08-003984 Hancock Bridge Marina, Llc. vs. Florida Fish And Wildlife Conservation Commission And Department Of Environmental Protection
 Status: Closed
Recommended Order on Friday, May 15, 2009.


View Dockets  
Summary: Application for an environmental resource permit and proprietary authorization to enlarge a dock and number of slips are denied, where the project will cause adverse impacts on manatees.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8HANCOCK BRIDGE MARINA, LLC, )

13)

14Petitioner, )

16)

17vs. ) Case No. 08-3984

22)

23DEPARTMENT OF ENVIRONMENTAL )

27PROTECTION and FLORIDA FISH )

32AND WILDLIFE CONSERVATION )

36COMMISSION, )

38)

39Respondents. )

41_______________________________ )

43RECOMMENDED ORDER

45Pursuant to notice, this matter was heard before the

54Division of Administrative Hearings by its assigned

61Administrative Law Judge, Donald R. Alexander, on February 24

70and 25, 2009, in Fort Myers, Florida.

77APPEARANCES

78For Petitioner: Matthew D. Uhle, Esquire

84Knott, Consoer, Ebelini,

87Hart & Swett, P.A.

911625 Hendry Street, Third Floor

96Fort Myers, Florida 33901-2969

100James E. Moon, Esquire

104Alvarez, Sambol, Winthrop & Madson, P.A.

1103451 Bonita Bay Boulevard

114Suite 200

116Bonita Springs, Florida 34134-4354

120For Respondent: Kelly K. Samak, Esquire

126(Department) Amanda G. Bush, Esquire

131Department of Environmental Protection

1353900 Commonwealth Boulevard

138Mail Station 35

141Tallahassee, Florida 32399-3000

144For Respondent: Stanley M. Warden, Esquire

150(Commission) Emily J. Norton, Esquire

155Florida Fish and Wildlife

159Conservation Commission

161620 South Meridian Street

165Tallahassee, Florida 32399-1600

168STATEMENT OF THE ISSUE

172The issue is whether an application by Petitioner, Hancock

181Bridge Marina, LLC (Petitioner or Hancock), for an Environmental

190Resource Permit (ERP) and sovereign submerged lands lease to

199expand an existing docking facility on Hancock Creek near the

209Caloosahatchee River in unincorporated Lee County (County),

216Florida, should be approved.

220PRELIMINARY STATEMENT

222This matter began on December 10, 2007, when Respondent,

231Department of Environmental Protection (Department), issued a

238Consolidated Notice of Denial [of] Environmental Resource Permit

246and Lease to Use Sovereign Submerged Lands (Notice of Intent)

256advising Petitioner that its application for a Permit/Water

264Quality Certification and Authorization to Use Sovereign

271Submerged Lands had been denied. Because of a federal

280consistency objection regarding the potential impacts on

287manatees lodged by Respondent, Florida Fish and Wildlife

295Conservation Commission (Commission), that agency was made a co-

304respondent. See § 373.428, Fla. Stat. (2008) 1 ("[a]n agency

315which submits a determination of inconsistency to the permitting

324agency shall be an indispensable party to any administrative or

334judicial proceeding in which such determination is an issue").

344After three extensions of time to file a request for a

355hearing were granted, on June 16, 2008, Petitioner filed its

365Petition for Formal Administrative Hearing (Petition) to contest

373the Department's preliminary determination. The Petition was

380forwarded by the Department to the Division of Administrative

389Hearings on August 18, 2008, with a request that an

399administrative law judge be assigned to conduct a hearing.

408By Notice of Hearing dated September 30, 2008, the matter

418was scheduled for final hearing on October 15-17, 2008, in Fort

429Myers, Florida. Petitioner's Unopposed Motion for Continuance

436filed on October 10, 2008, was granted, and the matter was

447continued to February 24-26, 2009, at the same location.

456However, the hearing was concluded on February 25, 2009.

465On February 10, 2009, the Department filed a Motion to

475Strike and Motion in Limine seeking to strike, or preclude the

486introduction of evidence in support of, paragraph 17 in the

496Petition, which alleged that the Department is estopped to deny

506a permit for Phase I of the marina in light of its acquiescence

519in the approval of a Development of Regional Impact (DRI) by the

531County. The Motion was denied by Order dated February 16, 2009,

542and Petitioner was allowed to introduce evidence on that issue

552at hearing. On February 16, 2009, the Commission filed a Motion

563in Limine seeking to preclude evidence on Petitioner's

571allegation that the Manatee Protection Plan (MPP) adopted by the

581County and later incorporated into its Comprehensive Plan was

590not based "on adequate data and analysis." The Motion was

600granted at the outset of the final hearing. 2

609On February 20, 2009, the parties filed a Joint Pre-Hearing

619Stipulation. At the final hearing, Petitioner presented the

627testimony of Dr. Thomas R. Cuba, a scientist and President of

638Delta Seven, Inc., and accepted as an expert; Steven Boutelle,

648Operations Manager for the Marine Program of the County's

657Division of Natural Resources; Donald Epler, one of two

666shareholders in Hancock; and Christopher R. Langen, an attorney

675for Stefan Heinke, the other shareholder in Hancock. Also, it

685offered Petitioner's Exhibits 1-8, which were received in

693evidence. The Department presented the testimony of Elizabeth

701A. Gillen, an Environmental Manager with the Department's South

710District Office and accepted as an expert. Also, it offered

720Department's Exhibit 1, which was received in evidence. The

729Commission presented the testimony of Mary Duncan, an

737Environmental Specialist III with the Imperiled Species

744Management Section and accepted as an expert, and Richard Kipp

754Frohlich, Leader of the Imperiled Species Management Section and

763accepted as an expert. Also, it offered Commission's Exhibits

7721, 2, 5, 16, 18, 20, 23, 24, 26-28, 30, 32-34, and 37, which

786were received in evidence. Finally, the Department's Request

794for Official Recognition was granted and the following matters

803were officially recognized: Sections 253.002, 253.77, 373.4132,

810373.414, 373.428, 373.2431, and 380.23, Florida Statutes (2008);

