15-001559EPP
Florida Power And Light Company Turkey Point Power Plant Units 3-5 Modification To Conditions Of Certification vs.
*
Status: Closed
Recommended Order on Monday, January 25, 2016.
Recommended Order on Monday, January 25, 2016.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8FLORIDA POWER AND LIGHT COMPANY Case No. 15 - 1559EPP
18TURKEY POINT POWER PLANT UNITS
233 - 5 MODIFICATION TO CONDITIONS
29OF CERTIFICATION
31_______________________________/
32RECOMMENDED ORDER
34The final hea ring in this matter was held on December 1 - 4,
482015, in Miami, Florida, before Bram D. E. Canter, an
58Administrative Law Judge of the Division of Administrative
66Hearings (ÐDOAHÑ).
68APPEARANCES
69For Florida Power and Light Company (ÐFPLÑ) :
77Peter C. Cunningham, Esquire
81Gary V. Perko, Esquire
85Douglas S. Roberts, Esquire
89Jonathan Harrison Maurer, Esquire
93Hopping, Green and Sams, P.A.
98Post Offic e Box 6526
103Tallahassee, Florida 32314
106Peter Cocotos, Esquire
109Florida Power and Light Company
114215 South Monroe Street, Suite 810
120Tallahassee, Florida 3230 1
124For Department of Environmental Protection (ÐDEPÑ) :
131Sarah M. Doar, Esquire
135Department of Environmental Protection
139Office of General Counsel
143Mail Station 35
1463900 Commonwealth Boulevard
149Tallahassee, Florida 32399
152For South Florida Water Management District (ÐSFWMDÑ) :
160Carlyn H. Kowalsky, Esquire
164South Florida Water Management District
169Mail Stop Code 1410
1733301 Gun Club Road
177West Palm Beach, Florida 33406
182For Intervenor Atlantic Civil, Inc. (ÐACIÑ)
188Andrew J. Baumann, Esquire
192Alfred J. Malefatto, E squire
197Rachel B. Santana, Esquire
201Lewis, Longman and Walker, P.A.
206515 North Flagler Drive, Suite 1500
212West Palm Beach, Florida 33401
217S TATEMENT OF THE ISSUE
222The issue to be determined in this case is whether the
233Governor and Cabinet, in their capacity as the Siting Board and
244pursuant to the Florida Electrical Power Plant Siting Act
253(ÐPPSAÑ) , should approve FPLÓs request to modify the Conditions
262of Certification for Units 3 , 4 , and 5 of the Turkey Point Power
275Plant in southeast Miami - Dade County.
282PRELIMINARY STATEMENT
284On September 5, 2014, FPL filed a petition with DEP pursuant
295to the PPSA, chapter 403, Part II, Florida Statutes, to modify
306the Conditions of Certification for T urkey Point Units 3, 4, and
3185 to authorize three Ð system improvement projects ,Ñ including the
329construction and operation of up to six new production wells to
340withdraw 14 million gallons per day (Ð mgd Ñ) of Upper Floridan
352Aquifer (ÐUFAÑ) water for use in the Turkey Point cooling canal
363system (ÐCCSÑ) for salinity and temperature management purposes.
371On December 23, 2014, DEP issued n otice of its i ntent to modify
385the Conditions of Certification to authorize the three projects
394proposed by FPL. All required pub lic notices were published by
405FPL and DEP.
408On March 19, 2015, DEP issued a final order authorizing the
419requested modifications for which no objections had been raised.
428Miami - Dade County, Tropical Audubon Society , Inc., and SFWMD
438each filed n otices of their intent to be parties to the
450modification proceeding . Miami - Dade County and Tropical Audubon
460Society , Inc., later voluntarily withdrew from the proceeding.
468On March 24, 2015, ACI filed a Motion to Intervene , which
479was opposed by FPL. The motion to interv ene was denied for
491failing to include an adequate explanation of ACIÓs alleged
500injury, but ACI was granted leave to file another motion to
511intervene. On April 3, 2015, ACI filed an Amended Motion to
522Intervene , which was granted . O n October 30, 2015, ACI filed a
535Second Amended Motion to Intervene , which was granted over the
545objection of FPL.
548At the final hearing, Joint Exhibits 1 - 6 were admitted into
560evidence. F PL presented the testimony of: Steven Scroggs,
569Senior Director of Project Development for FPL , who was accepted
579as an expert in power plant engineering, design , and siting;
589Peter Andersen, P.E., who was accepted as an expert in
599groundwater hydrology and groundwater flow and transport
606modeling; and Gregory Powell, Ph.D. FPL also submitted pre - filed
617expert testimony of: Dr. Powell, James Andersen, Karl Bullock,
626Kerri Kitchen, Kennard Kosky, and James Lindsay. FPL Exhibits
6351 - 6, 12 - 13, 19 - 22, 44, 46, 48, 54 - 59, and 61 were admitted into
655evidence.
656DEP presented the testimony of: Ann Seiler, an Enviro nmental
666Specialist III within DEPÓs Siting Coordination Office; Justin
674Green, a former Program Administrator for the Siting Coordination
683Office; and Phillip Coram, a DEP Program Administrator who was
693accepted as an expert in environmental engineering. DEP Exhibits
70223 and 28 were admitted into evidence.
709SFWMD presented the testimony of: Simon Sunderland, SFWMDÓs
717Section Leader for Lower East Coast Planning, Permitting, and
726Compliance; and Jefferson Giddings, a Principal Scientist at
734SFWMD who was accepted as an expert in groundwater modeling.
744SFWMD Exhibits 1, 2, 10 , and 13 were admitted into evidence.
755ACI presented the testimony of: Steve Torcise, Jr., who is
765ACIÓs President; Marc Harris, a DEP employee responsible for
774issuing National Pollution Discharg e Elimination System permits
782for power plants; Steven Krupa, who is in charge of the
793hydrogeology section in the SFWMDÓs Water Supply Department and
802who was accepted as an expert in hydrogeology and geology ;
812William Nuttle, Ph.D., who was accepted as an ex pert in coastal
824wetlands hydrology with emphasis in the area of water and salt
835budgets; Elezier Wexler, who was accepted as an expert in
845groundwater hydrology and groundwater transport modeling; and
852Edward Swakon, who was accepted as an expert in groundwat er
863resources and groundwater monitoring. ACI Exhibits 9 - 1 1 , 14 - 16,
87618, 24 - 26, 28, 31, 34 - 36, 38, 42, 48 - 50, 50A, 51, 52, 57, 61, 63,
896and 65 were admitted into evidence.
902No member of the public requested the opportunity to offer
912testimony on the proposed m odification. No written comments were
922received from the public.
926The six - volume T ranscript of the final hearing was filed
938with DOAH. The parties filed proposed recommended orders that
947were considered in the preparation of this Recommended Order.
956FINDINGS OF FACT
959The P arties
9621. FPL is a subsidiary of NextEra Energy and a regulated
973Florida utility. It provides electric service to 4.7 million
982customers in 35 counties. The Turkey Point Power Plant in
992southeast Miami - Dade County is one of 14 generating facil ities
1004operated by FPL.
10072. DEP is the state agency charged with administering the
1017PPSA pursuant to c hapter 403, Part II.
