13-000775
Ed And Kay Rankin vs.
Mahogany Mill Owners Association, Inc., And Department Of Environmental Protection
Status: Closed
Recommended Order on Tuesday, June 11, 2013.
Recommended Order on Tuesday, June 11, 2013.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8ROBERT V. KRIEGEL ,
11Petitioner ,
12vs. Case No. 13 - 0686
18MAHOGANY MILL OWNERS
21ASSOCIATION, INC., AND
24DEPARTMENT OF ENVIRONMENTAL
27PROTECTION ,
28Respondents .
30_______________________________ /
32BRYAN BAARS,
34Pe titioner,
36vs. Case No. 13 - 0687
42MAHOGANY MILL OWNERS
45ASSOCIATION, INC. , AND
48DEPARTMENT OF ENVIRONMENTAL
51PROTECTION,
52Respondents.
53_______________________________ /
55MIKE BEARD,
57Petitioner,
58vs. Case No. 13 - 0774
64MAHOGANY MILL OWNERS
67ASSOCIATION, INC. , AND
70DEPARTMENT OF ENVIRONME NTAL
74PROTECTION,
75Respondents.
76_______________________________ /
78ED AND KAY RANKIN,
82Petitioner,
83vs. Case No. 13 - 0775
89MAHOGANY MILL OWNERS
92ASSOCIATION, INC. , AND
95DEPARTMENT OF ENVIRONMENTAL
98PROTECTION,
99Respondents.
100/
101RECOMMENDED ORDER
103These consolidated cases were heard by David M. Maloney,
112Administrative Law Judge with the Division of Administrative
120Hear ings ("DOAH") , on April 3, 2013 , in Pensacola, Florida.
132APPEARANCES
133For Petitioner s : Robert Kriegel , pro se
141Apartment 14
1431280 Mahogany Mill Road
147Pensacola, Florida 32507
150Bryan Baars , pro se
1541516 East Mallory Street
158Pensacola, Florida 32503
161Ed Rankin , pro se
165Mahogany Mill Homeowners Association
1691280 Mahogany Mill Road, Unit 7
175Pensacola, Florida 32507
178For Mahogany Mill Owners Association, Inc. :
185William J. Dunaway, Esquire
189Clark, Partington, Hart, Larry,
193Bond an d Stackhouse
197Post Office Box 13010
201Pensacola, Florida 32591
204For Department o f Environmental Protection :
211Brynna J. Ross, Esquire
215Department of Environmental Prote ction
220Mail Station 35
2233900 Commonwealth Boulevard
226Tallahassee, Florida 32399 - 3000
231STATEMENT OF THE ISSUES
235Whether Petitioners Kay Rankin and Mike Beard have standing?
244Whether the proj ect by Mahogany Mill Owners As sociation,
254Inc. ("Mahogany Mill ") , to remove two existing finger piers and
266construct three new finger piers and two boat lifts (the
"276Project") is exempt from the need to obtain an Environmental
287Resource Permit ("ERP") from the Department of Environmental
297Protection (the "Department") ?
301Whether the Project qualifies for authorization from the
309Board of Trustees of the Internal Improvement Fund (the "Board of
320Trustees") to use sovereign submerged lands?
327PRELIMINARY STATEMENT
329On October 5, 2012, Mahogany Mill, through a firm with
339which it had contracted for environmental consulting services,
347Wetland Sciences, Inc. ("Wetland Sciences") , submitted an
356application to the Department.
360The application sought to have the Project decl ared exempt
370from permitting and to obtain an authorization to use sovereign
380lands held in trust by the Board of Trustees. On October 24,
3922012, the Department issued a letter to Mahogany Mill, LLC,
402c/o Robert Montgomery, an owner of one of the bays of the
414original group building used by Mahogany Mill . The letter
424announces the Department's determination that the Project is
432exempt from regulatory review. The letter also consents to the
442construction and use of the Project on submerged lands owned by
453the stat e on behalf of the Board of Trustees. The letter,
465therefore, is both an exemption l etter that constitutes action by
476the Department and a letter of consent that constitutes
485proprietary action by the State of Florida.
492On February 14, 2013, a Notice of Dete rmination of
502Qualification for Exemption was published in the Escambia Sun -
512Press to provide notice to persons whose substantial interests
521may be affected by the Department's action and an opportunity to
532file a petition for an administrative hearing. On th e same day,
544the Department received a letter from Robert V. Kriegel, mailed
554February 11, 2013, in which Mr. Kriegel identified himself as
"564Petitioner" and requested "that the department conclude that
572respondent is not entitled to the use of the exemption f or the
585existing construction and proposed usage (24' power boat ) and
595that these structures be removed and any usage of these
605structures ceased." The Department treated the letter as a
614petition for hearing and referred the matter to DOAH in a
"625Request for Assignment of Administrative Law Judge and Notice of
635Preservation of Rights." The r equest was filed at DOAH on
646February 20, 2013 , and assigned Case No. 13 - 0686.
656By February 28, 2013, three other letters followed that were
666similar to Mr. Kriegel's: one f rom Bryan Baars, a second from Ed
679and Kay Rankin, and a third from Mike Beard. All three were
691treated as requests for hearing by the Department and referred to
702DOAH. Mr. Baars ' request was assigned Case No. 13 - 0687;
714Mr. Beard's request was assigned Case No. 13 - 0774 ; and Ed and Kay
728Rankins' request was assigned Case No. 13 - 0775. The three cases
740were consolidated with Case No. 13 - 0686.
