07-002414 Quillon Yon And Kevin Yon vs. Town Of Grand Ridge And Department Of Environmental Protection
 Status: Closed
Recommended Order on Friday, February 8, 2008.


View Dockets  
Summary: With the additional recommended permit conditions, Grand Ridge provided reasonable assurances that the proposed domestic wastewater treatment plant and sprayfield would comply with all rules applicable to their construction and operation.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8QUILLON YON AND KEVIN YON , )

14)

15Petitioner s , )

18)

19vs. ) Case No. 07 - 2414

26)

27TOWN OF GRAND RIDGE AND )

33DEPARTMENT OF ENVIRONMENTAL )

37PROTECTION , )

39)

40Respondents . )

43)

44RECOMMENDED ORDER

46The final hearing in this case was held on September 18

57through 20, 2007, in Tallahassee, Florida, before Bram D.E.

66Canter, an Administrative Law Judge (ALJ), of the Division of

76Administrative Hearings (DOAH).

79APPEARANCES

80For Petitioners: Kenneth J. Plante, Esquire

86Tana D. Storey, Esquire

90Brewton Plante, P.A.

93225 South Adams Street, Suite 250

99Tallahassee, Florida 32301

102For Respondent Department of Environmental Protection :

109Nona R. Sc haffner, Esquire

114Department of Environmental

117Protection

1183900 Commonwealth Boulevard

121Mail Station 35

124Tallahassee, Florida 32399 - 3000

129For Respondent Town of Grand Ridge :

136Timothy P. Atkinson, Esquire

140Gavin D. Burge ss, Esquire

145Oertel, Fernandez, Cole and

149Bryant, P.A.

151Post Office Box 1110

155Tallahassee, Florida 3230 2 - 1110

161STATEMENT OF THE ISSUE

165The issue in this case is whether the Town of Grand Ridge

177(Grand Ridge) is entitled the Domestic Wast ewater Facility

186Permit that the Department of Environmental Protection intends

194to issue.

196PRELIMINARY STATEMENT

198On April 11, 2007, the Department gave notice of its intent

209to issue Domestic Wastewater Facility Permit N o. : FLA546429 - 001 -

222DW2P/NP) to Grand Ri dge to construct and operate a wastewater

233treatment plant and associated sprayfield . Petitioners Quillon

241Yon and Kevin Yon filed a petition for hearing to challenge the

253proposed agency action. The Department referred the matter to

262DOAH to conduct an evid entiary hearing.

269On September 12, 2007, Petitioners filed a Motion for

278Continuance based on the Town's identification of a revised site

288plan for the sprayfield . Following a telephonic hearing on the

299motion, the motion was denied. The ALJ also ruled that evidence

310presented at the hearing was to be confined to the proposed

321project with the revised sprayfield site plan.

328Respondents filed a Joint Motion in Limine, seeking to

337strike Petitioners' allegations that the proposed project would

345violate Departmen t statutes and rules that apply to projects

355that are designed to have a direct discharge of pollutants. The

366motion in limine was granted, because Grand Ridge does not

376propose, and the Department's proposed permit does not

384authorize, a direct discharge of treated wastewater to ground or

394surface waters of the state.

399Grand Ridge also filed a Motion for Costs and Attorneys'

409Fees. A r uling on that motion was deferred to this Recommended

421Order.

422At the final hearing, Joint Exhibit 1, consisting of

431documents in the Department's permitting file, were admitted

439into evidence. Grand Ridge presented the testimony of Clyde

448Moneyham, Jr., the t own m anager of Grand Ridge; Michael G.

460Varner, who was accepted as an expert in geotechnical

469engineering, including the study o f soils, field testing, soil

479sampling and testing, and laboratory testing of soils; Glen

488Allen, who was accepted as an expert certified wastewater

497treatment plant and sprayfield operator; Eric Guarino, who was

506accepted as an expert in geology, hydrogeology , groundwater

514assessment, groundwater monitoring and groundwater quality; Amir

521Zafar, who was accepted as an expert in wastewater treatment,

531reclaimed water holding ponds, sprayfield irrigation, sanitary

538sewer collection and transmission and hydraulic mode ling; and

547Frasier Bingham, Ph.D, who was accepted as an expert in ecology,

558state and federal wetlands delineation, including vegetation,

565soils and hydrology, and state and federal endangered and

574threatened species. Grand Ridge's Exhibits 1, 2, 5, 8, 12, 1 7,

58619b, 19c, 19d, 19f, 19g, 19j, 19k, 19m, 19n, 19o, 19p, 19q, 20,

59921, 24, 25, 28c, 28d, 29, 30a, 30b, 31, 32a, 32b, 32c, 32d, 33,

61334, 36, 37, 38, 39, 53, 54b, 54d, 54e, 55 and 77 were admitted

627into evidence. The Department presented the testimony of Jame s

637Billizon, who was accepted as an expert in geologic and

647groundwater issues pertaining to permit applications, both

654domestic and industrial wastewater; and William Evans, P.E., who

663was accepted as an expert in environmental engineering as it

673applies to do mestic wastewater facilities. The Department' s

682Exhibit 2 w as admitted into evidence . Petitioners presented the

693testimony of Quillon Yon, Jerry Gilley, and James Stevenson.

702Petitioners' Exhibits 2, 3, and 6 were admitted into evidence.

712At the request o f Grand Ridge, the ALJ officially

722recognized portions of the U.S. Environmental Protection Agency

730(EPA) publication entitled , "Land Treatment of Municipal

737Wastewater — Process Design Manual" (1981) , and the entirety of

747the EPA publication entitled "Design Cr iteria for Mechanical,

756Electric, and Fluid System s " (1974).

762The six - volume Transcript of the final hearing was filed

773with DOAH. The ALJ granted the motions of Petitioners and the

784Department to extend the time to file p roposed r ecommended

795o rders. Each par ty timely filed a Proposed Recommended Order

806which was carefully considered in the preparation of this

815Recommended Order.

817FINDINGS OF FACT

820The Parties

8221. The Department is the agency with the responsibility

831and authority to regulate the construction and o peration of

841domestic wastewater treatment facilities in Florida.

8472. The permit applicant, Town of Grand Ridge, is a

857municipality in Jackson County. Grand Ridge has a population of

867approximately 950 persons.

8703. Petitioner Quillon Yon is the owner of 95 a cres of land

883contiguous to the site of Grand Ridge's proposed wastewater

892treatment plant and sprayfield . He resides on this property

902half of each year. He grows Pensacola Bahia grass as pasturage

913for about 40 head of cattle. The rest of the property is

925forested. There are potable water wells on the property.

9344. Petitioners are co - owners of about 20 acres adjacent to

946Ocheesee Pond which is east of the project site. Part of the

958property is used to grow Coastal Bermuda grass as hay.

968Petitioners fish on Ocheesee Pond.

973The Proposed Project and Project Site

9795. The challenged Department permit authorizes Grand Ridge

987to construct and operate an "extended aeration secondary

995treatment domestic wastewater treatment plant consisting of flow

1003equalization, influe nt screening, comminution, grit removal,

1010aeration, secondary clarification, and chlorination." The

1016permit also authorizes Grand Ridge to construct and operate a

1026slow - rate, restricted public access, land application system

1035( sprayfield ).

