07-004365BID Expertech Network Installation, Inc. vs. City Of Cape Coral
 Status: Closed
Recommended Order on Friday, November 9, 2007.


View Dockets  
Summary: Respondent properly rejected Petitioner`s bid for the pipe replacement project.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8EXPERTECH NETWORK INSTALLATION, )

12INC. , )

14)

15Petitioner , )

17)

18vs. ) Case No. 07 - 4365BID

25)

26CITY OF CAPE CORAL , )

31)

32Respondent . )

35)

36RECOMMENDED ORDER

38Pursuant to notice, a final hearing was conducted in this

48case on October 10, 2007, in Cape Coral, Florida, before

58Administrative Law Judge R. Bruce McKibben of the Division of

68Administrative Hearings (DOAH).

71APPEARANCES

72For Petitioner: William S. Isenb erg, Esquire

79William S. Isenberg and Associates, P.A.

852005 South Federal Highway, Suite 100

91Fort Lauderdale, Florida 33316

95For Respondent: Mark Edward Lupe, Esquire

101Marilyn W. Miller, Esquire

105City of Cape Coral

109Post Office Box 150027

113Cape Coral, Florida 33915

117STATEMENT OF THE ISSUE

121The issue in this case is whether Respondent's decision to

131reject the galvanized pipe replacement bid of Petitioner as non -

142responsive was erroneous, an abuse of discre tion, arbitrary or

152capricious.

153PRELIMINARY STATEMENT

155Respondent, the City of Cape Coral (the "City") , issued an

166Invitation to Bid concerning replacement of gal vanized pipe.

175Petitioner was one of the companies responding to the Invitation

185to Bid. The City rejected Petitioner's bid as unresponsive and

195awarded the contract to Guymann Construction of Florida, Inc.

204(Guymann). Guymann did not file any pleadings or o ther

214materials in this case and did not make an appearance at final

226hearing. Upon entry of the Notice of Intent to Award by the

238City, Petitioner filed a Protest of Intended Bid Award. The

248matter was forwarded to the D OAH pursuant to the City's

259Administra ti ve Law Judge Services Contract.

266Pursuant to City Ordinance 68 - 07, a final hearing was

277scheduled by stipulation of the parties on October 10, 2007

287(even though that date was more than 15 days after receipt of

299the protest at DOAH). At final hearing both p arties were

310represented by counsel. Petitioner called four witnesses at the

319final hearing: John Wood, d irector of U.S. Operations for

329Petitioner; Michael Heitzler, s enior p roject m anager for

339Petitioner; David Marinelli, v ice p resident of U.S. Operations

349for Petitioner; and Justin Fredericksen, p roject m anager for

359TetraTech. Petitioner's E xhibits A through K were admitted into

369evidence. Respondent called three witnesses: Justin

375Fredericksen ; David Vallandingham, a ssistant s uperintendent for

383Public Works wit h the City; and George Reilly, u tilities m anager

396for the City. Respondent's E xhibits 1 through 1 3 were admitted

408into evidence by stipulation.

412A T ranscript of the final hearing was filed with DOAH on

424October 23, 2007 . The parties were given until Octo ber 26 ,

4362007, to file proposed findings of fact, conclusions of law, and

447written closing statements. Petitioner asked and was granted

455three additional days to submit its proposed recommended order.

464Each party timely filed a P roposed R ecommended O rder , an d each

478was duly - considered in the preparation of this R ecommended

489O rder.

491FINDINGS OF FACT

4941. Petitioner, Expertech Network Installation, Inc., is a

502division of Bell Canada. Petitioner is a construction and

511engineering division of the parent company. It was set up to

522expand the parent's operations into the United States about nine

532years ago. Petitioner has steadily replaced its Canadian

540employees with U.S. employees over those years.

5472. The City is a governmental entity established under the

557laws of t he State of Florida. By contract with the D OAH , the

571City has agreed to utilize Administrative Law Judges to hear,

581inter alia , bid protests involving the City.

