15-003082BID
The Middlesex Corporation vs.
Department Of Transportation
Status: Closed
Recommended Order on Monday, December 7, 2015.
Recommended Order on Monday, December 7, 2015.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8THE MIDDLESEX CORPORATION,
11Petitioner,
12vs. Case No. 15 - 3082BID
18DEPARTMENT OF TRANSPORTATION,
21Respondent,
22and
23PRI N CE CONTRACTING, L.L.C.,
28Intervenor.
29_______________________________/
30RECOMMENDED ORDER
32On September 28 through October 1, 2015, an administrative
41hearing in this case was conducted in Tallahassee, Florida,
50before William F. Quattlebaum, Administrative Law Judge, Division
58of Administrative Hearings.
61APPEARANCE S
63For Petitioner: Brian A. Newman, Esquire
69Brandice D. Dickson, Esquire
73Pennington, P.A.
75215 South Monroe Street, Second Floor
81Post Office Box 10095
85Tallahassee, Florida 32302 - 2095
90For Respondent: C. Denise Johnson, Esquire
96Department of Transportation
99Haydon Burns Building, Mail Station 58
105605 Suwannee Street
108Tallahassee, Florida 32399 - 0458
113For Inte rvenor: Karen D. Walker, Esquire
120Tiffany A. Roddenberry, Esquire
124Holland and Knight, LLP
128Suite 600
130315 South Calhoun Street
134Tallahassee, Florida 32301
137STATEMENT OF THE ISSUE
141The issue in this case is whether the Department of
151Transportation's (DOT) proposed award of a Ðdesign - buildÑ
160cont ract to Prince Contracting, LLC (Prince) , is contrary to the
171agency's governing statutes, rules or policies, or the
179specifications of th e Request for Proposals (RFP).
187PRELIMINARY STATEMENT
189DOT is seeking to award a contract pursuant to an RFP issued
201in September 2014 for the design and construction of highway
211improvements referenced herein.
214On April 14, 2015, DOT issued notice of its i ntent to award
227the contract to Prince. The Middlesex Corporation (Middlesex)
235filed a protest challenging the proposed award and requesting a
245hearing.
246On May 28, 2015, DOT forwarded the challenge to the Division
257of Administrative Hearings (DOAH). DOT al so forwarded a Notice
267of Intervention filed with DOT by Prince, which was granted.
277Based upon the information set forth in the referral, DOAH
287sch eduled the hearing for August 5 through 7, 2015. The hearing
299was subsequently rescheduled for September 28 th rough October 2,
3092015.
310On Septembe r 17, 2015, Middlesex filed an U nopposed Motion
321for Leave to File First Amended Petition, which was granted at
332the commencement of the hearing.
337On September 18, 2015, the parties filed a Joint Pre - hearing
349Stipulation that included a statement of admitted facts which
358have been adopted and incorporated herein as necessary.
366At the hearing, Middlesex presented the testimony of four
375witnesses and had Exhibits 1 through 7, 9 through 11, 13 through
38716, 18, 19, 22, 24, 27 t hrough 39, and 41 admitted into evidence.
401DOT presented the testimony of one witness. Prince presented the
411testimony of three witnesses and had Exhibits 1, 2, 4 through 6,
4238 through 11, 15, 19 through 21, 23 through 30, 32, and 46
436through 48 admitted int o evidence. Joint E xhibits 1 through 30
448were admitted by stipulation of the parties.
455A Transcript of the hearing was filed on Octobe r 27, 2015.
467All parties filed proposed recommended o rders that have been
477reviewed in the preparation of this Recommended Order.
485FINDING S OF FACT
4891. DOT is seeking to award a Ðdesign - buildÑ contract
500pursuant to RFP E7K24 for design and construction of additional
510lanes on I - 75/SR 93 (I - 75) in Hernando County from south of
525US 98/Cortez Boulevard to north of US 98/SR 50/Cor tez Boulevard,
536and from north of US 98/SR 50/Cortez Boulevard to the
546Hernando/Sumter County l ine. The project also includes
554reconstruction and rehabilitation of existing I - 75 lanes,
563replacement of the I - 75 bridges over US 98/SR 50, various
575improvements to the interchange and its ramps, added lanes and
585resurfacing of a portion of US 98/SR 50 in Hernando County, and
597other work as described in the RFP.
6042. Middlesex and Prince are qualified design - build firms
614capable of performing the project tasks required b y the RFP.
625DOT employed a two - phase process in seeking to award the
637contract.
6383. Phase One began with the solicitation of Expanded
647Letters of Interest (ELOIs) from design - build firms. The ELOIs
658were evaluated and scored by DOT to develop a Ðshortlist Ñ of four
671qualified firms.
6734. Phase Two commenced with the release of the formal RFP
684to the four firms on the shortlist. In response to the RFP, the
697shortlisted firms were to submit ÐTechnical ProposalsÑ and ÐPrice
706ProposalsÑ to DOT. The Technical Pro posals were to be scored by
718DOT, after which DOT was to calculate an Ðadjusted scoreÑ based
729on a formula that referenced the ELOI and Technical Proposal
739scores and the Price Proposals.
7445. On July 7, 2014, DOT posted an advertisement of the ELOI
756solicita tion. The deadline for submission of ELOIs was August 1,
7672014. DOT received timely ELOI submissions from seven firms.
776DOT scored the submissions and developed the shortlist of the
786four firms. Prince and Middlesex were included on the shortlist
796and were invited to submit responses to the RFP.
8056. According to the RFP, the DOT ÐConcept PlanÑ for the
816project was for the construction of a ÐSingle Point Diamond
826InterchangeÑ (also known as a Single Point Urban InterchangeÑ and
836referred to herein as a ÐSPUIÑ ) at the intersection of I - 75 and
851US 98/SR 50.
8547. The SPUI concept plan was developed by an engineering
864firm retained by DOT that issued an ÐInterchange Operational
873Analysis Report Ñ (IOAR) for the project. The IOAR was part of a
886ÐProject Development an d EnvironmentalÑ (PD&E) study, apparently
894required to obtain federal approval and funding of the project.
