11-000538BID Blue Chip Energy Llc vs. University Of Central Florida
 Status: Closed
Recommended Order on Friday, April 8, 2011.


View Dockets  
Summary: Petitioner's bid was not responsive to the ITB specification, and the letter purporting to be a notice of protest did not comply with UCF rules.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8BLUECHIP ENERGY LLC , )

12)

13Petitioner , )

15)

16vs. ) Case No. 11 - 0538BID

23)

24UNIVERSITY OF CENTRAL FLORIDA , )

29)

30Respondent . )

33)

34RECOMMENDED ORDER

36Pursuant to notice, a final hearing was held in this case

47on February 18, 2011, in Orlando, Florida, before Susan B.

57Harrell, a n Administrative Law Judge of the Division of

67Administrative Hearings.

69APPEARANCES

70For Petitioner: Thomas Gregory, Qualified Representative

76Dimitri Nikitin

78BlueChip Energy, LLC

81400 Rinehart Road, No. 1060

86Lake Mary, Florida 32746

90For Respondent: Jordan P. Clark, Esquire

96University of Central Florida

1004000 Central Florida Boulevard

104Post Office Box 160015

108Orlando, Florida 32816

111Richard E. Mitchell, Esquire

115GrayRobinson, P.A.

117Post Office Box 3068

121Orlando, Flo rida 32802

125STATEMENT OF THE ISSUE

129The issue in this case is whether Respondent's intended

138decision to reject Petitioner's bid for University of Central

147Florida (UCF) Invitation to Bid No. 1030LCSAR (ITB) was

156arbitrar y, unreasonable, or capricious.

161PRELI MINARY STATEMENT

164Respondent, U C F, issued ITB No. 1030LCSAR for photovoltaic

174systems for emergency systems. Petitioner, BlueChip , LLC

181(BlueChip) , submitted a bid. By letter dated November 19, 2010,

191U C F notified BlueChip that its bid was being rejected. B y

204letter dated November 20, 2010, BlueChip advised UCF that

213BlueChip was concerned that its bid was rejected and wanted a

224clear explanation for the reasons for rejection. The letter did

234not indicate that it was a notice of protest . By letter dated

247Novemb er 24, 2010, BlueChip wrote to UCF and addressed each of

259the grounds set forth in UCF's letter dated November 19, 2010.

270The second letter did not specifically request an administrative

279hearing, but stated: "[W]e insist UCF immediately reinstate and

288recon sider our bid."

292By letter dated January 26, 2011, UCF sent the two letters

303to the Division of Administrative Hearings and requested that

312the Division of Administrative Hearings conduct a bid protest

321hearing. However, UCF specifically preserved any objecti ons to

330the letters, including whether the letters constituted a bid

339protest in conformance with UCF regulations.

345At the final hearing, the following witnesses were

353presented by BlueChip: Andrew N. White, D i mitri Nikitin, and

364Thomas Gregory. Petitioner's Exhibits 1, 2, 3, 4, 6, 8, 9, 11,

376and 12 were admitted in evidence. Petitioner's Exhibits 5, 7,

386and 10 were not accepted in evidence. UCF called the following

397witnesses: Luis Aviles, Mary C. Huggins, and David K. Click .

408Respondent's Exhibits 1, 2, 3, 5, 6, 7, 8, 9, 10, 11, 17, 21,

42222, 23, 24, and 29 were admitted in evidence.

431The two - volume Transcript was filed on March 8, 2011. On

443March 18, 2011, the parties filed their Proposed Recommended

452Orders, whic h have been considered in the preparation of this

463Recommended Or der.

466FINDINGS OF FACT

4691. UCF received a grant for $10,000,000.00 through the

480United States Department of Energy pursuant to the American

489Recovery and Reinvestment Act (ARRA) for, among other things,

498the construction and installation of turnkey 10kW PV systems

507wi th battery back up at schools located in Florida and designated

519as emergency shelters. Part of the grant money was to be used

531for administration and for education of Florida school chil dren

541concerning renewable energy sources and energy efficiency.

5482. In order to procure the construction and installation

557of the PV systems, UCF issued the ITB. This was the second

569invitation to bid issued for PV systems. The first invitation

579to bid was issued during the summer of 2010, and all the bids

592received were over budget.

5963. The introduction in the ITB provides:

603As part of the Florida SunSmart Schools

610Emergency Shelter Program, the University of

616Central Florida intends to purchase at lea st

624ninety (90) turnkey installations of 10 kWdc

631(minimum) grid - tied photovoltaic (PV)

637systems with battery backup for specified

643Florida schools designated as EHPA (Enhanced

649Hurricane Protection Area) emergency

653shelters. This program provides for

658emergency electrical power for critical

663loads and provides ongoing educational

668programs for students. UCF/Florida Solar

673Energy Center will select the schools at

680which the PV systems will be installed. It

688is expected that at least one system will be

697installed in e ach County in the State of

706Florida.

