12-003369EPP
In Re: Tampa Electric Company, Polk Power Station, Polk 2-5 Combined Cycle Conversion Project vs.
*
Status: Closed
Recommended Order on Friday, August 23, 2013.
Recommended Order on Friday, August 23, 2013.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8IN RE: TAMPA ELECTRIC COMPANY,
13POLK POWER STATION, POLK 2 - 5
20COMBINED CYCLE CONVERSION Case No. 12 - 3369EPP
28PROJECT
29_______ /
31RECOMMENDED ORDER ON CERTIFICATION
35The certi fication hearing in this case was held on June 25 -
4826, 2013, in Lithia and Bartow, Florida, before Bram D. E.
59Canter, an Administrative Law Judge of the Division of
68Administrative Hearings (ÐDOAHÑ).
71APPEARANCES
72For Tampa Electric Company:
76Lawrence N. Curti n, Esquire
81Holland & Knight LLP
85315 South Calhoun Street, Suite 600
91Tallahassee, Florida 32301
94For the Department of Environmental Protection:
100Toni Sturtevant, Esquire
103Department of Environmental Protection
107Mail Station 35
1103900 Commonwealth Boulevard
113T allahassee, Florida 32399 - 3000
119For Hillsborough County:
122Marva M. Taylor, Esquire
126Hillsborough County Attorney's Office
130601 East County Boulevard
134County Center 27th Floor
138Tampa, Florida 33602 - 4156
143STATEMENT OF THE ISSUE
147The issue to be determined i n this proceeding is whether the
159Governor and Cabinet, sitting as the Siting Board, should certify
169the Polk 2 - 5 Combined Cycle Conversion Project (ÐProjectÑ) of
180Tampa Electric Company ("TEC"), including its associated
189electrical transmission lines, subject to the proposed Conditions
197of C ertification.
200PRELIMINARY STATEMENT
202On October 4, 2012, TEC filed its Application for Site
212Certification ("Application") with the Florida Department of
221Environmental Protection ("Department"). The Application was
229distribut ed to various agencies for review. The Department
238determined the Application was complete on December 17, 2012.
247On January 28, 2013, following the submittal of reports and
257proposed conditions for certification from the reviewing
264agencies, the Department issued its Project Analysis Report for
273the transmission line portion of the Project and, on April 26,
2842013, issued its Project Analysis Report for the power plant
294portion of the Project. The reports included the Department's
303recommended Conditions of Cert ification. On May 21, 2013, the
313Department filed a revised Project Analysis Report.
320Hillsborough County, the Florida Fish and Wildlife
327Conservation Commission ("FWC"), and the Southwest Florida Water
337Management District ("SWFWMD") each filed notices of i ntent to be
350parties. Of these agencies, only Hillsborough County appeared at
359the hearing.
361Hillsborough County requested that a p ublic h earing be held
372within its boundaries so that members of the public who are not
384parties to the certification hearing wou ld have an opportunity to
395provide testimony regarding the proposed transmission line
402corridors. The request was granted and the hearing was held on
413June 25, 2013, in Lithia. Public testimony was received and
423Public Testimony Composite Exhibit 1 was recei ved into the
433record.
434On June 26, 2013, the certification hearing was held in
444Bartow. TEC presented the testimony of eleven witnesses and
453TEC/Department Joint Exhibits 1 - 4 and TEC Exhibits 1 - 55 were
466admitted into evidence. The Department presented the tes timony
475of two witnesses and Department Exhibits 1 - 5, 6A, 6B, 7, and 8
489were admitted into evidence. No other party presented testimony
498or exhibits. Following the hearing, TEC requested and was
507allowed to supplement TEC/Department Joint Exhibit 4.
514The Tra nscripts of the public hearing and certification
523hearing proceeding were filed with DOAH. TEC and the Department
533filed a joint proposed recommended order, which has been
542considered in the preparation of this Recommended Order.
550FINDINGS OF FACT
5531. The p arties stipulated there are no disputed issues of
564fact.
5652. TEC is an investor - owned electric utility regulated by
576the Florida Public Service Commission. It is headquartered in
585Tampa and has supplied electricity to customers in the Tampa Bay
596area since 18 99.
6003. TEC's electric service territory covers approximately
6072,000 square miles and includes all of Hillsborough County and
618portions of Polk, Pasco, and Pinellas Counties. TEC has five
628generating stations, Big Bend, HL Culbreath Bayside, JH Phillips,
637Pol k Power Station, and Partnership Station. The Project is
647proposed for the Polk Power Station.
653Existing Facilities
6554. The Polk Power Station was certified pursuant to the
665Power Plant Siting Act in January 1994. It is located in
676southwest Polk County, 17 miles south of the City of Lakeland and
68828 miles southeast of the City of Tampa. The original site
699consists of 4,348 acres bordered by the Hillsborough County line
710on the west; County Road 663 (Fort Green Road) on the east;
722County Road 630, Bethlehem Road , and Albritton Road on the north;
733and State Road 674 and several former phosphate clay settling
743ponds on the south.
7475. The Polk Power Station has five electric generating
756units and associated facilities. Polk Unit 1 is 260 megawatt
766integrated gasificati on combined cycle facility fired with
774synthesis gas or ÐsyngasÑ produced by gasifying coal and other
784solid fuels. Polk Units 2 through 5 are 165 megawatt simple
795cycle combustion turbine generators fueled primarily with natural
803gas.
8046. Support facilities at the Polk Power Station include a
814755 - acre cooling reservoir, oxygen blown gasifier, air separation
824unit, sulfuric acid plant, slag byproduct storage area, and
833switchyard. The station is served by four 230 kilovolt (ÐkVÑ)
843transmission circuits, a railr oad line, and a natural gas
853pipeline. Water is supplied from four onsite groundwater wells
862for the cooling water reservoir and other plant processes. Other
872existing facilities include an administration building, control
879room, warehouse, and construction management building.