9048. The RFP included an ÐAlternative Technical ConceptÑ
912(ATC) process which allowed a firm to submit an alternative
922concept to DOT for review and ap proval (or disapproval) prior to
934the deadline for submission of responses to the RFP. Upon
944receiving DOT approval of the alternative concept, the firm could
954prepare a Technical Proposal based on the ATC. The RFP provided
965that DOT would not disclose a pro posed ATC to other bidders prior
978to the submission of Technical Proposals. The RFP also required
988DOT to issue an addendum to the RFP if an approved ATC had the
1002effect of altering the RFP specifications.
10089. The RFP specifically addressed the process gov erning
1017approval of an ATC, in relevant part, as follows:
1026B. Innovative Aspects:
1029All innovative aspects shall be
1034identified separately as such in the
1040technical proposal.
1042An innovative aspect does not include
1048revisions to specifications, standards o r
1054established Department policies.
1057Innovation should be limited to Design -
1064Build FirmÓs means and methods, roadway
1070alignments, approach to project, etc.
10751. Alternative Technical Concept (ATC)
1080Proposals
1081The ATC process allows innovation,
1086flexibility, time and cost savings on the
1093design and construction of Design - Build
1100Projects while providing the best value
1106for the public. Any deviation from the
1113RFP for which th e Design - Build Firms
1122seeks [sic] to obtain approval to utilize
1129prior to Technical Proposal submission
1134is, by definition, an ATC and therefore
1141must be submitted to the Department for
1148consideration through the ATC process.
1153Any proposed material or technology not
1159addressed by the RFP is considered an ATC
1167and therefore must be submitted to the
1174Dep artment for consideration through the
1180ATC process. The proposed ATC shall
1186provide an approach that is equal to or
1194better than the requirements of the RFP,
1201as determined by the Department. ATC
1207Proposals which reduce the scope,
1212quality, performance, or rel iability
1217should not be proposed. A proposed
1223concept does not meet the definition of
1230an ATC if the concept is contemplated by
1238the RFP.
1240The Department will keep all ATC
1246submissions confidential prior to the
1251Final Selection of the Proposer to the
1258fullest extent allowed by law, with few
1265exceptions. Although the Department will
1270issue an addendum for all ATC proposals
1277contained in the list below, the
1283Department will endeavor to maintain
1288confidentiality of the Design - Build Firms
1295specific ATC proposal. Prior to
1300approving ATCÓs which would result in the
1307issuance of an Addendum as a result of
1315the item being listed below, the Design -
1323Build Firm will be given the option to
1331withdraw previously submitted ATC
1335proposals . . . .
1340* * *
13432. One - on - One ATC Proposal Dis cussion
1353Meetings
1354One - on - One ATC discussion meetings may be
1364held in order for the Design - Build Firm
1373to describe proposed changes to supplied
1379basic configurations, Project scope,
1383design criteria, and/or construction
1387criteria. Each Design - Build Firm with
1394proposed changes may request a One - on - One
1404ATC discussion meeting to describe the
1410proposed changes. The Design - Build Firm
1417shall provide, by the deadline shown in
1424the Schedule of Events of this RFP, a
1432preliminary list of ATC proposals to be
1439reviewed and dis cussed during the One - on -
1449One ATC discussion meetings. This list
1455may not be inclusive of all ATCÓs to be
1464discussed but it should be sufficiently
1470comprehensive to allow the Department to
1476identify appropriate personnel to
1480participate in the One - on - One ATC
1489di scussion meetings. The purpose of the
1496One - on - One ATC discussion meeting is to
1506discuss the ATC proposals, answer
1511questions that the Department may have
1517related to the ATC proposal, review other
1524relevant information and when possible
1529establish whether the p roposal meets the
1536definition of an ATC thereby requiring
1542the submittal of a formal ATC submittal.
1549The meeting should be between
1554representatives of the Design - Build Firm
1561and/or the Design - Build Engineer of
1568Record and District/Central Office staff
1573as needed to provide feedback on the ATC
1581proposal. Immediately prior to the
1586conclusion of the One - on - One ATC
1595discussion meeting, the Department will
1600advise the Design - Build Firm as to the
1609following related to the ATC proposals
1615which were discussed:
1618¤ The Propo sal meets the criteria
1625established herein as a qualifying ATC
1631Proposal; therefore an ATC Proposal
1636submission IS required, or
1640¤ The Proposal does not meet the
1647criteria established herein as a
1652qualifying ATC proposal since the
1657Proposal is already allowed or
1662contemplated by the original RFP;
1667therefore an ATC Proposal submission is
1673NOT required.
16753. Submittal of ATC Proposals.
1680All ATC submittals must be in writing and
1688may be submitted at any time following
1695the Shortlist Posting but shall be
1701submitted prior to the deadline shown in
1708the Schedule of Events of this RFP.
1715* * *
17184. Review and Approval of ATC Submittals
1725* * *
1728Approved Design Exceptions or Design
1733Variations required as part of an
1739approved ATC submittal will result in the
1746issuance of an addendum to the RFP
1753notifying all Shortlisted Design - Build
1759Firms of the approved Design Exceptions
1765or Design Variation(s). Such a change
1771will be approved by the FHWA, as
1778applicable. Prior to approving ATCÓs
1783which would result in the issuance of an
1791Adden dum as a result of the Design
1799Exceptions and/or Design Variation, the
1804Design - Build Firm will be given the
1812option to withdraw previously submitted
1817ATC proposals. (Emphasis added ) .
1823The FHWA is the Federal Highway Administration.
183010. RFP also establish ed requirements that were not to be
1841changed other than by amendment or addenda issued by DOT. In
1852relevant part, the RFP provided as follows:
1859Any changes to requirements of the RFP by
1867a Design - Build Firm must be approved by
1876the Department through the Alter native
1882Technical Concept (ATC) Proposal process,
1887as described herein, prior to the
1893information cut - off date. For this
1900Project, the Department considers the
1905following to be requirements of the
1911Project that shall not be changed by the
1919Design - Build Firms exc ept as specifically
1927modified by the RFP and associated
1933addenda :
1935* * *
1938Provide a clear ten foot mowing strip
1945adjacent to the right of way.