707It is anticipated that multiple Bidders will

714be selected for participation in this

720program. One bidder will be selected for

727each Region, as defined in the Bid Document.

735A Bidder may be awarded more than one

743Region.

744A ll PV modules and systems must be certified

753by the Florida Solar Energy Center as

760specified in the bid document.

7654. The Florida Solar Energy Center (FSEC) is a statutory

775affiliate of UCF which "develop[s] and promulgate[s] standards

783for solar energy sys tems manufactured or sold in this state

794based on the best currently available information and shall

803consult with scientists, engineers, or persons in research

811centers who are engaged in the construction of, experimentation

820with, and research of solar energ y systems to properly identify

831the most reliable designs and types of solar energy systems."

841§ 377.705(4)(a), Fla. Stat. (2010). 1/ All solar equipment that

851is sold or manufactured in the S tate of Florida must be

863certified by FSEC. § 377.705(4)(d).

8685. Bl ueChip was among the 19 bidders, which submitted bid s

880in response to the ITB. On November 19, 2010, UCF posted the

892intent to award the contract for all regions to Vergona - Bowersox

904Electric, Incorporated (Vergona - Bowersox). By letter dated

912November 19, 20 10, UCF notified BlueChip that its bid was

923rejected for a number of deficiencies. The Sunny Island

932inverter, which BlueChip included in the system it bid, is not

943made in America, and, therefore, does not comply with the Buy

954America provision of the ITB. Sunny Boy inverters, which

963BlueChip included in the system it bid, are undersized and do

974not meet the specifications of the ITB. The batteries used in

985BlueChip's bid do not meet the specifications of the ITB. FSEC

996did not receive a PV System Certificatio n Application from

1006BlueChip as required by the ITB. BlueChip does not hold a solar

1018contractor license, nor does it hold an electrical contract or

1028license as required by the ITB.

10346. By letter dated November 20, 2010, Dimitri Ni k itin

1045(Dr. Nikitin) , presiden t of BlueChip, wrote to UCF concerning

1055the rejection of BlueChip's bid. The letter stated in part:

1065On behalf of BlueChip Energy, LLC, which

1072submitted a bid for the SunSmart Emergency

1079Shelters project on November 8, I would like

1087to express my concerns and ask for

1094clarification regarding the Intent to Award

1100notice for UCF Bid 1030lcsar posted on the

1108UCF Purchasing website on November 19.

1114First, we would like a written explanation

1121why UCF rejected BlueChip Energy's bid. Our

1128bid followed the requirements of the ITB to

1136the letter, including compliance with the

1142Buy America Act and ability t o provide a

1151payment and performance bond.

1155* * *

1158We would like to receive a clear explanation

1166of why the only solar panel manufacturing,

1173engineering and Installation Company in

1178Florida with first hand PV module

1184manufacturing experience and multi - Megawatt

1190international install base was simply

1195rejected as a bidder. To find out the

1203reasons for your decision we will initiate a

1211media investigation and congressional and

1216Fl orida Energy Commission inquiry into the

1223administration of UCF bid 1030LCSAR, and the

1230possible conflict of interests of UCF

1236employees and related parties.

1240Your timely response to our questions and

1247concerns is very much appreciated.

12527. The BlueChip lette r dated November 20, 2010, did not

1263state that it was intended to be a Notice of Protest. By letter

1276dated November 24, 2010, BlueChip responded to each of the

1286deficiencies listed in UCF's letter to BlueChip dated

1294November 19, 2010. BlueChip's letter dated November 24, 2010,

1303did not state that the letter was supposed to be a formal

1315protest, but did state:

1319Due to the spurious and baseless nature of

1327the issues raised by your November 19 letter

1335we insist UCF immediate ly reinstate and

1342reconsider our bid. In the absence of that

1350we will have no choice but to initiate a

1359media investigation and congressional and

1364Florida Energy Commission inquiry into the

1370administration of ECF [sic] bid 1030LCSAR

1376and the possible conflict o f interest of UC F

1386employees and related parties.

1390Additionally, the November 24, 2010, letter did not include a

1400protest bond.

14028. Appendix II, section 13 , of the ITB provides:

141113. Compliance with the Buy America

1417Recovery Act Provisions (Section 1605 of

1423Title XVI) --

1426By accepting funds under this Agreement

1432[State of Florida Grant Assistance Pursuant

1438to American Recovery and Reinvestment Act],

1444the Grantee [UCF] agrees to comply with

1451sections [sic] Section 1605 of the American

1458Recovery and Reinvestment Act (ARRA)." The

1464Grantee should review the provisions of the

1471Act to ensure that expenditures made under

1478this Agreement are in accordance with it.

