15-003082BID The Middlesex Corporation vs. Department Of Transportation
 Status: Closed
Recommended Order on Monday, December 7, 2015.


View Dockets  
Summary: Award of contract is contrary to specifications and governing statute.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8THE MIDDLESEX CORPORATION,

11Petitioner,

12vs. Case No. 15 - 3082BID

18DEPARTMENT OF TRANSPORTATION,

21Respondent,

22and

23PRI N CE CONTRACTING, L.L.C.,

28Intervenor.

29_______________________________/

30RECOMMENDED ORDER

32On September 28 through October 1, 2015, an administrative

41hearing in this case was conducted in Tallahassee, Florida,

50before William F. Quattlebaum, Administrative Law Judge, Division

58of Administrative Hearings.

61APPEARANCE S

63For Petitioner: Brian A. Newman, Esquire

69Brandice D. Dickson, Esquire

73Pennington, P.A.

75215 South Monroe Street, Second Floor

81Post Office Box 10095

85Tallahassee, Florida 32302 - 2095

90For Respondent: C. Denise Johnson, Esquire

96Department of Transportation

99Haydon Burns Building, Mail Station 58

105605 Suwannee Street

108Tallahassee, Florida 32399 - 0458

113For Inte rvenor: Karen D. Walker, Esquire

120Tiffany A. Roddenberry, Esquire

124Holland and Knight, LLP

128Suite 600

130315 South Calhoun Street

134Tallahassee, Florida 32301

137STATEMENT OF THE ISSUE

141The issue in this case is whether the Department of

151Transportation's (DOT) proposed award of a Ðdesign - buildÑ

160cont ract to Prince Contracting, LLC (Prince) , is contrary to the

171agency's governing statutes, rules or policies, or the

179specifications of th e Request for Proposals (RFP).

187PRELIMINARY STATEMENT

189DOT is seeking to award a contract pursuant to an RFP issued

201in September 2014 for the design and construction of highway

211improvements referenced herein.

214On April 14, 2015, DOT issued notice of its i ntent to award

227the contract to Prince. The Middlesex Corporation (Middlesex)

235filed a protest challenging the proposed award and requesting a

245hearing.

246On May 28, 2015, DOT forwarded the challenge to the Division

257of Administrative Hearings (DOAH). DOT al so forwarded a Notice

267of Intervention filed with DOT by Prince, which was granted.

277Based upon the information set forth in the referral, DOAH

287sch eduled the hearing for August 5 through 7, 2015. The hearing

299was subsequently rescheduled for September 28 th rough October 2,

3092015.

310On Septembe r 17, 2015, Middlesex filed an U nopposed Motion

321for Leave to File First Amended Petition, which was granted at

332the commencement of the hearing.

337On September 18, 2015, the parties filed a Joint Pre - hearing

349Stipulation that included a statement of admitted facts which

358have been adopted and incorporated herein as necessary.

366At the hearing, Middlesex presented the testimony of four

375witnesses and had Exhibits 1 through 7, 9 through 11, 13 through

38716, 18, 19, 22, 24, 27 t hrough 39, and 41 admitted into evidence.

401DOT presented the testimony of one witness. Prince presented the

411testimony of three witnesses and had Exhibits 1, 2, 4 through 6,

4238 through 11, 15, 19 through 21, 23 through 30, 32, and 46

436through 48 admitted int o evidence. Joint E xhibits 1 through 30

448were admitted by stipulation of the parties.

455A Transcript of the hearing was filed on Octobe r 27, 2015.

467All parties filed proposed recommended o rders that have been

477reviewed in the preparation of this Recommended Order.

485FINDING S OF FACT

4891. DOT is seeking to award a Ðdesign - buildÑ contract

500pursuant to RFP E7K24 for design and construction of additional

510lanes on I - 75/SR 93 (I - 75) in Hernando County from south of

525US 98/Cortez Boulevard to north of US 98/SR 50/Cor tez Boulevard,

536and from north of US 98/SR 50/Cortez Boulevard to the

546Hernando/Sumter County l ine. The project also includes

554reconstruction and rehabilitation of existing I - 75 lanes,

563replacement of the I - 75 bridges over US 98/SR 50, various

575improvements to the interchange and its ramps, added lanes and

585resurfacing of a portion of US 98/SR 50 in Hernando County, and

597other work as described in the RFP.

6042. Middlesex and Prince are qualified design - build firms

614capable of performing the project tasks required b y the RFP.

625DOT employed a two - phase process in seeking to award the

637contract.

6383. Phase One began with the solicitation of Expanded

647Letters of Interest (ELOIs) from design - build firms. The ELOIs

658were evaluated and scored by DOT to develop a Ðshortlist Ñ of four

671qualified firms.

6734. Phase Two commenced with the release of the formal RFP

684to the four firms on the shortlist. In response to the RFP, the

697shortlisted firms were to submit ÐTechnical ProposalsÑ and ÐPrice

706ProposalsÑ to DOT. The Technical Pro posals were to be scored by

718DOT, after which DOT was to calculate an Ðadjusted scoreÑ based

729on a formula that referenced the ELOI and Technical Proposal

739scores and the Price Proposals.

7445. On July 7, 2014, DOT posted an advertisement of the ELOI

756solicita tion. The deadline for submission of ELOIs was August 1,

7672014. DOT received timely ELOI submissions from seven firms.

776DOT scored the submissions and developed the shortlist of the

786four firms. Prince and Middlesex were included on the shortlist

796and were invited to submit responses to the RFP.

8056. According to the RFP, the DOT ÐConcept PlanÑ for the

816project was for the construction of a ÐSingle Point Diamond

826InterchangeÑ (also known as a Single Point Urban InterchangeÑ and

836referred to herein as a ÐSPUIÑ ) at the intersection of I - 75 and

851US 98/SR 50.

8547. The SPUI concept plan was developed by an engineering

864firm retained by DOT that issued an ÐInterchange Operational

873Analysis Report Ñ (IOAR) for the project. The IOAR was part of a

886ÐProject Development an d EnvironmentalÑ (PD&E) study, apparently

894required to obtain federal approval and funding of the project.

9048. The RFP included an ÐAlternative Technical ConceptÑ

912(ATC) process which allowed a firm to submit an alternative

922concept to DOT for review and ap proval (or disapproval) prior to

934the deadline for submission of responses to the RFP. Upon

944receiving DOT approval of the alternative concept, the firm could

954prepare a Technical Proposal based on the ATC. The RFP provided

965that DOT would not disclose a pro posed ATC to other bidders prior

978to the submission of Technical Proposals. The RFP also required

988DOT to issue an addendum to the RFP if an approved ATC had the

1002effect of altering the RFP specifications.

