09-004996BID
Close Construction, Inc. vs.
South Florida Water Management District
Status: Closed
Recommended Order on Tuesday, January 5, 2010.
Recommended Order on Tuesday, January 5, 2010.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8CLOSE CONSTRUCTION, INC., )
12)
13Petitioner, )
15)
16vs. ) Case No. 09-4996BID
21)
22SOUTH FLORIDA WATER MANAGEMENT )
27DISTRICT, )
29)
30Respondent, )
32)
33and )
35)
36WORTH CONTRACTING, INC., )
40)
41Intervenor. )
43)
44RECOMMENDED ORDER
46Pursuant to appropriate notice, this proceeding came on for
55formal hearing before P. Michael Ruff, duly-designated
62Administrative Law Judge of the Division of Administrative
70Hearings, on October 19, 2009. The hearing was conducted by
80video conference between Tallahassee, Florida, and West Palm
88Beach, Florida. The parties were located in West Palm Beach and
99the judge was located in Tallahassee. The appearances were as
109follows:
110APPEARANCES
111For Petitioner: Andrew J. Baumann, Esquire
117Lewis, Longman and Walker, P.A.
1221700 Palm Beach Lakes Boulevard,
127Suite 1000
129West Palm Beach, Florida 33401-2006
134For Respondent: Josef M. Fiala, Esquire
140South Florida Water Management District
1453301 Gun Club Road, MSC 1410
151West Palm Beach, Florida 33406
156For Intervenor: Robert L. Frye, Esquire
162Vezina, Lawrence & Piscitelli
166The Museum Building
169300 Southwest First Avenue, Suite 150
175Fort Lauderdale, Florida 33301
179STATEMENT OF THE ISSUES
183The issues to be resolved in this proceeding concern
192whether the Petitioner, Close Construction, Inc. (Petitioner),
199(Close) was the lowest responsive and responsible bidder in the
209Request For Bid (RFB) Number 6000000262, whether the subject
218contract should be awarded to the Petitioner, and,
226concomitantly, whether the Respondent agency's decision to award
234the contract to the Intervener, Worth Contracting, Inc. (Worth)
243was clearly erroneous, contrary to competition, arbitrary or
251capricious.
252PRELIMINARY STATEMENT
254This dispute arose when the South Florida Water Management
263District (Respondent or District) issued an RFB designed to
272procure refurbishment and automation of district-owned and
279operated water control structures G-123 and S-34. After the RFB
289was issued on June 5, 2009, the District issued two addenda to
301the RFB. On June 30, 2009, Addendum No. Two, which was the
313subject of this dispute, was issued. It would require that each
324bidder add a $40,000 discretionary owner-directed allowance, for
333Florida Power and Light utility work, to the base bid. Addendum
344No. Two also included a revised Bid form that included an
355itemization of this $40,000 owner-discretionary allowance as an
364expressly identified itemization. The new Bid form was attached
373to Addendum No. Two and the Addendum was supplied to the
384bidders, including the Petitioner and Intervenor, by electronic
392posting on the above date.
397Six bids were received in response to the RFB, including
407bids from Close, from Cone and Graham, Inc., Worth Contracting
417Inc., Inter-County Engineering, Inc., Murray Logan Construction,
424Inc. and Harry Pepper and Associates. The bids were opened on
435July 10, 2009.
438Cone and Graham, Inc., was the lowest bidder; however, it
448withdrew its bid from consideration. The next lowest bidder was
458Close. The District, however, determined Close to be non-
467responsive for purportedly failing to comply with the
475requirements of Addendum No. Two. Specifically, Close did not
484replace the original Bid form with the revised Bid Form
494expressly identifying, as a separate itemization, the additional
502$40,000 owner-directed allowance for the Florida Power and Light
512(FPL) utility work, as required by Addendum Two. Worth was
522deemed to be in compliance with Addendum Two, and otherwise
532compliant with the RFB. It was deemed responsible and
541responsive and awarded the bid by the District. The posting of
552the intent to award was on August 14, 2009.
561Close filed a timely protest of the intended award and the
572matter was then referred to the Division of Administrative
581Hearings on September 14, 2009. The undersigned Administrative
589Law Judge was assigned to conduct the formal proceeding and upon
600conferring with the parties, the matter was set for hearing for
611October 19, 2009, by video conference between Tallahassee and
620West Palm Beach. In the meantime, on October 1, 2009, the
631Notice to Bidders was filed and served by the Respondent
641District, which resulted in the intervention of Worth in this
651proceeding.
652The cause came on for final hearing as noticed. Close, the
663Petitioner, presented the testimony of Danny Boromei, the Vice-
672President for Civil Construction of the Petitioner Close,
680Christopher Rossi, Close's estimator, and Gerard Flynn, the
688Construction Manager for the South Florida Water Management
696District.
697The District presented the testimony of James Reynolds, the
706Senior Contract Specialist, and Donna Lavery, the Contracts
714Manager. The parties submitted Joint Exhibits 1 through 7 which
724were admitted into evidence. Official recognition was taken of
733Chapter 120, Florida Statutes, and of relevant portions of the
743Florida Administrative Code.
746The Petitioner contends that the intended award of the
755contract to Worth is erroneous based upon its position that the
766irregularity in the Petitioner's bid, involving mistakenly using
774the original Bid Form, was a non-material irregularity which
783conferred no competitive advantage upon the Petitioner. Close
791maintains that the District should have verified any question it
801had regarding Close's bid, based upon the requirements of the
811District's procurement and contracting policies and policy
818manual, and under the express terms of the RFB. The Petitioner
829thus contends that the irregularity as to its bid should have
840been waived, that the bid should have been verified by the
851Respondent District in accordance with its policies on
859verification of bids, and that the Petitioner should have
868received the award for its bid of $3,751,795.00, which is
880$146,615.00 lower than the awardee, Worth.