10386. The treatment p lant and sprayfield would be constructed

1048on a 475 - acre site owned by Grand Ridge and located within the

1062t own limits. The wastewater treatment plant would be

1071constructed in the approximate middle of the site. The

1080sprayfield would be located in the souther n portion of the site.

1092The northern portion of the site would remain in its natural

1103condition.

11047. The land uses surrounding the proposed project site are

1114mostly agriculture, consisting of row crops, hayfields,

1121vegetables, and cattle operations. Ocheesee Pond is a natural

1130waterbody located about 3,000 feet to the east of the project

1142site. Dickson Bay is a natural waterbody located 1,500 to 2,500

1155feet south of the project site. There are other wetlands and

1166unnamed surface waters near the project site.

11738. The treatment plant would have the capacity to treat an

1184annual average daily flow of 205,000 gallons of domestic

1194wastewater. This design capacity would accommodate the

1201projected population growth of Grand Ridge through 2028.

12099. The treatment plant is d esigned to meet Class 1

1220Reliability standards as established by the EPA . Class 1

1230Reliability relates primarily to the provision of backup systems

1239throughout the treatment plant, such as electrical power

1247sources, pumps, holding ponds, and treatment process es, which

1256give greater assurance that the facility will remain operational

1265in the event of system failures.

127110. Grand Ridge provided reasonable assurance that the

1279treatment plant would meet all the design and operational

1288standards applicable to domestic w astewater treatment plants of

1297this type.

129911. The treatment plant would be located a minimum of

13091,600 feet away from any of the project site boundaries. The

1321only part of the plant that might produce objectionable odor is

1332near the "headworks" where the sew age comes in from the

1343collection system. Based on the location of the treatment plant

1353on the project site and the odor control measures to be

1364utilized, Grand Ridge provided reasonable assurance that the

1372proposed project would not create objectionable odor s so as to

1383create a nuisance to persons residing near the project site.

139312. After the wastewater is treated, it would be stored in

1404two above - ground storage ponds until it is pumped to the

1416sprayfield . The ponds would be lined with a high - density

1428polyethyl ene liner.

143113. The ponds would hold ten days of wastewater flow at

1442the average daily flow rate. Under the Department's rules, only

1452three days of storage capacity is required. Grand Ridge

1461provided reasonable assurance that the storage ponds would

1469prevent wastewater from being released even during unusually

1477heavy rainfall or rainfall of unusually long duration and that

1487all other standards applicable to wastewater storage would be

1496met.

149714. Grand Ridge originally proposed a sprayfield of 168

1506acres. The pro posed sprayfield was later reduced to 106 acres

1517and generally occupies the relatively flatter terrain within the

1526original 168 acres. The rest of the 62 acres that had been part

1539of the originally proposed sprayfield are now proposed to be

1549left in their nat ural vegetation.

155515. A portion of the wastewater sprayed onto the

1564sprayfield would be taken up by the grasses grown there for that

1576purpose , and the balance of the wastewater would percolate

1585through the soil to the groundwater. Because the wastewater is

1595t reated and returned to the groundwater in this process, it is

1607also referred to as reclaimed water.

161316. The project is not designed to have a direct discharge

1624to ground or surface waters.

1629Soils at the Project Site

163417. The Jackson County Soil Survey indica tes that the

1644predominant soil types at the proposed sprayfield are Dothan

1653loamy sands and Fuquay coarse sands. Ninety - five percent of the

1665soils in area of the proposed sprayfield are defined in the soil

1677survey as being well - drained, meaning that water rea dily

1688percolates down through them. Because the soils are well -

1698drained, they are generally suitable for a sprayfield .

170718. Hand auger soil borings were taken throughout the

1716proposed site to determine the thickness of the sandy soils that

1727begin at the groun d surface. The thickness of the sandy soils

1739determines their capacity to store water. The thickness of the

1749sandy soils is greatest in the southern portion of the proposed

1760site where the sprayfield would be located, with an average of

1771about two feet.

177419. Six deeper soil borings were made, ranging in depth

1784from 70 to 80 feet. Each of the deeper borings showed that

1796beneath the sandy soils exists a thicker layer of clayey sands.

1807Beneath the clayey sands is a confining layer of highly plastic

1818(almost imperm eable) clay. Below the clay is limestone.

182720. Four double ring infiltrometer field tests were

1835conducted to determine the vertical infiltration rate of water

1844through the soils. The tests showed an average infiltration

1853rate in the area of the proposed spr ayfield of 4.5 inches per

1866hour. This is a good infiltration rate for a sprayfield .

187721. Wastewater percolating downward through the soil would

1885reach the confining layer of clay and then move horizontally

1895along the clay layer. "Slug tests" were conducted to determine

1905the horizontal conductivity of the soils. The average

1913horizontal conductivity was determined to be 0.06 feet per day,

1923which was characterized by a geotechnical engineer as "fairly

1932slow."

19332 2 . Permeability tests in a laboratory were performed on

1944the clay layer to determine how long it would take water to move

1957through the clay. The permeability of the clay layer was .00008

1968feet per day. At the thinnest clay layer (9 feet thick), it

1980would take approximately 189 years for treated wastewater

1988appl ied to the sprayfield to penetrate through the clay to the

2000underlying limestone.

20022 3 . The project site is not a recharge area for the

2015Floridan aquifer due to the clay confining layer beneath the

2025site.

20262 4 . The soils in the area of the proposed storage pond s

2040are stable and suitable for the construction of the proposed

2050ponds.

20512 5 . In conducting the evaluation of the soils on the

2063project site, Grand Ridge's consultants found a few depressions,

2072but no sinkholes or other "karst" features. A k arst feature is

2084a s inkhole or other geologic form which indicates exposed

2094limestone or the presence of limestone near the ground surface.

2104Groundwater

21052 6 . Five piezometers were installed at the site at depths

2117from 68 to 75 feet to determine the depth of the groundwater and

2130t he direction of the groundwater flow. Groundwater was

2139encountered at depths between 18.9 to 68.8 feet below the

2149surface. The direction of groundwater flow beneath the proposed

2158sprayfield was determined to be generally east and southeast.

216727. A "mounding " analysis, using a computer model, was

2176conducted to predict how groundwater levels would be affected by

2186the application of treated wastewater to the sprayfield . The

2196main purpose of the analysis was to determine whether treated

2206wastewater could be applied to the sprayfield without causing

2215ponding of water on the surface of the sprayfield . The permit

2227contains a condition that prohibits surface runoff or ponding of

2237the applied reclaimed water.

224128. Several conservative assumptions were used in the

2249mounding analysis. It assumed a perched groundwater condition

2257beneath the proposed sprayfield , because the Jackson County Soil

2266Survey indicated that the soils found there are indicative of

2276the presence of perched groundwater for part of the year.

2286Perched groundwa ter is a situation where a soil layer of low

2298permeability will cause groundwater to perch for a time before

2308it moves downward. Although the soil survey indicated that the

2318perched water condition might exist for three to four months a

2329year, the computer mo del used in the mounding analysis was run

2341with the assumption that the perched water condition was present

2351year round.

235329. Another conservative assumption used in the mounding

2361analysis was an average annual rainfall amount of 64.9 inches.

2371The historic an nual rainfall for the area is approximately 55

2382inches per year.

238530. Another conservative assumption used in the mounding

2393analysis was an infiltration rate of 3.5 inches per hour. That

2404was the average infiltration rate computed from the f ive

2414piezometers, but the piezometers in the area of the proposed

2424sprayfield showed an average infiltration rate of 4.5 inches per

2434hour.

