10-007772 Department Of Business And Professional Regulation, Construction Industry Licensing Board vs. Thomas Colan, D/B/A Thom Colan Construction, Inc.
 Status: Closed
Recommended Order on Thursday, April 14, 2011.


View Dockets  
Summary: Petitioner proved Respondent charged more than the contract price and committed mismanagement and incompetence in the practice of contracting. Respondent failed to prove that exceeding the contract price was due to circumstances beyond his control.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8DEPARTMENT OF BUSINESS AND )

13PROFESSIONAL REGULATION, )

16CONSTRUCTION INDUSTRY )

19LICENSING BOARD , )

22)

23Petitioner , )

25)

26vs. ) Case No. 10 - 7772

33)

34THOMAS COLAN, d/b/a THOM COLAN )

40CONSTRUCTION, INC. , )

43)

44Respondent . )

47)

48RECOMMENDED ORDER

50Pursuant to notice, a final hearing was held in this case

61on February 4, 2011, by video teleconference in Tallahassee and

71Sarasota, Florida, before Administrative La w Judge Elizabeth W.

80McArthur of the Division of Administrative Hearings.

87APPEARANCES

88For Petitioner: Brian P. Coats, Esquire

94Department of Business and

98Professional Regulation

1001940 North Monroe Street , Suite 42

106Tallahassee, Fl orida 32399

110For Respondent: Gregg M. Horowitz, Esquire

116Post Office Box 2927

120Sarasota, Florida 34230

123STATEMENT OF THE ISSUES

127The issues in this case are whether Respondent committed

136the violations alleged in the Administrative Complaint, and , if

145so, what discipline should be imposed.

151PRELIMINARY STATEMENT

153Petitioner, Department of Business and Professional

159Regulation, Construction Industry Licensing Board (Petitioner) ,

165filed a four - count Administrative Complaint against Respondent,

174Thom as Colan, d/b/a Thom Colan Construction, Inc. (Respondent or

184Mr. Colan), a licensed contractor. The Administrative Complaint

192alleged that in carrying out a contract with Kathleen and Robert

203Masten to build a house and pool, Respondent committed

212violations of sections 489.129(1)(g)1. and 3., (1)(m), and

220(1)(l), Florida Statutes (2005). 1/

225Respondent timely requested an administrative hearing to

232contest the allegations in the Administrative Complaint, and the

241matter was referred to the Division of Administra tive Hearings

251(DOAH) for assignment of an Administrative Law Judge to conduct

261the hearing requested by Respondent.

266The final hearing was set for November 15, 2010, in

276accordance with the parties' request. On November 10, 2010,

285Respondent moved for a cont inuance because of a scheduling

295conflict. Petitioner did not oppose the request, and the

304hearing was rescheduled for February 4, 2011.

311The parties entered into a pre - hearing stipulation in which

322they admitted certain facts, which are included in the F ind ings

334of F act below. In addition, by the pre - hearing stipulation,

346Petitioner voluntarily dismissed Count One of the Administrative

354Complaint, which alleged a violation of section 489.129(1)(g)1.

362Remaining in dispute for litigation at the final hearing wer e

373Counts Two through Four, charging violations of section

381489.129(1)(g)3., (1)(m), and (1)(l), respectively.

386At the final hearing, Petitioner presented the testimony of

395Mrs. Masten and Mr. Colan. Petitioner's E xhibits 1 through 19

406and 21 were received in to evidence. Respondent testified on his

417own behalf and presented the testimony of Mrs. Masten.

426Respondent's E xhibits 1 through 3 were received into evidence.

436At the close of the hearing, a transcript was ordered , and

447the parties agreed to file their p roposed recommended orders

457(PRO) within ten days after the filing of the transcript at

468DOAH. The T ranscript was filed on February 24, 2011.

478Petitioner timely filed its PRO on March 7, 2011. On March 16,

4902011, Respondent f iled a motion to allow the late filing of its

503PRO, because counsel for Respondent had failed to properly

512calendar the deadline and had just obtained a copy of the

523T ranscript. Petitioner objected on the grounds that Respondent

532would gain an unfair advantage by being able to respond to

543Pe titioner's submittal, when the uniform rules contemplate

551simultaneous filings. The undersigned issued an O rder allowing

560Respondent additional time to late file its PRO, but affording

570Petitioner the opportunity to supplement its PRO within ten days

580after s ervice of Respondent's filing. Respondent filed its PRO

590by the extended deadline. Petitioner did not supplement its PRO

600within the time allowed, but filed a Notice of Scrivener's Error

611to correct a statutory citation. Both Petitioner and

619Respondent's PR Os, as well as Petitioner's Notice of Scrivener's

629Error, have been considered in the preparation of this

638Recommended Order.

640FINDINGS OF FACT

643Admitted Facts Per Pre - Hearing Stipulation

6501. Petitioner is the state agency charged with regulating

659the practi ce of contracting pursuant to section 20.165 and

669chapters 455 and 489, Florida Statutes.

6752. Respondent is a state - certified building contractor in

685the State of Florida, having been issued license No. CBC 039025.

6963. Respondent was the licensed primary qua lifying agent

705for Thom Colan Construction, Inc. , from June 10, 2004 , to

715September 4, 2008.

7184. On January 10, 2006, Thom Colan Construction, Inc. ,

727entered into a contract with Kathleen and Robert Masten to

737construct a house and pool on property located at 547 Bradenton

748Road, Venice, Florida (the project).

7535. The contract price for the project was $260,000.00.

7636. The project was completed with the issuance of a

773certificate of occupancy.

