09-001567BID
Core Construction Company vs.
University Of North Florida
Status: Closed
Recommended Order on Thursday, April 30, 2009.
Recommended Order on Thursday, April 30, 2009.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8CORE CONSTRUCTION COMPANY, )
12)
13Petitioner, )
15)
16vs. ) Case No. 09-1567BID
21)
22UNIVERSITY OF NORTH FLORIDA, )
27)
28Respondent. )
30)
31RECOMMENDED ORDER
33On April 20, 2009, a duly-noticed hearing was held by means
44of video-teleconferencing in Tallahassee and Jacksonville,
50Florida, before Administrative Law Judge Lisa Shearer Nelson, of
59the Division of Administrative Hearings.
64APPEARANCES
65For Petitioner: Paul Christopher Wrenn, Esquire
71University of North Florida
75J.J. Daniel Hall, Suite 2100
801 University of North Florida Drive
86Jacksonville, Florida 32224-7699
89For Respondent: Jay Chung, President
94Core Construction Company
974940 Emerson Street, Suite 205
102Jacksonville, Florida 32207
105STATEMENT OF THE ISSUE
109The issue to be determined is whether Respondent's proposed award for ITB 09-22 for Building 14B renovation is contrary to
129law, against the University's governing statutes, rules or
137policies or the specifications of the invitation to bid.
146PRELIMINARY STATEMENT
148On February 27, 2009, the University of North Florida (UNF
158or the University) received a formal protest from Core
167Construction Company challenging the University's award of ITB-
17509-22 (GC's for Building 14B Renovation). On March 25, 2009, the
186protest was referred to the Division of Administrative Hearings
195pursuant to the University's contract with the Division with a
205request that an administrative law judge be assigned. The case
215was assigned to the undersigned and, after a telephone conference
225with the parties held March 30, 2009, it was agreed that the
237hearing would be held by means of video-conferencing on April 20,
2482009, and the hearing proceeded as scheduled.
255The hearing was conducted pursuant to the authority granted
264in Florida Board of Governors Rule 18.002, and the procedures
274outlined in University of North Florida Regulation 13.0020R.
282Consistent with that regulation, the parties exchanged exhibits
290in advance of the hearing, and submitted a prehearing statement
300including admitted facts which have been incorporated into the
309findings of fact below. Neither party objected to the
318documentary evidence submitted by the other. At hearing,
326Petitioner presented the testimony of Jay Chung, Dirk Harrison,
335and Gary Arcuri, and Petitioner's Exhibits 1-13 were admitted
344into evidence. Respondent submitted the testimony of Dianna
352White and Kathryn Ritter, and Respondent's Exhibits 1-12 were
361admitted.
362The parties both expressed the desire for the proceedings to
372be expedited as much as possible. To that end, it was agreed
384that proposed recommended orders would be submitted no later than
394April 27, 2009. Both parties timely submitted their proposed
403orders, which have been carefully considered in the preparation
412of this Recommended Order.
416FINDINGS OF FACT
4191. The University of North Florida published its Notice of
429Bid/Request for Proposal in reference to ITB #09-22 entitled
"438GC's for Building 14B Renovation" on December 19, 2008, with a
449submission deadline of January 27, 2009. The opening date was
459eventually extended to January 30, 2009.
4652. There were four addendums to the ITB #09-22 Project.
4753. The Notice of Bid/Request for Proposal document
483contained the following provisions:
487This project consists of the following scope
494of work: The work includes all labor,
501supervision, equipment, and materials
505required to execute the Contract Documents in
512two phases for the tenant build-out of the
520existing UNF Building 14-B (approximate
525square footage 9742). The work includes, but
532is not limited to, demolition of all interior
540walls, finishes, mechanical, electrical,
544plumbing and communication components as well
550as a new exterior curtain wall system.
557Exterior construction will include new
562glazing in aluminum curtain wall. Interior
568construction will include new gypsum
573wallboard partitions with metal stud walls,
579millwork, suspended acoustical and gypsum
584wallboard ceilings, wood and metal doors in
591hollow metal frames, coiling overhead
596grilles, toilet partitions and vanities.
