10-007669BID American Lighting And Signalization vs. Department Of Transportation
 Status: Closed
Recommended Order on Wednesday, December 1, 2010.


View Dockets  
Summary: Petitioner proved that Intervenor's bid was non-responsive.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8AMERICAN LIGHTING )

11AND SIGNALIZATION, )

14)

15Petitioner, )

17)

18vs. ) Case No. 10 - 7669BID

25)

26DEPARTMENT OF TRANSPORTATION, )

30)

31Respondent, )

33)

34and )

36)

37MILLER ELECTRIC COMPANY, )

41)

42Inte rvenor. )

45)

46RECOMMENDED ORDER

48A formal hearing was conducted in this case on September 16,

592010, and October 1, 2010, in Tallahassee, Florida, before

68Suzanne F. Hoo d, Administrative Law Judge with the Division of

79Administrative Hearings.

81APPEARANCES

82For Petitioner: Karen D. Walker, Esquire

88Holland and Knight

91315 South Calhoun Street, Suite 600

97Tallahassee, Flo rida 32301

101For Respondent: C. Denise Johnson, Esquire

107Department of Transportation

110Haydon Burns Building, Mail Station 58

116605 Suwannee Street

119Tallahassee, Florida 32399 - 0450

124For Intervenor: Charles R. Walker, Jr., Esquire

131Regan Zebouni and Walker, P.A.

1369905 Old St. Augustine Road

141Jacksonville, Florida 32257

144STATEMENT OF THE ISSUE

148The issue is whether Respondent Florida Dep artment of

157TransportationÓ s (the Department or FDOT) determination that

165Intervenor Miller Electric Company (Miller) is a responsive

173design - build proposer was clearly erroneous, contrary to

182competition, or arbitrary and capricious.

187PRELIMINARY STATEMENT

189B y formal written protest dated July 2, 2010, Petitioner

199American Lighting and Signalization, Inc. (ALS) protested FDOT's

207intended decision to award a design - build contract to Miller.

218The contract involves the design and construction of the SR 5

229(U.S. 1) I ntelligent Transportation System (ITS) from SR 9 north

240to Wister Street, Duval County, Florida, Contract Number E2077

249(Project).

250The Department referred this matter to the Division of

259Administrative Hearings on August 17, 2010. A Notice of Hearing

269date d August 18, 2010, scheduled the hearing for September 16,

2802010.

281On August 26, 2010, Miller filed its Petition to Intervene.

291An Order Granting Petition to Intervene was entered on

300September 1, 2010.

303The hearing commenced on September 16, 2010, as sc heduled.

313However, the matter could not be concluded in the time allotted.

324Therefore, the case was continued to October 1, 2010.

333During the hearing, Stipulated Exhibits 1 - 21 were received

343into evidence.

345AL S called five witnesses. ALS offered seven exhibits that

355were accepted as evidence.

359The Department called two witnesses. The Department offered

367one exhibit that was accepted as evidence.

374Miller called two witnesses. Miller offered one exhibit

382that was received into evidence.

387The transcript s of the first and second day of the hearing

399were filed on September 30, 2010, and October 14, 2010,

409respectively. The parties filed their Proposed Recommended

416Orders on October 28, 2010.

421Except as otherwise noted, all references hereinafter shall

429be t o Florida Statutes 2010.

435FINDINGS OF FACT

4381. This protest arises out of FDOT's April 19, 2010,

448request for a design - build proposal (RFP) relating to the Project

460referenced above. The RFP requires the services performed by the

470Proposer to be in complian ce with all applicable manuals and

481guidelines. FDOT issued three addenda to the RFP, the last of

492which (Addendum #3) was issued two days prior to the advertised

503proposal submission deadline.

5062. The specific services were outlined as follows in the

516RFP :

518The ITS Project (Project) consists of the

525installation of ten (10) arterial dynamic

531message signs (ADMS), interconnection with

536the existing FDOT District 2 and City of

544Jacksonville fiber optic networks (FON),

549installation of a closed - circuit televisio n

557(CCTV) camera subsystem with eighteen (18)

563CCTV cameras, and the upgrade of eighteen

570(18) existing signal cabinets for central

576command and communication. The Project shall

582also include all ancillary components and

588device configuration adjustments needed to

593connect and operate a complete ITS.

5993. The RFP is a low bid design - build technically acceptable

611procurement. The RFP states that after the public bid opening:

621The FDOT shall open all bids received at a

630public bid opening on the date found in

638Se ction II of this document. The FDOT

646Technical Review Committee will review the

652Technical Proposal of the lowest bidder. The

659Technical Review Committee will then

664establish if the Technical Proposal is

670responsive or non - responsive based on the

678criteria des cribed in the document. If the

686proposal is responsive, that Proposer will be

693awarded the project. If the proposal is

700found to be non - responsive, the FDOT

708Technical Review Committee will review the

714Technical Proposal of the next lowest bidder

721and establis h if the Technical Proposal is

729responsive or non - responsive based on the

737criteria described in this RFP and so on.