10253. S FWMD is a regional agency created by c hapter 373,
1037F lorida Statutes, with regulatory authority over water use
1046permitting within its geographic jurisdiction, which includes the
1054Turkey Point Power Plant site.
10594. ACI owns 2,598 acres of land in southeast Miami - Dade
1072County approximately four miles west of the Turkey Point CCS.
1082ACI has use d its property for agriculture and limerock minin g for
1095many years and continues to do so.
11025. ACI withdraws and uses water from the Biscayne Aquifer
1112pursuant to two SFWMD w ater u se p ermit s . ACI also has a Life - of -
1132the - Mine Environmental Resource Permit issued by DEP for its
1143mining activities. T he Life - o f - the - Mine permit requires that
1158mining be terminated if monitoring data indicate the occurrence
1167of chloride concentrations greater than 250 milligrams per liter
1176(Ð mg/L Ñ) in the mine pit.
1183The Requested Modifications
11866. FPL is requesting to modify the Condi tions of
1196Certification to authorize three projects related to water use:
1205(1) construction and operation of the new UFA production wells
1215for use in the CCS; (2) utilization of one of the new production
1228wells as a dual purpose well to comply with a recent or der of the
1243U.S. Nuclear Regulatory Commission related to providing emergency
1251cooling water supplies for the nuclear - fueled Units 3 and 4; and
1264(3) re - allocation of authorized water withdrawn from an existing
1275production well for Unit 5 (Well No. PW - 3) as a s ource of process
1291water for Units 3 and 4.
12977. DEP received three written objections to the proposed
1306production wells to provide water for use in the CCS. No
1317objection s w ere raised regarding th e two other FPL projects and
1330DEP issued a final order approving th ose two modifications. This
1341proceeding involves only the proposal to construct and operat e
1351new UFA production wells to discharge water into the CCS .
1362Turkey Point
13648. FPLÓs Turkey Point property covers approximately
13719,400 acres in unincorporated Miami - D ade County , located 25 miles
1384south of the City of Miami and along the coastline adjacent to
1396Biscayne Bay.
13989. Fi ve electrical generating units were built at Turkey
1408Point . Units 1 and 2 were built in the 1960s. Unit 2 ceased
1422operating as a power generatio n facility in 2010. Units 3 and 4
1435are FloridaÓs first nuclear generating units , which FPL
1443constructed in the 1970s. Unit 5 is a natural gas combined cycle
1455generating unit brought into service in 2007.
146210. Units 1 through 4 pre - date the PPSA and were not
1475certified when they were built . However, Units 3 and 4 were
1487certified pursuant to the PPSA in 2008 when FPL applied to
1498increase the ir power output, referred to as an Ð uprate. Ñ Unit 5
1512was built after the PPSA and was certified under the Act.
1523The CCS
152511 . The Turkey Point CCS is a 5,900 - acre network of canals ,
1540which provides a heat removal function for Units 1, 3 , and 4, and
1553receives cooling tower blowdown from Unit 5.
156012. FPL constructed the CCS in compliance with a 1 971
1571consent judgment with the U.S. Department of Justice in order to
1582terminate direct discharges of heated water into Biscayne Bay.
159113. The CCS is not a certified facility under the PPSA, but
1603it is an Ðassociated facility,Ñ which means it directly supports
1614the operation of the power plant .
162114. The CCS functions like a radiator, which uses
1630evaporation, convective heat transfer, and radiated heat loss to
1639lower the water temperature. When cooling water enters the
1648plant, heat is transferred to the water by flow - through heat
1660exchangers and t hen discharged to the ÐtopÑ or northeast corner
1671of the CCS . Circulating water pumps provide counter - clockwise
1682flow of water from the discharge point, down (south) through the
169332 westernmost canals, across the southern end of the CCS, and
1704then back up the seven easternmost canals to the power plant
1715intake .
171715. The full circuit through the CCS from discharge to
1727intake takes a bout 48 hours and results in a reduction in water
1740temperature of about 10 to 15 degrees Fahrenheit.
174816. The CCS canals are unlined, so they have a direct
1759connection to the groundwater. Makeup water for the CCS comes
1769from process water, rainfall, stormwater runoff, and groundwater
1777infiltration to replace water lost by evaporation and seepage.
178617. When the CCS was first constructed, FPL and SFWMDÓs
1796predecessor, the Central and Southern Florida Flood Control
1804District, entered into an agreement to address the operation and
1814management of the CCS. The agreement has been updated from time
1825to time. The original agreement and updates calle d for
1835monitoring the potential impacts of the CCS.
184218. Operation of the CCS is also subject to a state
1853industrial wastewater permit and National Pollution Discharge
1860Elimination System (ÐNPDESÑ) permit administered by DEP. The
1868state industrial wastewater /NPDES permit is incorporated into the
1877Conditions of Certification.
1880Hypersaline Conditions
188219. The original salinity levels in the CCS were probably
1892the same as Biscayne Bay .
189820. However, because the salt in saltwater is left behind
1908when the water eva porates, the water in the CCS becomes saltier.
1920Salinity levels in the CCS are also affected by the amount of
1932rainfall, air temperature, water temperature, the volume of flow
1941from the power plant, and the rate of water circulation.
195121. In 2008, when FPL applied for certification of the
1961uprate of Units 3 and 4, it reported average salinity to be 50 to
197560 Practical Salinity Units (ÐPSUÑ). This is a ÐhypersalineÑ
1984condition, which means the salinity level is higher than is
1994typical for seawater, which is abou t 35 PSU.
200322. Higher salinity makes water denser, so the hypersaline
2012water in the CCS sinks beneath the canals and to the bottom of
2025the Biscayne Aquifer, which is about 80 feet beneath the CCS. At
2037this depth, there is a confining layer that separates th e
2048Biscayne Aquifer from the deeper Upper Floridan Aquifer. The
2057confining layer stops the downward movement of the hypersaline
2066ÐplumeÑ and it spreads out in all directions.
207423. The 2008 Conditions of Certification included a
2082Section X, entitled ÐSurfac e Water, Ground Water, Ecological
2091Monitoring,Ñ which, among other things, required FPL and SFWMD to
2102execute a Fifth Supplemental Agreement regarding the operation
2110and management of the CCS. New monitoring was required and FPL
2121was to Ðdelineate the vertica l and horizontal extent of the
2132hyper - saline plume that originates from the cooling canal systemÑ
2143and Ðdetect changes in the quantity and quality of surface and
2154ground water over time due to the cooling canal system.Ñ
216424. In response, FPL installed 14 clu sters of groundwater
2174monitoring wells, each cluster allowing data to be collected from
2184shallow, middle, and deep zones of the Biscayne Aquifer.
219325. In late 2013, salinity levels in the CCS began to
2204spike, reaching a high of 92 PSU in the summer of 2014.
221626. FPL presented evidence to show the salinity spikes in
2226recent years are attributable in part to lower than normal
2236rainfall and to high er turbidity in the CCS caused by algal
2248blooms .
225027. In addition, t he retirement of Unit 2 and the uprate of
2263Units 3 and 4 during this time - period reduced flow and
2275circulation in the CCS, which contributed to i ncreased
2284temperature s in the CCS, more evaporation, and higher salinity
2294levels .
229628. ACI contends the uprate of Units 3 and 4 is the primary
2309cause of recent, hig her water temperatures and higher salinity .