887Upon conclusion of the hearing the parties ordered a
896transcription thereof and took the opportunity to submit
904Proposed Recommended Orders. The transcript of the proceeding
912was filed on November 6, 2009, and Proposed Recommended Orders
922were thereafter filed by agreement of the parties on
931November 16, 2009. The Proposed Recommended Orders have been
940considered in the rendition of this Recommended Order.
948FINDINGS OF FACT
9511. The South Florida Water Management District is a public
961corporation authorized under Chapter 373, Florida Statutes. It
969issued a request for bids for the refurbishment and automation
979of certain facilities in Broward County, Florida. Close is a
989construction company duly authorized to do business in the state
999of Florida. It was one of the bidders on the procurement
1010represented by the subject request for bids and is the
1020Petitioner in this case.
10242. This dispute had its beginnings on June 5, 2009, when
1035the Respondent issued RFB number 6000000262. The RFB solicited
1044construction services for the refurbishment and automation of
1052two facilities in Broward County. The procurement would involve
1061the installation of new direct-drive electric pumps at the
1070Respondent's G-123 Pump Station in Broward County, along with
1079the construction of an equipment shelter and the replacement of
1089a retaining wall with a poured concrete retaining wall, as well
1100as refurbishment of "pump flap gates." The RFB also requested
1110construction services for the replacement of gates at the
1119Respondent's S-34 water-control structure in Broward County.
1126Both facilities would thus be automated so that they can be
1137remotely operated from the Respondent's headquarters in West
1145Palm Beach.
11473. After issuance of the RFB, two addenda were supplied to
1158vendors and were posted. The first addendum was posted on or
1169about June 19, 2009, concerning a change in specifications for
1179flap gates and is not the subject of this dispute. Addendum
1190No. Two was electronically posted on or about June 30, 2009. It
1202amended the technical specifications of the RFB by deleting
1211Section 11212 regarding measurement of payment of electric
1219motors/belt-driven axial flow pumps. That addendum also added a
1228new measure and payment to Subpart 1.01 of the technical
1238specifications to provide for an owner-directed allowance of
1246$40,000.00 to provide for the potential need for certain
1256electrical utility work to be done by FPL in order to complete
1268the project.
12704. Addendum No. Two added an additional term to the RFB in
1282providing that the $40,000.00 allowance price "Shall be added to
1293the other costs to complete the bid." The second Addendum also
1304stated, "The allowance price shall be used at the discretion of
1315the District and, if not used, will be deducted from the final
1327Contract Price." That addendum also directed bidders to replace
1336the original Bid Form 00320-2, which had been enclosed with the
1347RFB, with a new Bid Form, 00320R1-2. The new Bid Form is
1359identical to the original form except that the schedule of bid
1370prices contained in paragraph four, on page 003201-2, was
1379altered to itemize the $40,000.00 discretionary cost allowance.
1388The original form had contained a single line for the bidder's
1399lump sum bid price, whereas the revised form provided for a lump
1411sum bid amount to be itemized and a base bid amount, which
1423required the bidder to enter on the form the amount of its bid,
1436then add the discretionary cost amount and write the sum of
1447those two numbers on a third line.
14545. In paragraph four of the new bid form there is re-
1466printed language concerning the use of the discretionary
1474allowance which appeared on the face of Addendum No. Two. Other
1485than the change to paragraph four and the alteration of the page
1497numbers to include an "R" in the page number, the revised bid
1509form is identical to the original bid form. The other bid
1520documents were not altered in any manner by Addendum No. Two.
15316. The deadline for bid submissions was Thursday, July 9,
15412009, at 2:30 p.m. The Petitioner timely submitted its bid to
1552the District. In submitting its bid however, the Petitioner
1561used the original bid form which had been enclosed with the RFB.
1573The bid form submitted was an exact copy of the bid form
1585furnished by the District which Close had printed from the
1595electronic copy of the RFB received from the District. The
1605Petitioner did not substitute the revised bid form, attached to
1615Addendum No. Two, for the original form in submitting its bid.
1626The Petitioner's bid was deemed non-responsive by the District
1635and was rejected on the basis that Close had failed to submit
1647the bid on the revised form required by Addendum No. Two.
16587. Thereafter, the District, at its August 13, 2009,
1667meeting, approved award of the bid to Worth. The intent to
1678award was posted electronically on or about August 14, 2009.
16888. The persuasive evidence establishes that Close received
1696both addenda to the bid documents. It was aware of the Addendum
1708No. Two, and it accounted for all of the changes to the
1720technical specifications made in both addenda in the preparation
1729of its bid.
17329. The evidence shows that Close was aware of the
1742$40,000.00, owner-directed cost allowance and that it
1750incorporated it in the formulation of its total bid price.
1760Thus, Close's final bid amount was $3,751,795.00. That number
1771included the $40,000.00 cost allowance at issue, added to the
1782bid documents by Addendum No. Two.
178810. The internal bid work sheets, prepared by personnel of
1798Close, identified and itemized the $40,000.00 discretionary cost
1807allowance as a component of the final bid price. The persuasive
1818evidence thus establishes that Close's final bid amount did
1827include the $40,000.00 cost allowance.
183311. Moreover, the written notes of witness Christopher
1841Rossi, the estimator for Close, show the $40,000.00 amount as an
"1853FPL Allowance." Both Mr. Rossi and Mr. Boromei, the Vice
1863President for Close, who prepared the bid, explained that the
1873$40,000.00 was understood by Close to be a cost allowance, that
1885it would only be charged to the District to the extent that it
1898was actually used, at the District's discretion. If it were not
1909used, it was to be deducted from the overall contract price.
