13-003601
Pelican Island Audubon Society, Dr. Richard Baker, And Dr. David Cox vs.
Indian River County And St. Johns River Water Management District
Status: Closed
Recommended Order on Tuesday, August 5, 2014.
Recommended Order on Tuesday, August 5, 2014.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8PELICAN ISLAND AUDUBON SOCIETY,
12DR. RICHARD BAKER, AND DR. DAVID
18COX,
19Petitioners,
20vs. Case No. 13 - 3601
26INDIAN RIVER COUNTY AND ST.
31JOHNS RIVER WATER MANAGEMENT
35DISTRICT,
36Respondents.
37___________________ ____________/
39RECOMMENDED ORDER
41T his matter was heard before the Division of Administrative
51Hearings (DOAH) by its assigned Administrative Law Judge, D . R.
62Alexander, on June 4 - 6 , 2014, in Vero Beach, Florida.
73APPEARANCES
74For Petitioner s: Marcy I. LaHart , Esquire
81Marcy I. LaHart, P.A.
854804 Southwest 45th Street
89Gainesville, Florida 32608 - 4922
94For Respondent: Gail L. Hankinson , Esquire
100(District) Karen C. Ferguson, Esquire
105St. Johns River Water Management District
111Post Office Box 1429
115Palatka , Florida 3217 8 - 1429
121For Respondent: William K. DeBraal, Esquire
127(County ) Kate P. Cotner, Esquire
133Indian River County Attorney's Office
1381801 27th Street
141Vero Beach, Florida 32960 - 3388
147STATEMENT OF THE ISSUE S
152The issue s are (1) whether the St. John s River Water
164Management District (District) should approve the application of
172Indian River County (County) for an environmental resource
180permit (ERP) authorizing the construction and operation of a
189surface water management system with stormwater treatment for
197the Oslo Road Boat Ramp Parking Lot ; and (2) whether t he
209District should approve the County's request for a variance from
219Florida Administrative Code Rule 40C - 4.302(1)(c) and sections
22810.1.1(c), 12.1.1(d), and 12.2.5(c) of the Applicant's Handbook:
236M anagement and Storage of Surface Waters (AH) in order to
247perform other related work .
252PRELIMINARY STATEMENT
254On August 16 , 2013, the District published notice that it
264intended to issue an ERP authorizing the County to construct a
275surface water management s ystem adjacent to the Indian River
285Lagoon (Lagoon) . On August 23, 2013, a Final Order was issued
297approving the County's request for a variance in order to
307conduct certain related work on the project. Pet itioners timely
317requested a hearing to contest thos e agency actions, and the
328matter was referred to DOAH to conduct a hearing. Petitioners
338were later authorized to file a First Amended Petition (Amended
348Petition).
349At the final hearing, Petitioners jointly presented the
357testimony of five witnesses; Petiti oners Exhibits 1 - 4, 8, 12,
36915, 18, 28, 33, 37, and 42 were received in evidence. The
381County presented the testimony of three witnesses; County
389Exhibits 1 - 5 5 were received in evidence. The District presented
401the testimony of five witnesses; District Exhib its 1 - 3, 5, 6,
41416, 20, 32, 34, 37, 38, 41, 42, 47, 48, 52, 56 - 58, 61, 61A, 62,
43163, 63A, 64, 67, 69, 72 - 75, 77, and 78 were accepted in
445evidence. Petitioners' Request to Supplement the Record with
453additional exhibits , filed after Proposed Recommended Order s
461(PROs) were submitted, is denied . All proposed findings in
471their PRO that are based on the excluded exhibits have been
482disregarded. Finally, the undersigned took official recognition
489of chapters 40C - 4 and 40C - 42, in e ffect when the proposed agency
505acti on was issued; the Applicant's Handbook: Management and
514Storage of Surface Waters (Dec. 27, 2010); Applicant's Handbook:
523Regulation of Stormwater Management Systems (Dec. 27, 2010); and
532rule 62 - 302.700 .
537A f ive - volume Transcript of the hearing has been pr epared.
550Proposed Recommended Orders were filed by the parties , and they
560have been considered in the preparation of this Recommended
569Order.
570FINDINGS OF FACT
573A . The Parties
5771. The Pelican Island Audubon Society is a Florida non -
588profit corporation whos e mission is to preserve and protect the
599animals, plants, and natural communities in the County through
608advocacy, education, and public awareness. It has more than
61725 members that live in the County and has been a chapter of the
631Audubon Society of Flori da since 1964.
6382. Dr. Richard Baker resides in the County and engages in
649water - based recreational activities such as canoeing, bird
658watching, nature photography, and fishing in the Lagoon near the
668b oat r amp.
6723. Dr. David Cox resides in the County and engages in
683water - based activities such as kayaking and nature observation
693in the vicinity of the b oat r amp .
7034. The County is the applicant for an ERP and variance for
715a project known as the Oslo Road Boat Ramp project .
7265. The District is the agency cha rged with the
736responsibility of regulating water resources within its
743geographic boundaries and to administer and enforce chapter 373 ,
752Florida Statutes, and the rules promulgated under title 40C.
761B. The Existing Oslo Road , Boat Ramp , and Lagoon
7706. Oslo R oad is a County - owned road that runs in an east -
786west direction and intersects with U.S. Highway 1 just south of
797State Road 60 . To the east of U.S. Highway 1 , the road is paved
812for a short distance ; the remain ing portion of the road ( 2,460
826feet ) is a narro w, two - lane dirt road that dead - ends at the bo at
845r amp.
8477. Most of the dirt road is bordered to the north and
859south by a mangrove swamp that extends to the edges of the road.
872All wetlands have been previously disturbed. The surrounding
880and abutting jur isdictional wetlands consist primarily of both
889tidal (north side) and impounded/partially tidal mangrove swamp
897(south side), which was created years ago by a mosquito control
908district in order to reduce the salt marsh mosquito population.
