14-002798BID Xerox State And Local Solutions, Inc. vs. Department Of Revenue
 Status: Closed
Recommended Order on Wednesday, February 18, 2015.


View Dockets  
Summary: Evidence showed intended ITN award appropriate. Neither statute nor ITN required negotiations to be concluded before intended award posted. Renewal price, unless separately stated, was the proposed contract price.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8XEROX STATE AND LOCAL SOLUTIONS,

13INC.,

14Petitioner,

15vs. Case No . 14 - 2798BID

22DEPARTMENT OF REVENUE,

25Respondent,

26and

27SYSTEMS AND METHODS, INC.,

31Intervenor.

32_______________________________/

33RECOMMENDED ORDER

35Pursuant to Notice, this cause came on for formal hearing

45before Diane Cleavinger, a designated Administrative Law Judge of

54the Division of Administrative Hearings, on August 6 and 7, 2014,

65in Tallahassee, Florida.

68APPEA RANCES

70For Petitioner: Eduardo S. Lombard, Esquire

76W. Robert Vezina, III, Esquire

81Megan Reynolds, Esquire

84Andrew Foti, Esquire

87Vezina, Lawrence and Piscitelli, P.A.

92413 East Park Avenue

96Tallahassee, Florida 32301

99For Respondent: Cindy Horne, Esquire

104Jeffrey Kelly, Esquire

107Department of Revenue

110Post Office Box 6668

114Tallahassee, Florida 32314 - 6668

119For Intervenor: Karen D. Walker, Esquire

125Mia McKown, Esquire

128Holland and Knight, LLP

132Post Office Drawer 810

136Tallahassee, Flori da 32302 - 1809

142STATEMENT OF THE ISSUE

146The issue in this proceeding is whether the Respondent's

155intended award of Invitation to Negotiate (ITN) 13/14 - 01 was

166contrary to the Department's governing statutes, rules or

174policies; contrary to the solicitation sp ecifications; and was

183clearly erroneous, contrary to competition, arbitrary or

190capricious.

191PRELIMINARY STATEMENT

193On August 27, 2013, Respondent, Department of Revenue (DOR

202or Department), issued Invitation to Negotiate 13/14 - 01, entitled

"212State Disbursemen t Unit." On December 2, 2013, replies to the

223ITN were submitted. The vendors submitting replies were Xerox

232State and Local Solutions, Inc. (Xerox) , and Systems and Methods,

242Inc. (SMI). On May 19, 2014, DOR posted its intent to award the

255contract to Inte rvenor, SMI.

260By Formal Written Protest dated June 2, 2014, Xerox timely

270protested DOR's intended decision to award the contract to SMI.

280On June 16, 2014, the matter was forwarded to the Division of

292Administrative Hearings (DOAH). That same day SMI file d a

302Petition to Intervene which was granted by Order issued June 23,

3132014.

314Prior to hearing, Xerox's Motion for Leave to File Amended

324Formal Written Protest Petition was granted by Order dated

333August 1, 2014. Additionally, Xerox's Motion for Leave to File

343Second Amended Formal Written Protest Petition was granted in

352part by Order dated August 16, 2014, but denied as to paragraphs

36474 through 82 of the Second Amended Petition since said

374paragraphs were untimely challenges to the ITN specifications.

382At hearin g, Joint Exhibits 1 through 12 were admitted into

393evidence. Xerox called four witnesses to testify: John Kinneer,

402Steve Updike, John Polk, and Michael Deckelman. Xerox's Exhibits

411numbered 1, 2, 4, 5, 10 through 16, portions of Exhibit 17 1/ ,

424Exhibit 32, portions of Exhibit 40 not rela ted to scoring, and

436Exhibits 46 through 54 were admitted into evidence. Xerox also

446proffered Exhibits 6, 8, 31, 33 through 39, portions of

456Exhibit 40 rela ted to scoring, and Exhibits 41 through 45. DOR

468called two witnesses to testify: Thomas Mato and Clark Rogers.

478Additionally, DOR's Exhibit 5 was admitted into evidence. SMI

487did not present any witness test imony. However, SMI Exhibits 1

498through 3 were admitted into evidence.

504The three - volume Transcript was filed with DOAH on

514August 22, 2014. Petitioner and Intervenor filed Proposed

522Recommended Orders on September 4, 2014. Respondent filed its

531Proposed Recommended Order on September 3 , 2014. After Proposed

540Recommended Orders were filed, the case was placed in abeya nce

551due to an action in Circuit Court involving Florida's Sunshine

561Law. Thereafter, DOR filed a Motion to remove the case from

572abeyance. The Motion was granted and the case proceeded to this

583Recommended Order which considered the parties earlier - filed

592Pr oposed Recommended Orders.

596FINDINGS OF FACT

5991. The Department is designated by section 409.2257,

607Florida Statutes (2014) , as the Title IV - D agency for the State

620of Florida. As such, it is responsible for the administration of

631the Child Support Enforcemen t program that is required in all

642states by the Federal Social Security Act. See § 409.2577, Fla.

653Stat.

6542 . As part of its duties under c hapter 409, the Department

667is authorized to solicit proposals from, and to contract with,

677private contractors to devel op, operate, and maintain a state

687disbursement unit (SDU). The SDU is responsible for processing,

696collecting and disbursing payments for most child support cases

705in Florida. The current contractor for the SDU is Xerox whose

716contract will expire on Februa ry 28, 2015.

7243. In general, Florida procurement law provides a continuum

733of competitive procurement processes running from invitations to

741bid, through requests for proposals, to invitations to negotiate.

750Invitations to bid are used where specifications c an be stated

761with certainty with the primary issue being price. Invitations

770to negotiate, on the other end of the procurement spectrum, are

781used to purchase services when state agencies need to "determine

791the best method for achieving a specific goal or s olving a

803particular problem." § 287.057(1)(c), Fla. Stat. (2014).

8104. In essence, an ITN contains the process a state agency

821follows in awarding a contract and the criteria to which a vendor

833should reply in order to be considered responsive to the ITN.

844Under an invitation to negotiate and even though a reply must be

856responsive to the invitation, specifications generally are more

864fluid and less mandatory. Price, while important, is negotiable.

873Indeed, an agency may "reply shop" the terms, including pri ce, of

885one vendor's reply against a competitor's reply in seeking

894revisions to that vendor's reply. As such, contract price is a

905more fluid concept under an ITN and is not the primary

916consideration in an ITN.

9205. In this case, the Department was seeking a solution for

931processing, collecting and paying child support payments based on

940a negotiated per transaction rate resulting from such SDU

949services plus negotiated service costs associated with the

957operation of the SDU. In fact, contracting for a transac tion -

969rate - based price was one of the prime considerations under this

981ITN because the Department felt it could gain significant

990contract sav ings by utilizing a transaction - rate - based pricing

1002scheme in its negotiations. Towards that end, the Department

1011issu ed Invitation to Negotiate 13/14 - 01 on August 27, 2013,

1023soliciting service solutions for the operation of the SDU.

10326. Prior to receiving replies to the ITN, the Department

1042issued seven addenda to the ITN, provided several replacement

1051pages to the ITN an d answered numerous vendor questions regarding

1062the ITN.

10647. After the release of the ITN and the seven addenda,

1075there was no protest filed pursuant to section 120.57, Florida

1085Statutes, regarding the ITN's specifications. As such, any

1093objection to those specifications was waived by Petitioner and

1102Intervenor.

11038. In this case, the ITN required a vendor's reply to be in

1116a particular format. Specifically, the ITN required that a

1125vendor's reply consist of two comp onents presented in two

1135multiple - tabbed binde rs: the Administrative/Technical Reply

1143(Technical Reply) and the Cost Data Reply (Cost Reply).

1152Technical Replies were to contain non - cost information such as

1163corporate capability, proposed solution technical components,

1169quality assurance and monitoring, and a variety of attachments.

1178Cost Replies were to contain a vendor's Transaction Rate,

1187Baseline Compensation, Reimbursable Costs, and other cost - related

1196information as specified by the ITN. Vendors were not permitted

1206to disclose any cost information in the Technical Reply.

12159. Additiona lly, the ITN required that a 15 - page

"1226Requirements Response Location Form" be completed and provided

1234by the vendor in its ITN reply. The form listed the section

1246numbers of the essential criteria of the ITN and the pages o f the

1260ITN on which each criterion could be found. The form also

1271contained blank spaces adjacent to each referenced criteria where

1280the vendor was to list the sections and pages of the vendor's

1292reply that responded to each of the referenced criteria in the

1303requirements response form.

130610. Relevant to thi s case, Section 1 of ITN 13/14 - 01

1319contained general definitions of terms used in the ITN. Under

1329Section 1, a "Responsive Reply" was defined as "[a] Reply

1339submitted by a responsible Vendor that conforms in a ll material

1350respects to the solicitation." A "Minor Irregularity" was

1358defined as "[v]ariations of terms and conditions from the

1367Invitation to Negotiate which do not affect the price of the

1378Reply or give the Vendor an advantage or benefit not enjoyed by

1390th e other Vendors or do not adversely impact the interests of the

1403State." Additionally, the Department reserved the right to waive

1412minor irregularities in a vendor's reply.

141811. ITN Section 2.4 provided: "The FDOR intends to

1427negotiate with one or more Vend ors who are compliant with the

1439mandatory compliance items identified throughout this document."

144612. ITN Section 2.5 addressed Desired vs. Mandatory

1454Requirements and Actions:

1457Within the ITN the use of "shall" or "must"

1466indicates a mandatory requirement or

1471mandatory action. The FDOR may consider

1477failure to meet a mandatory requirement to be

1485a material deficiency, in which case the FDOR

1493may reject the Reply and not consider it

1501further, or FDOR may have the option to score

1510that requirement with a zero (0). ( emphasis

1518added ) .

1521The use of "should" or "may" indicates a

1529desired requirement. The FDOR will not

1535reject a Reply just because it fails to meet

1544a desired requirement and may result in a

1552lower score for that requirement.

155713. Clearly under the ITN, the man datory nature of a

1568requirement did not result in the criteria also being material

1578since the Department could consider failure to meet a mandatory

1588requirement to be a material deficiency or allow the vendor to

1599move to the evaluation phase with the materiali ty of such

1610criteria to be addressed by the evaluators during scoring.

161914. ITN Section 3.1.9, titled "Material Requirements

1626Compliance Review," addressed the ITN's pro - forma review for

1636responsiveness and provided:

16393.1.9.1 Each Vendor shall submit a Repl y

1647that conforms in all material respects to

1654this solicitation. Material requirements of

1659the ITN are those set forth as mandatory or

1668those that affect the competitiveness of

1674Replies. All Replies will be reviewed to

1681determine if they are responsive.