748On March 15, 2013, Mahogany Mill, LLC, filed a motion for
759Mahogany Mill Owners Association, Inc., to be substituted as th e
770Respondent in the case. No objection was filed , and the motion
781was granted at the onset of the hearing which took place on
793April 3, 2013.
796At the commencement of the hearing, Carol Simpson, a non -
807attorney, made an ore tenus request for authori zation to
817represent Petitioner Beard at the hearing. The Department
825objected to Ms. Simpson's appearance as a qualified
833representative. The objection was sustained.
838Mahogany Mill presented the testimony of four witnesses:
846Robert Montgomery; Jason Taylor, an envi ronmental specialist with
855Wetland Sciences; Captain Benjamin Tyrone Cranford, accepted as
863an expert in marine navigation; and James W. Veal, an architect
874who owns property adjacent to the Project. Mahogany Mill offered
88422 exhibits, marked as Mahogany Mill Exhibits 1 - 21 and 5A. All
897were admitted.
899The Department presented the testimony of three witnesses:
907Susan Radford, an Environmental Specialist III with the
915Department; Randy Webb, accepted as an expert in marine
924navigation; and on rebuttal, Mike Lunn, a fact witness. The
934Department offered three exhibits, marked as Department
941Exhibits 1, 3, and 6. All were admitted.
949Petitioner Kriegel testified as an expert on his own behalf
959and was accepted as an expert in environmental permitting,
968resource permitti ng, sailboat handling and navigation, and
976powerboat handling and navigation. He also presented the
984testimony of Carol Simpson who was accepted as an expert in
995sailboat handling and navigation. Petitioner Kriegel offer e d one
1005exhibit, marked as Kr ie gel Exh ibit 1. It was admitted into
1018evidence. Petitioner Baars testified on his own behalf as an
1028expert in "handling of sailboats and navigation . " Hr'g Tr. 196 ,
1039Apr. 3, 2013. Petitioner Ed Rankin testified on behalf of
1049himself and Kay Rankin.
1053The T ranscri pt of the hearing was filed with DOAH on
1065April 18, 2013. The parties were given ten days after the filing
1077of the transcript to file proposed recommended orders. On
1086April 24, 2013, Mr. Baars filed "Petitioner's Proposed
1094Recommended Order , " which was signe d by M e ssrs. Kriegel, Baars ,
1106and Rankin. The Department and Mahogany Mill filed separate
1115proposed orders on Monday, April 29, 2013. All proposed
1124recommended orders are deemed filed in a timely manner and have
1135been consid ered in the preparation of this R e commended O rder .
1149FINDINGS OF FACT
1152Mahogany Mill Pond and the Channel
11581. Located in Pensacola, Florida, Mahogany Mill Pond is
1167connected by a channel (the "Channel") to Chico Bayou. The bayou
1179provides passage to Pensacola Bay and the bay, in turn, is
1190adja cent to the Gulf of Mexico.
11972. Prior to the dredging of the Channel in the 1950s to
1209connect the pond and the bayou, the pond was used to store logs
1222as part of a logging operation. After the dredging activity, the
1233storage of logs in the pond ceased. The pond began to serve as a
1247hold for sailboats and over the decades since, the Channel has
1258been used by sailboats and powerboat s alike to make their way to
1271the bayou and onward to the bay and the open waters of the Gulf.
12853. Currently, Mahogany Mill Pond is "one of the few places
1296left in Pensacola where you can have hurricane hold for deep
1307water sailboats." Hr'g Tr. 231. "Hurricane holds" are safe
1316places to moor a vessel in times of tropical storms and where, in
1329the words of Petitioner Rankin, "you can get your sailboat out of
1341the weather." Id.
13444. The petitioners in these four consolidated cases all own
1354deep draft sailboats which they moor in Mahogany Mill Pond.
13645. The Channel is bordered to the south by a spit of land
1377that juts into the bayou. The spit is approximately 600 feet
1388long , and its vegetation line (estimated to be the mean high
1399water line by an environmental consulting business) is roughly
140860 feet from the Project. The tip of the spit is opposed in the
1422bayou by the Palm Harbor Marina. T he marina is a busy one with
1436nearly every one of its slips occupied , as shown by photographic
1447evidence. The marina is about the same distance from the spit as
1459the Project is from the spit. There are shoals in the area and
1472they exist between the spit and the Project.
14806. Whether an excursion originates in the pond or the
1490Channel, boaters seeking egress to the bayou, the bay and t he
1502Gulf must make their way through th e Channel alongside the spit,
1514and around its tip in the vicinity of the marina, an area th at
1528includes shoals. Likewise from the bay or bayou, any boat headed
1539for the Channel or the pond must make its way through the narrow
1552area of the marina across from the spit, around the spit , and
1564through the shoals in and near the Channel so as to not run
1577aground.
15787 . Despite a "quiescent environment with a little bit of
1589intertidal flow" ( Hr'g T r. 149), the Channel requires dredging
"1600probably every 10 years , " id. , to maintain its navigability. It
1610has been dredged "a couple of times in the . . . 20 years , " id. ,
1625Petitioner Kriegel has lived in the area.
16328 . The last time the Channel was dredged was six or seven
1645years ago. To the best of Petitioner Rankin's memory, the cost
1656was about $16,000. Dredging costs are borne by the members of
1668the local homeowner s association.