10089. The RFP specifically addressed the process gov erning

1017approval of an ATC, in relevant part, as follows:

1026B. Innovative Aspects:

1029All innovative aspects shall be

1034identified separately as such in the

1040technical proposal.

1042An innovative aspect does not include

1048revisions to specifications, standards o r

1054established Department policies.

1057Innovation should be limited to Design -

1064Build FirmÓs means and methods, roadway

1070alignments, approach to project, etc.

10751. Alternative Technical Concept (ATC)

1080Proposals

1081The ATC process allows innovation,

1086flexibility, time and cost savings on the

1093design and construction of Design - Build

1100Projects while providing the best value

1106for the public. Any deviation from the

1113RFP for which th e Design - Build Firms

1122seeks [sic] to obtain approval to utilize

1129prior to Technical Proposal submission

1134is, by definition, an ATC and therefore

1141must be submitted to the Department for

1148consideration through the ATC process.

1153Any proposed material or technology not

1159addressed by the RFP is considered an ATC

1167and therefore must be submitted to the

1174Dep artment for consideration through the

1180ATC process. The proposed ATC shall

1186provide an approach that is equal to or

1194better than the requirements of the RFP,

1201as determined by the Department. ATC

1207Proposals which reduce the scope,

1212quality, performance, or rel iability

1217should not be proposed. A proposed

1223concept does not meet the definition of

1230an ATC if the concept is contemplated by

1238the RFP.

1240The Department will keep all ATC

1246submissions confidential prior to the

1251Final Selection of the Proposer to the

1258fullest extent allowed by law, with few

1265exceptions. Although the Department will

1270issue an addendum for all ATC proposals

1277contained in the list below, the

1283Department will endeavor to maintain

1288confidentiality of the Design - Build Firms

1295specific ATC proposal. Prior to

1300approving ATCÓs which would result in the

1307issuance of an Addendum as a result of

1315the item being listed below, the Design -

1323Build Firm will be given the option to

1331withdraw previously submitted ATC

1335proposals . . . .

1340* * *

13432. One - on - One ATC Proposal Dis cussion

1353Meetings

1354One - on - One ATC discussion meetings may be

1364held in order for the Design - Build Firm

1373to describe proposed changes to supplied

1379basic configurations, Project scope,

1383design criteria, and/or construction

1387criteria. Each Design - Build Firm with

1394proposed changes may request a One - on - One

1404ATC discussion meeting to describe the

1410proposed changes. The Design - Build Firm

1417shall provide, by the deadline shown in

1424the Schedule of Events of this RFP, a

1432preliminary list of ATC proposals to be

1439reviewed and dis cussed during the One - on -

1449One ATC discussion meetings. This list

1455may not be inclusive of all ATCÓs to be

1464discussed but it should be sufficiently

1470comprehensive to allow the Department to

1476identify appropriate personnel to

1480participate in the One - on - One ATC

1489di scussion meetings. The purpose of the

1496One - on - One ATC discussion meeting is to

1506discuss the ATC proposals, answer

1511questions that the Department may have

1517related to the ATC proposal, review other

1524relevant information and when possible

1529establish whether the p roposal meets the

1536definition of an ATC thereby requiring

1542the submittal of a formal ATC submittal.

1549The meeting should be between

1554representatives of the Design - Build Firm

1561and/or the Design - Build Engineer of

1568Record and District/Central Office staff

1573as needed to provide feedback on the ATC

1581proposal. Immediately prior to the

1586conclusion of the One - on - One ATC

1595discussion meeting, the Department will

1600advise the Design - Build Firm as to the

1609following related to the ATC proposals

1615which were discussed:

1618¤ The Propo sal meets the criteria

1625established herein as a qualifying ATC

1631Proposal; therefore an ATC Proposal

1636submission IS required, or

1640¤ The Proposal does not meet the

1647criteria established herein as a

1652qualifying ATC proposal since the

1657Proposal is already allowed or

1662contemplated by the original RFP;

1667therefore an ATC Proposal submission is

1673NOT required.

16753. Submittal of ATC Proposals.

1680All ATC submittals must be in writing and

1688may be submitted at any time following

1695the Shortlist Posting but shall be

1701submitted prior to the deadline shown in

1708the Schedule of Events of this RFP.

1715* * *

17184. Review and Approval of ATC Submittals

1725* * *

1728Approved Design Exceptions or Design

1733Variations required as part of an

1739approved ATC submittal will result in the

1746issuance of an addendum to the RFP

1753notifying all Shortlisted Design - Build

1759Firms of the approved Design Exceptions

1765or Design Variation(s). Such a change

1771will be approved by the FHWA, as

1778applicable. Prior to approving ATCÓs

1783which would result in the issuance of an

1791Adden dum as a result of the Design

1799Exceptions and/or Design Variation, the

1804Design - Build Firm will be given the

1812option to withdraw previously submitted

1817ATC proposals. (Emphasis added ) .

1823The FHWA is the Federal Highway Administration.

183010. RFP also establish ed requirements that were not to be

1841changed other than by amendment or addenda issued by DOT. In

1852relevant part, the RFP provided as follows:

1859Any changes to requirements of the RFP by

1867a Design - Build Firm must be approved by

1876the Department through the Alter native

1882Technical Concept (ATC) Proposal process,

1887as described herein, prior to the

1893information cut - off date. For this

1900Project, the Department considers the

1905following to be requirements of the

1911Project that shall not be changed by the

1919Design - Build Firms exc ept as specifically

1927modified by the RFP and associated

1933addenda :

1935* * *

1938Provide a clear ten foot mowing strip

1945adjacent to the right of way.

1951* * *

1954A Diverging Diamond Interchange will not

1960be accepted.

1962A Compressed/Tight Urban Design

1966Interchange wil l not be accepted.

1972The northbound exit ramp from I - 75 to

1981SR 50 shall not be shortened to exclude

1989the portion for the future flyover.

1995SR 50 shall consist of Concrete Pavement.

2002* * *

2005The SR 50 median shall be designed to and

2014accommodate the future fl yover.

