11-000236BID
L. Cobb Construction vs.
Hardee County School Board
Status: Closed
Recommended Order on Wednesday, March 30, 2011.
Recommended Order on Wednesday, March 30, 2011.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8L. COBB CONSTRUCTION , )
12)
13Petitioner , )
15)
16vs. ) Case No. 11 - 0236BID
23)
24HARDEE COUNTY SCHOOL BOARD , )
29)
30Respondent . )
33)
34RECOMMENDED ORDER
36Pursuant t o notice, a final hearing was conducted in this
47case on February 18, 2011, in Wauchula, Florida, before
56Administrative Law Judge R. Bruce McKibben of the Division of
66Administrative Hearings.
68APPEARANCES
69For Petitioner: Lavon Cobb, pro se
75Greig Drury , Representative
78L. Cobb Construction
81401 South 6th Avenue
85Wauchula, Florida 33873
88For Respondent: Gavin W. O'Brien, Esquire
945704 Holmes Boulevard
97Holmes Beach, Florida 34217
101STA TEMENT OF THE ISSUES
106This case is a bid protest filed by Petitioner, L. Cobb
117Construction ("Cobb"), to contest the award of a contract by
129Respondent, Hardee County School Board ("School Board"), to
139another bidder to the exclusion of Cobb. The issue is w he ther
152Cobb' s bid was responsive to the bid criteria ; and whether the
164School Board 's award of the bid to another party should be
176deemed clearly erroneous, contrary to competition, arbitrary or
184capricious.
185PRELIMINARY STATEMENT
187On or about October 21, 2010, the School Board issued a Bid
199Proposal for Roof Removal and Replacement. Seven bids were
208received in response to the b id p roposal, and a decision to
221award the contract to Latite Roofing Company ("Latite") was
232published on November 16, 2010. Cobb timely f iled a protest
243with the School Board, and a formal administrative hearing was
253conducted , as set forth above.
258At the final hearing, Cobb called three witnesses: Bill
267Jernigan, Mike Cobb, and Timothy Rink. Cobb did not introduce
277any exhibits into evidenc e. The School Board's Exhibits 2, 3
288(parts 1 and 5), 4, and 9 through 11 were admitted into
300evidence. The School Board called one witness: Scott Bonk.
309The parties advised that a transcript of the proceeding
318would be filed at the Division of Administrati ve Hearings
328("DOAH") and were given ten days from the date of filing the
342transcript to file proposed recommended orders. The Transcript
350was filed on March 4, 2011. The School Board timely filed
361Proposed Findings of Fact and Conclusions of Law, and the
371su bmission was duly considered in the rendering of this
381Recommended Order. As of the date of this Recommended Order,
391Cobb ha s not filed a post - hearing submission.
401FINDINGS OF FACT
404Based on the oral and documentary evidence presented at the
414final hearing and on the entire record of the proceeding,
424including the Amended Joint Pre - Hearing Stipulation of the
434parties, the following Findings of Fact are made:
4421. Cobb is a construction company with decades of
451experience and has been involved with projects for the School
461Board in the past.
4652. The School Board is responsible for bidding out all
475construction projects and must determine the best qualified
483bidder at the lowest price.
4883. The parties agreed to the following facts as set forth
499in their Amended Joint P re - Hearing Stipulation:
508Ʊ A "Bid Proposal for Roof Removal and Replacement"
517advertisement was placed in the Herald - Advocate
525newspaper on October 21, 2010. ( The roof
533replacement will be referred to herein as the
"541Project." )
543Ʊ A mandatory pre - bid meeting a t Wauchula
553Elementary was held for potential roofing
559contractors on October 29, 2010. The meeting was
567led by roofing consultant Scott Bonk and
574Associates ("Bonk").
578Ʊ The School Board received Cobb's bid on the
587Project at 12:34 p.m. , on November 15, 2010.
595Ʊ School Board officials began opening all bids for
604the Project at 1:00 p.m. , on November 15, 2010.
613Ʊ Project bids were received from Cobb, Advanced
621Roofing, Crowther Roofing, Hamilton Roofing,
626Latite Roofing & Sheet Metal, Southern Roofing,
633and THL Roof ing.
637Ʊ Bonk was present at the time the bids were
647opened.
648Ʊ Bonk sent an email to Rob Krahl on November 16,
6592010, concerning Cobb and Latite's bids. Bonk
666advised Krahl that the Cobb bid did not meet the
676specified components , but that the Latite bid met
684all components and timeframes for the Project.