16739 . The Channel's shallowness in some spots is a navigation
1684concern for sailboats and contributes to the Petitioners'
1692assessment of the Channel as "narrow" and "constricted . "
170110 . Despite shallowness and the presence of the shoals , as
1712well as the tight configuration created by the spit, the
1722Project's presence in the C hannel does not create a navigation
1733hazard for powerboat s that have two engines. This is due to the
1746ability of powerboat s to maintain position during a maneuver. As
1757explained by Petitioner Kriegel, "[A]s a result of [having two
1767engines], you can push one side of the boat forward and pull the
1780other side of the boat backwards and pivot the boat without
1791making any headway." Hr'g Tr. 152. A powerboat 's ability to
1802maintain positi on aids ma neuver ability, particularly in
1811constricted waterways. Sailboats, on the other hand, cannot
1819maintain position while they turn. In order for a sailboat to
1830execute a turn while under sail, it must be moving through the
1842water largely because their keels create lateral resistance.
1850When not under sail, sailboats are typically not able to maintain
1861position while turning because they are usually equipped with
1870only one engine.
18731 1 . A structure in a constricted waterway may be an obvious
1886navigational ha zard to any boat or it may be a hazard to some
1900boats but not others. More to the point, a structure that
1911extends into a waterway can be a navigational hazard to a
1922sailboat because of the sailboat's inability to maintain position
1931during a turn while at the same time it is not a hazard for a
1946powerboat that enjoys superior maneuverability based on its
1954capability to hold position during a pivot.
1961The Parties
19631 2 . Petitioners Kriegel, Baars, Ed and Kay Rankin, and
1974Beard are individual citizens who reside i n Escambia County.
1984They all own property in the vicinity of Mahogany Mill Pond , and
1996they all moor their deep draft sailboats in the hurricane hold
2007that is Mahogany Mill Pond. Each has extensive experience
2016navigating the pond, the C hannel, Chico Bayou , Pe nsacola Bay , and
2028the open waters of the Gulf of Mexico.
20361 3 . Mahogany Mill is a Florida homeowners association. It
2047has been substituted in this proceeding as a respondent in the
2058place of Mahogany Mill, LLC, the entity on whose behalf the
2069applica tion for the Project was submitted .
20771 4 . The Department is the agency of the State of Florida
2090that administers the provisions of section 403.813(1)(b) , Florida
2098Statutes (2012), 1/ and Florida Administrative Code R ule 62 -
2109346.051(5)(a) (which relates to exemptions fr om environmental
2117resource permitting in Northwest Florida) and, on behalf of the
2127Board of Trustees of the Internal Improvement Fund, if a p roject
2139is shown to qualify for an exemption from permitting, to
2149authorize the use of sovereign submerged lands pursua nt to
2159Florida Administrative Code R ule 18 - 21.005(1)(b), including
2168compliance with rule 18 - 21.004(7)(g).
2174The Application and the Pre - construction Mooring Pilings
21831 5 . The Application for the Project was submitted under
2194cover of a letter from Wetland Scie nces with a date of October 5,
22082012. The letter lists the applicant as "Mahogany Mill LLC,
2218c/o Robert Montgomery . " In the body of the letter, it states
2230that the Application was submitted "on behalf of Mr. Robert
2240Montgomery . " Mahogany Mill Ex. 1.
22461 6 . The October 5, 2012 , l etter is signed by Jason Taylor.
2260Wetland Sciences employs Mr. Taylor as an e nvironmental
2269s pecialist. Mr. Taylor holds a four - year degree from the
2281Univ ersity of West Florida and has been employed by Wetland
2292Sciences since 2004. Duri ng that time, he has been engaged in
2304marine permitting and has participated in the permitting of
2313several hundred projects.
23161 7 . In conducting the permitting of the Project, Mr. Taylor
2328interacted with both DEP personnel and personnel from the c ounty.
2339In t he discussions, Mr. Taylor was careful to address compliance
2350with any regulations related to the Project's water - ward
2360extension. His main concern was with the County Code because it
2371is slightly more stringent than DEP regulations. He informed
2380Mr. Montgom ery that a variance from the c ounty might be necessary
2393but that proved not to be the case. "[W]e could actually
2404construct [the Project] . . . as long as it stayed within the
2417same footprint as what was currently there, which extended . . .
242924 feet . . . in to the water body." Hr'g Tr. 89 - 90.
24441 8 . The "Plan View of Existing Site Conditions" drawn by
2456Mr. Taylor and submitted as an attachment to the Application ( see
2468page 2 of 6 attached to Mahogany Mill Ex. 1) shows that at the
2482time of the submission the Proj ect site encompassed two existing
2493mooring piles (the "Preconstruction Mooring Pilings") and two
2502finger piers. The Preconstruction Mooring Pilings served as bow
2511or stern lines for smaller vessels that would dock alongside the
2522two finger piers.
25251 9 . The fi nger piers extended approximately 12 feet
2536offshore. In contrast, the Preconstru c tion Mooring Pilings were
2546at a point that extended twice as far into the Channel , i.e.,
255824.0 feet offshore. In Mr. Taylor's opinion, the water - ward
2569extent of the location of the Preconstruction Mooring Pilings
2578justified a 24 - foot extension of the Project into the waterway.
259020 . Some of the exhibits attached to the Application were
2601scaled from an aerial. Others were supported by measurements
2610taken by Mr. Taylor in the field. The location of the
2621Preconstruction Mooring Pilings 24 feet offshore were among the
2630locations supported by field measurements taken by Mr. Taylor at
2640the site of the Project.
2645The Project
26472 1 . The Project is shown in the application to consist of
2660two 24 - foot by three - foot finger piers ( the "Outside Piers" ) and
2676a third finger pier between the other two (the "Middle Pier").