5883. On May 7, 2007 , the City issued Invitation to Bid

599No. ITB - PW060607 - 88. The Invitation t o Bid sought bids for

613replacement of approximately 38,000 linear feet of two - inch

624galvanized pipe and associated appurtenances with 38,000 feet of

634four and six - inch DR18 PVC piping and associated appurtenances.

645The replacement would include approximately 385 service

652connections with Sch - 80 PVC piping, all within the area known as

665Section 4 of the City. In addition, the scope of work included

677relocation of approximatel y 460 linear feet of eight - inch PVC

689water main pipe and associated appurtenances with 600 linear

698feet of eight - inch DR18 PVC piping and appu rtenances along State

711Road 78.

7134. A total specification package and complete set of

722drawings for the aforementioned work was prepared by the City's

732consulting engin eer, TetraTech - HAI (hereinafter "Ttech" ). The

742specifications and drawings by Ttech were made a part of the

753Invitation to Bid.

7565. A pre - bid conference was held on May 16, 2007. At that

770conference, several issues were discussed, resulting in issuance

778of an Addendum to the Invitation to Bid. The Addendum was

789issued the same day as the conference and in cluded the following

801paragraph:

802Will the City allow directional drilling on

809the galvanized pipe replacement project?

814No. All references to directional drilling

820on the galvanized pipe replacem ent project

827are to be modified to jack & bore. All

836water main piping proposed to cross

842driveways shall be installed via jack & bore

850or open cut methods. Water main piping

857proposed to cross roadways, including long

863side services, shall be installed by jac k &

872bore methods. Directional drilling is

877acceptable for the roadway crossings on the

884SR 78 Water Main Replacement portions only.

891Please see the enclosed revised Measurement

897and Payment section of the specifications

903(0 1025) and revised bid schedule. ( Em phasis

912in original document. )

9166. The Addendum also extended the due dates for bids by

927one week, to June 13, 2007. No protest was filed with the City

940with respect to the terms, conditions or specifications

948contained in the Invitation to Bid and the Adde ndum. On

959Wednesday, June 13, 2007, the City opened the bids.

9687. Petitioner's bid was the low bid for the project. Its

979bid included a price of $1,816,224 , as compared to the second

992lowest bidder, Guymann (whose bid came in at $1,987,561). 1 The

1005bids wer e then reviewed by Ttech for conformity to the

1016Invitation to Bid.

10198. On July 31, 2007 , Ttech notified the City that it was

1031recommending approval of the Guymann bid despite Petitioner

1039being the low bidder. The justification for that recommendation

1048was as follows:

1051The lowest apparent bidder on the project

1058was Expertech Network Installation, Inc.

1063(Expertech) with a total bid of

1069$1,8 16 , 2 24.00. [Ttech] reviewed Expertech's

1077bid package and found that the required list

1085of at least five completed projects of t he

1094type as the Galvanized Water Main

1100Replacement project was not included in the

1107package. [Ttech] contacted Expertech

1111concerning the incomplete bid package and

1117requested that Expertech provided the

1122required list of at least five projects

1129completed by Expe rtech of similar type as

1137the Galvanized Water Main Replacement

1142project. The list provided by Expertech did

1149not include any completed projects of the

1156type as the Galvanized Water Main

1162Replacement.

11639. On August 7, 2007, the City issued its Notice of Inte nt

1176to Award, stating that the procurement division of the City

1186would recommend award of the bid to Guymann as the most

1197responsive, responsible bidder meeting the terms, conditions ,

1204and specifications set forth in the Invitation to Bid.

121310. Petitioner t imely filed a Notice of Intent to Protest;

1224its Formal Written Protest was timely filed on August 24, 2007,

1235along with the required bond.

124011. There are three methods of drilling utilized for

1249laying pipe in the ground: d irectional drilling, o pen c ut

1261dri lling, and j ack & b ore drilling. A brief discussion of each

1275is necessary in order to understand the dispute in this matter.

