09-001567BID Core Construction Company vs. University Of North Florida
 Status: Closed
Recommended Order on Thursday, April 30, 2009.


View Dockets  
Summary: Petitioner did not demonstrate that it had successfully completed three projects over $1 million as required by the ITB.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8CORE CONSTRUCTION COMPANY, )

12)

13Petitioner, )

15)

16vs. ) Case No. 09-1567BID

21)

22UNIVERSITY OF NORTH FLORIDA, )

27)

28Respondent. )

30)

31RECOMMENDED ORDER

33On April 20, 2009, a duly-noticed hearing was held by means

44of video-teleconferencing in Tallahassee and Jacksonville,

50Florida, before Administrative Law Judge Lisa Shearer Nelson, of

59the Division of Administrative Hearings.

64APPEARANCES

65For Petitioner: Paul Christopher Wrenn, Esquire

71University of North Florida

75J.J. Daniel Hall, Suite 2100

801 University of North Florida Drive

86Jacksonville, Florida 32224-7699

89For Respondent: Jay Chung, President

94Core Construction Company

974940 Emerson Street, Suite 205

102Jacksonville, Florida 32207

105STATEMENT OF THE ISSUE

109The issue to be determined is whether Respondent's proposed award for ITB 09-22 for Building 14B renovation is contrary to

129law, against the University's governing statutes, rules or

137policies or the specifications of the invitation to bid.

146PRELIMINARY STATEMENT

148On February 27, 2009, the University of North Florida (UNF

158or the University) received a formal protest from Core

167Construction Company challenging the University's award of ITB-

17509-22 (GC's for Building 14B Renovation). On March 25, 2009, the

186protest was referred to the Division of Administrative Hearings

195pursuant to the University's contract with the Division with a

205request that an administrative law judge be assigned. The case

215was assigned to the undersigned and, after a telephone conference

225with the parties held March 30, 2009, it was agreed that the

237hearing would be held by means of video-conferencing on April 20,

2482009, and the hearing proceeded as scheduled.

255The hearing was conducted pursuant to the authority granted

264in Florida Board of Governors Rule 18.002, and the procedures

274outlined in University of North Florida Regulation 13.0020R.

282Consistent with that regulation, the parties exchanged exhibits

290in advance of the hearing, and submitted a prehearing statement

300including admitted facts which have been incorporated into the

309findings of fact below. Neither party objected to the

318documentary evidence submitted by the other. At hearing,

326Petitioner presented the testimony of Jay Chung, Dirk Harrison,

335and Gary Arcuri, and Petitioner's Exhibits 1-13 were admitted

344into evidence. Respondent submitted the testimony of Dianna

352White and Kathryn Ritter, and Respondent's Exhibits 1-12 were

361admitted.

362The parties both expressed the desire for the proceedings to

372be expedited as much as possible. To that end, it was agreed

384that proposed recommended orders would be submitted no later than

394April 27, 2009. Both parties timely submitted their proposed

403orders, which have been carefully considered in the preparation

412of this Recommended Order.

416FINDINGS OF FACT

4191. The University of North Florida published its Notice of

429Bid/Request for Proposal in reference to ITB #09-22 entitled

"438GC's for Building 14B Renovation" on December 19, 2008, with a

449submission deadline of January 27, 2009. The opening date was

459eventually extended to January 30, 2009.

4652. There were four addendums to the ITB #09-22 Project.

4753. The Notice of Bid/Request for Proposal document

483contained the following provisions:

487This project consists of the following scope

494of work: The work includes all labor,

501supervision, equipment, and materials

505required to execute the Contract Documents in

512two phases for the tenant build-out of the

520existing UNF Building 14-B (approximate

525square footage 9742). The work includes, but

532is not limited to, demolition of all interior

540walls, finishes, mechanical, electrical,

544plumbing and communication components as well

550as a new exterior curtain wall system.

557Exterior construction will include new

562glazing in aluminum curtain wall. Interior

568construction will include new gypsum

573wallboard partitions with metal stud walls,

579millwork, suspended acoustical and gypsum

584wallboard ceilings, wood and metal doors in

591hollow metal frames, coiling overhead

596grilles, toilet partitions and vanities.