2688Like the Outside Piers, the Middle Pier extends 24 feet into the
2700Channel , but it is six feet wide (twice as wide as the Outside
2713Piers ). Two uncovered boat lifts, 12 feet wide each, are also
2725part of the Project. The points of the boat lifts that extend
2737the farthest from shore are within the utmost extension of the
2748piers, that is, within 24 feet from the shore (the identical
2759distance fr om shore as the Preconstruction Mooring Pilings). As
2769described in the application (the "information submitted to the
2778Department"), there is no part of the Project that extends beyond
279024 feet from the shore , i.e., where the Preconstruction Mooring
2800Pilings stood at the time of the application's submission.
28092 2 . The width of the Project (from the corners of the Outer
2823Piers ) alongside the Channel is 36 feet. The distances to an
"2835APPROXIMATE CENTER THREAD OF CHANNEL" ( see the estimation in the
"2846Close - Up Plan View of Proposed Activity, " p age 5 of 6 attached
2860to the Application, DEP Ex. 2) are 20.5 feet from one Outside
2872Pier, 18.1 feet from the Middle Pier, and 16.0 feet from the
2884other Outside Pier.
28872 3 . The total area of submerged lands preempted by the
2899Proj ect is 288.0 square feet. At the shore (where there is a
2912seawall), the Project lies within 49.6 linear feet of shoreline
2922owned by the applicant.
29262 4 . The Project is on the side of the Channel across from
2940the spit . The Project's side would be starboard o f a sailboat
2953returning to the pond from the bayou. It is also the side for a
2967boat headed toward the pond that a vessel would be obligated to
2979keep under boating "rules of the road" to avoid collisions or
2990scrapes with a boat coming from the direction of the pond headed
3002out of the Channel.
3006The Veal Dock
30092 5 . Next to the Project is a dock and boat lift owned by
3024James Warren Veal (the "Veal Dock").
30312 6 . Mr. Veal has a 21 - foot Cobia powerboat that he keeps on
3047a boat lift supported by the Veal Dock. His boat, equipped with
3059an outboard motor and moored in the boat lift of the Veal Dock,
3072was shown in Mahogany Mill Ex h ibit 21 "to be sticking out a few
3087inches more , " Hr'g T r. 110, than the stern and engine of
3099Mr. Montgomery's boat while docked at the Project. At th e time
3111Mr. Montgomery's boat was photographed to produce Mahogany Mill
3120Ex hibit 21 , it's stern extended "[r]oughly, ball park, a foot and
3132a half," Hr'g T r. 109 , past the piling . T he boat's engine
3146extended another foot and a half toward the center thread of the
3158Channel.
31592 7 . When docked at the Veal Dock, Mr. Veal's boat
3171(including the outboard motor off its stern) at its water - ward -
3184most extension is referred to as a "limiting point " ( see Hr'g
3196T r. 191 ) , by the Petitioners. Extending farther out into the
3208Cha nnel than any other structure, boat or engine (inc luding the
3220Project) on the Project's side of the Channel, the limiting point
3231created by a boat in the Veal Dock is what a sailboat swinging
3244around the spit into the Channel must avoid in order to enjoy
3256safe passage in the Channel.
3261The Letter of Exemption
3265and State - owned Submerged Land Authorization
32722 8 . The Letter of Exemption locates the Project both by
3284Parcel ID Number , as shown in local government records , and at
3295the street address of 1263 Mahogany Mill in Pensacola, Florida.
3305Its description of the Project is consistent with the description
3315in the Application. See DEP Ex. 1.
33222 9 . The Letter of Exemption verifies that the Project is
3334exempt from regulatory review:
3338Based on the information submitted, the
3344Department has determined that the
3349construction of the boatlifts and finger
3355piers, [ sic ] is exempt, [ sic ] under paragraph
336662 - 346.0512(5)(a), F.A.C., from the need to
3374obtain a regulatory permit.
3378Therefore, the Department grants an exemption
3384for the propose d activity under paragraph 62 -
3393346.051(5)(a), F.A.C., and Section
3397403.813(1)(b), F.S.
3399Id.
340030 . The Department's Letter of Exemption also authorize s
3410the use of state - owned submerged lands for the Project by virtue
3423of the Department's status as staff to t he Board of Trustees:
3435The Department has reviewed the activity
3441. . . and has determined that the activity
3450qualifies for a Letter of Consent under rule
345818 - 21.005(1)9(c)2., F.A.C.[,] and section
3465253.77 of the Florida Statutes to construct
3472and use the activit y on the specified
3480sovereign submerged lands, as long as the
3487work performed is located within the
3493boundaries as described herein and is
3499consistent with [certain] terms and
3504conditions . . . .
3509Id. , p age 2 of 5 (the letter of consent incorporated in the
3522Lett er of Exemption).
35263 1 . The Letter of Exemption (with the letter of consent
3538incorporated) was issued on October 24, 2012.
3545Statutes and Rules
3548a. Regulatory Exemption
35513 2 . Section 403.813(1) provides, inter alia , that a permit
3562is not required for activitie s associated with "[t]he
3571installation . . . of private docks, piers and recreational
3581docking facilities . . . [ provided they] . . . [s]hall not impede
3595the flow of water or create a navigational hazard ."
3605§ 403.813(1)(b)3., Fla. Stat. (emphasis added).
36113 3 . The statue is implemented by rule 62 - 346.051. Among
3624the activities listed in the rule that do not require an ERP are
"3637the installation . . . of private docks, piers and recreational
3648docking facilities . . . in accordance with Section
3657403.813(1)(b), F.S. , [and its requirement that they not impede
3666the flow of water or create a navigational hazard]." Fla. Admin.
3677Code R. 62 - 346.051(5).
