13-000685BID
James Hinson Electrical Contracting Company, Inc. vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, June 21, 2013.
Recommended Order on Friday, June 21, 2013.
1Case No. 13-0685BID
4STATE OF FLORIDA
7DIVISION OF ADMINISTRATIVE HEARINGS
11JAMES HINSON ELECTRICAL
14CONTRACTING COMPANY, INC.,
17RECOMMENDED ORDER
19Petitioner,
20vs.
21DEPARTMENT OF TRANSPORTATION,
24Respondent.
25/
26Pursuant to notice, a formal hearing was held in this case
37on May 1, 2013, in Jacksonville, Florida, before W. David
47Watkins, the duly-designated Administrative Law Judge of the
55Division of Administrative Hearings.
59APPEARANCES
60For Petitioner: E. Lanny Russell, Esquire
66Jonathan Huffman, Esquire
69Smith, Hulsey & Busey
73225 Water Street, Suite 1800
78Jacksonville, Florida 32202
81For Respondent: C. Denise Johnson, Esquire
87Department of Transportation
90605 Suwannee Street, M.S. 58
95Haydon Burns Building
98Tallahassee, Florida 32399
101STATEMENT OF THE ISSUE
105Whether the Department of Transportation's (DOT) intended
112decision to award contract T2442 for the Intelligent
120Transportation System improvements (Project) and other
126incidental construction on State Road 9A, in Duval County, to
136American Lighting & Signalization, Inc. (ALS), is contrary to
145the agency's governing statutes, the agency's rules or policies,
154or the bid or proposal specifications.
160PRELIMINARY STATEMENT
162On October 24, 2012, DOT posted notice of its intent to
173award the contract for the Project to ALS. Thereafter, Hinson
183Electrical Contracting Company, Inc. (Hinson Electrical) timely
190filed a notice of protest and formal protest (with the required
201bond) of DOT's intended action. DOT referred this matter to the
212Division of Administrative Hearings (DOAH). ALS did not
220petition to intervene in this proceeding and is not a party
231hereto.
232This matter was initially assigned to Administrative Law
240Judge Jessica Varn, who issued a Notice of Hearing and an Order
252of Pre-hearing Instructions on February 26, 2013. On
260February 25, 2013, a scheduling teleconference was convened
268wherein the 30-day requirement to conduct a hearing was waived
278by the parties. On March 19, 2013, the Department filed an
289Unopposed Motion for Continuance, which was granted by Order
298dated March 22, 2013. The matter was transferred to the
308undersigned on March 26, 2013, and on April 3, 2013, an Order
320re-scheduling the hearing was entered scheduling the final
328hearing for May 1, 2013, in Jacksonville, Florida.
336The final hearing was held as scheduled. The 135-page
345Transcript was filed with DOAH on May 21, 2013, and Petitioner
356and Respondent timely filed their proposed findings of fact and
366conclusions of law on May 31, 2013. Prior to the hearing, the
378parties filed a Joint Pre-Hearing Stipulation with extensive and
387detailed admitted facts. The evidence presented at the hearing
396and the submissions from the parties have been carefully
405considered in the preparation of this Recommended Order.
413At the hearing, Hinson Electrical presented the testimony
421of its president and principal, J. Daniel Hinson, as well as its
433project manager, Chris Ginn. DOT presented the testimony of
442Juanita Moore, the manager of the Contracts Administration
450Office within DOT. A transcript of the deposition of Colette
460Jackson (a DOT employee who did not testify at the hearing) was
472received into evidence at the hearing. Hinson Electrical's
480Exhibits numbered 1-8, 11-24, and 30 were received into evidence
490without objection, and Hinson Electrical's Exhibits numbered 9,
49810, and 29 were received into evidence over DOT's objection.
508DOT's Exhibits numbered 1-6, were all received into evidence
517without objection.
519FINDINGS OF FACT
522Based upon the demeanor and credibility of the witnesses
531and other evidence presented at the final hearing and on the
542entire record of this proceeding, the following findings of fact
552are made: 1 /
5561. The contract being protested is T2442 for the
565Intelligent Transportation System improvements and other
571incidental construction for State Road 9A, in Duval County. The
581Department advertised the bid solicitation notice for the
589Project on July 27, 2012.