885The Proposed Project
888Need
8897. On January 8, 2013, the Florida Public Service
898Commission issued its Final Order Granting Certification of Need
907for Polk 2 - 5 Combined Cycle Conversion. The Commission
917determined that the most cost effecti ve and reliable alternative
927to meet future power needs is the construction of the Project at
939the Polk Power Station. The Commission ' s Final Order is
950TEC/Department Joint Exhibit 2.
9548. Among other findings, the Commission determined that the
963Project would improve fuel diversity and supply reliability,
971incorporate renewable energy and conservation factors, and is
979needed to maintain electric system reliability and integrity.
987Power Generation
9899. The Project involves the conversion of the four existing
999simple cycle combustion turbine generator units to combined cycle
1008operation. The Project would be a four - on - one combined cycle
1021unit consisting of the four existing combustion turbine
1029generators, each combined with a new heat recovery steam
1038generator, and a new steam turbine generator.
104510. The Project would achieve improved efficiency in
1053electrical power generation. When operated in a simple cycle
1062mode, a combustion turbine generator releases hot gases to the
1072atmosphere. In the proposed combined cycle configur ation, this
1081exhaust heat would be routed to the heat recovery steam
1091generators and the steam produced by the heat recovery generators
1101would be routed to the new steam turbine generator to produce
1112additional electricity.
111411. The Project is designed to allo w the combustion turbine
1125generators to be operated in simple cycle mode when the steam
1136turbine generator is not in service. The combustion turbine
1145generators may also be operated in simple cycle mode to meet peak
1157power demands.
115912. The conversion would i ncrease the nominal net
1168generating capacity of the four existing generators from 660
1177megawatts to 1,160 megawatts. Total capacity for the Polk Power
1188Station would be increased from 1,150 megawatts to 1,420
1199megawatts.
120013. The proposed generating facilitie s would be state - of -
1212the - art, incorporating improvements in technology that have
1221occurred over the past 20 years. They are designed by Black &
1233Veatch, an internationally - recognized engineering firm with
1241significant experience in designing similar facilitie s.
1248Fuels
124914. The four combustion turbine generators would be fired
1258with natural gas as the primary fuel. Ultra - low - sulfur diesel
1271fuel would be the backup fuel. The four heat recovery steam
1282generators would have natural - gas - fired duct burners for peaking
1294operations.
129515. The existing onsite natural gas pipeline would provide
1304the natural gas for the Project and the backup ultra - low - sulfur
1318diesel fuel would be stored in existing onsite fuel storage
1328facilities.
1329Water Use
133116. Groundwater withdrawals from f our wells are authorized
1340by the current Conditions of Certification for 4.3 million
1349gallons per day (ÐmgdÑ) on an annual average and 7.6 mgd on a
1362peak monthly average.
136517. The Project will require additional water for cooling
1374and plant process water uses. To minimize use of groundwater,
1384TEC would treat and reuse 5.7 mgd of treated reclaimed water from
1396the City of Lakeland. The treated reclaimed water would
1405primarily be used to supply the makeup water for the proposed new
1417cooling tower and the existing 75 5 - acre cooling reservoir, as
1429well as some process water needs. The cooling reservoir would be
1440used for condenser cooling purposes. The new six - cell mechanical
1451draft cooling tower would provide cooling for the ProjectÓs
1460auxiliary systems, which would be m odified to use the new cooling
1472tower instead of the reservoir.
147718. The reclaimed water would be initially provided by the
1487City of Lakeland through a 15 - mile pipeline. Later, reclaimed
1498water would be provided by the City of Mulberry and Polk County.
151019. The Project systems are designed to maximize water
1519reuse and recycling to reduce groundwater consumption. However,
1527TEC requests that the maximum groundwater withdrawals currently
1535authorized -- 4.3 mgd on an annual average and 7.6 mgd on a peak
1549monthly basi s Î - be maintained in this certification to ensure
1561that TEC can reliably and safely operate the facilities and
1571manage water quality and levels in the cooling reservoir during
1581extended periods of low rainfall conditions and in the event
1591there is an interrup tion in the delivery of reclaimed water.
160220. The ProjectÓs proposed water uses comply with all
1611applicable agency requirements.
1614Stormwater and Wastewater Discharges
161821. Stormwater and wastewater treatment systems are already
1626in use at the Polk Power Stat ion. These systems would be used
1639for the Project facilities.
164322. The proposed facilities will not significantly affect
1651the quantity or quality of stormwater runoff at the Polk Power
1662Station.
166323. The current wastewater streams include runoff from
1671industr ial areas and process wastewaters. Wastewaters would
1679continue to be collected and treated by the onsite industrial
1689wastewater systems , including the equalization basin,
1695neutralization basin, filtration system, and oil/water separator,
1702and then discharged to the cooling water reservoir.
171024. With the addition of the Project, cooling water
1719blowdown from the new cooling tower and treated reclaimed water
1729will be introduced to the cooling reservoir. TEC has a permit
1740for underground injection control wells whic h it plans to test
1751for disposal of nonhazardous wastewater such as reverse osmosis
1760reject water from the reclaimed water treatment process.
176825. The ProjectÓs stormwater and wastewater discharges
1775would comply with all applicable agency requirements.
1782Air Q uality Impacts
178626. Construction of the Project facilities at the Polk
1795Power Station would generate fugitive dust emissions. These
1803would be controlled by dust suppression control measures such as
1813watering.
181427. The vehicles used by construction workers w ould release
1824nitrogen oxide, carbon monoxide, and other fuel combustion -
1833related air pollutants. These kinds of emissions from
1841construction equipment would be minimized through the use of
1850ultra - low - sulfur - diesel fuel in various diesel engines.
186228. Even un der worst - case conditions, the air quality
1873impacts caused by construction activities would be minimal,
1881temporary, and limited to the construction site.