691Ʊ Bonk recommended Latite as contractor for the
699Project.
700Ʊ The School Board approved the recommendation of
708Latite, whose bid was $152,065 for the
716replacement of the roofs on building No s . 5 (the
727e xceptional s tudent e ducation or "ESE" building)
736and 6 (the media center).
741Ʊ On November 17, 2010, Deputy Superintendent Woody
749Caligan faxed School Board Policy 6.07(5),
755entitled Bid Disputes and Procedures, to Cobb.
762Ʊ A Notice to Proceed letter was faxed to Bonk on
773the same date, authorizing Latite to commence the
781Project. A denial letter was also faxed to each
790of the other bidders.
794Ʊ On November 18, 2010, Cobb hand - delivered a
804Notice of Protest to Rob Krahl at the School
813Board.
814Ʊ On November 26, 2010, Cobb mai led a cover letter
825and three original Letters of Protest, along with
833a cashier's check for the protest bond, to Rob
842Krahl.
843Ʊ On November 29, 2010, Cobb faxed a copy of proof
854of postage, School Board Rule 6.07(5), its Letter
862of Protest, and a copy of its p reviously - issued
873cashier's check to Wood Caligan after Caligan
880indicated that he had not received the mailed
888version.
889Ʊ The School Board is the governing entity of the
899school district of Hardee County, Florida.
905Ʊ David Durastanti is the superintendent of schools
913for Hardee County; Woody Caligan is the deputy
921superintendent. Rob Krahl is an employee of the
929School Board and is responsible for facilities
936and construction projects for the school system.
943Barbara Spears is a School Board employee serving
951unde r Krahl. Joann McCray serves as secretary to
960the superintendent. Greg Harrelson is the chief
967financial officer for the school district.
973H arrelson's duties include the receipt, review
980and award of bids for the school district.
9884. A document entitled , " Project Manual , " was issued by
997Bonk relative to the request for bids on the Project. The
1008Project Manual contained the specifications for the Project,
1016including a section entitled , "Bid Form" (comprised of pages 20
1026through 22). The Bid Form is the critica l portion of the
1038Project Manual for purposes of the instant proceeding.
10465. The Bid Form had several blanks to be filled in by the
1059bidding party. The bidder was to fill in the contractor's name,
1070a projected cost for the replacement of both roofs (the ESE
1081building and the media center), a total cost line, a line for
1093the amount of the payment, and a line for the performance bond
1105amount. Following those blanks, there was a section that forms
1115the crux of the dispute in this case. That section provided a
1127spa ce for identification of materials proposed by each bidder.
1137It appeared as follows:
11416. The base bid price is based on the following:
1151A. Manufacturer's Name ________________________
1155B. Base Sheet ________________________
1159C. Intermediate Ply _____ ___________________
1164D. Granulated Ply ________________________
1168E. Insulation Manufacturer ________________________
11727. The responses by Cobb to this section of the Bid Form
1184were deemed inappropriate by Bonk. Latite's responses to this
1193section were dee med appropriate and compliant with the bid
1203requirements.
12048. Cobb's responses were as follows:
1210A. Manufacturer's Name: GAF
1214B. Base Sheet: GAF - Ruberoid Modified Base
1222C. Intermediate Ply: GAF - Ruberoid
1228D. Granulated Ply: GAF - Ruberoid Mop Plus
1236E. Insulation Manufacturer: GAF
12409. Latite's responses were as follows:
1246A. Manufacturer's Name : Soprema
1251B. Base Sheet : Sopra 6
1257C. Intermediate Ply : Elastophene 180 Sanded
1264D. Granulated Ply : Elastophene FR 6R
1271E. Insulation Manufa cturer : GAF (Made by Atlas)
128010. These responses indicate the primary differences
1287between Cobb and Latite's bids. Another important factor (and
1296distinction between Cobb and Latite's bids) was the roof
1305insulation material proposed by each. Cobb proposed u sing
1314Perlite; Latite proposed Sopra Board. These will be discussed
1323more fully herein.
132611. GAF, referenced by both Cobb and Latite in their
1336responses, is the largest roofing manufacturer in the United
1345States. The company is 125 years old and is based in W ayne,
1358New Jersey. A representative of GAF testified at final hearing.
136812. At about the time bids were submitted for the Project,
1379a representative from Bonk's office called GAF to discuss
1388specifications about various GAF products. There were at least
1397two conversations, one of which was generic in nature and one
1408which somewhat addressed the Project specifically.
