10-007772
Department Of Business And Professional Regulation, Construction Industry Licensing Board vs.
Thomas Colan, D/B/A Thom Colan Construction, Inc.
Status: Closed
Recommended Order on Thursday, April 14, 2011.
Recommended Order on Thursday, April 14, 2011.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DEPARTMENT OF BUSINESS AND )
13PROFESSIONAL REGULATION, )
16CONSTRUCTION INDUSTRY )
19LICENSING BOARD , )
22)
23Petitioner , )
25)
26vs. ) Case No. 10 - 7772
33)
34THOMAS COLAN, d/b/a THOM COLAN )
40CONSTRUCTION, INC. , )
43)
44Respondent . )
47)
48RECOMMENDED ORDER
50Pursuant to notice, a final hearing was held in this case
61on February 4, 2011, by video teleconference in Tallahassee and
71Sarasota, Florida, before Administrative La w Judge Elizabeth W.
80McArthur of the Division of Administrative Hearings.
87APPEARANCES
88For Petitioner: Brian P. Coats, Esquire
94Department of Business and
98Professional Regulation
1001940 North Monroe Street , Suite 42
106Tallahassee, Fl orida 32399
110For Respondent: Gregg M. Horowitz, Esquire
116Post Office Box 2927
120Sarasota, Florida 34230
123STATEMENT OF THE ISSUES
127The issues in this case are whether Respondent committed
136the violations alleged in the Administrative Complaint, and , if
145so, what discipline should be imposed.
151PRELIMINARY STATEMENT
153Petitioner, Department of Business and Professional
159Regulation, Construction Industry Licensing Board (Petitioner) ,
165filed a four - count Administrative Complaint against Respondent,
174Thom as Colan, d/b/a Thom Colan Construction, Inc. (Respondent or
184Mr. Colan), a licensed contractor. The Administrative Complaint
192alleged that in carrying out a contract with Kathleen and Robert
203Masten to build a house and pool, Respondent committed
212violations of sections 489.129(1)(g)1. and 3., (1)(m), and
220(1)(l), Florida Statutes (2005). 1/
225Respondent timely requested an administrative hearing to
232contest the allegations in the Administrative Complaint, and the
241matter was referred to the Division of Administra tive Hearings
251(DOAH) for assignment of an Administrative Law Judge to conduct
261the hearing requested by Respondent.
266The final hearing was set for November 15, 2010, in
276accordance with the parties' request. On November 10, 2010,
285Respondent moved for a cont inuance because of a scheduling
295conflict. Petitioner did not oppose the request, and the
304hearing was rescheduled for February 4, 2011.
311The parties entered into a pre - hearing stipulation in which
322they admitted certain facts, which are included in the F ind ings
334of F act below. In addition, by the pre - hearing stipulation,
346Petitioner voluntarily dismissed Count One of the Administrative
354Complaint, which alleged a violation of section 489.129(1)(g)1.
362Remaining in dispute for litigation at the final hearing wer e
373Counts Two through Four, charging violations of section
381489.129(1)(g)3., (1)(m), and (1)(l), respectively.
386At the final hearing, Petitioner presented the testimony of
395Mrs. Masten and Mr. Colan. Petitioner's E xhibits 1 through 19
406and 21 were received in to evidence. Respondent testified on his
417own behalf and presented the testimony of Mrs. Masten.
426Respondent's E xhibits 1 through 3 were received into evidence.
436At the close of the hearing, a transcript was ordered , and
447the parties agreed to file their p roposed recommended orders
457(PRO) within ten days after the filing of the transcript at
468DOAH. The T ranscript was filed on February 24, 2011.
478Petitioner timely filed its PRO on March 7, 2011. On March 16,
4902011, Respondent f iled a motion to allow the late filing of its
503PRO, because counsel for Respondent had failed to properly
512calendar the deadline and had just obtained a copy of the
523T ranscript. Petitioner objected on the grounds that Respondent
532would gain an unfair advantage by being able to respond to
543Pe titioner's submittal, when the uniform rules contemplate
551simultaneous filings. The undersigned issued an O rder allowing
560Respondent additional time to late file its PRO, but affording
570Petitioner the opportunity to supplement its PRO within ten days
580after s ervice of Respondent's filing. Respondent filed its PRO
590by the extended deadline. Petitioner did not supplement its PRO
600within the time allowed, but filed a Notice of Scrivener's Error
611to correct a statutory citation. Both Petitioner and
619Respondent's PR Os, as well as Petitioner's Notice of Scrivener's
629Error, have been considered in the preparation of this
638Recommended Order.
640FINDINGS OF FACT
643Admitted Facts Per Pre - Hearing Stipulation
6501. Petitioner is the state agency charged with regulating
659the practi ce of contracting pursuant to section 20.165 and
669chapters 455 and 489, Florida Statutes.
6752. Respondent is a state - certified building contractor in
685the State of Florida, having been issued license No. CBC 039025.
6963. Respondent was the licensed primary qua lifying agent
705for Thom Colan Construction, Inc. , from June 10, 2004 , to
715September 4, 2008.
7184. On January 10, 2006, Thom Colan Construction, Inc. ,
727entered into a contract with Kathleen and Robert Masten to
737construct a house and pool on property located at 547 Bradenton
748Road, Venice, Florida (the project).
7535. The contract price for the project was $260,000.00.
7636. The project was completed with the issuance of a
773certificate of occupancy.