2019* * *

2022SR 50 shall be designed with seven (7)

2030foot Buffered Bicycle Lanes, including

2035but not limited to, minimum twelve (12)

2042foot wide thru and turn lanes. The

2049median width shall not be reduced to

2056accommodate the seven (7) foot Buffered

2062Bicycle Lanes . . . . The concrete

2070pavement shall be placed full width

2076incorporating the four 12 - foot thru

2083lanes, twelve (12) foot turn lanes, seven

2090foot Buffered Bicycle Lanes and offsets

2096to any islands from the furthest point of

2104the begin and end of the curb re turns of

2114the ramps east and west of SR 50 . . . .

2126(Emphasis added ) .

213011. Despite the RFPÓs clear declaration that ÐTight Urban

2139Interchange DesignsÑ (TUDI) would not be accepted, both Middlesex

2148and Prince proposed ATCs for construction of TUDIs during the ATC

2159review period. DOT rejected the TUDI proposals.

216612. Prince also submitted an ATC proposing construction of

2175a ÐPartial CloverleafÑ (PARCLO) interchange design. DOT approved

2183PrinceÓs request to proceed with the PARCLO ATC.

219113. DOT issued nine addenda to the RFP prior to the

2202deadline for submission of Technical Proposals.

220814. The deadline for submission of T echnical Proposals was

2218December 19, 2014. Prince proposed construction of the PARCLO

2227concept in its Technical Proposal. The Technical Proposal

2235submitted by Middlesex proposed to construct a SPUI concept

2244referenced in the RFP.

224815. On January 29, 2015, DOT conducted a question and

2258answer session with each firm that submitted a Technical

2267Proposal. DOT issued three more addenda (#10, #11 , and #12) to

2278the RFP after the Technic al Proposal submission deadline and

2288allowed each firm to submit an Addendum to its Technical Proposal

2299by March 10, 2015.

230316. On March 19, 2015, DOT conducted a second question and

2314answer session with each firm that submitted a Technical Proposal

2324and an Addendum to its Technical Proposal.

233117. DOTÓs Technical Review Committee (TRC) evaluated and

2339scored all of the submitted Technical Proposals.

234618. The RFP prohibits DOT from scoring a non - responsive

2357proposal. Th e RFP specifically provided as follows:

2365Non - Responsive Proposals

2369Proposals found to be non - responsive

2376shall not be considered. Proposals may

2382be rejected if found to be in

2389nonconformance with the requirements and

2394instructions herein contained. A

2398prop osal may be found to be non -

2407responsive by reasons, including, but not

2413limited to, failure to utilize or

2419complete prescribed forms, conditional

2423proposals , incomplete proposals,

2426indefinite or ambiguous proposals,

2430failure to meet deadlines and improper

2436and/or undat ed signatures. (Emphasis

2441added ) .

244419. The Prince PARCLO design has not been approved by the

2455FHWA. Both Prince and DOT concede that construction of the

2465PARCLO design is conditional on approval by the FHWA.

247420. Although the RFP allowed for the waiver of minor

2484irregularities in a proposal, the RPF precluded DOT from waiving

2494irregularities that affect the price of a proposal to the

2504disadvantage of other bidders. The RPF provided as follows:

2513Waiver of Irregularities

2516The Department may waive mino r

2522informalities or irregularities in

2526proposals received when such is merely a

2533matter of form and not substance, and the

2541correction or waiver of which is not

2548prejudicial to other Proposers. Minor

2553irregularities are defined as those that

2559will not have an ad verse effect on the

2568DepartmentÓs interest and will not affect

2574the price of the Proposals by giving a

2582Proposer an advantage or benefit not

2588enjoyed by other Proposers.

25921. Any design submittals that are part

2599of a proposal shall be deemed preliminary

2606only.

26072. Preliminary design submittals may

2612vary from the requirements of the Design

2619and Construction Criteria. The

2623Department, at their discretion, may

2628elect to consider those variations in

2634awarding points to the proposal rather

2640than rejecting the entire p roposal.

26463. In no event will any such elections

2654by the Department be deemed to be a

2662waiving of the Design and Construction

2668Criteria.

26694. The Proposer who is selected for the

2677Project will be required to fully comply

2684with the Design and Construction C riteria

2691for the price bid, regardless that the

2698proposal may have been based on a

2705variation from the Design and

2710Construction Criteria.

27125. Proposers shall identify separately

2717all innovative aspects as such in the

2724Technical Proposal. An innovative aspect

2729does not include revisions to

2734specifications or established Department

2738policies. Innovati ons should be limited

2744to Design Î Build FirmÓs means and methods,

2752roadway alignments, approach to Project,

2757use of new products, new uses for

2764established products, etc.

27676. The Proposer shall obtain any

2773necessary permits or permit modifications

2778not already provided.

27817. Those changes to the Design Concept

2788may be considered together with

2793innovative construction techniques, as

2797well as other areas, as the basis for

2805gradi ng the Technical Proposals in the

2812area of innovative measures.

281621. The TRCÓs technical scores were publicly announced on

2825April 9, 2015, which was also the deadline for submission of

2836sealed Price Proposals. After the technical scores were

2844announced, t he sealed Price Proposals were opened.

285222. Prince submitted the lowest Price Proposal with a bid

2862of $84,937,900. Middlesex submitted the second lowest Price

2872Proposal of $94,664,000.

287723. As provided in the RFP, the contract was to be awarded

2889to the f irm w ith the lowest adjusted score. The adjusted scores

2902were calculated pursuant to the formula set forth in the RFP, and

2914the proposals were ranked.

291824. Prince had the lowest adjusted score of 1,069,746.851.

2929Middlesex had the next lowest adjusted scor e of 1,083,112.128.

294125. DOT posted the Notice of Intent to award the contract

2952to Prince on April 14, 2015.

295826. Middlesex timely complied with all requirements to

2966protest the contract award in this proceeding.

297327. Middlesex correctly asserts that t he Prince PARCLO

2982proposal is non - responsive to various requirements of the RFP.

299328. Middlesex asserts that the Prince PARCLO proposal fails

3002to comply with the RFP requirements regarding northbound exit

3011lanes from I - 75 onto SR 50. The evidence supports the assertion.

3024Addendum #10 to the RFP required as

3031follows:

3032The north and southbound I - 75 exit ramps

3041to west and eastbound SR 50 shall consist

3049of triple lefts and shall provide for

3056two (2) WB62FL semi - trucks in the outside

3065two (2) lanes, turning left parallel to

3072each other at the same time through the

3080entire turn at a minimum, with at least

3088four (4) foot separation between those

3094vehicles and at least 10 feet of

3101separation between the outermost vehicles

3106in the opposing left turn movements.

