13-003601 Pelican Island Audubon Society, Dr. Richard Baker, And Dr. David Cox vs. Indian River County And St. Johns River Water Management District
 Status: Closed
Recommended Order on Tuesday, August 5, 2014.


View Dockets  
Summary: Applicant gave reasonable assurances that all criteria for issuance of an ERP were satisified and that all requirements for a variance were met.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8PELICAN ISLAND AUDUBON SOCIETY,

12DR. RICHARD BAKER, AND DR. DAVID

18COX,

19Petitioners,

20vs. Case No. 13 - 3601

26INDIAN RIVER COUNTY AND ST.

31JOHNS RIVER WATER MANAGEMENT

35DISTRICT,

36Respondents.

37___________________ ____________/

39RECOMMENDED ORDER

41T his matter was heard before the Division of Administrative

51Hearings (DOAH) by its assigned Administrative Law Judge, D . R.

62Alexander, on June 4 - 6 , 2014, in Vero Beach, Florida.

73APPEARANCES

74For Petitioner s: Marcy I. LaHart , Esquire

81Marcy I. LaHart, P.A.

854804 Southwest 45th Street

89Gainesville, Florida 32608 - 4922

94For Respondent: Gail L. Hankinson , Esquire

100(District) Karen C. Ferguson, Esquire

105St. Johns River Water Management District

111Post Office Box 1429

115Palatka , Florida 3217 8 - 1429

121For Respondent: William K. DeBraal, Esquire

127(County ) Kate P. Cotner, Esquire

133Indian River County Attorney's Office

1381801 27th Street

141Vero Beach, Florida 32960 - 3388

147STATEMENT OF THE ISSUE S

152The issue s are (1) whether the St. John s River Water

164Management District (District) should approve the application of

172Indian River County (County) for an environmental resource

180permit (ERP) authorizing the construction and operation of a

189surface water management system with stormwater treatment for

197the Oslo Road Boat Ramp Parking Lot ; and (2) whether t he

209District should approve the County's request for a variance from

219Florida Administrative Code Rule 40C - 4.302(1)(c) and sections

22810.1.1(c), 12.1.1(d), and 12.2.5(c) of the Applicant's Handbook:

236M anagement and Storage of Surface Waters (AH) in order to

247perform other related work .

252PRELIMINARY STATEMENT

254On August 16 , 2013, the District published notice that it

264intended to issue an ERP authorizing the County to construct a

275surface water management s ystem adjacent to the Indian River

285Lagoon (Lagoon) . On August 23, 2013, a Final Order was issued

297approving the County's request for a variance in order to

307conduct certain related work on the project. Pet itioners timely

317requested a hearing to contest thos e agency actions, and the

328matter was referred to DOAH to conduct a hearing. Petitioners

338were later authorized to file a First Amended Petition (Amended

348Petition).

349At the final hearing, Petitioners jointly presented the

357testimony of five witnesses; Petiti oners Exhibits 1 - 4, 8, 12,

36915, 18, 28, 33, 37, and 42 were received in evidence. The

381County presented the testimony of three witnesses; County

389Exhibits 1 - 5 5 were received in evidence. The District presented

401the testimony of five witnesses; District Exhib its 1 - 3, 5, 6,

41416, 20, 32, 34, 37, 38, 41, 42, 47, 48, 52, 56 - 58, 61, 61A, 62,

43163, 63A, 64, 67, 69, 72 - 75, 77, and 78 were accepted in

445evidence. Petitioners' Request to Supplement the Record with

453additional exhibits , filed after Proposed Recommended Order s

461(PROs) were submitted, is denied . All proposed findings in

471their PRO that are based on the excluded exhibits have been

482disregarded. Finally, the undersigned took official recognition

489of chapters 40C - 4 and 40C - 42, in e ffect when the proposed agency

505acti on was issued; the Applicant's Handbook: Management and

514Storage of Surface Waters (Dec. 27, 2010); Applicant's Handbook:

523Regulation of Stormwater Management Systems (Dec. 27, 2010); and

532rule 62 - 302.700 .

537A f ive - volume Transcript of the hearing has been pr epared.

550Proposed Recommended Orders were filed by the parties , and they

560have been considered in the preparation of this Recommended

569Order.

570FINDINGS OF FACT

573A . The Parties

5771. The Pelican Island Audubon Society is a Florida non -

588profit corporation whos e mission is to preserve and protect the

599animals, plants, and natural communities in the County through

608advocacy, education, and public awareness. It has more than

61725 members that live in the County and has been a chapter of the

631Audubon Society of Flori da since 1964.

6382. Dr. Richard Baker resides in the County and engages in

649water - based recreational activities such as canoeing, bird

658watching, nature photography, and fishing in the Lagoon near the

668b oat r amp.

6723. Dr. David Cox resides in the County and engages in

683water - based activities such as kayaking and nature observation

693in the vicinity of the b oat r amp .

7034. The County is the applicant for an ERP and variance for

715a project known as the Oslo Road Boat Ramp project .

7265. The District is the agency cha rged with the

736responsibility of regulating water resources within its

743geographic boundaries and to administer and enforce chapter 373 ,

752Florida Statutes, and the rules promulgated under title 40C.

761B. The Existing Oslo Road , Boat Ramp , and Lagoon

7706. Oslo R oad is a County - owned road that runs in an east -

786west direction and intersects with U.S. Highway 1 just south of

797State Road 60 . To the east of U.S. Highway 1 , the road is paved

812for a short distance ; the remain ing portion of the road ( 2,460

826feet ) is a narro w, two - lane dirt road that dead - ends at the bo at

845r amp.

8477. Most of the dirt road is bordered to the north and

859south by a mangrove swamp that extends to the edges of the road.

872All wetlands have been previously disturbed. The surrounding

880and abutting jur isdictional wetlands consist primarily of both

889tidal (north side) and impounded/partially tidal mangrove swamp

897(south side), which was created years ago by a mosquito control

908district in order to reduce the salt marsh mosquito population.