818Florida Administrative Code Rule Chapters 18-21, 62-330, and

82668A-27; Florida Administrative Code Rules 62-343.075, 40E-4.301,

833and 40E-4.302 (effective October 3, 1995); Section 4.2.7 of the

843South Florida Water Management District Basis of Review for

852Environmental Resource Permit Applications Within the South

859Florida Water Management District (1995); and the Conceptual

867State Lands Management Plan adopted March 17, 1981, and

876referenced in Florida Administrative Code Rule Chapter 18-21.

884The Transcript of the hearing (two volumes) was filed on

894March 13, 2009. By agreement of the parties, the time for

905filing proposed findings of fact and conclusions of law was

915extended to April 17, 2009. They were timely filed and have

926been considered in the preparation of this Recommended Order.

935FINDINGS OF FACT

938Based on the evidence presented by the parties, the

947following findings of fact are made:

953A. Background

9551. Hancock is a limited liability corporation with two

964shareholders: Donald Epler and Stefen Heinke. After conducting

972a feasibility study, on April 26, 2004, Hancock purchased a

9825.51-acre parcel of property in the County with the expectation

992of constructing and operating a 400-slip marina and a 5,000-

1003square-foot building housing a restaurant, ship's store, and

1011other sundry items needed for operation. (Hancock has

1019subsequently revised its plan by reducing the number of slips

1029requested from 400 to 352.) The cost of the property was around

1041$2.5 million.

10432. The property is located in an unincorporated part of

1053the County on the north side of the Caloosahatchee River

1063(River), a Class III water, south of Hancock Bridge Parkway,

1073east of the City of Cape Coral, and west of U.S. Highway 41 and

1087the City of North Fort Myers. The property currently contains a

109830-wet slip marina with 13 finger piers and a 4-slip T-dock.

1109The remainder of the parcel is essentially vacant. The parcel

1119borders a River tributary named Hancock Creek, which is a man-

1130altered tidal creek branching off of the River in a northwestern

1141direction, and the North Key Canal, which extends east from

1151Hancock Creek for approximately one-half mile. Access to the

1160River, which is no more than a hundred yards or so south of the

1174parcel, is by traversing North Key Canal and Hancock Creek.

11843. The Department is the state agency with the authority

1194under Part IV of Chapter 373, Florida Statutes, to issue an ERP.

1206In addition, the Department has authority from the Board of

1216Trustees of the Internal Improvement Trust Fund to review and

1226take final agency action on requests to authorize activities in

1236sovereign submerged lands. See § 253.002(1), Fla. Stat.

12444. The Commission is the agency with constitutional

1252regulatory authority over "wild animal life and fresh water

1261aquatic life and shall also exercise regulatory and executive

1270powers of the state with respect to marine life." See Art. IV,

1282§ 9, Fla. Const. The Commission's authority for the regulation

1292of manatees is derived from the Florida Manatee Sanctuary Act,

1302which is codified in Section 379.2431, Florida Statutes. Under

1311Sections 373.428 and 380.23, Florida Statutes, it also has

1320authority to review ERP applications for federal consistency

1328purposes pursuant to the federally approved Florida Coastal

1336Management Program.

13385. On September 12, 2005, Petitioner filed an application

1347for an ERP (a regulatory approval) and a lease to use sovereign

1359submerged lands (a proprietary approval) with the Department's

1367South District Office in Fort Myers, Florida. (For unknown

1376reasons, the application was resubmitted to the Department on

1385August 14, 2006.) The two requests are linked, and the

1395Department cannot approve one without approving the other. See

1404Fla. Admin. Code R. 62-343.075(2). The application seeks

1412authority to expand in two phases the existing 30-slip facility.

1422The first phase would generally authorize the construction of a

1432198-slip upland dry storage facility and reconfiguration of the

1441existing docks. In phase 2, Hancock would add 154 dry slips and

1453construct a 5,000-square-foot marina building. Because the

1461docks are constructed on and over sovereign submerged lands, a

1471proprietary authorization is necessary.

14756. Before making a decision on the application, the

1484Department forwarded a copy to the Commission for its

1493recommendation. After receiving the Commission's comments,

1499which consist of 89 pages, including transmittal letters, on

1508December 10, 2007, the Department issued its Notice of Intent to

1519deny the ERP and proprietary authorization on the grounds the

1529project area is sited in an area of very high level of manatee

1542use and the project will increase local boat traffic, resulting

1552in significant adverse effects on the manatee, which is listed

1562by the state and federal governments as an endangered species.

1572A more detailed description of the reasons for denial is found

1583in the Notice of Intent. See Petitioner's Exhibit 6, pages 4

1594through 9; Department's Exhibit 1.b., pages 4 through 9. The

1604Department acknowledges that its decision was based wholly upon

1613the Commission's determination that the project, as proposed,

1621would have an adverse impact on manatees.

