07-003151 Peter &Quot;Panagioti&Quot; Tsolkas, Palm Beach County Environmental Coalition, Alexandria Larson, Bonnie Brooks, Danny Brooks, And Peter Shulz vs. Gulfstream Natural Gas System, L.L.C. And Department Of Environmental Protection
 Status: Closed
Recommended Order on Friday, February 8, 2008.


View Dockets  
Summary: The Applicant provided reasonable assurances that the proposed natural gas pipeline meets the applicable regulatory criteria. Recommend that the permit be approved.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8PETER "PANAGIOTI" TSOLKAS, PALM )

13BEACH COUNTY ENVIRONMENTAL )

17COALITION, ALEXANDRIA LARSON, )

21BONNIE BROOKS, DANNY BROOKS, )

26and PETER SHULZ, )

30)

31Petitioners, )

33)

34vs. ) Case No. 07 - 3151

41)

42GULFSTREAM NATURAL GAS SYSTEM, )

47L.L.C. and DEPARTMENT OF )

52ENVIRONMENTAL PROTECTION, )

55)

56Respondents. )

58)

59RECOMMENDED ORDER

61A duly - noticed final hearing was held in this case by

73Administrative Law Judge T. Ken t Wetherell, II, on January 8 - 10,

862008, in West Palm Beach, Florida.

92APPEARANCES

93For Petitioners Peter “Panagioti” Tsolkas, Palm Beach

100County Environmental Coalition, Bonnie Brooks, Danny

106Brooks, and Peter Shulz:

110Barry M. Silver, Esquire

1141200 S outh Rogers Circle, Suite 8

121Boca Raton, Florida 33487 - 5703

127For Petitioner Alexandria Larson: 1

132Alexandria Larson, pro se

13616933 West Harlena Drive

140Loxahatchee, Florida 33470

143For Respondent Gulfstream Natural Gas System, L . L . C . :

156Richard S. Brightman, Esquire

160Hopping, Green & Sams, P.A.

165Post Office Box 6526

169Tallahassee, Florida 32314 - 6526

174For Respondent Department of Environmental Protection:

180Francine M. Ffolkes, Esquire

184Ronald W. Hoenstine, III, Esquire

189Department of Environmental Protection

193The Douglas Building, Mail Station 35

1993900 Commonwealth Boulevard

202Tallahassee, Florida 32399 - 3000

207STATEMENT OF THE ISSUE

211The issue is whether the Department of Environmental

219Protection should issue Enviro nmental Resource Permit No. 50 -

2290269698 - 002.

232PRELIMINARY STATEMENT

234On June 7, 2007, the Department of Environmental Protection

243(Department) gave notice of its intent to issue Environmental

252Resource Permit (ERP) No. 50 - 0269698 - 001 (the initial permit) to

265Gul fstream Natural Gas System, L . L . C . (Gulfstream). The initial

279permit authorized the installation of a 30 - inch natural gas

290pipeline across 34.30 miles in Martin and Palm Beach Counties.

300On June 28, 2007, a petition for administrative hearing was

310filed by Pe ter “Panagioti” Tsolkas and the Palm Beach County

321Environmental Coalition (PBCEC). The petition challenged the

328initial permit on a variety of grounds.

335On July 11, 2007, the Department referred the petition to

345the Division of Administrative Hearings (DOAH) for the

353assignment of an Administrative Law Judge (ALJ) to conduct the

363hearing requested by Mr. Tsolkas and the PBCEC. The referral

373was received by DOAH on July 12, 2007.

381The final hearing was initially scheduled for October 2 - 5,

3922007, but on September 1 2, 2007, the case was placed in abeyance

405upon Gulfstream’s motion so that the Department could consider

414Gulfstream’s revised application modifying the pipeline route.

421On October 12, 2007, the Department gave notice of its

431intent to approve ERP No. 50 - 02696 98 - 002 (the proposed permit)

445for the revised pipeline route. The proposed permit authorizes

454the installation of a 30 - inch natural gas pipeline across 34.26

466miles in Martin and Palm Beach Counties.

473On November 2, 2007, a petition for hearing was filed by

484M r. Tsolkas, the PBCEC, Alexandria Larson, Bonnie Brooks, Danny

494Brooks, and Peter Shulz (collectively, “Petitioners”). The

501petition challenges the proposed permit on a variety of grounds.

511A number of the allegations in the petition were directed

521to the pot ential impacts of a power plant project that will be

534served by the proposed pipeline. Those allegations were

542stricken as irrelevant under the ERP program. See Orders

551entered on December 5, 2007, and December 27, 2007 . 2 Petitioners

563were given an opportun ity to make written proffers of evidence

574on the excluded issues, but they did not do so.

584The final hearing was held on January 8 - 10, 2008. 3 At the

598hearing, Gulfstream presented the testimony of Al Taylor, Chris

607Brown (expert in pipeline design, engineerin g, and construction

616methods), Kimberly Rhodes - Edelstein (expert in natural gas

625pipeline permitting and impact assessment), Kristoffer Bowman

632(expert in wetland and wildlife ecology, including protected

640species), Dr. Kate Hoffman (expert in the analysis of potential

650impacts to archaeological resources), and Dr. Gregory Hempen

658(expert in vibration analysis, blast mitigation, and soil

666analysis); the Department presented the testimony of Jennifer

674Smith; and Petitioners presented the testimony of Mr. Shulz, Mr.

684Tsolkas, James Schuette, Ms. Larson, and Dr. William Louda

693(expert in biological sciences, environmental sciences, ecology,

700and organic geochemistry). The following exhibits were received

708into evidence: Exhibits JT - 1 through JT - 3, AT - 1 through AT - 3,

725CB - 1 through CB - 3, KR - 1, KB - 1, KB - 2, KH - 1 through KH - 5, GH - 1,

751GH - 2, DEP - 2, and Petitioners’ Exhibits 1, 2, and 4 through 6.

766Petitioners’ Exhibit 3 was offered, but not received. Official

775recognition was taken of Sections 373.413, 373.414, 373.4141,

783373.416, 3 73.417, 373.421, 373.4211,373.422, 373.423, 373.426,

791373.427, Florida Statutes 4 ; the rules in Florida Administrative

800Code Chapter 40E that have been adopted by reference by the

811Department 5 ; and the August 1995 version of the Basis of Review

823for Environment al Resource Permit Applications Within the South

832Florida Water Management District (BOR).

837The six - volume Transcript of the final hearing was filed on

849January 16, 2008. The parties were given until January 31,

8592008, to file proposed recommended orders (PRO s). Gulfstream

868and the Department filed PROs on January 31, 2008, and the

879Petitioners represented by Mr. Silver filed a “Proposed Final

888Order” on that same date. Ms. Larson did not file a PRO. The

901parties’ post - hearing filings have been given due consid eration.

912FINDINGS OF FACT

915A. Parties

9171. Mr. Tsolkas is a resident of Lake Worth, which is in

929southeastern Palm Beach County. He is the co - chair of the

941PBCEC, and he uses the Dupuis and J.W. Corbett Wildlife

951Management Areas (WMAs) for various recreatio nal and “peace of

961mind” activities. He is concerned that the proposed pipeline

970will adversely impact his enjoyment of the WMAs. 6

9792. PBCEC is an organization comprised of environmental

987groups and individuals that are concerned about the environment

996and qu ality of life in Palm Beach County. PBCEC has undertaken

1008public outreach, protests, and other advocacy efforts targeting

1016the West Coast Energy Center (WCEC) that will be served by the

1028proposed pipeline. No evidence was presented regarding PBCEC’s

1036members hip numbers.

10393. Mr. Shulz is a resident of Hope Sound, which is on the

1052eastern coast of Martin County. He is a member of the PBCEC,

1064and he uses the Dupuis and J.W. Corbett WMAs for various

1075recreational activities. He is concerned that the proposed

1083pipel ine will adversely impact his enjoyment of the WMAs. He

1094also has concerns regarding the safety of the proposed pipeline.