776Additional Findings of Fact
780Based on the weight and credibility of t he testimony and
791evidence presented, the following additional facts are found:
7997. The contract between Respondent and the Mastens was a
809fixed - price contract. Although the contract price was
818$260,000.00, the Mastens paid a total of $320.394.19 for the
829pr oject. The payments were made by the following methods:
839$49,968.58 was paid by check from the Mastens directly to
850Respondent; Respondent obtained an additional $222,320.71 in
858total bank draws, pursuant to a construction loan that
867authorized Respondent to draw funds directly from the bank for
877the project; and the remaining $48,104.90 was paid by check or
889credit card by the Mastens directly to subcontractors for labor
899and materials provided for the project. Thus, the Mastens paid
909$60,394.19 more than the c ontract price. At issue, and the
921subject of much dispute at the final hearing, was why the
932project exceeded the contract price by over $60,000.00 .
9428. Respondent asserted that the entire amount by which the
952contract price was exceeded was attributable ei ther to changes
962to the contract terms required by the Mastens or to
972circumstances beyond Respondent's control, such as price
979increases by subcontractors. 2/
9839. It was difficult to establish the causes for the price
994increases, in part , because the parties to the contract did not
1005adhere to the formalities called for by the contract. For
1015example, while both witnesses acknowledged that the Mastens
1023requested changes as the project progressed, there was
1031substantial disagreement about the extent of these change s and
1041the cost differential. Unfortunately, there were no written
1049change orders as required by the contract. Written change
1058orders would have documented exactly what was changed and what
1068cost was attributable to the change.
107410. Another problematic area in attempting to pinpoint why
1083the contract price was exceeded was that there was no clear
1094proof of the contract specifications detailing the design
1102features of the house and pool. The written contract described
1112a process of developing "plans" with "specif ications" as to
1122design elements. Initially, the plans would be preliminary,
1130with items designated for buyer selections. The contract
1138contemplated that the buyer would make these selections, which
1147would become part of the plans, and the plans would then b e
1160considered final. Thus, certain buyer selections would be part
1169of the contract. Thereafter, if the buyer wanted to change the
1180final plans and specifications, the buyer would be responsible
1189for the increased costs.
119311. No evidence was presented as to w hat the plans
1204provided with respect to design features and which of those
1214design features provided for buyer selections. Neither the
1222preliminary plans and specifications for the Masten contract,
1230nor the final plans and specifications after buyer selection s,
1240were offered into evidence, and it is unclear whether the
1250process contemplated by the written contract was even followed.
125912. Nonetheless, Mrs. Masten admitted that she requested
1267certain changes, which she acknowledged were not contemplated by
1276the co ntract and were more costly than what the contract
1287contemplated. For example, Mrs. Masten acknowledged that she
1295requested an upgrade in kitchen appliances, increasing the cost
1304by $2,703.55. She also acknowledged that she requested an
1314upgrade in bathroom fixtures, but she was unsure of the cost
1325attributable to the upgrade. Respondent testified that the
1333total cost increase for upgrades requested by Mrs. Masten to
1343plumbing and fixtures was $4,745.42. Mrs. Masten thought that
1353amount was too high; it include d changes claimed by Respondent ,
1364but disputed by Mrs. Masten, such as an upgrade to a hot tub
1377that Mrs. Masten said she did not want but , apparently , was
1388installed.
138913. The circumstances surrounding other apparent changes
1396were in dispute. For example, an expedition , including
1404Mrs. Masten and Respondent , trekked to a tile outlet store in
1415Fort Meyers to pick out tile to use in the shower stall and
1428floors. For the shower stall, Respondent testified that he
"1437insisted" on travertine; Mrs. Masten apparently ag reed, but
1446said that she felt pressured to do so. The purchase was made ,
1458and Respondent returned to haul the travertine and other tile
1468for the flooring on a trailer back to Venice. At some point,
1480Mrs. Masten changed her mind about the travertine after bei ng
1491told by a competitor that travertine was a high - maintenance bad
1503choice. Respondent claimed it was too late to return the tile,
1514which he valued at $750.00, and so he testified that he threw it
1527away. Mrs. Masten then selected different tile from the
1536com petitor at a price that was $1,292.16 higher than the
1548travertine.
154914. The circumstances surrounding the selection of
1556cabinetry w ere also in dispute. Respondent testified that he
1566planned to use Enrique Benitez, a subcontractor who was doing
1576other work in the house, to make the cabinets. Respondent
1586claimed that he had Enrique prepare wood samples with different
1596stains and that Mrs. Masten approved the samples and picked out
1607the stain. At that point, Respondent said he paid Enrique
1617$2,970.00 to begin const ructing the cabinets. Mrs. Masten
1627claimed that she never approved any samples, was shown only a
1638rough, long plank of splintered wood that she said was awful and
1650would not approve, and that she did not like any of the work
1663this particular subcontractor was doing throughout the house.
1671At some point, Mrs. Masten impressed upon Respondent that she
1681would not accept these cabinets, and she selected different
1690cabinets at an increased cost of $6,886.00. If Enrique ever
1701built cabinets for the Mastens, he kept the m.
171015. Another outing was made to select countertops.
1718Mrs. Masten did not like the granite pieces that Respondent had
1729intended to use, and the result was that the cost of the granite
1742countertops selected by Mrs. Masten was $5,000.00 higher.
175116. Responde nt and Mrs. Masten also could not agree on the
1763extent of requested changes to the plans for flooring or the
1774cost of those changes. Respondent testified that Mrs. Masten
1783changed the mix of tile and carpeting, but Mrs. Masten
1793disagreed. Respondent testifie d that Mrs. Masten required an
1802upgraded carpet style, and although Mrs. Masten acknowledged
1810that she selected a different carpet style, there was no
1820evidence pinpointing the cost difference of the carpet upgrade.