141413. Bonk determined from the discussions with GAF that
1423neither the Ruberoid Mop Plus proposed by Cobb for its
1433granulated ply , nor the Ruberoid Mo dified Base Sheet portion of
1444the bid was available in Florida. Further, Bonk learned that
1454the Perlite product proposed for the roof insulation by Cobb was
1465inferior to the Sopra Board proposed by Latite. A letter
1475setting forth his findings was sent to the School Board on
1486November 16, 2010.
148914. The Project Manual set forth certain specifications to
1498be used by bidders concerning materials to be used for the
1509Project. The roofing system specifications contained a
1516direction that " [s] hould Soprema products be u sed, the following
1527membrane sheets are required , " and then went on to list the
1538various products that could be used. Latite proposed the use of
1549Soprema products and most of its materials were Soprema brand
1559(except for its insulation, where a GAF brand prod uct was
1570proposed). Cobb, on the other hand, bid GAF products for each
1581of the major Project components.
158615. By using Soprema products, Latite e nsured compliance
1595with the basic specifications set forth in the Project Manual.
1605Generally a project bid sheet w ill contain an ASTM product code
1617number which allows contractors to look at comparable materials
1626from different manufacturers. The Project Manual in this case
1635did not include ASTM codes. Any bidder proposing to use
1645materials made by a company other than Soprema, therefore, would
1655be required to independently determine comparability with the
1663Soprema brand product.
166616. Cobb's proposed materials list included non - Soprema
1675manufactured products. The GAF products proposed by Cobb may
1684generally have been compara ble to the Soprema products, but the
1695evidence is not persuasive as to that fact. Although the GAF
1706representative testified that its products were of high quality
1715and would likely satisfy the requirements for the Project, there
1725was some question as to whet her the items set forth by Cobb in
1739its bid were sufficiently described. Bonk made some inquiry
1748into the matter by contacting GAF, but the hearsay and nebulous
1759nature of those discussions do es not provide sufficient detail
1769for formulation of a finding of f act as to whether the products
1782were of comparable quality.
178617. Cobb proposed a product for the top membrane ply that
1797was constructed using polyester material. The Project Manual
1805called for ply with fiberglass construction. Both are quality
1814products, bu t the polyester material has a tendency to shrink,
1825especially if it is installed incorrectly.
183118. Of the s ix other entities submit ting a bid for the
1844Project, all of them proposed use of Soprema products or
1854materials that were deemed equal in quality. Cobb 's bid was the
1866only bidder whose proposed products were deemed insufficient.
1874One other bidder was also rejected due to time frame issues.
1885None of the other bidders filed a protest or challenged the
1896final decision of the School Board.
190219. The School Board 's stated rationale for rejection of
1912Cobb's bid was that the generic description of Cobb's proposed
1922building materials made it difficult, if not impossible, to
1931ascertain whether they met the standards set forth in the
1941Project Manual. This rationale is nei ther arbitrary nor
1950capricious and is based on sound reasoning.
195720. Cobb's bid, although more generic than the School
1966Board would have liked, was nonetheless a viable bid. Cobb
1976would have been able to explain and make his bid more specific
1988had he been give n the opportunity. However, the School Board
1999did not owe Cobb the right to alter, amend , or explain its bid
2012more fully after the bid process was complete. To do so would
2024give Cobb an inequitable advantage , vis - à - vis , the competing
2036bidders.
203721. It is very likely that Cobb could effectively and
2047professionally complete wo rk on the Project. However, it s bid
2058was not exactly in accordance with the requirements of the
2068Project Manual and w as justifiably rejected in favor of Latite's
2079bid.
2080CONCLUSIONS OF LAW
208322. The Division of Administrative Hearings has
2090jurisdiction over the parties to and the subject matter of this
2101proceeding pursuant to s ections 120.569 and 120.57(1), Florida
2110Statutes (20 10 ). 1/
211523. Subsection 120.57(3)(f) provides in pertinent part:
2122In a prote st to an invitation to bid or
2132request for proposals procurement, no
2137submissions made after the bid or proposal
2144opening which amend or supplement the bid or
2152proposal shall be considered. . . Unless
2159otherwise provided by statute, the burden of
2166proof shall r est with the party protesting
2174the proposed agency action. In a
2180competitive - procurement protest, other than
2186a rejection of all bids, proposals, or
2193replies, the administrative law judge shall
2199conduct a de novo proceeding to determine
2206whether the agency's pr oposed action is
2213contrary to the agency's governing statutes,
2219the agency's rules or policies, or the
2226solicitation specifications. The standard
2230of proof for such proceedings shall be
2237whether the proposed agency action was
2243clearly erroneous, contrary to com petition,
2249arbitrary or capricious.