1920Addendum Two specifically provides that the discretionary cost
1928allowance was to be used only at the discretion of the District
1940and that the unused portion would be deducted from the contract
1951amount.
195212. When Close submitted its bid it mistakenly submitted
1961it on the original bid form and failed to exchange the bid forms
1974as directed in Item Two of Addendum No. 2.
198313. In paragraph one of both bid forms, however, the
1993bidder is required to specifically fill out, acknowledge and
2002identify all addenda. By doing so the bidder expressly agrees
2012to build the project in conformance with all contract documents,
2022including all addenda, for the price quoted in the bid. Close
2033completed this paragraph, specifically identified both Addendum
2040One and Addendum Two, and specifically agreed to strictly
2049conform, in performance of the work to the plans, specifications
2059and other contract documents, including Addendum Nos. One and
2068Two. Paragraph one was not changed by the addition of Addendum
2079No. Two and it is identical in both the original and the revised
2092forms at issue. Paragraph one of the original and the revised
2103bid forms constitutes an agreement by the bidder to perform and
2114construct a project "in strict conformity with the plans,
2123specifications and other Contract Documents. . . ." The addenda
2133are part of the contract documents and are expressly referenced
2143as such in this agreement. Both bid forms, the original and the
2155revised, include paragraph eight, which clearly states that the
2164bidder will post a bid bond to secure and guaranty that it will
2177enter into a contract with the District, if its bid is selected.
2189Paragraph eight was unchanged by Addendum No. Two and its terms
2200are identical in both Bid forms at issue, including the form
2211that Close signed and submitted as its bid.
221914. The persuasive evidence shows that in submitting its
2228bid, whether on either form, Close committed itself to the
2238identical terms as set forth in the identical contract documents
2248agreed to by Worth and the other bidders. The evidence
2258established that Close intended to bind itself to the terms of
2269the RFB, and all terms of Addendum No. Two, including the
2280discretionary cost allowance term. Close considered itself
2287bound to enter into a contract for the price of its bid if
2300selected by the District. It likewise considered that the price
2310of its bid, would only include the cost allowance if the
2321discretionary allowance was implemented by the District.
232815. Upon the opening of the bids, the firm of Cone and
2340Graham, Inc., was identified as the lowest bidder. Cone and
2350Graham's bid was in the amount of $2,690,000.00. Close was the
2363second lowest bidder, with a bid of $3,751,795.00. The third
2375lowest bidder was Worth Contracting, Inc., with a bid of
2385$3,898,410.00. Cone and Graham was allowed to provide
2395additional information and to even meet with some District staff
2405following the opening of its bid. The additional information it
2415was allowed to provide concerned technical specifications of the
2424pumps proposed in its bid. Through this verification process
2433conducted with the Agency, Cone and Graham ultimately convinced
2442the District to permit them to withdraw its bid without
2452forfeiting their bid bond. This left the Petitioner, Close, the
2462lowest bidder, at $146,615.00 less than the bid submitted by
2473Worth, the initially-awarded bidder.
247716. Close's bid, upon review, was rejected as non-
2486responsive due to its failure to exchange the original Bid form
2497with the revised Bid form, as indicated above, in spite of the
2509fact that Close had also agreed to adhere to the entirety of
2521Addendum No. Two on the face of the Bid form. Thus the
2533recommended award to Worth for the above-referenced additional
2541amount of bid price was adopted by the District, engendering
2551this protest.
255317. James Reynolds, the Contracts Specialist for the
2561District, conceded that it was apparent on the face of Close's
2572bid that a mistake had been made in the use of the original
2585form, rather than the revised form. He conceded there was an
2596inconsistency between Close's clear acknowledgement of and
2603agreement to the terms of the contract documents, which
2612expressly included Addendum No. Two and Close's apparent
2620mistaken use of the original Bid form.
262718. Under the express terms of Article 19.03 of the RFB,
"2638The Bid shall be construed as though the addendum(a) have been
2649received and acknowledged by the bidder." Mr. Reynolds
2657admitted, however, that he did not apply the terms of Article
266819.03 of the RFB in his review of Close's bid and did not
2681construe the bid in the manner provided in the RFB to resolve
2693the apparent inconsistency. He reasoned that Close had used the
2703wrong bid form and looked no further.
271019. The District's Procurement Manual provides a procedure
2718whereby a bidder may correct inadvertent mistakes in its bid.
2728Under the terms of Chapter 5-5 of that manual, where the
2739District knows or has reason to conclude, after unsealing of
2749bids, that a mistake may have been made by a bidder, the
2761District "shall request written verification of the bid." In
2770such a circumstance the bidder "shall be permitted the
2779opportunity to furnish information in support of the bid
2788verification as long as it does not affect responsiveness, i.e.,
2798the bid substantially conforms to the requirements of the RFB as
2809it relates to pricing, surety, insurance, specifications and any
2818other matter unequivocally stated in the RFB as determinant of
2828responsiveness." See Joint Exhibit 7,6 pages 61 and 62, in
2839evidence.
284020. Mr. Reynolds admitted in his testimony that he did not
2851follow the procedure set forth in the manual for verifying a bid
2863because, in his view, that would be allowing an impermissible
2873supplementation of Close's bid. Ms. Lavery, in her testimony,
2882in essence agreed.
288521. The Procurement Manual expressly required the
2892District, upon recognizing the mistake and an inconsistency
2900apparent on the face of Close's bid, to verify that bid and to
2913provide Close with the opportunity to furnish information in
2922support of bid verification. Thus, by the express terms of the
2933manual, a bidder must be given an opportunity to clarify
2943mistakes. The Procurement Manual expressly permits a bidder
2951under these circumstances to correct any "inadvertent, non-
2959judgmental mistake" in its bid. Chapter 5 of the Manual
2969provides that "a non-judgmental mistake" is a mistake not
2978attributable to an error in judgment, such as mistakes in
2988personal judgment or wrongful assumptions of contract
2995obligations. Inadvertent technical errors, such as errors of
3003form rather than substance, are considered non-judgmental
3010errors." See Joint Exhibit 7, page 62, in evidence.
