07-004410BID
Infrastructure Corporation Of America vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, December 14, 2007.
Recommended Order on Friday, December 14, 2007.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8INFRASTRUCTURE CORPORATION OF ) )
13AMERICA, )
15)
16Petitioner, )
18) Case No. 07-4410BID
22vs. )
24)
25DEPARTMENT OF TRANSPORTATION, )
29)
30Respondent, )
32)
33and )
35)
36DEANGELO BROTHERS, INC., d/b/a )
41DBI SERVICES CORPORATION, )
45)
46Intervenor. )
48RECOMMENDED ORDER
50A duly-noticed final hearing was held in this case by
60Administrative Law Judge T. Kent Wetherell, II, on October 30,
702007, in Tallahassee, Florida.
74APPEARANCES
75For Petitioner: W. Robert Vezina, III, Esquire
82Eduardo S. Lombard, Esquire
86Vezina, Lawrence & Piscitelli, P.A.
91413 East Park Avenue
95Tallahassee, Florida 32301
98For Respondent: C. Denise Johnson, Esquire
104Department of Transportation
107Haydon Burns Building, Mail Station 58
113605 Suwannee Street
116Tallahassee, Florida 32399-0450
119For Intervenor: Cynthia S. Tunnicliff, Esquire
125Brian A. Newman, Esquire
129Pennington, Moore, Wilkinson, Bell &
134Dunbar, P.A.
136215 South Monroe Street, Second Floor
142Post Office Box 10095
146Tallahassee, Florida 32302-2095
149STATEMENT OF THE ISSUE
153The issue is whether the proposed award of Contract No.
163E1G23 to DeAngelo Brothers, Inc. d/b/a DBI Services Corporation
172(DBI) is contrary to the Department of Transportations
180governing statutes, rules, policies, or the specifications in
188the Request for Proposals (RFP).
193PRELIMINARY STATEMENT
195On September 4, 2007, Infrastructure Corporation of
202America, Inc. (ICA), timely filed a Formal Protest Petition with
212the Department of Transportation (Department) challenging the
219Departments proposed award of Contract No. E1G23 to DBI. On
229September 24, 2007, the Department referred the petition to the
239Division of Administrative Hearings (DOAH) for a formal hearing
248pursuant to Section 120.57(3), Florida Statutes. 1 DBI was
257granted leave to intervene through an Order entered on
266September 27, 2007.
269At the final hearing, ICA presented the testimony of David
279Rader and the deposition testimony of Jennifer Perry and Amy
289Burlarley-Hyland; DBI presented the testimony of Ms. Perry and
298Ms. Burlarley-Hyland; and the Department did not present any
307witnesses. The following exhibits were received into evidence
315at the hearing: Joint Exhibits (Jt. Ex.) 1a, 2 through 21, 24,
32725, and 33 through 38 2 ; Petitioners Exhibits 1 and 2; and
339Intervenors Exhibits 1 and 2.
344The two-volume Transcript of the final hearing was filed on
354November 13, 2007. The parties requested and were given 21 days
365from that date to file proposed recommended orders (PROs), and
375thereby waived the deadline for this Recommended Order. See
384Fla. Admin. Code R. 28-106.216(2). The PROs were timely filed
394and have been given due consideration.
400FINDINGS OF FACT
4031. On June 18, 2007, the Department issued RFP No. E1G23,
414which solicited proposals for ultra asset maintenance for
422Interstate 75 (I-75) and interchanges in Broward, Collier, Lee,
431Charlotte, Manatee, Desoto, and Sarasota Counties.
4372. The Department issued three addenda to the RFP. The
447addenda did not make any material changes that are pertinent to
458the issues in this proceeding.
4633. The Scope of Services for the RFP stated that for all
475roadways and facilities covered by the contract, the contractor
484will be responsible for performing all of the maintenance
493activities that would otherwise have been performed by the
502Department, including but not limited to, mowing the right-of-
511way, maintaining guardrails, fixing potholes, maintaining
517stormwater management facilities, cleaning and maintaining rest
524areas, tree trimming, and incident response and management.
5324. In the asset management industry, this type of contract
542is known as a comprehensive asset management contract because
551the contractor is responsible for all maintenance activities
559within the right-of-way from fence to fence, including the
568fence.
5695. The RFP states that the contract will be awarded to the
581responsive and responsible vendor whose proposal receives the
589highest total score, which is composed of a price score and a
601technical score. The price score is weighted 30 percent, and
611the technical score is weighted 70 percent.
6186. The vendor proposing the lowest price received the full
62830 points for the price score. The other vendors price scores
639were calculated through a mathematical formula based upon the
648percentage that the vendors price exceeded the lowest price.