1485The Buy American provision in the American

1492Recovery and Reinvestment Act of 2009

1498(section 1605 of title XVI), pr ovides that,

1506unless one of the three listed exceptions

1513applies (nonavailability, unreasonable cost,

1517and inconsistent with the public interest),

1523and a waiver is granted, none of the funds

1532appropriated or otherwise made available by

1538the Act may be used for a project for the

1548construction, alteration, maintenance, or

1552repair of a public building or public work

1560unless all the iron, steel, and manufactured

1567goods are produced in the United States.

15749. On September 30, 2010, the United States Department of

1584Energy granted a limited waiver of the Buy America provision of

1595ARRA with respect to certain PV equipment. The waiver provided:

1605This amended public interest determination

1610waives the Buy American requirements of

1616EERE - funded Recovery Act projects for the

1624purchase of the following solar PV

1630equipment: (1) Domestically - manufactured

1635modules containing foreign - manufactured

1640cells, (2) foreign - manufactured modules,

1646when completely comprised of domestically -

1652manufactured cells, and (3) any ancillary

1658items and equipment (in cluding but not

1665limited to, charge controllers, combiners,

1670and disconnect boxes, breakers, fuses,

1675racks, lugs, wires, cables and all otherwise

1682incidental equipment with the exception of

1688inverters and batteries) when utilized in a

1695solar installation involvi ng a U.S.

1701manufactured PV module or a module

1707manufactured abroad but comprised

1711exclusively of domestically - manufactured

1716cells. ( e mphasis added ) .

172310. BlueChip's bid specifies inverters manufactured by SMA

1731America Solar Technologies, Inc. (SMA), specifica lly SMA's Sunny

1740Boy 4000US inverter and Sunny Island 5048US inverter. SMA's

1749Sunny Island 5048US inverter is made in Germany, not the United

1760States. The United States Office of Management and Budget (OMB)

1770has issued interim final guidance , directing that the Buy

1779American provision shall not be applied where the iron, steel,

1789or manufactured goods used in the project are subject to an

1800international agreement. The recipient of ARRA funds is to

1809treat the goods subject to an international agreement the same

1819as domestic goods and services. In Florida, only executive

1828branch agencies may invoke the United States' international

1836trade agreement s . State of Florida universities may not

1846participate in the international trade agreements.

185211. The total bid of BlueChip was $6,383,811.00. The

1863value of the contract awarded to Vergona - Bowersox pursuant to

1874the ITB was $6,720,896.70.

188012. Appendix 1, section 2(C)(8) , of the ITB states: "The

1890battery bank shall have a minimum usable capacity (at C/100) of

190125kWh. " BlueChip's bid specifies a battery bank capable of

1910producing and delivering a maximum energy output of 24 volts to

1921its specified Sunny Island 5048US inverter. In order to turn on

1932and function, the Sunny Island 5048US inverter requires a

1941minimum energy input of 41 v olts from the battery bank. The

195324 volts produced by the battery bank specified by BlueChip is

1964insufficient to turn on the inverter. Therefore, the PV system

1974bid by BlueChip would not be functional and would not meet the

1986minimum usable capacity required by the ITB , because the

1995inverter could not be activated by the battery bank.

200413. Appendix 1, section 2(C)(8) , of the ITB provides the

2014following requirements:

2016PV systems must be capable of parallel

2023operation with the utility supplied

2028electrical service to the facility. The

2034entire PV system must also be capable of

2042stand - alone operation, providing backup

2048power to a critical load panel when the

2056utility supplied electrical service is

2061unavailable. Systems will be grid -

2067interactive, providing power to a collecti on

2074of pre - determined critical loads.

208014. BlueChip's electrical schematic is non - conforming to

2089the ITB , because it does not properly allow for the required

2100operation with the utility supplied electrical service to the

2109facility and is not capable of a stan d - alone operation,

2121providing backup power to a critical load panel when the utility

2132supplied electrical service is unavailable.

213715. BlueChip's bid specifies a PV array capable of

2146producing and delivering a maximum energy output of

2154approximately 90 volts t o its specified Sunny Boy 4000US

2164inverter. In order to turn on and function, the Sunny Boy

21754000US inverter requires a minimum energy input of 295 volts

2185from the PV array. Therefore, the system bid by BlueChip cannot

2196turn on the Sunny Boy 4000US inverter included in BlueChips's

2206system, which makes the system nonfunctional.

221216. BlueChip's bid contains a schematic showing a Sunny

2221Boy 4000US inverter with two DC inputs and two AC outputs.

2232Sunny Boy 4000US inverters have only one DC input connection and

2243one AC output connection. Based on the schematic submitted by

2253BlueChip, the system is nonfunctional.

225817. The ITB provides that UCF may waive "any minor

2268irregularity." BlueChip contends that any technical issues with

2276the system bid could be corrected by FSEC during the

2286certification process after the bids were opened and the

2295intended award was announced.