776Additional Findings of Fact

780Based on the weight and credibility of t he testimony and

791evidence presented, the following additional facts are found:

7997. The contract between Respondent and the Mastens was a

809fixed - price contract. Although the contract price was

818$260,000.00, the Mastens paid a total of $320.394.19 for the

829pr oject. The payments were made by the following methods:

839$49,968.58 was paid by check from the Mastens directly to

850Respondent; Respondent obtained an additional $222,320.71 in

858total bank draws, pursuant to a construction loan that

867authorized Respondent to draw funds directly from the bank for

877the project; and the remaining $48,104.90 was paid by check or

889credit card by the Mastens directly to subcontractors for labor

899and materials provided for the project. Thus, the Mastens paid

909$60,394.19 more than the c ontract price. At issue, and the

921subject of much dispute at the final hearing, was why the

932project exceeded the contract price by over $60,000.00 .

9428. Respondent asserted that the entire amount by which the

952contract price was exceeded was attributable ei ther to changes

962to the contract terms required by the Mastens or to

972circumstances beyond Respondent's control, such as price

979increases by subcontractors. 2/

9839. It was difficult to establish the causes for the price

994increases, in part , because the parties to the contract did not

1005adhere to the formalities called for by the contract. For

1015example, while both witnesses acknowledged that the Mastens

1023requested changes as the project progressed, there was

1031substantial disagreement about the extent of these change s and

1041the cost differential. Unfortunately, there were no written

1049change orders as required by the contract. Written change

1058orders would have documented exactly what was changed and what

1068cost was attributable to the change.

107410. Another problematic area in attempting to pinpoint why

1083the contract price was exceeded was that there was no clear

1094proof of the contract specifications detailing the design

1102features of the house and pool. The written contract described

1112a process of developing "plans" with "specif ications" as to

1122design elements. Initially, the plans would be preliminary,

1130with items designated for buyer selections. The contract

1138contemplated that the buyer would make these selections, which

1147would become part of the plans, and the plans would then b e

1160considered final. Thus, certain buyer selections would be part

1169of the contract. Thereafter, if the buyer wanted to change the

1180final plans and specifications, the buyer would be responsible

1189for the increased costs.

119311. No evidence was presented as to w hat the plans

1204provided with respect to design features and which of those

1214design features provided for buyer selections. Neither the

1222preliminary plans and specifications for the Masten contract,

1230nor the final plans and specifications after buyer selection s,

1240were offered into evidence, and it is unclear whether the

1250process contemplated by the written contract was even followed.

125912. Nonetheless, Mrs. Masten admitted that she requested

1267certain changes, which she acknowledged were not contemplated by

1276the co ntract and were more costly than what the contract

1287contemplated. For example, Mrs. Masten acknowledged that she

1295requested an upgrade in kitchen appliances, increasing the cost

1304by $2,703.55. She also acknowledged that she requested an

1314upgrade in bathroom fixtures, but she was unsure of the cost

1325attributable to the upgrade. Respondent testified that the

1333total cost increase for upgrades requested by Mrs. Masten to

1343plumbing and fixtures was $4,745.42. Mrs. Masten thought that

1353amount was too high; it include d changes claimed by Respondent ,

1364but disputed by Mrs. Masten, such as an upgrade to a hot tub

1377that Mrs. Masten said she did not want but , apparently , was

1388installed.

138913. The circumstances surrounding other apparent changes

1396were in dispute. For example, an expedition , including

1404Mrs. Masten and Respondent , trekked to a tile outlet store in

1415Fort Meyers to pick out tile to use in the shower stall and

1428floors. For the shower stall, Respondent testified that he

"1437insisted" on travertine; Mrs. Masten apparently ag reed, but

1446said that she felt pressured to do so. The purchase was made ,

1458and Respondent returned to haul the travertine and other tile

1468for the flooring on a trailer back to Venice. At some point,

1480Mrs. Masten changed her mind about the travertine after bei ng

1491told by a competitor that travertine was a high - maintenance bad

1503choice. Respondent claimed it was too late to return the tile,

1514which he valued at $750.00, and so he testified that he threw it

1527away. Mrs. Masten then selected different tile from the

1536com petitor at a price that was $1,292.16 higher than the

1548travertine.

154914. The circumstances surrounding the selection of

1556cabinetry w ere also in dispute. Respondent testified that he

1566planned to use Enrique Benitez, a subcontractor who was doing

1576other work in the house, to make the cabinets. Respondent

1586claimed that he had Enrique prepare wood samples with different

1596stains and that Mrs. Masten approved the samples and picked out

1607the stain. At that point, Respondent said he paid Enrique

1617$2,970.00 to begin const ructing the cabinets. Mrs. Masten

1627claimed that she never approved any samples, was shown only a

1638rough, long plank of splintered wood that she said was awful and

1650would not approve, and that she did not like any of the work

1663this particular subcontractor was doing throughout the house.

1671At some point, Mrs. Masten impressed upon Respondent that she

1681would not accept these cabinets, and she selected different

1690cabinets at an increased cost of $6,886.00. If Enrique ever

1701built cabinets for the Mastens, he kept the m.

171015. Another outing was made to select countertops.

1718Mrs. Masten did not like the granite pieces that Respondent had

1729intended to use, and the result was that the cost of the granite

1742countertops selected by Mrs. Masten was $5,000.00 higher.

175116. Responde nt and Mrs. Masten also could not agree on the

1763extent of requested changes to the plans for flooring or the

1774cost of those changes. Respondent testified that Mrs. Masten

1783changed the mix of tile and carpeting, but Mrs. Masten

1793disagreed. Respondent testifie d that Mrs. Masten required an

1802upgraded carpet style, and although Mrs. Masten acknowledged

1810that she selected a different carpet style, there was no

1820evidence pinpointing the cost difference of the carpet upgrade.

1829Additionally, Respondent acknowledged that one reason why the

1837total cost for flooring was higher than expected was that

1847Enrique Benitez increased the price to install the tiles from

1857$3,000.00 to $7,500.00. Respondent sought to blame Mrs. Masten

1868for the increased installation price, claiming that Mrs. Masten

"1877fired" Enrique over the cabinet debacle, but Respondent had to

1887rehire Enrique to install the floors and had to pay the

1898increased price to overcome Enrique's hurt feelings.