243531. Using these conservative assumptions, t he mounding

2443analysis showed the sprayfield could absorb 2.75 inches per hour

2453without ponding. Therefore, Grand Ridge provided reasonable

2460assurance that mounding would not occur at the permitted

2469application rate of 0.5 inches per acre , per week.

2478Sprayfield Operation

248032. Grand Ridge's proposal to reduce the proposed

2488sprayfield from 168 acres to 10 6 acres did not affect the

2500permitted application rate of 0.5 inches per week, per week .

2511However, the permitted wastewater volume of .308 million gallons

2520per day (mgd) would have to be reduced to .205 mgd to correspond

2533with the reduction in the size of the sprayfield . Grand Ridge

2545agreed to this modification.

254933. The sprayfield would be divided into seven zones that

2559could be operated independently. It is Grand Ridge's general

2568plan to rotate from one zone to another through the week,

2579spraying 0.5 inches pe r acre each day. That is likely to

2591require spraying for two to three hours each day. Because each

2602of the seven sprayfield zones would only be sprayed once each

2613week, this method of operation would meet the permit condition

2623of 0.5 inches per week, per wee k .

263234. The spray nozzles along the boundary of the sprayfield

2642would be installed and operated to spray only inward, toward the

2653sprayfield .

265535. Florida Administrative Code Rule 62 - 610.421(2)

2663requires a 100 - foot setback from the property line to the wetted

2676area of the sprayfield , unless the setback is vegetated with

2686trees or shrubs that create a visual barrier, in which case the

2698required setback is 50 feet. Grand Ridge proposes an 80 - foot

2710buffer zone around the wetted area of the sprayfield and, beyond

2721thi s zone, an additional 100 - foot vegetated buffer, consisting

2732partly of thickly - planted yellow pine trees. The total buffer

2743from the wetted area of the sprayfield to the property

2753boundaries would be 180 feet.

275836. Because of the extensive buffers around the proposed

2767sprayfield , including forested areas, Grand Ridge provided

2774reasonable assurance that any aerosol drift from the sprayfield

2783would not move off the project site.

279037. The sprayfield would not be operated when it is

2800raining at the project site. Fur thermore, because the permit

2810does not require a treatment plant operator to be on the site at

2823all times, Grand Ridge proposes to install rain sensors that

2833would automatically shut down the sprinklers when the sensors

2842detect rain. The sprinklers would have to be restarted

2851manually. During the shut - down, treated effluent would remain

2861in the storage ponds.

286538. Grand Ridge has proposed to add a condition to the

2876permit that prohibits the operation of the sprayfield sooner

2885than four hours after a rainfall even t.

289339. The sprayfield would be located at least 100 feet from

2904the wetlands on the project site. The spray nozzles would

2914direct spray away from the wetlands.

292040. Grand Ridge also proposes to construct a one - foot - high

2933earthen berm around the wetlands near est the sprayfield to

2943direct any surface flow of rainwater away from them.

2952The Crops

295441. Grand Ridge proposes to plant Coastal Bermuda grass in

2964the summer and rye grass in the winter on the sprayfield . These

2977crops were chosen for their high nitrogen upta ke, high water

2988uptake, and moisture tolerance.

299242. The amount of nitrogen that would be applied to the

3003sprayfield as a component of the treated wastewater is about 120

3014pounds per acre , per year when the treatment plant is at full

3026capacity. This is less t han the amount of nitrogen generally

3037recommended for the fertilization of Coastal Bermuda and rye

3046grasses. Therefore, Grand Ridge might need to occasionally

3054apply supplemental nitrogen to fertilize the grasses. Grand

3062Ridge proposes to limit its applicati on of supplemental nitrogen

3072to only the amount necessary to maintain the crops, but never

3083more than 200 pounds per acre , per year. 1

309243. The Town of Sneads, approximately five miles east of

3102Grand Ridge, grows Coastal Bermuda grass on its sprayfield . The

3113o perator of the Sneads sprayfield said that the Coastal Bermuda

3124grass has done well without the need to apply supplemental

3134nitrogen. Petitioners grow Coastal Bermuda on their property

3142near Ocheesee Pond.

314544. Any supplemental nitrogen applied to the crop s would

3155be applied in split applications that will not exceed 40 pounds

3166per acre at a time. The supplemental nitrogen would be applied

3177just before spraying, which would help to release the nitrogen

3187into the soil.

319045. The total nitrogen in the wastewater and in the

3200supplemental nitrogen fertilizer that would be applied to the

3209grasses is less than the amount of nitrogen these grasses are

3220generally able to take up. Even though it is reasonable to

3231expect that some nitrogen will percolate past the root zone o f

3243the grasses before it can be taken up by the plants, only a

3256small fraction of the nitrogen would likely percolate through

3265the soils and reach the ground water beneath the sprayfield .

327646. Department rules provide for a "zone of discharge" for

3286a sprayfiel d that extends horizontally 100 feet from the wetted

3297area of the sprayfield or to the facility's property line,

3307whichever distance is smaller. Groundwater quality standards

3314must be met beyond the zone of discharge. In this case, the

3326100 - foot zone of disc harge would be applicable. Grand Ridge

3338provided reasonable assurance that nitrogen in the groundwater

3346would not reach concentrations that exceed the state groundwater

3355quality standard beyond the zone of discharge.

3362Monitoring

336347. There are to be six groun dwater monitoring wells on

3374the proposed site which would be sampled quarterly for

3383compliance with groundwater quality standards. Samples would be

3391taken from these wells before the sprayfield is placed in

3401operation to establish the background quality of th e

3410groundwater.

341148. The proposed placement of the groundwater monitoring

3419wells was determined by Grand Ridge in consultation with the

3429Department staff and takes into account the direction of

3438groundwater movement. The monitoring plan is reasonably

3445designed to intercept and determine the concentration of

3453nitrogen and other constituents of the reclaimed water as it

3463moves away from the proposed sprayfield .

347049. There would be one surface water monitoring station.

3479It would be located at a small pond just north of the treatment

3492plant and would also be sampled quarterly.

349950. Grand Ridge proposes to monitor the nitrogen levels in

3509the treated wastewater and in the soils of the sprayfield on a

3521bi - monthly basis to determine the amount of any supplemental

3532nitrogen th at should be applied to the grasses. This particular

3543monitoring is not required by Department rules.

3550Potable Water Wells

355351. Florida Administrative Code Rule 62 - 610.421(3)

3561requires a sprayfield to be set back at least 500 feet from the

3574edge of the wetted area to existing or approved potable water

3585supply wells, unless the treatment facility meets Class 1

3594Reliability standards, in which case the setback requirement is

3603200 feet. Because this proposed facility would meet Class 1

3613Reliability standards, the 20 0 - foot setback is applicable.

362352. Grand Ridge's consultants examined the records of the

3632Northwest Florida Water Management District (NWFWMD) to

3639determine whether there were any permitted potable water wells

3648near the proposed project. They also went to ev ery house near

3660the project site to determine if there were any unpermitted

3670wells. They found no record or other evidence of a potable

3681water well within 200 feet of the proposed sprayfield .