1829Additionally, Respondent acknowledged that one reason why the
1837total cost for flooring was higher than expected was that
1847Enrique Benitez increased the price to install the tiles from
1857$3,000.00 to $7,500.00. Respondent sought to blame Mrs. Masten
1868for the increased installation price, claiming that Mrs. Masten
"1877fired" Enrique over the cabinet debacle, but Respondent had to
1887rehire Enrique to install the floors and had to pay the
1898increased price to overcome Enrique's hurt feelings.
1905Mrs. Masten denied the claim that she "fired" Enrique, though
1915she ackn owledged that she was not happy with his work and that
1928she refused to approve the cabinets Enrique was supposed to
1938build , because the sample was unacceptable.
194417. Respondent testified that an additional $3,079.90 was
1953spent for upgraded lighting and fans r equested by the Mastens
1964and for other electrical upgrades to accommodate other changes ,
1973such as the pool heater and spa tub.
198118. The cost to construct the pool increased by $3,700.00.
1992According to Respondent, this increase was due to the cost of
2003adding a pool heater that was not part of the original plans, at
2016the request of the Mastens. Mrs. Masten disputed that this was
2027a change.
202919. Respondent testified that there was a $323.00 cost
2038increase because of the Mastens' request for an upgraded water
2048soft ener.
205020. Post - contract changes made by the engineer to relocate
2061the septic tank system necessary to obtain the requisite
2070permits, altered the elevation and slope of certain parts of the
2081property, including the space where the air conditioner would
2090sit. Those changes resulted in the need to add a concrete slab
2102and platform for the air conditioner. This additional cost was
2112$419.25.
211321. Also because of the septic system design change, the
2123county imposed additional landscaping requirements in order to
2131obta in a certificate of occupancy. This resulted in an
2141additional $979.05 spent to purchase trees.
214722. Respondent testified that permitting fees imposed by
2155the county exceeded the estimated cost by $2,365.63. Respondent
2165attributed the increase to the higher impact fee charged by the
2176county as a condition to obtain a certificate of occupancy
2186because the post - construction value of the house was higher than
2198estimated. In other words, the combination of cost increases
2207and upgrades led to imposition of a higher impact fee.
221723. The rest of the difference between the contract price
2227and the total paid by the Mastens was attributable to increases
2238in costs because of the delay in completing the project or
2249increases in prices charged by subcontractors for their labor
2258and materials. These included increases in the price of
2267concrete, plumbing work, framing, insulation, roofing, drywall,
2274hauling trash, installation of flooring, electrical work,
2281equipment rental, and electricity charges. Respondent explained
2288that he obta ined "bids" for various components of the project in
2300September 2005, although he did not sign the contract with the
2311Mastens until January 10, 2006. Respondent anticipated that he
2320would start the project that month, but the start was delayed by
2332more than t wo months because of the septic system permitting
2343difficulties encountered by the project engineer who had been
2352retained by the Mastens.
235624. Mr. Colan utilized the estimates he received from
2365others to develop his overall cost estimates for the project,
2375wh ich he used to establish the contract price. There was no
2387allowance built into the cost estimations for inflation, price
2396increases, or contingency reserves.
240025. Although Respondent characterized the price estimates
2407he obtained from subcontractors as "bid s," they were not bids in
2419the sense of being firm offers to do work or supply material at
2432a specific cost; they were essentially price estimates subject
2441to change. Respondent testified that at least in some cases, he
2452could count on a bid price being "good " for six months and , in
2465some cases , for as long as seven months. However, Respondent
2475did not lock in any of the bid prices by contracting with the
2488subcontractors in September 2005 or in January 2006 when the
2498Masten contract was executed. Thus, Responden t's reliance on
2507the price estimates given to him in September 2005 was not shown
2519to be reasonable. These estimates would have been four months
2529old before Respondent anticipated starting the project and
2537closer to seven months old before the project actuall y began.
2548Since many of the price estimates were for items that would not
2560be needed for months after the project began (such as bathroom
2571fixtures, appliances, cabinetry, flooring, and lighting), even
2578under the best - case scenario without any delays, Respond ent was
2590plainly taking a risk by using September 2005 cost estimates as
2601if they were guaranteed prices in determining the contract price
2611for the Mastens' project. Not surprisingly, many subcontractors
2619were not willing to honor the stale price estimates wh en
2630Respondent sought to contract with them many months later.
263926. Respondent suggested that he should not bear the risk
2649of others' price increases, because they were not within his
2659control. But Respondent controlled how he went about estimating
2668his costs for the project and how he established the fixed price
2680he agreed to in the contract. No credible evidence was
2690presented to establish that the price increases by Respondent's
2699subcontractors were due to such extraordinary market conditions
2707or delays that t hey could not have been reasonably anticipated
2718and addressed sufficiently through inflation allowances or
2725contingency reserves built into the cost estimations.
273227. While Respondent attempted to characterize certain
2739price increases, such as the rise in the price of cement and
2751copper or the increased cost of dirt, as attributable to a
"2762heated up" construction market, which caused unanticipated
2769demand, Respondent's testimony was not credible and was not
2778supported by any independent non - hearsay evidence. Inde ed,
2788Respondent admitted that in most cases, he did not shop around
2799before accepting the price increases demanded by his
2807subcontractors. In some cases, he had checked on prices within
2817the two - county area when obtaining the cost estimates in
2828September 2005, and then he assumed that by identifying the
2838lowest price or best supplier in September 2005, there was no
2849need to check around when that supplier demanded a price
2859increase later. In no instance did Respondent check prices
2868outside of his local area.