11044. Ms. Larson in a resident of the Loxahatchee area in

1115western Palm Beach County. She uses the Dupuis and J.W. Corbett

1126WMAs for vari ous recreational activities, and she is concerned

1136that the proposed pipeline will adversely impact her enjoyment

1145of the WMAs. She also has concerns regarding the safety of the

1157proposed pipeline.

11595. Bonnie Brooks and Danny Brooks were not present at the

1170f inal hearing, and the record contains no evidence about these

1181Petitioners.

11826. Gulfstream is a joint venture owned by Spectra Energy

1192Corporation and the Williams Companies and is in the business of

1203transporting natural gas through pipelines. Gulfstream is a

1211Dela ware limited liability company with its principle office in

1221Tampa.

12227. The Department is the state agency responsible for

1231regulating construction activities in surface waters and

1238wetlands under the ERP program in conjunction with the water

1248managemen t districts. The Department is responsible for taking

1257final agency action on the proposed permit at issue in this

1268case.

1269B. The Proposed Pipeline

1273(1) Generally

12758. The proposed pipeline is a 34.26 - mile, 30 - inch diameter

1288natural gas pipeline.

12919. The pro posed pipeline starts in western Martin County,

1301slightly northwest of Indiantown, and ends in western Palm Beach

1311County at the site of the WCEC being constructed by Florida

1322Power and Light Company (FPL), just north of Twenty Mile Bend.

133310. The proposed p ipeline is the third phase a pipeline

1344that runs from natural gas supply areas on the coasts of Alabama

1356and Mississippi across the Gulf of Mexico into central and

1366southern Florida. The entire pipeline is 691 miles long, with

1376approximately 240 miles in Flor ida.

138211. The first phase of the pipeline began operatin g in May

13942002, and the second phase began operatin g in February 2005.

1405The pipeline currently transports approximately 1.1 billion

1412cubic feet per day of natural gas into Florida.

142112. The proposed pipeline begins at the existing

1429Gulfstream Station 712, which is referred to as milepost (MP)

14390.00. It runs in a southerly direction along the east side of

1451the L - 65 Canal, crossing the St. Lucie Canal (at MP 6.3 4 ) and

1467continuing to the Martin/Palm Beach c ounty line (at MP 8.50);

1478then runs east to a point west of the Dupuis WMA (at MP 10.20)

1492and runs south along the western boundary of the Dupuis WMA

1503adjacent to an existing power line right - of - way; then turns

1516southeast (at MP 12.14) and runs on the east sid e of the L - 8

1532Canal; and then turns due south (at MP 30.08) and runs in an

1545existing FPL transmission line right - of - way to its terminus on

1558the WCEC site (at MP 34.26).

156413. Gulfstream acquired a non - exclusive pipeline easement

1573from the South Florida Water M anagement District (SFWMD), which

1583authorizes it to install the proposed pipeline within the L - 8

1595and L - 65 canal rights - of - way. The agreement limits the width of

1611the permanent easement to 20 feet, but it provides for 95 - foot

1624wide temporary construction ease ments along the pipeline route.

1633The agreement requires the proposed pipeline to be installed at

1643least three feet below the surface.

164914. The proposed pipeline crosses 121 artificial water

1657bodies. It does not cross any natural water bodies.

166615. Only thr ee of the crossed water bodies – - the L - 8

1681Canal, the L - 65 Canal, and the St. Lucie Canal -- are navigable.

1695The pipeline crosses the L - 65 Canal once (at MP 0.11); the St.

1709Lucie Canal once (at MP 6.34); and the L - 8 Canal three times (at

1724MP 12.31, MP 13.28 a nd MP 29.72). The other crossed water

1736bodies are agricultural ditches.

174016. The active land uses along the pipeline route are

1750primarily agricultural in nature, consisting of sugar cane

1758fields and sod farms. The passive land uses include the Dupuis

1769and J.W. Corbett WMAs, which are state - owned conservation areas.

178017. There is an existing mining operation adjacent to the

1790pipeline route in the vicinity of MP 32.80. The mining company,

1801Palm Beach Aggregates (PBA), uses blasting to produce limestone

1810aggrega te and sand. The PBA property line is approximately 290

1821feet from the proposed pipeline at its closest point, but the

1832actual blasting is as much as “500 feet to thousands of feet

1844away” from the proposed pipeline.

184918. The route of the proposed pipeline w as revised in

1860August 2007 at the request of the SFWMD and FPL.

187019. The initial pipeline route was along the west sides of

1881the L - 65 and L - 8 Canals. SFWMD requested that the route be

1896shifted to the east side of the canals in order to accommodate

1908potential future canal expansion.

191220. The initial pipeline route was along the eastern edge

1922of the FPL transmission line right - of - way. FPL requested that

1935the route be shifted to the center of the right - of - way in order

1951to accommodate future expansion of the trans mission line

1960facilities.

196121. The revised pipeline route has fewer impacts than the

1971initial route. For example, the initial route had 224 water

1981body crossings, and two wetland crossings, whereas the revised

1990route has only 121 water body crossings, and no wetland

2000crossings.

200122. Gulfstream submitted extensive documentation in

2007support of the revised pipeline route. After reviewing that

2016documentation, the Department gave notice of its intent to issue

2026the proposed permit for the revised pipeline route.

203423 . Notice of the Department’s decision was published in

2044newspapers of general circulation -- the Stuart News in Martin

2054County and in the Palm Beach Post in Palm Beach County -- on or

2068about October 17, 2007.

2072(2) Design and Construction Methods

207724. Federa l law prescribes minimum pipeline design

2085criteria, including standards for pipe wall thickness and the

2094testing of pipeline welds.

209825. Gulfstream took a “compliance plus” approach in the

2107design of the proposed pipeline by going “above and beyond” the

2118minim um requirements in federal law in several respects.

212726. First, the pipe used in the proposed pipeline will

2137meet or exceed the wall thickness requirements in federal law.

2147Thicker - walled pipe will used in areas where there is a

2159potential for external forc es to affect the pipe, such as under

2171road crossings and in the areas adjacent to PBA’s blasting

2181operations.

218227. Second, Gulfstream will x - ray 100 percent of the

2193welded joints on the proposed pipeline, which far exceeds the

2203requirement in federal law that 10 percent of the welds be

2214inspected.

221528. Third, Gulfstream will hydrostatically test the

2222prop os ed pipeline for leaks after construction is complete and

2233before the pipeline is put into operation. Hydrostatic testing

2242involves filling the pipeline with wa ter under pressure higher

2252than the pressure under which the pipeline will operate. A drop

2263in pressure during the test is an indication of a leak in the

2276pipeline, which will be fixed before the pipeline is put into

2287operation.

228829. Fourth, Gulfstream will coat the entire proposed

2296pipeline with an anti - corrosive substance - – fusion bond epoxy -

2309– and the pipeline will also be induced with a small DC current

2322in a process known as cathodic protection. These measures will

2332significantly reduce, if not eliminate potential corrosion on

2340the proposed pipeline.

234330. Gulfstream will use four construction methods to cross

2352the water bodies within the pipeline route: the isolation plate

2362open cut method; the sheet pile wet open cut method; the

2373horizontal directional dril l (HDD) method; and the conventional

2382bore method.

238431. The isolation plate open cut method will be used at

2395each minor and intermediate water body crossing, except for

2404those associated with the HDD method.

241032. The isolation plate open cut method involves the

2419installation of steel plates upstream and downstream of the

2428proposed crossing. The area between the plates is pumped out so

2439that it is essentially dry. A trench is dug in the dry area and

2453the pipeline is placed in the trench. The trench is then

2464back filled and stabilized with at least five feet of cover, and

2476then the plates are removed and the water flows back into the

2488area .

