11-000538BID
Blue Chip Energy Llc vs.
University Of Central Florida
Status: Closed
Recommended Order on Friday, April 8, 2011.
Recommended Order on Friday, April 8, 2011.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8BLUECHIP ENERGY LLC , )
12)
13Petitioner , )
15)
16vs. ) Case No. 11 - 0538BID
23)
24UNIVERSITY OF CENTRAL FLORIDA , )
29)
30Respondent . )
33)
34RECOMMENDED ORDER
36Pursuant to notice, a final hearing was held in this case
47on February 18, 2011, in Orlando, Florida, before Susan B.
57Harrell, a n Administrative Law Judge of the Division of
67Administrative Hearings.
69APPEARANCES
70For Petitioner: Thomas Gregory, Qualified Representative
76Dimitri Nikitin
78BlueChip Energy, LLC
81400 Rinehart Road, No. 1060
86Lake Mary, Florida 32746
90For Respondent: Jordan P. Clark, Esquire
96University of Central Florida
1004000 Central Florida Boulevard
104Post Office Box 160015
108Orlando, Florida 32816
111Richard E. Mitchell, Esquire
115GrayRobinson, P.A.
117Post Office Box 3068
121Orlando, Flo rida 32802
125STATEMENT OF THE ISSUE
129The issue in this case is whether Respondent's intended
138decision to reject Petitioner's bid for University of Central
147Florida (UCF) Invitation to Bid No. 1030LCSAR (ITB) was
156arbitrar y, unreasonable, or capricious.
161PRELI MINARY STATEMENT
164Respondent, U C F, issued ITB No. 1030LCSAR for photovoltaic
174systems for emergency systems. Petitioner, BlueChip , LLC
181(BlueChip) , submitted a bid. By letter dated November 19, 2010,
191U C F notified BlueChip that its bid was being rejected. B y
204letter dated November 20, 2010, BlueChip advised UCF that
213BlueChip was concerned that its bid was rejected and wanted a
224clear explanation for the reasons for rejection. The letter did
234not indicate that it was a notice of protest . By letter dated
247Novemb er 24, 2010, BlueChip wrote to UCF and addressed each of
259the grounds set forth in UCF's letter dated November 19, 2010.
270The second letter did not specifically request an administrative
279hearing, but stated: "[W]e insist UCF immediately reinstate and
288recon sider our bid."
292By letter dated January 26, 2011, UCF sent the two letters
303to the Division of Administrative Hearings and requested that
312the Division of Administrative Hearings conduct a bid protest
321hearing. However, UCF specifically preserved any objecti ons to
330the letters, including whether the letters constituted a bid
339protest in conformance with UCF regulations.
345At the final hearing, the following witnesses were
353presented by BlueChip: Andrew N. White, D i mitri Nikitin, and
364Thomas Gregory. Petitioner's Exhibits 1, 2, 3, 4, 6, 8, 9, 11,
376and 12 were admitted in evidence. Petitioner's Exhibits 5, 7,
386and 10 were not accepted in evidence. UCF called the following
397witnesses: Luis Aviles, Mary C. Huggins, and David K. Click .
408Respondent's Exhibits 1, 2, 3, 5, 6, 7, 8, 9, 10, 11, 17, 21,
42222, 23, 24, and 29 were admitted in evidence.
431The two - volume Transcript was filed on March 8, 2011. On
443March 18, 2011, the parties filed their Proposed Recommended
452Orders, whic h have been considered in the preparation of this
463Recommended Or der.
466FINDINGS OF FACT
4691. UCF received a grant for $10,000,000.00 through the
480United States Department of Energy pursuant to the American
489Recovery and Reinvestment Act (ARRA) for, among other things,
498the construction and installation of turnkey 10kW PV systems
507wi th battery back up at schools located in Florida and designated
519as emergency shelters. Part of the grant money was to be used
531for administration and for education of Florida school chil dren
541concerning renewable energy sources and energy efficiency.
5482. In order to procure the construction and installation
557of the PV systems, UCF issued the ITB. This was the second
569invitation to bid issued for PV systems. The first invitation
579to bid was issued during the summer of 2010, and all the bids
592received were over budget.
5963. The introduction in the ITB provides:
603As part of the Florida SunSmart Schools
610Emergency Shelter Program, the University of
616Central Florida intends to purchase at lea st
624ninety (90) turnkey installations of 10 kWdc
631(minimum) grid - tied photovoltaic (PV)
637systems with battery backup for specified
643Florida schools designated as EHPA (Enhanced
649Hurricane Protection Area) emergency
653shelters. This program provides for
658emergency electrical power for critical
663loads and provides ongoing educational
668programs for students. UCF/Florida Solar
673Energy Center will select the schools at
680which the PV systems will be installed. It
688is expected that at least one system will be
697installed in e ach County in the State of
706Florida.