5942. The bid solicitation notice included a list of all of
605the pay items and estimated quantities for the project. DOT
615also posted all of the pay items online in two formats. One
627format was a downloadable file that could be used in software,
638and the other was similar to an Excel spreadsheet file. These
649formats could be used to formulate a bid. Changes to pay items
661are issued in an Addendum, and while two addendums were issued
672for this project, neither affected the pay items for the
682project.
6833. For several years, DOT has mandated that prospective
692bidders use an automated, online bidding process, by which
701prospective bidders request bid documents and submit their bids
710using the DOT's website.
7144. The letting date established as the deadline for
723submission of bids via electronic submission was September 26,
7322012, and was set forth in the bid solicitation notice. In
743order to be considered, all bids were due by 10:30 a.m. on that
756day. Letting is the term used to indicate the date that the
768bids are due.
7715. The bid solicitation notice included a requirement that
780bidders for the Project attend a mandatory pre-bid meeting to be
791held on August 20, 2012.
7966. Hinson Electrical is a licensed electrical contracting
804company based in Jacksonville, Florida. The company has
812completed "hundreds" of projects for the State of Florida,
821including DOT, and is pre-qualified to bid on jobs with DOT.
8327. The mandatory pre-bid meeting was held on August 20,
8422012, as scheduled. G. Christopher Ginn, Project Manager for
851Hinson Electrical, attended the pre-bid meeting, signed his
859name, and identified the company he represented (Hinson
867Electrical) on the sign-in sheet.
8728. Section 337.168(2), Florida Statutes, provides:
878(2) A document revealing the identity
884of persons who have requested or obtained
891bid packages, plans, or specifications
896pertaining to any project to be let by the
905department is confidential and exempt from
911the provisions of section 119.07 (1) for the
919period which begins two working days prior
926to the deadline for obtaining bid packages,
933plans, or specifications and ends with the
940letting of the bid.
9449. As a business strategy, Hinson Electrical routinely
952orders bid documents within the two-day blackout period mandated
961by section 337.168(2), during which time DOT is required to take
972down its list of contractors who have requested bid documents
982concerning a particular project. Ordering bid documents within
990the blackout period prevents competitors from discovering
997whether Hinson Electrical is bidding for a particular project.
100610. The blackout period for the Project began at 5:00 p.m.
1017on Friday, September 21, 2012.
102211. The deadline to order the bid documents for the
1032Project was 10:30 a.m. on September 25, 2012. There is no
1043requirement that contractors request bid documents prior to the
1052pre-bid meeting (if one is required for a particular project),
1062or at any time prior to the order deadline, which is 24 hours
1075before the bid deadline. DOT acknowledged at hearing that it is
1086Hinson Electrical's prerogative to order the bid documents
1094within the blackout period during which the identities of
1103bidders are kept confidential.
110712. Hinson Electrical ordered the bid documents for the
1116Project at approximately 1:00 p.m. on September 24, 2012. The
1126computerized system immediately provided access for Hinson
1133Electrical to download the plans and specifications for the
1142project at issue. However, four minutes later, at approximately
11511:04 p.m., Hinson Electrical simultaneously received an email
1159with a "Prequalification Failure Notice," and a second email
1168stating that the bid document request for the Project was
"1178pending." The Prequalification Failure Notice indicated that
1185the bid document was not provided because Hinson Electrical had
1195not attended the required pre-bid meeting for the Project. 2 /
1206Failure to attend the pre-bid meeting was the only basis stated
1217in the Prequalification Failure Notice for DOT refusing to
1226provide the bid document.
123013. As noted, Hinson Electrical's representative did in
1238fact attend the pre-bid meeting for the Project, and he signed
1249the sign-in sheet, attesting to his presence at the meeting.
1259The sign-in sheet had been transmitted to DOT on August 21,
12702012, the day after the pre-bid meeting was held. Thus, DOT's
1281basis for sending Hinson Electrical a Prequalification Failure
1289Notice was in error.
129314. The Prequalification Failure Notice also stated,
"1300[Y]ou will be contacted by email or phone as soon as possible
1312during business hours regarding requirements for obtaining the
1320bid documents." However, DOT did not send an email or call
1331Hinson Electrical after 1:04 p.m. on September 24, 2012, or at
1342any time on September 25, 2012.