601Interior finishes include carpeting,

605resilient tile, ceramic tile, painting, and

611window treatments. Mechanical work includes

616installation of new Owner provided HVAC units

623with ductwork and all necessary connections

629to the UNF Central Plant chilled water

636system. Plumbing includes new piping and

642fixtures for the tenant build-out and

648renovation of the group male and female

655restrooms. Electrical work includes new

660wiring, devices and lighting for the new

667tenant build-out.

669Successful bidders must have demonstrable

674previous experience with the described

679systems and technical requirements. All

684bidders must be qualified at the time of the

693bid opening in accordance with the Bidders

700Qualification within the ITB 09-22 Bid

706documents. . .

7094. Article I, Section 2 includes a heading in bold stating

"720Qualification Criteria." This section states:

725Participants must qualify to bid on this

732project. UNF will utilize the following

738criteria to qualify the general contractors

744within this ITB. The information must be

751completed on the UNF Qualifications Form

757provided (page 10-11):

760Bonding: Demonstrates a bonding capacity of

766at least $2 million dollars and has an A.M.

775Best Rating of "A-V" or better.

781Licenses: Company is licensed to do business

788in the state of Florida and approved by the

797US Department of Treasury listing as an

804acceptable surety.

806Project references: Company has successfully

811completed at least 3 commercial construction

817projects of more than $1 million dollars each

825in the past three (3) years. List 3 such

834projects to include project name, client

840name, completion date, location, project

845value, role in project. Reference: Project

851name, owner, owner's representative

855name/phone number, completion date and

860construction cost.

862Years of experience: Company has a minimum

869five (5) years of GC experience under the

877current company name.

8805. The directions for the General Contractor's

887Qualification Summary, under Related Experience, reiterated that

894the bidder was to list "No more than 4 projects of comparable

906type, size and complexity. (1) Project must be for a

916college/university)."

9176. Addendum I for the Project, issued January 9, 2009,

927clarified that the requirement for having completed successfully

935a project of similar size and scope at a Florida University in

947the last three years is a qualification factor for this project.

9587. Addendum II, issued January 12, 2009, removed the

967requirement for bidders to have completed one project for a

977college or university. The other two addenda did not address

987contractor qualifications.

9898. Petitioner, Core Construction Company (Core Construction

996or Petitioner) bid in response to the ITB. Approximately 19

1006other bidders also responded. Core Construction was the apparent

1015low bidder on the project, with a bid of $1,073,000. There was

1029some concern expressed by the architect reviewing the bids

1038because the bids were all within ten percent of each other for

1050the top bidders, with the bidders 2-10 being within six percent

1061of each other. In an e-mail to Dianna White, the Senior Buyer

1073for UNF purchasing, Mr. Norman stated:

1079Overall there was a 20% range in bid prices

1088which I attribute to a significant difference

1095in the size, quality and abilities of the

1103contractors that bid this project. The

1109apparently low bidder was $60,516 below the

1117second low bidder and $83,000 below the third

1126low bidder. This is a significant concern

1133since there is only $46,484 between the

1141second and fifth low bidders. I suggest the

1149apparent low bidder be contacted and asked if

1157they feel comfortable with their bid, because

1164it appears to me they are missing something

1172significant in their pricing. Purchasing

1177should also carefully review their current

1183financials and current bonding capacity if

1189this is allowed.

11929. Project reference checks, price verification against the

1200architect's construction estimate and bonding checks were

1207performed with respect to the four lowest bidding companies:

1216Core Construction, Pooley Contracting, Rivers & Rivers and Warden

1225Construction.

122610. Pooley Contracting, the second-lowest bidder, was

1233disqualified as non-responsive because its bid package did not

1242include a bonding letter.

124611. Core provided the names of three completed projects

1255that were valued at over one million dollars. Dianna White

1265called each of the references provided, not only for Core but for

1277three of the four lowest bidders. The same questions were asked

1288of each reference for each company: 1) Was the project on time

1300and within budget; 2) Did the project run smoothly; 3) Were

1311project issues handled; and 4) Would you use the contractor

1321again.

132212. Calls related to Pooley Contracting were not completed

1331because it was disqualified as non-responsive. While the

1339references for Rivers & Rivers and Warden were consistently good,

1349two of the three references received for Core were not. Ms.

1360White described them as the most "strongly negative" references

1369she had ever received. In particular, the references indicated

1378difficulty in completing jobs within budget and on time, which

1388the Respondent viewed as the basis for determining whether a

1398contractor had successfully completed a project. Two of the

1407references indicated that they would not use the contractor

1416again, or as one put it, "not if there was any way around it."