918The boat ramp is bordered to the north by a clump of red

931mangroves and a sparsely vegetated sandy shoreline and to the

941south by a dense mangrove fringe.

9478 . During rain events, the dirt and sediment can wash off

959the road as erosion. Th is requires the County to continua lly

971maintain the dirt road by grading and adding marl material to

982bring it back up to grade.

9889 . The b oat r amp has been in existence for more than

100250 years and is the nearest public access to the popular South

1014County fishing areas in the Lagoon. Alt hough there are 1 7 other

1027boat ramps in the County, t he closest one is six miles to the

1041north in the City of Vero Beach. The typical users of the b oat

1055r amp are fishermen with shallow - draft boats , while the open

1067shoreline to the north is normally used to la unch canoes and

1079kayaks and to access the river by wading fishermen. There are

1090a number of water - based communities in the area, including one

1102directly to the east of the boat ramp. Many boats that do not

1115launch at the boat ramp use the nearby seagrass be ds as a

1128fishing destination.

113010 . The b oat r amp has a dirt cul - de - sac , a concrete boat

1148ramp with finger piers , and is surrounded by the Lagoon , the

1159receiving water body for the project and classified as Class III

1170waters . In December 2007, the Department o f Environmental

1180Protection (DEP) verified that the Lagoon is an Impaired Water

1190Body of the State, with the impairment being for nutrients in

1201the vicinity of the project.

12061 1 . Currently , there are no designated parking areas

1216associated with the b oat r amp . Vehicles both with and without

1229trailers park in the cul - de - sac and along the roadside. The

1243only limit to the extent of parking along Oslo Road is the

1255distance somebody is willing to walk. During peak times, the

1265dirt road and cul - de - sac become congeste d and blocked with cars,

1280trucks, and boat trailers.

12841 2 . In 1977, the County obtained a permit from the United

1297States Army Corps of Engineers (USACE) to construct the b oat

1308r amp with two appurtenant piers and a riprap groin . During the

1321subsequent years, t h ere was substantial deterioration to the

1331ramp, bulkhead, and docks . Accordingly , i n 2009, using an

1342exemption under rule 40C - 4.051(12)(i), the County rep laced the

1353concrete portion of the b oat r amp within the same footprint and

1366constructed two accessory doc ks that now define the width of the

1378one - lane boat ramp. During this process, the County removed

1389around 25 cubic yards of muck from the base of the boat ramp.

14021 3 . The b oat r amp is only 16 feet wide and 40 feet in

1419length and is located in water less than t hree feet below Mean

1432Low Water (MLW). In contrast, a typical boat ramp in the County

1444is around 76 feet, or twice a s long as the Oslo Road boat ramp.

14591 4 . The existing boat ramp was designed to be used by

1472motorized vessels. There is a separate launch area for kayak

1482and canoes next to the concrete ramp. T he motorized vessels

1493that currently use the boat ramp are small with a draft less

1505than 18 inches. This is partly due to the presence of cap rock

1518beyond the proposed dredging area, which limits the draft s ize

1529of the boats, and the small size of the single - lane ramp.

15421 5 . The only signage at the ramp advises the public that

1555this is a shallow draft vessel launch and that the limits of the

1568draft are 18 inches.

15721 6 . The channel leading out of the boat ramp wa s

1585previously dredged around 1950. During that era, only shallow

1594draft boats would launch at Oslo Road. In February 1977 , the

1605United States Fish and Wildlife Service confirmed that an old

1615channel about 75 feet long and 15 feet wide existed at the boat

1628ram p location. In May 1977, a dditional maintenance dredging of

1639the old silted channel to a depth of - 3.00 Mean Sea Level (MSL)

1653was authorized by the USACE. Although the parties disagree over

1663whether any dredging was ever performed , surveys , aerial

1671photograp hs, and research suggest that more than likely the

1681project site was dredged in the late 1970s or early 1980s . A

1694portion of the area that the County proposes to dredge falls

1705within the area that was previously permitted by the USACE in

17161977.

17171 7 . The dista nce from the boat ramp to the Intracoastal

1730Waterway (ICW) is approximately one - half mile . The channel is

1742delineated by a number of poly vinyl chloride pipes and six sets

1754of permitted navigational channel markers leading to the ICW.

1763The water depths in th e area surrounding the boat ramp,

1774including the channel to the ICW, are very shallow.

17831 8 . Drainage from the road currently runs down the ramp

1795c ausing sand and other material to build up in the ramp area.

1808Due primarily to this drainage, a t low tide the wa ter at the

1822boat ramp area has been so shallow that boaters have experienced

1833great d ifficulty when loading ; in some cases, launching or

1843retrieving a vessel is almost impossible. After a rain event,

1853turbidity plumes in the Lagoon have been observed extendin g

1863100 feet to the north of Oslo Road, 150 feet to the south, and

1877approximately 30 feet to the east.

18831 9 . The seagrass beds adjacent to the boat ramp were

1895described as lush, healthy, and productive . The proposed

1904dredging area contains less than 1.5 per cent of seagrass

1914coverage. There is no evidence that the current use of the boat

1926ramp causes prop scarring to the surrounding seagrass.

193420 . The Lagoon in the vicinity of the boat ramp has been

1947determined to be a high manatee use area, as defined by the

1959C ounty Manatee Protection Plan (MPP). However, this area is not

1970a h igh w atercraft - related m anatee m ortality area. Since 2002,

1984the waterway in the vicinity of the project site has been

1995regulated by seasonal manatee protection speed zones. Signs

2003have been posted since 2003. The shoreline to the ICW is

2014currently regulated at s low s peed between November 1 and April

202630 and is unregulated the remainder of the year. The County

2037intends , however, to adopt a new ordinance that makes the slow

2048speed zone effective the entire year, rather than just during

2058the winter months.