249033. The sheet pile wet open cut method is similar to the

2502isolation plate open cut method, except that it allows water to

2513contin ue to flow in the center of the water body during

2525installation of the pipe . This method will be used for the

2537crossing of the L - 65 Canal, the second and third crossings of

2550the L - 8 Canal, and the crossings of the forebays along the L - 8

2566Canal.

256734. Turbidity curtains or sediment barrier baffle systems

2575will be installed upstream and downstream of the areas where the

2586isolation plate open cut and the sheet pile wet open cut methods

2598are used in order to control turbidity.

260535. The HDD method will be used to cr oss the St. Lucie

2618Canal and the Couse Midden archaeological site, as well as at

2629the first crossing of the L - 8 Canal.

263836. The HDD method involves the boring of a horizontal

2648tunnel along a pre - determined path under the surface feature to

2660be avoided and the n pulling a pre - fabricated section of pipe

2673through the tunnel. The pipe installed using this method will

2683be 35 to 40 feet below the surface feature to be avoided.

269537. The conventional bore method will be used to cross the

2706railroad track and adjacent agr icultural ditch at MP 8.46, as

2717well as the wetland at MP 16.65.

272438. The conventional bore method involves the excavation

2732of bore pits on both sides of the feature to be crossed. A

2745tunnel is bored under the feature and then a section of pipe is

2758pulled th rough the tunnel. The pipe installed using this method

2769will be 10 feet under the railroad track, which is greater than

2781the depth required by federal law, and will be at least five

2793feet under the wetland.

2797C. Environmental Issues

2800(1) Wetlands and Vegetati on

280539. The proposed pipeline will not adversely impact the

2814current condition or relative functions of any wetlands. All of

2824the wetlands within the proposed pipeline route have been

2833avoided.

283440. The proposed pipeline will be installed under one

2843jurisdi ctional wetland (at MP 16.65) using the conventional bore

2853method described above. That wetland is a disturbed, low -

2863quality wetland within the actively managed L - 8 Canal right - of -

2877way. It is routinely mowed and provides no significant water

2887quality functio n or habitat value.

289341. Gulfstream will install erosion control devices in

2901areas where the pipeline construction corridor abuts wetlands.

2909The erosion control devices will be in place and functional

2919prior to commencement of earth disturbance. Gulfstream will

2927utilize reinforced sediment barriers in lieu of standard

2935sediment barriers, and increased buffers are proposed in areas

2944where construction abuts wetlands on the Dupuis and J.W. Corbett

2954WMAs.

295542. The proposed pipeline will not adversely impact liste d

2965plant species. No listed plant species were observed or are

2975likely to occur within the proposed pipeline route, which

2984consists of disturbed rights - of - way and agricultural areas .

299643. Vegetated areas that are disturbed during the

3004installation of the pro posed pipeline will be re - vegetated

3015immediately after construction is complete. Impacts to these

3023areas will be minor and temporary.

302944. The disturbed areas will be re - vegetated with

3039herbaceous cover such as bahia grass, common bermuda grass, or

3049annual r yegrass. The areas will be monitored for two growing

3060seasons to determine the success of the revegetation.

306845. The proposed pipeline route includes exotic and

3076nuisance plant species, including Brazilian pepper, cogon grass,

3084water hyacinth, and water let tuce.

309046. The installation of the proposed pipeline has the

3099potential to spread exotic and nuisance species if appropriate

3108precautions are not taken during construction.

311447. Gulfstream has developed, and will implement an

3122Exotic, Nuisance, and Invasive Plant Management Plan to minimize

3131the potential for spreading exotic and nuisance species. The

3140plan requires, among other things, environmental training of

3148construction personnel and “routine monitoring during all phases

3156of construction, clean up, and res toration.” The plan also

3166includes procedures for onsite disposal of exotic and nuisance

3175species disturbed during construction and the cleaning of

3183vehicles and equipment to ensure that exotic and nuisance

3192species are not inadvertently transported to uncolo nized areas.

320148. The proposed permit includes a specific condition that

3210requires Gulfstream to monitor and maintain the proposed

3218pipeline route – - a total of 214.85 acres - – free of exotic and

3233nuisance species for a period of five years after construction

3243of the pipeline is complete.

324849. The easement agreement between Gulfstream and SFWMD

3256requires Gulfstream to relocate approximately 158 native cabbage

3264palm trees within the construction corridor to “suitable

3272locations within the west right of way of L - 8 w ithin the Palm

3287Beach County Department of Environmental Resources Management

3294wildlife corridor.”

3296(2) Dupuis and J.W. Corbett WMAs

330250. The proposed pipeline route runs along the western

3311boundary of the Dupuis WMA for approximately seven miles

3320(between MP 13.30 and MP 20.18), and it runs along the western

3332boundary of the J.W. Corbett WMA for approximately 9.5 miles

3342(between MP 20.18 and MP 29.70).

334851. The revised pipeline route puts the pipeline closer to

3358the boundaries of the WMAs than did the initial p ipeline route

3370because the route was moved from the west side of the canals to

3383the east side of the canals.

338952. The Fish and Wildlife Conservation Commission (FWCC)

3397manage s the Dupuis and J.W. Corbett WMAs. The WMAs, which

3408include extensive wetlands and virtually no development, are

3416used for a variety of public recreation purposes.

342453. The proposed pipeline crosses approximately 3.67 acres

3432of the J.W. Corbett WMA. This land, although technically within

3442the boundaries of WMA, is subject to an easement fo r the L - 8

3457Canal and has been actively managed by SFWMD for canal purposes

3468for at least the past 55 years.

347554. Gulfstream is in the process of acquiring

3483approximately 3.75 acres of privately - held land within the

3493boundaries of the J.W. Corbett WMA that it w ill donate to the

3506State in accordance with the “linear facility policy” 7 as

3516mitigation for the crossing of the J.W. Corbett WMA.

352555. The parcel that Gulfstream is in the process of

3535acquiring contains oak trees, pine trees, and cypress trees. It

3545also cont ains the last Indian mound within the J.W. Corbett WMA

3557that is not already in public ownership.

356456. Gulfstream will install reinforced sediment barriers

3571and increase buffers adjacent to the wetlands on the WMAs in

3582order to prevent impacts to those areas d uring construction.

359257. The proposed pipeline will not have any direct or

3602indirect impact on the Dupuis WMA.

360858. The proposed pipeline’s only impact on the J.W.

3617Corbett WMA is the direct impact to the 3.67 acres of the WMA

3630that the pipeline will cross.

363559. This impact is negligible in light of the size of the

3647J.W. Corbett WMA - – approximately 60,000 acres – - and in light

3661of the fact that the portion of the J.W. Corbett WMA that is

3674being crossed is disturbed land that has been actively used for

3685canal p urposes for over 55 years. Moreover, this impact will be

3697mitigated in accordance with the “linear facility policy.”

370560. Any adverse impacts to the aesthetic qualities of the

3715Dupuis and J.W. Corbett WMAs will be temporary in nature during

3726construction. Once construction is complete, the pipeline will

3734not be visible from the surface.

3740(3) Wildlife

374261. The proposed pipeline route consists of disturbed

3750agricultural areas and canal and utility rights - of - way, which

3762are low quality habitat for listed specie s and other wildlife.

377362. The proposed permit is not likey to have any adverse

3784impact on wildlife, including listed species, or their habitat.

379363. Gulfstream conducted extensive wildlife surveys during

3800the ERP application process. The survey corridor “extended

3808beyond 150 feet to either side of the pipeline centerline for a

3820minimum survey width of 300 feet,” and also included the

3831temporary work space areas, contractor yards, and aboveground

3839facilities associated with the pipeline.

384464. The listed speci es whose potential habitat includes

3853the pipeline corridor are the wood stork, the Southeastern

3862American kestrel, the crested caracara, the bald eagle, and the

3872gopher tortoise and its commensal species.

387865. The wood stork uses areas within and along the

3888p roposed pipeline corridor for resting, but not nesting or

3898foraging.