3112(Emph asis a dded ) .

311829. The Prince proposal does not comply with this

3127requirement. During a pre - submittal meeting, Prince initially

3136proposed a variation from the Ðtriple leftÑ requirement for the

3146northbound exit ramp that included dual left and dual right turn

3157lane s with a shared left - right fifth lane. After DOT expressed

3170concern with the shared lane proposal, Prince revised the plan to

3181include only dual right and dual left turn lanes.

319030. Prince asserts that DOT approved its deviation from the

3200triple left turn lane requirement, essentially by silent

3208acquiescence during the meeting. Although Prince and DOT

3216discussed the issue, there is no evidence that DOT affirmatively

3226approved PrinceÓs deviation from the RFP triple - left requirement.

323631. At the hearing, Prin ce stated that it will comply with

3248the triple - left requirement at the proposed price, if DOT and/or

3260the FHWA insist.

326332. Middlesex asserts that the Prince proposal fails to

3272comply with RFP requirements regarding placement of Ðstop barsÑ

3281on exit lanes fr om I - 75 onto SR 50. The evidence supports the

3296assertion.

3297Addendum #10 to the RFP required as

3304follows:

3305It is acceptable to utilize parallel

3311cross walks across the ramps terminals

3317along SR 50, although adjustments should

3323be made to accommodate drainage

3328structures. However, for all interchange

3333types, the lead vehicles (at a minimum)

3340at the stop bar, shall be in front of the

3350bridge retaining wall and have no sight

3357obstructions at SR 50. (Emphasis added ) .

336533. The Prince proposal does not comply with t his

3375requirement. The requirement that the stop bar be placed in

3385front of a bridge retaining wall is for purposes of safety. The

3397Prince proposal results in a stop bar being located behind the

3408bridge retaining wall, creating a sight obstruction at SR 50.

3418Such a sight obstruction poses a safety hazard to drivers,

3428especially to drivers who fail to comply with traffic signals.

3438The failure to comply with this requirement also creates a

3448potential safety problem for pedestrians, because a driver must

3457pro ceed in to the pedestrian cross walk in order to clear the sight

3471obstruction.

347234. Prince suggested that the stop bar placement in its

3482proposal is preliminary and subject to change. However,

3490compliance with this requirement would require lengthening the

3498I - 75 br idges to provide additional space between bridge retaining

3510walls. Increasing the length of the bridges increases the

3519expense of constructing the project. Allowing a firm to deviate

3529from this requirement provides a substantial financial advantage

3537over oth er firms that complied with the requirement.

354635. At the hearing, Prince stated that it would comply with

3557the stop bar placement requirement at the proposed price, if

3567required to do so.

357136. Middlesex asserts that the Prince proposal fails to

3580comply with the RFP requirements regarding Ðth ru - lanesÑ on SR 50.

3593The evidence supports the assertion.

359837. In regards to SR 50 thr u - lanes, Addendum 7 of the RFP

3613provided as follows:

3616The concrete pavement shall be placed

3622full width incorporating the four 12 - foot

3630thru lanes, twelve (12) foot turn lanes,

3637seven (7) foot Buffered Bicycle Lanes and

3644offsets to any islands from the furthest

3651point of the begin and end of the curb

3660returns of the ramps east and west of

3668SR 50. (Emphasis added ) .

367438. Although only three t hr u - lanes on each side are

3687intended to be used for traffic when this project is completed,

3698the RFP clearly required installation of concrete pavement for

3707the full width of four thr u - lanes traveling on SR 50 in both east

3723and west directions through the inte rchange. The unused lanes

3733are intended to accommodate future expansion of SR 50.

374239. The Prince proposal fails to include four concrete

3751thr u - lanes in each direction on SR 50. The Prince proposal

3764includes only three westbound thr u - lanes on SR 50. The Middlesex

3777proposal includes concrete pavement of all lanes required by the

3787RFP.

378840. Prince asserts that DOTÓs acceptance of the Prince ATC

3798concept included approval of its deviation from the thr u - la ne

3811requirement. There is no evidence that DOT affirmat ively

3820approved the deviation.

382341. The RFP requires that DOT issue an addendum to notify

3834firms of ATC - proposed deviations from the RFP that result in

3846modification or abandonment of RFP requirements. DOT did not

3855issue an addendum that modified or abandon ed the referenced thr u -

3868lane requirement.

387042. The number of thr u - lanes impacts the cost of the

3883project th r ough both materials and construction expenses.

3892Allowing a firm to deviate from the thr u - lane requirement

3904provides a substantial financial advantage over firms that compl y

3914with the requirement.

391743. Middlesex asserts that the Prince ATC proposal fails to

3927comply with the traffic analysis requirements set forth in the

3937RFP. According to the RFP, any proposed modification from the

3947SPUI Concept Plan mus t be supported by a traffic analysis

3958demonstrating a ÐLevel - of - Service and reduction in delay

3969throughout the year that is better than or equal to the Concept

3981Plan configuration.Ñ The RFP further required that the traffic

3990analysis demonstrate that the conc ept is equal to or better than

4002the SPUI Concept Plan for Ðall movementsÑ as measured by the

4013criteria set forth therein.

401744. During the ATC review period, the DOT employees

4026responsible for determining whether the Prince ATC proposal

4034complied with the tra ffic analysis requirement on a Ðmovement - by -

4047movementÑ basis failed to do so prior to allowing Prince to

4058proceed with the ATC.

406245. At the hearing, Prince and Middlesex presented

4070Ðmovement - by - movementÑ traffic evaluations of both proposals.

4080The evidence failed to establish that either the SPUI or the

4091PARCLO proposal was superior in terms of concept design or

4101specific application to this project, or that either proposal

4110should have been rejected on the basis of a traffic analysis.

412146. Middlesex asserts that the Prince proposal should have

4130been rejected because of certain safety concerns observed by

4139members of the TRC during the scoring process. The evidence was

4150insufficient to establish that the remedy for such concerns was

4160rejection of the Prince propo sal, or that the TRC scores should

4172be revised.

417447. Both Middlesex and Prince assert opposing violations of

4183proposal page number limitations. There is no evidence that the

4193content of excess pages provided either party with any

4202sig nificant advantage over another; therefore, the deviation is

4211deemed to be a minor irregularity.

421748. Prince asserts that for various reasons, the Middlesex

4226proposal was not responsive to the RFP.