16863.1.9 .2 The FDOR will conduct a Material

1694Requirements Compliance Review of all Replies

1700submitted in response to this ITN. This

1707review does not assign scores, but is simply

1715a pass/fail review. Replies that do not meet

1723all material requirements of this ITN; fa il

1731any of the mandatory requirements in this

1738ITN; fail to timely respond to Reply

1745Qualification Requests (see Section 3.1.10);

1750fail to provide the required/requested

1755information, documents, or materials in the

1761Reply and/or during the Reply Qualification

1767Pr ocess; or include language that is

1774conditional, or takes exception to terms,

1780conditions and requirements, shall be

1785rejected as non - responsive and not considered

1793further.

17943.1.9.3 The FDOR reserves the right to

1801determine whether a Reply meets the material

1808requirements of the ITN.

181215. Addition ally, Section 3.1.10 of the ITN provided that

1822the Department was to initially review each reply "to determine a

1833Vendor's compliance with the requirements of the ITN not directly

1843related to the Technical Specifications and Cost Data of the

1853ITN." (emphasis added ) . A checklist titled "Material

1862Requirements Compliance Review" was used to determine the

1870responsiveness of a reply. The checklist items are not at issue

1881here. Importantly, per the ITN criteria, the material

1889r esponsiveness review was a review of the form of a reply and not

1903a review of the substance of the same. Indeed, deficient replies

1914could be cured as part of the "Reply Qualification Process."

192416. After the responsiveness review, an Evaluation

1931Committ ee chosen by the Department would score the

1940Administrative/Technical Volume for each vendor in accordance

1947with the evaluation criteria in the ITN. Towards that review,

1957the vendor was required to complete and submit the "Requirements

1967Response Location Form " as part of its reply. As indicated

1977earlier, the response location form listed the section numbers of

1987the essential criteria of the ITN and the pages of the ITN on

2000which each criterion could be found. The form's criteria

2009references matched the criteria references in the score sheets to

2019be used by the individual evaluators to score a vendor's reply.

2030Further, the evaluation committee used the location form to

2039locate information within a vendor's reply. In evaluating

2047replies, the committee members were no t expected to hunt down

2058information in a vendor's reply outside what was provided by a

2069vendor on its response location form. Thus, the form is a very

2081good indication of the materiality or importance of a particular

2091ITN criteria since those criteria were t he ones on which a

2103vendor's reply was to be evaluated.

210917. Relevant to this case, Section 7.13.1.1 of the ITN

2119required that a letter of commitment for a surety bond be

2130submitted with a vendor's cost reply. There was no prescribed

2140format or wording for th is letter.

214718. Additionally, S ection 12 of the ITN contained a table

2158titled "Attachments and Submittals." According to Section 12,

2166the table listed a variety of documents "to be completed and

2177included in Volume One: Administrative/Technical as

2183indi cated[.]" However, the table clearly listed documents that

2192the ITN, in other sect ions, required to be in Volume Two , the

2205Cost Data Reply. In fact, the table itself only indicated who

2216should complete a document. It did not indicate whether a

2226document was required , for responsiveness purposes , to be

2234submitted with a reply. The "as indicated" language, referenced

2243above, referred to other sections within the ITN to determine if

2254such documents should be submitted and in what volume they should

2265be submitted. Other than referral to other sections of the ITN,

2276Section 12 did not require that any document listed in its table

2288be attached to the ITN.

229319. Two of the documents listed in S ection 12 of the ITN

2306were "Incident Control Policy and Procedures" and "Ch ange

2315Management Policy and Procedures." In the column of the table

2325titled "Attachment" these two documents were listed as "Vendor's

2334Documents." However, unlike the other documents listed in the

2343S ection 12 table, these two documents had no attendant

2353requi rement in other sections of the ITN stating that the two

2365documents sh ould be provided or where in a v endor's reply the two

2379documents should be placed.

238320. The Department's responses to October 24, 2014, vendor

2392q uestions 18 and 19 regarding these docu ments were that the two

2405documents referred to the v endor's corporate documents and that a

2416copy of such documents were required to be submitted with a

2427vendor's "proposal." Except for the Department's responses,

2434there were no written addenda amendments to t he ITN document

2445making such submission mandatory or indicating in what section of

2455the vendor's multi - tabbed response the documents should be

2465included. Further, no addenda amendments were made to the

2474response location form to cover these documents. Simila rly, no

2484addenda amendments were made to the evaluator's score sheets to

2494cover or evaluate these documents. Thus, despite the use of the

2505word "required" in the Department's response to questions 18 and

251519 and in view of the lack of any amendments to the IT N in

2530relation to these responses, the evidence demonstrated that

2538submission of these two documents with a vendor's reply was only

2549desired by the Department and was not mandatorily required under

2559the ITN for purposes of responsiveness.

256521. Section 1 2 of the ITN a lso listed Attachment G,

"2577Individual Contractor Security and Agreement Form." The form

2585was to be "completed" by the vendor and subcontractors. As

2595discussed above, inclusion in the Section 12 table did not

2605indicate whether a document was req uired for responsiveness

2614purposes to be submitted with a reply. Those criteria were found

2625elsewhere in the ITN.

262922. Notably, the provision of the standard contract which

2638would emerge from this ITN required the security form be exe cuted

2650by subcontr actors within five days of signing the contract. More

2661importantly, Section 6.6 of the ITN stated that Attachment G

"2671should" be executed and submitted with a vendor's reply. As

2681such, the document's attachment was not mandatorily required for

2690responsivenes s purposes, but was only desired by the Department

2700at this point in the ITN process since the winning vendor and its

2713subcontractor's mu st provide the document within five days of

2723signing the contract.

272623. The ITN further provided in Section 10.3.2 that up on

2737completion of the Administrative/Technical evaluation, the Cost

2744Data Volume would be publicly opened and scored.

275224. Relevant to this case, the ITN addressed renewal cost

2762and renewal of any future contract in Section 7.4 of the ITN.

2774Section 7.4 stated , in pertinent part:

2780RENEWALS

2781The FDOR reserves the right to renew any

2789Contract resulting from this ITN. Renewals

2795shall be subject to the terms and conditions

2803set forth in the original Contract and

2810subsequent amendments, . . .

2815Vendors shall include the cost of any

2822contemplated renewals in their Reply, . . .

283025. In substance the s ection tracked the language of

2840s ection 287.057(13), Florida Statutes, making any renewal subject

2849to the same terms and conditions, including price, as the

2859original contra ct. Th e statute al so requires that the "price" of

2872any "services to be renewed" be provided in a vendor's reply.

2883However, if a separate renewal price was not provided in a

2894vendor's reply, any renewals would be at the price of the

2905original contract since under th e ITN the original price would be

2917the renewal price for s ection 287.057(13) purposes.

292526. On the other hand, Section 7.4 of the ITN deviated from

2937the statute's language and required that the "cost" of any

" 2947contemplated renewals" be included in the vendo r's reply.

2956Such cost information was not part of the criteria requirements

2966listed for the ITN on the "Requirements Response Location Form"

2976and was not part of the requirements to be evaluated by the

2988evaluation committee.

299027. Question 39 posited by SMI o n September 18, 2013, asked

3002about the handling of renewal cost information in the vendor

3012replies to the ITN. The Department's response to question 39 was

3023that "renewal rate information" "should" "please" be provided in

3032summary form in the cost volume of t he vendor's reply to the ITN.

3046Additionally, the Department's response stated that renewal cost

3054information was not to be "scored" as part of the transaction

3065rate. Clearly, the Department in its response viewed this "rate

3075information" as related to the tr ansaction rate , which was one of

3087several costs used to calculate total compensation under the ITN.

3097The Department's ex planation or interpretation of S ection 7.4 has

3108a reasonable basis since renewal of the contract was statutorily

3118restricted to the same te rms and conditions of the original

3129contract, making such renewal cost information immaterial.

3136Additionally, the renewal information was not part of the scoring

3146criteria that permitted a vendor to move through the negotiation

3156process under the ITN and was not required in order for a vendor

3169to be responsive to the ITN. In essence, the Department's

3179response made the provision of renewal cost information a non -

3190essential criteria of the ITN. Non - compliance with such criteria

3201can be waived by the Department as a minor irregularity. 2/

321228. ITN Section 10.3.2.1.4 provided:

3217Only cost submitted in the prescribed format

3224will be considered. Alternate cost models

3230will not be considered for scoring purposes.

3237Vendors selected for negotiations will be

3243provided the opportunity to present alternate

3249costing structures.

"3251Alternate cost models" referred to models that did not use a

3262transaction - based rate such as a fixed price model or did not use

3276the format for calculating compensation required by the ITN.

328529. Part o f the format for vendor cost replies included

3296Attachments K (Transaction Rate Cost Form), L (Baseline

3304Compensation Form), M (Reimbursable Cost Form), N (Unknown,

3312Unanticipated, and Unspecified Tasks Cost Form), and O (Total

3321Compensation Form). Additionall y, after questions posed by the

3330vendors, the Department supplied an estimate of the number of

3340transactions it predicted might be processed by the SDU under the

3351contract. The estimate provided by the Department was 69,425,110

3362transactions and was based in part on an assumed percentage

3372increase in actual transactions that occurred under the current

3381contract in 2012.

338430. Attachment K was the form used by a vendo r to explain

3397and report the per - transaction rate that the vendor would charge

3409the Department for e ach transaction it processed through the SDU.

3420The form required disclosure of the costs the vendor included in

3431determining its transaction rate. The form was required to be

3441signed by a representative who could bind the vendor.

345031. Relative to Attachme nt K under the ITN, neither the

3461method used nor the costs included by a vendor to calculate its

3473transaction rate was prescribed by the ITN criteria. There was

3483no requirement that the Department's estimated number of

3491transactions of 69,425,110 be used in c alculating the vendor's

3503transaction rate. The Department only supplied such estimates as

3512information to the vendor. In fact, a vendor was free to use its

3525own assumptions regarding the estimated number of transactions

3533that might be processed through the S DU in its calculation of its

3546transaction rate. The method of rate calculation did have to be

3557explained. However, once calculated, the vendor's transaction

3564rate was carried over to line "B" on Attachment L which, as

3576discussed below, ultimately filtered th rough to a contract price

3586and commensurate price of services that might be renewed in

3596Attachment O.