1286Directional drilling is done utilizing a machine that is guided

1296underground using steel rods. A person above ground with a

1306soundin g device directs the steel rods from one point to

1317another. Directional boring is used when trenching or

1325excavating is not practical. Directional boring minimizes

1332environmental disruption. Jack & b ore drilling (or auger

1341drilling) is similar to directiona l drilling in that it has an

1353entrance pit , and then the pipe is manually jacked along the

1364desired path while simultaneously excavating the soil. It is

1373often used in projects that have to go under existing roads or

1385driveways. Open c ut drilling is the old, traditional method of

1396digging a trench in the ground and l aying the pipe in the open

1410cut.

141112. The Invitation to Bid, at page 10 of 53, included a

1423request for each bidder to provide evidence of its experience

1433with similar projects. Paragraph 5 asked for a list "of the

1444last five projects of this type your organization has

1453completed." 2 Paragraph 6 asked for a list "of projects of this

1465type that your organization is currently engaged in." The lists

1475of projects were to be completed as set forth in a table

1487attached to the Invitation to Bid. The table is recreated

1497below:

1498PROJECT YOUR CONTRACTOR REQUIRED ACTUAL NAME,

1504TITLE CONTRACT OR SUB COMPLETION COMPLETION ADDRESS

1511& AMOUNT DATE DATE &

1516LOCATION PHONE #

151913. In its Bid, Petit ioner provided a document entitled

"1529Bidders Qualifications" in response to p aragraph 5. The

1538document was not on the table provided and was not entirely

1549responsive to the information requested ( i.e. , it did not

1559indicate whether Petitioner was contractor or subcontractor ;

1566there were no completion dates, and there were no contact

1576persons). Nonetheless, the list contained eight completed

1583projects. Those projects included two water main projects; the

1592other six completed projects were telecommunication project s.

1600While both types of projects would include drilling, there are

1610distinct differences between the two. For example, water and

1619wastewater projects require pressure testing, bacterial testing,

1626and permitting that telecommunication projects do not.

1633Petiti oner's list also included projects that involved

1641directional drilling. Since directional drilling was

1647specifically prohibited in the galvanized pipe replacement

1654project, those projects would not be deemed substantially

1662similar in type. 3

166614. During the i nitial review of the bids, Ttech had

1677specifically asked Petitioner to provide the required list of

1686five completed projects of a similar type. In response,

1695Petitioner submitted a list of four projects , which were listed

1705as "Currently in Progress." Again, the projects were submitted

1714on a form other than the table provided in the Invitation to

1726Bid. When Ttech followed up with the project contacts, it found

1737that there had been no open cut drilling on two of them; the

1750other two had not yet begun. However, by the date of final

1762hearing the projects were substantially complete.

176815. After Petitioner had submitted its list of projects, a

1778meeting was called at the City. Petitioner was represented at

1788the meeting along with City personnel and a representative fro m

1799Ttech. Notes from that meeting, though inconclusive, seem to

1808indicate that the requirement for five completed jobs of a

1818similar nature was discussed. It is unclear whether

1826Petitioner's representative was still at the meeting when this

1835was discussed. H owever, it does not appear that anyone from the

1847City or Ttech sent Petitioner a written request to provide

1857evidence of additional work performed. Nor is there any

1866evidence that the City or Ttech had an obligation to do so. At

1879any rate, Petitioner did not submit any evidence of similar

1889projects other than those discussed above.

189516. There were notes made by attendees of the meeting.

1905None of the notes submitted into evidence was conclusive as to

1916all issues that were discussed at that time. However, in no tes

1928relating to a telephone conversation five days later, Ttech's

1937representative noted discussing with Petitioner the need to

1945provide evidence of five similar projects , which means that at

1955the time of the June 9 , 2007, meeting, Ttech was still

1966attempting t o get the required list of projects from Petitioner.

197717. The projects submitted by Petitioner include

1984directional drill excavation projects , which involved at least

1992some open cuts ( i.e. , to make tie - ins at each end of the

2007directional drill section). No ne of those projects was

2016substantially similar in type to the proposed project, but did

2026include s ome open cut work.

2032CONCLUSIONS OF LAW

20351 8 . DOAH has jurisdiction over this matter pursuant to a

2047contract with the City and in accordance with City Ordinance

2057No. 68 - 07 .