1628B. The DRI and Estoppel

16337. In its Petition, Hancock contends that the Department

1642is "estopped to deny a permit for Phase 1 of the marina in light

1656of its acquiescence to the approval of DRI 2-8990-99."

16658. By way of background, in 1990, Hancock's predecessor in

1675interest (Waterway Group, Inc.) applied with the County for a

1685DRI which included, among other things, 400 dry boat spaces on

1696the property. DRI 2-8990-99 was approved by the County on

1706July 8, 1991, and has been amended three times. See

1716Petitioner's Exhibit 3. The original terms of approval

1724contained several conditions that specifically addressed manatee

1731protection. One separated the project into two phases of 200

1741spaces, the first of which was authorized without additional

1750studies, while the second was subject to additional study and

1760review by the Florida Department of Natural Resources (DNR).

17699. When the DRI was approved, the State's manatee

1778protection program was under the jurisdiction of the DNR. That

1788agency reviewed the DRI and recommended manatee protection

1796conditions. The conditions in the final approval were

1804consistent with the program's recommendation.

180910. On June 29, 2004, the County adopted a resolution

1819approving a MPP for the County. See Petitioner's Exhibit 4. It

1830was not adopted as an ordinance, and individual notice was not

1841provided to interested property owners, including Hancock's

1848principals. After adoption, the County incorporated the MPP

1856into its Comprehensive Plan. The MPP is a planning document

1866that provides a comprehensive review of manatee and boating data

1876on a county-wide basis. It is developed, reviewed, and approved

1886by local, state, and federal governments and is used for

1896guidance when considering appropriate levels of slip densities

1904within a county. The County is one of thirteen counties

1914directed to adopt a MPP.

191911. On October 20, 2004, Hancock filed with the County an

1930application to amend its DRI. The application included requests

1939to extend the DRI approval a third time and to revise the site

1952plan. The site plan changes included a reduction in the total

1963number of dry spaces from 400 to 352. On June 20, 2005, the

1976County approved the DRI amendment. The Development Order

1984included a finding of fact that the marina was exempt from the

1996requirements of the MPP because Section 8.4 of the MPP "exempts

2007existing projects with valid permits and Chapter 380 vested

2016status for the construction of slips (wet or dry) that have not

2028been constructed at the time the MPP was adopted by the Board of

2041County Commissioners." See Petitioner's Exhibit 3, Third

2048Development Order Amendment for Hancock Bridge Marina, page 4,

2057paragraph H. Hancock then filed the instant application on

2066September 12, 2005. To date, Hancock has expended $1,731,000.00

2077in its permitting efforts, including the DRI extension and ERP

2087application.

208812. There is no evidence that during the DRI process, the

2099Department or Commission made any representations to Hancock

2107about its ability to obtain an ERP or sovereign submerged lands

2118authorization. Also, neither agency was consulted during that

2126period of time, presumably because the DRI and ERP processes are

2137separate and independent of one another.

2143C. Permitting Criteria

214613. Section 373.414, Florida Statutes, contains the

2153standards and criteria governing the approval of an ERP.

2162Subsection (1) requires that the applicant provide reasonable

2170assurance that the regulated activity is "not contrary to the

2180public interest." In determining whether this test is met,

2189paragraph (1)(a) requires that the Department consider and

2197balance the following criteria:

22011. Whether the activity will adversely

2207affect the public health, safety, or welfare

2214or the property of others;

22192. Whether the activity will adversely

2225affect the conservation of fish and

2231wildlife, including endangered or threatened

2236species, or their habitats;

22403. Whether the activity will adversely

2246affect navigation or the flow of water or

2254cause harmful erosion or shoaling;

22594. Whether the activity will adversely

2265affect the fishing or recreational values or

2272marine productivity in the vicinity of the

2279activity;

22805. Whether the activity will be of a

2288temporary or permanent nature.

22926. Whether the activity will adversely

2298affect or will enhance significant

2303historical and archaeological resources

2307under the provisions of s. 267.061; and

23147. The current condition and relative value

2321of functions being performed by areas

2327affected by the proposed activity.

233214. These same factors are found in Florida Administrative

2341Code Rule 40E-4.302, an ERP rule adopted by the South Florida

2352Water Management District. This rule has been adopted by

2361reference by the Department to be used when it considers ERP

2372applications within the geographical jurisdiction of that water

2380management district. See Fla. Admin. Code R. 62-330.200(4). An

2389additional requirement in the rule is that an applicant give

2399reasonable assurance that the project will not cause

2407unacceptable cumulative impacts. See Fla. Admin. Code R. 40E-

24164.302(1)(b).

241715. Besides the foregoing requirements, additional

2423conditions for the issuance of an ERP are found in Florida

2434Administrative Code Rule 40E-4.301, also adopted by reference by

2443the Department. Relevant here are requirements that the

2451applicant give reasonable assurances that the proposed activity

2459(a) will not adversely impact the value of functions provided to

2470fish and wildlife and listed species by wetlands and other

2480surface waters, and (b) will not cause adverse secondary impacts

2490to the water resources. See Fla. Admin. Code R. 40E-4.301(1)(d)

2500and (f).

250216. Section 373.414(1)(b), Florida Statutes, provides that

2509if an applicant is unable to meet the above criteria, the

2520Department shall consider measures proposed by or acceptable to

2529the applicant to mitigate adverse effects that may be caused by

2540the regulated activity. In this case, mitigation measures have

2549been proposed by Hancock and are discussed below.