359832. Attachment L was the form used to calculate the

3608baseline compensation cost for the vendor. The initial form did

3618not require that the Department's estimate of 69,425,110

3628transactions be used in the calculation of the baseline

3637compensation cost. After questions from the vendors and internal

3646discussions within the Department, Attachment L was revised to

3655require that the Department's estimated number of transactions be

3664used on that form. Notably, the Department did not revise

3674Attachment K to require the use of the estimate when it revised

3686Attachment L. The formula used to calculate Projected Baseline

3695Compensation on Attachment L required the vendor t o multiply its

3706transaction rate from Attachment K by the Department's estimated

3715transactions of 69,425,110. The requirement to use the

3725Department's estimated number of transactions on Attachment L

3733normalized the vendors' baseline compensation calculation so that

3741an apples - to - apples comparison of baseline compensation could be

3753made between vendors. Once calculated, the projected baseline

3761compensation cost calculation was carried over to a line item in

3772Attachment O , which form calculated the total projected SDU

3781compensation, the cost factor used in awarding points to evaluate

3791a vendor's reply.

379433. Attachment M was the form on which a vendor was to

3806submit estimates of actual costs the vendor anticipated it would

3816expend for performing the contract. Although not specified,

3824presumably the costs listed by the vendor on Attachment M would

3835be those not used in the vendor's Attachment K transaction rate

3846calculation. Ad ditionally, ITN specifications S ections 7.10.4.3

3854and 10.3.2.3 provided that all vendors "shall ex ecute and submit

3865Attachment M: Reimbursable Costs." The term "execute" simply

3873means to complete.

387634. Within Attachment M, a list of several anticipated cost

3886categories (facilities rent/lease, postage, e - disbursement, post

3894office box fees, etc.) were p rovided by the Department. There

3905were also several blank fields for additional cost categories

3914contained on the form. The specifically - listed cost categories

3924were those categories the Department, in its experience,

3932anticipated a vendor might incur and fo r which it would reimburse

3944a vendor. The use of the phrase "will reimburse" in relation to

3956these anticipated cost categories did not make the reporting of

3966such costs mandatory given the format of Attachment M and the

3977instructions later provided on the for m discussed below. Such

3987anticipation only indicated interest by the Department in those

3996expense categories but did not create a requirement that those

4006specific expenses were required to be estimated by a vendor for

4017purposes of responsiveness to the ITN in order to move forward in

4029the evaluation and negotiation process. 3/ Indeed, such costs or

4039expenses were intentionally negotiable under the ITN.

404635. Following this list, a box to provide the amount of

4057each reimbursable cost and ultimate total was provid ed at the end

4069of Atta chment M. Notably, except for two of the anticipated cost

4081categories, the box did not include any of the anticipated costs

4092listed earlier in Attachment M. The two cost categories that

4102were listed in the reimbursable cost box were "Fa cilities

4112Rent/Lease" and "CSR Salary Expenses." Both these cost

4120categories had blank fields where the vendor was required to fill

4131in an amount in the reimbursable cost box at the end of

4143Attachment M. Additionally, the instructions for executing the

4151box c learly stated that amounts for these two categories must be

4163provided. As indicated, the other anticipated costs contained on

4172Attachment M were not specifically listed in the reimbursable

4181cost box. On ly blanks, labeled as "(other)," where amounts for

4192vend or "proposed" costs could be reported were contained within

4202the box. Given the format of this form and the instructions at

4214the top of the reimbursable cost box, amounts for anticipated

4224cost categories listed in Attachment M, other than the two

4234required co st categories in the box, were not required to be

4246proposed by the vendor in completing Attachment M and, as

4256indicated earlier, such amounts were not required in order for a

4267reply to be responsive to the ITN. As with the other forms, the

4280total from the rei mbursable cost box was carried over to a line

4293item in Attachment O.

429736. Attachment O was the form used to calculate the total

4308projected SDU compensation that constituted the vendor's proposed

4316contract price. The proposed price was also the price for

4326se rvices which may be renewed since, unless the vendor proposed a

4338different renewal price, this was the original price proposed as

4348a term of the initial contract.

435437. Section 10.3.2 sets forth the formula for scoring the

4364Cost Data Volume of a vendor. The formula was:

4373Total Available Cost Points x Amount of

4380Lowest Response Cost/Vendor's Reply Cost

4385(emphasis in original).

438838. The ITN further stated:

"4393Each Vendor's Cost Data points will be added

4401to their Administrative/Technical score to

4406obtain th e Vendor's Total Reply Score. The

4414Vendor's Total Reply Score will be used to

4422determine which Vendors the FDOR will

4428Negotiate with."

4430Thus, the vendor with the lowest cost would receive the maximum

4441points available for its Cost Data Volume with all other vendors

4452receiving a portion of the total available Cost Data points

4462proportionate to the difference between their proposed cost and

4471that of the vendor with the lowest cost. Notably, lower cost

4482points did not disqualify a vendor from selection for

4491negotia tion. Similarly, a lower Total Reply Score did not

4501disqualify a vendor from selection for negotiation because the

4510goal in an ITN procurement is t o develop a range of vendor

4523replies for negotiation.

452639. The ITN, in Section 11.3 , provided broad discretion to

4536the Department regarding the manner in which negotiations would

4545be conducted, including obtaining revised offers from v endors.

4554The section reserved to the Department the right to:

4563(a) negotiate with one or more, all, or none of the vendors;

4575(b) elim inate any vendor from consideration during negotiations

4584as deemed to be in the best interest of the State; and

4596(c) conduct negotiations sequentially, concurrently, or not at

4604all.

460540. Sections 3.1.19.1 and 11.5 of the ITN provided that at

4616the "conclusion" of negotiations, the Department would post a

4625Notice of Intended Agency Decision, as determined to be in the

4636best interest of the State. However, this language must be read

4647in conjunction with Section 11.4 of the ITN that authorized the

4658Department's negot iation team to request a Best and Final Offer

4669(BAFO) from one or more vendors with which the Department

4679concluded negotiations. The section reserved to the Department

4687the right to "request additional BAFO; reject submitted BAFO;

4696and/or move to the next ve ndor" after a BAFO had been submitted

4709and negotiations concluded. Additionally, Section 2.6.9

4715contemplates that discussions, i.e. negotiations, regarding the

4722form and language of the final contract would continue after the

4733Notice of Intent to Award was po sted. Section 2.6.9 states:

4744The FDOR anticipates initially addressing any

4750contract terms and conditions or concerns

4756during the Negotiation process and then

4762continue discussions post award.

4766Given this language, the Department, in its judgment and acting

4776i n the best interest of the state, may post an intended award

4789prior to the complete conclusion of negotiations and finalization

4798of the contract with a vendor.

480441. In this case, SMI and Xerox both timely submitted a

4815reply to the ITN. Each reply contained a Volume I:

4825Administrative/Technical; and a Volume II: Cost Data. Both

4833vendors submitted a completed Requirements Location Response Form

4841and had information contained in their reply relative to the

4851references contained in that form. As indicated earlier , under

4860the ITN's pro forma responsiveness review, the substance of each

4870vendor's reply was not a determining factor in whether a vendor's

4881reply was responsive to the ITN for purposes of being accepted

4892and moving forward in the ITN process.

489942. John Kin neer was a purchasing analyst with the

4909Department. He served as the procurement officer and as a

4919negotiator with respect to the ITN. Mr. Kinneer reviewed the

4929technical replies submitted by Xerox and SMI for pro - forma

4940responsiveness to the ITN sufficient to move forward in the ITN

4951process. In compliance with the ITN, he checked the Material

4961Requirements form for both vendors and checked that each vendor

4971had some information in its technical reply relative to the

4981response form. Per the ITN, he did not che ck the substance of

4994that information. In this case, the evidence demonstrated that

5003both replies met the preliminary responsiveness requirements of

5011the ITN and properly moved forward in the ITN process to the

5023evaluation phase.

502543. The Department appointed an evaluation team of seven

5034persons to evaluate and score the Technical Replies. The

5043Committee consisted of Shannon Herold, Barbara Johnson, Connie

5051Beach, Stan Eatman, Beth Doredant, Mark Huff, and Craig Curry.

5061Under the ITN, the evaluation team was tas ked with analyzing the

5073substance of each reply and scoring them accordingly with any

5083issues regarding the quality or responsiveness of a vendor's

5092reply to be addressed in that evaluator's scoring. Each

5101evaluator reviewed and independently scored each vend or's reply

5110according to the criteria listed in the "Requi rements Response

5120Location Form."

512244. In this case, both replies contained a surety letter of

5133commitment as required by Section 7.13.1.1 of the ITN. SMI's

5143letter was from OneBeacon, the apparent b onding agent in the

5154letter. Indeed, there was no evidence that OneBeacon was not a

5165bonding company. The letter indicated that OneBeacon intended to

5174provide a bond to SMI and that SMI qualified for such a bond in

5188an amount sufficient to meet the requireme nts of the ITN.

5199Xerox's letter of commitment was also from an apparent bonding

5209company and stated only that the bonding company was "prepared to

5220write the required performance bond" in an unspecified amount and

"5230subject to standard underwriting conditions ." While one may

5239quibble about the language used in both Xerox's and SMI's

5249letters, the evidence showed that both letters were not simply

5259letters of reference from a bonding company but were letters of

5270commitment from such companies and were intended as s uch by those

5282bonding agents. Moreover, the language of both letters was

5291acceptable to the Department as meeting the requirements of the

5301ITN. As such, both Xerox and SMI were responsive to the surety

5313commitment requirements of the ITN.

531845. Xerox's reply also attached a copy of its Corporate

5328Change Control P olicy and Procedures and a copy of its Corporate

5340Incident Control Policy. These documents were developed by Xerox

5349over several years of being in the business of providing SDU

5360services. They were not d eveloped in relation to this ITN and

5372the evidence did not show that Xerox was disadvantaged either

5382monetarily or otherwise by producing these documents for the ITN.

5392On the other hand, SMI did not attach such documents. Instead,

5403SMI summarized the substan ce of its policy and procedures in

5414Tabs 3, 10 and 13 of its Technical R eply and included a copy of

5429SMI's corporate Security Plan encompassing the incident and

5437control policies of SMI. The quality of SMI's reply was

5447evaluated by the evaluation committee m embers and scored

5456according to the criteria relevant to the ITN. Further, the

5466evidence demonstrated that failure to attach these two documents

5475would not adversely affect any vendor or impair the procurement

5485process since a vendor ultimately was required t o agree to adopt

5497the Department's incident control and change management policies

5505and procedures. Moreover, as indicated earlier, the documents

5513were not part of the responsiveness requirements under the ITN.