707It is anticipated that multiple Bidders will
714be selected for participation in this
720program. One bidder will be selected for
727each Region, as defined in the Bid Document.
735A Bidder may be awarded more than one
743Region.
744A ll PV modules and systems must be certified
753by the Florida Solar Energy Center as
760specified in the bid document.
7654. The Florida Solar Energy Center (FSEC) is a statutory
775affiliate of UCF which "develop[s] and promulgate[s] standards
783for solar energy sys tems manufactured or sold in this state
794based on the best currently available information and shall
803consult with scientists, engineers, or persons in research
811centers who are engaged in the construction of, experimentation
820with, and research of solar energ y systems to properly identify
831the most reliable designs and types of solar energy systems."
841§ 377.705(4)(a), Fla. Stat. (2010). 1/ All solar equipment that
851is sold or manufactured in the S tate of Florida must be
863certified by FSEC. § 377.705(4)(d).
8685. Bl ueChip was among the 19 bidders, which submitted bid s
880in response to the ITB. On November 19, 2010, UCF posted the
892intent to award the contract for all regions to Vergona - Bowersox
904Electric, Incorporated (Vergona - Bowersox). By letter dated
912November 19, 20 10, UCF notified BlueChip that its bid was
923rejected for a number of deficiencies. The Sunny Island
932inverter, which BlueChip included in the system it bid, is not
943made in America, and, therefore, does not comply with the Buy
954America provision of the ITB. Sunny Boy inverters, which
963BlueChip included in the system it bid, are undersized and do
974not meet the specifications of the ITB. The batteries used in
985BlueChip's bid do not meet the specifications of the ITB. FSEC
996did not receive a PV System Certificatio n Application from
1006BlueChip as required by the ITB. BlueChip does not hold a solar
1018contractor license, nor does it hold an electrical contract or
1028license as required by the ITB.
10346. By letter dated November 20, 2010, Dimitri Ni k itin
1045(Dr. Nikitin) , presiden t of BlueChip, wrote to UCF concerning
1055the rejection of BlueChip's bid. The letter stated in part:
1065On behalf of BlueChip Energy, LLC, which
1072submitted a bid for the SunSmart Emergency
1079Shelters project on November 8, I would like
1087to express my concerns and ask for
1094clarification regarding the Intent to Award
1100notice for UCF Bid 1030lcsar posted on the
1108UCF Purchasing website on November 19.
1114First, we would like a written explanation
1121why UCF rejected BlueChip Energy's bid. Our
1128bid followed the requirements of the ITB to
1136the letter, including compliance with the
1142Buy America Act and ability t o provide a
1151payment and performance bond.
1155* * *
1158We would like to receive a clear explanation
1166of why the only solar panel manufacturing,
1173engineering and Installation Company in
1178Florida with first hand PV module
1184manufacturing experience and multi - Megawatt
1190international install base was simply
1195rejected as a bidder. To find out the
1203reasons for your decision we will initiate a
1211media investigation and congressional and
1216Fl orida Energy Commission inquiry into the
1223administration of UCF bid 1030LCSAR, and the
1230possible conflict of interests of UCF
1236employees and related parties.
1240Your timely response to our questions and
1247concerns is very much appreciated.
12527. The BlueChip lette r dated November 20, 2010, did not
1263state that it was intended to be a Notice of Protest. By letter
1276dated November 24, 2010, BlueChip responded to each of the
1286deficiencies listed in UCF's letter to BlueChip dated
1294November 19, 2010. BlueChip's letter dated November 24, 2010,
1303did not state that the letter was supposed to be a formal
1315protest, but did state:
1319Due to the spurious and baseless nature of
1327the issues raised by your November 19 letter
1335we insist UCF immediate ly reinstate and
1342reconsider our bid. In the absence of that
1350we will have no choice but to initiate a
1359media investigation and congressional and
1364Florida Energy Commission inquiry into the
1370administration of ECF [sic] bid 1030LCSAR
1376and the possible conflict o f interest of UC F
1386employees and related parties.
1390Additionally, the November 24, 2010, letter did not include a
1400protest bond.
14028. Appendix II, section 13 , of the ITB provides:
141113. Compliance with the Buy America
1417Recovery Act Provisions (Section 1605 of
1423Title XVI) --
1426By accepting funds under this Agreement
1432[State of Florida Grant Assistance Pursuant
1438to American Recovery and Reinvestment Act],
1444the Grantee [UCF] agrees to comply with
1451sections [sic] Section 1605 of the American
1458Recovery and Reinvestment Act (ARRA)." The
1464Grantee should review the provisions of the
1471Act to ensure that expenditures made under
1478this Agreement are in accordance with it.
