07-003151
Peter &Quot;Panagioti&Quot; Tsolkas, Palm Beach County Environmental Coalition, Alexandria Larson, Bonnie Brooks, Danny Brooks, And Peter Shulz vs.
Gulfstream Natural Gas System, L.L.C. And Department Of Environmental Protection
Status: Closed
Recommended Order on Friday, February 8, 2008.
Recommended Order on Friday, February 8, 2008.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8PETER "PANAGIOTI" TSOLKAS, PALM )
13BEACH COUNTY ENVIRONMENTAL )
17COALITION, ALEXANDRIA LARSON, )
21BONNIE BROOKS, DANNY BROOKS, )
26and PETER SHULZ, )
30)
31Petitioners, )
33)
34vs. ) Case No. 07 - 3151
41)
42GULFSTREAM NATURAL GAS SYSTEM, )
47L.L.C. and DEPARTMENT OF )
52ENVIRONMENTAL PROTECTION, )
55)
56Respondents. )
58)
59RECOMMENDED ORDER
61A duly - noticed final hearing was held in this case by
73Administrative Law Judge T. Ken t Wetherell, II, on January 8 - 10,
862008, in West Palm Beach, Florida.
92APPEARANCES
93For Petitioners Peter Panagioti Tsolkas, Palm Beach
100County Environmental Coalition, Bonnie Brooks, Danny
106Brooks, and Peter Shulz:
110Barry M. Silver, Esquire
1141200 S outh Rogers Circle, Suite 8
121Boca Raton, Florida 33487 - 5703
127For Petitioner Alexandria Larson: 1
132Alexandria Larson, pro se
13616933 West Harlena Drive
140Loxahatchee, Florida 33470
143For Respondent Gulfstream Natural Gas System, L . L . C . :
156Richard S. Brightman, Esquire
160Hopping, Green & Sams, P.A.
165Post Office Box 6526
169Tallahassee, Florida 32314 - 6526
174For Respondent Department of Environmental Protection:
180Francine M. Ffolkes, Esquire
184Ronald W. Hoenstine, III, Esquire
189Department of Environmental Protection
193The Douglas Building, Mail Station 35
1993900 Commonwealth Boulevard
202Tallahassee, Florida 32399 - 3000
207STATEMENT OF THE ISSUE
211The issue is whether the Department of Environmental
219Protection should issue Enviro nmental Resource Permit No. 50 -
2290269698 - 002.
232PRELIMINARY STATEMENT
234On June 7, 2007, the Department of Environmental Protection
243(Department) gave notice of its intent to issue Environmental
252Resource Permit (ERP) No. 50 - 0269698 - 001 (the initial permit) to
265Gul fstream Natural Gas System, L . L . C . (Gulfstream). The initial
279permit authorized the installation of a 30 - inch natural gas
290pipeline across 34.30 miles in Martin and Palm Beach Counties.
300On June 28, 2007, a petition for administrative hearing was
310filed by Pe ter Panagioti Tsolkas and the Palm Beach County
321Environmental Coalition (PBCEC). The petition challenged the
328initial permit on a variety of grounds.
335On July 11, 2007, the Department referred the petition to
345the Division of Administrative Hearings (DOAH) for the
353assignment of an Administrative Law Judge (ALJ) to conduct the
363hearing requested by Mr. Tsolkas and the PBCEC. The referral
373was received by DOAH on July 12, 2007.
381The final hearing was initially scheduled for October 2 - 5,
3922007, but on September 1 2, 2007, the case was placed in abeyance
405upon Gulfstreams motion so that the Department could consider
414Gulfstreams revised application modifying the pipeline route.
421On October 12, 2007, the Department gave notice of its
431intent to approve ERP No. 50 - 02696 98 - 002 (the proposed permit)
445for the revised pipeline route. The proposed permit authorizes
454the installation of a 30 - inch natural gas pipeline across 34.26
466miles in Martin and Palm Beach Counties.
473On November 2, 2007, a petition for hearing was filed by
484M r. Tsolkas, the PBCEC, Alexandria Larson, Bonnie Brooks, Danny
494Brooks, and Peter Shulz (collectively, Petitioners). The
501petition challenges the proposed permit on a variety of grounds.
511A number of the allegations in the petition were directed
521to the pot ential impacts of a power plant project that will be
534served by the proposed pipeline. Those allegations were
542stricken as irrelevant under the ERP program. See Orders
551entered on December 5, 2007, and December 27, 2007 . 2 Petitioners
563were given an opportun ity to make written proffers of evidence
574on the excluded issues, but they did not do so.
584The final hearing was held on January 8 - 10, 2008. 3 At the
598hearing, Gulfstream presented the testimony of Al Taylor, Chris
607Brown (expert in pipeline design, engineerin g, and construction
616methods), Kimberly Rhodes - Edelstein (expert in natural gas
625pipeline permitting and impact assessment), Kristoffer Bowman
632(expert in wetland and wildlife ecology, including protected
640species), Dr. Kate Hoffman (expert in the analysis of potential
650impacts to archaeological resources), and Dr. Gregory Hempen
658(expert in vibration analysis, blast mitigation, and soil
666analysis); the Department presented the testimony of Jennifer
674Smith; and Petitioners presented the testimony of Mr. Shulz, Mr.
684Tsolkas, James Schuette, Ms. Larson, and Dr. William Louda
693(expert in biological sciences, environmental sciences, ecology,
700and organic geochemistry). The following exhibits were received
708into evidence: Exhibits JT - 1 through JT - 3, AT - 1 through AT - 3,
725CB - 1 through CB - 3, KR - 1, KB - 1, KB - 2, KH - 1 through KH - 5, GH - 1,
751GH - 2, DEP - 2, and Petitioners Exhibits 1, 2, and 4 through 6.
766Petitioners Exhibit 3 was offered, but not received. Official
775recognition was taken of Sections 373.413, 373.414, 373.4141,
783373.416, 3 73.417, 373.421, 373.4211,373.422, 373.423, 373.426,
791373.427, Florida Statutes 4 ; the rules in Florida Administrative
800Code Chapter 40E that have been adopted by reference by the
811Department 5 ; and the August 1995 version of the Basis of Review
823for Environment al Resource Permit Applications Within the South
832Florida Water Management District (BOR).
837The six - volume Transcript of the final hearing was filed on
849January 16, 2008. The parties were given until January 31,
8592008, to file proposed recommended orders (PRO s). Gulfstream
868and the Department filed PROs on January 31, 2008, and the
879Petitioners represented by Mr. Silver filed a Proposed Final
888Order on that same date. Ms. Larson did not file a PRO. The
901parties post - hearing filings have been given due consid eration.
912FINDINGS OF FACT
915A. Parties
9171. Mr. Tsolkas is a resident of Lake Worth, which is in
929southeastern Palm Beach County. He is the co - chair of the
941PBCEC, and he uses the Dupuis and J.W. Corbett Wildlife
951Management Areas (WMAs) for various recreatio nal and peace of
961mind activities. He is concerned that the proposed pipeline
970will adversely impact his enjoyment of the WMAs. 6
9792. PBCEC is an organization comprised of environmental
987groups and individuals that are concerned about the environment
996and qu ality of life in Palm Beach County. PBCEC has undertaken
1008public outreach, protests, and other advocacy efforts targeting
1016the West Coast Energy Center (WCEC) that will be served by the
1028proposed pipeline. No evidence was presented regarding PBCECs
1036members hip numbers.