287328. Respondent acknowledged that the total amount spent
2881for engineering and surveying fees exceeded his estimate by
2890$4,177.12. Respondent argued that these fees were beyond his
2900control , because the Mastens had retained the engineer and
2909surveyor before Respond ent entered into a contract with the
2919Mastens. However, Respondent included the engineer and surveyor
2927fee expenses in his cost estimates and assumed the
2936responsibility for covering these fees as part of the overall
2946construction of the house and pool within the fixed contract
2956price. No credible evidence established that the fees were
2965unusually high and could not have been anticipated or addressed
2975by appropriate contingency reserves.
297929. Respondent attempted to blame many of the price
2988increases on the tw o - plus month delay in starting the project
3001because of the engineer's need to relocate the septic system to
3012resolve permitting issues. As pointed out above, this delay did
3022not in and of itself cause the problem of price increases by
3034subcontractors unwillin g to honor price estimates quoted in
3043September 2005. In any event, Respondent did not testify that
3053the delays were extraordinary and not reasonably anticipated,
3061even if the exact reason for the delays may not have been known.
3074Instead, various delays for various reasons are to be expected,
3084and , indeed , are expressly contemplated throughout the written
3092contract. Notably, in a section called "Price Guarantee," the
3101contract form allowed the parties to specify a month by which
3112construction had to begin or els e the builder would have a
3124qualified right to adjust the contract price. Respondent waived
3133that right by specifying "N/A" in the blank where a start - by
3146month could have been named:
3151This Contract price is guaranteed to Buyer
3158only if it is possible for Buil der to start
3168construction on or before the month of N/A .
3177If start of construction is delayed beyond
3184this time by Buyer, or due to any ruling or
3194regulation of any governmental authority, or
3200due to any other cause which is not the
3209fault of the Builder, the Contract price may
3217be adjusted to the current list price or to
3226cover any cost increases incurred by
3232Builder.
323330. A plausible explanation for Respondent's lack of care
3242in developing reasonable, achievable cost estimates is that
3250Respondent did not conside r the fixed - price contract to be a
3263fixed - price contract. Respondent testified that even though the
3273contract on its face is a fixed - price contract, he believed that
3286he had an understanding with the Mastens that the contract was
3297really a "cost - plus" contrac t. Respondent testified that
3307despite what the contract said, the Mastens had agreed that they
3318would pay whatever the ultimate costs were, even if the prices
3329went up from his estimates, plus an additional $37,000 for
3340Respondent's profit. Respondent testif ied that the only reason
3349that the contract was written up as a fixed - price contract was
3362to secure the bank loan. That suggestion would be troubling, if
3373true, because the implication is that Respondent was a party to
3384fraud or deception to induce the constr uction loan. However,
3394there was no credible evidence to support Respondent's attempt
3403to justify recovering full costs , plus full profit , when the
3413fixed price he contracted for proved inadequate.
3420Notwithstanding Mr. Colan's apparent view that there was a
3429secret deal standing behind the written contract, he signed the
3439written contract, is bound by the fixed - price term, and must
3451bear the consequences of his inadequate cost estimations.
345931. At some point when the Mastens became concerned about
3469the extent to which they were apparently exceeding the contract
3479price while Respondent was still drawing bank funds from the
3489Mastens' construction loan, Mrs. Masten testified that she told
3498Respondent not to draw any more bank funds. The evidence did
3509not clearly establi sh whether Respondent violated Mrs. Masten's
3518instructions by withdrawing more bank funds after the
3526instructions were given. The Administrative Complaint had
3533alleged that the Mastens contacted the bank and ordered the bank
3544to make no further disbursements, and that the next day,
3554Respondent attempted to withdraw all remaining funds in the
3563construction loan account. No evidence was presented to
3571substantiate this allegation.
357432. Petitioner incurred total costs of $299.36 in the
3583investigation of this matter, excluding costs associated with
3591attorney time.
3593CONCLUSIONS OF LAW
359633. The Division of Administrative Hearings has
3603jurisdiction over the parties and the subject matter of this
3613proceeding. §§ 120.569 and 120.57(1), Fla. Stat. (2010).
362134. Petitioner has the burden of pleading with
3629particularity in the Administrative Complaint the facts and law
3638on which it relies to take disciplinary action against
3647Respondent. United Wisconsin Life Ins. Co. v. Off. of Ins.
3657Reg. , 849 So. 2d 417, 422 (Fla. 1st DCA 2003); Cottr ill v. Dep't
3671of Ins. , 685 So. 2d 1371, 1372 (Fla. 1st DCA 1996); Willner v.
3684Dep't of Prof ' l Reg., Bd. of Medicine , 563 So. 2d 805, 806 (Fla.
36991st DCA 1990).
370235. In addition, Petitioner has the burden to prove the
3712allegations in the Administrative Complain t by clear and
3721convincing evidence. Dep't of Banking and Fin. v. Osborne Stern
3731and Co. , 670 So. 2d 932 (Fla. 1996). The clear and convincing
3743evidence standard was defined in Slomowitz v. Walker , 429 So. 2d
3754797, 800 (Fla. 4th DCA 1983), as follows:
3762[C]lea r and convincing evidence requires
3768that the evidence must be found to be
3776credible; the facts to which the witnesses
3783testify must be distinctly remembered; the
3789testimony must be precise and explicit and
3796the witnesses must be lacking in confusion
3803as to the f acts in issue. The evidence must
3813be of such weight that it produces in the
3822mind of the trier of fact a firm belief or
3832conviction, without hesitancy, as to the
3838truth of the allegations sought to be
3845established.