2061C. The Project and Variance

20662 1 . In late 2009, the County submitted to the District its

2079ERP application . Since that time, the County has modified its

2090plans seven times and amended the applicatio n tw ice . Notably,

2102t he modifications reduce the direct impacts to wetlands from

21122.98 acres to 1.41 acres for the improvement of the dirt road

2124and parking lot ; they also reduce impacts to ditches that

2134support fisheries habitat and submerged lands. They wil l result

2144in 0.113 acres of combined direct impacts to seagrass and Lagoon

2155substrate from the proposed dredging. The project will not

2164change the hydroperiod of the surrounding wetlands. The number

2173of trailer parking spaces was reduced from 32 to 12 and th e

2186parking space angle changed . A dry retention area on the west

2198side of the project will be installed; a wet detention pond was

2210eliminated ; the dock extension reduced; and at Petitioners'

2218request, the project was shifted north to avoid impacting a

2228ditch t o the south .

22342 2 . The County eliminated and reduced impacts to surface

2245waters by reducing the width of the proposed dredge area so as

2257to not impact seagrass beds to the north and south of the

2269channel . Dredging is limited to a depth of - 2.5 feet MLW and

2283wi ll be within the same area that was dredged in the 1950s. It

2297is not expected to contribute to larger vessels launching at the

2308boat ramp.

23102 3 . The latest iteration of the project consists of

2321paving the 2,460 feet of dirt road to a width of 26 feet ,

2335constr ucting a surface water management system, and constructing

2344a parking area to accommodate 12 vehicles with boat trailers and

235511 vehicles without a trailer. No changes to the size or

2366configuration of the concrete boat ramp will be made.

23752 4 . The project w ill extend the northern accessory dock of

2388the existing one - lane boat ramp by approximately 3 2 feet to

2401allow more boats to tie off ; dredge 4,943 square feet (0.113

2413acres) of the ingress/egress access way within the Lagoon to a

2424depth of - 2.5 MLW; install an additional three sets of channel

2436markers (six in total); install "No Parking" signs to limit

2446vehicle parking to the designated parking area; and install

2455additional signage to warn boaters of the shallow depths in the

2466area and to notify boaters that to laun ch at this boat ramp,

2479vessel drafts must not exceed 18 inches.

24862 5 . The proposed surface water management system consists

2496of roadside conveyance swales, pipes, weirs, and two dry

2505retention areas which will provide water quality treatment for

2514stormwater run off from basins upstream of the project area and

2525the existing paved portion of Oslo Road. The two proposed dry

2536retention areas will provide water quality treatment in

2544accordance with the design and performance criteria in the

2553District's rules. Currently, these areas drain into existing

2561swales and then east in to the Lagoon with no water quality

2573treatment. The system will result in a net improvement to water

2584quality based on a nutrient loading analysis review by the

2594District.

25952 6 . The County is proposing o ff - site mitigation to offset

2609the direct and secondary impacts. It consists of 18 acres of

2620enhancement at Earman Island within the Lost Tree Island s

2630Conservation Area , including 14 acres of wetland enhancement.

2638Earman Island is part of the chain of island s in the Lagoon just

2652north of State Road 60 known as Lost Tree Island s purchased by

2665the County for conservation purposes. The proposed enhancement

2673area is building upon an existing mitigation area on the north

2684end of the island. The proposed mitigation i s within the same

2696drainage basin as the area of wetlands and other surface waters

2707to be adversely affected. There are no cumulative impacts

2716associated with the project.

27202 7 . The County owns all of the property that will be

2733dredged, filled, or paved, incl uding the submerged lands

2742waterward of the Mean High Water ( MHW ) line at the boat ramp out

2757approximately 215 feet. This area is not within an Aquatic

2767Preserve or Outstanding Florida Waters , and none of the dredging

2777will occur on sovereign submerged lands. See Jt. Pre - hearing

2788Stip., p. 13, ¶¶ 18 - 20.

27952 8 . In summary, t he purpose of the project is seven - fold:

2810provide water quality treatment for the runoff water; limit the

2820number of parking spaces available for users of the boat ramp;

2831decrease the need for the County to maintain the 2,460 feet of

2844dirt road; create a safe place for boaters to moor while waiting

2856to retrieve their boats from the Lagoon; allow boaters to safely

2867launch and retrieve their boats from the Lagoon at low tide;

2878create a clear channel for boaters to get from the base of the

2891boat ramp to the ICW; and decrease turbidity in and around the

2903mouth of the boat ramp.

29082 9 . The portion of the project that expands the accessory

2920dock and dredges the channel will be located in Class III waters

2932class ified by DEP as restricted for shellfish harvesting.

294130 . Rule 40C - 4.302(1)(c) places additional requirements on

2951regulated activities that are proposed in Class III waters

2960r estricted for shellfish harvesting. These requirements are set

2969forth in the AH. Without a variance from the rule and AH , the

2982District would be required to deny the ERP . Therefore, the

2993County must qualify for and obtain a variance from rule 40C -

30054.302(1)(c) and AH sections 10.1.1(c), 12.1.1(d), and 12.2.5(c) .

3014D . Petitioners' Concerns

30183 1 . The essence of Petitioners' objections is that once

3029Oslo Road and the parking lot are paved, and the channel

3040dredged, the boat ramp will attract a tremendous number of

3050fishermen from throughout the area who will use l arger and

3061deeper draft boats to a ccess the Lagoon . Petitioners contend

3072that more and larger boa ts , along with the proposed activities,

3083will result in the environmental impacts described in their

3092Amended Petition.

30943 2 . The conditions for issuance of an ERP are set forth in

3108rules 40C - 4.30 1 and 40C - 4.302. The standards and criteria in

3122the AH are used to determine whether an applicant has met the

3134conditions for issuance in the two rules. Rule 40C - 1.1002

3145establishes the requirements for obtaining a variance.

31523 3 . The parties have stipulat ed that the project either

3164complies with the following conditions for issuance of a permit

3174or that they are not applicable: rules 40C - 4.301(1)(a), (b),

3185(c), (e), (g), (h), (i), (j), and (k); and 40C - 4.302(1)(a)3.,

31975., and 6.