5523Therefore, SMI's reply was responsive without the attachment of

5532these two documents. However, assuming such documents were

5540required, the evidence demonstrated that the lack of copies of

5550specific documents titled in a certain way was a minor

5560irregularity which the Department reasonably waived since SM I

5569summarized the information relevant to these documents in its

5578reply. Such waiver was not clearly erroneous, contrary to

5587competition, arbitrary , or capricious.

559146. Additionally, Xerox submitted with its reply an

5599executed Attachment G, Individual Contrac tor Security Agreement

5607Form, for both itself and its proposed subcontractors. SMI

5616submitted an executed Attachment G for itself but did not submit

5627the attachment for its proposed subcontractors. The form was not

5637submitted for SMI's proposed subcontractor s because its

5645subcontractors could not access the Department's online

5652procurement library to determine what they would be agreeing to

5662by signing the form. The inaccessibility of the procurement

5671library was not the fa ult of SMI or its subcontractor s but wa s

5686due to the Department's failure to provide the policies

5695referenced. Additionally, the Department's Standard Contract

5701required Attachment G to be provided within five business days of

5712contract execution. The evidence did not demonstrate that SMI's

5721failu re to include an executed Attachment G for its

5731subcontractors constituted a material deviation from the ITN.

5739Further, as indicated above, Attachment G was not a mandatory

5749provision of the ITN for responsiveness purposes. As such, SMI's

5759reply was responsi ve on this criterion.

576647. However, even assuming Attachment G was required under

5775the ITN, the quality of SMI's reply was evaluated by the

5786evaluation committee members under the relevant criteria. The

5794evidence did not demonstrate that SMI obtained an un fair

5804competitive advantage by not including this form in its reply

5814since any subcontractor would have to submit the executed form

5824after contract execution as required by the Department's Standard

5833Contract. Additionally, the evidence did not demonstrate th at

5842the procurement process was undermined by the lack of a

5852subcontractor Attachment G in SMI's reply. Therefore, the lack

5861of such a document in SMI's reply was reasonably waived by the

5873Department as a minor irregularity and such waiver was not

5883clearly err oneous, contrary to competition, arbitrary , or

5891capricious.

589248. The evaluation team completed scoring of the vendor's

5901technical replies around January 17, 2014. Xerox scored 969

5910points and SMI scored 943 points. The difference of 26 points

5921was not shown by the evidence to be significant since both

5932vendors were experienced and well qualified to perform the

5941services required to operate the child support State Disbursement

5950Unit.

595149. After the technical replies were evaluated and scored,

5960the initial Cost Dat a replies of each vendor were opened and the

5973total costs read aloud at a public meeting. The initial cost

5984replies were reviewed by Mr. Kinneer to ensure the replies were

5995mathematically accurate and that the cost forms were used. He

6005did not review or cons ider the substance of the cost numbers

6017included on those forms or the narratives in the cost replies.

6028The substance of the cost replies was left for consideration by

6039the negotiation team.

604250. Xerox's proposed total compensation for years

60491 through 5 of the contract was $84,920,072.00. SMI's proposed

6061total compensation for the same period was $47,996,387.00,

6071approximately $36 million less than Xerox's proposed

6078compensation. Neither vendor submitted a separate price for

6086renewal of the SDU services contr act. Therefore, for purposes of

6097section 287.057(13), Florida Statutes, the "price" for the

"6105services to be renewed" was the amount stated above for that

6116vendor. Both Xerox and SMI were responsive for purposes of the

6127statutory requirement of section 287.0 57(13).

613351. Xerox also submitted a brief summary of renewal cost in

6144its introductory letter to its cost reply. In essence, Xerox did

6155not anticipate any renewal cost associated with future renewal of

6165the contract. SMI, also, did not anticipate any renewa l cost

6176associated with future renewal of the contract, but did not

6186submit a statement to that effect. However, as discussed above,

6196such cost information was not part of the criteria requirements

6206listed for the ITN on the "Requirements Response Location Fo rm"

6217and was not part of the requirements to be scored by the

6229Department for purposes of the cost reply. The evidence

6238demonstrated that the information was immaterial to the

6246Department in evaluating these replies. Further, the evidence

6254did not demonstrate that failure to summarize such renewal cost

6264information would adversely affect any vendor or impair the

6273procurement process. Under this ITN and the facts of this case,

6284the failure to provide such non - essential cost information

6294constituted a minor irregul arity and was appropriately waived by

6304the Department. The Department's action in that regard was not

6314unreasonable and was not clearly erroneous, contrary to

6322competition, arbitrary , or capricious.

632652. The evidence showed that both vendors filled out

6335Attac hments K, L, M, N , and O. Relative to A ttachment K,

6348Transaction Rate, both vendors completed the form based on their

6358unique assumptions regarding the appropriate transaction rate.

6365Neither vendor used the Department's estimated transaction amount

6373of 69,42 5,110 transactions. Xerox claimed that its assumptions

6384took into consideration the Department's estimate and that such

6393consideration was buried in its ultimate calculation. However,

6401Xerox's mathematical explanation of its transaction rate

6408calculation on its Attachment K does not reflect that it used the

6420Department's estimate in its calculation. In general, the

6428explanation of its transaction rate contained in its reply

6437reflects that Xerox based its transaction rate on the current

6447contract price minus the annualized costs contained in its

6456Attachment M, divided by the actual number of transactions Xerox

6466processed in 2012 and discounted by 12% to produce a transaction

6477rate of 1.150 for the ITN. Clearly, Xerox did not use the

6489Department's estimate in its calc ulation and, instead, based its

6499transaction rate on the current contract price, a meth od the

6510Department warned vendor s against using.

651653. Similarly, SMI did not use the Department's estimated

6525transaction number in its calculation of its transaction rate on

6535Attachment K. SMI based its proposed rate of .497 on its own

6547historical transaction volumes from other states. The estimated

6555number of transactions used by SMI was 45,066,694 transactions.

6566For unknown reasons, the detailed explanation of the amount of

6576transactions used by SMI was placed on Attachment L. However,

6586the explanation was not used on Attachment L and did not impact

6598the calculation contained on Attachment L. Such misplacement was

6607immaterial to the ITN and had no impact on the ultimate resu lt in

6621Attachment O. As such, the misplaced explanation did not render

6631SMI's Attachment K non - responsive to the ITN and both Xerox and

6644SMI were responsive to the ITN regarding Attachment K.

665354. Likewise, the misplaced explanation of SMI's

6660transaction volu me did not render SMI's Attachment L non -

6671responsive to the ITN since it was immaterial to that Attachment.

6682Further, the evidence demonstrated that both Xerox and SMI used

6692the Department's estimated transaction volume on Attachment L as

6701required by the ITN . Therefore, both Xerox and SMI were

6712responsive to the ITN regarding Attachment L.

671955. Relative to Attachment M, Reimbursable Costs, both

6727vendors supplied cost amounts for rent and CSR salaries as

6737required by Attachment M. However, neither vendor suppli ed all

6747of the cost amounts listed in Attachment M's list of anticipated

6758costs. SMI did not supply amounts for postage associated with

6768certain services, post office box fees, foreign bank fees , and

6778hand - signed paper check stock costs. Xerox did not supply

6789amounts associated with SDU mass mailings as li sted in cost

6800category two for postage - related items on Attachment M and did

6812not submit an amount for telecommunications cost. As discussed

6821earlier, except for two of the anticipated cost categories of

6831rent a nd CSR salaries, the ITN did not require that amounts be

6844supplied for those categories in order for a reply to be

6855responsive to the ITN. Therefore, both Xerox and SMI were

6865responsive to the ITN regarding Attachment M.

687256. Both Xerox and SMI submitted a r esponsive Attachment O

6883which included line items fro m Attachments K through N.

6893Attachment O formed the basis for awarding points based on the

6904lowest cost. As indicated earlier, Xerox's proposed total

6912compensation for years 1 through 5 of the contract was

6922$84,920,072.00. SMI's proposed total compensation for the same

6932period was $47,996,387.00.

693757. Under the ITN, the cost replies were scored according

6947to the ITN specifications in Section 10.3.2 and the formula

6957contained therein. SMI received a total of 6 60 points as the low

6970cost reply. As the second lowest cost reply, Xerox received 376

6981points as a proportion of the total 660 points received by SMI.

6993Both vendors' scores were added to their technical scores. SMI

7003received a combined Total Reply score of 1603 points for its

7014reply. Xerox received a combined Total Reply Score of 1346

7024points for its reply. As responsible and responsive vendors,

7033both Xerox and SMI were selected to participate in the

7043negotiation phase of the ITN, where, under the ITN, the cri teria

7055and terms of the ITN became negotiable. Further, the evidence

7065did not demonstrate that either the evaluation scores or the

7075Total Reply Scores impacted the ITN process beyond qualifying the

7085vendors to participate in the negotiation process.

709258. The Department formed a Negotiation Team consisting of

7101Thomas Mato, Clark Rogers, Nancy Luja, Max Smart, Steve Updike,

7111John Kinneer, and Bo Scearce.

711659. Several meetings of the Negotiation T eam were held

7126during which the team evaluated Xerox's and SMI's repli es, posed

7137written questions to the vendors and discussed technical issues

7146with technical experts. Face to face negotiating sessions

7154between the team and the vendors were also held, as well as

7166meetings to discuss technical issues with the parties.

7174Additio nally, two rounds of separate demonstrations of a vendor's

7184proposed system and solution were given to the Negotiation Team

7194by Xerox and SMI. The Negotiation T eam only observed the

7205demonstration of each vendor in the first such meeting. During

7215the second dem onstration by each vendor, the N egotiation T eam

7227observed the demonstration and asked questions of the vendor.

7236Based on these demonstrations and meetings, the team elected to

7246request revised replies from both vendors. At some point prior

7256to submission of the revised offers and per the ITN, the team

7268communicated to Xerox that, if it wish ed to stay competitive in

7280the ITN process, it should bring its price c loser to that of SMI.

7294The team also communicated its desire to SMI that costs from the

7306anticipated cost list on Attachment M that SMI had not included

7317in its initial reply should be included on that form.

732760. With that information from the Negotiation T eam, Xerox

7337and SMI submitted revised cost replies. Xerox's Total Projected

7346SDU Compensation droppe d from $84,920,072.00 to $48,200,000.00.

7358Its transaction rate was reduced from $1.150 to $.525. Its

7368Attachment M cost estimate increased from $5,081,195.50 to

7378$9,926,119.00. SMI's Total Projected SDU Compensation increased

7387from $47,996,387.00 to $49,500 ,000.00. Importantly, its

7397transaction rate remained the same at $.497. Its Attachment M

7407cost decreased from $13,492,107.00 to $12,433,125.00.