918The boat ramp is bordered to the north by a clump of red
931mangroves and a sparsely vegetated sandy shoreline and to the
941south by a dense mangrove fringe.
9478 . During rain events, the dirt and sediment can wash off
959the road as erosion. Th is requires the County to continua lly
971maintain the dirt road by grading and adding marl material to
982bring it back up to grade.
9889 . The b oat r amp has been in existence for more than
100250 years and is the nearest public access to the popular South
1014County fishing areas in the Lagoon. Alt hough there are 1 7 other
1027boat ramps in the County, t he closest one is six miles to the
1041north in the City of Vero Beach. The typical users of the b oat
1055r amp are fishermen with shallow - draft boats , while the open
1067shoreline to the north is normally used to la unch canoes and
1079kayaks and to access the river by wading fishermen. There are
1090a number of water - based communities in the area, including one
1102directly to the east of the boat ramp. Many boats that do not
1115launch at the boat ramp use the nearby seagrass be ds as a
1128fishing destination.
113010 . The b oat r amp has a dirt cul - de - sac , a concrete boat
1148ramp with finger piers , and is surrounded by the Lagoon , the
1159receiving water body for the project and classified as Class III
1170waters . In December 2007, the Department o f Environmental
1180Protection (DEP) verified that the Lagoon is an Impaired Water
1190Body of the State, with the impairment being for nutrients in
1201the vicinity of the project.
12061 1 . Currently , there are no designated parking areas
1216associated with the b oat r amp . Vehicles both with and without
1229trailers park in the cul - de - sac and along the roadside. The
1243only limit to the extent of parking along Oslo Road is the
1255distance somebody is willing to walk. During peak times, the
1265dirt road and cul - de - sac become congeste d and blocked with cars,
1280trucks, and boat trailers.
12841 2 . In 1977, the County obtained a permit from the United
1297States Army Corps of Engineers (USACE) to construct the b oat
1308r amp with two appurtenant piers and a riprap groin . During the
1321subsequent years, t h ere was substantial deterioration to the
1331ramp, bulkhead, and docks . Accordingly , i n 2009, using an
1342exemption under rule 40C - 4.051(12)(i), the County rep laced the
1353concrete portion of the b oat r amp within the same footprint and
1366constructed two accessory doc ks that now define the width of the
1378one - lane boat ramp. During this process, the County removed
1389around 25 cubic yards of muck from the base of the boat ramp.
14021 3 . The b oat r amp is only 16 feet wide and 40 feet in
1419length and is located in water less than t hree feet below Mean
1432Low Water (MLW). In contrast, a typical boat ramp in the County
1444is around 76 feet, or twice a s long as the Oslo Road boat ramp.
14591 4 . The existing boat ramp was designed to be used by
1472motorized vessels. There is a separate launch area for kayak
1482and canoes next to the concrete ramp. T he motorized vessels
1493that currently use the boat ramp are small with a draft less
1505than 18 inches. This is partly due to the presence of cap rock
1518beyond the proposed dredging area, which limits the draft s ize
1529of the boats, and the small size of the single - lane ramp.
15421 5 . The only signage at the ramp advises the public that
1555this is a shallow draft vessel launch and that the limits of the
1568draft are 18 inches.
15721 6 . The channel leading out of the boat ramp wa s
1585previously dredged around 1950. During that era, only shallow
1594draft boats would launch at Oslo Road. In February 1977 , the
1605United States Fish and Wildlife Service confirmed that an old
1615channel about 75 feet long and 15 feet wide existed at the boat
1628ram p location. In May 1977, a dditional maintenance dredging of
1639the old silted channel to a depth of - 3.00 Mean Sea Level (MSL)
1653was authorized by the USACE. Although the parties disagree over
1663whether any dredging was ever performed , surveys , aerial
1671photograp hs, and research suggest that more than likely the
1681project site was dredged in the late 1970s or early 1980s . A
1694portion of the area that the County proposes to dredge falls
1705within the area that was previously permitted by the USACE in
17161977.
17171 7 . The dista nce from the boat ramp to the Intracoastal
1730Waterway (ICW) is approximately one - half mile . The channel is
1742delineated by a number of poly vinyl chloride pipes and six sets
1754of permitted navigational channel markers leading to the ICW.
1763The water depths in th e area surrounding the boat ramp,
1774including the channel to the ICW, are very shallow.
17831 8 . Drainage from the road currently runs down the ramp
1795c ausing sand and other material to build up in the ramp area.
1808Due primarily to this drainage, a t low tide the wa ter at the
1822boat ramp area has been so shallow that boaters have experienced
1833great d ifficulty when loading ; in some cases, launching or
1843retrieving a vessel is almost impossible. After a rain event,
1853turbidity plumes in the Lagoon have been observed extendin g
1863100 feet to the north of Oslo Road, 150 feet to the south, and
1877approximately 30 feet to the east.
18831 9 . The seagrass beds adjacent to the boat ramp were
1895described as lush, healthy, and productive . The proposed
1904dredging area contains less than 1.5 per cent of seagrass
1914coverage. There is no evidence that the current use of the boat
1926ramp causes prop scarring to the surrounding seagrass.
193420 . The Lagoon in the vicinity of the boat ramp has been
1947determined to be a high manatee use area, as defined by the
1959C ounty Manatee Protection Plan (MPP). However, this area is not
1970a h igh w atercraft - related m anatee m ortality area. Since 2002,
1984the waterway in the vicinity of the project site has been
1995regulated by seasonal manatee protection speed zones. Signs
2003have been posted since 2003. The shoreline to the ICW is
2014currently regulated at s low s peed between November 1 and April
202630 and is unregulated the remainder of the year. The County
2037intends , however, to adopt a new ordinance that makes the slow
2048speed zone effective the entire year, rather than just during
2058the winter months.