188829. The Project qualifies as a major modification to an
1898existing major source. Air quality impacts fro m plant operations
1908would be primarily nitrogen oxide, sulfur dioxide, and carbon
1917monoxide emissions from the four combined cycle units,
1925particulate emissions from the cooling tower, and various
1933combustion emissions from operation of the emergency diesel
1941ge nerator.
194330. Air quality analyses were performed for nitrogen
1951oxides, sulfur dioxide, particulates, and carbon monoxide. The
1959dispersion modeling analyses demonstrate that the ProjectÓs air
1967quality impacts would not exceed the applicable regulatory limit s
1977and would not cause or contribute to an exceedance of any
1988Prevention of Significant Deterioration Increment or National
1995Ambient Air Quality Standard.
199931. For certain air emissions, Best Available Control
2007Technology ("BACT") is required. BACT controls for nitrogen
2017oxide would include the use of dry, low - nitrogen - oxide burners
2030when firing natural gas and water injection when firing ultra -
2041low - sulfur diesel fuel, and the installation of selective
2051catalytic reduction technologies for the combined cycle
2058comb ustion turbines. For sulfur dioxide emissions and emissions
2067of sulfuric acid mist, BACT controls would include the use of
2078low - sulfur natural gas as a primary fuel and ultra - low - sulfur
2093diesel fuel as a backup fuel.
209932. For carbon monoxide and volatile org anic compounds,
2108BACT calls for good combustion design and operation. BACT for
2118combustion particulates would be the use of low - ash natural gas
2130as a primary fuel and ultra - low - sulfur diesel fuel as a backup
2145fuel.
214633. For the emergency diesel engine, propos ed BACT for all
2157pollutants would be compliance with the applicable Standards of
2166Performance for Stationary Combustion Ignition Internal
2172Combustion Engines, which are federal standards that have been
2181adopted by the Department.
218534. Proposed BACT for particu late emissions from the
2194cooling tower is the use of high efficiency drift eliminators.
220435. The proposed air quality control technology for the
2213Project and the expected emissions from the ProjectÓs
2221construction and operation would comply with all applicab le
2230agency requirements.
2232Transmission Lines and Corridors
223636. The Project includes two new transmission line
2244corridors. The proposed ÐPolk - Pebbledale CorridorÑ is a
22535.5 - mile, single - circuit 250 kV transmission line from the Polk
2266Power Station north to the Pebbledale substation in Polk County.
2276The proposed ÐPolk - Fishhawk CorridorÑ would be a single - circuit
2288250 kV transmission line running west from the Polk Power Station
2299to the Mines substation near the intersection of State Road 674
2310and County Road 39 in Hillsborough County; from there, north and
2321then west again to connect to a new Aspen switching station to be
2334located near the intersection of County Road 672 and Balm - Boyette
2346Road; and from the Aspen station, two separate 230kV transmission
2356lines wo uld run northeast to the existing Fishhawk substation
2366near the intersection of Fishhawk Boulevard and Boyette Road; a
2376total length of 27 miles.
238137. TEC exercised its option under section 403.5064(1)(b),
2389Florida Statutes, to allow parties to file alternate transmission
2398line corridors. No alternate corridors were filed or reviewed in
2408this proceeding.
241038. TEC used a multidisciplinary team to evaluate
2418alternative corridors for the new transmission lines. The team
2427conducted initial data collection, prepared regional screening
2434maps, identified alternate route segments, developed evaluation
2441criteria, evaluated the routes, and selected the preferred
2449routes. Public participation was a part of this effort.
245839. A regional screening map was created to identify
2467ex isting infrastructure, roads, railroads, rivers and other water
2476bodies, and siting constraints within the study area. TEC has
2486existing transmission line rights - of - way in much of the study
2499area, which together with public road rights - of - way provided co -
2513loc ation opportunities.
251640. The Polk - Pebbledale Corridor runs across former
2525phosphate mining lands and follows roads and existing
2533transmission line corridors to a point south of the town of
2544Bradley Junction where it turns to the northeast and follows a
2555tran smission line through reclaimed phosphate lands to the
2564intersection with another existing transmission line.
257041. In this certification proceeding, no party or non - party
2581expressed opposition to the Polk - Pebbledale transmission line
2590corridor.
259142. The Polk - Fishhawk Corridor runs across former and
2601active phosphate mining lands, along road rights - of - way, and
2613agricultural lands. As it approaches the Fishhawk substation,
2621however, it passes through a residential development, referred to
2630as the Fishhawk Communit y. The portion of the corridor that runs
2642through the Fish h awk Community follows an existing TEC - owned
2654transmission line right - of - way.
266143. No developer, agricultural operator, commercial entity,
2668agency, or local government expressed opposition to the Polk to
2678Fishhawk transmission line corridor, but residents of the
2686Fishhawk Community testified in opposition to the corridor at the
2696public hearing held in the Fishhawk community center. Their
2705testimony at the public hearing is discussed later in this
2715Recommen ded Order.
271844. The proposed transmission lines would be installed on
2727steel poles embedded in the ground. Guy wires are generally not
2738needed except where a transmission line makes a large angle turn
2749or guy wires are otherwise necessary for safety and sou nd
2760engineering. Pole heights would vary from 80 to 135 feet. The
2771typical span length between poles would be 500 to 700 feet, but
2783it can range up to 1 , 000 feet, when necessary to avoid natural or
2797manmade obstacles or other siting constraints.
280345. The co rridors are wider than the rights - of - way that
2817will ultimately be determined in order to allow for flexibility
2827in the final selection of the rights - of - way. The proposed
2840rights - of - way would be reviewed by the agencies to insure
2853compliance with the Condition s of Certification.
286046. Each transmission line would be designed, constructed,
2868operated, and maintained in compliance with good engineering
2876practices and all applicable codes, standards, and industry
2884guidelines, including the National Electric Safety Code , the
2892North American Electric Reliability Corporation, the American
2899Society of Civil Engineers, requirements of the Florida Public
2908Service Commission and the Federal Energy Regulatory Commission,
2916the DOT Utility Accommodation Guide, applicable local and st ate
2926government requirements, and TEC's internal design standards.