229918. Appendix 1 , section 1(C)(1) , of the ITB provides:

2308Bidders will serve as the prime contractor

2315and must be licensed to install photovoltaic

2322systems in the State of Florida. Bidder

2329must hold a valid license as a certified

2337solar contractor or electrical contractor,

2342per Chapter 489, Florida Statutes. General

2348Contractors may not serve as a prime

2355contractor for the installation of a

2361photovoltaic system due to the limitations

2367provided in Section 489.113(3), Florida

2372Statutes. Bidders may include

2376subcontractors as deemed necessary, but

2381subcontractors must be iden tified in the bid

2389response, with a description of the work to

2397be performed by each subcontractor. A

2403successful Bidder will be solely responsible

2409for fulfilling the terms of award.

241519. BlueChip submitted the bid and identified itself as

2424the prime contrac tor in its bid. In its bid , BlueChip

2435identified Advanced Solar Photonics and Complete Electrical

2442Contractors as wholly - owned subsidiaries of BlueChip. BlueChip

2451purchased Complete Electric Contractors, Inc., and the name was

2460changed to Complete Electric C ontractors, LLC. On January 5,

24702010, Complete Electric Contractors, LLC , registered to do

2478business under the fictitious name of BlueChip Energy.

248620. No evidence was presented at the final hearing that

2496BlueChip was a certified solar contractor or that Bl ueChip was

2507registered or certified pursuant to section 489.521, Florida

2515Statutes.

251621. BlueChip contends that BlueChip me e ts the requirement

2526as an electrical contractor , because Complete Electrical

2533Contractors, Inc. , was registered as a business performing

2541electrical contracting with Andrew White (Mr. White) as the

2550qualifying agent and is a wholly - owned subsidiary of BlueChip.

2561Complete Electrical Contractors, LLC, is the wholly - owned

2570subsidiary of BlueChip and is a separate legal entity from

2580BlueChip . The bid was not submitted by Complete Electrical

2590Contractors, LLC, or by Complete Electrical Contractors, Inc.

2598Additionally, Mr. White is the qualifying agent for Complete

2607Electrical Contractors, Inc., not Complete Electrical

2613Contractors, LLC.

261522. BlueChip did not list Complete Electrical Contractors,

2623LLC, as a subcontractor in its bid.

263023. Appendix 1, section 1(D) , of the ITB provides that , if

2641a bidder chooses not to use a PV system that is not already

2654certified by FSEC, the bidder is responsible for submi tting an

2665application for system certification. There is a special

2673application process in FSEC for applications that are being made

2683as part of a bid solicitation process. The applications are

2693submitted, but the processing fee is not required at the time o f

2706the submittal of the application , and only the applications for

2716bidders selected for a contract will be certified.

272424. The directions for submittal of the applications for

2733certification are contained in Appendix 1, section 1(4) , of the

2743ITB, which provid es:

27474. IMPORTANT : The Florida Solar Energy

2754Center has established a modified

2759application process for certifying PV

2764systems for this program only. The

2770following process should be followed

2775carefully to qualify for this offer.

2781a. On or before the deadli ne date of the

2791ITB, Bidder must complete and electronically

2797submit (see ii below) the Photovoltaic

2803System Certification -- SunSmart E - Shelter

2810Program Application form available at:

2815http://www.fsec.ucf.edu/en/education/

2816sunsmart/e - shelters/documents/

2819EShelter Application.pdf . Applications

2823submitted under previous solicitations will

2828not be considered under this program. Only

2835certification applications submitted through

2839the current bid process will be considered.

2846i. Only fully completed applications will

2852be accepted for consideration under this

2858program. The application must include all

2864required documentation to be considered

2869complete. All materials must be submitted

2875electronically to FSEC in a single email.

2882FSEC will not accept partial submissions.

2888All em ail attachments must be in PDF format.

2897ii. All certification applications must be

2903sent to pvshelter@fsec.ucf.edu . A complete

2909electrical schematic that includes the

2914following information is required as part of

2921the system certification package. (This

2926lis t is provided for guidance and assistance

2934only and is not the only information

2941required in the certification application.)

29461) Modules labeled and shown in correct

2953array configuration (source circuits)

29572) Size, type, and location of all

2964conductors ( c, - dc, L1, L2, L3, N, G,

2974etc.) in the system

29783) Complete circuit paths shown

29834) Size, current rating, voltage rating,

2989and location of all over - current protection

2997devices

29985) Inverter/Charger/Controller equipment

3001correctly identified

30036) Data acquisition system (DAS)

3008[monitoring equipment] identified

30117) Battery wiring and cables labeled and

3018shown in correct bank configuration

30238) Complete details of the system grounding

3030in compliance with NEC 690 V. Grounding

30379) Point of interconnection sp ecified and

3044in compliance with NEC 690.64(B)(7)

304910) Ratings and locations of all

3055disconnects

3056iii. Incomplete applications will be

3061rejected and the applicant's system and bid

3068may be ineligible for an award under this

3076program. The applicant will be so n otified

3084but application materials will not be

3090returned to the applicant.

