DOTs full answer to Interrogatory No.
76411 , clearly does not omit DOTs view that, in addition to
7652itemized amounts, certain mand atory forms were required of
7662AMEC and that AMEC was being held non - responsible for not timely
7675submitting those forms.
767871. Specification 9 - 9 states that a contractor can be de -
7691certified for failure to follow DOTs instructions in the
7700execution of a contrac t. The letters of instruction by DOT were
7712clearly ignored by AMEC.
771672. Ms. Towers July 19, 2006, written instructions were
7726to submit itemized amounts by project/contract numbers . ( See
7736Finding of Fact 18 ) . If anything, the blank forms made these
7749instru ctions even clearer. ( See Finding of Fact 19). Without
7760determin ing whether or not a total on each project/contract was
7771absolutely necessary to comply with 9 - 9, it is concluded that
7783DOT was clearly entitled to seek itemized amounts (the term
7793specificall y used in 9 - 9) by various components within each
7805project number. Each of AMECs two claims commingled components
7814of the two project numbers. The November 1, 2006, AMEC letter
7825did not itemize any amounts. Th erefore, th at letters attempt
7836to incorporate t he two claims, each claim combining the two
7847projects, still did not provide any itemized amounts by
7856project number. That was one material flaw in the November 1,
78672006, and the February 13, 2007, proposed qualified
7875acceptances.
787673 . T he second branch o f AMECs fourth argument is a non -
7891issue. L egally, AMEC waived any Section 120.57(1)(e) issues
7900with regard to whether or not the Acceptance on Offer of Final
7912Payment form constituted a rule or should have been adopted as
7923a rule . ( S ee Preliminary Statemen t) . F actually, this is not a
7939situation of DOT arbitrarily requiring a specific form. DOT did
7949not require that AMEC use its Acceptance on Offer of Final
7960Payment forms. (See Finding of Fact 31 .) In fact, as AMEC is
7973quick to point out, DOTs answer to AME Cs Interrogatory No. 4 ,
7985states that DOT believes it cannot require that contractors use
7995that specific form but can require that contractors submit the
8005substance of the form.
800974. The evidence shows that DOTs Final Estimates Office
8018probably would have acc epted a reasonable incorporation by
8027reference, with minimal supporting documentation on each
8034project, provided AMEC had broken down the disputed amounts into
8044the two separate project numbers. Based on the evidence
8053presented ( see Findings of Fact 35 - 36), D OT might have regretted
8067such leniency , but use of a printed form for the balances
8078claimed was not required. Non - use of a standardized form is not
8091a genuine issue herein. What does matter here is that the
8102claims themselves, even if incorporated by referen ce, did not
8112break the balance claimed by AMEC down by project number, so
8123AMEC did not provide itemized amounts, the term used in
8134Specification 9 - 9.
813875. The remainder of AMECs fourth argument seems to be
8148that it is up to DOT's District II Final Estima tes Office to
8161sift through voluminous papers in other offices of DOT in order
8172to determine what are the particulars of a contractors
8181qualified acceptance, before DOT can close out a contract, and
8191that the contractor is not required to timely submit eith er a
8203regular acceptance or qualified acceptance that meets DOTs
8211instructions by contract or by letter. This interpretation is
8220inconsistent with the clear language of Supplemental
8227Specification 9 - 9 and DOTs Offer of Final Payment.
823776. Supplemental Spe cification 9 - 9 clearly requires that
8247specificity in the particulars of any disputed amount is
8256required from the contractor and that the specificity
8264requirement is designed to prevent any further claims or claim
8274amendments after the disputed amount and su pporting particulars
8283have been presented. AMECs Project Engineers testimony is
8291insuf ficient to show that even with a diligent search upstairs
8302and downstairs and in my ladys chamber , as it were, Ms. Towers
8315could have deciphered AMECs respective balan ces to resolve the
8325two projects . Therefore, DOT could reject AMECs November 1,
83352006, and February 13, 2007, letters as qualified acceptance
8344letters. T he second material flaw in AMECs November 1, 2006,
8355and February 13, 2007 , letters was the lack of part iculars.
83667 7 . Specification 9 - 9 clearly states the contractor must
8378submit either the regular acceptance or the compliant qualified
8387acceptance within 90 days of the Offer of Final Payment. AMEC
8398did not do either. It is un - refuted that the 21 - A and FHWA - 47
8416forms are contract documents that must be submitted under DOT
8426direction ; that direction of when to submit them was repeatedly
8436given by DOT ; and that the dates required by DOT for filing them
8449were repeatedly missed by AMEC.