2933TEC designs all of its 230 kV transmission lines to withstand a
2945130 - mile - per - hour wind band, which exceeds the criteria in the
2960National Electric Safety Code.
2964Electric and Magnetic Fields
29684 7. The electric field produced by a transmission line is
2979relatively constant over time. The magnetic field fluctuates
2987over time depending on the load on the line. Electric and
2998magnetic fields have been calculated for each of the
3007configurations that may be used for the Project, based on the
3018maximum requested voltage and current. The maximum expected
3026levels for the electric and magnetic fields are within the limits
3037in Florida Administrative Code Chapter 62 - 814.
304548. Considerable scientific research has b een conducted in
3054the past 30 years to understand the potential health effects
3064associated with electric and magnetic fields. There is general
3073agreement among scientists in national and international health
3081agencies that the available evidence does not show adverse health
3091effects can occur from exposure to the electric and magnetic
3101fields associated with transmission lines.
310649. The DepartmentÓs limits for electric and magnetic
3114fields at the edge of a transmission line right - of - way are lower
3129than the limits recommended by the World Health Organization.
3138Noise Impacts
314050 . The noise limits applicable to the Project are those
3151contained in the Polk Land Development Code and the in the rules
3163of the Environmental Protection Commission of Hillsborough
3170County. The Polk County noise limits are 75 decibels, A - weighted
3182measurement (ÐdBAÑ) from 7:00 a.m. to 9:00 p.m. for non -
3193residential areas and 65 dBA from 7:00 a.m. to 9:00 p.m. for
3205residential areas. The noise requirements applicable to
3212transmission lines in Hillsb orough County are 60 dBA from
32227:00 a.m. to 10:00 p.m. and 55 dBA from 10:00 p.m. to 7:00 a.m.
323651. Noise levels measured at four locations in the vicinity
3246of the Project site varied between 41.9 and 51.1 dBA. Offsite
3257noise levels during construction of P roject facilities at the
3267power station would be minimal because of the distance from the
3278construction area to the site boundaries. Noise levels at the
3288power station during operation are not expected to differ
3297significantly from existing levels.
330152. Audib le noise associated with transmission lines is
3310usually associated with Ðcorona,Ñ which is a phenomenon that
3320occurs when there is an irregularity on the surface of the
3331conductors, such as water droplets or other significant
3339particles. If the noise occurs d uring a rainstorm it is usually
3351masked by the noise of the rain. At other times, corona noise
3363will often be masked by other outdoor noises.
337153. Noise calculations were conducted for the proposed
3379transmission lines and ranged from 32.0 to 45.2 dBA. Thes e
3390levels do not exceed the applicable limits.
3397Wetlands and Terrestrial Ecology
340154. The areas proposed for the ProjectÓs generating and
3410associated facilities have been altered by the construction and
3419operation of the Polk Power Station. These areas are a lso
3430surrounded by lands altered by phosphate mining and reclamation.
3439Wildlife habitats have already been destroyed, altered, or
3447diminished by these activities and no longer have high functional
3457values.
345855. Construction activities at the power plant site would
3467not disturb any native or reclaimed wetland or upland habitats.
347756. Wildlife species expected to be found onsite would be
3487common species for the region. Only two listed species of
3497special concern were documented at the power station, the
3506American A lligator and Tricolored Heron. They are both found in
3517the reclaimed wetland west of the construction area and would not
3528be affected. Impacts to other wildlife caused by construction at
3538the Polk Power Station would be temporary and insignificant.
354757. The re are no known threatened or endangered plant
3557species at the Polk Power Station. No reclaimed or natural
3567upland or wetland habitats are proposed to be affected.
357658. Wildlife habitats along the proposed transmission line
3584corridors includes pine flat woo ds, mixed forested uplands, and
3594various wetlands, including cypress forests, mixed hardwood
3601swamps, and marshes. Surrounding land covers are dominated by
3610current or former phosphate mining, farmsteads, or landscaped
3618residential properties. The Balm - Boyet te Scrub Preserve, Little
3628Manatee River, Hurrah Creek, Fishhawk Creek, and Little Fishhawk
3637Creek provide the best wildlife habitats along the transmission
3646line corridors, but the corridors would cross these areas where
3656there are already existing transmissi on line rights - of - way or
3669roads.
367059. Wildlife found along the corridors are species commonly
3679found in the region. No listed species are known to occur.
3690Construction and maintenance of the transmission lines within the
3699corridors would not significantly im pact the habitats of fish and
3710wildlife found in these areas.
371560. Impacts to vegetation along the transmission line
3723corridors would be minimized by siting the rights - of - way within
3736the most disturbed areas or on existing road and transmission
3746line rights - o f - way. TEC would span all open waters such as
3761streams and tributaries. For smaller water crossings and
3769wetlands, the facilities would be co - located with existing linear
3780facilities to minimize impacts. Restrictive clearing practices
3787on forested wetlands would be utilized, removing vegetation
3795selectively. Impacts from filling would be avoided or minimized
3804to the greatest extent practicable through a careful alignment of
3814the transmission line rights - of - way and through the choice of
3827span distances between s tructures. Where wetland impacts cannot
3836be avoided, the impacts would be minimized and mitigation would
3846be provided.
384861. Prior to the final selection of rights - of - way and the
3862beginning of construction, surveys would be conducted to
3870determine the presenc e of protected plant and animal species and
3881the results would be shared with the FWC to determine if
3892mitigation may be required in accordance with Conditions of
3901Certification.
3902Archeological and Historic Sites
39066 2 . When the Polk Power Station was first cer tified and
3919subsequently, archeological surveys were conducted to determine
3926the presence of cultural and historical resources of
3934significance. No such resources were identified.