32003 4 . R emaining at issue is w hether reasonable assurance has

3213been provided to demonstrate that the proposed activities will

3222not adversely impact the value of functions provided to fish and

3233wildlife and listed species by wetlands and other surface waters

3243(40C - 4.301(1)(d)); that the pro posed activities will not cause

3254adverse secondary impacts (40C - 4.301(1)(f)); and that the

3263portion of the project located in wetlands or the Lagoon is not

3275contrary to the public interest (r ules 40C - 4.302(1)(a)1., 2.,

32864., and 7. and 40C - 4.302(1)(b) ) . As a p art of these claims,

3302Petitioners also contend that the County failed to implement all

3312practicable design modifications to reduce or eliminate the

3320adverse impacts to wetland and surface water functions ; the

3329proposed mitigation fail s to offset the adverse ef fects of the

3341project ; and the D istrict did not consider the impacts of

3352increased boat usage when reviewing secondary impacts generated

3360by the project . Finally, Petitioners contend that the County

3370has not shown that it meets the conditions in rule 40C - 1.10 02

3384for a variance. These contentions are addressed separately

3392below.

3393a. Rule 40C - 4.301(1)(d)

33983 5 . Pursuant to th is rule , and related AH provisions , the

3411County must g ive reasonable assurance that the proposed activity

3421will not adversely impact the value of functions provided to

3431fish and wildlife and listed species by wetlands and other

3441surface waters.

34433 6 . To meet th is requirement, t he County has implemented ,

3456to the extent p racticable , design modifications to reduce or

3466eliminate adverse impacts to wetl ands and other surface waters.

3476The original application submitted in 2009 proposed impacts to

34852.98 acres of wetlands and surface waters. Since that time, the

3496County has reduced or eliminated its proposed wetland impacts by

3506more than 50 percent. This was done by incorporating design

3516modifications that eliminated the construction of a stormwater

3524pond in wetlands and add ing compensating stormwater treatment;

3533shifting impacts out of critical fisheries and open water

3542habitat within the southern impoundment to upland areas;

3550installing a retaining wall along the trailer parking area to

3560limit the fill slope impacts; and making minor modifications to

3570reduce the project footprint in several locations.

35773 7 . The County also eliminated and reduced adverse impacts

3588to surface waters by reducing the width of the proposed dredge

3599area so as to not impact the seagrass beds to the north and

3612south of the channel and limiting the dredging to - 2.5 MLW.

3624Th at depth is consistent with the existing limitations adjacent

3634to the dre dge area and will not allow deeper draft vessels to

3647use the boat ramp. The addition of a permit condition that

3658requires the placement of "No Parking" signs along Oslo Road and

3669limiting the parking of boat trailers to the 12 designated

3679parking spaces will prevent an increase in boat traffic from the

3690existing boat ramp. The installation of signage at the boat

3700ramp advising boaters of the boat motor draft restriction and

3710the year - round manatee slow speed zone will also reduce impacts.

3722Finally, three sets of channel markers will also be installed to

3733keep boaters within the designated channel. As discussed below,

3742after these design modifications are implemented, t he remaining

3751impacts are sufficiently offset by mitigation proposed by the

3760County.

376138. The Dis trict also considered the condition of the

3771wetlands and surface waters to be impacted; their hydrologic

3780connection; their uniqueness; location; and fish and wildlife

3788utilization, and then evaluated the proposed mitigation. The

3796more persuasive evidence sup ports a finding that the mitigation

3806is sufficient to offset the proposed impacts.

38133 9 . As required by the AH, t he District provided a copy of

3828the County's application to the Florida Fish and Wildlife

3837Conservation Commission (FFWCC). Among other things, th e FFWCC

3846is the agency responsible for reviewing the County's MPP. The

3856FFWCC indicated that the project is consistent with the County's

3866MPP. It also recommended certain measures to be taken by the

3877County, which are now included as conditions in the propos ed

3888permit.

388940 . Petitioners assert that t he National Marine Fisheries

3899Service , a federal agency, considers the entire Lagoon, and the

3909ditches extending into it, to be an essential fish habitat (EFH)

3920that provides habitat required for the various life cycle s of

3931many types of fish. Petitioners contend that the project wil l

3942result in impacts to the EFH adjacent to the proposed dredging

3953areas , a nd that th is type of impact can not be mitigated. For

3967the following reasons, this contention is rejected.

39744 1. F irst, the more persuasive evidence is that the area

3986to be dredged contains less than 1.5 percent seagrass coverage ,

3996and channel markers will be used to keep boaters within the

4007designated channels. Only around 200 square feet (0.005 acres)

4016of seagrass will be a ffected , and not the much larger area that

4029Petitioners assert will be impacted . N o other impacts to

4040seagrass are expected to result from the project, other than

4050those identified and mitigated for during the application

4058review. Second, the District consid ered the actual Lagoon

4067impact area and determined that the same functions now being

4077provided in that area will be provided by the proposed

4087mitigation. Third, if one accepts Petitioners' a ssertion that

4096EFH can never be mitigated, no permit could ever be is sued for

4109any project that would impact the Lagoon or any ditches

4119connecting to it. Finally, b ased on the District's Uniform

4129Mitigation Assessment Method (UMAM) evaluation, the functional

4136loss, including direct and secondary impacts, was scored at

41451.212 wh ile the functional gain was 1.281. See Fla. Admin. Code

4157Ch. 62 - 345. With 1.5 acres of direct impacts, one acre of

4170secondary impacts, and 18 acres of mitigation, there are

4179approximately 0 .07 excess units of functional mitigation. Th e

4189UMAM review was not credibly refuted.

41954 2 . Petitioners failed to prove that the requirements of

4206rule 40C - 4.301(1)(d) have not been met.

4214b. Rule 40C - 4.301(1)(f)

42194 3 . Rule 40C - 4.301 (1) (f) require s an applicant to provide

4234reasonable assurance that a regulated activity will not cause

4243adverse secondary impacts to the water resources. Petitioners

4251contend that the project will increase the number and size of

4262boats that use the boat ramp and therefore cause secondary

4272impacts to seagrasses, manatees, and water quality.