389966. Southeastern American kestrel and crested caracara

3906habitat exists adjacent to the first four miles of the proposed

3917pipeline corridor. There is no habitat within the pipeline

3926corrido r itself, and no kestrels or caracaras were observed in

3937the adjacent habitat.

394067. The nearest bald eagle nest is approximately 2,550

3950feet from the proposed pipeline route, which is well beyond the

3961660 - foot regulatory protection zone. The nest is within a

3972heavily wooded area of the Dupuis WMA and is not visible from

3984the pipeline route.

398768. A total of 18 gopher tortoise burrows were observed

3997within the proposed p ipeline route. The burrows are located

4007along the berm of the L - 65 Canal between MP 0.04 and MP 1.44.

402269. Relocation is FWCC’s preferred method for avoiding

4030impacts to gopher tortoises that inhabit a construction area.

4039The gopher tortoises are moved to another area during

4048construction, but they are free to return to the area from which

4060they wer e relocated after construction is completed.

406870. In December 2007, FWCC issued a permit (No. WR07530a)

4078that allows Gulfstream to capture and relocate up to 18 gopher

4089tortoises. The permit also allows Gulfstream to capture and

4098relocate commensal species , such as the indigo snake, Florida

4107mouse, and gopher frog.

411171. The FWCC permit addresses the listed species’ concerns

4120raised by James Schuette, the FWCC employee who provided

4129comments to the Department on the ERP application and who

4139testified at the fina l hearing in Petitioner’s case - in - chief. 8

415372. Gulfstream successfully used gopher tortoise

4159relocation during construction of the first two phases of the

4169pipeline project.

417173. Gulfstream will conduct pre - construction surveys to

4180ensure that no listed spe cies have moved into the proposed

4191pipeline route. Qualified environmental inspectors will be on -

4200site on a daily basis during construction to look for listed

4211species and to monitor compliance with the FWCC permit.

4220(4) Water Quality

422374. The proposed pipe line will have no permanent adverse

4233impacts on water quality.

423775. The construction of the pipeline may have minor

4246temporary impacts on water quality through increased turbidity

4254in the water bodies crossed by the proposed pipeline.

426376. Gulfstream will u se turbidity curtains and other

4272barriers to control turbidity and minimize impacts to water

4281quality, and it is required to closely monitor water quality

4291during construction.

429377. The proposed permit establishes a turbidity standard -

4302- 29 Nephelometric Tur bidity Units (NTUs) above backgrou nd – -

4314that must be maintained outside of the 150 meter “mixing zone”

4325established by the permit. 9 The turbidity levels within the

4335“mixing zone” may exceed the 29 NTU standard during

4344construction.

434578. The construction me thods and turbidity controls used

4354by Gulfstream during construction will ensure that the turbidity

4363standards in the proposed permit are met. These methods were

4373successful in controlling turbidity during the construction of

4381the first two phases of the pipe line.

438979. Gulfstream will also undertake other measures to

4397minimize potential water quality impacts. For example, silt

4405fences and hay bales will be used between spoil piles and water

4417bodies, and disturbed areas will be immediately vegetated to

4426limit the potential for sedimentation from erosion.

4433(5) Archeological and Historic Sites

443880. Gulfstream conducted extensive cultural resource

4444assessment surveys as part of the ERP application process. The

4454surveys were conducted in a 300 - to - 400 - foot - wide corrido r around

4471the centerline of the entire pipeline route.

447881. The purpose of the surveys was to identify “historical

4488resources” and “archaeological resources” in the vicinity of the

4497proposed pipeline. Historical resources include structures and

4504buildings at or on the ground surface. Archaeological resources

4513are partial or totaled buried cultural resources.

452082. Two historical resources were identified in the

4528surveys: the St. Lucie Canal and the Bryant Sugar Mill. The

4539proposed pipeline will cross the St. L ucie Canal, and the land

4551in the vicinity of the Bryant Sugar Mill will be used for

4563parking and temporary storage of pipes.

456983. The proposed pipeline will have no adverse impact on

4579these historical sites. The proposed pipeline will be installed

4588under the St. Lucie Canal using the HDD method; and there will

4600be no parking or material storage within 25 feet of the Bryant

4612Sugar Mill buildings, which themselves will not be used.

462184. Two archaeological resources were identified in the

4629surveys: the Couse Midde n and a site known as JR - 1 that is

4644associated with the Belle Glade archaeological period. The

4652sites were described as “basically, trash, refuse areas,

4660possible habitation sites.”

466385. The proposed pipeline will have no adverse impact on

4673these archaeologi cal sites. The proposed pipeline will be

4682installed approximately 40 feet under the Couse Midden site

4691using the HDD method, and the JR - 1 site will be entirely

4704avoided.

470586. The Division of Historical Resources -- the state

4714agency responsible for evaluati ng the potential impacts of

4723construction projects on cultural resources - – concurred with

4732the assessment of Gulfstream’s consultant that the proposed

4740pipeline “will have no adverse affect on any cultural resources

4750listed or eligible for listing in the [Nat ional Register of

4761Historic Places].”

476387. Gulfstream has developed, and will implement an

4771Unanticipated Finds Plan that includes detailed procedures to be

4780followed in the event that previously unreported and

4788unanticipated historic properties or human rema ins are found

4797during construction. Among other things, the plan requires

4805construction work in the area of the find to be stopped

4816immediately and not restarted until clearance is granted by the

4826environmental manager and archaeological consultant.

483188. Ad ditionally, as noted above, Gulfstream is in the

4841process of acquiring a 3.75 - acre parcel within the J.W. Corbett

4853WMA that contains an Indian mound and that will be donated to

4865the State.

4867(6) Other Issues

487089. The proposed pipeline will have no adverse impa ct on

4881fishing or other recreational activities in the water bodies

4890within the pipeline route.

489490. The agricultural ditches are Class IV waters that are

4904not suitable for fishing or recreational activities.

491191. The proposed pipeline will be installed under the St.

4921Lucie Canal, the L - 8 Canal, and the L - 65 Canal, which are the

4937only water bodies that could support fishing or recreational

4946activities . A ny impacts on fishing or recreational activities

4956in the canals w ill be minor and temporary impacts during

4967cons truction.

496992. The proposed pipeline will not have any impact on

4979marine productivity because the water bodies within the proposed

4988pipeline route are freshwater, not marine or estuary.

499693. The proposed pipeline will have no permanent adverse

5005impact on nav igation. The only navigable waters crossed by the

5016proposed pipeline are the St. Lucie Canal, the L - 8 Canal, and

5029the L - 65 Canal, and the proposed pipeline will be installed

5041under the canal bottoms.

504594. There will be minor temporary impacts on the

5054navigab ility of the L - 8 and L - 65 C anals because those canals

5070will effectively be blocked while the pipeline is installed

5079under those canals using the sheet pile wet open cut method.

5090The impacts will last no more than 48 hours, which is the

5102maximum amount of time that it will take to complete the

5113crossings.

511495. The proposed pipeline will not cause harmful erosion.

5123The vegetation on the banks of the water bodies will not be

5135removed until the time of pipe installation, and the area will

5146be immediately re - vegetate d after construction. Other erosion

5156control measures will also be implemented, as reflected in the

5166Upland Erosion Control, Revegetation, and Maintenance Plan

5173included as part of the ERP application.

518096. The proposed pipeline will not cause harmful shoa ling.

5190The agriculture ditches are not flowing water bodies so they are

5201not subject to shoaling, and the construction in the L - 8 and L -

521665 Canals will occur during the drier months when there is low

5228flow in the canals. After construction is complete, the

5237p roposed pipeline will not impede the flow of water so as to

5250cause shoaling because it will be buried under the bottom of the

5262canal.

526397. Gulfstream has developed, and will implement a Spill

5272Prevention, Control, and Countermeasure Plan in order to reduce

5281t he chance for accidental spills during construction. The plan

5291also includes procedures to be followed in the event of a spill.