1485The Buy American provision in the American
1492Recovery and Reinvestment Act of 2009
1498(section 1605 of title XVI), pr ovides that,
1506unless one of the three listed exceptions
1513applies (nonavailability, unreasonable cost,
1517and inconsistent with the public interest),
1523and a waiver is granted, none of the funds
1532appropriated or otherwise made available by
1538the Act may be used for a project for the
1548construction, alteration, maintenance, or
1552repair of a public building or public work
1560unless all the iron, steel, and manufactured
1567goods are produced in the United States.
15749. On September 30, 2010, the United States Department of
1584Energy granted a limited waiver of the Buy America provision of
1595ARRA with respect to certain PV equipment. The waiver provided:
1605This amended public interest determination
1610waives the Buy American requirements of
1616EERE - funded Recovery Act projects for the
1624purchase of the following solar PV
1630equipment: (1) Domestically - manufactured
1635modules containing foreign - manufactured
1640cells, (2) foreign - manufactured modules,
1646when completely comprised of domestically -
1652manufactured cells, and (3) any ancillary
1658items and equipment (in cluding but not
1665limited to, charge controllers, combiners,
1670and disconnect boxes, breakers, fuses,
1675racks, lugs, wires, cables and all otherwise
1682incidental equipment with the exception of
1688inverters and batteries) when utilized in a
1695solar installation involvi ng a U.S.
1701manufactured PV module or a module
1707manufactured abroad but comprised
1711exclusively of domestically - manufactured
1716cells. ( e mphasis added ) .
172310. BlueChip's bid specifies inverters manufactured by SMA
1731America Solar Technologies, Inc. (SMA), specifica lly SMA's Sunny
1740Boy 4000US inverter and Sunny Island 5048US inverter. SMA's
1749Sunny Island 5048US inverter is made in Germany, not the United
1760States. The United States Office of Management and Budget (OMB)
1770has issued interim final guidance , directing that the Buy
1779American provision shall not be applied where the iron, steel,
1789or manufactured goods used in the project are subject to an
1800international agreement. The recipient of ARRA funds is to
1809treat the goods subject to an international agreement the same
1819as domestic goods and services. In Florida, only executive
1828branch agencies may invoke the United States' international
1836trade agreement s . State of Florida universities may not
1846participate in the international trade agreements.
185211. The total bid of BlueChip was $6,383,811.00. The
1863value of the contract awarded to Vergona - Bowersox pursuant to
1874the ITB was $6,720,896.70.
188012. Appendix 1, section 2(C)(8) , of the ITB states: "The
1890battery bank shall have a minimum usable capacity (at C/100) of
190125kWh. " BlueChip's bid specifies a battery bank capable of
1910producing and delivering a maximum energy output of 24 volts to
1921its specified Sunny Island 5048US inverter. In order to turn on
1932and function, the Sunny Island 5048US inverter requires a
1941minimum energy input of 41 v olts from the battery bank. The
195324 volts produced by the battery bank specified by BlueChip is
1964insufficient to turn on the inverter. Therefore, the PV system
1974bid by BlueChip would not be functional and would not meet the
1986minimum usable capacity required by the ITB , because the
1995inverter could not be activated by the battery bank.
200413. Appendix 1, section 2(C)(8) , of the ITB provides the
2014following requirements:
2016PV systems must be capable of parallel
2023operation with the utility supplied
2028electrical service to the facility. The
2034entire PV system must also be capable of
2042stand - alone operation, providing backup
2048power to a critical load panel when the
2056utility supplied electrical service is
2061unavailable. Systems will be grid -
2067interactive, providing power to a collecti on
2074of pre - determined critical loads.
208014. BlueChip's electrical schematic is non - conforming to
2089the ITB , because it does not properly allow for the required
2100operation with the utility supplied electrical service to the
2109facility and is not capable of a stan d - alone operation,
2121providing backup power to a critical load panel when the utility
2132supplied electrical service is unavailable.
213715. BlueChip's bid specifies a PV array capable of
2146producing and delivering a maximum energy output of
2154approximately 90 volts t o its specified Sunny Boy 4000US
2164inverter. In order to turn on and function, the Sunny Boy
21754000US inverter requires a minimum energy input of 295 volts
2185from the PV array. Therefore, the system bid by BlueChip cannot
2196turn on the Sunny Boy 4000US inverter included in BlueChips's
2206system, which makes the system nonfunctional.
221216. BlueChip's bid contains a schematic showing a Sunny
2221Boy 4000US inverter with two DC inputs and two AC outputs.