601Interior finishes include carpeting,
605resilient tile, ceramic tile, painting, and
611window treatments. Mechanical work includes
616installation of new Owner provided HVAC units
623with ductwork and all necessary connections
629to the UNF Central Plant chilled water
636system. Plumbing includes new piping and
642fixtures for the tenant build-out and
648renovation of the group male and female
655restrooms. Electrical work includes new
660wiring, devices and lighting for the new
667tenant build-out.
669Successful bidders must have demonstrable
674previous experience with the described
679systems and technical requirements. All
684bidders must be qualified at the time of the
693bid opening in accordance with the Bidders
700Qualification within the ITB 09-22 Bid
706documents. . .
7094. Article I, Section 2 includes a heading in bold stating
"720Qualification Criteria." This section states:
725Participants must qualify to bid on this
732project. UNF will utilize the following
738criteria to qualify the general contractors
744within this ITB. The information must be
751completed on the UNF Qualifications Form
757provided (page 10-11):
760Bonding: Demonstrates a bonding capacity of
766at least $2 million dollars and has an A.M.
775Best Rating of "A-V" or better.
781Licenses: Company is licensed to do business
788in the state of Florida and approved by the
797US Department of Treasury listing as an
804acceptable surety.
806Project references: Company has successfully
811completed at least 3 commercial construction
817projects of more than $1 million dollars each
825in the past three (3) years. List 3 such
834projects to include project name, client
840name, completion date, location, project
845value, role in project. Reference: Project
851name, owner, owner's representative
855name/phone number, completion date and
860construction cost.
862Years of experience: Company has a minimum
869five (5) years of GC experience under the
877current company name.
8805. The directions for the General Contractor's
887Qualification Summary, under Related Experience, reiterated that
894the bidder was to list "No more than 4 projects of comparable
906type, size and complexity. (1) Project must be for a
916college/university)."
9176. Addendum I for the Project, issued January 9, 2009,
927clarified that the requirement for having completed successfully
935a project of similar size and scope at a Florida University in
947the last three years is a qualification factor for this project.
9587. Addendum II, issued January 12, 2009, removed the
967requirement for bidders to have completed one project for a
977college or university. The other two addenda did not address
987contractor qualifications.
9898. Petitioner, Core Construction Company (Core Construction
996or Petitioner) bid in response to the ITB. Approximately 19
1006other bidders also responded. Core Construction was the apparent
1015low bidder on the project, with a bid of $1,073,000. There was
1029some concern expressed by the architect reviewing the bids
1038because the bids were all within ten percent of each other for
1050the top bidders, with the bidders 2-10 being within six percent
1061of each other. In an e-mail to Dianna White, the Senior Buyer
1073for UNF purchasing, Mr. Norman stated:
1079Overall there was a 20% range in bid prices
1088which I attribute to a significant difference
1095in the size, quality and abilities of the
1103contractors that bid this project. The
1109apparently low bidder was $60,516 below the
1117second low bidder and $83,000 below the third
1126low bidder. This is a significant concern
1133since there is only $46,484 between the
1141second and fifth low bidders. I suggest the
1149apparent low bidder be contacted and asked if
1157they feel comfortable with their bid, because
1164it appears to me they are missing something
1172significant in their pricing. Purchasing
1177should also carefully review their current
1183financials and current bonding capacity if
1189this is allowed.
11929. Project reference checks, price verification against the
1200architect's construction estimate and bonding checks were
1207performed with respect to the four lowest bidding companies:
1216Core Construction, Pooley Contracting, Rivers & Rivers and Warden
1225Construction.
122610. Pooley Contracting, the second-lowest bidder, was
1233disqualified as non-responsive because its bid package did not
1242include a bonding letter.
124611. Core provided the names of three completed projects
1255that were valued at over one million dollars. Dianna White
1265called each of the references provided, not only for Core but for
1277three of the four lowest bidders. The same questions were asked
1288of each reference for each company: 1) Was the project on time
1300and within budget; 2) Did the project run smoothly; 3) Were
1311project issues handled; and 4) Would you use the contractor
1321again.