255717. Finally, Section 373.4132, Florida Statutes, requires

2564that the Department evaluate applications for dry storage

2572facilities for ten or more vessels in the same manner as any

2584other ERP application, including that the applicant demonstrate

2592that the facility will not be harmful to the water resources,

2603provides reasonable assurance that the secondary impacts from

2611the facility will not cause adverse impacts to the functions of

2622the wetlands and surface waters, and meets the public interest

2632test in Section 373.414(1)(a), Florida Statutes.

263818. There are no rules or statutes which require that the

2649Department consider the status of, or otherwise take into

2658account, a DRI in evaluating an application for an ERP or

2669proprietary authorization.

2671D. Impacts on Manatees

267519. After reviewing the application for an ERP, the

2684Department determined that the project, as proposed, should be

2693denied because of direct, secondary, and cumulative effects it

2702would have on manatees. The Department further determined that

2711the applicant had not met the applicable requirements under

2720Florida Administrative Code Rule Chapter 18-21 for authorization

2728to use sovereign submerged lands. In making these

2736determinations, the Department considered not only potential

2743deaths of manatees, but also potential impacts such as

2752harassment, disturbance, and sub-lethal boat strikes. The

2759latter strikes may cause permanent injury and can affect

2768reproduction and behavior.

277120. The State is a refuge and sanctuary for the manatee.

2782See § 379.2431(2), Fla. Stat. The manatee is a marine mammal

2793that can live as long as sixty years. It is unable to tolerate

2806prolonged exposure to temperatures below around sixty-one

2813degrees, which makes it susceptible to cold-related stress and

2822death. Consequently, the manatees typically seek warm water

2830when temperatures drop below sixty-eight degrees, migrating

2837seasonally over extensive geographic areas.

284221. Hancock's marina is located just off the River. The

2852River is one of the most studied and significant habitats for

2863manatees on the west coast of Florida. The County's water

2873bodies, including the River, provide manatees with submerged

2881aquatic vegetation for foraging, fresh water sources, and

2889several warm-water sites to use as refuges during colder

2898weather. Hancock Creek, which is used to access the River from

2909the marina, is an area used by manatees because it provides

2920fresh water and a quiet environment. Manatees also use the

2930River as a major travel corridor between the Florida Power and

2941Light Company (FPL) power plant on the Orange River, a tributary

2952of the River located around eight miles upstream from the

2962project site, and the estuaries found downstream where foraging

2971resources are abundant. Hundreds of manatees go up and down the

2982River throughout the year, and those traveling to and from the

2993warm water around the FPL plant must travel past Hancock Creek.

300422. Manatee deaths have occurred within a five mile radius

3014of the project site. Also, the number of manatee watercraft-

3024related deaths in the River has steadily increased over the

3034years. According to a 1998 study of boating activity in the

3045County, vessels use the River more as a travel corridor to the

3057bays and estuaries outside of the River than as a destination

3068itself, and that on weekends there is almost constant traffic

3078with vessels leaving or entering the mouth of the River every

3089thirty-five seconds. The majority of the boats leaving the

3098project site are expected to travel downstream through the mouth

3108of the River, an area with substantial vessel congestion. This

3118travel pattern, in conjunction with the typical travel patterns

3127of manatees, indicates that there is a great potential for

3137boat/manatee overlap in the River, increasing the likelihood of

3146impacts to manatees.

314923. Besides manatee deaths, there are sub-lethal effects

3157of increased boat traffic in the area. Increased traffic in

3167important manatee areas may create disturbances which will alter

3176behaviors such as feeding, suckling, or resting, or it may

3186separate mothers from their calves. Also, vessel traffic may

3195cause them to leave preferred habitats. Finally, as noted

3204above, vessel collisions with manatees produce non-lethal

3211injuries as well, causing pain and extreme scarring, which can

3221alter natural behaviors and affect reproduction.

322724. The single biggest known cause of death to manatees is

3238impacts from boats. The project would increase the risk of

3248watercraft collisions with manatees in this region. As the

3257level of boat traffic increases, the probability of boat and

3267manatee collisions is also likely to increase. Because the

3276project is located along the travel corridor between the largest

3286wintering aggregation of manatees on Florida's west coast and

3295their local foraging habitat, the expected secondary impacts

3303from increased vessel traffic associated with the project is

3312expected to reduce the value of the functions of the River as a

3325travel corridor. Therefore, the secondary impacts of vessel

3333traffic from the expansion of the marina are expected to result

3344in adverse impacts to manatees.

334925. In 1990, the DNR reviewed the proposed DRI for this

3360site under the state manatee program. It found that during the

3371preceding thirteen years (1976-February 1990), thirty-six

3377manatees had died from water-related injuries in the County.

3386Within a five-mile radius of the site, four manatees had died

3397from watercraft-related injuries. DNR concluded that since the

3405manatee protection speed zones for the River had just been

3415established, they were expected to offset the impact of the

3425additional 198 slips. From March 1990 until September 2006,

3434however, twenty-five additional manatees have died from

3441watercraft-related injuries within a five-mile radius of the

3449site. Therefore, the number of deaths had increased without the

3459additional 198 slips. The logical inference is that if the new

3470slips are allowed, boat traffic and the associated adverse

3479impacts on manatees will likewise increase.