3682b. State - owned Submerged Lands Authorization
36893 4 . Section 253.77 , Florida Statutes, prohibits a person
3699from the use of so vereign or other lands of the state until the
3713person has the required the form of consent authorizing the
3723proposed use.
37253 5 . Rule 18 - 21.005 implements section 253.77. The form of
3738authorization required for the Project is a "Letter of Consent . "
3749See Fla. Admin. Code R . 18 - 21.005(1)(c)4. In addition, rule 18 -
376321.004(7) imposes general conditions for authorizations including
3770obtaining the necessary letters of consent. Among the other
3779conditions are that " [ s]tructures or activities shall not create
3789a navigat ional hazard." Fla. Admin. Code R. 18 - 21.004(7)(g).
3800Good Faith Efforts at Compliance
38053 6 . Mr. Montgomery and Mahogany Mill made deliberate and
3816careful effort to comply with the applicable statutes and rules
3826prior to the issuance of the Letter of Exempt ion. They hired a
3839consulting firm with appropriate expertise in the permitting of
3848docks. Their consultant worked with the c ounty and the
3858Department.
38593 7 . Based on the information submitted with the application
3870and the Department's preliminary review, it is no surprise that
3880the Department found the Project qualified for a Letter of
3890Exemption under the statutes and rules that provided an exemption
3900from regulatory review and that authorized the use of state - owned
3912lands. This is especially true given the ca re taken by
3923Mr. Montgomery and his environmental consultant in seeking the
3932exemption and in light of the Project's extension into the
3942Channel at a point no more than the Preconstruction Mooring
3952Pilings , i.e., 24.0 feet .
3957Installation
39583 8 . Without delay, Mr . Montgomery "contracted with a marine
3970contractor to install the improvements [authorized by the Letter
3979of Exemption]." Hr'g Tr. 69.
39843 9 . The Project was constructed and its installation was
3995completed in December 2012.
399940 . Mr. Montgomery and Mahogany M ill heard no objection
4010from any party while the Project was under construction. There
4020were no objections voiced in the month or so afterward.
40304 1 . The first objection was made known to Mahogany Mill
4042when Mr. Kriegel visited Mr. Montgomery in mid - February 2013.
4053The Challenges
40554 2 . Mr. Kriegel was out of town when the Project was
4068installed. He did not see the Project until mid - to - late February
4082aboard his sailboat when he "had great difficulty in getting [the
4093boat ] back in [his] slip [in Mahogany Mill Pond ]." Hr'g Tr. 169.
41074 3 . Following his experience navigating the Channel in
4117February 2013 , Mr. Kriegel met with Mr. Montgomery . From
4127Mr. Kriegel's perspective, the meeting was to no avail. The four
4138petitions challenging the Letter of Exemption and the le tter of
4149consent were filed shortly thereafter.
4154The Hearing
4156a. Mahogany Mill's Prima Facie Case
41624 4 . As the applicant for the exemption and the consent to
4175use state - owned submerged lands, Mahogany Mill provided evidence
4185that the Project is not a navigatio nal hazard to powerboat s. The
4198evidence included a video of Mr. Montgomery on board a 38 - foot
4211powerboat ( see Hr'g T r. 44) smoothly navigating its way from the
4224bayou around the s pit, into the Channel and to the Project. The
4237powerboat was piloted by Captain Ben Cranford, who has 12 years
4248of experience navigating vessels through the area , including into
4257Mahogany Mill Pond from the Channel. When asked at hearing about
4268navigating the Channel while being videotaped, Captain Cranford
4276replied, "I'm not having any [difficulty], at all." Hr'g Tr. 46.
42874 5 . After the presentation by the Applicant of a prima
4299facie case of compliance and immediately following the supportive
4308case of the Department, Petitioners presented their cases.
4316Petitioners' Cases
43184 6 . The evidenc e presented by Petitioners established that
4329sailboats have far less maneuverability than powerboat s as a
4339result of a number of factors . I nability to maintain position
4351during a turn is one of them. Sailboats may be less maneuverable
4363than powerboat s becaus e of hull and keel design as well, even
4376when equipped with an outboard motor which typically has a single
4387propeller. Sailboat maneuverability limitations may be
4393exacerbated, moreover, by wind and other conditions, particularly
4401in the summer when the preva iling direction of the winds tend to
4414push off a sailboat.
44184 7 . Mr. Kriegel related difficulty t he three to four times
4431since the construction of the Project that he has navigated a
4442return to the pond in his sailboat. On those occasions, he
4453brought his bo at in under "better than ideal conditions" ( Hr'g
4465T r. 171 ) , due in part to facilitation of the sailboat's turns by
4479a north breeze, the wind that typically prevails in winter time.
4490On one day, he brought the boat in twice on a relatively high
4503tide, another favorable condition. He "had to make two efforts
4513to do it because [he] ran aground . . . the first time. And the
4528second time [he] almost hit the structure." Id.
45364 8 . Mr. Baars owns a deep draft sailboat that is "45'3",
4549which includes . . . a Bowsprit." Hr'g Tr. 197. A bowsprit is a
4563spar that extends forward from a vessel's prow to which the stays
4575of the foremast are fastened.
45804 9 . As of the date of the hearing, Mr. Baars had not
4594attempted egress or ingress since the Project was installed. But
4604he su mmed up his worry about the Project when Mr. Kr ie gel asked
4619him on cross examination whether he thought he could safely
4629navigate around the structure, "I'm concerned, other than trying
4638to test it, I would not know. I mean, as I look down from my
4653dock . . . it doesn't look too good." Hr'g Tr. 213.