384636. The four - count Administrative Complaint charged
3854Respondent with violations of section 489.129(1)(g)1. (Count
3861One); (1)(g)3. (Count Two); (1)(m) (Count Three); and (1)(l)
3870(Count Four). Section 489.129(1) provides in pertinent part:
3878The board may take any of the following
3886actions against any c ertificateholder or
3892registrant: place on probation or reprimand
3898the licensee, revoke, suspend, or deny the
3905issuance or renewal of the certificate,
3911registration, or certificate of authority,
3916require financial restitution to a consumer
3922for financial harm di rectly related to a
3930violation of a provision of this part,
3937impose an administrative fine not to exceed
3944$10,000 per violation, require continuing
3950education, or assess costs associated with
3956investigation and prosecution, if the
3961contractor, financially respon sible officer,
3966or business organization for which the
3972contractor is a primary qualifying agent, a
3979financially responsible officer, or a
3984secondary qualifying agent responsible under
3989s. 489.1195 is found guilty of any of the
3998following acts:
4000* * *
4003( g) Committing mismanagement or
4008misconduct in the practice of contracting
4014that causes financial harm to a customer.
4021Financial mismanagement or misconduct occurs
4026when:
40271. Valid liens have been recorded against
4034the property of a contractor's customer fo r
4042supplies or services ordered by the
4048contractor for the customer's job; the
4054contractor has received funds from the
4060customer to pay for the supplies or
4067services; and the contractor has not had the
4075liens removed from the property, by payment
4082or by bond, wit hin 75 days after the date of
4093such liens; [or]
4096* * *
40993. The contractor's job has been
4105completed, and it is shown that the customer
4113has had to pay more for the contracted job
4122than the original contract price, as
4128adjusted for subsequent change order s,
4134unless such increase in cost was the result
4142of circumstances beyond the control of the
4149contractor, was the result of circumstances
4155caused by the customer, or was otherwise
4162permitted by the terms of the contract
4169between the contractor and the customer .
4176* * *
4179(l) Committing fraud or deceit in the
4186practice of contracting.
4189(m) Committing incompetency or misconduct
4194in the practice of contracting.
419937. Petitioner voluntarily dismissed Count One of the
4207Administrative Complaint via the parties' p re - hearing
4216stipulation. Thus, Respondent is not charged with a violation
4225of section 489.129(1)(g)1.
422838. Count Two charged Respondent with a violation of
4237section 489.129(1)(g)3., because the Mastens had to pay more
4246than the contract price, adjusted by any change orders.
4255Respondent claimed that the increased price was attributed
4263solely to either the increased cost of the Mastens' changes or
4274price increases caused by circumstances beyond Respondent's
4281control or caused by the Mastens.
428739. In Dep't of Bus. a nd Prof ' l Reg., Constr. Indus.
4300Licensing Bd. v. Battaglia , Case No. 07 - 0052PL (Fla. DOAH May 8,
43132007), Administrative Law Judge Stuart Lerner examined this
4321statute and reached the following conclusions with regard to
4330burden of proof:
4333To meet its burden of proving a violation of
4342Section 489.129(1)(g)3., the Department must
4347establish that the "contractor's job ha[d]
4353been completed, and . . . that the customer
4362ha[d] had to pay more for the contracted job
4371than the original contract price, as
4377adjusted for subseq uent change orders."
4383Once it makes such a showing, the burden
4391shifts to the licensee to demonstrate that
"4398such increase in cost was the result of
4406circumstances beyond the control of the
4412contractor, was the result of circumstances
4418caused by the customer, o r was otherwise
4426permitted by the terms of the contract
4433between the contractor and the customer."
4439Cited in support of these conclusions were a number of cases
4450explaining that the structure of this statute, with exceptions
4459following the main sentence, suc h as where the main part of the
4472sentence is followed by a phrase starting with the word
"4482unless," means that the phrase following "unless" serves as a
4492qualifier to the main part of the sentence and demonstrates that
4503the phrase is intended to be an affirmat ive defense. Battaglia ,
4514Case No. 07 - 0052PL, RO at 35 - 36 n. 9.
452640. Thus, under the Battaglia analysis, which is adopted
4535here, it was Petitioner's burden to prove by clear and
4545convincing evidence that the price paid by the Mastens exceeded
4555the contract pri ce as adjusted by change orders. It was
4566Respondent's burden to prove as affirmative defenses that any
4575increase in contract price was the result of circumstances
4584beyond his control, was caused by the Mastens, or was otherwise
4595permitted by the contract.
459941 . Petitioner met its burden of proof, by clear and
4610convincing evidence, that the amount the Mastens paid for the
4620project exceeded the contract price as adjusted by change
4629orders, in violation of section 489.129(1)(g)3. However, in
4637terms of the amount by w hich payment exceeded the adjusted
4648contract price, Respondent will be given credit for : (1) the
4659amount of proven cost increases caused by changes to which the
4670Mastens admitted; and (2) the amount of cost increases
4679established by credible testimony by Resp ondent for additional
4688project changes made at the Mastens' request that were not
4698contemplated by the final plans. Although the second category
4707of claimed changes was disputed, Petitioner bears the burden of
4717proving the adjusted contract price, and Petitio ner failed to
4727refute the claimed changes by clear and convincing evidence. 3/
473742. Accordingly, the contract price of $260,000.00 is
4746adjusted upward by the following amounts: $2,703.55 for the
4756upgrade to energy efficient appliances; $4,745.42 for chang es to
4767plumbing and fixtures; $1,292.16 for tiles; $6,886.00 for
4777cabinets; $5,000.00 for countertops; $3,079.90 for lighting and
4787other electrical material; $3,700.00 for the pool heater;
4796$323.00 for the water softener upgrade; $419.25 for the air
4806conditioni ng slab and platform; $979.05 for trees; and $1,182.82
4817for one - half of the increase in the county permitting and impact
4830fees. 4 / The specific costs of other claimed changes were not
4842sufficiently established by competent substantial evidence. The
4849resulting adjusted contract price is $290,311.15. 5 /
485843. Respondent did not meet his burden of proof with
4868regard to the claimed affirmative defenses. A preponderance of
4877the more credible evidence does not support Respondent's
4885assertion that exceeding the contract price was justified
4893because of circumstances beyond his control or because of
4902circumstances caused by the Mastens.