348526. The fact that dry slips will be used does not change

3497the Department and Commission's evaluation of the project. A

3506boat has the same risk to a manatee whether stored in a wet or

3520dry facility. Marine industry groups suggest that an average

3529usage rate is between ten and fifteen percent at any time, and

3541that usage is likely to increase on the weekends. Thus, as

3552density increases so does the risk.

355827. In addition to its own analysis, the Commission

3567reviewed the County MPP, which indicated that nine additional

3576slips at this location would be acceptable, for a total of

3587thirty-nine. This number was calculated by using a slip density

3597of three slips for every one hundred feet of shoreline owned.

3608(The actual linear feet of shoreline owned by Hancock is

3618unclear. The Commission concedes that Hancock "may own a total

3628of 1,214 linear feet of shoreline.") A MPP typically allows for

3641higher boat densities in areas that pose less risk to manatees

3652and lower boat densities in higher risk locations. Had the MPP

3663not been considered, the number of allowable slips would remain

3673at thirty since the MPP provides for a countywide strategy

3683instead of a case-by-case review. To date, the Commission has

3693never recommended approval of a marina application in the County

3703that would authorize more docks than the MPP would authorize.

371328. The Commission initially makes an independent

3720assessment of the application without regard to the MPP. In

3730this case, based upon mortality data, aerial surveys, telemetry

3739data, rescue data, and boat studies, the Commission determined

3748that no further slips are appropriate. Therefore, even if the

3758County's MPP is based upon outdated data and analysis, as

3768Hancock contends, approval of the application would not be

3777warranted.

377829. Petitioner's expert posited that the proposed project

3786would only result in one manatee death over the next twenty

3797years, which would amount to no more than a de minimus impact on

3810the overall population. Assuming this to be true, manatees are

3820nonetheless an endangered species, and there is no minimal

3829amount of death that is considered acceptable. The witness also

3839opined that Hancock is entitled to an unlimited number of slips

3850under the MPP due to flawed data and analysis underpinning that

3861document. In formulating his recommendations, however,

3867Hancock's expert relied on mathematical models and statistics

3875while ignoring the principles of manatee behavior and biology.

3884Finally, the expert agreed that the greater the number of boats

3895in the water, the greater the likelihood that a manatee could be

3907accidentally crushed. On the issue of impacts to manatees, the

3917testimony of the Commission witnesses is deemed to be the most

3928credible and persuasive.

393130. The more persuasive evidence supports a finding that

3940the marina will be located in an area adjacent to the River,

3952that large numbers of manatees use the River, and that the

3963project is expected to increase boat traffic. This in turn will

3974lead to a higher incidence of boating-related manatee casualties

3983in the area. Therefore, the proposed activity adversely affects

3992the conservation of wildlife and marine productivity in the

4001vicinity of the project; it adversely affects the marine

4010productivity in the area; it is permanent in nature; and it

4021diminishes the current condition and relative value of functions

4030performed by areas affected by the activity. On balance, then,

4040the project is contrary to the public interest.

404831. Based on the evidence presented, Hancock has not

4057provided reasonable assurance that the project will not cause

4066adverse secondary impacts to water resources, as required by

4075Florida Administrative Code Rule 40E-4.301(1)(f).

408032. Similarly, based on the evidence presented, Hancock

4088has not provided reasonable assurance that the project will not

4098result in unacceptable cumulative impacts upon wetlands and

4106other surface waters, as required by Florida Administrative Code

4115Rule 40E-4.302(1)(b).

411733. By failing to provide reasonable assurances that the

4126facility will not be harmful to water resources, that the

4136secondary impacts from the facility will not cause adverse

4145impacts to the functions of wetlands and surface waters, and

4155that the project meets the public interest test, Hancock has

4165failed to satisfy the requirements of Section 373.4132, Florida

4174Statutes.

4175E. Mitigation

417734. If an applicant cannot meet the requirements of

4186Section 373.414(1)(a), Florida Statutes, the Department "shall

4193consider measures proposed by or acceptable to the applicant to

4203mitigate adverse effects that may be caused by the regulated

4213activity." As noted in Finding of Fact 27, supra , the

4223Department is willing to approve an additional nine slips that

4233would be allowed under the County MPP, for a total of thirty-

4245nine. According to Hancock, this number is not acceptable

4254because more slips are needed to make the project financially

4264feasible.

426535. Although a copy of the application is not a part of

4277this record, the testimony suggests that in its application,

4286Hancock proposed certain measures to mitigate the impacts on

4295manatees. In a letter to the Department dated November 8, 2007,

4306however, the Commission stated that "[i]f the Applicant

4314propose[s] changes to the project to minimize fish and wildlife

4324resource impacts that are consistent with the Lee County MPP,

4334such a project would be consistent with Chapter 370.12(2), F.S."

4344(The Legislature has subsequently consolidated this statute into

4352Section 379.2431, Florida Statutes.) Despite this lack of

4360clarity in the record, sometime during the application process,

4369and presumably before the Notice of Intent was issued, the

4379Commission staff discussed with Hancock whether the following

4387mitigation measures would offset or adequately reduce the

4395impacts: placing a size restriction on boats docking at its

4405facility; providing boater education; installing speed zone

4412marking and making it a requirement for all boats at the marina

4424to be equipped with a speed zone map or a Global Positioning

4436Satellite unit with speed zone mapping; implementing a volunteer

4445watch program to enforce speed limits; making a cash donation to

4456study manatee population dynamics; and installing sonar

4463avoidance technology on vessels.