309425. The system bid by BlueChip had not been certified by

3105FSEC. BlueChip was required to submit an application to FSEC as

3116part of the bid process. BlueChip had submitted applicatio ns to

3127FSEC as part of the previous solicitation for PV systems for

3138emergency systems, which had been cancelled in October 2010. At

3148the final hearing, Dr. Nikitin testified that he had submitted

3158other applications for the ITB; however, the only receipt tha t

3169he could produce was for a n email delivery dated August 23,

31812010, which was before the ITB was issued. The totality of the

3193evidence does not establish that BlueChip sent an application by

3203email to FSEC for the ITB. BlueChip did include with its bid

3215two applications submitted in response to the previous

3223invitation to bid. One application was dated

3230July 28, 2010, and one was dated August 19, 2010. Because

3241BlueChip submitted no application to FSEC for the ITB by email,

3252FSEC evaluated the technical aspect of BlueChip's bid based on

3262the application submitted with the bid.

326826. BlueChip asserted in its letters to UCF, dated

3277November 20, 2010, and November 24, 2010, that there had been a

3289conflict of interest concerning a member of the Policy Advisory

3299Board of FSEC and Vergona - Bowersox. However, no evidence was

3310presented to support this assertion.

3315CONCLUSIONS OF LAW

331827. The Division of Administrative Hearings has

3325jurisdiction over the parties to and the subject matter of this

3336proceeding. § 120.65(7), Fla. S tat.

334228. UCF Regulation 7.130(5) sets forth the procedures for

3351solicitation and provides:

3354(5) Solicitation Protest Procedures

3358(a) Any qualified offeror who is adversely

3365affected by the university's decision may

3371file a written notice of intent to protes t

3380within 72 hours after university posting of

3387award or intent to award notice. The

3394protesting firm must reduce its complaint to

3401a written protest and file it with the

3409department that issued the solicitation

3414within ten (10) calendar days from

3420registration of the original complaint. The

3426bond shall be included with the formal

3433written protest.

3435(b) The notice of protest shall contain the

3443following information:

34451. The notice must be addressed to the

3453department that issued the solicitation or

3459that made a decision that is intended to be

3468protested;

34692. The notice must identify the

3475solicitation by number and title and any

3482other language that will allow for

3488identification; and

34903. The notice must state that the person

3498intends to protest the decision.

3503(c) T he "formal written protest" required

3510by BOG regulation 18.002 is a petition that

3518states with particularity the facts and law

3525upon which the protest is based. The formal

3533protest shall be filed with the office

3540issuing the competitive solicitation within

3545ten (10) calendar days of the notice of

3553intent to protest. The formal written

3559protest shall con tain the following

3565information:

35661. The name of the protestor;

35722. A statement of when and how the

3580protestor received notice of the

3585University's action or propos ed action;

35913. An explanation of how the protestor's

3598substantial interests are or will be

3604affected by the action or proposed action;

36114. A statement of all material facts

3618disputed by the protestor or a statement

3625that there are no disputed facts;

36315. A s tatement of the facts alleged,

3639including a statement of the specific facts

3646the protestor contends warrant reversal or

3652modification of the university's proposed

3657action;

36586. A statement of the specific regulations

3665or statutes that the protestor contends

3671req uire reversal or modification of the

3678university's proposed action, including an

3683explanation of how the alleged facts relate

3690to the specific regulations or statutes;

36967. A statement of the relief sought by the

3705protestor, stating precisely the action

3710protes tor wishes the agency to take with

3718respect to the proposed action.

3723(d) The failure to adhere to filing

3730deadlines will result in the rejection of

3737the protest.

373929. UCF Regulation 7.130(4)(c) requires that a protest

3747bond be submitted with the formal written protest and states:

3757Solicitation Protest Bond. Any contractor

3762that files a formal written protest pursuant

3769to the protest procedures of BOG Regulation

377618.002 and this regulation (see section (5)

3783below) protesting a decision or intended

3789decision pe rtaining to a solicitation, shall

3796at the time of filing of the formal protest,

3805post with the University a bond payable to

3813the University in an amount equal to 10% of

3822the estimated value of the protestor's bid

3829or proposal; 10% of the estimated

3835expenditure d uring the contract term;

3841$10,000; or whichever is less. The bond

3849shall be conditioned upon payment of all

3856costs which may be adjudged against the

3863contractor filing the protest action. In

3869lieu of a bond, the University may accept a

3878cashier's check or mone y order in the amount

3887of the bond. Failure to file a protest in

3896accordance with BOG regulation 18.002 or

3902failure to po s t the bond or other security

3912as required by the BOG regulation 18.003,

3919shall const itute a waiver of proceedings.