466550 . Like Mr. Kriegel, Mr. Baars has never collided with
4676structures in the Channel but "came very close to the previous
4687structures . . . [and safety] was always a concern when [he] came
4700around the spit." Hr'g Tr . 221. Mr. Baars sailboat has also run
4713aground in the Channel because of prevailing conditions that made
4723maneuvering difficult .
47265 1 . In his testimony, Mr. Rankin recollected that when the
4738seawall was installed by a previous owner in 2001, the
4748application showed eight pilings, all of which were "12 - foot
4759out." Hr'g Tr. 226. He has "bounced off and shoved of f one of
4773those pilings [the Preconstruction Mooring Pilings] before,
4780getting around the corner." Hr'g Tr. 227. Mr. Rankin described
4790his experience in navigating from the bayou through the Channel
4800headed for the pond:
4804. . . I've come in there, around that spit,
4814at low tide, and run aground because the pass
4823is so narrow you have to back up and find it.
4834In the process of finding it, you sometimes
4842have to power over it and that means you back
4852up as far as you can and go full tip wide up
4864to jump it. And in [the] process you're
4872aiming straight for the problems of the piers
4880where they are now. And I'm not saying I
4889can't do it. I'm just saying . . . I'm
4899afr aid I'm going to hit it someday. It's
4908that tight. It's that difficult.
4913* * *
4916So all of it [the shallowness, the shoals,
4924the spit, the difficulty in maneuvering
4930sailboats , the structures in the Channel ],
4937you've got to be moving. If you get stuck,
4946then you have to cut -- you dredge that area
4956and the y dredged it as close to . . . the end
4969of the spit. So it's very, cutting that
4977corner, you're aiming straight at those docks
4984or Mr. Veal's dock. And if I have to be
4994powering over it, by the time I get over the
5004hump, which is the end of the spit, then I
5014have to turn. I can't be turning over the
5023hump.
5024* * *
5027But I have pushed off -- my wife has pushed
5037off one of the pilings.
5042Hr'g Tr. 228 - 230.
50475 2 . Ms. Simpson has navigated the deep draft sailbo at owned
5060by Petitioner Beard through the Channel numerous times over the
5070past 20 years. She raced sailboats and participated in regattas
5080so often that she "started racing sailboats in the women's
5090regattas, where [she] captained and helmed [her] own boats. "
5099Hr'g Tr. 242. Compared to the three P etitioners who testified
5110and the sailing populati o n in the area , she and Petitioner Beard
5123sail their boats and "come . . . into Mahogany Mill Pond,
5135probably more often than anybody else." Hr'g Tr. 244.
51445 3 . Ms. Si mpson echoed the concerns of the three
5156Petitioners who testified . S he expressed her fear s of a
5168collision with the Project in the future based on difficulty in
5179navigating the Channel prior to the Project's installation . T hen
5190there were only the two Precon struction Mooring Pilings present
520024 fe et from shore as opposed to the Project that is now 24 feet
5215offshore with a width of 36 feet:
5222And like everybody else . . . we use Jim
5232Veal's slip . . . we have to go in almost
5243south of him . . . so you get the boat i n.
5256And once we pass the spit, we . . . do a
5268sharp turn and come up . . . if there's any
5279type of weather at all . . . you've got to
5290keep the boat moving . . . there [have] been
5300numerous occasions when the wind was heavy
5307. . . that we will come so close to the
5318pilings out there that I actually was on the
5327bow of the boat pushing it away . . . .
5338* * *
5341. . . if there's a wind blowing . . . you
5353have to be coming so fast to keep it up and
5364then you have to make sure that you can make
5374that run and keep it und er control. And like
5384I said, I've pushed off from [the pilings].
5392Hr'g Tr. 244 - 6 .
53985 4 . Mrs. Simpson's concerns were not limi ted to the
5410Project. B oats with engines attached to their sterns docked at
5421the Project can extend out further than the Project : "[N]ow
5432there's been another . . . 4 feet added on to [the Project]
5445because . . . everybody [who] builds a dock wants a boat bigger
5458than the dock is." Hr'g Tr. 247. The three Petitioners shared
5469the concern about the additional extension into a Channel of
5479boats and engines beyond the 24 feet of the Project's extension.
5490Ms. Simpson reiterated, "If there's any wind at all, [the Project
5501and boats docked at it] are going to cause major problems." Hr'g
5513Tr. 248.
55155 5 . As the three Petitioners who testified, Ms. Simpson has
5527never collided in a sailboat with the Preconstruction Mooring
5536Pilings . At the time of hearing, Petitioner Beard had been in
5548the Bahamas with his sailboat since October 2012 and had not
5559returned. Ms. Simpson, therefore, had not yet contended with the
5569Project or any boats docked there in navigat ing the Channel .
55815 6 . Ms. Simpson, however, did observe Mr. Kr ie gel attempt
5594to navigate his sailboat through the Channel clear of the
5604Project. He ran aground trying to avoid both the spit and the
5616struc tures. Ms. Simpson detailed potential consequences :
5624. . . [S] ailboats running aground, it's not a
5634good thing . . . y ou have got your keels and
5646. . . instruments on the b ottom close to your
5657rudder . . . you run a sailboat aground, you
5667take the bottom paint off and you hit
5675whatever else is down there . . . then you
5685have to put it in power drive t o get it back
5697off . . . y ou can do quite a bit of damage to
5711a boat when you run it aground, especially a
5720sailboat.
5721Hr'g Tr. 259.