2061C. The Project and Variance
20662 1 . In late 2009, the County submitted to the District its
2079ERP application . Since that time, the County has modified its
2090plans seven times and amended the applicatio n tw ice . Notably,
2102t he modifications reduce the direct impacts to wetlands from
21122.98 acres to 1.41 acres for the improvement of the dirt road
2124and parking lot ; they also reduce impacts to ditches that
2134support fisheries habitat and submerged lands. They wil l result
2144in 0.113 acres of combined direct impacts to seagrass and Lagoon
2155substrate from the proposed dredging. The project will not
2164change the hydroperiod of the surrounding wetlands. The number
2173of trailer parking spaces was reduced from 32 to 12 and th e
2186parking space angle changed . A dry retention area on the west
2198side of the project will be installed; a wet detention pond was
2210eliminated ; the dock extension reduced; and at Petitioners'
2218request, the project was shifted north to avoid impacting a
2228ditch t o the south .
22342 2 . The County eliminated and reduced impacts to surface
2245waters by reducing the width of the proposed dredge area so as
2257to not impact seagrass beds to the north and south of the
2269channel . Dredging is limited to a depth of - 2.5 feet MLW and
2283wi ll be within the same area that was dredged in the 1950s. It
2297is not expected to contribute to larger vessels launching at the
2308boat ramp.
23102 3 . The latest iteration of the project consists of
2321paving the 2,460 feet of dirt road to a width of 26 feet ,
2335constr ucting a surface water management system, and constructing
2344a parking area to accommodate 12 vehicles with boat trailers and
235511 vehicles without a trailer. No changes to the size or
2366configuration of the concrete boat ramp will be made.
23752 4 . The project w ill extend the northern accessory dock of
2388the existing one - lane boat ramp by approximately 3 2 feet to
2401allow more boats to tie off ; dredge 4,943 square feet (0.113
2413acres) of the ingress/egress access way within the Lagoon to a
2424depth of - 2.5 MLW; install an additional three sets of channel
2436markers (six in total); install "No Parking" signs to limit
2446vehicle parking to the designated parking area; and install
2455additional signage to warn boaters of the shallow depths in the
2466area and to notify boaters that to laun ch at this boat ramp,
2479vessel drafts must not exceed 18 inches.
24862 5 . The proposed surface water management system consists
2496of roadside conveyance swales, pipes, weirs, and two dry
2505retention areas which will provide water quality treatment for
2514stormwater run off from basins upstream of the project area and
2525the existing paved portion of Oslo Road. The two proposed dry
2536retention areas will provide water quality treatment in
2544accordance with the design and performance criteria in the
2553District's rules. Currently, these areas drain into existing
2561swales and then east in to the Lagoon with no water quality
2573treatment. The system will result in a net improvement to water
2584quality based on a nutrient loading analysis review by the
2594District.
25952 6 . The County is proposing o ff - site mitigation to offset
2609the direct and secondary impacts. It consists of 18 acres of
2620enhancement at Earman Island within the Lost Tree Island s
2630Conservation Area , including 14 acres of wetland enhancement.
2638Earman Island is part of the chain of island s in the Lagoon just
2652north of State Road 60 known as Lost Tree Island s purchased by
2665the County for conservation purposes. The proposed enhancement
2673area is building upon an existing mitigation area on the north
2684end of the island. The proposed mitigation i s within the same
2696drainage basin as the area of wetlands and other surface waters
2707to be adversely affected. There are no cumulative impacts
2716associated with the project.
27202 7 . The County owns all of the property that will be
2733dredged, filled, or paved, incl uding the submerged lands
2742waterward of the Mean High Water ( MHW ) line at the boat ramp out
2757approximately 215 feet. This area is not within an Aquatic
2767Preserve or Outstanding Florida Waters , and none of the dredging
2777will occur on sovereign submerged lands. See Jt. Pre - hearing
2788Stip., p. 13, ¶¶ 18 - 20.
27952 8 . In summary, t he purpose of the project is seven - fold:
2810provide water quality treatment for the runoff water; limit the
2820number of parking spaces available for users of the boat ramp;
2831decrease the need for the County to maintain the 2,460 feet of
2844dirt road; create a safe place for boaters to moor while waiting
2856to retrieve their boats from the Lagoon; allow boaters to safely
2867launch and retrieve their boats from the Lagoon at low tide;
2878create a clear channel for boaters to get from the base of the
2891boat ramp to the ICW; and decrease turbidity in and around the
2903mouth of the boat ramp.
29082 9 . The portion of the project that expands the accessory
2920dock and dredges the channel will be located in Class III waters
2932class ified by DEP as restricted for shellfish harvesting.
294130 . Rule 40C - 4.302(1)(c) places additional requirements on
2951regulated activities that are proposed in Class III waters
2960r estricted for shellfish harvesting. These requirements are set
2969forth in the AH. Without a variance from the rule and AH , the
2982District would be required to deny the ERP . Therefore, the
2993County must qualify for and obtain a variance from rule 40C -
30054.302(1)(c) and AH sections 10.1.1(c), 12.1.1(d), and 12.2.5(c) .
3014D . Petitioners' Concerns
30183 1 . The essence of Petitioners' objections is that once
3029Oslo Road and the parking lot are paved, and the channel
3040dredged, the boat ramp will attract a tremendous number of
3050fishermen from throughout the area who will use l arger and
3061deeper draft boats to a ccess the Lagoon . Petitioners contend
3072that more and larger boa ts , along with the proposed activities,
3083will result in the environmental impacts described in their
3092Amended Petition.
30943 2 . The conditions for issuance of an ERP are set forth in
3108rules 40C - 4.30 1 and 40C - 4.302. The standards and criteria in
3122the AH are used to determine whether an applicant has met the
3134conditions for issuance in the two rules. Rule 40C - 1.1002
3145establishes the requirements for obtaining a variance.