741761. After revi ewing the revised replies, the Negotiation

7426T eam elected to continue to conduct negotiations with SMI first.

7437Such vendor selection was appropriate under the ITN since its

7447transaction rate remained lower than Xerox's transaction rate and

7456the team preferred SMI's solution for a variety of legitimate

7466reasons to Xerox's solution.

747062. Additional negotia tions were conducted with SMI,

7478resulting in additional terms and cond itions. After several such

7488negotiation meetings, the evidence showed that the substantive

7496part of the negotiations, including price and scope of work, had

7507concluded with only final contr actual language remaining. As

7516such , the Negotiation T eam requested a Best and Final Offer

7527(BAFO) from SMI.

753063. On May 14, 2014, SMI submitted its BAFO. SMI's Total

7541Projected SDU Compensation increased from $49,500,000.00 to

7550$50,700,000.00. Its transact ion rate dropped slightly to $.495

7561and its Attachment M cost increased from $12,433,125.00 to

7572$13,740,152.09.

757564. The BAFO was acceptable to the negotiation team and

7585would, along with SMI's technical reply, become part of the

7595Department's standard contr act under the ITN. The team

7604reasonably concluded SMI's management team was superior, and its

7613solution was more customer friendly, intuitive, efficient , and

7621innovative. The Negotiation T eam documented its reasons for

7630selecting SMI in a memorandum to the p rocurement file.

764065. On May 19, 2014, the Department posted its Notice of

7651Intended Award to SMI. The evidence did not demon strate that the

7663award violated s ection 287.057, Florida Statutes , since that

7672section only requires that negotiations be "conducte d" prior to

7682an intended award of a contract. Notably, the award is only

7693intended and is not final since the Department under Sections

77033.1.19.2 and 7.3 is not required to enter into a contract if such

7716a document cannot be finalized. Indeed, the statutory language

7725of section 287.057(4) and the ITN in Section 2.6.9 permit

7735continued negotiation and finalization of a contract after the

7744Notice of Intended Award.

774866. In this case, the evidence demonstrated that the

7757negotiations between the negotiation team an d SMI resulted in a

7768meeting of the minds regarding the services that SMI would be

7779performing and the price for those services. Further, the

7788evidence showed that the negotiations had concluded in all

7797substantial respects prior to posting of the Notice of I ntent to

7809Award the contract to SMI. What remained for the Department and

7820SMI to accomplish was the finalization of the contract a ssembly

7831by inserting the BAFO, Technical R eply , and p rice into the

7843contract language; insertion of a start date; and work on

7853i mplementation issues such as invoices and background screening

7862of employees. Given these facts, the evidence demonstrated that

7871the point at which the Department elected to post its Notice of

7883Intended Award was reasonable since the substantive parts of the

7893negotiations were complete.

789667. Ultimately, the evidence in this case did not

7905demonstrate that the ITN process followed by the Department was

7915fundamentally flawed or gave an advantage to one vendor over

7925another. Further, the actions of the Department in this

7934procurement were not contrary to the Department's statutes;

7942contrary to the Department's rules or policies; or contrary to a

7953reasoned interpretation of the ITN specifications. Finally, the

7961evidence did not demonstrate that the Department's actions w ere

7971clearly erroneous, contrary to competition, arbitrary , or

7978capricious. Given these facts, the protest filed by Petitioner

7987should be dismissed.

7990CONCLUSIONS OF LAW

799368. The Division of Administrative Hearings has

8000jurisdiction over the parties to and the subject matter of this

8011proceeding. See §§ 120.569 and 120.57, Fla. S tat. (2014 ) .

802369. Chapter 287, Florida Statutes, deals with the

8031procurement of commodities and services by state agencies. In

8040this case, the Department utilized an invitation to negotiat e as

8051the method for procurement of the contract at issue. Section

8061287.057(1)(c) describes how a procurement by invitation to

8069negotiate is conducted and provides:

8074(c) Invitation to negotiate. -- The

8080invitation to negotiate is a solicitation

8086used by an agenc y which is intended to

8095determine the best method for achieving a

8102specific goal or solving a particular

8108problem and identifies one or more

8114responsive vendors with which the agency

8120may negotiate in order to receive the best

8128value.

81291. Before issuing an invi tation to

8136negotiate, the head of an agency must

8143determine and specify in writing the reasons

8150that procurement by an invitation to bid or a

8159request for proposal is not practicable.

81652. The invitation to negotiate must

8171describe the questions being explored, the

8177facts being sought, and the specific goals

8184or problems that are the subject of the

8192solicitation.

81933. The criteria that will be used for

8201determining the acceptability of the reply

8207and guiding the selection of the vendors

8214with which the agency will neg otiate must

8222be specified.

82244. The agency shall evaluate replies against

8231all evaluation criteria set forth in the

8238invitation to negotiate in order to establish

8245a competitive range of replies reasonably

8251susceptible of award. The agency may select

8258one or mo re vendors within the competitive

8266range with which to commence negotiations.

8272After negotiations are conducted, the agency

8278shall award the contract to the responsible

8285and responsive vendor that the agency

8291determines will provide the best value to the

8299state , based on the selection criteria.

83055. The contract file for a vendor selected

8313through an invitation to negotiate must

8319contain a short plain statement that

8325explains the basis for the selection of the

8333vendor and that sets forth the vendor's

8340deliverables an d price, pursuant to the

8347contract, along with an explanation of how

8354these deliverables and price provide the

8360best value to the state.

836570. Section 287.012(25) defines a responsive submission to

8373a solicitation as follows: "Responsive bid," "responsive

8380p roposal," or "responsive reply" means a bid, or proposal, or

8391reply submitted by a responsive and responsible vendor that

8400conforms in all material respects to the solicitation. A

8409responsive vendor is defined by section 287.012(26) as "a vendor

8419that has sub mitted a bid, proposal, or reply that conforms in

8431all material respects to the solicitation." Section 287.012(24)

8439defines a responsible vendor as "a vendor who has the capability

8450in all respects to fully perform the contract requirements and

8460the integrity and reliability that will assure good faith

8469performance." The statutory definition of a responsive vendor

8477does not change whether the procurement method is an invitation

8487to bid, a request for proposals, or an invitation to negotiate.

849871. The burden of p roof in a competitive - procurement

8509protest rests with the party protesting the agency's intended

8518decision. Section 120.57(3)(f) provides:

8522In a competitive - procurement protest, other

8529than a rejection of all bids, proposals, or

8537replies, the administrative la w judge shall

8544conduct a de novo proceeding to determine

8551whether the agency's proposed action is

8557contrary to the agency's governing statutes,

8563the agency's rules or policies, or the

8570solicitation specifications. The standard of

8575proof for such proceedings sha ll be whether

8583the proposed agency action was clearly

8589erroneous, contrary to competition,

8593arbitrary, or capricious.

8596As such, Xerox must establish whether the Department's action to

8606award the ITN to SMI was contrary to the ITN specifications;

8617contrary to gov erning statutes, applicable rules , or policies ;

8626and was clearly erroneous, contrary to competition, arbitrary , or

8635capricious. § 120.57(3)(f ), Fla. Stat. (2014); Florida Dep't of

8645Transp. v. J.W .C. Co. , 396 So. 2d 778, 787 (Fla. 1st DCA 1981).

865972. An agen cy action will be found to be "clearly

8670erroneous" if the agency's interpretation conflicts with the

8678plain and ordinary intent of the law. See Colbert v. Dep't of

8690Health , 890 So. 2d 11 65, 1166 (Fla. 1st DCA 2004). In such a

8704case, "judicial deference need not be given" to the agency's

8714interpretation. Id. An agency action will be found to be

"8724clearly erroneous" if it is without rational support, and,

8733consequently, the trier - of - fact has a "definite and firm

8745conviction that a mistake has been committed." U .S. v. U.S.

8756Gypsum Co. , 333 U.S. 364, 395 (1948).

876373. An act is "contrary to competition" if it unreasonably

8773interferes with the objectives of competitive bidding, which are:

8782[T]o protect the public against collusive

8788contracts; to secure fair competition upon

8794equal terms to all bidders; to remove not

8802only collusion but temptation for collusion

8808and opportunity for gain at public expense;

8815to close all avenues to favoritism and fraud

8823in its various forms; to secure the best

8831values for the county at the lowest possible

8839expense; and to afford equal advantage to all

8847desiring to do business with the county, by

8855affording an opportunity for an exact

8861comparison of bids.

8864Wester v. Belote , 103 Fla. 976, 981, 138 So. 721, 723 - 24 ( 1930).

8879See SYSLOGIC Tech. Servs., In c. v. S. Fl a . Water Mgm t . Dist . ,

8896Case No. 01 - 4385BID (Fla. DOAH Jan. 18, 2002; SFWMD Mar. 6,

89092002).

891074. "An action is 'arbitrary if it is not supported by

8921logic or the necessary facts,' and 'capricious if it is adopted

8933without thought or reason or is irr ational.'" Hadi v. Liberty

8944Behavioral Health Corp. , 927 So. 2d 34, 38 - 39 (Fla. 1st DCA 2006)

8958and Agrico Chem. Co. v. Dep't of Envtl. Reg. , 365 So. 2d 759, 763

8972(Fla. 1st DCA 1978). Thus, when reviewing a contract award

8982decision to determine whether it is arbitrary or capricious, it

8992must be upheld if the action is justifiable under any analysis

9003that a reasonable person would use to reach a decision of similar

9015weight. As long as the agency has acted in good faith, its

9027judgment should not be interfered with, even if reasonable men

9037could differ and even if the decision may seem erroneous to some

9049persons. Colbert v. Dep't. of Health , 890 So. 2d 1165 (Fla. 1st

9061DCA 2004); State Contracting & Eng'g Corp. v. Dep ' t. of Transp. ,

9074709 So. 2d 607, 610 (Fla. 1st DCA 199 8); and Volume Servs. Div.

9088v. Canteen Corp. , 369 So. 2d 391, 395 (Fla. 2d DCA 1979) ( quoted

9102in System Dev. Corp. v. Dep't of Health & Rehab. Servs. , 423 So.

91152d 433, 434 (Fla. 1st DCA 1982) ) . In that regard, the ITN in

9130Section 3.1.9.3 clearly reserves to t he Department the right to

9141determine whether a reply meets the material requirements of the

9151ITN. Additionally, Section 2.7 of the ITN, as well as paragraph

916216 of the General Conditions, reserve to the Department the right

9173to waive minor irregularities.