490744. Respondent's position that he should be entitled to
4916adjust the contract price any time a supplier increases its
4926price because that is a circumstance he does not control, is
4937rejected. To the contrary, when Respondent chooses to enter
4946into a fixed - price contract without locking in the prices of
4958subcontractors whose estimates Respondent uses, then Respondent
4965bears the risk of price changes, at least absent evidence of
4976circumstances beyond the realm of reasonable anticipation.
4983Market fluctuations in prices, particularly in what was
4991admittedly a "hot" construction market, should be expected. It
5000was wholly within Respondent's control to build price
5008fluctuations into his estimates. While Respondent testified
5015that in a few instances, the price increases were higher than
5026what he had seen in some time, Respondent did not adequately
5037support his position. Moreover, Respondent's attempted
5043rationale fails to explain why absolutely no price increases or
5053contingency reserves were built into his cost estimates. The
5062only apparent explanation was that Respondent was improperly
5070relying on a secret deal and thought he could charge the Mastens
5082the actual cos ts, whatever they were, plus his profit.
509245. Respondent likewise did not meet his burden of proving
5102his claim that he should be allowed to adjust the contract price
5114because the delay in starting construction was a circumstance
5123beyond his control. As poin ted out in the F indings of F act,
5137Respondent could have designated a limit to the guaranteed fixed
5147contract price by specifying a month by which, if construction
5157did not start, Respondent would have had a limited right to
5168adjust the contract price. Respond ent waived this option by
5178writing in "N/A , " instead of naming a specific start - by month.
519046. Petitioner met its burden of proving by clear and
5200convincing evidence that Respondent violated section
5206489.129(1)(m) as charged in Count Three, by committing
5214mis management or incompetence in the practice of contracting.
5223Petitioner proved at least mismanagement and incompetence by
5231proving the poor job Respondent did in estimating costs used to
5242establish the fixed contract price, by not making a greater
5252effort to a chieve those estimates, and by apparently believing
5262he could pass all cost increases on to the Mastens because of
5274the secret deal he thought would override his written contract.
528447. Petitioner did not prove by clear and convincing
5293evidence the allegation in Count Four that Respondent committed
5302fraud or deceit in violation of section 489.129(1)(l) by
5311attempting to withdraw all remaining funds from the construction
5320loan account after being instructed not to make further
5329withdrawals. The only evidence offer ed on the subject of
5339Respondent's withdrawal attempts was hearsay -- what Mrs. Masten
5348was told by someone at the bank and even that testimony did not
5361support the allegation underlying Count Four's charge.
5368Petitioner offered no documentation or testimony by a bank
5377representative with direct knowledge of the allegation that
5385Respondent attempted to withdraw the remaining balance of nearly
5394$38,000 after the Mastens discontinued his authority to make
5404bank draws by freezing the account.
541048. Respondent's own testi mony was suggestive of different
5419fraudulent conduct. According to Respondent, there was a secret
5428deal for the Mastens to pay actual costs, whatever they were,
5439plus Respondent's profit, and that the only reason the contract
5449with the Mastens was written as a fixed - price contract was in
5462order to secure the Mastens' construction loan. This suggestion
5471is troubling, but as it was not charged in the Administrative
5482Complaint, it cannot be the basis for disciplinary action.
5491However, Mr. Colan's explanation for wh at he understood to be
5502the secret agreement standing behind the actual agreement puts
5511into context his apparent inattention to developing realistic
5519cost estimates to arrive at the contract price. If Mr. Colan
5530never believed that the contract price was any kind of cap and
5542that he would not have to live with his estimates, good or bad,
5555high or low, that would explain why he did not use more care in
5569obtaining bids, shopping around for lower - cost suppliers or , at
5580least, building inflation and contingency reser ves into his cost
5590estimates.
5591Appropriate Penalty
559349. Section 455.2273(5) provides that the A dministrative
5601L aw J udge, in recommending penalties, must follow the penalty
5612guidelines established by the board or department and must state
5622in writing the mitigat ing or aggravating circumstances upon
5631which the recommended penalty is based.
563750. Petitioner's penalty guidelines are codified in
5644Florida Administrative Code Rule 61G4 - 17.001, which, effective
5653January 24, 2005, provided in pertinent part:
5660(1) The follo wing guidelines shall be
5667used in disciplinary cases, absent
5672aggravating or mitigating circumstances and
5677subject to other provisions of this chapter .
5685* * *
5688(g) Section 489.129(1)(g), F.S.:
5692Mismanagement or misconduct causing
5696financial harm to the c ustomer. First
5703violation, $1,500 to $2,500 fine,
5710restitution and/or probation.
5713* * *
5716(m) Section 489.129(1)(m), F.S.:
5720Misconduct or incompetence in the practice
5726of contracting shall include, but is not
5733limited to:
5735* * *
57382. Violation of any provision of Chapter
574561G4, F.A.C., or Chapter 489, Part I., F.S.