446736. The Commission established that these measures, even

4475if implemented, would not offset the impacts from 198 slips

4485expected with phase 1 of the project. For example, the research

4496associated with sonar technology is not yet completed, and

4505devices are not available for boaters. Also, given the location

4515of the project, even with additional law enforcement and boater

4525education, the impacts would not be offset due to the level of

4537traffic already existing on the River at that site, and the

4548importance of the area to manatees. The middle of the River is

4560a high-speed corridor (with a twenty-five miles per hour speed

4570limit) and even with one hundred percent compliance in that

4580zone, a small boat can still hit and kill a manatee.

4591F. The Proprietary Authorization

459537. Because denial of the ERP is being recommended, the

4605proprietary authorization must likewise be denied. See Fla.

4613Admin. Code R. 62-373.075(2). Even so, for the purpose of

4623addressing all issues in this Recommended Order, a discussion of

4633the application for proprietary authorization is set forth

4641below.

464238. Florida Administrative Code Rule Chapter 18-21

4649contains the rules that implement the administrative and

4657management responsibilities of the Department in authorizing

4664activities in sovereignty submerged lands. Florida

4670Administrative Code Rule 18-21.004 establishes the specific

4677standards and criteria to be applied by the Department in

4687determining whether Hancock should be allowed to use sovereign

4696submerged lands. Paragraph (1)(a) provides that "[f]or

4703approval, all activities on sovereignty lands must be not

4712contrary to the public interest." The public interest is

4721defined as "demonstrable environmental, social, and economic

4728benefits which would accrue to the public at large as a result

4740of a proposed action, and which would clearly exceed all

4750demonstrable environmental, social, and economic costs of the

4758proposed action." See Fla. Admin. Code R. 18-21.003(43). The

4767more persuasive evidence supports a finding that, on balance,

4776the project is contrary to the public interest based upon the

4787standards in the rules.

479139. Florida Administrative Code Rule 18-21.004(2)(a)

4797provides that "[a]ll sovereignty lands shall be considered

4805single use lands and shall be managed primarily for the

4815maintenance of essentially natural conditions, propagation of

4822fish and wildlife, and traditional recreational uses such as

4831fishing, boating, and swimming. Compatible secondary purposes

4838and uses which will not detract from or interfere with the

4849primary purpose may be allowed." The evidence does not show

4859that Hancock's proposed marina expansion constitutes a secondary

4867use not interfering with the propagation of wildlife.

4875Therefore, the project is not consistent with this rule.

488440. Florida Administrative Code Rule 18-21.004(2)(b)

4890provides that "unless there is no reasonable alternative and

4899adequate mitigation is proposed," activities which result in

4907significant adverse impacts to sovereignty lands and associated

4915resources shall not be approved. As previously found, the

4924mitigation measures proposed by Hancock are not adequate.

493241. Paragraph (2)(i) of the rule further provides that

4941activities in submerged lands "shall be designed to minimize or

4951eliminate adverse impacts on fish and wildlife habitat, and

4960other natural or cultural resources. Special attention and

4968consideration shall be given to endangered and threatened

4976species habitat." Because Hancock failed to prove that the

4985project would not result in unmitigated adverse impacts to

4994manatees, it fails to meet this criterion.

500142. Paragraphs (7)(d) and (e) of the rule are general

5011conditions for authorization and provide that activities "shall

5019be constructed and used to avoid or minimize adverse impacts to

5030sovereignty submerged lands and resources" and "shall not

5038adversely affect any species which is endangered, threatened, or

5047of special concern." Here the more persuasive evidence shows

5056that neither condition has been met.

5062CONCLUSIONS OF LAW

506543. The Division of Administrative Hearings has

5072jurisdiction over this matter pursuant to Sections 120.569 and

5081120.57(1), Florida Statutes.

508444. The burden of proof is on the party asserting the

5095affirmative of an issue before an administrative tribunal. See ,

5104e.g. , Balino v. Department of Health & Rehabilitative Servs. ,

5113348 So. 2d 349, 350 (Fla. 1st DCA 1977). Therefore, Petitioner

5124has the burden of proving by a preponderance of the evidence

5135that the proposed activity satisfies the requirements for an ERP

5145and a sovereign submerged lands lease.

515145. For the reasons set forth in the Findings of Fact, the

5163more credible and persuasive evidence supports a conclusion that

5172the applicant has failed to provide reasonable assurances that

5181the project will not violate the applicable statutes and rules.

5191Therefore, the application must be denied.

519746. Finally, in order to invoke the doctrine of equitable

5207estoppel, Hancock must prove the following elements: (1) a

5216representation by the first party as to a material fact that is

5228contrary to a later-asserted position; (2) a reliance on that

5238representation by the second party; and (3) a change in position

5249by the first party that is detrimental to the second party.

5260Council Brothers, Inc. v. City of Tallahassee , 634 So. 2d 264,

5271266 (Fla. 1st DCA 1994). There is no evidence that the

5282Department or Commission made a representation to Hancock during

5291the DRI process that it would be entitled to an ERP or

5303proprietary authorization.

530547. It should also be noted that the doctrine of equitable

5316estoppel may be asserted against a governmental entity only

5325under rare and exceptional circumstances. Associated Industries

5332Insurance Co., Inc. v. Department of Labor and Employment

5341Security , 923 So. 2d 1252, 1254-55 (Fla. 1st DCA 2006). To

5352invoke it against the Department, Hancock must demonstrate that

5361the Department's conduct exceeds mere negligence, that its act

5370will cause serious injustice, and that the imposition of

5379estoppel will not unduly harm the public interest. See Council

5389Brothers , supra at 264. Such a showing was not made here.