369153. In April 2007, NWFWMD issued permits for two water

3701wells to P etitioner Quillon Yon. These wells are to be located

3713on his property south of the proposed project site. They have

3724not yet been installed. Also , in April 2007, NWFWMD issued a

3735permit to Merita Stanley for a well to be located at 450 Highway

374869 in Grand Ridge. In May 2007, NWFWMD issued a permit to

3760Rodney Lewis for a well to be located at 7289 Shady Grove Road

3773in Grand Ridge. Grand Ridge 's counsel stated at the hearing

3784that he thinks the Stanley and Lewis wells have been installed.

3795Grand Ridge filed pe titions for administrative hearing with the

3805NWFWMD to challenge these four potable water well permits. No

3815information was provided about the status of the permit

3824challenges.

382554. The permit documents that are part of Grand Ridge's

3835Exhibit 53 do not indica te a precise location for the recently

3847permitted wells. However, because the sprayfield is set back

3856180 feet from the property boundaries, the new potable water

3866wells would have to be drilled less than 20 feet from the

3878boundaries of the project site in or der to be within 200 feet of

3892the sprayfield . Mr. Zafar testified that, if it were necessary,

3903the proposed wetted area of the sprayfield could be adjusted so

3914that it is 20 feet further from the property lines.

3924Surface Runoff Entering the Sprayfield

392955. Fl orida Administrative Code Rule 62 - 610.417(1)

3938requires a sprayfield to be designed to prevent the entrance of

3949surface runoff. The rule requires berms to be placed around the

3960application area, if necessary for this purpose.

396756. In a hydrogeologic report fr om Grand Ridge's

3976consultants, it was recommended that "sprayfield areas with

3984greater than 5 percent slopes or adjacent to wetland areas be

3995bermed with a one - foot high grassed berm to reduce the

4007possibility of surface runoff." Grand Ridge proposes to place

4016one - foot high berms around the wetlands near the sprayfield , but

4028it was not made clear whether berms are to be placed to prevent

4041runoff from entering the sprayfield . Grand Ridge ' s Exhibit 77

4053shows only berms down gradient of the sprayfield . There are no

4065berms shown above the sprayfield .

4071Stormwater Leaving the Project Site

40765 7 . One of the principal disputes in this case is whether

4089there would be contaminated runoff from the sprayfield that

4098would move off - site. Florida Administrative Code Rule

410762 - 610.400( 1) states that off - site surface runoff of the applied

4121reclaimed water is to be "generally avoided." Florida

4129Administrative Code Rule 62 - 610.417(1) states that provisions

4138for on - site surface runoff control are to be described in the

4151applicant's engineering report and are subject to Department

4159approval. There are no more specific requirements for

4167controlling runoff associated with a proposed sprayfield .

41755 8 . Grand Ridge's engineering report states that the

4185existing drainage patterns of the project site will be used.

4195The project site is highest near its southern boundary where the

4206elevation reaches 250 feet and slopes down to an elevation of

4217120 feet in the northeastern corner of the site. Grand Ridge

4228does not propose to do any grading on the site.

423859 . Gra nd Ridge has proposed a permit condition that it

4250must obtain a National Pollutant Discharge Elimination System

4258Permit for construction of the sprayfield in order to address

4268stormwater and erosion in greater detail.

42746 0 . Petitioner Quillon Yon testified tha t stormwater runs

4285off the northeastern corner of the project site and the

4295southwestern area of the project site and makes its way,

4305respectively, to Ocheesee Pond and to Dickson Bay. However,

4314Petitioners did not establish what size rainfall event causes

4323st ormwater to run off the project site (or, more importantly,

4334the proposed sprayfield area), what concentrations of

4341contaminants would be in the stormwater leaving the project

4350site, or what levels of contamination in the runoff would be

4361necessary to cause an adverse impact to Ocheesee Pond or Dickson

4372Bay.

43736 1 . The average infiltration rate of 4.5 inches per hour

4385far exceeds the permitted application rate of 0.5 inches per

4395week. Grand Ridge would not be applying treated effluent to the

4406sprayfield during a rai nstorm. Any runoff from the sprayfield

4416would have to flow across 180 feet of vegetated buffer before

4427reaching the site boundaries. These and several other

4435conditions of the proposed permit provide reasonable assurance

4443that contaminated stormwater would n ot flow off the project

4453site.

44546 2 . Petitioners' evidence was insufficient to rise above

4464speculation and to competently demonstrate that there is a

4473reasonable probability that stormwater contaminated with treated

4480effluent would flow off the proposed sprayfi eld , across the

4490vegetated buffer areas, and make its way to Ocheesee Pond or

4501Dickson Bay in concentrations that would adversely affect these

4510water bodies .

45136 3 . Petitioners' counsel, on cross - examination, frequently

4523asked witnesses to assume hurricane and o ther extreme storm

4533conditions. Rainstorms of extreme magnitude can overcome the

4541ability of man - made stormwater controls to prevent runoff, but

4552it is neither practicable nor reasonable to require permit

4561applicants to install stormwater controls that would prevent

4569runoff during a hurricane or other extreme circumstances that

4578only rarely occur. The infiltration rate compared to the

4587permitted application rate, the wide vegetated buffers, and

4595other proposed permit conditions (such as the automatic shutoff

4604duri ng rainfall) make it unlikely that stormwater would run off

4615the sprayfield and off the project site except under extreme

4625rainfall. If there was runoff under extreme storm conditions,

4634the runoff from the project site would constitute an

4643insignificant contr ibution to the overall natural and man -

4653induced contamination of Ocheesee Pond and Dickson Bay caused

4662from the flows they would receive from all areas within their

4673watersheds.

4674On - Site Spring

46786 4 . One of the factual disputes in this case is whether

4691there exi sts a spring on the project site. The Department

4702argues in its Proposed Recommended Order that, even if there

4712were a spring where Petitioners claim it is located, there is no

4724evidence that it is still flowing and, further, the operation of

4735the sprayfield would not adversely affect the spring even if it

4746were still flowing. However, the existence of a groundwater - fed

4757spring, whether it is still flowing or not, would suggest there

4768might be a direct conduit to the limestone aquifer. Therefore,

4778whether a spri ng exists is relevant to the question of whether

4790this project site is suitable for the operation of a sprayfield .

48026 5 . There was no evidence presented in the form of maps or

4816government records to indicate official knowledge of the

4824existence of a spring on the project site.

48326 6 . Petitioner Quillon Yon indicated that a spring is

4843located on a hill close to the southern boundary of the project

4855site. He described it as water flowing out of the ground and

4867running down the hill all through the year except during

4877droughts. He said that as a child growing up on the land he now

4891owns that is south of the project site, he would occasionally

4902gather water from the spring and his mother would sometimes wash

4913clothes at the spring.

49176 7 . Petitioner Quillon Yon said it has b een many years

4930since he has seen the spring. He also said that the spring

4942might not be flowing any more because of the dry conditions of

4954the past several years.

49586 8 . Jerry Gilley testified that he leased the project site

4970between 1985 and 2000 and construc ted some of the roads on the

4983site. He said he installed a culvert under a road located near

4995the spring, which he called Springhead Road, so the flow from

5006the spring would not wash out the road. He said the problem

5018occurred every time it rained. Curiousl y, Mr. Gilley said he

5029never actually saw the spring, but just the water running down

5040the hill from the spring.

504569 . There was a site inspection by Petitioners during the

5056discovery phase of this case, one purpose of which was to look

5068for the spring. No one reported finding the spring.