392630. BlueChip's letter dated November 20, 2010, did not

3935advise UCF that BlueChip was intending to protest the notice of

3946the award of the contract for PV systems to Vergona - Bowersox.

3958The letter asked for an explanation of why BlueChips's bid was

3969rejected and cited various conce rns about the rejection of

3979BlueChip's bid. The letter was not sufficient to put UCF on

3990notice that BlueChip was protesting the intended award. UCF

3999Regulation 7.130 clearly requires that the notice of protest

4008state that the bidder intends to protest the d ecision.

401831. If the letter dated November 19, 2010, were deemed to

4029be the notice of protest and the letter dated November 24, 2010,

4041were deemed to be the formal written protest, BlueChip did not

4052submit the required protest bond with the November 24, 2010,

4062letter as required by UCF Regulation 7.130(4) and has thus

4072waived any protest.

407532. Assuming arguendo that BlueChip's letter of

4082November 19, 2010, is deemed to be sufficient as a notice of

4094protest and a bid protest bond had been included with the

4105November 24, 2010, letter, BlueChip's bid fails to meet the

4115requirements of the ITB in numerous respects.

412233. The ITB provides that the bidders must abide by the

4133Buy America requirement of the A R RA. BlueChip 's bid included

4145SMA's Sunny Island 5048US inverter, whi ch is made in Germany.

4156Although the ARRA provides for a Buy American requirement, it

4166also provides that the Buy American requirement be applied in a

4177manner consistent with United States' obligations under

4184international agreements. Thus, goods purchased p ursuant to an

4193international agreement are to be considered the same as

4202domestic goods and services. Two C.F.R. section 176.90

4210provides:

4211The Buy American requirement set out in

4218§ 176.70 shall not be applied where the

4226iron, steel, or manufactured goods used in

4233the project are from a Party to an

4241international agreement, listed in paragraph

4246(b)(2) of this section, and the recipient of

4254is required under an international

4259agreement, described in the appendix to this

4266subpart, to treat the goods and services of

4274tha t Party the same as domestic goods and

4283services. This obligation shall only apply

4289to projects with an estimated value of

4296$7,443,000 or more and projects that are not

4306specifically excluded from the application

4311of those agreements.

431434. Article IX, s ection 7 , of the Florida Constitution

4324provides that there shall be a single state university system

4334that is comprised of all public universities, which includes

4343UCF. The state university system is not include d in the

4354executive branch of government. Appendix to subpart B of

43632 C.F.R . part 176 lists the state entities that are subject to

4376United States obligations under international agreements. Only

4383the executive agencies of the State of Florida are subject to

4394the World Trade Organization Government Procurement A greement,

4402which includes Germany. Thus, UCF is not exempt from the Buy

4413America provision of ARRA because of an international agreement.

442235. Even if UCF were considered to be obligated to abide

4433by international agreements, the project amount is less than

4442$7,443,000 .00 . BlueChip contends that the project amount is the

4455entire grant amount of $10,000,000 .00 . The project is

4467considered to be the construction, alteration, maintenance, or

4475repair of a public building. 2 C.F.R. § 176.70(a). The project

4486at issu e is the alteration of school buildings to include PV

4498systems for schools designated as emergency shelters. A school

4507building is a public building. Therefore, the project amount is

4517insufficient to exempt UCF from the Buy America provision s of

4528the ARRA.

45303 6. BlueChip did not meet several technical requirements

4539of the ITB. The battery bank and the Sunny Island 5048US

4550inverter bid by BlueChip are not compatible because the battery

4560bank does not have sufficient energy output to start the

4570inverter ; therefore, the system bid will not function.

457837. The electrical schematic submitted by BlueChip does

4586not properly allow for the operation with the utility supplied

4596electrical service to the facility as required by the ITB. The

4607electrical schematic does not show th at the system is capable of

4619stand - alone operation, with backup power to a critical load

4630panel when the utility supplied electrical service is

4638unavailable as required by the ITB.

464438. BlueChip stated that its system was capable of

4653producing a maximum energy output of 90 volts to the Sunny Boy

46654000US inverter, which BlueChip included in its system.

4673However, the Sunny Boy 4000US inverter requires a minimum of

4683285 volts in order to turn on and work. Additionally, the Sunny

4695Boy 4000US inverter does not have th e number of DC inputs and AC

4709outputs as specified in BlueChip's bid. Essentially, the use of

4719the Sunny Boy 4000US inverter as set forth in BlueChip's bid

4730will result in a nonfunctional system.