7454. In a low bid design - build procurement, price is

756particularly important because bidders are eliminated solely on

764price. In this RFP, bi dders were to base their technical and

776price proposals on the RFP package as well as the addenda and

788question and answers issued by FDOT. In Section III, Subsection

798H, the RFP states as follows in relevant part:

807The Department may waive minor informali ties

814or irregularities in proposals received where

820such is merely a matter of form and not

829substance, and the correction or waiver of

836which is not prejudicial to other Proposers.

843Minor irregularities are defined as those

849that will not have an adverse effe ct on the

859Department's interest and will not affect the

866price of the Proposals by giving a Proposer

874an advantage or benefit not enjoyed by other

882proposers.

8831. Any design submittals that are part of a

892proposal shall be deemed preliminary only.

8982. Prel iminary design submittals may vary

905from the requirements of the Design and

912Construction Criteria. The Department, at

917their discretion, may elect to consider those

924variations in awarding points to the proposal

931rather than rejecting the entire proposal.

9373. In no event will any such elections by

946the Department be deemed to be a waiver of

955the Design and Constructions Criteria.

9604. The Proposer who is selected for the

968project will be required to fully comply with

976the Design and Construction Criteria for the

983price bid, regardless that the proposal may

990have been based on a variation from the

998Design and Construction Criteria.

10025 . In Section III, Subsection I, the RFP addressed

1012modification of proposals. Proposers could modify previously

1019submitted proposals at any time prior to the proposal due date.

10306 . The Department opened eight proposals on June 9, 2010.

1041Miller was the low bidder with a total price of $1,549,875.00.

1054ALS was the second lowest bid with a total price of

1065$1,564,189.00, a difference of $1 4,314.00.

10747 . MillerÓ s proposal was submitted to the Department's

1084Technical Review Committee (TRC) for a determination whether its

1093Technical Proposal was responsive or non - responsive. The TRC was

1104comprised of the following members of FDOT's staff: (a) John

1114Kell, ITS Project Manager; (b) Jerry Ausher, P.E., Traffic

1123Operation Engineer; and (c) Amy Williams, P.E., Senior Project

1132Manager. Kathy Thomas, P.E., District Two Consultant Design

1140Engineer, was not a member of the TRC but provided guidance to

1152it.

11538 . The Department has adopted Design Build Guidelines (the

1163guidelines) that address the role of the TRC in low bid design -

1176build procurements. In Section 4.13, the guidelines state that

1185the "TRC shall review the design concepts and preliminary designs

1195of the lowest bidder proposed in order to assess the

1205resp onsiveness of the lowest bidderÓ s technical proposal compared

1215to the Design and Construction Criteria Package." The guidelines

1224also state as follows in pertinent part:

1231In the event the lowest bidd er's technical

1239proposal is found to be non - responsive, the

1248TRC will then review the next lowest bidder's

1256technical proposal to determine its

1261responsiveness . . . A Bid Proposal is

1269considered non - responsive if it does not

1277contain all of the required informa tion and

1285level of detail, or is non - compliant with the

1295design and construction criteria defined in

1301the RFP. It may be appropriate for the

1309Department to contact the non - responsive firm

1317to discuss/clarify its concerns prior to

1323moving on to the next lowest b idder.

1331However, once determined that the low bidder

1338is non - responsive, the process shall continue

1346until the lowest bidder having a responsive

1353proposal is found.

13569 . The Department has also adopted a Design - Build

1367Procurement and Administration Policy ( the policy) which

1375specifically references the guidelines and contains language

1382similar to the guidelines with respect to the role of the TRC.

1394The policy authorizes the Department to contact a firm to discuss

1405or clarify its concerns before moving on to the next lowest

1416bidder.

141710 . Sometime before the Department issued the RFP, it had a

1429meeting with some of its staff, including Ms. Thomas. During the

1440meeting, the Department's staff was advised that they were

1449scrutinizing technical proposals submitted by low bidders too

1457thoroughly. The new philosophy was for TRCs to ask clarifying

1467questions of the low bidder if they had concerns and if those

1479questions were not answered correctly, to find the low bidder

1489non - responsive.

149211 . The TRC in this case met for the first time on June 15,

15072010. During that meeting, the TRC developed a list o f concerns

1519they had with MillerÓ s proposal and su bmitted those to the

1531DepartmentÓ s procurement staff.

153512 . The Department forwarded three questions to Miller.

1544First, the T RC questioned whether Miller intended to reference

"1554mast arm" structures or cantilever sign structures in a section

1564of the proposal. Second, th e TRC questioned whether MillerÓ s bid

1576included the installation of new conduit at Shad Road as opposed

1587to using the less expensive existing conduit. Third, th e TRC

1598questioned whether MillerÓ s proposal included the deletion of the

1608wireless assembly at Shad Road.