31523 3 . The parties have stipulat ed that the project either
3164complies with the following conditions for issuance of a permit
3174or that they are not applicable: rules 40C - 4.301(1)(a), (b),
3185(c), (e), (g), (h), (i), (j), and (k); and 40C - 4.302(1)(a)3.,
31975., and 6.
32003 4 . R emaining at issue is w hether reasonable assurance has
3213been provided to demonstrate that the proposed activities will
3222not adversely impact the value of functions provided to fish and
3233wildlife and listed species by wetlands and other surface waters
3243(40C - 4.301(1)(d)); that the pro posed activities will not cause
3254adverse secondary impacts (40C - 4.301(1)(f)); and that the
3263portion of the project located in wetlands or the Lagoon is not
3275contrary to the public interest (r ules 40C - 4.302(1)(a)1., 2.,
32864., and 7. and 40C - 4.302(1)(b) ) . As a p art of these claims,
3302Petitioners also contend that the County failed to implement all
3312practicable design modifications to reduce or eliminate the
3320adverse impacts to wetland and surface water functions ; the
3329proposed mitigation fail s to offset the adverse ef fects of the
3341project ; and the D istrict did not consider the impacts of
3352increased boat usage when reviewing secondary impacts generated
3360by the project . Finally, Petitioners contend that the County
3370has not shown that it meets the conditions in rule 40C - 1.10 02
3384for a variance. These contentions are addressed separately
3392below.
3393a. Rule 40C - 4.301(1)(d)
33983 5 . Pursuant to th is rule , and related AH provisions , the
3411County must g ive reasonable assurance that the proposed activity
3421will not adversely impact the value of functions provided to
3431fish and wildlife and listed species by wetlands and other
3441surface waters.
34433 6 . To meet th is requirement, t he County has implemented ,
3456to the extent p racticable , design modifications to reduce or
3466eliminate adverse impacts to wetl ands and other surface waters.
3476The original application submitted in 2009 proposed impacts to
34852.98 acres of wetlands and surface waters. Since that time, the
3496County has reduced or eliminated its proposed wetland impacts by
3506more than 50 percent. This was done by incorporating design
3516modifications that eliminated the construction of a stormwater
3524pond in wetlands and add ing compensating stormwater treatment;
3533shifting impacts out of critical fisheries and open water
3542habitat within the southern impoundment to upland areas;
3550installing a retaining wall along the trailer parking area to
3560limit the fill slope impacts; and making minor modifications to
3570reduce the project footprint in several locations.
35773 7 . The County also eliminated and reduced adverse impacts
3588to surface waters by reducing the width of the proposed dredge
3599area so as to not impact the seagrass beds to the north and
3612south of the channel and limiting the dredging to - 2.5 MLW.
3624Th at depth is consistent with the existing limitations adjacent
3634to the dre dge area and will not allow deeper draft vessels to
3647use the boat ramp. The addition of a permit condition that
3658requires the placement of "No Parking" signs along Oslo Road and
3669limiting the parking of boat trailers to the 12 designated
3679parking spaces will prevent an increase in boat traffic from the
3690existing boat ramp. The installation of signage at the boat
3700ramp advising boaters of the boat motor draft restriction and
3710the year - round manatee slow speed zone will also reduce impacts.
3722Finally, three sets of channel markers will also be installed to
3733keep boaters within the designated channel. As discussed below,
3742after these design modifications are implemented, t he remaining
3751impacts are sufficiently offset by mitigation proposed by the
3760County.
376138. The Dis trict also considered the condition of the
3771wetlands and surface waters to be impacted; their hydrologic
3780connection; their uniqueness; location; and fish and wildlife
3788utilization, and then evaluated the proposed mitigation. The
3796more persuasive evidence sup ports a finding that the mitigation
3806is sufficient to offset the proposed impacts.
38133 9 . As required by the AH, t he District provided a copy of
3828the County's application to the Florida Fish and Wildlife
3837Conservation Commission (FFWCC). Among other things, th e FFWCC
3846is the agency responsible for reviewing the County's MPP. The
3856FFWCC indicated that the project is consistent with the County's
3866MPP. It also recommended certain measures to be taken by the
3877County, which are now included as conditions in the propos ed
3888permit.
388940 . Petitioners assert that t he National Marine Fisheries
3899Service , a federal agency, considers the entire Lagoon, and the
3909ditches extending into it, to be an essential fish habitat (EFH)
3920that provides habitat required for the various life cycle s of
3931many types of fish. Petitioners contend that the project wil l
3942result in impacts to the EFH adjacent to the proposed dredging
3953areas , a nd that th is type of impact can not be mitigated. For
3967the following reasons, this contention is rejected.
39744 1. F irst, the more persuasive evidence is that the area
3986to be dredged contains less than 1.5 percent seagrass coverage ,
3996and channel markers will be used to keep boaters within the
4007designated channels. Only around 200 square feet (0.005 acres)
4016of seagrass will be a ffected , and not the much larger area that
4029Petitioners assert will be impacted . N o other impacts to
4040seagrass are expected to result from the project, other than
4050those identified and mitigated for during the application
4058review. Second, the District consid ered the actual Lagoon
4067impact area and determined that the same functions now being
4077provided in that area will be provided by the proposed
4087mitigation. Third, if one accepts Petitioners' a ssertion that
4096EFH can never be mitigated, no permit could ever be is sued for
4109any project that would impact the Lagoon or any ditches
4119connecting to it. Finally, b ased on the District's Uniform
4129Mitigation Assessment Method (UMAM) evaluation, the functional
4136loss, including direct and secondary impacts, was scored at
41451.212 wh ile the functional gain was 1.281. See Fla. Admin. Code
4157Ch. 62 - 345. With 1.5 acres of direct impacts, one acre of
4170secondary impacts, and 18 acres of mitigation, there are
4179approximately 0 .07 excess units of functional mitigation. Th e
4189UMAM review was not credibly refuted.