134815. Phillip Davis, a DOT employee in the Contracts
1357Administration Office, was "blind copied" on the Hinson
1365Electrical Prequalification Failure Notice email, with a "high
1373importance" tag. Mr. Davis' job responsibilities include
1380following up on these types of notices, though he is not
1391supervised to ensure this occurs. Mr. Davis' responsibilities
1399also include checking sign-in sheets from pre-bid meetings to
1408authorize release of bid documents to contractors. DOT admits
1417that Mr. Davis did not read the Hinson Electrical
1426Prequalification Failure Notice; did not check the sign-in sheet
1435from the pre-bid meeting; and made no attempt to contact Hinson
1446Electrical, as promised in the notice.
145216. From September 20 through 25, 2012, Daniel Hinson and
1462Chris Ginn obtained quotes from suppliers and subcontractors to
1471prepare a bid for the Project. Hinson Electrical also secured a
1482bid bond for the Project, and had everything necessary to submit
1493a bid, except for the actual bid document.
150117. In the afternoon or early evening of September 25,
15112012, Daniel Hinson sat down at his computer with the price
1522lists and quotes he had obtained to prepare a bid for the
1534Project. It was then that Mr. Hinson discovered DOT had not
1545granted him access to the bid document for this Project, and
1556that the failure notice he had received pertained to this
1566Project, and was in error. Hinson Electrical was bidding on a
1577total of eight contracts at that time, some of which did not
1589have a mandatory pre-bid meeting.
159418. As of the close of business on September 25, 2012, DOT
1606had still not made any effort to contact Hinson Electrical, as
1617promised in the failure notice.
162219. At 7:55 p.m. on September 25, 2012, Hinson Electrical
1632sent an email to the Contracts Administration general email
1641address, stating that Hinson Electrical's representative had
1648attended the pre-bid meeting and asking why Hinson Electrical
1657was being excluded from the bidding.
166320. Shortly after 7:00 a.m. the following morning
1671(September 26, 2012, the bid deadline), Chris Ginn called the
1681project inspector, Thomas Woods of HNTB Corporation, on Hinson
1690Electrical's behalf, and requested that HNTB confirm that Hinson
1699Electrical's representative had attended the pre-bid meeting.
170621. At 7:32 a.m. that same morning, Mr. Woods sent an
1717email to Juanita Moore notifying her of the error and confirming
1728that Hinson Electrical's representative had indeed attended the
1736pre-bid meeting.
173822. The Contracts Administration Office opened at 8:00
1746a.m. on the day of the bidding deadline. Within 36 minutes (by
17588:36 a.m.), Ms. Moore reviewed Mr. Woods' email; checked the
1768sign-in sheet; and instructed a subordinate, Colette Jackson, to
1777send the bid document to Hinson Electrical. Ms. Jackson
1786immediately sent the bid document to Hinson Electrical under a
1796cover email.
179823. Ms. Moore testified that Phillip Davis could have
1807easily gone through these same steps on September 24, 2012 (two
1818days before the bid deadline), and timely transmitted the bid
1828document to Hinson Electrical, if he had only read the
1838Prequalification Failure Notice on which he was copied.
1846Ms. Moore agreed that 24 hours would have been sufficient time
1857for Mr. Davis to check the sign-in sheet and release the bid
1869document.
187024. When DOT finally provided the bid document to Hinson
1880Electrical, it was 1 hour, 54 minutes before the bid submission
1891deadline.
189225. At 8:40 a.m. on September 26, 2012, (four minutes
1902after receiving the bid document) Daniel Hinson spoke by
1911telephone with Colette Jackson about needing additional time to
1920complete Hinson Electrical's electronic bid submission. Colette
1927Jackson testified that one of her responsibilities at DOT is to
1938move bid deadlines, and that she can do so quickly upon
1949receiving instructions from Ms. Moore to do so. However,
1958Ms. Jackson did not have authority to provide the requested
1968relief, so she transferred the call to Ms. Moore.
197726. Upon being transferred to Ms. Moore, Mr. Hinson asked
1987for additional time to complete the Hinson Electrical bid for
1997the Project. That request was refused by Ms. Moore. In her
2008view, the fact that the pay items and estimated quantities for
2019the project had previously been provided should have enabled
2028Hinson Electrical to submit a bid within the two hours remaining
2039prior to the deadline. In addition, Ms. Moore felt Hinson
2049Electrical should have taken it upon itself to contact DOT
2059immediately upon receiving the disqualification notification if
2066it believed it had complied with all prerequisites.