1905Mrs. Masten denied the claim that she "fired" Enrique, though

1915she ackn owledged that she was not happy with his work and that

1928she refused to approve the cabinets Enrique was supposed to

1938build , because the sample was unacceptable.

194417. Respondent testified that an additional $3,079.90 was

1953spent for upgraded lighting and fans r equested by the Mastens

1964and for other electrical upgrades to accommodate other changes ,

1973such as the pool heater and spa tub.

198118. The cost to construct the pool increased by $3,700.00.

1992According to Respondent, this increase was due to the cost of

2003adding a pool heater that was not part of the original plans, at

2016the request of the Mastens. Mrs. Masten disputed that this was

2027a change.

202919. Respondent testified that there was a $323.00 cost

2038increase because of the Mastens' request for an upgraded water

2048soft ener.

205020. Post - contract changes made by the engineer to relocate

2061the septic tank system necessary to obtain the requisite

2070permits, altered the elevation and slope of certain parts of the

2081property, including the space where the air conditioner would

2090sit. Those changes resulted in the need to add a concrete slab

2102and platform for the air conditioner. This additional cost was

2112$419.25.

211321. Also because of the septic system design change, the

2123county imposed additional landscaping requirements in order to

2131obta in a certificate of occupancy. This resulted in an

2141additional $979.05 spent to purchase trees.

214722. Respondent testified that permitting fees imposed by

2155the county exceeded the estimated cost by $2,365.63. Respondent

2165attributed the increase to the higher impact fee charged by the

2176county as a condition to obtain a certificate of occupancy

2186because the post - construction value of the house was higher than

2198estimated. In other words, the combination of cost increases

2207and upgrades led to imposition of a higher impact fee.

221723. The rest of the difference between the contract price

2227and the total paid by the Mastens was attributable to increases

2238in costs because of the delay in completing the project or

2249increases in prices charged by subcontractors for their labor

2258and materials. These included increases in the price of

2267concrete, plumbing work, framing, insulation, roofing, drywall,

2274hauling trash, installation of flooring, electrical work,

2281equipment rental, and electricity charges. Respondent explained

2288that he obta ined "bids" for various components of the project in

2300September 2005, although he did not sign the contract with the

2311Mastens until January 10, 2006. Respondent anticipated that he

2320would start the project that month, but the start was delayed by

2332more than t wo months because of the septic system permitting

2343difficulties encountered by the project engineer who had been

2352retained by the Mastens.

235624. Mr. Colan utilized the estimates he received from

2365others to develop his overall cost estimates for the project,

2375wh ich he used to establish the contract price. There was no

2387allowance built into the cost estimations for inflation, price

2396increases, or contingency reserves.

240025. Although Respondent characterized the price estimates

2407he obtained from subcontractors as "bid s," they were not bids in

2419the sense of being firm offers to do work or supply material at

2432a specific cost; they were essentially price estimates subject

2441to change. Respondent testified that at least in some cases, he

2452could count on a bid price being "good " for six months and , in

2465some cases , for as long as seven months. However, Respondent

2475did not lock in any of the bid prices by contracting with the

2488subcontractors in September 2005 or in January 2006 when the

2498Masten contract was executed. Thus, Responden t's reliance on

2507the price estimates given to him in September 2005 was not shown

2519to be reasonable. These estimates would have been four months

2529old before Respondent anticipated starting the project and

2537closer to seven months old before the project actuall y began.

2548Since many of the price estimates were for items that would not

2560be needed for months after the project began (such as bathroom

2571fixtures, appliances, cabinetry, flooring, and lighting), even

2578under the best - case scenario without any delays, Respond ent was

2590plainly taking a risk by using September 2005 cost estimates as

2601if they were guaranteed prices in determining the contract price

2611for the Mastens' project. Not surprisingly, many subcontractors

2619were not willing to honor the stale price estimates wh en

2630Respondent sought to contract with them many months later.

263926. Respondent suggested that he should not bear the risk

2649of others' price increases, because they were not within his

2659control. But Respondent controlled how he went about estimating

2668his costs for the project and how he established the fixed price

2680he agreed to in the contract. No credible evidence was

2690presented to establish that the price increases by Respondent's

2699subcontractors were due to such extraordinary market conditions

2707or delays that t hey could not have been reasonably anticipated

2718and addressed sufficiently through inflation allowances or

2725contingency reserves built into the cost estimations.

273227. While Respondent attempted to characterize certain

2739price increases, such as the rise in the price of cement and

2751copper or the increased cost of dirt, as attributable to a

"2762heated up" construction market, which caused unanticipated

2769demand, Respondent's testimony was not credible and was not

2778supported by any independent non - hearsay evidence. Inde ed,

2788Respondent admitted that in most cases, he did not shop around

2799before accepting the price increases demanded by his

2807subcontractors. In some cases, he had checked on prices within

2817the two - county area when obtaining the cost estimates in

2828September 2005, and then he assumed that by identifying the

2838lowest price or best supplier in September 2005, there was no

2849need to check around when that supplier demanded a price

2859increase later. In no instance did Respondent check prices

2868outside of his local area.

287328. Respondent acknowledged that the total amount spent

2881for engineering and surveying fees exceeded his estimate by

2890$4,177.12. Respondent argued that these fees were beyond his

2900control , because the Mastens had retained the engineer and

2909surveyor before Respond ent entered into a contract with the

2919Mastens. However, Respondent included the engineer and surveyor

2927fee expenses in his cost estimates and assumed the

2936responsibility for covering these fees as part of the overall

2946construction of the house and pool within the fixed contract

2956price. No credible evidence established that the fees were

2965unusually high and could not have been anticipated or addressed

2975by appropriate contingency reserves.

297929. Respondent attempted to blame many of the price

2988increases on the tw o - plus month delay in starting the project

3001because of the engineer's need to relocate the septic system to

3012resolve permitting issues. As pointed out above, this delay did

3022not in and of itself cause the problem of price increases by

3034subcontractors unwillin g to honor price estimates quoted in

3043September 2005. In any event, Respondent did not testify that

3053the delays were extraordinary and not reasonably anticipated,

3061even if the exact reason for the delays may not have been known.