41954 2 . Petitioners failed to prove that the requirements of
4206rule 40C - 4.301(1)(d) have not been met.
4214b. Rule 40C - 4.301(1)(f)
42194 3 . Rule 40C - 4.301 (1) (f) require s an applicant to provide
4234reasonable assurance that a regulated activity will not cause
4243adverse secondary impacts to the water resources. Petitioners
4251contend that the project will increase the number and size of
4262boats that use the boat ramp and therefore cause secondary
4272impacts to seagrasses, manatees, and water quality.
42794 4 . Secon dary impacts occur outside the direct footprint
4290of the project but are very closely linked and causally related
4301to the activity to be permitted. De minimis or remotely related
4312secondary impacts are not considered.
43174 5 . To assess secondary impacts, the Dis trict evaluates
4328the impacts to wetlands and surface water functions; upland
4337habitat for aquatic or wetland dependent species; and historical
4346and archaeological resources.
43494 6 . The project will result in 0.86 acres of secondary
4361impacts to the remaining we tlands adjacent to the road paving
4372and parking area and 0.14 acres of secondary impacts associated
4382with sloughing and boat wake - related impacts.
43904 7 . The County has proposed mitigation that will
4400adequately offset the expected secondary impacts. I n
4408combi nation with dredging to only - 2.5 MLW and reducing parking
4420space for boat trailers, the mitigation will prevent additional
4429secondary impacts. Also, the boat ramp is significantly smaller
4438than the average boat ramp in the County and is designed
4449specificall y for small vessels. Th us, th e ramp itself limits
4461the size of the vessel that can launch at the site.
44724 8 . Through the use of additional channel markers,
4482signage, and a year - round slow speed zone, there should not be
4495an increased threat of boat collisions with manatees, prop
4504scarring of seagrass beds, or turbidity. Also, the removal of
4514the muck from the channel will be beneficial and reduce
4524turbidity in the nearby waters.
452949 . Petitioners have stipulated that no wetland dependent
4538listed species on site that use uplands for nesting or denning
4549are at issue.
45525 0 . There are no additional phases for this project.
4563Speculation of a future interchange at Interstate 95 and Oslo
4573Road, located many miles to the west of the boat ramp , and any
4586impacts that might occ ur if one was ever built, was not
4598considered under the District's secondary impact rule.
46055 1 . Petitioners failed to prove that the requirements of
4616the rule have not been met.
4622c. Rule 40C - 4.302 Î Public Interest Test
46315 2 . The public interest test for this type of project
4643requires that the County provide reasonable assurance that
4651activities to be located in, on, or over wetlands and other
4662surface waters will not be contrary to the public interest, as
4673determined by balancing seven criteria in subparagraphs 1. - 7 . of
4685the rule . The test takes into account the positive, negative,
4696and neutral effects of the activity. The parties have
4705stipulated that subparagraphs 3. and 6. are not at issue. The y
4717govern navigation, shoaling, and erosion, and historical and
4725archae ological resources. The navigation factor is positive and
4734the archaeological resource factor is neutral.
47405 3 . Subparagraph 1. requires the District to determine
4750whether the activity will adversely affect the public health,
4759safety, or welfare or the proper ty of others. The more
4770persuasive evidence supports a finding that the activities will
4779not adversely affect the public health, safety, or welfare of
4789the property of others. Presently, it is difficult to launch
4799and load boats at the ramp due to the area b eing silted down.
4813This can result in serious safety issues. By d redging this
4824area , public safety will be enhanced. The installation of
4833navigational channel markers and signage will also be beneficial
4842to the public health, welfare, and safety, as will th e year -
4855round slow speed zone. This factor is positive.
48635 4 . Subparagraph 2 . r equires the District to determine
4875whether the activity will adversely affect the conservation of
4884fish and wildlife, including endangered or threatened species,
4892or their habitats. The evidence supports a finding that the
4902proposed mitigation is appropriate and more than offsets the
4911proposed impacts. The County eliminated and reduced impact s by
4921more than one - half. The proposed dredging area contains less
4932than 1.5 percent seagrass coverage . The project will not result
4943in adverse impacts to manatee. Finally, the County is proposing
495318 acres of mitigation, including the creation of an open
4963water/tidal creek feature which will provide the same functions
4972as the areas being impacted. This factor is positive.
49815 5 . Subparagraph 4. requires the District to determine
4991whether the activity will adversely affect the fishing or
5000recreational values or marine productivity in the vicinity of
5009the project. The evidence supports a finding that the 18 acres
5020of mitigation will improve marine productivity by providing a
5029substantial amount of both mangrove and salt marsh vegetation
5038along the sides of the tidal creek and open water component of
5050fisheries. Also, the County has eliminated and reduced impa cts
5060to seagrasses by limiting the dredging area to an area with less
5072than 1.5 percen t seagrass coverage. Finally, it has removed the
5083stormwater system from the southern impoundment to avoid a
5092critical fisheries open water habitat. This factor is positive .
51025 6 . Subparagraph 5. requires the District to determine
5112whether the activity will be of a temporary or permanent nature.
5123Because the mitigation offsets the adverse impacts , and the
5132mitigation and dredging areas are both permanent in nature, the
5142temporar y or permanent factor is neutral.
51495 7 . Subparagraph 7. require s an evaluation of the current
5161condition and relative value of the functions being performed by
5171areas affected by the proposed activity. The current condition
5180and relative functions being perfo rmed by the areas affected by
5191the project are high functioning. The evidence shows that the
5201project will not change this high functioning aspect of the
5211area. The District also conducted a UMAM review , which
5220considered the relative value of plant communit ies, hydrology,
5229and other factors , and demonstrate d that the mitigation more
5239than offsets the impacts. Finally, t he County established that
5249the mitigation area provides the same functions as the impact
5259areas. Therefore, this factor is positive.