161313 . On or about June 16, 2010, Kirk Townsend, MillerÓ s

1625Senior Project Manager, responded to all three questions. The

1634next day, the TRC met and voted unanimously to recommend the

1645award to Miller.

164814 . The TRC did not look at each requirement in the RFP.

1661Instead, the TRC looked at the overall intent of MillerÓ s

1672technical proposal.

167415 . Mr. Kell, a m ember of the TRC, stated at hearing that

1688the procurement process for this RFP was different from any other

1699procurement that he has participated in and that he did not make

1711a specific responsiveness determination. Mr. Kell also stated

1719that Miller's proposa l did not contain all of the information

1730required by the RFP and that under the guidelines and policy

1741manuals, the proposal would have been deemed non - responsive.

1751However, under the terms of the RFP, Mr. Kell found that there

1763was sufficient information in MillerÓ s preliminary plans to

1772understand how Miller would prosecute the work to his

1781satisfaction.

178216 . Mr. Ausher, another member of the TRC, testified at the

1794hearing. According to Mr. Ausher, the essential items in the RFP

1805were included in MillerÓ s tec hnical proposal. Mr. Ausher was of

1817the opinion that the role of the TRC was to review the

1829requirements of the RFP, review the proposal, and verify that the

1840proposal met the intent of the RFP.

184717 . Ms. Williams was the third member of the TRC. She

1859evalua ted Miller Ó s proposal and found it to be responsive. She

1872did not believe that any additional clarificati on was needed, but

1883heard MillerÓ s response to the three clarifying questions and

1893found the response satisfactory.

189718 . On June 22, 2010, the Departm ent posted its notice of

1910intent to award the contract to Miller.

191719 . Whe n ALS learned of the DepartmentÓ s intended contract

1929award to Miller, ALS requested a copy of MillerÓ s technical

1940proposal from the Department. ALS then reviewed the proposal and

1950id entified a number of issues that ALS believed would render the

1962Miller proposal non - responsive.

196720 . James Hardiman is Vice President of ALS. Mr. Hard iman

1979contacted Jane Jones, FDOTÓ s Purchasing Director, and asked if

1989she would meet with him to discuss issues that ALS had with the

2002intended contract.

200421 . Ms. Jones met with Mr. Hardiman after June 22, 2010,

2016but prior to the protest period running on June 25, 2010.

2027Ms. Jones made a list of ALSÓ concer ns and provided the list to

2041Ms. Thomas by e - mail.

204722 . Ms. Thomas provided a revised list of issues to

2058Ms. Jones with instructions to question Miller regarding the

2067revised issue list. Ms. ThomasÓ revised list reflected only

2076those questions that she felt needed to be asked of Miller.

208723 . Ms. Jones se nt an e - mail to Mr. Townsend, Miller Ó s

2103Senior Project Manager on June 24, 2010. The e - mail stated that

2116the Department would like to clarify certain contract

2124requirements. The e - mail asked Miller to verify that it would

2136complete the scope in the RFP for t he price bid and within the

2150contract duration. The e - mail requested Miller to provide the

2161required listing of categories for the Schedule of Values.

217024 . On the evening of June 24, 2010, Mr. Townsend responded

2182by e - mail, stating that Miller would compl ete the scope req uired

2196by the RFP within the 360 - day contract duration. The following

2208morning, Mr. Townsend sent an e - mail to Ms. Jones, providing the

"2221preliminary schedule of values as required by the RFP."

223025 . The clarifications from Miller, as a re sult of the

2242allegations by Mr. Hardiman, were not received or considered by

2252the TRC. The TRC did not meet again following the posting of the

2265intended award to Miller.

226926 . There is nothing in the RFP, the guidelines or the

2281policy that authorizes the De partment to ask clarifying questions

2291of a bidder or to ask the bidder to provide additional

2302information not included in the technical proposal after the

2311intended award has been posted and prior to the protest period

2322running. It concerned Ms. Jones that th e Department was asking

2333Miller questions about its proposal during this time period.

234227 . On July 2, 2010, ALS filed its formal written protest

2354with the Department. The protest alleg es in relevant part that

2365MillerÓ s technical proposal was non - responsiv e for the following

2377reasons: (a) MillerÓ s preliminary schedule failed to provide 45

2387days for Department shop drawing review; (b) Miller failed to

2397provide splice boxes at all fiber optic splice field locations;

2407(c) Miller failed to include a preliminary li sting of categories

2418for the Schedule of Values; (d) Miller failed to comply with the

2430requirements for guardails ; and (e) Miller did not show a 60 -

2442month warranty period for the Ethernet Field Switches.