301922. It is patently apparent that Close's use of the
3029original bid form, inadvertently, while also unequivocally
3036acknowledging and agreeing to the entirety of Addendum No. Two,
3046represented a non-judgmental mistake. Both of the District
3054witnesses, however, testified that the policy regarding mistakes
3062was not followed and Close was not given an opportunity under
3073the District's policy to provide additional information to
3081support verification of the bid.
308623. Although Close failed to substitute the revised Bid
3095form for the original Bid form, as called for by Addendum No.
3107Two, its bid was substantively responsive to the technical
3116specifications and requirements of the RFB, and the irregularity
3125is technical in nature. The parties stipulated that the use of
3136the original form, rather than the revised bid form, was the
3147sole basis for Close being determined to be non-responsive by
3157the Agency.
315924. In accordance with Florida Administrative Code Rule
316740E-7.301, in Chapter 5 of the District's Procurement Manual,
3176the District reserves the right to waive minor irregularities in
3186a bid. A material irregularity is defined by the District's
3196policy as one which is not minor in that it: (a) affects the
3209price, quality, time or manner of performance of the service
3219such that it would deprive the District of an assurance that the
3231contract will be entered into, performed and guaranteed
3239according to the specified requirements; (b) provides an
3247advantage or benefit to a bidder which is not enjoyed by other
3259bidders; or (c) undermines the necessary common standards of
3268competition. See Joint Exhibit 7, page 58, in evidence.
327725. The preponderant, persuasive evidence shows that the
3285irregularity in Close's bid did not affect the price of the bid
3297or truly deprive the District of assurance that the contract
3307would be entered into and performed according to all the terms
3318of the RFB, including addenda. The evidence established that
3327Close actually included the $40,000.00 discretionary cost
3335allowance in its final bid price. It merely did not show it as
3348a separate itemization, because it did not use the revised form
3359providing that itemization line. The fact that the
3367discretionary allowance was itemized in the revised bid form, as
3377part of the bid amount, does not equate to an effect on the
3390contract price as a result of Close's using the original Bid
3401form. Close's error, by mistakenly submitting its bid on the
3411original bid form, did not alter the price of its bid. The
3423evidence clearly established that the bid price for Close's bid
3433would be the same regardless of which form it used.
344326. Moreover, the preponderant, persuasive evidence
3449establishes that the use of the original Bid form by Close did
3461not deprive the District of assurance that the contract would be
3472performed in accordance with the all bid documents. Close's
3481bid, secured by its bid bond, clearly acknowledged and agreed to
3492the express terms of Addendum No. Two in their entirety, which
3503included the terms under which the discretionary cost allowance
3512could be applied. Close considered itself bound to the terms of
3523the RFB and assured the Agency that it was so bound by the
3536written acknowledgement and agreement it submitted to the Agency
3545as part of its bid, concerning the elements of Addendum No. Two.
3557The evidence demonstrated that Close understood that the
3565$40,000.00 amount was a discretionary cost allowance and that
3575Close would not be entitled to it unless the District decided to
3587use it.
358927. Despite the opinion of Agency witnesses to the
3598contrary, the error in Close's bid was a technical one and non-
3610material because it did not confer a competitive advantage upon
3620Close. Close's use of the wrong form did not alter the price of
3633its bid. Its mistake in the use of the original bid form could
3646only change the relative, competitive positions of Close and
3655Worth if the amount of the discretionary cost allowance was
3665greater or equal to the difference between those two bids, i.e.,
3676the $146,650.00 amount by which Worth's bid exceeded the bid of
3688Close. 1 / The bid of Worth exceeds Close's bid by an amount far
3702greater than the amount at issue in the discretionary cost
3712allowance identified in Addendum No. Two and expressly itemized
3721in the revised Bid form, i.e. $40,000.00.
372928. The District contends that Close gained some
3737competitive economic advantage over other bidders by having the
3746means by which it could optionally withdraw its bid, based upon
3757alleged non-responsiveness, in not substituting the revised Bid
3765form which would contain the itemization of the $40,000.00 cost
3776allowance. It is difficult to see how it could gain a
3787competitive advantage versus other bidders through some
3794perceived ability to deem itself non-responsive, at its option,
3803and withdraw its bid, thus denying itself the contract. The
3813competitive bidding laws are designed to prevent a firm from
3823gaining a competitive advantage in obtaining a contract versus
3832the efforts of other bidders, not in depriving itself of the
3843opportunity to get the work. Moreover, concerning the argument
3852by the District that this may confer the advantage to Close of
3864allowing it to withdraw its bid at its option and still obtain a
3877refund of its bid bond; even if that occurred, it would not
3889confer a competitive advantage vis-à-vis other bidders. It
3897would merely involve a potential pecuniary advantage to Close's
3906interest, versus that of the Agency itself, which obviously is
3916not a bidder. Moreover, it should again be pointed out that
3927Cone and Graham was allowed to provide additional information
3936concerning its bid elements, and even to meet with the District
3947staff, following the opening of the bids. It was then allowed
3958to withdraw its bid without forfeiting its bid bond.
396729. If the District had inquired, by way of verification
3977of Close's bid, as to whether the discretionary cost amount was
3988included in it's bid, that inquiry does not equate to allowing
3999Close to unlawfully supplement its bid. Indeed, if in response
4009to such an inquiry, Close announced that the discretionary
4018allowance was not included in its bid, its bid at that point
4030would be materially non-responsive to the specifications. If
4038Close was then allowed to supplement its bid by changing its
4049price to add the allowance, such would indeed be an unfair
4060competitive advantage and a violation of law on the part of
4071Close and the Agency. The evidence does not show that such
4082happened or was proposed by any party.