20621 9 . Cape Coral City Ordinance No. 68 - 07 sets forth the

2076procedures for bidding on projects involving the City. Included

2085in the rules for the bid selection process is a mandate that the

2098City evaluate "[T]he professional qualifications, related

2104experience and adequacy of the personnel assigned to the

2113project" and also "[T]he prior experience and references of the

2123proposer." § 2 - 144(i)(4)(b), Ordinance 68 - 07. The failure of

2135Petitioner to submit a list of five completed projects related

2145to galvan ized pipe replacement made it impossible for the City

2156to properly evaluate Petitioner's experience and professional

2163qualifications.

216420 . The burden of proof in this case would be on

2176Petitioner , as it attempts to prove that its bid satisfied all

2187the requir ements of the invitation to bid. Petitioner must

2197establish by competent substantial evidence that it complied

2205with the requirements in the Invitation to Bid, i.e., that

2215Petitioner's bid included the required lists of pending and

2224approved projects of the s ame kind. See , e.g. , Asphalt Pavers,

2235Inc. v State of Florida, Department of Transportation , 602 So.

22452d 558 (Fla. 1st DCA 1992).

225121 . A bid challenge proceeding is de novo in nature, but

2263de novo in the form of an intra - agency review to evaluate the

2277action taken by the [municipality] at the time it took the

2288action. State Contracting and Engineering Corporation v .

2296Department of Transportation , 709 So. 2d 607 (Fla. 1st DCA

23061998). The Administrative Law Judge in such cases does not sit

2317as a substitute for th e municipality in determining whether the

2328right party prevailed in the proceeding. "Instead, the [ALJ]

2337sits in a review capacity , and must determine whether the bid

2348review criteria . . . have been satisfied." Intercontinental

2357Properties, Inc. v. State De partment of Health and

2366Rehabilitative Services , 606 So. 2d 380, 386 (Fla. 3rd DCA

23761992).

23772 2 . In order for Petitioner herein to prevail, it must

2389prove by a preponderance of the evidence that the City's

2399decision to reject Petitioner's bid was clearly erron eous,

2408contrary to competition or arbitrary and capricious. See Miami -

2418Dade County School Board v. Ruiz School Bus Service, Inc. ,

2428874 So. 2d 59 (Fla. 3rd DCA 2004), wherein the court discussed

2440material deviations from bid specifications. An omission or

2448de viation would be considered minor if it does not give the

2460owner of the project "a ny reason to doubt the bidder's ability

2472to fulfill their contracts." Id. at 60. Inasmuch as the City's

2483rejection of Petitioner's bid was based on the fact that

2493Petitioner fa iled to provide substantive information concerning

2501its experience, the omission of five similar projects could not

2511be deemed minor. Petitioner has not met its burden to prove

2522that Respondent's actions were erroneous, contrary to

2529competi tion, arbitrary or capricious.

25342 3 . The City's action concerning Petitioner's bid was

2544based on logic and reason. If it could not ascertain

2554Petitioner's experience, the City could not comfortably award a

2563contract to that entity.

2567RECOMMENDATION

2568Based on the foregoing Findi ngs of Fact and Conclusions of

2579Law, it is

2582RECOMMENDED that a final order be entered by the City of

2593Cape Coral upholding its rejection of Petitioner's bid for the

2603galvanized pipe replacement project.

2607DONE AND ENTERED this 9th day of November , 2007 , in

2617Tall ahassee, Leon County, Florida.

2622S

2623R. BRUCE MCKIBBEN

2626Administrative Law Judge

2629Division of Administrative Hearings

2633The DeSoto Building

26361230 Apalachee Parkway

2639Tallahassee, Florida 32399 - 3060

2644(850) 488 - 9675 SUNCOM 278 - 9675

2652Fax Filing (850) 921 - 6847

2658www.doah.state.fl.us

2659Filed with the Clerk of the

2665Division of Administrative Hearings

2669this 9th day of November, 2007 .

2676ENDNOTES

26771/ There were eight other bids submitted, but none of the other

2689bidders protested the award; thus, their bids are not relevant

2699to this discussion.