917775 . In this case, both replies contained a surety letter of

9189commitment as required by Section 7.13.1.1 of the ITN. The

9199evidence showed that both letters were not simply letters of

9209reference from a bonding company but were letters of commitment

9219from such co mpanies and were intended as such by those bonding

9231agents. As such, both Xerox and SMI were responsive to the

9242surety commitment requirements of the ITN.

924876. The evidence also showed that Attachment K did not

9258require that the Department's estimated number of transactions be

9267used by a vendor in its transaction rate calculation. Unlike

9277Veolia Transportation Services, Inc. v. Commission for the

9285Transportation Disadvantaged , DOAH Case No. 08 - 1636BID (DOAH

9294July 9, 2008), where the methodology for the rate cal culation by

9306a vendor was required to be used by that vendor in responding to

9319a request for proposal, the Department in this ITN did not

9330require a specific methodology or use of a specific cost estimate

9341by a vendor in calculating its transaction rate on Att achment K.

9353The Department's estimate was only required to be used in the

9364baseline compensation calculation on Attachment L , which use

9372normalized the baseline compensation calculation so that the

9380Department could make an apples - to - apples comparison of that

9392cost. Thus, the Department's calculation requirements on forms K

9401and L were reasonable and SMI met the requirements of the ITN in

9414completing its Attachment s K and L. Morphotrust USA v.

9424Dep't of Transp. and Solutions Thru Software, Inc. , DOAH Case

9434No. 12 - 2917BID (DOAH Dec. 7, 2012; FDHSMV Jan. 7, 2013).

944677. In Morphotrust USA v. Department of Transportation and

9455Solutions Thru Software, Inc. , the administrative law judge found

9464that the ITN did not impose a mandatory requirement or condition

9475as to the substance of a form , or direct that the pricing form be

9489filled out in a certain way. In reaching the decision, the

9500administrative law judge recognized that while the use of the

9510terms, "shall," "must" and "will" in the solicitation indicated a

9520mandatory re quirement or condition, the only portion of the ITN

9531that was mandatory was the requirement that "proposal forms must

9541be submitted with [the] proposal" since it was the only section

9552in the ITN specification that used the mandatory term. Id. at

956321. ¶ 79.

956678 . Like Morphotrust , the ITN required that a vendor submit

9577Attachment M. Except for two categories of costs, the ITN did

9588not require a vendor to seek reimbursements of any costs or to

9600complete the form in a specific way. In this case, both SMI a nd

9614Xero x submitted A ttachment M, did not deviate from the ITN

9626requirements , and were responsive on this requirement.

963379. However, the evidence did demonstrate that SMI's reply

9642deviated from the ITN since it did not contain renewal cost

9653information and did not have an attachment containing copies of

9663SMI's Incident Control Policy and Procedures and Change

9671Management Policy and Procedures. Importantly, not every

9678deviation from an ITN makes a reply non - responsive to the ITN.

9691The court in Robinson Electrical Co. v . Dade County , 417 So. 2d

97041032, 1034 (Fla. 3d DCA 1982), discussed the criteria for

9714determining whether a variance is a material deviation or a minor

9725irregularity and stated:

9728Although a bid containing a material variance

9735is unacceptable, Glatstein v. City of Miami ,

9742399 So. 2d 1005 (Fla. 3d DCA), rev. denied,

9751407 So. 2d 1102 (Fla. 1981), not every

9759deviation from the invitation is material.

9765In determining whether a specific

9770noncompliance constitutes a substantial and

9775hence non - waivable irregularity, the cou rts

9783have applied two criteria - first, whether the

9791effect of a waiver would be to deprive the

9800[government agency] of its assurance that

9806the contract will be entered into, performed

9813and guaranteed according to its specified

9819requirements, and second, whether i t is of

9827such a nature that its waiver would adversely

9835affect competitive bidding by placing a

9841bidder in a position of advantage over other

9849bidders or by otherwise undermining the

9855necessary common standard of competition.

9860In application of the general prin ciples

9867above discussed, sometimes it is said that a

9875bid may be rejected or disregarded if there

9883is a material variance between the bid and

9891the advertisement. A minor variance,

9896however, will not invalidate the bid. In

9903this context a variance is material i f it

9912gives the bidder a substantial advantage

9918over the other bidders, and thereby

9924restricts or stifles competition. 10

9929McQuillan, Municipal Corporations § 29.65 (3d

9935Ed. Rev. 1981) (footnotes omitted); see Harry

9942Pepper & Associates, Inc. v. City of Cape

9950Co ral , (Fla. 3d DCA 1982).

995680. In that regar d, section 287.057(13), Florida Statutes ,

9965grants an agency the authority to renew a contract under certain

9976conditions and requires that a reply to an invitation to

9986negotiate provide the "price" of the "servi ce to be renewed."

9997Section 287.057(13) states:

10000Contracts for commodities or contractual

10005services may be renewed for a period that may

10014not exceed 3 years or the term of the

10023original contract, whichever is longer.

10028Renewal of a contract for commodities or

10035c ontractual services must be in writing and

10043is subject to the same terms and conditions

10051set forth in the initial contract and any

10059written amendments signed by the parties. If

10066the commodity or contractual service is

10072purchased as a result of the solicitation of

10080bids, proposals, or replies, the price of the

10088commodity or contractual service to be

10094renewed must be specified in the bid,

10101proposal, or reply, except that an agency may

10109negotiate lower pricing. A renewal contract

10115may not include any compensation for c osts

10123associated with the renewal. Renewals are

10129contingent upon satisfactory performance

10133evaluations by the agency and subject to the

10141availability of funds . . . . (emphasis

10149added ) .

1015281. In Flordia Department of Environmental Protection v.

10160ContractPoint Florida Parks, L.L.C. , 986 So. 2d 1260 , 1265 (Fla.

101702008), the Florida S upreme Court stated:

10177This Court has long held that a "statute must

10186be given its plain and obvious meaning."

10193Holly v. Auld , 450 So. 2d 217, 219 (Fla.

102021984) (quoting A.R. Douglass, In c. v.

10209McRainey , 102 Fla. 1141, 137 So. 157, 159

10217(Fla. 1931)). If the language of the statute

10225is "clear and unambiguous and conveys a clear

10233and definite meaning" there is no need to

10241resort to statutory construction. Id.;

10246accord Forsythe v. Longboat Key B each

10253Erosion Control Dist. , 604 So. 2d 452, 454

10261(Fla. 1992). In interpreting section 11.066,

10267however, we cannot read subsection (3) in

10274isolation, but must read it within the

10281context of the entire section in order to

10289ascertain legislative intent for the

10294pr ovision. Id. at 455 ("Every statute must

10303be read as a whole with meaning ascribed to

10312every portion and due regard given to the

10320semantic and contextual interrelationship

10324between its parts." (quoting Fleischman v.

10330Dep't of Prof'l Reg. , 441 So. 2d 1121, 1123

10339(Fla. 3d DCA 1983))). A "statute should be

10347interpreted to give effect to every clause in

10355it, and to accord meaning and harmony to all

10364of its parts" and is not to be read in

10374isolation, but in the context of the entire

10382section. Jones v. ETS of New Orleans , Inc. ,

10390793 So. 2d 912, 914 - 15 (Fla. 2001) (quoting

10400Acosta v. Richter , 671 So. 2d 149, 153 - 54

10410(Fla. 1996)).

1041282. Importantly, s ection 287.057(13) is part of a statutory

10422scheme that provides a continuum of competitive procurement

10430options to the State. As indicated earlier, that continuum runs

10440from invitations to bid, through requests for proposals, to

10449invitations to negotiate. Each of these procurement processes

10457has statutory requirements associated with it. As part of that

10467statutory scheme and to unders tand the meaning of the term

"10478price" used in the above - quoted section, subsection (13) must be

10490read in pari materia with the rest of section 287.057.

1050083. Under sections 287.057 (1) (a)2. and (1) (b)3.b.,

10509governing invitations to bid and requests for proposal s, the

"10519price" for each year of the re newal must be specified in the

10532vendor's submission. In section 287.057 (1) (b)3.b. , "price" for

10541each year of renewal must also be used to evaluate a vendor's

10553proposal under a request for proposal. Additionally, subsect ions

10562287.057 (1) (a)3. and (1) (b)3.c. governing invitations to bid and

10573requests for proposals, require that the vendor's submission be

10582evaluated based on the total "cost" for each year of the

10593contract, including renewal years. Importantly, none of the

10601renew al requirements related to evaluation of renewal prices or

10611costs associated with the other procurement methods under section

10620287.057 are required under subsection (1) (c) of the statute

10630governing invitations to negotiate. Neither price nor cost are

10639defined in c hapter 287. However, the use of the terms "price"

10651and "cost" in the same statute indicates that such terms are not

10663synonymous with each other, but have more specific procurement -

10673related meanings.

1067584. In purchasing, price is not the same as cost. Price is

10687the quantity of one thing, e.g. , money, that is exchanged or

10698demanded in barter or sale for another thing, e.g. , SDU services,

10709of which cost is a component. Cost is the monetary value of

10721material, effort, products, resources, etc. which go into

10729p roducing and delivering a good or service. See "What is Price?"

10741BusinessDictionary.com. Web. 16 Feb. 2015.

10746and

"10747What is Cost?" BusinessDictionary.com. Web. 16 Feb. 2015.

10755.

1075685. In this case, both vendors stated the price of the

10767service to be renewed in their Attachment O. Like the statute,

10778the ITN, in this case, provided that renewal was to be on the

10791same terms and conditions as the initial co ntract. Therefore,

10801unless a vendor specified a separate section 287.057(13) "price"

10810for the "service to be renewed," the vendor's original price was

10821the renewal price under both the statute and the terms of the

10833ITN. Since neither vendor specified a separ ate "price" for the

"10844service to be renewed , " the price for such renewal was the

10855proposed contract price in that vendor's Attachment O. As such,

10865both Xerox and SMI met the statutory requirement of section

10875287.057(13).

1087686. The ITN did require that renewal costs , not price, be

10887summarized in a vendor's reply. In regards to these costs, the

10898evidence demonstrated that such costs were non - essential to the

10909ITN and were not required for a vendor to be responsive to the

10922ITN. Given the non - essential nature of this information, the

10933evidence did not demonstrate that any advantage or disadvantage

10942resulted to any vendor as a result of such information not being

10954provided by SMI. Similarly, the evidence did not demonstrate

10963that the competitive procurement process was im paired by SMI not

10974providing this cost information.

1097887. Further, the initial cost replies were used to score

10988vendors for the purpose of the Department determining the vendors

10998with which it would conduct negotiations. Neither renewal

11006pricing nor costs we re used in scoring the vendors' replies.