6577. The technical score was based upon a subjective
666evaluation of the proposals in four broad categories:
674administration plan (weighted 20 points); management and
681technical plan (weighted 30 points); operation plan (weighted 30
690points); and compliance plan (weighted 20 points). There are
699sub-categories in each of those categories, with a specific
708number of points assigned to each sub-category.
7158. Five evaluators independently reviewed the proposals.
722The evaluators - Jennifer Perry, Howard Summers, David Holden,
731Lance Grace, and Robert Mannix -- were Department employees
740selected based upon their familiarity with the areas and
749services covered by the contract.
7549. All of the evaluators attended the pre-bid conference,
763which was mandatory for prospective bidders. No questions or
772concerns were raised at the pre-bid conference or at any point
783prior to submittal of the proposals regarding the evaluators
792having experience with the prior I-75 contract or having been
802involved in the preparation of the RFP.
80910. Three companies -- ICA, DBI, and VMS, Inc. (VMS) --
820submitted responses to the RFP.
82511. ICA is a Tennessee corporation. DBI is a Pennsylvania
835corporation. Both companies provide asset management services
842in Florida and around the country, but ICA has more experience
853than DBI in providing comprehensive asset management services.
86112. The price offered by ICA -- $89,200,300.01 -- was the
874lowest of the three vendors that responded to the RFP; the price
886offered by DBI -- $92,630,739 -- was approximately 3.8 percent
898higher. As a result, ICA received a price score of 30 and DBI
911received a price score of 28.89.
91713. Three of the five evaluators -- Ms. Perry, Mr.
927Summers, and Mr. Golden -- scored DBIs proposal the highest.
937Two of the evaluators -- Mr. Grace and Mr. Mannix -- scored
949ICAs proposal higher than DBIs proposal, but they scored VMS's
959proposal the highest. None of the evaluators scored ICAs
968proposal the highest.
97114. DBIs proposal received an average score of 85.40 from
981the evaluators, and ICAs proposal received an average score of
99182.96. As result, DBI received a technical score of 59.78, and
1002ICA received a technical score of 58.07.
100915. When the price scores and the technical scores were
1019combined, DBI received the highest total score of 88.67. ICA
1029was the second-ranked vendor with a total score of 88.07. VMS
1040was the third-ranked vendor with a total score of 86.12. 3
105116. On August 21, 2007, the Department posted notice of
1061its intent to award the contract to DBI.
106917. The initial posting erroneously identified the winning
1077vendor as DeAngelo Brothers, Inc. T/A Aguagenix, Inc. rather
1086than DBI. The contract administrator, Cheryl Sanchious,
1093explained that this was a clerical error caused by the
1103Departments computer system and that it has been corrected in
1113the system.
111518. ICA timely filed a notice of protest and a formal
1126written protest challenging the award to DBI. ICA posted a
1136cashiers check in the statutorily required amount in lieu of a
1147protest bond.
114919. After the protest was filed, the Department entered
1158into temporary emergency asset management contracts for the
1166roadways and facilities covered by contract at issue in this
1176case. ICA was given the contract for Broward and Collier
1186Counties because it was already providing asset management in
1195those counties under the predecessor to the contract at issue in
1206this case, No. BC680. DBI was given the contract for the other
1218counties, Sarasota, Lee, Manatee, Charlotte, and Desoto.
122520. It is undisputed that ICAs proposal was responsive to
1235the RFP in all material respects.
124121. The focus of ICAs protest is four-fold. First, ICA
1251contends that DBIs proposal is not responsive because it did
1261not affirmatively state that it would grant a first right of
1272refusal to RESPECT of Florida (RESPECT). Second ICA contends
1281that DBI is not a responsible vendor and that the Department
1292confused the concepts of responsiveness and responsibility
1299in its review of the proposals. Third, ICA contends that the
1310evaluation committee failed to prepare a technical summary as
1319required by the RFP, and that its failure to do so was material
1332because it would have brought to light the discrepancies in Ms.
1343Perry's scoring. Fourth, ICA contends that Ms. Perry's scoring
1352was flawed and out of sync with the other evaluators in several
1364respects. Each issue is discussed in turn.
1371(1) Responsiveness / RESPECT First Right of Refusal
137922. Section 8.2 of the RFP provides that [a] responsive
1389proposal shall perform the scope of services called for in this
1400Proposal Requirements [sic] and receive a Technical Proposal
1408score of at least seventy (70) percent of the maximum attainable
1419points established for scoring the Technical Proposal.
142623. Section 17.1 of the RFP provides that [d]uring the
1436process of evaluation, the District Contracts Office will
1444conduct examinations of Proposals for responsiveness to
1451requirements of the Proposal Solicitation. Those determined to
1459be non-responsive will be automatically rejected.
146524. Section 16.5 of the RFP requires the proposal to
1475[u]se only statements of what the Proposer will or will not
1486accomplish rather than words such as may, might, should, etc.