50777 0 . Dr. Frasier Bingham, a biologist, walked throughout

5087the project site to delineate wetlands and to look for

5097threatened and endangered plant and animal species. He did not

5107find a spring. However, Dr. Bingham described two wetlands on

5117the project site associated with "slope seeps" where water in

5127the soil beneath the ground surface emerges on a hillside to

5138create wet conditions. One of the se wetlands is in the area

5150where Petitioner Quillon Yon said the spring is located.

51597 1 . Eric Guarino, a hydrogeologist, offered the opinion

5169that the spring described by Petitioner Quillon Yon would most

5179likely be caused by rainfall, rather than upwelling from a

5189hydraulic connection to groundwater, and, therefore, was not a

5198spring.

51997 2 . The more persuasive testimony in the record is that

5211the feature described as a spring by Petitioners was probably a

5222slope seep. The slope seeps are not within the proposed

5232sprayfield . The existence of slope seeps on the project site

5243does not make the site u nsuitable for use as a sprayfield .

5256On - Site Well

52607 3 . Mr. Gilley said there was a man - made well located on

5275the proposed project site which he thought was 40 to 50 feet

5287deep. No one else seemed to have any knowledge of the well's

5299existence.

5300Off - Site Featu res

53057 4 . Florida Administrative Code Rule 62 - 610.310(3)(c)

5315requires permit applicants to prepare and submit a hydrogeologic

5324survey , which includes geophysical information concerning known

5331solution openings and sinkhole features within one mile of the

5341site. Grand Ridge's hydrogeologist reviewed topographic maps to

5349determine whether there was potential for sinkhole development

5357within a one - mile radius of the project site. No features were

5370found that indicated a potential for sinkhole development .

53797 5 . Mr. Gilley said there is a sinkhole at the southeast

5392corner of Ocheesee Pond. It was not established in the record

5403how far this alleged sinkhole is from the project site.

5413Respondents contend that Mr. Gilley i s not competent to identify

5424a sinkhole. A sinkho le is a feature that occurs with regularity

5436in Florida and is recognizable to many people of average

5446intelligence without the need to have been trained or educated

5456as a hydrogeologist. Grand Ridge's hydrogeologist did not

5464identify this feature as a sinkho le in his hydrogeologic survey .

5476The record evidence does not show whether he was aware of the

5488feature, but did not consider it a sinkhole , or determined that

5499it was more than one mile from the project site.

55097 6 . James Stevenson said there were five sp rings east of

5522Ocheesee Pond, which he estimated to be four to six miles from

5534the project site.

55377 7 . Grand Ridge met the minimum requirement s of Florida

5549Administrative Code Rule 62 - 610.310(3)(c) .

5556CONCLUSIONS OF LAW

55597 8 . The Division of Administrative He arings has

5569jurisdiction over the parties to and subject matter of this

5579proceeding pursuant to Section 120.569 and Subsection 120.57(1),

5587Florida Statutes (2007) . 2

559279 . The Department is the state agency with authority and

5603responsibility to permit and regula te domestic wastewater

5611treatment facilities pursuant to Chapter 403, Florida Statutes,

5619and the rules promulgated thereunder.

56248 0 . Subs ection 120.569(1), Florida Statutes, provides that

5634the right to participate in administrative proceedings extends

5642to any pe rson whose substantial interests will be affected by

5653proposed agency action.

56568 1 . A petitioner's standing is not dependent on proving a

5668claim that the proposed agency action would violate applicable

5677law. Standing and the merits of a claim are different co ncepts.

5689See , e.g. , Village Park Mobile Home Ass'n., Inc. v. State Dept.

5700of Business Regulation , 506 So. 2d 426, 433 (Fla. 1st DCA 1987);

5712St. Martin's Episcopal Church v. Prudential - Bache Securities ,

5721613 So. 2d 108, 109, n. 4 (Fla. 4th DCA 1993). Instead,

5733standing requires proof that the petitioner has a substantial

5742interest and that the interest would be affected by the proposed

5753agency action. Whether the effect would constitute a violation

5762of applicable law is a separate question for determination.

57718 2 . Petitioner Quillon Yon's interest in protecting his

5781contiguous real property from groundwater and surface water

5789contamination is a substantial interest for purposes of

5797standing. Petitioner s' interest in fishing on Ocheesee Pond is

5807also a substantial inte rest. These are interests of the type

5818and nature which this proceeding was designed to protect.

58278 3 . The direction of groundwater flow and the horizontal

5838conductivity of the soils underlying the proposed sprayfield

5846shows that some of the groundwater benea th the proposed

5856sprayfield could move toward and then beneath the contiguous

5865property of Petitioner Quillon Yon. The record also shows that

5875this groundwater is likely to contain some nitrogen and other

5885wastewater constituents that percolated from the spra yfield .

5894This evidence is sufficient to show that Petitioner Quillon

5903Yon's substantial interest in protecting his contiguous real

5911property from groundwater contamination would be affected by the

5920proposed sprayfield operation. Although he did not prove tha t

5930the concentration of contaminants in the groundwater would

5938exceed applicable groundwater quality standards, Petitioner

5944Quillon Yon has the requisite standing to initiate and maintain

5954these administrative proceedings to present his contrary view.

59628 4 . On the other hand, the evidence in the record

5974regarding the effect of the proposed project on Quillon Yon's

5984and Kevin Yon's s ubstantial interest in fishing on Ocheesee Pond

5995was speculative and incomplete. 3 Necessary details, such as the

6005size of the rain even t that would cause runoff from the

6017sprayfield and the project site , and the concentration of

6026nitrogen or of other contaminants in the runoff that would be

6037necessary to result in a detectable increase in these

6046contaminants' levels in Ocheesee Pond, were not presented.

6054There was also insufficient evidence to show that Ocheesee Pond

6064would be affected by groundwater contamination originating from

6072the project site. The allegation of harm to Ocheesee Pond was

6083the only e ffect on the interests of Petitioner Kevin Yon

6094presented at the hearing. Therefore, Petitioner Kevin Yon

6102failed to prove his standing.

61078 5 . As the applicant for the permit, Grand Ridge has the

6120ultimate burden of proving its entitlement to the permit by a

6131preponderance of the evidence. Dept. of T ransp. v. J.W.C. Co.,

6142Inc. , 396 So. 2d 778 (Fla. 1st DCA 1981).

61518 6 . Florida Administrative Code Rule 62 - 4.070(1) states

6162that a permit shall be issued only if "the applicant

6172affirmatively provides the Department with reasonable assurance

6179based on plans, te st results, installation of pollution control

6189equipment, or other information, that the construction,

6196expansion, modification, operation, or activity of the

6203installation will not discharge, emit, or cause pollution in

6212contravention of Department standards or rules."

62188 7 . "Reasonable assurance" in this context means a

6228demonstration that there is a substantial likelihood of

6236compliance with standards, or "a substantial likelihood that the

6245project will be successfully implemented." Metropolitan Dade

6252County, v. Coscan Florida, Inc. , 609 So. 2d 644, 648 (Fla. 3d

6264DCA 1992).

62668 8 . The reasonable assurance standard requires the

6275applicant to address reasonably foreseeable contingencies. See

6282Rowe v. Oleander Power Project, L.P. , 1999 Fla. Env. Lexis 5752

6293(DEP 1999) ; Chipola Basin Protective Group, Inc. v. Fla. Chapter

6303Sierra Club , 1988 Fla. Env. Lexis 112 (DER 1988).