207427. Contrary to Ms. Moore's opinion, Mr. Hinson testified
2083that it would have taken him about four hours to go through the
2096various steps to submit Hinson Electrical's online bid for the
2106Project. DOT's position that Hinson Electrical could have
2114completed and submitted its bid with less than two hours
2124remaining is rejected as not credible. However, even if that
2134were possible, it would have put Hinson Electrical at a
2144disadvantage because every other bidder was able to download the
2154bid document immediately upon request after the pre-bid meeting.
216328. Daniel Hinson has submitted bids for hundreds of DOT
2173projects (including "dozens" using the current online system)
2181and he reasonably believed there was insufficient time remaining
2190before the deadline to prepare a competent bid and ensure its
2201accuracy. Mr. Hinson's testimony regarding the amount of time
2210necessary to prepare a complete and competent bid for the
2220Project is more credible than the testimony of Ms. Moore.
2230Considering the potential cost to Hinson Electrical of a mistake
2240made in haste, it was entirely reasonable for Hinson Electrical
2250to decline to submit a bid, and instead request a bid extension.
2262Likewise, it was unreasonable for DOT to decline the extension
2272request, given that it was DOT's mistake that necessitated the
2282extension.
228329. DOT extends bid deadlines dozens of times each year,
2293for various reasons, including computer issues, mistakes in the
2302bid documents, or bad weather. Ms. Moore testified about bid
2312deadlines that had been moved, three or four times in some
2323cases, for reasons including computer glitches, website issues,
2331and "technical problems." In one such instance, contractors
2339could not obtain their bid documents on the Monday before a
2350Wednesday letting (which is what happened to Hinson Electrical
2359in this case), and DOT postponed the bid deadline. In another
2370instance, a bid deadline was postponed for a third time "because
2381the vendors couldn't download what they needed to bid." And in
2392another example, the bid deadline was postponed with notice
2401provided just 92 minutes before the deadline due to "server
2411issues at the Department." In this final example, once the
2421malfunction was identified, DOT promptly sent the notice of
2430postponement to the bidders and later completed the other
2439necessary steps to move the bid deadline.
244630. A postponement notice can be sent to bidders in less
2457than ten minutes after the decision to postpone a bid is made.
2469All other steps required to move a bid deadline are typically
2480accomplished by DOT personnel in about an hour.
248831. DOT knows of no harm that would have come to the other
2501bidders had DOT agreed to move the bid deadline to allow Hinson
2513sufficient time to submit its online bid.
252032. At 9:22 a.m. on September 26, 2012, Daniel Hinson sent
2531an email to Colette Jackson in response to her email, stating
2542there was insufficient time for Hinson Electrical to prepare its
2552bid for the Project and that a protest would be filed if DOT
2565posted its intent to award the contract to one of the other
2577bidders.
257833. The letting of the project occurred as scheduled at
258810:30 a.m. on September 26, 2012. At approximately 4:00 p.m. on
2599October 24, 2012, DOT posted notice of its intent to award the
2611contract to ALS. This was the second posting date for the
2622September 26, 2012 letting date. Thereafter, Hinson Electrical
2630timely served its notice of protest, formal protest pleading,
2639and the required bond.
264334. The advertisement for the Project reads, in part,
"2652Bidders are hereby notified that all bids on any of the
2663following projects are likely to be rejected if the lowest
2673responsive bid received exceeds the engineer's estimate by more
2682than ten percent (10%)." DOT does reject all bids for being too
2694high in some cases. The bid submitted by ALS for the Project
2706exceeded the proposal budget estimate of $4,183,958 by 19.9
2717percent (ALS' winning bid was $5,016,501.73).
272535. The Contract Award Committee (Committee) is the DOT
2734body with discretion to reject all bids for a project. However,
2745Ms. Moore never informed the Committee of Hinson Electrical's
2754situation so that it could determine whether the Project should
2764be rebid. Even after posting notice of intent to award the
2775Project to ALS, DOT retained discretion to reject all bids, but
2786Ms. Moore was unaware of that discretion and never discussed the
2797matter with the Committee.
280136. Hinson Electrical credibly established that it would
2809have submitted a bid of $4,973,361.99 for the Project had DOT
2822provided the online bid document when Hinson Electrical first
2831requested it. Thus, Hinson Electrical would have been the low
2841bidder, and presumably awarded the contract.