149625. Section 8.5 of the RFP authorizes the Department to
1506waive minor informalities or irregularities in Proposals
1513received where such is merely a matter of form and not
1524substance, and the correction or waiver of which is not
1534prejudicial to other Proposers. That section defines minor
1542irregularities as those that will not have an adverse effect
1552on the Departments interest and will not affect the price of
1563the Proposal by giving a Proposer an advantage or benefit not
1574enjoyed by other Proposers.
157826. The Scope of Services for the RFP requires the
1588contractor to grant Respect of Florida a first right of
1598refusal to provide maintenance services at rest areas. This
1607was intended by the Department to be a mandatory requirement of
1618the RFP, and was understood as such by ICA and DBI.
162927. RESPECT is a not-for-profit organization that employs
1637disabled and disadvantaged individuals. RESPECT employees
1643perform janitorial and grounds maintenance functions at rest
1651areas, including one of the rest areas covered by the RFP.
166228. ICAs proposal expressly states that ICA will grant
1671Respect of Florida first right of refusal on rest area
1681janitorial work consistent with statewide maintenance
1687practices.
168829. DBIs proposal does not include an affirmative
1696statement that it will grant RESPECT a first right of refusal.
1707However, DBI stated in its proposal that it is currently in
1718negotiation with [RESPECT] to expand their existing maintenance
1726responsibilities for rest areas within the project limits and
1735that DBI Services believes that expanding [RESPECTs]
1742responsibilities in the project is the right thing to do.
175230. The absence of an affirmative statement in DBIs
1761proposal that it will grant RESPECT a first right of refusal was
1773not material to the evaluators. For example, evaluator Robert
1782Mannix testified that he generally looked for more of the
1792intent to give [RESPECT] the opportunity of making a bid rather
1803than the specific language of right of first refusal. 4
1813Similarly Ms. Perry testified that she considered granting
1821RESPECT a first right of refusal to be a requirement of the
1833contract whether or not the contractor mentioned it in its
1843proposal.
184431. Amy Burlarley-Hyland, director of asset management for
1852DBI, testified that DBI intends to provide a first right of
1863refusal to RESPECT and that, consistent with the statement in
1873DBIs proposal, DBI is committed to expanding Respects
1881responsibilities on this project. She explained that she did
1890not include an affirmative statement to that effect in the
1900proposal because it is a known requirement that will be part
1911of the contract by virtue of it being in the RFP.
192232. Mr. Rader, ICAs executive vice president, testified
1930that it is more costly to contract with RESPECT to provide
1941maintenance services than to contract with another entity to
1950provide those services. Ms. Hyland disagreed with that
1958testimony, as did Ms. Perry.
196333. No documentation was provided to support Mr. Raders
1972claim that it is more expensive to contract with RESPECT, and
1983the evidence was not persuasive that DBI received a competitive
1993advantage by not affirmatively stating in its proposal that it
2003will grant a first right of refusal to RESPECT.
201234. The RFP does not require the vendor to expressly
2022acknowledge and affirmatively agree to meet each and every
2031mandatory requirement in the RFP. Indeed, if this were the test
2042for responsiveness, ICAs proposal would be nonresopnsive
2049because it failed to expressly acknowledge and affirmatively
2057agree to meet a number of the mandatory requirements in the RFP.
206935. DBIs proposal complies with the intent of the RFP in
2080regards to RESPECT. Its failure to specifically state that it
2090will grant RESPECT a first right of refusal is, at most, a minor
2103irregularity.
2104(2) Failure to Determine DBIs Responsibility
211036. Responsiveness and responsibility are separate, but
2117related concepts in the competitive procurement context.
212437. Section 287.012(24), Florida Statutes, defines
2130responsible vendor to mean a vendor who has the capability in
2141all respects to fully perform the contract requirements and the
2151integrity and reliability that will assure good faith
2159performance.
216038. Section 287.012(26), Florida Statutes, defines
2166responsive vendor to mean a vendor that has submitted a bid,
2177proposal, or reply that conforms in all material respects to the
2188solicitation.
218939. In order to bid on certain Department contracts, a
2199vendor has to be pre-qualified under Florida Administrative Code
2208Rule Chapter 14-22. Pre-qualification serves as an advance
2216determination of the vendors responsibility.
222140. Pre-qualification is generally not required in order
2229to bid on maintenance contracts; bidders are presumed qualified
2238to bid on such contracts. However, as noted in the Bid
2249Solicitation Notice for the RFP, certain maintenance contracts
2257will contain specific requirements for maintenance contractor
2264eligibility if deemed necessary by the Department. This is
2273such a maintenance contract.