27022/ "Type" is defined in The American Heritage Dictionary of the

2713English Language as "A group of persons or things sharing common

2724traits or characteristics that distinguish them as an

2732identifiable group or c lass; a kind of category." As no other

2744definition of "type" was presented at final hearing, this

2753definition will be used for purposes of this case. No

2763substantive distinction exists between "same type" as opposed to

"2772'sim ilar type' " or any other type.

27793 / The addendum to the Invitation to Bid did allow for some

2792minor directional drilling, but the vast majority of the project

2802involved the other methods of drilling.

28084/ Unless specifically stated otherwise herein, all references

2816to Florida Statutes shall be to the 2007 version.

2825COPIES FURNISHED :

2828William S. Isenberg, Esquire

2832William S. Isenberg and Associates, P.A.

28382005 South Federal Highway, Suite 100

2844Fort Lauderdale, Florida 33316

2848Mark Edward Lupe, Esquire

2852Marilyn W. Miller, Esquire

2856City of Cape Cor al

2861Post Office Box 150027

2865Cape Coral, Florida 33915

2869NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

2875All parties have the right to submit written exceptions within

28851 0 days from the date of this Recommended Order. Any exceptions

2897to this Recommended Order should be filed with the agency that

2908will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 12/12/2007
Proceedings: Notice of Filing filed.
PDF:
Date: 12/12/2007
Proceedings: Agency Final Order filed.
PDF:
Date: 12/03/2007
Proceedings: Agency Final Order
PDF:
Date: 11/19/2007
Proceedings: Petitioner`s Exceptions to Findings of Fact and Conclusions of Law filed.
PDF:
Date: 11/09/2007
Proceedings: Recommended Order
PDF:
Date: 11/09/2007
Proceedings: Recommended Order (hearing held October 10, 2007). CASE CLOSED.
PDF:
Date: 11/09/2007
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 11/01/2007
Proceedings: Petitioner Expertech Network Installation, Inc.`s Proposed Recommended Order filed.
PDF:
Date: 10/29/2007
Proceedings: Petitioner Expertech Network Installation, Inc.`s Proposed Recommended Order filed.
PDF:
Date: 10/29/2007
Proceedings: Petitioner, Expertech Network Installation, Inc.`s Final Argument Summary of the Argument filed.
PDF:
Date: 10/26/2007
Proceedings: Order Granting Extension of Time (proposed recommended order to be filed by October 29, 2007).
PDF:
Date: 10/26/2007
Proceedings: Respondent, City of Cape Coral`s Proposed Findings of Fact, Conclusions of Law and Recommended Order filed.
PDF:
Date: 10/25/2007
Proceedings: Motion for Extension of Time filed.
PDF:
Date: 10/23/2007
Proceedings: Notice of Filing filed.
PDF:
Date: 10/23/2007
Proceedings: Transcript of Proceedings filed.
Date: 10/10/2007
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 10/08/2007
Proceedings: (Joint) Pre-hearing Stipulation filed.
PDF:
Date: 10/05/2007
Proceedings: Exhibits (exhibits not available for viewing) filed.
PDF:
Date: 10/05/2007
Proceedings: Main Exhibits filed.
PDF:
Date: 09/28/2007
Proceedings: Notice to Bidders filed.
PDF:
Date: 09/27/2007
Proceedings: Notice of Appearance (filed by M. Lupe).
PDF:
Date: 09/24/2007
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 09/24/2007
Proceedings: Notice of Hearing (hearing set for October 10, 2007; 9:30 a.m.; Cape Coral, FL).
Date: 09/21/2007
Proceedings: CASE STATUS: Pre-Hearing Conference Held.
PDF:
Date: 09/20/2007
Proceedings: Notice of Intent to Award filed.
PDF:
Date: 09/20/2007
Proceedings: Protest of Intended Bid Award filed.
PDF:
Date: 09/20/2007
Proceedings: Agency referral filed.

Case Information

Judge:
R. BRUCE MCKIBBEN
Date Filed:
09/20/2007
Date Assignment:
09/21/2007
Last Docket Entry:
12/12/2007
Location:
Cape Coral, Florida
District:
Middle
Agency:
ADOPTED IN PART OR MODIFIED
Suffix:
BID
 

Counsels