3074Instead, various delays for various reasons are to be expected,

3084and , indeed , are expressly contemplated throughout the written

3092contract. Notably, in a section called "Price Guarantee," the

3101contract form allowed the parties to specify a month by which

3112construction had to begin or els e the builder would have a

3124qualified right to adjust the contract price. Respondent waived

3133that right by specifying "N/A" in the blank where a start - by

3146month could have been named:

3151This Contract price is guaranteed to Buyer

3158only if it is possible for Buil der to start

3168construction on or before the month of N/A .

3177If start of construction is delayed beyond

3184this time by Buyer, or due to any ruling or

3194regulation of any governmental authority, or

3200due to any other cause which is not the

3209fault of the Builder, the Contract price may

3217be adjusted to the current list price or to

3226cover any cost increases incurred by

3232Builder.

323330. A plausible explanation for Respondent's lack of care

3242in developing reasonable, achievable cost estimates is that

3250Respondent did not conside r the fixed - price contract to be a

3263fixed - price contract. Respondent testified that even though the

3273contract on its face is a fixed - price contract, he believed that

3286he had an understanding with the Mastens that the contract was

3297really a "cost - plus" contrac t. Respondent testified that

3307despite what the contract said, the Mastens had agreed that they

3318would pay whatever the ultimate costs were, even if the prices

3329went up from his estimates, plus an additional $37,000 for

3340Respondent's profit. Respondent testif ied that the only reason

3349that the contract was written up as a fixed - price contract was

3362to secure the bank loan. That suggestion would be troubling, if

3373true, because the implication is that Respondent was a party to

3384fraud or deception to induce the constr uction loan. However,

3394there was no credible evidence to support Respondent's attempt

3403to justify recovering full costs , plus full profit , when the

3413fixed price he contracted for proved inadequate.

3420Notwithstanding Mr. Colan's apparent view that there was a

3429secret deal standing behind the written contract, he signed the

3439written contract, is bound by the fixed - price term, and must

3451bear the consequences of his inadequate cost estimations.

345931. At some point when the Mastens became concerned about

3469the extent to which they were apparently exceeding the contract

3479price while Respondent was still drawing bank funds from the

3489Mastens' construction loan, Mrs. Masten testified that she told

3498Respondent not to draw any more bank funds. The evidence did

3509not clearly establi sh whether Respondent violated Mrs. Masten's

3518instructions by withdrawing more bank funds after the

3526instructions were given. The Administrative Complaint had

3533alleged that the Mastens contacted the bank and ordered the bank

3544to make no further disbursements, and that the next day,

3554Respondent attempted to withdraw all remaining funds in the

3563construction loan account. No evidence was presented to

3571substantiate this allegation.

357432. Petitioner incurred total costs of $299.36 in the

3583investigation of this matter, excluding costs associated with

3591attorney time.

3593CONCLUSIONS OF LAW

359633. The Division of Administrative Hearings has

3603jurisdiction over the parties and the subject matter of this

3613proceeding. §§ 120.569 and 120.57(1), Fla. Stat. (2010).

362134. Petitioner has the burden of pleading with

3629particularity in the Administrative Complaint the facts and law

3638on which it relies to take disciplinary action against

3647Respondent. United Wisconsin Life Ins. Co. v. Off. of Ins.

3657Reg. , 849 So. 2d 417, 422 (Fla. 1st DCA 2003); Cottr ill v. Dep't

3671of Ins. , 685 So. 2d 1371, 1372 (Fla. 1st DCA 1996); Willner v.

3684Dep't of Prof ' l Reg., Bd. of Medicine , 563 So. 2d 805, 806 (Fla.

36991st DCA 1990).

370235. In addition, Petitioner has the burden to prove the

3712allegations in the Administrative Complain t by clear and

3721convincing evidence. Dep't of Banking and Fin. v. Osborne Stern

3731and Co. , 670 So. 2d 932 (Fla. 1996). The clear and convincing

3743evidence standard was defined in Slomowitz v. Walker , 429 So. 2d

3754797, 800 (Fla. 4th DCA 1983), as follows:

3762[C]lea r and convincing evidence requires

3768that the evidence must be found to be

3776credible; the facts to which the witnesses

3783testify must be distinctly remembered; the

3789testimony must be precise and explicit and

3796the witnesses must be lacking in confusion

3803as to the f acts in issue. The evidence must

3813be of such weight that it produces in the

3822mind of the trier of fact a firm belief or

3832conviction, without hesitancy, as to the

3838truth of the allegations sought to be

3845established.

384636. The four - count Administrative Complaint charged

3854Respondent with violations of section 489.129(1)(g)1. (Count

3861One); (1)(g)3. (Count Two); (1)(m) (Count Three); and (1)(l)

3870(Count Four). Section 489.129(1) provides in pertinent part:

3878The board may take any of the following

3886actions against any c ertificateholder or

3892registrant: place on probation or reprimand

3898the licensee, revoke, suspend, or deny the

3905issuance or renewal of the certificate,

3911registration, or certificate of authority,

3916require financial restitution to a consumer

3922for financial harm di rectly related to a

3930violation of a provision of this part,

3937impose an administrative fine not to exceed

3944$10,000 per violation, require continuing

3950education, or assess costs associated with

3956investigation and prosecution, if the

3961contractor, financially respon sible officer,

3966or business organization for which the

3972contractor is a primary qualifying agent, a

3979financially responsible officer, or a

3984secondary qualifying agent responsible under

3989s. 489.1195 is found guilty of any of the

3998following acts:

4000* * *

4003( g) Committing mismanagement or

4008misconduct in the practice of contracting

4014that causes financial harm to a customer.