227741. Section 7.1 of the RFP required the Department to
2287determine whether the proposer is qualified to perform the
2296services being contracted. That determination was to be made
2305based upon the[] Proposal Package demonstrating satisfactory
2312experience and capability in the work area. The RFP did not
2323specify when or by whom this determination was to be made.
233442. The Department and DBI contend that the determination
2343required by Section 7.1 is essentially a determination of
2352whether the bidder is responsible, and that the determination is
2362to be made by the evaluators during their scoring of the
2373proposals. In support of that contention, the Department and
2382DBI refer to Section 17.1 of the RFP, which provides that
2393[p]roposing firms must receive an average technical proposal
2401score of at least (70) percent of the maximum attainable points
2412established for scoring the Technical Proposal to be considered
2421responsive. Similar language is included in Section 8.2 of the
2431RFP under the heading Responsiveness of Proposals.
243843. The interpretation of the RFP advocated by the
2447Department and DBI is reasonable, and DBIs proposal received an
2457average score from the evaluators of 85.40, which exceeds the 70
2468percent threshold in Section 17.1 of the RFP. Indeed, each of
2479the evaluators gave DBI more than 70 points for its technical
2490proposal.
249144. The preponderance of the evidence presented at the
2500final hearing supports the Department's implicit determination
2507that DBI is qualified to perform the services being
2516contracted, as required by Section 7.1 of the RFP.
252645. DBI has a 29-year history. It employs approximately
2535700 employees in 34 offices nationwide; it is the largest
2545vegetation management company in the world; and it is ranked in
2556the top five nationally in Pavement Maintenance Magazine .
256546. Even though DBI has less experience in comprehensive
2574asset management contracts than does ICA, DBI has extensive
2583experience in managing comprehensive activities under large
2590contracts. DBI has managed over $400 million in performance-
2599based contracts nationwide, including a $9 million comprehensive
2607asset management contract with the Department in District 4 (US
261727/Belle Glade area), and DBIs director of asset management has
2627extensive experience in highway and facility asset management in
2636the private sector with DBI and VMS and in the public sector
2648with the New York Department of Transportation.
265547. In sum, a determination that DBI is a responsible
2665bidder was inherent in the Departments decision to award the
2675contract to DBI, which was based in large part on the technical
2687score of its proposal by the evaluators, and the evidence
2697presented in this de novo proceeding supports that
2705determination. Therefore, even if, as ICA argues, the
2713Department and DBI are improperly construing the word
2721responsive in Section 17.1 of the RFP to mean responsible,
2732ICA failed to prove that such error is material to the outcome
2744of this proceeding.
2747(3) Failure to Prepare Technical Summary
275348. Section 17.1 of the RFP describes the evaluation
2762process as follows:
2765A Technical Evaluation Committee . . . will
2773be established to review and evaluate each
2780Proposal Package submitted in response to
2786this Proposal Solicitation. The Committee
2791will be comprised of at least five persons
2799with background, experience, and/or
2803professional credentials in relative service
2808areas.
2809The District Contracts Office will
2814distribute to each member of the Committee a
2822copy of each technical proposal. The
2828Committee members will independently
2832evaluate the Proposals on the criteria in
2839the section below entitled Criteria for
2845Evaluation in order to ensure that the
2852Proposals are uniformly rated. The
2857Committee will then assign points, utilizing
2863the technical evaluation criteria identified
2868herein and complete a technical summary. .
2875. . . (Emphasis supplied).
2880The District Contracts Office and/or the
2886Project Manager/Technical Evaluation
2889Committee will review and evaluate the price
2896packages and prepare a summary of its price
2904evaluation. Points will be assigned based
2910on price evaluation criteria identified
2915herein.
2916During the process of the evaluation, the
2923District Contracts Office will conduct
2928examinations of Proposals for responsiveness
2933to requirements of the Proposal
2938Solicitation. Those determined to be non-
2944responsive will be rejected.
294849. ICA contends that the evaluation committee failed to
2957prepare a technical summary, which would have brought to light
2968the scoring issues discussed below concerning Ms. Perry.
297650. The RFP does not define technical summary nor does
2986it specify the form that the summary must take.
299551. The RFP does not specify how the evaluation committee
3005as a whole would assign points to the proposals in light of the
3018independent scoring mandated by Section 17.1 of the RFP.
302752. The evaluators did not assign points to the proposals
3037as a committee, but rather independently scored the proposals.
304653. The evaluators did not meet as a committee to prepare
3057a technical summary. Several of the evaluators testified that
3066they considered the evaluation form that they completed for each
3076proposal to be their technical summary for the proposal
3085because the form included the scores assigned in each technical
3095review category and summary comments about the proposal.
310354. The evaluators did not collectively discuss their
3111scoring of the proposals after they completed their independent
3120evaluations; they simply submitted their completed evaluation
3127forms to Ms. Sanchious.