473639. BlueChip contends that these errors could be corrected

4745by FSEC during the certification process after the bids were

4755opened and the intended award was announced. BlueChip's

4763contention is without merit. In Wester v. Belote , 138 So. 721,

4774723 - 24 (Fla. 1931), the court described the object and purpose

4786of fundamental policies underlying competitive procurement and

4793stated:

4794[T]he object and purpose of [the policies

4801underlying competitive procurement] is to

4806protect the public against collusive

4811contracts; to secure fair competition upon

4817equal terms to all bidde rs; to remove not

4826only collusion but temptation for collusion

4832and opportunity for gain at public expense;

4839to close all avenues to favoritism and fraud

4847in its various forms; to secure the best

4855values for the [governmental agency] at the

4862lowest possible expe nse, and to afford an

4870equal advantage to all desiring to do

4877business with the [governmental agency] by

4883affording an opportunity for an exact

4889comparison of bids.

489240. The ITB provides that UCF may waive "any minor

4902irregularities." A variance from the bid specifications is

4910considered minor if it does not give a bidder a competitive

4921advantage over another bidder. See Intercontinental Properties,

4928Inc. v. Dep ' t of HRS , 606 So. 2d 380 (Fla. 3d DCA 1992);

4943Trobabest Foods, Inc. v. Dep ' t of Gen . Servs . , 493 So. 2d 50

4959(Fla. 1st DCA 1986); and Robinson Electrical Co., Inc. v. Dade

4970C nty . , 417 So. 2d 1032 (Fla. 3d DCA 1982).

498141. The failure to bid a system that would work is not a

4994minor irregularity. To allow BlueChip to bid a nonfunctional

5003system and make corrections to the system after the bids were

5014opened in order to make the system functional would give

5024BlueChip an unfair advantage over the other bidders.

503242. BlueChip did not meet the ITB requirement that it hold

5043a valid license as a certified solar con tractor or electrical

5054contractor. No evidence was presented that BlueChip was

5062registered or certified as a business conducting electrical

5070contracting as required by section 489.521 or that it held a

5081valid license as a certified solar contractor. BlueChip relied

5090upon the electrical contractor license of Mr. White as the

5100qualifying agent for Complete Electric Contractors, Inc., as

5108meeting the license requirement for a certified electrical

5116contractor. BlueChip's contention is without merit. Complete

5123Electr ical Contractors, Inc., for whom Mr. White is the

5133qualifying agent, no longer exists and was changed to a limited

5144liability corporation. Complete Electrical Contractors, LLC, is

5151a separate legal entity from BlueChip, did not submit the bid,

5162and was not li sted as a subcontractor in BlueChip's bid.

517343. BlueChip did not submit an application for

5181certification to FSEC as required by the ITB. It did submit an

5193application for the previous invitation to bid. However, the

5202ITB provides that applications submitte d for previous

5210procurements would not be acceptable. FSEC did evaluate the

5219applications submitted with the bid, which were the applications

5228submitted for the previous invitation to bid, and found that

5238BlueChip's bid was nonresponsive.

524244. In Sutron Corp . v. Lake County Water Authority , 870

5253So. 2d 930, 932 - 933 (Fla. 5th DCA 2004), the court stated:

5266It is well established in Florida that a

5274public entity's rejection of contract bids

5280will be affirmed when challenged in court,

5287unless the action of the public b ody was

5296arbitrary, unreasonable or capricious. Even

5301if the public entity makes an erroneous

5308decision about which reasonable people may

5314disagree, the discretion of the public

5320entity to solicit, accept and or reject

5327contract bids should not be interfered wi th

5335by the courts, absent a showing of

5342dishonesty, illegality, fraud, oppression or

5347misconduct. See Scientific Games v. Dittler

5353Brothers, Inc. , 586 So. 2d 1128 (Fla. 1st

5361DCA 1991); City of Cape Coral v. Water

5369Services of America , 567 So. 2d 510 (Fla. 2d

5378DCA 1990); Capeletti Brothers v. State Dept.

5385of General Services , 432 So. 2d 1359 (Fla.

53931st DCA 1983).

539645. A decision is arbitrary if it is not supported by fact

5408or logic. A decision is capricious if it is taken without

5419thought or reason. In determinin g whether an agency has acted

5430arbitrarily or capriciously, consideration should be given to

5438the following factors: (1) has the agency considered all

5447relevant factors; (2) has the agency given actual, good faith

5457consideration to those factors; and (3) has the agency used

5467reason rather than whim to progress from consideration of those

5477factors to its final decision. Adam Smith Enterprises, Inc. v.

5487State Dep ' t of Envtl . Reg . , 553 So. 2d 1260, 1273 (Fla. 1st DCA

55041989). A decision is neither arbitrary nor capricious if the

5514decision is justifiable under any analysis that a reasonable

5523person would use to reach a decision of similar importance.

5533Dravco Basic Materials Co., Inc. v. State Dep ' t of Tra nsp . , 602

5548So. 2d 632, 634 n.3 (Fla. 2nd DCA 1992).