284737. DOT had at least three opportunities to correct its
2857mistake and allow Hinson Electrical an opportunity to bid. DOT
2867could have (l) extended the bid deadline, as it has in many
2879other cases; (2) rejected all bids and rebid the Project, before
2890posting notice of intent to award the contract; or (3) rejected
2901all bids even after posting notice of intent.
290938. In their Prehearing Stipulation, the parties
2916stipulated to the following:
2920DOT has no policy statements, handbook
2926provisions, internal memoranda, guidelines,
2930or other documents regarding the following
2936subjects:
2937a. How a failure to timely transmit
2944bid documents in response to a prospective
2951bidder's request, whether due to a
2957transmission error or otherwise, should be
2963handled or what relief may be provided to
2971the bidder;
2973b. Acceptable grounds for extending a
2979bid submission deadline;
2982c. How an erroneous determination that
2988a prospective bidder for a project was not
2996qualified to bid should be handled, either
3003before or after the bid deadline has
3010expired;
3011d. Relief that can or should be
3018provided to a prospective bidder who was
3025denied the opportunity to bid for a project
3033due, at least in part, to some irregularity
3041in the bidding process;
3045e. Relief that can or should be
3052provided to a prospective bidder who was
3059denied the opportunity to bid for a project
3067due, at least in part, to some error made by
3077FDOT (including its computer system); and
3083f. How to handle a situation in which
3091all received bids exceed the budget for the
3099project by more than 10%.
3104(Prehearing Stipulation, pgs. 11-12)
3108CONCLUSIONS OF LAW
311139. DOAH has jurisdiction over the subject matter of this
3121proceeding and of the parties hereto pursuant to sections
3130120.569, 120.57(1) and 120.57(3), Florida Statutes.
313640. Hinson Electrical has standing to file this protest by
3146virtue of being a prospective bidder who was wrongfully excluded
3156from the bidding process. See Advocacy Ctr. For Pers. with
3166Disabilities, Inc. v. Dep't of Child. & Fam. Servs. , 721 So. 2d
3178753, 755 (Fla. 1st DCA 1998) (citing and quoting Westinghouse
3188Elec. Corp. v. Jacksonville Transp. Auth. , 491 So. 2d 1238, 1241
3199(Fla. 1st DCA 1986), and Fairbanks, Inc. v. Dep't of Transp. ,
3210635 So. 2d 58, 59 (Fla. 1st DCA 1994)). The evidence shows that
3223Hinson Electrical would have had the low bid and would likely
3234have been awarded the Project, so Hinson Electrical has the
3244requisite substantial interest in this matter. "Standing will
3252inhere in a person who at least has some potential stake in the
3265contract to be awarded." Id. Hinson Electrical satisfies this
3274test.
327541. Petitioner, as the party challenging the proposed
3283agency action, has the burden of proof in this proceeding and
3294must show that the agency's proposed action is contrary to the
3305agency's governing statutes, rules or policies, or the bid or
3315proposal specifications. A de novo hearing was conducted to
3324evaluate the action taken by the agency. § 120.57(3)(f), Fla.
3334Stat.; State Contracting and Engg Corp. v. Dept of Transp. ,
3344709 So. 2d 607 (Fla. 1st DCA 1998). The administrative law
3355judge may receive evidence, as with any hearing held pursuant to
3366section 120.57(1), but the purpose of the proceeding is to
3376evaluate the action taken by the agency based on the information
3387available to the agency at the time it took the action. Id.
339942. Agencies enjoy wide discretion when it comes to
3408soliciting and accepting proposals, and an agency's decision,
3416when based upon an honest exercise of such discretion, will not
3427be set aside even where it may appear erroneous or if reasonable
3439persons may disagree. Baxter's Asphalt and Concrete, Inc. v.
3448Dept of Transp. , 475 So. 2d 1284, 1287 (Fla. 1st DCA 1985);
3460Capeletti Brothers, Inc. v. State, Dept of Gen. Servs. , 432
3470So. 2d 1359, 1363 (Fla. 1st DCA 1983). Section 120.57(3)(f)
3480establishes the standard of proof as whether the proposed action
3490was clearly erroneous, contrary to competition, arbitrary or
3498capricious. 3 /
350143. A decision is considered to be clearly erroneous when,
3511although there is evidence to support it, after review of the
3522entire record the tribunal is left with the definite and firm
3533conviction that a mistake has been committed. United States v.