132212. Calls related to Pooley Contracting were not completed
1331because it was disqualified as non-responsive. While the
1339references for Rivers & Rivers and Warden were consistently good,
1349two of the three references received for Core were not. Ms.
1360White described them as the most "strongly negative" references
1369she had ever received. In particular, the references indicated
1378difficulty in completing jobs within budget and on time, which
1388the Respondent viewed as the basis for determining whether a
1398contractor had successfully completed a project. Two of the
1407references indicated that they would not use the contractor
1416again, or as one put it, "not if there was any way around it."
143013. Based on the recommendations received, the Purchasing
1438Office for the University recommended that Core Construction be
1447disqualified for failing to demonstrate successful completion of
1455three projects over one million dollars that were similar in
1465scope. Because Pooley Construction was also disqualified, the
1473Purchasing Department recommended that the Project be awarded to
1482the third-lowest bidder, Rivers & Rivers.
148814. The recommendation to award the project to Rivers &
1498Rivers was accepted by the Vice President of Administration and
1508Finance, and on February 18, 2009, a Notice of Award issued
1519identifying Rivers & Rivers as the company receiving the award.
152915. On February 19, 2009, Core Construction notified
1537Respondent that it intended to protest the award of the Project
1548to Rivers & Rivers. On February 24, 2009, Core Construction
1558provided a $10,000.00 surety bond and a written protest of the
1570award.
157116. The basis of the protest was two-fold. First, Core
1581Construction contended that Rivers & Rivers did not meet the
1591qualification criteria set out in the ITB, because it was did not
1603have a minimum of five years of general contractor experience
1613under the current company name. Second, Core felt that the poor
1624references received should not be a basis for disqualification.
163317. Upon receiving the bid protest, Respondent contacted
1641Rivers & Rivers to verify its licensure status. Upon inquiry, it
1652was determined that while the principals of the company had over
166330 years of experience, the Rivers & Rivers entity had not been
1675licensed under that name for the requisite five years.
168418. While no action has been taken while this bid protest
1695is pending, Respondent indicated its intention to withdraw the
1704award from Rivers & Rivers and award the contract instead to the
1716next lowest bidder.
171919. The procedures used by the University in determining
1728the appropriate award were not contrary to law, against the
1738University's governing statutes, rules or policies or the
1746specifications of the invitation to bid.
175220. It was consistent with University policy to check
1761references for projects of similar scope and size. Therefore, it
1771was appropriate to ask for and check references for projects of
1782over one million dollars.
178621. There is no indication that any bidder questioned what
1796the University would consider as successful completion of a
1805project. The time for questioning this issue would have been
1815when the specifications were issued, consistent with Article I,
1824Section 7 of the ITB. Having a project come in on time and
1837within budget is a reasonable measure of successful completion.
1846It is not the same as "substantial completion," which generally
1856refers to a point of time in the construction process, not the
1868final completion of the project.
1873CONCLUSIONS OF LAW
187622. The Division of Administrative Hearings has
1883jurisdiction over the subject matter and the parties to this
1893action in accordance with Florida Board of Governors Regulation
190218.002. This hearing has been conducted in accordance with the
1912requirements of Board of Governor's Regulation 18.002 and the
1921University's Regulation 13.0020R.
192423. Core Construction has standing to bring this bid
1933protest inasmuch as it was the apparent low bidder for the
1944project.
194524. As the Petitioner in this proceeding, it is Core
1955Construction's obligation to demonstrate that the award of the
1964contract to the successful bidder is contrary to law, against the
1975University's governing statutes, rules or policies or the
1983specifications of the invitation to bid.
198925. Core Construction was successful in proving that Rivers
1998& Rivers should be disqualified because of its failure to meet
2009the qualification criteria in terms of years of experience.
2018The University acknowledged this problem and indicated its intent
2027to vacate the award to Rivers & Rivers on this basis.
203826. The elimination of Rivers & Rivers, however, does not
2048result in an award to Core Construction. Consistent with
2057University procedures and the terms of the ITB, the Purchasing
2067Department asked for references with respect to jobs completed in
2077the last three years that were over one million dollars in size.
