07-004365BID
Expertech Network Installation, Inc. vs.
City Of Cape Coral
Status: Closed
Recommended Order on Friday, November 9, 2007.
Recommended Order on Friday, November 9, 2007.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8EXPERTECH NETWORK INSTALLATION, )
12INC. , )
14)
15Petitioner , )
17)
18vs. ) Case No. 07 - 4365BID
25)
26CITY OF CAPE CORAL , )
31)
32Respondent . )
35)
36RECOMMENDED ORDER
38Pursuant to notice, a final hearing was conducted in this
48case on October 10, 2007, in Cape Coral, Florida, before
58Administrative Law Judge R. Bruce McKibben of the Division of
68Administrative Hearings (DOAH).
71APPEARANCES
72For Petitioner: William S. Isenb erg, Esquire
79William S. Isenberg and Associates, P.A.
852005 South Federal Highway, Suite 100
91Fort Lauderdale, Florida 33316
95For Respondent: Mark Edward Lupe, Esquire
101Marilyn W. Miller, Esquire
105City of Cape Coral
109Post Office Box 150027
113Cape Coral, Florida 33915
117STATEMENT OF THE ISSUE
121The issue in this case is whether Respondent's decision to
131reject the galvanized pipe replacement bid of Petitioner as non -
142responsive was erroneous, an abuse of discre tion, arbitrary or
152capricious.
153PRELIMINARY STATEMENT
155Respondent, the City of Cape Coral (the "City") , issued an
166Invitation to Bid concerning replacement of gal vanized pipe.
175Petitioner was one of the companies responding to the Invitation
185to Bid. The City rejected Petitioner's bid as unresponsive and
195awarded the contract to Guymann Construction of Florida, Inc.
204(Guymann). Guymann did not file any pleadings or o ther
214materials in this case and did not make an appearance at final
226hearing. Upon entry of the Notice of Intent to Award by the
238City, Petitioner filed a Protest of Intended Bid Award. The
248matter was forwarded to the D OAH pursuant to the City's
259Administra ti ve Law Judge Services Contract.
266Pursuant to City Ordinance 68 - 07, a final hearing was
277scheduled by stipulation of the parties on October 10, 2007
287(even though that date was more than 15 days after receipt of
299the protest at DOAH). At final hearing both p arties were
310represented by counsel. Petitioner called four witnesses at the
319final hearing: John Wood, d irector of U.S. Operations for
329Petitioner; Michael Heitzler, s enior p roject m anager for
339Petitioner; David Marinelli, v ice p resident of U.S. Operations
349for Petitioner; and Justin Fredericksen, p roject m anager for
359TetraTech. Petitioner's E xhibits A through K were admitted into
369evidence. Respondent called three witnesses: Justin
375Fredericksen ; David Vallandingham, a ssistant s uperintendent for
383Public Works wit h the City; and George Reilly, u tilities m anager
396for the City. Respondent's E xhibits 1 through 1 3 were admitted
408into evidence by stipulation.
412A T ranscript of the final hearing was filed with DOAH on
424October 23, 2007 . The parties were given until Octo ber 26 ,
4362007, to file proposed findings of fact, conclusions of law, and
447written closing statements. Petitioner asked and was granted
455three additional days to submit its proposed recommended order.
464Each party timely filed a P roposed R ecommended O rder , an d each
478was duly - considered in the preparation of this R ecommended
489O rder.
491FINDINGS OF FACT
4941. Petitioner, Expertech Network Installation, Inc., is a
502division of Bell Canada. Petitioner is a construction and
511engineering division of the parent company. It was set up to
522expand the parent's operations into the United States about nine
532years ago. Petitioner has steadily replaced its Canadian
540employees with U.S. employees over those years.
5472. The City is a governmental entity established under the
557laws of t he State of Florida. By contract with the D OAH , the
571City has agreed to utilize Administrative Law Judges to hear,
581inter alia , bid protests involving the City.
5883. On May 7, 2007 , the City issued Invitation to Bid
599No. ITB - PW060607 - 88. The Invitation t o Bid sought bids for
613replacement of approximately 38,000 linear feet of two - inch
624galvanized pipe and associated appurtenances with 38,000 feet of
634four and six - inch DR18 PVC piping and associated appurtenances.
645The replacement would include approximately 385 service
652connections with Sch - 80 PVC piping, all within the area known as
665Section 4 of the City. In addition, the scope of work included
677relocation of approximatel y 460 linear feet of eight - inch PVC
689water main pipe and associated appurtenances with 600 linear
698feet of eight - inch DR18 PVC piping and appu rtenances along State
711Road 78.
7134. A total specification package and complete set of
722drawings for the aforementioned work was prepared by the City's
732consulting engin eer, TetraTech - HAI (hereinafter "Ttech" ). The
742specifications and drawings by Ttech were made a part of the
753Invitation to Bid.
