07-001020 Amec Civil, Llc vs. Department Of Transportation
 Status: Closed
Recommended Order on Friday, January 18, 2008.


View Dockets  
Summary: Petitioner, who failed to comply with specification 9-9, was determined to be "non-responsible," for 90 days.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8DEPARTMENT OF TRANSPORTATION, )

12)

13Petitioner, )

15)

16vs. ) Case No. 0 7 - 1020

24)

25AMEC CIVIL, LLC, )

29)

30Respondent. )

32)

33RECOMMENDED ORDER

35Upon due notice, a disputed - fact hearing was convened in

46this cause on September 20, 2007 , in Jacksonville , Florida,

55before Ella Jane P. Davis, a duly - assigned Administrative Law

66Judge of the Division of Administrative Hearings.

73APPEARANCES

74For Petitioner: Erik Fenniman , Esquire

79Department of Transportation

82Haydon Burns Building

85605 Suwannee Street, Mail Station 58

91Tallahassee, Florida 32399

94For Respondent: F. Alan Cummings, Esquire

100S. Elysha Luken, Esquire

104Smith, Currie & Hancock

1081004 DeSoto Park Drive

112Tallahassee, Florida 32301

115STATEMENT OF THE ISSUE

119Whether the Department of Transportation (Petitioner) may

126declare AMEC CIVIL , LLC, (Respondent) non - responsible for 90

136days and ineligible to bid on Department contracts d uring that

147period, based upon Respondent's alleged failure to timely submit

156contract documents and comply with contract requirements on

164Contract Numbers 21349 and 21350 ( Financial Project Numbers

173209600 - 1 - 52 - 01 and 213290 - 1 - 52 - 01 ) .

190PRELIMINARY STATEMENT

192O n January 17, 200 7 , the Department of Transportation (D OT )

205notified AMEC Civil, LLC, of the Department’s intent to declare

215AMEC non - responsible for a period of three months based upon

227AMEC 's failure to timely comply with contract requirements on

237DOT Contra ct numbers 21349 and 21350.

244Respondent filed a Petition for Formal Administrative

251Proceedings, and on March 1, 2007, DOT referred the matter to

262the Division of Administrative Hearings.

267The hearing was initially scheduled for May 3, 2007, but

277was twice co ntinued. All interlocutory Motions and Order s

287appear in the case file.

292At the disputed - fact hearing held September 20, 2007, the

303style of this cause was orally amended , as set - out above, to

316reflect the duty to go forward . (TR - 19)

326The parties stipulated that Florida Stat ut es ( 2006 ) apply,

338in particular Sections 337.14, 337.16 , and 337.164.

345At hearing, Florida Administrative Code Rule 14 - 22. 0 141 as

357presented, was officially recognized . AMEC was granted 10 days

367from the close of hearing to object in writin g to any other

380portions of Chapter 14 - 22, as presented at hearing . (TR - 18 - 19)

396No written objection was filed, so Chapter 14 - 22 , has been

408officially recognized for purposes of this Recommended Order.

416Petitioner D OT presented the oral testimony of Terri

425To wers, its Final Estimate s Manager for District II, and B rian

438Blanchard, its Director , Office of Construction. Petitioner's

445Exhibits P - 1 through P - 10 were received in evidence. Respondent

458AMEC presented the oral testimony of Carlos Rosand, AMEC’s

467Project Manager, and had Exhibits R - 1 through R - 6 admitted in

481evidence .

483A Transcript was filed with the Division on October 10,

4932007. The parties had stipulated to 30 days thereafter for the

504filing of their respective Proposed Recommended Orders. Each

512party’s P roposed Recommended Order has been considered in

521preparation of this Recommended Order. 1/

527FINDINGS OF FACT

5301 . Respondent AMEC Civil, LLC, is a Florida corporation

540whose principal business is road and bridge construction.

5482. DOT is the state agency respon sible for entering into

559contracts for the construction , improvements , and maintenance of

567state roads. DOT’s legislative authority includes preserving

574the integrity of the public contracting process and determining

583contractors non - responsible. §§ 337.164 and 337.16, Fla. Stat.

593(2006). The point in contention herein is DOT’s January 17,

6032007, L etter of I ntent to D eclare AMEC N on - responsible.

6173. This case arises from two separate contracts Respondent

626AMEC entered into with Petitioner DOT to construct the

635i nterchange at Interstate 295 and Interstate 95 in Duval County,

646which construction project stretched over five years.

6534. AMEC has filed no challenge, pursuant to Section

662120.57(3), Florida Statutes, to the specifications of either

670contract. AMEC waived any Section 120.57(1 )( e) issues with

680regard to forms utilized by DOT , but which forms had not been

692adopted as rules in their own right. (TR - 26)

7025. The interchange was comprised of two separate financial

711project numbers with two separate sets of plans, o ne using the

723metric form of computation and the other using the English form

734of computation. The two projects were bid together and were

744combined for purposes of the total construction.

7516. The contract and bid specification package incorporated

759by refer ence the 2000 Edition of DOT’s Standard Specifications

769for Road and Bridge Construction, and also included supplemental

778specifications for each element. Therefore, all these items

786became part of the contracts between the parties.

7947. The construction was supposed to be completed in 1461

804days, but suffered significant delays.

8098 . DOT made periodic pay estimates to AMEC on the two

821separate contact numbers . Contract No. 21349, Financial Project

830209600 - 1 - 52 - 01, was the smaller project, in English Units, for

845w hich DOT paid AMEC $11,388,417.98. Contract No. 21350,

856Financial Project 213290 - 1 - 52 - 01 was the larger project, in

870Metric Units, for which DOT paid AMEC $98,816,947.85.

8809 . AMEC’s two contracts are still open and will be closed

892only when all claims are resolved.

89810 . DOT’s contracts provide a mechanism at the end of

909construction projects for a final “settling up” between the

918parties, recognizing that the periodic payments were only

926estim ates of quantities installed. This mechanism , handled by

935DOT’s Fi nal Estimates Office, affords the contractor and the

945Agency an opportunity to make a final identification of the full

956particulars of any payment issues within 90 days of final

966acceptance. This contractual “ACCEPTANCE AND FINAL PAYMENT”

973process, found at S ection 9 - 9 of the Supplemental Specifications

985of the instant contracts, states, in pertinent part:

993* * *

996. . . The Department will pay the estimate,

1005less any sums that the Department may have

1013deducted or retained under the provisions of

1020the Contract, as soon as practicable after

1027final acceptance of the work , provided the

1034Contractor has met the requirements of (a)

1041through (g) below.

1044If the Contractor fails to furnish all

1051required Contract Documents within 90 days

1057of the Department’s offer of final payment

1064or request for refund of overpayment, the

1071Department may suspend the Contractor’s

1076Certificate of Qualification under the

1081provision of Florida Administrative Code,

108614 - 22.

1089(a) The Contractor has agreed in writing

1096to accept the balance due or refund the

1104o verpayment, as determined by the

1110Department, as full settlement of his

1116account u nder the Contract and of all cla ims

1126in connection therewith, or the Contractor,

1132has through the use of the Qualified

1139Acceptance Letter, accepted the balance due

1145or refunded the overpayment, as determined

1151by the Department, with the stipulation that

1158his acceptance of such payment or the making

1166of such refund does not constitute any bar,

1174admission, or estoppel, or have any effect

1181as to those payments in dispute or the

1189subject of a pending claim between the

1196Contractor and the Department. To receive

1202payment based on a Qualified Acceptance

1208Letter, define in writing the dispute or

1215pending claim with full particular of all

1222items of all issues in dispute, including

1229itemized amounts clai med for all particulars

1236of all items, and submit it as part of the

1246Qualified Acceptance Letter. The Contractor

1251further agrees, by submitting a Qualified

1257Acceptance Letter that any pending or future

1264arbitration claim or suit is limited to

1271those particulars , including the itemi zed

1277amounts, defined in the orig inal Qualified

1284Acceptance Letter, and that he will commence

1291with any arbitration claim or suit within

1298820 calendar days from and after the time of

1307final acceptance of the work and that his

1315failure to fil e a formal claim within this

1324period constitutes his full acceptance of

1330the Engineer’s final estimate and payment.