10393. Mr. Shulz is a resident of Hope Sound, which is on the
1052eastern coast of Martin County. He is a member of the PBCEC,
1064and he uses the Dupuis and J.W. Corbett WMAs for various
1075recreational activities. He is concerned that the proposed
1083pipel ine will adversely impact his enjoyment of the WMAs. He
1094also has concerns regarding the safety of the proposed pipeline.
11044. Ms. Larson in a resident of the Loxahatchee area in
1115western Palm Beach County. She uses the Dupuis and J.W. Corbett
1126WMAs for vari ous recreational activities, and she is concerned
1136that the proposed pipeline will adversely impact her enjoyment
1145of the WMAs. She also has concerns regarding the safety of the
1157proposed pipeline.
11595. Bonnie Brooks and Danny Brooks were not present at the
1170f inal hearing, and the record contains no evidence about these
1181Petitioners.
11826. Gulfstream is a joint venture owned by Spectra Energy
1192Corporation and the Williams Companies and is in the business of
1203transporting natural gas through pipelines. Gulfstream is a
1211Dela ware limited liability company with its principle office in
1221Tampa.
12227. The Department is the state agency responsible for
1231regulating construction activities in surface waters and
1238wetlands under the ERP program in conjunction with the water
1248managemen t districts. The Department is responsible for taking
1257final agency action on the proposed permit at issue in this
1268case.
1269B. The Proposed Pipeline
1273(1) Generally
12758. The proposed pipeline is a 34.26 - mile, 30 - inch diameter
1288natural gas pipeline.
12919. The pro posed pipeline starts in western Martin County,
1301slightly northwest of Indiantown, and ends in western Palm Beach
1311County at the site of the WCEC being constructed by Florida
1322Power and Light Company (FPL), just north of Twenty Mile Bend.
133310. The proposed p ipeline is the third phase a pipeline
1344that runs from natural gas supply areas on the coasts of Alabama
1356and Mississippi across the Gulf of Mexico into central and
1366southern Florida. The entire pipeline is 691 miles long, with
1376approximately 240 miles in Flor ida.
138211. The first phase of the pipeline began operatin g in May
13942002, and the second phase began operatin g in February 2005.
1405The pipeline currently transports approximately 1.1 billion
1412cubic feet per day of natural gas into Florida.
142112. The proposed pipeline begins at the existing
1429Gulfstream Station 712, which is referred to as milepost (MP)
14390.00. It runs in a southerly direction along the east side of
1451the L - 65 Canal, crossing the St. Lucie Canal (at MP 6.3 4 ) and
1467continuing to the Martin/Palm Beach c ounty line (at MP 8.50);
1478then runs east to a point west of the Dupuis WMA (at MP 10.20)
1492and runs south along the western boundary of the Dupuis WMA
1503adjacent to an existing power line right - of - way; then turns
1516southeast (at MP 12.14) and runs on the east sid e of the L - 8
1532Canal; and then turns due south (at MP 30.08) and runs in an
1545existing FPL transmission line right - of - way to its terminus on
1558the WCEC site (at MP 34.26).
156413. Gulfstream acquired a non - exclusive pipeline easement
1573from the South Florida Water M anagement District (SFWMD), which
1583authorizes it to install the proposed pipeline within the L - 8
1595and L - 65 canal rights - of - way. The agreement limits the width of
1611the permanent easement to 20 feet, but it provides for 95 - foot
1624wide temporary construction ease ments along the pipeline route.
1633The agreement requires the proposed pipeline to be installed at
1643least three feet below the surface.
164914. The proposed pipeline crosses 121 artificial water
1657bodies. It does not cross any natural water bodies.
166615. Only thr ee of the crossed water bodies - the L - 8
1681Canal, the L - 65 Canal, and the St. Lucie Canal -- are navigable.
1695The pipeline crosses the L - 65 Canal once (at MP 0.11); the St.
1709Lucie Canal once (at MP 6.34); and the L - 8 Canal three times (at
1724MP 12.31, MP 13.28 a nd MP 29.72). The other crossed water
1736bodies are agricultural ditches.
174016. The active land uses along the pipeline route are
1750primarily agricultural in nature, consisting of sugar cane
1758fields and sod farms. The passive land uses include the Dupuis
1769and J.W. Corbett WMAs, which are state - owned conservation areas.
178017. There is an existing mining operation adjacent to the
1790pipeline route in the vicinity of MP 32.80. The mining company,
1801Palm Beach Aggregates (PBA), uses blasting to produce limestone
1810aggrega te and sand. The PBA property line is approximately 290
1821feet from the proposed pipeline at its closest point, but the
1832actual blasting is as much as 500 feet to thousands of feet
1844away from the proposed pipeline.
184918. The route of the proposed pipeline w as revised in
1860August 2007 at the request of the SFWMD and FPL.
187019. The initial pipeline route was along the west sides of
1881the L - 65 and L - 8 Canals. SFWMD requested that the route be
1896shifted to the east side of the canals in order to accommodate
1908potential future canal expansion.
191220. The initial pipeline route was along the eastern edge
1922of the FPL transmission line right - of - way. FPL requested that
1935the route be shifted to the center of the right - of - way in order
1951to accommodate future expansion of the trans mission line
1960facilities.
196121. The revised pipeline route has fewer impacts than the
1971initial route. For example, the initial route had 224 water
1981body crossings, and two wetland crossings, whereas the revised
1990route has only 121 water body crossings, and no wetland
2000crossings.
200122. Gulfstream submitted extensive documentation in
2007support of the revised pipeline route. After reviewing that
2016documentation, the Department gave notice of its intent to issue
2026the proposed permit for the revised pipeline route.
203423 . Notice of the Departments decision was published in
2044newspapers of general circulation -- the Stuart News in Martin
2054County and in the Palm Beach Post in Palm Beach County -- on or
2068about October 17, 2007.
2072(2) Design and Construction Methods
207724. Federa l law prescribes minimum pipeline design
2085criteria, including standards for pipe wall thickness and the
2094testing of pipeline welds.
209825. Gulfstream took a compliance plus approach in the
2107design of the proposed pipeline by going above and beyond the
2118minim um requirements in federal law in several respects.
212726. First, the pipe used in the proposed pipeline will
2137meet or exceed the wall thickness requirements in federal law.
2147Thicker - walled pipe will used in areas where there is a
2159potential for external forc es to affect the pipe, such as under
2171road crossings and in the areas adjacent to PBAs blasting
2181operations.
218227. Second, Gulfstream will x - ray 100 percent of the
2193welded joints on the proposed pipeline, which far exceeds the
2203requirement in federal law that 10 percent of the welds be
2214inspected.
221528. Third, Gulfstream will hydrostatically test the
2222prop os ed pipeline for leaks after construction is complete and
2233before the pipeline is put into operation. Hydrostatic testing
2242involves filling the pipeline with wa ter under pressure higher
2252than the pressure under which the pipeline will operate. A drop
2263in pressure during the test is an indication of a leak in the
2276pipeline, which will be fixed before the pipeline is put into
2287operation.