7565. A pre - bid conference was held on May 16, 2007. At that
770conference, several issues were discussed, resulting in issuance
778of an Addendum to the Invitation to Bid. The Addendum was
789issued the same day as the conference and in cluded the following
801paragraph:
802Will the City allow directional drilling on
809the galvanized pipe replacement project?
814No. All references to directional drilling
820on the galvanized pipe replacem ent project
827are to be modified to jack & bore. All
836water main piping proposed to cross
842driveways shall be installed via jack & bore
850or open cut methods. Water main piping
857proposed to cross roadways, including long
863side services, shall be installed by jac k &
872bore methods. Directional drilling is
877acceptable for the roadway crossings on the
884SR 78 Water Main Replacement portions only.
891Please see the enclosed revised Measurement
897and Payment section of the specifications
903(0 1025) and revised bid schedule. ( Em phasis
912in original document. )
9166. The Addendum also extended the due dates for bids by
927one week, to June 13, 2007. No protest was filed with the City
940with respect to the terms, conditions or specifications
948contained in the Invitation to Bid and the Adde ndum. On
959Wednesday, June 13, 2007, the City opened the bids.
9687. Petitioner's bid was the low bid for the project. Its
979bid included a price of $1,816,224 , as compared to the second
992lowest bidder, Guymann (whose bid came in at $1,987,561). 1 The
1005bids wer e then reviewed by Ttech for conformity to the
1016Invitation to Bid.
10198. On July 31, 2007 , Ttech notified the City that it was
1031recommending approval of the Guymann bid despite Petitioner
1039being the low bidder. The justification for that recommendation
1048was as follows:
1051The lowest apparent bidder on the project
1058was Expertech Network Installation, Inc.
1063(Expertech) with a total bid of
1069$1,8 16 , 2 24.00. [Ttech] reviewed Expertech's
1077bid package and found that the required list
1085of at least five completed projects of t he
1094type as the Galvanized Water Main
1100Replacement project was not included in the
1107package. [Ttech] contacted Expertech
1111concerning the incomplete bid package and
1117requested that Expertech provided the
1122required list of at least five projects
1129completed by Expe rtech of similar type as
1137the Galvanized Water Main Replacement
1142project. The list provided by Expertech did
1149not include any completed projects of the
1156type as the Galvanized Water Main
1162Replacement.
11639. On August 7, 2007, the City issued its Notice of Inte nt
1176to Award, stating that the procurement division of the City
1186would recommend award of the bid to Guymann as the most
1197responsive, responsible bidder meeting the terms, conditions ,
1204and specifications set forth in the Invitation to Bid.
121310. Petitioner t imely filed a Notice of Intent to Protest;
1224its Formal Written Protest was timely filed on August 24, 2007,
1235along with the required bond.
124011. There are three methods of drilling utilized for
1249laying pipe in the ground: d irectional drilling, o pen c ut
1261dri lling, and j ack & b ore drilling. A brief discussion of each
1275is necessary in order to understand the dispute in this matter.
1286Directional drilling is done utilizing a machine that is guided
1296underground using steel rods. A person above ground with a
1306soundin g device directs the steel rods from one point to
1317another. Directional boring is used when trenching or
1325excavating is not practical. Directional boring minimizes
1332environmental disruption. Jack & b ore drilling (or auger
1341drilling) is similar to directiona l drilling in that it has an
1353entrance pit , and then the pipe is manually jacked along the
1364desired path while simultaneously excavating the soil. It is
1373often used in projects that have to go under existing roads or
1385driveways. Open c ut drilling is the old, traditional method of
1396digging a trench in the ground and l aying the pipe in the open
1410cut.
141112. The Invitation to Bid, at page 10 of 53, included a
1423request for each bidder to provide evidence of its experience
1433with similar projects. Paragraph 5 asked for a list "of the
1444last five projects of this type your organization has
1453completed." 2 Paragraph 6 asked for a list "of projects of this
1465type that your organization is currently engaged in." The lists
1475of projects were to be completed as set forth in a table
1487attached to the Invitation to Bid. The table is recreated
1497below:
1498PROJECT YOUR CONTRACTOR REQUIRED ACTUAL NAME,
1504TITLE CONTRACT OR SUB COMPLETION COMPLETION ADDRESS
1511& AMOUNT DATE DATE &
1516LOCATION PHONE #
151913. In its Bid, Petit ioner provided a document entitled
"1529Bidders Qualifications" in response to p aragraph 5. The
1538document was not on the table provided and was not entirely
1549responsive to the information requested ( i.e. , it did not
1559indicate whether Petitioner was contractor or subcontractor ;
1566there were no completion dates, and there were no contact
1576persons). Nonetheless, the list contained eight completed
1583projects. Those projects included two water main projects; the
1592other six completed projects were telecommunication project s.