39406 3 . Cultural and historical resources in the study area for
3952the transmission line corridors were evaluated during the
3960corridor selection process. All National Register of Historic
3968Places sites and districts as well as other known cultural
3978resources were mapped and candidate corridors were laid out to
3988avoid those resources. Corrid ors were laid out to co - locate with
4001other transmission lines and linear facilities that have already
4010disturbed the land to reduce the potential for new disturbances
4020to cultural resources.
40236 4 . After the rights - of - way within the corridors have been
4038determin ed, cultural resource surveys would be conducted to
4047identify the location of any archeological or historical
4055resources and determine potential impacts whether they can be
4064avoided. The surveys would be submitted to the Division of
4074Natural Resources for its review and consideration.
4081Transportation Impacts
40836 5 . No additional transportation impacts are expected from
4093the operation of the Project because there would be no addition
4104to the current Polk Power Station staff of 78 employees to
4115operate all facilitie s.
41196 6 . The construction phase would generate 357 daily trips
4130by construction workers and 50 additional delivery trips. The
4139trip distribution per day is expected to be 228 northbound trips
4150on State Road 37, 82 southbound trips on State Road 37, 75
4162northb ound trips on Fort Green Road, and 22 southbound trips on
4174Fort Green Road. Even at the peak of construction activities,
4184the surrounding roadway network is expected to operate at
4193acceptable levels of service.
4197Land Use Compatibility
42006 7 . The Project facili ties would be located within the
4212existing power station site, which is the logical and efficient
4222location for the Project. There are no conflicting land uses in
4233the vicinity of the Project site.
42396 8 . Most of the land uses along the corridors are former
4252a nd active phosphate mining lands, undeveloped lands,
4260agriculture, and rural residences. The key exception is the
4269segment of the Polk - Fishhawk Corridor that runs through the
4280developed Fishhawk Community, which is a suburban residential
4288areaansmission lines of the types proposed are frequently
4296located in proximity to all of these affected land uses,
4306including the suburban residential areas.
431169 . It is officially recogni zed that many people, if given
4323a choice, would prefer not to have high voltage transm ission
4334lines near their homes, primarily based on aesthetic
4342considerations. However, it is also official ly recogni zed that
4352many people are willing to live near transmission lines. Until
4362there is a practical alternative to above - ground transmission
4372lines, they will have to be located in developed areas in order
4384to supply electricity to residences. The proposed transmission
4392lines are not incompatible with residential uses.
43997 0 . Polk County and Hillsborough County do not oppose the
4411Project on any basis, inc luding land use compatibility. The
4421Project is consistent with the comprehensive plans and the land
4431development regulations of these counties.
4436Soci oe conomic Impacts
44407 1 . The Project would provide additional clean and reliable
4451energy, additional jobs durin g construction, an increased
4459property tax base, and increased economic activity in the form of
4470purchases of goods and services.
44757 2 . Local revenues from property taxes levied on the new
4487plant facilities would primarily benefit Polk County. The
4495estimated additional property tax revenue is between $6 million
4504and $6.5 million annually.
45087 3 . Significant revenues are also expected from sales taxes
4519on goods purchased directly for the plant or indirectly from
4529purchases of goods and services by the construction w orkers.
4539Sales taxes are estimated to be $105,000 per year.
45497 4 . Construction of the Project would employ an average of
4561250 workers, with a peak projected in 2015 of about 500 workers.
4573Most of the construction workers would be drawn from an area
4584within a commuting distance from the Project site. The
4593construction payroll for the overall Project is expected to be
4603$88 million and much of this would likely be spent in Polk County
4616and the region.
4619Site Boundaries
46217 5 . TEC requests that the boundaries of the P olk Power
4634Station site be reduced from 4,348 acres to 2,837 acres to
4647reflect that the original certification required a donation of
46561,511 acres to the Board of Trustees of the Internal Improvement
4668Trust Fund as a wildlife management area and recreation are a.
4679The donation was completed in 2012.
4685Construction Schedule
46877 6 . Construction of the project is anticipated to begin in
4699January 2014 and be completed in time to allow commercial
4709operation in January 2017.
4713Public Notice and Participation
47177 7 . TEC enga ged in extensive public outreach for the
4729Project, using direct mail, a survey, public meetings, newspaper
4738advertisements, a project webpage, a toll - free telephone number
4748for information, and communications with agencies and public
4756officials.
47577 8 . TEC used two direct mailings, totaling over 10,000
4769letters in both English and Spanish. The letters were mailed to
4780landowners and residents within one - quarter mile of the proposed
4791transmission line corridors, all homeowners' associations within
4798one mile, and all landowners and residents within three miles of
4809the plant site boundaries.
481379 . Three public meetings were held regarding the Project.
4823The first meeting was held on April 10, 2012 , at the Little Union
4836Baptist Church. The second was on April 12, 2012 , at the
4847Fishhawk Fellowship Church. The third was on April 19, 2012 , at
4858the Wimauma Senior Center.
48628 0 . TEC held meetings with county commissioners, mayors,
4872state senators, and state representatives to inform them of the
4882Project and the certification process . TEC representatives also
4891met with developers in Hillsborough County who could be affected
4901by the corridors to provide information and answer questions.
49108 1 . Copies of the Application were available for inspection
4921at the Polk County Library in Bartow an d the John Germany Public
4934Library in Tampa. A copy was also available for public review at
4946TECÓs offices in Tampa.
49508 2 . On October 24, 2012, public notice of the filing of the
4964Application was published in The Tampa Tribune and The Ledger .
4975On April 18, 2 013, notice of the Certification Hearing was
4986published in The Tampa Tribune and The Ledger and on April 19,
49982013 , in the Tampa Bay Times . When the certification hearing was
5010rescheduled, TEC published notice of the rescheduling in The
5019Tampa Tribune , The Le dger , and the Tampa Bay Times on June 16,
50322013.