228829. Fourth, Gulfstream will coat the entire proposed
2296pipeline with an anti - corrosive substance - fusion bond epoxy -
2309 and the pipeline will also be induced with a small DC current
2322in a process known as cathodic protection. These measures will
2332significantly reduce, if not eliminate potential corrosion on
2340the proposed pipeline.
234330. Gulfstream will use four construction methods to cross
2352the water bodies within the pipeline route: the isolation plate
2362open cut method; the sheet pile wet open cut method; the
2373horizontal directional dril l (HDD) method; and the conventional
2382bore method.
238431. The isolation plate open cut method will be used at
2395each minor and intermediate water body crossing, except for
2404those associated with the HDD method.
241032. The isolation plate open cut method involves the
2419installation of steel plates upstream and downstream of the
2428proposed crossing. The area between the plates is pumped out so
2439that it is essentially dry. A trench is dug in the dry area and
2453the pipeline is placed in the trench. The trench is then
2464back filled and stabilized with at least five feet of cover, and
2476then the plates are removed and the water flows back into the
2488area .
249033. The sheet pile wet open cut method is similar to the
2502isolation plate open cut method, except that it allows water to
2513contin ue to flow in the center of the water body during
2525installation of the pipe . This method will be used for the
2537crossing of the L - 65 Canal, the second and third crossings of
2550the L - 8 Canal, and the crossings of the forebays along the L - 8
2566Canal.
256734. Turbidity curtains or sediment barrier baffle systems
2575will be installed upstream and downstream of the areas where the
2586isolation plate open cut and the sheet pile wet open cut methods
2598are used in order to control turbidity.
260535. The HDD method will be used to cr oss the St. Lucie
2618Canal and the Couse Midden archaeological site, as well as at
2629the first crossing of the L - 8 Canal.
263836. The HDD method involves the boring of a horizontal
2648tunnel along a pre - determined path under the surface feature to
2660be avoided and the n pulling a pre - fabricated section of pipe
2673through the tunnel. The pipe installed using this method will
2683be 35 to 40 feet below the surface feature to be avoided.
269537. The conventional bore method will be used to cross the
2706railroad track and adjacent agr icultural ditch at MP 8.46, as
2717well as the wetland at MP 16.65.
272438. The conventional bore method involves the excavation
2732of bore pits on both sides of the feature to be crossed. A
2745tunnel is bored under the feature and then a section of pipe is
2758pulled th rough the tunnel. The pipe installed using this method
2769will be 10 feet under the railroad track, which is greater than
2781the depth required by federal law, and will be at least five
2793feet under the wetland.
2797C. Environmental Issues
2800(1) Wetlands and Vegetati on
280539. The proposed pipeline will not adversely impact the
2814current condition or relative functions of any wetlands. All of
2824the wetlands within the proposed pipeline route have been
2833avoided.
283440. The proposed pipeline will be installed under one
2843jurisdi ctional wetland (at MP 16.65) using the conventional bore
2853method described above. That wetland is a disturbed, low -
2863quality wetland within the actively managed L - 8 Canal right - of -
2877way. It is routinely mowed and provides no significant water
2887quality functio n or habitat value.
289341. Gulfstream will install erosion control devices in
2901areas where the pipeline construction corridor abuts wetlands.
2909The erosion control devices will be in place and functional
2919prior to commencement of earth disturbance. Gulfstream will
2927utilize reinforced sediment barriers in lieu of standard
2935sediment barriers, and increased buffers are proposed in areas
2944where construction abuts wetlands on the Dupuis and J.W. Corbett
2954WMAs.
295542. The proposed pipeline will not adversely impact liste d
2965plant species. No listed plant species were observed or are
2975likely to occur within the proposed pipeline route, which
2984consists of disturbed rights - of - way and agricultural areas .
299643. Vegetated areas that are disturbed during the
3004installation of the pro posed pipeline will be re - vegetated
3015immediately after construction is complete. Impacts to these
3023areas will be minor and temporary.
302944. The disturbed areas will be re - vegetated with
3039herbaceous cover such as bahia grass, common bermuda grass, or
3049annual r yegrass. The areas will be monitored for two growing
3060seasons to determine the success of the revegetation.
306845. The proposed pipeline route includes exotic and
3076nuisance plant species, including Brazilian pepper, cogon grass,
3084water hyacinth, and water let tuce.
309046. The installation of the proposed pipeline has the
3099potential to spread exotic and nuisance species if appropriate
3108precautions are not taken during construction.
311447. Gulfstream has developed, and will implement an
3122Exotic, Nuisance, and Invasive Plant Management Plan to minimize
3131the potential for spreading exotic and nuisance species. The
3140plan requires, among other things, environmental training of
3148construction personnel and routine monitoring during all phases
3156of construction, clean up, and res toration. The plan also
3166includes procedures for onsite disposal of exotic and nuisance
3175species disturbed during construction and the cleaning of
3183vehicles and equipment to ensure that exotic and nuisance
3192species are not inadvertently transported to uncolo nized areas.
320148. The proposed permit includes a specific condition that
3210requires Gulfstream to monitor and maintain the proposed
3218pipeline route - a total of 214.85 acres - free of exotic and
3233nuisance species for a period of five years after construction
3243of the pipeline is complete.
324849. The easement agreement between Gulfstream and SFWMD
3256requires Gulfstream to relocate approximately 158 native cabbage
3264palm trees within the construction corridor to suitable
3272locations within the west right of way of L - 8 w ithin the Palm
3287Beach County Department of Environmental Resources Management
3294wildlife corridor.
3296(2) Dupuis and J.W. Corbett WMAs
330250. The proposed pipeline route runs along the western
3311boundary of the Dupuis WMA for approximately seven miles
3320(between MP 13.30 and MP 20.18), and it runs along the western
3332boundary of the J.W. Corbett WMA for approximately 9.5 miles
3342(between MP 20.18 and MP 29.70).
334851. The revised pipeline route puts the pipeline closer to
3358the boundaries of the WMAs than did the initial p ipeline route
3370because the route was moved from the west side of the canals to
3383the east side of the canals.
338952. The Fish and Wildlife Conservation Commission (FWCC)
3397manage s the Dupuis and J.W. Corbett WMAs. The WMAs, which
3408include extensive wetlands and virtually no development, are
3416used for a variety of public recreation purposes.
342453. The proposed pipeline crosses approximately 3.67 acres
3432of the J.W. Corbett WMA. This land, although technically within
3442the boundaries of WMA, is subject to an easement fo r the L - 8
3457Canal and has been actively managed by SFWMD for canal purposes
3468for at least the past 55 years.
347554. Gulfstream is in the process of acquiring
3483approximately 3.75 acres of privately - held land within the
3493boundaries of the J.W. Corbett WMA that it w ill donate to the
3506State in accordance with the linear facility policy 7 as
3516mitigation for the crossing of the J.W. Corbett WMA.
352555. The parcel that Gulfstream is in the process of
3535acquiring contains oak trees, pine trees, and cypress trees. It
3545also cont ains the last Indian mound within the J.W. Corbett WMA
3557that is not already in public ownership.
356456. Gulfstream will install reinforced sediment barriers
3571and increase buffers adjacent to the wetlands on the WMAs in
3582order to prevent impacts to those areas d uring construction.