313155. Ms. Sanchious office prepared a spreadsheet
3138summarizing the evaluators technical scoring of the proposals.
3146The spreadsheet - Joint Exhibit 33, titled Proposal
3154Evaluation/Breakdown Sheet -- lists the scores awarded by each
3163evaluator in each technical review category; calculates the
3171total points awarded by each evaluator for each proposal; and
3181calculates an overall score for each proposal by averaging the
3191five evaluators scores for each proposal.
319756. This spreadsheet is more akin to a technical summary
3207than is Joint Exhibit 21, which DBI and the Department contend
3218is the technical summary. Indeed, Joint Exhibit 21 only
3227includes the overall score and not the underlying data that
3237was used to calculate that score.
324357. It was not unreasonable for the Department to
3252calculate an overall score for each proposal by simply
3261averaging the five evaluators scores for each proposal, and ICA
3271failed to prove that the averaging being done by Ms. Sanchious
3282office (instead of the evaluation committee) was a material
3291deviation from the RFP. Indeed, ICAs contention that
3299discussion amongst the evaluation committee members to prepare
3307the technical summary would have changed Ms. Perrys scoring
3316of ICAs or DBIs proposal is speculative, at best, in light of
3328the findings below.
333158. In sum, the evaluation committees failure to prepare
3340a technical summary as required by Section 17.1 of the RFP
3351does not undermine the proposed award to DBI.
3359(4) Scoring by Jennifer Perry
336459. Ms. Perry was one of the five evaluators who reviewed
3375the technical proposals submitted in response to the RFP.
338460. Ms. Perry is a licensed professional engineer. She
3393has 10 years of work experience with the Department, and she
3404currently serves as the assistant maintenance engineer for
3412District 1. In that capacity, she is responsible for all forms
3423of maintenance contracting in District 1, including routine
3431maintenance and asset maintenance.
343561. Ms. Perry served for a time as the project manager for
3447the existing asset management contract for I-75, which was held
3457by ICA. As a result, she had the occasion to work with ICA
3470employees and become familiar with ICAs performance under that
3479contract.
348062. There is no evidence that Ms. Perry is biased against
3491ICA in any way. Indeed, she credibly testified that she had a
3503good working relationship with ICA; that she had no major issues
3514with ICAs performance under the existing contract; and that she
3524would have had no hesitation recommending that the contract be
3534awarded to ICA if its proposal had received the highest score.
354563. Ms. Perry was heavily involved in the preparation of
3555the RFP as a result of her position as assistant maintenance
3566engineer for District 1. She was also involved in the selection
3577of the evaluators.
358064. There is no Department rule or policy that prohibits a
3591person from serving as an evaluator if he or she was involved in
3604the preparation of the RFP.
360965. Likewise, the fact that Ms. Perry served as the
3619project manager for the asset management contract held by ICA
3629does not preclude her from serving as an evaluator. Indeed,
3639Section 17.1 of the RFP specifically contemplates that the
3648evaluators will have background, experience, and/or
3654professional credentials in relative service areas. Similar
3661language is contained in Section 287.057(17)(a), Florida
3668Statutes.
366966. Ms. Perry spent between 10½ and 11 hours reviewing and
3680scoring the proposals. She made detailed notes while she was
3690scoring in order to capture her general impressions of each
3700proposal and to serve as a reminder of issues to address with
3712the vendor who was ultimately awarded the contract.
372067. Ms. Perry gave ICAs proposal a score of 74. She gave
3732DBIs proposal a score of 86.
373868. Ms. Perry double-checked her scores before submitting
3746her completed score sheets. She specifically went back over her
3756scoring of ICAs proposal after she noticed that she scored ICA
3767lower than DBI and VMS because she thought she may have added
3779wrong or overlooked something. She decided not to make changes
3789to give ICA additional points just because she liked working
3799with ICA.
380169. The main difference in Ms. Perrys scoring of DBI's and
3812ICA's proposals relates to Plan for Compliance with Standards
3821(Plan for Compliance) section. She gave ICA 10 points for that
3832section, and she gave DBI 20 points, which is the maximum
3843available for that section. Each of the other evaluators gave
3853ICA and DBI very similar scores in the Plan for Compliance
3864section.
386570. The Plan for Compliance section describes the programs
3874that the proposer intends to implement to ensure compliance with
3884the applicable statutes, rules and Department policies. A
3892proposers quality assurance/quality control (QA/QC) program is
3899an important component of its plan for compliance.
390771. DBI gave the Plan for Compliance section significant
3916emphasis because of the weight assigned to the section in the
3927RFP. Ms. Burlarly-Hyland rewrote the section to make it more
3937detailed because of her perception of its importance to the
3947Department.