1951* * *
1954A Diverging Diamond Interchange will not
1960be accepted.
1962A Compressed/Tight Urban Design
1966Interchange wil l not be accepted.
1972The northbound exit ramp from I - 75 to
1981SR 50 shall not be shortened to exclude
1989the portion for the future flyover.
1995SR 50 shall consist of Concrete Pavement.
2002* * *
2005The SR 50 median shall be designed to and
2014accommodate the future fl yover.
2019* * *
2022SR 50 shall be designed with seven (7)
2030foot Buffered Bicycle Lanes, including
2035but not limited to, minimum twelve (12)
2042foot wide thru and turn lanes. The
2049median width shall not be reduced to
2056accommodate the seven (7) foot Buffered
2062Bicycle Lanes . . . . The concrete
2070pavement shall be placed full width
2076incorporating the four 12 - foot thru
2083lanes, twelve (12) foot turn lanes, seven
2090foot Buffered Bicycle Lanes and offsets
2096to any islands from the furthest point of
2104the begin and end of the curb re turns of
2114the ramps east and west of SR 50 . . . .
2126(Emphasis added ) .
213011. Despite the RFPÓs clear declaration that ÐTight Urban
2139Interchange DesignsÑ (TUDI) would not be accepted, both Middlesex
2148and Prince proposed ATCs for construction of TUDIs during the ATC
2159review period. DOT rejected the TUDI proposals.
216612. Prince also submitted an ATC proposing construction of
2175a ÐPartial CloverleafÑ (PARCLO) interchange design. DOT approved
2183PrinceÓs request to proceed with the PARCLO ATC.
219113. DOT issued nine addenda to the RFP prior to the
2202deadline for submission of Technical Proposals.
220814. The deadline for submission of T echnical Proposals was
2218December 19, 2014. Prince proposed construction of the PARCLO
2227concept in its Technical Proposal. The Technical Proposal
2235submitted by Middlesex proposed to construct a SPUI concept
2244referenced in the RFP.
224815. On January 29, 2015, DOT conducted a question and
2258answer session with each firm that submitted a Technical
2267Proposal. DOT issued three more addenda (#10, #11 , and #12) to
2278the RFP after the Technic al Proposal submission deadline and
2288allowed each firm to submit an Addendum to its Technical Proposal
2299by March 10, 2015.
230316. On March 19, 2015, DOT conducted a second question and
2314answer session with each firm that submitted a Technical Proposal
2324and an Addendum to its Technical Proposal.
233117. DOTÓs Technical Review Committee (TRC) evaluated and
2339scored all of the submitted Technical Proposals.
234618. The RFP prohibits DOT from scoring a non - responsive
2357proposal. Th e RFP specifically provided as follows:
2365Non - Responsive Proposals
2369Proposals found to be non - responsive
2376shall not be considered. Proposals may
2382be rejected if found to be in
2389nonconformance with the requirements and
2394instructions herein contained. A
2398prop osal may be found to be non -
2407responsive by reasons, including, but not
2413limited to, failure to utilize or
2419complete prescribed forms, conditional
2423proposals , incomplete proposals,
2426indefinite or ambiguous proposals,
2430failure to meet deadlines and improper
2436and/or undat ed signatures. (Emphasis
2441added ) .
244419. The Prince PARCLO design has not been approved by the
2455FHWA. Both Prince and DOT concede that construction of the
2465PARCLO design is conditional on approval by the FHWA.
247420. Although the RFP allowed for the waiver of minor
2484irregularities in a proposal, the RPF precluded DOT from waiving
2494irregularities that affect the price of a proposal to the
2504disadvantage of other bidders. The RPF provided as follows:
2513Waiver of Irregularities
2516The Department may waive mino r
2522informalities or irregularities in
2526proposals received when such is merely a
2533matter of form and not substance, and the
2541correction or waiver of which is not
2548prejudicial to other Proposers. Minor
2553irregularities are defined as those that
2559will not have an ad verse effect on the
2568DepartmentÓs interest and will not affect
2574the price of the Proposals by giving a
2582Proposer an advantage or benefit not
2588enjoyed by other Proposers.
25921. Any design submittals that are part
2599of a proposal shall be deemed preliminary
2606only.
26072. Preliminary design submittals may
2612vary from the requirements of the Design
2619and Construction Criteria. The
2623Department, at their discretion, may
2628elect to consider those variations in
2634awarding points to the proposal rather
2640than rejecting the entire p roposal.
26463. In no event will any such elections
2654by the Department be deemed to be a
2662waiving of the Design and Construction
2668Criteria.
26694. The Proposer who is selected for the
2677Project will be required to fully comply
2684with the Design and Construction C riteria
2691for the price bid, regardless that the
2698proposal may have been based on a
2705variation from the Design and
2710Construction Criteria.
27125. Proposers shall identify separately
2717all innovative aspects as such in the
2724Technical Proposal. An innovative aspect
2729does not include revisions to
2734specifications or established Department
2738policies. Innovati ons should be limited
2744to Design Î Build FirmÓs means and methods,
2752roadway alignments, approach to Project,
2757use of new products, new uses for
2764established products, etc.
27676. The Proposer shall obtain any
2773necessary permits or permit modifications
2778not already provided.
27817. Those changes to the Design Concept
2788may be considered together with
2793innovative construction techniques, as
2797well as other areas, as the basis for
2805gradi ng the Technical Proposals in the
2812area of innovative measures.
281621. The TRCÓs technical scores were publicly announced on
2825April 9, 2015, which was also the deadline for submission of
2836sealed Price Proposals. After the technical scores were
2844announced, t he sealed Price Proposals were opened.
285222. Prince submitted the lowest Price Proposal with a bid
2862of $84,937,900. Middlesex submitted the second lowest Price
2872Proposal of $94,664,000.
287723. As provided in the RFP, the contract was to be awarded
2889to the f irm w ith the lowest adjusted score. The adjusted scores
2902were calculated pursuant to the formula set forth in the RFP, and
2914the proposals were ranked.
291824. Prince had the lowest adjusted score of 1,069,746.851.
2929Middlesex had the next lowest adjusted scor e of 1,083,112.128.
294125. DOT posted the Notice of Intent to award the contract
2952to Prince on April 14, 2015.