555746. UCF's decision to reject BlueChip's bid is not

5566arbitrary or capricious. BlueChip's bid was evaluated and found

5575nonresponsive. The decision to reject BlueChip's bid is

5583reasonable based on BlueChip's failure to adhere to the

5592specifications of the ITB.

5596RECOMMENDATION

5597Based on the foregoing Findings of Fact and Conclusions of

5607Law, it is RECOMMENDED that a final order be entered finding

5618that BlueChip failed to submit a notice of protest in accordance

5629with UCF Regulation 7.130 ; finding that the rejection of

5638BlueChip's bid is not arbitrary, unreasonable, or capricious ;

5646and rejecting BlueChip's bid.

5650DONE AND ENTERED this 8th day of April , 2011 , in

5660Tallahassee, Leon County, Florida.

5664S

5665SUSAN B. HARRELL

5668Administrative Law Judge

5671Division of Administrative Hearings

5675The DeSoto Building

56781230 Apalachee Parkway

5681Tallahassee, Florida 32399 - 3060

5686(850) 488 - 9675

5690Fax Filing (850) 921 - 6847

5696www.doah.state.fl.us

5697Filed with the Clerk of the

5703Division of Administrative Hearings

5707this 8th day of April , 2011 .

5714ENDNOTE

57151/ Unless otherwise stated, all references to the Florida

5724Statutes are to the 2010 version.

5730COPIES FURNISHED :

5733Thomas Gregory

5735Dimitri Nikitin

5737BlueChip Energy, LLC

5740400 Rinehart Road, No. 1060

5745Lake Mary, Florida 32746

5749Jordan P. Clark, Esquire

5753University of Central Florida

57574000 Central Florida Boulevard

5761Post Office Box 160015

5765Orlando, Florida 32816

5768Richard E. Mitchell, Esquire

5772GrayRobinson, P.A.

5774Post O ffice Box 3068

5779Orlando, Florida 32802

5782NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

5788All parties have the right to submit written exceptions within

579810 days from the date of this Recommended Order. Any exceptions

5809to this Recommended Order should be filed with the agency that

5820will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 10/17/2019
Proceedings: Agency Final Order filed.
PDF:
Date: 09/12/2011
Proceedings: Agency Final Order
PDF:
Date: 04/08/2011
Proceedings: Recommended Order
PDF:
Date: 04/08/2011
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 04/08/2011
Proceedings: Recommended Order (hearing held February 18, 2011). CASE CLOSED.
PDF:
Date: 03/18/2011
Proceedings: (Proposed) Recommended Order filed.
PDF:
Date: 03/18/2011
Proceedings: UCF's Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 03/18/2011
Proceedings: (Petitioner`s) Proposed Recommended Order filed.
Date: 03/08/2011
Proceedings: Transcript of Proceedings Volume I and II (not available for viewing) filed.
Date: 02/18/2011
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 02/17/2011
Proceedings: Respondent UCF's Pre-hearing Statement filed.
PDF:
Date: 02/17/2011
Proceedings: Respondent UCF's Opposed Amended Motion for Leave for Witness to Appear by Telephone filed.
PDF:
Date: 02/17/2011
Proceedings: Respondent UCF's Motion for Leave for Witness to Appear By Telephone filed.
PDF:
Date: 02/16/2011
Proceedings: Letter to DOAH from T. Gregory regarding bluechip energy bid compliant filed.
PDF:
Date: 02/16/2011
Proceedings: Amended Notice of Hearing (hearing set for February 18, 2011; 9:00 a.m.; Orlando, FL; amended as to authority).
PDF:
Date: 02/15/2011
Proceedings: Notice of Appearance (of R. Mitchell) filed.
PDF:
Date: 02/10/2011
Proceedings: Request for Clarification of Governing Authority filed.
PDF:
Date: 02/03/2011
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 02/03/2011
Proceedings: Notice of Hearing (hearing set for February 18, 2011; 9:00 a.m.; Orlando, FL).
Date: 02/02/2011
Proceedings: CASE STATUS: Pre-Hearing Conference Held.
PDF:
Date: 01/31/2011
Proceedings: Invitation to BID filed.
PDF:
Date: 01/31/2011
Proceedings: Letter to L. Avilles from D. Nikitin regarding the Intent to Award filed.
PDF:
Date: 01/31/2011
Proceedings: Rejection of BID filed.
PDF:
Date: 01/31/2011
Proceedings: Referral Letter filed.
PDF:
Date: 01/26/2011
Proceedings: Referral Letter filed.

Case Information

Judge:
SUSAN BELYEU KIRKLAND
Date Filed:
01/31/2011
Date Assignment:
01/31/2011
Last Docket Entry:
10/17/2019
Location:
Orlando, Florida
District:
Middle
Agency:
ADOPTED IN PART OR MODIFIED
Suffix:
BID
 

Counsels

Related Florida Statute(s) (4):