359257. The proposed pipeline will not have any direct or
3602indirect impact on the Dupuis WMA.
360858. The proposed pipelines only impact on the J.W.
3617Corbett WMA is the direct impact to the 3.67 acres of the WMA
3630that the pipeline will cross.
363559. This impact is negligible in light of the size of the
3647J.W. Corbett WMA - approximately 60,000 acres - and in light
3661of the fact that the portion of the J.W. Corbett WMA that is
3674being crossed is disturbed land that has been actively used for
3685canal p urposes for over 55 years. Moreover, this impact will be
3697mitigated in accordance with the linear facility policy.
370560. Any adverse impacts to the aesthetic qualities of the
3715Dupuis and J.W. Corbett WMAs will be temporary in nature during
3726construction. Once construction is complete, the pipeline will
3734not be visible from the surface.
3740(3) Wildlife
374261. The proposed pipeline route consists of disturbed
3750agricultural areas and canal and utility rights - of - way, which
3762are low quality habitat for listed specie s and other wildlife.
377362. The proposed permit is not likey to have any adverse
3784impact on wildlife, including listed species, or their habitat.
379363. Gulfstream conducted extensive wildlife surveys during
3800the ERP application process. The survey corridor extended
3808beyond 150 feet to either side of the pipeline centerline for a
3820minimum survey width of 300 feet, and also included the
3831temporary work space areas, contractor yards, and aboveground
3839facilities associated with the pipeline.
384464. The listed speci es whose potential habitat includes
3853the pipeline corridor are the wood stork, the Southeastern
3862American kestrel, the crested caracara, the bald eagle, and the
3872gopher tortoise and its commensal species.
387865. The wood stork uses areas within and along the
3888p roposed pipeline corridor for resting, but not nesting or
3898foraging.
389966. Southeastern American kestrel and crested caracara
3906habitat exists adjacent to the first four miles of the proposed
3917pipeline corridor. There is no habitat within the pipeline
3926corrido r itself, and no kestrels or caracaras were observed in
3937the adjacent habitat.
394067. The nearest bald eagle nest is approximately 2,550
3950feet from the proposed pipeline route, which is well beyond the
3961660 - foot regulatory protection zone. The nest is within a
3972heavily wooded area of the Dupuis WMA and is not visible from
3984the pipeline route.
398768. A total of 18 gopher tortoise burrows were observed
3997within the proposed p ipeline route. The burrows are located
4007along the berm of the L - 65 Canal between MP 0.04 and MP 1.44.
402269. Relocation is FWCCs preferred method for avoiding
4030impacts to gopher tortoises that inhabit a construction area.
4039The gopher tortoises are moved to another area during
4048construction, but they are free to return to the area from which
4060they wer e relocated after construction is completed.
406870. In December 2007, FWCC issued a permit (No. WR07530a)
4078that allows Gulfstream to capture and relocate up to 18 gopher
4089tortoises. The permit also allows Gulfstream to capture and
4098relocate commensal species , such as the indigo snake, Florida
4107mouse, and gopher frog.
411171. The FWCC permit addresses the listed species concerns
4120raised by James Schuette, the FWCC employee who provided
4129comments to the Department on the ERP application and who
4139testified at the fina l hearing in Petitioners case - in - chief. 8
415372. Gulfstream successfully used gopher tortoise
4159relocation during construction of the first two phases of the
4169pipeline project.
417173. Gulfstream will conduct pre - construction surveys to
4180ensure that no listed spe cies have moved into the proposed
4191pipeline route. Qualified environmental inspectors will be on -
4200site on a daily basis during construction to look for listed
4211species and to monitor compliance with the FWCC permit.
4220(4) Water Quality
422374. The proposed pipe line will have no permanent adverse
4233impacts on water quality.
423775. The construction of the pipeline may have minor
4246temporary impacts on water quality through increased turbidity
4254in the water bodies crossed by the proposed pipeline.
426376. Gulfstream will u se turbidity curtains and other
4272barriers to control turbidity and minimize impacts to water
4281quality, and it is required to closely monitor water quality
4291during construction.
429377. The proposed permit establishes a turbidity standard -
4302- 29 Nephelometric Tur bidity Units (NTUs) above backgrou nd -
4314that must be maintained outside of the 150 meter mixing zone
4325established by the permit. 9 The turbidity levels within the
4335mixing zone may exceed the 29 NTU standard during
4344construction.
434578. The construction me thods and turbidity controls used
4354by Gulfstream during construction will ensure that the turbidity
4363standards in the proposed permit are met. These methods were
4373successful in controlling turbidity during the construction of
4381the first two phases of the pipe line.
438979. Gulfstream will also undertake other measures to
4397minimize potential water quality impacts. For example, silt
4405fences and hay bales will be used between spoil piles and water
4417bodies, and disturbed areas will be immediately vegetated to
4426limit the potential for sedimentation from erosion.
4433(5) Archeological and Historic Sites
443880. Gulfstream conducted extensive cultural resource
4444assessment surveys as part of the ERP application process. The
4454surveys were conducted in a 300 - to - 400 - foot - wide corrido r around
4471the centerline of the entire pipeline route.
447881. The purpose of the surveys was to identify historical
4488resources and archaeological resources in the vicinity of the
4497proposed pipeline. Historical resources include structures and
4504buildings at or on the ground surface. Archaeological resources
4513are partial or totaled buried cultural resources.
452082. Two historical resources were identified in the
4528surveys: the St. Lucie Canal and the Bryant Sugar Mill. The
4539proposed pipeline will cross the St. L ucie Canal, and the land
4551in the vicinity of the Bryant Sugar Mill will be used for
4563parking and temporary storage of pipes.
456983. The proposed pipeline will have no adverse impact on
4579these historical sites. The proposed pipeline will be installed
4588under the St. Lucie Canal using the HDD method; and there will
4600be no parking or material storage within 25 feet of the Bryant
4612Sugar Mill buildings, which themselves will not be used.
462184. Two archaeological resources were identified in the
4629surveys: the Couse Midde n and a site known as JR - 1 that is
4644associated with the Belle Glade archaeological period. The
4652sites were described as basically, trash, refuse areas,
4660possible habitation sites.
466385. The proposed pipeline will have no adverse impact on
4673these archaeologi cal sites. The proposed pipeline will be
4682installed approximately 40 feet under the Couse Midden site
4691using the HDD method, and the JR - 1 site will be entirely
4704avoided.
470586. The Division of Historical Resources -- the state
4714agency responsible for evaluati ng the potential impacts of
4723construction projects on cultural resources - concurred with
4732the assessment of Gulfstreams consultant that the proposed
4740pipeline will have no adverse affect on any cultural resources
4750listed or eligible for listing in the [Nat ional Register of
4761Historic Places].
476387. Gulfstream has developed, and will implement an
4771Unanticipated Finds Plan that includes detailed procedures to be
4780followed in the event that previously unreported and
4788unanticipated historic properties or human rema ins are found
4797during construction. Among other things, the plan requires
4805construction work in the area of the find to be stopped
4816immediately and not restarted until clearance is granted by the
4826environmental manager and archaeological consultant.
483188. Ad ditionally, as noted above, Gulfstream is in the
4841process of acquiring a 3.75 - acre parcel within the J.W. Corbett
4853WMA that contains an Indian mound and that will be donated to
4865the State.