295826. Middlesex timely complied with all requirements to
2966protest the contract award in this proceeding.
297327. Middlesex correctly asserts that t he Prince PARCLO
2982proposal is non - responsive to various requirements of the RFP.
299328. Middlesex asserts that the Prince PARCLO proposal fails
3002to comply with the RFP requirements regarding northbound exit
3011lanes from I - 75 onto SR 50. The evidence supports the assertion.
3024Addendum #10 to the RFP required as
3031follows:
3032The north and southbound I - 75 exit ramps
3041to west and eastbound SR 50 shall consist
3049of triple lefts and shall provide for
3056two (2) WB62FL semi - trucks in the outside
3065two (2) lanes, turning left parallel to
3072each other at the same time through the
3080entire turn at a minimum, with at least
3088four (4) foot separation between those
3094vehicles and at least 10 feet of
3101separation between the outermost vehicles
3106in the opposing left turn movements.
3112(Emph asis a dded ) .
311829. The Prince proposal does not comply with this
3127requirement. During a pre - submittal meeting, Prince initially
3136proposed a variation from the Ðtriple leftÑ requirement for the
3146northbound exit ramp that included dual left and dual right turn
3157lane s with a shared left - right fifth lane. After DOT expressed
3170concern with the shared lane proposal, Prince revised the plan to
3181include only dual right and dual left turn lanes.
319030. Prince asserts that DOT approved its deviation from the
3200triple left turn lane requirement, essentially by silent
3208acquiescence during the meeting. Although Prince and DOT
3216discussed the issue, there is no evidence that DOT affirmatively
3226approved PrinceÓs deviation from the RFP triple - left requirement.
323631. At the hearing, Prin ce stated that it will comply with
3248the triple - left requirement at the proposed price, if DOT and/or
3260the FHWA insist.
326332. Middlesex asserts that the Prince proposal fails to
3272comply with RFP requirements regarding placement of Ðstop barsÑ
3281on exit lanes fr om I - 75 onto SR 50. The evidence supports the
3296assertion.
3297Addendum #10 to the RFP required as
3304follows:
3305It is acceptable to utilize parallel
3311cross walks across the ramps terminals
3317along SR 50, although adjustments should
3323be made to accommodate drainage
3328structures. However, for all interchange
3333types, the lead vehicles (at a minimum)
3340at the stop bar, shall be in front of the
3350bridge retaining wall and have no sight
3357obstructions at SR 50. (Emphasis added ) .
336533. The Prince proposal does not comply with t his
3375requirement. The requirement that the stop bar be placed in
3385front of a bridge retaining wall is for purposes of safety. The
3397Prince proposal results in a stop bar being located behind the
3408bridge retaining wall, creating a sight obstruction at SR 50.
3418Such a sight obstruction poses a safety hazard to drivers,
3428especially to drivers who fail to comply with traffic signals.
3438The failure to comply with this requirement also creates a
3448potential safety problem for pedestrians, because a driver must
3457pro ceed in to the pedestrian cross walk in order to clear the sight
3471obstruction.
347234. Prince suggested that the stop bar placement in its
3482proposal is preliminary and subject to change. However,
3490compliance with this requirement would require lengthening the
3498I - 75 br idges to provide additional space between bridge retaining
3510walls. Increasing the length of the bridges increases the
3519expense of constructing the project. Allowing a firm to deviate
3529from this requirement provides a substantial financial advantage
3537over oth er firms that complied with the requirement.
354635. At the hearing, Prince stated that it would comply with
3557the stop bar placement requirement at the proposed price, if
3567required to do so.
357136. Middlesex asserts that the Prince proposal fails to
3580comply with the RFP requirements regarding Ðth ru - lanesÑ on SR 50.
3593The evidence supports the assertion.
359837. In regards to SR 50 thr u - lanes, Addendum 7 of the RFP
3613provided as follows:
3616The concrete pavement shall be placed
3622full width incorporating the four 12 - foot
3630thru lanes, twelve (12) foot turn lanes,
3637seven (7) foot Buffered Bicycle Lanes and
3644offsets to any islands from the furthest
3651point of the begin and end of the curb
3660returns of the ramps east and west of
3668SR 50. (Emphasis added ) .
367438. Although only three t hr u - lanes on each side are
3687intended to be used for traffic when this project is completed,
3698the RFP clearly required installation of concrete pavement for
3707the full width of four thr u - lanes traveling on SR 50 in both east
3723and west directions through the inte rchange. The unused lanes
3733are intended to accommodate future expansion of SR 50.
374239. The Prince proposal fails to include four concrete
3751thr u - lanes in each direction on SR 50. The Prince proposal
3764includes only three westbound thr u - lanes on SR 50. The Middlesex
3777proposal includes concrete pavement of all lanes required by the
3787RFP.
378840. Prince asserts that DOTÓs acceptance of the Prince ATC
3798concept included approval of its deviation from the thr u - la ne
3811requirement. There is no evidence that DOT affirmat ively
3820approved the deviation.
382341. The RFP requires that DOT issue an addendum to notify
3834firms of ATC - proposed deviations from the RFP that result in
3846modification or abandonment of RFP requirements. DOT did not
3855issue an addendum that modified or abandon ed the referenced thr u -
3868lane requirement.
387042. The number of thr u - lanes impacts the cost of the
3883project th r ough both materials and construction expenses.
3892Allowing a firm to deviate from the thr u - lane requirement
3904provides a substantial financial advantage over firms that compl y
3914with the requirement.
391743. Middlesex asserts that the Prince ATC proposal fails to
3927comply with the traffic analysis requirements set forth in the
3937RFP. According to the RFP, any proposed modification from the
3947SPUI Concept Plan mus t be supported by a traffic analysis
3958demonstrating a ÐLevel - of - Service and reduction in delay
3969throughout the year that is better than or equal to the Concept
3981Plan configuration.Ñ The RFP further required that the traffic
3990analysis demonstrate that the conc ept is equal to or better than
4002the SPUI Concept Plan for Ðall movementsÑ as measured by the
4013criteria set forth therein.