408930. If a verification inquiry had been made and Close
4099announced that, indeed, its bid price did include the subject
4109discretionary cost allowance, without further response to the
4117specifications being added, then no competitive advantage would
4125be afforded Close and no legal violation would occur. In fact,
4136however, as pointed out above, the verification request,
4144pursuant to the District's policy manual, was never made. This
4154was despite the fact that the District's witness, Mr. Reynolds,
4164acknowledged that the use of the original bid form was an
4175apparent mistake on the face of the bid, when considered in
4186conjunction with Close's express agreement to construct the
4194project in strict conformance with all contract documents, and
4203particularly with regard to Addenda Numbers One and Two.
421231. The non-judgmental mistake, involving use of the
4220original bid form in lieu of the revised bid form, could have
4232been easily clarified by a verification inquiry. That policy
4241was not followed, based solely on the fact that the wrong bid
4253form was used, even though the preponderant, persuasive evidence
4262shows that in all material and substantive respects the bid was
4273a conforming, responsive bid and included in its price the
4283discretionary cost allowance. The preponderance of the evidence
4291shows that the mistaken use of the original Bid form was a non-
4304material irregularity under the District's policies and the
4312terms of the RFB.
431632. The District's actions in failing to uniformly apply
4325its own bid verification policy when, in fact, it had allowed
4336verification to one of the other bidders, and when, according to
4347its own witness, it perceived an apparent mistake, was clearly
4357erroneous. It is true that Close may not supplement its bid by
4369changing material terms, but it is permitted to verify whether,
4379in light of the mistaken use of the original Bid form, its bid
4392price, as submitted, included the $40,000.00 discretionary
4400allowance or not. Providing such "yes or no" type of additional
4411information in order to clarify, and only clarify, information
4420already submitted in the bid, in response to an inquiry by the
4432District does not constitute "supplementation" of the bid for
4441purposes of Section 120.57(3)(f), Florida Statutes (2008). NCS
4449Pearson, Inc. v. Dept of Education , 2005 WL 31776, at page 18
4461(DOAH, Feb. 8, 2005).
446533. Even without verification of the bid, the bid on its
4476face agrees to compliance with all terms and specifications,
4485including Addendum No. Two. It is thus determined that there is
4496no material irregularity. The bid submitted by Close does not
4506afford it any competitive advantage vis-à-vis the other bidders
4515and it is responsive.
4519CONCLUSIONS OF LAW
452234. The Division of Administrative Hearings has
4529jurisdiction of the subject matter of and the parties to this
4540proceeding. §§ 120.569 and 120.57(1) and (3), Fla. Stat.
4549(2009).
455035. Section 120.57(3)(f), Florida Statutes, provides in
4557pertinent part as follows:
4561. . . Unless otherwise provided by statute,
4569the burden of proof shall rest with the
4577party protesting the proposed agency action.
4583In a competitive-procurement protest, other
4588than a rejection of all bids, proposals, or
4596replies, the Administrative Law Judge shall
4602conduct a de novo proceeding to determine
4609whether the agency proposed action is
4615contrary to the agency's governing statutes,
4621the agency's rules or policies, or the
4628solicitation specifications. The standard
4632of proof for such proceeding shall be
4639whether the proposed agency action was
4645clearly erroneous, contrary to competition,
4650arbitrary, or capricious. . .
465536. The Petitioner must therefore demonstrate that the
4663agency's proposed action is contrary to governing statutes, the
4672agency's rules or policies or the bid or proposal
4681specifications. It must demonstrate that action by preponderant
4689evidence. Dept. of Transportation v. J.W.C. Company, Inc. , 396
4698So. 2d 778, 787 (Fla. 1st DCA 1981); State Contracting and
4709Engineering Corp. v. Dept. of Transportation , 709 So. 2d 607,
4719609 (Fla. 1998). Stated differently, in a de novo proceeding
4729such as this, pursuant to the above-referenced statutory
4737authority, it must be demonstrated by the Petitioner whether the
4747agency erred in applying a governing principle of law, by virtue
4758of its interpretation or application of its bid specifications
4767or interpretation of the bidder's response thereto.
477437. Whether an act is contrary to competition is
4783determined by considering whether it offends the purpose of the
4793competitive bidding statutes. "The purpose of the competitive
4801bidding process is to secure fair competition on equal terms to
4812all bidders by affording an opportunity for an exact comparison
4822of bids." Harry Pepper and Associates, Inc. v. City of Cape
4833Coral , 352 So. 2d 1190 (Fla. 2d DCA 1977).
484238. Although Close mistakenly used the original Bid form
4851rather than the revised form, the preponderant, persuasive
4859evidence establishes that the deviation was a non-material one
4868and could have been easily remedied by the District by use of
4880its established bid-verification process. Even without the bid
4888verification policy being employed by the District, in the
"4897free-form" stage of this proceeding, the bid document submitted
4906by Close itself showed that it had unequivocally agreed to
4916comply with all specifications and requirements of the RFB and
4926contract documents, including, particularly, Addendum No. Two.
4933The assurance actually provided to the Agency by Close's bid
4943response demonstrates that Close would be bound by its contract
4953price, whether or not the relevant $40,000.00 discretionary cost
4963allowance was separately itemized. Under well-established
4969contract principles, the Agency would have been able to protect
4979itself against being charged such an amount, or portion thereof,
4989over and above the proposed contract price submitted by Close.