2232Sunny Boy 4000US inverters have only one DC input connection and
2243one AC output connection. Based on the schematic submitted by
2253BlueChip, the system is nonfunctional.
225817. The ITB provides that UCF may waive "any minor
2268irregularity." BlueChip contends that any technical issues with
2276the system bid could be corrected by FSEC during the
2286certification process after the bids were opened and the
2295intended award was announced.
229918. Appendix 1 , section 1(C)(1) , of the ITB provides:
2308Bidders will serve as the prime contractor
2315and must be licensed to install photovoltaic
2322systems in the State of Florida. Bidder
2329must hold a valid license as a certified
2337solar contractor or electrical contractor,
2342per Chapter 489, Florida Statutes. General
2348Contractors may not serve as a prime
2355contractor for the installation of a
2361photovoltaic system due to the limitations
2367provided in Section 489.113(3), Florida
2372Statutes. Bidders may include
2376subcontractors as deemed necessary, but
2381subcontractors must be iden tified in the bid
2389response, with a description of the work to
2397be performed by each subcontractor. A
2403successful Bidder will be solely responsible
2409for fulfilling the terms of award.
241519. BlueChip submitted the bid and identified itself as
2424the prime contrac tor in its bid. In its bid , BlueChip
2435identified Advanced Solar Photonics and Complete Electrical
2442Contractors as wholly - owned subsidiaries of BlueChip. BlueChip
2451purchased Complete Electric Contractors, Inc., and the name was
2460changed to Complete Electric C ontractors, LLC. On January 5,
24702010, Complete Electric Contractors, LLC , registered to do
2478business under the fictitious name of BlueChip Energy.
248620. No evidence was presented at the final hearing that
2496BlueChip was a certified solar contractor or that Bl ueChip was
2507registered or certified pursuant to section 489.521, Florida
2515Statutes.
251621. BlueChip contends that BlueChip me e ts the requirement
2526as an electrical contractor , because Complete Electrical
2533Contractors, Inc. , was registered as a business performing
2541electrical contracting with Andrew White (Mr. White) as the
2550qualifying agent and is a wholly - owned subsidiary of BlueChip.
2561Complete Electrical Contractors, LLC, is the wholly - owned
2570subsidiary of BlueChip and is a separate legal entity from
2580BlueChip . The bid was not submitted by Complete Electrical
2590Contractors, LLC, or by Complete Electrical Contractors, Inc.
2598Additionally, Mr. White is the qualifying agent for Complete
2607Electrical Contractors, Inc., not Complete Electrical
2613Contractors, LLC.
261522. BlueChip did not list Complete Electrical Contractors,
2623LLC, as a subcontractor in its bid.
263023. Appendix 1, section 1(D) , of the ITB provides that , if
2641a bidder chooses not to use a PV system that is not already
2654certified by FSEC, the bidder is responsible for submi tting an
2665application for system certification. There is a special
2673application process in FSEC for applications that are being made
2683as part of a bid solicitation process. The applications are
2693submitted, but the processing fee is not required at the time o f
2706the submittal of the application , and only the applications for
2716bidders selected for a contract will be certified.
272424. The directions for submittal of the applications for
2733certification are contained in Appendix 1, section 1(4) , of the
2743ITB, which provid es:
27474. IMPORTANT : The Florida Solar Energy
2754Center has established a modified
2759application process for certifying PV
2764systems for this program only. The
2770following process should be followed
2775carefully to qualify for this offer.
2781a. On or before the deadli ne date of the
2791ITB, Bidder must complete and electronically
2797submit (see ii below) the Photovoltaic
2803System Certification -- SunSmart E - Shelter
2810Program Application form available at:
2815http://www.fsec.ucf.edu/en/education/
2816sunsmart/e - shelters/documents/
2819EShelter Application.pdf . Applications
2823submitted under previous solicitations will
2828not be considered under this program. Only
2835certification applications submitted through
2839the current bid process will be considered.
2846i. Only fully completed applications will
2852be accepted for consideration under this
2858program. The application must include all
2864required documentation to be considered
2869complete. All materials must be submitted
2875electronically to FSEC in a single email.
2882FSEC will not accept partial submissions.
2888All em ail attachments must be in PDF format.
2897ii. All certification applications must be
2903sent to pvshelter@fsec.ucf.edu . A complete
2909electrical schematic that includes the
2914following information is required as part of
2921the system certification package. (This
2926lis t is provided for guidance and assistance
2934only and is not the only information
2941required in the certification application.)