4867(6) Other Issues
487089. The proposed pipeline will have no adverse impa ct on
4881fishing or other recreational activities in the water bodies
4890within the pipeline route.
489490. The agricultural ditches are Class IV waters that are
4904not suitable for fishing or recreational activities.
491191. The proposed pipeline will be installed under the St.
4921Lucie Canal, the L - 8 Canal, and the L - 65 Canal, which are the
4937only water bodies that could support fishing or recreational
4946activities . A ny impacts on fishing or recreational activities
4956in the canals w ill be minor and temporary impacts during
4967cons truction.
496992. The proposed pipeline will not have any impact on
4979marine productivity because the water bodies within the proposed
4988pipeline route are freshwater, not marine or estuary.
499693. The proposed pipeline will have no permanent adverse
5005impact on nav igation. The only navigable waters crossed by the
5016proposed pipeline are the St. Lucie Canal, the L - 8 Canal, and
5029the L - 65 Canal, and the proposed pipeline will be installed
5041under the canal bottoms.
504594. There will be minor temporary impacts on the
5054navigab ility of the L - 8 and L - 65 C anals because those canals
5070will effectively be blocked while the pipeline is installed
5079under those canals using the sheet pile wet open cut method.
5090The impacts will last no more than 48 hours, which is the
5102maximum amount of time that it will take to complete the
5113crossings.
511495. The proposed pipeline will not cause harmful erosion.
5123The vegetation on the banks of the water bodies will not be
5135removed until the time of pipe installation, and the area will
5146be immediately re - vegetate d after construction. Other erosion
5156control measures will also be implemented, as reflected in the
5166Upland Erosion Control, Revegetation, and Maintenance Plan
5173included as part of the ERP application.
518096. The proposed pipeline will not cause harmful shoa ling.
5190The agriculture ditches are not flowing water bodies so they are
5201not subject to shoaling, and the construction in the L - 8 and L -
521665 Canals will occur during the drier months when there is low
5228flow in the canals. After construction is complete, the
5237p roposed pipeline will not impede the flow of water so as to
5250cause shoaling because it will be buried under the bottom of the
5262canal.
526397. Gulfstream has developed, and will implement a Spill
5272Prevention, Control, and Countermeasure Plan in order to reduce
5281t he chance for accidental spills during construction. The plan
5291also includes procedures to be followed in the event of a spill.
530398. The easement agreement between Gulfstream and SFWMD
5311requires Gulfstream to pay any additional cost that SFWMD incurs
5321in th e installation, repair, or replacement of culverts within
5331the proposed pipeline route as a result of the pipeline being
5342located above an existing or future culvert. The agreement also
5352requires Gulfstream, at its expense, to promptly repair and
5361restore any damage to berms, levees, or other SFWMD improvements
5371that is caused by the construction or operation of the proposed
5382pipeline.
538399. The proposed pipeline will not have any material
5392secondary impacts on wetlands or water resources. To the extent
5402that the WCEC project can be considered to be a secondary impact
5414of the proposed pipeline, its impacts on wetlands and water
5424resources were considered as part of the certification
5432proceeding for that project under the Power Plant Siting Act. 10
5443100. The Department d id not specifically evaluate whether
5452the proposed pipeline will impact the Comprehensive Everglades
5460Restoration Project (CERP). Its failure to do so is not
5470unreasonable or inappropriate because the proposed pipeline is
5478not located within the Everglades Na tional Park or Loxahatchee
5488National Refuge areas, and no concerns related to CERP were
5498brought to the Departments attention by the agencies that
5507provided comments on the ERP application. Moreover, the
5515commenting agencies included SWFMD, which is actively involved
5523in CERP and upon whose property the proposed pipeline will be
5534located.
5535101. Petitioners expressed concerns regarding the impact
5542of the proposed pipeline on the Everglades and CERP. However,
5552t hey did not present any persuasive evidence in suppor t of these
5565concerns.
5566102. The proposed permit includes a specific condition
5574that prohibits Gulfstream from installing the proposed pipeline
5582on property that it does not own without prior written approval
5593of the property owner. This condition may prohibit the
5602installation of the pipeline across the J.W. Corbett WMA unless
5612Gulfstream obtains the approval of the Board of Trustees of the
5623Internal Improvement Trust Fund under the linear facility
5631policy.
5632D. Safety Concerns
5635103. Petitioners expressed concer ns regarding the safety
5643of the proposed pipeline and the potential adverse impacts to
5653the environment and the public if the pipeline were to explode.
5664104. T here is a potential for significant damage if the
5675proposed pipeline were to explode.
5680105. I t is impossible to eliminate all risk of the
5691pipeline exploding.
5693106. T he risk of an explosion has been minimized to the
5705greatest exten t practicable through the measures described above
5714that reduce the risk of leaks in the proposed pipeline through
5725corrosion or damage from external forces.
5731107. The pipe wall thickness was increased in areas
5740adjacent to PBAs blasting operations even though the
5748conservative blast mitigation analysis prepared by Gulfstream 's
5756expert shows that the normal pipe wall thickness is more than
5767adequate to withstand the vibrations caused by PBAs current
5776permitted and reasonably foreseeable blasting operations.
5782108. The location of the pipeline -- underground and in
5792existing canal and utility rights - of - way -- also serves to
5805minimize t he risk of accidental damage to the pipeline from
5816construction and development activities and hurricanes or other
5824natural disasters.
5826109. Pressure, temperature, and flow in the proposed
5834pipeline will be continuously monitored at a 24 - hour control
5845center, and the pipeline right - of - way will be visually inspected
5858at least once every two weeks.
5864110. The proposed pipeline includes test leads
5871approximately every mile that are used to assess the cathodic
5881protection on the pipeline.
5885111. The proposed pip eli ne includes two valves (at MP 0.00
5897and MP 14.87) that can be used to shut off the flow in the
5911pipeline if necessary. The valve setting at MP 14.87 is the
5922only above - ground component of the proposed pipeline other than
5933the valve settings at the start and end of the pipeline. The
5945area around the valve setting will be enclosed by an eight - foot -
5959high fence and covered with gravel.
5965112. The location of the proposed pipeline will be marked
5975at line - of - sight - intervals and at other key points. The markers
5990will clearly indicate the presence of the pipeline and provide
6000contact information in case of emergency or in the event of
6011excavation in the area of the pipeline by a third party.
6022113. Gulfstream has procedures in place to respond to any
6032emergency that may ar ise in the operation of the pipeline, as
6044required by federal law.
6048114. Gulfstream meets face - to - face with local emergency
6059responders on at least an annual basis to discuss emergency
6069response procedures. It also engages in public education and
6078outreach ef forts to address potential concerns regarding the
6087safety of the pipeline.
6091CONCLUSIONS OF LAW
6094115. DOAH has jurisdiction over the parties to and subject
6104matter of this proceeding pursuant to Sections 120.569 and
6113120.57(1), Florida Statutes.
6116116. Gulfstre am and the Department did not contest
6125Petitioners standing to challenge the proposed permit in the
6134Prehearing Stipulation, but they argue in their PROs that the
6144Brooks and PBCEC do not have standing. It is not necessary to
6156address this issue because Gulf stream and the Department concede
6166in their PROs (at paragraphs 58 and 64, respectively) that Mr.