423349. Although Prince asserts that Middlesex failed to obtain

4242approval of an ATC related to traffic signalization, Middlesex

4251was not required by the RFP to seek ATC approval from DOT for

4264traffic signalization in a SPUI concept proposal.

427150. Prince asserts that the Middlesex proposal failed to

4280meet stormwater management system requi rements included in

4288Addendum #10. Specifically , Prince asserts that the Middlesex

4296proposal failed to reflect a closed storm sewer system for

4306stormwater conveyance, and failed to reflect the installation of

4315any stormwater system in one specific location on its plan.

432551. The RFP does not specifically require that a submitted

4335proposal include a complete stormwater system plan for the entire

4345project area. Final design of the actual stormwater system,

4354including sewer design and pipe sizes, is depe ndent on a s - yet -

4369undetermined variables, including the speed limits of adjacent

4377roadways. Highway speeds impact stormwater system design because

4385curb and gutter installation is excluded where speed limits

4394exceed 45 miles per hour. The evidence is insufficient to

4404es tablish that the Middlesex proposal does not meet the

4414stormwater requirements of the RFP.

441952. Prince asserts that the Middlesex proposal failed to

4428comply, in particular locations, with RFP requirements related to

4437border width and mowing strips.

444253. T he RFP set minimum requirements for border width,

4452which is essentially an open area along the shoulder of the road.

4464The Middlesex proposal failed to comply with the border width

4474requirements. The Prince proposal included a similar deficiency.

448254. The RFP also required a minimum 10 - foot mowing strip

4494between the right - of - way and the edge of the shoulder of the road

4510or retaining wall. The Middlesex proposal failed to comply with

4520the mowing strip requirement. Both the Prince proposal and the

4530RFPÓs SPUI c oncept plan exhibits the same deficiency.

453955. The evidence failed to establish that the border width

4549or mowing strip deficiencies warranted rejection of either

4557proposal as non - responsive.

456256. Prince has asserted that the Middlesex Traffic Control

4571Pla n includes a diagram that displays a Ðcross slope breakÑ

4582condition in the vehicle wheel path that would exist during a

4593temporary traffic control situation. Such a condition could

4601present a safety hazard to drivers. The sole diagram upon which

4612the asserti on relies lacks scale and is insufficient to establish

4623that the Middlesex proposal will result in such a condition at

4634any time during the actual construction process.

464157. Prince has suggested that the Middlesex design fails to

4651comply with the RFP requir ements related to accommodation of a

4662future flyover. The RFP required that the proposed interchange

4671Ðaccommodate to the maximum extent possible the future design and

4681construction by others of a new directional flyover rampÑ

4690connecting northbound I - 75/SR 5 0 to westbound US 98/SR 50/Cortez

4702Boulevard Ðso as to maximize the salvaging of the then - existing

4714facilities, in order to reduce future probable costs.Ñ The

4723Middlesex proposal was principally based on the future flyover

4732included in the RFPÓs SPUI Concept Plan, and , accordingly, the

4742Middlesex proposal complies with the RFP.

4748CONCLUSIONS OF LAW

475158. The Division of Administrative Hearings has

4758jurisdiction over the parties to and subject matter of this

4768proceeding. §§ 120.57(1) and 120.57(3), Fl a . Stat . (201 5). 1/

478159. Although the Ðdesign - buildÑ contract at issue in this

4792proceeding is being a warded under the provisions of s ection

4803337.11 , Florida Statutes, and Florida Administrative Code Rule

481114 - 91.007, the pr ocurement is still governed by s ection

4823120.57(3)( f), which provides in relevant part as follows:

4832In a protest to an invitation to bid or

4841request for proposals procurement, no

4846submissions made after the bid or

4852proposal opening which amend or

4857supplement the bid or proposal shall be

4864considered. In a protes t to an

4871invitation to negotiate procurement, no

4876submissions made after the agency

4881announces its intent to award a contract,

4888reject all replies, or withdraw the

4894solicitation which amend or supplement

4899the reply shall be considered. Unless

4905otherwise provided by statute, the burden

4911of proof shall rest with the party

4918protesting the proposed agency action.

4923In a competitive - procurement protest,

4929other than a rejection of all bids,

4936proposals, or replies, the administrative

4941law judge shall conduct a de novo

4948proceed ing to determine whether the

4954agencyÓs proposed action is contrary to

4960the agencyÓs governing statutes, the

4965agencyÓs rules or policies, or the

4971solicitation specifications. The

4974standard of proof for such proceedings

4980shall be whether the proposed agency

4986actio n was clearly erroneous, contrary to

4993competition, arbitrary, or capricious.

4997In any bid - protest proceeding contesting

5004an intended agency action to reject all

5011bids, proposals, or replies, the standard

5017of review by an administrative law judge

5024shall be whethe r the agencyÓs intended

5031action is illegal, arbitrary, dishonest,

5036or fraudulent. (Emphasis added).

504060. The proposed award of the contract to Prince is

5050contrary to the solicitation specifications. The Prince proposal

5058fails to comply with RFP specificatio ns related to I - 75 exit ramp

5072turn lanes, the location of stop bars at exit lanes onto SR 50,

5085and the full concrete pavement of four thr u - lanes in each

5098direction on SR 50 through the I - 75 junction.

510861. The proposed award of the contract by DOT to Prince is

5120clearly erroneous. A decision is clearly erroneous when it is

5130based on substantial error in proceedings. Black Ó s Law

5140Dictionary , ( Rev. 4th Ed. (1968) ) . An agency's decision or

5152intended decision will be found to be "clearly erroneous" if it

5163is without rational support and, consequently, the Administrative

5171Law Judge has a "definite and firm conviction that a mistake has

5183been committed." See U.S. v. U.S. Gypsum Co. 68 S. Ct. 525

5195(1948). The award of a contract to a proposal that fails to meet

5208the requi rements of the RFP is clearly erroneous.

521762. Prince has suggested that such requirements are

5225inapplicable to the Prince PARCLO design, or that the approval by

5236DOT of Prince Ós request to submit the PARCLO released Prince from

5248complying with the cited req uirements of the RFP. The evidence

5259fails to establish that, in allowing Prince to proceed with an

5270alternative design in lieu of the SPUI, DOT exempted Prince from

5281complying with the requirements of the RFP.