42794 4 . Secon dary impacts occur outside the direct footprint

4290of the project but are very closely linked and causally related

4301to the activity to be permitted. De minimis or remotely related

4312secondary impacts are not considered.

43174 5 . To assess secondary impacts, the Dis trict evaluates

4328the impacts to wetlands and surface water functions; upland

4337habitat for aquatic or wetland dependent species; and historical

4346and archaeological resources.

43494 6 . The project will result in 0.86 acres of secondary

4361impacts to the remaining we tlands adjacent to the road paving

4372and parking area and 0.14 acres of secondary impacts associated

4382with sloughing and boat wake - related impacts.

43904 7 . The County has proposed mitigation that will

4400adequately offset the expected secondary impacts. I n

4408combi nation with dredging to only - 2.5 MLW and reducing parking

4420space for boat trailers, the mitigation will prevent additional

4429secondary impacts. Also, the boat ramp is significantly smaller

4438than the average boat ramp in the County and is designed

4449specificall y for small vessels. Th us, th e ramp itself limits

4461the size of the vessel that can launch at the site.

44724 8 . Through the use of additional channel markers,

4482signage, and a year - round slow speed zone, there should not be

4495an increased threat of boat collisions with manatees, prop

4504scarring of seagrass beds, or turbidity. Also, the removal of

4514the muck from the channel will be beneficial and reduce

4524turbidity in the nearby waters.

452949 . Petitioners have stipulated that no wetland dependent

4538listed species on site that use uplands for nesting or denning

4549are at issue.

45525 0 . There are no additional phases for this project.

4563Speculation of a future interchange at Interstate 95 and Oslo

4573Road, located many miles to the west of the boat ramp , and any

4586impacts that might occ ur if one was ever built, was not

4598considered under the District's secondary impact rule.

46055 1 . Petitioners failed to prove that the requirements of

4616the rule have not been met.

4622c. Rule 40C - 4.302 Î Public Interest Test

46315 2 . The public interest test for this type of project

4643requires that the County provide reasonable assurance that

4651activities to be located in, on, or over wetlands and other

4662surface waters will not be contrary to the public interest, as

4673determined by balancing seven criteria in subparagraphs 1. - 7 . of

4685the rule . The test takes into account the positive, negative,

4696and neutral effects of the activity. The parties have

4705stipulated that subparagraphs 3. and 6. are not at issue. The y

4717govern navigation, shoaling, and erosion, and historical and

4725archae ological resources. The navigation factor is positive and

4734the archaeological resource factor is neutral.

47405 3 . Subparagraph 1. requires the District to determine

4750whether the activity will adversely affect the public health,

4759safety, or welfare or the proper ty of others. The more

4770persuasive evidence supports a finding that the activities will

4779not adversely affect the public health, safety, or welfare of

4789the property of others. Presently, it is difficult to launch

4799and load boats at the ramp due to the area b eing silted down.

4813This can result in serious safety issues. By d redging this

4824area , public safety will be enhanced. The installation of

4833navigational channel markers and signage will also be beneficial

4842to the public health, welfare, and safety, as will th e year -

4855round slow speed zone. This factor is positive.

48635 4 . Subparagraph 2 . r equires the District to determine

4875whether the activity will adversely affect the conservation of

4884fish and wildlife, including endangered or threatened species,

4892or their habitats. The evidence supports a finding that the

4902proposed mitigation is appropriate and more than offsets the

4911proposed impacts. The County eliminated and reduced impact s by

4921more than one - half. The proposed dredging area contains less

4932than 1.5 percent seagrass coverage . The project will not result

4943in adverse impacts to manatee. Finally, the County is proposing

495318 acres of mitigation, including the creation of an open

4963water/tidal creek feature which will provide the same functions

4972as the areas being impacted. This factor is positive.

49815 5 . Subparagraph 4. requires the District to determine

4991whether the activity will adversely affect the fishing or

5000recreational values or marine productivity in the vicinity of

5009the project. The evidence supports a finding that the 18 acres

5020of mitigation will improve marine productivity by providing a

5029substantial amount of both mangrove and salt marsh vegetation

5038along the sides of the tidal creek and open water component of

5050fisheries. Also, the County has eliminated and reduced impa cts

5060to seagrasses by limiting the dredging area to an area with less

5072than 1.5 percen t seagrass coverage. Finally, it has removed the

5083stormwater system from the southern impoundment to avoid a

5092critical fisheries open water habitat. This factor is positive .

51025 6 . Subparagraph 5. requires the District to determine

5112whether the activity will be of a temporary or permanent nature.

5123Because the mitigation offsets the adverse impacts , and the

5132mitigation and dredging areas are both permanent in nature, the

5142temporar y or permanent factor is neutral.

51495 7 . Subparagraph 7. require s an evaluation of the current

5161condition and relative value of the functions being performed by

5171areas affected by the proposed activity. The current condition

5180and relative functions being perfo rmed by the areas affected by

5191the project are high functioning. The evidence shows that the

5201project will not change this high functioning aspect of the

5211area. The District also conducted a UMAM review , which

5220considered the relative value of plant communit ies, hydrology,

5229and other factors , and demonstrate d that the mitigation more

5239than offsets the impacts. Finally, t he County established that

5249the mitigation area provides the same functions as the impact

5259areas. Therefore, this factor is positive.

52655 8 . The District's determination that the project will not

5276be contrary to the public interest is supported by a

5286preponderance of the evidence .

5291E. Variance

529359 . Because a portion of the project will be within Class

5305III waters classified by DEP as restricted for sh ellfish

5315harvesting, the County must qualify for and obtain a variance.

5325A variance may be granted when an applicant demonstrates that it

5336would suffer a hardship, not self - imposed, if the variance is

5348denied. See Fla. Admin. Code R. 40C - 1.1002. In determin ing

5360whether a variance should be approved, the District balances the

5370social, economic, and environmental impacts on the applicant,

5378the residents of the area, and on the State with those same

5390im pacts if the variance is denied.

