14-002798BID
Xerox State And Local Solutions, Inc. vs.
Department Of Revenue
Status: Closed
Recommended Order on Wednesday, February 18, 2015.
Recommended Order on Wednesday, February 18, 2015.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8XEROX STATE AND LOCAL SOLUTIONS,
13INC.,
14Petitioner,
15vs. Case No . 14 - 2798BID
22DEPARTMENT OF REVENUE,
25Respondent,
26and
27SYSTEMS AND METHODS, INC.,
31Intervenor.
32_______________________________/
33RECOMMENDED ORDER
35Pursuant to Notice, this cause came on for formal hearing
45before Diane Cleavinger, a designated Administrative Law Judge of
54the Division of Administrative Hearings, on August 6 and 7, 2014,
65in Tallahassee, Florida.
68APPEA RANCES
70For Petitioner: Eduardo S. Lombard, Esquire
76W. Robert Vezina, III, Esquire
81Megan Reynolds, Esquire
84Andrew Foti, Esquire
87Vezina, Lawrence and Piscitelli, P.A.
92413 East Park Avenue
96Tallahassee, Florida 32301
99For Respondent: Cindy Horne, Esquire
104Jeffrey Kelly, Esquire
107Department of Revenue
110Post Office Box 6668
114Tallahassee, Florida 32314 - 6668
119For Intervenor: Karen D. Walker, Esquire
125Mia McKown, Esquire
128Holland and Knight, LLP
132Post Office Drawer 810
136Tallahassee, Flori da 32302 - 1809
142STATEMENT OF THE ISSUE
146The issue in this proceeding is whether the Respondent's
155intended award of Invitation to Negotiate (ITN) 13/14 - 01 was
166contrary to the Department's governing statutes, rules or
174policies; contrary to the solicitation sp ecifications; and was
183clearly erroneous, contrary to competition, arbitrary or
190capricious.
191PRELIMINARY STATEMENT
193On August 27, 2013, Respondent, Department of Revenue (DOR
202or Department), issued Invitation to Negotiate 13/14 - 01, entitled
"212State Disbursemen t Unit." On December 2, 2013, replies to the
223ITN were submitted. The vendors submitting replies were Xerox
232State and Local Solutions, Inc. (Xerox) , and Systems and Methods,
242Inc. (SMI). On May 19, 2014, DOR posted its intent to award the
255contract to Inte rvenor, SMI.
260By Formal Written Protest dated June 2, 2014, Xerox timely
270protested DOR's intended decision to award the contract to SMI.
280On June 16, 2014, the matter was forwarded to the Division of
292Administrative Hearings (DOAH). That same day SMI file d a
302Petition to Intervene which was granted by Order issued June 23,
3132014.
314Prior to hearing, Xerox's Motion for Leave to File Amended
324Formal Written Protest Petition was granted by Order dated
333August 1, 2014. Additionally, Xerox's Motion for Leave to File
343Second Amended Formal Written Protest Petition was granted in
352part by Order dated August 16, 2014, but denied as to paragraphs
36474 through 82 of the Second Amended Petition since said
374paragraphs were untimely challenges to the ITN specifications.
382At hearin g, Joint Exhibits 1 through 12 were admitted into
393evidence. Xerox called four witnesses to testify: John Kinneer,
402Steve Updike, John Polk, and Michael Deckelman. Xerox's Exhibits
411numbered 1, 2, 4, 5, 10 through 16, portions of Exhibit 17 1/ ,
424Exhibit 32, portions of Exhibit 40 not rela ted to scoring, and
436Exhibits 46 through 54 were admitted into evidence. Xerox also
446proffered Exhibits 6, 8, 31, 33 through 39, portions of
456Exhibit 40 rela ted to scoring, and Exhibits 41 through 45. DOR
468called two witnesses to testify: Thomas Mato and Clark Rogers.
478Additionally, DOR's Exhibit 5 was admitted into evidence. SMI
487did not present any witness test imony. However, SMI Exhibits 1
498through 3 were admitted into evidence.
504The three - volume Transcript was filed with DOAH on
514August 22, 2014. Petitioner and Intervenor filed Proposed
522Recommended Orders on September 4, 2014. Respondent filed its
531Proposed Recommended Order on September 3 , 2014. After Proposed
540Recommended Orders were filed, the case was placed in abeya nce
551due to an action in Circuit Court involving Florida's Sunshine
561Law. Thereafter, DOR filed a Motion to remove the case from
572abeyance. The Motion was granted and the case proceeded to this
583Recommended Order which considered the parties earlier - filed
592Pr oposed Recommended Orders.
596FINDINGS OF FACT
5991. The Department is designated by section 409.2257,
607Florida Statutes (2014) , as the Title IV - D agency for the State
620of Florida. As such, it is responsible for the administration of
631the Child Support Enforcemen t program that is required in all
642states by the Federal Social Security Act. See § 409.2577, Fla.
653Stat.
6542 . As part of its duties under c hapter 409, the Department
667is authorized to solicit proposals from, and to contract with,
677private contractors to devel op, operate, and maintain a state
687disbursement unit (SDU). The SDU is responsible for processing,
696collecting and disbursing payments for most child support cases
705in Florida. The current contractor for the SDU is Xerox whose
716contract will expire on Februa ry 28, 2015.
7243. In general, Florida procurement law provides a continuum
733of competitive procurement processes running from invitations to
741bid, through requests for proposals, to invitations to negotiate.
750Invitations to bid are used where specifications c an be stated
761with certainty with the primary issue being price. Invitations
770to negotiate, on the other end of the procurement spectrum, are
781used to purchase services when state agencies need to "determine
791the best method for achieving a specific goal or s olving a
803particular problem." § 287.057(1)(c), Fla. Stat. (2014).
8104. In essence, an ITN contains the process a state agency
821follows in awarding a contract and the criteria to which a vendor
833should reply in order to be considered responsive to the ITN.
844Under an invitation to negotiate and even though a reply must be
856responsive to the invitation, specifications generally are more
864fluid and less mandatory. Price, while important, is negotiable.
873Indeed, an agency may "reply shop" the terms, including pri ce, of
885one vendor's reply against a competitor's reply in seeking
894revisions to that vendor's reply. As such, contract price is a
905more fluid concept under an ITN and is not the primary
916consideration in an ITN.
9205. In this case, the Department was seeking a solution for
931processing, collecting and paying child support payments based on
940a negotiated per transaction rate resulting from such SDU
949services plus negotiated service costs associated with the
957operation of the SDU. In fact, contracting for a transac tion -
969rate - based price was one of the prime considerations under this
981ITN because the Department felt it could gain significant
990contract sav ings by utilizing a transaction - rate - based pricing
1002scheme in its negotiations. Towards that end, the Department
1011issu ed Invitation to Negotiate 13/14 - 01 on August 27, 2013,
1023soliciting service solutions for the operation of the SDU.
10326. Prior to receiving replies to the ITN, the Department
1042issued seven addenda to the ITN, provided several replacement
1051pages to the ITN an d answered numerous vendor questions regarding
1062the ITN.
10647. After the release of the ITN and the seven addenda,
1075there was no protest filed pursuant to section 120.57, Florida
1085Statutes, regarding the ITN's specifications. As such, any
1093objection to those specifications was waived by Petitioner and
1102Intervenor.
11038. In this case, the ITN required a vendor's reply to be in
1116a particular format. Specifically, the ITN required that a
1125vendor's reply consist of two comp onents presented in two
1135multiple - tabbed binde rs: the Administrative/Technical Reply
1143(Technical Reply) and the Cost Data Reply (Cost Reply).
1152Technical Replies were to contain non - cost information such as
1163corporate capability, proposed solution technical components,
1169quality assurance and monitoring, and a variety of attachments.
1178Cost Replies were to contain a vendor's Transaction Rate,
1187Baseline Compensation, Reimbursable Costs, and other cost - related
1196information as specified by the ITN. Vendors were not permitted
1206to disclose any cost information in the Technical Reply.
12159. Additiona lly, the ITN required that a 15 - page
"1226Requirements Response Location Form" be completed and provided
1234by the vendor in its ITN reply. The form listed the section
1246numbers of the essential criteria of the ITN and the pages o f the
1260ITN on which each criterion could be found. The form also
1271contained blank spaces adjacent to each referenced criteria where
1280the vendor was to list the sections and pages of the vendor's
1292reply that responded to each of the referenced criteria in the
1303requirements response form.
130610. Relevant to thi s case, Section 1 of ITN 13/14 - 01
1319contained general definitions of terms used in the ITN. Under
1329Section 1, a "Responsive Reply" was defined as "[a] Reply
1339submitted by a responsible Vendor that conforms in a ll material
1350respects to the solicitation." A "Minor Irregularity" was
1358defined as "[v]ariations of terms and conditions from the
1367Invitation to Negotiate which do not affect the price of the
1378Reply or give the Vendor an advantage or benefit not enjoyed by
1390th e other Vendors or do not adversely impact the interests of the
1403State." Additionally, the Department reserved the right to waive
1412minor irregularities in a vendor's reply.
141811. ITN Section 2.4 provided: "The FDOR intends to
1427negotiate with one or more Vend ors who are compliant with the
1439mandatory compliance items identified throughout this document."
144612. ITN Section 2.5 addressed Desired vs. Mandatory
1454Requirements and Actions:
1457Within the ITN the use of "shall" or "must"
1466indicates a mandatory requirement or
1471mandatory action. The FDOR may consider
1477failure to meet a mandatory requirement to be
1485a material deficiency, in which case the FDOR
1493may reject the Reply and not consider it
1501further, or FDOR may have the option to score
1510that requirement with a zero (0). ( emphasis
1518added ) .
1521The use of "should" or "may" indicates a
1529desired requirement. The FDOR will not
1535reject a Reply just because it fails to meet
1544a desired requirement and may result in a
1552lower score for that requirement.
155713. Clearly under the ITN, the man datory nature of a
1568requirement did not result in the criteria also being material
1578since the Department could consider failure to meet a mandatory
1588requirement to be a material deficiency or allow the vendor to
1599move to the evaluation phase with the materiali ty of such
1610criteria to be addressed by the evaluators during scoring.