245028 . To support its protest at hearing, ALS relied h eavily

2462on a strict interpretation of RFP language requiring a technical

2472proposal to contain all required information and level of detail

2482in order to be responsive. However, if that language was

2492strictly enforced, the Department could never award a contrac t.

250229 . With a design - build project there is more than one way

2516to build something. The technical proposals submissions are

2524preliminary in nature. The RFP would be the controlling document

2534if there is an unacceptable variance in the proposal.

2543Schedule of Values

254630 . ALS has complained that Miller failed to provide the

"2557preliminary listing of categories for the Schedule of Values"

2566with its technical proposal. Typically, the Department does not

2575request a Schedule of Values in a design - build proposal.

258631 . It is true that MillerÓ s original proposal did not

2598include the Schedule of Values. In Section V, Subsection P, the

2609RFP states the "[t]he Proposer shall submit a preliminary listing

2619of categories for the Schedule of Values with the Technical

2629Propos al. No price information shall be provided in the

2639Technical Proposal."

264132 . A Schedule of Values usually is the way a contractor

2653breaks down items for payment. It is a tool that the Department

2665uses to make sure that a contractor does not front load pa yments

2678on a job. In this case, the Department wanted to see a

2690preliminary listing of the categories of the Schedule of Values

2700so that it would know what the pay items would be and that they

2714would cover the contract.

271833 . Mr. Kell, as a member of the TR C, testified on direct

2732examination that the use of the word "shall" in the RFP made the

2745requirement for a Schedule of Values a mandatory requirement.

2754Mr. Kell also testified that under the terms of the guidelines

2765and policy manuals, the failure to include the Schedule o f Values

2777would mean that MillerÓ s proposal was non - responsive.

278734 . Mr. Kell testified that he helped develop the RFP but

2799did not know why the Department used the word "shall" in

2810requiring a Schedule of Values. His testimony that the wor d

"2821shall" was included in the RFP only because the Department used

2832a generic form to write the RFP is not persuasive.

284235 . Dale Cody is Senior Vice President over production for

2853Metric Engineer ing. Mr. Cody served as MillerÓ s proposal

2863designer. At the hearing, Mr. Cody admitted th at the plans

2874included in MillerÓ s proposal were not designed to show all of

2886the required parts of the RFP.

289236 . The most persuasive evidence indicates that the TRC

2902overlooked the missi ng Schedule of Values in MillerÓ s propo sal.

2914Allowing Miller to provide the schedule after announcing the

2923contract award permitted Miller to supplement its proposal.

293137 . In this case, the omission of the Schedule of Values

2943had no affect on the pricing of the project. During the hearing,

2955Ph il Karaganis, Supervisor for ALS, admitted that the failure to

2966timely submit a Schedule of Values had no price impact on the

2978bid. However, the absence of the mandatory schedule deprived the

2988Department of having knowledge of the proposed pay items and

2998know ledge that they would cover the contract.

3006Cantilevered Sign Supports

300938 . ALS contends that MillerÓ s technical proposal is non -

3021responsive based on a typographic al error in one place of

3032MillerÓ s proposal that references mast arm structures instead of

3042tr icord cantilever structures. MillerÓ s proposal clearly

3050included tricord cantilever sign supports. Several areas of the

3059technic al proposal demonstrated MillerÓ s understanding that

3067cantilevered sign supports were required. This issue was

3075resolved pursuant to the clarifying questions asked by the

3084Department before making the award.

3089Preliminary Schedule

309139 . ALS asserts that MillerÓ s proposal is non - responsive

3103based on alleged omission in the preliminary schedule submitted

3112with MillerÓ s technical proposal. The schedule provided with the

3122technical proposal is preliminary and simply shows that the

3131proposer possesses a basic understanding of the requirements of

3140the RFP.

314240 . The RFP required a construction sche dule to be included

3154in a bidderÓ s technical pr oposal with a maximum contract duration

3166of no more than 360 calendar days. Failure to complete the

3177project in 360 days would n egatively impact the DepartmentÓ s

3188interest and increase the cost of the project.

319641 . In Section VI, Subsection I, the RFP ini tially stated

3208as follows:

3210The Proposer must account for a 10 working

3218day shop drawing review time by the

3225Department in its schedule.

322942 . On June 7, 2010, the Department issued Addendum #3,

3240which changed the time to 45 working days for the Department Ó s

3253shop drawing review time. The addendum did not extend the

3263maximum contract duration of 360 days.

326943 . MillerÓ s proposal provides for only 14 calendar days

3280for review of shop drawings. Miller Ó s proposal identifies review

3291and approval of shop dra wing as a critical item by showing a red

"3305critical bar" next to this item on the schedule.