845478 . It is no t necessary to belabor whether F orm 21 - A, when
8470finally submitted on February 14 , 2007, was compliant. The
8479evidence is clear that AMEC did not timely (by November 7,
84902006 , ) or by any other date instructed by DOT, submit any
8502variety of the 21 - A or FHWA - 47 forms . It is a lso clear that
8520AMEC did not timely submit either a regular or qualified
8530acceptance letter which was materially compliant with
8537Supplemental S pecification 9 - 9 . AMEC thereby render ed itself
8549subject to being declared non - responsible under the cited
8559statutes a nd rules.
856379 . F inally, AMECs fifth argument, that DOTs intent to
8574declare AMEC non - responsible was related to the parties' lawsuit
8585simply because DOTs legal staff contributed to the contents of
8595DOTs November 16, 2006, letter, is pure speculation. No
8604c redible evidence to that effect was presented.
861280. AMECs corollary argument that this was selective
8620prosecution on a theory that " there have been no prior
8630declarations of non - responsibility separate from de -
8639certifications and therefore the non - responsi ble declaration in
8649this case must have been selective prosecution due to the
8659parties' lawsuit, is not supported in fact . While admittedly
8670not identical, there have been similar declarations of non -
8680responsibil ity which are discussed in Findings of Fact 51 - 54 .
8693AMEC's fifth argument also is not supported in law , because the
8704instant case is not, strictly speaking, a case of first
8714impression . Although the declarations as non - responsible in the
8725cases of CPW Enterprises, Inc. d/b/a Cherokee Construction
8733Compa ny v. DOT , DOAH Case No. 03 - 1253 (RO: 9/18/03; FO:
874612/02/03), and Larry Holley Tree and Lawn Spraying, Inc. v. DOT,
8757DOAH Case No. 02 - 3373 (RO: 3/11/03; FO: 4/24/03), were not based
8770on f ailure to submit a Letter of Qualified Acceptance after a
8782job was compl eted, DOT did, therein, successfully declare those
8792contractors non - responsible, without a concurrent de -
8802certification .
8804RECOMMENDATION
8805Based on the foregoing Findings of Facts and Conclusions of
8815Law, it is
8818RECOMMENDED that the Department of Transportat ion enter a
8827final order ratifying its January 17, 2007, declaration of AMEC
8837as non - responsible for 90 days, the 90 days to run from the date
8852of the Final Order .
8857DONE AND ENTERED this 18th day of January , 200 8 , in
8868Tallahassee, Leon County, Florida.
8872S
8873ELLA JANE P. DAVIS
8877Administrative Law Judge
8880Division of Administrative Hearings
8884The DeSoto Building
88871230 Apalachee Parkway
8890Tallahassee, Florida 32399 - 3060
8895(850) 488 - 9675 SUNCOM 278 - 9675
8903Fax Filing (850) 921 - 6847
8909www.do ah.state.fl.us
8911Filed with the Clerk of the
8917Division of Administrative Hearings
8921this 18th day of January , 200 8 .
8929ENDNOTE
89301 / One Proposed Re commended Order was filed three days late,
8942but has been considered, anyway.
8947COPIES FURNISHED:
8949Erik Fenniman, Es quire
8953Department of Transportation
8956Haydon Burns Building
8959605 Suwannee Street, Mail Station 58
8965Tallahassee, Florida 32399
8968F. Alan Cummings, Esquire
8972S. Elysha Luken, Esquire
8976Smith, Currie & Hancock
89801004 DeSoto Park Drive
8984Tallahassee, Florida 32301
8987Jam es C. Myers, Clerk of the Agency Proceedings
8996Department of Transportation
8999Haydon Burns Building, Mail Station 58
9005605 Suwannee Street
9008Tallahassee, Florida 32399 - 0450
9013Alexis M. Yarbrough, General Counsel
9018Department of Transportation
9021Haydon Burns Building, Mail Station 58
9027605 Suwannee Street
9030Tallahassee, Florida 32399 - 0450
9035Stephanie Kopelousos, Secretary
9038Department of Transportation
9041Haydon Burns Building, Mail Station 58
9047605 Suwannee Street
9050Tallahassee, Florida 32399 - 0450
9055NOTICE OF RIGHT TO SUBMIT EXCEP TIONS
9062All parties have the right to submit written exceptions within
907215 days from the date of this Recommended Order. Any exceptions
9083to this Recommended Order should be filed with the agency that
9094will issue the final order in this case.