528863. Notwithstanding PrinceÓs assertion that t he referenced

5296requirements are inapplicable to its proposal, Prince offered

5304during the hearing to cure the deficiencies after receiving the

5314contract, if required to do so. Section 120.57(3)(f) prohibits

5323consideration of submissions made after the proposal opening

5331which amend or supplement the proposal. Accordingly, PrinceÓs

5339offer to remedy the deficiencies in its proposal by complying

5349with the requirements of the RFP has been disregarded.

535864. The proposed award of the contract by DOT to Prince is

5370contr ary to competition. As to whether the RFP process is

"5381contrary to competition," the phrase is best understood by its

5391plain and obvious meaning -- i.e. , against or in opposition to

5402competition. "The purpose of the competitive bidding process is

5411to secure fa ir competition on equal terms to all bidders by

5423affording an opportunity for an exact comparison of bids." Harry

5433Pepper and Assoc., Inc. v . City of Cape Coral, 352 So. 2d 1190

5447(Fla. 2 d DCA 1977).

545265. While not every deviation from the specifications of an

5462RFP requires disqualification of a bid, a deviation from the

5472specifications is material , "if it gives the bidder a substantial

5482advantage over the other bidders and thereby restricts or stifles

5492competit ion." Tropabest Foods, Inc. v. Dept. of Gen . Ser v s . , 493

5507So. 2d 50 (Fla. 1st DCA 1986); Robinson Elec. Co., Inc. v. Dade

5520C nty. , 417 So. 2d 1032 (Fla. 3d DCA 1982).

553066. The deficiencies in the Prince proposal were not minor

5540irregularities that could be addressed through the evaluative

5548process because th ey precluded an appropriate comparison of

5557proposals. They were material deviations that, through the

5565omission of materials and construction costs related to the

5574deficiencies, provided Prince with an economic advantage over

5582other firms because the adjusted score calculations incorporated

5590each firmÓs Price Proposal.

559467. Finally, the RFP specifically provided that a

5602conditional proposal may found to be non - responsive, and that

5613non - responsive proposals Ðshall not be considered.Ñ The PARCLO

5623ATC design has n ot been approved by the FHWA, and both DOT and

5637Prince concede that the FHWA may not approve the Prince ATC

5648PARCLO design. While the ATC process is apparently intended to

5658reward a creative response from potential bidders, nothing in the

5668RFP suggests that t he ATC process permits DOT to award a contract

5681to a conditional proposal that fails, on its face, to comply with

5693the requirements of the RFP.

5698RECOMMENDATION

5699Based on the foregoing Findings of Fact and Conclusions of

5709Law, it is RECOMMENDED that the Depart ment of Transpo rtation

5720enter a final o rder awarding the contract issued pursuant to RFP

5732E7K24 to the Middlesex Corporation.

5737DONE AND ENTERED this 7th day of December , 2015 , in

5747Tallahassee, Leon County, Florida.

5751S

5752WILLIA M F. QUATTLEBAUM

5756Administrative Law Judge

5759Division of Administrative Hearings

5763The DeSoto Building

57661230 Apalachee Parkway

5769Tallahassee, Florida 32399 - 3060

5774(850) 488 - 9675

5778Fax Filing (850) 921 - 6847

5784www.doah.state.fl.us

5785Filed with the Clerk of the

5791Division of Administrative Hearings

5795this 7th day of December , 2015 .

5802ENDNOTE

58031/ All statutory references are to Florida Statutes (2015).

5812COPIES FURNISHED:

5814C. Denise Johnson, Esquire

5818Department of Transportation

5821Haydon Burns Building, Mail Station 58

5827605 Suwa nnee Street

5831Tallahassee, Florida 32399 - 0458

5836(eServed)

5837Brian A. Newman, Esquire

5841Pennington, P.A.

5843215 South Monroe Street, Second Floor

5849Post Office Box 10095

5853Tallahassee, Florida 32302 - 2095

5858(eServed)

5859Brandice D. Dickson, Esquire

5863Pennington, Moore, Wilki nson,

5867Bell and Dunbar, P.A.

5871215 South Monroe Street, Second Floor

5877Post Office Box 10095

5881Tallahassee, Florida 32302 - 2095

5886(eServed)

5887Karen D. Walker, Esquire

5891Holland and Knight, LLP

5895Suite 600

5897315 South Calhoun Street

5901Tallahassee, Florida 32301

5904(eServed)

5905Mia L. McKown, Esquire

5909Holland and Knight, LLP

5913Post Office Drawer 810

5917Tallahassee, Florida 32302 - 1809

5922(eServed)

5923Tiffany A. Roddenberry, Esquire

5927Holland & Knight, LLP

5931Suite 600

5933315 South Calhoun Street

5937Tallahassee, Florida 32301

5940(eServed)

5941Andrea Sh ulthiess, Clerk of

5946Agency Proceedings

5948Department of Transportation

5951Haydon Burns Building

5954605 Suwannee Street, M ai l S tation 58

5963Tallahassee, Florida 32399 - 0450

5968(eServed)

5969James C. Boxold, Secretary

5973Department of Transportation

5976Haydon Burns Building

5979605 Su wannee Street, M ai l S tation 57

5989Tallahassee, Florida 32399 - 0450

5994(eServed)

5995Tom Thomas, General Counsel

5999Department of Transportation

6002Haydon Burns Building

6005605 Suwannee Street, M ai l S tation 58

6014Tallahassee, Florida 32399 - 0450

6019(eServed)