4021Financial mismanagement or misconduct occurs

4026when:

40271. Valid liens have been recorded against

4034the property of a contractor's customer fo r

4042supplies or services ordered by the

4048contractor for the customer's job; the

4054contractor has received funds from the

4060customer to pay for the supplies or

4067services; and the contractor has not had the

4075liens removed from the property, by payment

4082or by bond, wit hin 75 days after the date of

4093such liens; [or]

4096* * *

40993. The contractor's job has been

4105completed, and it is shown that the customer

4113has had to pay more for the contracted job

4122than the original contract price, as

4128adjusted for subsequent change order s,

4134unless such increase in cost was the result

4142of circumstances beyond the control of the

4149contractor, was the result of circumstances

4155caused by the customer, or was otherwise

4162permitted by the terms of the contract

4169between the contractor and the customer .

4176* * *

4179(l) Committing fraud or deceit in the

4186practice of contracting.

4189(m) Committing incompetency or misconduct

4194in the practice of contracting.

419937. Petitioner voluntarily dismissed Count One of the

4207Administrative Complaint via the parties' p re - hearing

4216stipulation. Thus, Respondent is not charged with a violation

4225of section 489.129(1)(g)1.

422838. Count Two charged Respondent with a violation of

4237section 489.129(1)(g)3., because the Mastens had to pay more

4246than the contract price, adjusted by any change orders.

4255Respondent claimed that the increased price was attributed

4263solely to either the increased cost of the Mastens' changes or

4274price increases caused by circumstances beyond Respondent's

4281control or caused by the Mastens.

428739. In Dep't of Bus. a nd Prof ' l Reg., Constr. Indus.

4300Licensing Bd. v. Battaglia , Case No. 07 - 0052PL (Fla. DOAH May 8,

43132007), Administrative Law Judge Stuart Lerner examined this

4321statute and reached the following conclusions with regard to

4330burden of proof:

4333To meet its burden of proving a violation of

4342Section 489.129(1)(g)3., the Department must

4347establish that the "contractor's job ha[d]

4353been completed, and . . . that the customer

4362ha[d] had to pay more for the contracted job

4371than the original contract price, as

4377adjusted for subseq uent change orders."

4383Once it makes such a showing, the burden

4391shifts to the licensee to demonstrate that

"4398such increase in cost was the result of

4406circumstances beyond the control of the

4412contractor, was the result of circumstances

4418caused by the customer, o r was otherwise

4426permitted by the terms of the contract

4433between the contractor and the customer."

4439Cited in support of these conclusions were a number of cases

4450explaining that the structure of this statute, with exceptions

4459following the main sentence, suc h as where the main part of the

4472sentence is followed by a phrase starting with the word

"4482unless," means that the phrase following "unless" serves as a

4492qualifier to the main part of the sentence and demonstrates that

4503the phrase is intended to be an affirmat ive defense. Battaglia ,

4514Case No. 07 - 0052PL, RO at 35 - 36 n. 9.

452640. Thus, under the Battaglia analysis, which is adopted

4535here, it was Petitioner's burden to prove by clear and

4545convincing evidence that the price paid by the Mastens exceeded

4555the contract pri ce as adjusted by change orders. It was

4566Respondent's burden to prove as affirmative defenses that any

4575increase in contract price was the result of circumstances

4584beyond his control, was caused by the Mastens, or was otherwise

4595permitted by the contract.

459941 . Petitioner met its burden of proof, by clear and

4610convincing evidence, that the amount the Mastens paid for the

4620project exceeded the contract price as adjusted by change

4629orders, in violation of section 489.129(1)(g)3. However, in

4637terms of the amount by w hich payment exceeded the adjusted

4648contract price, Respondent will be given credit for : (1) the

4659amount of proven cost increases caused by changes to which the

4670Mastens admitted; and (2) the amount of cost increases

4679established by credible testimony by Resp ondent for additional

4688project changes made at the Mastens' request that were not

4698contemplated by the final plans. Although the second category

4707of claimed changes was disputed, Petitioner bears the burden of

4717proving the adjusted contract price, and Petitio ner failed to

4727refute the claimed changes by clear and convincing evidence. 3/

473742. Accordingly, the contract price of $260,000.00 is

4746adjusted upward by the following amounts: $2,703.55 for the

4756upgrade to energy efficient appliances; $4,745.42 for chang es to

4767plumbing and fixtures; $1,292.16 for tiles; $6,886.00 for

4777cabinets; $5,000.00 for countertops; $3,079.90 for lighting and

4787other electrical material; $3,700.00 for the pool heater;

4796$323.00 for the water softener upgrade; $419.25 for the air

4806conditioni ng slab and platform; $979.05 for trees; and $1,182.82

4817for one - half of the increase in the county permitting and impact

4830fees. 4 / The specific costs of other claimed changes were not

4842sufficiently established by competent substantial evidence. The

4849resulting adjusted contract price is $290,311.15. 5 /

485843. Respondent did not meet his burden of proof with

4868regard to the claimed affirmative defenses. A preponderance of

4877the more credible evidence does not support Respondent's

4885assertion that exceeding the contract price was justified

4893because of circumstances beyond his control or because of

4902circumstances caused by the Mastens.

490744. Respondent's position that he should be entitled to

4916adjust the contract price any time a supplier increases its

4926price because that is a circumstance he does not control, is

4937rejected. To the contrary, when Respondent chooses to enter

4946into a fixed - price contract without locking in the prices of

4958subcontractors whose estimates Respondent uses, then Respondent

4965bears the risk of price changes, at least absent evidence of

4976circumstances beyond the realm of reasonable anticipation.

4983Market fluctuations in prices, particularly in what was

4991admittedly a "hot" construction market, should be expected. It

5000was wholly within Respondent's control to build price

5008fluctuations into his estimates. While Respondent testified

5015that in a few instances, the price increases were higher than

5026what he had seen in some time, Respondent did not adequately

5037support his position. Moreover, Respondent's attempted

5043rationale fails to explain why absolutely no price increases or

5053contingency reserves were built into his cost estimates. The

5062only apparent explanation was that Respondent was improperly

5070relying on a secret deal and thought he could charge the Mastens

5082the actual cos ts, whatever they were, plus his profit.