53976 0 . The County has demonstrat ed that the application of

5409rule 40C - 4.30 2 (1)(c) and AH sections 10.1.1(c), 12.1.1(d), and

542112.2.5(c) would create a hardship in this case by precluding the

5432construction of the proposed accessory dock extension and the

5441dredging of an existing ingress/egress way within the Lagoon

5450that will improve public safety and enhance recreational

5458opportunities for the citizens of the area. There are no viable

5469alternatives that would address the functionality and safety of

5478the existing boat ramp.

54826 1 . The hardship is not self - imposed in that the normal

5496processes of erosion, wind, and tides contribute to the

5505accumulation of sand and muck within the ingress/egress access

5514way, which over time has impeded the process of launching and

5525loading vessels at the boat ramp. The nar row channel is

5536bordered on the north and south by productive seagrass beds.

5546The extension of the accessory dock and dredging of the access

5557channel will expedite the loading process and reduce the need

5567for boat operators to circle in the shallow waters wai ting their

5579turn to access the ramp.

55846 2 . The environmental impact of the project is positive.

5595There will be no harm to the water quality of Class III waters

5608and the shellfish beds. The Department of Agriculture and

5617Consumer Affairs reviewed the project a nd concluded that it

5627would not result in a reclassification of shellfish harvesting

5636waters. The stormwater treatment on the uplands will result in

5646a reduction of nutrient loading to the Lagoon, which is now

5657designated by DEP as impaired by nutrients. The extension of

5667the accessory dock, along with making the area a year - round slow

5680speed zone , will reduce potential impacts to manatees.

56886 3 . The dredging and extension of the dock will be a

5701convenience to the boating public and may enhance public safety

5711dur ing periods of inclement weather or other exigent

5720circumstances.

57216 4 . Petitioners failed to prove that all requirements for

5732a variance have not been met.

5738CONCLUSION S OF LAW

57426 5 . The parties have stipulated to the facts necessary to

5754establish that Petitio ners have standing to contest the permit

5764and variance.

57666 6 . The parties agree that the District's rules in effect

5778on August 23, 2013, contain the criteria applicable to the

5788permit that is the subject of this proceeding.

57966 7 . Section 120.569(2)(p) , Florida Statutes (2013), is

5805applicable to this case. It establishes the order of

5814presentation and burden of proof in a permit challenge case

5824under chapter 373. Because Petitioners have challenged a permit

5833issued under chapter 373, they have the "burden of ultima te

5844persuasion and the burden of going forward to prove the case in

5856opposition to the [permit] by competent and substantial

5864evidence." Id.

58666 8 . There are no reported cases that address the issue of

5879whether section 120.569(2)(p) applies to a person chall enging

5888the approval of a variance. The issue was not directly

5898addressed by the parties in the ir Joint Pre - hearing Stipulation

5910or PROs. The District defers to the criteria in section

5920403.201(1) to determine whether an application for a variance

5929should be approve d . See § 373.414(17), Fla. Stat. After a

5941written application (petition) is filed and reviewed , the

5949District renders a written final order stating whether an

5958exemption has been approved. In this case, a 15 - page Final

5970Order was issued on August 22, 2013. The District's written

5980approval of a variance is a "form of authorization" or a

"5991license" under chapter 373 and is therefore subject to the

6001requirements of section 120.569(2)(p). Cf. Pirtle v. Voss ,

6009Case No. 13 - 0515, 2013 Fla. ENV LEXIS 11 3 at *7 - 8 (Fla. DOAH

6026Sept. 27, 2013), adopted , OGC Case No. 12 - 1837, 2013 Fla. ENV

6039LEXIS 114 at *20 - 21 (Fla. DEP Dec. 26, 2013) (DEP's written

6052determination of exemption from permitting requirements is a

6060license subject to section 120.569(2)(p)) ; Spinrad v. Guerre ro ,

6069Case No. 13 - 2254 (Fla. DOAH Jul. 25, 2014)(same) . It is

6082concluded that Petitioners have the burden of ultimate

6090persuasion to prove that the County is not entitled to a

6101variance.

610269 . Because this is a de novo proceeding, and not merely a

6115review of th e prior agency action, the parties may present

6126additional evidence not included in the permit application and

6135other documents previously submitted to the District during the

6144permit application review process. See, e.g. , Hamilton Cnty.

6152Bd. of Cnty. Comm'rs v. State Dep't of Envtl. Reg. , 587 So. 2d

61651378, 1387 (Fla. 1st DCA 1991).

61717 0 . District rules and statutory provisions require that

6181an applicant give reasonable assurance that the conditions for

6190issuance of a permit have been met. Reasonable assurance

6199co ntemplates a substantial likelihood that the project will be

6209successfully implemented. Metro. Dade Cnty. v. Coscan Fla.,

6217Inc. , 609 So. 2d 644, 648 (Fla. 3d DCA 1992). This does not

6230require an absolute guarantee of compliance with environmental

6238standards. See, e.g. , Save Our Suwannee, Inc. v. Dep't of

6248Envtl. Prot. , Case Nos. 95 - 3899 and 95 - 3900, 1996 Fla. ENV LEXIS

626337 at *17 - 18 (Fla. DOAH Dec. 22, 1995; Fla. DEP Feb. 5, 1996).

6278Simply raising concerns or even informed speculation about what

6287might occur is not enough to carry the Petitioners' burden. See

6298Chipola Basin Prot. Grp., Inc. v. Fla. Dep't of Envtl. Reg. ,

6309Case No. 88 - 3355, 1988 Fla. ENV LEXIS 112 at *17 - 18 (Fla. DOAH

6325Nov. 14, 1988; Fla. DER Dec. 30, 1988).

63337 1 . As previously found, the County has provided

6343reasonable assurances that the proposed activity will not

6351adversely impact the value of functions provided to fish and

6361wildlife and listed species by wetlands and other surface waters

6371pursuant to rule 40C - 4.301(1)(d).

63777 2 . As previously found, the County has provided

6387reasonable assurances that the proposed activity will not cause

6396adverse secondary impacts to the water resources pursuant to

6405rule 40C - 4.301(1)(f).