394872. ICA did not place as significant of an emphasis on the
3960Plan for Compliance section in its proposal as did DBI. Indeed,
3971ICAs position in this case is that a plan for compliance is
3983quite standard and one would expect to see very similar plans
3994and therefore very similar scores among the proposals.
400273. DBI references its QA/QC program several times in the
4012Plan for Compliance section, but the detailed description of the
4022QA/QC program is included in the Management and Technical Plan
4032section of DBIs proposal.
403674. Ms. Perry relied on the description of the QA/QC
4046program in the Management and Technical Plan section of DBIs
4056proposal in her scoring of the Plan for Compliance section.
4066Similarly, in her scoring of the ICA and VMS proposals Ms. Perry
4078did not limit her scoring of a particular section of the
4089proposal to information presented in that section. Instead, she
4098looked at the proposals in their entirety and gave them credit
4109. . . in any section that [she] felt it applied to because . . .
4125[i]f they have a good idea, they need credit for it.
413675. Ms. Perry explained that that she scored DBI higher
4146than ICA in the Plan for Compliance section because, even though
4157both proposals discussed their QA/QC program, DBI went into much
4167greater detail about its program and its plan for compliance
4177generally. Ms. Perry viewed the level of detail provided by DBI
4188regarding its QA/QC program and its plan for compliance
4197generally as an indication of the importance of these matters to
4208DBI.
420976. Some of the material differences identified by Ms.
4218Perry were DBIs commitment to do its first QA/QC within the
4229first three months instead of waiting six months as ICA
4239proposed; DBIs identification of a high-level person, the
4247project manager, as being responsible for compliance; DBIs
4255commitment to provide its QA/QC reports directly to the
4264Department; DBIs corporate culture concept program that is
4272similar to the Departments grassroots program; DBIs more
4280detailed description of its training programs; and DBIs
4288commitment to have all of its herbicide applicators licensed by
4298the state, not just in compliance with state law.
430777. Ms. Perrys rationale for her scoring differences on
4316the Plan for Compliance section is generally consistent with
4325another evaluators overall impression that the ICA proposal
4333did not offer a lot of new innovation or continuous quality
4344improvement over the level of performance that we had already
4354experienced and . . . we were hoping to have in reletting the
4367new contract rather than renewing the existing contract . . . . 5
438078. ICA also takes issue with Ms. Perrys scoring of the
4391ICA and DBI proposals in the DBE/RESPECT/Agency Participation
4399section; the Proposed Facilities Capabilities section; the
4406Routine/Periodic Maintenance Operations section; and the Rest
4413Area Maintenance Operations section.
441779. Ms. Perry gave DBIs proposal five points and ICAs
4427proposal three points for the DBE/RESPECT/Agency Participation
4434section. She explained that she scored DBI higher than ICA in
4445this section because DBI provided more detail on how it would
4456help develop disadvantaged business subcontractors, including
4462training them on compliance with Department standards and
4470helping them obtain work. She recognized that ICA also had a
4481subcontractor development program, but she was more impressed
4489with DBI's proposal because DBI really went into a lot more
4500detail in what they were going to do.
450880. Ms. Perry gave DBIs proposal five points and gave
4518ICAs proposal three points for the Proposed Facilities
4526Capabilities section. She explained that she scored DBI higher
4535than ICA in this section because of the amount and type of
4547equipment that DBI was going to make available for the contract
4558and because of DBIs commitment to put an office on the
4569Alligator Alley corridor. Ms. Perry felt that the Alligator
4578office was very important because that area is isolated and
4588having an office in the area would make it easier for the
4600contractor to respond quickly to problems. ICAs proposal did
4609not commit to put an office on the Alligator Alley corridor.
462081. Ms. Perry gave DBIs proposal ten points and gave
4630ICAs proposal six points for the Routine/Periodic Maintenance
4638Operations section. She explained that she scored DBI higher
4647than ICA in this section because DBIs proposal included a week-
4658by-week maintenance plan that detailed the specific activities
4666that DBI would be working on each week and it also included
4678detailed charts identifying the efforts that DBI would undertake
4687to meet the requirements of the Departments maintenance
4695program. The description of the maintenance plan in ICAs
4704proposal was not nearly as detailed, and Ms. Perry was so
4715impressed with DBIs maintenance plan that she provided copies
4724of the plan to the other districts operation centers as an
4735example of the type of detained planning that she felt the
4746Department should move towards.
475082. Ms. Perry scored ICA and DBI the same for the Rest
4762Area Maintenance Operation section. She explained that even
4770though the proposals focused on different aspects of their rest
4780area maintenance plans, the plans were roughly equivalent
4788overall. For example, DBI committed to maintain the rest areas
4798in accordance with the Departments standard maintenance
4805requirements and, like ICA, DBI will handle customer comment
4814cards from rest areas through its QA/QC program.