5400Moreover, the doctrine does not apply to "transactions that are

5410forbidden by statute or that are contrary to public policy."

5420Dade County v. Gayer, et al. , 388 So. 2d 1292, 1294 (Fla. 3d DCA

54341980). The approval of the application here would be contrary

5444to the State and federal government policies of protecting an

5454endangered species, the manatee.

545848. Hancock's reliance on the case of Sakolsky v. The City

5469of Coral Gables , 151 So. 2d 433 (Fla. 1963), is not analogous to

5482the facts presented here. In Sakolsky , the City had halted a

5493building permit to which it had given tentative approval without

5503conditions. Unlike the instant proceeding, it was the City's

5512action on the same authorization that gave rise to a colorable

5523claim for estoppel. The instant case is closer to the facts in

5535Circle K General, Inc. v. Hillsborough County , 524 So. 2d 1143

5546(Fla. 2d DCA 1988), where the court found equitable estoppel did

5557not apply where the county approved a site plan yet later denied

5569a driveway permit for the site. In rejecting the claim of

5580estoppel, the court noted that "[t]he mere approval of the site

5591plan was not a guarantee that the county would issue a driveway

5603permit, and the applicant could not have reasonably relied upon

5613it as such." Id. at 1144.

5619RECOMMENDATION

5620Based on the foregoing Findings of Fact and Conclusions of

5630Law, it is

5633RECOMMENDED that the Department of Environmental Protection

5640enter a final order denying Petitioner's application for an ERP

5650and authorization to use sovereign submerged lands to expand an

5660existing marina on Hancock Creek in Lee County, Florida.

5669DONE AND ENTERED this 15th day of May, 2009, in

5679Tallahassee, Leon County, Florida.

5683S

5684DONALD R. ALEXANDER

5687Administrative Law Judge

5690Division of Administrative Hearings

5694The DeSoto Building

56971230 Apalachee Parkway

5700Tallahassee, Florida 32399-3060

5703(850) 488-9675

5705Fax Filing (850) 921-6847

5709www.doah.state.fl.us

5710Filed with the Clerk of the

5716Division of Administrative Hearings

5720this 15th day of May, 2009.

5726ENDNOTES

57271/ All statutory citations are in the 2008 version of the

5738Florida Statutes.

57402/ This proceeding is not the proper forum in which to litigate

5752alleged deficiencies ( i.e. , a lack of adequate data and

5762analysis) in the County's MPP, a document incorporated into its

5772Comprehensive Plan. Chapter 163, Florida Statutes, provides the

5780exclusive remedy for doing so. Therefore, if these concerns are

5790valid, they should be resolved by the County through an

5800amendment to its MPP or Comprehensive Plan, or in some other

5811action at the local level.

5816COPIES FURNISHED:

5818Lea Crandall, Agency Clerk

5822Department of Environmental Protection

58263900 Commonwealth Boulevard

5829Mail Station 35

5832Tallahassee, Florida 32399-3000

5835Matthew D. Uhle, Esquire

5839Knott, Consoer, Ebelini,

5842Hart & Swett, P.A.

58461625 Hendry Street

5849Fort Myers, Florida 33901-2969

5853James E. Moon, Esquire

5857Alvarez, Sambol, Winthrop & Madson, P.A.