6177Tsolkas, Ms. Larson, and Mr. Shulz proved their standing.
6186117. Gulfstream has the burden to prove by a preponderance
6196of the evidence that its permit applicati on should be approved.
6207See Dept. of Transportation v. J.W.C. Co., Inc. , 396 So. 2d 778,
6219788 (Fla. 1st DCA 1981).
6224118. This is a de novo proceeding, and no presumption of
6235correctness attaches to the Departments preliminary approval of
6243the proposed permit ; however, as explained in J.W.C. Co. :
6253as a general proposition, a party should be
6261able to anticipate that when agency
6267employees or officials having special
6272knowledge or expertise in the field accept
6279data and information supplied by the
6285applicant, the sam e data and information,
6292when properly identified and authenticated
6297as accurate and reliable by agency or other
6305witnesses, will be readily accepted by the
6312[ALJ], in the absence of evidence showing
6319its inaccuracy or unreliability.
6323J.W.C. Co. , 396 So. 2d at 789.
6330119. Thus, if Gulfstream makes a preliminary showing of
6339its entitlement to the proposed permit through credible and
6348credited evidence, the ALJ may not recommend denial of the
6359permit unless contrary evidence of equivalent quality is
6367presented by t he opponent of the permit. Id.
6376120. An applicant for an ERP must provide reasonable
6385assurances that the proposed activity will not cause or
6394contribute to a violation of state water quality standards and
6404that it is not contrary to the public interest. S ee
6415§ 373.414(1), Fla. Stat.; Fla. Admin. Code R. 40E - 4.301, 40E -
64284.302; BOR §§ 4.1.1, et seq.
6434121. Petitioners contend that Gulfstream has not provided
6442the requisite reasonable assurances and that the proposed permit
6451should be denied. 11 See Prehearing Stip ulation, at 4.
6461Gulfstream and the Department contend that reasonable assurances
6469have been provided and that the proposed permit should be
6479approved. Id.
6481122. The "reasonable assurance" standard does not require
6489Gulfstream to provide absolute guarantees, nor does it require
6498Gulfstream to eliminate all speculation concerning what might
6506occur if the project is developed as proposed; Gulfstream is
6516only required to establish a "substantial likelihood that the
6525project will be successfully implemented." See , e. g. , Metro
6534Dade County v. Coscan Florida, Inc. , 609 So. 2d 644, 648 (Fla.
65463d DCA 1992); Save Our Suwanee v. Dept. of Environmental
6556Protection , 18 F.A.L.R. 1467, 1472 (DEP 1996).
6563123. In evaluating whether reasonable assurances have been
6571provided, it is app ropriate to look at the totality of the
6583circumstances surrounding the proposed activity. See Booker
6590Creek Preservation, Inc. v. Mobil Chemical Co. , 481 So. 2d 10,
660113 (Fla. 1st DCA 1986). Permit conditions requiring mitigation
6610and monitoring of future imp acts may be considered in
6620determining whether reasonable assurances have been provided.
6627See Metropolitan Dade County , 609 So. 2d at 648.
6636124. Gulfstream provided reasonable assurances that the
6643proposed pipeline will not cause or contribute to a violation of
6654any applicable water quality standard, as required by Section
6663373.414(1), Florida Statutes, Florida Administrative Code Rule
667040E - 4.301(1)(e), and BOR Sections 4.1.1(c) and 4.2.4, et seq.
6681125. The potential impacts to water quality are limited to
6691tempo rary impacts during construction. The operation of the
6700pipeline will have no adverse impact on water quality.
6709126. The construction methods for the proposed pipeline
6717will minimize the potential for adverse water quality impacts
6726from turbidity and sedimen tation during construction, and
6734measures will be implemented to prevent and address accidental
6743leaks of contaminants during construction.
6748127. Gulfstream provided reasonable assurances that the
6755proposed pipeline will not be contrary to the public interest ,
6765as required by Section 373.414(1), Florida Statutes, Florida
6773Administrative Code Rule 40E - 4.302(1)(a), and BOR Sections
67824.2.3, et seq.
6785128. The pubic interest test requires a balanced
6793consideration of the following criteria:
67981. Whether the activity will adversely
6804affect the public health, safety, or welfare
6811or the property of others; [ 12 ]
68192. Whether the activity will adversely
6825affect the conservation of fish and
6831wildlife, including endangered or threatened
6836specieis, or their habitats;
68403. Wheth er the activity will adversely
6847affect navigation or the flow of water or
6855cause harmful erosion or shoaling;
68604. Whether the activity will adversely
6866affect the fishing or recreational values or
6873marine productivity in the vicinity of the
6880activity ;
68815. Whether the activity will be of a
6889temporary or permanent nature;
68936. Whether the activity will adversely
6899affect or will enhance significant
6904historical and archaeological resources . .
6910.;
69117. The current condition and relative
6917value of functions bein g performed by areas
6925affected by the proposed activity.
6930§ 373.414(1)(a), Fla. Stat.
6934128. With respect to the first criteri on in the public
6945interest test, the more persuasive evidence establishes that the
6954proposed pipeline will not adversely affect the pu blic health,
6964safety, or welfare. The proposed pipeline has been sited to
6974avoid impacting any wetlands , and it will be located in existing
6985canal and utility rights - of - way and across previously disturbed
6997agricultural areas. Additionally, the proposed pipel ine has
7005been designed to meet or exceed all minimum safety standards,
7015and Petitioners speculative concerns regarding an explosion of
7023the pipeline were not supported by the evidence, particularly in
7033light of the blast mitigation analysis that shows that PB As
7044blasting activities pose no risk to the pipeline.
7052129. Wit h respect to the second criterion of the public
7063interest test, the more persuasive evidence establishes that the
7072proposed pipeline will not adversely affect f ish and wildlife,
7082including listed species, or their habitat. The proposed
7090pipeline route consists of disturbed areas that provide low -
7100quality habitat, and any impacts to wildlife will be temporary
7110in nature related to the construction of the pipeline.
7119Moreover, the impacts will be minimi zed through the wildlife
7129surveys that will be conducted during construction and the
7138gopher tortoise relocation authorized by the FWCC permit.
7146130. With respect to the third criteri on of the public
7157interest test, the more persuasive evidence establishes th at
7166construction of the pipeline will impact navigation of the L - 8
7178and L - 65 Canals, but that the impacts will be minor and
7191temporary ( i.e. , no more than 48 hours); that the flow of water
7204in the canals will be maintained during construction through the
7214use o f the HDD method and the sheet pile wet open cut method for
7229the canal crossings; that the proposed pipeline will not cause
7239any harmful erosion or shoaling during or after construction;
7248and that after the pipeline is constructed, there will be no
7259impacts to navigation or the flow of water because the pipelines
7270will be located under the bottoms of the canals.
7279131. With respect to the fourth criteri on of the public
7290interest test, the more persuasive evidence establishes that any
7299impacts to the fishing and rec reational activities in the canals
7310will be temporary during construction of the crossings; and that
7320there will be no impact on marine productivity because the
7330canals and other water bodies in the proposed pipeline route are
7341freshwater, not marine or estuar y.