3543U.S. Gypsum Co. , 333 U.S. 354, 395 (1948). An agency action is
3555capricious if the agency takes the action without thought or
3565reason or irrationally. Agency action is arbitrary if is not
3575supported by facts or logic. See Agrico Chemical Co. v. State
3586Dept of Envtl. Reg. , 365 So. 2d 759, 763 (Fla. 1st DCA 1978).
3599An agency decision is contrary to competition if it unreasonably
3609interferes with the objectives of competitive bidding. See
3617Wester v. Belote , 103 Fla. 976, 138 So. 721, 723-24 (1931).
362844. By erroneously rejecting Hinson Electric's timely
3635request for the bid document, and then refusing its reasonable
3645request for a bid extension, DOT actions are clearly contrary to
3656competition.
3657The bid procedure was fashioned to
3663discourage discriminatory governmental
3666awards and to assure the procurement of the
3674best value in exchange for public funds.
3681When the procedure is not followed, those
3688objectives are not achieved.
3692Courtenay v. Dept of HRS , 581 So. 2d 621, 623 (Fla. 5th DCA
37051991). The purpose of the bidding process is settled in the
3716law:
3717[T]o protect the public against collusive
3723contracts; to secure fair competition upon
3729equal terms to all bidders; to remove not
3737only collusion but temptation for collusion
3743at public expense; to close all avenues to
3751favoritism and fraud in its various forms;
3758to secure the best values for the county at
3767the lowest possible expense; and to afford
3774an equal advantage to all desiring to do
3782business with the county, by affording an
3789opportunity for an exact comparison of bids.
3796Wester v. Belote
, 3799103 Fla. 976, 981, 138 So. 721, 723-24 (1931);
3808see also Harris v. Sch. Bd. of Duval Cnty. , 921 So. 2d
3820725 (Fla. 1st DCA 2006); Dept of Lottery v. GTech Corp. ,
3831816 So. 2d 648, 652 (Fla. 1st DCA 2001); Aurora Pump v. Goulds
3844Pumps, Inc. , 424 So. 2d 70, 75 (Fla. 1st DCA 1982); Harry
3856Pepper & Assocs., Inc. v. City of Cape Coral , 352 So. 2d
38681190, 1192 (Fla. 2d DCA 1977); Wood-Hopkins Contracting Co. v.
3878Roger J. Au & Son, Inc. , 354 So. 2d 446 (Fla. 1st DCA
38911978).
389245. Without question, bid procedures exist to ensure the
3901equal treatment of all potential bidders. When, as here, a
3911bidder who attended the pre-bid meeting and met all other
3921prerequisites was not provided with critical documentation that
3929the other bidders received, "the bidders were not treated
3938equally and fairly" and "the entire purpose of the competitive
3948bidding process [is] subverted." Opus South Corp. v. Bd. of
3958Regents , Case No. 93-2740BID (Fla. DOAH July 29, 1993; Fla. Bd.
3969of Regents Sept. 21, 1993). And when an agency's mistake denies
3980a contractor the opportunity to compete for a contract award,
3990relief should be provided to the contractor. In Asphalt Pavers,
4000Inc. v. Fla. Dep't of Transp. , 602 So. 2d 558, 562 (Fla. 1st DCA
40141992), the hearing officer held it was clearly arbitrary to
4024reject a bid for failure to include a form that the agency
4036itself lost, and that result was affirmed on appeal.
404546. There is no question that Hinson Electrical was
4054treated differently than the other bidders for the Project.
4063Hinson Electrical was the only bidder that received a
4072Prequalification Failure Notice with the erroneous statement
4079that it had failed to attend the mandatory pre-bid meeting.
4089Hinson Electrical is also the only bidder that was not able to
4101download the bid document promptly upon request. This unequal
4110treatment of bidders is contrary to competition for the Project.
412047. DOT responds that Hinson Electrical should have
4128identified DOT's error sooner, but there is no dispute that
4138Hinson Electrical timely satisfied every prerequisite for DOT to
4147deliver the requested bid package. Nor is there any dispute
4157that DOT (in its Prequalification Failure Notice) committed to
4166follow up "as soon as possible" to get the bid document to
4178Hinson Electrical. Bidders are entitled to rely upon the DOT to
4189timely provide bid documents in accordance with the DOT's
4198procedures. See Bell Atlantic Bus. Sys. Servs., Inc. v. Fla.