631289 . In advance of the final hearing, Grand Ridge proposed

6323several additional permit conditions affecting primarily the

6330operational aspects of the prop osed facility in order to address

6341some of the concerns raised by Petitioners. Each of the

6351proposed additional conditions would tend to reduce the

6359potential for adverse environmental impacts.

63649 0 . Proceedings under Section 120.57, Florida Statutes ,

6373are int ended to formulate final agency action, not to review

6384action taken earlier and preliminarily. J.W.C , supra , 396

6392So. 2d at 785 (quoting McDonald v. Department of Banking and

6403Finance , 346 So. 2d 569, 584 (Fla. 1st DCA 1977). Therefore, as

6415long as the due p rocess rights of the parties are preserved,

6427modifications to a project can be proposed and addressed at the

6438final hearing. In this case Petitioners' due process rights,

6447principally their right to have sufficient notice of the

6456proposed modifications to pre pare for the final hearing, were

6466preserved.

64679 1 . Florida Administrative Code Rule 62 - 110.106(7)(a)4.

6477provides that additional public notice does not have to be

6487published by a permit applicant for modifications made after a

6497notice of intent was published un less the modifications are

6507substantial. A substantial modification is defined in the rule

6516a s "a relocation or modification of the activity or project that

6528is reasonably expected to cause new or significantly greater

6537adverse environmental impacts." Becaus e Grand Ridge's

6544modifications would reduce potential environmental impacts,

6550additional public notice was not required.

65569 2 . Many of the rules that Petitioners contend Grand Ridge

6568failed to comply with are only applicable to projects designed

6578to have a dire ct discharge of a pollutant. Those rules are not

6591applicable here because Grand Ridge's project is not designed to

6601have a direct discharge , and Petitioners did not demonstrate

6610that the proposed project would have a direct discharge.

66199 3 . Based on all the c ompetent substantial evidence

6630submitted at the final hearing and as discussed in the Findings

6641of Fact set forth above, Grand Ridge demonstrated by a

6651preponderance of the evidence that the proposed wastewater

6659treatment plant and sprayfield would comply with all applicable

6668Department standards or rules for a facility of this kin d,

6679except as set forth below. If the permit modifications

6688recommended by the ALJ are made, the proposed facility would

6698comply in all respects.

67029 4 . Florida Administrative Code Rule 62 - 610.417(1)

6712requires that the sprayfield be designed to prevent the entrance

6722of surface runoff. There was competent evidence to support the

6732need for berms to prevent runoff from slopes greater than five

6743percent, but the evidence was not clear that berms w ould be

6755placed to prevent surface runoff into the sprayfield from higher

6765elevations adjacent to the sprayfield where the slope is greater

6775than five percent. Therefore, to comply with Rule

678362 - 610.417(1), the proposed permit would have to be modified to

6795inc lude a condition that berms be placed to prevent surface

6806runoff into the sprayfield from higher elevations adjacent to

6815the sprayfield where the slope is greater than five percent.

68259 5 . Florida Administrative Code Rule 62 - 610.421(3)

6835requires that the wetted area of this proposed sprayfield be set

6846back at least 200 feet from existing or approved potable water

6857supply wells. Because Grand Ridge stated at the hearing that

6867the Stanley and Lewis wells might have already been installed,

6877but did not show that these wells are more than 200 feet from

6890the wetted area of the proposed sprayfield , it failed to show

6901compliance with this rule. However, there is competent

6909substantial evidence in the record that the wetted area of the

6920sprayfield can be moved so that it is 20 0 feet from the property

6934boundaries. In order to show compliance with Rule

694262 - 610.421(3), the proposed permit would have to be modified to

6954require the wetted area of the proposed sprayfield to be set

6965back at least 200 feet from the property boundaries .

69759 6 . Grand Ridge filed a Motion for Costs and Attorneys'

6987Fees pursuant to Subs ections 120.569(2)(e) and Section 120.595,

6996Florida Statutes, arguing that the proceeding was initiated for

7005improper purposes. Grand Ridge presented no evidence of an

7014improper purp ose. Therefore, the Motion for Costs and

7023Attorneys' Fees is denied.

7027RECOMMENDATION

7028Based on the foregoing Findings of Fact and Conclusions of

7038Law, it is

7041RECOMMENDED that the Department of Environmental Protection

7048enter a final order approving t he permit requested by the Town

7060of Grand Ridge , with the following modifications:

70671. The permit should incorporate the conditions described

7075in Respondent's Exhibit 77;

70792. A condition should be added to require that berms be

7090placed to prevent surface runoff into th e sprayfield from higher

7101elevations adjacent to the sprayfield where the s lope is greater

7112than five percent ;

71153. A condition should be added to require the wetted area

7126of the sprayfield to be set back at least 200 feet from the

7139property boundaries ;

71414. The permitted capacity of the land application system

7150should be reduced to .205 mgd; and

71575. An investigation should be made to find the well

7167referred to by Mr. Gilley and, if it is found, to properly

7179abandon the well or take other appropriate action so that the

7190well does not impair the function of the land application

7200system.

7201DONE AND ENT ERED this 8th day of February , 2008 , in

7212Tallahassee, Leon County, Florida.

7216S

7217BRAM D. E. CANTER

7221Administrative Law Judge

7224Division of Adminis trative Hearings

7229The DeSoto Building

72321230 Apalachee Parkway

7235Tallahassee, Florida 32399 - 3060

7240(850) 488 - 9675 SUNCOM 278 - 9675

7248Fax Filing (850) 921 - 6847

7254www.doah.state.fl.us

7255Filed with the Clerk of the

7261Division of Administrative Hearings

7265this 8th day of Fe bruary , 2008 .

7273ENDNOTE S

72751/ Petitioner Quillon Yon applies about 300 pounds per acre each

7286year to his property south of the project site.

72952/ All references are to 2007 Florida Statutes, unless otherwise

7305indicated.

73063/ Petitioners do not use Dickson Ba y for fishing or for any

7319other purpose. Therefore, the alleged potential for the

7327proposed project to adversely impact Dickson Bay does not affect

7337any substantial interest of Petitioners.

7342COPIES FURNISHED :

7345Michael W. Sole, Secretary

7349Department of Enviro nmental Protection

7354Douglas Building, Mail Station 35

73593900 Commonwealth Boulevard

7362Tallahassee, Florida 32399 - 3000

7367Tom Beason, General Counsel

7371Department of Environmental Protection

7375Douglas Building, Mail Station 35

73803900 Commonwealth Boulevard

7383Tallahassee, Florida 32399 - 3000

7388Lea Crandall, Agency Clerk

7392Department of Environmental Protection

7396Douglas Building, Mail Station 35

74013900 Commonwealth Boulevard

7404Tallahassee, Florida 32399 - 3000

7409Kenneth J. Plante, Esquire

7413Tana D. Storey, Esquire

7417B rewton Plante, P.A.

7421225 South Adams Street, Suite 250

7427Tallahassee, Florida 32301

7430Timothy P. Atkinson, Esquire

7434Gavin D. Burgess, Esquire

7438Oertel, Fernandez, Cole and

7442Bryant , P.A.