- Date
- Proceedings
- PDF:
- Date: 01/18/2008
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 01/18/2008
- Proceedings: Recommended Order (hearing held September 20, 2007). CASE CLOSED.
- PDF:
- Date: 11/13/2007
- Proceedings: Letter to Judge Davis from S. Luken regarding the style of the case filed.
- PDF:
- Date: 11/13/2007
- Proceedings: Notice of Filing Proposed Findings of Fact and Conclusions of Law filed.
- Date: 10/10/2007
- Proceedings: Transcript filed.
- Date: 09/20/2007
- Proceedings: CASE STATUS: Hearing Held.
- Date: 08/23/2007
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 08/13/2007
- Proceedings: Respondent`s Opposition to Petitioner`s Third Motion for Continuance filed.
- PDF:
- Date: 08/07/2007
- Proceedings: Notice of Hearing (hearing set for September 20 and 21, 2007; 10:30 a.m.; Jacksonville, FL).
- Date: 08/06/2007
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 08/01/2007
- Proceedings: Defendant`s Response to Petitioner`s Second Request for Production filed.
- PDF:
- Date: 07/16/2007
- Proceedings: Respondent`s Response to Petitioner`s Supplement to Motion to Compel filed.
- PDF:
- Date: 07/02/2007
- Proceedings: Petitioner`s Motion for Extension of Time to Supplement Petitioner`s Motion to Compel filed.
- PDF:
- Date: 06/28/2007
- Proceedings: Respondent`s Notice of Service of Responses to Petitioner`s Second Interrogatories filed.
- PDF:
- Date: 06/27/2007
- Proceedings: Respondent, Department of Transportation`s, Request for Admissions to Petitioner filed.
- PDF:
- Date: 06/22/2007
- Proceedings: Order Cancelling Hearing, Providing for Mutual Response (parties to advise status by July 2, 2007).
- Date: 06/20/2007
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 06/15/2007
- Proceedings: Petitioner`s Notice of Deposition Duces Tecum (of B. Blanchard) filed.
- PDF:
- Date: 06/15/2007
- Proceedings: Petitioner`s Notice of Deposition for Department Corporate Representative filed.
- PDF:
- Date: 04/30/2007
- Proceedings: Order (Respondent is granted five days thereafter to object and file substitute items).
- PDF:
- Date: 04/30/2007
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for June 25 and 26, 2007; 1:00 p.m.; Jacksonville, FL).
- Date: 04/26/2007
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 04/18/2007
- Proceedings: Notice of Service of Petitioner`s Executed Response and Objections to First Interrogatories filed.
- PDF:
- Date: 04/18/2007
- Proceedings: Petitioner`s Response to Respondent`s First Request for Production filed.
- PDF:
- Date: 04/18/2007
- Proceedings: Notice of Service of Petitioner`s Response and Objections to First Interrogatories (Unexecuted) filed.
- PDF:
- Date: 04/18/2007
- Proceedings: Petitioner`s Response to Respondent`s First Request for Admissions filed.
- PDF:
- Date: 04/18/2007
- Proceedings: Respondent`s Opposition to Petitioner`s Motion for Continuance filed.
- PDF:
- Date: 04/12/2007
- Proceedings: Notice of Serving Respondent`s Answers to Plaintiff`s Interrogatories filed.
- PDF:
- Date: 04/03/2007
- Proceedings: Letter to Claudia Llado from E. Fenniman enclosing Exhibit D to Petition for Hearing filed.
- PDF:
- Date: 04/03/2007
- Proceedings: Notice of Serving Respondent`s First Set of Interrogatories filed.
- PDF:
- Date: 04/03/2007
- Proceedings: Respondent`s Department of Transportation First Request for Production of Documents filed.
- PDF:
- Date: 04/03/2007
- Proceedings: Respondent Department of Transportation`s Request for Admissions to Petitioner filed.
- PDF:
- Date: 03/29/2007
- Proceedings: Order (Motion is considered a stipulation and is adopted and ratified by this Order).
- PDF:
- Date: 03/23/2007
- Proceedings: Petitioner`s Unopposed Motion to Reduce Time for Responses to Written Discovery filed.
Case Information
- Judge:
- ELLA JANE P. DAVIS
- Date Filed:
- 03/01/2007
- Date Assignment:
- 03/09/2007
- Last Docket Entry:
- 07/01/2009
- Location:
- Jacksonville, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
Counsels
-
F. Alan Cummings, Esquire
Address of Record -
Erik Fenniman, Esquire
Address of Record -
S. Elysha Luken, Esquire
Address of Record