482283. Ms. Perry scored ICA higher than DBI in areas that she
4834found ICAs proposal to be better than DBIs proposal. For
4844example, in the Identification of Key Personnel Section, she
4853gave ICA four points and DBI three points; in the Contractor
4864Experience section, she gave ICA the maximum five points and DBI
4875two points; in the Bridge Inspection section, she gave ICA the
4886maximum 10 points and DBI seven points; in the Incident Response
4897Operations section, she gave ICA nine points and DBI eight
4907points; and in the Bridge Maintenance Operations section, she
4916gave ICA the maximum five points and DBI three points.
492684. Ms. Perrys explanation of her scoring decisions was
4935reasonable and supported by the preponderance of the evidence
4944presented at the final hearing. The evidence fails to establish
4954that Ms. Perry's scoring of the proposals was arbitrary,
4963capricious, or otherwise improper.
4967CONCLUSIONS OF LAW
497085. DOAH has jurisdiction over the parties to and subject
4980matter of this proceeding pursuant to Section 120.57(3), Florida
4989Statutes.
499086. ICA has standing to protest the proposed award of the
5001contract to DBI because its proposal received the second-highest
5010overall score. See Preston Carroll Co. v. Florida Keys Aqueduct
5020Authority , 400 So. 2d 524, 525 (Fla. 3d DCA 1981).
503087. ICA has the burden of proof in this proceeding. See
5041§ 120.57(3)(f), Fla. Stat.; State Contracting & Engineering
5049Corp. v. Dept. of Transportation , 709 So. 2d 607 (Fla. 1st DCA
50611998)
506288. The scope of this proceeding and the nature of ICAs
5073burden of proof are as follows:
5079In a competitive-procurement protest, other
5084than a rejection of all bids . . ., the
5094administrative law judge shall conduct a de
5101novo proceeding to determine whether the
5107agency's proposed action is contrary to the
5114agency's governing statutes, the agency's
5119rules or policies, or the solicitation
5125specifications. The standard of proof for
5131such proceedings shall be whether the
5137proposed agency action was clearly
5142erroneous, contrary to competition,
5146arbitrary, or capricious.
5149§ 120.57(3)(f), Fla. Stat.
515389. It is not enough under Section 120.57(3)(f), Florida
5162Statutes, for the protestor to show that the proposed award is
5173inconsistent with some provision of the RFP; the protestor must
5183also show that agencys "misstep" and, hence, the proposed award
5193is clearly erroneous, contrary to competition, arbitrary, or
5201capricious. See , e.g. , Granite Construction Co. of California
5209v. Dept. of Transportation , Case No. 03-2374BID, at ¶ 103 (DOAH
5220Aug. 25, 2003) (quoting Syslogic Technology Services, Inc. v.
5229South Fla. Water Mgmt. Dist. , Case No. 01-4385BID, 2002 Fla.
5239Div. Adm. Hear. LEXIS 235, at ¶¶ 40-74 (DOAH Jan. 18, 2002)),
5251adopted in pertinent part , Case No. 03-067 (DOT Sep. 23, 2003).
526290. The standards in Section 120.57(3)(f), Florida
5269Statutes, have been explained as follows:
5275A decision is considered to be clearly
5282erroneous when although there is evidence to
5289support it, after review of the entire
5296record the tribunal is left with the
5303definite and firm conviction that a mistake
5310has been committed. An agency action is
5317capricious if the agency takes the action
5324without thought or reason or irrationally.
5330Agency action is arbitrary if is not
5337supported by facts or logic. An agency
5344decision is contrary to competition if it
5351unreasonably interferes with the objectives
5356of competitive bidding.
5359Lakeview Center, Inc. v. Agency for Health Care Admin. , Case No.
537006-3412BID, Fla. Div. Adm. Hear. LEXIS 571, at ¶ 44 (DOAH Dec.
53826, 2006; AHCA Dec. 21, 2006) (citations omitted). Accord
5391Syslogic Technology Services , supra .
539691. ICA failed to meet its burden of proof; the evidence
5407fails to establish that the proposed award to DBI is contrary to
5419the RFP in any material respect or that the proposed award is
5431clearly erroneous, contrary to competition, arbitrary, or
5438capricious. Indeed, as detailed in the Findings of Fact, the
5448preponderance of the evidence establishes that DBIs proposal
5456was responsive to the RFP; that DBI is a responsible bidder; and
5468that the scoring of the proposals by Ms. Perry was reasonable
5479and consistent with the RFP as a whole.
5487RECOMMENDATION
5488Based upon the foregoing findings of fact and conclusions
5497of law, it is
5501RECOMMENDED that the Department issue a final order
5509dismissing the Formal Protest Petition filed by ICA, and
5518awarding Contract No. E1G23 to DBI.