161914. ITN Section 3.1.9, titled "Material Requirements
1626Compliance Review," addressed the ITN's pro - forma review for
1636responsiveness and provided:
16393.1.9.1 Each Vendor shall submit a Repl y
1647that conforms in all material respects to
1654this solicitation. Material requirements of
1659the ITN are those set forth as mandatory or
1668those that affect the competitiveness of
1674Replies. All Replies will be reviewed to
1681determine if they are responsive.
16863.1.9 .2 The FDOR will conduct a Material
1694Requirements Compliance Review of all Replies
1700submitted in response to this ITN. This
1707review does not assign scores, but is simply
1715a pass/fail review. Replies that do not meet
1723all material requirements of this ITN; fa il
1731any of the mandatory requirements in this
1738ITN; fail to timely respond to Reply
1745Qualification Requests (see Section 3.1.10);
1750fail to provide the required/requested
1755information, documents, or materials in the
1761Reply and/or during the Reply Qualification
1767Pr ocess; or include language that is
1774conditional, or takes exception to terms,
1780conditions and requirements, shall be
1785rejected as non - responsive and not considered
1793further.
17943.1.9.3 The FDOR reserves the right to
1801determine whether a Reply meets the material
1808requirements of the ITN.
181215. Addition ally, Section 3.1.10 of the ITN provided that
1822the Department was to initially review each reply "to determine a
1833Vendor's compliance with the requirements of the ITN not directly
1843related to the Technical Specifications and Cost Data of the
1853ITN." (emphasis added ) . A checklist titled "Material
1862Requirements Compliance Review" was used to determine the
1870responsiveness of a reply. The checklist items are not at issue
1881here. Importantly, per the ITN criteria, the material
1889r esponsiveness review was a review of the form of a reply and not
1903a review of the substance of the same. Indeed, deficient replies
1914could be cured as part of the "Reply Qualification Process."
192416. After the responsiveness review, an Evaluation
1931Committ ee chosen by the Department would score the
1940Administrative/Technical Volume for each vendor in accordance
1947with the evaluation criteria in the ITN. Towards that review,
1957the vendor was required to complete and submit the "Requirements
1967Response Location Form " as part of its reply. As indicated
1977earlier, the response location form listed the section numbers of
1987the essential criteria of the ITN and the pages of the ITN on
2000which each criterion could be found. The form's criteria
2009references matched the criteria references in the score sheets to
2019be used by the individual evaluators to score a vendor's reply.
2030Further, the evaluation committee used the location form to
2039locate information within a vendor's reply. In evaluating
2047replies, the committee members were no t expected to hunt down
2058information in a vendor's reply outside what was provided by a
2069vendor on its response location form. Thus, the form is a very
2081good indication of the materiality or importance of a particular
2091ITN criteria since those criteria were t he ones on which a
2103vendor's reply was to be evaluated.
210917. Relevant to this case, Section 7.13.1.1 of the ITN
2119required that a letter of commitment for a surety bond be
2130submitted with a vendor's cost reply. There was no prescribed
2140format or wording for th is letter.
214718. Additionally, S ection 12 of the ITN contained a table
2158titled "Attachments and Submittals." According to Section 12,
2166the table listed a variety of documents "to be completed and
2177included in Volume One: Administrative/Technical as
2183indi cated[.]" However, the table clearly listed documents that
2192the ITN, in other sect ions, required to be in Volume Two , the
2205Cost Data Reply. In fact, the table itself only indicated who
2216should complete a document. It did not indicate whether a
2226document was required , for responsiveness purposes , to be
2234submitted with a reply. The "as indicated" language, referenced
2243above, referred to other sections within the ITN to determine if
2254such documents should be submitted and in what volume they should
2265be submitted. Other than referral to other sections of the ITN,
2276Section 12 did not require that any document listed in its table
2288be attached to the ITN.
229319. Two of the documents listed in S ection 12 of the ITN
2306were "Incident Control Policy and Procedures" and "Ch ange
2315Management Policy and Procedures." In the column of the table
2325titled "Attachment" these two documents were listed as "Vendor's
2334Documents." However, unlike the other documents listed in the
2343S ection 12 table, these two documents had no attendant
2353requi rement in other sections of the ITN stating that the two
2365documents sh ould be provided or where in a v endor's reply the two
2379documents should be placed.
238320. The Department's responses to October 24, 2014, vendor
2392q uestions 18 and 19 regarding these docu ments were that the two
2405documents referred to the v endor's corporate documents and that a
2416copy of such documents were required to be submitted with a
2427vendor's "proposal." Except for the Department's responses,
2434there were no written addenda amendments to t he ITN document
2445making such submission mandatory or indicating in what section of
2455the vendor's multi - tabbed response the documents should be
2465included. Further, no addenda amendments were made to the
2474response location form to cover these documents. Simila rly, no
2484addenda amendments were made to the evaluator's score sheets to
2494cover or evaluate these documents. Thus, despite the use of the
2505word "required" in the Department's response to questions 18 and
251519 and in view of the lack of any amendments to the IT N in
2530relation to these responses, the evidence demonstrated that
2538submission of these two documents with a vendor's reply was only
2549desired by the Department and was not mandatorily required under
2559the ITN for purposes of responsiveness.
256521. Section 1 2 of the ITN a lso listed Attachment G,
"2577Individual Contractor Security and Agreement Form." The form
2585was to be "completed" by the vendor and subcontractors. As
2595discussed above, inclusion in the Section 12 table did not
2605indicate whether a document was req uired for responsiveness
2614purposes to be submitted with a reply. Those criteria were found
2625elsewhere in the ITN.
262922. Notably, the provision of the standard contract which
2638would emerge from this ITN required the security form be exe cuted
2650by subcontr actors within five days of signing the contract. More
2661importantly, Section 6.6 of the ITN stated that Attachment G
"2671should" be executed and submitted with a vendor's reply. As
2681such, the document's attachment was not mandatorily required for
2690responsivenes s purposes, but was only desired by the Department
2700at this point in the ITN process since the winning vendor and its
2713subcontractor's mu st provide the document within five days of
2723signing the contract.
272623. The ITN further provided in Section 10.3.2 that up on
2737completion of the Administrative/Technical evaluation, the Cost
2744Data Volume would be publicly opened and scored.
275224. Relevant to this case, the ITN addressed renewal cost
2762and renewal of any future contract in Section 7.4 of the ITN.
2774Section 7.4 stated , in pertinent part:
2780RENEWALS
2781The FDOR reserves the right to renew any
2789Contract resulting from this ITN. Renewals
2795shall be subject to the terms and conditions
2803set forth in the original Contract and
2810subsequent amendments, . . .
2815Vendors shall include the cost of any
2822contemplated renewals in their Reply, . . .
283025. In substance the s ection tracked the language of
2840s ection 287.057(13), Florida Statutes, making any renewal subject
2849to the same terms and conditions, including price, as the
2859original contra ct. Th e statute al so requires that the "price" of
2872any "services to be renewed" be provided in a vendor's reply.
2883However, if a separate renewal price was not provided in a
2894vendor's reply, any renewals would be at the price of the
2905original contract since under th e ITN the original price would be
2917the renewal price for s ection 287.057(13) purposes.
292526. On the other hand, Section 7.4 of the ITN deviated from
2937the statute's language and required that the "cost" of any
" 2947contemplated renewals" be included in the vendo r's reply.
2956Such cost information was not part of the criteria requirements
2966listed for the ITN on the "Requirements Response Location Form"
2976and was not part of the requirements to be evaluated by the
2988evaluation committee.
299027. Question 39 posited by SMI o n September 18, 2013, asked
3002about the handling of renewal cost information in the vendor
3012replies to the ITN. The Department's response to question 39 was
3023that "renewal rate information" "should" "please" be provided in
3032summary form in the cost volume of t he vendor's reply to the ITN.
3046Additionally, the Department's response stated that renewal cost
3054information was not to be "scored" as part of the transaction
3065rate. Clearly, the Department in its response viewed this "rate
3075information" as related to the tr ansaction rate , which was one of
3087several costs used to calculate total compensation under the ITN.
3097The Department's ex planation or interpretation of S ection 7.4 has
3108a reasonable basis since renewal of the contract was statutorily
3118restricted to the same te rms and conditions of the original
3129contract, making such renewal cost information immaterial.
3136Additionally, the renewal information was not part of the scoring
3146criteria that permitted a vendor to move through the negotiation
3156process under the ITN and was not required in order for a vendor
3169to be responsive to the ITN. In essence, the Department's
3179response made the provision of renewal cost information a non -
3190essential criteria of the ITN. Non - compliance with such criteria
3201can be waived by the Department as a minor irregularity. 2/
321228. ITN Section 10.3.2.1.4 provided:
3217Only cost submitted in the prescribed format
3224will be considered. Alternate cost models
3230will not be considered for scoring purposes.
3237Vendors selected for negotiations will be
3243provided the opportunity to present alternate
3249costing structures.
"3251Alternate cost models" referred to models that did not use a
3262transaction - based rate such as a fixed price model or did not use
3276the format for calculating compensation required by the ITN.
328529. Part o f the format for vendor cost replies included
3296Attachments K (Transaction Rate Cost Form), L (Baseline
3304Compensation Form), M (Reimbursable Cost Form), N (Unknown,
3312Unanticipated, and Unspecified Tasks Cost Form), and O (Total
3321Compensation Form). Additionall y, after questions posed by the
3330vendors, the Department supplied an estimate of the number of
3340transactions it predicted might be processed by the SDU under the
3351contract. The estimate provided by the Department was 69,425,110
3362transactions and was based in part on an assumed percentage
3372increase in actual transactions that occurred under the current
3381contract in 2012.
338430. Attachment K was the form used by a vendo r to explain
3397and report the per - transaction rate that the vendor would charge
3409the Department for e ach transaction it processed through the SDU.
3420The form required disclosure of the costs the vendor included in
3431determining its transaction rate. The form was required to be
3441signed by a representative who could bind the vendor.