7444Post Office Box 1110

7448Tallahassee, Florida 32302 - 1110

7453Nona R. Schaffner, Esquire

7457Department of Environmental Protection

74613900 Commonwealth Boulevard, Mail Station 35

7467Tallahassee, Florida 32399 - 3000

7472NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

7478All parties have the right to submit written exceptions within

748815 days from the date of this Recommended Order . Any exceptions

7500to this Recommended Order should be filed with the agency that

7511will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 04/03/2008
Proceedings: Order Re-opening Case for Limited Purpose of Addressing the Renewed Motion for Attorney`s Fees and Costs.
PDF:
Date: 03/24/2008
Proceedings: Final Order filed.
PDF:
Date: 03/24/2008
Proceedings: Petitioners` Response to the Town of Grand Ridge`s Renewed Motion for Costs and Attorneys` Fees filed.
PDF:
Date: 03/24/2008
Proceedings: Petitioners` Exceptions to Recommended Order filed.
PDF:
Date: 03/24/2008
Proceedings: Department of Environmental Protection`s Response to Petitioners` Exceptions to Recommended Order filed.
PDF:
Date: 03/24/2008
Proceedings: Respondent Grand Ridge`s Response to Petitioners` Exceptions to Recommended Order filed.
PDF:
Date: 03/20/2008
Proceedings: Agency Final Order
PDF:
Date: 03/14/2008
Proceedings: Renewed Motion for Costs and Attorneys` Fees filed.
PDF:
Date: 02/25/2008
Proceedings: Petitioners` Exceptions to Recommended Order filed.
PDF:
Date: 02/25/2008
Proceedings: Petitioner`s Exceptions to Recommended Order filed.
PDF:
Date: 02/08/2008
Proceedings: Recommended Order
PDF:
Date: 02/08/2008
Proceedings: Recommended Order (hearing held September 21, 2007). CASE CLOSED.
PDF:
Date: 02/08/2008
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 12/13/2007
Proceedings: Notice of Unavailability for Department of Environmental Protection filed.
PDF:
Date: 10/25/2007
Proceedings: DEP`s Proposed Recommended Order filed.
PDF:
Date: 10/25/2007
Proceedings: Respondent Town of Grand Ridge`s Proposed Recommended Order filed.
PDF:
Date: 10/25/2007
Proceedings: Petitioner`s Proposed Recommended Order filed.
PDF:
Date: 10/24/2007
Proceedings: Petitioners` Response to the Town of Grand Ridge`s Motion for Costs and Attorneys` Fees filed.
PDF:
Date: 10/24/2007
Proceedings: Consented Motion to Increase Proposed Recommended Order Page Length Requirement filed.
PDF:
Date: 10/01/2007
Proceedings: Order Granting Extension of Time to File Proposed Recommended Orders (proposed recommended orders to be filed by October 25, 2007).
PDF:
Date: 09/28/2007
Proceedings: Respondent Town of Grand Ridge`s Response to Respondent, Florida Department of Environmental Protection`s Motion to Extend Time for Filing Proposed Recommended Orders filed.
PDF:
Date: 09/28/2007
Proceedings: Respondent Town of Grand Ridge`s Response to Petitioners` Motion to Extend Time for Filing Proposed Recommended Orders filed.
PDF:
Date: 09/28/2007
Proceedings: DEP`s Motion for Extension of Time to File Proposed Recommended Order filed.
PDF:
Date: 09/28/2007
Proceedings: Petitioners` Joint Motion for Extension of Time in Which to File Proposed Recommended Orders filed.
Date: 09/26/2007
Proceedings: Transcript (volumes I through VI) filed.
Date: 09/21/2007
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 09/17/2007
Proceedings: Respondent`s Town of Grand Ridge and FDEP`s Joint Motion in Limine filed.
PDF:
Date: 09/17/2007
Proceedings: Town of Grand Ridge`s Motion for Costs and Attorneys` Fees filed.
Date: 09/13/2007
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 09/13/2007
Proceedings: Petitioners` Joint Notice of Filing filed.
PDF:
Date: 09/13/2007
Proceedings: Respondent, Town of Grand Ridge`s Notice of Filing filed.
PDF:
Date: 09/13/2007
Proceedings: Respondent Town of Grand Ridge`s Response to Petitioners` Joint Motion for Continuance filed.
PDF:
Date: 09/13/2007
Proceedings: Respondent Town of Grand Ridge`s Response to Petitioners` Joint Motion for Continuance filed.
PDF:
Date: 09/12/2007
Proceedings: Notice of Telephonic Hearing filed.
PDF:
Date: 09/12/2007
Proceedings: Petitioner`s Joint Motion for Continuance filed.
PDF:
Date: 09/11/2007
Proceedings: Respondent, Town of Grand Ridge`s Preliminary Witness List filed.
PDF:
Date: 09/11/2007
Proceedings: Respondent, Town of Grand Ridge`s Exhibit List filed.
PDF:
Date: 09/07/2007
Proceedings: Amended Notice of Taking Deposition Duces Tecum (of J. Gilley) filed.
PDF:
Date: 09/07/2007
Proceedings: Amended Notice of Taking Deposition Duces Tecum (of B. Dickson) filed.
PDF:
Date: 09/07/2007
Proceedings: Notice of Cancellation of Taking Deposition Duces Tecum of Louis Cross, III filed.
PDF:
Date: 09/07/2007
Proceedings: Notice of Taking Telephonic Deposition filed.
PDF:
Date: 09/07/2007
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 09/06/2007
Proceedings: Cross-Notice of Taking Deposition (of B. Evans) filed.
PDF:
Date: 09/06/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of V. Weeks) filed.
PDF:
Date: 09/06/2007
Proceedings: Amended Notice of Taking Deposition (amended as to case number only) filed.
PDF:
Date: 09/06/2007
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 09/04/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of B. Dickson) filed.
PDF:
Date: 09/04/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of J. Gilley) filed.
PDF:
Date: 09/04/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of L.Cross, III) filed.
PDF:
Date: 09/04/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of R. Lewis) filed.
PDF:
Date: 09/04/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of D. Clark) filed.
PDF:
Date: 09/04/2007
Proceedings: Notice of Taking Deposition Duces Tecum (of J. Stevenson) filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioners Joint Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioners` Signed Joint Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner Quillon Yon`s Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner, Quillon Yon`s Notice of Signed Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner Kevin Yon`s Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner, Kevin Yon`s Notice of Signed Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioners` Third Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioners` Notice of Signed Third Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner Kevin Yon`s Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner, Kevin Yon`s Notice of Serving Signed Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner`s Quillon Yon`s Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioner`s Quillon Yon`s Notice of Serving Signed Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioners` Third Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/29/2007
Proceedings: Petitioners` Unsigned Third Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/28/2007
Proceedings: Amended Notice of Taking Deposition filed.
Date: 08/28/2007
Proceedings: CASE STATUS: Pre-Hearing Conference Held.
PDF:
Date: 08/28/2007
Proceedings: Petitioner`s Joint Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/28/2007