50338 3 . The Department published notices of the Application,
5043the certification hearing, the public testimony hearing, and
5051rescheduling the certification hearing in the Florida
5058Administrative Register . Hillsbor ough County published notice of
5067the public testimony portion of the proceeding in The Tampa
5077Tribune on June 19, 2013.
5082Public Testimony
50848 4 . A hearing was held in Lithia, Florida , on June 25,
50972013, in the Fishhawk Community to provide members of the public
5108who are not parties to the certification proceeding an
5117opportunity to present sworn testimony concerning the
5124transmission line portion of the Project. Twelve members of the
5134public testified. Eight comment letters were received into the
5143record as Public Testimony Composite Exhibit 1.
51508 5 . A number of the residents expressed anger about what
5162they perceived as the failure of the developer who sold them
5173their homes, and TEC, to disclose to them that a transmission
5184line might be constructed near their homes. As previously
5193stated, the corridor is on property owned or controlled by TEC
5204for the installation of transmission lines. The record evidence
5213does not indicate any duty to disclose, any misrepresentation, or
5223any obfuscation by TEC in this regard. If ther e was a failure to
5237disclose or a misrepresentation by the developer, those are
5246matters between the homeowners and the developer and beyond the
5256scope of this proceeding.
52608 6 . Several residents expressed concern about possible
5269adverse health effects from ex posure to electric and magnetic
5279fields associated with the transmission lines. However, no
5287speaker referred to personal knowledge or to any study results to
5298support their comments on this subject. It is likely, therefore,
5308that their concerns are based on rumors or speculation. As
5318discussed above, independent scientists have not been able to
5327substantiate the occurrence of adverse health effects from
5335exposure to the electric and magnetic fields associated with
5344transmission lines.
53468 7 . There is a tennis cou rt and there are nature trails
5360underneath existing transmission lines located in another part of
5369the Fishhawk Community, indicating that the fear of electrical
5378and magnetic fields is not universal.
53848 8 . Some residents urged that TEC be required to install
5396the portion of the transmission line in the Fishhawk Community
5406underground. There are substantial engineering difficulties
5412associated with underground installation of high voltage
5419transmission lines. TEC has never installed this type of
5428transmission lin e underground. The cost for underground
5436installation could be as much as 15 times greater than for
5447overhead installation.
5449Agency Reports
545189 . Agency reports with proposed conditions of
5459certification were submitted to the Department by SWFWMD, FWC,
5468Florid a Department of Transportation, Hillsborough County, and
5476Hillsborough County Environmental Protection Commission.
54819 0 . Agency Reports without recommended conditions of
5490certification were submitted by the Florida Department of
5498Economic Opportunity, Central Florida Regional Planning Council,
5505Tampa Bay Regional Planning Council, and Polk County.
55139 1 . The Department of State, Division of Historical
5523Resources did not file an agency report, but recommended
5532conditions in its Completeness Review.
55379 2 . On January 28, 2013, The Department issued its Project
5549Analysis Report for the transmission line portion of the Project,
5559incorporating the reports of the reviewing agencies and proposing
5568Conditions of Certification.
55719 3 . On April 26, 2013, the Department issued its Project
5583Analysis Report on the power plant and proposed Conditions of
5593Certification. The Report was modified on May 21, 2013.
56029 4 . No agency opposes certification of the Project.
5612Conditions of Certification
56159 5 . The Department recommends certification of the Project
5625subject to the revised Conditions of Certification set forth in
5635Department Exhibit 8, which supersedes all prior statement s of
5645conditions. The Conditions of Certification address numerous
5652subjects and are designed to e nsure that the construct ion and
5664operation of the Project is protective of the public and the
5675environment.
56769 6 . The Conditions of Certification provide for post -
5687certification reviews and investigations to confirm, for example,
5695that sensitive areas will be avoided and that transmis sion lines
5706structures will avoid or have minimal adverse impacts.
57149 7 . TEC has agreed to construct, operate, and maintain the
5726Project in compliance with the Conditions of Certification. No
5735variances or exemptions from applicable state, regional, or local
5744standards or ordinances have been requested or are needed for the
5755construction, operation, and maintenance of the Project.
5762Certification Considerations
576498 . In determining whether TEC's application for the
5773Project should be approved, approved with conditi ons, or denied,
5783the Siting Board must determine whether, and the extent to which,
5794the location, construction, and operation of the Project would:
5803(a) Provide reasonable assurance that the
5809operational safeguards are technically
5813sufficient for the public we lfare and
5820protection.
5821(b) Comply with applicable nonprocedural
5826requirements of agencies.
5829(c) Be consistent with applicable local
5835government comprehensive plans and land
5840development regulations.
5842(d) Meet the electrical energy needs of the
5850state in an orderly, reliable, and timely
5857fashion.
5858(e) Effect a reasonable balance between the
5865need for the facility as established pursuant
5872to s. 403.519 and the impacts upon air and
5881water quality, fish and wildlife, water
5887resources, and other natural resources of the
5894state resulting from the construction and
5900operation of the facility.
5904(f) Minimize, through the use of reasonable
5911and available methods, the adverse affects on
5918human health, the environment, and the
5924ecology of the land and its wildlife and the
5933ecology of state waters and their aquatic
5940life.
5941(g) Serve and protect the broad interests of
5949the public.
5951§ 403.509(3), Fla. Stat.
595599 . The evidence presented demonstrates that the location,
5964construction, and operation of the Project would provide
5972reasonable as surance that the operational safeguards are
5980technically sufficient for the public welfare and protection.
598810 0 . The evidence presented demonstrates that the location,
5998construction, and operation of the Project would comply with
6007applicable nonprocedural req uirements of agencies.
601310 1 . The evidence presented demonstrates that the location,
6023construction, and operation of the Project would be consistent
6032with applicable local comprehensive plans and land development
6040regulations.
604110 2 . The evidence presented de monstrates that the location,
6052construction, and operation of the Project would meet the
6061electric energy needs of the state in an orderly, reliable, and
6072timely fashion.