1336The overpayment refund check from the

1342Contractor, if required, will be considered

1348a part of any Acceptance Letter executed.

1355* * *

1358(d) The surety on the Contract bond

1365consents, by completion of their portion of

1372the affidavit and surety release subsequent

1378to the Contractor’s completion of his

1384portion, to final payment to the Contractor

1391and agreed that the making of such payment

1399doe s not relieve the surety of any of its

1409obligations under the bond.

1413* * *

1416(g) The Contractor has submitted the Form

1423FHWA - 47 (formerly known as PR - 47) Record of

1434Materials and Labor on Federal - a id Projects,

1443to the Engineer for transmittal to the FHWA.

1451. . . (Emphasis supplied)

145611 . Section 5 - 12 .2 of the contracts provides , in pertinent

1469part :

14715 - 12.2 Notice of Claim .

14785 - 12.2.1 Claims For Extra Work : . . .

1489On projects with an original Contract amount

1496greater than $3,000,000 within 180 calendar

1504days after final acceptance of the project

1511in accordance with 5 - 11, the Contractor

1519shall submit full and complete documentation

1525as described in 5 - 12.3 . . . .

153512 . By contract, a contractor’s claim is a pre - requisite

1547to filing a circuit court action, and there is a Claims Office

1559and a complete claims resolution procedure within DOT, including

1568utilization of a three - member Dispute Resolution Board.

157713. Contrary to Contract Specification 9 - 9, AMEC filed

1587suit against DOT prior to final acceptance of the projects.

1597Tha t lawsuit became Duval County Circuit Court Case 03 - CA -

1610005462. Exactly when that lawsuit was instituted is not clear

1620on this record, but the prefix “03 , ” suggest s it was filed in

16342003, even before AMEC made its first formal claim . (See

1645Finding of Fact 14 .) DOT’s Director of the Office of

1656Construction, Brian Blanchard, was not aware of any prior

1665instance of a contractor suing DOT before the issuance of a

1676Qualified Acceptance Letter.

16791 4 . On May 5, 2006, AMEC submitted to DOT’s Claims Office,

1692a claim docu ment , addressing both project numbers , allegedly

1701pursuant to the contracts’ Section 5 - 12 , in relation to the

1713issue of “night work . ” Apparently, AMEC felt DOT had forbidden,

1725or put significant impediments on, AMEC’s doing “night work” on

1735the projects in or der to speed up construction by spending more

1747on labor , so th is claim involved the equivalent of time delays

1759as well as overtime costs.

17641 5 . On July 19, 2006, DOT issued to AMEC a single “Offer

1778of Final Payment” authored by Terri Towers, District II Fina l

1789Estimates Manager, for each of the two financial project s . This

1801letter essentially ask ed what balance AMEC w ould accept to close

1813the contract s . In this letter, DOT acknowledged May 5, 2006, as

1826the da te of “final acceptance of work . ” The effect of DOT’ s

1841designation of May 5, 2006, as the date of final acceptance was

1853that AMEC then had 180 days from May 5, 2006 (until November 5,

18662006) , to submit any and all claims , pursuant to Specification

18765 - 12 , to DOT’s Claims Office, while having 90 days from DOT’s

1889O ffer of Final Payment to submit all documents required by the

1901contract and to state a balance AMEC would accept for each

1912project , with all the particulars , pursuant to Supplemental

1920Specification 9 - 9. Under that contract specification, AMEC's

1929f ailure to ti mely challenge the amount(s) offered by DOT would

1941cut AMEC off from claiming more than was offered and constituted

1952AMEC’s a greement to take the amount DOT’s Final Estimates Office

1963had offered on each project . C hallenging the amount offered

1974through timely filing a qualified acceptance with full

1982particulars would not have preclude d payment of any additional

1992amounts AMEC claimed . However, within 90 days of DOT’s offer,

2003AMEC was required either to submit a signed regular acceptance

2013of the amount offered for e ach project or to submit a signed

2026qualified acceptance of the amount offered for each project .

2036Whichever type of acceptance AMEC elected to file, the contract

2046required, and DOT’s July 19, 2006, Offer of Final Payment letter

2057instructed, that AMEC’s accepta nce, the surety release, and the

2067FHWA - 47 form must be filed within 90 days of the Offer of Final

2082Payment. It is un - refuted that either a regular acceptance or a

2095qualified acceptance is a “contract document . ”

21031 6 . Ms. Towers acknowledged that the July 19, 2006 , Offer

2115of Final Payment letter incorrectly referred to “Article 9 - 9 of

2127the Standard Specifications,” when it stated, "P lease be advised

2138that this letter constitutes an offer of final payment and is

2149being made pursuant to an d subject to all requirement s and

2161conditions set out in Article 9 - 9 of the S tandard

2173S pecifications . " However, there is no material difference, for

2183purposes of this case, between that item and Supplemental

2192Specification 9 - 9, ( See DOT Exhibit 10, showing revision dates

2204and contents ) . Moreover, subsequent correspondence clarified

2212which specification was involved, and n o one testified that AMEC

2223was misled or confused as to which contract specification was

2233being invoked by DOT's July 19, 2006 , letter or which

2243specification is applicable to this case.

22491 7 . Ms. Towers testified that the Offer of Final Payment

2261is the last estimate of the total job and is the summary of

2274DOT’s whole estimate for each financial project.

22811 8 . DOT’s Offer of Final Payment dated July 19, 2006,

2293stated, i n sum, “We think that we owe AMEC nothing on No.

2306209600 - 1 - 52 - 01 and that we owe AMEC $752.63 on No. 213290 - 1 - 52 -

232701.” DOT’s accompanying pay estimates included categories for

2335item descriptions, item numbers, quantities, unit price and the

2344total payment amount to date for each financial project number.

2354The letter , which referenced both project numbers, requested

2362that AMEC , “Please sign and return the enclosed Letters of

2372Acceptance to this office (one for each financial project

2381number ) .” A form for AMEC to fill out on each project number

2395was attached.

23971 9 . The DOT form s AMEC was requested to sign (one form for

2412each financial project number) were entitled “Acceptance on

2420Offer of Final Payment.” They permitted AMEC to either accept

2430the final balance payment offered by D OT or to disagree with the

2443amount offered, stating the alternative balance AMEC believed to

2452be due from DOT; stating the additional amount separately , with

2462a breakdown of project number, pay item, and dollar amount; to

2473acknowledge that by accepting payment , AMEC was not subject to

2483any bar or estoppel, or to any effect as to those payments in

2496dispute or which w ere the subject of a pending claim. The form

2509also stated in all capital letters, “NOTE: FULL PARTICULARS OF

2519THE ABOVE DISPUTE OR PENDING CLAIM MUST B E SUBMITTED WITH THIS

2531ACCEPTANCE LETTER. ANY OUTSTANDING CONTRACT DOCUMENTS,

2537INCLUDING THE 21 - A, MUST BE RECEIVED BEFORE THIS PAYMENT CAN BE

2550ALLOWED.”

255120 . Blank Acceptance on Offer of Final Payment forms , with

2562the respective project number on each of the m , were attached to

2574the Offer of Final Payment letter . Ms . Towers acknowledged that

2586neither the Offer of Final Payment letter , no r the attached

2597forms upon which AMEC was expected to itemize the amounts still

2608in dispute, bore the specific words “qualified a cceptance

2617letter , ” a term used in Supplemental Specification 9 - 9 ( s ee

2631Finding of Fact 10 ) or the term “qualified letter of

2642acceptance.”