2320In support, ACI points to FPLÓs uprate application, which
2329predicted the uprate would increase CCS water temperature and
2338salinity, as well as other data indicating a correlation between
2348the uprate and higher temp erature and salinity. However, the
2358uprate application was filed before Unit 2 was decommissioned in
23682010. FPL presented evidence that elimination of the thermal
2377output from Unit 2 offset the thermal output from the uprate of
2389Units 3 and 4 , so that the to tal thermal output is now about f our
2405percent less. ACI did not refute this thermal output
2414calculation.
241529. It is undisputed that evaporation is the main cause of
2426hypersalinity in the CCS, but the testimony about the recent
2436spike in salinity and the rela tive influence of contributing
2446factors shows it is a complex subject due to the number of
2458factors, most of which vary by season and even daily. The
2469relative contribution of the factors affecting salinity in the
2478CCS is one that scientists can disagree abou t because the
2489analyses that have been conducted to date are not comprehensive
2499or meticulous enough to end reasonable disagreement.
250630. FPL has taken action to reduce salinity within the CCS
2517by adding stormwater from the L - 31E C anal (pursuant to emergency
2530orders), adding water from shallow saline water wells , and
2539remov ing sediment build - up in the canals to improve flow . Th ese
2554actions , combined with more normal rainfall , have decreased
2562salinity levels in the CCS to about 45 PSU at the time of the
2576final hea ring .
2580Saltwater Intrusion
258231. Historical data shows that when the CCS was constructed
2592in the 1970s, saltwater had already intruded inland along the
2602coast due to water withdrawals, flood control structures, and
2611other human activities.
261432. An intercepto r ditch was constructed just west of and
2625adjacent to the CCS to restrict the movement of saline water west
2637of the ditch. This was supposed to be accomplished by pumping
2648water out of the ditch as necessary to keep its water level lower
2661than the water level in the more western L - 31E Canal so that a
2676hydraulic gradient toward the east was maintained.
268333. The ÐfrontÑ or westernmost line of saltwater intrusion
2692is referred to as the saline water interface. More specifically,
2702the saline water interface is where groundwater with chloride
2711concentration of 10,000 mg/L or greater meets groundwater with a
2722lower chloride concentration. DEP classifies groundwater with a
2730chloride concentration less than 10,000 mg/L as G - II groundwater,
2742and groundwater with a chloride c oncentration equal to or greater
2753than 10,000 mg/L as G - III groundwater, so the saline water
2766interface can be described as the interface between G - II and G -
2780III groundwaters.
278234. In the 1980s, the sal ine water interface had moved just
2794west of the CCS inter ceptor ditch. Now, the saline water
2805interface is four or five miles west of the CCS, and it is still
2819moving west.
282135. The groundwater that comes from the CCS can be
2831identified by its tritium content because tritium occurs in
2840greater concentrations in CC S process water than occurs naturally
2850in groundwater. CCS water has been detected four miles west of
2861the CCS.
286336. CCS saline waters have also been detected northwest of
2873the CCS, moving in the direction of Miami - Dade CountyÓs public
2885water supply wellfiel ds.
288937. The hypersaline plume pushes the saline water interface
2898further west. Although Respondents indicated there are other
2906factors that affect saltwater intrusion, the preponderance of the
2915evidence shows the CCS is now the primary reason the saltwater
2926interface in this area is continuing to move inland.
293538. Section X of the Condition s of Certification provides
2945that, if monitoring data indicate harm or potential harm to the
2956waters of the State, then additional measures shall be required
2966by DEP to eval uate or to abate such impacts. D E P determined that
2981the CCS is harming waters of the State by contributing to
2992saltwater intrusion. Saltwater intrusion reduces the amount of
3000fresh groundwater available for natural resources and water
3008users .
301039. ACI estim ated that, with each day that passes, the
3021westward march of the saltwater interface is causing the loss of
3032855,000 more gallons of fresh groundwater from the Biscayne
3042Aquifer. Even if the amount is only half as much, it is a
3055substantial loss.
305740. The Bi scayne Aquifer is the main source of potable
3068water in Miami - Dade County and is designated by the federal
3080government as a sole source aquifer under the Safe Drinking Water
3091Act.
309241. When FPL applied to renew its NPDES permit, DEP was
3103concerned about the ef fect the CCS was having on saltwater
3114intrusion. DEP decided to administratively extend the NPDES
3122permit, rather than renew it, while the agency determined what
3132action should be taken to deal with the problem.
314142. On December 23, 2014, DEP issued a n Admin istrative
3152Order (ÐAOÑ) that requires FPL to prepare and submit for review
3163and approval a Salinity Management Plan to reduce hypersaline
3172conditions and their effect on saline water intrusion. The AO
3182was challenged in a separate administrative proceeding an d is not
3193yet in effect.
319643. A DEP administrator stated that DEP has not been able
3207to identify a specific violation of state water quality standards
3217attributable to the CCS , but his explanation did not reconcile
3227the undisputed evidence that the CCS has a g roundwater discharge
3238of hypersaline water that is contributing to saltwater intrusion.
3247Florida Administrative Code Rule 62 - 520.400, entitled ÐMinimum
3256Criteria for Ground Water,Ñ prohibits a discharge in
3265concentrations that Ðimpair the reasonable and benef icial use of
3275adjacent waters.Ñ
327744. As explained in the Conclusions of Law, this is not an
3289enforcement proceeding. However, Respondents thought it was
3296relevant to assert that FPLÓs proposal is not a response to a
3308water quality violation. If so, it is rel evant for the
3319Administrative Law Judge to state that the record evidence and
3329applicable law indicate FPL is in violation of the minimum
3339criteria for groundwater in rule 62 - 520.400.
3347Effect of the Proposed Modification on Saltwater Intrusion
335545. Responden ts emphasize that the FPL proposal is better
3365than a Ðno actionÑ alternative. However, the Conditions of
3374Certification require FPL to take action because operation of the
3384CCS is harming water resources. Asserting that FPLÓs proposal is
3394better than taking no action is no more meaningful than asserting
3405that FPLÓs proposal would be beneficial.
341146. FPL estimated that the addition of 14 mgd of water from
3423the UFA, which has a salinity of about 2 PSU, would reduce
3435salinity in the CCS to t h e salinity in Biscayne Bay , about 35
3449PSU, or even lower. ACIÓs evidence did not refute this estimate .
346147. Adding UFA water to the CCS would also reduce water
3472temperatures in the CCS. That is important in order to avoid
3483exceeding the temperature limit imposed by the Nuclear Re gulatory
3493Commission on operation of the nuclear units, Units 3 and 4. The
3505temperature limit is 104 degrees Fahrenheit and, if exceeded,
3514would require Units 3 and 4 to be shut down.
352448. The FPL proposal w ould remove the source of the
3535hypersaline water . Hypersaline water would no longer be sinking
3545beneath the CCS.
354849. FPL presented evidence to show the low saline water
3558would begin to mix with the hypersaline water already in the
3569Biscayne Aquifer, the groundwater in the area would steadily
3578Ðfreshen,Ñ and the hypersaline plume would begin to shrink and
3589eventually disappear.