5524DONE AND ENTERED this 14th day of December, 2007, in
5534Tallahassee, Leon County, Florida.
5538S
5539T. KENT WETHERELL, II
5543Administrative Law Judge
5546Division of Administrative Hearings
5550The DeSoto Building
55531230 Apalachee Parkway
5556Tallahassee, Florida 32399-3060
5559(850) 488-9675 SUNCOM 278-9675
5563Fax Filing (850) 921-6847
5567www.doah.state.fl.us
5568Filed with the Clerk of the
5574Division of Administrative Hearings
5578this 14th day of December, 2007.
5584ENDNOTES
55851 / All statutory references are to the 2007 version of the
5597Florida Statutes.
55992 / The Joint Exhibits include the deposition testimony of Cheryl
5610Sanchious (Jt. Ex. 34), Howard Summers (Jt. Ex. 35), David
5620Holden (Jt. Ex. 36), Lance Grace (Jt. Ex. 37), and Robert Mannix
5632(Jt. Ex. 38).
56353 / VMS received the highest technical score, but its price score
5647was the lowest because its price -- $108,057,300 -- was, by far,
5661the highest of the three proposals.
56674 / Jt. Ex. 38, at 31. Accord Jt. Ex. 35, at 32-33 (testimony of
5682evaluator Howard Summers).
56855 / Jt. Ex. 38, at 19. See also Jt. Ex. 19 (Mr. Mannix's
5699evaluation form, which states that ICA's proposal "lacks new
5708competitive improvement ideas-appears to maintain status quo").
5716COPIES FURNISHED :
5719James C. Myers, Clerk of Agency
5725Proceedings
5726Department of Transportation
5729Haydon Burns Building, Mail Station 58
5735605 Suwannee Street
5738Tallahassee, Florida 32399-0450
5741Alexis M. Yarbrough, General Counsel
5746Department of Transportation
5749Haydon Burns Building, Mail Station 58
5755605 Suwannee Street
5758Tallahassee, Florida 32399-0450
5761Stephanie Kopelousos, Secretary
5764Department of Transportation
5767Haydon Burns Building, Mail Station 57
5773605 Suwannee Street
5776Tallahassee, Florida 32399-0450
5779C. Denise Johnson, Esquire
5783Department of Transportation
5786Haydon Burns Building, Mail Station 58
5792605 Suwannee Street
5795Tallahassee, Florida 32399-0450
5798Eduardo S. Lombard, Esquire
5802Vezina, Lawrence & Piscitelli, P.A.
5807413 East Park Avenue
5811Tallahassee, Florida 32301
5814Cynthia S. Tunnicliff, Esquire
5818Pennington, Moore, Wilkinson,
5821Bell & Dunbar, P.A.
5825215 South Monroe Street, Second Floor
5831Post Office Box 10095
5835Tallahassee, Florida 32302-2095
5838NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5844All parties have the right to submit written exceptions within
585410 days from the date of this Recommended Order. Any exceptions
5865to this Recommended Order should be filed with the agency that
5876will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 12/14/2007
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 12/14/2007
- Proceedings: Recommended Order (hearing held October 30-31, 2007). CASE CLOSED.
- Date: 11/13/2007
- Proceedings: Transcript (volumes 1 and 2) filed.
- Date: 10/30/2007
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 10/12/2007
- Proceedings: ICA`s Notice of Service of Unverified Amended Response to DBI`s Interrogatories filed.
- PDF:
- Date: 10/12/2007
- Proceedings: ICA`s Amended Response to DBI`s First Set of Interrogatories filed.
- PDF:
- Date: 10/08/2007
- Proceedings: ICA`s Notice of Service of Response to DBI`s Interrogatories filed.
- PDF:
- Date: 10/02/2007
- Proceedings: DBI`s Notice of Service of First Interrogatories to Petitioner, Infrastructure Corporation of America filed.
- PDF:
- Date: 09/27/2007
- Proceedings: Order Granting Petition to Intervene (DeAngelo Brothers, Inc., d/b/a DBI Services Corporation).
- PDF:
- Date: 09/27/2007
- Proceedings: Notice of Hearing (hearing set for October 30 and 31, 2007; 9:00 a.m.; Tallahassee, FL).
- Date: 09/26/2007
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
Case Information
- Judge:
- T. KENT WETHERELL, II
- Date Filed:
- 09/24/2007
- Date Assignment:
- 09/25/2007
- Last Docket Entry:
- 01/14/2008
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
C. Denise Johnson, Esquire
Address of Record -
Eduardo S. Lombard, Esquire
Address of Record -
Cynthia S. Tunnicliff, Esquire
Address of Record -
C. Denise Johnson, Assistant General Counsel
Address of Record