607410 3 . The evidence presented demonstrates that the location,
6084construction, and operatio n of the Project would effect a
6094reasonable balance between the need for the facility as
6103established pursuant to section 403.519 and the impacts upon air
6113and water quality, fish and wildlife, water resources, and other
6123natural resources of the state.
612810 4 . The evidence presented demonstrates that the location,
6138construction, and operation of the Project would minimize,
6146through the use of reasonable and available methods, the adverse
6156effects on human health, the environment, and the ecology of the
6167land and it s wildlife and the ecology of state waters and their
6180aquatic life.
618210 5 . The evidence presented demonstrates that the location,
6192construction, and operation of the Project would serve and
6201protect the broad interests of the public.
6208CONCLUSIONS OF LAW
621110 6 . The parties stipulated that there are no disputed
6222issues of law.
622510 7 . This certification proceeding is governed by the
6235Florida Electrical Power Plant Siting Act, chapter 403, Part II,
6245Florida Statutes, and Florida Administrative Code Chapter 62 - 17.
6255108 . TEC, the Department, Hillsborough County, SWFWMD, and
6264FWC have standing to participate as parties.
62711 09 . Public notice was provided in compliance with the
6282requirements of section 403.515 and other applicable law.
62901 10 . The evidence presented in this pr oceeding demonstrates
6301that the Project favorably satisfies all of the factors in
6311section 403.509(3) that the Siting Board must consider in
6320determining whether to certify the Project.
6326RECOMMENDATION
6327Based upon the foregoing Findings of Fact and Conclusions of
6337Law, it is
6340RECOMMENDED that the Siting Board enter a final order:
6349a. approving TEC's application for certification to
6356construct, operate, and maintain the Polk 2 - 5 Combined Cycle
6367Conversion Project, including its associated transmission lines,
6374subjec t to the Conditions of Certification set forth in
6384Department Exhibit 8;
6387b. approving the increase in ultimate site capacity for the
6397Polk Power Station site from the previously approved 1150
6406megawatts to 1420 megawatts; and
6411c. modifying the Polk Power St ation site boundaries from
64214 , 348 acres to 2 , 837 acres, as depicted in TEC Exhibit 5.
6434DONE AND ENTERED this 23rd day of August , 2013 , in
6444Tallahassee, Leon County, Florida.
6448S
6449BRAM D. E. CANTER
6453Administrative Law Judge
6456Divis ion of Administrative Hearings
6461The DeSoto Building
64641230 Apalachee Parkway
6467Tallahassee, Florida 32399 - 3060
6472(850) 488 - 9675
6476Fax Filing (850) 921 - 6847
6482www.doah.state.fl.us
6483Filed with the Clerk of the
6489Division of Administrative Hearings
6493this 23rd day of Augus t , 2013 .
6501COPIES FURNISHED:
6503Lawrence N. Curtin, Esquire
6507Holland and Knight LLP
6511Suite 600
6513315 South Calhoun Street
6517Tallahassee, Florida 3230 1
6521Toni Sturtevant, Esquire
6524Department of Environmental Protection
6528Douglas Building, Mail Station 35
65333900 Comm onwealth Boulevard
6537Tallahassee, Florida 32399 - 3000
6542Kimberly Clark Menchion, Esquire
6546Department of Transportation
6549Mail Station 58
6552605 Suwannee Street
6555Tallahassee, Florida 32399
6558Anthony Justin Pinzino, Esquire
6562Florida Fish and Wildlife
6566Conservation C ommission
6569620 South Meridian Street
6573Tallahassee, Florida 32399
6576Adam Teitzman, Esquire
6579Florida Public Service Commission
65832450 Shumard oak Boulevard
6587Tallahassee, Florida 32399 - 0850
6592Michael S. Craig, Esquire
6596Polk County Attorney ' s Office
6602330 West Church Street, Drawer AT01
6608Post Office Box 9005
6612Bartow, Florida 33831 - 9005
6617Marva M. Taylor, Esquire
6621Hillsborough County Attorney`s Office
662527th Floor
6627601 East Kennedy Boulevard
6631Tampa, Florida 33602 - 4156
6636Richard Tschantz, Esquire
6639Environmental Protection Comm ission
6643of Hillsborough County
66463629 Queen Palm Drive
6650Tampa, Florida 33619
6653Patricia Anderson
6655Department of Health
6658Environmental Engineering
66604042 Bald Cypress Way
6664Tallahassee, Florida 32399 - 1742
6669Laura Kammerer
6671Bureau of Historic Preservation
6675R. A. Gray Building
6679500 South Bronough
6682Tallahassee, Florida 32399
6685Manny L. Pumariega
6688Tampa Bay Regional Planning Council
6693Suite 100
66954000 Gateway Center Boulevard
6699Pinellas Park, Florida 33782
6703Patricia M. Steed
6706Central Florida Regional
6709Planning Council
6711555 East Ch urch Street
6716Bartow, Florida 33830 - 3931
6721Forrest Watson
6723Department of Agriculture and
6727Consumer Services
6729Division of Forestry
67323125 Conner Boulevard
6735Tallahassee, Florida 32399 - 1650
6740Martha A. Moore, Esquire
6744Southwest Florida Water Management District
67497601 Highway 301 North
6753Tampa, Florida 33637
6756Herschel T. Vinyard, Jr., Secretary
6761Department of Environmental Protection
6765Douglas Building, Mail Station 35
67703900 Commonwealth Boulevard
6773Tallahassee, Florida 32399 - 3000
6778Matthew Z. Leopold, General Counsel
6783Depar tment of Environmental Protection
6788Douglas Building, Mail Station 35
67933900 Commonwealth Boulevard
6796Tallahassee, Florida 32399 - 3000
6801Lea Crandall, Agency Clerk
6805Department of Environmental Protection
6809Douglas Building, Mail Station 35
68143900 Commonwealth Boulevar d
6818Tallahassee, Florida 32399 - 3000
6823NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6829All parties have the right to submit written exceptions within
683915 days from the date of this Recommended Order. Any exceptions
6850to this Recommended Order should be filed with the ag ency that
6862will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 12/12/2013
- Proceedings: Tampa Electric Company's and Florida Department of Environmental Protection's Joint Exceptions to Recommended Order filed.