1600While both types of projects would include drilling, there are
1610distinct differences between the two. For example, water and
1619wastewater projects require pressure testing, bacterial testing,
1626and permitting that telecommunication projects do not.
1633Petiti oner's list also included projects that involved
1641directional drilling. Since directional drilling was
1647specifically prohibited in the galvanized pipe replacement
1654project, those projects would not be deemed substantially
1662similar in type. 3
166614. During the i nitial review of the bids, Ttech had
1677specifically asked Petitioner to provide the required list of
1686five completed projects of a similar type. In response,
1695Petitioner submitted a list of four projects , which were listed
1705as "Currently in Progress." Again, the projects were submitted
1714on a form other than the table provided in the Invitation to
1726Bid. When Ttech followed up with the project contacts, it found
1737that there had been no open cut drilling on two of them; the
1750other two had not yet begun. However, by the date of final
1762hearing the projects were substantially complete.
176815. After Petitioner had submitted its list of projects, a
1778meeting was called at the City. Petitioner was represented at
1788the meeting along with City personnel and a representative fro m
1799Ttech. Notes from that meeting, though inconclusive, seem to
1808indicate that the requirement for five completed jobs of a
1818similar nature was discussed. It is unclear whether
1826Petitioner's representative was still at the meeting when this
1835was discussed. H owever, it does not appear that anyone from the
1847City or Ttech sent Petitioner a written request to provide
1857evidence of additional work performed. Nor is there any
1866evidence that the City or Ttech had an obligation to do so. At
1879any rate, Petitioner did not submit any evidence of similar
1889projects other than those discussed above.
189516. There were notes made by attendees of the meeting.
1905None of the notes submitted into evidence was conclusive as to
1916all issues that were discussed at that time. However, in no tes
1928relating to a telephone conversation five days later, Ttech's
1937representative noted discussing with Petitioner the need to
1945provide evidence of five similar projects , which means that at
1955the time of the June 9 , 2007, meeting, Ttech was still
1966attempting t o get the required list of projects from Petitioner.
197717. The projects submitted by Petitioner include
1984directional drill excavation projects , which involved at least
1992some open cuts ( i.e. , to make tie - ins at each end of the
2007directional drill section). No ne of those projects was
2016substantially similar in type to the proposed project, but did
2026include s ome open cut work.
2032CONCLUSIONS OF LAW
20351 8 . DOAH has jurisdiction over this matter pursuant to a
2047contract with the City and in accordance with City Ordinance
2057No. 68 - 07 .
20621 9 . Cape Coral City Ordinance No. 68 - 07 sets forth the
2076procedures for bidding on projects involving the City. Included
2085in the rules for the bid selection process is a mandate that the
2098City evaluate "[T]he professional qualifications, related
2104experience and adequacy of the personnel assigned to the
2113project" and also "[T]he prior experience and references of the
2123proposer." § 2 - 144(i)(4)(b), Ordinance 68 - 07. The failure of
2135Petitioner to submit a list of five completed projects related
2145to galvan ized pipe replacement made it impossible for the City
2156to properly evaluate Petitioner's experience and professional
2163qualifications.
216420 . The burden of proof in this case would be on
2176Petitioner , as it attempts to prove that its bid satisfied all
2187the requir ements of the invitation to bid. Petitioner must
2197establish by competent substantial evidence that it complied
2205with the requirements in the Invitation to Bid, i.e., that
2215Petitioner's bid included the required lists of pending and
2224approved projects of the s ame kind. See , e.g. , Asphalt Pavers,
2235Inc. v State of Florida, Department of Transportation , 602 So.
22452d 558 (Fla. 1st DCA 1992).
225121 . A bid challenge proceeding is de novo in nature, but
2263de novo in the form of an intra - agency review to evaluate the
2277action taken by the [municipality] at the time it took the
2288action. State Contracting and Engineering Corporation v .
2296Department of Transportation , 709 So. 2d 607 (Fla. 1st DCA
23061998). The Administrative Law Judge in such cases does not sit
2317as a substitute for th e municipality in determining whether the
2328right party prevailed in the proceeding. "Instead, the [ALJ]
2337sits in a review capacity , and must determine whether the bid
2348review criteria . . . have been satisfied." Intercontinental
2357Properties, Inc. v. State De partment of Health and
2366Rehabilitative Services , 606 So. 2d 380, 386 (Fla. 3rd DCA
23761992).