26432 1 . Behind the Acceptance on Offer of Final Payment form

2655for the English project/contract, which the July 19, 2006, O ffer

2666of Final Payment letter requested that AMEC fill - out, were DOT’s

2678final audit, or accounting of, the amounts the Final Estimates

2688Office believed were owed by DOT to AMEC for the English

2699project/contract number s . Behind the Acceptance on Offer of

2709Final Payment forms for the Metric project/contract, which the

2718July 19, 2006, Offer of Final Payment letter requested that AMEC

2729fill - out, were DOT’s final audit, or accounting of, the amounts

2741the Final Estimates Office believed were owed by DOT to AMEC for

2753the Metric project/contract numbers.

27572 2 . A “ 21 - A ” is a surety release form. An “ FHWA - 47 ” is a

2779form required by the Federal Highway A dministration for release

2789of funds on a federally - funded project , such as the two projects

2802in the instant case. It is un - refu ted that each of these forms

2817qualifies as a “contract document.” A blank DOT - approved 21 - A

2830f orm and a blank FHWA - 47 f orm were supposed to be attached to ,

2846and transmitted to AMEC, with DOT's July 19, 2006, Final Offer

2857of Payment letter, but these forms wer e not attached.

28672 3 . On A ugust 16 , 2006, AMEC acknowledged receiving DOT’s

2879Offer of Final Payment letter on August 9, 2006 .

28892 4 . On August 31, 2006, DOT responded that , due to mailing

2902problems, the timetable for AMEC to submit the re q uired contract

2914docume nts was adjusted to 90 days from August 7, 2006. This

2926response date for AMEC would have been November 7 , 2006. DOT 's

2938August 31, 2006, letter re - stated that the FHWA - 47 form and the

2953Surety Release (Form 21 - A) also must be submitted with the

2965response.

296625. Having received nothing from AMEC in response to the

2976July 19, 2006 , Offer of Final Payment, the Final Estimates

2986Office, on October 11, 2006, sent AMEC a Notice of Missing or

2998Incomplete Contract Documents, advising that 60 days had elapsed

3007since DOT’s Offe r of Final Payment. DOT routinely sends this

3018type of letter to alert contractors that the 90 days from the

3030Offer of Final Payment in which to submit their regular

3040acceptance or qualified acceptance and required contract

3047documents is running out. The lett er to AMEC also specifically

3058named the 21 - A and FHWA - 47 forms. If the time provided by

3073S pecification 9 - 9 runs out without a challenge to the amount

3086offered by DOT, then the contractor loses the opportunity to

3096contest the amount offered. Therefore, when c ontractors receive

3105DOT’s Notice of Missing or Incomplete Documents letter, they

3114usually communicate with DOT’s Final Estimates Office or

3122otherwise coordinate the submittal of the appropriate missing

3130documents within the remaining 30 days allowed. DOT’s

3138Oc tober 11, 2006, letter contained boilerplate language warning

3147AMEC that its certificate of qualification to bid could be

3157suspended for failure to submit the necessary documents.

31652 6 . On October 30, 2006, AMEC submitted to DOT’s Claims

3177Office a second claim , again addressing both project numbers,

3186and allegedly pursuant to Contract Sectio n 5 - 12, on all

3198remaining issues besides the night work issue which had been

3208raised on May 5, 2006. (See Finding of Fact 14.)

32182 7 . The supporting documents for AMEC's two c laims

3229constitute 10 large notebooks , observed at final hearing but not

3239admitted in evidence . AMEC’s Project Engineer testified that

3248t here were also five or more boxes of paper related to impact

3261delay . It is not clear whether these boxes were or were not

3274sent to DOT ’s Claims Office with the two claims.

328428 . O n November 1, 2006, AMEC sent DOT a letter headed

3297“Qualified Acceptance” , stating:

3300This will acknowledge receipt of your

3306letter dated August 7, 2006, and a copy of

3315the Department’s Offer of Final Payme nt. We

3323agree to accept $752.63 payment as the

3330amount due to us under said contract with

3338the understanding that acceptance of such

3344payment shall not constitute any bar,

3350estoppels, or have any effect as to those

3358payments in dispute or those matters which

3365ar e the subject of a pending claim or

3374lawsuit.

3375The matters which are the subject of

3382pending claims and lawsuits are hereby

3388adopted by referenc e. The lawsuit is styled

3396AMEC C ivil, LLC v. State of Florida,

3404Department of Transportation, Duval County

3409Circuit C ourt, Case No: 03 - CA - 005462. The

3420Department is in possession of the complaint

3427and other pleadings, as well as matters

3434obtained through discovery. The documents

3439are extremely voluminous and too burdensome

3445to attach to this letter. All pending

3452claims have been certified and submitted to

3459the Department. Many of these claims have

3466already gone through the DRB process. The

3473Department is aware of all of AMEC’s

3480lawsuits and pending claims, in regard to

3487which AMEC reserves all of its rights.

349429 . “DRB” stands for “Dispute Resolution Board . ” AMEC had

3506provided a copy of the voluminous documentation supporting its

3515two claims (see Finding of Fact 2 7 ) to each of the three members

3530of the DRB as well as to DOT’s Claims Office.

354030 . Terri Towers testified that AMEC’s November 1, 2006,

3550letter to the Final Estimates Office was not sufficient to

3560constitute a Qualified Acceptance Letter, because it incorrectly

3568incorporated a lawsuit and the lawsuit’s pleadings and

3576referenced DOT’s possession of a circuit court complaint, a nd

3586because it did not give a separate dollar amount for each of the

3599two respective financial project number s . Brian Blanchard ,

3608Director of Construction, also testified that AMEC’s letter was

3617unacceptable for compliance with Supplemental Specification 9 - 9,

3626because the letter did not give the Department a high - level view

3639of the itemized amounts in dollars and time. Both DOT witnesses

3650were concerned because AMEC had provided no breakdown of the

3660dollar amount AMEC was still requesting for each respective

3669proj ect/ contract. The purpose of S pecification 9 - 9, is to cut

3683off any additional requests for payment , claims, amendments to

3692claims, or law s uits that could raise the dollar amount specified

3704in the qualified offer of acceptance . The statement of

3714particulars w ould limit how claims might move money demands

3724around. In short, a qualified acceptance letter is designed to

3734work as a final cut - off of demands , and AMEC’s submittal was

3747unclear and missing two respective “bottom line s .”

375631 . Ms. Towers testified that DO T would have accepted from

3768AMEC the filled - in Acceptance on Offer of Final Payment forms

3780she had enclosed with her July 19, 2006, Offer of Final Payment

3792letter (see Finding s of Fact 19 - 21 ); would have accepted a

3806summary of the 10 three – ring binders submitt ed with the two

3819claims; probably would have accepted the equivalent information

3827in another format; and would even have accepted AMEC’s

3836November 1, 2006, Q ualified Acceptance Letter, provided AMEC had

3846submitted the final separate totals (balances) it claime d on

3856each project and the supporting particulars for each amount by

3866project .

386832. Mr. Blanchard understood the concept AMEC was

3876attempting to use in its November 1, 2006, letter of

3886“incorporat ion by reference , ” but stated that the goal of an

3898acceptance o r qualified acceptance letter to the Final Estimates

3908O ffice , as required by 9 - 9, was to avoid overlaps and redundancy

3922and to limit amounts claimed , and accordingly, AMEC’s vague

3931November 1, 2006, incorporation by reference was unacceptable .