5724Potential Solution
57265 7 . Mr. Kri egel referred to a turning basin in the area of
5741the Palm Harbor Marina. The turning basin is where Petitioners
5751headed for the pond in their sailboats commence the swing around
5762the spit taking into consideration the limiting point of the Veal
5773Dock in order to avoid collision s with structures (or docked
5784boats) that extend into the Channel.
57905 8 . A potential solution to the difficulties encountered by
5801navigators of sailboats in the Channel is to dredge the turning
5812basin . If the turning basin were wide and deep enough, sailboats
5824would have more opportunity to enter the Channel straight on
5834rather than having t o swing around the spit when entering .
58465 9 . Some b oats headed for the pond are able to make the
5861necessary turn inside the turning basin now. Mike Lunn lives at
5872Mahogany Mill Pond. When he looks out the sliding glass door at
5884his house he has a clear view of the Project and the turning
5897basin. From what he has usually seen, boats "turn around in
5908[the] basin a little bit." Hr'g Tr. 266. He doesn't ever seem
5920them "cut like that , " id. , in the swi ng described by Petitioners.
5932Whether he was referring to sailboats or just powerboat s is not
5944entirely clear , but h e testified with regard to Petitioners and
5955the entry into the Channel they described, "that's what y'all are
5966saying but that's not what I see." Id .
597560 . I n testimony that followed Mr. Lunn's, Mr. Kriegel
5986explained that it is hard to judge whe n and where to make turn s
6001in the basin because of the narrowness of the Channel. There is
6013no doubt, howeve r, that navigation would be improved with
6023dredging of the turning basin to make it deeper and wider even if
6036it did not entirely cure the navigational problems described by
6046all of Petitioners and Ms. Simpson . As Mr. Kr ie gel offered on
6060cross - examination by Mr. Dunaway:
6066Now, if the turning radius were expanded, if
6074the turning basin were dredged out, if the
6082boats had more room to maneuver, some of [the
6091navigational problems getting to the pond
6097from the bayou] could be improved, yes.
6104Hr'g Tr. 166. Whether dre dging the turning basin is an
6115attainable solution was not confirmed . Mr. Kr ie gel testified,
"6126I'm not sure . . . everybody would like to see it dredged out."
6140Hr'g Tr. 167.
6143CONCLUSIONS OF LAW
6146a. Jurisdiction
61486 1 . The Division of Administrative Hearings has
6157jurisdiction over the subject matter of this case and the
6167parties. §§ 120.569 and 120.57, Fla. Stat.
6174b. Standing
61766 2 . Petitioners Kr ie gel, Baars , and Ed Rankin & Kay Rankin
6190proved that their substantial interests could reasonably be
6198affected by the Project. They demonstrated that they have
6207standing to bring their respective petitions. Palm Beach Cnty .
6217Envtl. Coal . v. Fla . Dep't of Envt l . Prot . , 14 So. 3d 1076 (Fla.
62354th DCA 2009).
62386 3 . The evidence offered by the three testifying
6248Petitioners and M s. Simpson proved that Petitioner Beard's
6257substantial interests could reasonably be affected by the Project
6266as well.
6268c. Burden and Standard of Proof
62746 4 . As the party seeking the exemption, Mahogany Mill bears
6286the burden of proving by a preponderance of the evidence that it
6298has clearly established entitlement. See Lardas v. Dep't of
6307Envtl. Prot . , Case No. 05 - 0458 (Fla. DOAH Aug. 24, 2005; Fla. DEP
6322Oct. 21, 2005).
6325d. Statutes and Rules at Issue
63316 5 . To qualify for an exemption for the Project under
6343se ction 403. 813 (1)(b), Florida Statutes, Mahogany Mill was
6353required to demonstrate that the Project will meet the
6362qualifications in the statute including that a project will not
"6372create a navigational hazard." § 403. 813 (1)(b), Fla. Stat. See
6383also Fla. Admi n. Code R. 62 - 346.051(5)(a).
63926 6 . Qualification for the regulatory exemption under
6401section 403. 813 (1)(b) entitles Mahogany Mill to an authorization
6411to use state - owned submerged lands. See Fla. Admin. Code R. 18 -
642521.005(1)(b) and 18 - 21.004(7)(g).
6430e. Entit lement to Exemption and Authorization
64376 7 . Mahogany Mill demonstrated by a preponderance of
6447evidence that the Project "will not create a navigational
6456hazard." This conclusion is based on the evidence that the
6466Project does not extend into the Channel more than 24.0 feet
6477offshore, the same extension into the Channel of the
6486Preconstruction Mooring Pilings with which no vessel was shown to
6496have ever collided with in the many trips taken by Petitioners in
6508and out of the Channel.
65136 8 . The conclusion that Mahog any Mill is entitled to the
6526regulatory exemption and the proprietary authorization does not
6534mean that the concerns of the Petitioners have no foundation.
6544The configuration of the Channel, the spit, the Palm Harbor
6554Marina, and the shoals in the area presen ts navigational
6564challenges particularly to deep draft sailboats seeking ingress
6572to Mahogany Mill Pond under certain weather conditions.
65806 9 . Nonetheless, the preponderance of the evidence clearly
6590establishes that the Project is no more of a navigational hazard
6601than the Preconstruction Mooring Pilings. Thus, it does not
"6610create" a navigational hazard. There is a potential solution,
6619moreover, to the difficulties in entering the Channel posed by
6629Petitioners . The solution was presented by the Department
6638th rough the rebuttal testimony of Mr. Lunn ; that is , turning in
6650the turning basin just before entering the Channel when heading
6660for the pond. Dredging of the turning basin would likely enhance
6671the chances of success.