52655 8 . The District's determination that the project will not
5276be contrary to the public interest is supported by a
5286preponderance of the evidence .
5291E. Variance
529359 . Because a portion of the project will be within Class
5305III waters classified by DEP as restricted for sh ellfish
5315harvesting, the County must qualify for and obtain a variance.
5325A variance may be granted when an applicant demonstrates that it
5336would suffer a hardship, not self - imposed, if the variance is
5348denied. See Fla. Admin. Code R. 40C - 1.1002. In determin ing
5360whether a variance should be approved, the District balances the
5370social, economic, and environmental impacts on the applicant,
5378the residents of the area, and on the State with those same
5390im pacts if the variance is denied.
53976 0 . The County has demonstrat ed that the application of
5409rule 40C - 4.30 2 (1)(c) and AH sections 10.1.1(c), 12.1.1(d), and
542112.2.5(c) would create a hardship in this case by precluding the
5432construction of the proposed accessory dock extension and the
5441dredging of an existing ingress/egress way within the Lagoon
5450that will improve public safety and enhance recreational
5458opportunities for the citizens of the area. There are no viable
5469alternatives that would address the functionality and safety of
5478the existing boat ramp.
54826 1 . The hardship is not self - imposed in that the normal
5496processes of erosion, wind, and tides contribute to the
5505accumulation of sand and muck within the ingress/egress access
5514way, which over time has impeded the process of launching and
5525loading vessels at the boat ramp. The nar row channel is
5536bordered on the north and south by productive seagrass beds.
5546The extension of the accessory dock and dredging of the access
5557channel will expedite the loading process and reduce the need
5567for boat operators to circle in the shallow waters wai ting their
5579turn to access the ramp.
55846 2 . The environmental impact of the project is positive.
5595There will be no harm to the water quality of Class III waters
5608and the shellfish beds. The Department of Agriculture and
5617Consumer Affairs reviewed the project a nd concluded that it
5627would not result in a reclassification of shellfish harvesting
5636waters. The stormwater treatment on the uplands will result in
5646a reduction of nutrient loading to the Lagoon, which is now
5657designated by DEP as impaired by nutrients. The extension of
5667the accessory dock, along with making the area a year - round slow
5680speed zone , will reduce potential impacts to manatees.
56886 3 . The dredging and extension of the dock will be a
5701convenience to the boating public and may enhance public safety
5711dur ing periods of inclement weather or other exigent
5720circumstances.
57216 4 . Petitioners failed to prove that all requirements for
5732a variance have not been met.
5738CONCLUSION S OF LAW
57426 5 . The parties have stipulated to the facts necessary to
5754establish that Petitio ners have standing to contest the permit
5764and variance.
57666 6 . The parties agree that the District's rules in effect
5778on August 23, 2013, contain the criteria applicable to the
5788permit that is the subject of this proceeding.
57966 7 . Section 120.569(2)(p) , Florida Statutes (2013), is
5805applicable to this case. It establishes the order of
5814presentation and burden of proof in a permit challenge case
5824under chapter 373. Because Petitioners have challenged a permit
5833issued under chapter 373, they have the "burden of ultima te
5844persuasion and the burden of going forward to prove the case in
5856opposition to the [permit] by competent and substantial
5864evidence." Id.
58666 8 . There are no reported cases that address the issue of
5879whether section 120.569(2)(p) applies to a person chall enging
5888the approval of a variance. The issue was not directly
5898addressed by the parties in the ir Joint Pre - hearing Stipulation
5910or PROs. The District defers to the criteria in section
5920403.201(1) to determine whether an application for a variance
5929should be approve d . See § 373.414(17), Fla. Stat. After a
5941written application (petition) is filed and reviewed , the
5949District renders a written final order stating whether an
5958exemption has been approved. In this case, a 15 - page Final
5970Order was issued on August 22, 2013. The District's written
5980approval of a variance is a "form of authorization" or a
"5991license" under chapter 373 and is therefore subject to the
6001requirements of section 120.569(2)(p). Cf. Pirtle v. Voss ,
6009Case No. 13 - 0515, 2013 Fla. ENV LEXIS 11 3 at *7 - 8 (Fla. DOAH
6026Sept. 27, 2013), adopted , OGC Case No. 12 - 1837, 2013 Fla. ENV
6039LEXIS 114 at *20 - 21 (Fla. DEP Dec. 26, 2013) (DEP's written
6052determination of exemption from permitting requirements is a
6060license subject to section 120.569(2)(p)) ; Spinrad v. Guerre ro ,
6069Case No. 13 - 2254 (Fla. DOAH Jul. 25, 2014)(same) . It is
6082concluded that Petitioners have the burden of ultimate
6090persuasion to prove that the County is not entitled to a
6101variance.
610269 . Because this is a de novo proceeding, and not merely a
6115review of th e prior agency action, the parties may present
6126additional evidence not included in the permit application and
6135other documents previously submitted to the District during the
6144permit application review process. See, e.g. , Hamilton Cnty.
6152Bd. of Cnty. Comm'rs v. State Dep't of Envtl. Reg. , 587 So. 2d
61651378, 1387 (Fla. 1st DCA 1991).
61717 0 . District rules and statutory provisions require that
6181an applicant give reasonable assurance that the conditions for
6190issuance of a permit have been met. Reasonable assurance
6199co ntemplates a substantial likelihood that the project will be
6209successfully implemented. Metro. Dade Cnty. v. Coscan Fla.,
6217Inc. , 609 So. 2d 644, 648 (Fla. 3d DCA 1992). This does not
6230require an absolute guarantee of compliance with environmental
6238standards. See, e.g. , Save Our Suwannee, Inc. v. Dep't of
6248Envtl. Prot. , Case Nos. 95 - 3899 and 95 - 3900, 1996 Fla. ENV LEXIS
626337 at *17 - 18 (Fla. DOAH Dec. 22, 1995; Fla. DEP Feb. 5, 1996).