225224. "A capricious action is one taken without thought or
2262reason or irrationally. An arbitrary decision is one not
2271supported by facts or logic." Agrico Chemical Co. v. Dep't of
2282Envt l ' Reg. , 365 So. 2d 759, 763 (Fla. 1st DCA 1978). In order
2297to prove that an action is arbitrary, capricious, contrary to
2307competition or clearly erroneous, the challenging party is held
2316to a preponderance of the evidence standard. Dep't of Transp.
2326v. Groves - Watkins Constructors , 530 So. 2d 91 2, 913 - 914 (Fla.
23401988).
234125. While section 120.57(3)(f) describes the standard of
2349review as de novo, for the purposes of a protest to a
2361competitive procurement , the courts have viewed the hearing as a
"2371form of inter - agency review." State Contracting & Eng ' g Corp.
2384v. Dep't of Transp. , 709 So. 2d 607, 609 (Fla. 1st DCA 1998)
2397(citing Intercontinental Prop. Inc. v. State Dep't of HRS , 606
2407So. 2d 380 (Fla. 3d DCA 1992)). The object of a bid dispute is
2421to evaluate the action taken by the agency based upon the
2432in formation that was available to the agency at the time it took
2445such action. § 120.57(1).
244926. Both Cobb and Latite submitted generally responsive
2457bids for the Project , which were reviewed by the School Board.
2468The review was done logically, with forethough t and reason. The
2479review was neither arbitrary , nor capricious as carried out by
2489the School Board. Cobb was within its rights to use other than
2501Soprema products , but , in doing so , was bound to submit a
2512proposal for comparable materials.
251627. Within the co ntext of its review of proposals, the
2527owner of the project is generally given the discretion to view
2538projects as a whole and to waive or ignore minor irregularities.
2549A minor irregularity is a variation from the bid invitation or
2560proposal terms and conditi ons, which does not affect the price
2571of the bid or give the bidder an advantage or benefit not
2583enjoyed by other bidders, or does not adversely affect the
2593interests of the governmental entity letting the bid. Liberty
2602Cnty . v. Baxter's Asphalt & Concrete, I nc. , 421 So. 2d 505 (Fla.
26161982).
261728. Cobb's failure to provide a list of products or
2627materials that could be deemed equal to those set forth in the
2639Project Manual's specifications was not a minor irregularity.
2647If the products were inferior or less expensi ve and there is
2659insufficient evidence in the record to determine one way or the
2670other , then Cobb may have had an improper advantage over its
2681competitors.
268229. Agencies enjoy wide discretion when it comes to
2691soliciting and accepting proposals ; and an agency' s decision,
2700when based upon an honest exercise of such discretion, will not
2711be set aside , even where it may appear erroneous or if
2722reasonable people might disagree. Baxter's Asphalt & Concrete,
2730Inc. v. Dep't of Transp . , 475 So. 2d 1284, 1287 (Fla. 1st DCA
27441985). Capelletti Bros . , Inc. v . State, Dep't of Gen . Servs . ,
2758432 So. 2d 1359, 1363 (Fla. 1st DCA 1983). DOAH has a history
2771of upholding an agency's decision if such action was within the
2782realm of reasonableness. See , e.g. , M/A Corn, Inc. v . Dep't of
2794M gmt . Servs . , State Tech . Of c . , Case No. 04 - 1091BID (DOAH
2811May 25, 2004); Hemophilia Health Servs . , Inc. v. A g. f or Hea l th
2827Care Admin. , Case No. 04 - 0017BID (DOAH Apr . 29, 2004); Paul
2840Sierra Constr . , Inc. v. S.W. Fla. Water Mgmt. Dist. , Case
2851No. 02 - 3790BID (D OAH Dec . 4, 2002); Just for Kids, Inc. v. Palm
2867C nt y . Sch . Bd . , Case No. 03 - 2168BID (DOAH Nov . 7, 2003).
288530. There is no evidence in the present case to suggest
2896that the School Board acted in any fashion other than honestly
2907and fairly. The review of compe ting bids was carried out
2918uniformly as it related to each bidder. The award of the
2929contract to Latite was based upon sound reasoning and rationale.
293931. Latite submitted a responsive bid. Cobb's bid
2947contained components which appeared to be less than wha t was
2958desired. Either entity could perform the terms of the contract,
2968but the School Board's decision to award Latite, rather than
2978Cobb, is a matter of discretion and was supported by the facts.