- PDF:
- Date: 09/09/2013
- Proceedings: Tampa Electric Company's and Florida Department of Environmental Protection's Joint Exception to Recommended Order filed.
- PDF:
- Date: 08/23/2013
- Proceedings: Recommended Order On Certification (hearing held June 25-26, 2013). CASE CLOSED.
- PDF:
- Date: 08/23/2013
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 08/06/2013
- Proceedings: Notice of Filing Tampa Electric Company's and Florida Department of Environmental Protection's Joint Proposed Recommended Order on Certification filed.
- Date: 07/12/2013
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 07/12/2013
- Proceedings: Transcript (not available for viewing) filed.
- Date: 06/28/2013
- Proceedings: Petitioner's Proposed Exhibits filed (exhibits not available for viewing).
- Date: 06/25/2013
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 06/24/2013
- Proceedings: Notice of Filing Revised Proposed Conditions of Certification filed.
- PDF:
- Date: 06/19/2013
- Proceedings: Notice of Availability and Distribution of Pre-filed Direct Testimony and Exhibits (exhibits not available for viewing) filed.
- PDF:
- Date: 06/19/2013
- Proceedings: Notice of Availability and Distribution of Pre-filed Direct Testimony and Exhibits filed.
- PDF:
- Date: 06/05/2013
- Proceedings: Amended Notice of Hearing (hearing set for June 26, 2013; 10:00 a.m.; Bartow, FL; amended as to dates and hearing locations).
- PDF:
- Date: 05/21/2013
- Proceedings: Notice of Filing Revised Project Analysis Report for Plant Portion of Project filed.
- PDF:
- Date: 04/26/2013
- Proceedings: Notice of Filing Project Analysis Report for Plant Portion of Project filed.
- PDF:
- Date: 03/25/2013
- Proceedings: Southwest Florida Water Management District's Notice of Filing District Agency's Report filed.
- PDF:
- Date: 03/25/2013
- Proceedings: Florida Fish and Wildlife Conservation Commission Notice of Intent to be Party filed.
- PDF:
- Date: 03/11/2013
- Proceedings: Southwest Florida Management District's Notice of Intent to be Party filed.
- PDF:
- Date: 01/28/2013
- Proceedings: Notice of Filing Project Analysis Report for Transmission Line Portion of Project filed.
- PDF:
- Date: 12/21/2012
- Proceedings: Amended Stipulation and Joint Motion to Alter Schedule [amended to correct scriveners error in proposed schedule] filed.
- PDF:
- Date: 12/21/2012
- Proceedings: Stipulation and Joint Motion to Alter Schedule (proposed schedule attached) filed.
- PDF:
- Date: 12/17/2012
- Proceedings: Department of Environmental Protection's Determination that Power Plant and Transmission Line Portions of Application are Complete filed.
- PDF:
- Date: 12/07/2012
- Proceedings: Order (granting Hillsborough County's request to become a party).
- PDF:
- Date: 12/07/2012
- Proceedings: Hillsborough County's Request to Become a Party to Tampa Electric Company's Polk Power Station 2-5 Combined Cycle Conversion Project Site Certification Hearing filed.
- PDF:
- Date: 12/03/2012
- Proceedings: Polk Power Station 2-5 Combined Cycle Conversion Project Completeness Submittal-Power Plant and Transmission Lines filed.
- PDF:
- Date: 11/26/2012
- Proceedings: Tampa Electric Company's Response to Department of Environmental Protection's Determination that Power Plant and Transmission Line Portions of Site Certification Application are Incomplete filed.
- PDF:
- Date: 11/26/2012
- Proceedings: Hillsborough County's Request for a Public Hearing Supplementing the Certification Hearing filed.
- PDF:
- Date: 11/13/2012
- Proceedings: Department of Environmental Protection's Determination that Power Plant and Transmission Line Portions of Application are Incomplete filed.
- PDF:
- Date: 10/23/2012
- Proceedings: Notice of Hearing (hearing set for June 24 through 28, 2013; 9:00 a.m.; Bartow, FL).
- PDF:
- Date: 10/15/2012
- Proceedings: Notice of Filing Site Certification Application for Power Plant Certification filed.
- PDF:
- Date: 10/11/2012
- Proceedings: Polk 2-5 Combined Cycle Conversion Project, Polk Power Station Site Certification Application Volumes 1 and 2, filed.
Case Information
- Judge:
- BRAM D. E. CANTER
- Date Filed:
- 10/11/2012
- Date Assignment:
- 10/15/2012
- Last Docket Entry:
- 12/12/2013
- Location:
- Bartow, Florida
- District:
- Middle
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- EPP
Counsels
-
Patricia Anderson
Address of Record -
Michael S. Craig, Esquire
Address of Record -
Lawrence N. Curtin, Esquire
Address of Record -
Laura Kammerer
Address of Record -
Kimberly Clark Menchion, Assistant General Counsel
Address of Record -
Martha A. Moore, Esquire
Address of Record -
Anthony Justin Pinzino, Esquire
Address of Record -
Manny L. Pumariega
Address of Record -
Patricia M. Steed
Address of Record -
Toni L. Sturtevant, Esquire
Address of Record -
Marva M. Taylor, Esquire
Address of Record -
Adam Teitzman, Esquire
Address of Record -
Richard Tschantz, Esquire
Address of Record -
Forrest Watson
Address of Record -
Adam Jared Teitzman, Esquire
Address of Record -
Richard Thomas Tschantz, Esquire
Address of Record -
Adam Jared Teitzman, Commission Clerk
Address of Record