345031. Relative to Attachme nt K under the ITN, neither the
3461method used nor the costs included by a vendor to calculate its
3473transaction rate was prescribed by the ITN criteria. There was
3483no requirement that the Department's estimated number of
3491transactions of 69,425,110 be used in c alculating the vendor's
3503transaction rate. The Department only supplied such estimates as
3512information to the vendor. In fact, a vendor was free to use its
3525own assumptions regarding the estimated number of transactions
3533that might be processed through the S DU in its calculation of its
3546transaction rate. The method of rate calculation did have to be
3557explained. However, once calculated, the vendor's transaction
3564rate was carried over to line "B" on Attachment L which, as
3576discussed below, ultimately filtered th rough to a contract price
3586and commensurate price of services that might be renewed in
3596Attachment O.
359832. Attachment L was the form used to calculate the
3608baseline compensation cost for the vendor. The initial form did
3618not require that the Department's estimate of 69,425,110
3628transactions be used in the calculation of the baseline
3637compensation cost. After questions from the vendors and internal
3646discussions within the Department, Attachment L was revised to
3655require that the Department's estimated number of transactions be
3664used on that form. Notably, the Department did not revise
3674Attachment K to require the use of the estimate when it revised
3686Attachment L. The formula used to calculate Projected Baseline
3695Compensation on Attachment L required the vendor t o multiply its
3706transaction rate from Attachment K by the Department's estimated
3715transactions of 69,425,110. The requirement to use the
3725Department's estimated number of transactions on Attachment L
3733normalized the vendors' baseline compensation calculation so that
3741an apples - to - apples comparison of baseline compensation could be
3753made between vendors. Once calculated, the projected baseline
3761compensation cost calculation was carried over to a line item in
3772Attachment O , which form calculated the total projected SDU
3781compensation, the cost factor used in awarding points to evaluate
3791a vendor's reply.
379433. Attachment M was the form on which a vendor was to
3806submit estimates of actual costs the vendor anticipated it would
3816expend for performing the contract. Although not specified,
3824presumably the costs listed by the vendor on Attachment M would
3835be those not used in the vendor's Attachment K transaction rate
3846calculation. Ad ditionally, ITN specifications S ections 7.10.4.3
3854and 10.3.2.3 provided that all vendors "shall ex ecute and submit
3865Attachment M: Reimbursable Costs." The term "execute" simply
3873means to complete.
387634. Within Attachment M, a list of several anticipated cost
3886categories (facilities rent/lease, postage, e - disbursement, post
3894office box fees, etc.) were p rovided by the Department. There
3905were also several blank fields for additional cost categories
3914contained on the form. The specifically - listed cost categories
3924were those categories the Department, in its experience,
3932anticipated a vendor might incur and fo r which it would reimburse
3944a vendor. The use of the phrase "will reimburse" in relation to
3956these anticipated cost categories did not make the reporting of
3966such costs mandatory given the format of Attachment M and the
3977instructions later provided on the for m discussed below. Such
3987anticipation only indicated interest by the Department in those
3996expense categories but did not create a requirement that those
4006specific expenses were required to be estimated by a vendor for
4017purposes of responsiveness to the ITN in order to move forward in
4029the evaluation and negotiation process. 3/ Indeed, such costs or
4039expenses were intentionally negotiable under the ITN.
404635. Following this list, a box to provide the amount of
4057each reimbursable cost and ultimate total was provid ed at the end
4069of Atta chment M. Notably, except for two of the anticipated cost
4081categories, the box did not include any of the anticipated costs
4092listed earlier in Attachment M. The two cost categories that
4102were listed in the reimbursable cost box were "Fa cilities
4112Rent/Lease" and "CSR Salary Expenses." Both these cost
4120categories had blank fields where the vendor was required to fill
4131in an amount in the reimbursable cost box at the end of
4143Attachment M. Additionally, the instructions for executing the
4151box c learly stated that amounts for these two categories must be
4163provided. As indicated, the other anticipated costs contained on
4172Attachment M were not specifically listed in the reimbursable
4181cost box. On ly blanks, labeled as "(other)," where amounts for
4192vend or "proposed" costs could be reported were contained within
4202the box. Given the format of this form and the instructions at
4214the top of the reimbursable cost box, amounts for anticipated
4224cost categories listed in Attachment M, other than the two
4234required co st categories in the box, were not required to be
4246proposed by the vendor in completing Attachment M and, as
4256indicated earlier, such amounts were not required in order for a
4267reply to be responsive to the ITN. As with the other forms, the
4280total from the rei mbursable cost box was carried over to a line
4293item in Attachment O.
429736. Attachment O was the form used to calculate the total
4308projected SDU compensation that constituted the vendor's proposed
4316contract price. The proposed price was also the price for
4326se rvices which may be renewed since, unless the vendor proposed a
4338different renewal price, this was the original price proposed as
4348a term of the initial contract.
435437. Section 10.3.2 sets forth the formula for scoring the
4364Cost Data Volume of a vendor. The formula was:
4373Total Available Cost Points x Amount of
4380Lowest Response Cost/Vendor's Reply Cost
4385(emphasis in original).
438838. The ITN further stated:
"4393Each Vendor's Cost Data points will be added
4401to their Administrative/Technical score to
4406obtain th e Vendor's Total Reply Score. The
4414Vendor's Total Reply Score will be used to
4422determine which Vendors the FDOR will
4428Negotiate with."
4430Thus, the vendor with the lowest cost would receive the maximum
4441points available for its Cost Data Volume with all other vendors
4452receiving a portion of the total available Cost Data points
4462proportionate to the difference between their proposed cost and
4471that of the vendor with the lowest cost. Notably, lower cost
4482points did not disqualify a vendor from selection for
4491negotia tion. Similarly, a lower Total Reply Score did not
4501disqualify a vendor from selection for negotiation because the
4510goal in an ITN procurement is t o develop a range of vendor
4523replies for negotiation.
452639. The ITN, in Section 11.3 , provided broad discretion to
4536the Department regarding the manner in which negotiations would
4545be conducted, including obtaining revised offers from v endors.
4554The section reserved to the Department the right to:
4563(a) negotiate with one or more, all, or none of the vendors;
4575(b) elim inate any vendor from consideration during negotiations
4584as deemed to be in the best interest of the State; and
4596(c) conduct negotiations sequentially, concurrently, or not at
4604all.
460540. Sections 3.1.19.1 and 11.5 of the ITN provided that at
4616the "conclusion" of negotiations, the Department would post a
4625Notice of Intended Agency Decision, as determined to be in the
4636best interest of the State. However, this language must be read
4647in conjunction with Section 11.4 of the ITN that authorized the
4658Department's negot iation team to request a Best and Final Offer
4669(BAFO) from one or more vendors with which the Department
4679concluded negotiations. The section reserved to the Department
4687the right to "request additional BAFO; reject submitted BAFO;
4696and/or move to the next ve ndor" after a BAFO had been submitted
4709and negotiations concluded. Additionally, Section 2.6.9
4715contemplates that discussions, i.e. negotiations, regarding the
4722form and language of the final contract would continue after the
4733Notice of Intent to Award was po sted. Section 2.6.9 states:
4744The FDOR anticipates initially addressing any
4750contract terms and conditions or concerns
4756during the Negotiation process and then
4762continue discussions post award.
4766Given this language, the Department, in its judgment and acting
4776i n the best interest of the state, may post an intended award
4789prior to the complete conclusion of negotiations and finalization
4798of the contract with a vendor.
480441. In this case, SMI and Xerox both timely submitted a
4815reply to the ITN. Each reply contained a Volume I:
4825Administrative/Technical; and a Volume II: Cost Data. Both
4833vendors submitted a completed Requirements Location Response Form
4841and had information contained in their reply relative to the
4851references contained in that form. As indicated earlier , under
4860the ITN's pro forma responsiveness review, the substance of each
4870vendor's reply was not a determining factor in whether a vendor's
4881reply was responsive to the ITN for purposes of being accepted
4892and moving forward in the ITN process.
489942. John Kin neer was a purchasing analyst with the
4909Department. He served as the procurement officer and as a
4919negotiator with respect to the ITN. Mr. Kinneer reviewed the
4929technical replies submitted by Xerox and SMI for pro - forma
4940responsiveness to the ITN sufficient to move forward in the ITN
4951process. In compliance with the ITN, he checked the Material
4961Requirements form for both vendors and checked that each vendor
4971had some information in its technical reply relative to the
4981response form. Per the ITN, he did not che ck the substance of
4994that information. In this case, the evidence demonstrated that
5003both replies met the preliminary responsiveness requirements of
5011the ITN and properly moved forward in the ITN process to the
5023evaluation phase.
502543. The Department appointed an evaluation team of seven
5034persons to evaluate and score the Technical Replies. The
5043Committee consisted of Shannon Herold, Barbara Johnson, Connie
5051Beach, Stan Eatman, Beth Doredant, Mark Huff, and Craig Curry.
5061Under the ITN, the evaluation team was tas ked with analyzing the
5073substance of each reply and scoring them accordingly with any
5083issues regarding the quality or responsiveness of a vendor's
5092reply to be addressed in that evaluator's scoring. Each
5101evaluator reviewed and independently scored each vend or's reply
5110according to the criteria listed in the "Requi rements Response
5120Location Form."
512244. In this case, both replies contained a surety letter of
5133commitment as required by Section 7.13.1.1 of the ITN. SMI's
5143letter was from OneBeacon, the apparent b onding agent in the
5154letter. Indeed, there was no evidence that OneBeacon was not a
5165bonding company. The letter indicated that OneBeacon intended to
5174provide a bond to SMI and that SMI qualified for such a bond in
5188an amount sufficient to meet the requireme nts of the ITN.
5199Xerox's letter of commitment was also from an apparent bonding
5209company and stated only that the bonding company was "prepared to
5220write the required performance bond" in an unspecified amount and
"5230subject to standard underwriting conditions ." While one may
5239quibble about the language used in both Xerox's and SMI's
5249letters, the evidence showed that both letters were not simply
5259letters of reference from a bonding company but were letters of
5270commitment from such companies and were intended as s uch by those
5282bonding agents. Moreover, the language of both letters was
5291acceptable to the Department as meeting the requirements of the
5301ITN. As such, both Xerox and SMI were responsive to the surety
5313commitment requirements of the ITN.