394033 . AMEC’s Nov ember 1, 2006 , letter referred to “lawsuits”

3951and “claims’ in the plural . It left Ms. Towers unsure about

3963wh e ther the final amount AMEC was seeking was included in the

3976lawsuit named and further unsure about how the two claims were

3987related to that lawsuit o r possible other lawsuits. Ms. Towers

3998did not consult DOT’s l egal staff about the status of any

4010lawsuits, but t here is no certainty that even if she had

4022con sulted DOT’s Legal Section conc er n ing the lawsuit

4033specifically named in AMEC’s November 1, 2006, le tter , she would

4044have gotten a current “bottom line” dollar amount request ed for

4055final payment on each project .

406134. Ms. Towers knew AMEC had filed claims on May 5, 2006,

4073and October 3 0 , 2006, but she did not take it upon herself to go

4088to DOT’s Claims Off ice in the same building and try to analyze

4101all AMEC’s claim documents, either as they had existed when they

4112had been submitted or as they may have been modified over time.

4124She thought that at least one payment of about $50,000 , was

4136about to be made by DO T upon negotiations that had occurred

4148since May 5, 2006, ( ultimately, $50,000 was actually paid to

4160AMEC in mid - 2007 ) , but how on - going negotiations might have

4174affect ed the balance AMEC was willing accept for the respective

4185projects 90 days past August 7, 2 006 ( November 7, 2006 ) , was not

4200up to Ms. Towers to ferret out. AMEC was required t o clarify

4213th ese amount s in writing and sign - off on them .

422635 . At hearing, AMEC’s P roject E ngineer testified that

4237each of AMEC’s two claims constituted “all particulars.” H e

4247also stated that both claims were covered in the single -

4258referenced lawsuit. He further testified that AMEC’s May 5,

42672006 , claim clearly demand ed a balance of $18,164,105.00 . This

4280amount is supported by the exhibit related thereto. However,

4289the October 3 0 , 2006, claim was divided into at least four

4301sections , and although each section was totaled, the reader

4310would have to add together the several sections’ bottom lines to

4321get the total $51,534,615.00 claim amount . Therefore, it

4332appears that only with su ch addition would even the DOT Claims

4344Office be able to discern the fiscal extent of AMEC’s second

4355claim. Moreover, the two claims AMEC had attempted to

4364incorporate by reference in its November 1, 2006, letter

4373contained at least one cross - over or redundan cy. AMEC

4384calculated a bonus amount into its May 5, 2006, claim and listed

4396the same bonus in the October 3 0 , 2006, claim with a caveat to

4410the effect of “DOT, don’t pay us a second time if you paid us

4424under the first claim.” This bonus redundancy constitut ed a

4434potential five - million dollar overlap of the two claims . AMEC's

4446P roject E ngineer did not know if there were any other

4458duplications within AMEC’s two claims. Finally, the two claims

4467each combined material concerning both project /contract numbers.

44753 6 . Mr. Blanchard had looked at the two claims only in

4488preparation for hearing , but he had noted a lot of duplication,

4499“over - accounting,” overlap, and redundancy, and testified that

4509Supplemental Specification 9 - 9 was designed to weed out such

4520problems by req uiring that the contractor list a tot al balance

4532claimed for each project.

45363 7 . Ms. Towers testified that AMEC did not provide the

4548three required contract documents ( a sufficient qualified

4556acceptance lette r, Form 21 - A, and Form FHWA - 47) within 90 days

4571of Au gust 7, 2006 (November 7, 2006).

45793 8 . On November 16, 2006, Ms. Towers notified AMEC that

4591AMEC’s November 1, 2006 , letter was materially unacceptable,

4599stating that the letter failed to comply with Supplemental

4608Specification 9 - 9 (a) - (g) and :

4617The Qualified Acceptance Letter

4621submitted by AMEC materially failed to meet

4628the express requirements set f orth in

4635Supplemental Specificati on 9 - 9, of the

4643Contract as previously stated. Specifically

4648AMEC requested to have “matters which are

4655the subject of pending claims and lawsuits

4662adopt ed by reference.” AMEC cited “C ase No.

467103 - CA - 005462” and stated that “the

4680Department is in possession of the complaint

4687and other pleadings.” Are the pending

4693claims referenced by AMEC included in the

4700cited Case No. 03 - CA - 005462? AMEC mu st

4711clearly provide the particulars, regarding

4716dollar amount, all issues and time being

4723requested in order to have the Qualified

4730Acceptance Letter properly processed. In

4735addition, as requested in the Offer of Final

4743Payment letter, AMEC must provide the

4749pro perly executed Form 21 - A (Affidavit as

4758noted in (c) and (d) above) and Form FHWA - 47

4769(as noted in (g) above). (Emphasis supplied)

47763 9 . The emphasized language explicitly stated DOT’s

4785problem with reconciling AMEC’s multiple claims with a single

4794lawsuit as described within AMEC’s November 1, 2006, Qualified

4803Acceptance letter . The rest of DOT’s November 16, 2006 , letter

4814also clearly enumerated the remainder of what was required under

4824Supplemental Specification 9 - 9 (a) through (g), and again listed

4835the missin g 21 - A and FHWA - 47 form s .

484840 . DOT's November 16, 2006 , letter also stated that

4858AMEC’s failure to comply with 9 - 9, within the 90 days provided

4871in 9 - 9, was sufficient for DOT to invoke Rule 14 - 22.012, to

4886suspend the contractor’s certificate of qualification , and if

4894the certificate of qualification were already suspended, DOT

4902would invoke Florida Administrative Code Rule 14 - 22.0141(a) and

4912Section 337.16(2)( c ), Florida Statutes, to declare the

4921contractor non - responsible. The language concerning non -

4930responsibi lity was apparently suggested by DOT’s Legal Section.

49394 1 . DOT's November 16, 2006, letter closed with the

4950language, “ As 90 days have already passed , please provide the

4961documentation as requested in the Offer of Final Payment within

497114 days from receipt of this letter so we may process the

4983pending payment . " (Emphasis supplied)

49884 2 . On November 16, 2006, DOT was still seeking 21 - A and

5003FHWA - 47 forms, even though DOT now viewed the balances DOT had

5016offered on July 19, 2006, as uncontested , due to AMEC ’s fai lure

5029to timely submit a qualified acceptance letter with sufficient

5038particulars.

50394 3 . AMEC did not return the executed 21 - A and FHWA - 47

5055forms within 14 days of DOT’s November 16, 2006, letter, so on

5067January 17, 2007, DOT issued its Notice of Intent to D ec lare

5080Non - Responsible, which is the subject of th e instant case. DOT

5093sought to declare AMEC non - responsible for only 90 days , since

5105theirs was a first offense.

51104 4 . DOT's January 17, 2007, letter cited AMEC’s failure to

5122submit an Acceptance Letter, Form 21 - A, and FHWA - 47 , within 90

5136days of August 7, 2006.

51414 5 . DOT’s January 17, 2007, letter stated that the

5152determination of non - responsibility would become "conclusive"

5160if, within 21 days, AMEC did not either submit the required

5171contract documents or reque st an administrative hearing.

51794 6 . The decision to cite AMEC as non - responsible was made

5193by Brian Blanchard, Director of Construction , after consultation

5201with employees of the Office of Construction , D istrict II

5211personnel, the Chief Engineer , and DOT legal staff, but the

5221January 17, 2007 , letter was signed by DOT’s Chief Engineer.

52314 7 . O n February 14, 2007, DOT receive d a l etter dated

5246February 13, 2007, from AMEC , entitled “O ffer of Final Payment.”