359150. ACI pointed out that the salt in the CCS and in the
3604Biscayne Aquifer would not disappear, but ACI did not explain the
3615significance of that fact. ACI did not explain how the model ing
3627efforts by FPL failed to account for salt or explain how the
3639presence of salt undermines the modelÓs prediction that
3647groundwater in the area would steadily freshen and the
3656hypersaline plume would shrink and eventually disappear.
366351. The testimony of ACIÓs expert hydrologists was
3671persuasive in showing the two - dimensional groundwater model used
3681by FPL and SFWMD to analyze and predict the effect of adding UFA
3694water to the CCS was not the best tool for the task. A two -
3709dimensional model cannot account for some of the factors
3718affecting water movement and salinity. A three - dimensional model
3728produces more reliable results and is a better predictive tool
3738for these purposes. Nevertheless, differences between the
3745results obtained from the two - dimensional model ing by FPL and the
3758three - dimensional modeling by ACI do not affect the
3768recommendation to the Siting Board.
377352. FPL and SFWMD estimated that the addition of 14 mgd of
3785water into the CCS would reduce the rate of westward movement of
3797CCS hypersaline saline waters in the Biscayne Aquifer and this,
3807in turn, would slow the westward movement of the sal ine water
3819interface.
382053. No party believes the FPL proposal will halt the
3830westward movement of the sal ine water interface.
383854. ACI contends the FPL proposal wo uld worsen groundwater
3848conditions because adding water to the CCS would increase the
3858hydraulic ÐheadÑ in the CCS and exert a greater westward push on
3870groundwaters in the Biscayne Aquifer, and a greater push on the
3881existing hypersaline plume. However, the water in the CCS would
3891be less dense after the UFA water is added, which RespondentsÓ
3902experts said would offset the increase in volume. ACI did not
3913show how water density was accounted for in its own analyses. In
3925addition, ACIÓs Exhibit s 38 , 39, 42, 51, and 63 appear to support
3938RespondentsÓ contention that the FPL proposal would slow the rate
3948of saltwater intrusion.
395155. The effect of the FPL proposal on the hypersaline plume
3962is the most difficult question in the case. The evidence
3972presented necessarily relied on many assumptions about physical
3980features and processes, some of which had to be simplified for
3991practical analysis. FPLÓs evidence does not create certainty,
3999but FPL met its prima facie burden to demonstrate that the
4010proposed water use would be consistent with the public interest
4020because the modification would improve current groundwater
4027conditions. ACIÓs evidence raises serious questions, but was not
4036sufficient to rebut FPLÓs showing.
404156. Respondents estimate that it would take about 25 years
4051for the sal ine w ater interface to reach ACIÓs property if the FPL
4065proposal is implemented.
406857. ACIÓs analysis focused, instead, on the movement of an
4078advancing contour of much lower salinity, 250 mg/L, because this
4088lower level is a limit in ACIÓs permit and would disrupt ACIÓs
4100mining operations. This Ðtoo salineÑ water will reach ACIÓs
4109property in 10 years, even with the FPL proposal.
4118Water Use Regulatory Criteria
412258. ACI did not raise any issues regarding FPL Ós compliance
4133with SFWMD water use criteri a associated with the proposed
4143withdrawal, itself. ACI does not contend that the proposed
4152withdrawal of 14 mgd of water from the UFA would interfere with
4164existing legal uses , cause saltwater intrusion , harm wetlands and
4173surface waters, or adversely affect off - site land uses.
418359. SFWMD reviewed the proposed use of the UFA water in the
4195CCS for consistency with the public interest and determined that
4205the use was consistent because it would improve current
4214conditions in the CCS and Biscayne Aquifer.
422160. FPL provided reasonable assurance that the FPL proposal
4230meets all applicable water use regulatory criteria.
4237PPSA C riteria for Approval
424261. For the reasons stated above, the record evidence
4251supports an affirmative determination by the Siting Board
4259regarding the certification criteria in section 403.509(3)(a)
4266through (g).
4268CONCLUSIONS OF LAW
4271Standing
427262. S ection 403.508( 3 ) (e) de scribes the parties to a PPSA
4286certification proceeding as includ ing persons whose substantial
4294interests are affected and being determ ined by the proceeding and
4305who timely file a motion to intervene.
431263. ACI has standing in this proceeding because the
4321Conditions of Certification acknowledge and address the potential
4329for harm to water resources caused by the CCS. The harm
4340encompasses le gal uses of the water resources, like ACIÓs uses,
4351that will be affected by the operation of the CCS.
436164. Respondents cite Agrico v. Dep artment of Environmental
4370Regulation , 406 So. 2d 478, 482 (Fla. 2d DCA 1981) , in support of
4383their argument that ACI has n ot demonstrated standing because t he
4395proposed modification does not present an immediate threat to
4404ACIÓs property. The injury to ACI is immediate in the sense that
4416it is predictable based on current conditions and does not
4426require the occurrence of interv ening events or forces. ACIÓs
4436injury is no less immediate than the injury that would be
4447suffered by anyone downstream of a pollution source, when the
4457timing of the ÐimpactÑ and the concentration of the pollution at
4468the time of impact can be calculated by accepted scientific
4478methods.
4479Burden and Standard of Proof
448465. Respondents state that FPL, a s the applicant for
4494certification, has the ultimate burden of persuasion to
4502demonstrate entitlement to the requested modifications, citing In
4510re: Progress Energy Fl orida Levy Nuclear Project Units 1 and 2 ,
45222009 Fla. ENV LEXIS 151 at *114; and Fl orida Department of
4534Transp ortation v. J.W.C. Co., Inc . , 396 So. 2d 778, 787 (Fla. 1st
4548DCA 1981). However, those cases pre - date the amendment of
4559chapter 120 , Florida Statutes, to create section 120.569(2)(p).
4567This section now places the ultimate burden of persuasion on the
4578challenger in all licensing proceedings arising under chapter 403
4587after the permit applicant has introduced the permit file
4596constituting its prima facie cas e . This is a licensing
4607proceeding arising under chapter 403. Therefore, ACI has the
4616ultimate burden of persuasion in this proceeding.
462366. The standard of proof is a preponderance of the
4633evidence. See § 120.57(1)(j), Fla. Stat. (2015). FPL must
4642demonst rate by a preponderance of the evidence that it has
4653provided reasonable assurances of its compliance with all
4661applicable regulatory criteria. Reasonable assurance
4666contemplates a Ðsubstantial likelihood that the project will be
4675successfully implemented.Ñ Metro. Dade Cnty. v. Coscan Fla.,
4683Inc . , 609 So. 2d 644, 648 (Fla. 3d DCA 1992) . It does not
4698require absolute guarantees.
4701Nonprocedural Agency Requirements
470467. Section 373.223(1) provides that Ð[t]o obtain a [ water
4714use] permit pursuant to the provisions o f this chapter, the
4725applicant must establish that the proposed use of water: (a) Is a
4737reasonable - beneficial use as defined in s. 373.019; (b) Will not
4749interfere with any presently existing legal use of water; and,
4759(c) Is consistent with the public interest .Ñ
476768. ACI claims in its Proposed Recommended Order that FPL
4777failed to demonstrate a need for the amount of water it requested
4789and did not consider mitigative measures, but these issues were
4799not raised in ACIÓs amended petition to intervene.