401744. During the ATC review period, the DOT employees
4026responsible for determining whether the Prince ATC proposal
4034complied with the tra ffic analysis requirement on a Ðmovement - by -
4047movementÑ basis failed to do so prior to allowing Prince to
4058proceed with the ATC.
406245. At the hearing, Prince and Middlesex presented
4070Ðmovement - by - movementÑ traffic evaluations of both proposals.
4080The evidence failed to establish that either the SPUI or the
4091PARCLO proposal was superior in terms of concept design or
4101specific application to this project, or that either proposal
4110should have been rejected on the basis of a traffic analysis.
412146. Middlesex asserts that the Prince proposal should have
4130been rejected because of certain safety concerns observed by
4139members of the TRC during the scoring process. The evidence was
4150insufficient to establish that the remedy for such concerns was
4160rejection of the Prince propo sal, or that the TRC scores should
4172be revised.
417447. Both Middlesex and Prince assert opposing violations of
4183proposal page number limitations. There is no evidence that the
4193content of excess pages provided either party with any
4202sig nificant advantage over another; therefore, the deviation is
4211deemed to be a minor irregularity.
421748. Prince asserts that for various reasons, the Middlesex
4226proposal was not responsive to the RFP.
423349. Although Prince asserts that Middlesex failed to obtain
4242approval of an ATC related to traffic signalization, Middlesex
4251was not required by the RFP to seek ATC approval from DOT for
4264traffic signalization in a SPUI concept proposal.
427150. Prince asserts that the Middlesex proposal failed to
4280meet stormwater management system requi rements included in
4288Addendum #10. Specifically , Prince asserts that the Middlesex
4296proposal failed to reflect a closed storm sewer system for
4306stormwater conveyance, and failed to reflect the installation of
4315any stormwater system in one specific location on its plan.
432551. The RFP does not specifically require that a submitted
4335proposal include a complete stormwater system plan for the entire
4345project area. Final design of the actual stormwater system,
4354including sewer design and pipe sizes, is depe ndent on a s - yet -
4369undetermined variables, including the speed limits of adjacent
4377roadways. Highway speeds impact stormwater system design because
4385curb and gutter installation is excluded where speed limits
4394exceed 45 miles per hour. The evidence is insufficient to
4404es tablish that the Middlesex proposal does not meet the
4414stormwater requirements of the RFP.
441952. Prince asserts that the Middlesex proposal failed to
4428comply, in particular locations, with RFP requirements related to
4437border width and mowing strips.
444253. T he RFP set minimum requirements for border width,
4452which is essentially an open area along the shoulder of the road.
4464The Middlesex proposal failed to comply with the border width
4474requirements. The Prince proposal included a similar deficiency.
448254. The RFP also required a minimum 10 - foot mowing strip
4494between the right - of - way and the edge of the shoulder of the road
4510or retaining wall. The Middlesex proposal failed to comply with
4520the mowing strip requirement. Both the Prince proposal and the
4530RFPÓs SPUI c oncept plan exhibits the same deficiency.
453955. The evidence failed to establish that the border width
4549or mowing strip deficiencies warranted rejection of either
4557proposal as non - responsive.
456256. Prince has asserted that the Middlesex Traffic Control
4571Pla n includes a diagram that displays a Ðcross slope breakÑ
4582condition in the vehicle wheel path that would exist during a
4593temporary traffic control situation. Such a condition could
4601present a safety hazard to drivers. The sole diagram upon which
4612the asserti on relies lacks scale and is insufficient to establish
4623that the Middlesex proposal will result in such a condition at
4634any time during the actual construction process.
464157. Prince has suggested that the Middlesex design fails to
4651comply with the RFP requir ements related to accommodation of a
4662future flyover. The RFP required that the proposed interchange
4671Ðaccommodate to the maximum extent possible the future design and
4681construction by others of a new directional flyover rampÑ
4690connecting northbound I - 75/SR 5 0 to westbound US 98/SR 50/Cortez
4702Boulevard Ðso as to maximize the salvaging of the then - existing
4714facilities, in order to reduce future probable costs.Ñ The
4723Middlesex proposal was principally based on the future flyover
4732included in the RFPÓs SPUI Concept Plan, and , accordingly, the
4742Middlesex proposal complies with the RFP.
4748CONCLUSIONS OF LAW
475158. The Division of Administrative Hearings has
4758jurisdiction over the parties to and subject matter of this
4768proceeding. §§ 120.57(1) and 120.57(3), Fl a . Stat . (201 5). 1/
478159. Although the Ðdesign - buildÑ contract at issue in this
4792proceeding is being a warded under the provisions of s ection
4803337.11 , Florida Statutes, and Florida Administrative Code Rule
481114 - 91.007, the pr ocurement is still governed by s ection
4823120.57(3)( f), which provides in relevant part as follows:
4832In a protest to an invitation to bid or
4841request for proposals procurement, no
4846submissions made after the bid or
4852proposal opening which amend or
4857supplement the bid or proposal shall be
4864considered. In a protes t to an
4871invitation to negotiate procurement, no
4876submissions made after the agency
4881announces its intent to award a contract,
4888reject all replies, or withdraw the
4894solicitation which amend or supplement
4899the reply shall be considered. Unless
4905otherwise provided by statute, the burden
4911of proof shall rest with the party
4918protesting the proposed agency action.
4923In a competitive - procurement protest,
4929other than a rejection of all bids,
4936proposals, or replies, the administrative
4941law judge shall conduct a de novo
4948proceed ing to determine whether the
4954agencyÓs proposed action is contrary to
4960the agencyÓs governing statutes, the
4965agencyÓs rules or policies, or the
4971solicitation specifications. The
4974standard of proof for such proceedings
4980shall be whether the proposed agency
4986actio n was clearly erroneous, contrary to
4993competition, arbitrary, or capricious.
4997In any bid - protest proceeding contesting
5004an intended agency action to reject all
5011bids, proposals, or replies, the standard
5017of review by an administrative law judge
5024shall be whethe r the agencyÓs intended
5031action is illegal, arbitrary, dishonest,
5036or fraudulent. (Emphasis added).