29461) Modules labeled and shown in correct
2953array configuration (source circuits)
29572) Size, type, and location of all
2964conductors ( c, - dc, L1, L2, L3, N, G,
2974etc.) in the system
29783) Complete circuit paths shown
29834) Size, current rating, voltage rating,
2989and location of all over - current protection
2997devices
29985) Inverter/Charger/Controller equipment
3001correctly identified
30036) Data acquisition system (DAS)
3008[monitoring equipment] identified
30117) Battery wiring and cables labeled and
3018shown in correct bank configuration
30238) Complete details of the system grounding
3030in compliance with NEC 690 V. Grounding
30379) Point of interconnection sp ecified and
3044in compliance with NEC 690.64(B)(7)
304910) Ratings and locations of all
3055disconnects
3056iii. Incomplete applications will be
3061rejected and the applicant's system and bid
3068may be ineligible for an award under this
3076program. The applicant will be so n otified
3084but application materials will not be
3090returned to the applicant.
309425. The system bid by BlueChip had not been certified by
3105FSEC. BlueChip was required to submit an application to FSEC as
3116part of the bid process. BlueChip had submitted applicatio ns to
3127FSEC as part of the previous solicitation for PV systems for
3138emergency systems, which had been cancelled in October 2010. At
3148the final hearing, Dr. Nikitin testified that he had submitted
3158other applications for the ITB; however, the only receipt tha t
3169he could produce was for a n email delivery dated August 23,
31812010, which was before the ITB was issued. The totality of the
3193evidence does not establish that BlueChip sent an application by
3203email to FSEC for the ITB. BlueChip did include with its bid
3215two applications submitted in response to the previous
3223invitation to bid. One application was dated
3230July 28, 2010, and one was dated August 19, 2010. Because
3241BlueChip submitted no application to FSEC for the ITB by email,
3252FSEC evaluated the technical aspect of BlueChip's bid based on
3262the application submitted with the bid.
326826. BlueChip asserted in its letters to UCF, dated
3277November 20, 2010, and November 24, 2010, that there had been a
3289conflict of interest concerning a member of the Policy Advisory
3299Board of FSEC and Vergona - Bowersox. However, no evidence was
3310presented to support this assertion.
3315CONCLUSIONS OF LAW
331827. The Division of Administrative Hearings has
3325jurisdiction over the parties to and the subject matter of this
3336proceeding. § 120.65(7), Fla. S tat.
334228. UCF Regulation 7.130(5) sets forth the procedures for
3351solicitation and provides:
3354(5) Solicitation Protest Procedures
3358(a) Any qualified offeror who is adversely
3365affected by the university's decision may
3371file a written notice of intent to protes t
3380within 72 hours after university posting of
3387award or intent to award notice. The
3394protesting firm must reduce its complaint to
3401a written protest and file it with the
3409department that issued the solicitation
3414within ten (10) calendar days from
3420registration of the original complaint. The
3426bond shall be included with the formal
3433written protest.
3435(b) The notice of protest shall contain the
3443following information:
34451. The notice must be addressed to the
3453department that issued the solicitation or
3459that made a decision that is intended to be
3468protested;
34692. The notice must identify the
3475solicitation by number and title and any
3482other language that will allow for
3488identification; and
34903. The notice must state that the person
3498intends to protest the decision.
3503(c) T he "formal written protest" required
3510by BOG regulation 18.002 is a petition that
3518states with particularity the facts and law
3525upon which the protest is based. The formal
3533protest shall be filed with the office
3540issuing the competitive solicitation within
3545ten (10) calendar days of the notice of
3553intent to protest. The formal written
3559protest shall con tain the following
3565information:
35661. The name of the protestor;
35722. A statement of when and how the
3580protestor received notice of the
3585University's action or propos ed action;
35913. An explanation of how the protestor's
3598substantial interests are or will be
3604affected by the action or proposed action;
36114. A statement of all material facts
3618disputed by the protestor or a statement
3625that there are no disputed facts;
36315. A s tatement of the facts alleged,
3639including a statement of the specific facts
3646the protestor contends warrant reversal or
3652modification of the university's proposed
3657action;
36586. A statement of the specific regulations
3665or statutes that the protestor contends
3671req uire reversal or modification of the
3678university's proposed action, including an
3683explanation of how the alleged facts relate
3690to the specific regulations or statutes;
36967. A statement of the relief sought by the
3705protestor, stating precisely the action
3710protes tor wishes the agency to take with
3718respect to the proposed action.
3723(d) The failure to adhere to filing
3730deadlines will result in the rejection of
3737the protest.