499939. The case of Intercontinental Properties v. DHRS , 606
5008So. 2d 380 (Fla. 3d DCA 1992), stands for the proposition that
5020the disqualification of a low bidder for non-responsiveness,
5028where the bid irregularity does not impart an unfair competitive
5038advantage to that bidder, is not favored by the courts. In that
5050case, the court reversed an Administrative Law Judge's finding
5059of unresponsiveness on the part of a low bidder, and the court
5071discussed at length the well-known case of Liberty County v.
5081Baxter's Asphalt and Concrete, Inc. , 421 So. 2d 505 (Fla. 1982).
5092The Intercontinental opinion contains an apt discussion of that
5101Supreme Court decision regarding bid irregularities and
5108principles of competitive bidding:
5112A minor irregularity is a variation from the
5120bid invitation or proposal terms and
5126conditions which does not affect the price
5133of the bid, or give the bidder an advantage
5142or benefit not enjoyed by other bidders, or
5150does not adversely impact the interest of
5157the [agency] . . . [quoting from F.A.C. Rule
516610-13.012]. . .
5169There is a very strong public interest in
5177favor of saving tax dollars in awarding
5184public contracts. There is no public
5190interest, much less a substantial public
5196interest, in disqualifying low bidders for
5202technical deficiencies in form, where the
5208low bidder did not derive any unfair
5215competitive advantage by reason of the
5221technical omission . . .
5226In either event, there is a strong public
5234policy in favor of awarding contracts to the
5242low bidder, and an equal strong public
5249policy against disqualifying the low bidder
5255for technical deficiencies which do not
5261confer an economic advantage on one bidder
5268over another.
5270Id. at 387 (emphasis added).
527540. In the instant situation, Close is the low bidder by a
5287substantial amount of $146,615.00. The preponderant, persuasive
5295evidence establishes that Close received and reviewed Addendum
5303No. Two and incorporated the technical requirements of that
5312addendum, including the $40,000.00 discretionary cost allowance,
5320into the development and submission of its bid. Close included
5330that discretionary cost amount in the bid.
533741. Close specifically agreed to the terms of Addenda
5346Nos. One and Two, but during the final hearing, Mr. Reynolds,
5357testifying for the District, indicated that he viewed Close's
5366agreement in paragraph one of its bid to be void, because an
5378obsolete form was used. He acknowledged, however, that Cone and
5388Graham, on the other hand, had submitted its bid using a portion
5400of the revised form, but had actually signed the page from the
5412original form, as did Close. Despite actually signing a portion
5422of what Mr. Reynolds had described as an obsolete form, he
5433nevertheless found that Cone and Graham's bid documents were
5442responsive in his bid checklist. His position that Close's bid
5452was unresponsive is thus intellectually inconsistent.
545842. Close's bid mistake was a technical error that did not
5469confer any competitive advantage to Close or undermine the
5478common standards of competition. The irregularity did not alter
5487the price of Close's bid and, in any event, the amount of the
5500cost allowance (whether or not it was included in Close's bid
5511price, which it was) was far less than the difference between
5522Close's bid and Worth's bid. Therefore, even if, assuming
5531arguendo , Close's bid did not include the $40,000.00 allowance
5541and, theoretically, it had to be added to Close's bid price,
5552Close's resulting bid price would still be $106,615.00 less than
5563Worth's bid, a not insignificant amount. Only if the amount of
5574the discretionary cost allowance was greater, or at least
5583approximately equal to the $146,615.00 difference between
5591Close's bid and Worth's bid, could Close's mistaken use of the
5602original Bid form possibly alter the competitive positions of
5611the two bidders, or any of the bidders in the procurement for
5623that matter. See , e.g. , Warren Building Company, Inc. v. Dept.
5633of Military Affairs , at page 8-9 Case No. 08-2369BID (DOAH,
5643Aug. 20, 2008). The relative competitive positions of the
5652bidders are simply too far apart to have been altered by the
5664cost allowance factor.
566743. The irregularity in Close's bid did not give it the
5678ability to "look back" to the comparative bids of the other
5689bidders and somehow then alter its bid to its advantage. The
5700notion that Close's mistake conferred upon it the right to
5710supplement its bid and "add" $40,000.00 to its price after the
5722bids are unsealed is entirely unsupported by any persuasive
5731evidence. According to un-refuted evidence, the bid included
5739the allowance. The only inquiry that would need to be made of
5751Close would be whether it could confirm or deny whether the
5762allowance was included, upon a proper verification request by
5771the District. No party to this matter, including Close, has
5781ever suggested that it should be permitted to alter its bid
5792price through the Agency verification process.
579844. In like vein, Close could gain no competitive,
5807economic advantage by having the ability to withdraw its bid
5817without penalty, through use of the obsolete form in its bid
5828submission, as the Respondent District suggests. It is
5836difficult to fathom how Close could gain any competitive
5845advantage over another bidder by acting to withdraw its bid and
5856thus deny itself the work represented by the ultimate contract
5866in this procurement. The public bidding laws are designed to
5876prevent a firm from gaining a competitive advantage over other
5886vendors or bidders in seeking to obtain the subject work, not in
5898depriving itself of the work. Moreover, this purported fear by
5908the Agency does not appear significant in the face of the fact
5920that it allowed another bidder this purported advantage of
5929withdrawing its bid without penalty.
593445. Close's use of the original bid form was clearly a
5945non-judgmental mistake, as identified and defined in the
5953Agency's Procurement Manual. The mistake was apparent on the
5962face of the bid, which not only expressly identified and agreed
5973to the terms of both addenda, but which must be construed by the
5986District as if all addenda are received and acknowledged by the
5997bidder, in submitting its bid.