531845. Xerox's reply also attached a copy of its Corporate
5328Change Control P olicy and Procedures and a copy of its Corporate
5340Incident Control Policy. These documents were developed by Xerox
5349over several years of being in the business of providing SDU
5360services. They were not d eveloped in relation to this ITN and
5372the evidence did not show that Xerox was disadvantaged either
5382monetarily or otherwise by producing these documents for the ITN.
5392On the other hand, SMI did not attach such documents. Instead,
5403SMI summarized the substan ce of its policy and procedures in
5414Tabs 3, 10 and 13 of its Technical R eply and included a copy of
5429SMI's corporate Security Plan encompassing the incident and
5437control policies of SMI. The quality of SMI's reply was
5447evaluated by the evaluation committee m embers and scored
5456according to the criteria relevant to the ITN. Further, the
5466evidence demonstrated that failure to attach these two documents
5475would not adversely affect any vendor or impair the procurement
5485process since a vendor ultimately was required t o agree to adopt
5497the Department's incident control and change management policies
5505and procedures. Moreover, as indicated earlier, the documents
5513were not part of the responsiveness requirements under the ITN.
5523Therefore, SMI's reply was responsive without the attachment of
5532these two documents. However, assuming such documents were
5540required, the evidence demonstrated that the lack of copies of
5550specific documents titled in a certain way was a minor
5560irregularity which the Department reasonably waived since SM I
5569summarized the information relevant to these documents in its
5578reply. Such waiver was not clearly erroneous, contrary to
5587competition, arbitrary , or capricious.
559146. Additionally, Xerox submitted with its reply an
5599executed Attachment G, Individual Contrac tor Security Agreement
5607Form, for both itself and its proposed subcontractors. SMI
5616submitted an executed Attachment G for itself but did not submit
5627the attachment for its proposed subcontractors. The form was not
5637submitted for SMI's proposed subcontractor s because its
5645subcontractors could not access the Department's online
5652procurement library to determine what they would be agreeing to
5662by signing the form. The inaccessibility of the procurement
5671library was not the fa ult of SMI or its subcontractor s but wa s
5686due to the Department's failure to provide the policies
5695referenced. Additionally, the Department's Standard Contract
5701required Attachment G to be provided within five business days of
5712contract execution. The evidence did not demonstrate that SMI's
5721failu re to include an executed Attachment G for its
5731subcontractors constituted a material deviation from the ITN.
5739Further, as indicated above, Attachment G was not a mandatory
5749provision of the ITN for responsiveness purposes. As such, SMI's
5759reply was responsi ve on this criterion.
576647. However, even assuming Attachment G was required under
5775the ITN, the quality of SMI's reply was evaluated by the
5786evaluation committee members under the relevant criteria. The
5794evidence did not demonstrate that SMI obtained an un fair
5804competitive advantage by not including this form in its reply
5814since any subcontractor would have to submit the executed form
5824after contract execution as required by the Department's Standard
5833Contract. Additionally, the evidence did not demonstrate th at
5842the procurement process was undermined by the lack of a
5852subcontractor Attachment G in SMI's reply. Therefore, the lack
5861of such a document in SMI's reply was reasonably waived by the
5873Department as a minor irregularity and such waiver was not
5883clearly err oneous, contrary to competition, arbitrary , or
5891capricious.
589248. The evaluation team completed scoring of the vendor's
5901technical replies around January 17, 2014. Xerox scored 969
5910points and SMI scored 943 points. The difference of 26 points
5921was not shown by the evidence to be significant since both
5932vendors were experienced and well qualified to perform the
5941services required to operate the child support State Disbursement
5950Unit.
595149. After the technical replies were evaluated and scored,
5960the initial Cost Dat a replies of each vendor were opened and the
5973total costs read aloud at a public meeting. The initial cost
5984replies were reviewed by Mr. Kinneer to ensure the replies were
5995mathematically accurate and that the cost forms were used. He
6005did not review or cons ider the substance of the cost numbers
6017included on those forms or the narratives in the cost replies.
6028The substance of the cost replies was left for consideration by
6039the negotiation team.
604250. Xerox's proposed total compensation for years
60491 through 5 of the contract was $84,920,072.00. SMI's proposed
6061total compensation for the same period was $47,996,387.00,
6071approximately $36 million less than Xerox's proposed
6078compensation. Neither vendor submitted a separate price for
6086renewal of the SDU services contr act. Therefore, for purposes of
6097section 287.057(13), Florida Statutes, the "price" for the
"6105services to be renewed" was the amount stated above for that
6116vendor. Both Xerox and SMI were responsive for purposes of the
6127statutory requirement of section 287.0 57(13).
613351. Xerox also submitted a brief summary of renewal cost in
6144its introductory letter to its cost reply. In essence, Xerox did
6155not anticipate any renewal cost associated with future renewal of
6165the contract. SMI, also, did not anticipate any renewa l cost
6176associated with future renewal of the contract, but did not
6186submit a statement to that effect. However, as discussed above,
6196such cost information was not part of the criteria requirements
6206listed for the ITN on the "Requirements Response Location Fo rm"
6217and was not part of the requirements to be scored by the
6229Department for purposes of the cost reply. The evidence
6238demonstrated that the information was immaterial to the
6246Department in evaluating these replies. Further, the evidence
6254did not demonstrate that failure to summarize such renewal cost
6264information would adversely affect any vendor or impair the
6273procurement process. Under this ITN and the facts of this case,
6284the failure to provide such non - essential cost information
6294constituted a minor irregul arity and was appropriately waived by
6304the Department. The Department's action in that regard was not
6314unreasonable and was not clearly erroneous, contrary to
6322competition, arbitrary , or capricious.
632652. The evidence showed that both vendors filled out
6335Attac hments K, L, M, N , and O. Relative to A ttachment K,
6348Transaction Rate, both vendors completed the form based on their
6358unique assumptions regarding the appropriate transaction rate.
6365Neither vendor used the Department's estimated transaction amount
6373of 69,42 5,110 transactions. Xerox claimed that its assumptions
6384took into consideration the Department's estimate and that such
6393consideration was buried in its ultimate calculation. However,
6401Xerox's mathematical explanation of its transaction rate
6408calculation on its Attachment K does not reflect that it used the
6420Department's estimate in its calculation. In general, the
6428explanation of its transaction rate contained in its reply
6437reflects that Xerox based its transaction rate on the current
6447contract price minus the annualized costs contained in its
6456Attachment M, divided by the actual number of transactions Xerox
6466processed in 2012 and discounted by 12% to produce a transaction
6477rate of 1.150 for the ITN. Clearly, Xerox did not use the
6489Department's estimate in its calc ulation and, instead, based its
6499transaction rate on the current contract price, a meth od the
6510Department warned vendor s against using.
651653. Similarly, SMI did not use the Department's estimated
6525transaction number in its calculation of its transaction rate on
6535Attachment K. SMI based its proposed rate of .497 on its own
6547historical transaction volumes from other states. The estimated
6555number of transactions used by SMI was 45,066,694 transactions.
6566For unknown reasons, the detailed explanation of the amount of
6576transactions used by SMI was placed on Attachment L. However,
6586the explanation was not used on Attachment L and did not impact
6598the calculation contained on Attachment L. Such misplacement was
6607immaterial to the ITN and had no impact on the ultimate resu lt in
6621Attachment O. As such, the misplaced explanation did not render
6631SMI's Attachment K non - responsive to the ITN and both Xerox and
6644SMI were responsive to the ITN regarding Attachment K.
665354. Likewise, the misplaced explanation of SMI's
6660transaction volu me did not render SMI's Attachment L non -
6671responsive to the ITN since it was immaterial to that Attachment.
6682Further, the evidence demonstrated that both Xerox and SMI used
6692the Department's estimated transaction volume on Attachment L as
6701required by the ITN . Therefore, both Xerox and SMI were
6712responsive to the ITN regarding Attachment L.
671955. Relative to Attachment M, Reimbursable Costs, both
6727vendors supplied cost amounts for rent and CSR salaries as
6737required by Attachment M. However, neither vendor suppli ed all
6747of the cost amounts listed in Attachment M's list of anticipated
6758costs. SMI did not supply amounts for postage associated with
6768certain services, post office box fees, foreign bank fees , and
6778hand - signed paper check stock costs. Xerox did not supply
6789amounts associated with SDU mass mailings as li sted in cost
6800category two for postage - related items on Attachment M and did
6812not submit an amount for telecommunications cost. As discussed
6821earlier, except for two of the anticipated cost categories of
6831rent a nd CSR salaries, the ITN did not require that amounts be
6844supplied for those categories in order for a reply to be
6855responsive to the ITN. Therefore, both Xerox and SMI were
6865responsive to the ITN regarding Attachment M.
687256. Both Xerox and SMI submitted a r esponsive Attachment O
6883which included line items fro m Attachments K through N.
6893Attachment O formed the basis for awarding points based on the
6904lowest cost. As indicated earlier, Xerox's proposed total
6912compensation for years 1 through 5 of the contract was
6922$84,920,072.00. SMI's proposed total compensation for the same
6932period was $47,996,387.00.
693757. Under the ITN, the cost replies were scored according
6947to the ITN specifications in Section 10.3.2 and the formula
6957contained therein. SMI received a total of 6 60 points as the low
6970cost reply. As the second lowest cost reply, Xerox received 376
6981points as a proportion of the total 660 points received by SMI.
6993Both vendors' scores were added to their technical scores. SMI
7003received a combined Total Reply score of 1603 points for its
7014reply. Xerox received a combined Total Reply Score of 1346
7024points for its reply. As responsible and responsive vendors,
7033both Xerox and SMI were selected to participate in the
7043negotiation phase of the ITN, where, under the ITN, the cri teria
7055and terms of the ITN became negotiable. Further, the evidence
7065did not demonstrate that either the evaluation scores or the
7075Total Reply Scores impacted the ITN process beyond qualifying the
7085vendors to participate in the negotiation process.
709258. The Department formed a Negotiation Team consisting of
7101Thomas Mato, Clark Rogers, Nancy Luja, Max Smart, Steve Updike,
7111John Kinneer, and Bo Scearce.
711659. Several meetings of the Negotiation T eam were held
7126during which the team evaluated Xerox's and SMI's repli es, posed
7137written questions to the vendors and discussed technical issues
7146with technical experts. Face to face negotiating sessions
7154between the team and the vendors were also held, as well as
7166meetings to discuss technical issues with the parties.