6278Simply raising concerns or even informed speculation about what
6287might occur is not enough to carry the Petitioners' burden. See
6298Chipola Basin Prot. Grp., Inc. v. Fla. Dep't of Envtl. Reg. ,
6309Case No. 88 - 3355, 1988 Fla. ENV LEXIS 112 at *17 - 18 (Fla. DOAH
6325Nov. 14, 1988; Fla. DER Dec. 30, 1988).
63337 1 . As previously found, the County has provided
6343reasonable assurances that the proposed activity will not
6351adversely impact the value of functions provided to fish and
6361wildlife and listed species by wetlands and other surface waters
6371pursuant to rule 40C - 4.301(1)(d).
63777 2 . As previously found, the County has provided
6387reasonable assurances that the proposed activity will not cause
6396adverse secondary impacts to the water resources pursuant to
6405rule 40C - 4.301(1)(f).
64097 3 . As previously found, five of the public interest test
6421factors to be balanced were positive and two were neutral.
6431Therefore, t he County has established that the project will not
6442be contrary to the public interest, as required by rule 40C -
64544.302(1).
64557 4 . The County has established its entitlement to a
6466variance by demonstrating that withou t one, it has a hardship
6477and a particular need for the improvement to enhance public
6487safety.
64887 5 . In summary, Petitioners have failed to meet their
6499burden of proving that the permit should not be issued and a
6511variance not approved.
6514RECOMMENDATION
6515Based o n the foregoing Findings of Fact and Conclusions of
6526Law, it is
6529RECOMMENDED that the St. Johns River Water Management
6537District enter a final order granting the County's application s
6547for an ERP and a variance .
6554DONE AND ENTERED this 5th day of August , 201 4 , in
6565Tallahassee, Leon County, Florida.
6569S
6570D. R. ALEXANDER
6573Administrative Law Judge
6576Division of Administrative Hearings
6580The DeSoto Building
65831230 Apalachee Parkway
6586Tallahassee, Florida 32399 - 3060
6591(850) 488 - 9675
6595Fax Filing ( 850) 921 - 6847
6602www.doah.state.fl.us
6603Filed with the Clerk of the
6609Division of Administrative Hearings
6613this 5th day of August , 201 4 .
6621COPIES FURNISHED:
6623Hans Tanzler , III, Executive Director
6628St. Johns River Water Management District
6634Post Office Box 1429
6638Pala tka, Florida 3217 8 - 1429
6645Marcy I. LaHart , Esquire
6649Marcy I. LaHart, P.A.
66534804 Southwest 45th Street
6657Gainesville, Florida 32 608 - 4922
6663Karen C. Ferguson, Esquire
6667St. Johns River Water Management District
6673Post Office Box 1429
6677Palatka , Florida 3217 8 - 1429
6683William K. DeBraal, Esquire
6687Indian River County Attorney's Office
66921801 27th Street
6695Vero Beach, Florida 32960 - 3388
6701NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
6707All parties have the right to submit written exceptions within 15
6718days of the date of this Recommende d Order. Any exceptions to
6730this Recommended Order should be filed with the agency that will
6741render a final order in this matter.
- Date
- Proceedings
- PDF:
- Date: 08/05/2014
- Proceedings: Recommended Order (hearing held June 4 through 6, 2014). CASE CLOSED.
- PDF:
- Date: 08/05/2014
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 07/21/2014
- Proceedings: Respondent St. Johns River Water Management District's Objection to Petitioner's Request to Supplement the Record filed.
- PDF:
- Date: 07/21/2014
- Proceedings: Indian River County's Response and Objection to Petitioner's Request to Supplement the Record filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Petitioners' Response to Respondents' Motion to Strike Portions of Petitioners' Proposed Order filed.
- PDF:
- Date: 07/09/2014
- Proceedings: Respondents' Motion to Strike Portions of Petitioners' Proposed Recommended Order filed.
- PDF:
- Date: 07/03/2014
- Proceedings: Proposed Recommended Order of the St. Johns River Water Management District filed.
- PDF:
- Date: 07/03/2014
- Proceedings: (Indian River County, Florida's) Proposed Recommended Order filed.
- Date: 06/23/2014
- Proceedings: Transcript of Proceedings Volume I - V (not available for viewing) filed.
- PDF:
- Date: 06/10/2014
- Proceedings: Letter to Judge Alexander from William DeBraal regarding enclosed exhibits (not available for viewing) filed.
- PDF:
- Date: 06/04/2014
- Proceedings: Letter to Judge Alexander from Jane Olsen regarding Oslo Ramp Improvements filed.
- PDF:
- Date: 06/04/2014
- Proceedings: Letter to Judge Alexander from Larry Close regarding Oslo Boat Ramp Improvements filed.
- Date: 06/04/2014
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 05/27/2014
- Proceedings: Indian River County's Unopposed Second Amended Witness List and Exhibit List filed.
- PDF:
- Date: 05/06/2014
- Proceedings: Notice of Hearing (hearing set for June 4 through 6, 2014; 9:00 a.m.; Vero Beach, FL).
- PDF:
- Date: 05/01/2014
- Proceedings: Petitioners' Unnopposed Motion for Continuance and Extension of Time to File Pre-hearing Stipulation filed.
- PDF:
- Date: 04/29/2014
- Proceedings: Indian River County's Amended Witness List and (Proposed) Exhibit List filed.
- PDF:
- Date: 04/22/2014
- Proceedings: St. John's River Water Management District's Amended Witness and (Proposed) Exhibit List filed.