331444 . Despite showing only 14 days for the DepartmentÓ s

3325review and ap proval of shop drawings, MillerÓ s schedule would not

3337have to be significantly revised in order to complete the project

3348in 360 days. Miller can adjust its activities during the 90

3359percent design phase by overlapping the shop drawing review with

3369the plans development period. The scheduling can be accomplished

3378by sliding certain activities and using "negative lag" to allow

3388for shop drawing review during the plans development period.

339745 . Mr. Ausher, as a member of the TRC, testified that he

3410reviewed Miller's preliminary schedule and was satisfied that

3418Miller could meet the 45 - day shop drawing revi ew and approval

3431requirement. Ms. Ausher made this determination by no ting the

344150 - day float in MillerÓ s schedule with respect to shop drawing

3454submittal.

345546 . In contrast, ALS Ó proposal expressly provided for a 45 -

3468day period as required by Addendum #3. After receiving the

3478addendum, ALS adjusted its schedule to account for the 31

3488additional days.

349047 . ALS also adjusted its price to add additional dollars

3501for overtime, equipment costs, and possible night work that it

3511believed would be needed to accommod ate the additional review and

3522approval time. If ALS had not been required to include 45 days

3534for Department review of sho p drawings in its schedule, ALSÓ

3545price would have been approximately $20,000 less. On the other

3556hand, there is no persuasive evidenc e that MillerÓ s accommodation

3567of additional time for shop drawing review and approval in the

3578design phase w ould modify the price of MillerÓ s proposal or

3590impact the bid price.

3594New Conduit at Shad Road

359948 . ALS complained that MillerÓ s proposal did not ac count

3611for new conduit at Shad Road as provided in Addendum #1 to the

3624RFP. However, upon receipt of the addendum, Miller adjusted its

3634price proposal to account for new conduit at Shad Road. Miller

3645also confirmed its intent to install the new conduit in re sponse

3657to the Department's clarifying questions prior to the award of

3667the contract.

3669Splice Boxes

367149 . ALS complained that MillerÓ s technical proposal

3680included pay item references to pull boxes instead of splice

3690boxes. The R F P required a proposer to "f urnish and install

3703splice boxes at all fiber optic field locations as shown on the

3715plans and at other locations as required." The plans that were

3726part of the RFP specifications require splice boxes at four

3736locations.

373750 . A splice box is different fro m a pull box. A splice

3751box is larger, deeper, and more expensive than a pull box.

376251 . MillerÓ s plans include references to Pay Item No. 783 -

37755 - 1 at locations where the RFP calls for splice boxes. That pay

3789item is for a pull box. Pay Item No. 783 - 6 - 1 is the pay item for

3808a splice box.

381152. However, the plan sheets submitted by Miller clearly

3820identify the utili zation of splice boxes. MillerÓ s failure to

3831use specific language referencing splice boxes was due to a

3841technician oversight. Most important l y, MillerÓ s Price Proposal

3851included the use of splice boxes. The typographical error in

3861omitting specific references to splice boxes in the technical

3870proposal had no impact on the method used to arrive at MillerÓ s

3883Price Proposal.

3885Guard r ails

388853 . ALS c omplained that Miller failed to provide guard r ails

3901at locations required by the RFP. The RFP states that guard r ails

3914will only be permitted upon the writt en approval of the

3925Department.

392654 . Chapter 2 of the Department's Plans Preparations Manual

3936(PPM) pr ovides that if a sign has to be placed in the clear zone,

3951it must be protected with a barrier. Based on the plans included

3963in the RFP, two of the Arterial Dynamic Messaging Sign (ADMS)

3974structures for the Project have to be placed in the clear zone

3986due to overhead power lines in the area.

399455 . Chapter 4 of the PPM addresses roadside safety. This

4005chapter of the PPM provided that a non - breakaway sign, such as

4018the ADMS signs required by the Project, are normally considered

4028more hazardous than a roadside ba rrier, such as a guard r ails .

4042MillerÓ s proposal did not include any guard r ails and was priced

4055accordingly. Including the guard r ails added approximately

4063$18,000.00 to ALSÓ price proposal.

406956 . MillerÓ s decision not to include guard r ails was an

4082engineeri ng determination based on the application of the

4091Resurfacing, Restoration and Rehabilitation (RRR) criteria in

4098Chapter 25 of the PPM. The RRR criteria provide for more relaxed

4110clear zone requirements and would eliminate the requirement for a

4120guard r ails in this case.

412657 . Ch apter 2 of the PPM states that Ð design criteria for

4140Resurfacing, Restoration, and Rehabilitation are presented in

4147Chapter 25 of this volume and are applicable only on programmed

4158RRR projects. Ñ The Project here has not been programmed as and

4170is not an RRR project. Further, Chapter 25 of the PPM states

4182that it does not apply to strategic intermodal systems (SIS) or

4193to new construction. The instant Project is both.