7174Additio nally, two rounds of separate demonstrations of a vendor's
7184proposed system and solution were given to the Negotiation Team
7194by Xerox and SMI. The Negotiation T eam only observed the
7205demonstration of each vendor in the first such meeting. During
7215the second dem onstration by each vendor, the N egotiation T eam
7227observed the demonstration and asked questions of the vendor.
7236Based on these demonstrations and meetings, the team elected to
7246request revised replies from both vendors. At some point prior
7256to submission of the revised offers and per the ITN, the team
7268communicated to Xerox that, if it wish ed to stay competitive in
7280the ITN process, it should bring its price c loser to that of SMI.
7294The team also communicated its desire to SMI that costs from the
7306anticipated cost list on Attachment M that SMI had not included
7317in its initial reply should be included on that form.
732760. With that information from the Negotiation T eam, Xerox
7337and SMI submitted revised cost replies. Xerox's Total Projected
7346SDU Compensation droppe d from $84,920,072.00 to $48,200,000.00.
7358Its transaction rate was reduced from $1.150 to $.525. Its
7368Attachment M cost estimate increased from $5,081,195.50 to
7378$9,926,119.00. SMI's Total Projected SDU Compensation increased
7387from $47,996,387.00 to $49,500 ,000.00. Importantly, its
7397transaction rate remained the same at $.497. Its Attachment M
7407cost decreased from $13,492,107.00 to $12,433,125.00.
741761. After revi ewing the revised replies, the Negotiation
7426T eam elected to continue to conduct negotiations with SMI first.
7437Such vendor selection was appropriate under the ITN since its
7447transaction rate remained lower than Xerox's transaction rate and
7456the team preferred SMI's solution for a variety of legitimate
7466reasons to Xerox's solution.
747062. Additional negotia tions were conducted with SMI,
7478resulting in additional terms and cond itions. After several such
7488negotiation meetings, the evidence showed that the substantive
7496part of the negotiations, including price and scope of work, had
7507concluded with only final contr actual language remaining. As
7516such , the Negotiation T eam requested a Best and Final Offer
7527(BAFO) from SMI.
753063. On May 14, 2014, SMI submitted its BAFO. SMI's Total
7541Projected SDU Compensation increased from $49,500,000.00 to
7550$50,700,000.00. Its transact ion rate dropped slightly to $.495
7561and its Attachment M cost increased from $12,433,125.00 to
7572$13,740,152.09.
757564. The BAFO was acceptable to the negotiation team and
7585would, along with SMI's technical reply, become part of the
7595Department's standard contr act under the ITN. The team
7604reasonably concluded SMI's management team was superior, and its
7613solution was more customer friendly, intuitive, efficient , and
7621innovative. The Negotiation T eam documented its reasons for
7630selecting SMI in a memorandum to the p rocurement file.
764065. On May 19, 2014, the Department posted its Notice of
7651Intended Award to SMI. The evidence did not demon strate that the
7663award violated s ection 287.057, Florida Statutes , since that
7672section only requires that negotiations be "conducte d" prior to
7682an intended award of a contract. Notably, the award is only
7693intended and is not final since the Department under Sections
77033.1.19.2 and 7.3 is not required to enter into a contract if such
7716a document cannot be finalized. Indeed, the statutory language
7725of section 287.057(4) and the ITN in Section 2.6.9 permit
7735continued negotiation and finalization of a contract after the
7744Notice of Intended Award.
774866. In this case, the evidence demonstrated that the
7757negotiations between the negotiation team an d SMI resulted in a
7768meeting of the minds regarding the services that SMI would be
7779performing and the price for those services. Further, the
7788evidence showed that the negotiations had concluded in all
7797substantial respects prior to posting of the Notice of I ntent to
7809Award the contract to SMI. What remained for the Department and
7820SMI to accomplish was the finalization of the contract a ssembly
7831by inserting the BAFO, Technical R eply , and p rice into the
7843contract language; insertion of a start date; and work on
7853i mplementation issues such as invoices and background screening
7862of employees. Given these facts, the evidence demonstrated that
7871the point at which the Department elected to post its Notice of
7883Intended Award was reasonable since the substantive parts of the
7893negotiations were complete.
789667. Ultimately, the evidence in this case did not
7905demonstrate that the ITN process followed by the Department was
7915fundamentally flawed or gave an advantage to one vendor over
7925another. Further, the actions of the Department in this
7934procurement were not contrary to the Department's statutes;
7942contrary to the Department's rules or policies; or contrary to a
7953reasoned interpretation of the ITN specifications. Finally, the
7961evidence did not demonstrate that the Department's actions w ere
7971clearly erroneous, contrary to competition, arbitrary , or
7978capricious. Given these facts, the protest filed by Petitioner
7987should be dismissed.
7990CONCLUSIONS OF LAW
799368. The Division of Administrative Hearings has
8000jurisdiction over the parties to and the subject matter of this
8011proceeding. See §§ 120.569 and 120.57, Fla. S tat. (2014 ) .
802369. Chapter 287, Florida Statutes, deals with the
8031procurement of commodities and services by state agencies. In
8040this case, the Department utilized an invitation to negotiat e as
8051the method for procurement of the contract at issue. Section
8061287.057(1)(c) describes how a procurement by invitation to
8069negotiate is conducted and provides:
8074(c) Invitation to negotiate. -- The
8080invitation to negotiate is a solicitation
8086used by an agenc y which is intended to
8095determine the best method for achieving a
8102specific goal or solving a particular
8108problem and identifies one or more
8114responsive vendors with which the agency
8120may negotiate in order to receive the best
8128value.
81291. Before issuing an invi tation to
8136negotiate, the head of an agency must
8143determine and specify in writing the reasons
8150that procurement by an invitation to bid or a
8159request for proposal is not practicable.
81652. The invitation to negotiate must
8171describe the questions being explored, the
8177facts being sought, and the specific goals
8184or problems that are the subject of the
8192solicitation.
81933. The criteria that will be used for
8201determining the acceptability of the reply
8207and guiding the selection of the vendors
8214with which the agency will neg otiate must
8222be specified.
82244. The agency shall evaluate replies against
8231all evaluation criteria set forth in the
8238invitation to negotiate in order to establish
8245a competitive range of replies reasonably
8251susceptible of award. The agency may select
8258one or mo re vendors within the competitive
8266range with which to commence negotiations.
8272After negotiations are conducted, the agency
8278shall award the contract to the responsible
8285and responsive vendor that the agency
8291determines will provide the best value to the
8299state , based on the selection criteria.
83055. The contract file for a vendor selected
8313through an invitation to negotiate must
8319contain a short plain statement that
8325explains the basis for the selection of the
8333vendor and that sets forth the vendor's
8340deliverables an d price, pursuant to the
8347contract, along with an explanation of how
8354these deliverables and price provide the
8360best value to the state.
836570. Section 287.012(25) defines a responsive submission to
8373a solicitation as follows: "Responsive bid," "responsive
8380p roposal," or "responsive reply" means a bid, or proposal, or
8391reply submitted by a responsive and responsible vendor that
8400conforms in all material respects to the solicitation. A
8409responsive vendor is defined by section 287.012(26) as "a vendor
8419that has sub mitted a bid, proposal, or reply that conforms in
8431all material respects to the solicitation." Section 287.012(24)
8439defines a responsible vendor as "a vendor who has the capability
8450in all respects to fully perform the contract requirements and
8460the integrity and reliability that will assure good faith
8469performance." The statutory definition of a responsive vendor
8477does not change whether the procurement method is an invitation
8487to bid, a request for proposals, or an invitation to negotiate.
849871. The burden of p roof in a competitive - procurement
8509protest rests with the party protesting the agency's intended
8518decision. Section 120.57(3)(f) provides:
8522In a competitive - procurement protest, other
8529than a rejection of all bids, proposals, or
8537replies, the administrative la w judge shall
8544conduct a de novo proceeding to determine
8551whether the agency's proposed action is
8557contrary to the agency's governing statutes,
8563the agency's rules or policies, or the
8570solicitation specifications. The standard of
8575proof for such proceedings sha ll be whether
8583the proposed agency action was clearly
8589erroneous, contrary to competition,
8593arbitrary, or capricious.
8596As such, Xerox must establish whether the Department's action to
8606award the ITN to SMI was contrary to the ITN specifications;
8617contrary to gov erning statutes, applicable rules , or policies ;
8626and was clearly erroneous, contrary to competition, arbitrary , or
8635capricious. § 120.57(3)(f ), Fla. Stat. (2014); Florida Dep't of
8645Transp. v. J.W .C. Co. , 396 So. 2d 778, 787 (Fla. 1st DCA 1981).
865972. An agen cy action will be found to be "clearly
8670erroneous" if the agency's interpretation conflicts with the
8678plain and ordinary intent of the law. See Colbert v. Dep't of
8690Health , 890 So. 2d 11 65, 1166 (Fla. 1st DCA 2004). In such a
8704case, "judicial deference need not be given" to the agency's
8714interpretation. Id. An agency action will be found to be
"8724clearly erroneous" if it is without rational support, and,
8733consequently, the trier - of - fact has a "definite and firm
8745conviction that a mistake has been committed." U .S. v. U.S.
8756Gypsum Co. , 333 U.S. 364, 395 (1948).
876373. An act is "contrary to competition" if it unreasonably
8773interferes with the objectives of competitive bidding, which are:
8782[T]o protect the public against collusive
8788contracts; to secure fair competition upon
8794equal terms to all bidders; to remove not
8802only collusion but temptation for collusion
8808and opportunity for gain at public expense;
8815to close all avenues to favoritism and fraud
8823in its various forms; to secure the best
8831values for the county at the lowest possible
8839expense; and to afford equal advantage to all
8847desiring to do business with the county, by
8855affording an opportunity for an exact
8861comparison of bids.
8864Wester v. Belote , 103 Fla. 976, 981, 138 So. 721, 723 - 24 ( 1930).
8879See SYSLOGIC Tech. Servs., In c. v. S. Fl a . Water Mgm t . Dist . ,
8896Case No. 01 - 4385BID (Fla. DOAH Jan. 18, 2002; SFWMD Mar. 6,
89092002).