373929. UCF Regulation 7.130(4)(c) requires that a protest
3747bond be submitted with the formal written protest and states:
3757Solicitation Protest Bond. Any contractor
3762that files a formal written protest pursuant
3769to the protest procedures of BOG Regulation
377618.002 and this regulation (see section (5)
3783below) protesting a decision or intended
3789decision pe rtaining to a solicitation, shall
3796at the time of filing of the formal protest,
3805post with the University a bond payable to
3813the University in an amount equal to 10% of
3822the estimated value of the protestor's bid
3829or proposal; 10% of the estimated
3835expenditure d uring the contract term;
3841$10,000; or whichever is less. The bond
3849shall be conditioned upon payment of all
3856costs which may be adjudged against the
3863contractor filing the protest action. In
3869lieu of a bond, the University may accept a
3878cashier's check or mone y order in the amount
3887of the bond. Failure to file a protest in
3896accordance with BOG regulation 18.002 or
3902failure to po s t the bond or other security
3912as required by the BOG regulation 18.003,
3919shall const itute a waiver of proceedings.
392630. BlueChip's letter dated November 20, 2010, did not
3935advise UCF that BlueChip was intending to protest the notice of
3946the award of the contract for PV systems to Vergona - Bowersox.
3958The letter asked for an explanation of why BlueChips's bid was
3969rejected and cited various conce rns about the rejection of
3979BlueChip's bid. The letter was not sufficient to put UCF on
3990notice that BlueChip was protesting the intended award. UCF
3999Regulation 7.130 clearly requires that the notice of protest
4008state that the bidder intends to protest the d ecision.
401831. If the letter dated November 19, 2010, were deemed to
4029be the notice of protest and the letter dated November 24, 2010,
4041were deemed to be the formal written protest, BlueChip did not
4052submit the required protest bond with the November 24, 2010,
4062letter as required by UCF Regulation 7.130(4) and has thus
4072waived any protest.
407532. Assuming arguendo that BlueChip's letter of
4082November 19, 2010, is deemed to be sufficient as a notice of
4094protest and a bid protest bond had been included with the
4105November 24, 2010, letter, BlueChip's bid fails to meet the
4115requirements of the ITB in numerous respects.
412233. The ITB provides that the bidders must abide by the
4133Buy America requirement of the A R RA. BlueChip 's bid included
4145SMA's Sunny Island 5048US inverter, whi ch is made in Germany.
4156Although the ARRA provides for a Buy American requirement, it
4166also provides that the Buy American requirement be applied in a
4177manner consistent with United States' obligations under
4184international agreements. Thus, goods purchased p ursuant to an
4193international agreement are to be considered the same as
4202domestic goods and services. Two C.F.R. section 176.90
4210provides:
4211The Buy American requirement set out in
4218§ 176.70 shall not be applied where the
4226iron, steel, or manufactured goods used in
4233the project are from a Party to an
4241international agreement, listed in paragraph
4246(b)(2) of this section, and the recipient of
4254is required under an international
4259agreement, described in the appendix to this
4266subpart, to treat the goods and services of
4274tha t Party the same as domestic goods and
4283services. This obligation shall only apply
4289to projects with an estimated value of
4296$7,443,000 or more and projects that are not
4306specifically excluded from the application
4311of those agreements.
431434. Article IX, s ection 7 , of the Florida Constitution
4324provides that there shall be a single state university system
4334that is comprised of all public universities, which includes
4343UCF. The state university system is not include d in the
4354executive branch of government. Appendix to subpart B of
43632 C.F.R . part 176 lists the state entities that are subject to
4376United States obligations under international agreements. Only
4383the executive agencies of the State of Florida are subject to
4394the World Trade Organization Government Procurement A greement,
4402which includes Germany. Thus, UCF is not exempt from the Buy
4413America provision of ARRA because of an international agreement.
442235. Even if UCF were considered to be obligated to abide
4433by international agreements, the project amount is less than
4442$7,443,000 .00 . BlueChip contends that the project amount is the
4455entire grant amount of $10,000,000 .00 . The project is
4467considered to be the construction, alteration, maintenance, or
4475repair of a public building. 2 C.F.R. § 176.70(a). The project
4486at issu e is the alteration of school buildings to include PV
4498systems for schools designated as emergency shelters. A school
4507building is a public building. Therefore, the project amount is
4517insufficient to exempt UCF from the Buy America provision s of
4528the ARRA.
45303 6. BlueChip did not meet several technical requirements
4539of the ITB. The battery bank and the Sunny Island 5048US
4550inverter bid by BlueChip are not compatible because the battery
4560bank does not have sufficient energy output to start the
4570inverter ; therefore, the system bid will not function.