420158 . In this case, Miller presented persuasive evidence that

4211the PPM is an engin eering guide to design. MillerÓ s design

4223engineer, Mr. Cody, pointed out that sections of the PPM

4233establish that RRR criteria can be used on projects not

4243specifically designated as RRR. In determining that guard r ail s

4254were not required, Mr. Cod y considered Chapters 2, 7, and 25 of

4267the PPM. Based on the only engineering testimony provided, the

4277Design - Build Criteria Requirements do not require the

4286installation of guard r ail s.

4292Warranty

429359. A table in MillerÓ s technical proposal relating to

4303war ranties included a typographical error referencing a 36 - month

4314warranty period instead of the specified 60 - month period for

4325Ethernet Swit ches. That same page of MillerÓ s proposal included

4336language clar ifying and demonstrating MillerÓ s knowledge that a

434660 - m onth warranty was required for the switches. The error had

4359no price impact on the bid.

4365ALSÓ Proposal

436760 . ALS alleged in its formal protest that its proposal was

4379fully compliant with the RFP. At hearing, Miller introduced

4388evidence in an attempt to sh ow that ALSÓ proposal was not

4400responsive, and therefore, that ALS had no standin g. FDOT has

4411never reviewed ALSÓ proposal.

441561 . ALSÓ construction schedule does not use the words

"4425operational test." However, the 14 - day operational test is

4435included in th e portion of the ALS schedule entitled Systems

4446Integration. Thus, ALS would not have to revise its construction

4456schedule to include the 14 - day operational test.

446562. ALS Ó construction schedule has no task that

4474specifically accounts for preparation of shop drawings. Even so,

4483there is no persuasive evidence that the failure to include time

4494for preparation of shop drawings would make ALSÓ proposal non -

4505responsive.

450663 . Similarly, although ALS did not specifically identify

4515environmental permit acquisit ion in its proposed schedule, this

4524was included under the heading of "Permitting" in ALSÓ

4533construction schedule inclu ded in its technical proposal.

454164 . ALSÓ proposal does not include pay items for a fiber

4553jumper or Gbic. There is no such pay item beca use the Gbic is

4567part of the Ethernet Switch included in ALSÓ proposal.

4576Additionally, jumpers are covered based on a plan note in the ALS

4588proposal.

458965 . ALSÓ proposal shows a directional bore for the fiber

4600optic conduit and cable, and uses the pay item 555 - 1 - 1 for the

4616directional bore. The proposal also uses a pay item for

4626underground conduit where there is a median.

463366 . Language in the RFP refers to CCTV cameras in MPEG2

4645format. The ALS proposal includes a cut sheet for a CCTV camera

4657that uses MPE G4 encoding, which is a better camera and cost about

4670the same as the camera required in the RFP.

467967 . The evidence relative to ALSÓ proposal shows that it

4690has standing to challenge the cont r act award to Miller. The

4702e vidence presented regarding ALSÓ pro posal does not speak to the

4714responsiveness of ALS Ó proposal as a whole.

4722CONCLUSIONS OF LAW

472568 . The Division of Administrative Hearings has

4733jurisdiction over the parties and the subject matter of this

4743proceeding pursuant to Sections 120.569, 120.57(1), and

4750120.57(3)(f), Florida Statutes.

475369 . ALS has two burdens in this case. First, ALS must

4765demonstrate that its bid was responsive before it can

4774successfully challenge the award of the contract to another

4783proposer. See Intercontinental Properties v. St ate of Florida,

4792Department of Health and Rehabilitative Services , 606 So. 2d 380,

4802384 (Fla. 3d DCA 1992). AlS has met its burden of proving

4814standing to challenge the contract award to Miller.

482270 . The scope of this p roceeding and the nature of ALSÓ

4835sec ond burden is set forth in Section 120.57(3)(f), Florida

4845Statutes, which states as follows in relevant part:

4853In a competitive - procurement protest, other

4860than a rejection of all bids, proposals o r

4869replies, the administrative l aw judge shall

4876conduct a de n ovo proceeding to determine

4884whether the agency's proposed action is

4890contrary to the agency's governing statutes,

4896the agency's rules or policies, or the

4903solicitation specification. The standard of

4908proof for such proceedings shall be whether

4915the proposed ag ency action was clearly

4922erroneous, contrary to competition,

4926arbitrary, or capricious.

492971 . Section 337.11, Florida Statutes, requires the

4937Department to adopt procedures by rule for administering design -

4947build contracts, including rules relating to TRCs . The

4956Department has adopted Florida Administrative Code Rule 14 -

496591.007(4)(b), which states in pertinent part as follows:

4973A technical proposal shall include all

4979information requested in response to the

4985request for proposals.

498872 . The Department has al so adopted the guidelines and

4999policy referenced above in the Findings of Fact that expressly

5009address low bid design - build procurement . In this case, the

5021DepartmentÓ s TRC failed to follow the policies requiring a TRC to

5033find a bid non - responsive if it does not contain all mandatory

5046information and if it is non - compliant with the design and

5058construction criteria defined in the RFP.