509245. Respondent likewise did not meet his burden of proving

5102his claim that he should be allowed to adjust the contract price

5114because the delay in starting construction was a circumstance

5123beyond his control. As poin ted out in the F indings of F act,

5137Respondent could have designated a limit to the guaranteed fixed

5147contract price by specifying a month by which, if construction

5157did not start, Respondent would have had a limited right to

5168adjust the contract price. Respond ent waived this option by

5178writing in "N/A , " instead of naming a specific start - by month.

519046. Petitioner met its burden of proving by clear and

5200convincing evidence that Respondent violated section

5206489.129(1)(m) as charged in Count Three, by committing

5214mis management or incompetence in the practice of contracting.

5223Petitioner proved at least mismanagement and incompetence by

5231proving the poor job Respondent did in estimating costs used to

5242establish the fixed contract price, by not making a greater

5252effort to a chieve those estimates, and by apparently believing

5262he could pass all cost increases on to the Mastens because of

5274the secret deal he thought would override his written contract.

528447. Petitioner did not prove by clear and convincing

5293evidence the allegation in Count Four that Respondent committed

5302fraud or deceit in violation of section 489.129(1)(l) by

5311attempting to withdraw all remaining funds from the construction

5320loan account after being instructed not to make further

5329withdrawals. The only evidence offer ed on the subject of

5339Respondent's withdrawal attempts was hearsay -- what Mrs. Masten

5348was told by someone at the bank and even that testimony did not

5361support the allegation underlying Count Four's charge.

5368Petitioner offered no documentation or testimony by a bank

5377representative with direct knowledge of the allegation that

5385Respondent attempted to withdraw the remaining balance of nearly

5394$38,000 after the Mastens discontinued his authority to make

5404bank draws by freezing the account.

541048. Respondent's own testi mony was suggestive of different

5419fraudulent conduct. According to Respondent, there was a secret

5428deal for the Mastens to pay actual costs, whatever they were,

5439plus Respondent's profit, and that the only reason the contract

5449with the Mastens was written as a fixed - price contract was in

5462order to secure the Mastens' construction loan. This suggestion

5471is troubling, but as it was not charged in the Administrative

5482Complaint, it cannot be the basis for disciplinary action.

5491However, Mr. Colan's explanation for wh at he understood to be

5502the secret agreement standing behind the actual agreement puts

5511into context his apparent inattention to developing realistic

5519cost estimates to arrive at the contract price. If Mr. Colan

5530never believed that the contract price was any kind of cap and

5542that he would not have to live with his estimates, good or bad,

5555high or low, that would explain why he did not use more care in

5569obtaining bids, shopping around for lower - cost suppliers or , at

5580least, building inflation and contingency reser ves into his cost

5590estimates.

5591Appropriate Penalty

559349. Section 455.2273(5) provides that the A dministrative

5601L aw J udge, in recommending penalties, must follow the penalty

5612guidelines established by the board or department and must state

5622in writing the mitigat ing or aggravating circumstances upon

5631which the recommended penalty is based.

563750. Petitioner's penalty guidelines are codified in

5644Florida Administrative Code Rule 61G4 - 17.001, which, effective

5653January 24, 2005, provided in pertinent part:

5660(1) The follo wing guidelines shall be

5667used in disciplinary cases, absent

5672aggravating or mitigating circumstances and

5677subject to other provisions of this chapter .

5685* * *

5688(g) Section 489.129(1)(g), F.S.:

5692Mismanagement or misconduct causing

5696financial harm to the c ustomer. First

5703violation, $1,500 to $2,500 fine,

5710restitution and/or probation.

5713* * *

5716(m) Section 489.129(1)(m), F.S.:

5720Misconduct or incompetence in the practice

5726of contracting shall include, but is not

5733limited to:

5735* * *

57382. Violation of any provision of Chapter

574561G4, F.A.C., or Chapter 489, Part I., F.S.

5753* * *

5756First violation, $1,000 to $2,500 fine.

5764* * *

5767(l) Section 489.129(1)(l), F.S.:

5771Committing fraud or deceit in the practice

5778of contracting.

5780* * *

57831. Causin g no monetary or other harm to

5792licensee's customer or physical harm to any

5799person. First violation, $1,000 to $2,500

5807fine and/or probation. . . .

581351. Aggravating and mitigating circumstances established

5819by Petitioner are codified in r ule 61G4 - 17.002, pr oviding in

5832pertinent part:

5834Circumstances which may be considered for

5840the purposes of mitigation or aggravation of

5847penalty shall include, but are not limited

5854to, the following:

5857(1) Monetary or other damage to the

5864licensee's customer, in any way associ ated

5871with the violation, which damage the

5877licensee has not relieved, as of the time

5885the penalty is to be assessed. . . .

5894(2) Actual job - site violations of

5901building codes, or conditions exhibiting

5906gross negligence, incompetence, or

5910misconduct by the lic ensee, which have not

5918been corrected as of the time the penalty is

5927being assessed.

5929(3) The danger to the public.

5935(4) The number of complaints filed

5941against the licensee.

5944(5) The length of time the licensee has

5952practiced.

5953(6) The actual dama ge, physical or

5960otherwise, to the licensee's customer.

5965(7) The deterrent effect of the penalty

5972imposed.

5973(8) The effect of the penalty upon the

5981licensee's livelihood.

5983(9) Any efforts at rehabilitation.

5988(10) Other mitigating or aggravating

5993ci rcumstances.

599552. Petitioner's r ule 61G4 - 17.003 addresses the effect of

6006repeat violations on penalty assessments. No evidence was

6014presented of any prior violations by Respondent.