23772 2 . In order for Petitioner herein to prevail, it must
2389prove by a preponderance of the evidence that the City's
2399decision to reject Petitioner's bid was clearly erron eous,
2408contrary to competition or arbitrary and capricious. See Miami -
2418Dade County School Board v. Ruiz School Bus Service, Inc. ,
2428874 So. 2d 59 (Fla. 3rd DCA 2004), wherein the court discussed
2440material deviations from bid specifications. An omission or
2448de viation would be considered minor if it does not give the
2460owner of the project "a ny reason to doubt the bidder's ability
2472to fulfill their contracts." Id. at 60. Inasmuch as the City's
2483rejection of Petitioner's bid was based on the fact that
2493Petitioner fa iled to provide substantive information concerning
2501its experience, the omission of five similar projects could not
2511be deemed minor. Petitioner has not met its burden to prove
2522that Respondent's actions were erroneous, contrary to
2529competi tion, arbitrary or capricious.
25342 3 . The City's action concerning Petitioner's bid was
2544based on logic and reason. If it could not ascertain
2554Petitioner's experience, the City could not comfortably award a
2563contract to that entity.
2567RECOMMENDATION
2568Based on the foregoing Findi ngs of Fact and Conclusions of
2579Law, it is
2582RECOMMENDED that a final order be entered by the City of
2593Cape Coral upholding its rejection of Petitioner's bid for the
2603galvanized pipe replacement project.
2607DONE AND ENTERED this 9th day of November , 2007 , in
2617Tall ahassee, Leon County, Florida.
2622S
2623R. BRUCE MCKIBBEN
2626Administrative Law Judge
2629Division of Administrative Hearings
2633The DeSoto Building
26361230 Apalachee Parkway
2639Tallahassee, Florida 32399 - 3060
2644(850) 488 - 9675 SUNCOM 278 - 9675
2652Fax Filing (850) 921 - 6847
2658www.doah.state.fl.us
2659Filed with the Clerk of the
2665Division of Administrative Hearings
2669this 9th day of November, 2007 .
2676ENDNOTES
26771/ There were eight other bids submitted, but none of the other
2689bidders protested the award; thus, their bids are not relevant
2699to this discussion.
27022/ "Type" is defined in The American Heritage Dictionary of the
2713English Language as "A group of persons or things sharing common
2724traits or characteristics that distinguish them as an
2732identifiable group or c lass; a kind of category." As no other
2744definition of "type" was presented at final hearing, this
2753definition will be used for purposes of this case. No
2763substantive distinction exists between "same type" as opposed to
"2772'sim ilar type' " or any other type.
27793 / The addendum to the Invitation to Bid did allow for some
2792minor directional drilling, but the vast majority of the project
2802involved the other methods of drilling.
28084/ Unless specifically stated otherwise herein, all references
2816to Florida Statutes shall be to the 2007 version.
2825COPIES FURNISHED :
2828William S. Isenberg, Esquire
2832William S. Isenberg and Associates, P.A.
28382005 South Federal Highway, Suite 100
2844Fort Lauderdale, Florida 33316
2848Mark Edward Lupe, Esquire
2852Marilyn W. Miller, Esquire
2856City of Cape Cor al
2861Post Office Box 150027
2865Cape Coral, Florida 33915
2869NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2875All parties have the right to submit written exceptions within
28851 0 days from the date of this Recommended Order. Any exceptions
2897to this Recommended Order should be filed with the agency that
2908will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 11/19/2007
- Proceedings: Petitioner`s Exceptions to Findings of Fact and Conclusions of Law filed.
- PDF:
- Date: 11/09/2007
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 11/01/2007
- Proceedings: Petitioner Expertech Network Installation, Inc.`s Proposed Recommended Order filed.
- PDF:
- Date: 10/29/2007
- Proceedings: Petitioner Expertech Network Installation, Inc.`s Proposed Recommended Order filed.
- PDF:
- Date: 10/29/2007
- Proceedings: Petitioner, Expertech Network Installation, Inc.`s Final Argument Summary of the Argument filed.
- PDF:
- Date: 10/26/2007
- Proceedings: Order Granting Extension of Time (proposed recommended order to be filed by October 29, 2007).
- PDF:
- Date: 10/26/2007
- Proceedings: Respondent, City of Cape Coral`s Proposed Findings of Fact, Conclusions of Law and Recommended Order filed.
- Date: 10/10/2007
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 09/24/2007
- Proceedings: Notice of Hearing (hearing set for October 10, 2007; 9:30 a.m.; Cape Coral, FL).
- Date: 09/21/2007
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
Case Information
- Judge:
- R. BRUCE MCKIBBEN
- Date Filed:
- 09/20/2007
- Date Assignment:
- 09/21/2007
- Last Docket Entry:
- 12/12/2007
- Location:
- Cape Coral, Florida
- District:
- Middle
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
William S. Isenberg, Esquire
Address of Record -
Mark Edward Lupe, Esquire
Address of Record -
Marilyn Wnek Miller, Esquire
Address of Record