457837. The electrical schematic submitted by BlueChip does
4586not properly allow for the operation with the utility supplied
4596electrical service to the facility as required by the ITB. The
4607electrical schematic does not show th at the system is capable of
4619stand - alone operation, with backup power to a critical load
4630panel when the utility supplied electrical service is
4638unavailable as required by the ITB.
464438. BlueChip stated that its system was capable of
4653producing a maximum energy output of 90 volts to the Sunny Boy
46654000US inverter, which BlueChip included in its system.
4673However, the Sunny Boy 4000US inverter requires a minimum of
4683285 volts in order to turn on and work. Additionally, the Sunny
4695Boy 4000US inverter does not have th e number of DC inputs and AC
4709outputs as specified in BlueChip's bid. Essentially, the use of
4719the Sunny Boy 4000US inverter as set forth in BlueChip's bid
4730will result in a nonfunctional system.
473639. BlueChip contends that these errors could be corrected
4745by FSEC during the certification process after the bids were
4755opened and the intended award was announced. BlueChip's
4763contention is without merit. In Wester v. Belote , 138 So. 721,
4774723 - 24 (Fla. 1931), the court described the object and purpose
4786of fundamental policies underlying competitive procurement and
4793stated:
4794[T]he object and purpose of [the policies
4801underlying competitive procurement] is to
4806protect the public against collusive
4811contracts; to secure fair competition upon
4817equal terms to all bidde rs; to remove not
4826only collusion but temptation for collusion
4832and opportunity for gain at public expense;
4839to close all avenues to favoritism and fraud
4847in its various forms; to secure the best
4855values for the [governmental agency] at the
4862lowest possible expe nse, and to afford an
4870equal advantage to all desiring to do
4877business with the [governmental agency] by
4883affording an opportunity for an exact
4889comparison of bids.
489240. The ITB provides that UCF may waive "any minor
4902irregularities." A variance from the bid specifications is
4910considered minor if it does not give a bidder a competitive
4921advantage over another bidder. See Intercontinental Properties,
4928Inc. v. Dep ' t of HRS , 606 So. 2d 380 (Fla. 3d DCA 1992);
4943Trobabest Foods, Inc. v. Dep ' t of Gen . Servs . , 493 So. 2d 50
4959(Fla. 1st DCA 1986); and Robinson Electrical Co., Inc. v. Dade
4970C nty . , 417 So. 2d 1032 (Fla. 3d DCA 1982).
498141. The failure to bid a system that would work is not a
4994minor irregularity. To allow BlueChip to bid a nonfunctional
5003system and make corrections to the system after the bids were
5014opened in order to make the system functional would give
5024BlueChip an unfair advantage over the other bidders.
503242. BlueChip did not meet the ITB requirement that it hold
5043a valid license as a certified solar con tractor or electrical
5054contractor. No evidence was presented that BlueChip was
5062registered or certified as a business conducting electrical
5070contracting as required by section 489.521 or that it held a
5081valid license as a certified solar contractor. BlueChip relied
5090upon the electrical contractor license of Mr. White as the
5100qualifying agent for Complete Electric Contractors, Inc., as
5108meeting the license requirement for a certified electrical
5116contractor. BlueChip's contention is without merit. Complete
5123Electr ical Contractors, Inc., for whom Mr. White is the
5133qualifying agent, no longer exists and was changed to a limited
5144liability corporation. Complete Electrical Contractors, LLC, is
5151a separate legal entity from BlueChip, did not submit the bid,
5162and was not li sted as a subcontractor in BlueChip's bid.
517343. BlueChip did not submit an application for
5181certification to FSEC as required by the ITB. It did submit an
5193application for the previous invitation to bid. However, the
5202ITB provides that applications submitte d for previous
5210procurements would not be acceptable. FSEC did evaluate the
5219applications submitted with the bid, which were the applications
5228submitted for the previous invitation to bid, and found that
5238BlueChip's bid was nonresponsive.
524244. In Sutron Corp . v. Lake County Water Authority , 870
5253So. 2d 930, 932 - 933 (Fla. 5th DCA 2004), the court stated:
5266It is well established in Florida that a
5274public entity's rejection of contract bids
5280will be affirmed when challenged in court,
5287unless the action of the public b ody was
5296arbitrary, unreasonable or capricious. Even
5301if the public entity makes an erroneous
5308decision about which reasonable people may
5314disagree, the discretion of the public
5320entity to solicit, accept and or reject
5327contract bids should not be interfered wi th
5335by the courts, absent a showing of
5342dishonesty, illegality, fraud, oppression or
5347misconduct. See Scientific Games v. Dittler
5353Brothers, Inc. , 586 So. 2d 1128 (Fla. 1st
5361DCA 1991); City of Cape Coral v. Water
5369Services of America , 567 So. 2d 510 (Fla. 2d
5378DCA 1990); Capeletti Brothers v. State Dept.