6020NOTICE OF RIGHT TO S UBMIT EXCEPTIONS

6027All parties have the right to submit written exceptions within

60371 0 days from the date of this Recommended Order. Any exceptions

6049to this Recommended Order should be filed with the agency that

6060will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 01/19/2016
Proceedings: Agency Final Order filed.
PDF:
Date: 01/05/2016
Proceedings: Agency Final Order
PDF:
Date: 12/07/2015
Proceedings: Recommended Order
PDF:
Date: 12/07/2015
Proceedings: Recommended Order (hearing held September 28 through October 1, 2015). CASE CLOSED.
PDF:
Date: 12/07/2015
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 11/06/2015
Proceedings: Department's Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 11/06/2015
Proceedings: Prince Contracting, LLC's Notice of Filing Proposed Recommended Order filed.
PDF:
Date: 11/06/2015
Proceedings: Middlesex's Proposed Findings of Fact and Conclusions of Law filed.
Date: 10/27/2015
Proceedings: Transcript of Proceedings (not available for viewing) filed.
PDF:
Date: 10/02/2015
Proceedings: Letter to Judge Quattlebaum from Brian Newman enclosing thumb drive filed (proposed exhibits not available for viewing).
Date: 09/28/2015
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 09/21/2015
Proceedings: Middlesex's Notice of Filing Designations of Thomas Creasey, Ph.D. Deposition Taken July 24, 2015 filed.
PDF:
Date: 09/18/2015
Proceedings: Joint Pre-Hearing Stipulation filed.
PDF:
Date: 09/17/2015
Proceedings: Middlesex's Unopposed Motion for Leave to File First Amended Petition filed.
PDF:
Date: 08/03/2015
Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for September 28 through October 2, 2015; 9:30 a.m.; Tallahassee, FL).
PDF:
Date: 08/03/2015
Proceedings: Notice of Taking Telephonic Depositions (Ali Gord and Henri Belrose) filed.
PDF:
Date: 07/30/2015
Proceedings: Order Granting Motion to Intervene.
PDF:
Date: 07/30/2015
Proceedings: Joint Request to Reschedule Final Hearing filed.
PDF:
Date: 07/29/2015
Proceedings: Middlesex's Notice of Taking Deposition of Daniel Lauricello, P.E. filed.
Date: 07/29/2015
Proceedings: CASE STATUS: Status Conference Held.
PDF:
Date: 07/29/2015
Proceedings: Prince Contracting, LLC's Notice of Filing Stipulation Regarding Expert Testimony filed.
PDF:
Date: 07/28/2015
Proceedings: (Intervenor's) Consented Motion for Status Conference filed.
PDF:
Date: 07/27/2015
Proceedings: Prince Contracting, LLC's Second Supplemental Response to The Middlesex Corporation's First Request for Production of Documents filed.
PDF:
Date: 07/24/2015
Proceedings: MIddlesex's Notice of Taking Deposition of David Sadler filed.
PDF:
Date: 07/24/2015
Proceedings: Middlesex's Notice of Taking Deposition of Walfry Pevida filed.
PDF:
Date: 07/24/2015
Proceedings: Middlesex's Notice of Taking Deposition of Scott Arnold filed.
PDF:
Date: 07/24/2015
Proceedings: Prince Contracting, LLC's Notice of Service of Answers and Objections to Middlesex Corporation's Third Set of Interrogatories filed.
PDF:
Date: 07/24/2015
Proceedings: Prince's Responses and Objections to Middlesex's Fourth Request for Production of Documents filed.
PDF:
Date: 07/23/2015
Proceedings: Respondent's Response to Petitioner's Fourth Request for Production filed.
PDF:
Date: 07/23/2015
Proceedings: Respondent's Response to Petitioner's Third Request for Production filed.
PDF:
Date: 07/23/2015
Proceedings: Respondent, Department of Transportation's, Response to Middlesex's First Request for Admission to the Department filed.
PDF:
Date: 07/20/2015
Proceedings: The Middlesex Corporation's Supplemental Response to Prince Contracting, LLC's Second Request for Production of Documents to the Middlesex Corporation filed.
PDF:
Date: 07/17/2015
Proceedings: Middlesex's Notice of Taking Deposition of D. Scot Leftwich filed.
PDF:
Date: 07/17/2015
Proceedings: Middlesex's Notice of Taking Deposition of Tom Creasey filed.
PDF:
Date: 07/17/2015
Proceedings: Notice of Taking Deposition Duces Tecum (of Ali Gord) filed.
PDF:
Date: 07/16/2015
Proceedings: Prince Contracting, LLC's Responses and Objections to Middlesex Corporation's Third Request for Production of Documents to Prince Contracting, LLC., filed.
PDF:
Date: 07/16/2015
Proceedings: Middlesex's Fourth Request for Production to the Department filed.
PDF:
Date: 07/16/2015
Proceedings: Middlesex's First Requests for Admission to the Department filed.
PDF:
Date: 07/16/2015
Proceedings: Middlesex's Fourth Request for Production to Prince filed.
PDF:
Date: 07/16/2015
Proceedings: Middlesex's Notice of Service of Third Set of Interrogatories to Prince filed.
PDF:
Date: 07/16/2015
Proceedings: Middlesex's Notice of Taking Deposition of Paul Staes filed.
PDF:
Date: 07/16/2015
Proceedings: Middlesex's Third Request for Production to the Department filed.
PDF:
Date: 07/15/2015
Proceedings: Prince Contracting, LLC's Responses and Objections to the Middlesex Corporation's Second Request for Production of Documents to Prince Contracting, LLC filed.
PDF:
Date: 07/15/2015
Proceedings: Notice of Taking Depositions (James Wills, Henri Belrose, and Al Aponas) filed.
PDF:
Date: 07/15/2015
Proceedings: Notice of Taking Deposition (Corporate Representative of Middlesex) filed.
PDF:
Date: 07/14/2015
Proceedings: Middlesex's Amended Notice of Taking Depositions of Jack Calandros and Walfry Pevida filed.
PDF:
Date: 07/14/2015
Proceedings: Middlesex's Notice of Taking Depositions (of Jack Calandros and Walfry Pevida) filed.
PDF:
Date: 07/14/2015
Proceedings: Middlesex's Notice of Taking Deposition of Prince Contracting, LLC's Agency Representative filed.
PDF:
Date: 07/14/2015
Proceedings: Middlesex's Corrected Notice of Taking Deposition of Waddah Farah, P.E. filed.
PDF:
Date: 07/13/2015
Proceedings: Notice of Taking Deposition of Wadah Farah, P.E filed.
PDF:
Date: 07/13/2015
Proceedings: Notice of Taking Depositions (of Sandra Gonzalez and Amy Neidringhaus) filed.
PDF:
Date: 07/13/2015
Proceedings: Middlesex's Notice of Taking Deposition of Department of Transportation's Agency Representative filed.
PDF:
Date: 07/10/2015
Proceedings: Department's List of Potential Witnesses filed.
PDF:
Date: 07/10/2015