4208Dep't of Labor & Emp. Sec. , 677 So. 2d 989, 991 (Fla. 1st DCA
42221996) (holding that bidders were entitled to rely upon the
4232Department's commitment to provide a notice of bid posting by
4242facsimile and were not required to make telephone calls or
4252personal visits to obtain the notice the Department was supposed
4262to provide by facsimile). Hinson Electrical took appropriate
4270action as soon as it became aware of DOT's error.
428048. DOT also argues that most contractors request bid
4289documents either before or shortly after the pre-bid meeting.
4298However, DOT candidly admits this is not required and that it
4309was Hinson Electrical's prerogative to order the bid documents
4318during the blackout period provided by 337.168(2), which statute
4327is intended to foster competition. Any actions or procedures of
4337the DOT that impede the protections afforded by that statute are
4348improper. Capeletti Bros., Inc. v. Dep't of Transp. , 499 So. 2d
4359855, 858 (Fla. 1st DCA 1986) ("The exemptions in section 337.168
4371were enacted after the Sunshine Law and constitute the later,
4381more specific expression of legislative will and must,
4389therefore, be given effect.").
439449. The absence of regulations, policies, or even
4402guidelines to govern the decision whether to postpone a bid
4412deadline or reject all bids under circumstances like this, is
4422problematic. Important decisions should not be made "on the
4431personal whim of a bureaucrat." See SAS Fountains at Pershing
4441Park. Ltd. v. Fla. Hous. Fin. Corp. , Case No. 10-8219 (Fla. DOAH
4453Sept. 30, 2010; Fla. Hous. Fin. Corp. June 24, 2011). DOT is
4465entrusted with millions of dollars in taxpayer funding. The
4474public trust demands appropriate policies, procedures, and
4481decision-making to ensure procedural and substantive fairness in
4489the bid procurement process and the use of this funding.
449950. DOT has discretion to extend bid deadlines, and in
4509fact does so regularly for various reasons. Given the facts of
4520this case, DOT should have provided some reasonable
4528accommodation to a bidder who was denied sufficient opportunity
4537to bid for the project due to DOT's error or an irregularity in
4550the bid procurement process that affected the bidder. DOT has
4560done so in many other cases, and should have done so here.
457251. On the facts found herein, DOT's unequal treatment of
4582Hinson Electrical was contrary to competition. Moreover, on
4590these facts, DOT's refusal to provide any accommodation for
4599Hinson Electrical, once DOT's mistake was brought to light prior
4609to the bid deadline, in the absence of standards and policies,
4620and without discussion with upper-management at DOT, was both
4629arbitrary and capricious.
463252. Petitioner urges a recommendation from the undersigned
4640that DOT enter a Final Order directing that all bids for the
4652Project be rejected and that the Project be rebid. However,
4662administrative law judges are without the authority to direct
4671how an agency must respond once a finding is made that the
4683procurement process violated applicable law. Dept of Transp.
4691v. Groves-Watkins Constructors , 530 So. 2d 912 (Fla. 1988);
4700see also , Moore v. State, Dept of HRS , 596 So. 2d 759 (Fla. 1st
4714DCA 1992); Courtenay v. Dept of HRS , 581 So. 621 (Fla. 5th DCA
47271991).
472853. Under the facts of this case, DOT's decision not to
4739extend the bid deadline for the Project was clearly erroneous,
4749contrary to competition, arbitrary and capricious, in violation
4757of section 120.57(3)(f).
4760RECOMMENDATION
4761Upon consideration of the facts found and conclusions of
4770law reached, it is
4774RECOMMENDED: That a final order be entered by the Department of
4785Transportation that rescinds the Notice of Intent to award
4794Contract T2442 to American Lighting & Signalization, Inc.
4802DONE AND ENTERED this 21st day of June, 2013, in
4812Tallahassee, Leon County, Florida.
4816S
4817W. DAVID WATKINS
4820Administrative Law Judge
4823Division of Administrative Hearings
4827The DeSoto Building
48301230 Apalachee Parkway
4833Tallahassee, Florida 32399-3060
4836(850) 488-9675
4838Fax Filing (850) 921-6847
4842www.doah.state.fl.us
4843Filed with the Clerk of the
4849Division of Administrative Hearings
4853this 21st day of June, 2013.
4859ENDNOTES
48601/ The parties are in agreement as to the timing and sequence of
4873virtually all of the relevant events. See Prehearing
4881Stipulation, pgs. 10-12.