2990It was neither arbitrary, nor capricious, to select Latite as
3000the prevailing bidder.
300332. A decision is considered to be clearly erroneous when
3013although there is evidence to support it, after review of the
3024entire record , the tribunal is left with the definite and firm
3035conviction that a mistake has been committed. U.S. v. U.S.
3045Gypsum Co. , 333 U.S. 3 6 4, 395 (1948). The record in the present
3059case does not support the contention that any mistake was made.
3070RECOMMENDATION
3071Based on the foregoing Findings of Fact and Conclusions of
3081Law, it is
3084RECOMMENDED that a final order be entered by Respondent,
3093Hardee County School Board , upholding its award of the contract
3103to Latite Roofing Company and denying the protest by Petitioner,
3113L. Cobb Construction.
3116DONE AND ENT ERED this 30th day of March , 2011 , in
3127Tallahassee, Leon County, Florida.
3131S
3132R. BRUCE MCKIBBEN
3135Administrative Law Judge
3138Division of Administrative Hearings
3142The DeSoto Building
31451230 Apalachee Parkway
3148Tallahassee, Florida 32399 - 3060
3153(850) 488 - 9675
3157Fax Filin g (850) 921 - 6847
3164www.doah.state.fl.us
3165Filed with the Clerk of the
3171Division of Administrative Hearings
3175this 30th day of March , 2011 .
3182ENDNOTE
31831/ All statutory references are to Florida Statutes (20 10 ),
3194unless otherwise noted.
3197COPIES FURNISHED :
3200Dr. Er ic J. Smith
3205Commissioner of Education
3208Department of Education
3211Turlington Building, Suite 1514
3215325 West Gaines Street
3219Tallahassee, Florida 32399 - 0400
3224Lois Tepper, Acting General Counsel
3229Department of Education
3232Turlington Building, Suite 1244
3236325 West Gain es Street
3241Tallahassee, Florida 32399 - 0400
3246David Durastanti, Superintendent
3249Hardee County School Board
32531009 North 6th Avenue
3257Post Office Box 1678
3261Wauchula, Florida 33873 - 1678
3266Lavon Cobb
3268Greig Drury, Representative
3271L. Cobb Construction
3274401 South 6th Ave nue
3279Wauchula, Florida 33873
3282Rob Krahl
3284Hardee County School Board
32881015 State Road 66
3292Wauchula, Florida 33890 - 3800
3297Gavin W. O'Brien, Esquire
33015704 Holmes Boulevard
3304Holmes Beach, Florida 34217
3308NOTICE OF R IGHT TO SUBMIT EXCEPTIONS
3315All parties have the right to submit written exceptions within
33251 0 days from the date of this Recommended Order. Any exceptions
3337to this Recommended Order should be filed with the agency that
3348will issue the Final Order in this cas e.
- Date
- Proceedings
- PDF:
- Date: 03/30/2011
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 03/11/2011
- Proceedings: School Board's Proposed Findings of Fact and Conclusions of Law filed.
- PDF:
- Date: 03/11/2011
- Proceedings: School Board's (Notice of Filing) Proposed Findings of Fact and Conclusions of Law filed.
- Date: 03/04/2011
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 02/18/2011
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 02/11/2011
- Proceedings: Order Re-scheduling Hearing (hearing set for February 18, 2011; 9:00 a.m.; Wauchula, FL).
- PDF:
- Date: 02/03/2011
- Proceedings: Order Granting Continuance (parties to advise status by February 14, 2011).
- PDF:
- Date: 02/02/2011
- Proceedings: Respondent's Amended Motion for Continuance of Final Hearing filed.
- PDF:
- Date: 01/31/2011
- Proceedings: Amended Notice of Hearing (hearing set for February 9, 2011; 9:00 a.m.; Wauchula, FL; amended as to date of hearing).
- PDF:
- Date: 01/14/2011
- Proceedings: Notice of Hearing (hearing set for February 7, 2011; 9:00 a.m.; Wauchula, FL).
- Date: 01/14/2011
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
Case Information
- Judge:
- R. BRUCE MCKIBBEN
- Date Filed:
- 01/13/2011
- Date Assignment:
- 01/13/2011
- Last Docket Entry:
- 10/16/2019
- Location:
- Wauchula, Florida
- District:
- Middle
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Lavon Cobb
Address of Record -
David Durastanti
Address of Record -
Rob Krahl
Address of Record -
Gavin W. O'Brien, Esquire
Address of Record