504060. The proposed award of the contract to Prince is
5050contrary to the solicitation specifications. The Prince proposal
5058fails to comply with RFP specificatio ns related to I - 75 exit ramp
5072turn lanes, the location of stop bars at exit lanes onto SR 50,
5085and the full concrete pavement of four thr u - lanes in each
5098direction on SR 50 through the I - 75 junction.
510861. The proposed award of the contract by DOT to Prince is
5120clearly erroneous. A decision is clearly erroneous when it is
5130based on substantial error in proceedings. Black Ó s Law
5140Dictionary , ( Rev. 4th Ed. (1968) ) . An agency's decision or
5152intended decision will be found to be "clearly erroneous" if it
5163is without rational support and, consequently, the Administrative
5171Law Judge has a "definite and firm conviction that a mistake has
5183been committed." See U.S. v. U.S. Gypsum Co. 68 S. Ct. 525
5195(1948). The award of a contract to a proposal that fails to meet
5208the requi rements of the RFP is clearly erroneous.
521762. Prince has suggested that such requirements are
5225inapplicable to the Prince PARCLO design, or that the approval by
5236DOT of Prince Ós request to submit the PARCLO released Prince from
5248complying with the cited req uirements of the RFP. The evidence
5259fails to establish that, in allowing Prince to proceed with an
5270alternative design in lieu of the SPUI, DOT exempted Prince from
5281complying with the requirements of the RFP.
528863. Notwithstanding PrinceÓs assertion that t he referenced
5296requirements are inapplicable to its proposal, Prince offered
5304during the hearing to cure the deficiencies after receiving the
5314contract, if required to do so. Section 120.57(3)(f) prohibits
5323consideration of submissions made after the proposal opening
5331which amend or supplement the proposal. Accordingly, PrinceÓs
5339offer to remedy the deficiencies in its proposal by complying
5349with the requirements of the RFP has been disregarded.
535864. The proposed award of the contract by DOT to Prince is
5370contr ary to competition. As to whether the RFP process is
"5381contrary to competition," the phrase is best understood by its
5391plain and obvious meaning -- i.e. , against or in opposition to
5402competition. "The purpose of the competitive bidding process is
5411to secure fa ir competition on equal terms to all bidders by
5423affording an opportunity for an exact comparison of bids." Harry
5433Pepper and Assoc., Inc. v . City of Cape Coral, 352 So. 2d 1190
5447(Fla. 2 d DCA 1977).
545265. While not every deviation from the specifications of an
5462RFP requires disqualification of a bid, a deviation from the
5472specifications is material , "if it gives the bidder a substantial
5482advantage over the other bidders and thereby restricts or stifles
5492competit ion." Tropabest Foods, Inc. v. Dept. of Gen . Ser v s . , 493
5507So. 2d 50 (Fla. 1st DCA 1986); Robinson Elec. Co., Inc. v. Dade
5520C nty. , 417 So. 2d 1032 (Fla. 3d DCA 1982).
553066. The deficiencies in the Prince proposal were not minor
5540irregularities that could be addressed through the evaluative
5548process because th ey precluded an appropriate comparison of
5557proposals. They were material deviations that, through the
5565omission of materials and construction costs related to the
5574deficiencies, provided Prince with an economic advantage over
5582other firms because the adjusted score calculations incorporated
5590each firmÓs Price Proposal.
559467. Finally, the RFP specifically provided that a
5602conditional proposal may found to be non - responsive, and that
5613non - responsive proposals Ðshall not be considered.Ñ The PARCLO
5623ATC design has n ot been approved by the FHWA, and both DOT and
5637Prince concede that the FHWA may not approve the Prince ATC
5648PARCLO design. While the ATC process is apparently intended to
5658reward a creative response from potential bidders, nothing in the
5668RFP suggests that t he ATC process permits DOT to award a contract
5681to a conditional proposal that fails, on its face, to comply with
5693the requirements of the RFP.
5698RECOMMENDATION
5699Based on the foregoing Findings of Fact and Conclusions of
5709Law, it is RECOMMENDED that the Depart ment of Transpo rtation
5720enter a final o rder awarding the contract issued pursuant to RFP
5732E7K24 to the Middlesex Corporation.
5737DONE AND ENTERED this 7th day of December , 2015 , in
5747Tallahassee, Leon County, Florida.
5751S
5752WILLIA M F. QUATTLEBAUM
5756Administrative Law Judge
5759Division of Administrative Hearings
5763The DeSoto Building
57661230 Apalachee Parkway
5769Tallahassee, Florida 32399 - 3060
5774(850) 488 - 9675
5778Fax Filing (850) 921 - 6847
5784www.doah.state.fl.us
5785Filed with the Clerk of the
5791Division of Administrative Hearings
5795this 7th day of December , 2015 .
5802ENDNOTE
58031/ All statutory references are to Florida Statutes (2015).
5812COPIES FURNISHED:
5814C. Denise Johnson, Esquire
5818Department of Transportation
5821Haydon Burns Building, Mail Station 58
5827605 Suwa nnee Street
5831Tallahassee, Florida 32399 - 0458
5836(eServed)
5837Brian A. Newman, Esquire
5841Pennington, P.A.
5843215 South Monroe Street, Second Floor
5849Post Office Box 10095
5853Tallahassee, Florida 32302 - 2095
5858(eServed)
5859Brandice D. Dickson, Esquire
5863Pennington, Moore, Wilki nson,
5867Bell and Dunbar, P.A.