480769. ACI clai ms the proposed use of the 14 mgd of water, in
4821contrast to the withdrawal of the water, was not properly
4831reviewed by SFWMD under the reasonable - beneficial use criteria.
4841However, SFWMD reviewed the proposed use of the water under the
4852public interest test, which is consistent with its rules and
4862practices. The FPL proposal is consistent with the public
4871interest because it would likely improve current groundwater
4879conditions. It would also reduce water temperature in the CCS to
4890avoid the shutdown of the nucle ar generating units pursuant to
4901N uclear Regulatory Commission requirements .
490770. FPLÓs proposed modification does not create any
4915inconsistencies with the industrial wastewater/NPDES permit.
492171. FPL provided reasonable assurance that the proposed
4929modificat ion would comply with all applicable water use
4938regulatory criteria.
494072. However, AC I urges the Siting Board to deny the
4951proposed modification because ACI believes it perpetuates a
4959problem created by the CCS and fails to prevent the eventual
4970contamination of the groundwater resources that ACI relies on for
4980its agricultural and mining operations. ACI does not propose a
4990condition or conditions under which FPLÓs proposal could be
4999approved.
50007 3 . ACI points out that the Conditions of Certification are
5012Ðfully en forceable,Ñ but this is not an enforcement proceeding.
5023Because the preponderance of the evidence demonstrates the FPL
5032proposal would result in an improvement in groundwater
5040conditions, the requested modification, itself, does not fail to
5049comply with the C onditions of Certification .
50577 4 . Respondents are probably correct that, in this
5067certification proceeding, it is sufficient for the Siting BoardÓs
5076approval of FPLÓs proposed modification that the modification
5084would result in an improvement over current grou ndwater
5093conditions. However, it is appropriate to inform the Siting
5102Board that the operation of the Turkey Point Power Plant, as
5113authorized by the Siting Board under the Conditions of
5122Certification, has caused harm to water resources because of the
5132effect s of the CCS, and the modification requested by FPL will
5144not prevent further harm from occurring.
5150RECOMMENDATION
5151B ased on the foregoing Findings of Fact and Conclusions of
5162Law , it is
5165RECOMMENDED that the Siting Board enter a final order
5174approving the mo difications to the Turkey Point C onditions of
5185Certification as proposed on December 23, 2014, with the addition
5195of the following condition , which was stipulated by the parties:
5205FPL shall monitor the proposed Floridan
5211production wells (F - 1, F - 2, F - 3, F - 4 an d F - 5)
5230on a quarterly basis for: water level or
5238pressure; temperature; pH, Total Dissolved
5243Solids; specific conductance; major
5247anions/cations (including chlorides); NH3;
5251total nitrogen; and total phosphorus. This
5257monitoring data shall be made available t o
5265Miami - Dade County as well as FDEP and the
5275SFWMD. On a semi - annual basis, Miami - Dade
5285County may collect groundwater samples of the
5292proposed Floridan production wells (F - 1, F - 2,
5302F - 3, F - 4 and F - 5) for constituents including
5315but not limited to 018/16 and St rontium
5323(87Sr/86Sr).
5324DONE AND ENTERED this 25th day of January , 2016 , in
5334Tallahassee, Leon County, Florida.
5338S
5339BRAM D. E. CANTER
5343Administrative Law Judge
5346Division of Administrative Hearings
5350The DeSoto Building
53531230 Apalac hee Parkway
5357Tallahassee, Florida 32399 - 3060
5362(850) 488 - 9675
5366Fax Filing (850) 921 - 6847
5372www.doah.state.fl.us
5373Filed with the Clerk of the
5379Division of Administrative Hearings
5383this 25th day of January , 2016 .
5390COPIES FURNISHED:
5392Sarah M. Doar, Esquire
5396Departme nt of Environmental Protection
5401Office of General Counsel
5405Mail Station 35
54083900 Commonwealth Boulevard
5411Tallahassee, Florida 32399
5414(eServed)
5415Peter C. Cunningham, Esquire
5419Gary V. Perko, Esquire
5423Douglas S. Roberts, Esquire
5427Jonathan Harrison Maurer, Esquire
5431Ho pping, Green and Sams, P.A.
5437Post Office Box 6526
5441Tallahassee, Florida 32314
5444(eServed)
5445Peter Cocotos, Esquire
5448Florida Power and Light Company
5453215 South Monroe Street, Suite 810
5459Tallahassee, Florida 32301
5462(eServed)
5463Carlyn H. Kowalsky, Esquire
5467South Fl orida Water Management District
5473Mail Stop Code 1410
54773301 Gun Club Road
5481West Palm Beach, Florida 33406
5486(eServed)
5487Andrew J. Baumann, Esquire
5491Alfred J. Malefatto, Esquire
5495Rachel B. Santana, Esquire
5499Lewis, Longman and Walker, P.A.
5504515 North Flagler Drive , Su ite 1500
5511West Palm Beach, Florida 33401
5516(eServed)
5517Abbie Schwaderer Raurell, Esquire
5521Miami - Dade County Attorney's Office
5527111 Northwest 1st Street , Suite 2810
5533Miami, Florida 33128
5536(eServed)
5537Anthony Justin Pinzino, Esquire
5541Florida Fish and Wildlife Conser vation Commission
5548Farris Bryant Building
5551620 South Meridian Street
5555Tallahassee, Florida 32399 - 1600
5560(eServed)
5561Adam Teitzman, Esquire
5564Florida Public Service Commission
55682450 Shumard Oak Boulevard
5572Tallahassee, Florida 32399 - 0850
5577Samuel S. Goren, Esquire
5581Go ren, Cherof, Doody and Ezrol, P.A.
55883099 East Commercial Boulevard, Suite 200
5594Fort Lauderdale, Florida 33308 - 4311
5600Kimberly Clark Menchion, Esquire
5604Department of Transportation
5607Mail Station 58
5610605 Suwannee Street
5613Tallahassee, Florida 32399
5616(eServed)
5617D eena Woodward
5620Department of State
5623Division of Historical Resources
5627RA Gray Building, 4th Floor
5632500 South Bronough Street
5636Tallahassee, Florida 32399
5639Edwin A. Steinmeyer, Esquire
5643Steinmeyer Fiveash LLP
5646310 West College Avenue
5650Tallahassee, Florida 32301
5653(e Served)
5655Christina Arzillo Shideler, Esquire
5659Department of Economic Opportunity
5663MSC 110
5665107 East Madison Street
5669Tallahassee, Florida 32399
5672(eServed)
5673Lea Crandall, Agency Clerk
5677Department of Environmental Protection
5681Mail Station 35
56843900 Commonwealth Boul evard
5688Tallahassee, Florida 32399
5691(eServed)
5692Jonathan P. Steverson, Secretary
5696Department of Environmental Protection
5700Mail Station 35
57033900 Commonwealth Boulevard
5706Tallahassee, Florida 32399
5709(eServed)
5710Craig Varn, General Counsel
5714Department of Environmental Protection
5718Mail Station 35
57213900 Commonwealth Boulevard
5724Tallahassee, Florida 32399
5727(eServed)
5728NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5734All parties have the right to submit written exceptions within
574415 days from the date of this Recommended Order. Any excepti ons
5756to this Recommended Order should be filed with the agency that
5767will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 05/09/2016
- Proceedings: Intervenor/Appellant Atlantic Civil, Inc.'s Directions to Clerk filed.