602153. In recommending penalties for the proven violations

6029charged in Counts Two and Three, the undersigned finds the

6039following aggravating circumstances: Respondent's violations

6044caused financial harm to the Mastens which Respondent has not

6054corrected; and imposition of a fine and restitution should have

6064a deterrent effect in that Respondent should understand that he

6074can avoid the problems presented here by adhering to the

6084formalities of the contracts he signs and using greater care and

6095caution in developing the cost estimations underlying his

6103contract prices.

610554. The undersigned f inds the following mitigating

6113circumstances: N o evidence was presented to show that

6122Respondent has any prior disciplinary history or has had

6131complaints filed against him in the past; and according to

6141Respondent's licensure record, Respondent held a licens e from

6150December 5, 1986, which was current and active through

6159September 21, 2008, when the status changed to current , but

6169inactive through August 31, 2010. However, as of the final

6179hearing, Respondent's licensure status had changed to

"6186delinquent, inactiv e."

618955. Upon consideration of the foregoing penalty guidelines

6197and the aggravating and mitigating circumstances found above,

6205the undersigned recommends the following as the appropriate

6213penalties: for Count Two, a fine of $1,500.00, plus restitution

6224in th e amount of $30,083.04; and for Count Three, an additional

6237fine of $1,500.00.

624156. Section 455.227(3)(a) authorizes imposition of the

6248costs associated with investigation and prosecution of a

6256disciplinary complaint, excluding costs associated with an

6263attorn ey's time, in addition to any other discipline imposed.

6273Under the authority of this statute, imposition of investigation

6282costs in the amount of $299.36 is warranted.

6290RECOMMENDATION

6291Based upon the foregoing Findings of Fact and Conclusions

6300of Law, it is

6304RECOMMENDED that a final order be entered by Petitioner,

6313Department of Business and Professional Regulation, Construction

6320Industry Licensing Board, finding that Respondent, Thomas Colan ,

6328d/b/a Thom Colan Construction, Inc. :

63341. V iolated section 489.129(1 )(g)3 . and (1)(m), as charged

6345in Counts Two and Three, and for those violations, imposing a

6356total fine of $3,000.00;

63612. R equiring Respondent to pay restitution to the Mastens

6371in the total amount of $30,083.04;

63783. R equiring Respondent to pay costs of $299.36; and

6388further

63894. D ismissing Count One (based on Petitioner's voluntary

6398dismissal) and Count Four (based on an absence of proof).

6408DONE AND ENTE RED this 14th day of April , 2011 , in

6419Tallahassee, Leon County, Florida.

6423S

6424ELIZABETH W. MCARTHUR

6427Administrative Law Judge

6430Division of Administrative Hearings

6434The DeSoto Building

64371230 Apalachee Parkway

6440Tallahassee, Florida 32399 - 3060

6445(850) 488 - 9675

6449Fax Filing (850) 921 - 6847

6455www.doah.state.fl.us

6456Filed with the Clerk of the

6462Division of Administrative Hearings

6466this 14th day of April , 2011 .

6473ENDNOTE S

64751/ Unless otherwise indicated, all references to the Florida

6484Statutes are to the 200 5 version.

64912/ Although Respondent argued in his Proposed Recommended Order

6500that he bears n o responsibility for any of the cost increases,

6512at the final hearing, Mr. Colan candidly accepted responsibility

6521for one small item, a $527.73 cost increase for trash hauling:

"6532[O]verall, it was just a matter of underestimating on my

6542part -- I'll admit to th is -- that it was going to be a lot more

6559trash on this job than I expected." Transcript at 82.

65693/ Petitioner argued that there should be no contract price

6579adjustment for change orders , because the change orders were not

6589in writing. Even though the contra ct requires written change

6599orders, the statute does not limit adjustments to only written

6609change orders or only change orders that comply with the

6619contract. However, because there were no change orders in

6628writing to document the cost difference, adjustmen ts could only

6638be made when competent substantial evidence was presented of

6647what was called for by the contract, how much the contract item

6659would have cost, and what the cost of the changed item was. For

6672example, although Respondent indicated in his testim ony that the

6682contract called for a certain mix of tiles and carpeting, and

6693that mix was changed, there was no evidence establishing what

6703exactly the contract called for, what it would have cost, what

6714exactly was changed, and what th e cost difference would be .

6726Vague testimony about "more tile" costing "more," or different

6735carpet costing "more" was insufficient to support an upward

6744adjustment to the contract in a specific dollar amount.

67534/ While the increase in permitting fees attributable to just

6763the up grades requested by the Mastens cannot be determined with

6774precision to the extent the increased value of the house (and ,

6785thus , the increased impact fee) is attributable to upgrades,

6794then that portion of the increased impact fee should be fairly

6805included as an upward adjustment to the contract price. Since

6815roughly one - half of the increased cost of the project was

6827attributable to upgrades, the contract price is adjusted upward

6836by one - half of the increased permitting fees.

68455/ No upward adjustment to th e con tract price is made for the

6859cost of the travertine tile that Respondent claimed to have

6869thrown away. Respondent's claim is not found to be credible and

6880would , in any event , be considered an unreasonable action that

6890is not chargeable to the Mastens. Likew ise, the contract price

6901is not adjusted for payments made by Respondent to Enrique

6911Benitez to begin building cabinets. Mrs. Masten credibly

6919testified that she did not approve any samples or authorize

6929construction of cabinets after seeing the unacceptable sample.