891074. "An action is 'arbitrary if it is not supported by
8921logic or the necessary facts,' and 'capricious if it is adopted
8933without thought or reason or is irr ational.'" Hadi v. Liberty
8944Behavioral Health Corp. , 927 So. 2d 34, 38 - 39 (Fla. 1st DCA 2006)
8958and Agrico Chem. Co. v. Dep't of Envtl. Reg. , 365 So. 2d 759, 763
8972(Fla. 1st DCA 1978). Thus, when reviewing a contract award
8982decision to determine whether it is arbitrary or capricious, it
8992must be upheld if the action is justifiable under any analysis
9003that a reasonable person would use to reach a decision of similar
9015weight. As long as the agency has acted in good faith, its
9027judgment should not be interfered with, even if reasonable men
9037could differ and even if the decision may seem erroneous to some
9049persons. Colbert v. Dep't. of Health , 890 So. 2d 1165 (Fla. 1st
9061DCA 2004); State Contracting & Eng'g Corp. v. Dep ' t. of Transp. ,
9074709 So. 2d 607, 610 (Fla. 1st DCA 199 8); and Volume Servs. Div.
9088v. Canteen Corp. , 369 So. 2d 391, 395 (Fla. 2d DCA 1979) ( quoted
9102in System Dev. Corp. v. Dep't of Health & Rehab. Servs. , 423 So.
91152d 433, 434 (Fla. 1st DCA 1982) ) . In that regard, the ITN in
9130Section 3.1.9.3 clearly reserves to t he Department the right to
9141determine whether a reply meets the material requirements of the
9151ITN. Additionally, Section 2.7 of the ITN, as well as paragraph
916216 of the General Conditions, reserve to the Department the right
9173to waive minor irregularities.
917775 . In this case, both replies contained a surety letter of
9189commitment as required by Section 7.13.1.1 of the ITN. The
9199evidence showed that both letters were not simply letters of
9209reference from a bonding company but were letters of commitment
9219from such co mpanies and were intended as such by those bonding
9231agents. As such, both Xerox and SMI were responsive to the
9242surety commitment requirements of the ITN.
924876. The evidence also showed that Attachment K did not
9258require that the Department's estimated number of transactions be
9267used by a vendor in its transaction rate calculation. Unlike
9277Veolia Transportation Services, Inc. v. Commission for the
9285Transportation Disadvantaged , DOAH Case No. 08 - 1636BID (DOAH
9294July 9, 2008), where the methodology for the rate cal culation by
9306a vendor was required to be used by that vendor in responding to
9319a request for proposal, the Department in this ITN did not
9330require a specific methodology or use of a specific cost estimate
9341by a vendor in calculating its transaction rate on Att achment K.
9353The Department's estimate was only required to be used in the
9364baseline compensation calculation on Attachment L , which use
9372normalized the baseline compensation calculation so that the
9380Department could make an apples - to - apples comparison of that
9392cost. Thus, the Department's calculation requirements on forms K
9401and L were reasonable and SMI met the requirements of the ITN in
9414completing its Attachment s K and L. Morphotrust USA v.
9424Dep't of Transp. and Solutions Thru Software, Inc. , DOAH Case
9434No. 12 - 2917BID (DOAH Dec. 7, 2012; FDHSMV Jan. 7, 2013).
944677. In Morphotrust USA v. Department of Transportation and
9455Solutions Thru Software, Inc. , the administrative law judge found
9464that the ITN did not impose a mandatory requirement or condition
9475as to the substance of a form , or direct that the pricing form be
9489filled out in a certain way. In reaching the decision, the
9500administrative law judge recognized that while the use of the
9510terms, "shall," "must" and "will" in the solicitation indicated a
9520mandatory re quirement or condition, the only portion of the ITN
9531that was mandatory was the requirement that "proposal forms must
9541be submitted with [the] proposal" since it was the only section
9552in the ITN specification that used the mandatory term. Id. at
956321. ¶ 79.
956678 . Like Morphotrust , the ITN required that a vendor submit
9577Attachment M. Except for two categories of costs, the ITN did
9588not require a vendor to seek reimbursements of any costs or to
9600complete the form in a specific way. In this case, both SMI a nd
9614Xero x submitted A ttachment M, did not deviate from the ITN
9626requirements , and were responsive on this requirement.
963379. However, the evidence did demonstrate that SMI's reply
9642deviated from the ITN since it did not contain renewal cost
9653information and did not have an attachment containing copies of
9663SMI's Incident Control Policy and Procedures and Change
9671Management Policy and Procedures. Importantly, not every
9678deviation from an ITN makes a reply non - responsive to the ITN.
9691The court in Robinson Electrical Co. v . Dade County , 417 So. 2d
97041032, 1034 (Fla. 3d DCA 1982), discussed the criteria for
9714determining whether a variance is a material deviation or a minor
9725irregularity and stated:
9728Although a bid containing a material variance
9735is unacceptable, Glatstein v. City of Miami ,
9742399 So. 2d 1005 (Fla. 3d DCA), rev. denied,
9751407 So. 2d 1102 (Fla. 1981), not every
9759deviation from the invitation is material.
9765In determining whether a specific
9770noncompliance constitutes a substantial and
9775hence non - waivable irregularity, the cou rts
9783have applied two criteria - first, whether the
9791effect of a waiver would be to deprive the
9800[government agency] of its assurance that
9806the contract will be entered into, performed
9813and guaranteed according to its specified
9819requirements, and second, whether i t is of
9827such a nature that its waiver would adversely
9835affect competitive bidding by placing a
9841bidder in a position of advantage over other
9849bidders or by otherwise undermining the
9855necessary common standard of competition.
9860In application of the general prin ciples
9867above discussed, sometimes it is said that a
9875bid may be rejected or disregarded if there
9883is a material variance between the bid and
9891the advertisement. A minor variance,
9896however, will not invalidate the bid. In
9903this context a variance is material i f it
9912gives the bidder a substantial advantage
9918over the other bidders, and thereby
9924restricts or stifles competition. 10
9929McQuillan, Municipal Corporations § 29.65 (3d
9935Ed. Rev. 1981) (footnotes omitted); see Harry
9942Pepper & Associates, Inc. v. City of Cape
9950Co ral , (Fla. 3d DCA 1982).
995680. In that regar d, section 287.057(13), Florida Statutes ,
9965grants an agency the authority to renew a contract under certain
9976conditions and requires that a reply to an invitation to
9986negotiate provide the "price" of the "servi ce to be renewed."
9997Section 287.057(13) states:
10000Contracts for commodities or contractual
10005services may be renewed for a period that may
10014not exceed 3 years or the term of the
10023original contract, whichever is longer.
10028Renewal of a contract for commodities or
10035c ontractual services must be in writing and
10043is subject to the same terms and conditions
10051set forth in the initial contract and any
10059written amendments signed by the parties. If
10066the commodity or contractual service is
10072purchased as a result of the solicitation of
10080bids, proposals, or replies, the price of the
10088commodity or contractual service to be
10094renewed must be specified in the bid,
10101proposal, or reply, except that an agency may
10109negotiate lower pricing. A renewal contract
10115may not include any compensation for c osts
10123associated with the renewal. Renewals are
10129contingent upon satisfactory performance
10133evaluations by the agency and subject to the
10141availability of funds . . . . (emphasis
10149added ) .
1015281. In Flordia Department of Environmental Protection v.
10160ContractPoint Florida Parks, L.L.C. , 986 So. 2d 1260 , 1265 (Fla.
101702008), the Florida S upreme Court stated:
10177This Court has long held that a "statute must
10186be given its plain and obvious meaning."
10193Holly v. Auld , 450 So. 2d 217, 219 (Fla.
102021984) (quoting A.R. Douglass, In c. v.
10209McRainey , 102 Fla. 1141, 137 So. 157, 159
10217(Fla. 1931)). If the language of the statute
10225is "clear and unambiguous and conveys a clear
10233and definite meaning" there is no need to
10241resort to statutory construction. Id.;
10246accord Forsythe v. Longboat Key B each
10253Erosion Control Dist. , 604 So. 2d 452, 454
10261(Fla. 1992). In interpreting section 11.066,
10267however, we cannot read subsection (3) in
10274isolation, but must read it within the
10281context of the entire section in order to
10289ascertain legislative intent for the
10294pr ovision. Id. at 455 ("Every statute must
10303be read as a whole with meaning ascribed to
10312every portion and due regard given to the
10320semantic and contextual interrelationship
10324between its parts." (quoting Fleischman v.
10330Dep't of Prof'l Reg. , 441 So. 2d 1121, 1123
10339(Fla. 3d DCA 1983))). A "statute should be
10347interpreted to give effect to every clause in
10355it, and to accord meaning and harmony to all
10364of its parts" and is not to be read in
10374isolation, but in the context of the entire
10382section. Jones v. ETS of New Orleans , Inc. ,
10390793 So. 2d 912, 914 - 15 (Fla. 2001) (quoting
10400Acosta v. Richter , 671 So. 2d 149, 153 - 54
10410(Fla. 1996)).
1041282. Importantly, s ection 287.057(13) is part of a statutory
10422scheme that provides a continuum of competitive procurement
10430options to the State. As indicated earlier, that continuum runs
10440from invitations to bid, through requests for proposals, to
10449invitations to negotiate. Each of these procurement processes
10457has statutory requirements associated with it. As part of that
10467statutory scheme and to unders tand the meaning of the term
"10478price" used in the above - quoted section, subsection (13) must be
10490read in pari materia with the rest of section 287.057.
1050083. Under sections 287.057 (1) (a)2. and (1) (b)3.b.,
10509governing invitations to bid and requests for proposal s, the
"10519price" for each year of the re newal must be specified in the
10532vendor's submission. In section 287.057 (1) (b)3.b. , "price" for
10541each year of renewal must also be used to evaluate a vendor's
10553proposal under a request for proposal. Additionally, subsect ions
10562287.057 (1) (a)3. and (1) (b)3.c. governing invitations to bid and
10573requests for proposals, require that the vendor's submission be
10582evaluated based on the total "cost" for each year of the
10593contract, including renewal years. Importantly, none of the
10601renew al requirements related to evaluation of renewal prices or
10611costs associated with the other procurement methods under section
10620287.057 are required under subsection (1) (c) of the statute
10630governing invitations to negotiate. Neither price nor cost are
10639defined in c hapter 287. However, the use of the terms "price"
10651and "cost" in the same statute indicates that such terms are not
10663synonymous with each other, but have more specific procurement -
10673related meanings.