530398. The easement agreement between Gulfstream and SFWMD

5311requires Gulfstream to pay any additional cost that SFWMD incurs

5321in th e installation, repair, or replacement of culverts within

5331the proposed pipeline route as a result of the pipeline being

5342located above an existing or future culvert. The agreement also

5352requires Gulfstream, at its expense, to promptly repair and

5361restore any damage to berms, levees, or other SFWMD improvements

5371that is caused by the construction or operation of the proposed

5382pipeline.

538399. The proposed pipeline will not have any material

5392secondary impacts on wetlands or water resources. To the extent

5402that the WCEC project can be considered to be a secondary impact

5414of the proposed pipeline, its impacts on wetlands and water

5424resources were considered as part of the certification

5432proceeding for that project under the Power Plant Siting Act. 10

5443100. The Department d id not specifically evaluate whether

5452the proposed pipeline will impact the Comprehensive Everglades

5460Restoration Project (CERP). Its failure to do so is not

5470unreasonable or inappropriate because the proposed pipeline is

5478not located within the Everglades Na tional Park or Loxahatchee

5488National Refuge areas, and no concerns related to CERP were

5498brought to the Department’s attention by the agencies that

5507provided comments on the ERP application. Moreover, the

5515commenting agencies included SWFMD, which is actively involved

5523in CERP and upon whose property the proposed pipeline will be

5534located.

5535101. Petitioners expressed concerns regarding the impact

5542of the proposed pipeline on the Everglades and CERP. However,

5552t hey did not present any persuasive evidence in suppor t of these

5565concerns.

5566102. The proposed permit includes a specific condition

5574that prohibits Gulfstream from installing the proposed pipeline

5582on property that it does not own without prior written approval

5593of the property owner. This condition may prohibit the

5602installation of the pipeline across the J.W. Corbett WMA unless

5612Gulfstream obtains the approval of the Board of Trustees of the

5623Internal Improvement Trust Fund under the “linear facility

5631policy.”

5632D. Safety Concerns

5635103. Petitioners expressed concer ns regarding the safety

5643of the proposed pipeline and the potential adverse impacts to

5653the environment and the public if the pipeline were to explode.

5664104. T here is a potential for significant damage if the

5675proposed pipeline were to explode.

5680105. I t is impossible to eliminate all risk of the

5691pipeline exploding.

5693106. T he risk of an explosion has been minimized to the

5705greatest exten t practicable through the measures described above

5714that reduce the risk of leaks in the proposed pipeline through

5725corrosion or damage from external forces.

5731107. The pipe wall thickness was increased in areas

5740adjacent to PBA’s blasting operations even though the

5748conservative blast mitigation analysis prepared by Gulfstream 's

5756expert shows that the normal pipe wall thickness is more than

5767adequate to withstand the vibrations caused by PBA’s current

5776permitted and reasonably foreseeable blasting operations.

5782108. The location of the pipeline -- underground and in

5792existing canal and utility rights - of - way -- also serves to

5805minimize t he risk of accidental damage to the pipeline from

5816construction and development activities and hurricanes or other

5824natural disasters.

5826109. Pressure, temperature, and flow in the proposed

5834pipeline will be continuously monitored at a 24 - hour control

5845center, and the pipeline right - of - way will be visually inspected

5858at least once every two weeks.

5864110. The proposed pipeline includes “test leads”

5871approximately every mile that are used to assess the cathodic

5881protection on the pipeline.

5885111. The proposed pip eli ne includes two valves (at MP 0.00

5897and MP 14.87) that can be used to shut off the flow in the

5911pipeline if necessary. The “valve setting” at MP 14.87 is the

5922only above - ground component of the proposed pipeline other than

5933the valve settings at the start and end of the pipeline. The

5945area around the valve setting will be enclosed by an eight - foot -

5959high fence and covered with gravel.

5965112. The location of the proposed pipeline will be marked

5975at line - of - sight - intervals and at other key points. The markers

5990will clearly indicate the presence of the pipeline and provide

6000contact information in case of emergency or in the event of

6011excavation in the area of the pipeline by a third party.

6022113. Gulfstream has procedures in place to respond to any

6032emergency that may ar ise in the operation of the pipeline, as

6044required by federal law.

6048114. Gulfstream meets face - to - face with local emergency

6059responders on at least an annual basis to discuss emergency

6069response procedures. It also engages in public education and

6078outreach ef forts to address potential concerns regarding the

6087safety of the pipeline.

6091CONCLUSIONS OF LAW

6094115. DOAH has jurisdiction over the parties to and subject

6104matter of this proceeding pursuant to Sections 120.569 and

6113120.57(1), Florida Statutes.

6116116. Gulfstre am and the Department did not contest

6125Petitioners’ standing to challenge the proposed permit in the

6134Prehearing Stipulation, but they argue in their PROs that the

6144Brooks and PBCEC do not have standing. It is not necessary to

6156address this issue because Gulf stream and the Department concede

6166in their PROs (at paragraphs 58 and 64, respectively) that Mr.

6177Tsolkas, Ms. Larson, and Mr. Shulz proved their standing.

6186117. Gulfstream has the burden to prove by a preponderance

6196of the evidence that its permit applicati on should be approved.

6207See Dept. of Transportation v. J.W.C. Co., Inc. , 396 So. 2d 778,

6219788 (Fla. 1st DCA 1981).

6224118. This is a de novo proceeding, and no presumption of

6235correctness attaches to the Department’s preliminary approval of

6243the proposed permit ; however, as explained in J.W.C. Co. :

6253as a general proposition, a party should be

6261able to anticipate that when agency

6267employees or officials having special

6272knowledge or expertise in the field accept

6279data and information supplied by the

6285applicant, the sam e data and information,

6292when properly identified and authenticated

6297as accurate and reliable by agency or other

6305witnesses, will be readily accepted by the

6312[ALJ], in the absence of evidence showing

6319its inaccuracy or unreliability.

6323J.W.C. Co. , 396 So. 2d at 789.

6330119. Thus, if Gulfstream makes a preliminary showing of

6339its entitlement to the proposed permit through “credible and

6348credited evidence,” the ALJ may not recommend denial of the

6359permit “unless contrary evidence of equivalent quality is

6367presented by t he opponent of the permit.” Id.

6376120. An applicant for an ERP must provide reasonable

6385assurances that the proposed activity will not cause or

6394contribute to a violation of state water quality standards and

6404that it is not contrary to the public interest. S ee

6415§ 373.414(1), Fla. Stat.; Fla. Admin. Code R. 40E - 4.301, 40E -

64284.302; BOR §§ 4.1.1, et seq.

6434121. Petitioners contend that Gulfstream has not provided

6442the requisite reasonable assurances and that the proposed permit

6451should be denied. 11 See Prehearing Stip ulation, at 4.

6461Gulfstream and the Department contend that reasonable assurances

6469have been provided and that the proposed permit should be

6479approved. Id.

6481122. The "reasonable assurance" standard does not require

6489Gulfstream to provide absolute guarantees, nor does it require

6498Gulfstream to eliminate all speculation concerning what might

6506occur if the project is developed as proposed; Gulfstream is

6516only required to establish a "substantial likelihood that the

6525project will be successfully implemented." See , e. g. , Metro

6534Dade County v. Coscan Florida, Inc. , 609 So. 2d 644, 648 (Fla.

65463d DCA 1992); Save Our Suwanee v. Dept. of Environmental

6556Protection , 18 F.A.L.R. 1467, 1472 (DEP 1996).

6563123. In evaluating whether reasonable assurances have been

6571provided, it is app ropriate to look at the totality of the

6583circumstances surrounding the proposed activity. See Booker

6590Creek Preservation, Inc. v. Mobil Chemical Co. , 481 So. 2d 10,

660113 (Fla. 1st DCA 1986). Permit conditions requiring mitigation

6610and monitoring of future imp acts may be considered in

6620determining whether reasonable assurances have been provided.