Proceedings: Prince Contracting, LLC's Witness List filed.
PDF:
Date: 07/10/2015
Proceedings: Middlesex's Witness List filed.
PDF:
Date: 07/09/2015
Proceedings: Prince Contracting, LLC's Supplemental Response to the Middlesex Corporation's First Request for Production of Documents to Prince Contracting, LLC filed.
PDF:
Date: 07/09/2015
Proceedings: Middlesex's Third Request for Production to Prince filed.
PDF:
Date: 07/08/2015
Proceedings: The Middlesex Corporation's Objection to Intervenor Prince's Notice of Production from Non-party filed.
PDF:
Date: 07/08/2015
Proceedings: Notice of Taking Depositions (of Richard Moss, Terence Jennings, Tom Lay and Rochelle Garrett) filed.
PDF:
Date: 07/08/2015
Proceedings: Middlesex's Second Request for Production to Prince filed.
PDF:
Date: 07/07/2015
Proceedings: Prince Contracting, LLC's Notice of Service of Answers and Objections to MIddllesex Corporation's Second Set of Interrogatories filed.
PDF:
Date: 07/06/2015
Proceedings: Departments Response to Middlesexs Second Request for Production filed.
PDF:
Date: 07/06/2015
Proceedings: Departments Notice of Service of Answers to Middlesexs Second Set of Interrogatories filed.
PDF:
Date: 07/06/2015
Proceedings: Middlesex's Response to Prince's Second Request for Production filed.
PDF:
Date: 07/06/2015
Proceedings: Middlesex's Response to Prince's Second Requests for Admission filed.
PDF:
Date: 07/06/2015
Proceedings: Middlesex's Notice of Service of Answers to Prince's Second Set of Interrogatories filed.
PDF:
Date: 07/06/2015
Proceedings: Prince Contracting, LLC's Notice of Service of Supplemental Production to The Middlesex Corporation's First Request for Production of Documents filed.
PDF:
Date: 07/06/2015
Proceedings: Intervenor, Prince Contracting, LLC's Objections to Petitioner's Notice of Production from Non-party Dated June 26, 2015 filed.
PDF:
Date: 06/30/2015
Proceedings: Middlesex's Second Request for Production to the Department filed.
PDF:
Date: 06/30/2015
Proceedings: Middlesex's Notice of Service of Second Set of Interrogatories to the Department filed.
PDF:
Date: 06/30/2015
Proceedings: Middlesex's Notice of Service of Second Set of Interrogatories to Prince filed.
PDF:
Date: 06/26/2015
Proceedings: Intervenor Prince Contracting, LLC's Second Request for Production of Documents to Petitioner filed.
PDF:
Date: 06/26/2015
Proceedings: Intervenor Prince Contracting, LLC's Second Request for Admissions to Petitioner filed.
PDF:
Date: 06/26/2015
Proceedings: Intervenor, Prince Contracting, LLC's Notice of Service of its Second Set of Interrogatories to Petitioner filed.
PDF:
Date: 06/26/2015
Proceedings: Notice of Production from Non-party filed.
PDF:
Date: 06/26/2015
Proceedings: (Petitioner's) Notice of Filing Privilege Log filed.
PDF:
Date: 06/26/2015
Proceedings: Notice of Production of Non-party filed.
PDF:
Date: 06/24/2015
Proceedings: Notice of Serving Department's Answers to Petitioners First Set of Interrogatories filed.
PDF:
Date: 06/24/2015
Proceedings: Middlesex's Notice of Service of Answers to the Department's First Interrogatories filed.
PDF:
Date: 06/23/2015
Proceedings: Respondent's Response to Petitioner's First Request for Production filed.
PDF:
Date: 06/23/2015
Proceedings: Middlesex's Response to Prince's First Requests for Admission filed.
PDF:
Date: 06/23/2015
Proceedings: Middlesex's Response to Prince's First Request for Production filed.
PDF:
Date: 06/22/2015
Proceedings: Middlesex's Notice of Service of Answers to Prince's First Interrogatories filed.
PDF:
Date: 06/22/2015
Proceedings: Prince Contracting, LLC's Responses and Objections to The Middlesex Corporation's First Request for Production of Documents to Prince Contracting, LLC filed.
PDF:
Date: 06/22/2015
Proceedings: Prince Contracting, LLC's Notice of Service of Answers and Objections to The Middlesex Corporation's First Set of Interrogatories filed.
PDF:
Date: 06/16/2015
Proceedings: Notice of Serving Department's First Set of Interrogatories to Petitioner filed.
PDF:
Date: 06/12/2015
Proceedings: Intervenor Prince Contracting, LLC's First Request for Admissions to Petitioner filed.
PDF:
Date: 06/12/2015
Proceedings: Intervenor Prince Contracting, LLC's First Request for Prouction of Documents to Petitioner filed.
PDF:
Date: 06/12/2015
Proceedings: Intervenor, Prince Contracting, LLC's Notice of Service of Its First Set of Interrogatories to Petitioner filed.
PDF:
Date: 06/12/2015
Proceedings: Middlesex's Notice of Service of First Set of Interrogatories to the Department filed.
PDF:
Date: 06/12/2015
Proceedings: Middlesex's Notice of Service of First Set of Interrogatories to Prince filed.
PDF:
Date: 06/12/2015
Proceedings: Middlesex's First Request for Production to Prince filed.
PDF:
Date: 06/12/2015
Proceedings: Middlesex's First Request for Production to the Department filed.
PDF:
Date: 06/12/2015
Proceedings: Order on Joint Motion for Modification of Pre-Hearing Instructions.
PDF:
Date: 06/11/2015
Proceedings: Joint Motion for Modification of Order of Pre-hearing Instructions filed.
PDF:
Date: 06/10/2015
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 06/10/2015
Proceedings: Notice of Hearing (hearing set for August 5 through 7, 2015; 9:30 a.m.; Tallahassee, FL).
PDF:
Date: 06/02/2015
Proceedings: Notice of Appearance (Tiffany Roddenberry) filed.
PDF:
Date: 06/02/2015
Proceedings: Notice of Appearance (Mia McKown) filed.
PDF:
Date: 06/02/2015
Proceedings: Notice of Appearance (Karen Walker) filed.
PDF:
Date: 06/01/2015
Proceedings: Notice of Appearance (Brandice Dickson) filed.
PDF:
Date: 05/28/2015
Proceedings: Notice of Intervention (Prince Contracting, LLC) filed.
PDF:
Date: 05/28/2015
Proceedings: Notice of Intent to Protest filed.
PDF:
Date: 05/28/2015
Proceedings: Formal Written Protest and Request for Hearing Involving Disputed Issues of Fact filed.
PDF:
Date: 05/28/2015
Proceedings: Agency referral filed.

Case Information

Judge:
WILLIAM F. QUATTLEBAUM
Date Filed:
05/28/2015
Date Assignment:
05/29/2015
Last Docket Entry:
01/19/2016
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Counsels

Related DOAH Cases(s) (2):

Related Florida Statute(s) (4):