1067584. In purchasing, price is not the same as cost. Price is
10687the quantity of one thing, e.g. , money, that is exchanged or
10698demanded in barter or sale for another thing, e.g. , SDU services,
10709of which cost is a component. Cost is the monetary value of
10721material, effort, products, resources, etc. which go into
10729p roducing and delivering a good or service. See "What is Price?"
10741BusinessDictionary.com. Web. 16 Feb. 2015.
"10747What is Cost?" BusinessDictionary.com. Web. 16 Feb. 2015.
1075685. In this case, both vendors stated the price of the 10767service to be renewed in their Attachment O. Like the statute, 10778the ITN, in this case, provided that renewal was to be on the 10791same terms and conditions as the initial co ntract. Therefore, 10801unless a vendor specified a separate section 287.057(13) "price" 10810for the "service to be renewed," the vendor's original price was 10821the renewal price under both the statute and the terms of the 10833ITN. Since neither vendor specified a separ ate "price" for the "10844service to be renewed , " the price for such renewal was the 10855proposed contract price in that vendor's Attachment O. As such, 10865both Xerox and SMI met the statutory requirement of section 10875287.057(13). 1087686. The ITN did require that renewal costs , not price, be 10887summarized in a vendor's reply. In regards to these costs, the 10898evidence demonstrated that such costs were non - essential to the 10909ITN and were not required for a vendor to be responsive to the 10922ITN. Given the non - essential nature of this information, the 10933evidence did not demonstrate that any advantage or disadvantage 10942resulted to any vendor as a result of such information not being 10954provided by SMI. Similarly, the evidence did not demonstrate 10963that the competitive procurement process was im paired by SMI not 10974providing this cost information. 1097887. Further, the initial cost replies were used to score 10988vendors for the purpose of the Department determining the vendors 10998with which it would conduct negotiations. Neither renewal 11006pricing nor costs we re used in scoring the vendors' replies. 11017Such scoring demonstrates the insignificance of renewal cost 11025information under the ITN. The evidence did not demonstrate that 11035SMI received a competitive advantage by failing to state in its 11046cost reply that there w ould be no change in its cost during any 11060renewal period. The evidence did demonstrate that failure to 11069provide such information was a minor deviation from the ITN 11079criteria and could be properly waived by DOR. Juvenile Services 11089Program, Inc. v. Dep't of Ju venile Justice , Case No. 07 - 1975BID, 11102(DOAH Oct. 31, 2007 ; OJJ Nov. 30, 2007 ). Thus, not providing 11114such information was properly waived by the Department. The 11123evidence did not demonstrate that the Department's actions were 11132clearly erroneous, contrary to c ompetition, arbitrary , or 11140capricious. 1114188. Finally, Xerox contends that the posting of the 11150Department's intended contract award to SMI , before negotiations 11158were concluded , violated Florida law or materially deviated from 11167the ITN specifications. However , s ection 287.057 does not 11176require that posting of an award decision be held until the 11187conclusion of negotiations with a vendor. Section 11194287.057(1)(c)4 . states, in pertinent part: 11200[A ]fter negotiations are conducted , the 11206agency shall award the contract to the 11213responsible and responsive vendor that the 11219agency determines will provide the best value 11226to th e state . . . (emphasis added ). 11236Further, the ITN process provides agencies more discretion in 11245negotiating with vendors than does the RFP process described i n 11256sect ion 287.057(b) . See Cushman and Wakefield of Fla., Inc. v. 11268Dep't of Mgmt. Servs. , DOAH Case No. 13 - 3894BID, ¶ 102 (DOAH 11281Jan. 24, 2014; DMS Feb. 5, 2014) (ALJ re cognized there is no 11294provision under Florida law that prohibits an agency from 11303attemptin g to maximize the best value to the state and, as a 11316result, rejected an argument that an agency is prohibited from 11326asking vendors to modify their price once a BAFO has been 11337submitted since this would frustrate the agency's ability to 11346maximize the best valu e for the state). Thus, the statute does 11358not require that negotiations be "concluded" but only that they 11368have been "conducted" prior to the contract award. In that 11378regard, DOR did not violate the statute by posting its intended 11389award prior to finalizat ion of the contract with SMI. 1139989. However in this case, the ITN refers to the "11409conclusion" of negotiations prior to the Negotiation Team 11417requesting a BAFO or posting a notice of intent to award the 11429contract. On the other hand, S ection 2.6.9 contemplates that 11439additional discussions regarding the contract could occur after 11447the contract award. Clearly, the reference to the conclusion of 11457negotiations in the ITN does not mean that the contract document 11468itself has been completed. 1147290. In this case, the evide nce demonstrated that extensive 11482negotiations were conducted between the Department's Negotiation 11489Team a nd SMI prior to posting of the Notice of Intent to A ward 11504the contract to SMI. The evidence further demonstrated tha t the 11515negotiations between the N egoti ation T eam and SMI resulted in a 11528meeting of the minds regarding the services that SMI would be 11539performing and the price for those services. Further, the 11548evidence showed that the negotiations had concluded in all 11557substantial respects prior to posting of th e Notice of Intent to 11569Award the contract to SMI. The evidence did not demonstrate that 11580such posting was contrary to competition, impeded the nature of 11590competitive procurement or created an unfair advantag e in the 11600award. Additionally, t he evidence did not demonstrate that the 11610timing of t he Department's posting of its Notice of Intent to 11622A ward the contract to SMI was contrary to any statute, rule, 11634policy , or ITN specification and was, at worst, a minor deviation 11645from those specifications. 1164891. Therefore, th e Department's interpretation of the ITN 11657as not requiring the contract document itself, including 11665Attachment A to the contract document, to be finalized prior to 11676contract award , as long as the substantive terms and conditions 11686and price have been negotiated , is certainly a rational and 11696reasonable interpretation of its own specifications that should 11704not be disturbed. 1170792. The evidence did not demonstrate that the Department's 11716intended award of a contract to SMI deviated from governing 11726statutes, applicable rul es , or policies of the Department or 11736reasonable interpretations of the ITN specifications. Further, 11743there was no evidence that the Department's decision was clearly 11753erroneous, contrary to competition, arbitrary, or capricious. 11760Therefore, the award of the contract arising out of the ITN to 11772SMI should stand and this protest should be dismissed. 11781RECOMMENDATION 11782Based on the foregoing Findings of Fact and Conclusions of 11792Law, it is, therefore, 11796RECOMMENDED that the Respondent, Florida Department of 11803Revenue, en ter a final order dismissing the protest of 11813Petitioner, Xerox State and Local Solutions, Inc. , and approving 11822the award of the contract to Intervenor, Systems and Methods, 11832Inc. 11833DONE AND ENTERED this 18 th day of February , 2015 , in 11844Tallahassee, Leon County, F lorida. 11849S 11850DIANE CLEAVINGER 11852Administrative Law Judge 11855Division of Administrative Hearings 11859The DeSoto Building 118621230 Apalachee Parkway 11865Tallahassee, Florida 32399 - 3060 11870(850) 488 - 9675 11874Fax Filing (850) 921 - 6847 11880www.doah.state.f l.us 11882Filed with the Clerk of the 11888Division of Administrative Hearings 11892this 18 th day of February, 2015 . 11900ENDNOTE S 119021/ Xerox designated the follow ing excerpt from the audio tape: 1191317:40 - 20:32. SMI cross - designated the following excerpt to 11924Xerox's Exhibit 1 7: 17:43 - 23:38. Xerox then added the following 11936excerpt: 17:39 - 24:31. 119402/ Statutory requireme nts such as the requirement in s ection 11951287.057(13) cannot be waived by an agency. 119583/ The Department's response to October 24, 2014, vendor question 1196824 about Attachment O does not clarify whether amounts for the 11979cost items in Attachment M were mandatory since the Department's 11989answer also indicated that Attachment M should include expenses 11998for which the vendor wishes to be reimbursed. Notably, 12007Attachment M was not amended as a result of the Department's 12018response to question 24. Moreover, the Department's response to 12027October 24, 2014, vendor question 53 does not resolve the issue 12038regarding Attachment M costs since the Department's response 12046seemingly made teleco mmunications costs mandatory by use of the 12056word "shall" in relation to reporting those costs on 12065Attachment M. Again, Attachment M was not amended as a result of 12077the D epartment's response to question 53. Thus, Xerox's reply 12087was responsive to the ITN even though it did not include 12098seemingly mandatory telecommunications costs in its reply. 12105COPIES FURNISHED: 12107Cindy Horne, Esquire 12110Department of Revenue 12113Post Office Box 6668 12117Tallahassee, Florida 32314 - 6668 12122(eServed) 12123W. Robert Vezina, III, Esquire 12128Vezina, Lawrence and Piscitelli, P.A. 12133413 East Park Avenue 12137Tallahassee, Florida 32301 12140(eServed) 12141Mia L. McKown, Esquire 12145Holland and Knight, LLP 12149Post Office Drawer 810 12153Tallahassee, Florida 32302 - 1809 12158(eServed) 12159Nancy L. Staff, General Counsel 12164Department of Reven ue 12168Post Office Box 6668 12172Tallahassee, Florida 32314 - 6668 12177(eServed) 12178Marshall Stranburg, Executive Director 12182Department of Revenue 12185Post Office Box 6668 12189Tallahassee, Florida 32314 - 6668 12194(eServed) 12195NOTICE OF RIGHT TO SUBMIT EXCEPTIONS 12201All parties have the ri ght to submit written exceptions within 122121 0 days from the date of this Recommended Order. Any exceptions 12224to this Recommended Order should be filed with the agency that 12235will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 03/20/2015
- Proceedings: Respondent, Department of Revenue's, Response to Exceptions filed by Petitioner Xerox's State & Local Solutions, Inc. filed.