2089Consistent with University procedures and the terms of the ITB,
2099Purchasing Staff asked a set of questions designed to determine
2109whether bidders met the specified criteria regarding completion
2117of similar projects within the last three years. Completion of
2127reference checks from the persons identified by Petitioner in its
2137response to the ITB led to the reasonable conclusion that
2147Petitioner did not meet this criteria.
215327. Petitioner maintains that it had very good references
2162from other projects completed during the three year period.
2171However, these projects were smaller in scope and did not meet
2182the criteria for references specified in the ITB. To consider
2192these references, when no other bidder was given the opportunity
2202to supplement its bid, would serve to give to Core Construction
2213an unfair advantage.
221628. The decision to eliminate Core Construction from
2224consideration is not contrary to law, against the University's
2233governing statutes, rules or policies or the specifications of
2242the invitation to bid.
2246RECOMMENDATION
2247Upon consideration of the facts found and conclusions of law
2257reached, it is
2260RECOMMENDED:
2261That the President of the University of North Florida,
2270pursuant to his authority under Board of Governor's Regulation
227918.002, enter a final order dismissing Petitioner's written
2287protest.
2288DONE AND ENTERED this 30th day of April, 2009, in
2298Tallahassee, Leon County, Florida.
2302S
2303LISA SHEARER NELSON
2306Administrative Law Judge
2309Division of Administrative Hearings
2313The DeSoto Building
23161230 Apalachee Parkway
2319Tallahassee, Florida 32399-3060
2322(850) 488-9675 Fax Filing 921-6847
2327www.doah.state.fl.us
2328Filed with the Clerk of the
2334Division of Administrative Hearings
2338this 30th day of April, 2009.
2344COPIES FURNISHED:
2346Jay H. Chung
2349Core Construction Company, Inc.
23534940 Emerson Street, Suite 205
2358Jacksonville, Florida 32207
2361Paul Christopher Wrenn, Esquire
2365University of North Florida
2369J.J. Daniel Hall, Suite 2100
23741 University of North Florida Drive
2380Jacksonville, Florida 32224
2383John A. Delaney, President
2387University of North Florida
2391J.J. Daniel Hall, Suite 2800
23961 University of North Florida Drive
2402Jacksonville, Florida 32224
2405NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2411Pursuant to the procedure specified in Board of Governor's Rule
242118.002, upon submission of this Recommended Order to the President
2431of the University of North Florida, the President will issue a
2442preliminary order for final action and notify the parties of such
2453order. The preliminary order of the president shall be final,
2463unless the firm under consideration takes exception to such order;
2473in which event it may file with the President such exceptions within
2485twenty-one days of receipt of notice of the preliminary order.
- Date
- Proceedings
- PDF:
- Date: 05/27/2009
- Proceedings: Notice of Filing and President's Confirmation of President's Final Order Dismissing Peitioner's Written Protest filed.
- PDF:
- Date: 05/04/2009
- Proceedings: Notice of Filing President's Final Order Dismissing Peitioner's Written Protest filed.
- PDF:
- Date: 05/04/2009
- Proceedings: President's Final Order Dismissing Bid Protest of Core Construction Company filed.
- PDF:
- Date: 04/30/2009
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 04/28/2009
- Proceedings: Core Construction Company/The University of North Florida Board of Trustees Proposed Recommended Order filed.
- PDF:
- Date: 04/20/2009
- Proceedings: Letter to Judge Nelson from N. Cooper enclosing documents to be added as evidence (documents not available for viewing) filed.
- Date: 04/20/2009
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 04/07/2009
- Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for April 20, 2009; 9:30 a.m.; Jacksonville and Tallahassee, FL; amended as to blank).
Case Information
- Judge:
- LISA SHEARER NELSON
- Date Filed:
- 03/25/2009
- Date Assignment:
- 03/25/2009
- Last Docket Entry:
- 05/27/2009
- Location:
- Jacksonville, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Jay H. Chung
Address of Record -
Paul Christopher Wrenn, Esquire
Address of Record