48842/ other bidders for the Project also received a All
4894Prequalification Failure Notice stating that the bid documents
4902could not be issued at the time of request because attendance at
4914the pre-bid conference was a prerequisite. However, since all
4923other bidders requested the bid documents prior to the date of
4934the pre-bid conference the Prequalification Failure Notices sent
4942to them was appropriate, whereas the Prequalification Failure
4950Notice sent to Hinson Electrical was not.
49573/ Section 120.57(3)(f) provides in relevant part:
4964Unless otherwise provided by statute, the
4970burden of proof shall rest with the party
4978protesting the proposed agency action. In a
4985competitive-procurement protest, other than
4989a rejection of all bids, proposals, or
4996replies, the administrative law judge shall
5002conduct a de novo proceeding to determine
5009whether the agencys proposed action is
5015contrary to the agencys governing statutes,
5021the agencys rules or policies, or the
5028solicitation specifications. The standard
5032of proof for such proceedings shall be
5039whether the proposed agency action was
5045clearly erroneous, contrary to competition,
5050arbitrary, or capricious. In any bid-
5056protest proceeding contesting an intended
5061agency action to reject all bids, proposals,
5068or replies, the standard of review by an
5076administrative law judge shall be whether
5082the agencys intended action is illegal,
5088arbitrary, dishonest, or fraudulent.
5092:
5093C. Denise Johnson, Esquire COPIES FURNISHED
5099Department of Transportation
5102Haydon Burns Building, Mail Station 58
5108605 Suwannee Street
5111Tallahassee, Florida 32399
5114E. Lanny Russell, Esquire
5118Smith Hulsey and Busey
5122Suite 1800
5124225 Water Street
5127Jacksonville, Florida 32202
5130Trish Parsons, Clerk of Agency Proceedings
5136Department of Transportation
5139Haydon Burns Building, Mail Station 58
5145605 Suwannee Street
5148T allahassee, Florida 32399
5152Gerald B. Curington, General Counsel
5157Department of Transportation
5160Haydon Burns Building, Mail Station 58
5166605 Suwannee Street
5169Tallahassee, Florida 32399
5172Ananth Prasad, Secretary
5175Department of Transportation
5178Haydon Burns Building, Mail Station 57
5184605 Suwannee Street
5187Tallahassee, Florida 32399
5190NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5196All parties have the right to submit written exceptions within
520610 days from the date of this Recommended Order. Any exceptions
5217to this Recommended Order should be filed with the agency that
5228will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 07/19/2013
- Proceedings: Notice Regarding Petitioner`s Motion for Recovery of Costs and Bond.
- PDF:
- Date: 07/11/2013
- Proceedings: Petitioner's Response to Respondent's Exceptions to Recommended Order filed.
- PDF:
- Date: 06/21/2013
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- Date: 05/21/2013
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 05/01/2013
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 04/30/2013
- Proceedings: Joint Pre-Hearing Stipulation (exhibits not available for viewing) filed.
- PDF:
- Date: 04/03/2013
- Proceedings: Respondent's Notice of Serving Answers to Petitioner's First Set of Interrogatories filed.
- PDF:
- Date: 04/03/2013
- Proceedings: Order Re-scheduling Hearing (hearing set for May 1, 2013; 9:00 a.m.; Jacksonville, FL).
- PDF:
- Date: 03/22/2013
- Proceedings: Order Granting Continuance (parties to advise status by March 29, 2013).
- PDF:
- Date: 02/27/2013
- Proceedings: Amended Notice of Hearing (hearing set for March 28, 2013; 9:00 a.m.; Jacksonville, FL; amended as to Final Hearing Location).
- PDF:
- Date: 02/26/2013
- Proceedings: Notice of Hearing (hearing set for March 28, 2013; 9:00 a.m.; Jacksonville, FL).
- Date: 02/25/2013
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
Case Information
- Judge:
- W. DAVID WATKINS
- Date Filed:
- 02/19/2013
- Date Assignment:
- 03/26/2013
- Last Docket Entry:
- 07/19/2013
- Location:
- Jacksonville, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- BID
Counsels
-
Jonathan R Huffman, Esquire
Address of Record -
C. Denise Johnson, Esquire
Address of Record -
E. Lanny Russell, Esquire
Address of Record -
C. Denise Johnson, Assistant General Counsel
Address of Record