5257AMEC’s February 13, 2007, letter incorporated by referen ce

5266AMEC’s November 1, 2006, letter as its Qualified Acceptance

5275Letter . Th e letter dated February 13, 2007, attempted to

5286incorporate both claims into the only named lawsuit, but it also

5297refer red to actions both prior to , and since , each of AMEC’s

5309claims h ad been filed. The letter again stated that “As the

5321Department is fully aware, the documentation requested by the

5330Department in the lawsuit is already within the Department’s

5339possession, and constitutes several hundred boxes . The Claims

5348themselves, also within the possession of the Department,

5356comprise over ten three - inch ring binders, which included

5366detailed itemization and documentation.” (Emphasis added.)

5372This language only further complicated and undermined any

5380attempt to incorporate other materials by reference.

538748 . Attached to AMEC’s February 13, 2006, letter was a

5398completed FHWA - 47 Form and a completed Form 21 - A. February 1 4 ,

54132006, when the letter was received by DOT’s Final Estimates

5423Office, was 1 91 days after the Offer of Final Payment (see

5435Fi nding of Fact 24 , counting from August 7, 2006 ) ; 90 days after

5449DOT’ s Nov ember 16, 2006 , letter requesting tha t the executed

5461forms be filed within 14 days ; and 2 8 days after DOT’s

5473January 17, 2007 , letter gave AMEC another 21 days to submit the

5485forms.

548649 . On February 21, 2007, one of Ms. Towers ’ subordinates

5498sent AMEC a letter acknowledging the February 14, 2007, receipt

5508of AMEC’s letter . This DOT letter re ferenc ed both contract

5520numbers and both project numbers and request ed that AMEC fill

5531out and submit a n attached two - page Acceptance on Offer of Final

5545Payment form (see Finding s of Fact 19 - 20 ) on Project 213290 - 1 -

556252 - 01. Only the second page of the two - page Acceptance on Offer

5577of Final Payment form for Project 209600 - 1 - 52 - 01 was attached .

5593The letter als o stated that Form 21 - A, which had been received

5607with AMEC’s February 14, 2007 , letter, was unacceptable because

5616the accompanying power of attorney did not grant the proper

5626authority to execute consents.

563050 . No testimony was presented at hearing concern ing the

5641sufficiency vel non of the 21 - A form submitted by AMEC on

5654February 14, 2006.

56575 1 . T he most common procedure DOT employs when a

5669contractor fails to comply with 9 - 9 or other DOT requirements in

5682the execution of a contract is one in which a pre - qualif ied

5696contractor is declared “not qualified,” or “de - certified.” That

5707procedure , technically called a “suspension of qualification,”

5715renders the previously pre - qualified contractor ineligible to

5724bid on DOT projects.

57285 2 . However, p ursuant to Florida Admini strative Code Rule

574014 - 22.0141, a contractor who wishes to bid for the performance

5752of construction contracts less than $250,000, or to work on any

5764DOT maintenance project is presumed to be a responsible bidder

5774unless DOT determines good cause exists to decl are the

5784contractor non - responsible.

57885 3 . There was credible testimony herein that, in order to

5800prevent a de - certified contractor from “subbing” or “supplying”

5810on a DOT contract while disqualified, DOT uniformly follows - up

5821its de - certification to bid with a determination that the de -

5834certified contractor is also “non - responsible.”

58415 4 . The credible testimony herein also shows that DOT has

5853de - certified at least two contractors who failed to timely

5864submit Letters of Qualified Acceptance after a job was

5873complet ed. Whether or not these particular contractors also

5882were declared non - responsible is not in this record.

589255 . When DOT entered its intent to declare Respondent AMEC

5903non - responsible o n January 17, 2007, AMEC had not been pre -

5917qualified with DOT since May 2 004, and AMEC has not applied for

5930pre - qualification/certification with DOT since May 2004. A

5939settlement agreement regarding resolution of AMEC’s pre -

5947qualification application from 2004, indicates that DOT agreed

5955that “[n]o further action will be taken by the Department in

5966relation to the May 26, 2004, Application for Qualification.”

597556 . Since 2004, AMEC also has not attempted to obtain any

5987DOT bid documents for construction projects of less than

5996$250,000 , for which a contractor need not be pre - qualified, and

6009has not attempted to “sub” or to do maintenance work on any DOT

6022project. AMEC’s Project E ngineer testified that AMEC has no

6032current intent to apply for jobs with such a low financial

6043return .

604557 . However, absent a de - certification or declaration of

6056AM EC as non - responsible, AMEC remains eligible at any time to

6069apply for certification or to apply for the low financial return

6080work that does not require pre - certification.

608858 . DOT’s Construction Director, Brian Blanchard , manages

6096the State’s 2.5 billion do llar work program, and testified that

6107the integrity of the bidding process depend s upon treating all

6118contractors alike , and therefore , AMEC should be declared non -

6128responsible because it did not meet the contract requirements

6137that all other contractors had to meet, such as the timely

6148filing of its final acceptace figures and the appropriate forms

6158in compliance with a contract specification.

616459 . On or about March 1, 2007, AMEC filed its petition for

6177formal hearing herein, and the case was referred to the Div ision

6189of Administrative Hearings. DOT has not challenged the

6197timeliness of the petition .

6202CONCLUS IONS OF LAW

620660 . The Division of Administrative Hearings has

6214jurisdiction over the parties and subject matter of this

6223proceeding, pursuant to Section 120.569 and Subsection

6230120.57(1), Florida Statutes (200 7 ) .

623761 . The duty to go forward and burden of proof is upon

6250DOT , which seeks to change the status quo . See Department of

6262Transportation v. J.W.C. Co., Inc. , 396 So. 2d 778 (Fla. 1 st DCA

62751981). Pursuant to Section 337.167 (1), de - certification is not

6286equivalent to revocation of a license, and it is concluded here

6297that a declaration of non - responsibility also is not equivalent

6308to revocation of a license. Therefore, the standard of proof

6318herein is “ by a prep onderance of the evidence . ”

633062 . Supplemental Specification 9 - 9, quoted in Finding of

6341Fact 10 , is adopted by reference here. Although that

6350specification only provides for de - certification, the statutes

6359and rules permit a declaration of non - responsibility.

636863 . Section 337.16(2), Flor ida Statutes, provides, in

6377pertinent part :

6380[T]he department, for good cause, may

6386determine any contractor not having a

6392certificate of qu alification nonresponsible

6397for a specified period of time or may deny,

6406suspend, or revoke a ny certificate of

6413qualification. Good cause includes, but is

6419not limited to, circumstances in which a

6426contractor or the contractor’s official

6431representative:

6432* * *

6435(c) Fails to comply with contract

6441requirements, in terms of payment or

6447performance record, or to timely furnish

6453contract documents as required by the

6459contract or by any state o r f ederal statute

6469or regulation ; (E mphasis supplied)

64746 4 . Florida Administrative Code Rule 14 - 22.0141, which

6485implements this statute , provides in pertinent part:

6492(1) Contractors who wish to bid for

6499the performance of construction contracts

6504less than or equal to $250,000, or any

6513maintenance contracts, are presumed to be

6519responsible bidders unless the Department

6524determines that good cause exists to declare

6531the contractor non - responsible, which shall

6538include the following:

6541(a) One of the circumstances specified

6547in Section 337.16(2), Florida Statu t es,

6554occurs ;

6555* * *

6558(e) The contractor failed to comply

6564with contract requirements, or failed to

6570follow Department direction in the execution

6576of the contract ;

6579* * *

6582(j) When the Department determines

6587that any other circumstance constituting

6592“good cause” under Section 337.16 (2), F.S.,

6599exists.

6600* * *

6603(2) Determination o f Contractor Non -

6610Responsibility . The Contractor will be

6616determined to be non - responsible and

6623ineligible to bid on Department Contracts

6629for a period of time, based on the

6637seriousness of the deficiency.

6641(a) Examples of factors affecting th e

6648seriousness of the deficiency.