5753* * *
5756First violation, $1,000 to $2,500 fine.
5764* * *
5767(l) Section 489.129(1)(l), F.S.:
5771Committing fraud or deceit in the practice
5778of contracting.
5780* * *
57831. Causin g no monetary or other harm to
5792licensee's customer or physical harm to any
5799person. First violation, $1,000 to $2,500
5807fine and/or probation. . . .
581351. Aggravating and mitigating circumstances established
5819by Petitioner are codified in r ule 61G4 - 17.002, pr oviding in
5832pertinent part:
5834Circumstances which may be considered for
5840the purposes of mitigation or aggravation of
5847penalty shall include, but are not limited
5854to, the following:
5857(1) Monetary or other damage to the
5864licensee's customer, in any way associ ated
5871with the violation, which damage the
5877licensee has not relieved, as of the time
5885the penalty is to be assessed. . . .
5894(2) Actual job - site violations of
5901building codes, or conditions exhibiting
5906gross negligence, incompetence, or
5910misconduct by the lic ensee, which have not
5918been corrected as of the time the penalty is
5927being assessed.
5929(3) The danger to the public.
5935(4) The number of complaints filed
5941against the licensee.
5944(5) The length of time the licensee has
5952practiced.
5953(6) The actual dama ge, physical or
5960otherwise, to the licensee's customer.
5965(7) The deterrent effect of the penalty
5972imposed.
5973(8) The effect of the penalty upon the
5981licensee's livelihood.
5983(9) Any efforts at rehabilitation.
5988(10) Other mitigating or aggravating
5993ci rcumstances.
599552. Petitioner's r ule 61G4 - 17.003 addresses the effect of
6006repeat violations on penalty assessments. No evidence was
6014presented of any prior violations by Respondent.
602153. In recommending penalties for the proven violations
6029charged in Counts Two and Three, the undersigned finds the
6039following aggravating circumstances: Respondent's violations
6044caused financial harm to the Mastens which Respondent has not
6054corrected; and imposition of a fine and restitution should have
6064a deterrent effect in that Respondent should understand that he
6074can avoid the problems presented here by adhering to the
6084formalities of the contracts he signs and using greater care and
6095caution in developing the cost estimations underlying his
6103contract prices.
610554. The undersigned f inds the following mitigating
6113circumstances: N o evidence was presented to show that
6122Respondent has any prior disciplinary history or has had
6131complaints filed against him in the past; and according to
6141Respondent's licensure record, Respondent held a licens e from
6150December 5, 1986, which was current and active through
6159September 21, 2008, when the status changed to current , but
6169inactive through August 31, 2010. However, as of the final
6179hearing, Respondent's licensure status had changed to
"6186delinquent, inactiv e."
618955. Upon consideration of the foregoing penalty guidelines
6197and the aggravating and mitigating circumstances found above,
6205the undersigned recommends the following as the appropriate
6213penalties: for Count Two, a fine of $1,500.00, plus restitution
6224in th e amount of $30,083.04; and for Count Three, an additional
6237fine of $1,500.00.
624156. Section 455.227(3)(a) authorizes imposition of the
6248costs associated with investigation and prosecution of a
6256disciplinary complaint, excluding costs associated with an
6263attorn ey's time, in addition to any other discipline imposed.
6273Under the authority of this statute, imposition of investigation
6282costs in the amount of $299.36 is warranted.
6290RECOMMENDATION
6291Based upon the foregoing Findings of Fact and Conclusions
6300of Law, it is
6304RECOMMENDED that a final order be entered by Petitioner,
6313Department of Business and Professional Regulation, Construction
6320Industry Licensing Board, finding that Respondent, Thomas Colan ,
6328d/b/a Thom Colan Construction, Inc. :
63341. V iolated section 489.129(1 )(g)3 . and (1)(m), as charged
6345in Counts Two and Three, and for those violations, imposing a
6356total fine of $3,000.00;
63612. R equiring Respondent to pay restitution to the Mastens
6371in the total amount of $30,083.04;
63783. R equiring Respondent to pay costs of $299.36; and
6388further
63894. D ismissing Count One (based on Petitioner's voluntary
6398dismissal) and Count Four (based on an absence of proof).
6408DONE AND ENTE RED this 14th day of April , 2011 , in
6419Tallahassee, Leon County, Florida.
6423S
6424ELIZABETH W. MCARTHUR
6427Administrative Law Judge
6430Division of Administrative Hearings
6434The DeSoto Building
64371230 Apalachee Parkway
6440Tallahassee, Florida 32399 - 3060
6445(850) 488 - 9675
6449Fax Filing (850) 921 - 6847
6455www.doah.state.fl.us
6456Filed with the Clerk of the
6462Division of Administrative Hearings
6466this 14th day of April , 2011 .
6473ENDNOTE S
64751/ Unless otherwise indicated, all references to the Florida
6484Statutes are to the 200 5 version.
64912/ Although Respondent argued in his Proposed Recommended Order
6500that he bears n o responsibility for any of the cost increases,
6512at the final hearing, Mr. Colan candidly accepted responsibility
6521for one small item, a $527.73 cost increase for trash hauling:
"6532[O]verall, it was just a matter of underestimating on my
6542part -- I'll admit to th is -- that it was going to be a lot more
6559trash on this job than I expected." Transcript at 82.