506473 . The RFP here requested some preliminary information and

5074allowed the Department to ask clarifying questions before

5082announ cing the award. The RFP allows the Department to waive

5093minor irregularities. It does not allow the Depart to waive or

5104ignore information that is mandatory on its face.

511274 . In Robinson Electrical Co. v. Dade County , 417 So. 2d

51241032, 1034 (Fla. 3d DCA 1982), the court set forth the analysis

5136for determining what constitutes a material variance or

5144irregularity as follows:

5147In determining whether a specific

5152noncompliance constitutes a substantial and

5157hence nonwaivable irregularity, the courts

5162have applied t wo criteria - first, whether

5170the effect of a waiver would be to deprive

5179the [government entity] of its assurance that

5186the contract will be entered into, performed

5193and guaranteed according to its specified

5199requirements, and second, whether it is of

5206such a n ature that its waiver would adversely

5215affect competitive bidding by placing the

5221bidder in a position of advantage over other

5229bidders or by otherwise undermining the

5235common standard of competition.

523975 . MillerÓ s proposal contains a material variation fr om

5250the RFP specifications that the Department could not waive.

5259Specifically, the omission of preliminary listing of the

5267categories for the Schedule of Values was a mandatory requirement

5277t hat the TRC overlooked. MillerÓ s failure to include this

5288informatio n was fatal to the responsiveness of Miller's proposal.

5298In other words, it deprived FDOT of its assurance that the

5309contract will be entered into, performed and guaranteed according

5318to its "specified requirements."

532276 . The fa ilure of the TRC to find Mill erÓ s proposal non -

5338responsive based on the missin g schedule was contrary to FDOTÓ s

5350rules, policies, and/or the solicitation specifications. The

5357Department's contract award to Miller was clearly erroneous,

5365arbitrary and capricious, because the TRC did not r equire all

5376mandatory information to be included in the proposal. Instead,

5385the TR C looked only to whether MillerÓ s technical proposal

5396conformed to the "intent" of the RFP. See Coin Landry Equip. Co.

5408v. The University of West Florida , Case No. 96 - 0962BID ( DOAH

5421July 5, 1996)("The failure of a public entity to follow its own

5434bid specifications is an arbitrary and capricious act and

5443undermines the integrity of the bid process.") .

545277 . In all other respects , it is arguable that the TRC

5464properly waived other mi nor i rregularities in MillersÓ proposal.

5474As to the cantilevered sign supports, construction schedule, new

5483conduit, splice boxes, guardrails, and warranties, the TRC could

5492read the proposal as a whole to find that it was responsive.

5504RECOMMENDATION

5505Based o n the Foregoing Findings of Fact and Conclusions of

5516Law, it is

5519RECOMMENDED:

5520That the Department of Transportation enter a final order

5529rescinding its intended award to Miller, finding Miller Ó s

5539proposal non - responsive, and providing for review of ALSÓ

5549pro posal by FDOTÓ s TRC.

5555DONE AND ENTERED this 1st day of Dec ember , 2010, in

5566Tallahassee, Leon County, Florida.

5570S

5571SUZANNE F. HOOD

5574Administrative Law Judge

5577Division of Administrative Hearings

5581The DeSoto Building

55841230 Apalachee Parkway

5587Tallahassee , Florida 32399 - 3060

5592(850) 488 - 9675

5596Fax Filing (850) 921 - 6847

5602www.doah.state.fl.us

5603Filed with the Clerk of the

5609Division of Administrative Hearings

5613this 1st day of Dec em ber, 2010.

5621COPIES FURNISHED :

5624C. Denise Johnson, Esquire

5628Department of Transportation

5631Haydon Burns Building, Mail Station 58

5637605 Suwannee Street

5640Tallahassee, Florida 32399 - 0450

5645Karen D. Walker, Esquire

5649Holland & Knight, LLP

5653315 South Calhoun Street, Suite 600

5659Tallahassee, Florida 32301

5662Anthony B. Zebouni, Esquire

5666Regan Zebouni & Walker, P.A.