600246. The District did not follow the clear terms of Article
601319.03 of the RFB in construing the bid. This is especially the
6025case in light of the express agreement to comply with Addendum
6036No. Two contained in Close's submittal. The District did not
6046follow its own policies contained in Chapter 5 of its
6056Procurement Manual and exercise the opportunity to verify
6064Close's bid as to the obvious mistake, and afford an opportunity
6075to correct that non-judgmental mistake. That mistake and the
6084simple verification question of whether the bid price included
6093the discretionary cost allowance, would not have affected the
6102price of Close's bid nor Close's relative competitive position
6111vis-à-vis any other bidders, by conferring it any competitive
6120advantage. A simple yes or no question and answer procedure
6130would have sufficed.
613347. Contrary to the testimony of the District's witnesses,
6142the Procurement Manual expressly permits a bidder to furnish
6151additional information to support verification of its bid in the
6161face of a mistake. As stated above, another bidder was indeed
6172given this opportunity. Under that policy, the bidder is not
6182allowed to alter or supplement its bid and there was no effort
6194or intent to do so. If the simple opportunity to clarify the
6206mistake and verify the bid had been taken, this proceeding might
6217have been unnecessary.
622048. In summary, after conduct of this de novo proceeding,
6230the preponderant, persuasive evidence shows that, if the
6238District's position and action persisted through final order, it
6247would be clearly erroneous by its failure to apply the
6257interpretive presumptions in Article 19.03 of the RFB and in
6267failing to apply the bid verification process as delineated
6276above. That would also be the case if it made a legal
6288determination that, although the Petitioner agreed to all terms
6297of all bid documents, including Addendum No. Two, that as to the
6309cost allowance matter and the use of the original bid form, the
6321bid was non-responsive. By allowing Cone and Graham to submit
6331additional information after the bids were opened, in its
6340verification process, and ultimately allowing it to withdraw its
6349bid without sacrificing its bid bond, while denying such an
6359opportunity to Close, under the above-found circumstances, the
6367District would be acting arbitrarily. It would also be acting
6377in a manner "contrary to competition" by allowing such a
6387technical mistake, which did not affect the price of Close's
6397bid, to result in denying the work to a bidder which was a
6410substantial amount cheaper, by $146,615.00, than the price
6419proposed by the bidder initially chosen by the Agency.
642849. Thus Close has established by preponderant, persuasive
6436evidence that the District's proposed award to Worth would be
6446clearly erroneous, contrary to competition, and arbitrary, as
6454those terms are defined herein and in the decisional law cited
6465by the parties. The bid submitted by Close was thus responsive,
6476responsible, and was the lowest bid of the remaining bidders.
6486RECOMMENDATION
6487Having considered the foregoing Findings of Fact,
6494conclusions of law, the evidence of record, the candor and
6504demeanor of the witnesses, and the pleadings and arguments of
6514the parties, it is, therefore,
6519RECOMMENDED that a Final Order be entered by the South
6529Florida Water Management District, awarding the subject contract
6537for RFB 6000000262 to the Petitioner herein, Close Construction,
6546Inc.
6547DONE AND ENTERED this 5th day of January, 2010, in
6557Tallahassee, Leon County, Florida.
6561S
6562P. MICHAEL RUFF
6565Administrative Law Judge
6568Division of Administrative Hearings
6572The DeSoto Building
65751230 Apalachee Parkway
6578Tallahassee, Florida 32399-3060
6581(850) 488-9675
6583Fax Filing (850) 921-6847
6587www.doah.state.fl.us
6588Filed with the Clerk of the
6594Division of Administrative Hearings
6598this 5th day of January, 2010.
6604ENDNOTE
66051 / See , e.g. , Warren Building Company, Inc. v. Dept. of Military
6617Affairs , page 8-9, Case No. 08-2369BID (DOAH, August 20, 2008).
6627In that case it was determined that a low bidder's cost savings
6639in preparing its bid, by failing to certify that it had visited
6651the project site in preparing its bid, would only change the
6662relative competitive positions of the two lowest bidders if the
6672amount of any such cost savings equaled or exceeded the
6682difference between the two bids.
6687COPIES FURNISHED :
6690Josef M. Fiala, Esquire
6694South Florida Water Management District
66993301 Gun Club Road, MSC 1410
6705West Palm Beach, Florida 33406
6710Andrew J. Baumann, Esquire
6714Lewis, Longman and Walker, P.A.
67191700 Palm Beach Lakes Boulevard, Suite 1000
6726West Palm Beach, Florida 33401-2006
6731Joseph W. Lawrence, II, Esquire
6736Robert L. Frye, Esquire
6740Vezina, Lawrence & Piscitelli
6744The Museum Building
6747300 Southwest 1st Avenue, Suite 150
6753Fort Lauderdale, Florida 33301
6757Carol Ann Wehle, Executive Director
6762South Florida Water Management District
67673301 Gun Club Road
6771West Palm Beach, Florida 33416-4680
6776NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6782All parties have the right to submit written exceptions within
679210 days from the date of this Recommended Order. Any exceptions
6803to this Recommended Order should be filed with the agency that
6814will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/13/2011
- Proceedings: BY ORDER OF THE COURT: Ordered that appellant's motion filed May 19, 2011, for rehearing or clarification by written opinion is hereby denied filed.
- PDF:
- Date: 06/20/2011
- Proceedings: BY ORDER OF THE COURT: Appellant's motion filed May 19, 2011, for rehearing or clarification by written opinion is hereby denied filed.
- PDF:
- Date: 06/10/2011
- Proceedings: BY ORDER OF THE COURT: Ordered that pursuant to the June 2, 2011, stipulation for substitution of counsel is granted filed.
- PDF:
- Date: 05/06/2011
- Proceedings: BY ORDER OF THE COURT: Appellant's motion filed September 13, 2010, for attorney fees is hereby denied filed.
- PDF:
- Date: 02/07/2011
- Proceedings: BY ORER OF THE COURT: Appellant's motion for review of stay order is hereby dismissed filed.