65693/ Petitioner argued that there should be no contract price
6579adjustment for change orders , because the change orders were not
6589in writing. Even though the contra ct requires written change
6599orders, the statute does not limit adjustments to only written
6609change orders or only change orders that comply with the
6619contract. However, because there were no change orders in
6628writing to document the cost difference, adjustmen ts could only
6638be made when competent substantial evidence was presented of
6647what was called for by the contract, how much the contract item
6659would have cost, and what the cost of the changed item was. For
6672example, although Respondent indicated in his testim ony that the
6682contract called for a certain mix of tiles and carpeting, and
6693that mix was changed, there was no evidence establishing what
6703exactly the contract called for, what it would have cost, what
6714exactly was changed, and what th e cost difference would be .
6726Vague testimony about "more tile" costing "more," or different
6735carpet costing "more" was insufficient to support an upward
6744adjustment to the contract in a specific dollar amount.
67534/ While the increase in permitting fees attributable to just
6763the up grades requested by the Mastens cannot be determined with
6774precision to the extent the increased value of the house (and ,
6785thus , the increased impact fee) is attributable to upgrades,
6794then that portion of the increased impact fee should be fairly
6805included as an upward adjustment to the contract price. Since
6815roughly one - half of the increased cost of the project was
6827attributable to upgrades, the contract price is adjusted upward
6836by one - half of the increased permitting fees.
68455/ No upward adjustment to th e con tract price is made for the
6859cost of the travertine tile that Respondent claimed to have
6869thrown away. Respondent's claim is not found to be credible and
6880would , in any event , be considered an unreasonable action that
6890is not chargeable to the Mastens. Likew ise, the contract price
6901is not adjusted for payments made by Respondent to Enrique
6911Benitez to begin building cabinets. Mrs. Masten credibly
6919testified that she did not approve any samples or authorize
6929construction of cabinets after seeing the unacceptable sample.
6937COPIES FURNISHED :
6940G.W. Harrell, Executive Director
6944Construction Industry Licensing Board
6948Department of Business and
6952Professional Regulation
69541940 North Monroe Street
6958Tallahassee, Florida 32399
6961Layne Smith, General Counsel
6965Department of Busin ess and
6970Professional Regulation
69721940 North Monroe Street
6976Tallahassee, Florida 32399
6979Gregg M. Horowitz, Esquire
6983Post Office Box 2927
6987Sarasota, Florida 34230
6990Paul Nathan Rendleman, Esquire
6994Department of Business and
6998Professional Regulation
70001940 Nor th Monroe Street, Suite 42
7007Tallahassee, Florida 323 99
7011NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
7017All parties have the right to submit written exceptions within
702715 days from the date of this Recommended Order. Any exceptions
7038to this Recommended Order should be filed with the agency that
7049will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 04/15/2011
- Proceedings: Transmittal letter from Claudia Llado forwarding Respondent's Proposed Exhibits numbered 1-149, which were not offered into evidence, to the Respondent.
- PDF:
- Date: 04/14/2011
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 03/17/2011
- Proceedings: Order Granting Motion to File Proposed Recommended Order After Deadline.
- PDF:
- Date: 03/16/2011
- Proceedings: Petitioner's Objection to Motion to Submit Proposed Recommended Order After Deadline filed.
- PDF:
- Date: 03/16/2011
- Proceedings: (Amended) Order on Motion to Allow Recommended Order Past Deadline filed.
- PDF:
- Date: 03/16/2011
- Proceedings: Amended Verified Motion to Allow Respondent to Submit Proposed Recommended Order after Deadline filed.
- PDF:
- Date: 03/16/2011
- Proceedings: (Proposed) Order on Motion to Allow Recommended Order Past Deadline filed.
- PDF:
- Date: 03/16/2011
- Proceedings: Verified Motion to Allow Respondent to Submit Proposed Recommended Order After Deadline filed.
- Date: 02/24/2011
- Proceedings: Transcript (not available for viewing) filed.
- Date: 02/04/2011
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 11/22/2010
- Proceedings: Order Re-scheduling Hearing by Video Teleconference (hearing set for February 4, 2011; 9:30 a.m.; Sarasota and Tallahassee, FL).
- PDF:
- Date: 11/12/2010
- Proceedings: Order Granting Continuance (parties to advise status by November 24, 2010).
- PDF:
- Date: 11/10/2010
- Proceedings: Petitioner's Response to Respondent's Verified Notice of Conflict and Motion to Continue Hearing filed.
- PDF:
- Date: 11/10/2010
- Proceedings: Verified Notice of Conflict and Motion for Continuance Hearing filed.
- Date: 11/10/2010
- Proceedings: Respondent's Exhibits (exhibit not available for viewing) filed.
- PDF:
- Date: 11/09/2010
- Proceedings: Copy of Petitioner's Exhibits (exhibits not available for viewing) filed.
- PDF:
- Date: 10/19/2010
- Proceedings: Petitioner's Second Supplement Response to Respondent's Request for Production filed.
- PDF:
- Date: 09/15/2010
- Proceedings: Petitioner's Supplemental Response to Respondent's Request for Production filed.
- PDF:
- Date: 09/01/2010
- Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for November 15, 2010; 9:30 a.m.; Sarasota and Tallahassee, FL; amended as to date of hearing).
- PDF:
- Date: 08/30/2010
- Proceedings: Petitioner's Response to Respondent's Request for Production filed.
Case Information
- Judge:
- ELIZABETH W. MCARTHUR
- Date Filed:
- 08/17/2010
- Date Assignment:
- 08/18/2010
- Last Docket Entry:
- 11/12/2019
- Location:
- Sarasota, Florida
- District:
- Middle
- Agency:
- Other
Counsels
-
Gregg Horowitz, Esquire
Address of Record -
Paul Nathan Rendleman, Esquire
Address of Record