143013. Based on the recommendations received, the Purchasing

1438Office for the University recommended that Core Construction be

1447disqualified for failing to demonstrate successful completion of

1455three projects over one million dollars that were similar in

1465scope. Because Pooley Construction was also disqualified, the

1473Purchasing Department recommended that the Project be awarded to

1482the third-lowest bidder, Rivers & Rivers.

148814. The recommendation to award the project to Rivers &

1498Rivers was accepted by the Vice President of Administration and

1508Finance, and on February 18, 2009, a Notice of Award issued

1519identifying Rivers & Rivers as the company receiving the award.

152915. On February 19, 2009, Core Construction notified

1537Respondent that it intended to protest the award of the Project

1548to Rivers & Rivers. On February 24, 2009, Core Construction

1558provided a $10,000.00 surety bond and a written protest of the

1570award.

157116. The basis of the protest was two-fold. First, Core

1581Construction contended that Rivers & Rivers did not meet the

1591qualification criteria set out in the ITB, because it was did not

1603have a minimum of five years of general contractor experience

1613under the current company name. Second, Core felt that the poor

1624references received should not be a basis for disqualification.

163317. Upon receiving the bid protest, Respondent contacted

1641Rivers & Rivers to verify its licensure status. Upon inquiry, it

1652was determined that while the principals of the company had over

166330 years of experience, the Rivers & Rivers entity had not been

1675licensed under that name for the requisite five years.

168418. While no action has been taken while this bid protest

1695is pending, Respondent indicated its intention to withdraw the

1704award from Rivers & Rivers and award the contract instead to the

1716next lowest bidder.

171919. The procedures used by the University in determining

1728the appropriate award were not contrary to law, against the

1738University's governing statutes, rules or policies or the

1746specifications of the invitation to bid.

175220. It was consistent with University policy to check

1761references for projects of similar scope and size. Therefore, it

1771was appropriate to ask for and check references for projects of

1782over one million dollars.

178621. There is no indication that any bidder questioned what

1796the University would consider as successful completion of a

1805project. The time for questioning this issue would have been

1815when the specifications were issued, consistent with Article I,

1824Section 7 of the ITB. Having a project come in on time and

1837within budget is a reasonable measure of successful completion.

1846It is not the same as "substantial completion," which generally

1856refers to a point of time in the construction process, not the

1868final completion of the project.

1873CONCLUSIONS OF LAW

187622. The Division of Administrative Hearings has

1883jurisdiction over the subject matter and the parties to this

1893action in accordance with Florida Board of Governors Regulation

190218.002. This hearing has been conducted in accordance with the

1912requirements of Board of Governor's Regulation 18.002 and the

1921University's Regulation 13.0020R.

192423. Core Construction has standing to bring this bid

1933protest inasmuch as it was the apparent low bidder for the

1944project.

194524. As the Petitioner in this proceeding, it is Core

1955Construction's obligation to demonstrate that the award of the

1964contract to the successful bidder is contrary to law, against the

1975University's governing statutes, rules or policies or the

1983specifications of the invitation to bid.

198925. Core Construction was successful in proving that Rivers

1998& Rivers should be disqualified because of its failure to meet

2009the qualification criteria in terms of years of experience.

2018The University acknowledged this problem and indicated its intent

2027to vacate the award to Rivers & Rivers on this basis.

203826. The elimination of Rivers & Rivers, however, does not

2048result in an award to Core Construction. Consistent with

2057University procedures and the terms of the ITB, the Purchasing

2067Department asked for references with respect to jobs completed in

2077the last three years that were over one million dollars in size.

2089Consistent with University procedures and the terms of the ITB,

2099Purchasing Staff asked a set of questions designed to determine

2109whether bidders met the specified criteria regarding completion

2117of similar projects within the last three years. Completion of

2127reference checks from the persons identified by Petitioner in its

2137response to the ITB led to the reasonable conclusion that

2147Petitioner did not meet this criteria.

215327. Petitioner maintains that it had very good references

2162from other projects completed during the three year period.

2171However, these projects were smaller in scope and did not meet

2182the criteria for references specified in the ITB. To consider

2192these references, when no other bidder was given the opportunity

2202to supplement its bid, would serve to give to Core Construction

2213an unfair advantage.