58633451 Bonita Bay Boulevard, Suite 200

5869Bonita Springs, Florida 34134-4354

5873Kelly K. Samek, Esquire

5877Department of Environmental Protection

58813900 Commonwealth Boulevard

5884Mail Station 35

5887Tallahassee, Florida 32399-3000

5890Stanley M. Warden, Esquire

5894Florida Fish and Wildlife

5898Conservation Commission

5900620 Meridian Street

5903Tallahassee, Florida 32399-1600

5906Thomas M. Beason, General Counsel

5911Department of Environmental Protection

59153900 Commonwealth Boulevard

5918Mail Station 35

5921Tallahassee, Florida 32399-3000

5924NOTICE OF RIGHT TO FILE EXCEPTIONS

5930All parties have the right to submit written exceptions within

594015 days of the date of this Recommended Order. Any exceptions

5951to this Recommended Order should be filed with the agency that

5962will render a final order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 08/13/2009
Proceedings: Agency Final Order
PDF:
Date: 08/13/2009
Proceedings: Final Order Closing File.
PDF:
Date: 05/15/2009
Proceedings: Recommended Order
PDF:
Date: 05/15/2009
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 05/15/2009
Proceedings: Recommended Order (hearing held February 24, 2009). CASE CLOSED.
PDF:
Date: 04/17/2009
Proceedings: Respondents' Joint Proposed Recommended Order filed.
PDF:
Date: 04/17/2009
Proceedings: Petitioner Hancock Bridge Marina, LLC`s Proposed Recommended Order filed.
PDF:
Date: 04/08/2009
Proceedings: Unopposed Motion for Extension of Time to File Proposed Recommended Orders filed.
PDF:
Date: 03/19/2009
Proceedings: Amended Index Page filed.
PDF:
Date: 03/19/2009
Proceedings: Amended First Pages of Transcript of Proceedings (Volumes I&II) filed.
Date: 03/13/2009
Proceedings: Transcript of Proceedings (Volumes I&II) filed.
Date: 02/24/2009
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 02/23/2009
Proceedings: Notice of Appearance (filed by J. Moon).
PDF:
Date: 02/20/2009
Proceedings: Department of Environmental Protection`s Request for Official Recognition filed.
PDF:
Date: 02/20/2009
Proceedings: Joint Pre-hearing Stipulation filed.
PDF:
Date: 02/19/2009
Proceedings: Petitioner`s Response to Florida Fish and Wildlife Conservation Commission`s Motion in Limine filed.
PDF:
Date: 02/18/2009
Proceedings: Subpoena for Telephonic Deposition (C. Deutsch) filed.
PDF:
Date: 02/18/2009
Proceedings: Notice of Taking Telephonic Deposition (of C. Deutsch) filed.
PDF:
Date: 02/16/2009
Proceedings: Respondent Florida Fish and Wildlife Conservation Commission`s Motion in Limine filed.
PDF:
Date: 02/16/2009
Proceedings: Order (motion is denied).
PDF:
Date: 02/12/2009
Proceedings: Amended Notice of Hearing (hearing set for February 24 through 26, 2009; 9:00 a.m.; Fort Myers, FL; amended as to hearing room location).
PDF:
Date: 02/12/2009
Proceedings: Petitioner`s Response to Motion to Strike and Motion in Limine filed.
PDF:
Date: 02/12/2009
Proceedings: Notice of Taking Deposition (of E. Gillen) filed.
PDF:
Date: 02/11/2009
Proceedings: Service Return Affidavit (of S. Boutelle) filed.
PDF:
Date: 02/11/2009
Proceedings: Notice of Taking Telephonic Deposition Duces Tecum (of S. Boutelle) filed.
PDF:
Date: 02/11/2009
Proceedings: Notice of Taking Telephonic Deposition (of M. Duncan) filed.
PDF:
Date: 02/11/2009
Proceedings: Notice of Taking Telephonic Deposition (of K. Frolich) filed.
PDF:
Date: 02/11/2009
Proceedings: Notice of Service of Petitioner`s Answers to Florida Fish and Wildlife Conservation Commission`s First Interrogatories filed.
PDF:
Date: 02/11/2009
Proceedings: Notice of Service of Petitioner`s Response to Florida Fish and Wildlife conservation Commission`s Request for Production filed.
PDF:
Date: 02/11/2009
Proceedings: Notice of Deposition filed.
PDF:
Date: 02/10/2009
Proceedings: Respondent, Department of Environmental Protection`s Motion to Strike and Motion in Limine filed.
PDF:
Date: 01/21/2009
Proceedings: Notice of Service of Department of Environmental Protection`s Answers to Petitioner`s First Set of Interrogatories filed.
PDF:
Date: 01/12/2009
Proceedings: Fish and Wildlife Conservation Commission First Request for Production filed.
PDF:
Date: 01/12/2009
Proceedings: Notice of Service of Response to Petitioner`s First Interrogatories filed.
PDF:
Date: 01/12/2009
Proceedings: Fish and Wildlife Conservation Commission`s Response to Petitioner`s First Request for Production filed.
PDF:
Date: 01/08/2009
Proceedings: Notice of Service of Respondent`s First Interrogatories to Petitioner filed.
PDF:
Date: 01/07/2009
Proceedings: Notice of Appearance (filed by S. Warden).
PDF:
Date: 12/23/2008
Proceedings: Respondent`s Response to Petitioner`s Request for Production filed.
PDF:
Date: 12/12/2008
Proceedings: Notice of Appearance (filed by Kelly Samek) filed.
PDF:
Date: 12/05/2008
Proceedings: Petitioner`s Request for Production to Respondent, Florida Fish and Wildlife Conservation Commission filed.
PDF:
Date: 12/05/2008
Proceedings: Notice of Service of Petitioner`s First Set of Interrogatories to Respondent, Florida Fish and Wildlife Conservation Commission filed.
PDF:
Date: 12/05/2008
Proceedings: Petitioner`s Request for Production to Respondent, State of Florida, Department of Environmental Protection filed.
PDF:
Date: 12/05/2008
Proceedings: Notice of Service of Petitioner`s First Set of Interrogatories to Respondent, State of Florida, Department of Environmental Protection filed.
PDF:
Date: 10/17/2008
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for February 24 through 26, 2009; 9:00 a.m.; Fort Myers, FL).
PDF:
Date: 10/10/2008
Proceedings: Petitioner`s Unopposed Motion for Continuance filed.
PDF:
Date: 09/30/2008
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 09/30/2008
Proceedings: Notice of Hearing (hearing set for October 15 through 17, 2008; 9:00 a.m.; Fort Myers, FL).
PDF:
Date: 08/26/2008
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
PDF:
Date: 08/18/2008
Proceedings: Initial Order.
PDF:
Date: 08/18/2008
Proceedings: Letter to E. Gillen from R. Frohlich regarding Manatee Impact Review Application filed.
PDF:
Date: 08/18/2008
Proceedings: Consolidated Notice of Denial filed.
PDF:
Date: 08/18/2008
Proceedings: Petition for Formal Administrative Proceeding filed.
PDF:
Date: 08/18/2008
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
08/18/2008
Date Assignment:
08/18/2008
Last Docket Entry:
08/13/2009
Location:
Fort Myers, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
 

Counsels

Related DOAH Cases(s) (1):

Related Florida Statute(s) (9):

Related Florida Rule(s) (6):