66521. Impacts on project schedule,

6657cost, or quality of work;

66622. Unsafe conditions are allowed

6667to exist;

66693. Complaints from the public;

66744. Delay or interference with the

6680bidding process ;

66825. The potential for repetition;

66876. Integrity of the public

6692construction process; and

66957. The effect on the health,

6701safety, and welfare of the

6706public. (Emphasis supplied)

67096 5 . Florida Administrative Code Rule 14 - 22. 012 addresses

6721only de - certifications, but DOT submits that rule is

6731instructional for this non - responsibility case , because the

6740situations and actions are analogous . Therein, s ub - paragraph

6751(b)(1) states that a suspension of 90 days shall occur for pre -

6764qual ified contractors who fail to timely provide contract

6773documents.

67746 6 . Section 337.164, Florida Statutes, states:

6782Recognizing that the preservation of

6787the integrity of the public contracting

6793process of the department is vital to the

6801development of a balance d and efficient

6808transportation system and is a matter of

6815interest to all the people of the state, the

6824Legislature determines and declares that :

6830(1) The procedures of the department

6836for bidding and qualification of bidders on

6843department contracts exist to secure the

6849public benefits of free and open competition

6856and to secure the quality of public works.

6864(2) The opportunity to bid on

6870department contracts or to supply goods or

6877services to the department is a privilege,

6884not a right.

6887* * *

6890To this end, it is the intent of the

6899Legislature to provide sufficiently broad

6904authority to the department to ensure the

6911integrity of its public contacting process.

69176 7 . AMEC submits the following propositions: (1) That

6927AMEC does not meet the definition of “contractor” under Section

6937337.165, because AMEC has neither “bid” or “applied to bid”;

6947(2) That because Rule 14 - 22.0141 addresses only “contractors who

6958wish to bid” and AMEC does not wish to bid, that rule does not

6972apply to AMEC; (3) That contract S pecif ication 9 - 9 lists only

6986the penalty of de - certification, and accordingly DOT cannot

6996declare AMEC “non - responsible”; (4) That, in the present

7006situation, the appropriate and required information was timely

7014provided by AMEC, but the information just was not pu t on the

7027appropriate Acceptance on Offer of Final Payment form, provided

7036with DOT’s July 19, 2006, Offer of Final Payment (see Findings

7047of Fact 18 and 21) , and that AMEC’s incorporation by reference,

7058of voluminous documents associated with AMEC’s two pendi ng

7067claims plus the circuit court case citation, in a separate

7077November 1, 2006, letter labeled “Qualified Acceptance,” was

7086sufficient to comply with Specification 9 - 9, which uses the term

7098“qualified acceptance letter,” and which does not use the term

7109“acce ptance on offer of final payme nt" or “total”; and (5) t hat

7123DOT’s January 17, 2007 , n otice of intent to declare non -

7135r esponsible was selective enforcement , used by DOT as leverage

7145in the parties’ circuit court case, because th e portion s of the

7158November 16, 2 006 , and January 17, 2007, letters concerning the

7169“non - responsible” declaration were drafted by DOT’s legal staff,

7179without any precedent .

718368 . AMEC’s first three argument s ( “ not a contractor ” , “ not

7198a contractor wishing to bid ” , and “ exclusivity of contrac t

7210specification penalty ” ) are without merit. AMEC admits it is

7221the “contractor” pursuant to the existing interchange contracts

7229between the parties . DOT can not be expected to “get inside the

7242head” of every corporate contractor to determine if that

7251contrac tor will ever , in the future , “ wish to bid.” Just as a

7265statute must be construed in a reasonable manner so as to avoid

7277absurd results ( see State v. Webb , 398 So. 2d 820 (Fla. 1981) ) ,

7291so must rules. Finally, just because Supplemental Specification

72999 - 9 onl y threatened de - certification as a penalty, DOT is not

7314required to ignore applicable statutes and rules and restrict

7323itself to the contract specifications when it administers State

7332contract s and addresses the contractors it employs. Herein, the

7342quoted sta tute s , rules, and contract terms all apply to AMEC.

735469 . There are two branches to AMEC’s fourth argument .

7365B oth are related to DOT’s a nswers to AMEC’s interrogatories.

7376Interrogatory No. 1 requested a detailed statement of DOT’s

7385basis for its January 17, 2007, declaration of non -

7395responsibility . A s part of a much longer answer, DOT responded

7407“ . . . AMEC had not submitted the proper forms or itemized the

7421total amount claimed in a Qualified Acceptance Letter.” In

7430response to AMEC’s Interrogatory No. 4, DOT responded, in

7439sum mary , that it agreed it could not require AMEC to use its

7452“Acceptance on Offer of Final Payment " forms ( see Findings of

7463Fact 19 - 21 ), but it did require the substance of the form.

747770. First, there is no significant difference between

7485thes e interrogatory answers and the DOT witnesses’ testimony at

7495hearing , nor are these interrogatory answers and the testimony

7504contrary to contract specifications or any of the correspondence

7513between the parties. While AMEC is entirely correct that the

7523word “ total” does not appear in Specification 9 - 9, the overall

7536thrust of that specification and of all DOT’s correspondence was

7546that AMEC was expected to provide “itemized amounts” for each

7556project number . These amounts had to be stated so that DOT’s

7568Final Esti mates Office could rely upon them as being truly final

7580claim s for each project, much as an insurance company sets up

7592reserves against outstanding accident claims, and so that the

7601final finite amount requested by the contractor could be

7610analyzed by DOT for payment and/or negotiation, ultimately

7618leading to a close - out of the contract file(s). Likewise, even

7630th e truncated portion of DOT’s full answer to Interrogatory No.

76411 , clearly does not omit DOT’s view that, in addition to

7652“itemized amounts,” certain mand atory forms were required of

7662AMEC and that AMEC was being held non - responsible for not timely

7675submitting those forms.

767871. Specification 9 - 9 states that a contractor can be de -

7691certified for failure to follow DOT’s instructions in the

7700execution of a contrac t. The letters of instruction by DOT were

7712clearly ignored by AMEC.

771672. Ms. Towers ’ July 19, 2006, written instructions were

7726to submit itemized amounts by project/contract numbers . ( See

7736Finding of Fact 18 ) . If anything, the blank forms made these

7749instru ctions even clearer. ( See Finding of Fact 19). Without

7760determin ing whether or not a total on each project/contract was

7771absolutely necessary to comply with 9 - 9, it is concluded that

7783DOT was clearly entitled to seek “itemized amounts” (the term

7793specificall y used in 9 - 9) by various components within each

7805project number. Each of AMEC’s two claims commingled components

7814of the two project numbers. The November 1, 2006, AMEC letter

7825did not itemize any amounts. Th erefore, th at letter’s attempt

7836to incorporate t he two claims, each claim combining the two

7847projects, still did not provide any “itemized amounts” by

7856project number. That was one material flaw in the November 1,

78672006, and the February 13, 2007, proposed “qualified

7875acceptances”.

787673 . T he second branch o f AMEC’s fourth argument is a non -

7891issue. L egally, AMEC waived any Section 120.57(1)(e) issues

7900with regard to whether or not the Acceptance on Offer of Final

7912Payment form constituted a “rule” or should have been adopted as

7923a rule . ( S ee Preliminary Statemen t) . F actually, this is not a

7939situation of DOT arbitrarily requiring a specific form. DOT did

7949not require that AMEC use its Acceptance on Offer of Final

7960Payment forms. (See Finding of Fact 31 .) In fact, as AMEC is

7973quick to point out, DOT’s answer to AME C’s Interrogatory No. 4 ,

7985states that DOT believes it cannot require that contractors use

7995that specific form but can require that contractors submit the

8005substance of the form.