- PDF:
- Date: 08/30/2010
- Proceedings: BY ORDER OF THE COURT: Ordered that appellant's stipulated motion filed August 26, 2010, to amend initial brief is granted filed.
- PDF:
- Date: 08/13/2010
- Proceedings: BY ORDER OF THE COURT: Appellee's motion filed August 9, 2010, for extension of time is granted filed.
- PDF:
- Date: 08/05/2010
- Proceedings: BY ORDER OF THE COURT: Devin R. Maxwell shall file the CD-ROM in the lower tribunal within (10) days from the date of this order filed.
- PDF:
- Date: 06/30/2010
- Proceedings: BY ORDER OF THE COURT: appellant's amended motion to supplement the record is granted filed.
- PDF:
- Date: 06/25/2010
- Proceedings: BY ORDER OF THE COURT: Appellee's suggestion of mootness filed June 7, 2010, is hereby denied filed.
- PDF:
- Date: 06/17/2010
- Proceedings: BY ORDER OF THE COURT: Appellant's motion filed June 8, 2010, to supplement the record is hereby denied without prejudice filed.
- PDF:
- Date: 06/16/2010
- Proceedings: BY ORDER OF THE COURT: Appellee's motin filed June 7, 2010, to show cause as to why this appeal is not moot is hereby stricken as unauthorized; further ordered that appellee's motion filed June 7, 2010, for stay is hereby denied filed.
- PDF:
- Date: 01/05/2010
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 11/16/2009
- Proceedings: Intervener (sic) Worth Contracting, Inc.'s Notice Adopting South Florida Water Management District's Proposed Recommended Order filed.
- PDF:
- Date: 11/16/2009
- Proceedings: Petitioner, Close Construction, Inc.'s Proposed Recommended Order filed.
- PDF:
- Date: 11/16/2009
- Proceedings: Respondent South Florida Water Management District's Proposed Recommended Order filed.
- Date: 11/06/2009
- Proceedings: Transcript filed.
- PDF:
- Date: 11/05/2009
- Proceedings: Letter to Judge Ruff from J. Fiala regarding new submission date for Proposed Recommended Orders filed.
- Date: 10/19/2009
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 10/16/2009
- Proceedings: South Florida Water Management District's Motion to Take Official Recognition filed.
- PDF:
- Date: 10/16/2009
- Proceedings: Letter to Judge Ruff from A. Baumann enclosing additional exhibits (exhibits not available for viewing) filed.
- PDF:
- Date: 10/16/2009
- Proceedings: Letter to Judge Ruff from J. Fiala enclosing Respondent's Exhibits (exhibits not available for viewing) filed.
- PDF:
- Date: 10/15/2009
- Proceedings: Notice of Pre-filing Respondents Exhibits (exhibits not attached) filed.
- PDF:
- Date: 10/15/2009
- Proceedings: Letter to Judge Ruff from A. Baumann enclosing joint exhibit list (exhibits not available for viewing) filed.
- PDF:
- Date: 10/13/2009
- Proceedings: South Florida Water Management District's Notice of Taking Deposition (Andrew Hall) filed.
- PDF:
- Date: 10/12/2009
- Proceedings: Respondent, South Florida Water Management District's Response to Petitioners First Request for Production filed.
- PDF:
- Date: 10/12/2009
- Proceedings: Respondent, South Florida Water Management District's Notice of Filing Answers to Petitioner's First Set of Interrogatories filed.
- PDF:
- Date: 10/07/2009
- Proceedings: Petitioner's Amended Notice of Service of First Set of Interrogatories and First Request for Production of Documents Directed to Respondent South Florida Water Management District filed.
- PDF:
- Date: 10/07/2009
- Proceedings: South Florida Water Management District's Notice of Taking Deposition (Chris Rossi) filed.
- PDF:
- Date: 10/06/2009
- Proceedings: Petitioner's Notice of Service of First Set of Interrogatories Directed to Respondent South Florida Water Management District filed.
- PDF:
- Date: 10/06/2009
- Proceedings: Petitioner's First Request for Production to Respondent, South Florida Water Management District filed.
- PDF:
- Date: 10/06/2009
- Proceedings: Petitioner's Notice of Service of Answers to Respondent's First Set of Interrogatories filed.
- PDF:
- Date: 10/06/2009
- Proceedings: Petitioner's Response to Respondent's First Request for Production filed.
- PDF:
- Date: 10/01/2009
- Proceedings: Respondent, South Florida Water Management District's Notice of Service of First Set of Interrogatories to Close Construction, Inc. filed.
- PDF:
- Date: 10/01/2009
- Proceedings: Respondent, South Florida Water Management District's Notice of Service of First Request for Production to Close Construction, Inc. filed.
- PDF:
- Date: 09/30/2009
- Proceedings: South Florida Water Management District's Notice of Taking Deposition (2) filed.
- PDF:
- Date: 09/29/2009
- Proceedings: Notice of Hearing by Video Teleconference (hearing set for October 19, 2009; 10:00 a.m.; West Palm Beach and Tallahassee, FL).
- PDF:
- Date: 09/14/2009
- Proceedings: South Florida Water Management Districts Solicitation Addendum (2) filed.
- PDF:
- Date: 09/14/2009
- Proceedings: South Florida Water Management Districts Solicitation Addendum (1) filed.
Case Information
- Judge:
- P. MICHAEL RUFF
- Date Filed:
- 09/14/2009
- Date Assignment:
- 09/17/2009
- Last Docket Entry:
- 07/13/2011
- Location:
- West Palm Beach, Florida
- District:
- Southern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
Andrew J. Baumann, Esquire
Address of Record -
Josef M. Fiala, Esquire
Address of Record -
Joseph W Lawrence, II, Esquire
Address of Record