11017Such scoring demonstrates the insignificance of renewal cost

11025information under the ITN. The evidence did not demonstrate that

11035SMI received a competitive advantage by failing to state in its

11046cost reply that there w ould be no change in its cost during any

11060renewal period. The evidence did demonstrate that failure to

11069provide such information was a minor deviation from the ITN

11079criteria and could be properly waived by DOR. Juvenile Services

11089Program, Inc. v. Dep't of Ju venile Justice , Case No. 07 - 1975BID,

11102(DOAH Oct. 31, 2007 ; OJJ Nov. 30, 2007 ). Thus, not providing

11114such information was properly waived by the Department. The

11123evidence did not demonstrate that the Department's actions were

11132clearly erroneous, contrary to c ompetition, arbitrary , or

11140capricious.

1114188. Finally, Xerox contends that the posting of the

11150Department's intended contract award to SMI , before negotiations

11158were concluded , violated Florida law or materially deviated from

11167the ITN specifications. However , s ection 287.057 does not

11176require that posting of an award decision be held until the

11187conclusion of negotiations with a vendor. Section

11194287.057(1)(c)4 . states, in pertinent part:

11200[A ]fter negotiations are conducted , the

11206agency shall award the contract to the

11213responsible and responsive vendor that the

11219agency determines will provide the best value

11226to th e state . . . (emphasis added ).

11236Further, the ITN process provides agencies more discretion in

11245negotiating with vendors than does the RFP process described i n

11256sect ion 287.057(b) . See Cushman and Wakefield of Fla., Inc. v.

11268Dep't of Mgmt. Servs. , DOAH Case No. 13 - 3894BID, ¶ 102 (DOAH

11281Jan. 24, 2014; DMS Feb. 5, 2014) (ALJ re cognized there is no

11294provision under Florida law that prohibits an agency from

11303attemptin g to maximize the best value to the state and, as a

11316result, rejected an argument that an agency is prohibited from

11326asking vendors to modify their price once a BAFO has been

11337submitted since this would frustrate the agency's ability to

11346maximize the best valu e for the state). Thus, the statute does

11358not require that negotiations be "concluded" but only that they

11368have been "conducted" prior to the contract award. In that

11378regard, DOR did not violate the statute by posting its intended

11389award prior to finalizat ion of the contract with SMI.

1139989. However in this case, the ITN refers to the

"11409conclusion" of negotiations prior to the Negotiation Team

11417requesting a BAFO or posting a notice of intent to award the

11429contract. On the other hand, S ection 2.6.9 contemplates that

11439additional discussions regarding the contract could occur after

11447the contract award. Clearly, the reference to the conclusion of

11457negotiations in the ITN does not mean that the contract document

11468itself has been completed.

1147290. In this case, the evide nce demonstrated that extensive

11482negotiations were conducted between the Department's Negotiation

11489Team a nd SMI prior to posting of the Notice of Intent to A ward

11504the contract to SMI. The evidence further demonstrated tha t the

11515negotiations between the N egoti ation T eam and SMI resulted in a

11528meeting of the minds regarding the services that SMI would be

11539performing and the price for those services. Further, the

11548evidence showed that the negotiations had concluded in all

11557substantial respects prior to posting of th e Notice of Intent to

11569Award the contract to SMI. The evidence did not demonstrate that

11580such posting was contrary to competition, impeded the nature of

11590competitive procurement or created an unfair advantag e in the

11600award. Additionally, t he evidence did not demonstrate that the

11610timing of t he Department's posting of its Notice of Intent to

11622A ward the contract to SMI was contrary to any statute, rule,

11634policy , or ITN specification and was, at worst, a minor deviation

11645from those specifications.

1164891. Therefore, th e Department's interpretation of the ITN

11657as not requiring the contract document itself, including

11665Attachment A to the contract document, to be finalized prior to

11676contract award , as long as the substantive terms and conditions

11686and price have been negotiated , is certainly a rational and

11696reasonable interpretation of its own specifications that should

11704not be disturbed.

1170792. The evidence did not demonstrate that the Department's

11716intended award of a contract to SMI deviated from governing

11726statutes, applicable rul es , or policies of the Department or

11736reasonable interpretations of the ITN specifications. Further,

11743there was no evidence that the Department's decision was clearly

11753erroneous, contrary to competition, arbitrary, or capricious.

11760Therefore, the award of the contract arising out of the ITN to

11772SMI should stand and this protest should be dismissed.

11781RECOMMENDATION

11782Based on the foregoing Findings of Fact and Conclusions of

11792Law, it is, therefore,

11796RECOMMENDED that the Respondent, Florida Department of

11803Revenue, en ter a final order dismissing the protest of

11813Petitioner, Xerox State and Local Solutions, Inc. , and approving

11822the award of the contract to Intervenor, Systems and Methods,

11832Inc.

11833DONE AND ENTERED this 18 th day of February , 2015 , in

11844Tallahassee, Leon County, F lorida.

11849S

11850DIANE CLEAVINGER

11852Administrative Law Judge

11855Division of Administrative Hearings

11859The DeSoto Building

118621230 Apalachee Parkway

11865Tallahassee, Florida 32399 - 3060

11870(850) 488 - 9675

11874Fax Filing (850) 921 - 6847

11880www.doah.state.f l.us

11882Filed with the Clerk of the

11888Division of Administrative Hearings

11892this 18 th day of February, 2015 .

11900ENDNOTE S

119021/ Xerox designated the follow ing excerpt from the audio tape:

1191317:40 - 20:32. SMI cross - designated the following excerpt to

11924Xerox's Exhibit 1 7: 17:43 - 23:38. Xerox then added the following

11936excerpt: 17:39 - 24:31.

119402/ Statutory requireme nts such as the requirement in s ection

11951287.057(13) cannot be waived by an agency.

119583/ The Department's response to October 24, 2014, vendor question

1196824 about Attachment O does not clarify whether amounts for the

11979cost items in Attachment M were mandatory since the Department's

11989answer also indicated that Attachment M should include expenses

11998for which the vendor wishes to be reimbursed. Notably,

12007Attachment M was not amended as a result of the Department's

12018response to question 24. Moreover, the Department's response to

12027October 24, 2014, vendor question 53 does not resolve the issue

12038regarding Attachment M costs since the Department's response

12046seemingly made teleco mmunications costs mandatory by use of the

12056word "shall" in relation to reporting those costs on

12065Attachment M. Again, Attachment M was not amended as a result of

12077the D epartment's response to question 53. Thus, Xerox's reply

12087was responsive to the ITN even though it did not include

12098seemingly mandatory telecommunications costs in its reply.

12105COPIES FURNISHED:

12107Cindy Horne, Esquire

12110Department of Revenue

12113Post Office Box 6668

12117Tallahassee, Florida 32314 - 6668

12122(eServed)

12123W. Robert Vezina, III, Esquire

12128Vezina, Lawrence and Piscitelli, P.A.

12133413 East Park Avenue

12137Tallahassee, Florida 32301

12140(eServed)

12141Mia L. McKown, Esquire

12145Holland and Knight, LLP

12149Post Office Drawer 810

12153Tallahassee, Florida 32302 - 1809

12158(eServed)

12159Nancy L. Staff, General Counsel

12164Department of Reven ue

12168Post Office Box 6668

12172Tallahassee, Florida 32314 - 6668

12177(eServed)

12178Marshall Stranburg, Executive Director

12182Department of Revenue

12185Post Office Box 6668

12189Tallahassee, Florida 32314 - 6668

12194(eServed)