5385of General Services , 432 So. 2d 1359 (Fla.
53931st DCA 1983).
539645. A decision is arbitrary if it is not supported by fact
5408or logic. A decision is capricious if it is taken without
5419thought or reason. In determinin g whether an agency has acted
5430arbitrarily or capriciously, consideration should be given to
5438the following factors: (1) has the agency considered all
5447relevant factors; (2) has the agency given actual, good faith
5457consideration to those factors; and (3) has the agency used
5467reason rather than whim to progress from consideration of those
5477factors to its final decision. Adam Smith Enterprises, Inc. v.
5487State Dep ' t of Envtl . Reg . , 553 So. 2d 1260, 1273 (Fla. 1st DCA
55041989). A decision is neither arbitrary nor capricious if the
5514decision is justifiable under any analysis that a reasonable
5523person would use to reach a decision of similar importance.
5533Dravco Basic Materials Co., Inc. v. State Dep ' t of Tra nsp . , 602
5548So. 2d 632, 634 n.3 (Fla. 2nd DCA 1992).
555746. UCF's decision to reject BlueChip's bid is not
5566arbitrary or capricious. BlueChip's bid was evaluated and found
5575nonresponsive. The decision to reject BlueChip's bid is
5583reasonable based on BlueChip's failure to adhere to the
5592specifications of the ITB.
5596RECOMMENDATION
5597Based on the foregoing Findings of Fact and Conclusions of
5607Law, it is RECOMMENDED that a final order be entered finding
5618that BlueChip failed to submit a notice of protest in accordance
5629with UCF Regulation 7.130 ; finding that the rejection of
5638BlueChip's bid is not arbitrary, unreasonable, or capricious ;
5646and rejecting BlueChip's bid.
5650DONE AND ENTERED this 8th day of April , 2011 , in
5660Tallahassee, Leon County, Florida.
5664S
5665SUSAN B. HARRELL
5668Administrative Law Judge
5671Division of Administrative Hearings
5675The DeSoto Building
56781230 Apalachee Parkway
5681Tallahassee, Florida 32399 - 3060
5686(850) 488 - 9675
5690Fax Filing (850) 921 - 6847
5696www.doah.state.fl.us
5697Filed with the Clerk of the
5703Division of Administrative Hearings
5707this 8th day of April , 2011 .
5714ENDNOTE
57151/ Unless otherwise stated, all references to the Florida
5724Statutes are to the 2010 version.
5730COPIES FURNISHED :
5733Thomas Gregory
5735Dimitri Nikitin
5737BlueChip Energy, LLC
5740400 Rinehart Road, No. 1060
5745Lake Mary, Florida 32746
5749Jordan P. Clark, Esquire
5753University of Central Florida
57574000 Central Florida Boulevard
5761Post Office Box 160015
5765Orlando, Florida 32816
5768Richard E. Mitchell, Esquire
5772GrayRobinson, P.A.
5774Post O ffice Box 3068
5779Orlando, Florida 32802
5782NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5788All parties have the right to submit written exceptions within
579810 days from the date of this Recommended Order. Any exceptions
5809to this Recommended Order should be filed with the agency that
5820will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 04/08/2011
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- Date: 03/08/2011
- Proceedings: Transcript of Proceedings Volume I and II (not available for viewing) filed.
- Date: 02/18/2011
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 02/17/2011
- Proceedings: Respondent UCF's Opposed Amended Motion for Leave for Witness to Appear by Telephone filed.
- PDF:
- Date: 02/17/2011
- Proceedings: Respondent UCF's Motion for Leave for Witness to Appear By Telephone filed.
- PDF:
- Date: 02/16/2011
- Proceedings: Letter to DOAH from T. Gregory regarding bluechip energy bid compliant filed.
- PDF:
- Date: 02/16/2011
- Proceedings: Amended Notice of Hearing (hearing set for February 18, 2011; 9:00 a.m.; Orlando, FL; amended as to authority).
- PDF:
- Date: 02/03/2011
- Proceedings: Notice of Hearing (hearing set for February 18, 2011; 9:00 a.m.; Orlando, FL).
- Date: 02/02/2011
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
Case Information
- Judge:
- SUSAN BELYEU KIRKLAND
- Date Filed:
- 01/31/2011
- Date Assignment:
- 01/31/2011
- Last Docket Entry:
- 10/17/2019
- Location:
- Orlando, Florida
- District:
- Middle
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
Jordan P. Clark, Esquire
Address of Record -
Richard E. Mitchell, Esquire
Address of Record -
Dimitri Nikitin
Address of Record