5871215 South Monroe Street, Second Floor
5877Post Office Box 10095
5881Tallahassee, Florida 32302 - 2095
5886(eServed)
5887Karen D. Walker, Esquire
5891Holland and Knight, LLP
5895Suite 600
5897315 South Calhoun Street
5901Tallahassee, Florida 32301
5904(eServed)
5905Mia L. McKown, Esquire
5909Holland and Knight, LLP
5913Post Office Drawer 810
5917Tallahassee, Florida 32302 - 1809
5922(eServed)
5923Tiffany A. Roddenberry, Esquire
5927Holland & Knight, LLP
5931Suite 600
5933315 South Calhoun Street
5937Tallahassee, Florida 32301
5940(eServed)
5941Andrea Sh ulthiess, Clerk of
5946Agency Proceedings
5948Department of Transportation
5951Haydon Burns Building
5954605 Suwannee Street, M ai l S tation 58
5963Tallahassee, Florida 32399 - 0450
5968(eServed)
5969James C. Boxold, Secretary
5973Department of Transportation
5976Haydon Burns Building
5979605 Su wannee Street, M ai l S tation 57
5989Tallahassee, Florida 32399 - 0450
5994(eServed)
5995Tom Thomas, General Counsel
5999Department of Transportation
6002Haydon Burns Building
6005605 Suwannee Street, M ai l S tation 58
6014Tallahassee, Florida 32399 - 0450
6019(eServed)
6020NOTICE OF RIGHT TO S UBMIT EXCEPTIONS
6027All parties have the right to submit written exceptions within
60371 0 days from the date of this Recommended Order. Any exceptions
6049to this Recommended Order should be filed with the agency that
6060will issue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 12/07/2015
- Proceedings: Recommended Order (hearing held September 28 through October 1, 2015). CASE CLOSED.
- PDF:
- Date: 12/07/2015
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 11/06/2015
- Proceedings: Prince Contracting, LLC's Notice of Filing Proposed Recommended Order filed.
- PDF:
- Date: 11/06/2015
- Proceedings: Middlesex's Proposed Findings of Fact and Conclusions of Law filed.
- Date: 10/27/2015
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- PDF:
- Date: 10/02/2015
- Proceedings: Letter to Judge Quattlebaum from Brian Newman enclosing thumb drive filed (proposed exhibits not available for viewing).
- Date: 09/28/2015
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 09/21/2015
- Proceedings: Middlesex's Notice of Filing Designations of Thomas Creasey, Ph.D. Deposition Taken July 24, 2015 filed.
- PDF:
- Date: 09/17/2015
- Proceedings: Middlesex's Unopposed Motion for Leave to File First Amended Petition filed.
- PDF:
- Date: 08/03/2015
- Proceedings: Order Granting Continuance and Re-scheduling Hearing (hearing set for September 28 through October 2, 2015; 9:30 a.m.; Tallahassee, FL).
- PDF:
- Date: 08/03/2015
- Proceedings: Notice of Taking Telephonic Depositions (Ali Gord and Henri Belrose) filed.
- PDF:
- Date: 07/29/2015
- Proceedings: Middlesex's Notice of Taking Deposition of Daniel Lauricello, P.E. filed.
- Date: 07/29/2015
- Proceedings: CASE STATUS: Status Conference Held.
- PDF:
- Date: 07/29/2015
- Proceedings: Prince Contracting, LLC's Notice of Filing Stipulation Regarding Expert Testimony filed.
- PDF:
- Date: 07/27/2015
- Proceedings: Prince Contracting, LLC's Second Supplemental Response to The Middlesex Corporation's First Request for Production of Documents filed.
- PDF:
- Date: 07/24/2015
- Proceedings: Prince Contracting, LLC's Notice of Service of Answers and Objections to Middlesex Corporation's Third Set of Interrogatories filed.
- PDF:
- Date: 07/24/2015
- Proceedings: Prince's Responses and Objections to Middlesex's Fourth Request for Production of Documents filed.
- PDF:
- Date: 07/23/2015
- Proceedings: Respondent's Response to Petitioner's Fourth Request for Production filed.
- PDF:
- Date: 07/23/2015
- Proceedings: Respondent's Response to Petitioner's Third Request for Production filed.
- PDF:
- Date: 07/23/2015
- Proceedings: Respondent, Department of Transportation's, Response to Middlesex's First Request for Admission to the Department filed.
- PDF:
- Date: 07/20/2015
- Proceedings: The Middlesex Corporation's Supplemental Response to Prince Contracting, LLC's Second Request for Production of Documents to the Middlesex Corporation filed.
- PDF:
- Date: 07/17/2015
- Proceedings: Middlesex's Notice of Taking Deposition of D. Scot Leftwich filed.
- PDF:
- Date: 07/16/2015
- Proceedings: Prince Contracting, LLC's Responses and Objections to Middlesex Corporation's Third Request for Production of Documents to Prince Contracting, LLC., filed.
- PDF:
- Date: 07/16/2015
- Proceedings: Middlesex's Fourth Request for Production to the Department filed.
- PDF:
- Date: 07/16/2015
- Proceedings: Middlesex's First Requests for Admission to the Department filed.
- PDF:
- Date: 07/16/2015
- Proceedings: Middlesex's Notice of Service of Third Set of Interrogatories to Prince filed.
- PDF:
- Date: 07/16/2015
- Proceedings: Middlesex's Third Request for Production to the Department filed.
- PDF:
- Date: 07/15/2015
- Proceedings: Prince Contracting, LLC's Responses and Objections to the Middlesex Corporation's Second Request for Production of Documents to Prince Contracting, LLC filed.
- PDF:
- Date: 07/15/2015
- Proceedings: Notice of Taking Depositions (James Wills, Henri Belrose, and Al Aponas) filed.
- PDF:
- Date: 07/15/2015
- Proceedings: Notice of Taking Deposition (Corporate Representative of Middlesex) filed.
- PDF:
- Date: 07/14/2015
- Proceedings: Middlesex's Amended Notice of Taking Depositions of Jack Calandros and Walfry Pevida filed.
- PDF:
- Date: 07/14/2015
- Proceedings: Middlesex's Notice of Taking Depositions (of Jack Calandros and Walfry Pevida) filed.
- PDF:
- Date: 07/14/2015
- Proceedings: Middlesex's Notice of Taking Deposition of Prince Contracting, LLC's Agency Representative filed.
- PDF:
- Date: 07/14/2015
- Proceedings: Middlesex's Corrected Notice of Taking Deposition of Waddah Farah, P.E. filed.
- PDF:
- Date: 07/13/2015
- Proceedings: Notice of Taking Depositions (of Sandra Gonzalez and Amy Neidringhaus) filed.
- PDF:
- Date: 07/13/2015
- Proceedings: Middlesex's Notice of Taking Deposition of Department of Transportation's Agency Representative filed.