- PDF:
- Date: 05/09/2016
- Proceedings: Notice of Designation of Transcription of Siting Board Hearing filed.
- PDF:
- Date: 04/01/2016
- Proceedings: Joint Response to Intervenor Atlantic Civil, Inc.'s Exceptions to the Recommended Order filed.
- PDF:
- Date: 04/01/2016
- Proceedings: State of Florida Department of Environmental Protection's Exception to Recommended Order filed.
- PDF:
- Date: 04/01/2016
- Proceedings: Intervenor Atlantic Civil, Inc.'s Exceptions to Recommended Order filed.
- PDF:
- Date: 01/25/2016
- Proceedings: Recommended Order (hearing held December 1-4, 2015). CASE CLOSED.
- PDF:
- Date: 01/25/2016
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- Date: 12/30/2015
- Proceedings: Transcript of Proceedings (Hearing Correction Pages for Volumes I, II, IV; not available for viewing) filed.
- PDF:
- Date: 12/23/2015
- Proceedings: Intervenor-Defendant Atlantic Civil's Inc., Proposed Recommended Order filed.
- PDF:
- Date: 12/23/2015
- Proceedings: Respondent's Notice of Filing Joint Proposed Recommended Order filed.
- Date: 12/15/2015
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 12/07/2015
- Proceedings: Recieved Parties Exhibits filed (exhibits not available for viewing).
- Date: 12/01/2015
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 11/30/2015
- Proceedings: Notice of Filing Deposition Transcript of Sharon Ewe (Part III) filed.
- PDF:
- Date: 11/30/2015
- Proceedings: Notice of Filing Deposition Transcript of Sharon Ewe (Part II) filed.
- PDF:
- Date: 11/30/2015
- Proceedings: Notice of Filing Deposition Transcript of Sharon Ewe (Part I) filed.
- PDF:
- Date: 11/30/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Motion in Limine and Deposition Designations filed.
- PDF:
- Date: 11/24/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of William Nuttle) filed.
- PDF:
- Date: 11/20/2015
- Proceedings: Notice of Substitution of Counsel for Department of Economic Opportunity (Christina Shideler) filed.
- PDF:
- Date: 11/20/2015
- Proceedings: (Petitioner's) Notice of Filing Direct Written Testimony and Exhibits filed (exhibits not available for viewing).
- PDF:
- Date: 11/18/2015
- Proceedings: Tropical Notice of Withdrawing Notice of Intent to Be A Party filed.
- PDF:
- Date: 11/17/2015
- Proceedings: Re-notice of Taking Deposition Duces Tecum (of Phil Coram) filed.
- PDF:
- Date: 11/16/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Fifth Amended Witness Disclosure filed.
- PDF:
- Date: 11/13/2015
- Proceedings: Department of Environmental Protections Second Amended Witness Disclosure filed.
- PDF:
- Date: 11/12/2015
- Proceedings: Notice of Filing Florida Power & Light Companys Second Amended Witness Disclosure filed.
- PDF:
- Date: 11/12/2015
- Proceedings: Department of Environmental Protections Amended Exhibit Disclosure filed.
- PDF:
- Date: 11/11/2015
- Proceedings: Intervenor Atlantic Civil, Inc.'s Amended Exhibit Disclosure filed.
- PDF:
- Date: 11/10/2015
- Proceedings: Notice of Filing Florida Power & Light Companys Amended Exhibit List filed.
- PDF:
- Date: 11/06/2015
- Proceedings: Amended Joint Statement of Issues of Atlantic Civil and Tropical Audubon filed.
- PDF:
- Date: 11/05/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Fourth Amended Witness Disclosure filed.
- PDF:
- Date: 11/03/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Third Amended Witness Disclosure filed.
- PDF:
- Date: 11/02/2015
- Proceedings: Response in Opposition to Atlantic Civil, Inc.'s Second Amended Motion to Intervene filed.
- PDF:
- Date: 10/30/2015
- Proceedings: South Florida Water Management Districts Statement of the Issues filed.
- PDF:
- Date: 10/22/2015
- Proceedings: Florida Department of Environmental Protection's Amended Witness Disclosure filed.
- PDF:
- Date: 10/22/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Second Amended Witness Disclosure filed.
- PDF:
- Date: 10/22/2015
- Proceedings: Notice of Filing Florida Power & Light Company's Amended Witness Disclosure filed.
- PDF:
- Date: 10/14/2015
- Proceedings: Notice of Filing Proof of Publication of Rescheduling of Hearing filed.
- PDF:
- Date: 10/08/2015
- Proceedings: Notice of Cancellation of Taking Deposition Duces Tecum of William Nuttle filed.
- PDF:
- Date: 10/08/2015
- Proceedings: Notice of Filing Stipulation and Settlement Agreement Between Miami-Dade County, Florida Department of Environmental Protection, South Florida Water Management District, and Florida Power & Light Company filed.
- PDF:
- Date: 10/07/2015
- Proceedings: Notice of Cancellation of Taking Depositions Duces Tecum (of Gwen Burzycki) filed.
- PDF:
- Date: 10/06/2015
- Proceedings: Florida Power & Light Company's Objection to Notice of Deposition Duces Tecum to Scott Burns filed.
- PDF:
- Date: 10/01/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Gwen Burzycki, Lee Hefty, Pamela Sweeney, Wilbur Mayorga, and Craig Grossenbacher) filed.
- PDF:
- Date: 10/01/2015
- Proceedings: Notice of Submittal of Proof of Publication of Notice of Hearing filed.
- PDF:
- Date: 09/23/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Tom Lodge and Laura Reynolds) filed.
- PDF:
- Date: 09/22/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Steve Torcise) filed.
- PDF:
- Date: 09/10/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Eliezer Wexler) filed.
- PDF:
- Date: 09/09/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Eliezer Wexler) filed.
- PDF:
- Date: 08/27/2015
- Proceedings: South Florida Water Management District's Amended Notice of Witness Disclosure filed.
- PDF:
- Date: 07/22/2015
- Proceedings: Department of Environmental Protection's Proposed Modification of Conditions of Certification First Revised Schedule for Proceeding with Hearing filed.
- PDF:
- Date: 07/20/2015
- Proceedings: Order (rescinding the Order of April 27, 2015, establishing time limits for this certification proceeding).
- PDF:
- Date: 07/17/2015
- Proceedings: Amended Notice of Hearing (hearing set for December 1 through 4, 2015; 9:00 a.m.; Miami, FL; amended as to hearing room location).
- PDF:
- Date: 07/15/2015
- Proceedings: Notice of Submittal of Proof of Publication of Notice of Continuation of Hearing filed.
- PDF:
- Date: 07/09/2015
- Proceedings: Notice of Filing Proof of Publication of Cancellation of Hearing filed.
- PDF:
- Date: 07/09/2015
- Proceedings: Notice of Hearing (hearing set for December 1 through 4, 2015; 9:00 a.m.; Miami, FL).
- PDF:
- Date: 06/25/2015
- Proceedings: Order Granting Continuance (parties to advise status by July 1, 2015).