- PDF:
- Date: 03/20/2015
- Proceedings: Systems & Methods, Inc.'s Response to Xerox's Exceptions to Corrected Recommended Order filed.
- PDF:
- Date: 02/27/2015
- Proceedings: Corrected Recommended Order (hearing held August 6 and 7, 2014). CASE CLOSED.
- PDF:
- Date: 02/27/2015
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 02/20/2015
- Proceedings: Transmittal letter from Claudia Llado returning the Department of Revenue's Exhibits, which were not admitted into evidence to Respondent.
- PDF:
- Date: 02/19/2015
- Proceedings: Transmittal letter from Claudia Llado returning Petitioner's Exhibits, which were not admitted into evidence to Petitioner.
- PDF:
- Date: 02/18/2015
- Proceedings: Recommended Order (hearing held August 6 and 7, 2014). CASE CLOSED.
- PDF:
- Date: 02/18/2015
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 01/07/2015
- Proceedings: Attorney Matthew H. Mears' Unopposed Motion for Order Permitting Withdrawal from Representation filed.
- PDF:
- Date: 12/08/2014
- Proceedings: Order Granting Respondent`s Motion to Discontinue Abatement and Request Issuance of Recommended Order.
- PDF:
- Date: 12/04/2014
- Proceedings: Respondent's Motion to Discontinue Abatement and Request Issuance of Recommended Order filed.
- PDF:
- Date: 09/11/2014
- Proceedings: Order Placing Case in Abeyance (parties to advise status by December 15, 2014).
- PDF:
- Date: 09/11/2014
- Proceedings: Systems and Methods, Inc.'s Reply to Xerox's Response to Department of Revenue's Motion to Abate the Proceedings filed.
- PDF:
- Date: 09/08/2014
- Proceedings: System and Methods, Inc.'s Memorandum in Opposition to the Department of Revenue's Motion to Abate the Proceedings filed.
- PDF:
- Date: 09/08/2014
- Proceedings: Respondent's Withdrawal of Respondent's Motion Requesting that the Division of Administrative Hearings Relinquish Jurisdiction and Motion to Abate Proceedings filed.
- PDF:
- Date: 09/04/2014
- Proceedings: System and Methods, Inc.'s Memorandum In Opposition to the Department of Revenue's Motion to Relinquish Jurisdiction filed.
- PDF:
- Date: 09/03/2014
- Proceedings: Respondent's Motion Requesting that Division of Administrative Hearings Relinquish Jurisdiction filed.
- Date: 08/22/2014
- Proceedings: Transcript Volumes I-III (not available for viewing) filed.
- PDF:
- Date: 08/22/2014
- Proceedings: Order Granting Extension of Time to File Proposed Recommended Orders.
- PDF:
- Date: 08/20/2014
- Proceedings: Xerox's Unopposed Motion for Extension of Time to File Proposed Recommended Orders filed.
- Date: 08/06/2014
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 08/06/2014
- Proceedings: Order Granting in Part Xerox`s Motion for Leave to File Second Amended Formal Written Protest Petition.
- PDF:
- Date: 08/05/2014
- Proceedings: Xerox's Motion in Limine Regarding Alleged Curing of SMI's Reply Deficiencies filed.
- PDF:
- Date: 08/05/2014
- Proceedings: Intervenor, SMI's Joinder in Respondent's Response in Opposition to Xerox's Motion for Santions for Spoliation of Evidence filed.
- PDF:
- Date: 08/05/2014
- Proceedings: Xerox's Motion in Limine Regarding Which Vendor Presents the Best Value to the State filed.
- PDF:
- Date: 08/05/2014
- Proceedings: Respondent's Response to Xerox's Motion for Sanctions for Spoliation of Evidence filed.
- PDF:
- Date: 08/05/2014
- Proceedings: Notice of Filing (exhibits and depositions) (exhibits not available for viewing) filed.
- PDF:
- Date: 08/05/2014
- Proceedings: (Intervenor's) Objection to Xerox's Motion for Leave to File Second Amended Formal Written Protest Petition or, in the Alternative, Motion to Dismiss or Strike filed.
- PDF:
- Date: 08/04/2014
- Proceedings: (Intervenor's) Notice of Objection to Xerox's Motion for Leave to File Second Amended Formal Written Protest Petition filed.
- PDF:
- Date: 08/04/2014
- Proceedings: Respondent's Motion for Extension of Time to file Pre-hearing Stipulation filed.
- PDF:
- Date: 08/04/2014
- Proceedings: Xerox's Motion for Leave to File Second Amended Formal Written Protest Petition filed.
- PDF:
- Date: 08/01/2014
- Proceedings: Order Granting Xerox`s Motion for Leave to File Amended Formal Written Protest Petition.
- PDF:
- Date: 07/31/2014
- Proceedings: Xerox's Notice that the Department and SMI Do Not Oppose Xerox's Motion for Leave to File Amended Formal Written Protest Petition filed.
- PDF:
- Date: 07/30/2014
- Proceedings: Xerox's Motion for Leave to File Amended Formal Written Protest Petition filed.
- PDF:
- Date: 07/29/2014
- Proceedings: Amended Notice of Taking Deposition (of Department of Revenue's Corporate Representative) filed.
- PDF:
- Date: 07/28/2014
- Proceedings: Xerox's Notice of Taking Deposition (of Agency Representative for Department of Revenue) filed.
- PDF:
- Date: 07/28/2014
- Proceedings: Amended Notice of Taking Depositions (of Mark Huff, Craig Curry, Connie Beach, and Stan Eatman) filed.
- PDF:
- Date: 07/24/2014
- Proceedings: Notice of Taking Depositon (of Systems & Methods, Inc.'s Corporate Representative) filed.
- PDF:
- Date: 07/23/2014
- Proceedings: Systems & Methods, Inc.'s Notice of Taking Xerox State & Local Solutions, Inc.'s Corporate Representative Deposition filed.
- PDF:
- Date: 07/21/2014
- Proceedings: Xerox's Notice of Serving Verified Responses to SMI's First Set of Interrogatories filed.
- PDF:
- Date: 07/17/2014
- Proceedings: Amended Notice of Taking Deposition (of Bo Searce, Shannon Herold, and Beth Doredant) filed.
- PDF:
- Date: 07/17/2014
- Proceedings: Amended Notice of Taking Deposition (of John Kinneer and Max Smart) filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Notice of Taking Deposition (of Stan Eatman, Debbie Stephens, and Chris Butterworth) filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Notice of Taking Deposition (of Mark Huff, Craig Curry, and Connie Beach) filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Notice of Taking Deposition (of Babs Johnson and Tom Mato) filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Notice of Taking Deposition (of Maz Smart, Shannon Herold, and Beth Doredant) filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Notice of Taking Deposition (of Clark Rogers, Steve Updike, and Nancy Luja) filed.
- PDF:
- Date: 07/16/2014
- Proceedings: Notice of Taking Deposition (of John Kinneer and Bo Searce) filed.
- PDF:
- Date: 07/09/2014
- Proceedings: Systems & Methods, Inc.'s Responses to Xerox State & Local Solutions, Inc.'s First Request for Admissions filed.
- PDF:
- Date: 07/09/2014
- Proceedings: Systems & Methods, Inc.'s Responses and Objections to Xerox State & Local Solutions, Inc.'s First Request for Production of Documents to SMI filed.
- PDF:
- Date: 07/09/2014
- Proceedings: Systems & Methods, Inc.'s Notice of Service of Answers and Objections to Xerox State & Local Solutions, Inc.'s First Set of Interrogatories filed.
- PDF:
- Date: 07/03/2014
- Proceedings: (Intervenor's) Unopposed Motion for Entry of Protective Order Regarding Confidential Information filed.
- PDF:
- Date: 07/02/2014
- Proceedings: Xerox's Notice of Serving First Set of Interrogatories to SMI filed.
- PDF:
- Date: 06/30/2014
- Proceedings: Xerox's Notice of Serving Unverified Responses to SMI's First Set of Interrogatories filed.
- PDF:
- Date: 06/30/2014
- Proceedings: Respondent's Response to Xerox's First Request for Admissions filed.
- PDF:
- Date: 06/30/2014
- Proceedings: Respondent's Response to Petitioner's First Request for Production to the Department filed.
- PDF:
- Date: 06/30/2014
- Proceedings: Respondent's Notice of Serving Responses to Petitioner's First Set of Interrogaties to the Department filed.
- PDF:
- Date: 06/25/2014
- Proceedings: Intervenor, Systems & Methods, Inc.'s First Request for Admissions to Petitioner filed.
- PDF:
- Date: 06/25/2014
- Proceedings: Intervenor, Systems & Methods, Inc.'s Notice of First Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 06/25/2014
- Proceedings: Intervenor, Systems & Methods, Inc.'s First Request for Production of Documents to Petitioner filed.
- PDF:
- Date: 06/24/2014
- Proceedings: Xerox's Notice of Serving First Set of Interrogatories to the Department filed.
- PDF:
- Date: 06/24/2014
- Proceedings: Notice of Hearing (hearing set for August 6 through 8, 2014; 9:30 a.m.; Tallahassee, FL).
- PDF:
- Date: 06/23/2014
- Proceedings: Order Granting Petition to Intervene (Systems and Methods, Inc.).
- Date: 06/23/2014
- Proceedings: CASE STATUS: Pre-Hearing Conference Held.
- PDF:
- Date: 06/20/2014
- Proceedings: Notice of Telephonic Status Conference (status conference set for June 23, 2014; 11:00 a.m.).
Case Information
- Judge:
- DIANE CLEAVINGER
- Date Filed:
- 06/16/2014
- Date Assignment:
- 06/16/2014
- Last Docket Entry:
- 03/20/2015
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Cindy Horne, Esquire
Address of Record -
Jeffrey J Kelly, Esquire
Address of Record -
Eduardo S. Lombard, Esquire
Address of Record -
Mia L. McKown, Esquire
Address of Record -
Megan S. Reynolds, Esquire
Address of Record -
William Robert Vezina, Esquire
Address of Record -
Karen D. Walker, Esquire
Address of Record -
Mia L McKown, Esquire
Address of Record -
Karen D Walker, Esquire
Address of Record -
William Robert Vezina, III, Esquire
Address of Record