221628. The decision to eliminate Core Construction from

2224consideration is not contrary to law, against the University's

2233governing statutes, rules or policies or the specifications of

2242the invitation to bid.

2246RECOMMENDATION

2247Upon consideration of the facts found and conclusions of law

2257reached, it is

2260RECOMMENDED:

2261That the President of the University of North Florida,

2270pursuant to his authority under Board of Governor's Regulation

227918.002, enter a final order dismissing Petitioner's written

2287protest.

2288DONE AND ENTERED this 30th day of April, 2009, in

2298Tallahassee, Leon County, Florida.

2302S

2303LISA SHEARER NELSON

2306Administrative Law Judge

2309Division of Administrative Hearings

2313The DeSoto Building

23161230 Apalachee Parkway

2319Tallahassee, Florida 32399-3060

2322(850) 488-9675 Fax Filing 921-6847

2327www.doah.state.fl.us

2328Filed with the Clerk of the

2334Division of Administrative Hearings

2338this 30th day of April, 2009.

2344COPIES FURNISHED:

2346Jay H. Chung

2349Core Construction Company, Inc.

23534940 Emerson Street, Suite 205

2358Jacksonville, Florida 32207

2361Paul Christopher Wrenn, Esquire

2365University of North Florida

2369J.J. Daniel Hall, Suite 2100

23741 University of North Florida Drive

2380Jacksonville, Florida 32224

2383John A. Delaney, President

2387University of North Florida

2391J.J. Daniel Hall, Suite 2800

23961 University of North Florida Drive

2402Jacksonville, Florida 32224

2405NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

2411Pursuant to the procedure specified in Board of Governor's Rule

242118.002, upon submission of this Recommended Order to the President

2431of the University of North Florida, the President will issue a

2442preliminary order for final action and notify the parties of such

2453order. The preliminary order of the president shall be final,

2463unless the firm under consideration takes exception to such order;

2473in which event it may file with the President such exceptions within

2485twenty-one days of receipt of notice of the preliminary order.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 05/27/2009
Proceedings: Notice of Filing and President's Confirmation of President's Final Order Dismissing Peitioner's Written Protest filed.
PDF:
Date: 05/04/2009
Proceedings: Agency Final Order
PDF:
Date: 05/04/2009
Proceedings: Notice of Filing President's Final Order Dismissing Peitioner's Written Protest filed.
PDF:
Date: 05/04/2009
Proceedings: President's Final Order Dismissing Bid Protest of Core Construction Company filed.
PDF:
Date: 04/30/2009
Proceedings: Recommended Order
PDF:
Date: 04/30/2009
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 04/30/2009
Proceedings: Recommended Order (hearing held April 20, 2009). CASE CLOSED.
PDF:
Date: 04/28/2009
Proceedings: Core Construction Company/The University of North Florida Board of Trustees Proposed Recommended Order filed.
PDF:
Date: 04/24/2009
Proceedings: (Respondent`s Proposed) Recommended Order filed.
PDF:
Date: 04/20/2009
Proceedings: Letter to Judge Nelson from N. Cooper enclosing documents to be added as evidence (documents not available for viewing) filed.
Date: 04/20/2009
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 04/16/2009
Proceedings: Pre-hearing Stipulation filed.
PDF:
Date: 04/07/2009
Proceedings: Amended Order of Pre-hearing Instructions.
PDF:
Date: 04/07/2009
Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for April 20, 2009; 9:30 a.m.; Jacksonville and Tallahassee, FL; amended as to blank).
PDF:
Date: 04/06/2009
Proceedings: Motion in Limine filed.
PDF:
Date: 04/01/2009
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 04/01/2009
Proceedings: Notice of Hearing by Video Teleconference (hearing set for April 20, 2009; 9:30 a.m.; Jacksonville and Tallahassee, FL).
PDF:
Date: 03/25/2009
Proceedings: Invitation to Bid filed.
PDF:
Date: 03/25/2009
Proceedings: Notice of Intent to Protest filed.
PDF:
Date: 03/25/2009
Proceedings: Agency referral

Case Information

Judge:
LISA SHEARER NELSON
Date Filed:
03/25/2009
Date Assignment:
03/25/2009
Last Docket Entry:
05/27/2009
Location:
Jacksonville, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related DOAH Cases(s) (1):