7347132. Wi th respect to the fifth criterion of the public
7358interest test, the more persuasive evidence establishes that the
7367proposed pipeline will be permanent in nature, but that its
7377impacts will be minor and temporary in nature. The operation of
7388the pro posed pipeline will have no environmental impacts because
7398it will be underground.
7402133. With respect to the sixth criteri on of the public
7413interest test, the more persuasive evidence establishes that the
7422proposed pipeline will not adversely affect significa nt
7430historical or archaeological resources. The HDD method will be
7439used to install the pipeline 40 feet under the Couse Midden
7450archaeological site, and an adequate buffer has been provided
7459between the proposed pipeline and the Bryant Sugar Mill historic
7469si te. Additionally, Gulfstream is in the process of acquiring
7479the last remaining Indian mound in private ownership within the
7489J.W. Corbett WMA for donation to the State.
7497134. With respect to the seventh criteri on of the public
7508interest test, the more persu asive evidence establishes that the
7518areas directly affected by the proposed pipeline -- agricultural
7527fields, canal rights - of - way , and transmission line right - of - way
7542-- are in a disturbed condition and are of relatively low
7553environmental value, and that the proposed pipeline will not
7562have any direct, indirect, or secondary impacts on the WMAs
7572adjacent to the proposed pipeline route.
7578135. The Department is also required to consider the
7587cumulative impacts of the proposed activity under the ERP
7596program. See § 373.414(8)(a), Fla. Stat.; Fla. Admin. Code R.
760640E - 4.302(1)(b); BOR §§ 4.2.8 through 4.2.8.2.
7614136. If the applicant proposes mitigation within the same
7623drainage basin as the adverse impacts to be mitigated, and if
7634the mitigation offsets these advers e impacts, the . . .
7645department shall consider the regulated activity to meet the
7654cumulative impact requirements . . . . § 373.414(8)(b), Fla.
7664Stat.
7665137. The mitigation proposed by Gulfstream -- removal of
7674exotic species within the pipeline route -- off sets the
7684potential adverse impacts caused by the construction of the
7693pipeline and will occur in the same drainage basin as the
7704pipeline. Therefore, pursuant to Section 373.414(8)(b), Florida
7711Statutes, the pipeline meets the cumulative impact requirements.
7719138. In sum, Gulfstream met its burden to provide
7728reasonable assurances that the proposed pipeline meets the
7736applicable regulatory criteria. The evidence presented by
7743Petitioners in opposition to the proposed pipline was, on
7752balance, considerably less p ersuasive than the evidence
7760presented by Gulfstream and the Department in support of the
7770pipeline.
7771RECOMMENDATION
7772Based upon the foregoing findings of fact and conclusions
7781of law, it is
7785RECOMMENDED that the Department issue a final order
7793approving ERP No. 50 - 0269698 - 002.
7801DONE AND ENTERED this 8th day of February, 2008, in
7811Tallahassee, Leon County, Florida.
7815S
7816T. KENT WETHERELL, II
7820Administrative Law Judge
7823Division of Administrative Hearings
7827The DeSoto Building
78301230 Apalac hee Parkway
7834Tallahassee, Florida 32399 - 3060
7839(850) 488 - 9675 SUNCOM 278 - 9675
7847Fax Filing (850) 921 - 6847
7853www.doah.state.fl.us
7854Filed with the Clerk of the
7860Division of Administrative Hearings
7864this 8th day of February, 2008.
7870ENDNOTES
78711 / Ms. Larson was represented by Mr. Silver up to the final
7884hearing, but she discharged Mr. Silver at the outset of the
7895final hearing and represented herself from that point forward.
7904See Transcript, at 26 - 29.
79102 / The December 5 Order exclud ed [e] vidence and argument
7922relating to the potential impacts of Florida Power and Lights
7932West Coast Energy Center project that were considered and
7941determined in the site certification proceeding or that are not
7951cognizable under part IV of Chapter 373, Fl orida Statutes, and
7962its implementing rules. The December 27 Order excluded
7970[e]vidence and argument relating to potential impacts of
7978greenhouse gas emissions from the West Coast Energy Center
7987project on global climate change.
79923 / Petitioners filed an e mergency motion to continue the final
8004hearing on January 7, 2008. Gulfstream filed a response in
8014opposition to the motion on that same date. The motion was
8025denied at the outset of the final hearing. See Transcript, at
803621. Several ore tenus motions for continuance made by Ms.
8046Larson at the final hearing were also denied. See Transcript,
8056at 31, 349 - 50.
80614 / All statutory references in this Recommended Order are to the
80732007 version of the Florida Statutes.
80795 / See Fla. Admin. Code R. 62 - 330.200(4).
80896 / Mr. Tsolkas and the other Petitioners also have a number of
8102concerns regarding the impacts of the power plant that will
8112served by the proposed pipeline, but those issues were
8121determined to be beyond the scope of this proceeding. See
8131Endnote 2.
81337 / The pa rties did not identify the citation for the linear
8146facility policy, but it appears to be Florida Administrative
8156Code Rule 18 - 2.018(2)(i), which provides that [e] quitable
8166compensation shall be required when the use of uplands will
8176generate income or reve nue for a private user or will limit or
8189preempt use by the general public.
81958 / Mr. Schuette provided draft comments to the Department on
8207or about November 9, 2007. See Petitioners Exhibit 2. The
8217letter raised concerns about gopher tortoises and othe r listed
8227species, and it also raised concerns that are clearly outside of
8238FWCCs jurisdiction, such as concerns regarding the WCEC
8246project. The official FWCC comment letter, dated December 10,
82552007, was much more focused. See Petitioners Exhibit 1. T he
8266Department did not consider FWCCs comments in its review of the
8277revised permit application because the letters were received
8285outside of the applicable 30 - day comment period. See
8295§ 373.4141(1), Fla. Stat. That said, Mr. Schuette testified at
8305the final hearing that all of the concerns raised in the
8316official FWCC letter have been addressed, except for the concern
8326regarding the the integrity of the L - 8 levee. Mr. Scheutte
8338acknowledged in his testimony that the proposed pipeline is
8347adjacent to the L - 8 l evee, not in the levee, and he conceded
8362that the operation and maintenance of the levee is the
8372responsibility of SFWMD, not FWCC. Moreover, the easement
8380agreement between Gulfstream and the District adequately
8387addresses this issue. See Exhibit AT - 3 (para graph 1 of easement
8400agreement).
84019 / The 150 - meter mixing zone in the proposed permit is within
8415the standard range for projects of this type. See Fla. Admin.
8426Code R. 62 - 4.244(5)(c); BOR § 4.2.4.4.
843410 / See In re Florida Power & Light Co. West County Energ y
8448Center Power Plant Siting Application No. PA05 - 47 , Case No. 05 -
84611493EPP (DOAH Oct. 24, 2006; Siting Board Dec. 26, 2006).
847111 / Petitioners argue in their Proposed Final Order that the
8482proposed permit should also be denied because the pipeline did
8492not go through the permitting process under the Natural Gas
8502Transmission Pipeline Siting Act (NGTPSA), Part VIII of Chapter
8511403, Florida Statutes. This issue will not be considered
8520because it was not raised in Petitioners petition challenging
8529the proposed perm it or in the Prehearing Stipulation. That
8539said, it is noteworthy that the application (Exhibit JT - 1, at
8551page 4 - 3) indicates that Gulfstream has applied for a
8562Certificate of Public Convenience and Necessity from the Federal
8571Energy Regulatory Commission (FE RC). If that certificate is
8580issued, the proposed pipeline will be exempt from the NGTPSA.