800974. The evidence shows that DOT’s Final Estimates Office

8018probably would have acc epted a reasonable incorporation by

8027reference, with minimal supporting documentation on each

8034project, provided AMEC had broken down the disputed amounts into

8044the two separate project numbers. Based on the evidence

8053presented ( see Findings of Fact 35 - 36), D OT might have regretted

8067such leniency , but use of a printed form for the balances

8078claimed was not required. Non - use of a standardized form is not

8091a genuine issue herein. What does matter here is that the

8102claims themselves, even if incorporated by referen ce, did not

8112break the balance claimed by AMEC down by project number, so

8123AMEC did not provide “itemized amounts,” the term used in

8134Specification 9 - 9.

813875. The remainder of AMEC’s fourth argument seems to be

8148that it is up to DOT's District II Final Estima tes Office to

8161sift through voluminous papers in other offices of DOT in order

8172to determine what are “the particulars” of a contractor’s

8181qualified acceptance, before DOT can close out a contract, and

8191that the contractor is not required to timely submit eith er a

8203regular acceptance or qualified acceptance that meets DOT’s

8211instructions by contract or by letter. This interpretation is

8220inconsistent with the clear language of Supplemental

8227Specification 9 - 9 and DOT’s Offer of Final Payment.

823776. Supplemental Spe cification 9 - 9 clearly requires that

8247specificity “in the particulars” of any disputed amount is

8256required from the contractor and that the specificity

8264requirement is designed to prevent any further claims or claim

8274amendments after the disputed amount and su pporting particulars

8283have been presented. AMEC’s Project Engineer’s testimony is

8291insuf ficient to show that even with a diligent search “upstairs

8302and downstairs and in my lady’s chamber , ” as it were, Ms. Towers

8315could have deciphered AMEC’s respective balan ces to resolve the

8325two projects . Therefore, DOT could reject AMEC’s November 1,

83352006, and February 13, 2007, letters as qualified acceptance

8344letters. T he second material flaw in AMEC’s November 1, 2006,

8355and February 13, 2007 , letters was the lack of part iculars.

83667 7 . Specification 9 - 9 clearly states the contractor must

8378submit either the regular acceptance or the compliant qualified

8387acceptance within 90 days of the Offer of Final Payment. AMEC

8398did not do either. It is un - refuted that the 21 - A and FHWA - 47

8416forms are “contract documents” that must be submitted under DOT

8426direction ; that direction of when to submit them was repeatedly

8436given by DOT ; and that the dates required by DOT for filing them

8449were repeatedly missed by AMEC.

845478 . It is no t necessary to belabor whether F orm 21 - A, when

8470finally submitted on February 14 , 2007, was compliant. The

8479evidence is clear that AMEC did not timely (by November 7,

84902006 , ) or by any other date instructed by DOT, submit any

8502variety of the 21 - A or FHWA - 47 forms . It is a lso clear that

8520AMEC did not timely submit either a regular or qualified

8530acceptance letter which was materially compliant with

8537Supplemental S pecification 9 - 9 . AMEC thereby render ed itself

8549subject to being declared non - responsible under the cited

8559statutes a nd rules.

856379 . F inally, AMEC’s fifth argument, that DOT’s intent to

8574declare AMEC non - responsible was related to the parties' lawsuit

8585simply because DOT’s legal staff contributed to the contents of

8595DOT’s November 16, 2006, letter, is pure speculation. No

8604c redible evidence to that effect was presented.

861280. AMEC’s corollary argument that this was selective

8620prosecution on a theory that " there have been no prior

8630declarations of non - responsibility separate from de -

8639certifications and therefore the non - responsi ble declaration in

8649this case must have been selective prosecution due to the

8659parties' lawsuit, ” is not supported in fact . While admittedly

8670not identical, there have been similar declarations of non -

8680responsibil ity which are discussed in Findings of Fact 51 - 54 .

8693AMEC's fifth argument also is not supported in law , because the

8704instant case is not, strictly speaking, a case of first

8714impression . Although the declarations as non - responsible in the

8725cases of CPW Enterprises, Inc. d/b/a Cherokee Construction

8733Compa ny v. DOT , DOAH Case No. 03 - 1253 (RO: 9/18/03; FO:

874612/02/03), and Larry Holley Tree and Lawn Spraying, Inc. v. DOT,

8757DOAH Case No. 02 - 3373 (RO: 3/11/03; FO: 4/24/03), were not based

8770on f ailure to submit a Letter of Qualified Acceptance after a

8782job was compl eted, DOT did, therein, successfully declare those

8792contractors “non - responsible,” without a concurrent de -

8802certification .

8804RECOMMENDATION

8805Based on the foregoing Findings of Facts and Conclusions of

8815Law, it is

8818RECOMMENDED that the Department of Transportat ion enter a

8827final order ratifying its January 17, 2007, declaration of AMEC

8837as non - responsible for 90 days, the 90 days to run from the date

8852of the Final Order .

8857DONE AND ENTERED this 18th day of January , 200 8 , in

8868Tallahassee, Leon County, Florida.

8872S

8873ELLA JANE P. DAVIS

8877Administrative Law Judge

8880Division of Administrative Hearings

8884The DeSoto Building

88871230 Apalachee Parkway

8890Tallahassee, Florida 32399 - 3060

8895(850) 488 - 9675 SUNCOM 278 - 9675

8903Fax Filing (850) 921 - 6847

8909www.do ah.state.fl.us

8911Filed with the Clerk of the

8917Division of Administrative Hearings

8921this 18th day of January , 200 8 .

8929ENDNOTE

89301 / One Proposed Re commended Order was filed three days late,

8942but has been considered, anyway.

8947COPIES FURNISHED:

8949Erik Fenniman, Es quire

8953Department of Transportation

8956Haydon Burns Building

8959605 Suwannee Street, Mail Station 58

8965Tallahassee, Florida 32399

8968F. Alan Cummings, Esquire

8972S. Elysha Luken, Esquire

8976Smith, Currie & Hancock

89801004 DeSoto Park Drive

8984Tallahassee, Florida 32301

8987Jam es C. Myers, Clerk of the Agency Proceedings

8996Department of Transportation

8999Haydon Burns Building, Mail Station 58

9005605 Suwannee Street

9008Tallahassee, Florida 32399 - 0450

9013Alexis M. Yarbrough, General Counsel

9018Department of Transportation

9021Haydon Burns Building, Mail Station 58

9027605 Suwannee Street

9030Tallahassee, Florida 32399 - 0450

9035Stephanie Kopelousos, Secretary

9038Department of Transportation

9041Haydon Burns Building, Mail Station 58

9047605 Suwannee Street

9050Tallahassee, Florida 32399 - 0450

9055NOTICE OF RIGHT TO SUBMIT EXCEP TIONS

9062All parties have the right to submit written exceptions within

907215 days from the date of this Recommended Order. Any exceptions

9083to this Recommended Order should be filed with the agency that

9094will issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 07/01/2009
Proceedings: Opinion filed.
PDF:
Date: 06/30/2009
Proceedings: Opinion
PDF:
Date: 04/25/2008
Proceedings: (Agency) Final Order filed.
PDF:
Date: 04/23/2008
Proceedings: Agency Final Order
PDF:
Date: 01/18/2008
Proceedings: Recommended Order
PDF:
Date: 01/18/2008
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 01/18/2008
Proceedings: Recommended Order (hearing held September 20, 2007). CASE CLOSED.
PDF:
Date: 11/13/2007
Proceedings: Letter to Judge Davis from S. Luken regarding the style of the case filed.
PDF:
Date: 11/13/2007
Proceedings: Proposed Findings of Fact and Conclusions of Law filed.
PDF:
Date: 11/13/2007
Proceedings: Notice of Filing Proposed Findings of Fact and Conclusions of Law filed.
PDF:
Date: 11/09/2007
Proceedings: Respondent`s Proposed Recommended Order filed.
PDF:
Date: 10/11/2007
Proceedings: Post-hearing Order.
Date: 10/10/2007
Proceedings: Transcript filed.
Date: 09/20/2007
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 08/27/2007
Proceedings: Order on All Pending Motions.
Date: 08/23/2007
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 08/13/2007
Proceedings: Respondent`s Opposition to Petitioner`s Third Motion for Continuance filed.
PDF:
Date: 08/13/2007
Proceedings: Response to Motion for Continuance filed.
PDF:
Date: 08/10/2007
Proceedings: Petitioner`s Third Motion to Continue Final Hearing filed.
PDF:
Date: 08/07/2007
Proceedings: Discovery Order.
PDF:
Date: 08/07/2007
Proceedings: Notice of Hearing (hearing set for September 20 and 21, 2007; 10:30 a.m.; Jacksonville, FL).
Date: 08/06/2007
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 08/01/2007
Proceedings: Defendant`s Response to Petitioner`s Second Request for Production filed.
PDF:
Date: 07/24/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of L. Harper) filed.
PDF:
Date: 07/24/2007
Proceedings: Notice of Taking Deposition Duces Tecum ( of A. Prasad) filed.
PDF:
Date: 07/16/2007
Proceedings: Respondent`s Response to Petitioner`s Supplement to Motion to Compel filed.
PDF:
Date: 07/06/2007
Proceedings: Petitioner`s Supplemental to Motion to Compel filed.
PDF:
Date: 07/05/2007
Proceedings: Defendant`s Response to Order on Discovery filed.
PDF:
Date: 07/02/2007
Proceedings: Petitioner`s Motion for Extension of Time to Supplement Petitioner`s Motion to Compel filed.
PDF:
Date: 07/02/2007
Proceedings: Response to Rescheduling Order filed.
PDF:
Date: 06/28/2007
Proceedings: Respondent`s Notice of Service of Responses to Petitioner`s Second Interrogatories filed.
PDF:
Date: 06/27/2007
Proceedings: Respondent, Department of Transportation`s, Request for Admissions to Petitioner filed.
PDF:
Date: 06/22/2007
Proceedings: Order on Discovery.
PDF:
Date: 06/22/2007
Proceedings: Order Cancelling Hearing, Providing for Mutual Response (parties to advise status by July 2, 2007).
Date: 06/20/2007
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 06/19/2007
Proceedings: Respondent`s Response to Petitioner`s Motion to Compel filed.
PDF:
Date: 06/19/2007
Proceedings: Motion for Protective Order filed.
PDF:
Date: 06/19/2007
Proceedings: Notice of Telephonic Hearing filed.
PDF:
Date: 06/18/2007
Proceedings: Petitioner`s Second Motion to Continue Final Hearing filed.
PDF:
Date: 06/18/2007
Proceedings: Petitioner`s Motion to Compel filed.
PDF:
Date: 06/18/2007
Proceedings: Motion for Protective Order filed.
PDF:
Date: 06/15/2007
Proceedings: Petitioner`s Notice of Deposition Duces Tecum (of B. Blanchard) filed.
PDF:
Date: 06/15/2007
Proceedings: Petitioner`s Notice of Deposition for Department Corporate Representative filed.
PDF:
Date: 06/13/2007
Proceedings: Petitioner`s First Request for Admissions to Respondent filed.
PDF:
Date: 06/13/2007
Proceedings: Motion for Protective Order filed.
PDF:
Date: 06/08/2007
Proceedings: Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 06/06/2007
Proceedings: Petitioner`s Second Request for Production to Respondent filed.
PDF:
Date: 06/06/2007
Proceedings: Notice of Service of Petitioner`s Second Interrogatories filed.
PDF:
Date: 04/30/2007
Proceedings: Order (Respondent is granted five days thereafter to object and file substitute items).
PDF:
Date: 04/30/2007
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for June 25 and 26, 2007; 1:00 p.m.; Jacksonville, FL).
Date: 04/26/2007
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 04/20/2007
Proceedings: AMEC`s Reply to FDOT`s Opposition to a Continuance filed.
PDF:
Date: 04/19/2007
Proceedings: Respondent`s Motion for Official Recognition filed.
PDF:
Date: 04/18/2007
Proceedings: Petitioner`s Separate Pre-hearing Statement filed.
PDF:
Date: 04/18/2007
Proceedings: Notice of Service of Petitioner`s Executed Response and Objections to First Interrogatories filed.
PDF:
Date: 04/18/2007
Proceedings: Petitioner`s Response to Respondent`s First Request for Production filed.
PDF:
Date: 04/18/2007
Proceedings: Notice of Service of Petitioner`s Response and Objections to First Interrogatories (Unexecuted) filed.
PDF:
Date: 04/18/2007
Proceedings: Petitioner`s Response to Respondent`s First Request for Admissions filed.
PDF:
Date: 04/18/2007
Proceedings: Department Pre-hearing Statement filed.
PDF:
Date: 04/18/2007
Proceedings: Respondent`s Opposition to Petitioner`s Motion for Continuance filed.
PDF:
Date: 04/16/2007
Proceedings: Petitioner`s Motion to Continue Final Hearing filed.
PDF:
Date: 04/12/2007
Proceedings: Notice of Serving Respondent`s Answers to Plaintiff`s Interrogatories filed.
PDF:
Date: 04/11/2007
Proceedings: Defendant`s Response to Request for Production filed.
PDF:
Date: 04/03/2007
Proceedings: Letter to Claudia Llado from E. Fenniman enclosing Exhibit D to Petition for Hearing filed.
PDF:
Date: 04/03/2007
Proceedings: Notice of Serving Respondent`s First Set of Interrogatories filed.
PDF:
Date: 04/03/2007
Proceedings: Respondent`s Department of Transportation First Request for Production of Documents filed.
PDF:
Date: 04/03/2007
Proceedings: Respondent Department of Transportation`s Request for Admissions to Petitioner filed.
PDF:
Date: 03/29/2007
Proceedings: Order (Motion is considered a stipulation and is adopted and ratified by this Order).
PDF:
Date: 03/26/2007
Proceedings: Petitioner`s First Request for Production to Respondent filed.
PDF:
Date: 03/26/2007
Proceedings: Notice of Service of Petitioner`s First Interrogatories filed.
PDF:
Date: 03/23/2007
Proceedings: Petitioner`s Unopposed Motion to Reduce Time for Responses to Written Discovery filed.
PDF:
Date: 03/21/2007
Proceedings: Notice of Hearing (hearing set for May 3, 2007; 10:00 a.m.; Jacksonville, FL).
PDF:
Date: 03/21/2007
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 03/16/2007
Proceedings: Notice of Hearing filed.
PDF:
Date: 03/09/2007
Proceedings: Respondent`s Response to Initial Order filed.
PDF:
Date: 03/08/2007
Proceedings: Notice of Compliance with Initial Order filed.
PDF:
Date: 03/08/2007
Proceedings: Notice of Appearance (filed by S. Luken).
PDF:
Date: 03/01/2007
Proceedings: Initial Order.
PDF:
Date: 03/01/2007
Proceedings: Petition for Formal Administrative Proceedings filed.
PDF:
Date: 03/01/2007
Proceedings: Notice of Appearance (filed by F. Cummings).
PDF:
Date: 03/01/2007
Proceedings: Contractor`s Affidavit and Surety Consent filed.
PDF:
Date: 03/01/2007
Proceedings: Notice of Intent to Declare Non-Responsible filed.
PDF:
Date: 03/01/2007
Proceedings: Agency referral filed.

Case Information

Judge:
ELLA JANE P. DAVIS
Date Filed:
03/01/2007
Date Assignment:
03/09/2007
Last Docket Entry:
07/01/2009
Location:
Jacksonville, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Counsels

Related Florida Statute(s) (7):