6627See Metropolitan Dade County , 609 So. 2d at 648.

6636124. Gulfstream provided reasonable assurances that the

6643proposed pipeline will not cause or contribute to a violation of

6654any applicable water quality standard, as required by Section

6663373.414(1), Florida Statutes, Florida Administrative Code Rule

667040E - 4.301(1)(e), and BOR Sections 4.1.1(c) and 4.2.4, et seq.

6681125. The potential impacts to water quality are limited to

6691tempo rary impacts during construction. The operation of the

6700pipeline will have no adverse impact on water quality.

6709126. The construction methods for the proposed pipeline

6717will minimize the potential for adverse water quality impacts

6726from turbidity and sedimen tation during construction, and

6734measures will be implemented to prevent and address accidental

6743leaks of contaminants during construction.

6748127. Gulfstream provided reasonable assurances that the

6755proposed pipeline will not be contrary to the public interest ,

6765as required by Section 373.414(1), Florida Statutes, Florida

6773Administrative Code Rule 40E - 4.302(1)(a), and BOR Sections

67824.2.3, et seq.

6785128. The “pubic interest” test requires a balanced

6793consideration of the following criteria:

67981. Whether the activity will adversely

6804affect the public health, safety, or welfare

6811or the property of others; [ 12 ]

68192. Whether the activity will adversely

6825affect the conservation of fish and

6831wildlife, including endangered or threatened

6836specieis, or their habitats;

68403. Wheth er the activity will adversely

6847affect navigation or the flow of water or

6855cause harmful erosion or shoaling;

68604. Whether the activity will adversely

6866affect the fishing or recreational values or

6873marine productivity in the vicinity of the

6880activity ;

68815. Whether the activity will be of a

6889temporary or permanent nature;

68936. Whether the activity will adversely

6899affect or will enhance significant

6904historical and archaeological resources . .

6910.;

69117. The current condition and relative

6917value of functions bein g performed by areas

6925affected by the proposed activity.

6930§ 373.414(1)(a), Fla. Stat.

6934128. With respect to the first criteri on in the public

6945interest test, the more persuasive evidence establishes that the

6954proposed pipeline will not adversely affect the pu blic health,

6964safety, or welfare. The proposed pipeline has been sited to

6974avoid impacting any wetlands , and it will be located in existing

6985canal and utility rights - of - way and across previously disturbed

6997agricultural areas. Additionally, the proposed pipel ine has

7005been designed to meet or exceed all minimum safety standards,

7015and Petitioners’ speculative concerns regarding an explosion of

7023the pipeline were not supported by the evidence, particularly in

7033light of the blast mitigation analysis that shows that PB A’s

7044blasting activities pose no risk to the pipeline.

7052129. Wit h respect to the second criterion of the public

7063interest test, the more persuasive evidence establishes that the

7072proposed pipeline will not adversely affect f ish and wildlife,

7082including listed species, or their habitat. The proposed

7090pipeline route consists of disturbed areas that provide low -

7100quality habitat, and any impacts to wildlife will be temporary

7110in nature related to the construction of the pipeline.

7119Moreover, the impacts will be minimi zed through the wildlife

7129surveys that will be conducted during construction and the

7138gopher tortoise relocation authorized by the FWCC permit.

7146130. With respect to the third criteri on of the public

7157interest test, the more persuasive evidence establishes th at

7166construction of the pipeline will impact navigation of the L - 8

7178and L - 65 Canals, but that the impacts will be minor and

7191temporary ( i.e. , no more than 48 hours); that the flow of water

7204in the canals will be maintained during construction through the

7214use o f the HDD method and the sheet pile wet open cut method for

7229the canal crossings; that the proposed pipeline will not cause

7239any harmful erosion or shoaling during or after construction;

7248and that after the pipeline is constructed, there will be no

7259impacts to navigation or the flow of water because the pipelines

7270will be located under the bottoms of the canals.

7279131. With respect to the fourth criteri on of the public

7290interest test, the more persuasive evidence establishes that any

7299impacts to the fishing and rec reational activities in the canals

7310will be temporary during construction of the crossings; and that

7320there will be no impact on marine productivity because the

7330canals and other water bodies in the proposed pipeline route are

7341freshwater, not marine or estuar y.

7347132. Wi th respect to the fifth criterion of the public

7358interest test, the more persuasive evidence establishes that the

7367proposed pipeline will be permanent in nature, but that its

7377impacts will be minor and temporary in nature. The operation of

7388the pro posed pipeline will have no environmental impacts because

7398it will be underground.

7402133. With respect to the sixth criteri on of the public

7413interest test, the more persuasive evidence establishes that the

7422proposed pipeline will not adversely affect significa nt

7430historical or archaeological resources. The HDD method will be

7439used to install the pipeline 40 feet under the Couse Midden

7450archaeological site, and an adequate buffer has been provided

7459between the proposed pipeline and the Bryant Sugar Mill historic

7469si te. Additionally, Gulfstream is in the process of acquiring

7479the last remaining Indian mound in private ownership within the

7489J.W. Corbett WMA for donation to the State.

7497134. With respect to the seventh criteri on of the public

7508interest test, the more persu asive evidence establishes that the

7518areas directly affected by the proposed pipeline -- agricultural

7527fields, canal rights - of - way , and transmission line right - of - way

7542-- are in a disturbed condition and are of relatively low

7553environmental value, and that the proposed pipeline will not

7562have any direct, indirect, or secondary impacts on the WMAs

7572adjacent to the proposed pipeline route.

7578135. The Department is also required to consider the

7587“cumulative impacts” of the proposed activity under the ERP

7596program. See § 373.414(8)(a), Fla. Stat.; Fla. Admin. Code R.

760640E - 4.302(1)(b); BOR §§ 4.2.8 through 4.2.8.2.

7614136. If the applicant “proposes mitigation within the same

7623drainage basin as the adverse impacts to be mitigated, and if

7634the mitigation offsets these advers e impacts, the . . .

7645department shall consider the regulated activity to meet the

7654cumulative impact requirements . . . .” § 373.414(8)(b), Fla.

7664Stat.

7665137. The mitigation proposed by Gulfstream -- removal of

7674exotic species within the pipeline route -- off sets the

7684potential adverse impacts caused by the construction of the

7693pipeline and will occur in the same drainage basin as the

7704pipeline. Therefore, pursuant to Section 373.414(8)(b), Florida

7711Statutes, the pipeline meets the cumulative impact requirements.

7719138. In sum, Gulfstream met its burden to provide

7728reasonable assurances that the proposed pipeline meets the

7736applicable regulatory criteria. The evidence presented by

7743Petitioners in opposition to the proposed pipline was, on

7752balance, considerably less p ersuasive than the evidence

7760presented by Gulfstream and the Department in support of the

7770pipeline.

7771RECOMMENDATION

7772Based upon the foregoing findings of fact and conclusions

7781of law, it is

7785RECOMMENDED that the Department issue a final order

7793approving ERP No. 50 - 0269698 - 002.

7801DONE AND ENTERED this 8th day of February, 2008, in

7811Tallahassee, Leon County, Florida.

7815S

7816T. KENT WETHERELL, II

7820Administrative Law Judge

7823Division of Administrative Hearings

7827The DeSoto Building

78301230 Apalac hee Parkway

7834Tallahassee, Florida 32399 - 3060

7839(850) 488 - 9675 SUNCOM 278 - 9675

7847Fax Filing (850) 921 - 6847

7853www.doah.state.fl.us

7854Filed with the Clerk of the

7860Division of Administrative Hearings

7864this 8th day of February, 2008.

7870ENDNOTES

78711 / Ms. Larson was represented by Mr. Silver up to the final

7884hearing, but she discharged Mr. Silver at the outset of the

7895final hearing and represented herself from that point forward.

7904See Transcript, at 26 - 29.