- PDF:
- Date: 06/25/2015
- Proceedings: Notice of Cancellation of Taking Depositions Duces Tecum of Jeff Giddings and John Janzen filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Notice of Filing Florida Power & Light Company's (Proposed) Exhibit List filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Thomas Lodge) filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Wilbur Mayorga) filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Second Amended Notice of Taking Depositions Duces Tecum (of Craig Grossenbaucher) filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Department of Environmental Protection's (Proposed) Exhibit Disclosure filed.
- PDF:
- Date: 06/24/2015
- Proceedings: South Florida Water Management District's Notice of Filing Proposed Exhibits filed.
- PDF:
- Date: 06/23/2015
- Proceedings: Notice of Miami-Dade County's (Proposed) Exhibit Disclosure filed.
- PDF:
- Date: 06/23/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Craig Grossenbacher) filed.
- PDF:
- Date: 06/23/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Pamela Sweeney) filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Atlantic Civil, Inc.'s Response to Florida Power and Light Company's Request for Admissions filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Notice of Serving Unverified Answers to Florida Power & Light Company's First Set of Interrogatories (Nos. 1-14) filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Intervenor Atlantic Civil, Inc.'s Response to Florida Power & Light Company's First Request for Production of Documents filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Tropical Audubon Society, Inc.'s Response to Florida Power & Light Company's Request for Production filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Tropical Audubon Society, Inc.'s Response to Florida Power & Light Company's First Request for Admissions filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Tropical Audubon Society, Inc.'s Notice of Serving Responses to Florida Power & Light Company's First Set of Interrogatories (Nos. 1-14) filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Peter Anderson) filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Florida Power & Light Company's Objection to Notice of Deposition Duces Tecum to Peter Andersen filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Wilbur Mayorga) filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Craig Grossenbacher) filed.
- PDF:
- Date: 06/19/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of S. Torcise and E. Wexler) filed.
- PDF:
- Date: 06/19/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Virginia Walsh) filed.
- PDF:
- Date: 06/19/2015
- Proceedings: FPL's Response in Opposition to ACI's Motion to Compel or Alternatively Motion to Strike Testimony filed.
- PDF:
- Date: 06/18/2015
- Proceedings: Atlantic Civil's Response to FPL's Objection to Atlantic Civil, Inc.'s Notice of Taking Deposition Duces Tecum of Steven Scroggs and Gregory Powell, and Motion to Compel or Alternatively Motion to Strike Testimony filed.
- PDF:
- Date: 06/18/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s Amended Witness Disclosure filed.
- PDF:
- Date: 06/18/2015
- Proceedings: Florida Power & Light Company's Objection to Notice of Deposition Duces Tecum to Gregory Powell filed.
- PDF:
- Date: 06/18/2015
- Proceedings: Florida Power & Light Company's Objection to Notice of Deposition Duces Tecum to Steven Scroggs filed.
- PDF:
- Date: 06/17/2015
- Proceedings: Florida Power & Light Company's Supplemental Response to Atlantic Civil, Inc.'s First Request for Production to FPL filed.
- PDF:
- Date: 06/17/2015
- Proceedings: Florida Power & Light Company's Notice of Serving Supplemental Response to Atlantic Civil, Inc.'s First Set of Interrogatories filed.
- PDF:
- Date: 06/17/2015
- Proceedings: Notice of Taking Deposition Duces Tecum (of Roy Soenshien and Kirk Martin) filed.
- PDF:
- Date: 06/17/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Ann Seiler) filed.
- PDF:
- Date: 06/17/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Allan Stodgill) filed.
- PDF:
- Date: 06/17/2015
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Justin Green) filed.
- PDF:
- Date: 06/15/2015
- Proceedings: Corrected Notice of Taking Deposition Duces Tecum (Simon Sunderland, P.G.) filed.
- PDF:
- Date: 06/15/2015
- Proceedings: Notice of Taking Depositions Duces Tecum (Bertha Goldenberg and Doug Yoder) filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Joint Statement of the issues of Miami-Dade County, Atlantic Civil and Tropical Audubon Society filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Notice of Filing Proof of Publication of Notice of Hearing filed.
- PDF:
- Date: 06/04/2015
- Proceedings: Notice of Serving Florida Department of Environmental Protection's Witness Disclosure filed.
- PDF:
- Date: 06/04/2015
- Proceedings: Florida Department of Environmental Protection's Witness Disclosure filed.
- PDF:
- Date: 06/03/2015
- Proceedings: Notice of Filing Florida Power & Light Company's Witness Disclosure filed.
- PDF:
- Date: 06/03/2015
- Proceedings: South Florida Water Management District's Notice of Witness Disclosure filed.
- PDF:
- Date: 05/28/2015
- Proceedings: Florida Power & Light Company's Notice of Serving Responses to the Atlantic Civil, Inc.'s First Set of Interrogatories filed.
- PDF:
- Date: 05/28/2015
- Proceedings: Florida Power & Light Co.'s Response to Atlantic Civil, Inc.'s First Request for Production to FPL filed.
- PDF:
- Date: 05/28/2015
- Proceedings: Notice of Serving Florida Department of Environmental Protection's Answers to Intervenor, Atlantic Civil, Inc.'s First Set of Interrogatories filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's First Request for Production of Documents to Miami-Dade County filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's First Request for Admissions to Miami-Dade County, Florida filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's Notice of Serving First Set of Interrogatories (Nos. 1-14) to Miami-Dade County ("MDC") filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's First Request for Production to Tropical Audubon Society, Inc., filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's First Request for Admissions to Intervenor Tropical Audubon Society, Inc., filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's Notice of Serving First Set of Interrogatories (Nos. 1-14) to Tropocal Audubon Society, Inc.,("TAS") filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's First Request for Production of Documents to Atlantic Civil, Inc., filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's First Request for Admissions to Intervenor Atlantic Civil, Inc., filed.
- PDF:
- Date: 05/21/2015
- Proceedings: Florida Power and Light Company's Notice of Serving First Set of Interrogatorties (Nos. 1-14) to Atlantic Civil, Inc., ("ACI") filed.
- PDF:
- Date: 05/19/2015
- Proceedings: South Florida Water Management District's Notice of Intent to be a Party filed.
- PDF:
- Date: 05/12/2015
- Proceedings: Notice of Submittal of Proof of Publication of Notice of Filing Petition for Modification and Notice of Hearing filed.
- PDF:
- Date: 04/28/2015
- Proceedings: Intervenor, Atlantic Civil, Inc.'s, First Request for Production to Florida Power & Light Company filed.
- PDF:
- Date: 04/28/2015
- Proceedings: (Intervenor's) Notice of Serving First Set of Interrogatories to Respondent Florida Department of Environmental Protection filed.
- PDF:
- Date: 04/28/2015
- Proceedings: (Intervenor's) Notice of Serving First Set of Interrogatories to Petitioner Florida Power & Light Company filed.
- PDF:
- Date: 04/28/2015
- Proceedings: Amended Notice of Hearing (hearing set for July 13 through 17, 2015; 9:00 a.m.; Miami, FL; amended as to hearing room location).
- PDF:
- Date: 04/27/2015
- Proceedings: Order (on Proposed Modification of Conditions of Certification Schedule and Stipulation for Establishment of Time Limits).