Proceedings: Petitioners` Unsigned Joint Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/27/2007
Proceedings: Notice of Taking Depositions (2) filed.
PDF:
Date: 08/23/2007
Proceedings: Notice of Telephonic Statust Conference filed.
PDF:
Date: 08/23/2007
Proceedings: Notice of Taking Deposition, T. Montgomery filed.
PDF:
Date: 08/22/2007
Proceedings: Petitioner Quillon Yon`s Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/22/2007
Proceedings: Petitioner Quillon Yon`s Notice of Serving Unsigned Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/22/2007
Proceedings: Petitioner Kevin Yon`s Supplemental Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/22/2007
Proceedings: Petitioner Kevin Yon`s Notice of Serving Unsigned Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 08/17/2007
Proceedings: Order on Motion for Reconsideration.
PDF:
Date: 08/16/2007
Proceedings: Petitioners` Joint Motion for Reconsideration filed.
PDF:
Date: 08/15/2007
Proceedings: Amended Notice of Taking Depositions Duces Tecum filed.
PDF:
Date: 08/14/2007
Proceedings: Petitioners` Joint Motion for Protective Order filed.
PDF:
Date: 08/13/2007
Proceedings: Petitioners` Joint Response to Respondent Town of Grand Ridge`s Motion to Compel and Alternatively for Additional Interrogatories and for Attorney`s Fees filed.
PDF:
Date: 08/13/2007
Proceedings: Respondent, Town of Grand Ridge`s Notice of Service of Answers to Petitioner, Kevin Yon`s First Set of Interrogatories filed.
PDF:
Date: 08/13/2007
Proceedings: Respondent, Town of Grand Ridge`s Notice of Service of Answers to Petitioner, Kevin Yon`s Request for Production filed.
PDF:
Date: 08/13/2007
Proceedings: Order (Motion to Compel is granted; Town`s request for attorney`s fees is denied).
PDF:
Date: 08/09/2007
Proceedings: Notice of Taking Depositions Duces Tecum filed.
PDF:
Date: 08/02/2007
Proceedings: Notice of Unavailability filed.
PDF:
Date: 08/01/2007
Proceedings: Notice of New Contact Information filed.
PDF:
Date: 07/31/2007
Proceedings: Motion to Compel and Alternatively for Additional Interrogatories and for Attorney`s Fees filed.
PDF:
Date: 07/26/2007
Proceedings: Petitioner Kevin Yon`s Notice of Serving Unsigned Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 07/26/2007
Proceedings: Petitioner Quillon Yon`s Notice of Serving Unsigned Answers to Respondent Town of Grand Ridge`s First Set of Interrogatories filed.
PDF:
Date: 07/23/2007
Proceedings: DEP`s Notice of Serving Answers to Petitioner Kevin Yon`s Interrogatories filed.
PDF:
Date: 07/12/2007
Proceedings: Petitioner Kevin Yon`s Response to Respondent Town of Grand Ridge`s First Request for Production filed.
PDF:
Date: 07/12/2007
Proceedings: Petitioner Quillon Yon`s Response to Respondent Town of Grand Ridge`s First Request for Production filed.
PDF:
Date: 07/12/2007
Proceedings: Petitioner Kevin Yon`s Response to Respondent Town of Grand Ridge`s First Request for Production filed.
PDF:
Date: 06/22/2007
Proceedings: Amended Notice of Hearing (hearing set for September 17 through 20, 2007; 10:00 a.m.; Tallahassee, FL; amended as to location and time of hearing).
PDF:
Date: 06/22/2007
Proceedings: Petitioners` Response to Order filed.
PDF:
Date: 06/22/2007
Proceedings: Notice of Service of Petitioner Kevin Yon`s First Set of Interrogatories to Respondent, Town of Grand Ridge filed.
PDF:
Date: 06/22/2007
Proceedings: Petitioner Kevin Yon`s First Set of Interrogatories to Respondent, Town of Grand Ridge filed.
PDF:
Date: 06/21/2007
Proceedings: Notice of Service of Petitioenr Kevin Yon`s Request for Production of Documetns to Respondent, Town of Grand Ridge filed.
PDF:
Date: 06/21/2007
Proceedings: Petitioner Kevin Yon`s Request for Production of Documents to Respondent, Town of Grand Ridge filed.
PDF:
Date: 06/21/2007
Proceedings: Notice of Service of Petitioner Kevin Yon`s Request for Production of Documents to Respondent, Department of Environmental Protection filed.
PDF:
Date: 06/21/2007
Proceedings: Petitioner Kevin Yon`s Request for Production of Documents to Respondent, Department of Environmental Protection filed.
PDF:
Date: 06/21/2007
Proceedings: Notice of Service of Petitioner Kevin Yon`s First Set of Interrogatories to Respondent, Department of Environmental Protection filed.
PDF:
Date: 06/21/2007
Proceedings: Petitioner Kevin Yon`s First Set of Interrogatories to Respondent Department of Environmental Protection filed.
PDF:
Date: 06/13/2007
Proceedings: (Amended) Respondent, Town of Grand Ridge`s Notice of Service of First Set of Interrogatories to Petitinoer, Kevin Yon filed.
PDF:
Date: 06/13/2007
Proceedings: (Amended) Respondent, Town of Grand Ridge`s Notice of Service of First Set of Interrogatories to Petitioner, Quillon Yon filed.
PDF:
Date: 06/13/2007
Proceedings: (Amended) Notice of Service of Respondent, Town of Grand Ridge`s First Request for Production of Documents to Petitioner, Kevin Yon filed.
PDF:
Date: 06/13/2007
Proceedings: (Amended) Notice of Service of Respondent, Town of Grand Ridge`s First Request for Production of Documents to Petitioner, Quillon Yon filed.
PDF:
Date: 06/13/2007
Proceedings: (Amended) Notice of Service of Respondent, Town of Grand Ridge`s First Request for Production of Documents to Petitioner, Quillon Yon filed.
PDF:
Date: 06/12/2007
Proceedings: Notice of Service of Respondent, Town of Grand Ridge`s First Request for Production of Documents to Petitioner Quillon Yon filed.
PDF:
Date: 06/12/2007
Proceedings: Notice of Service of Respondent, Town of Grand Ridge`s First Request for Production of Documents to Petitioner, Kevin Yon filed.
PDF:
Date: 06/12/2007
Proceedings: Respondent, Town of Grand Ridge`s Notice of Service of First Set Interrogatories to Petitioner, Quillon Yon filed.
PDF:
Date: 06/12/2007
Proceedings: Respondent, Town of Grand Ridge`s Notice of Service of First Set of Interrogatories to Petitioner, Kevin Yon filed.
PDF:
Date: 06/12/2007
Proceedings: Order (parties shall confer with the other parties and inform the undersigned in writing no later than June 22, 2007, of the location for the hearing that would be most convenient to the parties).
PDF:
Date: 06/12/2007
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 06/12/2007
Proceedings: Notice of Hearing (hearing set for September 17 through 20, 2007).
PDF:
Date: 06/11/2007
Proceedings: Notice of Appearance (filed by T. Atkinson).
PDF:
Date: 06/08/2007
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
PDF:
Date: 06/08/2007
Proceedings: Notice of Substitution of Counsel for Department of Environmental Protection (filed by N. Schaffner).
PDF:
Date: 05/30/2007
Proceedings: (Proposed) Domestic Wastewater Facility Permit filed.
PDF:
Date: 05/30/2007
Proceedings: Notice of Intent to Issue Permit filed.
PDF:
Date: 05/30/2007
Proceedings: Intent to Issue filed.
PDF:
Date: 05/30/2007
Proceedings: Petition for Administrative Hearing filed.
PDF:
Date: 05/30/2007
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.
PDF:
Date: 05/30/2007
Proceedings: Initial Order.

Case Information

Judge:
BRAM D. E. CANTER
Date Filed:
05/30/2007
Date Assignment:
05/30/2007
Last Docket Entry:
04/03/2008
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Counsels

Related Florida Statute(s) (3):