79102 / The December 5 Order exclud ed “[e] vidence and argument

7922relating to the potential impacts of Florida Power and Light’s

7932West Coast Energy Center project that were considered and

7941determined in the site certification proceeding or that are not

7951cognizable under part IV of Chapter 373, Fl orida Statutes, and

7962its implementing rules.” The December 27 Order excluded

7970“[e]vidence and argument relating to potential impacts of

7978greenhouse gas emissions from the West Coast Energy Center

7987project on global climate change.”

79923 / Petitioners filed an e mergency motion to continue the final

8004hearing on January 7, 2008. Gulfstream filed a response in

8014opposition to the motion on that same date. The motion was

8025denied at the outset of the final hearing. See Transcript, at

803621. Several ore tenus motions for continuance made by Ms.

8046Larson at the final hearing were also denied. See Transcript,

8056at 31, 349 - 50.

80614 / All statutory references in this Recommended Order are to the

80732007 version of the Florida Statutes.

80795 / See Fla. Admin. Code R. 62 - 330.200(4).

80896 / Mr. Tsolkas and the other Petitioners also have a number of

8102concerns regarding the impacts of the power plant that will

8112served by the proposed pipeline, but those issues were

8121determined to be beyond the scope of this proceeding. See

8131Endnote 2.

81337 / The pa rties did not identify the citation for the “linear

8146facility policy,” but it appears to be Florida Administrative

8156Code Rule 18 - 2.018(2)(i), which provides that “[e] quitable

8166compensation shall be required when the use of uplands will

8176generate income or reve nue for a private user or will limit or

8189preempt use by the general public.”

81958 / Mr. Schuette provided “draft ” comments to the Department on

8207or about November 9, 2007. See Petitioner’s Exhibit 2. The

8217letter raised concerns about gopher tortoises and othe r listed

8227species, and it also raised concerns that are clearly outside of

8238FWCC’s jurisdiction, such as concerns regarding the WCEC

8246project. The “official” FWCC comment letter, dated December 10,

82552007, was much more focused. See Petitioner’s Exhibit 1. T he

8266Department did not consider FWCC’s comments in its review of the

8277revised permit application because the letters were received

8285outside of the applicable 30 - day comment period. See

8295§ 373.4141(1), Fla. Stat. That said, Mr. Schuette testified at

8305the final hearing that all of the concerns raised in the

8316official FWCC letter have been addressed, except for the concern

8326regarding the “the integrity of the L - 8 levee.” Mr. Scheutte

8338acknowledged in his testimony that the proposed pipeline is

8347adjacent to the L - 8 l evee, not in the levee, and he conceded

8362that the operation and maintenance of the levee is the

8372responsibility of SFWMD, not FWCC. Moreover, the easement

8380agreement between Gulfstream and the District adequately

8387addresses this issue. See Exhibit AT - 3 (para graph 1 of easement

8400agreement).

84019 / The 150 - meter mixing zone in the proposed permit is within

8415the standard range for projects of this type. See Fla. Admin.

8426Code R. 62 - 4.244(5)(c); BOR § 4.2.4.4.

843410 / See In re Florida Power & Light Co. West County Energ y

8448Center Power Plant Siting Application No. PA05 - 47 , Case No. 05 -

84611493EPP (DOAH Oct. 24, 2006; Siting Board Dec. 26, 2006).

847111 / Petitioners argue in their “Proposed Final Order” that the

8482proposed permit should also be denied because the pipeline did

8492not go through the permitting process under the Natural Gas

8502Transmission Pipeline Siting Act (NGTPSA), Part VIII of Chapter

8511403, Florida Statutes. This issue will not be considered

8520because it was not raised in Petitioners’ petition challenging

8529the proposed perm it or in the Prehearing Stipulation. That

8539said, it is noteworthy that the application (Exhibit JT - 1, at

8551page 4 - 3) indicates that Gulfstream has applied for a

8562Certificate of Public Convenience and Necessity from the Federal

8571Energy Regulatory Commission (FE RC). If that certificate is

8580issued, the proposed pipeline will be exempt from the NGTPSA.

8590See § 403.9405(2)(c), Fla. Stat. Indeed, although not part of

8600the record of this proceeding, it appears that the certificate

8610has been issued by FERC. See Gulfstre am Natural Gas System, LLC

8622119 F.E.R.C. P61,250; 2007 FERC LEXIS 1048 (FERC June 7, 2007).

863412 / The BOR clarifies that this criterion refers to

8644environmental concerns, not general public health, safety, and

8652welfare concerns, as argued by Petitioners at the final hearing.

8662See BOR § 4.2.3.1(a).

8666COPIES FURNISHED :

8669Lea Crandall, Agency Clerk

8673Department of Environmental Protection

8677The Douglas Building, Mail Station 35

86833900 Commonwealth Boulevard

8686Tallahassee, Florida 32399 - 3000

8691Tom Beason, General Counsel

8695De partment of Environmental Protection

8700The Douglas Building, Mail Station 35

87063900 Commonwealth Boulevard

8709Tallahassee, Florida 32399 - 3000

8714Michael W. Sole, Secretary

8718Department of Environmental Protection

8722The Douglas Building

87253900 Commonwealth Boulevard

8728Tall ahassee, Florida 32399 - 3000

8734Barry M. Silver, Esquire

87381200 South Rogers Circle, Suite 8

8744Boca Raton, Florida 33487

8748Richard S. Brightman, Esquire

8752Hopping, Green & Sams, P.A.