8590See § 403.9405(2)(c), Fla. Stat. Indeed, although not part of
8600the record of this proceeding, it appears that the certificate
8610has been issued by FERC. See Gulfstre am Natural Gas System, LLC
8622119 F.E.R.C. P61,250; 2007 FERC LEXIS 1048 (FERC June 7, 2007).
863412 / The BOR clarifies that this criterion refers to
8644environmental concerns, not general public health, safety, and
8652welfare concerns, as argued by Petitioners at the final hearing.
8662See BOR § 4.2.3.1(a).
8666COPIES FURNISHED :
8669Lea Crandall, Agency Clerk
8673Department of Environmental Protection
8677The Douglas Building, Mail Station 35
86833900 Commonwealth Boulevard
8686Tallahassee, Florida 32399 - 3000
8691Tom Beason, General Counsel
8695De partment of Environmental Protection
8700The Douglas Building, Mail Station 35
87063900 Commonwealth Boulevard
8709Tallahassee, Florida 32399 - 3000
8714Michael W. Sole, Secretary
8718Department of Environmental Protection
8722The Douglas Building
87253900 Commonwealth Boulevard
8728Tall ahassee, Florida 32399 - 3000
8734Barry M. Silver, Esquire
87381200 South Rogers Circle, Suite 8
8744Boca Raton, Florida 33487
8748Richard S. Brightman, Esquire
8752Hopping, Green & Sams, P.A.
8757Post Office Box 6526
8761Tallahassee, Florida 32314
8764Francine M. Ffolkes, Esq uire
8769Department of Environmental Protection
8773The Douglas Building, Mail Station 35
87793900 Commonwealth Boulevard
8782Tallahassee, Florida 32399 - 3000
8787Alexandria Larson
878916933 West Harlena Drive
8793Loxahatchee, Florida 33470
8796NOTICE OF RIGHT TO SUBMIT EXCEPT IONS
8803All parties have the right to submit written exceptions within
881315 days from the date of this Recommended Order. Any exceptions
8824to this Recommended Order should be filed with the agency that
8835will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 02/08/2008
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 01/31/2008
- Proceedings: Amended Verified Motion to Disqualify Administrative Law Judge filed.
- PDF:
- Date: 01/31/2008
- Proceedings: Petitioner`s Notice of Filing Amended Verified Motion to Disqualify Administrative Law Judge filed.
- PDF:
- Date: 01/22/2008
- Proceedings: Amended Verified Motion to Disqualify Administrative Law Judge filed.
- Date: 01/16/2008
- Proceedings: Transcript (pages 1 through 986) filed.
- PDF:
- Date: 01/16/2008
- Proceedings: Respondent Gulfstream Natural Gas System, LLC`s Notice of Filing Hearing Transcript filed.
- Date: 01/08/2008
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 01/07/2008
- Proceedings: Respondent Gulfstream`s Response in Opposition to Petitioners` Emergency Motion for Continuance filed.
- PDF:
- Date: 01/02/2008
- Proceedings: Department of Environmental Protection`s Response to Motion to Disqualify the ALJ filed.
- PDF:
- Date: 01/02/2008
- Proceedings: Respondent Gulfstream`s Response in Opposition to Peter Panagioti Tsolkas and Alexandra Larson`s Motion to Disqualify Administrative Law Judge filed.
- PDF:
- Date: 12/31/2007
- Proceedings: Petitioner Panagioti Tsolkas and Alexandria Larson`s Motion to Disqualify Administrative Law Judge filed.
- Date: 12/05/2007
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 11/28/2007
- Proceedings: Amended Response to Respondent Gulfstream Natural Gas, L.L.C.`s Motion in Limine and Motion to Strike filed.
- PDF:
- Date: 11/26/2007
- Proceedings: Department`s Response to Respondent Gulfstream Natural Gas, L.L.C`s Motion in Limine and Motion to Strike filed.
- PDF:
- Date: 11/26/2007
- Proceedings: Notice of Appearance of Additional Counsel for Department of Environmental Protection filed.
- PDF:
- Date: 11/21/2007
- Proceedings: Amended Notice of Hearing (hearing set for January 8 through 11, 2008; 9:00 a.m.; West Palm Beach, FL; amended as to issue).
- PDF:
- Date: 11/21/2007
- Proceedings: Notice of Hearing (hearing set for January 8 through 11, 2008; 9:00 a.m.; West Palm Beach, FL).
- PDF:
- Date: 11/21/2007
- Proceedings: Order (parties shall coordinate a telephonic hearing on the pending Motion in Limine and Motion to Strike during the week of December 3-7, 2007).
- PDF:
- Date: 11/13/2007
- Proceedings: Department`s Notice of Filing Amended Petition and Addition of Parties by Petitioners filed.
- PDF:
- Date: 10/15/2007
- Proceedings: Order Continuing Case in Abeyance (parties to advise status by November 16, 2007).
- PDF:
- Date: 10/05/2007
- Proceedings: Petitioner`s Notice of Service of Answers to Respondents` First Set of Interrogatories filed.
- PDF:
- Date: 09/12/2007
- Proceedings: Order Granting Continuance and Placing Case in Abeyance (parties to advise status by October 12, 2007).
- Date: 09/12/2007
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 08/31/2007
- Proceedings: Department of Environmental Protection`s Disclosure of Witnesses filed.
- PDF:
- Date: 08/28/2007
- Proceedings: Respondent, Gulfstream Natural Gas System, LLC`s Disclosure of Witnesses filed.
- PDF:
- Date: 08/10/2007
- Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s First Request for Production of Documents to Petitioner the Palm Beach County Environmental Coalition filed.
- PDF:
- Date: 08/10/2007
- Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s First Request for Production of Documents to Petitioner Peter "Panagioti" Tsolkas filed.
- PDF:
- Date: 08/10/2007
- Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s Notice of Serving First Set of Interrogatories to Petitioner the Palm Beach County Environmental Coalition filed.
- PDF:
- Date: 08/10/2007
- Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s Notice of Serving First Set of Interrogatories to Petitioner Peter "Panagioti" Tsolkas filed.
- PDF:
- Date: 07/31/2007
- Proceedings: Notice of Hearing (hearing set for October 2 through 5, 2007; 9:00 a.m.; West Palm Beach, FL).
Case Information
- Judge:
- T. KENT WETHERELL, II
- Date Filed:
- 07/12/2007
- Date Assignment:
- 07/13/2007
- Last Docket Entry:
- 04/18/2008
- Location:
- West Palm Beach, Florida
- District:
- Southern
- Agency:
- ADOPTED IN PART OR MODIFIED
Counsels
-
Richard S. Brightman, Esquire
Address of Record -
Francine M. Ffolkes, Esquire
Address of Record -
Ronald Woodrow Hoenstine, III, Esquire
Address of Record -
Alexandria Larson
Address of Record -
Barry M. Silver, Esquire
Address of Record -
Ronald Woodrow Hoenstine, Esquire
Address of Record -
Ronald W. Hoenstine, II, Esquire
Address of Record