64097 3 . As previously found, five of the public interest test

6421factors to be balanced were positive and two were neutral.

6431Therefore, t he County has established that the project will not

6442be contrary to the public interest, as required by rule 40C -

64544.302(1).

64557 4 . The County has established its entitlement to a

6466variance by demonstrating that withou t one, it has a hardship

6477and a particular need for the improvement to enhance public

6487safety.

64887 5 . In summary, Petitioners have failed to meet their

6499burden of proving that the permit should not be issued and a

6511variance not approved.

6514RECOMMENDATION

6515Based o n the foregoing Findings of Fact and Conclusions of

6526Law, it is

6529RECOMMENDED that the St. Johns River Water Management

6537District enter a final order granting the County's application s

6547for an ERP and a variance .

6554DONE AND ENTERED this 5th day of August , 201 4 , in

6565Tallahassee, Leon County, Florida.

6569S

6570D. R. ALEXANDER

6573Administrative Law Judge

6576Division of Administrative Hearings

6580The DeSoto Building

65831230 Apalachee Parkway

6586Tallahassee, Florida 32399 - 3060

6591(850) 488 - 9675

6595Fax Filing ( 850) 921 - 6847

6602www.doah.state.fl.us

6603Filed with the Clerk of the

6609Division of Administrative Hearings

6613this 5th day of August , 201 4 .

6621COPIES FURNISHED:

6623Hans Tanzler , III, Executive Director

6628St. Johns River Water Management District

6634Post Office Box 1429

6638Pala tka, Florida 3217 8 - 1429

6645Marcy I. LaHart , Esquire

6649Marcy I. LaHart, P.A.