6675RECOMMENDATION
6676Based on the foregoing Fi ndings of Fact and Conclusions of
6687Law, it is
6690RECOMMENDED that that the Department of Environmental
6697Protection issue a f inal o rder determining that Mahogany Mill
6708Owners Association, Inc.'s Project qualifies for an exemption
6716from the need to obtain an Envir onmental Resource Permit under
6727section 403.813(1)(b) and qualifies for authorization to use
6735sovereign submerged lands under r ule 18 - 21.005(1)(b).
6744DONE AND ENTERED this 11th day of June , 2013 , in
6754Tallahassee, Leon County, Florida.
6758S
6759DAVID M. MALONEY
6762Ad ministrative Law Judge
6766Division of Administrative Hearings
6770The DeSoto Building
67731230 Apalachee Parkway
6776Tallahassee, Florida 32399 - 3060
6781(850) 488 - 9675
6785Fax Filing (850) 921 - 6847
6791www.doah.state.fl.us
6792Filed with the Clerk of the
6798Division of Administrative Hea rings
6803this 11th day of June , 2013 .
6810ENDNOTE
68111/ References to statutes are to Florida Statutes (2012) unless
6821otherwise noted.
6823COPIES FURNISHED:
6825Brynna J. Ross, Esquire
6829Department of Environmental Protection
6833Mail Station 35
68363900 Commonwealth Boulevard
6839Tallahassee, Florida 32399 - 3000
6844Robert Kriegel
6846Apartment 14
68481280 Mahogany Mill Road
6852Pensacola, Florida 32507
6855William J. Dunaway, Esquire
6859Clark, Partington, Hart, Larry,
6863Bond and Stackhouse
6866Post Office Box 13010
6870Pensacola, Florida 32591
6873Bryan Baars
68751516 East Mallory Street
6879Pensacola, Florida 32503
6882Mike Beard
68841280 Mahogany Mill Road, Unit 15
6890Pensacola, Florida 32507
6893Ed Rankin
6895Kay Rankin
6897Mahogany Mill Homeowners Association
69011280 Mahogany Mill Road, Unit 7
6907Pensacola, Florida 32507
6910Lea Crandall, Ag ency Clerk
6915Department of Environmental Protection
6919Douglas Building, Mail Station 35
69243900 Commonwealth Boulevard
6927Tallahassee, Florida 32399 - 3000
6932Matthew Z. Leopold, General Counsel
6937Department of Environmental Protection
6941Douglas Building, Mail Station 35
69463 900 Commonwealth Boulevard
6950Tallahassee, Florida 32399 - 3000
6955Herschel T. Vinyard, Jr., Secretary
6960Department of Environmental Protection
6964Douglas Building
69663900 Commonwealth Boulevard
6969Tallahassee, Florida 32399 - 3000
6974NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6980Al l parties have the right to submit written exceptions within
699115 days from the date of this Recommended Order. Any exceptions
7002to this Recommended Order should be filed with the agency that
7013will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 09/10/2013
- Proceedings: Department of Environmental Protection's Response to Petitioners Kriegel, Baars, and Rankin's Exceptions to Recommended Order filed.
- PDF:
- Date: 09/10/2013
- Proceedings: Respondent, Mahogany Mill Owners Association, Inc., Response to Exceptions to Recommended Order Filed by Petitioners, Robert V. Kriegel, Bryan Barrs, and Ed & Kay Rankin filed.
- PDF:
- Date: 09/10/2013
- Proceedings: Florida Department of Environmental Protection's Exceptions to Recommended Order filed.
- PDF:
- Date: 06/12/2013
- Proceedings: Transmittal letter from Claudia Llado forwarding Exhibits, which were not admitted into evidence, to the agency.
- PDF:
- Date: 06/11/2013
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 04/29/2013
- Proceedings: Respondent, Mahogany Mills, LLC's, Proposed Recommended Order filed.
- Date: 04/18/2013
- Proceedings: Transcript Volume I-II (not available for viewing) filed.
- Date: 04/03/2013
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 03/29/2013
- Proceedings: Respondent, Mahogany Mills, LLC's Supplement to its Prehearing Statement filed.
- PDF:
- Date: 03/13/2013
- Proceedings: Notice of Hearing (hearing set for April 3 and 4, 2013; 9:30 a.m., Central Time; Pensacola, FL).
- PDF:
- Date: 03/11/2013
- Proceedings: Order of Consolidation (DOAH Case Nos. 13-0686, 13-0687, 13-0774, and 13-0775).
- PDF:
- Date: 03/11/2013
- Proceedings: Department of Environmental Protection's Response to Initial Order filed.
- PDF:
- Date: 03/06/2013
- Proceedings: Respondent Department of Environmental Protection's First Request for Production of Documents to Petitioner Ed Rankin filed.
- PDF:
- Date: 03/06/2013
- Proceedings: Respondent Department of Environmental Protection's First Request for Production of Documents to Petitioner Kay Rankin filed.
- PDF:
- Date: 03/06/2013
- Proceedings: Notice and Certificate of Service of Respondent DEP's First Set of Interrogatories to Petitioner, Kay Rankin filed.
Case Information
- Judge:
- DAVID M. MALONEY
- Date Filed:
- 03/01/2013
- Date Assignment:
- 03/04/2013
- Last Docket Entry:
- 09/10/2013
- Location:
- Pensacola, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
Counsels
-
William J. Dunaway, Esquire
Address of Record -
Robert Montgomery
Address of Record -
Ed Rankin
Address of Record -
Brynna J. Ross, Esquire
Address of Record