56719905 Old St. Augustine Road, Suite 400

5678Jacksonville, Florida 32257

5681Deanna Hurt, Clerk of Agency Proceedings

5687Department of Transportation

5690Haydon Burns Building, Mail Station 57

5696605 Suwannee Street

5699Tallahassee, Florida 32399 - 0450

5704Stephanie C. Kopel ousos, Secretary

5709Department of Transportation

5712Haydon Burns Building, Mail Station 57

5718605 Suwannee Street

5721Tallahassee, Florida 32399 - 0450

5726Alexis M. Yarbrough, General Counsel

5731Department of Transportation

5734Haydon Burns Building, Mail Station 58

5740605 Suwannee Street

5743Tallahassee, Florida 32399 - 0450

5748NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

5754All parties have the right to submit written exceptions within

576410 days from the date of this recommended order. Any exceptions to

5776this recommended ord er should be filed with the agency that will

5788issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 01/03/2011
Proceedings: (Agency) Final Order filed.
PDF:
Date: 12/30/2010
Proceedings: Agency Final Order
PDF:
Date: 12/01/2010
Proceedings: Recommended Order
PDF:
Date: 12/01/2010
Proceedings: Recommended Order (hearing held September 16 and October 1, 2010). CASE CLOSED.
PDF:
Date: 12/01/2010
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 10/29/2010
Proceedings: Motion to Accept Late Filling of Intervenor's Recommended Order filed.
PDF:
Date: 10/29/2010
Proceedings: Intervenor's Proposed Recommended Order filed.
PDF:
Date: 10/28/2010
Proceedings: Petitioner's Proposed Recommended Order filed.
PDF:
Date: 10/28/2010
Proceedings: Department's Proposed Recommended Order filed.
PDF:
Date: 10/28/2010
Proceedings: Department's Notice of Filing Proposed Recommended Order filed.
Date: 10/14/2010
Proceedings: Transcript of Proceedings Volume I-II (not available for viewing) filed.
Date: 10/01/2010
Proceedings: CASE STATUS: Hearing Held.
Date: 09/30/2010
Proceedings: Transcript of Proceedings Volume I and II (not available for viewing) filed.
PDF:
Date: 09/17/2010
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for October 1, 2010; 9:00 a.m.; Tallahassee, FL).
Date: 09/16/2010
Proceedings: CASE STATUS: Hearing Partially Held; continued to October 1, 2010; 9:00 a.m.; Tallahassee, FL.
PDF:
Date: 09/15/2010
Proceedings: Joint Pre-hearing Stipulation filed.
PDF:
Date: 09/13/2010
Proceedings: Respondent's Answers to Petitioner's First Set of Interrogatories filed.
PDF:
Date: 09/13/2010
Proceedings: Notice of Filing Respondent's Answers to Petitioner's First Set of Interrogatories.
PDF:
Date: 09/09/2010
Proceedings: Petitioner, American Lighting and Signalization, Inc's Notice of Service of Objections and Responses to Respondent, Department of Transportation's First Set of Interrogatories filed.
PDF:
Date: 09/08/2010
Proceedings: Notice of Taking Deposition (Dale Cody, P.E., Lirk Townsend) filed.
PDF:
Date: 09/03/2010
Proceedings: Notice of Taking Deposition (Jane Jones) filed.
PDF:
Date: 09/03/2010
Proceedings: Notice of Serving Respondent, Department of Transportation's, First Set of Interrogatories to Petitioner filed.
PDF:
Date: 09/02/2010
Proceedings: Amended Notice of Taking Deposition (Jerry Ausher, John Kell, Kathy Thomas) filed.
PDF:
Date: 09/02/2010
Proceedings: Amended Notice of Taking Deposition (Any Williams, Richard Moss, Pastsy Elkins) filed.
PDF:
Date: 09/01/2010
Proceedings: Response to Request for Admissions filed.
PDF:
Date: 09/01/2010
Proceedings: Order Granting Petition to Intervene.
PDF:
Date: 08/30/2010
Proceedings: Department's Response to Request for Production filed.
PDF:
Date: 08/30/2010
Proceedings: Respondent's Notice of Serving Answers to Petitioner's First Set of Interrogatories filed.
PDF:
Date: 08/30/2010
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 08/26/2010
Proceedings: Petition to Intervene (of Miller Electric Company) filed.
PDF:
Date: 08/25/2010
Proceedings: American Lighting and Signlization, Inc.'s First Request for Production of Documents to Respondent filed.
PDF:
Date: 08/24/2010
Proceedings: Notice of Taking Depositions (Amy Williams, Richard Moss, and Patsy Elkins) filed.
PDF:
Date: 08/23/2010
Proceedings: Petitioner's, American Lighting and Signalization, Inc., First Request for Admissions to Respondent filed.
PDF:
Date: 08/23/2010
Proceedings: American Lighting and Signalization, Inc.'s First Set of Interrogatories to Respondent filed.
PDF:
Date: 08/18/2010
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 08/18/2010
Proceedings: Notice of Hearing (hearing set for September 16, 2010; 10:00 a.m.; Tallahassee, FL).
PDF:
Date: 08/17/2010
Proceedings: Petition for Written Protest and Petition for Formal Administrative Hearing filed.
PDF:
Date: 08/17/2010
Proceedings: Agency referral filed.

Case Information

Judge:
SUZANNE F. HOOD
Date Filed:
08/17/2010
Date Assignment:
08/17/2010
Last Docket Entry:
01/03/2011
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (3):