8757Post Office Box 6526

8761Tallahassee, Florida 32314

8764Francine M. Ffolkes, Esq uire

8769Department of Environmental Protection

8773The Douglas Building, Mail Station 35

87793900 Commonwealth Boulevard

8782Tallahassee, Florida 32399 - 3000

8787Alexandria Larson

878916933 West Harlena Drive

8793Loxahatchee, Florida 33470

8796NOTICE OF RIGHT TO SUBMIT EXCEPT IONS

8803All parties have the right to submit written exceptions within

881315 days from the date of this Recommended Order. Any exceptions

8824to this Recommended Order should be filed with the agency that

8835will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 04/18/2008
Proceedings: Notice of Appeal filed.
PDF:
Date: 03/21/2008
Proceedings: Respondents` Joint Exceptions to Recommended Order filed.
PDF:
Date: 03/21/2008
Proceedings: Final Order filed.
PDF:
Date: 03/19/2008
Proceedings: Agency Final Order
PDF:
Date: 02/08/2008
Proceedings: Recommended Order
PDF:
Date: 02/08/2008
Proceedings: Recommended Order (hearing held January 8, 2008). CASE CLOSED.
PDF:
Date: 02/08/2008
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 02/08/2008
Proceedings: Order Denying Motion Disqualify.
PDF:
Date: 01/31/2008
Proceedings: DEP`s Proposed Recommended Order filed.
PDF:
Date: 01/31/2008
Proceedings: Proposed Recommended Order filed.
PDF:
Date: 01/31/2008
Proceedings: Petitioner`s Notice of Filing Proposed Order filed.
PDF:
Date: 01/31/2008
Proceedings: Amended Verified Motion to Disqualify Administrative Law Judge filed.
PDF:
Date: 01/31/2008
Proceedings: Petitioner`s Notice of Filing Amended Verified Motion to Disqualify Administrative Law Judge filed.
PDF:
Date: 01/31/2008
Proceedings: Proposed Final Order filed.
PDF:
Date: 01/23/2008
Proceedings: Order Denying Motions to Disqualify.
PDF:
Date: 01/22/2008
Proceedings: Amended Verified Motion to Disqualify Administrative Law Judge filed.
Date: 01/16/2008
Proceedings: Transcript (pages 1 through 986) filed.
PDF:
Date: 01/16/2008
Proceedings: Respondent Gulfstream Natural Gas System, LLC`s Notice of Filing Hearing Transcript filed.
PDF:
Date: 01/15/2008
Proceedings: Verified Motion to Disqualify Administrative Law Judge filed.
Date: 01/08/2008
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 01/07/2008
Proceedings: Respondent Gulfstream`s Response in Opposition to Petitioners` Emergency Motion for Continuance filed.
PDF:
Date: 01/07/2008
Proceedings: Petitioners` Supplement to Exhibit List filed.
PDF:
Date: 01/07/2008
Proceedings: Petitioners` Emergency Motion for Continuance filed.
PDF:
Date: 01/02/2008
Proceedings: Prehearing Stipulation filed.
PDF:
Date: 01/02/2008
Proceedings: Department of Environmental Protection`s Response to Motion to Disqualify the ALJ filed.
PDF:
Date: 01/02/2008
Proceedings: Respondent Gulfstream`s Response in Opposition to Peter Panagioti Tsolkas and Alexandra Larson`s Motion to Disqualify Administrative Law Judge filed.
PDF:
Date: 01/02/2008
Proceedings: Order Denying Motion to Disqualify.
PDF:
Date: 12/31/2007
Proceedings: Petitioner Panagioti Tsolkas and Alexandria Larson`s Motion to Disqualify Administrative Law Judge filed.
PDF:
Date: 12/27/2007
Proceedings: Order (Second Motion in Limine and Motion to Strike is granted).
PDF:
Date: 12/26/2007
Proceedings: Notice of Taking Deposition Duces Tecum (P. Tsolkas) filed.
PDF:
Date: 12/26/2007
Proceedings: Notice of Taking Deposition Duces Tecum (P. Shulz) filed.
PDF:
Date: 12/26/2007
Proceedings: Notice of Taking Deposition Duces Tecum (D. Brooks) filed.
PDF:
Date: 12/26/2007
Proceedings: Notice of Taking Deposition Duces Tecum (B. Brooks) filed.
PDF:
Date: 12/26/2007
Proceedings: Notice of Taking Deposition Duces Tecum (A. Larson) filed.
PDF:
Date: 12/26/2007
Proceedings: Notice of Taking Deposition Duces Tecum (B. Louda) filed.
PDF:
Date: 12/19/2007
Proceedings: Notice of Cancellation of Taking Deposition Duces Tecum filed.
PDF:
Date: 12/17/2007
Proceedings: Petitioners` Addendum to Witness List filed.
PDF:
Date: 12/14/2007
Proceedings: Second Motion in Limine and Motion to Strike filed.
PDF:
Date: 12/11/2007
Proceedings: Notice of Taking Deposition Duces Tecum (L. Purvis) filed.
PDF:
Date: 12/11/2007
Proceedings: Notice of Taking Deposition Duces Tecum (P. Shulz) filed.
PDF:
Date: 12/11/2007
Proceedings: Notice of Taking Deposition Duces Tecum (D. Brooks) filed.
PDF:
Date: 12/11/2007
Proceedings: Notice of Taking Deposition Duces Tecum (B. Brooks) filed.
PDF:
Date: 12/11/2007
Proceedings: Notice of Taking Deposition Duces Tecum (A. Larson) filed.
PDF:
Date: 12/11/2007
Proceedings: Notice of Taking Deposition Duces Tecum (P. Tsolkas) filed.
PDF:
Date: 12/05/2007
Proceedings: Order (motion in limine and motion to strike granted).
Date: 12/05/2007
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 11/29/2007
Proceedings: Notice of Filing Copy of Proposed Agency Action filed.
PDF:
Date: 11/28/2007
Proceedings: Amended Response to Respondent Gulfstream Natural Gas, L.L.C.`s Motion in Limine and Motion to Strike filed.
PDF:
Date: 11/27/2007
Proceedings: Amended Notice of Telephonic Hearing filed.
PDF:
Date: 11/27/2007
Proceedings: Notice of Telephonic Hearing filed.
PDF:
Date: 11/26/2007
Proceedings: Department`s Response to Respondent Gulfstream Natural Gas, L.L.C`s Motion in Limine and Motion to Strike filed.
PDF:
Date: 11/26/2007
Proceedings: Notice of Appearance of Additional Counsel for Department of Environmental Protection filed.
PDF:
Date: 11/26/2007
Proceedings: Notice of Appearance (filed by F. Ffolkes).
PDF:
Date: 11/21/2007
Proceedings: Amended Notice of Hearing (hearing set for January 8 through 11, 2008; 9:00 a.m.; West Palm Beach, FL; amended as to issue).
PDF:
Date: 11/21/2007
Proceedings: Notice of Hearing (hearing set for January 8 through 11, 2008; 9:00 a.m.; West Palm Beach, FL).
PDF:
Date: 11/21/2007
Proceedings: Order (parties shall coordinate a telephonic hearing on the pending Motion in Limine and Motion to Strike during the week of December 3-7, 2007).
PDF:
Date: 11/19/2007
Proceedings: Case Status Report and Request for Hearing Date filed.
PDF:
Date: 11/16/2007
Proceedings: Motion in Limine and Motion to Strike filed.
PDF:
Date: 11/13/2007
Proceedings: Department`s Notice of Filing Amended Petition and Addition of Parties by Petitioners filed.
PDF:
Date: 10/15/2007
Proceedings: Order Continuing Case in Abeyance (parties to advise status by November 16, 2007).
PDF:
Date: 10/12/2007
Proceedings: Case Status Report filed.
PDF:
Date: 10/05/2007
Proceedings: Petitioner`s Notice of Service of Answers to Respondents` First Set of Interrogatories filed.
PDF:
Date: 09/12/2007
Proceedings: Order Granting Continuance and Placing Case in Abeyance (parties to advise status by October 12, 2007).
Date: 09/12/2007
Proceedings: CASE STATUS: Motion Hearing Held.
PDF:
Date: 09/07/2007
Proceedings: Notice of Telephonic Hearing filed.
PDF:
Date: 09/05/2007
Proceedings: Motion for Continuance filed.
PDF:
Date: 08/31/2007
Proceedings: Department of Environmental Protection`s Disclosure of Witnesses filed.
PDF:
Date: 08/30/2007
Proceedings: Notice of Cancellation of Taking Deposition Duces Tecum filed.
PDF:
Date: 08/28/2007
Proceedings: Respondent, Gulfstream Natural Gas System, LLC`s Disclosure of Witnesses filed.
PDF:
Date: 08/20/2007
Proceedings: Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 08/10/2007
Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s First Request for Production of Documents to Petitioner the Palm Beach County Environmental Coalition filed.
PDF:
Date: 08/10/2007
Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s First Request for Production of Documents to Petitioner Peter "Panagioti" Tsolkas filed.
PDF:
Date: 08/10/2007
Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s Notice of Serving First Set of Interrogatories to Petitioner the Palm Beach County Environmental Coalition filed.
PDF:
Date: 08/10/2007
Proceedings: Respondent Gulfstream Natural Gas System, L.L.C.`s Notice of Serving First Set of Interrogatories to Petitioner Peter "Panagioti" Tsolkas filed.
PDF:
Date: 07/31/2007
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 07/31/2007
Proceedings: Notice of Hearing (hearing set for October 2 through 5, 2007; 9:00 a.m.; West Palm Beach, FL).
PDF:
Date: 07/20/2007
Proceedings: Department of Enviromental Protection`s Response to Initial Order filed.
PDF:
Date: 07/16/2007
Proceedings: Notice of Appearance (filed by R. Brightman).
PDF:
Date: 07/13/2007
Proceedings: Initial Order.
PDF:
Date: 07/12/2007
Proceedings: Notice of Intent to Issue Environmental Resource Permit filed.
PDF:
Date: 07/12/2007
Proceedings: Petition for Administrative Hearing filed.
PDF:
Date: 07/12/2007
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
T. KENT WETHERELL, II
Date Filed:
07/12/2007
Date Assignment:
07/13/2007
Last Docket Entry:
04/18/2008
Location:
West Palm Beach, Florida
District:
Southern
Agency:
ADOPTED IN PART OR MODIFIED
 

Counsels

Related Florida Statute(s) (9):