- PDF:
- Date: 04/24/2015
- Proceedings: Department of Environmental Protection's Proposed Modification of Conditions of Certification Schedule and Stipulation for Establishment of Time Limits filed.
- PDF:
- Date: 04/20/2015
- Proceedings: (FPL's) Notice of Filing Amended Response to Motion to Consolidate filed.
- PDF:
- Date: 04/17/2015
- Proceedings: (Department's) Response in Opposition to Joint Motion to Consolidate for Hearing and Discovery Purposes filed.
- PDF:
- Date: 04/10/2015
- Proceedings: Joint Motion to Consolidate for Hearing and Discovery Purposes by Miami-Dade County, Tropical Audubon, and Atlantic Civil, Inc. filed.
- PDF:
- Date: 04/10/2015
- Proceedings: Florida Power & Light Company's Response to Amended Motion to Intervene Filed by Atlantic Civil, Inc. filed.
- PDF:
- Date: 03/31/2015
- Proceedings: Florida Power & Light Company's Response in Opposition to Motion to Intervene Filed by Atlantic Civil, Inc. filed.
- PDF:
- Date: 03/30/2015
- Proceedings: Notice of Hearing (hearing set for July 13 through 17, 2015; 9:00 a.m.; Miami, FL).
- PDF:
- Date: 03/24/2015
- Proceedings: Atlantic Civil, Inc.'s, Response in Opposition to Florida Power and Light's Request for Expedited Administrative Hearing filed.
- PDF:
- Date: 03/19/2015
- Proceedings: Letter to Justin Green from Matthew Raffenberg regarding submitting a petition for modification.
- PDF:
- Date: 03/19/2015
- Proceedings: Written Objections to the Proposed Modifications to Florida Power and Light Company Turkey Point Plant Units 3 and 4 Nuclear Power Plant Unit 5 Combines Cycle Plant - Conditions of Certification PA03-45E filed.
- PDF:
- Date: 03/19/2015
- Proceedings: Miami-Dade County's Response and Objections to Notice of Intent to Modify Conditions of Certification filed.
- PDF:
- Date: 03/19/2015
- Proceedings: Petition for Modification of Certification and Expedited Administrative Proceedings filed.
Case Information
- Judge:
- BRAM D. E. CANTER
- Date Filed:
- 03/19/2015
- Date Assignment:
- 03/20/2015
- Last Docket Entry:
- 05/09/2016
- Location:
- Miami, Florida
- District:
- Southern
- Agency:
- ADOPTED IN PART OR MODIFIED
- Suffix:
- EPP
Counsels
-
Andrew J. Baumann, Esquire
Lewis, Longman and Walker, P.A.
Suite 1500
515 North Flagler Drive
West Palm Beach, FL 33401
(561) 640-0820 -
Peter Cocotos, Esquire
Florida Power & Light Company
215 South Monroe Street, Suite 810
Tallahassee, FL 32301
(850) 521-3920 -
Jeffrey A. Collier, Esquire
South Florida Water Management District
Mail Stop Code 1410
3301 Gun Club Road
West Palm Beach, FL 33406
(561) 682-6778 -
Peter C Cunningham, Esquire
Hopping, Green and Sams, P.A.
Post Office Box 6526
Tallahassee, FL 32314
(850) 222-7500 -
Sarah M. Doar, Esquire
Department of Environmental Protection
Mail Stop 35
3900 Commonwealth Boulevard
Tallahassee, FL 32399
(850) 245-2284 -
Aaron Charles Dunlap, Esquire
Department of Economic Opportunity
107 East Madison Street
Caldwell Building, MSC110
Tallahassee, FL 32399
(850) 245-7150 -
Samuel S. Goren, Esquire
Goren, Cherof, Doody and Ezrol, P.A.
3099 East Commercial Boulevard, Suite 200
Fort Lauderdale, FL 333084311
(954) 771-4500 -
Dennis Alexander Kerbel, Esquire
Miami-Dade County
Suite 2810
111 Northwest 1st Street
Miami, FL 33128
(305) 375-5151 -
Brooke E. Lewis, Esquire
Hopping Green and Sams, P.A.
Suite 300
119 South Monroe Street
Tallahassee, FL 32300
(850) 425-3464 -
Benjamin M. Melnick, Esquire
Department of Environmental Protection
Mail Station 35
3900 Commonwealth Boulevard
Tallahassee, FL 32399
(850) 245-2194 -
Kimberly Clark Menchion, Assistant General Counsel
Department of Transportation
Mail Station 58
605 Suwannee Street
Tallahassee, FL 323990450
(850) 414-5293 -
Gary V. Perko, Esquire
Hopping Green and Sams, P.A.
Post Office Box 6526
Tallahassee, FL 32314
(850) 222-7500 -
Anthony Justin Pinzino, Esquire
Florida Fish and Wildlife Conservation Commission
Farris Bryant Building
620 South Meridian Street
Tallahassee, FL 323991600
(850) 487-1764 -
James Michael Porter, Esquire
James M. Porter, P.A.
9350 South Dixie Highway, 10th Floor
Miami, FL 33156 -
Abbie Schwaderer Raurell, Esquire
Miami-Dade County Attorney's Office
Suite 2810
111 Northwest 1st Street
Miami, FL 33128
(305) 375-5151 -
Adam Teitzman, Esquire
Florida Public Service Commission
2450 Shumard Oak Boulevard
Tallahassee, FL 323990850 -
Deena Woodward
Department of State
RA Gray Building, 4th Floor
500 South Bronough Street
Tallahassee, FL 32399 -
Jennifer D. Brown, Esquire
South Florida Water Management District
Mail Stop Code 1410
3301 Gun Club Road
West Palm Beach, FL 33406
(561) 682-2791 -
Rachael Bruce, Esquire
Lewis, Longman & Walker, P.A.
Suite 1500
515 North Flagler Drive
West Palm Beach, FL 33401
(561) 640-0820 -
Erin L. Deady, Esquire
Erin L. Deady, P.A.
1111 Hypoluxo Road, Suite 207
Lantana, FL 33462
(954) 593-5102 -
Sarah M. Doar, Esquire
Dept. of Environmental Protection - Office of General Counsel
3900 Commonwealth Blvd.
#MS-35
Tallahassee, FL 32399
(850) 245-2284 -
Alfred J Malefatto, Esquire
Lewis Longman & Walker, P.A.
515 North Flagler Drive
Suite 1500
West Palm Beach, FL 33401
(561) 660-0820 -
Edwin A. Steinmeyer, Esquire
Lewis, Longman, and Walker, P.A.
Suite 100
2600 Centennial Place
Tallahassee, FL 32308
(850) 222-5702 -
Carlyn H. Kowalsky, Esquire
Address of Record -
Jonathan Harrison Maurer, Attorney
Address of Record -
James Edward Nutt, Senior Practice Expert
Address of Record -
Doug S. Roberts, Esquire
Address of Record -
Rachael B. Santana, Esquire
Address of Record -
Amelia A. Savage, Esquire
Address of Record -
Christina Arzillo Shideler, Esquire
Address of Record -
Jennifer Brown, Esquire
Address of Record -
Adam Jared Teitzman, Esquire
Address of Record -
Amelia A Savage, Esquire
Address of Record -
Edwin A Steinmeyer, Esquire
Address of Record -
Adam Jared Teitzman, Commission Clerk
Address of Record