- PDF:
- Date: 07/09/2015
- Proceedings: Prince Contracting, LLC's Supplemental Response to the Middlesex Corporation's First Request for Production of Documents to Prince Contracting, LLC filed.
- PDF:
- Date: 07/08/2015
- Proceedings: The Middlesex Corporation's Objection to Intervenor Prince's Notice of Production from Non-party filed.
- PDF:
- Date: 07/08/2015
- Proceedings: Notice of Taking Depositions (of Richard Moss, Terence Jennings, Tom Lay and Rochelle Garrett) filed.
- PDF:
- Date: 07/07/2015
- Proceedings: Prince Contracting, LLC's Notice of Service of Answers and Objections to MIddllesex Corporation's Second Set of Interrogatories filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Departments Response to Middlesexs Second Request for Production filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Departments Notice of Service of Answers to Middlesexs Second Set of Interrogatories filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Middlesex's Response to Prince's Second Request for Production filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Middlesex's Response to Prince's Second Requests for Admission filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Middlesex's Notice of Service of Answers to Prince's Second Set of Interrogatories filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Prince Contracting, LLC's Notice of Service of Supplemental Production to The Middlesex Corporation's First Request for Production of Documents filed.
- PDF:
- Date: 07/06/2015
- Proceedings: Intervenor, Prince Contracting, LLC's Objections to Petitioner's Notice of Production from Non-party Dated June 26, 2015 filed.
- PDF:
- Date: 06/30/2015
- Proceedings: Middlesex's Second Request for Production to the Department filed.
- PDF:
- Date: 06/30/2015
- Proceedings: Middlesex's Notice of Service of Second Set of Interrogatories to the Department filed.
- PDF:
- Date: 06/30/2015
- Proceedings: Middlesex's Notice of Service of Second Set of Interrogatories to Prince filed.
- PDF:
- Date: 06/26/2015
- Proceedings: Intervenor Prince Contracting, LLC's Second Request for Production of Documents to Petitioner filed.
- PDF:
- Date: 06/26/2015
- Proceedings: Intervenor Prince Contracting, LLC's Second Request for Admissions to Petitioner filed.
- PDF:
- Date: 06/26/2015
- Proceedings: Intervenor, Prince Contracting, LLC's Notice of Service of its Second Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Notice of Serving Department's Answers to Petitioners First Set of Interrogatories filed.
- PDF:
- Date: 06/24/2015
- Proceedings: Middlesex's Notice of Service of Answers to the Department's First Interrogatories filed.
- PDF:
- Date: 06/23/2015
- Proceedings: Respondent's Response to Petitioner's First Request for Production filed.
- PDF:
- Date: 06/23/2015
- Proceedings: Middlesex's Response to Prince's First Requests for Admission filed.
- PDF:
- Date: 06/23/2015
- Proceedings: Middlesex's Response to Prince's First Request for Production filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Middlesex's Notice of Service of Answers to Prince's First Interrogatories filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Prince Contracting, LLC's Responses and Objections to The Middlesex Corporation's First Request for Production of Documents to Prince Contracting, LLC filed.
- PDF:
- Date: 06/22/2015
- Proceedings: Prince Contracting, LLC's Notice of Service of Answers and Objections to The Middlesex Corporation's First Set of Interrogatories filed.
- PDF:
- Date: 06/16/2015
- Proceedings: Notice of Serving Department's First Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Intervenor Prince Contracting, LLC's First Request for Admissions to Petitioner filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Intervenor Prince Contracting, LLC's First Request for Prouction of Documents to Petitioner filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Intervenor, Prince Contracting, LLC's Notice of Service of Its First Set of Interrogatories to Petitioner filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Middlesex's Notice of Service of First Set of Interrogatories to the Department filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Middlesex's Notice of Service of First Set of Interrogatories to Prince filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Middlesex's First Request for Production to the Department filed.
- PDF:
- Date: 06/12/2015
- Proceedings: Order on Joint Motion for Modification of Pre-Hearing Instructions.
- PDF:
- Date: 06/11/2015
- Proceedings: Joint Motion for Modification of Order of Pre-hearing Instructions filed.
- PDF:
- Date: 06/10/2015
- Proceedings: Notice of Hearing (hearing set for August 5 through 7, 2015; 9:30 a.m.; Tallahassee, FL).
Case Information
- Judge:
- WILLIAM F. QUATTLEBAUM
- Date Filed:
- 05/28/2015
- Date Assignment:
- 05/29/2015
- Last Docket Entry:
- 01/19/2016
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Brandice D. Dickson, Esquire
Pennington, Moore, Wilkinson,
215 South Monroe Street, Second Floor
Post Office Box 10095
Tallahassee, FL 323022095
(850) 222-3533 -
C. Denise Johnson, Esquire
Department of Transportation
Haydon Burns Building, Mail Station 58
605 Suwannee Street
Tallahassee, FL 323990458
(850) 414-5265 -
Mia L. McKown, Esquire
Holland and Knight, LLP
Post Office Drawer 810
Tallahassee, FL 323021809
(850) 224-7000 -
Brian A. Newman, Esquire
Pennington, P.A.
215 South Monroe Street, Second Floor (32301)
Post Office Box 10095
Tallahassee, FL 323022095
(850) 222-3533 -
Tiffany A Roddenberry
Tallahassee, FL 32301
(850) 224-7000 -
Cynthia S. Tunnicliff, Esquire
Pennington, P.A.
215 South Monroe Street, Second Floor (32301)
Post Office Box 10095
Tallahassee, FL 32302
(850) 222-3533 -
Karen D. Walker, Esquire
Holland and Knight, LLP
Suite 600
315 South Calhoun Street
Tallahassee, FL 32301
(850) 224-7000 -
Tiffany A Roddenberry, Esquire
Holland & Knight LLP
315 South Calhoun Street, Suite 600
Tallahassee, FL 32301
(850) 224-7000 -
Brandice Davidson Dickson, Esquire
Address of Record -
Brian A Newman, Esquire
Address of Record -
Mia L McKown, Esquire
Address of Record -
Karen D Walker, Esquire
Address of Record -
C. Denise Johnson, Assistant General Counsel
Address of Record -
Tiffany A. Roddenberry, Esquire
Address of Record