66534804 Southwest 45th Street

6657Gainesville, Florida 32 608 - 4922

6663Karen C. Ferguson, Esquire

6667St. Johns River Water Management District

6673Post Office Box 1429

6677Palatka , Florida 3217 8 - 1429

6683William K. DeBraal, Esquire

6687Indian River County Attorney's Office

66921801 27th Street

6695Vero Beach, Florida 32960 - 3388

6701NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

6707All parties have the right to submit written exceptions within 15

6718days of the date of this Recommende d Order. Any exceptions to

6730this Recommended Order should be filed with the agency that will

6741render a final order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 08/27/2014
Proceedings: Agency Final Order filed.
PDF:
Date: 08/22/2014
Proceedings: Agency Final Order
PDF:
Date: 08/05/2014
Proceedings: Recommended Order
PDF:
Date: 08/05/2014
Proceedings: Recommended Order (hearing held June 4 through 6, 2014). CASE CLOSED.
PDF:
Date: 08/05/2014
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 07/21/2014
Proceedings: Respondent St. Johns River Water Management District's Objection to Petitioner's Request to Supplement the Record filed.
PDF:
Date: 07/21/2014
Proceedings: Indian River County's Response and Objection to Petitioner's Request to Supplement the Record filed.
PDF:
Date: 07/16/2014
Proceedings: Petitioners' Response to Respondents' Motion to Strike Portions of Petitioners' Proposed Order filed.
PDF:
Date: 07/09/2014
Proceedings: Respondents' Motion to Strike Portions of Petitioners' Proposed Recommended Order filed.
PDF:
Date: 07/03/2014
Proceedings: Proposed Recommended Order of the St. Johns River Water Management District filed.
PDF:
Date: 07/03/2014
Proceedings: (Indian River County, Florida's) Proposed Recommended Order filed.
PDF:
Date: 07/03/2014
Proceedings: Petitioners' Notice of Filing Proposed Recommended Order filed.
Date: 06/23/2014
Proceedings: Transcript of Proceedings Volume I - V (not available for viewing) filed.
PDF:
Date: 06/10/2014
Proceedings: Letter to Judge Alexander from William DeBraal regarding enclosed exhibits (not available for viewing) filed.
PDF:
Date: 06/04/2014
Proceedings: Letter to Judge Alexander from Jane Olsen regarding Oslo Ramp Improvements filed.
PDF:
Date: 06/04/2014
Proceedings: Letter to Judge Alexander from Larry Close regarding Oslo Boat Ramp Improvements filed.
Date: 06/04/2014
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 05/30/2014
Proceedings: Joint Pre-hearing Stipulation filed.
PDF:
Date: 05/27/2014
Proceedings: Indian River County's Unopposed Second Amended Witness List and Exhibit List filed.
PDF:
Date: 05/06/2014
Proceedings: Notice of Hearing (hearing set for June 4 through 6, 2014; 9:00 a.m.; Vero Beach, FL).
PDF:
Date: 05/02/2014
Proceedings: Order Granting Motion for Continuance.
PDF:
Date: 05/01/2014
Proceedings: Petitioners' Unnopposed Motion for Continuance and Extension of Time to File Pre-hearing Stipulation filed.
PDF:
Date: 04/30/2014
Proceedings: Order Granting Request for Official Recognition.
PDF:
Date: 04/29/2014
Proceedings: Indian River County's Amended Witness List and (Proposed) Exhibit List filed.
PDF:
Date: 04/29/2014
Proceedings: (Respondent's) Motion for Official Recognition filed.
PDF:
Date: 04/25/2014
Proceedings: Notice of Transcription filed.
PDF:
Date: 04/22/2014
Proceedings: St. John's River Water Management District's Amended Witness and (Proposed) Exhibit List filed.
PDF:
Date: 04/22/2014
Proceedings: St. John's River Water Management District's Witness and (Proposed) Exhibit List filed.
PDF:
Date: 04/17/2014
Proceedings: Indian River County's Witness List and (Proposed) Exhibit List filed.
PDF:
Date: 04/11/2014
Proceedings: Respondent, St. Johns River Water Management District's Amended Notice of Taking Deposition of Patrick Rose filed.
PDF:
Date: 04/09/2014
Proceedings: Amended Notice of Hearing (hearing set for May 6 through 8, 2014; 9:00 a.m.; Vero Beach, FL; amended as to hearing room location).
PDF:
Date: 04/08/2014
Proceedings: Respondent, St. Johns River Water Management District's Notice of Taking Deposition of Patrick Rose filed.
PDF:
Date: 04/04/2014
Proceedings: Respondent, St. Johns River Water Management District's Notice of Taking Deposition of Lange Sykes filed.
PDF:
Date: 02/03/2014
Proceedings: Indian River County's Response to Petitioners Baker and Cox's First Request for Production filed.
PDF:
Date: 01/28/2014
Proceedings: St. Johns River Water Management District's Response to Petitioners Baker and Cox's First Requests for Production filed.
PDF:
Date: 01/28/2014
Proceedings: St. Johns River Water Management District's Notice of Service of Answers and Objections to Petitioner Dr. David Cox's First Set of Interrogatories filed.
PDF:
Date: 01/22/2014
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for May 6 through 8, 2014; 9:00 a.m.; Vero Beach, FL).
PDF:
Date: 01/22/2014
Proceedings: Indian River County's Unopposed Motion for Continuance filed.
PDF:
Date: 01/21/2014
Proceedings: Order Granting Motion to Amend.
PDF:
Date: 01/21/2014
Proceedings: (Petitioners') First Amended Petition for Administrative Hearing filed.
PDF:
Date: 01/21/2014
Proceedings: Petitioners' Unopposed Motion for Leave to File First Amended Petition filed.
PDF:
Date: 01/13/2014
Proceedings: Amended Notice of Hearing (hearing set for February 4 through 6, 2014; 9:00 a.m.; Vero Beach, FL; amended as to hearing room location).
PDF:
Date: 01/07/2014
Proceedings: Notice of Appearance (Gail Hankinson) filed.
PDF:
Date: 01/06/2014
Proceedings: Respondent St. Johns River Water Management District's Cross-notice of Taking Deposition Duces Tecum of Leonard Nero filed.
PDF:
Date: 01/06/2014
Proceedings: Respondent's Notice of Taking Deposition (of Leronard Nero) filed.
PDF:
Date: 01/03/2014
Proceedings: Respondent St. Johns River Water Management District's Cross-notice of Taking Deposition Duces Tecum of Dr. David Cox and Dr. Grant Gilmore filed.
PDF:
Date: 01/03/2014
Proceedings: Repondent's Notice of Taking Deposition (of Grant Gilmore) filed.
PDF:
Date: 01/03/2014
Proceedings: Respendent's Notice of Taking Deposition (of David Cox) filed.
PDF:
Date: 12/26/2013
Proceedings: Petitiner Dr. David Cox's Notice of Serving of Interrogatories Upon Respondent St. Johns River Water Management District filed.
PDF:
Date: 12/06/2013
Proceedings: Notice of Unavailability filed.
PDF:
Date: 12/02/2013
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for February 4 through 6, 2014; 9:00 a.m.; Vero Beach, FL).
PDF:
Date: 11/26/2013
Proceedings: Motion for Continuance filed.
PDF:
Date: 11/07/2013
Proceedings: Notice of Aerving Pelican Island Audubon Society, Dr. David Cox and Dr. Robert Baker's Answers to St. Johns River Water Management District's Interrogatories filed.
PDF:
Date: 11/07/2013
Proceedings: Notice of Serving Pelican Island Audubon Society's Answers to Indian River County's Interrogatories filed.
PDF:
Date: 11/07/2013
Proceedings: Notice of Serving Dr. Richard Baker's Answers to Indian River County's Interrogatories filed.
PDF:
Date: 11/07/2013
Proceedings: Notice of Serving Dr. David Cox's Answers to Indian River County's Interrogatories filed.
PDF:
Date: 10/04/2013
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 10/04/2013
Proceedings: Notice of Hearing (hearing set for January 8 through 10, 2014; 9:00 a.m.; Vero Beach, FL).
PDF:
Date: 09/27/2013
Proceedings: Respondent St. Johns River Water Management District's Notice of Service of First Set of Interrogatories on Petitioner Pelican Island Audubon Society filed.
PDF:
Date: 09/27/2013
Proceedings: Respondent St. Johns River Water Management District's Notice of Service of First Set of Interrogatories on Petitioner Dr. David Cox filed.
PDF:
Date: 09/27/2013
Proceedings: Respondent St. Johns River Water Management District's Notice of Service of First Set of Interrogatories on Petitioner Dr. Richard Baker filed.
PDF:
Date: 09/27/2013
Proceedings: Co-Respondent Indian River County's Notice of Service of First Set of Interrogatories on Co-Petitioner Dr. David Cox filed.
PDF:
Date: 09/27/2013
Proceedings: Co-Respondent Indian River County's Notice of Service of First Set of Interrogatories on Co-Petitioner Dr. Richard Baker filed.
PDF:
Date: 09/27/2013
Proceedings: Co-Respondent Indian River County's Notice of Service of First Set of Interrogatories on Co-Petitioner Pelican Island Audubon Society filed.
PDF:
Date: 09/27/2013
Proceedings: Notice of Appearance (Kate Cotner) filed.
PDF:
Date: 09/24/2013
Proceedings: Joint Response to Initial Order filed.
PDF:
Date: 09/20/2013
Proceedings: Notice of Appearance (William DeBraal) filed.
PDF:
Date: 09/20/2013
Proceedings: Notice of Appearance (Kate Cotner) filed.
PDF:
Date: 09/17/2013
Proceedings: Initial Order.
PDF:
Date: 09/16/2013
Proceedings: Final Order Granting Variance filed.
PDF:
Date: 09/16/2013
Proceedings: Third Amended Petition for Variance filed.
PDF:
Date: 09/16/2013
Proceedings: Individual Environmental Resource Permit Technical Staff Report filed.
PDF:
Date: 09/16/2013
Proceedings: Petition for Administrative Hearing filed.
PDF:
Date: 09/16/2013
Proceedings: Notice of Referral filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
09/16/2013
Date Assignment:
09/17/2013
Last Docket Entry:
08/27/2014
Location:
Vero Beach, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
 

Counsels

Related Florida Statute(s) (3):