12195NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

12201All parties have the ri ght to submit written exceptions within

122121 0 days from the date of this Recommended Order. Any exceptions

12224to this Recommended Order should be filed with the agency that

12235will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 03/20/2015
Proceedings: Agency Final Order
PDF:
Date: 03/20/2015
Proceedings: Respondent, Department of Revenue's, Response to Exceptions filed by Petitioner Xerox's State & Local Solutions, Inc. filed.
PDF:
Date: 03/20/2015
Proceedings: Systems & Methods, Inc.'s Response to Xerox's Exceptions to Corrected Recommended Order filed.
PDF:
Date: 03/20/2015
Proceedings: Xerox's Exceptions to Corrected Recommended Order filed.
PDF:
Date: 03/20/2015
Proceedings: Agency Final Order filed.
PDF:
Date: 02/27/2015
Proceedings: Corrected RO
PDF:
Date: 02/27/2015
Proceedings: Corrected Recommended Order (hearing held August 6 and 7, 2014). CASE CLOSED.
PDF:
Date: 02/27/2015
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 02/20/2015
Proceedings: Transmittal letter from Claudia Llado returning the Department of Revenue's Exhibits, which were not admitted into evidence to Respondent.
PDF:
Date: 02/19/2015
Proceedings: Transmittal letter from Claudia Llado returning Petitioner's Exhibits, which were not admitted into evidence to Petitioner.
PDF:
Date: 02/18/2015
Proceedings: Recommended Order
PDF:
Date: 02/18/2015
Proceedings: Recommended Order (hearing held August 6 and 7, 2014). CASE CLOSED.
PDF:
Date: 02/18/2015
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 01/08/2015
Proceedings: Order Granting Motion to Withdraw.
PDF:
Date: 01/07/2015
Proceedings: Attorney Matthew H. Mears' Unopposed Motion for Order Permitting Withdrawal from Representation filed.
PDF:
Date: 12/08/2014
Proceedings: Order Granting Respondent`s Motion to Discontinue Abatement and Request Issuance of Recommended Order.
PDF:
Date: 12/04/2014
Proceedings: Respondent's Motion to Discontinue Abatement and Request Issuance of Recommended Order filed.
PDF:
Date: 09/11/2014
Proceedings: Order Denying Xerox`s Motion to Strike SMI`s Reply.
PDF:
Date: 09/11/2014
Proceedings: Order Placing Case in Abeyance (parties to advise status by December 15, 2014).
PDF:
Date: 09/11/2014
Proceedings: Xerox's Motion to Strike SMI's Reply filed.
PDF:
Date: 09/11/2014
Proceedings: Systems and Methods, Inc.'s Reply to Xerox's Response to Department of Revenue's Motion to Abate the Proceedings filed.
PDF:
Date: 09/10/2014
Proceedings: Xerox's Response to the Department's Motion to Abate filed.
PDF:
Date: 09/08/2014
Proceedings: System and Methods, Inc.'s Memorandum in Opposition to the Department of Revenue's Motion to Abate the Proceedings filed.
PDF:
Date: 09/08/2014
Proceedings: Respondent's Withdrawal of Respondent's Motion Requesting that the Division of Administrative Hearings Relinquish Jurisdiction and Motion to Abate Proceedings filed.
PDF:
Date: 09/04/2014
Proceedings: Xerox's Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 09/04/2014
Proceedings: System & Methods, Inc.'s Proposed Recommended Order filed.
PDF:
Date: 09/04/2014
Proceedings: System and Methods, Inc.'s Memorandum In Opposition to the Department of Revenue's Motion to Relinquish Jurisdiction filed.
PDF:
Date: 09/03/2014
Proceedings: Respondent's Motion Requesting that Division of Administrative Hearings Relinquish Jurisdiction filed.
PDF:
Date: 09/03/2014
Proceedings: Respondent's Proposed Recommended Order filed.
Date: 08/22/2014
Proceedings: Transcript Volumes I-III (not available for viewing) filed.
PDF:
Date: 08/22/2014
Proceedings: Order Granting Extension of Time to File Proposed Recommended Orders.
PDF:
Date: 08/20/2014
Proceedings: Xerox's Unopposed Motion for Extension of Time to File Proposed Recommended Orders filed.
PDF:
Date: 08/19/2014
Proceedings: Systems and Methods, Inc.'s Depsition Designators filed.
Date: 08/06/2014
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 08/06/2014
Proceedings: Order Granting in Part Xerox`s Motion for Leave to File Second Amended Formal Written Protest Petition.
PDF:
Date: 08/05/2014
Proceedings: Joint Prehearing Stipulation filed.
PDF:
Date: 08/05/2014
Proceedings: Xerox's Motion in Limine Regarding Alleged Curing of SMI's Reply Deficiencies filed.
PDF:
Date: 08/05/2014
Proceedings: Intervenor, SMI's Joinder in Respondent's Response in Opposition to Xerox's Motion for Santions for Spoliation of Evidence filed.
PDF:
Date: 08/05/2014
Proceedings: Xerox's Motion in Limine Regarding Which Vendor Presents the Best Value to the State filed.
PDF:
Date: 08/05/2014
Proceedings: Respondent's Response to Xerox's Motion for Sanctions for Spoliation of Evidence filed.
PDF:
Date: 08/05/2014
Proceedings: Deposition of Michael Deckeiman filed.
PDF:
Date: 08/05/2014
Proceedings: Deposition of John Polk filed.
PDF:
Date: 08/05/2014
Proceedings: Deposition of James Howard filed.
PDF:
Date: 08/05/2014
Proceedings: Deposition of Jennifer Donaldson filed.
PDF:
Date: 08/05/2014
Proceedings: Notice of Filing (exhibits and depositions) (exhibits not available for viewing) filed.
PDF:
Date: 08/05/2014
Proceedings: (Intervenor's) Notice of Filing (deposition transcripts) filed.
PDF:
Date: 08/05/2014
Proceedings: Xerox's Motion for Sanctions for Spoliation of Evidence filed.
PDF:
Date: 08/05/2014
Proceedings: (Intervenor's) Objection to Xerox's Motion for Leave to File Second Amended Formal Written Protest Petition or, in the Alternative, Motion to Dismiss or Strike filed.
PDF:
Date: 08/04/2014
Proceedings: (Intervenor's) Notice of Objection to Xerox's Motion for Leave to File Second Amended Formal Written Protest Petition filed.
PDF:
Date: 08/04/2014
Proceedings: Respondent's Motion for Extension of Time to file Pre-hearing Stipulation filed.
PDF:
Date: 08/04/2014
Proceedings: Xerox's Motion for Leave to File Second Amended Formal Written Protest Petition filed.
PDF:
Date: 08/01/2014
Proceedings: Order Granting Xerox`s Motion for Leave to File Amended Formal Written Protest Petition.
PDF:
Date: 07/31/2014
Proceedings: Xerox's Notice that the Department and SMI Do Not Oppose Xerox's Motion for Leave to File Amended Formal Written Protest Petition filed.
PDF:
Date: 07/30/2014
Proceedings: Xerox's Motion for Leave to File Amended Formal Written Protest Petition filed.
PDF:
Date: 07/29/2014
Proceedings: Amended Notice of Taking Deposition (of Department of Revenue's Corporate Representative) filed.
PDF:
Date: 07/28/2014
Proceedings: Xerox's Notice of Taking Deposition (of Agency Representative for Department of Revenue) filed.
PDF:
Date: 07/28/2014
Proceedings: Amended Notice of Taking Depositions (of Mark Huff, Craig Curry, Connie Beach, and Stan Eatman) filed.
PDF:
Date: 07/25/2014
Proceedings: Notice of Cancellation of Depositions filed.
PDF:
Date: 07/24/2014
Proceedings: Notice of Taking Depositon (of Systems & Methods, Inc.'s Corporate Representative) filed.
PDF:
Date: 07/23/2014
Proceedings: Systems & Methods, Inc.'s Notice of Taking Xerox State & Local Solutions, Inc.'s Corporate Representative Deposition filed.
PDF:
Date: 07/23/2014
Proceedings: Xerox's Second Request for Production to the Department filed.
PDF:
Date: 07/21/2014
Proceedings: Xerox's Notice of Serving Verified Responses to SMI's First Set of Interrogatories filed.
PDF:
Date: 07/17/2014
Proceedings: Amended Notice of Taking Deposition (of Bo Searce, Shannon Herold, and Beth Doredant) filed.
PDF:
Date: 07/17/2014
Proceedings: Amended Notice of Taking Deposition (of John Kinneer and Max Smart) filed.
PDF:
Date: 07/17/2014
Proceedings: Stipulated Protective Order Regarding Confidential Information.
PDF:
Date: 07/16/2014
Proceedings: Notice of Taking Deposition (of Stan Eatman, Debbie Stephens, and Chris Butterworth) filed.
PDF:
Date: 07/16/2014
Proceedings: Notice of Taking Deposition (of Mark Huff, Craig Curry, and Connie Beach) filed.
PDF:
Date: 07/16/2014
Proceedings: Notice of Taking Deposition (of Babs Johnson and Tom Mato) filed.
PDF:
Date: 07/16/2014
Proceedings: Notice of Taking Deposition (of Maz Smart, Shannon Herold, and Beth Doredant) filed.
PDF:
Date: 07/16/2014
Proceedings: Notice of Taking Deposition (of Clark Rogers, Steve Updike, and Nancy Luja) filed.
PDF:
Date: 07/16/2014
Proceedings: Notice of Taking Deposition (of John Kinneer and Bo Searce) filed.
PDF:
Date: 07/09/2014
Proceedings: Systems & Methods, Inc.'s Responses to Xerox State & Local Solutions, Inc.'s First Request for Admissions filed.
PDF:
Date: 07/09/2014
Proceedings: Systems & Methods, Inc.'s Responses and Objections to Xerox State & Local Solutions, Inc.'s First Request for Production of Documents to SMI filed.
PDF:
Date: 07/09/2014
Proceedings: Systems & Methods, Inc.'s Notice of Service of Answers and Objections to Xerox State & Local Solutions, Inc.'s First Set of Interrogatories filed.
PDF:
Date: 07/03/2014
Proceedings: (Intervenor's) Unopposed Motion for Entry of Protective Order Regarding Confidential Information filed.
PDF:
Date: 07/02/2014
Proceedings: Xerox's Notice of Serving First Set of Interrogatories to SMI filed.
PDF:
Date: 07/02/2014
Proceedings: Xerox's First Request for Admissions to SMI filed.
PDF:
Date: 07/02/2014
Proceedings: Xerox's First Request for Production to SMI filed.
PDF:
Date: 06/30/2014
Proceedings: Xerox's Notice of Serving Unverified Responses to SMI's First Set of Interrogatories filed.
PDF:
Date: 06/30/2014
Proceedings: Xerox's Responses to SMI's First Request for Production filed.
PDF:
Date: 06/30/2014
Proceedings: Xerox's Responses to SMI's First Request for Admission filed.
PDF:
Date: 06/30/2014
Proceedings: Respondent's Response to Xerox's First Request for Admissions filed.
PDF:
Date: 06/30/2014
Proceedings: Respondent's Response to Petitioner's First Request for Production to the Department filed.
PDF:
Date: 06/30/2014
Proceedings: Respondent's Notice of Serving Responses to Petitioner's First Set of Interrogaties to the Department filed.
PDF:
Date: 06/25/2014
Proceedings: Intervenor, Systems & Methods, Inc.'s First Request for Admissions to Petitioner filed.
PDF:
Date: 06/25/2014
Proceedings: Intervenor, Systems & Methods, Inc.'s Notice of First Set of Interrogatories to Petitioner filed.
PDF:
Date: 06/25/2014
Proceedings: Intervenor, Systems & Methods, Inc.'s First Request for Production of Documents to Petitioner filed.
PDF:
Date: 06/24/2014
Proceedings: Xerox's Notice of Serving First Set of Interrogatories to the Department filed.
PDF:
Date: 06/24/2014
Proceedings: Xerox's First Request for Production to the Department filed.
PDF:
Date: 06/24/2014
Proceedings: Xerox's First Request for Admission to the Department filed.
PDF:
Date: 06/24/2014
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 06/24/2014
Proceedings: Notice of Hearing (hearing set for August 6 through 8, 2014; 9:30 a.m.; Tallahassee, FL).
PDF:
Date: 06/23/2014
Proceedings: Order Granting Petition to Intervene (Systems and Methods, Inc.).
Date: 06/23/2014
Proceedings: CASE STATUS: Pre-Hearing Conference Held.
PDF:
Date: 06/20/2014
Proceedings: Notice of Telephonic Status Conference (status conference set for June 23, 2014; 11:00 a.m.).
PDF:
Date: 06/20/2014
Proceedings: Xerox's Request for Issuance of Order of Pre-hearing Instructions filed.
PDF:
Date: 06/17/2014
Proceedings: Notice of Appearance (Matthew Mears) filed.
PDF:
Date: 06/17/2014
Proceedings: Notice of Appearance (Mia McKown) filed.
PDF:
Date: 06/16/2014
Proceedings: Notice of Appearance (Karen Walker) filed.
PDF:
Date: 06/16/2014
Proceedings: Notice of Intervention (filed by Systems & Methods, Inc.) filed.
PDF:
Date: 06/16/2014
Proceedings: Formal Written Protest filed.
PDF:
Date: 06/16/2014
Proceedings: Notice of Filing Protest Petition filed.

Case Information

Judge:
DIANE CLEAVINGER
Date Filed:
06/16/2014
Date Assignment:
06/16/2014
Last Docket Entry:
03/20/2015
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related Florida Statute(s) (7):