6937COPIES FURNISHED :

6940G.W. Harrell, Executive Director

6944Construction Industry Licensing Board

6948Department of Business and

6952Professional Regulation

69541940 North Monroe Street

6958Tallahassee, Florida 32399

6961Layne Smith, General Counsel

6965Department of Busin ess and

6970Professional Regulation

69721940 North Monroe Street

6976Tallahassee, Florida 32399

6979Gregg M. Horowitz, Esquire

6983Post Office Box 2927

6987Sarasota, Florida 34230

6990Paul Nathan Rendleman, Esquire

6994Department of Business and

6998Professional Regulation

70001940 Nor th Monroe Street, Suite 42

7007Tallahassee, Florida 323 99

7011NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

7017All parties have the right to submit written exceptions within

702715 days from the date of this Recommended Order. Any exceptions

7038to this Recommended Order should be filed with the agency that

7049will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 11/12/2019
Proceedings: Agency Final Order filed.
PDF:
Date: 10/04/2011
Proceedings: Agency Final Order
PDF:
Date: 04/15/2011
Proceedings: Transmittal letter from Claudia Llado forwarding Respondent's Proposed Exhibits numbered 1-149, which were not offered into evidence, to the Respondent.
PDF:
Date: 04/14/2011
Proceedings: Recommended Order
PDF:
Date: 04/14/2011
Proceedings: Recommended Order (hearing held February 4, 2011). CASE CLOSED.
PDF:
Date: 04/14/2011
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 04/07/2011
Proceedings: Notice of Scrivener's Error filed.
PDF:
Date: 03/28/2011
Proceedings: Respondent`s Proposed Recommended Order filed.
PDF:
Date: 03/17/2011
Proceedings: Order Granting Motion to File Proposed Recommended Order After Deadline.
PDF:
Date: 03/16/2011
Proceedings: Petitioner's Objection to Motion to Submit Proposed Recommended Order After Deadline filed.
PDF:
Date: 03/16/2011
Proceedings: (Amended) Order on Motion to Allow Recommended Order Past Deadline filed.
PDF:
Date: 03/16/2011
Proceedings: Amended Verified Motion to Allow Respondent to Submit Proposed Recommended Order after Deadline filed.
PDF:
Date: 03/16/2011
Proceedings: (Proposed) Order on Motion to Allow Recommended Order Past Deadline filed.
PDF:
Date: 03/16/2011
Proceedings: Verified Motion to Allow Respondent to Submit Proposed Recommended Order After Deadline filed.
PDF:
Date: 03/07/2011
Proceedings: Petitioner's Proposed Recommended Order filed.
Date: 02/24/2011
Proceedings: Transcript (not available for viewing) filed.
PDF:
Date: 02/23/2011
Proceedings: Order Allowing Withdrawal of Counsel.
PDF:
Date: 02/21/2011
Proceedings: Motion to Withdraw as Attorney of Record for Petitioner filed.
Date: 02/04/2011
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 02/03/2011
Proceedings: Amended Exhibit List (exhibits not available for viewing) filed.
PDF:
Date: 02/02/2011
Proceedings: Notice of Appearance (of P. Rendleman) filed.
PDF:
Date: 02/02/2011
Proceedings: Amended Exhibit List (exhibits not attached) filed.
PDF:
Date: 01/06/2011
Proceedings: Letter to parties of record from Judge Mcarthur.
PDF:
Date: 11/22/2010
Proceedings: Order Re-scheduling Hearing by Video Teleconference (hearing set for February 4, 2011; 9:30 a.m.; Sarasota and Tallahassee, FL).
PDF:
Date: 11/18/2010
Proceedings: Joint Response to Establish Hearing filed.
PDF:
Date: 11/12/2010
Proceedings: Order Granting Continuance (parties to advise status by November 24, 2010).
PDF:
Date: 11/10/2010
Proceedings: Petitioner's Response to Respondent's Verified Notice of Conflict and Motion to Continue Hearing filed.
PDF:
Date: 11/10/2010
Proceedings: Verified Notice of Conflict and Motion for Continuance Hearing filed.
Date: 11/10/2010
Proceedings: Respondent's Exhibits (exhibit not available for viewing) filed.
PDF:
Date: 11/09/2010
Proceedings: Copy of Petitioner's Exhibits (exhibits not available for viewing) filed.
PDF:
Date: 11/09/2010
Proceedings: Pre-hearing Stipulation filed.
PDF:
Date: 10/25/2010
Proceedings: Answer to Request for Production filed.
PDF:
Date: 10/19/2010
Proceedings: Petitioner's Second Supplement Response to Respondent's Request for Production filed.
PDF:
Date: 09/17/2010
Proceedings: Answer filed.
PDF:
Date: 09/15/2010
Proceedings: Petitioner's Supplemental Response to Respondent's Request for Production filed.
PDF:
Date: 09/10/2010
Proceedings: Petitioner's First Request to Produce to Respondent filed.
PDF:
Date: 09/01/2010
Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for November 15, 2010; 9:30 a.m.; Sarasota and Tallahassee, FL; amended as to date of hearing).
PDF:
Date: 08/30/2010
Proceedings: Petitioner's Response to Respondent's Request for Production filed.
PDF:
Date: 08/27/2010
Proceedings: Request for Production filed.
PDF:
Date: 08/27/2010
Proceedings: Respondent's Response to Initial Order filed.
PDF:
Date: 08/27/2010
Proceedings: Answer filed.
PDF:
Date: 08/26/2010
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 08/26/2010
Proceedings: Notice of Hearing by Video Teleconference (hearing set for October 29, 2010; 9:30 a.m.; Sarasota and Tallahassee, FL).
PDF:
Date: 08/20/2010
Proceedings: Petitioner's First Request for Admissions to Respondent filed.
PDF:
Date: 08/20/2010
Proceedings: Petitioner's Response to Initial Order filed.
PDF:
Date: 08/18/2010
Proceedings: Initial Order.
PDF:
Date: 08/17/2010
Proceedings: Notice of Appearance (filed by G. Horowitz).
PDF:
Date: 08/17/2010
Proceedings: Administrative Complaint filed.
PDF:
Date: 08/17/2010
Proceedings: Election of Rights filed.
PDF:
Date: 08/17/2010
Proceedings: Agency referral filed.

Case Information

Judge:
ELIZABETH W. MCARTHUR
Date Filed:
08/17/2010
Date Assignment:
08/18/2010
Last Docket Entry:
11/12/2019
Location:
Sarasota, Florida
District:
Middle
Agency:
Other
 

Counsels

Related Florida Statute(s) (12):