- PDF:
- Date: 04/22/2014
- Proceedings: St. John's River Water Management District's Witness and (Proposed) Exhibit List filed.
- PDF:
- Date: 04/17/2014
- Proceedings: Indian River County's Witness List and (Proposed) Exhibit List filed.
- PDF:
- Date: 04/11/2014
- Proceedings: Respondent, St. Johns River Water Management District's Amended Notice of Taking Deposition of Patrick Rose filed.
- PDF:
- Date: 04/09/2014
- Proceedings: Amended Notice of Hearing (hearing set for May 6 through 8, 2014; 9:00 a.m.; Vero Beach, FL; amended as to hearing room location).
- PDF:
- Date: 04/08/2014
- Proceedings: Respondent, St. Johns River Water Management District's Notice of Taking Deposition of Patrick Rose filed.
- PDF:
- Date: 04/04/2014
- Proceedings: Respondent, St. Johns River Water Management District's Notice of Taking Deposition of Lange Sykes filed.
- PDF:
- Date: 02/03/2014
- Proceedings: Indian River County's Response to Petitioners Baker and Cox's First Request for Production filed.
- PDF:
- Date: 01/28/2014
- Proceedings: St. Johns River Water Management District's Response to Petitioners Baker and Cox's First Requests for Production filed.
- PDF:
- Date: 01/28/2014
- Proceedings: St. Johns River Water Management District's Notice of Service of Answers and Objections to Petitioner Dr. David Cox's First Set of Interrogatories filed.
- PDF:
- Date: 01/22/2014
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for May 6 through 8, 2014; 9:00 a.m.; Vero Beach, FL).
- PDF:
- Date: 01/21/2014
- Proceedings: (Petitioners') First Amended Petition for Administrative Hearing filed.
- PDF:
- Date: 01/21/2014
- Proceedings: Petitioners' Unopposed Motion for Leave to File First Amended Petition filed.
- PDF:
- Date: 01/13/2014
- Proceedings: Amended Notice of Hearing (hearing set for February 4 through 6, 2014; 9:00 a.m.; Vero Beach, FL; amended as to hearing room location).
- PDF:
- Date: 01/06/2014
- Proceedings: Respondent St. Johns River Water Management District's Cross-notice of Taking Deposition Duces Tecum of Leonard Nero filed.
- PDF:
- Date: 01/06/2014
- Proceedings: Respondent's Notice of Taking Deposition (of Leronard Nero) filed.
- PDF:
- Date: 01/03/2014
- Proceedings: Respondent St. Johns River Water Management District's Cross-notice of Taking Deposition Duces Tecum of Dr. David Cox and Dr. Grant Gilmore filed.
- PDF:
- Date: 01/03/2014
- Proceedings: Repondent's Notice of Taking Deposition (of Grant Gilmore) filed.
- PDF:
- Date: 12/26/2013
- Proceedings: Petitiner Dr. David Cox's Notice of Serving of Interrogatories Upon Respondent St. Johns River Water Management District filed.
- PDF:
- Date: 12/02/2013
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for February 4 through 6, 2014; 9:00 a.m.; Vero Beach, FL).
- PDF:
- Date: 11/07/2013
- Proceedings: Notice of Aerving Pelican Island Audubon Society, Dr. David Cox and Dr. Robert Baker's Answers to St. Johns River Water Management District's Interrogatories filed.
- PDF:
- Date: 11/07/2013
- Proceedings: Notice of Serving Pelican Island Audubon Society's Answers to Indian River County's Interrogatories filed.
- PDF:
- Date: 11/07/2013
- Proceedings: Notice of Serving Dr. Richard Baker's Answers to Indian River County's Interrogatories filed.
- PDF:
- Date: 11/07/2013
- Proceedings: Notice of Serving Dr. David Cox's Answers to Indian River County's Interrogatories filed.
- PDF:
- Date: 10/04/2013
- Proceedings: Notice of Hearing (hearing set for January 8 through 10, 2014; 9:00 a.m.; Vero Beach, FL).
- PDF:
- Date: 09/27/2013
- Proceedings: Respondent St. Johns River Water Management District's Notice of Service of First Set of Interrogatories on Petitioner Pelican Island Audubon Society filed.
- PDF:
- Date: 09/27/2013
- Proceedings: Respondent St. Johns River Water Management District's Notice of Service of First Set of Interrogatories on Petitioner Dr. David Cox filed.
- PDF:
- Date: 09/27/2013
- Proceedings: Respondent St. Johns River Water Management District's Notice of Service of First Set of Interrogatories on Petitioner Dr. Richard Baker filed.
- PDF:
- Date: 09/27/2013
- Proceedings: Co-Respondent Indian River County's Notice of Service of First Set of Interrogatories on Co-Petitioner Dr. David Cox filed.
- PDF:
- Date: 09/27/2013
- Proceedings: Co-Respondent Indian River County's Notice of Service of First Set of Interrogatories on Co-Petitioner Dr. Richard Baker filed.
- PDF:
- Date: 09/27/2013
- Proceedings: Co-Respondent Indian River County's Notice of Service of First Set of Interrogatories on Co-Petitioner Pelican Island Audubon Society filed.
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 09/16/2013
- Date Assignment:
- 09/17/2013
- Last Docket Entry:
- 08/27/2014
- Location:
- Vero Beach, Florida
- District:
- Southern
- Agency:
- ADOPTED IN TOTO
Counsels
-
Kate P. Cotner, Esquire
Address of Record -
William K. DeBraal, Esquire
Address of Record -
Karen C. Ferguson, Esquire
Address of Record -
Gail L. Hankinson, Esquire
Address of Record -
Marcy I. LaHart, Esquire
Address of Record -
Marcy LaHart, Esquire
Address of Record